U.S. Nuclear Weapon “Pit” Production Options for Congress
Congressional research reportFeb 21, 2014
Ask Donna
What actually matters in this document.
Text
U.S. Nuclear Weapon “Pit” Production
Options for Congress
(name redacted)
Specialist in Nuclear Weapons Policy
February 21, 2014
Congressional Research Service
7-....
www.crs.gov
R43406
U.S. Nuclear Weapon “Pit” Production Options for Congress
Summary
A “pit” is the plutonium core of a nuclear weapon. Until 1989, the Rocky Flats Plant (CO) massproduced pits. Since then, the United States has made at most 11 pits per year (ppy). U.S. policy
is to maintain existing nuclear weapons. To do this, the Department of Defense states that it needs
the Department of Energy (DOE), which maintains U.S. nuclear weapons, to produce 50-80 ppy
by 2030. While some argue that few if any new pits are needed, at least for decades, this report
focuses on options to reach 80 ppy.
Pit production involves precisely forming plutonium—a hazardous, radioactive, physically quirky
metal. Production requires supporting tasks, such as analytical chemistry (AC), which monitors
the chemical composition of plutonium in each pit.
With Rocky Flats closed, DOE established a small-scale pit manufacturing capability at PF-4, a
building at Los Alamos National Laboratory (LANL). DOE also proposed higher-capacity
facilities; none came to fruition. In 2005, Congress rejected the Modern Pit Facility, viewing as
excessive the capacity range DOE studied, 125-450 ppy. In 2012, the Administration “deferred”
construction of the Chemistry and Metallurgy Research Replacement Nuclear Facility (CMRRNF) on grounds of availability of interim alternatives and affordability.
Nonetheless, options remain:
•
Build CMRR-NF. Congress mandated it in the FY2013 cycle, but provided no
funds for it then, and permitted consideration of an alternative in the FY2014
cycle.
•
Remove from PF-4 tasks not requiring high MAR and security. Casting pits
uses much plutonium that an accident might release (“Material At Risk,” MAR)
and requires high security. Making 80 ppy would require freeing more MAR and
floor space in PF-4 for casting.
•
Provide regulatory relief so RLUOB could hold 1,000 grams of plutonium
with few changes to the building. AC for 80 ppy needs much floor space but
not high MAR or high security. Several options involve LANL’s Radiological
Laboratory/Utility/Office Building (RLUOB). Regulations permit it to hold 26
grams of weapons-grade plutonium, the volume of two nickels; AC for 80 ppy
would require 500 to 1,000 grams and perhaps space elsewhere. Augmenting
RLUOB to hold the latter amounts within regulations would be costly even
though the radiation dose if the building collapsed would be very low. Regulatory
relief would save time and money, but would raise concerns about compliance
with regulations. A complementary option is to perform some AC at Lawrence
Livermore National Laboratory or Savannah River Site.
•
Move plutonium-238 work to Idaho National Laboratory or Savannah River
Site. Fabricating plutonium-238 into power sources for space probes entails high
MAR, but not high security because it is not used in pits. Moving it would free
MAR and floor space in PF-4. At issue is whether to conduct all plutonium work
at LANL, the plutonium “center of excellence.”
Congressional Research Service
U.S. Nuclear Weapon “Pit” Production Options for Congress
•
Build concrete “modules” connected to PF-4. This would enable high-MAR
work to move out of PF-4, so PF-4 and modules could do the needed pit work. At
issue: are modules needed, at what cost, and when.
Several options have the potential to produce 80 ppy and permit other plutonium activities at
relatively modest cost, in a relatively short time, with no new buildings, and with minimal
environmental impact. Determining their desirability and feasibility would require detailed study.
Observations include:
•
Differing time horizons between Congress and DOE, and between political and
technical imperatives, cause problems.
•
Doing nothing entails costs and risks. Keeping a 1950s-era building open while
options are explored exposes workers to a relatively high risk of death in an
earthquake.
•
Congress may wish to consider limiting a building’s permitted plutonium
quantity by estimated dose instead of MAR. A facility can be safe even if it is not
compliant with regulations.
•
The political system is more flexible than the regulatory system. Regulations
derive their authority from statutes. Regulators, bound by these statutes, cannot
make cost-benefit tradeoffs regarding compliance. In contrast, the political
system has the authority, ability, and culture to decide which tradeoffs are worth
making.
Congressional Research Service
U.S. Nuclear Weapon “Pit” Production Options for Congress
Contents
Introduction...................................................................................................................................... 1
Background ...................................................................................................................................... 2
Technical Aspects ...................................................................................................................... 2
Plutonium ............................................................................................................................ 2
Pits ....................................................................................................................................... 3
The Pit Production Process ................................................................................................. 4
Life Extension Programs ..................................................................................................... 5
Pit Production Capacity: How Much Is Needed?................................................................ 5
Plutonium-238 ................................................................................................................... 10
Key Regulatory Terms ............................................................................................................. 10
Facility Aspects: Buildings to Support Pit Production ............................................................ 14
Existing Buildings at Los Alamos for Plutonium Work .................................................... 14
A Sisyphean History: Failed Efforts to Construct a Building to Restore Pit
Production ...................................................................................................................... 18
Options for Congress ..................................................................................................................... 25
Analysis of Alternatives .......................................................................................................... 25
The Role of the National Environmental Protection Act (NEPA) Process in an
Analysis of Alternatives ................................................................................................. 26
Potential Options ..................................................................................................................... 29
Option 1. Focus PF-4 on Pit Production; Move Other Tasks Elsewhere as Needed ......... 30
Option 2. Build CMRR-NF ............................................................................................... 31
Option 3. Build a New Building Combining PF-4 and CMRR-NF Functions at
LANL ............................................................................................................................. 32
Option 4. Build a Building Combining PF-4 and CMRR-NF Functions at Another
Site ................................................................................................................................. 33
Option 5. Refurbish the Chemistry and Metallurgy Research (CMR) Facility ................. 33
Options 6-12 Overview: Matching Plutonium Tasks to Buildings.................................... 34
Option 6: Conduct Plutonium-238 Work at INL or SRS ................................................... 36
Option 7: Conduct Some or All Analytical Chemistry at LLNL or SRS........................... 39
Option 8. Use RLUOB As Is for Analytical Chemistry, with PF-4 Conducting the
Balance of Pit Work ....................................................................................................... 43
Option 9. Convert RLUOB to Hazard Category 3 for Analytical Chemistry.................... 43
Option 10. Use RLUOB, with Regulatory Relief, for Analytical Chemistry, with
PF-4 Conducting the Balance of Pit Work ..................................................................... 45
Option 11. Build a Copy of RLUOB Minus the Office, with Regulatory Relief,
for Analytical Chemistry, with PF-4 Conducting the Balance of Pit Work .................... 50
Option 12. Build Modules Connected to PF-4 for High-MAR Plutonium Work.............. 51
Making RLUOB/PF-4 Options Safer and More Efficient ....................................................... 53
Increasing Safety ............................................................................................................... 53
Increasing Efficiency......................................................................................................... 60
Gathering Information on Various Options.................................................................................... 61
Concluding Observations............................................................................................................... 62
Congressional Research Service
U.S. Nuclear Weapon “Pit” Production Options for Congress
Figures
Figure 1. Relationship Between National Goals and Pit Production Infrastructure ........................ 1
Figure 2. Plutonium-238 ................................................................................................................ 10
Figure 3. Chemistry and Metallurgy Research Building ............................................................... 15
Figure 4. PF-4 and TA-55 .............................................................................................................. 16
Figure 5. Radiological Laboratory/ Utility/Office Building .......................................................... 17
Figure 6. Air Filters in RLUOB ..................................................................................................... 18
Figure 7. Building CPP-1634......................................................................................................... 37
Figure 8. H Canyon and HB-Line .................................................................................................. 39
Figure 9. Building 332 ................................................................................................................... 41
Figure 10. F/H Laboratory ............................................................................................................. 42
Figure 11. Volume of Weapons-Grade Plutonium Allowed in RLUOB ........................................ 44
Figure 12. A Gas Gun in PF-4........................................................................................................ 45
Figure 13. Seismic Bracing of Office Buildings ............................................................................ 55
Figure 14. Notre Dame Cathedral .................................................................................................. 55
Figure 15. A Base-Isolation System ............................................................................................... 56
Figure 16. Progressive Strengthening of Gloveboxes and Open-Front Hoods .............................. 57
Tables
Table 1. Hazard Categories and Radiological Facilities ................................................................ 11
Table 2. Matching Plutonium Tasks to Buildings .......................................................................... 34
Table B-1. Sample Calculation for Deriving Dose Values for RLUOB ........................................ 68
Table B-2. Dose from a Plutonium Spill and Fire in RLUOB ....................................................... 70
Table C-1. Security and Hazard Categories for Plutonium ............................................................ 72
Table F-1. Space for Plutonium Analytical Chemistry in Three Scenarios ................................... 81
Appendixes
Appendix A. The Regulatory Structure.......................................................................................... 66
Appendix B. Calculation of Dose as a Function of Material At Risk ............................................ 68
Appendix C. Security and Hazard Categories for Plutonium ........................................................ 72
Appendix D. Preliminary Outline of Potential Tasks Required for RLUOB to Exceed
Hazard Category 3 Nuclear Facility Threshold Quantity ........................................................... 73
Appendix E. Comparison of Seismic Resiliency of CMR and RLUOB ....................................... 80
Appendix F. Space Requirements for Analytical Chemistry to Support Production of 80
Pits Per Year................................................................................................................................ 81
Congressional Research Service
U.S. Nuclear Weapon “Pit” Production Options for Congress
Appendix G. Abbreviations ............................................................................................................ 82
Contacts
Author Contact Information........................................................................................................... 83
Acknowledgments ......................................................................................................................... 83
Congressional Research Service
U.S. Nuclear Weapon “Pit” Production Options for Congress
Introduction
Of all the problems facing the nuclear weapons program and nuclear weapons complex over the
past several decades, few, if any, have been as vexing as pit production. A “pit” is a hollow
plutonium shell that is imploded, creating an explosion that triggers the rest of the weapon. The
Rocky Flats Plant (CO) manufactured pits on a large scale during the Cold War until production
halted in 1989. It took until FY2007 for the United States to produce even a small quantity, 11
pits per year (ppy), for the stockpile.1 Yet the Department of Defense (DOD) calls for a capacity
to produce 30 ppy by 2021 as an interim goal and 50 to 80 ppy by around 2030. At issue is how to
reach the higher capacity.
This report is intended primarily for Members and staff with a direct interest in pit issues,
including Members who will be making decisions on pit projects that could total several billion
dollars. Since the issues are complicated, this report contains technical and regulatory details that
are needed to understand the advantages, drawbacks, and uncertainties of various options. It may
also be of value for Members and staff with an interest in nuclear weapons, stockpile stewardship,
and nuclear policy more broadly. This report begins with a description of plutonium, pits, and pit
factory problems. It next considers several pit production options. It notes studies that could
provide information to assist Congress in choosing among options, and concludes with several
observations. There are several Appendixes, including a list of abbreviations.
The pit issue is important because of the
Figure 1. Relationship Between National
relationship between pit production
Goals and Pit Production Infrastructure
infrastructure and national goals, as shown in
GOALS
Figure 1. National goals include minimizing
the risk of nuclear war and, for the longer
POLICIES
term, “the peace and security of a world
STRATEGIES
without nuclear weapons,” as President
2
Obama declared in his 2009 Prague speech.
DELIVERY SYSTEMS
The Nuclear Posture Review sets out policy
WEAPONS
objectives, such as “preventing nuclear
proliferation,” “reducing the role of U.S.
PITS
nuclear weapons in U.S. national security
INFRA
strategy,” “maintaining strategic deterrence
and stability at reduced nuclear force levels,”
Source: CRS.
“strengthening regional deterrence,” and
Note: “Infrastructure” is abbreviated as “infra.”
“sustaining a safe, secure, and effective
nuclear arsenal.”3 Various strategies, such as
deterrence, counterproliferation, and arms control, seek to implement policy. In turn, delivery
systems, such as heavy bombers and long-range ballistic missiles, are one means of implementing
strategy. Nuclear weapons (a term used in this report to refer to nuclear bombs and warheads) arm
delivery systems. The Nuclear Posture Review declares, “The United States will not develop new
1
Information provided by Los Alamos National Laboratory, email, November 13, 2013.
U.S. White House. Office of the Press Secretary. Remarks by President Barack Obama, Hradcany Square, Prague,
Czech Republic, April 5, 2009, http://www.whitehouse.gov/the-press-office/remarks-president-barack-obama-praguedelivered.
3
U.S. Department of Defense. Nuclear Posture Review Report, April 2010, p. iii, http://www.defense.gov/npr/docs/
2010%20nuclear%20posture%20review%20report.pdf.
2
Congressional Research Service
1
U.S. Nuclear Weapon “Pit” Production Options for Congress
nuclear warheads.”4 Accordingly, the United States will retain the weapons in its arsenal for the
foreseeable future. Yet weapons deteriorate over time. Extending the service life of existing
weapons requires replacing or modifying some components. While “life extension programs”
(LEPs) for some weapons can use existing pits, DOD and the Department of Energy (DOE) state
that LEPs for other weapons will require newly manufactured pits. The current infrastructure
cannot produce pits at the capacity DOD requires, and many efforts stretching back to the late
1980s to produce pits have been canceled or have otherwise foundered. A concern is that if a type
of nuclear weapon could no longer perform satisfactorily, an inability to make new pits in the
quantities required so the weapons could be replaced could lead to that weapon type being
removed from service. That, in turn, would leave missiles and bombers without those weapons,
which would undermine strategies, the policies they seek to implement, and the ability to attain
national goals.
Background
This section begins by discussing plutonium, pits, pit production, programs to extend the service
life of nuclear weapons, and production capacity required. It next turns to current plutonium
facilities and provides a brief history of unsuccessful efforts to build a facility to produce pits on a
scale larger than about 10 per year. It concludes by presenting important regulatory terms.
Technical Aspects
Plutonium
Plutonium is a radioactive metal that is 1.75 times more dense than lead. It has several
undesirable characteristics, and is difficult to work with. According to Siegfried Hecker, a
plutonium metallurgist and a former director of Los Alamos National Laboratory (LANL),
Plutonium is an element at odds with itself—with little provocation, it can change its density
by as much as 25 percent; it can be as brittle as glass or as malleable as aluminum; it expands
when it solidifies; and its freshly-machined silvery surface will tarnish in minutes, producing
nearly every color in the rainbow. To make matters even more complex, plutonium ages
from the outside in and from the inside out. It reacts vigorously with its environment—
particularly with oxygen, hydrogen, and water—thereby, degrading its properties from the
surface to the interior over time. In addition, plutonium’s continuous radioactive decay
causes self-irradiation damage that can fundamentally change its properties over time.5
To make plutonium more stable, it is typically alloyed with other materials, such as gallium.6
Handling and safeguarding plutonium poses significant risks. Plutonium is hazardous: if minute
particles are inhaled and lodge in the lungs, their radiation (in the form of alpha particles) can
cause lung cancer. In addition, terrorists might be able to build an improvised nuclear device if
4
Ibid., p. 39.
Siegfried Hecker, “Plutonium and Its Alloys: From Atoms to Microstructure,” Los Alamos Science, vol. 26 (2000), p.
291, http://www.fas.org/sgp/othergov/doe/lanl/pubs/00818035.pdf. For additional information on plutonium, see
Argonne National Laboratory, Environmental Science Division, “Plutonium,” Human Health Fact Sheet, August 2005,
2 p., http://www.evs.anl.gov/pub/doc/Plutonium.pdf.
6
“The Plutonium Challenge,” Los Alamos Science, no. 26, 2000, p. 25.
5
Congressional Research Service
2
U.S. Nuclear Weapon “Pit” Production Options for Congress
they were to obtain enough plutonium, so facilities holding more than a small quantity of certain
plutonium isotopes require extremely high security.
Plutonium does not occur in nature except in trace amounts. It is manufactured by exposing
uranium fuel rods to neutrons in nuclear reactors, and then using chemical processes to separate it
from other elements in the fuel rods. The result is a mix of plutonium isotopes. The isotope
desired for nuclear weapons is plutonium-239, which fissions readily when struck by slow or fast
neutrons. Weapons-grade plutonium (WGPu) consists mainly of plutonium-239 and a small
fraction of other plutonium isotopes. (Note: When an isotope of plutonium is mentioned, such as
plutonium-239, it is abbreviated using its chemical symbol, e.g., Pu-239.)
Pits
A pit is the trigger for detonating a thermonuclear weapon, or hydrogen bomb. It is a hollow shell
of plutonium and other materials surrounded by chemical explosives. When the explosives
detonate, they create an inward-moving pressure wave (an implosion wave) that compresses the
plutonium enough to make it supercritical. It undergoes a runaway fission chain reaction, that is,
an explosion. Various means are used to augment the explosion. This part of the weapon is called
the primary stage. The weapon is designed so that energy from the primary stage explosion
implodes the weapon’s secondary stage, in which nuclear fission and fusion release most of the
weapon’s total explosive force.
While some pits in older weapons were made of uranium and plutonium (“composite pits”),
modern pits use only plutonium because much less of that material is required to generate a given
explosive force, permitting nuclear weapons to be smaller and lighter. Reducing the size and
weight of weapons was important during the Cold War to maximize the number of weapons that
could be fitted on a missile and to maximize the explosive force of a weapon of given weight. All
nuclear weapons in the current U.S. nuclear stockpile were designed and tested during the Cold
War; all but a handful were built during that time.
