Power Plants: Characteristics and Costs

Congressional research reportNov 13, 2008

Ask Donna

What actually matters in this document.

Text

Power Plants: Characteristics and Costs

(name redacted)

Specialist in Energy and Environmental Policy

November 13, 2008

Congressional Research Service

7-....

www.crs.gov

RL34746

CRS Report for Congress

Prepared for Members and Committees of Congress

Power Plants: Characteristics and Costs

Summary

This report analyzes the factors that determine the cost of electricity from new power plants.

These factors—including construction costs, fuel expense, environmental regulations, and

financing costs—can all be affected by government energy, environmental, and economic

policies. Government decisions to influence, or not influence, these factors can largely determine

the kind of power plants that are built in the future. For example, government policies aimed at

reducing the cost of constructing power plants could especially benefit nuclear plants, which are

costly to build. Policies that reduce the cost of fossil fuels could benefit natural gas plants, which

are inexpensive to build but rely on an expensive fuel.

The report provides projections of the possible cost of power from new fossil, nuclear, and

renewable plants built in 2015, illustrating how different assumptions, such as for the availability

of federal incentives, change the cost rankings of the technologies.

None of the projections is intended to be a “most likely” case. Future uncertainties preclude firm

forecasts. The rankings of the technologies by cost are therefore also an approximation and

should not be viewed as definitive estimates of the relative cost-competitiveness of each option.

The value of the discussion is not as a source of point estimates of future power costs, but as a

source of insight into the factors that can determine future outcomes, including factors that can be

influenced by the Congress.

Key observations include the following:

•

Government incentives can change the relative costs of the generating

technologies. For example, federal loan guarantees can turn nuclear power from a

high cost technology to a relatively low cost option.

•

The natural gas-fired combined cycle power plant, the most commonly built type

of large natural gas plant, is a competitive generating technology under a wide

variety of assumptions for fuel price, construction cost, government incentives,

and carbon controls. This raises the possibility that power plant developers will

continue to follow the pattern of the 1990s and rely heavily on natural gas plants

to meet the need for new generating capacity.

•

With current technology, coal-fired power plants using carbon capture equipment

are an expensive source of electricity in a carbon control case. Other power

sources, such as wind, nuclear, geothermal, and the natural gas combined cycle

without capture technology currently appear to be more economical.

Congressional Research Service

Power Plants: Characteristics and Costs

Contents

Introduction and Organization .....................................................................................................1

Types of Generating Technologies...............................................................................................2

Electricity Demand and Power Plant Choice and Operation...................................................2

Generation and Load.......................................................................................................2

Economic Dispatch and Heat Rate...................................................................................3

Capacity Factor...............................................................................................................4

Utility Scale Generating Technologies...................................................................................5

Supercritical Pulverized Coal ..........................................................................................6

Integrated Gasification Combined Cycle (IGCC).............................................................7

Natural Gas Combined Cycle ..........................................................................................8

Nuclear Power ................................................................................................................9

Geothermal Power ........................................................................................................ 10

Wind Power .................................................................................................................. 10

Solar Thermal and Solar Photovoltaic (PV) Power ........................................................ 10

Factors that Drive Power Plant Costs......................................................................................... 11

Government Incentives ....................................................................................................... 11

Renewable Energy Production Tax Credit ..................................................................... 12

Nuclear energy production tax credit ............................................................................. 12

Loan Guarantees for Nuclear and Other Carbon-Control Technologies .......................... 12

Energy Investment Tax Credit ....................................................................................... 13

Clean Coal Technologies Investment Tax Credit ............................................................ 14

State and Local Incentives............................................................................................. 14

Capital and Financing Costs ................................................................................................ 15

Construction Cost Components and Trends ................................................................... 15

Financing Power Plant Projects ..................................................................................... 17

Fuel Costs ........................................................................................................................... 20

Air Emissions Controls for Coal and Gas Plants .................................................................. 22

Conventional Emissions ................................................................................................ 23

Carbon Dioxide............................................................................................................. 25

Financial Analysis Methodology and Key Assumptions............................................................. 30

Analysis of Power Project Costs................................................................................................ 31

Case 1: Base Case............................................................................................................... 32

Key Observations.......................................................................................................... 32

Discussion .................................................................................................................... 32

Case 2: Influence of Federal and State Incentives ................................................................ 37

Key Observations.......................................................................................................... 37

Discussion .................................................................................................................... 37

Case 3: Higher Natural Gas Prices....................................................................................... 40

Key Observations.......................................................................................................... 40

Discussion .................................................................................................................... 41

Case 4: Uncertainty in Capital Costs ................................................................................... 43

Key Observations.......................................................................................................... 43

Discussion .................................................................................................................... 44

Case 5: Carbon Controls and Costs...................................................................................... 45

Key Observations.......................................................................................................... 45

Discussion .................................................................................................................... 45

Congressional Research Service

Power Plants: Characteristics and Costs

Figures

Figure 1. Illustrative Load Curve.................................................................................................3

Figure 2. Total U.S. Electric Power Generation by Energy Source, 2007......................................7

Figure 3. Coal and Natural Gas Constant Dollar Price Trends .................................................... 21

Figure 4. Uranium Price Trends................................................................................................. 22

Figure 5. EIA’s Projections of S. 2191 CO2 Allowance Prices (2006$ per Metric Ton of

CO2 Equivalent) ..................................................................................................................... 29

Figure 6. Comparison of EIA’s Reference Case Coal Prices and S. 2191 Core Case CO2

Allowance Prices ................................................................................................................... 30

Figure 7. Natural Gas Price Trends (Henry Hub Spot Price)....................................................... 41

Figure 8. Projection of Natural Gas Prices to Electric Power Plants, 2006 $ per MMBtu............ 42

Figure A-1. Process Schematic: Pulverized Coal without Carbon Capture.................................. 52

Figure A-2. Process Schematic: Pulverized Coal with Carbon Capture....................................... 52

Figure A-3. Representative Pulverized Coal Plant: Gavin Plant (Ohio) ...................................... 53

Figure A-4. Process Schematic: IGCC without Carbon Capture................................................. 53

Figure A-5. Process Schematic: IGCC with Carbon Capture...................................................... 54

Figure A-6. Representative IGCC Plant: Polk Plant (Florida)..................................................... 54

Figure A-7. Process Schematic: Combined Cycle Power Plant................................................... 55

Figure A-8. Representative Combined Cycle: McClain Plant (Oklahoma).................................. 55

Figure A-9. Process Schematic: Pressurized Water Reactor (PWR)........................................... 56

Figure A-10. Process Schematic: Boiling Water Reactor (BWR)............................................... 57

Figure A-11. Representative Gen III/III+ Nuclear Plant: Rendering of the Westinghouse

AP1000 (Levy County Project, Florida) ................................................................................. 58

Figure A-12. Schematic of a Wind Turbine................................................................................ 58

Figure A-13. Representative Wind Farm: Gray County Wind Farm (Kansas) ............................. 59

Figure A-14. Wind Turbine Size and Scale (FPL Energy) .......................................................... 59

Figure A-15. Process Schematic: Binary Cycle Geothermal Plant .............................................. 60

Figure A-16. Representative Geothermal Plant: Raft River Plant (Idaho) ................................... 60

Figure A-17. Process Schematic: Parabolic Trough Solar Thermal Plant .................................... 61

Figure A-18. Representative Solar Thermal Plant: Nevada Solar One ........................................ 61

Figure A-19. Nevada Solar One: Parabolic Collector Detail....................................................... 61

Figure A-20. Process Schematic: Central Station Solar Photovoltaic Power ............................... 62

Figure A-21. Representative Solar PV Plant: Nellis Air Force Base (Nevada) ............................ 63

Figure A-22. Nellis AFB Photovoltaic Array Detail ................................................................... 63

Figure B-1. Pulverized Coal Project Cost Trends ....................................................................... 69

Figure B-2. IGCC Project Cost Trends ...................................................................................... 72

Congressional Research Service

Power Plants: Characteristics and Costs

Figure B-3. Nuclear Project Cost Trends ................................................................................... 76

Figure B-4. Combined Cycle Project Cost Trends...................................................................... 79

Figure B-5. Wind Project Cost Trends ....................................................................................... 82

Figure B-6. Geothermal Project Cost Trends ............................................................................. 84

Figure B-7. Solar Thermal Project Cost Trends.......................................................................... 87

Figure B-8. Solar PV Project Cost Trends.................................................................................. 89

Tables

Table 1. Shares of Total National Electric Generation and Generating Capacity, 2006................ 18

Table 2. Emission Controls as an Estimated Percentage of Total Costs for a New

Pulverized Coal Plant............................................................................................................. 25

Table 3. Estimates of the Change in IGCC Plant Capacity and Capital Cost from Adding

Carbon Capture...................................................................................................................... 27

Table 4. Estimated Base Case Results........................................................................................ 34

Table 5. Benchmark Comparison to Natural Gas Combined Cycle Plant Power Costs:

Base Case Values ................................................................................................................... 36

Table 6. Effect of Public Power Financing on Base Case Results ............................................... 37

Table 7. Power Costs with Additional Government Incentives ................................................... 39

Table 8. Benchmark Comparison to Combined Cycle Power Costs: Additional

Government Incentives .......................................................................................................... 40

Table 9. Benchmark Comparison to Natural Gas Combined Cycle Plant Power Costs:

50% Higher Gas Price............................................................................................................ 42

Table 10. Change in the Base Case Gas Price Needed to Equalize the Cost of Combined

Cycle Power with Other Technologies .................................................................................... 43

Table 11. Effect of Higher and Lower Capital Costs on the Cost of Power ................................. 44

Table 12. Benchmark Comparison to Combined Cycle Power Costs: Higher and Lower

Capital Costs.......................................................................................................................... 45

Table 13. Effect of Current Technology Carbon Controls on Power Plant Capital Cost and

Efficiency .............................................................................................................................. 46

Table 14. Estimated Annualized Cost of Power with Carbon Controls........................................ 48

Table 15. Change in the Price of Natural Gas Required to Equalize the Cost of Combined

Cycle Generation (Without Carbon Controls) with Other Technologies................................... 50

Table 16. Cost of Power with Base and Reduced Carbon Capture Cost and Efficiency

Impacts .................................................................................................................................. 51

Table B-1. Pulverized Coal Projects Selected for Cost Estimate................................................. 66

Table B-2. Coal Integrated Gasification Combined Cycle (IGCC) Projects Selected for

Cost Estimate......................................................................................................................... 70

Table B-3. Nuclear Projects Selected for Cost Estimate ............................................................. 73

Table B-4. Combined Cycle Projects Selected for Cost Estimate................................................ 77

Congressional Research Service

Power Plants: Characteristics and Costs

Table B-5. Wind Projects Selected for Cost Estimate ................................................................. 80

Table B-6. Geothermal Projects Selected for Cost Estimate ....................................................... 83

Table B-7. Solar Thermal Projects Selected for Cost Estimate ................................................... 85

Table B-8. Solar Photovoltaic (PV) Projects Selected for Cost Estimate..................................... 88

Table D-1. Financial Factors ..................................................................................................... 93

Table D-2. Power Plant Technology Assumptions...................................................................... 94

Table D-3. Air Emission Characteristics .................................................................................... 95

Table D-4. Fuel and Allowance Price Projections (Selected Years)............................................. 96

Appendixes

Appendix A. Power Generation Technology Process Diagrams and Images ............................... 52

Appendix B. Estimates of Power Plant Overnight Costs ............................................................ 64

Appendix C. Estimates of Technology Costs and Efficiency with Carbon Capture ..................... 90

Appendix D. Financial and Operating Assumptions ................................................................... 93

Appendix E. List of Acronyms and Abbreviations ..................................................................... 97

Contacts

Author Contact Information ...................................................................................................... 98

Congressional Research Service

Power Plants: Characteristics and Costs

Introduction and Organization

The United States may have to build many new power plants to meet growing demand for electric

power. For example, the Energy Information Administration (EIA) estimates that the nation will

have to construct 226,000 megawatts of new electric power generating capacity by 2030.1 This is

the equivalent of about 450 large power plants. Whatever the number of plants actually built,

different combinations of fossil, nuclear, or renewable plants could be built to meet the demand

for new generating capacity. Congress can largely determine which kinds of plants are actually

built through energy, environmental, and economic policies that influence power plant costs.

This report analyzes the factors that determine the cost of electricity from new power plants.

These factors—including construction costs, fuel expense, environmental regulations, and

financing costs—can all be affected by government energy and economic policies. Government

decisions to influence, or not influence, these factors can largely determine the kind of power

plants that are built in the future. For example, government policies aimed at reducing the cost of

constructing power plants could especially benefit nuclear plants, which are costly to build.

Policies that reduce the cost of fossil fuels could benefit natural gas plants, which are inexpensive

to build but rely on an expensive fuel.

The report provides projections of the possible cost of power for new fossil, nuclear, and

renewable plants built in 2015. The projections illustrate how different assumptions, such as for

the availability of federal incentives, change the cost rankings of the technologies. Key

observations include the following:

•

Government incentives can change the relative costs of the generating

technologies. For example, federal loan guarantees can turn nuclear power from a

high cost technology to a relatively low cost option.

•

The natural gas-fired combined cycle power plant, the most commonly built type

of large natural gas plant, is a competitive generating technology under a wide

variety of assumptions for fuel price, construction cost, government incentives,

and carbon controls. This raises the possibility that power plant developers will

continue to follow the pattern of the 1990s and rely heavily on natural gas plants

to meet the need for new power generation.

•

With current technology, coal-fired power plants using carbon capture equipment

are an expensive source of electricity in a carbon control case. Other power

sources, such as wind, nuclear, geothermal, and the natural gas combined cycle

plant without capture technology, currently appear to be more economical.

None of the projections is intended to be a “most likely” case. Future uncertainties preclude firm

forecasts. The value of this discussion is not as a source of point estimates of future power costs,

but as a source of insight into the factors that can determine future outcomes, including factors

that can be influenced by the Congress.

1

EIA, an independent arm of the Department of Energy, is the primary public source of energy statistics and forecasts

for the United States. The estimated amount of new generating capacity is taken from the Excel output spreadsheet for

the Annual Energy Outlook 2008 report. Note that EIA forecasts assume no change to the laws and regulations in effect

at the time the forecasts are made.

Congressional Research Service

1

Power Plants: Characteristics and Costs

The main body of report is divided into the following sections:

•

Types of generating technologies;

•

Factors that drive power plant costs;

•

Financial analysis methodology;

•

Analysis of power project costs.

The report also includes the following appendixes:

•

Appendix A presents power generation technology process diagrams and images.

•

Appendix B and Appendix C provide the data supporting the capital cost

estimates used in the economic analysis. Appendix C also shows how operating

costs and plant efficiencies were estimated for certain carbon control

technologies.

•

Appendix D presents the financial and operating assumptions used in the power

cost estimates.

•

Appendix E is a list of acronyms used in the report.

Types of Generating Technologies

The first part of this section describes how the characteristics of electricity demand influence

power plant choice and operation. The next part describes the generating technologies analyzed in

the report.

Electricity Demand and Power Plant Choice and Operation

Generation and Load

The demand for electricity (“load”) faced by an electric power system varies moment to moment

with changes in business and residential activity and the weather. Load begins growing in the

morning as people waken, peaks in the early afternoon, and bottoms-out in the late evening and

early morning. Figure 1 is an illustrative daily load curve.

The daily load shape dictates how electric power systems are operated. As shown in Figure 1,

there is a minimum demand for electricity that occurs throughout the day. This base level of

demand is met with “baseload” generating units which have low variable operating costs.2

Baseload units can also meet some of the demand above the base, and can reduce output when

demand is unusually low. The units do this by “ramping” generation up and down to meet

fluctuations in demand.

The greater part of the daily up and down swings in demand are met with “intermediate” units

(also referred to as load-following or cycling units). These units can quickly change their output

2

Variable costs are costs that vary directly with changes in output. For fossil fuel units the most important variable cost

is fuel. Solar and wind plants have minimal or no variable costs, and nuclear plants have low variable costs.

Congressional Research Service

2

Power Plants: Characteristics and Costs

to match the change in demand (that is, they have a fast “ramp rate”). Load-following plants can

also serve as “spinning reserve” units that are running but not putting power on the grid, and are

immediately available to meet unanticipated increases in load or to back up other units that go

off-line due to breakdowns.

Figure 1. Illustrative Load Curve

16,000

Peak

Demand

Hourly Load (MW)

14,000

12,000

Intermediate

Demand

10,000

8,000

Baseload

Demand

6,000

This report covers

generating

technologies used

to meet

intermediate and

baseload demand.

4,000

2,000

Midnight to Midnight

The highest daily loads are met with peaking units. These units are typically the most expensive

to operate, but can quickly startup and shutdown to meet brief peaks in demand. Peaking units

also serve as spinning reserve, and as “quick start” units able to go from shutdown to full load in

minutes. A peaking unit typically operates for only a few hundred hours a year.

