Environmental Streamlining Provisions in the Transportation Equity Act for the 21st Century: Status of Implementation

Congressional research reportMay 30, 2003

Ask Donna

What actually matters in this document.

Text

Order Code RS20841

Updated May 30, 2003

CRS Report for Congress

Received through the CRS Web

Environmental Streamlining Provisions in the

Transportation Equity Act for the 21st Century:

Status of Implementation

Linda G. Luther and David M. Bearden

Resources, Science, and Industry Division

Summary

Before construction on a federally funded surface transportation project can

proceed, the Department of Transportation’s (DOT’s) Federal Highway Administration

must comply with all state and federal legal requirements regarding the environment,

including the National Environmental Policy Act of 1969 (NEPA, 42 U.S.C. 4321 et

seq.). In 1998, Congress passed the Transportation Equity Act for the 21st Century

(TEA-21, P.L. 105-178), which reauthorized the federal surface transportation programs.

At the time, various stakeholders reported to Congress that the numerous federal

environmental approvals and permits needed to build a highway were inefficient and

overly time-consuming. Congress attempted to address these concerns by including

“Environmental Streamlining” provisions in TEA-21 that required DOT to develop and

implement a “coordinated environmental review process” for projects that do or may

have a significant impact on the environment (approximately 10% of all highway

projects). This review process is intended to encourage full and early participation by

all relevant federal and state agencies required to participate in a highway project.

Numerous administrative activities have been undertaken to facilitate streamlining.

However, regulations to implement the streamlining provisions of TEA-21 have not

been finalized. Some Members of Congress have expressed concern over the lack of

regulations, and have argued that further legislative action is necessary to achieve faster

project delivery. The Administration’s legislative proposal for surface transportation

reauthorization was introduced in the House (H.R. 2088) and Senate (S. 1072) on May

14 and 15, 2003, respectively. Included in the bill are provisions intended to further

streamline the NEPA process. This report will be updated.

Introduction

The National Environmental Policy Act of 1969 (NEPA, P.L. 91-190) requires all

federal agencies to consider the environmental impact of their proposed actions. To

ensure that environmental impacts are considered before final decisions are made, NEPA

requires federal agencies to provide a detailed statement of environmental impacts for

every proposed federal action significantly affecting the quality of the environment. The

“detailed statement” was subsequently referred to as an environmental impact statement

Congressional Research Service ˜ The Library of Congress

CRS-2

(EIS). Projects with less than significant impacts also require documentation. Such

projects either require an Environmental Assessment (EA) or are categorically excluded

from requirements to prepare an EA or EIS. According to the Federal Highway

Administration (FHWA), in 2001 approximately 3% of all highway projects required an

EIS, 7% required an EA, and 90% were classified as categorical exclusions. Projects

requiring an EIS accounted for 9% of the funds allocated by FHWA. While the number

of projects requiring an EIS represents a small portion of the total projects and funds

allocated, they are often complex and affect sizable populations.

In 1998, Congress passed the Transportation Equity Act for the 21st Century (TEA21, P.L. 105-178), which reauthorized the federal surface transportation programs for

highways, highway safety, and transit for the fiscal years 1998-2003. During the

reauthorization process, states reported to Congress that the numerous federal

environmental approvals and permits needed to build a highway were inefficient and

overly time-consuming. To address these concerns, Congress included in TEA-21 Section

1309, “Environmental Streamlining,” which was intended to better coordinate federal

agency involvement in the NEPA process.

This report describes how the NEPA process is used to demonstrate compliance with

environmental requirements and also discuses environmental documents required for

highway projects, the time involved in completing them, environmental streamlining

provisions under TEA-21, administrative actions taken to implement these requirements,

and legislative activity in the 108th Congress.

