Military Base Closures: Agreement on a 2005 Round

Congressional research reportJan 22, 2003

Ask Donna

What actually matters in this document.

Text

Order Code RL30051

Report for Congress

Received through the CRS Web

Military Base Closures:

Agreement on a 2005 Round

Updated January 22, 2003

name redacted

Specialist in U.S. Foreign Policy and National Defense

Foreign Affairs, Defense, and Trade Division

Congressional Research Service ˜ The Library of Congress

Military Base Closures: Agreement on a 2005 Round

Summary

Ninety-seven major military bases were recommended for closure and

realignment by the 1988, 1991, 1993, and 1995 base realignment and closure

(BRAC) commissions. Action on all 451 installations (major and minor) from the

first four rounds was completed by the end of FY2001, as scheduled. The U.S.

General Accounting Office has estimated that these closures and realignments

produced net savings of about $16.7 billion as of the end of FY2001 and will

continue to produce an estimated annual recurring savings thereafter of about $6.6

billion.

In mid-1997, Secretary of Defense William Cohen called for two new rounds

of base closures and realignments. He explained that, while four previous rounds

had achieved significant savings, it was important to continue the process of closing

underutilized facilities. Despite DOD pressure, most Members of Congress were

reluctant to support authorization of new base closure legislation, at least for the

foreseeable future. The reasons given included, among others, grass-roots opposition

from communities likely to be affected and President Clinton’s “intervention” in the

1995 base closure commission’s recommendations regarding McClellan and Kelly

air force bases. Of the two chambers, the House of Representatives expressed the

stronger and more united opposition. In the Senate, proponents of new base closure

rounds have attempted to attach amendments to each year’s defense authorization bill

since 1997, achieving success only toward the end of 2001.

The principal advocates in Congress for new base closures have been Senator

John McCain and Senator Carl Levin. On February 27, 2001, they introduced

legislation (S. 397) to authorize two new closure rounds in 2003 and 2005. On

August 3, 2001, the Secretary of Defense submitted his own proposal to Congress,

calling for one additional round in 2003. On September 6, 2001, the Senate’s

defense panel incorporated elements of both proposals and passed the measure by a

vote of 17 to 8. Later, in Senate floor debate (September 24, 2001), the

Levin/McCain initiative passed by a margin of 53 to 47.

However, many Members of the House were reluctant to support S. 397, thus

creating an impasse in the conference phase that delayed final passage of the FY

2002 defense legislation. Finally, on December 12, 2001, the conferees reached a

compromise. They agreed to authorize one new round of base closures in 2005.

They also added language that revised various aspects of previous base closure law

– the most notable of which, perhaps, will be the enhanced role and influence of the

Secretary of Defense in the base closure selection process. President Bush signed

the defense authorization bill into law (P.L. 107-107) on December 28, 2001.

This report will be updated as warranted.

Contents

Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

Closures and the 105th Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

Dispute over Depot Privatization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

DOD Report on Costs and Savings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

CBO and GAO Assessments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

Closures and the 106th Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

Closures and the 107th Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

Conclusion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

Table

Table 1. 2005 BRAC Timeline . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Military Base Closures:

Agreement on a 2005 Round

Introduction1

This report discusses key base closure developments, beginning with the 105th

Congress and continuing into the 107th Congress. The most recent notable

development has been the December 28, 2001 signing into law (P.L. 107-107) of

legislation, initially sponsored by Senator Carl Levin and Senator John McCain, to

conduct one new base closure round in 2005. The legislation extends and amends

the 1990 base closure and realignment Act (P.L. 101-510) that expired after the 1995

round.

All action on the 451 installations scheduled to be closed and realigned by the

1988, 1991, 1993, and 1995 BRAC commissions was completed by the end of

FY2001, as scheduled.2 Ninety-seven installations were major military bases.

According to the most recent estimates, these BRAC closures and realignments have

produced net savings of about $16.7 billion, and annual recurring savings thereafter

of about $6.6 billion.3

It was widely acknowledged, at the time of the 1995 round, that additional base

closures would be necessary, given the continuing downward trend in defense

spending and force structure (units and personnel). Two years later, the Department

of Defense began to press its case in earnest. On May 19, 1997, Secretary of

Defense William Cohen released a long awaited report, the Quadrennial Defense

Review (QDR). In the report, a major review of military strategy and capabilities,

he called for two more rounds of closures, one in 1999 and the second in 2001. He

explained that, despite four previous rounds, the downsizing of DOD’s base structure

had fallen behind the downsizing of its force structure. He pointed out that:

1

For context and background, see CRS Report 97-305, Military Base Closures: A Brief

Historical Review since 1988, by George Siehl, 16 p.

2

“Realignment” is an action distinct from “closure.” It involves transferring units and

functions, in and/or out of an installation, whereby the result is a net reduction of DOD

civilian personnel. “Closure” involves shutting down or relocating most, if not all, of an

installation’s mission. Small portions of the base may be retained for use by reserve

components.