Economic Dispatch and Heat Rate

The generating units available to meet system load are “dispatched” (put on-line) in order of

lowest variable cost. This is referred to as the “economic dispatch” of a power system’s plants.

For a plant that uses combustible fuels (such as coal or natural gas) a key driver of variable costs

is the efficiency with which the plant converts fuel to electricity, as measured by the plant’s “heat

rate.” This is the fuel input in British Thermal Units (btus) needed to produce one kilowatt-hour

of electricity output. A lower heat rate equates with greater efficiency and lower variable costs.

Other things (most importantly, fuel and environmental compliance costs) being equal, the lower

a plant’s heat rate, the higher it will stand in the economic dispatch priority order. Heat rates are

inapplicable to plants that do not use combustible fuels, such as nuclear and non-biomass

renewable plants.

As an illustration of economic dispatch, consider a utility system with coal, nuclear, geothermal,

natural gas combined cycle, and natural gas peaking units in its system:

•

Nuclear, coal, and geothermal baseload units, which are expensive to build but

have low fuel costs and therefore low variable costs, will be the first units to be

put on line. Other than for planned and forced maintenance, these baseload

generators will run throughout the year.

Congressional Research Service

3

Power Plants: Characteristics and Costs

•

Combined cycle units, which are very efficient but use expensive natural gas as a

fuel, will meet intermediate load. These cycling plants will ramp up and down

during the day, and will be turned on and off dozens of times a year.

•

Peaking plants, using combustion turbines,3 are relatively inefficient and burn

expensive natural gas. They run only as needed to meet the highest loads.4

An exception to this straightforward economic dispatch are “variable renewable” power plants—

wind and solar—that do not fall neatly into the categories of baseload, intermediate, and peaking

plants. Variable renewable generation is used as available to meet demand. Because these

resources have very low variable costs they are ideally used to displace generation from gas-fired

combined cycle plants and peaking units with higher variable costs. However, if wind or solar

generation is available when demand is low (such as a weekend or, in the case of wind, in the

evening), the renewable output could displace coal generation.

Power systems must meet all firm loads at all times, but variable renewable plants do not have

firm levels of output because they are dependent on the weather. They are not firm resources

because there is no guarantee that the plant can generate at a specific load level at a given point in

time. 5 Variable renewable generation can be made firm by linking wind and solar plants to

electricity storage, but with current technology, storage options are limited and expensive.6

Capacity Factor

As discussed above, baseload units run more often than cycling units, and peaking units operate

the least often. The utilization of a generating unit is measured by its “capacity factor.” This is the

ratio of the amount of power generated by a unit for a period of time (typically a year) to the

maximum amount of power the unit could have generated if it operated at full output, non-stop.

For example, the maximum amount of power a 1,000 megawatt (MW) unit can generate in a year

is 8.76 million megawatt-hours (Mwh), calculated as:

1,000 MW x 8,760 hours in a year = 8.76 million Mwh.

3

A combustion turbine is an adaption of jet engine technology to electric power generation. A combustion turbine can

either be used stand-alone as a peaking unit, or as part of a more complex combined cycle plant used to meet

intermediate and baseload demand.

4

This alignment of generating technologies is for new construction using current technology. The existing mix of

generating units in the United States contains many exceptions to this alignment of load to types of generating plants,

due to changes in technology and economics. For instance, there are natural gas and oil-fired units built decades ago as

baseload stations that now operate as cycling or peaking plants because high fuel prices and poor efficiency has made

them economically marginal Some of these older plants were built close to load centers and are now used as reliability

must-run (RMR) generators that under certain circumstances must be operated, regardless of cost, to maintain the

stability of the transmission grid.

5

Hydroelectric generation is a special case. Hydro generation is very low cost and is firm, dispatchable capacity to the

degree there is water in the dam’s reservoir. However, operators have to consider not only how much water is currently

available, but how much may be available in upcoming months, and competing demands for the water, such as drinking

water supply, irrigation, and recreation. These factors make hydro dispatch decisions very complex. In general hydro is

used to meet load during high demand hours, when it can displace expensive peaking and cycling units, but if hydro is

abundant it can also displace baseload coal plants.

6

For example, a solar project developer decided to leave storage and other “extras” out of a proposed plant in order to

make it “commercially viable.” “Storage: Solar Power’s Next Frontier,” Platts Global Power Report, November 1,

2007.

Congressional Research Service

4

Power Plants: Characteristics and Costs

If this unit actually produced only 4.0 million Mwh its capacity factor would be 46% (calculated

as 4.0 million Mwh divided by 8.76 million Mwh).

Note in this calculation the distinction between capacity and energy. Capacity is the potential

instantaneous output of a generating unit, measured in watts.7 Energy is the actual amount of

electricity generated by a power plant during a time period, measured in watt-hours. The units are

usually expressed in thousands (kilowatts and kilowatt-hours) or millions (megawatts and

megawatt-hours).

The difference between actual and theoretical maximum output is caused by planned

maintenance, mechanical breakdowns (forced outages), and any instances in which the plant is

backed-down from maximum output due to lack of load or because the plant’s power is more

expensive than that from other plants. It is rare for a plant to have a capacity factor of 100%.

Baseload plants typically have capacity factors of about 70% or greater, peaking plants about

25% or less, and cycling plants fall in the middle.

Utility Scale Generating Technologies

The types of generating technologies discussed in this report are often referred to as “utility

scale” plants for baseload or intermediate service. These technologies generate large amounts of

electricity at a single site for transmission to customers. In 2006, large baseload and intermediate

service power plants accounted for about 86% of total power generation in the United States.8

Utility scale plants typically have generating capacities ranging from dozens to over a thousand

megawatts.

The one smaller scale generating technology covered in this report is solar photovoltaic power.

The capacity of the largest U.S. central station solar photovoltaic plant, at Nellis Air Force Base

in Nevada, is only 14 MW. Because of their small size, high capital costs, and low utilization

rates, solar photovoltaic plants built with current technology have very high electricity production

costs. Central station solar photovoltaic power is nonetheless included in the cost analysis

because of public interest.

The report excludes peaking plants, which play an important but small role in the power system.

The report also excludes oil-fired generation, which has all but disappeared from the nation’s

generating mix because of the high cost of the fuel. In 1978, oil-fired plants produced 22% of the

7

There are different measures of capacity. Nameplate capacity is the nominal maximum output of a generator, and

gross capacity is the actual maximum output. Net capacity is gross output minus the electricity needed to operate the

plant. Net capacity is therefore the amount of capacity that can actually put electric power on the grid. Net capacity can

vary with air and water temperatures, so a further distinction is made between summer and winter net capacity.

Capacity factor is most commonly computed using net summer capacity.

8

The estimate of 86% of 2006 generation from large baseload and intermediate generating units was computed from

the EIA-860 (generating capacity) and EIA-906/920 (generation) data files for 2006, available at

http://www.eia.doe.gov/cneaf/electricity/page/data.html. The calculation assumed that plants with a capacity factor of

25% or greater fall into the intermediate/baseload category, and that plants with a capacity of 200 MW or greater are

“large.” These thresholds are assumptions because there are no official categorizations of what constitutes intermediate,

baseload, or large power plants. However, large changes to the threshold values do not change the conclusion. For

example, if the capacity factor floor for what constitutes intermediate/baseload generation is increased to 33%, the

intermediate/baseload percentage of generation is 83%; if the size threshold is increased to 300 MW, the

intermediate/baseload percentage of generation is also 83%; and if both changes are made the intermediate/baseload

percentage of generation is 81%.

Congressional Research Service

5

Power Plants: Characteristics and Costs

nation’s electricity. By 2007 the oil-fired share was less than 2%.9 Significant construction of new

oil-fired plants is not expected.

The report also does not cover combined heat and power (CHP) plants. These are typically

industrial plants that co-produce electricity and steam for internal use and for sale. Unlike plants

that generate power exclusively to put electricity on the grid, CHP facilities have unique, plantspecific operating modes and cost structures, and economics fundamentally different from utility

scale generation. CHP generation is a small part of the electric power industry, accounting for

about 3.7% of total electricity output in 2007.10 Hydropower is excluded because no significant

construction of new, large hydroelectric plants is expected (due to environmental concerns and

the small number of available sites).11

The cost analysis is for plants entering service on January 1, 2015, which means construction

would start soon (between 2009 and 2013 depending on the technology). The plants therefore

incorporate only small projected changes from 2008 cost and performance for mature

technologies, and reflect current estimates of cost and performance for new or evolving

technologies (such as advanced nuclear power and coal gasification).

The technologies covered in the report are described briefly below. Process diagrams and images

of each technology are in Appendix A.

Supercritical Pulverized Coal

Pulverized coal plants account for the great majority of existing and planned coal-fired generating

capacity. In this system coal is ground to fine power and injected with air into a boiler where it

ignites. Combustion heat is absorbed by water-carrying tubes embedded in the boiler walls and

downstream of the boiler. The heat turns the water to steam, which is used to rotate a turbine and

produce electricity. Since about 2000 most plans for new pulverized coal plants have been for

“supercritical” designs that gain efficiency by operating at very high steam temperatures and

pressures.

In 2007, coal generation of all types12 accounted for 49% of total power generation in the United

States (see Figure 2).

9

Generation from petroleum products dropped from 365.1 billion kilowatt-hours (kWh) in 1978 to 65.7 billion kWh in

2007. Almost a quarter of the 2007 petroleum generation came not from liquid fuels, such as distillate fuel oil, but from

a solid refinery waste product, petroleum coke. EIA, Annual Energy Review 2006, Table 8.2a, and Electric Power

Monthly, March 2008, Table ES1.B.

10

In 2007 total generation was 4,160 million Mwh. Generation from the industrial and commercial sectors totaled 154

million Mwh, some of which was from non-CHP industrial and commercial generators. EIA, Annual Energy Review

2007, Table 8.1.

11

North American Electric Reliability Corp., 2008 Long-Term Reliability Assessment, October 2008, p. 46.

12

The primary alternative to pulverized coal technology for new coal plants is the circulating fluidized bed (CFB)

boiler. CFB is a commercial system used mainly for relatively small scale plants (about 250 MW and less) that burn

waste products (such as petroleum coke, a refinery residue) as well as coal. CFB is currently a niche technology and is

not covered further in this report. For additional information see Steve Blankinship, “CFB: Technology of the Future?,”

Power Engineering, February 2008. (The article is available online by searching at http://pepei.pennnet.com/).

Congressional Research Service

6

Power Plants: Characteristics and Costs

Figure 2.Total U.S. Electric Power Generation by Energy Source, 2007

Sources: EIA, Electric Power Monthly March 2008, Table ES1.B, and the EIA906/923 preliminary data file for 2007.

Integrated Gasification Combined Cycle (IGCC)

In this process coal is converted to a “synthesis gas” (syngas) before combustion. IGCC plants are

more expensive to build than pulverized coal generation, but proponents believe they have

compensating advantages, including:

•

Lower emissions of air pollutants, such as sulfur dioxide (SO2), nitrogen oxides

(NOx), and mercury. However, modern pulverized coal plants also have low

emissions of air pollutants, so the advantage of IGCC plants over conventional

technology is limited.

•

Greater efficiency (i.e., a lower heat rate), although with current technology

IGCC has only a small efficiency advantage over conventional coal plants.13

•

The syngas that results from the gasification process can be processed to convert

the carbon in the gas into a concentrated stream of carbon dioxide (CO2). The

syngas can then be processed, before it is burned, to remove the CO2.

In principle this pre-combustion capture of CO2 can be accomplished more easily and cheaply

than post-combustion removal of CO2 from the exhaust gases (“flue gas”) emitted by a

13

EIA estimates a heat rate advantage of 4.7% for current technology. With projected improvements the difference

widens substantially, to almost 15%. EIA, Assumptions to the Annual Energy Outlook 2008, Table 38. Another study is

less optimistic, finding that IGCC “electricity generating efficiencies demonstrated to date do not live up to earlier

projections due to the many engineering design compromises that have been made to achieve acceptable operability

and cost. The current IGCC units have and next-generation IGCC units are expected to have electricity generating

efficiencies that are less than [i.e., worse than] or comparable to those of supercritical P[ulverized] C[oal] generating

units.” Massachusetts Institute of Technology (MIT), The Future of Coal, 2007, p. 124.

Congressional Research Service

7

Power Plants: Characteristics and Costs

conventional coal plant. The promise of more efficient carbon capture is one of the primary

rationales for IGCC technology.

Coal-fired IGCC experience in the United States is limited to a handful of research and prototype

plants, none of which is designed for carbon capture. A commercial IGCC plant is being

constructed by Duke Energy at its Edwardsport site in Indiana, and other projects have been

proposed. However, some other power plant developers will not build IGCC plants because of

concerns over cost and the reliability of the technology.14 In general, the cost and operational

advantages of IGCC over conventional coal technology and the commercial readiness of IGCC

technology are disputed.15

Natural Gas Combined Cycle

Combined cycle plants are built around one or more combustion turbines, essentially the same

technology used in jet engines. The combustion turbine is fired by natural gas to rotate a turbine

and produce electricity. The hot exhaust gases from the combustion turbine are captured and used

to produce steam, which drives another generator to produce more electricity. By converting the

waste heat from the combustion turbine into useful electricity the combined cycle achieves very

high efficiencies, with heat rates below 7,000 btus per kWh (compared to around 9,000 btus per

kWh for new pulverized coal plants). This high efficiency partly compensates for the high cost of

the natural gas used in these plants.

Modern combined cycle plants, which evolved in the 1990s, have a relatively low construction

cost and modest environmental impacts; can be used to meet baseload, intermediate, and peaking

demand; can be built quickly; and are very efficient. Because of these advantages, since 1995

natural gas combined cycle plants have accounted for 88% of the all the new generating capacity

built in the United States capable of baseload and intermediate service. 16

Natural gas combined cycle plants and other types of gas-fired power plants are expected to

continue to dominate capacity additions into the next decade. 17 According to EIA, combined cycle

14

For instance, LS Power, a coal project developer, describes IGCC technology as “experimental.” Steve Raabe,

“‘Clean Coal’ Plant Setbacks Mount in U.S.,” The Denver Post, November 1, 2007.

15

For example, Appalachian Power (APCo, a subsidiary of the large utility American Electric Power) has proposed

building an IGCC plant to serve customers in Virginia and West Virginia. The Virginia State Corporation Commission

rejected the proposal, citing the technical immaturity and uncertain costs of IGCC technology. The same project was

approved by the West Virginia Public Service Commission, which concluded that “the Project is an efficient and

capable proposal to meet the baseload needs of APCo’s customers” and is the “best option” available to APCo.

(Virginia State Corporation Commission, Application of Appalachian Power Co., Case No. PUE-2007-0068, Final

Order, April 14, 2008, pp. 12-13; West Virginia Public Service Commission, Application for a Certificate of Public

Convenience and Necessity, Case No. 06-0033-E-CN, Commission Order, March 6, 2008, p. 25.)

16

According to the 2006 version of the EIA-860 data file of generating units, between 1995 and 2006, inclusive,

255,980 MW of new generating capacity of all types entered service. Out of this total, 168,800 MW used generating

technologies suitable for baseload and intermediate service, including geothermal, combined cycle, fuel cell,

hydroelectric, steam turbines using combustible fossil or renewable fuels, and wind turbines. Of this

baseload/intermediate segment, 148,119 MW was gas-fired combined cycles, or 88%. The next largest shares were

wind power (6%) and coal (4%).

17

EIA, Annual Energy Outlook 2008, p. 68; Matthew Wald, “Utilities Turn From Coal to Gas, Raising Risk of Price

Increases,” The New York Times, February 5, 2008; “FERC’s Moeler Just Wants to Make it Clear: Natural Gas ‘Fuel of

Choice’ in the Near Future,” Platts Electric Utility Week, October 22, 2007; Alexander Duncan, “Power Needs,

Climate Concerns to Spark ‘Bullish’ Natural Gas Market: Experts,” Platts Inside Energy, October 8, 2007.

Congressional Research Service

8

Power Plants: Characteristics and Costs

plants will account for 29% of all capacity additions between 2008 and 2015.18 However, this

forecast may understate actual combined cycle plant additions. The EIA estimates that coal plants

will account for almost a quarter of new capacity built through 2015, the equivalent of about 170

new coal-fired generating units.19 It is questionable whether this much coal capacity will actually

be built because of public opposition to new coal plants and the cost of the plants. Utilities

reportedly canceled 16,577 MW of planned generating capacity in 2007, of which 84% was coalfired.20 According to a Department of Energy (DOE) report, only 12% (4,500 MW) of the coal

capacity planned in 2002 to be built by 2007 was actually constructed. The report notes that

“delays and cancellations have been attributed to regulatory uncertainty (regarding climate

change) or strained project economics due to escalating costs in the industry.”21

If less coal capacity is built than planned, the main replacement is likely to be combined cycle

plants, the type of gas-fired unit capable of replacing a baseload coal plant. For example, in 2007,

power generators in Florida planned to install 4,627 MW of new coal fired capacity through

2016. By 2008 the plans for new coal-fired capacity had dropped to 738 MW, primarily “due to

environmental concerns at the State level. The majority of this decrease in planned coal-fired

generation was replaced with gas-fired units.”22

Natural gas combined cycle plants accounted for 17% of total generation in 2007,23 and natural

gas plants of all types accounted for 21% of total power generation in the United States (Figure

2).

