The National Ignition Facility: Management, Technical, and Other Issues

Congressional research reportNov 8, 2001

Ask Donna

What actually matters in this document.

Text

Order Code RL30540

CRS Report for Congress

Received through the CRS Web

The National Ignition Facility:

Management, Technical, and Other Issues

Updated November 8, 2001

Richard Rowberg

Senior Specialist in Science and Technology

Resources, Science, and Industry Division

Congressional Research Service ˜ The Library of Congress

The National Ignition Facility: Management, Technical,

and Other Issues

Summary

The U.S. Department of Energy (DOE) is building a very large laser facility to

provide scientific support for its program to maintain the safety, reliability, and

performance levels of the nation’s stockpile of nuclear weapons in the absence of

nuclear testing. This National Ignition Facility (NIF), which is designed to simulate

the behavior of nuclear explosions, is under construction at DOE’s Lawrence

Livermore National Laboratory (LLNL).

In August 1999, however, DOE announced that the project had run into some

serious problems that would likely result in a significant increase in its cost estimate.

The root cause of this problem was determined to be inadequate experience and

capabilities in managing large, complex projects on the part of the LLNL NIF project

team. Correcting these problems would require obtaining outside expertise and

management that would significantly increase the project’s cost. In addition, a

review by the NIF Council of LLNL reported that substantial technical issues

remained unresolved, although LLNL is confident that they can be resolved. In some

cases, however, solutions do not appear to be obvious.

In its revised project baseline and schedule, DOE now estimates the project cost

to be $3.45 billion, 60% above the original estimate, and its completion date as 2006.

A GAO report issued in August 2000 estimated the cost of the project at $3.89

billion. In response to congressional direction, DOE submitted a letter to Congress

on April 5, 2001, certifying that NIF should be built to the full 192 beams and that the

September cost estimate and schedule would be met.

On June 1, 2001, GAO released a second report stating that the three DOE

weapons labs do not agree on the value of NIF, as currently configured, for the

stockpile stewardship program. GAO also noted that DOE has not set up an external,

independent review of the project and does not intend to do so.

For FY2002, DOE requested $245 million for NIF construction. Congress

(H.R.2311 and S.1171, H.Rept.107-258) appropriated the full FY2002 request for

NIF, adding $7 million to the DOE inertial confinement fusion (ICF) program for

NIF-related activities. The House (H.R.2586) and Senate (S.1438) each authorized

$245 million for NIF construction, adding $10 million to the DOE ICF program for

NIF-related activities.

In addition to the management and technology concerns, the NIF project raises

other issues, including: the effectiveness of NIF in meeting the goals of the DOE

program to maintain the nuclear weapons stockpile; the likelihood that NIF will reach

its principal scientific goals; the potential effect NIF may have on nuclear

nonproliferation; and uncertainty about NIF’s contribution to the advancement of

inertial fusion energy research. The management and technical issues, and the role of

NIF in the stockpile stewardship program appear to be of particular concern.

Contents

Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

Stockpile Stewardship . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

Technical Description and Applications of NIF . . . . . . . . . . . . . . . . . . . . . . 2

NIF Project Schedule and Cost Overruns – Chronology . . . . . . . . . . . . . . . 3

Congressional Actions – 106th Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

Congressional Actions – 107th Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

Issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

Project Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

Technical Concerns . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Contribution to Stockpile Stewardship . . . . . . . . . . . . . . . . . . . . . . . 19

NIF and Ignition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

NIF and Nonproliferation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

NIF and Inertial Fusion Energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

Outlook for the 107th Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

The National Ignition Facility: Management,

Technical, and Other Issues

Introduction

As part of the U.S. Department of Energy’s (DOE) program to maintain the

nation’s nuclear weapon stockpile, the DOE is building the National Ignition Facility

(NIF), which is planned to be the largest laser ever built. DOE anticipates that NIF

could achieve conditions of temperature and pressure in a laboratory setting that have

only been reached in explosions of thermonuclear weapons and in the stars. It is

hoped that NIF would be capable of achieving ignition of thermonuclear fusion of

deuterium and tritium — isotopes or forms of hydrogen — for the first time in the

laboratory.

NIF is to be a principal tool of the nation’s Stockpile Stewardship Program

(SSP) whose goal is to maintain the safety, reliability, and performance level of the

nation’s nuclear weapons in the absence of nuclear testing. It is one of several

experimental facilities being built for that program and is expected to provide

important contributions to the goals of stockpile stewardship and to contribute to the

advancement of inertial fusion energy (IFE) and other civilian scientific research

efforts. Recent problems with the construction of the facility, however, are likely to

result in a significant increase in the project’s cost. Also, technical problems remain

unsolved that might compromise the ability of NIF to reach its goals. In addition to

having implications for DOE appropriations and authorization, problems with NIF

also could increase the difficulty of the Administration’s continuing efforts to gain

ratification of the Comprehensive Test Ban Treaty.

Stockpile Stewardship

Largely as a result of the end of the Cold War, the United States has initiated

several steps designed to reduce the threat of nuclear weapons. On August 11, 1995,

the President announced that the United States would pursue a zero-yield

Comprehensive Test Ban Treaty (CTBT), which would institute a worldwide ban of

nuclear weapons tests of any yield.1 The treaty was signed by the United States at the

United Nations in September 1996. At the same time, the nation is not abandoning

I

For a discussion of the CTBT see, Congressional Research Service. Nuclear Weapons

Testing and Negotiation of a Comprehensive Test Ban Treaty. CRS Issue Brief 92099.

Regularly updated. On October 13, 1999, the U.S. Senate voted against ratification of the

CTBT. While the Russian Duma recently (April 2000) ratified START II, other related

actions must be taken by the U.S. Senate before it can enter into force. See, Congressional

Research Service, START II Debate in the Russian Duma: Issues and Prospects, by Amy

Woolf, CRS Report RL97-359, updated April 17, 2000.

CRS-2

its reliance on a nuclear deterrent as a key element of its national security policy.

Under the terms of the Strategic Arms Reduction Treaty II (START II), which has

been ratified by both the United States and Russia, the United States would retain a

stockpile of about 3,500 weapons if and when the treaty is fully implemented.2 The

Administration and Congress have stated that a capability must be in place to maintain

the safety and reliability of the existing stockpile.3

A program to carry out this mandate, the Stockpile Stewardship and Program,

has been instituted by DOE.4 Because the SSP cannot rely on nuclear testing, a

surrogate testing process based on laboratory experiments and computer simulation

is being developed by the SSP, the research portion of the SSP. The goals of the SSP

include enhanced surveillance of the aging weapons stockpile to detect aging-related

defects, an improved capability to predict when defects will occur, increased

understanding of the physics of nuclear weapons, and better computer simulation of

nuclear explosions to assess the potential effects of defects. In addition, the program

will explore means to simulate the testing of nuclear explosion effects. Finally, the

SSP will attempt to help preserve the core expertise in weapons science and

technology now in place at the DOE weapons laboratories.

Technical Description and Applications of NIF

An important component of the SSP is to be the National Ignition Facility (NIF),

which will house the largest laser ever built. If completed, NIF will be capable of

delivering light from an assembly of 192 laser beams at an energy level of 1.8 million

joules (MJ) to a very small target.5 The energy will be delivered in a few billionths of

a second, and the total power delivered on target will be about 500 trillion watts. The

ultimate target is a tiny pellet of deuterium and tritium, two isotopes or forms of the

element hydrogen. The laser beams, called drivers, are configured to compress this

pellet to very high temperatures and pressures, forcing the deuterium and tritium to

undergo nuclear fusion, releasing large amounts of energy. If all goes as planned,

fusion ignition will occur, whereby the nuclear fusion reactions would release more

energy than provided by the laser to cause the reactions in the first place.

NIF is designed to achieve, on a laboratory scale, conditions similar to those in

a nuclear weapon explosion. It will be the only experimental facility that would be

capable of attaining fusion ignition conditions. The pressure and temperature reached

in an NIF laser-driven capsule that reaches ignition is projected to be similar to that

2

U.S. Department of Energy, Draft Programmatic Environmental Impact Statement for

Stockpile Stewardship and Management, DOE/EIS-0236, February 1996, p. S-10.

3

President William Clinton, “Statement on a Comprehensive Nuclear Weapons Test Ban,”

August 11, 1995, Weekly Compilation of Presidential Documents, August 14, 1995.

Washington, U.S. Govt. Print. Off., p. 1433; and P.L. 103-160, Sec. 3138.

4

U.S. Department of Energy, Office of Defense Programs, The Stockpile Stewardship and

Management Program: Maintaining Confidence in the Safety and Reliability of the

Enduring U.S. Nuclear Weapon Stockpile, May 1995, p. 3.

