Coast Guard Polar Security Cutter (PSC) and Arctic Security Cutter (ASC) Icebreaker Programs: Background and Issues for Congress

Congressional research reportJan 21, 2026

Ask Donna

What actually matters in this document.

Text

Coast Guard Polar Security Cutter (PSC) and

Arctic Security Cutter (ASC) Icebreaker

Programs: Background and Issues for

Congress

Updated January 21, 2026

Congressional Research Service

https://crsreports.congress.gov

RL34391

SUMMARY

Coast Guard Polar Security Cutter (PSC) and

Arctic Security Cutter (ASC) Icebreaker

Programs: Background and Issues for Congress

RL34391

January 21, 2026

Ronald O'Rourke

Specialist in Naval Affairs

The size of the Coast Guard’s polar icebreaker fleet and Coast Guard programs for building new

polar icebreakers have been oversight matters for Congress for many years. A 2023 Coast Guard

fleet mix analysis concluded that the service will require a total of eight to nine polar icebreakers,

including four to five heavy polar icebreakers and four to five medium polar icebreakers, to perform the Coast Guard’s polar

(i.e., Arctic and Antarctic) missions in coming years. The Coast Guard’s operational polar icebreaker fleet currently consists

of one heavy polar icebreaker, Polar Star, and two medium polar icebreakers, Healy and Storis. Polar Star entered service in

1976 and is now well beyond its originally intended 30-year service life. Healy entered service in 2000. Storis was built in

2012 to serve as a commercial Arctic oil-exploration support ship. It was purchased by the Coast Guard in 2024 and

converted into a Coast Guard medium polar icebreaker. It entered service with the Coast Guard in 2025 and was renamed

Storis.

To recapitalize and expand its polar icebreaking fleet, the Coast Guard is procuring new heavy polar icebreakers called Polar

Security Cutters (PSCs) and new medium polar icebreakers called Arctic Security Cutters (ASCs). Polar Star is to be retired

when new PSCs enter service. ASCs will be smaller and individually less expensive to procure than PSCs. The Coast Guard

initiated the PSC program in its FY2013 budget submission. In April 2019, the Coast Guard awarded a contract for designing

and building up to three PSCs to Halter Marine Inc. of Pascagoula, MS, a shipyard that was then owned by Singapore

Technologies (ST) Engineering. In November 2022, ST Engineering sold Halter Marine to Louisiana-based Bollinger

Shipyards. The former Halter Marine is now called Bollinger Mississippi Shipbuilding. Subsequent to the April 2019 contract

award, the PSC program fell years behind schedule, in large part due to the time needed to complete the design of the ship.

The first PSC was originally projected to be delivered in 2024 but is now projected to be delivered no earlier than 2030.

Much of the delay in the delivery date occurred prior to Bollinger’s November 2022 purchase of Halter.

On December 26, 2025, the Coast Guard awarded contracts for the construction of up to six ASCs. Rauma Marine

Constructions Oy (RMC) of Rauma, Finland, was awarded a contract to build up two ASCs, with the first to be delivered in

2028. Bollinger Shipyards was awarded a contract to build up to four ASCs at the firm’s shipyard in Houma, LA, with the

first to be delivered in 2029. RMC, Bollinger, Seaspan Shipyards of North Vancouver, Canada, and ship design and

engineering firm Aker Arctic Technology Oy of Helsinki, Finland, partnered to compete for the contracts. RMC and

Bollinger will build the ASCs to a design based on the Multi-Purpose Icebreaker (MPI), an icebreaker design developed by

Seaspan and Aker Arctic.

Prior to the FY2025 reconciliation act (H.R. 1/P.L. 119-21 of July 4, 2025, also known as the One Big Beautiful Bill Act, or

OBBBA), the PSC program had received a total of about $1.7 billion in procurement funding. The FY2025 reconciliation act

provided an additional $4.3 billion in procurement funding for PSC program and $3.5 billion in procurement funding for the

ASC program. The combination of Healy, Storis, up to three PSCs, and up to six ASCs would produce a future polar

icebreaking fleet of up to 11 ships, including up to three heavy polar icebreakers (the three PSCs) and up to eight medium

polar icebreakers (Healy, Storis, and six ASCs).

Issues for Congress regarding Coast Guard polar icebreakers include the risk of cost growth, schedule delay, or technical

problems in the PSC and ASC programs; Coast Guard intentions regarding the procurement of a fourth or fifth PSC, so as to

meet the stated requirement (following the retirement of Polar Star) for a total of four or five heavy polar icebreakers; the

total number of ASCs that will eventually be built, given the two existing medium polar icebreakers (Healy and Storis) and

the stated requirement for a total of four or five medium polar icebreakers; whether required numbers of polar icebreakers

would increase, and if so, by how many ships, if Greenland were to become part of the United States; and whether the

building some ASCs in Finland should serve as a model for building ships for the U.S. Navy in foreign shipyards.

The Coast Guard also operates Great Lakes icebreakers that are much smaller than the Coast Guard’s polar icebreakers. The

Coast Guard’s FY2024 budget initiated a program for procuring a new Great Lakes icebreaker (GLIB) that would have

capabilities similar to those of Mackinaw, the Coast Guard’s sole existing heavy GLIB. The Coast Guard estimates the total

procurement cost of the ship at about $350 million.

Congressional Research Service

Coast Guard Polar Security Cutter

Contents

Introduction ..................................................................................................................................... 1

Background ..................................................................................................................................... 1

Missions of Coast Guard Polar Icebreakers .............................................................................. 1

Statutory Duties and Missions ............................................................................................ 1

Multiple Missions (Not Just Icebreaking) ........................................................................... 2

Polar (Not Just Arctic) Operations ...................................................................................... 2

Required Numbers of Coast Guard Polar Icebreakers .............................................................. 3

Trilateral Polar Icebreaker Collaboration Effort (ICE Pact) ..................................................... 4

Current Coast Guard Polar Icebreakers ..................................................................................... 5

Overview ............................................................................................................................. 5

Heavy Polar Icebreaker Polar Star ..................................................................................... 5

Medium Polar Icebreakers Healy and Storis....................................................................... 5

Coast Guard Polar Icebreaker Procurement Programs .............................................................. 7

Polar Security Cutter (PSC) Program ................................................................................. 7

Arctic Security Cutter (ASC) Program ............................................................................. 13

Total Number of Polar Icebreakers Existing or Under Contract ............................................. 17

Coast Guard Great Lakes Icebreakers ..................................................................................... 17

Current Fleet ..................................................................................................................... 17

New Great Lakes Icebreaker (GLIB) ................................................................................ 19

Issues for Congress ........................................................................................................................ 21

Overview ................................................................................................................................. 21

Discussions of Selected Issues ................................................................................................ 21

Program-Execution Risk ................................................................................................... 22

Potential Impact of Greenland Annexation on Required Numbers of Icebreakers ........... 26

Use of Foreign Shipyards for Building U.S. Navy Ships ................................................. 27

Figures

Figure 1. Rendering of Halter Marine Design for PSC ................................................................... 9

Figure 2. Model of Halter Marine Design for PSC ....................................................................... 10

Figure 3. Rendering of Halter Marine Design for PSC ................................................................. 10

Figure 4. Rendering of Halter Marine Design for PSC ..................................................................11

Figure 5. Rendering of Halter Marine Design for PSC ..................................................................11

Figure 6. Rendering of Arctic Security Cutter (ASC) ................................................................... 15

Figure 7. Great Lakes Icebreaker Mackinaw ................................................................................. 18

Figure A-1. Polar Star and Polar Sea ........................................................................................... 28

Figure A-2. Polar Star ................................................................................................................... 29

Figure A-3. Polar Sea .................................................................................................................... 30

Figure A-4. Healy .......................................................................................................................... 31

Figure A-5. Storis .......................................................................................................................... 32

Figure A-6. Storis .......................................................................................................................... 33

Figure B-1. Rendering of 2019 SDC Concept Design for Polarstern II ....................................... 38

Congressional Research Service

Coast Guard Polar Security Cutter

Figure B-2. Rendering of 2024 Design for PolarStern II .............................................................. 39

Tables

Table 1. Procurement Funding for PSC Program .......................................................................... 12

Table 2. Total Number of Polar Icebreakers Existing or Under Contract ...................................... 17

Table A-1. Coast Guard Polar Icebreakers .................................................................................... 35

Table C-1. Major Polar Icebreakers as of April 4, 2022 ................................................................ 42

Appendixes

Appendix A. Current U.S. Coast Guard Polar Icebreakers ........................................................... 28

Appendix B. Design of PSC .......................................................................................................... 36

Appendix C. Required Numbers of U.S. Polar Icebreakers .......................................................... 41

Contacts

Author Information........................................................................................................................ 61

Congressional Research Service

Coast Guard Polar Security Cutter

Introduction

This report provides background information and issues for Congress on the Coast Guard’s Polar

Security Cutter (PSC) and Arctic Security Cutter (ASC) icebreaker programs. It also provides

background information on the Coast Guard’s Great Lakes icebreaker (GLIB) program.

Issues for Congress regarding Coast Guard polar icebreakers include

•

•

•

•

•

program-execution risk (i.e., the risk of cost growth, schedule delay, or technical

problems) in the PSC and ASC programs;

Coast Guard intentions regarding the procurement of a fourth or fifth PSC, so as

to meet the Coast Guard’s stated requirement (following the retirement of the

Coast Guard’s existing heavy polar icebreaker, Polar Star) for having a total of

four or five heavy polar icebreakers;

the total number of ASCs that will eventually be built, given the Coast Guard’s

two existing medium polar icebreakers (Healy and Storis) and the Coast Guard’s

stated requirement for having a total of four or five medium polar icebreakers;

whether required numbers of polar icebreakers would increase, and if so, by how

many ships, if Greenland were to become part of the United States; and

whether the building some ASCs in Finland should serve as a model for building

ships for the U.S. Navy in foreign shipyards.

Separate CRS reports cover acquisition of Coast Guard general-purpose cutters1 and Coast Guard

waterways commerce cutters (WCCs).2 Another CRS report provides an overview of various

issues relating to the Arctic.3

Background

Missions of Coast Guard Polar Icebreakers

Statutory Duties and Missions

The permanent statute that sets forth the Coast Guard’s primary duties—14 U.S.C. §102—states

that among other things, the Coast Guard shall (emphasis added) “develop, establish, maintain,

and operate, with due regard to the requirements of national defense, aids to maritime navigation,

icebreaking facilities, and rescue facilities for the promotion of safety on, under, and over the

high seas and waters subject to the jurisdiction of the United States,” and “pursuant to

international agreements, develop, establish, maintain, and operate icebreaking facilities on,

under, and over waters other than the high seas and waters subject to the jurisdiction of the United

States.”4

1 CRS Report R42567, Coast Guard Cutter Procurement: Background and Issues for Congress, by Ronald O'Rourke.

2 CRS In Focus IF11672, Coast Guard Waterways Commerce Cutter (WCC) Program: Background and Issues for

Congress, by Ronald O'Rourke.

3 CRS Report R41153, Changes in the Arctic: Background and Issues for Congress, coordinated by Ronald O'Rourke.

4 14 U.S.C. §102(4) and §102(5), respectively. This statute was previously 14 U.S.C. §2; it was renumbered as 14

U.S.C. §102 by Section 103 of the Frank LoBiondo Coast Guard Authorization Act of 2018 (S. 140/P.L. 115-282 of

December 4, 2018). (Title I of P.L. 115-282, consisting of Sections 101-124, specified a general reorganization of Title

14.)

Congressional Research Service

1

Coast Guard Polar Security Cutter

In addition, Section 888(a) of the Homeland Security Act of 2002 (H.R. 5005/P.L. 107-296 of

November 25, 2002)—the law that established the Department of Homeland Security (DHS) and

transferred the Coast Guard from the Department of Transportation to DHS—sets forth 11

specific missions for the Coast Guard (often referred to as the Coast Guard’s 11 statutory

missions), including the mission of “ice operations.”5

Multiple Missions (Not Just Icebreaking)

The Coast Guard’s polar icebreakers do not simply break ice—they are multimission cutters6 that

conduct a variety of other operations that are conducted in lower-latitude waters by the Coast

Guard’s general-purpose cutters. U.S. polar ice operations conducted in large part by the Coast

Guard’s polar icebreakers support 9 of the Coast Guard’s 11 statutory missions.7 The roles of U.S.

polar icebreakers can be summarized as follows:

•

•

•

•

•

conducting and supporting scientific research in the Arctic and Antarctic;

defending U.S. sovereignty in the Arctic by helping to maintain a U.S. presence

in U.S. territorial waters in the region;

defending other U.S. interests in polar regions, including economic interests in

waters that are within the U.S. exclusive economic zone (EEZ) north of Alaska;

monitoring sea traffic in the Arctic, including ships bound for the United States;

and

conducting other typical Coast Guard missions (such as search and rescue, law

enforcement, and protection of marine resources) in Arctic waters, including U.S.

territorial waters north of Alaska.8

Polar (Not Just Arctic) Operations

The Coast Guard’s large icebreakers are called polar icebreakers rather than Arctic icebreakers

because they perform missions in both the Arctic and Antarctic. Operations to support National

Science Foundation (NSF) research activities in both polar regions account for a significant

portion of U.S. polar icebreaker operations.

Supporting NSF research in the Antarctic focuses on performing an annual mission, called

Operation Deep Freeze (ODF), to break through Antarctic sea ice so as to reach and resupply

McMurdo Station, the large U.S. Antarctic research station located on the shore of McMurdo

Sound, near the Ross Ice Shelf. The Coast Guard stated in 2018 that Polar Star, the Coast

Guard’s only operational heavy polar icebreaker, “spends the [northern hemisphere] winter [i.e.,

the southern hemisphere summer] breaking ice near Antarctica in order to refuel and resupply

McMurdo Station. When the mission is complete, the Polar Star returns to dry dock [in Seattle]

5 The 11 missions set forth in Section 888(a) are marine safety; search and rescue; aids to navigation; living marine

resources (fisheries law enforcement); marine environmental protection; ice operations; ports, waterways and coastal

security; drug interdiction; migrant interdiction; defense readiness; other law enforcement.

6 Cutters are commissioned Coast Guard vessels greater than 65 feet in length.

7 For a list of the 11 missions, see footnote 5. The two statutory missions not supported by polar ice operations are

illegal drug interdiction and undocumented migrant interdiction. (Department of Homeland Security, Polar Icebreaking

Recapitalization Project Mission Need Statement, Version 1.0, approved by DHS June 28, 2013, p. 10.)

8 This passage, beginning with “The roles of ... ,” originated in an earlier iteration of this CRS report and was later

transferred by the Government Accountability Office (GAO) with minor changes to GAO, Coast Guard[:]Efforts to

Identify Arctic Requirements Are Ongoing, but More Communication About Agency Planning Efforts Would Be

Beneficial, GAO-10-870, September 2010, p. 53.

Congressional Research Service

2

Coast Guard Polar Security Cutter

in order to complete critical maintenance and prepare it for the next ODF mission. Once out of

dry dock, it’s back to Antarctica, and the cycle repeats itself.”9 In terms of the maximum

thickness of the ice to be broken, the annual McMurdo resupply mission generally poses the

greatest icebreaking challenge for U.S. polar icebreakers, though Arctic ice can frequently pose

its own significant icebreaking challenges for U.S. polar icebreakers. The Coast Guard’s medium

polar icebreaker Healy spends most of its operational time in the Arctic supporting NSF research

activities and performing other operations.

Although polar ice is diminishing due to climate change, observers generally expect that this

development will not eliminate the need for U.S. polar icebreakers, and in some respects might

increase mission demands for them. Even with the diminishment of polar ice, there are still

significant ice-covered areas in the polar regions, and diminishment of polar ice could lead in

coming years to increased commercial ship, cruise ship, and naval surface ship operations, as well

as increased exploration for oil and other resources, in the Arctic—activities that could require

increased levels of support from polar icebreakers, particularly since waters described as “ice

free” can actually still have some amount of ice.10 The Coast Guard’s Arctic strategic outlook

document, released in April 2019, states

In order to prosecute its missions in the Arctic, the Coast Guard must fully understand and

operate freely in this vast and unforgiving environment. Effective capability requires

sufficient heavy icebreaking vessels, reliable high-latitude communications, and

comprehensive Maritime Domain Awareness. In order to respond to crises in the Arctic,

our Nation must also muster adequate personnel, aviation, and logistics resources in the

region. The Coast Guard is the sole provider and operator of the U.S. polar capable fleet

but currently does not have the capability or capacity to assure access in the high latitudes.

Closing the gap requires persistent investment in capabilities and capacity for polar

operations, including the Polar Security Cutter.11

Required Numbers of Coast Guard Polar Icebreakers

A 2023 Coast Guard fleet mix analysis concluded that the service will require a total of eight to

nine polar icebreakers, including four to five heavy polar icebreakers and four to five medium

polar icebreakers, to perform the Coast Guard’s polar (i.e., Arctic and Antarctic) missions in

coming years.12 Prior to this new fleet mix analysis, the Coast Guard had stated that it would need

9 NyxoLyno Cangemi, “Coast Guard Icebreaker Crew Completes Second Arctic Mission; U.S. Interests in Arctic

Domain Depends [sic] on Fleet Recapitalization,” DVIDS (Defense Visual Information Distribution System), October

19, 2018.

10 For more on changes in the Arctic due to diminishment of Arctic ice, see CRS Report R41153, Changes in the

Arctic: Background and Issues for Congress, coordinated by Ronald O'Rourke.

11 United States Coast Guard, Arctic Strategic Outlook, April 2019, p. 6.

12 Source: spoken testimony of Coast Guard officials, as reflected in CQ hearing transcripts, of

•

Admiral Linda L. Fagan, then-Commandant of the Coast Guard, at an April 18, 2023, hearing on the Coast

Guard’s proposed FY2024 budget before the Coast Guard and Maritime Transportation subcommittee of the

House Transportation and Infrastructure Committee, for the total figure of eight to nine polar icebreakers;

•

Admiral Steven D. Poulin, then-Vice Commandant of the Coast Guard, at a June 21, 2023, hearing before the

same subcommittee on the on the Coast Guard’s emerging challenges and statutory needs, again for the total

figure of eight to nine polar icebreakers; and

•

Vice Admiral Peter Gautier, then-Coast Guard Deputy Commandant for Operations, at a November 29, 2023,

hearing before the House Homeland Security Committee on how U.S. Arctic strategy impacts homeland

security, for both the total figure of eight to nine polar icebreakers and how that total includes four to five

heavy polar icebreakers and four to five medium polar icebreakers.

