The Role of the Environmental Review Process in Federally Funded Highway Projects: Background and Issues for Congress

Congressional research reportApr 11, 2012

Ask Donna

What actually matters in this document.

Text

The Role of the Environmental Review

Process in Federally Funded Highway

Projects: Background and Issues for Congress

-name redactedAnalyst in Environmental Policy

April 11, 2012

Congressional Research Service

7-....

www.crs.gov

R42479

CRS Report for Congress

Prepared for Members and Committees of Congress

The Role of the Environmental Review Process in Federally Funded Highway Projects

Summary

Under programs administered by the Department of Transportation’s (DOT’s) Federal Highway

Administration (FHWA), certain highway and bridge projects may be eligible for federal funding.

Project approval and the receipt of federal funds are conditioned on the project sponsor (e.g., a

local public works or state transportation agency) meeting certain standards and complying with

federal law. Activities necessary to demonstrate compliance with those requirements may be

completed at various stages of project development. Although the names of each stage may vary

from state to state, project development generally includes the following: planning, preliminary

design and environmental review, final design and rights-of-way acquisition, construction, and

facility operation and maintenance.

When there is debate over the time it takes to complete federal highway projects, the

environmental review stage has been a primary focus of congressional attention concerning

legislative options to speed project delivery. The current process includes activities necessary to

demonstrate that all potential project-related impacts to the human, natural, and cultural

environment are identified; effects of those impacts are taken into consideration (among other

factors such as economic or community benefits) before a final decision is made; the public is

included in that decision-making process; and all state, tribal, or federal compliance requirements

applicable as a result of the project’s environmental impacts are, or will be, met.

Compliance requirements depend on site-specific factors, including the size and scope of the

project, and whether and to what degree it may affect resources such as parks, historic sites, water

resources, wetlands, or urban communities. For all proposed federal-aid highway projects,

however, some level of review will be required under the National Environmental Policy Act of

1969 (NEPA, 42 U.S.C. §4321 et seq.). Broadly, NEPA requires federal agencies to consider the

environmental effects of an action before proceeding with it and to involve the public in the

decision-making process.

The time it takes to complete the NEPA process is often the focus of debate over project delays

attributable to the overall environmental review stage. However, the majority of FHWA-approved

projects require limited documentation or analyses under NEPA. Further, when environmental

requirements have caused project delays, requirements established under laws other than NEPA

have generally been the source. This calls into question the degree to which the NEPA compliance

process is a significant source of delay in completing either the environmental review process or

overall project delivery. Causes of delay that have been identified are more often tied to

local/state and project-specific factors, primarily local/state agency priorities, project funding

levels, local opposition to a project, project complexity, or late changes in project scope. Further,

approaches that have been found to expedite environmental reviews involve procedures that local

and state transportation agencies may implement currently, such as efficient coordination of

interagency involvement; early and continued involvement with stakeholders interested in the

project; and identifying environmental issues and requirements early in project development.

Bills in the House and Senate (the American Energy and Infrastructure Jobs Act of 2012 (H.R. 7)

and Moving Ahead for Progress in the 21st Century (MAP-21; S. 1813)) would reauthorize DOT

programs. Both include provisions intended to expedite project delivery by changing elements of

the environmental review process, particularly NEPA requirements. This report provides

information on existing NEPA and environmental review requirements, particularly requirements

that may be subject to change under the House and Senate proposals.

Congressional Research Service

The Role of the Environmental Review Process in Federally Funded Highway Projects

Contents

Introduction...................................................................................................................................... 1

Background and Overview of Issues ............................................................................................... 2

Environmental Reviews and Project Delays ............................................................................. 3

Challenges to Tying Project Delays to NEPA Compliance........................................................ 4

Highway Construction Impacts That Led to the Current Process.................................................... 6

Elements of the Environmental Review Process ............................................................................. 7

Requirements Applicable to Federal-aid Highways .................................................................. 8

Requirements Applicable to “Federal Actions”......................................................................... 9

Requirements Applicable to Certain Resources ...................................................................... 11

Implementing the Environmental Review Process ........................................................................ 12

Demonstrating Compliance with NEPA.................................................................................. 12

Identifying the Appropriate NEPA Document................................................................... 13

FHWA-Approved Projects By NEPA Class of Action ...................................................... 13

Selected Requirements for Each Category of NEPA Document ....................................... 17

Agency Roles and Responsibilities in the NEPA Process ................................................. 26

Public Involvement ........................................................................................................... 28

Demonstrating Compliance with Additional Requirements .................................................... 29

Environmental Reviews and Project Development ....................................................................... 31

Stages of Project Development................................................................................................ 31

Challenges in Measuring Stages of Project Development....................................................... 33

Causes of Delay in Completing Environmental Reviews........................................................ 35

Benefits to the Environmental Review Process....................................................................... 36

Expediting Environmental Reviews .............................................................................................. 37

Lessons Learned ...................................................................................................................... 37

Administrative Efforts ............................................................................................................. 40

Conclusions.................................................................................................................................... 40

Figures

Figure 1. FHWA-Approved Projects—By NEPA Class of Action ................................................ 14

Figure 2. Active FHWA Projects Requiring an EIS in Each State................................................. 15

Figure 3. Percentage of FHWA Program Funding Allocation by NEPA Class of Action .............. 16

Figure 4. NEPA Decision-Making Process .................................................................................... 17

Tables

Table 1. Federally Funded Highway Projects Specifically Listed as CEs ..................................... 18

Table 2. Examples of FHWA-Approved Projects That May Be Classified as a CE ...................... 19

Table 3. Required Elements of an EIS as Implemented by FHWA ............................................... 22

Table 4. Federal Law Commonly Applicable to FHWA-Approved Projects................................. 30

Congressional Research Service

The Role of the Environmental Review Process in Federally Funded Highway Projects

Table 5. Stages of Federal-Aid Highway Project Development .................................................... 32

Appendixes

Appendix. Surveys and Studies Applicable to the Environmental Review Process ...................... 42

Contacts

Author Contact Information........................................................................................................... 43

Congressional Research Service

The Role of the Environmental Review Process in Federally Funded Highway Projects

Introduction

Under programs administered by the Department of Transportation’s (DOT’s) Federal Highway

Administration (FHWA), certain highway and bridge projects may be eligible to receive federalaid funding.1 As a condition of receiving those funds, a project sponsor (e.g., a local or state

transportation agency) must meet certain standards and requirements applicable to activities

completed at every stage of project development. Although the names of those stages may vary

somewhat from state to state, those stages generally include initial project planning, preliminary

design/engineering and environmental review, final design and rights-of-way acquisition,

construction, and facility operation and maintenance.

Each stage of project development is initiated and completed largely at the state or local level,

with FHWA having ultimate responsibility for ensuring that individual projects comply with

requirements applicable to federal-aid highways.2 Also, each development stage involves a range

of activities that will affect the time it takes to deliver the project. Required elements of the

preliminary design and environmental review stage will vary by project, but generally include

processes necessary to identify and demonstrate compliance with environmental requirements

applicable to that project.

When there is debate over the time it takes to complete federally funded highway projects,3

particularly debate over activities that may expedite or delay project delivery, various elements of

the environmental review stage of project development have been the focus of attention.

However, whether or the degree to which elements of that process may delay projects is unclear.4

The two most recent laws authorizing DOT programs included requirements intended to expedite

the environmental review process that focused primarily on procedures necessary to demonstrate

compliance with the National Environmental Policy Act of 1969 (NEPA, 42 U.S.C. §4321 et

seq.).5 Current legislation to authorize DOT programs in the House and the Senate (the American

Energy and Infrastructure Jobs Act of 2012 (H.R. 7) and Moving Ahead for Progress in the 21st

Century (MAP-21; S. 1813)) also include provisions intended to expedite project delivery that

focus primarily on the NEPA process.6

1

This report focuses on projects approved under programs administered by FHWA. Although they involve similar

regulatory requirements, issues unique to transit projects approved under programs administered by the Federal Transit

Administration (FTA) are not addressed in this report.

2

Those requirements are largely established under Chapter 1, “Federal-aid Highways,” of Title 23, “Highways” of the

U.S. Code.

3

In this report, reference to “federal-aid highways,” “federal highways,” or “federal highway projects” means projects

that may receive federal funding pursuant to the Federal-aid Highways provisions of Title 23. Those projects include,

but are not limited to, the initial construction, reconstruction, replacement, rehabilitation, restoration, or other

improvements of a highway, road, street, parkway, right-of-way, bridge, or tunnel.

4

See CRS Report R41947, Accelerating Highway and Transit Project Delivery: Issues and Options for Congress, by

(name redacted) and (name redacted).

5

The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU or

SAFETEA; P.L. 109-59, for FY2005-FY2009) and the Transportation Equity Act for the 21st Century (TEA-21; P.L.

105-178, for FY1998-FY2003).

6

H.R. 7 was reported favorably by the House Transportation and Infrastructure Committee on February 13, 2012.

MAP-21 passed the Senate on March 14, 2012.

Congressional Research Service

1

The Role of the Environmental Review Process in Federally Funded Highway Projects

Despite the focus on the NEPA process, it is unclear whether or how changes to that process

would result in faster highway project delivery. Available evidence regarding potential causes of

project delays associated with environmental compliance is largely anecdotal and specific to

unique, individual projects. Still, that evidence, while limited, points to issues or requirements

apart from NEPA as more common causes of project delays.

This report identifies issues relevant to the debate over the role of the environmental review

process in transportation project delivery. It identifies social and environmental issues that led

Congress to enact the range of requirements that now make up the environmental review process,

as well as selected requirements applicable to its implementation (particularly NEPA

requirements). The report also identifies complexities in tying the environmental review process

to federal-aid highway project delivery time. In particular, it identifies issues that make it difficult

to determine the time it takes to complete the project development process, in general, or

individual stages of development (e.g., activities related explicitly to environmental reviews); or

to identify root causes of project delays tied to specific elements of the environmental review

process. This report also discusses various approaches identified by transportation stakeholders as

those that have expedited the environmental review process and overall project delivery.

Information and issues in this report were selected to help Members of Congress and their staff

understand the NEPA compliance process as well as additional environmental compliance

requirements that may be affected by H.R. 7 and MAP-21. Discussion of specific legislation is

provided separately in CRS Report R42445, Surface Transportation Reauthorization Legislation

in the 112th Congress: MAP-21 and H.R. 7, Major Provisions, coordinated by (name redacted).

Background and Overview of Issues

Activities that may take place during the environmental review process and how that process is

implemented will vary from project to project, from state to state. The environmental review

process does not involve compliance with a single federal compliance requirement. It involves

processes necessary to demonstrate compliance with a potentially wide array of requirements

applicable to projects approved under the Federal-aid Highways program. Broadly, for federally

funded highway projects, it involves two separate, but related processes—preparing appropriate

documentation required under NEPA; and identifying and demonstrating compliance with any

additional state, tribal, or federal environmental requirements applicable to that project.

For a given project, how NEPA and other environmental compliance requirements must be

demonstrated will largely depend on the degree to which the proposed project would have

adverse effects on communities, natural or cultural resources (e.g., wetlands, endangered species

habitat, historic sites, parks, or recreation areas), or special status land (e.g., farmland,

floodplains, or coastal zones). Compliance with those requirements may include obtaining a

permit, approval, study, or some level of analysis or consultation from an agency outside DOT.

NEPA was intended, in part, to ensure that federal agencies would consider the environmental

impacts of an action among other factors (e.g., economic or community benefits) in the federal

decision-making process. NEPA has two primary aims—to assure that federal agencies consider

the environmental effects of their actions before proceeding with them and to involve the public

in the decision-making process.

Congressional Research Service

2

The Role of the Environmental Review Process in Federally Funded Highway Projects

NEPA does not require an agency to elevate environmental concerns above other factors in the

overall federal decision-making process. If the adverse environmental effects of a proposed action

are adequately identified and evaluated, an agency is not constrained by NEPA from deciding that

other project benefits outweigh the environmental costs and moving forward with the action. In

contrast, other requirements applicable to federal-aid highways may dictate or somehow affect the

outcome of a project decision. For example, other federal laws may require the selected project

alternative to be the one with the least impact to a particular resource, prohibit FHWA approval of

a project alternative that uses certain resources, require certain mitigation measures to limit a

project’s impacts, or require that certain activities take place in accordance with certain criteria

(e.g., as specified in a permit or approval).

Environmental Reviews and Project Delays

Required elements of the environmental review process, particularly compliance with NEPA, will

have an effect on project development. For example, before DOT can approve a project and allow

final project design, property acquisition, or project construction to proceed, the project sponsor

must appropriately document compliance with NEPA and complete any investigation, review, or

consultation necessary to demonstrate compliance with other applicable environmental

requirements. Further, it is DOT policy to use the NEPA compliance process as a mechanism to

balance transportation decision making by taking into account the potential impacts on the human

and natural environment and the public’s need for safe and efficient transportation.7

State and local transportation agency officials and other stakeholders with an interest in

transportation improvement generally acknowledge that elements of the environmental review

process provide important protections to the human, cultural, and natural environment. However,

those officials also sometimes argue that completing the process can be difficult and timeconsuming. Some have argued, for example, that the time it takes to complete required NEPA

documentation and supporting analysis or to obtain required input or approval from outside

agencies can delay completion of federally funded transportation projects.

It is generally not disputed that the time it takes to complete the environmental review process for

federally funded highway projects can take months or even years. What is unclear is the degree to

which elements of the environmental review process directly or routinely delay project delivery.

Determining the time it takes to complete activities associated with the environmental review

process, or delays directly attributable to those activities, is difficult for several reasons including,

but not limited to:

•

Limits to available data. There is no centralized source of data regarding

highway project delivery. States generally do not track project development time

from planning to construction. States generally do not attempt to isolate elements

of the environmental review process, which may overlap with preliminary project

planning, design, or engineering activities. Further, there is no standard measure

for determining when a project or the environmental review process, in

particular, is completed “quickly” or would be considered “delayed.”

7

See NEPA and Project Development: Program Overview on FHWA’s “Environmental Review Toolkit” webpage at

http://environment.fhwa.dot.gov/projdev/index.asp.

Congressional Research Service

3

The Role of the Environmental Review Process in Federally Funded Highway Projects

•

The influence of local factors on project delivery. The environmental review

process may start, stop, and restart for reasons unrelated to environmental issues.

