Keystone XL Pipeline Project: Key Issues

Congressional research reportDec 2, 2013

Ask Donna

What actually matters in this document.

Text

Keystone XL Pipeline Project: Key Issues

Paul W. Parfomak

Specialist in Energy and Infrastructure Policy

Robert Pirog

Specialist in Energy Economics

Linda Luther

Analyst in Environmental Policy

Adam Vann

Legislative Attorney

December 2, 2013

Congressional Research Service

7-5700

www.crs.gov

R41668

Keystone XL Pipeline Project: Key Issues

Summary

TransCanada’s proposed Keystone XL Pipeline would transport oil sands crude from Canada and

shale oil produced in North Dakota and Montana to a market hub in Nebraska for further delivery

to Gulf Coast refineries. The pipeline would consist of 875 miles of 36-inch pipe with the

capacity to transport 830,000 barrels per day. Because it would cross the Canadian-U.S. border,

construction of Keystone XL requires a Presidential Permit from the State Department. A decision

to issue or deny a Presidential Permit is based on a determination that a project would serve the

national interest, considering potential impacts on the environment, the economy, energy security,

foreign policy, and other factors. Environmental impacts are evaluated and documented in an

Environmental Impact Statement (EIS) under the National Environmental Policy Act (NEPA).

TransCanada originally applied for a Presidential Permit for the Keystone XL Pipeline in 2008.

The initial proposal included a southern segment from Oklahoma to the Gulf Coast. A key issue

that arose during the permit review was concern over environmental impacts in the Sand Hills

region of Nebraska. This concern led the Nebraska legislature to enact new state pipeline siting

requirements that would alter the pipeline route through Nebraska. In January 2012, the State

Department concluded that it would not have sufficient information to evaluate an altered

pipeline route before a deadline imposed by Congress and denied the permit. The southern

segment of the original Keystone XL proposal, now called the Gulf Coast Project, was

subsequently separated from the original proposal because it did not require a Presidential Permit.

It has been approved by the relevant states and is currently under construction.

In May 2012, TransCanada reapplied to the State Department for a Presidential Permit to build

the northern, cross-border segment of Keystone XL. The new permit application initiated a new

NEPA process. The governor of Nebraska approved a new route through the state avoiding the

Sand Hills on January 22, 2013. On March 6, 2013, notice was published in the Federal Register

that the State Department draft EIS for the reconfigured Keystone XL Project was available for

public comment. The department is in the process of addressing these comments as it prepares a

final EIS. When the final EIS is issued, a 90-day public review period for the national interest

determination begins. The department has not stated when it plans to complete this process.

Development of Keystone XL has been controversial. Proponents base their arguments primarily

on increasing the diversity of the U.S. petroleum supply and economic benefits, especially jobs.

Pipeline opposition stems in part from concern regarding the greenhouse gas emissions associated

with the development of Canadian oil sands, continued U.S. dependency on fossil fuels, and the

risk of a potential release of heavy crude.

In light of the State Department’s denial of the 2008 permit application, some in Congress seek

other means to support development of the pipeline. The Energy Production and Project Delivery

Act of 2013 (S. 17) would eliminate the Presidential Permit requirement for the reconfigured

Keystone XL Project. The Keystone for a Secure Tomorrow Act (H.R. 334) and a Senate bill to

approve the Keystone XL Project (S. 582) would directly approve Keystone XL under the

authority of Congress to regulate foreign commerce. The Northern Route Approval Act (H.R. 3)

would eliminate the Presidential Permit requirement for Keystone XL, among other provisions.

The Senate passed an amendment to the Fiscal 2014 Senate Budget Resolution (S.Con.Res. 8)

that would provide for the approval and construction of the Keystone XL Project (S.Amdt. 494).

The North American Energy Infrastructure Act (H.R. 3301) would transfer permit authority for

oil pipelines from the State Department to the Department of Commerce and would make other

changes to the pipeline permitting process.