Congressional Research Service

3

Coast Guard Polar Security Cutter

at least six polar icebreakers, including three heavy polar icebreakers. For additional background

information on required numbers of U.S. polar icebreakers, see Appendix C.

Trilateral Polar Icebreaker Collaboration Effort (ICE Pact)

On July 11, 2024, the leaders of the United States, Canada, and Finland announced a trilateral

partnership on polar icebreakers, called the Icebreaker Collaboration Effort (ICE Pact), to

implement a “collaborative effort to continue building best-in-class Arctic and polar icebreakers

and other Arctic and polar capabilities in each of our respective countries by sharing expertise,

information, and capabilities.”13 On November 13, 2024, officials from the three ICE Pact

governments signed a memorandum of understanding (MOU) for implementing the ICE Pact.14

On October 9, 2025, the United States and Finland signed an MOU for procuring up to 11 ASCs

for the U.S. Coast Guard, including up to four to be built in Finland and up to seven to be built in

the United States.15 Under the MOU,

•

•

up to six of the ASCs are to be built by an industry partnership consisting of

Bollinger Shipyards of Lockport, LA; shipbuilder Rauma Marine Constructions

Oy (RMC) of Rauma, Finland; Seaspan Shipyards of North Vancouver, Canada;

and ship design and engineering firm Aker Arctic Technology Oy of Helsinki,

Finland, with up to two of the ships to be built by RMC in Finland and up to four

of the ships to be built by Bollinger in the United States; and

up to five ASCs reportedly are to be built by Canadian shipbuilder Davie of

Lauzon, Quebec, Canada, with up to two of the ships to be built at Helsinki

Shipyard, a shipyard in Helsinki, Finland, owned by Davie, and up to three to be

built at the Davie-owned Gulf Copper shipyard in Galveston, TX.16

13 White House, “Joint Statement on ICE Pact,” July 11, 2024. See also Justin Katz, “ICE Pact: Why the US Had to

Recruit Help in Race with Russia, China for Arctic Icebreakers,” Breaking Defense, August 16, 2024; Rana Foroohar,

“The New Maritime Statecraft,” Financial Times, August 12, 2024; Katy Buda, Gregory Sanders, and Cynthia Cook,

“Recruiting Friends for the Polar Icebreaker Express: Viewing the ICE Pact Through Broader Defense Industrial

Cooperation,” Center for Strategic and International Studies, August 1, 2024; Cal Biesecker, “Following ICE Pact,

Canadian Shipbuilder Seeking to Partner in U.S.,” Defense Daily, July 29, 2024; Howard Altman, “Allied Pact Aims to

Close Yawning Icebreaker Gap with Adversaries,” The War Zone, July 12, 2024; Eric Bazail-Eimil, Lee Hudson, and

Kyle Duggan, “US, Canada and Finland to Challenge Russia and China in the Arctic,” Politico Pro, July 11, 2024;

Laura Dhillon Kane and Josh Wingrove, “US, Finland, Canada Forge Icebreaker Ship Pact to Counter Russia, China in

Arctic,” Bloomberg, July 11, 2024; Lee Ferran, “US Teams with Canada, Finland on Polar Icebreakers to Chill

Russian, Chinese Power Up North” Breaking Defense, July 11, 2024; Michael Martina, “US, Canada, Finland Launch

Effort to Build Ice-Breaking Ships as China and Russia Cooperate in Arctic,” Reuters, July 11, 2024; Patrick Tucker,

“US Agrees to Build Icebreakers with Canada, Finland,” Defense One, July 11, 2024.

14 Department of Homeland Security, “United States, Canada, and Finland Sign MOU to Build Arctic and Polar

Icebreakers,” press release dated November 13, 2024. See also Cal Biesecker, “U.S., Canada And Finland Formalize

Effort On Polar Icebreaker Development And Production,” Defense Daily, November 13, 2024; Justin Katz, “US,

Canada, Finland Ink Joint MOU, Latest Step in High North-Focused ICE Pact,” Breaking Defense, November 13,

2024; Aaron-Matthew Lariosa, “U.S. Signs Icebreaker Pact with Finland, Canada,” USNI News, November 13, 2024.

15 Finnish Government, “Finland and USA Deepen Icebreaker Cooperation,” October 10, 2025; White House, “Fact

Sheet: President Donald J. Trump Authorizes Construction of Arctic Security Cutters,” October 9, 2025.

16 Nick Blenkey, “Bollinger-led Team Picked to Build six Arctic Security Cutters,” Marine Log, October 10, 2025;

Bollinger, “White House Selects Bollinger-Led International Team to Build Six U.S. Coast Guard Arctic Security

Cutters,” news release dated October 9, 2025; Steve Holland, Anne Kauranen, Jeff Mason, and Gram Slattery, “Trump

and Finland’s Stubb Approve Deal tor Icebreaker Ships,” Reuters, October 9, 2025; Justin Katz, “White House, Finland

Sign Deal for Four Icebreakers,” Breaking Defense, October 9, 2025; Aaron-Matthew Lariosa, “Trumps Inks Deal for

American and Finnish Yards to Deliver First Arctic Security Cutters by 2028,” USNI News, October 9 (updated

October 10), 2025; Maritime Executive, “U.S. and Finland Reach $6 Billion Deal to Build Up to 11 Icebreakers,”

(continued...)

Congressional Research Service

4

Coast Guard Polar Security Cutter

On November 18, 2025, the United States, Finland, and Canada signed a joint statement of intent

reaffirming their collaboration under the October 2025 ICE Pact MOU.17

Current Coast Guard Polar Icebreakers

Overview

The Coast Guard’s operational polar icebreaker fleet currently consists of three ships: one heavy

polar icebreaker, Polar Star (Figure A-1 and Figure A-3 in Appendix A), and two medium polar

icebreakers, Healy (Figure A-4 in Appendix A) and Storis (Figure A-5 and Figure A-6 in

Appendix A). A second Coast Guard heavy polar icebreaker, Polar Sea—a sister ship of Polar

Star—suffered an engine casualty in June 2010 and has been nonoperational since then.

Heavy Polar Icebreaker Polar Star

Polar Star entered service in 1976 and is now well beyond its originally intended 30-year service

life.18 The Coast Guard in recent years has invested millions of dollars to overhaul, repair, and

extend the service life of the ship, but as a result of its advancing age, the ship’s material

condition has nevertheless become increasingly fragile, if not precarious. During its annual

deployments to McMurdo Station in Antarctica, shipboard equipment frequently breaks, and

shipboard fires have occurred.19 Replacements for many of the ship’s components are no longer

commercially available. To help keep Polar Star operational, the Coast Guard has used the nonoperational Polar Sea as a source of replacement parts.

Medium Polar Icebreakers Healy and Storis

Healy entered service in 2000. In February 2023, the Coast Guard issued a Request for

Information (RFI) from companies interested in conducting a service life extension project

(SLEP) for Healy that would begin in December 2025.20 Responses to the RFI were due by

March 16, 2023.21 A December 19, 2024, GAO report on Coast Guard acquisition of polar ships

Maritime Executive, October 9, 2025; Seapower Staff, “White House Selects Bollinger-Led International Team to

Build Six U.S. Coast Guard Arctic Security Cutters,” Seapower, October 10, 2025; Peter Rybski, “First Look at the

USA-Finland Icebreaker Deal,” Sixty Degrees North, October 11, 2025, which provides many details. See also Peter

Rybski, “Exclusive First Look at Davie/Helsinki Shipyard’s Arctic Security Cutter Design,” Sixty Degrees North,

August 21, 2025.

17 See, for example, U.S. Naval Institute Staff, “U.S., Canada and Finland Statement of Intent on the Icebreaker

Collaboration Effort Pact,” USNI News, November 19, 2025, which includes the text of the joint statement of intent;

“Canada Signs Joint Statement of Intent with Finland and United States to Advance Icebreaker Collaboration Effort,”

Associated Press, November 18, 2025.

18 The non-operational Polar Sea entered service in 1977 and is similarly well beyond its originally intended 30-year

service life.

19 See, for example, Richard Read, “Meet the Neglected 43-Year-Old Stepchild of the U.S. Military-Industrial

Complex,” Los Angeles Times, August 2, 2019; Melody Schreiber, “The Only Working US Heavy Icebreaker Catches

Fire Returning from Antarctica,” Arctic Today, March 2, 2019; Calvin Biesecker, “Fire Breaks Out on Coast Guard’s

Aging, and Only, Heavy Icebreaker,” Defense Daily, March 1, 2019.

20 The project is envisaged as being accomplished through five annual work periods, each beginning in December of a

given year and ending in April of the following year, with the first period beginning in December 2025 and ending in

April 2026, and the fifth period beginning in December 2029 and ending in April 2030.

21 See “Healy Service Life Extension Project (SLEP),” accessed November 19, 2024, at https://sam.gov/opp/

63af5d5f7b9e492dbdc6b106210f5716/view.

Congressional Research Service

5

Coast Guard Polar Security Cutter

states that the Coast Guard plans to conduct service life extension work on Healy in 2027-2031 at

an estimated cost of $97 million, with the aim of extending the ship’s life to at least 2035.22

On December 11, 2024, the Coast Guard purchased Aiviq, a U.S.-registered commercial ship that

was built in 2012 to serve as an Arctic oil-exploration support ship and that has an icebreaking

capability sufficient for the ship to serve as a Coast Guard medium polar icebreaker. The Coast

Guard purchased Aiviq for $125.0 million from Offshore Service Vessels of Cut Off, LA, a

subsidiary of Edison Chouest Offshore (ECO) of Cut Off, LA, a firm that operates more than 200

ships.23

The Coast Guard purchased Aiviq with $125.0 million in funding that the FY2024 Department of

Homeland Security (DHS) Appropriations Act (Division C of H.R. 2882/P.L. 118-47 of March

23, 2024) provided for purchasing an existing commercially available polar icebreaker and

modifying it into a Coast Guard polar icebreaker.24 In addition to its acquisition cost, the Coast

Guard reportedly expects to spend $25 million modifying the ship before it enters service.25

The Coast Guard completed acceptance of Aiviq on December 20, 2024, and renamed it Storis in

honor of a previous Coast Guard cutter of that name.26 On August 14, 2024, the Coast Guard

announced that it plans to homeport the ship in Juneau, AK.27 The ship was commissioned into

service with the Coast Guard on August 10, 2025. The Coast Guard reportedly aims to have it

operating from its Alaska home port starting the summer of 2026.28 The Coast Guard states that

22 Government Accountability Office, Coast Guard Acquisitions: Further Cost and Affordability Analysis of Polar

Fleet Needed, GAO-25-106822, Q&A Report to the Committee on Transportation and Infrastructure, House of

Representatives, December 19, 2024, pp. 5-6.

23

For more on ECO, see the firm’s website at https://chouest.com/.

24 Prior to 2021, the Coast Guard plans did not include the acquisition of a commercially available polar icebreaker.

The Coast Guard’s FY2022 UPL, dated June 29, 2021, however, included a $150.0 million item for the lease or

purchase of a commercially available vessel to provide polar icebreaking capability until the future delivery of PSCs.

(U.S. Coast Guard, FY 2022 Unfunded Priorities List, Report to Congress, June 29, 2021, p. 3.) The following year, the

Coast Guard as part of its proposed FY2023 budget requested $125.0 million in procurement funding for the purchase

of a commercially available polar icebreaker. Congress, in acting on the Coast Guard’s proposed FY2023 budget,

denied the request. The Coast Guard once again requested the $125.0 million as part of its proposed FY2024 budget,

and the FY2024 DHS Appropriations Act (Division C of H.R. 2882/P.L. 118-47 of March 23, 2024) approved the

request.

25 Malte Humpert, “Icebreaker ‘Aiviq’ to Join U.S. Coast Guard Before End of Year to Bolster Arctic Presence,”

gCaptain, November 14, 2024.

26 U.S. Coast Guard, “USCGC Storis Departs on Maiden Voyage,” press release dated June 4, 2025. The press release

states: “This is the second vessel in Coast Guard history to bear the name Storis. The original Storis, known as the

“Galloping Ghost of the Alaskan Coast,” had a storied history conducting 64 years of icebreaking operations in Alaska

and the Arctic before being decommissioned in 2007.”

27 U.S. Coast Guard, “U.S. Coast Guard Announces Juneau Homeporting for Future Icebreaker,” press release, August

14, 2024. See also Maritime Executive, “U.S. Coast Guard Closes In on Purchase of Icebreaker Aiviq,” Maritime

Executive, August 14, 2024; Heather Mongilio, “Coast Guard Names Juneau as Home Port for New Icebreaker,” USNI

News, August 15, 2024; James Brooks, “Coast Guard Confirms Plans to Buy Polar Icebreaker, Station It in Juneau,”

Alaska Beacon, August 17, 2024. The Coast Guard states: “Storis will be commissioned this August in Juneau, Alaska,

which will eventually be the vessel’s permanent homeport. Until the necessary shore infrastructure improvements are

completed in Juneau, Storis will be temporarily berthed in Seattle, Washington, with the Service’s two other polar

icebreakers.” (U.S. Coast Guard, “USCGC Storis Departs on Maiden Voyage,” press release dated June 4, 2025.)

28 See, for example, Edward Lundquist, “Aiviq Becomes USCGC Storis, to Be Based in Juneau,” Marine News,

February 2025; Malte Humpert, “Icebreaker ‘Storis’ Officially Joins U.S. Coast Guard Fleet,” gCaptain, January 6,

2025; Patricia Kime, “Coast Guard’s Newest Icebreaker to Honor Storis, the Historic Cutter Known for 6 Decades of

Service,” Military.com, December 9, 2024; Cal Biesecker, “Coast Guard Awards $125 Million To Offshore Service

Vessels For Commercial Icebreaker,” Defense Daily, November 26, 2024.

Congressional Research Service

6

Coast Guard Polar Security Cutter

acquisition of a commercially available polar icebreaker does not affect the acquisition of

the PSCs, and the vessel will not be included in the PSC program of record…. The future

Storis will provide near-term operational presence and support national security as a

bridging strategy until the full complement of PSCs is delivered.29

For additional background information on current U.S. polar icebreakers, see Appendix A.

Coast Guard Polar Icebreaker Procurement Programs

To recapitalize and expand its polar icebreaking fleet, the Coast Guard is planning to acquire new

heavy polar icebreakers called Polar Security Cutters (PSCs) and new medium polar icebreakers

called Arctic Security Cutters (ASCs).

Polar Security Cutter (PSC) Program

Overview

The PSC program was initiated in the Coast Guard’s FY2013 budget submission. The first PSC is

under construction; the Coast Guard expects the ship to be delivered no earlier than 2030.

Program Name and Name of First Ship

The PSC program was previously known as the polar icebreaker (PIB) program. Changing the

program’s name to the PSC program is intended to call attention to the fact that the Coast Guard’s

polar icebreakers perform a variety of missions relating to national security, not just

icebreaking.30 Although it is now called the PSC program, observers as a matter of convenience

might refer to it as the heavy polar icebreaker program. On February 24, 2022, the Coast Guard

announced that the first PSC will be named Polar Sentinel and that the Coast Guard has candidate

names in mind for the second and third PSCs.31

Home Port

On June 17, 2019, the Coast Guard announced that it intends to homeport PSCs at Seattle, WA,

where Polar Star and Healy are homeported.32

Coast Guard-Navy Integrated Program Office (IPO)

The PSC program is managed by a Coast Guard-Navy Integrated Program Office (IPO). A key

aim in establishing the IPO was to permit the Navy to share its ship-procurement best practices

with the Coast Guard so as to help the Coast Guard reduce the time and cost needed to design and

procure the PSCs.

29 U.S. Coast Guard, “Coast Guard Accepts Ownership of Commercially Available Polar Icebreaker,” news release

dated December 30, 2024.

30 See, for example, Ben Werner and Sam LaGrone, “Coast Guard Renames New Icebreaker Program ‘Polar Security

Cutter,’” USNI News, September 27, 2018. See also Sydney J. Freedberg Jr., “With Funding In Peril, Coast Guard

Pushes Icebreaker as ‘Polar Security Cutter,’” Breaking Defense, October 29, 2018.

31 See, for example, Richard R. Burgess, “Commandant Names Future Polar Security Cutter ‘Polar Sentinel,’”

Seapower, February 24, 2022.

32 See, for example, Ben Werner, “Coast Guard Polar Security Cutter Will Be Homeported in Seattle,” USNI News,

June 17, 2019; Navy Times Staff, “Coast Guard Picks Homeport for New Icebreaker Fleet,” Navy Times, June 17,

2019.

Congressional Research Service

7

Coast Guard Polar Security Cutter

Procurement Cost

The Coast Guard as of March 2025 estimated the total procurement cost of the first PSC at $2,397

million (i.e., about $2.4 billion).33

April 2019 Contract Award

On April 23, 2019, the Coast Guard-Navy IPO for the PSC program awarded a $745.9 million

fixed-price, incentive-firm contract for the detail design and construction (DD&C) of the first

PSC to Halter Marine Inc. of Pascagoula, MS, a shipyard that was then owned by Singapore

Technologies (ST) Engineering. Halter Marine was the leader of one of three industry teams that

competed for the DD&C contract; the other two bidders reportedly were Bollinger Shipyards of

Lockport, LA, and a partnership between Philly Shipyard of Philadelphia and

Fincantieri/Marinette Marine, of Marinette, WI.34 The DD&C contract includes options for

building the second and third PSCs. If both of these options are exercised, the total value of the

contract (excluding the March 2025 contract modification discussed below) would increase to

$1,942.8 million (i.e., about $1.9 billion).35 On December 29, 2021, the Coast Guard exercised a

$552.7 million fixed price incentive option to its contract with Halter Marine Inc. for the second

PSC.36

The above figures of $745.9 million, $552.7 million, and $1,942.8 million cover only the

shipbuilder’s portion of the PSCs’ total procurement cost as estimated in 2019; they do not

include the cost of government-furnished equipment (or GFE, meaning equipment that the

government purchases and then provides to the shipbuilder for incorporation into the ship), postdelivery costs, costs for Navy-specific equipment, or government program-management costs.