Local and state issues have been shown to have the most significant influence on

whether a project moves forward relatively quickly or takes longer than

anticipated. Those issues include the project’s level of priority among others

proposed in the state; changes in funding availability; and local controversy or

opposition to the project (which may or may not be connected to environmental

issues).

•

The variation in project type and complexity. The wide range of projects

approved under programs administered by FHWA (e.g., bridge repair versus

major new highway construction) do not easily allow an “apples to apples”

comparison of the time it takes to complete the environmental review process or

factors that may delay it. Anecdotal evidence regarding projects identified as

“delayed” have involved multiple, complex causes of delay (including local

issues) unique to that project, not a single cause that may be commonly

applicable to other projects.

•

Variation among state requirements and implementation processes. The

effect of requirements under federal law may be difficult to isolate since local,

state, or tribal requirements and procedures will also affect how environmental

compliance requirements are implemented. State DOTs implement their project

delivery process differently, depending on factors specific to their state and its

needs. For example, some states may implement unique design and contracting

processes that expedite project delivery that other states do not.

•

Time “saved” cannot be gauged. Depending on the scope and complexity of the

project, more time spent addressing environmental issues in the project planning

and preliminary design stage may result in faster completion of final design and

project construction (when delays may require actions that take more time and

money to address). Time may also be saved when adverse project impacts that

could lead to local opposition to the project are identified and addressed during

the early stages of project development.

Challenges to Tying Project Delays to NEPA Compliance

Transportation agency officials and project sponsors have broadly identified environmental

compliance requirements as a common source of frustration in completing the project

development process. However, limits to and contradiction in available data make it difficult to

clearly identify specific causes of delay that are directly and routinely attributable to specific

elements of environmental compliance. Identifying a distinct root cause of a delay will arguably

be necessary before effective “solutions” (procedures that would result in faster project delivery)

can be identified. That is, knowing that a delay occurred may be irrelevant if it is not determined

why the delay occurred. An understanding of why is useful in identifying a solution that directly

addresses a problem’s underlying cause.

Determining why a project was delayed may be difficult or may be attributable to multiple,

interrelated factors. Generally, the more complex the project, the more complex the potential

cause(s) of delay. For example, compared to a maintenance or repair project, a major new

construction project will require more extensive review, documentation, or analysis to

demonstrate compliance with NEPA and other applicable environmental requirements. However,

Congressional Research Service

4

The Role of the Environmental Review Process in Federally Funded Highway Projects

the following factors call into question the degree to which NEPA alone is a significant source of

project delay in overall project development:

•

The majority of projects require limited review under NEPA. The majority of

FHWA-approved projects (approximately 96%) involve no significant

environmental impacts and, hence, require limited documentation, analysis, or

review under NEPA.

•

Compliance with DOT’s “NEPA regulations” extends beyond what is

required under NEPA. DOT’s “Environmental Impact and Related Procedures”8

prescribe the policies and procedures to ensure that FHWA-approved projects

will comply with NEPA as well as requirements established under Title 23

applicable to Federal-aid Highways (e.g., provisions applicable to the

consideration of adverse economic, social, and environmental effects (under

§109(h)), public hearings (§128), and preservation of parklands (§138)).

•

The NEPA compliance process is used to demonstrate compliance with all

applicable environmental review requirements. It is DOT policy that any

investigation, review, or consultation necessary to demonstrate compliance with

applicable environmental requirements be completed within the context of the

NEPA process. This use of NEPA as an “umbrella” compliance process can blur

the distinction between what is required under NEPA and what is required under

separate authority.

Transportation agency officials asked to identify sources of frustration or delay in completing the

environmental review process most commonly cite compliance requirements applicable to the

protection of parklands, historic sites, wetlands, or threatened or endangered species. The

potential root cause of delay in complying with those requirements could be attributable to a wide

range of project-specific factors (e.g., incomplete permit applications, challenges in obtaining

multiple approvals or permits for a complex project, or disagreement with a resource agency over

appropriate methods to mitigate project impacts).

Both existing law and regulations implementing NEPA include explicit directives and

requirements intended to streamline the NEPA process. Included among those requirements are

procedures intended to coordinate efficient agency interaction and cooperation, reduce NEPArelated paperwork and duplication of effort (e.g., documentation and analysis that may be

required by similar state, tribal, or federal requirements or from one stage of project development

to the next), and integrate the consideration of environmental compliance issues in a project’s

planning stage. Barriers to efficiently implementing existing requirements may be project-specific

or involve issues that may be difficult to address by simply amending or eliminating existing

federal requirements.

This is not to suggest that there are not instances where preparation of documentation and

analysis required under NEPA is not time-consuming or may contribute to delays in project

delivery. However, it is unclear whether or what additional federal requirements may be

implemented to expedite the NEPA process. Conversely, it is not clear whether the elimination of

certain NEPA-specific requirements may expedite project delivery or would alter the framework

for coordinating an already complex compliance process, resulting in additional project delay. For

8

23 C.F.R. Part 771.

Congressional Research Service

5

The Role of the Environmental Review Process in Federally Funded Highway Projects

a given project, whether changes to the NEPA process might result in faster project delivery will

likely depend on the project’s scope and complexity; the degree to which it is affected by “local”

factors (e.g., state funding or project priorities); and compliance requirements applicable to the

project, in addition to those under NEPA.

Highway Construction Impacts That Led to the

Current Process

To understand why a complex array of requirements may apply to highway projects, it is useful to

understand the social and environmental concerns that led Congress to enact the various laws that

now form the framework of the environmental review process. Each requirement included within

that process represents past efforts by Congress to minimize adverse impacts from federally

funded highway projects or to minimize adverse impacts to certain communities or resources that

Congress identified as needing some level of protection.

The current debate over the environmental review process frequently centers around the effect

that completion of that process has on project delivery. The debate rarely recognizes the issues

that led Congress to enact the requirements that now make up that process. Requirements

included within the environmental review process, and procedures to demonstrate compliance

with them, have evolved over the past 50 years. However, many of the requirements that are

subject to particular scrutiny today were enacted between 1966 and 1972.

During the 1950s and 1960s, the public was becoming increasingly aware of and concerned about

the impacts that human activity were having on the environment. Increasing attention turned to

the effect that federally funded programs and projects were having on the human, cultural, and

natural environment. One federal program that generated particular concern was the development

and construction of the Interstate Highway System.

The Federal-Aid Highway Act of 1956 (P.L. 84-627) authorized and provided revenue sources for

the construction of the National System of Interstate and Defense Highways (commonly known

as the Interstate Highway System, Interstate System, or the Interstate). The Interstate System is a

network of limited-access roads including freeways, highways, and expressways forming part of

the National Highway System of the United States.9 Construction of the Interstate System took

approximately 35 years and resulted in a network of roads and bridges that currently includes

over 45,000 miles of rural highways, suburban and urban freeways, and bridges.10

Although the connection of rural, urban, and suburban communities resulted in a host of

economic and cultural benefits, construction of the Interstate System also brought certain adverse

impacts to both the human and natural environment. Those impacts were seen particularly in the

construction of the urban freeways. Planning for such projects often involved locating freeways

within available open space or where land acquisition costs were relatively low. “Available open

9

The National Highway System is approximately 160,000 miles of roadway important to the nation’s economy,

defense, and mobility.

10

For more information about the Interstate Highway System, see the U.S. Department of Transportation’s Federal

Highway Administration website, “Celebrating the Eisenhower Interstate Highway System,” http://www.fhwa.dot.gov/

interstate/homepage.cfm.

Congressional Research Service

6

The Role of the Environmental Review Process in Federally Funded Highway Projects

space” often meant historic sites, parks, or recreation areas. Adverse impacts to those resources

from highway projects drew increased attention from newly formed stakeholder groups with an

interest in environmental protection and historic preservation.

Project planning that involved lower land acquisition costs often meant property acquisitions in

densely populated, working-class or high-poverty neighborhoods. Resulting urban freeway

projects had a disproportionate impact on the urban poor. One such example involved a segment

of I-95 north of Miami. The route selected by local transportation officials cut through the innercity community of Overtown, a once-thriving African-American community known as the

“Harlem of the South.” A 2009 FHWA report discussing lessons learned in complying with

environmental requirements describes the project as follows:

In 1957, the Overtown community was almost decimated by the development of the I-95 and

I-395 freeways. The constructed roadway had a disastrous impact on the economic and social

structure of the community. The community continues to shoulder the lingering effects of

those negative impacts, and as a result there is also persistent anger towards and distrust of

[the Florida Department of Transportation].11

Opposition to other urban freeway projects led to “freeway revolts” spearheaded by newly

established environmental and social justice groups.12 Freeway revolts took place in cities like

Baltimore, Boston, Los Angeles, New Orleans, New York, Reno, and San Francisco. As a result, a

significant number of projects were abandoned or significantly scaled back due to widespread

public opposition, especially by those whose neighborhoods would be disrupted or who would

displaced by the proposed freeways.

Elements of the Environmental Review Process

By the mid to late 1960s, Congress began to enact legislation intended to address the growing

public concern over projects implemented under the Federal-aid Highways program. During that

period, Congress also enacted legislation in response to increasing awareness and concern over

the impacts of all federal actions—not just federal highway projects. Also during the 1960s and

into the 1970s Congress began to enact a wide range of laws intended to identify, prohibit,

control, or mitigate adverse impacts of human activities to specific community, natural, or

cultural resources that Congress identified as in need of certain protection. This report identifies

and summarizes requirements that have been identified as those most commonly applicable to

federally funded highway projects.

11

Report prepared by the John A. Volpe National Transportation Systems Center Research and Innovative Technology

Administration, U.S. Department of Transportation for the Office of Project Development and Environmental Review,

Federal Highway Administration, “Strategies and Approaches for Effectively Moving Complex Environmental

Documents Through the EIS Process: A Peer Exchange Report,” January 2009, available on the Federal Highway

Administration’s “Streamlining/Stewardship” website at http://environment.fhwa.dot.gov/strmlng/eisdocs.asp.

12

For a discussion of issues related to freeway revolts and general issues with urban freeway construction, see “Paved

with Good Intentions: Fiscal Politics, Freeways and the 20th Century American City,” by Jeffrey A. Brown, Eric A.

Morris, and Brian D. Taylor, in the University of California Transportation Center’s Access magazine, Fall 2009,

available at http://www.uctc.net/access/35/access35_Paved_with_Good_Intentions_Fiscal_Politics_.shtml.

Congressional Research Service

7

The Role of the Environmental Review Process in Federally Funded Highway Projects

Requirements Applicable to Federal-aid Highways

FHWA is prohibited from approving a project for funding under the Federal-aid Highway

program until the project sponsor demonstrates that the proposed project will comply with all

applicable federal, tribal, and state requirements. To the extent possible, compliance with any

requirements that apply to a project, as a result of that project’s effect on the human and natural

environment, must be appropriately documented and demonstrated during the environmental

review stage of project development.

Requirements specific to Federal-aid Highways include a host of standards, procedures, and

conditions applicable to the various stages of project development. Several requirements

(applicable primarily to activities that take place during the project planning, preliminary design,

and environmental review phases of development) reflect concern over the effects of urban

freeway construction (discussed above), including the following:

•

Directive to establish guidelines to assure consideration of adverse project

impacts (23 U.S.C. §109(h)). Directed DOT to establish guidelines to assure that

possible adverse, economic, social, and environmental effects of proposed

highway projects and project locations were fully considered during project

development, and that final project decisions be made in the best overall public

interest, taking into consideration the costs of eliminating or minimizing adverse

effects to air, noise, and water pollution; destruction or disruption of man-made

and natural resources; aesthetic values, community cohesion, and the availability

of public facilities and services; adverse employment effects, and tax and

property value losses; and injurious displacement of people, businesses, and

farms.

•

Directive to establish noise standards (23 U.S.C. §109(i)). Directed DOT to

establish standards for highway noise levels compatible with different land uses.

DOT cannot approve plans and specifications for any proposed federal-aid

project unless it includes adequate measures to implement those noise standards.

As implemented under DOT regulations, a project may be required to

demonstrate compliance with applicable standards through an analysis of traffic

noise impacts and, when necessary, to implement noise abatement measures.

•

Public hearings requirements (23 U.S.C. §128). For a proposed project

bypassing or going through any city, town, or village, a state transportation

department is required to certify that it held or afforded the opportunity for public

hearings; considered the economic and social effects of the project location, and

its impact on the environment; and considered the consistency of the project with

local planning goals and objectives.

•

Preservation of parklands requirements (23 U.S.C. §138). More commonly

referred to as “Section 4(f)”13 requirements, DOT is prohibited from approving a

13

The term “Section 4(f)” refers to the section of the Department of Transportation Act of 1966 (P.L. 89-670) under

which the requirement was originally set forth. It was initially codified at 49 U.S.C. §1653(f) and only applied to DOT

agencies. Later that year, 23 U.S.C. §138 was added with somewhat different language, which applied only to the

highway program. In 1983, as part of a general recodification of the DOT Act, §1653(f) was formally repealed and

codified in 49 U.S.C. §303 with slightly different language. This provision no longer falls under a “Section 4(f),” but

DOT has continued this reference, given that over the years, the whole body of provisions, policies, and case law has

been collectively referenced as Section 4(f).

Congressional Research Service

8

The Role of the Environmental Review Process in Federally Funded Highway Projects

project that uses publicly owned (local, state, or federal) parks and recreation

areas, wildlife and waterfowl refuges, and publicly or privately owned historic

sites of national, state, or local significance. DOT may approve a project that uses

a 4(f) resource only if there is no prudent and feasible alternative to do otherwise,

and that use includes all possible planning to minimize harm to the resource.

Of the requirements specifically applicable to Federal-aid Highways, the preservation of

parklands requirements may have the greatest effect on highway project development and

delivery. Projects that would use a 4(f) resource require an evaluation analyzing project

alternatives (including location and design shifts) that avoid the resource.14 To be approved by

FHWA, the evaluation must show that alternatives that would not use the resource would result in

“truly unique problems,” resulting in costs or community disruption of extraordinary magnitude.

This test is often referred to as the “Overton Park Criteria,” after a court case in the 1970s in

Memphis, TN.15 In approving the use of a 4(f) resource, FHWA must also consider the

significance and importance of the resource itself.