Congressional Research Service

Keystone XL Pipeline Project: Key Issues

Congressional Research Service

Keystone XL Pipeline Project: Key Issues

Contents

Introduction...................................................................................................................................... 1

Description of the Keystone Pipeline System.................................................................................. 2

The Keystone and Keystone XL Pipelines ................................................................................ 2

Marketlink for Bakken Oil Production ...................................................................................... 4

Presidential Permit Applications ...................................................................................................... 5

Consideration of Environmental Impacts Under NEPA ............................................................ 7

EPA Rating of the Environmental Impact Statement .......................................................... 8

The National Interest Determination ....................................................................................... 11

State Siting and Additional Environmental Requirements ...................................................... 13

Legislative Efforts to Change Permitting Authority ................................................................ 15

Arguments For and Against the Pipeline ....................................................................................... 16

Impact on U.S. Energy Security .............................................................................................. 17

Canadian Oil Imports in the Overall U.S. Supply Context ............................................... 18

Oil Sands, Keystone XL, and the U.S. Oil Market ........................................................... 19

Economic Impact of the Pipeline............................................................................................. 26

Lifecycle Greenhouse Gas Emissions ..................................................................................... 27

Private Land Use and Oil Spill Impacts .................................................................................. 28

Issues with the Original Pipeline Route Across the Sand Hills ............................................... 30

Figures

Figure 1. Existing Keystone Pipeline and Proposed Keystone Expansions .................................... 3

Figure 2. The Keystone XL Project and Gulf Coast Pipeline .......................................................... 4

Figure 3. Proposed Enbridge Flanagan South Pipeline Route ....................................................... 23

Figure 4. Keystone XL Project—Pipeline Route in Nebraska....................................................... 32

Tables

Table 1. Milestones in the NEPA process for the Keystone XL Project ........................................ 10

Table 2. Milestones in National Interest Determination Process for the 2008 Keystone XL

Pipeline ....................................................................................................................................... 13

Table 3. U.S. Oil Imports ............................................................................................................... 19

Appendixes

Appendix A. Presidential Permitting Authority ............................................................................. 33

Appendix B. Details of the Initial NEPA Review .......................................................................... 35

Congressional Research Service

Keystone XL Pipeline Project: Key Issues

Contacts

Author Contact Information........................................................................................................... 38

Acknowledgments ......................................................................................................................... 38

Congressional Research Service

Keystone XL Pipeline Project: Key Issues

Introduction1

In 2008, TransCanada (a Canadian company) submitted to the U.S. Department of State an

application for a Presidential Permit authorizing construction and operation of pipeline facilities

for the importation of crude oil at the United States-Canada border. The Keystone XL Pipeline

system would transport Canadian oil sands crude extracted in Alberta, Canada, and crude

produced from the Bakken region in North Dakota and Montana to a market hub in Nebraska for

further delivery to Gulf Coast refineries. A decision to issue or deny the Presidential Permit would

be based on the State Department’s determination of whether the pipeline system would serve the

national interest.

By August 2011, the State Department had compiled data necessary to begin the required 90-day

public review period for making its national interest determination. During that period, one key

issue that arose pertained to potential impacts associated with the construction and operation of

the proposed pipeline segment across the Sand Hills region of Nebraska. This concern led the

Nebraska legislature to enact new state pipeline siting requirements that would alter the pipeline

route through Nebraska. As a result, in November 2011, the State Department announced that it

would need additional time to gather information needed to assess a new pipeline route avoiding

the Sand Hills. However, the Temporary Payroll Tax Cut Continuation Act of 2011 (P.L. 112-78),

enacted on December 23, 2011, included provisions requiring the Secretary of State (hereinafter

the Secretary) to issue a permit for the project within 60 days, unless the President determined the

project not to be in the national interest. Citing insufficient time to meet the deadline established

by Congress, the State Department, with the President’s consent, denied the permit for the

Keystone XL Project.

