Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs: Background and Oversight Issues for Congress

Congressional research reportFeb 1, 2008

Ask Donna

What actually matters in this document.

Text

Navy-Marine Corps Amphibious and

Maritime Prepositioning Ship Programs:

Background and Oversight Issues for

Congress

Ronald O’Rourke

Specialist in Naval Affairs

February 1, 2008

Congressional Research Service

7-....

www.crs.gov

RL32513

CRS Report for Congress

Prepared for Members and Committees of Congress

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

Summary

The Navy is proposing to maintain in coming years a Navy with 31 amphibious ships and an

additional squadron of 14 Maritime Prepositioning Force (Future), or MPF(F), ships. The MPF(F)

squadron is intended to implement a new operational concept called sea basing, under which

forces would be staged at sea and used to conduct expeditionary operations ashore with little or

no reliance on nearby land bases.

The Navy’s proposed FY2008 budget requests $1,398.3 million in procurement funding for a

ninth San Antonio (LPD-17) amphibious ship to be procured in FY2008. The Navy estimates the

total procurement cost of this ship at $1,798.3 million. The ship received $296.2 million in

FY2008 advance procurement funding, and the Navy’s proposed FY2008 budget calls for the

final $103.2 million of the ship’s procurement cost to be provided in FY2009 as a “program

closeout” cost. Although the Navy’s proposed force of 31 amphibious ships includes ten LPD-17

class ships, the Navy is proposing in its FY2008 budget to end LPD-17 procurement with the

ninth ship.

The Navy’s proposed FY2008 budget also requests $1,377.4 million in procurement funding to

complete the procurement cost of LHA-6, a large-deck amphibious assault ship that was procured

in FY2007 using split funding (two-year incremental funding) in FY2007 and FY2008. The Navy

estimates the total procurement cost of LHA-6 at $2,806.2 million.

The Navy’s FY2008 unfunded programs list (UPL)—a list of programs that the Navy desires but

which are not funded in the Navy’s proposed FY2008 budget—includes, as its top item, an

additional LPD-17 at an estimated cost of about $1,700 million, and, as its second item, two

modified Lewis and Clark (TAKE-1) dry cargo ships for the MPF(F) squadron, at an estimated

combined cost of about $1,200 million. These two TAKEs are currently scheduled for

procurement in FY2009 and FY2010. (The FY2008 budget also requests $456.1 million in the

National Defense Sealift Fund (NDSF) for one “regular” TAKE-1 class ship intended for general

Navy use, not for the MPF(F)).

One potential issue for Congress is whether to fund an additional LPD-17 and/or one or more

additional TAKEs in FY2008. Additional potential oversight issues for Congress include cost

growth and construction problems in the LPD-17 program, the estimated cost of the two TAKEs

in the Navy’s FY2008 UPL, the adequacy of the 31-ship amphibious-ship force-level goal, the

stability of the amphibious and MPF(F) force-level goals, the clarity of the sea basing concept,

the potential affordability and cost-effectiveness of the sea basing concept, sea basing’s

relationship to the Navy’s new Global Fleet Stations (GFS) concept, and Navy and Marine Corps

coordination with other services in developing the sea basing concept.

This report will be updated as events warrant.

Congressional Research Service

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

Contents

Introduction ................................................................................................................................1

Background ................................................................................................................................2

Current Amphibious and Maritime Prepositioning Ships........................................................2

Amphibious Ships...........................................................................................................2

Maritime Prepositioning Ships ........................................................................................3

Amphibious and MPF(F) Force-Level Goals .........................................................................5

Sea Basing Concept ..............................................................................................................6

The Concept in General...................................................................................................6

Capability and Cost of MPF(F) Squadron........................................................................7

Related Transport Ships ..................................................................................................8

Global Fleet Station (GFS) Concept ......................................................................................9

Ship Procurement Programs ................................................................................................ 11

LPD-17 Program........................................................................................................... 12

LHD-8 .......................................................................................................................... 12

LHA-6/LHA(R) Program.............................................................................................. 12

MPF Lease Buyout ....................................................................................................... 13

Potential Issues for Congress..................................................................................................... 13

LPD-17 Cost Growth and Construction Problems................................................................ 13

Cost Growth ................................................................................................................. 13

Construction Problems .................................................................................................. 14

Funding Additional Ships in FY2008 .................................................................................. 18

Estimated Cost of Two TAKEs in FY2008 UPL .................................................................. 19

Adequacy of 30- or 31-Ship Amphibious Ship Force ........................................................... 19

Stability of Amphibious and MPF(F) Force Level Goals...................................................... 21

Crewing of Large-Deck MPF(F) Ships ................................................................................ 22

Clarity of Sea Basing Concept............................................................................................. 23

Affordability and Cost-Effectiveness of Sea Basing............................................................. 24

Navy Perspective .......................................................................................................... 25

CBO Perspective........................................................................................................... 26

CSBA Perspective......................................................................................................... 27

Potential Oversight Questions ....................................................................................... 27

Relationship to Global Fleet Station (GFS) Concept ............................................................ 28

Coordination with Other Services on Sea Basing................................................................. 28

Legislative Activity for FY2008 ................................................................................................ 31

FY2008 Budget Request ..................................................................................................... 31

LPD-17 Program........................................................................................................... 31

LHA-6/LHA(R) Program.............................................................................................. 31

TAKE Program ............................................................................................................. 32

Navy FY2008 Unfunded Priorities List (UPL)............................................................... 32

FY2008 Defense Authorization Bill (H.R. 1585/S. 1547) .................................................... 32

House ........................................................................................................................... 32

Senate........................................................................................................................... 33

Conference.................................................................................................................... 34

FY2008 Defense Appropriations Bill (H.R. 3222/P.L. 110-116)........................................... 35

House ........................................................................................................................... 35

Senate........................................................................................................................... 36

Congressional Research Service

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

Conference.................................................................................................................... 36

Tables

Table 1. Funding For Acquisition of MPF(F) Ships......................................................................8

Table 2. FY2008-FY2013 Amphibious and MPF(F) Ship Procurement Plan .............................. 11

Contacts

Author Contact Information ...................................................................................................... 37

Congressional Research Service

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

Introduction

The Navy is proposing to maintain in coming years a Navy with 31 amphibious ships and an

additional squadron of 14 Maritime Prepositioning Force (Future), or MPF(F), ships. The MPF(F)

squadron is intended to implement a new operational concept called sea basing, under which

forces would be staged at sea and used to conduct expeditionary operations ashore with little or

no reliance on nearby land bases.

The Navy’s proposed FY2008 budget requests $1,398.3 million in procurement funding for a

ninth San Antonio (LPD-17) amphibious ship to be procured in FY2008. The Navy estimates the

total procurement cost of this ship at $1,798.3 million. The ship received $296.2 million in

FY2008 advance procurement funding, and the Navy’s proposed FY2008 budget calls for the

final $103.2 million of the ship’s procurement cost to be provided in FY2009 as a “program

closeout” cost. Although the Navy’s proposed force of 31 amphibious ships includes ten LPD-17

class ships, the Navy is proposing in its FY2008 budget to end LPD-17 procurement with the

ninth ship.

The Navy’s proposed FY2008 budget also requests $1,377.4 million in procurement funding to

complete the procurement cost of LHA-6, a large-deck amphibious assault ship that was procured

in FY2007 using split funding (two-year incremental funding) in FY2007 and FY2008. The Navy

estimates the total procurement cost of LHA-6 at $2,806.2 million.

The Navy’s FY2008 unfunded programs list (UPL)—a list of programs that the Navy desires but

which are not funded in the Navy’s proposed FY2008 budget—includes, as its top item, an

additional LPD-17 at an estimated cost of about $1,700 million, and, as its second item, two

modified Lewis and Clark (TAKE-1) dry cargo ships for the MPF(F) squadron, at an estimated

combined cost of about $1,200 million. These two TAKEs are currently scheduled for

procurement in FY2009 and FY2010. (The FY2008 budget also requests $456.1 million in the

National Defense Sealift Fund (NDSF) for one “regular” TAKE-1 class ship intended for general

Navy use, not for the MPF(F)).

The issue for Congress is whether to approve, modify, or reject the Navy’s plans for procuring

amphibious and MPF(F) ships. Decisions that Congress makes on this issue could affect Navy

and Marine Corps capabilities, Navy and Marine Corps funding requirements, and the

shipbuilding industrial base.

Congressional Research Service

1

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

Background

Current Amphibious and Maritime Prepositioning Ships

Amphibious Ships

Amphibious ships are one of four principal categories of combat ships that traditionally have

helped define the size and structure of the U.S. Navy. The other three are aircraft carriers, surface

combatants (e.g., cruisers, destroyers, frigates, and Littoral Combat Ships), and submarines.1

The primary function of amphibious ships is to transport Marines and their equipment to distant

operating areas, and enable Marines to conduct expeditionary operations ashore in those areas.

Amphibious ships have berthing spaces for Marines, flight decks and hangar decks for their

helicopters and vertical/short take-off and landing (VSTOL) fixed-wing aircraft, well decks for

storing and launching their landing craft,2 and storage space for their wheeled vehicles, their other

combat equipment, and their supplies. Although amphibious ships are designed to support Marine

landings against opposing military forces, they can also be used for Marine landings in so-called

permissive or benign situations where there are no opposing forces.

U.S. amphibious ships are Navy ships operated by Navy crews, with the Marines as passengers.

They are built to survivability standards similar to those of other U.S. Navy combat ships,3 and

are included in the total number of battle force ships in the Navy, which is the commonly cited

figure for the total number of ships in the fleet.4 Amphibious ships are procured in the Navy’s

shipbuilding budget, known as the Shipbuilding and Conversion, Navy (SCN) appropriation

account. Designations of amphibious ship classes start with the letter L, as in amphibious landing.

Today’s amphibious ships can be divided into two main groups—the so-called “big-deck”

amphibious assault ships, designated LHA and LHD, which look like medium-sized aircraft

carriers, and the smaller (but still sizeable) LSD- and LPD-type amphibious ships.5 The LHAs

and LHDs have large flight decks and hangar decks for embarking and operating numerous

helicopters and VSTOL fixed-wing aircraft, while the LSDs and LPDs have much smaller flight

decks and hangar decks for embarking and operating smaller numbers of helicopters. The LHAs

1

The Navy also includes mine warfare ships and a variety of auxiliary and support ships.

A well deck is a large, garage-like space in the stern of the ship. It can be flooded with water so that landing craft can

leave or return to the ship. Access to the well deck is protected by a large stern gate that is somewhat like a garage

door.

3

To enhance their survivability in battle—their ability to absorb damage from enemy weapons—U.S. Navy ships are

built with features such as extensive interior compartmentalization and increased armor protection of certain critical

interior spaces.

4

Battle force ships are ships that are readily deployable overseas and which contribute to the overseas combat

capability of the Navy. They include both active duty and Naval Reserve Force combat ships as well Navy- and

Military Sealift Command-operated auxiliaries—such as oilers, ammunition ships, dry cargo ships, and multiproduct

resupply ships—that transport supplies from shore to Navy combat ships operating at sea.

5

LHA can be translated as landing ship, helicopter-capable, assault. LHD can be translated as landing ship, helicoptercapable, well deck. LSD can be translated as landing ship, well deck. LPD can be translated as landing ship, helicopter

platform, well deck. Whether noted in the designation or not, all these ships have well decks.

2

Congressional Research Service

2

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

and LHDs, as bigger ships, in general can embark more Marines and equipment than the LSDs

and LPDs. As of the end of FY2006, the Navy included 33 amphibious ships:

•

7 Wasp (LHD-1) class ships, commissioned between 1989 and 2001, each

displacing about 40,500 tons;6

•

4 Tarawa (LHA-1) class ships, commissioned between 1976 and 1980, each

displacing about 40,000 tons;

•

12 Whidbey Island/Harpers Ferry (LSD-41/49) class ships, commissioned

between 1985 and 1998, each displacing about 16,000 tons;

•

1 San Antonio (LPD-17) class ship, commissioned in 2006, displacing about

26,000 tons; and

•

9 Austin (LPD-4) class ships, commissioned between 1965 and 1971, each

displacing about 17,000 tons.7

The Navy organizes its amphibious ships into expeditionary strike groups (ESGs). Each ESG

notionally includes one LHA or LHD, one LSD, and one LPD. The amphibious ships in an ESG

together can embark a Marine expeditionary unit (MEU) consisting of about 2,200 Marines, their

aircraft, their landing craft, their combat equipment, and about 15 days worth of supplies. Each

ESG also notionally includes three surface combatants (some or all armed with Tomahawk cruise

missiles), one submarine, and perhaps one or more P-3 long-range, land-based maritime patrol

aircraft. ESGs are designed to be independently deployable, strike-capable naval formations, but

they can also operate in conjunction with carrier strike groups (CSGs) to form larger naval task

forces. On average, two (or perhaps three) ESGs might be forward-deployed at any given time.

Maritime Prepositioning Ships

Today’s maritime prepositioning ships are large military cargo ships that are loaded with combat

equipment and supplies and forward-located to sea areas that are close to potential U.S. military

operating zones. They are essentially forward-located, floating warehouses. Most have a rollon/roll-off (RO/RO) capability, which means that they are equipped with ramps that permit

wheeled or tracked vehicles to quickly roll on or off the ship when the ship is at pier.

A total of 36 U.S. prepositioning ships, controlled by the Military Sealift Command (MSC), store

equipment and supplies for various parts of DOD. The 16 ships used primarily for storing Marine

Corps equipment and supplies are called Maritime Prepositioning Force (MPF) ships. The 10

ships used primarily for storing equipment and supplies for the Army are called the Combat

Prepositioning Force. The remaining 10 ships used primarily for storing equipment and supplies

for the Air Force, Navy, and Defense Logistics Agency are called Logistics Prepositioning Ships.

This report focuses on the 16 MPF ships.

6

For comparison, a Nimitz-class nuclear-powered aircraft carrier displaces about 100,000 tons, and a cruiser or

destroyer displaces about 9,000 tons.