SAFETEA amended Section 138 to allow for the use of a 4(f) resource if that use can be proven

to have de minimis impacts to the resource.16 Generally, de minimis impacts would result from the

use of minor amounts of a particular resource. Such a determination requires concurrence from an

official with jurisdiction over the resource. For example, for a transportation project adjacent to a

publicly owned park, recreation area, or wildlife and waterfowl refuge, FHWA would be required

to consult with, as appropriate, agencies within the Department of the Interior (e.g., the U.S. Fish

and Wildlife Service, National Park Service, or the Bureau of Indian Affairs) or state or local park

authorities. For historic sites, a de minimis impacts determination must be based on criteria

established under the National Historic Preservation Act applicable to uses that will have no

“adverse effect” on the site (16 U.S.C. §470f). The determination must receive concurrence from

the State Historic Preservation Officer (SHPO) and, if appropriate, the Advisory Council on

Historic Preservation (ACHP).

Compared to other environmental requirements likely applicable to federal-aid highway projects,

Section 4(f) is unique in its limits on the use of a protected resource. Most requirements intended

to protect communities or specific natural or cultural resources allow for adverse project impacts

if those impacts are sufficiently identified and considered in the decision-making process. Some

requirements may specify that a project implement certain mitigation measures or be

implemented in accordance with an approval or permit from an agency responsible for protecting

that resource. An outright prohibition on the use of a particular resource, except for de minimis

impacts or under extraordinary conditions, is not common to other environmental requirements.

Requirements Applicable to “Federal Actions”

In the 1960s Congress debated legislative options to address potential adverse impacts associated

with federal actions. An action may be deemed “federal” based on the role that a federal agency

14

Depending on project alternatives under consideration for a given project, compliance with Section 4(f) requirements

can be complex. This report does not discuss those requirements in detail. For more information, see the “Section 4(f)”

website included in FHWA’s “Environmental Review Toolkit,” at http://www.environment.fhwa.dot.gov/4f/index.asp.

15

Citizens to Preserve Overton Park v. Volpe, 401 U.S. 402 (1971).

16

See Department of Transportation, “Parks, Recreation Areas, Wildlife and Waterfowl Refuges, and Historic Sites,”

final rule, 73 Federal Register 13367-13401, March 12, 2008.

Congressional Research Service

9

The Role of the Environmental Review Process in Federally Funded Highway Projects

plays in a project’s approval or funding. A project funded under the Federal-aid Highways

program would generally be considered a federal action. Two laws applicable specifically to

federal actions that significantly affect the environmental review process for highway project

development are NEPA and the National Historic Preservation Act (16 U.S.C. §470, et seq.).

As discussed previously, NEPA has two primary aims—to require federal agencies to consider the

environmental impacts of a project and to give the public a meaningful opportunity to learn about

and comment on the proposed project before a final decision is made. It is a procedural statute.

That is, NEPA requires federal agencies to implement procedures to ensure that environmental

impacts of a project are included among, but not elevated above, other factors considered during

the federal decision-making process. If the adverse environmental impacts of the proposed action

are adequately identified and evaluated, the agency is not constrained by NEPA from deciding

that other benefits (e.g., community and economic benefits) outweigh the environmental costs

and moving forward with the action. (The NEPA compliance process is discussed under

“Demonstrating Compliance with NEPA.”)

The National Historic Preservation Act (NHPA) declared a national policy of historic preservation

to protect districts, sites, buildings, structures, and objects significant to American architecture,

history, archaeology, and culture. NHPA did not mandate preservation of historic resources or

prohibit adverse impacts to them, but Section 106 requires all federal agencies to consider the

impacts of a proposal prior to taking any action that may affect a site included in, or eligible for

inclusion on, the National Register of Historic Places.

NHPA also requires federal agencies to afford the Advisory Council on Historic Preservation (an

independent federal agency created by the law) a reasonable opportunity to comment on federal

actions that would affect properties on or eligible for inclusion on the National Register of

Historic Places. For federally funded highway projects, FHWA must consult with the Advisory

Council or the designated SHPO to determine project impacts to historic sites and potential ways

to mitigate those impacts.

There are similarities between requirements established under Section 4(f) and Section 106, but

also important differences between the statutes. Like NEPA, Section 106 establishes a procedural

requirement that directs all federal agencies only to consider project impacts on certain resources.

Section 4(f) applies only to DOT projects and prohibits the use of certain resources for those

projects, except under certain conditions.

Additional federal laws and executive orders apply explicitly to federal actions that affect certain

resources or communities. For example, a federally funded highway project may require

compliance with additional requirements applicable to federal actions if that project may:

•

involve the acquisition, rehabilitation, or demolition of real property that will

displace persons from their homes, businesses, or farms as protected under the

Uniform Relocation Assistance and Real Property Acquisition Act of 1970 (42

U.S.C. §4601, et seq., more commonly referred to as the Uniform Act);

•

affect wetlands or floodplains pursuant to Executive Order 11990 or Executive

Order 11988, respectively;

•

convert farmland to nonagricultural uses pursuant to the Farmland Protection

Policy Act of 1981 (7 U.S.C. §4201 et seq.);

Congressional Research Service

10

The Role of the Environmental Review Process in Federally Funded Highway Projects

•

cause disproportionately high and adverse impacts on minority and low-income

populations with respect to human health and the environment pursuant to

Executive Order 12898; or

•

affect human remains and cultural material of Native American and Hawaiian

groups pursuant to the Native American Grave Protection and Repatriation Act

(25 U.S.C. §3001 et seq.).

Requirements Applicable to Certain Resources

In addition to requirements applicable to federal-aid highways, specifically, and federal actions,

in general, Congress has enacted a host of individual statutes intended to protect certain natural,

environmental, and cultural resources from human-induced activities. A potentially long list of

federal compliance requirements could apply to a given highway or bridge project, but

requirements that will actually apply to a project will be limited by site-specific conditions and

the degree to which the proposed project may affect protected resources. Broadly, highway

projects may be subject to requirements intended to identify, minimize, or control adverse

impacts to:

•

Land—including land use that may affect the habitat of threatened or endangered

plant and animal species, migratory birds, archaeological sites, and land

designated as a national trail or national wilderness; and

•

Water resources or water quality—including projects that may affect wetlands,

aquatic ecosystems, navigable waters (e.g., rivers, streams, harbors), floodplains,

coastal zones, or designated “wild and scenic” rivers, or projects that may affect

water quality (e.g., discharge pollutants into U.S. waters).17

For a given federally funded highway project, compliance with a number of federal, state, or

tribal regulations intended to identify, control, mitigate, or minimize project impacts to land and

water resources may be required. Specific compliance requirements will depend on standards or

regulatory requirements of that law and the degree to which the proposed project may adversely

affect that resource. Depending on those factors, project development and implementation may

require some level of consultation, analysis, or approval from an agency with jurisdiction over the

resource. For example, a highway or bridge project that results in pollutants being discharged into

wetlands, rivers, or streams or that may affect navigable waterways or harbors likely will require

project development be completed in accordance with provisions established under the Clean

Water Act or the Rivers and Harbors Act. Pursuant to those laws, the selection of a particular

project alternative may require a permit or certification from the Army Corps of Engineers (the

Corps), the Environmental Protection Agency (EPA), the United States Coast Guard, or a state or

tribal water quality control agency.

17

Air quality issues are also relevant to federal-aid highway project development. Under the Clean Air Act, FHWA

must insure that transportation plans, programs, and projects conform to the state’s air quality implementation plans.

Conformance with a state implementation plan is largely determined during project planning. Issues associated with

meeting federal air quality requirements are not discussed in this report.

Congressional Research Service

11

The Role of the Environmental Review Process in Federally Funded Highway Projects

Implementing the Environmental Review Process

The individual requirements discussed above were enacted by Congress after a particular concern

arose or need was identified. For an individual project, several requirements involving similar

compliance directives could apply. For example, depending on its impacts, a project may be

subject to different public hearing or notification requirements under separate federal regulatory

or statutory requirements.

The environmental review process is intended to function as the mechanism under which

potentially duplicative requirements are identified and coordinated (including duplicative state or

tribal requirements). Specifically, it is DOT policy that, to the fullest extent possible, any

investigation, review, and consultation necessary to demonstrate environmental compliance be

coordinated as a single process. The environmental review process is that single process. It forms

the framework under which all applicable compliance requirements intended to protect the

human, natural, or cultural environment are identified and demonstrated. Further, the NEPA

compliance process forms the framework for completing the environmental review process.

In the past, suggestions made by transportation stakeholders to expedite project delivery, as well

as legislative options proposed by some Members of Congress, have focused on requirements

established specifically under NEPA. However, examples of individual projects delayed by

environmental requirements more often involve issues associated with environmental compliance

obligations established under separate state or federal requirements. In identifying and

determining the potential effectiveness of nationally applicable approaches to expedite the

environmental review process, it is necessary to distinguish between what is required explicitly

under NEPA versus other federal environmental requirements.

Demonstrating Compliance with NEPA

The Council on Environmental Quality (CEQ) promulgated regulations implementing NEPA that

were broadly applicable to all federal agencies.18 CEQ required each federal agency to develop its

own NEPA procedures specific to typical classes of actions undertaken by that agency.19 In 1987,

DOT promulgated “Environmental Impact and Related Procedures.”20 Those regulations

prescribe the policies and procedures for FHWA to implement NEPA as it may apply to federally

funded highway projects. They also include procedures necessary to ensure compliance with

environmental requirements established under Title 23 applicable to Federal-aid Highways (e.g.,

procedures necessary to demonstrate compliance with requirements applicable to economic,

social, and environmental effects, public hearings, and preservation of parklands (Section 4(f))).

DOT’s regulations have been revised periodically in accordance with legislative directives from

Congress and to reflect court decisions applicable to DOT’s implementation of both the NEPA

process and its other environmental compliance obligations. Most recently, the regulations were

modified to reflect the new environmental review process established under SAFETEA.

18

40 C.F.R. §§1500-1508.

40 C.F.R. §1507.3.

20

23 C.F.R. Part 771.

19

Congressional Research Service

12

The Role of the Environmental Review Process in Federally Funded Highway Projects

Identifying the Appropriate NEPA Document

For a given highway project that receives funding or approval under Federal-aid Highways

programs, compliance with NEPA is demonstrated in the “NEPA document.” Requirements that

define the various categories of NEPA document and required elements of each are found in the

NEPA regulations promulgated by both CEQ and DOT.

Transportation projects vary in type, size, complexity, and potential to affect the environment. To

account for the variability of potential project impacts, NEPA regulations establish three basic

“classes of action” that dictate how NEPA compliance will be documented and implemented.

Determining the appropriate NEPA document and level of environmental review and analysis

necessary for that document is dependent upon the answer to the following question: “Will the

proposed action have any significant environmental impact?” Answers to that question, and the

corresponding NEPA documents, are as follows:

•

Yes. Those projects require an Environmental Impact Statement (EIS) followed

by a final Record of Decision (ROD).

•

Maybe. When the significance of a project’s impacts is not clear, an

Environmental Assessment (EA) must be prepared to determine whether an EIS

is necessary or a Finding of No Significant Impact (FONSI) is appropriate.

•

No. Those projects are categorically excluded from the requirement to prepare an

EIS or EA; as such, those projects are generally referred to as Categorical

Exclusions (CEs or CATEX).

Pursuant to NEPA’s aims, an evaluation of environmental impacts is required prior to

commitment of federal resources. To meet that requirement, preparation of the NEPA document

may begin in the project planning stage, but must be completed within the preliminary design and

environmental review stage of project development. Generally, subsequent stages of project

development (final design activities, property acquisition, or project construction) cannot proceed

until the necessary NEPA document is complete and approved by FHWA.

FHWA-Approved Projects By NEPA Class of Action

Major highway projects that require an EIS are the most studied and discussed when there is

debate over the time it takes to complete the NEPA process. Further, past legislative efforts to

expedite the NEPA process have focused primarily on the NEPA process as it applies to EIS

preparation. However, FHWA data from 1998 to 2007 show that approximately 4% of federal-aid

highway projects approved under programs administered by FHWA required an EIS. Projects

processed as a CE or with an EA/FONSI accounted for approximately 96% (see Figure 1).

Congressional Research Service

13

The Role of the Environmental Review Process in Federally Funded Highway Projects

Figure 1. FHWA-Approved Projects—By NEPA Class of Action

Average from 1998 to 2007

Source: Congressional Research Service, based on data available from FHWA’s “Streamlining/Stewardship:

Performance Reporting” website at http://environment.fhwa.dot.gov/strmlng/projectgraphs.asp.

More recent FHWA data illustrate a similar proportion of major new projects and smaller

maintenance/rehabilitation projects. In FY2009, of the approximately 55,043 miles of roadway

projects receiving federal-aid highway funds, approximately 50,166 miles (91%) involved

reconstruction projects with no added roadway capacity, restoration and rehabilitation activities,

or road resurfacing (i.e., projects likely to be processed as CEs). Approximately 4,877 miles of

road construction projects involved new construction, relocation, or reconstruction with added

capacity (i.e., projects likely to require preparation of an EA or EIS).21

In addition to representing a small number of overall projects, few projects currently being

developed require an EIS. As of November 18, 2011, 10 states had no active projects that

involved EIS preparation, 12 states and the District of Columbia and Puerto Rico were preparing

1, and 18 states were preparing between 2 and 5 (illustrated in Figure 2). Further, a significant

number of active EISs (68 of 175 or 39%) were being prepared in just five states—California,

Texas, North Carolina, Florida, and New York.

21

These statistics apply to projects funded under the Federal-aid Highway program. For more detail, see the Federal

Highway Administration’s “Highway Statistics for 2009: Obligation of Federal-Aid Highway Funds For Highway

Improvements Fiscal Year 2009 (Intended to Show Only Projects Authorized in FY 2009),” Table FA-10, October

2010, available at http://www.fhwa.dot.gov/policyinformation/statistics/2009/fa10.cfm.

Congressional Research Service

14

The Role of the Environmental Review Process in Federally Funded Highway Projects

Figure 2. Active FHWA Projects Requiring an EIS in Each State

Source: Congressional Research Service, based on FHWA’s list of Active and Inactive Environmental Impact

Statements (EISs) as of November 18, 2011, available on the agency’s “NEPA and Project Development” website

at http://www.environment.fhwa.dot.gov/projdev/active_eis.asp.