Nuclear Power

Nuclear power plants use the heat produced by nuclear fission to produce steam. The steam drives

a turbine to generate electricity. Nuclear plants are characterized by high investment costs but low

variable operating costs, including low fuel expense. Because of the low variable costs and design

factors, nuclear plants in the United States operate exclusively as baseload plants and are

typically the first plants in a power system’s dispatch order. Nuclear power supplied 19% of the

nation’s electricity in 2007 (Figure 2).

This report discusses projected costs for Generation III/III+ technology nuclear plants. These

plants are more advanced versions of the 104 reactors currently operating in the United States,

and all reactors currently proposed for construction in the United States are Generation III/III+

designs. Compared to existing reactors, the Gen III/III+ plants are designed to reduce costs and

enhance safety through, for example, reduced complexity, standardized designs, and improved

construction techniques. Some designs also incorporate passive safety systems that are supposed

to be capable of preventing a catastrophic accident even without operator action.

18

Calculated from the Annual Energy Outlook 2008 output spreadsheet. EIA projects that natural gas-fired combined

cycle plants plus natural gas combustion turbine peaking plants will account for 54% of capacity additions through

2015.

19

Ibid. EIA projects the construction of 85,300 MW of new coal fired capacity.

20

Rebecca Smith, “Banks Hope to Expand Carbon Rules to Public Utilities,” The Wall Street Journal, March 20, 2008.

21

DOE/NETL, Tracking New Coal-Fired Power Plants, June 2008, p. 5. This report is periodically updated and posted

at http://www.netl.doe.gov/coal/refshelf/ncp.pdf.

22

North American Electric Reliability Corp., 2008 Long-Term Reliability Assessment, October 2008, p. 88.

23

According to the EIA-906/920 data file for 2007, gas-fired combined cycles accounted for 688 million megawatthours of generation, out of a total of 4,160 million megawatt-hours.

Congressional Research Service

9

Power Plants: Characteristics and Costs

There are several competing Gen III/III+ designs,24 but only one design has been built (General

Electric’s Advanced Boiling Water Reactor, of which four units have been constructed in Japan).

Plants based on other Gen III/III+ designs are under construction in France, Finland, and China.

As discussed later in the report, the costs of building a new nuclear plant in the United States will

apparently be very high.

Geothermal Power

Geothermal plants have operated for many years in the western United States, mainly in

California. In a typical binary cycle geothermal facility, wells draw hot water and steam from

underground into a heat exchanger. In the heat exchanger a working fluid is vaporized and used to

drive a turbine generator (the underground steam is not used directly because it contains corrosive

impurities and can release air pollutants). In geothermal fields that have been depleted by years of

use, such as the Geysers field in California, operators can inject water into the layers of hot rock

to supplement the naturally available water and boost steam production. Unlike solar and wind

power, which are weather-dependent, geothermal plants operate as dispatchable baseload plants.

However, with current technology, geothermal plants are limited to small facilities (typically

under 50 MW) at sites in the western United States.25 In 2007, geothermal plants produced 0.4%

of the nation’s power supply (Figure 2).26

Wind Power

Wind power plants (sometimes referred to as wind farms) use wind-driven turbines to generate

electricity. An individual turbine typically has a capacity in the range of 1.5 to 2.5 MW, and a

wind plant installs dozens or hundreds of these turbines. As noted above, wind is a variable

renewable resource because its availability depends on the vagaries of the weather. Wind supplied

1% of total U.S. power supply in 2007 (Figure 2); EIA estimates that assuming no changes to

current law and regulation, this will increase to 2.4% by 2030.27

Solar Thermal and Solar Photovoltaic (PV) Power

Solar thermal and PV power are alternative means of harnessing sunlight to produce electricity.

PV power uses solar cells to directly convert sunlight to electricity. To date most of the solar PV

installations in the United States have been small (about one MW or less). Two exceptions are the

installations at Nellis Air Force Base in Nevada (14 MW) and the Alamosa Photovoltaic Power

Plant in Colorado (8 MW).

24

For an illustrated summary of several of the Gen III/III+ designs, see “UK Nuclear Power: The Contenders,” BBC

News, January 10, 2008 http://news.bbc.co.uk/2/hi/science/nature/5165182.stm. Additional information is available

from the links at http://www.nei.org/keyissues/newnuclearplants/newreactordesigns/.

25

As of August 2008, a reported 95 geothermal projects with publicly known generating capacities were in

development in the United States. The upper estimate of the total capacity of these projects was 3,959.7 MW, or an

average of 42 MW per project. All the projects are located in western states except for a single 1 MW project in

Florida. Kara Slack, U.S. Geothermal Power Production and Development Update, Geothermal Energy Association,

August 2008, p. 8.

26

For additional information on geothermal power see Steve Blankinship, “What Lies Beneath,” Power Engineering,

January 2007, available by searching http://pepei.pennnet.com/).

27

EIA, Annual Energy Outlook 2008, p. 70. For more detail on wind power, see CRS Report RL34546, Wind Power in

the United States: Technology, Economic, and Policy Issues, by (name redacted) and (name redacted).

Congressional Research Service

10

Power Plants: Characteristics and Costs

Solar thermal plants, also referred to as concentrated solar power (CSP), concentrate sunlight to

heat a working liquid to produce steam that drives a power-generating turbine. Two major types

of solar thermal systems are parabolic trough and power tower technologies. Parabolic trough

plants use an array of mirrors to focus sunlight on liquid-carrying tubes integrated with the

mirrors. Several parabolic trough installations have operated successfully in California since the

1980s, and the 64 MW Nevada Solar One plant began operating in 2007.

The power tower technology uses a mirror field to focus sunlight on a central tower, where the

heat is used to produce steam for power generation. A research power tower, the Solar One/Two

plant, operated for several years in the 1980s and 1990s in California. A power tower plant has

recently been constructed in Spain and a 400 MW project has been proposed for California.

Several new solar thermal projects, primarily of the parabolic trough and related types, are in

development. The capacity of these projects range up to 554 MW. A potential advantage of solar

thermal systems is the ability to produce electricity when sunlight is weak or unavailable by

storing solar heat in the form of molten salt. If storage proves economical for large-scale plants,

then solar thermal facilities in regions with strong, near continuous daytime sunlight, such as the

Mojave desert, could be operated as dispatchable plants with firm capacity.

In 2007, solar thermal generation accounted for 0.01% of total generation, and solar PV power for

less (Figure 2).

Factors that Drive Power Plant Costs

This section of the report discusses the major factors that determine the costs of building and

operating power plants. These factors include:

•

Government incentives.

•

Capital (investment) cost, including construction costs and financing.

•

Fuel costs.

•

Air emissions controls for coal and natural gas plants.

Government Incentives

Many government incentives influence the cost of generating electricity. In some cases the

incentives have a direct and clear influence on the cost of building or operating a power plant,

such as the renewable investment tax credit. Other programs have less direct affects that are

difficult to measure, such as parts of the tax code that influence the cost of producing fossil fuel.28

The economic analysis in this report incorporates the following incentives that directly affect the

cost of building or operating power plants.29

28

For a comprehensive list of energy market incentives, see EIA, Federal Financial Interventions and Subsidies in

Energy Markets 2007, April 2008.

29

The analysis does not include the credit for carbon dioxide sequestration established by P.L. 110-343, Division B,

Title I, Subtitle B, Section 115 (adding a new §45Q to 26 U.S.C.). The law provides for tax credits of $20 per metric

(continued...)

Congressional Research Service

11

Power Plants: Characteristics and Costs

Renewable Energy Production Tax Credit30

The credit has a 2008 value of 2.0 cents per kWh, with the value indexed to inflation. The credit

applies to the first 10 years of a plant’s operation. As of October 2008 the credit is available to

plants that enter service before the end of 2009. The credit is currently available to new wind,

geothermal, and several other renewable energy sources. New solar energy projects do not

qualify, and geothermal projects can take the production tax credit only if they do not use the

renewable investment tax credit (discussed below).

Nuclear energy production tax credit31

The credit, which is for new advanced nuclear plants, has a nominal value of 1.8 cents per kWh.

The credit applies to the first eight years of plant operation. Unlike the renewable production tax

credit the nuclear credit is not indexed to inflation and therefore drops in real value over time.

This credit is subject to several limitations:

•

It is available to advanced (i.e., Gen III/III+) nuclear plants that begin

construction before January 1, 2014, and enter service before January 1, 2021.

•

For each project the annual credit is limited to $125 million per thousand

megawatts of generating capacity.

•

The full amount of the credit will be available to qualifying facilities only if the

total capacity of the qualifying facilities is 6,000 megawatts or less. If the total

qualifying capacity exceeds 6,000 megawatts the amount of the credit available

to each plant will be prorated. EIA estimates in its 2008 Annual Energy Outlook

that 8,000 megawatts of new nuclear capacity will qualify;32 in this case the

credit amount would drop to 1.35 cents per kWh once all the qualifying plants

are on-line. This pro-rated value is used in the report’s economic analysis of

generating costs.

Loan Guarantees for Nuclear and Other Carbon-Control Technologies33

Under final Department of Energy (DOE) rules the loan guarantees can cover up to 80% of the

cost of a project, and are awarded based on a detailed evaluation of each applicant project.

Entities receiving loan guarantees must make a “credit subsidy cost” payment to the federal

(...continued)

ton of CO2 sequestered and $10 per metric ton for CO2 captured and used for enhanced oil recovery. The credit is in

effect through the year in which the cumulative volume of CO2 captured totals 75 million metric tons. This credit is

excluded because it is very difficult to predict how long the credit will be in effect. The EIA analysis of the LiebermanWarner Climate Security Act of 2009 (S. 2191) estimates, for the cases that project carbon capture, cumulative CO2

capture of about 80 million to 100 million tons by 2014, which is prior to the on-line data of 2015 assumed for new

power plants in this study. (For the spreadsheets which contain the detailed S. 2191 outputs, see the EIA website at

http://www.eia.doe.gov/oiaf/servicerpt/s2191/index.html.)

30

26 U.S.C. §45, as amended by P.L. 110-343, Division B, Title I, Subtitle A, Section 101(a).

31

26 U.S.C. §45J.

32

For a discussion of the operation of the credit see EIA, Annual Energy Outlook 2007, p. 21. For the forecast of 8,000

MW of nuclear capacity on-line before 2021, see the Annual Energy Outlook 2008, p. 70.

33

10 CFR § 609 (RIN 1901-AB21), October 4, 2007 http://www.lgprogram.energy.gov/keydocs.html.

Congressional Research Service

12

Power Plants: Characteristics and Costs

treasury that reflects the anticipated cost of the guarantee to the government, including a

probability weighted cost of default. Because the debt is backed by the federal government, it is

expected to carry the highest credit rating and therefore a low interest rate.34 The guarantees are

unavailable to publicly owned utilities, such as municipal systems.35

Congress periodically determines the total value of the guarantees that the DOE is authorized to

grant. In April 2008, the Department of Energy announced plans to solicit up to $18.5 billion in

loan guarantee applications for nuclear projects.36 As of November 2008, DOE was considering

several applications for loan guarantees.

Developers and investors have stated that the loan guarantees are critical to constructing at least

the first wave of new nuclear plants. This is because of the multi-billion dollar cost of a nuclear

project, which can exceed the total market value of the company building a plant. For example, in

2008 the president of Exelon Generation, which operates a large fleet of existing nuclear plants

and plans to build new units, stated that constructing new nuclear plants would be “impossible”

without loan guarantees.37

Energy Investment Tax Credit38

Tax credits under this program are available to solar and geothermal electricity generation, and

some other innovative energy technologies. Wind energy systems do not qualify. The credit is

10% for geothermal systems, and is 30% for solar electric systems installed before January 1,

2017 (after which it reverts to 10%). Geothermal projects that take the investment tax credit

cannot claim the renewable production tax credit.39 The depreciable basis of the project for tax

purposes is reduced by 50% of the credit value. The investment tax credit is available to

34

On the assumption that the guaranteed debt would have a high (AAA) rating, see “Loan Guarantees for Projects that

Employ Innovative Technologies,” 10 CFR § 609 (RIN 1901-AB21), October 4, 2007, p. 24.

35

Entities receiving loan guarantees must make a substantial equity contribution to the project’s financing. Public

power entities normally do not have the retained earnings needed to make such payments. The rules also preclude

granting a loan guarantee if the federal guarantee would cause what would otherwise be tax exempt debt to become

subject to income taxes. Under current law this situation would arise if the federal government were to guarantee public

power debt. For further information on these and other aspects of the loan guarantee program see U.S. DOE, final rule,

“Loan Guarantees for Projects that Employ Innovative Technologies,” 10 CFR § 609 (RIN 1901-AB21), October 4,

2007 http://www.lgprogram.energy.gov/keydocs.html.

36

DOE Announces Plans for Future Loan Guarantee Solicitations, Department of Energy press release, April 11, 2008.

According to press reports, the Japanese and French governments may also offer loan guarantees to American nuclear

projects. French and Japanese companies are expected to be major suppliers to new U.S. nuclear projects. The terms of

the loan guarantees, assuming they come to fruition, are unknown. Elaine Hiruo, “Japanese Government Considers

Loan Guarantees for U.S. Reactors,” Platts Nucleonics Week, August 14, 2008, and Elaine Hiruo, “Japan Clears Way

for Loan Guarantees in US,” Platts Nucleonics Week, September 25, 2008.

37

Steven Dolley, “Nuclear Power Key to Exelon’s Low-Carbon Plan,” Platts Nucleonics Week (February 14, 2008).

For similar comments see “House Appropriators Seek DOE Loan Guarantees Delay Pending GAO Review,”

EnergyWashington.com, June 10, 2008; Dr. Joe C. Turnage, UniStar Nuclear, presentation to the California Energy

Commission, “New Nuclear Development: Part of the Path Toward a Lower Carbon Energy Future,” June 28, 2007;

and Selina Williams, “US Government Loan Guarantees For New Nuclear Too Small NRC,” CNNMoney.com, March

10, 2008.

38

26 U.S.C. §48, as amended by P.L. 110-343, Division B, Title I, Subtitle A, Section 103(a)(1).

39

For additional information see the discussion of the investment tax credit in the federal incentives section of the

Database of State Incentives for Renewable Energy website http://www.dsireusa.org/.

Congressional Research Service

13

Power Plants: Characteristics and Costs

independent power producers and investor owned utilities, but is inapplicable to tax-exempt

publicly owned utilities.40

Clean Coal Technologies Investment Tax Credit41

This tax credit can be used by investor owned utilities or independent power producers (it is

inapplicable to tax-exempt publicly owned utilities). It is limited to a total of $2.55 billion in tax

credits, of which (1) $0.8 billion is specifically for IGCC plants; (2) $0.5 billion is for non-IGCC

advanced coal technologies, and (3) $1.25 billion is for advanced coal projects generally. The tax

credits in the third category will not be awarded until after the program that encompasses the first

two categories of tax credits is completed or until such other date designated by the Secretary of

Energy.42 The depreciable basis of a project for tax purposes is reduced by 50% of the credit

value.

State and Local Incentives

State and local governments can offer additional incentives, such as property tax deferrals. The

combined value of the government tax breaks can run into the hundreds of millions of dollars per

project. For example, Duke Energy’s Edwardsport IGCC project in Indiana is expected to receive

almost half-a-billion dollars in federal, state, and local tax incentives. 43

State utility commissions can use rate treatment of new plants as a financial incentive for the

investor owned utilities they regulate. Under traditional rate making a utility is not permitted to

earn a return on its construction investment until a plant is in service. This approach to

ratemaking is used to motivate the utility to prudently manage construction, and to ensure that

customers do not have to pay for a power plant until it is operating. However, if a project is very

expensive, the time lag between when costs are incurred and when return on the investment is

allowed in rates can put a financial strain on the company. If the plant is expensive, adding the

return into rates as a single big adjustment can inflict “rate shock” on customers.

For these reasons, utilities sometimes argue for an alternative rate making method called

“construction work in progress (CWIP) in rates.” In this approach, a utility is allowed to recover

in rates the return on its investment as the plant is being built. CWIP in rates relieves the utility of

the financial strain of carrying an expensive investment that is yielding no income, phases-in the

rate increase to customers, and decreases the utility’s financial exposure if the project is delayed.

On the other hand, the pressures for prudent construction management inherent in traditional

ratemaking are dampened.

40

Investor owned utilities did not qualify for this credit until the passage of P.L. 110-343 in October 2008. See P.L.

110-343, Division B, Title I, Subtitle A, Sections 103(e) and 103(f)(4).

