Summary

Growth in U.S. natural gas production has driven the development of new pipelines from

producing regions to consuming markets. Over 300,000 miles of transmission pipeline already

transport natural gas across the country. However, if domestic natural gas trends continue, the

need for new pipelines could still be substantial. As a result of military conflict in Europe,

demand for U.S. liquefied natural gas exports is growing as well, which is driving associated

natural gas infrastructure development. This new infrastructure could amount to several thousand

miles of new interstate pipeline and on the order of $40 billion in capital investment.

Under the Natural Gas Act (NGA), companies seeking to build interstate natural gas pipelines

need certificates of public convenience and necessity from the Federal Energy Regulatory

Commission (FERC). The commission’s regulatory process for certificate applications consists of

pre-filing, certificate application, application review (including environmental review),

authorization, and post-certificate proceedings. Several aspects of FERC’s review practices have

been the subject of FERC dissent, debate in Congress, or litigation. Key challenges to FERC

certification involve environmental review, evaluating project need, review timing, relations with

other agencies, changes in industry structure, export issues, environmental justice, and public

participation. The Bush, Obama, Trump, and Biden Administrations issued executive orders

intended to change federal permitting of infrastructure, specifically including energy

infrastructure. Exactly how these orders may have affected natural gas pipeline siting is not clear.

Pipeline expansion has prompted numerous congressional hearings and legislative proposals

regarding FERC’s role in natural gas pipeline siting. At least a dozen related bills have been

introduced in the 117th Congress, including the FREE American Energy Act (S. 3982), the

ENSURE Act (S. 3908), the Energy Freedom Act (S. 3762, H.R. 7094), the Rebuild America

Now Act (S. 1254), the Landowner Fairness Act (S. 641), the Ukraine Assistance and American

Energy Acceleration Act (H.R. 7012), a bill addressing pipeline landowners’ rights (H.R. 2889),

the SAFER Pipelines Act of 2021 (H.R. 2115), the Promoting Interagency Coordination for

Review of Natural Gas Pipelines Act (H.R. 1616), the CLEAN Future Act (H.R. 1512), the

Ending Natural Gas Companies’ Seizure of Land for Export Profits Act (S. 655), and the

Environmental Justice Mapping and Data Collection Act of 2021 (H.R. 516).

On February 17, 2022, FERC issued two statements updating its policies for the certification of

natural gas pipelines. The first established a new policy “to provide a more comprehensive

analytical framework” for how FERC would evaluate certificate applications. The second

established FERC’s interim policy for evaluating the greenhouse gas impacts of proposed

pipelines and described how FERC would “integrate climate considerations into its public interest

determinations.” On March 24, 2022, facing criticism of these new policies, FERC redesignated

both policy statements as drafts and invited additional comments. The commission has not stated

if or when it intends to reissue revised policy statements. The draft statements will not apply to

pending or new permit applications before FERC issues final guidance.

FERC’s policy proceedings cover key congressional concerns as well as issues arising in

certificate reviews and litigation. While FERC’s policy proceedings do not guarantee any

particular changes to gas pipeline certification, they may provide valuable information and

context for congressional oversight. If Congress disagrees with FERC’s future policy choices

based on the findings of its policy proceedings, those findings could provide an informed basis

and clearer context for subsequent legislative proposals. FERC’s policy options may apply only

to those aspects of gas pipeline regulation which fall directly within the commission’s statutory

authority under the NGA or within its discretion under other federal statutes.

Congressional Research Service

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Contents

Introduction ..................................................................................................................................... 1

A Growing Gas Pipeline Network ................................................................................................... 2

FERC Pipeline Certification Process............................................................................................... 4

Application Pre-Filing............................................................................................................... 4

Certificate Application and FERC Review ............................................................................... 5

Environmental Review Under NEPA.................................................................................. 6

Certificate Authorities ............................................................................................................... 7

Post-Certificate Proceedings ..................................................................................................... 8

Gas Pipeline Siting Challenges ....................................................................................................... 9

Identifying Indirect Environmental Impacts ............................................................................. 9

Evaluating Project Need ........................................................................................................... 11

Timing and Relations with Other Agencies ............................................................................ 13

Changes in the Domestic Gas Industry Structure.................................................................... 14

Natural Gas Infrastructure for Export ..................................................................................... 15

Environmental Justice ............................................................................................................. 16

Public Participation ................................................................................................................. 17

Recent Executive Orders ............................................................................................................... 17

Executive Order 13212 ........................................................................................................... 18

Executive Order 13604 ........................................................................................................... 18

Executive Order 13766 ........................................................................................................... 19

Executive Order 13777 ........................................................................................................... 19

Executive Order 13783 ........................................................................................................... 19

Executive Order 13807 ........................................................................................................... 20

Executive Order 13868 ........................................................................................................... 20

Executive Orders 13990, 13992, and 14008 ........................................................................... 21

Legislative Proposals ..................................................................................................................... 21

Proposals in Prior Congresses ................................................................................................. 22

Legislative Proposals in the 117th Congress ............................................................................ 22

FERC’s Policy Review .................................................................................................................. 24

Reopening the Policy Review ................................................................................................. 24

Issuance of New Policy Statements ........................................................................................ 26

Reaction and Reconsideration ................................................................................................. 26

Policy Issues for Congress............................................................................................................. 27

Figures

Figure 1. U.S. Natural Gas Transmission Pipelines ........................................................................ 3

Figure 2. U.S. Natural Gas Transmission Pipeline Mileage Additions and Expansions ................. 4

Tables

Table 1. Current Legislative Proposals Involving FERC Certification of Pipelines ..................... 22

Congressional Research Service

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Table A-1. Past Legislative Proposals to Change FERC Certification of Pipelines ...................... 29

Appendixes

Appendix. Past FERC Permit Legislative Proposals ..................................................................... 29

Contacts

Author Information........................................................................................................................ 33

Congressional Research Service

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Introduction

On February 17, 2022, the Federal Energy Regulatory Commission (FERC) issued two

statements updating its policies and procedures for the certification (permitting) of interstate

natural gas pipelines and associated natural gas infrastructure. The first statement, Certification of

New Interstate Natural Gas Facilities, established a new policy “to provide a more

comprehensive analytical framework” for how FERC would evaluate certificate applications.1

The second statement, Consideration of Greenhouse Gas Emissions in Natural Gas Infrastructure

Project Reviews, established the commission’s interim policy for evaluating the greenhouse gas

(GHG) impacts of proposed gas pipeline projects and described how FERC would “integrate

climate considerations into its public interest determinations.”2 On March 24, 2022, facing

criticism of these new policies and requests for rehearing, FERC issued an order redesignating

both policy statements as drafts and inviting additional comments.3 The commission has not

stated if or when it intends to reissue revised policy statements based on these proceedings.

The United States is the world’s largest producer of natural gas.4 Policy changes by FERC

affecting natural gas infrastructure could have significant implications related to U.S. natural gas

resource development, prices, and associated environmental and social impacts. They also could

have implications for the expansion of U.S. liquefied natural gas (LNG) exports, which have

become a priority of the Biden Administration due to Russia’s invasion of Ukraine. For these

reasons, FERC’s policies are the subject of scrutiny within Congress and among a wide range of

stakeholders.

FERC’s new policy statements were intended to supersede the commission’s 1999 Policy

Statement on Certification of New Interstate Natural Gas Pipeline Facilities—which remains in

effect.5 The 2022 policy statements and subsequent order continue the commission’s February

2021 Notice of Inquiry (NOI) process to reconsider its gas pipeline certification policies and

procedures.6 They are the latest developments in a series of legislative proposals, executive

orders, court rulings, and commission orders which address the federal regulation of gas pipeline

permitting. FERC’s inquiry process has provided both advocates and opponents of natural gas

pipeline development an opportunity to express their views about how the commission considers

such projects. The proceedings may also highlight issues of focus for future congressional

oversight and legislation.

1 Federal Energy Regulatory Commission (FERC), Certification of New Interstate Natural Gas Facilities, Docket No.

PL18-1-000, February 18, 2022, p. 38. (Hereinafter, FERC 2022 Draft Policy Statement.)

2 FERC, Consideration of Greenhouse Gas Emissions in Natural Gas Infrastructure Project Reviews, Docket No.

PL21-3-000, February 18, 2022. (Hereinafter, FERC 2022 Draft GHG Interim Policy Statement.) Although this policy

statement was issued as an interim policy subject to future revision, the commission intended to apply the policy to

pending and future environmental reviews. FERC invited public comments on the interim policy to be submitted by

April 4, 2022.

3 FERC, Order on Draft Policy Statements, Docket Nos. PL18-1-000 and PL21-3-000, March 24, 2022.

4 BP, Statistical Review of World Energy 2021, 2021, p. 36.

5 FERC, Certification of New Interstate Natural Gas Pipeline Facilities: Statement of Policy, 88 FERC ¶ 61,227,

Docket No. PL-99-3-000, September 15, 1999.

6 FERC, Certification of New Interstate Natural Gas Facilities, Notice of Inquiry, Docket No. PL18-1-000, February

18, 2021. (Hereinafter, FERC 2021 NOI.) The 2021 NOI, itself, continued a certification policy review originally

initiated in 2018. See FERC, Certification of New Interstate Natural Gas Facilities, Notice of Inquiry, Docket No.

PL18-1-000, April 19, 2018. (Hereinafter, FERC 2018 NOI.)

Congressional Research Service

1

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Development of the U.S. natural gas pipeline network has been an ongoing focus of Congress,

prompting numerous hearings and legislative proposals over the last decade. A number of related

bills have been introduced in the 117th Congress, including the FREE American Energy Act (S.

3982), the ENSURE Act (S. 3908), the Energy Freedom Act (S. 3762, H.R. 7094), the Ukraine

Assistance and American Energy Acceleration Act (H.R. 7012), the CLEAN Future Act (H.R.

1512), the Environmental Justice Mapping and Data Collection Act of 2021 (H.R. 516), the

Promoting Interagency Coordination for Review of Natural Gas Pipelines Act (H.R. 1616), the

Rebuild America Now Act (S. 1254), the Safe and Accountable Federal Energy Review for

Pipelines Act of 2021 (H.R. 2115), the SAFER Pipelines Act of 2021 (H.R. 2115), and several

bills addressing pipeline landowners’ rights.7

This report provides an overview of the federal certification process for interstate natural gas

pipelines and recent policy issues which have been the subject of debate, legislation, and

litigation. It reviews recent executive orders intended to influence federal approval of natural gas

pipeline projects. The report summarizes select legislative proposals in the 117th Congress (and

prior Congresses in the Appendix) directed at the federal review of interstate natural gas pipeline

certificate applications. It also summarizes FERC’s new policy statements for natural gas pipeline

certification and evaluation of pipeline climate impacts. The report concludes with a discussion of

policy issues for Congress.

A Growing Gas Pipeline Network

The United States’ supply of natural gas has grown substantially due to technological

advancements, such as horizontal drilling and hydraulic fracturing, which have increased

producers’ ability to extract natural gas from shale formations. Shale gas is now the dominant

source of U.S. natural gas supply.8 The continued growth in U.S. shale gas production to meet

growing demand in key consuming sectors has been driving the expansion of natural gas pipeline

infrastructure at the local level (to gather and process the gas) and at the national level to

transport natural gas from producing regions to consuming markets, typically in other states.

7 Ending Natural Gas Companies’ Seizure of Land for Export Profits Act (S. 655), Fairness for Landowners Facing

Eminent Domain Act (H.R. 2889), Landowner Fairness Act (S. 641), Landowners’ Right to Due Process in Rehearings

at FERC Act of 2021 (H.R. 4774), and a bill to amend the Natural Gas Act with respect to actions for eminent domain

by holders of certificates of public convenience and necessity, and for other purposes (H.R. 2889).

8 U.S. Energy Information Administration, Annual Energy Outlook 2021, “U.S. Dry Natural Gas Production by Type,”

February 3, 2021, https://www.eia.gov/outlooks/aeo/pdf/03%20AEO2021%20Natural%20gas.pdf.

Congressional Research Service

2

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Figure 1. U.S. Natural Gas Transmission Pipelines

Source: U.S. Energy Information Administration. “U.S. Energy Mapping System,” online maps, accessed May 19,

2022, https://www.eia.gov/state/maps.php.

Note: There are no significant natural gas transmission lines in Alaska or Hawaii.