While projects requiring an EIS represent a small proportion of total projects and a small number

of active projects being developed in each state, they are more likely to be high-profile, complex

projects that affect sizeable populations and take years, even decades, from planning to

construction. They may cost millions, or even hundreds of millions, of dollars. For example, data

from 1998 to 2007 regarding FHWA funding allocation show that while projects processed as

CEs generally represent 90% of projects approved, those projects accounted for approximately

76% of FHWA program funds. Over that period, projects requiring an EIS accounted for

approximately 4% of the total projects approved, but 12% of allocated program funds (see Figure

3).

Congressional Research Service

15

The Role of the Environmental Review Process in Federally Funded Highway Projects

Figure 3. Percentage of FHWA Program Funding Allocation by NEPA Class of Action

Average from 1998 to 2007

Source: Congressional Research Service, based on data available on FHWA’s “Streamlining/Stewardship:

Performance Reporting” website, http://www.environment.fhwa.dot.gov/strmlng/projectgraphs.asp/.

While a project requiring an EIS will likely cost more than a project processed as a CE, there is

not necessarily a direct relationship between a project’s cost and its level of environmental

impacts. For example, it cannot be stated that projects that cost over $1 million, or even $10

million, will require an EIS. This point is illustrated by reviewing FHWA’s list of “Major

Projects,” defined to include those expected to receive over $500 million in federal assistance.22

Included on FHWA’s list of currently active major projects are several that are being processed as

CEs or with an approved FONSI.23 For example, the “Loop 12/State Highway 35E Corridor”

project in the Dallas-Fort Worth, TX, area is described as a reconstruction and widening project

estimated to cost $1.6 billion. Project letting for that project began after approval of an

EA/FONSI. Also included on the list is the “I-595 Corridor Improvements Project.” That project,

determined to be a CE, will add reversible lanes and involve major interchange improvements

along 10.5 miles of the I-595 corridor in Florida. It is estimated to cost $1.8 billion.

22

That definition of “Major Projects” was included among provisions in Section 1904 of SAFETEA that amended the

“Project approval and oversight” requirements under 23 U.S.C. §106. The identification of a project as “major,” in this

context, is unrelated to its potential distinction as a “major federal action significantly affecting the quality of the

human environment” pursuant to NEPA under 42 U.S.C. §4332(c).

23

See the FHWA Active Project Status Report, available on FHWA’s “Project Delivery” website,

https://fhwaapps.fhwa.dot.gov/foisp/publicActive.do.

Congressional Research Service

16

The Role of the Environmental Review Process in Federally Funded Highway Projects

Selected Requirements for Each Category of NEPA Document

Each NEPA document (EIS, EA, and CE) must include certain required elements (see Figure 4).

That is, the NEPA document must show that environmental impacts were considered as part of

the federal decision-making process, not a paperwork exercise to document impacts from a

project after a decision was made.

Figure 4. NEPA Decision-Making Process

Required Elements of NEPA Documentation

Source: FHWA guidance document, Integrating Road Safety into NEPA Analysis: A Primer for Safety and

Environmental Professionals, in the “FHWA Environmental Toolkit,” available at

http://www.environment.fhwa.dot.gov/projdev/pd6rs_primer_sec2.asp.

Requirements applicable to each element of each NEPA document, and how DOT requires an

applicant for federal funds to demonstrate compliance with each element, largely evolved in the

20 years after NEPA was enacted. Those requirements are reflected in both CEQ and DOT

regulations implementing NEPA. The evolution of the NEPA compliance process was also

influenced by the courts. For example, the courts played a prominent role in determining issues

such as what constitutes “significant” impacts, who must prepare an EIS, at what point an EIS

must be prepared, and how adverse comments from agencies should be handled. Changes to

required elements of the NEPA process, applicable to projects funded under DOT programs, are

also made by Congress.

Selected requirements applicable to each category of NEPA document, including requirements

established under SAFETEA, are discussed below.

Congressional Research Service

17

The Role of the Environmental Review Process in Federally Funded Highway Projects

Categorical Exclusion (CE) Determinations

As discussed above, projects processed as CEs represent the greatest proportion of projects

approved for federal-aid highway funds. DOT defines CEs as actions that, based on past

experience with similar actions, do not individually or collectively have a significant impact on

any natural, cultural, recreational, historic, or other resource, or involve significant air, noise, or

water quality impacts; and that will not

•

induce significant impacts to planned growth or land use for the area;

•

require the relocation of significant numbers of people;

•

have significant impacts on travel patterns; or

•

otherwise, either individually or cumulatively, have any significant

environmental impacts.24

A project may meet these criteria, but still involve “unusual circumstances” that would require

FHWA to ensure that a CE designation is appropriate. Unusual circumstances applicable to

federally funded highway projects include substantial project controversy on environmental

grounds; a significant impact on properties protected under Section 4(f) or Section 106 of the

National Historic Preservation Act (NHPA); or inconsistencies with any federal, state, or local

requirements relating to the environmental aspects of the action.25

DOT identifies two groups of surface transportation projects that would likely meet the CE

criteria (absent any unusual circumstances applicable to the project). The first group includes

specific actions that meet criteria applicable to CEs.26 DOT has determined that these projects

(presented in Table 1) will likely result in insignificant environmental impacts because they either

do not involve or directly lead to construction or involve minor construction.

Table 1. Federally Funded Highway Projects Specifically Listed as CEs

Non-construction activities (e.g., planning, technical

studies, or research activities).

Emergency repairs after a natural disaster or catastrophic

failure.

Installing fencing, signs, pavement markings, small

passenger shelters, and traffic signals that involve no

substantial land acquisition or traffic disruption.

Deploying electronic, photonic, communication, or

information processing systems to improve system

efficiency or safety.

Altering a facility to make it accessible to elderly and

handicapped persons.

Landscaping activities.

Implementing ridesharing programs.

Improving existing rest areas or truck weigh stations.

Scenic easement acquisition.

Installing noise barriers.

Activities in a state highway safety plan.

Constructing bicycle or pedestrian lanes or facilities.

Source: Congressional Research Service, taken from actions listed at 23 C.F.R. §771.117(c).

24

23 C.F.R. §771.117(a); further DOT criteria used to determine whether a project would meet necessary CE criteria

extend from CEQ regulations defining CEs at 40 C.F.R. §1508.4.

25

23 C.F.R. §771.117(b).

26

Listed at 23 C.F.R. §771.117(c).

Congressional Research Service

18

The Role of the Environmental Review Process in Federally Funded Highway Projects

A proposed action included in this list may or may not require an applicant for federal funds to

submit supporting documentation to FHWA. Necessary paperwork could range from a simple

checklist to substantial documentation. The extent of paperwork or supporting documentation is

directly related to the extent of the impacts and necessary analysis of those impacts. For example,

construction of a bicycle path or installation of traffic signals in a historic district may require

some level of compliance with Section 106 of the NHPA or Section 4(f).

The second group of CEs includes actions that past DOT experience has shown to have

substantial, but generally not “significant,” effects.27 For this group, DOT regulations include

“examples” of actions commonly approved by FHWA that may meet the regulatory definition of a

CE (presented in Table 2). Such projects require the project sponsor to provide FHWA with

documentation to confirm that the project does not involve “unusual circumstances” resulting in

significant environmental impacts. Unlike specifically “listed CEs” (Table 1), the potential

universe of “documented CEs” is not limited to projects identified by DOT. Instead, FHWA may

approve a CE designation for any action as long as documentation is provided that demonstrates

the project meets the regulatory definition of a CE.

Table 2. Examples of FHWA-Approved Projects That May Be Classified as a CE

Actions That May Be Designated a CE with Appropriate Documentation and FHWA Approval

Highway modernization through resurfacing, restoration,

rehabilitation, or reconstruction.

Bridge rehabilitation, reconstruction, or replacement.

Highway safety or traffic operations improvement

projects.

New truck weigh station or rest area construction.

Approval for changes in access control.

Approval for disposal of excess right-of-way or for joint

or limited use of right-of-way.

Acquisition of certain preexisting railroad right-of-way.

Land acquisition for hardship or protective purposes.

Construction of transportation corridor fringe parking

facilities.

Source: Congressional Research Service, taken from examples of actions listed at 23 C.F.R. §771.117(d).

Although they are excluded from the requirement to prepare an EIS or EA, CEs are sometimes

incorrectly identified as being exempt from NEPA or having no environmental impacts. No

significant environmental impact under NEPA does not mean the project has no other regulated

environmental impacts. For example, to demonstrate that a project meets both the CE criteria and

will comply with other environmental requirements, state DOTs routinely gather information

regarding a CE’s potential to

27

•

involve work that requires highway traffic or construction noise abatement;

•

be located within certain limits of a sole source aquifer or alter stream flow;

•

involve the acquisition of more than minor amounts of temporary or permanent

right-of-way;

•

require a Section 4(f) evaluation or “an opinion of adverse effect” under Section

106 of NHPA;

Listed at 23 C.F.R. §771.117(d).

Congressional Research Service

19

The Role of the Environmental Review Process in Federally Funded Highway Projects

•

involve commercial or residential displacement;

•

involve work in wetlands that would require a permit from the Corps; or

•

be constructed in a county that lists federal threatened and endangered species.

A project may involve any one or more of these (or other) activities that will have some effect on

the human or natural environment, yet have environmental impacts that do not rise to the level of

“significant” under NEPA. However, the threshold of significant impacts is primarily relevant to

NEPA compliance. Other laws intended to protect or mitigate impacts to natural or cultural

resources will have their own compliance thresholds applicable to that law. FHWA approval of a

project processed as a CE may be delayed if the project sponsor does not realize that its proposed

project may be subject to compliance requirements in addition to NEPA.

Within its responsibilities to oversee the Federal-aid Highway program, FHWA typically

establishes procedures with each state DOT regarding CE review and approval. In a given state,

“listed CEs” generally require minimal documentation before FHWA approval. NEPA review for

those projects would be included as part of FHWA’s project oversight and approval obligations

established under Title 23. For “documented CEs,” FHWA either reviews the NEPA

documentation as part of the project development process and any agreed-upon procedures as part

of the project review and approval, or the state DOT does this review in accordance with a formal

programmatic CE agreement established between FHWA and the state DOT.

A programmatic CE agreement sets forth specific project circumstances for which a CE could be

processed, and maintains FHWA oversight and responsibility for the NEPA determination. A

programmatic approach involves establishing a streamlined process for handling routine

environmental requirements, commonly applicable to specific types of project (e.g., bridge

maintenance or road resurfacing activities). It allows for repetitive actions to be considered on a

programmatic basis rather than project by project. Established on a local, regional, or statewide

basis, a programmatic CE may establish procedures for consultation, review, and compliance with

one or more federal laws. FHWA suggests that, to the extent possible, state DOTs take a

programmatic approach to CE determinations.

Apart from its potential to enter into programmatic CE agreements with FHWA, state DOTs may

assume FHWA responsibility for CE determinations. Pursuant to provisions in Section 6004 of

SAFETEA,28 FHWA may assign and a state DOT may assume responsibility for determining

whether certain highway projects meet the CE criteria. Under that authority, a participating state

would be authorized to determine all CE applicability, including determining whether proposed

projects that are not specifically listed under DOT’s NEPA regulations may meet the CE criteria.

States that choose to assume FHWA responsibility would be required to do so in accordance with

terms and conditions established in a memorandum of understanding (MOU) between the state

and FHWA.29 States assuming federal authority are legally liable for the NEPA determination.

That is, FHWA would not be liable for the NEPA determinations for CEs in states participating in

the program. FHWA would be required to conduct an annual review of a participating state’s

28

23 U.S.C. §326.

For more information, see memorandum from the U.S. Department of Transportation, Federal Highway

Administration, to Directors of Field Services and Division Administrators, regarding “Guidance on the State

Assumption of Responsibility for Categorical Exclusions (CE),” April 6, 2006, available at http://www.fhwa.dot.gov/

hep/6004memo.htm.

29

Congressional Research Service

20

The Role of the Environmental Review Process in Federally Funded Highway Projects

process for making CE determinations. To date, three states (Alaska, California, and Utah) have

requested and been assigned responsibilities under the Section 6004 program.

Environmental Impact Statements (EIS)

Projects requiring an EIS make up the smallest percentage of projects approved by FHWA, but

have generated the most attention when debating NEPA’s potential role in delaying highway

projects. FHWA does not specifically identify actions that require an EIS. That determination

must be made on a case-by-case basis. However, DOT identifies the following as examples of

highway projects that normally require an EIS: a new controlled access freeway; a highway

project of four or more lanes on a new location; and new construction or extension of a separate

roadway for buses or high-occupancy vehicles not located within an existing highway facility.30

Both the steps to complete an EIS and the EIS itself include certain required elements. Each

required element represents the evolution of NEPA compliance requirements—as established by

CEQ and, in part, as a result of judicial interpretation of NEPA’s mandate and how its procedural

requirements must be implemented. Required components in EIS preparation are

•

file a Notice of Intent (NOI)

•

scope the environmental issues

•

prepare a draft EIS

•

circulate the draft EIS for comment

•

prepare the final EIS

•

issue a final record of decision (ROD)

The NOI serves as the formal announcement of the project to the public and to interested federal,

state, tribal, and local agencies.31 As soon as possible after, or in conjunction with, the

determination that an EIS is needed, the agency is required to determine the scope of the project.

During that process, the project sponsor/applicant for federal funds should determine which

environmental laws, regulations, or other requirements may apply to the project. During the

scoping process, routes that may pose certain challenges and could be avoided may be identified

(e.g., the presence of terrain or resources that may involve potential engineering or technical

problems, regulatory restrictions, or public opposition). For example, during the scoping process,

a potential route or alignment may be identified that would avoid property of historical

significance, endangered species habitat, or wetlands—each of which may require compliance

with the NHPA, the Endangered Species Act, or the Clean Water Act, respectively.

Once the scope of the action and its environmental issues have been determined, EIS preparation

can begin. Required elements of an EIS, including selected elements in DOT’s NEPA regulations

or FHWA policy, are summarized in Table 3.

30

31

23 C.F.R. §771.115(a).

40 C.F.R. §1508.22.

Congressional Research Service

21

The Role of the Environmental Review Process in Federally Funded Highway Projects

Table 3. Required Elements of an EIS as Implemented by FHWA

Elements of

an EIS

Definition/Description

Purpose

and need

statement

(§1502.13)

A brief statement, developed by the lead agency, specifying the underlying purpose of a project

and the need to which the agency is responding. According to FHWA, this section may be the

most important, as it establishes why the agency is proposing to spend large amounts of

taxpayers’ money while at the same time causing significant environmental impacts. A clear, welljustified statement explains to the public and decision makers that the use of funds is necessary

and worthwhile, particularly as compared to other needed highway projects. The statement forms

the basis on which potential alternatives to meet that need are identified and a final alternative is

ultimately selected. It cannot be so narrow that it effectively defines competing “reasonable

alternatives" out of consideration. The "purpose" may be a discussion of the goals and objective.

