Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Congressional research reportSep 20, 2010
Ask Donna
What actually matters in this document.
Text
Defense Logistical Support Contracts in Iraq
and Afghanistan: Issues for Congress
(name redacted)
Specialist in Defense Acquisition
September 20, 2010
Congressional Research Service
7-....
www.crs.gov
RL33834
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Summary
This report examines Department of Defense (DOD) logistical support contracts for troop support
services in Iraq and Afghanistan administered through the U.S. Army’s Logistics Civil
Augmentation Program (LOGCAP), as well as legislative initiatives which may impact the
oversight and management of logistical support contracts. LOGCAP is an initiative designed to
manage the use of civilian contractors that perform services during times of war and other
military mobilization. The first LOGCAP was awarded in 1992. Four LOGCAP contracts have
been awarded for combat support services in Iraq and Afghanistan. The current LOGCAP III
contractor supports the drawdown in Iraq by providing logistical services, theater transportation,
augmentation of maintenance services, and other combat support services.
On April 18, 2008, DOD announced the Army’s LOGCAP IV contract awards to three
companies—DynCorp International LLC, Fort Worth, TX; Fluor Intercontinental, Inc, Greenville,
SC; and KBR, Houston, TX, through a full and open competition. The LOGCAP IV contract calls
for each company to compete for task orders. Each company may be awarded up to $5 billion
annually for troop support services with a maximum annual value of $15 billion. As of March
2010, each company has been awarded at least one task order under LOGCAP IV. Over the life
of LOGCAP IV, the maximum contract value is $150 billion. The U.S. Army Sustainment
Command awarded the first performance task order on September 25, 2008, to Fluor
Intercontinental, Inc., for logistical support services in Afghanistan. As of April 2010,
approximately 12 tasks orders have been awarded under LOGCAP IV for a total of $1.8 billion in
obligations under LOGCAP IV contracts.
In May 2010, the U.S. Army announced that it would continue to use the LOGCAP III contract to
provide support services until the scheduled withdrawal of all troops in December 2011. Previous
to this announcement, the Army had announced that the LOGCAP III contract would be cancelled
and that all services would be transferred to the LOGCAP IV contract. However, the Army has
reportedly completed a business case analysis and concluded that keeping the LOGCAP III
contract would be of greater benefit to the federal government. Some Members of Congress have
questioned this decision and asked the Secretary of Defense to reconsider, particularly in light of
the Justice Department’s decision to bring civil action against the LOGCAP III contractor.
Congress is concerned about the federal oversight and management of DOD contracting in Iraq
and Afghanistan, particularly under programs like LOGCAP. Assessments from the Government
Accountability Office (GAO), DOD Office of the Inspector General (DOD-IG), the Special
Inspector General for Iraq Reconstruction (SIGIR), and the Defense Contract Audit Agency
reveal a lack of accountability for large sums of money spent for Iraq contracts.
Congressional concerns over the federal oversight and management of defense contracts were the
subject of a House Armed Services Committee (HASC) Panel on Defense Acquisition Reform to
conduct a systematic review of the defense acquisition system. On March 23, 2010, the panel
provided the HASC its findings and recommendations. Largely as a result of the panel’s work,
H.R. 5013, the Implementing Management for Performance and Related Reforms to Obtain Value
in Every Acquisition Act (IMPROVE) of 2010, was introduced on April 14, 2010, seeking to
improve the management and oversight of DOD’s procurement of goods and services.
Congressional Research Service
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Contents
Introduction .................................................................................... Error! Bookmark not defined.
Purpose and Scope .................................................................................................................... 1
Legislative Activity, H.R. 5013 ................................................................................................. 1
Air Force Contract Augmentation Program .............................................................................. 5
Logistics Civil Augmentation Program ........................................................................................... 6
LOGCAP Contracts (1992-2010).............................................................................................. 7
Latest Update on LOGCAP III Contract ................................................................................... 8
LOGCAP IV Contract Awards .................................................................................................. 9
The Planning Contract Was Awarded to Serco ................................................................... 9
ASC Selected the Performance Contractors ....................................................................... 9
Protests .............................................................................................................................. 10
Contract Details ................................................................................................................ 10
Performance Task Orders ................................................................................................... 11
Congressional Interest .............................................................................................................. 11
The Defense Base Act (DBA) and LOGCAP ................................................................... 14
Background ................................................................................................................................... 16
Awarding of Defense Contracts .............................................................................................. 16
Full and Open Competition............................................................................................... 16
Emergency Contracting Authorities .................................................................................. 17
Contingency Contracting .................................................................................................. 17
Rapid Acquisition Methods............................................................................................... 17
Audits, Investigations, and Reports......................................................................................... 18
Role of Federal Agencies .................................................................................................. 18
Special Inspector General for Iraq Reconstruction (SIGIR) ............................................. 18
Special Inspector General for Iraq Reconstruction (SIGIR) LOGCAP Reviews .................... 19
Quarterly Report to Congress ........................................................................................... 19
Reviews of Task Orders 130 and 151 ............................................................................... 19
DOD Inspector General .................................................................................................... 20
Government Accountability Office (GAO)....................................................................... 21
Potential Oversight Issues ............................................................................................................. 21
Contract Oversight ............................................................................................................ 21
Contract Administration .................................................................................................... 22
DOD Contracting Officials ............................................................................................... 23
Development of Contract Requirements ........................................................................... 24
Use of Indefinite-Delivery/Indefinite-Quantity Contracts ................................................ 24
Costs and the Use of No-Bid and Sole-Source Contracts ................................................. 25
Cost-reimbursement Contracts.......................................................................................... 25
Use of Overhead Fees ....................................................................................................... 25
Transparency ..................................................................................................................... 26
Acquisition Workforce ...................................................................................................... 26
The Gansler Commission.................................................................................................. 28
Independent Panel to Examine the Defense Contract Audit Agency ................................ 29
Potential Options for Congress ...................................................................................................... 30
Option 1: Implementing the Gansler Commission Recommendations ................................... 30
Option 2: Expanding the SIGIR’s Jurisdiction ........................................................................ 30
Option 3: Convening a Study of the Federal Employee and Contractor Workforce ............... 31
Congressional Research Service
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Option 4: Requiring More Detail for Better Oversight ........................................................... 31
Option 5: Establishing a Dedicated Office to Conduct Audits and Investigation of
DOD Contracts..................................................................................................................... 32
Appendixes
Appendix A. Selected Reports ....................................................................................................... 33
Appendix B. Selected Legislative Initiatives on Iraq Contracting ................................................ 35
Contacts
Author Contact Information ........................................................... Error! Bookmark not defined.
Congressional Research Service
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Introduction
Purpose and Scope
This report will examine logistical support contracts for troop support services (also known as
service contracts1) in Iraq and Afghanistan, primarily administered through a smaller program, the
United States Air Force Contract Augmentation Program (AFCAP) and a larger program, the
United States Army’s Logistics Civil Augmentation Program (LOGCAP).2 This report will focus
primarily on contracts involving Department of Defense (DOD) appropriated funds, although
some projects involve a blending of funds from other agencies.3
Legislative Activity, H.R. 5013
This section of the report will provide some background on proposed legislative initiatives which
seek to improve the acquisition, management, and oversight of defense service contracts such as
LOGCAP.
In March 2009, the House Armed Services Committee (HASC) appointed a Panel on Defense
Acquisition Reform to conduct a systematic review of the defense acquisition system. On March
23, 2010, the panel issued its final report, and provided the HASC its findings and
recommendations. On March 23, 2010, the House Armed Services Committee’s Defense
Acquisition Reform Panel issued its final report, and provided its findings and recommendations
to the House Armed Services Committee.4 Largely due to the recommendations of the panel, a
new set of legislative initiatives have been introduced to address the ongoing and systemic
problems with DOD’s acquisition of goods and services. They are described below.
H.R. 5013, the Implementing Management for Performance and Related Reforms to Obtain Value
in Every Acquisition Act (IMPROVE) of 2010, was introduced on April 14, 2010, by
Representative Robert Andrews.5 The proposed bill is largely a result of the recommendations of
the House Armed Services Committee’s Panel on Defense Acquisition Reform, a yearlong effort
1
Federal Acquisition Regulation (FAR) 37, Subpart 37.1 defines “service contracts” as contracts that directly engage
the time and effort of a contractor whose primary purpose is to perform an identifiable task rather than to furnish an end
item of supply.
2
Department of the Army. Logistics Civil Augmentation Program (LOGCAP). Army Regulation (AR) 700-137,
Introduction, 1-1. Purpose, p. 1.
3
For a fact sheet on the application of federal procurement statutes to contracts for the reconstruction of Iraq, see CRS
Report RS21555, Iraq Reconstruction: Frequently Asked Questions Concerning the Application of Federal
Procurement Statutes, by (name redacted); for a discussion on Iraqi Relief and Reconstruction Fund (IRRF) contracting
issues, see CRS Report RL31833, Iraq: Reconstruction Assistance, by (name redacted)
. For a discussion on private
security contracting see CRS Report RL32419, Private Security Contractors in Iraq: Background, Legal Status, and
Other Issues, by (name redacted), (name redacted), and (name redacted)
. For a discussion of war-related costs
see CRS Report RL33110, The Cost of Iraq, Afghanistan, and Other Global War on Terror Operations Since 9/11, by
(name redacted)
. For a discussion on the FY2008 DOD appropriations and authorization bills, refer to CRS Report
RL33999, Defense: FY2008 Authorization and Appropriations, by (name redacted), (name redacted),
d (name
an
redacted)
.
4
Final Report of the Defense Acquisition Reform Panel, Findings and Recommendations. House Armed Services
Committee, .March 23, 2010.
5
H.Rept. 111-465, Part I. H.R. 5013, 111th Congress, 2nd Session. The bill has nine co-sponsors, and was referred to
the House Armed Services Committee (HASC) and the House Oversight and Government Reform Committee on was
reported out of the House Armed Services Committee on April 14, 2010. The bill was amended by the HASC on April
21, 2010, discharged by the House Oversight and Government Reform Committee on April 23, 2010, and reported
favorably in a HASC vote of 56-0.
Congressional Research Service
1
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
to study the defense acquisition system with the goal of identifying systemic failures that impact
DOD’s acquisition of goods and services. H.R. 5013 appears to represent a significant overhaul of
Department of Defense (DOD) acquisition policy and one of the first attempts to address the
oversight and management of defense service contracts. Some estimates are that DOD’s annual
spending for goods and services comprise some 60% to 80% of DOD’s total annual spending,
including spending for logistical support contracts.6
H.R. 5013 is divided into four major areas of reform: Title I, the Defense Acquisition System;
Title II, the Defense Acquisition Workforce; Title III, the Financial Management System; and
Title IV, the Industrial Base. Selected highlights from each section of the bill appear below.7
Title 1—Defense Acquisition System. Title I amends Title 10 of the United States Code (U.S.C)
to insert a new chapter, Chapter 149—Performance Management of the Defense Acquisition
System. Title I would require the Secretary of Defense to regularly assess the performance of the
defense acquisition system designed to “ensure that all elements of the defense acquisition system
are subject to regular performance assessments – (A) to determine the extent to which such
elements deliver appropriate value to the Department of Defense; and (B) to enable senior
officials of the Department of Defense to manage the elements of the defense acquisition to
maximize their value to the Department.”8
Highlights of Title I include the following provisions:
The development of system-wide categories of metrics to ensure that there is
sufficient uniformity in performance assessments across the defense acquisition
system;
The conduct of periodic audits to determine the accuracy and reliability of the
performance assessments;
The establishment of linkages between the performance assessments, the
management of personnel, and the criteria for promotion, awards, and other
workforce incentives;
The establishment of a process for generating requirements for the acquisition of
services that includes commanders of unified combatant commands and other
designated officers, to provide input on joint requirements for the acquisition of
services;
The revision of the Federal Acquisition Regulation (FAR) to provide appropriate
references to service contracting that are in addition to those references in FAR
Part 37;9 and
6
Donnelly, John M. Commission Warnings Raise Doubts on Oversight of Pentagon Contracts. Congressional
Quarterly (CQ) Today, April 20, 2010, p. 9. The Government Accountability Office, in a recent report, has stated: “In
fiscal year 2008, the Department of Defense (DOD) obligated over $200 billion on contracts for services, which
accounted for more than half of its total contract obligations.” Defense Acquisitions: Actions Needed to Ensure Value
for Service Contracts. Statement of John Hutton, Director, Acquisition and Sourcing Management and William Solis,
Director, Defense Capabilities and Management, in testimony before the Defense Acquisition Reform Panel, House
Armed Services Committee. GAO-09-643T, April 23, 2009.
7
Title I - Sections 102, 103, and 105, which address performance management initiatives in weapon system
acquisition, are discussed in CRS Report RL34026, Defense Acquisitions: How DOD Acquires Weapon Systems and
Recent Efforts to Reform the Process, by (name redacted) .
8
H.R. 5013 RH, p. 5.
9
FAR Part 37 prescribes the policy and procedure for the acquisition and management of services by contract. For
further information, see https://www.acquisition.gov/far/html/FARTOCP37.html.
Congressional Research Service
2
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
The amendment of Title 10, Chapter 14110 by adding a section on the acquisition
of certain “military purpose, nondevelopmental items.”
Title II—Defense Acquisition Workforce. Title II amends Title 10, Chapter 87, by adding a new
section on the management of the acquisition workforce. Title II focuses on workforce
improvements designed to develop and maintain a highly skilled and professionally trained
acquisition workforce.11
Highlights of Title II include the following provisions:
The requirement for the Secretary of Defense to use the full authorities granted in
Title 5, Section 9902,12 to manage the defense acquisition workforce in a way
that complements and reinforces the performance management of the defense
acquisition system;
The hiring and training of managers, and the development of performance plans
for individual members of the acquisition workforce;
The incorporation of best practices adopted from the acquisition demonstration
project carried out under Section 1762 of this title;
The full use of the Defense Civilian Leadership Program established under
Section 1112 of P.L. 111-84, the National Defense Authorization Act for
FY2010;13
The full use of authorities under Title 5, Section 990314 to hire highly qualified
experts and skilled acquisition professionals;
The revision of the acquisition workforce demonstration project by the addition
of Section 1762, “Demonstration Project Relating to certain Acquisition
Personnel Management Policies and Procurements;”
The revision of Title 10, Chapter 87 by the addition of Section 1763, “Incentive
Programs for Civilian and Military Personnel in the Acquisition Workforce;”
The revision of Title 10, Chapter 87 by the addition of Section 1722b. “Special
Requirements for Civilian Employees in the Acquisition Field”, including
educational, recertification, training, and career advancement requirements;
The development of guidance and standards for acquisition workforce training;
The amendment of Title 10, Chapter 87, Subchapter II, by requiring the Secretary
of Defense to develop and carry out a plan to strengthen the segment of the
workforce that specializes in information technology acquisition;
The requirement for a review of the curriculum offered by the Defense
Acquisition University, “to ensure that it adequately supports the training and
education requirements of acquisition professionals, particularly in service
10
Title 10, Subtitle A, Part 4, Chapter 141, Miscellaneous Procurement Provisions.