TransCanada and Nebraska have since agreed upon an alternative pipeline route avoiding the

Sand Hills. In May 2012, TransCanada submitted an application to the State Department for a

Presidential Permit to build a newly configured cross-border segment of Keystone XL Pipeline

system.2 This report describes the Keystone XL Project as it is proposed in the 2012 Presidential

Permit application and the process that the State Department is obligated to complete to issue or

deny that application. To the extent that they may affect the State Department’s decision to issue

or deny the current permit application, this report discusses selected issues related to the project

proposed in 2008 and issues that have arisen since the State Department denied the initial permit

application in 2012. This report also summarizes key arguments that have been raised, both for

and against the pipeline, by the pipeline’s developers, state and federal agencies, environmental

groups, private property owners, and other stakeholders. Finally, the report discusses the

constitutional basis for the State Department’s authority to issue a Presidential Permit, and

opponents’ possible challenges to this authority.

1

This report provides an overview of the Keystone XL project, permit review process, and general policy issues. For

more detailed legal analysis, see CRS Report R42124, Proposed Keystone XL Pipeline: Legal Issues, by Adam Vann,

Kristina Alexander, and Kenneth R. Thomas. For more analysis of U.S.-Canada energy trade, see CRS Report R41875,

The U.S.-Canada Energy Relationship: Joined at the Well, by Paul W. Parfomak and Michael Ratner. For additional

environmental analysis associated with Canadian oil sands, see CRS Report R42537, Canadian Oil Sands: Life-Cycle

Assessments of Greenhouse Gas Emissions, by Richard K. Lattanzio. For more analysis of Presidential Permits, see

CRS Report R43261, Presidential Permits for Border Crossing Energy Facilities, by Adam Vann and Paul W.

Parfomak.

2

The southern segment of the original Keystone XL proposal, now called the Gulf Coast Project, was separated from

the original proposal because it does not require a Presidential Permit. It is currently under construction.

Congressional Research Service

1

Keystone XL Pipeline Project: Key Issues

Description of the Keystone Pipeline System

In 2005, TransCanada announced a plan to address expected increases in Western Canadian

Sedimentary Basin production by constructing the Keystone Pipeline System. When complete,

the system would transport crude oil from Hardisty, Alberta, to U.S. markets in the Midwest and

Gulf Coast. The pipeline system was proposed as two distinct phases—the Keystone Pipeline

(complete and in service) and the Keystone XL Pipeline.

The Keystone and Keystone XL Pipelines

The Keystone Pipeline was completed in two segments—the Keystone Mainline and the Cushing

Extension. The Mainline is 1,353 miles of 30-inch pipeline from Hardisty, Alberta, to the United

States refineries in Wood River and Patoka, Illinois. The U.S. portion of the pipeline runs 1,086

miles and begins at the international border in Cavalier County, ND, and has been in service since

June 2010. The Cushing Extension is 298 miles of 36-inch pipeline and associated facilities that

run from Steele City, NE (near the Kansas border), to existing crude oil terminals and tanks farms

in Cushing, OK. The Cushing Extension has been in service since February 2011.

The original Keystone XL Pipeline Project is now also being developed in two project segments,

as follows:

•

The Gulf Coast Pipeline Project, 485 miles of 36-inch pipeline and associated

facilities linking the Cushing, OK, tank farms to refineries in Houston and Port

Arthur, TX. This segment includes the Cushing Marketlink project that will

provide receipt facilities to transport U.S. crude oil to the Gulf Coast.

TransCanada anticipates this segment to be in service by 2014.

•

The Keystone XL Pipeline Project, 875 miles of 36-inch pipeline and

associated facilities linking Hardisty, Alberta, to Steele City, NE. This segment

also includes the Bakken Marketlink in Baker, MT—a pipeline lateral that can

transport crude oil from the Williston Basin to Steele City (further discussed

below).

In the 2008 Presidential Permit application, the “Keystone XL Project” referred to both pipeline

segments. For the 2012 Presidential Permit application, the “Keystone XL Project” refers to only

the northern, cross-border pipeline segment.

