Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Congressional research reportDec 5, 2025

Ask Donna

What actually matters in this document.

Text

Navy DDG-51 and DDG-1000 Destroyer

Programs: Background and Issues for

Congress

Updated December 5, 2025

Congressional Research Service

https://crsreports.congress.gov

RL32109

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Summary

The Arleigh Burke (DDG-51) class destroyer program is one of the longest-running shipbuilding

programs in Navy history. The Navy began procuring DDG-51s, also known as Aegis destroyers,

in FY1985, and a total of 97 have been procured through FY2025, including three in FY2025.

From FY1989 through FY2005, DDG-51s were procured in annual quantities of two to five ships

per year. Since FY2010, they have been procured in annual quantities of one to three ships per

year. (The Navy did not procure any DDG-51s in FY2006-FY2009. Instead, the Navy in FY2007FY2009 procured three Zumwalt [DDG-1000] class destroyers. The Navy plans no further

procurement of DDG-1000s.)

As part of its FY2023 budget submission, the Navy requested authority for using a multiyear

procurement (MYP) contract for DDG-51s scheduled for procurement in FY2023-FY2027.

Congress, as part of its action on the Navy’s proposed FY2023 budget, approved this request.

Four previous MYP contracts for the DDG-51 program covered DDG-51s procured in FY1998FY2001, FY2002-FY2005, FY2013-FY2017, and FY2018-FY2022.

The first DDG-51 entered service in 1991, and a total of 75 have been delivered as of October 1,

2025. The DDG-51 design has been updated multiple times over the years; the version currently

being procured, called the Flight III DDG-51 design, incorporates a new and more capable radar

called the SPY-6 radar.

DDG-51s currently cost about $2.7 billion each when procured at a rate of two ships per year.

The Navy’s proposed FY2026 budget requests the procurement of two more DDG-51s in

FY2026, and estimates their combined procurement cost at $5,410.8 million (i.e., about $5.4

billion).

Congressional Research Service

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Contents

Introduction ..................................................................................................................................... 1

Background ..................................................................................................................................... 1

Navy’s Force of Large Surface Combatants (LSCs) ................................................................. 1

LSC Definition .................................................................................................................... 1

LSC Force as of End of FY2025......................................................................................... 1

LSC Force-Level Goal ........................................................................................................ 2

DDG-51 Program ...................................................................................................................... 2

Overview ............................................................................................................................. 2

Design Changes .................................................................................................................. 3

Multiyear Procurement (MYP) ........................................................................................... 4

Shipbuilders, Combat System Lead, and Radar Maker ...................................................... 5

Modernization of In-Service Ships ..................................................................................... 5

FY2026 Procurement Funding Request .............................................................................. 5

DDG-1000 Program .................................................................................................................. 5

Surface Combatant Construction Industrial Base ..................................................................... 7

Issues for Congress .......................................................................................................................... 7

Shipbuilding Industrial-Base Capacity and DDG-51 Procurement Rate .................................. 7

Cost, Technical, and Schedule Risk in Flight III DDG-51 Effort ............................................. 8

June 2025 GAO Report ....................................................................................................... 8

January 2025 DOT&E Report ............................................................................................ 9

Transition of Procurement from DDG-51s to DDG(X)s ......................................................... 12

Figures

Figure 1. DDG-51 Class Destroyer ................................................................................................. 3

Figure 2. DDG-51 Class Destroyer ................................................................................................. 4

Figure 3. DDG-51 Class Destroyer ................................................................................................. 5

Figure A-1. DDG-1000 Class Destroyer ....................................................................................... 13

Tables

Table A-1. Estimated Combined Procurement Cost of DDGs 1000, 1001, and 1002 ................... 18

Appendixes

Appendix. Additional Background Information on DDG-1000 Program ..................................... 13

Congressional Research Service

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Contacts

Author Information........................................................................................................................ 25

Congressional Research Service

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Introduction

This report presents background information and potential oversight issues for Congress on the

Navy’s Arleigh Burke (DDG-51) and Zumwalt (DDG-1000) class destroyer programs. The Navy

began procuring DDG-51s, also known as Aegis destroyers, in FY1985, and a total of 97 have

been procured through FY2025, including three in FY2025. The Navy’s proposed FY2026 budget

requests the procurement of two more DDG-51s in FY2026.

Potential issues for Congress for the DDG-51 program in FY2025 include the shipbuilding

industrial base’s capacity for building DDG-51s, the impact this could have on the DDG-51

procurement rate, and how the Navy proposes to transition several years from now from

procurement of DDG-51s to procurement of a successor destroyer design now in development

called the DDG(X). Decisions that Congress makes on these issues could substantially affect

Navy capabilities and funding requirements, and the U.S. shipbuilding industrial base.

For more on the DDG(X) program, see CRS In Focus IF11679, Navy DDG(X) Next-Generation

Destroyer Program: Background and Issues for Congress, by Ronald O'Rourke.

Background

Navy’s Force of Large Surface Combatants (LSCs)

LSC Definition

Decades ago, the Navy’s cruisers were considerably larger and more capable than its destroyers.

In the years after World War II, however, the Navy’s cruiser designs in general became smaller

while its destroyer designs in general became larger. As a result, since the 1980s there has been

substantial overlap in size and capability of Navy cruisers and destroyers. (The Navy’s new

Zumwalt [DDG-1000] class destroyers, in fact, are considerably larger than the Navy’s cruisers.)

In part for this reason, the Navy now refers to its cruisers and destroyers collectively as large

surface combatants (LSCs), and distinguishes these ships from the Navy’s small surface

combatants (SSCs), the term the Navy now uses to refer collectively to its frigates, Littoral

Combat Ships (LCSs), mine warfare ships, and patrol craft. The Navy’s annual 30-year

shipbuilding plan, for example, groups the Navy’s surface combatants into LSCs and SSCs.1

LSC Force as of End of FY2025

As of the end of FY2025, the Navy’s LSC force included 84 ships, including 7 Ticonderoga (CG47) class cruisers,2 75 DDG-51s, and two Zumwalt (DDG-1000) class destroyers.

1 The Navy sometimes also uses the term Cru-Des (an abbreviation of cruiser-destroyer, pronounced “crew-dez”) to

refer collectively to its cruisers and destroyers.

2 A total of 27 CG-47s (CGs 47 through 73) were procured for the Navy between FY1978 and FY1988; the ships

entered service between 1983 and 1994. The first five ships in the class (CGs 47 through 51), which were built to an

earlier technical standard in certain respects, were judged by the Navy to be too expensive to modernize and were

retired in 2004-2005, leaving 22 ships in operation (CGs 52 through 73). The Navy began retiring the remaining 22

ships in FY2022 and wants to retire all 22 by the end of FY2027.

Congressional Research Service

1

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

LSC Force-Level Goal

The Navy’s FY2025 30-year (FY2025-FY2054) shipbuilding plans calls for achieving a future

fleet of 381 manned battle force ships, including 87 LSCs. Prior to the 381-ship force-level goal

shown in the Navy’s FY2025 30-year shipbuilding plan, Navy plans called for achieving a future

fleet of 355 manned battle force ships, including 104 LSCs. Section 121 of the FY2021 National

Defense Authorization Act (H.R. 6395/P.L. 116-283 of January 1, 2021) states

SEC. 121. LIMITATION ON ALTERATION OF THE NAVY FLEET MIX.

(a) LIMITATION.—

(1) IN GENERAL.—The Secretary of the Navy may not deviate from the large surface

combatant requirements included in the 2016 Navy Force Structure Assessment until the

date on which the Secretary submits to the congressional defense committees the

certification under paragraph (2) and the report under subsection (b).

(2) CERTIFICATION.—The certification referred to in paragraph (1) is a certification, in

writing, that the Navy can mitigate the reduction in multi-mission large surface combatant

requirements, including anti-air and ballistic missile defense capabilities, due to having a

reduced number of DDG–51 Destroyers with the advanced AN/SPY–6 radar in the next

three decades.

(b) REPORT.—Not later than 90 days after the date of the enactment of this Act, the

Secretary of the Navy shall submit to the congressional defense committees a report that

includes—

(1) a description of likely detrimental impacts to the large surface combatant industrial

base, and a plan to mitigate such impacts, if the fiscal year 2021 future-years defense

program is implemented as proposed;

(2) a review of the benefits to the Navy fleet of the new AN/SPY–6 radar to be deployed

aboard Flight III variant DDG–51 Destroyers, which are currently under construction, as

well as an analysis of impacts to the warfighting capabilities of the fleet should the number

of such destroyers be reduced; and

(3) a plan to fully implement section 131 of the National Defense Authorization for Fiscal

Year 2020 (Public Law 116–92; 133 Stat. 1237), including subsystem prototyping efforts

and funding by fiscal year.

DDG-51 Program

Overview

The DDG-51 program was initiated in the late 1970s.3 It is one of the longest-running

shipbuilding programs in Navy history, and the DDG-51 class is one of the Navy’s numerically

largest classes of ships since World War II. The first DDG-51 was procured FY1985, and a total

of 97 have been procured through FY2025, including three in FY2025. From FY1989 through

FY2005, DDG-51s were procured in annual quantities of two to five ships per year. Since

FY2010, they have been procured in annual quantities of one to three ships per year. (The Navy

3 The program was initiated with the aim of developing a surface combatant to replace older destroyers and cruisers

that were projected to retire in the 1990s. The DDG-51 was conceived as an affordable complement to the Navy’s

Ticonderoga (CG-47) class Aegis cruisers. For an early discussion of the DDG-51 program, see Alva M. Bowen and

Ronald O’Rourke, “DDG-51 and the Future Surface Navy,” U.S. Naval Institute Proceedings, May 1985: 176-189.

