Promoting Transmission Investment Through Pricing Reform
Federal RegisterJul 31, 2006
Ask Donna
What actually matters in this document.
Text
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
18 CFR Part 35
[Docket No. RM06-4-000; Order No. 679]
Promoting Transmission Investment Through Pricing Reform
Issued July 20, 2006.
AGENCY:
Federal Energy Regulatory Commission, DOE.
ACTION:
Final rule.
SUMMARY:
In this Final Rule, pursuant to the requirements of the Transmission Infrastructure Investment provisions in section 1241 of the Energy Policy Act of 2005, which adds a new section 219 to the Federal Power Act, the Federal Energy Regulatory Commission (Commission) is amending its regulations to establish incentive-based (including performance-based) rate treatments for the transmission of electric energy in interstate commerce by public utilities for the purpose of benefiting consumers by ensuring reliability and reducing the cost of delivered power by reducing transmission congestion. This Final Rule is intended to encourage transmission infrastructure investment.
DATES:
Effective Date:
This Final Rule will become effective September 29, 2006.
FOR FURTHER INFORMATION CONTACT:
Jeffrey Hitchings (Technical Information), Office of Energy Markets and Reliability, Federal Energy Regulatory Commission, 888 First Street, NE, Washington, DC 20426, 202-502-6042.
Sebastian Tiger (Technical Information), Office of Energy Markets and Reliability, Federal Energy Regulatory Commission, 888 First Street, NE, Washington, DC 20426, 202-502-6079.
Andre Goodson (Legal Information), Office of the General Counsel, Federal Energy Regulatory Commission, 888 First Street, NE, Washington, DC 20426, 202-502-8560.
Tina Ham (Legal Information), Office of the General Counsel, Federal Energy Regulatory Commission, 888 First Street, NE, Washington, DC 20426, 202-502-6224.
Martin Kirkwood (Legal Information), Office of the General Counsel, Federal Energy Regulatory Commission, 888 First Street, NE, Washington, DC 20426, 202-502-8125.
SUPPLEMENTARY INFORMATION:
Paragraph Nos.
I. Introduction
1
.
II. Background
1
.
III. Overview
10
.
A. The Need for New Transmission Facilities
10
.
1. Background
10
.
2. Comments
11
.
3. Commission Determination
14
.
B. The Need for Incentives
15
.
1. Background
15
.
2. Comments
16
.
3. Commission Determination
19
.
C. Summary of the Nature and Applicability of Incentives Adopted by the Final Rule
21
.
D. Effective Date and Duration of Effectiveness For Incentives
30
.
1. Background
30
.
2. Comments
31
.
3. Commission Determination
34
.
IV. Discussion
37
.
A. Standard for Approval of Incentive-Based Rate Treatments
37
.
1. The Final Rule Applies to the Recovery of Costs Incurred to Ensure Reliability or to Reduce Transmission Congestion, or Both
37
.
2. Other Criteria For Approval of Incentives
44
.
3. Rebuttable Presumptions
57
.
4. Applicants Seeking Incentive-Based Rates Will Not Be Required To File A Cost-Benefit Analysis
59
.
5. Procedural Requirements for Obtaining Incentive-Based Rate Treatments
66
.
B. Incentives Available To All Jurisdictional Public Utilities
84
.
1. ROE Sufficient to Attract Capital
85
.
2. Construction Work in Progress (CWIP) and Pre-Commercial Expenses
103
.
3. Hypothetical Capital Structure
123
.
4. Accelerated Depreciation
135
.
5. Recovery of Costs of Abandoned Facilities
155
.
6. Deferred Cost Recovery
168
.
7. Other Incentives—Single-Issue Ratemaking
179
.
C. Incentives Available to Transcos
194
.
1. Definition of Transco
194
.
2. Transco ROE Incentive
206
.
3. Accumulated Deferred Income Taxes (ADIT)
242
.
4. Acquisition Premiums for Transco Formation
251
.
5. Merchant Transmission
259
.
D. Performance-Based Ratemaking
263
.
1. General Comments
263
.
2. Comments Proposing Performance Tests and Competitive Bidding
273
.
E. Advanced Technologies
280
.
1. General
280
.
2. Case-by-Case Review
294
.
3. Whether To Require A Technology Statement
300
.
4. Risk Sharing
303
.
5. Other Technology-Related Issues
308
.
F. Transmission Organization Incentive
312
.
1. Background
312
.
2. Comments
314
.
3. Commission Determination
326
.
G. Recovery of Prudently Incurred Costs to Comply with Reliability Standards and Recovery of Prudently Incurred Costs Associated with Transmission Infrastructure Development
334
.
1. Background
334
.
2. Comments
336
.
3. Commission Determination
343
.
H. Public Power
349
.
1. Background
349
.
2. Comments
350
.
3. Commission Determination
354
.
V. Reporting Requirement
358
.
A. Background
358
.
B. Comments
360
.
C. Commission Determination
367
.
VI. Other Issues
377
.
A. Rate Related Issues
377
.
1. Rate Related Issues
377
.
B. Section 35.34
395
.
1. The Proposal to Eliminate Section 35.34(e)
395
.
VII. Information Collection Statement
406
.
VIII. Environmental Statement
410
.
IX. Regulatory Flexibility Act Certification
411
.
X. Document Availability
412
.
XI. Effective Date and Congressional Notification
415
.
Appendices
Before Commissioners: Joseph T. Kelliher, Chairman; Nora Mead Brownell, and Suedeen G. Kelly.
I. Introduction
1. Pursuant to the directives in section 1241 of the Energy Policy Act of 2005 (EPAct 2005)
1
which added a new section 219 to the Federal Power Act (FPA), in this Final Rule the Commission provides incentives for transmission infrastructure investment that will help ensure the reliability of the bulk power transmission system in the United States and reduce the cost of delivered power to customers by reducing transmission congestion. The Rule does not grant outright any incentives to any public utility, but rather identifies specific incentives that the Commission will allow when justified in the context of individual declaratory orders or section 205 filings by public utilities under the FPA. A number of these incentives reflect departures from what the Commission has permitted in the past and a willingness to consider much greater flexibility with respect to the nature and timing of rate recovery for needed transmission infrastructure. While the Commission in recent years has permitted higher rates of return and deviations from past ratemaking practices in a few individual transmission infrastructure cases,
2
we here determine generically that these types of ratemaking options and others should be considered on a broader basis for those applicants that can demonstrate that their infrastructure proposals meet section 219 requirements.
1
Energy Policy Act of 2005, Pub. L. No. 109-58, 119 Stat. 594, 315 and 1283 (2005).
2
See Western Area Power,
99 FERC ¶ 61,306,
reh'g denied,
100 FERC ¶ 61,331 (2002) (
Western
),
aff'd sub nom. Public Utilities Commission of the State of California
v.
FERC,
367 F.3d 925 (D.C. Cir. 2004);
Michigan Electric Transmission Co., LLC,
105 FERC ¶ 61,214 (2003) (
METC
);
American Transmission Company, L.L.C.,
105 FERC ¶ 61,388 (2003) (
American Transmission
);
ITC Holdings Corp.,
102 FERC ¶ 61,182,
reh'g denied,
104 FERC ¶ 61,033 (2003) (
ITC Holdings
).
2. In reaching our determinations in this Final Rule, we have considered comments that reflect widely divergent views with respect to whether and when utilities should receive incentives and what they must demonstrate in order to receive particular incentives. As noted, the Rule does not grant incentives to any public utility but instead permits an applicant to tailor its proposed incentives to the type of transmission investments being made and to demonstrate that its proposal meets the requirements of section 219. Further, under the Rule, the Commission will permit incentives only if the incentive package as a whole results in a just and reasonable rate. For example, an incentive rate of return sought by an applicant must be within a range of reasonable returns and the rate proposal as a whole must be within the zone of reasonableness before it will be approved.
3. An important component of this Rule is the willingness to provide procedural flexibility, including the use of expedited declaratory orders on permitted ratemaking treatments, to help with financing and up-front regulatory certainty for project investments. We are particularly attuned to the need for flexibility to support long-distance interstate projects that significantly reduce the cost of delivered power by reducing transmission congestion on the interstate grid.
4. The Final Rule provides incentive-based rate treatments to any public utility transmitting electric energy in interstate commerce that meets the requirements of section 219 and this Final Rule. The Commission will not limit an applicant's ability to seek incentive-based rate treatments based on corporate structure or ownership. In addition, the Final Rule provides additional incentives, to the extent within our jurisdiction,
3
to any transmitting utility or electric utility transmitting electric energy in interstate commerce that joins a Transmission Organization.
4
Finally, as explained below, to the extent our jurisdiction allows, we encourage public power entities to take advantage of the incentive-based rate treatments outlined in the Final Rule.
3
With regard to non-public utilities, although the Commission's regulatory authority is bound by statute, such entities could be covered by a public utility's incentive rate proposal by a separate agreement between the public utility and a non-public utility.
See Bonneville Power Administration, et al.
v.
FERC,
422 F.3d 408 (9th Cir. 2005).
4
Transmission Organization is defined in 18 CFR 35.35(a)(2) of this Final Rule as “a Regional Transmission Organization, Independent System Operator, independent transmission provider, or other transmission organization finally approved by the Commission for the operation of transmission facilities.” Electric Utility is defined in section 3(22) of the FPA as “any person or State agency (including any municipality) which sells electric energy; such term includes the Tennessee Valley Authority, but does not include any Federal power marketing agency.” 16 U.S.C. 796(22). Transmitting Utility is defined in section 3(23) of the FPA as “any electric utility, qualifying cogeneration facility, qualifying small power production facility, or Federal power marketing agency which owns or operates electric power transmission facilities which are used for the sale of electric energy at wholesale.” 16 U.S.C. 796(23).
5. Some commenters have argued that few or no incentives are needed to encourage new transmission investment. We reject these comments as fundamentally inconsistent with section 219. Section 219 reflects Congress' determination that the Commission's traditional ratemaking policies may not be sufficient to encourage new transmission infrastructure. Although section 219 does not permit approval of rates that are inconsistent with section 205 or 206, section 219 nonetheless constitutes a clear directive that “the Commission
shall
establish, by rule, incentive-based * * * rate treatments * * * for the purpose of benefiting consumers by ensuring reliability and reducing the cost of delivered power by reducing transmission congestion” (emphasis added). We therefore cannot simply rely on existing ratemaking policy to faithfully implement section 219. This Final Rule therefore identifies a non-exclusive list of ratemaking reforms and requires applicants to tailor their proposals to fit the facts of their particular case.
6. We do agree, however, with the position of certain wholesale customers and state commissions that the Commission should not provide incentives that only serve to increase rates without providing any real incentives to construct new transmission infrastructure. Section 219(a) states that transmission incentives should be “
benefiting consumers
by ensuring reliability and reducing the cost of delivered power by reducing transmission congestion” (emphasis added). The purpose of our Rule is to benefit customers by providing real incentives to encourage new infrastructure, not simply increasing rates in a manner that has no correlation to encouraging new investment. The Final Rule, therefore, makes clear that not every incentive identified herein will be necessary or appropriate for every new transmission investment. To provide guidance in this regard to potential applicants, we discuss below why certain incentives may, as a general matter, be better tailored to certain types of investments than others.
II. Background
7. Section 219 of the FPA requires the Commission to establish, by rule, incentive-based (including performance-based) rate treatments for the transmission of electric energy in interstate commerce by public utilities for the purpose of benefiting consumers by ensuring reliability and reducing the cost of delivered power by reducing transmission congestion. Section 219(b) requires that the rule:
1. Promote reliable and economically efficient transmission and generation of electricity by promoting capital investment in the enlargement, improvement, maintenance, and operation of all facilities for the transmission of electric energy in interstate commerce, regardless of the ownership of the facilities;
2. Provide a return on equity that attracts new investment in transmission facilities (including related transmission technologies);
3. Encourage deployment of transmission technologies and other measures to increase the capacity and efficiency of existing transmission facilities and improve the operation of the facilities; and
4. Allow the recovery of all prudently incurred costs necessary to comply with mandatory reliability standards issued pursuant to section 215 of the FPA, and all prudently incurred costs related to transmission infrastructure development, pursuant to section 216 of the FPA (transmission national interest corridors).
8. Section 219(c) requires that the Rule provide for incentives to each transmitting utility or electric utility that joins a Transmission Organization and to ensure that any recoverable costs associated with joining may be recovered through transmission rates charged by the utility or through the transmission rates charged by the Transmission Organization that provides transmission service to the utility. Finally, section 219(d) provides that all rates approved under the Rule are subject to the requirements of sections 205 and 206 of the FPA,
5
which require that all rates, charges, terms and conditions be just and reasonable and not unduly discriminatory or preferential.
5
16 U.S.C. 824(d) and 824(e) (2000).
9. Congress directed the Commission to issue a Final Rule establishing incentive-based rate treatments for transmission construction within one year of enactment of EPAct 2005, or by August 8, 2006. The Commission issued a Notice of Proposed Rulemaking (NOPR) on November 18, 2005 seeking comment on the Commission's proposal to comply with section 219.
6
In the NOPR, the Commission proposed to amend Part 35 of Chapter I, Title 18 of the
Code of Federal Regulations
by eliminating paragraph 35.34(e) under Subpart F and adding paragraph 35.35 under Subpart G. The Commission received several hundred pages of comments. A list of the commenters appears in Appendix B. As explained below, based on the comments filed, the Commission clarifies and adopts the proposed regulations in the NOPR.
6
Promoting Transmission Investment Through Pricing Reform,
70 FR 71409 (Nov. 29, 2005), FERC Stats. & Regs., Proposed Regs. ¶ 32,593 (2005).
III. Overview
A. The Need for New Transmission Facilities
1. Background
10. As indicated in the NOPR, investment in transmission facilities in real dollar terms declined significantly between 1975 and 1998. Although the amount of investment has increased somewhat in the past few years, data for the most recent year available, 2003, shows investment levels still below the 1975 level in real dollars.
7
This decline in transmission investment in real dollars has occurred while the electric load using the nation's grid more than doubled.
8
Further, the record shows that the growth rate in transmission mileage since 1999 is not sufficient to meet the expected 50 percent growth in consumer demand for electricity over the next two decades.
9
7
EEI Survey of Transmission Investment: Historical and Planned Capital Expenditures (1999-2008) at 3 (2005).
8
Barriers to Transmission Investment, Presentation by Brendan Kirby (U.S. Department of Energy, Oak Ridge National Laboratory), April 22, 2005 Technical Conference, Transmission Independence and Investment, Docket No. AD05-5-000 (April 22, 2005 Technical Conference).
9
Energy Policy Act of 2005: Hearings before the House Subcommittee on Energy and Commerce, 109th Congress, First Sess. (2005) (Prepared statement of Thomas R. Kuhn, President of EEI).
2. Comments
11. Many commenters agree that there is a significant need for new investment in transmission facilities. EEI states that, although increases in transmission investment are predicted over the 2004 to 2008 period, the industry still has not reached the optimal level of investment.