Because plutonium decays radioactively, there was concern that pits could deteriorate in ways
that would cause them to fail. However, several studies have projected increased pit life. In 2003,
pit life was thought to be 45-60 years;7 a 2007 study placed life for most pits at over 100 years;8
and a 2012 Livermore study placed the figure at 150 years.9 A 2013 Los Alamos study raised
uncertainties on the latter claim:
Since 2006, plutonium aging work has continued at a low level. That research does not
indicate any [e]ffects that would preclude the possibility of pit reuse. However, additional
studies that had been planned were never undertaken, leaving some aging questions
unanswered for the range of plutonium alloys in the stockpile, and for the potential
applications of pit reuse now under consideration.10
7
U.S. Department of Energy. National Nuclear Security Administration, Draft Supplemental Programmatic
Environmental Impact Statement on Stockpile Stewardship and Management for a Modern Pit Facility, Summary
volume, DOE/EIS-236-S2, Washington, DC, May 2003, pp. S-12, http://energy.gov/sites/prod/files/EIS-0236-S2DEIS-Summary-2003_1.pdf.
8
R.J. Hemley et al., Pit Lifetime, The MITRE Corporation, JASON Program Office, JSR-06-335, McLean, VA,
January 11, 2007, p. 1, http://www.fas.org/irp/agency/dod/jason/pit.pdf.
9
Arnie Heller, “Plutonium at 150 Years: Going Strong and Aging Gracefully,” Science & Technology Review,
December 2012, pp. 12, 14, https://str.llnl.gov/Dec12/pdfs/12.12.2.pdf.
10
David Clark, “Summary Remarks on Plutonium Aging,” LA-UR-13-27541, September 2013, p. 1.
Congressional Research Service
3
U.S. Nuclear Weapon “Pit” Production Options for Congress
Penrose Albright, then Director of Lawrence Livermore National Laboratory, testified in 2013,
And there has been a pretty concerted effort at both Los Alamos and at Livermore over the
last decade or more that has been looking at plutonium aging, and we actually have samples
that we keep in our laboratory—and Los Alamos does the same—that are 40, 50, 60 years
old that so far show no—that support the conclusions that the last decade of study has
implied, which is that these pits are good for many, many more decades to come.11
Longer pit life means that a stockpile of given size can be maintained with a lower pit production
rate and opens the possibility of reusing retired pits.
The Pit Production Process
Pits must be made to exacting standards in order to function as designed. This requires precision
in fabricating them and in supporting tasks.
As plutonium decays, it produces other elements, such as americium. That radioactive element
increases the radiation dose to workers and is an impurity to weapons-grade plutonium.
Plutonium scrap, such as from old pits or from faulty castings, may pick up other impurities.
Accordingly, plutonium must be purified for use in new pits. This may involve nitric acid
processing, high-temperature processing, electrorefining, and other processes.12 Such processes
result in a substantial stream of waste contaminated with radioactive material, acid, and other
harmful substances. This waste must be processed and disposed of; waste processing requires a
substantial infrastructure.
Pits are fabricated as “hemishells” (half-pits) that are welded together. Rocky Flats Plant made
pits using a wrought process, in which sheets of plutonium were run through rollers to attain the
desired thickness, then punched into a die. LANL, where pits are currently made, uses a cast
process, in which plutonium is melted in crucibles in a foundry, poured into a mold, and finished.
The plutonium is analyzed chemically, and each hemishell is inspected through such techniques
as physical measurements and x-ray imaging to ensure that there are no flaws. Given the many
steps required, it typically takes three months to make a pit.
Various tasks support production. Materials characterization (MC) examines bulk properties of
plutonium samples, such as tensile strength, magnetic susceptibility, and surface characteristics.
Such properties must be determined to be correct to assure that a pit will, for example, implode
symmetrically. MC is generally used to qualify manufacturing processes and to troubleshoot
production problems. As such, it does not generate a large number of samples during production,
and that number is largely independent of the number of pits to be produced. Of relevance to
options considered below, MC does not require a large amount of laboratory floor space.
In contrast, analytical chemistry (AC) is performed across the entire manufacturing process, from
metal purification through waste processing.13 Samples are analyzed for isotopic composition of
11
U.S. Congress, Senate Committee on Armed Services, Subcommittee on Strategic Forces, Hearing to Receive
Testimony on National Nuclear Security Administration Management of Its National Security Laboratories in Review
of the Defense Authorization Request for Fiscal Year 2014 and the Future Years Defense Program, 113th Cong., 1st
sess., May 7, 2013, committee transcript, p. 14, http://www.armed-services.senate.gov/Transcripts/2013/05%20May/
13-36%20-%205-7-13.pdf.
12
David Clark et al., “Plutonium Processing at Los Alamos,” Actinide Research Quarterly, 3rd Quarter 2008, pp. 6-16.
13
Information in this paragraph and the next paragraph was provided by Los Alamos National Laboratory, telephone
(continued...)
Congressional Research Service
4
U.S. Nuclear Weapon “Pit” Production Options for Congress
plutonium and for the type and amount of various impurities. AC is performed on an average of
22 samples per pit. Metal samples taken directly from hemishells are typically 5 grams each. In
preparing for AC, these samples are cut into smaller pieces. Most of the smaller pieces are
dissolved in acid because most AC instruments do not use samples in solid form. The resulting
plutonium-acid mixture is split into still smaller samples, many of which contain milligram or
microgram quantities of plutonium. Each sample must be prepared in a specific way, and
analyzed using specific equipment, depending on the type of analysis that it is to undergo. In
addition, before plutonium ingots are used for a hemishell, their purity must be assayed. This
involves taking a sample from a piece of the purified product as well as plutonium standard and
reference materials for comparison. In order to provide one assay result for the plutonium, the
assay process is typically run 10 times.
Pit fabrication generates waste, such as the plutonium-acid samples used in AC, the MC samples,
and any shavings or trimmings from finishing hemishells. Accordingly, pit production requires a
way to handle the waste. It is treated two ways at Los Alamos; in some cases by extracting
plutonium, and in other cases by solidifying it for burial at the Waste Isolation Pilot Plant (WIPP)
(NM).
Life Extension Programs
While pits may last for many decades, other weapon components do not. Weapons contain
organic components like explosives and adhesives that deteriorate under the influence of heat and
radiation given off by plutonium; they may change characteristics over time. Some components,
such as electronics, become hard to support after several decades, would be even harder to
support several decades from now, and would be difficult to make compatible with new delivery
systems like aircraft. Beyond that, some in the National Nuclear Security Administration (NNSA)
and DOD want to increase the surety (safety, security, use control, and use denial) of weapons.
(NNSA is the semiautonomous DOE agency responsible for nuclear weapons maintenance,
several nuclear nonproliferation programs, and all naval nuclear propulsion work.) Accordingly,
the Nuclear Weapons Council, a joint DOD-NNSA body that oversees and coordinates nuclear
weapon programs, plans a life extension program (LEP) for each weapon type, including some
LEPs that may combine two or more weapon types. LEPs range in scope from replacing a few
components to a major overhaul that includes new pits, new electronics, and new surety features.
Some dispute the need for LEPs that do more than the minimum needed to keep a weapon in
service. They argue, for example, that features to further enhance surety are unnecessary given
the perfect safety record of U.S. nuclear weapons and that these features add greatly to cost and
may impair weapon performance. Nonetheless, LEPs are underway for the W76 warhead for the
Trident II submarine-launched ballistic missile and the B61 bomb, and both Congress and the
Administration support them. Additional LEPs are being planned.
Pit Production Capacity: How Much Is Needed?
Some LEPs can use the original pit and replace other components, while other LEPs might reuse
pits from retired weapons if that proves feasible, and still other LEPs are expected to require
fabrication of new pits. U.S. policy, as stated in the Nuclear Posture Review, is specific on its
preference among these choices:
(...continued)
conversations, notes, and emails, June-August 2013.
Congressional Research Service
5
U.S. Nuclear Weapon “Pit” Production Options for Congress
The United States will study options for ensuring the safety, security, and reliability of
nuclear warheads on a case-by-case basis, consistent with the congressionally mandated
Stockpile Management Program. The full range of LEP approaches will be considered:
refurbishment of existing warheads, reuse of nuclear components from different warheads,
and replacement of nuclear components.
In any decision to proceed to engineering development for warhead LEPs, the United States
will give strong preference to options for refurbishment or reuse. Replacement of nuclear
components would be undertaken only if critical Stockpile Management Program goals
could not otherwise be met, and if specifically authorized by the President and approved by
Congress.14
The need for new “nuclear components,” pits in this case, drives pit capacity requirements.
However, the pit production capacity considered has varied greatly, from 10 to 450 pits per year.
The Nuclear Weapons Council has decided that, to meet the likely demands of future LEPs, a
production capacity of 50 to 80 ppy is needed. Andrew Weber, Assistant Secretary of Defense for
Nuclear, Chemical, and Biological Defense Programs, testified in April 2013 that “there is no
daylight between the Department of Energy and the Department of Defense on the need for both a
near-term pit production capacity of 10 to 20 and then 30 by 2021, and then in the longer term for
a pit production capacity of 50 to 80 per year.”15
While this range of pit production drives the planning for the U.S. plutonium strategy, it is not a
precise range based on a careful analysis of military requirements. When asked to explain the
basis for this range, Linton Brooks, former Administrator of NNSA, and John Harvey, then
Principal Deputy Assistant Secretary of Defense for Nuclear, Chemical, and Biological Defense
Programs, responded:
MR. HARVEY: We established that requirement back in 2008 for a capability to produce in
the range of 50 to 80 per year. That evolved from a decision to basically not take the path
that we originally were taking with the Modern Pit Facility, but to go and be able to exploit
the existing infrastructure at Los Alamos to meet our pit operational requirements. The
capability at Los Alamos was assessed to be somewhere in the range of 50 to 80 per year that
they could get with the modernization program they anticipated. The Nuclear Weapons
Council looked at that number. It’s a capacity-based number, and said it’s probably good
enough. We’ll have to accept some risk, but it’s probably good enough.
MR. BROOKS: So you can’t tie it to a specific – you can’t tie it to a specific deployment
schedule or something. It’s a judgment that is a combined judgment on yeah, you can
probably do this, and yeah in the most reasonable world this will be enough.
MR. MEDALIA: But there’s a big difference in the facilities, between 50 and 80. Is it 80 or
is it 50 to 80?
MR. HARVEY: We understood that the capability to deliver, based on the anticipated
modernization at Los Alamos which would include the CMRR or equivalent, coupled with
the PF-4 production, appropriately reconfigured, could deliver in that range. So it was a
14
U.S. Department of Defense. Nuclear Posture Review Report, April 2010, p. 39.
Testimony of Andrew Weber, Assistant Secretary of Defense for Nuclear, Chemical, and Biological Defense
Programs, in U.S. Congress. Senate. Committee on Armed Services. Subcommittee on Strategic Forces. Hearing to
Receive Testimony on Nuclear Forces and Policies in Review of the Defense Authorization Request for Fiscal Year
2014 and the Future Years Defense Program, April 17, 2013, p. 15.
15
Congressional Research Service
6
U.S. Nuclear Weapon “Pit” Production Options for Congress
range. I mean, it’s always been cited as single shift range. By going to double shifts you
could probably get the higher end of that range.
MR. BROOKS: But no person now living can tell you for sure the answer to that question. I
mean, you know, beware of spurious precision. … Fifty to 80 is probably as precise as the
facts will allow people to be, although people will say other things.16
NNSA was also imprecise as to required production capacity. It stated in a 2013 report,
“Preliminary plans call for pit production of potentially up to 80 pits per year starting as early as
FY 2030. NNSA continues to develop options to achieve a higher production rate as part of the
plutonium strategy.”17 John Harvey subsequently added, “The level of 50-80 ppy was consistent
with existing PF-4 production capacity plus the analytical chemistry capacity anticipated for the
planned CMRR-NF. However, NNSA officials in 2006 believed that a capacity in the range of
125 ppy was needed to respond to anticipated requirements and provide some resilience to
surprise. Thus the 50-80 ppy level, while the best that could be done, accepted significant risk in
their view.”18
It may be possible to reduce the capacity required below 80 ppy and still meet DOD’s
requirements. This might be done in several ways:
•
One option under serious study is reusing retired pits in LEPs. Whether this could
be done for a particular LEP depends on details of the LEP, whether there are
suitable pits available, and whether such pits are available in the quantity
required; decisions would have to be made on a case-by-case basis.
•
In some LEPs, it may be possible to simply reinstall a weapon’s original pit.
Neither that method nor reuse of retired pits from other weapons require AC or
foundry work. By producing new pits while another LEP is underway with
retired or original pits, LANL could use its otherwise-unused capacity to produce
pits ahead of schedule for a LEP requiring new pits. Stockpiling new pits would
enable lower rates of production and of AC to produce the aggregate number of
pits needed by the time they are needed, even if the maximum production rate
attainable is less than 80 ppy. In addition, keeping the pit production and support
line in continuous operation would be useful if not essential for maintaining
processes, equipment, and worker skills, and for training new workers. On the
other hand, LEPs require considerable planning and design work, and designs for
new pits would have to be certified. In the near term, it might not be possible to
do this work far enough in advance to permit continuous production.
•
Since the figure of 80 ppy was based on LANL’s presumed pit production
capacity using PF-4 and CMRR-NF (an existing building and one that has been
16
Reserve Officers Association, Air Force Association and National Defense Industrial Association Capitol Hill
Breakfast Forum with Linton Brooks, Senior Adviser at the Center for Strategic and International Studies; and John
Harvey, Principal Deputy Assistant Secretary of Defense for Nuclear, Chemical and Biological Defense Programs, on
“The Nuclear Infrastructure Challenge And Deterrence Implications,” June 13, 2013, http://secure.afa.org/HBS/
transcripts/2013/June%2013%20-%20Brooks.pdf. CMRR refers to the Chemistry and Metallurgy Research
Replacement Nuclear Facility, which has been deferred for at least five years, and PF-4 is the building in which pits are
currently manufactured; see ““Existing Buildings at Los Alamos for Plutonium Work.”
17
U.S. Department of Energy. National Nuclear Security Administration. Fiscal Year 2014 Stockpile Stewardship and
Management Plan, Report to Congress, June 2013, page 2-22.
18
Personal communication, January 19, 2014.
Congressional Research Service
7
U.S. Nuclear Weapon “Pit” Production Options for Congress
deferred for at least five years), not on a strategic analysis of military needs, and
since the range cited is 50 to 80 ppy, a capacity of less than 80 ppy might suffice.
The Union of Concerned Scientists stated regarding required pit production capacity:
If pits last 150 years or more, there is no need to replace aging pits for the foreseeable future,
and no rationale for expanding production capacity beyond the existing 10 to 20 annually for
this purpose. Even if the NNSA finds that pits will last only 100 years and that all need to be
replaced by 2089, production capacity of 50 per year would be adequate.
The NNSA could replace all existing pits by 2089 if it started doing so in 2019, based on the
agency’s conservative assumption that the U.S. stockpile will remain at 3,500 warheads.
However, the United States is likely to reduce its arsenal in coming decades. In that case, the
NNSA could either wait longer to begin producing replacement pits … or reduce the annual
rate of production. …
Thus, even under the most conservative assumptions about pit lifetime and arsenal size, there
is no need to expand pit production capacity beyond 50 per year to replace aging pits.
Because both pit lifetime and the future size of the arsenal are uncertain, it makes no sense to
expand production capacity until it is needed.19
In contrast, John Harvey argues that there is risk in not providing margin to accommodate
unknowns:
Required pit production capacity cannot be based solely on known LEP requirements. We
must consider the possibly of surprise: either technical problems in the stockpile that arise
unexpectedly or geopolitical reversals. For example, we cannot anticipate at this point a need
to increase stockpile size based on renewed threats, but we should not rule out that
possibility in setting our pit production needs. Some reserve production capacity is required
above and beyond known LEP needs to ensure we have some ability to respond to surprise.
This is entirely consistent with the President’s NPR [Nuclear Posture Review] vision for a
responsive nuclear infrastructure. The longer we wait on achieving needed capacity, the
greater the risk we are accepting in not having responsive capabilities.20
It could be argued that an ability to meet the higher requirement—the most challenging case—
would enable the United States to meet lower requirements and would put this nation in a better
position to meet higher requirements should that be deemed necessary. Further, if 80 ppy proves
unattainable, an effort to reach that goal might increase the likelihood that this nation could reach
50 ppy, the lower end of the range.
On the other hand, it could be argued that it is not desirable to have a goal of 80 ppy if that is
excess to needs. According to Greg Mello, Executive Director of Los Alamos Study Group,
It is not clear that efforts to reach a larger pit production capacity will enable lesser pit
production capacities. History shows that efforts to acquire pit production capacity above
that which is clearly needed, have failed. Facilities to support a larger-than-needed pit
production capacity cost more for construction and operation than smaller facilities, and are
19
Lisbeth Gronlund et al., Making Smart Security Choices: The Future of the U.S. Nuclear Weapons Complex, Union
of Concerned Scientists, October 2012, p. 12, http://www.ucsusa.org/assets/documents/nwgs/nuclear-weaponscomplex-report.pdf.
