Revisions to Environmental Review for Renewal of Nuclear Power Plant Operating Licenses

Federal RegisterJun 20, 2013

Ask Donna

What actually matters in this document.

Text

NUCLEAR REGULATORY COMMISSION

10 CFR Part 51

RIN 3150-AI42

[NRC-2008-0608]

Revisions to Environmental Review for Renewal of Nuclear Power Plant Operating Licenses

AGENCY:

Nuclear Regulatory Commission.

ACTION:

Final rule.

SUMMARY:

The U.S. Nuclear Regulatory Commission (NRC) is amending its environmental protection regulations by updating the Commission's 1996 findings on the environmental effect of renewing the operating license of a nuclear power plant. The final rule redefines the number and scope of the environmental impact issues that must be addressed by the NRC during license renewal environmental reviews. This final rule also incorporates lessons learned and knowledge gained from license renewal environmental reviews conducted by the NRC since 1996.

DATES:

This rule is effective on July 22, 2013. However, compliance is not required until June 20, 2014.

ADDRESSES:

Please refer to Docket ID NRC-2008-0608 when contacting the NRC about the availability of information for this final rule. You may access information and comment submittals related to this final rulemaking, which the NRC possesses and is publicly available, by the following methods:

•

Federal Rulemaking Web site:

Go to

http://www.regulations.gov

and search for Docket ID NRC-2008-0608. Address questions about NRC dockets to Carol Gallagher; telephone: 301-492-3668; email:

Carol.Gallagher@nrc.gov.

For technical questions, contact the individuals listed in the

FOR FURTHER INFORMATION CONTACT

section of this final rule.

•

NRC's Agencywide Documents Access and Management System (ADAMS

): You may access publicly available documents online in the NRC Library at

http://www.nrc.gov/reading-rm/adams.html

. To begin the search, select “

ADAMS Public Documents

” and then select “

Begin Web-based ADAMS Search.

” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by email to

pdr.resource@nrc.gov

. The ADAMS accession number for each document referenced in this notice (if that document is available in ADAMS) is provided the first time that a document is referenced. In addition, for the convenience of the reader, the ADAMS accession numbers are provided in a table in Section XII, “Availability of Documents,” of this document.

•

NRC's PDR:

You may examine and purchase copies of public documents at the NRC's PDR, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT:

Mr. Stewart Schneider, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-4123; email:

Stewart.Schneider@nrc.gov;

or Mr. Jeffrey Rikhoff, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-1090; email:

Jeffrey.Rikhoff@nrc.gov

.

Executive Summary

Purpose of the Regulatory Action

The Atomic Energy Act of 1954 authorizes the NRC to issue commercial nuclear power plant operating licenses for up to 40 years. The NRC's regulations allow for the renewal of these operating licenses for up to an additional 20 years. The license renewal process includes reviewing a license renewal application, conducting the assessment, and then, if all applicable safety standards are met, renewing the license. The NRC's review of a license renewal application proceeds along two independent regulatory tracks: one for safety issues and another for environmental issues. The license renewal process is defined by a clear set of regulations that are designed to ensure safe operation and protection of the environment during the license renewal term. The NRC's regulations for the license renewal safety review are set forth in Part 54 of Title 10 of the

Code of Federal Regulations

(10 CFR). The NRC's environmental protection regulations are set forth in 10 CFR part 51.

The renewal application is the principal document that an applicant provides to both request and support renewal for a nuclear power reactor's operating license. The license renewal application includes both general and technical information that demonstrates that an applicant is in compliance with the NRC's regulations in 10 CFR part 54. During the renewal process, the license renewal applicant must confirm whether the design assumptions used for the original licensing basis will continue to be valid throughout the period of extended operation and that the aging effects will be adequately managed. The applicant must demonstrate that the effects of aging will be managed in such a way that the intended functions of “passive” or “long-lived” structures and components (such as the reactor vessel, reactor coolant system, piping, steam generators, pressurizer, pump casings, and valves) will be maintained during the license renewal term (also known as the period of extended operation). For active components, such as motors, diesel generators, cooling fans, batteries, relays, and switches, the Commission's ongoing regulatory oversight programs already ensure that the components continue to perform their intended function during the period of license renewal. This information must be sufficiently detailed in the application to permit the NRC staff to determine if the applicant's management of these issues is adequate to allow operation during the extended period of operation without undue risk to the public and workers' health and safety.

In addition to the safety assessment, the applicant must also prepare an evaluation of the potential impacts to the environment of facility operation for an additional 20 years. Under the NRC's environmental protection regulations in 10 CFR part 51, which implement the National Environmental Policy Act (NEPA), renewal of a nuclear power plant operating license requires the preparation of an environmental impact statement (EIS). To support the preparation of these EISs, the NRC issued a rule in 1996 to define which impacts would essentially be the same at all nuclear power plants (Category 1 issues) and which ones could be different at different plants and would require a plant-specific analysis to determine the impacts (Category 2 issues). For each license renewal application, those impacts that require a plant-specific analysis must be analyzed by the applicant in its environmental report and by the NRC in its associated EIS. The final rule amends those regulations by updating the Commission's 1996 rule. The final rule redefines the number and scope of the environmental impact issues that must be addressed by the NRC and applicants during license renewal environmental reviews. These changes are based primarily on lessons learned and knowledge gained from license renewal environmental reviews conducted by the NRC since 1996.

The NRC prepared a regulatory analysis to determine the expected quantitative and qualitative costs and benefits of the final rule. The analysis concluded that the final rule will result

in net savings to the industry and the NRC. For more information, please see the regulatory analysis (ADAMS Accession No. ML110760321).

Summary of the Major Rule Changes

In the 1996 rule, there were 92 environmental impact issues, 23 of which required a plant-specific analysis (Category 2 issues) during license renewal environmental reviews. In the final rule, there are 78 environmental impact issues, 17 of which require a plant-specific analysis. The following bullets summarize the major changes to the rule:

• Based on the related nature of the issues, several Category 1 issues were consolidated with other Category 1 issues. This includes some issues that were changed from Category 2 to Category 1 and subsequently combined with other, related Category 1 issues. Similarly, several Category 2 issues were combined with related Category 2 issues.

• New Category 1 issues were added: geology and soils; effects of dredging on surface water quality; groundwater use and quality; exposure of terrestrial organisms to radionuclides; exposure of aquatic organisms to radionuclides; effects of dredging on aquatic organisms; impacts of transmission line right-of-way management on aquatic resources; employment and income; tax revenues; human health impacts from chemicals; and physical occupational hazards.

• Several issues were changed from Category 2 to Category 1: Offsite land use, air quality, public services (several issues), and population and housing.

• New Category 2 issues were added: Radionuclides released to groundwater, water use conflicts with terrestrial resources, water use conflicts with aquatic resources, and cumulative impacts.

• One uncharacterized issue was reclassified as Category 2: Environmental justice/minority and low-income populations.

• One Category 1 issue was revised to narrow the scope of its finding due to the United States Court of Appeals for the District of Columbia Circuit (D.C. Circuit) decision in

New York

v.

NRC,

681 F.3d 471 (D.C. Cir. 2012), which vacated the NRC's 2010 Waste Confidence Decision and Rule (75 FR 81032 and 81037; December 23, 2010): Onsite storage of spent nuclear fuel.

• One Category 1 issue was reclassified as uncategorized due to the

New York

v.

NRC

decision: Offsite radiological impacts of spent nuclear fuel and high-level waste disposal.

SUPPLEMENTARY INFORMATION:

I. Background

II. Public Meetings

III. Discussion

IV. Response to Public Comments

A. Overview

B. Summary of Comments Resulting in Substantive Changes to the Rule

C. Summary of Other Comments

V. Related Issues of Importance

A. Fukushima Events

B. Removal of References to the Waste Confidence Decision and Rule

C. Effective and Compliance Dates for Final Rule

D. Best Management Practices

E. Definition of “Historic Properties”

VI. Revisions to 10 CFR 51.53

A. Reclassifying Category 2 Issues as Category 1 Issues

B. Adding New Category 2 Issues

VII. Response to Specific Request for Voluntary Information

VIII. Final Actions and Basis for Changes to Table B-1

IX. Section-by-Section Analysis

X. Guidance Documents

XI. Agreement State Compatibility

XII. Availability of Documents

XIII. Voluntary Consensus Standards

XIV. Environmental Impact—Categorical Exclusion

XV. Paperwork Reduction Act Statement

XVI. Plain Writing

XVII. Regulatory Analysis

XVIII. Regulatory Flexibility Act Certification

XIX. Backfitting and Issue Finality

XX. Congressional Review Act

I. Background

Rulemaking History

In 1986, the NRC initiated a program to develop license renewal regulations and associated regulatory guidance in anticipation of receiving applications for the renewal of nuclear power plant operating licenses. In 1996, the NRC published a final rule that amended the environmental protection regulations in 10 CFR part 51 for applicants seeking to renew an operating license for up to an additional 20 years.

1

The 1996 final rule was based upon the analyses and findings of a May 1996 NRC environmental impact statement, “Generic Environmental Impact Statement for License Renewal of Nuclear Plants,” NUREG-1437 (the “1996 GEIS”) (Vol. 1, “Main Report,” ADAMS Accession No. ML040690705; Vol. 2, “Appendices,” ADAMS Accession No. ML040690738).

1

61 FR 28467 (June 5, 1996).

Based upon the findings of the 1996 GEIS, the 1996 final rule identified those license renewal environmental impact issues for which a generic analysis had been determined to be appropriate and therefore, did not have to be addressed by a license renewal applicant in its plant-specific environmental report or by the NRC in its plant-specific supplemental environmental impact statements (SEISs) to the 1996 GEIS. Similarly, based upon the findings of the 1996 GEIS, the 1996 final rule identified those environmental impacts for which a site- or plant-specific analysis was required, both by the applicant in its environmental report and by the NRC in its SEIS. The 1996 final rule, amongst other amendments to 10 CFR part 51, added Appendix B to Subpart A of 10 CFR part 51, “Environmental Effect of Renewing the Operating License of a Nuclear Power Plant.” Appendix B included Table B-1, “Summary of Findings on NEPA Issues for License Renewal of Nuclear Power Plants,” which summarized the findings of the 1996 GEIS.

In preparing the 1996 GEIS, the Commission determined that certain environmental impacts associated with the renewal of a nuclear power plant operating license were the same or similar for all plants and, as such, could be treated on a generic basis. In this way, repetitive reviews of these environmental impacts could be avoided. The Commission based its generic assessment of certain environmental impacts on the following factors:

(1) License renewal will involve nuclear power plants for which the environmental impacts of operation are well understood as a result of lessons learned and knowledge gained from operating experience and completed license renewals.

(2) Activities associated with license renewal are expected to be within this range of operating experience; thus, environmental impacts can be reasonably predicted.

(3) Changes in the environment around nuclear power plants are gradual and predictable.

The 1996 GEIS improved the efficiency of the license renewal process by: (1) Providing an evaluation of the types of environmental impacts that may occur from renewing commercial nuclear power plant operating licenses; (2) identifying and assessing impacts that are expected to be generic (i.e., the same or similar) at all nuclear power plants or plants with specified plant or site characteristics; and (3) defining the number and scope of environmental impacts that need to be addressed in plant-specific SEISs to the 1996 GEIS.

In short, the 1996 final rule identified environmental impact issues (i.e., Category 1 issues)

2

that do not have to

be addressed by licensees in environmental reports for nuclear power plant license renewal applications or by the NRC in plant-specific SEISs because these issues have been addressed generically for all nuclear power plants in the 1996 GEIS. Similarly, the 1996 final rule also identified environmental impact issues (i.e., Category 2 issues)

3

that must be addressed in plant-specific reviews by licensees in their environmental reports and by the NRC in the SEISs.

2

A Category 1 issue is one that meets the following criteria: (1) The environmental impacts

associated with the issue have been determined to apply either to all plants or, for some issues, to plants having a specific type of cooling system or other specified plant or site characteristic; (2) a single significance level (i.e., small, moderate, or large) has been assigned to the impacts (except for collective offsite radiological impacts from the fuel cycle and from high-level waste and spent fuel disposal); and (3) mitigation of adverse impacts associated with the issue has been considered in the analysis, and it has been determined that additional plant-specific mitigation measures are not likely to be sufficiently beneficial to warrant implementation.

3

A Category 2 issue is one where one or more of the Category 1 criteria cannot be met, and therefore additional plant-specific review is required.

On December 18, 1996 (61 FR 66537), the NRC amended the final rule published in 1996 to incorporate minor clarifying and conforming changes and to add language omitted from Table B-1 in Appendix B to Subpart A of 10 CFR part 51 (hereafter “Table B-1 in Appendix B to Subpart A of 10 CFR Part 51” is referred to as “Table B-1”).

1999 Final Rule

The NRC amended 10 CFR part 51, including Table B-1, on September 3, 1999 (64 FR 48496). This amendment expanded the generic findings pertaining to the environmental impacts resulting from transportation of fuel and waste to and from a single nuclear power plant. This amendment also incorporated rule language consistent with the 1996 GEIS, which addressed local traffic impacts attributable to the continued operations of a nuclear power plant during the license renewal term.

Current Rulemaking

As stated in the 1996 final rule that incorporated the findings of the GEIS in 10 CFR part 51, the NRC recognized that environmental impact issues might change over time and that additional issues may need to be considered. As further stated in the preamble to Table B-1, the NRC indicated that it intended to review the material in Table B-1 on a 10-year basis.

The NRC began this review on June 3, 2003, by publishing a notice of intent to revise the 1996 GEIS (68 FR 33209). As part of this process and pursuant to 10 CFR 51.29, the NRC conducted scoping and held a series of public meetings (

see

74 FR 38119 for more details). The original public comment period began in June 2003 and closed in September 2003. The project was inactive for the next 2 years due to limited NRC staff resources and competing demands. On October 3, 2005 (70 FR 57628), the NRC reopened the public comment period and extended it until December 30, 2005.

On July 31, 2009 (74 FR 38117), the NRC published the proposed rule, “Revisions to Environmental Review for Renewal of Nuclear Power Plant Operating Licenses,” for public comment in the

Federal Register

. The proposed rule would amend Table B-1 by updating the Commission's 1996 findings on the environmental impacts related to the renewal of nuclear power plant operating licenses and other NRC environmental protection regulations (e.g., 10 CFR 51.53, which sets forth the contents of the applicant's environmental report). Together with the proposed rule, the NRC also published a notice of availability of the draft revised GEIS (ADAMS Accession No. ML090220654); a proposed Revision 1 of Regulatory Guide (RG) 4.2, Supplement 1, “Preparation of Environmental Reports for Nuclear Power Plant License Renewal Applications” (ADAMS Accession No. ML091620409); and a proposed Revision 1 to NUREG-1555, Supplement 1, “Standard Review Plans for Environmental Reviews for Nuclear Power Plants” (ADAMS Accession No. ML090230497), in the

Federal Register

(74 FR 38238). All of the documents requested public comments.

The proposed amendments were based on consideration of (1) Comments received from the public during the public scoping period, (2) a review of comments received on plant-specific SEISs completed since the 1996 GEIS was issued, and (3) lessons learned and knowledge gained from previous and ongoing license renewal environmental reviews. The history of this rulemaking is discussed in more detail in the July 31, 2009 (74 FR 38117), proposed rule. The draft revised GEIS provided the regulatory basis for the July 2009 proposed rule.

