Eagle Creek Racine Hydro, LLC; Notice of Waiver Period for Water Quality Certification Application

Federal RegisterDec 28, 2022

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2570-034]

Eagle Creek Racine Hydro, LLC; Notice of Waiver Period for Water Quality Certification Application

On December 21, 2022, Eagle Creek Racine Hydro, LLC submitted to the Federal Energy Regulatory Commission (Commission) a copy of its application for a Clean Water Act section 401(a)(1) water quality certification filed with the Ohio Environmental Protection Agency (Ohio EPA), in conjunction with the above captioned project. Pursuant to 40 CFR 121.6 and section 5.23(b) of the Commission's regulations,

1

we hereby notify the Ohio EPA of the following:

1

18 CFR 5.23(b).

Date of Receipt of the Certification Request:

December 20, 2022

Reasonable Period of Time To Act on the Certification Request:

One year (December 20, 2023)

If the Ohio EPA fails or refuses to act on the water quality certification request on or before the above date, then the agency certifying authority is deemed waived pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1).

Dated: December 21, 2022.

Kimberly D. Bose,

Secretary.

[FR Doc. 2022-28250 Filed 12-27-22; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.