20
Personal communication, January 19, 2014.
Congressional Research Service
8
U.S. Nuclear Weapon “Pit” Production Options for Congress
more likely to encounter political objections. So trying for 80 pits per year may decrease the
probability of successfully acquiring 50 pits per year, and trying for 50 pits per year may
decrease the probability of achieving 30 pits per year. It may be far better to acquire the
minimum necessary pit production capacity, and include a contingency plan that can be
activated should conditions warrant.21
Because of concern over required pit production capacity, Section 3147 of the FY2013 National
Defense Authorization Act, P.L. 112-239, directed the Secretary of Defense, in coordination with
the Secretary of Energy and the Commander of the U.S. Strategic Command, to “assess the
annual plutonium pit production requirement needed to sustain a safe, secure, and reliable nuclear
weapon arsenal.” The accompanying Joint Explanatory Statement of the Committee of
Conference states that the assessment shall include “an assessment of cost and national security
implications for various smaller and larger pit production rates from the current 50-80 pit
requirement. The conferees note that rates including 10 to 20 pits per year, 20 to 30 pits per year,
30 to 50 pits per year, 50 to 80 pits per year, and larger should be included as part of the
analysis.”22 Note that reducing required capacity would reduce facility requirements and might
permit delaying facility construction.
The purpose of this report, however, is not to address contending arguments on the capacity
needed, but to discuss options for acquiring the maximum capacity DOD states that it needs, 80
ppy, by 2030. Even if in 16 years it turns out that a lower capacity would suffice, it is difficult at
best to know that so far in advance.
The difference between 50 and 80 ppy has consequences. As discussed above, the Nuclear
Weapons Council reasoned that a capacity to build 50 ppy in single-shift operations could be
scaled up to produce 80 ppy in double-shift operations, that is, double-shift operations can
produce 1.6 times as many pits as single-shift operations. But if the actual need is 50 ppy, then by
using the same ratio, a capacity to build approximately 30 ppy in single-shift operations could be
scaled up to 50 ppy by using two shifts. Deploying and operating a smaller capacity would be less
costly and easier to implement.
21
Personal communication, December 16, 2013.
U.S. Congress. House. Committee on Armed Services. National Defense Authorization Act for Fiscal Year 2013.
Conference report to accompany H.R. 4310. 112th Congress, 2nd Session, H.Rept. 112-705, December 18, 2012, p. 991.
22
Congressional Research Service
9
U.S. Nuclear Weapon “Pit” Production Options for Congress
Plutonium-238
Figure 2. Plutonium-238
Pu-238 is an isotope of plutonium. While it is
not used in pits, it figures prominently in
several pit production options presented later
in this report. It has very different properties
and applications than Pu-239. Pu-238 has a
much shorter half-life than Pu-239 (87.7 years
vs. 24,110 years), so is 275 times more
radioactive. Because of its intense
radioactivity, it is so hot that a lump of it
glows, as Figure 2 shows. This radioactivity
makes it useful in applications requiring a
long-lived power source. It is used to provide
heat to generate electricity for deep space
probes and for defense purposes. At the same
time, according to Los Alamos,
Source: U.S. Department of Energy,
Pu-238 is not desirable for using in pits
because it has a relatively short half-life
(87.7 years) and the associated decay
generates large amounts of heat in the material. Pu-238 is listed in the [DOE] Safeguards
Table (DOE 474.2) as attractiveness level D (Low-Grade Materials) because its half-life and
associated properties would make it extremely difficult to fabricate into a pit, handle, and
may cause problems for surrounding materials [in a nuclear weapon] such as electronics,
plastics, etc.23
Note: This figure shows a Pu-238 source glowing
under its own light.
Key Regulatory Terms
Statutes, regulations, DOE orders, etc., as described in Appendix A, use many terms. While they
are often technical and complicated, understanding several of them is essential for understanding
facilities, presented next, and options. Selected terms are presented here; they provide a basis for
discussing constraints on plutonium buildings, various ways to comply with these constraints, and
how the constraints might be modified.
Dose: The amount of ionizing radiation a person receives, measured in rem.
Rem: This is a unit of measure of the biological effects of all types of ionizing radiation on
people. One expert lists a dose of between 0 and 25 rem as having “no detectable clinical effects;
small increase in risk of delayed cancer and genetic effects,” a dose of 25 to 100 rem as “serious
effects on average individual highly improbable,” and for 100-200 rem “minimal symptoms;
nausea and fatigue with possible vomiting.”24 Note that cancer risks in exposed populations
generally increase with dose and number of people exposed.
23
Information provided by Los Alamos National Laboratory, email, November 4, 2013.
Dade Moeller, Environmental Health, revised edition, Cambridge, Harvard University Press, 1997, p. 250. There is
debate on the biological effects of very low levels of radiation. See CRS Report R41890, “Dirty Bombs”: Technical
Background, Attack Prevention and Response, Issues for Congress, by (name redacted), Appendix A, Technical
Background; and Dr. Y, “Once More into the Breach,” November 5, 2013, which contains links to various documents
in the debate, http://blogs.fas.org/sciencewonk/2013/11/breach/.
24
Congressional Research Service
10
U.S. Nuclear Weapon “Pit” Production Options for Congress
Plutonium-239 equivalent: Weapons-grade plutonium (WGPu) consists mainly of Pu-239 but
includes small quantities of other plutonium isotopes. Some are much more radioactive than
Pu-239, and there are many other radioactive substances. It is convenient to convert all
radioactive materials to a single standard for purposes of assessing the radiological hazard from a
building in the event of an accident. That standard is “plutonium-239 equivalent,” abbreviated as
Pu-239E in this report. Because WGPu is more radioactive than pure Pu-239, 1 gram (g) of
WGPu has the radioactivity of 1.49 g of Pu-239. Similarly, Pu-238 is very much more radioactive
than Pu-239; 1 g of Pu-238 has the radioactivity of 275 g of Pu-239.
Hazard Categories (HCs) and Radiological Facilities: Nuclear facilities are categorized in
several ways. One is by the hazard they could pose in the event of a major accident. HCs are
based on “the consequences of unmitigated releases of hazardous radioactive and chemical
material.”25 10 CFR 830, “Nuclear Safety Management,” Appendix A, “General Statement of
Safety Basis Policy,” divides these consequences into three categories; Table 1 also includes a
related category.
Table 1. Hazard Categories and Radiological Facilities
As Applicable to Plutonium
Hazard
Category
(HC)
Pu-239 Equivalent (g) a
building of this Hazard
Category is designed to hold
Description in 10 CFR 830
Comment
Applies to nuclear reactors,
not applicable to pits
1
N/A
Potential for “significant off-site
consequences”
2
≥2,610 g
Potential for “significant on-site
consequences beyond localized
consequences”
3
Less than HC-2, but >38.6 g
Potential for “only local
significant consequences”
Radiological
Facility
Less than HC-3
Not part of the Hazard
Category System
Source: Hazard Categories are based on an NNSA document, “Guidance on Using Release Fraction and
Modern Dosimetric Information Consistently with DOE STD 1027-92, Hazard Categorization and Accident Analysis
Techniques for Compliance with DOE Order 5480.23, Nuclear Safety Analysis Reports, Change Notice No. 1,”
Supplemental Guidance, NA-1 SD G 1027, November 28, 2011, http://nnsa.energy.gov/sites/default/files/nnsa/
inlinefiles/NNSA_Supp_Guide_1027.pdf. DOE STD 1027-92, Establishing Hazard Categories is required by 10
CFR 830 (Nuclear Safety Management), Subpart B (Safety Basis Requirements), Section 202(b)(3),
http://www.gpo.gov/fdsys/pkg/CFR-2011-title10-vol4/pdf/CFR-2011-title10-vol4-part830.pdf.
Notes: See Appendix C for additional details.
Hazard Categories are determined by the amount of Pu-239E a building is designed to hold; each
category has the potential for certain consequences in the event of a major accident. 10 CFR 830,
Appendix A, states that “the hazard categorization must be based on an inventory of all
radioactive materials within a nuclear facility.” The HC structure builds in a conservative feature:
“The final categorization is based on an ‘unmitigated release’ of available hazardous material. For
the purposes of hazard categorization, ‘unmitigated’ is meant to consider material quantity, form,
25
National Nuclear Security Administration, “Main Points of Draft Supplemental Directive: Alternative Hazard
Categorization Methodology for Compliance with 10 CFR 830, Nuclear Safety Management, Safety Basis
Requirements,” Rev. 0, 3/15/2010, p. 10.
Congressional Research Service
11
U.S. Nuclear Weapon “Pit” Production Options for Congress
location, dispersibility and interaction with available energy sources, but not to consider safety
features (e.g., ventilation system, fire suppression, etc.) which will prevent or mitigate a
release.”26 Hazard Categories apply to the design and construction of a building, not to its
operation. For example, a building intended to hold 5,000 g of Pu-239E must be designed to
HC-2 standards, while a building intended to hold 1,000 g of Pu-239E must be designed to HC-3
standards, which are less stringent.
Closely related, and central to some options discussed later in this report, is the category
“Radiological Facility.” A Radiological Facility holds less Pu-239E than an HC-3 building. It is
not part of the HC system because the amount of material is so small as to pose little threat; a
hospital, for example, might be a Radiological Facility. The Radiological Laboratory/Utility/
Office Building (RLUOB) figures in several options below and is discussed in “Existing
Buildings at Los Alamos for Plutonium Work.” As a Radiological Facility, HC standards limit it
to 38.6 g of Pu-239E, or 26 g of WGPu, far less than enough to perform the AC needed to support
production of 80 ppy.
Design Basis Earthquake (DBE): The DBE is used to set standards for the resilience to
earthquakes that buildings in various HCs must have. LANL provided the following information:
The design basis earthquake is defined as the ground motion that has an annual frequency of
4 x 10-4 or [once in] 2,500 years. This is the ground motion that structures, systems, and
components (SSCs) are designed for using national consensus codes and standards. This
approach would lead to a failure probability of the SSCs for loads associated with the design
basis ground motion of 1-2%. Using this approach it is also expected that at ground motion
associated with an annual frequency of 1 x 10-4, or [once in] 10,000 years, the failure
probability of the SSCs would be about 50%.27
Design Basis Accident (DBA): This is the accident scenario against which a nuclear facility must
be designed and evaluated. Each HC building is required to be built to survive a DBA, the worstcase accident that could plausibly affect the building. Because each building will face different
threats, the DBA is necessarily building-specific. For one building, the DBA might be a flood; for
another, an explosion of a nearby gas main; for a third, a tornado; and for a fourth, an earthquake.
For the plutonium buildings at Los Alamos, described next, the main threat is an earthquake, so
the DBA involves (1) an earthquake more powerful than the DBE that (2) collapses a building
and (3) starts a fire that involves all material at risk in the facility and (4) releases a certain
fraction of the plutonium into the air as plutonium oxide particles. The fraction, in turn, is based
on (1) the Airborne Release Fraction (ARF), the fraction of the MAR that the postulated fire
could release into the air; (2) the Leak Path Factor (LPF), the fraction of ARF that actually
escapes from the building into the air; some of it would be trapped, such as by the collapse of the
building; and (3) the Respirable Fraction (RF), the fraction of the plutonium oxide particles
released into the atmosphere that are of a size (3 microns or less) that could readily be inhaled and
lodge in the lungs, where they would cause biological damage and, quite possibly, lung cancers;
larger particles would fall to the ground or would be trapped in the nose. Other variables enter as
well; Appendix B discusses them in detail.
26
U.S. Department of Energy. National Nuclear Security Administration. “Guidance on Using Release Fraction and
Modern Dosimetric Information Consistently with DOE STD 1027-92, Hazard Categorization and Accident Analysis
Techniques for Compliance with DOE Order 5480.23, Nuclear Safety Analysis Reports, Change Notice No. 1,”
Supplemental Guidance, NA-1 SD G 1027, November 28, 2011, Attachment 1, page 1-2.
27
Information provided by Los Alamos National Laboratory, email, August 8, 2013.
Congressional Research Service
12
U.S. Nuclear Weapon “Pit” Production Options for Congress
The frequency of the DBA is much less than the frequency of the DBE because several steps must
occur for the DBE to result in the DBA. NNSA commented on this difference:
There is also margin in the assumed accident frequencies (e.g., once in 5,000 years); these
were based on the structural failure probabilities and did not consider other conditional
probabilities, such as the conditional probability of a large fire starting and growing within
the facility and progressively effecting and engaging all of the assumed material at risk; this
refinement would reduce the frequency of the event from once in thousands of years to once
in hundreds of thousands of years.28
The difference between DBE and DBA is crucial because the path from the one to the other can
be interrupted at many places and in many ways in order to reduce the probability of the DBA, as
discussed in “Increasing Safety,” below.
Radiological Facilities like RLUOB do not have a DBA and do not have to be designed to survive
a DBA because they have so little radioactive material, though, as discussed in Appendix E,
RLUOB was built (but not certified) to HC-3 standards. If RLUOB were to be converted to an
HC-3 building, it would need a DBA and might need structural and other upgrades to be able to
survive it. Appendix D describes some of the tasks needed to convert RLUOB to HC-3.
Material At Risk (MAR): DOE defines this term as “the amount of radioactive materials (in
grams or curies of activity for each radionuclide) available to be acted on by a given physical
stress.”29 For purposes of this report, it is a measure of the amount of plutonium that might be
dispersed in a DBA. Molten plutonium or plutonium shavings in a crucible that topples over in an
earthquake, spilling plutonium onto the floor, would be MAR because a fire would create
plutonium oxide particles, while plutonium in specially designed containers that are fire-resistant
and rugged enough to survive a building collapse would not face this risk and thus would not be
counted as MAR.
Maximally-exposed Offsite Individual (MOI) and other exposure standards: An MOI is a
hypothetical person located at the spot—outside the site boundary but nearest to a specific
building—where a member of the public could reasonably be, such as a dwelling or a public road.
The guideline set by DOE is that the MOI should receive a dose of no more than 25 rem for an
exposure of 2 hours (or up to 8 hours in certain situations). “The value of 25 rem TEDE [total
effective dose equivalent] is not considered an acceptable public exposure either. It is, however,
generally accepted as a value indicative of no significant health effects (i.e., low risk of latent
health effects and virtually no risk of prompt health effects).”30 To avoid “challenging” the 25rem dose, another DOE document sets the dose at 5 rem, and sets a guideline of 100 rem TEDE
for nearby (“collocated”) workers.31
28
Letter from Donald Cook, Deputy Administrator for Defense Programs, National Nuclear Security Administration, to
Peter Winokur, Chairman, Defense Nuclear Facilities Safety Board, January 30, 2012, Enclosure 1, pp. 3-4,
http://www.dnfsb.gov/sites/default/files/Board%20Activities/Letters/2012/ltr_2012130_18446_0.pdf.
29
U.S. Department of Energy. DOE Handbook: Airborne Release Fractions/Rates and Respirable Fractions for
Nonreactor Nuclear Facilities, Volume I - Analysis of Experimental Data, DOE-HDBK-3010-94, December 1994, p.
xix, http://www.orau.gov/ddsc/dose/doehandbook.pdf.
30
U.S. Department of Energy. DOE-STD-3009-94, July 1994, Change Notice No. 3, March 2006, “DOE Standard:
Preparation Guide for U.S. Department of Energy Nonreactor Nuclear Facility Documented Safety Analyses,”
Appendix A, “Evaluation Guideline,” p. A-2, http://www.hss.doe.gov/enforce/docs/std/DOE_STD_3009.pdf.
31
U.S. Department of Energy, DOE Standard: Integration of Safety into the Design Process, DOE-STD-1189-2008,
March 2008, pp. A-5, A-6.
Congressional Research Service
13
U.S. Nuclear Weapon “Pit” Production Options for Congress
Documented Safety Analysis (DSA): Once an HC-2 or HC-3 building is built, a DSA must be
prepared for it. A DSA is an agreement on how much MAR it can contain in order to stay within
the dose limits for a collocated worker (for an HC-3 building) or an MOI (for an HC-2 building).
The DSA MAR limit is typically less than the upper bound for an HC-3 building; for an HC-2
building, the DSA MAR limit is a specific figure because HC-2 sets no upper bound. For two
HC-2 buildings at LANL, CMR and PF-4, discussed below, the agreement is between NNSA and
Los Alamos National Security, LLC, the site contractor. The MAR permitted is building-specific
based on hazard analysis, including accident scenarios, and on multiple measures designed to
contain radioactive material in an accident. For CMR, the MAR permitted by the DSA is 9 kg of
Pu-239E; for the main floor of PF-4, the comparable figure is 2,600 kg.32 A DOE document
provides detailed standards for preparing a DSA.33 No DSA is required for a Radiological Facility
because MAR is so small that such facilities fall outside the Hazard Category system.
Security Category (SC): DOE places uranium and plutonium into SCs depending on their
attractiveness level, such as to terrorists. SC I and II pertain to facilities with Special Nuclear
Materials (SNM, mainly uranium highly enriched in the isotope 235 and plutonium) in quantities
or forms that would pose a severe threat if seized by terrorists. The highest level, SC-I, includes
assembled weapons and 2 kg or more of plutonium ingots. SC I and II require armed guards, a
special security fence, and similar measures. SC-IV requires much less security. It includes less
than 200 g of metallic plutonium and less than 3 kg of solutions of less than 25 g of plutonium
per liter. Table C-1 shows amounts of plutonium in various hazard and security categories.
