Judicial Review and the National Environmental Policy Act of 1969

Congressional research reportAug 4, 2022

Ask Donna

What actually matters in this document.

Text

Judicial Review and the National

Environmental Policy Act of 1969

August 4, 2022

Congressional Research Service

https://crsreports.congress.gov

R47205

SUMMARY

Judicial Review and the National

Environmental Policy Act of 1969

R47205

August 4, 2022

Nina M. Hart

The National Environmental Policy Act (NEPA), enacted in 1969, requires federal agencies to

Legislative Attorney

integrate environmental considerations into their decisionmaking processes. It also directs

agencies to use interdisciplinary approaches in these processes and, for specified actions, to

prepare a “detailed statement” about the actions’ effects on the human environment. Because

NEPA applies to many different kinds of agency actions, including construction, land

management, permitting, and funding, it plays a significant role in the administration of many federal programs.

The Council on Environmental Quality (CEQ), an executive branch entity, has issued regulations that instruct agencies on

how to comply with NEPA, and many agencies have promulgated agency-specific regulations that supplement CEQ’s

regulations. Together, these regulations require agencies to prepare different environmental documents depending on the

degree to which a proposed action may cause significant effects to the human environment. If a proposed action will not

cause significant effects, no further analysis is required. In that case, an agency may also rely on a categorical exclusion to

document its determination that the project falls within a category of actions without significant effects. If an agency is

unclear about whether a proposed action will have significant effects, it must prepare an environmental assessment (EA). An

EA showing no significant effects allows an agency to issue a Finding of No Significant Impact (FONSI), while an EA

showing significant effects requires an agency to prepare an environmental impact statement (EIS). An EIS is required for all

proposed actions that have significant effects.

The federal courts have been instrumental in guiding agency compliance with NEPA. Although NEPA contains no provision

for judicial review, courts allow plaintiffs to challenge agency compliance with NEPA by filing challenges under the

Administrative Procedure Act (APA). Plaintiffs often allege that an agency acted “arbitrarily or capriciously” when taking

steps to comply with NEPA, and they seek a variety of remedies, including declarations that an agency violated the APA;

court orders remanding a decision to the agency for further consideration; and preliminary or permanent injunctions that

prevent an agency from implementing disputed actions.

Plaintiffs challenge the steps that agencies take to comply with NEPA in a number of different ways. Some of the more

frequently litigated issues are the following:

Improper Type or Level of NEPA Review. Plaintiffs sometimes allege that an agency improperly relied on a categorical

exclusion because the proposed action would have significant effects. When agencies prepare EAs and then issue FONSIs,

plaintiffs also may allege that the agencies violated the APA by concluding that the project would have no significant effects

and that the agencies therefore should have prepared an EIS.

Failure to Prepare a Supplemental Environmental Review. Agencies must prepare supplemental documents to EAs or

EISs when they learn of new information or make changes to a proposed action that may affect their decisionmaking process.

Plaintiffs challenging an agency’s failure to prepare a supplemental environmental document tend to focus on whether such

new information or changes are sufficient to trigger an agency’s duty to prepare a supplemental document.

Inadequacy of NEPA Review. Plaintiffs often challenge the sufficiency of an agency’s analysis of particular effects in EAs

or EISs. Sometimes, these challenges allege that an agency violated the APA by failing to obtain or analyze sufficient data.

Other challenges focus on the types of effects that CEQ set out in its 1978 regulations—direct effects, indirect effects, and

cumulative impacts—and allege that an agency failed to consider one or more of these specific types of effects. Courts often

consider claims that agencies failed to consider a reasonable range of alternatives to their proposed actions, as required by

NEPA. Plaintiffs also challenge the adequacy of an agency’s NEPA compliance by arguing that an agency failed to consult

with other relevant federal or state agencies or with public stakeholders.

Congressional Research Service

Judicial Review and the National Environmental Policy Act of 1969

Contents

Introduction ..................................................................................................................................... 1

Statutory and Regulatory Background ............................................................................................ 1

NEPA......................................................................................................................................... 1

CEQ and Agency Regulations ................................................................................................... 2

Major Federal Actions......................................................................................................... 3

Determining Significance: Which Level of Environmental Review Is

Appropriate? .................................................................................................................... 4

Supplemental Environmental Review................................................................................. 6

Judicial Review of NEPA: An Overview......................................................................................... 6

Limits on Judicial Review ......................................................................................................... 7

Standing .............................................................................................................................. 7

Statute of Limitations.......................................................................................................... 8

Exhaustion .......................................................................................................................... 8

Remedies in NEPA Litigation ................................................................................................... 9

Selected Issues in NEPA Litigation ................................................................................................ 11

Confirming When NEPA Review Is Required ......................................................................... 11

Assessing Significance of Impacts .......................................................................................... 12

Use of Categorical Exclusions .......................................................................................... 12

Use of EA/FONSI Instead of EIS ..................................................................................... 13

Supplemental Environmental Review ..................................................................................... 14

Adequacy of an EA or EIS ...................................................................................................... 14

Failure to Adequately Consider Effects in an EA or EIS .................................................. 14

Failure to Consider Alternatives ....................................................................................... 17

Insufficient Consultation with the Public.......................................................................... 18

Tables

Table 1. NEPA Litigation Injunctions, 2001-2011......................................................................... 10

Contacts

Author Information........................................................................................................................ 19

Congressional Research Service

Judicial Review and the National Environmental Policy Act of 1969

Introduction

The National Environmental Policy Act (NEPA), enacted in 1969, generally requires federal

agencies to integrate environmental considerations into their decisionmaking processes. Because

this requirement applies to a wide range of federal actions, including both the government’s own

activities and its decisions to allow or to fund other parties’ activities, NEPA plays a significant

role in the administration of many federal programs.

NEPA directs agencies to use interdisciplinary approaches in considering environmental effects

and, for specified actions, requires them to prepare a “detailed statement” about the actions’

effects on the human environment. NEPA also created the Council on Environmental Quality

(CEQ), an entity within the Executive Office of the President. CEQ oversees agency compliance

with NEPA, and, as directed by executive order, has issued regulations used by the agencies for

complying with NEPA. Agencies have also created their own regulations that supplement the

CEQ regulations.

The federal courts have been instrumental in guiding agency compliance with NEPA. Although

NEPA contains no provision addressing the availability of judicial review, courts have long

allowed plaintiffs to challenge an agency’s compliance with NEPA under the Administrative

Procedure Act (APA). This report focuses on the role of the federal courts in reviewing agency

compliance with NEPA. First, the report provides an overview of the relevant statutory and

regulatory framework. Next, it discusses how judicial review works in the NEPA context. Finally,

the report provides an overview of selected issues that arise often in litigation or tend to generate

controversy about NEPA.

Statutory and Regulatory Background

NEPA

NEPA imposes a general directive that, “to the fullest extent possible, [] the policies, regulations,

and public laws of the United States shall be interpreted and administered in accordance” with the

Act.1 It further directs all federal agencies to

(A) utilize a systematic, interdisciplinary approach which will insure the integrated use of

the natural and social sciences and the environmental design arts in planning and in

decisionmaking which may have an impact on man’s environment;

(B) identify and develop methods and procedures, in consultation with the Council on

Environmental Quality . . . which will insure that presently unquantified environmental

amenities and values may be given appropriate consideration in decisionmaking along with

economic and technical considerations;

(C) include in every recommendation or report on proposals for legislation and other major

Federal actions significantly affecting the quality of the human environment, a detailed

statement by the responsible official . . . .2

1 42 U.S.C. § 4332(1). National Environmental Policy Act of 1969, Pub. L. 91-190, 83 Stat. 852 (1970). For more

information on NEPA, see CRS In Focus IF11549, The Legal Framework of the National Environmental Policy Act.