10
International Transmission notes that growth in transmission capacity has lagged behind the growth in peak demand over the last three decades and this trend is projected to continue through at least 2012.
11
International Transmission cites to studies estimating the cost of power interruptions and fluctuations to range from between $29 billion and $135 billion annually,
12
the cost of the August 2003 Northeast-Midwest blackout to be between $4 billion and $10 billion,
13
congestion costs of $4.8 billion in the ISO/RTO markets of California, New York, New England, the Midwest and PJM for 1999 to 2002,
14
and increases in PJM congestion costs, from $499 million in 2003 to $808 million in 2004.
15
10
2004 State of the Markets Report, Federal Energy Regulatory Commission, Staff Report by the Office of Market Oversight and Investigations, June 2005, at p 27.
11
See
Eric Hirst, U.S. Transmission Capacity: Present Status and Future Prospects, a study prepared for EEI and the U.S. Department of Energy Office of Electric Transmission and Distribution, June 2004 (Hirst) and Keeping Energy Flowing: Ensuring a Strong Transmission System to Support Consumer Needs for Cost-Effectiveness, Security and Reliability, a report of the Consumer Energy Council of America, Transmission Infrastructure Forum, January 2005.
See also
Affidavit of Jon E. Jipping, Exhibit A to the Reply Comments of International Transmission (the transmission system purchased in Michigan was 2.5 to 7 years behind schedule in maintenance on key transmission facilities).
12
Kristina LaCommare and Joseph Eto, Understanding the Cost of Power Interruptions to U.S. Electricity Consumers, Lawrence Berkeley National Laboratory (September 2004) at xiv.
13
See
Final Report on the August 14, 2003 Blackout in the United States and Canada by the U.S.-Canada Power System Outage Task Force (April 2004) at 1.
14
See
Hirst at 8.
15
See
2004 PJM State of the Market Report at 37 (March 8, 2005).
12. Many transmission users and state commissions also agree that there is a need for additional investment in transmission infrastructure.
16
16
E.g.,
TDU Systems, APPA, and Maryland Commission.
13. However, some commenters dispute the need for new transmission investment. They assert the Commission has overlooked that investment in transmission has increased in recent years.
17
They also contend that investment in transmission by utilities in RTOs and ISOs has been significant, citing to the approximately $2 billion of approved spending in PJM since 2000. E.ON U.S. asserts that wide-spread system shortages have rarely occurred during the past 40 or more years, and that there does not appear to be any trend line that would suggest that it is becoming a serious problem now.
17
E.g.,
NASUCA and Connecticut DPUC.
3. Commission Determination
14. The issue of whether there is a need for new transmission investment that is sufficient to justify transmission incentives was put to rest by section 219. Section 219 mandates that the Commission “establish, by rule, incentive-based (including performance-based) rate treatments” and, in doing so, “promote reliable and economically efficient transmission and generation of electricity by
promoting capital investment
in the enlargement, improvement, maintenance, and operation of all facilities for the transmission of electric energy in interstate commerce” (emphasis added). If this were not enough, the legislative
mandate of section 219 is supported by abundant evidence, as discussed above, including the fact that transmission investment in real dollars terms is lower today than it was in 1975 when the load was significantly smaller and that, even with the transmission additions of recent years, the industry still incurs significant congestion costs due to inadequate transmission.
B. The Need for Incentives
1. Background
15. In section 219(a) of the FPA, Congress directed the Commission to establish incentive-based rate treatments to foster investment in transmission facilities.
2. Comments
16. Several commenters argue that incentive-based rates are not necessary to encourage transmission construction or that incentives will not accomplish the intended goal.
18
Others assert that reliance on incentives may increase the price of electricity without any real benefit.
19
18
E.g.,
APPA, TAPS, NECOE, E.ON U.S., NARUC, and New Jersey Board.
19
E.g.,
Connecticut DPUC, NASUCA, NECPUC, Delaware Commission, Missouri Commission, and New Mexico AG.
17. Commenters urge the Commission to limit the scope of any incentive-based treatments or to adopt mechanisms to ensure that they have their intended effect. For example, the New Mexico AG and TAPS assert that the Commission may implement an incentive-based mechanism by penalizing utilities or RTOs that fail to make investments necessary to ensure the reliability of the transmission grid. The Delaware Commission contends that providing incentives without assessing penalties for failure to meet obligations violates the just and reasonable standard. NASUCA states that it is unfair to provide incentives that increase utility profits but do not hold applicants accountable for performance. The Missouri Commission proposes that the Commission implement a process that determines performance-based return on equity. Other commenters recommend that the Commission make approval of any incentives conditional on the applicant showing a need for the incentive or that the facility would not have been built absent the incentive.
18. In contrast, a number of commenters, including EEI and a large number of utility and Transco commenters, argue that incentives are needed to foster investment in transmission facilities. EEI asserts that incentives are needed to stimulate planning and investment in national interest electric transmission corridors. NU states that the many risk factors associated with transmission investments, such as considerable time delays, negative public opinion of transmission construction, state siting uncertainties and recovery of project costs, justify incentives.
3. Commission Determination
19. Here again, the fundamental issue raised by certain commenters—whether transmission incentives are necessary to encourage new infrastructure—was put to rest by the plain language of section 219(a), which requires the Commission issue a rule that adopts “incentive-based * * * rate treatments.” Certain commenters urge the Commission to adopt “penalties” in this rulemaking for entities that do not build sufficient transmission. We decline to do so here.
20. Other commenters do not oppose incentives outright, but rather are concerned with the extent to which incentives may increase rates to consumers. Those concerns are premature. The Final Rule does not grant incentive-based rate treatments or authorize any entity to recover incentives in its rates. Rather, it informs potential applicants of incentives that the Commission is willing to allow when justified. Before adopting any incentive-based rate treatments for a particular company, the Commission will need to determine that the applicant has justified its specific incentive request. In addition, although the Commission intends to provide flexible procedural mechanisms by which an applicant may obtain an early determination of which incentives it may receive (
e.g.
, through an expedited declaratory order proceeding), before recovering any incentives in its rates, specific rates must be approved under section 205 of the FPA.
C. Summary of the Nature and Applicability of Incentives Adopted by the Final Rule
21. The incentives adopted by this Final Rule are properly understood only in the context of the traditional regulatory principles they seek to further. The longstanding rule is that utility rate regulation must adequately balance both consumer and investor interests. It is not enough to ensure that investors are properly compensated, and it is not enough to ensure that consumers are protected against excessive rates. Our policies must ensure both outcomes and, in doing so, strike the appropriate balance between these twin objectives. In striking that balance, the courts have recognized that there is no single formula for establishing a just and reasonable rate. Rather, the test is whether the “end result” is just and reasonable.
20
20
See FPC
v.
Hope Natural Gas Co.,
320 U.S. 591, 602-03 (1944).
22. The traditional policies that we re-examine here reflect both fundamental precepts: the need to balance investor and consumer interests and the recognition that there is no single formula for doing so. For example, in ensuring that rates produce adequate returns for investors, we do not set a single return on equity for all public utilities, nor do we presume that there is only one return on equity that is appropriate for any individual utility. Rather, our precedents require the establishment of a range of returns and we select an ROE within that range that reflects the facts and circumstances of a particular case. Similarly, our policies regarding the recovery of Construction Work in Progress (CWIP) seek to balance investor and consumer interests by allowing, in the typical case, 50 percent of CWIP in rate base. This policy balances investor and consumer interests in the ordinary case by permitting investors recovery of some construction costs on a current basis while also protecting consumers against full rate recovery before a particular facility is placed into service.
23. Our procedural regulations respecting rate recovery also seek to balance investor and consumer interests. For example, we allow public utilities to determine, as a general matter, the timing and frequency of when to seek a rate increase, which ensures that investors can file a rate increase when current rates are no longer adequate (
e.g.
, when the utility is undergoing a large construction program). However, we also typically require a utility seeking a rate increase to expose all of its costs to review and therefore do not generally permit “single issue” rate filings (selective rate adjustment).
24. Section 219 requires the Commission to re-examine these and other policies to determine whether they continue to strike the appropriate balance in encouraging new transmission investment given the significant need for new transmission infrastructure in the Nation. We do so in recognition of the unique and substantial challenges faced by large new transmission projects. Siting major new transmission lines is extraordinarily difficult, given the environmental and land use concerns associated with obtaining and permitting new rights-of-way. The
experience of American Electric Power Corp. in taking 16 years to complete construction of a new high-voltage transmission line from Wyoming County, West Virginia to Jackson Ferry, Virginia represents an extreme example, but it is illustrative of the significant risks and challenges associated with siting large new transmission projects.
21
21
Although new section 216 of the FPA improves the siting process for certain new projects, it does not eliminate all risks faced by such projects nor does it address the risks faced by other projects that do not reside in a national interest transmission corridor.
25. These challenges and risks are underscored by the fact that, in many instances, new transmission projects will not be financed and constructed in the traditional manner. New transmission is needed to connect new generation sources and to reduce congestion. However, because there is a competitive market for new generation facilities, these new generation resources may be constructed anywhere in a region that is economic with respect to fuel sources or other siting considerations (
e.g.
, proximity to wind currents), not simply on a “local” basis within each utility's service territory. To integrate this new generation into the regional power grid, new regional high voltage transmission facilities will often be necessary and, importantly, no single utility will be “obligated” to build such facilities. Indeed, many of these projects may be too large for a single load serving entity to finance. Thus, for the Nation to be able to integrate the next generation of resources, we must encourage investors to take the risks associated with constructing large new transmission projects that can integrate new generation and otherwise reduce congestion and increase reliability. Our policies also must encourage all other needed transmission investments, whether they are regional or local, designed to improve reliability or to lower the delivered cost of power.
26. To address the substantial challenges and risks in constructing new transmission, the Final Rule identifies instances where our regulatory policies may no longer strike the appropriate balance in encouraging new investment. The Final Rule identifies several policies that should be adjusted, where appropriate on the facts of a particular case, to encourage new transmission investment or otherwise remove impediments to such investment. Although each reform adopted by the Final Rule constitutes an “incentive” as that term is used by section 219, this label has caused some confusion in the comments. It is true that our reforms adopted in the Final Rule provide “incentives” to construct new transmission, but they do not constitute an “incentive” in the sense of a “bonus” for good behavior. Rather, as we explain below, each will be applied in a manner that is rationally tailored to the risks and challenges faced in constructing new transmission. Not every incentive will be available for every new investment. Rather, each applicant must demonstrate that there is a nexus between the incentive sought and the investment being made. Our reforms therefore continue to meet the just and reasonable standard by achieving the proper balance between consumer and investor interests on the facts of a particular case and considering the fact that our traditional policies have not adequately encouraged the construction of new transmission.
27. A few examples will illustrate this point. The Final Rule permits higher returns on equity for certain transmission investments. This may be appropriate in several contexts, such as where the risks of a particular project exceed the normal risks undertaken by a utility (and hence are not reflected in a traditional discounted cash flow (DCF) analysis) and where necessary to encourage creation of a Transco or participation in a Transmission Organization. However, this does not mean that every new transmission investment should receive a higher return than otherwise would be the case. For example, routine investments to meet existing reliability standards may not always, for the reasons discussed below, qualify for an incentive-based ROE.
28. The Final Rule also adopts incentives that are designed to reduce the risks of new investments. For example, the Final Rule provides that the Commission will provide assurance of recovery of abandoned plant costs if the project is abandoned for reasons outside the control of the public utility. Although this qualifies as an “incentive” under section 219, it is perhaps more properly characterized as reducing a regulatory barrier—the potential lack of recovery of costs— to infrastructure development. Moreover, this reform adequately balances consumer and investor interests because it is available only when a project is abandoned for reasons beyond the control of the public utility.
29. Our Final Rule also adopts certain reforms that affect the timing of recovery of new transmission investments. Given the long lead time required to construct new transmission, and the associated cash flow difficulties faced by many entities wishing to invest in new transmission, the Final Rule provides that, where appropriate, the Commission will allow for the recovery of 100 percent of CWIP in rate base. Here again, we seek to remove an impediment—inadequate cash flow—that our current regulations can present to those investing in new transmission. We also will permit, where appropriate, the recovery of the costs of new transmission through a single issue rate filing without requiring the public utility to re-open all its transmission rates to review. We do not, however, suggest that such selective rate adjustments will be appropriate in all cases, as discussed in more detail below. Rather, as with each incentive adopted by the Final Rule, an applicant must show that there is a nexus between its proposal to make a single issue rate adjustment and the facts of its particular case.
D. Effective Date and Duration of Effectiveness For Incentives
1. Background
30. Congress directed the Commission to issue a rule establishing incentive-based rate treatments no later than one year after enactment of EPAct 2005, or by August 8, 2006.
2. Comments
31. Certain commenters urge the Commission to apply the rule to investments made before August 8, 2005 while others ask the Commission to apply the rule to investments made after August 8, 2005.
22
Certain commenters argue that the Commission should not approve incentives for facilities that are pending at the time the Final Rule becomes effective, while others request that the Commission not allow incentives for investment in facilities that an applicant already has committed to build or for Transcos that already exist.
23
22
E.g.
, Progress, NEMA, and PG&E.
23
E.g.
, PG&E, Connecticut DPUC, NASUCA, TDU Systems and TANC.
32. Several commenters argue that, once the incentives have been granted, the Commission should not eliminate them, or should do so only under very limited circumstances.
24
In contrast, others argue that the Commission should grant incentives for a specific time period or retain the flexibility to change or review any incentives if it is found the incentives provide no customer benefit.
25
The California Oversight Board requests that any
authorized incentives be subject to refund.
24
E.g.
, Progress, NEMA, EEI, Trans-Elect, and National Grid.
25
E.g.
, TANC, Snohomish, Municipal Commenters, and TDU Systems.
33. KKR explains that, under certain circumstances, investors in transmission assets may need favorable rate treatment for a sufficient period of time to ensure an appropriate return on their capital,
i.e.
, for a 15 to 30-year period.
26
KKR recommends that public utilities requesting incentive treatment for an extended period into the future propose criteria that can be used to evaluate that entity's performance during periodic evaluations. KKR notes that applicants may not always be able to meet certain proposed metrics due to circumstances beyond their control. For example, a transmission owner should not lose its incentive rate treatments if it does not succeed in meeting desired reductions in congestion because the applicant may not have complete control of the factors affecting congestion, such as generation additions, changes in load location and operation of neighboring systems, and RTO policies. KKR emphasizes that the Commission should retain the flexibility to assess an applicant's proposal as the facts and circumstances will vary case-by-case. Finally, KKR recommends that applicants be required to file a report on their performance every several years and that the Commission may initiate a proceeding to review incentives only if the criteria are not met. KKR explains that frequent reviews run the risk of distorting results due to the “lumpiness” of capital investment and the long time periods to make capital additions and for capital additions to have effects. Further, KKR states that frequent reviews will make long-term investments more uncertain and, hence, less likely. In supplemental comments, KKR asserts that higher ROEs are of material value for Transcos only when long-term. KKR cites International Transmission as an example, noting that it is only able to invest in excess of every dollar it earns back into its system due to the certainty afforded it by its rate compact, which is long-term, formula-based, and includes a reasonable ROE. The certainty and long-term horizon of International Transmission's rates give debt and equity investors in International Transmission comfort that they will ultimately receive an adequate return on their capital.