Congressional Research Service

2

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

did not procure any DDG-51s in FY2006-FY2009. Instead, the Navy in FY2007-FY2009

procured three Zumwalt [DDG-1000] class destroyers, which are discussed later in this report.)

The first DDG-51 entered service in 1991, and a total of 75 have been delivered as of October 1,

2025. The remaining 22 DDG-51s are in various stages of construction. Earlier DDG-51s, known

as the Flight I/II DDG-51s, generally have an estimated service life (ESL) of 35 years, meaning

that retirement of these ships could begin in the late 2020s, although some Flight I/II DDG-51s

have been certified for a 40-year life. Additional Flight I/II DDG-51s might eventually receive

similar certifications, depending on their condition and Navy mission needs. Later DDG-51s,

known as the Flight IIA and Flight III DDG-51s, have an estimated service life of 40 years.

DDG-51s (Figure 1, Figure 2 and Figure 3) are multi-mission destroyers with an emphasis on

air defense (which the Navy refers to as anti-air warfare, or AAW) and blue-water (mid-ocean)

operations. DDG-51s, like the Navy’s Ticonderoga (CG-47) class cruisers, are equipped with the

Aegis combat system, an integrated ship combat system named for the mythological shield that

defended Zeus. CG-47s and DDG-51s consequently are often referred to as Aegis cruisers and

Aegis destroyers, respectively, or collectively as Aegis ships. The Aegis system has been updated

numerous times over the years. Many DDG-51s (and also some CG-47s) have a capability for

conducting ballistic missile defense (BMD) operations.4

Figure 1. DDG-51 Class Destroyer

Source: Cropped version of photograph at Huntington Ingalls Industries, “Delbert Black (DDG 119) Completes

Builder’s Trials,” February 26, 2020, accessed November 17, 2021, at https://newsroom.huntingtoningalls.com/

file/delbert-black-ddg119-builders-trials.

Design Changes

The DDG-51 design has been modified and updated periodically over the years. The first 28

DDG-51s (DDGs 51 through 78) are called Flight I/II DDG-51s. In FY1994, the Navy shifted

DDG-51 procurement to the Flight IIA DDG-51 design, which incorporated certain changes,

4 For more on Navy BMD programs, see CRS Report RL33745, Navy Aegis Ballistic Missile Defense (BMD) Program:

Background and Issues for Congress, by Ronald O'Rourke.

Congressional Research Service

3

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

including the addition of a helicopter hangar. A total of 47 Flight IIA DDG-51s (DDGs 79

through 124 and DDG-127) were procured in FY1994-FY2016. In FY2017, the Navy shifted

DDG-51 procurement to the current Flight III DDG-51 design, which incorporates a new and

more capable radar called the SPY-6 radar (previously known as the Air and Missile Defense

Radar, or AMDR), as well as associated changes to the ship’s electrical power and cooling

systems. DDGs 125 and higher, except for DDG-127 as noted above, are to be Flight III DDG51s.

Figure 2. DDG-51 Class Destroyer

Source: Cropped version of undated photograph of USS Jason Dunham (DDG-109) at “Bath Iron Works,”

accessed November 17, 2021, at https://www.gd.com/our-businesses/marine-systems/bath-iron-works.

Multiyear Procurement (MYP)

As part of its FY2023 budget submission, the Navy requested authority for using a multiyear

procurement (MYP) contract for DDG-51s scheduled for procurement in FY2023-FY2027.5

Congress, as part of its action on the Navy’s proposed FY2023 budget, approved this request.6

Four previous MYP contracts for the DDG-51 program covered DDG-51s procured in FY1998FY2001, FY2002-FY2005, FY2013-FY2017, and FY2018-FY2022.

5 For more on MYP contracting, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting

in Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke.

6 See Section 125 of the FY2023 National Defense Authorization Act (NDAA) (H.R. 7776/P.L. 117-263 of December

23, 2022) and Section 8010 of the FY2023 DOD Appropriations Act, (Division C of H.R. 2617/P.L. 117-328 of

December 29, 2022).

Congressional Research Service

4

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Figure 3. DDG-51 Class Destroyer

Source: Cropped version of photograph accompanying Oren Liebermann and Natasha Bertrand, “US Warship

Had Close Call with Houthi Missile in Red Sea,” CNN, February 1, 2024. The article credits the photograph to

Mass Communication Specialist 3rd Class Janae Chambers/U.S. Navy.

Shipbuilders, Combat System Lead, and Radar Maker

DDG-51s are built by General Dynamics/Bath Iron Works (GD/BIW) of Bath, ME, and

Huntington Ingalls Industries/Ingalls Shipbuilding (HII/Ingalls) of Pascagoula, MS. Lockheed is

the lead contractor for the Aegis system installed on all DDG-51s. The SPY-6—the primary radar

for the Aegis system on Flight III DDG-51s—is made by Raytheon.

Modernization of In-Service Ships

The Navy is modernizing existing DDG-51s (and a few CG-47s) so as to maintain their mission

and cost-effectiveness out to the end of their projected service lives. Older CRS reports provide

additional historical and background information on the DDG-51 program.7

FY2026 Procurement Funding Request

DDG-51s currently cost about $2.7 billion each when procured at a rate of two ships per year.

The Navy’s proposed FY2026 budget requests the procurement of two more DDG-51s in

FY2026, and estimates their combined procurement cost at $5,410.8 million (i.e., about $5.4

billion).

DDG-1000 Program

As noted earlier, in FY2007-FY2009, during the time when the Navy was not procuring DDG51s, the Navy instead procured three Zumwalt (DDG-1000) class destroyers. The Navy plans no

further procurement of DDG-1000s.

7 See CRS Report 94-343, Navy DDG-51 Destroyer Procurement Rate: Issues and Options for Congress, by Ronald

O’Rourke (April 25, 1994; out of print and available to congressional clients directly from the author), and CRS Report

80-205, The Navy’s Proposed Arleigh Burke (DDG-51) Class Guided Missile Destroyer Program: A Comparison with

an Equal-Cost Force Of Ticonderoga (CG-47) Class Guided Missile Destroyers, by Ronald O’Rourke (November 21,

1984; out of print and available to congressional clients directly from the author).

Congressional Research Service

5

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

DDG-1000s are multi-mission destroyers with an originally intended emphasis on naval surface

fire support (NSFS)8 and operations in littoral (i.e., near-shore) waters. Consistent with that

mission orientation, the ship was designed with two new-design 155mm guns called Advanced

Gun Systems (AGSs). The AGSs were to fire a new 155mm, gun-launched, rocket-assisted

guided projectile called the Long-Range Land-Attack Projectile (LRLAP, pronounced LUR-lap).

In November 2016, however, it was reported that the Navy had decided to stop procuring LRLAP

projectiles because the projected unit cost of each projectile had risen to at least $800,000.9

In December 2017, it was reported that, due to shifts in the international security environment and

resulting shifts in Navy mission needs, the mission orientation of the DDG-1000s would be

shifted from an emphasis on NSFS to an emphasis on surface strike, meaning the use of missiles

to attack surface ships and perhaps also land targets.10

To further optimize the three ships for conducting surface strike missions, the Navy plans to

remove one of the AGSs on each ship, along with its associated below-deck equipment, and

replace it with large-diameter vertical launch tubes capable of storing and firing the Navy’s new

hypersonic Conventional Prompt Strike (CPS) missile, with a goal of having the first CPSequipped DDG-1000 class ship ready for testing by the end of 2025.11 Each DDG-1000 class ship

reportedly is to be equipped with four of the large-diameter tubes, with each tube capable of

holding three CPS missiles, for a total of 12 CPS missiles per ship.12

The Navy reportedly also wants to replace some of the combat system equipment on the three

ships with equipment more similar to, and interoperable with, combat system equipment on other

8 NSFS is the use of naval guns to provide fire support for friendly forces operating ashore.

9 Christopher P. Cavas, “New Warship’s Big Guns Have No Bullets,” Defense News, November 6, 2016; Sam

LaGrone, “Navy Planning on Not Buying More LRLAP Rounds for Zumwalt Class,” USNI News, November 7, 2016;

Ben Guarino, “The Navy Called USS Zumwalt A Warship Batman Would Drive. But at $800,000 Per Round, Its

Ammo Is Too Pricey to Fire,” Washington Post, November 8, 2016.

10 Megan Eckstein, “New Requirements for DDG-1000 Focus on Surface Strike,” USNI News, December 4, 2017. See

also Richard Abott, “Navy Will Focus Zumwalt On Offensive Surface Strike,” Defense Daily, December 5, 2017;

David B. Larter, “The Navy’s Stealth Destroyers to Get New Weapons and a New Mission: Killing Ships,” Defense

News, February 15, 2018.

11 Rich Abott, “Zumwalt To Finish Hypersonic Weapon Tube Install By End Of 2025, DDG-1002 to Start Mod in

2026,” Defense Daily, January 16, 2025.