Title 10, Subchapter A, Part II, Chapter 87, Defense Acquisition Workforce.
12
Title 5, Part III, Subchapter I, Chapter 99, Section 9902. Establishment of Human Resources Management System.
13
Title XI-Civilian Personnel Matters, Subtitle A-Personnel, Section 1112. Department of Defense Civilian Leadership
Program.
14
Title 5, Part III, Subchapter I, Chapter 99, Section 9903, Attracting Highly Qualified Experts.
11
Congressional Research Service
3
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
contracting, long term sustainment strategies, information technology, and rapid
acquisition;”15 and
The requirement for the Secretary of Defense to develop internship and
scholarship programs in cost estimating “to underscore the importance of cost
estimating as a core acquisition function to the acquisition process.”16
Title III—Financial Management. Title III provides DOD with a new structure for increased
accountability for financial management.
Highlights of Title III include the following provisions:
The offering of incentives and other inducements to encourage DOD to produce
financial statements validated and ready for audit, earlier than September 30,
2017;
The development of penalties and other inducements in the event that a DOD
component fails to take corrective measures (to address the failure to achieve a
financial statement validated as ready for audit by September 30, 2017);
The requirement for the DOD Chief Management Officer, in coordination with
the Chief Management Officers for each military service, to review and update
policies and instructions regarding obligation and expenditure benchmarks to
ensure best value for the federal government; within 180 days of enactment of
this act; and
The requirement for the DOD Chief Management Officer, in coordination with
the Chief Management Officer for each military service, the Director of the
Office of Performance Assessment and Root Cause Analysis, the Under Secretary
of Defense (Comptroller), and the Comptrollers of the military services, to
conduct a comprehensive review of the “use and value of obligation and
expenditure benchmarks, and propose new benchmarks or processes for tracking
financial performance.”17
Title IV—Industrial Base. Title IV requires the Secretary of Defense to “establish a program
designed to expand the industrial base and to increase the Department’s access to innovation and
the benefits of competition.”18
Highlights of Title IV include the following provisions:
The establishment of a program to identify and communicate with
“nontraditional suppliers” and “markets of importance to the Department of
Defense.”19
The requirement for the Secretary of Defense to develop and implement
procedures for a price trend analysis for certain categories of commercial items;
15
H.R. 5013 RH, p. 49.
H.R. 5013 RH, p. 54.
17
H.R. 5013 RH, p. 59.
18
H.R. 5013 RH, p. 60.
19
H.R. 5013 RH, p. 61. As defined in the proposed legislation, the terms “nontraditional suppliers” means companies
having been awarded DOD contracts with a total value of not more than $100,000 in the previous 5 years. The terms
“markets of important to the Department of Defense” means business sectors where DOD spends more than
$500,000,000 annually.
16
Congressional Research Service
4
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
The requirement for contractors and grantees to disclose any delinquent Federal
tax debts;
The amendment of Title 10, Chapter 8, Subchapter II20 to authorize the
appointment of a General Counsel for the Defense Contract Audit Agency;
The amendment of Title 10, Subtitle A, Part 4, Chapter 13121 to require the
Secretary of Defense to adhere to guidelines governing the conduct of contractor
business system reviews;
The requirement for the Secretary of Defense to establish a panel “consisting of
owners of large and small businesses that are not traditional defense suppliers, for
purposes of creating a set of recommendations on eliminating barriers to
contracting with the Department of Defense and its defense supply centers;”22
and
The revision of Title 10, Section 2500 to expand the National Technology and
Industrial Base to include the providers of services and information technology.
Air Force Contract Augmentation Program
The U.S. Air Force has a smaller contingency contracting support program for services in Iraq.
The Air Force Contract Augmentation Program (AFCAP) administers logistical support service
contracts in Iraq. AFCAP is the largest contingency support contract awarded by the Air Force.
AFCAP is an “umbrella” contract, similar to the U.S. Army’s LOGCAP. It was designed to
provide an on-call capability for troop sustainment and support. The program was established in
1997 for a wide-range of non-combatant, civil engineering services during wartime, contingency
operation, and humanitarian efforts. AFCAP provides for contractor support to relieve active duty
and air reserve personnel in the areas of food service, lodging, carpentry, plumbing, electrical,
mechanical, air conditioning, laundry plant operations, fire protection emergency management,
and project and program management.
Initially, AFCAP began as a five-year, $475 million program; now it is a 10-year, $10 billion
program. AFCAP is managed by the Air Force Civil Engineer Support Agency at Tyndall Air
Force Base and the Air Force Services Agency in San Antonio, TX.23 The first AFCAP contract
was awarded as a result of a competitive bidding process. Readiness Management Support LC
(RMS) was awarded the contract in February 1997. The cost-reimbursement plus award fee
contract was valued up to $452,600,000 for one base year plus four option years. RMS was again
awarded the contract when the contract was rebidded in February 2002. The new contract
(AFCAP II) calls for one base year and seven option years, and the contract is in effect until
February 2010. RMS is supported by its parent company, Johnson Controls, Inc., and eight other
subcontractors on the AFCAP team.24
20
Title 10, Chapter 8 – Defense Agencies and Department of Defense Field Activities, Subchapter II – Miscellaneous
Defense Agency Matters
21
Title 10, Subtitle A – General Military Law, Part IV – Service, Supply, and Procurement, Chapter 131 – Planning
and Coordination
22
H.R. 5013 RH, p. 71.
23
$10 Billion AFCAP III Award Provides Expeditionary Engineering. Defense Industry Daily: Military Purchasing
News for Defense Procurement Managers and Contractors, at http://www.defenseindustrydaily.com/10b-afcap-iiiprogram-contract-provides-expeditionary-engineering-01468/.
24
See http://www.globalsecurity.org/military/agency/usaf/afcap.htm, viewed on March 4, 2010.
Congressional Research Service
5
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
The Air Force Civil Engineer Agency describes the AFCAP program elements in this way:
AFCAP consists of five key players; 1) the customer, 2) MAJCOM Civil Engineer or
Director of Services, 3) AFCAP program managers located at HQ AFCESA/CEK, 4)
AFCAP contracting officers (AETC Contracting Detachment at AFCESA), and 5) the six
AFCAP contractors (Bechtel, CH2M Hill, DynCorp, Readiness Management Support,
URS & Washington Group). The customer is responsible for providing on-site contract
administration, quality assurance and task order surveillance. The MAJCOM Civil
Engineer/Director of Services (or delegated individual) provides resource advocacy,
appropriate programming and guidance on execution method to complete tasks. The
AFCESA AFCAP program managers work as an interface between customers and the
AFCAP contracting officers to solidify requirements available under this contract.25
Logistics Civil Augmentation Program
LOGCAP was established by the U.S. Army on December 6, 1985, with the publication of Army
Regulation 700-137. LOGCAP is an initiative to manage the use of civilian contractors who
perform services in support of DOD missions during times of war and other military
mobilizations. The use of LOGCAP contracts augments combat support and combat service
support to military forces.26
In September 2006 the Army Sustainment Command (ASC) was created to serve as the “logistics
integrator” for the contingency contracting and sustainment needs of the military worldwide. ASC
oversees about 65,000 contractors and manages about $25 billion in contracts.27 The Defense
Contract Management Agency (DCMA) manages the task orders issued under the LOGCAP
contract.28
In a May 2009 hearing before the Senate Commission on Wartime Contracting, the Executive
Director for the U.S. Army Contracting Command, Army Material Command, testified on the
status of the LOGCAP IV contract. Excerpts of his remarks appear below:
Eight task orders have been awarded to date, including five task orders for performance
and three task orders for project management offices (one for each contractor). Services
are transitioned from LOGCAP III to LOGCAP IV as task orders are awarded. In
addition to protests against the award of the basic contracts, nearly all the task orders
issued or awarded to date under LOGCAP IV have been protested. 29
25
Air Force Civil Engineer Agency, Fact Sheet on AFCAP, at
http://www.afcesa.af.mil/library/factsheets/factsheet.asp?id=9381; also, $10 Billion AFCAP III Provides Expeditionary
Engineering. Defense Industry Dailey, November 5, 2005. Accessed online at
http://www.defenseindustrydaily.com/10b-afcap-iii-program-contract-provides-expeditionary-engineering-01468/.
26
LOGCAP contracts have been previously awarded for work in Rwanda, Haiti, Saudi Arabia, Kosovo, Ecuador,
Qatar, Italy, southeastern Europe, Bosnia, South Korea, Iraq, and Kuwait. Under LOGCAP, private sector contractors
are used to provide a broad range of logistical and other support services to U.S. and allied forces during combat,
peacekeeping, humanitarian and training operations.
27
http://www.aschq.army.mil/home/missionvision.htm.
28
U.S. Congress. Deficient Electrical Facilities at U.S. Facilities in Iraq. Hearing before the House Oversight and
Government Reform Committee. Statement of Jeffrey P. Parsons, Executive Director, Army Contracting Command,
U.S. Army Materiel Command, July 30, 2008.
29
U.S Congress. Military Logistics Contracts: Committee on Senate Commission on Wartime Contracting in Iraq and
Afghanistan. Statement of Jeffrey P. Parsons, Executive Director, U.S. Army Contracting Command, U.S. Army
Materiel Command, May 4, 2009.
Congressional Research Service
6
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
In testimony before the Senate Homeland Security and Governmental Affairs Subcommittee, U.S.
Army officials discussed the status of combat support operations under the LOGCAP program, as
described in excerpts taken from the hearing transcript:
All LOGCAP requirements in Kuwait have successfully transitioned from LOGCAP
III to LOGCAP IV and LOGCAP requirements are in the process of transitioning in
Afghanistan. The current LOGCAP III contractor supports the responsible drawdown in
Iraq through base closure and de-scoping of LOGCAP services which began in May
2009 and continues through August 2010. The two contractors that were awarded the
LOGCAP IV Afghanistan task orders, Fluor and DynCorp will increase their support as
troops transition to the Afghanistan theater. The competitively bid pricing matrixes for
the Afghanistan task orders will be used to adjust the cost estimate for the increased
support associated with the President’s decision.
We are currently conducting a fair opportunity competition for Transportation and Corps
Logistics Support Services requirements in Iraq that will result in requirements
transitioning from LOGCAP III to LOGCAP IV. The next anticipated action involves
Base Life Support. We are in the presolicitation phase for that acquisition with a draft
Request for Proposal issued the week of December 7, 2009.
The Army anticipates that the LOGCAP III contractor will provide logistics services in
support of the Iraq drawdown with theater transportation assets, augmentation of
maintenance services, and support for the supply support activities in the retrograde of
supplies and equipment from theater. The LOGCAP III contractor also possesses other
capabilities in support of the responsible drawdown of forces, such as packaging,
blocking, bracing, and crating of equipment for shipment, wash rack operations, and
cleaning of equipment for agriculture and customs. These services are available to the
supported unit upon request. We expect the LOGCAP IV contractor to provide the same
level of services in support of the responsible drawdown but only for those bases that will
remain after August 2010.30
As of March 29, 2010, 12 task orders have been awarded under LOGCAP IV, as revealed in
recent testimony before the Senate Commission on Wartime Contracting in Iraq and Afghanistan:
Twelve task orders have been awarded to date, including nine task orders for
performance and three task orders for project management offices (one for each
contractor.) To date, $1.8 billion has been obligated under the LOGCAP IV contracts.
With inclusion of the core logistics support, theater transportation, and postal operations
services (CPT), 76 percent of LOGCAP work has been competitively awarded under
LOGCAP IV. Services are transitioned from LOGCAP III to LOGCAP IV as task orders
are awarded.31
LOGCAP Contracts (1992-2010)
The first LOGCAP contract (LOGCAP I) for combat support services in Iraq was awarded on
August 3, 1992, to Brown and Root Services of Houston, TX (also referred to as KBR).
Reportedly, the contract was competitively awarded and consisted of a cost-plus-award-fee
30
U.S. Congress. Senate Homeland Security and Governmental Affairs Subcommittee. Contracting Oversight Hearing
on Afghanistan Contracts: An Overview. Edward Harrington, Deputy Assistant Secretary of the Army for Procurement,
U.S. Department of the Army, and Jeffrey Parsons, Executive Director, Army Contracting Command, U.S. Department
of the Army, December 17, 2009.
31
U.S. Congress. Managing Contractors During Iraq Drawdown. Testimony by James Loehrl, Executive Director,
Rock Island Contracting Center, before the Senate Commission on Wartime Contracting in Iraq and Afghanistan. ,
March 29, 2010.
Congressional Research Service
7
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
contract for one year followed by four option years. The Army Corp of Engineers reportedly held
a competition to award the second LOGCAP contract (LOGCAP II). The contract, a cost-plus
award fee contract for one base year followed by four option years was awarded to Dyncorp on
January 1, 1997. The third LOGCAP contract (LOGCAP III) was awarded in 2001 to
Halliburton/KBR.32
LOGCAP III, a 10-year contract (one base year followed by nine option years), was awarded to
Halliburton/KBR to perform a variety of tasks. Initial press reports indicated that the 2001
LOGCAP III contract would be for the development of a contingency plan for extinguishing oil
well fires in Iraq; however, subsequent press reports indicate that the contract included such tasks
as providing housing for troops, preparing food, supplying water, and collecting trash. This
contract was awarded under a cost-plus-award-fee, Indefinite-Delivery/Indefinite-Quantity
(ID/IQ) contract.33 The 2001 contract was based on specific task orders which are issued
individually and only for those services that DOD felt were necessary to support the mission in
the near term. During 2003, LOGCAP III contract rose to more than $3.5 billion. According to
one press account, Halliburton/KBR reportedly earned a fixed 1% profit above costs on LOGCAP
III, with the possibility of an additional 2% incentive bonus,34 while another press account
reported that the Halliburton/KBR LOGCAP III contract was a cost-plus, award fee contract that
earned a 2% fixed fee with the potential for an extra 5% incentive fee.35
The fourth LOGCAP contract (LOGCAP IV) was executed with a different acquisition strategy.
According to the Army, the LOGCAP IV contract award as based on a full and open competition.