26
See also
National Grid and EEI.
3. Commission Determination
34. Section 219 of the FPA became effective on August 8, 2005. Codification of section 219 on that date and the requirement for a rule authorizing investment incentives provided notice to the industry that Congress intended that the Commission provide incentive-based rate treatments promptly. Thus, the Final Rule will become effective 60 days after publication in the
Federal Register
. However, we clarify that any investment made in, or costs incurred for, transmission infrastructure after August 8, 2005 that ensures reliability or lowers the cost of delivered power by reducing transmission congestion will be eligible for incentive-based rate treatments under this Rule. Applicants seeking incentive-based rate treatments for investments made or costs incurred after August 8, 2005 will need to satisfy the requirements of this Rule to obtain and recover any incentives and will need to make an appropriate filing under section 205.
35. The fact that a proposed expansion was in a utility's expansion plan as of August 8, 2005 does not disqualify the project for incentive treatment. Inclusion of a facility in a plan does not mean that a project can or will get built. Even where a project already has been planned or announced, the granting of incentives may help in securing financing for the project or may bring the project to completion sooner than originally anticipated. Congress's directive that the Commission issue a rule within one year of enactment of EPAct 2005 shows that Congress intended for the Commission to take steps to bring new transmission on line expeditiously.
36. With respect to the issue of how long an incentive-based proposal should remain in effect, the Commission recognizes that it may be necessary to authorize incentives that may extend over several years in order to support investment in long-term transmission. It can be important to investors making long-term investments in long-lived facilities to be assured that a ratemaking proposal adopted prior to construction of those facilities will not later be altered in a manner that undermines the basis for the financing of those facilities. The Commission will therefore allow applicants to propose specific time periods by which their incentive-based proposals will not be “re-opened” in a manner incompatible with the nature of the initial approvals. However, to ensure that ratepayers are also adequately protected, we will require any applicants seeking such a fixed term for its plan to explain how ratepayers can be assured that such a plan is delivering the benefits that formed the basis for the Commission's initial approval of it. For example, an applicant may propose periodic progress assessments with appropriate metrics to measure how well the project is progressing and whether the proposed investment in new transmission is improving reliability or reducing congestion. Such metrics would provide the Commission a means to determine whether and how the applicant is providing the anticipated benefits and thus that the approved incentives need not be revisited. Because the scope and size of each project will differ, any applicant seeking incentive-based rate treatments may propose metrics for its project as well as the frequency for review of those metrics.
27
An applicant may include its proposed metrics and any timetable for review in its section 205 rate filing seeking recovery of incentives.
28
Where such metrics are found to be needed and are approved by the Commission, an applicant would be required to submit information filings to the Commission consistent with the approved metrics and timetable. We clarify, however, that the metrics reviews will not be opportunities to re-argue the issues addressed in proceedings granting the incentive-based rates; they are for the purpose of measuring whether the plan is being implemented as initially approved.
27
The information may include, as well as supplement, information provided in FERC-730, discussed in section V below.
28
An applicant has the option to include metrics proposals in a declaratory order proceeding, but would also need to include them in the subsequent section 205 rate filing.
IV. Discussion
A. Standard for Approval of Incentive-Based Rate Treatments
1. The Final Rule Applies to the Recovery of Costs Incurred to Ensure Reliability or to Reduce Transmission Congestion, or Both.
a. Background
37. Proposed § 35.35(d)(1) specifies that the Commission will authorize incentive-based rate treatments for investment by public utilities, including Transcos, in new transmission capacity that reduces the cost of delivered power by reducing congestion or promotes reliability, as demonstrated in an application to the Commission.
b. Comments
38. Many commenters urge the Commission to be flexible in applying the incentives.
29
Southern and the Nevada Companies assert the Commission should not require that facilities both improve regional reliability and reduce congestion to be eligible for an incentive ROE. They
argue that the guiding factor should be to provide incentives that improve regional reliability and/or reduce transmission congestion. AEP urges the Commission to adopt a functional approach to determine whether a project qualifies for incentives. For example, AEP suggests that projects that connect newer technology generation or renewables be eligible for incentives. Upper Great Plains contends that incentives should be available for projects that support the development of new electric generation in recognition of the expected growth in electric consumption and the need for additional investment to keep pace.
29
E.g.
, FirstEnergy, Southern, Nevada Companies, AEP.
39. Several commenters urge the Commission to establish criteria for transmission projects to demonstrate that they achieve Congress' goals before projects receive an incentive.
30
The New York Commission asks the Commission to convene a technical conference to develop the criteria.
30
E.g.
, AEP and New York Commission.
40. The Maryland Commission supports incentives that are forward-looking and targeted to support electric reliability, competitive markets and diversity in fuel sources, including renewable resources, in the short and long term.
c. Commission Determination
41. The purpose of section 219 of the FPA is to benefit consumers by promoting transmission capital investments that result in reliable and economically efficient transmission and generation. Congress did not enact section 219 in isolation. Section 219 is a part of a larger statutory framework in which Congress directed the Commission to take steps to address reliability of the bulk power system as well as to remedy the adverse effects of transmission congestion. For example, in new section 215 of the FPA Congress enacted a regulatory regime under which the Commission will, for the first time in its history, approve and enforce mandatory reliability standards for the nation's power grid.
31
In new section 216, Congress directed the Secretary of Energy to identify areas of the nation in which transmission congestion adversely affects consumers (national interest electric transmission corridors) and gave the Commission certain permitting authority to ensure timely construction of transmission facilities to remedy transmission congestion in those corridors. In section 1223 of EPAct 2005, Congress directed the Commission to encourage the deployment of advanced transmission technologies that increase the capacity, efficiency and reliability of an existing or new transmission facility. In enacting these provisions of EPAct, Congress made clear that it was equally concerned with reliability as well as the adverse impacts of transmission congestion and that the Commission should take steps to address both issues. New FPA section 219, which is complementary to these other EPAct provisions, directs the Commission to provide rate incentives for the purpose of ensuring reliability and reducing transmission congestion. However, nowhere in section 219 does the language say that the Commission may provide incentives only to applicants that propose to both improve reliability and reduce congestion. In fact, we believe it would be contrary to the intent of the new provisions, taken together, to limit incentives this way.
31
See
Order No. 672, Rules Concerning Certification of the Electric Reliability Organization; and Procedures or the Establishment, Approval, and Enforcement of Electric Reliability Standards, 71 FR 8662 (Feb. 17, 2006), FERC Stats. & Regs. ¶ 31,204 (2006).
42. Consistent with the overall goals of Congress in EPAct 2005, and in particular its focus on reliability improvements and relief of transmission congestion, we interpret section 219 to promote capital investment in a wide range of infrastructure investments that can have either reliability or congestion benefits rather than investments that have both reliability and congestion benefits. The alternative to this reading would be to apply section 219 in a manner that would deny incentive-based rate treatments to a transmission facility that significantly enhances reliability but does not reduce the cost of delivered power by reducing transmission congestion. This would be contrary to a fundamental goal of EPAct 2005 to improve reliability of the interstate transmission grid. We do not consider such an interpretation to be reasonable. In any event, we expect there will be few transmission projects that provide one type of benefit but not the other.
43. Commenters seeking a narrow reading of section 219 are primarily concerned with the impact of any incentive-based rate treatment on an applicant's rates. These concerns are premature. Before the Commission will permit any applicant to recover incentives in its rates, the Commission will evaluate the rate impact under section 205 or 206 of the FPA. Interested parties may raise any rate concerns at that time. Further, our case-by-case approach ensures that the incentives granted will be tailored to particular circumstances. Finally, except for the rebuttable presumptions addressed below, we will not at this time establish more detailed criteria an applicant must meet to be eligible for incentive-based rate treatments. Establishing criteria now would limit the flexibility of the Rule or improperly pre-judge which projects are acceptable for incentives. The Commission will, on a case-by-case basis, require each applicant to justify the incentives it requests. Because these proceedings will provide ample opportunity for parties to comment on any incentive proposal, we do not see the need for a technical conference or detailed criteria now. This notwithstanding, we provide certain guidance, as described below, regarding the types of projects that may be particularly well suited to certain incentives and others that may not.
2. Other Criteria For Approval of Incentives
a. Comments
44. Numerous commenters seek additional conditions to be considered in the grant of incentives. Some argue that the number of incentives should be limited while others recommend additional criteria that an applicant must satisfy
32
or that the incentives be limited to certain types of facilities. For example, TDU Systems assert that the Final Rule should specifically identify other incentives that will be considered under § 35.35(d)(viii) and specify the parameters for eligibility for the incentives. EEI, however, contends the Commission should allow individual companies to propose any incentives on a case-by-case basis because the individual companies are in a better position to understand the efficacy of particular incentive mechanisms. Similarly, National Grid requests clarification that the incentives are not mutually exclusive and transmission owners should be free to propose customized rate packages that include one or more of the incentives in combination.
32
E.g.
, East Texas, TANC, and TAPS.
45. With regard to additional conditions, some commenters argue, for example, that the Commission should authorize incentives only for proposals that recognize regional differences, that are the product of an open and inclusive regional transmission planning process, increase network capacity, or that respond to specific reliability or congestion concerns. TANC argues that the Commission should limit qualification for the incentives to those transmission projects that are 200 kV and above. NECOE argues that incentives should be provided to
utilities that conform to good utility practice and minimize total costs. Also, NECOE asserts that, when more than one incentive is requested, the Commission should require the applicant to demonstrate why a single, appropriately targeted incentive is insufficient. Several commenters urge the Commission to grant incentives for existing facilities and for maintenance of existing facilities.
33
The Southern Companies state that the Commission should grant incentives to proposals that resolve a significant inter or intra-regional constraint, or preclude or mitigate anticipated constraints that may or may not arise. Progress asserts that incentives should be granted to encourage installation of new software to better manage flowgates and calculate Available Transfer Capability values on existing transmission facilities. The Steel Manufacturers state that a utility does not deserve special rate treatment to maintain or upgrade its facility to comply with mandated reliability standards.
33
E.g.
, FirstEnergy, PSEG, AEP, EEI, Duquesne and MidAmerican.
46. Several commenters urge the Commission to condition any incentive-based rate treatment on the applicant, among other things, divesting the subject facility to a Transco, demonstrating that the subject facility solves congestion constraints on a regional basis or results in significant new transfer capacity, complying with the 1992 and 1994 Policy Statements, showing that the facilities would not have been built absent the incentives, or showing that the facilities were not already necessary to meet NERC reliability criteria or normal load growth.
34
PJM proposes a tiered procedure to determine whether incentives are warranted. TDU Systems recommend that incentives should be denied to public utilities that have refused to provide requested relief from transmission congestion in the form of transmission upgrades or otherwise, until such congestion is remedied without the incentive rates.
34
E.g.
, TDU Systems, APPA, TAPS, NRECA, NARUC, NASUCA, Connecticut DPUC, New Jersey Board, WPS.
47. Several commenters request that the Commission allow states to play a role in the approval or recovery of incentives because states may hinder recovery of incentives in bundled rates.
35
National Grid asserts that the Commission and states should have an alignment of interests on transmission investment and, therefore, there is no basis to believe that the rule will warrant shifts in states' roles.
35
E.g.,
CREPC, KCPL, Steel Manufacturers, Montana-Dakota, MidAmerican, and EEI.
b. Commission Determination
48. Congress has determined that there is a need for incentives, and has directed the Commission to issue a rule to provide them. Most of the prerequisites and preconditions raised in the comments reflect a desire to limit or circumscribe the nature or applicability of incentives that may be granted under the rule. We have considered these comments and do not believe that any of them should be adopted at this time. Some of them are consistent with our overall policy goals (such as the emphasis on regional planning) and, to that extent, we explain how we will factor those considerations into an analysis of a proposed incentive. However, some are inconsistent with the policy goals of section 219 because they will only serve to discourage transmission investment. Therefore, unless adopted in other sections of this rule, we will not require applicants to satisfy the requirements proposed in the comments. For example, we reject arguments that an applicant must show that, but for the incentives, the expansion would not occur. Those arguments are based on commenters' conclusions that the Commission's prior issuances (
i.e., Removing Obstacles
order, the 1992 Policy Statement, or the innovative rate proposal in Order No. 2000) required an applicant to show need prior to receiving incentives. However, the Final Rule is based on a clear directive from Congress that does not require an applicant to show that it would not build the facilities but for the incentives. This notwithstanding, we do require applicants to show some nexus between the incentives being requested and the investment being made,
i.e.
, to demonstrate that the incentives are rationally related to the investments being proposed.
49. We also consider our procedures for the approval of incentives to be comprehensive and, therefore, will not attempt to establish gradations regarding either approval requirements or the amount of incentive approved, as recommended by TANC, PJM, Industrial Consumers and others. Section 219 does not mandate higher returns for projects that are part of independent regional planning processes, nor does it require higher standards of review for projects that do not result from independent planning processes. As long as the project ensures reliability or reduces the cost of delivered power by reducing congestion, regardless of where it is located on the nationwide transmission grid, the project is eligible for incentive ratemaking.
50. We will not impose size limits on eligible transmission projects. Projects below 200 kV can have a significant impact on reliability or reduce congestion, and therefore would qualify for incentive treatment. We will also not condition approval of incentives on market power findings. Our regulations and penalties on market power and market behavior are sufficient inducements to ensure markets are not manipulated and, therefore, additional provisions are not necessary.
51. We will not deny incentives to public utilities that have not built transmission upgrades requested by transmission customers. The scope of this Rule is restricted to implementing the requirements of section 219; the appropriate means to address this issue is to file a complaint in a separate proceeding.
52. While the promotion of renewable energy projects supports other policy and regulatory objectives, we will not adopt separate rate-based incentives for renewable energy projects. Congress directed the Commission to issue a rule to ensure reliability or to reduce the cost of delivered power by reducing transmission congestion regardless of the nature of the energy carried over the new transmission facilities. We believe that, by providing incentives applicable to all transmission facilities, the Final Rule provides incentives for transmission to serve renewable resources and, therefore, additional incentives are not necessary.
53. Because section 219 provides a new directive to the Commission to permit greater incentives and does not on its face require an individual showing of need by incentive applicants, we will not require compliance with the 1992 or 1994 Transmission Policy Statements as a precondition for approval of incentives.
54. With regard to state review, the Commission recognizes that incentives for many utilities are incorporated into rates that must receive state commission approval and that many decisions on siting and permitting of new facilities are under the jurisdiction of state and local government authorities. Because of this, we will carefully consider the views of any state bodies having jurisdiction over these matters. We also will, as discussed below, adopt a rebuttable presumption that projects approved by an appropriate state commission or siting authority are eligible for incentives under section 219. We believe that, in these ways, we will appropriately coordinate our consideration of incentives with the
views of responsible state agencies. We will not, however, adopt any further requirements regarding state approval, such as the requirement that an applicant receive state approval of any proposed incentives. While state approval is desirable it is not required by section 219. However, if state approval of a particular plan is required, we expect that any applicant will seek that approval in due course.
