Environmental Requirements Addressed During Corps Civil Works Project Planning: Background and Issues for Congress

Congressional research reportSep 5, 2013

Ask Donna

What actually matters in this document.

Text

Environmental Requirements Addressed

During Corps Civil Works Project Planning:

Background and Issues for Congress

-name redactedAnalyst in Environmental Policy

September 5, 2013

Congressional Research Service

7-....

www.crs.gov

R43209

Environmental Requirements Addressed During Corps Civil Works Project Planning

Summary

Under its civil works mission, the U.S. Army Corps of Engineers (the Corps) undertakes water

resource projects. The majority of Corps civil works projects involve commercial navigation,

flood risk management, and ecosystem restoration.

Before Congress will authorize the construction of or appropriate funds for most Corps civil

works projects, the agency must prepare various studies, reports, and evaluations of project

benefits and detriments, including adverse environmental impacts. Those impacts, in turn, may

obligate the Corps to demonstrate compliance with certain environmental requirements.

Environmental Requirements Addressed During Planning

Some interested stakeholders have questioned the degree to which environmental requirements

hamper project delivery, and debate what changes could be made to accelerate delivery. In

particular, some have questioned whether compliance with federal environmental laws and

regulations delays the completion of reports that Congress uses to inform legislation authorizing

project construction such as Water Resources Development Acts (WRDAs).

The planning process is used to develop a recommended water resource project that Congress

may authorize. Among other requirements, planning must include an evaluation of project

impacts on the environment and applicable federal requirements that arise from those impacts.

Depending on the project, a wide array of environmental requirements may apply. There are two

types of environmental requirements that may affect a water resource project: those that obligate

the Corps to evaluate certain issues during planning, and those intended to protect human health

or minimize harm to a protected resource from project-specific impacts. Integrating the

evaluation of environmental impacts into project planning is intended, in part, to minimize the

potential for unanticipated impacts from the project and mitigate the severity of unavoidable

adverse impacts.

Generally, the Corps identifies and considers environmental impacts, including any applicable

requirements arising from federal environmental laws such as the Clean Water Act, within the

framework of documenting compliance with the National Environmental Policy Act (NEPA).

Compliance with NEPA and other “environmental” laws may obligate the Corps to consult with

outside agencies to determine the degree to which a protected resource (e.g., historic site,

endangered species habitat, wetlands) may be affected; to develop measures to mitigate or

minimize adverse impacts; and/or to identify required approvals or permits.

Factors That Cause Delay

The time that it takes the Corps to move from one phase of project development to another

depends on a complex array of factors. When comparing individual Corps projects to each other,

larger, more complex, and costly projects generally take longer. When looking at all civil works

projects, Congress’s role in authorizing required studies and project construction, and in

appropriating funds necessary for the required studies and construction, often significantly affects

project delivery timing.

Given the range of environmental issues and impacts that Congress has statutorily obligated the

Corps to evaluate, the body of requirements that may be deemed environmental that apply to

Congressional Research Service

Environmental Requirements Addressed During Corps Civil Works Project Planning

Corps projects can represent a significant element of project development. What is unclear is

whether or which specific environmental requirements routinely delay project delivery, in

general, or completion of necessary reports to Congress, in particular.

Scope of This Report

This report provides information about the civil works project development process, with a focus

on the planning phase of development and challenges associated with determining the extent to

which project delivery is affected by environmental requirements. To provide some context, the

report identifies selected issues that have arisen in the past 50 years that resulted in Congress

enacting various environmental requirements that affect the Corps’ project planning process and

that are intended to minimize adverse impacts of Corps projects. It also provides an overview of

key federal requirements that generally must be addressed before the Corps’ Chief of Engineers

will issue a report (i.e., a Chief’s Report). The transmission of that report to Congress by the

Assistant Secretary of the Army for Civil Works is typically the final step in the planning process

and is intended to inform congressional authorization of project construction.

Congressional Research Service

Environmental Requirements Addressed During Corps Civil Works Project Planning

Contents

Introduction...................................................................................................................................... 1

Background ...................................................................................................................................... 2

The Evolution of Environmental Requirements ........................................................................ 4

Changes in Water Resources Development Acts ....................................................................... 6

Overview of the Current Planning Process for Civil Works Projects ........................................ 7

Environmental Evaluation and Compliance Requirements ........................................................... 10

Corps-Specific Requirements Addressed During Planning ..................................................... 11

Impact-Specific Environmental Requirements ........................................................................ 12

Integrating Environmental Requirements into the Project Development Process ......................... 15

Detailed Actions During the 21 Steps of Project Development............................................... 16

Factors Identified as Causing Delay .............................................................................................. 18

Figures

Figure 1. 21 Steps of Civil Works Project Development ................................................................. 9

Tables

Table 1. Selected Federal Laws That Require Outside Agency Review ........................................ 14

Contacts

Author Contact Information........................................................................................................... 20

Congressional Research Service

Environmental Requirements Addressed During Corps Civil Works Project Planning

Introduction

U.S. “water resources” include streams, rivers, wetlands, estuaries, lakes, and coasts. Those

resources support billions of dollars in commerce, provide drinking water, supply habitat for fish

and wildlife, and provide recreational opportunities. The U.S. Army Corps of Engineers (the

Corps) is one of several federal agencies that undertake water resource projects.1 The majority of

Corps civil works projects involve commercial navigation, flood risk management, and

ecosystem restoration.

Congress generally authorizes Corps activities and provides policy direction in Water Resources

Development Acts (WRDAs). Many studies of civil works projects prepared by the Corps are

prepared in response to a project-specific authorization from Congress to study a water resources

problem.2 Generally, the outcome of the Corps’ study process is a Corps Chief of Engineers report

to Congress (a Chief’s Report) that supports the recommendation for Congress to authorize

project construction.

Project development involves multiple stages, from study initiation to planning and design and

ultimately to construction and operation. Years or even decades may pass from the time the Corps

is authorized to study a water resources-related problem and the Corps constructs a project to

address that problem. In recent decades, few projects authorized for study have led to constructed

projects. Of the projects that do proceed, various factors affect the time it takes to move from

project planning to the completion of construction. Generally, the most significant factors in some

way relate to the availability of federal funding and the time it takes to obtain necessary

congressional authorizations.

Recently, to expedite project development, congressional attention has focused on activities that

must be completed before a Chief’s Report can be submitted to Congress recommending project

construction.3 These activities generally comprise the planning stage of project development.

Pursuant to various statutory requirements, during project planning, the Corps is obligated to

complete a potentially complex array of studies, reports, and evaluations.