The existing Keystone Pipeline has the capacity to deliver up to 590,000 bpd of Canadian crude

oil to U.S. refineries and export terminals. Both the Keystone XL and Gulf Coast pipelines would

have a capacity of 830,000 bpd. As a result, the entire Keystone Pipeline System may ultimately

have the capacity to deliver up to 1.3 million bpd of crude oil. The existing Keystone Pipeline and

proposed expansions are illustrated in Figure 1. The proposed Keystone XL Project and

associated pipeline segments are illustrated in Figure 2.

Congressional Research Service

2

Keystone XL Pipeline Project: Key Issues

Figure 1. Existing Keystone Pipeline and Proposed Keystone Expansions

Source: U.S. State Department, March 2013, Draft EIS for the Keystone XL Project,

Section 1.2 “Overview of Proposed Project,” p. 1.2-5.

TransCanada has estimated the capital cost of the U.S. portion of the 2012 Keystone XL Project,

from the U.S. border to Steele City, NE, would be $5.3 billion.3 This figure is higher than the cost

estimate when the 2008 permit application was filed, reportedly due to currency swings, changing

regulatory requirements, and permitting delays.4

3

TransCanada Keystone Pipeline, L.P., “Application of TransCanada Keystone Pipeline L.P. for a Presidential Permit

Authorizing the Construction, Operation, and Maintenance of Pipeline Facilities for the Importation of Crude Oil to be

Located at the United States-Canada Border,” submitted to the U.S. Department of State, May 4, 2012, p. 39, available

at http://keystonepipeline-xl.state.gov/proj_docs/permitapplication/index.htm.

4

“TransCanada Expects $1-Billion Cost Escalation for Keystone XL Pipeline,” Canadian Press, February 17, 2011.

Congressional Research Service

3

Keystone XL Pipeline Project: Key Issues

Figure 2. The Keystone XL Project and Gulf Coast Pipeline

Source: U.S. State Department, March 2013, Draft EIS for the Keystone XL

Project. Section 1.2 “Overview of Proposed Project,” p. 1.2-3.

Marketlink for Bakken Oil Production

The Bakken Formation is a large unconventional petroleum and natural gas resource underlying

parts of North Dakota, Montana, and the Canadian provinces of Saskatchewan and Manitoba.

Although the region has been producing since 1951, it is only since 2006 that prices and

technology have made it economic for industry to increase production. In March 2012, Bakken

production exceeded 500,000 bpd the first time.5 However, production has been increasing

steadily, with average daily output in August 2013 exceeding 900,000 bpd.6 To date,

infrastructure to transport oil produced from the Bakken Formation has not kept up with the

5

North Dakota Department of Mineral Resources, “North Dakota Monthly Oil Production Statistics,” Bismarck, ND,

November 2013, https://www.dmr.nd.gov/oilgas/stats/historicaloilprodstats.pdf.

6

Ibid.

Congressional Research Service

4

Keystone XL Pipeline Project: Key Issues

increased production. Bakken crude oil is transported to refineries by rail and truck, in addition to

more economical transport by pipeline.7

As stated earlier, the proposed Keystone XL Project would include a lateral pipeline, the Bakken

Marketlink, to provide crude oil transportation service from Baker, MT, to Cushing, OK, via the

proposed Keystone XL Pipeline and from Cushing to Texas via the proposed Gulf Coast

Pipeline.8 Keystone Marketlink9 estimates that the project will cost $140 million and have the

ability to deliver approximately 100,000 bpd of crude oil to the proposed Keystone XL Pipeline.10

Thus, of the Keystone Pipeline’s 830,000 bpd ultimate capacity, up to 12% has been set aside to

transport Bakken crude oil. Keystone Marketlink currently has firm, long-term contracts to

transport 65,000 bpd of the 100,000 bpd.11

The Bakken contracts improve the economics for Keystone XL Pipeline, raising the amount of oil

slated to flow through the pipeline.12 Lower transportation costs and access to new markets may

support further investment in the Bakken. However, TransCanada is not the only company adding

pipeline capacity in the region. Notably, Enbridge, another Canadian pipeline company, has

proposed the Bakken Pipeline Project, which would add 120,000 bpd of transport capacity to