55. Finally, we reiterate that an applicant may request any combination of the incentives listed in the Final Rule. Applicants also may request incentives that are not listed in the Final Rule. The Commission will not use the Final Rule to identify each and every incentive an applicant may request. However, this in no way relieves the applicant of fully supporting its rate request and demonstrating that its request for incentives satisfies section 219 and the requirements of this Final Rule. If an interested party believes a particular incentive is not warranted, it may raise its concerns when an applicant proposes that incentive in a declaratory order or in a section 205 rate application.
56. Because section 219 makes clear that the Final Rule should promote capital investment in the operation and maintenance of all facilities for the transmission of electric energy in interstate commerce, new investment in existing facilities will be eligible for incentive-based rate treatments.
36
The reliability benefits of operation and maintenance capital spending are obvious, and we expect applicants incurring this type of capital spending will be able to demonstrate reliability benefits and thereby be eligible for incentive treatment.
36
In addition, the Final Rule makes available incentives for joining a Transmission Organization.
3. Rebuttable Presumptions
57. As we discussed above, we will not adopt the variety of preconditions recommended by the commenters. However, we are nonetheless required to make findings that a particular investment falls within the scope of section 219. In making that finding, we have chosen to rely on existing processes to the extent practicable in determining whether a particular facility is needed to maintain reliability or reduce congestion. We describe these processes below and find that, if an applicant satisfies them, its project will be afforded a rebuttable presumption that it qualifies for transmission incentives. Other applicants not meeting these criteria may nonetheless demonstrate that their project is needed to maintain reliability or reduce congestion by presenting us a factual record that would support such findings. Once we determine that the project is eligible for incentives, we would, as described below, consider whether the particular incentives being proposed are appropriate for the particular investments being made.
58. The first rebuttable presumption we will adopt relates to regional planning. Although we will not require participation in regional planning processes as a precondition for obtaining incentives, as section 219 does not require such a precondition, we believe that regional planning processes can provide an efficient and comprehensive forum through which those seeking to make transmission investments can have their projects evaluated to see if they meet the requirements of section 219. Regional planning processes can help determine whether a given project is needed, whether it is the better solution, and whether it is the most cost-effective option in light of other alternatives (
e.g.
, generation, transmission and demand response). It does so by looking at a variety of options across a large geographic footprint; thus, regional planning can allow for a broad assessment of loop flows and impacts on neighboring systems. Regional Planning also can serve as a forum in which states can readily participate.
37
This benefit of a regional planning process is difficult to duplicate on a utility-by-utility basis. It may prove difficult for applicants, on an individual basis, to timely gain access to all the information that might be required to make a showing that the project ensures reliability and/or reduces the cost of delivered power by reducing congestion. The Commission expressly recognized the value of regional planning when it proposed to amend the pro forma Open Access Transmission Tariff of jurisdictional public utilities to require regional planning to ensure that transmission is planned and constructed on a nondiscriminatory basis to support reliable and economic service to all eligible customers in a region.
38
Consistent with our actions in that NOPR and our belief that power markets are regional in nature and that the transmission systems supporting those markets must be supported by regional planning, we will create a rebuttable presumption for projects that result from regional planning. Thus, the Commission will rebuttably presume that transmission projects that result from a fair and open regional planning process that considers and evaluates projects for reliability and/or congestion and is found to be acceptable to the Commission satisfy the requirements of this Rule.
39
In addition, the Commission will adopt the following other rebuttable presumptions. We will also attach a rebuttable presumption that an applicant has met the requirements of section 219 if a proposed project is located in a National Interest Electric Transmission Corridor or where a project has received construction approval from an appropriate state commission or state siting authority.
37
State representation in stakeholder committee is a feature of the Midwest ISO,
i.e.
, the Organization of MISO States (MISO States or OMS).
38
Preventing Undue Discrimination and Preference in Transmission Service,
Notice of Proposed Rulemaking, 71 FR 32,636 (June 6, 2006), FERC Stats. & Regs., Regs. Preambles ¶ 32,603 at P 36 (2006) (OATT Reform NOPR):
We conclude that the inadequacy of the existing obligation to conduct joint and regional transmission system planning, coupled with the lack of transparency surrounding system planning generally, require reform of the
pro forma
OATT to ensure that transmission infrastructure is constructed on a nondiscriminatory basis and is otherwise sufficient to support reliable and economic service to all eligible customers.
39
An applicant may wish to file a request for incentive treatment for a project which is undergoing consideration in a regional planning process. The Commission will consider such requests, but may make any requested rate treatment contingent upon the project being approved under the regional planning process. As discussed elsewhere in this Final Rule, different types of projects and the circumstances under which they are undertaken may warrant different rate treatments and incentives.
4. Applicants Seeking Incentive-Based Rates Will Not Be Required To File a Cost-Benefit Analysis
a. Background
59. The NOPR explained that no cost-benefit analysis would be required to obtain incentives because customers will be protected by the Commission's review of applications pursuant to sections 205, 206 and 219 of the FPA, which require that all rates be just and reasonable and not unduly discriminatory or preferential.
40
40
NOPR at P 16.
b. Comments
60. Certain commenters argue that judicial precedent requires that incentive rates be supported by a showing of a quantifiable relationship between the incentive and the result the incentive is intended to achieve
41
They also argue that the level of the incentive must be calibrated to a level that it is no more than needed to achieve the outcome that the incentive is supposed to produce.
42
They further argue that
section 219 does not require significant changes to the Commission's existing rules and ratemaking policies governing incentive rates, such as its 1992 Policy Statement
43
and Order No. 2000,
44
in which the Commission required that applications for incentives be supported with cost-benefit analyses. They contend that the Commission's existing rules and policies already satisfy the Commission's obligations under the FPA, even as amended by section 219, and should be retained.
45
41
E.g.,
NECOE, PSE&G, and WPC Companies.
42
E.g.,
NECOE.
43
Incentive Ratemaking for Interstate Natural Gas Pipelines, Oil Pipelines, and Electric Utilities: Policy Statement on Incentive Regulation,
61 FERC ¶ 61,168 at 61,590 (1992).
44
Regional Transmission Organizations,
Order No. 2000, 65 FR 809 (Jan. 6, 2000), FERC Stats. & Regs., Regulations Preambles July 1996-December 2000 ¶31,089 (1999),
order on reh'g,
Order No. 2000-A, 65 FR 12,088 (Mar. 8, 2000), FERC Stats. & Regs., Regulations Preambles July 1996-December 2000 ¶31,092 (2000),
aff'd sub nom. Public Utility District. No. 1 of Snohomish County, Washington v. FERC,
272 F.3d 607 (D.C. Cir. 2001).
45
E.g.,
TDU Systems, NRECA, NECOE, and SMUD.
61. Several commenters state that, without a cost-benefit analysis, the Commission has no basis for concluding that a particular incentive provides customers with a net benefit or will be just and reasonable.
46
The New York Commission suggests that criteria for a cost-benefit analysis be established through a separate technical conference or rulemaking.
46
E.g.,
NRECA, NARUC, TAPS, East Texas, Connecticut AG, Industrial Customers, NECPUC, California Oversight Board, MISO States, DTE Energy, Wyoming Consumer Advocate, and New York Commission.
62. PJM argues that the Commission should provide incentives for transmission owners' participation in robust regional transmission planning that identifies both the costs and economic benefits of a given project. PJM proposes that such a process should support a rebuttable presumption that the decision to build is prudent and warrants an ROE incentive.
63. East Texas states that utilities engaged in meeting reliability standards, constructing projects across designated corridors and joining qualified Transmission Organizations should be allowed the incentive rates on the simple showing that they seek to recover no more than their prudently incurred costs. SMUD states that, under section 219, an incentive is appropriate only when it results in lower power costs to consumers. The Oklahoma Commission states that the Commission should give direction as to the showing by applicants that is acceptable in lieu of the cost-benefit analysis.
64. Other commenters argue that a cost-benefit analysis is unnecessary.
47
National Grid states that the Commission already recognized generically the benefits of using ROE adders as an incentive for needed transmission investment in the
Removing Obstacles
order.
48
FirstEnergy asserts that consumers benefit by strengthening the transmission grid and by encouraging new investment in transmission and that the benefits of these factors potentially far exceed the costs. International Transmission asserts that requiring a cost-benefit analysis could delay needed transmission upgrades.
47
E.g.,
National Grid.
48
Removing Obstacles to Increased Electric Generation and Natural Gas Supply in the Western United States,
94 FERC ¶ 61,272,
reh'g denied,
95 FERC ¶ 61,225,
order on reh'g,
96 FERC ¶ 61,155,
further order on reh'g,
97 FERC ¶ 61,024 (2001).
c. Commission Determination
65. We reaffirm the NOPR's determination not to require applicants for incentive-based rate treatments to provide cost-benefit analyses. The courts have long recognized that a primary purpose of the FPA, and its counterpart the Natural Gas Act, is to encourage the orderly development of plentiful supplies of electricity and natural gas at reasonable prices.
49
To carry out this purpose, the Commission may consider non-cost factors as well as cost factors.
50
Moreover, Congress's enactment of section 219 reflects its determination that incentives generally can spur transmission investment which will, in turn, provide the benefits of a robust transmission system identified by the commenters. The Commission will consider the justness and reasonableness of any proposal for incentive rate treatment in individual proceedings.
49
See, e.g., Pub. Utilities Comm'n of the State of California
v.
FERC,
367 F.3d 925, 929 (D.C. Cir. 2004) (
CPUC
v.
FERC
),
citing NAACP
v.
FPC,
425 U.S. 662, 670 (1976).
50
Id., citing Permian Basin Area Rate Cases,
390 U.S. 747, 791, 815 (1968);
Maine Public Utilities Commission
v.
FERC,
No. 05-1001, slip op. at 19 (D.C. Cir., June 30, 2006).
5. Procedural Requirements for Obtaining Incentive-Based Rate Treatments
a. Background
66. Section 35.35(c) in the NOPR proposed that all rates approved under the rule would be subject to sections 205 and 206 of the FPA. Section 35.35(d) in the NOPR proposed certain options by which an applicant may seek incentive-based rate treatments. The NOPR proposed that applicants must explain whether the proposed facilities are part of an independent regional planning process. The Commission also sought comment on whether the Final Rule should establish a definition of “independent regional planning process” or if the Commission should consider this issue on a case-by-case basis.
b. Comments
67. Most transmission owners request that the Commission implement a streamlined process to review and approve incentive-based rate treatments. For example, some suggest that the Commission adopt a pre-approval procedure that provides a preliminary determination of a project's rate treatment, similar to the expedited pre-approval in the Path 15 upgrade in California,
51
to promote timely construction of additional needed transmission facilities.
52
51
See Western supra
note 2.
52
E.g.
, Mid-American, Nevada Companies, PacifiCorp, and Northwestern.
68. A number of commenters urge the Commission not to require transmission owners to make section 205 filings to implement incentive-based rates. They argue that such proceedings may result in unreasonable delay and uncertainty and thereby discourage, if not preclude, incentive-based rate proposals.
53
Many of these parties urge the Commission automatically to approve incentives once the facilities or investment have been shown to ensure reliability or reduce congestion.
54
Other commenters suggest that the Commission create a category of incentives that would not require any review under section 205 and then hold paper hearings only for those incentives that do not fall within the designated category of incentives.
55
Other commenters request that the Commission establish a rebuttable presumption that each incentive is just and reasonable or allow transmission owners to self-certify that they meet the criteria of section 219.
56
Others similarly ask that there be a presumption that facilities included in a regional planning process are eligible for incentives.
57
Another group of commenters argue that projects need not be part of an independent regional planning process to receive an incentive
because other regional processes will also provide the same benefits.
58
53
E.g.
, United Illuminating, Vectren, NSTAR, and EEI.
54
E.g.
, Nevada Companies and MidAmerican.
55
E.g.
, EEI, NU, New England TOs, NYSEG, and RGE.
56
E.g.
, Southern and FirstEnergy.
57
E.g.
, BG&E, PEPCO, KCPL, National Grid, PJM, PJM TOs, United Illuminating and Vectren.
58
E.g.
, EEI, Progress, Nevada Companies and FirstEnergy.
69. EEI argues that public utilities should be permitted to make limited section 205 filings to specifically address recovery of incentives in rates, regardless of the form of rate.
70. National Grid requests clarification that the Commission will continue to accept incentive and rate reforms that are tailored to the specific needs of the transmission owner, so that transmission owners can be allowed more traditional rate treatment, such as accruing the allowance for funds used during construction, capitalization of pre-commercial costs and a 30-year depreciation.
71. BG&E requests clarification that, once the Commission approves an incentive-based ROE for a particular regional planning process, any entity within that planning process will be authorized to receive the approved incentive-based ROE without being required to individually apply for, or rejustify, the incentive.
72. Some commenters argue that the Commission must review all elements of an applicant's cost of service before authorizing any incentives.
59
The Steel Manufacturers assert that applicants must justify each incentive they request under sections 205, 206, and 219 and that those applications seeking more than one incentive must demonstrate that the overall package results in rates that satisfy the same criteria.
59
E.g.
, Dairyland, TDU Systems, and NASUCA.
73. TAPS asserts that, when an applicant files a facility-specific incentive filing the load divisor and depreciation reserve should be updated, in the circumstance that existing rate inputs are known; and, if they are not known because they are part of a “black box” settlement, they should be imputed. TAPS suggests ways in which this can be done.
74. Snohomish argues that applicants should be required to submit a schedule of lower-cost alternatives, including potential non-wires solutions, and to explain why these alternatives were not chosen. The Oklahoma Commission recommends that state commissions make the determination as to whether the cost of the project, including the cost of the incentive, is more beneficial for ratepayers than if a generation facility were built closer to avoid the cost of transmission.
75. Finally, several commenters urge the Commission to adopt a generic definition of independent regional planning as well as guidelines and minimum criteria for acceptable independent regional planning processes.
60
Other commenters ask the Commission to be flexible in determining what constitutes a satisfactory “regional planning process,” and to take into consideration any differences among regions on a case-by-case basis.
61
60
E.g.
, PJM TOs, APPA, International Transmission, MidAmerican, Pacificorp, National Grid, Kentucky Commission, PJM, OMS, NRECA and Semantic.
61
E.g.
, Consumer Energy Council, Ameren, SDG&E, Southern Companies, NorthWestern and PEPCO, Dairyland, and Vectren.
c. Commission Determination
76. Our goal is to provide procedural options that offer applicants flexibility to address their construction and investment opportunities while at the same time ensuring that the resulting rates are just and reasonable and not unduly discriminatory or preferential. The Commission offers two ways to accomplish this. An applicant may obtain these rulings: (1) Through a combination of a petition for a declaratory order and a subsequent section 205 filing or (2) by filing only a section 205 filing. For both of these options, the applicant must demonstrate that the facilities for which it seeks incentives either ensure reliability or reduce the cost of delivered power by reducing transmission congestion consistent with the requirements of section 219, that there is a nexus between the incentive sought and the investment being made, and that the resulting rates are just and reasonable.