Over 300,000 miles of high-capacity transmission pipeline already transport natural gas across

the United States (Figure 1).9 However, if long-term growth trends in U.S. shale gas production

and demand continue, the need for new pipelines could still be substantial. For example, a 2020

analysis by the INGAA Foundation, a pipeline industry research organization, concluded, “As the

impacts of COVID-19 diminish over time, the drivers of new infrastructure return.... [A]lmost 33

billion cubic feet (BCF) per day of capacity is expected to be placed into service through major

gas pipeline projects from 2020 through 2025.”10

If it were all to be constructed, this new infrastructure would amount to several thousand miles of

additional interstate pipeline and on the order of $40 billion in additional capital investment.11

Figure 2 shows annual expansions and additions to natural gas transmission pipeline mileage in

the United States since 2004. As the figure indicates, federal and state agencies have approved

significant additions to the pipeline system over these years, especially after the onset of the shale

gas expansion in 2006-2008. Pipeline construction slowed for a five-year period through 2016 as

newly added capacity absorbed new shale gas supplies, but construction increased again after

2016. Altogether, over 25,000 miles of newly constructed or expanded gas transmission pipeline

have begun service since 2004. Additional gas pipeline capacity has also become available

through conversion of pipelines carrying other commodities or flow reversal of existing natural

9 Pipeline and Hazardous Materials Safety Administration, “Annual Report Mileage for Natural Gas Transmission and

Gathering Systems,” web page, February 1, 2022, https://www.phmsa.dot.gov/data-and-statistics/pipeline/annualreport-mileage-natural-gas-transmission-gathering-systems.

10 INGAA Foundation, “North American Midstream Infrastructure—A Near Term Update Through 2025,” December

2020, p. 55. The INGAA Foundation is affiliated with the Interstate Natural Gas Association of America (INGAA), the

interstate gas pipeline industry trade association.

11 Ibid., and INGAA Foundation, “North American Midstream Infrastructure Through 2035: Significant Development

Continues,” June 18, 2018, p. 48. The mileage and capital investment values are CRS estimates based on data in the

INGAA Foundation reports.

Congressional Research Service

3

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

gas pipelines. Approximately 800 miles of pipeline have been permitted or are under construction

with startup anticipated in 2022.12 Anticipated additions fall to approximately 500 miles in 2023.

Figure 2. U.S. Natural Gas Transmission Pipeline Mileage Additions and Expansions

(Miles)

Source: Energy Information Administration (EIA), “U.S. Natural Gas Pipeline Projects,” online spreadsheet,

January 31, 2022, https://www.eia.gov/naturalgas/data.cfm#pipelines.

Notes: Excludes reversal and conversion projects as well as gathering and distribution lines. Anticipated projects

in 2022 and 2023 include approved projects and projects under construction but excludes projects “on hold.”

2022 also excludes the Mountain Valley Pipeline due to permit litigation. Includes some state-regulated

(intrastate) pipelines. EIA figures are based on the agency’s analysis of regulatory filings and industry reports.

FERC Pipeline Certification Process

Under Section 7(c) of the Natural Gas Act of 1938 (NGA), FERC is authorized to issue

certificates of “public convenience and necessity” for “the construction or extension of any

facilities ... for the transportation in interstate commerce of natural gas” (15 U.S.C. §717f(c)).

Therefore, companies seeking to build interstate natural gas pipelines must first obtain certificates

of public convenience and necessity from FERC.13 The commission’s regulatory process for the

review of certificate applications consists of several principal steps, explained below, which may

vary somewhat depending upon whether or not a pipeline developer opts to enter into a voluntary

pre-filing process before formally applying for a pipeline certificate.

Application Pre-Filing

Prior to applying to FERC for a pipeline certificate, developers may file a request to use the

commission’s pre-filing procedures (18 C.F.R. §157.21). The commission established the prefiling process to encourage the industry to engage early in project development with the relevant

public and government agencies. The expectation is that the pre-filing will improve a developer’s

12 This figure excludes the 303-mile Mountain Valley Pipeline, which is largely constructed, but may not be completed

due to permit litigation. See Maya Weber, “Mountain Valley Pipeline takes another hit in court as 4th Circuit strikes

species authorization,” S&P Global Platt’s, February 3, 2022.

13 FERC must also approve the abandonment of gas facility use and services. The commission does not have similar

siting authority over oil pipelines, nor over natural gas pipelines located entirely within a state’s borders not involved in

interstate commerce. Siting of oil and intrastate natural gas pipelines is, instead, variously regulated by the states.

Congressional Research Service

4

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

proposal and avoid problems during the review of a subsequent FERC certificate application.

However, while FERC encourages pre-filing, it is not required to apply for a pipeline certificate.

The pre-filing process involves a set of specific activities by the developer—typically studying

potential project sites, identifying stakeholders, and holding an open house to discuss the project.

Through this process, a developer notifies all stakeholders—including tribal, state, local, and

other federal agencies, and potentially affected property owners—about a proposed project so that

the developer and commission staff can provide public forums to hear stakeholder concerns. The

pipeline developer may then incorporate proposed environmental mitigation measures into the

project design, taking into account stakeholder input. Concurrent with the developer’s activities,

FERC staff participate in public forums and take steps necessary to ensure FERC compliance

with the National Environmental Policy Act (NEPA, discussed below). For example, FERC

consults with interested stakeholders, including relevant government agencies, and also holds

public scoping meetings and site visits in the proposed project area.14 At the conclusion of prefiling, the developer prepares a final application and submits it to FERC.

Certificate Application and FERC Review

Whether pre-filing or not, a pipeline developer must formally apply to FERC for a certificate of

public convenience and necessity. Among other requirements, the application must contain a

description of the proposed pipeline, route maps, construction plans, schedules, and a list of other

statutory and regulatory requirements, such as permits needed from other agencies. The

application must also include environmental reports analyzing route alternatives—to avoid or

minimize environmental damage—and studies of potential environmental impacts (on water,

plants, and wildlife), cultural resources, socioeconomics, soils, geology, aesthetic resources, and

land use.15 Upon receiving an application, the commission issues a public Notice of Application

in the Federal Register and begins the application review process.

Any person seeking to become a party to FERC’s proceeding must file a motion to intervene

pursuant to the commission’s rules (18 C.F.R. §385.214). Intervenors receive the certificate

applicant’s filings and other FERC documents related to the case, as well as materials filed by

other interested parties.16 Only intervenors have the right to file briefs, attend hearings, and appeal

the commission’s decision regarding the certificate. They may also challenge final commission

actions in the U.S. Circuit Courts of Appeals.

FERC exercises its NGA Section 7(c) pipeline certification authority in accordance with its own

regulations and the guidance of its certification policy. The 2022 draft policy statement lays out

how FERC will “determine whether a proposed natural gas project ‘is or will be required by the

present or future public convenience and necessity,’ as that standard is established in section 7.”17

The draft policy statement “does not establish binding rules,” but is intended to “provide clarity

on how the Commission will evaluate all factors bearing on the public interest, including the

14 For a flowchart of steps taken by both FERC and certificate applicants, see FERC, “EIS Pre-Filing Environmental

Review Process,” web page, June 25, 2020, https://www.ferc.gov/resources/processes/flow/process-eis.

15 During the review process, FERC, or any intervenor or public commenter, may suggest additional siting alternatives

and modifications to reduce impacts on buildings, fences, crops, water supplies, soil, vegetation, wildlife, air quality,

noise, safety, landowner interests, etc. Commission staff also consider whether a proposed pipeline can be placed near

or within the right-of-way of an existing pipeline, power line, highway, or railroad. See FERC, An Interstate Natural

Gas Facility on My Land?, August 2015, p. 8.

16 Intervenors are also obligated to mail copies of their own filings to all other parties to the proceeding.

17 FERC 2022 Draft Policy Statement, p. 1.

Congressional Research Service

5

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

balancing of economic and environmental interests.”18 Economic factors may include precedent

agreements with shippers for new pipeline capacity, how the gas will ultimately be used, expected

pipeline utilization rate, projections of natural gas market growth, and projections of the net

benefits to consumers, such as lower natural gas prices due to increased supply competition,

among other factors.19 Consideration of potential adverse factors includes examining impacts to

the certificate applicant’s existing customers (e.g., subsidization), the interests of existing

pipelines (and their captive customers), environmental impacts, and the interests of landowners

and surrounding communities (including environmental justice communities, discussed in later

section).20 FERC may also take into account certain safety issues, but generally defers to the

Department of Transportation, which regulates pipeline safety.21 Of the factors above,

environmental review typically comprised the bulk of FERC’s certificate application review

under its 1999 policy statement, and may continue to do so under the 2022 draft certificate policy,

especially in light of FERC’s 2022 draft interim GHG policy.

Environmental Review Under NEPA

Before FERC can issue a final decision on an application, the agency must identify and consider

the environmental impacts of the proposed project in accordance with NEPA (42 U.S.C. §4321 et

seq.). NEPA requires federal agencies to “take a hard look at environmental consequences” of

their proposed actions (e.g., granting a certificate), consider alternatives, and publicly disseminate

such information before taking final action.22 Although an agency must consider these impacts, it

need not elevate these environmental concerns above others. Under NEPA, federal agencies must

prepare an environmental impact statement (EIS) for federal actions “significantly affecting the

quality of the human environment.”23

NEPA also established the Council on Environmental Quality (CEQ), which issues regulations

and guidance detailing how federal agencies must implement NEPA.24 CEQ’s guidance has

included, for example, guidance on consideration of greenhouse gas emissions and the effects of

climate change (discussed below). In its regulations, CEQ has directed each federal agency to

adopt and supplement the CEQ regulations as necessary to include procedures relevant to that

agency’s authority and ensure that the procedures implementing NEPA are integrated into the

agency’s broader decisionmaking process. Accordingly, FERC has promulgated its own

regulations implementing NEPA at 18 C.F.R. §380.

The CEQ regulations focus primarily on requirements applicable to the preparation of an EIS, but

recognize that documenting compliance with NEPA may involve other procedures. If an agency is

uncertain whether a proposal would have significant impacts, it may prepare an environmental

18 FERC 2022 Draft Policy Statement, pp. 2, 38.

19 Ibid., pp. 41-42.

20

Ibid., p. 45.

21 Pipeline safety regulations are covered in Title 49 of the Code of Federal Regulations. In granting pipeline

certificates, FERC requires that developers comply with Department of Transportation (DOT) pipeline safety standards

for design, construction, operation, and maintenance.

22 Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350 (1989).

23 NEPA §102(2)(C); 42 U.S.C. §4332(2)(C). Of note, federal actions subject to NEPA are defined to include actions

that require federal agency approvals via a permit or other regulatory approval (40 C.F.R. §1508.18). For more NEPA

information, see CRS Report RL33152, The National Environmental Policy Act (NEPA): Background and

Implementation, by Linda Luther.

24 Council on Environmental Quality, “Regulations for Implementing the Procedural Provisions of the National

Environmental Policy Act,” in 40 C.F.R. Parts 1500-1508 (43 Federal Register 55990, November 28, 1978).

Congressional Research Service

6

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

assessment (EA) to determine if an EIS is necessary or a finding of no significant impact

(FONSI) may be issued. Also, each federal agency is required to identify categories of actions

they are authorized to undertake that have been found to have no significant effect on the

environment. Such actions are categorically excluded from the need to prepare an EIS or EA and

are, hence, broadly referred to as “categorical exclusions” (CEs or CATEXs).25

CEQ requires agencies to determine whether a proposal has significant impacts by identifying

and analyzing its direct, indirect, and cumulative effects, defined as follows:

Direct effects—caused by the project that occur at the same time and place;26

Indirect effects—caused by the action that are later in time or farther removed in

distance but still reasonably foreseeable;27 and

Cumulative effects—those that result from the incremental impacts of the action

when added to other past, present, or reasonably foreseeable future actions

regardless of what agency (federal or nonfederal) or person undertakes that other

action.28

The Energy Policy Act of 2005 (P.L. 109-58, EPAct) designates FERC as the “lead agency” for

coordinating NEPA compliance and “all applicable Federal authorizations” in reviewing pipeline

certificate applications (§313(b)). As the lead agency, FERC is required to obtain input from other

“cooperating” agencies with statutory jurisdiction or special expertise regarding any

environmental impact associated with the project (40 C.F.R. §1508.5). Cooperating agencies for a

pipeline project often include the Environmental Protection Agency; the Department of

Transportation’s Pipeline and Hazardous Materials Safety Administration; the Department of the

Interior’s Bureau of Land Management (BLM), Fish and Wildlife Service, and National Park

Service; and the U.S. Army Corps of Engineers (the Corps), among others.

After FERC staff complete their environmental analysis and cooperating agency consultations,

the commission issues a draft EIS with initial recommendations for approval or denial of the

certificate. Issuance of the draft EIS also begins a public comment period of at least 45 days,

during which FERC is to hold public meetings in the proposed project area.29 After the conclusion

of the comment period, FERC reviews the comments and revises its draft EIS in response. FERC

then issues a final EIS with final recommendations for approval or denial of the certificate. Under

NEPA, a record of decision—in this context a FERC order—cannot be issued until at least 30

days after FERC publishes a notice of availability of the final EIS (40 C.F.R. §1506.10(b)(2)).

However, there is no additional opportunity for public comment. When the 30-day period is over,

the commission may issue an order approving or denying the certificate.

Certificate Authorities

If FERC grants a pipeline certificate, the commission’s order states the terms and conditions of

the approval, including the authorized pipeline route and any construction or environmental

25 Each agency’s regulations implementing NEPA are required to provide for “extraordinary circumstances” in which a

normally excluded action may have significant environmental effect (40 C.F.R. §1508.4).

26 40 C.F.R. §1508.8(a).

27 40 C.F.R. §1508.8(b). In the definition of effects (at 40 C.F.R. §1508), it is noted that the words effects and impacts

are synonymous, as they are used in the CEQ regulations.