41

26 U.S.C. §48A, as amended by P.L. 110-343, Division B, Title I, Subtitle B, Section 111.

42

The IGCC credit is 20% capped at $133.5 million per project, with a requirement that the credits be allocated to

projects in each of three categories: Bituminous coal-fired, subbituminous coal-fired, and lignite-fired plants. Other

advanced coal technologies can qualify for a 15% credit (with a cap of $125 million per project) if 1) a new unit can

achieve a heat rate of 8,530 btus/kWh or less and near zero non-CO2 emissions, or 2) an existing plant can meet various

criteria for improving thermal efficiency, including by replacing inefficient old units at a plant site with new units.

43

“Consumers Energy Latest to Win Tax Concessions,” Platts Electric Power Daily, November 29, 2007.

Congressional Research Service

14

Power Plants: Characteristics and Costs

Some states, such as South Carolina and Mississippi, have passed legislation allowing utility

projects that meet certain criteria to receive CWIP in rates.44 In other cases utilities have received

CWIP in rates under existing rules. CWIP in rates has expanded beyond its historic application to

very expensive coal and nuclear projects. For example, the Kansas and Wisconsin commissions

have allowed CWIP in rates for relatively small wind projects.45

Capital and Financing Costs

Construction Cost Components and Trends

Most of the generating technologies discussed in this report are capital intensive; that is, they

require a large initial construction investment relative to the amount of generating capacity built.

Power plant capital costs are often discussed in terms of dollars per kilowatt (kW) of generating

capacity. All of the technologies considered in this report have estimated 2008 costs of $2,100 per

kW or greater, with the exception of the natural gas combined cycle plant ($1,200 see Appendix

B). Nuclear, geothermal, and IGCC plants have estimated costs in excess of $3,000 per kW.

Power plant capital costs have several components. Published information on plant costs often do

not clearly distinguish which components are included in an estimate, or different analysts may

use different definitions. The capital cost components are:

•

Engineering, Procurement, and Construction (EPC) cost: this is the cost of the

primary contract for building the plant. It includes the cost of designing the

facility, buying the equipment and materials, and construction.46

•

Owner’s costs: these are any construction costs that the owner handles outside

the EPC contract. This could include arranging for the construction of

transmission and fuel delivery facilities (such as a natural gas pipeline) to a

power plant.

•

Capitalized financing charges: a plant developer incurs financing charges while a

power plant is being built. This includes interest on debt and an imputed cost of

equity capital. Until the plant is operating these costs are capitalized; that is,

44

Mary Powers, “Governor Expected to Sign Mississippi Bill on Collecting Costs of Building Baseload,” Platts

Electric Utility Week, April 21, 2008; Elaine Hiruo and Tom Harrison, “Summer Owners Lock in Price, Schedule for

Planned New Reactors,” Platts Nucleonics Week, May 29, 2008. In addition, Florida, Louisiana, Virginia, and North

Carolina will reportedly allow return on CWIP for nuclear plants (Dr. Joe C. Turnage, UniStar Nuclear, “New Nuclear

Development: Part of the Strategy for a Lower Carbon Energy Future,” presentation to the Center for Strategic and

International Studies meeting “Evaluating the Business Case for Nuclear Power,” July 31, 2008, p. 4). The treatment of

CWIP in rates varies by jurisdiction and by case. The amount of CWIP allowed is typically updated periodically and

may be limited by a total project cost approved by the commission.

45

Wisconsin Public Service Commission, Certificate and Order, Docket 6680-CE-171, May 10, 2007 (for Wisconsin

Power & Light’s Cedar Ridge project, estimated to cost $179 million); Kansas State Corporation Commission, Final

Order, Docket 08-WSEE-309-PRE, December 27, 2007 (for Westar Energy’s investment in the Central Plains and Flat

Ridge wind projects, estimated to cost the utility $282 million).

46

Typical practice is for the project developer to enter into a single EPC contract with a large construction and

engineering firm. The firm is responsible for most plant construction activities and absorbs significant cost, delay, and

technical risk, which is reflected in the contract price. A developer can act as its own EPC manager and avoid paying

the risk premium to a third party contractor, but in this case the developer absorbs the price and performance risks.

Congressional Research Service

15

Power Plants: Characteristics and Costs

become part of the investment cost of the project for tax, regulatory, and financial

analysis purposes (see further discussion of financing costs, below).

Construction costs for power plants have escalated at an extraordinary rate since the beginning of

this decade. According to one analysis, the cost of building a power plant increased by 131%

between 2000 and 2008 (or by 82% if nuclear plants are excluded from the estimate). Costs

reportedly increased by 69% just since 2005. The cost increases affected all types of generation.

For example, between 2000 and 2008, the cost of wind capacity reportedly increased by 108%,

coal increased by 78%, and gas-fired plants by 92%.47 The cost increases have been attributed to

many factors, including:

•

High prices for raw and semi-finished materials, such as iron ore, steel, and

cement.

•

Strong worldwide demand for generating equipment. China, for example, is

reportedly building an average of about one coal-fired generating station a

week. 48

•

Low value of the dollar.

•

Rising construction labor costs, and a shortage of skilled and experienced

engineering staff.49

•

An atrophied domestic and international industrial and specialized labor base for

nuclear plant construction and components.

•

In the case of wind, competition for the best plant sites and a tight market for

wind turbines; in the case of nuclear plants, limited global capacity to produce

large and ultra-large forgings for reactor pressure vessels.50

•

Coincident worldwide demand for similar resources from other business sectors,

including general construction and the construction of process plants such as

refineries. Much of the demand is driven by the rapidly growing economies of

Asia.51

The future trend in construction costs is a critical question for the power industry. Continued

increases in capital costs would favor building natural gas plants, which have lower capital costs

than most alternatives. Stable or declining construction costs would improve the economics of

capital-intensive generating technologies, such as nuclear power and wind. 52 At least some long47

IHS CERA press release, “Construction Costs for New Power Plants Continue to Escalate IHS-CERA Power Capital

Costs Index,” May 27, 2008 http://energy.ihs.com/News/Press-Releases/2008/IHS-CERA-Power-Capital-CostsIndex.htm.

48

Keith Bradsher and David Barboza, “Pollution From Chinese Coal Casts a Global Shadow,” The New York Times,

June 11, 2006.

49

Christopher D. Kirkpatrick, “A Bidding War for Engineers: Power Plant Construction Boom Creates a Labor

Shortage,” The Charlotte (North Carolina) Observer, September 5, 2008.

50

Yuliya Chernova, “Change in the Air,” The Wall Street Journal, February 11, 2008; Bert Caldwell, “BPA’s wind

power tops 1,000 megawatts,” The (Spokane, Washington) Spokesman-Review, January 12, 2008; Yoshifumi Takemoto

and Alan Katz, “Samurai-Sword Maker’s Reactor Monopoly May Cool Nuclear Revival,” Bloomberg.com, March 13,

2008.

51

Matthew L. Wald, “Costs Surge For Building Power Plants,” The New York Times, July 10, 2007.

52

Wind power is less costly to build than, for example, coal or nuclear plants. However, because wind plants are

weather dependent, wind plants have much lower capacity factors than coal or nuclear plants. A typical wind plant

(continued...)

Congressional Research Service

16

Power Plants: Characteristics and Costs

term moderation in cost escalation is likely, as demand growth slackens and new supply capacity

is added. 53 But when and to what degree cost increases will moderate is as unpredictable as the

recent cost escalation was unforeseen.

Financing Power Plant Projects

Even relatively small power plants cost millions of dollars. For example, the capital cost for a 50

MW wind plant would be about $105 million at $2,100 per kW of capacity. The investment cost

is typically financed by a combination of debt and equity.54 The financing structure and the cost

of money depends on the type of developer and project-specific risk.

Three types of entities typically develop power plants:

•

Investor-owned utilities (IOUs): IOUs are owned by private investors and are

subject to government regulation of rates and conditions of service. They have

guaranteed service territories and face limited competition. State utility

commissions set electric rates designed to maintain the financial health of the

utility, assuming it operates prudently. The commission also must approve

proposals by the utility to build new power plants.55

•

Publicly-owned utilities (POUs): A POU is a utility that is an agency of a

municipality, a state, or the federal government. Electric cooperatives are also

considered to be POUs. Like IOUs, POUs have guaranteed service territories and

face limited competition. Most POUs are small, provide only distribution service,

and have limited financial and management resources.56 But larger and some

smaller POUs also own and operate power plants, sometimes as co-owners of

projects where an IOU or independent power producer is the lead developer.

Examples of POUs with large amounts of generation include the Tennessee

Valley Authority and the municipal utilities serving the cities of Los Angeles and

(...continued)

capacity factor is about 34%, compared to 70% to over 90% for coal and nuclear plants. This means the capital costs of

a wind plant are spread over relatively few megawatt-hours of generation, increasing the cost per unit of electricity

sold. In the case of variable renewable resources like wind and solar power, anything that reduces capital costs or

increases utilization can significantly improve plant economics.

53

For example, vendors in Asia and Europe are planning to add new capacity to manufacture very large forgings,

particularly important for nuclear plants. Mark Hibbs, “Chinese Equipment Fabricators Set Ambitious Capacity

Targets,” Platts Nucleonics Week, May 22, 2008; Pearl Marshall, “UK’s Sheffield Forgemasters Plans to Produce

Ultra-large Forgings,” Platts Nucleonics Week, April 3, 2008.

54

Equity capital includes the funds provided by the owners of the firm (i.e., the stockholders). Debt is borrowed

money. The owners of a project seek to repay debt, and to both recover their equity investment and earn a return on that

investment.

55

Prior to the restructuring of the electric power industry that began in the 1990s, IOUs were typically vertically

integrated, providing generation, transmission, and distribution (final delivery of electricity to consumers) in a statesanctioned monopoly service area. With restructuring, some states required or encouraged utilities to divest their power

plants. In many parts of the country control (though not ownership) of transmission assets is now in the hands of

federally sponsored regional transmission organizations (RTOs). Some states that required IOUs to divest generation

are now allowing utilities to once again own and operate power plants, such as California.

56

In 2006, out of 2,010 government-owned electric utilities, only 98 had total revenues in excess of $100 million

dollars. In contrast, the fuel cost for a single large power plant can exceed $100 million per year. American Public

Power Association, 2008-09 Annual Directory and Statistical Report, p. 30 (data does not include electric

cooperatives).

Congressional Research Service

17

Power Plants: Characteristics and Costs

San Antonio. POUs set their own rates and make their own decisions to build

power plants.

•

Independent Power Producers (IPPs): IPPs are merchant developers and

operators of power plants that sell wholesale power to utility and industrial

buyers. Within limits they can sell power at whatever price the market will bear.57

IPPs face more financial risk than regulated utilities—they do not have

guaranteed service territories and can face intense competition for power sales—

but can also earn larger profits. IPPs make their own decisions to build power

plants.

All three types of entities play a major role in the electric power industry (Table 1). The lines

between the entities can blur. Holding companies that own IOUs can also own IPPs. POUs

sometimes own large shares of power projects developed by IOU or IPPs.

Table 1. Shares of Total National Electric Generation and Generating Capacity, 2006

Generation

Generating Capacity

Publicly-Owned Utilities

22%

21%

Investor-Owned Utilities

41%

38%

Non-Utilities

37%

41%

National Total

100%

100%

Source: American Public Power Association http://www.appanet.org/files/PDFs/nameplate2006.pdf, citing Energy

Information Administration.

Notes: Non-utility generation includes independent power producers and power marketers. Non-utility

capacity includes industrial and commercial facilities. Capacity shares are for nameplate capacity.

The cost of the money used to finance power projects varies significantly between IOU, POUs,

and IPPs. A POU will normally finance a project with 100% debt at a low interest rate. The rate is

low because interest paid on public debt is exempt from federal or state income taxes, 58 and

because public entities have a very low risk of default (failure to make debt payments), much

lower than for private businesses. 59 Typical municipal bonds have ratings in the middle or upper

tiers of investment grade debt.60

57

In some parts of the country RTOs operate power markets and have capped spot electricity prices, such as at $1,000

per Mwh, to prevent extraordinary price spikes. These caps apply to spot sales of electricity, not to bilateral contracts.

58

Because the debt is tax free, the POU can pay the bond holder a lower interest rate than taxable debt must offer. The

bond holder accepts the lower POU tax-free interest rate since, other things being equal, its after-tax return is the same.

59

Moody’s Investors Service, Mapping of Moody’s U.S. Municipal Bond Rating Scale to Moody’s Corporate Rating

Scale and Assignment of Corporate Equivalent Ratings to Municipal Obligations, June 2006, p.2. According to

Moody’s, between 1970 and 2000, out of 699 rated municipal bond issues for electric power, only two defaulted

(including the Washington Public Power Supply System default on a large nuclear construction program). Over the

same period, about 70% of municipal bonds were rated A or higher, and less than 1% were rated below investment

grade. Moody’s Investors Service, Moody’s US Municipal Bond Rating Scale, November 2002, pp. 5-6.

60

Moody’s Investors Service, Moody’s US Municipal Bond Rating Scale, November 2002, p. 6. Rating agencies assign

debt to credit worthiness categories. Investment grade debt has a rating of BBB- or higher in the nomenclature used by

Standard & Poors and Fitch. The equivalent category for Moody’s is Baa3 and higher. Lower rated debt is referred to

as speculative or high yield issues, or less pleasantly as “junk bonds.” For descriptions of the ratings systems and

crosswalks see Edison Electric Institute, 2007 Financial Review, p. 86, and http://www.nnnsales.com/faq/faqbuyersinvestors8.htm. Note that the municipal bond market was roiled by the 2008 financial crisis (Tom Herman,

(continued...)

Congressional Research Service

18

Power Plants: Characteristics and Costs

Privately owned IOUs and IPPs finance power projects with a mix of debt and equity. Debt is

more costly to these companies than to POUs because it is not tax exempt and because they

usually have lower credit ratings. The electric utility industry as a whole has a credit rating in the

lower tier of the investment grade category (BBB).61 IPP debt often falls in the speculative

category and has a higher interest rate than IOU or POU issues.62

Investors expect private developers to make a significant equity contribution to a project.63

Reliance on equity versus debt varies by company and project. The cost analysis used in this

study assumes that IPPs and IOUs rely on, respectively, 40% and 50% equity (see Table D-1),

except in the case where federal loan guarantees are available (see discussion of “Government

Incentives”, above). Equity is more expensive than debt,64 and is more expensive for IPPs than

IOUs because IPPs typically face more competition and financial risk.

In summary:

•

Because POUs can finance a power project with 100% low-cost debt they can

build power plants more cheaply than IOUs or IPPs. However, because of the

small size of most POUs they do not have the financial or management resources

to take on large and complex projects by themselves, so POUs often partner on

projects where an IOU or IPP is the lead developer.

•

IOU’s typically have lower financing costs than IPP’s because they have lower

costs of debt and equity. 65

(...continued)

“Muni Yields Rise to Rare Levels” The Wall Street Journal, November 5, 2008).

61

Roughly 70% of utility companies were rated between BBB+ and BBB- in 2007. About 10% were rated below

investment grade. Edison Electric Institute, 2007 Financial Review, pp. 81 and 87.

62

Most IPP debt is reportedly rated below investment grade (telephone conversation with Scott Solomon, Moody’s

Investors Service, February 15, 2008). For instance, in June 2008 the debt ratings for several large IPP developers were

all speculative grade: NRG (Standard & Poors B rating), AES (B+ to BB-), Edison Mission Energy (BB-), and Dynegy

(B-). (Source: Standard & Poors NetAdvantage on-line data system). IPP power plants may be project-financed; that is,

the financing and the recourse of the debt holders is tied to a specific project, not to the corporation as a whole. For

example, the LS Power Sandy Creek, AES Ironwood, and Calpine’s Riverside and Rocky Mountain projects all have

project-specific, speculative grade debt ratings. (Source: Moody’s Investors Service press releases, August 3, 2006,

August 14, 2007, and February 8, 2008.)

63

Over-reliance on debt is considered risky for private entities and leads investors to demand higher interest rates. At

some level of debt a project would be impossible to finance. POUs can rely on 100% debt financing because they

control their own rates and are backed-up by the government entity that owns or finances the utility.

64

Equity is more expensive than debt in part because interest payments on debt are tax deductible while the imputed

cost of equity is not an expense for income tax purposes. Another consideration is that in the event of bankruptcy

bondholders are paid before shareholders. An equity investment is therefore riskier than holding debt and investors

demand higher compensation. (Unlike a bond which has a known interest rate, there is no directly measurable cost of

equity. Its cost is essentially the return investors will expect on their equity stake in the firm. Various techniques are

used to estimate the cost of equity. The concepts are discussed in standard finance texts; see for example, Stewart

Myers and Richard Brealey, Principles of Corporate Finance, 7th edition, 2003, Chapter 9.)