77. The Commission has found that the first option—petition for declaratory order followed by a section 205 filing—to be a valuable tool. In certain instances, it is valuable for an applicant to obtain an order indicating it qualifies for incentive-based rates prior to making a formal section 205 filing and prior to commencing siting, permitting and construction activities because such orders facilitate financing and investment in new facilities.
62
To provide applicants with as much flexibility as possible, the Commission will permit applicants to seek a declaratory order prior to construction of the facilities to request a finding that the facilities qualify for incentive-based rate treatments. The petitioner would have to demonstrate that its proposal will either ensure reliability or reduce the cost of delivered power by reducing transmission congestion. The petitioner may rely on one of the rebuttable presumptions outlined above or make an independent demonstration. The applicant may also use the petition to justify which incentives it seeks to implement. We clarify that any declaratory order will only rule on whether the applicant's proposal qualifies for incentive-based rate treatment and, if requested, which incentives the applicant may adopt. The applicant must seek to put the rates into effect through a separate single-issue or comprehensive section 205 filing. The Commission's expectation is that, based on past practice, a declaratory order finding that the applicant is eligible for incentive-based rate treatments would be sufficient for the applicant to obtain funding or otherwise acquire financing for the project. The Commission will seek to process petitions for declaratory order quickly. While we cannot guarantee Commission action within 60 days of the request (as is statutorily required for section 205 filings), we will strive to meet that standard.
62
See Western supra
note 2.
78. If an applicant obtains a declaratory order finding that the proposal qualifies for incentive-based rate treatment, the subsequent section 205 proceeding would be limited to a review of the applicant's rates and would not include a review of whether the applicant's facility qualifies to receive incentive-based rate treatments. If the petition addresses the applicant's incentives or finds that the required nexus has been demonstrated, the applicant would not be required to re-justify those findings in the section 205 filing. Therefore, if an interested party believes a petitioner's proposal does not qualify for incentive-based rate treatments or that the incentives requested are not justified, the party must raise its objections when the petition is filed and not wait to raise them in the subsequent section 205 proceeding. If an applicant obtains a declaratory order and the proposal changes from the facts on which the declaratory order was issued, the applicant may seek another declaratory order or wait to seek approval of the changes in the subsequent section 205 filing. In that event, interested parties may challenge the changes in the section 205 proceeding.
79. The second option involves filing only a section 205 filing (either “single-issue” or comprehensive) to request all of the required approvals. Prior to recovering any incentive-based rate treatments in rates, an applicant must demonstrate that the rates in which the applicant seeks to recover any incentives are just and reasonable and not unduly discriminatory. However, the applicant will have the option of filing a comprehensive section 205 rate case in which all of the utility's rates
would be reviewed in conjunction with the proposed recovery of the incentive-based rate treatments or filing a single-issue section 205 rate filing in which only the impact of the incentive-based rate treatment for the facility granted the incentive will be addressed. As explained below in section IV.B.7 (the discussion of single-issue section 205 proceedings), the Commission believes there is a sufficient need for timely investment in transmission infrastructure to justify, in certain circumstances, a departure from our past practice by allowing an applicant to seek to recover any incentive in a single-issue section 205 rate proceeding. Single issue section 205 proceedings, as well as the declaratory order procedural option discussed above, can remove obstacles to new investments by allowing for timely cost recovery. Single issue filings also can support new investment by allowing applicants to compare the returns of such investments with the risks of the project itself, as opposed to having to compare those returns to both the risks of the project being pursued and the risks associated with re-opening all their rates, which is ordinarily a time-consuming, expensive, litigious and uncertain process. Additionally, in further facilitating these goals, the Commission does not intend to routinely convene trial-type, evidentiary hearings to review either a comprehensive or a single-issue section 205 filing but will attempt to render a decision based on the paper submissions whenever possible.
80. We clarify that no incentives will be granted on a final basis without a section 205 filing. Therefore, an RTO member will not automatically receive incentives granted to another RTO member. However, when evaluating applications for incentive-based rate treatments filed by an RTO member, the Commission will take into account incentives granted to other RTO members, particularly in cases where investments being made by that other RTO member pursuant to a regional plan also lead to the need for expansions by the applicant in its own footprint.
81. We will not specify the rate calculations for section 205 proceedings, as requested by TAPS. These issues are appropriately addressed in individual section 205 proceedings.
82. The Commission will require applicants to justify each of the incentive-based rate treatments it proposes by showing how the proposed incentive satisfies section 219.
63
For example, an applicant will be required to show how the granting of the incentive will promote reliable and economically efficient transmission and generation of electricity, attract new investment, or increase capacity and efficiency of existing transmission facilities or improve their operation. The Commission, as set forth above, provides several vehicles for making this showing, including reliance on a Commission accepted regional planning process. We also will require the applicant to show that there is a nexus between the incentives being proposed and the investment being made.
63
An applicant would not be required to demonstrate that, but for the incentive, the project would not be completed. Section 219 does not require such a condition.
83. With respect to procedures applicable to joining Transmission Organizations in § 35.35(e), we clarify that applicants also may file a petition for declaratory order as to whether the applicant qualifies for incentives under section 219(c) and then submit a comprehensive or single-issue section 205 filing to obtain approval of the rates, or simply file a comprehensive or single-issue section 205 case to obtain all necessary approvals.
B. Incentives Available To All Jurisdictional Public Utilities
84. In the NOPR, the Commission proposed eight incentive-based rate treatments for transmission infrastructure investments for all public utilities, including Transcos. As discussed below, the Commission will adopt these in the Final Rule.
1. ROE Sufficient To Attract Capital
a. ROE
i. Background
85. The Commission proposed to consider granting an incentive-based ROE to all public utilities (
i.e.
, traditional public utilities and Transcos) that build new transmission facilities that benefit consumers by ensuring reliability and reducing the cost of delivered power by reducing transmission congestion thereby fulfilling the requirements of section 219. As proposed, to receive an incentive-based ROE, a public utility must submit a request in an application under section 205 of the FPA and must support the ROE request by demonstrating how the new facilities will improve regional reliability and reduce transmission congestion. In addition, the application must explain whether the facilities are part of an independent regional planning process, such as that administered by an RTO or ISO or another independent regional planning process recognized by the Commission and how the proposed ROE was derived and why it is appropriate to encourage new investment. (NOPR at P 22) Recognizing that the Commission had approved higher ROEs (referred to in the NOPR as an “adder”) for certain projects that were designed to increase transfer capability or reduce congestion, the Commission sought comments on the appropriateness of a higher ROE as a mechanism for increasing investment in new capacity.
ii. Comments
86. Numerous Commenters
64
express general support for the proposal to grant incentive-based ROEs to encourage transmission investment stating that it is the most direct and effective means of attracting needed capital to improve the nation's transmission infrastructure. Southern Companies assert that allowing an incentive ROE only “within the zone of reasonableness” is inconsistent with Congress's mandate in section 219 that the Commission provide incentive ROEs for transmission investment. NSTAR and Vectren state that an incentive need not be cost-based; an incentive is justified under the statute as just and reasonable if it serves the statutory purpose of improving reliability or reducing the overall cost of delivered power.
64
E.g.
, National Grid, FirstEnergy, EEI, KCPL, Xcel, Kentucky Commission, Nevada Companies, Progress, and Southern Companies.
87. Other commenters oppose the Commission's proposal to grant incentive-based ROEs for investment in new transmission facilities. For example, APPA states that an ROE adder is basically a bonus payment to reward transmission providers for doing the job for which they are already getting paid an adequate ROE under current Commission standards and relevant FPA requirements. Connecticut DPUC argues ROE adders are not a useful policy tool for improving transmission and the Commission's standard rate review process of assessing the firm's risk-adjusted cost of capital assures a completely adequate ROE without any adders. TDU Systems and New Mexico AG contend that ROE adders will fail the judicial mandate that rates be just and reasonable. CREPC maintains that a blanket ROE increase generally runs counter to the Commission's goal of encouraging transmission investment because it will either unnecessarily increase the cost of electricity to end-users or render an otherwise economic transmission
project uneconomic in comparison to its alternatives. The California Commission states that the Commission's reliance on incentives granted to Trans-Elect with respect to financing the critical Path 15 upgrade in California several years ago is misleading since the special consideration accorded to Trans-Elect was a direct consequence of the unique, emergency energy crisis facing California and the Western United States in 2001.
88. Some commenters
65
assert that the Commission must consider the certainty of rate recovery for investment in new transmission facilities and associated lower risk—providing the basis for a lower ROE—before granting incentive-based ROEs. Others, however, such as MidAmerican and PacifiCorp, state that the Commission should consider ROE adders or other forms of enhanced returns if a project investment entails levels of risk to investors and consumers that a traditional rate of return would not cover or otherwise lacks the economic or commercial incentives necessary to attract needed capital. PJM recommends the Commission establish an equity return range based on a generic analysis of investor expectations concerning transmission investment as opposed to an analysis of a vertically integrated company or, as an alternative, recognize the overall risk of each project, such as the risk of delayed recovery at the state level.
65
E.g.
, NRECA, CREPC, AWEA, the Delaware Commission, New Mexico AG, NY Association, the New York Commission, the California Commission and SMUD.
89. TAPS states that any incentive-based adjustment to transmission returns should take the form of an equivalent adjustment to total return (
i.e.
, return on both debt and equity), rather than making the value of the adjustment vary with the transmitter's capital structure. TDU Systems state that if the Commission allows ROE adders, it should consider applying the adders to the overall rate of return as an alternative to estimating equity returns using public utility returns as a proxy.
90. MISO States argues that the Commission should make clear that proposed ROE incentives are on investments in new transmission, as contrasted with all of a public utility's transmission investment. TAPS claims that increasing the ROE for existing facilities does nothing to encourage investment in new transmission facilities. TDU Systems recommends limiting ROE adders to the portion of rate base related to the new investment.
iii. Commission Determination
91. Consistent with the proposal in the NOPR, the Commission will allow, when justified, an incentive-based ROE to all public utilities (
i.e.
, traditional public utilities and Transcos) for new investments in transmission facilities that benefit consumers by ensuring reliability or reducing the cost of delivered power by reducing transmission congestion. By including this provision in the Final Rule, we meet the requirement of section 219 to provide an ROE that attracts new investment in transmission facilities (including related transmission technologies). Public utilities making investments in transmission infrastructure have made clear, both in their applications for new projects and in their comments on this Rule, that the ROE incentives encourage investment. We expect that an incentive ROE will make transmission projects more attractive, and therefore more likely, when transmission projects must compete for capital in vertically-integrated utilities as well as in transmission and delivery utilities. Accordingly, the Commission will approve an ROE at the upper end of the zone of reasonableness for new infrastructure investments that meet the requirements of section 219 as discussed elsewhere in this Final Rule.
92. Concerns of blanket ROE increases and ROEs that exceed the DCF determined ROE are misplaced. The NOPR's use of the term “adder” may have contributed some confusion regarding the Commission's proposal. The Commission, as discussed later in this section, will continue to use the DCF analysis for ROE determinations. That analysis can result in a range of returns (
e.g.
, 9 percent to 13 percent), any of which falling within the range are just and reasonable. This analysis, undertaken in individual rate applications, assesses representative proxy companies and the impact of other factors, including risk, on the zone of reasonableness for ROE. Thus, contrary to certain comments, our justification for a higher ROE is not based on a risk assessment; the risk assessment is part of the traditional DCF analysis.
93. Under the Rule adopted herein, the Commission will provide ROEs at the upper end of the zone of reasonableness for transmission investments that meet the requirements of section 219 as discussed elsewhere in this Final Rule. Incentive-based ROEs, like other incentives offered in this Rule, are to be filed with the Commission for approval before rates that reflect such incentives can be charged. Accordingly, because the approved ROE, including the impact of an incentive, will be within the zone of reasonableness, we consider this provision consistent with section 205 of the FPA. We will not create specific ROE adders (
e.g.
, 100 basis points); the Commission has always considered a range of returns in determining the appropriate ROE and we see no reason to depart from this practice. Though some commenters assert that the incentive need not be cost-based and therefore can justifiably be above the upper-end of the zone of reasonableness, we believe a return within the zone will be adequate to attract new investment and consistent with the intent of Congress in section 219. The Commission will determine the level of the ROE on a case-by-case basis when an application for an incentive-based ROE is filed with the Commission. This is consistent with the approach the Commission has employed to date, which has been found to be just and reasonable.
66
66
Public Utilities Commission of the State of California
v.
FERC
, 367 F.3d 925 (D.C. Cir. 2004).
94. The foregoing does not mean, however, that we will grant incentive-based ROEs to every new investment that increases reliability or reduces congestion. The purpose of section 219 was, as described above, to require the Commission to re-examine whether its current policies are adequate to encourage new investment and strike the appropriate balance between the investor and consumer interests. In many instances, an incentive-based ROE is appropriate because our traditional policies are not sufficient to encourage new investment. For example, a large new interstate transmission project that reduces congestion or increases reliability can face substantial risks that the ordinary transmission investment does not. Further, such projects will often be undertaken only at the election of investors, given that no single entity is “required” to undertake them, and thus an incentive-based ROE is appropriate to encourage proactive behavior. Other projects also may present special risks or considerations that merit an incentive-based ROE. By contrast, there are certain projects that may not merit such an incentive. For example, routine investments made to comply with existing reliability standards may not always qualify for an incentive-based ROE. These are the types of investments that have, as a general matter, been adequately addressed through traditional ratemaking because there is an
obligation to construct them and high assurance of recovery of the related costs. For these and other reasons, traditional ROE determinations may continue to be appropriate for these investments. This does not mean that other incentives may not be appropriate for such investments (such as 100 percent CWIP recovery) or that other reliability investments (
e.g.
, substantial new investments to meet new standards) would not qualify for incentive-based ROE determinations.
95. We decline to apply incentives to total return, including debt, as requested by TAPS. Section 219 directs the Commission to focus on ROE, not total return; and this focus is proper. In a competitive market for debt financing, any incentives added to the actual costs of debt will flow to equity investors without actually increasing the returns of debt capital providers. Unlike debt investors who do not propose new investment or make direct investment decisions, equity investors make investment decisions directly or by giving management their proxy. Thus the opportunity for a higher ROE will directly and more transparently influence the actions of those in the position to make initial investment decisions.
96. With regard to questions about whether the opportunity to earn an incentive-based ROE applies to all of a public utility's transmission investment, we clarify that it applies to new transmission investment including investment that results in the enlargement of or improved operation and maintenance of all facilities, consistent with section 219 as discussed elsewhere in this Final Rule.
b. Alternatives to DCF Analysis
i. Background
97. While the Commission has typically utilized a DCF analysis, the NOPR (at P 20) sought comment on whether it should consider alternatives to the DCF analysis as a way to provide incentives for investment in new transmission capacity.
ii. Comments
98. A number of commenters
67
do not support a departure from the DCF method that the Commission currently uses to determine allowed ROE. APPA, for example, states that the DCF approach is generally analytically sound and has produced consistent, predictable results over time, eliminating some of the subjectivity and randomness in equity forecasts that might occur if the Commission were to change methods on a case-by-case basis. The New York Commission supports the use of a DCF analysis as an appropriate means to determine an ROE that reflects commensurate risks and thus would attract new investments.
