Approval and Promulgation of Implementation Plans; Indiana

AGENCY: Environmental Protection Agency.

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: The United States Environmental Protection Agency (USEPA) is

taking action to approve a requested revision to the Indiana State

Implementation Plan (SIP) for ozone. USEPA's action is based upon a

revision request which was submitted by the State to satisfy the

requirements of the Clean Air Act (Act), which requires certain ozone

nonattainment areas to require specified gasoline dispensing facilities

to install and operate Stage II vapor recovery equipment. The subject

areas established in the SIP revision are the Indiana portion of the

Chicago ozone nonattainment area (Lake and Porter Counties) and the

Indiana portion of the Louisville, Kentucky ozone nonattainment area

(Clark and Floyd Counties). USEPA's action is being taken without prior

proposal.

DATES: This final rule will be effective June 27, 1994, unless notice

is received by May 31, 1994, that someone wishes to submit adverse

comments. If the effective date is delayed, timely notice will be

published in the Federal Register.

ADDRESSES: Copies of the requested SIP revision, technical support

documents and public comments received are available at the following

address: United States Environmental Protection Agency, Region 5, Air

and Radiation Division, Regulation Development Branch, 77 West Jackson

Boulevard, Chicago, Illinois 60604.

This SIP revision is also available for inspection at the Office of

Air and Radiation (OAR) Docket and Administration Center (Air Docket

6102), room M1500, U.S. Environmental Protection Agency, 401 M Street

SW., Washington, DC 20460, (202) 260-7548.

Comments on this rulemaking should be addressed to: J. Elmer

Bortzer, Chief, Regulation Development Section, Regulation Development

Branch (5AR-18J), United States Environmental Protection Agency, Region

5, 77 West Jackson Boulevard, Chicago, Illinois 60604.

FOR FURTHER INFORMATION CONTACT:

Francisco J. Acevedo, Environmental Engineer, Regulation Development

Section, Regulation Development Branch (5AR-18J), United States

Environmental Protection Agency, Region 5, 77 West Jackson Boulevard,

Chicago, Illinois 60604, (312) 886-6061. Anyone wishing to come to

Region 5 offices should contact Francisco J. Acevedo first and

reference file IN29-1-5822.

SUPPLEMENTARY INFORMATION:

I. Background/Summary of State Submittal

On February 25, 1994, the Indiana Department of Environmental

Management (IDEM) submitted to USEPA Stage II Vapor Recovery Rules:

Amendments to 326 IAC 8-1-0.5 and 326 IAC 8-4-6 as requested revisions

to the Indiana SIP. The rules were adopted by the Indiana Air Pollution

Control Board (IAPCB) on July 21, 1993, and were published in the

Indiana Register on December 1, 1993. The State submitted these rules

to satisfy the Stage II vapor recovery requirements of section

182(b)(3) of the Act. The SIP revision submitted by the State of

Indiana sets out procedures for the establishment of a Stage II Vapor

Recovery Program in the ozone nonattainment counties of Lake, Porter,

Clark, and Floyd. The information presented below summaries the

requested SIP revision and USEPA's action on it. A more detailed

analysis of the State's submittal is contained in USEPA's technical

support documents dated March 23, 1993, and March 31, 1994, which are

available from the Region 5 office listed above.

Indiana's regulations specify that Stage II vapor recovery systems

are required at gasoline dispensing facilities that dispense more than

10,000 gallons per month, and independent small business marketers of

gasoline (ISBMG) that dispense an average monthly volume of more than

50,000 gallons per month. Private fueling facilities such as government

and company fleet fueling facilities, as well as retailers, are subject

to the Stage II requirements. The regulations specify the use of

California Air Resource Board (CARB) certified Stage II systems, which

have been demonstrated to achieve at least 95 percent control of

Volatile Organic Compound (VOC) emissions during the refueling of motor

vehicles. The rules also mandate that the proper installation and

operation of such systems be achieved by requiring the installed

systems to be tested for proper installation and requiring the State to

perform all necessary enforcement of the rules.

The rules mandate the Stage II vapor recovery systems for nonexempt

facilities be implemented pursuant to the following phase-in schedule:

(1) Facilities that commenced construction after November 15, 1990,

must comply six months after promulgation of the rules by the State;

(2) facilities that commenced construction before November 15, 1990,

and dispense an average monthly volume of more than 100,000 gallons of

motor fuel per month, must comply by one year after promulgation of the

rules by the State; and (3) all other facilities must comply two years

after promulgation of the rules by the State.