2 Id. § 4332(2).

Congressional Research Service

1

Judicial Review and the National Environmental Policy Act of 1969

The “detailed statement,” now commonly known as an “environmental impact statement” or

“EIS,” must discuss five types of information:

1. the environmental impact of the proposed action;

2. any adverse environmental effects that cannot be avoided should the proposal be

implemented;

3. alternatives to the proposed action;

4. the relationship between local short-term uses of man’s environment and the

maintenance and enhancement of long-term productivity; and

5. any irreversible and irretrievable commitments of resources that would be

involved in the proposed action should it be implemented.3

While creating a detailed statement, agencies must consult and obtain comments from other

federal agencies with jurisdiction or “special expertise with respect to any environmental impact

involved.”4 Agencies must provide copies of the detailed statement and any comments received

during the environmental review process to the President, CEQ, and the public.5

NEPA also created CEQ within the Executive Office of the President.6 CEQ comprises three

members appointed by the President with the advice and consent of the Senate, and one of the

members is designated by the President as Chair.7 NEPA directs CEQ to, among other things,

develop and recommend to the President national policies that further environmental quality;

perform a continuing analysis of changes or trends in the national environment; review and

appraise programs of the federal government to determine their contributions to sound

environmental policy; and oversee implementation of NEPA.8

CEQ and Agency Regulations

CEQ has been instrumental in implementing NEPA by developing regulations that provide more

details about what agencies must do when creating a detailed statement or taking other actions to

comply with NEPA. President Carter ordered CEQ to develop regulations to implement NEPA.9

The 1978 regulations10 created the baseline for agencies structuring their own NEPA procedures

and regulations. The Trump Administration amended parts of these regulations in 2020.11 In

October 2021, the Biden Administration proposed to reinstate some provisions of the 1978

3 Id. § 4332(2)(C)(i)-(v).

4 Id. § 4332(2)(C).

5 Id.

6 Id. § 4342.

7 Id.

8 Id. § 4344.

9 Exec. Order No. 11514, 3 C.F.R. 902 (1970 Comp.), as amended by Exec. Order No. 11991, 3 C.F.R. 123 (1977

Comp.).

10 National Environmental Policy Act—Regulations; Implementation of Procedural Provisions, 43 Fed. Reg. 55,978

(Nov. 29, 1978) (codified at 40 C.F.R. pts. 1500-1508).

11 Update to the Regulations Implementing the Procedural Provisions of the National Environmental Policy Act, 85

Fed. Reg. 43,304 (July 16, 2020) (codified at 40 C.F.R. pts. 1500-1508).

Congressional Research Service

2

Judicial Review and the National Environmental Policy Act of 1969

regulations that the 2020 rulemaking amended or eliminated.12 The Biden Administration

finalized part of its revisions (“Phase One”) in April 2022.13

Major Federal Actions

While NEPA applies to all agencies, as discussed above, it imposes requirements on those

agencies only when they undertake major federal actions.14 NEPA does not define what qualifies

as “major federal actions,” prompting one Supreme Court Justice to note that the statute could

thus “hardly be termed precise.”15 However, federal courts have interpreted the phrase, and

CEQ’s 2020 regulations (informed by that case law) listed actions that tend to qualify as major

federal actions and those that do not. As CEQ’s 2020 rule stated, the list reflects the court

decisions regarding whether actions are “major federal actions” that CEQ chose to include in the

regulations.16

First, the regulations describe what “may” qualify as a major federal action: (1) new and

continuing activities, including projects and programs entirely or partly financed, assisted,

conducted, regulated, or approved by federal agencies; (2) new or revised agency rules,

regulations, plans, policies, or procedures; and (3) legislative proposals.17

Second, the regulations list categories of actions that do not qualify or that “tend” to qualify as

major federal actions. Categories of actions that do not qualify are

extraterritorial activities or decisions, which means agency activities or decisions

with effects located entirely outside of the jurisdiction of the United States;

activities or decisions that are nondiscretionary and made in accordance with the

agency’s statutory authority;

activities or decisions that do not result in final agency action under the

Administrative Procedure Act or another statute that includes a finality

requirement;18

judicial or administrative civil or criminal enforcement actions;

funding assistance solely in the form of general revenue sharing funds with no

federal agency control over the subsequent use of such funds;

nonfederal projects with minimal federal funding or minimal federal involvement

where the agency does not exercise sufficient control and responsibility over the

outcome of the project; and

12 National Environmental Policy Act Implementing Regulations Revisions; Notice of Proposed Rulemaking, 86 Fed.

Reg. 55,757 (Oct. 7, 2021).

13 National Environmental Policy Act Implementing Regulations Revisions; Final Rule, 87 Fed. Reg. 23,453 (Apr. 20,

2022).

14 42 U.S.C. § 4332(c) (“major Federal actions significantly affecting the quality of the human environment”).

15 Kleppe v. Sierra Club, 427 U.S. 390, 420-21 (1976) (Marshall, J., concurring in part and dissenting in part).

16 Update to the Regulations Implementing the Procedural Provisions of the National Environmental Policy Act, 85

Fed. Reg. 43,345-43,346 (July 16, 2020).

17 40 C.F.R. § 1508.1(q)(2). These lists were amended or included in the Biden Administration’s “Phase One”

revisions.

18 Under the Administrative Procedure Act (APA) and some other statutes, an agency action must be “final” before an

individual affected by an agency’s actions may seek judicial review of the action. The Supreme Court defines as “final”

actions that (1) mark the “consummation” of an agency’s decisionmaking process and (2) determine rights or

obligations or result in legal consequences. Bennett v. Spear, 520 U.S. 154, 177-78 (1997).

Congressional Research Service

3

Judicial Review and the National Environmental Policy Act of 1969

loans, loan guarantees, or other forms of financial assistance where the federal

agency does not exercise sufficient control and responsibility over the effects of

such assistance.19

Categories of proposed actions that “tend” to qualify as major federal actions are

adoption of official policy, such as rules, regulations, and interpretations adopted

under the APA or other statutes;

implementation of treaties and international conventions or agreements,

including those implemented pursuant to statute or regulation;

formal documents establishing an agency’s policies which will result in or

substantially alter agency programs;

adoption of formal plans, such as official documents prepared or approved by

federal agencies, which prescribe alternative uses of federal resources, upon

which future agency actions will be based;

adoption of programs, such as a group of concerted actions to implement a

specific policy or plan;

systematic and connected agency decisions allocating agency resources to

implement a specific statutory program or executive directive; and

approval of specific projects, such as construction or management activities

located in a defined geographic area, including those approved by permit or other

regulatory decision as well as federal and federally assisted activities.20

The types of actions that might fall within the scope of major federal actions reach a wide variety

of proposals considered by federal agencies. Examples of major federal actions include

development of wildlife management plans; issuance of commercial use permits within federally

managed lands; construction of new rail lines or facilities; approval of airport layouts; and natural

gas pipeline approvals.21

Determining Significance: Which Level of Environmental Review Is

Appropriate?

Whether a proposed major federal action is expected to cause significant effects on the human

environment determines the level of environmental review an agency must complete to

demonstrate that it has met the requirements of NEPA. Depending on whether the potential

effects are or are not significant, agencies proceed in one of three ways: (1) categorical exclusion;

(2) environmental assessment (EA); or (3) environmental impact statement (EIS). In general,

agencies’ NEPA regulations set out certain types of actions that they consider to be subject to each

of these levels of review, based on their experiences and other analyses. CEQ estimates that

19 40 C.F.R. § 1508.1(q)(1).

20 Id. § 1508.1(q)(3).

21 See, e.g., National Park Service, NEPA Handbook,

https://www.nps.gov/subjects/nepa/upload/NPS_NEPAHandbook_Final_508.pdf; FERC, Environmental Documents,

https://www.ferc.gov/industries-data/natural-gas/environmental-overview/environmental-documents-2022; U.S. Dep’t

of Transportation, Order 5610.1D, Procedures for Considering Envt’l Impacts (draft),

https://www.transportation.gov/office-policy/transportation-policy/dot-order-56101d-procedures-consideringenvironmental-impacts.

