Remedying Undue Discrimination Through Open Access Transmission Service and Standard Electricity Market Design

Federal RegisterAug 29, 2002

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

18 CFR Part 35

[Docket No. RM01-12-000]

Remedying Undue Discrimination Through Open Access Transmission Service and Standard Electricity Market Design

July 31, 2002.

AGENCY:

Federal Energy Regulatory Commission, DOE.

ACTION:

Notice of proposed rulemaking.

SUMMARY:

The Federal Energy Regulatory Commission (Commission) proposes to amend its regulations under the Federal Power Act (FPA) to modify the

pro forma

open access transmission tariff established under the Commission's Order No. 888 to remedy remaining undue discrimination in the provision of interstate transmission services and in other industry practices, and to assure just and reasonable rates within and among regional power markets. The Commission proposes to require all public utilities with open access transmission tariffs to file modifications to their tariffs to reflect non-discriminatory, standardized transmission service and standardized wholesale electric market design.

DATES:

Initial comments are due on October 15, 2002. Comments should include an executive summary that does not exceed 10 pages.

ADDRESSES:

Send comments to: Office of the Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.

FOR FURTHER INFORMATION CONTACT:

Alice Fernandez (Technical Information), Office of Markets, Tariffs and Rates, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. (202) 208-0089. (202) 502-6389 (after Aug. 7, 2002).

David Mead (Technical Information), Office of Markets, Tariffs and Rates, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. (202) 208-1024. (202) 502-8028 (after Aug. 7, 2002).

Mark Hegerle (Technical Information), Office of Markets, Tariffs and Rates, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. (202) 208-0287. (202) 502-8287 (after Aug. 7, 2002).

David Withnell (Legal Information), Office of General Counsel, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. (202) 208-2063. (202) 502-8421 (after Aug. 15, 2002).

SUPPLEMENTARY INFORMATION:

In addition to publishing the full text of this document in the

Federal Register

, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the Internet through FERC's home page (

http://www.ferc.gov

) and in FERC's Public Reference Room during normal business hours (8:30 a.m. to 5 p.m. Eastern time) at 888 First Street, NE., Washington, DC 20426.

Table of Contents

Paragraph

I. Introduction

1

II. Background: Order No. 888 and Order No. 2000

20

A. Order Nos. 888 and 888-A

20

B. Order No. 2000

24

III. Need for Reform

31

A. Undue Discrimination and Impediments to Competition Remain

31

B. Specific Instances of Undue Discrimination and Impediments to Competition

36

1. Transmission Market Power by Utilities that are Not Independent

38

a. Load Growth

41

b. Delays in Responding to Requests for Service

43

c. Scheduling Advantages

45

d. Imbalance Resolution

48

e. Available Transfer Capability and Affiliates

50

f. OASIS Postings

52

g. Capacity Benefit Margin Manipulation

55

h. Discretionary Use of Transmission Loading Relief

57

2. Lack of Common Rules Governing Transmission

61

3. Congestion Management

71

4. Seams Problems

80

5. Market Design Flaws

86

C. Reform Essential Given the Changed Nature of the Electric Industry

91

D. Legal Authority and Findings

100

IV. The Proposed Remedy

107

A. The Interim Tariff

117

1. Placing Bundled Retail Customers under the Interim Tariff

118

2. Additional Interim Revisions to the

Pro Forma

Tariff

121

B. Independent Transmission and Markets

124

1. Independent Transmission Providers

125

2. Role of Independent Transmission Companies in Standard Market Design

132

C. The New Transmission Service

136

1. Basic Rights

139

2. Access to Transmission Service

143

3. Service Limitations in the Existing

Pro Forma

Tariff

146

4. Conditions for Receiving Service

148

5. Scheduling Transmission Service and Acquiring Congestion Revenue Rights

149

6. Designating Resources and Loads

152

7. Substituting Receipt and Delivery Points

154

8. System Impact and Facilities Studies

157

9. Load Shedding and Curtailments

158

10. Trading (Reassigning) Congestion Revenue Rights

162

11. Ancillary Services

164

D. Transmission Pricing

165

1. Recovery of Embedded Costs

167

2. Rates for Bundled Retail Customers

176

3. Inter-Regional Transfers

179

4. Application of Inter-Regional Pricing to Parallel Path Flows

190

5. Pricing of New Transmission Capacity

191

E. The New Congestion Management System

203

1. Locational Marginal Pricing

204

2. LMP and Energy Markets

221

3. Congestion Revenue Rights

235

a. General Features

237

b. Types of Congestion Revenue Rights

241

(1) Receipt Point-to-Delivery Point Rights

242

(2) Obligations and Options

245

(3) Flowgate Rights

246

c. Requirement for Offering Rights

248

d. Funding for the Congestion Revenue Rights

250

e. Auctions and Resales of Congestion Revenue Rights

252

f. Including Energy and Ancillary Services in the Congestion Revenue Rights Auctions

254

F. Day-Ahead and Real-Time Market Services

256

1. Design of the Day-Ahead Markets

257

a. Scheduling Transmission Service Day Ahead

258

(1) General Features

258

(2) Transmission Service Across Borders

264

b. Transmission Losses

267

c. Day-Ahead Energy Market

269

(1) General Features

269

(2) Bidding and Scheduling Rules

270

(3) Price Determination and Settlement

277

d. Day-Ahead Ancillary Service Markets

284

(1) General Features

284

(2) Bidding and Scheduling Rules

287

(3) Price Determination and Settlement

291

2. Scheduling After the Close of the Day-Ahead Market

298

a. Replacement Reserves

298

b. Changes to Transmission Schedules

303

3. Design of the Real-Time Markets

305

a. Real-Time Energy Markets

306

(1) General Features

306

(2) Bidding and Scheduling Rules

307

(3) Price Determination and Settlement

310

b. Real-Time Ancillary Services Markets

320

4. Market Rules for Shortages or Emergencies

326

G. Other Changes to Improve the Efficiency of the Markets under Standard Market Design

328

1. Capacity Benefit Margin

330

2. Regional and Independent Calculation of Available Transfer Capability, Performance of Facilities Studies and OASIS

333

3. Regional Planning Process

335

4. Modular Software Design

351

5. Transmission Facilities That Must be Under the Control of an Independent Transmission Provider

361

a. Before Order No. 888

362

b. Order No. 888

365

c. Test for Transmission Facilities

367

H. Transition to Single Transmission Tariff

370

1. Treatment of Customers under Existing Wholesale Contracts

372

2. Allocation of Congestion Revenue Rights

376

3. Reciprocity Provision

383

4. Force Majeure and Indemnification Provisions

385

I. Market Power Mitigation and Monitoring in Markets Operated by the Independent Transmission Provider

390

1. Principles and Objectives

390

2. Overview of the Market Power Mitigation Measures

398

3. Market Power Mitigation for Local Market Power

406

4. The Safety-Net Bid Cap

413

5. Mitigation Triggered by Market Conditions

415

6. Establishing Bid Caps or Competitive Reference Bids

418

7. Exemptions

428

8. Monitoring

429

a. Framework for Analyzing Market Structure and Market Conduct

436

b. Data Requirements and Data Collection

447

c. Reporting Requirements

451

d. Enforcement of the Tariff Rules

454

J. Long-Term Resource Adequacy

457

1. The Reason for the Requirement

460

a. Spot Market Prices Alone Will Not Signal The Need to Begin Development of New Resources in Time to Avert a Shortage

462

b. Spot Market Prices that are Subject to Mitigation Measures May Not Produce an Adequate Level of Investment When a Shortage Occurs

467

c. Load-Serving Entities Will Underinvest in Resources Needed for Reliability if They Can Depend on the Resource Development Investments of Others

469

2. Basic Features of the Requirement

474

a. Demand Forecast

485

b. Level of Resource Adequacy

487

c. Load-Serving Entities

494

d. Load-Serving Entity's Share of the Regional Resource Requirement

497

e. Resources That Can Satisfy the Resource Needs

503

(1) Generation and Transmission

504

(2) Demand Response

507

3. Resource Standards

509

a. Generation Standards

511

b. Transmission Standards

514

c. Demand Response Standards

517

4. Planning Horizon

520

5. Enforcement

526

6. Regional Flexibility

542

K. State Participation in RTO Operations

551

L. Governance for Independent Transmission Providers

556

1. Responsibilities of the Board of Directors

558

2. Stakeholder Participation

560

3. Initial Selection Process for Board of Directors

562

4. Succession of Board Members

569

5. Mergers of Independent Transmission Providers

573

M. System Security

575

V. Implementation

580

VI. Public Comment Procedures

595

VII. Regulatory Flexibility Act

599

VIII. Environmental Statement

603

IX. Public Reporting Burden and Information Collection Statement

604

X. Document Availability

612

Regulatory Text

Appendices

A. Interim

Pro Forma

Tariff Revisions

B. Standard Market Design Tariff (SMD Tariff)

C. Examples of Flaws in the Current Regulatory Environment

D. Conversion of the Order No. 888-A

Pro Forma

Tariff to the Revised Standard Market Design

Pro Forma

Tariff

E. Standard Market Design and Trading Strategies Encountered in the Independent Transmission System Operators

F. Access Charges and Congestion Revenue Rights

G. Form for the Annual Self-Certification of Compliance with FERC Security Standards

I. Introduction

1. This notice of proposed rulemaking represents the third in a series of initiatives undertaken by the Commission to harness the benefits of competitive markets for the nation's electric energy customers, in order to meet our statutory responsibility to assure adequate and reliable supplies of electric energy at a just and reasonable price. In 1996, the Commission issued Order No. 888, which required, as a remedy for undue discrimination, that all public utilities provide open access transmission.

1

In 1999, the Commission issued Order No. 2000.

2

The Commission's objective was “for all transmission owning entities in the Nation, including non-public utility entities, to place their transmission facilities under the control of appropriate regional transmission institutions [RTOs] in a timely manner.”

3

1

Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission Services by Public Utilities and Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888, 61 FR 21,540 (May 10, 1996), FERC Stats. & Regs. ¶ 31,036 (1996),

order on reh'g,

Order No. 888-A, 62 FR 12,274 (March 14, 1997), FERC Stats. & Regs. ¶ 31,048 (1997),

order on reh'g,

Order No. 888-B, 81 FERC ¶ 61,248 (1997),

order on reh'g,

Order No. 888-C, 82 FERC ¶ 61,046 (1998),

aff'd in relevant part, remanded in part on other grounds sub nom. Transmission Access Policy Study Group, et al.

v.

FERC,

225 F.3d 667 (D.C. Cir. 2000),

aff'd sub nom. New York

v.

FERC,

122 S. Ct. 1012 (2002).

2

Regional Transmission Organizations, Order No. 2000, 65 FR 809 (January 6, 2000), FERC Stats. & Regs. ¶ 31,089 (1999),

order on reh'g,

Order No. 2000-A, 65 FR 12,088 (February 25, 2000), FERC Stats. & Regs ¶ 31,092 (2000),

petitions for review dismissed,

Public Utility District No. 1 of Snohomish County,

Washington

v.

FERC,

272 F.3d 607 (D.C. Cir. 2001).

3

Regional Transmission Organizations, 64 FR 31,389 (May 13, 1999), FERC Stats. & Regs. ¶ 32,541 at 33,685 (1999) (Notice of Proposed Rulemaking).

2. Order No. 888 and Order No. 2000 set the foundation upon which to build regional transmission institutions and competitive electricity markets. However, as events have transpired, there remain significant impediments to competitive markets and to the infrastructure needed to meet our electric energy demand. Unduly discriminatory transmission practices have continued to occur and inconsistent design and administration of short-term energy markets has resulted in pricing inefficiencies that can cause rates to be unjust and unreasonable. At the same time, the nature of the electric industry has changed in a way that makes the development of competitive wholesale markets all the more critical. The electric industry has evolved from one characterized by large, vertically integrated utilities to an industry with increasing wholesale trade and increasing numbers of independent buyers and sellers of wholesale power seeking non-discriminatory access to transmission facilities. Public utilities

today purchase significantly more wholesale power to meet their load than in the past. Indeed, from 1989 through 2000, their wholesale purchases increased from 18 percent of their total available electric energy to over 37 percent, and this percentage is expected to continue to grow.

4

4

See

Section III.C. for a more detailed discussion.

3. The Commission's objectives in this third rulemaking initiative, therefore, are to remedy remaining undue discrimination and establish a standardized transmission service and wholesale electric market design that will provide a level playing field for all entities that seek to participate in wholesale electric markets. The Commission proposes to provide new choices through a flexible transmission service, and an open and transparent spot market

5

design that provides the right pricing signals for investment in transmission and generation facilities, as well as investment in demand reduction.

5

The term “spot market” typically refers to a trade that covers a short period in the very near future. Trading in an independent transmission system operator (ISO) real-time or day-ahead market is referred to here as occurring in the spot market. In the Western price mitigation order, the Commission defined a spot market trade as any trade lasting 24 hours or less, whether a bilateral trade or a trade occurring in an organized real-time or day-ahead market that does not match up particular sellers and buyers.

See

San Diego Gas and Electric Company v. Sellers of Energy and Ancillary Services into Markets Operated by the California Independent System Operator and the California Power Exchange, 95 FERC ¶ 61,418 at 64,525 n.3 (2001). We will adopt this meaning for this rulemaking.

4. When supply and demand do not support fully competitive markets, market design should provide protection against market power. We seek in this rulemaking to put in place sufficient regulatory backstops to protect customers against the exercise of market power when structures do not support a competitive market. Market monitoring at all times, and market power mitigation when needed, are critical pieces of this initiative.

5. A significant impediment to achieving the full benefits of competition is that there is no single set of rules governing transmission of electric energy. Not only does the Order No. 888

pro forma

tariff contain provisions that allow different types of customers to be treated differently, but there also are conflicting state and Federal rules governing the use of interstate transmission facilities. This provides opportunities for transmission providers to establish and apply rules in a way that unduly discriminates against certain classes of customers, leads to significant transaction costs and threatens reliability.

6. To remedy undue discrimination, enhance competition, remove economic inefficiencies and ensure just and reasonable rates, terms and conditions transmission of electric energy, the Commission proposes to: Exercise jurisdiction over the transmission component of bundled retail transactions; modify the existing

pro forma

transmission tariff to include a single flexible transmission service (Network Access Service) that applies consistent transmission rules for all transmission customers—wholesale, unbundled retail and bundled retail; and provide a standard market design for wholesale electric markets. While it is critical that the same non-rate terms and conditions be applied to all transmission uses, including bundled retail, as soon as possible, we intend to work closely with our state colleagues with respect to transition issues involving bundled retail transmission rates

7. The proposed Network Access Service would combine features of both existing open access transmission services—the flexibility and resource and load integration of Network Integration Transmission Service; and the reassignment rights of Point-to-Point Transmission Service. It would give a customer the right to transmit power between any points on the transmission system—so long as the transaction is feasible under a security-constrained dispatch.