12 See, for example, Diana Stancy, “Time to Test a Ship-Based Hypersonic Missile Launcher,” Military Times,

December 31, 2023; Mallory Shelbourne, “Navy Planning for December 2025 Hypersonic Missile Test off USS

Zumwalt,” USNI News, February 1, 2023; Kyle Mizokami, “The Navy’s Stealth Destroyers Are Getting a Serious

Upgrade: 12 Hypersonic Missiles Each,” Popular Mechanics, December 1, 2022; Sam LaGrone, “Navy Details

Hypersonic Missile Plan for Zumwalt Destroyers, Virginia Submarines,” USNI News, November 3, 2022; Sam

LaGrone, “HII Set to Install First Hypersonic Missiles on USS Zumwalt, USS Michael Monsoor During Repair

Period,” USNI News, August 12, 2022; Sam LaGrone, “Latest Zumwalt Hypersonic Missile Installation Plan Calls For

Removing Gun Mounts,” USNI News, March 16, 2022; Joseph Trevithick, “The Navy’s Stealth Destroyers Will Have

Their Deck Guns Replaced With Hypersonic Missiles,” The Drive, November 2, 2021; Rich Abott, “Navy Plans to

Field 12 Hypersonic Missiles on Each Zumwalt Destroyer, Replacing Gun,” Defense Daily, June 8, 2021; Jason

Sherman, “Navy Plans to Pack Each DDG-1000 with 12 Long-Range Hypersonic Strike Missiles,” Inside Defense,

June 8, 2021; Jason Sherman, “Navy to Rip Out DDG-1000 Advanced Gun System Mounts to Make Room for

Hypersonic Weapons,” Inside Defense, May 26, 2021; Sam LaGrone, “CNO: Hypersonic Weapons at Sea to Premiere

on Zumwalt Destroyers in 2025,” USNI News, April 28, 2021; David B. Larter, “What Should Become of the Zumwalt

Class? The US Navy Has Some Big Ideas,” Defense News, March 25, 2021; Joseph Trevithick, “Navy Wants TriplePacked Hypersonic Missile Modules On Its Stealthy Zumwalt Destroyers,” The Drive, March 19, 2021; Paul McLeary,

“Exclusive[:] Eying China, CNO Plans Hypersonics & Lasers On Zumwalt Destroyers,” Breaking Defense, February

26, 2021. For more on the CPS program, see CRS Report R41464, Conventional Prompt Global Strike and LongRange Ballistic Missiles: Background and Issues, by Amy F. Woolf.

Congressional Research Service

6

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

U.S. Navy surface combatants. The Navy refers to this as the Zumwalt Enterprise Upgrade

Solution (ZEUS).13

For additional background information on the DDG-1000 program, see the Appendix.

Surface Combatant Construction Industrial Base

All cruisers and destroyers procured since FY1985 have been built at GD/BIW and HII/Ingalls.

Both of these shipyards have long histories of building larger surface combatants. Construction of

Navy surface combatants in recent years has accounted for virtually all of GD/BIW’s shipconstruction work and for a significant share of HII/Ingalls’ ship-construction work. (HII/Ingalls

also builds amphibious ships for the Navy and cutters for the Coast Guard.) Navy surface

combatants are overhauled, repaired, and modernized at GD/BIW, HII/Ingalls, and other U.S.

shipyards.

Lockheed Martin and Raytheon are generally considered the two leading Navy surface combatant

radar makers and combat system integrators. Lockheed is the lead contractor for the DDG-51

combat system (the Aegis system), while Raytheon is the lead contractor for the DDG-1000

combat system, the core of which is called the Total Ship Computing Environment Infrastructure

(TSCE-I). Lockheed has a share of the DDG-1000 combat system, and Raytheon has a share of

the DDG-51 combat system. Lockheed, Raytheon, and Northrop competed to be the maker of the

SPY-6 radar to be carried by the Flight III DDG-51. On October 10, 2013, the Navy announced

that it had selected Raytheon to be the maker of the SPY-6.

The surface combatant construction industrial base also includes hundreds of additional firms that

supply materials and components. Several Navy-operated laboratories and other facilities support

the Aegis system and other aspects of the DDG-51 and DDG-1000 programs.

Issues for Congress

Shipbuilding Industrial-Base Capacity and DDG-51 Procurement

Rate

One issue for Congress concerns the shipbuilding industrial base’s capacity for building DDG51s, and the impact this could have on the DDG-51 procurement rate, specifically on the question

of whether to procure two or three DDG-51s per year. Although DDG-51s have been procured at

annual rates of two or three ships per year since FY2016, deliveries of DDG-51s have averaged

less than two ship per year,14 resulting in an increasing backlog of ships that have been procured

but not completed. A January 2025 Congressional Budget Office (CBO) report on the Navy’s

FY2025 30-year shipbuilding plan states that “according to CBO’s analysis of the Navy’s budget

documents, delays in the DDG-51 class destroyers have grown by 18 months over the past two

years. From a broader perspective, whereas the shipbuilding industry took 5 to 6 years to build

13 See, for example, Kyle Mizokami, “The Navy’s Stealth Destroyers Are Getting a Serious Upgrade: 12 Hypersonic

Missiles Each,” Popular Mechanics, December 1, 2022; Mallory Shelbourne, “Navy Exploring ‘Surface Strike’

Upgrades for Zumwalt Destroyers,” USNI News, November 28, 2022; Justin Katz, “Navy Eyeing ‘ZEUS,’ an Upgrade

Program for the Zumwalt Destroyers,” Breaking Defense, November 22, 2022.

14 Source: Navy information paper on DDG shipbuilding delivery rates, October 1, 2025, provided by navy Office of

Legislative Affairs to CRS and CBO on November 25, 2025.

Congressional Research Service

7

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

destroyers and submarines in the 2000s, under current schedules, the shipyards now need 8 to 9

years, on average, to build those ships.”15

Cost, Technical, and Schedule Risk in Flight III DDG-51 Effort

Another issue for Congress concerns cost, technical, and schedule risk for the Flight III DDG-51.

June 2025 GAO Report

A June 2025 Government Accountability Office (GAO) report—the 2025 edition of GAO’s

annual report surveying DOD major acquisition programs—stated the following in its assessment

of the Flight III DDG-51:

Current Status

Since last year’s assessment, persistent shipyard performance issues contributed to

additional schedule growth. The DDG 51 program office stated that both shipbuilders have

made progress but continue to struggle to meet hiring, training, and retention targets needed

to stabilize construction schedules. The schedule instability led to additional delivery

delays since our last assessment for each of the first 13 follow-on ships. The delivery delays

for these ships now range from 8 to 41 months compared with the contract dates provided

by the program. These delays undermine Navy efforts to provide timely new capability to

counter current and future air and surface threats.

The program office said that it assessed shipyard capacity and workload prior to its 2023

construction contract awards and conducted studies to understand the shipyards’

challenges. To address the challenges, the program office said that it is using funding

received above the program’s request to support shipbuilder infrastructure projects and the

supplier base for the program. Further, the program office stated that it is using workforce

development contract incentives to help DDG 51 shipbuilders improve their facilities,

employee training, and retention and recruitment.

Since our last assessment, the program also delayed the planned start of initial operational

test and evaluation by at least 18 months. The program office stated that it added two

developmental test periods—one completed in 2024—to reduce overall risk to the initial

capability. The revised schedule maintains the program’s plan to complete testing in 2027.

However, the changes to the operational testing approach delay the Navy’s achievement of

initial operational capability by roughly 3 years as compared to previous plans. The

program office deemed the initial operational capability date as not suitable for public

release.

Program Office Comments

We provided a draft of this assessment for program office review. The DDG 51 program

office provided technical comments, which we incorporated where appropriate. The

program office stated that it has delivered 74 ships as one of the Navy’s longest-running

production lines, with 25 new ships under contract and in various stages of production or

pre-construction. The program office added that the first Flight III ship, DDG 125,

continues to make progress in achieving the Navy’s objective to deliver a fully tested and

certified integrated air and missile defense-capable ship in fiscal year 2027.16

Regarding the SPY-6 (AMDR) radar specifically, the report stated the following:

15 Congressional Budget Office, An Analysis of the Navy’s 2025 Shipbuilding Plan, January 2025, p. 23.

16 Government Accountability Office, Weapon Systems Annual Assessment[:] DOD Leaders Should Ensure That

Newer Programs Are Structured for Speed and Innovation, GAO-25-107569, June 2025, p. 123.

Congressional Research Service

8

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Current Status

Due to shipbuilding delays, radar production continues to outpace ship production of DDG

51 Flight III and other ships. This production mismatch has required the Navy to store

some delivered radars as the AMDR program waits for ships to become available for

installation. To mitigate the costs of storage, AMDR officials stated, the program is

establishing a government secure storage facility. Additionally, AMDR program officials

told us that it remains cost effective and efficient to maintain continuous production of the

AMDR family of radars to complete and deliver equipment at a predictable pace.

Program officials reported that the first radar variant is currently in development testing

and that deficiencies found under certain testing conditions for the inverter modules have

been addressed and modules in production are being delivered with the updates. However,

program officials told us that they conducted a root cause analysis and software fixes and

are addressing integration issues with the radar to support upcoming test events. The

program received its first software to address this risk in spring 2024.