Safety Class, Safety Significant: 10 CFR 830.3 defines safety class structures, systems, and
components (SSCs) as SSCs, “including portions of process systems, whose preventive and
mitigative function is necessary to limit radioactive hazardous material exposure to the public, as
determined from the safety analyses.” In contrast, safety significant SSCs “are not designated as
safety class structures, systems, and components, but whose preventive or mitigative function is a
major contributor to defense in depth and/or worker safety as determined from safety analyses.”
LANL added this explanation: “Safety-class systems must operate in conditions that otherwise
would result in an unacceptable risk (dose) to the public. Relative to the public, safety-significant
systems support safety-class systems with additional protections that might help in an accident,
but are not counted upon to do so.”34
Facility Aspects: Buildings to Support Pit Production
Existing Buildings at Los Alamos for Plutonium Work
The nuclear weapons complex (the “Complex”) consists of eight sites that maintain U.S. nuclear
weapons; during the Cold War, the Complex designed, developed, tested, and manufactured these
weapons. The Department of Energy (DOE) and its predecessor agencies used to own and set
policy for the Complex. Beginning in 2000, the National Nuclear Security Administration
(NNSA), a semiautonomous agency within DOE, took over these functions. Contractors operate
Complex sites at the direction of NNSA. One of these sites, Los Alamos National Laboratory
(LANL), has three buildings relevant to pits:
32
Information provided by Los Alamos National Laboratory, email, November 4, 2013.
U.S. Department of Energy. DOE-STD-3009-94, July 1994, Change Notice No. 3, March 2006, “DOE Standard:
Preparation Guide for U.S. Department of Energy Nonreactor Nuclear Facility Documented Safety Analyses.”
34
Information provided by Los Alamos National Laboratory, email, January 22, 2014.
33
Congressional Research Service
14
U.S. Nuclear Weapon “Pit” Production Options for Congress
Chemistry and Metallurgy Research (CMR) Building
This building was designed beginning in the late 1940s; most of it was completed by 1952, with
another part completed in the early 1960s. It was used mainly for plutonium R&D, and at present
provides AC and some MC to support pit production and all other plutonium missions in PF-4.
CMR is showing signs of age. In 2009, a congressional commission found that it and a uranium
processing building at the Y-12 National Security Complex are “genuinely decrepit and are
maintained in a safe and secure manner only at high cost.”35 In 2010, the staff of the Defense
Nuclear Facilities Safety Board (DNFSB), which monitors safety and health issues at the nuclear
weapons complex, “questioned CMR’s ability to detect promptly ventilation system failure, a
particularly important function given the system’s age and lack of local alarms to notify facility
workers.”36 In a 2010 report to Congress, DNFSB stated that CMR and Y-12 uranium processing
facilities “are structurally unsound and are unsuitable for protracted use.”37
CMR suffers from another problem. As Los
Alamos is on several seismic faults,
earthquakes pose the greatest threat to CMR.
It is not seismically robust. Its design, in the
late 1940s, gave little consideration to seismic
loads. Further, when it was constructed, there
was a steel shortage due to a steel strike and
the Korean War. To save on steel, each
concrete beam in CMR is reinforced with
only two steel reinforcing rods, which are of
different diameters, while the concrete floor
between the beams is 2 to 4 inches thick,
reinforced with chicken wire. A Los Alamos
Source: Los Alamos National Laboratory.
seismic expert calculates that, for CMR, “the
annual probability of failure [i.e., building collapse, is] somewhere between 1 in 370 years and 1
in 333 years.” This means that for ground motion that might be associated with an earthquake that
may occur approximately every 250 years, there is a 50% probability of collapse. This expert also
calculates that the probability that CMR would survive a Design Basis Earthquake, in this case
one occurring once in 2,500 years, is less than 0.2%.38 Another calculation using these data is that
CMR has a 1 in 36 chance of collapsing in 10 years. DNFSB arrived at a similar calculation:
Figure 3. Chemistry and Metallurgy
Research Building
Seismic fragility of building: There is a 1 in 55 chance of seismic collapse during a 10-year
timeframe, which would result in release of nuclear material and injury/death of facility
workers.
35
William Perry et al., America’s Strategic Posture, Congressional Commission on the Strategic Posture of the United
States, Washington, United States Institute for Peace Press, 2009, p. 50.
36
Defense Nuclear Facilities Safety Board, Staff Issue Report, “Chemistry and Metallurgy Research Facility
Documented Safety Analysis,” memorandum from C. Shuffler to T.J. Dwyer, Technical Director, September 1, 2010,
pp. 4-5, http://www.dnfsb.gov/sites/default/files/Board%20Activities/Reports/Staff%20Issue%20Reports/
Los%20Alamos%20National%20Laboratory/2010/sir_2010127_4969_65.pdf.
37
Defense Nuclear Facilities Safety Board, “Summary of Significant Safety-Related Infrastructure Issues at Operating
Defense Nuclear Facilities,” letter report to the Congress, September 10, 2010, p. 1, http://www.dnfsb.gov/sites/default/
files/Board%20Activities/Reports/Reports%20to%20Congress/2010/sr_2010910_4673.pdf.
38
Emails, September 17, September 27, and October 1, 2, and 10, 2013.
Congressional Research Service
15
U.S. Nuclear Weapon “Pit” Production Options for Congress
The Board is concerned that prolonged operations in the existing CMR facility pose a serious
safety risk to workers. In late 2010, the NNSA limited material-at-risk in the facility to
reduce the public dose consequence following an earthquake to a value below the Evaluation
Guideline of 25 rem.39
PF-4 (Plutonium Facility 4)
Figure 4. PF-4 and TA-55
Source: Los Alamos National Laboratory.
Notes: Technical Area 55 (TA-55) is the main area at
Los Alamos National Laboratory for plutonium work,
such as pit manufacturing, R&D, stabilizing of waste
for disposition, and nuclear forensics. The photo
shows most of TA-55. TA-55 includes PF-4, RLUOB,
and the site for the proposed CMRR-NF.
PF-4 is the nation’s main building for
plutonium work. It manufactures pits and
supports many other plutonium projects. It
produces Pu-238 heat sources for deep space
probes and defense purposes. It houses the
Advanced Recovery and Integrated
Extraction System (ARIES), which converts
the plutonium in pits into plutonium oxide for
use in mixed oxide nuclear reactor fuel.40 It is
the venue for pit surveillance, in which pits
from deployed weapons are returned to Los
Alamos for detailed inspection to search for
actual or potential problems. It used to
recover americium, a decay product of
plutonium, for use in smoke detectors and
industrial gauges, and is reestablishing that
capability. It conducts plutonium R&D.
DNFSB expressed concern about PF-4’s
vulnerability to an earthquake:
PF-4 was designed and constructed in the
1970s and lacks the structural ductility and redundancy required by today’s building codes
and standards. In 2007, a DOE-required periodic reanalysis of the seismic threat present at
the Los Alamos site was completed. It indicated a greater than fourfold increase in the
predicted earthquake ground motion. Total facility collapse is now considered a credible
event. … In response to this increased seismic threat, LANL undertook a series of actions to
improve the safety posture of PF-4.41
Radiological Laboratory/ Utility/Office Building (RLUOB)
Design of this building was completed in 2006. The building was completed in FY2010,42 office
operations began in October 2011, and laboratory operations are expected to start in 2014.43 As a
39
U.S. Defense Nuclear Facilities Safety Board. “Summary of Significant Safety-Related Aging Infrastructure Issues at
Operating Defense Nuclear Facilities.” Fourth Annual Report to Congress, Enclosure, p. E-2, emphasis in original;
http://www.dnfsb.gov/sites/default/files/Board%20Activities/Reports/Reports%20to%20Congress/2013/
ar_20131030_23051.pdf.
40
For further information on ARIES, see ”Aries Turns Ten,” full issue of Actinide Research Quarterly, Quarters 1 and
2, 2008, http://arq.lanl.gov/source/orgs/nmt/nmtdo/AQarchive/1st_2ndQuarter08/.
41
Defense Nuclear Facilities Safety Board, “Summary of Significant Safety-Related Infrastructure Issues at Operating
Defense Nuclear Facilities,” letter report to the Congress, September 10, 2010, p. 1, http://www.dnfsb.gov/sites/default/
files/Board%20Activities/Reports/Reports%20to%20Congress/2010/sr_2010910_4673.pdf
42
U.S. Department of Energy. Office of Chief Financial Officer. FY 2014 Congressional Budget Request, DOE/CF0084, April 2013, Volume 1, National Nuclear Security Administration, p. WA-267.
Congressional Research Service
16
U.S. Nuclear Weapon “Pit” Production Options for Congress
Radiological Facility, it is permitted to hold 26 grams (g) of WGPu. It has 19,500 square feet (sf)
of laboratory space, as compared to 22,500 sf of lab space planned for the Chemistry and
Metallurgy Research Replacement Nuclear Facility (CMRR-NF), a building planned but not
built, as described in “A Sisyphean History: Failed Efforts to Construct a Building to Restore Pit
Production,” below. RLUOB (pronounced “rulob”) was intended to conduct unclassified R&D on
plutonium and some AC in support of pit production; the latter amount was to be very small
because CMRR-NF was intended for that purpose. Nonetheless, the design of RLUOB is suitable
for AC because it uses open hoods instead of gloveboxes as in PF-4;44 hoods are more efficient
for most AC because it is much easier to work with small samples in them, but they require a
powerful ventilation system, which RLUOB has, as shown in Figure 6. Indeed, a LANL report
stated that “RLUOB has effectively perfect alignment with analytical chemistry activities.”45
Figure 5. Radiological Laboratory/
Utility/Office Building
While RLUOB was intended to be a
Radiological Facility, it was constructed to a
much higher standard than was required:
RLUOB was built as a “radiological-plus”
or robust radiological facility. The
engineering controls associated with
worker radiation protection are on par with
those inside of PF-4 and well in excess of
those in the 1950s-era CMR Building.
Additionally, the RLUOB uses modern
HEPA filtration, which protects the
Source: Los Alamos National Laboratory.
environment from a release of
contamination, and contains a state-of-the-art operations center for managing facility
operations including ventilation. In an overarching sense, the RLUOB was built with a focus
on the Nuclear Quality Assurance (NQA)-1 standard, which technically is only required for
hazard category 3 facilities, but was constructed as such to provide lessons-learned to aid in
constructing the CMRR-NF. However, despite its inherent robustness, the RLUOB does not
meet the standards established for either a hazard category 2 or 3 nuclear facility because it
was by design intended to work in conjunction with a hazard category 2 nuclear facility (the
CMRR-NF).46
RLUOB was designed to withstand the design basis earthquake (DBE), in this case an earthquake
anticipated to strike RLUOB once in 2,500 years. The force of the DBE was based on seismic
calculations made in 1995. Accordingly, it is more resilient to earthquakes than PF-4 was as
originally built, since PF-4 was designed to an earlier, less energetic DBE. (Upgrades have
(...continued)
43
Information provided by Los Alamos National Laboratory, email, December 11, 2013.
44
Hoods and gloveboxes are used to manipulate hazardous material, such as acid or plutonium. They contain
equipment, such as spectrometers for AC or crucibles for melting plutonium. They have negative air pressure so as to
prevent material from escaping into the lab room: air is drawn through the hood or glovebox and then exhausted
through a series of filters. A glovebox is a box with a transparent front panel and ports to which heavy gloves are
attached. It is supposed to be airtight. An open-front hood is open to the air; laboratory personnel manipulate material
using much thinner gloves than is the case for gloveboxes. It is more suitable for handling very small samples or
precise adjustment of equipment. Being open, a hood requires much more suction than does a glovebox to keep
material from leaking into the room. Figure 16 shows hoods and gloveboxes.
45
Brett Kniss and Drew Kornreich, “A Proposal for an Enduring Plutonium Infrastructure,” Los Alamos National
Laboratory, LA-CP-13-00728 (OUO), June 27, 2013, pp. 22-23. Note: While the report is Official Use Only, this
passage has been cleared for unlimited distribution.
46
Ibid. This passage has been cleared for unlimited distribution.
Congressional Research Service
17
U.S. Nuclear Weapon “Pit” Production Options for Congress
increased PF-4’s resiliency.) As detailed in Appendix E, Los Alamos estimates that “collapsing
RLUOB would take an earthquake with 4 to 12 times more force than an earthquake that would
collapse CMR.” However, the current DBE is more energetic than the 1995 DBE; it is unclear
what measures, if any, would be needed to strengthen RLUOB to withstand the current DBE.
Figure 6. Air Filters in RLUOB
Source: Los Alamos National Laboratory, October
23, 2013.
Notes: This photo shows a two-stage system in the
basement of RLUOB that is used to filter air from the
hoods and lab rooms on the laboratory floor. (A
separate exhaust system handles air from
gloveboxes.) It is essential to maintain “negative
pressure” (air pressure lower than that of the room)
in the laboratory rooms, hoods, and gloveboxes to
prevent fumes and particles from escaping. Multiple
exhaust systems are used to maintain negative
pressure. Air is drawn from the lab room into the
hoods and gloveboxes, then through small HEPA
(high-efficiency particulate air) filters in the hoods and
gloveboxes; these filters remove at least 99.975% of
any particles. The air is then drawn into the ductwork
and through large filters in the basement. The system
shown here consists of a first stage with pre-filters
(over 95% efficiency), which provides cooldown and
moisture separation, and a second stage with certified
HEPA (at least 99.95% efficiency) filters. This filtered
air is exhausted through a stack equipped with a
radiation monitor to verify compliance with the
Radiation National Emissions Standards for
Hazardous Pollutants permitting process. The total
air-handling capacity of the hood and glovebox
exhaust systems in RLUOB is 32,000 cubic feet per
minute.
A Sisyphean History: Failed Efforts
to Construct a Building to Restore Pit
Production
Beginning in 1952, the United States made
pits on a large scale at the Rocky Flats Plant
(CO), sometimes over 1,000 ppy. Operations
there halted in 1989 as a result of an FBI raid
investigating safety and environmental
violations. At that point, Rocky Flats was
producing pits for the W88 warhead to be
carried by Trident II submarine-launched
ballistic missiles, but W88 production was not
complete. DOE initially considered restarting
operations at Rocky Flats, but ultimately
decided not to. The United States has not had
the capacity to make more than about 10 ppy
since 1989.47
The history of efforts to restore pit production
capacity on a larger scale is voluminous. The
key takeaways from the brief summary that
follows are: (1) many projects have been
proposed over the years; (2) none has been
successfully completed; and (3) key
parameters, such as cost, schedule, proposed
facility site, and capacity, have changed from
one proposal to the next.
Complex 21
As the Cold War was winding down,
Congress, in Section 3132 of the National
Defense Authorization Act for FY1988 and
1989 (P.L. 100-180, December 4, 1987),
directed the President to conduct a study on
nuclear weapons complex modernization and
to “formulate a plan … to modernize the nuclear weapons complex by achieving the necessary
47
In 2007, Los Alamos produced 17 pits, but only 11 were “war reserve” pits, that is, accepted for use in the stockpile.
Of the others, some were scrap, and some were used for engineering tests and did not need to be qualified as war
reserve. Los Alamos could have made 10 ppy in subsequent years, but there was no DOD requirement for so doing. As
a result, in no other year did the total number of pits exceed 10. Information provided by Los Alamos National
Laboratory, email, November 12, 2013.
Congressional Research Service
18
U.S. Nuclear Weapon “Pit” Production Options for Congress
size and capacity determined under the study.” The report was submitted in January 1989, but as
Secretary of Energy James Watkins noted in January 1991,
dramatic world changes forced further reassessments of the future Nuclear Weapons
Complex.” A DOE report resulting from the reassessments “presents a plan to achieve a
reconfigured complex, called Complex-21. Complex-21 would be smaller, less diverse, and
less expensive to operate than the Complex of today. Complex-21 would be able to safely
and reliably support nuclear deterrent stockpile objectives set forth by the President and
funded by the Congress.48
In addition to a No Action alternative, the study proposed two Reconfiguration alternatives. One
would downsize existing sites and modernize them in place. “As an exception to the existing site
theme, the functions of the Rocky Flats Plant (RFP) would be relocated.” The second, “maximum
consolidation,” would
relocate RFP and at least one other NMP&M [Nuclear Materials Production and
Manufacturing] facility to a common location. The Pantex Plant and the Oak Ridge Y-12
Plant are candidates for collocation with the Rocky Flats functions, either singly or together.
… The probable outcome of this option would be an integrated site which could consolidate
much of the NMP&M elements at a single site.
As part of this effort, DOE would develop a Programmatic Environmental Impact Statement “to
analyze the consequences of alternative configurations for the Complex,” with completion of that
statement expected in early FY1994. “Complex-21 should be fully operational early in the 21st
century and will sustain the nation’s nuclear deterrent until the middle of that century.”49
What emerged was a two-pronged approach to restore pit production. After conducting an
environmental impact statement (EIS) process, DOE issued a Record of Decision (ROD) on
Stockpile Stewardship and Management in December 1996 that included reestablishing pit
production capability at PF-4 while raising the prospect of a larger-capacity facility.50 Los Alamos
would build a small number of pits for W88s so DOE could replace W88 pits destroyed in an
ongoing surveillance program that monitored their condition. Producing these pits, and certifying
them as “war reserve,” that is, meeting standards for use in the nuclear stockpile, took many
years; PF-4 produced its first war reserve W88 pits, 11 of them, in 2007. This small capacity
would also serve as a pilot plant for developing production techniques for a larger plant. Since the
total number of additional W88 pits required was small, about 30, there was no need for PF-4 to
achieve high manufacturing rates. Producing these pits and certifying them as war reserve without
nuclear testing was a major early challenge for the stockpile stewardship program.
