Data Centers and the Electricity Grid: Frequently Asked Questions

Congressional research reportSep 1, 2026

Ask Donna

What actually matters in this document.

Text

Data Centers and the Electricity Grid:

Frequently Asked Questions

September 1, 2026

Congressional Research Service

https://crsreports.congress.gov

R49326

SUMMARY

Data Centers and the Electricity Grid:

Frequently Asked Questions

A data center is a physical facility that houses computer systems for managing and transmitting

data. The federal government has been pursuing policies to promote data center development,

particularly as a primary component of artificial intelligence (AI), a “critical and emerging

technology” with enormous data storage and processing requirements. Data centers require large

quantities of electrical power. To date, data centers have generally secured power from their local

electric utilities, utilizing existing transmission and distribution infrastructure (i.e., the grid).

Many observers anticipate a need for new power plants and grid infrastructure to meet the needs

of data centers in addition to other growing sources of electricity demand. The anticipated pace

of U.S. electricity demand growth exceeds that of the last 20 years, raising questions of whether

existing regulatory requirements and processes are suited for such development.

R49326

September 1, 2026

Ashley J. Lawson

Specialist in Energy Policy

Paul W. Parfomak

Specialist in Energy Policy

Martin C. Offutt

Analyst in Energy Policy

Congress has an ongoing interest in the development of data centers, generally, and their impacts

on the electricity grid, specifically. Hearings in the 119th Congress have examined data center and grid-related issues.

Ensuring data centers do not raise costs or affect grid reliability for other electricity consumers, especially residential

consumers, has been a focus of legislative activity in the 119th Congress. This report discusses frequently asked questions

about data center electricity use, the potential impacts of data center growth on the electric grid, and government actions

related to data center development. This report is intended as an introduction to data center electricity issues and does not

provide in-depth coverage of all data-center- and electric-grid-related issues. CRS has several other published products that

may be helpful in further examining specific data-center-related energy policy issues.

Congressional Research Service

Data Centers and the Electricity Grid: Frequently Asked Questions

Contents

Introduction ..................................................................................................................................... 1

Frequently Asked Questions ............................................................................................................ 1

What are data centers and how do they use electric power? ..................................................... 1

What is the electricity grid and how is it regulated? ................................................................. 2

How do data centers get their electric power? .......................................................................... 4

How much electric power will data centers need? .................................................................... 5

What types of electricity generation are preferred for data centers? ......................................... 6

What is the federal role in permitting electricity infrastructure for data centers? ..................... 7

What are the requirements for interconnecting power plants to the grid? ................................ 7

What is data center flexibility and how does it affect the grid? ................................................ 8

Can data centers provide benefits to the grid? .......................................................................... 9

How have data centers affected electricity prices? ................................................................. 10

Where is data center growth happening? ................................................................................. 11

Can data centers cause blackouts? .......................................................................................... 12

What has the federal government been doing about data centers and the grid?...................... 13

What have states been doing about data centers and the grid? ............................................... 14

What has Congress been doing about data centers and the grid? ............................................ 15

Additional Resources .................................................................................................................... 16

Figures

Figure 1. Regional Transmission Organizations and Independent System Operators ..................... 3

Figure 2. Standalone Data Center Electricity Use by State in 2024 ............................................... 11

Figure 3. Projected Standalone Data Center Electricity Use by State in 2030 .............................. 12

Contacts

Author Information........................................................................................................................ 17

Congressional Research Service

Data Centers and the Electricity Grid: Frequently Asked Questions

Introduction

A data center is a physical facility that houses computer systems for managing and transmitting

data. The federal government has been pursuing policies to promote data center development,

particularly as a primary component of artificial intelligence (AI), a “critical and emerging

technology” with enormous data storage and processing requirements.1 Data centers require large

quantities of electrical power. To date, data centers have generally secured power from their local

electric utilities. Reportedly, some utilities are experiencing infrastructure constraints and cannot

accommodate new data center requests until new grid infrastructure—power plants, transmission

facilities, and distribution facilities—is built. Typically, building grid infrastructure takes several

years longer than building data centers. Many observers in the technology industry and their

supporters, including the Trump Administration, see grid infrastructure constraints as a hurdle to

U.S. competitiveness in new technologies like AI.2

Opposition has been growing, especially at the local level, to construction of new data centers. A

key point of debate is the need for new grid infrastructure and whether this buildout might lead to

higher electricity prices for other customers. This report addresses frequently asked questions

about data center electricity use, the potential impacts of data center growth on electricity prices

and grid reliability, and government actions related to data center development.

Frequently Asked Questions

What are data centers and how do they use electric power?

A data center is a physical facility housing computer servers, data storage devices, and network

equipment that can provide information technology (IT) infrastructure services for storing,

managing, processing, and transmitting large amounts of data.3 Different types of data centers are

based on their ownership or intended purposes. For example, a large company may choose to

build an on-premises data center to house and manage its own IT infrastructure.4 Other, typically

smaller, organizations often choose to rent space, equipment, or services within a colocation data

center owned and operated by another company.5

The increasing demand for data storage and processing capacities, especially for computational

tasks such as AI deployment, has led to the development of “hyperscale” data centers notable for

their size.6 Hyperscale data centers contain at least 5,000 computer servers and occupy at least

1 National Science and Technology Council, Critical and Emerging Technologies List Update, February 2024,

https://www.govinfo.gov/content/pkg/CMR-PREX23-00185928/pdf/CMR-PREX23-00185928.pdf. The report states

that “[c]ritical and emerging technologies (CETs) are a subset of advanced technologies that are potentially significant

to U.S. national security” and lists artificial intelligence (AI) among CETs. See pages 1-2.

2 See, for example, remarks of Secretary of Energy Chris Wright to attendees of the Special Competitive Studies

Project’s AI Expo, at C-SPAN, “Energy Secy. Wright Warns Failure to Overhaul Electric Grid System Could Slow

Down AI,” May 7, 2026, https://www.c-span.org/clip/public-affairs-event/energy-secy-wright-warns-failure-tooverhaul-electric-grid-system-could-slow-down-ai/5199999.

3 For more discussion on data centers and their role in AI development and deployment, see CRS In Focus IF12899,

Data Centers and Cloud Computing: Information Technology Infrastructure for Artificial Intelligence, by Ling Zhu.

4 Equinix, “What Is a Data Center? What Are Different Types of Data Centers?,” August 1, 2024,

https://blog.equinix.com/blog/2022/10/13/what-is-a-data-center-what-are-different-types-of-data-centers/.

5 Stephanie Susnjara and Ian Smalley, “What Is a Data Center?,” IBM, https://www.ibm.com/think/topics/data-centers.

6 Phill Powell and Ian Smalley, “What Is a Hyperscale Data Center?,” IBM, https://www.ibm.com/think/topics/

hyperscale-data-center.

Congressional Research Service

1

Data Centers and the Electricity Grid: Frequently Asked Questions

10,000 square feet of physical space, although they can be much larger—some occupying a

million square feet or more.7

Data centers use electricity to run their computers and the systems that cool them. Roughly half

of data center electricity demand stems directly from operating electronic IT equipment.8 Because

IT equipment generates heat as it operates, data centers require extensive cooling systems to

maintain IT system stability and performance. These cooling systems typically account for

another 40% of electricity consumption in a data center.9 Lighting, security systems, power

distribution losses, and other facility systems account for the rest of data center electricity

demand.