In an effort to expedite that project delivery, some groups have focused particular attention on the

time it takes the Corps to comply with federal environmental requirements that must be addressed

during planning. Given the congressional interest in this topic, this report assesses certain

elements of the project planning process in an effort to identify whether or the degree to which

meeting environmental requirements is a significant cause of delay in project delivery. To do so,

the report provides background information on the potentially wide array of environmental

requirements that may apply to a given civil works project (including why Congress established

such requirements), how the Corps integrates compliance with those requirements into the project

planning process, and how required elements of the planning process may affect project delivery.

1

For example, the Bureau of Reclamation also undertakes water resource projects.

This includes projects that require the preparation of a feasibility report, pursuant to 33 U.S.C. §2282, but does not

include projects referred to as “continuing authorities” projects, or CAPs.

3

See the House Committee on Transportation and Infrastructure, Subcommittee on Water Resources and

Environment’s hearing “A Review of the United States Army Corps of Engineer’s Reports,” June 5, 2013,

http://transportation.house.gov/hearing/review-united-states-army-corps-engineers-chief%E2%80%99s-reports.

2

Congressional Research Service

1

Environmental Requirements Addressed During Corps Civil Works Project Planning

To provide necessary background, this report identifies selected issues that have arisen in the past

50 years that resulted in Congress enacting numerous environmental requirements that (1)

directly affect the Corps’ project planning process and (2) are intended to minimize adverse

project-specific impacts. It also provides an overview of the Corps’ environmental evaluation and

compliance requirements, including how those requirements are integrated into the project

planning process. More specifically, the report provides an overview of the federal requirements

that obligate the Corps to evaluate the impacts of a given civil works project and the compliance

requirements that generally must be addressed before the Corps will submit a Chief’s Report to

Congress.

The Corps project development process is complex. By focusing on environmental requirements

that must be addressed during planning, this report does not identify every element of project

development that may affect project delivery. More specifically, it does not provide detail

regarding other factors that have been identified as particularly relevant to the timing of project

delivery—federal funding availability and the timing of necessary congressional approvals. As

they affect the project planning process, selected issues associated with congressional funding

and approvals may be discussed, but are generally beyond the scope of this report. For

information about those issues, see CRS Report R41243, Army Corps of Engineers Water

Resource Projects: Authorization and Appropriations, and CRS Report R41961, Army Corps

Fiscal Challenges: Frequently Asked Questions, by (name redacted) and (name redacted).

Background

The majority of civil works projects undertaken by the Corps fall within its navigation, flood risk

management, and ecosystem restoration and environmental protection missions. Historically,

navigation and flood risk projects involved a potentially wide range of activities such as the

construction of levees, floodgates, or dams; channel deepening (i.e., dredging) or widening; or

changing floodplain uses. Some of those projects resulted in adverse impacts such as

unanticipated flood damage after alterations to wetlands or floodplains, the destruction of aquatic

plant or animal habitat, or impaired or altered water quality after dredging or channelizing

waterways or building locks and dams.

The Corps’ civil works mission was expanded to include ecosystem restoration projects, in part,

to authorize the agency to address adverse effects from past civil works projects. Addressing

those impacts involves actions such as restoring natural channel conditions, modifying

obstructions to fish passage, or removing levees to restore wetland hydrology.

Many of the environmental requirements that apply to Corps civil works projects today were put

in place at the direction of Congress to ensure that project planning reduces the potential for

unanticipated adverse impacts and/or identifies measures to minimize or mitigate unavoidable

impacts. In reviewing the range of federal4 environmental requirements potentially applicable to

civil works projects, the requirements may fall into the one of the following categories:

4

State or tribal requirements generally do not apply to civil works projects. However, states or tribes may be authorized

to implement certain federal environmental laws. For example, depending on a project’s impacts, the Corps may be

required to comply with state water quality requirements implemented by an authorized state pursuant to the Clean

Water Act.

Congressional Research Service

2

Environmental Requirements Addressed During Corps Civil Works Project Planning

•

Requirements to address certain environmental aspects of a proposed

project during planning. These include requirements, established by Congress,

that apply explicitly to federal investment in water resources development. For

example, the Corps is obligated to conduct specific studies, reports, and

evaluations to ensure that the environmental impacts of a project are identified

and considered; evaluate a project’s economic and public safety benefits

compared to its adverse environmental impacts; and identify opportunities to

protect, preserve, and/or enhance the quality of the environment.

•

Requirements intended to protect human health or minimize harm to a

protected resource. These include requirements that arise from federal laws,

regulations, executive orders, or Corps policy that may apply as a result of

project-specific impacts. Compliance requirements will be identified during

planning and will generally depend on the degree to which project impacts

adversely affect air or water quality, or natural or cultural resources specifically

protected by Congress (e.g., historic sites, Native American graves, endangered

species or their habitat). They may also include any requirements that direct the

Corps to enhance the quality of the environment.

Both sets of requirements are largely implemented by the Corps, but may require the Corps to

consult with or obtain some level of review by an outside federal agency or a state or tribal

agency authorized to implement a specific federal law (see Table 1 in the section “ImpactSpecific Environmental Requirements”).

As required by Congress, the Corps cannot recommend a project to Congress for construction

authorization until it has evaluated and can describe “economic, environmental, and social

benefits and detriments” of a recommended plan and possible alternative plans.5 A key element of

its evaluation of environmental detriments and benefits involves identifying a project’s impacts

and environmental compliance requirements associated with those impacts.

When there is debate over the degree to which environmental requirements affect project

delivery, that debate often centers around the time it takes the Corps to demonstrate compliance

with specific requirements. Most recently, that debate has centered around the time that it takes

the Corps to complete some level of coordination with or obtain necessary approvals from other

federal agencies (e.g., the Department of the Interior’s U.S. Fish and Wildlife Service). The

process required to obtain necessary federal reviews of civil works projects may be highly

complex, among other reasons, in order to ensure compliance with protections established by

Congress. As a result, they may require a high degree of resources agency involvement (e.g., in

developing ecosystem restoration projects).

To understand why a potentially complex array of environmental requirements may apply to

water resource projects, it is useful to understand the social and environmental concerns that led

Congress to enact the various laws that may apply to both the project development process and

projects themselves.

5

33 U.S.C. §2282(a)(2).

Congressional Research Service

3

Environmental Requirements Addressed During Corps Civil Works Project Planning

The Evolution of Environmental Requirements

How the Corps is currently obligated to evaluate the environmental impacts of a project, as well

as document and demonstrate compliance with any requirements that may apply as a result of

those impacts, has evolved over many years. Several key requirements that require the Corps to

plan and implement projects as it does currently were originally enacted in the 1960s and 1970s.

