DEPARTMENT OF ENERGY
Energy Information Administration
Forms; Availability, etc.: Coordinated Regional Bulk Power Supply
Program Report
AGENCY: Energy Information Administration (EIA), DOE.
ACTION: Solicitation of comments on proposed revisions to Form OE-411,
``Coordinated Regional Bulk Power Supply Program Report,'' and its
filing frequency.
-----------------------------------------------------------------------
SUMMARY: EIA, as part of its continuing effort to reduce paperwork and
respondent burden (required by the Paperwork Reduction Act of 1980,
Public Law No. 96-511, 44 U.S.C. 3501 et seq.), conducts a presurvey
consultation program to provide the general public and other Federal
agencies with an opportunity to comment on proposed and/or continuing
reporting forms. This program helps to ensure that requested data can
be provided in the desired format, reporting burden is minimized,
reporting forms are clearly understood, and the impact of data
collection requirements on respondents can be properly assessed.
Currently, EIA is soliciting comments concerning proposed revisions to
the Form OE-411, ``Coordinated Regional Bulk Power Supply Program
Report'' and its filing cycle.
Any changes to Form OE-411, determined to be necessary, based on
evaluation of comments received in response to this notice will be
reflected in and apply to the data submission scheduled for April 1,
1995.
DATES: Written comments must be submitted on or before July 15, 1994.
If you anticipate that you will submit comments, but cannot do so
within the period of time allowed by this notice, please advise the
contact listed below. An additional 30 days may be allowed.
ADDRESSES: Send comments to Dennis K. Taillie, Director, Office of
Emergency Planning, 1000 Independence Avenue SW., Washington, DC 20585
(Phone number (202) 586-3271, FAX (202) 586-1737).
FOR FURTHER INFORMATION OR TO OBTAIN COPIES OF THE EXISTING FORM AND
INSTRUCTIONS: Requests for additional information or copies of the form
and instructions should be directed to Mr. Taillie at the address
listed above.
SUPPLEMENTARY INFORMATION:
I. Background
II. Current Actions
III. Request for comments
I. Background
Among the documents currently used to collect U.S. electric power
system data is Form OE-411 (Coordinated Regional Bulk Power Supply
Program Report). Formerly, authority for the Form OE-411 data
collection was delegated to the Office of Emergency Planning and
Operations (OE) within the Department of Energy. The OE organization no
longer exists, but its functions relevant to the Form are now in the
Office of Emergency Planning, Assistant Secretary for Policy, Planning,
and Program Evaluation; and the Office of Emergency Management,
Director of Nonproliferation and National Security.
EIA also has functions relevant to the Form. In order to fulfill
its responsibilities under the Federal Energy Administration Act of
1974 (Pub. L. No. 93-275), and the Department of Energy Organization
Act (Pub. L. No. 95-91), EIA is obliged to carry out a central,
comprehensive, and unified energy data and information program. This
program will collect, evaluate, assemble, analyze, and disseminate data
and information related to energy resource reserves, production, demand
and technology, and related economic and statistical information
relevant to the adequacy of energy resources to meet demands in the
near and longer term future for the Nation's economic and social needs.
The Form annually collects data needed to assess the adequacy and
reliability of U.S. bulk power supply for a 10-year advance period.
This assessment is necessary for DOE to fulfill the requirements of
section 202(a) of the Federal Power Act, as amended.
Supplemented by additional reports published by the North American
Electric Reliability Council (NERC), EIA and others, the data in the
Form enable DOE to perform its assigned tasks, which include:
Assessment of the adequacy of the U.S. electric power
supply;
Assessment of the vulnerability of the U.S. electric
power supply to disruptions from all causes, and evaluation of the
risks of such disruptions; and
Energy-related support activities designated by the
Federal Response Plan (the Robert T. Stafford Disaster Relief and
Emergency Assistance Act, Public Law 93-228, as amended).
The supplemental additional reports noted above include NERC's 10
year forward reliability assessment and its yearly pre-season and post-
season summer and winter operations assessments.
The Form is filed with the DOE annually on April 1 by each of the
Regional Electric Reliability Councils of NERC in the United States.
