Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

Congressional research reportApr 16, 2024

Ask Donna

What actually matters in this document.

Text

Class VI Carbon Sequestration Wells:

Permitting and State Program Primacy

April 16, 2024

Congressional Research Service

https://crsreports.congress.gov

R48033

SUMMARY

Class VI Carbon Sequestration Wells:

Permitting and State Program Primacy

R48033

April 16, 2024

Angela C. Jones

Analyst in Environmental

The U.S. Environmental Protection Agency (EPA) regulates wells used for underground injection

Policy

of carbon dioxide, known as Class VI wells. The Safe Drinking Water Act (SDWA),

administered by EPA, prohibits underground injection of fluids without a permit, including

underground injection of carbon dioxide for geologic sequestration. Under SDWA, EPA is

authorized to delegate primary enforcement authority, or primacy, for underground injection

control (UIC) programs to individual states that meet minimum UIC program requirements. As

the number of carbon capture and sequestration (CCS) projects using deep well injection has increased in the United States in

recent years, Class VI permitting and state program primacy have been topics of interest to Congress.

EPA has established minimum permitting requirements for Class VI injection wells and for state UIC programs.

Requirements are specified for well siting and construction, operation and maintenance, monitoring and testing, reporting and

recordkeeping, site closure, financial responsibility, and post-injection site care. The minimum contents of a permit are

established in regulation, but each Class VI permit is developed and approved based on the site-specific characteristics of the

injection well project and is designed to address potential leakage or endangerment of underground sources of drinking water.

Currently, there are 4 federal EPA-permitted Class VI wells in Illinois and Indiana, and at least 11 state-permitted Class VI

wells in operation in the United States. According to EPA, 130 Class VI permits are currently pending review by the agency.

Additional permits are under review by three states with delegated authority for state Class VI UIC programs.

Class VI permits are required to include information about the project and underground formations, demonstrate site

suitability, and provide financial assurances. Permits must also include six required plans that provide detail on how the

owner or operator will conduct injection well activities throughout the project lifecycle of the project. When reviewing permit

applications, the permitting authority (either EPA or a state) typically conducts five stages of review: completion review,

technical review, draft permit, public comment, and final permit. The technical review, which involves evaluation of

information and plans in the application package, is the longest and most complex step in the permitting process. Once the

permit is in place, the permitting authority is responsible for ensuring the permit requirements continue to be met.

EPA has approved UIC Class VI program primacy for three states: North Dakota, Wyoming, and Louisiana. When granted

primacy for a class of UIC wells, a state administers that UIC program through enforcement of state laws and regulations in

lieu of EPA regulations. EPA retains oversight authority over all state UIC programs under federal law. EPA UIC regulations

set out the specific requirements for state programs in permitting, compliance evaluation, enforcement, and information

sharing. A state must demonstrate that it has the legal authorities and processes in place to administer the Class VI program.

A memorandum of agreement between a state with primacy and EPA, which is submitted along with other required

documents, typically serves as the foundation of a state’s specific responsibilities and commitments in administering the

Class VI program.

Congress has appropriated funding in recent years to EPA for implementation of federal and state Class VI programs. In

2021, the Infrastructure Investment and Jobs Act (IIJA; P.L. 117-58) provided $50 million in supplemental appropriations to

EPA for grants to states that have or are working toward Class VI primacy. The IIJA provided an additional $25 million to

EPA for Class VI program administration. As Congress continues to debate policy on Class VI well permitting and state

primacy, several issues may arise regarding Class VI wells, including EPA appropriations, legislation, and EPA oversight.

Specific policy issues may include

•

•

•

•

the levels of EPA resources needed to process and oversee Class VI permits and state primacy applications;

state resources and capacity to administer UIC Class VI programs;

whether EPA’s Class VI regulations should be amended; and

whether Congress should address stakeholder concerns about public participation in permit and primacy

processes, and concerns about the potential environmental and community impacts of carbon sequestration

through Class VI wells.

Congressional Research Service

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

Contents

Introduction ..................................................................................................................................... 1

Class VI Injection Wells .................................................................................................................. 1

Class VI Well Permits...................................................................................................................... 2

Class VI Permit Phases ............................................................................................................. 3

Elements of a Class VI Permit .................................................................................................. 3

General Project Information and Permit Conditions........................................................... 4

Required Plans .................................................................................................................... 4

Optional Injection Depth Waiver ........................................................................................ 5

Class VI Permitting Process ...................................................................................................... 5

Permit Compliance and Enforcement ....................................................................................... 6

Public Participation ................................................................................................................... 6

Class VI Well Permits Issued .................................................................................................... 7

State UIC Class VI Program Primacy ............................................................................................. 8

Current States with UIC Class VI Program Primacy ................................................................ 9

UIC Class VI Program Primacy Requirements ....................................................................... 10

Primacy Application Process .................................................................................................... 11

Enforcement and EPA Oversight ............................................................................................. 12

UIC Grants for States .............................................................................................................. 12

State Public Participation and Environmental Justice ............................................................. 13

Issues for Congress ........................................................................................................................ 13

EPA Funding and Resources ................................................................................................... 13

Potential Amendments to the 2010 Class VI Rule .................................................................. 14

Environmental Justice Concerns ............................................................................................. 14

Figures

Figure 1. Class VI Permits Issued and Under Review by EPA ....................................................... 8

Figure 2. States with UIC Class VI Program Primacy .................................................................. 10

Contacts

Author Information........................................................................................................................ 15

Congressional Research Service

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

Introduction

Several industries in the United States are expanding the use of injecting captured carbon dioxide

(CO2) through deep underground wells into geologic formations in order to reduce CO2 emissions

reaching the atmosphere. As one potential option for mitigating the potential impacts of climate

change, this carbon capture and sequestration (CCS) process could reduce the amount of CO2—

an important greenhouse gas—from power plants and other large industrial facilities. The U.S.