8. We expect that most if not all entities will become members of RTOs and that the new Network Access Service would be provided through these RTOs. However, this rule may become effective at a time when some transmission owners and operators have not yet become members of functioning RTOs. Thus, we propose that all transmission owners and operators that have not yet joined an RTO must contract with an independent entity to operate their transmission facilities. This proposed rule refers to both the RTO and those independent entities as “Independent Transmission Providers.” An Independent Transmission Provider would have no financial interest, either directly or through an affiliate, as defined in section 2(a)(11) of the Public Utility Holding Company Act (15 U.S.C. 79b(a)(11), in any market participant

6

in the region in which it provides transmission services or in neighboring regions. We propose that all Independent Transmission Providers administer the day-ahead and real-time markets. As discussed

infra,

we also have identified long-term planning and expansion, system impact and facilities studies and transmission transfer capability calculations (including postings on an Open Access Same-time Information System (OASIS)) as tasks that must be done on a regional basis. Thus, we propose that all Independent Transmission Providers perform these tasks.

6

A market participant means: (i) Any entity that, either directly or through an affiliate, sells or brokers electric energy, or provides ancillary services to the [RTO], unless the Commission finds that the entity does not have economic or commercial interests that would be significantly affected by the [RTO's] actions or decisions; and (ii) Any entity that the Commission finds has economic or commercial interests that would be significantly affected by the [RTO's] actions or decisions. 18 CFR 35.34 (2) (2002).

9. In addition to creating the new Network Access Service, the revised tariff would include requirements to standardize wholesale electric market design. The fundamental goal of the Standard Market Design requirements, in conjunction with the standardized transmission service, is to create “seamless” wholesale power markets that allow sellers to transact easily across transmission grid boundaries and that allow customers to receive the benefits of lower-cost and more reliable electric supply. For example, currently a supplier that seeks to serve load in a distant state may need to cross several utility systems or independent system operator systems (ISOs), all of which have different rules for such things as reserving and scheduling transmission and scheduling generation. This can either result in an efficient transaction not occurring at all or it can add significant time and costs to the transaction. Standard Market Design seeks to eliminate such impediments.

10. Central to the Standard Market Design concept is its reliance on bilateral contracts entered into between buyers and sellers. The resource adequacy requirement strongly encourages such long-term contracts. The short-term spot markets set out below are intended to complement bilateral procurement. To handle generation imbalances and the procurement of ancillary services, the Commission proposes to require that all Independent Transmission Providers operate markets for energy and for the procurement of certain ancillary services in conjunction with markets for transmission service. These markets would be bid-based, security-constrained spot markets operated in two time frames: (1) A day ahead of real-time operations, and (2) in real time. The adoption of a market-based

locational marginal pricing (LMP) transmission congestion management system is designed to provide a mechanism for allocating scarce transmission capacity to those who value it most, while also sending proper price signals to encourage short-term efficiency in the provision of transmission service as well as wholesale energy, and to encourage long-term efficiency in the development of transmission, generation and demand response infrastructure. We expect that market participants will strike an appropriate balance between bilateral contracts and spot market transactions. Efficient spot markets with appropriate price signals bring bilateral and spot market prices closer together, helping to assure customers of efficient bilateral markets.

11. Several changes required by Standard Market Design promote greater customer access to low-cost power. We note that this may raise concerns that cheap power may leave one region for sale in another, higher-priced region. This can only happen with generation that is not already under contract for purchase. Thus, customers in low-cost regions can ensure that low-cost power “stays home” by contracting for that power. This way, only excess power will leave the region to serve another market.

12. The Commission proposes a pricing policy and process for recovering the costs of new transmission investment so as to develop the infrastructure needed to support competitive markets. The policy builds on the price signals provided by the proposed spot market design. However, there are cases where LMP price signals alone will not encourage all beneficial transmission investments. Therefore, we propose to require market participants to participate in a regional process to identify the most efficient and effective means to maintain reliability and eliminate critical transmission constraints.

13. Even with good market design rules, current supply and demand conditions make a market monitoring and market power mitigation plan necessary. The market power mitigation proposed in this rule would rely on a combination of methods to protect against the exercise of market power by preventing sellers from withholding economical supplies from the market, while permitting prices to reflect true scarcity. The proposed market power mitigation method should be more restrictive at times or places where the exercise of market power is more likely to occur than at times or places where the market is sufficiently competitive.

14. However, because market power mitigation may tend to suppress scarcity prices that signal the need for investment, a companion mechanism besides spot prices is needed. The Commission proposes a resource adequacy requirement to ensure adequate electric generating, transmission and demand response infrastructure, the level of which is to be determined on a regional basis. Recognizing that supply planning and retail customer demand response are the states' responsibility, the Commission proposes a resource adequacy requirement intended to complement existing state programs. In particular, the Commission proposes that an RTO or other regional entity must forecast the region's future resource needs, facilitate regional determination of an adequate future level of resources and assess the adequacy of the plans of load-serving entities

7

to meet the regional needs. Each load-serving entity would be required to meet its share of the future regional need through a combination of generation and demand reduction.

7

A load-serving entity is an entity, including a municipal electric system and an electric cooperative, authorized by law, regulatory authorization or requirement, agreement, or contractual obligation to supply energy, capacity, and/or ancillary services to retail customers located within the transmission provider's service area, including an entity that takes service directly from the transmission provider to supply its own load in the transmission provider's service area.

See

SMD Tariff § 1.

15. In summary, in this proceeding, the Commission, pursuant to its authority under sections 205 and 206 of the Federal Power Act,

8

proposes to:

8

16 U.S.C. 824d and 824e (1994).

(1) Establish a single non-discriminatory open access transmission tariff with a single transmission service (Network Access Service) that is applicable to all users of the interstate transmission grid: wholesale and unbundled retail transmission customers, and bundled retail customers;

(2) Require all public utilities that own, control or operate interstate transmission facilities to become an Independent Transmission Provider, turn over their transmission facilities to an Independent Transmission Provider or contract with an Independent Transmission Provider to operate their facilities. An Independent Transmission Provider is any public utility that owns, controls or operates facilities used for the transmission of electric energy in interstate commerce, that administers the day-ahead and real-time energy and ancillary services markets in connection with its provision of transmission services pursuant to the SMD Tariff, and that is independent (

i.e.

, has no financial interest, either directly or through an affiliate, as defined in section 2(a)(11) of the Public Utility Holding Company Act (15 U.S.C. 79b(a)(11), in any market participant in the region in which it provides transmission service or in neighboring regions).

(3) Require that an Independent Transmission Provider provide transmission services and administer the day-ahead and real-time energy and ancillary services markets;

(4) Establish an access charge to recover embedded transmission costs based on a customer's load ratio share of the Independent Transmission Provider's costs, and would be paid by any customer taking power off the grid;

9

9

As explained in section IV.D.1, current long-term point-to-point customers that seek to receive Congestion Revenue Rights would also pay the access charge.

(5) Use LMP as the system for transmission congestion management and provide tradable financial rights—Congestion Revenue Rights

10

as a means to lock in a fixed price for transmission service;

10

These rights were called “Transmission Rights” in the Working Paper on Standardized Transmission Service and Wholesale Electric Market Design, Docket No. RM01-12-000 (Mar. 15, 2002) (hereinafter Working Paper).

(6) Establish a preference for the auction of Congestion Revenue Rights, but initially allow regional flexibility for a four-year transition period in determining whether to allocate Congestion Revenue Rights to existing customers or auction such rights such that revenues are allocated to existing customers to hold them financially harmless;

(7) Establish open imbalance energy markets to allow all market participants to buy or sell their imbalances in a fair, efficient and non-discriminatory market. Imbalance markets would be neutral towards fuel sources and treat demand resources on an equal footing with supply;

(8) Permit customers under existing contracts to receive the same level and quality of service under Standard Market Design that they receive under their current contracts, to the greatest extent feasible;

(9) Establish procedures to mitigate market power in the day-ahead and real-time markets required by Standard Market Design and mechanisms for market monitoring;

(10) Establish procedures to assure, on a long-term regional basis, that there are adequate transmission, generation and demand-side resources;

(11) Provide a formal role for state representatives to participate in the

decision-making processes of Independent Transmission Providers; and

(12) Clarify the obligation of all users of the transmission system to comply with all appropriate standards for ensuring system security and reliability.

16. The Commission's focus is on promoting the development of competitive wholesale markets and we do not intend to interfere with the legitimate concerns of state regulatory authorities. It remains within a state's authority to determine whether or not to provide retail access. Nevertheless, the reforms proposed in this rulemaking will benefit customers in states with or without retail access. In addition, we seek to formally involve state representatives in the decision-making processes of regional entities. We also recognize the need to permit parties to continue to rely on existing contracts and scheduling practices, including those involving hydroelectric power, and these are fully accommodated under Standard Market Design.

17. The Commission recognizes that differences exist throughout the regions of the country; however, the Commission's goal is to remedy undue discrimination by standardizing transmission service and wholesale electric market design as much as possible. We propose to allow certain regional variations, as described

infra

.

18. Finally, the Commission recognizes that implementation of a revised open access transmission tariff and Standard Market Design on a nationwide basis may take some time. Thus, the Commission proposes a phased compliance process. By July 31, 2003, all public utilities that own, operate or control interstate transmission facilities must file revised open access transmission tariffs (Interim Tariffs) to become effective September 30, 2004, that reflect the inclusion of bundled retail customers as eligible customers. By December 1, 2003, all public utilities that own, control or operate interstate transmission facilities must file revised open access transmission tariffs (SMD Tariffs), to become effective no later than September 30, 2004, or such other time as directed by the Commission, that reflect all of the remaining revisions and requirements of the Final Rule in this proceeding. The Commission and its staff will work with regional organizations and stakeholders in facilitating full and efficient compliance with this rule.

19. Below in Section II we set out the relevant developments in the electric industry. In Section III and Appendix C we explain the need for further reform. In Appendix E, we discuss various allegations of market manipulation strategies encountered in the organized markets and how Standard Market Design will address these strategies. In Section IV we explain our specific remedy for pervasive problems in the industry consistent with our statutory responsibilities. In Section V, we set out the implementation process and dates. Finally, the glossary for the terms used in this document is found in the Definitions section of the SMD Tariff in Appendix B, and the revisions to the Interim Tariff are set out in Appendix A.

II. Background: Order No. 888 and Order No. 2000

A. Order Nos. 888 and 888-A

20. In April 1996, in Order No. 888, the Commission found that unduly discriminatory and anticompetitive practices existed in the electric industry, and that public utilities that own, control or operate interstate transmission facilities had discriminated against others seeking transmission access. It determined that non-discriminatory open access transmission services, including access to transmission information, and stranded cost recovery were the most critical components of a successful transition to competitive wholesale electricity markets.

11

The Commission stated that its goal was to ensure that customers have the benefits of competitively priced generation.

11

See

Order No. 888 at 31,652.

21. Order No. 888 required all public utilities that own, control or operate facilities used for transmitting electric energy in interstate commerce to: (1) File open access non-discriminatory transmission tariffs containing certain minimum, non-price terms and conditions, and (2) functionally unbundle wholesale power services from transmission services.

12

Functional unbundling requires public utilities to: (1) Take wholesale transmission services under the same tariff of general applicability as they offer their customers; (2) state separate rates for wholesale generation, transmission, and ancillary services; and (3) rely on the same electronic information network that their transmission customers rely on to obtain information about the utilities' transmission systems.

13

In Order No. 889, issued concurrent with Order No. 888, the Commission also imposed standards of conduct governing communications between the utility's transmission and wholesale power functions, to prevent the utility from giving its power marketing arm preferential access to transmission information.

14

Under Order No. 889, all public utilities that own, control or operate facilities used in the transmission of electric energy in interstate commerce are required to create or participate in an OASIS that provides existing and potential transmission customers the same access to transmission information that will enable them to obtain open access non-discriminatory transmission service.

12

See id.

at 31,635-36.

13

See id.

at 31,654.

14

See

Open Access Same-Time Information System and Standards of Conduct, Order No. 889, 61 FR 21,737 (April 24 1996), FERC Stats. & Regs. ¶ 31,035 at 31,588-91 (1996),

order on reh'g,

Order No. 889-A, 62 FR 12,484 (March 4, 1997), FERC Stats. & Regs. ¶ 31,049 (1997).

22. The Commission declined to require corporate unbundling at the time of Order No. 888, and stated instead that efforts to remedy undue discrimination should begin by requiring the less intrusive functional unbundling approach.

15

While the Commission in Order No. 888 encouraged the creation of ISOs and set forth eleven principles for assessing ISO proposals submitted to the Commission, it did not mandate regional organizations.

16

The Commission in Order No. 888 stated:

15

See

Order No. 888 at 31,654.

16

See

id. at 31,730-32.

[W]e see many benefits in ISOs, and encourage utilities to consider ISOs as a tool to meet the demands of the competitive marketplace. As a further precaution against discriminatory behavior, we will continue to monitor electricity markets to ensure that functional unbundling adequately protects transmission customers. At the same time, we will analyze all alternative proposals, including formation of ISOs, and, if it becomes apparent that functional unbundling is inadequate or unworkable in assuring non-discriminatory open access transmission, we will reevaluate our position and decide whether other mechanisms, such as ISOs, should be required.

17

17

Id.

at 31,655.

Order No. 888-A reaffirmed the findings of Order No. 888. The Court of Appeals for the District of Columbia Circuit upheld the orders “in nearly all respects.”

18

The Supreme Court recently affirmed.

19

18

Transmission Access Policy Study Group, 225 F.3d at 681.

19

See New York

v.

FERC,

122 S.Ct. 1012.

23. A number of significant developments took place in the electric utility industry following issuance of Order No. 888. All public utilities filed non-discriminatory, open access transmission tariffs stating rates, terms and conditions for comparable

wholesale transmission service to third-party users of their transmission systems. With the advent of OASIS systems, improved information about transmission systems became available to all participants in the bulk power market at the same time that it was available to utilities' own wholesale merchant functions and wholesale marketing affiliates (although further information improvements are still needed). New generation resources were developed in areas that had experienced generation shortages.

20

Regional trading patterns have expanded. In addition, the Commission granted a large number of merger applications and applications to charge market-based rates, effecting structural changes in the industry. The industry thus became less localized and more regionalized, with a growing need for regional planning and regulation. And as part of that regionalization, the Commission also approved voluntary ISOs in five regions of the country—New England, New York, PJM,

21

the Midwest and California (an ISO was also formed in ERCOT, but it is not under the Commission's full jurisdiction). These ISOs are the precursors to regional entities identified as RTOs, in the Commission's Order No. 2000, discussed below.

20

See

Staff Report to the Federal Energy Regulatory Commission on the Causes of the Pricing Abnormalities in the Midwest During June 1998 (1998),

available in http://www.ferc.gov/electric/mastback.pdf.

