Pacific Gas and Electric Company; Notice of Reasonable Period of Time for Water Quality Certification Application
Federal RegisterAug 12, 2025
Ask Donna
What actually matters in this document.
Text
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2735-104]
Pacific Gas and Electric Company; Notice of Reasonable Period of Time for Water Quality Certification Application
On July 31, 2025, the California State Water Resources Control Board (Water Board) submitted to the Federal Energy Regulatory Commission (Commission) notice that it received a request for a Clean Water Act section 401(a)(1) water quality certification as defined in 40 CFR. 121.5, from Pacific Gas and Electric Company, in conjunction with the above captioned project, on July 25, 2025. Pursuant to the Commission's regulations,
1
we hereby notify the Water Board of the following:
1
18 CFR 4.34(b)(5).
Date of Receipt of the Certification Request: July 25, 2025
Reasonable Period of Time to Act on
If the Water Board fails or refuses to act on the water quality certification request on or before the above date, then the certifying authority is deemed waived pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1).
Dated: August 6, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-15232 Filed 8-11-25; 8:45 am]
BILLING CODE 6717-01-P
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.