It was during that time that national priorities and perspectives on the federal investment in water

resources development were changing; at the time, public attention was turning to the impacts

that human activities were having on the human and natural environment—that is, adverse

impacts on air and water quality and on cultural and natural resources such as historic sites, plant

and animal species, and/or their habitats.

Beginning in the 1960s, Congress began to respond to that increased public awareness and

concern by enacting various laws that affect project planning, development, approval, and

funding, as well as laws intended to protect human health and the environment. Most

requirements that currently apply to water resource project development that may be deemed

“environmental” represent past efforts by Congress to minimize the potential for unforeseen

adverse impacts and/or to mitigate or minimize any unavoidable adverse impacts.

During the 1960s, Congress also turned its attention to the effects that federally funded projects

were having on the environment—including Corps water resource projects. Generally, until the

mid-1960s, analysis of water resource projects focused on the potential economic benefits and

costs. With increased attention to adverse impacts of civil works projects, including the costs

associated with remedying those impacts (see text box below), Congress enacted various laws

that broadened Corps planning requirements to include an evaluation of project impacts to

environmental quality.

Of particular relevance to the Corps’ planning process today was the enactment of the following:

•

The Water Resources Planning Act of 1965 (P.L. 89-80)—created the Water

Resources Council (WRC, now defunct due to lack of funding) and established

“Water Resources Planning” requirements (42 U.S.C. §1962), which created a

coordinated planning process related to the conservation, development, and use

of water resources. The law also required the establishment of principles,

standards, and procedures to be used for the formulation and evaluation of water

and related land resources projects. A WRC Task Force subsequently specified

that water resources agencies should identify impacts in four areas—national

economic development, environmental quality, regional economic development,

and social well-being.

•

The National Environmental Policy Act of 1969 (NEPA)—requires all federal

agencies to consider the environmental impacts of an action and to give the

public a meaningful opportunity to learn about and comment on the proposed

project before a final decision is made to proceed with that action. The NEPA

compliance process forms the framework used by the Corps to identify any

project impacts to natural or cultural resources or to air or water quality,

including impacts that may require the Corps to comply with other federal

environmental requirements. Depending on the resource affected, the Corps is

Congressional Research Service

4

Environmental Requirements Addressed During Corps Civil Works Project Planning

required to coordinate its NEPA analysis in consultation with agencies with

jurisdiction over any affected resources or expertise necessary to assess the

significance of the impacts.6

By the late 1960s, construction

of major waterworks had

declined. Changing national

priorities and local needs,

increasing construction costs,

and completed projects at most

prime locations decreased the

attractiveness of major water

projects.7

At the same time, as a reflection

of changing national priorities,

congressional concern over the

impacts that human activities

were having on the quality of the

human and natural environment

was further demonstrated in

wide-ranging laws enacted in the

late 1960s and into the 1970s.

Included among them were the

National Historic Preservation

Act (1966), the Endangered

Species Act (1973), and the

Clean Water Act (1972). By the

mid-1970s, the Corps began to

identify and coordinate its

compliance obligations under

NEPA and the Water Resources

Planning Act by integrating its

assessment of environmental

impacts into the project planning

process. That included

identifying any applicable nonNEPA environmental

requirements and documenting

necessary compliance

requirements during project

planning.

Impacts and Costs of the

Central and Southern Florida (C&SF) Project

In the early 1900s, the principal impediment to development in south

Florida was flooding. To realize the economic potential of the state’s

natural resources, major drainage projects were initiated by the state of

Florida and later in partnership with the Corps. That partnership worked

to control conditions hampering economic development.

Authorized by Congress in 1948, activities associated with the Central

and Southern Florida (C&SF) Project were intended to control flooding,

provide water for municipal, industrial, and agricultural uses, prevent

saltwater intrusion, create a water supply for Everglades National Park,

and protect fish and wildlife resources. The primary system includes

about 1,000 miles each of levees and canals, 150 water control structures,

and 16 major pump stations. To create that system, the Kissimmee River

was channelized; Lake Okeechobee was diked to prevent uncontrolled

overflows; part of the Everglades was drained and groundwater levels

were managed to reduce flood damages to agricultural production; a

drainage system was constructed in the lower East Coast to allow for

urban, suburban, and agricultural development; and central portions of

the Everglades were diked to store water for human needs and to make

deliveries to Everglades National Park.

The emphasis on economic goals focused project design on development

of the region with little understanding of or concern for the

consequences to the Everglades ecosystem. As a result of CS&F projects,

nearly half of the original Everglades ecosystem was converted to

agricultural uses. The overall impact of the construction and operation

was a substantial reduction in habitat options for wildlife, a network of

canals and levees that has accelerated the spread of polluted water and

exotic species and significantly reduced the water storage capacity within

the remaining natural system, and an unnatural mosaic of impounded and

overdrained marshes throughout the natural system.

In an effort to address these impacts and restore the south Florida

ecosystem, Congress authorized the Comprehensive Everglades

Restoration Plan (CERP, also known as the C&SF Restudy). The CERP

provides a guide to restore, protect, and preserve the water resources of

central and southern Florida, including the Everglades. Ultimately,

activities related to the plan will cover 16 counties over an 18,000square-mile area, and include more than 60 project elements.

Construction is expected to take more than 30 years and $11.9 billion.

Source: Project history taken from the Comprehensive Everglades

Restoration Plan, available at http://www.evergladesplan.org/.

6

For more information, see CRS Report RL33152, The National Environmental Policy Act (NEPA): Background and

Implementation, by (name redacted).

7

A discussion of the evolution of the Corps’ civil works mission is included in CRS Report R41243, Army Corps of

Engineers Water Resource Projects: Authorization and Appropriations, by (name redacted) and (name redacted).

Congressional Research Service

5

Environmental Requirements Addressed During Corps Civil Works Project Planning

Changes in Water Resources Development Acts

Since 1974, congressional authorization to study or construct civil works projects has been

provided to the Corps largely through Water Resources Development Acts (WRDAs). Early

WRDAs were largely project authorization acts, but since the mid-1980s, WRDAs have also

included significant directives to the Corps with regard to the management of environmental

issues or impacts.8 The following are selected9 examples:

•

WRDA 1986 (P.L. 99-662). Directed the Corps to improve fish habitat affected

by water resources facilities, authorized changes in justification for beach

nourishment projects, and authorized the Corps to determine the need for and

make modifications to existing structures to improve the quality of the

environment or to address project operations that degraded environmental

quality.

•

WRDA 1990 (P.L. 101-640). Directed the Secretary of the Army to include

environmental protection as a primary Corps mission.