The proposed rule provided a 75-day public comment period, which closed on October 14, 2009. The NRC received requests to extend the comment period to provide the public more time to analyze and review the legal, regulatory, and policy issues covered by the proposed rule and supporting documents. On October 7, 2009 (74 FR 51522), the NRC granted the requests, and the public comment period for the proposed rule and the proposed revisions to the GEIS, the regulatory guide, and standard review plan was extended to January 12, 2010.

II. Public Meetings

During the public comment period, the NRC conducted six public meetings to solicit comments on the proposed rule, draft revised GEIS, and related draft guidance documents. The official transcripts, written comments, and meeting summaries for the following public meetings are available electronically for public inspection at the NRC's PDR or online in the NRC Library at

http://www.nrc.gov/reading-rm/adams.html:

(1) September 15, 2009, Atlanta, GA (ADAMS Accession No. ML092810007);

(2) September 17, 2009, Newton, MA (ADAMS Accession No. ML092931681);

(3) September 24, 2009, Oak Brook, IL (ADAMS Accession No. ML092931545);

(4) October 1, 2009, Rockville, MD (ADAMS Accession No. ML092931678);

(5) October 20, 2009, Pismo Beach, CA (ADAMS Accession No. ML093070174); and

(6) October 22, 2009, Dana Point, CA (ADAMS Accession No. ML093100505).

A summary of these meetings is publicly available under ADAMS Accession No. ML093070141.

On June 21, 2011, the NRC conducted another public meeting to discuss final rule implementation in Rockville, MD. No public comments were solicited at this meeting because the public comment period for the proposed rule had closed on January 12, 2010. A summary of this meeting is publicly available in ADAMS under Accession No. ML11182B535.

III. Discussion

1996 GEIS

Under the NRC's environmental protection regulations in 10 CFR part 51, which implements Section 102(2) of NEPA, renewal of a nuclear power plant operating license requires the preparation of an EIS (

see

10 CFR 51.20(b)(2)). The 1996 GEIS summarized the findings of a systematic inquiry into the environmental impacts of continued operations and refurbishment activities associated with license renewal. Of the 92 environmental issues identified and analyzed by the NRC, 69 issues were determined to be generic (i.e., Category 1); 21 were determined to be plant-specific (i.e., Category 2); and two did not fit into either category (i.e., uncategorized). Category 1 issues concern those potential environmental impacts resulting from license renewal that are common or generic to all

nuclear power plants (or for some issues, to plants having a specific type of cooling system or other specified plant or site characteristic). Category 2 issues concern those potential environmental impacts resulting from license renewal that are not common or generic to all nuclear power plants and, as such, require a plant-specific analysis to determine the level of impact. The two uncategorized issues would be addressed by the NRC in each SEIS. Table B-1 summarizes the findings of the environmental impact analyses conducted for the 1996 GEIS and lists each issue and its category level.

Impact levels (small, moderate, or large) were determined for most NEPA issues (e.g., land use, air, water) evaluated in the 1996 GEIS. A small impact means that the environmental effects are not detectable, or are so minor that they would neither destabilize nor noticeably alter any important attribute of the resource. A moderate impact means that the environmental effects are sufficient to alter noticeably, but not destabilize, important attributes of the resource. A large impact means that the environmental effects would be clearly noticeable and would be sufficient to destabilize important attributes of the resource.

The 1996 GEIS has been effective in focusing the NRC's resources on important license renewal environmental impact issues and has increased the efficiency of the environmental review process. Currently, 73 nuclear units at 43 plant sites have received renewed operating licenses.

Revised GEIS

The revised GEIS (Vol. 1, “Main Report,” ADAMS Accession No. ML13106A241; Vol. 2, “Public Comments,” ADAMS Accession No. ML13106A242; and Vol. 3, “Appendices,” ADAMS Accession No. ML13106A244) is both an update and a re-evaluation of the potential environmental impacts arising from the renewal of an operating license for a nuclear power reactor for an additional 20 years. Lessons learned and knowledge gained during previous license renewal environmental reviews provided a significant source of new information for the revised GEIS. In addition, public comments received during previous license renewal environmental reviews were re-examined to validate existing environmental issues and identify new ones. In preparing the revised GEIS, the NRC considered the need to modify, add to, consolidate, or delete any of the 92 environmental issues evaluated in the 1996 GEIS.

In the proposed rule and draft revised GEIS, the NRC carried forward 78 environmental impact issues for detailed consideration. Fifty-eight of these issues were determined to be Category 1. Of the remaining 20 issues, 19 were determined to be Category 2 and one issue, “Electromagnetic fields, chronic effects,” remained uncategorized.

4

These issues were summarized in the July 31, 2009 (74 FR 38117), proposed rule.

4

“Electromagnetic fields, chronic effects” remains an uncategorized issue. Due to the lack of a scientific consensus on the impacts of chronic exposure to electromagnetic fields, the NRC has not categorized this issue and did not perform a plant-specific analysis. Once a scientific consensus is reached, the NRC will categorize the issue for license renewal.

Based on public comments received on the proposed rule and draft revised GEIS, a number of the environmental impact issues identified in the proposed rule were re-evaluated for detailed consideration in the final revised GEIS and are reflected in the changes made by the final rule. These changes are discussed in detail in Section VIII, “Final Actions and Basis for Changes to Table B-1,” of this document and are briefly summarized as follows:

(1) “Air quality during refurbishment (nonattainment and maintenance areas)” issue was changed from a Category 2 to a Category 1 issue and renamed, “Air quality impacts (all plants).”

(2) “Groundwater and soil contamination” issue was changed from a Category 2 to a Category 1 issue and consolidated with the “Groundwater use and quality” issue into a single renamed Category 1 issue, “Groundwater contamination and use (non-cooling system impacts).”

(3) “Thermal impacts on aquatic organisms” issue was changed to remove several Category 1 thermal impacts issues (these Category 1 issues were consolidated together with a Category 2 thermal impact issue in the proposed rule) to create a new separate combined Category 1 issue, “Infrequently reported thermal impacts (all plants),” which also includes the previously separate “Stimulation of aquatic nuisance species (e.g., shipworms),” Category 1 thermal impact issue.

(4) “Impingement and entrainment of aquatic organisms” issue was changed to remove a single impingement and entrainment Category 1 issue (consolidated with other impingement and entrainment issues in the proposed rule) to create a new, separate Category 1 issue, “Entrainment of phytoplankton and zooplankton (all plants).”

In addition to the changes previously discussed, the NRC has made changes to the “Onsite storage of spent nuclear fuel” issue and the “Offsite radiological impacts of spent nuclear fuel and high-level waste disposal” issue as a result of the United States Court of Appeals decision in

New York

v.

NRC,

681 F.3d 471 (D.C. Cir. 2012), which vacated the NRC's 2010 Waste Confidence Decision and Rule (75 FR 81032 and 81037; December 23, 2010). The Category 1 “Onsite storage of spent nuclear fuel” issue was revised to limit the period of time covered by the issue to the license renewal term. Similarly, the NRC revised the Category 1 issue, “Offsite radiological impacts of spent nuclear fuel and high-level waste disposal” by reclassifying the issue from a Category 1 issue with an impact level of small to an uncategorized issue with an impact level of uncertain. Section V of this document, “Related Issues of Importance,” provides further details on the NRC's revisions to these issues in response to the

New York

v.

NRC

decision.

Ultimately, 59 environmental impact issues were determined to be Category 1 and would not require additional plant-specific analysis unless new and significant information is identified during the license renewal environmental review. Of the remaining 19 issues, 17 were determined to be Category 2, one remained uncategorized with respect to determining the impact level (“Chronic effects of electromagnetic fields (EMFs)”), and one was reclassified from Category 1 to uncategorized (“Offsite radiological impacts of spent nuclear fuel and high-level waste disposal”). These 78 issues were evaluated in the revised GEIS and are summarized in the final rule. No environmental issues identified in Table B-1 and evaluated in the 1996 GEIS were eliminated, but certain issues were consolidated or grouped according to similarities.

Environmental issues in the revised GEIS are arranged by resource area. This perspective is a change from the 1996 GEIS in which environmental issues are arranged by power plant systems (e.g., cooling systems, transmission lines) and activities (e.g., refurbishment). The structure of the revised GEIS conforms to the NRC's standard format for EISs found in Appendix A to Subpart A of 10 CFR part 51, “Format for Presentation of Material in Environmental Impact Statements.” The environmental impacts of license renewal activities, including plant operations, maintenance, and

refurbishment activities, along with replacement power alternatives, are addressed in each resource area. The revised GEIS evaluated environmental impact issues under the following resource areas: (1) Land use and visual resources, (2) air quality and noise, (3) geologic environment, (4) water resources (surface water resources and groundwater resources), (5) ecological resources (terrestrial resources, aquatic resources, special status species and habitats), (6) historic and cultural resources, (7) socioeconomics, (8) human health, (9) environmental justice, and (10) waste management and pollution prevention. The final rule revises Table B-1 to follow the organizational format of the revised GEIS.

In the 1996 GEIS, the NRC assumed that licensees would need to conduct major refurbishment activities to ensure the safe and economic operation of nuclear power plants beyond the current license term. Activities included replacement and repair of major components and systems, upgrades, and equipment. Replacement of many systems, structures, and components included steam generators and pressurizers for pressurized water reactors (PWRs) and recirculation piping systems for boiling water reactors (BWRs). It was assumed that many nuclear power plants would also undertake construction projects to replace or improve infrastructure. Such projects could include construction of new parking lots, roads, storage buildings, structures, and other facilities.

Licensee practice since publication of the 1996 GEIS has shown that many refurbishment activities have already taken place (e.g., steam generator and vessel head replacement). Most license renewal applicants have not identified any refurbishment activities associated with license renewal. Therefore, the revised GEIS assumes that impacts from refurbishment activities outside of license renewal have been accounted for in annual site evaluation reports, environmental operating reports, and radiological environmental monitoring program reports. Detailed analyses have not been performed for refurbishment actions in the revised GEIS. Instead, the impacts of typical activities during the license renewal term, including any refurbishment activities, are addressed for each resource area.

Environmental impacts of license renewal and the resources that could be affected are identified in the revised GEIS. The general analytical approach for identifying environmental impacts was to: (1) Describe the nuclear power plant activity that could result in an environmental impact, (2) identify the resource that may be affected, (3) evaluate past license renewal reviews and other available information, (4) assess the nature and magnitude of the environmental impact on the affected resource, (5) characterize the significance of the effects, and (6) determine whether the results of the analysis apply to all nuclear power plants (i.e., whether the impact issue is Category 1 or Category 2).

The revised GEIS, and therefore the final rule, retains the 1996 GEIS definitions of a Category 1 and Category 2 issue. While some Category 2 issues have been changed to Category 1, no Category 1 issue has been changed to Category 2. The final rule makes four major types of changes:

(1)

New Category 1 Issues:

New Category 1 issues are either new Category 1 issues (i.e., not previously evaluated in the 1996 GEIS and listed in Table B-1) or multiple Category 1 issues from the 1996 GEIS (and listed as multiple Category 1 issues in Table B-1 of the current rule) that have been consolidated into a single Category 1 issue in the revised GEIS and in Table B-1. An applicant for license renewal does not need to assess the potential environmental impacts from these issues in its environmental report. However, under 10 CFR 51.53(c)(3)(iv), the applicant is still responsible for reporting in the environmental report any “new and significant information” of which the applicant is aware. If the applicant is not aware of any new and significant information that changes the conclusion in the revised GEIS, the applicant must state this determination in the environmental report. The NRC has addressed the environmental impacts of these Category 1 issues generically for all plants in the revised GEIS.

(2)

New Category 2 Issues:

New Category 2 issues are either new Category 2 issues (i.e., not previously evaluated in the 1996 GEIS and listed in Table B-1) or multiple Category 2 issues from the 1996 GEIS (and listed as multiple Category 2 issues in Table B-1 of the current rule) that have been consolidated into a single Category 2 issue in the revised GEIS and in Table B-1. For each new Category 2 issue, an applicant must conduct a plant-specific assessment of the potential environmental impacts related to that issue and include it in its environmental report. The NRC will then analyze the potential environmental impacts related to that issue in the SEIS.

(3)

Existing Issue Category Changes from Category 2 to Category 1:

These are issues that were determined to be Category 2 in the 1996 GEIS and have been re-evaluated and determined to be Category 1 in the revised GEIS. Table B-1 has been amended by the final rule. An applicant is no longer required to conduct a plant-specific assessment of the environmental impacts associated with these issues in its environmental report. Similarly, the NRC is no longer required to analyze the potential environmental impacts related to that issue in the SEIS. However, consistent with the requirements of 10 CFR 51.53(c)(3)(iv), an applicant is still required to describe in its environmental report any “new and significant information” of which it is aware.

(4) Existing Issue Changes from Category 1 to Uncategorized:

The “Offsite radiological impacts of spent nuclear fuel and high-level waste disposal” issue

5

was determined to be a Category 1 issue in the 1996 GEIS, but given the DC Circuit decision in

New York

v.

NRC,

the NRC reclassified the issue to uncategorized in the revised GEIS. Table B-1 has been amended by the final rule. Because the issue is uncategorized in this final rule, pending further action by the Commission, an applicant is not required to conduct a plant-specific assessment of the environmental impacts associated with this issue in its environmental report.

5

The issue was named “Offsite radiological impacts (spent fuel and high waste disposal)” in the 1996 rule and GEIS.

IV. Response to Public Comments

A. Overview

The public comment period for the proposed rule, draft revised GEIS, and draft guidance documents associated with this rulemaking, ended on January 12, 2010. The NRC received 32 document submissions containing comments from industry stakeholders, representatives of Federal and State agencies, and other interested parties. The NRC also received verbal comments at the six public meetings held during the public comment period. A detailed description of all public comments submitted on the proposed rule, draft revised GEIS, and draft guidance documents, and the NRC's responses to those comments, are contained in separate documents (

see

Section XII, “Availability of Documents,” of this document). The following section summarizes the major issues raised during the public comment period resulting in substantive changes to the rule and other issues raised for which no changes were made to the rule.

B. Summary of Comments Resulting in Substantive Changes to the Rule

Several issues were raised during the public comment period that resulted in substantive changes to the proposed rule, which are briefly discussed in the following paragraphs.

Seismic issues.

Many commenters wanted seismic issues to be included in the rule and pointed out the importance of reassessing seismic conditions in determining the safety of operating nuclear power plants. Industry commenters disagreed and argued that seismology should not be considered as part of the issue of “Impacts of nuclear plants on geology and soils” in the proposed rule because it is an ongoing safety issue that is being addressed at all plants.

NRC Response.

The NRC agrees with the industry commenters that consideration of seismic conditions is an ongoing safety issue. Although seismic conditions at nuclear power plants were generically discussed in the revised GEIS as part of the geologic environment, seismology was not identified as a separate issue in the revised GEIS because the NRC considered historical earthquake data for each nuclear power plant when that plant was first licensed. The NRC requires all licensees to take seismic hazards into account in order to maintain safe operating conditions at all nuclear power plants. When new seismic hazard information becomes available, the NRC evaluates the new data and models to determine if any changes are needed at existing plants. This continuous oversight process, which includes seismic safety, remains separate from license renewal and takes place on an ongoing basis at all licensed nuclear facilities.

Sections 3.4 and 4.4.1 of the revised GEIS explain that geologic and seismic conditions were considered in the original design of nuclear power plants and are part of the license bases for operating plants. Seismic conditions are attributes of the geologic environment that are not affected by continued plant operations and refurbishment and are not expected to change appreciably during the license renewal term for all nuclear power plants. The findings relative to geologic and soil conditions were re-evaluated in the revised GEIS and as such, the issue has been renamed, “Geology and soils,” in Table B-1, and the findings have been revised for clarity.

Air quality impacts.