What is the electricity grid and how is it regulated?

Electricity grid is a term commonly used to refer to the U.S. electricity system. The grid is made

up of three distinct but interrelated systems for generation, transmission, and distribution of

electricity.10 The generation system consists of the power plants that generate electricity using a

variety of energy sources across the country. The transmission system consists of high-voltage

(rated above 100 kilovolts) power lines and associated equipment that move power across long

distances. The distribution system consists of low-voltage power lines and associated equipment

that makes final delivery of electricity to most homes and businesses.

In the early 1900s, the states passed laws granting monopoly franchises to electric utilities such

that only a single utility could sell electricity in a defined service territory. Under this regulatory

compact, the utilities must have their rates approved by a state regulator and they must provide

universal service.

Originally, most utilities were vertically integrated—that is, they owned and operated all the

generation, transmission, and distribution infrastructure required to serve their customers. Due to

state and federal policy changes late in the 20th century, in many parts of the United States, the

electricity industry has transitioned (restructured) to a business model in which power generation

is competitive. Even when companies compete for generation, the transmission and distribution

functions remain primarily operated by monopoly utilities regulated by state or local regulators.

In regions with restructured electricity industries, competitive markets largely set the wholesale

price of power.

The U.S. electricity market regions are shown in Figure 1. The markets are composed of regional

transmission organization (RTO) and independent system operator (ISO) areas, each serving

multiple, interconnected utility service territories. PJM is the nation’s largest electric grid

operator, managing the electricity transmission system for more than 65 million people in all or

7 Powell and Smalley, “What Is a Hyperscale Data Center?”; VIAVI Solutions, “What Is a Hyperscaler?,”

https://www.viavisolutions.com/en-us/what-hyperscaler.

8 A. Shehabi et al., 2024 United States Data Center Energy Usage Report, Lawrence Berkeley National Laboratory

(LBNL), LBNL-2001637, December 2024, p. 47.

9 Karthik Ramachandran et al., “As Generative AI Asks for More Power, Data Centers Seek More Reliable, Cleaner

Energy Solution,” Deloitte, November 9, 2024, https://www.deloitte.com/us/en/insights/industry/technology/

technology-media-and-telecom-predictions/2025/genai-power-consumption-creates-need-for-more-sustainable-datacenters.html.

10 For additional discussion, see CRS Report R47521, Electricity: Overview and Issues for Congress, by Ashley J.

Lawson.

Congressional Research Service

2

Data Centers and the Electricity Grid: Frequently Asked Questions

part of 13 states and the District of Columbia.11 What consumers ultimately pay for electricity is

based on auctions among competing generators bidding to provide electricity in these markets.

Figure 1. Regional Transmission Organizations and Independent System Operators

Source: Federal Energy Regulatory Commission (FERC), “RTOs and ISOs,” https://www.ferc.gov/power-salesand-markets/rtos-and-isos.

Notes: FERC does not regulate the electricity industry in Alaska, Hawaii, or U.S. territories. CAISO = California

Independent System Operator; SPP = Southwest Power Pool; ERCOT = Electric Reliability Council of Texas;

MISO = Midcontinent Independent System Operator; PJM = PJM Interconnection; NYISO = New York

Independent System Operator; ISO-NE = ISO New England. Regional transmission organizations and

independent system operators do not operate electricity systems in the Northwest, Southwest, or Southeast.

RTO and ISO rules are under Federal Energy Regulatory Commission (FERC) jurisdiction,

except for the Electric Reliability Council of Texas (ERCOT).12 Wholesale rates for electricity

transmission are set by FERC and are generally directly passed through into retail rates. The retail

rate consumers pay is the sum of wholesale generation costs plus transmission and distribution

costs, and any other costs approved by the state or local utility regulator (e.g., costs associated

with low-income bill assistance or environmental programs). While FERC is largely responsible

for regulation of the interstate transmission system and wholesale power markets, regulation of

the distribution function of the electric power business is still largely carried out by state or local

authorities.

11 For more details about PJM, see CRS Report R48553, PJM’s Electric Capacity Market: Background and Current

Issues, by Ashley J. Lawson. The PJM states are Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New

Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, and West Virginia, plus the District of Columbia.

12 Pursuant to the Federal Power Act, the Federal Energy Regulatory Commission (FERC) has authority over wholesale

electricity transactions in interstate commerce. The transmission system throughout most of Texas does not exchange

electricity with neighboring states, so FERC’s authority does not extend to that region. For additional discussion on

FERC’s authority over electricity rates, see CRS In Focus IF11411, The Legal Framework of the Federal Power Act,

by Adam Vann, and CRS Report R48349, The Federal Energy Regulatory Commission (FERC): Authorities and

Membership, by Paul W. Parfomak.

Congressional Research Service

3

Data Centers and the Electricity Grid: Frequently Asked Questions

How do data centers get their electric power?

Data centers have three main options for getting electric power. First, they can buy electricity

directly from the local utility; this is the most common scenario. A data center that purchases

from the local utility receives the same electricity as other retail customers, sourced from the

same mix of power plants and carried on the local utility’s power lines. Buying electricity from

the local utility is the preferred option for most data center developers and is expected to remain

so for the foreseeable future.13 Data center owners who prefer this option typically choose to

locate their facilities in areas with more readily available existing utility electricity supply.

A second option for a data center developer is to enter into a power purchase agreement (PPA)

with a specific power plant. The power plant may be located near the data center or far from it. In

either case, the power plant delivers electricity onto the grid, and (in a separate transaction) the

data center receives electricity from the grid. PPAs can also include terms for the acquisition of

the renewable attributes of the power plant, where applicable.14 Some data center owners or users

procure these renewable attributes as part of their corporate sustainability goals.15

A third option for data center developers is to self-supply electricity by buying or building

behind-the-meter power plants, also referred to as behind-the-meter generation.16 This

arrangement is sometimes called “bring your own power” (BYOP) or “bring your own

generation” (BYOG). In this case, the electricity generated by the power plant is delivered

directly to the data center without using the utility’s electric grid.17 Such power plants may be

colocated with the data center on the same site, or they may be offsite adjacent to the data center,

connecting to them via dedicated power lines. Some behind-the-meter power plants can be

configured in such a way that allows electricity to flow back to the grid. This configuration could

allow data centers to sell electricity to the local utility when the electricity is not needed for data

center operations; to support utility grid reliability; or to supply electricity in the event of a utility

electricity shortage. Behind-the-meter power plants may be owned and operated by the data

center itself or by a third party.

Which electricity supply option best meets the electricity needs of an individual data center

depends on several considerations, including the availability of grid power from the local utility,

whether the data center developer prefers a specific energy source to make the electricity, and

13 Michael Thomas, “Bypassing the Grid: How Data Center Developers Are Building Their Own Power Plants,”

Cleanview, https://cleanview.co/reports/behind-the-meter-data-centers. Based on a proprietary database of announced

data centers, the analysis found that only 25% of the planned data center capacity intended to use behind-the-meter

power sources. The analysis found that 2 gigawatts (GW) or 2.2% of the announced behind-the-meter power was

operational as of mid-2026.