21

The PJM ISO takes its name from the former Pennsylvania, New Jersey, Maryland Power Pool, which serves New Jersey, Maryland, Delaware, much of eastern Pennsylvania, the District of Columbia, and a small area of Virginia.

B. Order No. 2000

24. Order No. 2000, issued in December 1999, was the Commission's second major step toward establishing competitive wholesale power markets and eliminating residual undue discrimination in interstate transmission services. It identified two broad categories of impediments to competitive electricity markets: (1) The engineering and economic inefficiencies inherent in the current operation and expansion of the transmission grid, and (2) continuing opportunities for transmission owners to unduly discriminate in the operation of their transmission systems so as to favor their own (or their affiliates') power marketing activities.

22

Further, evidence indicated that local management of the transmission grid by many individual vertically integrated utilities was inadequate to support the efficient, reliable regionwide operation that was needed for continued development of competitive markets. The Commission concluded that establishing independent RTOs would eliminate residual undue discrimination in transmission, enhance the benefits of competitive electricity markets, and could: (1) Improve efficiency in transmission grid management; (2) improve grid reliability; (3) remove remaining opportunities for discriminatory transmission practices; (4) improve market performance; and (5) facilitate lighter-handed regulation. The Commission anticipated that formation of regional transmission grids would result in a substantial cost savings to the electric utility industry and its customers.

23

22

Order No. 2000 identified four specific areas of concerns: (1) Calculation and posting of Available Transfer Capability in a manner favorable to the transmission provider; (2) standards of conduct violations; (3) line loading relief and congestion management; and (4) OASIS sites that are difficult to use. See Order No. 2000 at 31,005 n.69. The order also identified parallel path flows, planning and investing in new transmission facilities, pancaking of access charges, the absence of secondary markets in transmission service and the possible disincentives created by the level and structure of transmission rates.

See id.

at 31,014.

23

See id.

at 30,993.

25. Order No. 2000 encouraged all transmission owners to voluntarily place their transmission facilities in the hands of appropriate RTOs. The Commission stated that RTOs could include ISOs or independent for-profit transmission companies (ITCs). However, all RTOs must meet four minimum characteristics and eight minimum functions that were identified in Order No. 2000, and also must have an open architecture framework that would permit an RTO and its members flexibility to improve their structures over time.

24

24

The four RTO characteristics are: (1) Independence; (2) scope and regional configuration; (3) operational authority; and (4) short-term reliability. The eight RTO functions are: (1) Tariff administration and design; (2) congestion management; (3) parallel path flow; (4) ancillary services; (5) OASIS, Total Transfer Capability and Available Transfer Capability; (6) market monitoring; (7) planning and expansion; and (8) interregional coordination.

See

Order No. 2000 at 30,993-94.

26. Following Order No. 2000, some transmission-owning public utilities began to file proposals to participate in RTOs. The process has been slow for several reasons, one of which is stakeholder uncertainty about what the Commission would require for RTO approval—not only for the RTO scope and independence characteristics, but also regarding such RTO functions as congestion management and market-oriented provision of ancillary services.

27. Order No. 2000 called for RTOs to be in operation across the nation by December 2001. To date, there is only one RTO fully approved by the Commission, the Midwest ISO, which began operating in early 2002.

25

The Midwest ISO is large. It stretches from an eastern boundary in western Pennsylvania westward to the Rocky Mountains, northward into Manitoba, Canada and southward to the Texas border.

25

See

Midwest Independent System Operator, Inc., 97 FERC ¶ 61,326 (2001).

28. Although progress with Commission-approved RTOs has been slow, regionalization has also occurred through the ISO formation process that was encouraged in Order No. 888. The Northeast and California ISOs are engaged in a process to become Commission-approved RTOs or to join larger RTOs. In eastern North America, close coordination is developing between U.S. and Canadian transmission systems and market designs.

29. In addition to the Midwest ISO, the Commission has provisionally approved other RTOs,

26

and authorized operation of ITCs that operate under an RTO umbrella.

27

The Commission also ordered Northeastern and Southeastern RTO applicants, including some applicants whose RTO proposals had been provisionally approved, into mediation proceedings to facilitate the formation of RTOs in those areas.

28

The Commission further noted that a “west wide RTO, or a seamless integration of Western RTOs, is the best vehicle for designing and implementing a long-term regional solution” to the West's electric generation supply crisis.

29

26

See

GridSouth Transco, LLC, 94 FERC ¶ 61,273 (2001); GridFlorida, LLC, 94 FERC ¶61,363 (2001); and PJM Interconnection, LLC, 96 FERC ¶61,061 (2001).

27

See

TRANSLink Transmission Company, L.L.C.,

et al.,

99 FERC ¶61,106 (2002) (authorizing operation of ITC within the Midwest ISO),

reh'g pending,

[Docket Nos. EC01-156-001

et al.;

Alliance Companies,

et al.,

99 FERC ¶61,105 (2002) (authorizing the operation of an ITC).

28

See

Regional Transmission Organizations, 96 FERC ¶61,065 (2001) (initiating mediation proceedings between Northeastern RTO applicants); Regional Transmission Organizations, 96 FERC ¶61,066 (2001) (initiating mediation proceedings between Southeastern RTO applicants).

29

Removing Obstacles to Increased Electric Generation and Natural Gas Supply in the Western United States, 94 FERC ¶61,272 at 61,974 (2001). A coalition of Western utilities (RTO West Filing Utilities) filed a proposal on October 16, 2001 to create RTO West. The Commission granted several of the RTO West Filing Utilities' requests for declaratory order on April 26, 2001, finding some of RTO West's proposed characteristics and functions compliant with Order No. 2000.

See

Avista Corporation,

et al.,

95 FERC ¶61,114 (2001). The RTO West Filing Utilities then filed a proposal for Stage 2 of RTO West's creation on March 28, 2002. The Stage 2 proposal is intended to enable the Commission to determine whether the RTO West proposal fulfills all of the Order No. 2000 characteristics and functions.

See

Stage 2 Filing and Request for Declaratory Order Pursuant to Order 2000 at 5, Docket No. RT01-35-000 (Mar. 28, 2002).

30. The following section and related Appendix C discuss specific features of today's wholesale electricity markets that inhibit the development of competition and efficient regional markets, and identify areas in which the Commission must direct reforms to eliminate remaining undue discrimination and inefficiencies, and ensure just and reasonable rates.

III. Need for Reform

A. Undue Discrimination and Impediments to Competition Remain

31. Since the issuance of Order Nos. 888 and 2000, it has become clear that additional, mandatory measures are needed to achieve the goals of non-discriminatory transmission access and competition in electricity markets. Vertically integrated transmission owners and operators continue to use their interstate transmission facilities in ways that inhibit competition in wholesale power markets as well as competition in those retail power markets where states have adopted retail choice. The discriminatory preferences that these transmission owners and operators give to their own uses of the interstate transmission grid to serve their retail customers (whether or not they are in retail choice states) results in discrimination against, and in costs being borne by, other wholesale and retail customers who also rely on the interstate transmission facilities to buy power. The discriminatory preferences also create barriers to new sellers that could provide lower-cost power. This could result in higher prices to the native load served by the transmission owner. For example, transmission-dependent utilities

30

and other load-serving entities need the interstate transmission facilities to move power they are purchasing by contract from distant generators or suppliers, but allege that despite the requirements of Order No. 888, they are denied comparable access to the grid. Similarly, new generators wishing to compete in wholesale markets or for retail customers in retail choice states tell us that they are denied comparable access to the grid, thus inhibiting entry of new, lower-cost, efficient and environmentally superior power suppliers.

30

A transmission-dependent utility is a utility that does not own generation and relies on its neighboring utilities to transmit power to it that it purchases from its suppliers.

32. The Commission recently has taken additional steps to address some of the remaining impediments to non-discriminatory transmission access and competition in wholesale power markets. For example, the Commission's recently issued Generator Interconnection proposed rule seeks to remove one particular type of undue discrimination occurring in the marketplace—barriers to obtaining interconnections to the interstate transmission grid—so that new generators can compete with vertically integrated transmission providers to serve load.

31

However, this initiative will resolve only one aspect of remaining discriminatory practices. Other opportunities for vertically integrated transmission providers to operate in ways that favor their own generation remain within the construct of the pro forma tariff (

e.g.

, preferences for native load and network customers to reserve transmission capability, differing transmission services that raise barriers to competition, the lack of inclusion of all services under the same tariff). As noted in Order No. 2000, “perceptions of discrimination are significant impediments to competitive markets. Efficient and competitive markets will develop only if market participants have confidence that the system is administered fairly.”

32

31

See Standardization of Generator Interconnection Agreements and Procedures, 67 FR 22,249 (May 2, 2002), FERC Stats. & Regs. ¶32,560 at 34,174 (2002) (Notice of Proposed Rulemaking). The proposed rule defines interconnection study time frames and grants all generators the opportunity to be treated as competing network resources in meeting load and load growth.

See id.

at 34,243-45.

32

Order No. 2000 at 31,017. Lack of market confidence may lead to a reluctance on the part of market participants to share operational real-time and planning data with transmission providers because of the suspicion that they could be providing a competitive advantage to their affiliated power marketers. It may also deter generation expansion and lead to the perception that the transmission provider's generation is more reliable, thereby reducing competition and raising prices for customers.

See id.

33. Furthermore, it has become apparent that there are also opportunities to discriminate and to hinder an efficient, competitive marketplace due to the absence of standardization with respect to market rules and practices within and between regional markets. So-called “seams” problems (

e.g.

, different rules and different pricing systems) create transaction costs and artificial barriers to trade. These problems inhibit the Commission from fulfilling its statutory responsibility to ensure that customers receive reliable power supplies at the lowest reasonable costs.

33

33

See FPC

v.

Hope Natural Gas Company,

320 U.S. 591, 610 (1944).

34. Finally, innovation that the Commission expected to see with respect to new service offerings has been sporadic and unsteady. Innovations in transmission control and pricing (

e.g.

, ISO control of transmission and LMP for generation and transmission services in the Northeast, RTO formation in the Midwest), while impressive, have been slow to take root in other regions of the country. The

pro forma

tariff was envisioned as the baseline above which transmission providers were encouraged to develop competitive and customer-responsive service offerings. But Florida Power Corporation's network contract demand service, a hybrid of Network Integration Transmission Service and Point-to-Point Transmission Service features,

34

and Duke Energy Corporation's “recallable long-term firm” service

35

are the only noteworthy new services accepted by the Commission for use with a single utility's open access transmission tariff. Other proposed

pro forma

tariff revisions amounted to little more than working around the edges of the existing services and procedures and did not produce more competitive transmission service that reduces overall electricity costs.

34

See

Florida Power Corporation, 81 FERC ¶ 61,247 (1997).

35

See

Duke Energy Corporation, 88 FERC ¶ 61,184, reh'g denied, 89 FERC ¶ 61,190 (1999).

35. Most ISOs recently introduced centralized short-term real-time hourly markets and day-ahead markets for energy (

i.e.

, spot markets) where sellers sell into the market and buyers buy from the market without matching a particular seller with a particular buyer. In such organized spot markets, there is a single market clearing price established that is received by all generators who bid into the market below that price and is paid by all load that bids in above that price. However, the ability of customers to bid demand reductions into the spot market in response to supplier prices is still limited and needs to be improved significantly for short-term markets to operate more competitively. Further, while there have been benefits of market development in the Northeast (PJM, New York ISO, ISO-New England), Texas and California (during the first two years of its restructuring), the Midwest ISO is still in the formative stages of operation with respect to markets, and few market benefits have materialized in the Southeast and West.

B. Specific Instances of Undue Discrimination and Impediments to Competition

36. The specific reasons for requiring reform are many. Market participants

have identified, through formal complaints, hotline calls, public conferences, and pleadings, the difficulties they have experienced in gaining equal access to the transmission grid to compete with vertically integrated utilities to serve load. Much of this problem is directly attributable to the remaining ability of such vertically integrated utilities (and the existence of sufficient incentives) to exercise some degree of transmission market power in order to protect their own generation market share. Further complicating transmission access is the fact that not all transmission service is provided under the rates, terms and conditions of the Commission's

pro forma

tariff. Rather, over 60 percent of load has been subject to various state rules governing the transmission component of bundled retail transactions. Independent transmission service under a common set of rules would solve many of these problems.

37. Nevertheless, new problems have been created by some of the market design experiments. In regions of the country where the separation of transmission from generation has been addressed through the creation of ISOs (which, in some instances, have placed nearly all load under a single tariff), market design flaws create inefficiencies in the marketplace and opportunities for the exercise of market power. Conflicting market rules and procedures in neighboring ISOs have created or perpetuated seams problems that impede the economic flow of power from one region to another. All of these problems have hindered the progress towards competitive regional electricity markets. Standard Market Design is intended to address these problems.

1. Transmission Market Power by Utilities That Are Not Independent

38. By differing means, Order Nos. 888 and 2000 attempt to effect open access transmission by reducing the ability of transmission owners that also own generators to act in anticompetitive or unduly discriminatory ways against other generators. In both orders, the Commission attempted to move the electric industry into a competitive wholesale market without mandating corporate restructuring. Through Order Nos. 888 and 2000, the Commission required open access to public utility transmission systems, encouraged the formation of ISOs and, later, RTOs to achieve control of the transmission grid by entities that are independent from generation marketing or sales. However, only limited portions of the country have moved beyond the basic requirements of open access (

e.g.

, through the voluntary divestiture of generation or establishment of RTOs, ISOs, or ITCs). In the rest of the country, the remaining corporate ties between generation and transmission within public utilities have proven problematic for transmission access. Thus, across most of the nation, barriers to entry remain for new generators and new load-serving entities.

39. A large portion of this problem is directly attributable to the continued ability of vertically integrated transmission providers to exercise some degree of transmission market power to advantage their own or affiliated generation. The longer the vertically integrated transmission provider can use access to interconnection or transmission service to delay or prevent entry of competing generators to its service territory, the longer it can profit from its own generation sales with a limited threat of competition. Vertically integrated transmission providers have found numerous ways to delay or prevent entry of competitors, some within the existing rules and some by exceeding reasonable discretion afforded to the transmission provider. All of these are difficult to monitor or prevent with behavioral rules.

36

36

See

Working Paper at 21 (Mar. 15, 2002);

see also

Comment of the Staff of the Bureau of Economics and Office of General Counsel of the Federal Trade Commission, Docket No. RM01-12-000 (July 23, 2002).

40. As part of Standard Market Design, we propose that an Independent Transmission Provider operate all transmission facilities. The requirement for independent control of the transmission grid, preferably by an RTO, resolves these types of problems.

a. Load Growth

41. Under the current

pro forma

tariff, a transmission provider is required to plan its system to allow customers with existing long-term contracts to extend, or roll over, those contracts.

37

However, the transmission provider has a right to recall that transmission capacity if it identified in the initial agreement with the customer that it had projected native load growth that would require that transmission capacity.