Instead of using a single contractor, the contract called for multiple contractors. Competitions
were held and the contracts were awarded based on what represented the best value to the
government.36 In best value source selections, the government may make tradeoffs to make
awards based on factors other than costs or technical superiority. The use of multiple LOGCAP
contractors is reportedly intended to reduce the government’s risk. Under the new strategy, the
three performance contractors may compete for individual LOGCAP task orders, creating a
competitive environment meant to control costs and enhance quality.
Latest Update on LOGCAP III Contract
In May 2010, the U.S. Army announced that it would not hold a new competition for contract
support services in Iraq. Rather, the Army would continue to use KBR to execute the LOGCAP
III contract to provide support services until the scheduled withdrawal of all troops in December
2011. Reportedly, the Army will extend the task orders until LOGCAP III through the end of
2011. Estimates are that KBR stands to earn approximately $568 million in additional work on
the contract, which would bring KBR’s total value until LOGCAP III to approximately $35.7
billion.37
32
KBR was formerly known as Brown and Root Services. Brown & Root Services was the original LOGCAP
contractor.
33
Indefinite delivery/indefinite quantity contracts, also known as ID/IQ contracts, supply an indefinite quantity of
supplies, goods, or materials for an indefinite period of time. See FAR, Part 16, Types of Contracts.
34
Jaffe, Greg and King, Neil, Jr. U.S. General Criticizes Halliburton. Wall Street Journal, March 15, 2004.
35
See the Center for Public Integrity’s website at http://www.publicintegrity.org/wow/ under the section for Windfalls
of War, U.S. Contractors in Afghanistan and Iraq.
36
FAR, Part 15. Contracting by Negotiation.
37
Brodsky, Robert. Army Cancels Competition for LOGCAP work in Iraq. Government Executive, May 6, 2010.
Congressional Research Service
8
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Previous to this announcement, the Army had maintained that the LOGCAP III contract would be
cancelled and that all services would be transferred to the LOGCAP IV contract. However, the
Army has reportedly completed a business case analysis and concluded that keeping the
LOGCAP III contract would be of greater benefit to the federal government. Some Members of
Congress have questioned this decision and asked the Secretary of Defense to reconsider,
particularly in light of the Justice Department’s decision to bring civil action against the
LOGCAP III contractor.38
LOGCAP IV Contract Awards
The Planning Contract Was Awarded to Serco
In August 2006 the Army held a competition to select a logistical planning and program support
contractor for LOGCAP IV. Two proposals were received and in February 2007 the ASC selected
Serco, Inc., of Vienna, VA. This contract will have a minimum value of $613,677 with a contract
period of one base year followed by up to four one-year options with a maximum annual contract
value of $45 million and a maximum contract value of $225 million.39
The ASC news release announcing the initial award selection described the range of logistical and
program services provided under the contract. They appear on ASC’s website.
Augmenting the Army’s capability to develop and update worldwide
management and staffing plans for contingencies;
working with LOGCAP IV performance contractors to assure that they
understand these plans;
helping theater planners integrate LOGCAP into their plans;
assisting planners in incorporating a broad range of contracted logistics support;
developing scopes of work officially referred to as procurement work statements;
preparing independent government cost estimates which are compared against
the contractor’s bids to assure valid costs for task orders;
conducting analysis of how performance contractors will do the work outlined in
the task orders’ scopes of work;
analyzing performance contractors’ costs;
working with the Army to measure LOGCAP IV contractor performance; and
recommending process improvements in the above actions.40
ASC Selected the Performance Contractors
The Army conducted a competition to select up to three performance contractors for services
similar to those rendered under LOGCAP III.41 Solicitations were issued in October 2006 and six
38
U.S. ,April 30, 2010.
U.S. Army Sustainment Command, February 16, 2007; News Release, U.S. Army Sustainment Command, June 27,
2007.
40
Ibid., p. 1.
41
From the Army’s FY2008 Budget Estimates for the Global War on Terrorism: LOGCAP augments combat support
and combat service support force structure by reinforcing military assets with civilian contract support. The program
provides primarily base life support services to the forces in theater. Base life support services provide a full spectrum
(continued...)
39
Congressional Research Service
9
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
proposals were received. In June 2007 the ASC selected three companies to serve as performance
contractors—DynCorp International LLC, Fort Worth, TX; Fluor Intercontinental, Inc,
Greenville, SC; and KBR, Houston, TX.
Protests
On June 27, 2007 the losing companies filed protests with GAO over the LOGCAP IV award
decision.42 GAO sustained the protests on October 5, 2007. The Army reopened the competition.
Five companies submitted bids. On April 17, 2008, the Army announced that it would re-award
the LOGCAP IV contract to the three companies previously awarded contracts under LOGCAP
IV.
Contract Details
The LOGCAP IV contract will cover a range of services:
supply operations, including food, water, fuel, spare parts, and other items;
field operations, including food, laundry, housing, sanitation, waste management,
postal services, and morale, welfare and recreation activities; and
other operations, including engineering and construction; support to the
communication networks; transportation and cargo services; and facilities and
repair.43
LOGCAP IV contracts were awarded as ID/IQ contracts with one base year followed by nine
option years. Each company will compete for task orders. Each of the three contracts will have a
maximum value of $5 billion per year, with a collective annual maximum value of $15 billion and
lifetime maximum value of $150 billion for LOGCAP IV.44
(...continued)
of services, including food service, power generation, electrical distribution, facilities management, dining facility
operations, pest management, hazardous and non-hazardous waste management, latrines, water systems, billeting
management, fire fighting and fire protection services, and laundry service operations. In Iraq, the program provides for
the Multi-National Force—Iraq base logistics support, base camp reorganization, the International Zone, Camp Bucca
Prisoner of War base operations support, and contractor support management in theater. In Afghanistan, the program
manages base operations support for the Coalition Joint Operations Area—Afghanistan, and the Kabul, Bagram,
Kandahar, and Salerno airfields. In Kuwait, the program manages Camps Spearhead, Udari, Arifjan; theater Retrograde
operations; the theater-wide transportation mission; theater oil analysis and test facilities; management and diagnostic
equipment, and bulk fuel operations. Army Operations and Maintenance, Volume 1, February 2007, p. 13, at
http://www.asafm.army.mil/budget/fybm/fybm.asp.
42
Kelley, Matt. GAO Challenges $150B Contract Awarded By Army: Urges Review of 10-year Deal to Support
Troops. USA Today, October 31, 2007, p. 5A. According to the article, the ASC spokesperson identified was Daniel
Carlson. According to Dan Gordon, a GAO official identified in the article, the ruling was issued under seal. Also, see
GAO Upholds Protests to Army’s Award of $50 Billion for LOGCAP 4. Engineering News-Record, November 5,
2007, Construction Week; pg. 9, Vol. 259, No. 16. An ASC spokesperson announced that the LOGCAP III contract
would be extended while the Army made a final decision.
43
Sheftick, Gary. Three Firms to Vie for LOGCAP Services in Theater. Department of Defense, U.S. Army Release.
April 18, 2008.
44
U.S. Army Sustainment Command. ASC Selects LOGCAP IV Contractors, June 27, 2007, at
http://www.aschq.army.mil/commandnews/default.asp.
Congressional Research Service
10
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Performance Task Orders
The U.S. Army Sustainment Command announced the award of the first performance task order
under LOGCAP IV, on September 25, 2008, to Fluor Intercontinental, Inc. The purpose of the
task order is to provide logistical support services in Afghanistan to personnel (both U.S.
personnel and coalition forces) in the field. The performance period is from September 25, 2008,
through September 24, 2009, and the task order is valued at $68 million.45
Each company has been awarded task orders under LOGCAP IV. The latest task order on
LOGCAP IV was awarded to KBR, representing KBR’s first task order under LOGCAP IV.46
Congressional Interest
Policymakers continue to express concern over the oversight of Iraq contracts for several
reasons—including the expense and difficulty of managing logistical support contracts;
allegations and reported instances of contract waste, fraud, abuse, and financial mismanagement;
and questions regarding DOD’s ability and capacity to manage such contracts. Some
policymakers have raised questions as to whether DOD has the right mix of acquisition workforce
personnel trained and equipped to oversee these large-scale contracts. Due to these and other
concerns, Congress extended the tenure of the Office of the Special Inspector General for Iraq
Reconstruction (SIGIR) from March 2004 through September 2009.47 SIGIR conducts audits and
investigations and presents recommendations for improving the management of Iraq
reconstruction and relief activities.48 The SIGIR has identified at least two ongoing investigations
into LOGCAP activities, as reported in the SIGIR’s latest quarterly report to Congress.49
Recent assessments from GAO, DOD’s IG, and the SIGIR reveal a lack of federal oversight,
management, and accountability for funds spent for Iraq contracting. According to Charles
Williams, Director, Defense Contract Management Agency, there are vacancies for more than 600
oversight positions in Iraq and Afghanistan.50 An audit conducted by the DOD IG revealed that
45
Theis, Linda, HQ, ASC. First LOGCAP IV Performance Task Order Awarded. Army.mil/News, at
http://www.army.mil/-news/2008/09/30/12832-first-logcap-iv-performance-task-order-awarded.
46
Several news outlets have reported the Army’s announcement of this task order award, including the following media
sources: An Up and Down Week for KBR. The Project on Government Oversight (POGO), March 1, 2010; Hefling,
Kimberly and Lardner, Richard, Army Awards Lucrative Iraq Support Contract to KBR, NewsWest.com, March 2,
2010, accessed online at http://www.newswest9.com/Global/story.asp?S=12069959; and KBR Awarded Major Task
Order Under LOGCAP IV, KBR, March 2, 2010, accessed online at http://www.kbr.com/Newsroom/PressReleases/2010/03/02/KBR-Awarded-Major-Task-Order-Under-Logistics-Civil-Augmentation-Program-LOGCAP-IVContract/.
47
P.L. 110-252.
48
See the Special Inspector General for Iraq Reconstruction, Quarterly Report to Congress, April 30, 2009, at
http://www.sigir.mil/reports/quarterlyreports/default.aspx. The SIGIR replaced the Inspector General for the Coalition
Provisional Authority (CPA-IG). As provided for in P.L. 108-106, the SIGIR provides an independent and objective
audit, analysis, and investigation into the use of U.S.-appropriated resources for Iraq relief and reconstruction. The
SIGIR, Stuart W. Bowen, Jr., was appointed as CPA-IG on January 20, 2004. He reports to both the Department of
State and the Department of Defense, provides quarterly reports and semi-annual reports to Congress, and has offices in
Baghad and Arlington, VA. For a summary of the history of U.S. reconstruction assistance in Iraq, see CRS Report
RL31833, Iraq: Reconstruction Assistance, by (name redacted)
.
49
Ongoing Oversight Activities of Other U.S. Agencies: DOD, Project Number D2009-DIPOAI-0141, “Review of
Army Decision Not to Withhold Funds on the Logistics Civil Augmentation Program (LOGCAP) III Contract, initiated
1/29/09; and DOD, D2008-D000AS-0270.000, Transition Planning for the Logistics Civil Augmentation Program IV
Contract, initiated 8/25/08. See http://www.sigir.mil/reports/quarterlyreports/Apr09/pdf/Section5_-_April_2009.pdf.
50
LOGCAP: Support Contracting Challenges in Iraq and Afghanistan. Public Hearing Before the Commission on
(continued...)
Congressional Research Service
11
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
the federal government failed to substantiate the disbursement of at least $7.8 billion of $8.2
billion dollars spent for goods and services in Iraq. In a May 22, 2008, congressional hearing
before the House Oversight and Government Reform Committee, DOD officials revealed
estimates that the Army disbursed $1.4 billion in commercial payments that lacked the minimum
supporting justification and documentation for a valid payment—such as certified vouchers and
invoices. In one reported instance, a $320 million payment in cash was made without justification
beyond a signature.51
The FY2009 National Defense Authorization Act (P.L. 110-417) contains provisions that impact
federal contracting. Some key highlights are provided here:52
Section 832 offers a “Sense of Congress” provision that security operations in
“uncontrolled or unpredictable high-threat environments” should ordinarily be
performed by the military forces; that private security contractors should not
perform inherently governmental functions in the area of combat operations, but
that it should be in the “sole discretion of the commander of the relevant
combatant command” to determine whether such activities should be delegated to
individuals not in the chain of command;
Section 833 amends 10 U.S.C. 1705 by designating an expedited hiring authority
for the DOD acquisition workforce;
Section 834 sets certain acquisition personnel requirements for military personnel
in the acquisition field;
Section 841 establishes a policy to address personal conflicts of interest by
employees of federal government contractors;
Section 842 requires the Secretary of Defense to ensure that DOD contractors
inform their employees, in writing, of employee whistleblower rights and
protections under 10 U.S.C. 2409, as implemented by Subpart 3.9, Part I, Title
48, Code of Federal Regulations;
Section 844 requires the Comptroller General to provide a report to the House
and Senate Armed Services Committees on the use of off-shore subsidiaries by
DOD contractors;
Section 845 sets requirements for the Secretary of Defense in the area of defense
industrial security;
Section 851 clarifies the pay and annuities of certain Members and staff related to
the Commission on Wartime Contracting in Iraq and Afghanistan;
Section 852 calls for the Army Audit Agency, the Navy Audit Services, and the
Air Force Audit Agency to each conduct a comprehensive audit of spare parts
(...continued)
Wartime Contracting in Iraq and Afghanistan, May 4, 2009. According to the testimony of Charles Williams, Director,
Defense Contracting Management Agency: “At present, we have 57 unfilled SME (Subject Matter Expert) theater
requirements: 36 SMEs in Iraq and 21 SMEs in Afghanistan. We have unfulfilled requirements for 335 CORs
(Contractor Officer Representatives) in Iraq and 335 CORS in Afghanistan.”
51
U.S. Congress. Accountability Lapses in Multiple Funds for Iraq. Testimony of Mary L. Ugone, Deputy Inspector
General for Auditing, U.S. Department of Defense, Office of the Inspector General. Hearing before the House
Oversight and Government Reform Committee, May 22, 2008.
52
The following provisions can be found, in their entirety, in S. 3001, the Duncan Hunter National Defense
Authorization Act for 2009, P.L. 110-417. Excerpts are provided here.
Congressional Research Service
12
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
purchases and depot maintenance and repair equipment activities for operations
in Iraq and Afghanistan, the purpose of which is to identify potential waste,
fraud, and abuse in the performance of DOD contracts, subcontracts, and task
and delivery orders, and make such audits available to the Commission on
Wartime Contracting in Iraq and Afghanistan;
Section 853 sets additional reporting requirements for contractors that perform
security functions in areas of combat operations and are involved in the discharge
of a weapon or other active, non-lethal countermeasures; and
Section 854 sets additional reporting requirements for contractors related to
alleged crimes by or against contractor personnel in Iraq and Afghanistan.