14

An energy attribute conveys information about a unit of energy, including the resource used (e.g., solar power) to

create it and its associated emissions. For more details, see U.S. Environmental Protection Agency, “Energy Attribute

Certificates (EACs),” updated October 20, 2025, https://www.epa.gov/green-power-markets/energy-attributecertificates-eacs.

15 See, for example, Google, Environmental Report 2025, June 2025, p. 79, https://www.gstatic.com/gumdrop/

sustainability/google-2025-environmental-report.pdf. Google announced an “aim to run on 24/7 carbon-free energy on

every grid where we operate by 2030.”

16 Behind-the-meter is sometimes abbreviated in the industry as BTM.

17 Ian Fischer, “Behind-the-Meter Power Solutions: The Data Center Industry’s New Reality,” datacenterHawk,

February 19, 2026, https://datacenterhawk.com/resources/market-insights/behind-the-meter-power-solutions-the-datacenter-industry-s-new-reality.

Congressional Research Service

4

Data Centers and the Electricity Grid: Frequently Asked Questions

utility-specific requirements regarding behind-the-meter options. Reportedly, many data center

developers prefer to secure their electricity supplies in whatever way is fastest.18

The above discussion applies to the primary power source for data center operations. Data centers

also typically have backup generators on-site designed to operate in case of a grid outage. As is

the case for other electricity customers, any backup option is at the full expense of the data center

and is not operated by the utility. Whereas the primary power source for a data center might be

expected to run for most hours of the year, backup generation is expected to run a minimal

number of hours and primarily during emergency events.

How much electric power will data centers need?

Estimates of existing data center power demand vary, in part because comprehensive

consumption statistics are not available.19 Likewise, projections of future demand vary and are

uncertain, in large part due to uncertainty about future technology changes—both the adoption of

AI technology in the broader United States and the hardware and software used for AI and other

computational applications.

A 2026 Department of Energy (DOE) study examined the nationwide energy consumption of data

centers in response to direction by Congress in the Energy Act of 2020 (P.L. 116-260, Division Z,

Section 1003).20 The study found that U.S. data center annual electricity consumption in 2024

was approximately 4.7% of total U.S. consumption—192 terawatt-hours (TWh)—and was

projected to rise to 9.5%-15.3% of U.S. consumption by 2030, between 521 TWh and 843 TWh.21

A 2026 study by the Electric Power Research Institute (EPRI) projected data center electricity use

to rise to 9% to 17% of U.S. total electricity consumption in 2030, roughly 380 TWh to 790 TWh

according to their model.22 Other studies have projected similarly large growth in data sector

electricity demand.23

Some studies have suggested that current projections of future data center demand may be

overstated. One study, prepared for an environmental advocacy group, found “that data center

electricity demand projections remain highly uncertain and currently reflect a bias to

overestimating growth in the number of data centers that will be built, and therefore also

overestimating future electricity demand.”24 A May 2026 analysis from an investment bank found

18 Drew Robb, “Data Centers Bypassing the Grid to Obtain the Power They Need,” Data Center Knowledge, May 1,

2025, https://www.datacenterknowledge.com/energy-power-supply/data-centers-bypassing-the-grid-to-obtain-thepower-they-need.

19 See the section “Are there reports on the actual energy use of U.S. data centers?” in CRS Report R48646, Data

Centers and Their Energy Consumption: Frequently Asked Questions, by Martin C. Offutt et al.

20 Sarah Smith et al., United States Data Center Energy Usage Report: 2025 Update, LBNL, Energy Analysis Division,

June 2026, https://escholarship.org/content/qt33m6w3x0/qt33m6w3x0.pdf.

21 Smith et al., United States Data Center Energy Usage Report: 2025 Update, pp. 8-9. These estimates did not account

for cryptocurrency.

22 Electric Power Research Institute (EPRI), Powering Intelligence 2026: Updated Scenarios of U.S. Data Center

Electricity Use and Power Strategies, February 25, 2026, pp. 5-6, https://powering-intelligence.epri.com.

23 See, for example, International Energy Agency, Energy and AI, April 10, 2025, https://iea.blob.core.windows.net/

assets/de9dea13-b07d-42c5-a398-d1b3ae17d866/EnergyandAI.pdf; Alastair Green et al., “How Data Centers and the

Energy Sector Can Sate AI’s Hunger for Power,” McKinsey & Company, September 17, 2024,

https://www.mckinsey.com/industries/private-capital/our-insights/how-data-centers-and-the-energy-sector-can-sate-aishunger-for-power.

24 London Economics International LLC, Uncertainty and Upward Bias Are Inherent in Data Center Electricity

Demand Projections, prepared for Southern Environmental Law Center, July 7, 2025, p. 8, https://www.selc.org/wpcontent/uploads/2025/07/LEI-Data-Center-Final-Report-07072025-2.pdf.

Congressional Research Service

5

Data Centers and the Electricity Grid: Frequently Asked Questions

that “only about 50-60% of data center capacity scheduled for the next one to two years is

expected to come online on time amid delays and cancellations.”25 Other studies have projected

that even lower percentages of announced new data center capacity will be built.26 In May 2026,

the North American Electric Reliability Corporation (NERC) observed that grid operators in

many parts of the country revised their projections for electricity demand in the summer of 2026

downward, “to account for the observed rate of completion for large load interconnections and

the slower-than-expected pace at which some of those loads are coming on-line.”27 Despite these

lowered projections, NERC expected electricity demand at peak times to be 11 gigawatts (GW)

higher in 2026 than in 2025, largely due to data center demand growth.

What types of electricity generation are preferred for data centers?

Generation technologies being deployed for data centers via PPAs or behind-the-meter electricity

generation span fossil fuel-fired thermal power plants (e.g., natural gas turbines), renewable

generation (e.g., wind, solar, geothermal), nuclear power, fuel cells, and other types of energy

technology.28 There is no comprehensive, publicly available analysis of all generation projects for

existing and proposed data centers. However, an industry analysis based on limited data center

announcements and regulatory filings suggests that, where new on-site generation has been

proposed for data center projects, natural gas-fired turbines or engines have been the preferred

option, by far, followed by nuclear power and fuel cells.29 The extent to which these proposed

power plants will become operational remains to be seen.

In its 2026 Annual Energy Outlook, the U.S. Energy Information Administration (EIA) states that

“natural gas use for electric power generation by 2050 increases more than it does in any other

end-use sector,” largely due to data center expansion.30 Natural gas generation is reportedly

preferred because it is dispatchable and can be constructed relatively quickly—in one to three

years—depending on local permitting requirements and the availability of the required

equipment.31 Dispatchable generation can be turned on and off or otherwise adjusted whenever it

is needed to meet demand. Choosing natural gas for generation also depends on the availability of

adequate natural gas supplies through regional pipeline infrastructure or, in some cases, proximity

to natural gas production fields (e.g., the Permian Basin in Texas).32

25 Goldman Sachs, “US Data Center Power Demand Projected to Double by 2027,” May 20, 2026,

https://www.goldmansachs.com/insights/articles/us-data-center-power-demand-projected-to-double-by-2027.