•

WRDA 1992 (P.L. 102-580). Authorized the Corps to use the “spoils” from

dredging in implementing projects for protecting, restoring, and creating aquatic

and ecologically related habitats, including wetlands.

•

WRDA 1996 (P.L. 104-303). Authorized the Secretary of the Army to carry out

aquatic ecosystem restoration and protection projects and to add environmental

protection and restoration as another project purpose.

•

WRDA 2000 (P.L. 106-541). Approved the Florida Everglades restoration

program, the agency’s first multiyear, multibillion-dollar effort of this type.

These legislative changes gave the Corps environmental responsibility beyond traditional water

resources development. More recently, WRDA 2007 (P.L. 110-114) included “Project

Streamlining” requirements that directed the Secretary of the Army to develop and implement a

coordinated review process for water resource project development.

WRDA 2007 also required the Secretary of the Army to revise the Principles and Guidelines

(P&G) for water resource implementation studies.10 Until recently, the Corps used the P&G to

guide its development of processes and procedures for formulating, evaluating, and implementing

water resources development projects.11 In March 2013, the Administration released Principles

8

Prior to WRDAs, Congress typically authorized Corps projects in successive Rivers and Harbor and Flood Control

Acts.

9

Primarily amendments identified in the Analytical Methods and Approaches for Water Resources Project Planning,

prepared by the Panel on Methods and Techniques of Project Analysis, Committee to Assess the U.S. Army Corps of

Engineers Methods of Analysis and Peer Review for Water Resources Project Planning, National Research Council,

2004, National Academies Press, p. 21.

10

See Section 2031(b) in WRDA 2007, “Water Resources Principles and Guidelines.” Under Section 2031(b)(3), the

Corps was directed to consult with the Secretaries of the Interior, Agriculture, Commerce, Housing and Urban

Development, Transportation, Energy, and Homeland Security, the Administrator of the Environmental Protection

Agency (EPA), the National Academy of Sciences, and the Council on Environmental Quality (CEQ), and to solicit

and consider public and expert comments.

11

The P&G were originally prepared pursuant to Section 103 of the Water Resources Planning Act (42 U.S.C. 1962a2). The 1983 P&G issued by the WRC are reflected in two documents, Economic and Environmental Principles for

Water and Related Land Resources Implementation Studies and the Economic and Environmental Guidelines for Water

(continued...)

Congressional Research Service

6

Environmental Requirements Addressed During Corps Civil Works Project Planning

and Requirements for Federal Investments in Water Resources (Principles & Requirements, or

P&R), as well as draft Interagency Guidelines for implementing the P&R.12

Section 2031 of WRDA 2007 also amended the national Water Resources Planning policy,13

included originally in the Water Resources Planning Act, to specify that all water resource

projects should reflect national priorities, encourage economic development, and protect the

environment by

•

seeking to maximize sustainable economic development;

•

seeking to avoid the unwise use of floodplains and flood-prone areas and

minimizing adverse impacts and vulnerabilities in any case in which a floodplain

or flood-prone area must be used; and

•

protecting and restoring the functions of natural systems and mitigating any

unavoidable damage to natural systems.

This policy highlights the evolution of water resource project development. Once focused largely

on project construction for “flood control” or “economic development,” congressionally derived

policy now includes the consideration of measures that may be needed to protect the environment

and/or mitigate unavoidable damage to the quality of the environment, not simply compliance

with applicable requirements intended to protect the environment.

Overview of the Current Planning Process for Civil Works Projects

The water resources development process that evolved since the 1960s reflects changing needs

and concerns related to environmental impacts, as those needs and concerns were identified by

Congress. Most of those changes added requirements or steps to the civil works project

development process. The resulting process is complex.

The Corps’ civil works program is led by a civilian Assistant Secretary of the Army for Civil

Works (ASA(CW)). A military Chief of Engineers oversees the Corps’ civil and military

operations and reports on civil works matters to the ASA(CW). A Director of Civil Works reports

to the Chief of Engineers. The Corps’ civil works responsibilities are organized under eight Major

Subordinate Commands (MSCs, also referred to as Divisions), further divided into 38 Districts.

Figure 1 outlines the steps of the project development process. It typically begins when a local,

nonfederal interest identifies a water resources problem that it wants the Corps to address. If the

Corps determines it appropriate, a request is made to Congress to authorize the Corps to study the

issue. Project-specific study authority is typically provided in a resolution by an authorizing

committee or a WRDA.14 While a study authorization may allow the Corps to receive federal

funding to initiate a study, those funds must be appropriated separately for the study to proceed.

(...continued)

and Related Land Resources Implementation Studies.

12

See the CEQ web page, “Updated Principles and Guidelines for Water and Land Related Resources Implementation

Studies,” at http://www.whitehouse.gov/administration/eop/ceq/initiatives/PandG.

13

See WRDA 2007 Section 2031 amendments to 42 U.S.C. §1962-3(a).

14

The congressional authorizing committees are the House Committee on Transportation and Infrastructure and the

Senate Committee on Environment and Public Works.

Congressional Research Service

7

Environmental Requirements Addressed During Corps Civil Works Project Planning

Not all authorized studies receive appropriations, or funds may be appropriated years after the

study is authorized.

Once the initial study is approved and federal funds are made available, the Corps planning

process begins with the preparation of the following:

•

A reconnaissance study—an investigation into the water resources problem and

assessment of the federal government’s interest in the project (i.e., whether it

falls within one of the Corps’ missions), as well as the interest and ability of the

nonfederal sponsor(s) to participate in the project. If nonfederal support/funding

is forthcoming and the Corps recommends proceeding, a feasibility study can

begin once federal funding for the feasibility study is made available.

•

A feasibility study and report—studies, reports, and evaluations necessary to

formulate and recommend solutions to the water resources problem identified in

the reconnaissance study. A feasibility study that results in the preparation of a

feasibility report is required to include a description of the economic,

environmental, and social benefits and detriments of the recommended and

alternative plans considered by the Corps.15 To provide that information, among

other activities, the District in which the project is proposed formulates

alternative plans, investigates engineering feasibility, conducts cost-benefit

analyses, and evaluates potential environmental impacts of project alternatives

and compliance requirements associated with those impacts.

It is generally during the feasibility study process that actions necessary to comply with NEPA are

completed, as well as evaluations necessary to demonstrate compliance with any other applicable

environmental requirements (see discussion in the section below).