Finally, P.L. 110-417 contains Subtitle G – Government Wide Acquisition Improvement, which
includes provisions that affect all federal contracts. These provisions are known as the Clean
Contracting Act of 2008. Key highlights are provided here:
Section 862 limits the length of certain federal executive agency and DOD
contracts (for any contract in an amount greater than the simplified acquisition
threshold) by certain conditions: (1) the contract may not exceed the time
necessary to meet the “unusual and compelling requirements” of the work to be
performed; (2) the contract may not exceed the time necessary for the executive
agency to enter into a competition for a new contract; and (3) the contract may
not exceed one year unless the head of the executive agency determines that
exceptional circumstances apply.
Section 863 amends the Federal Acquisition Regulation (FAR) to require
competition for the procurement of property and services, in excess of the
simplified acquisition threshold, that is made under a multiple award contract,
unless the contracting officer waives the requirement on the basis of certain
determinations, and justifies the determination in writing.53
Section 864 requires a revision of the FAR to address the use of costreimbursement contracts, including guidance when they are to be used; under
what circumstances; justification; and what appropriate workforce resources are
necessary to award and manage cost-reimbursement contracts. This provision
also requires that the Inspector General for certain federal executive agencies
review the agency’s use of cost-reimbursement contracts for compliance with
such regulations, and that the Director of the Office of Management and Budget
(OMB) submit an annual report by March 1 of each year on each agency’s use of
cost-reimbursement contracts, and submit such a report to certain congressional
committees (House Oversight and Government Reform, Senate Homeland
Security and Governmental Affairs, House and Senate Appropriations, and the
House and Senate Armed Services Committees).
Section 865 requires that the OMB Director submit a comprehensive report on
the use of interagency contracts, and include guidelines to improve the
management of such contracts.
53
It should be noted that DOD has been subject to requirements for competition since 2001 under Section 803 of P.L.
107-107, which was repealed by P.L. 110-417. Section 863 subjects other federal agencies to the same requirements as
DOD, and provides a common authority for the requirements for all federal agencies.
Congressional Research Service
13
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Section 866 amends the FAR to minimize the excessive use of contracts by
contractors, subcontractors, or tiers of subcontractors, that add none or negligibly
no value to the work. This practice is sometimes referred to as “pass-through
charges or fees.” This provision would eliminate a contractor, subcontractor, or
tiers of subcontractors, from receiving indirect costs or profit on work performed
by a lower-tier contractor, to which the higher tier adds no value or negligible
value to the work. This section of the provision applies to any costreimbursement contract type, contract, or task or delivery order in an amount
greater than the simplified acquisition threshold. DOD will continue to be subject
to guidance pursuant to Section 852 of the John Warner National Defense
Authorization Act for Fiscal Year 2007 (P.L. 109-364).54
Section 867 amends the FAR to provide federal executive agencies (excluding
DOD) with guidance on the appropriate use of award and incentive fees in
federal acquisition programs. DOD will continue to be subject to guidance
pursuant to Section 852 of the John Warner National Defense Authorization Act
for Fiscal Year 2007 (P.L. 109-364).55
Section 868 amends the FAR to clarify the procurement of items from (and
minimize the abuse of) the commercial services inventory.
Section 869 authorizes the preparation and completion of the Acquisition
Workforce Development Strategic Plan for federal agencies (except DOD) to
develop “a specific and actionable 5-year plan to increase the size of the
acquisition workforce,” and to operate a government wide, acquisition intern
program for such federal agencies. The plan is to be completed within one year of
the enactment of this act and “in a fashion that allows for immediate
implementation of its recommendations and guidelines.”
Section 870 amends the Office of Federal Procurement Policy Act to establish a
Government Wide Contingency Contracting Corps. The Corps is under the
authority of the Administrator of General Services. Members of the Corps shall
be available for deployment in responding to an emergency or major disaster, or
contingency operation, both within and outside the continental United States.
Legislation passed in the FY2008 National Defense Authorization Act (P.L. 110-181) required
increased oversight and accountability for DOD contracting during combat operations. Overall
these provisions sought to enhance competition; reduce sole-source contracts; improve the
acquisition workforce; address waste, fraud, and mismanagement; and provide mechanisms for
greater oversight and transparency. A group of 24 provisions included in the bill known as the
Clean Contracting Act of 2008 were introduced in the 109th Congress and enacted in the 110th
Congress.56
The Defense Base Act (DBA) and LOGCAP
Congress is also interested in costs under the Defense Base Act (DBA). The DBA requires that
many federal government contractors and subcontractors provide workers’ compensation
54
Section 852. Report and Regulations on Excessive Past-Through Charges. This section applies to contracts for or on
behalf of DOD made on or after May 1, 2007.
55
Section 814. Linking of Award and Incentive Fees to Acquisition Outcomes.
56
P.L. 110-417 was enacted into law on October 14, 2008.
Congressional Research Service
14
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
insurance for their employees who work outside of the United States.57 The U.S. Army’s
LOGCAP covers costs for DBA insurance and includes significant overheard and other costs
beyond the costs of the actual insurance claims. In testimony before the Commission on Wartime
Contracting in Iraq and Afghanistan, the Director of the Defense Contract Audit Agency stated
that from 2003 to 2007 KBR incurred $592 million in costs for DBA insurance premiums.58
The Duncan Hunter National Defense Authorization Act of 2009 (P.L. 110-417) includes a
provision that requires the Secretary of Defense to adopt an acquisition strategy to acquire
insurance under the Defense Base Act; such a strategy should minimize overhead and coverage
costs, provide a low level of risk to DOD, and present a competitive marketplace strategy. A
report is due to congressional committees within 270 days of the date of the act’s enactment into
law.59
In September 2007, the U.S. Army Audit Agency (USAAA) released its audit report of DBA costs
under LOGCAP and uncovered rising program costs and wide fluctuations in insurance rates. In
early 2007, an audit of the DBA program was initiated by the U.S. Army Audit Agency (USAAA)
due to several factors, including the growing complexity of the DBA program, rising program
costs, and wide fluctuations in insurance rates.60 The audit report stated that the costs of DBA
insurance charges were paid through the Army’s LOGCAP contract with KBR. Chairman
Waxman offered the following testimony on the DBA financial transactions under the LOGCAP
contract:
On September 28, 2007, the Army Audit Agency issued a report examining DBA
payments under the single largest contract in Iraq, KBR’s $27 billion contract to provide
meals, housing, laundry, and other logistical support to the troops, also known as the
Logistics Civil Augmentation Program (LOGCAP). The findings in this audit provide an
illustration of the waste in the DBA program.
In its audit, the Army Audit Agency reported that the Army had reimbursed KBR for
DBA charges of $284 million made by its insurance company AIG through fiscal year
2005. Of this amount, the auditors reported that AIG would be required to pay out only
$73 million in actual claims. The auditors observed that “the cost of DBA insurance
substantially exceeded the losses experienced by the LOGCAP contractor.”
The data the Committee received from AIG indicate that expenses in providing DBA
insurance are typically 40% of premiums. Using this estimate, AIG’s expenses under the
LOGCAP contract would be $114 million, and its underwriting profit would be $97
million. The Army Audit Agency concluded that AIG’s rates appear “unreasonably high”
and “excessive,” warning of an “increased risk that the Army could be overcharged.” The
audit report found that there is “a high risk that the contractor may have been paying
more than necessary for this insurance” and that “significant annual increases insurance
57
The provisions of the Defense Base Act (DBA) are provided in statute at 42 U.S.C. §§ 1651-1654 and as part of the
Longshore and Harbor Workers’ Compensation Act (LHWCA) at 33 U.S.C. §§ 901-950. Regulations implementing the
DBA are provided in Parts 701-704 of Title 20 of the Code of Federal Regulations (CFR) and in the Federal
Acquisition Regulation at 48 C.F.R. §§ 28.305, 52.228-3, and 52.228-4.
58
Commission on Wartime Contracting in Iraq and Afghanistan. Testimony of April Stephenson, Director of the
Defense Contract Audit Agency, May 4, 2009.
59
Section 843. Requirement for Department of Defense to Adopt An Acquisition Strategy for Defense Base Act
Insurance. P.L. 110-417, enacted into law on October 14, 2008.
60
The USAAA does not publicly release its audit reports. However, the House Committee on Oversight and
Government Reform has posted a copy of this report, titled Audit of Defense Base Insurance for the Logistics Civil
Augmentation Program, Audit of Logistics Civil Augmentation Program Operations in Support of Operation Iraqi
Freedom, on its website at http://oversight.house.gov/documents/20080515102103.pdf.
Congressional Research Service
15
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
companies made to DBA insurance rates don’t appear to be consistent with the risk.”
Army auditors also raised concerns about the cost-plus nature of these charges.
As the auditors stated, “because the LOGCAP contract is primarily a cost-reimbursable
contract, the cost of this insurance is ultimately passed on to the government. As a result,
there is little incentive for KBR to control its costs for DBA insurance. To the contrary,
under the LOGCAP contract, KBR itself is paid its fee as a percentage of these DBA
costs, ranging from 1% to 3%, meaning that KBR may have received between $2.8
million and $8.4 million on top of AIG’s 61 profits. Although the Army auditors found that
“Army personnel at all levels appear to be aware of, and concerned with, the high cost of
DBA insurance,” they concluded that “sufficient action hadn’t been taken to scrutinize
these costs.” The auditors also warned that “we believe similar problems could exist on
other contracts outside the LOGCAP arena.”62
Background
Awarding of Defense Contracts
In most cases, federal government contracts are awarded under “full and open competition.”
However, there are exceptions, particularly during situations involving national security.63
Full and Open Competition
The foundation for the awarding of federal government contracts is in the Competition in
Contracting Act of 1984 (CICA),64 which explicitly states that the federal government “shall
obtain full and open competition through use of the competitive procedures in accordance with
the requirements of the CICA and the FAR.”65 The Competition in Contracting Act, FAR, and the
Defense Federal Acquisition Regulation Supplement (DFARS) outline at least seven exceptions
to the use of other than full and open competition in the awarding of contracts.66
61
AIG stands for American International Group, Inc.
U.S. Congress. House Oversight and Government Reform Committee Hearing. Defense Base Act Insurance: Are
Taxpayers Paying Too Much? Supplemental Information on Defense Base Act Insurance Costs. Memorandum from the
Majority Staff, to the Members of the House Oversight and Government Reform Committee, May 15, 2008, p. 7.
63
For a detailed discussion on the legal requirements for federal contracting, see CRS Report R40516, Competition in
Federal Contracting: An Overview of the Legal Requirements, by (name redacted) .
64
41 U.S.C. 253. CICA can also be found in Title 10 U.S.C., Chapter 137, and was included in Section 805 of the
FY2004 National Defense Authorization Act (P.L. 108-136).
65
41 U.S.C. 253 (a)(1)(A).
66
The Defense Federal Acquisition Regulation and AIDAR are supplements to the FAR. See DFARS, Subpart 206.3,
and AIDAR, Subpart 706.3, Other Than Full and Open Competition. The exceptions are: (1) There is only one
responsible source available to fulfill the contract requirements; (2) the federal agency’s need for these goods or
services is of such an unusual and compelling urgency that the federal government would be seriously injured if this
contract were not awarded; (3) the federal government needs to ensure that suppliers are maintained in the event of a
national emergency, or to achieve industrial mobilization, or to establish or achieve or maintain an engineering,
development, or research capability; (4) The federal government has an international agreement to make this
acquisition through means other than through full and open competition; (5) a statute specifically authorizes or requires
that the contract be made through a specific source; (6) The use of full and open competition may compromise national
security; (7) The public interest would be better served by use of other than full and open competition. The procedures
for submitting written justifications to use other than full and open competition, including review requirements and
delegation of authority, are outlined in DFARS, Subparts 206.303-1 and 206.304, and AIDAR 706.3. For a more
detailed discussion on the seven exceptions to the use of full and open competition, refer to CRS Report RS21555, Iraq
(continued...)
62
Congressional Research Service
16
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Emergency Contracting Authorities
Title 41 USC Section 428a grants special emergency procurement authority to heads of executive
agencies where it is determined that a procurement is to be used in support of a contingency
operation, or to facilitate defense against or recovery from nuclear, biological, chemical, or
radiological attack.
Contingency Contracting
Contingency contracting differs from emergency contracting—the first usually describes
situations where urgent requirements are necessitated by disasters, while the second usually
describes military, humanitarian, or peacekeeping operations.67 DOD has developed initiatives to
strengthen DOD contracting operations, particularly in contingency contracting situations.68
Section 817 of the National Defense Authorization Act for Fiscal Year (FY) 200669 directs the
Secretary of Defense, in consultation with the Chairman of the Joint Chiefs of Staff, to develop a
joint policy for contingency contracting during combat operations and post-conflict operations no
later than one year from the bill’s enactment. Sections 815 and 854 of the John Warner National
Defense Authorization Act for FY2007 required DOD to report to Congress on contingency
contracting requirements and program management, and to develop instructions to implement a
contingency contracting program. The report was issued in October 2007.70
Rapid Acquisition Methods
Section 811 of the FY2005 National Defense Authorization Act71 grants the Secretary of Defense
limited rapid acquisition authority to acquire goods and services during combat emergencies.
Also, Title 10, Section 2304 outlines the use of ID/IQ task orders, sealed bidding, certain contract
actions, and set-aside procurement under section 8(a) of the Small Business Act72 as examples of
ways to expedite the delivery of goods and services during combat operations or post-conflict
operations.
(...continued)
Reconstruction: Frequently Asked Questions Concerning the Application of Federal Procurement Statutes, by (name re
dacted).
67
Drabkin, David, and Thai, Khi V. Emergency Contracting in the US Federal Government. Journal of Public
Procurement 2007, Vol. 7, No. 1, p. 84.
68
For further information on DOD Procurement and Acquisition Policy governing contingency contracting, refer to
http://www.acq.osd.mil/dpap/pacc/cc/about.html.
69
P.L. 109-16.
70
Report on DOD Program for Planning, Managing, and Accounting for Contractor Services and Contractor Personnel
during Contingency Operations, accompanied by a memorandum to the Honorable Richard B. Cheney from the
Honorable P. Jackson Bell, Deputy Under Secretary of Defense for Logistics and Materiel Readiness, October 15,
2007. Section 815 covers the implementation of DOD Instruction (DODI) 3020.41,Contractor Personnel Authorized to
Accompany Armed Forces, October 3, 2005, at http://www.dtic.mil/whs/directives/corres/html/302041.htm.