38

Transmission providers have failed to identify any native load growth at the time of the initial agreement, and disputes have arisen with customers claiming they were denied the ability to roll over their contracts because the transmission provider claimed, well after the contract was executed, that the transmission capacity at issue was required to serve native load growth.

39

37

See

Section 2.2 of the current

pro forma

tariff.

38

See

Order No. 888-A at 30,277.

39

See Public Service Company of New Mexico

v.

Arizona Public Service Co.,

99 FERC ¶ 61,162 (2002), for a recent example. In this case, the Commission directed APS to grant PSNM's request to extend its contract for 60 MW of Point-to-Point Transmission Service. APS had attempted to deny the rollover request on the basis that it had verbally informed PSNM that capacity would not be available due to APS's future native load growth. The Commission restated the principle that a transmission provider can deny a customer the ability to roll over its long-term firm service contract only if the transmission provider includes in the service agreement a specific limitation based on reasonably forecasted native load needs that will use the transmission capacity provided under the contract at the end of the contract term.

42. In Standard Market Design, we propose to eliminate the preference for future native load growth. Instead, since Congestion Revenue Rights will be used to assure price certainty, Congestion Revenue Rights will be apportioned based on historical use or by an auction, neither of which grants preference for future load growth by a particular supplier; this approach resolves these concerns.

b. Delays in Responding to Requests for Service

43. Another type of anticompetitive behavior centers on a vertically integrated transmission provider delaying the processing of a competitor's request for new transmission service or interconnection (including the related system impact or facilities studies). Transmission providers have done so by failing to follow time lines or expansively interpreting the tariff procedures. These delays may be enough to cause the competing generator to lose the sale, particularly if the potential customer is concerned that it may lose service completely if it does not stay with the transmission provider.

40

40

See Kinder Morgan Power Co.

v.

Southern Company Services, Inc.,

97 FERC ¶ 61,240 (2001),

reh'g denied,

98 FERC ¶ 61,044 (2002) (finding Southern's interconnection procedures delayed and discriminated against customer's ability to develop new projects).

44. Under Standard Market Design, these types of delays are resolved through the requirement for an independent entity, preferably an RTO, to perform studies and calculate available transfer capability (ATC),

41

since an independent entity would have no incentive to favor one customer over another.

41

The Commission used the term ‘‘Available Transmission Capability” in Order No. 888 to describe the amount of additional capability available in the transmission network to accommodate additional transmission services. To be consistent with the term generally accepted throughout the industry, “Available Transfer Capability” will be used.

c. Scheduling Advantages

45. A vertically integrated transmission provider has a structural advantage over many competitors to make economy sales or to serve its own load, primarily because it has a large portfolio of both generators and loads. A competitor with access only to generation outside of the control area and no native load has to identify the delivery point of its power before being able to secure transmission service. But a vertically integrated transmission provider does not have to identify a specific location on the grid to serve its load because its load is dispersed across its entire system. A vertically integrated transmission provider also does not have to identify a single generation location, but can run a combination of its own generators or purchase from lower cost-suppliers inside or outside of its system. It can schedule purchased power to one of its own loads (in place of power from one of its own generators) in order to secure transmission service for the purchase. Later, it can find a buyer for the power and schedule transmission service from one of its internal generators to the load. This often is enough of a scheduling advantage over a competing supplier to ensure that the transmission provider (or its affiliated power marketer) gets the sale.

46. While it is true that all network customers have these same rights and abilities, in many areas of the country the only customer using network service is the vertically integrated transmission provider. Moreover, the vertically integrated transmission provider's size of resources and loads is usually much greater than any other network customer, giving it that much more of an advantage in flexibility. In addition, the vertically integrated transmission provider may have an advantage through access to better or more transmission and other related information.

47. Under Standard Market Design, all transmission service will be provided under a new Network Access Service. Having one service for all customers will eliminate scheduling advantages of competing suppliers.

d. Imbalance Resolution

48. Customers have also alleged that vertically integrated transmission providers have an advantage over competitors in the resolution of energy imbalances. Transmission providers with generation and load of their own can resolve their own energy imbalances through in-kind energy exchanges with neighboring systems. In contrast, other customers of the transmission provider face higher costs if they take service from other suppliers that could balance against each other. This difference gives the transmission provider a competitive advantage over other sellers of power.

49. Under Standard Market Design, all suppliers and loads on a system will resolve imbalances through the same energy imbalance procedures. This will remove any competitive advantage the transmission owner with its own generation and load may have over competing power suppliers.

e. Available Transfer Capability and Affiliates

50. Another source of discrimination is the calculation of Available Transfer Capability. A transmission provider that is not independent calculates its Available Transfer Capability, using its own proprietary data and its own equations. This discretion gives it the ability and the opportunity to discriminate in its own favor against entities that rely upon the OASIS for Available Transfer Capability information. In several cases, the Commission has found that utilities' OASIS postings reflect an inaccurate Available Transfer Capability. Indeed, in response to “serious concerns about the integrity of the postings of ATC” on the OASIS systems of two transmission providers, the Commission required the transmission providers to employ an independent third party to administer their OASIS systems.

42

42

See

AEP Power Marketing, Inc.,

et al.,

97 FERC ¶ 61,219 at 61,973 (2001),

reh'g pending,

Docket Nos. ER96-2495-016,

et al. See also

American Electric Power Company, Inc. and Central and South West Corporation, 90 FERC ¶ 61,242 at 61,789 (2000) (requiring AEP to turn over its OASIS and ATC calculation functions to an independent entity as a condition of the applicants' merger).

See also

Appendix C for other examples.

51. Under Standard Market Design, an independent entity will calculate Available Transfer Capability and schedule transmission service. This will eliminate this potential for undue discrimination.

f. OASIS Postings

52. Manipulation or violation of OASIS posting requirements and the Commission's standards of conduct is another way vertically integrated transmission providers that control their own OASIS sites are able to engage in undue discrimination. This can occur through prohibited off-OASIS communications between the transmission provider and its affiliated market participant,

e.g.

, informing only the affiliate about Available Transfer Capability that will soon become available and posted on the OASIS so that the affiliate will be first in line to claim the capability.

43

Such abuses reinforce our belief that, in the absence of an independent entity calculating Available Transfer Capability and operating a transmission provider's OASIS, “a transmission provider's self-monitoring of its standards of conduct is not sufficient, and that it is essential for interested parties to be able to participate in this process” of reviewing communications between market participants.

44

Further, even with the best of intentions, it is not possible for a single transmission provider in a region to calculate Available Transfer Capability on its system alone without accounting for the transactions over all the other systems in its region and neighboring regions.

43

See Aquila Energy Marketing Corporation

v.

Niagara Mohawk Power Corporation,

87 FERC ¶ 61,328 (1999) (finding that off-OASIS communication between utility and its marketing affiliate led to preferential treatment of the affiliate); The Washington Water Power Company, 83 FERC ¶ 61,097 (1998) (finding favorable treatment of affiliate and expressing concern that this treatment may have been the result of prohibited off-OASIS communication).

44

Aquila Energy Marketing Corporation

v.

Niagara Mohawk Power Corporation,

87 FERC ¶ 61,238 at 62,279 (1999).

53. Similarly, control over the design, function and maintenance of OASIS systems may also present opportunities for discrimination. The Commission has been concerned for some time that transmission providers have the ability to impede competition by making their OASIS sites difficult to use, limiting users' access to OASIS and limiting access to information about transmission curtailments and interruptions that would allow the Commission to identify instances of undue discrimination.

45

45

See

Regional Transmission Organizations, FERC Stats. & Regs. ¶ 32,541 at 33,713 (describing market participants' perceptions that transmission providers may use OASIS to discriminate among market participants); Open Access Same-Time Information System, 64 FR 34,117 (June 25, 1999), FERC Stats. & Regs. ¶ 31,075 (1999) (articulating changes to Commission regulations that would make available more information about transmission curtailments and interruptions and limit OASIS hosts' ability to disconnect users).

54. Under Standard Market Design, an independent entity will operate an OASIS on a regional basis, and thus will remove any advantages one seller may have over another and improve the accuracy of regional Available Transfer Capability postings on the OASIS.

g. Capacity Benefit Margin Manipulation

55. The Commission has found instances of transmission providers taking advantage of their ability to reserve interface capability to serve their

own load while limiting the ability of competing suppliers to access customers on its system. For instance, transmission providers have reserved excessive amounts of capacity benefit margin (CBM) to serve their own load,

46

and violated the

pro forma

tariff by reserving large amounts (

e.g.

, 2,000 MW) of transfer capability at multiple interfaces, under the label of “firm import for native load,” without designating resources or loads associated with the reservations as other transmission customers are required to do.

47

Import capability reserved by the transmission provider blocks a competing supplier from securing firm service across the interface, limiting that supplier's ability to compete to serve load on the system, or on neighboring systems. A related issue is whether those who set aside transmission for CBM are reserving it and paying for it under the terms of the

pro forma

tariff. When transfer capability for CBM is set aside for the use of one market participant, its cost is not necessarily allocated to that market participant alone. Because transmission facility embedded costs are allocated to transmission customers on the basis of use—capacity reservation for Point-to-Point Transmission Service customers and load ratio share (which does not include the transmission capability set-aside of CBM) for Network Integration Transmission Service customers—all customers may unfairly subsidize the cost of the CBM capability.

46

See

Delegated Letter in Docket No. ER98-4410-000 (Feb. 8, 1999); Entergy Services, Inc., 87 FERC ¶ 61,156 (1999) (directing Entergy, which had reserved 2900 MW, to recompute ATC).

47

See Aquila Power Corporation

v.

Entergy Services, Inc.,

90 FERC ¶ 61,260,

reh'g denied,

92 FERC ¶ 61,064 (2000),

appeal docketed,

No. 00-1417 (D.C. Cir. Sept. 22, 2000). The Commission did not order a remedy in the complaint docket since the compliance filing in Docket No. ER98-4410 to remedy the excessive native load reservations would also provide a remedy for the improper native load reservations at the interfaces.

See id.

at 61,860.

56. Under Standard Market Design, entities that want to reserve transfer capability must pay for that capability to reach generation reserves across an interface. Thus, the preferential treatment would be eliminated.

h. Discretionary Use of Transmission Loading Relief

57. The opportunity for anticompetitive behavior arises when transmission providers have discretion to dispatch their own generation to serve their own load in a way that requires transmission service curtailments through the use of transmission loading relief (TLR) procedures.

58. There has been a sharp increase in the number of TLRs used in some regions, suggesting that transmission operators rely upon them to do more than simply relieve emergency transmission overloads.

48

There are unmistakable financial incentives to rely on TLRs in forward transmission planning:

48

In the Southeast, the incidence of TLRs increased 354 percent from the summer of 1999 to the summer of 2000.

See

Staff Report to the Federal Energy Regulatory Commission on the Bulk Power Markets in the United States (Nov. 1, 2000),

available in <http://www.ferc.gov/electric/bulkpower/southeast.pdf>,

at 3-38. In the Midwest, the incidence increased 472 percent over the same time period.

See

Staff Report to the Federal Energy Regulatory Commission on the Bulk Power Markets in the United States (Nov. 1, 2000),

available in <http://www.ferc.gov/electric/bulkpower/midwest.pdf>,

at 2-32. The lack of a centralized market, particularly in the Southeast, has limited market liquidity and, thus, increased the likelihood of TLRs.

The increased incidence of TLRs may suggest that some transmission capacity is being oversold. Market participants have attributed a tendency to implement a greater number of TLRs to the commercial reality that transmission providers do not have to refund transmission reservation fees for service curtailed because a TLR is called.

49

49

Staff Report to the Federal Energy Regulatory Commission on the Bulk Power Markets in the United States (Nov. 1, 2000),

available in <http://www.ferc.gov/electric/bulkpower/southeast.pdf>

at 3-39.

59. When a vertically integrated transmission provider injects power from its own generation onto its own power lines to meet the constantly shifting demands of the load on its system, it has both the opportunity and the incentive to manipulate the transmission system for its own benefit. It can either dispatch generators to create a transmission constraint that prevents a competitor from making a sale that the transmission provider would also like to make, or it can capitalize on legitimate constraints into a load pocket to curtail a competitor's transmission transaction and serve the customer with its own generation instead. The key here is that none of the transmission provider's actions require direct communication with its merchant function or marketing affiliate. A simplified hypothetical example of such anti-competitive behavior is set forth in Appendix C.

60. Several aspects of our proposed remedy address this concern, including the use of LMP to manage congestion and the requirement that transmission facilities be operated by an Independent Transmission Provider.

2. Lack of Common Rules Governing Transmission

61. Some of the difficulties that come from having different rules as power moves across the grid are discussed later in the Seams Problems Section III.B.4), where a “seam” is a dividing line between different sets of grid rules.

62. Having two or more different sets of rules governing the operation of a transmission system makes it difficult—if not at times impossible—for that system to support an efficient regional electric power market. If the interstate transmission system is to provide fair and efficient movement of power on behalf of all users of the system, the same general rules must govern such matters as who gets service, who has the right to transmission service when not all service requests can be accepted, how the transmission facility costs are allocated among transmission customers, who gets its transmission curtailed and by how much when a transmission outage prevents all the planned services from being accommodated, who plans the additions to the grid and who pays for these additions.

63. Today there are not only different rules in different public utility systems, but there may be more than one set of rules for transmission owned by a single utility. This is because there are different rules for two types of wholesale transmission service, and the rules for bundled retail transmission service may differ from the rules for wholesale and unbundled retail transmission services.

64. The Commission established an open access transmission tariff under Order No. 888 that provides for two distinct types of wholesale transmission services—Network Integration Transmission Service and Point-to-Point Transmission Service. Network Integration Transmission Service was designed primarily to meet the needs of the transmission customer that wants to integrate many generators and many loads at diverse locations on the public utility's grid; it was intended to be comparable to the service that the public utility provided to its own bundled retail customers. Point-to-Point Transmission Service, as the name implies, was designed primarily for the customer that wants to move power from one discrete location to another.

65. At the time Order No. 888 issued, the Commission recognized the potential for problems with having two wholesale services that could not be truly equal, especially the problem of dealing with claims of undue discrimination between the services.

Consequently, along with the issuance of Order No. 888 the Commission proposed a rule to create a new tariff, called the Capacity Reservation Tariff.

50

It was intended to remedy the anticipated problems by establishing a new tariff that would replace the two wholesale services with one. The Commission received many comments on the proposed rule and held a technical conference with representatives of diverse stakeholders.

51

50

See

Capacity Reservation Open-Access Transmission Tariffs, 61 FR 21,847 (May 10, 1996), FERC Stats. and Regs. ¶ 32,519 (1996) (Notice of Proposed Rulemaking).

51

See

Capacity Reservation Open-Access Transmission Tariffs, 76 FERC ¶ 61,065 (1996) (notice extending deadline for filing written comments and convening technical conference).