26 See, for example, Gabriel Levin and Emily Forgash, “Most Power Sought for US Data Centers Will Never

Materialize, Analysts Say,” Bloomberg, August 12, 2026, https://www.bloomberg.com/news/articles/2026-08-12/mostelectricity-sought-for-ai-data-centers-in-us-will-never-materialize.

27 North American Electric Reliability Corporation (NERC), 2026 Summer Reliability Assessment, p. 1,

https://www.nerc.com/globalassets/our-work/assessments/nerc_sra_2026.pdf.

28 For examples of projects, see Table 1 in CRS Report R48762, Data Center Energy Infrastructure: Federal Permit

Requirements, by Paul W. Parfomak et al.

29

Data reported in Amy Harder, “The AI Boom Is Making Natural Gas Great Again,” Axios, February 4, 2026,

https://www.axios.com/2026/02/04/ai-natural-gas-power-data-centers, based on analysis (not publicly available) in

Michael Thomas, Bypassing the Grid: How Data Center Developers Are Building Their Own Power Plants,

Cleanview; an executive summary of Bypassing the Grid is available at https://cleanview.co/reports/behind-the-meterdata-centers.

30 U.S. Energy Information Administration (EIA), Annual Energy Outlook 2026, April 2026, p. 25,

https://www.eia.gov/outlooks/aeo/pdf/AEO_Narrative.pdf.

31 Will Gruver, “Gas Turbine Power Plant for Data Center in Texas: How Fast Can It Go Live?,” USP&E, October 2,

2025, https://uspeglobal.com/articles/gas-turbine-power-plant-for-data-center-in-texas/.

32 Bedrock, “How Is Natural Gas Powering Data Centers in the Permian Basin?,” June 23, 2026,

https://www.bedrockpcl.com/news/how-is-natural-gas-powering-data-centers-in-the-permian-basin/.

Congressional Research Service

6

Data Centers and the Electricity Grid: Frequently Asked Questions

What is the federal role in permitting electricity infrastructure for

data centers?33

Numerous federal, state, and local laws and regulations affect the permitting for grid

infrastructure, data center interconnection to the grid, and backup electricity facilities. As a result,

data centers in different states might face different sets of permitting requirements associated with

their access to power and environmental requirements.

Because an individual data center has a discrete footprint, permits for on-site energy

infrastructure typically fall under state and local jurisdiction. Power plants developed off-site to

serve data centers face the same permitting requirements as any other power plant. The permit

requirements are largely specific to individual projects and depend, among other things, on

location, the type of generation involved, and whether the power plant is grid-connected or

behind-the-meter.

The Federal Power Act (16 U.S.C. §§791 et seq.) reserves most authority for permitting and siting

of power plants to the states. Specific types of generation may require federal agency

authorizations from the Federal Energy Regulatory Commission (FERC), the Nuclear Regulatory

Commission, or the U.S. Army Corps of Engineers. Power plants developed on federal lands

typically require approval from the relevant land management agency or other executive agency

controlling those lands (e.g., Bureau of Land Management). In addition, energy infrastructure for

data center projects may require permits, approvals, or reviews under delegated federal authority

from state, tribal, and local agencies. Relevant requirements may fall under the Clean Air Act, the

Clean Water Act, the Safe Drinking Water Act, and the Coastal Zone Management Act. State

requirements under these statutes may apply more broadly to data center energy infrastructure

than federal agency requirements.

What are the requirements for interconnecting power plants to the

grid?

Since 2003, FERC has set requirements for the terms and conditions under which power plants

interconnect to the grid.34 A key aspect of this requirement is a technical study, known as an

interconnection study, that grid operators must conduct to determine whether a proposed new

power plant would pose reliability risks to the system. Power plant developers requesting to

interconnect to the grid are placed in an interconnection queue to wait their turn for an

interconnection study to be completed.

In 2023, FERC began implementing reforms to the interconnection study process aimed at

reducing the time to complete the process. Key aspects of the reforms, specified in Order No.

2023, are increased “readiness requirements” aimed at reducing speculative generation

interconnection requests and the use of “cluster studies” so that multiple proposed power plants

can be studied together. 35 Many observers believe that the Order No. 2023 reforms will accelerate

33 For details, see CRS Report R48762, Data Center Energy Infrastructure: Federal Permit Requirements, by Paul W.

Parfomak et al.

34 FERC, Standardization of Generator Interconnection Agreements and Procedures (Order No. 2003), July 24, 2003,

https://www.ferc.gov/sites/default/files/2020-06/order-2003.pdf. FERC’s regulations apply only to utilities subject to

its jurisdiction. Many utilities outside FERC’s jurisdiction nonetheless maintain similar procedures for interconnecting

new power plants.

35 FERC, Improvements to Generator Interconnection Procedures and Agreements, Order No. 2023, Docket No.

RM22-14-000, 184 FERC ¶ 61,054, July 28, 2023, https://www.ferc.gov/media/order-no-2023.

Congressional Research Service

7

Data Centers and the Electricity Grid: Frequently Asked Questions

the pace of power plant development, though other factors (e.g., permitting, financing) remain

important in determining how many new power plants become operational.

Separate from the Order No. 2023 reforms, FERC has approved “fast-track” interconnection

study processes for several other grid operators. These processes are aimed at addressing

concerns that growth in electricity demand—largely from data centers—will outpace supply in

the next few years. Under the fast-track processes, grid operators select a limited number of

power plant projects for accelerated interconnection study, regardless of when they were

announced (typically, projects are studied in order of announcement). Selected projects must meet

certain criteria, such as being “advanced projects of significant size” and being dispatchable (i.e.,

controllable by a grid operator).36

What is data center flexibility and how does it affect the grid?

For most hours of the year, the existing U.S. electricity system has sufficient electricity supply

and transmission capacity to accommodate new load growth. Load refers to electricity demand

and can be used to refer to either a volume of electricity sales or a number of electricity

customers. Utility planners design the system around the relatively few hours of the year with

peak electricity demand when the system is constrained—typically the hottest summer afternoons

and the coldest winter nights. New demand from data centers could potentially overwhelm the

grid’s capacity during these hours. Utilities review applications to interconnect new load to

identify potential reliability risks during peak hours. If a utility finds a risk, the new customer

must wait until new grid infrastructure is in place to reduce the reliability risk.

Some data centers have the technical potential to decrease their demand during peak demand

hours, either by pausing or slowing computational tasks or by switching to backup power

supplies. This behavior is known as flexibility, and electricity consumers that have flexibility are

known as flexible loads. Flexibility has multiple advantages to electricity customers. If data

centers were to implement this kind of flexible behavior, either through voluntary demand

response programs or mandatory requirements, they could potentially be connected to the grid

faster because they might not have to wait for grid infrastructure to be built.37 Also, avoiding the

need for new infrastructure could reduce the risk of electricity prices increases. Additionally, data

centers—or more specifically, their backup generators—could be utilized during peak demand

times to reduce blackout risks for other customers. Secretary of Energy Chris Wright has

encouraged grid operators to direct consumers like data centers to shift to backup power sources

“as a last resort” during grid emergencies.38

Because of these perceived advantages, increased flexibility has been identified as one potential

solution to the mismatch between electricity supply and demand growth.39 When data centers

agree to be flexible loads, demand during peak times is lower, reducing the need for new power

plants. For example, NERC found after accounting for flexibility that summer 2026 peak demand

36 FERC, Order Accepting Tariff Revisions, 95 FERC ¶ 61,197, June 9, 2026, https://www.pjm.com/-/media/DotCom/

documents/ferc/orders/2026/20260609-er26-1563-000.PDF.