3

U.S. General Accounting Office. Military Base Closures: Progress in Completing Actions

from Prior Realignments and Closures, April 2002, p. 8-11.

CRS-2

Since the first base closure round, force structure has come down by 33% and

will have declined by a total of 36% when we finish the reductions under the

QDR. During the same period, we will have reduced domestic infrastructure by

21%.... We must shed more weight.4

He further explained that closing more bases was dictated not only by the need

to achieve a proper balance between infrastructure and force structure, but also by

the need to secure significant savings that would allow DOD to fund adequately

future readiness and weapons acquisition programs. He stated that without the

savings from new rounds of closing, DOD would be hard-pressed to fulfill its

missions and responsibilities in the future.

Closures and the 105th Congress

Secretary of Defense Cohen’s plan to begin new rounds of closures within the

next five years was met with a decided lack of enthusiasm on Capitol Hill. Many

Members expressed deep concern over the likely economic and political fallout in

their districts from any such new rounds. Both defense committees of the House and

Senate, during their mark-ups of the FY1998 DOD authorization bills, declined to

support new base closure legislation. On June 12, 1997, the Senate Armed Services

Committee narrowly failed, on a 9-9 vote, to approve a proposal to authorize two

more rounds of base closing in 1999 and 2001. The next day, Senator Carl Levin,

the committee’s ranking Democrat, along with Senator John McCain, Senator Dan

Coats, and Senator Charles Robb, pledged to push for more base closings when the

DOD authorization bill went to the floor. Senator Levin said that, if Congress was

serious about having funds for new weapons, it was necessary to reduce excess

infrastructure.

On July 9, the full Senate voted 66-33 against the McCain-Levin initiative and

in support of a substitute amendment that delayed any new base closings until DOD

developed “accounting techniques” to accurately measure the costs and savings from

previous and future rounds. Under the substitute amendment, sponsored by Senator

Byron Dorgan, Senator Trent Lott, and Senator Tom Daschle, DOD was required to

prepare and submit its cost/savings report to Congress “in a timely manner.”

Although no specific date was set, the provision stipulated that the report must be

completed with adequate time for Congress to authorize another round of base

closings in 2001.

In the House National Security Committee, opposition to a new round of

closures was considerably stronger. Representative Joel Hefley, chairman of the

subcommittee on military installations, indicated that there should be no new base

closure rounds for at least five years. He, as well as others, questioned DOD’s

estimate of actual savings, especially in the short- and medium-term, given the

substantial up-front costs of shutting down bases. Although DOD officials have

claimed net savings, beginning in FY1996 and increasing into the future, the

4

U.S. Department of Defense. Report of the Quadrennial Defense Review, May 1997, pp.

viii-ix.

CRS-3

Congressional Budget Office, in a December 1996 report, stated that it was unable

to confirm or assess those estimates.5

Congressional opponents, further, objected to rushing into new rounds of

closures without a complete and thorough understanding of the military implications

of previous rounds. In this regard, they also questioned the validity of DOD’s major

premise that there should be a one-to-one correlation between the percentage of

reduction in end-strength and in base closings.

Despite the lack of broad support on Capitol Hill, senior DOD officials, as well

as the President, continued to press for new rounds of base closures in the near

future. Both Secretary of Defense Cohen and the retiring Chairman of the Joint

Chiefs of Staff, Gen. John Shalikashvili, issued statements in September 1997 calling

for more base closures as a way of making funds available for top priority weapons

programs.6 On November 10, the Secretary of Defense and other senior Pentagon

officials announced a series of reforms, titled “Defense Reform Initiative” (DRI),

that included two additional rounds of base closures in 2001 and 2005. These

rounds, it was asserted, would eventually result in annual savings of about $1.4

billion each, or a total of $2.8 billion.7 This figure represented about half of the

overall $6 billion annual savings anticipated from DRI actions that include, in

addition to base closings, increased outsourcing to private industry, shifting to

paperless contracting, administration, and publishing, and reducing the number of

personnel employed by the Office of the Secretary of Defense and other agencies,

departments, and activities.

Further support for two, or more, new rounds of base closures came from the

December 1997 report entitled Transforming Defense: National Security in the 21st

Century.8 Members of the DOD-sponsored National Defense Panel that prepared

the report strongly urged Congress and the Defense Department to “move quickly

to restore the base realignment and closure process.” They called for closures to

begin “earlier than the current 2001-2005 department proposal.” In his endorsement

of the panel’s findings, Secretary of Defense Cohen emphasized, as he had in the

past, the importance of two additional BRAC rounds as a means of financing and

accelerating the transformation of U.S. military capabilities.9

5

U.S. Congressional Budget Office. Closing Military Bases: An Interim Assessment,

December 1996, 74 p.