II. Review Criteria

The USEPA reviewed the submittal against the requirements of

section 182(b)(3) of the Act, as interpreted in the General Preamble

for the Implementation of Title I of the Clean Air Act Amendments of

1990 (57 FR 13498, 13513 (April 16, 1992)), and two USEPA documents

entitled Technical Guidance-Stage II Vapor Recovery Systems for Control

of Vehicle Refueling Emissions at Gasoline Dispensing Facilities

(Technical Guidance) and the Enforcement Guidance for Stage II Vehicle

Refueling Control Programs (Enforcement Guidance). Specifically, the

following seven general criteria need to be met for a Stage II vapor

recovery regulation to be approvable by USEPA:

(1) Installation of Stage II Controls and Determination of Regulated

Facilities

Facilities that dispense more than 10,000 gallons per month must

install and operate Stage II controls. For gasoline dispensing

facilities that are owned and operated by an ISBMG, the State may

establish a cut-point as high as 50,000 gallons per month. Section

324(c) of the Act establishes a definition of a ISBMG as a person

engaged in the marketing of gasoline who would be required to pay for

the installation and operation of Stage II equipment. There are four

exemptions to this definition (i.e., four groups that will not be

considered ISBMGs): (1) A refiner; (2) a person who controls, is

controlled by or is under common control with a refiner; (3) a person

who otherwise is directly or indirectly affiliated with a refiner or a

person who controls, is controlled by or is under common control with a

refiner (unless the sole affiliation is by means of a supply contract

or an agreement or contract to use trademark, trade name, service mark,

or other identifying symbol or name owned by such refiner or any such

person); or (4) a person who receives less than 50 percent of this

annual income from refining or marketing of gasoline. In the General

Preamble, USEPA indicated that the suggested method for calculating the

gallons per month dispensed by affected facilities is determined by

calculating the average volume of product dispensed per month for the

2-year period prior to the adoption of the rule by the State. (See

General Preamble, 57 FR at 13514.) The Enforcement Guidance suggests

that if sufficient data is not available for a full 2-year period, then

the period should be extended to include a total of 24 months of

activity, or the actual months of operation during that 2-year period

should be used to calculate the facility's average gallons per month.

(See Enforcement Guidance, Sec. 3.2.)

(2) Establishment of a Time Schedule for Installation of Stage II

Control Equipment

Section 182(b)(3)(B) of the Act establishes three standard

deadlines for the installation and application of Stage II controls,

after adoption by the State of the Stage II requirements. The phase-in

schedule given in the Act is the following: (a) 6 months after adoption

for all facilities commencing construction after November 15, 1990; (b)

1 year after adoption for all facilities which dispense 100,000 gallons

or more of gasoline per month; and (c) 2 years after adoption for all

other facilities required to be regulated. For ISBMGs, section 324(a)

of the Act provides that the phase in periods may be: (a) 33 percent of

the facilities owned by an ISBMG by the end of the first year after the

regulations take effect; (b) 66 percent of such facilities by the end

of the second year; and (c) 100 percent of such facilities after the

third year.

(3) System Certification

An approved system should be tested and certified so as to meet a

minimum requirement of 95 percent emission reduction efficiency. The

USEPA believes that this efficiency rate has been demonstrated to be

feasible. As stated in the General Preamble, the States may achieve

this by utilizing one of the following three alternatives: (a) A method

tested and approved by CARB past, current or future recognized testing

methods, or (b) an equivalent testing program adopted by the State,

conducted by the Program Oversight Agency (POA) or by a third party

recognized by the POA, and submitted and approved by USEPA for

incorporation in the SIP, or (c) a system approved by CARB. (See

Enforcement Guidance, Sec. 4.2.)

(4) Facility Verification of the Proper Installation and Function of

Stage II Vapor Control Systems

The General Preamble indicates in order for the State Stage II

requirements to be enforceable, the State must require the regulated

facility to verify proper installation and function of the Stage II

equipment. The Enforcement Guidance specifies performing a Liquid

Blockage Test which determines if there is an unacceptable low point in

the piping, and a Leak Test which measures the vapor tightness of the

Stage II system. The Enforcement Guidance also states that a facility

should recertify the functions of the Stage II equipment as least every

5 years, or upon major system replacement or facility modification (75

percent or more of the facility's Stage II equipment), whichever occurs

first. (See April 16, 1992 (57 FR 13514) General Preamble, and;

Enforcement Guidance, Sec. 8.2.)