71
Section 806 of the Bob Stump National Defense Authorization Act for Fiscal Year 2003 (10 U.S.C. 2302 note) is
amended through the passage of Section 811.
72
15 U.S.C. 637(a).
Congressional Research Service
17
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Audits, Investigations, and Reports
Role of Federal Agencies
No one federal agency has the sole mission to audit, investigate, or oversee DOD-appropriated
funds for troop support services under LOGCAP. Multiple agencies share responsibility, among
them the Defense Contract Audit Agency (DCAA), the Defense Contract Management Agency
(DCMA), the Army Audit Agency (AAA), and the DOD Inspector General.
Special Inspector General for Iraq Reconstruction (SIGIR)
Media reports suggests that a perceived lack of transparency in the earliest Iraq contracts led to
the appointment of the Special Inspector General for the Coalition Provisional Authority (now
SIGIR). SIGIR Stuart Bowen has audited and investigated contracts for Iraq reconstruction and
relief funds, although some projects have involved a blending of IRRF funds with DOD
appropriated funds.73 The SIGIR’s additional investigations into LOGCAP contracts have largely
described LOGCAP contracts as lacking transparency, oversight, and financial accountability, and
his investigations have documented some cases of waste, fraud, abuse, and financial
mismanagement. According to the Congressional Budget Office, the SIGIR has produced more
than 150 reports, audits, or investigations of reconstruction-related activities.74 Estimates have
been made that the SIGIR’s work has resulted in significant benefits to the federal government.75
In June 2007 the SIGIR released a report based on its partial audit of Task Order 130, awarded to
KBR on April 27, 2006, to provide support services to officials at the U.S. Embassy in Iraq as
well as other Iraq sites. This report found substantial deficiencies in both KBR’s ability to provide
enough data for the SIGIR to perform an adequate audit and investigation of (what appeared to
be) gross overcharges for fuel and food services. Additionally, the report found that the
government’s oversight and management of the contract was inadequate and contributed to the
SIGIR’s inability to completely audit and investigate the contract—including an evaluation of the
government’s ability to provide oversight and management.76
Overall, the SIGIR has recommended that the federal government “generally avoid the use of
sole-source and limited-competition contracting actions.”77 The report concludes that the use of
sole-source and limited competition contracting in Iraq should have ended sooner, and that
contracts issued previously under limited or sole-source competition should have been subject to
re-competition.
73
For a discussion of contract funds for Iraqi Relief and Reconstruction projects, see CRS Report RL31833, Iraq:
Reconstruction Assistance, by (name redacted)
. Also, for a discussion on federal procurement statutes as they affect Iraq
reconstruction projects see CRS Report RS21555, Iraq Reconstruction: Frequently Asked Questions Concerning the
Application of Federal Procurement Statutes, by (name redacted).
74
Paying for Iraq Reconstruction. An Update of the January 2004 analysis. Congressional Budget Office, December 8,
2006.
75
Senator Collins Works To Extend The Term of the Office that Oversees Billions in Iraqi Reconstruction Dollars.
Press Release of the United States Senate Committee on Governmental Affairs, November 13, 2006. Also, see SIGIR
website http://www.sigir.mil/ for audits reports.
76
Logistics Civil Augmentation Program Task Order 130: Requirements Validation, Government Oversight, and
Contractor Performance. SIGIR 07-001, June 22, 2007, at http://www.sigir.mil/reports/pdf/audits/07-001.pdf.
77
Lessons in Contracting from Iraq Reconstruction. Lessons Learned and Recommendations from the SIGIR, July
2006.
Congressional Research Service
18
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Special Inspector General for Iraq Reconstruction (SIGIR)
LOGCAP Reviews
Quarterly Report to Congress
The SIGIR’s July 30, 2010, Quarterly Report to Congress discussed two LOGCAP-related
activities, as described here:
(1) The Department of State (DOS) has requested permission to use the existing
LOGCAP program to continue to with essential services, including meals, mail delivery
and laundry, to the five Enduring Presence Posts (EPPs).78
(2) According to DOS, if State is unable to use the LOGCAP contract, DOS does not
have a plan to meet its support and requirements.79
Reviews of Task Orders 130 and 151
The SIGIR LOGCAP review of Task Order 130 is a continuation of a past review (awarded on
April 27, 2006, with an estimated value of $283 million) and a new review of LOGCAP Task
Order 151 (awarded on June 6, 2007, with an estimated value of $200 million). Both task orders
were awarded to KBR for support services to the Chief of Mission and Multi-National Force-Iraq
staffs (located at the U.S. Embassy-Iraq) and for services at other Chief of Mission sites within
Iraq (located in Baghdad, Basra, Al Hillah and Kirkuk.) SIGIR conducted its review at KBR sites
in Baghdad and involved interviews with personnel responsible for the administration and
oversight from DCMA, DCAA, and DOS; personnel with the Joint Area Support Group-Central
appointed as the Contracting Officer’s Technical Representatives (COTR); the LOGCAP Task
Order 151 Support Officer; personnel at the Army’s Logistic and Budget Offices, and KBR
managers and operational personnel.80 From the report, here is an excerpt which described the
costs:
Because these task orders provided support to both the Department of Defense (DOD)
and Department of State (DOS) missions in Iraq, DOD and DOS agreed that the
reimbursement of costs associated with these task orders would be shared 60% by DOS
and 40% by DOD. The total cost of these four task orders is approximately $1.5 billion.81
Overall, the SIGIR’s audit and investigation found that the federal government and KBR had
improved its oversight and management of Task Orders 130 and 151. However, the report
78
Lardner, Richard. State Department Wants a Mini-Army in Iraq. Army Times, June 14, 2010. According to the
article, “By September 2011,the 22 U.S.-led reconstruction teams spread throughout Iraq will be replaced by five
Enduring Presence Posts... State will be responsible for all the costs of operating these stations, including security, until
at least 2015.”
79
U.S. Congress. Special Inspector General for Iraq Reconstruction. Quarterly Report and Semiannual Report to the
United States Congress. July 30, 2010, pages 5 and 43.
80
Both Task Orders are a continuation of services previously awarded under Task Order 100 and Task Order 44.
Logistics Civil Augmentation Program Task Orders 130 and 151: Program Management, Reimbursement, and
Transition. SIGIR-08-002, October 30, 2007, Appendix A, Scope and Methodology p. 22, at http://www.sigir.mil/
reports/pdf/audits/08-002.pdf
81
Logistics Civil Augmentation Program Task Orders 130 and 151: Program Management, Reimbursement, and
Transition. SIGIR-08-002, October 30, 2007, pages 1-2, at http://www.sigir.mil/reports/pdf/audits/08-002.pdf.
Congressional Research Service
19
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
identified areas where the government should make specific improvements in both oversight and
management.82
DOD Inspector General
Thomas F. Gimble, Principal Deputy Inspector General for the Department of Defense, testified
at the September 20, 2007, hearing before the House Armed Services Committee on
“Accountability During Contingency Operations: Preventing and Fighting Corruption in
Contracting and Establishing and Maintaining Appropriate Controls on Materiel.”83 In his
testimony he described DOD’s past and present efforts to provide oversight for contracting during
contingency operations:
To date, over $550 billion has been appropriated to the Department of Defense in support
of the men and women of our Armed Forces in Southwest Asia and the fight against
terrorism. To provide oversight, we have over 225 personnel working on 29 audits and 90
investigations that address a wide variety of matters to include contracting,
accountability, and required documentation. Additionally, we are working with other
DoD organizations, such as the Army Audit Agency, the Army Criminal Investigation
Command, and the Defense Finance and Accounting Service, to evaluate and provide
recommendations for actions addressing these critical mission support areas. 84
He also described the formation of a new partnership to combine the efforts of multiple federal
agencies to combat both waste, fraud, abuse, and mismanagement of Iraq reconstruction
contracts:
More recently, as a result of the magnitude of alleged criminal activities within the Iraqi
theater, a group of Federal agencies has formalized a partnership to combine resources to
investigate and prosecute cases of contract fraud and public corruption related to U.S.
Government spending for Iraq reconstruction. The participating agencies in the
International Contract Corruption Task Force (ICCTF) are DCIS; Army CIDs Major
Procurement Fraud Unit; the Office of the Inspector General, Department of State; the
FBI; the Special Inspector General for Iraq Reconstruction; and the Office of the
Inspector General, Agency for International Development.
The ICCTF has established a Joint Operations Center which is a case coordination cell
and criminal intelligence element aimed at achieving maximum interagency cooperation
to successfully prosecute fraud and corruption cases in support of the war effort in Iraq.
The mission and objectives of the ICCTF are a shared responsibility of the participating
agencies. Case information and criminal intelligence are shared without reservation and
statistical accomplishments will be reported jointly.
As a result of closed and ongoing investigations, five Federal criminal indictments and
ten Federal criminal information have been issued, and two Article 32 hearings under the
Uniform Code of Military Justice have been conducted. As a result of the investigations,
nine U.S. persons and one foreign person have been convicted of felonies, resulting in a
total of approximately fifteen years of confinement and eleven years of probation. Four
individuals and one company were debarred from contracting with the U.S. Government;
nineteen companies and persons were suspended from contracting; and two contractors
signed settlement agreements with the U.S. Government. In all, $9.84 million was paid to
82
Ibid, pp. 4-20.
Statement of Mr. Thomas F. Gimble, Principal Deputy Inspector General, Department of Defense, before the House
Armed Services Committee, September 20, 2007.
84
Ibid, p. 1.
83
Congressional Research Service
20
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
the U.S. in restitution; $323,525 was levied in fines and penalties; $3,500 was forfeited;
and $61,953 was seized.85
Government Accountability Office (GAO)
GAO has identified DOD contract management as a high-risk area and monitors DOD’s
performance with periodic progress updates.86 GAO has conducted numerous studies of Iraq
contracting including several studies of logistical support contracts.87 Since 2003 GAO has issued
a number of Iraq-related reports and testimonies to Congress.
The Comptroller General David Walker appeared in July 2007 before the Senate Homeland
Security and Governmental Affairs Committee to discuss four specific challenges facing federal
agencies in the oversight and management of contracts. There he made several important
observations:
Managing risks when requirements are in transition requires effective oversight. DOD
lacked the capacity to provide sufficient numbers of contracting, logistics, and other
personnel, thereby hindering oversight efforts. The challenges faced in Iraq are a symbol
of systematic challenges facing DOD. DOD cannot develop a complete picture of the
extent to which it relies on contractors to support its operations. Information on the
number of contractor employees, and the services they provide, is not aggregated within
DOD or its components. DOD recently established an office to address contractor support
issues, but the office’s specific roles and responsibilities are under study. DOD and its
contractors need to clearly understand DOD’s objectives and needs. To produce desired
outcomes with available funding and within required time frames, they need to know the
goods or services required, the level of performance or quality desired, the schedule, and
the cost.88
Potential Oversight Issues
Potential contract oversight issues that Congress may choose to examine include various aspects
of contract administration, such as contract costs; development of contract requirements; costsreimbursement and sole-source contracts; transparency; and the size, shape, and skill diversity of
the acquisition workforce.
Contract Oversight
One rationale often cited for the outsourcing of program management to industry is that DOD no
longer has the in-house expertise needed to manage such complicated acquisition programs.
Some Members of Congress may want DOD to develop a long-term plan to restore in-house
expertise to make the government a smarter customer. Because of several cases in which highprofile weapons acquisition programs have been affected by escalating costs and technical
85
Ibid, pp. 11-13.
“High Risk Area: Defense Contract Management.” GAO-05-207, February 2005.
87
GAO-04-854, Military Operation. DOD’s Extensive Use of Logistics Support Contracts Requires Strengthened
Oversight. July 2004.
88
GAO-07-358T, p. 13. Also see GAO-07-1098T. Federal Acquisitions and Contracting. Systemic Challenges Need
Attention. Statement of David M. Walker, Comptroller General of the United States, July 17, 2007; GAO-07-145.
Military Operations: High-Level DOD Action Needed to Address Long-standing Problems with Management and
Oversight of Contractors Supporting Deployed Forces, December 2006, p. 53.; and GAO-04-854. Military Operations:
DOD’s Extensive Use of Logistics Support Contracts Requires Strengthened Oversight. July 2004, p. 67.
86
Congressional Research Service
21
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
shortcomings, Congress may choose to review the management of individual programs and the
evolution of DOD’s acquisition management processes with an eye toward using the FY2008
funding bills to strengthen the government’s hand in dealing with industry. As an example,
Secretary of the Navy Donald C. Winter and Chief of Naval Operations Adm. Michael G. Mullen
have reported that the Navy intends to reclaim some of the authority over ship design it has ceded
to industry. Congress may also choose to study the Army’s Future Combat System (FCS) and may
question the amount of managerial discretion the Army has vested in the Lead System Integrator
(LSI).89
Contract Administration
Contract administration includes contract management and contract oversight. FAR Part 37 states
that “agencies shall ensure that sufficiently trained and experienced professionals are available to
manage contracts.”90 The burden rests with the federal government to ensure that enough
appropriately trained professionals are available to manage contracts. This is essential,
particularly before the requirements generation process, when the government determines the
scope of work to be completed. Contract management is also described in the Office of Federal
Procurement Policy’s (OFPP) “Guide To Best Practices for Contract Administration” where it
states that “the technical administration of government contracts is an essential activity ... [it is]
absolutely essential that those entrusted with the duty ensure that the government gets all that it
bargains for ... and they must be competent in the practice of contractor administration.”91
Over the past few years the size, shape, and complexity of logistical support service contracts
have grown with the technical requirements. However, the size of the federal contractor
workforce has decreased. There is now an imbalance—there are fewer federal contracting
officials to manage the large-scale contracts and in some cases the government has sought to hire
contractors to do the job that federal employees use to perform. For example, GAO reported that
military officials utilizing LOGCAP had little understanding of LOGCAP or their contract
management responsibilities. Additionally, some logistical support units intended to assist
military commanders had no prior LOGCAP or contracting experience.92
Two former OFPP administrators, Steven Kelman and Allan Burman, stated that the current
contracting situation creates a crisis. Here they offer their assessment:
Hiring contracting officials is hardly the way to dress for political success—who wants to
bring in more “bureaucrats?”—but there can’t be well-managed contracts without people
to manage them. The current situation creates a vicious circle: Overstretched people
make mistakes, producing demands for more rules, creating additional burdens, giving
people even less time to plan effective procurement and manage performance.93
89
For a discussion of the LSI concept, see CRS Report RS22631, Defense Acquisition: Use of Lead System Integrators
(LSIs)—Background, Oversight Issues, and Options for Congress, by (name redacted)
; CRS Report RL33753,
Coast Guard Deepwater Acquisition Programs: Background, Oversight Issues, and Options for Congress, by Ronald
O’Rourke; and CRS Report RL32888, Army Future Combat System (FCS) “Spin-Outs” and Ground Combat Vehicle
(GCV): Background and Issues for Congress, by (name redacted) and (name redacted) .