6

Jeff Erlich, “Cohen: Procurement Spending Is at Risk,” Defense News, September 15,

1997, p.1.; “More Base Closings May Be Fiscal Answer for Pentagon,” Los Angeles Times,

September 3, 1997, p. 10.

7

U.S. Department of Defense. Defense Reform Initiative Report,” November 1997, p. 37-40.

8

U.S. Department of Defense. Report of the National Defense Panel. Transforming Defense:

National Security in the 21st Century, December 1997, 94 p.

9

U.S. Department of Defense. “Defense Secretary Cohen Endorses Panel’s Key Conclusion

that Fundamental Infrastructure Reform is Essential to Transformation of U.S. Military,”

December 1, 1997, 2 p.

CRS-4

Dispute over Depot Privatization

A highly contentious aspect of the base closure debate involved President

Clinton’s actions concerning the last of the four rounds. The 1995 base closure

commission had recommended the closing of two of the Air Force’s five major

maintenance depots: at McClellan Air Force Base (CA) and Kelly Air Force Base

(TX). The recommendation had been justified on the grounds that all five depots

were operating at under 50% capacity, and that significant savings could be achieved

by transferring McClellan’s and Kelly’s workloads to the three remaining depots in

Utah, Oklahoma, and Georgia.10

President Clinton vigorously opposed closing McClellan and Kelly depots,

arguing that California and Texas had already suffered disproportionately from

effects of the three previous closure rounds.11 He moved to prevent further loss of

jobs in California and Texas by directing that private firms be allowed to assume the

work on site -- otherwise known as “privatization-in-place.” Opponents of the

President, however, were quick to charge him with unprecedented political meddling

in the base closing process. They accused him of trying to curry favor with the

people of vote-rich California and Texas, vital in his bid for reelection.12

Legislators from Oklahoma, Georgia, and Utah opposed the privatization plan,

believing that it deprived their local populations of jobs that would have been

otherwise created under the initial recommendation of the 1995 base closure

commission. Also, they knew that the existing privatization plan, if permitted to

proceed, left their depots highly vulnerable to closure whenever the next round of

base reductions occurred.13

Resentment among some Members over President Clinton’s 1995 intervention

persisted until the end of his second term. His action was repeatedly cited by

congressional opponents as reason for their opposition to any new base closure

rounds.14 Some Members sought to block DOD from proceeding with plans to

privatize depot maintenance work at McClellan and Kelly air force bases. On June

5, 1997, the House military readiness subcommittee approved an amendment to the

FY1998 defense authorization bill prohibiting privatization at the two depots unless

the Secretary of Defense certified that the three remaining depots were operating at

an efficient 80% capacity. These other depots, as mentioned above, were operating

at approximately 50% capacity. The full House National Security Committee

approved the measure on June 16. Similar depot language was approved by the full

Senate Armed Services Committee on June 17. However, in the face of a threatened

filibuster by the four Senators representing California and Texas, the depot-related

10

U.S. Defense Base Closure and Realignment Commission. Report to the President, July

1, 1995, p. 108-109.

11

“Base Closures Enter Final Phase,” CQ Almanac 1995, p. 9-19 to 9-22.

12

James Kitfield, “Off Base.” Government Executive, June 1998, p. 1-11.

13

Ibid.

14

“Congress Resists Pentagon Plans to Shutter Bases,” USA Today, July 30, 2001, p. 13.

CRS-5

provisions were removed from the DOD authorization bill prior to floor

consideration.15

In floor debate, on June 23, 1997, Representative Terry Everett led an effort to

delete the depot-related restrictions in the House FY1998 defense authorization bill.

His amendment was defeated by a vote of 145 to 278. In the other chamber, Senator

Inhofe spearheaded an effort to restore depot-restrictions to the Senate bill. He and

his co-sponsors, however, withdrew their amendment on July 11, just before its floor

consideration.

In conference committee, the depot-related language in the House bill became

a major bone of contention and obstacle to reaching final agreement on the FY1998

defense authorization bill. As of early October, it was reportedly the only remaining

issue to be resolved. Neither of the opposing camps seemed willing to yield -- with

one side threatening filibuster and/or veto if public-private depot competition at

McClellan and Kelly air force bases were not allowed to go forward, and the other

side insisting that without language prohibiting depot competition, there would be

no bill. A resolution was achieved by the Senate and House conferees and reported

on October 23 (H.Rept. 105-340). Under the compromise agreement, the limit on

depot work that could be done by private contractors was increased from 40% to

50%. On the other hand, a broadened definition of the “core work” that must be

done by government depots served to offset the benefits to private contractors of

their percentage increase.

On October 28, the House passed the conference report by a vote of 286 to 123.

On the following day, the Senate debated the conference report’s provisions

regarding depot maintenance operations at length, but did not move to a final vote.

