Judicial Review and the National Environmental Policy Act (NEPA)

Congressional research reportSep 19, 2025

Ask Donna

What actually matters in this document.

Text

Judicial Review and the National

Environmental Policy Act (NEPA)

September 19, 2025

Congressional Research Service

https://crsreports.congress.gov

R48717

SUMMARY

Judicial Review and the National

Environmental Policy Act (NEPA)

R48717

September 19, 2025

Kristen Hite

Legislative Attorney

The National Environmental Policy Act (NEPA) is one of the most frequently litigated federal

environmental statutes. NEPA is also one of the most broadly applicable federal environmental

statutes, with over 100,000 actions taken by the federal government each year subject to NEPA.

Enacted in 1969, NEPA generally requires federal agencies to integrate environmental

considerations into their decisionmaking processes. Under NEPA, agencies evaluate the

significance of environmental effects of major federal actions that are discretionary in nature. Actions subject to NEPA

include federal permits and licenses.

Federal courts have long allowed plaintiffs to challenge an agency’s compliance with NEPA under the Administrative

Procedure Act (APA). NEPA claims are commonly reviewed under the APA’s arbitrary-and-capricious standard based on

allegations that the agency action was arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.

Some of the more frequently litigated issues include allegations that an agency failed to prepare NEPA documentation,

mischaracterized the significance of an action’s environmental impact, and failed to adequately consider relevant information

or comments about a proposed action. If an agency’s NEPA review is challenged under the arbitrary-and-capricious standard

under the APA, courts generally review the agency’s administrative record and determine whether the agency was

unreasonable or unsupported in its analysis or otherwise violated the law. While most NEPA-related litigation falls under the

APA, NEPA itself allows a project sponsor to seek judicial review of an agency’s alleged failure to comply with statutory

deadlines for completing NEPA documentation. Other environmental statutes may include judicial review provisions that

broadly allow a court to review agency actions, including NEPA-related decisions.

A court typically has broad latitude to order a spectrum of remedies when it finds an agency violated the law with respect to

NEPA. Courts typically tailor any relief ordered to fact-specific circumstances particular to the case in question. In cases

involving NEPA, such relief may include declaring an agency action unlawful, remanding the disputed action to the agency,

vacating (i.e., nullifying) all or part of an agency decision, and issuing an injunction. While courts can typically choose which

remedy to issue, courts have recognized that vacatur is the “ordinary” remedy for an APA violation. For example, courts

typically vacate an action if an agency fails to conduct a NEPA review prior to acting, or violates a procedural obligation that

casts “serious doubt” over an agency’s decision. In other instances, courts may remand a NEPA matter without vacatur.

Injunctions are a less common remedy for NEPA violations and must satisfy criteria—including the significance of harm,

balance of equities, and the public interest—in the event a judge were to consider granting injunctive relief.

Congressional Research Service

Judicial Review and the National Environmental Policy Act (NEPA)

Contents

Introduction ..................................................................................................................................... 1

Statutory and Regulatory Background ............................................................................................ 2

Administrative Framework ....................................................................................................... 2

Environmental Review Under NEPA ........................................................................................ 3

Judicial Review Authorities ...................................................................................................... 5

Administrative Procedure Act ............................................................................................. 6

Enforcing NEPA Deadlines to Prepare an EA or EIS ......................................................... 7

Deputizing Federal Actors: Waiver of Sovereign Immunity ............................................... 8

Considerations for Judicial Review of NEPA Litigation ................................................................. 8

Agency Discretion and Deference in Arbitrary-and-Capricious Cases ..................................... 9

Standing .................................................................................................................................. 10

Exhaustion ................................................................................................................................ 11

Statute of Limitations ............................................................................................................... 11

Common Issues in NEPA Litigation .............................................................................................. 12

Is a NEPA Review Required? .................................................................................................. 12

Is the Action Reviewable as a Final Major Federal Action? ............................................ 12

Is the Action Exempt from NEPA Due to Competing Authority?..................................... 13

Does New Activity Warrant Additional Analysis? ............................................................ 13

Did the Agency Properly Apply a Categorical Exclusion? ..................................................... 14

Did the Agency Adequately Analyze Environmental Impacts? .............................................. 15

Did the Agency Reasonably Determine the Appropriate Scope of Impacts? .................... 16

Can the Agency Substantiate Its Determination of Whether Impacts Are

Significant? .................................................................................................................... 17

Did the Agency Consider a Reasonable Set of Alternatives?.................................................. 18

Did the Agency Follow Appropriate Procedures for Consultation? ........................................ 19

Remedies in NEPA Litigation........................................................................................................ 19

Declaratory Relief ................................................................................................................... 20

Remand ................................................................................................................................... 20

Vacatur .................................................................................................................................... 20

Injunctive Relief ...................................................................................................................... 22

Considerations for Congress.......................................................................................................... 23

Contacts

Author Information........................................................................................................................ 24

Congressional Research Service

Judicial Review and the National Environmental Policy Act (NEPA)

Introduction

The National Environmental Policy Act (NEPA), enacted in 1969, generally requires federal

agencies to integrate environmental considerations into their decisionmaking processes.1 NEPA

directs agencies to use interdisciplinary approaches in considering environmental effects and, for

specified actions, requires a “detailed statement” about an action’s significant effects on the

human environment.2 Agencies must take a “hard look” at a covered action, consider alternative

options, and issue a detailed description of effects (environmental impact statement or EIS) when

a “reasonably foreseeable” impact may significantly affect the quality of the human

environment.3 Because this requirement applies to a wide range of federal actions—including

both the government’s own activities and its decisions to allow or to fund other parties’

activities—NEPA plays a significant role in the administration of many federal programs.4

Over the past five decades, the federal courts have been instrumental in guiding agency

compliance with NEPA. The courts review NEPA-related claims amid an evolving statutory and

regulatory landscape. The statute historically operated at more of a framework level and has seen

considerable engagement from all branches of government in recent years. Congress amended the

statute in 2023 and 2025.5 During that same time period, federal courts issued a number of

prominent opinions on NEPA, including the first Supreme Court case in two decades to address

the scope of NEPA reviews.6 In 2025, the Council on Environmental Quality (CEQ)—tasked by

Congress with oversight of NEPA’s implementation—rescinded implementing regulations

governing how agencies implement NEPA, deferring to individual agencies on how to implement

NEPA.7 To date, federal agencies have responded in varying degrees with updates to their

approaches to NEPA implementation.8 Agencies’ changes to NEPA procedures are themselves

1

Pub. L. No. 91–161, 83 Stat. 852 (1970) (codified as amended at 42 U.S.C. §§ 4321–4347). For a general overview of

NEPA, see CRS In Focus IF11549, The Legal Framework of the National Environmental Policy Act (2021).

2 42 U.S.C. § 4332.

3 Id.; id. §§ 4336(b)(1), 4336e(6).

4 See id. § 4336e(10) (defining major Federal action as one that an agency determines is “subject to substantial Federal

control and responsibility,” subject to certain exclusions).

5 Pub. L. No. 118–5, 137 Stat. 38 (2023); Pub. L. No. 119–21, 139 Stat. 157 (2025).

6 In November 2024, the U.S. Court of Appeals for the D.C. Circuit declared that President Carter’s 1977 executive

order mandating the Council on Environmental Quality (CEQ) to issue regulations binding on all federal agencies

exceeded the President’s statutory authority. Marin Audubon Soc’y v. Fed. Aviation Admin., 121 F.4th 902 (D.C. Cir.

2024). However, a subsequent majority concurring en banc declined to extend that reasoning, Marin Audubon Soc’y. v.

Fed. Aviation Admin., No. 23-1067, 2025 WL 374897, at *1 (D.C. Cir. Jan. 31, 2025) (Srinivasan, J., concurring). In

2025, the Supreme Court issued an opinion clarifying that agencies have substantial discretion in defining the scope of

impacts analyzed during a NEPA review and did not address the authority of CEQ to issue regulations, Seven Cnty.

Infrastructure Coal. v. Eagle County, 145 S. Ct. 1497 (2025). For a general discussion of the Seven County ruling, see

CRS Legal Sidebar LSB11333, “Deference Squared”: Supreme Court Limits NEPA’s Scope and Courts’ Reach in

Seven County Infrastructure Coalition, by Kristen Hite (2025).

7 Id. § 4344(3) (establishing CEQ’s duty to review and appraise federal programs and activities in the context of NEPA

and make recommendations to the President thereto); NEPA Implementing Regulations Revisions Phase 2, 89 Fed.

Reg. 35442 (May 1, 2024); Removal of NEPA Implementing Regulations, 90 Fed. Reg. 10610 (Feb. 25, 2025)

(amending subchapter A of chapter V in title 40 of the Code of Federal Regulations by removing and reserving parts

1500, 1501, 1502, 1503, 1504, 1505, 1506, 1507, and 1508); Memorandum from Katherine Scarlet, Chief of Staff,

CEQ, to Heads of Fed. Dep’ts & Agencies 1 (Feb. 19, 2025) [hereinafter CEQ Memo], https://ceq.doe.gov/docs/ceqregulations-and-guidance/CEQ-Memo-Implementation-of-NEPA-02.19.2025.pdf [https://perma.cc/HU63-R9LA]. See

also CRS In Focus IF12960, Council on Environmental Quality Rescinds NEPA Regulations: Legal and Policy

Considerations, by Heather McPherron and Kristen Hite (2025).

8 See, e.g., National Environmental Policy Act, 90 Fed. Reg. 29632 (July 3, 2025) (Dep’t of Agriculture); National

Environmental Policy Act Implementing Regulations, 90 Fed. Reg. 29498 (July 3, 2025) (Dep’t of the Interior).

Congressional Research Service

1

Judicial Review and the National Environmental Policy Act (NEPA)

typically subject to judicial review, including recission of regulations and other changes that may

potentially limit or otherwise affect judicial review of NEPA determinations.

Most NEPA-related legal complaints are brought under the Administrative Procedure Act (APA),

as NEPA does not contain a broad judicial review provision addressing challenges to agencies’

actions under the statute. The APA provides broad authority for plaintiffs to challenge final

agency actions, including administrative reviews and permitting decisions.9 A narrower provision

in NEPA itself allows a project sponsor to seek judicial review of an agency’s alleged failure to

comply with certain statutory deadlines.10 Additionally, some statutes have general judicial review

provisions that broadly allow a court to review agency actions, including environmental reviews

under NEPA. For example, the Natural Gas Act vests the federal appellate courts with exclusive

jurisdiction to review an agency order covered by the Natural Gas Act, which may include a

NEPA review.11

This report focuses on the role of the federal courts in reviewing agency compliance with NEPA.

First, the report provides an overview of the relevant statutory and regulatory framework. Next, it

discusses how judicial review works in the NEPA context. Finally, the report provides an

overview of select issues that arise during litigation or tend to generate controversy about NEPA.

Statutory and Regulatory Background

Administrative Framework12

NEPA establishes a procedural framework for federal agencies to consider environmental impacts

when undertaking major federal actions. It requires agencies to evaluate whether a proposed

action is likely to have significant environmental effects and, if so, to document those effects and

consider reasonable alternatives.13 NEPA does not mandate which decisions agencies must make

or require them to select the most environmentally protective alternative. Rather, NEPA requires

agencies to conduct thorough analyses before making final decisions. In the words of the

Supreme Court, NEPA “merely prohibits uninformed—rather than unwise—agency action.”14

NEPA also created CEQ in the Executive Office of the President to provide oversight of NEPA’s

implementation, among other duties.15

In 1978, CEQ issued its first NEPA-implementing regulations and also directed federal agencies

to establish their own agency-specific procedures consistent with CEQ regulations while

reflecting agency-specific statutory requirements, regulations, and guidance.16 While CEQ has

historically provided regulations intended to standardize federal agencies’ approaches to

implementing NEPA, courts have recently questioned CEQ’s authority to issue binding

9 5 U.S.C. §§ 701–706.

10 42 U.S.C. § 4336a(g)(3). An agency that determines that it is unable to meet a statutory deadline may extend it for

“only so much additional time as is necessary,” in consultation with any applicant, if applicable. Id. § 4336a(g)(2).

11 15 U.S.C. § 717r.

12 CRS Analysts Heather McPherron and Omar Hammad contributed to portions of this section.

13 42 U.S.C. § 4332(C).

14 Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 351 (1989).

15 42 U.S.C. § 4344(3) states that “it shall be the duty and function of the Council . . . to review and appraise the

various programs and activities of the Federal Government in the light of the policy set forth in subchapter I of [NEPA]

for the purpose of determining the extent to which such programs and activities are contributing to the achievement of

such policy, and to make recommendations to the President with respect thereto.”