7

The Navy also operates two Blue Ridge (LCC-19) class command ships. As their designation suggests, these ships

were originally built as amphibious command ships. In recent years, they have evolved into general fleet command

ships. Some listings of U.S. Navy ships include the two LCCs as amphibious ships, while others list them in a separate

category of command ships, along with one other fleet command ship—the Coronado (AGF-11), which is a converted

LPD.

Congressional Research Service

3

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

The 16-ship MPF fleet is organized into three squadrons of five or six ships each. Each squadron

stores enough combat equipment and supplies to equip and support a MEB for a period of 30

days. One squadron is normally forward-located in the Atlantic or Mediterranean, one is normally

forward-located in the Indian Ocean at Diego Garcia, and one is normally forward-located in the

Western Pacific at Guam and Saipan.8

Today’s MPF ships are designed to support Marine landings at friendly ports or ports that

Marines or other U.S. or friendly forces have previously seized by force. Under the basic MPF

concept of operations, the MPF ships would steam into such a port, while Marines would be

flown into a nearby friendly or seized airbase. The Marines would then travel to the port, help

unload the MPF ships, unpack and “marry up” with their equipment and supplies, and begin

conducting their operations ashore. MPF operations can be used to reinforce an initial Marine

presence ashore that was created by a Marine landing against opposing forces, or to establish an

initial Marine presence ashore in a permissive or benign landing environment.

The MPF concept permits a MEB-sized Marine force to be established in a distant operating area

more quickly than would be possible if the MEB’s equipment and supplies had to be transported

all the way from the United States. Unlike prepositioning of equipment and supplies on the soil of

foreign countries, maritime prepositioning in international waters does not require permanent host

nation access. The MPF concept also provides a degree of intertheater operational flexibility,

since an MPF squadron can be moved from one theater (e.g., the Mediterranean) to an adjoining

theater (e.g., the Indian Ocean) relatively quickly if needed to respond to a contingency. DOD

used the Mediterranean and Western Pacific MPF squadrons to supplement the Indian Ocean

MPF squadron in the 1991 Gulf War (Operation Desert Storm) and the more recent Iraq War

(Operation Iraqi Freedom).

Today’s MPF ships are DOD sealift ships operated with civilian crews. They are built to

survivability standards similar to those of commercial cargo ships, which are lower than those of

U.S. Navy combat ships. They are not included in the total number of battle force ships in the

Navy. 9 Today’s MPF ships are designated TAKs. The “T” means the ships are operated by the

MSC; the “A” means auxiliary; and the “K” means cargo.

The MPF fleet was established in the mid-1980s. It includes 13 ships (TAK-3000 through TAK3012) that entered service with the MPF in 1984-1986, and three ships (TAK-3015 through TAK3017) that were added to the MPF fleet in 2000-2003 under the MPF Enhancement, or MPF(E),

program, so as to increase the storage capacity of the MPF fleet in accordance with lessons

learned during the 1991 Gulf War. One MPF(E) ship was added to each squadron.

The 13 earlier MPF ships, which each displace between about 44,000 and 49,000 tons, are owned

and operated by private companies under 25-year charters (i.e., leases) to MSC. The three more

recently added MPF(E) ships, which each displace between about 50,000 and 55,000 tons, are

owned by the U.S. government and are operated by private companies under contract to MSC.

8

The maritime prepositioning ships serving the other military services are located principally at Diego Garcia.

9

In contrast to Navy auxiliaries that are counted as battle force ships because they transport supplies from land to Navy

ships operating at sea, MPF ships, like most other DOD sealift ships, transport supplies from one land mass to another,

primarily for the benefit of a service (in this case, the Marine Corps) other than the Navy.

Congressional Research Service

4

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

Since FY1993, new-construction DOD sealift ships similar to the MPF ships have been procured

not in the SCN account, but rather in the National Defense Sealift Fund (NDSF), a DOD

revolving fund that is outside both the Department of the Navy budget and the procurement title

of the annual DOD appropriation act. NDSF funding is used for acquiring, operating, and

maintaining DOD sealift ships and certain Navy auxiliary ships.

As of the end of FY2005, the MPF fleet included the following ships:

•

5 Cpl. Louis J. Hauge Jr. (TAK-3000) class ships, which were originally built

in Denmark in 1979-1980 as civilian cargo ships for Maersk Line Ltd. Their

conversions into MPF ships began in 1983-1984. The ships are owned and

operated by Maersk.

•

3 Sgt. Matej Kocak (TAK-3005) class ships, which were originally built in the

United States in 1981-1983 as civilian cargo ships for the Waterman Steamship

Corporation. Their conversions into MPF ships began in 1982-1983. The ships

are owned and operated by Waterman.

•

5 2nd Lt. John P. Bobo (TAK-3008) class ships, which were built in the United

States in 1985-1986 as new-construction ships for the MPF. They are owned and

operated by American Overseas Marine.

•

1 1st Lt. Harry L. Martin (TAK-3015) class ship, which was originally built in

Germany in 1980 as a civilian cargo ship. Its conversion into an MPF ship began

in 1999.

•

1 LCPL Roy M. Wheat (TAK-3016) class ship, which was originally built in

Ukraine as a Soviet auxiliary ship. It was acquired for conversion in 1997.10

•

1 Gunnery Sgt. Fred W. Stockham (TAK-3017) class ship, which was

originally built in Denmark in 1980 as a commercial cargo ship. In the early

1990s, it was acquired for conversion into a kind of DOD sealift ship called a

large, medium-speed, roll-on/roll-off (LMSR) ship. It was used by MSC as an

LMSR under the name Soderman (TAKR-299) until 2000, when it was converted

into an MPF(E) ship, and renamed the Stockham. 11

Amphibious and MPF(F) Force-Level Goals

The Navy is proposing to maintain in coming years a fleet of 313 ships, including 31 amphibious

ships and a 14-ship MPF(F) squadron.12 The 31-ship amphibious force is to include the following:

10

The conversion of this ship took considerably longer than expected and was the subject of a lawsuit. For discussion,

see Christopher J. Castelli, “MSC Names and Deploys MPF(E) Vessel, While Bender Pursues Lawsuit,” Inside the

Navy, October 13, 2003; Christopher J. Castelli, “Finally, MSC Plans to Name Converted Cargo Ship This October,”

Inside the Navy, August 25, 2003; Christopher J. Castelli, “MSC: Beleaguered Cargo Vessel to Make First Deployment

This Year,” Inside the Navy, June 2, 2003; Christopher J. Castelli, “MSC Postpones Wheat Christening, Citing Current

Military Ops,” Inside the Navy, February 17, 2003; Christopher J. Castelli, “Cargo Ship Mired in Conversion Process to

Reach Fleet In 2003,” Inside the Navy, January 6, 2003.

11

Another LMSR was built as a new-construction LMSR and named the Soderman (TAKR-317).

12

For additional discussion of the proposed 313-ship fleet, see CRS Report CRS Report RL32665, Navy Force

Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O’Rourke.

Congressional Research Service

5

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

•

9 LHD- or LHA-type large-deck amphibious assault ships;

•

10 LPD-17 class amphibious ships; and

•

12 LSD-41/49 class amphibious ships.

The 14-ship MPF(F) squadron is intended to help implement a new operational concept called sea

basing, which is discussed in the next section. The squadron is to include 2 new-construction

amphibious assault ships, 1 existing LHD-type amphibious assault ship, 9 new-construction

sealift-type ships, and 2 existing, older-generation MPF ships. The 11 new-construction ships are

as follows:

•

2 modified LHA Replacement, or LHA(R), ships equipped with Marine

Expeditionary Brigade (MEB) command and control (C2) facilities;

•

3 modified Large, Medium-Speed, Roll-on/Roll-off (LMSR) sealift ships;

•

3 modified Lewis and Clark (TAKE-1) class cargo and ammunition resupply

ships; and

•

3 Mobile Landing Platform (MLP) ships.

Sea Basing Concept

The Concept in General

The Navy and Marine Corps are proposing to implement a new concept of operations for staging

forces at sea and conducting expeditionary operations ashore with little or no reliance on nearby

land bases. The concept is called enhanced networked sea basing, or sea basing for short.

Under the traditional concept of operations for conducting expeditionary operations ashore, the

Navy and Marine Corps would establish a base ashore, and then use that base to conduct

operations against the desired ashore objective. Under sea basing, the Navy and Marine Corps

would launch, direct, and support expeditionary operations directly from a base at sea, with little

or no reliance on a nearby land base. 13

A key rationale for the sea basing concept is that in the future, fixed land bases ashore will

become vulnerable to enemy attack from weapons such as cruise missiles or short-range ballistic

missiles. Launching the operation directly from a base at sea, advocates of sea basing argue, will

enhance the survivability of the attacking Navy-Marine Corps force by putting the base out of the

range of shorter-range enemy weapons and targeting sensors, and by permitting the sea to be used

as a medium of maneuver for evading detection and targeting by longer-range enemy weapons

and sensors.

A second rationale for sea basing is that by eliminating the nearby base ashore—the logistical

“middleman”—sea basing will permit the Marine Corps to initiate and maintain a higher pace of

13

For an in-depth discussion of the sea basing concept, see Defense Science Board Task Force on Sea Basing, op. cit.

See also Otto Kreisher, “Sea Basing,” Air Force Magazine, July 2004, p. 64; Scott C. Truver, “Sea Basing: More Than

the Sum of Its Parts?” Jane’s Navy International, March 2004, pp. 16-18, 20-21; Art Corbett and Vince Goulding, “Sea

Basing: What’s New?” U.S. Naval Institute Proceedings, November 2002, pp. 34-39.

Congressional Research Service

6

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

operations against the desired objective, thus enhancing the effectiveness of the operation. A third

rationale for sea basing is that it could permit the Marine force, once the operation is completed,

to reconstitute and redeploy—that is, get back aboard ship and be ready for conducting another

operation somewhere else—more quickly than under the traditional concept of operations.

The sea base being referred to is not a single ship, but rather a collection of ships, including the

MPF(F) squadron, other ships (such as an aircraft carrier strike group), and intertheater and sea

base-to-shore connector ships. Under sea basing, certain functions previously carried out from the

nearby base ashore, including command and control and logistics, would be transferred back to

the ships at sea that collectively make up the sea base.

The Defense Science Board (DSB) in August 2003 issued a report on sea basing which concluded

that “sea basing represents a critical future joint military capability for the United States.”14

In August 2005, the Joint Chiefs of Staff unanimously approved a Joint Integrating Concept (JIC)

document for sea basing.15 Approval of the JIC gave seabasing DOD recognition as a key future

U.S. military capability, and created a more formal requirement for seabasing to be implemented

in a way that satisfies joint requirements rather than those of the Navy and Marine Corps alone.

The seabasing concept must still complete DOD’s Joint Capabilities Integration and Development

System (JCIDS) process and obtain acquisition milestone approvals.16

Capability and Cost of MPF(F) Squadron

The MPF(F) squadron will replace one of the three existing MPF squadrons. The MPF(F)

squadron was described in a June 2005 Navy report to Congress on the MPF(F) program17 that

was required by the conference report (H.Rept. 108-622 of July 20, 2005) on the FY2005 defense

appropriations act (H.R. 4613/P.L. 108-287 of August 5, 2004),18 and again in a February 2007

Navy report to Congress on the MPF(F) program19 that was directed by the report of the Senate

Armed Services Committee (H.Rept. 109-254 of May 9, 2006) on the FY2007 defense

authorization bill (S. 2766).20

14

Defense Science Board Task Force on Sea Basing, op.cit., p. xi. Italics as in the original. Similar statements are made

in two cover memos included at the front of the report, and on p. 87. For press reports about this study, see John T.

Bennett, “Marine Corps Commandant, DSB Describe Visions of Seabasing Concept,” Inside the Pentagon, October 30,

2004; Jason Ma, “DSB Study, Conference Examine Seabasing Needs and Challenges,” Inside the Navy, October 27,

2003; Jason Sherman, “Pentagon Group Details Sea Base Concept,” Defense News, October 27, 2003.

15

Christopher J. Castelli, “Joint Chiefs Endorse Pentagon’s Proposed Seabasing Concept,” Inside the Navy, September

19, 2005. See also David W. Munns, “Forward Progress,” Seapower, September 2005: 14-16, 18.

16

Jason Ma, “Navy Weighted U.S. Shipbuilding Capabilities When Crafting MPF(F) Plan,” Inside the Navy,

September 19, 2005.

17

U.S., Department of the Navy, Report to Congress, Maritime Prepositioning Force, Future, MPF(F), Washington,

2005, 8 pp. (Prepared by Program Executive Officer, Ships, Washington DC 20376, June 2005.) A 20-page appendix to

the report provides supporting budget details. Letters of transmission to Congress accompanying the report are dated

June 6, 2005.

18

The requirement for the report on the MPF(F) program is on page 360 of H.Rept. 108-622.

19

U.S., Department of the Navy, Report to Congress, Maritime Prepositioning Force (Future) [or] MPF(F)

[Program], Washington, 2007, 22 pp. (Prepared by Director, Expeditionary Warfare Division (OPNAV N85), 1000

Navy Pentagon, Washington, DC 20350, February 2007.)

20

The requirement for the report on the MPF(F) program is on pages 114-115 of H.Rept. 109-254.

Congressional Research Service

7

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

The February 2007 Navy report states that the key performance parameters for the MPF(F)

squadron include, among other things, an ability to deliver ashore, in a period of 8 to 10 hours,

one Marine Brigade Landing Team (BLT) by surface transportation from a range of up to 25

nautical miles, and a second BLT by air transportation (i.e., “vertically”) from a range of up to

110 nautical miles. The report states that

Affordability and industrial base considerations were key elements of the MPF(F) squadron

composition decision. The squadron includes existing assets (an LHD and two T-AKs)

which reduces overall squadron procurement costs. It also leverages hot production lines for

two ship classes (T-AKE and LHA(R)) which significantly reduces non-recurring costs,

reduces technical and cost risk, and takes advantage of learning curves during the production

process. The MPF(F) squadron includes an additional vessel type (MPF(F) LMSR) which is

based on an existing design, further reducing non-recurring costs. The MLP is the only new

design platform included in the MPF(F) squadron. The MLP was also selected with

affordability in mind, as the vessel will leverage existing commercial technology in

performing the mission.21

The February 2007 report estimates the acquisition cost of the MPF(F) squadron at $11.1 billion

to $13.8 billion in constant FY2008 dollars. The report states that this estimate includes test and

evaluation (T&E), outfitting, and post-delivery costs, but excludes the cost of additional shore

facilities. The report estimates the MPF(F) squadron’s life-cycle costs, including disposal costs, at

$25.8 billion to $33.5 billion in constant FY2008 dollars.22

Table 1 below shows annual funding for the acquisition of MPF(F) squadron ships in the

proposed FY2008 budget.