A bid by Senator Kay Bailey Hutchison to postpone a final vote on the FY1998

defense authorization until January 18, 1998 was denied. On November 6, the

Senate reached final agreement, passing the conference report by a vote of 90 to 10.

President Clinton signed the bill into law on November 18 (P.L. 105-85).

DOD Report on Costs and Savings

In the FY1998 defense authorization act cited above, Congress included

language (Section 2824) that prohibited DOD from taking any concrete steps towards

planning and implementing new base closures until it had submitted a report on

“costs and savings attributable to the first four rounds of closure and realignment;

and on the need, if any, for additional rounds.” The detailed requirements set forth

in the Dorgan Amendment included ten “Elements” and eight “Methods of

Presenting Information.” The deadline for delivery of the report was set for “no later

than the President’s submission to Congress of the budget for FY2000” (JanuaryFebruary 1999).

15

“Hill Impedes New Round of Base Closings,” Washington Post, June 23, 1997, p 1.

CRS-6

On April 2, 1998, far in advance of the deadline, the Department of Defense

submitted its report to Congress.16 Secretary of Defense Cohen, in his introductory

statements, stressed several key points in calling for new base closure and

realignment legislation in the current year. He stated that the base structure was,

currently, 23% in excess of what was needed, and that savings from two new rounds

of closings would provide vital funding for modernization of weapons systems and

improved readiness. He reminded Congress that while the defense budget was down

40% and force structure 36%, base structure had declined only 21%. He cited

several other examples of the significant imbalance between force and base

structures. The number of Navy ships was scheduled to drop by 46% between 1989

and 2003; while berthing space would decline by only 18%. The number of Army

soldiers was slated to fall 43% in the same period, compared with only a 7% planned

reduction in classroom space.

The base closure report, in providing information requested by Congress in

Section 2824, claimed that the closure costs of the 1988 and 1993 rounds were less

than the Pentagon’s original estimate. It asserted that the costs of the 1991 and 1995

rounds, when completed, would be roughly equal to the estimates. The report

claimed that the resulting savings from the shutdown of bases and facilities during

BRAC’s 1988-1995 rounds would exceed initial estimates. More specifically, DOD

expected net total savings of about $14 billion through 2001. Annual savings,

thereafter, were estimated at $5.6 billion. These figures were later revised upward

by the Department of Defense and General Accounting Office.17

The two new rounds of closures in 2001 and 2005 sought by the Pentagon were

expected to produce, after implementation, additional savings of about $3 billion a

year. As required by Congress in Section 2824, both CBO and GAO were to review

and comment on the accuracy and reliability of the report’s findings. Other

significant features of the base closure report included: (1) a recommendation by

DOD to apply the model of previous independent base closure commissions for the

two rounds proposed for 2001 and 2005; and (2) a statement touting the successful

economic recovery from base closures of many impacted communities.

A subsequent Air Force memo (April 26) added fuel to the controversy over

base closures. The memo reportedly cited John D. Podesta, the White House deputy

chief of staff, as having tried through a DOD official, to encourage Lockheed Martin

Corporation to go after some of the depot maintenance work at McClellan Air Force

Base and keep the work in Sacramento.18 Members adamantly opposed to keeping

depot maintenance work at both McClellan AFB and Kelly AFB accused the

Administration of continuing to meddle in the base closure process. The level of

suspicion increased, as did the level of rhetoric, with Members issuing forceful

16

U.S. Department of Defense. The Report of the Department of Defense on Base

Realignment and Closure, April 1998, 144 p.

17

U.S. General Accounting Office. Military Base Closures: Progress in Completing Actions

from Prior Realignments and Closures, April 2002, p. 8-11.

18

“USAF Officials Backtrack on Depot Comments,” Defense News, June 8-14, 1998, p. 8.

CRS-7

statements in opposition to new base closures, such as “dead on arrival,”“smoking

gun,” and “over my dead body.”19

Reaction on Capitol Hill to the April 2, 1998 report’s call for two new base

closure rounds was similar to that of the previous year -- strong and widespread

resistance. The House National Security Committee remained broadly opposed to

any closings in the near future. This degree of opposition was mirrored also in the

House as a whole. The Senate Armed Services Committee was more evenly divided

on the issue than the House committee. In its mark-up session, the Senate committee

defeated by a 10-8 margin a proposed new round of base closures in 2001 (press

release dated May 8, 1998). Senator John McCain and Senator Carl Levin, principal

co-sponsors of new BRAC legislation the previous year (as well as in 1997),

indicated that they were prepared, however, to seek support for passage of a floor

amendment during Senate consideration of the FY1999 defense authorization bill (S.