16 National Environmental Policy Act—Regulations, 43 Fed. Reg. 55978, 56002–03 (Nov. 29, 1978).

Congressional Research Service

2

Judicial Review and the National Environmental Policy Act (NEPA)

regulations.17 In January 2025, President Trump issued an executive order instructing CEQ to

propose rescinding its NEPA regulations and provide new guidance for NEPA implementation.18

On February 25, 2025, CEQ published an interim final rule to remove all of its NEPAimplementing regulations effective April 11, 2025.19 CEQ also directed federal agencies to revise

or establish their own NEPA procedures in consultation with CEQ within twelve months to align

with the 2023 NEPA amendments adopted in the Fiscal Responsibility Act (Pub. L. No. 118-5).20

CEQ further advised agencies to continue adhering to their existing NEPA practices and

procedures while adjusting for consistency with the amended statute.21 In July 2025, a number of

federal agencies rescinded or updated their NEPA regulations and issued new directives for

implementing NEPA.22

Environmental Review Under NEPA

NEPA requires that federal policies,

regulations, and public laws must be

interpreted and administered in

accordance with the statute “to the fullest

extent possible.”23 To determine whether

NEPA applies to a proposed action, an

agency must assess whether the action

qualifies as a major federal action and, if

so, whether its environmental impacts

NEPA and Federal Permitting

NEPA establishes procedural requirements for federal

decisionmaking. It mandates that federal agencies evaluate a

proposed action’s potential significant environmental

impacts. NEPA provides inputs to federal decisions. While

completion of a NEPA review does not automatically grant

or deny project approval, it may be a prerequisite for an

agency to finalize a federal decision to issue a permit.

Federal permitting, by comparison, typically regulates

nonfederal actors by requiring that they obtain specific

authorizations from regulatory agencies to proceed with

project activities. An agency decision to approve or

authorize a proposed course of action (e.g., issuing permits,

licensing, or granting rights-of-way across federal lands) is

often subject to NEPA. Even after an agency approves an

authorization, a federal permit alone may not be sufficient

for a project to proceed. For example, permits may also be

required at the state or local level before a project may

proceed.

17 In November 2024, the U.S. Court of Appeals for the D.C. Circuit declared that President Carter’s 1977 executive

order mandating CEQ to issue regulations binding on all federal agencies exceeded the President’s statutory authority.

Marin Audubon Soc’y v. Fed. Aviation Admin., 121 F.4th 902 (D.C. Cir. 2024). In February 2025, the U.S. District

Court for the District of North Dakota invalidated CEQ’s 2024 regulations based in part on the fact that they exceeded

statutory authority. Iowa v. CEQ, 765 F. Supp. 3d 859 (D.N.D. 2025), vacated and appeal dismissed by, No. 25-1641,

2025 WL 2205808 (8th Cir. July 29, 2025); see also CRS Legal Sidebar LSB11260, Marin Audubon Society v. Federal

Aviation Administration: D.C. Circuit Challenges CEQ’s Authority to Issue NEPA Regulations, by Kristen Hite and

Abigail A. Graber (2025).

18 Exec. Order No. 14,154, 90 Fed. Reg. 8353, 8353–55 (Jan. 29, 2025).

19 Removal of NEPA Implementing Regulations, 90 Fed. Reg. 10610 (Feb. 25, 2025). See also CRS In Focus IF12960,

Council on Environmental Quality Rescinds NEPA Regulations: Legal and Policy Considerations, by Heather

McPherron and Kristen Hite (2025).

20 On February 19, 2025, CEQ issued guidance on the implementation of the interim final rule and Executive Order No.

14,154. CEQ Memo, supra note 7. The passage of the Fiscal Responsibility Act (FRA) (Pub. L. No. 118-5) in 2023

introduced statutory amendments to NEPA, codifying several procedural elements previously established only through

CEQ regulations. For further information on the amendments to NEPA as a result of the FRA, see CRS In Focus

IF12417, Environmental Reviews and the 118th Congress, by Kristen Hite (2023).

21 CEQ Memo, supra note 7, at 1.

22 See, e.g., Removal of Environmental Impact Analysis Process (EIAP) Regulation, 90 Fed. Reg. 28021 (July 1, 2025)

(to be codified in 32 C.F.R. pt. 989).

23 42 U.S.C. § 4332. NEPA, Pub. L. No. 91–190, 83 Stat. 852 (1970).

Congressional Research Service

3

Judicial Review and the National Environmental Policy Act (NEPA)

will be significant.24 The steps an agency takes to identify and document a proposed action’s

environmental impacts, as well as to consider alternatives to the action and their anticipated

environmental impacts, are commonly referred to as environmental review. Agencies may also

incorporate other environmental laws into their environmental review processes. Environmental

review is typically one step in the federal permitting process. NEPA can also apply to other

agency actions beyond permitting. Additionally, other federal laws may independently impose

procedural or substantive requirements and require authorizations or permits particular to a given

resource.25

NEPA does not apply to actions that are exempted by statute or involve non-discretionary agency

functions, or where the preparation of an environmental document would conflict with another

provision of federal law.26

If a proposed agency action is subject to NEPA and qualifies as a major federal action, the agency

must evaluate its potential environmental impacts to determine the level of environmental review

required.27 The statutory text of NEPA generally dictates the contours of the environmental

review, informed by CEQ guidance, agency procedures, and court decisions.28 Depending on

whether the potential effects are or are not significant, agencies proceed in one of three ways:29

•

Environmental impact statement (EIS). An EIS is required if a proposed agency action

would have a “reasonably foreseeable significant effect on the quality of the human

environment.”30 An EIS is generally limited to 150–300 pages in length; generally has a

two-year deadline; and includes a detailed analysis of potential environmental impacts,

reasonable alternatives to the proposed action, inter-agency consultation, and public

input.31

•

Environmental assessment (EA). An EA sets forth the basis of the agency’s decision to

issue a finding of no significant impact (FONSI) or a determination that significant

impacts are likely, in which case the agency prepares an EIS.32An EA is required when a

proposed agency action not covered by a categorical exclusion is not expected to have a

24 42 U.S.C. § 4332(C).

25 E.g., Endangered Species Act, 16 U.S.C. §§ 1531–1544; National Historic Preservation Act, 54 U.S.C. §§ 300101–

307108.

26 42 U.S.C. § 4336(a). Further, a discretionary action refers to an action where a federal agency has the authority to

choose among different courses of action or decide whether or not to take the action at all, as opposed to an action

where the agency’s decisions are guided by a statutory or regulatory mandate. CEQ, A CITIZEN’S GUIDE TO NEPA:

HAVING YOUR VOICE HEARD 4 (2021), https://ceq.doe.gov/docs/get-involved/citizens-guide-to-nepa-2021.pdf

[https://perma.cc/DTA2-FCK4].

27 42 U.S.C. § 4336(b).

28 For a general overview of NEPA’s environmental review process, see CRS In Focus IF12560, National

Environmental Policy Act: An Overview, by Kristen Hite and Heather McPherron (2025).

29 42 U.S.C. § 4336; id. § 4336(b)(1).

30 Id. § 4332(C).

31 Id. § 4336a. Page limits do not include citations or appendices; as necessary, timelines may be extended in

consultation with the applicant. Id. CEQ recently reported that the median time for EISs completed in 2024 was 2.2

years. CEQ, ENVIRONMENTAL IMPACT STATEMENT TIMELINES (2010−2024), at 1 (2025), https://ceq.doe.gov/docs/nepapractice/CEQ_EIS_Timeline_Report_2025-1-13.pdf [https://perma.cc/2DXL-G4PG]. Agencies are required to consult

with other federal agencies that have “jurisdiction by law or special expertise” and must further share inputs from

federal, state, and local agencies with the public, see 42 U.S.C. §§ 4332, 4336a. Additionally, while agency procedures

vary with respect to public input, every notice of intent to prepare an EIS must include an opportunity for public

comment on alternatives, impacts, and relevant information. Id. § 4336a(c).

32 42 U.S.C. § 4336a. Page limits are exclusive of citations and appendices; as necessary, timelines may be extended in

consultation with the applicant. Id.

Congressional Research Service

4

Judicial Review and the National Environmental Policy Act (NEPA)

“reasonably foreseeable significant effect on the quality of the human environment, or if

the significance of such effects is unknown.”33 An EA is generally limited to seventy-five

pages in length and generally has a one-year deadline.34

•

Categorical exclusion (CE). CEs are categories of actions that a federal agency has

determined normally do not significantly affect the quality of the human environment.35

Agencies maintain lists of available CEs and in some cases may adopt another agency's

CE.36 When a federal agency determines that a proposed action falls within the scope of

an identified CE, it typically does not prepare an EA or EIS absent extraordinary

circumstances.37 Congress may also establish CEs.38

Historically, an estimated 95% or more of actions that are subject to NEPA result in CEs,

approximately 4% in EAs, and 1% or less in EISs.39

Judicial Review Authorities

Under certain circumstances, federal agency environmental reviews may be challenged in federal

court. Historically, fewer than 1% of federal actions subject to NEPA have been litigated.40 While

some have expressed concern that litigation increases the risk of project delays due to the

33 42 U.S.C. § 4336(b)(2).

34 Id. § 4336a. Page limits are exclusive of citations and appendices; as necessary, timelines may be extended in

consultation with the applicant. Id.

35 Id. § 4336e(1).

36

Id. § 4336c; CEQ, Categorical Exclusions: List of Federal Agency Categorical Exclusions (CE List), NEPA.GOV,

https://ceq.doe.gov/nepa-practice/categorical-exclusions.html [https://perma.cc/KK5P-NP3B] (last visited Aug. 12,

2025).

37 Many agencies maintain criteria or lists of conditions known as extraordinary circumstances that warrant special

consideration of impacts for proposed actions otherwise anticipated to have insignificant impacts. See, e.g., DEP’T OF

ENERGY, NATIONAL ENVIRONMENTAL POLICY ACT IMPLEMENTING PROCEDURES 23 (2025).

38 See, e.g., 16 U.S.C. § 6591e (directing the Forest Service to establish a categorical exclusion for mule deer and sage

grouse vegetation enhancement). Congress sometimes provides direction to agencies on CEs See, e.g., 42 U.S.C. §

15492 (creating a “rebuttable presumption” allowing the agency to apply a CE); 16 U.S.C. § 6592b (establishing a CE

for wildfire management subject to specific conditions); 49 U.S.C. § 304 (detailing conditions for applying a CE for

multimodal projects, including that extraordinary circumstances do not apply); see also CRS Report R48595,

Legislative Categorical Exclusions Under the National Environmental Policy Act (2025).

39 Update to the Regulations Implementing NEPA Procedural Provisions, 85 Fed. Reg. 43304, 43305 (July 16, 2020)

(estimating that agencies applied at least 100,000 CEs compared to several hundred EISs undertaken each year); U.S.

GOV’T ACCOUNTABILITY OFF., GAO-14-370, NATIONAL ENVIRONMENTAL POLICY ACT: LITTLE INFORMATION EXISTS ON

NEPA ANALYSES 7 (2014), https://www.gao.gov/assets/gao-14-370.pdf [https://perma.cc/BU4A-Q36B] (citing CEQ

statistics). CEQ has reported that out of 192,707 NEPA reviews associated with activities and projects funded between

2009 and 2011 by the American Recovery and Reinvestment Act of 2009, Pub. L. No. 111-5, 123 Stat. 115, 184,733

were completed using CEs, 7,133 were completed using EAs, and 841 required EISs. CEQ, THE ELEVENTH AND FINAL

REPORT ON THE NEPA STATUS AND PROGRESS FOR AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009 ACTIVITIES

AND PROJECTS 4 (2011).

40 CEQ, NEPA LITIGATION SURVEYS 2001–2013, https://ceq.doe.gov/docs/ceq-reports/nepa-litigation-surveys-20012013.pdf [https://perma.cc/G58E-BTFZ] (identifying an average of 145 cases/year subject to litigation); 85 Fed. Reg. at

43305, 43309 & n.5, n.40 (July 16, 2020) (identifying over 100,000 NEPA actions annually). An analysis of the CEQ

NEPA Litigation data set found that roughly 1 in 450 NEPA decisions were litigated. See John Ruple & Kayla Race,

Measuring the NEPA Litigation Burden: A Review of 1,499 Federal Court Cases, 50 ENV’T L. 479 (2020). For context,

NEPA has been the most litigated of all environmental laws, see CEQ, FACT SHEET: MODERNIZING CEQ’S NEPA

REGULATIONS (2020), https://ceq.doe.gov/docs/laws-regulations/ceq-final-rule-fact-sheet-2020-07-15.pdf

[https://perma.cc/UG5R-8W5F].