37 Demand response programs typically compensate electricity customers for reducing their electricity demand when

their utility requests it, usually when utility electricity supplies are constrained.

38 Letter from Chris Wright, Secretary of Energy, to Reliability Coordinators and Balancing Authorities, January 22,

2026, https://www.energy.gov/documents/leveraging-backup-generation-facilities-during-energy-emergencies.

39 T. H. Norris et al., Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US

Power Systems, NI R 25-01, Nicholas Institute for Energy, Environment & Sustainability, Duke University, 2025,

https://nicholasinstitute.duke.edu/publications/rethinking-load-growth-assessing-potential-integration-large-flexibleloads-us-power.

Congressional Research Service

8

Data Centers and the Electricity Grid: Frequently Asked Questions

forecast in the ERCOT area40 is 3.7 GW (4.6%) lower than summer 2025 peak demand “because

more data centers can be curtailed by grid operators when needed to prevent grid emergencies.”41

Some data centers may have flexibility limitations, however. Google has stated that “[t]here are

limits to how flexible a given data center can be, since high levels of reliability are critical for

services like Search and Maps, as well as Cloud customers in essential industries like

healthcare.”42 Data centers may also be constrained for technical and operational reasons, such as

legacy software, limited grid analytic capability, and a lack of real-time markets for demand-side

energy resources.43

Can data centers provide benefits to the grid?

There are several ways data center development could potentially provide benefits to the electric

grid. Data centers with behind-the-meter generation could (subject to any local utility limitation)

export power to the grid to supply other customers, temporarily relieving utility generation

constraints.44 Groups of data centers in different electricity markets could also coordinate to shift

computational tasks to other regions when local electricity demand is higher.

Being able to shift workloads and their associated electricity demands in this way (spatial

flexibility), together with flexibility in the scheduling of peak workloads (as described in the

previous question), can potentially lower electricity costs for all customers by smoothing out

demand and avoiding the costliest peak generation supplies across markets.45 Data centers with

on-site energy storage systems could charge storage systems using “excess” electricity from the

grid, when available (e.g., midday when solar generation peaks), or using any electricity from

behind-the-meter generation that is in excess of what is needed to meet a data center’s current

demand. These energy storage systems could then discharge electricity to the grid when overall

demand is higher, increasing and improving the utilization of renewable generation in the

regional generation portfolio.46 Some advocates also see data center demand growth as an

opportunity to invest in modernizing and expanding the transmission grid.47

40 The Electric Reliability Council of Texas (ERCOT) manages approximately 90% of Texas’s electrical load and

serves 24 million customers.

41 NERC, 2026 Summer Reliability Assessment, May 2026, p. 8, https://www.nerc.com/globalassets/our-work/

assessments/nerc_sra_2026.pdf.

42 Michael Terrell, “How We’re Making Data Centers More Flexible to Benefit Power Grids,” Google blog, August 4,

2025, https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/how-were-making-data-centersmore-flexible-to-benefit-power-grids/.

43 Thomas W. Kirchstetter et al., “DOE Data Center Load Flexibility Workshop Summary,” LBNL, January 2025,

https://eta-publications.lbl.gov/sites/default/files/2025-03/

final_doe_data_center_load_flexibility_workshop_summary.v0307.pdf.

44 Christopher Tozzi, “How Grid-Safe Data Centers Can Help Ease the Power Crisis,” Data Center Knowledge, March

5, 2026, https://www.datacenterknowledge.com/energy-power-supply/how-grid-safe-data-centers-can-help-ease-thepower-crisis.

45 Evan Lerner, “How Data Center Flexibility Can Relieve Stress on the Western Grid,” University of Utah, June 16,

2026, https://attheu.utah.edu/science-technology/how-data-center-flexibility-can-relieve-stress-on-the-western-grid/.

46 Patrick Donovan, “The Rise of BESS: Powering the Future of Data Centers,” Schneider Electric Blog, May 1, 2024,

https://blog.se.com/datacenter/2024/05/01/the-rise-of-bess-powering-the-future-of-data-centers/.

47 See, for example, Jane Flegal, Seizing the Data Center Buildout for Grid Modernization, Searchlight Institute, March

9, 2026, https://www.searchlightinstitute.org/research/seizing-the-data-center-buildout-for-grid-modernization/.

Congressional Research Service

9

Data Centers and the Electricity Grid: Frequently Asked Questions

How have data centers affected electricity prices?

The price (rate) that retail customers pay for electricity is determined primarily by two factors:

the cost of generating electricity and the cost of delivering electricity to customers through the

grid.48 Utility regulators at the state or local level approve rates that reflect a utility’s cost for

these components. Rates typically change every few years in response to shifts in utility costs

over time. For example, if a utility invests in a new power plant or in upgrades to the grid, rates

might need to change to reflect those capital investments. Utility sales also affect rates. When

sales increase, a utility earns more revenue; conversely, when sales decrease, a utility earns less

revenue. If a utility’s revenue is less than its costs, rates might need to increase to compensate.

Conversely, if a utility’s revenue exceeds its costs, regulators might lower rates.

Researchers at Lawrence Berkeley National Laboratory (LBNL) have studied the extent to which

data centers and other drivers have affected retail electricity prices.49 Their most recent analysis,

which covered the years 2019 through 2025, found that the main driver behind increases in

electricity prices during this period was utility investments in grid infrastructure, mostly in

response to aging infrastructure and resilience needs. Other key drivers included natural gas

prices (natural gas is a key fuel for power generation); recovery from natural disasters (e.g.,

storms, wildfires); and state energy and environmental policies. LBNL found that states with the

largest data center demand growth generally saw electricity price decreases during the period

from 2019 through 2025, although some states with relatively large data center growth saw prices

increase or stay the same.50 One explanation for this finding may be that increased demand in

some states allowed utility costs to be spread over a larger sales volume, putting downward

pressure on rates.51 Other studies have reached similar conclusions about rates during this

period.52

Although the studies discussed above found only a limited effect of data centers on electricity

prices in the past, data centers could have a greater impact on prices as the industry continues to

grow and demand more electricity. In electricity markets with little spare generation capacity, the

added demand of data centers may increase the future price of electricity for all customers. This

appears to be one of several contributing factors to electricity price increases in 2025 and 2026 in

the PJM region, a part of the country that includes “Data Center Alley” in northern Virginia (see

Figure 1).53 A recent modeling study led by North Carolina State University found that data

centers (and cryptocurrency mining facilities) could cause national average electricity costs to

increase by 6% to 29%, across different modeling scenarios, with increases up to 57% in some

48 EIA, “Electricity Explained: Factors Affecting Electricity Prices,” https://www.eia.gov/energyexplained/electricity/

prices-and-factors-affecting-prices.php.

49 Ryan Wiser et al., “Retail Electricity Price Trends and Drivers: Data Update—2026 Edition,” LBNL and the Brattle

Group, April 2026, https://emp.lbl.gov/sites/default/files/2026-03/Retail%20Price%20Trends_2026%20edition.pdf.