90
FAR Part 37.
91
OFPP Guide at http://www.acqnet.gov/comp/seven_steps/library/OFPPguide-bp.pdf.
92
Logistical support units write performance statements of work, prepare independent government cost estimates, and
review contractor estimates on behalf of the government. See GAO-04-854. Military Operations: DOD’s Extensive Use
of Logistics Support Contracts Strengthen Oversight, July 21, 2004.
93
Burman, Allan and Kelman, Steven. “Better Oversight of Contractors,” The Boston Globe, January 16, 2007, p. A9.
Congressional Research Service
22
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
It is important that both civilian and military procurement sectors have qualified and experienced
contract professionals. In the case of service contracts, having professionally trained contracting
personnel could be even more critical than contracts for tangible goods. With tangible goods,
there is an identifiable product. In the absence of a product, it becomes even more important that
DOD and the contractor both exercise good stewardship of federally appropriated dollars.
DOD Contracting Officials
Contracting officials are expected to make tough decisions. As an example, Ms. Bunnatine
Greenhouse, formerly the highest-ranking civilian at the U.S. Army Corps of Engineers
(USACE), raised important questions on the rationale for the awarding of one KBR contract: first,
in her opinion, because the awarding of the contract lacked an appropriate level of competition;
and second, because in her view there existed an organizational conflict of interest. She objected
to the awarding of one contract award as well as the five-year contract term.94 The basis for her
refusal to approve the proposed five-year, sole-source contract between KBR and the U.S. Army
[for the Restore Iraqi Oil (RIO) contract] was because (1) KBR had been paid $1.9 million to
draft a contingency plan to design the “guts” of the contract, including the process, budget, and
other details; and (2) selecting KBR for the five-year contract would violate procurement
protocol, as (reportedly, Ms. Greenhouse stated) contractors who draw up a contingency plan
cannot be allowed to bid on the job to execute the same plan.95 She stated that bidding on the
contract would give KBR an unfair advantage over any competitors. When pressured to sign the
KBR contract, Ms. Greenhouse added the following contract language: “I caution that extending
this sole source effort beyond a one-year period could convey an invalid perception that there is
not strong intent for a limited competition.”96 The contract was later investigated by the SIGIR.97
Various media reports suggested that in the case of Bunnatine Greenhouse, a trained and
experienced senior DOD contract management official was eventually demoted and later fired for
doing her job.98
Another senior DOD civilian testified that he made a decision to award KBR a task order under
the LOGCAP contract without conducting any competition. Michael Mobbs, then-Special
Assistant to the Under Secretary of Defense for Policy, testified that he made the decision to
award KBR the contingency planning contract over the objections of an attorney with the Army
Materiel Command. The attorney had determined that the oil-related task order was outside of the
scope of the LOGCAP troop support contract. Later, GAO concluded that the lawyer’s position
94
Schnayerson, Michael. “Oh, What a Lucrative War,” Vanity Fair, April 2005, p. 9.
For additional information, see CRS Report RL32229, Iraq: Frequently Asked Questions About Contracting, by
(name redacted) et al.
96
Vanity Fair, p. 149.
97
It should be noted here that the KBR sole-source contract, according to the SIGIR, complied with applicable federal
regulations for sole-source contracts, according to the SIGIR. The SIGIR concluded that “the justification used was that
KBR had drafted the Contingency Support Plan (CSP), had complete familiarity with it, had the security clearances
necessary to implement it, and the contract needed] to be immediately available to implement.” Lessons In Contracting
and Procurement. Iraq Reconstruction. Special Inspector General for Iraq Reconstruction. July 2006, p. 20.
98
Witte, Griff. Halliburton Contract Critic Loses Her Job. Washington Post, August 29, 200, p. A11. For additional
information, see the following documents: Letter to Tom Davis, Chairman, Committee on Government Reform, House
of Representatives, from Henry A. Waxman, Ranking Minority Member, House of Representatives, November 10,
2004; Testimony of Bunnatine Greenhouse before the Senate Democratic Policy Committee, June 27, 2005; and Letter
to Donald Rumsfeld, Secretary of Defense, from Senators Byron L. Dorgan and Frank Lautenberg, and Representative
Henry A. Waxman, August 29, 2005.
95
Congressional Research Service
23
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
was the correct one and that the work “should have been awarded using competitive
procedures.”99
Development of Contract Requirements
LOGCAP contracts have often bypassed the process to define realistic funding, appropriate time
frames, and other important requirements through the use of “undefinitized” contract actions.
Undefinitized contract actions100 do not require that the DOD contracting official write a
completed performance work statement before the work is performed. Some proponents of
undefinitized task orders have stated that they give the contractor more flexibility in getting work
started sooner. However, recent DCAA audits have found that these undefinitized task orders
have given KBR a significant cost advantage. Auditors have found that DOD contracting officials
were more willing to rely on KBR’s costs estimates, estimates later found to be greatly inflated.
According to DCAA auditors, DOD contracting officials rarely challenged these cost estimates.
The estimates became the baseline from which KBR established their costs upon which to bill the
government, which later increased their overall profit.
In testimony before the Senate Armed Services Committee, the SIGIR stated that contracting
personnel must be provided with an adequate description of a customer’s needs. The inability to
properly define and prepare requirements appeared to be a significant oversight challenge in the
Iraq contracting process.101
Use of Indefinite-Delivery/Indefinite-Quantity Contracts102
FAR Subpart 16.5 defines Indefinite-Delivery/Indefinite-Quantity (ID/IQ) contracts.103 In the case
of ID/IQ contracts, task and delivery orders are issued; these orders do not define a firm quantity
of goods or services.104 While task and delivery orders under ID/IQ contracts are not subject to
the Competition in Contracting Act (CICA), they are subject to competition-type requirements
under other provisions of law. Task orders are the “to do” portion of the contract, the contractor’s
action list. LOGCAP contracts allow task orders to be approved as needed without being subject
to competition among multiple contractors. Task orders are not contracts but can potentially allow
significant amounts of work to be performed on a non-competitive basis. Task Order 59 was one
of the largest single task orders on the LOGCAP III contract. It was issued in May 2003 and
includes various discrete functions, supporting up to 130,000 U.S. troops, and has reportedly
resulted in estimates of charges to the government of about $5.2 billion dollars from June 2003
through June 2004.
99
Briefing by Michael Mobbs, Special Assistant to the Undersecretary of Defense for Policy, for staff of the House
Government Reform Committee, June 8, 2003. Also, see GAO-04-605. Rebuilding Iraq: Fiscal Year 2003 Contract
Award Procedures and Management Challenges, June 2004.
100
Also referred to as undefinitized task orders.
101
Testimony of the Special Inspector General for Iraq Reconstruction, before the Senate Armed Services Committee,
February 7, 2006.
102
For a discussion of indefinite-delivery/
103
FAR Subpart 16.5 Indefinite-delivery/indefinite-quantity contracts, also known as ID/IQ contracts, supply an
indefinite quantity of supplies, goods, or materials, for an indefinite period of time. See FAR, Part 16, Types of
Contracts.
104
Indefinite-quantity contracts are also known as delivery order contracts or task order contracts.
Congressional Research Service
24
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Costs and the Use of No-Bid and Sole-Source Contracts
Much has been written in the media about the use of sole-source contracting in Iraq.105 In general,
most authorities believe that government contract costs are influenced significantly by the degree
of competition; that having several competitors will reduce overall cost. However, questions have
been raised as to whether contract costs in a war zone are inherently uncontrollable. DOD has
argued that Iraq contracting costs are expensive because of the uncertainty of war-related
requirements for goods and services. Government contingency contracting in times of war has
often favored using programs such as LOGCAP because it enables contracting officials to move
quickly to secure contractors, who in turn can be deployed quickly into the combat theater.
While full and open competition is the standard for government contracting, full and open
competition has not been the standard for contracting for troop support services under LOGCAP.
One report stated that of the $145 billion in non-competitive contracts awarded by the federal
government in 2005, $97.8 billion was awarded in “no-bid” contracts. Of that $97.8 billion in
contracts, $63.4 billion was awarded under the rationale that only one contractor could supply the
needed goods or services. The remaining $34.4 billion was awarded in no-bid contracts under a
variety of other exceptions to full and open competition. $8.7 billion was awarded for emergency
situations, and $2.9 billion was awarded for circumstances where a statute authorizes or requires
restricted competition.106 Finally, $47.2 billion in contracts was awarded in cases where the
competitive range was limited to a small group of companies.
The Special Investigations Division of the House Government Reform Committee has issued a
report titled Dollars, not Sense: Government Contracting Under the Bush Administration.
According to this report, in 2000 the federal government awarded $67.5 billion in noncompetitive contracts; that figure rose to $145 billion in 2005, an increase of 115%. While the
contracts awarded were larger, the value of contracts overseen by the average government
procurement official rose by 83% (between 2000-2005).
Cost-reimbursement Contracts
Cost-reimbursement contracts can be (1) cost-plus award fee; (2) cost-plus incentive fee; or (3)
cost-plus fixed fee.107 In 2000, the federal government spent $62 billion on cost-plus contracts; in
2005, that figure increased to $110 billion. Nearly half of all costs-plus contracts ($52 billion)
were costs-plus award fee contracts. LOGCAP was the single largest cost-plus award fee contract,
and at one time was valued at about $16.4 billion.108
Use of Overhead Fees
The SIGIR’s past investigations into reconstruction contracts revealed that, in some contracts,
overhead expenses accounted for more than half of the costs that Kellogg, Brown, and Root
(KBR) billed the federal government. A recent audit report, “Review of Administrative Task
Orders for Iraq Reconstruction Contracts,” found that relatively high overhead costs were
105
Sole-source contracts are contracts which are not subject to competition.
Dollars, Not Sense: Government Contracting Under the Bush Administration. United States House of
Representatives, Committee on Government Reform - Minority Staff, Special Investigations Division, p. 7-9.
107
Cost-reimbursement types of contracts provide for payment of allowable incurred costs, to the extent prescribed in
the contract. These contracts establish an estimate of total cost for the purpose of obligating funds and establishing a
ceiling that the contractor may not exceed (except at its own risk) without the approval of the contracting officer.
108
Army Field Support Command, Media Obligation Spreadsheet, April 20, 2006.
106
Congressional Research Service
25
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
charged, and that these costs were significantly higher than work performed by other companies
in Iraq. For these contracts, overhead costs ranged from 11% to 55% of projected contract
budgets. For example, the SIGIR found that in five KBR projects, administrative costs
outdistanced the costs of the projects alone. For example, the report cites a project where
administrative costs totaled about $52.7 million, while the actual project costs were about $13.4
million. In another case, the combined administrative costs for five contractors totaled about $62
million, while the direct construction costs totaled $26.7 million.109 The SIGIR found that
overhead expenses accounted for more than half of the costs KBR billed the federal government.
Overhead fees can also result as a part of fees passed from one contractor to another. One such
example is the case of Blackwater Security Firm’s contract for private security services in Iraq.
Blackwater’s contract paid workers who guarded food trucks a salary of $600 a day. The
company added overhead costs and a 36% markup to its bill, then forwarded the bill to a Kuwaiti
company. The Kuwaiti company then added costs and profit, then sent the bill to the food
company. The food company did the same, and finally sent the bill to KBR. KBR passed its cost
to DOD. Yet the U.S. Army stated in a congressional committee hearing that it had never
authorized KBR to enter into a subcontracting relationship with Blackwater. The matter remains
pending.110
Transparency
Transparency allows the federal government to better administer contracts and oversee
contractors. For example, the federal government has had difficulty getting certain contractors to
provide important information on their invoices and billing statements. The SIGIR released a
series of audit and investigative reports which drew attention to barriers that hampered the
government’s efforts. In one report, SIGIR Bowen reported that it was difficult to complete the
investigation into the KBR contracts because KBR “routinely and inappropriately marked their
data as proprietary.”111
Another problem with a lack of transparency is the relationship between the federal government,
the prime contractor, and the subcontractors. The federal government has a contractual
relationship with the prime contractor, not with subcontractors. Thus the government may be
somewhat limited in providing full accountability for tax-payer dollars. While the prime
contractor-subcontractor relationship is between private sector companies, the monies are from
public funds.112
Acquisition Workforce
Secretary Gates has announced a move to significantly increase the size of the defense acquisition
workforce, primarily achieved by converting about 10,000 private-sector contractor positions to
full-time government positions, and hiring an additional 10,000 defense acquisition workforce
employees by 2015. According to DOD officials, the long-term goal is to increase the size of the
109
Powers, Mary Buckner. Congress Moves To Reinstate Iraq Contracting Overseer. Engineering News-Record, Vol.
257, No. 19, p. 13. November 13, 2006.
110
“Watching War Costs,” The News & Observer, Raleigh, NC, December 9, 2006. Retrieved January 21, 2007, at
http://www.nexis.com/research/search/submitViewTagged.
111
Powers, Mary Buckner. Congress Moves To Reinstate Iraq Contracting Overseer. Engineering News-Record, Vol.
257, No. 19, p. 13. November 13, 2006.
112
“Commentary: Watching War Costs,” The News & Observer, Raleigh, NC, at http://www.nexis.com/research/
search/submitViewTagged.