After all supporting evaluations, studies, and reports are completed, a feasibility report and

associated documents are subject to review and approval at the Headquarters level. Once those

reviews are complete, the Chief of Engineers uses these documents to produce a Chief’s Report,

which, if the Corps chooses to move forward with the project, will support its recommendation to

Congress to authorize construction. The Chief’s Report, along with all the supporting information

about the project, is then submitted to the ASA(CW) and the Office of Management and Budget

(OMB) for policy compliance review; an informational copy of the Chief’s Report, feasibility

report, and other documents generally also are transmitted to Congress at this time.

These project planning steps are generally included among four phases of project development

and 21 distinct steps that must occur from project initiation to construction. Those phases and

steps, as they have been identified by the Corps, are illustrated in Figure 1. (Details are provided

in the chart in the “Detailed Actions During the 21 Steps of Project Development” section.)

15

33 U.S.C. §2282(a)(4).

Congressional Research Service

8

Environmental Requirements Addressed During Corps Civil Works Project Planning

Figure 1. 21 Steps of Civil Works Project Development

Source: CRS, based on the Corps’ “21 Steps to a Civil Works Project,” available at

http://planning.usace.army.mil/toolbox/process/21-Steps.pdf.

Congressional Research Service

9

Environmental Requirements Addressed During Corps Civil Works Project Planning

As illustrated in Figure 1, Congress is responsible for key milestones in the project development.

For example, Congress generally

•

authorizes the Corps to prepare a study of the water resources problem;

•

appropriates funds for the Corps study;

•

authorizes the Corps to construct a project; and

•

appropriates funds to the Corps to construct the project.

Congress also provides oversight during project development, in part, when deciding whether it

will continue to appropriate funds for necessary studies, reports, or evaluations that are required

throughout the project development process.

Generally, few Corps studies into water resources problems lead to project construction.

Historically, of every 100 reconnaissance studies undertaken, approximately 33% led to

feasibility studies and approximately 16% resulted in project construction.16 Further, the rate of

Corps authorizations exceeds the rate of the agency’s annual appropriations.17 Consequently, only

a subset of authorized activities is included in the President’s budget request and is funded by

enacted appropriations. This results in competition for funds among authorized activities during

the appropriations process.

To concentrate limited resources and to move ongoing projects toward completion, budget

requests by the George W. Bush and Obama Administrations have focused funding on projects

near completion, and have limited requests for funding for new studies and projects. Few new

Corps studies or projects have received funding in recent fiscal years; new activities or activities

that have not recently received funding in Administration requests are often referred to as “new

starts.” With limited new starts receiving funding from Congress, the majority of studies and

construction projects authorized in WRDA 2007 are currently unfunded and cannot proceed

unless or until funds are appropriated. As a result, whether or when project studies or construction

activities receive funding will have the greatest impact on the time it takes to deliver a project.18

Environmental Evaluation and

Compliance Requirements

During planning, the Corps is obligated to determine a project’s potential economic, social, and

environmental benefits and detriments. Processes and procedures that the Corps uses to ensure

compliance with that directive and any other applicable planning requirements are implemented

in accordance with the Corps’ Planning Guidance Notebook.19 The Notebook provides the overall

16

Lt. General Robert B. Flowers, Army Corps Chief of Engineers, oral statement, Reforms to Address the Corps of

Engineers Feasibility Studies, hearing before Senate Committee on Environmental and Public Works, Subcommittee

on Transportation and Infrastructure, March 15, 2001, available at http://epw.senate.gov/stm1_107.htm. These

proportions were cited using project data from the early 1990s. More recent statistics are not publicly available.

17

For example, it has been reported that the Corps has a construction backlog of $60 billion.

18

See CRS Report R41243, Army Corps of Engineers Water Resource Projects: Authorization and Appropriations, by

(name redacted) and (name redacted).

19

The Corps currently implements the planning stage of project development in accordance with “Engineer Regulation

1105-2-100: Planning Guidance Notebook,” April 2000. The “Planning Guidance Notebook” provides the overall

(continued...)

Congressional Research Service

10

Environmental Requirements Addressed During Corps Civil Works Project Planning

internal agency direction by which civil works projects are formulated, evaluated, and selected

for recommendation to Congress.

As the Corps implements the project development process, environmental requirements are

integrated into the planning process in accordance with the “Environmental Evaluation and

Compliance” requirements provided in the Notebook.20 Processes and procedures necessary to

meet the environmental evaluation and compliance requirements are intended to ensure Corps

compliance with NEPA, the Water Resources Planning Act (as reflected previously in planning

requirements established in the P&G and now in the P&R), and other applicable federal

environmental laws, regulations, and executive orders, and other applicable federal planning

requirements.

As noted previously, this report looks at two separate but related groups of environmental

requirements: (1) those explicitly applicable to water resources development that must be

addressed by the Corps during planning, and (2) those applicable as a result of project-specific

impacts that are intended to protect human health or minimize harm to certain aquatic and other

resources. Activities necessary to ensure compliance with the second group of requirements may

take place during project design, construction, and operation. However, it is largely within the

planning phase of development that the Corps completes required studies, reports, evaluations,

and analyses, and conducts necessary outside agency consultations to determine how compliance

with those requirements is to be met.

Integrating the Corps’ environmental evaluation and compliance requirements into the planning

process is intended to ensure that actions necessary to demonstrate Corps compliance with any

applicable requirements will be identified and largely addressed before Congress authorizes

project construction. For any given project, environmental compliance does not end with project

planning. It continues through final project design, construction, and operation. A discussion of

activities that may occur during those additional phases of project development and operation is

beyond the scope of this report.

Corps-Specific Requirements Addressed During Planning

The Water Resources Planning Act resulted in the establishment of planning requirements

applicable to all federal water resource projects, including those undertaken by the Corps. Among

other study planning objectives, Congress requires federal investment in water resources

development to characterize the beneficial and adverse effects of a project based, in part, on its

evaluation of environmental quality (EQ) measures associated with a project.21 Congress also

(...continued)

direction by which the Corps’ civil works projects are formulated, evaluated, and selected for overall implementation.

The April 2000 notebook includes appendixes that have been added at later dates to address various issues specific to

the project planning process.

20

Planning Guidance Notebook, Appendix C, “Environmental Evaluation and Environmental Compliance.”

21

EQ measures include activities that meet the national objective that federally financed water resource programs

enhance the quality of the environment, including the protection of the environment, and that opportunities for such

activities be considered in the planning, design, construction, and operation and maintenance of projects.

“Opportunities” for enhancement of the environment are to be sought through each phase of project development. See

42 U.S.C. §§1962-2 and 1962-3, and Water Resource Policies and Authorities: Corps of Engineers Participation in

Improvements for Environmental Quality, at 33 C.F.R. Part 236.

