Green River Power Corporation; Notice of Reasonable Period of Time for Water Quality Certification Application
Federal RegisterSep 9, 2026
Ask Donna
What actually matters in this document.
Text
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 8405-024]
Green River Power Corporation; Notice of Reasonable Period of Time for Water Quality Certification Application
On September 2, 2026, the New Hampshire Department of Environmental Services (New Hampshire DES) filed with the Federal Energy Regulatory Commission (Commission) notice that it received a complete request for Clean Water Act section 401(a)(1) water quality certification from Green Mountain Power Corporation in conjunction with the above captioned project, on July 20,
2026. Pursuant to section 5.23(b) of the Commission's regulations,
1
we hereby notify New Hampshire DES of the following:
1
18 CFR 5.23(b).
Date of Receipt of the Certification Request:
July 20, 2026.
Reasonable Period of Time to Act on the Certification Request:
One year, July 20, 2027.
If New Hampshire DES fails or refuses to act on the water quality certification requests on or before the above date, then the certifying authority is deemed waived pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1).
(Authority: 18 CFR 2.1.)
Dated: September 3, 2026.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2026-18359 Filed 9-8-26; 8:45 am]
BILLING CODE 6717-01-P