2057/S. 2060). In the end, with sentiment of the majority clearly running against

them, the Senators abandoned their initiative.20

In floor action (June 25), the Senate voted 48-45 in support of an amendment

to the FY1999 defense authorization bill that would have made it more difficult for

the Pentagon to move ahead with base closings. Amendment No. 2981, sponsored

by Senator James Inhofe, would have restricted the Administration from closing

bases with 225 or more civilian personnel (a reduction from the current threshold of

300 set in law). It would also have restricted the Pentagon from realigning bases

with 750 civilian personnel, or more than “40% of the total number of civilian

personnel authorized to be employed at such military installation.” Further, the

amendment would have prevented the Pentagon from closing a base within four

years after completing a realignment of such base. The intent of this provision was

to delay, if not block, the Department of Defense from quickly moving to close a

particular base by reducing the number of civilian employees to less than 225. In

addition, the Inhofe amendment expressed congressional opposition to any new

rounds of closures and realignments until all actions from previous rounds had been

completed.

The Inhofe amendment was dropped from the FY1999 defense authorization bill

during conference.

19

Bradley Graham, “Air Force Memo Inflames Debate over Politics in Base Closings,”

Washington Post, May 3, 1998, p. A9; also, George C. Wilson, “Cohen Finding It Difficult

to Take the Hill for Clinton,” Legi-slate News Service, May 15, 1998.

20

Steven Lee Myers, “Senate Panel Votes No on Military Base Closings,” New York Times,

May 8, 1998.

CRS-8

CBO and GAO Assessments

The Congressional Budget Office submitted its review of DOD’s base

realignment and closure report on July 1, 1998.21 It stated that the report provided

most, but not all, of the information that the Congress had requested. It found

DOD’s estimates of savings from previous closure rounds, as fully implemented,

consistent with its own estimates: $5.6 billion as compared to $5 billion. However,

CBO explained that the firm measures of BRAC savings requested by the Congress

“do not -- and cannot exist.” It elaborated, as follows:

BRAC savings are really avoided costs -- costs that DOD would have incurred

if BRAC actions had not taken place. Because those avoided costs are not actual

expenditures, DOD cannot observe them and record them in its financial records.

As a result, DOD can only estimate savings rather than actually measure them.

In its review, CBO observed that DOD’s report had provided a clear and

coherent summary of why future base closure rounds would produce significant

savings. It noted, however, that DOD provided “little analysis of those data or

insight into the number and types of installations that might be closed in the event

of future BRAC rounds.” Other significant CBO findings included:

An analysis of the likely impact of future base closures on local communities

cannot be attempted until the specific communities are identified; even then, it

would be very difficult to do.

DOD was unable to locate some of the requested data, including the original cost

and savings estimates that it gave to the BRAC commissions.

Estimates of BRAC costs and savings would be more accurate if they included

[DOD’s] environmental and caretaker costs for some bases after the six-year

implementation period is over.

The General Accounting Office submitted its review of DOD’s report on

November 13, 1998.22 It was longer and provided more supporting detail than the

CBO review. GAO gave DOD generally good grades. It said that, overall, DOD had

provided most of the information required by Section 2824. GAO affirmed that the

four previous BRAC closure rounds would result in substantial net savings. It noted,

however, that “DOD’s report should be viewed as providing a rough approximation

of costs and savings rather than precise accounting.” It pointed out that “DOD’s data

systems do not capture all savings associated with BRAC actions, nor has DOD

established a separate system to track BRAC savings.” Other significant GAO

findings included:

DOD’s analysis of operational and readiness indicators has shown no long-term

problems affecting military capabilities that can be related to BRAC actions.

This general conclusion is also consistent with our prior work.

21

U.S. Congressional Budget Office. Review of the “Report of the Department of Defense

on Base Realignment and Closure,” July 1998, 7 p.

22

U.S. General Accounting Office. Military Bases: Review of DOD’s 1998 Report on Base

Realignment and Closure, November 1998, 54 p.

CRS-9

DOD’s report emphasizes that communities affected by prior BRAC actions

appear to be rebounding economically. We also have found this to be the case,

although our work also shows that some communities are faring better than

others.

DOD’s report suggests that proposed BRAC rounds in 2001 and 2005 would be

conducted like prior rounds. DOD’s legislative proposal requesting authority to

conduct two additional BRAC rounds provides a good starting point for

considering future legislation, should the Congress decide to authorize additional

rounds.

Closures and the 106th Congress

A “front-burner” issue for Congress at the outset of the 106th Congress was

whether to authorize a new round of base closings. At a November 1998 American

Bar Association symposium on national security, the general counsel of the Senate

Armed Services Committee predicted that: “There will be a significant attempt to put

BRAC in the FY2000 authorization bill, which may well succeed.”23 On January 20,

1999, Senator John McCain, along with Senator Carl Levin, sponsored a bill (S. 258)

calling for two new rounds in 2001 and 2003. In support of the bill, Senator McCain

pointed to the 23% excess capacity in infrastructure claimed by DOD, and said that

it was “unconscionable” for anyone to avoid looking at the billions of dollars to be

saved by closing and realigning more bases.24 In an effort to win support, he and his

cosponsors offered two significant changes in the law. First, the whole BRAC

selection process would begin and finish two months later in calendar year 2001 than

in previous rounds. It would give a new President the opportunity to nominate

members of a base closure commission. Second, privatization-in-place would not

be permitted in closing installations unless the new base closure commission

explicitly recommended it.