Last year the program reported the initial capability date as August 2024. However,

program officials explained that the AMDR program adjusted this date to September 2027

to align with the DDG 51 Flight III initial operational testing plan and fleet needs. The

Navy does not plan to certify radars until fiscal year 2026. We previously reported on the

potential for discovery of additional deficiencies during ongoing testing that could result

in costly, time-intensive revisions, particularly if rework is required for installed radars.

Program officials acknowledged this risk, and the Navy continues to try to mitigate these

issues.

Program Office Comments

We provided a draft of this assessment to the program office for review and comment. It

stated that it is on track to support combat systems for all variants, and that the secure

storage facility’s first intake is scheduled for April 2025. It noted that new builds of radar

and combat system software for continuing DDG 125 at-sea testing match those planned

for operational testing. In April 2025, the office of DOD’s Director, Operational Test and

Evaluation provided comments stating that AMDR’s operational testing date should be

reflected as the fourth quarter of fiscal year 2029. The Navy’s comments did not provide a

revision to this date.17

January 2025 DOT&E Report

A January 2025 report from DOD’s Director, Operational Test and Evaluation (DOT&E)—

DOT&E’s annual report for FY2024—stated the following regarding the DDG-51 Flight III

destroyer:

TEST ADEQUACY

In March 2024, USS Jack H. Lucas (DDG 125) participated in FTM-32, an integrated test

to demonstrate the capability to detect, track, engage, and intercept a medium-range

ballistic missile target utilizing a simulated Standard Missile-6 (SM-6). This event is

detailed in the classified DOT&E FY24 Missile Defense System Annual Assessment, that

will be published in 2QFY25. Significant intended data collection on DDG 51 Flight III’s

performance were not attained during test execution due to challenges with the ship’s ACS

[Aegis Combat System) and AN/SPY-6(V)1 during test execution. As a result, insufficient

data are available to assess DDG 51 Flight III operational effectiveness from this flight

test.

17 Government Accountability Office, Weapon Systems Annual Assessment[:] DOD Leaders Should Ensure That

Newer Programs Are Structured for Speed and Innovation, GAO-25-107569, June 2025, p. 118.

Congressional Research Service

9

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Evaluation of DDG 51 Flight III capability to defeat incoming threat anti-ship cruise

missiles is constrained by available aerial test targets, or threat surrogates, that do not fully

emulate the most stressing threats. Aerial targets provide demonstration of warship

capability in the represented scenario and provide validation data to accredit M&S and

estimate capability beyond the limited live test scenarios.

In October 2023, the Navy commenced blast fragility testing at Aberdeen Proving Ground

in Aberdeen, Maryland. Testing was completed in accordance with the DOT&E-approved

test plan and observed by DOT&E. The first series of tests evaluated the blast resistance

of representative electrical equipment and provided data to set equipment fragility

thresholds within survivability M&S [modeling and simulation]. The Navy expects the

second series of test to evaluate the blast resistance of Navy Standard doors and hatches to

complete in FY25 and enable the setting of their thresholds with survivability M&S.

PERFORMANCE

EFFECTIVENESS, SUITABILITY, AND SURVIVABILITY

No data are available to determine DDG 51 Flight III operational effectiveness, suitability,

and survivability. DOT&E will report on the operational effectiveness, suitability, and

survivability of DDG 51 Flight III after IOT&E [Initial Operational Test and Evaluation]

and LFT&E [Live Fire Test and Evaluation] are complete, currently expected by the Navy

to be FY28.

RECOMMENDATIONS

The Navy should:

1. Fund development and procure aerial anti-ship cruise missile targets that emulate

advanced and stressing threat ASCMs [anti-ship cruise missiles].

2. Determine and correct issues that limited evaluation of DDG 51 Flight III performance

in FTM-32.18

Regarding the SPY-6 (AMDR) radar specifically, the report stated the following:

TEST ADEQUACY

In March 2024, DOT&E published a classified AMDR / AN/SPY-6(V)1 OA report.

OPTEVFOR conducted the OA of AN/SPY-6(V)1 in FY23 at the ARDEL on PMRF, in

Kauai, Hawaii, as detailed in the FY23 Annual Report. The OA evaluated capability of

AN/SPY-6(V)1 to detect and track fighter aircraft, anti-ship cruise missile surrogates,

unmanned aerial vehicles, helicopters, airborne early warning and control aircraft, and

small-boat targets. The OA provided early evaluation of the AN/SPY-6(V)1 radar

performance in its AW and surface warfare missions in clear and electromagnetic contested

environments and demonstrated the Navy’s test method for assessing AN/SPY-6(V)1’s

classified electromagnetic protection waveforms. The OA additionally informed planning

of IOT&E test events. The OA was not intended to determine operational effectiveness and

suitability of the delivered AMDR due to the AN/SPY-6(V)1 at ARDEL being an

engineering development model (EDM) that uses obsolete T/R Integrated Microwave

Modules that will not be used by the delivered system. The AMDR Program Office did not

evaluate cyber survivability due to differences between the delivered AMDR and the EDM

version of AMDR at ARDEL.

In March 2024, the MDA, in collaboration with OPTEVFOR, conducted the Flight Test

Aegis Weapon System (FTM-32) as an integrated test to demonstrate the capability to

detect, track, engage, and intercept a medium-range ballistic missile target utilizing a

simulated Standard Missile-6 (SM-6). USS Jack H. Lucas (DDG 125), equipped with AWS

18 Director, Operational Test & Evaluation, FY 2024 Annual Report, January 2025, pp. 222-223.

Congressional Research Service

10

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Baseline 10 and AN/SPY-6(V)1 radar, participated in FTM-32 as part of IOT&E.

Significant intended data collection on AN/SPY-6(V)1 performance was not attained due

to system challenges during test execution. As a result, insufficient data are available to

assess AMDR operational effectiveness from this flight test. This event is detailed in the

classified DOT&E FY24 Missile Defense System Annual Assessment, to be published in

February 2025.

As identified in the FY23 Annual Report and the AN/SPY-6(V)1 OA Report, assessment

of the resident AN/SPY-6(V)1 at ARDEL was limited by the following:

• AMDR EDM was not operationally representative. The AMDR program plans to install

a low-rate initial production (LRIP) AMDR unit in FY26.

• The current aerial anti-ship cruise missile targets do not emulate more stressing threats,

including advanced electromagnetic attack capabilities.

• System setup and software configuration of the AMDR EDM could not evaluate

performance of all capabilities that are prohibited from testing in an open-air environment

due to security reasons. An anechoic chamber would provide the ability to test these

capabilities.

PERFORMANCE

EFFECTIVENESS

The AN/SPY-6(V)1 OA demonstrated radar performance in a limited set of scenarios.

DOT&E provided performance results and risks to IOT&E in the classified AN/SPY-6(V)1

OA report in March 2024.

AMDR performance cannot be fully evaluated from the flight test event, FTM-32, due to

unavailable data resulting from system challenges during test execution. DOT&E will

report on operational effectiveness of AMDR after OT&E completes, currently expected

by the Navy to be FY28.

SUITABILITY AND SURVIVABILITY

No observations on suitability and survivability can be made due to differences in the

AMDR EDM used in the OA to the AMDR being delivered to the fleet. The flight test

event, FTM-32, identified concerns that could degrade AMDR reliability if not addressed.

DOT&E will report on operational suitability and survivability of AMDR after IOT&E that

the Navy expects to complete in FY28.

RECOMMENDATIONS

The Navy should:

1. As stated in the FY23 DOT&E Annual Report and the AN/SPY-6(V)1 OA Report,

replace the radar system at ARDEL with a production-representative AN/SPY-6(V)1 in

FY26 to enable use in integrated and operational test of capabilities.

2. Develop an AN/SPY-6 test environment, such as an anechoic chamber, to effectively

assess critical AN/SPY-6 capabilities that are restricted from evaluation in open-air test

environments.

3. Evaluate AN/SPY-6(V)1 during large fleet exercises that provide representative

complex electromagnetic spectrum environments.

4. Fund development and procure aerial anti-ship cruise missile targets that emulate

modern and stressing threats, including advanced electromagnetic attack, to support

AMDR IOT&E.

Congressional Research Service

11

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

5. Continue to develop and submit the combined AN/SPY-6(V)2, AN/SPY-6(V)3, and the

Ship Self-Defense System Baseline 12 Combat System TEMP for DOT&E approval in

FY25.19

Transition of Procurement from DDG-51s to DDG(X)s

Another issue for Congress concerns how the Navy proposes to transition several years from now

from procurement of DDG-51s to procurement of a successor destroyer design now in

development called the DDG(X). Navy plans for transitioning from procurement of DDG-51s to

procurement of DDG(X)s have been an oversight focus for the defense committees. DON’s

prepared statement for the April 26, 2022, hearing on DON investment programs before the

Seapower subcommittee of the Senate Armed Services Committee states

The Navy is committed to a smooth and successful transition from DDG 51 to DDG(X)

starting around FY 2030.20 The transition will preserve the critical shipbuilding and

supplier industrial base by executing a collaborative design process with current DDG 51

shipyards and transitioning to a proven limited competition model between these shipyards

at the right point in ship construction.21

A January 10, 2024, press report states

The Navy is looking for a three-year overlap between the start of construction on its nextgeneration guided-missile destroyer DDG(X) and its current crop of Flight III Arleigh

Burke DDGs, the director of Navy surface warfare told USNI News on Wednesday

[January 10]….

The service is keen on feathering in the DDG(X) to create a smooth transition at the yards

from the Flight IIIs.