Congressional Research Service

5

Judicial Review and the National Environmental Policy Act (NEPA)

potential for a judge to order a project halted (a form of injunctive relief), others have suggested

that NEPA-related litigation delay concerns are “overblown.”41

Plaintiffs seeking to challenge agency NEPA reviews (or failures therein) can bring their

challenges in federal court. Many of these challenges are brought pursuant to the APA, which

provides a cause of action for challenges to final agency actions.42 The APA is a default statute

that applies in the absence of another statute providing judicial review for a particular agency

action. NEPA’s provision allowing a project sponsor to sue to enforce an agency deadline for

completing an EA or EIS is one such example.43 Other examples of more specific statutes

providing for review include the Natural Gas Act and the Air Tour Management Act of 2000.44

Unless a statute provides otherwise, a plaintiff filing a claim to challenge a federal agency’s

NEPA review (or lack thereof) typically files suit in federal district court, with cases decided by a

presiding judge as opposed to a jury.45

Administrative Procedure Act

Except where a more specific statute controls, the APA permits agency actions to be challenged in

federal district court. The APA generally establishes how courts review agency actions, including

the appropriate standards of review.46 Most commonly for NEPA, a plaintiff may ask a court to

“set aside” an agency action if it was “arbitrary, capricious, an abuse of discretion, or otherwise

not in accordance with law.”47 In such a situation, a court considers whether the agency action

was reasonable and reasonably explained.48 Additional bases for setting aside an agency action

include when an agency violates a statutory right or fails to follow a procedure required by law,

among others.49 By statute, an action may not be reviewed until it is final, so documents such as a

41 For more discussion of permitting litigation considerations, compare Michael Bennon & David Wilson, NEPA

Litigation over Large Energy and Transport Infrastructure Projects, 53 ENV’T L. REP. 10836 (2023) (identifying

litigation arising in 28% of select major transportation infrastructure projects requiring an EIS, of which 89% involved

a NEPA claim) with David E. Adelman et al., Dispelling the Myths of Permitting Reform and Identifying Effective

Pathways Forward, 55 ENV’T L. REP. 10038, 10041–42 (2025) (characterizing as a “myth” the notion that federal

permitting is the cause for most project delays and noting a 90% decline in the number of EISs prepared annually from

the 1970s to 2020s).

42 5 U.S.C. § 704.

43 See id. § 706; 42 U.S.C. § 4336a(g)(3).

44 15 U.S.C. § 717r; 49 U.S.C. § 40128(b)(5).

45 See 5 U.S.C. § 703; 28 U.S.C. § 1331. Some statutes specifically provide for direct review of an agency action in the

federal courts of appeals, bypassing district courts with further appeal available only directly to the United States

Supreme Court. E.g., 15 U.S.C. § 717r(d). Others expressly exempt an agency from NEPA compliance or otherwise

limit NEPA’s application. See, e.g., Ctr. for Biological Diversity v. Trump, 453 F. Supp. 3d 11 (D.D.C. 2020)

(declining to require NEPA compliance where a statute allowed the Department of Homeland Security to waive NEPA

requirements for border wall construction).

46 5 U.S.C. § 704. For more information on judicial review under the APA, see CRS Legal Sidebar LSB10558, Judicial

Review Under the Administrative Procedure Act (APA), by Jonathan M. Gaffney (2024); CRS Report R44699, An

Introduction to Judicial Review of Federal Agency Action, by Jared P. Cole (2016).

47 5 U.S.C. § 706; see also Marsh v. Or. Nat. Res. Council, 490 U.S. 360, 378 (1989) (explaining that an arbitrary-andcapricious review is a “searching and careful” factual inquiry based on a “narrow” standard of “whether the decision

was based on a consideration of the relevant factors and whether there has been a clear error of judgment.” (quoting

Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 416 (1971))). As a part of the judicial review process

under the APA, federal courts “decide all relevant questions of law, interpret constitutional and statutory provisions;

and determine the meaning or applicability of the terms of an agency action.” 5 U.S.C. § 706.

48 See Motor Vehicle Mfrs. Ass’n of United States, Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43, 103 (1983);

Seven Cnty. Infrastructure Coal. v. Eagle County, 145 S. Ct. 1497, 1511 (2025).

49 5 U.S.C. § 706.

Congressional Research Service

6

Judicial Review and the National Environmental Policy Act (NEPA)

draft EIS typically cannot be challenged as violating the APA.50 When evaluating the action, a

judge reviews the whole applicable portion of the agency’s record, typically accepting the facts as

the agency has found them barring certain exceptions.51

Enforcing NEPA Deadlines to Prepare an EA or EIS

As amended in 2023, NEPA contains one provision that directly allows for judicial review,

available only to a project sponsor seeking to enforce statutory time limits for an agency to

prepare an EIS or EA.52 One of the first cases to consider this provision is Signal Peak Energy v.

Haaland, which concerned a proposed expansion of the Bull Mountain Mine in Montana.53 In

February 2024, Signal Peak Energy petitioned the U.S. District Court for the District of Columbia

to enforce NEPA’s two-year timeline for agencies to complete an EIS.54 In August 2024, the court

determined that the claim was “prudentially unripe.”55 The court reasoned that the government

could plausibly still make or extend the deadline, so it was premature to find a violation, and

further that the project sponsor was unlikely to suffer substantial immediate economic harm from

the delay.56 The agency subsequently issued an EIS in June 2025, resulting in the case being

dismissed.57 Prior to dismissal, conservation groups tried unsuccessfully to intervene in the

lawsuit. In rejecting their attempt, the court reasoned that NEPA’s provision allowing a court to

review EIS deadlines “does not appear to have been designed with conservation groups in

mind.”58 If other courts take the same approach, both environmental interests and project sponsors

may be unsuccessful in seeking to prospectively enforce NEPA’s deadlines for agencies to

complete an EIS (two years) or EA (one year). In other words, a project sponsor could seek

judicial review only once an agency has failed to meet that deadline.

50 Id. § 704; Bennett v. Spear, 520 U.S. 154, 178 (1997) (explaining that a “final” action is the consummation of an

agency’s decisionmaking affecting rights and obligations or other legal consequences). Examples of situations where

finality issues affected plaintiffs’ NEPA claims include Whitewater Draw Nat. Res. Conservation Dist. v. Mayorkas, 5

F.4th 997 (9th Cir. 2021) (affirming that lack of instructions on how to implement NEPA in an agency handbook did

not rise to a final agency action); Cnty. Comm’rs of Cnty. of Sierra v. U.S. Dep’t of the Interior, 614 F. Supp. 3d 944,

947, 953 (D.N.M. 2022) (dismissing a claim challenging a decision to transfer two individual wolves); see also

Driftless Area Land Conservancy v. Rural Utils. Serv., 74 F.4th 489, 495 (7th Cir. 2023) (finding that adoption of an

EIS without issuing a record of decision was insufficient to constitute final agency action for the purpose of challenging

the underlying decision).

51 5 U.S.C. § 706; see also Citizens to Preserve Overton Park, 401 U.S. at 415 (discussing de novo review of facts

when an adjudication involves inadequate factfinding resulting in an “unwarranted” agency decision as one of two

specific circumstances).

52 42 U.S.C. § 4336a(g)(3).

53 Signal Peak Energy, LLC v. Haaland, No. 24-cv-00366, 2024 WL 3887386 (D.D.C. Aug. 21, 2024).

54 Id. 42 U.S.C. § 4336a(g) provides that agencies generally complete an EIS within two years, which may be extended

if necessary to allow completion, “in consultation with the applicant.” 42 U.S.C. § 4336a(g)(3) allows a project sponsor

to petition a court to review an agency’s alleged failure to meet the deadline and to order a schedule for EIS

completion.

55 The court partially dismissed the claim and denied as moot Signal Peak Energy’s petition for a preliminary injunction

to enforce the two-year EIS deadline on the basis. Signal Peak Energy, 2024 WL 3887386, at *9. The doctrine of

prudential ripeness encourages courts to not prematurely decide abstract disagreements that are not yet fit for a judicial

decision where the parties will not suffer hardship if the court withholds consideration until an agency’s action is

sufficiently final. See Abbott Labs. v. Gardner, 387 U.S. 136, 148–49 (1967); Nat’l Treasury Emps. Union v. United

States, 101 F.3d 1423, 1431 (D.C. Cir. 1996).

56 Signal Peak Energy, 2024 WL 3887386, at *9–10.

57 Minute Order, Signal Peak Energy, LLC v. Haaland, No. 24-cv-00366 (D.D.C. July 3, 2025).

58 Signal Peak Energy, 2024 WL 3887386, at *6–7. The court allowed conservation groups to submit an amicus brief.

Id. at *7.

Congressional Research Service

7

Judicial Review and the National Environmental Policy Act (NEPA)

Deputizing Federal Actors: Waiver of Sovereign Immunity

Certain statutes allow states or local authorities to assume responsibility for NEPA compliance in

limited circumstances.59 In those cases, federal law generally requires that any such nonfederal

authority expressly waive sovereign immunity and accept jurisdiction of the federal courts to

consider allegations of noncompliance.60 For example, the Federal Highway Administration and

the Department of Transportation have procedures available to sign a memorandum of

understanding allowing a state or local agency to assume responsibility for NEPA or broader

environmental review authority generally reserved to federal agencies.61 As of July 2025, seven

states had entered into such an agreement.62 In those cases, the nonfederal implementing authority

is required to accept jurisdiction in federal court for suits alleging violations of NEPA, and the

federal government may be immune from lawsuits.63 In such circumstances, the assigned

nonfederal implementing authority is held to the same standards of review under NEPA as if it

were a federal agency.64

Considerations for Judicial Review of NEPA

Litigation

A number of questions frequently arise with respect to how courts resolve NEPA disputes. Many

of these questions relate to principles that limit the availability of judicial review of agency

action.65 Some limitations are constitutional, while others are rooted in statute. In the context of

challenges to federal agencies’ NEPA reviews, some of the more commonly cited limitations for

permitting-related challenges are briefly discussed below. Other limitations include mootness and

statutory preclusion.66 As discussed above, Congress may further limit review of NEPA claims.

59

E.g., 23 U.S.C. §§ 326, 327 (allowing the Federal Highway Administration to assign states oversight of

environmental reviews including NEPA or CE decisions, respectively).

60 E.g., id. at § 327(c) (requiring a written agreement from a state consenting to federal court jurisdiction over

“compliance, discharge, and enforcement of any responsibility of the Secretary assumed by the State”).

61 Id.; 23 C.F.R. §§ 773.101–117 (2025); FED. HWY. ADMIN., ENVIRONMENTAL REVIEW TOOLKIT – NEPA ASSIGNMENT,

https://www.environment.fhwa.dot.gov/nepa/program_assignment.aspx [https://perma.cc/48Y6-TLP6] (last visited

Aug. 5, 2025).

62 FED. HWY. ADMIN., supra note 61. The seven states are Alaska, Arizona, California, Florida, Ohio, Utah, and Texas.

Nebraska was listed as “under consideration.” Id. Under a pilot program, the Federal Highway Administration may

elect to enter into a further agreement with two states that have a signed a memorandum of understanding to allow

substitution of state procedures for NEPA. See 23 U.S.C. § 330; Program for Eliminating Duplication of Environmental

Review, 85 Fed. Reg. 84213 (Dec. 28, 2020) (to be codified at 23 C.F.R. pts. 773, 778).

63 See, e.g., Bitters v. Fed. Hwy. Admin., No. 1:14-cv-01646-KJM-SMS, 2016 WL 159216, at *18 (E.D. Cal. Jan. 13,

2016) (reviewing California Department of Transportation’s compliance with NEPA); Salt Lake City Corp. v.

Shepherd, No. 2:23-CV-786, 2024 WL 2158128, at *3 (D. Utah May 14, 2024) (finding the federal government to be

shielded from suit by sovereign immunity).

64 See, e.g., Fath v. Tex. Dep’t of Transp., 924 F.3d 132 (5th Cir. 2018) (upholding Texas Department of

Transportation’s NEPA review based on Federal Highway Administration NEPA regulations and federal case law).

65 For an overview of judicial review of agency action and a discussion of limitations on the availability of judicial

review, see CRS Report R44699, An Introduction to Judicial Review of Federal Agency Action, by Jared P. Cole

(2016).

66 A case is moot if the controversy initially existing at the time the lawsuit was filed is no longer “live.” See, e.g.,

Native Village of Nuiqsut v. Bureau of Land Mgmt., 9 F.4th 1201 (9th Cir. 2021) (denying NEPA claim as moot where

oil and gas producer had completed a project following agency approval of winter drilling exploration activities after

all equipment had been demobilized, weather had warmed, and wells were capped). Statutory preclusion refers to a

provision in the APA specifying that the judicial review provisions do not apply if “statutes preclude judicial review.” 5

U.S.C. § 701(a)(1). While a modest set of statutes exclude specific actions or types of actions from judicial review

(continued...)

Congressional Research Service

8

Judicial Review and the National Environmental Policy Act (NEPA)

Courts have also addressed what level of deference is appropriate when applying the arbitraryand-capricious standard of review to agency actions taken pursuant to NEPA.

