DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EG94-86-000, et al.]

CMS Operating S.A., et al.; Electric Rate and Corporate

Regulation Filings

July 28, 1994.

Take notice that the following filings have been made with the

Commission:

1. CMS Operating S.A.

[Docket No. EG94-86-000]

On July 21, 1994, CMS Operating S.A., Av. Roque Saenz Pena 1116,

piso 9 (1035), Buenos Aires, Argentina, filed with the Federal Energy

Regulatory Commission an application for determination of exempt

wholesale generator status pursuant to Part 365 of the Commission's

regulations.

CMS Operating S.A. is a subsidiary of CMS Generation S.A., which is

a subsidiary of CMS Enterprises Company, which in turn is a wholly-

owned subsidiary of CMS Energy Corporation. Through affiliates, CMS

Operating S.A. was pre-awarded on June 29, 1994, the right to operate

the Lujan de Cuyo and Cruz de Piedra locations of Centrales Termicas

Mendoza S.A., which have a nominal capacity exceeding 400 MW. The

Facility is located near the City of Mendoza in Argentina.

Comment date: August 12, 1994, in accordance with Standard

Paragraph E at the end of this notice. The Commission will limit its

consideration of comments to those that concern the adequacy or

accuracy of the application.

2. The City of Cleveland, Ohio v. The Cleveland Electric

Illuminating Company

[Docket No. EL94-80-000]

Take notice that on July 20, 1994, the City of Cleveland, Ohio

tendered for filing a complaint against the Cleveland Electric

Illuminating Company for breaches of the 1975 Interconnection Agreement

between the parties.

Comment date: August 29, 1994, in accordance with Standard

Paragraph E at the end of this notice.

3. Southern California Edison Company

[Docket No. ER88-83-011]

Take notice that on July 21, 1994, Southern California Edison

Company tendered for filing its compliance filing in the above-

referenced docket.

Comment date: August 12, 1994, in accordance with Standard

Paragraph E at the end of this notice.

4. Southern California Edison Company

[Docket No. ER91-201-004]

Take notice that on July 21, 1994, Southern California Edison

Company tendered for filing its compliance filing in the above-

referenced docket.

Comment date: August 12, 1994, in accordance with Standard

Paragraph E at the end of this notice.

5. Wisconsin Power and Light Company

[Docket No. ER94-158-000]

Take notice that on July 22, 1994, Wisconsin Power and Light

Company (WP&L) tendered for filing a signed Service Agreement under

WP&L's Bulk Power Tariff between itself and Consolidated Water Power

Company. WP&L respectfully requests a waiver of the Commission's notice

requirements, and an effective date of May 15, 1994.

Comment date: August 12, 1994, in accordance with Standard

Paragraph E at the end of this notice.

6. Northeast Empire L.P. #2

[Docket No. ER94-1448-000]

Take notice that on July 14, 1994, Northeast Empire L.P. #2

tendered for filing an amendment to its July 6, 1994, filing in the

above-referenced docket.

Comment date: August 12, 1994, in accordance with Standard

Paragraph E at the end of this notice.

7. San Diego Gas & Electric Company

[Docket No. ER94-1455-000]

Take notice that on July 15, 1994, San Diego Gas & Electric Company

(SDG&E) tendered for filing an Interchange Agreement (Agreement)

between SDG&E and Eclipse Energy, Inc. (Eclipse).

SDG&E requests that the Commission allow the Agreement to become

effective on the 15th of September, 1994, or at the earliest possible

date.

Copies of this filing were served upon the Public Utilities

Commission of the State of California and Eclipse.

Comment date: August 12, 1994, in accordance with Standard

Paragraph E at the end of this notice.

8. Pepperell Power Associates Limited Partnership

[Docket Nos. AC94-214-000 ER94-1474-000]

Take notice that on July 15, 1994, Pepperell Power Associates

Limited Partnership tendered for filing a notice of termination of its

Power Sale Agreement with the Commonwealth Electric Company and a

request for waiver of the requirement to file a Form 1 for the calendar

years 1993 and 1994.

Comment date: August 12, 1994, in accordance with Standard

Paragraph E at the end of this notice.

9. Cal Ban Corp.

[Docket Nos. QF83-333-002 and QF83-333-003]

On July 25, 1994, Cal Ban Corp. tendered for filing an amendment to

its filing in this docket.

The amendment pertains to the technical aspects of the facility. No

determination has been made that the submittal constitutes a complete

filing.

Comment date: August 17, 1994, in accordance with Standard

Paragraph E at the end of this notice.

Standard Paragraphs

E. Any person desiring to be heard or to protest said filing should

file a motion to intervene or protest with the Federal Energy

Regulatory Commission, 825 North Capitol Street, N.E., Washington, D.C.

20426, in accordance with Rules 211 and 214 of the Commission's Rules

of Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such

motions or protests should be filed on or before the comment date.

Protests will be considered by the Commission in determining the

appropriate action to be taken, but will not serve to make protestants

parties to the proceeding. Any person wishing to become a party must

file a motion to intervene. Copies of this filing are on file with the

Commission and are available for public inspection.

Linwood A. Watson, Jr.,

Acting Secretary.

[FR Doc. 94-18977 Filed 8-3-94; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.