“The answer is three years to make sure we do no harm to our shipbuilding industry,

whether it’s Bath Iron Works or [Ingalls],” Pyle said.22

For more on the DDG(X) program, see CRS In Focus IF11679, Navy DDG(X) Next-Generation

Destroyer Program: Background and Issues for Congress, by Ronald O'Rourke.

19 Director, Operational Test & Evaluation, FY 2024 Annual Report, January 2025, pp. 191-192.

20 Under the Navy’s proposed FY2024 budget, procurement of the first DDG(X) has been deferred from FY2030 to

FY2032.

21 Statement of Frederick J. Stefany, Principal Civilian Deputy, Assistant Secretary of the Navy (Research,

Development and Acquisition), Performing the Duties of the Assistant Secretary of the Navy (Research, Development

and Acquisition), and Vice Admiral Scott Conn, Deputy Chief of Naval Operations, Warfighting Requirements and

Capabilities (OPNAV N9), and Lieutenant General Karsten S. Heckl, Deputy Commandant, Combat Development and

Integration, Commanding General, Marine Corps Combat Development Command, before the Subcommittee on

Seapower of the Senate Armed Services Committee on Department of the Navy Fiscal Year 2023 Budget Request for

Seapower, April 26, 2022, PDF page 10 of 37.

22 Sam LaGrone, “Navy Wants 3-Year Overlap Between Arleigh Burkes and DDG(X), Considering Propulsion

System,” USNI News, January 10, 2024.

Congressional Research Service

12

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Appendix. Additional Background Information on

DDG-1000 Program

This appendix presents additional background information on the DDG-1000 program.

Overview

The DDG-1000 program was initiated in the early 1990s.23 DDG-1000s (Figure A-1) are multimission destroyers with an originally intended emphasis on naval surface fire support (NSFS) and

operations in littoral (i.e., near-shore) waters. (NSFS is the use of naval guns to provide fire

support for friendly forces operating ashore.)

Figure A-1. DDG-1000 Class Destroyer

Source: U.S. Navy photo 151207-N-ZZ999-435, posted December 8, 2015, with a caption that reads in part:

“The future USS Zumwalt (DDG 1000) is underway for the first time conducting at-sea tests and trials in the

Atlantic Ocean Dec. 7, 2015.”

DDG-1000s were originally intended to replace, in a technologically more modern form, the

large-caliber naval gun fire capability that the Navy lost when it retired its Iowa-class battleships

in the early 1990s,24 to improve the Navy’s general capabilities for operating in defended littoral

waters, and to introduce several new technologies that would be available for use on future Navy

23 The program was originally designated DD-21, which meant destroyer for the 21st century. In November 2001, the

program was restructured and renamed DD(X), meaning a destroyer whose design was in development. In April 2006,

the program’s name was changed again, to DDG-1000, meaning a guided missile destroyer with the hull number 1000.

24 The Navy in the 1980s reactivated and modernized four Iowa (BB-61) class battleships that were originally built

during World War II. The ships reentered service between 1982 and 1988 and were removed from service between

1990 and 1992.

Congressional Research Service

13

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

ships. The DDG-1000 was also intended to serve as the basis for a planned cruiser called CG(X)

that was subsequently canceled.25

DDG-1000s are to have reduced-size crews of 175 sailors (147 to operate the ship, plus a 28person aviation detachment), compared to roughly 300 on the Navy’s Aegis destroyers and

cruisers, so as to reduce its operating and support (O&S) costs. The DDG-1000 design

incorporates a significant number of new technologies, including an integrated electric-drive

propulsion system26 and automation technologies enabling its reduced-sized crew.

With an estimated full load displacement of 15,656 tons, the DDG-1000 design is substantially

larger than the Navy’s Aegis cruisers and destroyers, which have displacements of up to about

9,700 tons, and are larger than any Navy destroyer or cruiser since the nuclear-powered cruiser

Long Beach (CGN-9), which was procured in FY1957.

The first two DDG-1000s were procured in FY2007 and split-funded (i.e., funded with two-year

incremental funding) in FY2007-FY2008; the Navy’s FY2024 budget submission estimates their

combined procurement cost at $9,450.8 million. The third DDG-1000 was procured in FY2009

and split-funded in FY2009-FY2010; the Navy’s FY2024 budget submission estimates its

procurement cost at $4,342.4 million.

The first DDG-1000 was commissioned into service on September 7, 2016. Its delivery date was

revised multiple times and reportedly was April 2020.27 This created an unusual situation in

which a ship was commissioned into service more than three years prior to its delivery date. The

delivery dates for the second and third ships have also been revised multiple times.28 In the

Navy’s FY2024 budget submission, the delivery dates for the two ships are listed as October 2023

and December 2026, respectively.

Program Origin

The program known today as the DDG-1000 program was announced on November 1, 2001,

when the Navy stated that it was replacing a destroyer-development effort called the DD-21

program, which the Navy had initiated in the mid-1990s, with a new Future Surface Combatant

Program aimed at developing and acquiring a family of three new classes of surface

combatants:29

25 For more on the CG(X) program, see CRS Report RL34179, Navy CG(X) Cruiser Program: Background for

Congress, by Ronald O'Rourke.

26 For more on integrated electric-drive technology, see CRS Report RL30622, Electric-Drive Propulsion for U.S. Navy

Ships: Background and Issues for Congress, by Ronald O'Rourke.

27 See Aidan Quigley, “Final Delivery of Zumwalt-class Destroyer Monsoor Delayed,” Inside Defense, January 21,

2021.

28 The revised delivery dates for the three ships reflect Section 121 of the FY2017 National Defense Authorization Act

(S. 2943/P.L. 114-328 of December 23, 2016), a provision that establishes standards for determining vessel delivery

dates and which also required the Secretary of the Navy to certify that the delivery dates for certain ships, including the

three DDG-1000s, had been adjusted in accordance with the provision. The Navy’s original plan for the DDG-1000

program was to install certain elements of each DDG-1000’s combat system after delivering the ship and

commissioning it into service. Section 121 of P.L. 114-328 in effect requires the Navy to defer the delivery date of a

DDG-1000 until those elements of the combat system are installed. By the time P.L. 114-328 was enacted, DDG-1000,

per the Navy’s original plan, had already been commissioned into service without those elements of its combat system.

29 The DD-21 program was part of a Navy surface combatant acquisition effort begun in the mid-1990s and called the

SC-21 (Surface Combatant for the 21st Century) program. The SC-21 program envisaged a new destroyer called DD-21

and a new cruiser called CG-21. When the Navy announced the Future Surface Combatant Program in 2001,

development work on the DD-21 had been underway for several years, while the start of development work on the CG(continued...)

Congressional Research Service

14

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

•

•

•

a destroyer called DD(X) for the precision long-range strike and naval gunfire

mission;

a cruiser called CG(X) for the air defense and ballistic missile mission; and

a smaller combatant called the Littoral Combat Ship (LCS) to counter

submarines, small surface attack craft (also called “swarm boats”), and mines in

heavily contested littoral (near-shore) areas.30

On April 7, 2006, the Navy announced that it had redesignated the DD(X) program as the DDG1000 program. The Navy also confirmed in that announcement that the first ship in the class,

DDG-1000, would be named Zumwalt, in honor of Admiral Elmo R. Zumwalt, the Chief of Naval

operations from 1970 to 1974. The decision to name the first ship after Zumwalt was made by the

Clinton Administration in July 2000, when the program was still called the DD-21 program.31

New Technologies

The DDG-1000 incorporates a significant number of new technologies, including a wavepiercing, tumblehome hull design for reduced detectability,32 a superstructure on the first two

ships (but not the third) that is made partly of large sections of composite (i.e., fiberglass-like)

materials rather than steel or aluminum, an integrated electric-drive propulsion system,33 a totalship computing system for moving information about the ship, automation technologies enabling

its reduced-sized crew, a dual-band radar (that was later changed to a single-band radar), a new

kind of vertical launch system (VLS) for storing and firing missiles, and two copies of a new

155mm gun called the Advanced Gun System (AGS).

Shipbuilders and Combat System Prime Contractor

GD/BIW is the builder for all three DDG-1000s, with some portions of each ship being built by

HII/Ingalls for delivery to GD/BIW. Raytheon is the prime contractor for the DDG-1000’s

combat system (its collection of sensors, computers, related software, displays, and weapon

launchers).

Under a DDG-1000 acquisition strategy approved by the Under Secretary of Defense for

Acquisition, Technology, and Logistics (USD AT&L) on February 24, 2004, the first DDG-1000

was to have been built by HII/Ingalls, the second ship was to have been built by GD/BIW, and

contracts for building the first six were to have been equally divided between HII/Ingalls34 and

GD/BIW.

21 was still years in the future. The current DDG-1000 destroyer CG(X) cruiser programs can be viewed as the

descendants, respectively, of the DD-21 and CG-21. The acronym SC-21 is still used in the Navy’s research and

development account to designate the line item (i.e., program element) that funds development work on both the DDG1000 and CG(X).

30 For more on the LCS program, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background

and Issues for Congress, by Ronald O'Rourke.

31 For more on Navy ship names, see CRS Report RS22478, Navy Ship Names: Background for Congress, by Ronald

O'Rourke.

32 A tumblehome hull slopes inward, toward the ship’s centerline, as it rises up from the waterline, in contrast to a

conventional flared hull, which slopes outward as it rises up from the waterline.