65

Financing arrangements can be far more complex than described in this brief overview. As an illustration, see the

discussions of wind power financing in Ryan Wiser and Mark Bolinger, Annual Report on U.S. Wind Power

Installation, Cost, and Performance Trends: 2007, U.S. DOE, May 2008, p. 14; and John P. Harper, Matthew D.

Karcher, and Mark Bolinger, Wind Project Financing Structures: A Review & Comparative Analysis, Lawrence

Berkeley Laboratory, September 2007. For a description of the financing arrangements for an IPP-developed coal plant,

see the discussion of the Plum Point project in “North American Single Asset Power Deal of the Year 2006,” Project

Finance, February 2007.

Congressional Research Service

19

Power Plants: Characteristics and Costs

•

Financing costs are highest for IPPs, which makes them somewhat less prone to

take on the highest cost projects (such as coal and nuclear plants) unless POUs or

IOUs are co-owners.

Fuel Costs

Fuel costs are important to the economics of coal, nuclear, and natural gas plants, and irrelevant

to solar, geothermal, and wind power. Recent trends in the delivered cost of coal and natural gas

to power plants are illustrated below in Figure 3. The constant dollar prices of both fuels have

increased since the beginning of the decade, but the price escalation has been especially severe

for natural gas.66 Natural gas has also been consistently more expensive than coal. The

comparatively low cost of coal partly compensates for the high cost of building coal plants, while

the high cost of natural gas negates part of the capital cost and efficiency advantages of combined

cycle technology.

Because it takes years to build a power plant, and plants are designed to operate for decades,

generation plans largely pivot on fuel price forecasts. However, fuel prices have been notoriously

difficult to predict. For example, EIA forecasts of delivered coal prices and natural gas wellhead

prices have been off target by an average of, respectively, 47% and 64%.67 EIA attributes the gap

between actual and forecasted gas prices to a host of factors:

As regulatory reforms that increased the role of competitive markets were implemented in

the mid-1980s, the behavior of natural gas was especially difficult to predict. The

technological improvement expectations embedded in early AEOs [Annual Energy

Outlooks] proved conservative and advances that made petroleum and natural gas less costly

to produce were missed. After natural gas curtailments that artificially constrained natural

gas use were eased in the mid-1980s, natural gas was an increasingly attractive fuel source,

particularly for electricity generation and industrial uses. Historically, natural gas price

instability was strongly influenced by natural gas resource estimates, which steadily rose,

and by the world oil price. More recently, the AEO reference case has overestimated natural

gas consumption due to the use of natural gas wellhead price projections that proved to be

significantly lower than what actually occurred.68

EIA’s analysis illustrates how the confluence of technological, regulatory, resource, and domestic

and international market factors make fuel forecasts so problematic. Fuel price uncertainty is

especially important in evaluating the economics of natural gas-fired combined cycle plants. For

the base assumptions used in this study, fuel constitutes half of the total cost of power from a new

combined cycle plant, compared to 18% for a coal plant and 6% for a nuclear plant.

66

Coal and gas prices have increased due to national and global demand growth, limited excess production capacity,

certain unusual circumstances (such as flooding that reduced Australian coal production and exports), increases in rail,

barge, and ocean-going vessel rates for delivering coal to consumers, and the run-up in world oil prices. For a

discussion of energy price trends, see EIA’s Annual Energy Outlook for long-term projections and the Short-Term

Energy Outlook for near-term forecasts http://www.eia.doe.gov/oiaf/forecasting.html.

67

EIA, Annual Energy Outlook Retrospective Review, April 2007, p. 5.

68

Ibid., pp. 2 and 3 [table citations omitted].

Congressional Research Service

20

Power Plants: Characteristics and Costs

Figure 3. Coal and Natural Gas Constant Dollar Price Trends

Sources: EIA, Monthly Energy Review on-line data, Table 9.10, converted to constant dollars by CRS.

The price of the uranium used to make nuclear fuel has, like coal and natural gas, increased

sharply and has been volatile (Figure 4). Although prices have recently dropped, they are still far

above historic levels.69 Over the long term, EIA expects nuclear fuel prices to increase in real

terms from $0.58 per mmbtu in 2007 to $0.77 per mmbtu in 2023, and then slowly decline.70

Even prices twice as high would not have a major impact on nuclear plant economics, which are

dominated by the capital cost of building the plant.

69

Factors that caused prices to rise include increased demand, problems bringing new uranium mines into service, and

the depletion of commercial inventories of uranium. The recent decline in prices may be due in part to an improved

short-term production outlook; see “ERI Expects Base Price to Drop, Then Rise Again,” Platts Nuclear Fuel, June 16,

2008. It takes years before a change in uranium prices is reflected in a reactor fuel load. The lag is caused by the time it

takes to process the uranium and manufacture fuel rods; multi-year contracts that do not reflect current prices; and

reactor fueling schedules (refueling takes place on 18 or 24 month cycles, and at each refueling only about a third of the

core is replaced). This lag can cut both ways: If uranium prices decline, a plant may still have reloads based on

expensive uranium in the pipeline.

70

For the EIA nuclear fuel price forecast used in the Annual Energy Outlook 2008, go to http://www.eia.doe.gov/oiaf/

aeo/electricity.html and click on “figure data” for Figure 70.

Congressional Research Service

21

Power Plants: Characteristics and Costs

Figure 4. Uranium Price Trends

Sources: Trade Tech Exchange Values, as reported in Platts Nuclear Fuel and http://www.uranium.info/.

Air Emissions Controls for Coal and Gas Plants

Regulations that limit air emissions from coal and natural gas plants can impose two types of

costs: The cost of installing and operating control equipment, and the cost of allowances71 that

permit plants to emit pollutants. The following emissions are discussed below:

Emissions from coal:

•

Sulfur dioxide (SO2), a precursor to acid rain and the formation in the atmosphere

of secondary particulates72 that are unhealthy to breathe and can impair visibility.

•

Mercury, a toxic heavy metal.

•

Primary particulates (soot) entrained in the power plant’s flue gas.

71

Under the existing federal SO2 and NOx regulatory programs, most existing plants have been allocated allowances

sufficient to cover their emissions. These existing plants do not need to buy emissions, and may have surplus emissions

to sell, especially if the plants have retrofitted pollution control equipment.

72

Coal plants can produce two types of particulates. Primary particulates, sometimes referred to as soot, are formed in

the combustion process. Secondary particulates form in the atmosphere through the condensation of nitrates and

sulfates. Particulates are objectionable because of visibility and health effects. For more information see Rod Truce,

Robert Crynack, and Ross Blair, “The Problem of Fine Particles,” Coal Power, September 30, 2008

http://www.coalpowermag.com/environmental/156.html.

Congressional Research Service

22

Power Plants: Characteristics and Costs

Emissions from coal and natural gas:

•

Nitrogen oxides (NOx), a precursor to ground level ozone, acid rain, and the

formation in the atmosphere of secondary particulates.

•

Carbon dioxide (CO2), a greenhouse gas produced by the combustion of fossil

fuels.

The regulations and control technologies for SO2, NOx, particulates, and mercury are discussed

briefly under the category of “conventional emissions.” These pollutants are subject to either

existing regulations or regulations being developed under current law, and can be controlled with

well-understood, commercially-available technologies. CO2 is discussed in more detail because

control technologies are still under development and may be far more costly than controls for

conventional emissions.73 While CO2 is not currently subject to federal regulation, control

legislation is being actively considered by the Congress and some states are taking action to limit

CO2 emissions.

More information on air emissions, particularly on regulatory and policy issues, is available in

numerous CRS reports. The reports can be accessed through the “Energy, Environment, and

Resources” link on the CRS website, http://www.crs.gov.

Conventional Emissions

The Environmental Protection Agency (EPA) has established National Ambient Air Quality

Standards (NAAQS) for several pollutants, including SO2, NOx, ozone, and particulates. New

coal and natural gas plants built in areas in compliance with a NAAQS standard must install Best

Available Control Technology (BACT) pollution control equipment that will keep emissions

sufficiently low that the area will stay in compliance. Plants built in areas not in compliance with

a NAAQS (referred to as “non-attainment” areas) must meet a tighter Lowest Achievable

Emission Rate (LAER) standard.74 In practice, air permit emissions are negotiated case-by-case

between the developer and state air authorities. Federal standards set a ceiling; state permits can

specify lower emission limits.

In addition to technology control costs, new plants that emit SO2 must buy SO2 emission

allowances under the acid rain control program established by Title IV of the Clean Air Act.75

Depending on the location of a new plant, it may also need to purchase NOx allowances.76

73

Renewable power plants that do not burn fuels, such as solar, wind, and geothermal power, do not have air

emissions. The depleted fuel rods from nuclear plants contain high level radioactive wastes. The nuclear fuel costs used

in this study include the federal one mill (i.e., one tenth of a cent) per kWh fee for supporting creation of a permanent

waste repository. In the interim depleted fuel is stored at each reactor site. For more information see CRS Report

RL33461, Civilian Nuclear Waste Disposal, by (name redacted).

74

BACT requirements take into account cost-effectiveness; LAER requires the lowest possible emission rate without

cost considerations. For an overview of the regulatory framework see MIT, The Future of Coal, 2007, pp. 135-136. The

federal New Source Performance Standards for new, large fossil-fired plants are found at 40 C.F.R. §60(Da).

75

An allowance is authorization to emit one unit of a pollutant during a specified time period, usually a year. For

example, under the acid rain cap and trade program, national total SO2 emissions are capped and each coal plant must

submit sufficient allowances to cover its annual emissions. Older plants can comply by staying within emission

allocations, installing control equipment, and/or buying SO2 allowances. New plants must install control equipment and

buy allowances.

76

NOx regulation is complex and involves both federal and state rules. For a summary of NOx regulation see the

(continued...)

Congressional Research Service

23

Power Plants: Characteristics and Costs

Regulation of mercury is unsettled. On February 8, 2008, the U.S. Court of Appeals for the D.C.

Circuit vacated the Bush administration’s Clean Air Mercury Rule, which would have allowed

new coal plants to comply with mercury emission limits by purchasing mercury allowances.

Because of the court’s action, coal plant mercury emissions are now categorized as a hazardous

air pollutant. If the decision stands,77 it will trigger a requirement for all coal plants, old and new,

to install mercury control equipment that meets a Maximum Available Control Technology

(MACT) standard. EPA has not yet defined a MACT standard for mercury, but state air officials

will probably require new plants to meet tight mercury emission limits.78

The technology and costs for controlling sulfur, NOx, particulate, and mercury emissions are

briefly described below. For additional information on emission control technologies see the

International Energy Agency Clean Coal Center at http://www.iea-coal.org/site/ieacoal/databases/

clean-coal-technologies.

•

Sulfur. Commercial technologies can remove 95% to 99% of the SO2 formed by

burning coal in pulverized coal plants, and over 99% of the sulfur in IGCC

synthesis gas before it is burned. To the degree that a new pulverized coal unit or

IGCC plant releases SO2 to the atmosphere, it must buy SO2 emission

allowances. Because SO2 emissions by plants with controls are so small,

allowances are not a major expense compared to the other costs of running a

power plant. At mid-2008 allowance and fuel prices, the annual cost of SO2

allowances for a coal plant burning eastern coal would be on the order of $1

million, compared to over $220 million just for fuel. 79 The cost of the control

equipment is more significant. An SO2 control system will account for about 12%

of the capital cost of a new pulverized coal plant and 29% of non-fuel operating

costs (Table 2). (It is difficult to isolate environmental control costs for an IGCC

plant because emissions control is largely integral with cleanup of the synthesis

gas that is necessary, irrespective of environmental rules, prior to combustion.)

•

Mercury. Some pulverized coal plants can achieve 90% removal of mercury as a

co-benefit of operating SO2 and particulate control equipment. Other plants will

have to install a powdered activated carbon injection system (accounting for

about 1% of the plant’s capital cost and 9% of non-fuel operating costs). IGCC

(...continued)

National Energy Technology Laboratory website at http://www.netl.doe.gov/technologies/coalpower/ewr/nox/

regs.html.

77

The decision has been appealed by the EPA to the U.S. Supreme Court.

78

CRS Report RS22817, The D.C. Circuit Rejects EPA’s Mercury Rules: New Jersey v. EPA, by (name redacted) and

(name redacted); Amena Saiyid, “Utilities with Permits to Build New Units Caught in MACT Regulatory Bind,”

Platts Coal Outlook, June 23, 2008.

79

A 600 MW coal plant with an 85% capacity factor and a heat rate of 9,000 btus per kWh, will consume about 40.2

trillion btus of fuel per year. At a controlled emission rate of 0.157 lbs of SO2 per million btus of fuel consumed, this

results in emissions of about 3,200 tons of SO2 annually. At a late June 2008, SO2 allowance price of $330 per ton, this

equals an annual cost of $1.1 million. Emissions and the resulting allowance cost would be still less for an IGCC. In

contrast, the fuel cost for this hypothetical plant (assuming a delivered cost of Central Appalachian coal of $137.92 per

ton and a heat content of 12,500 btus per pound) would be about $222 million per year. The SO2 system does consume

a material amount of the electricity produced by a pulverized coal plant, in the range of 1% to 3% of output. Sources:

MIT, The Future of Coal, 2007, p. 138; Spark Spreads table, Platts Coal Trader, June 30, 2008; U.S. DOE, 20% Wind

Energy by 2030, Table B-12; Delivered Coal Price Comparison table, Argus Coal Transportation, June 24, 2008.

Congressional Research Service

24

Power Plants: Characteristics and Costs

plants would remove 90% to 95% of the mercury from the synthesis gas using

another technology also based on activated carbon.

•

NOx. Commercial technologies can reduce NOx emissions to very low levels for

pulverized coal and IGCC plants. Depending on a plant’s location, it may have to

purchase NOx emission allowances. As in the case of SO2 allowances, because

the controlled emission rates for new plants are so low the total cost of

allowances is small compared to other plant operating costs. The cost of the

control equipment for a pulverized coal plant is about 2% of capital expense and

9% of non-fuel operating costs.

•

Particulates. Primary particulates are controlled using removal systems that have

been a standard feature of pulverized coal plants for many years. Removal

efficiencies exceed 99%. Primary particulate removal rates for IGCC plants are

expected to be similar. Secondary particulates are controlled by reducing NOx

and SO2 emissions, as discussed above.

Table 2. Emission Controls as an Estimated Percentage of Total Costs for a New

Pulverized Coal Plant

Percent of Total Cost

Plant Capital Cost

Plant O&M Cost

SO2 Controls

12%

29%

NOx Controls

2%

12%

Mercury Controls

1%

9%

Total for Emission Controls

16%

51%

Source: Calculated by CRS from MIT, The Future of Coal, 2007, Tables A-3.D.3. and Tables A-3.D.4. Calculations

were made for the point estimates in the report; the tables have cost ranges for capital costs and for mercury

control O&M costs.

Notes: SO2 = sulfur dioxide; NOx = nitrogen oxides; O&M = operations and maintenance.

Carbon Dioxide

This section of the report discusses the technical and cost characteristics of carbon control

technologies for coal and natural gas plants. The estimates of the cost and performance affects of

installing carbon controls are uncertain because no power plants have been built with full-scale

carbon capture. For additional information on carbon control technologies, see CRS Report

RL34621, Capturing CO2 from Coal-Fired Power Plants: Challenges for a Comprehensive

Strategy, by (name redacted), (name redacted), and (name redacted); and Steve Blankinship, “The

Evolution of Carbon Capture Technology, Parts 1 and 2,” Power Engineering, March and May

2008.80

80

There are also many CRS reports on climate change issues. These reports can be retrieved by using the “Energy,

Environment, and Resources” link on the CRS home page to access the “Climate Change” link.

Congressional Research Service

25

Power Plants: Characteristics and Costs

CO2 Removal for Pulverized Coal and Natural Gas Plants

Technology developed by the petrochemical industry, using a class of chemicals called amines,

can be used to scrub CO2 from flue gas. Amine scrubbing is currently used to extract CO2 from

part of the flue gas at a handful of coal-fired plants, to produce CO2 for enhanced oil recovery and

the food industry, but the scale is about a tenth of what would be needed to scrub 90% of the CO2

from the entire flue gas stream of a large power plant.81 Scaling up amine technology to handle

much larger gas flows at a power plant may be technically challenging.

Amine scrubbing is energy intensive. It diverts steam from power production and uses part of the

plant’s electricity production to compress the CO2 for pipeline transportation to its final

disposition. Amine scrubbing is estimated to cut a coal plant’s electricity output by about 30% to

40%.82 The equipment is also costly. According to one study, the cost for building a new coal

plant with amine scrubbing is an estimated 61% higher than building the a plant without carbon

controls.83 The same study estimated the cost for a coal plant retrofit installation, without taking

into account the recent rapid increase in power plant construction costs, at about $1,600 per kW

of net capacity, or almost $1 billion for a 600 MW plant.84

The cost and performance impacts for adding amine scrubbing to a natural gas-fired combined

cycle are also large. The estimated reduction in net electricity output is 14%, and the estimated

increase in the plant capital cost is about 100%.85 Researchers are attempting to commercialize

less costly carbon capture technologies for conventional coal and gas plants, but these are still in

early development.