Congressional Research Service

4

Judicial Review and the National Environmental Policy Act of 1969

agencies demonstrate NEPA compliance through categorical exclusions for 95% of actions that

are subject to NEPA; EAs for approximately 4%; and EISs for 1%.22

No Significant Impacts: Categorical Exclusions

When a proposed action will not have significant impacts, an agency may use a categorical

exclusion to demonstrate that NEPA does not require detailed analysis. Agencies identify types of

actions that normally do not result in significant impacts and thus require no environmental

review, and list these categorical exclusions in their NEPA regulations.23 In these regulations,

agencies also include provisions for addressing when actions that typically fall into a categorical

exclusion require environmental review due to “extraordinary circumstances.”24 Congress may

also identify categorical exclusions in the first instance.25

Significant Impacts Uncertain: Environmental Assessment

For proposed federal actions that may have some impacts—but potentially not significant

impacts—agencies may prepare an EA, although they may proceed directly to an EIS instead.

The process of preparing an EA can help an agency determine whether to make a Finding of No

Significant Impact (FONSI) or, alternatively, instead prepare a full EIS.26 While preparing an EA,

an agency must involve stakeholders “to the extent practicable.”27 In addition, when a proposed

action is similar to those that typically require an EIS or is unprecedented in nature, an agency

must release a draft FONSI for public review before making its final determination.28

Significant Impacts: Environmental Impact Statement

Proposed actions with significant environmental impacts require an agency to prepare an EIS

(i.e., the “detailed statement” required by NEPA).29 This statement is generally the most

comprehensive of the types of environmental review documents that an agency may use to

comply with NEPA. Although the CEQ regulations require each EIS to be either (1) less than 150

pages or (2) less than 300 pages for projects of “unusual scope or complexity,” unless an

appropriate official authorizes a longer page limit,30 it is common for an EIS to exceed this

length.31

As detailed above, NEPA requires each EIS to analyze the five types of information listed in the

statute. While preparing an EIS, an agency must also submit a draft EIS to the public for review32

22 U.S. Government Accountability Office, National Environmental Policy Act: Little Information Exists on NEPA

Analyses, GAO-14-370 at 7 (Apr. 2014) (citing CEQ statistics).

23 40 C.F.R. § 1501.4.

24 Id. § 1501.4(b).

25

See, e.g., 42 U.S.C. § 15492. Congress sometimes also provides direction about how an agency should make

categorical exclusion determinations. See, e.g., 49 U.S.C. § 304.

26 40 C.F.R. § 1501.5.

27 Id.

28 Id. § 1501.6(a)(2).

29 Id. pt. 1502.

30 Id. § 1502.7.

31 Council on Envt’l Quality, Length of Envt’l Impact Statements (2013-2018) (June 2020),

https://ceq.doe.gov/docs/nepa-practice/CEQ_EIS_Length_Report_2020-6-12.pdf.

32 Id. § 1503.1.

Congressional Research Service

5

Judicial Review and the National Environmental Policy Act of 1969

and respond to comments received.33 Once an agency completes an EIS, it must issue a Record of

Decision (ROD), which identifies the agency’s decision regarding the proposed action, alternative

actions considered, and any mitigation measures that will be implemented.34

Supplemental Environmental Review

Although NEPA does not expressly require an agency to perform a supplemental review, the

Supreme Court has indicated that NEPA implies such a requirement in some cases.35 CEQ’s

regulations codify this requirement. Specifically, agencies must prepare supplemental analyses

when major federal action remains to occur and (1) “the agency makes substantial changes to the

proposed action that are relevant to environmental concerns” or (2) “there are significant new

circumstances or information relevant to environmental concerns and bearing on the proposed

action or its impacts.”36 An agency may also prepare a supplemental EIS whenever it determines

that doing so furthers NEPA’s purposes.37

Judicial Review of NEPA: An Overview

NEPA contains no provision addressing the availability of judicial review. Instead, plaintiffs may

challenge an agency’s compliance with NEPA under the APA.38 The APA generally establishes

how courts review final agency actions, including the appropriate standards of review. Among

other things, courts may find an agency action unlawful and set it aside if it was “arbitrary,

capricious, an abuse of discretion, or otherwise not in accordance with law.”39 In the NEPA

context, plaintiffs often allege that an agency’s actions were arbitrary or capricious, and thus

violate the APA. Reviewing courts generally interpret this to mean that they must consider

whether an agency took a “hard look” at the environmental consequences of their proposed

actions, considered alternatives, and publicly disclosed such information before reaching a final

decision.40 Thus, a court may not “substitute its judgment for that of the agency.”41 In other

words, neither NEPA, nor the courts, direct agencies to prioritize certain values over others or to

reach specific outcomes. It “prohibits uninformed—rather than unwise—agency action.”42

33 Id. § 1503.4.

34 Id. § 1505.2.

35 Marsh v. Or. Nat. Res. Council, 490 U.S. 360, 370-71 (1989) (“The subject of postdecision supplemental

environmental impact statements is not expressly addressed in NEPA. Preparation of such statements, however, is at

times necessary to satisfy the Act’s ‘action-forcing’ purpose.”).

36 40 C.F.R. § 1502.9(d)(1).

37 Id. § 1502.9(d)(2).

38 See, e.g., Lujan v. Nat’l Wildlife Fed’n, 497 U.S. 871, 882 (1990) (“Respondent does not contend that . . . NEPA

provides a private right of action for violations of its provisions. Rather, respondent claims a right to judicial review

under § 10(a) of the APA.”).

39 5 U.S.C. § 706. For more information about the APA, see CRS Legal Sidebar LSB10558, Judicial Review Under the

Administrative Procedure Act (APA).

40 Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350 (1989).

41 Kleppe v. Sierra Club, 427 U.S. 390, 410 n.21 (1976).

42 Methow Valley Citizens Council, 490 U.S. at 351.

Congressional Research Service

6

Judicial Review and the National Environmental Policy Act of 1969

Limits on Judicial Review

The Constitution, the courts, and Congress may limit judicial review of actions taken to comply

with NEPA. This section provides an overview of some of these limitations.

Standing

A plaintiff must have standing to bring a case. Article III of the Constitution requires a plaintiff to

demonstrate an injury in fact that is caused by the alleged statutory violation and that can be

remedied by a court.43 In the NEPA context, injuries are generally procedural in nature (i.e., a

plaintiff is harmed by an agency’s failure to follow NEPA procedures), but to meet the Article III

injury threshold, a plaintiff must allege that the agency’s action will harm the plaintiff’s concrete

interest and that the relevant procedure is designed to protect that interest. For example, in

Cantrell v. City of Long Beach, plaintiffs alleged the Navy did not comply with NEPA in

proposing to convert a closed naval station to a commercial marine container terminal.44 The

plaintiffs were “birdwatchers,” residents of Long Beach and Lakewood, CA, who opposed the

Navy’s plans.45 The U.S. Court of Appeals for the Ninth Circuit held that plaintiffs sufficiently

alleged an injury by pleading that the naval station was currently home to bird habitats, which

plaintiffs enjoyed recreationally as birdwatchers, and that their ability to enjoy the habitats would

be impaired by the proposed conversion.46

The Constitution also prohibits courts from addressing alleged injuries that are “generalized

grievances,” as these do not present “cases” or “controversies,” as required by Article III.47 For

example, plaintiffs asserting “generalized harm to the forest or the environment” lack a concrete

or particularized injury. By contrast, if they assert that harm “affects the recreational or even

the[ir] mere esthetic interests,” then plaintiffs may satisfy the Constitution’s standing

requirements.48

Finally, plaintiffs must demonstrate that the type of injury alleged falls within the “zone of

interests” of the statute invoked.49 The Supreme Court has held that NEPA protects a broad range

of harms, including recreational or aesthetic enjoyment of the environment.50 However, NEPA

does not reach purely economic injuries.51 As the Third Circuit explained:

To accept NEPA litigants whose interests accidentally overlap with the statute’s intended

purpose would not only create a class of plaintiffs far larger than Congress originally

intended, it also would serve to distort the effect of NEPA itself.52

43 Friends of the Earth v. Laidlaw, 528 US 167, 180-81 (2000); Lujan v. Defenders of Wildlife, 504 U.S. 555, 560

(1992).