The "need" may be a discussion of existing conditions that call for some improvement, including

those applicable to transportation demand, safety, legislative direction, urban transportation plan

consistency, modal interrelationships, system linkage, and the condition of an existing facility.

Alternatives

(§1502.14)

Defined as the “heart” of the EIS, this section includes the identification and evaluation of all

reasonable alternatives that may meet a project’s purpose and need. FHWA requires the range of

alternatives to include a discussion of how and why all reasonable alternatives were selected for

consideration, and to explain why other alternatives were eliminated from detailed study. Each

alternative, and its associated impacts, must be evaluated in sufficient detail to allow decision

makers and the public an opportunity to compare the merits of each option.

Affected

environment

(§1502.15)

A succinct description of the environment of the area(s) to be affected or created by the

alternatives under consideration. DOT requires this section to include a description of the

existing social, economic, and environmental setting of the area potentially affected by all

alternatives presented in the EIS. Data may include demographics of the general population served

by the proposed project, as well as an identification of socially, economically, and environmentally

sensitive locations or features in the proposed project area. For example, the EIS should identify

the presence of affected minority or ethnic groups, parks, hazardous material sites, historic sites,

or wetlands, among other factors.

Environmental

Consequences

(§1502.16)

Analysis of impacts of each project alternative on the affected environment, including a discussion

of the probable beneficial and adverse social, economic, and environmental effects of each

alternative. Where applicable, this section must include a description of the measures proposed

to mitigate adverse impacts and methods of compliance with applicable legal requirements.

FHWA recommends this section be devoted largely to a scientific analysis of the direct and

indirect environmental effects of the proposed action relative to each alternative. Potential

environmental consequences identified by FHWA include land use, farmland, social, economic, air

quality, noise, water quality, wetland, wildlife, floodplain, or construction impacts; the requirement

to obtain any permits; impacts to wild and scenic rivers, coastal barriers, threatened or

endangered species, historic and archeological preservation, or hazardous waste sites; and any

irreversible and irretrievable commitment of resources. This section would likely require input

from other federal, state, tribal, or local agencies with expertise on the environmental

consequences under review.

List of

preparers

(§1502.17)

List of names and qualifications of individuals responsible for preparing the EIS. FHWA requires

this section to include lists of state and local agency personnel, including consultants, who were

primarily responsible for preparing the EIS/performing environmental studies and FHWA

personnel responsible for EIS preparation/review.

Appendix

(§1502.18)

Prepared if necessary. An appendix normally consists of material that substantiates analysis

fundamental to the impact statement.

Source: Congressional Research Service, taken from CEQ regulatory definitions under 40 C.F.R. §1502 and

requirements and definitions applicable to highway projects included in FHWA guidance “NEPA and

Transportation Decisionmaking: The Importance of Purpose and Need in Environmental Documents,” and

“Guidance for Preparing and Processing Environmental and Section 4(f) Documents.”

Congressional Research Service

22

The Role of the Environmental Review Process in Federally Funded Highway Projects

The EIS is prepared in two stages, resulting in a draft and a final EIS.32 Supplemental documents

may be required in some instances. Among other requirements, the final EIS must identify the

preferred project alternative; reflect an evaluation of all reasonable alternatives considered;

identify and respond to public and agency comments on the draft EIS; and summarize public

involvement. The final EIS should document compliance with requirements of all applicable

environmental laws, executive orders, and other related requirements. If full compliance is not

possible by the time the final EIS is prepared, it should reflect consultation with the appropriate

agencies and provide reasonable assurance that the requirements will be met. FHWA approval of

the environmental document constitutes adoption of any findings and determinations in the EIS.

The ROD presents the basis for the agency’s final decision and summarizes any mitigation

measures that will be incorporated in the project.

Each required element of the EIS involves compliance requirements established under both NEPA

and other environmental requirements. For example, a clear delineation of project purpose and

need is also necessary to meet the requirements under Section 4(f), executive orders on wetlands

and floodplains, and permitting requirements established under Section 404 of the Clean Water

Act. Identifying the potentially affected environment and analysis of environmental consequences

also demonstrate that environmental impacts are considered during, not after, the decision-making

process (as required under NEPA), but also include consultation, analysis, or input from resource

agencies that may be necessary to ensure compliance with other applicable environmental law.

SAFETEA included several provisions that applied to projects that require an EIS. Section 6002

amended Title 23 by adding “Efficient Environmental Reviews for Project Decision-making”

(§138). It established a new environmental review process applicable to all highways, transit, and

multi-modal projects requiring an EIS. Among other requirements, the new process

•

requires the project sponsor to notify DOT of the type of work, termini, length,

general location of the proposed project, and a statement of any anticipated

federal approvals;

•

establishes a new entity required to participate in the NEPA process, referred to

as a “participating agency,” which includes any federal, state, tribal, regional, and

local government agencies that may have an interest in the project;33

•

requires the lead agency to establish a plan for coordinating public and agency

participation in and comment on the environmental review process for a project

or category of projects;

•

requires the lead agency to establish a 60-day deadline on agency and public

comments on a draft EIS and a 30-day deadline on all other comment periods in

the environmental review process, except under certain circumstances (e.g., the

deadline is extended by the lead agency for “good cause”); and

•

prohibits claims seeking judicial review of a permit, license, or approval issued

by a federal agency for highway or transit projects unless they are filed within

180 days after publication of a notice in the Federal Register announcing the

32

40 C.F.R. §1502.9.

This category of agency participant in the NEPA process differs from a “cooperating agency,” discussed below, that

is defined as an agency having jurisdiction by law or special expertise with respect to any environmental impact of a

proposed project or project alternative.

33

Congressional Research Service

23

The Role of the Environmental Review Process in Federally Funded Highway Projects

final agency action, unless a shorter time is specified in the federal law under

which the judicial review is allowed (previously, the six-year limit under the

Administrative Procedure Act applied to NEPA-related claims).

DOT has produced guidance to help state DOTs implement SAFETEA’s revised environmental

review process and modified regulations implementing NEPA to reflect SAFETEA’s amendments

to Title 23.34

The National Cooperative Highway Research Program conducted a survey of state DOTs to

determine their impressions of the new environmental review process established by SAFETEA.

The DOTs responding to the survey were generally favorable regarding the act’s requirements.35

In particular, there was wide approval of the 180-day statute of limitations.36 However, survey

respondents expressed concerns about some provisions, including their impressions that it

represented no major change from what state DOTs were doing previously; it duplicated existing

coordination procedures; and DOT already involved outside agencies prior to implementing the

new procedures. Further, many survey respondents expressed concern that some requirements of

the new environmental review process seemed to run counter to streamlining initiatives by

creating additional requirements that could have a negative impact on schedules and budgets.37

Under Section 6005, SAFETEA amended Title 23 to establish a “Surface Transportation Project

Delivery Pilot Program” (§327). The pilot program allowed Oklahoma, California, Texas, Ohio,

and Alaska to assume certain federal environmental review responsibilities (in addition to the

assumption of CE determinations established under Section 6004, discussed above).

Responsibility could be assumed for environmental reviews required under NEPA, or any federal

law, for one or more highway projects within the state. As a condition of assuming federal

authority, Congress required the state to waive its right to sovereign immunity against actions

brought by citizens in federal court and consent to the jurisdiction of federal courts. That is, the

state would become solely liable for complying with and carrying out the federal authority that it

consents to assume.

To date, only California has agreed to and developed a program to participate in the pilot

program. Other states declined, primarily due to state legislature concerns regarding the potential

liability associated with assuming federal responsibility for NEPA.

Additionally, some state transportation agency officials and stakeholders with an interest in

transportation project development have expressed concern over DOT requirements

implementing the pilot program (as required pursuant to the directive in Section 6005). Those

objections have centered largely around DOT’s requirement applicable to rights-of-way (ROW)

acquisitions in states that choose to assume federal authority under NEPA. As discussed earlier,

34

See “SAFETEA-LU Environmental Review Process, Final Guidance,” November 15, 2006, available at

http://www.fhwa.dot.gov/hep/section6002/index.htm and the Department of Transportation’s “Environmental Impact

and Related Procedures; Final Rule,” 74 Federal Register 12517, March 24, 2009.

35

See the National Cooperative Highway Research Program’s “Legal Research Digest 54: Practice Under the

Environmental Provisions of SAFETEA-LU,” December 2010, available at http://onlinepubs.trb.org/onlinepubs/nchrp/

nchrp_lrd_54.pdf.

36

There was also wide approval of changes made to Section 4(f) under SAFETEA Section 6002, applicable to de

minimis project impacts (see “Requirements Applicable to Federal-aid Highways”) regarding the “preservation of

parklands” requirements.

37

See the summary of survey respondent impressions of SAFETEA provisions at pp. 16-21.

Congressional Research Service

24

The Role of the Environmental Review Process in Federally Funded Highway Projects

one of NEPA’s primary aims is to ensure that federal agencies consider the impacts of their

actions before proceeding with them. The NEPA process cannot simply document a decision that

has already been made. This requirement means that federal funds cannot be used for ROW

acquisitions (an action that could indicate that a final project decision has been made) before the

NEPA process is complete. Currently, states may make ROW acquisitions using state funds on an

at-risk basis. That is, they may purchase land using state funds, but risk losing future federal

funding for that purchase if the project ultimately involves an alternative that does not use that

property. By assuming DOT’s authority, a state would assume federal agency-level responsibility

to comply with NEPA. DOT has found that would mean, in its capacity as a federal agency, the

state would be precluded from making such advanced ROW acquisitions.

Some have argued that the loss of a state’s ability to make at-risk ROW acquisitions has been a

disincentive to states that may otherwise want to assume federal authority under NEPA. However,

when the fear of taking on federal liability and subjecting the state to the jurisdiction of federal

court were primary reasons that states did not want to assume NEPA authority, it is unclear how

states could be protected from potential judicial review if they are allowed to complete a

transaction that could appear to violate one of NEPA’s primary goals. Although state DOTs may

be willing to accept that risk, a state legislature may not, particularly when an incentive for a state

to assume the federal role under NEPA is to eliminate FHWA’s oversight of the NEPA process

(e.g., FHWA’s legal sufficiency review of an EIS).

Environmental Assessments (EAs)

The third category of NEPA document is an EA. It is required for an action that is not a CE and

does not clearly require an EIS, or where FHWA believes an EA would assist in determining the

need for an EIS. An EA is intended to be a concise public document that serves to provide

sufficient evidence and analysis for determining whether to prepare an EIS or a Finding of No

Significant Impact (FONSI).38

In preparing an EA, the applicant, in consultation with FHWA, is required to consult with

interested agencies at the earliest appropriate time to determine the project scope; determine

which aspects of the proposed action have potential for social, economic, or environmental

impact; identify alternatives and measures which might mitigate adverse environmental impacts;

and identify other environmental review and consultation requirements which should be

performed concurrently with the EA.39

The EA is subject to FHWA approval before it is made available to the public. The document

itself need not be circulated, but must be made available for public inspection and comment

(typically for at least 30 days). A notice of availability must be sent to state- and area-wide

clearinghouses and should be published locally. Depending on FHWA-approved state procedures,

a public hearing may or may not be required.

FHWA requires the basis of a request for a FONSI be clearly and adequately documented. Like an

EIS, the EA or FONSI is required to clearly document compliance with NEPA and all other

applicable environmental laws, executive orders, and related requirements. An approved FONSI

functions as the final agency decision on a project.

38

39

40 C.F.R. §1508.9.

23 C.F.R. §771.119(b).

Congressional Research Service

25

The Role of the Environmental Review Process in Federally Funded Highway Projects

Like projects processed as CEs, determining the time it takes to complete an EA is difficult. Local

and state transportation officials do not routinely, nor could they easily, track the time it takes to

complete an EA. A distinct end point could be identified (issuance of a FONSI), but a starting

point may be hard to identify. Further, since EAs likely require limited environmental review or

analysis under NEPA, any analysis or review that is prepared to support a FONSI would likely be

required under separate state or federal law. However, transportation agency officials have

complained that EAs sometimes approach the length of an EIS. If that is the case, factors

indirectly related to the NEPA compliance likely apply to the project. For example, a project that

may involve local controversy or opposition, but still have no significant impacts, may require

more analysis or documentation than anticipated. Also, a project with substantial environmental

impacts to certain resources may require time-consuming consultation, analysis, or approvals

from agencies outside DOT to confirm that no significant impacts will occur, or it could be an

indication that an EIS should have been prepared initially.

Agency Roles and Responsibilities in the NEPA Process

The NEPA document is prepared by a “lead agency,” and may require input and analysis from

“cooperating” or “participating” agencies. Depending on the environmental impacts of a given

project, both the lead and cooperating agencies are obligated to meet certain federal requirements.

The time it takes to meet those obligations has been identified by transportation agencies as a

potential source of frustration or project delay.

Lead Agencies

The “lead agency” is the federal agency responsible for preparing the NEPA document.40 DOT

must serve as the lead federal agency for a federally funded transportation project (FHWA

generally serves as the lead for highway projects). The direct recipient of federal funds for the

project must serve as a joint lead agency (a requirement explicitly established under SAFETEA).

For a federal-aid highway project, that is typically the state DOT, but may include a local agency

project sponsor or a federally recognized Indian tribal governmental unit. At the discretion of the

required lead agencies, other federal, state, or local governmental entities may act as joint lead

agencies. These include, but are not limited to toll, port, and turnpike authorities and metropolitan

planning organizations (MPOs). For example, the U.S. Department of Homeland Security may

serve as a joint lead agency with DOT and the project sponsor on a transportation improvement at

a national border crossing.

In practice, the entity seeking federal funds will prepare the NEPA document, and other

supporting environmental review documents, with guidance from FHWA (as necessary or as

requested). FHWA, however, has ultimate responsibility to ensure that a project seeking federal

funds will comply with the various laws, regulations, and executive orders applicable to the

project. In that capacity, before final approval and project funding, FHWA is required to

independently evaluate the necessary environmental documents and review the legal sufficiency

of a final EIS41 or Section 4(f) evaluation.42 This review is intended to ensure that the Section 4(f)

40

See 40 C.F.R. §1508.16.