81

Currently four commercial facilities in the United States treat fossil plant flue gas to recover CO2. The largest amount

of CO2 captured is about 800 tons per day. In contrast, a 600 MW coal plant would produce about 13,300 tons of CO2

daily; 90% removal would require extracting 12,000 tons of CO2 each day. (Information on current commercial

projects from HDR|Cummins & Barnard, Inc., Carbon Dioxide Capture and Sequestration, report to Alliant Energy,

April 2008, Report No. 5561.06 R-002, p. 8; and http://www.mgs.md.gov/geo/pub/co2seqpaper.pdf. CO2 emissions for

a 600 MW plant computed as follows: 600 MW x 9 million btus of fuel input per MWh x 24 hours x 205.3 pounds of

CO2 released per mmbtu of heat input for bituminous coal, divided by 2 million. Rate of CO2 released from burning

coal is from EIA, Electric Power Annual 2006, p. 92.)

82

MIT, The Future of Coal, 2007, pp. 25 and 28; “Pilot Project Uses Innovative Process to Capture CO2 From Flue

Gas,’ EPRI Journal, Spring 2008, p. 4).

83

Calculated from MIT, The Future of Coal, 2007, Table 3.1 (estimates for supercritical pulverized coal).

84

Ibid., p. 28. The cost and practicality of a retrofit would vary with specific plant conditions. Another consideration is

that retrofitting carbon capture to an IGCC plant may not be straightforward. An MIT study suggests that for technical

reasons a developer looking toward possible future carbon legislation cannot build an IGCC plant that will provide

optimal efficiency today (without carbon technology) and tomorrow (after carbon control retrofit). The developer must

make a choice that may result in suboptimal performance (higher costs and less efficiency) either in current or future

operation (MIT, The Future of Coal, 2007, pp. 149-150).

85

National Energy Technology Laboratory, Cost and Performance Baseline for Fossil Energy Plants, Volume 1, May

2007, Exhibit 5-25 and page 481; EIA, Assumptions to the Annual Energy Outlook 2008, Table 38. The plant capacity

derate for the natural gas combined cycle plant is less than for the pulverized coal plant primarily because natural gas

generation is much less carbon intensive than burning coal, so less CO2 must be processed. The lower carbon intensity

is due to the greater efficiency of a gas-fired combined cycle compared to a pulverized coal plant (fewer btus of fuel are

needed to generate a unit of electricity), and because burning a btu of gas produces about half as much CO2 as burning

a btu of coal.

Congressional Research Service

26

Power Plants: Characteristics and Costs

CO2 Removal for IGCC Coal Plants

Carbon capture for an IGCC plant involves multi-step treatment of the synthesis gas using

technology originally developed for the petrochemical industry. Estimates of the cost and

performance impact of incorporating carbon capture into a IGCC design vary widely. For the

sample of studies shown in Table 3, the estimated increase in capital costs ranges from 32% to

51%. The estimated loss in generating capacity varies by more than a factor of two, from 13% to

28%. This wide variation reflects in part factors specific to different IGCC technologies, but is

also an indication of limited experience with IGCC technology generally and the integration of

carbon capture in particular.

Table 3. Estimates of the Change in IGCC Plant Capacity and Capital Cost from

Adding Carbon Capture

Source and

IGCC Technology

Change in Net

Generating Capacity

Change in Plant Cost

GE/Radiant

-13%

32%

CoP E-Gas

-17%

40%

Shell

-19%

35%

n/a

43%

-25%

51%

GE/Full Quench (retrofit)

-17%

n/a

CoP E-Gas (retrofit)

-28%

n/a

Generic

-28%

32%

NETL, 2007

EIA, 2008

Generic

EPRI 2006

Shell

MIT 2007

Sources: NETL, Cost and Performance Baseline for Fossil Energy Plants, Volume 1, Exhibit 3-114; EIA, Assumptions to

the Annual Energy Outlook 2008, Table 38; EPRI, Feasibility Study for an Integrated Gasification Combined Cycle Facility

at a Texas Site, October 2006, Tables 7-1, 13-2, and 13-3; MIT, The Future of Coal, 2007, pp. 122, 150, and 151,

and Table 30.

Notes: IGCC = Integrated Gasification Combined Cycle; NETL = National Energy Technology Laboratory; EIA

= Energy Information Administration; EPRI = Electric Power Research Institute; MIT = Massachusetts Institute of

Technology; n/a = not available; GE = General Electric; CoP = ConocoPhillips. Radiant and full quench refer to

alternative means of heat capture from cooling of the synthesis gas. Values are for units built to incorporate

carbon capture, except when retrofit is indicated.

While IGCC technology is arguably better-suited for carbon capture than pulverized coal systems,

it does not currently provide a simple or inexpensive path to carbon control. In addition to the

cost and performance penalties and uncertainties, other factors complicate implementing IGCC

carbon control. For example, the nation’s largest and least expensive coal supply is western

Congressional Research Service

27

Power Plants: Characteristics and Costs

subbituminous coal. However, the IGCC technologies best suited for using this coal also appear

to incur the largest cost and performance penalties from adding carbon control technology.86

CO2 Allowance Costs

Congress has considered legislation that would put a cost on carbon emissions, such as the

Lieberman-Warner Climate Security Act of 2007 (S. 2191). If Congress ultimately legislates

allowance-based carbon controls, the estimated costs of such allowances are very uncertain. As an

illustration of this uncertainty, Figure 5 shows EIA’s alternative projections of CO2 allowance

prices under S. 2191. Depending on assumptions for such factors as the speed with which new

technologies are deployed and their costs, and the availability for purchase of international CO2

emission offsets, EIA’s estimate of the price of allowances by 2030 ranges from about $60 to

$160 per metric ton of CO2 (2006 dollars).

86

The dry feed Shell and ConocoPhillips E-Gas systems appear to be better suited to high moisture subbituminous and

lignite coals than the GE technology, which brings coal into the gasifier as a coal/water slurry (excess water reduces the

efficiency of the gasifier and requires more oxygen). However, the GE technology operates at higher pressures and can

use full quench cooling of the synthesis gas to produce steam for the CO2 shift reactor, which may make it the better

choice for carbon capture. MIT, The Future of Coal, 2007, pp. 149-151; EPRI, Feasibility Study for an Integrated

Gasification Combined Cycle Facility at a Texas Site, October 2006, pp. v and vi; and Nexant, Inc., Environmental

Footprints and Costs of Coal-Based Integrated Gasification Combined Cycle and Pulverized Coal Technologies, report

for the U.S. EPA, July 2006, p. 5-13.

Congressional Research Service

28

Power Plants: Characteristics and Costs

Figure 5. EIA’s Projections of S. 2191 CO2 Allowance Prices (2006$ per Metric Ton of

CO2 Equivalent)

Sources: Supporting spreadsheets for EIA, Energy Market and Economic Impacts of S.2191, the Lieberman-Warner

Climate Security Act of 2007, April 2008.

Even the low end of EIA’s allowance price forecasts would impose costs far beyond those of

existing air emissions regulations. Figure 6 compares the price of coal in EIA’s long-term

Reference Case projection (which assumes only current law, and therefore no carbon controls) to

EIA’s “core” case estimate of allowance prices from the S. 2191 study. Based on EIA’s forecasts,

by 2030 the allowance price is the equivalent of triple the coal price. 87 (As noted above, the

outlook for CO2 allowance prices is uncertain. Different legislative approaches and changes to

other forecasting assumptions can produce very different estimates from those shown here.)

87

For a broader summary of S. 2191 allowance price forecasts see CRS Report RL34489, Climate Change: Costs and

Benefits of S. 2191/S. 3036, by (name redacted) and (name redacted). For an example of how a different legislative

approach can effect allowance prices, see CRS Report RL34520, Climate Change: Comparison and Analysis of S. 1766

and S. 2191 (S. 3036), by (name redacted) and (name redacted).

Congressional Research Service

29

Power Plants: Characteristics and Costs

Figure 6. Comparison of EIA’s Reference Case Coal Prices and S. 2191 Core Case

CO2 Allowance Prices

Sources: Supporting spreadsheets for EIA, Energy Market and Economic Impacts of S. 2191, the Lieberman-Warner

Climate Security Act of 2007, April 2008; CRS calculations (assumes 20 MMBtus per ton of coal and 209 lbs. of

CO2 per MMBtu if coal consumed).

Financial Analysis Methodology and Key

Assumptions

This financial analysis of new power plants provides estimates of the operating costs and required

capital recovery of each generating technology through 2050. Plant operating costs will vary from

year to year depending, for example, on changes in fuel prices and the start or end of government

incentive programs. To simplify the comparison of alternatives, these varying yearly expenses are

converted to a uniform annualized cost expressed as 2008 present value dollars.

Converting a series of cash flows to a financially equivalent uniform annual payment is a twostep process. First, the cash flows for the project are converted to a 2008 “present value.” The

present value is the total cost for the analysis period, adjusted (“discounted” using a “discount

factor”) to account for the time value of money and the risk that projected costs will not occur as

expected. This lump-sum 2008 present value is then converted to an equivalent annual payment

using a uniform payments factor. 88

88

For a more detailed discussion of the annualization method see, for example, Chan Park, Fundamentals of

Engineering Economics, 2004, Chapter 6; or Eugene Grant, et al., Principles of Engineering Economy, 6th Ed., 1976,

(continued...)

Congressional Research Service

30

Power Plants: Characteristics and Costs

The capital costs for the generating technologies are also converted to annualized payments. An

investor-owned utility or independent power producer must recover the cost of its investment and

a return on the investment, accounting for income taxes, depreciation rates, and the cost of

money. These variables are encapsulated within an annualized capital cost for a project computed

using a “capital charge rate.” The financial model used for this study computes a project-specific

capital charge rate that reflects the assumed cost of money, depreciation schedule, book project

life, financing structure (percent debt and percent equity), and composite federal and state income

tax rate. For a POU project, which is 100% debt financed, a “capital recovery factor” reflecting

each project’s cost of money is computed and used to calculate a mortgage-type annual

payment.89

Combining the annualized capital cost with the annualized operating costs yields the total

estimated annualized cost of a project. This annualized cost is divided by the projected yearly

output of electricity to produce a cost per Mwh for each technology. By annualizing the costs in

this manner, it is possible to compare alternatives with different year-to-year cost patterns on an

apples-to-apples basis.

Inputs to the financial model include financing costs, forecasted fuel prices, non-fuel operations

and maintenance expense, the efficiency with which fossil-fueled plants convert fuel to

electricity, and typical utilization rates (see Appendix D, Table D-1 through Table D-4, below).

Most of these inputs are taken from published sources, such as the assumptions EIA used to

produce its 2007 and 2008 long-term energy forecasts. The power plant capital costs are

estimated by CRS based on a review of public information on recent projects. Appendixes B and

C of the report displays the data used for the capital costs estimates.

Analysis of Power Project Costs

This section of the report analyzes the cost of power from the generating technologies discussed

above. Results are first presented for a Base Case analysis. Results are then presented for four

additional cases, each of which explores a key variable that influences power plant costs. These

cases are:

•

Influence of federal and state incentives.

•

Higher natural gas price.

•

Uncertainty in capital costs.

•

Carbon controls and costs.

In each case the cost of power from a natural gas-fired combined cycle plant is used as a

benchmark for evaluating the cost of power from the other generating technologies. The gas-fired

combined cycle plant is used as a benchmark because of the dominant role it has played, and may

(...continued)

Chapter 7.

89

For additional information on capital charge rates see Hoff Stauffer, “Beware Capital Charge Rates,” The Electricity

Journal, April 2006. For additional information on the calculation of capital recovery factors see Chan Park,

Fundamentals of Engineering Economics, 2004, Chapter 2; or Eugene Grant, et al., Principles of Engineering

Economy, 6th Ed., 1976, Chapter 4.

Congressional Research Service

31

Power Plants: Characteristics and Costs

continue to play, as the source of new generating capacity capable of meeting baseload and

intermediate demand. The closer a generating technology comes to meeting or beating the power

cost of the combined cycle, the better its chances of competing in the market for new power

plants.

The Base Case is a starting point for comparing how different assumptions, such as for fuel and

construction costs, change estimated power costs. None of the cases is a “most likely” estimate of

future costs. Future power costs are subject to so many variables with high degrees of uncertainty

that projecting a most likely case is impractical. The object of the analysis is provide insight into

how key factors influence the costs of power plants, including factors under congressional control

such as incentive programs.

These estimates are approximations subject to a high degree of uncertainty. The rankings of the

technologies by cost are therefore also an approximation and should not be viewed as definitive

estimates of the relative cost-competitiveness of each option. Also note that project-specific

factors would weigh into an actual developer’s decisions, including how close a fossil plant

would be to fuel sources, local climate (for wind and solar), the need for and cost of transmission

upgrades, the developer’s appetite for risk, and the developer’s financial resources.

Case 1: Base Case

Key Observations

•

The lowest cost generating technologies in the Base Case are pulverized coal,

geothermal, and natural gas combined cycle plants. All have costs around $60 per

Mwh (2008 dollars). Based on the assumptions in this report, other technologies

are at least a third more expensive.

•

Of the three lowest cost technologies, geothermal plants are limited to available

sites in the West that typically support only small plants, and coal plants have

become harder to build due to cost and environmental issues. The gas-fired

combined cycle plant is currently a technology that can be built at a large scale,

for cycling or baseload service, throughout the United States.

•

The above projections are based on private (IOU or IPP) funding of power

projects. The cost per Mwh drops precipitously if the developer is assumed to be

a POU with low-cost financing. However, most POUs are small and do not have

the financial or managerial resources to build large power projects.

Discussion

As noted earlier in the report, power plants can be built by investor-owned utilities (IOUs),

publicly owned utilities (POUs), or independent power producers (IPPs). The Base Case assumes

that coal and nuclear plants are constructed by IOUs because they are most likely to have the

financial resources and regulatory support to undertake these very large and expensive projects.

The natural gas combined cycle plant is assumed to be built by an IPP. IPPs often prefer to build

and operate gas-fired projects because of their relatively low capital costs. The wind, solar, and

geothermal plants are also assumed to be IPP projects. The most common current practice is for

IPPs to develop renewable projects and sell the power to regulated utilities.

Congressional Research Service

32

Power Plants: Characteristics and Costs

The Base Case has the following characteristics:

•

The analysis is for new projects beginning operation in 2015.

•

Estimates of fuel prices, allowance prices, and most operational characteristics

are from EIA’s Reference Case assumptions for the 2008 Annual Energy

Outlook.90

•

The 2008 overnight capital costs for each technology are estimated by CRS from

public information on recent projects (see Appendix B).

•

The Base Case excludes “discretionary” incentives: The federal loan guarantee

program and clean coal tax credit programs, state utility commission decisions to

allow CWIP in rates, and the federal renewable energy production tax credit,

which is scheduled to expire at the end of 2010. These incentives are excluded

because they are granted by government entities based on a case-by-case analysis

of individual projects, and/or are dependent on congressional action to fund or

extend the incentives. Accordingly, there is no certainty that most projects will

receive these incentives. For example, as of November 2008, DOE had received

requests from nuclear plant developers for $122 billion in loan guarantees,

compared to congressional approval of only $18.5 billion for nuclear projects.91

•

The only incentives included in the Base Case are (1) the 30% investment tax

credit for solar and geothermal energy systems, which has been extended to 2017

and is automatically available to any qualifying facility; and (2) the nuclear

production tax credit, which is available to any qualifying facility. As discussed

above, the assumed value of the nuclear credit is 1.35 cents per kWh.

•

The Base Case includes no carbon emission controls or costs.

Given these assumptions, Table 4 presents the resulting annualized cost of power per Mwh for

each technology.

90

The Annual Outlook main report, assumptions report, and related information are available on the EIA website at

http://www.eia.doe.gov/oiaf/aeo/index.html.

91

George Lobsenz, “Nuke Overload: Utilities Seeking $122 Billion in DOE Loan Guarantees,” The Energy Daily,

October 3, 2008.

Congressional Research Service

33

Table 4. Estimated Base Case Results

(2008 $)

Fuel Cost

(4)

SO2 and NOx

Allowance Cost

(5)

CO2 Allow.