Several commenters objected to the issue, “Air quality (nonattainment and maintenance areas),” being listed as a Category 2 issue in the proposed rule. These commenters argued that air quality impacts would be small even in worst-case situations, because licensees are required to operate within State air permit requirements.

NRC Response.

The NRC agrees with the commenters. The final rule revises Table B-1 by reclassifying the issue as a Category 1 issue. Operating experience has shown that the potential impact from emergency generators and boilers on air quality would be small for all plants and, given the infrequency and short duration of maintenance testing, would not be an air quality concern even at plants located in or adjacent to nonattainment areas.

In addition, the analysis presented in the revised GEIS has shown that the worst-case emissions from cooling tower drift and particulate emissions at operating plants were also small. Air quality impacts from vehicle, equipment, and fugitive dust emissions associated with refurbishment would also be small for most plants but could be a cause for concern for plants located in or near air quality nonattainment or maintenance areas. However, the impacts are expected to be temporary and would cease once projects were completed. In addition, operating experience has shown that refurbishment activities have not required the large numbers of workers and extended durations conservatively predicted and analyzed in the 1996 GEIS, nor have such activities resulted in exceedances in the

de minimis

thresholds for criteria pollutants in nonattainment and maintenance areas. Consequently, the NRC agrees with these commenters' arguments that air quality impacts would be small for all plants and, therefore, a Category 1 issue.

Groundwater and soil contamination.

Several commenters objected to the new Category 2 issue, “Groundwater and soil contamination,” in the proposed rule and asserted that contamination from industrial practices is addressed by the U.S. Environmental Protection Agency (EPA) and State regulations that monitor and address these impacts. Specifically, the use, storage, disposal, release, and/or cleanup of spilled or leaked solvents, hydrocarbons, and other potentially hazardous materials are governed by the Resource Conservation and Recovery Act (RCRA); Comprehensive Environmental Response, Compensation, and Liability Act; Toxic Substances Control Act; Federal Insecticide, Fungicide, and Rodenticide Act; and the Federal Water Pollution Control Act (also known as the Clean Water Act (CWA)).

NRC Response.

While classified as a Category 2 issue in the proposed rule, further consideration of the “Groundwater and soil contamination” issue and public comments revealed that the potential impacts on groundwater and soil quality from common industrial practices (e.g., the use, handling, storage, and disposal of chemicals, petroleum products, waste, and hazardous material) can be addressed generically because industrial practices employed by nuclear power plants are not unique, but common to all industrial facilities. The NRC concludes that the overall impact of industrial practices on groundwater use and quality from past and current operations is small for all nuclear power plants and not expected to change appreciably during the license renewal term. The NRC agrees with the commenters to the extent that clarification was needed and that common industrial practices that can cause groundwater or soil contamination can be addressed generically as a Category 1 issue.

Further, the final rule combines the reclassified “Groundwater and soil contamination” issue with the Category 1 proposed rule issue, “Groundwater use and quality,” and renames the consolidated Category 1 issue as “Groundwater contamination and use (non-cooling system impacts).” These issues were consolidated because they both consider the impact of industrial activities associated with the continued operations of a nuclear power plant (not directly related to cooling system effects) on groundwater use and quality. Consolidating these issues also conforms to the resource-based approach used in the revised GEIS and serves to facilitate the license renewal environmental review process.

The finding column of Table B-1 for “Impacts of refurbishment on groundwater use and quality” prior to the final rule, as analyzed in the 1996 GEIS, indicated that impacts of continued operations and refurbishment on groundwater use and quality would be small, as extensive dewatering is not anticipated, and the application of best management practices for handling any materials produced or used during activities would reduce impacts. These findings were re-evaluated in the revised GEIS and are retained in the finding column of Table B-1 for the consolidated issue.

This new consolidated issue also considers the impacts on groundwater, soil, and subsoil from the industrial use of solvents, hydrocarbons, heavy metals, or other chemicals at nuclear power plant sites during the license renewal

term, including the impacts resulting from the use of wastewater disposal ponds or lagoons (both lined or unlined). Industrial practices at all nuclear power plants have the potential to contaminate groundwater and soil, especially on sites with unlined wastewater and storm water lagoons. Contaminants have been found in groundwater and soil samples at some nuclear power plants during previous license renewal environmental reviews.

Any groundwater and soil contamination at operating nuclear power plants is subject to characterization and clean-up under EPA- and State-regulated remediation and monitoring programs. In addition, wastewater disposal ponds and lagoons are subject to discharge authorizations under the National Pollutant Discharge Elimination System (NPDES) and related State wastewater discharge permit programs. Each operating nuclear power plant must comply with these EPA and State regulatory requirements. As such, each site has an established program for handling chemicals, waste, and other hazardous materials. Moreover, nuclear power plant licensees are expected to employ best management practices, both in minimizing effluents and in remediation. Thus, this new consolidated issue, as set forth in the final revised GEIS and the final rule, is listed as a Category 1 issue.

C. Summary of Other Comments

Radionuclides in groundwater.

Several commenters expressed opposition to the inclusion of a new Category 2 issue, “Radionuclides released to groundwater,” with an impact estimate of small to moderate in the proposed rule. Some commenters indicated that the issue category should be changed to Category 1; others suggested that the levels of significance should range to large. The argument for changing the issue to Category 1 was based on the voluntary industry-wide initiative, Nuclear Energy Institute (NEI) 07-07, “Industry Ground Water Protection Initiative—Final Guidance Document” (ADAMS Accession No. ML072610036), designed to protect groundwater.

NRC Response.

This new, Category 2 issue evaluates the potential contamination and degradation of groundwater resources resulting from inadvertent discharges of radionuclides into groundwater from nuclear power plants. Within the past several years, there have been numerous events at power reactor sites that involved unknown, uncontrolled, and unmonitored releases of radionuclides into the groundwater. The number of these events and the high level of public controversy have made this an issue that the NRC believes needs a “hard look,” as required by NEPA.

As a voluntary action, NEI 07-07 cannot be enforced by the NRC. As such, no violations can be issued against a licensee who fails to comply with the guidance in NEI 07-07. Furthermore, the NRC cannot rely on a voluntary initiative as a basis to ensure that the nuclear power industry will monitor and have adequate information available for the NRC to determine whether the issue does or does not have an adverse impact on groundwater resources.

Regarding the magnitude of impact, the NRC bases its determination of small to moderate impact on a review of existing plants that have had inadvertent releases of radioactive liquids. Even though the NRC expects impacts for all plants to be within this range, a conclusion of large impact would not be precluded for a future license renewal review based on new and significant information, if the data supports such a conclusion. As reflected in the revised final GEIS and the final rule, “Radionuclides released to groundwater,” remains a Category 2 issue.

Radiation exposures to the public.

Several commenters identified recent studies that claim an association between cancer risk and proximity to nuclear power facilities.

NRC Response.

The NRC's regulatory limits for radiological protection are set to protect workers and the public from the harmful health effects (i.e., cancer and other biological impacts) of radiation to humans. The limits are based on the recommendations of scientific standards-setting organizations. These radiation standards reflect extensive scientific study by national and international organizations. The NRC actively participates in and monitors the work of these organizations to remain current on the latest trends in radiation protection. If the NRC determines that there is a need to revise its radiation protection regulations, it will initiate a separate rulemaking. The models recognized by the NRC for use by licensees to calculate dose incorporate conservative assumptions to ensure that workers and members of the public are adequately protected from radiation.

On April 7, 2010, the NRC announced that it asked the National Academy of Sciences (NAS) to perform a state-of-the-art study on cancer risk for populations surrounding nuclear power facilities (ADAMS Accession No. ML100970142). The NAS has a broad range of medical and scientific experts who can provide the best available analysis of the complex issues involved in discussing cancer risk and commercial nuclear power plants. The NAS is a nongovernmental organization chartered by the U.S. Congress to advise the nation on issues of science, technology, and medicine. Through the National Research Council and Institute of Medicine, it carries out studies independently of the Government, using processes designed to promote transparency, objectivity, and technical rigor. More information on its methods for performing studies is available at

http://www.nationalacademies.org/studycommitteprocess.pdf.

The NAS study will update the 1990 U.S. National Institutes of Health National Cancer Institute (NCI) report, “Cancer in Populations Living Near Nuclear Facilities” (NCI 1990), which concluded there was no evidence that nuclear facilities may be linked causally with excess death from leukemia or from other cancers in populations living nearby.

6

The study's objectives are to: (1) Evaluate whether cancer risk is different for populations living near nuclear power facilities, (2) include cancer occurrence, (3) develop an approach to assess cancer risk in geographic areas that are smaller than the county level, and (4) evaluate the study results in the context of offsite doses from normal reactor operations. The study began in the summer of 2010 and is expected to be completed within 4 years. The final revised GEIS has added a discussion on the NRC's sponsorship of this follow-up to the 1990 NCI study.

6

More information on this report is available at

http://www.cancer.gov/cancertopics/factsheet/Risk/nuclear-facilities

.

Onsite storage of spent nuclear fuel, waste disposal, and Yucca Mountain.

Several commenters expressed concern about the increasing volume of spent nuclear fuel at existing power plant sites and the availability of a geological repository at Yucca Mountain for future waste disposal.

NRC Response.

The Commission is aware that geologic disposal, at Yucca Mountain or elsewhere, may not be available in the timeframe that was originally envisioned. As an alternative, the Commission has considered the storage of spent nuclear fuel on reactor sites where it is generated. The impacts associated with onsite storage of spent nuclear fuel at nuclear power plant sites during the license renewal term are discussed in Section 4.11.1.2 of the revised GEIS. The impacts associated with offsite radiological impacts from

spent nuclear fuel and high-level waste disposal are discussed in Section 4.11.1.3 of the revised GEIS. In light of the DC Circuit's decision in

New York

v.

NRC,

681 F.3d 471, the NRC has revised two Table B-1 issues, “Onsite storage of spent nuclear fuel” and “Offsite radiological impacts of spent nuclear fuel and high-level waste disposal.” Section V of this document, “Related Issues of Importance,” provides a discussion of the NRC's revisions to these two issues, as well as the actions the NRC has taken or will take in response to the

New York

v.

NRC

decision.

Postulated accidents.

Numerous comments were received on the NRC's evaluation and classification of postulated accidents in the draft revised GEIS. One commenter disagreed with the GEIS' conclusion that environmental impact from design basis accidents (DBAs) is small. Also, several commenters disagreed with the GEIS conclusion that the environmental impact from severe accidents is small and further, that the evaluation is not adequate because of its use of probability-weighted risk assessments. Their position is that for severe accidents, the revised GEIS should also evaluate the consequences of reactor accidents and expand the evaluation to include spent fuel pool accidents and accidents due to age-related plant component degradation. In addition, some of the commenters stated that the NRC has gained enough information from the many plant licenses it has renewed to make a determination, on a generic basis, that the “severe accidents” issue should be reclassified as Category 1.

NRC Response.

Design Basis Accidents.

The NRC does not agree that the GEIS' evaluation of DBAs is incorrect. The NRC evaluates and presents the potential consequences of DBAs in nuclear power plant licensing documents and considers them in the GEIS for license renewal.

In order to receive NRC approval for an initial operating license, an applicant must submit a final safety analysis report (FSAR) as part of its application. The FSAR presents the applicable design criteria and design information for the proposed reactor, as well as comprehensive data on the proposed site. The FSAR also discusses hypothetical reactor accident situations and addresses the safety features that prevent and mitigate those accidents. During the initial licensing process for a power reactor, the NRC reviews the FSAR to determine whether or not the plant design meets the NRC's regulations.

At initial licensing, the NRC also considered the environmental impact of DBAs at each operating nuclear power plant. The DBAs are those events that both the applicant and the NRC evaluate to ensure that the plant can withstand normal and abnormal transients (e.g., rapid changes in reactor power) without undue risk to the health and safety of the public. Although the NRC does not expect that all of these postulated events will occur during the life of the plant, the NRC evaluates them to establish the basis for the preventive and mitigative safety systems of the facility. The acceptance criteria for DBAs are described in 10 CFR part 50, “Domestic Licensing of Production and Utilization Facilities,” and 10 CFR part 100, “Reactor Site Criteria.” Compliance with these regulations provides reasonable assurance of adequate protection of public health and safety.

During operations, the NRC requires each power plant licensee to maintain acceptable design and performance criteria in accordance with the NRC's regulations, including during any license renewal period. Therefore, the calculated releases from DBAs will remain within the NRC's regulatory limits.

The 1996 GEIS, in Section 5.2, discusses the impacts of potential accidents. It contains a discussion of plant accidents and consequences. This discussion addresses general characteristics of design basis (and severe) accidents, characteristics of fission products, meteorological considerations, possible exposure pathways, potential adverse health effects, avoiding adverse health effects, accident experience and observed impacts, and emergency preparedness. The revised GEIS reexamined the information from the 1996 GEIS and concluded that it is still valid. Because the information on DBAs is valid and has not changed, the revised GEIS does not repeat the information from the 1996 GEIS.

Severe Accidents.

The NRC does not agree with the comments that the revised GEIS evaluation is inadequate regarding the impacts from severe accidents because it uses probability-weighted risk assessments. Severe accidents (i.e., beyond design basis accidents) are those that could result in substantial damage to the reactor core, whether or not there are serious off-site consequences. The 1996 GEIS estimated and considered the potential impacts on human health and economic factors from full-power severe reactor accidents initiated by internal events at different types of nuclear facilities located in different types of settings. That evaluation included modeling the release of radioactive materials into the environment and modeling the pathways (i.e., exposure to the radioactive plume, inhalation of radioactivity, consumption of contaminated food) through which members of the public could potentially be exposed to doses of radiation. Based on the calculated doses, the GEIS reported the consequences (i.e., potential early and latent fatalities) from such accidents. In developing a potential impact level, however, the NRC took into account the very low probability of such events, as well as their potential consequences, and concluded that the likely impact from individual nuclear power plants is small.

In the revised GEIS, the NRC expanded the scope of the severe accident evaluations and used more recent technical information that included both internal and external event core-damage frequency, as well as improved severe accident source terms, spent fuel pool accidents, low power and reactor shutdown events, new radiation risk-coefficients from the National Academy of Sciences, “Health Risks from Exposure to Low Levels of Ionizing Radiation: Biological Effects of Ionizing Radiation (BEIR) VII” report,

7

and risk impacts of reactor power uprates and higher fuel burn-up levels. As a result, the revised GEIS considers updated information in determining the potential consequences of a reactor accident. Considering this updated information and that severe reactor accidents remain unlikely, the revised GEIS concludes that the environmental impacts of a severe accident remain small.

7

The BEIR VII report can be accessed at

http://search.nap.edu/napsearch.php?term=beir+vii.

The NRC staff reviewed this report in SECY-05-0202, “Staff Review of the National Academies Study of the Health Risks from Exposure to Low Levels of Ionizing Radiation (BEIR VII),” dated October 29, 2005 (ADAMS Accession No. ML052640532).

The NRC notes, however, that the GEIS is not the primary vehicle the NRC uses to address and regulate risks from severe accidents. The NRC's regulations and regulatory practices employ safety standards in the design, construction, and operation of nuclear power plants as well as risk models to ensure the public is adequately protected on an on-going basis. The NRC's ongoing oversight addresses the public's risk from nuclear power plant accidents, accounts for the effects of proposed changes that may be made as part of power plant operations, and considers new information about the facility or its environment when necessary.