Table 1. Funding For Acquisition of MPF(F) Ships

(millions of then-year dollars)

FY06

and

prior

FY07

FY08

FY09

FY10

FY11

FY12

FY13

Beyond

FY13

Total

95

86

68

1,682

2,612

3,748

1,015

2,074

1,381

12,761

Source: U.S., Department of the Navy, Report to Congress, Maritime Prepositioning Force (Future) [or] MPF(F)

[Program], Washington, 2007, 22 pp. (Prepared by Director, Expeditionary Warfare Division (OPNAV N85),

1000 Navy Pentagon, Washington, DC 20350, February 2007.)

Related Transport Ships

In addition to the MPF(F) squadron ships, the Navy and Army plan to procure several Joint High

Speed Vessels (JHSVs) for high-speed intra-theater transport of Marine Corps and Army forces

and equipment. The JHSV is to be a 35- to 45-knot, shallow-draft, intratheater transport ship

similar to the leased commercial high-speed ferries that DOD has used experimentally in recent

years. The Navy also plans to procure sea base-to-shore connector (SSC) ships for transporting

personnel and equipment from the sea base to the shore area of operations. The SSCs would

replace the Navy’s current LCAC air-cushioned landing craft.

21

22

Report to Congress, Maritime Prepositioning Force (Future) [or] MPF(F) [Program], op cit, p. 14.

Report to Congress, Maritime Prepositioning Force (Future) [or] MPF(F) [Program], op cit, p. 15.

Congressional Research Service

8

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

Global Fleet Station (GFS) Concept

In connection with the sea basing concept and the concept of adaptive force packaging (which

refers to the ability of U.S. naval forces to be split apart and recombined into force packages of

various sizes and mission orientations, so as to meet the needs of various contingencies), the

Navy is proposing to establish what it calls global fleet stations, or GFSs. A 2006 Navy

operations concept document states that one method for furthering the Navy’s contribution to

national security will involve:

Providing operational maneuver and assured access to the joint force while significantly

reducing our footprint ashore and minimizing the permissions required to operate from host

nations. With a sustainable logistics tail safely at sea, sea basing leverages the ability to

operate from international waters. We are exploring innovative operational concepts that

combine sea basing with adaptive force packaging that will further support national security

and the Combatant Commanders’ objectives worldwide. One such concept is the Global

Fleet Station (GFS). GFS is a persistent sea base of operations from which to coordinate and

employ adaptive force packages within a regional area of interest. Focusing primarily on

Phase 0 (shaping) operations, Theater Security Cooperation, Global Maritime Awareness,

and tasks associated specifically with the War on Terror, GFS offers a means to increase

regional maritime security through the cooperative efforts of joint, inter-agency, and

multinational partners, as well as Non-Governmental Organizations. Like all sea bases, the

composition of a GFS depends on Combatant Commander requirements, the operating

environment, and the mission. From its sea base, each GFS would serve as a self-contained

headquarters for regional operations with the capacity to repair and service all ships, small

craft, and aircraft assigned. Additionally, the GFS might provide classroom space, limited

medical facilities, an information fusion center, and some combat service support capability.

The GFS concept provides a leveraged, high-yield sea based option that achieves a persistent

presence in support of national objectives. Additionally, it complements more traditional

CSG/ESG training and deployment cycles. 23

The document describes a hypothetical scenario in which a future GFS is organized around an

LPD-type ship that operates in the region for up to two years. In the scenario, the LPD-type ship

acts as a host or support platform for sailors, Marines, Army personnel, Air Force personnel, and

a Coast Guard small boat unit.24

A March 20, 2006, Navy white paper on the GFS concept posted online by InsideDefense.com

states that

The purpose of a GFS is to establish a base of operations from which to coordinate and

launch a variety of missions within a regional area of interest, focusing primarily on Phase

0/Shaping and Stability operations, Theater Security Cooperation, Maritime Domain

Awareness, and tasks associated specifically with the War on Terror.... These activities range

from traditional counter piracy, MIO, and security patrols, to mobile training teams (MTTs),

construction assistance, medical outreach, and information sharing....

By taking advantage of existing host nation basing arrangements, it is anticipated that five

Fleet Stations could be developed within the next five to seven years, based upon the

availability of trained personnel, ships, helicopters and equipment. Possible locations for

these initial Global Fleet Stations include Guam or Singapore (GFS - SE Asia); Bahrain or

23

24

U.S. Department of the Navy, Naval Operations Concept 2006, Washington, 2006, pp. 30-31

U.S. Department of the Navy, Naval Operations Concept 2006, op. cit., p. 32.

Congressional Research Service

9

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

UAE (GFS - East Africa, Arabian Gulf); Diego Garcia (GFS—South Asia); Rota (GFS West Africa); and, Key West (GFS—South and Central America). These locations were

selected due to the availability of facilities that could support a US military presence with

dependents. As a pilot, Naval Station Key West could serve as the site for proof of concept....

Each GFS is a self-sustaining home base from which to conduct regional Phase 0 operations

ranging from Theater Security Cooperation (TSC) activities to Maritime Interdiction and

counter-piracy. It is a base from which tailored and adaptive force packages can be launched

in response to humanitarian crises, natural disasters, and counter-terrorism tippers. It is a

center for intelligence and information fusion in support of enhanced Maritime Domain

Awareness, and when networked with other Fleet Stations, each GFS fusion center will serve

as an intelligence feeder for Global Maritime Intelligence Integration. Most importantly,

these information fusion centers will offer increased regional maritime domain awareness to

host nation partners and will provide timely queuing to interdict illegal transnational

activities.

Each GFS is a base from which to sustain and deploy riverine units throughout the region,

whether in concert with Mobile Training Teams and other Phase 0 activities or to conduct

missions in direct support of GWOT (surveillance, MIO [maritime intercept operations],

combat insertion, etc). Each GFS will serve as the logistics and C2 HQ for regional

expeditionary operations, to include the basing of Blue and Gold crews to sustain high

OPTEMPO [operational tempo] throughout the region with a limited number of ships, small

craft, helicopters and UAVs [unmanned aerial vehicles]. Each GFS is home base for regional

NECC [Naval Expeditionary Combat Command] detachments consisting of Seabees

[construction battalions, or CBs], salvage divers, EOD [explosive ordnance disposal], and

security force personnel as well as small expeditionary medical and logistics teams. It is also

the hub for FAOs [Foreign Area Officers] dedicated to supporting activities within the

region, tailored to the needs of the host nations involved. Further, each GFS will leverage

existing SOFA’s [Status of Forces Agreements with other countries] and MOU’s

[Memoranda of Understanding] to manage bilateral and multi-lateral cooperation as well as

IMET [International Military Education and Training] funds and other incentive programs,

and will be the focal point for coordination with local representatives from the Inter-Agency,

International Organizations, and NGOs [non-governmental organizations]....

At a minimum, each GFS must include at least one expeditionary warfare ship

LPD/LSD/HSV [high-speed vessel] capable of serving as a mother/command ship to

transport a variety of riverine craft and helicopters/UAVs, mobile training teams, Seabees

and materiel, medical teams, and a limited security force. This ship should also provide

sufficient C4I, limited medical facilities, and configurable classroom space to sustain Phase 0

operations throughout the region. Initially one or two FFGs [frigates] (to be replaced by

LCSs [littoral combat ships]) would provide limited NSFS [naval surface fire support],

MIO/VBSS [visit, board, search, and seizure], AAW [anti-air warfare] and ASW [antisubmarine warfare] support (as well as the ability to train with larger regional and coastal

Navy’s). Each GFS must serve as a self-contained Group HQ for regional operations, and

should have the capacity to repair and service all ships, small craft, and aircraft assigned.

Additionally, the GFS should have a limited combat service support capability. The GFS

(and mother ship) must maintain robust and secure Joint C4I capabilities to support a

JFMCC [Joint Force Maritime Component Commander] or JFLCC [Joint Force Land

Component Commander] command structure. There should be a medical treatment facility at

the GFS (and/or on the command ship assigned) to provide medical support/humanitarian

assistance as well as sufficient combat construction equipment and material to support Phase

0 operations in remote locations. The intelligence fusion cell should be equipped with

sufficiently robust and secure communications to handle the fusion of open source

information as well as tactical and strategic intelligence (to include IMINT, SIGINT,

HUMINT [imagery, signal, and human intelligence] and other sensitive intelligence

Congressional Research Service

10

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

sources). Each GFS would include at least two small boat units and eventually, perhaps, an

entire riverine squadron. Additionally, at least one helicopter detachment (and eventually a

UAV detachment) would be assigned to each GFS. The GFS would ideally have regular

access to, and contact with, inter-agency, international community, and NGO representatives

throughout the region. There would be sufficient language expertise on board the Station,

through FAO and other personnel, to provide direct interaction with indigenous populations

throughout the region....

The most feasible place to test the Global Fleet Station concept would be Key West (Naval

Station Annex and Truman Annex) serving Central and South America.25

Ship Procurement Programs

Table 2 shows the Navy’s plan for procuring amphibious and MPF(F) ships in FY2008-FY2013.

Table 2. FY2008-FY2013 Amphibious and MPF(F) Ship Procurement Plan

(Ships fully funded in FY2006 shown for reference)

FY08

FY09

FY10

FY11

FY12

FY13

For the 31-ship amphibious force

LPD-17

1

LHA(R)

(0)a

For the 14-ship MPF(F) squadron

LHA(R)-MPF(F)

TAKE-MPF(F)

1

(1)b

1

LMSR-MPF(F)

MLP-MPF(F)

1

1

1

1

1

1

1

1

1

1

Sources: Department of the Navy, Highlights of the Department of the Navy FY 2007 Budget, Chart 15 (p. 5-3),

and Draft Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2007.

Key:

LPD-17—San Antonio (LPD-17) class amphibious ship

LHA(R)—LHA(R) class amphibious assault ship. Also known as the LHA-6 class.

LHA(R)-MPF(F)—Modified LHA(R) intended for MPF(F) squadron

TAKE-MPF(F)—Modified Lewis and Clark (TAKE-1) class resupply ship intended for MPF(F) squadron

LMSR-MPF(F)—Modified large, medium-speed, roll-on/roll-off (LMSR) sealift ship intended for MPF(F) squadron

MLP-MPF(F)—Mobile Landing Platform ship intended for MPF(F) squadron

25

a.

FY2008 budget request includes funding for an LHA(R) procured in FY2007 using split funding in FY2007

and FY2008.

b.

The Navy’s FY2008-FY2013 shipbuilding plan includes a “regular” TAKE in FY2008 intended for general

Navy use rather than the MPF(F) squadron.

“Navy White Paper on Global Fleet Stations,” posted online at InsideDefense.com [subscription required].

Congressional Research Service

11

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

LPD-17 Program

As a replacement for older LPDs and other older amphibious ships, the Navy is currently

procuring new San Antonio (LPD-17) class amphibious ships. The ships are built primarily at

Northrop Grumman Ship Systems (NGSS), which includes, among other things, the old Avondale

shipyard near New Orleans, LA, and the old Ingalls shipyard at Pascagoula, MS.26

A total procurement of 12 LPD-17s was originally planned. The Navy’s proposed 31-ship

amphibious fleet includes a total of 10 LPD-17s. In spite of this 10-ship goal, the Navy plans to

end LPD-17 procurement with the ninth ship, which is to be procured in FY2008.

The Navy’s proposed FY2008 budget requests $1,398.3 million in procurement funding for ninth

ship. This ship received $296.2 million in FY2008 advance procurement funding, and the Navy’s

proposed FY2008 budget calls for the final $103.2 million of the ship’s procurement cost to be

provided in FY2009 as a “program closeout” cost.

The Navy’s FY2008 unfunded programs list (UPL)—a list of programs that the Navy desires but

which are not funded in the Navy’s proposed FY2008 budget—includes, as its top item, an

additional (i.e., tenth) LPD-17 at an estimated cost of about $1,700 million.

LHD-8

To replace one of its five aging LHAs, the Navy in FY2002 procured LHD-8—an eighth Waspclass ship27—at a total budgeted cost of about $2.06 billion. At the direction of the FY2000 and

FY2001 defense appropriation bills, the ship was incrementally funded in the SCN account, with

the final funding increment being provided in FY2006. The ship is being built by the Ingalls

shipyard at Pascagoula, MS, that now forms part of NGSS. The Ingalls shipyard is the builder of

all previous LHAs and LHDs, and is scheduled to be delivered to the Navy in May 2008.

LHA-6/LHA(R) Program

As a successor to the Wasp-class design, the Navy is procuring a new class of amphibious assault

ships called the LHA Replacement (LHA[R]) or LHA-6 class. The Navy estimates the

procurement cost of the first such ship, LHA-6, at $2,806.2 million. The ship was procured in

FY2007 using split funding (two-year incremental funding) in FY2007 and FY2008. The ship

received $149.3 million in FY2005 advance procurement funding, $148.4 million in FY2006

advance procurement funding, and $1,131.1 million in FY2007 procurement funding. The Navy’s

proposed FY2008 budget requests $1,377.4 million in procurement funding to complete the

procurement cost of the ship. The ship is scheduled to be delivered to the Navy in December

2011.