Congressional Research Service

11

Environmental Requirements Addressed During Corps Civil Works Project Planning

established additional planning requirements that apply to water resource projects undertaken

specifically by the Corps. These Corps-specific requirements are codified primarily in Title 33 of

the U.S. Code. Such requirements include, but are not limited to, those that specify the following:

•

Matters to be addressed in planning—requires that the quality of the total

environment (including preservation and enhancement of the environment) and

the preservation of cultural and historical values be included, among other

factors, in the formulation and evaluation of the costs/benefits of water resource

projects (§2281(a)).

•

Reconnaissance studies—requires a preliminary analysis of the federal interest,

costs, benefits, and environmental impacts of the project (§2282(b)).

•

Contents of feasibility reports—requires reports to describe the economic,

environmental, and social benefits and detriments of the recommended plan and

alternative plans considered by the Corps (§2282(a)(1)).

•

Benefits and costs attributable to environmental measures—directive to the

Corps to, when considering costs/benefits, evaluate measures to achieve EQ

benefits, such as fish and wildlife enhancement, at least equal to the costs of such

measures (§2284).

Processes and procedures to meet these and other Corps-specific planning requirements are found

primarily in the Corps’ Planning Guidance Notebook, but are also included in various other Corps

documents such as Engineer Regulations (ER), Engineer Circulars (EC), Engineer Pamphlets

(EP), and other documents.

Impact-Specific Environmental Requirements

As noted previously, during the planning process, the Corps must identify requirements that arise

from federal laws, regulations, executive orders, or Corps policy that may apply as a result of

project-specific impacts. The NEPA compliance process (hereinafter the NEPA process) generally

forms the framework that the Corps uses to identify those requirements and any actions that must

be taken to ensure Corps compliance with applicable requirements, before a project is authorized

for construction.

NEPA is intended, in part, to ensure that federal agencies include a consideration of the

environmental impacts of an action among other factors (e.g., economic or community benefits)

considered before the agency makes a final decision on a project. The Corps identifies and

demonstrates its consideration of environmental impacts, pursuant to NEPA, through the

preparation of certain publicly available environmental review documents. Requirements that

define the appropriate NEPA documents and required elements of those documents are found in

the regulations promulgated by the Council on Environmental Quality (CEQ)22 and by the

Corps.23 NEPA documents of relevance to Corps civil works projects will likely be the following:

22

40 C.F.R. Parts 1500-1508; CEQ regulations implementing NEPA that are broadly applicable to all federal agencies.

33 C.F.R. Part 230; Corps procedures for implementing NEPA. The Corps regulations supplement the CEQ

regulations to include detail specific to projects implemented by the Corps.

23

Congressional Research Service

12

Environmental Requirements Addressed During Corps Civil Works Project Planning

•

Environmental Impact Statements (EIS)—prepared for every major federal action

that may have a “significant” effect on the quality of the human environment.24

The Corps identifies feasibility reports for the authorization and construction of

major projects among those that normally require an EIS. An EIS is prepared in

two stages, a draft and final EIS. If significant time passes after issuance of a

final EIS (as may occur if significant time lapses between the time Congress

authorizes project construction and appropriates funding for that construction), a

Supplemental EIS may be required. Completion of the NEPA process is reflected

in the issuance by the agency of a final record of decision (ROD).

•

Environmental Assessments (EA)—prepared if a project’s degree of impact is

uncertain. It will result in either a determination that an EIS is needed or that a

Finding of No Significant Impact (FONSI) may be issued. Maintenance or

modifications to existing Corps facilities or structures may require an EA

resulting in a FONSI.

Among other information, both an EIS and, to a lesser degree of detail, an EA must include a

statement of the purpose and need for an action, a description of all reasonable alternatives to

meet that purpose and need, a description of the environment to be affected by those alternatives,

and an analysis of the direct and indirect effects of the alternatives, including cumulative

impacts.25 Similar information may also be required for water resource projects under other laws

or requirements. For example, during the planning process, the Corps is obligated to identify and

evaluate reasonable alternatives that may meet a project’s purpose and need, and to describe the

areas affected by the alternatives under consideration.

If a project requires the preparation of an EIS or EA, that generally means that it has some

impacts that will require compliance with additional (non-NEPA) environmental requirements.

Generally, any additional environmental requirements will include those that may apply to a

project as a result of that project’s physical or aesthetic impacts to natural or cultural resources

(e.g., direct impacts to fish and wildlife habitat or historic sites, or noise or visual impacts to those

resources) or to air or water quality. Those requirements will likely depend on the resources

affected, the severity of impacts to that resource, and the details of the applicable federal law.

A state, tribal, or federal agency may be required to provide the Corps with certain data or

analysis to allow the Corps to determine the severity of a project’s impact to a protected resource

or whether such a resource is in the project area (e.g., to identify sites of historic significance, the

presence of Native American graves). Depending on the compliance requirements triggered, the

Corps may also be required to consult with or obtain certain approvals (e.g., permits or licenses)

from other state, tribal, or federal agencies.

The potential extent of outside agency involvement will also likely depend on the type of Corps

project being planned. For example, any project that would involve the construction of a facility

that may adversely affect endangered species habitat or result in killing threatened or endangered

species would likely obligate the Corps to consult with the Department of the Interior’s U.S. Fish

and Wildlife Service to identify appropriate measures that could be taken to minimize harm to the

species, pursuant to the Endangered Species Act. Similarly, for ecosystem restoration projects, it

24

42 U.S.C. §4332(2)(C).

For information about required elements of NEPA documents, see CRS Report RL33152, The National

Environmental Policy Act (NEPA): Background and Implementation, by (name redacted).

25

Congressional Research Service

13

Environmental Requirements Addressed During Corps Civil Works Project Planning

is likely that the Corps would consult with the U.S. Fish and Wildlife Service to determine

restoration measures necessary to restore endangered species habitat.

Table 1 identifies selected federal statutes that are frequently applicable to civil works projects,

and the action subject to some control or regulation by an outside agency. Pursuant to its authority

under the applicable law, the agency with jurisdiction to implement the law may be required to

consult with or coordinate some element of project development with the Corps, including the

issuance of some approval (e.g., a permit or license) that specifies conditions under which the

protected resource may be used or affected. Outside agency consultations may also be required to

determine appropriate mitigation measures that the Corps will implement to ensure protection of

the resource in accordance with federal law or Corps policy.