They also do not include the March 2025 contract modification discussed below.

In March 2025, the Coast Guard reportedly awarded Bollinger a contract modification for an

additional $951.6 million for the first PSC.37

Change in Contractor

In November 2022, ST Engineering sold Halter Marine to Louisiana-based Bollinger Shipyards.

The former Halter Marine is now called Bollinger Mississippi Shipbuilding.38 The shipyard’s

former name of Halter Marine occurs in the remainder of this report in connection with

33 Source: U.S. Coast Guard email to CRS of May 21, 2025.

34 “Mississippi Shipyard Gets $746M Contract for Icebreaker,” Associated Press, April 23, 2019.

35 See Naval Sea Systems Command, “Polar Security Cutter Contract Awarded to Recapitalize Nation’s Arctic

Capabilities,” April 23, 2019; Department of Defense, “Contracts for April 23, 2019” (Release No. CR-076-19); Sam

LaGrone, “VT Halter Marine to Build New Coast Guard Icebreaker,” USNI News, April 23, 2019; Maria Armental,

“U.S. Orders First Heavy Icebreaking Vessel in Decades, as Rivals Expand Arctic Presence,” Wall Street Journal,

April 23, 2019; “Mississippi Shipyard Gets $746M Contract for Icebreaker,” Associated Press, April 23, 2019.

36 U.S. Coast Guard, “Polar Security Cutter Integrated Program Office Exercises Option for Second Cutter,” U.S. Coast

Guard, December 30, 2021; Department of Defense, “Contracts for December 29, 2021.”

37 See, for example, Sam LaGrone, “Bollinger Awarded $951.6M for Modification for First Polar Security Cutter,”

USNI News, March 27, 2025; Maritime Executive, “US Awards $951M in Contract Modifications for Polar Cutter

Program,” Maritime Executive, March 26, 2025; Cal Biesecker, “Coast Guard Awards $952 Million Contract Mod To

Bollinger To Complete First Polar Icebreaker,” Defense Daily, March 25, 2025.

38 See, for example, Sam LaGrone, “Bollinger Closes $15M Acquisition of Halter Marine, New Name: ‘Bollinger

Mississippi Shipbuilding,’” USNI News, November 14, 2022; Cal Biesecker, “Bollinger Completes Acquisition of

Halter Marine,” Defense Daily, November 14, 2022; Justin Katz, “Why a Small Shipyard Merger Could Signal Bigger

Problems for the US Military,” Breaking Defense, November 14, 2022; Sam LaGrone, “Updated: Bollinger to Buy

Halter Marine Shipyard, Oversee Coast Guard Polar Security Cutter Program,” USNI News, November 6, 2022.

Congressional Research Service

8

Coast Guard Polar Security Cutter

developments prior to November 2022. As a result of this shipyard purchase, the program’s

contractor changed from Halter to Bollinger.

Lead Ship Delivery Date

Subsequent to the April 2019 contract award, the PSC program fell years behind schedule, in

large part due to the time needed to complete the design of the ship. The first PSC was originally

projected to be delivered in 2024, but as noted above, is now projected to be delivered no earlier

than 2030. Much of the delay in the delivery date occurred prior to Bollinger’s November 2022

purchase of Halter. The second and third PSCs reportedly are expected to be delivered in 2032

and 2034, respectively.39

Ship Design

Figure 1, Figure 2, Figure 3, Figure 4, and Figure 5 show renderings and a photograph of a

model of the design for the PSC. An April 25, 2019, press report states that “the Coast Guard and

Navy said VT Halter Marine’s winning design for the new PSC ‘meets or exceeds all threshold

requirements’ in the ship specification” for the PSC program.40 For additional information

regarding the design of the PSC, see Appendix B.

Figure 1. Rendering of Halter Marine Design for PSC

Source: Illustration accompanying Sam LaGrone, “UPDATED: VT Halter Marine to Build New Coast Guard

Icebreaker,” USNI News, April 23, 2019, updated April 24, 2019. The caption to the illustration states, “An

artist’s rendering of VT Halter Marine’s winning bid for the U.S. Coast Guard Polar Security Cutter. VT Halter

Marine image used with permission.”

39 Cal Biesecker, “Coast Guard Approved For Full Production Of First Polar Security Cutter,” Defense Daily, May 1,

2025.

40 Rich Abott, “Polar Icebreaker Winner Meets Threshold Requirements, Has Incentives for Early Delivery,” Defense

Daily, April 25, 2019.

Congressional Research Service

9

Coast Guard Polar Security Cutter

Figure 2. Model of Halter Marine Design for PSC

(Photograph of model displayed at 2021 trade show)

Source: Cropped version of photograph accompanying Peter Ong, “USGC’s Polar Security Cutters to Receive

Mark 38 Mod 4 Guns,” Naval News, April 21, 2022. The article credits the photograph to Naval News at the Sea

Air Space exposition 2021.

Figure 3. Rendering of Halter Marine Design for PSC

Source: Illustration posted by Robert A. Socha, Senior Vice President, Halter Marine, accessed May 6, 2019, at

https://www.linkedin.com/feed/update/urn:li:activity:6526621529113976832.

Congressional Research Service

10

Coast Guard Polar Security Cutter

Figure 4. Rendering of Halter Marine Design for PSC

Source: Technology Associates, Inc. (cropped version of rendering posted at http://www.navalarchitects.us/

pictures.html, accessed November 19, 2024). A similar image was included in Halter Marine press release, “VT

Halter Marine Awarded the USCG Polar Security Cutter,” May 7, 2019, accessed November 19, 2024, at

https://web.archive.org/web/20190513165621/http://www.vthm.com/public/files/20190507.pdf.

Figure 5. Rendering of Halter Marine Design for PSC

Source: Photograph accompanying Connie Lee, “New Coast Guard Icebreaker Remains on Tight Schedule,”

National Defense, May 21, 2020. The article credits the photograph to Technology Associated, Inc.

Congressional Research Service

11

Coast Guard Polar Security Cutter

Procurement Funding Through FY2024

As shown in Table 1, the PSC program received a total of about $1,731.8 million in procurement

funding through FY2024. This total reflects a rescission of $150.0 million in unobligated prioryear funding in the Coast Guard’s Procurement, Construction, and Improvements (PC&I) account

that was made by Section 543(10) of the FY2024 DHS Appropriations Act (Division C of H.R.

2882/P.L. 118-47 of March 23, 2024). The Coast Guard applied the rescission to the PSC

program’s FY2021 PC&I account appropriation, reducing it from the originally enacted figure of

$555.0 million to the figure shown in Table 1 of $405.0 million.

As also shown in Table 1, the PSC program received an additional $4.3 billion in procurement

funding in the FY2025 reconciliation act (H.R. 1/P.L. 119-21 of July 4, 2025, also known as the

One Big Beautiful Bill Act, or OBBBA).

Table 1. Procurement Funding for PSC Program

(In millions of dollars)

Appropriated

Fiscal year

Coast Guard

funding

Navy funding

Total funding

Requested by

Coast Guard

for that year

FY13

7.609

7.609

8.0

FY14

2.0

2.0

2.0

FY15

0.0

0.0

6.0

FY16

36.0

36.0

4.0

FY17

25.0

150.0

175.0

147.6

FY18

19.0

150.0

169.0

19.0

FY19

675.0

675.0

750.0

FY20

135.0

135.0

35.0

FY21

405.0

405.0

405.0

FY22

80.0

80.0

170.0

FY23

47.2

47.2

167.2

FY24

0

0

170.0

4,300.0

4,300.0

0

6,031.809

n/a

FY25 reconciliation act

Total

5,731.809

300.0

Source: U.S. Coast Guard and Navy budget data. Figures reflect post-enactment adjustments due to

reprogramming actions or recissions.

Notes: Coast Guard procurement funding shown in the table was provided through the PC&I account. (Prior to

FY2019, the PC&I account was called the Acquisition, Construction, and Improvements [AC&I] account.) Navy

procurement funding shown in the table was provided through the Shipbuilding and Conversion, Navy (SCN)

account (i.e., the Navy’s shipbuilding account). All procurement funding requested over the years for the PSC

program has been requested by the Coast Guard for the Coast Guard’s AC&I/PC&I account. The Navy

procurement funding provided in FY2017 and FY2018 was not requested by the Administration and was added

by Congress in marking up the Navy’s proposed FY2017 and FY2018 shipbuilding budgets. The FY2016 figure of

$36.0 million includes $30.0 million that was added after enactment through a reprogramming action, as noted in

the Coast Guard’s FY2018 budget submission. Section 543(10) of the FY2024 DHS Appropriations Act (Division

C of H.R. 2882/P.L. 118-47 of March 23, 2024) rescinded $150.0 million in unobligated prior-year funding for the

Coast Guard’s Procurement, Construction, and Improvements (PC&I) account. The Coast Guard applied the

Congressional Research Service

12

Coast Guard Polar Security Cutter

rescission to the PSC program’s FY2021 PC&I account appropriation, reducing it from the originally enacted

figure of $555.0 million to the figure shown in the table of $405.0 million. The FY2025 reconciliation act, also

known as the One Big Beautiful Bill Act (OBBBA), is H.R. 1/P.L. 119-21 of July 4, 2025.

Service Life Extension for Polar Star

The Coast Guard plans to extend the service life of Polar Star until the delivery of at least the

second PSC.41 The Coast Guard estimated the cost of Polar Star’s service life extension work at

$75 million, a sum that was funded at a rate of $15 million per year for five years, with the final

$15 million increment being provided in FY2023. The funding was included in the vessels

portion of the Coast Guard’s PC&I account, in a line item called “Polar Sustainment” that is

separate from the line items for the PSC and CAPI programs.

Arctic Security Cutter (ASC) Program

Overview

As mentioned earlier, the Coast Guard refers to its planned new medium polar icebreakers as

Arctic Security Cutters (ASCs).

April 2025 Request for Information (RFI)

On April 11, 2025, the Coast Guard released a Request for Information (RFI) for ASCs.

Responses to the RFI were due by April 25, 2025. The posting for the RFI states

The United States Coast Guard (USCG) is conducting market research to assess the current

capabilities of the U.S. and international maritime industrial base to support Arctic Security

Cutter (ASC) acquisition efforts. Specifically, the USCG is seeking to increase their

understanding of existing icebreaking capable vessels or vessel designs that are ready for

construction or already in production.

The USCG is also interested in proven execution and build strategies and the ability of

global shipyards to support the construction and subsequent launch of an icebreakingcapable vessel within 36-months of a contract award.42

An RFI document attached to the posting states the following (including the table of vessel

preliminary capability parameters):43

41 In February 2020, for example, the Coast Guard testified that

The Coast Guard also understands that we must maintain our existing heavy and medium

icebreaking capability while proceeding with recapitalization.... Maintenance of POLAR STAR

will be critical to sustaining this capability until the new PSCs are delivered. Robust planning

efforts for a service life extension project on POLAR STAR are already underway and initial work

for this project will begin in 2020, with phased industrial work occurring annually from 2021

through 2023. The end goal of this process will be to extend the vessel’s service life until delivery

of at least the second new PSC.

(Testimony of Admiral Charles W. Ray, Coast Guard Vice Commandant, on “Arctic Security

Issues,” before the House Homeland Security Subcommittee on Transportation & Maritime

Security, February 5, 2020, p. 9.)

42 “Request for Information—Arctic Security Cutter (ASC): Icebreaking Capable Vessels or Vessel Designs that are

Ready for Construction,” SAM.gov, accessed April 16, 2025, at https://sam.gov/opp/

ee911f0016fd4bb0b98d589cfcfc3dca/view.

43 U.S. Coast Guard, Request For Information (RFI), Arctic Security Cutter (ASC): Icebreaking Capable Vessels or

Vessel Designs that are Ready for Construction, p. 1. (Document attached to ASC RFI posted at SAM.gov, accessed

(continued...)

Congressional Research Service

13

Coast Guard Polar Security Cutter

The purpose of this RFI is to increase the USCG’s understanding of the current status and

capability of both the U.S. and broader international maritime industrial base as it pertains

to existing icebreaking capable vessels or vessel designs that are ready for construction or

already in production.

Specifically, the USCG seeks to understand what existing vessels or production ready

vessel designs satisfy or closely satisfy the below preliminary capability parameters.

Additionally, the USCG would like to gain insight on recently proven execution and build

strategies as well as the current capability and availability of global shipyards that could

support the construction and subsequent launch of an existing icebreaking capable vessel

design within THIRTY-SIX (36) months of a contract award date.

Regarding the figure of 36 months in the above-quoted passage, an April 3, 2025, blog entry

states that building icebreakers

shouldn’t be that hard. European shipyards, especially those located in Finland, routinely

design and build these specialized ships for a variety of purposes….

I recently wrote about Davie—the Canadian shipbuilder—and their plan to build their own

design polar icebreaker for the Canadian Coast Guard. According to a press report, 30% of

the ship will be built in Helsinki. Before the contract was awarded, Davie was advertising

that they could build this design in Helsinki in only 36 months.

How can the Finns do that? Often, U.S. Coast Guard Admirals and officials state before

Congress that Finland doesn’t build the kind of icebreakers they’re talking about. This PC2

[class] icebreaker [i.e., heavy polar icebreaker in U.S. parlance]—for the Canadian Coast

Guard—seems to be exactly that kind of icebreaker.44

December 2025 Contract Awards

On December 26, 2025, the Coast Guard awarded contracts for the construction of up to six

ASCs. Rauma Marine Constructions Oy (RMC) of Rauma, Finland, was awarded a contract to

build up two ASCs, with the first to be delivered in 2028. Bollinger Shipyards was awarded a

contract to build up to four ASCs at the firm’s shipyard in Houma, LA, with the first to be

delivered in 2029. RMC, Bollinger, Seaspan Shipyards of North Vancouver, Canada, and ship

design and engineering firm Aker Arctic Technology Oy of Helsinki, Finland, partnered to

April 16, 2025, at https://sam.gov/opp/ee911f0016fd4bb0b98d589cfcfc3dca/view.) See also Nick Blenkey, “USCG

Issues RFI for Icebreaking Arctic Security Cutter,” Marine Log, April 15, 2025; Justin Katz, “Coast Guard Seeks Info

on Medium Icebreaker Options from US, International Industry,” Breaking Defense, April 15, 2025; John Grady,

“Coast Guard Asking U.S., Foreign Yards for Arctic Security Cutter Pitches,” USNI News, April 16, 2025.

44 Peter Rybski, “How to Build an Icebreaker in Three Years,” Arctic Today, April 3, 2025.

Congressional Research Service

14

Coast Guard Polar Security Cutter

compete for the contracts. RMC and Bollinger will build the ASCs to a design based on the

Multi-Purpose Icebreaker (MPI) (Figure 6), an icebreaker design developed by Seaspan and Aker

Arctic.45

Figure 6. Rendering of Arctic Security Cutter (ASC)

Source: Rendering accompanying Nick Blenkey, “USCG Awards Bollinger and Finland’s RMC Contracts for Up

to Six Arctic Security Cutter Icebreakers,” Marine Log, December 29, 2025. A caption to the rendering credits

the rendering to Seaspan Shipyards.

Laws Relating to Building Ships in Foreign Shipyards

Some observers have suggested that a U.S. law known as the Jones Act prevents the U.S. Coast

Guard from buying or operating a foreign-built polar icebreaker. The Jones Act, however, does

not prevent the U.S. Coast Guard from buying or operating a foreign-built polar icebreaker, as the

operations of Coast Guard polar icebreakers do not fall under the Jones Act.46

45 See U.S. Coast Guard, “Coast Guard Awards Contracts to Build Arctic Security Cutters,” press release dated

December 26, 2025. See also “Seaspan Inks Deal with Bollinger, Rauma for U.S. Coast Guard ASC Program,” press

release dated January 7, 2025; Malte Humpert, “U.S. Signs Contracts With Foreign and Domestic Builders to Finally

Launch Long-Delayed Icebreaker Fleet Overhaul,” High North News, January 5, 2025; Nick Blenkey, “USCG Awards

Bollinger and Finland’s RMC Contracts for Up to Six Arctic Security Cutter Icebreakers,” Marine Log, December 29,

2025; Gary Warner, “Coast Guard Issues Contract to Build Icebreakers in Louisiana and Finland,” Stars and Stripes,

December 29, 2025.

46 The Jones Act (Section 27 of the Merchant Marine Act of 1920, P.L. 66-261) applies to vessels transporting

(continued...)

Congressional Research Service

15

Coast Guard Polar Security Cutter

Two other laws, however, are of note in connection with the idea of building a U.S. Coast Guard

polar icebreaker in a foreign shipyard. One is 14 U.S.C. §1151, which was added to the U.S. Code

by Section 26(a) of the Coast Guard Authorization Act of 1988 (H.R. 2342/P.L. 100-448 of

September 28, 1988). The provision states,

§1151. Restriction on acquisition, procurement, or construction of vessels in foreign

shipyards

(a) IN GENERAL.—Except as provided in subsection (b), the Commandant may not lease,

charter, or otherwise procure a vessel which contains a major component of the hull or

superstructure constructed in a foreign shipyard.

(b) EXCEPTIONS.—

(1) IN GENERAL.—The President may authorize exceptions to the prohibition in

subsection (a) when the President determines that it is in the national security interest of

the United States to do so.

(2) NOTICE.—The President shall transmit notice to the Committee on Transportation and

Infrastructure of the House of Representatives and the Committee on Commerce, Science,

and Transportation of the Senate of any such determination made by the President under

paragraph (1), and no contract may be awarded pursuant to the exception authorized until

the end of the 30-day period beginning on the date the notice of such determination is

received by such committees of Congress.