As shown in Table 2, the Navy’s FY2008-FY2013 shipbuilding plan does not include any

additional “regular” LHA(R)s through FY2013, but does include two modified LHA(R)s for the

MPF(F) squadron—one in FY2010 and the other in FY2013. The Navy’s 30-year (FY200826

LPD-17-related work is also done at Northrop’s Ingalls shipyard at Pascagoula, MS, and at a third Northrop facility

at Gulfport, MS. The Avondale, Ingalls, and Gulfport facilities together make up Northrop Grumman Ship Systems

(NGSS).

27

LHD-8 will differ from the earlier LHDs in terms of propulsion plant and other respects.

Congressional Research Service

12

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

FY2037) shipbuilding plan shows the next “regular” LHA(R) being procured in FY2017. Both

“regular” LHA(R)s and modified LHA(R)s built for the MPF(F) squadron will be built at the

Ingalls shipyard that forms part of NGSS.

The LHA(R) design is to have enhanced aviation features compared to the basic Wasp-class

design, but would lack a well deck, making it the first amphibious ship in decades built without a

well deck. The sacrifice of the well deck appears to be, in part at least, a consequence of building

enhanced aviation features and other improvements into the design while staying within the

envelope of the Wasp-class hull.

MPF Lease Buyout

The Navy’s FY2008 UPL includes, at the 17th of 20 items, a $430-million proposal to buyout the

leases of the nine ships in the existing MPS force still under lease. Buying out the leases means

DOD would purchase the ships from the private companies that currently lease them to DOD.

DOD estimated in 2005 that buying out the leases on all 13 MPS ships would save about $840

million in payments between FY2006 and FY2020 (when the last of the 13 ships is to be phased

out of service). Since five of these 13 ships (the TAK-3000 class ships) were built in a foreign

country (Denmark), DOD requested legislative authority to spend NDSF funds to purchase these

five ships.28 The owners of some of these 13 ships reportedly believed in 2005 that the Navy

underestimated the market value of their ships, and that buying out the leases on them would cost

at least $500 million more than the Navy has budgeted. 29

Potential Issues for Congress

LPD-17 Cost Growth and Construction Problems

The LPD-17 program has experienced considerable cost growth and construction problems.

Cost Growth

The Congressional Budget Office (CBO) testified in July 2007 that the first LPD-17 experienced

cost growth of about 70% and was, on a per-ton basis, the most expensive amphibious ship ever

built for the Navy. 30 When LPD-17 procurement began, follow-on ships in the class were

estimated to cost roughly $750 million each. Estimated procurement costs for the follow-on ships

subsequently grew to figures between about $1,200 million and about $1,500 million. The Navy

estimates the procurement cost of the ninth ship at $1,798.3 million.

28

Christopher J. Castelli, “Pentagon Seeks Authority on Carl Vinson, LHA(R), Prepositioning Ships,” Inside the Navy,

May 2, 2005; Geoff Fein, “Navy Underestimated Cost to Buyout Leases on MSC Ships, Source Says,” Defense Daily,

May 10, 2005.

29

Geoff Fein, “Navy Underestimated Cost to Buyout Leases on MSC Ships, Source Says,” Defense Daily, May 10,

2005.

30

CBO Testimony, Statement of J. Michael Gilmore, Assistant Director for National Security, and Eric J. Labs, Senior

Analyst, [on] The Navy’s 2008 Shipbuilding Plan and Key Ship Programs, before the Subcommittee on Seapower and

Expeditionary Forces, Committee on Armed Services, U.S. House of Representatives, July 24, 2007, pp. 13 and 20.

Congressional Research Service

13

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

A relatively small portion of the cost growth in the program since its inception is attributable to

the decision to reduce the program’s sustaining procurement rate from two ships per year to one

ship per year. Most of the program’s cost growth is attributable to other causes.31

Construction Problems

The first LPD-17, which was procured in FY1996, encountered a roughly two-year delay in

design and construction. It was presented to the Navy for acceptance in late June 2005. A Navy

inspection of the ship conducted June 27-July 1, 2005, found numerous construction

deficiencies.32 The ship was commissioned into service on January 14, 2006. In April 2007, it was

reported that the first LPD-17 had thousands of construction deficiencies.33

The Navy accepted delivery of LPD-17 with about 1.1 million hours of construction work

remaining to be done on the ship. This equates to about 8.7% of the total hours needed to build

the ship, and (with material costs included) about 7% of the total cost to build the ship.

The Navy accepted delivery of LPD-18 with about 400,000 hours of construction work remaining

to be done on the ship. This equates to about 3.3% of the total hours needed to build the ship.

The Navy projects that it will accept delivery of LPD-19 with about 100,000 hours of

construction work remaining to be done on the ship. This would equate to about 0.8% of the total

hours needed to build the ship.

The Navy states that it accepted LPD-17 in incomplete condition for four reasons:

•

It permitted the fleet to begin sooner the process of evaluating LPD-17 through

operational use so as to identify problems with the LPD-17 class design that need

to be fixed in follow-on LPD-17s.

31

RAND estimates that halving a shipbuilding program’s annual procurement rate typically increases unit procurement

cost by about 10%. (Mark V Arena, et al, Why Has the Cost of Navy Ships Risen? A Macroscopic Examination of the

Trends in U.S. Naval Ship Costs Over the Past Several Decades. RAND, Santa Monica (CA), 2006. p. 45. (National

Defense Research Institute, MG-484-NAVY). The December 2006 Selected Acquisition Report (SAR) summary table,

available online at http://www.acq.osd.mil/ara/am/sar/2006-DEC-SST.pdf, states that in then-year dollars, changes in

the LPD-17 program’s production schedule (including the reduction in annual procurement rate) account for

$768.1million in increased costs for the program, or about 11.2% of the increased costs caused by all factors. The other

factors leading to increased costs were economic errors (meaning errors in projected rates of inflation), which account

for $361.7 million; estimating errors, which account for $4,648.8 million; and “other,” which accounts for $1,093.4

million. The LPD-17 program’s total cost was also reduced by $4,037.8 million due to the reduction in program

quantity from an originally planned total of 12 ships to the currently planned total of 9 ships. The resulting net change

in the program’s estimated cost is an increase of $2,832.2 million.

32

Associated Press, “Shipbuilder: Navy Will Accept New Vessel,” NavyTimes.com, July 21, 2005; Christopher J.

Castelli, “Naval Inspection Report Finds Numerous Problems With LPD-17,” Inside the Navy, July 18, 2005; Dale

Eisman and Jack Dorsey, “Problems On New Ship A Bad Sign, Analyst Warns,” Norfolk Virginian-Pilot, July 14,

2005; Nathan Hodge, “Navy Inspectors Flag ‘Poor Construction’ On LPD-17,” Defense Daily, July 14, 2005. A copy

of the Navy’s inspection report, dated July 5, 2005, is posted online at http://www.coltoncompany.com/

newsandcomment/comment/lpd17insurv.htm.

33

See, for example, Louis Hansen, “New Navy Ship San Antonio Found To Be Rife With Flaws,” Norfolk VirginianPilot, April 14, 2007; Christopher P. Cavas, “Thousands of Problems Found On New Amphibious Ship,”

DefenseNews.com, April 23, 2007.

Congressional Research Service

14

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

•

It avoided further delays in giving the LPD-17’s crew an opportunity to conduct

post-delivery tests and trial events that are intended to identify construction (as

opposed to class design) problems with LPD-17 itself.

•

It permitted LPD-17 to leave the shipyard sooner and thereby mitigated schedule

and cost impacts on other ships being built at the shipyard (other LPD-17s, LHD8, and DDG-51s) that would have resulted from having LPD-17 remain in the

shipyard longer.

•

It reduced the cost of the remaining construction work to be done on LPD-17

because the work in question could be performed by repair shipyards that charge

lower rates for their work than the construction shipyard.

Of the approximately $160 million in post-delivery work performed on LPD-17, $108 million

was for the 1.1 million hours of construction work remaining to complete the ship. (The rest was

for post-shakedown and other work that normally occurs after a ship is completed and delivered

to the Navy.)34 This $160 million in work was funded through the post-delivery part of the

outfitting/post-delivery (OF/PD) line item in the Shipbuilding and Conversion, Navy (SCN)

account. Since OF/DP costs are not included in ship end cost, the reported end cost of LPD-17

will understate the ship’s actual construction cost by $108 million.

The Navy plans to fund post-delivery construction work on LPD-18 and LPD-19 through the

completion of prior-year shipbuilding line item in the SCN account—a line item that is included

in ship end cost.

The Government Accountability Office (GAO) testified in July 2007 that:

The Navy moved forward with ambitious schedules for constructing LPD 17 and [the

Littoral Combat Ship] despite significant challenges in stabilizing the designs for these ships.

As a result, construction work has been performed out of sequence and significant rework

has been required, disrupting the optimal construction sequence and application of lessons

learned for follow-on vessels in these programs.

In the LPD 17 program, the Navy’s reliance on an immature design tool led to problems that

affected all aspects of the lead ship’s design. Without a stable design, work was often

delayed from early in the building cycle to later, during integration of the hull. Shipbuilders

stated that doing the work at this stage could cost up to five times the original cost. The lead

ship in the LPD class was delivered to the warfighter incomplete and with numerous

mechanical failures, resulting in a lower than promised level of capability. These problems

continue today—2 years after the Navy accepted delivery of LPD 17. Recent sea trials of the

ship revealed problems with LPD 17’s steering system, reverse osmosis units, shipwide area

computing network, and electrical system, among other deficiencies. Navy inspectors noted

that 138 of 943 ship spaces remained unfinished and identified a number of safety concerns

related to personnel, equipment, ammunition, navigation, and flight activities. To date, the

Navy has invested over $1.75 billion constructing LPD 17.35

34

On July 16, 2007, CRS and CBO asked the Navy to break down the $160 million figure into ship-construction work

and other work. The Navy’s response was not provided to CRS in time to be incorporated into this statement.

35

Government Accountability Office, Defense Acquisitions[:] Realistic Business Cases Needed to Execute Navy

Shipbuilding Programs, Statement of Paul L. Francis, Director Acquisition and Sourcing Management Team,

Testimony Before the Subcommittee on Seapower and Expeditionary Forces, Committee on Armed Services, House of

Representatives, July 24, 2007 (GAO-07-943T), p. 10.

Congressional Research Service

15

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

In late June and early July 2007, it was reported that Secretary of the Navy Donald Winter had

sent a letter to the chairman and chief executive officer of Northrop Grumman, Ronald Sugar,

dated June 22, 2007, expressing deep concerns about NGSS’s performance, particularly in

connection with the LPD-17 program. According to these news reports, Winter’s letter contained

the following statements among others, although not necessarily in the order shown below:

•

“I am deeply concerned about Northrop Grumman Ship Systems’ (NGSS) ability

to recover in the aftermath of Hurricane Katrina, particularly in regard to

construction of LPD 17 Class vessels.”

•

“I am equally concerned about NGSS’ ability to construct and deliver ships that

conform to the quality standards maintained by the Navy and that adhere to the

cost and schedule commitments agreed upon at the outset by both NGSS and the

Navy.”

•

“... even prior to Katrina [NGSS’s performance] was marginal, resulting in

significant cost overruns that forces the Navy to take delivery of the LPD-17 with

numerous outstanding deficiencies....”

•

“NGSS’ inefficiency and mismanagement of LPD 17 put the Navy in an

untenable position.”

•

“By taking delivery of ships with serious quality problems, the Fleet has suffered

unacceptable delays in obtaining deployable assets. Twenty-three months after

commissioning of LPD 17, the Navy still does not have a mission-capable ship.”

•

“These delays create further problems as work must be completed or redone by

other shipyards that are not as familiar with the ship’s design.”

•

“The Navy also took delivery of LPD-18 (USS New Orleans) in an incomplete

fashion, albeit more complete than LPD-17.”

•

“... persistent shortcomings at the NGSS yards are troubling and causing me not

only grave concern about the LPD program, but also the LHA and DDG-1000

programs.”

•

“The Navy does not wish to find itself in the same situation [with other ships

that] it faces with LPD 17 & 18.”

•

“It is imperative that NGSS deliver future ships devoid of significant quality

problems and that it meet its cost and schedule obligations.”

•

One press report stated: “‘Continued, focused management’ is necessary to

successfully deliver the remainder of the class, according to Winter.”

•

“[Navy acquisition executive] Dr. [Delores] Etter will be closely monitoring

metrics with NGSS and the acquisition team as we move forward.”36

36

Sources for these reported passages from the June 22 letter: Louis Hansen, “Navy Ship $840 Million Over Budget

And Still Unfinished,” Norfolk Virginian-Pilot, June 30, 2007; Tony Capaccio, “Northrop Grumman Criticized For

‘Mismanagement’ By U.S. Navy, Bloomberg News, July 2, 2007; Geoff Fein, “Navy To Monitor Work At Northrop

Grumman Gulf Coast Shipyards, Official Says,” Defense Daily, July 5, 2007; Christopher P. Cavas, “U.S. Navy

Furious Over LPD-17,” DefenseNews.com, July 9, 2007. InsideDefense.com on July 9, 2007, posted on the subscribersonly portion of its website a copy of what it says is the June 22 letter.

Congressional Research Service

16

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

Northrop chairman and CEO Sugar reportedly sent a reply letter to Winter dated June 29, 2007.

According to one press report, Sugar stated in the letter: “I share your concern regarding the need

to fully recover and improve our shipyards, and produce completed LPD 17 class vessels of the

highest quality with increasing efficiency.... Irrespective of Hurricane Katrina, Northrop has much

work to do to meet the needs of the U.S. Navy.”37 Another press report stated:

Northrop Grumman Corp (NOC) has ‘much more work to do’ to improve its performance on

Navy ships, but problems with a $13.6-billion amphibious ship program were not solely the

contractor’s making, Chief Executive Ron Sugar said in a June 29 letter.

“The original acquisition strategy was changed after contract award, there was funding

instability, limited early funding for critical vendor information, and the ‘integrated’

Navy/contractor design team produced constant design churn and thousands of design

changes,” Sugar wrote, responding to a tersely worded letter from Navy Secretary Donald

Winter.