The “NEPA Umbrella”

In addition to complying with NEPA, any given transportation project may require

compliance with a wide variety of legislative and regulatory requirements, enforceable by

multiple agencies. Under FHWA regulations, compliance with all applicable

environmental laws, executive orders, and other related requirements must be documented

within the appropriate NEPA documentation.1 It is FHWA policy that compliance with

all applicable environmental requirements be coordinated under the “NEPA umbrella.”

This means that, for any given transportation project, any study, review, or consultation

required by law that is related to the environment should be conducted within the

framework of the NEPA process. Legal requirements that frequently apply to

transportation projects include the Endangered Species Act of 1973 (16 U.S.C. 1536), the

National Historic Preservation Act (16 U.S.C. 470), or the Clean Water Act (33 U.S.C.

1344).

Environmental Documents Required Under NEPA

Under NEPA, FHWA must prepare an EIS for federally funded highway projects if

it is known that the action will have a significant effect on the environment. The EIS

must include a description of the project’s purpose and need, an analysis of all reasonable

project alternatives, a description of the affected environment, and the environmental

1

23 CFR 771.133

CRS-3

consequences of impacts to the affected environment of each alternative.2 The EIS must

also demonstrate that appropriate comments were solicited from relevant federal, state and

local agencies and from the public. Relevant agencies obligated to provide comments are

those with jurisdiction by law or special expertise with regard to the environmental

impacts of the project. For example, if a project alternative impacts a historical site, the

Advisory Council on Historic Preservation may be required to participate in the NEPA

process. If impacts to wetlands are identified, the U.S. Army Corps of Engineers may

need to provide comments or issue a permit before a project may proceed.

If it is not clear whether a project would have significant impacts, an Environmental

Assessment (EA) must be prepared. An EIS is required if significant impacts are

identified at any time during preparation of the EA. Otherwise, a Finding of No

Significant Impact (FONSI) will be issued. Projects that do not individually or

cumulatively have a significant social, economic, or environmental impact are excluded

from the requirement to prepare an EA or EIS. Such projects are processed as Categorical

Exclusions (CEs). State agencies are required to provide FHWA with documentation to

prove the action qualifies as a CE. The type of documentation required will depend upon

the project. Final design activities, property acquisition, or project construction cannot

proceed until one of the following occurs: an action is classified as a CE; a FONSI is

approved for an EA; or an EIS is approved.3

Time to Prepare NEPA Documentation

In 2001, FHWA undertook an analysis of the direct effect that compliance with the

requirements of NEPA has on the ultimate schedule and cost of a completed

transportation project.4 The report was intended to establish a baseline for completion of

NEPA documentation, against which progress on its streamlining initiatives could be

gauged. On average, the time to complete an EIS in the 1990s was 5.0 years. In 1999,

the average time was 5 years and 10 months. FHWA reported that its streamlining efforts

reduced that time to 5 years and 2 months in 2001. The study also found a correlation

between average environmental review time and factors such as the FHWA region in

which the EIS was processed and the number and type of regulations that applied to a

given project. FHWA estimated that the average time to complete and approve an EA

was 18 months, and the average time to complete a CE determination was 6 months.

Streamlining Requirements Under TEA-21

TEA-21 authorized federal surface transportation programs for highways, highway

safety, and transit for the 6-year period FY1998-FY2003. To address concerns about

construction delays, Section 1309 on Environmental Streamlining was included. FHWA

2

FHWA regulations implementing the NEPA process are specified at 23 CFR 771; further

guidance is available on the “NEPA: Project Development Process” web page at

[http://www.fhwa.dot.gov/environment/00001.htm].

3

4

23 CFR 771.113.

See FHWA’s Evaluating the Performance of Environmental Streamlining: Development of a

NEPA Baseline for Measuring Continuous Performance, May 8, 2001, available at

[http://www.fhwa.dot.gov/environment/strmlng/baseline].

