City of Hamilton, Ohio, American Municipal Power, Inc.: Notice of Reasonable Period of Time for Water Quality Certification Application

Federal RegisterOct 31, 2024

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2614-042]

City of Hamilton, Ohio, American Municipal Power, Inc.: Notice of Reasonable Period of Time for Water Quality Certification Application

On October 23, 2024, the Ohio Environmental Protection Agency (Ohio EPA) submitted to the Federal Energy Regulatory Commission (Commission) notice that it received a complete application for a Clean Water Act section 401(a)(1) water quality certification, as defined in 40 CFR 121.5, from City of Hamilton, Ohio and American Municipal Power, Inc. in conjunction with the above captioned project on October 17, 2024. Pursuant to section 4.34(b)(5) of the Commission's regulations,

1

we hereby notify Ohio EPA of the following:

1

18 CFR 4.34(b)(5) (2024).

Date of Receipt of the Certification Request:

October 17, 2024.

Reasonable Period of Time to Act on the Certification Request:

One year (October 17, 2025).

If Ohio EPA fails or refuses to act on the water quality certification request on or before the above date, then the certifying authority is deemed waived pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1).

Dated: October 24, 2024.

Debbie-Anne A. Reese,

Secretary.

[FR Doc. 2024-25271 Filed 10-30-24; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.