Northrop “certainly had performance problems,” but the unprecedented effects of Hurricane

Katrina, which severely damaged Northrop’s three shipyards in the Gulf region in August

2005, “only served to greatly exacerbate the situation.”...

Sugar said he shared Winter’s concerns and vowed that Northrop would invest, train and

manage its operations to produce Navy ships of the highest quality with increasing

efficiency. “Irrespective of Hurricane Katrina, Northrop has much more work to do to meet

the needs of the U.S. Navy.”

“We are not happy with this history,” Sugar added in the letter obtained by Reuters, “but we

are incorporating the lessons from this experience into our operational plans going forward

for new ships in the design, planning and production stages.”

He noted that Navy recently praised Northrop’s work on a destroyer that was damaged by

Hurricane Katrina, and termed it “one of the best ships ever delivered.”

Sugar said Northrop officials had given the Navy a list of efforts under way to improve

training, quality, processes, productivity and facilities at the Gulf Coast shipyards. He

promised “substantial investment,” but gave no details.

He said Northrop was aggressively reworking schedules for delivery of all ships affected by

the hurricane. “We know we must do our part,” Sugar said.38

Potential oversight issues for Congress, including the following:

37

38

•

To what extent are cost growth and construction problems in the LPD-17

program due to poor performance by NGSS, poor performance by other

contractors, inadequate program management and oversight by the Navy,

Hurricane Katrina, and other factors?

•

What specific actions have NGSS, other contractors, and the Navy taken, and

what additional actions do they plan to take, to avoid further cost growth and

construction problems in the LPD-17 program?

Christopher P. Cavas, “U.S. Navy Furious Over LPD-17,” DefenseNews.com, July 9, 2007.

Andrea Shalal-Esa, “Northrop Says Katrina Exacerbated Ship Problems,” Reuters, July 10, 2007.

Congressional Research Service

17

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

•

Although the Navy in the past has accepted delivery of ships that were not

complete, has the Navy previously accepted delivery of a ship with one million

or more hours of shipyard construction work remaining to be done, and if so,

when?

Funding Additional Ships in FY2008

A potential key issue for Congress in marking up the Navy’s proposed FY2008 budget is whether

to procure an additional LPD-17 and/or one or two modified TAKEs in FY2008. As discussed

earlier, the additional LPD-17 is not currently in the Navy’s shipbuilding plan, and the two

modified TAKEs are currently in the plan for procurement in FY2009 and FY2010.

Supporters of procuring an additional LPD-17 in FY2008 could argue that this is the top item on

the Navy’s FY2008 UPL, and that building this ship would give the Navy a force of ten LPD-17s,

as called for in the Navy’s 313-ship plan. Supporters could argue that if Congress decides that it

has the funding available in FY2008, but perhaps not in a future year, to procure an additional

LPD-17, it should procure the ship in FY2008, even if the shipyard is not able to start work on it

right away, because the shipyard will eventually be able to build it, and because what will matter

more in the long run is the presence of this additional ship in the force structure, not the fact that

it took longer than average to build.

Opponents of procuring an additional LPD-17 in FY2008 could argue that unless the Navy’s

budget top line were increased, the $1,700 million or so needed to procure the ship might have to

come from other FY2008 Navy programs, disrupting these other programs and possibly creating

operational risks for the Navy in other areas. Opponents could argue that the shipyard that would

build this ship—the Avondale yard near New Orleans, LA, that forms part of NGSS—would not

be able to start work right away on an additional LPD-17 procured in FY2008 due to disruption

of the yard’s workforce and work schedule caused by Hurricane Katrina. Consequently,

opponents could argue, procuring this ship in FY2008 would amount to booking but not

(immediately) building a ship. Such an action, they could argue, would tie up $1,700 million in

budget authority that would not result in immediate obligations and expenditures.

Supporters of procuring one or two modified TAKEs in FY2008 could argue that this is the

second item on the Navy’s FY2008 UPL, and that accelerating these two ships from FY2009 and

FY2010, where they are currently planned, into FY2008, could release funding in the Navy’s

FY2009 and FY2010 budgets for additional ships or other programs. Supporters could argue that

funding one or both of these TAKEs in FY2008 in addition to the “regular” TAKE for Navy use

that is requested in the Navy’s FY2008 budget could improve economies of scale for these ships,

reducing their costs.

Opponents of procuring one or two modified TAKEs in FY2008 could argue that unless the

Navy’s budget top line were increased, the $1,200 million or so needed to procure the ship might

have to come from other FY2008 Navy programs, disrupting these other programs and possibly

creating operational risks for the Navy in other areas. Opponents could argue that the $1,200

million cost listed in the FY2008 UPL for these two ships suggests that procuring one or two

modified TAKEs in addition to the “regular” TAKE being procured in FY2008 will not

significantly reduce their cost.

Congressional Research Service

18

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

Estimated Cost of Two TAKEs in FY2008 UPL

As mentioned above, the Navy’s FY2008 UPL includes, as its second item, two modified TAKEs

for the MPF(F) squadron at an estimated combined procurement cost of about $1,200 million,

implying a unit procurement cost of about $600 million per ship. The “regular” TAKE that the

Navy wants to procure in FY2008 has an estimated procurement cost of $456.1 million. The

difference in unit procurement cost between the “regular” TAKE and the two modified TAKEs

raises a potential oversight question for Congress: Why does the Navy estimate that the two

modified TAKEs in the Navy’s FY2008 UPL would be approximately one-third more expensive

to procure than the “regular” TAKE that the Navy wants to procure in FY2008?

At a May 3, 2007, markup meeting of the Seapower and Expeditionary Forces subcommittee of

the House Armed Services Committee, the Representative Bartlett, the subcommittee’s ranking

member, stated the following in connection with the subcommittee’s decision to recommend $456

million in FY2008 for the procurement of an additional TAKE for the MPF(F) squadron:

Mr. Chairman, as we discussed earlier this week, I would ask that as we move forward, we

continue to refine funding for T-AKE. I understand that while the mark in Title III [in the

National Defense Sealift Fund] fully funds the procurement cost for an additional T-AKE in

Fiscal Year 2008, the actual cost of an additional T-AKE in 2008, may be $122 million $145 million greater than the amount provided in the mark. This is due to additional post

delivery and outfitting costs, which are separate from procurement costs, and also due to

material cost escalations, not reflected in the baseline budget request for the Fiscal Year 2008

ship.39

Adequacy of 30- or 31-Ship Amphibious Ship Force

The Navy and Marine Corps currently appear to disagree on whether a 30 or 31-ship amphibious

force would be adequate. The Marine Corps has testified that it would prefer a 33-ship force, so

as to support a required total force of 30 operationally available ships (i.e., ships not in depotlevel maintenance and repair) at any given point:

For forcible entry, the Marine Corps’ requirement is a single, simultaneously-employed two

Marine Expeditionary Brigade (MEB) assault capability. One MEB requires seventeen

amphibious warfare ships; however, given the fiscally constrained environment, the Navy

and Marine Corps have agreed to assume risk by only using fifteen. Historical amphibious

ship availability rates dictate a minimum of eleven ships of each of the current types of

amphibious ship—a minimum of thirty-three total ships—resulting in a Battle Force that

provides thirty operationally available amphibious warfare ships. In that Battle Force, ten

aviation-capable big deck ships (LHA/LHD/LHA(R)) and ten LPD 17 class ships are

required to accommodate the MEB’s aviation combat element.40

The Navy has testified that when the capabilities of the MPF(F) squadron, which includes three

amphibious assault ships, are taken into account, a force of 30 amphibious ships (one fewer than

the 31 called for in the 313-ship plan) is adequate:

39

Opening Statement of Ranking Member Roscoe Bartlett, Mark-up of the National Defense Authorization Act for

Fiscal Year 2008, May 3, 2007.

40

See, for example, Statement of General James T. Conway, Commandant of the Marine Corps, Before the Senate

Armed Services Committee on Marine Corps Posture, March 29, 2007, p. 24. Italics and underlining as in the original.

Congressional Research Service

19

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

The ability of our future fleet to meet the demand signal for amphibious forces must be

viewed in the aggregate. Given the cost of ships today, we cannot discount the value of ships

procured to support prepositioned equipment. Prepositioned assets must be included in the

overall force availability equation—ignoring MPF(F) as the lift component of an additional

MEB is would be incongruous with today’s fiscal environment. The capabilities provided by

the MPF(F) mitigate concerns regarding the operational availability of the assault echelon

force required to deliver 2.0 Marine Expeditionary Battalion (MEB) lift, vehicle square

footage, and passenger requirements. As reflected in our 30 year shipbuilding plan, we

believe 30 amphibious ships will meet these requirements, when supported by, and

supporting, the MPF(F).41

A May 2007 press report states:

Navy and Marine Corps officials are engaged in a major debate about the kind of fleet the

sea service will need in the future, but senior leaders are pledging to resolve their differences.

The debate focuses on the number of amphibious ships that will be built in future years as

well as plans for new vessels designed to create bases at sea.

Marine Commandant Gen. James Conway and Chief of Naval Operations Adm. Michael

Mullen recently agreed to “come to grips” with these issues, Conway told Inside the Navy on

May 2, noting both sides need to understand each other’s philosophies.

“We’re going to meet on that,” he said. “We’ve got a meeting coming up as soon as Mike

Mullen can get with us.” The meeting will be the “next step in the process,” he said.

Mullen made similar remarks the next day at a Senate Armed Services seapower

subcommittee hearing on Capitol Hill.

The admiral said he and Conway agreed there is a requirement to have 30 amphibious ships

operationally available in the future. Based on past experience, the services estimate 33 ships

would be needed to ensure 30 are always available, Mullen said.

“Now that’s how we’ve done it historically,” Mullen said.

But the Navy’s shipbuilding plan maintains only 30 amphibious vessels from fiscal year

2015 onward, which has sparked complaints from Conway....

Mullen told senators he has committed to providing the Marine Corps with the lift capability

it needs. But he seemed to suggest alternatives to buying more amphibious ships.

“We’ve got to look at how we’re going to fight in the future and specifically how we’re

going to move this 2.0 [i.e., Marine expeditionary brigades] into the fight,” Mullen said.

“Gen. Conway and I have agreed to figure out a way together to make that work.”

The fixes could include achieving a higher availability rate for ships (some of which would

depend on the warning time involved in particular situations), Mullen said.

The admiral also said new maritime prepositioning ships—MPF(F) vessels designed to form

sea bases—could help move Marines to the fight in the future.

41

Statement of Admiral Michael G. Mullen, Chief of Naval Operations, Before the Senate Armed Services

Subcommittee on Seapower, May 3, 2007, p. 12.

Congressional Research Service

20

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

But MPF(F) has been a contentious subject. The Marine Corps has argued civilian-manned,

unarmed MPF(F) ships cannot provide the forcible-entry capability associated with

amphibious warships.

Sorting through these issues will not be easy, but the outcome will have very important

implications for plans to build sea bases with MPF(F) ships, Mullen said....

[T]he cost of the [MPF(F)] squadron—which Mullen called “significant”—has been a source

of tension with the Marine Corps because the Navy argues it cannot afford to develop

MPF(F) ships without buying fewer traditional amphibious ships, which carry Marine

forces....

Further, unlike amphibious warships, the MPF(F) squadron’s amphibious vessels will lack

active self-defense systems and will not be operated by Navy sailors.

Conway has publicly argued MPF(F) vessels will not provide forcible-entry capabilities and

should not be considered part of the traditional amphibious fighting force known as the

assault echelon....

Further, officials have discussed the idea of having the big-deck amphibious ships associated

with MPF(F) sail with other amphibious ships in the expeditionary strike force and not with

the unarmed, civilian-manned ships.

Vice Adm. Jonathan Greenert, deputy chief of naval operations for integration of capabilities

and resources, acknowledged this discussion late last month, but did not say how the Navy

views the idea.

“It’s an option,” he told [Inside the Navy] on April 24, following a congressional hearing....

Greenert declined to predict the outcome of the talks.

“I can’t tell you how it’s going to come out because we’re having the debate,” he said. “And

it’s more of a discussion than a debate. Debate would imply that there’s only two ways to

solve this. We’re sitting down and going through the capabilities in the aggregate.”42

Potential oversight questions for Congress include the following:

•

What are the potential operational risks of having a force of 30 or 31 amphibious

ships rather than 33? What steps can be taken to mitigate these risks?

•

What are the operational risks of having 15 operational amphibious ships for

each MEB, rather than 17?

Stability of Amphibious and MPF(F) Force Level Goals

Perhaps reflecting the apparent disagreement between the Navy and Marine Corps regarding the

required size of the amphibious force, the Navy has suggested that it might change its required

numbers of amphibious and MPF(F) ships. The Navy’s February 2007 report on the 30-year

(FY2008-FY2037) shipbuilding plan stated:

42

Christopher J. Castelli, “Conway and Mullen Seek To Resolve Debate On Future Fleet,” Inside the Navy, May 7,

2007.

Congressional Research Service

21

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

Future combat operations may require us to revisit many of the decisions reflected in this

report, including those associated with amphibious lift. As the Navy embarks on production

of the Maritime Prepositioning Force in this FYDP, the Navy will continue to analyze the

utility of these ships in terms of their contribution to, and ability to substitute for, the assault

echelon forces in the Navy’s future battle-force inventory. The current force represents the

best balance between these forces available today. However, changing world events and

resulting operational risk associated with the various force structure elements that make up

these two components of overall lift will be analyzed to ensure the Navy is not taking

excessive risk in lift capability and capacity. While there needs to be a balance between

expeditionary and prepositioning ships for meeting the overall lift requirement, future reports

may adjust the level of support in one or both of these solutions. Any adjustments made in

these capabilities will have to be accommodated in light of the resources available and could

require the Navy to commit additional funding to this effort in order to support the overall

balance of our shipbuilding program.43

Potential oversight questions for Congress include the following:

•

When might the Navy know whether it wants to change its required numbers of

amphibious and/or MPF(F) ships?

•

How might these numbers change?

•

How much confidence can Congress have in the stability of the Navy’s current

stated requirements for amphibious and MPF(F) ships?