50

Wiser et al., “Retail Electricity Price Trends and Drivers: Data Update—2026 Edition,” p. 47.

51 Keaton Peters, “Utilities Are Now Pitching Data Centers as a Way to Cut Electric Costs,” Straight Arrow News,

August 9, 2026, https://san.com/cc/utilities-are-now-pitching-data-centers-as-a-way-to-cut-electric-costs/.

52 Energy and Environmental Economics (E3), Understanding the Drivers of Rising Electricity Rates and the Role of

Data Centers, May 2026, https://www.ethree.com/wp-content/uploads/2026/05/Understanding-the-Drivers-of-RisingElectricity-Rates-and-the-Role-of-Data-Centers_E3-2026.pdf; and Angela Ryu and Shon R. Hiatt, Data Center Entry

and U.S. Electricity Prices: From the Wholesale Market to the Power Bill, University of Southern California Marshall

School of Business, Zage Business of Energy Initiative, May 22, 2026, https://drive.google.com/file/d/

1IWolyGYxOv5ENI3frcRU8U0Mge_fbWUr/view.

53 For additional discussion of PJM electricity price increases, see CRS Report R48553, PJM’s Electric Capacity

Market: Background and Current Issues, by Ashley J. Lawson.

Congressional Research Service

10

Data Centers and the Electricity Grid: Frequently Asked Questions

regions.54 Another modeling study led by Carnegie Mellon University found that “data center and

cryptocurrency mining growth through 2030 could increase average U.S. electricity generation

costs by 8%.”55 Whether electricity costs rise due to data centers, and by how much, would vary

by region and depend on assumptions about market response. The potential price impacts on

electricity customers in any market area remain uncertain.

Where is data center growth happening?

Data center growth has been affecting the electricity grid more in some regions than others.

Information from 2024 shows that data centers in 15 states together consumed 80% of electricity

nationwide used by such facilities.56 On an individual basis, Virginia was the only state with

greater than 20% of total electricity consumed by data centers (Figure 2).

Figure 2. Standalone Data Center Electricity Use by State in 2024

Source: CRS using data provided by Electric Power Research Institute, Powering Intelligence 2026: Updated

Scenarios of U.S. Data Center Electricity Use and Power Strategies, February 25, 2026, https://poweringintelligence.epri.com/.

Note: Includes cryptocurrency facilities.

Developers anticipate future data center buildouts to occur more in new geographic regions, with

some analysis expecting these to be in rural areas as time-to-power exceeds developers’

requirement in traditional areas.57 One analysis projects that by 2030 a greater range of states will

have large shares of electricity consumption attributable to data centers (Figure 3).

54 Jeremiah X. Johnson et al., “Power System Costs and Emissions from Data Center and Cryptocurrency Mining

Expansion in the United States,” Environmental Research Letters, Vol. 21, June 4, 2026, https://iopscience.iop.org/

article/10.1088/1748-9326/ae6c3d.

55 Michael Blackhurst et al., “Data Center Growth Could Increase Electricity Bills 8% Nationally and as Much as 25%

in Some Regional Markets,” white paper, Carnegie Mellon University, July 16, 2025, https://www.cmu.edu/work-thatmatters/energy-innovation/data-center-growth-could-increase-electricity-bills.

56 EPRI, Powering Intelligence: Analyzing Artificial Intelligence and Data Center Energy Consumption, May 28, 2024,

p. 5. The top six were, in decreasing order, Virginia, Texas, California, Illinois, Oregon, and Arizona.

57 Bloom Energy, 2026 Data Center Power Report, January 2026, p. 4, https://www.bloomenergy.com/wp-content/

(continued...)

Congressional Research Service

11

Data Centers and the Electricity Grid: Frequently Asked Questions

Figure 3. Projected Standalone Data Center Electricity Use by State in 2030

Source: CRS using data provided by Electric Power Research Institute, Powering Intelligence 2026: Updated

Scenarios of U.S. Data Center Electricity Use and Power Strategies, February 25, 2026, https://poweringintelligence.epri.com/.

Note: Includes cryptocurrency facilities.

Can data centers cause blackouts?

Data centers do not appear to have caused blackouts to date. Electric reliability in the United

States remains generally high, barring local or regional outages associated with natural disasters

or weather events.58 Nonetheless, generation capacity constraints have raised concerns in some

electricity markets that the added electricity demand of data centers on peak demand days (e.g.,

during heat waves) could lead to electricity blackouts or brownouts (in which utilities are forced

to reduce grid voltage system-wide to avoid full blackouts).59 Although such events are possible,

electric utilities generally have processes in place to avoid supply disruptions. In addition, the

Secretary of Energy may issue emergency orders under the Federal Power Act temporarily

authorizing grid operators to take additional actions to ensure grid reliability.60 For example, at

the request of the PJM grid operator (which serves the Mid-Atlantic and parts of the Midwest),

DOE issued an emergency order on May 18, 2026, authorizing PJM “to direct backup generation

resources at data centers (including, but not limited to, hyperscaler facilities), and at other large

uploads/2026-power-report.pdf; and Skyler Seets and Kaitlyn Radde, “Most New Data Centers in the U.S. Are Coming

to Rural Areas,” Pew Research Center, April 13, 2026, https://www.pewresearch.org/short-reads/2026/04/13/mostnew-data-centers-in-the-us-are-coming-to-rural-areas/.

58 See, for example, EIA, “Hurricanes in 2024 Led to the Most Hours Without Power in the United States in 10 Years,”

December 1, 2025, https://www.eia.gov/todayinenergy/detail.php?id=66744. U.S. islands and remote areas may

experience relatively more electricity disruptions. See, for example, EIA, “Even Without Hurricanes, Customers in

Puerto Rico Lose About 27 Hours of Power per Year,” Today in Energy, August 13, 2025, https://www.eia.gov/

todayinenergy/detail.php?id=65925.

59 Scott Gelman, “Could Extreme Heat, Data Center Demand Prompt Brownouts Across DC Region?,” WTOP News,

July 15, 2026, https://wtop.com/local/2026/07/is-extreme-heat-data-center-demand-enough-to-prompt-brownoutsacross-dc-region/.

60 16 U.S.C. §824a(c). For more details, see CRS Report R48568, Federal Power Act: The Department of Energy’s

Emergency Authority, by Ashley J. Lawson.

Congressional Research Service

12

Data Centers and the Electricity Grid: Frequently Asked Questions

load industrial and commercial customer sites … to operate as a last resort” to prevent

blackouts.61

An emerging concern is the risk that large loads such as data centers will unexpectedly go offline,

causing voltage and frequency levels on the grid to increase. Events like this have occurred in

recent years in Virginia and Texas, prompting NERC to issue an alert in May 2026 directing grid

operators to take certain precautionary actions to prevent equipment damage from such events.62

Additionally, NERC is developing new reliability requirements for large load customers,

including large data centers, and expects to file proposed requirements with FERC by December

31, 2026, for approval.63

What has the federal government been doing about data centers

and the grid?