Table 1. Selected Federal Laws That Require Outside Agency Review

Actions Commonly Associated with Corps Civil Works Projects

Statute

Action Subject to Outside Agency

Review, Consultation, or Coordination

Agencies with Jurisdictiona

Fish and Wildlife

Coordination Act (1934,

as amended)

The construction of or modification to

projects that affect fish and wildlife habitats,

and all types of aquatic and land vegetation

upon which wildlife is dependent

Department of the Interior’s (DOI’s)

U.S. Fish and Wildlife Service (FWS);

National Oceanic Atmospheric

Administration’s National Marine

Fisheries Service (NOAA Fisheries);

and/or state fish and wildlife agencies.

National Historic

Preservation Act of

1966

Federal projects that affect districts, sites,

buildings, structures, and objects significant to

American architecture, history, archaeology,

and culture.

State or tribal historic preservation

officer; and/or Advisory Council on

Historic Preservation.

The Federal Water

Pollution Control Act

Amendments, or Clean

Water Act (1972; P.L.

92-500)

The discharge of pollutants into waters of the

United States, including the discharge of

dredged material into wetlands or streams.

Environmental Protection Agency

(EPA); and/or authorized state water

quality agency.

Coastal Zone

Management Act of

1972 (P.L. 92-583)

Federal actions that would affect land or water

uses of the coastal zone.

State coastal zone management agency,

NOAA Fisheries, EPA.

Endangered Species Act

of 1973 (P.L. 93-205)

Action that would jeopardize the continued

existence of listed species, or destroy or

adversely modify their designated critical

habitats.

FWS and NOAA Fisheries.

Marine Protection,

Research, and

Sanctuaries Act of 1972

(P.L. 92-532)

The dumping of waste, including dredge or fill

material, into U.S. ocean waters.

EPA.

Wild and Scenic Rivers

Act (1968; P.L. 90-542)

Federal construction of water resource

projects that would have a direct and adverse

effect on the values for which a river was

designated “Wild and Scenic.”

DOI’s National Park Service; state

agencies.

Source: CRS. Statutes selected were included among those identified by the Corps in its Planning Guidance

Notebook, “Appendix C: Environmental Evaluation and Compliance,” as potentially applicable to a project as a

result of its impacts to ecological, cultural, and aesthetic resources, and air and water quality.

a.

This table provides a list of selected agencies from which the Corps may be required to seek some level of

review, consultation, or coordination. It is not intended to be an exhaustive list.

Congressional Research Service

14

Environmental Requirements Addressed During Corps Civil Works Project Planning

As evidenced in the enactment of the Fish and Wildlife Coordination Act, as early as 1934

Congress recognized the potential harm to fish and wildlife associated with developing the

nation’s water resources and established provisions to coordinate the protection of fish and

wildlife. However, most of the laws or relevant amendments to existing laws (as illustrated in

Table 1) that affect water resources development today were enacted between 1966 and 1973.

Some establish requirements that apply only to federal actions. These later requirements provide

additional examples of how Congress responded to increased public concern over the impacts of

human activity, in general, and federal agency actions, in particular, to the human and natural

environment.

By identifying any environmental requirements applicable to a project in a single environmental

review document, the NEPA process is used to coordinate and document compliance with

potentially duplicative requirements—that is, to ensure compliance with environmental

requirements established pursuant to NEPA and other project-specific requirements (e.g., the

Clean Water Act or Endangered Species Act), but also to ensure compliance with Corps-specific

evaluation requirements (e.g., requirements pertaining to the environment codified in Titles 33

and 43).

The Corps identifies all applicable impact-specific environmental compliance requirements

within the context of evaluating project impacts pursuant to NEPA. The Corps does not have to

comply with all applicable environmental requirements (obtain necessary permits) before the

NEPA process is complete (i.e., a FONSI or ROD is issued). However, the draft NEPA document

must include a summary of outside agency review and consultation requirements, analyses, and

status of coordination associated with applicable laws and executive orders and memoranda, as

well as a list of all federal permits, licenses, and other entitlements that must be obtained to

implement a proposed action.26 Further, the results of any outside agency coordination completed

or under way, required pursuant to the applicable environmental law, must be summarized in the

final NEPA document.27

Integrating Environmental Requirements

into the Project Development Process

For each of the 21 steps of project development identified by the Corps (see Figure 1 above), the

chart below lists activities that occur during those steps. The chart is not an exhaustive list of all

studies, reviews, decisions, approvals, or activities required to be completed in each step of civil

works project development. Instead, it illustrates key processes, procedures, and Corps decision

points associated with completion of the Corps’ environmental evaluation and compliance

requirements that occur during planning, particularly as they are integrated into overall project

development.

26

27

40 C.F.R. §1502.26 and 33 C.F.R. §230.25(a).

33 C.F.R. §230.25(a).

Congressional Research Service

15

Environmental Requirements Addressed During Corps Civil Works Project Planning

Detailed Actions During the 21 Steps of Project Development

Congressional Research Service

16

Environmental Requirements Addressed During Corps Civil Works Project Planning

Congressional Research Service

17

Environmental Requirements Addressed During Corps Civil Works Project Planning

Source: CRS, using information included in the Corps’ Civil Works Process Flowcharts with corresponding

Guidance and Regulation posted on the Corps’ “Planning Community Toolbox: Project Delivery” website at

http://planning.usace.army.mil/toolbox/project.cfm?Option=Start&Step=0; Corp Procedures for implementing

NEPA at 33 C.F.R. 230, including requirements in Appendix A specific to the development of feasibility studies;

and the Corps Planning Guidance Notebook, particularly requirements in Appendix C, “Environmental Evaluation

and Compliance.”

Notes: The chart is not an exhaustive list of all studies, reviews, decisions, approvals, or activities required to be

completed in each step of civil works project development. Instead, it is intended to illustrate key processes,

procedures, and Corps decision points associated with completion of the environmental evaluation and

compliance requirements that occur during planning and are integrated into overall project development.

Factors Identified as Causing Delay

The timeliness of Corps delivery has been the subject of scrutiny and oversight by Congress. As

reflected in legislative proposals intended to streamline certain elements of the project

development process, focus has been almost entirely on the time it takes to complete certain

environmental requirements, particularly elements of the NEPA process. However, it is difficult to

determine the degree to which the NEPA process delays projects. That difficulty stems largely

from the unique issues that must be considered by the Corps during the development of water

resource projects. Further, the NEPA evaluation is embedded in the feasibility process, which

requires compliance with other congressional directives. These factors result in a NEPA

implementation process that is unique to water resources development.