(3) JUSTIFICATION.—The notice required under paragraph (2) shall include a written

explanation of the national security interest and a detailed summary of market research

demonstrating the lack of availability of United States shipyards to meet the Coast Guard

requirements consistent with national security interest.47

The other is 10 U.S.C. §8679, which was added to the U.S. Code by Section 824(b) of the

FY1994 National Defense Authorization Act (NDAA) (H.R. 2401/P.L. 103-160 of November 30,

1993). The provision states,

§8679. Construction of vessels in foreign shipyards: prohibition

“merchandise” from one U.S. point to another U.S. point. It requires that such transportation be performed in U.S.-built

vessels owned by U.S. citizens and registered in the United States; U.S. registration, in turn, requires that crew

members be U.S. citizens. Merchandise is defined to include “merchandise owned by the U.S. Government, a State, or

a subdivision of a State; and valueless material” (46 U.S.C. §55102). Merchandise is further defined at 19 U.S.C.

§1401(c) to mean “goods, wares, and chattels of every description.” It is the waterborne transportation of merchandise

domestically that triggers the Jones Act. A vessel wishing to engage in such transportation would apply to the U.S.

Coast Guard for a “coastwise endorsement.” Thus, an icebreaker strictly performing the task it is designed for and not

transporting cargo from one U.S. point to another would not be subject to the Jones Act.

The federal agency in charge of deciding what kind of maritime activity must comply with the Jones Act, U.S. Customs

and Border Protection (CBP), has confirmed that icebreaking is not one of those activities. In a 2006 ruling, which

appears to be its most recent ruling on the subject, CPB informed Alcoa, Inc., that it could use foreign-built and

foreign-flagged vessels for icebreaking on the Hudson River in New York State. CBP reasoned that the transporting of

equipment, supplies, and materials used on or from the vessel in effecting its service is not coastwise trade, provided

that these articles are necessary for the accomplishment of the vessel’s mission and are usually carried aboard the

vessel as a matter of course. The 2006 ruling cited earlier rulings in 1974, 1985, and 2000 as precedent.

For more on the Jones Act, see CRS Report R45725, Shipping Under the Jones Act: Legislative and Regulatory

Background, by John Frittelli.

47 This is the text of 14 U.S.C. §1151 as amended by Section 7213(a) of the FY2026 National Defense Authorization

Act (NDAA) (S. 1071/P.L. 119-60 of December 18, 2025).

Congressional Research Service

16

Coast Guard Polar Security Cutter

(a) Prohibition.-Except as provided in subsection (b), no vessel to be constructed for any

of the armed forces,48 and no major component of the hull or superstructure of any such

vessel, may be constructed in a foreign shipyard.

(b) Presidential Waiver for National Security Interest.-(1) The President may authorize

exceptions to the prohibition in subsection (a) when the President determines that it is in

the national security interest of the United States to do so.

(2) The President shall transmit notice to Congress of any such determination, and no

contract may be made pursuant to the exception authorized until the end of the 30-day

period beginning on the date on which the notice of the determination is received by

Congress.

(c) Exception for Inflatable Boats.-An inflatable boat or a rigid inflatable boat, as defined

by the Secretary of the Navy, is not a vessel for the purpose of the restriction in subsection

(a).

As shown above, 14 U.S.C. §1151 and 10 U.S.C. §8679 both include a presidential waiver or

exception for the national security interest. On October 8, President Trump exercised the waiver

and exception for the national security interest for these two statutes.49

Total Number of Polar Icebreakers Existing or Under Contract

As shown in Table 2, the combination of Healy, Storis, up to three PSCs, and up to six ASCs

would produce a future polar icebreaking fleet of up to 11 ships, including up to three heavy polar

icebreakers (the three PSCs) and up to eight medium polar icebreakers (Healy, Storis, six ASCs).

Table 2. Total Number of Polar Icebreakers Existing or Under Contract

Coast Guard

stated

requirement

Existing

Under

contract

Total

existing

or under

contract

Heavy polar icebreakers

4 or 5

1 (Polar Star)

Up to 3 (PSCs)

Up to 4

Medium polar icebreakers

4 or 5

2 (Healy and Storis)

Up to 6 (ASCs)

Up to 8

Subtotal above

8 or 9

3

Up to 9

Up to 12

TOTAL following retirement of Polar Star

8 or 9

2

Up to 9

Up to 11

Source: Table prepared by CRS based on Coast Guard data.

Coast Guard Great Lakes Icebreakers

Current Fleet

The Coast Guard’s current Great Lakes icebreaker (GLIB) fleet consists of nine cutters:

•

one heavy icebreaker—Mackinaw (WLBB-30), a 240-foot ship displacing 3,500

tons (Figure 7);

48 14 U.S.C. §101, which establishes the Coast Guard, states the following: “The Coast Guard, established January 28,

1915, shall be a military service and a branch of the armed forces of the United States at all times.”

49 White House, “Construction of Arctic Security Cutters, Presidential Memoranda, October 8, 2025, accessed January

21, 2025, at https://www.whitehouse.gov/presidential-actions/2025/10/construction-of-arctic-security-cutters/.

Congressional Research Service

17

Coast Guard Polar Security Cutter

•

•

six 140-foot Bay-class icebreaking tugs displacing 662 tons each; and

two 225-foot Juniper-class seagoing buoy tenders displacing about 2,000 tons

each that have a light icebreaking capability.50

Figure 7. Great Lakes Icebreaker Mackinaw

Source: Cropped version of photograph at U.S. Coast Guard, “Coast Guard Assets, 240-foot Great Lakes

Class,” accessed April 15, 2025, at https://www.uscg.mil/Assets/Display/Article/1822555/240-foot-great-lakesclass/.

Although Mackinaw is referred to as a heavy icebreaker, the word heavy in this instance is being

used in the context of Great Lakes icebreaking—Mackinaw is much larger and has more

icebreaking capability than the eight other Great Lakes icebreaking ships listed above.51

Mackinaw would not, however, qualify as a heavy polar icebreaker, as it is much smaller and has

much less icebreaking capability than a heavy polar icebreaker.52

50 Source: U.S. Coast Guard, “Ninth Coast Guard District,” accessed November 19, 2024, at

https://www.atlanticarea.uscg.mil/Atlantic-Area/Units/District-9/Ninth-District-Units/. A total of 10 cutters are

assigned to the Ninth District, which is responsible for the Great Lakes, the Saint Lawrence Seaway, and parts of the

surrounding states. The 10th cutter assigned to the Ninth District is a 100-foot inland buoy tender whose primary

missions do not include icebreaking.

51 At continuous speeds of 3 knots, Mackinaw can break ice up to 32 inches thick, the 140-foot icebreaking tugs can

break ice up to 22 inches thick, and the 225-foot seagoing buoy tenders can break ice up to 14 inches thick.

52 As discussed earlier in this report, the Coast Guard’s two heavy polar icebreakers—the operational Polar Star and

the nonoperational Polar Sea—are 399 feet long and displace about 13,200 tons each. Polar Star can break ice up to

six feet (72 inches) thick at a continuous speed of 3 knots. The Coast Guard states that Mackinaw is equivalent to the

Canadian Coast Guard ship Samuel Risley, a Great Lakes-homeported icebreaker and buoy tender that Canada

classifies as a light icebreaker in a comparison conducted across its entire icebreaking fleet, including its Arctic

icebreakers. (U.S. Coast Guard, Great Lakes Icebreaking Mission Analysis, Fiscal Year 2016 Report to Congress,

August 30, 2016, p. 5.)

Congressional Research Service

18

Coast Guard Polar Security Cutter

New Great Lakes Icebreaker (GLIB)

Overview

Since at least 2009, some Members of Congress have expressed interest in bolstering the Coast

Guard’s Great Lakes icebreaking fleet by procuring a second icebreaker with capabilities

generally similar to those of Mackinaw.53 Prior to October 2021, the Coast Guard generally stated

that it did not view the procurement of additional GLIBs as an urgent near-term acquisition need,

given the capabilities of the current Great Lakes icebreaking fleet, the relatively young age of

Mackinaw (which entered service in 2006), service life extension work being done on the icebreaking tugs that is designed to add 15 years to their service lives, and Canada’s own Great

Lakes icebreaking capabilities.54 In October 2021, then-Commandant of the Coast Guard Admiral

Karl Schultz expressed support for procuring an additional heavy GLIB as part of a budget

reconciliation bill.55

The Coast Guard’s FY2024 budget initiated a program for procuring a new GLIB that would have

capabilities similar to those of Mackinaw. The ship’s total acquisition cost, the Coast Guard

estimates, might be roughly $350 million, depending in part on the exact design that is developed

for the ship.56 (In January 2024, the Government Accountability Office [GAO] reported that the

Coast Guard’s 2022 Mission Need Statement for domestic icebreaking estimated the procurement

cost of a heavy domestic icebreaker at $216.3 million as of 2020.57)

53 See, for example, H.R. 1747 of the 111th Cong., the Great Lakes Icebreaker Replacement Act, which was introduced

on March 26, 2009, reported by the Committee on Transportation and Infrastructure on April 21, 2009 (H.Rept. 11181), and agreed to by the House by voice vote on April 27, 2009. A similar bill, S. 1024, was introduced in the Senate

on May 12, 2009.

54 A 2016 Coast Guard report to Congress on the Great Lakes icebreaking mission, for example, stated the following:

The current mix of heavy and medium [Great Lakes] icebreakers is capable of managing priorities

and requests for icebreaking in Tier 1 and 2 waterways. When a severe ice season stresses Coast

Guard asset capabilities, the existing agreement and partnership with Canada fills the capability gap

and brings in extra heavy-icebreaking resources to manage the ice.... [T]he 2014 and 2015 ice

seasons were a 20-year anomaly, consuming almost twice as many cutter resource hours as in any

other year since 2005.

The Coast Guard cannot reliably predict the economic impact of maintaining a single heavy Great

Lakes icebreaker. Additionally, given the extreme conditions when ice coverage exceeds 90

percent, it is not clear that shipping delays would be significantly mitigated by an increase in

icebreaking capability. Delays can be associated with several factors such as slow transit speeds,

availability of pilots, and simultaneous and competing demand signals for icebreaking services

across the Great Lakes.

(U.S. Coast Guard, Great Lakes Icebreaking Mission Analysis, Fiscal Year 2016 Report to

Congress, August 30, 2016, p. 11. The report was required by S.Rept. 114-68 of June 18, 2015, the

Senate Appropriations Committee’s report on S. 1619, the Department of Homeland Security

Appropriations Bill, 2016 (see page 75).)

55 Admiral Schultz expressed support for procuring an additional heavy Great Lakes icebreaker as part of a budget

reconciliation bill as part of his testimony at an October 19, 2021, hearing on Coast Guard oversight before the Oceans,

Fisheries, Climate Change, and Manufacturing subcommittee of the Senate Commerce, Science, and Transportation

Committee.

56 Source: Coast Guard email to CRS, May 1, 2024.

57 GAO, Coast Guard: Improved Reporting on Domestic Icebreaking Performance Could Clarify Resource Needs and

Tradeoffs, GAO-24-106619, January 16, 2024, Table 1 on page 8. In a footnote to the table, GAO states that “the actual

costs [for items shown in the table] are likely to be higher than reported because the estimates do not include other

costs, such as shore infrastructure costs at port locations that the Coast Guard has not yet determined.”

Congressional Research Service

19

Coast Guard Polar Security Cutter

March 1, 2024, Hearing

On March 1, 2024, the Oceans, Fisheries, Climate Change, and Manufacturing subcommittee of

the Senate Commerce, Science, and Transportation Committee held a field hearing in Green Bay,

WI, on the importance of Great Lakes icebreaking to the regional economy.58 At this hearing,

Admiral Linda Fagan, Commandant of the Coast Guard, testified:

The Coast Guard recently completed a Fleet Mix Analysis which recommended a future

fleet of in-kind capacity to replace [the Coast Guard’s] current [Great Lakes icebreaking]

fleet. The results showed a need for another heavy domestic icebreaker to meet future

service needs across the Great Lakes. The ability to achieve continued success in this

mission and reliably facilitate navigation within the MTS [marine transportation system]

year-round requires sustainment and modernization of the Coast Guard’s domestic

icebreaking fleet, and I am committed to developing the next system of icebreaking assets.

Consistent with Congressional direction, we are focused on acquiring a second heavy

domestic icebreaker, at least as capable as CGC [Coast Guard cutter] Mackinaw. We

established a Great Lakes Icebreaking Program Management Office to analyze

requirements for the next generation of domestic icebreaking capability and have

completed pre-acquisition activities, readying the Service to advance upon receipt of an

appropriation. The FY 2024 President’s Budget requests $55 million to fund initial

acquisition activities and prepare for the purchase of long lead time materials for a second

heavy domestic icebreaker. I look forward to continuing to work with Congress to support

this acquisition.59

January 2024 GAO Report

A January 16, 2024, GAO report on U.S. domestic icebreaking performance stated

The Coast Guard conducts domestic icebreaking operations in three of its nine districts—

the Great Lakes, New England, and the Mid-Atlantic.

In the Great Lakes, 55 percent of the regional economy is dependent on key shipping

channels, according to the Coast Guard. In 2020, industries shipped 100 million tons of

iron ore, limestone, coal, and other commodities through the Great Lakes, according to

data from the Army Corps of Engineers Waterborne Commerce Statistics Center. Some

industry stakeholders who rely on these shipping channels have raised questions about

whether the Coast Guard has adequate icebreaking resources available to facilitate

commerce.

Section 11212 of the James M. Inhofe National Defense Authorization Act for Fiscal Year

2023 [H.R. 7776/P.L. 117-263 of December 23, 2022] includes a provision for GAO to

review Coast Guard icebreaking operations in the Great Lakes and examine proposed

performance standards for the Coast Guard’s Great Lakes icebreaking program. This report

discusses the associations between ice coverage on the Great Lakes and effects on certain

economic indicators, the Coast Guard’s icebreaking resource needs, and the potential

effects of the proposed standards on the Coast Guard’s icebreaking efforts.

Key Takeaways

•

Great Lakes vessel-based commerce declines during the winter, primarily due to lock

closures and weather conditions. We found that the amount of ice coverage on the

58 For details on this hearing, see https://www.commerce.senate.gov/2024/3/importance-of-great-lakes-icebreaking-to-

the-regional-economy.

59 Testimony of Admiral Linda L. Fagan, Commandant, U.S. Coast Guard, on “The Importance of Great Lakes

Icebreaking to the Regional Economy” before the Senate Committee on Commerce, Science, and Transportation

Subcommittee on Oceans, Fisheries[,] Climate Change, and Manufacturing, March 1, 2024, p. 4.

Congressional Research Service

20

Coast Guard Polar Security Cutter

Great Lakes was generally not associated with selected economic indicators we

examined, such as regional unemployment rates and unfilled orders for steel

production. Industries may mitigate the effects of delays caused by ice coverage, such

as stockpiling iron ore inventory to maintain steel production throughout the winter.

•

The Coast Guard identified heavy icebreaking capability gaps and its reliance on an

aging fleet as risks to its ability to conduct its domestic icebreaking mission. As a

result, the Coast Guard anticipates needing at least $3 billion in lifecycle costs to

replace and acquire new vessels for domestic icebreaking.

•

The proposed standards for the Coast Guard’s domestic icebreaking program will

largely not have an operational impact. The proposed standards may lead to

improvements in data collection and reporting, which could help the Coast Guard

better communicate its resource needs and tradeoffs. However, the data collection

efforts may increase operating costs and information sharing needs with industry,

according to the Coast Guard.

•

We recommend that the Coast Guard, using data it already collects, report more

complete information on its icebreaking performance to better articulate its resource

needs and tradeoffs.60

Issues for Congress

Overview

Issues for Congress regarding Coast Guard polar icebreakers include the following:

•

•

•

•

•

program-execution risk (i.e., the risk of cost growth, schedule delay, or technical

problems) in the PSC and ASC programs;

Coast Guard intentions regarding the procurement of a fourth or fifth PSC, so as

to meet the stated requirement (following the retirement of Polar Star) for a total

of four or five heavy polar icebreakers;

the total number of ASCs that will eventually be built, given the two existing

medium polar icebreakers (Healy and Storis) and the stated requirement for a

total of four or five medium polar icebreakers;

whether required numbers of polar icebreakers would increase, and if so, by how

many ships, if Greenland were to become part of the United States; and

whether the building some ASCs in Finland should serve as a model for building

ships for the U.S. Navy in foreign shipyards.

Discussions of Selected Issues

The following sections provide additional discussion of some of the above issues.

60 GAO, Coast Guard: Improved Reporting on Domestic Icebreaking Performance Could Clarify Resource Needs and

Tradeoffs, GAO-24-106619, January 16, 2024, pp. 1-2.

Congressional Research Service

21

Coast Guard Polar Security Cutter

Program-Execution Risk

February 2025 GAO Report

Regarding program-execution risk in the PSC program, a February 2025 GAO report assessing

DHS acquisition programs states the following regarding the PSC program:

Key Findings

• Cost and Schedule. The program indicated in November 2023 that it would breach its

cost and schedule goals. It planned to rebaseline those goals by seeking approval from DHS

in December 2024. As of November 2024, the cost estimate is expected to grow by over

20 percent above the previous baseline of $3.3 billion but is not yet completed. Program

officials stated that they plan to seek approval for the new baseline before completing

ongoing contract negotiations with the shipbuilder.

• Design and Construction. Design immaturity continues to delay the start of construction,

which the program originally planned for 2021. With 81 percent of functional design

complete more than 5 years after the award of the detail design contract, the Coast Guard

has not yet met its standard of 95 percent completion before starting construction. As of

November 2024, the Coast Guard reported authorizing six of the 85 total sections of the

ship to help inform full production, but none are finished….

Program History and Acquisition Strategy

The Coast Guard established its initial acquisition program baseline for the PSC program

in 2018 and has revised it twice, once in 2021 to reflect higher costs and a delayed schedule

and in 2022 due to schedule delays related to COVID-19…. We previously made

recommendations to help the program maintain its cost and schedule baselines. For

example: (1) To implement recommendations we made in 2018, the program conducted a

technology readiness assessment, reevaluated its cost estimate, and identified and mitigated

schedule risks (GAO-18-600), and (2) In 2023, we made a priority recommendation to

DHS to ensure design is mature prior to authorizing lead ship construction. DHS concurred

with the recommendation. As of August 2024, this recommendation remains open (GAO23-105949).

Cost and Schedule Status

In November 2023, the program notified DHS that it would breach its cost and schedule

goals. As of November 2024, the program is planning to update its acquisition program

baseline by the end of 2024. The program’s notional schedule as of November 2023

indicates the lead PSC will be delivered in late 2029—a delay of over 5 years since initial

plans. The program had planned to complete its cost estimate by September 2024 but still

had not done so by November 2024. However, when the program declared the cost breach,

it reported costs had exceeded at least 20 percent of the previous goal of $3.3 billion.