66. Some parties expressed concern about moving quickly to a single service based on the Capacity Reservation Tariff model, while other parties asserted that, although a single tariff reducing the two services to one was a good policy, there were problems with the particular Capacity Reservation Tariff that was proposed. They recommended that the Commission delay acting on the proposed rule until it learned the best form of single service tariff through industry experience with open access. This is the approach that the Commission in effect followed. Since the two Order No. 888 services were adopted, however, there have been allegations of undue discrimination between customers of the two services as discussed later in this section.

67. There are also different rules for bundled retail transmission service and for wholesale and unbundled retail transmission services. States have historically established the rules for the transmission component of bundled retail transactions, while the Commission has established the rules for wholesale and unbundled retail transmission services.

68. Despite the requirement in Order No. 888 that no transmission customer may have any undue advantage over another, there remain real or perceived advantages for the customers of vertically integrated transmission owners. In many cases, the perceived advantage is one of Network Integration Transmission Service over Point-to-Point Transmission Service, where Network Integration Transmission Service is available to both bundled retail transmission customers and wholesale Network Integration Transmission Service customers, while Point-to-Point Transmission Service is taken primarily for wholesale transmission by independent power producers and marketers.

69. Four prominent examples highlight the alleged advantages that a public utility's bundled retail customers have over wholesale and unbundled retail customers. First, certain reliability practices related to keeping the transmission system balanced may allow a public utility that is responsible for keeping generation and load in balance to obtain lower costs for its own power customers. Second, a transmission-owning public utility may have more

de facto

flexibility to designate transmission receipt and delivery points than other transmission customers, if that public utility also provides power to customers on its transmission system. Third, the bundled retail customers of a transmission owner may have certain transmission reservation and pricing advantages regarding transmission transfer capability set aside for reliability. Fourth, state transmission curtailment rules that favor a public utility's bundled retail customers may conflict with the Commission's transmission curtailment rules, resulting in a transmission preference to customers in one state over customers served in other states.

52

The first three of these were summarized above, and a detailed discussion with examples is set forth in Appendix C.

52

We emphasize that transmission curtailment does not necessarily mean a power outage.

70. The requirement for all services on the transmission grid to be taken under a common set of rates, terms and conditions will resolve these concerns.

3. Congestion Management

71. Due to new transmission usage patterns and the lack of transmission infrastructure improvements, congestion has increased. However, economically sound congestion management plans do not exist in most parts of the country, and transmission customers have been exposed to transmission service interruptions and increasing generation costs due to the risk of interruption. The operating rules that do exist were not designed as a congestion management tool for allocating scarce transmission capacity, but were designed to keep facilities from overloading in an emergency, such as when a transmission facility unexpectedly goes out of service.

72. Currently, under the existing

pro forma

tariff, congestion is managed primarily through a system of physical reservation of capacity, based on each individual transmission provider's calculation of the Available Transfer Capability of its grid, a calculation often made without knowledge of the power flows on its grid that result from transactions scheduled over other grids in its region. Under the current

pro forma

tariff, customers reserve capacity on either a firm or non-firm basis, based on the assumed contract path that the transaction will use. Once the customer has reserved capacity on a firm basis, it is supposed to receive certainty both that power will be delivered and the price that the customer will be charged for transmission. If the customer has non-firm capacity, it has no certainty that capacity will be available to deliver power, but does know that there will be no congestion charge if the delivery does occur.

73. The existing

pro forma

tariff also provides that the redispatch of a transmission provider's generating units to relieve congestion is required only if it can be achieved while maintaining reliable operation of the transmission system in accordance with prudent utility practice. The recovery of the higher generation costs resulting from such generator redispatch, which are a subset of opportunity costs, requires that (1) a formal generator redispatch protocol be developed and made available to all transmission customers and (2) all information to calculate redispatch costs be made available to the customer for audit. If a transmission provider collects revenues to cover the redispatch costs from a specific transmission customer, it must credit these revenues to the cost of fuel and purchased power expense included in its wholesale fuel adjustment clause. Various tariff provisions specify how redispatch is to be implemented. For instance, Sections 33.2 and 33.3 of the existing

pro forma

tariff provide that the redispatch of all network resources and the transmission provider's own resources, on a least-cost basis without regard to ownership, is to be performed only to maintain system reliability, not for economic reasons. Under those circumstances, the redispatch costs would be shared among the network customers and the transmission provider on a load ratio basis. Sections 13.5 and 27 of the existing

pro forma

tariff permit the transmission provider to provide the requested transmission service and relieve a system constraint by redispatching the transmission provider's resources: (1) If this costs less than constructing network upgrades; and (2) if, under Section 13.5, the transmission customer agrees to compensate the transmission provider for any such redispatch costs on an incremental basis as specified in the

customer's service agreement prior to the commencement of service.

74. Although the existing

pro forma

tariff allows the recovery of generating unit redispatch costs, the Commission generally has not accepted proposals submitted by single-utility transmission providers to recover such costs. For instance, the Commission rejected Bangor Hydro-Electric Company's (Bangor Hydro) proposed formula to recover opportunity costs for lack of supporting data showing that its opportunity cost pricing would be consistent with the principle of comparability and because the formula lacked sufficient detail to operate as a rate formula itself.

53

The Commission directed Bangor Hydro to submit a separate section 205 filing with revised opportunity cost pricing before implementing such pricing. The Commission also rejected a proposal by the operating companies of Central and South West Corporation (CSW) regarding redispatch costs because they did not provide sufficient specificity to enable a customer to calculate or verify redispatch costs and because the formula lacked sufficient detail to operate as a formula rate.

54

The Commission also directed CSW to submit a separate filing under section 205 before implementing such pricing.

53

See

Allegheny Power System, Inc.,

et al.

, 80 FERC ¶ 61,143 (1997).

54

Central Power and Light Company, 81 FERC ¶ 61,311 (1997).

75. Because it is difficult for a single-utility transmission provider to develop a formula that specifies the costs of redispatch and protects transmission customers' interests, generation redispatch has not been used as extensively as it could be used to relieve congestion. A transmission provider will not redispatch generating units if it cannot collect its higher generation costs, and less transmission transfer capability will be available to the energy market.

76. In 1998, the Commission called on public utilities to work with the North American Electric Reliability Council (NERC) to develop a congestion management system based on redispatch.

55

NERC responded with its pilot Market Redispatch program that relied on counterflow transactions,

i.e.

, power transfers against the prevailing flows on the constraint, to relieve the congestion.

56

Although the program has been in place for several years, it has been implemented only infrequently because of the difficulty in establishing counterflow transactions and the limited availability of data to the transmitting customer.

57

55

The NERC rules for protecting the system were designed to adapt the Commission's Order No. 888 individual utility transmission curtailment requirements to multi-system transactions and parallel flows.

See

North American Electric Reliability Council, 85 FERC ¶ 61,353, 62,363-64 (1998).

56

See

North American Electric Reliability Council,

et al.

, 87 FERC ¶ 61,160 (1999).

57

NERC identified several problems with the program in a January 31, 2002 submittal to the Commission: (1) The Market Redispatch customer cannot easily anticipate and specify in advance which facilities will overload and require transmission curtailment; (2) the Market Redispatch transaction must provide a counterflow for the entire protected transaction even though the required transmisssion curtailment may be only a portion of the original protected transaction; and (3) the Market Redispatch customer cannot easily discover the availability of generator pairs for counterflow transactions.

See

Report on Market Redispatch Pilot Program by NERC Market Interface Committee and Motion to Continue Market Redispatch Program, Docket No. ER02-933-000, at 3 (Jan. 31, 2002).

77. In 1998, Commonwealth Edison Company (ComEd) proposed a similar voluntary redispatch program, which predated NERC's Market Redispatch Program.

58

In November 1998, ComEd submitted the first of two interim reports to the Commission summarizing its experience with the program.

59

It determined that a single utility cannot effectively offer redispatch over other systems, especially where other generation owners do not participate.

58

See

Commonwealth Edison Company,

et al.

, 83 FERC ¶ 61,145 (1998).

59

Interim Report on Non-Firm Redispatch

, Docket No. ER98-2279-000 (Dec. 17, 1998).

78. The overall result of the Order No. 888 congestion management system is that the transmission system is not utilized in the most efficient manner. Customers can be denied access to lower-cost supplies that could be made available if the congestion management and pricing system had an efficient and fair method of recovering the cost of generator redispatch.

79. Managing congestion using an LMP system, coupled with a single transmission service that relies on price (rather than first-come, first-served) to allocate limited transmission capacity, will resolve these problems.

4. Seams Problems

80. A lack of common transmission rules inhibits competition in power markets not only when there are different rules for different customers under one public utility's tariff or one RTO's tariff, but also when there are different rules from one public utility to the next, or from one RTO to the next. The term “seam” has come into common use in the electric power industry over the last several years to refer to a boundary between areas with different transmission or other market rules. Market participants assert that it can be difficult to move power “across a seam” from one area to another.

81. Seams issues include differences in transmission rules as well as differences in power market rules. They include such diverse matters as different operating rules (

e.g.

, rules for recalling firm transmission capacity; coordination of generation and transmission maintenance schedules; how parallel path flows are determined to affect other regions); different market rules (

e.g.

, bidding rules; market product definitions); different market designs (

e.g.

, congestion management procedures; demand response rules; market price intervention practices); different business practices (

e.g.

, scheduling practices; reservation practices; OASIS designs; processes to verify transactions between ISOs and market participants; transmission and generation outage information dissemination, compensation, and coordination rules; generation interconnection practices; liability provisions); and different electronic and telephonic communications protocols.

82. Market participants have called for a “seamless market,” by which they mean a market whose operation is not encumbered by differences in rules at public utility or RTO boundaries. To achieve a seamless market, some assert that rules may differ but only in ways that the differences are invisible to power sellers and buyers. Others assert that such management of differences rarely works in practice and that the rules must be the same everywhere to achieve a seamless market.

83. The Commission has long recognized the need for more coordination and uniformity throughout a region in transmission matters. Our Regional Transmission Group Policy Statement of 1993

60

encouraged public utilities to develop a common set of rules for regional expansion planning, and our Transmission Pricing Policy Statement of 1994

61

encouraged the development of a common pricing policy for a region that would internalize and rationalize the pricing of parallel path flows. As explained above, Order Nos. 888 and 2000 recognized the need to bring the various public utility

transmission systems in a region under a common set of transmission rules. Order No. 888 not only applied a common set of open access transmission rules to public utility transmission systems, but included a reciprocity provision that conditioned a non-public utility's use of a public utility's open access transmission tariff on the non-public utility's agreement to provide comparable transmission service to the public utility. Indeed, Order No. 888 also encouraged the formation of ISOs not only to bring all the transmission systems in a region under common rules, but also under unified operation. Many parties in Canada have stressed the necessity of having a common set of rules for reliability and trading protocols for cross-border transmission facilities.

62

Order No. 2000 built on this theme by strongly encouraging the formation of RTOs to bring all facilities in a region under a common set of transmission rules. However, RTOs have not developed at the pace anticipated when Order No. 2000 was issued and seams problems continue to exist. In June 2001, the Commission held a technical conference on seams issues.

63

Participants to the seams conference explained that resolution of seams issues is critical for making the inter-RTO transmission systems and power markets work.

60

Policy Statement Regarding Regional Transmission Groups: Policy Statement, 58 FR 41,626 (August 5, 1993), FERC Stats. & Regs. ¶ 30,976 (Jul. 30, 1993).

61

Inquiry Concerning the Commission's Pricing Policy for Transmission Services Provided by Public Utilities Under the Federal Power Act, 59 FR 55,031 (November 3, 1994), FERC Stats. & Regs. ¶ 31,005 (Oct. 26, 1994),

order on reconsideration and clarifying policy statement

, 71 FERC ¶ 61,195 (1995).

62

See, e.g.

, Ambassador Michael Kergin (Canada) letter to Honorable Thomas A. Daschle, Senate Majority Leader, dated November 2, 2001:

Canadian electricity companies are linked to their counterparts in the U.S. through a number of major connections crossing our common border. We share a truly international electricity grid. This interconnectedness itself enhances our respective energy security, but it also places an onus on our countries to act together to manage the grid. Nowhere is that more important than in the area of electricity reliability. * * * Because uniformity in reliability standards is required to enable effective electricity trade, variations in standards would impede electricity trade and balkanize markets.

63

Conference on RTO Interregional Coordination

, Docket No. PL01-5-000, June 19, 2001. Called by many the “FERC Seams Conference,” this technical conference on the RTO interregional coordination requirements of Order No. 2000 helped the Commission learn about seams issues and about how uniform standards for some rules could benefit power markets.

84. We set forth in Appendix C a number of examples of differences in rules that can create seams problems, and a discussion of efforts at the Commission or within the industry to address seams problems.

85. The requirement under Standard Market Design for a single tariff and a single market design operating with the same set of rules throughout the entire interconnection resolves the seams problems discussed above.

5. Market Design Flaws

86. Poorly designed market rules, or market rules with unforeseen or unintended consequences, can have a debilitating effect on markets, market pricing and overall confidence in the markets of the market participants. Moreover, differences in market designs in neighboring regions can also lead to problems such as the exercise of market power through the exploitation of the differences.

87. Wholesale electricity markets are complex, with multiple products traded at multiple locations on different time-frames, while subject to the unique physical characteristics of electricity (

e.g.

, non-storable, need for system stability and balancing, physics of power flows). Market rules have been affected by the variation in generation mix, the transmission network layout and the local and regional regulatory history in different regions of the country. For example, the initial California markets had a design quite different from the designs of the markets in the Northeast region (PJM, New York and New England).

88. In the regions where voluntary, organized ISO markets for energy, transmission and ancillary services have been established under the existing tariff, problems due to the design choices have been characterized as “market design flaws.” A market design flaw is a market rule—including product specification, bid format, auction rules and pricing rules—that allows distortions in the market prices or availability of a product or service, whether energy, ancillary services, transmission service or installed capacity. In the years since the ISO markets have been operating, dozens of market design flaws have been identified, ranging from minor problems that cause temporary inconveniences to major problems that require markets to be re-designed. No region has been exempt from market design flaws of one type or another. We set forth in Appendix C examples of specific design flaws.

89. These problems have resulted in markets that are inefficient and do not produce the lowest reasonable prices for electric power. These problems cannot be resolved on a case-by-case basis because that will maintain and exacerbate the problems due to local differences in rules. Only standardization of electricity market design will solve these problems. In the parts of the country in which markets are most mature, including the Northeast, Midwest and California, there is broad consensus on the principal elements of market design and business practices. A standard market design rule will help advance this process and extend it to other regions. Our goal is to use the Standard Market Design rulemaking to address and remedy many of the market design flaws identified to date and to raise the quality of all electric markets simultaneously.

90. Market rules will need to be flexible and have the ability to evolve over time. However, consistent rules across the entire interconnection based on best practices, coupled with sound market monitoring to promptly identify and correct any design flaws will provide the necessary foundation for future market innovation and improvement.