Environmental Protection Agency (EPA) issues permits for CO2 injection wells, known as Class

VI wells, used for injection and geologic sequestration of CO2. In some cases, EPA delegates

authority to states, known as program primacy, to administer underground injection programs and

issue Class VI permits.

In recent years, Class VI permitting and state program delegation has been a topic of interest to

Congress. Congress provided targeted appropriations for Class VI well activities in the

Consolidated Appropriations Act, 2021 (P.L. 116-260). The act also directed EPA to provide

recommendations to “improve Class VI permitting procedures.”1

In 2022, EPA responded with a report to Congress on Class VI permitting.2 Some Members have

continued to express interest in Class VI well permitting and primacy issues, including the current

status of applications, EPA review processes, public participation in applications, and options for

increasing the numbers of approved well permits and state delegation applications.

This report discusses the statutory and regulatory framework for permitting Class VI wells;

describes Class VI permit application requirements and the permit review process; describes state

primacy requirements and the primacy review process; and highlights selected policy issues for

Congress.

Other environmental regulations and permit requirements may apply to projects injecting CO2,

depending on the scope and purpose of the project, such as requirements under the Clean Air Act

and Clean Water Act administered by EPA. EPA also regulates injection of CO2 for crude oil

production (in a process known as enhanced oil recovery) through Class II UIC injection wells.3

These regulations and permits are beyond the scope of this report. For more information on CO2

injection and sequestration, including the federal statutory and regulatory framework, and general

policy issues, see CRS Report R46192, Injection and Geologic Sequestration of Carbon Dioxide:

Federal Role and Issues for Congress, by Angela C. Jones.

Class VI Injection Wells

As part of the CCS process, CO2 is first captured from a stationary source, such as a coal-fired

power plant or chemical production facility. The CO2 is then injected into subsurface geologic

formations for geologic sequestration, the long-term containment of a fluid (including a gas,

liquid, or supercritical CO2 stream) in subsurface geologic formations.4

1 P.L. 116-260, Division G, Title II, Environmental Protection Agency.

2 U.S. Environmental Protection Agency (EPA), EPA Report to Congress: Class VI Permitting, October 2022,

https://www.epa.gov/system/files/documents/2022-11/

EPA%20Class%20VI%20Permitting%20Report%20to%20Congress.pdf (hereinafter, EPA Report to Congress).

3 Through multiple injection cycles into the underground formation, injection of CO for enhanced oil recovery (EOR)

2

results in incidental underground storage of some of the injected CO2.

4 CO for injection is initially captured as a gas and then is compressed into a supercritical fluid, a relatively dense fluid

2

(continued...)

Congressional Research Service

1

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

The CO2 is injected through Class VI wells, typically injecting fluid a half a mile or more below

the earth’s surface. Geologic formations used for injecting CO2 include, for example, large deep

saline reservoirs (underground basins containing salty fluids) and oil and gas reservoirs no longer

in production.

The Safe Drinking Water Act (SDWA), administered by EPA, provides authorities for regulating

the underground injection of fluids.5 SDWA prohibits any underground injection activity, except

when authorized by a permit or rule, to prevent endangerment of underground sources of drinking

water (USDWs).6 As part of EPA’s Underground Injection Control (UIC) program, the agency has

promulgated regulations and established minimum federal requirements for injection wells,

including for Class VI wells for the purpose of long-term geologic sequestration.7

SDWA also authorizes EPA to delegate primary enforcement authority, called primacy, of UIC

programs to states (see “State UIC Class VI Program Primacy” below). As directed by SDWA,

EPA has established minimum requirements for state UIC programs and permitting for injection

wells.8 EPA has delegated primacy for the state UIC Class VI programs in North Dakota,

Wyoming, and Louisiana.

Class VI Well Permits

Federal requirements for injection well permits, including Class VI well permits, are codified in

UIC regulations at 40 C.F.R. §§144-146. Minimum requirements are specified for well siting and

construction, operation and maintenance, monitoring and testing, reporting and recordkeeping,

site closure, financial responsibility, and post-injection site care. The well owner or operator must

seek a permit for each individual Class VI well.9

Each UIC Class VI permit is specific to the characteristics of the individual injection site and

operation. Site-specific permitting is necessary to address the risks of CO2 injection at high

pressures, such as leaks into the atmosphere, underground leaks, or movement of formation water

into USDWs that could affect drinking water quality.

Class VI permit requirements and standards are generally more stringent than requirements for

other well classes. EPA based the regulation and permitting requirements of Class VI wells on

several risk factors specific to this type of injection activity. These risk factors include the large

volumes of CO2 expected to be injected through wells, the mobility of CO2 within subsurface

with both gas-like and liquid-like properties. An emerging technology that captures CO2 directly from the

atmosphere—called direct air capture—could also provide a source of CO2 for geologic sequestration. For more

information on carbon capture and direct air capture, see CRS In Focus IF11501, Carbon Capture Versus Direct Air

Capture, by Ashley J. Lawson.