Program officials said that the cost and schedule increases are attributable to several factors

including the lack of U.S. shipbuilding expertise for designing and constructing heavy

polar icebreakers, the complexity of and changes to the design, and the effects of the

COVID-19 pandemic on the program’s planned activities.

In October 2023, the shipyard requested restructuring of the contract’s detail design and

construction line items because it determined it could not meet the original contract terms.

In April 2024, the Coast Guard made several modifications to the contract, including

changing the line item for advance planning, engineering, and design for the lead ship from

a fixed-price incentive to a firm-fixed-price contract type. Program officials do not have

an anticipated completion date for contract restructuring as negotiations are ongoing.

However, officials said that they plan to finalize the updated acquisition program baseline

Congressional Research Service

22

Coast Guard Polar Security Cutter

before negotiations are completed, which introduces uncertainty with the forthcoming cost

and schedule goals.

Design and Construction

Design immaturity continues to be a top program risk, even though program officials said

they entered the critical design review in September 2024. As of September 2024, and after

more than 5 years of work since the contract was awarded, functional design is

approximately 81 percent complete. As a result, it is unlikely that the design will be mature

enough to start construction on the lead PSC by the end of 2024. Program officials said

they aim to have 95 percent of the functional design complete to start construction by that

time, which is inconsistent with ship design leading practices we previously identified.

To address slower than expected design progress, program officials said that the shipyard

brought on additional engineering personnel to accelerate design maturity. Program

officials said that the shipyard demonstrated completion of significant design work as of

the September 2024 critical design review. Further, they said that the Coast Guard will

seek approval from DHS to begin lead ship construction in December 2024.

In July 2023, the Coast Guard reported authorizing production of the first of 85 total

sections for the ship, an incremental approach to production. As of July 2024, the first

section is over half complete. As of November 2024, the shipyard has since begun

production on six total sections to build workforce capability, test new processes and

equipment, and reduce production risk while design matures.

Coast Guard officials stated that the program conducted cybersecurity assessments in 2023

and 2024 and deemed the results as classified.

Program Office Comments

We provided a draft of this assessment to the program office for review and comment. The

program office provided technical comments, which we incorporated where appropriate.

In this assessment, we included information for key events as of November 2024 to the

extent it was provided by the Coast Guard.61

December 2024 GAO Report

A December 19, 2024, GAO report on Coast Guard acquisition of polar ships states,

Key Takeaways

• The Coast Guard is considering multiple efforts to expand its polar icebreaker fleet from

the current two to either eight or nine. However, it has yet to determine the mix of medium

and heavy polar icebreakers, known as Arctic Security Cutters and Polar Security Cutters,

respectively, or the associated costs that are a part of its long-term strategy.

• To address near-term gaps, the Coast Guard plans to extend the service life of its two

operational polar icebreakers. It also plans to purchase and convert a commercially

available polar icebreaker (CAPI), something it has never done before. But it lacks

information on the full cost to do so.

• We recommend that the Coast Guard develop a detailed cost estimate for the CAPI and

that it develop an analysis of the cost and sequencing for the planned polar icebreaker fleet

expansion within the context of its larger acquisition portfolio and priorities. DHS did not

concur with the first recommendation and did concur with the second….

61 Government Accountability Office, DHS Annual Assessment[;} Improved Guidance on Revised Acquisition Goals

Would Enhance Transparency, GAO-25-107317, February 2025, pp. 66-67.

Congressional Research Service

23

Coast Guard Polar Security Cutter

What are some open questions that remain for the Coast Guard to answer as it plans

its future polar icebreaker fleet?

The Coast Guard faces many questions as it expands its polar icebreaking fleet in the

coming decades. However, it has already started planning this expansion without a

complete understanding of how to achieve its goals. It will gain information to answer

some questions as the planning progresses for a potential Arctic Security Cutter program.

But other answers are external to that effort and have potential implications for other

programs, such as any expansion of the Polar Security Cutter program to build more than

three cutters. Some open questions that remain for the Coast Guard related to the polar

icebreaker fleet expansion are listed below (see fig. 4).

Congressional Research Service

24

Coast Guard Polar Security Cutter

… With so many questions unanswered, the Coast Guard has yet to make a business case

to adequately support committing resources to expanding its polar fleet to its desired state

of eight to nine polar icebreakers. As we have previously found, high levels of uncertainty

set up programs for poor outcomes. In this case, any poor outcomes would be compounded

because multiple programs are involved. Moving forward without better understanding the

commitments, costs, and affordability may bind the Coast Guard to a portfolio that cannot

be executed.

Congressional Research Service

25

Coast Guard Polar Security Cutter

Conclusions

The Coast Guard is working to increase its presence in the Arctic region and expand the

polar icebreaking fleet. Polar icebreaker programs take over a decade to deliver a

capability, so the Coast Guard is trying to add an existing commercial icebreaker to its fleet

sooner by purchasing and converting it within 2 years. But it does not understand the likely

cost of this effort, such as the full cost of converting a commercially available polar

icebreaker or what modifications it will need to make. The Coast Guard has prepared a

rough estimate, which is not sufficient to inform a budget request, and lacks updated

information now that a specific polar icebreaker has been identified. To meet its time frame

of 2 years, it plans to purchase the icebreaker and figure out the detailed cost estimate for

any modifications later.

The Coast Guard is already beset by affordability challenges in its portfolio of major

acquisition programs within a constrained budget environment to support the missions it

performs. However, it has not yet shown how it could achieve its goal to enlarge the polar

fleet to eight or nine polar icebreakers.

It is not too late for the Coast Guard to get more information since it has yet to make

financial commitments outside of the first three Polar Security Cutters. As the Coast Guard

moves forward, it could develop more detailed cost estimates and determine if it can afford

its plans within the context of its larger acquisition portfolio. Doing so could help the Coast

Guard take a step in the right direction to determine what it can afford and when, among

its many acquisition priorities. Finally, these plans will demonstrate whether the necessary

resources will be there when the Coast Guard is ready to move forward or what trade-offs

it can make to better position itself to fill its capability gaps.62

Potential Impact of Greenland Annexation on Required Numbers of

Icebreakers

If Greenland were to become a part of the United States, requirements for U.S. polar icebreakers

could increase due to a need for performing icebreaking and other U.S. Coast Guard missions in

waters surrounding Greenland. Baffin Bay, which separates Greenland from Canada’s Baffin

Island, forms part of the Northwest Passage linking the North Atlantic to the North Pacific via the

Canadian archipelago, the north coast of Alaska, and the Bering Strait. As discussed in a CRS

report on Arctic issues, under a May 2011 agreement among the eight Arctic states on cooperation

on aeronautical and maritime search and rescue (SAR) in the Arctic, Denmark currently has

primary responsibility for conducting SAR operations in coastal waters surrounding Greenland.63

If Greenland were to become part of the United States, primary responsibility for conducting

SAR operations in these waters could shift to the United States.

62 Government Accountability Office, Coast Guard Acquisitions: Further Cost and Affordability Analysis of Polar

Fleet Needed, GAO-25-106822, Q&A Report to the Committee on Transportation and Infrastructure, House of

Representatives, December 19, 2024, pp. 1, 11-13.

63 CRS Report R41153, Changes in the Arctic: Background and Issues for Congress, coordinated by Ronald O'Rourke.

Congressional Research Service

26

Coast Guard Polar Security Cutter

Use of Foreign Shipyards for Building U.S. Navy Ships

As discussed in two CRS reports on Navy shipbuilding programs,64 President Trump,65 some

other U.S. officials,66 and other observers67 have suggested or advocated using foreign

shipyards—particularly shipyards in South Korea and/or Japan—to build ships for the U.S. Navy,

at least as a stop-gap measure until U.S. shipbuilding capacity constraints can be alleviated. Other

observers oppose proposals for using foreign shipyards to build ships for the U.S. Navy.68

Supporters of building ships for the Navy in foreign shipyards could argue that building some of

the Coast Guard’s ASCs in shipyards in Finland can serve as a model for building some ships for

the Navy in foreign shipyards. Opponents of building ships for the Navy in foreign shipyards

could argue that building some of the Coast Guard’s ASCs in shipyards in Finland should be

viewed as a one-time exception to a longstanding pattern of using only U.S. shipyards to build

ships for the U.S. armed services.

64 CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by

Ronald O'Rourke; CRS Report R44972, Navy Constellation (FFG-62) and FF(X) Class Frigate Programs:

Background and Issues for Congress, by Ronald O'Rourke.

65 See, for example, Rich Abott, “DoD Advisor Confirms Potential To Build Navy Warships Outside U.S. Akin To ICE

Pact,” Defense Daily, December 11, 2025; Howard Altman, “Trump Considering Buying Foreign Ships To Make Up

Gap With China,” The War Zone, April 11, 2025; Song Sang-ho, “Trump Says U.S. May Buy ‘Top-Of-The-Line’

Ships from ‘Close’ Countries,” Yonhap, April 11, 2025; Oh Sam-Gwon, “Korean Shipbuilders Gear Up as Trump

Suggests U.S. May Buy Warships,” Korea JoongAng Daily, April 11, 2025; Tom Sharpe, “Trump Plans to Rebuild the

US Navy in Korean Shipyards. We Already Know This Works Well,” Telegraph (UK), January 9, 2025; Morgan

Phillips, “Trump Threatens to Tap Allies for Military Shipbuilding if US Can't Produce,” Fox News, January 7, 2025;

Joe Gould, “Trump Hints Pentagon Could Lean on Allies to Build Warships,” Politico Pro, January 6, 2025.

66 See, for example, Daryl Caudle, “Winning the Long Game: Sustaining Sea Power as Our Enduring Advantage,”

Defense News, December 18, 2025, in which the author—the Chief of Naval Operations—states (emphasis added):

“Until American [ship]yards fully recover from workforce shortages, supply chain fragility and lack of automation, we

are exploring responsible cooperation with allied shipbuilders in places like South Korea and Japan to bridge near-term

gaps in maintenance, repair and production.” See also “U.S. Navy Looks to Korean and Japanese Shipyards to Address

Submarine and Destroyer Delays,” Army Recognition, November 26, 2025; Kim Hyun-soo, “Arms Agency, U.S. Navy

Discuss Cooperation on Naval Shipbuilding, MRO,” Yonhap, August 8, 2025.

67 See, for example, Jennifer Hlad, “Can Partner Nations Help Solve the Navy’s Shipbuilding Woes?” Defense One,

November 24, 2025; Maritime Executive, “South Korean Yards Want to Build U.S. Navy Ships in Korea,” Maritime

Executive, November 16, 2025; Jihoon Yu, “ROK–U.S. Shipbuilding Cooperation Matters for Maritime Power,” Real

Clear World, December 17, 2025; Juliana Liu, “South Korea Is the Answer to America’s Naval Problem,” Bloomberg,

December 4, 2025; Brad Lendon, Gawon Bae, Yoonjung Seo, Mike Valerio, and Charlie Miller, “US Navy

Shipbuilding Is ‘a Mess.’ South Korean companies Think They Can Help Fix It,” CNN, updated October 20, 2025;

William Hawkins, “Trade Is Not What Matters Most,” U.S. Naval Institute Proceedings, July 2025; Namyeon Kwon,

“Don’t Miss the Boat: Considerations for U.S.-South Korea Maritime Cooperation,” Center for Strategic and

International Studies (CSIS), June 12, 2025; Steve Forbes, “Making Our Navy Supreme Again,” Forbes, May 27,

2025; Arjun Akwei and Jinwan Park, “Trump Wants More Ships? Korea Stands Ready to Help Build Them,” The Hill,

May 8, 2025; Miyeon Oh and Michael Cecire, “Why the United States, South Korea, and Japan Must Cooperate on

Shipbuilding,” RAND, May 6, 2025; “South Korea Offers to Build Five Aegis Destroyers per Year to Help the US

Counter China at Sea,” Army Recognition, April 11, 2025; Fatima Bahtić, “Facing New Realities amid Rising Costs:

Could Future US Navy Warships Be Built at Foreign Shipyards?” NavalToday.com, February 17, 2025; Peter Suciu,

“The 21st Century U.S. Navy Might Be Built in South Korea,” National Interest, January 9, 2025; Brian T. Di Mascio,

“Foreign Shipyards Can Help the U.S. Navy Build Its Fleet,” U.S. Naval Institute Proceedings, October 2024; Douglas

Robb, “Japan, South Korea and the US Should Mirror AUKUS for Destroyers,” Defense News, October 5, 2023; Brad

Lendon, “These May Be the World’s Best Warships. And They’re Not American,” CNN, June 3, 2023.

68 See, for example, Rebecca Grant, “6 Reasons to Say ‘No Thanks’ to Building U.S. Navy Warships in South Korea,”

Real Clear Defense, July 30, 2025; Matthew Paxton, “Outsourcing the US Shipyard Industrial Base Will Outsource

American Sovereignty,” Breaking Defense, August 5, 2024; Shipbuilders Council of America, “‘We Stand Ready’ Ad

Campaign Shows American Shipbuilders Can Deliver the Fleet of the Future,” undated, accessed January 4, 2026.

Congressional Research Service

27

Coast Guard Polar Security Cutter

Appendix A. Current U.S. Coast Guard Polar

Icebreakers

This appendix provides additional background information on current U.S. Coast Guard polar

icebreakers

Polar Icebreakers

Heavy Polar Icebreaker Polar Star

The heavy polar icebreakers Polar Star (WAGB-10) and Polar Sea (WAGB-11)69 (Figure A-1,

Figure A-2, and Figure A-3) are sister ships built to the same general design. Polar Star is

operational; Polar Sea suffered an engine casualty in June 2010 and has been nonoperational

since then.

Figure A-1. Polar Star and Polar Sea

(Side by side in McMurdo Sound, Antarctica)

Source: Coast Guard photograph that was accessed on November 19, 2024, at https://web.archive.org/web/

20080917122344/http://www.uscg.mil/pacarea/cgcpolarsea/history.asp. The photograph accompanies Kyung M.

Song, “Senate Passes Cantwell Measure to Postpone Scrapping of Polar Sea Icebreaker,” Seattle Times, September

22, 2012, accessed November 19, 2024, at https://web.archive.org/web/20121116160404/http://

69 The designation WAGB means Coast Guard icebreaker. More specifically, W means Coast Guard ship, A means

auxiliary, G means miscellaneous purpose, and B means icebreaker.

Congressional Research Service

28

Coast Guard Polar Security Cutter

blogs.seattletimes.com/politicsnorthwest/2012/09/22/senate-passes-cantwell-measure-to-postpone-scrapping-ofpolar-sea-icebreaker/.

Figure A-2. Polar Star

Source: Cropped version of photograph accompanying U.S. Navy, Naval Sea Systems Command, “U.S. Coast

Guard’s Polar Star Cuts through Ice with help of NSWCPD,” January 23, 2024, accessed April 17, 2024, at

https://www.navsea.navy.mil/Media/News/Article-View/Article/3653655/us-coast-guards-polar-star-cuts-throughice-with-help-of-nswcpd/. The caption to the photograph credits the photograph to “U.S. Navy photo by Senior

Chief Mass Communication Specialist RJ Stratchko.”

The two ships were procured in the 1970s as replacements for earlier U.S. icebreakers. They were

designed for 30-year service lives, and were built by Lockheed Shipbuilding of Seattle, WA, a

division of Lockheed that also built ships for the U.S. Navy, but which exited the shipbuilding

business in the late 1980s.

The ships are 399 feet long and displace about 13,200 tons. They are among the world’s most

powerful nonnuclear-powered icebreakers, with a capability to break through ice up to 6 feet

thick at a speed of 3 knots. Because of their icebreaking capability, they are referred to (in U.S.

parlance) as heavy polar icebreakers. In addition to a crew of 134, each ship can embark a

scientific research staff of 32 people.

Polar Star was commissioned into service in 1976, and consequently is well beyond its originally

intended 30-year service life. Due to worn-out electric motors and other problems, the Coast

Guard placed the ship in caretaker status on July 1, 2006.70 Congress in FY2009 and FY2010

provided funding to repair Polar Star and return it to service for 7 to 10 years. The repair work

70 Source for July 1, 2006, date: U.S. Coast Guard email to CRS on February 22, 2008. The Coast Guard’s official term

for caretaker status is “In Commission, Special.”

Congressional Research Service

29

Coast Guard Polar Security Cutter

was completed at a reported cost of about $57 million, and the ship was reactivated on December

14, 2012.71

Figure A-3. Polar Sea

Source: Coast Guard photograph that was accessed April 17, 2025, at https://web.archive.org/web/

20160229010100/http://www.uscg.mil/pacarea/cgcpolarsea/img/PSEApics/FullShip2.jpg. The photograph

accompanies Associated Press, “Reprieve for Seattle-Based Icebreaker Polar Sea,” KOMO News, June 15, 2012,

accessed April 17, 2025, at https://komonews.com/news/local/reprieve-for-seattle-based-icebreaker-polar-sea.

Although the Coast Guard in recent years has invested millions of dollars to overhaul, repair, and

extend the service life of Polar Star, the ship’s material condition, as a result of its advancing age,

has nevertheless become increasingly fragile, if not precarious. During its annual deployments to

McMurdo Station in Antarctica, shipboard equipment frequently breaks, and shipboard fires

sometimes occur.72 Replacements for many of the ship’s components are no longer commercially

available. To help keep Polar Star operational, the Coast Guard has used Polar Sea as a source of

replacement parts.

Polar Sea was commissioned into service in 1977, and consequently is also well beyond its

originally intended 30-year service life. In 2006, the Coast Guard completed a rehabilitation

project that extended the ship’s expected service life to 2014. On June 25, 2010, however, the

Coast Guard announced that Polar Sea had suffered an engine casualty, and the ship was

unavailable for operation after that.73 The Coast Guard placed Polar Sea in commissioned,

inactive status on October 14, 2011. The Coast Guard transferred certain major equipment from

71 See, for example, Kyung M. Song, “Icebreaker Polar Star Gets $57 Million Overhaul,” Seattle Times, December 14,

2012.