28 40 C.F.R. §1508.7.

29 FERC usually establishes a 45-day comment period, the minimum required under 40 C.F.R. §1506.10(c). In some

cases involving very large projects or complex environmental issues, FERC has established longer periods.

Congressional Research Service

7

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

mitigation measures required for the project. For example, a construction condition might require

that the pipeline be buried at a specific depth under a particular river crossing, or that construction

be limited during a certain time of year to avoid impacts on wildlife. A FERC certificate confers

on the developer the authority to exercise the government’s eminent domain authority if certain

conditions are met (15 U.S.C. §717f(h)). Also, federal law preempts any state or local law that

duplicates or obstructs that federal law (e.g., siting or zoning) relevant to the project.30 In this

way, a FERC certificate provides a developer with the authority to secure the necessary rights-ofway to lay the pipeline if the developer cannot secure them from landowners through negotiation.

Although a FERC certificate authorizes a pipeline under the Natural Gas Act, it does not preempt

other federal laws that also may apply—such as the Endangered Species Act or the National

Historic Preservation Act. Any requirements under other federal statutes must still be met. These

requirements may include, for example, securing federal authorizations for water crossings from

the Corps, permission to cross federal lands from the BLM, and other federal approvals.31

Pipeline developers also may need to secure approvals from state agencies under delegated

federal authorities, such as Section 401 water quality certifications under the Clean Water Act (33

C.F.R. §330.4). A developer must secure all these approvals before proceeding with construction.

Post-Certificate Proceedings

Once FERC issues an order granting or denying a pipeline certificate, parties to the proceeding

(e.g., the developer or intervenors) who object to the order for any reason may formally request a

rehearing so that the commission can reconsider its decision. A party to the proceeding must file a

request for rehearing within 30 days after issuance of the final order—a statutory deadline which

the commission cannot waive or extend (15 U.S.C. §717(r)). Upon receiving a rehearing request,

FERC has 30 days to rule on it or the request is deemed denied, in either case allowing a party

involved to appeal FERC’s ruling in federal court.32 The commission, by its own order, may not

authorize pipeline construction to proceed until the earlier of either the date that a qualifying

rehearing request is no longer pending before the Commission or 90 days after the date that a

qualifying rehearing request may be deemed denied.33 If a pipeline certificate is approved after

rehearing, the pipeline project may proceed even if additional court challenges have been filed.

Once the developer has provided FERC with any outstanding information or taken other actions

to satisfy the terms and conditions of the certificate order FERC can issue a Notice to Proceed

with Construction Activities and construction can begin. The pipeline developer must then file

weekly status reports with the commission documenting project inspection and certificate

compliance until construction is completed.

30 FERC addresses the input of Indian tribes in its NEPA documents and orders in accordance with its policy statement,

Policy Statement on Consultation with Indian Tribes in Commission Proceedings, which was amended in 2019. FERC,

“Revision to Policy Statement on Consultation with Indian Tribes in Commission Proceedings,” Docket No. PL20-1000, Order No. 863, October 17, 2019.

31 For details about Corps approvals, see CRS Report R44880, Oil and Natural Gas Pipelines: Role of the U.S. Army

Corps of Engineers, by Nicole T. Carter et al.

32 This 30-day deadline was affirmed in a June 30, 2020, judgment by the United States Court of Appeals for the

District of Columbia Circuit in a case which challenged FERC’s prior use of “tolling” orders to delay ruling on the

merits of certificate rehearing requests. Allegheny Defense Project v. FERC, 964 F. 3d 1 (D.C. Circuit Court of

Appeals, 2020).

33 171 FERC ¶ 61,201 and 175 FERC ¶ 61,098. The limit on construction authorization applies “only when a request

for rehearing raises issues reflecting opposition to project construction, operation, or need.”

Congressional Research Service

8

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Gas Pipeline Siting Challenges

Over the last decade, proposals for new interstate natural gas pipelines have become increasingly

controversial. Many certificate applications have been subjected to heavy public scrutiny, and

some have faced significant delays in review, in some cases due to protracted litigation. A May

2018 report by the Department of Energy Inspector General stated that “nothing came to our

attention to indicate that FERC had not generally performed the natural gas certification process

in accordance with applicable laws, regulations, policies, and procedures.”34 Nonetheless, aspects

of FERC’s permitting practices remain a focus of attention among policymakers because they

have been the subject of FERC dissent, debate in Congress, or litigation in federal court.

Identifying Indirect Environmental Impacts

As noted above, FERC is obligated under NEPA to consider the direct and indirect environmental

impacts of certificate proposals. Direct effects often are relatively easy to identify. In the context

of a pipeline project, a direct effect would be associated with the pipeline itself, such as forest

impacts from clearing rights-of-way, or water quality impacts from construction across waterways

and wetlands. However, identifying the indirect effects of a proposed gas pipeline has presented

challenges and, in some cases, has been controversial. Some stakeholders assert that the indirect

“upstream” impacts of a proposed pipeline should include impacts associated with the production

of natural gas, such as fugitive methane emissions from gas wells and gas gathering pipelines.

They also assert that the indirect “downstream” impacts should include the environmental effects

of using natural gas, such as carbon dioxide emissions from natural gas combustion.35

In the past, FERC limited its review of certain upstream or downstream impacts, claiming that

they were not reasonably foreseeable. However, in February 2017, a FERC commissioner argued

that FERC should analyze the upstream environmental effects of increased natural gas production

and should be “open to analyzing the downstream impacts of the use of natural gas.”36 In a related

legal challenge to a pipeline (Sabal Trail) in Florida for which the effects of natural gas use could

be identified, the court ruled that FERC must “either quantify and consider the project’s

downstream carbon emissions or explain in more detail why it cannot do so.”37

In FERC’s 2018 order responding to the Sabal Trail ruling, the majority of commissioners

concluded that, although its supplemental EIS quantified downstream greenhouse gas emissions

associated with the pipeline, there was “no way to determine the significance” of those

emissions.38 However, two commissioners raised objections to the majority’s conclusion, arguing

that the significance of the downstream greenhouse gas emissions could—and should—be

quantified.39 In an unrelated FERC order involving a pipeline in New York, the majority stated

34 U.S. Department of Energy, Office of Inspector General, The Federal Energy Regulatory Commission’s Natural Gas

Certification Process, Audit Report, DOE-OIG-18-33, May 2018, p. 1. The report did identify four areas for

improvement: process transparency, public access to FERC records, tracking stakeholder comments, and data integrity.

35 See, for example, Sierra Club, “FERC Further Abdicates Its Obligations in Favor of More Pollution,” press release,

May 18, 2018.

36 FERC, Order Granting Abandonment and Issuing Certificates, 158 FERC ¶ 61,145, Docket Nos. CP15-115-000 and

CP-15-115-001, Commissioner Bay, Separate Statement, February 3, 2017, p. 5.

37 Sierra Club, et al. vs. FERC, 857 F.3d 1357, 1375 (D.C. Cir. 2017).

38 FERC, Order on Remand Reinstating Certificate and Abandonment Authorization, 162 FERC ¶ 61,233, Docket Nos.

CP14-554-002, CP15-16-003, and CP15-17-002, March 14, 2018, p. 25.

39 Ibid., “LaFLEUR, Commissioner, dissenting in part,” p. 2, and “GLICK, Commissioner, dissenting,” p. 5.

Congressional Research Service

9

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

that they were “unable to find based on the record that the potential increase in greenhouse gas

emissions associated with production, non-project transport, and non-project combustion are

causally related” to the commission’s certification of the project, and that “providing a broad

analysis based on generalized assumptions rather than reasonably specific information does not

meaningfully inform the Commission’s project-specific review.”40 The two commissioners

dissented from this conclusion as well, one arguing that “the mere fact that the record does not

contain specific information regarding the greenhouse gas emissions associated with increased

production or consumption from a particular natural gas pipeline cannot excuse the Commission

from considering those effects under NEPA.”41

Litigation related to FERC’s environmental reviews has continued—along with disagreement

among commissioners about the proper scope of environmental impacts for pipelines under

FERC’s jurisdiction. For example, in a 2019 legal challenge involving FERC’s approval of a new

natural gas pipeline compressor station, while upholding FERC’s approval, the court nonetheless

was critical of FERC’s examination of both upstream and downstream greenhouse gas emissions

associated with the project.42 In a 2020 FERC order approving another gas pipeline project,

concurring and dissenting opinions by two commissioners, respectively, expanded upon their

prior support for, or rejection of, FERC’s treatment of greenhouse gas emissions in environmental

reviews.43 In March 2021, FERC announced that it had “for the first time assessed the

significance of a proposed natural gas pipeline project’s greenhouse gas emissions and their

contribution to climate change.”44 The associated certificate order (approving Northern Natural

Gas Company pipeline facilities) states

In previous orders, the Commission has concluded that it was unable to assess the

significance of a project’s greenhouse gas (GHG) emissions or those emissions’

contribution to climate change. Upon reconsideration, we no longer believe that to be the

case. Accordingly ... we assess the significance of the project’s GHG emissions and their

contribution to climate change. Based on the record in this proceeding, we conclude that

those impacts are not significant.45

However, adopting this approach was not unanimous. While concurring with the approval of the

pipeline project, two commissioners dissented (in part) with respect to the greenhouse gas

assessment on legal grounds or because they believed that FERC’s change in approach was

premature.46

FERC’s 2022 draft GHG interim policy establishes an approach to GHG emissions along the

lines of its order in the Northern Natural Gas Company application. The draft GHG policy states

that the commission

will quantify a project’s GHG emissions that are reasonably foreseeable and have a

reasonably close causal relationship to the proposed action, including those effects that

occur at the same time and place as the proposed action and effects that are later in time or

farther removed in distance from the proposed action. This will include GHG emissions

40 FERC, Order Denying Rehearing, Docket No. CP14-497-001, 163 FERC ¶ 61,128, May 18, 2018.

41 Ibid., “GLICK, Commissioner, dissenting in part,” p. 7.

42 Birckhead vs. FERC, 925 F. 3d 510 (D.C. Cir. 2019).

43 172 FERC ¶ 61,039.

44 FERC, “FERC Reaches Compromise on Greenhouse Gas Significance,” press release, March 18, 2021.

45 174 FERC ¶ 61,189, p. 11.

46 Ibid.

Congressional Research Service

10

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

resulting from construction and operation of the project as well as, in most cases, GHG

emissions resulting from the downstream combustion of transported gas.47

Furthermore, the draft GHG interim policy establishes a specific numerical threshold to

determine the significance of GHG emissions for the purpose of establishing the appropriate level

of environmental review under NEPA. According to commission staff, FERC “will presume,

unless refuted by record evidence, that projects with estimated greenhouse gas emissions of

100,000 metric tons per year of carbon dioxide equivalent will have a significant impact on the

environment.”48 Presuming that a proposed pipeline project would have a “significant”

environmental impact would necessitate the completion of an EIS (rather than a less extensive

EA) for environmental review under NEPA. The draft policy also encourages pipeline developers

to propose measures to mitigate the upstream or downstream GHG emissions associated with

their projects that the commission could evaluate on a case-by-case basis in making permit

decisions. As it does for other types of permit conditions which the commission may impose

under the NGA, FERC states that it may condition a pipeline permit approval on further

mitigation of GHG impacts.49

Evaluating Project Need

FERC’s review of a certificate application requires the commission to evaluate the public benefit

from the proposed project. Benefits the commission may consider include meeting unserved

demand, eliminating pipeline bottlenecks, accessing new gas supplies, lowering consumer costs,

providing greater reliability, and increasing competition, among others. The principal component

of this evaluation historically has been demonstrated market need for the pipeline in the form of

contracts with future customers for its capacity. According to FERC’s 1999 policy statement,

a new pipeline project must show market support through contractual commitments for at

least 25 percent of the capacity for the application to be processed by the Commission. An

applicant showing 10-year firm commitments for all of its capacity, and/or that revenues

will exceed costs is eligible to receive a traditional certificate of public convenience and

necessity.50

Some stakeholders have questioned FERC’s reliance on contracts from future customers (known

as “precedent agreements”) to prove market need, particularly when those contracts involve

companies affiliated with the pipeline developer. The commission considered this concern in

1999 but established no special provisions for developer affiliates. FERC “gives equal weight to

contracts between an applicant and its affiliates and an applicant and unrelated third parties and

does not look behind the contracts to determine whether the customer commitments represent

genuine growth in market demand.”51 Nonetheless, in January 2018 one FERC commissioner

dissented from the approval of a certificate because over three-quarters of the pipeline’s capacity

under precedent agreements was associated with affiliates, and was therefore “insufficient to

carry the developer’s burden to show that the pipeline is needed.”52

47 FERC 2022 Draft GHG Interim Policy Statement, pp. 20-21.

48 FERC, “Staff Presentation | Consideration of Greenhouse Gas Emissions in Natural Gas Infrastructure Project

Reviews,” February 17, 2022, https://www.ferc.gov/news-events/news/staff-presentation-consideration-greenhousegas-emissions-natural-gas.