5 SDWA Part C, “Protection of Underground Sources of Drinking Water” (42 U.S.C. §§300h-300h-9).

6 SDWA §1421; 42 U.S.C. §300h. EPA defines underground source of drinking water as an “aquifer or its portion

which supplies any public water system or which contains a sufficient quantity of ground water to supply a public

water system; and currently supplies drinking water for human consumption; or contains fewer than 10,000 mg/l total

dissolved solids; and which is not an exempted aquifer” (40 C.F.R. §146.3).

7 EPA has established six “classes” of underground injection wells, based on the types of fluids injected; 40 C.F.R.

§§144-146; EPA, “Federal Requirements Under the Underground Injection Control (UIC) Program for Carbon Dioxide

(CO2) Geologic Sequestration Wells; Final Rule,” 75 Federal Register 77230-77303, December 10, 2010, p. 77245.

(Hereinafter, “EPA, Federal Requirements”).

8 40 C.F.R. §§144-146.

9 SDWA regulations for some other UIC well classes allow wells to be permitted in groups, known as “area permits.”

Congressional Research Service

2

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

formations, and the corrosive properties of CO2 in the presence of water that can affect well

materials.10

To assist states and owners/operators with the permitting process, EPA has issued 11 technical

guidance documents on Class VI wells.11 These documents are not legally enforceable, but they

provide additional information on site characterization, area of review, construction, reporting and

recordkeeping, site closure, financial responsibility, and other permit elements.

Class VI Permit Phases

During the Class VI well permit application process, the owner or operator works with the

permitting authority, either EPA or a state that has primacy for the Class VI UIC program. EPA

identifies four phases of permitting for a Class VI project:12

1. Pre-construction. The permitting authority reviews geologic, underground

formation, hydrogeologic, engineering, and financial information about a

proposed Class VI project to confirm site suitability. The permitting authority

then develops a draft permit.

2. Pre-operation. Following well testing and submission of additional site

information, the permitting authority confirms the adequacy of well construction

and makes a determination regarding authorization to inject CO2.

3. Injection. After granting an authorization to inject, the permitting authority

confirms that the well and the project are operating in compliance with the permit

and that USDWs are not endangered.

4. Post-injection. After injection is complete, the well is plugged, and the site is

closed, the permitting authority verifies that the project continues to be protective

of USDWs and that the injection and monitoring wells at the site will not

endanger USDWs after site closure.

Class VI permits extend for the operating life of the facility and a 50-year post-injection site care

period.13 The duration of a Class VI well injection project varies depending on the amount of CO2

captured for storage and the capacity of the underground formation, but current projects estimate

a 10- to 15-year timeframe for injection. Permitting authorities are required to review Class VI

permits at least once every five years.14

Elements of a Class VI Permit

For EPA-issued Class VI permits, 40 C.F.R. Parts 144 and 146 set out specific requirements for

the permit application and approval process. While the minimum contents of a permit are

established in federal regulation, the site-specific permit conditions, technical standards, and other

requirements in each permit are based on the permitting authority’s evaluation of the potential

risks to USDWs and the necessary conditions and standards required for the project to prevent

and manage potential endangerment of USDWs. Permits are updated based on site or project

10 EPA, “Federal Requirements,” p. 77234.

11 “Class VI Guidance Documents,” EPA, https://www.epa.gov/uic/class-vi-guidance-documents.

12 EPA Report to Congress. For more details on permitting requirements and guidelines, see “Class VI Guidance

Documents.”

13 40 C.F.R. §144.36.

14 Ibid.

Congressional Research Service

3

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

circumstances. States must have equivalent requirements if administering their own UIC Class VI

programs and issuing Class VI permits (see “State UIC Class VI Program Primacy”).

General Project Information and Permit Conditions

Class VI permit applicants are required to include general project information and set out the

permit conditions applicable to all UIC permits, as well as Class VI-specific permit criteria and

standards.15 Injection project information includes

•

•

•

•

•

basic facility and siting information;

detailed information on the CO2 stream;

geochemical data on subsurface formations, including relevant USDWs;

detailed information on the geologic structure and hydrogeologic properties of

the storage site and overlaying formation; and

the history of seismic activity at the site.16

Class VI permits applications are also required to

•

•

•

•

identify the area of review for the project that accounts for the physical and

chemical properties of CO2;

demonstrate that the injection site is in a suitable geologic formation for geologic

sequestration;

document that the materials used for well construction are adequate to prevent

movement of fluids into or between USDWs and are suitable for long-term

contact with CO2 for the life of the project;17 and

include the owner’s or operator’s financial assurances in the form of financial

responsibility instruments to cover corrective action, injection, well plugging,

post-injection site care, and any emergency and remedial response that meets the

regulatory requirements of those actions.18

For more information on Class VI well standards and permitting requirements, see CRS Report

R46192, Injection and Geologic Sequestration of Carbon Dioxide: Federal Role and Issues for

Congress, Appendix C.