There are nine Councils in the contiguous U.S. and one in Alaska. No
Council has been established by the electric utilities in Hawaii. Each
Council files Form OE-411 with DOE and provides copies to the Federal
Energy Regulatory Commission and to the Public Service Commission of
each State that is wholly or partly within the Council's boundaries.
The DOE makes the OE-411 reports available to the public for inspection
and copying in its Office of Freedom of Information Reading Room at its
Washington, DC, headquarters, 1000 Independence Avenue, SW.,
Washington, DC 20585.
The Form collects numerical and descriptive information concerning
regional electric power supply systems. The numerical information
consists of historic data and data projected for a 10-year advance
period. The descriptive data consist of each Council's assessment of
the projected reliability of the bulk power supply in its region over
the next five years, and material concerning planning and operating
practices of the Council.
Form OE-411 originated as ``Appendix A'' of Order 383-2, issued by
the then Federal Power Commission on April 10, 1970. Since then, the
Form has been incrementally revised from time-to-time and transferred
to the jurisdiction of several groups within DOE, being variously
designated as ERA-411, EP-411, IE-411 and currently OE-411. The title
``Coordinated Regional Bulk Power Supply Program Report'' has not been
changed, as it reflects the continuing focus and purpose of the
document.
The concept of regional electric power supply, coordinated for the
purposes of reliability and adequacy on a regional scale by electric
utilities working in the cooperative setting provided by the Regional
Councils, was developed by the industry and the Federal Power
Commission in the aftermath of the November 9, 1965, Northeast
Blackout. That event made clear the need for neighboring interconnected
electric utilities to coordinate their planning and operation in the
interests of electric power supply reliability. Accordingly, the
electric power industry, with the assistance and encouragement of the
Federal Power Commission, organized Regional Electric Reliability
Councils to improve inter-utility coordination of system planning and
operation. These Councils provide an institutional mechanism for the
activities needed to assure region-wide planning and operation of power
system facilities, establishment of appropriate standards for the
improvement of interconnected system operation and response to
contingencies, and other relevant matters.
Form OE-411 provides a mechanism for recording in a single compact
volume the basic data and practices resulting from regionally
coordinated efforts by electric utilities to assure adequate,
continuous and reliable electric power supply. The Form annually
provides, in convenient, form basic information needed by the Federal
government, State agencies, electric utilities and the public to assess
the reliability and adequacy of electric bulk power supply as projected
for a decade ahead.
II. Current Actions
Since the predecessor of Form OE-411 was initiated in 1970,
significant changes have occurred in the technology of electric power
generation, transmission, distribution and use which have been
accompanied by reduced growth of electric demand. Coupled with changes
in the national economy, the structure of the electric power industry,
new Federal energy legislation and changes in Federal and State
regulatory practices, it is appropriate to reconsider Form OE-411 at
this time with respect to: Frequency of reporting, scope and content,
duplicate reporting of data, and administrative arrangements.
Administrative Arrangements
The Survey Management Division, Office of Coal, Nuclear, Electric
and Alternate Fuels of the EIA is assuming responsibility for
administration of the Form. EIA will be responsible for preparing the
blank Form, sending it to the Reliability Councils (in hard copy,
diskette or by other means), receiving the completed Form from each
Council, entering the data into an electronic database readily
accessible to government agencies and the public, and providing a hard
copy of each Council's Form to the DOE Freedom of Information Reading
Room for inspection and copying by the public.
EIA also will be responsible for making changes to the Form, if
revisions are found to be needed, after consultation with DOE's Office
of Emergency Planning and Office of Emergency Management, the North
American Electric Reliability Council (acting for the Regional
Councils) and other interested parties. If this change in
administrative responsibility is implemented, the designation of the
Form will become EIA-411. Response to Form OE-411 and its predecessors
was voluntary. It is now proposed that response to Form EIA-411 will be
mandatory.
Frequency of Reporting
The Department of Energy is considering reducing the filing
frequency for the new Form (EIA-411) to biennially instead of annually.