72 See, for example, Richard Read, “Meet the Neglected 43-Year-Old Stepchild of the U.S. Military-Industrial

Complex,” Los Angeles Times, August 2, 2019; Melody Schreiber, “The Only Working US Heavy Icebreaker Catches

Fire Returning from Antarctica,” Arctic Today, March 2, 2019; Calvin Biesecker, “Fire Breaks Out on Coast Guard’s

Aging, and Only, Heavy Icebreaker,” Defense Daily, March 1, 2019.

73 “Icebreaker POLAR SEA Sidelined by Engine Troubles,” Coast Guard Compass (Official Blog of the U.S. Coast

Guard), June 25, 2010. See also “USCG Cancels Polar Icebreaker’s Fall Deployment,” DefenseNews.com, June 25,

2010; Andrew C. Revkin, “America’s Heavy Icebreakers Are Both Broken Down,” Dot Earth (New York Times blog),

June 25, 2010.

Congressional Research Service

30

Coast Guard Polar Security Cutter

Polar Sea to Polar Star to facilitate Polar Star’s return to service,74 and, as mentioned above, has

since used Polar Sea as a source of repair parts for Polar Star.

Medium Polar Icebreaker Healy

Healy (WAGB-20) (Figure A-4) was funded in the early 1990s as a complement to Polar Star

and Polar Sea, and was commissioned into service on August 21, 2000.

Figure A-4. Healy

Source: Coast Guard photograph accessed November 19, 2024, at https://www.history.uscg.mil/US-CoastGuard-Photo-Gallery/igphoto/2002136680/.

The procurement of Healy was funded largely (about 89%) through the Navy’s shipbuilding

account (i.e., the Shipbuilding and Conversion, Navy, or SCN account).75 The ship was built by

74 Source: October 17, 2011, email to CRS from Coast Guard Congressional Affairs office. Section 222 of the Coast

Guard and Maritime Transportation Act of 2012 (H.R. 2838/P.L. 112-213 of December 20, 2012) prohibited the Coast

Guard from removing any part of Polar Sea and from transferring, relinquishing ownership of, dismantling, or

recycling the ship until it submitted a business case analysis of the options for and costs of reactivating the ship and

extending its service life to at least September 30, 2022, so as to maintain U.S. polar icebreaking capabilities and fulfill

the Coast Guard’s high latitude mission needs, as identified in the Coast Guard’s July 2010 High Latitude Study. The

business case analysis was submitted to Congress with a cover date of November 7, 2013. For more on the High

Latitude Study, see Appendix C.

75 The somewhat complicated funding history for the ship is as follows: The Coast Guard’s proposed FY1990 budget

requested $244 million for the acquisition of an icebreaker. The FY1990 DOD Appropriations Act (H.R. 3072/P.L.

101-165 of November 21, 1989) provided $329 million for the ship in the SCN account. (See pages 77 and 78 of

H.Rept. 101-345 of November 13, 1989.) This figure was then reduced by $4.2 million by a sequester carried out under

the Balanced Budget And Emergency Deficit Control Act of 1985, also known as the Gramm-Rudman-Hollings Act

(H.J.Res. 372/P.L. 99-177 of December 12, 1985). Another $50 million was rescinded by the Dire Emergency

Supplemental Appropriations for Disaster Assistance, Food Stamps, Unemployment Compensation Administration,

and Other Urgent Needs, and Transfers, and Reducing Funds Budgeted for Military Spending Act of 1990 (H.R.

(continued...)

Congressional Research Service

31

Coast Guard Polar Security Cutter

Avondale Industries, a shipyard located near New Orleans, LA, that built numerous Coast Guard

and Navy ships, and which eventually became part of Huntington Ingalls Industries (HII). HII

subsequently wound down shipbuilding activities at Avondale, and the facility no longer builds

ships.

Although it is referred to (in U.S. parlance) as a medium polar icebreaker, Healy is actually larger

than Polar Star and Polar Sea—it is 420 feet long and displaces about 16,000 tons. Compared to

Polar Star and Polar Sea, Healy has less icebreaking capability (which is why it is referred to as

a medium polar icebreaker rather than a heavy polar icebreaker), but more capability for

supporting scientific research. The ship can break through ice up to 4½ feet thick at a speed of 3

knots, and embark a scientific research staff of 35 (with room for another 15 surge personnel and

2 visitors). The ship is used primarily for supporting scientific research and conducting other

operations in the Arctic.

Medium Polar Icebreaker Storis (Former Aiviq)

The 360-foot Arctic oil-exploration support ship Aiviq (Figure A-5 and Figure A-6) was built in

2012 to be used by the Royal Dutch Shell oil company in an oil exploration and drilling effort in

Arctic waters off Alaska.

Figure A-5. Storis

Source: Cropped version of photograph accompanying U.S. Coast Guard, “USCGC Storis Departs on Maiden

Voyage,” press release dated June 4, 2025. The article credits the photograph to Edison Chouest Offshore.

4404/P.L. 101-302 of May 25, 1990). An additional $59 million for the ship was then appropriated in the FY1992 DOD

Appropriations Act (H.R. 2521/P.L. 102-172 of November 26, 1991). Also, an additional $40.4 million in procurement

funding for the ship was provided through a series of annual appropriations in the Coast Guard’s Acquisition,

Construction, and Improvements (AC&I) account (as it was known prior to FY2019) from FY1988 through FY2001.

The resulting net funding for the ship was thus $374.2 million, of which $333.8 million, or 89.2%, was DOD funding,

and $40.4 million, or 10.8%, was Coast Guard procurement funding. (Source: Undated Coast Guard information paper

provided to CRS by Coast Guard legislative liaison office, March 3, 2016.)

Congressional Research Service

32

Coast Guard Polar Security Cutter

Figure A-6. Storis

Source: Cropped version of photograph accompanying U.S. Coast Guard, “USCGC Storis Departs on Maiden

Voyage,” press release dated June 4, 2025. The article credits the photograph to Edison Chouest Offshore.

The ship was owned by Edison Chouest Offshore (ECO) of Cut Off, LA, a firm that operates

more than 200 ships.76 It was used primarily for towing and laying anchors for drilling rigs but

was also equipped for responding to oil spills. The Coast Guard purchased Aiviq under the

Commercially Available Polar Icebreaker (CAPI) program, modified the ship to become a Coast

Guard medium polar icebreaker, and renamed the ship Storis (WAGB-21), in honor of a previous

Coast Guard cutter of that name.

A December 19, 2024, GAO report on Coast Guard acquisition of polar ships states that the ship

is not configured like a traditional Coast Guard polar icebreaker. For example, the Aiviq’s

flight deck is mounted on the front of the icebreaker and not on the back like with other

current or planned Coast Guard polar icebreakers and there is no aircraft hangar.

The Coast Guard is acquiring and modifying the CAPI in two phases separated by a few

years. The first phase will include inspecting and purchasing the polar icebreaker, making

modifications to ensure it can operate in the Arctic, getting needed certifications, painting

it in Coast Guard colors, and placing a commissioned officer in command. The goal of this

phase is to reach initial operational capability to begin Arctic operations within 18 to 24

months after receiving the funding, or by the end of March 2026. The second phase will

entail yet-to-be determined ship modifications to achieve full operational capability 7 years

after the initial operational capability is achieved, or by the end of fiscal year 2033,

according to the Coast Guard’s April 2024 notional schedule. After operating the

icebreaker a few years, the Coast Guard’s acquisition strategy shows that it will achieve

full operational capability after iterative modifications to the ship over the course of up to

5 years. The Coast Guard has yet to determine the extent of these modifications but they

may include consideration of structural work like reconfiguring the helicopter pad and, in

76 For more on ECO, see the firm’s website at https://chouest.com/.

Congressional Research Service

33

Coast Guard Polar Security Cutter

conjunction with National Oceanic and Atmospheric Administration requirements, add

scientific capabilities.77

A January 23, 2025, article about the ship states

The icebreaker Aiviq is a gas guzzler with a troubled history. The ship was built to operate

in the Arctic, but it has a type of propulsion system susceptible to failure in ice. Its waste

and discharge systems weren’t designed to meet polar code, its helicopter pad is in the

wrong place to launch rescue operations and its rear deck is easily swamped by big

waves….

The United States urgently needs new icebreakers in an era when climate change is

bringing increased traffic to the Arctic, including military patrols near U.S. waters by

Russia and China. That the first of the revamped U.S. fleet is a secondhand vessel a top

Coast Guard admiral once said “may, at best, marginally meet our requirements” is a sign

of how long the country has tried and failed to build new ones….

The U.S. Coast Guard’s problem with the Aiviq, retired officers told ProPublica, was the

ship’s design. Originally built for oil operations, it had a low, wet deck and a helipad near

its bow, where it would be ill suited for launching rescue operations. Its direct-drive

propulsion system was both less efficient and more likely to get jammed up in ice than the

diesel-electric systems the Coast Guard used….

Former Coast Guard icebreaker captains were reluctant to criticize the purchase of the

Aiviq when contacted by ProPublica, in part because it has taken impossibly long for the

service to build the new heavy icebreakers it says it needs.

“Is the Coast Guard getting the Aiviq a bad thing? No,” said Rear Adm. Jeff Garrett, a

former captain of the Healy icebreaker. But “is it the ideal resource? No.”…

Lawson Brigham78 said he had questions about the Aiviq “since it’s our tax dollars at

work,” but he granted that “it’s bringing some capability into the Coast Guard at a time

when we’re awaiting whenever the shipbuilder can get the first ship out, which is still

unknown.”

[Former Coast Guard Commandant Paul] Zukunft, who retired in 2018, stands by his past

opposition to the Aiviq.

“I remain unconvinced,” he wrote in response to questions from ProPublica, that it “meets

the operational requirements and design of a polar icebreaker that have been thoroughly

documented by the Coast Guard.” By acquiring the Aiviq, “the Coast Guard runs the risk

that those requirements can be compromised.”

In a statement, the Coast Guard described the purchase of the Aiviq as a “bridging strategy”

and said the ship “will be capable of projecting U.S. sovereignty in the Arctic and

conducting select Coast Guard missions.”

The fuel vents that flooded during the [2012] Kulluk accident79 have since been raised, a

Chouest engineer has testified. The Coast Guard did not respond to questions about the

Aiviq’s fuel consumption or whether its waste systems will comply with polar code. It did

not say whether its helicopter deck will be moved aft for safer search-and-rescue

77 Government Accountability Office, Coast Guard Acquisitions: Further Cost and Affordability Analysis of Polar

Fleet Needed, GAO-25-106822, Q&A Report to the Committee on Transportation and Infrastructure, House of

Representatives, December 19, 2024, pp. 6-7.

78 Brigham is identified earlier in the article as “a former Coast Guard heavy icebreaker commander who has a

doctorate from Cambridge University and has researched polar shipping since the 1980s.”

79 This is a reference to an accident, discussed earlier in the article, that occurred when Aiviq was attempting to tow a

polar drill rig named Kulluk.

Congressional Research Service

34

Coast Guard Polar Security Cutter

operations. It confirmed that there will be no changes to the propulsion system. “Initial

modifications to the vessel will be minimal,” the statement reads.80

Summary of Above Ships

Table A-1 summarizes the above ships.

Table A-1. Coast Guard Polar Icebreakers

Polar Star

(operational) and

Polar Sea

(nonoperational)

Healy

Storis

(former

Aiviq)

Entered service

1976 (Polar Star)

1977 (Polar Sea)

2000

Built in

2012

Length (feet)

399

420

361

Beam (feet)

83.5

82

80

Draft (feet)

31

29.25

28.25

Displacement (tons)

13,200

16,000

n/a

Icebreaking capability (ice thickness

in feet) at 3 knots or other speed

6 feet

4.5 feet

n/a

Icebreaking capability using back and

ram (ice thickness in feet)

21 feet

8 feet

n/a

-60o Fahrenheit

-50o Fahrenheit

n/a

Crew

155a

85b

About 60

Additional scientific staff

32

35c

Operating temperature

Sources: Prepared by CRS using data from U.S. Coast Guard, National Research Council, National Science

Foundation, DHS Office of Inspector General, and (for Palmer) additional online reference sources.

Notes: n/a is not available.

a. Includes 24 officers, 20 chief petty officers, 102 enlisted, and 9 in the aviation detachment.

b. Includes 19 officers, 12 chief petty officers, and 54 enlisted.

c. In addition to 85 crew members and 35 scientists, the ship can accommodate another 15 surge personnel

and 2 visitors.

d. Plus 9 more in a berthing van.

80 McKenzie Funk, “This Icebreaker Has Design Problems and a History of Failure. It’s America’s Latest Military

Vessel,” ProPublica, January 23, 2025.

Congressional Research Service

35

Coast Guard Polar Security Cutter

Appendix B. Design of PSC

This appendix presents additional background information on the design of the PSC.

The horsepower generated by the propulsion plant in the PSC’s design—more than 45,200,

according to a May 7, 2019, press release from Halter Marine81—is roughly one-quarter less than

the 60,000 shaft horsepower of the propulsion plant in the Coast Guard’s heavy polar icebreaker,

Polar Star. As shown in Figure 1 and Figure 3, however, the PSC’s design includes a centerline

shafted propeller flanked by two azimuthing (i.e., swiveling) podded propulsors—an arrangement

that, along with other modern icebreaker hull design features, is expected to give the design a

capability for breaking ice comparable to that of Polar Star.

The PSC’s design is considerably larger than the Coast Guard’s current polar icebreakers. As

shown in Table A-1, the Coast Guard’s largest polar icebreaker, Healy, is 420 feet long and has a

full load displacement of 16,000 tons. The 460-foot design for the PSC is 40 feet longer than

Healy, and its 22,900-ton displacement is about 43% greater than Healy’s.

A May 8, 2019, press report states the following:

“We picked the most modern icebreaker that was on the market, soon to be productionlevel design that roughly met the Coast Guard’s requirements, and we took it and modified

it,” [Ron] Baczkowski [the shipyard’s chief executive] said.

“It has a contoured shape. The shape of the hull does the icebreaking. Instead of being a

mass breaking ice, this actually slices the ice. The shape of the hull pushed the broken ice

aside, so it doesn’t interfere with your propulsion systems, with your instrumentation that’s

on the other side of the ship.”

The design of the cutter is optimized for seakeeping to support the long voyage from its

homeport in Washington State to as far away as the Antarctic, he said.

“It’s an optimum design between icebreaking and seakeeping.”

“With the propulsors, with one fixed and two steerable, we were able to optimize the

seakeeping capability so when you’re going on long transits from Washington to Antarctica

the crew is not beat to a pulp or heavily fatigued because of the stability characteristics in

open water.”82

Parent Design Approach

The PSC program is using the parent design approach, meaning that the design of the PSC is

based on an existing icebreaker design. Bidders for the PSC program were required to show a

parent design on which their proposed design was based. A key aim in using the parent design

approach is to reduce cost, schedule, and technical risk in the PSC program. A May 7, 2019, press

release from Halter Marine about its design for the PSC stated the following:

VT Halter Marine is teamed with Technology Associates, Inc. [TAI] as the ship designer

and, for over two years, has participated in the U.S. Coast Guard’s Heavy Polar Icebreaker

Industry Study. The ship design is an evolution from the mature “Polar Stern II” [German

icebreaker] currently in design and construction; the team has worked rigorously to

demonstrate its maturity and reliability. During the study, TAI incrementally adjusted the

design and conducted a series of five ship model tank tests to optimize the design. The

81 Halter Marine press release, “VT Halter Marine Awarded the USCG Polar Security Cutter,” May 7, 2019, updated

May 29, accessed April 17, 2025, at https://web.archive.org/web/20201028114950/http://vthm.com/wp-content/

uploads/2019/05/Press-Release_USCG-PSC_Singapore-Exchange-FINAL_updatedMay29.pdf.

82 Sam LaGrone, “VT Halter Marine Details Coast Guard Icebreaker Bid,” USNI News, May 8, 2019.

Congressional Research Service

36

Coast Guard Polar Security Cutter

vessels are 460 feet in length with a beam of 88 feet overall, a full load displacement of

approximately 22,900 long tons at delivery. The propulsion will be diesel electric at over

45,200 horse power and readily capable of breaking ice between six to eight feet thick. The

vessel will accommodate 186 personnel comfortably for an extended endurance of 90 days.

In addition to TAI, VT Halter Marine has teamed with ABB/Trident Marine for its Azipod

propulsion system,83 Raytheon for command and control systems integration, Caterpillar

for the main engines, Jamestown Metal Marine for joiner package, and Bronswerk for the

HVAC system. The program is scheduled to bring an additional 900 skilled craftsman and

staff to the Mississippi-based shipyard.84

The German icebreaker design referred to in Halter Marine’s press release is a design that was

developed for Polar Stern II (also spelled Polarstern II) (Figure B-1),85 a ship that is to be built

as the replacement for Polarstern, Germany’s current polar research and supply icebreaker.86

A May 9, 2019, press report states that the original design for Polarstern II was developed by

Germany’s Ship Design & Consult (SDC), a firm based in Hamburg, Germany, and that

VT Halter’s teammates on the PSC include ship designer Technology Associates, Inc.

(TAI), which has been involved in the design for over two years and has made “a lot of

modifications” in a number of areas to meet Coast Guard requirements, [Ronald

Baczkowski, president and CEO of VT Halter Marine] said. The team went through six

design spirals to refine the design and the major modifications include changes in the hull

form to enhance the ship’s icebreaking capabilities and keep the ice clear from the

propulsors and sensors, habitability improvements for comfort particularly in open water,

easier access to different areas of the ship, and maintenance and endurance capabilities….

Raytheon [RTN] is the integrator for C5I capabilities87 on the ship and the main engines

will be supplied by Caterpillar [CAT]. Switzerland-based ABB and Netherlands-based

Trident are supplying the Azipod propulsion system, Florida-based Jamestown Metal

Marine is supplying the joiner package, and Netherlands-based Bronswerk the heating,

ventilation and cooling system.88

83 ABB is ASEA Brown Boveri, a multinational corporation headquartered in Zurich, Switzerland, that is, among other

things, a leading maker of electric-drive propulsion systems for ships. (ASEA is an acronym for Allmänna Svenska

Elektriska Aktiebolaget [i.e., General Swedish Electrical Limited Company], which merged with Brown, Boveri & Cie

[BBC] in 1988 to create ABB.) Azipod is ABB’s term for its azimuthing (i.e., swiveling) podded propulsors.