(5) Recordkeeping and Reporting

In the Enforcement Guidance, USEPA identifies various records that

the State should require facilities to keep and to make available upon

request. The USEPA believes that these documents must be available in

order to make the Stage II requirement enforceable. These documents

include: (a) A license/permit to install and operate the Stage II

system; (b) verification of passing functional tests after installation

of equipment, this includes the Liquid Blockage Test, Leak Test, and

all shutoff/flow prohibiting devise testing; (c) a general station file

containing initial station information such as motor vehicle fuel

throughput information; (d) an equipment maintenance and compliance

file log containing verification that proper maintenance has been

conducted in accordance with manufacturer's specifications and

requirements; and (e) training certification files. (See Enforcement

Guidance, Sec. 8.0.)

(6) Periodic Inspection of Regulated Facility

The State POA should conduct a minimum of 1 compliance inspection

per facility per year with mandatory follow-up at stations with

violations. USEPA believes such inspections are necessary to ensure

that facilities are complying with the Stage II requirements. This is

necessary not only for enforcement action but to notify sources that

are violating the Stage II requirements so they can make the necessary

adjustments to come into compliance. The compliance inspection should

consist of a visual inspection of the required paperwork and Stage I

and II equipment. In addition to the visual inspection, a functional

inspection to determine if the facility's Stage II equipment is

functioning properly must also be performed. (See Enforcement Guidance,

Sec. 5.2(d).)

(7) Regulated Facility Compliance

The State is required to ensure regulated facility compliance with

program requirements through enforcement mechanisms, and a penalty

schedule that establishes appropriate penalties for facilities

violating the Stage II requirements. (See Enforcement Guidance, Sec.

5.2(e).)

III. Results of USEPA Review

The USEPA reviewed the Indiana submittal to determine if criteria

for approval have been met. The results of USEPA's review are as

follows:

(1) Installation of Stage II Controls and Determination of Regulated

Facilities

Indiana's submittal mandates the requirement of Stage II vapor

recovery systems on any gasoline dispensing facility that dispenses a

monthly average volume of 10,000 gallons or more, and on ISBMGs who

dispense more than 50,000 gallons. The submittal also includes a

requirement that affected facilities be identified by calculating the

average volume of product dispensed per month for the 2-year period

prior to adoption of the rule by the State. Monthly averages are to

include only those months when the facility was operating. The USEPA

finds this acceptable because if fully addresses the Federal

requirement.

(2) Establishment of a Time Schedule for Installation of Stage II

Control Equipment

The Act specifies that the time period for installation and

operation of the Stage II equipment shall run from the State adoption

date of the Stage II rule. The Act defines adoption to mean the date

the State adopts the requirements for installation and operation of the

Stage II equipment. For all facilities, these compliance dates,

calculated from the time of State adoption of the regulation, are: (1)

6 months for facilities for which construction began after November 15,

1990; (2) 1 year for facilities that dispense greater than 100,000

gallons of gasoline per month; and (3) 2 years for all other

facilities. The Indiana Stage II rule time schedule sets compliance

dates of June 1, 1994, December 1, 1994, and December 1, 1995,

respectively for the above three deadlines based on the December 1,

1993, publication date of the rule in the Indiana Register. The State

has adopted this schedule for all affected facilities, including those

owned or operated by ISBMGs. Although Indiana adopted its regulations

on July 21, 1993, USEPA believes it is appropriate to interpret the

adoption date to be December 1, 1993, under the limited circumstances

presented in this submittal.

The USEPA is approving the submitted time table for the following

reasons. First, the Act states that the adoption date must be used to

calculate the compliance schedule for Stage II implementation at

facilities. In this case, USEPA defines the adoption date to be the

date after which a rule becomes effective in a State. Based on this

definition of adoption date USEPA accepts the December 1, 1993, rule

publication date as the adoption date from which the compliance

schedule is calculated. Second, the compliance deadlines triggered by

this date begin within the time schedule specified by the Act. Third,

remedying this deficiency by amending the compliance schedule would

cause further delay in the implementation of Stage II in Indiana.