Although the NRC has determined that impacts from severe accidents are small for all facilities, the NRC continues to maintain that severe accidents cannot be a Category 1 issue because plant-specific mitigation measures vary greatly based on plant designs, safety systems, fuel type, operating procedures, local environment, population, and siting characteristics. Thus, severe accidents remain a Category 2 issue. Accordingly, the NRC has not changed the requirements in 10 CFR 51.53(c)(3)(ii)(L) that an applicant's environmental report must contain a discussion that considers alternatives to mitigate severe accidents if the NRC has not previously considered this issue in an environmental impact statement or environmental assessment for the facility.

Spent Fuel Pool Accidents.

The 1996 GEIS included a quantitative analysis of a severe accident involving a reactor operating at full power. A qualitative evaluation of SFP accidents is presented in Appendix E of the revised GEIS. Based on this evaluation, the revised GEIS concludes that the environmental impacts from accidents involving SFPs are comparable to those from the reactor accidents at full power that were evaluated in the 1996 GEIS and as such, SFP accidents do not warrant separate evaluation. Based on the continued validity of conclusions from the 1996 GEIS, as affirmed by the Commission (

see

following paragraph), the revised GEIS does not contain a quantitative evaluation of SFP accidents.

The issue of an accident involving the spent fuel pool was specifically addressed by the NRC in its denial of two petitions for rulemaking (PRM): PRM-51-10 and PRM-51-12, submitted by the Attorney General of the Commonwealth of Massachusetts in 2006 and the Attorney General of California in 2007, respectively.

8

The petitioners requested that the NRC initiate a rulemaking concerning the environmental impacts of the high density storage of spent nuclear fuel in SFPs. The petitioners asserted that “new and significant information” shows that the NRC incorrectly characterized the environmental impacts of high-density spent fuel storage as “insignificant” in the 1996 GEIS for the renewal of nuclear power plant licenses. Specifically, the petitioners asserted that spent fuel stored in high-density SFPs is more vulnerable to a zirconium fire than the NRC concluded in its NEPA analysis. The NRC denied the two petitions, and the NRC denial was upheld by the United States Court of Appeals.

8

These PRMs were denied in the same

Federal Register

notice (73 FR 46204; August 8, 2008).

Aging-related Degradation.

Issues related to age-related plant component degradation are addressed in the NRC's safety evaluation of the plant's license renewal application. The regulations covering the safety review for license renewal are in 10 CFR part 54, “Requirements for Renewal of Operating Licenses for Nuclear Power Plants.”

The 1996 GEIS discusses the potential effects of age on the physical plant and notes that such deterioration could result in an increased likelihood of component or structure failure that could increase the rate of plant accidents. The GEIS notes that the NRC requires an applicant for license renewal to address the issue of age-related degradation by identifying, in an integrated plant assessment process, those passive, long-lived structures and components that are susceptible to age-related degradation and whose functions are necessary to ensure that the facility's current licensing basis is maintained. The GEIS found that the safety evaluation performed by the NRC as part of the license renewal process provides reasonable assurance that age-related degradation is managed and adequate protection of the health and safety of the public is maintained during the license renewal period. Therefore, the 1996 GEIS concluded, “. . . the probability of any radioactive releases from accidents will not increase over the license renewal period.” Based on nuclear power plants' continued compliance with 10 CFR part 54 to manage age-related degradation, the revised GEIS did not alter or revise this conclusion from the 1996 GEIS.

Greenhouse gas emissions and climate change.

Several commenters discussed the need to include a discussion of the effects of climate change on plant operations and the effect of continued operations during the license renewal period on environmental resources affected by climate change.

NRC Response.

The NRC acknowledges these concerns. The NRC has begun to evaluate the effects of greenhouse gas (GHG) emissions and its implications for global climate change in its environmental reviews for both new reactor and license renewal applications. Changes in climate have the potential to affect air and water resources, ecological resources, and human health, and should be taken into account when evaluating cumulative impacts over the license renewal term.

Subsequent to the publication of the proposed rule and during the public comment period, the Commission issued a memorandum and order concerning two combined operating license applications for new reactor units at the Tennessee Valley Authority Bellefonte site in Alabama and the Duke Energy Carolinas Lee site in South Carolina (CLI-09-21). The memorandum and order stated:

because the Staff is currently addressing the emerging issues surrounding greenhouse gas emissions in environmental reviews required for the licensing of nuclear facilities, we believe it is prudent to provide the following guidance to the Staff. We expect the Staff to include consideration of carbon dioxide and other greenhouse gas emissions in its environmental reviews for major licensing actions under the National Environmental Policy Act. The Staff's analysis for reactor applications should encompass emissions from the uranium fuel cycle as well as from construction and operation of the facility to be licensed. The Staff should ensure that these issues are addressed consistently in agency NEPA evaluations and, as appropriate, update Staff guidance documents to address greenhouse gas emissions.

9

9

In the matter of Duke Energy Carolinas, LLC (Combined License Application for William States Lee III Nuclear Station, Units 1 and 2); In the matter of Tennessee Valley Authority (Bellefonte Nuclear Power Plant, Units 3 and 4), CLI-09-21 (NRC November 3, 2009).

Presently, insufficient data exists to support an impact level on a generic basis. The NRC only has direct emission data for a handful of facilities. Although some states have varying reporting requirements, GHG emissions reporting nationwide is in its infancy. The EPA promulgated its GHG emissions reporting rule on October 30, 2009 (74 FR 56260). In accordance with this rule, the first industry reporting date was March 31, 2011.

10

Moreover, the 25,000 annual metric ton reporting threshold EPA established in the final rule of October 30, 2009, is not an indication of what EPA considers to be a significant (or insignificant) level of GHG emissions on a scientific basis, but a threshold chosen by EPA for policy evaluation purposes.

11

10

74 FR at 56267: October 30, 2009, codified at 40 CFR 98.3(b) (“The annual GHG report must be submitted no later than March 31 of each calendar year for GHG emissions in the previous calendar year”).

11

The EPA concluded for policy evaluation purposes, that the 25,000 metric ton threshold more effectively targets large industrial emitters and suppliers, covers approximately 85 percent of the U.S. emissions, and minimizes the burden on smaller facilities (74 FR 56264; October 30, 2009).

In order to comply with the Commission's direction in CLI-09-21 and in response to the comments received, a new section, “Greenhouse Gas Emissions and Climate Change” (Chapter 4, Section 4.12.3), summarizing the potential cumulative

impacts of GHG emissions and global climate change, has been added to the final revised GEIS. The NRC will also include within each SEIS a plant-specific analysis of any impacts caused by GHG emissions over the course of the license renewal term as well as any impacts caused by potential climate change upon the affected resources during the license renewal term. The final rule was not revised to include any reference to GHG emissions or climate change.

Recent advances in alternative energy technologies.

Several commenters asserted that much of the information describing alternative energy technologies did not reflect the state-of-the-science. In some cases, commenters noted facts and events that occurred after the publication date of the draft revised GEIS.

NRC Response.

The NRC has updated the final revised GEIS to incorporate the latest information on replacement power alternatives, but it is inevitable that rapidly evolving technologies will outpace the information presented in the final revised GEIS. Incorporation of this information is more appropriately made in the context of plant-specific license renewal reviews, rather than in the evaluations contained in the revised GEIS. As with renewable energy technologies, energy policies are evolving rapidly. While the NRC acknowledges that legislation, technological advancements, and public policy can underlie a fundamental paradigm shift in energy portfolios, the NRC cannot make decisions based on anticipated or speculative changes. Instead, the NRC considers the status of replacement power alternatives and energy policies when conducting plant-specific reviews. The final revised GEIS has been updated to clarify the NRC's approach to conducting replacement power alternative evaluations.

Emergency preparedness and security.

Several commenters expressed concern with emergency preparedness, evacuation, and safety and security at nuclear power plants. Commenters stated that these topics were not addressed in the proposed rule and not adequately covered in the revised GEIS and should be included in the scope of the plant-specific SEISs.

NRC Response.

Emergency preparedness and planning are part of the current licensing basis for each holder of a 10 CFR part 50 operating license and are outside the regulatory scope of license renewal. Before a plant is licensed to operate, the NRC must have “reasonable assurance that adequate protective measures can and will be taken in the event of a radiological emergency” (10 CFR 50.47). The Commission's regulatory scheme provides continuing assurance that emergency planning for every operating nuclear power plant is adequate. The Commission has determined that there is no need for a special review of emergency planning issues in the context of an environmental review for license renewal because the ongoing decisions and findings concerning emergency preparedness at nuclear power plants address concerns as they arise.

The Commission considered the need for a review of emergency planning issues in the context of license renewal during its rulemaking proceedings on 10 CFR part 54, which included public notice and comment. As discussed in the Statement of Considerations for the 10 CFR part 54 rulemaking (56 FR 64966; December 13, 1991), the programs for emergency preparedness at nuclear power facilities apply to all nuclear power facility licensees and require the specified levels of protection from each licensee regardless of plant design, construction, or license date. The NRC requirements related to emergency planning are in the regulations at 10 CFR 50.47 and Appendix E to 10 CFR part 50, “Emergency Planning and Preparedness for Production and Utilization Facilities.” These requirements apply to all holders of operating licenses and will continue to apply to facilities with renewed licenses. Through its standards and required exercises, the Commission reviews existing emergency preparedness plans throughout the life of any facility, keeping up with changing demographics and other site-related factors.

Further, the NRC actively reviews its regulatory framework to ensure that the regulations are current and effective. The agency began a major review of its emergency preparedness framework in 2005, including a comprehensive review of the emergency preparedness regulations and guidance, the issuance of generic communications regarding the integration of emergency preparedness and security, and outreach efforts to interested persons to discuss emergency preparedness issues. These activities informed a rulemaking effort to enhance the NRC's emergency preparedness regulations and guidance. This effort culminated in a final rule, which was published in the

Federal Register

on November 23, 2011 (76 FR 72560).

Security issues are not tied to a license renewal action but are treated on an ongoing basis as a part of the current (and renewed) operating license. If issues related to security are discovered at a nuclear power plant, they are addressed immediately, and any necessary changes are reviewed and incorporated under the current operating license. For example, after the terrorist attacks of September 11, 2001, the NRC issued security-related orders and guidance to nuclear power plant licensees. These orders and guidance included interim measures for emergency planning. Nuclear industry groups and Federal, State, and local government agencies assisted in the prompt implementation of these measures and participated in drills and exercises to test these new planning elements. The NRC reviewed licensees' commitments to address these requirements and verified their implementation through inspections to ensure public health and safety.

In summary, the issue of security is not unique to nuclear power plants requesting license renewal. The NRC routinely assesses threats and other information provided by other Federal agencies and sources. The NRC also ensures that licensees meet their security requirements through its ongoing regulatory process (routine inspections) as a current and generic regulatory issue that affects all nuclear power plants. Therefore, as discussed in the Statement of Considerations for the 10 CFR part 54 rulemaking (56 FR 64966), the Commission determined that there is no need for an evaluation of security issues in the context of a license renewal review.

V. Related Issues of Importance

This section addresses five issues of related importance to the final rule: (1) Consideration of the recent events at the Fukushima Dai-ichi Nuclear Power Plant, (2) removal of those parts of the final rule that refer to and rely upon the NRC's Waste Confidence Decision and Rule, (3) a description of the final rule's effective and compliance dates, (4) clarification of the term “best management practices,” and (5) deletion of the proposed definition of the term “historic properties.”

A. Fukushima Events

On March 11, 2011, a massive earthquake off the east coast of Honshu, Japan produced a devastating tsunami that struck the coastal town of Fukushima. The six-unit Fukushima Dai-ichi Nuclear Power Plant was directly impacted by these events. The resulting damage caused the failure of several of the units' safety systems needed to maintain cooling water flow to the reactors. As a result of the loss of cooling, the fuel overheated, and there

was a partial meltdown of the fuel contained in several of the reactors. Damage to the systems and structures containing reactor fuel resulted in the release of radioactive material to the surrounding environment.

In response to the earthquake, tsunami, and resulting reactor accidents at the Fukushima Dai-ichi Nuclear Power Plant (hereafter referred to as the “Fukushima events”), the Commission directed the NRC staff to convene an agency task force of senior leaders and experts to conduct a methodical and systematic review of the relevant NRC regulatory requirements, programs, and processes, including their implementation, and to recommend whether the agency should make near-term improvements to its regulatory system. As part of the short-term review, the task force concluded that, while improvements are expected to be made as a result of the lessons learned from the Fukushima events, the continued operation of nuclear power plants and licensing activities for new plants do not pose an imminent risk to public health and safety.

12

12

Recommendations for Enhancing Reactor Safety in the 21st Century, The Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident” (July 12, 2011) (ADAMS Accession No. ML111861807).

During the time that the task force was conducting its review, groups of individuals and non-governmental organizations petitioned the Commission to suspend all licensing decisions in order to conduct a separate, generic NEPA analysis to determine whether the Fukushima events constituted “new and significant information” under NEPA that must be analyzed as part of environmental reviews. The Commission found the request premature and noted, “[i]n short, we do not know today the full implications of the [Fukushima] events for U.S. facilities.”

13

However, the Commission found that if “new and significant information comes to light that requires consideration as part of the ongoing preparation of application-specific NEPA documents, the agency will assess the significance of that information, as appropriate.”

14

The Federal courts of appeal and the Commission have interpreted NEPA such that an EIS must be updated to include new information only when that new information provides “a seriously different picture of the environmental impact of the proposed project from what was previously envisioned.”

15

13

Union Electric Co. d/b/a Ameren Missouri

(Callaway Plant, Unit 2), CLI-11-05, _ NRC _, _ (slip op. at 30) (Sept. 9, 2011).

14

Id.

at 30-31.

15

Id.

at 31 (quoting

Hydro Resources, Inc.

(2929 Coors Road, Suite 101, Albuquerque, NM 87120), CLI-99-22, 50 NRC 3, 14 (1999) (citing

Marsh

v.

Oregon Natural Resources Council,

490 U.S. 360, 373 (1989))). The Commission also noted that it can modify a facility's operating license outside of a renewal proceeding and made clear that “it will use the information from these activities to impose any requirement it deems necessary, irrespective of whether a plant is applying for or has been granted a renewed operating license.”

Id.

at 26-27.

In the context of the revised GEIS and this rulemaking, the Fukushima events are considered a severe accident (i.e., a type of accident that may challenge a plant's safety systems at a level much higher than expected) and more specifically, a severe accident initiated by an event external to the plant. The 1996 GEIS concluded that risks from severe accidents initiated by external events (such as an earthquake) could have potentially high consequences but found that external events are adequately addressed through a consideration of a severe accident initiated by an internal event (such as a loss of cooling water). Therefore, an applicant for license renewal need only analyze the environmental impacts from an internal event in order to adequately characterize the environmental impacts from either type of event. The revised GEIS examined more recent and up-to-date information regarding external events and concluded that the analysis in the 1996 GEIS remains valid. The Fukushima events are not considered in the revised GEIS because the analysis in the revised GEIS was completed prior to the Fukushima events.

The NRC's evaluation of the consequences of the Fukushima events is ongoing. As such, the NRC will continue to evaluate the need to make improvements to existing regulatory requirements based on the task force report and additional studies and analyses of the Fukushima events as more information is learned. To the extent that any revisions are made to the NRC's regulatory requirements, they would be made applicable to nuclear power reactors regardless of whether or not they have a renewed license. Therefore, no additional analyses have been performed in the revised GEIS as a result of the Fukushima events. In the event that the NRC identifies information from the Fukushima events that constitutes new and significant information with respect to the environmental impacts of license renewal, the NRC will discuss that information in its site-specific SEISs to the GEIS, as it does with all such new and significant information.