C. Reform Essential Given the Changed Nature of the Electric Industry

91. The need to address the instances of discrimination described above is all the more critical given the changing nature of the electric industry. The United States electric power industry is in the middle of a transition from a predominantly monopoly industry to a predominantly competitive industry. The fundamental economic driver of change has been, and continues to be, the reduction of economies of scale in new generation construction, combined with environmental restrictions that encourage gas-fired units. This is due in large part to the introduction during the 1980s of highly efficient gas turbines and combined cycle generators that produce much more electricity from a given amount of gas. A relatively small gas-fired generator can compete effectively with power from a large central generating station. Additionally, small distributed generation is becoming economic, and some renewable energy resources, especially wind power generation, are also on the verge of becoming competitive.

64

In the right locations, wind generating units can compete with the much larger coal, nuclear and hydroelectric units.

65

64

See, e.g.

, International Energy Agency, Distributed Generation in Liberalized Electricity Markets, International Energy Agency (June 2002); and Ann Chambers,

et al.

, Distributed Generation: A Nontechnical Guide (PennWell Corp. 2001).

65

See

Christine Real de Azua, Wind Power: Poised for Take Off? A Survey of Projects and Economics, Pub. Util. Fort., Aug. 2001 at 38.

92. Because of these fundamental changes in industry technology, small producers of electricity can compete with large producers, and both the smaller utilities and the retail customers of a number of utilities have demanded access to competing power suppliers in hopes of lowering their electric bills,

improving service and harnessing new technologies. The pressures for retail access have been greater in regions with higher rates, which are typically regions with few low-cost natural resources for generating electric power, such as nearby coal mines, gas fields, and hydroelectric areas.

66

Many of these regions have taken the lead in retail restructuring, while regions with historically low electricity production costs have proceeded more cautiously or even affirmatively decided not to change their retail access policies or to support their local utilities' participation in regional programs at this time.

67

66

See

Energy Information Administration, The Changing Structure of the Electric Power Industry 2000: An Update, at 81-82 (2000),

available in

http://www.eia.doe.gov/cneaf/electricity/

chg_stru_update/update2000.pdf

> (hereinafter Electric Power Industry 2000 Update).

67

See id.

93. One hallmark of electric industry restructuring has been the growth of wholesale trade. In the past, wholesale power purchases made up a small fraction of a large vertically integrated utility's power supply, with most of its power needs met by its own generation. Today, however, even large vertically integrated utilities rely increasingly on wholesale purchases for their energy supplies. For example, as shown in Table 1, between 1989 and 2000, generation by investor-owned utilities grew from 2,132 thousand GWh to 2,230 thousand GWh, an increase of less than 5 percent. During this time, wholesale power purchases by these utilities almost tripled. Table 1 also shows that in 1989 wholesale power purchases provided 18 percent of the total electric energy available to investor-owned utilities from both wholesale purchases and their own generation. By 2000, wholesale purchases provided over 37 percent of investor-owned utility electric energy. This percentage has steadily increased since 1989, and is expected to continue to grow as utility-owned plants are sold or retired and new power supplies are acquired competitively in most parts of the country.

Table 1.—Investor-Owned Utilities' Total Purchases, 1989-2000, As a Percentage of Energy Purchased and Self-Generated

Year

IOUs' purchases

(GWh)

IOUs'

generation

(GWh)

Purchases

(purchases + generation) (%)

1989

460,627

2,132,065

17.8

1990

530,325

2,134,429

19.9

1991

635,015

2,145,435

22.8

1992

671,758

2,143,847

23.9

1993

718,876

2,216,724

24.5

1994

732,710

2,237,652

24.7

1995

786,676

2,269,958

25.7

1996

916,087

2,308,156

28.4

1997

1,080,538

2,321,225

31.8

1998

1,073,638

2,402,571

30.9

1999

1,083,892

2,353,639

31.5

2000

1,324,558

2,229,617

37.3

Source: RDI POWERDAT Database.

Note:

Data for 2001 is not yet available. Investor-owned utility purchases include purchases from affiliates.

94. Table 1 demonstrates the increasing importance of competitive wholesale energy acquisition in the United States electric power industry, and the need for this Commission to ensure that transmission, market rules and institutions are reformed as necessary to support the new environment. It also makes clear that a retreat from competitive markets to a cost-regulated vertically integrated world would be difficult—the nation now depends increasingly on wholesale interstate electricity markets.

95. Similar data are presented in Tables 2 and 3 for large public power utilities and generation and transmission cooperatives that generate at least some of their own power.

68

These tables show that wholesale purchases, on average, provide about 40 percent of the power needs of these large utilities. Data are not presented for the smaller public power and cooperative utilities because they typically do not self-generate but buy all of their power at wholesale.

68

Note that the data available for large public power and cooperative utilities is not complete but represents a sampling of these utilities. The sample size typically grew each year so that an apparent growth in the wholesale purchase percentages could reflect the addition of smaller utilities that purchase more power at wholesale.

Table 2.—Large Public Power Utilities' Total Purchases, 1992—2000, As a Percentage of Energy Purchased and Self-Generated

Year

Utilities'

purchases

(GWh)

Utilities'

generation

(GWh)

Purchases

(Purchases + generation)

(%)

1992

297,076

520,348

36.3

1993

314,472

549,810

36.4

1994

331,643

555,198

37.4

1995

332,962

586,737

36.2

1996

350,880

645,740

35.2

1997

349,641

674,725

34.1

1998

364,434

676,698

35.0

1999

394,617

634,548

38.3

2000

429,369

631,143

40.5

Source: RDI POWERDAT Database.

“Large Public Power Utilities” includes municipals, federal power authorities. Data for 2001 is not yet available.

Table 3.—Generation & Transmission Cooperatives' Total Purchases, 1992—2000 As a Percentage of Energy Purchased and Self-Generated

Year

Cooperatives' purchases (GWh)

Cooperatives' generation (GWh)

Purchases

(Purchases + generation)

(%)

1992

85,226

136,417

38.5

1993

93,756

149,783

38.5

1994

96,148

156,589

38.0

1995

99,909

166,099

37.6

1996

117,455

172,161

40.6

1997

112,822

176,689

39.0

1998

115,003

177,534

39.3

1999

122,151

172,323

41.5

2000

127,785

171,198

42.7

Source: RDI POWERDAT Database.

Note:

“Generation & Transmission Cooperatives” includes cooperatives with generation and transmission facilities, but excludes distribution cooperatives. Data for 2001 is not available yet.

96. The transition to competitive electricity markets is characterized by opportunity and uncertainty. The promise of competition is the opportunity to develop more innovative technologies, improve services, lower average electric rates and provide more customer choice than is likely under a strictly regulated monopoly environment. During the transition to competition, these promises are only partly fulfilled, and results vary regionally as a result of different choices about retail restructuring. Additionally, the California electricity crisis of 2000-2001, allegations of improper trading practices, the collapse of Enron Corporation in December 2001 and the deteriorating financial health of many electric suppliers and marketers at this time have added unprecedented uncertainty about, and lack of confidence in, today's electric markets.

97. In addition to general concerns about adequate constraints on the exercise of market power by power sellers, there is uncertainty in the industry about impediments to new generators entering the market, adequacy of incentives to build much needed generation and transmission infrastructure, availability of non-discriminatory transmission service for all sellers and buyers in a regional market and the risk of making long-term commitments when market rules are subject to frequent experiment and change. Differences in market rules between regions make it difficult to transact business across regions and thus also lead to increased uncertainty in the industry and the risk of market manipulation.

98. Investors, generators and transmission providers are reluctant to invest in new generation and transmission infrastructure if the rules for setting energy or transmission prices are not yet known or are subject to frequent revision.

69

Thus, uncertainty about the direction of competition policies inhibits the development of the very infrastructure needed both to allow competition to work and to assure reliability in a competitive environment. Customers are reluctant to sign contracts for power or to change suppliers if long-term power markets are unnecessarily volatile and they cannot obtain price certainty.

69

See generally

U.S. Department of Energy, National Transmission Grid Study (May 2002),

available in

<http://tis.eh.doe.gov/ntgs/

> (hereinafter DOE National Transmission Grid Study).

99. The promise of wholesale competition may go unfulfilled—or at best continue to be delayed at great cost—unless many of these uncertainties are resolved. This proposed rule is intended to help resolve generically many of the uncertainties facing the electric power industry and to restore confidence in future power markets.

D. Legal Authority and Findings

100. The primary purposes of the Federal Power Act are to curb abusive practices by public utilities and to protect customers from excessive rates and charges. To achieve these ends, section 205 of the Federal Power Act requires that no public utility shall “make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage,” with respect to the transmission of electric energy in interstate commerce or wholesale sales.

70

Section 206 of the Federal Power Act authorizes the Commission

to investigate and remedy unduly discriminatory or preferential rules, regulations, practices or contracts affecting public utility rates for transmission in interstate commerce and for sales for resale of electric energy in interstate commerce.

71

It also authorizes the Commission to investigate and remedy unjust and unreasonable rates, charges or classifications, and any rules, regulations, practices or contracts affecting such rates, charges or classifications.

70

16 U.S.C. 824d.

71

16 U.S.C. 824e.

101. Moreover, the Commission's regulatory authority “clearly carries with it the responsibility to consider, in appropriate circumstances, the anticompetitive effects of regulated aspects of interstate utility operations pursuant to [Federal Power Act sections] 202 and 203, and under like directives contained in [Federal Power Act sections] 205, 206, and 207.”

72

The Commission's authority to remedy undue discrimination and anticompetitive effects is broad.

73

72

See

Order No. 888 at 31,669 (quoting

Gulf States Utilities Co.

v.

FPC,

411 U.S. 747, 758-59,

reh'g denied,

412 U.S. 944 (1973)).

See also City of Huntingburg

v.

FPC

, 498 F.2d 778, 783-84 (D.C. Cir. 1974) (finding that the Commission has a duty to consider the potential anticompetitive effects of a proposed interconnection agreement).

73

See

Order No. 888 at 31,669 (the Federal Power Act fairly bristles with concern for undue discrimination (citing

Associated Gas Distributors

v.

FERC,

824 F.2d 981, 998 (D.C. Cir. 1987),

cert. denied,

485 U.S. 1006 (1988))).

102. The Court of Appeals for the District of Columbia Circuit reviewed challenges to Order No. 888 and found that the “open access requirement is authorized by and consistent with the [Federal Power Act],” and upheld the order.

74

On appeal, the Supreme Court affirmed the Commission in applying its open access requirements to transmission used for wholesale and unbundled retail sales of electric energy in interstate commerce, but also concluded that the Commission had jurisdiction over transmission used for bundled retail sales of electric energy in interstate commerce. The Supreme Court further stated that the Commission may regulate bundled retail transmission of energy as a means of addressing undue discrimination. While the Court did not adopt the appellants' suggestions that the Commission's finding of discrimination in the wholesale electricity market suggested the presence of discrimination in the retail electricity markets,

75

it stated that “[w]ere FERC to investigate this alleged discrimination and make findings concerning undue discrimination in the retail electricity market, § 206 of the FPA would require FERC to provide a remedy for that discrimination * * * And such a remedy could very well involve FERC's decision to regulate bundled retail transmissions” of energy.

76

74

Transmission Access Policy Study Group

v.

FERC,

225 F.3d at 685.

75

See id.

at 1028.

76

Id.

103. We find that undue discrimination and anticompetitive behavior persist, as detailed in Section III and Appendix C, in both wholesale and retail transmission of energy. Pursuant to our statutory mandate to remedy undue discrimination and anticompetitive effects in these markets, as interpreted by the Supreme Court, we will apply the requirements of this rule to the transmission component of bundled retail transactions. At a minimum, all transmission service in interstate commerce must be subject to the same non-discriminatory non-rate terms and conditions in order to eliminate undue discrimination in wholesale markets and in retail choice markets. With respect to rates for bundled retail transmission service, however, we will work with states to address difficult transition rate issues.

104. In light of these statutory responsibilities and authorities under the Federal Power Act, we have assessed the state of the electric utility industry and determined that it is necessary to act promptly to provide stability to the industry and to assure that customers receive adequate supplies of electric energy at the lowest reasonable price. During the past six years, the implementation of open access transmission under Order No. 888 has fundamentally altered the landscape of the electric utility industry by removing major discriminatory barriers to the use of the interstate transmission grid and thereby opening the door to competition in wholesale electric power markets. However, even with the Order No. 888 open access

pro forma

transmission tariff and Order No. 889 transmission standards of conduct in place, there continues to be undue discrimination in the provision of interstate services. Experience under the

pro forma

tariff has demonstrated that unduly discriminatory transmission practices continue today. Further, existing trading rules and design of wholesale power markets do not consistently prevent market manipulation or send proper price signals to participants or allocate scarce resources to those who value them most and thus could result in unjust and unreasonable rates. Thus, competition either does not exist in many areas of the country or competition is distorted.

105. We find that:

(1) the operation of the Commission's

pro forma

transmission tariff (which is administered by vertically integrated as well as non-vertically integrated public utilities such as ISOs) contains provisions that, in practice, permit undue discrimination in the provision of transmission services;

(2) public utilities that own, operate or control transmission facilities and also participate in power markets continue to possess substantial transmission market power and retain the ability to unduly discriminate in the provision of transmission service and spot market energy services;

(3) lack of standardized wholesale electric market design allows undue discrimination within and across regions, can result in unjust and unreasonable pricing and allocation of transmission and permits the exercise of market power (and thus unjust and unreasonable rates) in power markets; and

(4) proper price signals are not being sent to the marketplace, with the result that market-based rates in many places are distorted, and reasonably accurate price signals necessary for infrastructure additions are not being sent.

106. To remedy remaining undue discrimination in the provision of interstate transmission services and in other industry practices, and to ensure just and reasonable rates for sales of electric energy within and among regional power markets, the Commission proposes to modify the Order No. 888

pro forma

tariff to reflect non-discriminatory, standardized transmission service and require standardized wholesale electric market design. The Commission also proposes to expressly exercise jurisdiction over all transmission in interstate commerce by public utilities.

IV. The Proposed Remedy

107. The Commission's goal in Order Nos. 888 and 2000 was to harness the benefits of competition for the nation's electricity customers by assuring adequate and reliable supplies of electricity at a just and reasonable price. As discussed above in the Need for Reform section (Section III), the current rules and regulations have prevented the full attainment of that objective. To address these problems in the current system, we are proposing a comprehensive package of reforms that are described more fully in this section.

108. Section III and Appendix C provide numerous examples of ways that an entity that owns both

transmission and generation can discriminate in favor of its own customers or generation under the current tariff. The problem stems from the differences in the sets of rules that apply to users of the transmission system. First, the current regulatory system allows vertically integrated utilities to discriminate in favor of their bundled retail load at the expense of wholesale customers. This occurs because transmission service for bundled retail customers is subject to different rules and rates than service for wholesale customers. Second, the current distinction between Point-to-Point Transmission Service and Network Integration Transmission Service also creates opportunities for undue discrimination in favor of generation owned by the transmission owner or an affiliate.