44 Cantrell v. City of Long Beach, 241 F.3d 674 (9th Cir. 2001).

45

Id. at 676-77.

46 Id. at 682.

47 Lexmark Int’l, Inc. v. Static Control Components, Inc., 572 U.S. 118, 127 n.3 (2014).

48 Summers v. Earth Island Inst., 555 U.S. 488, 494 (2009).

49 Id. at 127-28. The Supreme Court previously described this requirement as part of its “prudential standing” doctrine,

but in Lexmark, recharacterised the requirement as a question of statutory interpretation. Id.

50 Lujan v Nat’l Wildlife Fed’n, 497 US 871 (1990).

51 See, e.g., Maiden Creek Assoc. LP v. U.S. Dep’t of Transp., 823 F.3d 184, 194 (3d Cir. 2016); Ashley Creek

Phosphate Co. v. Norton, 420 F.3d 934, 940 (9th Cir. 2005).

52 Maiden Creek Assoc. LP, 823 F.3d at 194.

Congressional Research Service

7

Judicial Review and the National Environmental Policy Act of 1969

Nonetheless, plaintiffs who allege both environmental and economic injuries may satisfy the

“zone of interests” test.53 Further, plaintiffs who assert environmental injuries, but whose primary

motive for bringing a case is economic interest, also “routinely satisfy” this test.54

Aside from individuals who bring NEPA cases, organizations often bring cases on behalf of their

members. They may do so if (1) at least one of the members has standing; (2) the interests that the

organization seeks to protect are germane to its purposes; and (3) neither the claim nor the type of

relief sought would require the individual members to actively participate in the litigation.55

Statute of Limitations

NEPA does not include a statute of limitations—i.e., a time by which a plaintiff must file a

lawsuit. As discussed above, plaintiffs generally bring NEPA claims using the APA. Courts have

generally held that the statute requiring civil claims against the United States to be brought within

six years applies to APA claims.56 Congress may legislate other time limitations for NEPA claims

if it so chooses. For example, in the Fixing America’s Surface Transportation Act, Congress

imposed a two-year statute of limitations on certain infrastructure projects that require

environmental review under NEPA.57

Exhaustion

Courts generally require plaintiffs to raise their issues with the relevant agency during the

appropriate comment period for the proposed agency action, and if plaintiffs do not do so, the

courts may bar them from later filing a claim involving those issues.58 Nonetheless, the Supreme

Court has suggested that flaws in an EA or EIS “might be so obvious that there is no need for a

commentator to point them out specifically in order to preserve its ability to challenge a proposed

action.”59 Some federal appellate courts follow the Supreme Court’s dicta, allowing some NEPA

challenges to move forward even if the issues were not raised during the public comment

period.60

CEQ’s 2020 regulations state that comments on issues not raised during the public comment

period “shall be considered unexhausted and forfeited.”61 That was a departure from CEQ’s 1978

regulations, which did not expressly limit judicial review of an agency’s NEPA compliance to

53 Centr. S. Dak. Co-op Grazing Dist. v. Sec’y of U.S. Dep’t of Agric., 266 F.3d 889, 895-96 (8th Cir. 2001).

54 Nat’l Ass’n of Home Builders v. U.S. Army Corps of Eng’rs, 417 F.3d 1272, 1287 (D.C. Cir. 2005).

55 Sierra Club v. Morton, 405 U.S. 727, 739-40 (1972); Sierra Club v. FERC, 827 F.3d 59, 65 (D.C. Cir. 2016) (citing

Hunt v. Wash. State Apple Adver. Comm’n, 432 U.S. 333, 343 (1977)).

56 See, e.g., Jersey Hgts. Neighborhood Ass’n v. Glendening, 174 F.3d 180, 186 (4th Cir. 1999); Sierra Club v. Slater,

120 F.3d 623, 630-31 (6th Cir. 1997); Sierra Club v. Penfold, 857 F.2d 1307, 1315 (9th Cir. 1988). Accord Sierra Club

v. U.S. Army Corps of Eng’rs, 446 F.3d 808, 815 (8th Cir. 2006) (noting without deciding that other courts use the sixyear statute of limitations). 28 U.S.C. § 2401(a) states that “every civil action commenced against the United States

shall be barred unless the complaint is filed within six years after the right of action first accrues.”

57 42 U.S.C. § 4370m-6; id. § 4370m(6) (defining “covered project”).

58 Vt. Yankee Nuclear Power Corp. v. Nat. Res. Def. Council, 435 U.S. 519, 553 (1978).

59 Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752, 765 (2004).

60 See, e.g., Friends of Tims Ford v. Tenn. Valley Auth., 585 F.3d 955, 964 (6th Cir. 2009) (allowing a NEPA challenge

to proceed because the agency had not shown why the “deficient” EIS “was not so obvious that [plaintiffs] needed to

comment to preserve its right to appeal”).

61 40 C.F.R. § 1503.3(b) (2020).

Congressional Research Service

8

Judicial Review and the National Environmental Policy Act of 1969

issues raised through public comment, and may be in tension with the Supreme Court’s dicta.62 In

any event, Congress may also legislate on the issue of exhaustion, providing either that potential

plaintiffs must or need not comment during administrative proceedings to preserve an issue for

judicial review.63

Remedies in NEPA Litigation

Plaintiffs ask for a variety of remedies in NEPA litigation. In general, when a plaintiff prevails in

a NEPA case, a court grants declaratory relief and may remand the disputed action to the agency.

The agency then must either abandon its proposed action or take steps to remedy the APA

violations by producing an environmental review that demonstrates that it has complied with

NEPA in selecting that action.

Courts often vacate an agency’s final action in addition to remanding to the agency, meaning that

the agency’s original decision is declared void and ineffective. When a court finds that an agency

violated the APA, the statute directs the court to “set aside”—i.e., vacate—the agency’s action.64

Thus, in NEPA cases, courts have recognized that vacatur is the “ordinary” remedy.65

Nonetheless, courts have created an equitable exception, sometimes ordering remand without

vacatur. That remedy allows the agency’s original action or decision to remain in place while the

agency corrects a deficiency in its NEPA compliance. The leading articulation of this exception is

Allied-Signal, Inc. v. Nuclear Regulatory Commission.66 In this case, the D.C. Circuit stated that

not all actions that violate the APA must be vacated; rather, the court should consider (1) “the

seriousness of the order’s deficiencies” and (2) “the disruptive consequences of” vacatur.67

Applying this test, one court of appeals declined to vacate the Federal Energy Regulatory

Commission’s environmental review on the ground that the agency was “likely to remedy any

deficiencies in its orders on remand, and because vacating the orders would imperil Intervenors’

ability to obtain funding necessary to complete the projects in a timely fashion.”68 By contrast,

another court of appeals affirmed a district court’s decision to vacate a U.S. Army Corps of

Engineers’ decision on the ground that the Corps had previously failed to remedy APA violations

and comply with NEPA.69

According to some legal scholars, the use of the “remand without vacatur” remedy has increased

since the 1970s, particularly in the D.C. Circuit and primarily in cases involving the Clean Air

Act rather than NEPA.70 Judges and practitioners continue to debate whether that remedy is legal

62 See id. § 1503.3 (2019) (detailing specificity of public and agency comments). It is unclear whether the Biden

Administration will seek to amend this provision in its “Phase Two” reforms to CEQ’s regulations.

