DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. IC25-5-000]
Commission Information Collection Activities (FERC-545); Comment Request; Extension
AGENCY:
Federal Energy Regulatory Commission.
ACTION:
Notice of information collection and request for comments.
SUMMARY:
In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is soliciting public comment on the currently approved information collection, “FERC 545: Gas Pipeline Rates: Rate Change (Non-Formal)”. No comments were received on the 60-day notice that was published on January 8, 2025.
DATES:
Comments on the collection of information are due April 25, 2025.
ADDRESSES:
Send written comments on FERC-545 to OMB through
www.reginfo.gov/public/do/PRAMain
. Attention: Federal Energy Regulatory Commission Desk Officer. Please identify the OMB Control Number (FERC 545: 1902-0154) in the subject line of your comments. Comments should be sent within 30 days of publication of this notice to
www.reginfo.gov/public/do/PRAMain
.
Please submit copies of your comments to the Commission. You may submit copies of your comments (identified by Docket No. IC25-5-000) by one of the following methods:
Electronic filing through
https://www.ferc.gov,
is preferred.
•
Electronic Filing:
Documents must be filed in acceptable native
applications and print-to-PDF, but not in scanned or picture format.
• For those unable to file electronically, comments may be filed by USPS mail or by other delivery methods:
○
Mail via U.S. Postal Service Only:
Federal Energy Regulatory Commission, Secretary of the Commission, 888 First Street NE, Washington, DC 20426.
○ All other delivery methods: Federal Energy Regulatory Commission, Secretary of the Commission, 12225 Wilkins Avenue, Rockville, MD 20852.
Instructions:
OMB submissions must be formatted and filed in accordance with submission guidelines at
www.reginfo.gov/public/do/PRAMain
. Using the search function under the “Currently Under Review” field, select Federal Energy Regulatory Commission; click “submit,” and select “comment” to the right of the subject collection.
FERC submissions
must be formatted and filed in accordance with submission guidelines at:
https://www.ferc.gov/ferc-online/overview
. For user assistance, contact FERC Online Support by email at
ferconlinesupport@ferc.gov,
or by phone at: (866) 208-3676 (toll-free).
Docket:
Users interested in receiving automatic notification of activity in this docket or in viewing/downloading comments and issuances in this docket may do so at
https://www.ferc.gov/ferc-online/overview.
FOR FURTHER INFORMATION CONTACT:
Kayla Williams may be reached by email at
DataClearance@FERC.gov,
telephone at (202) 502-6468.
SUPPLEMENTARY INFORMATION:
Title:
FERC-545: Gas Pipeline Rates: Rate Change (Non-formal).
OMB Control No.:
1902-0154.
Type of Request:
Three-year extension of the FERC-545 information collection requirements with no changes to the reporting requirements.
Abstract:
FERC-545 is required to implement sections 4, 5, and 16 of the Natural Gas Act (NGA) (15 U.S.C. 717c, 717d, and 717o). NGA Sections 4, 5, and 16 authorize the Commission to inquire into rate structures and methodologies and to set rates at a just and reasonable level. Specifically, a natural gas company must obtain Commission authorization for all rates and charges made, demanded, or received in connection with the transportation or sale of natural gas in interstate commerce. FERC-545 consists of: (1) Tariff Filings which are filings regarding proposed changes to a pipeline's tariff and any related compliance filings; 2) Rate Filings which are rate-related filings under NGA sections 4 and 5 and any related compliance filings and settlements; (3) Informational Reports, for example, annual reconciliation reports. (4) Negotiated Rates and Non-Conforming Agreement Filings; (5) North American Energy Standards Board (NAESB) Filings; (6) Market-Based Rates for Storage Filings; and (6) the Labor-Wage Policy which allows jurisdictional entities to include wages consistent with project-area standards in cost-of-service rates filed with the Commission where the record supports that outcome.
Under the NGA, a natural gas company's rates must be just and reasonable and not unduly discriminatory or preferential. The Commission may act under different sections of the NGA to effect a change in a natural gas company's rates. When the Commission reviews rate increases that a natural gas company has proposed, it is subject to the requirement of section 4(e) of the NGA. These types of filings are referred to as general section 4 rate cases. In the proceedings, the Commission reviews a pipeline's rates and services. A pipeline can file a general section 4 rate case anytime it wishes, provided the pipeline did not agree otherwise in a settlement. A pipeline must demonstrate that the new rates it proposes to charge are just and reasonable. When a rate increase filing is made pursuant to section 4, the application is typically suspended and set for hearing by a Commission Order. On the other hand, when the Commission seeks to impose its own rate determination, it must do so in compliance with section 5(a) of the NGA. Under section 5, the Commission must first establish and demonstrate that a pipeline's existing rate is no longer just and reasonable.