49 Ibid.

50 88 FERC ¶ 61,227, p. 14.

51 88 FERC ¶ 61,227, p. 15.

52 FERC, “Statement of Commissioner Richard Glick on the PennEast Project,” Docket No. CP15-558-000, January 19,

Congressional Research Service

11

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

In remarks at a February 13, 2018, meeting of state utility regulators, the FERC chairman stated

that the commission would “have to take a look at” whether recent precedent agreements, and

particularly affiliate agreements, represent “valid, arm’s length” demonstrations of pipeline

capacity demand.53 However, an April 2020 order denying a request for certificate rehearing

reaffirmed the commission’s reliance upon precedent agreements, asserting that such agreements

“are significant evidence of demand for a project,” and that FERC is not required to assess project

benefits “by looking beyond the market need reflected by the applicant’s precedent agreements

with shippers.”54

Also related to the issue of market need, some stakeholders have objected to FERC’s project-byproject approach to evaluating applications—especially for multiple pipelines proposed in one

region.55 Some in Congress have called on FERC to adopt a more overarching approach to

pipeline development, collectively considering existing capacity and multiple projects together

rather evaluating them independently.56 However, FERC asserted in 2015 that it “does not engage

in regional planning exercises that would result in the selection of one project over another.”57

Nonetheless, in October 2017, one FERC commissioner dissented from the approval of two

pipelines through Virginia on the grounds that both projects might not be needed due to

geographic proximity.58

FERC’s 2022 draft policy would reaffirm the importance of precedent agreements in application

review, but would expand the scope of what FERC would consider in evaluating project need.

According to the 2022 draft policy statement, “although precedent agreements remain important

evidence of need, ... the existence of precedent agreements may not be sufficient in and of

themselves to establish need for the project.”59 With respect to affiliate agreements, specifically,

the policy states that “projects supported by precedent agreements with affiliates raise unique

concerns regarding need for the project... [and] will generally be insufficient to demonstrate

need.”60 Under its new policy, in addition to precedent agreements, the commission would

consider “the circumstances surrounding the precedent agreements, as well as other evidence of

need, including demand projections underlying the capacity subscribed, estimated capacity

utilization rates, potential cost savings to customers, regional assessments, and statements from

state regulatory commissions or local distribution companies.”61

2018, https://www.ferc.gov/media/statements-speeches/glick/2018/01-19-18-glick.pdf.

53 Kevin McIntyre, FERC Chairman, remarks before the National Association of Regulatory Utility Commissioners,

February 13, 2018, https://www.facebook.com/NARUCToday/videos/2025186407497968/?rc=p.

54 171 FERC ¶ 61,049, pp. 5-6.

55 FERC, Roanoke County’s Motion to Intervene and Identification of Issues, Docket Nos. CP16-10-000 and CP16-13000, November 24, 2015, p. 6.

56 See, for example, U.S. Representative Bonnie Watson Coleman, “Watson Coleman, Malinowski Introduce Bill to

Ensure Full Reviews of Proposed Pipelines,” press release, March 31, 2021; and Duncan Adams, “Senators Hope to

Compel FERC to Broaden Analysis of Pipeline Projects,” The Roanoke Times, February 4, 2016.

57 Tamara Young-Allen, FERC, as quoted in “Feds Reject Consolidated Review of Pipeline Projects,” Associated

Press, December 10, 2015.

58 FERC, “Statement of Commissioner Cheryl A. LaFleur on Order Issuing Certificates and Granting Abandonment

Authority,” Docket No. CP16-10-000, October 13, 2017, https://www.ferc.gov/media/statements-speeches/lafleur/

2017/10-13-17-lafleur.pdf.

59 FERC 2022 Draft Policy Statement, p. 41.

60 Ibid., pp. 43-44.

61 FERC, “Fact Sheet | Updated Pipeline Certificate Policy Statement (PL18-1-000),” February 17, 2022.

Congressional Research Service

12

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

The commission also would “look for information about the intended end use of gas to help

explain why a project is needed.”62 Although FERC’s 2022 draft policy does not call for

commission-driven regional planning for pipeline capacity, it calls for the commission to evaluate

whether “other suppliers,” presumably including other existing or proposed pipelines, “would be

able to meet some or all of the needs to be served by the proposed project on a timely,

competitive basis or whether other factors may eliminate or curtail such needs.”63

Timing and Relations with Other Agencies

There are no statutory time limits within which FERC must complete its own certificate review

process or issue an order. However, EPAct authorizes FERC to establish a schedule for all federal

authorizations and creates a cause of action “if a Federal or State administrative agency” fails to

comply with that schedule (§313(b)). As discussed above, natural gas pipelines typically require

permits from federal and state agencies in addition to FERC. Since 2002, FERC and nine other

federal agencies have operated under an interagency agreement on early coordination required for

review of interstate natural gas pipeline certificate applications.64 Under this agreement, when

FERC receives a certificate application, the agencies commit to early involvement, proactive

participation, sharing of data, informal communication, and resolving disputes. FERC has

promulgated regulations under the EPAct authority requiring certificate-related final decisions

from federal agencies or state agencies (acting under delegated federal authority) no later than 90

days after the commission issues its final environmental document, unless another schedule is

established by federal law (18 C.F.R. §157.22).

Congress included the schedule provisions in EPAct to address concerns that some interstate gas

pipeline approvals were being unduly delayed by a lack of coordination or insufficient action

among agencies involved in the certification process.65 Notwithstanding the directives above,

pipeline developers have long asserted that cooperating federal agencies have not always

coordinated effectively with FERC in its review of certificate applications and have not always

complied with FERC’s deadlines.66 For example, a 2012 study by the INGAA Foundation

concluded that, despite the schedule provisions in EPAct intended to expedite the review of FERC

certificate applications for gas pipelines, “the time required to secure regulatory approvals for

such projects is increasing.”67 Likewise, some in Congress have argued that gas pipeline reviews

have been “delayed unnecessarily due to a lack of coordination or insufficient action among

agencies involved.”68 Subsequent debate in congressional hearings about the timing of FERC’s

62 Ibid.

63 Ibid., p. 43.

64 FERC et al., “Interagency Agreement on Early Coordination of Required Environmental and Historic Preservation

Reviews Conducted in Conjunction with the Issuance of Authorizations to Construct and Operate Interstate Natural

Gas Pipelines Certificated by the Federal Energy Regulatory Commission,” May 2002; See also 42 U.S.C. §15928(b).

65 Senate Committee on Environment and Public Works, Oversight Hearing to Review the Permitting of Energy

Projects, S. Hrg. 109-856, May 25, 2005.

66 See, for example, Interstate Natural Gas Association of America, “INGAA Comments on United States Army Corps

of Engineers; Subgroup of the Department of Defense Regulatory Reform Task Force, Review of Existing Rules,” 82

Fed. Reg. 33,470 (July 20, 2017); Docket ID No. COE-2017-0004,” October 18, 2017, p. 3, http://www.ingaa.org/

File.aspx?id=33450.

67 INGAA Foundation, Expedited Federal Authorization of Interstate Natural Gas Pipelines: Are Agencies Complying

with EPAct?, Washington, DC, December 21, 2012, p. 2.

68 House Committee on Energy and Commerce, Subcommittee on Energy, majority staff memorandum RE: Hearing

entitled “Legislation Addressing Pipeline and Hydropower Infrastructure Modernization,” May 1, 2017, p. 3,

http://docs.house.gov/meetings/IF/IF03/20170503/105916/HHRG-115-IF03-20170503-SD020.pdf.

Congressional Research Service

13

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

certificate reviews indicated both criticism of and support for FERC’s process.69 The length of

permit review, and project delays due to challenges to FERC reviews, remain a key interest

among developers and in Congress.70

FERC staff have stated in the past that the commission seeks to complete review of certificate

applications within 18 to 24 months of filing.71 However, there has been disagreement, even

among FERC commissioners, as to the extent FERC is meeting this standard. For example, in

September 2021, the FERC chairman testified that the time the commission was taking to

approve certificate applications was comparable to that in previous years.72 By contrast, in

November 2021, another FERC commissioner argued that FERC’s average time to review

pipeline certificate applications was significantly longer than it was from 2011 through 2020

based on the commissioner’s own analysis of NGA Section 7 applications.73

Whether FERC’s record of certificate application review demonstrates process efficiency is open

to debate. Pipeline projects are complex and unique, each with its own potentially complicating

factors. Moreover, attempting to compare FERC’s recent certificate review timing to historical

timing is complicated by the lack of a quorum of FERC commissioners (required for certificate

decisions) for six months in 2017 and the impacts of the COVID-19 pandemic on FERC’s

staffing and administrative functions beginning in 2020. Permit application review may also

include time taken by developers responding to questions or providing supplemental information

or analysis requested by regulators, which may be outside the control of the commission.

Changes in the Domestic Gas Industry Structure

Over the last 20 years, there have been fundamental changes in the structure of the U.S. natural

gas sector. Most significant among these are widespread use of hydraulic fracturing, new gas

production regions (e.g., the Marcellus formation underlying parts of Pennsylvania and other

states), increasingly interconnected natural gas infrastructure in more populated areas, and greater

dependence on natural gas to fuel power plants. These changes, in turn, have introduced new

considerations in pipeline permit review, including new concerns about greenhouse gas

emissions, potential groundwater and seismic risks, pipeline safety, energy infrastructure security,

and changing contractual relationships with pipeline customers. For example, with the shift away

from coal to natural gas for power generation, regulators and operators have expressed concerns

about the potential linkage between the availability of natural gas and the reliability of electricity

supply in markets with constrained infrastructure.74 This linkage was demonstrated in the

February 2021 Texas blackout which happened, in part, because freezing temperatures disrupted

69 See, for example, debate in the House Energy and Commerce Committee, Energy Subcommittee hearing on

Oversight of the Federal Energy Regulatory Commission and the FY2019 Budget, April 17, 2018.

70

Sen. John Barrasso, letter to FERC Chairman Richard Glick and Commissioners, December 15, 2021,

https://www.energy.senate.gov/services/files/E83D94D6-377A-42DD-BA1E-41CAF62B5310; Sen. John Hoeven et

al., letter to the Honorable Richard Glick, Chairman, et al., FERC, April 29, 2021. “The Commission’s Policy

Statement is critical to the advancement of important natural gas infrastructure projects.”

71 FERC, Office of Congressional Affairs, personal communication, May 30, 2018.

72 Richard Glick, FERC Chairman, testimony before the Senate Committee on Energy and Natural Resources hearing

to Review Administration of Laws Within FERC’s Jurisdiction, September 28, 2021.

73 James Danly, FERC Commissioner, letter to Sen. John Barrasso, November 29, 2021, https://www.ferc.gov/media/

commissioner-danly-letter-responding-senator-barrasso-regarding-docket-nos-cp20-27-et-al.

74 North American Electric Reliability Corporation (NERC), Special Reliability Assessment: Potential Bulk Power

System Impacts Due to Severe Disruptions on the Natural Gas System, November 2017.

Congressional Research Service

14

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

natural gas supplies to gas-fired power plants.75 Some stakeholders have asserted that FERC

should change or expand the nature of its certificate reviews to better account for such

considerations.76

Natural Gas Infrastructure for Export

The rapid growth in U.S. natural gas production has led to increased exports of pipeline gas to

Canada and Mexico and of LNG to overseas buyers. Some communities affected by pipeline

development have questioned whether FERC appropriately applies the “public convenience and

necessity” standard under the Natural Gas Act to pipeline projects which would serve export

markets.77 FERC has asserted that considerations regarding the domestic versus foreign

destination of natural gas are solely under the jurisdiction of the Department of Energy, which has

statutory authority to approve the export of the natural gas commodity. 78 Nonetheless, some

analysts have questioned whether FERC may evaluate pipelines proposed to facilitate natural gas

exports differently from those proposed to supply domestic markets.79

In litigation involving a pipeline project proposed partly for exports, a September 2019 court

decision remanded to FERC “for further explanation of why ... it is lawful to credit precedent

agreements with foreign shippers serving foreign customers toward a finding that an interstate

pipeline is required by the public convenience and necessity.”80 In its response to the court, the

commission provided additional justification for using export precedent agreements as

appropriate evidence of market demand.81 However, some legal analysts have questioned FERC’s

certification of infrastructure developed partly or primarily to serve export markets.82

Russia’s invasion of Ukraine has complicated such considerations by focusing attention on

geopolitical aspects of natural gas supply, which Russia has exploited for strategic and economic

advantage in Europe.83 Russia’s manipulation of pipeline gas deliveries has prompted European

countries to urgently seek alternative natural gas supplies from LNG exporters, especially in the

United States. In support of these efforts, on March 25, 2022, President Biden announced an

initiative to increase U.S. LNG exports to the European Union market.84 To expand European

LNG trade, developers in the United States may proceed with plans to construct new LNG export

75 FERC, The February 2021 Cold Weather Outages in Texas and the South Central United States, FERC, NERC and

Regional Entity Staff Report, November 2021.

76 See, for example, American Public Power Association, “APPA Urges FERC To Ensure Reliable And Affordable

Supply Of Natural Gas,” May 11, 2022, https://www.publicpower.org/periodical/article/appa-urges-ferc-ensurereliable-and-affordable-supply-natural-gas.