63 See, e.g., 42 USC 4370m-6(a)(1)(B).

64 5 U.S.C. § 706(2).

65 Black Warrior Riverkeeper v. U.S. Army Corps of Eng’rs, 781 F.3d 1271, 1290 (11th Cir. 2015) (discussing history

of remand without vacatur).

66 988 F.2d 146 (D.C. Cir. 1993).

67 Id. at 150-51.

68 Vecinos para el Bienestar de al Comunidad Costera v. Fed. Energy Reg. Comm’n, 6 F.4th 1321, 1332 (D. C. Cir.

2021).

69 Standing Rock Sioux Tribe v. U.S. Army Corps of Eng’rs, 985 F.3d 1032, 1050-53 (D.C. Cir. 2021).

70 Stephanie J. Tatham, The Unusual Remedy of Remand Without Vacatur, Administrative Conference of the United

States at 30-36 (Jan. 3, 2014),

https://www.acus.gov/sites/default/files/documents/Remand%20Without%20Vacatur%20Final%20Report.pdf.

Congressional Research Service

9

Judicial Review and the National Environmental Policy Act of 1969

and appropriate, however, because it is in tension with the APA’s textual instruction that courts

“set aside” unlawful agency actions and because it is inconsistently granted by the courts.71

In some cases, parties request permanent injunctive relief in addition to the types of remedies

discussed above. Vacatur often has the same practical effect as a permanent injunction in that,

once an agency’s final decision is set aside, an agency cannot proceed with the proposed action.

However, while vacatur generally leaves an agency free to make a new decision without further

court supervision, an injunction may provide a more specific direction to an agency prohibiting it

from proceeding with part or all of a proposed action until the agency comes into compliance

with NEPA.72 In choosing between those two remedies, the Supreme Court has stressed there is

no “thumb on the scales” in favor of an injunction.73 Instead, the Court affirmed that the

traditional requirements for permanent injunctive relief apply in the NEPA context:

A plaintiff must demonstrate: (1) that it has suffered an irreparable injury; (2) that remedies

available at law, such as monetary damages, are inadequate to compensate for that injury;

(3) that, considering the balance of hardships between the plaintiff and defendant, a remedy

in equity is warranted; and (4) that the public interest would not be disserved by a

permanent injunction.74

CEQ data on NEPA litigation from 2001 to 2011 indicates that the number of injunctions varied

significantly, although never reaching above 18 per year (Table 1).75

Table 1. NEPA Litigation Injunctions, 2001-2011

Preliminary Injunctions Granted Per Year

Permanent Injunctions Issued Per Year

Year

Number

Year

Number

2001

5

2001

0

2002

4

2002

8

2003

4

2003

2

2004

6

2004

1

2005

18

2005

7

2006

8

2006

16

2007

10

2007

18

2008

6

2008

10

2009

2

2009

15

2010

5

2010

4

2011

5

2011

3

Source: Created by CRS with data from CEQ.

71 See id. at 9-18.

72 See, e.g., Minn. Pub. Interest Research Grp. v. Butz, 358 F. Supp. 584 (D. Minn. 1973) (issuing injunction after

Forest Service indicated it would continue to log approximately 3,000 acres despite the court’s ruling that the Service’s

EIS on the logging project was deficient).

73 Monsanto Co. v. Geertson Seed Farms, 561 U.S. 139, 157 (2010).

74 Id. at 156-57 (quoting eBay Inc. v. MercExchange L.L.C., 547 U.S. 388, 391 (2006)).

75 CEQ, NEPA Litigation Surveys: 2001-2013, https://ceq.doe.gov/docs/ceq-reports/nepa-litigation-surveys-20012013.pdf. CEQ did not report on whether courts granted any requests for permanent injunctions in 2012 or 2013.

Congressional Research Service

10

Judicial Review and the National Environmental Policy Act of 1969

When plaintiffs file a complaint, they sometimes request a preliminary injunction, which is an

order prohibiting an agency from implementing the action in dispute while the litigation is

ongoing.

The Supreme Court most recently addressed what a party seeking a preliminary injunction must

demonstrate in Winter v. Natural Resources Defense Council. In that case, the Court emphasized

its “frequently reiterated standard” for obtaining a preliminary injunction:

A plaintiff seeking a preliminary injunction must establish that he is likely to succeed on

the merits, that he is likely to suffer irreparable harm in the absence of preliminary relief,

that the balance of equities tips in his favor, and that an injunction is in the public interest. 76

Selected Issues in NEPA Litigation

NEPA litigation involves a wide range of agencies and raises issues involving agency choices and

determinations. This section provides an overview of selected issues raised in NEPA litigation

that may be of interest to Congress.

Confirming When NEPA Review Is Required

Courts must occasionally address what happens when an agency is faced with a potential conflict

between NEPA and other statutory mandates. As discussed above, the requirements of NEPA

apply “to the fullest extent possible.”77 In other words, as the Supreme Court has held, NEPA was

not intended to repeal any other statute by implication. Thus, when “a clear and unavoidable

conflict in statutory authority exists, NEPA must give way.”78 Such a conflict may exist, for

example, if the period for implementing a statutory mandate is too short for an agency to

complete environmental review under NEPA.79

Related to this point, an agency need include in its environmental analyses only those alternatives

it has discretion to select. As the Supreme Court described, agencies should be guided by a “rule

of reason” when taking steps to comply with NEPA, and such a rule is not served by requiring

agencies to evaluate the effects of actions it lacks legal authority to prevent.80 In Department of

Transportation v. Public Citizen, the Supreme Court considered whether the Federal Motor

Carrier Safety Administration (FMCSA) failed to satisfy NEPA by not considering the

environmental effects related to increased entry of trucks from Mexico into the United States. The

Court held that the FMCSA did not violate NEPA because the agency lacked any statutory ability

to regulate or prevent the cross-border traffic, which had been ordered by the President in

response to a ruling from an arbitral panel convened under the North American Free Trade

Agreement.81

Some courts also hold NEPA does not apply when an agency’s actions to comply with other

statutes are “functionally equivalent” to NEPA. This requires courts to assess, on a case-by-case

basis, what an agency must take into account when complying with other statutes, especially

76 Winter, 555 U.S. at 20-21.

77 42 U.S.C. § 4332(2).

78 Flint Ridge Dev. Corp. v. Scenic Rivers Ass’n of Okla., 426 U.S. 776, 788 (1976).

79 Id. at 788-89 (“inconceivable” that an agency could comply with NEPA within 30-day deadline for issuance of

statement of record under Disclosure Act).

80 Dep’t of Transp. v. Pub. Citizen, 541 U.S. 762, 767-68 (2004).

81 Id. at 768; see also Ala. Wilderness League v. Jewell, 788 F.3d 1212, 1225-26 (9th Cir. 2015).

Congressional Research Service

11

Judicial Review and the National Environmental Policy Act of 1969

environmental effects or considerations.82 Other courts do not use the “functional equivalent”

approach, instead asking whether another statute has “displaced” NEPA.83

Assessing Significance of Impacts

Plaintiffs sometimes challenge an agency’s assessment of whether an action will have significant

impacts, arguing that an agency inappropriately relied on a categorical exclusion or should have

prepared an EIS instead of an EA.

Use of Categorical Exclusions

When an agency relies on a categorical exclusion (CX) to determine that further NEPA analysis is

not required, plaintiffs may argue that the agency (1) improperly used a CX for a specific action

or (2) created an improperly scoped CX.