Modern Pit Facility
The second prong was to build a facility able to produce large numbers of pits. This was the
Modern Pit Facility (MPF). NNSA approved Critical Decision 0 (mission need) for MPF in
48
U.S. Department of Energy. Nuclear Weapons Complex Reconfiguration Study, DOE/DP-0083, January 1991, cover
letter by Secretary of Energy James D. Watkins, Admiral, U.S. Navy (Retired), January 24, 1991.
49
Ibid., pp. 4-5.
50
Department of Energy, “Record of Decision: Programmatic Environmental Impact Statement for Stockpile
Stewardship and Management,” 61 Federal Register 68015, December 26, 1996, http://www.gpo.gov/fdsys/pkg/FR1996-12-26/pdf/96-32759.pdf.
Congressional Research Service
19
U.S. Nuclear Weapon “Pit” Production Options for Congress
FY2002. The capacity of MPF was left to be decided, for reasons a National Environmental
Policy Act (NEPA) document of May 2003 noted:
Classified studies have examined capacity requirements that would result from a wide range
of enduring stockpile sizes and compositions, pit lifetimes, emergency production needs
(referred to as “contingency” requirements), and facility full-production start dates. Although
the precise future capacity requirements are not known with certainty, enough clarity has
been obtained through these ongoing classified studies that the NNSA has identified a range
of pit production capacity requirements (125-450 ppy) that form the basis of the capacity
evaluations in this EIS. The EIS evaluates the impacts of a MPF designed to produce three
capacities: 125 ppy, 250 ppy, and 450 ppy. A pit lifetime range of 45-60 years is assumed.51
Congress initially supported MPF, but became increasingly concerned with the lack of study of
alternatives, a lack of clarity on the production capacity required, and uncertainty on pit aging and
pit life. Finally, Congress eliminated funds for MPF in the FY2006 budget cycle.
Consolidated Nuclear Production Center
Another effort to reconfigure the nuclear weapons complex began in 2004, when the House
Appropriations Committee sought to have DOE link the nuclear weapons stockpile with the
nuclear weapons complex that would support it:
During the fiscal year 2005 budget hearings, the Committee pressed the Secretary on the
need for a systematic review of requirements for the weapons complex over the next twentyfive years, and the Secretary committed to conducting such a review. The Secretary’s report
should assess the implications of the President’s decisions on the size and composition of the
stockpile, the cost and operational impacts of the new Design Basis Threat, and the
personnel, facilities, and budgetary resources required to support the smaller stockpile. The
report should evaluate opportunities for the consolidation of special nuclear materials,
facilities, and operations across the complex to minimize security requirements and the
environmental impact of continuing operations.52
The Secretary of Energy Advisory Board (SEAB) formed the Nuclear Weapons Complex
Infrastructure Task Force to carry out this study. The task force issued its report in July 2005. It
recommended immediate design of a Reliable Replacement Warhead (RRW). RRW was a
concept in which Cold War aspects of nuclear weapon design, notably maximizing the explosive
yield of the weapon per unit weight (the “yield-to-weight ratio”), would be traded off for design
features more suitable to the post-Cold War world, such as ease of manufacture, enhanced
confidence without nuclear testing, reduced use of hazardous materials, and enhanced surety
features.53 The task force envisioned RRW as a “family of weapons,” with RRWs ultimately
making up most if not all of the future stockpile. The task force also recommended a
Consolidated Nuclear Production Center (CNPC), “a modern set of production facilities with 21st
century cutting-edge nuclear component production, manufacturing, and assembly technologies,
51
U.S. Department of Energy. Draft Supplemental Programmatic Environmental Impact Statement on Stockpile
Stewardship and Management for a Modern Pit Facility, DOE/EIS-236-S2, summary volume, May 2003, p. S-27,
http://www.energy.gov/sites/prod/files/EIS-0236-S2-DEIS-Summary-2003.pdf.
52
U.S. Congress, House Committee on Appropriations, Energy and Water Development Appropriations Bill, 2005,
Report to accompany H.R. 4614, 108th Cong., 2nd sess., June 18, 2004, H.Rept. 108-554 (Washington: GPO, 2004), p.
111, http://www.gpo.gov/fdsys/pkg/CRPT-108hrpt554/pdf/CRPT-108hrpt554.pdf.
53
For detailed information on the RRW program, see CRS Report RL33748, Nuclear Warheads: The Reliable
Replacement Warhead Program and the Life Extension Program, by (name redacted).
Congressional Research Service
20
U.S. Nuclear Weapon “Pit” Production Options for Congress
all at one location … When operational, the CNPC will produce and dismantle all RRW
weapons.”54 CNPC would have an SNM manufacturing facility, part of which would support
plutonium operations. “All of the functions currently identified in the proposed Modern Pit
Facility (MPF) will be located in this building” except for plutonium R&D.55 CNPC would not
manufacture non-nuclear components.56 Regarding capacity, the report stated:
A classified Supplement analyzes the issue of timing for the CNPC for a stockpile of 2200
active and 1000 reserve [weapons] and the expected pit manufacturing capacity of the future
Complex. The conclusion is that if the NNSA is required to: 1) protect a pit lifetime of 45
years, 2) support the above stockpile numbers, and 3) demonstrate production rates of 125
production pits to the stockpile per year, the CNPC must be functional by 2014. If one
accepts the uncertainty of pit lifetime of 60 years, the CNPC can be delayed to 2034. In
either case TA-55 is assumed to be producing 50 production pits to the stockpile per year.57
Complex 2030
The FY2007 National Defense Authorization Act, P.L. 109-364, directed the Secretary of Energy
to develop a plan for transforming the nuclear weapons complex to provide a responsive
infrastructure by 2030, and to submit this plan to Congress. The report was submitted in October
2006.58 The goal was to implement U.S. policy on strategic deterrence as called for in the 2001
Nuclear Posture Review, which recognized the need to transform U.S. nuclear forces from
deterring the U.S.S.R. to responding to emerging threats.59 Regarding the stockpile, NNSA
envisioned a smaller stockpile that, by 2030, would be composed mainly if not entirely of RRWs.
While the nuclear weapons complex of 2030, “Complex 2030,” would continue to have eight
sites, quantities of SNM requiring high levels of security would be “only present at production
and testing sites.”60 As to labs, in Complex 2030 “No laboratory operations require Category I/II
SNM levels of security. Laboratory facilities are not used for nuclear production missions.”61
Unlike the SEAB report, Complex 2030 would not have a Consolidated Nuclear Production
Complex but would have “full operations of a consolidated plutonium center at an existing
Category I/II SNM site in the early 2020s.”62 Further, “By 2022, LANL will not operate facilities
containing CAT I/II quantities of SNM. The location and operator of the consolidated plutonium
center will be determined following completion of appropriate National Environmental Policy
Act (NEPA) reviews.”63 NNSA would “Plan, construct, and startup a consolidated plutonium
center for long-term R&D, surveillance, and manufacturing operations. Plan the consolidated
54
U.S. Department of Energy. Secretary of Energy Advisory Board. Nuclear Weapons Complex Infrastructure Task
Force. Recommendations for the Nuclear Weapons Complex of the Future, final report, July 13, 2005, p. vii,
http://www.doeal.gov/SWEIS/DOEDocuments/049%20SEAB%202005.pdf.
55
Ibid., p. 15.
56
Ibid., p. 14.
57
Ibid., p. 17.
58
U.S. Department of Energy. National Nuclear Security Administration. Office of Defense Programs. Complex 2030:
An Infrastructure Planning Scenario for a Nuclear Weapons Complex Able to Meet the Threats of the 21st Century.
DOE/NA-0013, October 2006, 21 p., http://fissilematerials.org/library/doe06e.pdf.
59
For an unclassified summary of the review, see U.S. Department of Defense. Nuclear Posture Review Report, 3 p.,
no date, http://www.defense.gov/news/jan2002/d20020109npr.pdf.
60
Department of Energy, Complex 2030, p. 3. Note that SNM quantities meeting the lower threshold of Category II are
different for safety and for security.
61
Ibid.
62
Ibid., p. 7.
63
Ibid., p. 10.
Congressional Research Service
21
U.S. Nuclear Weapon “Pit” Production Options for Congress
plutonium center for a baseline capacity of 125 units [i.e., pits] per year net to the stockpile by
2022.” NNSA would “Upgrade LANL plutonium facilities at Technical Area 55 to support an
interim production rate of 30 to 50 RRW war reserve pits per year net to the stockpile by 2012.”64
Regarding another building, NNSA would “Complete and operate the Chemistry and Metallurgy
Research Replacement (CMRR) as a CAT I/II facility up to 2022 (use as a CAT III/IV facility and
focal point and for material science thereafter) to support plutonium operations at LANL, closure
of existing LANL Chemistry and Metallurgy Research (CMR) facility, and the removal of CAT
I/II quantities of plutonium from LLNL [Lawrence Livermore National Laboratory].”65
Importantly, the plan for Complex 21 shifted capacity from a range of 125 to 450 ppy examined
in the MPF EIS to a baseline of 125 ppy.
Chemistry and Metallurgy Research Replacement Project
While nuclear weapons production was at issue, so was R&D on SNM, with a focus at LANL on
plutonium. The CMR building had significant problems due to aging and design. As described in
a Government Accountability Office report of 2013,
DOE’s and NNSA’s plans for replacing the CMR have changed over the past several
decades. In 1983, DOE first decided that the CMR was outdated and began making plans to
replace it. Over the next nearly 2 decades, several large replacement projects were proposed,
but none progressed beyond conceptual stages. … NNSA has taken a number of steps to
develop the CMRR nuclear facility or some facility to replace the CMR, but its plans have
continued to change over time.66
One such project was the Special Nuclear Materials Research and Development Laboratory
Replacement Project at LANL. It would have replaced CMR, and would have included a
laboratory and facilities for laboratory support, offices, utilities, and waste pretreatment.
According to a LANL document of 1990, funding was $10 million for FY1988 and $22 million
for FY1989. Anticipated milestones included completion of preliminary design in January 1990,
completion of an EIS in 1991, site work start in mid-1991, and construction completed in the fall
of 1994.67
This project did not happen. Instead, it eventually morphed into the Chemistry and Metallurgy
Research Replacement (CMRR) project. In 2002, NNSA reached Critical Decision 0, approve
mission need, for the project. In 2003, NNSA completed an environmental impact statement on
the project, and in 2004 NNSA issued a Record of Decision (ROD) on it.68 The preferred option
in the ROD included two buildings. The Chemistry and Metallurgy Research Replacement
Nuclear Facility (CMRR-NF) was to be a laboratory building that would have provided support,
such as AC, for pit production. A separate building, RLUOB, would have provided offices,
utilities for both buildings, and laboratory space for R&D. Because the amount of plutonium
64
Ibid., p. 11.
Ibid., p. 12.
66
U.S. Government Accountability Office, Modernizing the Nuclear Security Enterprise: Observations on NNSA’s
Options for Meeting Its Plutonium Research Needs, GAO-13-533, September 2013, p. 8.
67
Los Alamos National Laboratory, fact sheet: “Special Nuclear Materials Research and Development Laboratory
Replacement Project at Los Alamos National Laboratory, LANL-89-48, January 1990, p. 2.
68
Department of Energy, National Nuclear Security Administration, “Record of Decision: Final Environmental Impact
Statement for the Chemistry and Metallurgy Research Building Replacement Project, Los Alamos National Laboratory,
Los Alamos, NM,” 69 Federal Register 6968-6969, February 12, 2004.
65
Congressional Research Service
22
U.S. Nuclear Weapon “Pit” Production Options for Congress
RLUOB would have held under then-current regulations was so small, at most 6 grams of WGPu,
it was expected to do only a small amount of AC to support weapons production work. In 2005,
“NNSA authorized the preliminary design (Critical Decision 1 or CD-1) for the CMRR project.”69
In 2008, NNSA issued an ROD to keep plutonium manufacturing and R&D at Los Alamos and to
build CMRR-NF there to support these tasks.70 RLUOB was completed in FY2010, but CMRRNF was still in preliminary design at that time.
Congress initially approved the project, but concerns grew as the cost escalated and the schedule
slipped. Concurrently, the need to replace CMR became more urgent. Michael Anastasio, then
Director of LANL, testified that CMR “is at the end of its useful life,” that CMRR “is critical to
sustaining the nation’s nuclear deterrent” and to other missions, and that “to successfully deliver
this project, it will be important to have certainty in funding and consistency of requirements
throughout the project.”71 Also, as noted earlier, CMR was “decrepit” and not seismically robust.
In an effort to secure Senate approval of the New START Treaty, the Administration issued a
report in November 2010 stating that it “is committed to fully fund the construction of the
Uranium Processing Facility (UPF) and the Chemistry and Metallurgy Research Replacement
(CMRR)” and set out a 10-year funding profile for both facilities.72 The New START resolution
of ratification included provisions related to the nuclear weapons complex in general and to
CMRR and UPF in particular.73 The Administration requested the amount indicated in its
November 2010 report in the FY2012 budget. However, in the FY2013 request, the
Administration eliminated funding for CMRR-NF and “deferred” it “for at least five years” on
grounds that the CMRR facility, UPF, and a life extension project for the B61 bomb were
unaffordable concurrently and that there were alternative ways of accomplishing the tasks that
CMRR-NF was to perform.74 However, Section 3114 of the FY2013 National Defense
Authorization Act (P.L. 112-239) directed the Secretary of Energy to “construct at Los Alamos
National Laboratory, New Mexico, a building to replace the functions of the existing Chemistry
and Metallurgy Research Building at Los Alamos National Laboratory associated with
69
U.S. Department of Energy. National Nuclear Security Administration. “Chemistry and Metallurgy Research
Building Replacement Project,” May 2007 p. 3, http://www.doeal.gov/SWEIS/OtherDocuments/
427%20NNSA%202007%20CMR%20senate%20report.pdf
70
National Nuclear Security Administration, “Record of Decision for the Complex Transformation Supplemental
Programmatic Environmental Impact Statement—Operations Involving Plutonium, Uranium, and the Assembly and
Disassembly of Nuclear Weapons,” 73 Federal Register 77647, December 19, 2008.
71
“Prepared Statement of Dr. Michael R. Anastasio, Director, Los Alamos National Laboratory, Los Alamos, NM,” in
ibid., p. 405.
72
U.S. White House. November 2010 Update to the National Defense Authorization Act of FY2010 Section 1251
Report: New START Treaty Framework and Nuclear Force Structure Plans, pp. 5, 9, http://www.lasg.org/CMRR/
Sect1251_update_17Nov2010.pdf. The Uranium Processing Facility at the Y-12 National Security Complex (TN)
would replace Y-12’s 9212 complex, a uranium processing facility; its first buildings were built during World War II.
Note that 9212 is sometimes referred to as a building, and sometimes as a complex.
73
This resolution, “Treaty with Russia on Measures for Further Reduction and Limitation of Strategic Offensive Arms”
(Treaty Doc. 111–5), as agreed to by the Senate, is available at “Treaty with Russia on Measures for Further Reduction
and Limitation of Strategic Offensive Arms—continued,” Congressional Record, December 22, 2010, pp. S10982S10985, http://www.gpo.gov/fdsys/pkg/CREC-2010-12-22/pdf/CREC-2010-12-22-pt1-PgS10982.pdf#page=1.
74
U.S. Department of Energy. Office of Chief Financial Officer, FY 2013 Congressional Budget Request, Volume 1,
National Nuclear Security Administration, DOE/CF-0071, February 2012, p. 185, http://www.mbe.doe.gov/budget/
13budget/Content/Volume1.pdf; and Statement of Donald Cook, Deputy Administrator for Defense Programs, National
Nuclear Security Administration, in U.S. Congress. Senate. Committee on Armed Services. Subcommittee on Strategic
Forces. Hearing to Receive Testimony on Strategic Forces Programs of the National Nuclear Security Administration
and the Department of Energy’s Office of Environmental Management in Review of the Department of Energy Budget
Request for Fiscal Year 2013, March 14, 2012, pp. 29-30, http://www.armed-services.senate.gov/Transcripts/2012/
03%20March/12-12%20-%203-14-12.pdf.
Congressional Research Service
23
U.S. Nuclear Weapon “Pit” Production Options for Congress
Department of Energy Hazard Category 2 special nuclear material operations.” This provision
also barred any funds to be spent on a plutonium strategy for NNSA “that does not include
achieving full operational capability of the replacement project by December 31, 2026.”
However, Congress appropriated no funds for CMRR-NF for FY2013.
For FY2014, the Administration requested no funds for CMRR-NF, and Congress authorized and
appropriated no funds for it. However, Section 3117 of the FY2014 National Defense
Authorization Act (H.R. 3304, P.L. 113-66) included an exception to the plutonium strategy
provision just noted. It authorized NNSA to spend funds on a modular building strategy, that is,
“constructing a series of modular structures, each of which is fully useable, to complement the
function of the plutonium facility (PF–4) at Los Alamos National Laboratory, New Mexico, in
accordance with all applicable safety and security standards of the Department of Energy.”