23 C.F.R. §771.125(b). A legal sufficiency review of an EA may be required if FHWA determines that details of the

individual project warrant such a review.

42

23 C.F.R. §774.7(d).

41

Congressional Research Service

26

The Role of the Environmental Review Process in Federally Funded Highway Projects

evaluation or NEPA document is consistent with legal requirements. It includes a review of the

documentation and associated compliance efforts to determine if those efforts are sufficient to

assure compliance with applicable law. A separate technical review of the final NEPA/Section4(f)

document is also conducted by FHWA, prior to document approval.

Cooperating and, after SAFETEA, Participating Agencies

The lead agency must consult with and obtain the comments of any federal agency that has

“jurisdiction by law or special expertise with respect to any environmental impact involved” in an

action that requires an EIS.43 In CEQ’s NEPA regulations, those agencies are identified as

“cooperating” agencies.44 Pursuant to directive from Congress in SAFETEA, DOT’s NEPA

regulations were supplemented to also identify “participating” agencies, which may include any

federal and non-federal agencies that may have an interest in the project.45

At the request of the lead agency, the cooperating agency is required to assume responsibility for

developing information and preparing environmental analyses, including portions of the EIS

related to its special expertise. Cooperating agencies are also obligated to provide comments on

the NEPA document on areas within their jurisdiction, expertise, or authority. For projects

requiring an EIS, that role may be set out in a memorandum of understanding or agreement

between the agencies. The lead agency is also required to request comments from appropriate

state, local, or tribal agencies; any agency that has requested to receive EISs on similar actions;

and the project applicant.46

CEQ regulations specify requirements for inviting and responding to comments on the draft EIS

(including requirements that specify a cooperating agency’s duty to comment on the draft).47 The

lead agency is required to consider those comments and respond in one of the following ways:

•

modify proposed alternatives, including the proposed action;

•

develop and evaluate alternatives not previously considered;

•

supplement, improve, or modify its analyses;

•

make factual corrections in the EIS; or

•

explain why the comments do not warrant further response from the lead agency,

citing the sources, authorities, or reasons that support its position.48

As illustrated in the choices listed above, the lead agency is not precluded from moving forward

with a project if it explains why a cooperating agency’s comments do not warrant further

response. However, FHWA suggests that every reasonable effort be made to resolve interagency

43

42 U.S.C. §4332(2)(C).

40 C.F.R. §1508.5.

45

Specific only to DOT’s NEPA requirements, “participating” agencies for federal highway projects are defined at 23

C.F.R. §771.107(h) as a state, local, tribal, or federal agency that may have an interest in the proposed project and have

accepted an invitation to participate in the environmental review process.

46

40 C.F.R. §1503.1.

47

40 C.F.R. §1503.

48

40 C.F.R. §1503.4.

44

Congressional Research Service

27

The Role of the Environmental Review Process in Federally Funded Highway Projects

disagreements on actions before processing the final EIS. If significant issues remain unresolved,

the final EIS shall identify those issues and any consultation or other effort made to resolve them.

Some highway projects have involved disagreements regarding the appropriate authority and

extent of involvement of coordinating agencies in the NEPA process. For example, in 2003,

Transportation Secretary Norman Mineta requested CEQ Chairman James Connaughton to clarify

the role of lead and cooperating agencies in developing EIS statements of project purpose and

need statements.49 Secretary Mineta cited the sometimes lengthy interagency debates over those

statements as a cause of delay in highway project development. In his response, Chairman

Connaughton referred to CEQ regulations specifying that the lead agency has the authority and

responsibility to define a project’s purpose and need. Further, Chairman Connaughton referenced

previous federal court decisions giving deference to the lead agency in determining a project’s

purpose and need. Chairman Connaughton’s letter also quotes CEQ’s regulations, citing the lead

agency’s “responsibilities throughout the NEPA process for the ‘scope, objectivity, and content of

the entire statement or of any other responsibility’ under NEPA.”

Public Involvement

To meet NEPA’s goal applicable to public participation in federal decision making, CEQ’s

regulations require agencies to provide public notice of NEPA-related hearings, public meetings,

and the availability of environmental documents so as to inform public stakeholders.50 DOT

procedures extend beyond those established under CEQ regulations to reflect requirements

applicable to “public hearings” established under Title 23.51 For example, EAs do not need to be

circulated, but must be made available to the public through notices of availability in local, state,

or regional clearinghouses, newspapers, and other means. Depending on a state’s public

involvement procedures (approved by FHWA), a public hearing may or may not be required for

projects that proceed with an EA. Pursuant to DOT regulations implementing NEPA,

documentation necessary to demonstrate compliance with Title 23’s public hearing requirements

(e.g., public comments or hearing transcripts) must be included in the final EIS or FONSI, as

applicable.

Stakeholders that comment on surface transportation projects may be expected to vary depending

on a project’s impacts. They may include individuals or groups who may benefit from or be

adversely impacted by the project, or special interest groups with concerns about the project’s

impacts on certain affected environments. For example, a highway project that involves

upgrading existing roadways may involve construction activities that would affect adjacent

homes or businesses. The project may elicit comments from the local business community (e.g.,

individual businesses, the Chamber of Commerce, or local development organizations) or area

homeowners. A project that may affect sensitive environmental resources, such as wetlands or

endangered species, may generate comments from local or national environmental organizations.

If a member of the public has concerns about a project’s impacts, comments may be directed at

virtually any element of the NEPA process or related documentation. Someone may disagree with

the definition of project’s purpose and need discussion, the range of “reasonable” alternatives

49

Text of Secretary Mineta’s May 6, 2003, letter, and Chairman Connaughton’s May 12, 2003, response, are available

at http://www.environment.fhwa.dot.gov/guidebook/Ginterim.asp.

50

40 C.F.R. §§1500.2(d). 1506.6.

51

23 U.S.C. §128.

Congressional Research Service

28

The Role of the Environmental Review Process in Federally Funded Highway Projects

selected for consideration and analysis, or the identified level of significance of the project’s

impacts (e.g., a FONSI was issued when the individual felt an EIS should have been required).

Issues that arise during the public comment period may also be the subject of legal action. Critics

of NEPA charge that those who disapprove of a federal project will use NEPA as the basis for

litigation to delay or halt that project. Others argue that litigation results only when agencies do

not comply with NEPA.52

Actual litigation played a prominent role in NEPA’s early implementation. However, it may be the

threat of litigation that affects its current implementation. The number of NEPA-related lawsuits

filed annually against FHWA is low.53 Still, the potential threat of litigation may result in an effort

to prepare a “litigation-proof” NEPA document. This may be the case particularly for projects that

are costly, technically complex (potentially requiring compliance with multiple environmental

laws), or controversial (e.g., opposed by or individuals affected by the project or groups that

anticipate adverse impacts to resources of concern to them). Some look at this positively,

asserting that the fear of a lawsuit makes agencies more likely to adhere to NEPA’s requirements.

Others counter that the threat of litigation may lead to the generation of wasteful documentation

and analyses that do not add value to, and slow, decision making.

Demonstrating Compliance with Additional Requirements

Unlike NEPA, which will apply in some way to all federally funded highway projects, additional

environmental requirements applicable to a project will depend on site-specific conditions and

potential impacts to resources at the site. For example, what and how requirements may apply to a

project will depend on its effect on water quality, water resources, and land use as well as

community, visual, noise, or social impacts, to name a few. While a wide array of requirements

may apply to federally funded highway projects, certain federal requirements apply more

commonly than other requirements. Also, certain compliance requirements have been identified

by transportation stakeholders as those more likely to delay the environmental review process

(see surveys and studies listed in Appendix). The most commonly applicable laws, and selected

compliance requirements, are listed in Table 4.

52

Plaintiffs have generally cited some inadequacy in the NEPA documentation as the basis for filing NEPA-related

lawsuits (see CEQ’s Litigation Surveys for each year from 2001 to 2009 on its “NEPA Litigation” web page at

http://ceq.hss.doe.gov/legal_corner/litigation.html). They may charge, among other things, that an EIS or EA did not

include sufficient analysis of all project alternatives, did not consider all “reasonable” project alternatives, did not

adequately analyze the effects of project alternatives, or that an EA was prepared when an EIS should have been (i.e., a

FONSI was issued when impacts were in fact significant).

53

From 2001 to 2009, NEPA-related lawsuits filed annually against FHWA ranged from a low of three to a high of 12;

see CEQ’s Litigation Surveys cited in footnote 52.

Congressional Research Service

29

The Role of the Environmental Review Process in Federally Funded Highway Projects

Table 4. Federal Law Commonly Applicable to FHWA-Approved Projects

Federal Law

Selected Compliance Requirements

Section 4(f)

For projects that would use a 4(f) resource, an evaluation or a determination of de minimis

impacts must be prepared (see the discussion regarding “Preservation of parklands” in the

“Requirements Applicable to Federal-aid Highways” section). The evaluation or de minimis

impacts determination requires some level of consultation with or concurrence from the

official with jurisdiction over the resource (e.g., the Department of the Interior’s U.S. Fish and

Wildlife Service (FWS); federal, state or local park authorities; or the designated SHPO).

Section 106 of the

National Historic

Preservation Act

For projects that may affect a site included, or eligible for inclusion, in the National Register of

Historic Places, FHWA must consult with the Advisory Council on Historic Preservation

(ACHP) or the designated SHPO to determine impacts to the site and seek ways to avoid,

minimize, or mitigate adverse impacts. Affected parties must be involved in mitigation plans.

Endangered

Species Act

(Section 7)

FHWA must prepare a biological assessment when the presence of threatened or endangered

animals or plants is suspected to occur in the vicinity of a project. FHWA must consult with

the federal agency of jurisdiction (FWS or the Department of Commerce’s National Marine

Fisheries Service (NMFS)) that will issue a biological opinion on whether the proposed action

would jeopardize the continued existence of listed species, or destroy or adversely modify

their designated critical habitats.

The Clean Water

Act (Section 404)

Requires that the discharge of dredge and fill materials into navigable waters of the United

States be done in accordance with review and permitting procedures administered by the

Corps, under guidelines developed by EPA. Other federal agencies potentially involved in

permit evaluation process include FWS or NMFS.

Source: Congressional Research Service, taken from requirements listed in FHWA’s “Summary of

Environmental Legislation Affecting Transportation,” at http://www.fhwa.dot.gov/environment/env_sum.htm.

Note: This is not intended to be an exhaustive list of federal requirements potentially applicable to federally

funded highway projects or a complete description of potentially applicable compliance requirements established

pursuant to each law. However, the selected requirements illustrate the potential need to obtain permits or

consult with agencies outside DOT. Further, federal laws selected for listing in this table represent those

identified by transportation agency officials as a common source of delay in completing the environmental review

process.

As illustrated by the requirements listed in Table 4, when a federal highway project involves

regulated impacts to certain resources, an agency with jurisdiction over that resource may be

required to provide some level of analysis, consultation, or approval before a project can proceed.

Resulting consultation or approval may include directive(s) to the project sponsor regarding how

or whether the proposed project may use the resource. These requirements can lengthen the time

it takes to complete the overall environmental review process, if outside agency opinions, input,

and/or evaluations are required before the NEPA review can be completed. Whether such

requirements will lead to project delays could depend on a host of factors such as whether the

project sponsor anticipated the need for outside agency approval or the workload of the agency

processing the approval.

To integrate the NEPA compliance process and avoid duplication of effort associated with a

project’s overall environmental compliance obligations, CEQ’s NEPA regulations specify that, to

the fullest extent possible, agencies must prepare the NEPA documentation concurrently with any

other environmental requirements. The appropriate NEPA documentation should demonstrate

compliance with all applicable environmental requirements. It must indicate any federal permits,

licenses, and other approvals required to implement the proposed project. This means that

compliance requirements of any additional environmental laws, regulations, or executive orders

must be identified (but not necessarily completed) during the NEPA process. If full compliance is

not possible by the time the final NEPA document is prepared, the document should reflect

Congressional Research Service

30

The Role of the Environmental Review Process in Federally Funded Highway Projects

consultation with the appropriate agencies and provide reasonable assurance that the requirements

will be met.

Environmental Reviews and Project Development

To understand how the environmental review process may affect project delivery, it is useful to

understand how the process fits into overall project development, as well as the challenges

associated with measuring each stage of that development. It is also useful to recognize root

causes of delay in completing the environmental review process, as well as how the process can

lead to more efficient project development.

Stages of Project Development

Federal-aid highway funds are generally apportioned to each state by FHWA for the construction,

reconstruction, and improvement of highways and bridges on eligible highway routes, and for

other special-purpose programs. Individual state DOTs are responsible for determining how and

on which projects those funds will be spent. In making that determination, multiple activities and

decisions occur from the time a tribal or state DOT, metropolitan planning organization, or local

program agency (such as a municipal public works agency) identifies a transportation-related

need and a project addressing that need is constructed.

Each stage of project development is initiated and completed largely at the local, tribal, or state

level, with ultimate project approval at the federal level—from FHWA for federally funded

highway projects. Although the names and details of each step may vary from state to state, they

generally include project planning, preliminary design and environmental review, final design and

right-of-way acquisition, and project construction. Activities common to each phase of the project

development process, including maintenance activities that may take place after project

construction, are described in Table 5. The table also identifies potential environmental

compliance obligations that may occur in each stage of project development.

Congressional Research Service

31

The Role of the Environmental Review Process in Federally Funded Highway Projects

Table 5. Stages of Federal-Aid Highway Project Development

Common Project Activities and Environmental Compliance Obligations in Each Phase of Development

Project

Phase

Description/Common Activities

Common Environmental

Compliance Obligations

Planning

Transportation program or project planning

involves a cooperative process designed to

foster involvement by all users of the planned

system—such as the business community,

community groups, environmental

organizations, the traveling public, freight

operators, and the general public. During this

stage, a proactive public participation process

is conducted by the metropolitan planning

organization (MPO), state DOT, and transit

operators. Among other activities, MPOs and

state DOTs identify current and projected

future transportation problems and needs, and

analyze, through detailed planning studies,

various transportation improvement strategies

to address those needs. They also develop

long-range plans and short-range programs for

alternative capital improvement and

operational strategies for moving people and

goods.

Efforts have been made, in both FHWA

guidance and statutory directive from

Congress, to link statewide and metropolitan

planning to the environmental review process.