Cost

(6)

Prod. Tax

Credit

(7)

Total

Operating

Costs

(8)

Capital

Return

(9)

Total

Annualized

$/Mwh

(10)

$5.57

$11.13

$0.61

$0.00

$0.00

$17.31

$45.79

$63.10

IOU

$5.46

$10.41

$0.10

$0.00

$0.00

$15.97

$67.02

$82.99

NG: Combined

Cycle

IPP

$2.57

$30.57

$0.14

$0.00

$0.00

$33.27

$28.50

$61.77

Nuclear

IOU

$6.13

$5.29

$0.00

$0.00

($3.18)

$8.23

$74.99

$83.22

Wind

IPP

$6.67

$0.00

$0.00

$0.00

$0.00

$6.67

$74.07

$80.74

Geothermal

IPP

$13.69

$0.00

$0.00

$0.00

$0.00

$13.69

$45.54

$59.23

Solar: Thermal

IPP

$13.71

$0.00

$0.00

$0.00

$0.00

$13.71

$86.61

$100.32

Solar:

Photovoltaic

IPP

$4.17

$0.00

$0.00

$0.00

$0.00

$4.17

$251.24

$255.41

Technology

(1)

Developer

Type

(2)

Non-Fuel

O&M Cost

(3)

Coal: Pulverized

IOU

Coal: IGCC

Source: CRS estimates.

Notes: Projections are subject to a high degree of uncertainty. These results should be interpreted as indicative given the projection assumptions rather than as definitive

estimates of future outcomes. Mwh = megawatt-hour; IGCC = integrated gasification combined cycle; NG = natural gas; CCS = carbon capture and sequestration; SO2 =

sulfur dioxide; NOx = nitrogen oxides; O&M = operations and maintenance; IPP = independent power producer; IOU = investor owned utility.

CRS-34

Power Plants: Characteristics and Costs

Under the Base Case assumptions, the lowest-cost options are pulverized coal, natural gas

combined cycle, and geothermal generation, all in the $60 per Mwh (2008 dollars) range (column

10). These results are attributable to the following factors:

•

Pulverized coal is a mature technology that relies on a relatively low cost fuel.

•

Natural gas is an expensive fuel, but combined cycle technology is highly

efficient and has a low construction cost.

•

Geothermal energy has no fuel cost and unlike variable renewable technologies,

such as wind and solar, can operate at very high utilization rates (high utilization

allows the plant to spread fixed operating costs and capital recovery charges over

many megawatt-hours of sales).

Although all three technologies have similar power costs, the coal and geothermal technologies

have limitations and risks that the natural gas combined cycle does not face. Geothermal plants

are limited to relatively small facilities (about 50 MW) at western sites. As discussed above,

many coal projects have been canceled due to environmental opposition and escalating

construction costs. In contrast, the gas-fired combined cycle plant has limited environmental

impacts, can be located wherever a gas pipeline with sufficient capacity is available, and plants

can be built with generating capacities in the hundreds of megawatts. Probably the main risk

factor for a combined cycle plant is uncertainty over the long term price and supply of natural

gas.

In the Base Case, wind power, IGCC coal, and nuclear energy have costs in the $80 per Mwh

range. IGCC and nuclear plants are very expensive to build, with estimated overnight capital

costs of, respectively, $3,359 and $3,682 per kW of capacity (2008 dollars; see Table D-2).

Because the plants are expensive and take years to construct (an estimated four years for an IGCC

plant and six years for a nuclear plant) these technologies also incur large charges for interest

during construction that must be recovered in power costs.

Wind has a relatively high cost per Mwh because wind projects have high capital costs ($2,100

per kW of capacity) and are assumed to operate with a capacity factor of only 34%. The low

capacity factor means that the plant is the equivalent of idle two-thirds of the year. Consequently,

the capital costs for the plant must be recovered over a relatively small number of units of

electricity production, driving up the cost per Mwh. High capital costs and low rates of utilization

also drive up the costs of the solar thermal and solar PV plants to, respectively, $100 per Mwh

and $255 per Mwh.

Comparison to a Benchmark Price of Electricity

Another way of viewing the results is to compare each technology’s costs to a benchmark cost of

electricity. As discussed above, the benchmark used is the cost of power from a natural gas

combined cycle plant.

Column 3 of Table 5 shows the difference between the Base Case power cost for each technology

and the Base Case cost of power from the gas-fired combined cycle. Geothermal energy and

pulverized coal are the only technologies that have power costs similar to the natural gas

combined cycle plant. Nuclear, wind, and coal IGCC power are projected to have costs 31% to

35% higher, and solar thermal has a projected power cost 62% higher. Solar photovoltaic is over

300% higher.

Congressional Research Service

35

Power Plants: Characteristics and Costs

Table 5. Benchmark Comparison to Natural Gas Combined Cycle Plant Power

Costs: Base Case Values

Developer Type

(2)

Difference in the Power

Cost Compared to the

Combined Cycle Plant

(3)

Geothermal

IPP

-4%

Coal: Pulverized

IOU

2%

Wind

IPP

31%

Coal: IGCC

IOU

34%

Nuclear

IOU

35%

Solar: Thermal

IPP

62%

Solar: Photovoltaic

IPP

313%

Technology

(1)

Source: CRS estimates.

Notes: A negative number indicates that the technology has a power cost lower than that of the combined

cycle. Projections are subject to a high degree of uncertainty. These results should be interpreted as indicative

given the projection assumptions rather than as definitive estimates of future outcomes. IGCC = integrated

gasification combined cycle; IPP = independent power producer; IOU = investor owned utility.

Effect of Financing Costs

The cost of money can have a significant impact on the cost of power. As discussed earlier, POUs

have access to lower cost financing than IOUs or IPPs. The significance of lower cost financing is

illustrated in Table 6, which compares the cost of power assuming IOU and IPP financing

(column 3) with the cost of power assuming POU financing (column 4). Excluding for the

moment the solar technologies, the reduction in the cost of power ranges from 14% for the

combined cycle plant (the least capital-intensive option, which makes it least sensitive to

financing costs) to 37% for the capital-intensive IGCC and nuclear plants (column 5). The low

cost of public financing helps explain why many capital intensive coal and nuclear projects have

POU co-owners.92

92

Recent coal projects with public power participation include Prairie State (Illinois), Spruce 2 (Texas), Spurlock 4

(Kentucky), Dallman 4 (Illinois), Smith CFB (Kentucky), Sutherland 4 (Iowa), Pee Dee (South Carolina), Cross 3 and

4 (South Carolina), Whelan 2 (Nebraska), Hugo 2 (Oklahoma), Southwest 2 (Missouri), Dry Fork (Wyoming),

Nebraska City 2 (Nebraska), Weston 4 (Wisconsin), Big Stone II (South Dakota), Plum Point (Arkansas), Turk

(Arkansas), American Municipal Power Generating Station (Ohio), and Holcomb 2&3 (Kansas). Proposed new nuclear

projects with POU involvement include Summer 2 and 3 (South Carolina), Vogtle 3 and 4 (Georgia), North Anna 3

(Virginia), Bellefonte 3 and 4 (Alabama), Calvert Cliffs 3 (Maryland), and South Texas 3 and 4 (Texas). Some of the

coal projects and all of the nuclear projects other than Bellefonte have IOU or IPP co-owners. The POU participant in

the Calvert Cliffs 3 project is EDF, a French government-owned utility.

Congressional Research Service

36

Power Plants: Characteristics and Costs

Table 6. Effect of Public Power Financing on Base Case Results

(2008 $)

Developer

(2)

Annualized Cost

per Mwh

(3)

Annualized Cost

Per Mwh

Assuming POU

Developer

(4)

Coal: Pulverized

IOU

$63.10

$43.97

-30%

Coal: IGCC

IOU

$82.99

$52.44

-37%

NG: Combined

Cycle

IPP

$61.77

$53.35

-14%

Nuclear

IOU

$83.22

$52.25

-37%

Wind

IPP

$80.74

$54.41

-33%

Geothermal

IPP

$59.23

$47.40

-20%

Solar: Thermal

IPP

$100.32

$89.24

-11%

Solar: Photovoltaic

IPP

$255.41

$219.02

-14%

Technology

(1)

Percent

Difference

(5)

Source: CRS estimates.

Notes: Projections are subject to a high degree of uncertainty. These results should be interpreted as indicative

given the projection assumptions rather than as definitive estimates of future outcomes. IGCC = integrated

gasification combined cycle; NG = natural gas; Mwh = megawatt-hour; IPP = independent power producer; IOU

= investor owned utility; POU = publicly owned utility.

The reduction in cost by using public financing is only 11% for the solar thermal plant and 14%

for the solar photovoltaic plant. The reductions are small because when the plants are publicly

financed they lose the 30% renewable energy investment tax credit (POUs do not pay taxes and

so cannot take advantage of any tax-based incentives). The loss of the tax credit largely negates

the benefit of lower cost POU financing for solar projects.

Case 2: Influence of Federal and State Incentives

Key Observations

•

Government financial incentives can make high-cost technologies into low-cost

options. The incentive with the greatest impact is the federal loan guarantee,

which reduces the cost of financing capital-intensive technologies. With a loan

guarantee the cost of nuclear power flips from a high-cost option ($83.22 per

Mwh) to one of the low cost ($63.73 per Mwh).

•

Even when competing technologies have the advantage of the discretionary

government incentives, no technology currently has a significant cost advantage

over the natural gas combined cycle.

Discussion

The Base Case includes only non-discretionary incentives: The renewable energy investment tax

credit and the nuclear production tax credit. This analysis includes the following discretionary

incentives:

Congressional Research Service

37

Power Plants: Characteristics and Costs

•

Federal loan guarantees for nuclear power.

•

A clean coal tax credit for the IGCC plant.

•

A production tax credit for wind (assumes continuation of the terms and

conditions of the current production tax credit).

•

Return on construction work in progress (CWIP) in rates for IOUs.

Table 7 shows the effect of the discretionary incentives compared to the Base Case. The

additional incentives have the greatest effect on nuclear power. The annualized cost of nuclear

generation drops by 23% (column 7), from one of the highest to one of the lowest costs. The most

important driver for the nuclear plant is the federal loan guarantee, which allows a developer to

fund a project with 80% debt at a much reduced interest rate. The loan guarantee alone cuts the

cost of nuclear power by 20% ($15.44 per Mwh).

Congressional Research Service

38

Table 7. Power Costs with Additional Government Incentives

(2008 $)

Developer

(2)

Government

Incentives in the

Base Case

(3)

Annualized Cost

per Mwh in

Base Case

(4)

Additional

Government

Incentives

(5)

Annualized Cost Per

Mwh With Additional

Incentives

(6)

Percent Difference

(7)

Coal: Pulverized

IOU

None

$63.10

CWIP in rates.

$60.02

-5%

Coal: IGCC

IOU

None

$82.99

ITC; CWIP in rates.

$73.28

-12%

NG: Combined Cycle

IPP

None

$61.77

None

$61.77

0%

Nuclear

IOU

PTC

$83.22

Loan guarantee;

CWIP in rates.

$63.73

-23%

Wind

IPP

None

$80.74

PTC

$72.79

-10%

Geothermal

IPP

ITC

$59.23

None

$59.23

0%

Solar: Thermal

IPP

ITC

$100.32

None

$100.32

0%

Solar: Photovoltaic

IPP

ITC

$255.41

None

$255.41

0%

Technology

(1)

Source: CRS estimates.

Notes: Projections are subject to a high degree of uncertainty. These results should be interpreted as indicative given the projection assumptions rather than as definitive

estimates of future outcomes. IGCC = integrated gasification combined cycle; NG = natural gas; Mwh = megawatt-hour; IOU = investor owned utility; IPP = independent

power producer; POU = publicly owned utility; PTC = production tax credit; CWIP = construction work in progress; ITC = investment tax credit.

CRS-39

Power Plants: Characteristics and Costs

The renewable production tax credit reduces the cost of wind power by 10%. Geothermal and

combined cycle plants (with no additional incentives) and coal (with a 5% reduction in cost due

to CWIP in rates) remain low-cost options.

Table 8 compares the combined cycle benchmark cost of power (column 3) to the cost of power

with discretionary incentives (column 4). The table is limited to the technologies that receive the

additional incentives: Pulverized coal (CWIP in rates), IGCC coal (CWIP and an investment tax

credit), wind (production tax credit), and nuclear (loan guarantee and CWIP). With discretionary

incentives, nuclear power swings from a 35% higher cost than the combined cycle to only a 3%

difference (comparing columns 3 and 4). The cost advantage of the combined cycle over wind

and IGCC coal drops from more than 30% to just under 20%. The cost of power from pulverized

coal remains similar to that of the combined cycle.

Table 8. Benchmark Comparison to Combined Cycle Power Costs: Additional

Government Incentives

Difference in Power Cost from Combined Cycle

Technology

(1)

Developer Type

(2)

Base Case

(3)

Additional Incentives

(4)

Coal: Pulverized

IOU

2%

-3%

Wind

IPP

31%

18%

Coal: IGCC

IOU

34%

19%

Nuclear

IOU

35%

3%

Source: CRS estimates.

Notes: The table only includes the four technologies that receive additional incentives (see Table 7). A negative

number indicates that the technology has a power cost lower than that of the combined cycle. Projections are

subject to a high degree of uncertainty. These results should be interpreted as indicative given the projection

assumptions rather than as definitive estimates of future outcomes. IOU = investor owned utility; IPP =

independent power producer.

Case 3: Higher Natural Gas Prices

Key Observations

•

If the price of natural gas is assumed to be 50% higher than in the Base Case,

geothermal and pulverized coal power are clearly less costly than the combined

cycle. However, the use of the geothermal power is limited to available sites in

the western United States, and pulverized coal by construction cost and

environmental issues.

•

In the higher gas price case, the cost of power from the natural gas combined

cycle plant converges with wind, nuclear, and IGCC coal. The combined cycle

plant no longer has a clear economic advantage over these technologies, but

neither is it at a great disadvantage.

Congressional Research Service

40

Power Plants: Characteristics and Costs

Discussion

The economics of natural gas-fired generation pivot on fuel prices. For the base assumptions used

in this study, fuel constitutes half of the total cost of power from a new combined cycle power

plant, compared to 18% for a coal plant and 6% for a nuclear plant. In addition to being critical to

the cost of gas-fired power, natural gas prices are also one of the most uncertain elements in this

analysis. As discussed earlier in this report, natural gas prices have been exceptionally difficult to

forecast. If the United States becomes more dependent in the future on imports of liquefied

natural gas, the domestic and international natural gas markets will be increasingly linked, adding

an additional element of uncertainty to the natural gas price outlook.93

Underestimates of natural gas prices were pervasive among government and private forecasters in

the 1990s and contributed to over-investment in gas-fired generating capacity. 94 If future gas

prices are higher than assumed in this report’s Base Case, the economics of gas-fired generation

could change substantially. The gas market has historically been volatile. Gas prices increased

more than 200% from the early 1990s through 2007, and annual increases sometimes exceeded

50% (Figure 7).

Figure 7. Natural Gas Price Trends (Henry Hub Spot Price)

Source: St. Louis Federal Reserve Bank FRED database.

Figure 8 illustrates the Base Case gas price projection and an alternative that ramps up to a level

50% higher than in the Base Case. In the Base Case the annualized cost of power from a natural

gas combined cycle plant is $61.77 per Mwh. With a 50% higher gas price, the combined cycle

93

EIA, Annual Energy Outlook 2008, p. 75.

Rebecca Smith, “Utilities Question Natural-Gas Forecasting—Cheap and Plentiful Was Outlook a Few Years Ago;

Price Is Double Prediction,” The Wall Street Journal, December 27, 2004.

94

Congressional Research Service

41

Power Plants: Characteristics and Costs

power cost is $77.05 per Mwh. At this power cost the combined cycle is substantially more costly

than pulverized coal or geothermal power, and has a clear economic advantage only over the solar

technologies (Table 9, column 4). On the other hand, even with this much higher fuel price

projection, the cost of power from the combined cycle is still comparable to that of wind, nuclear,

and IGCC coal generation; and while pulverized coal and geothermal power have lower costs, as

discussed above the former is increasingly hard to build for cost and environmental reasons, and

the latter is limited to small plants at western sites. Therefore, even with a 50% increase in fuel

prices, the gas-fired combined cycle is still a competitive option for new generating capacity.

Figure 8. Projection of Natural Gas Prices to Electric Power Plants, 2006 $ per

MMBtu

$18

$16

$ per MMBtu, 2006$

$14

$12

$10

$8

$6

$4

$2

Base Case (EIA Reference Case)

48

20

45

20

9

42

20

20

3

36

20

0

33

20

20

3

4

27

20

20

2

21

20

18

20

20

1

5

$-

50% Higher Forecast

Source: EIA, Annual Energy Outlook 2008, and CRS estimates.

Table 9. Benchmark Comparison to Natural Gas Combined Cycle Plant Power

Costs: 50% Higher Gas Price

Difference in Power Cost from Combined Cycle Plant

Developer Type

(2)

Base Case

(3)

50% Higher Natural Gas

Price

(4)

Geothermal

IPP

-4%

-22%

Coal: Pulverized

IOU

2%

-18%

Wind

IPP

31%

5%

Coal: IGCC

IOU

34%

8%

Nuclear

IOU

35%

8%

Solar: Thermal

IPP

104%

30%

Solar: Photovoltaic

IPP

432%

231%

Technology

(1)

Congressional Research Service

42

Power Plants: Characteristics and Costs

Source: CRS estimates.