Secretary of Defense William Cohen stressed, at almost every opportunity

during the early part of the year, the importance of further base closures. In speaking

to the Illinois legislature on January 28, 1999, he stated that the most politically

challenging aspect of his effort to improve DOD efficiency and save money was

base closures. He said:

I know that BRAC is now seen as a four-letter word, but I must tell you that the

vast sums of money we waste on unneeded facilities is robbing our men and

women in uniform of needed training, modern weapons, and a better quality of

life. .... The two additional rounds we will fight for this year will ultimately save

$20 billion [during implementation] and generate $3 billion annually [thereafter].

Despite such appeals, many Members of Congress remained opposed to new

rounds, at least for the time-being, because of widespread fear among constituents

over such closings. This was underscored in hearings on February 2 before the

23

Inside the Pentagon. “Armed Services Committee to Tackle Readiness, BRAC in Next

Congress,” November 19, 1998, p. 15.

24

U.S. Government Printing Office. Congressional Record, May 25, 1999, p. S5940-S5973.

CRS-10

House Armed Services Committee (formerly, House National Security Committee),

when Secretary of Defense Cohen’s call for two more closure rounds reportedly

received a cool response. More ominously, from the Pentagon’s perspective, the

Senate Armed Services Committee voted on May 12 and 13 against authorizing any

new rounds of closings during its mark-up of the FY2000 defense authorization bill

(S. 1059). On May 26, the full Senate rejected a last-ditch effort by Senator John

McCain and Senator Carl Levin to revive their base closure initiative during floor

debate and passage of the defense bill. The 60 to 40 vote marked the third year in

a row that DOD’s attempt to win support in the Senate to shut down more bases had

been blocked. With opposition to base closures even stronger in the House, most

observers believed that DOD’s high priority initiative had been effectively quashed

for the remainder of the year -- if not longer.

In the second session of the 106th Congress, the Administration’s FY2000 DOD

budget proposal sought authority to close more military bases in the years 2003 and

2005. Deputy Defense Secretary John Hamre emphasized that it was a particularly

opportune time for Congress to take the initiative since the national economy was

so strong.25 In an effort to win the support of Congress, Secretary of Defense Cohen

said that the base closing process needed to be improved -- that there were too many

bureaucratic obstacles in the transition to private use of a closed base. Also, he

contended that the failure to close more bases would cost the Pentagon as much as

$20 billion that could be better spent on upgrading and building new weapon

systems, as well as increasing the performance levels of U.S. fighting forces. He

also pledged that politics would not be permitted to intrude in any future base closure

rounds.26

Congress, however, chose not to authorize any new rounds of closures in the

year 2000. In floor debate, on June 7, 2000, the Senate defeated an amendment to

the FY2001 defense authorization bill, once again sponsored by Senator McCain and

Senator Levin. The amendment, which would have authorized two new rounds in

2003 and 2005, was rejected by a vote of 63 to 35. The positions of the opposing

sides in the debate reflected the same concerns expressed in previous years.

Closures and the 107th Congress

In the early stages of the 107th Congress, one of DOD’s top agenda items was

securing authority for additional military base closures and realignments. On

February 27, 2001, Senator Carl Levin and Senator John McCain introduced a bill

(S. 397) to authorize two new rounds of base closures in 2003 and 2005. The

Taxpayers for Common Sense (TCS), a national budget watchdog organization,

immediately applauded the initiative and said in a February 27 press release that the

initiative “would save billions for other important defense priorities.” It estimated

the cost of maintaining excess military bases at about $3.6 billion each year and said

25

Robert Burns, “Clinton to Seek More Base Closings,” Associated Press, January 18, 2000.

26

Larry Favinger, “Clinton Seeks Base Closings,” Portsmouth Herald, January 19, 2000.

CRS-11

that projected Pentagon savings could amount to as much as $21 billion through

2015 if the military were allowed to close bases in 2003 and 2005.27

Senator Kay Bailey Hutchison, however, expressed a different point of view in

an Austin TX editorial article.28 She noted a trend toward increasing restrictions on

U.S. military training in locations abroad, such as Germany, Okinawa, Korea, and

Puerto Rico, and she suggested that it “cast into doubt the wisdom of prematurely

closing more domestic military bases.” She also drew attention to the fact that some

BRAC decisions, such as at Reese Air Force Base, TX, and Fort Hood, TX, are now

regarded as having been mistakes. In the case of the latter installation, the BRAC

decision has been essentially reversed.