For example, Section 6001of SAFETEA

requires the development of long-range

transportation plans to include consultations

with resource agencies responsible for landuse management, natural resources,

environmental protection, conservation, and

historic preservation, which may involve

comparisons of resource maps and

inventories; discussion of potential mitigation

activities; and participation plans that identify

a process for stakeholder involvement.

Preliminary

design and

environmental

review

A project applicant identifies the preliminary

engineering issues, such as proposed alignment

of roadways, costs, and project details. This

stage includes preliminary engineering and

other activities and analyses, such as

topographic or metes and bounds surveys,

geotechnical investigations, hydrologic or

hydraulic analysis, utility engineering, traffic

studies, financial plans, revenue estimates,

hazardous materials assessments, and general

estimates of the types and quantities of

materials and other work needed to establish

parameters for the final design.

An applicant for federal-aid funds must

determine the appropriate NEPA document

to be prepared and identify various resources

potentially affected by a proposed project and

its alternatives. The final NEPA document

must identify and demonstrate compliance

with any other applicable environmental

requirement, to the maximum extent

possible, including completing necessary

environmental or engineering studies, outside

agency coordination or approvals, and public

involvement.

Final design

and rightof-way

acquisition

Final construction plans and detailed

construction specifications for the selected

project alternative are prepared. If necessary,

property appraisals and the acquisition of

rights-of-way (ROW) or property to mitigate

environmental impacts are made. Property

acquisition that may involve the relocation of

residents and businesses must be done in

accordance with the Uniform Act of 1970.

Also, if necessary, utilities are relocated.

Project costs are finalized.

Property or material purchases cannot

proceed until the NEPA document is

approved by FHWA. Property acquisitions

must be completed in compliance with

requirements identified in the document. If

late changes to the project are required, the

environmental review process may have to be

revisited if design changes result in

unanticipated or previously unidentified

environmental impacts.

Congressional Research Service

32

The Role of the Environmental Review Process in Federally Funded Highway Projects

Project

Phase

Description/Common Activities

Common Environmental

Compliance Obligations

Construction

The state DOT, or other project sponsor,

requests and evaluates bids, and awards

contracts. Project construction must reflect

decisions made during the planning,

environmental review, and design stages of

project development.

Necessary permits or other compliance

requirements identified during environmental

review must be in place. Mitigation measures

must be complete (e.g., installation of noise

barriers or implementation of wetland

mitigation). If elements of the project change,

the environmental review process may have

to be revisited if changes result in

unanticipated environmental impacts.

Maintenance

Although not considered part of project

development, the majority of projects funded

under FHWA-approved programs involve

activities that may be broadly described as

“maintenance.” Highway maintenance may

include modernization through roadway

resurfacing, restoration, rehabilitation,

reconstruction, or adding shoulders or

auxiliary lanes. Bridge maintenance may

include rehabilitation, reconstruction, or

replacement.

Identifying, planning, and implementing

necessary maintenance activities are likely

initiated and carried out at the local level,

with state DOT approval. Maintenance

activities would commonly involve a CE

determination as well as an assessment of

impacts that may require compliance with

additional environmental requirements (e.g.,

impacts to historic sites or structures or

endangered species habitat).

Source: Congressional Research Service, based on a review of state DOT practices.

Frequently, “environmental review” is considered synonymous with “NEPA compliance.” That is

not the case. However, completion of the NEPA compliance process and the overall

environmental review process are linked by DOT’s requirement that a project cannot be approved

and subsequent stages of project development cannot proceed until the project sponsor

appropriately documents compliance with NEPA and other applicable environmental

requirements.

Challenges in Measuring Stages of Project Development

There are distinct activities associated with each stage of project development. However, the

following factors make it difficult to estimate the time it takes to complete each stage:

•

Most state and local transportation agencies do not maintain a centralized source

of data tracking the time it takes to complete transportation projects. Further,

there is no acceptable measure of when a project is delivered in a timely manner

versus delayed. A project or a stage of its development may be considered

“delayed” if it took the project sponsor longer than anticipated.

•

Most state and local transportation agencies do not attempt to extract and

measure the time it takes to complete individual activities attributable to a single

stage of development (e.g., activities categorized distinctly as applicable to

“environmental review”). Further, tracking that data may be difficult since

elements of one phase may overlap with another (e.g., project planning activities

may include elements of environmental review) and a distinct start and end point

of individual activities may be difficult to identify.

•

Project development may start, stop, and restart for reasons unrelated to

environmental compliance. For example, EIS preparation may begin with

publication of a NOI, but preparation may stop and restart due to changes in state

Congressional Research Service

33

The Role of the Environmental Review Process in Federally Funded Highway Projects

priorities, funding availability, or a host of other issues unrelated to NEPA. In

such cases, the time between issuing a NOI and ROD are an inaccurate measure

of the NEPA process.

•

Differences between state DOT project development processes make it difficult

to establish a nationally applicable measure of project development stages. Also,

the influence of tribal- or state-specific environmental compliance requirements

makes it difficult to isolate the time it takes to comply with federal requirements.

Considering these points, it is difficult to determine either the time it takes to meet specific

elements of the environmental review process (e.g., NEPA compliance or agency consultations

under the Endangered Species Act) or the degree to which completing the process delays project

delivery. Further, it is not possible to assert, with any degree of accuracy, broad, nationally

applicable values to the time it takes to complete the environmental review process. For example,

there are no data available to substantiate a statement such as “environmental compliance

accounts for X% to Y% of surface transportation project development time,” or “compliance with

NEPA or Clean Water Act permitting requirements delays X% to Y% of projects for X to Y

months/years.” Instead, it may be possible to determine “bridge reconstruction or rehabilitation in

state A takes from X to Y months/years” if state A is one that tracks such information.

Also, it may be generally stated that the time it takes to deliver larger, more complex or

controversial projects takes longer to complete than is typical for the majority of FHWAapproved highway projects (e.g., maintenance and rehabilitation projects). In addition to taking

longer to complete due to their potential cost, size, and complexity, they will likely require

compliance with more state, tribal, and federal requirements and may generate more public

interest or opposition.

In 2002, the General Accounting Office (GAO) released a report that attempted to determine the

typical amount of time it takes to complete overall project delivery as well as individual phases of

project development for certain federally funded highway projects.54 Data for this report were

compiled based on the professional judgment of FHWA staff, staff of state departments of

transportation, and transportation associations. According to FHWA, planning, gaining approval

for, and constructing federally funded major highway projects that involved new construction

typically took from nine to 19 years from planning to construction. FHWA estimated that the

preliminary design and environmental review phase for those projects typically took from one to

five years, depending on the complexity of the design and possible environmental impacts that

must be considered.55 It was noted that projects studied in the GAO report included those that

would typically require an EIS and represent a small percentage of federally funded projects. It

was also noted that, while there are many reasons new highway construction projects may take a

long time to complete, most studies on project delivery focused only on the timely resolution of

environmental issues to improve project completion times, rather than examining all aspects of

project development.56

54

U.S. General Accounting Office (now the Government Accountability Office), Highway Infrastructure: Preliminary

Information on the Timely Completion of Highway Construction Projects, September 19, 2002.

55

In addition to information from FHWA and state DOT staff, this report also looked at the time it took and the steps

necessary to complete six new highway construction projects in California, Florida, and Texas (the largest in the state,

in terms of federal funds received, and a randomly selected “medium-sized” project).

56

Consistent with the factors that make it difficult to measure individual phases of project development, discussed

above, GAO noted that federal and state governments do not maintain information centrally (or, in some cases, at all)

(continued...)

Congressional Research Service

34

The Role of the Environmental Review Process in Federally Funded Highway Projects

Causes of Delay in Completing Environmental Reviews

Although the extent to which the environmental review process may delay project delivery is

unclear, it is generally not disputed that the time it takes to demonstrate compliance with

environmental requirements can be time-consuming, particularly in cases where EIS preparation

is required. Also, while transportation agency officials may cite elements of the environmental

review process as a source of frustration or delay, it is not clear what specific environmental

compliance requirements currently and routinely lead to project delays or the root cause of those

delays.57 For example, a common complaint among transportation agency officials is that outside

agencies (including FHWA review and approval of the final NEPA documents) do not provide

necessary input or approval in a timely way. However, there is little information available that

clearly indicates why that may be the case on anything other than a project-specific level.

Few studies have looked at the root causes of project delay directly attributable to the

environmental review process. Available studies have looked at a limited number of major new

construction projects that required an EIS. By their nature, those projects involve unique projectspecific issues and are likely to involve complex design, engineering, and compliance issues.

Causes of delay for those projects more likely represent the exception and not the rule.

A 2003 FHWA study that attempted to identify causes of delay in completing EISs was unable to

identify common factors or conditions that directly or indirectly affected the time it took to

complete the NEPA process.58 Although timing varied by broad geographic region, it did not seem

to vary in relation to the majority of other variables considered (e.g., the presence of certain

“controversial issues” or the required participation of agencies outside DOT). Instead, it was

observed that the time it took to complete the NEPA process may have been more affected by

external social and economic factors associated with broad geographic regions of the country.59

Subsequent, albeit limited, study data and anecdotal evidence regarding individual projects also

point to factors external to environmental reviews as those most likely to delay the process. In

particular, causes of delay in completing environmental reviews arise primarily from potentially

overlapping local and project-specific issues including, but not limited to, the following:

•

Local issues—the project’s level of priority among others proposed in the state;

changes in funding availability; concerns of local property owners; or opposition

to the project (which may or may not be connected to environmental issues).

(...continued)

on the time it takes to complete highway projects. GAO also noted that there was no accepted measuring stick with

which to gauge whether project performance is “timely.” To make its determination on project timing, GAO relied on a

best estimate prepared by FHWA. According to FHWA, the estimate it provided to GAO was based on the professional

judgment of its staff and several state DOTs.

57

The identification of factors that currently affect project delivery is particularly relevant when considering legislative

options to address potential causes of delay in the environmental review process. State DOTs have improved their

environmental review procedures in the past 10 years. Also, FHWA has expanded its efforts to provide information and

guidance on the process, including increased efforts to encourage states to implement programmatic agreements

applicable to NEPA compliance and other environmental laws.

58

Federal Highway Administration and the Louis Berger Group, Evaluating the Performance of Environmental

Streamlining: Phase II, 2003, available on FHWA’s “Streamlining/Stewardship” website,

http://www.environment.fhwa.dot.gov/strmlng/baseline/phase2rpt.asp.

59

Ibid., under “Conclusions 4.2.”

Congressional Research Service

35

The Role of the Environmental Review Process in Federally Funded Highway Projects

•

Project-specific issues—the project’s technical complexity; changes in project

scope or design; lawsuits or the threat of litigation (which may or may not be

connected to environmental issues); poor consultant work; issues with city

documentation; issues with new alignment or coordination with other

transportation projects; or land use planning issues.60

As discussed previously, environmental requirements identified as a source of delay have been

associated with selected requirements established under Section 4(f); the Endangered Species

Act; the National Historic Preservation Act; and the Clean Water Act. If a project is delayed by

requirements under those laws, that delay may be attributable to project-specific issues.

Efforts to identify specific problems or causes of delay in meeting requirements other than NEPA

have found differing perceptions among resource agency and transportation agency officials. For

example, in completing its obligations as part of the environmental review process, resource

agencies have identified poor communication, problems with the project’s alternative analysis,

being given incorrect or incomplete information, disagreements or differences of opinion among

agencies, or environmental or biological issues associated with the project. Transportation agency

officials also cited disagreements or differences of opinion and environmental or biological issues

associated with the project, but identified a lack of timely response from resource agencies as the

primary problem.61

Benefits to the Environmental Review Process

When there is debate over potential options to expedite the environmental review process, that

process may be viewed as simply an obstacle to overcome before a highway or bridge project can

be built. Benefits to the process may be overlooked or hard to quantify. Potential benefits may

generally be thought of as those associated with balancing transportation and infrastructure needs

with environmental protection and community concerns. However, one benefit that is not often

considered is the degree to which the environmental review process may ultimately save time and

reduce overall project costs by identifying and avoiding problems in later stages of project

development. A study prepared for the Transportation Research Board made this point when

evaluating causes of delay in the construction phases of development.62

Among other findings, the study found that certain recognized management principles, identified

as relevant to timely completion of highway construction projects, should be applied by state

highway administrators and contractors. It found that adherence to these principles was often

inconsistent and lacking, usually resulting in construction delays. Among the principles identified

was the “Cost-Time Relationship,” under which, the study found,

60

Factors listed here are those that have been most commonly identified in surveys or studies conducted by FHWA and

GAO, as well as selected university and transportation organizations. For a list of the surveys and studies used to

prepare this report, see Appendix. Those surveys and studies have looked primarily at causes of delay applicable to

projects that require an EIS.

61

See “FHWA/Gallup Study on Implementing Performance Measurement in Environmental Streamlining,” available at

http://environment.fhwa.dot.gov/strmlng/gallup_05-07.asp.

62

Thomas, H.R. and Ellis, R.D, Avoiding Delays During the Construction Phase of Highway Projects, Transportation

Research Board, National Research Council, October 2001, NCHRP 20-24(12). Also see “The Root Causes of Delays

in Highway Construction,” a summary of the study’s findings submitted for presentation by the authors at the TRB

annual meeting in 2003, available at http://www.ltrc.lsu.edu/TRB_82/TRB2003-000646.pdf.

Congressional Research Service

36

The Role of the Environmental Review Process in Federally Funded Highway Projects

More time spent in design identifying problems will reduce construction time and result in a

shorter overall project time. A widely recognized principle is that spending more monies

during planning and design will reduce the time and cost required for construction by

avoiding unforeseen conditions, reducing to a minimum design errors and omissions, and

developing schemes that will support the most efficient approach to construction. In the

design phase, the opportunity to make decisions to influence the final project cost is greatest.

Yet, the expenditure of project funds is comparatively minimal, typically about 10% of the

capital budget.63

These study findings illustrate the potential problem with considering time spent in the planning

or preliminary design stage as a delay. It is impossible to determine whether or how much time

may be saved, and project delivery ultimately accelerated, by avoiding conditions identified early

in the process.