B. Removal of References to the Waste Confidence Decision and Rule

The Waste Confidence Decision and Rule represented the Commission's generic determination that spent nuclear fuel can continue to be stored safely and without significant environmental impacts for a period of time after the end of the licensed life for operation of a nuclear power plant.

16

This generic determination meant that the NRC did not need to consider the storage of spent nuclear fuel after the end of a reactor's licensed life for operation in the NEPA documents that support its reactor and spent-fuel storage license application reviews.

16

The NRC first adopted the Waste Confidence Decision and Rule in 1984. The NRC amended the decision and rule in 1990, reviewed them in 1999, and amended them again in 2010. 49 FR 34694 (August 31, 1984); 55 FR 38474 (September 18, 1990); 64 FR 68005 (December 6, 1999); and 75 FR 81032 and 81037 (December 23, 2010). The NRC made a minor amendment to the rule in 2007 to clarify that it applies to combined licenses. 72 FR 49509 (August 28, 2007). The Waste Confidence Decision and Rule are codified in the NRC regulation 10 CFR 51.23.

On December 23, 2010, the Commission published a revision of the Waste Confidence Decision and Rule to reflect information gained from experience in the storage of spent nuclear fuel and the increased uncertainty in the siting and construction of a permanent geologic repository for the disposal of spent nuclear fuel and high-level waste.

17

In response to the 2010 Waste Confidence Decision and Rule, the states of New York, New Jersey, Connecticut, and Vermont, along with several other parties, challenged the Commission's NEPA analysis in the decision, which provided the regulatory basis for the rule. On June 8, 2012, the United States Court of Appeals, District of Columbia Circuit, in

New York

v.

NRC,

681 F.3d 471 (D.C. Cir. 2012), vacated the NRC's Waste Confidence Decision and Rule, after finding that it did not comply with NEPA.

17

75 FR 81032 and 81037.

The court concluded that the Waste Confidence Decision and Rule is a major federal action necessitating either an EIS or an environmental assessment that results in a “finding of no significant impact.” In vacating the 2010 decision and rule, the court identified three specific deficiencies in the analysis:

1. As to the Commission's conclusion that permanent disposal will be available “when necessary,” the court held that the Commission did not evaluate the environmental effects of failing to secure permanent disposal;

2. As to the storage of spent fuel on-site at nuclear plants after the expiration

of a plant's operating license, the court concluded that the Commission failed to properly examine the risk of spent fuel pool leaks in a forward-looking fashion; and

3. Also related to the post-license storage of spent fuel, the court concluded that the Commission failed to properly examine the consequences of spent fuel pool fires.

In response to the court's ruling, the Commission issued CLI-12-16 on August 7, 2012 (ADAMS Accession No. ML12220A212), in which the Commission determined that it would not issue licenses that rely upon the Waste Confidence Decision and Rule until the issues identified in the court's decision are appropriately addressed by the Commission. CLI-12-16 provided, however, that the decision not to issue licenses only applied to final license issuance; all licensing reviews and proceedings should continue to move forward. In SRM-COMSECY-12-0016, “Approach for Addressing Policy Issues Resulting from Court Decision to Vacate Waste Confidence Decision and Rule,” dated September 6, 2012 (ADAMS Accession No. 12250A032), the Commission directed the NRC staff to proceed with a rulemaking that includes the development of a generic EIS to support a revised Waste Confidence Decision and Rule and to publish both the EIS and the revised decision and rule in the

Federal Register

within 24 months. The Commission indicated that both the EIS and the revised Waste Confidence Decision and Rule should build on the information already documented in various NRC studies and reports, including the existing environmental assessment that the NRC developed as part of the 2010 Waste Confidence Decision and Rule. The Commission directed that any additional analyses should focus on the three deficiencies identified in the court's decision. The Commission also directed that the NRC staff provide ample opportunity for public comment on both the draft EIS and the proposed Waste Confidence Decision and Rule.

In accordance with CLI-12-16, the NRC will not approve any site-specific license renewal applications until the deficiencies identified in the court's decision have been resolved. Two Table B-1 license renewal issues that rely, wholly or in part, upon the Waste Confidence Decision and Rule are the “Onsite storage of spent nuclear fuel” and “Offsite radiological impacts of spent nuclear fuel and high-level waste disposal.” Both of these issues were classified as Category 1 in the 10 CFR part 51 rule that was promulgated in 1996; the 2009 proposed rule continued the Category 1 classification for both of these issues. As part of the NRC's response to the

New York

v.

NRC

decision, this final rule revises these two issues accordingly. Specifically, this final rule revises the Category 1 “Onsite storage of spent nuclear fuel” issue to narrow the period of onsite storage to the license renewal term. In both the 1996 rule

18

and the 2009 proposed rule, the NRC relied upon the Waste Confidence Decision and Rule to make a generic finding that spent nuclear fuel could be stored safely onsite with no more than a small environmental impact for the term of the extended license (from approval of the license renewal application to the expiration of the operating license) plus a 30-year period following the permanent shutdown of the power reactor and expiration of the operating license.

19

18

The issue was named “On-site spent fuel” in the 1996 rule.

19

Prior to the December 23, 2010, final rule, 10 CFR 51.23(a) read: “The Commission has made a generic determination that, if necessary, spent fuel generated in any reactor can be stored safely and without significant environmental impacts for at least 30 years beyond the licensed life for operation (which may include the term of a revised or renewed license) of that reactor at its spent fuel storage basin or at either onsite or offsite independent spent fuel storage installations.”

The Waste Confidence Decision and Rule provided the basis for the 30-year period following the permanent shutdown of the reactor and expiration of the operating license. The 2010 Waste Confidence Decision and Rule extended this post-reactor shutdown onsite storage period from 30 years to 60 years. Given the

New York

v.

NRC

decision, and pending the issuance of a generic EIS and revised Waste Confidence Decision and Rule (as directed by SRM-COMSECY-12-0016), the final rule excludes from this issue the period of onsite storage of spent nuclear fuel following the permanent shutdown of the power reactor and expiration of the operating license. As revised by this final rule, this issue now covers the onsite storage of spent fuel for the term of the extended license only.

Similarly, this final rule revises the Category 1 issue “Offsite radiological impacts of spent nuclear fuel and high level waste disposal.”

20

In both the 1996 rule and the 2009 proposed rule, this issue pertained to the long-term disposal of spent nuclear fuel and high-level waste, including possible disposal in a deep geologic repository. Although the Waste Confidence Decision and Rule did not assess the impacts associated with disposal of spent nuclear fuel and high-level waste in a repository, it did reflect the Commission's confidence, at the time, in the technical feasibility of a repository and when that repository could have been expected to become available. Without the analysis in the Waste Confidence Decision, the NRC cannot assess how long the spent fuel will need to be stored onsite. Therefore, the final rule reclassifies this issue from a Category 1 issue with no assigned impact level to an uncategorized issue with an impact level of uncertain.

20

The issue was named “Offsite radiological impacts (spent fuel and high level waste disposal)” in the 1996 rule.

Upon issuance of the generic EIS and revised Waste Confidence Rule, the NRC will make any necessary conforming amendments to this rule. As referenced previously, the Commission will not approve any license renewal application for an operating nuclear power plant until the issues identified in the court's decision are appropriately addressed by the Commission.

C. Effective and Compliance Dates for Final Rule

The amendments made by the final rule shall be effective 30 days after the final rule's publication in the

Federal Register

. License renewal applicants are not required to comply with the amended rule until 1 year after the final rule's publication in the

Federal Register

. The Commission has decided on a 1-year compliance date given the long lead time required for preparation of license renewal applicant environmental reports.

D. Best Management Practices

“Best management practices” is a term used to describe a type, method, or treatment technique for preventing pollution or reducing the quantities of pollutants released to the environment. The term, as used herein, includes the physical components used to control or minimize pollution (e.g., filters, barriers, mechanical devices, and retention ponds), as well as operational or procedural practices (e.g., minimizing use of a pollutant, spill control, and operator training). Best management practices are used in a variety of industrial sectors. In the nuclear power reactor sector, as in other industrial sectors, best management practices offer flexibility to achieve a balance between protecting the environment and the efficiency and economic limitations associated with the operations of a given plant. Both in the 1996 GEIS and in the revised GEIS, several issues have been determined to be a Category 1 issue with an impact level of small based upon the assumption that the license renewal applicant employs and will continue to employ best management practices

during the license renewal term. The NRC's regulatory experience has shown that licensees employ such best management practices.

The NRC's jurisdiction is limited to radiological health and safety and common defense and security. Therefore, the NRC does not generally impose a requirement that its licensees adopt those best management practices that concern non-radiological pollutants. The NRC nuclear power plant licensees, however, are subject to a host of regulatory requirements that are monitored and enforced by other Federal agencies (e.g., the EPA) or State or local regulatory agencies. The NRC-licensed nuclear power plants must obtain a variety of permits from these other agencies before they can operate (e.g., under the CWA, a licensee must obtain a NPDES permit from the EPA or, if the EPA has delegated its CWA authority to a particular State, from the appropriate agency of that State). These permits typically require that the licensee adopt and adhere to best management practices.

Therefore, an assumption underlying the revised GEIS is that NRC licensees will use best management practices to comply with other Federal, State, and local government requirements to prevent or reduce the quantities of non-radiological pollutants released to the environment. This description of best management practices is not a regulatory or policy change by the NRC because the use of best management practices by nuclear power plant licensees was also an underlying assumption of the 1996 GEIS. Rather, the NRC seeks to make transparent its basis for determining that certain issues are Category 1 issues with a small level of impact.

E. Definition of “Historic Properties”

The proposed rule would have amended 10 CFR part 51 by adding a definition of the term “historic properties” to 10 CFR 51.14(a). Upon further consideration, the NRC determined that adding the definition was unnecessary. The NRC's license renewal determination to renew or not renew a nuclear power plant operating license is considered an undertaking as defined by Section 106 of the National Historic Preservation Act (NHPA) and its implementing regulations in 36 CFR part 800. The regulations define the term “historic property” in 36 CFR 800.16(l)(1). The NRC uses the term “historic property” or “historic properties” in the same context as set forth in 36 CFR 800.16(l)(1).

VI. Revisions to 10 CFR 51.53

The final rule revises 10 CFR 51.53 to conform to those changes made by the final rule to Table B-1. Because some Category 2 issues have been reclassified as Category 1 issues, license renewal applicants no longer need to assess these issues and, therefore, the final rule removes the requirements for applicants to provide information on these issues in their environmental reports. The final rule also adds new requirements to 10 CFR 51.53 for the new Category 2 issues for which applicants are now required to provide information in their environmental reports. The following describes each revision.

A. Reclassifying Category 2 Issues as Category 1 Issues

Section 51.53(c)(3)(ii)(F).

The final rule removes and reserves 10 CFR 51.53(c)(3)(ii)(F) because the final rule reclassifies the Category 2 issue, “Air quality during refurbishment (nonattainment and maintenance areas),” to Category 1 and renames the issue, “Air quality impacts (all plants).” The removed regulatory language required the applicant to assess anticipated vehicle exhaust emissions at the time of refurbishment for plants located in or near a nonattainment or maintenance area, as those terms are defined under the Clean Air Act.

The final rule reclassifies this issue as Category 1 based upon public comments received on the proposed rule

21

and a subsequent re-evaluation of the data in the draft revised GEIS, which showed that air quality impacts from refurbishment have not resulted in exceedances in the

de minimis

thresholds for criteria pollutants in nonattainment and maintenance areas due to construction vehicle, equipment, and fugitive dust emissions. Significant air quality impacts are no longer anticipated from future license renewals. Therefore, applicants no longer need to assess the impacts on air quality of continued operations and refurbishment associated with license renewal in their environmental reports.

21

The proposed rule renamed the “Air quality during refurbishment (nonattainment and maintenance areas)” issue as “Air quality (nonattainment and maintenance areas)” and retained the Category 2 classification.

Section IV, “Response to Public Comments,” of this document provides a summary of the comments received on this issue, and Section VIII, “Final Actions and Basis for Changes to Table B-1,” of this document discusses this issue in more detail under Issue 5, “Air quality impacts (all plants).”

Section 51.53(c)(3)(ii)(I).

The final rule removes and reserves 10 CFR 51.53(c)(3)(ii)(I) because several Category 2 socioeconomic issues are reclassified as Category 1. The removed regulatory language required the applicant to assess the impacts of the proposed license renewal on housing availability, land use, and public schools (impacts from refurbishment activities only) within the vicinity of the plant. Additionally, the removed regulatory language required the applicant to assess the impact of population increases attributable to the proposed project on the public water supply. Specifically, the final rule reclassifies the following 1996 GEIS Category 2 socioeconomic issues: Housing impacts;

22

Public services: public utilities;

23

Public services, education (refurbishment);

24

Offsite land use (refurbishment); and Offsite land use (license renewal term).

25

22

The final rule renames this issue as “Population and housing” (

see

Issue (55) under Section VIII, “Final Actions and Basis for Changes to Table B-1,” of this document).

23

The final rule merges this issue into the consolidated issue, “Community services and education” (

see

Issue (54) under Section VIII of this document).

24

The final rule merges this issue into the consolidated issue, “Community services and education” (

see

Issue (54) under Section VIII of this document).

25

The final rule merges “Offsite land use (refurbishment)” and “Offsite land use (license renewal term) into the consolidated issue, “Offsite land use” (

see

Issue (2) under Section VIII of this document).

The final rule reclassifies these issues as Category 1 because significant changes in housing availability, land use, and increased population demand attributable to the proposed refurbishment project on the public water supply have not occurred at relicensed nuclear power plants. Therefore, impacts to these resources are no longer anticipated for future license renewals. In addition, refurbishment activities (such as steam generator and vessel head replacement) have not required the large numbers of workers and the months of time that were conservatively analyzed in the 1996 GEIS. As such, significant impacts on housing availability, land use, public schools, and the public water supply are no longer anticipated from continued operations during the license renewal term and refurbishment associated with license renewal.

Section 51.53(c)(3)(ii)(J).

The final rule removes and reserves 10 CFR 51.53(c)(3)(ii)(J) because the Category 2 issue, “Public services, transportation,” is reclassified as Category 1 (the final rule also renames the issue, “Transportation”). The removed

regulatory language required the applicant to assess the impact of highway traffic generated by the proposed project on the level of service of local highways during periods of license renewal refurbishment activities and during the term of the renewed license. Therefore, applicants no longer need to assess the impacts on local traffic volumes of continued operations and refurbishment associated with license renewal in their environmental reports.

The issue was reclassified to Category 1 because refurbishment activities (such as steam generator and vessel head replacement) have not required the large numbers of workers and the months of time that was conservatively analyzed in the 1996 GEIS. As such, significant transportation impacts are not anticipated from future refurbishment activities. Section VIII, “Final Actions and Basis for Changes to Table B-1,” of this document discusses this issue in more detail under Issue 56, “Transportation.”

Section 51.53(c)(3)(ii)(O).

The proposed rule added a new paragraph 10 CFR 51.53(c)(3)(ii)(O) to address “Groundwater and soil contamination” as a Category 2 issue. However, based upon public comments received on the proposed rule

26

and further evaluation by the NRC, it was determined that this issue is properly classified as Category 1. Therefore, the proposed paragraph was not adopted by the final rule.

27

26

Section IV, “Response to Public Comments,” of this document provides a summary of the comments received on this issue.

27

The final rule merges this issue into the consolidated issue, “Groundwater contamination and use (non-cooling system impacts)” (

see

Issue (20) under Section VIII of this document).

B. Adding New Category 2 Issues

Section 51.53(c)(3)(ii)(N).