67
E.g.
, APPA, the Kentucky Commission, New Mexico AG, NY Association, New York Commission, TDU Systems and TAPS.
99. A number of commenters,
68
request that the Commission adopt additional methodologies, such as risk premium, comparable earnings, Fama-French, and/or capital asset pricing, to use along with the current DCF analysis because a multiple model approach will result in a more representative ROE range. These commenters contend that the Commission should make clear that it will consider and use alternative methods of calculating ROEs. They argue that the Commission's final determination of a just and reasonable ROE should be based on a combination of the results from those alternative methods of calculating ROEs, not on the result from any single method, because each method has its own set of theoretical deficiencies and a range of methods ensures all applicable variables are considered.
68
E.g.
, AEP, Ameren, EEI, California Commission, KCPL, PacifiCorp, PEPCO, PJM TOs, Progress Energy, NSTAR, SDG&E, SCE, Southern Companies, Trans-Elect, Vectren and WPS.
100. Other Commenters
69
ask that the Commission consider changes to how it determines proxy groups in the DCF analysis, by permitting adjustments for leveraging effects, or adopting modified or expanded proxy groups, as appropriate on a case-by-case basis, and by looking more to companies in the primary or sole business of providing electric delivery service or by isolating those activities from the other activities of public utilities included in proxy groups. EEI recommends that the Commission should use after-tax weighted average cost of capital to adjust for leverage differences among sample companies and recommends applying DCF results to the market value of equity rather than to the book value of equity.
69
E.g.
, PEPCO, APPA, PJM, AEP, FirstEnergy, and Ameren.
101. NSTAR and New England TOs assert that any changes to the Commission's ROE methodology should not be considered an incentive because updating the ROE methodology including appropriate recognition of risk is not an incentive, but rather is necessary to assure that the ROEs received by transmission-owning utilities are compensatory and fair under current market conditions and recover their cost of capital.
iii. Commission Determination
102. While commenters note that every alternative method has a theoretical deficiency and there is a benefit to introducing more information into the analysis process, we do not see any basis to conclude that the alternative methods would encourage more transmission investment than continued reliance on the DCF analysis. Our past practice of using the DCF approach has yielded just and reasonable results and is consistent with long-standing ratemaking principles. Therefore, at this time, we will not make broadly applicable changes to how the Commission has traditionally performed its DCF analysis on companies in the electric industry. However, we will consider on a case-by-case basis whether the application of the traditional DCF analysis should be modified and entertain proposals to use different proxy groups as a way of capturing different business models.
2. Construction Work in Progress (CWIP) and Pre-Commercial Expenses
a. Background
103. In the NOPR, the Commission noted that the long lead times required to plan and construct new transmission can impact utility cash flow, in turn affecting the overall financial health of a company and its ability to attract capital at reasonable prices. The Commission proposed including 100 percent of CWIP in rate base;
70
and expensing rather than capitalizing pre-commercial operations costs associated with new transmission investment in order to relieve the pressures on utility cash flows associated with transmission investment programs.
70
CWIP is a return on capital. Since 1987, the Commission's general policy has been to allow only 50 percent of the non-pollution control/fuel conversion construction costs as CWIP in rate base. The remaining construction costs, including an allowance for funds used during construction (AFUDC) which provides a return on those expenditures, generally would have been capitalized and included in rate base only when the plant went into commercial operation,
i.e.
, when the plant became used and useful. Allowing some portion of the costs in rate base prior to commercial operation provides utilities with additional cash flow in the form of an immediate earned return.
See
18 CFR 35.25(c)(3).
104. In 2004, the Commission accepted a proposal by American Transmission Company (American Transmission) to include 100 percent of CWIP in the calculation of transmission rates and to expense pre-commercial operations costs for new transmission investment, instead of capitalizing those costs and earning a return.
71
American
Transmission stated that these incentives would help maintain adequate cash flow during the construction process and that without these incentives it could face a downgrade of its fixed income rating over the next several years due to inadequate cash flow, thereby increasing its capital costs by $176 million over a twenty-year horizon.
71
See American Transmission, supra
note 2.
105. The Commission stated in the NOPR that allowing public utilities, on a case-by-case basis, to include up to 100 percent of prudently incurred transmission-related CWIP in rate base and permitting them to expense prudently incurred pre-commercial operations costs will further the goals of section 219 by relieving the pressures on utility cash flows associated with their transmission investment programs and providing up-front regulatory certainty. The Commission specifically requested comment on (1) the types of costs that should be considered “pre-commercial” operation costs; and (2) whether there should be a presumption that these incentives meet the requirements of FPA section 219 that investments ensure reliability and reduce the cost of delivered power.
b. Comments
106. Most of the commenters,
72
support including 100 percent of prudently-incurred CWIP in rate base and expensing all pre-commercial operation costs, stating that these incentives will encourage transmission investment through improved cash flow, greater rate stability and lower rates to future customers. Additionally, SDG&E notes that this incentive will balance short-term rates and long-term rates by increasing the rates during construction but lowering the rates during operation of a facility.
72
E.g.
, EEI, American Transmission, AWEA, PG&E, AEP, NSTAR, WPS and TDU Systems.
107. Opponents, such as the New Mexico AG and California Commission, state that maintaining the status quo would be in keeping with the long-standing ratemaking doctrine that recovery of utility plant costs should be based on utility plant that is “used and useful.” They also oppose expensing pre-commercial costs instead of capitalizing such costs because there will be no opportunity for a comprehensive review of project costs before those costs are passed on to ratepayers.
108. Snohomish argues that the Commission must implement a procedure to handle refunds where the project is never ultimately completed, and must condition inclusion of CWIP and other pre-operation costs in rates on adherence to the construction schedule submitted with the application.
109. In its supplemental comments, EEI recommends the Commission waive the requirement that a utility requesting CWIP must provide a forward-looking allocation that estimates the average use a wholesale customer will make of the utility system over the life of a project, as currently required by 18 CFR 35.25(c)(4). EEI states the purpose of the required forward-looking allocation is to protect wholesale customers against a double whammy (
i.e.
, being required to pay for the construction of new generation facilities if the customer switched supplier). EEI states that the double whammy concern is not present with transmission facilities because the customer will almost certainly not switch transmission suppliers.
110. TDU Systems assert that CWIP should not be allowed for projects for which the public utility receives upfront interconnection payments, nor for any project for which the funds have been provided by a third party, except in tandem with crediting-back of such prepayments or investments on a schedule to which the transmission customer agrees. TDU Systems assert that if formula rates are in place for the public utility seeking to expense the cost of capital assets, inter-generational inequity is even more egregious since the public utility may well receive a one-year amortization of that expense although future rate payers will benefit from the use of those facilities for years to come.
111. Other commenters state that pre-commercial costs should be defined and the Commission should provide guidance.
73
Commenters' proposals for pre-commercial costs definitions include all costs associated with pre-construction activities, such as planning, related studies, and siting costs, including (1) costs of routing studies for placement of transmission lines, (2) costs of certification associated with regulatory approvals including legal and consulting costs, (3) costs of public hearings and informational hearings, (4) costs for design, planning, drafting, surveying services, material procurement and labor in support of project construction, and (5) costs associated with development and implementation of interim measures to maintain adequate reliability level due to the delayed completion of the proposed project.
73
E.g.
, EEI, SCE, AEP, NSTAR, WPS, NU, FirstEnergy, the Nevada Companies, KCPL, NRECA and Ameren.
112. Additionally, EEI argues the Commission should also include as pre-commercial costs other costs that have been traditionally expensed such as costs of resetting relays, using a mobile transformer, making payments to other transmission owners for upgrades to their lines, and the write-offs of the undepreciated cost of facilities that are being replaced with new transmission investment.
113. NRECA states that these costs should be limited to prudently incurred direct transmission investment costs. TDU Systems states that in no event should the Commission allow public utilities to expense costs associated with transmission facilities such as land, towers, transformers, lines, and substations.
114. PJM recommends that costs of developing a transmission proposal through a planning process should be considered a pre-commercial cost.
c. Commission Determination
115. After considering all the comments, we adopt in this Final Rule the proposal from the NOPR to give public utilities, where appropriate, the ability to include 100 percent of prudently incurred transmission-related CWIP in rate base and to expense prudently incurred “pre-commercial” costs. These rate treatments will further the goals of section 219 by providing up-front regulatory certainty, rate stability and improved cash flow for applicants thereby easing the pressures on their finances caused by transmission development programs. As noted by many commenters, these proved effective for American Transmission by easing the pressures on American Transmission's finances caused by its transmission development program allowing American Transmission to, among other things, stay on schedule with its development program. For American Transmission, this also meant a higher credit rating and lower cost of capital, thus benefiting customers. Similar results can be expected for other transmission developers availing themselves of such opportunities.
116. We appreciate the concerns, as expressed by the California Commission and others, that the proposal is a departure from existing ratemaking doctrine that rates should be based on plant that is “used and useful.” However, as times and circumstances warrant, the Commission has revised its ratemaking policies. In fact in Order No. 298,
74
the Commission did just that
when it decided to allow any public utility engaged in the sale of electric power for resale to file to include in rate base up to 50 percent of CWIP, subject to limitations. Thus, the Commission already allows inclusion of some CWIP in rate base. The Commission also departed from existing principles in the
American Transmission
and
Southern California Edison
cases.
75
The nation has suffered a decline in transmission investment and it is time that the Commission revisit ratemaking policies that may serve as a barrier to investment and revise them accordingly while ensuring that customers are protected and rates remain just and reasonable. Finally, we note that 100 percent recovery of CWIP costs is already provided for pollution control facilities of public utilities.
76
74
Construction Work in Progress for Public Utilities; Inclusion of Costs in Rate Base
, Order No.
298, FERC Stats. & Regs. ¶ 30,455 (1983),
order on reh'g
, 25 FERC ¶ 61,023 (1983).
75
See American Transmission, supra
note 2; Southern California Edison Co., 112 FERC ¶ 61,014, at P 61,
reh'g denied
, 113 FERC ¶ 61,143 (2005) (SCE).
76
See
18 CFR 35.25(c)(1).
117. Allowing public utilities the opportunity, in appropriate situations, to include 100 percent of CWIP in the calculation of transmission rates and to expense pre-commercial operations costs for new transmission investment (instead of capitalizing these costs and earning a return) removes a disincentive to construction of transmission, which can involve very long lead times and considerable risk to the utility that the project may not go forward. The fact that public utilities have the opportunity to recover these costs in rates in a different manner than in the past does not mean that the rates are not subject to review under FPA sections 205 and 206. Even for rates that are formulaic, it may be necessary for the utility to revise the rate formula under section 205 to capture the recovery of these types of costs to the extent that they are not provided for in the formula. Moreover, as the D.C. Circuit has found, the Commission can depart from the norm as long as it reasonably balances consumers’ interest in fair rates against investors' interest in “maintaining financial integrity and access to capital markets.”
77
Finally, if the transmission facility never enters service (
i.e.
, is never used or useful), the transmission owner may still seek recovery of the expenses associated with the construction work in progress (
i.e.
, the return on capital) under our abandoned plant incentive, as discussed below. Accordingly, we find that the “used and useful” ratemaking principle is not a sufficient basis to deny adoption of the NOPR's proposal. However, as explained above, we will require each applicant to demonstrate that there is a nexus between its request for 100 percent CWIP recovery and the investments being made. Ordinarily, such an incentive would be appropriate for large new investments or in situations, as occurred with ATC, where denying such an incentive would adversely affect the utility's ratings. There may be other situations as well where such an incentive is appropriate and we will consider each proposal on the basis of the particular facts of the case.
77
Jersey Central Power & Light Co.
v.
FERC
, 810 F.2d 1168, 1178 (D.C. Cir. 1987) (
Jersey Central
). “Although a utility's rate base normally consists only of items presently ‘used and useful’ (
see New England Power Co. Mun. Rate Comm.
v.
FERC
, 668 F.2d 1327, 1333 (D.C. Cir. 1981),
cert. denied
, 457 U.S. 1117 (1982)), a utility may include ‘prudent but canceled investments’ in its rate base as long as the Commission reasonably balances consumers' interest in fair rates against investors' interest in ‘maintaining financial integrity and access to capital markets.’ ”
Jersey Central
, 810 F.2d 1168, 1178 (D.C. Cir. 1987).
118. With regard to requests that the Commission condition inclusion of CWIP and pre-operation costs on adherence to the construction schedule submitted with the application and that we implement a procedure to handle refunds in the event the facility is not put into service, we find them to be unnecessary and/or inconsistent with the other measures we adopt in this Final Rule. As discussed further below, the Commission is proposing to provide a public utility with the opportunity to file for abandoned plant costs. Thus, requiring a refund procedure that raises perceived risks of proposing new transmission at this time would be inconsistent. We also do not see the need to condition inclusion of CWIP on adherence to a construction schedule. Because the actual recovery of CWIP will occur either under a rate on file or a rate to be filed under FPA section 205, parties will have an opportunity to raise any concerns with regard to actual expenditures vis-a-vis construction progress at that time. Accordingly, we see no reason to condition inclusion of CWIP on adherence to a construction schedule.
119. The Commission's current CWIP regulations were developed in an era of bundled wholesale services and apply to any rate schedule. Since that time, most wholesale transmission service subject to the Commission's jurisdiction is provided at unbundled rates under open access transmission tariffs. EEI points out that the requirement for a forward looking allocation that estimates the average use a wholesale customer will make of the utility system over the life of the project is not necessary with transmission facilities. We agree. The forward looking allocation ratio was to prevent a customer that was switching power plant suppliers from having to share in the cost of CWIP of a particular plant if the customer had no responsibility in the decision of the utility to build the plant. We believe it highly unlikely that transmission customers will be faced with such an opportunity. Accordingly, because we do not view the “double whammy” to be a concern in the transmission context, we grant EEI's request and waive the requirement in 18 CFR 35.25(c)(4) as it pertains to preventing double whammy with regard to CWIP associated with new investment in transmission.
78
Further, we clarify § 35.35(d)(1)(ii) to state that other provisions of § 35.25 apply, unless waived by the Commission on a case-by-case basis. We believe that these clarifications to the regulatory text will avoid uncertainty expressed by commenters regarding the procedures for obtaining the CWIP incentive.
78
However, this waiver does not relieve transmission owners from supplying the necessary information required in § 35.25(c)(4) that pertains to CWIP-induced price squeeze. The Commission will evaluate CWIP-induced price squeeze concerns on a case-by-case basis.
120. In response to comments, we clarify that pre-payments,
i.e.
, payments prior to the start of construction, for project costs by third-parties should not be included in CWIP. If a customer is making contributions in aid of construction, these amounts should not be included in rate base. Similarly, in the instance of generator interconnect, the up-front amount paid by the customer should not be included in rate base; rather it is included in rate base over time as the transmission provider provides credits to the customer.