77 John Dizard, “Trump’s Plan for Energy Dominance Meets Resistance,” Financial Times, February 24, 2018.

78 158 FERC ¶ 61,145, p. 10.

79 L.M. Sixel, “FERC May Rethink Pipeline Permits When LNG Is Headed Overseas,” Houston Chronicle, updated

February 19, 2018, https://www.chron.com/business/energy/article/FERC-may-rethink-pipeline-permits-when-LNG-is12619700.php.

80 City of Oberlin v. FERC, 937 F. 3d (D.C. Cir. 2019).

81 172 FERC ¶ 61,199, pp. 7-13.

82 See, for example, Alexandra B. Klass, “The Public Use Clause in an Age of U.S. Natural Gas Exports,” Stanford

Law Review Online, April 15, 2020.

83 See, for example, Emily Rauhala et al., “E.U. Accuses Russia of ‘Blackmail’ After Gas Cut to Poland, Bulgaria,”

Washington Post, April 27, 2022.

84 The White House, “FACT SHEET: United States and European Commission Announce Task Force to Reduce

Europe’s Dependence on Russian Fossil Fuels,” March 25, 2022.

Congressional Research Service

15

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

infrastructure which has already been permitted by FERC and other agencies.85 Natural gas

pipeline companies, in turn, are pursuing plans to expand domestic pipeline capacity to supply

new LNG export terminals and existing terminal expansions.86 How FERC’s pipeline certification

policies should account for geopolitical considerations arising from military conflict in Europe,

and how they should be balanced against domestic policy considerations, are evolving topics

within and outside the commission. How FERC incorporates these issues in its pipeline policy

decisions may present new challenges for stakeholders.

Environmental Justice87

Environmental justice, which involves concerns of disproportionate risks to health and safety

across communities with differing demographics (e.g., race, national origin, or income), has

become an important factor in natural gas pipeline siting.88 For example, the siting of a natural

gas compressor station for the proposed Atlantic Coast Pipeline in Union Hill, VA—a

predominately African-American community—became the subject of litigation on environmental

justice grounds.89 Since 1997, the Council on Environmental Quality has provided guidance for

taking into account environmental justice in NEPA reviews.90 In 2020, FERC officials reportedly

stated that the commission “takes environmental justice concerns very seriously,” and that the

agency’s environmental reviews properly analyze “socioeconomic issues such as environmental

justice.”91 Nonetheless, some on the commission and other stakeholders have criticized FERC’s

consideration of environmental justice issues in its pipeline certification process.92 In February

2021, the FERC chairman announced plans to create a new senior-level staff position “charged

with working with the experts in all FERC program offices to integrate environmental justice and

equity matters into Commission decisions.”93 In May 2021, the FERC chairman announced the

appointment of a Senior Counsel for Environmental Justice and Equity “to work in building a

culture and program that ensures FERC appropriately integrates environmental justice and equity

issues into our decisionmaking.”94

85 Marcy de Luna, “Rising Calls for U.S. LNG Revive Stalled Export Projects, but at Higher Costs,” Reuters, April 21,

2022.

86 Kelsey Hallahan, “Midstream Eyes Adding Haynesville, Gulf Coast Gas Delivery Capacity on Bright LNG Demand

Prospects,” S&P Global Commodity Insights, May 19, 2022.

87 For further discussion, see CRS Legal Sidebar LSB10590, Addressing Environmental Justice Through NEPA, by

Nina M. Hart and Linda Tsang.

88 For further discussion of the concept of environmental justice, see CRS In Focus IF10529, Role of the U.S.

Environmental Protection Agency in Environmental Justice, by David M. Bearden and Angela C. Jones.

89 Friends of Buckingham v. State Air Pollution Control Board, 19-1152 (U.S. Court of Appeals, 4th Cir. 2020).

90 Council on Environmental Quality, Environmental Justice Guidance Under the National Environmental Policy Act,

December 10, 1997. This guidance was issued consistent with Executive Order 12898, “Federal Actions to Address

Environmental Justice in Minority Populations and Low-Income Populations,” 59 Federal Register 7629, February 16,

1994.

91 Arianna Skibell and Niina H. Farah, “FERC Faces Environmental Justice Reckoning,” E&E News, July 31, 2020.

92 See, for example, FERC, “Commissioner Richard Glick Dissent Regarding the Rio Grande LNG Terminal and Rio

Bravo Pipeline Projects,” press release, January 23, 2020.

93 FERC, “FERC Chairman Acts to Ensure Prominent FERC Role for Environmental Justice,” press release, February

11, 2021.

94 FERC, “Glick Names Montina Cole to Top Environmental Justice Post at FERC,” press release, May 20, 2021.

Congressional Research Service

16

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Public Participation

Some in Congress have expressed concern about the ability of landowners and other members of

the public to understand and participate effectively in FERC’s pipeline certification process.95

Specific issues have included landowner notification, understanding of property rights, securing

intervenor status, and providing input and comments to FERC during project scoping and review

of permit applications, including NEPA review. In 1978, Congress amended the Federal Power

Act (Section 319) authorizing FERC to establish an Office of Public Participation (OPP) to

“coordinate assistance to the public with respect to authorities exercised by the Commission,” and

“also coordinate assistance available to persons intervening or participating or proposing to

intervene or participate in proceedings before the Commission” (16 U.S.C. § 825q–1). However,

funds were not subsequently appropriated for this office and FERC did not establish it. In the

past, FERC has asserted that the office was unnecessary, stating in a 2007 proceeding that “even

if funding were available, the public interest is adequately represented ... by the Commission, its

staff and state agencies,” but various public advocates and Members of Congress have disagreed

with this assertion.96 Likewise, the FERC chairman remarked in April 2021, “the people who can

afford the high-priced Washington, DC, law firms that participate in our proceedings, they’re

adequately represented, but a lot of other people aren’t—their voices aren’t heard.”97

In the joint House-Senate Appropriations Committee Report accompanying the Consolidated

Appropriations Act, 2021 (P.L. 116-260) Congress again addressed the OPP. The committee

directed FERC to submit a report by June 25, 2021, detailing how the commission will establish

and operate the OPP, including an organizational structure and budget, beginning in FY2022 and

funded through annual charges and filing fees as authorized by the Federal Power Act and the

Omnibus Budget Reconciliation Act of 1986.98 In accordance with this requirement, on June 24,

2021, FERC published a report laying out its plans to develop the OPP, including staffing to assist

the public with learning about, and participating in, FERC proceedings.99 In October 2021, the

FERC chairman announced the appointment of the OPP’s first director.100

Recent Executive Orders

The development of energy pipelines has been a focus of the last four presidents. The Bush,

Obama, Trump, and Biden Administrations issued a series of executive orders directed at the

federal permitting of infrastructure projects, specifically including energy infrastructure. A

number of these orders have been applicable to interstate natural gas pipelines under FERC’s

jurisdiction. Exactly how these orders have affected, or may affect, federal review of interstate

95 See, for example, U.S. Senator Jeanne Shaheen, “Shaheen Reintroduces Legislation to Boost Public Participation in

Approval of Energy Projects and Rates,” press release, May 15, 2019.

96 121 FERC ¶ 61,184.

97 Richard Glick, FERC Chairman, online video, FERC official Facebook page, April 13, 2021,

https://www.facebook.com/watch/?v=264040458557354.

98 “Explanatory Statement Submitted by Mrs. Lowey, Chairwoman of the House Committee on Appropriations,

Regarding the House Amendment to the Senate Amendment to, Consolidated Appropriations Act, 2021,”

Congressional Record, daily edition, vol. 166 (December 21, 2020), p. H8378.

99 FERC, The Office of Public Participation, June 24, 2021.

100 FERC, “Glick Announces Appointment of Elin Katz as Director of FERC’s New Office of Public Participation,”

press release, October 12, 2021.

Congressional Research Service

17

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

natural gas pipeline siting is not entirely clear, however, due to the complexity of the certification

process and permit obligations under related statutory requirements (e.g., NEPA).

Executive Order 13212

President George W. Bush issued Executive Order (E.O.) 13212 in 2001. Focusing specifically on

“energy-related projects,” the order directs federal agencies to “expedite their review of permits

or take other actions as necessary to accelerate the completion of such projects, while maintaining

safety, public health, and environmental protections.”101 In the context of natural gas pipelines,

the principal outcome of this order was the 2002 interagency agreement on early coordination of

pipeline certificate review, which remains in force. In 2005, FERC also signed a memorandum of

understanding with the Corps expanding upon this agreement “to further streamline respective

regulatory processes” consistent with the executive order.102

Executive Order 13604

President Obama issued E.O. 13604 in 2012, “to significantly reduce the aggregate time required

to make decisions in the permitting and review of infrastructure projects by the Federal

Government, while improving environmental and community outcomes.”103 Among other

requirements, the order called for federal agencies to select “infrastructure projects of national or

regional significance” to track on the online Federal Infrastructure Projects Dashboard (§2(c)).

In the context of this executive order, the Administration cited as a best practice for “preapplication/application improvements” FERC’s certificate pre-filing process, which was already

in place at the time.104 A 2013 Presidential Memorandum expanded upon the order, directing the

Steering Committee on Federal Infrastructure Permitting and Review Process Improvement

established by E.O. 13604 “to modernize Federal infrastructure review and permitting

regulations, policies, and procedures to significantly reduce the aggregate time required by the

Federal Government to make decisions in the review and permitting of infrastructure projects,”

including pipelines.105 However, it is not clear to what extent, if any, the executive order and

memorandum may have led to changes to aspects of FERC certification for pipelines. None of the

three pipelines from this period presumably identified as being “of national or regional

significance” (because they were listed on the federal permitting dashboard) were natural gas

pipelines.106

101 Executive Order 13212, “Actions to Expedite Energy-Related Projects,” May 18, 2001.

102 Department of the Army, “Memorandum of Understanding between the Army Corps of Engineers and the Federal

Energy Regulatory Commission for Interstate Natural Gas Pipeline Projects,” July 11, 2005, https://www.ferc.gov/

legal/mou/mou-30.pdf.

103 Executive Order 13604, “Improving Performance of Federal Permitting and Review of Infrastructure Projects,”

March 22, 2012. In a memorandum released the same day, the President called on federal agencies to “coordinate and

expedite their reviews, consultations, and other processes as necessary to expedite decisions related to domestic

pipeline infrastructure projects,” but this directive was limited to a “domestic pipeline system for the transportation of

crude oil.” See The White House, “Presidential Memorandum—Expediting Review of Pipeline Projects from Cushing,

Oklahoma, to Port Arthur, Texas, and Other Domestic Pipeline Infrastructure Projects,” March 22, 2012.

104 The White House, Implementing Executive Order 13604 on Improving Performance of Federal Permitting and

Review of Infrastructure Projects, June 2012, p. 26.

105 The White House, “Modernizing Federal Infrastructure Review and Permitting Regulations, Policies, and

Procedures,” Presidential memorandum, May 17, 2013.

106 Federal Permitting Improvement Steering Council, “Permitting Dashboard,” online database, May 21, 2018,

https://www.permits.performance.gov/projects. The three listed projects were oil pipelines and are currently

Congressional Research Service

18

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Executive Order 13766

Issued by President Trump in January 2017, the order was intended “to streamline and expedite,

in a manner consistent with law, environmental reviews and approvals for all infrastructure

projects, especially projects that are a high priority for the Nation, such as ... pipelines.”107 Among

other provisions, the order permitted governors, federal department and agency heads, or the

FERC chairman to request “high priority” status for a project with respect to “expedited

procedures and deadlines for completion of environmental reviews and approvals” (§3). CRS has

identified no interstate natural gas pipelines which were classified as high priority under this

order.

Executive Order 13777

Issued by President Trump on February 2017, the order was intended “to lower regulatory

burdens on the American people by implementing and enforcing regulatory reform.”108 The order

required agencies to evaluate existing regulations and identify regulations for repeal, replacement,

or modification. Targeted regulations included those that, among other considerations, eliminated

jobs (or inhibited job creation); were outdated, unnecessary, or ineffective; or imposed costs that

exceeded benefits. In response to the order, FERC “established a regulatory reform task force to

perform a thorough review of the Commission’s regulations, policies, and processes, and to

identify opportunities to reduce regulatory burdens.”109 The commission also issued its April 2018

NOI regarding its pipeline certification policies.

Executive Order 13783

Issued by President Trump in March 2017, the order generally aimed to establish a policy to

promote domestic energy development and use, and ensure affordable and reliable electricity. To

accomplish these broad goals, the order directed executive agencies to review their existing

regulations and “appropriately suspend, revise, or rescind those that unduly burden” domestic

energy production or use, “with particular attention to oil, natural gas, coal, and nuclear energy

resources.”110 The order also rescinded guidance intended to help federal agencies determine how

and when to assess climate change effects and costs in rulemakings and environmental reviews.