The Trump Administration has taken several actions related to data centers and the grid. President

Trump issued Executive Order 14318 of July 23, 2025, “Accelerating Federal Permitting of Data

Center Infrastructure,” intended “to facilitate the rapid and efficient buildout” of data center

infrastructure.64 In October 2025, the Secretary of Energy directed FERC to initiate a rulemaking

to ensure that “large loads, including AI data centers, served by public utilities [will] be able to

connect to the transmission system in a timely, orderly, and non-discriminatory manner.”65 In

response, FERC initiated a proceeding on June 18, 2026, requiring FERC-jurisdictional regional

transmission organizations and independent system operators (shown in Figure 1) to either

demonstrate that their existing rules appropriately address large load interconnections or propose

rules changes that would do so.66 On July 16, 2026, FERC directed NERC to develop new or

modified reliability standards to address reliability risks associated with integrating

“computational loads” (e.g., data centers) into the grid.67

On March 4, 2026, President Trump announced a “Ratepayer Protection Pledge,” which called on

“the leading United States hyperscalers and AI companies to build, bring, or buy all of the energy

61 Department of Energy, Order No. 202-26-23, May 18, 2026, https://www.energy.gov/documents/doe-emergency-

order-no-202-26-23pdf.

62 NERC, “NERC Issues Level 3 Alert, Reliability Guideline Focused on Large Load Challenges,” press release, May

4, 2026, https://www.nerc.com/newsroom/nerc-issues-level-3-alert-reliability-guideline-focused-on-large-loadchallenges.

63 NERC, Large Loads Action Plan Q1 2026 Update: Addressing an Emerging Reliability Issue, April 2026,

https://www.nerc.com/globalassets/initiatives/large-loads-action-plan/llap-quarterly-update-q1-2026.pdf.

64 Executive Order 14318 of July 23, 2025, “Accelerating Federal Permitting of Data Center Infrastructure,” 90 Federal

Register 35385, July 28, 2025, https://www.federalregister.gov/documents/2025/07/28/2025-14212/acceleratingfederal-permitting-of-data-center-infrastructure.

65 Letter from Chris Wright, Secretary of Energy, to FERC Commissioners, October 23, 2025, p. 1,

https://www.energy.gov/sites/default/files/2025-10/403%20Large%20Loads%20Letter.pdf. Although FERC generally

acts independently of the Secretary, the Department of Energy Organization Act (P.L. 95-91) authorizes the Secretary

of Energy “to propose rules, regulations, and statements of policy of general applicability with respect to any function

within the jurisdiction of [FERC].” 42 U.S.C. §7173.

66 FERC staff, RTO/ISO Show Cause Orders, presentation, June 18, 2026, p. 4, https://ferc.gov/news-events/news/

presentation-items-e-7-through-e-12-rtoiso-show-cause-orders. Regional transmission organizations (RTOs) and

independent system operators (ISOs) are entities that operate regional transmission systems independently of wholesale

electricity market participants (e.g., generators). For more information, see FERC, “Electric Power Markets,” updated

March 27, 2025, https://www.ferc.gov/electric-power-markets.

67 FERC, “Order Directing the North American Electric Reliability Corporation to File Reliability Standard(s)

Pertaining to Computational Load Integration,” 196 FERC ¶ 61,031, July 16, 2026, https://www.ferc.gov/media/e-1rd26-7-000.

Congressional Research Service

13

Data Centers and the Electricity Grid: Frequently Asked Questions

needed for building and operating data centers, paying the full cost of their energy and

infrastructure.”68 Reportedly, several major technology companies—including Google, Microsoft,

Meta, Oracle, xAI, OpenAI, and Amazon—voluntarily agreed to abide by the pledge.69 On July

23, 2026, President Trump announced “a historic expansion of the Ratepayer Protection Pledge,

bringing more than 200 additional utilities, data center developers, cooperatives, and states into

this growing national commitment.”70 As of the date of this publication, over 300 organizations

have committed to the pledge, according to the Trump Administration.71 The pledge does not

have an enforcement mechanism. Some observers contend that while the pledge creates a

framework that could shield non-data-center consumers, its long-term success will depend on

various implementation measures.

What have states been doing about data centers and the grid?

Most regulation of electricity generation and electric utilities falls under state jurisdiction. States

have been pursuing various independent policies to address concerns about data centers and the

grid. Many state legislatures have considered or passed “affordability” legislation intended to

ensure that data centers cover the full costs of their electricity demand and not shift their

electricity costs onto other electricity customers.72

Some states have proposed legislation requiring data centers to build new generation plants, an

approach often referred to as “bring your own power” (BYOP) or “bring your own generation”

(BYOG), as noted in “How do data centers get their electric power?” above. Others have

proposed requiring data centers to participate in electricity demand response programs or agree to

be disconnected first in case of a shortage of electricity supplies. Texas, for example, legislated

both requirements in 2025.73 Some states have considered legislation requiring data centers to

procure some or all of their electricity from energy sources that do not emit greenhouse gases.74

States have also pursued transparency legislation requiring data centers to report certain

information about their energy use to inform regulators and legislators about their impacts to the

grid.75

Absent new legislation, state utility regulators have considered or imposed various policies under

their existing statutory authorities to address concerns about data center grid impacts by

68 Executive Office of the President, “Ratepayer Protection Pledge,” 91 Federal Register 11439, March 9, 2026.

69 Katherine Long and Peter Behr, “What to Know About Trump’s AI Deal,” Politico Pro, March 4, 2026,

https://subscriber.politicopro.com/article/2026/03/what-to-know-about-trumps-ai-deal-00811909.

70 White House, “President Trump’s Ratepayer Protection Pledge Secures American AI Dominance, Protects

Consumers,” press release, July 23, 2026, https://www.whitehouse.gov/releases/2026/07/president-trumps-ratepayerprotection-pledge-secures-american-ai-dominance-protects-consumers/.

71 White House, “Ratepayer Protection Pledge,” accessed August 17, 2026, https://www.whitehouse.gov/ratepayerprotection-pledge/.

72 North Carolina Clean Energy Technology Center, 50 States of Energy Affordability: Quarterly Report, June 2026,

https://www.dsireinsight.com/publications?_sp=ad9b8524-e005-421e-80a5-64cf979f30df.1784042352567; Morgan

Scarboro, “How States Are Requiring Data Centers to Pay for Grid Expansion (Comparing Ratepayer Protection Bills

Across Five States),” MultiState, June 4, 2026, https://www.multistate.us/insider/2026/6/4/how-states-are-requiringdata-centers-to-pay-for-grid-expansion-comparing-ratepayer-protection-bills-across-five-states.

73 For a discussion of the 2025 Texas data center law, see Brian Martucci, “Texas Law Gives Grid Operators Power to

Disconnect Data Centers During Crisis,” Utility Dive, June 25, 2025, https://www.utilitydive.com/news/texas-lawgives-grid-operator-power-to-disconnect-data-centers-during-crisi/751587/.

74 See, for example, New Jersey Senate Bill S4143, Session 2024-2025, https://www.njleg.state.nj.us/bill-search/2024/

S4143. The bill was not enacted.

75 See, for example, Pennsylvania Senate Act No. 21, PA SB146, July 12, 2026, https://legiscan.com/PA/bill/SB146/

2025.