84 Halter Marine press release, “VT Halter Marine Awarded the USCG Polar Security Cutter,” May 7, 2019, updated

May 29, accessed April 17, 2025, at https://web.archive.org/web/20201028114950/http://vthm.com/wp-content/

uploads/2019/05/Press-Release_USCG-PSC_Singapore-Exchange-FINAL_updatedMay29.pdf. The original (May 7)

version of the press release stated that the design’s full load displacement at delivery would be approximately 33,000

tons. Halter Marine updated the press release on May 29 to provide a corrected figure of 22,900 tons for the design’s

full load displacement.

85 Polarstern is the German word for Polar Star—coincidentally, the same name as the U.S. Coast Guard’s operational

heavy polar icebreaker.

86 For more on Polarstern II, see Alfred-Wegener-Institut (AWI), “The New Polarstern: Contract for New German

Research Icebreaker Awarded,” press release dated December 19, 2024.

87 C5I stands for command, control, communications, computers, collaboration, and intelligence.

88 Calvin Biesecker, “Long-Lead Funding in FY ‘20 for Second Polar Security Cutter Would Help with Planning,

Shipbuilder Says,” Defense Daily, May 9, 2019. Abbreviations for firm names in brackets as in original.

Congressional Research Service

37

Coast Guard Polar Security Cutter

Figure B-1. Rendering of 2019 SDC Concept Design for Polarstern II

Source: Cropped version of SDC Ship Design & Consult GmbH, design SDC2187, 133m Research Vessel,

accessed November 19, 2024, at http://www.shipdesign.de/html/index.php?navi=3&navi2=80&navi3=115. The

image is enlarged at http://www.shipdesign.de/html/detail.php?id=396.

As shown in Figure B-2, the design for Polarstern II as of December 2024 appears to have

evolved in certain respects from the 2019 design shown in Figure B-1.89

As noted earlier, much of the delay in the delivery date of the first PSC occurred prior to

Bollinger’s November 2022 purchase of Halter. A principal cause of the delay was the time

needed to achieve design maturity (i.e., to complete the detail design of the ship). The parent

design strategy used for the PSC program was intended by the Coast Guard and Navy to reduce

the PSC’s design time. The expected reduction in design time does not appear have been realized.

The time needed to mature the PSC design suggests that the parent design used for the PSC

program—the design for the new German polar icebreaker Polar Stern II—might now more

closely resemble a parent design in name only (PDINO).90 In this regard, the PSC program

appears somewhat similar to the Navy’s Constellation (FFG-62) class frigate program, which the

Navy initiated as a program that would use a parent design, but which observers might now

characterize as having moved over time toward a PDINO situation.91

89 See also Chuck Hill, “‘Elomatic awarded Polarstern 2 icebreaker design contract’—Marine Log / A Little Late for

the Polar Security Cutter,” Chuck Hill’s CG Blog, February 19, 2025.

90 The phrase parent design in name only (with the resulting acronym PDINO) is only one possible shorthand way of

referring to the situation. One possible way to pronounce the acronym PDINO would be pa-DEE-no.

91 For more on the FFG-62 program, see CRS Report R44972, Navy Constellation (FFG-62) Class Frigate Program:

Background and Issues for Congress, by Ronald O'Rourke. On the issue of the FFG-62’s parent design strategy, the

report states

An April 2, 2024, press report states: “At one point the Constellation design shared about 85

percent commonality with the original [Italian-French] FREMM [Fregata Europea Multi-Missione

(continued...)

Congressional Research Service

38

Coast Guard Polar Security Cutter

Figure B-2. Rendering of 2024 Design for PolarStern II

Source: Cropped version of rendering accompanying Alfred-Wegener-Institut (AWI), “The New Polarstern:

Contract for New German Research Icebreaker Awarded,” press release dated December 19, 2024. The caption

to the rendering credits it to “RV Polarstern New Construction 3D View in Ice (Photo: Alfred-WegenerInstitut/thyssenkrupp Marine Systems).”

Limited numbers of available naval architects and design engineers within the United States also

appear to have contributed to delays in maturing the PSC design. A January 22, 2024, press report

states (emphasis added), “Rear Adm. Chad Jacoby, the assistant commandant of the Coast Guard

for acquisition, said this month workforce challenges—specifically, needing more highly trained

welders and design engineers—are contributing to delays on the Polar Security Cutter program

at Bollinger Mississippi, formerly VT Halter Marine.92

Some observers have questioned the value of using parent designs in military shipbuilding

programs. A 2015 journal article, for example, states

The U.S. Navy has experimented with many approaches to design and build its ships. Using

an existing design as the “parent” design, also referred to as “modified-repeat” design, is

on its face an attractive option. Many acquisition executives, program managers and some

ship design engineers believe that a design based on a parent has fewer technical risks than

a new “clean sheet of paper” design and therefore the time and cost to design and build it

will be reduced. They assume early in the ship acquisition program that “the design is

mature” and because of that fewer problems will be encountered in completing the design

and savings will thus be accrued. Yet, a number of naval ships based on a parent design

have in fact experienced unanticipated cost and schedule growth during construction as

well as technical problems during their in-service life. The authors will examine some of

parent] design, but the alterations [incorporated into the FFG-62 design] have brought that

commonality down to under 15 percent, a person familiar with the changes told USNI News.” If the

FFG-62 design shares less than 15% commonality with the FREMM design, then some observers

might characterize the FFG-62 program as having moved over time toward what might be termed a

parent design in name only (PDINO) design approach.

92 Megan Eckstein, “Coast Guard Ship Programs Facing Delays amid National Worker Shortage,” Defense News,

January 22, 2024.

Congressional Research Service

39

Coast Guard Polar Security Cutter

these ship designs which were based on an existing design and/or prototypes and highlight

the fallacies of such beliefs and assumptions.93

93 Robert G. Keane Jr. and Barry F. Tibbitts, “The Fallacy of Using a Parent Design: ‘The Design Is Mature,’”

Transactions (Society of Naval Architects and Marine Engineers [SNAME]), 2015, No. 1 (January): 91-104, with

additional discussion from the authors and other commentators on pages 105-122. The quoted passage appears at the

start of the article, on page 91, where it forms part of an abstract or summary for the article.

Congressional Research Service

40

Coast Guard Polar Security Cutter

Appendix C. Required Numbers of U.S. Polar

Icebreakers

This appendix provides additional background information on required numbers of U.S. polar

icebreakers.

2023 Coast Guard Fleet Mix Analysis

As discussed earlier in this report, the Coast Guard testified in April, June, and November 2023

that a new Coast Guard fleet mix analysis concluded that the service will require a total of eight

to nine polar icebreakers, including four to five heavy polar icebreakers and four to five medium

polar icebreakers, to perform the Coast Guard’s polar (i.e., Arctic and Antarctic) missions in

coming years.94 Prior to this new fleet mix analysis, the Coast Guard had stated that it would need

at least six polar icebreakers, including three heavy polar icebreakers.

Polar Icebreakers Operated by Other Countries as of 2022

In discussions of U.S. polar icebreakers, observers sometimes note the sizes of polar icebreaking

fleets operated by other countries. Table C-1 shows a 2022 Coast Guard summary of major polar

icebreakers around the world. Some observers highlight the difference between the number of

U.S. polar icebreakers and the much larger number of Russian polar icebreakers, and characterize

the situation as an “icebreaker gap.”95 Other observers question the relevance of that comparison

and characterization.96 In considering the number of Russian polar icebreakers, factors that may

94 Spoken testimony, as reflected in CQ hearing transcripts, of

•

Admiral Linda L. Fagan, Commandant of the Coast Guard, at an April 18, 2023, hearing on the Coast

Guard’s proposed FY2024 budget before the Coast Guard and Maritime Transportation subcommittee of the

House Transportation and Infrastructure Committee, for the total figure of eight to nine polar icebreakers;

•

Admiral Steven D. Poulin, Vice Commandant of the Coast Guard, at a June 21, 2023, hearing before the

same subcommittee on the on the Coast Guard’s emerging challenges and statutory needs, again for the total

figure of eight to nine polar icebreakers; and

•

Vice Admiral Peter Gautier, Coast Guard Deputy Commandant for Operations, at a November 29, 2023,

hearing before the House Homeland Security Committee on how U.S. Arctic strategy impacts homeland

security, for both the total figure of eight to nine polar icebreakers and how that total includes four to five

heavy polar icebreakers and four to five medium polar icebreakers.

95 See, for example, Juliana Wheeler, “How Icebreakers Are Becoming the Litmus Test for the U.S. Arctic Strategy,”

Arctic Today, November 13, 2024; James Stavridis, “Putin Is Crushing the Arctic Ice While the US Is Barely Afloat,”

Bloomberg, July 13, 2024; Mike Glenn, “U.S. Icebreaker Gap with Russia a Growing Concern as Arctic ‘Cold War’

Heats Up,” Washington Times, September 23, 2021; Lin A. Mortensgaard and Kristian Søby Kristensen, “The

‘Icebreaker-Gap’—How US Icebreakers Are Assigned New, Symbolic Roles as Part of an Escalating Military

Competition in the Arctic,” Safe Seas, January 5, 2021; Christopher Woody, “As US Tries to Close ‘Icebreaker Gap’

with Russia, Its Only Working Icebreaker Is Making a Rare Trip North,” Business Insider, November 9, 2020; Peter

Kikkert, Gaps and Bridges: The Case for American Polar Icebreakers, North American Arctic Defence and Security

Network, August 12, 2020, 5 pp.; Marc Lanteigne, “So What Is the ‘Icebreaker Gap’ Anyway?” Over the Circle,

March 3, 2019; Charlie Gao, “The ‘Icebreaker Gap’: How Russia Is Planning to Build More Icebreakers to Project

Power in the Arctic,” National Interest, August 19, 2018; Dermot Cole, “The US Is Finally Picking Up the Pace to

Build a Modern Heavy Icebreaker,” Arctic Today, April 21, 2018; Craig H. Allen Sr., “Addressing the US Icebreaker

Shortage,” Pacific Maritime, December 2017: 30-33; Adam Lemon and Brian Slattery, “Standoff in the Arctic: Closing

the Icebreaker Gap,” Newsweek, August 14, 2016; Franz-Stefan Gady, “Will the US Coast Guard Close the ‘Icebreaker

Gap’?” Diplomat, January 14, 2016; Jen Judson, “The Icebreaker Gap,” Politico, September 1, 2015.

96 See, for example, Peter Rybski, “The Challenge of Counting Icebreakers, The Numerical Gap Is Far Less Important

(continued...)

Congressional Research Service

41

Coast Guard Polar Security Cutter

be considered include the length of Russia’s Arctic coastline and Russia’s use of maritime

transportation along its Arctic coastline to support numerous Russian Arctic communities.

(Russia’s Arctic population is roughly 2 million.97) Countries with interests in the polar regions

have differing requirements for polar icebreakers, depending on the nature and extent of their

polar interests and activities. (The term icebreaker gap is also sometimes used to refer to a

potential gap in time between the end of Polar Star’s service life and the entry into service of the

first PSC, or to discuss options, such as leasing existing icebreakers, for bolstering U.S. polar

icebreaking capability prior to the entry into service of the first PSC.98)

Table C-1. Major Polar Icebreakers as of April 4, 2022

Government owned or operated

PC1, PC2,

or equiv.

6

[+2 unavailable]

Russia

Canada

Finland

United States

PC3, PC4,

or equiv.

22

PC5, PC6,

or equiv.

8

2

7

2 (Healy

and Storis

[former

Aiviq])

4

1

10

2

1 (Polar Star)

[+1

nonoperational

(Polar Sea)]

Sweden

China

Denmark

Norway

Estonia

France

United Kingdom

Japan

Australia

Italy

Latvia

South Korea

South Africa

Argentina

Chile

1

Privately owned and operated

PC1, PC2,

or equiv.

PC3, PC4,

or equiv.

9

PC5, PC6,

or equiv.

6

2 (Sikuliaq

and Palmer)

3

3

1

2

1

1

1

1

1

1

1

1

1

1

1

Total

51

[+2 unavailable]

12

9

5

[+1

nonoperational]

4

4

3

2

2

2

1

1

1

1

1

1

1

1

1

than the Gap between Required and Actual Capabilities,” Sixty Degrees North, October 27, 2025; Keith Johnson, “The

Arctic Great Game Won’t Be Won in U.S. Shipyards, The High North Is an Arena of Great-Power Competition, but

Russia Is the one with Something to Lose,” Foreign Policy, September 3, 2024; Robert D. English, “Why an Arctic

Arms Race Would Be a Mistake,” Arctic Today, June 18, 2020; Paul C. Avey, “The Icebreaker Gap Doesn’t Mean

America Is Losing in the Arctic,” War on the Rocks, November 28, 2019; Chuck Hill, “Horrors, It’s the Icebreaker Gap

(cringe),” Chuck Hill’s CG Blog, December 21, 2017; Jeremy Hsu, “U.S. Icebreaker Fleet Is Overdue for an Upgrade,”

Scientific American, June 1, 2017; Andreas Kuersten, “Icebreakers and U.S. Power: Separating Fact from Fiction,” War

on the Rocks, October 11, 2016; Andreas Kuersten, “The Dangerous Myth of an ‘Icebreaker Gap,’” Defense One,

September 6, 2016; Andrew C. Revkin, “The U.S. Icebreaker Gap Is About Arctic Needs, Not About Chasing Russia,”

New York Times (Dot Earth New York Times Blog), September 1, 2015.

97 For additional discussion, see the “Background” section of CRS Report R41153, Changes in the Arctic: Background

and Issues for Congress, coordinated by Ronald O'Rourke.

98 See, for example, Liz Ruskin, “Trump Administration May Hire Private Ship to Fill Arctic ‘Icebreaker Gap’ by

Year’s End,” Alaska Public Media, December 14, 2020; GAO, Coast Guard Acquisitions[:] Polar Icebreaker Program

Needs to Address Risks before Committing Resources, GAO-18-600, September 2018, summary page; Norton A.

Schwartz and James G. Stavridis, “A Quick Fix for the U.S. ‘Icebreaker Gap,’” Wall Street Journal, February 3, 2016.

Congressional Research Service

42

Coast Guard Polar Security Cutter

Government owned or operated

PC1, PC2,

or equiv.

PC3, PC4,

or equiv.

PC5, PC6,

or equiv.

Privately owned and operated

PC1, PC2,

or equiv.

Germany

PC3, PC4,

or equiv.

PC5, PC6,

or equiv.

1

Total

1

Source: Table prepared by CRS based on U.S. Coast Guard graphic of homeports of major polar icebreakers,

updated April 4, 2022; provided to CRS by U.S. Coast Guard on August 11, 2022. (An earlier version of the

graphic, reflecting data as of May 1, 2017, was posted at https://www.dco.uscg.mil/Portals/9/

DCO%20Documents/Office%20of%20Waterways%20and%20Ocean%20Policy/

20170501%20major%20icebreaker%20chart.pdf?ver=2017-06-08-091723-907 as of September 21, 2022.) The

U.S. Coast Guard states that the vessels shown in the graphic “were selected and organized based on IACS Polar

Class notation [see note below], or best equivalent based on publicly available estimates. All vessels included are

believed to be capable of independent Arctic or Antarctic operations.” The Coast Guard graphic includes the

two unavailable Russian government-owned or -operated PC1 or PC2 icebreakers shown above, but it does not

include the U.S. nonoperational PC1 or PC2 icebreaker Polar Sea, which was added by CRS.

Notes: PC1 through PC6 are IACS (International Association of Classification Societies) classifications for polarclass ships. PC1 through PC5 are ships capable of year-round operation in all polar waters (PC1); moderate

multiyear ice conditions (PC2); second-year ice, which may include multiyear ice inclusions (PC3); thick first-year

ice, which may include old ice inclusions (PC4); or medium first-year ice, which may include old ice inclusions

(PC5). PC6 are ships capable of summer/autumn operation in medium first-year ice, which may include old ice

inclusions. (An additional category not shown in the table, PC7, are ships capable of summer/autumn operation

in thin first-year ice, which may include old ice inclusions.) Source: Requirements concerning Polar Class,

International Association of Classification Societies, undated, including Revision 4 of December 2019, Table 1,

entitled Polar Class descriptions, p. I1-2.

June 9, 2020, Presidential Memorandum

On June 9, 2020, President Trump issued a memorandum entitled “Memorandum on

Safeguarding U.S. National Interests in the Arctic and Antarctic Regions,” which states

To help protect our national interests in the Arctic and Antarctic regions, and to retain a

strong Arctic security presence alongside our allies and partners, the United States requires

a ready, capable, and available fleet of polar security icebreakers that is operationally tested

and fully deployable by Fiscal Year 2029. Accordingly, by the authority vested in me as

President by the Constitution and the laws of the United States of America, I hereby direct

the following:

Section 1. Fleet Acquisition Program. The United States will develop and execute a polar

security icebreaking fleet acquisition program that supports our national interests in the

Arctic and Antarctic regions.

(a) The Secretary of Homeland Security, in coordination with the Secretary of State, the

Secretary of Defense, the Secretary of Commerce, and the Director of the Office of

Management and Budget (OMB), shall lead a review of requirements for a polar security

icebreaking fleet acquisition program to acquire and employ a suitable fleet of polar

security icebreakers, and associated assets and resources, capable of ensuring a persistent

United States presence in the Arctic and Antarctic regions in support of national interests

and in furtherance of the National Security Strategy and the National Defense Strategy, as

appropriate. Separately, the review shall include the ability to provide a persistent United

States presence in the Antarctic region, as appropriate, in accordance with the Antarctic

Treaty System. The Secretary of Homeland Security and the Director of OMB, in executing

this direction, shall ensure that the United States Coast Guard’s (USCG) Offshore Patrol

Cutter acquisition program is not adversely impacted.