Agency Discretion and Deference in Arbitrary-and-Capricious

Cases

The Supreme Court has observed that on matters of agency policymaking and factfinding

(including as applies to NEPA), the APA imposes a deferential standard of review; no similar

deference exists with respect to matters of statutory interpretation.67 In Seven County

Infrastructure Coalition v. Eagle County, the Supreme Court reiterated that the role of courts is

deferential and limited when evaluating agency NEPA reviews under the APA’s arbitrary-andcapricious standard.68 Particularly on factual matters such as evaluation of significant impacts,

courts have held that they should not substitute their judgment for that of the agency. Instead, a

court typically considers whether the agency action was reasonable and reasonably explained.69

Applying NEPA’s inherent “rule of reason,” courts have identified various factors for determining

whether an agency’s NEPA review may be found arbitrary and capricious.70 Many courts have

applied long-standing Supreme Court precedent in a NEPA-specific context, such as when an

agency has relied on factors Congress did not intend it to consider, “entirely failed” to consider an

important aspect of the problem, offered an explanation for its decision that runs counter to the

evidence before it, or is implausible beyond a mere difference in view or the product of agency

expertise.71 A court may also find an agency’s NEPA review was arbitrary and capricious if it

“failed to base its decision on consideration of the relevant factors” or made a “clear error in

judgment.”72

under NEPA, the exception is relatively uncommon and generally requires a “persuasive reason” to believe that

Congress intended to exclude a claim from judicial review. Bowen v. Mich. Acad. of Family Physicians, 476 U.S. 667,

670 (1986); see also Mass. Coal. for Immig. Reform v. U.S. Dep’t of Homeland Sec., 621 F. Supp. 3d 84, 98 (D.D.C.

2022) (finding review of alleged failure to conduct a NEPA review prior to instituting administrative closure in

immigration courts was not barred by a provision in the Immigration and Nationality Act excluding review of

immigration removal decisions themselves).

67 Seven Cnty. Infrastructure Coal., 145 S. Ct. 1497; Loper Bright Enters. v. Raimondo, 603 U.S. 369, 371, 392 (2024)

(citing 5 U.S.C. § 706(2)).

68 Seven Cnty. Infrastructure Coal., 145 S. Ct. 1497.

69 Id. at 1511 (citing Motor Vehicle Mfrs. Ass’n of United States, Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29,

103 (1983)).

70 Seven Cnty. Infrastructure Coal., 145 S. Ct. at 1513; Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752, 767 (2004); see

also Diné Citizens Against Ruining Our Env't v. Haaland, 59 F.4th 1016, 1029 (10th Cir. 2023) (specifying four ways

in which an agency’s NEPA review may be arbitrary and capricious). Courts may further apply a “substantial

evidence” standard to NEPA reviews, setting aside agency action under the APA only where it is supported by

substantial evidence. See, e.g., WildEarth Guardians v. U.S. Army Corps of Eng’rs, 429 F. Supp. 3d 1224, 1263

(D.N.M. 2019) (citing Forest Guardians v. U.S. Fish & Wildlife Serv., 611 F.3d 692, 704 (10th Cir. 2010)).

71 Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43. For example, an agency “entirely failed” to consider an important element

of the analysis when it failed to consider greenhouse gas impacts or at least explain its reason for not doing so when

there were methods available for such a calculation. See Gulf v. Burgum, 775 F. Supp. 3d 455, 481 (D.D.C. 2025).

Another example is an “unexplained inconsistency” in analysis, see Montana Wildlife Fed’n v. Haaland, 127 F.4th 1,

36 (9th Cir. 2025). Courts may, however, uphold an agency’s review where it explained its choice of methodology for

calculating climate impacts. See Diné Citizens, 59 F.4th at 1043. But see Citizens Action Coal. of Indiana, Inc. v.

FERC, 125 F.4th 229, 241 (D.C. Cir. 2025) (upholding an agency’s choice of climate methodology).

72 For examples of how courts consider relevant factors in NEPA cases, see Am. Wild Horse Campaign v. Raby, No.

24-8055, 2025 WL 1933473, at *4 (10th Cir. July 15, 2025) (quoting New Mexico ex rel. Richardson v. Bureau of

Land Mgmt., 565 F.3d 683, 704 (10th Cir. 2009); Utah Env’t Cong. v. Troyer, 479 F.3d 1269, 1280 (10th Cir. 2007)).

(continued...)

Congressional Research Service

9

Judicial Review and the National Environmental Policy Act (NEPA)

Standing

Article III of the Constitution limits the federal courts’ jurisdiction to adjudicating “cases” and

“controversies.”73 As part of this requirement, a litigant must have standing in order to invoke the

jurisdiction of a federal court. To establish standing, a plaintiff must demonstrate (1) an injury in

fact (2) that is fairly traceable to the challenged action (e.g., caused by an alleged statutory

violation) and (3) that can be remedied by a court.74 To meet the Article III injury threshold, a

plaintiff must allege that the agency’s action has harmed or will harm the plaintiff’s concrete

interest.75 Standing principles also prohibit courts from addressing alleged injuries that are

“generalized grievances,” as these do not present “cases” or “controversies” as required by Article

III.76

The Supreme Court has long recognized that a plaintiff alleging a procedural injury—including a

NEPA violation—may be subject to a modified standing requirement of demonstrating a concrete

interest in a legally recognized procedure.77 For example, in considering whether an alleged

injury falls within the “zone of interests” of NEPA,78 the Supreme Court has held that NEPA

protects a broad range of harms, including recreational or aesthetic enjoyment of the

environment.79 While NEPA does not reach purely economic injuries, plaintiffs who allege both

environmental and economic injuries may satisfy the “zone of interests” test.80 Additionally,

An example of an error in judgment is City of Los Angeles v. Fed. Aviation Admin., 63 F.4th 835, 851–52 (9th Cir.

2023) (finding a “fundamental error” where the agency failed to consider combined noise impacts from multiple pieces

of construction running simultaneously and had instead analyzed conditions as if only one machine were operating at

any given time).

73 U.S. CONST. art. III, § 2.

74 Friends of the Earth v. Laidlaw, 528 US 167, 180–81 (2000); Lujan v. Defenders of Wildlife, 504 U.S. 555, 560

(1992).

75 Defs. of Wildlife, 504 U.S. at 560 (applying imminent and concrete injury to a protected right as the general standard

for a plaintiff to establish standing).

76 Lexmark Int’l, Inc. v. Static Control Components, Inc., 572 U.S. 118, 127 n.3 (2014).

77 Id. at 572 & n.7 (recognizing procedural rights as “special” and applying a modified standing requirement applies to

a plaintiff with a concrete interest in a legally recognized procedural right “without meeting all the normal standards for

redressability and immediacy,” such as could be the case for a claim arising under NEPA if a plaintiff alleges an EIS

failed to consider future impacts to a nearby property in a pending permitting decision).

78 Ondrusek v. U.S. Army Corps of Eng’rs, 123 F.4th 720, 734 (5th Cir. 2024) (noting the redressability standard is

“not demanding” (citing Sierra Club v. FERC, 827 F.3d 59, 67 (D.C. Cir. 2016) and Defs. of Wildlife, 504 U.S. at 572

n.7). The Supreme Court previously described this requirement as part of its “prudential standing” doctrine, but in

Lexmark, recharacterized the requirement as a question of statutory interpretation. Lexmark Int’l., 572 U.S. at 127–28.

79 Lujan v Nat’l Wildlife Fed’n, 497 U.S. 871 (1990).

80 See, e.g., Maiden Creek Assoc. LP v. U.S. Dep’t of Transp., 823 F.3d 184, 195 (3d Cir. 2016) (“To accept NEPA

litigants whose interests accidentally overlap with the statute’s intended purpose would not only create a class of

plaintiffs far larger than Congress originally intended, it also would serve to distort the effect of NEPA itself.”); Solar

Energy Indus. Ass’n v. FERC, 80 F.4th 956, 991 (9th Cir. 2023) (allowing a NEPA suit even if a plaintiff’s interest is

primarily economic so long as there as the economic injuries are “causally related to an act within NEPA’s embrace” or

if there is a separate environmental interest (quoting Port of Astoria. v. Hodel, 595 F.2d 467, 476 (9th Cir. 1979))).

Plaintiffs who assert environmental injuries, but whose primary motive for bringing suit is economic interest, also

“routinely satisfy” this test; however, plaintiffs who assert purely economic injuries do not. Compare Mass. Coal. for

Immig. Reform v. U.S. Dep’t of Homeland Sec., 621 F. Supp. 3d 84, 94 (D.D.C. 2022) (finding sufficient connection

to an environmental interest to meet a relaxed zone of interest test due to NEPA being a procedural statute) with

Louisiana v. Dep’t of Homeland Sec., 726 F. Supp. 3d 653, 688 (E.D. La. 2024) (dismissing case due to lack of

standing after plaintiffs failed the “zone of interest” test under NEPA where injuries were “purely economic”).

Congressional Research Service

10

Judicial Review and the National Environmental Policy Act (NEPA)

courts have found that a NEPA violation could be remedied if the agency could conceivably

change its position on whether or how to proceed with the underlying action.81

Organizations often bring cases on behalf of their members, including NEPA-based challenges.

They may satisfy the standing requirements if (1) at least one of the members has standing, (2)

the interests that the organization seeks to protect are germane to its purposes, and (3) neither the

claim nor the type of relief sought would require the individual members to actively participate in

the litigation.82

Exhaustion

Some statutes have explicit requirements that bar a claim if a plaintiff has not first exhausted

administrative options, such as by participating in an agency’s administrative process for raising

objections to a permitting matter.83 The Supreme Court has determined the APA has no express

exhaustion requirement.84 Even where a statute is silent, courts generally expect a plaintiff to

provide notice to and raise their issues with the relevant agency during the appropriate comment

period for the proposed agency action, and if a plaintiffs does not do so, a judge has some degree

of discretion to bar a later claim involving those issues.85 In other situations, a court may follow

the Supreme Court’s suggestion that flaws in an EA or EIS “might be so obvious that there is no

need for a commentator to point them out specifically in order to preserve its ability to challenge

a proposed action.”86

Statute of Limitations

A statute of limitations is a provision in law specifying a time by which a plaintiff must file a

lawsuit. If the specific statute at issue is silent, courts have generally defaulted to a six-year limit

for a plaintiff who challenges a permitting action under the APA.87 Some permitting-related

statutes include limitations affecting timelines for review on certain NEPA claims. For example,

judicial review of some transportation projects is limited to 150 days after notice that the permit,

81 Ondrusek, 123 F.4th at 734.

82 Sierra Club v. Morton, 405 U.S. 727, 739–40 (1972); Sierra Club v. FERC, 827 F.3d 59, 65 (D.C. Cir. 2016) (citing

Hunt v. Wash. State Apple Advert. Comm’n, 432 U.S. 333, 343 (1977)); Mountain Cmtys. for Fire Safety v. Elliott, 25

F.4th 649, 6554 & n.6 (9th Cir. 2022) (citing Friends of the Earth, Inc. v. Laidlaw Env't Servs. (TOC), Inc., 528 U.S.

167, 169 (2000).

83 See, e.g., 16 U.S.C. § 6515(c).

84 Darby v. Cisneros, 509 U.S. 137, 146–47 (1993).

85 See, e.g., Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752, 764−765 (2004); Vt. Yankee Nuclear Power Corp. v. Nat.

Res. Def. Council, 435 U.S. 519, 553 (1978). But see Mulgrew v. U.S. Dep’t of Transp., 750 F. Supp. 3d 171, 215

(S.D.N.Y. 2024) (“[A]n issue is exhausted if it was included in a comment on the EA—regardless of who submitted the

comment.”).

86 Pub. Citizen, 541 U.S. at 765. See also, e.g, Friends of Tims Ford v. Tenn. Valley Auth., 585 F.3d 955, 964 (6th Cir.

2009) (allowing a NEPA challenge to proceed because the agency had not shown why the “deficient” EIS “was not so

obvious that [plaintiffs] needed to comment to preserve its right to appeal”); Mulgrew, 750 F. Supp. 3d at 215

(permitting a claim to proceed based on constructive notice of a matter raised by a third party).

87 28 U.S.C. § 2401(a) states that “every civil action commenced against the United States shall be barred unless the

complaint is filed within six years after the right of action first accrues.” The Supreme Court held in 2024 that, for the

purposes of facial challenges to agency actions, a claim accrues when an injury to the plaintiff occurs, rather than at the

time the agency action becomes final. Corner Post, Inc. v. Bd. of Governors of the Fed. Reserve Sys., 603 U.S. 799

(2024); see also CRS Legal Sidebar LSB11197, Corner Post and the Statute of Limitations for Administrative

Procedure Act Claims, by Benjamin M. Barczewski and Jonathan M. Gaffney (2024).

Congressional Research Service

11

Judicial Review and the National Environmental Policy Act (NEPA)

license, or approval is final.88 For large infrastructure and other projects covered under FAST-41,

Congress has imposed a maximum two-year statute of limitations on authorizations.89

Common Issues in NEPA Litigation

NEPA litigation involves a wide range of agencies and raises issues involving agency choices and

determinations. This section provides an overview of selected issues raised in NEPA litigation

that may be of interest to Congress.

Is a NEPA Review Required?

Is the Action Reviewable as a Final Major Federal Action?