5

The largest laser was the NOVA facility at Lawrence Livermore National Laboratory, which

was capable of delivering 40 thousand joules. It was recently decommissioned.

CRS-3

in a nuclear weapon, although the total energy output would be at least a million times

less than that of a weapon. The principal goals of NIF are to improve understanding

of the physics of specific aspects of weapon behavior, to validate improved computer

simulation codes,6 to evaluate the impact of defects discovered in the stockpile, to

simulate the effects of nuclear explosions on systems, and to help maintain the core

of “intellectual and technical competency” of the U.S. nuclear weapons program. NIF

is also expected to have several civilian scientific applications. DOE hopes that NIF

will be able to demonstrate fusion ignition as an important step toward harnessing

fusion energy for the production of electric power (inertial fusion energy or IFE).

NIF Project Schedule and Cost Overruns – Chronology

When the NIF project first appeared in the DOE budget request for FY1996, its

total project cost (TPC) — construction plus associated project costs — was reported

as $1.074 billion including construction and design costs (total estimated costs or

TEC) of $842.6 million. A completion date of the third quarter, 2002 was also given.

In the FY1998 budget request, DOE reported the total project cost of NIF to be an

estimated $1.196 billion including construction and design costs of $1.05 billion and

$146 million in associated project costs. The increase was a result of DOE’s decision

to stretch the project out by one year to a completion date of the third quarter, 2003.

These figures remained unchanged through the FY2000 budget request, and no

mention was made of any possible difficulties in meeting those targets. A hint of

some problems, however, could be seen in the detailed project description

accompanying the FY2000 request. DOE reported that total construction and design

cost estimates increased over the previous DOE estimate, but those changes were

compensated by a decrease in contingency funds from 12.6% of the total estimated

costs (the original contingency factor was 15%) to 7.6% of the total estimate. At this

point, the project was less than 50% complete, and the size of the remaining

contingency funds appeared to be quite low for a project this complex.

In March 1999, a preliminary assessment by NIF project officials at Lawrence

Livermore National Laboratory (LLNL) determined that there were major potential

problems with NIF construction that threatened to increase substantially project

costs.7 LLNL staff attempted over the next several months to see if the additional

cost could be accommodated within total project costs already approved, but did not

notify DOE until June 1999, when it reported these problems to NIF project staff at

DOE Headquarters. It was not until August 1999, however, that the Secretary of

Energy was informed. At that point, LLNL reported that the project cost would

increase by about 20–30% and completion would be delayed by 12 to 18 months.

LLNL stated that the cause of the cost increase was that assembly of the laser system

6

As weapon codes are changed, they need to be validated to ensure that they are accurately

modeling weapon processes. In the past, nuclear weapons tests were the primary means of

accomplishing this validation. Without tests, the codes will have to be checked by seeing how

well they describe the phenomena that occur during operation of the stockpile stewardship

experimental facilities such as NIF.

7

U.S. Department of Energy, Energy Department Announces Major Changes to Improve

National Ignition Facility Management and Accountability, News Release, March 24, 2000,

[http://www.doe.gov/news/releases00/marpr/pr00084.htm]

CRS-4

infrastructure was considerably more complicated than anticipated.8 An important

contributor to this added complexity was the difficulty in maintaining NIF’s stringent

cleanliness requirements during assembly. Officials at LLNL determined that the lab

did not have the capability to meet these more complex assembly requirements and

must contract for them. According to LLNL, securing those services through the

contract process was the primary source of the added cost and time to completion.

Upon learning of the potential cost overruns, the Secretary of Energy requested

an internal review of the project to determine the source of the problems. A special

task force of the Secretary of Energy Advisory Board (SEAB) was set up to

investigate management and technical problems at the project. In addition, the

University of California (UC), which manages LLNL under contract to DOE, also

initiated a review by a special committee of the UC President’s Council. The Council

was set up to advise the UC President on matters about the three DOE labs managed

by UC — LLNL, Los Alamos National Laboratory, and Lawrence Berkeley National

Laboratory. A third study focusing on technical issues was carried out by the

Technology Resource Group of the NIF Council, an advisory group internal to

LLNL.

The SEAB9 and UC10 reviews both confirmed that the assembly and installation

of the NIF laser system would be more difficult and rigorous, and would require a

cleaner environment than originally anticipated. They both concluded that the original

approach of having the assembly done by an operating contractor and LLNL

personnel while relying extensively on LLNL management would not succeed.

Rather, an outside contractor with experience in clean assembly of large, complex

systems and management of large engineering projects would be needed.11 As a

consequence, a significant increase in cost and time-to-completion would result.12

The NIF technical review found a number of potential technical issues that if not

resolved could seriously compromise the operation of NIF.13 Foremost is the

possibility that the optics facing the laser target — the final optics assembly — would

not be able to handle the laser energy intensities needed to achieve ignition. Both the

UC and SEAB reviews agreed with that assessment.

8

Personal communication, David Crandall, United States Department of Energy, Oct. 20,

1999.

9

Secretary of Energy Advisory Board, U.S. Department of Energy, Interim Report of the

National Ignition Facility Laser system Task Force, January 10, 2000. (Hereafter called the

SEAB Laser Task Force.)

10

University of California, Report of the University of California President’s Council

National Ignition Facility (NIF) Review Committee, November 18, 1999,

[http://labs.ucop.edu/internet/nr/nr112399.html]. (Hereafter called the UC President’s

Council.)

11

UC President’s Council, 3.

12

SEAB Laser System Task Force, 3.

13

Lawrence Livermore National Laboratory, Technology Resource Group of the NIF Council,

NIF Technology Review, Nov. 4, 1999. [http://www.nrdc.org/fpprog.html]

CRS-5

In response to the management problems uncovered by the SEAB and UC

reviews, the Secretary of Energy in March 2000, announced several changes in the

project structure: an Associate Director of NIF reporting to the LLNL director was

established; UC established a special panel of the President’s Council charged with

oversight of the NIF project; a headquarters NIF project office was established; the

NIF project was made part of the DOE Project Management and Oversight function

— mandated by Congress — that will provide an on-site DOE contractor with

expertise in large, complex project management; and important decisions about NIF

had to be approved by the DOE Deputy Secretary before funding is provided.14 In

making this announcement, the Secretary reiterated his belief that while the NIF

project has had serious problems with its management, the science underlying NIF

“remains sound.”15

On May 3, 2000, the Secretary of Energy announced a new budget and schedule

for NIF.16 He stated that DOE would increase funding for NIF by $95 million for

FY2001 to a total of $169.1 million for construction. In addition, the NIF funding

requirements would increase from $100 million to $150 million for FY2002

depending on the results of the new baseline, then scheduled for completion in August

2000. DOE did not ask for additional funding for FY2001, but proposed shifting

funds from other sources within the department. It was further stated at the press

conference accompanying the DOE announcement that most of the funds would come

from LLNL.17 The new schedule announced by the Secretary would have the first

batch of laser beams in operation by 2004 and the entire facility completed by 2008,

nearly five years past the original date. That completion date would be well beyond

the first estimates of the delay cited above.

On June 1, 2000, DOE delivered an interim report to Congress containing a new

plan for NIF with a revised cost estimate and schedule.18 In this plan, NIF would have

a total project cost (TPC) of $2.12 billion, would provide first laser light at the end

of FY2004, and would reach the full 192 -beam facility late in FY2008. Cost

increments would be $95 million for FY2001 and $150 million for FY2002 over the

original plan ($74.1 million for FY2001 and $65 million for FY2002). In addition to

the TPC, DOE also included costs that are directly related to NIF that had not

previously been counted as part of the NIF project but had been included in the

Inertial Confinement Fusion (ICF) program. These costs, estimated to be $833.1

million at the time of the FY1998 baseline, were now estimated to be $1.137 billion.

Therefore, the total NIF cost estimate in the June 1, 2000 document were $3.26

billion compared to the original baseline estimate of $2.03 billion, a cost overrun of

$1.23 billion or about 60%.

14

U.S. DOE March 24, 2000, News Release.

15

U.S. DOE March 24, 2000, News Release.

16

U.S. Department of Energy, Secretary Richardson Settles on a New Budget Schedule for

National Ignition Facility, News Release, May 3, 2000.

17

Tarun Reddy, “New NIF plan calls for delay in facility’s opening, more funding,” Inside

Energy/ with Federal Lands, McGraw-Hill, May 8, 2000, 3.