Finally, the Indiana rule otherwise fulfills the Stage II requirements

and USEPA believes it will provide substantial air quality benefits to

the regulated areas. Therefore, USEPA believes it is in the public

interest to approve and make enforceable this requirement at the

earliest time feasible. In the limited circumstances above, USEPA

believes that it is not inconsistent to interpret the adoption date to

the December 1, 1993.

(3) System Certification

The adopted rule mandate that all Stage II vapor control systems

used be certified by CARB to meet 95 percent emission reduction

efficiency. Use of CARB-certified systems is acceptable to USEPA. The

USEPA has specified in its guidance documents that it believes that

CARB-approved Stage II systems meet the requirement of the Act with no

additional efficiency testing required. Therefore, USEPA finds the

specified system certification in the Indiana submittal acceptable.

(4) Installation of Stage II Vapor Control Systems

The Indiana rule mandates that proper tests be performed to verify

proper installation and function of the Stage II systems, and requires

systems to be retested every five years, or upon major system

replacement or modification. The USEPA believes the testing procedures

specified help make the rule enforceable and, therefore, are consistent

with the requirements of the Act.

(5) Recordkeeping and Reporting

The Indiana rule requires that the affected facilities submit a

registration form of their Stage II equipment to IDEM within forty-five

days after the installation of the Stage II equipment. In addition, the

rule requires that registration material be kept onsite. It also

requires that, at a minimum, the registration information includes: the

facility name and address, signature of owner or operator, the CARB

Executive Order Number for the Stage II system used, number of nozzles

used, the monthly average volume of gasoline dispensed, and the

location (including contact person's name, address, and telephone

number) of other records and reports required by the rule. Other

records and reports required by the rule to be kept on file by the

owner or operator and which need to be made available to the POA upon

request include: proof that a certified Stage II system has been

installed and tested to verify its performance according to its

specifications; records that show that proper maintenance has been

conducted according to manufacturer specifications; records that show

time periods and duration of all malfunctions of the Stage II system;

motor vehicle fuel throughput information for each calendar month of

the previous year; and proof of employee training certification. The

USEPA finds Indiana's recordkeeping and reporting requirements

acceptable.

(6) Periodic Inspection Requirements

The IDEM has committed to adhere to the Enforcement Guidance that

specifies annual inspections for the facilities with mandatory follow-

up at stations with violations or the development of an inspection

schedule approved by USEPA through IDEM's inspection program plan.

(7) Regulated Facility Compliance With Program Requirements

The Indian Code (IC 13-7-13-1, states that any person who violates

any provision of this article, IC 13-1-1, IC 13-1-3, or IC 13-1-11, or

any regulation or standard adopted by one (1) of the boards (i.e.,

Indiana Air Pollution Control Board), or who violates any

determination, permit, or order made or issued by the Commissioner (of

IDEM) pursuant to this article, IC 13-1-1, or IC 13-1-3, is liable for

a civil penalty not to exceed twenty-five thousand dollars ($25,000)

per day of any violation. In that this submittal is a regulation

adopted by the IAPCB, a violation of which subjects the violator to

penalties under IC 13-7-13-1, the submittal is consistent with the

policy established by USEPA in its Enforcement Guidance. In addition,

IDEM has submitted a civil penalty policy document which accounts for

various factors in the assessment of an appropriate civil penalty for

noncompliance with IAPCB rules. Some factors accounted for include:

severity of the violation, intent, frequency of violations, and other

factors.

IV. Rulemaking Action

The USEPA approves 326 IAC 8-1-0.5 and 8-4-6 as revisions to the

Indiana ozone SIP because the submittal meets all the criteria required

for approvability, as cited above. The Stage II vapor recovery SIP

revision for the Lake, Porter, Clark, and Floyd Counties ozone

nonattainment areas will be complete following this action.

The USEPA is approving this action without prior proposal because

the USEPA views this as a noncontroversial revision and anticipate no

adverse comments. This action will be effective on June 27, 1994

unless, May 31, 1994 someone wishes to submit adverse comments. If such

notice is received, this action will be withdrawn before the effective

date by publishing two subsequent documents. One document will withdraw

the final action and another will begin a new rulemaking by announcing

a proposal of the action and establishing a comment period. If no such

comments are received, the public is advised that this action will be

effective on June 27, 1994.