CRS-4

defines “environmental streamlining” as cooperatively establishing realistic project

development time frames among the transportation and environmental agencies, and then

working together to adhere to those time frames.5 Key elements of Section 1309 are:

Directs the Secretary of Transportation to establish and implement a

“coordinated environmental review process” that encourages full and

early participation by all relevant agencies required to review a highway

construction project or issue a permit, license, analysis, opinion or

approval relating to the project. The process may be documented in a

memorandum of understanding between DOT and affected agencies.

! Requires the coordinated environmental review process to encourage

agencies to conduct reviews concurrently, rather than sequentially,

according to cooperatively determined time periods.

! Creates a dispute resolution process that directs the Secretary to close the

record on an activity if it is not completed by an agency within the agreed

upon time frame. If an unresolved matter involves an activity required by

law, the Secretary and the affected agency are directed to resolve the

matter within 30 days.

! Allows state DOTs to require all state agencies with jurisdiction over

environmental issues to be subject to the coordinated environmental

review process.

! Provides states with the authority to request funds to reimburse affected

agencies for expenses associated with meeting time limits for

environmental review, if those time limits are less than usual.

!

The streamlining requirements in TEA-21 do not permit the Secretary to override the

authority of another agency. TEA-21 also clarifies that nothing in the streamlining

requirements will affect the reviewability of any final federal agency action in a U.S.

district court or state court, affect the applicability of NEPA or any other environmental

statute, or affect the responsibility of any federal officer to comply with such statutes.

Administrative Actions to Implement Streamlining Goals

DOT has undertaken a variety of actions to meet the goals of TEA-21's streamlining

requirements. However, no final regulations have been implemented. In May 2000,

under the Clinton Administration, FHWA submitted a proposed rule on “NEPA and

Related Procedures for Transportation Decisionmaking.”6 Some commenters indicated

that the proposed rule failed to streamline the review process. Elements of the rule

presented an increased burden of paperwork and procedural requirements, they said, and

increased the potential for litigation. There was also a concern that the proposed rule

lacked specific provisions addressing timeframes, comment deadlines, dispute resolution,

and “closing the record” on decisionmaking at an appropriate stage. Due to these

concerns, the proposed rule was withdrawn by FHWA in September 2002.7 Since

withdrawal of the proposed rule came within a year of the legislative reauthorization of

5

See [http://www.fhwa.dot.gov/environment/strmlng/overview.htm]

6

65 Federal Register 33960.

7

67 Federal Register 59225.

CRS-5

surface transportation programs, the agency stated that it would wait for the outcome of

the legislative process to see what further regulatory changes were needed. In lieu of final

regulations, DOT has implemented a variety of administrative actions in response to

TEA-21's streamlining requirements. Selected actions are described below.

Executive Order Implementation. In September 2002, President Bush issued

an executive order directing federal agencies to expedite environmental reviews for

transportation projects deemed “high-priority” by DOT.8 Among the criteria for project

selection are whether they are of national or regional significance and whether they may

experience delays from lack of federal interagency coordination. As required by the order,

an Interagency Transportation Infrastructure Streamlining Task Force, chaired by the

Secretary of Transportation, is to monitor work on expedited projects, review the list of

suggested projects, and identify and promote policies that aid in streamlining. The Task

Force also includes members from federal agencies likely involved in environmental

project reviews. To date, ten highway projects have been chosen for expedited review.

2002 Report to Congress. In April 2003, FHWA submitted its Report to

Congress on FHWA environmental streamlining activities during 2002.9 The report

provided an update on the status of such activities as the implementation of the executive

order regarding streamlining, the creation of guidance materials to facilitate streamlining,

efforts to re-engineer the environmental review process, and state efforts at streamlining.

National Memorandum of Understanding. In July 1999, FHWA and six other

federal agencies signed a National Memorandum of Understanding (MOU) on

streamlining.10 It expresses the commitment of each agency to streamline the

environmental review process in accordance with TEA-21.

Dispute Resolution Procedures. FHWA developed the National Dispute

Resolution System, one element of which was the development of guidance to be used to

manage conflict and resolve disputes between state and federal agencies during the

transportation project development and environmental review process.11 Workshops in

the application and use of alternative dispute resolution are currently being scheduled and

will use the guidance as the principal reference document.