18

Letters to Senator Pete V. Domenici and Representative Ron Packard from Bill Richardson,

Secretary of Energy, June 1, 2000. [http://www.dp.doe.gov/dp_web/news_f.htm]

CRS-6

As the basis for this interim report, on May 30, 2000, the Director of LLNL

delivered a letter to the Secretary of Energy providing a certified estimate for a

revised cost and schedule baseline for NIF.19 The letter noted that LLNL as directed

by DOE had developed a detailed plan for completing the project as rapidly as

possible. Under this plan, the first laser light ( 8 beams) would be obtained at the end

of FY2003 and the full 192 beams would be operational at the end of FY2006. In

each case, two years later than originally planned. The total project cost of this new

plan was estimated at $1.95 billion. Funding increases of $150 million for FY2001

and $240 million for FY2002 over the original plan would be required.

The LLNL Director noted, however, that such increases would likely have a

“negative impact” on the rest of the stockpile stewardship program. As a result, he

provided other estimates that would not require such large initial funding increases.

Those estimates, however, were not developed in a detailed, bottoms-up manner, as

was the plan noted above, but were determined by estimating the effects of stretching

out that plan. When this stretched-out plan was presented to the NIF Program

Review Committee (NPRC), a group formed as part of the management reforms

instituted by DOE, the Committee expressed its dissatisfaction with the LLNL costestimate methodology. Further it was concerned about how well the stretched-out

plan would meet the requirements of the stockpile stewardship program (SSP) to

certify the readiness of the nation’s nuclear stockpile. As a result, LLNL created a

new plan that meets the funding increase limits imposed by DOE for the next two

years (as reported by the Secretary of Energy in March 2000) and would meet the

SSP certification requirements. This plan was the basis of the June 1, 2000 interim

report.

Because the June 1, 2000 estimate had not undergone a detailed, bottoms-up

review, DOE did not consider that it was adequate to fulfill the congressional

requirement for a revised baseline. This review was completed in August 2000, and

DOE delivered the revised baseline to Congress on September 14, 2000.20 The new

cost estimate is $2.248 billion for the TPC and $1.2 billion for associated program

activities giving a total of $3.448 billion or $1.42 billion above the original baseline.

Of this amount, $1.46 billion will have been spent by the end of FY2000. According

to the new baseline, first light (eight of the planned 192 beams) would be achieved in

FY2004 and the project would be completed by FY2008.

DOE also submitted to Congress on June 27, 2000, an FY2001 budget

amendment requesting budget authority for FY2001 for an additional $95 million for

NIF to come from other Stockpile Stewardship programs and $40 million to be

reallocated from the FY2001 Readiness in Technical Base and Facilities originally

planned for NIF operational support. This amendment, which would have added

$135 million in budget authority to the original FY2001 request of $74 million, was

rejected by the House and Senate authorization and appropriations committees.

DOE, however, reiterated the request in the September 14, 2000 revised baseline. As

19

Letter to the Secretary of Energy from the Dr. Bruce Tarter, Director, Lawrence Livermore

National Laboratory, May 30, 2000.[http://www.dp.doe.gov/dp_web/news_f.htm]

20

Letters to Senator Pete V. Domenici and Representative Ron Packard from Bill Richardson,

Secretary of Energy, September 14, 2000. [http://www.dp.doe.gov/dp_web/news_f.htm]

CRS-7

noted below, most of this request was approved by the House-Senate conference on

the FY2001 DOE appropriations bill, although with significant provisos.

On April 6, 2001, the NNSA of DOE delivered a report to Congress responding

to the certification request contained in the FY2001 Energy and Water Development

Appropriations Act (see below for details).21 DOE was required to submit this report

in order to receive the remainder of the FY2001 appropriation for NIF. In the letter

accompanying the report, the Administrator of the NNSA recommended that the NIF

proceed with the full complement of 192 beams. He also certified that the project was

on schedule and budget as set forth in the revised baseline. The Administrator stated

that a Workshop had been held to consider alternatives to a 192-beam facility and had

concluded that full-scale NIF was the best course for meeting the Stockpile

Stewardship program requirements. The Workshop concluded that any construction

path that paused the project at fewer than 192 beams and then completed the project

would cost more than proceeding directly to the full 192 beams. The Administrator

also noted that a five-year plan for the SSP is currently under development and will

be submitted to Congress after completion of the President’s national security

strategic review.

The Administrator also concluded that the High-Energy-Density Physics (HEDP)

program within the SSP should not only include a 192-beam NIF, but also the Omega

laser at the University of Rochester and the Z-machine at Sandia National Laboratory.

As for the latter, the Administrator stated that the proposed refurbishment of that

facility was promising but that it would not be a replacement for NIF. Finally, the

Administrator emphasized the importance of NIF in attracting and training new

scientific and technical personnel to the HEDP program.

In a related action, the Secretary of Energy announced on April 5, 2001, that

DOE would not make any changes in the design, construction, or operation of NIF

as a result of a supplemental environmental impact statement (SEIS).22 The SEIS was

carried out as a result of the uncovering of capacitors containing PCBs during

excavation for the NIF.

Congressional Actions – 106th Congress

In September 1999, the House Science Committee requested an investigation of

the NIF project by the General Accounting Office (GAO). The GAO review, released

in August 2000, concluded that

“NIF’s cost increases and schedule delays were caused by poor Laboratory

management, which included weaknesses in planning, budgeting, and project

21

Letter from John A. Gordon, Administrator of NNSA to The Honorable Dennis J. Hastart,

Speaker of the House of Representatives, April 6, 2001. This letter and the accompanying

documents were obtained at [http://www.dp.doe.gov/dp_web/news_f.htm]. At this time,

however, the document is no longer on that website.

22

U.S. Department of Energy, National Nuclear Security Administration, “Record of Decision

for the Final Supplemental Environmental Impact Statement for the National Ignition

Facility,” Federal Register, 60, No. 66, (April 5, 2001) 18078.

CRS-8

control. DOE’s oversight weaknesses contributed to cost and schedule

problems, and coupled with no effective independent review of NIF, allowed

NIF problems to go undetected.”23

The GAO report also noted that other factors contributed to the cost overruns and

delays, including initial budgets that did not reflect project complexity and

performance of major project construction in parallel with critical R&D.

In its report, GAO estimated total costs for the NIF project to be $4.08 billion.24

In addition to the TPC and costs for the associated program activities included by

DOE in its revised baseline, GAO includes $627 million for target-physics R&D and

NIF support supplied by other DOE labs that are not included in the DOE revision.

DOE disputes the inclusion of these costs arguing that they are part of the general

inertial confinement fusion research program supported by DOE and support

experiments in all of its ICF facilities. GAO claims that the target-physics work is

essential to NIF and should be counted. No estimate of these disputed costs for the

original baseline is given either by DOE or GAO. Assuming they would have been

the same, the original baseline estimate would have been $2.66 billion, leading to a

cost overrun, as accounted for by GAO, of 53.4%. GAO did not attempt to make an

independent assessment of the construction and supporting R&D cost estimates that

DOE did acknowledge.

On October 30, 2000, the President signed the Floyd D. Spence National

Defense Authorization Act for FY2001 (P.L. 106-398, H.Rept. 106-945). The Act

authorizes $209.1 million for NIF, $135 million above the original request. Included

in the funds are $40 million to be transferred from the Inertial Confinement Fusion

program. The Congress also included a provision in the Act requiring a report from

the NNSA with a revised baseline cost and schedule estimate. The Act prohibited

more than 50% of the authorized funds from being spent until this report was

delivered. The Act also required the General Accounting Office to carry out a

detailed review of the NIF program focusing on NIF’s role in ensuring stockpile

reliability and safety, its relationship with the rest of the stockpile stewardship

program, and the possible effects further delays in the NIF project could have on the

stockpile stewardship program. In addition, the GAO was to review the revised NIF

baseline report. Congress expressed its continuing disappointment in the management

and technical difficulties of the project, but also stated that it continues to believe in

the importance of the project and that recent management improvements justify the

funding increase.

On September 28 and October 3, 2000, the House and Senate respectively

approved the Energy and Water Development Appropriations Act conference report

23

United States General Accounting Office, Report to the Committee on Science, House of

Representatives, National Ignition Facility: Management and Oversight Failures Caused

Major Cost Overruns and Schedule Delays, GAO/RCED-00-141, August 2000, p.13.

24

GAO, National Ignition Facility, p. 10. The total reported by GAO was $3.89 billion.

That figure was based on an earlier DOE estimate for the TPC and associated costs. If the

DOE estimate for these costs given in the revised baseline are used, the GAO estimate would

increase to $4.08 million.

CRS-9

(H.Rept. 106-907). The bill was signed by the President on October 27, 2000 (P.L.

106-377, H.Rept. 106-988). The Act provided an appropriations of $199.1 million

for NIF for FY2001.25 Of this amount, $25 million was to come from a reduction in

other weapons activities funds allocated to LLNL, $40 million from transfer of NIF

operating funds to NIF construction, and $60 million in new appropriations.