NEPA applies if an agency’s proposed activity is a major federal action.90 To qualify, the

proposed action must be “subject to substantial Federal control and responsibility” and not

subject to any statutory exceptions.91 For example, NEPA excludes actions with no or minimal

federal funding and those with no or minimal federal involvement where the agency cannot

control the outcome of the project.92

If an agency fails to initiate any environmental review for an action covered by NEPA, plaintiffs

may challenge that in court, provided they can show the proposed action qualifies as a final

agency action subject to the requirements of NEPA. For example, there may be questions about to

what extent NEPA is triggered in discrete agency actions associated with a project implemented

in multiple phases that require assorted federal approvals over the course of the project.93 In

deciding whether any particular agency action for such a project requires NEPA review, courts

may consider whether the agency action would irreversibly commit federal resources in

furtherance of the proposed action as a standard to determine whether the agency activity is a

qualifying action under NEPA.94 Even where an action qualifies as a major federal action under

NEPA, there may be disputes over whether a proposed action is reviewable in court as a final

agency action under the APA. To have a cause of action under the APA, the challenged action

must also be considered a final agency action.95

88 E.g., 23 U.S.C. § 139(l).

89 42 U.S.C. § 4370m-6; id. § 4370m(6) (defining “covered project”); see also 42 U.S.C. § 4370m (3) defining

authorization as “any license, permit, approval, finding, determination, or other administrative decision issued by an

agency and any interagency consultation that is required or authorized under Federal law in order to site, construct,

reconstruct, or commence operations of a covered project administered by a Federal agency or, in the case of a State

that chooses to participate in the environmental review and authorization process in accordance with section 4370m–

2(c)(3)(A) of this title, a State agency.” “Authorization” includes both permits and federal actions related to the

permitting process). The two-year time limit for FAST-41’s statute of limitations begins upon publication in the

Federal Register, and the time period may be shorter if so specified in federal law. Id. at § 4370m-6(1).

90 Id. §§ 4332(c), 4336e(10).

91 Id. § 4336e(10).

92 See id. § 4336e(10)(B).

93 See, e.g., N. Alaska Env’t Ctr. v. U.S. Dep’t of the Interior, 983 F.3d 1077 (9th Cir. 2020).

94 Id. at 1086 (discussing circumstances under which a federal lease could trigger NEPA based on whether it would

allow or preclude surface-disturbing activity); Ctr. for Biological Diversity v. U.S. Dep’t of the Interior, 563 F.3d 466,

480 (D.C. Cir. 2009).

95 5 U.S.C. § 704; Bennett v. Spear, 520 U.S. 154, 178 (1997) (explaining that a “final” action is the consummation of

an agency’s decisionmaking affecting rights and obligations or other legal consequences). Examples of situations

(continued...)

Congressional Research Service

12

Judicial Review and the National Environmental Policy Act (NEPA)

Is the Action Exempt from NEPA Due to Competing Authority?

Courts must occasionally address what happens when an agency is faced with a potential conflict

or overlap between NEPA and other statutory mandates. As the Supreme Court has held, NEPA

was not intended to repeal any other statute by implication.96 Thus, when “a clear and

unavoidable conflict in statutory authority exists, NEPA must give way.”97 Such a conflict may

exist, for example, if the period for implementing a statutory mandate is too short for an agency

to complete environmental review under NEPA.98 Some courts have also held that NEPA does not

apply when an agency’s actions to comply with other statutes are “functional[ly] equivalent” to

NEPA.99 This analysis requires courts to assess, on a case-by-case basis, what an agency must

take into account when complying with other statutes, especially with respect to environmental

effects or considerations.100

Does New Activity Warrant Additional Analysis?

When considering new activity related to a prior action that already has documented analysis of

environmental impacts or when supplementing earlier NEPA analysis, an agency may refer back

to the existing analysis and incorporate it by reference or take a multiphased approach such as

starting with a broader strategic level review and then supplementing on a project-specific basis

with analysis limited to new conditions or information (tiering).101 Sometimes this analysis is

undertaken as a supplemental EA or EIS. Other times, an agency incorporates earlier NEPA

analysis by reference. In some cases, an agency may issue supplemental analysis when a court

remands environmental review to an agency to correct a deficiency in its initial analysis.102

where finality issues affected plaintiffs’ NEPA claims include Whitewater Draw Nat. Res. Conservation Dist. v.

Mayorkas, 5 F.4th 997 (9th Cir. 2021) (affirming that lack of instructions on how to implement NEPA in an agency

handbook did not rise to a final agency action); Cnty. Comm’rs of Cnty. of Sierra v. U.S. Dep’t of the Interior, 614 F.

Supp. 3d 944, 947, 953 (D.N.M. 2022) (dismissing a claim challenging a decision to transfer two individual wolves);

see also Driftless Area Land Conservancy v. Rural Utils. Serv., 74 F.4th 489, 495 (7th Cir. 2023) (finding that adoption

of an EIS without issuing a record of decision was insufficient to constitute final agency action for the purpose of

challenging the underlying decision); Citizens for Clean Energy v. U.S. Dep’t of the Interior, 384 F. Supp. 3d 1264,

1281 (D. Mont. 2019) (clarifying that a decision to not prepare a NEPA document is reviewable as a final agency

action).

96 United States v. SCRAP, 412 U.S. 669, 694 (1973); see also 42 U.S.C. § 4332(C) (stating that environmental review

is not required “where compliance would be inconsistent with other statutory requirements”).

97 Flint Ridge Dev. Corp. v. Scenic Rivers Ass’n of Okla., 426 U.S. 776, 788 (1976).

98 Id. at 788–89 (finding it “inconceivable” that an agency could comply with NEPA within the thirty-day deadline for

issuance of statement of record under Disclosure Act).

99 Prutehi Litekyan: Save Ritidian v. U.S. Dep’t of Airforce, 128 F.4th 1089, 1117 (9th Cir. 2025) (quoting Alabama ex

rel. Siegelman v. EPA, 911 F.2d 499, 504 (11th Cir. 1990)).

100 See, e.g., Env’t Def. Fund, Inc. v. EPA, 489 F.2d 1247 (D.C. Cir. 1973) (holding the Federal Insecticide, Fungicide,

and Rodenticide Act to be the functional equivalent of NEPA because the statute required the agency to take

environmental effects into account and consider public comments about such effects); see also Pac. Legal Found. v.

Andrus, 657 F.2d 829, 834 (6th Cir. 1981) (discussing lower court practice applying the “functional equivalent” test).

101 See, e.g., Theodore Roosevelt Conservation P’ship v. Salazar, 616 F.3d 497, 512 (D.C. Cir. 2010) (noting that

projects implemented over the course of several decades could understandably be subject to a change of conditions, but

tiering enables agencies to refer back to older analysis so long as the effects are reasonably considered, even if

methodologies have improved); see also 42 U.S.C. § 4336b (authorizing reliance on prior programmatic analysis within

five years of publication barring new circumstances or information or later so long as the agency reevaluates the

analysis and underlying assumptions to verify the earlier analysis “remains valid”).

102 See, e.g., Ctr. for Biological Diversity v. U.S. Bureau of Land Mgmt., 141 F.4th 976, 990–91 (9th Cir. 2025)

(addressing the adequacy of an agency’s supplemental EIS prepared in response to Sovereign Iñupiat for a Living

Arctic v. Bureau of Land Mgmt., 555 F. Supp. 3d 739, 770, 805 (D. Alaska 2021) (invalidating the agency’s initial

NEPA analysis concerning the Willow Project)).

Congressional Research Service

13

Judicial Review and the National Environmental Policy Act (NEPA)

Additionally, a plaintiff may claim that an agency failed to conduct an appropriate supplemental

environmental review. These disputes tend to center on situations where existing NEPA analysis

exists and new information or circumstances arise.103 For example, supplemental analysis could

be warranted for proposed changes to agency salvage logging operations following a wildfire

unless the agency’s environmental review already factored in post-fire conditions.104

Alternatively, if additional action is contemplated where an existing NEPA analysis has already

been completed and there has been no material change in circumstances or information, even a

one-paragraph explanation may be sufficient to defend an agency’s decision to reference back to

existing analysis (tiering) so long as the agency has documented that it determined that no new

information or circumstances warranted further consideration.105

Did the Agency Properly Apply a Categorical Exclusion?

When an agency applies a CE to a specific action, it does not prepare an EA or EIS. Where an

agency determines that site-specific conditions (extraordinary circumstances) exist that could

result in more significant impacts from an action that would otherwise qualify for a CE, the

agency may decline to apply a CE to the action. The presence of an extraordinary circumstance

does not automatically restrict application of the CE, but it can lead an agency to evaluate

whether impacts are anticipated to be significant such that it would be appropriate to prepare an

EA or EIS.106 Agency CE procedures generally require the agency to consider extraordinary

circumstances, but the same may not always be true of congressionally created CEs. At least one

court has ruled that the Forest Service was not required to consider extraordinary circumstances

before applying a congressionally created CE where the statute did not mandate such

consideration.107

When an agency relies on a CE to determine that further NEPA analysis is not required, plaintiffs

may argue that the agency improperly used a CE for a specific action or may challenge the

creation of the CE itself. Whether an agency’s decision to create or apply a CE was arbitrary or

capricious is a fact-specific determination where courts consider whether an agency acted

rationally and followed the appropriate procedures to do so.108

In disputes involving challenges to specific uses of CEs, plaintiffs have raised different theories.

For example, some plaintiffs have alleged that an agency failed to follow its own procedures to

103 See, e.g., No Mid-Currituck Bridge-Concerned Citizens v. N.C. Dep’t of Transp., 60 F.4th 794, 805 (4th Cir. 2023)

(upholding agency’s decision not to supplement in part because the agency determined that new information reinforced

a previous analysis).

104 See, e.g., Earth Island Inst. v. Elliott, 318 F. Supp. 3d 1155, 1184 (E.D. Cal. 2018) (differentiating an obligation to

supplement following new conditions potentially present following a forest fire from a supplemental review that relied

on existing post-fire NEPA analysis).

105 Gulf v. Burgum, 775 F. Supp. 3d 455, at 488–90 (D.D.C. 2025).

106 See, e.g., Los Padres ForestWatch v. U.S. Forest Serv., No. 23-55801, 2024 WL 4750504, at *1 (9th Cir. Nov. 12,

2024) (upholding the agency’s NEPA review because the agency followed applicable NEPA procedures in considering

whether any extraordinary circumstances pertaining to the proposed action would result in significant impacts for the

proposed action prior to applying the CE); Int’l Soc’y for Prot. of Mustangs & Burros v. U.S. Dep’t of Agric., No. CV22-08114-PHX-SPL, 2022 WL 3588223, at *12 (D. Ariz. July 28, 2022) (upholding the agency’s decision to apply a

CE notwithstanding the extraordinary circumstance of endangered species present because the agency showed its

proposed action would be beneficial to the endangered species present).

107 Wild Watershed v. Hurlocker, 961 F.3d 1119, 1127 (10th Cir. 2020).

108 See, e.g., San Luis Obispo Mothers for Peace v. U.S. Nuclear Reg. Comm’n, 100 F.4th 1039, 1058 (9th Cir. 2024)

(determining agency followed its own procedures and reasonably applied its CE).

Congressional Research Service

14

Judicial Review and the National Environmental Policy Act (NEPA)

use a CE.109 In other cases, plaintiffs have argued that an agency improperly relied on multiple

CEs to avoid preparing an EIS.110 While many plaintiffs have alleged that an agency improperly

relied on a CE and should have instead prepared an EIS, at least one plaintiff unsuccessfully sued

an agency for opting to prepare an EIS when it allegedly could have opted to apply a CE.111

Courts may consider whether an agency validly created a CE (sometimes referred to as

“adopting” a CE) or appropriately adopted another agency’s CE. For example, in Sierra Club v.

Bosworth, the plaintiffs alleged that the Forest Service violated the APA by categorically

excluding all fuel reduction projects of up to 1,000 acres and burn projects of up to 4,500 acres.112

The U.S. Court of Appeals for the Ninth Circuit concluded that the Forest Service’s CE violated

the APA because the Service (1) collected data only to justify, rather than assess, the

appropriateness of a CE; (2) failed to explain why the cumulative effect of each project would not

have significant environmental effects; and (3) failed to specify criteria for each type of project

that would ensure a project had no significant environmental effects.113 Additionally, as amended

in 2023, NEPA has also allowed agencies to apply another agency’s CE provided they follow the

appropriate procedures and consults with the “host” agency about the appropriateness of applying

the exclusion in question.114 Some plaintiffs have challenged these applications in court.115

Did the Agency Adequately Analyze Environmental Impacts?

A court may evaluate whether an agency’s NEPA review was arbitrary or capricious based on an

alleged failure to consider certain impacts or to fully consider the weight of the impacts reviewed.