The final rule adds a new paragraph 10 CFR 51.53(c)(3)(ii)(N)

28

to address “Minority and low-income populations” as a Category 2 issue. This new Category 2 issue is listed under the resource area “Environmental Justice” in the revised Table B-1. It addresses the effects of nuclear power plant operations and refurbishment associated with license renewal on minority populations and low-income populations living in the vicinity of the plant. This issue was listed in the original Table B-1 but was not evaluated in the 1996 GEIS. The finding in the original Table B-1 stated that “[t]he need for and the content of an analysis of environmental justice will be addressed in plant specific reviews.” This issue was not classified as either a Category 1 or 2 issue in the 1996 GEIS because guidance for implementing Executive Order (E.O.) 12898, dated February 16, 1994 (59 FR 7629), which initiated the Federal government's environmental justice program, was not available before the completion of the 1996 GEIS.

28

The final rule adopts the proposed rule language.

In August 2004, the Commission issued a policy statement on implementation of E.O. 12898: “NRC's Policy Statement on the Treatment of Environmental Justice Matters in NRC Regulatory and Licensing Actions” (69 FR 52040). As stated therein, “the NRC is committed to the general goals of E.O. 12898, [and] it will strive to meet those goals through its normal and traditional NEPA review process.” By making this a Category 2 issue, the final rule requires license renewal applicants to identify, in their environmental reports, minority and low-income populations and communities residing in the vicinity of the nuclear power plant. The NRC will then assess the information provided by the applicant in the NRC's plant-specific environmental review.

Section 51.53(c)(3)(ii)(O).

The final rule adds a new paragraph 10 CFR 51.53(c)(3)(ii)(O)

29

to address “Cumulative impacts” as a Category 2 issue. This new Category 2 issue was added to Table B-1 to evaluate the potential cumulative impacts of continued operations during the license renewal term and refurbishment associated with license renewal at nuclear power plants. The NRC did not address cumulative impacts in the 1996 GEIS but has been evaluating these impacts in plant-specific supplements to the GEIS. The Council on Environmental Quality (CEQ) in 40 CFR 1508.7 defines cumulative impacts as “the impact on the environment which results from the incremental impact of the action when added to other past, present, and reasonably foreseeable future actions regardless of what agency (Federal or non-Federal) or person undertakes such other actions.”

30

The NRC considers potential cumulative impacts on the environment resulting from the incremental impact of license renewal when added to other past, present, and reasonably foreseeable future actions.

29

The proposed rule added this paragraph as 10 CFR 51.53(c)(3)(ii)(P). The final rule redesignates it as 10 CFR 51.53(c)(3)(ii)(O) because paragraph 10 CFR 51.53(c)(3)(ii)(O) of the proposed rule, which concerned “Groundwater and soil contamination” (

see

discussion in Section VI, “A. Reclassifying Category 2 Issues as Category 1 Issues,” of this document) was not adopted by the final rule.

30

The NRC's regulations in 10 CFR part 51 incorporate the CEQ definition of cumulative impacts (10 CFR 51.14(b)).

The final rule change requires license renewal applicants to provide information about other past, present, and reasonably foreseeable future actions occurring in the vicinity of the nuclear power plant that may result in a cumulative impact. An example of the type of information to be provided includes data on the construction and operation of other power plants and other industrial commercial facilities in the vicinity of the nuclear power plant. Section VIII, “Final Actions and Basis for Changes to Table B-1,” of this document discusses this issue in more detail under Issue 73, “Cumulative impacts.”

Section 51.53(c)(3)(ii)(P).

The final rule adds a new paragraph 10 CFR 51.53(c)(3)(ii)(P)

31

to address “Radionuclides released to groundwater” as a Category 2 issue. This new Category 2 issue has been added to Table B-1 to evaluate the potential combined impact of inadvertent discharges of radioactive liquids from all plant systems into groundwater. The issue is relevant to license renewal because all commercial nuclear power plants have spent fuel pools, liquid storage tanks, and piping that contain and transport radioactive liquids. Over time, these systems and piping have a potential to degrade and release radioactive liquids that could migrate into the groundwater. The NRC has investigated several cases where radioactive liquids have been inadvertently released into the groundwater in an uncontrolled manner. In accordance with NRC requirements, residual activity from these inadvertent releases is subject to characterization and evaluation of the potential hazard. For this new Category 2 issue, the license renewal applicant is required to provide information on radioactive liquids released to groundwater.

31

The proposed rule added this paragraph as 10 CFR 51.53(c)(3)(ii)(Q). The final rule redesignates it as paragraph 10 CFR 51.53(c)(3)(ii)(P) because the paragraph added as 10 CFR 51.53(c)(3)(ii)(O) by the proposed rule, which concerned groundwater and soil contamination caused by non-radionuclide, industrial contaminants, was not adopted by the final rule (

see

discussion in Section VI, “A. Reclassifying Category 2 Issues as Category 1 Issues,” of this document).

In the final rule, the NRC modified the language of the proposed rule to specify that only “documented” releases need to be included in the applicant's environmental report. The NRC provides specific guidance on what constitutes a documented release in Regulatory Guide 4.2, Supplement 1, Revision 1, “Preparation of Environmental Reports for Nuclear

Power Plant License Renewal Applications.”

Section IV, “Response to Public Comments,” of this document provides a summary of the comments received on this issue, and Section VIII, “Final Actions and Basis for Changes to Table B-1,” of this document discusses this issue in more detail under Issue 27, “Radionuclides released to groundwater.”

VII. Response to Specific Request for Voluntary Information

In Section VII of the Statement of Considerations for the July 31, 2009 (74 FR 38129-38130), proposed rule, the NRC requested voluntary information from industry about refurbishment activities and employment trends at nuclear power plants. Information on refurbishment would have been used to evaluate the significance of impacts from this type of activity. Information on employment trends would have been used to assess the significance of socioeconomic effects of ongoing plant operations on local economies.

The NRC received no response to these requests. The NRC interprets this lack of response on these issues to mean that information on major refurbishment and replacement activities and employment trends is either unavailable or insufficient to assist the NRC in re-evaluating the significance of refurbishment-related environmental impacts and socioeconomic effects of ongoing plant operations on local economies. Although no information was received regarding refurbishment activities and employment trends at nuclear power plants, the NRC believes that it has sufficient information based on lessons learned and knowledge gained from completed license renewal environmental reviews to substantiate the conclusions made in the final rule and GEIS.

VIII. Final Actions and Basis for Changes to Table B-1

The final rule revises Table B-1 to reflect the changes made in the revised GEIS. The revised GEIS is being made available with the final rule and provides a summary change table (in Appendix B) comparing the 92 environmental issues in the 1996 GEIS with the 78 environmental issues in the revised GEIS.

Land Use

(1) Onsite Land Use:

“Onsite land use” remains a Category 1 issue. The final rule amends Table B-1 by making minor clarifying changes to the finding column entry for this issue. Specifically, the final rule replaces the sentence “Projected onsite land use changes required during refurbishment and the renewal period would be a small fraction of any nuclear power plant site and would involve land that is controlled by the applicant,” with “Changes in onsite land use from continued operations and refurbishment associated with license renewal would be a small fraction of the nuclear power plant site and would involve only land that is controlled by the licensee.”

(2) Offsite Land Use:

The final rule amends Table B-1 by consolidating two Category 2 issues, “Offsite land use (refurbishment),” with an impact level range small to moderate, and “Offsite land use (license renewal term),” with an impact level range small to large, and reclassifying the consolidated issue as a Category 1 issue, with an impact level of small, and naming the consolidated issue, “Offsite land use.” The final rule also creates a new Category 1 issue, “Tax revenues” (Issue 53), which concerns the impact of license renewal on state and local tax revenues, thereby removing tax revenues from the 1996 GEIS “Offsite land use (license renewal term)” issue. The final rule amends Table B-1 by removing the entries for “Offsite land use (refurbishment)” and “Offsite land use (license renewal term),” and by adding an entry for “Offsite land use.” The finding column entry of “Offsite land use” states “[o]ffsite land use would not be affected by continued operations and refurbishment associated with license renewal.”

The Table B-1 finding column entry for the “Offsite land use (refurbishment)” issue indicated that impacts may be of moderate significance at plants in low population areas. Similarly, the finding column entry for the “Offsite land use (license renewal term)” issue indicates that significant changes (moderate to large) in land use may be associated with population and tax revenue changes resulting from license renewal. As described in the 1996 GEIS, environmental impacts are considered to be small if refurbishment activities were to occur at plants located in high population areas and if population and tax revenues would not change.

As reflected in the revised GEIS, significant impacts on offsite land use are not anticipated. Previous plant-specific license renewal reviews conducted by the NRC have shown no substantial increases in the number of workers during the license renewal term and that refurbishment activities (such as steam generator and vessel head replacement) have not required the large numbers of workers and the months of time that was conservatively estimated in the 1996 GEIS. These reviews support a finding that offsite land use impacts during the license renewal term would be small for all nuclear power plants.

(3) Offsite Land Use in Transmission Line Right-of-Ways (ROWs):

The final rule amends Table B-1 by renaming the “Power line right of way” issue as “Offsite land use in transmission line right-of-ways (ROWs).” It remains a Category 1 issue with an impact level of small. The final rule amends the Table B-1 finding column entry for this issue by replacing the statement,

Ongoing use of power line right of ways would continue with no change in restrictions. The effects of these restrictions are of small significance.

with the following:

Use of transmission line ROWs from continued operations and refurbishment associated with license renewal would continue with no change in land use restrictions.

The final rule further amends Table B-1 by appending a footnote to the issue column entry for “Offsite land use in transmission line right-of-ways (ROWs),” concerning the extent to which transmission lines and their associated ROWs have been analyzed in the revised GEIS. The footnote states,

This issue applies only to the in-scope portion of electric power transmission lines which are defined as transmission lines that connect the nuclear power plant to the substation where electricity is fed into the regional power distribution system and transmission lines that supply power to the nuclear plant from the grid.

As stated in the revised GEIS, the final environmental statements (essentially, the equivalent of environmental impact statements) prepared for the original construction of the various nuclear power plants (the construction permits) and for the initial operating licenses evaluated the impacts of those transmission lines built to connect the nuclear power plant to the regional electrical grid. Since the original construction of those lines, regional expansion of the electrical distribution grid has resulted in incorporation of those lines originating at the power plant substations. In most cases, the transmission lines originating at the power plant substations are no longer owned or managed by the nuclear power plant licensees. These lines would remain in place and be energized regardless of whether the subject nuclear power plant license was renewed or not. For this reason, those transmission lines that would not be impacted by a license renewal decision (i.e., those lines that would not be

dismantled or otherwise decommissioned as a result of a plant terminating operations because its operating license had not been renewed) are considered beyond the scope of, and as such are not analyzed in, the revised GEIS.

Visual Resources

(4) Aesthetic Impacts:

The final rule amends Table B-1 by consolidating three Category 1 issues, “Aesthetic impacts (refurbishment),” “Aesthetic impacts (license renewal term),” and “Aesthetic impacts of transmission lines (license renewal term),” each with an impact level of small, into one new Category 1 issue, “Aesthetic impacts.” The new consolidated issue also has an impact level of small. The 1996 GEIS concluded that renewal of operating licenses and the refurbishment activities would have no significant aesthetic impact during the license renewal term. Impacts are considered to be small if the visual appearance of plant and transmission line structures would not change. Previous license renewal reviews conducted by the NRC show that the appearance of nuclear power plants and transmission line structures do not change significantly over time or because of refurbishment activities. Therefore, because aesthetic impacts are not anticipated and the three issues are similar, they have been consolidated to facilitate the environmental review process. The final rule amends Table B-1 by removing the entries for “Aesthetic impacts (refurbishment),” “Aesthetic impacts (license renewal term),” and “Aesthetic impacts of transmission lines (license renewal term),” and adding an entry for “Aesthetic impacts.” The finding column entry for the new combined entry states “[n]o important changes to the visual appearance of plant structures or transmission lines are expected from continued operations and refurbishment associated with license renewal.”

Air Quality

(5) Air Quality Impacts (All Plants):

The final rule amends Table B-1 by renaming the “Air quality during refurbishment (nonattainment and maintenance areas)” issue as “Air quality impacts (all plants).” The final rule reflects the revised GEIS's expansion of the issue to include air emission impacts from emergency diesel generators, boilers, and particulate emissions from cooling towers. Based on public comments received on the proposed rule and the re-evaluation of information as described in the revised GEIS, the final rule further amends Table B-1 by revising this Category 2 issue, with an impact level range small to large, to a Category 1 issue with an impact level of small.

32

The final rule further amends Table B-1 by revising the finding column entry for this issue to state,

32

Under the proposed rule, the issue had been proposed to be renamed “Air quality (nonattainment and maintenance areas);” it would have remained a Category 2 issue with an impact level range of small to large (74 FR 38121, 38134; July 31, 2009).

Air quality impacts from continued operations and refurbishment associated with license renewal are expected to be small at all plants. Emissions resulting from refurbishment activities at locations in or near air quality nonattainment or maintenance areas would be short-lived and would cease after these refurbishment activities are completed. Operating experience has shown that the scale of refurbishment activities has not resulted in exceedance of the

de minimis

thresholds for criteria pollutants, and best management practices including fugitive dust controls and the imposition of permit conditions in State and local air emissions permits would ensure conformance with applicable State or Tribal Implementation Plans.

Emissions from emergency diesel generators and fire pumps and routine operations of boilers used for space heating would not be a concern, even for plants located in or adjacent to nonattainment areas. Impacts from cooling tower particulate emissions even under the worst-case situations have been small.

Operating experience has shown that air quality impacts from these emission sources (including particulate emissions from cooling towers at operating plants) have been small at all nuclear power plants, including those plants located in or adjacent to nonattainment areas.

In addition, air quality impacts during refurbishment have also been small. These types of emissions could be a cause for concern if they occur at plants located in or near air quality nonattainment or maintenance areas. However, these impacts have been temporary and would cease once these activities were completed. Operating experience has also shown that refurbishment activities have not required the large numbers of workers and the months of time that was conservatively predicted and analyzed in the 1996 GEIS, nor have such activities resulted in exceedances in the

de minimis

thresholds for criteria pollutants in nonattainment and maintenance areas.

Implementation of best management practices, including fugitive dust controls as required by the imposition of conditions in State and local air emissions permits, would ensure conformance with applicable State or Tribal Implementation Plans, in accordance with EPA's revised General Conformity Regulations (75 FR 17254; April 5, 2010). On the basis of these considerations, the NRC has concluded that the air quality impact of continued nuclear power plant operations and refurbishment associated with license renewal would be small for all plants.

(6) Air Quality Effects of Transmission Lines

:

The final rule amends Table B-1 by appending a footnote to the issue column entry for “Air quality effects of transmission lines,” concerning the extent to which transmission lines and their associated right of ways have been analyzed under the revised GEIS. This footnote is the same one that was added to Issue 3, “Offsite land use in transmission line right-of-ways (ROWs).” See the description of the changes made by the final rule to Issue 3 for further explanation of this amendment.

Noise

(7) Noise Impacts

:

The final rule amends Table B-1 by renaming the issue “Noise” as “Noise impacts.” The issue remains a Category 1 issue with an impact level of small. The final rule further amends Table B-1 by making minor clarifying changes to the finding column entry for this issue. Specifically, the final rule replaces the sentence “Noise has not been found to be a problem at operating plants and is not expected to be a problem at any plant during the license renewal term,” with “Noise levels would remain below regulatory guidelines for offsite receptors during continued operations and refurbishment associated with license renewal.”