Congress also included language in the bill stating that only $130 million of the

appropriation would be available at the start of FY2001 with the remaining funds

becoming available after March 1, 2001, upon certification by NNSA that several

requirements had been met. (See above for a discussion of that certification report.)

Among those requirements are a recommendation from NNSA on the path the project

should take based on an assessment of options including a smaller facility (48 or 96

beams); certification that the project is meeting its construction milestones and is on

budget and schedule; completion of a study as to whether a full-scale NIF is needed

to meet SSP goals; and a five-year budget plan for the SSP including how NIF will

be paid for in the out years. Congress expressed its belief that NNSA had not

adequately reviewed all options for NIF, particularly an assessment of a smaller

facility. Congress also directed the NNSA to “fully reflect a balanced set of programs

and investments within the stockpile stewardship program,” in its FY2002 budget

request and to ensure that the $3.4 billion NIF can be accommodated within these

programs.

Congressional Actions – 107th Congress

The DOE budget submission for FY2002 requested $245.0 million for NIF

construction, 24.2% above the FY2001 level. In addition, DOE requested $222.9

million for the remainder of the inertial confinement fusion program, much of which

is directly tied to the NIF project. According to the budget submission, the request

is consistent with the revised baseline described above. No changes were reported in

the FY2002 budget submission in total cost, scope, or schedule of the project from

the revised baseline.

On June 1, 2001, the GAO released its follow-up report as called for by the

FY2001 defense authorization act (see above).26 GAO concluded that the role of NIF

in the SSP was uncertain because the three weapons laboratories were not in

agreement on the contribution NIF would be able to make. In addition, GAO noted

that DOE has not yet certified that completion of NIF at its full design level will have

no negative consequences for the rest of the SSP. GAO further stated that any more

delays in completing NIF could affect the weapons’ research program primarily by

adversely affecting the programs ability to attract high quality scientific talent. GAO

also noted that DOE has not set up an independent external review process for NIF

and does not intend to do so.

25

For a discussion of the entire DOE R&D budget request for FY2001, see, Congressional

Research Service, Department of Energy Research and Development Budget for FY2001:

Description and Analysis, by Richard Rowberg, CRS Report RL30445, Jan. 5, 2001.

26

U.S. General Accounting Office, Department of Energy: Follow-Up Review of the National

Ignition Facility, GAO-01-677R, June 1, 2001.

CRS-10

On June 28, 2001, the House approved funding the full request for NIF

construction for FY2002 (H.R. 2311, H.Rept. 107-112). In addition, the House

appropriated $492.9 million for the ICF program, $25 million above the request. The

increase is to be used for R&D on high average power lasers. The House noted the

recent GAO report about NIF and cited some of the findings including the lack of an

outside, independent review group. The House stated its expectation that DOE

would address the GAO concerns. On July 19, 2001, the Senate approved $492.4

million for the DOE ICF program for FY2002 (S. 1171, S.Rept. 107-39). Included

was the full request for NIF construction, and $59.7 million for ICF/NIF experimental

support activities. The latter is $24.5 million above the request. Included in that

increase are $10 million to enhance NIF diagnostics and target development, and $7

million for the base program. In approving the request for NIF construction, the

Senate stated that despite the certification provided by DOE about the NIF cost and

schedule, that a “high level of vigilance and extraordinary management attention is

warranted” to ensure that the program remains on course. The Senate also noted its

agreement with the recent GAO study. In particular, the Senate expressed its concern

about the continuation of project oversight by the same people in that role before

project costs began to grow in 1999.

On November 1, 2001, both the House and Senate approved the conference

report (H.Rept.107-258) for the Energy and Water Development Appropriation Act,

2002. In that act, Congress approved the full request for NIF for FY2002. Congress

also provided and additional $7 million to the ICF program to enhance NIF

diagnostics and target development. There was no language in the conference report

about the cost overruns or other potential concerns about the project.

On September 25, 2001, the House passed its version of the National Defense

Authorization Act for Fiscal Year 2002 (H.R. 2586, H.Rept. 107-194). The bill

authorizes the entire request for NIF of $245.0 million for FY2002. In addition, the

House authorized an increase of $10 million for the remainder of the ICF program to

be used for NIF efforts to reduce risk and develop needed technology. The House

argued that there was a funding shortfall in that part of the NIF program. The House

also noted the improvements in NIF management and project oversight but expressed

concern about the remaining technical problems facing the project. It directed DOE

to inform it “expeditiously” of any future delays or cost escalation. The House noted

that NIF offers many basic and applied research opportunities beyond its weapons

mission, but directed DOE to ensure that the Stockpile Stewardship program be the

facility’s primary focus.

The Senate passed its version of the defense authorization act (S.1438,

S.Rept.107-62) on October 2, 2001. In that bill, the Senate authorized an

appropriation of $245.0 million for NIF construction, the requested amount. The

Senate also authorized an additional $10 million for the ICF program to support

enhancements of NIF diagnostics and target development. In addition, the Senate

directed the NNSA to report to the two Armed Services Committees when the NIF

project has reached its level 1 and level 2 milestones. Noting the importance of the

project to the stockpile stewardship program, the Senate directed these reports to

ensure that Congress is kept apprised of the project’s progress in meeting the revised

baseline. While expressing confidence that NIF’s budgetary and scheduling problems

have been solved, the Senate still intends that Congress keep close tab on the project.

CRS-11

Issues

Project Management. Until the reports of cost overruns in early September

1999, DOE officials were quite confident of cost and schedule estimates for NIF. As

recently as June 11, 1999, the Secretary of Energy publicly noted that the project was

on schedule and budget. As noted above, the project’s cost estimates were increased

from the original estimates by about 11.6% during the Title I design phase, but no

other changes were reported. The project had undergone several technical and

management reviews and confidence was high that the estimates would hold. Clearly,

that confidence was misplaced.

The SEAB, UC, and GAO reviews found the NIF project to suffer from severe

management problems. The principal source of the problems was LLNL’s

inexperience with managing large, complex engineering projects.27 The SEAB Task

Force concluded that the management structure in which the DOE weapons labs

(LANL, LLNL, and Sandia National Lab) operate encourages a self-reliant attitude

that inhibited LLNL’s willingness to seek help from outside for activities in which it

did not have adequate competence, in particular management of large engineering

systems.28 This conclusion was also arrived at by the UC review. A particularly

egregious example of this inexperience, according to all three reviews, was the setting

of the original contingency factor at 15%. They all argued that this was much too low

for a project this complex. The fact that the contingency level had dropped to less

than 8% with the project less than half done appears to corroborate this conclusion.

GAO noted that LLNL failed at the outset to appoint a project manager with the

“management and technical expertise” required of such a large and complex project.

It also stated that LLNL did not install a reporting system that could have effectively

noted technical and other issues that would put the project at risk.29

The SEAB and GAO reviews also concluded that all three participants in the

process — LLNL, DOE, and UC — must share in the blame for allowing this cost

overrun to occur. The UC report stated that the project was far more complex than

any ever attempted by the LLNL and required management capabilities it did not

possess. LLNL was not capable of identifying those management weaknesses, and

neither were DOE nor UC.30 The three assessments also noted that the project was

not adequately reviewed and monitored by either DOE or UC. The SEAB Task

Force stated that independent reviews are a necessity, a view concurred with by UC.

All three reviews pointed out the absence of effective communications throughout the

entire NIF project. The UC review suggested that success in solving earlier problems

on the project led to a reluctance to report problems to anyone outside the immediate

project staff. GAO concluded that DOE’s historic reliance on contractors was at the

27

SEAB Laser System Task Force, 9.

28

SEAB Laser System Task Force, 5.

29

GAO, National Ignition Facility, p. 15.

30

UC President’s Council, 5.

CRS-12

“core” of its oversight weakness. GAO stated that DOE did not have staff with

“adequate management and technical skills” to provide effective oversight.31

The GAO report elaborated on the absence of effective DOE oversight.32 GAO

concluded that the monthly and quarterly reports prepared by LLNL did not indicate

the growth and extent of cost and schedule problems as they appeared. Further, the

chain of command between DOE and LLNL was confusing leaving ambiguous at best

questions of to whom laboratory officials should report. GAO also argued that DOE

did not act expeditiously when problems were first suspected.