As discussed in more detail below, if an agency makes a decision to move forward with an action

without preparing an EIS—whether by applying a CE, issuing a FONSI, or failing to prepare any

document—plaintiffs can challenge the agency’s decision, asserting that the action would result

in significant impacts and therefore requires preparation of an EIS. In other instances, an agency

may prepare an EIS where plaintiffs allege the analysis failed to consider a key element of the

analysis or an alternative. In these cases, courts generally review the agency’s analysis under the

APA to determine whether the agency’s decision to limit or exclude consideration of particular

effects was arbitrary or capricious. In Seven County Infrastructure Coalition, the Supreme Court

underscored that courts must afford agencies substantial deference in determining whether an

agency reasonably exercised its discretion in determining the appropriate scope and contents of

an EIS.116 In particular, the Court clarified that under this standard, the “only role” for courts is to

109 See, e.g., Oak Ridge Env’t Peace All. v. Perry, 412 F. Supp. 3d 786, 845 (E.D. Tenn. 2019) (invalidating multiple

decisions to apply CEs due to agency’s failure to follow its own regulations in considering extraordinary

circumstances); U.S. Citrus Sci. Council v. U.S. Dep’t of Agric., 312 F. Supp. 3d 884, 915 (E.D. Cal. 2018) (resolving

a disputed application of an agency regulation in favor of the agency’s decision to apply a CE).

110 Compare, e.g., Los Padres, No. CV 22-2781-JFW (SKX), 2023 WL 5667533, at *11 (C.D. Cal. July 19, 2023),

aff'd, 2024 WL 4750504 (9th Cir. Nov. 12, 2024) (upholding the Forest Service’s use of multiple CEs in a single

proposed action where each was separately considered to apply to the overall proposed action and discussing how other

courts have allowed this practice) with Friends of the Inyo v. U.S. Forest Serv., 103 F.4th 543, 556 (9th Cir. 2024)

(invalidating agency action that impermissibly combined CEs in a manner that failed to take a hard look at how each

individual CE applied to the proposed action).

111 See Town of Ogden Dunes v. U.S. Dep’t of the Interior, No. 2:20-CV-34-TLS-JEM, 2022 WL 715549, at *11 (N.D.

Ind. Mar. 10, 2022).

112 510 F.3d 1016 (9th Cir. 2007).

113 Id. at 1026–33.

114 Fiscal Responsibility Act of 2023, Pub. L. No. 118-5, sec. 321(b), § 109, 137 Stat. 10, 43–44.

115 See, e.g., Plaintiffs’ Motion for Summary Judgement, Sierra Club, v. U.S. Dep’t of the Interior, No. 4:24-cv-04651JST (N.D. Cal. Apr. 28, 2025), Dkt. No. 37.

116 Seven Cnty. Infrastructure Coal. v. Eagle County, 145 S. Ct. 1497, 1512 (2025).

Congressional Research Service

15

Judicial Review and the National Environmental Policy Act (NEPA)

“confirm that the agency has addressed environmental consequences and feasible alternatives as

to the relevant project.”117

Did the Agency Reasonably Determine the Appropriate Scope of Impacts?

Disputes regarding the appropriate scope of analysis can arise, including whether anticipated

effects are too attenuated from a proposed action to include in an EIS or EA. As the Supreme

Court explained in Seven County Infrastructure Coalition, an agency should follow a “rule of

reason” rooted in its statutory authority to determine the appropriate scope of a NEPA analysis.118

This analysis built on Department of Transportation v. Public Citizen, in which the Court ruled

that the Federal Motor Carrier Safety Administration did not violate NEPA by not considering the

environmental effects related to a decision beyond the agency’s (and NEPA’s) purview: increased

entry of trucks from Mexico into the United States, which had been authorized by the President

(who is not subject to NEPA) as an outcome of a trade dispute.119 Additionally, the Court has

clarified that a NEPA analysis should focus on the “project at hand” as opposed to broader effects

associated with separate future projects.120

Another set of cases involves allegations that an agency failed to consider all relevant indirect

effects arising from a proposed action. The Supreme Court has acknowledged that the extent to

which an agency must include indirect effects in its NEPA analysis is a matter of agency

discretion.121 In Seven County Infrastructure Coalition, the Court overturned a D.C. Circuit

decision that had relied in part on a series of cases ruling that indirect effects, such as greenhouse

gas impacts, must be considered where relevant to the underlying authority.122 While the Court

acknowledged that environmental effects that “might extend outside the geographic territory of

the project or might materialize later in time”—“so-called indirect effects”—“may fall within

NEPA,” the Court asserted that “courts should defer to agencies’ decisions about where to draw

the line” as to “how far to go in considering indirect environmental effects from the project at

hand.”123 Ultimately, the Court in Seven County upheld the agency’s decision to include some

degree of greenhouse gas impacts in its NEPA analysis in part due to its determination that many

of the effects concerned pertained to separate projects, and further, the APA’s arbitrary-andcapricious standard mandates that courts defer to an agency’s determination on what effects to

include or exclude.124

117 Id. at 1511 (quoting Strycker’s Bay Neighborhood Council, Inc. v. Karlen, 444 U.S. 223, 227 (1980)).

118 Id. at 1513.

119 Dep’t of Transp. v. Pub. Citizen, 541 U.S. 762, 767–68 (2004); see Ala. Wilderness League v. Jewell, 788 F.3d

1212, 1225–26 (9th Cir. 2015).

120 Seven Cnty. Infrastructure Coal., 145 S. Ct. at 1515–16.

121 Id. at 1512–13.

122 Id. at 1518; Eagle County v. Surface Transp. Bd., 82 F.4th 1152, 1178 (D.C. Cir. 2023) (citing, e.g., Sierra Club v.

FERC, 867 F.3d 1357, 1374 (D.C. Cir. 2017) (“[G]reenhouse-gas emissions are an indirect effect of authorizing this

project, which FERC could reasonably foresee, and which the agency has legal authority to mitigate.”)).

123 Seven Cnty. Infrastructure Coalition, 145 S. Ct. at 1513, 1515.

124 Id. at 1520 (Sotomayor, J., concurring) (explaining how the agency included consideration of greenhouse gas

impacts in its environmental analysis); id. at 1516 (specifying that the agency was not required to ask another agency to

consider climate impacts to Gulf Coast communities associated with a separate project); id., at 1517 (“[E]ven if the

reviewing court in such a case might think that NEPA would support drawing a different line, a court should defer to an

agency so long as the agency drew a reasonable and ‘manageable line.’” (quoting Dep’t of Transp. v. Pub. Citizen, 541

U.S. 752, 767 (2004)).

Congressional Research Service

16

Judicial Review and the National Environmental Policy Act (NEPA)

Can the Agency Substantiate Its Determination of Whether Impacts Are

Significant?

Agencies and plaintiffs sometimes disagree about whether an agency should have prepared an

EIS in instances when an agency applied a CE or prepared an EA and then issued a FONSI

documenting the determination that a proposed action would not have significant effects. Courts

consistently require that an agency must take a “hard look” at a proposed action’s potential effects

in order to determine whether impacts are significant, though the specific details are often factand case-specific.125 For example, some plaintiffs have argued an agency improperly segmented a

project by dividing it into discrete, separate actions to “avoid a more thorough consideration of

the impacts of the entire project” or parsed a proposal into subcomponents that could be

completed via some combination of EAs and/or CEs in order to stay below the “significance”

threshold.126 Others have alleged (to varying degrees of success) that an agency lacked enough

data to make a reasoned decision about whether effects were significant.127 Other disputes involve

questions about an agency’s reliance on certain types of information, such as whether an agency

inappropriately relied on outdated information or circumstances substantially changed before the

agency finalized its decision (and failed to update its analysis).128

In some situations, an agency may face litigation over its decision to prepare an EA and issue a

FONSI where impacts could have been significant but for mitigation measures intended to

address anticipated impacts.129 This is sometimes known as a mitigated FONSI.130 Agencies may

also include mitigation measures as a condition for proceeding with a proposed action when

issuing an EIS or authorizing use of a CE. Such mitigation measures may be enforceable in

court.131

125 Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350 (1989); see also Friends of the Floridas v. U.S.

Bureau of Land Mgmt., 746 F. Supp. 3d 1039, 1151 & n.48 (D.N.M. 2024) (discussing how courts apply a “hard look”

requirement for NEPA and the APA).

126 Tinian Women Ass’n v. U.S. Dep’t of the Navy, 976 F.3d 832, 838 (9th Cir. 2020); see, e.g., Sierra Club v. U.S.

Army Corps of Eng’rs, No. 2:20-CV-396-LEW, 2025 WL 961432, at *22 (D. Me. Mar. 31, 2025).

127 Compare Sierra Club, 2025 WL 961432, at *22 (declining to hold agency to standard of “perfection” in considering

best available evidence and upholding a NEPA review where agency adequately considered information available to it)

with Cascadia Wildlands v. Adcock, No. 6:22-CV-01344-MTK, 2025 WL 1194191, at *8 (D. Or. Apr. 24, 2025)

(finding it was unreasonable for an agency to knowingly undertake field surveys only after the NEPA review had been

completed unless it was for a landscape-level analysis where subsequent field-level analysis was planned as a part of a

separate NEPA review).

128 See, e.g., Gulf v. Burgum, 775 F. Supp. 3d 455, 483 (D.D.C. 2025) (finding it was unreasonable for agency to refuse

to consider new information resulting from changed conditions resulting from enactment of new legislation affecting

the proposed action). Whether an agency relied on outdated information for its current analysis is different than

analysis of whether an agency violated the law by declining to supplement existing NEPA analysis where new

information has become available. See, e.g., WildEarth Guardians v. Bernhardt, 423 F. Supp. 3d 1083, 1102 (D. Colo.

2019) (upholding agency decision not to supplement notwithstanding new information).

129 See, e.g., O’Reilly v. U.S. Army Corps of Eng’rs, 477 F.3d 225, 234 (5th Cir. 2007) (invalidating a mitigated

FONSI following preparation of an EA that provided “only cursory detail” in describing the extent of the mitigation

measures and how they would reduce the significance of impacts).

130 Previously, CEQ regulations in 40 C.F.R. § 1501.6 set forth conditions under which agencies could issue a mitigated

FONSI. Some agencies adopted their own procedures, which may still be in effect although CEQ regulations have

since been revoked, see Removal of NEPA Implementing Regulations, 90 Fed. Reg. 10610 (Feb. 25, 2025). NEPA

itself is silent on the use of a mitigated FONSI.

131 See, e.g., Mulgrew v. U.S. Dep’t of Transp., 750 F. Supp. 3d 171, 217 (S.D.N.Y. 2024) (upholding agency FONSI

based on application mitigation measures for congestion pricing); Protect Our Cmtys. Found. v. LaCounte, 939 F.3d

1029 (9th Cir. 2019) (addressing mitigation measures intended to protect golden eagles as conditions in an EIS

pertaining to construction and operation of wind turbines).

Congressional Research Service

17

Judicial Review and the National Environmental Policy Act (NEPA)

Did the Agency Consider a Reasonable Set of Alternatives?

NEPA requires agencies to consider alternatives to their proposed actions as part of the

environmental review process.132 Courts and CEQ have referred to this requirement as the “heart”

of the environmental review.133 Agencies need not analyze every possible option; rather, “the

concept of alternatives must be bounded by some notion of feasibility.”134 Thus, agencies must

exercise “common sense” when determining which proposals to include in an EIS; courts will not

find an EIS insufficient “simply because the agency failed to include every alternative device and

thought conceivable by the mind of man.”135 While some specific authorities limit consideration

of alternatives, agencies typically have broad latitude under NEPA to decide what alternatives to

include or exclude in a NEPA analysis. For example, courts have found it reasonable for an

agency to limit alternatives analysis to a preferred option and a no-action option.136 Additionally,

if there was opportunity for public comment in preparation of a NEPA document, courts typically

dismiss claims alleging the agency failed to consider an alternative if that argument was not

raised during the comment period.137

Challenges to an agency’s consideration of alternatives to the proposed action arise in a variety of

ways. Under the APA’s arbitrary-and-capricious standard, agencies are typically judged by

whether they considered a reasonable range of alternatives and explained their reasoning for

accepting or rejecting specific options.138 For example, in a decision that presaged Seven County

Infrastructure Coalition, the U.S. Court of Appeals for the First Circuit refused to find that the

Bureau of Land Management was arbitrary or capricious in its rejection of alternatives outside the

geographic area for a proposed lease, reasoning that activity beyond the planned area could be

considered as a separate project at a later date.139 Similarly, the D.C. Circuit has refused to require

the Federal Energy Regulatory Commission to consider the type of energy used in its alternatives

analysis where a state controlled the selection of energy sources.140 A court may, however, find

132 42 U.S.C. § 4332.

133 See, e.g., CEQ, A CITIZEN’S GUIDE TO THE NEPA 16 (2007), https://ceq.doe.gov/docs/get-

involved/Citizens_Guide_Dec07.pdf [https://perma.cc/UW2Y-2CJG]; Wyoming v. U.S. Dep’t of Agric., 661 F.3d

1209, 1243 (10th Cir. 2011); City of Carmel-By-The-Sea v. U.S. Dep’t of Transp., 123 F.3d 1142, 1155 (9th Cir.

1997); Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190, 194 (D.C. Cir. 1991).