•

Should Congress take actions to hedge against the possibility of the Navy

changing its requirements for amphibious and MPF(F) ships, and if so, what

actions?

Crewing of Large-Deck MPF(F) Ships

The Navy and Marine Corps have not yet determined what combination of civilian mariners and

Navy personnel will be used to crew the three large-deck amphibious assault ships in the MPF(F)

squadron. The February 2007 Navy report on the MPF(F) program contains a section devoted to

the question of crewing MPF(F) ships, which states in part:

The use of Civilian Mariners or MSC contracted Mariners as operational crews for MPF(F)

ships has been proposed and briefed to Navy Judge Advocate General (JAG) representatives

on August 30, 2006. The Navy JAG provided a memorandum on September 19, 2006,

confirming that there are no legal objections to developing the two options defined. The one

option is to initially designate the aviation big decks as naval auxiliaries (USNS), manned

with 100% civilian crew, but develop the capability to timely and seamlessly convert them to

warships (USS) in order to employ them during an international armed conflict. The other

option is to designate the big decks as warships (USS) upon initial commissioning, and man

them with mixed military-civilian crews. Regardless of option, when operating as a warship,

the platforms will need a Navy Commanding Officer and selected senior staff (this

requirement may be met by Mariners who are in the Navy Reserve). Ship crew not engaged

in warfighting functions may remain civilian mariners, performing propulsion, ship

auxiliaries, and housekeeping type operations. With both options the other ships in the

squadron (due to their roles and logistics centric activities) may be permanently designated

43

U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2008, p. 5.

Congressional Research Service

22

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

as USNS throughout their employment. Precedence has been established for selected

capabilities by ships such as the USNS STOCKHAM and USS MOUNT WHITNEY.44

Potential oversight questions for Congress include the following:

•

What are the potential cost and operational implications of manning options for

the large-deck amphibious assault ships in the MPF(F) squadron?

•

When do the Navy and Marine Corps anticipate making a decision on the

manning strategy for these ships?

Clarity of Sea Basing Concept

The February 2007 report to Congress on the MPF(F) program refers to sea basing as “an

emerging concept.”45 Some observers have expressed concern about a lack of clarity regarding

the meaning of sea basing, and consequently about what kinds of shipbuilding and other

programs are needed to implement it. For example, Robert Work, a naval analyst at the Center for

Strategic and Budgetary Assessments (CSBA), an independent defense-policy research institute,

states the following in a lengthy report on sea basing released in November 2006:

“Seabasing” is a new defense buzzword of growing importance and prominence in both joint

and naval circles. Unfortunately, despite the increasingly common use of the term by both

joint and naval planners alike, there still remains much mystery and misunderstanding about

this important “new” concept. Indeed, one of the key problems that has hindered meaningful

debate and discussion about seabasing—and especially the priorities revealed in its

associated plans and programs—is that its contemporary definition and the important ideas

that support it are poorly understood except among the relatively small group of officers and

planners who have been intimately involved with their development.

To make matters worse, since its grand unveiling by the Department of the Navy (DoN) in

2002, the concept’s definition has constantly changed. For example, in August 2005, the

Seabasing Joint Integrating Concept (JIC) defined seabasing as “the rapid deployment,

assembly, command, projection, reconstitution, and re-employment of joint combat power

from the sea, while providing continuous support, sustainment, and force protection to select

expeditionary joint forces without reliance on land bases within the Joint Operations Area

(JOA). These capabilities expand operational maneuver options and facilitate assured access

and entry from the sea.” However, in the very month the Seabasing JIC was published, The

DOD Dictionary of Military and Associated Terms, amended through August 31, 2005,

defined seabasing as, “in amphibious operations, a technique of basing certain landing force

support functions aboard ship which decreases shore-based presence.” Moreover, as is

explained in this report, both of these definitions—and others like them—are unduly

restrictive, incomplete, confusing, or all of these things.

Partly as a result, there remains much uncertainty over exactly what seabasing is, and over

the current programmatic and budgetary direction of joint seabasing programs....

[T]he current definition for seabasing and the direction of its programs are narrowly focused

on one thing: revitalizing the DoN’s seabased operational maneuver and seabased

expeditionary power-projection capabilities which were allowed atrophy during the Cold

44

45

Report to Congress, Maritime Prepositioning Force (Future) [or] MPF(F) [Program], op cit, p. 14.

Report to Congress, Maritime Prepositioning Force (Future) [or] MPF(F) [Program], op cit, p. 2.

Congressional Research Service

23

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

War. The list of seabasing functions is much longer.... Only if all of these seabasing

functions are understood and compared can a rational prioritization of planned seabasing

improvements occur....

[A]lthough seabasing concept development within both the Department of the Navy and the

Department of Defense (DoD) is focused on seabased operational maneuver and

expeditionary power-projection capabilities, its disjointed development since the end of the

Cold War has only served to confuse an urgently needed open debate and discussion about

the future of naval maneuver in general and amphibious operations in particular, and the best

mix of platforms to support both. Central to this debate is whether or not future forcible entry

operations from the sea should be conducted from amphibious warships or commercialstandard MPF(F) ships, or a combination of both; and whether or not these operations should

emphasize surface maneuver, aerial maneuver, or a combination of the two. The current

understanding of both these issues need to be thoroughly questioned and reviewed.46

A January 8, 2008 defense trade press article states:

The Navy and Marine Corps have spent the past year working to better define the

requirement for sea base operations, looking at platform needs and how best to move

warfighters and their equipment from ship to shore, a Marine Corps official said.

The cornerstone of the sea basing effort is the Navy’s Maritime Preposition Force Future or

MPF(F).

“We learned a lot in the last year in developing the requirement,” Maj. Gen. Thomas Benes,

director, Expeditionary Warfare, told Defense Daily in a recent interview.

The two services took a step back and spent a lot more time reviewing the MPF(F), he

added. “We needed to define the requirement a little bit more between the two services, and

we did that.

“There is alignment between the Commandant (Gen. James Conway) and the CNO (Chief of

Naval Operations Adm. Gary Roughead). They definitely understand and have given us

guidance as to where we need to develop this,” Benes said. “MPF(F) is now going to be a

reinforcing capability to deliver a MEB (Marine Expeditionary Brigade) from a sea base.”47

Affordability and Cost-Effectiveness of Sea Basing

One issue in assessing the cost of the sea basing concept concerns the accuracy of the Navy’s

procurement cost estimate for the new-construction sea basing ships. If these estimates turn out to

be too low, the sea basing concept would be more difficult to afford. Navy ship construction costs

in recent years have risen more quickly than some anticipated. Several recent Navy ships

procured in recent years have turned out to be more expensive to build than the Navy originally

46

Robert Work, Thinking About Seabasing: All Ahead, Slow. Washington, CSBA, 2006. pp. iii-v.

47

Geoff Fein, “Navy, Marine Corps Gaining Better Understanding of Sea Basing Requirements,” Defense Daily,

January 8, 2008.

Congressional Research Service

24

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

projected. 48 CBO believes the Navy is currently underestimating the procurement cost of

proposed ships.49

In addition, as previously discussed, fully implementing the sea basing concept will involve

procuring connector ships as well as research and development work to develop supporting sea

basing technologies. The costs of these development and procurement efforts are currently

unclear, making it difficult to assess the potential overall affordability of the sea basing concept.

Although sea basing offers potential advantages in terms of eliminating vulnerable intermediate

land bases, enabling higher-paced operations ashore, and permitting more rapid reconstitution and

redeployment of the expeditionary force, uncertainty regarding the total potential cost to

implement sea basing makes it difficult to assess its potential cost-effectiveness compared to

alternative concepts for conducting future expeditionary operations ashore or compared to

programs for meeting other, unrelated defense priorities. Potential alternative concepts for

conducting future expeditionary operations include making improvements to today’s capabilities

for conducting amphibious operations and making improvements to Army capabilities for

inserting airborne forces.50

Skeptics of the Navy’s plan for implementing the sea basing concept could argue that the

capability to be provided by the MPF(F) squadron is more than what is needed for the Navy’s

contribution to the global war on terrorism (GWOT), and of uncertain relevance to U.S.

participation in a conflict with China in the Taiwan Strait area.51 Navy and Marine officials

disagree with this view (see discussion below).

Navy Perspective

Regarding the affordability of the MPF(F) squadron, the February 2007 Navy report on the

MPF(F) program states:

The MPF(F) squadron will be affordable over its lifecycle (research, development,

acquisition, operation and maintenance costs). Doctrine, Organization, Training, Materiel,

Leadership and education, Personnel and Facilities (DOTMLPF) cost will be considered.

Life cycle cost reduction will be stressed in the development of the one new design, the

MLP, to ensure long term value to the Navy and Marine Corps.

The Navy’s independent cost estimating arm, NAVSEA Code 017, led all AoA [Analysis of

Alternatives] and post AoA cost analyses and produced all comparative cost estimates using

approved Navy and DoD cost estimating practices. The threshold and objective values below

48

See, for example, Government Accountability Office, Defense Acquisitions[:] Improved Management Practices

Could Help Minimize Cost Growth in Navy Shipbuilding Programs. (GAO-05-183, February 2005)

49

See, for example, Congressional Budget Office, Resource Implications of the Navy’s Fiscal Year 2008 Shipbuilding

Plan, March 23, 2007, and CBO Testimony, Statement of J. Michael Gilmore, Assistant Director for National Security,

and Eric J. Labs, Senior Analyst, [on] The Navy’s 2008 Shipbuilding Plan and Key Ship Programs, before the

Subcommittee on Seapower and Expeditionary Forces, Committee on Armed Services, U.S. House of Representatives,

July 24, 2007.

50

See also John P. Patch, “Sea Basing: Chasing the Dream,” U.S. Naval Institute Proceedings, May 2005: 38-43.

51

For more discussion of these two issues, see CRS Report RS22373, Navy Role in Counterterrorism and Irregular

Warfare: Background and Issues for Congress, by Ronald O’Rourke, and CRS Report RL33153, China Naval

Modernization: Implications for U.S. Navy Capabilities—Background and Issues for Congress, by Ronald O’Rourke.

Congressional Research Service

25

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

represent a more affordable prepositioned lift and delivery of warfighting capability than

other alternatives with the same or similar capability.52

Navy and Marine Corps officials argue that seabasing is relevant to a spectrum of potential future

operations, ranging from humanitarian and disaster-relief operations to stability operations and

major combat operations (MCOs). In support of this argument, they note the recent use of U.S.

naval forces in providing disaster relief following the December 2004 tsunami in the Indian

Ocean and Hurricane Katrina along the U.S. Gulf Coast.53

CBO Perspective

A November 2004 Congressional Budget Office (CBO) report on the Navy’s amphibious and

maritime prepositioning ship forces expressed concerns about the Navy prospective ability to

expressed concerns about the Navy’s potential ability to afford desired numbers of both MPF(F)

ships and ships for the regular amphibious force.54

A July 2007 CBO study compared the potential costs and capabilities of eight alternatives for

deploying and/or sustaining ground combat forces—the Navy’s proposed MPF(F) squadron

(referred to in the CBO report as Alternative E1) and seven other approaches. The report states:

Five of the alternatives would include some form of a base at sea. The other three would

deliver forces and supplies by aircraft. To examine the potential benefits of new

technologies, four of the alternatives would develop new systems—rotorcraft able to carry a

greater payload of passengers and cargo and with a longer range than existing rotorcraft, and

large airships with greater payloads than conventional aircraft.

The eight alternatives are grouped into two sets of four. The first group of four (Alternatives

E1 through E4) could both employ one brigade and sustain two brigades; the second group

of four (Alternatives S1 through S4) could only sustain two brigades that were already in

place. Although the alternatives are generally structured to employ and/or sustain ground

forces that are similar in size, their specific capabilities would vary considerably.

CBO’s analysis of those alternatives points to several general conclusions.

—The planned MPF(F) would provide a capability similar to today’s amphibious task forces

but with improved responsiveness—a MEB-sized force could be ready one to two weeks

earlier for a conflict in the Persian Gulf or Indian Ocean region—and with a much smaller

logistics presence required ashore.

—Alternative systems could provide lesser but still substantial improvements in capability at

a significantly lower cost than that of the MPF(F). For example, although Alternative E3

(adding sea-based logistics to amphibious task forces) would not improve response time, it

52

Report to Congress, Maritime Prepositioning Force (Future) [or] MPF(F) [Program], op cit, p. 15.

53

See, for example, Geoff Fein, “Relief Efforts In Gulf Demonstrate Sea Basing Capability, CNO Says,” Inside the

Navy, October 7, 2005; Nathan Hodge, “Marine Corps Commandant Stumps For ‘Sea Basing’ Capability,” Defense

Daily, August 19, 2005; John Liang, “Hagee: Seabasing Can Contribute To More Than Just Combat Ops,” Inside the

Navy, August 15, 2005.

54

U.S. Congressional Budget Office, The Future of the Navy’s Amphibious and Maritime Prepositioning Force,

November 2004, pp. xiii-xv. See also Aarti Shah, “Unclear Seabasing Concept, High Costs Worry Military Officials,”

Inside the Navy, February 14, 2005.

Congressional Research Service

26

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

would offer most of the logistics improvements expected from the MPF(F) but at less than

one-fifth of the cost.

—Achieving greater capabilities than those currently envisioned for the MPF(F) would

probably require significantly higher investment—either larger numbers of systems or new,

more capable, and therefore more expensive systems.

The alternatives examined by CBO in this study would satisfy the primary objectives of the

third and/or fourth of the [Joint Chiefs of Staff Sea Basing Joint Integrating Concept’s, or

JIC’s] lines of operation (employment and sustainment, respectively). Alternatives E1

through E4 are structured to provide a ship-to-shore delivery capacity sufficient to employ a

Marine expeditionary brigade in 8 to 10 hours and to deliver enough supplies per day by

aircraft to support the MEB plus an Army light brigade. Alternatives S1 through S4 are

structured to deliver enough supplies per day by aircraft to sustain those two types of

brigades. The extent to which the alternatives meet the performance objectives for the JIC’s

other lines of operation varies.55

CSBA Perspective

Robert Work of CSBA characterized sea basing in 2004 as “a rich man’s approach to solving the

[access denial] problem.”56 In his November 2006 report on sea basing, Work states that

seabasing programs

are being conceived of and pursued long before the full range of desired and possible joint

seabasing capabilities have been adequately explored and debated. The end result: current

seabasing plans are rather narrowly focused on two rather limited capabilities—landing a

single brigade on a hostile shore in 11 to 17 days from the “go” order, and thereafter

providing seabased logistical support for two early entry brigades until follow-on joint forces

arrive.