Option 12 describes the modular strategy.
Two Other Failed Attempts
As a further illustration of difficulties in building facilities to handle plutonium, this section
presents two facilities that were built, found to be unusable, and demolished.
Nuclear Materials Storage Facility (NMSF): This building was built at LANL. According to
the DOE FY1984 budget request, “This project provides for the construction of a repository for
long and intermediate storage of large quantities of source and special nuclear materials. It will be
designed to meet security, safety, and safeguards requirements for the storage and handling of
nuclear materials. The new 29,100-square-foot building will contain a vault area of approximately
13,000 square feet.”75 A 1997 report by the DOE Inspector General was scathing:
We found that the NMSF, which was originally completed in 1987, was so poorly designed
and constructed that it was never usable and that DOE officials were proposing to renovate
the entire facility. Departmental and contractor officials discovered numerous design,
construction and operational deficiencies after the facility was occupied in February 1987.
These deficiencies included: (1) the inability to control and balance the heating, ventilation
and air conditioning (HVAC) system to maintain acceptable negative pressures within the
facility; (2) the inability to dissipate the heat generated by radioactive decay of the materials
to be stored; (3) the inability to limit personnel radiation exposures to “as low as reasonably
achievable;” (4) a peeling of the “Placite” decontamination epoxy coating throughout the
facility; and (5) the inability to open and secure the Safe Secure Trailer (SST) doors due to
the inadequate width of the garage once the SSTs were parked in the garage.76
Because of these and other deficiencies, “This structure was never used for storage of nuclear
materials, and a decision was made in 2006 to demolish the structure.”77 Demolition was
completed by the end of FY2008.78
75
U.S. Department of Energy. Assistant Secretary for Management and Administration. Office of the Controller.
Congressional Budget Request, FY 1984, Volume 1: Atomic Energy Defense Activities, DOE/MA-0064/1, January
1983, p. 61
76
U.S. Department of Energy. Office of Inspector General. Report on Inspection of Alleged Design and Construction
Deficiencies in the Nuclear Materials Storage Facility at the Los Alamos National Laboratory, report. INS-O-97-01,
January 16, 1997, p. 3, http://energy.gov/sites/prod/files/ins-9701.pdf. SSTs are DOE trucks specially outfitted to
transport nuclear weapons and related components and materials.
77
U.S. Department of Energy. National Nuclear Security Administration. Los Alamos Site Office. Final Site-Wide
Environmental Impact Statement for Continued Operation of Los Alamos National Laboratory, Los Alamos, New
Mexico, Volume 3, Comment Response Document, Book 1, DOE/EIS-0380, May 2008, page 1-8, http://www.doe.gov/
(continued...)
Congressional Research Service
24
U.S. Nuclear Weapon “Pit” Production Options for Congress
Building 371: A press report tells the story of a plutonium project at Rocky Flats:
One striking example of a construction project that turned out to be a failure was a $225
million plutonium processing building at the Rocky Flats Plant near Golden, Colo. The
processing plant, Building 371, was started in 1973, completed in 1981 and operated for a
month in 1982 before being shut because the new processing technology did not work. The
Energy Department has estimated that it will cost nearly $400 million and take eight years to
make the equipment in the building work.
“The fact of the matter is that Building 371 is a fiasco,” said Joseph F. Salgado, the Deputy
Secretary of Energy. “It’s a horror story. It’s unacceptable.”
Building 371 was intended to replace another, much older processing plant, Building 771. …
The Energy Department shut Building 771 on Oct. 8 after three employees were exposed to
plutonium dust, which can be extremely dangerous if it is inhaled. The closing of Building
771 was, [sic] the nation’s sole source of reprocessed plutonium, which is used in triggers for
thermonuclear bombs. The closing has brought most of the plant’s operations at the Rocky
Flats Plant to a halt.79
The building was never put into operation. Instead, the buildings at Rocky Flats Plant, including
Building 371, were torn down and the site was decontaminated.80
Options for Congress
Analysis of Alternatives
For many years, Congress has been concerned with cost growth and schedule delays in nuclear
weapons complex programs for facilities and weapons. One way to help resolve this problem may
be to have a thorough airing of alternatives before decisions are made. Most recently, in its work
on the FY2014 budget, Congress pressed NNSA to analyze alternatives:
•
The Senate Armed Services Committee noted that “NNSA spent about 10 years and more
than $350 million on the design of the CMRR Nuclear Facility” before it was deferred
and a larger amount on another project that was canceled. The committee stated that
“these decisions raise serious questions about how well NNSA scrutinizes the analyses of
alternatives prior to submitting them for review and approval.” Accordingly, it directed
GAO to study, among other things, NNSA’s process for analyzing alternatives.81
(...continued)
sites/prod/files/EIS-0380-FEIS-03-1-2008.pdf.
78
Los Alamos National Laboratory, Fiscal Year 2008 Institutional Commitments—Final Report, c. late 2008, p. 4.
79
Keith Schneider, “U.S. Spent Billions on Atom Projects That Have Failed,” New York Times, December 12, 1988,
http://www.nytimes.com/1988/12/12/us/us-spent-billions-on-atom-projects-that-have-failed.html?pagewanted=all&
src=pm.
80
U.S. Department of Energy. Office of Legacy Management. Rocky Flats Site. Colorado, “Fact Sheet,” p. 1, available
via http://www.lm.doe.gov/land/sites/co/rocky_flats/rocky.htm.
81
U.S. Congress. Senate. Committee on Armed Services. National Defense Authorization Act for Fiscal Year 2014.
Report to accompany S. 1197. S.Rept. 113-44, 113th Congress, 1st Session, June 20, 2013, p. 259.
Congressional Research Service
25
U.S. Nuclear Weapon “Pit” Production Options for Congress
•
The House Armed Services Committee, in its report on H.R. 1960, the FY2014 defense
authorization bill, stated that Section 3113 would “require the Secretary of Energy, acting
through the [NNSA] Administrator, to request an independent review of each guidance
issued for the analysis of alternatives for each nuclear weapon system undergoing life
extension and each new nuclear facility of the nuclear security enterprise as well as the
results of such analysis of alternatives. The Secretary of Energy, acting through the
Administrator, would be required to submit the results of any such analysis to the Nuclear
Weapons Council and the congressional defense committees.” Section 3113 also “would
express the sense of Congress that Congress encourages the Administrator and the
Nuclear Weapons Council to follow the results of the analysis of alternatives of a life
extension program or a defense nuclear facility construction project when selecting a
final option.”82 This provision was included in H.R. 1960 as passed by the House. Section
3112 of the FY2014 National Defense Authorization Act (H.R. 3304, P.L. 113-66)
contained related language.
•
Section 311 of H.R. 2609, the FY2014 energy and water development appropriations bill
as passed by the House, directs the Secretary of Energy to submit “a report which
provides an analysis of alternatives for each major warhead refurbishment program that
reaches [a certain stage].”
•
The Senate Appropriations Committee expressed its concern “about NNSA’s ability to
assess alternatives, which may significantly reduce cost, at the preliminary planning
stages of a project.” It referred to the deferral of CMRR-NF and the cancellation of
another project, each incurring planning costs of hundreds of millions of dollars, and
noted, “The Committee believes this wasteful spending could have been avoided had
NNSA better assessed alternatives.” Accordingly, it directed NNSA to submit a plan on
how NNSA “will strengthen its ability to assess alternatives.”83
•
Section 312 of the FY2014 Consolidated Appropriations Act (H.R. 3547, P.L. 113-76)
requires the Secretary of Energy to submit to Congress an analysis of alternatives for the
B61-12 LEP and certain other major warhead refurbishment programs.
The Role of the National Environmental Protection Act (NEPA) Process in an
Analysis of Alternatives
Over the past several decades, many projects, including some in the nuclear weapons complex,
have been delayed or stopped by lawsuits brought by nongovernmental organizations under the
National Environmental Policy Act (NEPA) of 1969, P.L. 91-140, as amended. These lawsuits
typically involve procedural issues of compliance with NEPA in preparing an environmental
impact statement (EIS). For example, plaintiffs might charge that an agency filed an inadequate
EIS or did not consider all reasonable alternatives adequately.
Secretary of Energy Steven Chu stressed the importance for DOE of complying with NEPA:
82
U.S. Congress, House. Committee on Armed Services, National Defense Authorization Act for Fiscal Year 2014,
Report on H.R. 1960 together with additional and dissenting views, 113th Cong., 1st sess., June 7, 2031, H.Rept. 113102 (Washington: GPO, 2013), p. 351.
83
U.S. Congress. Senate. Committee on Appropriations. Energy and Water Development Appropriations Bill, 2014.
Report to accompany S. 1245. S.Rept. 113-47, 113th Congress, 1st Session, June 27, 2013, p. 100.
Congressional Research Service
26
U.S. Nuclear Weapon “Pit” Production Options for Congress
Compliance with the National Environmental Policy Act (NEPA) is a pre-requisite to
successful implementation of DOE programs and projects. Moreover, the NEPA process is a
valuable planning tool and provides an opportunity to improve the quality of DOE’s
decisions and build public trust. Hence, timely attention to NEPA compliance is critical to
accomplishing our missions. …
I cannot overstate the importance of integrating the NEPA compliance process with program
and project management and of applying best management practices to NEPA compliance in
DOE,” and pointed to the DOE NEPA Order as a “[tool] available to help improve the
efficiency of its NEPA compliance efforts.84
Several options discussed below involve increasing the amount of plutonium in RLUOB beyond
that permitted for a Radiological Facility so it could perform the AC needed to support production
of 80 ppy. Section 102 of NEPA would seem to require an EIS for those options because the
increase could raise the risk to the “human environment” in a major accident. Section 102 directs
all federal agencies to
(C) include in every recommendation or report on proposals for legislation and other major
Federal actions significantly affecting the quality of the human environment, a detailed
statement by the responsible official on—
(i) the environmental impact of the proposed action,
(ii) any adverse environmental effects which cannot be avoided should the proposal be
implemented,
(iii) alternatives to the proposed action,
(iv) the relationship between local short-term uses of man’s environment and the
maintenance and enhancement of long-term productivity, and
(v) any irreversible and irretrievable commitments of resources which would be
involved in the proposed action should it be implemented.
In 2008, NNSA prepared a broad (“site-wide”) EIS for LANL that included the plutonium
program there. Given the state of flux of the plutonium program, NNSA has not prepared an EIS
on it since then, though in 2011 it prepared a Supplemental EIS narrowly focused on the CMRRNF component of the CMRR project.
However, Greg Mello, Executive Director of Los Alamos Study Group, a nongovernmental
organization, argues that “an EIS must precede NNSA’s choice between post-CMRR-NF
plutonium sustainment alternatives.” He prepared the following analysis in August 2013 for this
report. Since the study group has filed four NEPA lawsuits against Los Alamos construction
projects over the past two decades, this analysis merits particular attention.85
84
“Memorandum for Heads of Departmental Elements,” from Steven Chu, Secretary of Energy, subject: “Improved
Decision Making through the Integration of Program and Project Management with National Environmental Policy Act
Compliance,” June 12, 2012, http://energy.gov/sites/prod/files/S1MemoIntegratingNEPA_with_Program_and_ProjectManagement_2012.pdf. The DOE Order referenced, DOE O
451.1B, “National Environmental Policy Act Compliance Program,” Change 3, January 19, 2012, is available at
http://energy.gov/sites/prod/files/DOEO4511B_011912.pdf.
85
For information on its most recent litigation, see Los Alamos Study Group, “CMRR Nuclear Facility: Litigation
under the National Environmental Policy Act (NEPA),” updated August 5, 2013, http://www.lasg.org/CMRR/
(continued...)
Congressional Research Service
27
U.S. Nuclear Weapon “Pit” Production Options for Congress
The main elements of the NEPA landscape are (1) a statute that elevates environmental
values to a major purpose of governance, establishes a procedural approach to integrating
those values in decisions, and creates a Council on Environmental Quality (CEQ) to oversee
this process; (2) CEQ regulations that are binding on agencies; (3) agency regulations,
harmonious with CEQ’s but tailored to each agency; (4) CEQ guidance that lacks the force
of law but is frequently cited by courts; and (5) a body of case law, based on thousands of
cases, that creates a sort of NEPA “common law”—some universally binding, some binding
in some federal districts, and some influential for such reasons as lucidity. Early NEPA case
law established some basic parameters of implementation, such as that citizens could sue
agencies to enforce NEPA compliance. Over time, a body of NEPA law has developed that
is relatively settled for most basic legal issues but contested in other areas, especially where
decisions depend on particular facts.
DOE requires an EIS and a Record of Decision (ROD) as early steps for all major projects
that may have significant impacts. In the case of CMRR-NF, a careful EIS that really
compared alternatives realistically would have noticed the earthquake-amplifying stratum of
volcanic ash beneath the site and incorporated the latest seismic information, problems that
later bedeviled the project. The underlying weaknesses in purpose and need could have been
vetted as well, and hundreds of millions of dollars in design costs and many years of delay in
acquiring safer plutonium capabilities could have been avoided. Sound EISs and formal
RODs would strengthen DOE’s project management.
I believe that an EIS must precede NNSA’s choice between post-CMRR-NF plutonium
sustainment alternatives. An EIS requires objective environmental analysis of all reasonable
alternatives prior to actions that irreversibly commit federal resources or bias the agency
toward an alternative, with an initial business-case analysis used to establish which
alternatives are reasonable. Because NNSA has proposed alternatives to CMRR-NF that are
major federal actions that could have significant effects on the human environment, and
since NNSA has no EIS that analyzes the impact of these alternatives, NNSA must initiate an
EIS to do so. Some proposed CMRR-NF alternatives encompass multiple states and sites and
may cost billions of dollars. All alternatives will have significant environmental impacts over
much of this century.
The relative environmental benignity of upgrading RLUOB to an HC-3 facility might tilt the
scales toward that choice but is not a reason not to do an EIS. Upgrading RLUOB may not
be the whole of the post-CMRR-NF redirection in plutonium programs. Other nuclear
weapons complex sites are under consideration for involvement, including [Lawrence
Livermore National Laboratory, Nevada National Security Site, Waste Isolation Pilot Plant],
and perhaps [Savannah River Site]. LANL is also considering building “modular” plutonium
facilities and is actively briefing this option to Congress. An EIS is definitely required for
choices of this magnitude. None of these alternatives, let alone “all reasonable alternatives”
as the law requires, have been weighed and their impacts compared in any EIS. Furthermore,
NEPA’s regulations and case law are clear that an agency cannot analyze one project’s
alternatives and build something quite different, or take one action today and significantly
add to that action later, or do so contemporaneously with separate but connected projects.
Congress has been anxious to see a formal plan for plutonium sustainment; the formality of
NEPA process would help provide that plan while also serving as a barrier to “scope creep”
and associated cost escalation.
It cannot be overemphasized that NEPA’s analysis of alternatives serves public purposes
beyond environmental ones. As John Immele, former director of LANL’s nuclear weapons
program, wrote in late 1999 regarding the NEPA process, “A ... lesson from the weapons
(...continued)
Litigation/CMRR-NF_litigation.html.
Congressional Research Service
28
U.S. Nuclear Weapon “Pit” Production Options for Congress
program of the early and mid 1990s as well as the fissile materials disposition program is the
necessity for and (surprising) success of publicly vetting our strategies through
environmental impact statements.”
A thorough EIS analysis of plutonium program alternatives would be a way of complying with
NEPA, would be responsive to congressional desires to have NNSA analyze alternatives, would
reduce the likelihood that lawsuits filed to challenge the alternative chosen would succeed, and
would thus reduce the likelihood that such lawsuits would be filed.
Potential Options
Many options are possible. Ideally, all would meet multiple, and sometimes conflicting, goals,
such as:
•
Support production of 80 ppy.
•
Support all other necessary plutonium work, however “necessary” is defined.
Examples might include ARIES, producing plutonium-238 sources, conducting
plutonium R&D, and processing liquid waste containing plutonium in order to
reduce its volume for shipment to WIPP.
•
Reduce safety and security risks (building collapse in an earthquake or other
disaster, dose to workers and the public resulting from an accident, terrorist
attack leading to detonation of a nuclear device, etc.) to an acceptably low level.
•
Maximize cost-effectiveness and ensure affordability.
•
Complete the project on a schedule that supports needed work.
•
Halt program operations in CMR in approximately 2019.86
•
Provide a planning margin for the facility to meet, in the future, new or expanded
missions or more stringent regulatory requirements.
•
Maximize useful life of the facility or facilities.
•
Comply with all existing regulations.
Clearly, the more requirements that are levied on a project, the harder it is to comply with them
all. In this case, none of the options presented here could meet all these goals simultaneously, and
in some cases there is little or no data to evaluate how well an option would meet its goals. Thus
Congress is faced with a choice among imperfect options.
The following list includes a broad spectrum of options. The list is presented as a progression,
with a logical connection from one option to the next. Each connection is shown in italics.
As a start, consider options using existing buildings at Los Alamos, home to the only U.S. pit
manufacturing capability. Since RLUOB is permitted to hold only a few grams of plutonium and
CMR is at considerable seismic risk and due to be closed out, why not …
86
U.S. Department of Energy. Office of Chief Financial Officer. FY 2014 Congressional Budget Request, DOE/CF0084, April 2013, Volume 1, National Nuclear Security Administration, p. WA-168.