Required Plans

Class VI regulations require that permit application packages include several plans that provide

detailed information on how the owner or operator will conduct injection well activities from

construction through closure.19 These plans are finalized and approved by the permitting authority

as part of the permitting process. The following plans are required in a permit application:

•

•

•

Testing and Monitoring Plan

Injection Well Plugging Plan

Site Closure Plan and Post-Injection Site Care Plan

15 40 C.F.R. §144.51; 40 C.F.R. §§144.82-146.95.

16 40 C.F.R. §144.82.

17 40 C.F.R. §144.83; §144.84; §144.86.

18 40 C.F.R. §144.85.

19 40 C.F.R. §144.82.

Congressional Research Service

4

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

•

•

•

Corrective Action Plan

Emergency and Remedial Response Plan

Quality Assurance Surveillance Plan

Optional Injection Depth Waiver

By regulation, Class VI wells are defined as wells that are used for the geologic sequestration of

CO2 beneath the lowermost formation containing a USDW (emphasis added).20 In some cases, the

USDWs may be deep in the formation. In these cases, during the permitting process, well owners

or operators may seek a waiver to allow injection into non-USDWs above or between USDWs.

Class VI regulations include specific requirements for approval of a depth waiver, such as the

information to be provided to the state or EPA, consultations with state Public Water System

Directors and tribes, public notice, and approval or concurrence by the EPA Regional

Administrator.21

Class VI Permitting Process

Class VI permit regulations require that an owner or operator submitting a permit application

package meet specific requirements and follow certain processes. Once an applicant submits a

permit application to EPA, that application is reviewed by staff in the EPA regional office

covering that state. While EPA has stated that its objective is to complete the permit review

process within two years, review times may vary due to differences in the initial completeness of

the application, timing of revisions by the applicant, the public comment process, agency review

capacity, and other factors.22

EPA’s Class VI permit application review process includes five steps, listed below.23

1. Completeness Review—determination by EPA that the permit application

package meets requirements for completeness and necessary information.

2. Technical Review—detailed review of the application by EPA to ensure the

project will not endanger USDWs.

3. Draft Permit—preparation of the draft permit by EPA specifying conditions of

well construction and operation.

4. Public Comment—opportunity for the public to review and comment on the

draft permit through written comments to EPA or requests for a hearing

conducted by EPA.

5. Final Permit—preparation of final permit and authorization to construct or

convert the injection well, construct monitoring wells, and perform required

testing.

Once construction and testing are completed and approved, the final phase includes an

authorization from EPA to inject. At this point, the operator is permitted to begin injecting CO2.

20 40 C.F.R. §144.6(f).

21 40 C.F.R. §144.95. State programs with delegated authority may choose whether to offer injection waivers to owners

or operators as part of a UIC Class VI program. 40 C.F.R. §146.95(d) requires that the relevant EPA regional

administrator concur on approval of an injection depth waiver for a project.

22 EPA Report to Congress.

23 EPA Report to Congress. For more details on permitting requirements and guidelines, see herein “Class VI Guidance

Documents.”

Congressional Research Service

5

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

The technical review is the longest and most complex step in the permitting process, with an

estimated time frame of 18 months.24 During this step, EPA reviews the detailed siting,

construction, operation, injection, and closure information submitted, as well as each of the draft

plans required in the application package.

During the review and drafting steps, EPA typically works with the applicant to seek clarification

on permit elements and identify additional information required. The permitting authority may

issue a formal Request for Additional Information (RAI). Applicants are expected to respond to

an RAI within 30 days or provide an alternative timeline for a response.

Permit Compliance and Enforcement

Once the permit is in place, the permitting authority is responsible for ensuring that the owner or

operator continues to meet the permit conditions and requirements.25 The permitting authority

reviews testing, monitoring, and verification data reported by the owner and operator to evaluate

compliance and enforce permit conditions in place to prevent endangerment of USDWs.

Potential violations include, among others, a loss of well mechanical integrity; failure to follow

monitoring, testing, or reporting requirements; or movement of CO2 or formation fluids out of the

designated injection zone. The permitting authority may also conduct on-site inspections to

observe well testing and operation, review records, or evaluate procedures being taken to bring

the facility into compliance, among other purposes.

Public Participation

Class VI permit application review processes are subject to the general public participation

requirements under SDWA.26 These regulations apply to EPA issuance of UIC permits. They

outline minimum requirements for public information, public notice, and public consultation.

Public participation activities may include providing notice in the media, holding hearings,

responding to public comments, and involving stakeholders.

While the above general public participation requirements exist, EPA has not issued specific

regulatory requirements for public participation for the Class VI permit application process. EPA

guidance on public participation in Class VI permitting, issued in 2011, anticipated “high levels”

of public interest in geologic sequestration.27 The guidance encouraged UIC programs and owners

and operators to provide information on Class VI permits early in the process and to involve a

broad range of stakeholders.28

In its 2022 report to Congress on Class VI well permitting, EPA identified several stakeholder

concerns regarding environmental justice (EJ) in the permitting process, including concerns about

project siting and public involvement. EPA stated that the agency intends to expand the amount of

24 “Class VI—Wells Used for Geologic Sequestration of Carbon Dioxide,” EPA, https://www.epa.gov/uic/class-vi-

wells-used-geologic-sequestration-carbon-dioxide.