121. The Commission has previously determined that recovery of CWIP on a formulary basis is not permitted without prior Commission review to ensure that the Commission's CWIP standards are met.
79
The Commission in
Maine Yankee
allowed Maine Yankee to propose a method to limit its filing obligation to once a year so that Maine Yankee did not have to file each month that it changed the CWIP balances in its monthly formula charges.
80
Likewise, we will allow public utilities to propose a method to limit their filing requirement related to CWIP to an annual filing. These annual filings may be limited to CWIP and will not subject
public utilities to a comprehensive rate review.
81
79
Maine Yankee Atomic Power Co.
, 66 FERC ¶ 61,375, at 62,252-53 & n. 10 (1994) (
Maine Yankee
).
80
Id.
, at 62,252.
81
We deny the request to limit recovery of these incentives to the amount originally budgeted. We note that, as a practical matter, it would be difficult to hold electric transmission projects to the original budget estimate when it can be 10 to 15 years between the time the project is proposed and lines are actually built. Also, if public utilities are held to recovering only originally estimated budgets, they would either have incentives to overestimate costs or to avoid the risky projects which the policy is intended to facilitate.
122. With respect to the types of pre-commercial operations costs that we will allow to be expensed rather than capitalized, we will allow, on a generic basis, the same types of costs that we approved in the American Transmission settlement.
82
Further, we will entertain proposals by public utilities to expense other types of costs for consideration on a case-by-case basis.
82
American Transmission, in its application approved in American Transmission defined pre-certification costs as preliminary survey and investigation costs in Account 183. These costs include all expenditures for, preliminary surveys, plans and investigations, made for the purpose of determining the feasibility of utility projects and costs of studies and analyses mandated by regulatory bodies related to plant in service.
3. Hypothetical Capital Structure
a. Background
123. The Commission stated in the NOPR (at P 29) that it has largely relied on the actual capitalization of a utility in setting its rate of return, but recognized that an overly rigid approach to evaluating a proposed capital structure could be a disincentive to investment in new transmission projects and Transco formation. Each project or company may have unique financial and cash flow requirements, and a rigid approach to acceptable capital structures could threaten the viability of some projects. Accordingly, the Commission proposed allowing applicants to file an overall rate of return based on a hypothetical capital structure, and giving them the flexibility to refinance or employ different capitalizations as may be needed to maintain the viability of new capacity additions. The Commission stated that it expected applicants to develop their proposals based on the specific requirements and circumstances of their projects, and that the Commission would evaluate proposals for this incentive on a case-by-case basis. The Commission required public utilities to provide support in their application for why the hypothetical capital structure incentive is needed to promote investment consistent with the goals of section 219. The Commission required the applicant to provide its transmission investment plan and explain the specific projects to which the proposed return will apply.
b. Comments
124. Many commenters support the hypothetical capital structure as an incentive.
83
Both American Transmission and Trans-Elect note that they received approval to use a hypothetical capital structure and that they had been able to stay on schedule for extensive transmission construction programs.
84
83
American Transmission, EEI, First Energy, KCPL, Nevada Companies, NSTAR, NU, NYSEG and RGE, PJM, PG&E, Progress, Semantic, Trans-Elect, United Illuminating and Xcel support the proposal.
84
Trans-Elect cites
Western
, 99 FERC ¶ 61,306 at 62,280,
reh'g denied
, 100 FERC ¶ 61,331 at P 7, 9 (stating that rate treatments including hypothetical capital structure were necessary for the Path 15 project to be built).
See also, METC
, 105 FERC ¶ 61,214 at P 20 (Commission recognized the need to encourage, through regulatory rate-making policy, the independent business model).
125. Several parties, including EEI, NSTAR and NU argue in a similar vein that hypothetical capital structures can aid investments by companies that are entering a large capital expenditure program or are emerging from financial distress and may be aiming for a capital structure they have not yet realized. Semantic suggests a 75 percent equity and 25 percent debt capital structure be used to reflect the higher risks of early adoption of advanced technologies.
126. PJM and NSTAR state that hypothetical capital structures are particularly useful for projects involving consortia. PJM cites its proposed consortium approach to building transmission, where a capital structure could be based on the project as a whole rather than piecemeal based on the individual capital structures of each participant in individual rate cases.
85
85
PJM TOs concur that the incentive could be helpful in project-specific rates.
127. A number of commenters oppose hypothetical capital structures.
86
APPA and CREPC argue hypothetical capital structures could result in a windfall to public utilities by increasing actual return far in excess of the Commission's allowed return on equity. Commenters also express concern that the proposed incentive represents a departure from Commission precedent and could result in unjust and unreasonable rates.
86
E.g.
, California Commission, TDU Systems, APPA, CREPC, Steel Manufacturers, New Mexico AG, the Oklahoma Commission, PPC, NECOE, Connecticut AG, and the Delaware Commission.
128. Other commenters, such as the Kentucky Commission, Dairyland and MISO States, assert that the Commission should preclude a public utility from receiving both hypothetical capital structure and the ROE incentive because combining the incentives could result in adopting a cost of equity well in excess of the DCF range of reasonableness.
129. Because of concerns about the criteria to be used in evaluating proposals for hypothetical capital structures, many parties, including CREPC, California Commission, NRECA and California Oversight Board, recommend evaluating the proposal on a case-by-case basis, with California Oversight Board arguing for standard of proof much higher than merely having to support the proposal as the NOPR proposes.
130. NECOE states that the Commission should categorically prohibit vertically-integrated utilities from using a hypothetical capital structure. MISO States argues that this incentive is not reasonable, especially if applied to a company's entire rate base, instead of just its new transmission. APPA states that if a specific transmission project is financed separately from other projects within a transmission network (
e.g.
, merchant transmission line), it may be appropriate to evaluate its capitalization separately from other affiliates; however, the evaluation should be based on actual capitalization instead of hypothetical capitalization. In contrast, Ameren asserts that hypothetical capital structures beyond project-financed investments can be supported and should be considered on a case-by-case basis.
87
87
Ameren states that the Commission has approved the use of a hypothetical capital structure to better reflect the risk profile of a regulated enterprise.
See High Island Offshore Systems, L.L.C.
, 110 FERC ¶ 61,043, at P 143,
order on reh'g
, 112 FERC ¶ 61,050 (2005) (
High Island
).
c. Commission Determination
131. The Commission finds that hypothetical capital structures can be an effective tool available to public utilities to foster transmission investment in appropriate circumstances. As some commenters point out, use of a hypothetical capital structure is not new. For example, the Commission has allowed independent transmission companies to use a hypothetical capital structure to recognize the significant benefits of independent ownership and operation of transmission including, among other things, improved access to capital markets for transmission investment
88
and the Commission has allowed its use for specific projects when shown to be necessary for project financing, among other things.
89
Further, as PJM argues in its comments, hypothetical capital structures may be
effective for development of consortium projects. This can be especially important for projects with a diverse set of sponsors, some of which have different capital structures, (
e.g.
, a power marketing agency that contributes access but no equity compared to a project sponsor that brings only equity to a proposed investment). We note the rise in interest in these types of projects, including such large-scale, multiple-developer projects as the Frontier Line and TransWest proposals. Thus, the Commission finds that, in certain contexts, this incentive is appropriate for consideration under section 219 because it has been demonstrated to foster the development of transmission investment, as indicated by the experience of American Transmission and Trans-Elect.
88
METC
, 105 FERC ¶ 61,214 at P 20.
89
Western, supra
note 2.
132. The Commission continues to believe that an overly rigid approach to evaluating proposed capital structures may discourage the development of new transmission projects. Therefore, the Commission will evaluate each proposal on a case-by-case basis but will not prescribe specific criteria or set target debt/equity ratios for evaluating hypothetical capital structures, as requested by some commenters.
90
90
We note that many commenters support case-by-case review and recognize the merits of evaluating the specific circumstances of hypothetical capital structure proposals.
133. We will not categorically deny the incentive to vertically-integrated utilities, as recommended by NECOE. We agree with Ameren that there may be circumstances in which a hypothetical capital structure may be appropriate for a transmission investment by a vertically-integrated utility. However, we are not suggesting that hypothetical capital structures will become the norm. As with the other incentives, we will require that the applicant demonstrate a nexus between its proposed incentive and the facts of its particular case.
134. In this regard, we note that many of the instances in which hypothetical capital structures are used and can be used reflect unique circumstances, such as a project or consortium that requires a special capital structure where the capital structure may change significantly with new investments. We disagree with TDU Systems that the Commission has (or should adopt) a general policy on when to use hypothetical capital structures. Moreover, we do not believe that the Commission's recent approvals of hypothetical capital structures for electric transmission companies have resulted in abnormally high equity ratios or over-compensation for the equity holder at the expense of the ratepayer.
4. Accelerated Depreciation
a. Background
135. In the NOPR (at P 30), the Commission proposed accelerated depreciation as another way to increase cash flow to utilities, thereby removing a potential disincentive to investing. The Commission has determined that in some circumstances allowing accelerated depreciation is warranted to encourage investment in transmission infrastructure because it provides improved cash flow and better positions public utilities for longer-term transmission investments.
91
The Commission stated that permitting accelerated depreciation more broadly than just for emergency conditions or special projects may further the goals of section 219 by providing incentives to undertake transmission projects that have the potential to reduce the cost of delivered power and ensure reliability, and, therefore, proposed to allow transmission facilities to be depreciated over a period of 15 years, in place of the typical Commission practice to allow depreciation over the useful life of the facilities.
92
91
See Removing Obstacles
and
Western, supra
note 2.
92
Removing Obstacles
, 94 FERC ¶ 61,272, at 61,968-69.
136. The Commission also sought comment on two issues. The Commission asked whether 15 years is an appropriate time period for cost recovery or whether the Commission should establish a presumption of a shorter or longer depreciable life for new transmission facilities.
93
The Commission also requested comment on whether accelerated depreciation has any longer-term negative impacts that would undermine the goals of section 219.
93
For example, in
Removing Obstacles
, the Commission permitted a 10-year depreciable life for facilities that will increase transmission capacity to relieve existing constraints and could be in service within a few months.
b. Comments
137. A number of commenters support the proposal to allow accelerated depreciation of 15 years for the reasons set forth in the NOPR.
94
Some of the supporters, such as the Delaware Commission, KCPL, International Transmission, NYSEG and RGE, Progress, Siemens, Upper Great Plains, and United Illuminating recommend that the incentive should be optional.
94
E.g.
, Ameren, EEI, BG&E, FirstEnergy, NSTAR, PG&E, PJM, PJM TOs, SCE and WPS. Ameren, MidAmerican and Nevada Companies assert that the Commission should be receptive to a shorter depreciable life or that a different life may be appropriate, possibly tied to the term of a service agreement.
138. Other commenters oppose the proposal to allow accelerated depreciation of transmission facilities.
95
For example, Connecticut AG, NECOE and TANC assert the accelerated depreciation incentive will increase costs and rates and result in gold-plating and over-building of transmission infrastructure. APPA claims that after new transmission facilities have been depreciated over the shorter time period proposed by the Commission, the transmission owners will essentially be providing transmission service for free. APPA is concerned that when this happens the transmission owners will propose to “recalibrate” (
i.e.
, increase) the transmission rate base to depreciate the same facilities yet another time at ratepayer expense.
95
E.g.
, TDU Systems, the California Commission, APPA, the Connecticut AG, NY Association, NECOE, TAPS, the New York Commission and TANC.
139. Additionally, TAPS opposes accelerated depreciation because transmitting utilities will no longer earn a return on their investments after the facility has been depreciated and would potentially seek to recover a management fee which would deny ratepayers of the supposed benefits of accelerated depreciation.
96
TAPS claims that given the likelihood of this management fee, the Commission cannot refer to accelerated depreciation as a timing difference. Ameren, on the other hand, states the one drawback to accelerated depreciation is that once the asset has been fully depreciated, the public utility can not earn a return.
97
Ameren states the Commission should consider generic procedures for the establishment of compensatory management fees for fully depreciated transmission assets.
96
TAPS cites
High Island
, 110 FERC ¶ 61,043, at P 105-115.
97
AEP and International Transmission also note this concern.
140. TAPS also argues that accelerated depreciation would skew investments towards depreciable plant and away from non-depreciable land even if acquisition of rights-of-way was the cheaper alternative. TAPS states that, if the Commission is intent on permitting accelerated depreciation, the Commission should require the utility to auction off the fully depreciated facilities at full market value with the proceeds credited to ratepayers.
141. California Commission opposes accelerated depreciation because when a facility is placed into service, the value of the undepreciated plant is at its highest; therefore, the company earns a high return on the plant. As a result, the company has immediate cash flow that does not need to be enhanced. California Commission, TAPS and TDU Systems express concern that accelerated depreciation may cause generational inequities between those who pay for the facilities now and those who do not have to pay later.
142. EEI states that this incentive should not be dependent on corporate structure, should not be limited to 15 years when it may be appropriate to use a shorter depreciable life for certain facilities, and when 15 years is used by a public utility, the company should be able to match the tax law depreciation methodology, which weights the tax depreciation more heavily toward the beginning of the life of the project rather than spreading it evenly over 15 years.
143. APPA cites to a number of concerns including the effect of such accelerated depreciation on book-tax timing differences, and the associated deferred tax accounts, and complications in calculating inter-period income tax allocations. APPA also contends that, if the Commission allows rate recovery over a 15 year life for transmission assets, then there should be no provision for deferred income taxes allowed with respect to such assets in any rate case (and no deduction from rate base), because such book and taxable income with respect to such assets would then be matched.
144. International Transmission asserts that in Order No. 618, the Commission correctly determined that the choice of depreciation method should be left to industry.
98
International Transmission argues that flexibility in determining depreciation methods is particularly important when new technologies are deployed that may not be proven, may cost more or have uncertain useful lives, and may be needed to accommodate ongoing industry restructuring or regulatory innovation.
98
Depreciation Accounting
, Order No. 618, FERC Stats. and Regs. ¶ 31,104, at 31,694 (2000) (Order No. 618). According to International Transmission, in Order No. 618, the Commission modified its initial proposal to require straight-line depreciation to permit other methods of depreciation that allocated the cost of utility property over its useful life in a systematic and rational manner. The Commission recognized that this approach would “[allow] flexibility in a changing business environment.”
145. International Transmission states that accelerated depreciation does not increase cash flow for companies with formula rates as it would for companies with stated rates, because the formula rates reset every year. International Transmission urges the Commission to clarify that any changes to depreciation rates for a company using a formula rate will be accepted as a ministerial filing with issues limited only to estimation of the depreciation life and salvage parameters; and that an added bonus of this approach would permit companies with formula rates to remove from their formula rates, in ministerial filings, accumulated deferred income tax balances from rate base. International Transmission argues that to do so would increase cash coverage ratios and the return on equity during the early years of an asset's life and thereby create a tax-related incentive that furthers the Congressional intent to encourage transmission investment.