As directed by the order, the CEQ withdrew its 2016 guidance, Consideration of Greenhouse Gas

Emissions and the Effects of Climate Change in National Environmental Policy Act Reviews. In

June 2019, CEQ published draft NEPA guidance on consideration of greenhouse gas emissions

intended to replace the 2016 guidance.111

Being an independent agency, FERC was not subject to the executive order. Nonetheless, in

November 2017, the commission voluntarily submitted a report reviewing FERC actions pursuant

to the order, which, among other things, encompassed the commission’s regulations, guidance

documents, and policies related to pipeline certification and environmental review under

categorized as “legacy” projects.

107 Executive Order 13766, “Expediting Environmental Reviews and Approvals for High Priority Infrastructure

Projects,” January 24, 2017.

108 Executive Order 13777, “Enforcing the Regulatory Reform Agenda,” February 24, 2017.

109 FERC, “Federal Energy Regulatory Commission One Federal Decision Implementation Plan,” July 9, 2018, p. 3.

110 Executive Order 13783, “Promoting Energy Independence and Economic Growth,” March 28, 2017.

111 Council on Environmental Quality, “Draft National Environmental Policy Act Guidance on Consideration of

Greenhouse Gas Emissions,” 84 Federal Register 30097-30099, June 26, 2019.

Congressional Research Service

19

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

NEPA.112 The report concluded that “the majority of agency actions relating to the siting and

construction of interstate natural gas transportation ... do not materially burden the transportation

or delivery of domestically produced natural gas,” and that there was “no need for the

Commission to consider any revision to this regulation.”113

Executive Order 13807

Issued by President Trump in August 2017, the order was intended “to ensure that the Federal

environmental review and permitting process for infrastructure projects is coordinated,

predictable, and transparent.” The explicit goal of the order was to complete federal

environmental reviews and permitting decisions for major projects within two years of

application (§2(h)).114 A key component of E.O. 13807 was a “One Federal Decision” framework,

whereby each “major” infrastructure project had one lead federal agency responsible for the

overall permit process and issuing one Record of Decision, incorporating individual decisions

from cooperating or participating agencies (§5(b)).

In April 2018, the FERC chairman signed a memorandum of understanding (MOU) with other

federal agencies to implement E.O. 13807.115 Under the MOU, the agencies agree to “undertake

to meet the goal set forth in E.O. 13807 of reducing the time to two years for each agency to

complete all environmental reviews and authorization decisions for major infrastructure projects”

through implementation of One Federal Decision, communication, concurrent reviews, adherence

to a review timetable, and commitment to agency-specific and collective review process

enhancements (§V). FERC already was the lead agency for pipeline certificate environmental

review and had statutory authority to set a review timetable under EPAct, so it appears the impact

of the MOU may have been primarily from cooperating agency coordination and setting the twoyear goal. It is an open question how the MOU has affected FERC’s ongoing review of pipeline

certificate applications. Nonetheless, FERC stated at the time that it was “committed to carrying

out the goals of Executive Order 13807 to improve the efficiency, timing, and overall

predictability of the certification process.”116

Executive Order 13868

Issued by President Trump in April 2019, the order stated that “outdated federal guidance and

regulations regarding Section 401” of the Clean Water Act are “causing confusion and uncertainty

and are hindering the development of energy infrastructure.”117 Among other things, the order

directed the Environmental Protection Agency (EPA) to review and issue new guidance to

supersede the existing Section 401 guidance and to revise the agency’s existing Section 401

112 FERC, “Final Report: Review of Federal Energy Regulatory Commission Agency Actions Pursuant to Executive

Order 13783, Promoting Energy Independence and Economic Growth,” 82 Federal Register 50517-50523, November

1, 2017.

113 Ibid., p. 50521.

114 Executive Order 13807, “Establishing Discipline and Accountability in the Environmental Review and Permitting

Process for Infrastructure Projects,” August 15, 2017.

115 The White House, “Memorandum of Understanding Implementing One Federal Decision Under Executive Order

13807,” April 9, 2018, https://www.whitehouse.gov/wp-content/uploads/2018/04/MOU-One-Federal-Decision-m-1813-Part-2.pdf.

116 Federal Energy Regulatory Commission (FERC), Certification of New Interstate Natural Gas Facilities, Notice of

Inquiry, Docket No. PL18-1-000, April 19, 2018, p. 22.

117 Executive Order 13868, “Promoting Energy Infrastructure and Economic Growth,” April 10, 2019.

Congressional Research Service

20

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

implementing regulations. The order instructed EPA to focus on the need to promote timely

federal-state cooperation, the appropriate scope of water quality reviews, the types of conditions

that may be appropriate to include in a certification, expectations for review times for different

types of certification requests, and the nature and scope of information states may need to act on a

certification request. EPA subsequently issued revised Section 401 guidance and, in July 2020, a

final water quality certification rule which replaced the prior implementing regulations.118

Although not directed at FERC, the EPA’s guidance and rulemaking was intended, in part, to

facilitate the state permitting of interstate natural gas pipelines also under FERC’s NGA

jurisdiction.

Executive Orders 13990, 13992, and 14008

President Biden has issued several executive orders that affect interstate natural gas pipeline

siting. First, on January 20, 2021, the President issued E.O. 13990 asserting a policy to, among

other things, “hold polluters accountable, including those who disproportionately harm

communities of color and low-income communities; to reduce greenhouse gas emissions; to

bolster resilience to the impacts of climate change; ... and to prioritize ... environmental

justice.”119 The order directs all executive departments and agencies to review and address the

promulgation of regulations and other actions during the last four years that conflict with these

objectives, “and to immediately commence work to confront the climate crisis.”120 This order also

revokes Executive Orders 13766, 13783, 13807, and 13868.

On January 25, 2021, President Biden also issued E.O. 13992, which “revokes harmful policies

and directives that threaten to frustrate the Federal Government’s ability to confront ... problems”

including the COVID-19 pandemic, economic recovery, racial justice, and climate change.121 The

order revokes Executive Order 13777.

On January 27, 2021, President Biden issued E.O. 14008, which asserts an Administration policy

“to organize and deploy the full capacity of its agencies to combat the climate crisis to implement

a Government-wide approach that reduces climate pollution in every sector of the economy” and

“delivers environmental justice,” among other objectives.122 Although FERC, being an

independent agency, is not directly subject to these executive orders, the commission stated in

March 2021 that “there have been a series of recent administrative changes,” specifically E.O.

13990 and E.O. 14008, “and we continue to evaluate their impact on our review process.”123

Legislative Proposals

Over the last 20 years, Congress has acted frequently to oversee FERC’s certification of interstate

natural gas pipelines through hearings and correspondence with the commission.124 Members of

118 Environmental Protection Agency, “Clean Water Act Section 401 Certification Rule,” 85 Federal Register 42210-

42287, July 13, 2020.

119 Executive Order 13990, “Protecting Public Health and the Environment and Restoring Science to Tackle the

Climate Crisis,” January 20, 2021.

120 Ibid.

121 Executive Order 13992, “Revocation of Certain Executive Orders Concerning Federal Regulation,” January 25,

2021.

122 Executive Order 14008, “Tackling the Climate Crisis at Home and Abroad,” January 27, 2021.

123 FERC, East Lateral XPress Project, Environmental Assessment, Docket No. CP20-527-000, March 2021, p. 72.

124 See, for example, U.S. Representative Stephen F. Lynch, and U.S. Senators Elizabeth Warren and Edward Markey,

Congressional Research Service

21

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Congress also have proposed legislation to change FERC’s review of gas pipeline certificate

applications, either specifically or as one category among a broader range of infrastructure

projects. Proposals also have sought to change FERC’s regulations with respect to certificates it

has issued to pipeline developers.

Proposals in Prior Congresses

In the 111th-116th Congresses, bills which were not enacted sought to increase FERC public

hearings, limit eminent domain authority, expand the scope of FERC’s environmental review,

require regional review of multiple projects, and impose specific deadlines on FERC and

cooperating agencies, among other measures. Title 41 of the Fixing America’s Surface

Transportation Act (P.L. 114-94; FAST-41), which became law in December 2015, revised the

process for federal approval of a range of major infrastructure projects by establishing best

practices, requiring coordination of federal agency review of projects, and shortening the period

for challenges to final decisions for issuing project permits. Infrastructure projects covered by the

act are those requiring environmental review under NEPA and requiring investment exceeding

$200 million (§41001).125 As of May 2022, the permitting dashboard listed 10 projects involving

natural gas pipelines (7 with completed permit reviews and 3 cancelled) covered under FAST-41

with FERC as the lead agency.126 A summary table of the relevant legislative proposals in the

111th-116th Congresses is provided in the Appendix.

Legislative Proposals in the 117th Congress

Some Members of Congress have introduced legislative proposals in the 117th Congress involving

FERC’s certification authority or review process. Table 1 summarizes the key provisions in these

bills related to natural gas pipeline certification. As the table shows, the proposals variously

would require FERC to collectively review multiple pipelines proposed in the same region, hold

more public meetings, restrict the use of eminent domain, meet shorter permit review deadlines,

suspend proposed policy changes, and more broadly consider greenhouse gas emissions. Some

would require environmental monitoring of completed pipelines and mandate greater cooperation

and transparency of permit review by federal agencies.

Table 1. Current Legislative Proposals Involving FERC Certification of Pipelines

(117th Congress)

Bill Title

Bill Number

Key FERC Provisions

Landowner Fairness Act

S. 641

Would require FERC to consider certain factors in

pipeline permitting, would modify eminent domain

requirements, and would prohibit using NGA

eminent domain for a pipeline built for exports.

Ending Natural Gas Companies’ Seizure of

Land for Export Profits Act

S. 655

Would prohibit the use of eminent domain by a

FERC permit holder for a pipeline to be built

substantially for exports.

letter to the Honorable Richard Glick, Chairman, FERC, February 19, 2021, https://lynch.house.gov/index.cfm?a=

Files.Serve&File_id=CDF3115A-C4E0-4B4C-9C4F-EC87566542ED.

125 The Office of Management and Budget (OMB) and Council on Environmental Quality (CEQ) jointly issued

guidance for agencies to comply with FAST-41. See OMB and CEQ, “Guidance to Federal Agencies Regarding the

Environmental Review and Authorization Process for Infrastructure Projects,” memorandum, January 13, 2017.

126 Federal Permitting Improvement Steering Council, “Federal Infrastructure Permitting Dashboard,” online database,

May 25, 2022, accessible at https://www.permits.performance.gov/projects.

Congressional Research Service

22

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Bill Title

Bill Number

Key FERC Provisions

Rebuild America Now Act

S. 1254

Would impose a one-year deadline on FERC review

for pipeline permit applications, and would impose a

90-day deadline after FERC’s final environmental

document on other federal agency permit decisions.

Energy Freedom Act

S. 3762

H.R. 7094

Would impose a one-year deadline on FERC review

permit decisions for pipeline permit applications and

requires permit approval for projects that meet

federal pipeline safety standards.

Ensuring National Security Using Reliable

Energy (ENSURE) Act

S. 3908

Would bar FERC’s February 2022 policy statements

from taking effect without certification that (1)

pipeline natural gas supplies do not pose a reliability

risk to the bulk power system and (2) natural gas and

electricity prices are stabilized at historical levels.

FREE American Energy Act

S. 3982

Would require FERC and other federal agencies to

approve or deny permits for natural gas pipeline

projects within 60 days.

Environmental Justice Mapping and Data

Collection Act of 2021

H.R. 516

Would establish an interagency Environmental Justice

Mapping Committee, including FERC, to create a tool

to identify environmental justice communities.

CLEAN Future Act

H.R. 1512

Would revise and fund FERC’s Office of Public

Participation to represent the interests of the public

in NGA-related proceedings. Would prohibit

pipeline companies from using NGA eminent domain

authority until they have all necessary federal and

state permits and comply with environmental permit

conditions. Would also prohibit using eminent

domain for natural gas pipelines to be built for

import or export.

Promoting Interagency Coordination for

Review of Natural Gas Pipelines Act

H.R. 1616

Would expand FERC’s authority to act as the lead

agency for coordinating all federal authorizations and

NEPA environmental reviews with respect to a

natural gas pipeline project. Also would require

consultation with the Transportation Security

Administration regarding pipeline security.

Safe and Accountable Federal Energy

Review for Pipelines Act of 2021

H.R. 2115

Would require FERC to conduct an evidentiary

hearing and/or cumulative review of major energy

infrastructure projects planned throughout a region.

Would require FERC to consider the existence of

other regional pipelines or underutilized pipeline

capacity in permit application reviews. Would

require FERC to monitor environmental impacts of

all approved and constructed projects for five years.

To amend the Natural Gas Act with

respect to actions for eminent domain by

holders of certificates of public

convenience and necessity, and for other

purposes.

H.R. 2889

Would prevent pipeline companies from using NGA

eminent domain authority until they have all

necessary federal and state permits for construction

and operation.

Ukraine Assistance and American Energy

Acceleration Act

H.R. 7012

Would require FERC to permit pipelines “bona fide

engaged” in natural gas transportation and sales, and

requires permit approval for projects that meet

federal pipeline safety standards.

Sources: http://www.congress.gov, CRS analysis.