134 Vt. Yankee Nuclear Power Corp. v. Nat. Res. Def. Council, Inc., 435 U.S. 519, 551 (1978).

135 Id.

136 Earth Island Inst. v. U.S. Forest Serv., 87 F.4th 1054, 1065 (9th Cir. 2023) (citing N. Idaho Cmty. Action Network

v. U.S. Dep’t of Transp., 545 F.3d 1147, 1154 (9th Cir. 2008)); see also 16 U.S.C. § 6514 (allowing consideration of

only one alternative for covered hazardous fuels reduction projects); Friends of the Floridas v. U.S. Bureau of Land

Mgmt., 746 F. Supp. 3d 1039, 1175–76 (D.N.M. 2024) (accepting agency’s reasoned rejection of two alternatives

beyond the preferred action/no-action alternatives where the project proposal was “straightforward” and the proposed

alternatives met the stated purpose and need of the proposed action).

137 See, e.g., Earth Island Inst., 87 F.4th at 1063 (noting an exception for commenting on alternatives where an agency

has independent information available, but that was not the case here and plaintiffs made no effort to raise the matter

during the applicable comment period). For additional discussion of limitations based on failure to first raise a concern

directly with the agency, see discussion supra “Exhaustion.”

138 See, e.g., Hualapai Indian Tribe v. Haaland, 755 F. Supp. 3d 1165, 1193 (D. Ariz. 2024) (finding a NEPA violation

for failure of agency to at least consider including reasonable alternatives identified by plaintiff in public comments).

139 Seafreeze Shoreside, Inc. v. U.S. Dept. of the Int., 123 F.4th 1, 22 (1st Cir. 2024), cert. denied sub nom.,

Responsible Offshore Dev. v. Dep’t of the Interior, No. 24-966, 2025 WL 1287066 (U.S. May 5, 2025), and cert.

denied sub nom., Seafreeze Shoreside Inc. v. Dep’t of the Interior, No. 24-971, 2025 WL 1287076 (U.S. May 5, 2025).

140 Citizens Action Coal. of Ind., Inc. v. FERC, 125 F.4th 229, 239 (D.C. Cir. 2025).

Congressional Research Service

18

Judicial Review and the National Environmental Policy Act (NEPA)

that the agency is arbitrary and capricious where it ignores consideration of any alternatives and

fails to explain why options submitted during public comment were not viable.141

Did the Agency Follow Appropriate Procedures for Consultation?

NEPA’s goals encourage informed agency decisionmaking and include certain public disclosure

and participation requirements.142 Since 2023, NEPA has required that an agency publicly

circulate a notice of intent to prepare an EIS.143 Additionally, an agency drafting an EIS must

obtain comments from federal agencies with “jurisdiction by law or special expertise with respect

to any environmental impact involved.”144 These comments—as well as any additional comments

and views of federal, state, and local agencies—must accompany the proposal through any

agency review processes, and are also made available to the President, CEQ, and the public.145

Agencies also engage with relevant tribal authorities and may also receive public comments

during this time.146 Whether or not an agency followed these procedures is generally reviewable

as a matter of law.147

Remedies in NEPA Litigation

A court typically has broad latitude to order a spectrum of remedies when it finds an agency

violated the law with respect to NEPA. In cases considering the validity of a permit or related

authorization, such relief could include declaring an agency’s NEPA or permitting action illegal,

remanding the disputed NEPA analysis to the agency for further consideration, vacating all or part

of a permitting decision, or further enjoining project activity.148

141 See, e.g., Hualapai Indian Tribe v. Haaland, 755 F. Supp. 3d 1165, 1193 (D. Ariz. 2024) (finding tribe’s proposed

alternatives for alternate oil well design options to be not “infeasible, ineffective, or inconsistent” with policy) (citing

Headwaters, Inc. v. Bureau of Land Mgt., Medford Dist., 914 F.2d 1174, 1181 (9th Cir. 1990)).

142 See 42 U.S.C. § 4332; Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 333 (1989) (noting NEPA’s

EIS requirement and other procedures implement “sweeping policy goals by ensuring that agencies will take a ‘hard

look’ at environmental consequences and by guaranteeing broad public dissemination of relevant information”).

143 Fiscal Responsibility Act of 2023, Pub. L. No. 118-5, sec. 321(b), § 107(c), 137 Stat. 10, 41. Until April 2025, CEQ

regulations required agencies to circulate a draft EIS for public comment. See Exec. Order No. 14,154, 90 Fed. Reg.

8353 (Jan. 20, 2025); CEQ Memo, supra note 7; Removal of NEPA Implementing Regulations, 90 Fed. Reg. 10610

(Feb. 25, 2025).

144 42 U.S.C. § 4332(C)(v). Federal, state, tribal, and local cooperating agencies may contribute to the development of

the EIS, potentially including analysis or proposals such as mitigation measures related to the proposed action. Id.

145 Id.

146 Aside from scoping inputs (42 U.S.C. § 4336a(c)), NEPA itself does not explicitly require public comment on a

draft EIS. For decades, CEQ regulations required public input with a public comment period that typically lasted at

least forty-five days between the draft and final EIS across all iterations of their NEPA implementing regulations. See,

e.g., NEPA Implementing Regulations Revisions Phase 2, 89 Fed. Reg. 35442, 35567, 33572 (May 1, 2024); Update to

the Regulations Implementing NEPA Procedural Provisions, 85 Fed. Reg. 43304, 43365, 43372 (July 16, 2020); NEPA

Regulations: Implementation of Procedural Provisions, 43 Fed. Reg. 55978, 55997–98 (Nov. 29, 1978)). Following

recission of the CEQ guidance, some agencies provide for public comment on a draft EIS, while others do not.

147 See., e.g., Idaho Wool Growers Ass’n v. Vilsack, 816 F.3d 1095, 1102–04 (9th Cir. 2019) (describing NEPA’s

“expansive” consultation requirements).

148 For an example of a NEPA claim that included remand, vacatur, and an injunction, see CRS Legal Sidebar

LSB10943, The Willow Project: History and Litigation, by Adam Vann (2023).

Congressional Research Service

19

Judicial Review and the National Environmental Policy Act (NEPA)

Declaratory Relief

Declaratory relief refers to the court’s formal determination of whether there was any violation of

the law.149 Permitting cases that are decided on the merits typically include a determination of

whether an agency violated the law. If no further remedy is ordered by the court, a prevailing

party would receive only declaratory relief. Declaratory relief alone is not a common remedy in

permitting actions, although the APA does expressly allow a claim for declaratory judgments.150

Remand

If a court determines an agency’s NEPA process requires reconsideration or a potential change, it

may order a lower court or agency to revisit a decision in order to cure a violation.151 For

example, remand may be ordered for an agency to consider certain information that was initially

excluded from its analysis, or to explain its reasoning for why it made a certain decision.152 A

court generally remands an issue to an agency where a judge decides an agency is best suited to

exercise its discretion on a NEPA matter and may order additional measures to bring that agency

into compliance with statutory obligations.153

Vacatur

When a court finds that an agency violated the APA, the statute directs the court to “set aside the

agency’s action,” which may result in vacatur.154 In NEPA cases, courts have recognized that

vacatur is the “ordinary” remedy.155 For example, a court may vacate a NEPA review or the

underlying action if an agency neglected to analyze a key impact or if the agency violated notice

and comment requirements or other procedural obligations that cast “serious doubt” over an

agency’s decision.156 Courts may vacate an agency’s environmental document or could potentially

149 See generally 28 U.S.C. § 2201(a) (“any court of the United States . . . may declare the rights and other legal

relations of any interested party seeking such declaration, whether or not further relief is or could be sought.”);

MedImmune, Inc. v. Genentech, Inc., 549 U.S. 118 (2007) (allowing the possibility of relief solely on declaratory

grounds, subject to judicial discretion); see also Kunkel v. Cont’l. Cas. Co., 866 F.2d 1269, 1274 (10th Cir. 1989)

(citing Aetna Life, 300 U.S. 227, 241 (1937) (“The declaration of rights, however, need not include injunctive or

monetary relief.”)).

150 5 U.S.C. § 703; see also 28 U.S.C. § 2201 (allowing for declaratory judgment “whether or not further relief is or

could be sought”).

151 See generally Fla. Power & Light Co. v. Lorion, 470 U.S. 729, 744 (1985) (“If the record before the agency does not

support the agency action, if the agency has not considered all relevant factors, or if the reviewing court simply cannot

evaluate the challenged agency action on the basis of the record before it, the proper course, except in rare

circumstances, is to remand to the agency for additional investigation or explanation.”). Additionally, an appellate court

may remand a matter to a lower court if there is additional action needed in order to proceed with a case.

152 See, e.g., Standing Rock Sioux Tribe v. U.S. Army Corps of Eng’rs, 282 F. Supp. 3d 91, 109 (D.D.C. 2017);

WildEarth Guardians v. Zinke, 368 F. Supp. 3d 41, 75 (D.D.C. 2019).

153 See, e.g., Mont. Wildlife Fed’n. v. Haaland, 127 F.4th 1, 52 (9th Cir. 2025).

154 5 U.S.C. § 706(2); see also Diné Citizens Against Ruining Our Env’t v. Haaland, 59 F.4th 1016, 1048 (10th Cir.

2023) (noting vacatur is a “common” and “appropriate” form of injunctive relief for a NEPA claim); Harmon v.

Thornburgh, 878 F.2d 484, 495 & n.21 (D.C. Cir. 1989) (“When a reviewing court determines that agency regulations

are unlawful, the ordinary result is that the rules are vacated—not that their application to the individual petitioners is

proscribed.”).

155 See Sierra Club v. U.S. Dep’t of Transp., 125 F.4th 1170, 1186 (D.C. Cir. 2025) (citing United Steel v. Mine Safety

& Health Admin., 925 F.3d 1279, 1287 (D.C. Cir. 2019)); Black Warrior Riverkeeper v. U.S. Army Corps of Eng’rs,

781 F.3d 1271, 1290 (11th Cir. 2015) (discussing history of remand without vacatur).

156 See, e.g., Vecinos para el Bienestar de la Comunidad Costera v. FERC, 6 F.4th 1321, 1332 (D.C. Cir. 2021)

(continued...)

Congressional Research Service

20

Judicial Review and the National Environmental Policy Act (NEPA)

vacate the underlying decision that is the subject of the NEPA analysis.157 Courts may also vacate

a rule implementing NEPA promulgated by an agency.158

Notwithstanding the statutory requirement for a court to “set aside” agency action that violates

the APA, there are situations in NEPA cases where a court can remand a NEPA matter to an

agency without vacatur.159 Seven County Infrastructure Coalition clarified that a NEPA deficiency

may not be sufficient to warrant vacatur of an underlying project approval “absent reason to

believe that the agency might disapprove the project if it added more” to the NEPA analysis.160

Courts sometimes order remand without vacatur when finding “harmless error,” or if vacatur

would prove particularly disruptive.161 The D.C. Circuit and some other courts apply two primary

factors in considering vacatur: (1) the seriousness of the order’s deficiencies and (2) any

disruptive consequences of vacatur.162 For example, the D.C. Circuit has declined to vacate an

agency’s environmental review based on a conclusion that the agency was likely to remedy

deficiencies on remand, whereas vacating would have imperiled project funding.163 By contrast, a

court may be more likely to vacate if, for example, an agency’s actions on remand could change a

(declining to vacate FERC’s environmental review on the ground that the agency would likely remedy deficiencies on

remand, while vacating would imperil needed financing to ensure timely project completion); see generally Charles H.

Koch, Jr. & Richard Murphy, Types of Remedies in Review, 3 ADMINISTRATIVE LAW & PRACTICE § 8:31 (3d ed. 2020)

(describing the meaning of “set aside” under the APA) (citing, e.g., Nat. Res. Def. Council v. Wheeler, 955 F.3d 68, 85

(D.C. Cir. 2020); Standing Rock Sioux Tribe v. U.S. Army Corps of Eng’rs, 985 F.3d 1032 (D.C. Cir. 2021); Env’t

Def. Fund v. FERC, 2 F.4th 953, 976 (D.C. Cir. 2021)).

157 5 U.S.C. § 706(2) generally identifies the circumstances for courts to “set aside” an agency action.

158 See, e.g., Mila Sohoni, The Power to Vacate a Rule, 88 GEO. WASH. L. REV. 1121 (2020), https://www.gwlr.org/wpcontent/uploads/2020/09/88-Geo.-Wash.-L.-Rev.-1121.pdf [https://perma.cc/J68H-XYHJ]; Jameson M. Payne &

GianCarlo Canaparo, Is Vacatur Unconstitutional? (July 1, 2025) (draft manuscript),

https://papers.ssrn.com/sol3/papers.cfm?abstract_id=5333468 [https://perma.cc/E6QM-S8AT]. See also Harmon v.

Thornburgh, 878 F.2d 484, 495 & n.21 (D.C. Cir. 1989) (contemplating the possibility of vacating a rule under the

APA at a level that applies nationally).

159 Black Warrior Riverkeeper, 781 F.3d at 1290; STEPHANIE J. TATHAM, ADMIN. CONF. OF THE UNITED STATES, THE

UNUSUAL REMEDY OF REMAND WITHOUT VACATUR 30–36 (2014),

https://www.acus.gov/sites/default/files/documents/Remand%20Without%20Vacatur%20Final%20Report.pdf

[https://perma.cc/F6EL-4KAA] (finding a trend of remanding without vacatur in the D.C. Circuit, in particular with

respect to the Clean Air Act); cf. United States v. Texas, 599 U.S. 670, 686–703 (2023) (Gorsuch, J., concurring)

(discussing the meaning of “set aside” under the APA in the context of vacatur and other options for relief).