Congressional Research Service

14

Data Centers and the Electricity Grid: Frequently Asked Questions

establishing new large load rate classes, demand response requirements, and other measures to

avoid cost shifts and ensure reliability, especially for residential customers.76 Some states have

pursued voluntary commitments from data center developers to protect electricity consumers

from electricity cost increases associated with growing data center electricity demand. For

example, on July 15, 2026, the governor of Michigan announced a Michigan Affordable and

Responsible Growth Action Plan seeking voluntary commitments from data center developers “to

protect Michigan consumers from higher energy bills,” among other provisions.77

Additionally, some states have considered imposing moratoria on new data center development to

allow time to more thoroughly evaluate their effects on communities and the grid, and to

implement associated policies and regulations.78 On July 14, 2026, New York became the first

state to impose such a moratorium, “temporarily pausing State environmental permits for up to

one year in order to build a nation-leading regulatory framework that protects ratepayers, the

environment, the energy grid and communities across the state.”79 On August 3, 2026, the

governor of Texas, in order to “keep the grid stable and reliable,” ordered a pause on data center

development until the completion of “a comprehensive verification and audit of all data centers

advancing through ERCOT’s interconnection process.”80

What has Congress been doing about data centers and the grid?

Congress has an ongoing interest in the development of data centers, generally, and their impacts

on the electricity grid and electricity customers, specifically. Hearings in the 119th Congress have

examined data-center- and grid-related issues.81 Ensuring data centers do not raise costs for

residential customers or reduce grid reliability has been a focus of legislative activity.

As of the date of this publication, at least a dozen bills have been introduced in the 119th Congress

with the primary intention being to ensure that data centers (or, more generally, any large load

customer) cover the full costs of their electricity demand or do not shift their electricity costs onto

76 See, for example, Diana DiGangi, “Virginia SCC Weighs Dominion Data Center Transmission Cost Allocation,”

Utility Dive, July 15, 2026, https://www.utilitydive.com/news/virginia-scc-dominion-data-center-transmission-costallocation/825300/.

77 Michigan Governor Gretchen Whitmer, “Gov. Whitmer Launches Michigan Affordable and Responsible Growth

Action Plan, Calls on Data Center Companies to Sign Pledge,” press release, July 15, 2026, https://www.michigan.gov/

whitmer/news/press-releases/2026/07/15/gov-whitmer-data.

78 National Conference of State Legislatures, “Which States Are Banning Data Centers?” July 1, 2026,

https://www.ncsl.org/fiscal/which-states-are-banning-data-centers.

79 New York Governor Kathy Hochul, “First Statewide Moratorium on New Hyperscale Data Centers Launched by

Governor Kathy Hochul,” press release, July 14, 2026, https://www.governor.ny.gov/news/first-statewide-moratoriumnew-hyperscale-data-centers-launched-governor-kathy-hochul. Prior to this, in 2022, New York passed a two-year

moratorium that blocked issuance of permits and approval of new cryptocurrency mines while the state evaluated their

environmental effects. See NY Laws of 2022, Chapter 628.

80 Letter from Greg Abbott, Governor of Texas, to Thomas Gleeson, Chairman, Public Utility Commission of Texas,

and Pablo Vegas, President and Chief Executive Officer, ERCOT, August 3, 2026, https://gov.texas.gov/uploads/files/

press/Thomas_Gleeson_Pablo_Vegas_Data_Centers_Directive_Letter_to_PUCT_ERCOT_August_2026_.pdf.

81 See, for example, U.S. Congress, House Committee on Energy and Commerce, Subcommittee on Energy, AI and the

Grid: Meeting Growing Power Demand While Protecting Ratepayers, hearing, 119th Cong., 2nd sess., April 29, 2026,

https://energycommerce.house.gov/events/energy-hearing-ai-and-the-grid-meeting-growing-power-demand-whileprotecting-ratepayers; U.S. Congress, House Committee on Science, Space, and Technology, Subcommittee on

Investigations and Oversight, Powering America’s AI Future: Assessing Policy Options to Increase Data Center

Infrastructure, hearing, 119th Cong., 2nd sess., February 24, 2026, https://science.house.gov/hearings?ID=17369F69BFD6-4F4A-A499-C38B73CCD1A6.

Congressional Research Service

15

Data Centers and the Electricity Grid: Frequently Asked Questions

other electricity customers.82 One such bill, the Ratepayer Protection Act (H.R. 9340), was

ordered to be reported by the House Energy and Commerce Committee on July 21, 2026. A

related bill (S. 5028) was introduced in the Senate. In addition, two bills (S. 4214 and H.R. 9442)

would impose a nationwide data center construction moratorium until “laws are enacted to ensure

that” data centers do not increase electricity costs for other consumers, among other provisions.

Some Members have introduced bills in the 119th Congress that focus on other aspects of data

centers and the grid. Two bills (S. 5199 and S. 4806) would clarify that FERC has regulatory

authority over the interconnection of large loads (e.g., data centers) to the grid. Two bills (S. 1475

and H.R. 6179) would require collection of data center electricity consumption information and

establish emissions standards and an associated fee system for data center electricity

consumption. One bill (H.R. 6983) would require data centers to generate their own electricity

and that certain fractions be from clean energy sources as defined in the bill. Finally, one bill

(H.R. 5927) would amend the Defense Production Act to accelerate the development of critical AI

projects, including electricity infrastructure projects.

In addition to the bills cited above, other proposed legislation may address data centers’

electricity issues. The set of bills discussed above should not be considered comprehensive.

Additional Resources

CRS has several other published products which may be helpful in further examining specific

data-center-related energy policy issues:

•

•

•

•

•

CRS Report R49057, Data Centers and Water: Frequently Asked Questions,

coordinated by Peter Folger and Elena H. Humphreys

CRS Report R48914, Cryptocurrency Mining and the Electricity Sector, by

Corrie E. Clark

CRS Report R48762, Data Center Energy Infrastructure: Federal Permit

Requirements, by Paul W. Parfomak et al.

CRS Report R48646, Data Centers and Their Energy Consumption: Frequently

Asked Questions, by Martin C. Offutt et al.

CRS Report R48583, Energy Tax Benefits for Data Centers: In Brief, by

Nicholas E. Buffie

For additional information, congressional clients may also contact the CRS policy experts and

legal points of contact listed in CRS Report R48920, Data Centers: CRS Experts, coordinated by

Paul W. Parfomak.

82 See, for example, H.R. 9777, H.R. 9655, H.R. 9419, H.R. 8033, H.R. 7977, H.R. 7066, H.R. 6529, S. 4559, S. 3852,

and H.R. 8241/S. 3682.

Congressional Research Service

16

Data Centers and the Electricity Grid: Frequently Asked Questions

Author Information

Ashley J. Lawson

Specialist in Energy Policy

Martin C. Offutt

Analyst in Energy Policy

Paul W. Parfomak

Specialist in Energy Policy

Disclaimer

This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan

shared staff to congressional committees and Members of Congress. It operates solely at the behest of and

under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other

than public understanding of information that has been provided by CRS to Members of Congress in

connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not

subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in

its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or

material from a third party, you may need to obtain the permission of the copyright holder if you wish to

copy or otherwise use copyrighted material.

Congressional Research Service

R49326 · VERSION 1 · NEW

17

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.