(b) The Secretary of Homeland Security, acting through the Commandant of the Coast

Guard, in coordination with the Secretary of Defense, acting through the Secretary of the

Navy, and the Secretary of Energy, as appropriate, shall conduct a study of the comparative

operational and fiscal benefits and risks of a polar security icebreaking fleet mix that

Congressional Research Service

43

Coast Guard Polar Security Cutter

consists of at least three heavy polar-class security cutters (PSC) that are appropriately

outfitted to meet the objectives of this memorandum. This study shall be submitted to the

President, through the Director of OMB and the Assistant to the President for National

Security Affairs, within 60 days from the date of this memorandum and at a minimum shall

include:

(i) Use cases in the Arctic that span the full range of national and economic security

missions (including the facilitation of resource exploration and exploitation and undersea

cable laying and maintenance) that may be executed by a class of medium PSCs, as well

as analysis of how these use cases differ with respect to the anticipated use of heavy PSCs

for these same activities. These use cases shall identify the optimal number and type of

polar security icebreakers for ensuring a persistent presence in both the Arctic and, as

appropriate, the Antarctic regions;

(ii) An assessment of expanded operational capabilities, with estimated associated costs,

for both heavy and medium PSCs not yet contracted for, specifically including the

maximum use of any such PSC with respect to its ability to support national security

objectives through the use of the following: unmanned aviation, surface, and undersea

systems; space systems; sensors and other systems to achieve and maintain maritime

domain awareness; command and control systems; secure communications and data

transfer systems; and intelligence-collection systems. This assessment shall also evaluate

defensive armament adequate to defend against threats by near-peer competitors and the

potential for nuclear-powered propulsion;

(iii) Based on the determined fleet size and composition, an identification and assessment

of at least two optimal United States basing locations and at least two international basing

locations. The basing location assessment shall include the costs, benefits, risks, and

challenges related to infrastructure, crewing, and logistics and maintenance support for

PSCs at these locations. In addition, this assessment shall account for potential burdensharing opportunities for basing with the Department of Defense and allies and partners, as

appropriate; and

(iv) In anticipation of the USCGC POLAR STAR’s operational degradation from Fiscal

Years 2022-2029, an analysis to identify executable options, with associated costs, to

bridge the gap of available vessels as early as Fiscal Year 2022 until the new PSCs required

to meet the objectives of this memorandum are operational, including identifying

executable, priced leasing options, both foreign and domestic. This analysis shall

specifically include operational risk associated with using a leased vessel as compared to a

purchased vessel to conduct specified missions set forth in this memorandum.

(c) In the interest of securing a fully capable polar security icebreaking fleet that is capable

of providing a persistent presence in the Arctic and Antarctic regions at the lowest possible

cost, the Secretary of State shall coordinate with the Secretary of Homeland Security in

identifying viable polar security icebreaker leasing options, provided by partner nations, as

a near- to mid-term (Fiscal Years 2022-2029) bridging strategy to mitigate future

operational degradation of the USCGC POLAR STAR. Leasing options shall contemplate

capabilities that allow for access to the Arctic and Antarctic regions to, as appropriate,

conduct national and economic security missions, in addition to marine scientific research

in the Arctic, and conduct research in Antarctica in accordance with the Antarctic Treaty

System. Further, and in advance of any bid solicitation for future polar security icebreaker

acquisitions, the Secretary of State shall coordinate with the Secretary of Homeland

Security to identify partner nations with proven foreign shipbuilding capability and

expertise in icebreaker construction.

(d) The Secretary of Defense shall coordinate with the Secretary of State and the Secretary

of Homeland Security to continue to provide technical and programmatic support to the

USCG integrated program office for the acquisition, outfitting, and operations of all classes

of PSCs.

Congressional Research Service

44

Coast Guard Polar Security Cutter

Sec. 2. General Provisions. (a) Nothing in this memorandum shall be construed to impair

or otherwise affect:

(i) the authority granted by law to an executive department or agency, or the head thereof;

or

(ii) the functions of the Director of OMB relating to budgetary, administrative, or

legislative proposals.

(b) This memorandum shall be implemented consistent with applicable law and subject to

the availability of appropriations.

(c) This memorandum is not intended to, and does not, create any right or benefit,

substantive or procedural, enforceable at law or in equity by any party against the United

States, its departments, agencies, or entities, its officers, employees, or agents, or any other

person.99

A September 10, 2020, press report states

The White House dropped a surprise directive in June calling for a new strategy in the High

North, a move applauded by Arctic watchers who've been waiting for an administration to

make the issue a priority….

Yet a month after the report was due to the White House, it’s not clear when, or if, anyone

will see it.

The report, which was to include new designs for a fleet of possibly nuclear-powered

icebreakers, has been submitted to the National Security Council. Yet an NSC

spokesperson did not respond to a query on the timing of a release, and would only say the

report is “under review.”100

A December 3, 2020, press report states

The Coast Guard and its partners are assessing options for additional polar icebreaking

capacity in the next decade beyond current plans pursuant to a directive from the Trump

administration, Coast Guard Commandant Adm. Karl Schultz said on Thursday [December

3].

The Coast Guard’s current polar strategy calls for six new icebreakers, at least three of

them heavy, and one immediately, and now “The good news is there’s been a conversation

beyond the 6-3-1 strategy,” Schultz said during a virtual address hosted by the Navy

League. “The president and his team have pressed us here since this past summer pulling

together the energy of five cabinet level officials and OMB [Office of management and

Budget] about saying, ‘Hey, what does more capacity for high-latitude work between now

and 2029 look like?’”…

The Coast Guard hasn’t looked favorably in the past on leasing options for ice breakers, at

least not as a permanent solution to its polar requirements. But Schultz said leasing could

fill near-term gaps.

“We clearly don’t want to be looking at leasing options as a replacement for the

procurement of ships that are going to serve us for decades to come, but there might be

some bridging strategies and some leasing options,” he said. “So, we’re working really

99 White House, “Memorandum on Safeguarding U.S. National Interests in the Arctic and Antarctic Regions,” June 9,

2020. For press reports about the memorandum, see, for example, David B. Larter, Joe Gould, and Aaron Mehta,

“Trump Memo Demands New Fleet of Arctic Icebreakers Be Ready by 2029,” Defense News, June 9, 2020; Paul

McLeary, “White House Orders New Icebreaker Strategy For Coast Guard,” Breaking Defense, June 9, 2020; Cal

Biesecker, “Trump Wants Review of Polar Security Cutter Needs in Arctic, Antarctic,” Defense Daily, June 9, 2020.

100 Sarah Cammarata, “Trump’s Arctic Plan Stuck in the Ice,” Politico Pro, September 10, 2020.

Congressional Research Service

45

Coast Guard Polar Security Cutter

hard on that, answering some deliverables over to the White House and hope we can keep

some momentum.”

A Coast Guard spokesman told Defense Daily following Schultz’s speech that the service

and the Navy “have formed a joint working group to assess available foreign and domestic

vessels that would meet short-term mission needs in the Arctic. The Coast Guard is

continuing to evaluate all options and provide detailed analysis of icebreaker capacity,

lease options, and long-term strategies to protect vital economic and national security

interests in the Polar Regions.”101

A December 16, 2020, press report stated

The White House National Security Adviser and the Navy may be on the verge of agreeing

to move forward shortly with a plan to lease medium polar icebreakers to fill a near-term

gap in the Coast Guard’s icebreaking needs, Alaska Sen. Dan Sullivan (R) said last week.

Sullivan, during a Dec. 8 hearing that he chaired that morning on the Coast Guard’s

capabilities in the Arctic, said he spoke earlier that day with White House National Security

Adviser Robert O’Brien, who told him that the U.S. is looking at leasing polar icebreakers

from Finland.

“My understanding is the White House National Security Adviser [and] possibly the Navy

with regard to some of their funding, are looking at moving forward on leases soon,

hopefully as early as the end of this month,” Sullivan told Adm. Charles Ray, vice

commandant of the Coast Guard.

Ray replied that discussions on leasing are part of a presidential directive issued in June,

noting that a joint Coast Guard and Navy group are looking into this.

Later during the hearing, in response to a question from Sen. Mike Lee (R-Utah) about

potentially buying polar icebreakers from NATO allies or friendly Arctic nations, Ray said

the “The bridging strategy that makes the most sense to the Coast Guard at this point is this

potential to lease one of these icebreakers.”

Ray pointed out to Sullivan that the potential leasing strategy is not in place of the Coast

Guard eventually acquiring new polar icebreakers.

A Coast Guard spokesman on Wednesday told Defense Daily that the exact number if

icebreakers that would be leased hasn’t been determined and “depends on individual vessel

availability and capabilities, crew availability, funding, and other factors.” He also said the

options only included medium icebreakers because no heavy icebreakers are currently

available that meet the service’s minimum requirements.…

The Coast Guard spokesman said a bridging strategy is being examined because the first

PSC won’t begin operations until 2027. Any leased vessels, which potentially could be

domestic or foreign flagged, would operate in the Arctic “to project U.S. sovereignty;

protect vital economic and national security interests; and conduct maritime domain

awareness, search and rescue, and other Coast Guard missions,” he wrote in an email

response to questions.…

Ray said that a key shortfall of leasing commercial polar icebreakers is they aren’t built to

military specifications, highlighting communications, damage control and

compartmentalization in case of an incident.

“They’re a different cat,” Ray said. “We would have to do some work to them. It’s not just,

take one off the shelf. If it was, we probably would have done that a long time ago. So,

there will be some work required to make these for the Coast Guard. But with that said, it

101 Cal Biesecker, “Coast Guard, Partners Assessing Options for More Polar Icebreaking Capacity,” Defense Daily,

December 3, 2020.

Congressional Research Service

46

Coast Guard Polar Security Cutter

is the commandant’s position and our position we will certainly consider this and work to

see what makes sense to bridge this gap.”102

Coast Guard Statements Prior to 2023 Fleet Mix Analysis

Prior to the Coast Guard’s 2023 fleet mix analysis, Coast Guard officials tended to refer to a total

Coast Guard requirement for three heavy and three medium polar icebreakers. For example, in the

October 25, 2016, summary of an RFI that the Coast Guard released the next day to receive

industry feedback on its notional polar icebreaker acquisition approach and schedule, the Coast

Guard states that “the United States Coast Guard has a need for three Heavy Polar Icebreakers

and three Medium Polar Icebreakers with the priority being Heavy Polar Icebreakers.”103 A

requirement for three heavy and three medium polar icebreakers was often abbreviated as 3+3.

Short of a 3+3 requirement, Coast Guard officials sometimes stated that, as a bare minimum

number of heavy polar icebreakers, the Coast Guard needs two such ships. For example, at a

November 17, 2015, hearing before the Europe, Eurasia, and Emerging Threats subcommittee

and the Western Hemisphere subcommittee of the House Foreign Affairs Committee, then-Vice

Admiral Charles Michel, the Vice Commandant of the Coast Guard, stated during the discussion

portion of the hearing that the “Coast Guard needs at least two heavy icebreakers to provide yearround assured access and self-rescueability in the polar regions.”104 Similarly, at a June 14, 2016,

hearing before the Coast Guard and Maritime Transportation subcommittee of the House

Transportation and Infrastructure Committee, Admiral Michel testified that “our commandant

also testified that we need self-rescue capability for our heavy icebreaker and that includes the

existing Polar Star that we have out there now. So that means at least two [ships], [and] the High

Latitude study says three heavy polar icebreakers is what the Coast Guard’s requirement is. So

that’s kind of where we’re talking about for heavy icebreakers.”105 (The High Latitude Study is

discussed later in this appendix.)

July 2017 National Academies (NASEM) Report

A July 2017 report on the acquisition and operation of polar icebreakers by the National

Academies of Sciences, Engineering, and Medicine (NASEM) that was directed by Congress in

Section 604 of the Coast Guard Authorization Act of 2015 (H.R. 4188/P.L. 114-120 of February

8, 2016) concluded the following:

INTRODUCTION

The United States has strategic national interests in the polar regions. In the Arctic, the

nation must protect its citizens, natural resources, and economic interests; assure

sovereignty, defense readiness, and maritime mobility; and engage in discovery and

research. In the Antarctic, the United States must maintain an active presence that includes

access to its research stations for the peaceful conduct of science and the ability to

participate in inspections as specified in the Antarctic Treaty. The committee’s charge...

was to advise the U.S. House of Representatives and the U.S. Senate on an assessment of

the costs incurred by the federal government in carrying out polar icebreaking missions

and on options that could minimize lifecycle costs. The committee’s consensus findings

102 Cal Biesecker, “Senator Says Decision Could Come Soon to Lease Icebreakers for Coast Guard,” Defense Daily,

December 16, 2020. See also Liz Ruskin, “Trump Administration May Hire Private Ship to Fill Arctic ‘Icebreaker

Gap’ by Year’s End,” Alaska Public Radio, December 14, 2020.

103

Summary of RFI, October 25, 2016, page 2.

104 Transcript of hearing.

105 Transcript of hearing.

Congressional Research Service

47

Coast Guard Polar Security Cutter

and recommendations are presented below. Unless otherwise specified, all estimated costs

and prices for the future U.S. icebreakers are expressed in 2019 dollars, since that is the

year in which the contracts are scheduled to be made. Supporting material is found in the

appendices.

FINDINGS AND RECOMMENDATIONS

1. Finding: The United States has insufficient assets to protect its interests, implement

U.S. policy, execute its laws, and meet its obligations in the Arctic and Antarctic

because it lacks adequate icebreaking capability.

For more than 30 years, studies have emphasized the need for U.S. icebreakers to maintain

presence, sovereignty, leadership, and research capacity—but the nation has failed to

respond.... The strong warming and related environmental changes occurring in both the

Arctic and the Antarctic have made this failure more critical. In the Arctic, changing sea

ice conditions will create greater navigation hazards for much of the year, and expanding

human industrial and economic activity will magnify the need for national presence in the

region. In the Antarctic, sea ice trends have varied greatly from year to year, but the annual

requirements for access into McMurdo Station have not changed. The nation is ill-equipped

to protect its interests and maintain leadership in these regions and has fallen behind other

Arctic nations, which have mobilized to expand their access to ice-covered regions. The

United States now has the opportunity to move forward and acquire the capability to fulfill

these needs....

2. Recommendation: The United States Congress should fund the construction of four

polar icebreakers of common design that would be owned and operated by the United

States Coast Guard (USCG).

The current Department of Homeland Security (DHS) Mission Need Statement (DHS

2013) contemplates a combination of medium and heavy icebreakers. The committee’s

recommendation is for a single class of polar icebreaker with heavy icebreaking capability.

Proceeding with a single class means that only one design will be needed, which will

provide cost savings. The committee has found that the fourth heavy icebreaker could be

built for a lower cost than the lead ship of a medium icebreaker class....

The DHS Mission Need Statement contemplated a total fleet of “potentially” up to six ships

of two classes—three heavy and three medium icebreakers. Details appear in the High

Latitude Mission Analysis Report. The Mission Need Statement indicated that to fulfill its

statutory missions, USCG required three heavy and three medium icebreakers; each vessel

would have a single crew and would homeport in Seattle. The committee’s analysis

indicated that four heavy icebreakers will meet the statutory mission needs gap identified

by DHS for the lowest cost. Three of the ships would allow continuous presence in the

Arctic, and one would service the Antarctic.

As noted in the High Latitude Report, USCG’s employment standard is 185 days away

from home port (DAFHP) for a single crew. Three heavy icebreakers in the Arctic provide

555 DAFHP, sufficient for continuous presence. In addition, the medium icebreaker USCG

Cutter Healy’s design service life runs through 2030. If greater capacity is required, USCG

could consider operating three ships with four crews, which would provide 740 DAFHP.

The use of multiple crews in the Arctic could require fewer ships while providing a

comparable number of DAFHP. For example, two ships (instead of the recommended

three) operating in the Arctic with multiple crews could provide a similar number of annual

operating days at a lower cost, but such an arrangement may not permit simultaneous

operations in both polar regions and may not provide adequate redundancy in capability.

More important, an arrangement under which fewer boats are operated more often would

require more major maintenance during shorter time in port, often at increasing cost. In

addition, if further military presence is desired in the Arctic, USCG could consider icestrengthening the ninth national security cutter.

Congressional Research Service

48

Coast Guard Polar Security Cutter

One heavy icebreaker servicing the Antarctic provides for the McMurdo breakout and

international treaty verification. The availability of the vessel could be extended by

homeporting in the Southern Hemisphere. If the single vessel dedicated to the Antarctic is

rendered inoperable, USCG could redirect an icebreaker from the Arctic, or it could rely

on support from other nations. The committee considers both options to be viable and

believes it difficult to justify a standby (fifth) vessel for the Antarctic mission when the

total acquisition and lifetime operating costs of a single icebreaker are projected to exceed

$1.6 billion. Once the four new icebreakers are operational, USCG can reasonably be

expected to plan for more distant time horizons. USCG could assess the performance of

the early ships once they are operational and determine whether additional capacity is

needed.

USCG is the only agency of the U.S. government that is simultaneously a military service,

a law enforcement agency, a marine safety and rescue agency, and an environmental

protection agency. All of these roles are required in the mission need statement for a polar

icebreaker. USCG, in contrast to a civilian company, has the authorities, mandates, and

competencies to conduct the missions contemplated for the polar icebreakers. Having one

agency with a multimission capability performing the range of services needed would be

more efficient than potentially duplicating effort by splitting polar icebreaker operations

among other agencies.

The requirement for national presence is best accomplished with a military vessel. In

addition, USCG is fully interoperable with the U.S. Navy and the nation’s North Atlantic

Treaty Organization partners. USCG is already mandated to operate the nation’s domestic

and polar icebreakers. Continuing to focus this expertise in one agency remains the logical

approach....

Government ownership of new polar icebreakers would be less costly than the use of lease

financing (see Appendix C). The government has a lower borrowing cost than any U.S.based leasing firm or lessor. In addition, the lessor would use higher-cost equity (on which

it would expect to make a profit) to cover a portion of the lease financing. The committee’s

analysis shows that direct purchase by the government would cost, at a minimum, 19

percent less than leasing on a net present value basis (after tax). There is also the risk of

the lessor going bankrupt and compromising the availability of the polar icebreaker to

USCG. For its analysis, the committee not only relied on its extensive experience with

leveraged lease financing but also reviewed available Government Accountability Office

reports and Office of Management and Budget rules, examined commercial leasing

economics and current interest rates, and validated its analysis by consulting an outside

expert on the issue....

This text is long and has been trimmed here. Open the source document for the complete record.