DOE has taken many steps to implement the recommendations of the SEAB and

UC reviews. The announcements — noted above — that were made by the Secretary

of Energy indicate that substantial management changes have been made at both

LLNL and DOE. The May 30 LLNL letter also notes substantial changes in project

management.33 In particular, the letter says that the external review process has been

“completely revamped” including the establishment of the NIF Programs Review

Committee. The LLNL director also noted that every attempt is being made to

coordinate the activities of all of the new review groups. The committee established

to validate the revised baseline of the NIF project concluded that DOE has made the

management changes necessary to ensure successful completion of the project.34 It

stated that the “management approach is appropriate for the project with the size and

complexity of NIF” and “that the proposed NIF scope, cost, and schedule baselines

are reasonable.” The committee also agreed that the new contingency level of 25%

of remaining costs was reasonable. The Chairman of the SEAB review team also

concluded that the management concerns raised in its interim report have been

addressed and that he was “confident” that the responsible parties could perform their

tasks “properly.”35 It is apparent that changes have been made that suggest a shift

from science to engineering expertise has taken place within the project management

hierarchy.

It remains to be determined, of course, whether these changes will guide the

project to a successful completion within the new baseline. A particularly crucial

issue is the degree of outside, independent review. GAO noted that the “absence of

effective independent reviews” was a major reason that problems were not recognized

and dealt with in a more timely manner.36 As noted above, the latest GAO report

31

GAO, National Ignition Facility, p.16.

32

GAO, National Ignition Facility, p.16.

33

LLNL, May 30, 2000, letter, 7.

34

U.S. Department of Energy, Department of Energy Rebaseline Validation Review of the

National

Ignition

Facility

Project,

August,

2000,

[http://www.dp.doe.gov/dp_web/news_f.htm], ii.

35

Letters to William B. Richardson, Secretary of Energy, from John P. McTague, Chairman,

SEAB NIF Laser System Task Force, September 7, 2000.

[http://www.dp.doe.gov/dp_web/news_f.htm]

36

GAO, National Ignition Facility, p.18.

CRS-13

repeated the observation that DOE has not yet formed an external independent

review, and further noted that DOE does not intend to do so.

While new oversight panels have been established by UC, DOE, and LLNL it is

not clear how effective these reviews will be. In addition, while coordination among

these review groups is important to avoid duplication and minimize the burden on the

NIF project team, care must be taken to ensure the independence of the review

groups. Without an effective outside review mechanism, there is increased risk that

the project will continue to run into significant problems even with the new

management structure in place.

The revised baseline validation committee also pointed out a number of potential

problem areas.37 It concluded that a single NIF review process that satisfies NNSA,

UC, and LLNL was necessary to avoid excessive demands on the NIF project. The

committee also recommended strengthening the NIF project office within NNSA

headquarters. In addition, it argued for strong support from LLNL in terms of getting

and retaining the right personnel for the project. The committee also found that a

system for measuring progress and performance using earned-value techniques was

critical for the project and should be put in place. The committee also noted that the

separation of most R&D activities from project control was a significant contributor

to the problems encountered by NIF. While recognizing the steps taken to integrate

R&D into the project, the committee stated that the scope and cost of R&D necessary

to complete NIF needs to be identified and incorporated into the project’s schedule.

In connection with this last point, the June 2001 GAO report noted that about

$700 million of R&D that is supporting the NIF project is not managed by the project

and is not included in the monthly reports issued by NIF.38 While the report notes that

DOE is currently reviewing how the integrate those activities within the NIF project.

A critical aspect of these management issues is the degree of involvement of

industry in the project. As noted, one of the major contributors to the cost overrun

was the substantial underestimate of how difficult it would be to assemble the 192

beamlines to the required degree of cleanliness. According to the May 30 LLNL

letter, the project, after consultation with the semiconductor industry, has taken two

steps to correct this problem.39 It is asking industry to provide a higher level of

component integration than originally planned. Component integration by laboratory

personnel will be greatly reduced. Also, installation of the mechanical and electrical

infrastructure for the beampath will be done by one contractor. These actions will

place much of the installation of the beam assembly in the hands of industry with more

experience in large, complex project management. In August 2000, DOE completed

these actions by awarding a $230 million contract to Jacobs Engineering for

integration management and installation.

37

DOE, Rebaseline Validation, p.39.

38

GAO, Department of Energy, 4.

39

LLNL, May 30, 2000, letter, 8.

CRS-14

Because of the unique nature of NIF, however, it is not clear whether these steps

will ensure successful construction of NIF within the revised budget. In particular,

care will be needed to ensure a close and cooperative working relationship between

industry with the project management expertise and LLNL staff with expertise in large

laser systems. The revised baseline evaluation committee also argued for close

management, communications, and monitoring by LLNL of the industrial contractors

obtained to perform beam hardware integration.40

Another important management issue is the rate the NIF should be completed

given the extent of the cost overruns. A number of options were considered by

LLNL at the direction of DOE.41 Two options were described in a review carried out

by the Target Physics Program Review Committee at the request of the NIF Program

Review Committee on the impact of NIF construction delays on the DOE SSP.42 The

first option called for the first laser bundles to come on line by the end of FY2003 and

final project completion by the end of FY2006. The other option (labeled option 3)

called for the first bundles by the end of FY2004 with final project completion by the

end of FY2009.

The May 30, 2000, letter from LLNL to DOE suggests that LLNL favored an

aggressive completion path described by the first option. As noted, that path would

have required an increase in FY2001 funding of $150 million and an increase of $240

million for FY2002.43 This option was also the one apparently favored by the Target

Physics Review Committee (TPRC).44 It argued that the first option would provide

the “earliest benefit” from NIF because it would allow operation of a partially

completed facility — 48 beams — well before the other options (the end of FY2004)

while the facility was being completed. The TPRC stated that operation of a 48-beam

cluster would be very beneficial for DOE’s SSP. The TPRC also expressed its belief

that if deployment of NIF took too long, the project might not be completed.

DOE has chosen a path about mid-way between the two options. As argued in

the May 30, 2000, LLNL letter to DOE, the large increases required by the first

option could have serious consequences for the rest of the SSP. Therefore, DOE has

chosen to limit those increases. Presumably, DOE hopes that its path will balance

budget concerns with the technical and programmatic concerns of the Target Physics

Review Committee. The DOE-selected path would reach the 48-beams bundle in

FY2006, about one and one-half years later than the LLNL choice, and result in a

completed NIF about one to 1.5 years after the LLNL choice. This path was

40

DOE Rebaseline Validation, p. 20.

41

U.S. Department of Energy, Memorandum for Dr. Bruce Tarter, Director, Lawrence

Livermore National Laboratory, Options for National Ignition Facility, March 9, 2000.

42

U.S. Department of Energy, Lawrence Livermore National Laboratory, Report of the

National Ignition Facility Target Physics Program Review Committee, Draft, April 13,

2000, 3. The NIF Program Review Committee is the successor to the NIF Council. The

Committee along with the Target Physics Program Review Committee are made up of

individuals outside the NIF program and, for the most part, outside of the DOE labs.

43

LLNL, May 30, 2000, letter, 2.

44

Target Physics Review Committee, 4.

CRS-15

confirmed in the revised baseline presented on September 15, 2000 and in the March

2001 certification report to Congress.

A final point concerns project milestones. One result of the management

problems has been the establishment of detailed milestones for the project including

a comprehensive work schedule. The June 2001 GAO report, however, noted that

none of the major milestones take place until after 2004.45 As a consequence, GAO

recommended that earlier milestones be set up in order to track more carefully the

progress of the project.

Technical Concerns. In addition to the management issues uncovered by the

reviews of the NIF program, several technical concerns were highlighted. These

included the high degree of cleanliness required during assembly of the laser system

infrastructure and optics, and some potentially serious limitations of key optical

components.

The NIF design has always incorporated the need to maintain stringent

cleanliness requirements during construction and operation. As noted above,

however, the degree of cleanliness required was greater than anticipated. As pointed

out by the SEAB Task Force, maintaining the necessary level of cleanliness while

assembling the laser infrastructure and optics is a major challenge. In addition, budget

constraints early in the project constrained the size of the laser building, limiting clean

air flow below the levels needed.46 Further, because the infrastructure is to be

completed before the first optical elements are installed, any cleanliness-related

lessons learned during installation cannot be used to modify the infrastructure.

As noted by LLNL and the SEAB Task Force, the size and cleanliness

requirements of NIF are similar to those of semiconductor fabrication, and the lab

plans to make use of that expertise. There are, however, some differences.47 Unlike

a semiconductor manufacturing facility, the NIF infrastructure will lack adequate air

flow, which, combined with the constrained height of the building, will make it

impossible for the laser bay to be a truly clean room. Also, unlike semiconductor

manufacturing, there can be no period of operation at less than optimal cleanliness

conditions because an NIF laser bundle cannot be operated with any particulate

contaminations. Also, nonvolatile organics — used to clean optical components prior

to installation — must be at a much lower concentration for NIF than for a

semiconductor plant. Therefore, it is not clear that using industrial expertise to

manage the installation of the laser assembly will by itself ensure that cleanliness

requirements will be met. If NIF had constructed an engineering prototype beam,

some of these problems might have been addressed earlier. Construction of such a

beam does not appear feasible at this point and it is likely that the first bundle will

have to serve in that capacity. The SEAB Task Force, however, stated that if

adequate care is taken and it is understood by NIF project management that assembly

45

GAO, Department of Energy, 4.

