DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 15366-000]

Town of Stowe Electric Department; Notice of Reasonable Period of Time for Water Quality Certification Application

On April 30, 2025, the Town of Stowe Electric Department submitted to the Federal Energy Regulatory Commission (Commission) documentation from the Vermont Department of Environmental Conservation (Vermont DEC) that it received a request for a Clean Water Act section 401(a)(1) water quality certification as defined in 40 CFR 121.5, from the Town of Stowe Electric Department, in conjunction with the above captioned project on April 25, 2025. Pursuant to the Commission's regulations,

1

we hereby notify Vermont DEC of the following.

1

18 CFR 4.34(b)(5)(iii).

Date of Receipt of the Certification Request:

April 25, 2025.

Reasonable Period of Time to Act on the Certification Request:

One year, April 25, 2026.

If Vermont DEC fails or refuses to act on the water quality certification request on or before the above date, then the certifying authority is deemed waived pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1).

Dated: May 2, 2025.

Debbie-Anne A. Reese,

Secretary.

[FR Doc. 2025-08069 Filed 5-7-25; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.