99
International Transmission states that if it allows companies to use accelerated depreciation, the Commission will need to revisit its Accounting Directive in Order No. 618, in which the Commission stated that recovery over the useful life generally best matches benefits with costs. International Transmission offer that accelerated depreciation could lead to the following problems: (1) Depreciation would no longer be representative of the useful life of assets, (2) the representation of net fixed asset value in financial statements could be distorted; (3) there would be a divergence between Generally Accepted Accounting Principles and Commission reporting and (4) efforts by FASB, the Commission and others to clarify financial reporting could be frustrated.
c. Commission Determination
99
International Transmission notes that Congress reduced the tax depreciable life on transmission investments from 20 years to 15 years to encourage transmission investment. EPAct 2005, section 1308.
146. After considering all comments, we will adopt the NOPR proposal to allow, as an option, accelerated depreciation for new transmission facilities that meet the goals of section 219. Accelerated depreciation increases the cash flow of public utilities thereby providing an incentive to undertake transmission investment. However, we are not proposing to grant accelerated depreciation on a generic basis; rather, as with the other incentives, the applicant must demonstrate a nexus between its proposal and the facts of its particular case (
e.g.
, the need for additional cash flow produced by accelerated depreciation in order to fund new transmission investment).
147. We do not share the commenters' concerns that this incentive will result in intergenerational inequity. Most transmission customers are dependent upon the transmission system serving them and are likely to continue to receive transmission service over the long-term. Thus, unlike in power supply situations where there are greater options to change suppliers, there is little likelihood of intergenerational impact through the use of accelerated depreciation for transmission investment. In the event accelerated depreciation results in higher rates in the near-term, most of the same customers paying the higher rates will benefit from lower transmission rates in the longer-term. We clarify that the use of accelerated depreciation may be proposed for new transmission facilities including additions to capacity on existing facilities.
148. Given the long-term under-investment in transmission, we disagree with the comments of the California Commission that existing policy is sufficient to encourage transmission investment in all situations. As the California Commission is aware, Trans-Elect stated that accelerated depreciation was a necessary component for its participation in the Path 15 project. In response to the mandate of section 219, we believe it is appropriate to offer this rate treatment more broadly to encourage the same successful outcome that was achieved with Path 15. This does not mean that accelerated depreciation is necessary or will be granted for every project. Instead, the applicant will be required to demonstrate that there is a need for the additional cash flow produced by the accelerated depreciation or that the incentive is appropriate for other reasons. Likewise, at this juncture, concerns expressed by some commenters about the potential for overbuilding of transmission facilities as a result of this rate treatment are unsupported and highly speculative.
149. We concur with the comments that suggest the need for flexibility in the length of the depreciable life. Therefore, public utilities may propose using accelerated depreciation for rate purposes over a period of time as short as 15 years. Moreover, we will consider, on a case-by-case basis, depreciable lives of less than 15 years because shorter depreciable lives may be appropriate in certain cases, such as advanced technologies for which the useful life is not necessarily known.
150. Based on the comments, we are mindful of the potential consequences of this rate treatment when the facilities are fully depreciated. Commenters
express concern that the Commission will allow public utilities to recalibrate the amount of depreciation, or institute a management fee. Other commenters state the Commission should require certain rules for sale of the facilities because of complications that will arise from selling fully depreciated assets. We will not address those issues here but will address such issues if and when they occur.
151. Commenters raise various accounting issues. With respect to the effect of this rate treatment on ADIT (accumulated deferred incomes taxes), we disagree that this proposal will necessarily require that no provision for deferred incomes taxes be allowed with respect to such assets (and no deduction from rate base). As stated previously, we are going to be flexible with respect to the depreciable lives of qualifying assets; therefore, public utilities may choose 30 years as Trans-Elect did with Path 15 and as a result deferred income taxes may still be necessary. Moreover, even if public utilities choose 15 years, depreciation expense for rate recovery purposes will likely be calculated using the straight-line method over those 15 years,
100
while accelerated depreciation for tax purposes may be calculated using a different method (
e.g.
, double declining balance) over 15 years. Therefore, despite the use of the same 15 year life, method differences could continue to create timing differences for which deferred income taxes would be required.
100
The straight-line method is typically used by utilities and will likely continue to be used for most utility property. However, consistent with Order No. 618 we will not require its universal use, as they may be overly prescriptive. Order No. 618 at 31,694.
152. With respect to APPA's concern about potential difficulties in applying SFAS 71,
101
the Commission and other rate regulatory authorities often include amounts in allowable costs for ratemaking purposes in periods other than the period in which those amounts would ordinarily be charged to expense or included in income for financial accounting purposes. In those instances, the rate actions of regulators have economic consequences that must be recognized in financial statements. Under both SFAS 71 and the Commission's Uniform System of Accounts, if regulation provides reasonable assurance that incurred costs will be recovered in future periods, companies must capitalize the costs. If current recovery is provided for costs that are expected to be incurred in the future, companies must recognize the current receipts as a credit amount on the balance sheet. Therefore, because the accounting requirements for accelerated depreciation are no different than accounting for the economic consequences of other rate actions, we do not see an impediment to implementing accelerated rate recovery of transmission assets.
101
SFAS 71 applies to general-purpose external financial statements of an enterprise that has regulated operations. The Commission's Uniform System of Accounts for Public Utilities and Licensees (18 CFR Part 101) contains provisions similar to SFAS 71 that apply to financial statements public utilities must file with the Commission.
153. We are not persuaded that we need to revisit Order No. 618 in this proceeding as some commenters suggest. In Order No. 618, the Commission established standards for determining depreciation expense for book purposes. Here we are establishing a standard for determining depreciation expense allowable for rate purposes. Although accounting and cost-based rate setting generally share common standards, there are instances, and this is one, where different standards should be used by each discipline and the difference bridged by recognition of regulatory assets or liabilities as provided for in our Uniform System of Accounts.
102
Therefore, companies will continue to depreciate transmission assets over their economic service life in a systematic and rational manner for accounting purposes and separately recognize as a regulatory liability any difference between depreciation expense recognized for accounting purposes and accelerated depreciation expense included in the development of rates. In order to clarify this distinction the Commission shall revise § 35.35(d)(1)(v) of the regulatory text proposed in the NOPR which read “(v) accelerated regulatory book depreciation.” The revised regulatory text shall read “(v) accelerated depreciation used for rate recovery.”
102
18 CFR part 101.
154. We deny International Transmission's request to alter our section 205 filing requirements for public utilities operating under formula rates. In Order No. 618, the Commission permitted utilities to not make a filing to change depreciation rates for accounting purposes but maintained the filing requirement for changes in depreciation rates for rate purposes.
103
The Commission said it would monitor changes in depreciation rates for accounting purposes when companies filed for rate changes. We decline in this Final Rule to adopt International Transmission's requested changes to formula rates. International Transmission is free to petition the Commission to revise its formula rate to allow flexibility going forward, but we decline to make such a generic determination here because to do so would presume that all formula rates worked in the same manner.
103
Order No. 618 at 31,695.
5. Recovery of Costs of Abandoned Facilities
a. Background
155. The Commission noted that public utilities, in considering investments that fulfill the requirements of FPA section 219, may encounter investment opportunities with significant risk associated with factors beyond their control, such as generation developers' decisions to develop or terminate the development of potential resources or difficulty obtaining state or local siting approvals. In these circumstances, the Commission stated that it may be appropriate to consider ways to reduce the risk associated with potential upgrades or other improvements to the transmission system. To reduce the uncertainty associated with higher risk projects, thereby facilitating investment in these projects, the Commission proposed allowing recovery of 100 percent of the prudently incurred costs of transmission facilities that are cancelled or abandoned due to factors beyond the control of the public utility.
156. The Commission's proposal was an extension of a recent Commission decision to allow Southern California Edison Company
104
to recover all prudently incurred costs related to certain proposed transmission facilities if those facilities were later cancelled or abandoned.
105
The Commission noted that the company's management did not control the decision to develop or cancel the wind farm generation project and that the company's shareholders did not share in the earnings associated with the generation project. The
Commission further determined that the company might be at a higher risk in developing the project because of factors beyond its control. It also noted that SCE was not a wind farm developer and therefore would not directly benefit from the facilities. Thus, the Commission concluded that SCE should not shoulder the risk of the project.
106
104
SCE
, 112 FERC ¶ 61,014 at P 58-61,
reh'g denied
, 113 FERC ¶ 61,143 at P 9-15.
105
Prior to
SCE
, the Commission's policy with respect to recovery of cancelled plant costs provided that 50 percent of the prudently incurred costs of a cancelled generating plant should be amortized as an expense over a period reflecting the life of the plant if it had been completed and that the remaining 50 percent of the prudently incurred costs of the cancelled plant should be written off as a loss. Under this policy, ratepayers are entitled to the income tax deduction associated with that portion of the loss for which they are paying. In addition, they are entitled to a rate base reduction to reflect the accumulated deferred income tax amounts associated with 50 percent of the abandonment loss.
See New England Power Co.
, Opinion No. 295, 42 FERC ¶ 61,016 at 61,068, 61,081-83,
order on reh'g
, 43 FERC ¶ 61,285 (1988).
See also
,
Public Service Company of New Mexico
, 75 FERC ¶ 61,266 at 61,859 (1996) (
PSNew Mexico
).
106
SCE.
at P 61.
b. Comments
157. A number of commenters support the 100 percent recovery of prudently incurred costs of transmission projects that must be abandoned for reasons beyond the transmission provider's control as a way to reduce the up-front risk associated with important regional projects.
107
Some, like the Kentucky Commission,
108
advocate that the Commission should adopt a case-by-case approach to recovery of costs related to cancelled plant.
109
Kentucky Commission agrees that this incentive should be evaluated on a case-by-case basis to ensure that the decision to abandon the facility was truly beyond the utility's control. California Commission and CADWR do not oppose the recovery of 100 percent of the recovery of prudently incurred costs as long as the determination is made on a case-by-case basis. International Transmission states that preliminary surveys and investigations should also be included in the costs that can be recovered.
107
E.g.
, AWEA, Ameren, AEP, EEI, KCPL, NSTAR, Vectren, International Transmission, WPS, APPA, NYSEG-RGE, NorthWestern, National Grid, New York Commission, NY Association, Progress, PNM and TNMP, SDG&E, and Upper Great Plains.
108
E.g.
, California Commission and CADWR.
109
Trans-Elect supports the case-by-case approach and cites
San Diego Gas & Elec. Co.
, 98 FERC ¶ 61,332 at 62,408,
reh'g denied
, 100 FERC ¶ 61,073 (2002) (“claims for full recovery of any infrastructure projects that are ultimately cancelled will be addressed by the Commission on a case-specific basis”).
158. SCE supports the recovery of abandoned plant and recommends specific standards to facilitate the recovery. SCE states that 100 percent of prudently incurred costs should be approved for recovery if the facility was initially proposed and sited through a process involving stakeholder input and the subsequent decision to abandon is not under the control of management. Additionally, SCE states that utilities should be able to recover the costs of abandoned plant even when they have some control over the decision to abandon but the project was cancelled or abandoned due to problems in obtaining regulatory or other approvals. SCE also supports recovery where economic circumstances have changed, causing there to be no demonstrable net benefits.
159. Others
110
oppose the incentive. For example, CREPC states that guaranteeing the cost recovery of cancelled plant allows investors to ignore risk and places the risk on parties who are unable to manage the risk. ESAI argues that allowing recovery of 100% of prudently incurred development costs runs the risk of producing a proliferation of white elephants.
110
E.g.
, CREPC, the New Mexico AG, Steel Manufacturers and TANC.
160. TANC argues that the Commission has upheld and enforced its existing cancelled plant policy and rejected the utility's arguments that it be allowed full recovery of the cancelled plant because it could not get state regulatory approvals; and that the Commission should not adopt a separate policy now.
111
TANC argues the proposal violates the intent of Opinion 295-A which is to encourage investors to make efficient production and consumption decisions.
111
TANC cites
PSNew Mexico.
161. Commenters
112
offer numerous instances where they believe it would be inappropriate to allow a utility to recover abandoned plant costs. For example, the Commission should not permit recovery: where the nature of the project was speculative; and where the project was abandoned for reasons within the control of the utility; or where there is an unexpected turn in the economy. TAPS questions whether project abandonment is really beyond a utility's control if a state siting authority does not outright reject a proposal but instead conditions its acceptance in a way that the utility finds objectionable.
112
E.g.
, Industrial Consumers, Oklahoma Commission, PPC, MISO States, and TAPS.
162. Snohomish asserts applicants must make showings of why the project failed and recoverable costs should be limited to the original budget. New Mexico AG, TDU Systems and TAPS assert that if utilities are guaranteed their investment in abandoned facilities they need a lower ROE to represent the reduced risk of recovery.
c. Commission Determination
163. We find that an applicant may request 100 percent of prudently-incurred costs associated with abandoned transmission projects can be included in transmission rates if such abandonment is outside the control of management. This incentive will be an effective means to encourage transmission development by reducing the risk of non-recovery of costs.
164. Many commenters request that we evaluate proposals on a case-by-case basis and we affirm that we intend to do so. The case-by-case approach and the limitation to prudently-incurred costs should adequately discipline investment decisions. However, we will not prescribe specific rules to govern our evaluation but offer limited guidance below.
165. We agree with many commenters that when local, state and federal (as applicable) siting authorities reject an application outright, we would view those circumstances, generally, as abandonment beyond the control of management. As TAPS points out, the situation is less clear when siting authorities do not reject the application outright but add conditions to the application that make it uneconomical or otherwise objectionable. In these instances we would expect the utility to file with the Commission and support the decision to abandon. The Commission will evaluate, in these instances, the change in circumstances from those originally planned on a case-by-case basis.
166. We see no need to specify unique application procedures for this incentive. We will require a section 205 filing for recovery of abandoned plant costs in rates at the time the project is abandoned. We disagree with CREPC that this incentive shifts risk from those who can manage the risk to those who cannot because this incentive is limited by definition to abandonment that is beyond the control of the utility. We will not by rule limit the recovery of costs associated with abandoned plant to the costs included in the original budget estimate. The Commission will evaluate the public utility's cost recovery to ensure no double recovery of costs. For example, if a utility already recovered survey costs by expensing these costs as a pre-commercial cost, it would be unjust and unreasonable for the utility to recover those costs again if the facility was subsequently abandoned.
113
113
We also clarify that we maintain the timing of recovery as set forth in Opinion No. 295 which required recovery over the life of the asset as if it had gone into service.
167. We will not mandate a reduction in ROE for utilities that receive approval for this rate treatment. As stated in the ROE incentive discussion, determinations of a just and reasonable ROE include risk evaluations made in individual rate proceedings and are based on the facts pertinent to the utility and its proxy group. We note, however, that a utility that receives approval to recover abandoned plant in rate base would likely face lower risk and thus may warrant a lower ROE than would
otherwise be the case without this assurance.
114
This does not mean that the Commission would reject an incentive-based ROE for a project that also receives assurance of abandoned plant costs that are beyond the utility's control. We would consider any such request on a case-by-
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.