33 For more on integrated electric-drive technology, see CRS Report RL30622, Electric-Drive Propulsion for U.S. Navy

Ships: Background and Issues for Congress, by Ronald O'Rourke.

34 At the time of the events described in this section, HII was owned by Northrop Grumman and was called Northrop

Grumman Shipbuilding (NGSB).

Congressional Research Service

15

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

In February 2005, Navy officials announced that they would seek approval from USD AT&L to

instead hold a one-time, winner-take-all competition between HII/Ingalls and GD/BIW to build

all DDG-1000s. On April 20, 2005, the USD AT&L issued a decision memorandum deferring this

proposal, stating in part, “at this time, I consider it premature to change the shipbuilder portion of

the acquisition strategy which I approved on February 24, 2004.”

Several Members of Congress also expressed opposition to the Navy’s proposal for a winnertake-all competition. Congress included a provision (§1019) in the Emergency Supplemental

Appropriations Act for 2005 (H.R. 1268/P.L. 109-13 of May 11, 2005) prohibiting a winner-takeall competition. The provision effectively required the participation of at least one additional

shipyard in the program but did not specify the share of the program that is to go to the additional

shipyard.

On May 25, 2005, the Navy announced that, in light of Section 1019 of P.L. 109-13, it wanted to

shift to a “dual-lead-ship” acquisition strategy, under which two DDG-1000s would be procured

in FY2007, with one to be designed and built by HII/Ingalls and the other by GD/BIW.

Section 125 of the FY2006 defense authorization act (H.R. 1815/P.L. 109-163) again prohibited

the Navy from using a winner-take-all acquisition strategy for procuring its next-generation

destroyer. The provision again effectively requires the participation of at least one additional

shipyard in the program but does not specify the share of the program that is to go to the

additional shipyard.

On November 23, 2005, the USD AT&L granted Milestone B approval for the DDG-1000,

permitting the program to enter the System Development and Demonstration (SDD) phase. As

part of this decision, the USD AT&L approved the Navy’s proposed dual-lead-ship acquisition

strategy and a low rate initial production quantity of eight ships (one more than the Navy

subsequently planned to procure).

On February 14, 2008, the Navy awarded contract modifications to GD/BIW and HII/Ingalls for

the construction of the two lead ships. The awards were modifications to existing contracts that

the Navy has with GD/BIW and HII/Ingalls for detailed design and construction of the two lead

ships. Under the modified contracts, the line item for the construction of the dual lead ships is

treated as a cost plus incentive fee (CPIF) item.

Until July 2007, it was expected that HII/Ingalls would be the final-assembly yard for the first

DDG-1000 and that GD/BIW would be the final-assembly yard for the second. On September 25,

2007, the Navy announced that it had decided to build the first DDG-1000 at GD/BIW, and the

second at HII/Ingalls.

On January 12, 2009, it was reported that the Navy, HII/Ingalls, and GD/BIW in the fall of 2008

began holding discussions on the idea of having GD/BIW build both the first and second DDG1000s, in exchange for HII/Ingalls receiving a greater share of the new DDG-51s that would be

procured under the Navy’s July 2008 proposal to stop DDG-1000 procurement and restart DDG51 procurement.35

On April 8, 2009, it was reported that the Navy had reached an agreement with HII/Ingalls and

GD/BIW to shift the second DDG-1000 to GD/BIW, and to have GD/BIW build all three ships.

HII/Iingalls will continue to make certain parts of the three ships, notably their composite

deckhouses. The agreement to have all three DDG-1000s built at GD/BIW was a condition that

Secretary of Defense Robert Gates set forth in an April 6, 2009, news conference on the FY2010

35 Christopher P. Cavas, “Will Bath Build Second DDG 1000?” Defense News, January 12, 2009: 1, 6.

Congressional Research Service

16

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

defense budget for his support for continuing with the construction of all three DDG-1000s

(rather than proposing the cancellation of the second and third).

Reduction in Procurement to Three Ships

Navy plans for many years called for ending DDG-51 procurement in FY2005, to be followed by

procurement of up to 32 DDG-1000s and some number of CG(X)s. In subsequent years, the

planned total number of DDG-1000s was reduced to 16 to 24, then to 7, and finally to 3.

At the end of July 2008, in a major reversal of its destroyer procurement plans, the Navy

announced that it wanted to end procurement of DDG-1000s and resume procurement of DDG51s. In explaining this reversal, which came after two DDG-1000s had been procured, the Navy

stated that it had reevaluated the future operating environment and determined that its destroyer

procurement now needed to emphasize three missions: open-ocean antisubmarine warfare

(ASW), countering anti-ship cruise missiles (ASCMs), and countering ballistic missiles. Although

the DDG-1000 could perform the first two of these missions and could be modified to perform

the third, the Navy concluded that the DDG-51 design could perform these three missions

adequately and would be less expensive to procure than the DDG-1000 design.

The Navy’s proposal to stop procuring DDG-1000s and resume procuring DDG-51s was

presented in the Navy’s proposed FY2010 budget, which was submitted to Congress in 2009.

Congress, in acting on the Navy’s FY2010 budget, approved the idea of ending DDG-1000

procurement and restarting DDG-51 procurement, and procured a third DDG-1000 as the final

ship in the class.

In retrospect, the Navy’s 2008 reversal in its destroyer procurement plans can be viewed as an

early indication of the ending of the post-Cold War era (during which the Navy focused its

planning on operating in littoral waters against the land- and sea-based forces of countries such as

Iran and North Korea) and the shift in the international security environment to renewed great

power competition (during which the Navy is now focusing its planning more on being able to

operate in mid-ocean waters against capable naval forces from near-peer competitors such as

China and Russia).36

Increase in Estimated Procurement Cost

As shown in Table A-1 below, the estimated combined procurement cost for all three DDG1000s, as reflected in the Navy’s annual budget submissions, has grown by $4,879.8 million (i.e.,

about $4.9 billion), or 54.4%, since the FY2009 budget (i.e., the budget for the fiscal year in

which the third DDG-1000 was procured).

Some of the cost growth in the earlier years in the table was caused by the truncation of the DDG1000 program from seven ships to three, which caused some class-wide procurement-rated costs

that had been allocated to the fourth through seventh ships in the program to be reallocated to the

three remaining ships.

36 For additional discussion, see CRS Report R43838, Great Power Competition: Implications for Defense—Issues for

Congress, by Ronald O'Rourke, and CRS Report RL33153, China Naval Modernization: Implications for U.S. Navy

Capabilities—Background and Issues for Congress, by Ronald O'Rourke.

Congressional Research Service

17

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Table A-1. Estimated Combined Procurement Cost of DDGs 1000, 1001, and 1002

In millions, rounded to nearest tenth, as shown in annual Navy budget submissions

Budget

submission

Estimated combined

procurement cost

(millions of dollars)

Change from prior

year’s budget

submission

Cumulative change

from FY2009 budget

submission

FY09

8,977.1

—

—

FY10

9,372.5

+395.4 (+4.4%)

+395.4 (+4.4%)

FY11

9,993.3

+620.8 (+6.6%)

+1,016.2 (+11.3%)

FY12

11,308.8

+1,315.5 (+13.2%)

+2,331.7 (+26.0%)

FY13

11,470.1

+161.3 (+1.4%)

+2,493.0 (+27.8%)

FY14

11,618.4

+148.3 (+1.3%)

+2,641.3 (+29.4%)

FY15

12,069.4

+451.0 (+3.9%)

+3,092.3 (+34.4%)

FY16

12,288.7

+219.3 (+1.8%)

+3,311.6 (+36.9%)

FY17

12,738.2

+449.5 (+3.7%)

+3,761.1 (+41.9%)

FY18

12,882.0

+143.8 (+1.1%)

+3,904.0 (+43.5%)

FY19

13,032.2

+150.2 (+1.2%)

+4,055.1 (+45.1%)

FY20

13,195.5

+163.3 (+1.3%)

+4,218.4 (+47.0%)

FY21

13,275.6

+80.1 (+ 0.6%)

+4,298.5 (+47.9%)

FY22

13,305.9

+30.3 (+0.2+%)

+4,328.8 (+48.2%)

FY23

13,378.7

+72.8 (+0.5%)

+4,401.6 (+49.0%)

FY24

13,793.2

+414.5 (+3.1%)

+4,816.1 (+53.6%)

FY25

13,830.9

+37.7 (+0.3%)

+4,853.8 (+54.1%)

FY26

13,856.9

+26.0 (+0.2%)

+4,879.8 (+54.4%)

Source: Table prepared by CRS based on data in annual Navy budget submissions.

The Navy stated in 2014 that the cost growth shown through FY2015 in the table reflects, among

other things, a series of incremental, year-by-year movements away from an earlier Navy cost

estimate for the program, and toward a higher estimate developed by the Cost Assessment and

Program Evaluation (CAPE) office within the Office of the Secretary of Defense (OSD). As one

consequence of a Nunn-McCurdy cost breach experienced by the DDG-1000 program in 2010

(see discussion below), the Navy was directed to fund the DDG-1000 program to CAPE’s higher

cost estimate for the period FY2011-FY2015, and to the Navy’s cost estimate for FY2016 and

beyond. The Navy states that it implemented this directive in a year-by-year fashion with each

budget submission from FY2010 through FY2015, moving incrementally closer each year

through FY2015 to CAPE’s higher estimate. The Navy stated in 2014 that even with the cost

growth shown in the table, the DDG-1000 program as of the FY2015 budget submission was still

about 3% below the program’s rebaselined starting point for calculating any new Nunn-McCurdy

cost breach on the program.37

The Navy’s FY2024 budget submission stated that $234 million of the increase shown for

FY2024 is for modifying the third ship in the program (DDG-1002) during its construction to

include large-diameter vertical launch tubes capable of storing and firing the Navy’s new

37 Source: Navy briefing for CRS and the Congressional Budget Office (CBO) on the DDG-1000 program, April 30,

2014.