25 The permitting authority is either EPA or a state granted UIC Class VI program authority by EPA.

26 40 C.F.R. Part 25. 40 C.F.R. §§124.10-124.11 requires the permitting authority to provide public notice of the permit

application, hold a public hearing if it is determined to be of significant public interest, and consider public comments

in making permit decisions.

27 EPA, Geologic Sequestration of Carbon Dioxide – UIC Quick Reference Guide: Additional Considerations for UIC

Program Directors on the Public Participation Requirements for Class VI Injection Wells, EPA 816-R-11-001, June

2011, https://www.epa.gov/sites/default/files/2015-07/documents/uic-quick-reference-guide_public-participation_final508.pdf.

28 EPA, Geologic Sequestration of Carbon Dioxide – Quick Reference Guide.

Congressional Research Service

6

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

information available to the public about Class VI well permit applications and “explore

additional ways in which EPA Class VI permitting can consider the specific needs of any EJ

communities located near a proposed Class VI project.”29

In August 2023, EPA issued a memorandum and accompanying guidance that outlined

expectations for how agency staff should consider EJ in permitting and primacy evaluations.30

The guidance notes that, while Class VI wells are regulated under an “existing, rigorous”

permitting framework, stakeholders have raised concerns about the potential impacts of Class VI

well projects on “overburdened communities.”31 Specifically, the guidance includes information

for EPA and state UIC programs on identifying communities with potential EJ concerns,

enhancing public involvement during the permitting applications processes, conducting EJ

assessments of potential well projects, and enhancing transparency in the permitting process.32

Class VI Well Permits Issued

As of March 2024, EPA has issued a total of eight Class VI permits for injection of CO2. Four

EPA-permitted Class VI wells are currently in operation.

•

•

•

In 2015, EPA issued four Class VI permits associated with the FutureGen project

in Illinois, but the project was cancelled before well construction.

In 2017, EPA issued final permits for two wells injecting CO2 into a saline aquifer

at the Archer Daniels Midland (ADM) ethanol plant in Decatur, Illinois.33

In 2024, EPA issued permits for two wells at Wabash Carbon Services in Indiana,

which plan to store captured CO2 from offsite fertilizer production.34

Two of the three states with Class VI permitting authority have issued permits:

•

North Dakota has issued eight Class VI permits for three facilities for injection of

CO2.35

• The Red Trail Energy (RTE) storage facility was permitted in 2022. RTE

injects CO2 captured from ethanol production facilities.

• The Dakota Gasification Company (DSG) storage facility was permitted

in 2023. DSG injects CO2 captured from a natural gas production facility.

• The Blue Flint storage facility was permitted in 2023. Blue Flint injects

CO2 captured from ethanol production facilities.

29 EPA Report to Congress.

30 EPA, Environmental Justice Guidance for UIC Class VI Permitting and Primacy, August 17, 2023,

https://www.epa.gov/system/files/documents/2023-08/

Memo%20and%20EJ%20Guidance%20for%20UIC%20Class%20VI_August%202023.pdf (hereinafter, EPA,

Environmental Justice Guidance).

31 Ibid.

32 Ibid.

33 EPA, “Table of EPA’s Draft and Final Class VI Well Permits,” https://www.epa.gov/uic/table-epas-draft-and-finalclass-vi-well-permits, accessed April 1, 2024.

34 EPA, “EPA Approves Permits to Begin Construction of Wabash Carbon Services Underground Injection Wells in

Indiana’s Vermillion and Vigo Counties,” news release, January 24, 2024, https://www.epa.gov/newsreleases/epaapproves-permits-begin-construction-wabash-carbon-services-underground-injection.

35 North Dakota Department of Mineral Resources, “Class VI – Geologic Sequestration Wells,”

https://www.dmr.nd.gov/dmr/oilgas/ClassVI, accessed December 7, 2023.

Congressional Research Service

7

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

•

•

In 2023, Wyoming issued three Class VI permits to the Frontier Carbon Solutions

project for a storage hub that would store CO2 from various capture projects.36

Louisiana has not yet issued Class VI permits.

According to EPA, as of April 2024, 130 Class VI permit applications are pending for 44 projects

in 12 states and 1 tribal reservation.37 All of these permits being reviewed by EPA are in the preconstruction phase as of April 1, 2024. See Figure 1 for details on permit applications and Class

VI well locations.

Figure 1. Class VI Permits Issued and Under Review by EPA

Source: CRS graphic based on U.S. Environmental Protection Agency, “Current Class VI Projects Under Review

at EPA,” accessed on April 1, 2024, https://www.epa.gov/uic/current-class-vi-projects-under-review-epa.

Note: Figure includes permits under review by EPA as of April 1, 2024. Figure does not include permits that

may be under review by states with UIC Class VI program primacy, as these are managed by individual states

rather than EPA.

State UIC Class VI Program Primacy38

SDWA authorizes EPA to delegate primary enforcement authority for UIC programs, known

as primacy, to individual states.39 EPA grants a state primacy through a federal rulemaking

process for one or more classes of wells. To be delegated Class VI program primacy, states must

adopt laws and regulations at least as stringent as EPA regulations and must meet other statutory

36 Wyoming Department of Environmental Quality, “Class VI,” https://deq.wyoming.gov/water-quality/groundwater/

uic/class-vi/, accessed January 11, 2024.