160 Seven Cnty. Infrastructure Coal. v. Eagle County, 145 S. Ct. 1497, 1514 (2025).

161 See, e.g., Ground Zero Ctr. for Non-Violent Action v. U.S. Dep’t of Navy, 860 F.3d 1244, 1252 (9th Cir. 2017)

(examining “whether the error materially impeded NEPA’s goals” such as by “precluding informed decisionmaking

and public participation” and not being “fully aware of the environmental consequences of the proposed action);

WildEarth Guardians v. U.S. Bureau of Land Mgmt., 870 F.3d 1222, 1240 (10th Cir. 2017) (remanding to lower court

to consider a narrower form of injunctive relief aside from vacatur); see generally Allied-Signal, Inc. v. Nuclear Reg.

Comm’n, 988 F.2d 146, 150–51 (D.C. Cir. 1993) (establishing factors for vacatur to include the seriousness of an

agency’s deficiencies and the “disruptive consequences” of potential ensuing changes); Diné Citizens Against Ruining

Our Env’t v. Haaland, 59 F.4th 1016, 1025 (10th Cir. 2023) (adopting the Allied-Signal approach).

162 Allied-Signal, 988 F.2d at 150–51. NEPA-specific opinions applying the Allied Signal test include Vecinos para el

Bienestar de la Comunidad Costera v. FERC, 6 F.4th 1321, 1332 (D. C. Cir. 2021), Mont. Wildlife Fed’n v. Haaland,

127 F.4th 1, 52 (9th Cir. 2025) (finding the disruptive consequences of lease vacatur significantly outweighed the

seriousness of the agency’s procedural error and further remanding to the agency for NEPA compliance while

enjoining (prohibiting) surface-disturbing activities “in the interim”), WildEarth Guardians v. U.S. Forest Serv., 137

F.4th 1068, 1092 (10th Cir. 2025) (directing trial court consideration of Allied Signal factors in consideration of the

remedy), Black Warrior Riverkeeper, 781 F.3d at 1290 (“In circumstances like these, where it is not at all clear that the

agency’s error incurably tainted the agency’s decisionmaking process, the remedy of remand without vacatur is surely

appropriate.”), and Ackerman Bros. Farms, LLC v. U.S. Dep’t of Agric., No. 1:17-CV-11779, 2021 WL 6133910, at *7

(E.D. Mich. Dec. 29, 2021) (finding the disruptive consequences of vacatur to outweigh the seriousness of the violation

that otherwise slightly weighed in favor of vacatur).

163 Vecinos para el Bienestar de la Comunidad Costera, 6 F.4th at 1332.

Congressional Research Service

21

Judicial Review and the National Environmental Policy Act (NEPA)

project’s design based on a revised NEPA analysis or if the agency has a history of violating the

APA and NEPA.164

Injunctive Relief

A plaintiff may ask a court to impose injunctive relief in the form of requiring an agency to

undertake or refrain from undertaking a specific activity.165 When a court determines injunctive

relief is appropriate, that relief could be complete, in the sense of entirely halting an agency action

or project, or partial, such as by ordering that a project component proceed (or not) in a specific

manner without affecting the underlying action more broadly than the specific issue of concern.

The Supreme Court has stressed there is no “thumb on the scales” in favor of an injunction as

compared to ordering relief in the form of vacatur.166 A court could, for example, decline to vacate

an action and instead remand to correct a NEPA violation while ordering an interim injunction,

such as temporarily delaying project-level activity until the NEPA matter is cured.167

Sometimes in NEPA-related legal challenges, a plaintiff asks a court to impose a preliminary

injunction early in litigation before the matter can receive a full ruling on the merits or a

temporary restraining order to prevent imminent harm while the court considers whether to enter

a preliminary injunction.168 The Supreme Court has explained that a preliminary injunction is an

“extraordinary remedy” that is “never awarded as of right.”169 To obtain a preliminary injunction,

a plaintiff must show (1) a likelihood of success on the merits, (2) a likelihood of irreparable

harm in the absence of preliminary relief, (3) that the balance of the equities tips in the plaintiff’s

favor, and (4) that an injunction is in the public interest.170 While these four factors are generally

universal in application, courts vary in interpreting how they apply.171 For example, the Ninth

Circuit has explained that one way in which this four-part test could be met is where the plaintiff

has adequately raised “serious questions” on the merits, the balance of hardships sharply tilts in a

plaintiff’s favor, and the other two factors are also satisfied.172

164 See, e.g., Standing Rock Sioux Tribe v. U.S. Army Corps of Eng’rs, 985 F.3d 1032, 1050–53 (D.C. Cir. 2021).

165 See generally Types of Remedies in Review, 3 ADMINISTRATIVE LAW & PRACTICE § 8:31 (3d ed. 2024) (discussing

the scope of injunctive relief) (citing Sampson v. Murray, 415 U.S. 61, 78, 88 (1974)). Note that vacatur is sometimes

characterized as a specific form of injunctive relief. See, e.g., Diné Citizens, 59 F.4th at 1048.

166 Monsanto Co. v. Geertson Seed Farms, 561 U.S. 139, 157 (2010).

167 See, e.g., Mont. Wildlife Fed’n, 127 F.4th at 52 (reversing a lower court’s decision to vacate while temporarily

enjoining “surface-disturbing activity” until the agency complied with NEPA).

168 FED. R. CIV. P. 65. Temporary restraining orders typically expire within fourteen days or less and may be issued

without notice to the opposing party; preliminary injunctions typically last until judgment is rendered on the merits and

may be of longer duration than a temporary restraining order and typically require notice to the opposing party. Id.

169

Winter v. Nat. Res. Def. Council, Inc., 555 U.S. 7, 24 (2009).

170 Id. These four findings are sometimes referred to as the Winter factors. When a plaintiff seeks an injunction against

the government, the balance of equities and public interest factors merge. See Nken v. Holder, 556 U.S. 418, 435

(2009).

171 Compare Sierra Club, Inc. v. Bostick, 539 Fed. Appx. 885, 889 (10th Cir. 2013) (describing various opinions

interpreting Winter’s four factors, including several to support the proposition that failure to prove any one of the four

factors could result in a denial of a request for injunctive relief) with All. for the Wild Rockies v. Cottrell, 632 F.3d

1127, 1134 (9th Cir. 2011) (joining the Second and Seventh Circuits in adopting a “sliding scale” approach for

satisfying the four Winter factors).

172 See, e.g., Earth Island Inst. v. Muldoon, 82 F.4th 624, 640 (9th Cir. 2023) (denying a request for a preliminary

injunction in a NEPA where plaintiff’s failure to raise serious questions on the merits was dispositive and quoting Env’t

Prot. Info. Ctr. v. Carlson, 968 F.3d 985, 989 (9th Cir. 2020) (“Likelihood of success on the merits is a threshold

inquiry and is the most important factor.”)).

Congressional Research Service

22

Judicial Review and the National Environmental Policy Act (NEPA)

A plaintiff seeking a permanent injunction must demonstrate (1) irreparable injury; (2) that

remedies available at law, such as monetary damages, are inadequate to compensate for that

injury; (3) that, considering the balance of hardships between the plaintiff and defendant, a

remedy in equity is warranted; and (4) that the public interest would not be disserved by a

permanent injunction.173 The burden is on a plaintiff to prove why the test is satisfied and the

injunction should be granted; such relief is not presumed.174 For example, the Supreme Court has

said that where a less “drastic” remedy, such as partial or complete vacatur of an underlying

action, is adequate to address a plaintiff’s injury, a court should not order additional extraordinary

relief in the form of an injunction.175 When a court orders an injunction in a NEPA case, it may be

lifted once the underlying violation is cured.176 In this context, even a “permanent” injunction for

a NEPA matter may be time limited, as the goal of any remedied NEPA analysis is to inform the

underlying agency decision on whether and how to proceed with a proposed action.

Considerations for Congress

Congress has numerous options to address judicial review of agency NEPA actions. While NEPA

itself has been amended a handful of times since its inception, Congress typically considers

hundreds of bills each congressional term with provisions addressing NEPA.177 Some of those

bills would affect how courts consider NEPA cases, while others would affect reviewability by

amending requirements in NEPA or individual agencies’ environmental review processes.

Introduced bills have offered changes to how courts would review an agency’s NEPA documents

in the context of a proposed action and to potential remedies a court may order if an agency’s

NEPA review has violated the law. Bills have also included approaches to clarify the scope of

environmental effects an agency considers in its decisionmaking.

Congress has considerable latitude to specify when and under what circumstances courts would

review an agency’s NEPA analysis. Congress could limit judicial review of NEPA claims by

restricting the scope of agency NEPA review or modifying the availability judicial review itself.

For example, some bills introduced in the 118th Congress, such as Senate Amendment 1911 to

H.R. 3935 or House Amendment 272 to H.R. 3935, would have limited consideration to effects

the agency has the authority to directly regulate (as opposed to effects of actions an agency has

the authority to take).178 Additionally, some Members have introduced bills that would affect the

173 Monsanto Co. v. Geertson Seed Farms, 561 U.S. 139, 156–57 (2010) (quoting eBay Inc. v. MercExchange L.L.C.,

547 U.S. 388, 391 (2006) and citing Winter, 555 U.S. at 31–33).

174 Id. at 158 (“It is not enough for a court considering a request for injunctive relief to ask whether there is a good

reason why an injunction should not issue; rather, a court must determine that an injunction should issue under the

traditional four-factor test set out above.”).

175 Id. at 165–66.

176 Where a court finds a NEPA violation and orders an underlying action vacated without additional injunctive relief,

the Supreme Court has clarified that plaintiffs concerned that an agency’s underlying action in response to vacatur

could subsequently violate NEPA would still have the right to bring a new legal challenge based on any ensuring

violations. Monsanto, 561 U.S. at 162. The practical distinction between this outcome and additional equitable relief in

the form of an injunction pending cure of a NEPA violation is not always clear, as both situations could result in a

temporary pause in an agency’s action in order to address the NEPA violation.

177 CONGRESS.GOV, “National Environmental Policy Act,” 1574 results (Aug. 27, 2025) (filtered by “Legislation”,

“1973–2026”), https://perma.cc/BDK7-ZHW9.

178 E.g., S.Amdt. 1911 to H.R. 3935, 118th Cong. (2024); H.Amdt. 272 to H.R. 3935, 118th Cong. (2024); see CRS In

Focus IF12417, Environmental Reviews and the 118th Congress, by Kristen Hite (2023).

Congressional Research Service

23

Judicial Review and the National Environmental Policy Act (NEPA)

availability of judicial review of an agency’s NEPA analysis.179 Congress may also specify a more

or less deferential standard of review of the merits of an agency’s NEPA analysis.

Congress could also affect judicial review of NEPA analysis by amending the scope of which

agency actions are subject to NEPA and what agencies are required to consider when analyzing

environmental effects. Such changes could affect judicial review by expanding or contracting the

universe of actions for which NEPA analysis is required and therefore what a court could review.

Such amendments could also potentially affect NEPA litigation by imposing statutory guardrails

that courts would consider when evaluating whether an agency’s NEPA analysis was lawful.

Congress could consider enacting legislation in response to NEPA’s evolving regulatory

landscape.180 Recission of NEPA regulations and the Seven County opinion have shifted the onus

more squarely onto individual agencies to navigate NEPA implementation. Codifying some or all

of the elements of the NEPA process that were previously found only in CEQ regulations would

limit agency discretion in implementing NEPA and thus would somewhat limit the deference that

courts would otherwise afford to agencies. For example, incorporating specific procedural

requirements into statute would provide federal agencies, stakeholders, and courts with clarity on

the environmental review requirements Congress intends for agencies to apply. Alternatively, if

Congress believes NEPA is best implemented via a less standardized approach, Congress could

consider directing agencies to promulgate or update regulations detailing their NEPA procedures

based on any additional parameters that Congress believes to be warranted.

Author Information

Kristen Hite

Legislative Attorney

Disclaimer

This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan

shared staff to congressional committees and Members of Congress. It operates solely at the behest of and

under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other

than public understanding of information that has been provided by CRS to Members of Congress in

connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not

subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in

its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or

material from a third party, you may need to obtain the permission of the copyright holder if you wish to

copy or otherwise use copyrighted material.

179 E.g., H.R. 471, § 121(c), 119th Cong. (2025); S. 4753, 118th Cong. (2024).

180 In 2025, after CEQ rescinded all government-wide regulations implementing NEPA, a number of agencies

subsequently rescinded all or part of their NEPA regulations. See, e.g., 90 Fed. Reg. 29393, 29393–29715 (July 3,

2025) (containing multiple agencies’ recissions or amendments to NEPA rules).

Congressional Research Service

R48717 · VERSION 1 · NEW

24

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.