It is true that these two key capabilities reflect the “top level requirements” identified in the

aforementioned Seabasing JIC. However, these two capabilities reflect a view of seabasing

that rests upon questionable assumptions and analysis.57

Potential Oversight Questions

Potential oversight and policy questions for Congress include the following:

•

If the procurement costs of the new-construction ships in the proposed MPF(F)

squadron turn out to be higher than the Navy estimates, how might this affect the

affordability of the sea basing concept?

•

When does DOD intend to present to Congress an estimate of the potential total

cost to fully implement all aspects of the sea basing concept? How does the

current absence of such an estimate affect Congress’s ability to assess the

potential affordability of sea basing or its potential cost effectiveness compared

55

Congressional Budget Office, Sea Basing and Alternatives for Deploying and Sustaining Ground Forces, July 2007:

ix.

56

As quoted in Otto Kreisher, “Sea Basing,” Air Force Magazine, July 2004. Material in brackets as in the article.

57

Thinking About Seabasing: All Ahead, Slow, op. cit., p. iv.

Congressional Research Service

27

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

to potential alternatives for conducting future expeditionary operations ashore or

compared to programs for meeting other defense priorities?

•

What is the potential applicability of the capability to be provided by the MPF(F)

squadron to the GWOT or to other potential conflict or non-conflict scenarios?

•

Would an ability to employ one surface Marine battalion and one vertical Marine

battalion from a sea base in a period of 8 to 10 hours be worth the cost to field

this capability? What are the potential costs and merits of alternatives to sea

basing for conducting future expeditionary operations ashore? How do land bases

and sea bases compare in terms of vulnerability to attack and cost to defend

against potential attacks of various kinds?

•

What other defense programs might need to be reduced to finance the

implementation of sea basing?

•

What are the potential operational risks of not implementing sea basing?

Relationship to Global Fleet Station (GFS) Concept

Another potential oversight issue for Congress concerns the Global Fleet Station (GFS) concept

and its relationship to the form of sea basing to be implemented with the planned MPF(F)

squadron. Potential oversight questions for Congress include the following:

•

Since the Navy has stated that each of a potential total of five GFSs might be

built around an LPD- or LSD-type amphibious ship, or around a high-speed

vessel (HSV), how might implementing the GFS concept affect planned

deployments and force-structure requirements for these kinds of ships?

•

What is the relationship between the GFS concept and the form of sea basing to

be implemented with the MPF(F) squadron? Can the GFS concept be viewed as

“sea basing light”? How might the existence of up to five GFSs in various

regions affect requirements for the planned MPF(F) squadron, or for the ships

that are to make up that squadron? Is the Navy proposing the GFS with the

partial aim or hope that the concept will eventually take the place in Navy

planning of the MPF(F)-based notion of sea basing?

Coordination with Other Services on Sea Basing

Regarding interservice coordination in the development of sea basing, the February 2007 Navy

report on the MPF(F) program states:

Joint Force requirements are included and validated via the Joint Capabilities Integration and

Development System (JCIDS) process. The MPF(F) CDD [Capability Development

Document] has been introduced and fully vetted to the Joint community within JCIDS,

which will result in a Joint Requirement Oversight Council (JROC) review in March 2007.

Additionally, the MPF(F) CDD provides traceability to the emerging Seabasing concept, and

to associated capability gaps. The Seabasing Capabilities Based Assessment Functional

Needs Assessment has identified capability gaps (JROC approved November 6, 2006).58

58

Report to Congress, Maritime Prepositioning Force (Future) [or] MPF(F) [Program], op cit, p. 16.

Congressional Research Service

28

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

A January 2007 Government Accountability Office (GAO) report states:

While DOD has taken action to establish a joint seabasing capability, it has not developed a

comprehensive management approach to guide and assess joint seabasing. GAO’s prior work

showed that sound management practices for developing capabilities include involving top

leadership, dedicating an implementation team, and establishing a communications strategy.

DOD is developing a joint seabasing concept and various DOD organizations are sponsoring

seabasing initiatives. However, DOD has not provided sufficient leadership to guide joint

seabasing development and service initiatives are outpacing DOD’s analysis of joint

requirements. DOD also has not established an implementation team to provide day-to-day

management to ensure joint seabasing receives the focused attention needed so that efforts

are effective and coordinated. Also, DOD has not fully developed a communications strategy

that shares information among the organizations involved in seabasing. Without a

comprehensive management approach containing these elements, DOD may be unable to

coordinate activities and minimize redundancy among service initiatives.

DOD has not developed a joint experimentation campaign plan, although many seabasing

experimentation activities—including war games, modeling and simulation, and live

demonstrations—have taken place across the services, combatant commands, and other

defense entities. No overarching joint seabasing experimentation plan exists to guide these

efforts because the U.S. Joint Forces Command has not taken the lead in coordinating joint

seabasing experimentation, although it has been tasked with developing a biennial joint

experimentation campaign plan for future joint concepts. While the U.S. Joint Forces

Command is in the process of developing the plan, it is unclear the extent to which this plan

will address joint seabasing or will be able to guide joint seabasing experimentation efforts.

Without a plan to direct experimentation, DOD and the services’ ability to evaluate

solutions, coordinate efforts, and disseminate results could be compromised.

While service development efforts tied to seabasing are approaching milestones for

investment decisions, it is unclear when DOD will complete development of total ownership

cost estimates for a range of joint seabasing options. Joint seabasing is going through a

capabilities-based assessment process that is intended to produce preliminary cost estimates

for seabasing options. However, DOD has not yet begun the specific study that will identify

potential approaches, including changes to doctrine and training as well as material solutions,

and produce preliminary cost estimates. DOD officials expect the study will not be complete

for a year or more. Meanwhile, the services are actively pursuing a variety of seabasing

initiatives, some of which are approaching milestones which will guide future program

investments. Until total ownership cost estimates for joint seabasing options are developed

and made transparent to DOD and Congress, decision makers will not be able to evaluate the

cost-effectiveness of individual service initiatives.59

Robert Work’s November 2006 report on sea basing states that

under no circumstances should seabasing be viewed as a naval concept that “enables” joint

operations. As a maritime concept and key component of emerging forms of joint littoral

warfare marked by the widespread use of guided weapons, seabasing initiatives should be

prioritized and pursued by a joint organization. Therefore, the 2004 decision by the Office of

the Secretary of Defense (OSD) not to stand up a Joint Project Office for Seabasing and to

instead consign the concept to the new Joint Concept Integration and Development System

59

Government Accountability Office, Force Structure[:] Joint Seabasing Would Benefit from a Comprehensive

Management Approach and Rigorous Experimentation before Services Spend Billions on New Capabilities, GAO-07211, January 2007.

Congressional Research Service

29

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

process was a serious mistake—one only compounded by assigning the Navy to be the lead

agent for the Seabasing [Joint Integrating Concept]....

[Observations developed throughout this report] suggest that OSD should order a thorough

zero baseline review of the joint seabasing concept. This review should take its basic

guidance from the 2005 National Defense Strategy and the 2005/06 Quadrennial Defense

Review. These two documents provide guidance that is broad enough to facilitate a thorough

and independent zero baseline seabasing review that is free of any preconceived notions or

concepts. In this regard, while such a review should consider all concept work and program

definitions to date, it is important that the review be in no way constrained by them. In this

regard, OSD should not make the same mistake it made in 2002, when it directed the

Defense Science Task Force on Seabasing to use an existing naval seabasing concept as its

start point. It should instead direct the group conducting the review—either a newly formed

Joint Project Office on Seabasing or a group composed of retired Combatant Commanders—

to start from a clean sheet of paper, and to recommend the seabasing program with the

highest joint payoff in the 21st century.60

An October 2005 press article stated:

Cultural differences between the services are one of the stumbling blocks holding up

development of the U.S. Navy’s new Sea Basing concept, a former officer told a group of

industry representatives here last week.

Greg Cook, a U.S. Air Force colonel who retired in August after working to develop Sea

Basing plans and concepts for the Joint Chiefs of Staff, said the “roles-and-missions debate”

centered on how different services and commands viewed the idea of a squadron of large

ships gathered as an operating base about 100 miles off an enemy shore.

“If the Army operates from the sea, isn’t that what the Marines do?” Cook asked an audience

gathered here Oct. 26 to discuss future naval planning. “If the Air Force operates from the

sea, isn’t that what the Navy does?”

Cook said the services view the Sea Basing concept in light of their own traditional missions.

The Army looks at the idea as allowing for faster and greater strategic access via the highspeed, shallow-draft connectors to transfer troops, vehicles and gear between the ships and

shore.

The Air Force doesn’t see the concept as supporting its core competencies and is concerned

about costs, said Cook, a former pilot for that service’s Air Mobility Command.

“The Air Force is not that excited” about the idea, he said.

The Navy, he said, looks at Sea Basing as “a foundation of strategic access and power

projection,” but the Marine Corps is looking at it simply as a faster means to deliver a

Marine Expeditionary Brigade to the fight.

Special Operations Command sees it as a “high-speed mothership for rapid access,” while

joint commanders have a wider view, regarding it as a mobile base that provides options and

flexibility that increases global presence and provides strategic access.

60

Thinking About Seabasing: All Ahead, Slow, op. cit., p. iv-v, vi.

Congressional Research Service

30

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

“These things have to be worked out,” Cook said. The question of who should operate the

ships is another issue, he said.61

Potential oversight questions for Congress include the following:

•

To what degree, if any, does the Navy-Marine Corps concept for sea basing

conflict with emerging Army or Air Force concepts of operation for conducting

future expeditionary operations? Are the Navy and Marine Corps taking potential

Army, Air Force, and Special Operations Command requirements sufficiently

into account in developing the sea basing concept?

•

How might the Army’s new plan for reorganizing itself into modular, brigadesized entities called units of action (UAs)62 affect, or be affected by, the sea

basing concept? How might the Army’s plans for procuring its own nextgeneration sealift ships affect, or be affected by, the sea basing concept?

•

Should OSD order a review of the seabasing concept by a newly formed joint

project office on seabasing or a group composed or retired combatant

commanders, as suggested by the 2006 CSBA report?

Legislative Activity for FY2008

FY2008 Budget Request

LPD-17 Program

The Navy’s proposed FY2008 budget requests $1,398.3 million in procurement funding a ninth

San Antonio (LPD-17) amphibious ship to be procured in FY2008. The Navy estimates the total

procurement cost of this ship at $1,798.3 million. The ship received $296.2 million in FY2008

advance procurement funding, and the Navy’s proposed FY2008 budget calls for the final $103.2

million of the ship’s procurement cost to be provided in FY2009 as a “program closeout” cost.

Although the Navy’s proposed force of 31 amphibious ships includes 10 LPD-17 class ships, the

Navy is proposing in its FY2008 budget to end LPD-17 procurement with the ninth ship.

LHA-6/LHA(R) Program

The Navy’s proposed FY2008 budget also requests $1,377.4 million in procurement funding to

complete the procurement cost of LHA-6, a large-deck amphibious assault ship that was procured

in FY2007 using split funding (a two-year form of incremental funding) in FY2007 and FY2008.

The Navy estimates the total procurement cost of LHA-6 at $2,806.2 million.

61

Christopher P. Cavas, “‘Cultural Differences’ Slow USN Sea Basing Progress,” DefenseNews.com, October 31,

2005.

62

For more on this plan, see CRS Report RL32476, U.S. Army’s Modular Redesign: Issues for Congress, by (name r

edacted).

Congressional Research Service

31

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

TAKE Program

The Administration’s proposed FY2008 defense budget requests $1,044.2 million for the National

Defense Sealift Fund (NDSF). Included in this request is $456.1 million for a “regular” Lewis

and Clark (TAKE-1) class dry cargo ship to be used a Navy auxiliary (rather than as part of the

MPF(F) squadron).

Navy FY2008 Unfunded Priorities List (UPL)

The Navy’s FY2008 unfunded programs list (UPL)—a list of programs that the Navy desires but

which are not funded in the Navy’s proposed FY2008 budget—includes, as its top item, an

additional LPD-17 at an estimated cost of about $1,700 million, and, as its second item, two

modified TAKE-1 class ships for the MPF(F) squadron, at an estimated combined cost of about

$1,200 million. These two TAKEs are currently scheduled for procurement in FY2009 and

FY2010.

FY2008 Defense Authorization Bill (H.R. 1585/S. 1547)

House

The House Armed Services Committee, in its report (H.Rept. 110-146 of May 11, 2007) on H.R.

1585, recommended approving the Navy’s FY2008 request for procurement funding in the

Shipbuilding and Conversion, Navy (SCN) appropriation account for the LPD-17 and LHA-6

programs, and also recommended adding $1,700 to the SCN account for the procurement of an

additional LPD-17. The report states:

The committee understands that a tenth [LPD-17 class] ship is the top priority on the Chief

of Naval Operations’ unfunded priority list. The committee recognizes that authorizing a

tenth ship of this class would allow the Marine Corps to more fully meet its requirement for

amphibious assault.

The committee recommends $1.4 billion for the [LPD-17 class] ship contained in the budget

request and recommends an increase of $1.7 billion, to include advance procurement, for the

construction of an additional San Antonio [i.e., LPD-17 class] class amphibious assault ship.