Congressional Research Service
29
U.S. Nuclear Weapon “Pit” Production Options for Congress
Option 1. Focus PF-4 on Pit Production; Move Other Tasks Elsewhere as
Needed
PF-4 has enough lab space, about 60,000 sf, to produce about 10 ppy with RLUOB supporting
some low-MAR AC. LANL estimates that PF-4 could be used to manufacture 30 ppy without
having to move out any ongoing programs. Attaining this higher capacity would require several
actions including reconfiguring existing space and “invest[ing] in new equipment (acquire/install)
to increase capacity to 30 pits per year.”87 As a hedge against inadequate plutonium processing
capacity, NNSA’s Plutonium Metal Processing subprogram would process plutonium alloy from
pits returned from Pantex so as to create an inventory of metal for pits before it is needed; doing
so “helps ease constraints on Analytical Chemistry (AC) capacity and reduce out-year risk to
achieve capacity targets.”88 Both of these activities serve to increase pit-manufacturing capacity
without requiring additional laboratory space.
Furthermore, NNSA’s plutonium strategy is considering ways to make better use of space in PF-4
and RLUOB to support the transition of AC and MC capabilities from CMR. Some space would
be made available for this transition by reclaiming or “repurposing” rooms in PF-4 that are no
longer in use (e.g., because the projects they housed have been completed), and some would
come from reconfiguration, that is, rearranging equipment to increase efficiency. The former
would add net space for AC/MC; the latter would not. AC equipment also would be added in
RLUOB. In total, these actions would affect 8,000 sf in PF-4.89 A Los Alamos study considered
using a facility at Livermore (see Option 7) and RLUOB for AC but did not consider having PF-4
perform all the AC work itself. In part this is because AC is space-intensive and PF-4 would not
have sufficient space for production of 30 ppy plus the AC needed to support that capacity.
AC would pose this problem because PF-4 is not configured for a large amount of AC. While
some AC operations that use gram quantities of plutonium can be performed in gloveboxes, most
AC operations use tiny samples, such as milligram or microgram quantities of plutonium
dissolved in acid and placed in very small containers. Manipulating them is much easier in openfront hoods using thin gloves; it would be much harder to manipulate these samples with the
multiple layers of gloves required for PF-4 glovebox work. However, hoods require a powerful
ventilation system to create negative pressure in the hoods (so no fumes or plutonium escape),
and multiple large HEPA filters. Gloveboxes require much less ventilation capacity since any air
that flows into them does so through small leaks. PF-4, which is mostly outfitted with
gloveboxes, does not have sufficient air handling capacity to support the hoods needed for 30
ppy.90 It would be difficult to replace gloveboxes with open-front hoods in PF-4 because the PF-4
ventilation system was not configured for the large airflow that hoods require.91 Upgrading PF-4
ventilation to support the large number of hoods needed to provide high AC capacity would at
best be extremely costly. Indeed, the ventilation system to support open-front hoods is so bulky,
as shown in Figure 6, that it might not be possible to retrofit it into PF-4 at any cost. By
87
U.S. Department of Energy. FY 2014 Congressional Budget Request, Volume 1, National Nuclear Security
Administration, p. WA-64.
88
Ibid., p. WA-68.
89
Figure provided by Los Alamos National Laboratory, January 24, 2014.
90
Information provided by Los Alamos National Laboratory, September 2013.
91
An open-front hood in normal operations draws 500 cubic feet per minute (cfm) of air, while a glovebox in an
accident condition (i.e., with a glove breach) draws about 33 cfm, and a glovebox in normal operations draws very little
air. Thus air handling equipment for a hood must have about 15 times the capacity of equipment for gloveboxes.
Information provided by Los Alamos National Laboratory, email, October 16, 2013.
Congressional Research Service
30
U.S. Nuclear Weapon “Pit” Production Options for Congress
extension, even if all of PF-4 were devoted to pit manufacture and supporting tasks, it appears
highly improbable that PF-4, by itself, could do all the work needed to produce 80 ppy. There
would also be the issue of where to house the tasks that would be moved out.
Given those problems, why not …
Option 2. Build CMRR-NF
Another option is to resume work on CMRR-NF. That building, after all, was not canceled—it
was merely “deferred” for “at least five years.” Los Alamos estimates that if construction were to
begin in FY2018, the building would be completed in 2029, with the five-year delay adding
another two years to construction time due to the need to assemble crews, let contracts, etc. Even
so, this completion date would be in time for CMRR-NF to contribute to reaching the goal of
producing 80 pits per year by 2030. CMRR-NF would provide HC-2 space for AC and MC in
support of weapons production. While it is not at all certain that the facility will be built, it could
be built if Congress chose to provide funding for it.
This option faces many difficulties. The conditions that led the Administration to defer CMRRNF in FY2013 remain in place, and in some cases have arguably become more salient since then.
•
In deferring CMRR-NF, the Administration argued that building UPF and CMRR-NF and
beginning the B61-12 LEP simultaneously would be unaffordable, and that available
options would enable the nuclear weapons complex to perform the tasks of CMRR-NF.
•
The cost of UPF has increased and its schedule has slipped, possibly necessitating a
scaled-back version of UPF.92 This adds weight to the Administration’s judgment about
the affordability of CMRR-NF, UPF, and the B61-12 LEP if done simultaneously.
•
Section 3114 of the National Defense Authorization Act for FY2013, P.L. 112-239,
required the Secretary of Energy to construct, at Los Alamos, “a building to replace the
functions of the existing Chemistry and Metallurgy Research Building at Los Alamos
National Laboratory associated with Department of Energy Hazard Category 2 special
nuclear material operations.” However, NNSA requested no funds for CMRR-NF in
FY2013 or FY2014, and Congress appropriated no funds for it in those years.
•
As detailed in P.L. 113-66, FY2014 National Defense Authorization Act, Section 3117,
“Authorization of Modular Building Strategy as an Alternative to the Replacement
Project for the Chemistry and Metallurgy Research Building, Los Alamos National
Laboratory, New Mexico,” Congress is willing to consider modules (see Option 12) as an
alternative to CMRR-NF. (Note that modules would perform high-MAR work while
CMRR-NF would have performed mainly AC, which involves much less MAR.)
•
A modified RLUOB that could “perform the functions of the existing Chemistry and
Metallurgy Research Building,” as discussed under Options 8-10, would meet most of the
functionality requirement of Section 3114 of P.L. 112-239, though not the requirement for
92
“A seismic shift on UPF? NNSA to develop alternative scenarios for getting out of 9212, replacing uranium
capabilities within ‘original cost range,’” Frank Munger’s Atomic City Underground (blog), January 15, 2014,
http://knoxblogs.com/atomiccity/2014/01/15/shift-upf-nnsa-develop-alternative-scenarios-getting-9212-replacinguranium-capabilities-within-original-cost-range/#more-11019.
Congressional Research Service
31
U.S. Nuclear Weapon “Pit” Production Options for Congress
a new building. (It would not provide vault space, as CMRR-NF would have, but it
appears that the PF-4 vault will suffice, as discussed in “Options 6-12 Overview:
Matching Plutonium Tasks to Buildings.”)
•
By the time construction could resume on CMRR-NF, other options, such as those the
Administration was considering, would presumably be well developed, reducing the
added value of CMRR-NF.
•
Congress expressed concern over the escalating cost and delays of CMRR-NF, going so
far as to impose cost and schedule caps on the project in Section 3114; would Congress
be confident that NNSA could bring CMRR-NF online on schedule and on budget?
But even building CMRR-NF would not address the fact that PF-4 would be over 50 years old
when CMRR-NF came online, leaving aging and seismic issues unresolved. It may be possible to
resolve them with another option …
Option 3. Build a New Building Combining PF-4 and CMRR-NF Functions at
LANL
A new building could combine the functions of PF-4 and CMRR-NF. The argument for this
option is that PF-4 will be 50 years old in 2028, about when CMRR-NF could be completed.
Combining the two buildings into one would presumably cost less than building two separate
buildings and would avoid the need to transfer material between buildings, increasing efficiency.
A new building would incorporate the most advanced techniques to minimize seismic risk.
This option encounters many difficulties. The building would be larger and more complex than
either of the two smaller buildings, and complexity in a major nuclear construction project could
be expected to drive up costs and stretch out the schedule. Whereas CMRR-NF design work is
nearly completed, the new building would have to be designed from scratch, adding time and
cost. Also at issue is the need for this facility. NNSA’s TA-55 Reinvestment Project (TRP) plans
to extend PF-4’s life to approximately 2039,93 so combining the two buildings would forgo a
decade of PF-4 useful life. TRP cannot be halted on the chance that the new building would be
built: given the immense difficulties that earlier large facilities have encountered, there is no
assurance that the new building would be built. Some key nuclear facilities, notably Building
9212 and CMR, have service lives of over 60 years.94 RLUOB, too, should have at least a 50-year
life, that is, to 2059, since it was built to much higher standards than CMR or Building 9212.
Upgrades could presumably extend its life. If RLUOB and PF-4 together can do the necessary
plutonium work for at least another quarter-century, it would seem premature to even start
planning a replacement facility now.
Despite advances in design and construction that reduce seismic risk, this building would still be
at some risk from an earthquake if sited at Los Alamos. A simple way to avoid this risk is to …
93
U.S. Department of Energy. Office of Chief Financial Officer, FY 2014 Congressional Budget Request, Volume 1,
National Nuclear Security Administration, DOE/CF-0084, April 2013, p. WA-211.
94
Building 9212 at Y-12 is a uranium processing facility; “9212” is sometimes referred to as a building, and sometimes
as a complex with its first buildings built during World War II.
Congressional Research Service
32
U.S. Nuclear Weapon “Pit” Production Options for Congress
Option 4. Build a Building Combining PF-4 and CMRR-NF Functions at
Another Site
Constructing this building at a nuclear weapons complex site other than LANL with low seismic
risk, such as Pantex, would solve seismic issues regarding LANL, although the Virginia
earthquake of 2011 raises doubts about the seismicity of any site. The difficulty lies in the
tradeoff. LANL has a large human and facility infrastructure for plutonium work; much of that
would have to be built from scratch at Pantex Plant (TX), the nuclear weapons complex site that
performs final assembly and initial disassembly of nuclear weapons, taking considerable time and
involving considerable expense. Savannah River Site has a plutonium waste infrastructure, but
not the equipment or personnel for weapons manufacture. Its seismicity is in the same range as
that of Los Alamos.95 Further, while the regulatory issues of dealing with plutonium buildings are
well known for LANL, they would have to be examined in detail at another site. Siting,
permitting, and preparing an EIS would be time-consuming. In addition, this option would not
resolve problems with design, construction, and cost of the building itself.
If building a new building at another site has problems, what about using another existing
building at LANL …
Option 5. Refurbish the Chemistry and Metallurgy Research (CMR) Facility
CMR currently performs some AC for pit production in PF-4, as well as nuclear forensics. Given
that these are the only two facilities at Los Alamos contributing to pit production, and that it will
be many years before a new one could be built, CMR is being maintained at a minimal level in
order to keep it operational until approximately 2019, at which point NNSA plans to halt
plutonium work there. One option would go beyond currently planned maintenance and upgrades
so as to keep it in operation longer. Just as PF-4 is being upgraded on an ongoing basis to reduce
the risks of building collapse and fire, keeping it in operation until 2039, more substantial
upgrades to CMR might in theory keep it in service well beyond 2019. So doing would provide
AC and other capability until a new building could be built.
This option has many problems and uncertainties. As noted, a congressional commission called
CMR “genuinely decrepit” and a DNFSB study found it to be “structurally unsound.” Multiple
wings of the building have been stripped to bare walls and floors to reduce nuclear material and
prepare for decommissioning. A manager at Los Alamos indicated that CMR was built to the
standards of the 1950s and there is a “vast mismatch” between the safety requirements of then
and now. This individual pointed to problems with heating, electrical, and ventilation systems,
and stated that refurbishing the ductwork would be “cost-prohibitive.”96 A tour of the building in
September 2013 by the author revealed drains that had been concreted shut, gloveboxes with
plastic bags instead of drain connections, gloveboxes with little to no anchoring to the floor,
patches to pipes to keep them in operation, and water leaks in the ceiling. Laboratory staff stated
that utility panels behind walls were contaminated with radioactive material and that corrosion in
some piping had greatly reduced the inside diameter. Since NNSA plans to halt CMR operations
in approximately 2019, there have been no studies of how to extend its service life well beyond
that time, or what it would cost to do so.97 However, the fatal flaw in this option is that CMR
95
Mehmet Celebi and Robert Page, “Monitoring Earthquake Shaking in Federal Buildings,” U.S. Geological Survey
Fact Sheet 2005-3052, http://pubs.usgs.gov/fs/2005/3052/.
96
Telephone interview, April 21, 2010.
97
Information provided to the author while on a site visit to Los Alamos National Laboratory, September 11-12, 2013.
Congressional Research Service
33
U.S. Nuclear Weapon “Pit” Production Options for Congress
lacks seismic robustness. Given these problems, it appears that retrofitting CMR to provide
adequate utility and seismic robustness may not be possible at any reasonable cost.
Despite these problems, if no other facility is ready to do the work of CMR by 2019, there would
appear to be no other option than keeping CMR operational beyond that date, which would entail
additional costs, inefficiencies, and the risk of keeping workers in a seismically fragile structure.
Given problems with some obvious options, are other options available? A logical construct
matching tasks to buildings may help …
Options 6-12 Overview: Matching Plutonium Tasks to Buildings
Table 2. Matching Plutonium Tasks to Buildings
Hazard Category (HC)
Security Category (SC)
High (SC-I/II)
High (HC-2)
Task: Pit destruction (ARIES) and
casting
Low (HC-3)
null set (no plutonium tasks require
this combination of attributes)
Building: PF-4 or a module (new)
Low (SC-III/IV)
Task: Plutonium-238 work
Task: AC, some MC
Buildings: HB Line, H Canyon, PTPF
(new) at SRS; Building CPP-1634
(expanded) at INL; module at LANL
(new)
Buildings: RLUOB with 1 kg WGPu,
Building 332 at LLNL, F/H
Laboratory or Building 773-A at SRS
Source: CRS.
Notes: AC, analytical chemistry; MC, materials characterization; RLUOB, Radiological Laboratory/Utility/Office
Building; WGPu, weapons-grade plutonium; LLNL, Lawrence Livermore National Laboratory, INL, Idaho
National Laboratory; SRS, Savannah River Site; PTPF, Plutonium Testing and Processing Facility; CPP, Chemical
Processing Plant (a historical name for the site in which the building is located).
As Table 2 shows, plutonium work may be divided into tasks requiring low or high security, and
tasks involving lower- or higher-hazard quantities of MAR. This overview discusses each cell.
High SC/High HC: Most work on pits, whether fabricating them using foundries, performing
such supporting tasks as sample prep and some MC, or destroying them using ARIES, involves
large amounts of WGPu in a form that could be immediately usable by terrorists. As such, this
work requires high security and high MAR. PF-4 is HC-2/SC-I, and has the necessary equipment
and supporting infrastructure for pit work. PF-4 is the only building in the nuclear weapons
complex with this combination of attributes. Therefore, the most efficient use of PF-4 is for tasks
requiring high MAR and high security. As a corollary, pit production capacity and efficiency can
be increased by moving tasks that do not require high MAR and high security out of PF-4.
Low SC/High HC: Producing 80 ppy would require casting more hemishells, increasing MAR
substantially. While LANL has not done a detailed analysis, this added MAR could raise PF-4
above the limit allowed by the Documented Safety Analysis unless countervailing steps are taken.
One approach, discussed in Option 12, would be to build a new module at LANL to hold the pit
foundry. A second approach, discussed in Options 6 and 12, is to move Pu-238 work out of PF-4
Congressional Research Service
34
U.S. Nuclear Weapon “Pit” Production Options for Congress
to a module at LANL or to another site. Pu-238 is an ideal “candidate” to be moved out of PF-4.
It is 275 times as radioactive as Pu-239, and even though it is a small fraction of plutonium by
weight in PF-4, it accounts for 40% of its MAR allowance.98 It is in a low security category
because it would be unattractive to terrorists. Moving Pu-238 out of PF-4 would also free up
8,000 sf of floor space, which could be made available for pit work.
Low SC/Low HC: Casting hemishells for 80 ppy would also require increasing floor space
dedicated to that task. AC is floor-space intensive. At the same time, it involves low MAR;
indeed, the MAR is so low, and the form of the material (typically tiny samples of plutonium
dissolved in acid) of so little value for use in a nuclear weapon if captured by terrorists, that much
less security is required than PF-4 provides. The same holds for MC using samples of several
grams of metallic plutonium. Accordingly, AC and some MC can be performed in SC-III/IV
buildings. Thus, floor space could be made available in PF-4 by performing AC and some MC
elsewhere. Manufacturing 10 ppy in PF-4 would have required 2,400 sf of floor space for AC in
PF-4, plus about 7,000 sf for AC in RLUOB. The amount in PF-4, 2,400 sf, is a small fraction of
that building’s space, but since AC for 80 ppy would require considerably more floor space and
ventilation capacity, the key value of conducting AC elsewhere would be in keeping additional
AC from moving into PF-4. Options for moving AC out of PF-4 are discussed in Options 7-11.