move Bakken oil to Midwest markets.13 According to Enbridge, sufficient pipeline capacity has

been slow to emerge in the region because “they’re smaller players in the Bakken. They are not

able to make the 20-year commitments and it’s been a lot of work to get them to commit to the

level that [is] required to underwrite a major project out of the Bakken.”14 Rail transport capacity

has also been expanding.15

Presidential Permit Applications

Federal agencies ordinarily have no authority to site oil pipelines, even interstate pipelines.16 The

primary siting authority for oil pipelines generally would be established under applicable state

law. However, the construction, connection, operation, and maintenance of a pipeline that

connects the United States with a foreign country requires executive permission conveyed

through a Presidential Permit.

7

For more analysis, see CRS Report R42032, The Bakken Formation: Leading Unconventional Oil Development, by

Michael Ratner et al.

8

The Bakken Marketlink project is described in the August 2011 final EIS for the 2008 Presidential Permit application

in Section 2.5.3, available at http://keystonepipeline-xl.state.gov/documents/organization/182012.pdf.

9

Keystone Marketlink, LLC, is a wholly owned subsidiary of TransCanada Pipelines Limited.

10

2012 Application of TransCanada Keystone Pipeline, L.P. for a Presidential Permit (footnote 3), p. 16.

11

Ibid.

12

Vanderklippe, 2011.

13

Enbridge, “Bakken Pipeline Project—Project Overview,” press release, http://www.enbridge.com/

BakkenPipelineProjects/BakkenPipelineProjectUS.aspx.

14

Lauren Krugel, “TransCanada attracts support for Montana-to-Oklahoma crude pipeline,” The Canadian Press,

January 20, 2011.

15

Energy Information Administration, “Rail Delivery of U.S. Oil and Petroleum Products Continues to Increase, but

Pace Slows,” July 10, 2013, http://www.eia.gov/todayinenergy/detail.cfm?id=12031.

16

This is in contrast to interstate natural gas pipelines, which, under Section 7(c) (15 USC §717f(c)) of the Natural Gas

Act, must obtain a “certificate of public convenience and necessity” from the Federal Energy Regulatory Commission.

Congressional Research Service

5

Keystone XL Pipeline Project: Key Issues

Executive Order 13337 delegates to the Secretary the President’s authority to receive applications

for Presidential Permits.17 Issuance of a Presidential Permit depends on a State Department

determination that the project would serve the “national interest.” The term is not defined in the

Executive Orders or elsewhere. Regarding its interpretation of the term, the State Department has

asserted that, consistent with the President’s broad discretion in the conduct of foreign affairs, it

has significant discretion in deciding the factors it will examine in making a national interest

determination.18 The State Department will not necessarily evaluate the same factors for each

project seeking a permit. However, for the 2008 Keystone XL Project, the State Department

identified the following as key factors it considered when making determinations for previous

applications for pipeline permits:

•

Environmental impacts of the proposed projects;

•

Impacts of the proposed projects on the diversity of supply to meet U.S. crude oil

demand and energy needs;

•

The security of transport pathways for crude oil supplies to the United States

through import facilities constructed at the border relative to other modes of

transport;

•

Stability of trading partners from whom the United States obtains crude oil;

•

Relationship between the United States and various foreign suppliers of crude oil

and the ability of the United States to work with those countries to meet overall

environmental and energy security goals;

•

Impact of proposed projects on broader foreign policy objectives, including a

comprehensive strategy to address climate change;

•

Economic benefits to the United States of constructing and operating proposed

projects; and

•

Relationships between proposed projects and goals to reduce reliance on fossil

fuels and to increase use of alternative and renewable energy sources.19

The State Department identifies and considers environmental impacts of a project within the

context of its obligation to comply with the National Environmental Policy Act (NEPA).20 NEPA

requires federal agencies to consider the environmental impacts of an action (e.g., granting or

denying a Presidential Permit) before proceeding with them and to inform the public of those

potential impacts.