Geologic Environment

(8) Geology and Soils

:

The final rule amends Table B-1 by adding a new Category 1 issue, “Geology and soils.” This issue has an impact level of small. The finding column entry for this issue states,

The effect of geologic and soil conditions on plant operations and the impact of continued operations and refurbishment activities on geology and soils would be small for all nuclear power plants and would not change appreciably during the license renewal term.

This issue was not evaluated in the 1996 GEIS, as described in the proposed rule.

33

This new Category 1 issue considers geology and soils from the perspective of those resource conditions or attributes that can be affected by

continued operations during the renewal term. The final rule does not require the license renewal applicant to assess this issue in its environmental report unless the applicant is aware of new and significant information about geologic and soil conditions and associated impacts at or near the nuclear power plant site that could change the conclusion in the GEIS.

33

The proposed rule named the issue “Impacts of nuclear plants on geology and soils.” Under the proposed rule, the issue was also a Category 1 issue, with an impact level of small (74 FR 38121, 38134; July 31, 2009).

An understanding of geologic and soil conditions has been well established at all nuclear power plants and associated transmission lines during the current licensing term, and these conditions are expected to remain unchanged during the 20-year license renewal term for each plant. The impact of these conditions on plant operations and the impact of continued power plant operations and refurbishment activities on geology and soils are small for all nuclear power plants and not expected to change appreciably during the license renewal term. Operating experience shows that any impacts to geologic and soil strata would be limited to soil disturbance from construction activities associated with routine infrastructure renovation and maintenance projects during continued plant operations. Implementing best management practices would reduce soil erosion and subsequent impacts on surface water quality. Information in plant-specific SEISs prepared to date and reference documents have not identified these impacts as being significant.

Surface Water Resources

(9) Surface Water Use and Quality (Non-Cooling System Impacts)

:

The final rule amends Table B-1 by consolidating two Category 1 issues, “Impacts of refurbishment on surface water quality” and “Impacts of refurbishment on surface water use,” both with an impact level of small, and names the consolidated issue, “Surface water use and quality (non-cooling system impacts).” These two issues were consolidated because the impacts of refurbishment on both surface water use and quality are negligible and the effects are closely related. The consolidated issue has also been expanded to include the impacts of continued operations. The consolidated issue is a Category 1 issue with an impact level of small.

The final rule amends Table B-1 by removing the entries for “Impacts of refurbishment on surface water quality” and “Impacts of refurbishment on surface water use” and adding an entry for “Surface water use and quality (non-cooling system impacts).” The finding column entry for the new consolidated issue states,

Impacts are expected to be small if best management practices are employed to control soil erosion and spills. Surface water use associated with continued operations and refurbishment associated with license renewal would not increase significantly or would be reduced if refurbishment occurs during a plant outage.

The NRC expects licensees to use best management practices during the license renewal term for both continuing operations and refurbishment activities. Use of best management practices will minimize soil erosion. In addition, implementation of spill prevention and control plans will reduce the likelihood of any liquid chemical spills. If refurbishment activities take place during a plant outage, with the reactor shutdown, the overall water use by the facility will be reduced. Based on this conclusion, the impact on surface water use and quality during the license renewal term will continue to be small for all plants.

(10) Altered Current Patterns at Intake and Discharge Structures, (11) Altered Salinity Gradients, (12) Altered Thermal Stratification of Lakes, and (13) Scouring Caused by Discharged Cooling Water:

These four issues remain Category 1 issues, each with an impact level of small. The final rule amends Table B-1 by making minor clarifying changes to the finding column entries for each of these issues.

The final rule amends the “Altered current patterns at intake and discharge structures” finding column entry by replacing the statement,

Altered current patterns have not been found to be a problem at operating nuclear power plants and are not expected to be a problem during the license renewal term.

with the following:

Altered current patterns would be limited to the area in the vicinity of the intake and discharge structures. These impacts have been small at operating nuclear power plants.

The final rule amends the “Altered salinity gradients” finding column entry by replacing the statement,

Salinity gradients have not been found to be a problem at operating nuclear power plants and are not expected to be a problem during the license renewal term.

with the following:

Effects on salinity gradients would be limited to the area in the vicinity of the intake and discharge structures. These impacts have been small at operating nuclear power plants.

The final rule amends the “Altered thermal stratification of lakes” finding column entry by replacing the statement,

Generally, lake stratification has not been found to be a problem at operating nuclear power plants and is not expected to be a problem during the license renewal term.

with the following:

Effects on thermal stratification would be limited to the area in the vicinity of the intake and discharge structures. These impacts have been small at operating nuclear power plants.

The final rule amends the “Scouring caused by discharged cooling water” finding column entry by replacing the statement,

Scouring has not been found to be a problem at most operating nuclear power plants and has caused only localized effects at a few plants. It is not expected to be a problem during the license renewal term.

with the following:

Scouring effects would be limited to the area in the vicinity of the intake and discharge structures. These impacts have been small at operating nuclear power plants.

These changes reflect the findings of environmental reviews conducted since the publication of the 1996 GEIS, which show that the effects of these four issues are localized in the vicinity of the plant's intake and discharge structures.

(14) Discharge of Metals in Cooling System Effluent:

The final rule amends Table B-1 by renaming “Discharge of other metals in waste water” as “Discharge of metals in cooling system effluent.” It remains a Category 1 issue with an impact level of small. The final rule also makes minor clarifying changes to the finding column entry for this issue. Specifically, the final rule amends the finding column entry by replacing the statement,

These discharges have not been found to be a problem at operating nuclear power plants with cooling-tower-based heat dissipation systems and have been satisfactorily mitigated at other plants. They are not expected to be a problem during the license renewal term.

with the following:

Discharges of metals have not been found to be a problem at operating nuclear power plants with cooling-tower-based heat dissipation systems and have been satisfactorily mitigated at other plants. Discharges are monitored and controlled as part of the National Pollutant Discharge Elimination System (NPDES) permit process.

(15) Discharge of Biocides, Sanitary Wastes, and Minor Chemical Spills:

The final rule amends Table B-1 by consolidating two Category 1 issues, “Discharge of chlorine or other biocides” and “Discharge of sanitary wastes and minor chemical spills,” both with an impact level of small, and naming the consolidated issue “Discharge of biocides, sanitary wastes,

and minor chemical spills.” The consolidated issue is a Category 1 issue with an impact level of small. Specifically, the final rule amends Table B-1 by removing the entries for “Discharge of chlorine or other biocides” and “Discharge of sanitary wastes and minor chemical spills” and adding an entry for “Discharge of biocides, sanitary wastes, and minor chemical spills.” The finding column entry for the new consolidated issue states,

The effects of these discharges are regulated by Federal and State environmental agencies. Discharges are monitored and controlled as part of the NPDES permit process. These impacts have been small at operating nuclear power plants.

(16)

Surface Water Use Conflicts (Plants with Once-Through Cooling Systems):

“Water use conflicts (plants with once-through cooling systems)” remains a Category 1 issue with an impact level of small. The final rule amends Table B-1 by adding the word “Surface” to the title of this issue.

(17)

Surface Water Use Conflicts (Plants with Cooling Ponds or Cooling Towers Using Makeup Water from a River):

The final rule amends Table B-1 by adding the term “surface” and removing the terms “small” and “low flow” from the title and the associated numerical definition contained in 10 CFR 51.53(c)(3)(ii)(A) for low flow rivers from this and other related river flow issues. This issue remains a Category 2 issue with an impact range of small to moderate. The final rule also amends the finding column entry by replacing the statement,

The issue has been a concern at nuclear power plants with cooling ponds and at plants with cooling towers. Impacts on instream and riparian communities near these plants could be of moderate significance in some situations. See § 51.53(c)(3)(ii)(A).

with the following:

Impacts could be of small or moderate significance, depending on makeup water requirements, water availability, and competing water demands.

The 1996 GEIS distinguished between surface water use impacts during low flow conditions on “small” versus “large” rivers. Any river, regardless of size, can experience low flow conditions of varying severity during periods of drought and changing conditions in the affected watersheds such as upstream diversions and use of river water. Similarly, the NRC has determined that the use of the term “low flow” in categorizing river flow is of little value considering that plants that withdraw makeup water from a river can experience low flow conditions and would be required to conduct a plant-specific assessment of water use conflicts.

(18)

Effects of Dredging on Surface Water Quality:

The final rule amends Table B-1 by adding a new Category 1 issue, “Effects of dredging on surface water quality,” which evaluates the impacts of dredging to maintain intake and discharge structures at nuclear power plant facilities. This issue has an impact level of small. The finding column entry for this issue states,

Dredging to remove accumulated sediments in the vicinity of intake and discharge structures and to maintain barge shipping has not been found to be a problem for surface water quality. Dredging is performed under permit from the U.S. Army Corps of Engineers, and possibly, from other State or local agencies.

The impact of dredging on surface water quality was not considered in the 1996 GEIS and was not listed in Table B-1 prior to this final rule. Most plants have intake and discharge structures that must be maintained by periodic dredging of sediment accumulated in or on the structures. The NRC has found that dredging, while temporarily increasing turbidity in the source water body, generally has little long-term effect on water quality. In addition to maintaining intake and discharge structures, dredging is often done to keep barge slips and channels open to service the plant. Dredged material is most often disposed on property owned by the applicant and usually contains no hazardous materials. Dredging must be performed under a permit issued by the U.S. Army Corps of Engineers (the Corps) and consequently, each dredging action would be subject to a site-specific environmental review conducted by the Corps. Temporary impacts of dredging are measurable in general water quality terms, but the impacts have been shown to be small.

(19)

Temperature Effects on Sediment Transport Capacity:

There are no changes to this issue, and it remains a Category 1 issue with an impact level of small.

Groundwater Resources

(20)

Groundwater Contamination and Use (Non-Cooling System Impacts):

The final rule amends Table B-1 by expanding the scope of “Impacts of refurbishment on groundwater use and quality” issue to include the effects of continued nuclear power plant operations during the license renewal term. This Category 1 issue, with an impact level of small, was renamed “Groundwater use and quality” in the proposed rule.

The final rule also amends Table B-1 by changing the proposed rule's new Category 2 issue “Groundwater and soil contamination,” with an impact range of small to moderate (see 74 FR 38122, 38135), to Category 1, with an impact level of small. This issue was then consolidated with the “Groundwater use and quality” issue and renamed “Groundwater contamination and use (non-cooling system impacts).” These issues were consolidated because they consider the impact of industrial activities associated with the continued operations of a nuclear power plant (not directly related to cooling system effects) and refurbishment on groundwater use and quality. The final rule further amends Table B-1 by replacing the finding column entry, which states,

Extensive dewatering during the original construction on some sites will not be repeated during refurbishment on any sites. Any plant wastes produced during refurbishment will be handled in the same manner as in current operating practices and are not expected to be a problem during the license renewal term.

with the following:

Extensive dewatering is not anticipated from continued operations and refurbishment associated with license renewal. Industrial practices involving the use of solvents, hydrocarbons, heavy metals, or other chemicals, and/or the use of wastewater ponds or lagoons have the potential to contaminate site groundwater, soil, and subsoil. Contamination is subject to State or Environmental Protection Agency regulated cleanup and monitoring programs. The application of best management practices for handling any materials produced or used during these activities would reduce impacts.

The consolidated Category 1 issue considers the impacts from groundwater use and the impacts on groundwater, soil, and subsoil from the industrial use of solvents, hydrocarbons, heavy metals, or other chemicals at nuclear power plant sites from continued operation during the license renewal term and refurbishment. The consolidated issue also includes the use of wastewater disposal ponds or lagoons and non-radionuclide, industrial contaminants released inadvertently or as effluents into the environment. Industrial practices at all nuclear power plants have the potential to contaminate groundwater and soil, especially on sites with unlined wastewater and storm water ponds or lagoons. Any contamination of this type is subject to characterization and clean-up under EPA or State regulated remediation and monitoring programs.

Non-radionuclide contaminants have been found in groundwater and soil

samples at some nuclear power plants during previous license renewal environmental reviews. Release of these contaminants into groundwater and soil degrades the quality of these resources, even if applicable groundwater quality standards are not exceeded. However, each site has its own program for handling chemicals, waste, and other hazardous materials in accordance with Federal and State regulations and is expected to employ best management practices. The use of wastewater disposal ponds or lagoons, whether lined or unlined, may increase the potential for groundwater and soil contamination. However, they are subject to discharge authorizations under NPDES and related State wastewater discharge permit programs.

The finding column of Table B-1 for “Groundwater use and quality” prior to this final rule, as analyzed in the 1996 GEIS, indicated that impacts of continued operations and refurbishment on groundwater use and quality would be small, as extensive dewatering is not anticipated. This finding was re-evaluated in the revised GEIS and is retained in Table B-1.

While the proposed rule's “Groundwater and soil contamination” issue was identified as a Category 2 issue, further consideration of the “Groundwater and soil contamination” issue and public comments revealed that the potential impacts on groundwater and soil quality from common industrial practices can be addressed generically, as these practices are common to all industrial facilities and are not unique to nuclear power plants. Moreover, as supported by the analysis in the revised GEIS, the NRC concludes that the overall impact of industrial practices on groundwater use and quality from past and current operations is small for all nuclear power plants and not expected to change appreciably during the license renewal term.

(21)

Groundwater Use Conflicts (Plants that Withdraw Less Than 100 Gallons per Minute [gpm]):

The final rule amends Table B-1 by renaming the “Ground-water use conflicts (potable and service water; plants that use <100 gpm)” issue as “Groundwater use conflicts (plants that withdraw less than 100 gallons per minute [gpm]).” It remains a Category 1 issue with an impact level of small. The final rule further amends Table B-1 by making minor clarifying changes to the finding column entry for this issue. Specifically, the final rule replaces the entry statement “Plants using less than 100 gpm are not expected to cause any ground-water conflicts,” with “Plants that withdraw less than 100 gpm are not expected to cause any groundwater use conflicts.”

(22)

Groundwater Use Conflicts (Plants that Withdraw More Than 100 Gallons per Minute [gpm]):

The final rule amends Table B-1 by consolidating two Category 2 issues, “Groundwater use conflicts (potable and service water, and dewatering; plants that use >100 gpm)” and “Ground-water use conflicts (Ranney wells),” each with an impact level range of small to large, and names the consolidated issue, “Groundwater use conflicts (plants that withdraw more than 100 gallons per minute [gpm]).” Because Ranney wells produce significantly more than 100 gpm, the Ranney wells issue was consolidated with the general issue of groundwater use conflicts for plants using more than 100 gpm of groundwater. The consolidated issue is a Category 2 issue, with an impact level range of small to large. The final rule further amends Table B-1 by removing the entries for “Groundwater use conflicts (potable and service water, and dewatering; plants that use >100 gpm)” and “Ground-water use conflicts (Ranney wells)” and adding an entry for “Groundwater use conflicts (plants that withdraw more than 100 gallons per minute [gpm]).” The finding column entry for the new consolidated issue states “Plants that withdraw more than 100 gpm could cause groundwater use conflicts with nearby groundwater users.”

(23)

Groundwater Use Conflicts (Plants with Closed-Cycle Cooling Systems that Withdraw Makeup Water from a River):

The final rule amends Table B-1 by renaming “Ground-water use conflicts (plants using cooling towers withdrawing makeup water from a small river)” as “Groundwater use conflicts (plants with closed-cycle cooling systems that withdraw makeup water from a river).” It remains a Category 2 issue, with an impact level range of small to large. The final rule further amends Table B-1 by replacing the finding column entry, which states,

Water use conflicts may result from surface water withdrawals from small water bodies during low flow conditions which may affect aquifer recharge, especially if other ground-water or upstream surface water users come on line before the time of license renewal. See § 51.53(c)(3)(ii)(A).

with the following:

Water use conflicts could result from water withdrawals from rivers during low-flow conditions, which may affect aquifer recharge. The significance of impacts would depend on makeup water requirements, water availability, and competing water demands.