37 EPA, “Current Class VI Projects Under Review at EPA,” https://www.epa.gov/uic/current-class-vi-projects-underreview-epa, accessed April 1, 2024.

38 This report focuses on requirements for new UIC Class VI programs. Applications for revisions of existing UIC

programs may require the state to submit less information, as outlined in “Class VI Guidance Documents.”

39 SDWA §1421; 42 U.S.C. §300h.

Congressional Research Service

8

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

and regulatory requirements. UIC regulations allow states to apply for primacy either for the

Class VI program only or for multiple UIC well programs at once.

If granted primacy for a UIC program, such as a Class VI well program, a state administers the

program through enforcement of state laws and regulations in lieu of EPA regulations. The state

administers the UIC program and is responsible for day-to-day program responsibilities,

including issuing permits and enforcing permit requirements and standards. Under SDWA, EPA

retains oversight of states with primacy to ensure that the state programs comply with federal

regulatory requirements.

Current States with UIC Class VI Program Primacy

EPA has delegated primacy for Class VI wells to three states: North Dakota (2018), Wyoming

(2020), and Louisiana (2023).40 Additional states are applying for Class VI primacy. As of April

1, 2024, West Virginia and Arizona are in a pre-application phase for all six well classes,

including Class VI, and Texas is in a pre-application phase for the Class VI program.41 See

Figure 2 for a map of states that have been granted UIC Class VI program primacy or are in the

application process. As Class VI wells require specific types of geologic conditions and

underground formations to receive and store injected CO2, some states may not have appropriate

sites for Class VI wells. These states would not apply for Class VI program primacy.

40 North Dakota, Wyoming, and Louisiana have primacy for all six UIC well classes. EPA implements Class VI

programs in all other states and territories.

41 EPA, “Primary Enforcement Authority for the Underground Injection Control Program,” https://www.epa.gov/uic/

primary-enforcement-authority-underground-injection-control-program-0, accessed January 20, 2024.

Congressional Research Service

9

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

Figure 2. States with UIC Class VI Program Primacy

Source: CRS graphic based on U.S. Environmental Protection Agency, “Primary Enforcement Authority for the

Underground Injection Control Program,” https://www.epa.gov/uic/primary-enforcement-authorityunderground-injection-control-program-0.

UIC Class VI Program Primacy Requirements

As directed in Section 1421 of SDWA, EPA has established minimum requirements for state UIC

programs. If a state seeks primacy for its UIC program, Section 1422 of SDWA requires the state

to submit an application “showing satisfactorily” to EPA that, after reasonable notice and public

hearings, the state will implement a program that meets the minimum requirements of Section

1421.

EPA UIC regulations promulgated at 40 C.F.R. Part 145 set out the specific requirements for state

programs for permitting, compliance evaluation, enforcement, and information sharing. The

regulations set out the process and requirements for state applications to EPA for primacy, as well

as the procedures EPA follows in evaluating primacy applications.

Class VI regulations require the state to demonstrate that it has the authorities and processes in

place to administer the Class VI program, including

•

•

•

•

legal authority to implement all permit requirements;

necessary procedures for the state’s compliance evaluation program;

necessary administrative, civil, and criminal enforcement penalty remedies;

state Class VI UIC regulations for permitting, inspection, operation, monitoring

and recordkeeping, and other requirements at least as stringent as federal Class

VI regulations; and

Congressional Research Service

10

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

•

statewide jurisdiction over underground injection projects.42

States seeking primacy are required to submit a detailed description of their UIC program that

includes information on

•

•

•

•

•

the structure and processes of the program;

staffing and expertise;

schedule and priorities for issuing Class VI permits;

expected number of permits to be issued; and

the state’s compliance tracking and enforcement program.43

A state seeking primacy must submit copies of its UIC statutes and regulations to EPA and must

demonstrate that these laws and regulations are at least as stringent as federal UIC requirements.

Other documents required to be included in a primacy application package include

•

•

•

•

a letter from the governor of the state requesting program approval;

a state attorney general statement indicating that the state has adequate legal

authority to carry out the UIC program;

a memorandum of agreement (MOA) between the state and the EPA Regional

Administrator that includes provisions on program administration,

implementation, and enforcement; and

documentation of the state’s public participation activities prior to submission of

the program application.44

The MOA typically serves as the foundation of the state’s specific responsibilities and

commitments in administering the UIC program.

Primacy Application Process

Once a state submits a Class VI primacy application, EPA assesses the completeness of the

application and evaluates the contents of the application against federal regulatory requirements.

Specifically, EPA examines the stringency and equivalency of the state’s regulations in protection

of USDWs. According to EPA, the agency maintains a goal of completing the review in 30

days.45

In reviewing applications, EPA seeks to ensure that the state’s UIC Class VI regulations are at

least as strict as federal regulations and that they contain the same necessary requirements for

well permitting, construction, operation, recordkeeping, site closure, and other requirements

established in federal Class VI regulations. The typical UIC primacy application process involves

a series of communications and discussions among state agencies and the relevant EPA regional

office during review and evaluation. During the review process, EPA may request additional

information or clarification from the state.

42 40 C.F.R. §145.

43 Ibid.

44 Ibid.

45 EPA, Geologic Sequestration of Carbon Dioxide: Underground Injection Control (UIC) Program Directors Class VI

Primacy Manual for State Directors, April 2014, https://www.epa.gov/sites/default/files/2015-07/documents/

epa816b14003.pdf. EPA standard operating procedures for Class VI primacy application review include a goal of a 30day time frame for determining the completeness of the application, but this is not a statutory deadline.