Support of State Streamlining Initiatives. In April 1999, the FHWA,

Environmental Protection Agency, and the American Association of State Highway and

Transportation Officials (AASHTO) established a pilot program to gain practical

experience in streamlining. The program focuses on various aspects of the review

process, such as early coordination and establishing time frames for environmental

reviews. In 2002, AASHTO launched the “Center for Environmental Excellence” to

assist its members in promoting “innovative streamlining” of the project delivery process.

8

Executive Order 13274 is available at [http://www.fhwa.dot.gov/stewardshipeo/index.htm]

9

The report is available at [http://www.fhwa.dot.gov/environment/strmlng/final02rpt.htm].

10

11

Full text of the MOU is available at [http://www.fhwa.dot.gov/environment/nmou4.htm].

The guidance, issued December 2002, “Collaborative Problem Solving: Better and Streamlined

Outcomes for All,” is available at [http://nepa.fhwa.dot.gov/ReNepa/ReNepa.nsf/].

CRS-6

FHWA is also supporting individual states in implementing streamlining initiatives by

providing program funding or technical support.

Legislative Actions to Facilitate Streamlining

During the 107th Congress, oversight hearings were to held to evaluate the

Administration’s progress in implementing TEA-21's requirements, such as the

development of a consistent process to put streamlining into practice on a national scale.

Some Members expressed disappointment that regulations to implement TEA-21's

streamlining requirements have not been issued. Two bills were introduced late in the

107th Congress. In September 2002, Representative Young introduced the Expediting

Project Delivery to Improve Transportation and the Environment Act (H.R. 5455). In

October 2002, Senator Baucus introduced the Maximum Economic Growth for America

Through Environmental Streamlining Act (S. 3031). Neither bill was enacted, and neither

has been reintroduced in the 108th Congress. However, due to ongoing concerns over

highway project delays, elements of these or similar bills may be included as part of the

transportation program reauthorization process.

On May 13, 2003, DOT formally submitted its legislative proposal to reauthorize

surface transportation programs. The Administration’s proposal was introduced in the

House (H.R. 2088) and Senate (S. 1072) on May 14 and 15, 2003, respectively. The

proposal, the Safe, Accountable, Flexible and Efficient Transportation Equity Act of 2003

or SAFETEA, includes three sections that deal with NEPA-related issues. They are:

Section 1602. Efficient Environmental Reviews for Project

Decisionmaking. Would repeal Section 1309 and replace it with similar

provisions, including the addition of provisions to: allow for the

coordinated environmental review process and establishment of time

frames to be initiated by project sponsors; allow the coordinated review

process to be implemented for transit projects; codify the right of states

to prepare environmental documents; allow the dispute resolution process

to be initiated by state governors; and impose a 180-day limit on judicial

review of an final permit, license or other approval related to the project.

! Section 1603. Assumption of Responsibility for Categorical Exclusions.

Would allow states to assume authority to designate and approve CEs.

! Section 1604. “Section 4(f)” Policy on Lands, Wildlife and Waterfowl

Refuges, and Historic Sites. Would revise current statutory requirements

prohibiting the use of public parks and recreation lands, wildlife and

waterfowl refuges, and historic sites unless there is no prudent and

feasible alternative to do otherwise, and the project includes all possible

planning to minimize harm to land. The proposal clarifies conditions

under which such resources could be used for transportation projects.

!

These provisions are likely to generate controversy. For example, the establishment

of time frames for environmental reviews has been an issue of ongoing concern with

environmental groups. Also, clarifying situations in which “Section 4(f)” lands could be

used may be interpreted as weakening current requirements. It is expected that a variety

of additional issues may arise in response to the Administration’s proposal. Also,

subsequent bills introduced in the 108th Congress may differ from this proposal.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.