(Page 79)

According to the committee’s press release on its markup of H.R. 1585, the markup also

recommends an increase of $456 million for the procurement of an additional TAKE-1 class dry

cargo ship.63 Section 302 of the House-reported version of H.R. 1585 recommends authorizing a

total of $1,535.2 million for the National Defense Sealift Fund (NDSF)—an increase of $456

million over the requested amount. The NDSF is the part of the DOD budget in which TAKE-1

class ships are procured. The committee’s press release states:

The Committee understands that accelerating the construction of the T-AKE class of vessels

would more fully support the Maritime Prepositioning Force, Future (MPF(F)) concept and

63

House Armed Services Committee press release, “House Armed Services Committee Approves Fiscal Year 2008

Defense Authorization Bill,” May 9, 2007, p. 20.

Congressional Research Service

32

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

notes that acceleration of this ship class is the Chief of Naval Operations number two priority

on his Unfunded Priority List.64

Senate

The Senate Armed Services Committee, in its report (S.Rept. 110-77 of June 5, 2007) on S. 1547,

recommended approving the Navy’s FY2008 request for procurement funding in the Shipbuilding

and Conversion, Navy (SCN) appropriation account for the LPD-17 and LHA-6 programs.

Regarding planned numbers of amphibious ships and the option of procuring a tenth LPD-17

class ship, the report states:

The budget request for fiscal year 2008 included funding for the ninth ship of the USS San

Antonio (LPD-17) class amphibious ship program. The Secretary of the Navy’s 2007 report

to Congress on the long-range plan for construction of naval vessels calls for a “below

threshold” expeditionary warfare force. Specifically, the plan would reduce expeditionary

force size, including a reduction in the LPD-17 class from a total of 12 to 9 ships. The

committee is concerned that this plan does not provide the total number of amphibious ships

needed to support the Department of the Navy’s two Marine Expeditionary Brigade lift

requirements for forcible entry operations. In testimony before Congress in fiscal years 2005,

2006, and 2007, Marine Corps leadership stated that a class of 10 LPD-17 ships was required

to meet Marine Corps forcible entry requirements, with acceptable risk. The Chief of Naval

Operations has identified procurement of a tenth LPD-17 ship in 2008 as the Navy’s top

unfunded priority.

The committee is aware that construction for a tenth LPD-17 ship would not commence until

fiscal year 2009, but delaying procurement beyond 2009 would cause significant cost growth

and jeopardize industrial base stability by introducing production breaks in the program.

Therefore, the committee directs the Secretary of the Navy to submit a report not later than

November 1, 2007, that outlines the funding required for a “smart buy” of LPD-26,

maintaining continuous, uninterrupted production at critical vendors’ and shipbuilders’

facilities. (Page 134)

Regarding MPF(F) ships, particularly the LHA(R), and the National Defense Sealift Fund

(NDSF), the report states:

The fiscal year 2008 budget request included $96.6 million within the National Defense

Sealift Fund (NDSF) for various research and development activities, including $67.8

million for the Maritime Prepositioning Force (Future), MPF(F). This amount includes $4.9

million for amphibious assault replacement ships which are to be assigned to the MPF(F),

designated MPF(F) LHA(R).

The Navy’s concept for MPF(F) operations indicates that these ships will be multi-mission

vessels capable of afloat prepositioning, sea basing operations in support of amphibious

assault, and routine operations in support of lesser contingencies. MPF(F) ships are planned

to be operated by a Military Sealift Command crew. However, the MPF(F) concept of

operations differs sharply from current maritime prepositioning ships as a result of the

MPF(F) contribution to the Navy’s sea basing capability.

64

Ibid, p. 38.

Congressional Research Service

33

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

The MPF(F) role to embark and deploy marines ashore while sustaining expeditionary

warfare operations potentially exposes these ships and embarked marines to hostile fire. The

Navy plans to protect the MPF(F) ships through employment of the naval “sea shield,” and

therefore the Navy does not plan to outfit MPF(F) ships with self defense features. The

committee has expressed concern regarding the Navy’s MPF(F) survivability concept and, in

particular, the Navy’s proposal to eliminate the self defense features for the MPF(F)

LHA(R). The restoration of the ship’s combat system would allow the MPF(F) LHA(R) to

fill current shortfalls to the Navy’s forcible entry lift capability.

The committee is aware that the Department of the Navy is continuing to review the military

features for the MPF(F), and that the Navy expects to present the program plan to the Joint

Requirements Oversight Council (JROC) later in fiscal year 2007. Accordingly, the

committee directs the Secretary of Defense to submit a report to the congressional defense

committees within 30 days of the JROC MPF(F) decision outlining the findings of the

JROC. The report shall include a detailed vulnerability assessment of MPF(F) for major

combat operations.

The committee has been advised by the Navy that the Department of the Navy will need to

rephase into fiscal year 2009 certain MPF(F) research and development efforts. Therefore,

the committee recommends a decrease of $30.0 million for MPF(F) research and

development. Furthermore, the committee does not agree with funding development and

procurement for amphibious assault ships within the NDSF.

This ship type is specifically not included within the scope of sealift vessels eligible for

NDSF, defined within section 2218 of title 10, United States Code. Therefore, the committee

recommends a decrease of $4.9 million in PE 48042N, and a corresponding increase of $4.9

million in PE 64567N for MPF(F) LHA(R).

The committee recommends a total authorization of $32.9 million in PE 48042N for

MPF(F). (Page 429)

Conference

The conference report (H.Rept. 110-477 of December 6, 2007) on H.R. 1585 states:

The Senate report (S.Rept. 110-77) accompanying the National Defense Authorization Act

for Fiscal Year 2008 (S. 1547) contained direction for the Navy to maintain decommissioned

LHA—1 class amphibious assault ships in a reduced operating status until such time that the

active fleet could deliver 2.0 Marine Expeditionary Brigade forcible entry lift capability in

response to a national emergency. Total forcible lift entry capability was to be assessed under

the assumption that no less than 10 percent of the force will be unavailable due to extended

duration maintenance availabilities.

The conferees agree with the intent of this provision. The conferees understand that the

Navy’s preferred method of meeting this intent would be to retain decommissioned LHA-1

class amphibious assault ships in a mobilization category B status.

The conferees agree to direct the Navy to: (1) maintain these ships in mobilization category

B status until such time that the active fleet could deliver 2.0 Marine Expeditionary Brigade

forcible entry lift capability in response to a national emergency; and (2) assess total forcible

lift entry capability under the assumption that no less than 10 percent of the force will be

unavailable due to extended duration maintenance availabilities. (Pages 981-982)

Congressional Research Service

34

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

FY2008 Defense Appropriations Bill (H.R. 3222/P.L. 110-116)

House

The House Appropriations Committee, in its report (H.Rept. 110-279 of July 30, 2007) on H.R.

3222, recommended reducing by $7 million the Navy’s FY2008 SCN funding request for the

ninth LPD-17—the LPD-17 that the Navy requested for procurement in FY2008. Of the $7

million reduction, $5 million was for C4ISR equipment on the ship, and $2 million was for a

guided missile launch system on the ship. (Page 226)

The committee also recommended an additional $1,700 million in the SCN account for the

procurement of an additional (i.e., tenth) LPD-17. Taking into account the recommended $7

million reduction for the ninth LPD-17, the committee recommended a net increase of $1,693

million to the LPD-17 program for FY2008. (Page 226)

The committee’s report recommended reducing by $2 million the Navy’s FY2008 SCN funding

request for the LHA(R) program. The $2 million reduction is for the Cooperative Engagement

Capability (CEC) system on the ship. (Page 226)

The Administration’s budget requested $456.1 million in the National Defense Sealift Fund

(NDSF) for the procurement of a final “regular” TAKE-1 class cargo ship for use as a Navy

auxiliary. The committee’s report recommended $1,866.1 million NDSF for the procurement of

four TAKEs—an increase of $1,400 million and three ships over the requested amount. The

additional three TAKEs are to be for the MPF(F) squadron, which is to include three TAKEs.

(Page 390)

Regarding the LPD-17 and TAKE programs, the committee’s report stated that

the Committee believes that more stability can be gained in the shipbuilding program by

increasing the throughput of ships with proven design and construction processes. Therefore,

funding is being added to the request for an additional LPD-17 amphibious transport dock

ship, three additional T-AKE dry cargo/ammunition ships (which will buy out the

requirement for the Maritime Pre-positioned Force (Future)), and advance procurement for a

Virginia Class attack submarine. (Page 227)

Regarding the LPD-17 program, the report stated:

The request includes $1,398,922,000 for the procurement of the ninth San Antonio Class

(LPD-17) Amphibious Transport Dock Ship. This ship is the final LPD-17 class ship that the

Navy has in the budget. The Committee notes that the 313 ship fleet that the Navy has stated

as a goal requires ten San Antonio Class ships and that this tenth ship was the highest

priority listed on the Navy’s unfunded priority list. In an effort to achieve stability in the

Navy’s shipbuilding program by increasing throughput and helping the Navy meet its stated

requirement for LPD-17 Class ships, the Committee provides an additional $1,700,000,000

for the procurement of a tenth San Antonio Class Amphibious Transport Dock Ship. (Page

228)

Regarding the TAKE program, the report stated:

The Lewis and Clark Class of Dry Cargo/Ammunition Ships (T-AKE) will provide logistic

lift capability as a shuttle ship from supply sources to ships at sea. The request includes

Congressional Research Service

35

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

$456,110,000 for the acquisition of the eleventh Lewis and Clark Class T-AKE Dry

Cargo/Ammunition Ship. In an effort to provide stability to the Navy’s shipbuilding program

by increasing throughput, the Committee provides $1,866,110,000 for the procurement of 3

additional T-AKE ships, which is $1,410,000,000 above the request. In addition to providing

stability, this effort satisfies the second highest priority on the Navy’s unfunded priority list.

This increase will allow the Navy to buy out the T-AKE requirement for the Maritime Prepositioned Force (Future) while at the same time promoting stability to the construction yard

and sub-vendors and achieving volume efficiencies. (Page 390)

Senate

The Senate Appropriations Committee, in its report (S.Rept. 110-155 of September 14, 2007) on

H.R. 3222, recommended approving the Navy’s request for FY2008 procurement funding for the

LPD-17 and LHA-6 programs. The committee’s report states:

The Committee fully supports the CNO’s [Chief of Naval Operations’] goal of a 313 ship

Navy as a minimum requirement for the Nation. The Committee, however, has serious

concerns with the Navy’s ability to deliver on the current shipbuilding program of record.

The Navy’s track record for building ships on time and on budget has not been good. The

Government Accountability Office (GAO) has recently pointed out that the ships under

construction at the beginning of the current fiscal year have experienced cumulative cost

growth of almost $5,000,000,000 above their original budgets. Significant cost growth,

schedule delay, or both have occurred in the LPD-17 program, Littoral Combat Ship (LCS)

program, the T-AKE program, as well as the next-generation destroyer and aircraft carrier

programs. While supportive of additional funding for shipbuilding, the Committee is very

concerned that accelerating any of the current shipbuilding programs is unexecutable and

would have the effect of just “banking” funds.

Naval shipbuilding has been plagued with too frequent design changes, requirements creep,

poor cost estimating, and poor government performance in program management and

contractor oversight. Under staffing of critical government oversight functions has also been

a major problem for the Navy. The Committee believes that the acquisition changes

proposed by current Navy leadership is movement in the right direction, however, the

Committee would like to see some positive results in cost, schedule and performance of the

current program of record before supporting significant increases to the shipbuilding

account. (Page 133)

Conference

The conference report (H.Rept. 110-434 of November 6, 2007) on H.R. 3222/P.L. 110-116 of

November 13, 2007, reduced by $7 million the Navy’s FY2008 SCN funding request for the ninth

LPD-17—the LPD-17 that the Navy requested for procurement in FY2008. Of the $7 million

reduction, $5 million was for C4ISR equipment on the ship, and $2 million was for a guided

missile launch system on the ship.

The conference report also provided an additional $50 million in the SCN account for the

procurement in a future fiscal year of an additional (i.e., 10th) LPD-17. Taking into account the

$7-million reduction for the ninth LPD-17, the conference report provided a net increase of $43

million to the LPD-17 program for FY2008. (Page 189)

Congressional Research Service

36

Navy-Marine Corps Amphibious and Maritime Prepositioning Ship Programs

The conference report reduced by $2 million the Navy’s FY2008 SCN funding request for the

LHA(R) program. The $2 million reduction is for the Cooperative Engagement Capability (CEC)

system on the ship. (Page 189)

The Administration’s budget requested $456.1 million in the National Defense Sealift Fund

(NDSF) for the procurement of a final “regular” TAKE-1 class cargo ship for use as a Navy

auxiliary. The conference report approved this request and provided an additional $300 million in

funding “for advance procurement of long-lead time material and advance construction activities”

for three other TAKEs that the administration currently plans to procure in FY2009-FY2011.

These three other TAKEs are intended for the MPF(F) squadron. The conference report stated that

the $300 million in additional funding is “to support economic order quantity purchases of

materials in fiscal year 2008 that could yield additional savings and reduce pressure on the

outyear shipbuilding budget.” (Page 350)

Author Contact Information

Ronald O’Rourke

Specialist in Naval Affairs

[redacted]@crs.loc.gov, 7-....

Congressional Research Service

37

EveryCRSReport.com

The Congressional Research Service (CRS) is a federal legislative branch agency, housed inside the

Library of Congress, charged with providing the United States Congress non-partisan advice on

issues that may come before Congress.

EveryCRSReport.com republishes CRS reports that are available to all Congressional staff. The

reports are not classified, and Members of Congress routinely make individual reports available to

the public.

Prior to our republication, we redacted names, phone numbers and email addresses of analysts

who produced the reports. We also added this page to the report. We have not intentionally made

any other changes to any report published on EveryCRSReport.com.

CRS reports, as a work of the United States government, are not subject to copyright protection in

the United States. Any CRS report may be reproduced and distributed in its entirety without

permission from CRS. However, as a CRS report may include copyrighted images or material from a

third party, you may need to obtain permission of the copyright holder if you wish to copy or

otherwise use copyrighted material.

Information in a CRS report should not be relied upon for purposes other than public

understanding of information that has been provided by CRS to members of Congress in

connection with CRS' institutional role.

EveryCRSReport.com is not a government website and is not affiliated with CRS. We do not claim

copyright on any CRS report we have republished.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.