Congressional Research Service

11

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

Class VI regulations require that, once EPA determines that a new Class VI primacy application is

complete, the agency must hold a public hearing announced through notice in the Federal

Register and provide information on the availability of the application to the public for review

and comment.46

Once the application is approved, EPA promulgates a rulemaking finalizing the decision to award

primacy to the state for the UIC program. The regulations require that EPA must approve,

disapprove, or approve in part the UIC program through a rule published in the Federal

Register.47 The three approved state Class VI primacy rules are available in the Federal Register

and codified in 40 C.F.R. Part 147.48

For the three state primacy applications that have been approved to date, the timing from EPA

receiving a complete primacy application package to approval has varied. For the first state to

apply, North Dakota, the review process took four years. EPA approved Wyoming’s primacy in

eight months.

For Louisiana, the most recent state to be granted primacy, EPA finalized approval more than two

years after a completed submission. In May 2023, EPA published a proposed rule indicating the

agency’s intent to approve Louisiana’s Class VI program revision package and soliciting public

comment. In August 2023, Louisiana amended its application to include a new state law related to

long-term liability for injection well sites.49 EPA signed final approval for Louisiana’s Class VI

primacy on December 28, 2023, effective on February 5, 2024.50

Enforcement and EPA Oversight

Once granted primacy, the state is responsible for the day-to-day administration of the program,

such as issuing permits, monitoring compliance with state regulations, and leading enforcement

actions in the event of violations. Under SDWA, however, EPA retains oversight and enforcement

authority over all delegated UIC programs. The MOA between the state and EPA typically

includes provisions specifying that EPA will conduct periodic performance evaluations of the

state program to ensure that minimum federal requirements are being met.

UIC Grants for States

In recent years, Congress has appropriated funding for EPA to provide grants to states for

implementation of new and existing UIC programs, including Class VI programs. For FY2023,

EPA’s enacted operating plan included $13.16 million for categorical grants for all classes of UIC

wells, some of which is available for state Class VI well programs. In 2021, the Infrastructure

Investment and Jobs Act (IIJA; P.L. 117-58) directed EPA to establish a specific UIC Class VI

46 40 C.F.R. §145.31.

47 Ibid.

48 EPA, “State of North Dakota Underground Injection Control Program; Class VI Primacy Approval,” 83 Federal

Register 17758-17761, April 24, 2018, and 40 C.F.R. §147.1751 (North Dakota); EPA, “Wyoming Underground

Injection Control Program; Class VI Primacy,” 85 Federal Register 64053-64056, October 2020, and 40 C.F.R.

§147.2550 (Wyoming); EPA, “State of Louisiana Underground Injection Control Program; Class VI Primacy,” 89

Federal Register 703-712, January 5, 2024 (Louisiana), rule signed on December 28, 2023.

49 EPA, “State of Louisiana Underground Injection Control Program; Class VI Primacy,” 89 Federal Register 703-712,

January 5, 2024 (Louisiana), rule signed on December 28, 2023.

50 EPA, “Primary Enforcement Authority for Underground Injection Control Program,” https://www.epa.gov/uic/

primary-enforcement-authority-underground-injection-control-program-0.

Congressional Research Service

12

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

grant program for states. Division J of the act provided $50 million in supplemental

appropriations to EPA for grants to states that have or are working toward Class VI primacy.

States may use these funds for Class VI primacy applications, program revisions, or existing

Class VI program implementation activities.51 Twenty-three states and two tribes submitted letters

of intent to participate in the grant program. EPA has allocated $1.93 million to each of these

states and tribes, for a total of $48.25 million of the $50 million in grant funding available.52

State Public Participation and Environmental Justice

In December 2022, EPA sent a letter to all state governors regarding environmental justice

considerations in Class VI well permitting and state primacy.53 The letter encouraged states to

include approaches for considering the impact of Class VI well projects on vulnerable

communities in their primacy applications and in implementation of their state programs once

primacy is granted. EPA’s August 2023 publication Environmental Justice Guidance for UIC

Class VI Well Permitting and Primacy provides further guidance for how states can support these

objectives.

Issues for Congress

In recent Congresses, some Members have demonstrated interest in Class VI permitting and

primacy by introducing legislation specific to Class VI wells, providing targeted appropriations to

EPA, and discussing Class VI well issues in hearings.54 For example, in the 117th Congress, the

SECURE Act (H.R. 9230) would have amended IIJA appropriations to increase EPA

appropriations for Class VI grants from $50 million to $100 million. In the 118th Congress, the

Primacy Certainty Act of 2023 (H.R. 3568/S. 1718) would amend SDWA to require EPA to issue

a determination on a state’s Class VI primacy application within 90 days.

As Congress continues debate on Class VI well permitting and state primacy, Members may

consider several policy issues related to EPA appropriations, legislation, and oversight. While the

issues outlined below focus on policies specifically related to Class VI wells, policy support for

CCS project deployment, such as research funding and federal tax credits, are part of broader

climate change policy discussions in Congress. For more information on policy considerations for

Class VI wells and CCS as a climate change mitigation option, see CRS Report R44902, Carbon

Capture and Sequestration (CCS) in the United States.