The 1996 GEIS distinguished between surface water use impacts during low flow conditions on “small” versus “large” rivers. Any river, regardless of size, can experience low flow conditions of varying severity during periods of drought and changing conditions in the affected watersheds such as upstream diversions and use of river water. The NRC has thus determined that the use of the term “small river” or “small water bodies” is of little value considering that plants that withdraw makeup water from a river can experience low-flow conditions and would be required to conduct a plant-specific assessment of water use conflicts.

(24)

Groundwater Quality Degradation Resulting from Water Withdrawals:

The final rule amends Table B-1 by consolidating two Category 1 issues, “Ground-water quality degradation (Ranney wells)” and “Ground-water quality degradation (saltwater intrusion),” each with an impact level of small, and names the consolidated issue, “Groundwater quality degradation resulting from water withdrawals.” The consolidated issue remains a Category 1 issue, with an impact level of small. The final rule further amends Table B-1 by removing the entries for “Ground-water quality degradation (Ranney wells)” and “Ground-water quality degradation (saltwater intrusion)” and, by adding an entry for “Groundwater quality degradation resulting from water withdrawals.” The finding column entry for the consolidated issue states “Groundwater withdrawals at operating nuclear power plants would not contribute significantly to groundwater quality degradation.” The two issues were consolidated as they both consider the possibility of groundwater quality becoming degraded as a result of plant operations drawing water of potentially lower quality into the aquifer.

(25) Groundwater Quality Degradation (Plants with Cooling Ponds in Salt Marshes): The final rule amends Table B-1 by revising the title of the issue “Ground-water quality degradation (cooling ponds in salt marshes)” to “Groundwater quality degradation (plants with cooling ponds in salt marshes).” The issue remains a Category 1 issue, with an impact level of small. The final rule further amends Table B-1 by replacing the finding column entry, which states,

Sites with closed-cycle ponds may degrade ground-water quality. Because water in salt marshes is brackish, this is not a concern for plants located in salt marshes.

with the following:

Sites with closed-cycle cooling ponds could degrade groundwater quality. However, groundwater in salt marshes is naturally brackish and thus, not potable. Consequently, the human use of such groundwater is limited to industrial purposes.

The final rule change to the finding column entry reflects the NRC's response to a public comment on the proposed rule by: (1) Deleting the term “plants” to eliminate any confusion that the NRC might have meant marsh “plants” rather than “nuclear power plants;” and (2) clarifying that the focus of this issue is on the degradation of groundwater quality for human use. Brackish groundwater has limited human use, thus, any impacts on groundwater quality caused by continued operations and refurbishment associated with license renewal are not significant.

(26) Groundwater Quality Degradation (Plants with Cooling Ponds at Inland Sites): The final rule amends Table B-1 by revising the title of the issue “Ground-water quality degradation (cooling ponds at inland sites)” to “Groundwater quality degradation (plants with cooling ponds at inland sites).” The issue remains a Category 2 issue, with an impact level range of small to large. The final rule further amends Table B-1 by replacing the finding column entry, which states,

Sites with closed-cycle cooling ponds may degrade ground-water quality. For plants located inland, the quality of the ground water in the vicinity of the ponds must be shown to be adequate to allow continuation of current uses. See § 51.53(c)(3)(ii)(D).

with the following:

Inland sites with closed-cycle cooling ponds could degrade groundwater quality. The significance of the impact would depend on cooling pond water quality, site hydrogeologic conditions (including the interaction of surface water and groundwater), and the location, depth, and pump rate of water wells.

(27)

Radionuclides Released to Groundwater:

The final rule amends Table B-1 by adding a new Category 2 issue, “Radionuclides released to groundwater,” with an impact level range of small to moderate, to evaluate the potential impact of discharges of radionuclides from plant systems into groundwater. The finding column entry for this issue states,

Leaks of radioactive liquids from plant components and pipes have occurred at numerous plants. Groundwater protection programs have been established at all operating nuclear power plants to minimize the potential impact from any inadvertent releases. The magnitude of impacts would depend on site-specific characteristics.

This new Category 2 issue has been added to evaluate the potential impact to groundwater quality from the discharge of radionuclides from plant systems, piping, and tanks. This issue was added because within the past several years there have been events at nuclear power reactor sites that involved unknown, uncontrolled, and unmonitored releases of radioactive liquids into the groundwater. The issue is relevant to license renewal because this experience has shown that components and piping at nuclear power plants have the potential to leak radioactive material into the groundwater and degrade its quality. While the NRC's regulations in 10 CFR part 20 and in 10 CFR part 50 limit the amount of radioactive material released (i.e., from routine and inadvertent sources) from a nuclear power plant into the environment, the regulations are focused on protecting the public, not the quality of the groundwater. Therefore, as required by NEPA, the NRC must consider the potential impacts to the groundwater from radioactive liquids released into groundwater.

The majority of the inadvertent radioactive liquid release events involved tritium, which is a radioactive isotope of hydrogen. However, in some of the events, radioactive isotopes of cesium and strontium have also been released. Non-routine releases of radioactive liquids into the groundwater have occurred from plant systems and buried piping.

In 2006, the NRC's Executive Director for Operations chartered a task force to conduct a lessons-learned review of these incidents. On September 1, 2006, the Task Force issued its report: “Liquid Radioactive Release Lessons Learned Task Force Report” (ADAMS Accession No. ML062650312). A significant conclusion of the report dealt with the potential health impacts to the public from the inadvertent releases. Although there were numerous events where radioactive liquids were released to the groundwater in an unplanned, uncontrolled, and unmonitored fashion, based on the data available, the task force did not identify any instances where public health and safety was adversely impacted. However, the task force did not evaluate the impact of the releases to groundwater quality. The task force also identified that under the existing regulatory requirements, the potential exists for radioactive liquid releases from leaking systems to not be detected for a period of time and, therefore, the contaminants could migrate into groundwater.

In response to these groundwater events, NEI, which represents the nuclear industry, in 2007 committed to the NRC to develop a voluntary initiative for each nuclear power plant to have a site-specific groundwater protection program. NEI provided guidance to the nuclear industry (NEI 07-07, ADAMS Accession No. ML072610036) on the development and implementation of a groundwater protection program. The program covers the assessment of plant systems and components, site hydrogeology, and methods to detect leaks to determine the needs for each site-specific program. To monitor the actions of the nuclear industry, the NRC routinely inspects nuclear power plant licensees to verify continued implementation of the Groundwater Protection Initiative programs, to review records of identified leakage and spill events, to assess whether the source of the leak or spill was identified and mitigated, and to review any remediation actions taken for effectiveness.

On the basis of the information and experience with these groundwater events and the evaluation in the revised GEIS, the NRC concludes that the impact to groundwater quality from the release of radionuclides is dependent on site-specific variables and could be small or moderate, depending on the magnitude of the leak, radionuclides involved, and the response time of plant personnel to identify and stop the leak in a timely fashion. Therefore, “Radionuclides released to groundwater” is a Category 2 issue and, as such, a site-specific evaluation in the environmental report is needed for each application for license renewal. Similarly, the NRC will analyze this issue in the SEIS for each license renewal action.

Terrestrial Resources

(28)

Effects on Terrestrial Resources (Non-Cooling System Impacts):

The final rule amends Table B-1 by renaming the “Refurbishment impacts” issue as “Effects on terrestrial resources (non-cooling system impacts).” It remains a Category 2 issue, with an impact level range of small to large.

34

The issue, as set forth in the 1996 GEIS, addressed only the impacts upon terrestrial resources resulting from any refurbishment activities during the license renewal term. The analysis in the revised GEIS builds on the analysis in the 1996 GEIS to include the environmental impacts resulting from continued plant operations during the license renewal term. The final rule

further amends Table B-1 by replacing the finding column entry, which states,

34

The proposed rule named the issue, “Impacts of continued plant operations on terrestrial ecosystems” (74 FR 38123, 38136; July 31, 2 009).

Refurbishment impacts are insignificant if no loss of important plant and animal habitat occurs. However, it cannot be known whether important plant and animal communities may be affected until the specific proposal is presented with the license renewal application. See § 51.53(c)(3)(ii)(E).

with the following:

Impacts resulting from continued operations and refurbishment associated with license renewal may affect terrestrial communities. Application of best management practices would reduce the potential for impacts. The magnitude of impacts would depend on the nature of the activity, the status of the resources that could be affected, and the effectiveness of mitigation.

(29)

Exposure of Terrestrial Organisms to Radionuclides:

The final rule amends Table B-1 by adding a new Category 1 issue, “Exposure of terrestrial organisms to radionuclides.” The new issue has been determined to have an impact level of small. The finding column entry for this issue states,

Doses to terrestrial organisms from continued operations and refurbishment associated with license renewal are expected to be well below exposure guidelines developed to protect these organisms.

This new issue evaluates the potential impact of radionuclides on terrestrial organisms resulting from continued operations of a nuclear power plant during the license renewal term and refurbishment associated with license renewal. This issue was not evaluated in the 1996 GEIS. Subsequent to the publication of the 1996 GEIS, however, members of the public and various Federal and State agencies commented on the need to evaluate the potential impact of radionuclides on terrestrial organisms during plant-specific license renewal reviews.

The revised GEIS evaluates the potential impact of radionuclides on terrestrial biota at nuclear power plants from continued operations during the license renewal term. For the evaluation, site-specific radionuclide concentrations in environmental media (e.g., water, air, milk, crops, food products, sediment, and fish and other aquatic biota) were obtained from publicly available Radiological Environmental Monitoring Program (REMP) annual reports from 15 nuclear power plants. The REMP is conducted at every NRC licensed nuclear power plant to assess the environmental impacts from plant operations. This is done by collecting samples of environmental media from areas surrounding the plant for analysis to measure the amount of radioactivity, if any, in the samples. The media samples reflect the radiation exposure pathways to the public from radioactive effluents released by the nuclear power plant and from background radiation (i.e., cosmic sources, naturally-occurring radioactive material, including radon and global fallout). These 15 plants were selected to represent sites that reported a range of radionuclide concentrations in the sample media and included both boiling water reactors and pressurized water reactors. Site-specific radionuclide concentrations in water and sediments, as reported in the plant's REMP reports, were used in the calculations. The calculated radiation dose rates to terrestrial biota, based on exposure to radioactivity in the environmental media, were compared against radiation-safety guidelines issued by the U.S. Department of Energy (DOE), the International Atomic Energy Agency (IAEA), the National Council of Radiation Protection and Measurements (NCRP), and the International Commission on Radiological Protection (ICRP). The NRC concluded that the impacts of radionuclides on terrestrial biota from past and current normal operations are small for all nuclear power plants and should not change appreciably during the license renewal term.

(30)

Cooling System Impacts on Terrestrial Resources (Plants with Once-Through Cooling Systems or Cooling Ponds):

The final rule amends Table B-1 by renaming the “Cooling pond impacts on terrestrial resources” issue as “Cooling system impacts on terrestrial resources (plants with once-through cooling systems or cooling ponds).” It remains a Category 1 issue, with an impact level of small. The analysis in the revised GEIS expands the scope of this issue to include plants with once-through cooling systems. This analysis concludes that the impacts on terrestrial resources from once-through cooling systems, as well as from cooling ponds, is of small significance at all plants. The final rule further amends Table B-1 by replacing the finding column entry, which states,

Impacts of cooling ponds on terrestrial ecological resources are considered to be of small significance at all sites.

with the following:

No adverse effects to terrestrial plants or animals have been reported as a result of increased water temperatures, fogging, humidity, or reduced habitat quality. Due to the low concentrations of contaminants in cooling system effluents, uptake and accumulation of contaminants in the tissues of wildlife exposed to the contaminated water or aquatic food sources are not expected to be significant issues.

(31)

Cooling Tower Impacts on Vegetation (Plants with Cooling Towers):

The final rule amends Table B-1 by consolidating two Category 1 issues, “Cooling tower impacts on crops and ornamental vegetation” and “Cooling tower impacts on native plants,” both issues having an impact level of small, and names the consolidated issue, “Cooling tower impacts on vegetation (plants with cooling towers).” The consolidated issue is a Category 1 issue with an impact level of small. The two issues were consolidated to conform to the resource-based approach used in the revised GEIS. With the recent trend of replacing lawns with native vegetation, some ornamental plants and crops are native plants, and the original separation into two issues is unnecessary and cumbersome. The final rule further amends Table B-1 by removing the entries for “Cooling tower impacts on crops and ornamental vegetation” and “Cooling tower impacts on native plants,” and by adding an entry for “Cooling tower impacts on vegetation (plants with cooling towers).” The finding column entry for the new consolidated issue states,

Impacts from salt drift, icing, fogging, or increased humidity associated with cooling tower operation have the potential to affect adjacent vegetation, but these impacts have been small at operating nuclear power plants and are not expected to change over the license renewal term.

(32)

Bird Collisions with Plant Structures and Transmission Lines:

The final rule amends Table B-1 by consolidating two Category 1 issues, “Bird collisions with cooling towers” and “Bird collision with power lines,” both issues having an impact level of small. The final rule also expands the scope of the consolidated issue to address collisions with all plant structures and names the issue, “Bird collisions with plant structures and transmission lines.” The consolidated issue is a Category 1 issue with an impact level of small. The two issues were consolidated to conform to the resource-based approach used in the revised GEIS. The final rule further amends Table B-1 by removing the entries for “Bird collisions with cooling towers” and “Bird collision with power lines,” and by adding an entry for “Bird collisions with plant structures and transmission lines.” The finding column entry for the new consolidated issue states,

Bird collisions with cooling towers and other plant structures and transmission lines occur at rates that are unlikely to affect local or migratory populations and the rates are not expected to change.

The final rule further amends Table B-1 by appending a footnote to the issue column entry for “Bird collisions with plant structures and transmission lines,” concerning the extent to which transmission lines and their associated right of ways have been analyzed under the revised GEIS. This footnote is the same one that was added to Issue 3, “Offsite land use in transmission line right-of-ways (ROWs).” See the description of the changes made by the final rule to Issue 3 for further explanation of this amendment.

(33)

Water Use Conflicts with Terrestrial Resources (Plants with Cooling Ponds or Cooling Towers Using Makeup Water from a River):

The final rule amends Table B-1 by adding a new Category 2 issue, “Water use conflicts with terrestrial resources (plants with cooling ponds or cooling towers using makeup water from a river),” to evaluate water use conflict impacts with terrestrial resources in riparian communities. The 1996 GEIS already addresses the resource aspects of this issue, and 10 CFR 51.53(c)(3)(ii)(A) requires a plant-specific analysis of the impacts of surface water withdrawals from rivers for cooling pond or cooling tower makeup on riparian ecological communities. However, this stand-alone issue was created to clearly separate out the related aspects and potential impacts on terrestrial, riparian communities associated with surface water withdrawals from a river for consumptive cooling water uses. The new issue has an impact level range of small to moderate. The finding column entry for this issue states,

Impacts on terrestrial resources in riparian communities affected by water use conflicts could be of moderate significance.

As described in the revised GEIS, such impacts could occur when water that supports these resources is diminished because of decreased availability due to droughts; increased water demand for agricultural, municipal, or industrial usage; or a combination of these factors. The potential range of impact levels at plants, subject to license renewal, with cooling ponds or cooling towers using makeup water from a river cannot be generically determined. The NRC h

This text is long and has been trimmed here. Open the source document for the complete record.