46

SEAB Laser System Task Force, 15.

47

SEAB Laser System Task Force, 16.

CRS-16

of that first bundle will necessarily require a steep learning rate, the cleanliness issue

should not stop NIF from achieving its goals.

The review by the revised baseline validation committee did not explicitly

address the cleanliness issue. It did, however, comment on beamline assembly and

installation, and on the beampath infrastructure systems, all of which are critically

coupled to the cleanliness issue. The committee found the personnel involved in these

activities to be of high quality and experienced.48 It further noted that the Integration

Management and Installation (IMI) contract was an “innovative solution” to the

problem of installing the beamline in the NIF building with adequate cleanliness. The

committee cautioned, however, that the contract must be well-managed and

monitored closely to ensure success. This is particularly true because the contract

does not contain allowances to correct problems that might arise during installation.

It is clear that DOE is depending critically on the IMI contractor to resolve the

cleanliness issue.

Also problematic are the issues about the laser optics. The report of the

Technology Resource Group (TRG) of the NIF Council noted that major technical

advances in eight areas were needed from the start of the project to reach NIF’s goals.

In other words, substantial research and development (R&D) to develop key project

components remained even while NIF was under construction. Furthermore, the

original NIF budget and program did not adequately account for that R&D, and the

technology development budget associated with the NIF project was exhausted by the

end of FY1998.49 The TRG noted that the deployment goal, which assumed that the

required technology and associated manufacturing processes were complete and

available, was unrealistic. It went on to say that the original plan, to begin operation

as soon as the facility was complete, was not possible because of the technical

uncertainties and required technology development.

While the TRG reports that significant progress has been made in these eight

areas, substantial technical challenges remain.50 The TRG identified four specific

technical areas of special concern. The most important of these, as noted above,

appears to be the potential for severe damage to the final optics assembly (FOA)

because of NIF energy intensity requirements.51 To reach the design level of 1.8

million joules (MJ), a fluence — beam energy per unit of area — of 8 to 9 joules per

square centimeter (J/cm2) is required. This level is a result of an original design

compromise that reduced the number of beams from 240 to 192. At that fluence

level, it was discovered, unexpectedly, that the fused silica optics when operated in

a vacuum with light at the wavelength at which NIF would operate — conditions that

48

DOE Rebaseline Validation, p. 20, 25.

49

Technology Resource Group, 6.

50

Technology Resource Group, 5.

51

The final optics assembly is that portion of the beam path that fronts on the target chamber.

That portion of the beam path operates in a vacuum.

CRS-17

would occur in the FOA — are subject to “catastrophic” damage in that the damage

grew rapidly with each pass of the beam.52

At this point, there is no obvious technical solution to this problem. The TRG

stated that design alternatives for the FOA are likely to be needed. It proposed that

the NIF project “get out of the box” in addressing the FOA problems.53 Further, the

TRG noted, it is possible that fused silica may never be able to permit full-fluence

operation of NIF, and that such operation is likely to need a superior optical material.

Without a solution, NIF would be forced to operate at either fluence levels of about

one-half the design level, reducing laser output below one MJ, precluding achieving

ignition, or the optics would have to be changed at a rate 10 times greater than now

planned, significantly increasing NIF operating costs.54 Indeed, GAO argues in its

June 2001 report that DOE may have significantly underestimated the annual

operating cost of the completed NIF because those cost estimate assume solution to

the FOA problem. DOE claims that it has developed a theoretical solution, but it has

not been tested in the laboratory.55

Another of the four areas concerns the quality of laser glass produced by the

continuous melt process. That process was selected by the NIF project team because

of the large quantity of glass required for the facility. The first batches produced in

this manner showed higher levels of water vapor trapped in the glass and greater

variations in the optical quality (measured by the index of refraction) than could be

tolerated. The laser glass is where the physical phenomena that produces the laser

beam takes place, and the two problems would result in beam energy intensity below

the design level. LLNL believes that it has found solutions for these problems. It

intends to use special furnaces to heat the laser glass material prior to its introduction

into the continuous melt process to reduce its water content. Recently, LLNL

announced that continuous-melt laser glass produced by one it its principal vendors

using this preheating technique met specifications for water content.56 As a result, it

appears that water content, at least, will not prevent the laser glass from being able

to support the design fluence of 8-9 J/cm2.57 The laser glass from this run, however,

still did not meet optical quality specifications. For this purpose, LLNL proposes

using special polishing techniques called “small tool” polishing. Such methods, while

appearing straightforward, have not yet been tested for NIF laser glass design

parameters.

Technology Resource Group, 17. This problem is also referred to as the 3T problem

because the frequency of the laser light is increased by a factor of three as it enters the FOA

region. It is this higher frequency that creates the problems with the FOA optics.

52

53

Technology Resource Group, 18.

54

SEAB Laser System Task Force, 21.

55

GAO, Department of Energy, 4.

56

Lawrence Livermore National Laboratory, “National Ignition Facility and Glass Vendors

Achieve Continuous Melt Milestone,” NR-00-03-13, March 31, 2000.

57

Beam conditions for the laser glass and the laser glass itself are different than the FOA glass,

and the ability of the former to support the design fluence will not affect the problems

described about the FOA glass.

CRS-18

The TRG offered a number of recommendations to address the concerns it

raised. It estimated the cost of implementing these recommendations to be about $5080 million over the next eight years. The Group concluded that by following these

recommendations, “NIF can reach its original performance goals, although with some

delay and at higher cost than projected.”58

The MAY 30 LLNL letter also addressed the technical issues. The LLNL

Director reported that all of the external reviews concluded that NIF is “technically

sound and based on good engineering design.”59 Addressing the FOA issue explicitly,

the LLNL Director noted that it was not yet completely resolved. He stated that the

current plan is to operate NIF at fluence levels below the damage threshold for the

initial experiments. For those experiments that require higher levels, such as for

achieving ignition, it would be possible to replace the optics more frequently although

operating costs would increase. The NIF project team, however, expressed its belief

that the optics current limitations with the FOA will be overcome and that NIF will

be able to operate economically at the higher fluence levels.60

The revised baseline evaluation committee also addressed the FOA damage issue.

It concluded that existing technology would allow NIF to meet its goals but at a very

high damage rate that would adversely affect operating costs.61 At the same time, the

committee, expressed confidence that the problem would be solved provided

sufficient resources are made available. It stated, however, that while progress

towards a solution appears to be promising, the relevant R&D program described in

the NIF project, now estimated to cost $27 million, appears to be underfunded and

the committee recommended an increase of $30 million.62 The DOE certification

report of April 2001 did not address the FOA problem. On a related issue, the

committee recommended that LLNL contract with a second vendor for the critical

optics to ensure that a single-point production failure situation would not occur. Such

an occurrence is possible with just one vendor producing all of the critical optics.

While the cost estimate of the TRG and the revised baseline evaluation

committee are relatively modest compared to estimates of $3.5 to 4.1 billion for the

total NIF project cost, it should be emphasized that the issue with these technology

concerns is not cost but whether they can be solved at all. Solutions will likely require

basic research for which the outcomes cannot be predicted and success is only weakly

dependent on funds available. This is particularly true of the FOA concerns.

Therefore, while the TRG, the NIF Laser Task Force, and the revised baseline

evaluation committee all appear confident that the technical problems can be solved,

there remains considerable uncertainty, and success is not assured. Underscoring this

concern is a finding of the GAO study that criticized DOE for starting construction

of the project in parallel with critical R&D. GAO noted that results of that R&D have

58

Technology Resource Group, 5.

59

LLNL, May 30, 2000, letter, 4.

60

LLNL, May 30, 2000, letter, 6.

61

DOE Rebaseline Validation, p. 19.

62

DOE Rebaseline Validation, p. 18-19.

CRS-19

forced changes in the project that were difficult to make and contributed to the cost

overrun because construction of the infrastructure had advanced so far.63

The SEAB Task Force also argued that LLNL should consider a different

approach to installing the full 192 beams. Currently, plans call for installation of two

bundles of 96 beams, the second to follow immediately upon completion of the first.

The Task Force suggested that an extended pause between the two bundles would be

preferable. While adding costs to the facility, such a pause would allow the NIF team

to commission the first 96 beams and determine if any modifications need to be made

in the second bundle before it is installed.64 Such a process could save a significant

amount of time in installing the second bundle. In essence, the first bundle could act

as the prototype which was not constructed earlier in the project. The Target Physics

Review Committee, however, did not favor a pause. It stated that there did not

appear to be any “programmatic reason” as far as the SSP was concerned for any

pause.65 The Committee noted, however, that if technical or budget reasons required

a pause, it should be done at a point where enough beams were available to do

important stockpile stewardship physics. It recommended that 120 beams would

provide the best opportunity for this situation.