Expediting Environmental Reviews

Lessons Learned

The potential for the environmental review process to expedite project delivery is illustrated in

findings of a 2009 peer exchange between representatives from state DOTs and FHWA Division

Offices. The exchange was intended to identify strategies to more effectively move complex

environmental documents through the EIS process.64 Participants presented information on

projects in their states that had moved through the environmental review process quickly. They

highlighted the challenges encountered, methods used to successfully and efficiently navigate the

EIS process, and lessons learned from their experience. It was observed that the practices

described by state DOTs represented a fundamental shift in the way agencies have conducted

environmental reviews over the last 10 to 15 years. Those state DOTs were found to have

embraced innovative and creative solutions to balance transportation and infrastructure needs

with environmental protection and community concerns. The environmental review

processes for the successful projects … were conducted in a collaborative and transparent

manner, whereby [state DOTs] sought to include stakeholders early and often throughout

development of the EIS. Such methods not only lead to a faster completion of the

environmental review process, but perhaps more importantly, they result in the delivery of

better quality projects, ones that fulfill the transportation needs of communities while

maintaining protection of environmental resources at the same time.65

One recent event serves as a good example of how environmental compliance requirements can

be coordinated efficiently. That event was the reconstruction of the I-35 bridge in Minneapolis

after its August 1, 2007, collapse. A new bridge opened just over a year later on September 18,

63

“The Root Causes of Delays in Highway Construction,” p. 3.

Strategies and Approaches for Effectively Moving Complex Environmental Documents Through the EIS Process: A

Peer Exchange Report, prepared by the John A. Volpe National Transportation Systems Center Research and

Innovative Technology Administration, U.S. Department of Transportation for the Office of Project Development and

Environmental Review, Federal Highway Administration, January 2009, available on FHWA’s

“Streamlining/Stewardship” website at http://environment.fhwa.dot.gov/strmlng/eisdocs.asp.

65

Ibid., under “Recommendations for Successful Tools & Techniques.”

64

Congressional Research Service

37

The Role of the Environmental Review Process in Federally Funded Highway Projects

2008. The timing of that bridge reconstruction led to the question “Why can’t all projects be

completed that quickly?”

The answer to this question can be found, in part, in an FHWA study that examined how the key

elements of the environmental review process were completed after a bridge collapse.66 A primary

factor cited in the study was that, in the wake of an emergency, the major causes of surface

transportation project delay are absent. The “major causes of delay” identified were a lack of

funding or priority in the state for the project; local controversy; interested stakeholder or local

opposition; or insufficient political support.67 Other potential causes of delay could still apply to

emergency projects, including issues with the projects’ complexity, poor consultant work, or the

environmental review process.

The FHWA study looked at the Minnesota bridge collapse as well as other projects that involved

bridge reconstruction after a collapse. Projects in the study illustrated how efficiently the

environmental review process could be implemented if the more common sources of delay are

absent and environmental review involves efficient interagency cooperation.

Bridge reconstruction for the I-35 project required the same environmental permits that would

apply to any bridge reconstruction project of similar scope and scale. Despite the urgency of the

project, there was no waiver or exemption from the environmental review or permit requirements.

The replacement bridge was widened to accommodate future transit options, but did not increase

capacity. The project fit the criteria necessary to be processed as a CE, but still required

•

a permit issued by the Corps under Section 404 of the Clean Water Act;

•

a bridge construction permit issued by the U.S. Coast Guard;

•

an assessment of potential impacts to threatened and endangered species by a

consultation team formed by FHWA, Minnesota DOT (MnDOT), and the

Department of the Interior’s U.S. Fish and Wildlife Service (FWS);

•

a Minnesota Pollution Control Agency permit certifying compliance with the

Clean Water Act’s National Pollutant Discharge Elimination System and other

requirements; and

•

an assessment of potential cultural and historic issues through MnDOT’s Cultural

Resources Unit (CRU), in part, in accordance with a programmatic agreement

with the Minnesota SHPO and tribes interested in reviewing state projects.

Efficient interagency coordination on the project was a factor identified as one associated with

expedited reconstruction of the bridge. However, the efficiency of that agency interaction did not

begin with this project. FHWA observed that staff from state and federal agencies involved in the

environmental review process had worked collaboratively on past projects. The agencies

established lines of communication and understood the tasks and concerns of each other’s

66

See “Meeting Environmental Requirements After a Bridge Collapse,” prepared for the Office of Project

Development and Environmental Review, Federal Highway Administration, U.S. Department of Transportation, and

prepared by the John A. Volpe National Transportation Systems Center Research and Innovative Technology

Administration, U.S. Department of Transportation, August 2008, available at http://www.environment.fhwa.dot.gov/

projdev/bridge_casestudy.asp.

67

Major sources of project delay cited in the bridge study are those identified in FHWA survey results included in

Appendix.

Congressional Research Service

38

The Role of the Environmental Review Process in Federally Funded Highway Projects

agencies. Those existing relationships led to a quick response among those agencies after the

bridge collapse. Further, FHWA and MnDOT recognized that by limiting the scope of the project,

the environmental review process was expedited because no expanded environmental review was

needed (e.g., it met the criteria applicable to a CE). Further, federal and state resources were

focused on this project—its completion was a priority to the state.

Apart from issues cited in the FHWA bridge study, MnDOT cited its use of a design-build

procurement process as an important factor in the expediting project completion. A “designbuild” process brings designers and contractors together early in the project development process

and allows for a shortened process completion time by overlapping design and construction.68

Lessons learned from projects completed relatively quickly as well as suggested solutions from

transportation agency officials69 involve certain common approaches or procedures that have or

could streamline the environmental review process. Those approaches include the following:

•

efficient interagency communication and project coordination;

•

early and continued communication with stakeholders affected by a project;

•

improvements in internal processes and procedures;

•

demonstrated agency commitment to priority projects and project schedules;

and/or

•

programmatic approaches to meeting compliance obligations.

Each of these approaches can be implemented under existing standards and requirements

applicable to federally funded highway projects. For example, CEQ and DOT regulations

implementing NEPA include explicit requirements intended to identify potential environmental

issues early in the project development process and coordinate efficient interagency cooperation.

CEQ also provides federal agencies with guidance on improving the efficiency and timeliness of

their environmental reviews under NEPA.70 DOT provides guidance and information intended to

assist state and local agencies in implementing the environmental review process more

efficiently.71

68

For more information about the bridge reconstruction project, see the Minnesota DOT “I-35W St. Anthony Falls

Bridge” website at http://projects.dot.state.mn.us/35wbridge/index.html.

69

See findings in the 2007 FHWA/Gallup study (cited in footnote 61).

70

CEQ guidance “Improving the Process for Preparing Efficient and Timely Environmental Reviews under the

National Environmental Policy Act,” released on March 6, 2012, available at http://www.whitehouse.gov/

administration/eop/ceq/initiatives/nepa/efficiencies-guidance. CEQ stated that the guidance is part of its broader effort

to “modernize and reinvigorate” federal agency implementation of NEPA and to support goals established in President

Obama’s August 31, 2011, memorandum, “Speeding Infrastructure Development through More Efficient and Effective

Permitting and Environmental Review.” For information about CEQ pilot programs established to support those goals,

see http://www.whitehouse.gov/administration/eop/ceq/initiatives/nepa/nepa-pilot-project.

71

See FHWA’s online “Environmental Review Toolkit,” available at http://environment.fhwa.dot.gov/index.asp. It

includes, for example, guidance and information regarding linking project planning and environmental requirements;

NEPA requirements applicable to project development; a database of “lessons learned” related to streamlining and

environmental stewardship; and guidance on compliance requirements such as those applicable to wetlands, Section

4(f), and historic preservation.

Congressional Research Service

39

The Role of the Environmental Review Process in Federally Funded Highway Projects

Administrative Efforts

In 2009, DOT initiated its “Every Day Counts” program to identify and implement approaches to

shortening project delivery (among other goals). The program includes an evaluation of potential

changes in DOT’s role in implementing the environmental review process, including the

following efforts:

•

Improve the link between project planning and environmental review—sets

up a framework for incorporating planning documents and decisions from the

earliest stages of project planning into the environmental review process.

•

Enhance legal sufficiency reviews—uses the process to identify the most

common problems in NEPA and Section 4(f) document development, their root

causes, and the measures local and state transportation agencies can take to avoid

the problems; and encourages reviews when documents are in their draft stage,

reducing the potential need for multiple legal reviews of a “final” document and

helping to resolve conflict and potential controversy earlier in the process, when

project schedules can better accommodate the change.

•

Expand the use of programmatic agreements—identify new and existing

programmatic agreements that may be expanded to a regional or national level.

•

Encourage the use of existing regulatory flexibility—clarify existing

requirements applicable to activities that may be allowed during the preliminary

design phase of development and to ROW acquisition and utility relocation.

These issues identified by both DOT and state transportation agencies illustrate the need to more

efficiently implement existing requirements or to identify barriers to implementing them.

Conclusions

There is little debate that delays in transportation project delivery can result in higher project

costs, as well as delay potential positive economic advantages such as bringing project-related

jobs to the community. Also, it is known that completing the environmental review process takes

time, sometimes years for complex, major projects. Meeting environmental compliance

requirements may result in project delays or, at least, a project taking longer than anticipated by

its sponsor. However, what is unclear is whether or what specific elements of the environmental

review process routinely delay project delivery.

The time it takes to complete the NEPA process is often the focus of debate over project delays

attributable to the environmental review process. However, the influence of environmental

requirements established under Title 23 and other federal law call into question the degree to

which changes in the NEPA process will expedite the environmental reviews and accelerate

project delivery. Further, although there are no comprehensive data and available information

tends to be anecdotal, when delays in the environmental review process have been identified, they

primarily stemmed from local or project-specific issues (e.g., project complexity, changes in state

priorities, or late changes in project scope).

Regardless of potential changes to the NEPA process or the overall environmental review process,

local factors will strongly influence project delivery time. State or local decision makers will

continue to have the most significant influence on project delivery in their capacity to establish

Congressional Research Service

40

The Role of the Environmental Review Process in Federally Funded Highway Projects

(and change) project priorities, allocate available funds, and be influenced by local controversy or

project opposition. A project’s environmental review process may be efficiently executed and

involve no delays in the process itself, but still take decades or never be completed if local and

state issues are acting against the project.

The potential success of efforts intended to expedite the environmental review process would

involve evidence that transportation projects were delivered more quickly. However, considering

the limits to measuring the time it takes to complete the environmental review process, the

relative success of a particular approach may be gauged in terms of the degree to which state or

local transportation agencies find it useful in meeting their environmental compliance obligations.

Compared to transportation planning and project development during construction of the

Interstate Highway System, state and local transportation agencies are more inclined to consider a

project’s effects on communities and resources. Apart from any potential changes to federal

environmental review requirements, local and state agency decisions regarding transportation

project planning, funding, and development will continue to be strongly influenced by a project’s

benefits and adverse effects to the environment and the community it serves.

Congressional Research Service

41

The Role of the Environmental Review Process in Federally Funded Highway Projects

Appendix. Surveys and Studies Applicable to the

Environmental Review Process

In this report, summary information and conclusions regarding factors applicable to measuring

the stages of project development, the time it takes to complete the environmental review process,

and primary sources of delay or perceptions among transportation agency officials regarding

causes of delay in completing the environmental review process were drawn from data included

in the following surveys and studies conducted by FHWA, GAO, universities, or transportation

organizations:

Federal Highway Administration (available on FHWA’s “Environmental Toolkit:

Streamlining/Stewardship—Performance Reporting” website, http://environment.fhwa.dot.gov/

strmlng/es10measures.asp).

•

Evaluating the Performance of Environmental Streamlining: Phase II, an FHWAcommission study conducted by the Louis Berger Group, 2003.

•

FHWA surveys, Reasons for EIS Project Delays and Information on Timeliness

on Completing the NEPA Process.

•

Strategies and Approaches for Effectively Moving Complex Environmental

Documents Through the EIS Process: A Peer Exchange Report, prepared for

FHWA by DOT’s John A. Volpe National Transportation Systems Center

Research and Innovative Technology Administration, January 2009.

•

FHWA/Gallup Study on Implementing Performance Measurement in

Environmental Streamlining, “Implementing Performance Measurement in

Environmental Streamlining,” May 2007.

Government Accountability Office.

•

Highway Infrastructure: Stakeholders’ Views on Time to Conduct Environmental

Reviews of Highway Projects, GAO-03-534, May 23, 2003.

•

Highway Infrastructure: Preliminary Information on the Timely Completion of

Highway Construction Projects, GAO-02-1067T, September 19, 2002.

University and Transportation Organization Studies.

•

What Influences the Length of Time to Complete NEPA Reviews? An Examination

of Highway Projects in Oregon and the Potential for Streamlining, by Jennifer

Dill, Center for Urban Studies, Nohad A. Toulan School of Urban Studies &

Planning, Portland State University, submitted for presentation at the 85th Annual

Meeting of the Transportation Research Board, November 15, 2005 (revised).

•

Causes and Extent of Environmental Delays in Transportation Projects, prepared

by TransTech Management, Inc., for the American Association of State Highway

and Transportation Officials (AASHTO), December 2003.

•

Environmental Streamlining: A Report on Delays Associated with the Categorical

Exclusion and Environmental Assessment Processes, prepared by TransTech

Management, Inc., for AASHTO, October 2000.

Congressional Research Service

42

The Role of the Environmental Review Process in Federally Funded Highway Projects

Author Contact Information

(name redacted)

Analyst in Environmental Policy

[redacted]@crs.loc.gov, 7-....

Congressional Research Service

43

EveryCRSReport.com

The Congressional Research Service (CRS) is a federal legislative branch agency, housed inside the

Library of Congress, charged with providing the United States Congress non-partisan advice on

issues that may come before Congress.

EveryCRSReport.com republishes CRS reports that are available to all Congressional staff. The

reports are not classified, and Members of Congress routinely make individual reports available to

the public.

Prior to our republication, we redacted names, phone numbers and email addresses of analysts

who produced the reports. We also added this page to the report. We have not intentionally made

any other changes to any report published on EveryCRSReport.com.

CRS reports, as a work of the United States government, are not subject to copyright protection in

the United States. Any CRS report may be reproduced and distributed in its entirety without

permission from CRS. However, as a CRS report may include copyrighted images or material from a

third party, you may need to obtain permission of the copyright holder if you wish to copy or

otherwise use copyrighted material.

Information in a CRS report should not be relied upon for purposes other than public

understanding of information that has been provided by CRS to members of Congress in

connection with CRS' institutional role.

EveryCRSReport.com is not a government website and is not affiliated with CRS. We do not claim

copyright on any CRS report we have republished.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.