On June 27, 2001, the Department of Defense urged Congress to approve

another round of base closures and realignments. It noted that the DOD’s military

infrastructure had an excess capacity of approximately 25%.29 Later, on August 2,

2001, the Pentagon outlined its proposal in greater detail. It called for a single, new

round of base closings and consolidations, beginning in 2003. The term “BRAC”

was dropped and replaced by a new title called the “Efficient Facilities Initiative of

2001 (EFI).”30

It also introduced a new approach for reducing excess infrastructure, based on

the experience of Brooks Air Force Base, San Antonio, TX. As a demonstration

project, approved by Congress, Brooks AFB was permitted to transfer its property

to the local community. In turn, the city leased back to the base commander property

that the service needed to continue its mission. Other details of DOD’s base closure

and realignment proposal conformed, in most respects, to the base-closure laws of

past years.

In the Senate Armed Services Committee, Members grappled with the two base

closure proposals -- S. 397 and the Administration’s plan. They ultimately agreed

upon, and recommended, a series of provisions incorporating elements of both.

Meeting in closed session on September 6, 2001, the committee voted 17 to 8 for a

new round.

On September 25, 2001, the full Senate approved a new round of base closures

and realignments in 2003 by a margin of 53 to 47 – after an effort by Senator Jim

Bunning to shelve the proposal failed. It was, for the Senate proponents of base

closure, their first success in 5 years of effort. Immediately prior to the vote, General

Henry H. Shelton had sent a letter to Senator John Warner, ranking Republican on

the Armed Services Committee, stating that the country “cannot afford the costs

27

New Base Closure Bill Could Save Taxpayers over $20 Billion, Taxpayers for Common

Sense, February 27, 2001.

28

Senator Kay Bailey Hutchison, “Asking the Right Questions on Military Readiness,”

Austin-American Statesman, March 29, 2001.

29

Katherine McIntyre Peters, “Administration Seeks Base Closings, Budget Boost,”

Government Executive, June 28, 2001.

30

U.S. Department of Defense, Special Briefing on Proposed Legislation for an Additional

Round of Base Closures, August 2, 2001.

CRS-12

associated with carrying this excess infrastructure.”31 In a separate letter, Secretary

of Defense Rumsfeld stressed that the current struggle with terrorist groups made it

all the more “imperative to convert excess capacity into war-fighting ability.”32

Opponents of the proposal, however, argued that the current war on terrorism,

coupled with an uncertain economy, made it the worst time to start closing bases.

Minority Leader Trent Lott said: “At a time our reserves are being called up to

support our military ... we’re going to say, ‘Oh, by the way, we’re going to look at

closing your base. I think the timing is not good.’”33

Supporters of the initiative, on the other hand, emphasized the importance of

putting aside home-state interest in favor of making certain the military enjoyed the

full range of resources needed to combat terrorism. Senator John McCain asserted:

“This is the time we should place our trust in the Commander-in-Chief and the

Secretary of Defense and the Chairman of the Joint Chiefs of Staff.”34

No base-closing language was included in the House of Representatives

FY2002 defense authorization bill. Indeed, shortly following passage of the Senate

bill, Representative James Hansen reportedly stated that the House would oppose the

Senate’s provision: “We’re going to hang tough.”35

In conference, the House and Senate leaders stood by their respective positions,

while resolving most of the other issues on their agenda. The stalemate over base

closures lasted for several weeks, holding up passage of S. 1438. In the absence of

a compromise, Senator John McCain reportedly warned that the President might veto

the defense bill.36 Senior negotiators finally agreed to a compromise on December

10, and unveiled it to the public on December 12, 2001. The President signed the

defense authorization bill (P.L. 107-107) on December 28, 2001.

The conference report retains most of the former 1990 BRAC Act language, but

makes some important changes and modifications that are set forth below.37

31

U.S. Government Printing Office. Congressional Record, September 25, 2001, p. S9764.

32

Ibid., p. S9766

33

Ibid., p. S9767.

34

Ibid., p. S9765.

35

(name redacted), “Defense Conferees Face Sharp Division over Base Closings,”

CQ Weekly,

October 6, 2001, p. 2349.

36

Helen Dewar, Base-Closing Issue Delays Defense Bill, Washington Post, December 1,

2001, p. 5.

37

See, also Table 1: 2005 BRAC Timeline, below.

CRS-13

Congress (Sec. 3001)

(1)

Extend the authority of the 1990 base closure and realignment act to authorize

one new round in 2005

Secretary of Defense (Sec. 3002)

(1)

Submit a force structure plan to include detailed information on end strength and

force levels, etc.

(2)

Submit (at Sec/Def’s discretion) revised force structure plan with FY2006 budget.