Notes: A negative number indicates that the technology has a power cost lower than that of the combined

cycle. Projections are subject to a high degree of uncertainty. These results should be interpreted as indicative

given the projection assumptions rather than as definitive estimates of future outcomes. IGCC = integrated

gasification combined cycle; IOU = investor owned utility; IPP = independent power producer.

Another perspective is to determine the increase in the Base Case natural gas price projection

required for the cost of power from the natural gas combined cycle plant to equal the cost of

power from an alternative technology. This is illustrated in Table 10. The table shows that the

price of gas would have to be between 62% to 69% higher than in the Base Case for the cost of

power from a combined cycle to equal the projected cost of electricity from nuclear, wind, or coal

IGCC technologies (column 3). Natural gas prices would have to increase by about 125% to

635% for the cost of combined cycle power to match solar thermal or solar photovoltaic

electricity costs.

Table 10. Change in the Base Case Gas Price Needed to Equalize the Cost of

Combined Cycle Power with Other Technologies

Developer Type

(2)

Change in the Base Case Price of

Natural Gas Needed to Equalize the

Cost of Combined Cycle Power with

Other Technologies

(3)

Coal: Pulverized

IOU

5%

Coal: IGCC

IOU

69%

Nuclear

IOU

69%

Wind

IPP

62%

Geothermal

IPP

-8%

Solar: Thermal

IPP

125%

Solar: Photovoltaic

IPP

635%

Technology

(1)

Source: CRS estimates.

Notes: Projections are subject to a high degree of uncertainty. These results should be interpreted as indicative

given the projection assumptions rather than as definitive estimates of future outcomes. IGCC = integrated

gasification combined cycle; IOU = investor owned utility; IPP = independent power producer.

Case 4: Uncertainty in Capital Costs

Key Observations

•

Because of its low capital costs and assumed high utilization rate, the power cost

of the gas-fired combined cycle plant is about half as sensitive to changes in

capital costs as the other technologies.

•

The implication is that if power plant capital costs continue to increase rapidly,

the competitive position of the combined cycle will improve compared to all

other technologies.

•

If capital costs decline, the competitive position of the other technologies will

substantially improve versus the combined cycle. However, even assuming a

Congressional Research Service

43

Power Plants: Characteristics and Costs

25% drop in capital costs compared to the Base Case, the combined cycle is still

competitive with all other technologies.

Discussion

As noted above, the cost of building power plants has recently increased dramatically. Whether

costs will continue to increase, remain steady in real dollar terms, or decline is unknown. Table

11 illustrates the effect on the cost of power of assuming a uniform 25% increase or decrease in

capital costs for all technologies compared to the Base Case. Power costs change by about +/20% for each technology except for the gas-fired combined cycle plant (+/-12%; see column 3).

This is because the combined cycle has a relatively low capital cost and a high capacity factor.

Table 11. Effect of Higher and Lower Capital Costs on the Cost of Power

Developer

(2)

Change in Cost of Power for a

25% Increase or Decrease in

Capital Costs

(3)

Coal: Pulverized

IOU

+/-18%

Coal: IGCC

IOU

+/-20%

NG: Combined Cycle

IPP

+/-12%

Nuclear

IOU

+/-23%

Wind

IPP

+/-23%

Geothermal

IPP

+/-19%

Solar: Thermal

IPP

+/-22%

Solar: Photovoltaic

IPP

+/-25%

Technology

(1)

Source: CRS estimates.

Notes: Projections are subject to a high degree of uncertainty. These results should be interpreted as indicative

given the projection assumptions rather than as definitive estimates of future outcomes. IGCC = integrated

gasification combined cycle; NG = natural gas; IOU = investor owned utility; IPP = independent power producer.

Table 11 shows that the power cost of the combined cycle is about half as sensitive to changes in

capital costs as the other generating technologies. The implication is that continued rapid

escalation in the cost of building power plants will favor the economics of combined cycles. This

is illustrated by Table 12. In the Base Case (Column 3), the power costs of wind, nuclear, and

IGCC coal are about a third higher than the combined cycle. In the high capital cost case (Column

4) the difference widens to almost 50%. On the other hand, decreases in capital costs, whether the

result of market forces or government incentives, would reduce the cost of power from the other

technologies about twice as much as for the combined cycle. This is illustrated by the low capital

cost case (Column 5), in which all the non-solar technologies are within 21% or less of the

generating cost of the combined cycle.

Congressional Research Service

44

Power Plants: Characteristics and Costs

Table 12. Benchmark Comparison to Combined Cycle Power Costs: Higher and

Lower Capital Costs

Difference from the Power Cost of the Combined Cycle

Developer Type

(2)

Base Case

(3)

25% Higher

Capital Costs

(4)

25% Lower

Capital Costs

(5)

Geothermal

IPP

-4%

3%

-12%

Coal: Pulverized

IOU

2%

8%

-5%

Nuclear

IOU

35%

48%

18%

Wind

IPP

31%

44%

14%

Coal: IGCC

IOU

34%

45%

21%

Solar: Thermal

IPP

62%

77%

44%

Solar: Photovoltaic

IPP

313%

362%

252%

Technology

(1)

Source: CRS estimates

Notes: A negative number indicates that the technology has a power cost lower than that of the combined

cycle. Projections are subject to a high degree of uncertainty. These results should be interpreted as indicative

given the projection assumptions rather than as definitive estimates of future outcomes. IGCC = integrated

gasification combined cycle; IOU = investor owned utility; IPP = independent power producer.

Case 5: Carbon Controls and Costs

Key Observations

•

The estimates of carbon-related allowance costs and control technology costs

used in this analysis are subject to an exceptional degree of uncertainty, including

whether Congress will actually pass carbon control legislation. The results of this

analysis are therefore equally uncertain.

•

With the carbon control assumptions used in this analysis, coal-fired generation

is expensive, ranging from about $100 to almost $120 per Mwh. The least

expensive options include zero-carbon emission technologies: Geothermal

($59.23 per Mwh), nuclear ($83.22) and wind ($80.74).

•

The natural gas combined cycle plant without carbon capture is competitive with

the other options, even with allowance costs, at $77.21 per Mwh.

•

If the cost and efficiency penalties of carbon capture technologies are assumed to

drop by 50%, the gas-fired combined cycle plant with capture has an electricity

cost comparable to wind and nuclear power. However, a coal plant with capture

is still more expensive than wind or nuclear power.

Discussion

Carbon control legislation is under consideration by the Congress, but there has been no

agreement on the structure of a control regime or a timetable for implementation. No power

plants have been built with full scale carbon capture equipment. The costs of CO2 allowances and

control systems are therefore very uncertain. Actual costs will depend on the content of final

Congressional Research Service

45

Power Plants: Characteristics and Costs

legislation (if any), the development of allowance markets in the United States and abroad, and

the evolution of control technologies.

The carbon capture power cost analysis for this study is based on the following assumptions:

•

Power plant cost and performance with carbon controls assume current

(petrochemical industry based) technology capable of removing 90% of the CO2.

As discussed above, the cost of carbon capture for power plants using

petrochemical industry derived technology will be very high. Table 13 provides

estimates of how the capital costs and heat rates of coal and gas plants increase

with the addition of carbon controls based on current technology. Capital costs

increase by 42% to 97% (column 4), and heat rates increase by 21% to 27%

(column 7) resulting in a decline in efficiency. Newer technologies may be less

costly and more efficient, but these are still in development.

Table 13. Effect of Current Technology Carbon Controls on Power Plant Capital Cost

and Efficiency

(2008 $)

Capital Cost for a Plant

Entering Service in 2015

(2008$/kW)

Heat Rate for a Plant

Entering Service in 2015

(btus/kWh)

Base

Case

(2)

With

Carbon

Controls

(3)

Percent

Change

(4)

Base Case

(5)

With

Carbon

Controls

(6)

Percent

Change

(7)

Coal: Pulverized

$2,485

$3,935

58%

9,118

11,579

27%

Coal: IGCC

$3,359

$4,774

42%

8,528

10,334

21%

$1,186

$2,342

97%

6,647

8,332

25%

Technology

(1)

Coal Technologies

Natural Gas Technologies

NG: Combined Cycle

Source: Table D-2.

Notes: A higher heat equates to less efficient, and therefore more costly operation. IGCC = integrated

gasification combined cycle; NG = natural gas; kW =kilowatt; kWh = kilowatt-hour. Projections are subject to a

high degree of uncertainty. These results should be interpreted as indicative given the projection assumptions

rather than as definitive estimates of future outcomes.

•

The CO2 allowance price projection is adapted from the EIA “core” case forecast

from its analysis of S. 2191.95 Allowance costs begin in 2012 at $17.70 per metric

ton of CO2 (2008 dollars); increase by 2020 and 2030 to, respectively, $31.34 and

$63.99; and reach $266.80 by 2050 (see Table D-4). All allowances must be

purchased (i.e., there is no free distribution of allowances to power plants).

•

Fuel prices are the same prices used in the Base Case (see Table D-4).

95

EIA, Energy Market and Economic Impacts of S. 2191, the Lieberman-Warner Climate Security Act of 2007, April

2008. The report and output spreadsheets are available at the EIA website at http://www.eia.doe.gov/oiaf/servicerpt/

s2191/index.html. Note that the carbon case in this report does not include other aspects of S. 2191 that would affect

compliance costs, including a free allowance allocation and carbon control bonus allocations of allowances.

Congressional Research Service

46

Power Plants: Characteristics and Costs

•

As in the Base Case, the only financial incentives included are the nuclear

production tax credit and the investment tax credit for solar and geothermal

plants.

•

From a financing standpoint, units with carbon controls are assumed to be high

risk projects that incur financing costs equivalent to below investment grade

interest rates. This assumption is made because units coming on-line in 2015, as

assumed for this study, would be part of the first wave of power plants with

carbon controls.

Table 14, below, shows estimates of the levelized cost of power for a carbon capture case.

Congressional Research Service

47

Table 14. Estimated Annualized Cost of Power with Carbon Controls

(2008 $)

Developer

Type

(2)

Non-Fuel

O&M Cost

(3)

Fuel

Cost

(4)

SO2 and NOx

Allowance

Cost

(5)

CO2

Allow.

Cost

(6)

Prod.

Tax

Credit

(7)

Total

Operating

Costs

(8)

Capital

Return

(9)

Total

Annualized

$/Mwh

(10)

Coal: Pulverized

IOU

$5.57

$11.13

$0.61

$33.80

$0.00

$51.11

$49.58

$100.69

Coal: Pulverized/CCS

IOU

$13.48

$14.13

$0.77

$4.29

$0.00

$32.67

$78.87

$111.54

Coal: IGCC

IOU

$5.46

$10.41

$0.10

$31.61

$0.00

$47.58

$67.02

$114.60

Coal: IGCC/CCS

IOU

$7.10

$12.61

$0.13

$3.83

$0.00

$23.67

$95.25

$118.92

NG: Combined Cycle

IPP

$2.57

$30.57

$0.14

$13.06

$0.00

$46.34

$30.88

$77.21

NG: Combined Cycle/CCS

IOU

$3.68

$38.32

$0.17

$1.64

$0.00

$43.81

$51.09

$94.90

Geothermal

IPP

$13.69

$0.00

$0.00

$0.00

$0.00

$13.69

$45.54

$59.23

Nuclear

IOU

$6.13

$5.29

$0.00

$0.00

($3.18)

$8.23

$74.99

$83.22

Wind

IPP

$6.67

$0.00

$0.00

$0.00

$0.00

$6.67

$74.07

$80.74

Solar: Thermal

IPP

$13.71

$0.00

$0.00

$0.00

$0.00

$13.71

$86.61

$100.32

Solar: Photovoltaic

IPP

$4.17

$0.00

$0.00

$0.00

$0.00

$4.17

$251.24

$255.41

Technology

(1)

Coal Technologies

Natural Gas Technologies

Zero Carbon Technologies

Source: CRS estimates.

Notes: Projections are subject to a high degree of uncertainty. These results should be interpreted as indicative given the projection assumptions rather than as definitive

estimates of future outcomes. Mwh = megawatt-hour; IGCC = integrated gasification combined cycle; NG = natural gas; CCS = carbon capture and sequestration; SO2 =

sulfur dioxide; NOx = nitrogen oxides; O&M = operations and maintenance; IOU = investor owned utility; IPP = independent power producer.

CRS-48

Power Plants: Characteristics and Costs

The results indicate:

•

The power costs for coal plants using control technologies are high compared to

the Base Case. The costs in the carbon case range from $100.69 per Mwh to

almost $120 per Mwh (column 10), compared to $63.19 per Mwh for a

pulverized coal unit in the Base Case (Table 14, column 10). This illustrates the

impact of the high capital costs and efficiency penalties of current carbon capture

technologies.

•

With the imposition of carbon costs on fossil plants, three of the least expensive

options are zero-carbon technologies: Geothermal ($59.23 per Mwh), nuclear

($83.22) and wind ($80.74). Because geothermal plants are limited to specific

sites in the western states, nuclear power (a baseload technology) and wind

power (a variable renewable resource) are the zero carbon options with relatively

low costs and wide latitude for plant sites.

•

A fourth relatively low-cost technology is the natural gas combined cycle plant

without carbon capture ($77.21 per Mwh including allowance costs). The

relatively low cost is due to the technology’s low capital cost, high capacity

factor, and relatively low emissions of CO2 per megawatt-hour of power

generated. As shown in Table 14, the natural gas combined cycle plant without

carbon capture incurs allowance costs of $13.06 per Mwh, which is 61% less

than the pulverized coal plant cost of $33.80 per Mwh (column 6). In other

words, for every dollar of allowance costs incurred by a coal plant without

capture technology, the combined cycle incurs only about 40 cents in costs.96

•

Solar thermal power ($100.32 per Mwh) has a lower cost than fossil plants with

carbon capture technology, but is still estimated to be about 20% more expensive

than nuclear and wind power.

The relatively low cost of power from the natural gas combined cycle plant is in part a function of

the fuel price. As noted above, the carbon capture analysis uses the same fuel price projections as

in the Base Case. It is possible that in a carbon-constrained world demand for gas will increase,

driving up prices. As shown below in Table 15:

•

A 12% increase in the price of gas would equalize the cost of electricity from the

combined cycle plant without carbon capture with wind power (column 3);

•

A 20% increase would equalize the power cost of the combined cycle plant and

the nuclear plant;

•

The price of natural gas would have to more than double for the power cost of the

gas-fired combined cycle plant to equal the cost of coal power with carbon

controls, or increase by 75% to match the cost of solar thermal power.

96

The pulverized coal plant modeled in this study emits about 1,906 pounds of CO2 per Mwh. This is computed as

follows. The plant has a heat rate of 9,118 btus per kWh. This equates to coal consumption of 9.118 MMbtus per Mwh.

Coal is assumed to emit 209 pounds of CO2 per mmbtu of coal consumed, so 9.118 MMbtus per Mwh x 209 pounds of

CO2 per mmbtu = 1,905.7 pounds of CO2 per Mwh. In the case of a combined cycle burning natural gas, the gas emits

only 117.08 pound of CO2 per mmbtu when burned (44% less than coal) and the plant’s heat rate is 6,647 btus per kWh

(27% better than the coal plant). The combined cycle’s CO2 emissions are therefore 6.647 MMbtus per Mwh x 117.08

pounds of CO2 per mmbtu = 778.2 pounds of CO2 per Mwh, 59.2% less than the pulverized coal plant.

Congressional Research Service

49

Power Plants: Characteristics and Costs

This scale of natural gas price increases has precedent. As shown in Figure 7, between the early

1990s and 2007 the market price of natural gas increased by about 200%.

Table 15. Change in the Price of Natural Gas Required to Equalize the Cost of

Combined Cycle Generation (Without Carbon Controls) with Other Technologies

Developer

(2)

Change in Price of Natural Gas

from Base Case Necessary to

Equalize Cost of Power

(3)

Coal: Pulverized

IOU

77%

Coal: IGCC

IOU

123%

Coal: Pulverized/CCS

IOU

112%

Coal: IGCC/CCS

IOU

136%

Nuclear

IOU

20%

Wind

IPP

12%

Geothermal

IPP

-59%

Solar: Thermal

IPP

75%

Solar: Photovoltaic

IPP

580%

Technology

(1)

Source: CRS estimates.

Notes: Projections are subject to a high degree of uncertainty. These results should be interpreted as indicative

given the projection assumptions rather than as definitive estimates of future outcomes. IGCC = integrated

gasification combined cycle; NG = natural gas; CCS = carbon capture and sequestration; IOU = investor owned

utility; IPP = independent power producer.

As discussed above, the cost and efficiency impacts of current carbon capture technologies are

high, and improved technologies are under development. Table 16 shows the estimated cost of

power for plants with carbon capture assuming that capital cost and heat rate (efficiency)

penalties are both reduced by 50%. In this case the combined cycle plant with capture has an

electricity cost slightly less than wind and nuclear power, and the pulverized coal pla

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.