In disputes involving challenges to specific uses of CXs, plaintiffs have raised different theories

under the APA. For instance, in some cases, plaintiffs have alleged that an agency failed to

document its determination to use a CX. In Wilderness Watch & Public Employees for

Environmental Responsibility v. Mainella, plaintiffs alleged that the National Park Service’s

decision to use a CX to authorize tourist operation of motor vehicles on protected “wilderness

areas” violated the APA because the agency failed to document its decision.84 The Park Service

argued it did not need to document its decision because requiring any such written evidence

would “defeat the purpose of the exclusion.”85 The Eleventh Circuit rejected that argument,

holding that the agency’s failure to provide any documents to indicate why use of a CX was

appropriate made it “difficult for a reviewing court to determine if the application of an exclusion

is arbitrary and capricious.”86

In other cases, plaintiffs challenge whether an agency reasonably determined that no

“extraordinary circumstances” existed that would have prevented the agency from relying on a

CX. For instance, in Alaska Center for the Environment v. U.S. Forest Service, the Forest Service

relied on a CX to issue one-year licenses for commercial helicopter activities in National Forest

lands.87 Plaintiffs sued, alleging that such activities would have significant environmental impacts

and fell within the “extraordinary circumstances” exception to the CX.88 The Ninth Circuit

affirmed the district court’s decision that the Forest Service acted arbitrarily and capriciously

when issuing certain licenses because it merely restated the CX and failed to provide reasons for

why the CX applied.89

82 See, e.g., Envtl. Def. Fund, Inc. v. Envtl. Protection Agency, 489 F.2d 1247 (D.C. Cir. 1973) (holding FIFRA the

functional equivalent of NEPA since the statute required the agency to take environmental effects into account and

consider public comments about such effects). See also Pac. Legal Fndtn. v. Andrus, 657 F.2d 829, 834 (6th Cir. 1981)

(discussing lower court practice applying the “functional equivalent” test).

83 See, e.g., San Luis & Delta-Mendota Water Auth. v. Jewell, 747 F.3d 581, 650-51 (9th Cir. 2014) (Section 7 of the

Endangered Species Act does not displace NEPA requirements and agency must comply with both statutes).

84 375 F.3d 1085, 1094 (11th Cir. 2004).

85 Id.

86 Id. See also California v. Norton, 311 F.3d 1162 (9th Cir. 2002).

87 189 F.3d 851 (9th Cir. 1999).

88 Id. at 854.

89 Id. at 859.

Congressional Research Service

12

Judicial Review and the National Environmental Policy Act of 1969

As noted above, plaintiffs sometimes seek to invalidate an agency’s adoption of a CX. In Sierra

Club v. Bosworth, the plaintiffs alleged that the Forest Service violated by the APA by

categorically excluding all fuel reduction projects of up to 1,000 acres and burn projects of up to

4,500 acres.90 The Ninth Circuit concluded that the Forest Service’s CX violated the APA because

the Service (1) collected data only to justify, rather than assess, the appropriateness of a CX; (2)

failed to explain why the cumulative effect of each project would not have significant

environmental effects; and (3) failed to specify criteria for each project that would ensure they

had no significant environmental effects.91

Use of EA/FONSI Instead of EIS

Agencies and plaintiffs sometimes disagree about whether an agency should have prepared an

EIS in instances when an agency had prepared an EA, concluded that the project would not result

in significant environmental effects, and then issued a FONSI.

Some plaintiffs assert that an agency failed to take the requisite “hard look” by reasonably

assessing the evidence before it. For example, in O’Reilly v. U.S. Army Corps of Engineers, the

Fifth Circuit considered whether the Corps reasonably issued an EA and FONSI when it had

allegedly failed to explain how mitigation measures would offset environmental damage.92 The

Fifth Circuit found that “the EA provides only cursory detail as to what those measures are and

how they serve to reduce those impacts to a less-than-significant level,” and thus the agency did

not comply with NEPA.93 By contrast, in Spiller v. White, the Fifth Circuit upheld a FONSI for a

project approving use of a pre-existing pipeline to transport petroleum products, subject to

specific mitigation measures.94 Specifically, the court found that the “exhaustive and extensive”

EA demonstrated that the agencies adequately considered and explained the proposed mitigation

measures and how such measures could offset the environmental impacts caused by the pipeline’s

use.95

Other disputes involve questions about an agency’s reliance on certain types of information. As

discussed above, one of NEPA’s objectives is to ensure that agencies are informed about the

environmental consequences of their actions. Litigation thus arises about whether an agency

inappropriately relied on outdated information. In Native Ecosystems Council v. U.S. Forest

Service, the Forest Service had prepared an EA for a resource management plan covering parts of

the Helena National Forest as a means of reducing the number of high-intensity, stand-replacing

fires. Based in part on a 1996 EIS it had prepared for a larger-scale version of the newly proposed

resource management plan, the Forest Service concluded that the management techniques would

not create significant environmental impacts. Plaintiff argued that the Forest Service erred in

relying on the 1996 EIS in part because subsequent data showed that the 1996 project eliminated

one pair of goshawks (a bird species inhabiting the area). The Ninth Circuit rejected plaintiff’s

claim, finding that the Forest Service took a “hard look” by considering this fact against other

90 510 F.3d 1016 (9th Cir. 2007).

91 Id. at 1026-33.

92 477 F.3d 225 (5th Cir. 2007).

93 Id. at 234.

94 352 F.3d 235 (5th Cir. 2003).

95 Id. at 241-44.

Congressional Research Service

13

Judicial Review and the National Environmental Policy Act of 1969

data showing that goshawks change nesting sites each year and nest near logged sites before

concluding that the proposed project would not have significant effects on the goshawks.96

Courts that determine an agency violated the APA when issuing a FONSI must decide whether to

remand with the specific instruction to prepare a new EA or a full EIS. As explained by the Fifth

and Ninth Circuits, a deficient EA does not necessarily warrant such an instruction. Rather, such

an instruction may be warranted if “the evidence in a complete administrative record

demonstrates that the project or regulation may have a significant impact.”97 By contrast, when a

court cannot determine whether a proposed action will have significant impacts, it may remand

with instructions for the agency to comply with NEPA through the appropriate environmental

review process.98 For example, in O’Reilly v. U.S. Army Corps of Engineers, the Fifth Circuit

remanded with instructions to prepare a new EA or an EIS, as appropriate, because the court

could not determine, based on the agency’s deficient explanations, whether or not the proposed

mitigation measures would eliminate significant environmental effects.99

Supplemental Environmental Review

Plaintiffs sometimes claim that an agency failed to prepare an appropriate supplemental

environmental review. These disputes tend to center on whether new information or changes to a

proposed action trigger additional NEPA requirements. For example, in DuBois v. U.S.

Department of Agriculture, the Forest Service issued a permit for expansion of a ski facility in a

national forest, approving “Alternative 6” in the final EIS.100 Plaintiffs challenged the permit,

arguing that Alternative 6 appeared for the first time in the final EIS and represented a substantial

change from the original proposal and other alternatives listed in the draft EIS, thus requiring the

Forest Service to prepare a supplemental EIS. The First Circuit agreed with plaintiffs, finding that

Alternative 6 was sufficiently different from the other alternatives considered in the EIS that

“public commenters might have pointed out, if given the opportunity—and the Forest Service

might have seriously considered—wholly new problems posed.”101 Based on these findings, the

court ordered the Forest Service to prepare a supplemental EIS.

Adequacy of an EA or EIS

Plaintiffs sometimes challenge the procedural or substantive adequacy of an EA or EIS, with

issues ranging from an agency’s alleged failure to consider certain effects or alternative proposals

to an agency’s alleged failure to consult adequately with the public.

Failure to Adequately Consider Effects in an EA or EIS102

In some cases, plaintiffs allege that an agency failed to analyze adequately all relevant effects in

an EA or EIS and therefore violated the APA. In these cases, courts review the agency’s analysis

96 Id. at 1243-44.

97 Ctr. for Biological Diversity v. Nat’l Highway Traffic Safety Admin., 538 F.3d 1172, 1225 (9th Cir. 2008); see also

O’Reilly v. U.S. Army Corps of Eng’rs, 477 F.3d 225, 239 (5th Cir. 2007).