Congressional Research Service

18

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

hypersonic Conventional Prompt Strike (CPS) missile.38 (Costs to modify the first two DDG1000 class ships—DDG-1000 and DDG-1001—for the CPS are budgeted in the Other

Procurement, Navy [OPN] appropriation account.)

Technical Risk and Test and Evaluation Issues

June 2025 GAO Report

A June 2024 GAO report—the 2025 edition of GAO’s annual report surveying DOD major

acquisition programs—stated the following in its assessment of the DDG-1000 program:

Current Status

Since last year’s assessment, the DDG 1000 program made progress with its installation of

the CPS hypersonic weapon system on the lead ship and accepted final delivery of DDG

1001. The Navy also continued DDG 1002 combat systems testing in the lead up to CPS

installation, builder’s trials, and acceptance trials, intended to support ship delivery in late

2026.

After years of delays, program officials stated that they plan to complete initial operational

test and evaluation in fiscal year 2025. Following live fire testing of the Tomahawk missile

systems on the DDG 1001 in January 2025, the Navy deployed DDG 1001 before the ship

enters a planned modernization period for CPS installation in mid-2026.

According to DDG 1000 officials, CPS program challenges resulted in a roughly 24-month

delay to the DDG 1000 live fire demonstration of the weapon system, which was previously

scheduled for 2025. DDG 1000 program officials stated that these developmental

challenges do not affect their current installation of the Large Missile Vertical Launch

System for CPS on the lead ship. This is because the CPS program is responsible for

ensuring that the hypersonic missile launches from the shipboard system. Still, key CPS

technologies—including the missile canister and system to eject the missile—remain

immature. Such immaturity poses design, cost, and schedule risks to achieving the DDG

1000 program’s hypersonic strike capability as planned.

DDG 1000 officials noted that risk remains for CPS software and integration. They said

that the DDG 1000 program will use testing to assess integration risk involving software

interfaces once the CPS program delivers a developmental version of the advanced payload

module that will hold the hypersonic missile and cannister. Delivery of this module is

scheduled for spring 2025.

Program Office Comments

We provided a draft of this assessment for program office review and comment. It provided

technical comments, which we incorporated where appropriate. The program office stated

that it has made significant progress in the testing and modernization of Zumwalt class

ships and noted that CPS installation efforts are in various stages on DDG 1000 and DDG

1002. It also stated that the Zumwalt class is on track to field CPS’ capability. In May 2025,

after our cutoff date for new information, program officials told us that they have yet to

achieve initial operational capability as planned, but they expect to do so in fiscal year

2025.39

38 Department of Defense, Fiscal Year (FY) 2024 Budget Estimates, Navy Justification Book Volume 1 of 1,

Shipbuilding and Conversion, Navy, March 2023, pp. 178-179.

39 Government Accountability Office, Weapon Systems Annual Assessment[:] DOD Leaders Should Ensure That

Newer Programs Are Structured for Speed and Innovation, GAO-25-107569, June 2025, p. 122.

Congressional Research Service

19

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

January 2025 DOT&E Report

A January 2025 report from DOD’s Director, Operational Test and Evaluation (DOT&E)—

DOT&E’s annual report for FY2024—stated the following regarding the DDG-1000 program:

TEST ADEQUACY

In FY23, the Navy completed a cyber cooperative vulnerability and penetration assessment

and an adversarial assessment between November 2022 and March 2023. Testing

encompassed Internet Protocol (IP) networks aboard the ship along with industrial control

systems associated with its hull, mechanical, and electrical systems. These tests were

adequate to assess cyber survivability of the class, were in accordance with the DOT&Eapproved test plan, and were observed by DOT&E.

In FY24, OPTEVFOR [the Navy’s Operational Test and Evaluation Force] continued

operational test of the Zumwalt-class in accordance with DOT&E-approved test plans and

DOT&E observation. The Navy conducted four live fire anti-air warfare tests in December

2023. Data collected from these tests were adequate to demonstrate the Zumwalt-class’s

ability to defeat ASCM [anti-ship cruise missile] raids in representative scenarios.

In FY24, OPTEVFOR continued Probability of Raid Annihilation M&S [modeling and

simulation] testbed runs with completion expected in FY25. These M&S runs are intended

to predict the Zumwalt-class’s probability of defeating inbound ASCMs and aircraft across

an expanded set of scenarios from the previously identified live fire test events. The Navy

expects to complete validation of the testbed in FY25 and expects to accredit it for this use.

DOT&E continues to work with OPTEVFOR to ensure appropriate use of the M&S testbed

for the determined uncertainties from the validation process.

The Navy plans to evaluate the Zumwalt-class primary mission of offensive surface strike

with a Tomahawk missile launch in FY25, including shipborne strike planning events.

Evaluation of Zumwalt-class employment of CPS will occur during FOT&E [Follow-on

Operational Test and Evaluation], in conjunction with CPS program testing, in FY27.

Torpedo defense testing, conducted with DDG 1000 in October 2021, provided data on the

class’s ability to evade torpedoes. However, full evaluation of the class’s effectiveness

against undersea threats has not been completed.

The Navy has yet to fund or schedule an FSST [Full Ship Shock Trials] for the Zumwaltclass. As previously identified in the FY22 and FY23 Annual Reports, this test is required

to adequately assess ship survivability against underwater threat weapons and determine

residual mission capability following such an occurrence.

The Navy reports that budget and schedule shortfalls preclude updates to vulnerability and

recoverability M&S to reflect the as-built Zumwalt-class or inclusion of CPS when

installed. The Navy intends to complete a Final Survivability Assessment Report in FY25

that includes survivability findings related to earlier ship design. DOT&E will not be able

to provide a complete assessment of the Zumwalt-class’s vulnerability to threat weapons

until M&S reflects the as-built ship and FSST is complete.

EFFECTIVENESS

Insufficient data are available to determine Zumwalt-class operational effectiveness or

change the preliminary assessment provided in DOT&E’s classified early fielding report

from November 2022. DOT&E will publish an IOT&E [Initial Operational Test and

Evaluation] report of the Zumwalt-class operational effectiveness after completion of

operational test that the Navy expects to occur in FY25. DOT&E will publish an update to

this report after test of the Zumwalt-class employment of CPS that the Navy expects to

occur in FY27.

SUITABILITY

Congressional Research Service

20

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Insufficient data are available to determine Zumwalt-class operational suitability or change

the preliminary assessment provided in DOT&E’s classified early fielding report from

November 2022. DOT&E will publish an IOT&E report of the Zumwalt-class operational

suitability after completion of operational test that the Navy expects to occur in FY25.

DOT&E will publish an update to this report after test of the Zumwalt-class employment

of CPS, as well as evaluation of the technological refresh of the class’s Command, Control,

Communication, Computer, Cyber and Intelligence systems, that the Navy expects to occur

in FY27.

SURVIVABILITY

Assessment of Zumwalt-class cyber survivability is classified. DOT&E will publish a

classified report of the Zumwalt-class cyber survivability after completion of IOT&E that

the Navy expects to occur in FY25.

Due to vulnerability and recoverability M&S not yet being validated, and not reflecting the

ship as-built, data remain insufficient to determine Zumwalt-class survivability against

threat weapons. DOT&E will require that the survivability M&S be updated and validated

as part of the upcoming TEMP revision.

Failure and recoverability mode testing aboard DDG 1001, conducted in 2022, provided

insight into the recoverability of the class after damage. However, testing was not sufficient

to resolve associated LFT&E [Live Fire Test and Evaluation] critical issues due to

limitations on the systems under test. DOT&E will address the strategy for completing the

LFT&E assessment of the Zumwalt-class’s mission system recoverability as part of the

upcoming TEMP revision.

RECOMMENDATIONS

The Navy should:

1. Complete remaining IOT&E events as recommended in the FY23 Annual Report.

2. Submit for DOT&E approval a revision of the TEMP [Test and Evaluation Master Plan]

for modifications to the operational requirements and employment of the Zumwalt-class to

include installation of CPS.

3. Submit for DOT&E approval an update to the LFT&E Strategy that includes FSST and

evaluation of the as-built Zumwalt-class following the installation of CPS.

4. Fund and schedule an FSST prior to the first deployment of a Zumwalt-class ship with

CPS installed as recommended in the FY23 Annual Report.

5. As noted in the FY22 and FY23 Annual Reports, document the risk to the warfighter

associated with incomplete component shock qualification and lack of an FSST, prior to

deployment.