EPA Funding and Resources

As discussed in this report, Congress has supported state UIC well programs through regular

annual appropriations to EPA for grants to states to be used for UIC program implementation.

51 EPA, Underground Injection Control (UIC) Class VI Wells Grant Program: Grant Implementation Document,

November 2023, https://www.epa.gov/system/files/documents/2023-11/uic-class-vi-primacy-grant-implementationdocument.pdf (Hereinafter, EPA, UIC Grant Implementation).

52 Ibid.

53 Letter from Michael S. Regan, EPA Administrator, to Governors, December 9, 2022, https://www.epa.gov/system/

files/documents/2022-12/AD.Regan_.GOVS_.Sig_.Class%20VI.12-9-22.pdf.

54 CRS searched Congress.gov with the term “Class VI” to identify relevant legislation in the 116 th-118th Congresses.

In November 2023, the Senate Committee on Energy and Natural Resources held a hearing on general CCS topics that

included discussions of Class VI permitting and primacy.

Congressional Research Service

13

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

Congress has also directed additional funding support for Class VI permitting and primacy

activities, providing $25 million for EPA Class VI program administration in the IIJA.55

EPA is currently reviewing at least 130 Class VI permit applications. Congress may consider how

the level of EPA UIC Class VI program resources aligns with some Members’ interest in

increasing the number and facilitating the prompt processing of Class VI permit and primacy

approvals as part of supporting CCS projects.

As discussed in this report, three states currently have Class VI primacy. In 2023, in response to a

request from EPA, 23 states and 2 tribes communicated an intent to pursue Class VI primacy. EPA

would need sufficient staffing and resources at the headquarters and regional office level to

manage the significant increase in primacy applications for review.

If more states were to be granted primacy, there could be a long-term decrease in the number of

Class VI permit applications under federal EPA review as these delegated states took on

permitting and enforcement responsibility. One consideration for Congress is whether states differ

in capacity and expertise to administer all the elements of a Class VI program. For example, some

states have regulated deep oil and natural gas-related wells for decades, while other states with

smaller numbers or different types of UIC wells have relied on EPA to administer programs.

States without experience regulating wells for oil and gas production or complex wells may need

additional time and resources to establish state regulations and develop all the program elements

needed to administer a state UIC program.

Potential Amendments to the 2010 Class VI Rule

Another consideration for policymakers involves potential amendments to the 2010 Class VI rule

that established specific regulations and standards for Class VI wells and permitting. For

example, Congress could consider whether to direct EPA to amend the 2010 Class VI rule based

on new information available since it was promulgated. Some stakeholders support EPA

promulgating revisions to the rule. They note that the rule has been in place for over a decade and

that requirements such as monitoring standards, area of review modeling, financial assurances,

and individual well permits should be revised to reflect more recent technology and conditions.56

In the preamble to the 2010 rule, EPA stated its intention to review the rule every six years.57 In

its 2022 report to Congress, however, EPA stated that it would need additional data from more

projects before amending the Class VI rule.58 As the first permits for an operating facility were

issued in 2017, and injection is expected to continue for approximately 10 years for that facility,

no Class VI well project has completed its permit cycle from construction and injection through

post-injection site care, which occurs once injection and well closure is complete.

Environmental Justice Concerns

In recent years, some stakeholders have raised concerns about the community impacts of carbon

capture and sequestration and Class VI well projects. Specifically, they have expressed concerns

that the construction and operation of the wells may place additional burdens on certain

55 P.L. 117-58, Division J.

56 EPA Report to Congress.

57 EPA, “Federal Requirements,” p. 77241.

58 EPA Report to Congress.

Congressional Research Service

14

Class VI Carbon Sequestration Wells: Permitting and State Program Primacy

communities already facing disproportionate environmental, health, or economic challenges.59

Congress may consider exploring these concerns, particularly in the context of other policy

objectives.

Some stakeholders support changes in public participation in the permitting of Class VI wells and

the state UIC Class VI program primacy application process. As discussed earlier in this report,

EPA has promulgated regulations on public participation and issued guidance on consideration of

environmental justice in Class VI permitting and primacy processes. In its oversight role,

Congress may consider issues related to how EPA is implementing relevant public participation

regulations and guidance, including actions detailed in the agency’s 2022 report to Congress on

Class VI permitting.

Author Information

Angela C. Jones

Analyst in Environmental Policy

Disclaimer

This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan

shared staff to congressional committees and Members of Congress. It operates solely at the behest of and

under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other

than public understanding of information that has been provided by CRS to Members of Congress in

connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not

subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in

its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or

material from a third party, you may need to obtain the permission of the copyright holder if you wish to

copy or otherwise use copyrighted material.

59 For example, see “EPA Grants Louisiana Primacy to Permit CCS Wells, Despite EJ Concerns,” InsideEPA.com,

December 29, 2023, https://insideepa.com/daily-news/epa-grants-louisiana-primacy-permit-ccs-wells-despite-ejconcerns,” and “Biden Officials Face Fierce Opposition as They Defend CCS,” InsideEPA.com, January 8, 2024,

https://insideepa.com/outlook/biden-officials-face-fierce-environmental-opposition-they-defend-ccs.

Congressional Research Service

R48033 · VERSION 1 · NEW

15

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.