Congressional Research Service
26
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
organic defense acquisition workforce to its 1998 levels of approximately 147,000 employees. At
the same time, statements issued by President Obama have signaled his intention to reduce
defense contracting spending by reviewing DOD’s acquisition processes prior to the
commencement of the next Quadrennial Defense Review. President Obama has reportedly
announced that he may perform a line-by-line review of the federal budget, eliminate government
programs that are not performing, reduce federal spending on contractors by at least 10%, and
require each federal agency to justify the use of cost-reimbursement (also known as costs-plus)
and sole-source (also known as non-competitive) contracts with possible implications for DOD
acquisition policy.113
According to DOD, its acquisition workforce has been reduced by more than 50% between 1994
and 2005.114 In future years, between 2006-2010, half of the federal acquisition workforce will be
eligible to retire.115 It has been reported that DOD does not have sufficient numbers of contractor
oversight personnel, particularly at deployed locations. This limits DOD’s ability to assure that
taxpayer dollars are being used in a judicious manner. For example, in recent testimony before
Congress, a GAO official reported that if adequate staffing had been in place, the Army could
have realized substantial savings on LOGCAP contracts in Iraq.116 The GAO official also stated
that one DCMA official, who is responsible for overseeing the LOGCAP contractor’s
performance at 27 locations, reported that he was “unable to visit all of those locations during his
six-month tour to determine the extent to which the contractor was meeting the contract’s
requirements.”117
Earlier mandates to reduce the size of the DOD acquisition workforce reflected Congress’ view
that the workforce had not been downsized enough—that reductions continued to lag in
proportion to the decline in the size of the overall defense budget, in general, and to the
acquisition portion of the defense budget, in particular. At that time, Congress and DOD were at
odds over the need for further reductions in the defense acquisition workforce. Reducing the
defense acquisition workforce had been viewed by the Congress, in the past, as a necessary
113
See the following two documents: Defense Budget Recommendation Statement, as prepared for delivery by
Secretary of Defense Robert M. Gates, Arlington, VA, Monday, April 06, 2009; and The White House, Office of the
Press Secretary, Government Contracting: Memorandum for the Heads of Executive Departments and Agencies, March
4, 2009.
114
In 1998, the House National Security Committee asked GAO to review DOD’s progress in achieving a 25-percent
reduction in the acquisition organizations’ workforce, examine the potential savings associated with such reductions,
determine the status of DOD efforts to redefine the acquisition workforce, and examine DOD’s efforts to restructure
acquisition organizations. GAO concluded that “DOD has been reducing its acquisition workforce at a faster rate than
its overall workforce and is on schedule to accomplish a 25-percent reduction by the fiscal year 2000. However,
potential savings from these reductions cannot be precisely tracked in DOD’s budget. In addition, some of the potential
savings from acquisition workforce reductions may be offset by other anticipated costs. Such costs include those for
contracting with private entities for some services previously performed by government personnel (i.e., substituting one
workforce for another.” U.S. Congress. General Accounting Office. Defense Acquisition Organizations: Status of
Workforce Reductions. Report to the Chairman, Committee on National Security, House of Representatives.
GAO/NSIAD-98-161. June 1998. 20 pages. For another source of data on the federal acquisition, see Report on the
Federal Acquisition Workforce, FY2003-2004, Federal Acquisition Institute Report, Executive Summary, p. vii.
115
S. Assad, Director, Defense Procurement and Acquisition Policy, in testimony before the Acquisition Advisory
Panel, June 13, 2006, p. 57-58 (excerpted from the Final Panel Working Draft, Report of the Acquisition Advisory
Panel to the Office of Federal Procurement Policy and the U.S. Congress, December 2006.
116
GAO-07-359T. Defense Acquisitions: DOD Needs to Exert Management and Oversight to Better Control
Acquisition of Services. Statement of Katherine V. Schinasi, Managing Director, Acquisition and Sourcing
Management, before the Subcommittee on Readiness and Management Support Committee on Armed Services, United
States Senate, January 17, 2007.
117
GAO-07-359T, p. 8.
Congressional Research Service
27
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
requirement for eliminating wasteful spending, and providing DOD with increased funding for
other priorities.
Staffing shortages in the defense contracting personnel to oversee Iraq contracts have become part
of a larger, systemic problem within DOD.118 In reducing the size and shape of the federal
acquisition workforce, an unanticipated result has been the increase in the growth of the private
sector service contracts. With the growth in service contracting; the increase in the number of
complex, billion dollar contracts; and the decline in the number of federal acquisition workforce
employees, some officials have asserted that there are not enough DOD contracting officials,
onsite in Iraq, who are available and experienced enough to manage the complexities of the new
acquisition programs, or oversee private sector contractors.
It appears to some that DOD has downsized the federal acquisition workforce, particularly those
that oversee large-scale contracts like LOGCAP, to dangerously low levels. They note that the
past downsizing of the defense acquisition workforce has resulted in the loss of technical
personnel and a talent drain on DOD’s ability to meet its mission and objectives. There are
concerns over potential deficits and imbalances in the skills and experience levels of personnel
who manage large-scale weapon acquisition programs and defense contracts.
The Gansler Commission
The Secretary of the Army commissioned a study headed by former Deputy Secretary of Defense
Jacques Gansler to analyze “structural weaknesses and organizational deficiencies in the Army’s
acquisition and contracting system used to support expeditionary operations.” Dr. Gansler has
recently presented the commission’s findings and recommendations before Congress.119 Here is
an excerpt of the commission’s analysis of the acquisition workforce:
The expeditionary environment requires more trained and experienced military officers
and non-commissioned officers (NCOs). Yet, only 3 percent of Army contracting
personnel are active duty military and there are no longer any Army contracting career
General Officer (GO) positions. The Army’s acquisition workforce is not adequately
staffed, trained, structured, or empowered to meet the Army needs of the 21 st Century
deployed war fighters. Only 56 percent of the military officers and 53 percent of the
civilians in the contracting career field are certified for their current positions.
Notwithstanding a seven-fold workload increase and greater complexity of contracting,
the Institutional Army is not supporting this key capability. Notwithstanding there being
almost as many contractor personnel in the Kuwait/Iraq/Afghanistan theater as there are
U.S. military, the Operational Army does not yet recognize the impact of contracting and
contractors in expeditionary operations and on mission success. What should be a core
competence—contracting (from requirements definition, through contract management,
to contract closeout)—is treated as an operational and institutional side issue. 120
118
The same observations were made about the U.S. Coast Guard’s Deepwater contract. According to Admiral Thad
Allen, Commandant, the issue concerns “the capacity of our acquisition staffs to deal with the myriad definitization of
task orders, particular line items, the ability to interact with the extensive amount of nodes that you have in Integrated
Coast Guard Systems ... I’m not sure that we understood going how much we had to be prepared to handle the work
load in terms of capacity and competency in human capital, and that’s one of the main things I’m focusing on.” Cavas,
Christopher P. Millions for Deepwater, No One to Spend It. U.S. Coast Guard Adds Acquisition Experts for
Modernization. Defense News, Vol. 22, No. 2, January 8, 2007, p. 1.
119
Senate Armed Services Committee, Subcommittee on Readiness and Management Support on December 6, 2007.
http://armed-services.senate.gov/e_witnesslist.cfm?id=3048.
120
U.S. Army. Urgent Attention Required: Army Expeditionary Contracting, Report of the Commission on Army
Acquisition and Program Management, November 1, 2007, p. 10, at http://www.army.mil/docs/
(continued...)
Congressional Research Service
28
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
The commission’s report recommends that the Army makes systemic and fundamental changes in
the way it conducts business, and has divided its recommendations into four major areas as
described here:
Increase the stature, quantity, and career development of military and civilian
contracting personnel (especially for expeditionary operations);
Restructure the organization and restore responsibility to facilitate contracting
and contract management in expeditionary and CONUS operations;
Provide training and tools for overall contracting activities in expeditionary
operations; and
Obtain legislative, regulatory, and policy assistance to enable contracting
effectiveness in expeditionary operations.121
Independent Panel to Examine the Defense Contract Audit Agency
DOD has asked the Defense Business Board to examine the performance of the Defense Contract
Audit Agency (DCAA) and report their findings within 60 days.122 DCAA has come under
increased scrutiny, in part, because of a July 2008 GAO report which investigated certain
complaints it received from the FraudNet hotline alleging questionable and improper auditing
irregularities. GAO found that the allegations were substantiated; the report concluded with the
following observations, as stated below:
In the cases we investigated, pressure from the contracting community and buying
commands for favorable opinions to support contract negotiations impaired the
independence of three audits involving two of the five largest government contractors. In
addition, DCAA management pressure to (1) complete audit work on time in order to
meet performance metrics and (2) report favorable opinions so that work could be
reduced on future audits and contractors could be approved for direct-billing privileges
led the three DCAA personnel to take inappropriate short cuts—ultimately resulting in
noncompliance with GAAS and internal DCAA CAM guidance. Although it is important
for DCAA to issue products in a timely manner, the only way for auditors to determine
whether “prices paid by the government for needed goods and services are fair and
reasonable” is by performing sufficient audit work to determine the adequacy of
contractor systems and related controls, and contractors compliance with laws,
regulations, CAS, and contract terms. Further, it is important that managers and
supervisory auditors at the three locations we investigated work with their audit staff to
foster a productive, professional relationship and ensure that auditors have the
appropriate training, knowledge, and experience. 123
(...continued)
Gansler_Commission_Report_Final_071031.pdf.
121
Ibid, p. 13.
122
From the Defense Business Board’s website: “The Defense Business Board, under the provisions of the Federal
Advisory Committee Act of 1972, as amended, shall provide the Secretary of Defense, through the Deputy Secretary of
Defense, independent advice and recommendations on effective strategies for the implementation of best business
practices of interest to the Department of Defense. The ultimate objective of this advice is to enhance the efficiency and
effectiveness of organizational support to the nation’s warfighters.” Board members are appointed by the President and
serve for two-year terms. For further information, refer to http://www.defenselink.mil/dbb/charter.html.
123
U.S. Government Accountability Office. DCAA Audits: Allegations That Certain Audits at Three Locations Did
Not Meet Professional Statements Were Substantiated. Report to Congressional Addressees, GAO-09-857, July 2008,
p. 65. Also, see Peters, Katherine McIntire. Defense Taps Independent Panel to Examine Contracting Agency.
Government Executive, August 12, 2008; and Brodsky, Robert. Defense Audit Agency Maps Out Response to
(continued...)
Congressional Research Service
29
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Potential Options for Congress
Congress may choose to consider the following options when examining DOD contracts for troop
support: (1) implementing of the Gansler Commission’s recommendations; (2) broadening of the
jurisdiction of the SIGIR to include DOD contracts for troop support services (like LOGCAP
contracts); (3) convening of a study of the federal employee and contractor workforce; (4)
requiring more detail to give Congress better information to perform its oversight role; and (5)
establishing a dedicated office to conduct audits and investigation of DOD contracts.
Option 1: Implementing the Gansler Commission
Recommendations
Perhaps the most significant recommendation of the Gansler Commission is that the Army
address some institutional and cultural issues that may provide an obstacle to moving forward.
The commission interviewed a number of knowledgeable Army officials and concluded with the
following observations about the challenges that the Army will face in making significant
improvements in its business operations, as described here in the report:
Those charged with getting the job done have provided valuable insight into the doctrine,
policies, tools, and resources needed for success. Clearly, the Army must address the
repeated and alarming testimony that detailed the failure of the institution (both the
Institutional Army and the Department of Defense) to anticipate, plan for, adapt, and
adjust acquisition and program management to the needs of the Operational Army as it
has been transformed, since the end of the Cold War, into an expeditionary force. The
Institutional Army has not adjusted to the challenges of providing timely, efficient, and
effective contracting support to the force in Operation Iraqi Freedom (more than half of
which is contractor personnel). Essentially, the Army sent a skeleton contracting force
into theater without the tools or resources necessary to adequately support our war
fighters. The personnel placed in that untenable position focused on getting the job done,
as best they could under the circumstances—where support is needed in a matter of
hours, or, at best, days. They used their knowledge, skill, limited resources, and
extraordinary dedication to get contracts awarded. Alarmingly, most of the institutional
deficiencies remain four-and-a-half-years after the world’s best Army rolled triumphantly
into Baghdad.124
Option 2: Expanding the SIGIR’s Jurisdiction
Another option is to give the SIGIR the authority to audit and investigate DOD logistical support
contracts in Iraq. The SIGIR has already established a presence in Iraq, and has issued more than
150 reports, including audits and investigations. His efforts have largely resulted in the arrest of
five people, and the convictions of four of them, with more than $17 million in assets seized.125
The SIGIR has made several recommendations related to his audit and investigation of contracts
(...continued)
Damaging Report. Government Executive, August 14, 2008.
124
Ibid, p. 16.
125
Senator Collins Works To Extend The Term of the Office that Oversees Billions in Iraqi Reconstruction Dollars.
Press Release of the United States Senate Committee on Governmental Affairs, November 13, 2006.
Congressional Research Service
30
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
under his jurisdiction. His observations and insights may be relevant and appropriate for the
contract administration and oversight of DOD contracts for troop support services.126
Option 3: Convening a Study of the Federal Employee and
Contractor Workforce
Congress may want to convene a study of the federal employee and contractor workforce. The
study could examine three important questions: (1) Is there an appropriate balance of federal
employee and contractor roles? (2) Is there an appropriate federal role and presence in the
oversight area? and (3) Is the federal government attracting the right types of acquisition
professionals?
Congress could require a separate report, from each military service, on the size, scope, costs, and
structure of its acquisition workforce (including military, civilian, and contractor personnel).
Option 4: Requiring More Detail for Better Oversight
Congress could require DOD to provide more details for better congressional oversight. There are
five questions that Congress could consider: (1) Should DOD move to limit sole-source or limited
competition for Iraq contracts? (2) Should DOD use more fixed-priced contracting in Iraq? (3)
Should task and delivery orders have certain dollar constraints? (4) Should task orders be subject
to public notice? and (5) Should larger contracts be divided into smaller contracts, with betterdefined, discrete tasks?
To create more transparency and openness in defense acquisitions regarding contract
administration, costs, and performance, Congress could require a separate report from each
military service. Each report could include data on the size, scope, costs, and structure of all
contracts, particularly no-bid, sole-source, and costs-reimbursement contracts.
Congress also could require that specific criteria be met before certain contract arrangements can
be approved by DOD or by Congress. In addition, Congress could require a periodic recompetition of certain types of contracts, like LOGCAP, that have the potential of spanning for
many years. Congress could also require, for example, that task orders beyond a certain size be
treated as a separate contract, and thus subject to competition among multiple contractors.
And finally, Congress could require that large defense contracts be subject to competition and that
a minimum of three contractors be selected for contracts beyond a certain size.127 Some have
suggested based on available press accounts that some contracts for services in Iraq might have
been segregated (into smaller contracts) and opened for competitive bidding. Financial oversight
might be more manageable in administering smaller contracts. Small businesses may have more
of an ability to compete for contracts.
126
As an example, the SIGIR recommends the creation of an “enhanced contingency FAR” to simplify the rules
governing contingency contracting. SIGIR, Lessons in Contracting and Procurement, July 2006, p. 97.
127
On April 18, 2008, DOD announced that the Army had awarded contracts to three companies under LOGCAP IV.
Each company will compete for task orders.