Moving the PF-4 gas gun (see Figure 12) out of that building and into a building for AC would
release 1,200 sf of floor space, and a small amount of MAR, from PF-4.
In sum, moving (and keeping) AC and some MC out of PF-4 would free up space but little MAR,
while moving Pu-238 out of PF-4 would free up substantial space and MAR. In combination,
these measures would free up much space and MAR in PF-4, making it more likely that it could
produce 80 ppy and conduct other plutonium work.
High SC/Low HC: This is a null set; no plutonium tasks require high security for low MAR.
A note on vault storage space: A vault for storing plutonium is an integral part of pit production.
It acts as a buffer to hold plutonium because one production task may not dovetail precisely with
another. For example, pit production requires a place to hold plutonium metal that has been
qualified for use in pits until it is needed, to hold hemishells until they can be joined into
completed pits, and to hold completed pits until they are shipped to Pantex for incorporation into
weapons. A vault is also needed to store pits from weapons that have been returned from
deployment sites for surveillance. PF-4 is the only building at Los Alamos with a vault qualified
to hold the large quantity of plutonium that such tasks require.
When CMRR-NF was being designed in the early 2000s, SNM vault space at PF-4 and other sites
was mostly filled and the final disposition of material from other sites was unknown.
Accordingly, NNSA decided to add vault space to CMRR-NF. RLUOB could not have a vault
because it was designed as a Radiological Facility. At issue is whether there is enough vault space
in PF-4 to support production of 80 ppy.
Over many years, the PF-4 vault has accumulated much material that is no longer needed for
programmatic operations. Some, in excess to current or foreseeable needs, can be deacquisitioned and shipped to the Waste Isolation Pilot Plant for permanent disposal, to Savannah
River Site for other disposition, or to Y-12 for uranium items. Plutonium that might be needed for
future operations could be stored elsewhere, such as Pantex Plant, which stores thousands of pits,
98
Information provided by Los Alamos National Laboratory, October 23, 2013.
Congressional Research Service
35
U.S. Nuclear Weapon “Pit” Production Options for Congress
or the Device Assembly Facility at the Nevada National Security Site, an HC-2/SC-I facility that
has space available for storage of plutonium, or the K Reactor at Savannah River Site, which is
currently used to store plutonium. Thus there are many ways to reduce the amount of material
stored in the PF-4 vault, and NNSA accelerated vault cleanout as a mitigation effort associated
with the deferral of CMRR-NF. Cleaning out the vault at PF-4 will make more room available for
plutonium needed for production. LANL has not studied whether cleanout would provide enough
space to support production of 80 ppy, but it appears likely that an effort focused on this goal and
coordinated with other sites could do so. Since additional PF-4 vault space could readily be made
available and it is not known how much would be needed to support production of 80 ppy, this
report does not discuss increasing available vault space as a separate option.
As a first step in moving through the options presented in Table 2, perhaps NNSA could …
Option 6: Conduct Plutonium-238 Work at INL or SRS
Pu-238 accounts for 40% of the MAR allowance at PF-4. Increasing pit production to 80 pits per
year (ppy) would increase MAR, and the increased pit foundry work, combined with Pu-238
work and other work, could exceed the MAR limit permitted for PF-4. One option would be to
move Pu-238 work out of PF-4, whether to a module connected to PF-4 or to another site. While
LANL is DOE’s center of excellence for plutonium, Pu-238 work is readily separable from Pu239 work because the two isotopes have very different properties and applications. Pu-239 is used
in weapons and might be used as mixed oxide fuel (a mixture of oxides of Pu-239 and uranium
isotopes) for nuclear power reactors, while kilogram quantities of Pu-238 are used to generate
heat for conversion to electric power for defense and space missions.99
In a report of May 2013, DOE examined several options for processing Pu-238 for fabrication of
radioisotope power systems.100 One was to upgrade the existing line in PF-4; however, this would
not address the possibility of reducing Pu-238 MAR in order to release MAR for weapons work.
The report also considered performing Pu-238 work at Idaho National Laboratory (INL) or
Savannah River Site (SRS). It did not address the LANL proposal to build modules connected to
PF-4, one of which might perform Pu-238 work.101
INL currently conducts operations with clad heat sources of Pu-238. It operates the Space and
Security Power Systems Facility, which further encapsulates the Pu-238 heat sources produced by
LANL, mates them to the power systems that convert their heat to electric power, tests the
resulting system, and delivers them to users.
99
For example, the National Aeronautics and Space Administration (NASA) Cassini mission, which used more Pu-238
than any other NASA mission, used a total of 23.8 kg of Pu-238 in three radioisotopic thermoelectric generators. Email
from NASA, November 12, 2013.
100
U.S. Department of Energy. Space and Defense Power Systems. Radioisotope Heat Source Infrastructure Review
Team. “Evaluation of Radioisotope Fuel Processing and Heat Source Fabrication Infrastructure Capabilities, Final
Report,” May 2013.
101
INL and SRS staff provided information on the possible use of their facilities for this option, personal
communications, October 24 and 31, 2013.
Congressional Research Service
36
U.S. Nuclear Weapon “Pit” Production Options for Congress
INL states that all current LANL Pu-238
operations could be transferred to INL, such
as recovery, purification, and source
At Idaho National Laboratory
fabrication, and that INL would have a
capacity of processing 5 kg per year. The
option to bring Pu-238 source fabrication to
INL would use an existing building, CPP1634, that was built in 1993 as an HC-2
building and was since downgraded.102 It
would have to be upgraded back to HC-2 in
order to handle 5 kg of Pu-238 per year.103
INL would also build an addition to CPP1634 that would more than double its size.
The upgrade would require modifying the
safety analysis report and upgrading the
building’s safety systems (such as ventilation)
and equipment (such as gloveboxes) to be
consistent with the hazards and operations
Source: Idaho National Laboratory.
proposed.104 Pu-238 in quantities of up to 16
kg is SC-III because it is unattractive for use in making a nuclear weapon. CPP-1634 would have
more security than is needed to meet SC-III requirements because it would be within the INL
security perimeter.
Figure 7. Building CPP-1634
The DOE report noted several advantages of establishing this capability at INL, including a new
design that minimizes down time and maintenance cost, and process improvements that minimize
operational costs and worker exposure and improve product quality. Also, locating the program in
a facility owned by DOE’s Nuclear Energy program, which is responsible for plutonium-238,
would allow “more control and lower operational costs as compared to operating within TA-55
that seems to have large overhead costs resulting in high operational costs.” Drawbacks include
“inexperience with Pu-238 processing operations,” “loss of co-location and leveraging with
related NNSA program,” risk due to uncertainty in safety requirements because “no new Pu-238
processing facility has been constructed in many years,” and “risk of moving Pu-238 operations
away from DOE’s plutonium operations center of excellence,” that is, LANL.105
There is also an SRS option. From the mid-1960s to early 1980s, SRS produced Pu-238 in its
reactors by bombarding neptunium-237 target tubes with neutrons. It then dissolved the target
tubes, separated and purified Pu-238 in H Canyon, turned the Pu-238 into plutonium oxide in
HB-Line, pressed that material into heat sources, and clad them in iridium in the 235-F facility. In
1983, the last neptunium-237 targets were irradiated and in 1985-1986, Pu-238 operations were
102
“CPP” stands for Chemical Processing Plant, a historical name for the site.
103
Pu-238 is 275 times more radioactive than Pu-239, so 5 kg of the former has the same level of radioactivity as 1,375
kg of the latter.
104
Because Pu-238 is an intense emitter of neutrons and gamma rays, people working with it require shielding, so the
work could not be done in open-front hoods or standard gloveboxes.
105
Department of Energy, “Evaluation of Radioisotope Fuel Processing and Heat Source Fabrication Infrastructure
Capabilities, Final Report,” pp. 4-2, 4-3.
Congressional Research Service
37
U.S. Nuclear Weapon “Pit” Production Options for Congress
moved to LANL. Subsequently, the last SRS reactor was shut down in 1993. Work is underway to
develop the capability to produce Pu-238 at Oak Ridge National Laboratory (TN).106
SRS has two buildings that could be used for Pu-238. Its H Canyon is a large, highly shielded
concrete structure, approximately 1,000 feet long by 120 feet wide by 75 feet high, that began
operations in 1955. It was built to process irradiated targets and fuel rods from SRS reactors for
various nuclear materials. These targets and fuel rods had very high levels of radioactivity, so
they required processing in a facility that was heavily shielded and remotely operated. As such, it
is off limits to personnel, and all material is processed by moving it through pipes or handling it
with a remotely operated crane. It is the only remaining U.S. facility that is heavily shielded and
remotely operated and that can chemically process large quantities of radioactive material, such
as spent fuel rods. It is currently operational, processing irradiated fuel stored in an underwater
pool at SRS. SRS also has the HB-Line, which is built atop H Canyon to provide a work space
with heavily shielded gloveboxes for work on Pu-238. It became operational in the late 1980s. It
is currently operating, but its Pu-238 lines would have to be restarted, which could take three or
four years. A third building at SRS that was used in the Pu-238 program, Building 235-F,
contained a process line that fabricated heat sources from Pu-238 oxide. However, the facility has
not been operated since 1984 and is not part of the current proposal due to high levels of
contamination.
In the SRS plan, Pu-238 could arrive at the plant as irradiated target tubes of neptunium-237 from
a DOE reactor, as unpurified Pu-238 oxide from Russia, or as scrap Pu-238 oxide.107 These
oxides would be dissolved in nitric acid in the HB-Line. This solution would be transferred
through pipes to H Canyon, where it would be purified by removing other chemical elements.
The purified Pu-238 solution would be transferred back to HB-Line, where plutonium would be
precipitated out of solution and then turned into plutonium oxide, a solid. In an option in the SRS
plan, a new Plutonium Testing and Processing Facility (PTPF), consisting of prefabricated hot
cells (capable of handling highly radioactive material) and gloveboxes, would be installed in H
Canyon. This facility would press plutonium oxide into pellets, which would be fabricated into
heat sources, clad in iridium, and sent to INL, where they would be mated with power generating
equipment and then delivered to end users.
The DOE report noted several advantages and disadvantages of this option. H Canyon and
HB-Line can process a wide quantity range of Pu-238, from 1 to over 30 kg per year. These
facilities are built to high safety standards. Infrastructure requirements are well understood, such
as environment, safety, and health, material control and accountability, and waste management;
there is also an AC capability. On the other hand, the length of time that missions will support H
Canyon is not clear because “its mission length is defined by a campaign by campaign basis.”
Operations there are planned until 2018-2020, with operations beyond that time uncertain.
106
“ORNL’s plutonium-for-space project on pace,” Frank Munger’s Atomic City Underground (blog), December 26,
2013, http://knoxblogs.com/atomiccity/2013/12/26/ornls-plutonium-space-project-pace/.
107
The United States has reportedly purchased Pu-238 (in oxide form) from Russia since the 1990s. See Geoffrey
Brumfiel, “Curiosity’s Dirty Little Secret,” Slate, August 20, 2012, http://www.slate.com/articles/health_and_science/
science/2012/08/mars_rover_curiosity_its_plutonium_power_comes_courtesy_of_soviet_nukes_.single.html.
However, this material still requires the plutonium-238 operations carried out in the United States, such as removing
impurities, fabricating plutonium oxide into ceramic pellets, and encapsulating the fuel in cladding.
Congressional Research Service
38
U.S. Nuclear Weapon “Pit” Production Options for Congress
Figure 8. H Canyon and HB-Line
At Savannah River Site
Further, required production “[does] not
necessitate a large throughput capacity. Thus,
revitalization of the facilities may not be
justified.” And without a long-term mission,
there is no clear advantage to building
PTPF.108 At issue: There is value to the
weapons program in removing Pu-238 from
PF-4. Would processing Pu-238 be a longterm mission that would justify, and that
might contribute funding to, PTPF?
The DOE report compared cost and schedule
estimates for these two options, as follows.109
Source: Savannah River Site.
•
For the INL option, $12
million for technology
development taking three years, and $110 million to $260 million for generalpurpose heat source fabrication capability, taking five years.
Notes: The photo shows HB-Line atop H Canyon.
•
For the SRS option, $28 million to $45 million for plutonium purification
revitalization, taking 3½ to 4½ years, and $125 million to $170 million for PTPF,
taking four to five years.
•
Combining these figures, the INL option would cost $122 million to $272 million
and take eight years, and the SRS option would cost $153 million to $215 million
and take 7½ to 9½ years.
It must be emphasized that these estimates are preliminary and are not based on extensive
analysis.
DNFSB commented that “H-Canyon is exhibiting degradation of systems and structures that if
not addressed, could challenge safe operations and pose a risk to facility workers. … DOE
completed repairs to address some of the identified deficiencies … There are some safety-related
repairs that have not yet been completed.”110
Having addressed Pu-238, this report now turns to options to address analytical chemistry …
Option 7: Conduct Some or All Analytical Chemistry at LLNL or SRS
Lawrence Livermore National Laboratory (LLNL) has a large building, Building 332, that is part
of its “Superblock” complex.111 Building 332 was built for plutonium work. One wing
(“Increment 1”) was built in 1961; another wing (“Increment 3”) was built in 1975. Increments 1
108
Department of Energy, “Evaluation of Radioisotope Fuel Processing and Heat Source Fabrication Infrastructure
Capabilities, Final Report,” May 2013, p. 4-4.
109
Ibid., p. 3-6.
110
U.S. Defense Nuclear Facilities Safety Board. “Summary of Significant Safety-Related Aging Infrastructure Issues
at Operating Defense Nuclear Facilities.” Fourth Annual Report to Congress, Enclosure, p. E-8, http://www.dnfsb.gov/
sites/default/files/Board%20Activities/Reports/Reports%20to%20Congress/2013/ar_20131030_23051.pdf.
111
This section is based on discussions with Livermore and Los Alamos staff, October 2013. For information on
Superblock, see Joseph Sefcik, “Inside the Superblock,” Science & Technology Review (a Lawrence Livermore
National Laboratory publication), March 2001, https://www.llnl.gov/str/March01/Sefcik.html.
Congressional Research Service
39
U.S. Nuclear Weapon “Pit” Production Options for Congress
and 3 are laboratory buildings; Increment 2 is the control room, without laboratory space.
Building 332 was a Hazard Category 2/Security Category I facility, like PF-4, so it was used to
handle hundreds of kilograms of plutonium. Its ventilation systems (including fans and HEPA
filters) and electrical systems have been updated in the past decade. Even though Livermore is in
a seismically active area, Building 332 was designed to take into account seismicity, and an
analysis showed that it does not require an upgrade to make it more seismically robust. Its
gloveboxes (new and retrofitted) are reinforced so as not to fall over in an earthquake.
Building 332 remains an HC-2 building, but its plutonium quantity is limited by its Security
Category. It was SC-I. To reduce vulnerability and security costs, NNSA consolidated SNM to
fewer facilities at fewer sites. As part of that plan, LLNL removed all SC-I/II quantities of SNM
from the lab, a task completed in September 2012.112 Building 332 is now SC-III, which limits it,
as a first approximation, to 400 g of plutonium metal and 16,000 g of plutonium in solution.113
Plutonium in solution poses much less risk—is less attractive to terrorists—than metallic
plutonium, which is why much more plutonium is allowed in solution than in metal form.
Building 332 has ample space for AC work. It has 24,000 total sf of laboratory space, as
compared to 19,500 sf for RLUOB and 22,500 sf in the CMRR-NF design. Some space is being
used to fabricate plutonium samples for experiments that subject plutonium to impact (such as
from a gas gun projectile) and for material processing studies. LLNL is currently using 5,000 sf
for AC and MC, and could make another 6,000 sf available. Building 332 has a substantial excess
of air handling capacity, which would support the use of open-front hoods. LLNL believes that
Building 332 has sufficient air handling capacity to support AC for 80 ppy.114
Once analyzed, samples would be processed as waste. For final disposition, waste is shipped to
WIPP. Since WIPP does not accept liquids, liquid waste is solidified by mixing it with cement.
LANL and LLNL differ in how they would handle waste. LANL has the capability to recover
plutonium from liquid samples and to process the waste stream, solidifying it for shipment to
WIPP. LANL uses AC to support these operations. LANL also uses AC to send liquid waste to
LANL’s Radioactive Liquid Waste Treatment Facility because that facility places requirements
(such as the amount of mercury) in the waste it accepts for treatment. LLNL does not have these
capabilities, and would not perform AC on material (liquids and solids) to be disposed of as
waste. However, the liquid waste generated by the AC for 80 ppy would be very much less than
the waste that LANL generates for various other missions, so LLNL holds that simply cementing
the liquid waste would be a satisfactory way to prepare its liquid waste for shipping.
112
U.S. Department of Energy. National Nuclear Security Administration. “NNSA Completes Removal of All High
Security Special Nuclear Material from LLNL,” press release, September 21, 2012, http://nnsa.energy.gov/mediaroom/
pressreleases/snmremoval092112.
113
More precisely, the upper bound for SC-III is as follows: the sum of the weight of plutonium metal plus 1/3 the
weight of such other materials as plutonium oxide must be less than 400 grams and the weight of plutonium in solution
(of up to 25 grams of plutonium per liter) must be less than 16,000 grams. See U.S. Department of Energy. Office of
Security and Safety Programs Assurance. Nuclear Material Control and Accountability. Manual DOE M 470.4-6,
Change 1, August 14, 2006, Section A, pages I-8 throug
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.