As the Corps implements its environmental evaluation and compliance process, it is difficult to

extract and measure the degree to which certain activities may be attributable to a single

environmental requirement. For example, actions necessary to comply with the Endangered

Species Act may overlap with Corps-specific requirements to mitigate project-specific impacts

(i.e., mitigation measures the Corps may be obligated to consider or implement apart from any

explicit requirement to do so pursuant to the Endangered Species Act). Further, activities that may

be necessary to demonstrate compliance with applicable environmental requirements may take

place while the Corps is completing actions required by other laws or requirements (e.g.,

preparing analyses necessary to determine the project’s economic benefits). As a result, it may be

difficult to identify a specific time frame or step in project development in which only

environmental compliance activities are taking place, as illustrated in the chart above.

One issue that has been the subject of particular scrutiny has been the time it takes to complete

consultation or obtain approvals from other federal and state agencies. As discussed above, an

agency with jurisdiction over that resource may be required to provide some level of analysis,

consultation, or approval before a project can proceed. According to Corps procedures, shown in

Congressional Research Service

18

Environmental Requirements Addressed During Corps Civil Works Project Planning

the chart above, such activities would take place largely within the overall planning process.

Anecdotal evidence indicates that individual projects may take longer than anticipated due to

disagreements with federal resource agencies or state permitting agencies, but there are limited

data available to determine whether such delays are systemic. Instead, issues that may lead to

such delays are likely project-specific.

The time it takes the Corps to move from one step in the project delivery process to another

depends on a complex array of factors. When comparing individual Corps projects to each other,

the larger, more complex, and costly the project, often the longer each step will take to complete.

However, the role that Congress plays in authorizing studies and project construction and the

timing of appropriations have been identified as factors that have the most significant effect on

the timing of project delivery.28 For example, in terms of the project development process, years

may pass between the following:

•

Approval to initiate a study to the appropriation of federal funds. Funds to

initiate new studies have been limited in recent years. As a result, many

authorized studies never receive appropriations or take several years before initial

funding.

•

Transition from the reconnaissance phase to the feasibility phase. Authorized

studies are subject to annual funding during the budget process. Overall study

funding has been limited in recent years. Also, feasibility phase funding has

received more scrutiny during the budget process in recent years. As a result,

moving from the reconnaissance to the feasibility phase may take years or may

never occur.

•

Transmission of the feasibility report to Congress to construction

authorization. Congress chooses to authorize most Corps projects in Water

Resources Development Acts. While consideration of WRDA bills has been

fairly regular, enactment has not been. Only two WRDAs have been enacted in

the past 13 years (in 2000 and 2007). While waiting for authorization, the Corps

can continue with preconstruction engineering and design (PED) activities, if it is

funded to do so, but cannot move forward until the project is approved by

Congress.

•

Construction authorization to the appropriation of construction funds. Once

the project receives congressional authorization, federal funds for construction

may be sought in the annual Energy and Water Development Appropriations Act.

Competition for inclusion in annual appropriations has curtailed the initiation of

28

On June 5, 2013, Major General Michael Walsh, Deputy Commanding General for Civil and Emergency Operations,

testified before the House Committee on Transportation and Infrastructure, Subcommittee on Water Resources and

Environment’s hearing “A Review of the United States Army Corps of Engineer’s Reports” (testimony available at

http://transportation.house.gov/hearing/review-united-states-army-corps-engineers-chief%E2%80%99s-reports). In

response to various questions from several Members of Congress, the General discussed issues that may delay project

delivery, as well as efforts being implemented by the Corps to streamline project delivery. Processes or procedures

related to meeting environmental compliance requirements were not included among those that delay projects or that

were being changed to accelerate delivery, he testified. The limited availability of funds necessary to continue the

number of projects authorized for construction was identified as the primary factor that affects the timing of project

delivery. When asked specifically whether or which environmental regulatory requirements implemented by outside

agencies could be eliminated to expedite project delivery, the General stated that he could not identify a single set of

requirements established by Congress that he would suggest eliminating to streamline the process.

Congressional Research Service

19

Environmental Requirements Addressed During Corps Civil Works Project Planning

new construction projects. For example, many new civil works projects

authorized in WRDA 2007 have not received construction funding as of FY2013.

Instead, funding priorities have generally been on existing projects (e.g., ongoing

construction or maintenance activities).

Given the range of environmental issues and impacts that Congress requires the Corps to evaluate

for civil works projects, there is little debate that the body of requirements that may be deemed

“environmental” that apply to Corps projects often represents a significant element of the project

development process. What is unclear is whether or which specific environmental requirements

routinely delay project delivery. For example, the issuance of permits by a state water quality

agency pursuant to the Clean Water Act or consultations with the U.S. Fish and Wildlife Service

required pursuant to the Endangered Species Act may take longer than anticipated for a given

project. That does not necessarily mean that compliance with those requirements will delay

project delivery, especially if compliance is demonstrated concurrently with other required

elements of project development. Further, issues that may result in the compliance process taking

longer than anticipated for a given project will likely be related to that project. It may not

necessarily be related to an issue that could be avoided in the future by changing procedures or

requirements applicable to all projects.

Even so, the length of time it takes to plan for and initiate construction of water resource projects

has been of increasing concern to some stakeholders and a subject of congressional oversight.

Because of the complex body of planning requirements, some believe reexamination of the

existing requirements and processes to implement these requirements is in order. Some observers

believe such examination and reform of the status quo could lead to a more streamlined and

ultimately a faster review process. The challenge, however, may lie in deciding whether or which

existing steps in the project planning process can be eliminated, combined, or otherwise

streamlined. Background information included in this report is provided for the consideration of

these issues.

Author Contact Information

(name redacted)

Analyst in Environmental Policy

/redacted/@crs.loc.gov, 7-....

Congressional Research Service

20

EveryCRSReport.com

The Congressional Research Service (CRS) is a federal legislative branch agency, housed inside the

Library of Congress, charged with providing the United States Congress non-partisan advice on

issues that may come before Congress.

EveryCRSReport.com republishes CRS reports that are available to all Congressional staff. The

reports are not classified, and Members of Congress routinely make individual reports available to

the public.

Prior to our republication, we redacted names, phone numbers and email addresses of analysts

who produced the reports. We also added this page to the report. We have not intentionally made

any other changes to any report published on EveryCRSReport.com.

CRS reports, as a work of the United States government, are not subject to copyright protection in

the United States. Any CRS report may be reproduced and distributed in its entirety without

permission from CRS. However, as a CRS report may include copyrighted images or material from a

third party, you may need to obtain permission of the copyright holder if you wish to copy or

otherwise use copyrighted material.

Information in a CRS report should not be relied upon for purposes other than public

understanding of information that has been provided by CRS to members of Congress in

connection with CRS' institutional role.

EveryCRSReport.com is not a government website and is not affiliated with CRS. We do not claim

copyright on any CRS report we have republished.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.