Congressional Research Service
31
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Option 5: Establishing a Dedicated Office to Conduct Audits and
Investigation of DOD Contracts
One of the recommendations of the SIGIR is to “designate a single, unified contracting entity to
coordinate all contracting in theater.”128 One way to accomplish this is to establish a Contingency
Contracting Corp (a DOD initiative currently underway is studying the issue) that will deploy to
Iraq and establish a standing presence. However, what additional resources might be necessary in
order to provide better contract management and oversight of DOD-appropriated funds?
Given that the mission of the DOD Inspector General’s office is to promote “integrity,
accountability, and improvement of Department of Defense personnel, programs and operations
to support the Department’s mission and to serve the public interest”,129 should the DOD
Inspector General have a stronger presence in Iraq? Given the many problems associated with
LOGCAP contracts, oversight agencies like the DOD IG could have a pivotal role in preventing
future contractor waste, fraud, or mismanagement.
Congress may want to consider creating a singularly dedicated office for the audit and
investigation of DOD contracts for troop support services.
128
129
Lessons in Contracting and Procurement, SIGIR, July 2006, p. 95.
From the DOD Inspector General’s website at http://www.dodig.osd.mil/mission.htm.
Congressional Research Service
32
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Appendix A. Selected Reports
During the last four years, the Congressional Research Service, General Accounting Office,
Department of Defense Inspector General, Army Audit Agency, Air Force Audit Agency, and the
Special Inspector General for Iraq Reconstruction have issued numerous reports on Iraq
contracting issues, including those listed below.
Congress
Dollars, Not Sense: Government Contracting Under the Bush Administration. Prepared by the
Special Investigations Division, Committee on Government Reform-Minority Staff, U.S. House
of Representatives, June 2006.
Congressional Research Service
CRS Report RS22923, Department of Defense Fuel Costs in Iraq, by (name redacted) and
(name redacted) .
CRS Report RL34026, Defense Acquisitions: How DOD Acquires Weapon Systems and Recent
Efforts to Reform the Process, by (name redacted) .
CRS Report RL33110, The Cost of Iraq, Afghanistan, and Other Global War on Terror
Operations Since 9/11, by (name redacted)
.
CRS Report RL32419, Private Security Contractors in Iraq: Background, Legal Status, and
Other Issues, by (name redacted), (name redacted), and ( name redacted)
.
CRS Report RS21555, Iraq Reconstruction: Frequently Asked Questions Concerning the
Application of Federal Procurement Statutes, by (name redacted).
CRS Report RL31833, Iraq: Reconstruction Assistance, by (name redacted)
.
CRS Report RL32229, Iraq: Frequently Asked Questions About Contracting, by (name redacted)
et al.
Congressional Budget Office
Contractor’s Support of U.S. Operations in Iraq, Congressional Budget Office, August 2008.
Government Accountability Office
GAO-08-857. DCAA Audits: Allegations That Certain Audits at Three Locations Did Not Meet
Professional Standards Were Substantiated. Report to Congressional Addressees, July 2008.
GAO-07-1098T. Federal Acquisitions and Contracting. Systemic Challenges Need Attention.
Statement of David M. Walker, Comptroller General of the United States, July 17, 2007.
GAO-07-359T. Defense Acquisitions: DOD Needs to Exert Management and Oversight to Better
Control Acquisition of Services. Statement of Katherine V. Schinasi, Managing Director,
Acquisition and Sourcing Management. Testimony Before the Subcommittee on Readiness and
Management Support, Committee on Armed Services, U.S. Senate, January 17, 2007.
GAO-07-145. Military Operations: High-Level DOD Action Needed to Address Long-standing
Problems with Management and Oversight of Contractors Supporting Deployed Forces,
December 16, 2006.
Congressional Research Service
33
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
GAO-06-800T. DOD Acquisitions: Contracting for Better Outcomes. September 7, 2006.
GAO-06-838R. Contract Management: DOD Vulnerabilities to Contracting Fraud, Waste, and
Abuse, GAO-06-838R, July 7, 2006.
GAO-05-274. Contract Management: Opportunities to Improve Surveillance on Department of
Defense Service Contracts, March 17, 2005.
GAO-05-207. GAO, High Risk Series: An Update, January 2005.
GAO-04-854. Military Operations: DOD’s Extensive Use of Logistics Support Contracts
Requires Strengthened Oversight, July 19, 2004.
Special Inspector General for Iraq Reconstruction
Department of Defense Inspector General, Quarterly Report to
Congress, April 30, 2008
Semi-Annual Report to Congress. October 1, 2006-March 31, 2007.
Semi-Annual Report to Congress. April 1, 2006-September 30, 2006.
Semi-Annual Report to Congress. October 1, 2005-March 31, 2006.
Semi-Annual Report to Congress. April 1, 2005-September 30, 2005.
Semi-Annual Report to Congress. October 1, 2004-March 31, 2005.
Army Audit Agency
(The website is restricted to military domains (.mil) and to the Government Accountability
Office)
Report Number A-2005-0043-ALE Logistics Civil Augmentation Program in Kuwait, U.S. Army
Field Support Command, November 24, 2004.
Gansler Commission
U.S. Army. Urgent Attention Required: Army Expeditionary Contracting, Report of the
Commission on Army Acquisition and Program Management, at http://www.army.mil/docs/
Gansler_Commission_Report_Final_071031.pdf. Published November 2007.
Congressional Research Service
34
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Appendix B. Selected Legislative Initiatives on Iraq
Contracting
Selected Legislation Introduced in the 110th Congress
The House has approved the following bills, as noted below.
H.R. 5658, National Defense Authorization Act for FY2009
Passed House, May 22, 2008; placed on Senate Legislative Calendar, June 3, 2008.
H.R. 3033, Contractors and Federal Spending Accountability Act of 2008
This provision would require the Administrator of General Services to establish and maintain a
database on defense contractors containing updated information on criminal, civil, or debarment
and suspension proceedings as well as establish the Interagency Committee on Debarment and
Suspension. Congress would require a report within 180 days of the act’s enactment.
H.R. 5712, Close the Contractor Fraud Loophole Act
This provision would require federal contractors to report violations of federal criminal law and
over-payments on contracts valued greater than $5 million.
H.R. 3928, Government Contractor Accountability Act of 2007
This provision would require “covered” government contractors to submit certification and other
financial disclosure requirements in cases where the contractor receives 80% or less of its annual
gross revenue from federal contracts. Contractors covered by this provision are those receiving
more than $25 million in annual gross revenues from federal contracts, but are not publicly traded
companies required to file reports with the Security and Exchange Commission.
H.R. 4881, Contracting and Tax Accountability Act of 2008
This provision would require tax compliance as a prerequisite for receiving federal contracts, and
would prohibit contract awards to certain delinquent federal tax debtors.
Several other bills have been introduced during the 110th Congress. Each could potentially impact
DOD contracting in Iraq, as described below.
H.R. 4102/S. 2398, Stop Outsourcing Security Act
This provision would require that only U.S. federal government personnel provide security to
personnel at U.S. diplomatic or consular mission in Iraq by six months after enactment, and
require the President to report to Congress s on “the status of planning for the transition away
from the use of private contractors for mission critical or emergency essential functions by
January 1, 2009, in all conflict zones in which Congress has authorized the use of force.”
S. 2147, Security Contractor Accountability Act of 2007
This provision would expand the coverage of the Military Extraterritorial Jurisdiction Act
(MEJA) to include all persons “while employed under a contract (or subcontract at any tier)
Congressional Research Service
35
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
awarded by any department or agency of the United States, where the work under such contract is
carried out in a region outside the United States in which the Armed Forces are conducting a
contingency operation.”
H.R. 528, Iraq Contracting Fraud Review of 2007
This provision would require the Secretary of Defense, acting through the Defense Contract Audit
Agency, to review all Iraq defense contracts for reconstruction or troop support involving any
contractors, subcontractors, or federal officers or employees indicted or convicted for contracting
improprieties.
H.R. 663, New Direction for Iraq Act of 2007
These bill contains provisions addressing war profiteering, the recovery of funds from terminated
contracts, and other issues. A select number of additional legislative initiatives, proposed during
the 110th Congress, that may impact defense contracting will follow.
H.R. 4102, Stop Outsourcing Security Act
This provision would require that only U.S. federal government personnel provide security to
personnel at U.S. diplomatic or consular mission in Iraq within six months after bill enactment,
and would require that the President report to specified congressional committees on “the status
of planning for the transition away from the use of private contractors for mission critical or
emergency essential functions by January 1, 2009, in all conflict zones in which Congress has
authorized the use of force.”
S. 2147, Security Contractor Accountability Act of 2007
This provision would broaden the Military Extraterritorial Jurisdiction Act (MEJA) to include all
persons “while employed under a contract (or subcontract at any tier) awarded by any department
or agency of the United States, where the work under such contract is carried out in a region
outside the United Sates in which the Armed Forces are conducting a contingency operation.”
H.R. 897, Iraq and Afghanistan Contractor Sunshine Act
This provision would require the Secretaries of Defense, State, Interior, and the Administrator of
the U.S. Agency for International Development to provide Congress with copies and descriptions
of all contracts and task orders valued at over $5 million.
H.R. 3695, Freeze Private Contractors in Iraq Act
This provision would prohibit an increase in the number of private security contractors employed
by DOD, State, and USAID that perform certain security functions in Iraq.
Congressional Research Service
36
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Selected Legislation Passed in the 110th Congress
P.L. 110-181, the FY2008 National Defense Authorization Act, H.R. 4986
(formerly H.R. 1585)
Several provisions contained in H.R. 4986 focus on the management and oversight of DOD
contracts.130 Key provisions are listed below:
Section 802 prohibits future contracts for the use of new Lead System
Integrators;131
Section 813 requires the Comptroller General to report to Congress on potential
modifications to the organization and structure of DOD Major Defense
Acquisition Programs;
Section 816 directs the Under Secretary of Defense for Acquisition, Technology,
and Logistics to conduct an annual review on the systematic deficiencies in
Major Defense Acquisition Programs;
Section 830 directs the Comptroller General to report to Congress on DOD’s use
of noncompetitive awards;
Section 841 establishes a commission to study federal contracting in Iraq and
Afghanistan, called the “Commission on Wartime Contracting;”
Section 842 requires the DOD Inspector General, the SIGIR for Iraq
Reconstruction, and the SIGIR for Afghanistan Reconstruction to collaborate on
the development of comprehensive plans to perform a series of audits on DOD
contracts, subcontracts, and task and delivery orders for the performance of
logistical support activities of coalition forces in Iraq and Afghanistan, as well as
audits for federal agency contracts, subcontracts, and task and delivery orders for
the performance of security and reconstruction functions in Iraq and Afghanistan;
Section 851, which would require that the Secretary of Defense (as part of the
Strategic Human Capital Plan for 2008) include a separate section of the report
focused on the military and civilian acquisition workforce;
Section 852 establishes a Defense Acquisition Workforce Development Fund;
Section 861 requires coordination between the DOD, the Department of State,
and the United States Agency for International Development through the creation
of a Memorandum of Understanding between the three agency heads on matters
relating to contracting in Iraq and Afghanistan;
130
Excerpts from H.R. 1585 discuss the rationale for legislative initiatives focused on the oversight and accountability
for contracts in Iraq and Afghanistan: “The committee remains concerned about the level of oversight for contracting in
Iraq and Afghanistan. These countries present uniquely complex challenges for contracting and contract oversight, but
U.S. efforts in these countries will continue to require significant contractor support. The committee believes that
government responsibilities for a range of issues involving contracting in Iraq and Afghanistan are unclear. The
committee believes that clarification of roles and responsibilities for contracting in Iraq and Afghanistan and increased
oversight will enhance the effectiveness of U.S. Government efforts in both countries.
131
For a brief discussion on the role of the Lead System Integrator, see CRS Report RS22631, Defense Acquisition:
Use of Lead System Integrators (LSIs)—Background, Oversight Issues, and Options for Congress, by (name redacted)
.
Congressional Research Service
37
Defense Logistical Support Contracts in Iraq and Afghanistan: Issues for Congress
Section 862 requires that the Secretary of Defense prescribe, within 120 days of
enactment, regulations on the selection, training, equipping, and conduct of
personnel performing private security functions under a covered contract or
covered subcontract in a combat area. These regulations would include processes
for registering, processing, and accounting for such personnel; and authorizing
and accounting for weapons, and investigating the death and injury of such
personnel, their discharge of weapons, and incidents of alleged misconduct. The
regulations would also provide guidance to combatant commanders on orders,
directives, and instructions to contractors and subcontractors performing private
security functions relating to force protection, security, health, safety, relations
and interaction with locals, and rules of engagement;
Section 863 requires the Comptroller General to review annually all contracts in
Iraq and Afghanistan and report to Congress on the total number of contracts and
task orders, total number of active contracts and task orders, total value of all
contracts and task orders, the degree to which DOD has awarded noncompetitive
contracts, the total number of contractor personnel (including the total number of
contractor personnel performing security functions and the total number of
contractor personnel killed or wounded); also, Section 863 would require the
Secretaries of Defense and State to provide the Comptroller General full accesses
to the database as described in Section 861;
Section 871 establishes a Defense Materiel Readiness Board;
Section 872 grants authority to the Secretary of Defense to designate critical
readiness shortfalls; and
Section 941 requires the Secretary of Defense to conduct a comprehensive
assessment of the roles and missions of the military forces, known as a
quadrennial roles and missions review.
Author Contact Information
(name redacted)
Specialist in Defense Acquisition
r[ edacted]@crs.loc.gov
, 7-....
Congressional Research Service
38
EveryCRSReport.com
The Congressional Research Service (CRS) is a federal legislative branch agency, housed inside the
Library of Congress, charged with providing the United States Congress non-partisan advice on
issues that may come before Congress.
EveryCRSReport.com republishes CRS reports that are available to all Congressional staff. The
reports are not classified, and Members of Congress routinely make individual reports available to
the public.
Prior to our republication, we redacted names, phone numbers and email addresses of analysts
who produced the reports. We also added this page to the report. We have not intentionally made
any other changes to any report published on EveryCRSReport.com.
CRS reports, as a work of the United States government, are not subject to copyright protection in
the United States. Any CRS report may be reproduced and distributed in its entirety without
permission from CRS. However, as a CRS report may include copyrighted images or material from a
third party, you may need to obtain permission of the copyright holder if you wish to copy or
otherwise use copyrighted material.
Information in a CRS report should not be relied upon for purposes other than public
understanding of information that has been provided by CRS to members of Congress in
connection with CRS' institutional role.
EveryCRSReport.com is not a government website and is not affiliated with CRS. We do not claim
copyright on any CRS report we have republished.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.