109. To remedy this discrimination we propose to place all transmission customers under the same set of rules. We propose to place transmission service for bundled retail customers under the same terms and conditions of service as wholesale transmission service. To accomplish this we propose to revise the existing

pro forma

tariff to remove provisions that grant preferential treatment to transmission service for bundled retail customers. We propose that all public utilities that own, control or operate interstate transmission file these interim changes no later than July 31, 2003. We also propose that no later than September 30, 2004, or such date as the Commission may establish, only Independent Transmission Providers would operate Commission-jurisdictional facilities. This requirement will apply whether or not the public utility that owns, controls or operates interstate transmission facilities has joined an RTO.

77

We are proposing specific governance requirements that must be met by the Independent Transmission Provider.

77

A Commission-approved RTO would meet the requirements of an Independent Transmission Provider.

110. Also, no later than September 30, 2004, or such date as the Commission may establish, we propose to eliminate the distinction between Point-to-Point and Network Integration Transmission Services by having one service, Network Access Service, that contains elements of both types of service—the flexibility of Network Integration Transmission Service and the tradability of Point-to-Point Transmission Service. We propose these time periods to provide sufficient time for the development of the necessary new software systems. Network Access Service is based on an open spot market for imbalance energy and a uniform congestion management methodology,

i.e.

, LMP, to more efficiently manage the transmission grid. The spot energy market and LMP rely on management of the transmission system and bidding by supply and demand resources attached to the transmission grid under market rules and protocols.

111. To provide the price signals needed to manage congestion, the Independent Transmission Provider will be required to operate a day-ahead and real-time market for energy. To provide customers with a mechanism for achieving price certainty under the new congestion management system, we also propose to require that customers be given Congestion Revenue Rights for their historical uses that protect against congestion costs when specific receipt and delivery points are used.

112. LMP and Congestion Revenue Rights will provide price signals to indicate where new investment is needed; however, the price signals alone may not guarantee sufficient investment. We also propose to require a regional transmission planning and expansion process to provide a backstop process for ensuring that needed transmission construction is undertaken. We propose that this process begin six months from the effective date of the Final Rule, even though much of the country will not have had the opportunity to respond to LMP and Congestion Revenue Rights for another few years.

113. At this stage of the industry's evolution, structural barriers to competitive markets remain, so to address this we are proposing market power mitigation measures for the spot markets that will be operated by the Independent Transmission Provider. These measures are designed to address the two significant structural problems in wholesale energy markets—the existence of localized market power that arises from transmission constraints, and the lack of price-responsive demand. The market power mitigation proposal is a framework that can be tailored to reflect the competitive conditions of the particular region. It is designed to be reexamined annually and adjusted as needed to reflect changes in the competitive structure of the region, including a phasing out of mitigation measures as resource adequacy and demand response develops. Because market power mitigation of spot market prices will tend to suppress the price signals for new entry, we are also proposing a non-price mechanism to assure that load meets a long-term resource adequacy requirement.

114. To avoid the market design flaws discussed in the Need for Reform section (Section III) and Appendix C and market manipulation in Appendix E, and to minimize the potential for seams issues, we propose a standardized tariff that incorporates the best practices and builds on the lessons from our experience with organized markets. In Appendix B, the proposed SMD Tariff standardizes many aspects of the basic market design. However, it also allows flexibility in a number of areas to customize the basic market design to meet regional requirements where such customization will not lead to further discrimination or inefficiencies.

115. We propose to permit small entities to seek waiver of the Standard Market Design Final Rule requirements. The regulations we propose include waiver provisions under which public utilities, and non-public utilities seeking exemption from the reciprocity condition, may file requests for waivers from all or part of the Commission's regulations.

116. Finally, while we have attempted to standardize the basic aspects of the market design policy, this proposed rule does not include detailed business practices and communication protocols that will be needed to administer Standard Market Design. We fully appreciate the benefits of business practice standardization and, as we did in the natural gas industry, we believe it is best if industry participants develop these types of highly detailed and technical standards. Thus, we are proposing a process, similar to that used in the natural gas industry, that could be used for standardization of business practices, data sets and communication protocols that includes representation of all affected market participants. Upon its formation, the Wholesale Electric Quadrant of the North American Energy Standards Board (NAESB), working closely with Independent Transmission Providers who would collectively serve in an advisory capacity to the board, would produce business practice and electronic communication standards. NAESB would notify the Commission when it has adopted standards, and the Commission would then use rulemaking proceedings to propose the incorporation of these standards by reference into the Commission's regulations. If the industry is unable to reach consensus on a particular standard, the Commission would be available to resolve the dispute, so that the industry process can continue, or the Commission could develop its own standards if necessary. Consistent with gas industry regulation, issues of policy that affect significant resources or that

may cause cost-shifting would be resolved at the Commission rather than through the standard setting body.

A. The Interim Tariff

117. Standard Market Design is intended to cure undue discrimination, in part, with respect to the use of the transmission grid. As we discussed in Section III.B.2, there are different rules for bundled retail transmission service and for wholesale and unbundled retail transmission services. These differences result in unduly discriminatory preferences for the vertically integrated transmission owner's bundled retail customers.

1. Placing Bundled Retail Customers Under the Interim Tariff

118. We propose that to eliminate this undue discrimination, the transmission component of bundled retail service must be taken under an open access transmission tariff. Under the current

pro forma

tariff, a vertically integrated utility is required to designate the resources it uses to serve bundled retail customers in the same manner as wholesale customers are required to designate network resources under the Network Integration Transmission Service. We propose to use these designations of network resources in converting service used to meet retail obligations. The existing level of service would be provided pursuant to the new Network Access Service. The load-serving entity or the retail customer would receive either Congestion Revenue Rights or the auction revenues for these rights for the currently designated resources. In Section V of this Notice of Proposed Rulemaking, the Commission sets forth a proposed time-line and implementation process for this conversion process.

119. In the interim, however, we propose to require that bundled retail load be placed under the existing

pro forma

tariff. While many of the revisions required by Standard Market Design are dependent on the production and adoption of software to determine locational marginal prices and to operate markets, placing bundled retail load under the existing

pro forma

tariff can be done immediately. This will remove certain discriminatory practices and is the first step towards placing all transmission service under one tariff. This will require several revisions to the existing

pro forma

tariff to modify provisions that define the different treatment granted to the service of bundled retail load. Among the revisions that the Commission proposes to require public utilities to file are revisions to Sections 1.19, 13.5, 13.6, 14.2, 22.1(a), 22.1(a), 28.2, 28.3, 33.2, 33.3, 33.3 and 33.5. The specific changes are identified in Appendix A.

120. We propose that the public utilities file these revisions to their tariffs and execute service agreements to take Network Integration Transmission Service on behalf of their bundled retail load no later than July 31, 2003. We recognize, however, that some public utilities (

e.g.

, ISOs) may already be serving bundled retail load under the

pro forma

tariff. Accordingly, to the extent that a public utility can demonstrate that it complies with this requirement, it may so indicate in its compliance filing.

2. Additional Interim Revisions to the

Pro Forma

Tariff

121. Since the implementation of the existing

pro forma

tariff, the Commission has offered clarifications to various provisions of the tariff. Perhaps the most important of these dealt with a customer's right to roll over its existing contract for long-term firm service (Section 2, Initial Allocation and Renewal Procedures).

122. In several orders, the Commission clarified three significant points: (1) A customer must submit a request to roll over its contract no later than sixty days prior to the date the current service agreement expires;

78

(2) the public utility may only deny a customer its right to roll over a contract due to future load growth if the public utility includes in the original service agreement a specific, reasonably forecasted need for the transfer capability to serve load growth for network customers at the end of the term of the service agreement;

79

and (3) a long-term firm customer that requests to use alternate point(s) of receipt or delivery retains its right of first refusal for service at the original point(s) of receipt and delivery at the time the current service agreement expires.

80

78

Entergy Power Marketing Corporation

v.

Southwest Power Pool,

91 FERC ¶61,276 (2000).

79

Order No. 888-A, as clarified by Public Service Company of New Mexico, 85 FERC at 62,006 (1998);

Public Service Company of New Mexico

v.

Arizona Public Service Company,

99 FERC ¶61,162 (2002);

Exelon Generation Company, LLC

v.

Southwest Power Pool,

99 FERC ¶ 61,235 (2002).

80

Commonwealth Edison Company, 95 FERC ¶ 61,027 (2000).

123. These revisions have a significant impact on the rights of current transmission customers and will continue to do so up until the time the SMD Tariff, including auctions of Congestion Revenue Rights, is in place.

81

We propose to require public utilities to make the tariff changes to Section 2.2 of the existing

pro forma

tariff, as outlined in Appendix A.

81

The protections offered by rollover rights are of value in a first-come, first-served priority system, and are valuable for a direct allocation of Congestion Revenue Rights. Once Congestion Revenue Rights are fully auctioned, and access to transmission service will be based on a willingness to pay congestion costs (and losses), it may no longer be necessary.

B. Independent Transmission and Markets

124. Another form of undue discrimination is the lack of independence of the transmission provider in many regions of the country. As discussed in Section III.B.1, remaining corporate ties between generation and transmission within public utilities are problematic since they allow the vertically integrated utility to exercise market power to advantage its affiliated generation.

1. Independent Transmission Providers

125. To remedy this undue discrimination, transmission service must be provided by an independent entity. Therefore, we propose to require all public utilities that own, control or operate facilities used for the transmission of electric energy in interstate commerce to: (1) Meet the definition of Independent Transmission Provider, (2) turn over the operation of its transmission facilities to an RTO that meets the definition of Independent Transmission Provider, or (3) contract with an entity that meets the definition of Independent Transmission Provider to operate its transmission facilities.

126. An Independent Transmission Provider is any public utility that owns, controls or operates facilities used for the transmission of electric energy in interstate commerce, that administers the day-ahead and real-time energy and ancillary services markets in connection with its provision of transmission services pursuant to the SMD Tariff, and that is independent (

i.e.

, has no financial interest, either directly or through an affiliate, in any market participant in the region in which it provides transmission services or in neighboring regions).

127. We propose that affected public utilities must inform the Commission which Independent Transmission Provider will operate the public utility's transmission facilities no later than July 31, 2003. However, a public utility that is a member of an approved RTO or ISO or other entity that meets the definition of Independent Transmission Provider may file a request for a waiver of the filing requirements of this paragraph on the ground that it has already complied with the requirement.

128. Any entity meeting the definition of Independent Transmission Provider would file the SMD Tariff to provide transmission services, including ancillary services, and to administer the day-ahead and real-time energy and ancillary services markets. As discussed further below, an Independent Transmission Provider would also perform market monitoring and market power mitigation, long-term resource adequacy and transmission planning and expansion on a regional basis.

129. An Independent Transmission Provider would also file under section 205 any changes to transmission rates necessary to implement Standard Market Design, no later than 60 days prior to the date on which it proposes to implement Standard Market Design.

130. In addition, one or more public utilities may jointly file an application to meet the requirements of Standard Market Design. Also, an Independent Transmission Provider may make necessary filings on behalf of public utilities required to meet the requirements of this paragraph.

131. We seek comment on whether this remedy is adequate to remove the potential for unduly discriminatory behavior on the part of a vertically integrated transmission provider. Can the requirements of Standard Market Design be satisfied either by performing the function through an RTO or contracting with an independent entity to perform them? Given that most transmission providers have filed proposals to join an RTO, is a non-RTO compliance option necessary to cure undue discrimination and produce just and reasonable rates for transmission service and the sale of electric energy?

2. Role of Independent Transmission Companies in Standard Market Design

132. We have long recognized that the Independent Transmission Company (ITC) business model can bring significant benefits to the industry. Their for-profit nature with a focus on the transmission business is ideally suited to bring about: (1) Improved asset management including increased investment; (2) improved access to capital markets given a more focused business model than that of vertically integrated utilities; (3) development of innovative services; and (4) additional independence from market participants. We believe that these characteristics of ITCs can have significant benefits for the implementation of Standard Market Design, particularly in the areas of development of transmission infrastructure and structural independence from market participants.

133. The Commission recently approved a proposal by several transmission owners to form an ITC, TRANSLink Transmission Company, LLC (TRANSLink), to share responsibility with the Midwest ISO Regional Transmission Organization (the Midwest ISO)

82

and other regions for the RTO functions prescribed in Order No. 2000. In that proceeding, the Commission approved a hybrid RTO formation under which specific RTO functions were delegated to either the RTO or the ITC. Regarding the delegation of functions we stated:

82

TRANSLink Transmission Company, L.L.C.,

et al.,

99 FERC ¶ 61,106 (2002).

Our rulings on the allocation of functions issues are based on our belief that for effective RTO operations, regional trading, and one-stop shopping, a single transmission provider must have overall authority and ultimate responsibility for transmission service in the region. We further believe that the security-constrained, economic dispatch needed for an efficient and reliable market is best operated by an independent regional transmission provider. However, we believe that it is acceptable for some functions with predominantly local characteristics to be delegated to an ITC so long as the RTO has oversight authority in the event that local actions have a regional impact. We find that this is critical to successful RTO development and especially important given the characteristics of the interstate transmission grid. It has become increasingly evident in recent years that even seemingly local issues, such as generator location or isolated transmission bottlenecks, can and do impact the larger grid, and that is why we believe that centralized RTO oversight is needed.

We also remain concerned that vesting control into sub-regional entities may create seams which could easily lead to re-balkanization. These difficult delegation decisions are made with our firm belief that ITCs can flourish under the RTO umbrella and that in performing certain delegated functions, ITCs will be able to effectively manage their assets, protect their value, and bring their expertise to increase efficiencies and enhance the value of their business. Nevertheless, these delegation decisions should not prevent ITCs from seeking additional authority, subject to Commission approval, at a later date after ITCs have gained experience under RTO operations.

83

We are also guided by the premise that any delegation of functions to an ITC must be consistent with and further the Commission's goals in the SMD Proceeding. We assume in this order that the Midwest ISO will be the transmission provider in the TRANSLink area and will operate a real-time and day-ahead market, or any functions that are required under the SMD final rule.

84

83

We recognize that as the Midwest ISO and ITCs gain experience, they should, from time to time, reassess the assignment of the functions and reevaluate whether some that have been delegated to a local level need to be performed at a regional level and vice versa. Likewise, after SMD is implemented, the assignment of functions may need to be reassessed. (Footnote 37 in original).

84

TRANSLink, 99 FERC at 61,463.

134. We seek comment on the functions that an ITC should perform under Standard Market Design. Should the Commission retain the same delegation of functions that was approved in

TRANSLink?

Are there elements of the proposed Standard Market Design that would justify a different delegation of functions? Should an ITC qualify as an Independent Transmission Provider?