The LLNL director in his May 30 letter argued that the path proposed by DOE

would have the same effect as the pause recommended by the SEAB Task Force.66

He stated that while there is no “distinct” pause in the preferred schedule, the fact that

it is stretched out would give the project team time to carry out the testing

recommended by SEAB. He noted that the completion dates in the preferred

schedule are the same as those recommended by SEAB including the pause. The

revised baseline evaluation committee did not make an explicit statement about

phased beam installation. Rather, the report appeared to assume a full 192-beam

facility.

Contribution to Stockpile Stewardship. The potential contribution of

NIF research to the Stockpile Stewardship program (SSP) is substantial and diverse.

It could be a valuable platform for investigating a range of scientific and technical

problems about nuclear weapons performance and reliability that could be significant

for the long-term security of the nation. All outside review groups setup by DOE to

date agree that these capabilities are critical for the success of the DOE SSP.67

Some other groups, however, believe that nuclear weapons safety should be the

primary concern of the SSP, and oppose NIF because its contribution to verifying

63

GAO, National Ignition Facility, p.14.

64

SEAB Laser System Task Force, 11.

65

Target Physics Review Committee, 8.

66

LLNL, May 30, 2000, letter, 6.

67

See, for example, JASON, The Mitre Corporation, Science Based Stockpile Stewardship,

JSR-94-345, McLean, VA, November 1994. This study was performed under DOE contract.

CRS-20

weapon safety would be relatively small.68 In addition, a few critics argue that the

level of reliability and performance that DOE is trying to maintain for the stockpile

through NIF and other elements in the program is excessive and not needed for a

credible deterrent. Others, however, believe that the level of confidence desired by

the DOE program cannot be achieved without nuclear testing.

Recent advances in pulsed-power research at Sandia National Laboratories

(SNL) have also raised questions about whether other, lower cost technologies might

be able to achieve many of the goals of NIF. Based on successful experiments

completed in 1998 on the SNL’s Z accelerator, a new machine, called the X-1, is

being proposed at a cost of about $300 million. That machine might be able to

explore important conditions needed for the SSP.69 As currently envisioned, NIF

would still be able to reach temperatures greater than those likely for the X-1 allowing

NIF to investigate conditions not otherwise attainable. It is possible, however, that

the X-1 could also achieve ignition, although that is uncertain at this time. If so, it

might be able to achieve a large fraction of NIF objectives. Currently, no decision has

been made whether to proceed with the X-1. For FY2001, DOE is requesting

funding to continue experiments on existing pulsed-power devices in order to assess

such devices for a high yield. DOE, however, did not request any funding for

development of advanced pulsed-power devices, suggesting that any decision about

the X-1 remains on hold.

The Target Physics Program Review Committee

recommended that the Z accelerator, along with the Omega laser at the University of

Rochester, be used extensively to explore important SSP scientific issues as both a

supplement to NIF and to mitigate some of the consequences of the delay in

completing NIF.70 The Committee, however, said nothing about the X-1.

The May 30, 2000, LLNL letter repeats the arguments made at the projects

inception in support of the need for NIF.71 It states that the completed NIF (with the

full 192-beam assembly) is the only instrument capable of reaching the conditions of

temperature and density necessary for greater understanding of the physics of nuclear

explosions. Further, it is stated in the letter that NIF will be necessary to help validate

the codes being developed for the Accelerated Strategic Computer Initiative whose

goal is to simulate the nuclear explosion as a substitute for nuclear weapons testing.

In both cases, the letter’s author notes that ignition is essential, and the potential of

NIF to reach ignition is one of the most important features of the project.

The delay in construction and cost overruns have raised the question about

whether NIF should be completed to its original design level of 192 laser beams. In

particular, could NIF still make a significant contribution to the SSP if it were built

68

See the National Resources Defense Council web site for an extended critique of NIF and

SSP [http://www.nrdc.org/nrdcpro/fpprog.html]; and Unpublished memorandum to Marylia

Kelly, Tri-Valley Citizens Against a Radioactive Environment, from Greg Mello, May 13,

1994.

69

James Glanz, “Will NIF Put the Squeeze on Sandia’s Z Pinch?” Science, v. 277, July 18,

1997.

70

Target Physics Review Committee, 8-9.

71

LLNL, May 30, 2000, letter, 4.

CRS-21

with only a fraction of the beams, say 48 or 96? The Target Physics Program Review

Committee argues that the facility should be completed to the full 192 beams.72 In

particular, the Committee states that ignition is very important if NIF is to be of

maximum utility, and it very likely will require all 192 beams to reach ignition. At the

same time, however, the committee noted that important contributions to the SSP can

be made with a 48-beam laser, and it recommended that experimentation begin as

soon as that level was reached. The committee also argued that operation of 48

beams could help resolve several of the operational issues and ease attainment of the

192-beam goal.73

A report issued by directors of the three weapons laboratories also argued for

completing the laser to the full 192 beams.74 In order to study critical physical

phenomena in the laboratory in regimes that permit extrapolation or the results to the

behavior of actual nuclear weapons, minimum laser energy levels are needed. The

report notes that the energy threshold for some of these phenomena will be crossed

at the 48 to 96 beam level. Others will require 96 beams or more, while still others

will require the full 192 beams.75 Furthermore, the report’s authors argue, the full 192

beams are likely to be required to reach ignition and to provide enough energy to test

the computer models being developed to simulate nuclear weapons behavior.76 The

April 2001 certification report reiterated the need to develop the full complement of

beams. As noted above, the report cited a study by the High-Energy-Density Physics

Workshop that examined alternatives to a 192-beam facility and concluded the SSP

requirements were best met with the full 192 beams.

It appears that a critical factor in this debate is whether all 192 beams are needed

to reach ignition. While some scientific issues of stockpile stewardship can be

addressed if NIF did not reach ignition, many observers believe it is critical to do so.

In particular, the authors of the Foster report concluded that it “is very important that

the NIF produce ignition in order to address a new range of stockpile issues ... .”

They argued that “a half-power NIF without ignition is not worth the investment for

stockpile stewardship.”77 If ignition could be reached with a smaller number of beams,

it is possible that a smaller facility could be built or that NIF can make a greater

contribution to the SSP before it is complete than now seems to be the case. The

studies requested in the conference report along with the FY2001 DOE

appropriations appear to ask for a DOE justification of building the full-scale NIF.

Another aspect of this issue is how the delays in completing NIF and paying for

its cost overruns will affect the remainder of the SSP. GAO concluded that the

72

Target Physics Review Committee, 4.

73

Target Physics Review Committee, 7.

74

U.S. Department of Energy, The National Ignition Facility and Stockpile Stewardship

White Paper, April 24, 2000, [http://www.dp.doe.gov/dp_web/news_f.htm].

75

White Paper, 6.

76

White Paper, 7.

77

John S. Foster, Jr., et.al., FY2000 Report to Congress of the Panel to Assess the Reliability,

Safety, and Security of the United States Nuclear Stockpile, February 1, 2001.

CRS-22

consequences for the program could be substantial.78 In particular, GAO reported

that construction delays will mean that some of the experiments needed to reach the

SSP milestones for 2010 could be delayed by three years. The budget consequences

could be much more serious. GAO argues that if the cost overruns are taken from

existing programs as is now DOE’s plan, “significant portions of the weapons

program could be affected.”79 Further, GAO reports that the three weapons labs —

LLNL, LANL, and SNL — are not in agreement about how to proceed with NIF to

minimize the potential budgetary impact. At this point, according to GAO, DOE has

not sought to resolve these differences and the new baseline decision was made

without adequate consideration of its effects on the rest of the SSP.80

The revised baseline evaluation committee also raised this issue, although

somewhat obliquely.81 It noted that NNSA and DOE Defense Programs should take

steps to ensure a balance between the long-term NIF operating costs and the

resources needed for other facilities and activities “essential” for the stockpile

stewardship program. The committee stated that a plan for governing NIF as a user

facility must be in place before research begins on the facility.

The June 2001 GAO report noted that there appears to be difference of opinion

among the three weapons laboratories about the potential usefulness of NIF to the

SSP.82 In particular, it stated that Los Alamos National Laboratory believes that NIF

will be limited in its contribution to the SSP unless it can use plutonium and can

achieve ignition. The former is currently not planned and the latter, as discussed

below, is uncertain. Sandia National Laboratory argues that NIF’s contribution will

be limited because it will not be able to certify whether weapons can exist in a hostile

(radiation) environment. GAO notes that the two labs reportedly have recommended

that NIF be limited to a smaller number of beams until its performance can be assured.