6. As recommended in the FY22 and FY23 Annual Reports, sufficiently fund

modernization and sustainment of the DDG 1000 class to include improvements

determined from failure and recoverability mode testing as documented in the Navy’s

report on the event.40

Procurement Cost Cap

Section 123 of the FY2006 defense authorization act (H.R. 1815/P.L. 109-163 of January 6, 2006)

limited the procurement cost of the fifth DDG-1000 to $2.3 billion, plus adjustments for inflation

40 Director, Operational Test & Evaluation, FY 2024 Annual Report, January 2025, pp. 218-220.

Congressional Research Service

21

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

and other factors. Given the truncation of the DDG-1000 program to three ships, this unit

procurement cost cap appears moot.

2010 Nunn-McCurdy Breach, Program Restructuring, and

Milestone Recertification

On February 1, 2010, the Navy notified Congress that the DDG-1000 program had experienced a

critical cost breach under the Nunn-McCurdy provision. The Nunn-McCurdy provision (10

U.S.C. 2433a) requires certain actions to be taken if a major defense acquisition program exceeds

(i.e., breaches) certain cost-growth thresholds and is not terminated. Among other things, a

program that experiences a cost breach large enough to qualify under the provision as a critical

cost breach has its previous acquisition system milestone certification revoked. (In the case of the

DDG-1000 program, this was Milestone B.) In addition, for the program to proceed rather than be

terminated, DOD must certify certain things, including that the program is essential to national

security and that there are no alternatives to the program that will provide acceptable capability to

meet the joint military requirement at less cost.41

The Navy stated in its February 1, 2010, notification letter that the DDG-1000 program’s critical

cost breach was a mathematical consequence of the program’s truncation to three ships.42 Since

the DDG-1000 program has roughly $9.3 billion in research and development costs, truncating

the program to three ships increased to roughly $3.1 billion the average amount of research and

development costs that are included in the average acquisition cost (i.e., average research and

development cost plus procurement cost) of each DDG-1000. The resulting increase in program

acquisition unit cost (PAUC)—one of two measures used under the Nunn-McCurdy provision for

measuring cost growth43—was enough to cause a Nunn-McCurdy critical cost breach.

In a June 1, 2010, letter (with attachment) to Congress, Ashton Carter, the DOD acquisition

executive (i.e., the Under Secretary of Defense for Acquisition, Technology and Logistics), stated

that he had restructured the DDG-1000 program and that he was issuing the certifications

required under the Nunn-McCurdy provision for the restructured DDG-1000 program to

proceed.44 The letter stated that the restructuring of the DDG-1000 program included the

following:

•

•

•

A change to the DDG-1000’s design affecting its primary radar.

A change in the program’s Initial Operational Capability (IOC) from FY2015 to

FY2016.

A revision to the program’s testing and evaluation requirements.

Regarding the change to the ship’s design affecting its primary radar, the DDG-1000 originally

was to have been equipped with a dual-band radar (DBR) consisting of the Raytheon-built X41 For more on the Nunn-McCurdy provision, see CRS Report R41293, The Nunn-McCurdy Act: Background,

Analysis, and Issues for Congress, by Moshe Schwartz and Charles V. O'Connor.

42 Source: Letter to congressional offices dated February 1, 2010, from Robert O. Work, Acting Secretary of the Navy,

to Representative Ike Skelton, provided to CRS by Navy Office of Legislative Affairs on February 24, 2010.

43 PAUC is the sum of the program’s research and development cost and procurement cost divided by the number of

units in the program. The other measure used under the Nunn-McCurdy provision to measure cost growth is average

program unit cost (APUC), which is the program’s total procurement cost divided by the number of units in the

program.

44 Letter dated June 1, 2010, from Ashton Carter, Under Secretary of Defense (Acquisition, Technology and Logistics)

to the Honorable Ike Skelton, with attachment. The letter and attachment were posted on InsideDefense.com

(subscription required) on June 2, 2010.

Congressional Research Service

22

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

band SPY-3 multifunction radar (MFR) and the Lockheed-built S-band SPY-4 Volume Search

Radar (VSR). (Raytheon is the prime contractor for the overall DBR.) Both parts of the DBR

have been in development for the past several years. An attachment to the June 1, 2010, letter

stated that, as a result of the program’s restructuring, the ship is now to be equipped with “an

upgraded multifunction radar [MFR] and no volume search radar [VSR].” The change eliminates

the Lockheed-built S-band SPY-4 VSR from the ship’s design. The ship might retain a space and

weight reservation that would permit the VSR to be backfitted to the ship at a later point. The

Navy states that

As part of the Nunn-McCurdy certification process, the Volume Search Radar (VSR)

hardware was identified as an acceptable opportunity to reduce cost in the program and

thus was removed from the current baseline design....

Modifications will be made to the SPY-3 Multi-Function Radar (MFR) with the focus of

meeting ship Key Performance Parameters. The MFR modifications will involve software

changes to perform a volume search functionality. Shipboard operators will be able to

optimize the SPY-3 MFR for either horizon search or volume search. While optimized for

volume search, the horizon search capability is limited. Without the VSR, DDG 1000 is

still expected to perform local area air defense....

The removal of the VSR will result in an estimated $300 million net total cost savings for

the three-ship class. These savings will be used to offset the program cost increase as a

result of the truncation of the program to three ships. The estimated cost of the MFR

software modification to provide the volume search capability will be significantly less

than the estimated procurement costs for the VSR.45

Regarding the figure of $300 million net total cost savings in the above passage, the Navy during

2011 determined that eliminating the SPY-4 VSR from the DDG-1000 increased by $54 million

the cost to integrate the dual-band radar into the Navy’s new Gerald R. Ford (CVN-78) class

aircraft carriers.46 Subtracting this $54 million cost from the above $300 million savings figure

would bring the net total cost savings to about $246 million on a Navy-wide basis.

A July 26, 2010, press report quotes Captain James Syring, the DDG-1000 program manager, as

stating the following: “We don’t need the S-band radar to meet our requirements [for the DDG1000],” and “You can meet [the DDG-1000’s operational] requirements with [the] X-band [radar]

with software modifications.”47

An attachment to the June 1, 2010, letter stated that the PAUC for the DDG-1000 program had

increased 86%, triggering the Nunn-McCurdy critical cost breach, and that the truncation of the

program to three ships was responsible for 79 of the 86 percentage points of increase. (The

attachment stated that the other seven percentage points of increase are from increases in

development costs that are primarily due to increased research and development work content for

the program.)

Carter also stated in his June 1, 2010, letter that he had directed that the DDG-1000 program be

funded, for the period FY2011-FY2015, to the cost estimate for the program provided by the Cost

Assessment and Program Evaluation (CAPE) office (which is a part of the Office of the Secretary

45 Source: Undated Navy information paper on DDG-51 program restructuring provided to CRS and CBO by Navy

Office of Legislative Affairs on July 19, 2010.

46 Source: Undated Navy information paper on CVN-78 cost issues, provided by Navy Office of Legislative Affairs to

CRS on March 19, 2012.

47 Cid Standifer, “Volume Radar Contracted For DDG-1000 Could Be Shifted To CVN-79,” Inside the Navy, July 26,

2010. See also Joseph Trevithick and Tyler Rogoway, “Navy’s Troubled Stealth Destroyers May Have Radars

Replaced Before Ever Sailing On A Mission,” The Drive, October 15, 2020.

Congressional Research Service

23

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

of Defense [OSD]), and, for FY2016 and beyond, to the Navy’s cost estimate for the program.

The program was previously funded to the Navy’s cost estimate for all years. Since CAPE’s cost

estimate for the program is higher than the Navy’s cost estimate, funding the program to the

CAPE estimate for the period FY2011-FY2015 will increase the cost of the program as it appears

in the budget for those years. The letter states that DOD “intends to address the [resulting]

FY2011 [funding] shortfall [for the DDG-1000 program] through reprogramming actions.”

An attachment to the letter stated that the CAPE in May 2010 estimated the PAUC of the DDG1000 program (i.e., the sum of the program’s research and development costs and procurement

costs, divided by the three ships in the program) as $7.4 billion per ship in then-year dollars

($22.1 billion in then-year dollars for all three ships), and the program’s average procurement unit

cost (APUC), which is the program’s total procurement cost divided by the three ships in the

program, as $4.3 billion per ship in then-year dollars ($12.8 billion in then-year dollars for all

three ships). The attachment stated that these estimates are at a confidence level of about 50%,

meaning that the CAPE believes there is a roughly 50% chance that the program can be

completed at or under these cost estimates, and a roughly 50% chance that the program will

exceed these cost estimates.

An attachment to the letter directed the Navy to “return for a Defense Acquisition Board (DAB)

review in the fall 2010 timeframe when the program is ready to seek approval of the new

Milestone B and authorization for production of the DDG-1002 [i.e., the third ship in the

program].”

On October 8, 2010, DOD reinstated the DDG-1000 program’s Milestone B certification and

authorized the Navy to continue production of the first and second DDG-1000s and commence

production of the third DDG-1000.48

48 Christopher J. Castelli, “Pentagon Approves Key Milestone For Multibillion-Dollar Destroyer,” Inside the Navy,

November 22, 2010.

Congressional Research Service

24

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Author Information

Ronald O'Rourke

Specialist in Naval Affairs

Disclaimer

This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan

shared staff to congressional committees and Members of Congress. It operates solely at the behest of and

under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other

than public understanding of information that has been provided by CRS to Members of Congress in

connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not

subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in

its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or

material from a third party, you may need to obtain the permission of the copyright holder if you wish to

copy or otherwise use copyrighted material.

Congressional Research Service

RL32109 · VERSION 283 · UPDATED

25