135. We seek comment on whether an ITC that has no ties to a Market Participant, as defined in this proposal, is sufficiently independent to act as the Independent Transmission Provider. The ITC may hold grid assets such as transmission facilities and Congestion Revenue Rights and may be allowed a performance-based ratemaking program. Thus the Commission is concerned that the ITC may unduly discriminate in favor of its own transmission interests when carrying out operational and planning decisions in its role as Independent Transmission Provider. We seek comment on whether such ITC interests in transmission investment may cause the ITC to unduly discriminate in day ahead or real time markets operations or to discount generation, demand response, and other transmission owners' (

e.g.

, merchant transmission) solutions to grid problems. On the other hand, generation and demand response solutions are likely to have the first opportunity to respond to LMPs if it makes economic sense to do so, given the difficulty in siting transmission. Given the planning process and stakeholder input, as well as the Commission's authority to set rates, we seek comment on what specific ways an ITC could make such unduly discriminatory decisions? The Commission is convinced that, if its role is appropriately defined, and opportunities for undue discrimination are addressed, the ITC shows great promise to address grid problems through profit driven activities. One such activity could be reducing congestion where an ITC with properly structured performance based rates would have an incentive. What is the appropriate role for the ITC?

C. The New Transmission Service

136. To address the discrimination described in Section III above and in Appendix C, we will require Independent Transmission Providers to provide a nondiscriminatory, standard transmission service to all customers.

This new service, Network Access Service, combines features of both the existing open access transmission services—Network Integration Transmission Service and Point-to-Point Transmission Service. The Network Access Service is grounded in the flexibility of network integration transmission service, but adds a measure of reassignability similar to that available under firm Point-to-Point Transmission Service. Thus, Network Access Service will give all customers the opportunity to have tradable Congestion Revenue Rights

85

that will expand their transmission options and enhance competition in wholesale electric markets. It also will result in all transmission services being performed under a single set of rules.

85

Congestion Revenue Rights entitle the holder to receive specified congestion revenues in the day-ahead market. To the extent that a customer's real-time schedule coincides with its day-ahead schedule and its Congestion Revenue Rights, these rights offer complete protection against uncertain congestion charges.

137. To complement Network Access Service and implement the Standard Market Design, Independent Transmission Providers will manage congestion using LMP. Management of transmission grid congestion is difficult to do through bilateral transactions alone; thus a spot market is required to manage congestion efficiently. We believe that congestion management, balancing of load and generation in real time, and the provision of ancillary services can be accomplished most reliably and efficiently by a bid-based, security-constrained spot market.

138. In addition to administering a spot market to manage congestion, the Independent Transmission Provider will also use it to handle imbalances and the procurement of ancillary services. The Independent Transmission Provider would operate markets for energy, regulation, operating reserve—spinning and operating reserve—supplemental. These markets would be security-constrained, bid-based markets operated in two time frames: (1) A day ahead of real-time operations, and (2) in real time. Transmission services will be scheduled through the day-ahead and real-time markets. The Independent Transmission Provider would establish schedules for transmission service, and sales and purchases of energy, regulation, and both operating reserves, to ensure the most efficient use of the transmission grid. Although the Independent Transmission Provider will not be required to operate an organized market for either short- or long-term bilateral transactions, its scheduling process must accommodate such bilateral trades.

1. Basic Rights

139. Network Access Service builds upon the existing Order No. 888 Network Integration Transmission Service and will be available to all eligible customers. As with Network Integration Transmission Service, Network Access Service offers flexible use of the transmission grid—it allows the load-serving entity to choose to serve its load with any available resource on the system (or access any interface to import power from a neighboring system), consistent with the Network Resource Interconnection Service discussed in the Generator Interconnection proposed rule.

86

Network Access Service allows a customer to have the Independent Transmission Provider integrate, dispatch and regulate the customer's current and planned resources to serve its load as is currently done under the

pro forma

tariff. Customers, including generators and marketers, can also use this service for through-and-out service, to aggregate resources for resale, and to perform hub-to-hub transactions similar to Point-to-Point Transmission Service. In addition, Network Access Service allows the customer (1) to trade (reassign) its Congestion Revenue Rights and (2) to access points, which, under the current

pro forma

tariff, are secondary points that may be fully subscribed, by paying all applicable congestion charges.

86

Standardization of Generator Interconnection Agreements and Procedures, FERC Stats. & Regs. ¶ 32,560. Network Resource Interconnection Service requires that sufficient network upgrades be built so that interconnecting generators can serve load as a Network Resource, as defined by the existing

pro forma

tariff.

140. Network Access Service is premised on dispatching of the regional transmission grid so that the customers that value transmission service the most will get it. All requested transactions must be physically feasible under a security-constrained dispatch. Where there are transmission constraints, the LMP system we propose will price out all transactions and redispatch available generation as needed to accommodate all requests for service.

87

87

In all but limited cases, this should allow the Independent Transmission Provider to satisfy all requests for service by customers willing to pay the applicable congestion charges.

141. Network Access Service gives the customer the right to transmit power between any number of combinations of receipt and delivery points. A receipt point is defined here as the location where a transaction originates, and a delivery point is defined as the location where a transaction terminates. Receipt and delivery points include both individual nodes as well as aggregated points,

e.g.

, trading hubs. Thus, a Network Access Service customer could use this service to move power from a generator (receipt point) to a load (delivery point), from a generator (receipt point) to a trading hub (delivery point), from one trading hub to another, or from a trading hub (receipt point) to a load (delivery point). A Network Access Service customer would have access to all receipt and delivery points on the system and would be able to substitute receipt points on a daily or hourly basis through the day-ahead and real-time scheduling processes.

142. Any customer using transmission service, whether a load-serving entity, generator, or marketer, would take Network Access Service. However, as explained more fully in Section IV.D.1, only those customers taking power off of the grid would pay the access charge. (All customers would pay congestion costs and losses associated with their particular transaction.) We expect that, in most instances, it would be a load-serving entity, rather than a generator or marketer, that would be the customer for transactions that result in power leaving the grid, and thus, the load-serving entity would be the entity paying the access charge.

88

88

An end-use customer in a state with retail access could be the entity taking transmission service and paying the access charge.

2. Access to Transmission Service

143. Under the existing

pro forma

tariff, “firm” transmission service implies certainty both with respect to delivery and price. Once a customer taking firm service under the existing

pro forma

tariff agrees to pay the transmission rate and schedules service, it has full assurance that it will be able to transmit power between its chosen receipt and delivery points without service interruption (absent force majeure or curtailment) and without being subject to any additional costs (

e.g.

, redispatch). However, there are times when a transmission provider cannot offer a guarantee of service availability (absent the long-term solution of a customer agreeing to pay for system expansion). At these times, under the existing pro forma tariff, only non-firm transmission service (which can be interrupted for economic reasons)

89

is available at the stated maximum rate. Thus, the existing

pro forma

transmission service begins with the basic premise of price certainty, but includes a measure of uncertainty

regarding service availability that is resolved only if firm service can be secured. In sum, the customer is generally assured of the rate it will pay for transmission service, but, unless it has secured firm transmission service between the specified points, is not necessarily assured that it will receive transmission service.

89

All services, including firm service, can be curtailed for reliability reasons.

144. With Network Access Service, all customers who want physically feasible service will be able to receive service; however, uncertainty can arise as to the rate paid to receive the service. In addition to the access charge (which recovers the embedded costs of the transmission system), the customer would be subject to the cost of congestion between its chosen receipt and delivery points. To achieve certainty with respect to price and avoid congestion costs, the customer would have to acquire the Congestion Revenue Rights associated with its specific receipt point-delivery point combination(s).

90

Thus, Network Access Service, coupled with Congestion Revenue Rights for the desired points, provides the customer with certainty with respect to delivery and price, comparable to the existing

pro forma

tariff's firm service.

90

Congestion Revenue Rights provide the rights holder with the revenues associated with congestion between the associated points; thus, any congestion costs it pays are fully offset by these revenues. To the extent the Congestion Revenue Rights holder opts not to schedule transmission service at those points, it would still receive the congestion revenues.

145. Accordingly, customers desiring service comparable to (but actually more dependable than) existing firm transmission service would need to acquire Congestion Revenue Rights for their receipt and delivery points and schedule service between those points in the day-ahead market. With the allocation process we propose in Section IV.H.2, customers under existing contracts will receive Congestion Revenue Rights that match their current use of the system, which will ease and simplify the conversion process. Customers using non-firm transmission service under the existing pro forma tariff could request service when needed in the day-ahead or real-time markets. To the extent the customer is willing to pay congestion costs and transmission losses, its requested transmission service would be available and provided.

91

A customer also has the option of placing a limit on the amount of congestion charges it is willing to pay—to the extent that amount is exceeded, the customer would not take transmission service for that receipt point-delivery point combination during the requested time period. This means no separate non-firm transmission service option is needed under Network Access Service.

91

As discussed in Section IV.D.3, customers exporting power from or transmitting through one region would not be subject to that region's access charge, but would be liable for the cost of congestion and transmission losses associated with its transaction.

3. Service Limitations in the Existing

Pro Forma

Tariff

146. The existing

pro forma

tariff limits how the Network Integration Transmission Service and Point-to-Point Transmission Service can be used. It limits the use of interface capability by Network Integration Transmission Service customers to the amount of the customer's load. Under the LMP system that we are proposing, transmission service would be available to any customer up to the full amount of the transfer capability, so long as the customer is willing to pay the applicable congestion charges. The specifics of scheduling power across interfaces is discussed in a later section.

147. The existing

pro forma

tariff also requires the network customer to take Point-to-Point Transmission Service for any additional third-party sales transaction or to serve load on another transmission provider's system. This will no longer be necessary with Network Access Service, which will be used for all transmission services, including third-party sales transactions and transmission service for load on another transmission provider's system. A customer, however, may prefer to have separate service agreements for service to particular loads for accounting or tracking purposes.

4. Conditions for Receiving Service

148. To receive Network Access Service, a customer must meet the same requirements as those under the existing

pro forma

tariff for acquiring the right to schedule transmission service: all customers must meet creditworthiness and other eligibility standards, complete an application for service, and meet certain operating standards (

e.g.

, reliability maintenance of customer-owned facilities for integration with the transmission provider's system, including metering and communications equipment) as defined in the current

pro forma

tariff. Similarly, the customer must have a service agreement to take service under the tariff. A load-serving entity would also need a network operating agreement, which would detail how the Independent Transmission Provider's system under the SMD Tariff and the load-serving entity's system would work together (similar to a generator interconnection agreement).

92

These standards are largely unchanged from the existing

pro forma

tariff. In addition, the customer must agree to pay any congestion charges and transmission losses associated with its request

93

and any customer serving load located within the Independent Transmission Provider's system must agree to pay the applicable access charge.

92

Consistent with the existing

pro forma

tariff, a Network Access Service customer would retain the right to request that the Independent Transmission Provider file an unexecuted transmission agreement or network operating agreement if the two parties cannot agree on the terms and conditions of service.

93

As noted earlier and more fully explained in Section IV.E.3., a customer can protect itself against the costs of congestion by acquiring Congestion Revenue Rights in the amount of its load and between the receipt/delivery points where its desired resources and loads are located.

5. Scheduling Transmission Service and Acquiring Congestion Revenue Rights

149. As noted above, a customer would acquire Congestion Revenue Rights to assure price and delivery certainty for its transactions. Anyone can hold Congestion Revenue Rights. Congestion Revenue Rights can be acquired through a variety of means, including: (1) Direct allocation that is based on some measure of current or historical rights to the system; (2) periodic auctions; or (3) some combination of these methods. The initial process for acquiring these rights is discussed in Section IV.H.2.

150. Transmission service will be scheduled through the day-ahead market with deviations accounted for in the real-time market, as discussed in later sections. These scheduling opportunities are comparable to the existing

pro forma

tariff's requirements (

e.g.

, firm point-to-point transmission service scheduled by no later than 10 a.m. the day before, with schedules submitted after that time accommodated, if practicable, and allowance to make changes to that “day-ahead” schedule prior to the start of the next clock hour). However, the new service synchronizes the scheduling of transmission service and energy, and relies on a transmission customer holding Congestion Revenue Rights or its willingness to pay the cost of congestion, rather than on a firm/non-firm, first-come, first served method, to ration capacity.

151. A Network Access Service customer would have to indicate the location of its receipt and delivery points when it schedules service in the day-ahead or real-time markets.

94

If a

customer holds Congestion Revenue Rights between a set of receipt and delivery points in the day-ahead market, but later decides to take transmission service between a different set of points, the customer would no longer have full protection against congestion costs for its transaction in the day-ahead market and could incur different congestion costs than the congestion revenues associated with the Congestion Revenue Rights it holds. Similarly, to the extent that a customer's real-time transactions differ from its day-ahead schedule, the customer would be liable for any redispatch costs that occur in real time that are necessary to accommodate its real-time transactions.

94

Further, consistent with the existing

pro forma

tariff and the Commission's decision regarding “tagging,” the customer must identify the ultimate source and sink so that the various system operators in an interconnection can assess the simultaneous feasibility of all scheduled power flows.

See

Coalition Against Private Tariffs, 83 FERC ¶ 61,015 at 61,040,

reh'g denied,

84 FERC ¶ 61,050 (1998).

6. Designating Resources and Loads

152. The existing

pro forma

tariff allows a Network Integration Transmission Service customer to designate resources that the customer owns or has committed to purchase pursuant to an executed, non-interruptible contract. The transmission provider must then plan and operate its system to be able to provide firm transmission service from these resources to the customer's load. Under the proposed Standard Market Design, the reservation of capacity for service is no longer required, since a transmission customer pays the congestion cost for transmission service. Thus, there is no longer a need for a Network Access Service customer to designate network resources to get transmission service. While the integration of resources and loads (including behind-the-meter generation) that occurs under Network Integration Transmission Service will continue, a Network Access Service customer will now request receipt and delivery points through the day-ahead scheduling process and real-time transactions.

153. Thus, we believe that the requirement to designate network resources to receive transmission service may no longer be needed. Further, we note that under the existing

pro forma

tariff the designation of network resources was used in addressing long-term resource adequacy concerns and in the planning process undertaken to ensure that the resources could be integrated. Because we are now proposing a resource adequacy requirement and a regional planning process to meet these requirements, the requirement to designate network resources may no longer be needed. (

See

Section IV.J). We request comment on whether designating network resources and loads is necessary for Network Access Service, particularly with respect to performing the integration of resources and loads.

95

Similarly, with respect to the information required to complete an application for service (Section 2 of the SMD Tariff), is it necessary for the Independent Transmission Provider to request information beyond the identity of and contact information for the customer, service term and commencement date, and receipt and delivery points for the reques

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Remedying Undue Discrimination Through Open Access Transmission Service and Standard Electricity Market Design · 67 FR 55452 | Frix