98 Id.

99 O’Reilly, 477 F.3d at 240-41.

100 102 F.3d 1273 (1st Cir. 1996).

101 Id. at 1292-93.

102 This section was prepared by CRS Legislative Attorney Adam Vann.

Congressional Research Service

14

Judicial Review and the National Environmental Policy Act of 1969

to determine whether the agency’s decision to limit or exclude consideration of particular effects

was arbitrary or capricious. Plaintiffs frame these claims in a variety of ways.

For example, some plaintiffs argue that an agency’s evaluation of a particular effect was

insufficient because the agency lacked enough data to make a reasoned decision. The Tenth

Circuit considered this type of claim in Colorado Environmental Coalition v. Dombeck. In that

case, plaintiffs argued that the Forest Service failed to gather sufficient data about the effects of

expansion of a ski area on the lynx population and failed to disclose in the EIS that such

information was unavailable.103 The Tenth Circuit disagreed with plaintiffs, holding that the

record demonstrated that the Service collected and analyzed the “best available data” while also

explaining the data’s limitations, and held that plaintiffs’ claim amounted to nothing more than an

effort to impose additional data gathering requirements on the agency.104

Other cases involve allegations that an agency failed to assess the cumulative impacts of proposed

actions. Cumulative impacts “result from the incremental effects of the action when added to the

effects of other past, present, and reasonably foreseeable actions regardless of what agency

(Federal or non-Federal) or person undertakes such other actions.”105 Agencies retain some

discretion as to how to make these assessments, and the courts examine whether the methodology

or explanation was reasonable. For example, the Sixth Circuit concluded that the U.S. Army

Corps of Engineers could reasonably look at the effects of prior permits for mining activities that

discharged dredged or fill material into U.S. waterways “in the aggregate” as a method of

performing a cumulative impacts analysis.106 The court concluded, however, that the Corps did

not comply with the cumulative impact analysis requirement because the Corps described its

methodology but then “failed to identify any impact—aggregate or otherwise—of past

actions.”107 By contrast, the Ninth Circuit upheld a Bureau of Reclamation EA with regard to its

consideration of past events that may have cumulative impacts on the proposed action.

Specifically, the court held that although the agency’s discussion in the “cumulative effects” part

of the EA was vague and cursory, the EA overall included “quantified or detailed information”

relevant to cumulative impacts and satisfied NEPA’s requirements.108

Another set of cases involves allegations that an agency failed to consider all relevant indirect

effects arising from a proposed action. Recent federal litigation involving indirect effects has

addressed how agencies should consider the effects of climate change in their NEPA analyses. In

2017, the D.C. Circuit issued a significant decision assessing the Federal Energy Regulatory

Commission’s duty to consider the climate-change-related impacts of upstream and downstream

activities associated with a proposed pipeline.109 In Sierra Club v. FERC, the court reviewed

103 185 F.3d 1162 (10th Cir. 1999).

104 Id. at 1172-73.

105 40 C.F.R. § 1508.1(g)(3). CEQ’s 1978 definition of cumulative impact was substantively the same as the definition

currently in force, and adopted by the Biden Administration. The 1978 definition, which was applied by the courts in

the decisions discussed here, states as follows: cumulative impacts are “the impact on the environment which results

from the incremental impact of the [proposed] action when added to other past, present, and reasonably foreseeable

future actions.” 40 C.F.R. §§ 1508.7, 1508.9(b) (1978).

106 Ky. Riverkeeper, Inc. v. Rowlette, 714 F.3d 402, 408 (6th Cir. 2013).

107 Id.; see also Nat. Res. Defense Council, Inc. v. Hodel, 865 F.2d 288 (D.C. Cir. 1988) (holding Secretary of the

Interior failed to discuss any cumulative impacts in FEIS).

108 Ctr. for Envtl. Law and Pol’y v. U.S. Bur. of Reclamation, 655 F.3d 1000, 1008-09 (9th Cir. 2011).

109 When an agency approves a project, the “upstream” and “downstream” impacts of that project are those that will

result from the project and other activities that may increase as a result of the project. For example, in a case involving

approval for an offshore oil and drilling pipeline, the Ninth Circuit described these effects as follows:

“Upstream emissions are those that result directly from the project itself (e.g., construction and operation),

Congressional Research Service

15

Judicial Review and the National Environmental Policy Act of 1969

FERC’s decision to issue a certificate of public convenience and necessity for the proposed

Southeast Market Pipelines Project and the Sabal Trail pipeline. Environmental groups and

landowners challenged the decision, arguing among other things that the EIS prepared by FERC

“failed to adequately consider the project’s contribution to greenhouse-gas emissions.”110 The

court agreed:

[G]reenhouse-gas emissions are an indirect effect of authorizing this project, which FERC

could reasonably foresee, and which the agency has legal authority to mitigate. The EIS

accordingly needed to include a discussion of the “significance” of this indirect effect, as

well as “the incremental impact of the action when added to other past, present, and

reasonably foreseeable future actions.”

Quantification would permit the agency to compare the emissions from this project to

emissions from other projects, to total emissions from the state or the region, or to regional

or national emissions-control goals. Without such comparisons, it is difficult to see how

FERC could engage in “informed decision making” with respect to the greenhouse-gas

effects of this project, or how “informed public comment” could be possible. 111

Two years later, the same court elaborated on agencies’ obligation to evaluate upstream and

downstream impacts on climate change in Birckhead v. FERC.112 In this case, a number of local

stakeholders challenged FERC’s decision to issue a certificate of public convenience and

necessity for the construction and operation of a natural gas compression facility in Tennessee.

The court dismissed that claim on procedural grounds, but nonetheless noted that agencies must

attempt to obtain information needed to fulfill their statutory obligations, which in that case

included consideration of indirect upstream and downstream environmental effects related to the

proposed facility.113

The same court considered FERC’s responsibility to evaluate climate change impacts during a

NEPA review in Vecinos para el Bienestar de la Comunidad Costera v. FERC. In that case, the

D.C. Circuit heard a challenge to FERC’s decision to issue certificates for the construction and

operation of three export LNG terminals and associated pipeline facilities in Texas. FERC

concluded in its EISs that it had been “unable to determine the significance of the Project’s

contribution to climate change” because “there is not universally accepted methodology to

attribute discrete, quantifiable, physical effects on the environment” of a particular project.114 The

petitioners claimed, among other things, that in that situation CEQ regulations require an agency

to “include within the environmental impact statement … [t]he agency’s evaluation of such

impacts based on theoretical approaches or research methods generally accepted in the scientific

community.”115 The court agreed, finding that FERC was required to use the social cost of carbon

or some other generally accepted methodology to assess the impact of the projects’ greenhouse

gas emissions.116

and downstream emissions are those that result from the consumption of the oil produced by the project (e.g., heating

homes or fueling cars).” Ctr. for Biological Diversity v. Bernhardt, 982 F.3d 723, 735 (9th Cir. 2020).

110 Sierra Club v. FERC, 867 F.3d 1357 (D.C. Cir. 2017).

111 Id. at 1363.

112 925 F.3d 510 (D.C. Cir. 2019).

