DEPARTMENT OF TRANSPORTATION

Federal Highway Administration

Notice of Final Federal Agency Action on Proposed Highway in

Georgia the Interstate 75 (I-75) Express, Clayton and Henry Counties,

Georgia (Atlanta Metropolitan Area)

AGENCY: Federal Highway Administration (FHWA), DOT.

ACTION: Notice of Limitation on Claims for Judicial Review of Actions

by Army Corps of Engineers (USACE).

-----------------------------------------------------------------------

SUMMARY: This notice announces actions taken by USACE and other Federal

agencies that are final within the meaning of 23 U.S.C. 139(l)(1). The

I-75 Express Lanes Project will design a managed lane system along I-75

from the SR 155 (Zack Hinton Parkway, South) interchange in Henry

County north to the SR 138 (Stockbridge Highway) interchange in Clayton

County located in Georgia. The project spans a distance of

approximately 17.94 miles. Those actions grant licenses, permits and

approvals for the project.

DATES: By this notice, the FHWA is advising the public of the final

agency actions subject to 23 U.S.C. 139(l)(1). A claim seeking judicial

review of the Federal agency action on the highway project will be

barred unless the claim is filed on or before April 3, 2015. If the

Federal law that authorizes judicial review of a claim provides a time

period of less than 150 days for filing such claim, then that shorter

time period still applies.

FOR FURTHER INFORMATION CONTACT: Mr. Rodney Barry, Division

Administrator, Georgia Division, Federal Highway Administration, 61

Forsyth Street, Suite 17T100, Atlanta, Georgia 30303; 8:00 a.m. to 5:00

p.m. (eastern time) Monday through Friday, 404-562-3630; email:

[email protected]; for USACE: Edward Johnson, Chief, Regulatory

Branch, U.S. Army Corps of Engineers, Savanah District-Piedmont Branch,

1590 Adamson Parkway, Suite 200, Morrow, Georgia, 30260-1777; telephone

(678) 422-2235, Email: [email protected]; and for Georgia

Department of Transportation (GDOT): Mr. Keith Golden, Commissioner,

Georgia Department of Transportation, 600 West Peachtree Street, 22th

Floor, Atlanta, Georgia 30308, 8:00 a.m. to 5:00 p.m. (eastern time)

Monday through Friday, Telephone: (404) 631-1005, Email:

[email protected]. USACE's normal business hours are 8:00 a.m. to 5:00

p.m. (Eastern Time).

SUPPLEMENTARY INFORMATION: On July 5, 2013, the FHWA published a

``Notice of Final Federal Agency Actions on Proposed Highway in

Georgia'' the Interstate 75 (I-75) Express located in Clayton and Henry

Counties (Atlanta Metropolitan Area) in the Federal Register at [FR

Doc. 2013-16112] for the following project: The I-75 Express lanes

project consists of constructing managed lanes from the SR 155 (Zack

Hinton Parkway, South) interchange in Henry County north to the SR 138

(Stockbridge Highway) interchange located in metropolitan Atlanta,

Georgia. The Selected Alternative will construct managed lanes in Henry

County at the I-75 Bridge over SR 155 and terminate in Clayton County

approximately 600 feet south of the I-75 southbound on-ramp from SR 139

and at SR 139 on I-675. From SR 155 to approximately one mile south of

Mt. Carmel Road, a single reversible lane will be constructed. The

single lane will then transition to two reversible lanes, which will

continue to the northern terminus of the facility. Intelligent

Transportation System infrastructure will be constructed to support the

usage of the managed lanes. The facility will include improvements of

approximately 17.94 miles on I-75. Congestion on this facility will be

managed by electronic toll lane (ETL). The purpose of the project is

listed below:

Consistency with regional transportation planning

initiatives

[[Page 65476]]

Provide reliable trip times and mobility

Improve travel choices

Expedite project delivery through the use of tolling for

financing (construction financing implications)

Reduce congestion

Accommodate regional growth and accessibility.

The actions by the Federal agencies and the laws under which such

actions were taken are described in the Draft Environmental Assessment

(DEA), Final Environmental Assessment (EA) and in the FHWA Finding of

No Significant Impact (FONSI) approved on March 12, 2013 and June 28,

2013 respectively, and in other documents in the FHWA project records.

Notice is hereby given that, subsequent to the earlier FHWA notice, the

USACE has taken final agency actions within the meaning of 23 U.S.C.

139(1)(1) by issuing a permit and approval for the highway project. The

actions of the USACE, related final actions by other Federal agencies,

and the laws under which such actions were taken are described in the

USACE decisions and its project records, referenced as [SAS-2012-

00385]. This information by contacting the USACE at the address

provided above.

Information about the project and project records are available

from FHWA and the Georgia Department of Transportation (GDOT) at the

addresses provided above. The FHWA National Environmental Policy Act

(NEPA) documents such as DEA, FEA/FONSI, the reevaluated FEA/FONSI and

other project records are available by contacting FHWA or GDOT at the

addresses listed above. The FHWA EA/FONSI, can be reviewed and

downloaded from the project Web site at http://www.I75Express.com or at

the following offices: GDOT District 3 Area Office, 115 Transportation

Boulevard, Thomaston, Georgia 30286; GDOT District 7 Office, 5025 New

Peachtree Road, Chamblee, Georgia 30341; McDonough Public Library, 1001

Florence McGarity Boulevard, McDonough, Georgia 30252; Cochran Public

Library, 174 Birch Street, Stockbridge, Georgia 30281 and Clayton

County Library System, Morrow Branch, 6225 Maddox Road, Morrow, Georgia

30260. The USACE decision can be viewed and downloaded from the project

Web site at [http://www.I75Express.com] or viewed at public libraries

in the project area listed above. Paper copies are available on request

by contacting Loren Bartlett, Georgia Department of Transportation, 600

West Peachtree Street, 22th Floor, Atlanta, Georgia 30308, Telephone:

(404) 631-1642, Email: [email protected]. This notice applies to all

USACE and other Federal agency final actions taken after the issuance

date of the FHWA Federal Register notice described above. The laws

under which actions were taken include, but are not limited to:

1. Wetlands and Water Resources: Clean Water Act (Section 404).

(Catalog of Federal Domestic Assistance Program Number 20.205,

Highway Planning and Construction. The regulations implementing

Executive Order 12372 regarding intergovernmental consultation on

Federal programs and activities apply to this program)

Authority: 23 U.S.C. 139(l)(1), as amended by Moving Ahead for

Progress in the 21st Century Act (MAP-21), Public Law 112-141, Sec.

1308, 126 Stat. 405 (2012).

Issued On: October 28, 2014.

Rodney Barry,

Division Administrator, Atlanta, Georgia.

[FR Doc. 2014-26134 Filed 11-3-14; 8:45 am]

BILLING CODE P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.