In any case, the potential contribution of NIF is a matter of dispute. The

increased cost of the project has revived these concerns. Although Congress at this

point appears to have agreed that a full-scale NIF is necessary for the program, it has

asked DOE, through the NNSA, to certify this conclusion in light of the cost

increases. It may be difficult, however, to verify whether the several contributions of

NIF, combined with those of the other elements of the SSP, are effective in helping

to maintain performance and reliability without some kind of nuclear test validation.

NIF and Ignition. NIF is being designed to reach thermonuclear ignition —

the condition where energy released by the fusion reactions is sufficient to sustain the

reaction. Nearly all scientists who have reviewed the project believe that ignition will

78

GAO, National Ignition Facility, p.25.

79

GAO, National Ignition Facility, p.26.

80

GAO, National Ignition Facility, p.27.

81

DOE Rebaseline Evaluation, p. 48.

82

GAO, Department of Energy, 2-3.

CRS-23

be reached at the design level of 192 laser beams.83 Some critics have argued that

certain physical conditions concerning the interaction of the laser beam and the plasma

that is generated when the target is vaporized will prevent attainment of ignition.

They have said that more analysis is needed before a decision to begin physical

construction is made.84 Recent experiments on the NOVA laser at LLNL, however,

showed that some of those concerns might not be warranted. Other improvements

in target design have also raised confidence that ignition can be achieved. Indeed,

some have suggested that combining all of the advances could result in ignition being

reached with as few as 96 beams, although there would be virtually no margin in

terms of laser performance.85 Nevertheless, if these improvements are possible, then

the margin at 192 beams should be substantial. Furthermore, it is possible that higher

fusion energy yields (gain)86 than were envisioned in the original NIF design would

be possible, leading to the ability to study physical phenomena still closer to actual

conditions in nuclear weapons.

While confidence is high that ignition will be achieved, it is still not certain,

however, and confirmation probably will have to await until NIF is operational. If NIF

cannot achieve ignition for any reason, its value to the SSP would be reduced

significantly as noted above. It would still be able to perform physics useful for the

program, although it is not clear whether its contribution in that case would be

commensurate with its cost. Because of the uncertainty and the importance of

ignition to the program, the lab director’s and the Target Physics Program Review

Committee recommend the full 192 beams.

NIF and Nonproliferation. Because NIF would explore certain physical

regimes (temperature and density) similar to that of a thermonuclear weapon, some

concern has been expressed that results from NIF studies could contribute to nuclear

proliferation.87 Accessibility to NIF for investigations of civilian applications of

inertial confinement fusion would likely enhance the expertise of individuals who are

or could become weapons designers. Such knowledge likely is not sufficient by itself

for proliferation, however, and is irrelevant for the design of fission weapons likely

to be the objective of first-time nuclear weapons states or organizations. It should be

noted that the basic scientific principles of operation of thermonuclear weapons are

widely known. Also, a DOE study, coordinated with the Arms Control and

Disarmament Agency, found that potential proliferation concern can be managed.88

83

JASON, Science Based Stockpile Stewardship; Target Physics Review Committee, 11.

84

Stephen E. Bodner, “Time-Dependent Asymmetries in Laser-Fusion Hohlraums,”

Comments on Plasma Physics and Controlled Fusion, v. 16, 1995, pp. 351-374.

85

Target Physics Review Committee, 10.

86

Fusion yield or gain is the ratio of energy produced by nuclear fusion reactions to the energy

required to drive those reactions. Ignition occurs when gain just exceeds one.

87

Jacqueline Cabasso and John Burroughs, “End Run Around the NPT,” The Bulletin of the

Atomic Scientists, September/October 1995, pp. 27-29.

88

U.S. Department of Energy, Office of Arms Control and Nonproliferation, The National

Ignition Facility (NIF) and the Issue of Nonproliferation, NN-40, December 19, 1995.

CRS-24

NIF and Inertial Fusion Energy. While NIF is being designed to achieve

ignition, an important milestone for inertial fusion energy (IFE) research, the specific

type of laser used by NIF is unlikely to be a candidate for a practical fusion power

plant driver, the device that supplies energy to initiate the fusion reaction. Although

DOE is currently funding research to develop alternate driver technology, there is no

certainty one will emerge that can meet conditions of a practical power plant.

Without such assurance, therefore, even successful demonstration of ignition on NIF,

prior to alternate driver development, may be for naught as far as development of

inertial fusion energy is concerned. On the other hand, proceeding with driver

development before demonstration of ignition could also result in misallocated

resources. If ignition cannot be achieved at conditions that would allow a practical

fusion reactor, then a feasible driver candidate could be of little value.

A potential added complication is the emergence of the National Nuclear

Security Administration (NNSA). This organization, which was mandated by

Congress in the FY2000 defense authorization act (P.L. 106-65, H.Rept. 106-301),

might create added organizational barriers between the defense and civilian activities

within DOE.89 If so, coordination between the civilian and defense inertial

confinement fusion research efforts might be made more difficult. Recently, however,

DOE announced the formation of a “Heavy Ion Fusion Virtual National Laboratory

(VNL)” involving three of the DOE labs including LLNL.90 The purpose of the

collaboration is to conduct research on heavy-ion drivers for inertial fusion energy

applications. Such an agreement might serve as a means to smooth the passage for

future inertial fusion energy research involving NIF.

Outlook for the 107th Congress. The limitations on spending for the NIF

project imposed by the FY2001 DOE appropriations and Defense authorization acts

(see above) ensure that Congress will continue to monitor this project closely during

the 107th Congress. The primary focus will probably be how DOE is performing in

meeting the changes in the project baseline announced on September 15, 2000. In

addition, there is likely to be close oversight of DOE’s efforts to resolve the remaining

technical problems with the project. Of particular interest are the consequences of

any actions on the eventual cost and effectiveness of NIF. Besides the management

and technical issues, the role of NIF in the stockpile stewardship program may be

raised in the 107th Congress. As noted above, questions to this effect were raised

during the 106th Congresses review of the difficulties encountered by the NIF project.

Any assessment of the stockpile stewardship program as a whole is also likely to

consider the need for NIF.

Conclusions

The importance of NIF to the Stockpile Stewardship and Management Program

makes it difficult to separate decisions about NIF from decisions about the entire

program. If one agrees that the SSP as defined by DOE is both feasible and

89

Congressional Research Service, Department of Energy: programs and reorganization

proposals, by Carl Behrens and Richard Rowberg, RL30307, Oct. 28, 1999.

90

Fusion Power Associates, “Heavy Ion Fusion VNL,” FPN00-20, April 5, 2000,

[http://aries.ucsd.edu/fpa/fpn00-20.shtml].

CRS-25

necessary, then NIF now appears necessary to achieve the program’s goals,

particularly if it achieves ignition. Without NIF or nuclear testing, there currently

does not appear to be any way to examine important aspects of nuclear weapon

physics critical for the computer codes designed to simulate nuclear weapons or to

carry out complete validation of those codes. If one believes that the SSP is either not

feasible or not needed, however, then NIF could be called into question.91 If NIF

were not needed to assure a credible nuclear weapons stockpile, then it would have

to be evaluated on the merits of its civilian scientific applications. While those areas

appear to be important, the project’s high cost would make it difficult to justify solely

as a civilian scientific research instrument.

The recent problems with NIF have added considerably to the controversy

surrounding the project. With a cost overrun of nearly 60%, it is difficult to see how

completion of NIF could be funded from existing stockpile stewardship funds.

Indeed, actions by Congress for FY2001 are providing additional funds although not

the entire increase requested, however, do not suggest that additional funds will be

easily forthcoming. While the current sentiment is to build NIF to its original design

specifications, it is possible that the laser will be scaled back. If the cost overruns are

even greater than now estimated, if the technical challenges with the laser optics are

more daunting than now appears, and/or confidence in ignition with a lower number

of beams grows, pressure could mount to reduce the scope of the project.

At this point, it is unclear how extensive any action on NIF by the 107th Congress

will be. The 106th Congress did agree that the project was necessary and approved

most of the adjustments requested by DOE. There has been no indication thus far that

the 107th Congress may have a different view of NIF. If the new project management

demonstrates that it has control of the project and meets the revised schedule, and if

good progress is made in resolving the technical issues, then it is likely that oversight

will be confined to the review of the budget request. If new problems emerge,

however, it is likely that the entire project will be subject to extensive review and

possible modification.

91

For a description of other options for stockpile stewardship see Congressional Research

Service, Nuclear Weapons Stockpile Stewardship: Alternatives for Congress, by Jonathan

Medalia, CRS Report 96-11 F, December 14, 1995.