113 Id. at 520.

114 Vecinos para el Bienestar de la Comunidad Costera v. FERC, 6 F.4th 1321, 1328 (D.C. Cir. 2021).

115 Id. at 1328.

116 Id. at 1329. See also Ctr. for Biological Diversity v. Bernhardt, 982 F.3d 723 (9th Cir. 2020). Cf. 350 Montana v.

Bernhardt, 443 F. Supp. 3d 1185, 1196 (D. Mont. 2020) (holding agency was not required to use the social cost of

Congressional Research Service

16

Judicial Review and the National Environmental Policy Act of 1969

Failure to Consider Alternatives

NEPA requires agencies to consider alternatives to their proposed actions as part of the

environmental review process. Courts and CEQ often refer to this requirement as the “heart” of

the environmental review.117 Agencies need not analyze every idea; rather, “the concept of

alternatives must be bounded by some notion of feasibility.”118 Thus, agencies must exercise

“common sense” when determining which proposals to include in an EIS, and courts will not find

an EIS insufficient “simply because the agency failed to include every alternative device and

thought conceivable by the mind of man.”119

Challenges to an agency’s consideration of alternatives to the proposed action arise in a variety of

ways. Some case law requires the courts to determine whether an agency impermissibly narrowed

the purpose of its project to predetermine what reasonable alternatives to the proposed action

existed. For example, in Simmons v. U.S. Army Corps of Engineers, the Seventh Circuit held that

the Corps unreasonably narrowed the range of feasible alternatives by defining the project’s

purpose as “supplying two users (Marion and the Water District) from a single source—namely, a

new lake.”120 The court found that the Corps failed to study and therefore to appropriately justify

whether addressing water shortage problems in Marion and the Water District was well-served by

a single-source project, and thereby improperly narrowed the parameters of the project and its

consideration of alternatives only to single-source options.121 By contrast, the Ninth Circuit in

Muckleshoot Indian Tribe v. U.S. Forest Service held that the agency did not improperly narrow

the scope of the project and thereby unreasonably limit the alternatives it considered. There,

plaintiffs alleged that the statement of purpose—to “consolidate ownership and enhance future

resource conservation and management by exchanging parcels of National Forest System and

Weyerhaeuser land”—impermissibly predetermined the contours of the project and dictated the

alternatives that the agency could consider.122 The Ninth Circuit agreed that the statement of

purpose read in isolation might impermissibly restrict the range of alternatives. However, the

court concluded that the narrow statement was part of the agency’s broader, more general

objective of “creat[ing] consolidated land ownership patterns where consistent management

mandates, policies and objectives apply across large blocks of land.”123

In other cases, plaintiffs have contended that an agency failed to assess adequately the alternatives

on their merits. For instance, plaintiffs sometimes argue that an agency improperly refused to

include or improperly eliminated from consideration a proposed alternative that would meet the

agency’s stated purpose. The Ninth Circuit rejected such an argument in Northern Alaska

Environmental Center v. Kempthorne. In that case, the court held that the Bureau of Land

Management (BLM) reasonably refused to analyze an alternative proposed by the Audubon

carbon protocol when agency gave reasons that the protocol was too indeterminate to be helpful for decisionmaking).

117 See, e.g., 40 C.F.R. § 1502.14(f) (1988); CEQ, A Citizen’s Guide to the NEPA 16 (Dec. 2007) (“The identification

and evaluation of alternative ways of meeting the purpose and need of the proposed action is the heart of the NEPA

analysis.”); Wyoming v. U.S. Dep’t of Agric., 661 F.3d 1209, 1243 (10th Cir. 2011); City of Carmel-By-The-Sea v.

U.S. Dep’t of Transp., 123 F.3d 1142, 1155 (9th Cir. 1997); Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190,

194 (D.C. Cir. 1991).

118 Vt. Yankee Nuclear Power Corp. v. Nat. Res. Defense Council, Inc., 435 U.S. 519, 551 (1978).

119 Id.

120 120 F.3d 664, 666-67 (7th Cir. 1997).

121 Id. at 667.

122 177 F.3d 800, 811 (9th Cir. 1999).

123 Id. at 812-13.

Congressional Research Service

17

Judicial Review and the National Environmental Policy Act of 1969

Society in the EIS because (1) BLM determined that its inclusion “was inconsistent with the

[Nuclear Waste Power Act] project and statutory mandates,” and (2) BLM included aspects of the

Audubon Society’s proposal in the preferred alternative, suggesting the agency carefully

evaluated the proposal.124 By contrast, the Tenth Circuit held that the Department of

Transportation violated the APA by removing an alternative proposal from the EIS, ostensibly

because of its high costs, without providing a verified cost estimate to support its conclusion.125

Insufficient Consultation with the Public

In addition to encouraging informed agency decisionmaking, one of NEPA’s purposes is to

provide for public disclosure and participation. Plaintiffs sometimes allege that an agency failed

to consult with the public to the extent that NEPA requires for a particular decision.

In general, claims involving the consultation requirements for EISs allege that an agency denied

the public a meaningful opportunity to comment by (1) failing to give sufficient information

about the project; (2) failing to disclose certain aspects of a proposed action; or (3) failing to

provide timely disclosures. For example, in State of California v. Block, California challenged the

U.S. Forest Service’s EIS for classifying roadless national forest management land into three

management categories, arguing that the Service failed to provide adequate opportunity for public

comment because it did not disclose all contours of the proposed action until the final EIS.126 The

Ninth Circuit agreed, holding that the agency’s final proposed action was so different in

substance from the alternatives considered in the draft EIS that the public could not have

provided meaningful input on the proposed action before the final EIS.127 Similarly, in Idaho v.

Kempthorne, the federal district court held that the Forest Service violated the APA when

preparing an EIS for a rule to preserve roadless forest system land because (1) the Service did not

present maps or other concrete data to the public during the public comment period and (2)

Service officials “were ill-prepared to answer the questions and concerns of the general public”

during hearings.128

In preparing an EA, an agency must involve the public to the extent practicable,129 and cases

involving EAs likewise raise questions about the sufficiency of an agency’s disclosure of

information. For example, in a challenge to the U.S. Army Corps of Engineers’ EA for proposed

surface mines that required the Corps to issue dredge and fill permits, a federal court held that the

Corps failed to disseminate significant and “substantive information concerning compensatory

mitigation” in public notices about the EA.130

Because preparation of an EA requires agencies to involve the public only to the extent

practicable, however, agencies retain greater discretion as to when and how to fulfill this

mandate. In Theodore Roosevelt Conservation Partnership v. Salazar, the D.C. Circuit considered

whether BLM satisfied its obligation to involve the public while preparing EAs for natural gas

drilling permits. The D.C. Circuit stressed that an agency “need not include the public in the

preparation of every EA”; rather, an agency may involve the public at different stages as

124 457 F.3d 969, 978 (9th Cir. 2006).

125 Utahns for Better Transp. v. U.S. Dep’t of Transp., 305 F.3d 1152, 1164-65 (10th Cir. 2002).

126 690 F.2d 753, 769-70 (9th Cir. 1982). This case involved CEQ guidelines about public consultation, which were

later incorporated into CEQ’s 1978 regulations.

127 Id. at 772.

128 142 F. Supp. 2d 1248, 1260-61 (D. Idaho 2001).

129 40 C.F.R. § 1501.5(e); id. § 1501.4(b) (1978).

130 Ohio Valley Envtl. Coal. v. U.S. Army Corps of Eng’rs, 674 F. Supp. 2d 783, 809-10 (S.D. W. Va. 2009).

Congressional Research Service

18

Judicial Review and the National Environmental Policy Act of 1969

appropriate.131 Applying this flexible standard, the court upheld BLM’s public involvement for

several reasons. First, BLM posted notices of its intent to prepare EAs for the permits, and even

though it did not expressly seek comments, plaintiffs had ample time to submit comments before

BLM issued final EAs, according to the court. Second, BLM provided copies of the draft EAs to

plaintiffs when they requested copies and responded to comments from plaintiffs in the final

EAs.132

Author Information

Nina M. Hart

Legislative Attorney

Disclaimer

This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan

shared staff to congressional committees and Members of Congress. It operates solely at the behest of and

under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other

than public understanding of information that has been provided by CRS to Members of Congress in

connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not

subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in

its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or

material from a third party, you may need to obtain the permission of the copyright holder if you wish to

copy or otherwise use copyrighted material.

131 616 F.3d 497, 519 (D.C. Cir. 2010).

132 Id. at 519-20.

Congressional Research Service

R47205 · VERSION 1 · NEW

19

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.