Accordingly, the 1995 filing would be required, but the next filing
would not be due until 1997. When the Form's predecessor was initiated
in 1970 the demand for electric power was exhibiting a high rate of
annual increase and the planning and construction of electric system
facilities was correspondingly rapid. Annual reporting was appropriate
at that time so that assessment of reliability could be based on the
latest data, which changed rapidly. The present annual growth rate of
electricity demand is approximately half of what it was in the late
1960's and early 1970's. It appears probable that the growth rate will
not increase greatly in the foreseeable future. The pace of facilities
construction has slowed correspondingly and it seems appropriate to
reduce the frequency of data reporting.
Biennial preparation of Form EIA-411 will reduce the reporting
burden on the utility industry (which provides the data to the
Councils) and on the Councils (which aggregate the data, prepare the
response and make distribution to the Department of Energy, the Federal
Energy Regulatory Commission and State Public Service Commissions).
Since year-to-year changes are smaller than previously, the validity of
adequacy assessments based on the biennial reports is not likely to be
affected significantly.
Elimination of Duplication
Some data on utility-owned generating units are currently reported
by utilities twice: To EIA on Form EIA-860 (Annual Electric Generator
Report) and also on Form OE-411. Currently, data on the mode of
transportation of fuel to these units are reported on Form OE-411 but
not on Form EIA-860; however, EIA intends to modify Form EIA-860 to
include reporting of the fuel transportation data. Also, electric
utility, unauthorized planned new generators are reported on Form OE-
411 but not on Form EIA-860. EIA will modify Form EIA-860 to include
electric utility, unauthorized planned new generators. Once this is
done, Form EIA-860 will include all of the utility-owned generating
unit data required, and the duplicative work of the Councils in
preparing a separate list of utility-owned generating unit data
(including mode of fuel transportation) for Form EIA-411 will become
unnecessary.
However, complete and accurate generating unit data will be needed
in Form EIA-411 to make it a ``stand-alone'' document. Therefore, EIA
will furnish to each Council the data (reported on Form EIA-860)
concerning the utility-owned units in that Council, to be incorporated
by the Council in its response to Form EIA-411. The procedure to do
this will be developed jointly by EIA and the Councils to assure that
the data reported in Form EIA-411 are complete, accurate and correctly
reflect the generating capacity owned by utilities and non-utility
generators (NUGs) within the Council boundaries. Data concerning non-
utility generating capacity will be obtained by utilities as is done
currently, will be reported by the utilities to the Councils and will
be reported by each Council in its response to Form EIA-411.
Content of Proposed Form EIA-411
The following discussion lists items being considered for inclusion
in proposed Form EIA-411. A brief justification for each proposed
change from Form OE-411 is also provided.
Item No.
1. Projected energy and peak demand for ten years and actual data
for the previous year.
No change is proposed for this item.
2A. Existing generating capacity.
No change is proposed for the content of this item. The method by
which the data are to be obtained is discussed above under the heading
``Elimination of Duplication.''
2B. Projected Generating Capacity Installations, Changes and
Removals.
No change is proposed for this item. The method by which the data
are to be obtained is discussed above under the heading ``Elimination
of Duplication.''
2C. Projected capacity purchases and sales.
It is proposed to add to this item, for the peak hour of each month
of the preceding year, the actual purchases and sales of capacity
resulting from transactions with sources external to the Council area.
Justification: For some Councils, purchased capacity is a
significant portion of the total available and significantly affects
the adequacy of regional power supply. No means now exist for tracking
this information in Form OE-411.
3A. Projected capacity and demand for ten years.
No change is proposed for this item.
3B. Five-year assessment of adequacy by the Council.
No change is proposed for this item.
3C. Regional generating capacity unavailability.
Only data on utility-owned generating capacity are currently
reported. It is proposed that unavailability data for non-utility (NUG)
generator capacity be added to this item to the extent that it is made
available by NUG entities.
Justification: As NUG capacity becomes a larger portion of total
installed capacity in a Council area, it becomes more important to be
able to assess its reliability.
New Item 3D. Regional Demand Projections.
Discuss the forecasting method and basic assumptions employed by
the Council in reaching aggregate demand and energy projections,
tabulated in Item 3A, for normal weather. Also discuss how the Council
plans to meet contingencies caused by extreme weather.
Justification: The discussion will provide a basis, not currently
available, for understanding the forecasts.
4A. Bulk Power Transmission System Maps.
No change is proposed for this item.
4B. Projected Bulk Power Transmission Line Additions.