Section 16 of the NGA states that the Commission “shall have the power to perform any and all acts, and to prescribe, issue, make, amend, and rescind such orders, rules, and regulations as it may find necessary or appropriate to carry out provisions of [the NGA].” In other words, section 16 of the NGA grants the Commission the power to define accounting, technical and trade terms, prescribe forms, statements, declarations or reports and to prescribe rules and regulations.
Pipelines adjust their tariffs to meet market and customer needs. Commission review of these proposed changes is required to ensure rates remain just and reasonable and that services are not provided in an unduly or preferential manner. The Commission's regulation in 18 CFR part 154 specifies what changes are allowed and the procedures for requesting Commission approval.
Type of Respondents:
Jurisdictional natural gas companies.
Estimate of Annual Burden:
1
The Commission estimates the annual public reporting burden for the information collection as:
1
Burden is defined as the total time, effort, or financial resources expended by persons to generate, maintain, retain, or disclose or provide information to or for a Federal agency. Refer to 5 CFR 1320.3 for additional information.
FERC-545—Gas Pipeline Rates: Rate Change
[Non-Formal] [No change]
Number of
respondents
Average
number of
responses per
respondent
Total
number of
responses
Average burden &
cost per response
2
Total annual burden hours & total annual cost
Cost per
respondent
($)
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
(5) ÷ (1)
Tariff Filings
141
3
423
211 hrs.; $22,999
89,253 hrs.; $9,728,577
$68,997
Rate Filings
19
2
38
354 hrs.; $38,586
13,452 hrs.; $1,466,268
77,172
Informational Reports
80
2
160
235 hrs.; $25,615
37,600 hrs.; $4,098,400
51,230
Negotiated Rates & Non-Conforming Agreement Filings
75
8
600
233 hrs.; $25,397
139,800 hrs.; $15,238,200
203,176
Market-Base Rates for Storage Filings
2
1
2
230 hrs.; $25,070
460 hrs.; $50,140
25,070
NAESB (version 3.2) one time over 3 years carried over from RM96-1-042
3
59.33
1
59.33
10 hrs.; $1,090
593.30 hrs.; $64,669.70
1,090
Labor-Wage Policy
4
11
1
11
15 hrs.; $1,635
165 hrs.; $17,985
1,635
Total (Including Section 4 Rate Cases)
1,293 (rounded)
281,323 hrs. (rounded); $30,664,240
Comments:
Comments
are invited on: (1) whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency's estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use of automated collection techniques or other forms of information technology.
2
The estimated hourly cost (salary plus benefits) provided in this section is based on the salary figures for May 2023 posted by the Bureau of Labor Statistics for the Utilities sector (available at
https://www.bls.gov/oes/current/naics3_221000.htm
) and scaled to reflect benefits using the relative importance of employer costs for employee compensation from March 2023 available at
https://www.bls.gov/news.release/ecec.nr0.htm
). The hourly estimates for salary plus benefits are: Computer and Information Systems Manager (Occupation Code: 11-3021), $115.47; Computer and Information Analysts (Occupation Code: 15-1210), $80.10; Electrical Engineer (Occupation Code: 17-2071), $79.31; Legal (Occupation Code: 23-0000), $162.66. The average hourly cost (salary plus benefits) weighting all of the above skill sets evenly, is $109.38. We round it to $109/hour.
3
At the time of this notice for extension request, Docket No. RM96-1-043 was issued by the Commission on November 22, 2024. The Order updated the requirement to reflect the Wholesale Gas Quadrant (WGQ) 4.0 standards. OMB has not yet approved this modification as it has not published in the
Federal Register
, which is required for Information Collection Requests (ICRs) to be submitted. However, to prevent a lapse in the approval of the existing collection's expiration date, the Commission is publishing this Notice with the currently approved burden estimates that involve the NAESB standards (59.33 responses). The updated burden estimates for the NAESB revisions will increase the burden to 64.33 (rounded) responses, which is the average number of responses per annum.
4
Project-Area Wage Standards in the Labor Cost Component of Cost-of-Service Rates under Docket No. PL24-1-000 was issued on March 21, 2024, which allows jurisdictional entities to include wages consistent with project-area standards in cost-of-service rates filed with the Commission where the record supports that outcome.
Dated: March 20, 2025.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2025-05107 Filed 3-25-25; 8:45 am]
BILLING CODE 6717-01-P
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.