(3)

Review all types of installation and take into account anticipated need for, and

availability of, overseas bases in future.

Include:

(a)

(b)

(c)

inventory of military installations

description of categories of excess infrastructure

economic analysis of options for eliminating or reducing excess

infrastructure, including efficiencies from joint use

(4)

Certify (after submitting force structure plan and infrastructure inventory)

whether need exists for closure and realignment. If so, certify that it would

provide annual net savings within 6 years. If Sec/Def fails to provide

certification, the process is terminated.

(5)

Ensure that military value is the primary consideration in the making of

recommendations for closing or realigning military installations.

Commission (Sec. 3003-3004)

(1)

Increase number of members from 8 to 9.

(2)

Permit Sec/Def to testify before commission on any commission-proposed

addition of a base. Decision to add a base must be supported by at least 7

commissioners. Also, Sec/Def must also be given opportunity to testify on other

changes proposed by commission.

(3)

Prohibit privatization-in-place of closed or realigned bases prohibited, unless

specifically recommended by commission and determined to be the most costeffective option.

CRS-14

Conclusion

In May 1997, two years after the 1995 base closure commission completed its

task, the Department of Defense announced that two further closure rounds were

needed in 1999 and 2001 in order to reduce its excess infrastructure. The proposal

met with little enthusiasm on the part of most Members of Congress. Subsequent

appeals by Secretary of Defense Cohen in 1998, 1999, and 2000 fared no better. In

2001, however, Secretary of Defense Rumsfeld succeeded in winning approval from

Congress for a new round. He had to settle, however, for a round in 2005, rather

than his preferred date of 2003.

As a result of the new BRAC, many communities next to military bases are

worried about the survival of their installations. Various strategies have been

developed, both defensive and offensive. First, and foremost, community leaders are

working diligently to keep their military units/functions at home. On the other hand,

they are not averse to acquiring units/functions from other parts of the country. In

the latter case, success would almost certainly ensure a base’s survival in the next

round.

A serious concern of many communities near military bases is the growing

impact of “range encroachment” – the process whereby bases are progressively

hemmed in by urban growth, competition for air space, protection of endangered

species, and other factors that may detract from a base’s desirability to the

Department of Defense or the BRAC commission. If allowed to continue unabated,

such encroachment can have the effect of de-valuing installations to the point that

they may become prime candidates for closure in 2005.

CRS-15

Table 1. 2005 BRAC Timeline

Sec/Def sends initial selection criteria to defense committeesa

December 31, 2003

Sec/Def sends final selection criteria to defense committees;

publishes criteria in Federal Register

February 16, 2004

Criteria final, unless disapproved by Act of Congress

March 15, 2004

President forms new BRAC Commission; sends nominees to

Senateb

March 15, 2005

Sec/Def sends closure/realignment list to Commission/defense

committees

May 16, 2005

GAO reviews DOD’s list; reports findings to

President/defense committees

July 1, 2005

Commission sends its findings and recommendations to

President

September 8, 2005

President reviews Sec/Def’s and Commission’s list of

recommendationsc

September 23, 2005

Commission may submit revised list in response to President’s

review

October 20, 2005

President certifies closure/realignment list (or process is

terminated)d

November 7, 2005

Work of the closure/realignment Commission must be

terminated.

April 15, 2006

Source: U.S. Congress. House of Representatives, National Defense Authorization

Act for Fiscal Year 2002, Conference Report (H.Rept. 107-333), December 12, 2001,

p. 331-341 and 792-795.

a

Also, Sec/Def publishes criteria in Federal Register.

If President does not send nominations by required date, process is terminated.

c

President prepares report containing approval or disapproval.

d

Congress has 45 days to pass motion of disapproval, or Commission’s list becomes

law.

b

EveryCRSReport.com

The Congressional Research Service (CRS) is a federal legislative branch agency, housed inside the

Library of Congress, charged with providing the United States Congress non-partisan advice on

issues that may come before Congress.

EveryCRSReport.com republishes CRS reports that are available to all Congressional staff. The

reports are not classified, and Members of Congress routinely make individual reports available to

the public.

Prior to our republication, we redacted names, phone numbers and email addresses of analysts

who produced the reports. We also added this page to the report. We have not intentionally made

any other changes to any report published on EveryCRSReport.com.

CRS reports, as a work of the United States government, are not subject to copyright protection in

the United States. Any CRS report may be reproduced and distributed in its entirety without

permission from CRS. However, as a CRS report may include copyrighted images or material from a

third party, you may need to obtain permission of the copyright holder if you wish to copy or

otherwise use copyrighted material.

Information in a CRS report should not be relied upon for purposes other than public

understanding of information that has been provided by CRS to members of Congress in

connection with CRS' institutional role.

EveryCRSReport.com is not a government website and is not affiliated with CRS. We do not claim

copyright on any CRS report we have republished.