This action has been classified as a Table 2 action by the Regional

Administrator under the procedures published in the Federal Register on

January 19, 1989, (54 FR 2214-2225). A revision to the SIP processing

review tables was approved by the Acting Assistant Administrator for

Office of Air and Radiation on October 4, 1993 (Michael Shapiro's

memorandum to Regional Administrators). A future document will inform

the general public of these tables. Under the revised tables this

action remains classified as a Table 2. On January 6, 1989, the Office

of Management and Budget (OMB) waived Table 2 and 3 SIP revisions (54

FR 2222) from the requirements of section 3 of Executive Order 12291

for a period of 2 years. USEPA has submitted a request for a permanent

waiver for Table 2 and Table 3 SIP revisions. OMB has agreed to

continue the waiver until such time as it rules on USEPA's request.

This request continued in effect under Executive Order 12866 which

superseded Executive Order 12291 on September 30, 1993.

Nothing in this action should be construed as permitting or

allowing or establishing a precedent for any future request for

revision to any SIP. Each request for revision to the SIP shall be

considered separately in light of specific technical, economic, and

environmental factors and in relation to relevant statutory and

regulatory requirements.

Under the Regulatory Flexibility Act, 5 U.S.C. 600 et seq, USEPA

must prepare a regulatory flexibility analysis assessing the impact of

any proposed or final rule on small entities. 5 U.S.C. 603 and 604.

Alternatively, USEPA may certify that the rule will not have a

significant impact on a substantial number of small entities. Small

entities include small businesses, small not-for-profit enterprises,

and government entities with jurisdiction over populations of less than

50,000.

SIP approvals under section 110 and subchapter I, part D of the Act

do not create any new requirements, but simply approve requirements

that the State is already imposing. Therefore, because the Federal SIP

approval does not impose any new requirements, I certify that it does

not have a significant impact on any small entities affected. Moreover,

due to the nature of the federal-state relationship under the Act,

preparation of a regulatory flexibility analysis would constitute

Federal inquiry into the economic reasonableness of state action. The

Act forbids USEPA to base its actions concerning SIPs on such grounds.

Union Electric Co. v. U.S. E.P.A., 427 U.S. 246, 256-66 (S.Ct. 1976);

42 U.S.C. 7410(a)(2).

Under section 307(b)(1) of the Act, petitions for judicial review

of this action must be filed in the United States Court of Appeals for

the appropriate circuit by June 27, 1994. Filling a petition for

reconsideration by the Administrator of this final rule does not affect

the finality of this rule for the purposes of judicial review not does

it extend the time within which a petition for judicial review may be

filed, and shall not postpone the effectiveness of such rule or action.

This action may not be challenged later in proceedings to enforce

requirements. (See section 307(b)(2).)

List of Subjects in 40 CFR Part 52

Environmental protection, Air pollution control, Hydrocarbons,

Incorporation by reference, Intergovernmental relations, Ozone,

Reporting and record keeping requirements, Volatile organic compounds.

Dated: April 8, 1994.

Michelle D. Jordan,

Acting Regional Administrator.

For the reasons set out in the preamble, part 52, chapter I, title

40 of the Code of Federal Regulations is amended as follows:

PART 52--[AMENDED]

1. The authority citation for part 52 continues to read as follows:

Authority: 42 U.S.C. 7401-7671q.

Subpart P--Indiana

2. Section 52.770 is amended by adding paragraph (c)(93) to read as

follows:

Sec. 52.770 Identification of plan.

* * * * *

(c) * * *

(93) On February 25, 1994 the Indiana Department of Environmental

Management requested a revision to the Indiana State Implementation

Plan in the form of Stage II Vapor Recovery Rules as amendments to

Title 326 of the Indiana Administrative Code (326 IAC) 8-1-0.5 and 8-4-

6.

(i) Incorporation by reference. (A) 326 IAC 8-1-0.5 Definitions and

8-4-6 Gasoline dispensing facilities. Filed with the Secretary of State

October 28, 1993, effective November 29, 1993. Published at Indiana

Register, Volume 17, Number 3, December 1, 1993.

[FR Doc. 94-10111 Filed 4-26-94; 8:45 am]

BILLING CODE 6560-50-M

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.