Congressional Research Service

23

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Notes: FERC = Federal Energy Regulatory Commission, NEPA = National Environmental Policy Act, NGA =

Natural Gas Act.

FERC’s Policy Review

As discussed earlier, FERC’s review of pipeline certificate applications is guided by its Policy

Statement on Certification of New Interstate Natural Gas Pipeline Facilities issued in 1999. In

December 2017, the FERC chairman announced that the commission would undertake a review

of its permitting policies and procedures for interstate natural gas pipelines. Accordingly, in April

2018, the commission issued an NOI “to examine its policies in light of changes in the natural gas

industry and increased stakeholder interest in how it reviews natural gas pipeline proposals.”127

More specifically, the commission’s notice posed “a range of questions that reflected concerns

raised in numerous public comments, court proceedings and other forums,” and sought input on

“potential changes to both the existing Policy Statement and the structure and scope of the

Commission’s environmental analysis” as well as “feedback on the transparency, timing, and

predictability of its certification process.”128

According to its notice, FERC’s inquiry focused on four general aspects of its certificate

application review, with specific questions posed under each aspect

relying on precedent agreements to demonstrate project need,

eminent domain and landowner interests,

evaluating project alternatives and environmental effects, and

the efficiency and effectiveness of FERC’s certificate processes.129

FERC’s inquiry was opened for public comments through July 25, 2018.130 However, according

to the NOI, the commission intended to make no decisions on possible further action related to its

inquiry until it had reviewed the comments filed; the commission did not state any timetable for

completing this review.131 (FERC issued its 1999 policy statement over 13 months after

publishing an NOI for that proceeding.132) Through 2020, the commission took no further action

related to the NOI.

Reopening the Policy Review

On January 21, 2021 President Biden appointed a new FERC chairman (elevating a commissioner

who joined FERC in 2017).133 The appointment followed the November 30, 2020, Senate

confirmation of two new commissioners, restoring FERC to its full statutory complement of five

commissioners.134 On February 18, 2021, under its new chairman, FERC announced that it had

127 FERC, “Commission Initiates Notice of Inquiry into Pipeline Certificate Policy Statement,” press release, R-18-16,

April 19, 2018.

128 Ibid.

129 FERC 2018 NOI, pp. 45-46.

130 FERC, “Certification of New Interstate Natural Gas Facilities,” 83 Federal Register 24780, May 30, 2018. The

comment period was extended 30 days from an original closing date of June 25, 2018.

131 FERC 2018 NOI, p. 4.

132 FERC, “Regulation of Interstate Natural Gas Transportation Services,” Notice of Inquiry, 63 Federal Register

42974, 84 FERC ¶ 61,087, July 29, 1998.

133 FERC, “President Biden Names Glick Chairman of FERC,” press release, January 21, 2021.

134 FERC, “Senate Votes to Confirm Christie, Clements to Commission,” press release, November 30, 2020.

Congressional Research Service

24

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

“reopened” its review of the 1999 policy statement and published a new NOI “asking for new

information and additional perspectives that would assist the Commission in moving forward

with its review ... looking to build upon the record already established.”135 In the announcement,

the FERC chairman stated “it’s important to recognize that many changes have occurred since our

initial inquiry three years ago.” At an industry event, the FERC chairman subsequently stated “we

have ... reinvigorated a proceeding that was begun many years ago,” noting that “our whole

process has come under some criticism—I’ve been critical of some aspects of it.”136

The 2021 NOI reaffirmed the commission’s interest in the four general aspects of its certificate

application review covered in its 2018 NOI, some with modification. It also posed new questions

on an additional issue area examining FERC’s “identification and addressing of any

disproportionately high and adverse human health or environmental effects of its programs,

policies, and activities on environmental justice communities and the mitigation of those adverse

impacts and burdens.”137 The NOI solicited new information and stakeholder perspectives related

to the following five aspects of review, again, with specific questions posed under each aspect:

potential adjustments to determination of need,

eminent domain and landowner interests,

consideration of environmental impacts,

efficiency of the commission’s review process, and

consideration of effects on environmental justice communities.138

The initial deadline for comments in the NOI was April 26, 2021, but it was subsequently

extended to May 26, 2021.139 The commission established no deadline for taking further actions

with respect to the NOI, although the chairman stated, “I suspect we’ll be able to act ..., hopefully

soon on this gas pipeline certificate proceeding.”140 Any FERC pipeline certification activities or

decisions in the meantime were to be made in accordance with the 1999 policy statement.

Moreover, the FERC Chairman stated that “the Commission will not wait to act on Certificate

applications while we consider options for improving the process.”141 However, with the

departure of a FERC commissioner in August 2021 (bringing the number of sitting

commissioners down to four), some analysts suggested that FERC could be “deadlocked” on any

proposed policy changes and so it was unlikely to finalize them without an additional voting

member.142

135 FERC, “FERC Revisits Review of Policy Statement on Interstate Natural Gas Pipeline Proposals,” press release,

February 18, 2021.

136 Richard Glick, FERC Chairman, remarks at the Women’s Council on Energy and the Environment, Virtual

Executive Series, April 29, 2021, video available at https://youtu.be/NT0jnNl6tpw.

137 FERC 2021 NOI, p. 4.

138 FERC 2021 NOI.

139 FERC, “Notice Extending Time for Comments,” Docket No. PL18-1-000, March 31, 2021.

140 Richard Glick, April 29, 2021.

141 Richard Glick, May 21, 2021.

142 Robert Walton, “With FERC Now Split 2-2, Clean Energy Advocates Call for Caution and Urgency to Fill Vacant

Seat,” Utility Dive, September 3, 2021, https://www.utilitydive.com/news/with-ferc-now-split-2-2-clean-energyadvocates-call-for-caution-and-urgenc/606038/.

Congressional Research Service

25

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Issuance of New Policy Statements

On December 13, 2021, a new FERC commissioner appointed by President Biden was sworn in,

restoring the commission to a full complement of five members.143 Approximately two months

later, FERC issued its two updated policy statements for the certification of interstate natural gas

pipelines and infrastructure. As discussed above, the first policy statement established a new

“analytical framework” for evaluating pipeline certificate applications, and the second established

FERC’s interim policy for examining the GHG impacts of and integrating climate considerations

into pipeline certificate decisions.

The two policy statements were approved by a 3-2 vote. One commissioner dissented on the

grounds that the statements, taken together, would

have profound implications for the ability of natural gas companies to secure capital, on

the timelines for ... applications to be processed, and on the costs that a pipeline and its

customers will bear as a result of the potentially unmeasurable mitigation that the majority

expects each company to propose when filing its application and the possibility of further

mitigation measures added unilaterally by the Commission. 144

Another commissioner dissented on the grounds that the changes in the new certificate policy

would “exceed the Commission’s legal authority under the NGA and NEPA,” and would make it

“even more costly and difficult to build the infrastructure that will be critically needed to

maintain reliable power service to consumers as the generation mix changes to incorporate lower

carbon-emitting resources.”145

Reaction and Reconsideration

Reaction in Congress to the new FERC policy statements was mixed. For example, at a March 3,

2022, hearing of the Senate Energy and Natural Resources Committee, both the chairman and

ranking member were critical of the policy statements, with the chairman asserting that FERC

was “setting in motion a process that will serve to further shut down the infrastructure we

desperately need as a country and further politicize energy development.”146 However, other

committee members were supportive of the policy statements, agreeing that they were required by

the courts and characterizing them, for example, as “common sense regulation.”147 The chairman

of the House Energy and Commerce Committee also expressed support for FERC’s policies as

“necessary and long-overdue actions” which were “consistent with ... court directives.”148

Reaction to FERC’s new policy statements among key stakeholders was also mixed. One gas

pipeline trade association objected to them on the grounds that the policy statements created

additional uncertainty for pipeline developers, unfairly changed policies for pending permit

143 FERC, “Willie L. Phillips Sworn in as FERC Commissioner,” press release, December 13, 2021.

144 James Danly, FERC Commissioner, Certification of New Interstate Natural Gas Facilities, Docket No.

PL18-1-000, Dissent, February 18, 2022, p. 2.

145 Mark Christie, FERC Commissioner, Certification of New Interstate Natural Gas Facilities, Docket No.

PL18-1-000, Dissent, February 18, 2022, p. 2.

146 Sen. Joe Manchin, Remarks before the Senate Energy and Natural Resources Committee hearing “To Review

FERC’s Recent Guidance On Natural Gas Pipelines,” March 3, 2022.

147 Sen. Angus King, Remarks before the Senate Energy and Natural Resources Committee hearing “To Review

FERC’s Recent Guidance On Natural Gas Pipelines,” March 3, 2022.

148 Rep. Frank Pallone Jr., “Pallone Applauds FERC’s Decision to Consider Climate, Environmental Justice in Natural

Gas Certification Process,” press release, House Energy and Commerce Committee, February 17, 2022.

Congressional Research Service

26

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

applications, applied an arbitrary threshold in considering GHG emissions, was unclear about the

nature of GHG mitigation requirements, and imposed such requirements outside of FERC’s

jurisdiction.149 Other trade associations filed motions for rehearing, arguing among other things

that FERC had overstepped its NGA authority, and that the commission’s process for establishing

its new policy statements was not transparent, lacking sufficient opportunity for stakeholder

input.150 Environmental groups, on the other hand, supported the policy statements, describing

them, for example, as “sorely needed” and “putting in place a process that better reflects

[FERC’s] legal duties and restores balance to its reviews of new gas pipelines and affiliated

infrastructure.”151

In light of the reactions in Congress and among energy sector stakeholders, on March 24, 2022,

FERC issued an order redesignating both of its both policy statements as drafts. According to the

FERC chairman,

in light of concerns that the policy statements created further confusion about the

Commission’s approach to the siting of natural gas projects, the Commission decided it

would be helpful to gather additional comments from all interested stakeholders, including

suggestions for creating greater certainty, before implementing the new policy

statements.152

FERC’s order invited additional comments by April 25, 2022 (and reply comments by May 25,

2022), but did not indicate when revised policy statements might be issued. The commission

stated that the two draft policy statements would not apply to pending or new permit applications

before the commission issues any final guidance. Because a FERC policy statement is a guidance

document, not a regulation or statute, the commission has considerable discretion regarding if,

when, and how it will apply any policy changes to pending certificate applications.153

Policy Issues for Congress

Congress has been interested in the development of natural gas pipelines for decades, with a

particular focus on siting and environmental impacts in recent years. Some in Congress generally

see such pipeline development as positive, primarily due to its perceived economic benefits in

terms of construction employment, lower natural gas prices, and environmental benefits relative

to burning more carbon-intensive fossil fuels (i.e., coal). Others generally view gas pipeline

development more critically, primarily due to environmental concerns from greenhouse gas

emissions. Still others are focused primarily on the local effects of gas pipeline development

related to public safety, the impacts on lands, the acquisition of private property through eminent

domain, and impacts on environmental justice communities. The geopolitical importance of

secure natural gas supplies to U.S. allies is yet another factor which has become important given

149 Interstate Natural Gas Association of America, “INGAA Reacts to FERC Certificate Policy Statement Changes,”

press release, February 17, 2022.

150 American Petroleum Institute, “API Files Motion for Rehearing on FERC Policy Statement,” press release, March

18, 2022; Natural Gas Supply Association and the Center for LNG, “NGSA and CLNG Request Rehearing of FERC

Updated Certificate and Greenhouse Gas Policy Statements,” press release, March 18, 2022.

151 Gillian Giannetti and Morgan Johnson, “FERC’s New Gas Policies Bring Balance to Pipeline Reviews,” March 2,

2022, https://www.nrdc.org/experts/gillian-giannetti/fercs-new-gas-policies-bring-balance-pipeline-reviews-0.

152 FERC, “FERC Seeks Comment on Draft Policy Statements on Pipeline Certification, GHG Emissions,” press

release, March 24, 2022, https://www.ferc.gov/news-events/news/ferc-seeks-comment-draft-policy-statementspipeline-certification-ghg-emissions.

153 U.S. Court of Appeals for the District of Columbia, Consolidated Edison Company of New York, Inc., et al., v.

Federal Energy Regulatory Commission, No. 01-1345, January 17, 2003, https://www.cadc.uscourts.gov/internet/

opinions.nsf/4B1331E528B23FC485256F82005F46BE/$file/01-1345a.txt.

Congressional Research Service

27

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

the military conflict in Ukraine. Pipeline proponents would rather see more and faster pipeline

development, whereas opponents would rather see less—preferring instead a greater policy

emphasis on energy alternatives, such as renewable electricity generation, they view as more

environmentally or socially benign.

Because FERC has the statutory authority to approve or deny certificates for interstate natural gas

pipelines, the policy views above have led to persistent congressional scrutiny of FERC’s pipeline

certification process and decisions. Concerns about gas pipelines have motivated repeated

attempts at congressional intervention. In total, over 40 bills have been introduced since the 111th

Congress (over a dozen in the 117th Congress alone) which would affect various aspects of

FERC’s review of pipeline certificate applications. Of these, only the FAST Act (which seems to

have applied to only a few of FERC’s gas pipeline reviews) and the Consolidated Appropriations

Act, 2021 became law. Therefore, absent any other statutory changes, Congress must rely on

FERC to address policy concerns on its own volition in response to congressional oversight,

federal court decisions, and public input.