No change is projected for this item.
5A. Near-term Transmission Adequacy.
No change is projected for this item.
5B. Future Critical Bulk Power Transmission Facilities That Will
Not Be In Service When Required.
It is proposed to replace this item by a new item 5B requesting:
(1) Summary data on actual inter-Council purchase and sale
transactions which took place during the seasonal (summer and winter)
peak load periods of the preceding year and (2) a discussion of the
extent to which the magnitude of these transactions approached the
transfer capacity of the inter-Council transmission facilities under
conditions then existing.
Justification: Industry reports claim that some U.S. transmission
facilities are approaching their capacity transfer limits but do not
support these claims with quantitative information. The data requested
will provide an understanding of the ability of transmission facilities
to transfer the capacity purchases and sales reported in item 3A among
Councils.
5C. System Evaluation Criteria.
It is proposed to enlarge this item to include discussion of the
effects of non-utility generating sources and increased access by
independent power producers to transmission facilities as they
specifically relate to reliability of supply in the Council's area.
Justification: Increasing non-utility generation and the issues
associated with integrating that generation into the utility network
may have effects on system reliability that are not thoroughly explored
elsewhere.
6A. Coordination of Operations.
No change is proposed for this item.
6B. Load preservation program.
It is proposed to add to this item requests for: (1) description of
the voltage reduction procedures employed by the utilities in the
Council area, their effectiveness in reducing peak demands and the
effects on customer equipment; and (2) discussion of conditions and
practices related to reduction of peak demand under control of or at
the request of the system operator. These practices are usually
described by such terms as ``direct load control,'' ``interruptible
load,'' or ``load management.'' The terminology used should be defined.
Justification: Load preservation practices and procedures differ
among Councils. Further information is necessary to understand their
potential for preserving load.
7. Additional Information.
No change is proposed for this item.
III. Request for Comments
Prospective respondents and other interested parties are requested
to comment on the proposed revisions discussed above and to propose
such other modifications as they deem useful. The following general
questions are provided to assist in the preparation of responses:
For the potential respondent and user:
A. Are current instructions and definitions in Form OE-411 clear
and sufficient? If not, what changes do you suggest?
B. Can the information requested be submitted consistent with
the existing definitions? (Note: It is intended to adopt, if
possible, the definitions in the ``Glossary of Terms For NERC
Publications'' to be published by the North American Electric
Reliability Council on June 9, 1994.)
C. Can the information requested be submitted within the
response time specified in the instructions?
D. For Form OE-411 as currently constituted, public reporting
burden is estimated to average 13 hours per response for the
utilities that provide the basic information and 1000 hours for each
Reliability Council respondent. How much time, including time for
reviewing instructions, searching existing data sources, gathering
and maintaining the data needed, and completing and reviewing the
collection of information, do you estimate would be required to
complete Form EIA-411 if it should be promulgated as proposed in
this Notice?
E. What specific changes do you suggest?
F. If you know of any Federal, State or local governmental
agency that collects identical data in the same single volume
format, specify the agency and a reference citation.
G. For what purposes would you use the EIA-411 report? Please be
specific.
H. What are the deficiencies and strengths of any alternate
source of numerical and descriptive information that you use?
EIA also is interested in receiving comments regarding the need for
the information provided in Form OE-411 (existing) or Form EIA-411
(proposed).
Comments will become a matter of public record.
The Office Of Emergency Planning and EIA will review and evaluate
all comments received as a result of this Notice in the context of best
serving the interests of the public, the electric utility industry,
State governments and the Federal government. A statement will be
prepared integrating the views expressed above with the comments
received in response to this notice. If appropriate after review by
these offices, the Office of Management and Budget (OMB) will be
requested to authorize use of Form EIA-411 for the period 1995-1997.
Statutory Authorities: Sec. 2(a) of the Paperwork Reduction Act
of 1980, (Public Law No. 96-511), which amended Chapter 35 of Title
44 United States Code. [See 44 U.S.C. 3506(a) and (c)(1)].
Issued in Washington, DC June 9, 1994.
Yvonne M. Bishop,
Director, Office of Statistical Standards, Energy Information
Administration.
[FR Doc. 94-14554 Filed 6-14-94; 8:45 am]