FERC’s ongoing proceedings regarding its pipeline certification policies cover a number of

congressional concerns raised either in oversight hearings or bill provisions in the 117th Congress.

Examples include eminent domain authority (H.R. 2115), environmental justice (H.R. 516),

determining market need (S. 1314), and natural gas exports (S. 655). Therefore, while FERC’s

policy review does not guarantee any particular changes to the gas pipeline certification status

quo, it may provide valuable information and context for congressional oversight. If Congress

disagrees with FERC’s future policy choices based on the findings of its policy statement

proceedings, those findings could provide an informed basis and clearer policy context for

subsequent legislative proposals.

Although recent executive and agency actions, including FERC’s agreements with other agencies

and its policy review, may lead to changes in FERC policies or process, they may apply only to

those aspects of gas pipeline regulation which fall directly within the commission’s statutory

authority under the Natural Gas Act or within its discretion under other federal statutes. This is a

significant limitation because much of FERC’s pipeline certificate review is environmental

review in compliance with NEPA. While the bills identified in this report, and FERC’s policy

review, could change how FERC interprets or fulfills its obligations under NEPA, they would not

amend NEPA itself. Likewise, they would not amend other federal statutes, such as the Clean

Water Act or the Clean Air Act, which also may have a bearing on gas pipeline siting approval.

Congressional Research Service

28

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Appendix. Past FERC Permit Legislative Proposals

Table A-1. Past Legislative Proposals to Change FERC Certification of Pipelines

(111th through 116th Congresses)

Congress

111th

Bill Title

Bill

Number

Last Major

Action

Key FERC Provisions

To require [FERC] to

hold at least one public

hearing before

issuance of a permit

affecting public or

private land use in a

locality

S. 32

Referred to

Subcommittee

H.R. 1922

Referred to

Committee

112th

Reaffirming

Constitutional

Property Rights Act

H.R. 3913

Referred to

Subcommittee

Would have prohibited eminent domain

for pipelines to be constructed for

transporting natural gas to an LNG

terminal for export.

113th

American Energy

Solutions for Lower

Costs and More

American Jobs Act

H.R. 2

Passed in

House

113th

American Renaissance

in Manufacturing Act

H.R. 5360

Introduced

Both bills would have imposed on FERC a

12-month deadline to approve or deny

pipeline permit applications after pre-filing.

Would have required 90-day permit

review for pre-filed pipeline projects by

other federal agencies involved; if a permit

were not approved or denied by this

deadline, approval would have taken effect.

114th

North American

Energy Security and

Infrastructure Act of

2016

S. 2012

House/Senate

Conference

Held

Would have required FERC to identify and

notify agencies participating in certificate

review; federal permit decisions within 90

days of FERC completing NEPA review;

and concurrent review by cooperating

agencies of non-NEPA actions. Would have

required greater transparency in review

scheduling, status, and reporting of delays.

114th

Fixing America’s

Surface Transportation

(FAST) Act

H.R. 22

Became P.L.

114-94

Title 41 requires greater agency

coordination and oversight of federal

review for infrastructure projects (e.g.,

pipelines) subject to NEPA and requiring

investment over $200 million. Establishes a

Federal Permitting Improvement Steering

Council—including FERC—to oversee,

facilitate, and recommend schedules and

best practices for federal permitting.

Requires greater transparency in review

scheduling, status, and reporting of delays.

114th

Natural Gas Pipeline

Permitting Reform Act

H.R. 161

Passed in

House

Would have imposed on FERC a 12-month

deadline to approve or deny pipeline

permit applications after pre-filing. Would

have required 90-day permit review for

pre-filed pipeline projects by other federal

agencies involved; if a permit were not

approved or denied by this deadline,

approval would have taken effect.

Congressional Research Service

Would have required FERC to hold a

public hearing in each county and locality

affected by a pipeline proposal. Also would

have required additional public hearings, if

requested, for issues not addressed in an

initial hearing.

29

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Congress

Bill Title

Bill

Number

Last Major

Action

Key FERC Provisions

114th

Safer Pipelines Act of

2016

H.R. 5630

Referred to

Committee

If a proposed pipeline expansion were

challenged, would have required a FERC

evidentiary hearing on the need for

expansion or a cumulative review of

energy projects planned in the region. For

new pipelines, would have required FERC

to consider under NEPA the cumulative

impacts of other pipeline projects in the

same state or within 100 miles.

115th

Timely Review of

Infrastructure Act

S. 8

Referred to

Committee

115th

Timely Review of

Infrastructure Act

H.R. 6552

Referred to

Subcommittee

Would have authorized FERC to raise staff

pay so as to carry out its functions in a

timely, efficient, and effective manner.

115th

Public Engagement at

FERC Act

S. 1240

Referred to

Committee

115th

Public Engagement at

FERC Act

H.R. 2656

Referred to

Subommittee

115th

Pipeline Fairness and

Transparency Act

S. 1314

Referred to

Subcommittee

115th

Pipeline Fairness and

Transparency Act

H.R. 2893

Referred to

Committee

115th

Independent Agency

Regulatory Analysis

Act of 2017

S. 1448

Referred to

Committee

115th

Promoting Interagency

Coordination for

Review of Natural Gas

Pipelines Act

H.R. 2910

Passed in

House

115th

Energy and Natural

Resources Act of 2017

S. 1460

Committee

Hearings Held

Congressional Research Service

Would have revised and expanded FERC’s

Office of Public Participation to represent

the interests of the public in proceedings

on rates, service, and infrastructure siting.

Would have required FERC to prepare a

supplemental EIS for an application if FERC

makes a substantial change or in case of

new environmental circumstances or

information. Also would have required

environmental impact mitigation plans;

public meetings in project counties; and

review of cumulative visual impacts on

national scenic trails. S. 1314 also would

have required multiple pipelines proposed

within 100 miles of each other to be

evaluated as one project under NEPA.

Would have authorized the President to

require an independent regulatory agency

to comply with analysis requirements

applicable to other federal agencies, and

assess costs and benefits of economically

significant rules and alternatives.

Would have required FERC to identify and

notify agencies participating in review.

Would have required federal permit

decisions within 90 days of FERC

completing NEPA and concurrent review

by cooperating agencies of non-NEPA

actions. Would have required greater

transparency in review scheduling, status,

and reporting of delays.

30

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Congress

Bill Title

Bill

Number

Last Major

Action

Key FERC Provisions

115th

Rebuild America Now

Act

S. 1756

Committee

Hearings Held

Would have imposed on FERC a one-year

deadline to approve or deny pipeline

permit applications after pre-filing. Would

have required 90-day permit review for

pre-filed pipeline projects by other federal

agencies involved; if a permit were not

approved or denied by this deadline,

approval would take effect. Would have

allowed aerial survey data to satisfy

pipeline permit preliminary requirements.

115th

Safer Pipelines Act of

2017

H.R. 2649

Referred to

Subcommittee

If a proposed pipeline expansion were

challenged, it would have required FERC to

assign the application to an administrative

law judge to conduct an evidentiary hearing

on the need for the expansion and report

the findings. Would have required FERC to

cumulatively review major energy projects

planned in the region. For new interstate

pipelines, would have required FERC to

consider under NEPA the cumulative

impacts of other projects in the same state

or within 100 miles.

115th

To require [FERC] to

consider greenhouse

gas emissions related

to natural gas

pipelines, and for

other purposes

H.R. 3241

Referred to

Committee

Would have required FERC environmental

reviews under NEPA to consider

greenhouse gas emissions from pipeline

construction and operation, and the

production, transportation, and

combustion of the natural gas to be

transported through the pipeline.

115th

Natural Gas Pipeline

Public Health

Protection Act of 2017

H.R. 4381

Referred to

Committee

Would have suspended construction of

FERC-certificated natural gas facilities until

remediation of air quality violations.

115th

No title

H.Amdt.

204 to

H.R. 2910

Not agreed to

Would have excluded from provisions in

H.R. 2910 pipelines on lands managed for

conservation or recreation.

115th

No title

H.Amdt.

206 to

H.R. 2910

Not agreed to

Would have required FERC to supplement

an environmental impact statement under

NEPA for a pipeline project if there is a

substantial change in the proposed action

or significant new circumstances or

information.

116th

Timely Review of

Infrastructure Act

S. 607

Reported by

Committee

Would have authorized FERC to raise staff

pay so as to carry out its functions in a

timely, efficient, and effective manner.

116th

Independent Agency

Regulatory Analysis

Act

S. 869

Referred to

Committee

Would have authorized the President to

require an independent regulatory agency

to comply with analysis requirements

applicable to other federal agencies, and

assess costs and benefits of economically

significant rules and alternatives.

116th

Public Engagement at

FERC Act

S. 1477

Referred to

Committee

Would have revised and expanded FERC’s

Office of Public Participation to represent

Congressional Research Service

31

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

Congress

Bill Title

Bill

Number

Last Major

Action

Key FERC Provisions

116th

Public Engagement at

FERC Act

H.R. 3240

Referred to

Subcommittee

the interests of the public in proceedings

on rates, service, and infrastructure siting.

116th

Federal Permitting

Reform and Jobs Act

S. 1976

Referred to

Committee

116th

Federal Permitting

Reform and Jobs Act

H.R. 3671

Reported by

Subcommittee

Would have required FERC to report to

Congress recommendations on ways to

reconcile FERC permitting regulations with

requirements under the FAST Act.

116th

Pipeline Fairness,

Transparency, and

Responsible

Development Act of

2020

S. 4502

Referred to

Committee

Would have amended the NGA to address

landowner notice, eminent domain, and

environmental review for interstate natural

gas pipelines, as well as their impacts on

national scenic trails. Also would have set a

45-day deadline on FERC permit rehearing

decisions.

116th

Reaffirming Property

Rights Through

Natural Gas Act

Modernization Act

S. 4673

Referred to

Committee

Would have required FERC to consider

certain factors in issuing pipeline permits

and would modify eminent domain

requirements for pipeline construction.

116th

Consolidated

Appropriations Act,

2021

H.R. 133

Became P.L.

116-260

Committee report directs FERC to submit

a report detailing how it will establish and

operate the Office of Public Participation,

including an organizational structure and

budget, beginning in FY2022.

116th

Pipeline Fairness and

Transparency Act

H.R. 173

Referred to

Subcommittee

Would have amended the NGA to address

eminent domain and environmental review

for interstate natural gas pipelines, as well

as their impacts on national scenic trails.

116th

Reaffirming

Constitutional

Property Rights Act

H.R. 2198

Referred to

Subcommittee

Would have prohibited the use of eminent

domain by a FERC permit holder for a

pipeline supplying an LNG export facility.

116th

Promoting Interagency

Coordination for

Review of Natural Gas

Pipelines Act

H.R. 3983

Referred to

Committee

116th

Promoting Interagency

Coordination for

Review of Natural Gas

Pipelines Act

H.R. 7401

Referred to

Subcommittee

Would have required that federal, state,

and local agencies involved in

environmental review defer to FERC’s

approved scope for NEPA review. Would

have required FERC permit decisions

within 90 days of completing NEPA review.

Would require concurrent review by

cooperating agencies. H.R. 3983 also would

have required consultation with the

Transportation Security Administration

regarding pipeline security

116th

To require [FERC] to

consider greenhouse

gas emissions related

to natural gas

pipelines, and for

other purposes

H.R. 4657

Referred to

Subcommittee

Congressional Research Service

Would have required FERC environmental

reviews under NEPA to consider

greenhouse gas emissions from pipeline

construction and operation, and the

production, transportation, and

combustion of the natural gas to be

transported through the pipeline.

32

Interstate Natural Gas Pipeline Siting: FERC Policy and Issues for Congress

116th

Fairness for

Landowners Facing

Eminent Domain Act

H.R. 5454

Referred to

Subcommittee

Would have prohibited or suspended the

use of eminent domain under a FERC

pipeline permit under certain

circumstances. Would have prohibited the

use of eminent domain attached to any

facility that imports or exports natural gas.

116th

Scenic Trail Viewshed

Protection Act

H.R. 7878

Referred to

Committee

Would have allowed FERC to permit

pipelines crossing or impacting the view

from a national scenic trail only under

certain conditions.

Source: http://www.congress.gov, CRS analysis.

Notes: FERC = Federal Energy Regulatory Commission, LNG = liquefied natural gas, NEPA = National

Environmental Policy Act, NGA = Natural Gas Act.

Author Information

Paul W. Parfomak

Specialist in Energy Policy

Acknowledgments

Lynn J. Cunningham, Senior Research Librarian, helped prepare the legislative tables in this report.

Disclaimer

This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan

shared staff to congressional committees and Members of Congress. It operates solely at the behest of and

under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other

than public understanding of information that has been provided by CRS to Members of Congress in

connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not

subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in

its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or

material from a third party, you may need to obtain the permission of the copyright holder if you wish to

copy or otherwise use copyrighted material.

Congressional Research Service

R45239 · VERSION 11 · UPDATED

33

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.