17

See Executive Order 13337, “Issuance of Permits With Respect to Certain Energy-Related Facilities and Land

Transportation Crossings on the International Boundaries of the United States,” 69 Federal Register 25299, May 5,

2004, as amended, and Department of State Delegation of Authority No. 118-2 of January 26, 2006. The source of

Permitting Authority for relevant Executive Orders is discussed further in the 0.

18

U.S. Department of State, “Final Environmental Impact Statement for the Proposed Keystone XL Project,” August

2011, p. 1-4.

19

Ibid. It was noted that this list is not exhaustive and that the State Department may consider additional factors in its

national interest determination process.

20

In processing Presidential Permit applications, the State Department is also explicitly directed to review the project’s

compliance with the National Historic Preservation Act (16 U.S.C. §470f), the Endangered Species Act (16 U.S.C.

§1531 et seq.), and Executive Order 12898 of February 11, 1994 (59 Federal Register 7629), concerning environmental

justice.

Congressional Research Service

6

Keystone XL Pipeline Project: Key Issues

The State Department has discretion in determining what additional factors it will examine to

inform its national interest determination and, ultimately, whether a proposed project is in the

national interest. However, the State Department is required to consult with and seek the views of

the Secretaries of Defense, the Interior, Commerce, Transportation, Energy, and Homeland

Security; the Attorney General; and the Administrator of the Environmental Protection Agency.

The department is also required to solicit input from affected local, tribal, and state agencies and

to invite public comment in arriving at its determination.

Consideration of Environmental Impacts Under NEPA

To ensure that environmental impacts are considered before final agency decisions are made, an

Environmental Impact Statement (EIS) must be prepared for every major federal action that may

have a “significant” impact upon the environment.21 With respect to the Presidential Permit

applications submitted by TransCanada for Keystone XL, the State Department concluded that

approval of a permit requires the preparation of an EIS.22

Preparing an EIS is the responsibility of a designated “lead agency,” in this case, the State

Department. In developing an EIS for a private party applicant (TransCanada) the State

Department may use a third-party contractor. Consistent with regulations implementing NEPA,

such a contractor is one that is selected by and works under the direction of the State Department,

but is being paid by the applicant.23

An EIS is generally prepared in two stages resulting in a draft and final EIS. Among other

requirements, an EIS must include a statement of the purpose and need for an action, a

description of all reasonable alternatives to meet that purpose and need, a description of the

environment to be affected by those alternatives, and an analysis of the direct and indirect effects

of the alternatives, including cumulative impacts.24 Accordingly, the State Department EIS must

demonstrate that it has identified and considered potential environmental impacts of the entire

pipeline project (including the construction, operation, and maintenance of the pipeline and its

associated facilities), not just the facilities at the border crossing.

For the 2008 Presidential Permit application, the State Department prepared a draft, supplemental

draft, and final EIS. If the State Department modified its final EIS for the 2008 Presidential

Permit application and continued its national interest determination, as it originally proposed in

November 2011, it could have completed the NEPA process with only the publication of a

supplemental final EIS that included analysis of new routes through Nebraska. However, denial

of the Presidential Permit ended the NEPA process for the 2008 project. With the new Presidential

21

42 U.S.C. §4332(2)(C).

U.S. Department of State, “Notice of Intent to Prepare a Supplemental Environmental Impact Statement (SEIS) and

To Conduct Scoping and To Initiate Consultation Under Section 106 of the National Historic Preservation Act for the

Proposed TransCanada Keystone XL Pipeline Proposed To Extend From Phillips, MT (the Border Crossing) to Steele

City, NE,” 77 Federal Register 36032, June 15, 2012.

23

U.S. Department of State, “Interim Guidance for the Use of Third-Party Contractors in Preparation of Environmental

Documents by the Department of State,” available online at http://www.state.gov/documents/organization/190304.pdf.

24

In preparing an EIS associated with a Presidential Permit, NEPA regulations promulgated by both the Council of

Environmental Quality (CEQ) and the State Department would apply. CEQ regulations implementing NEPA (under 40

C.F.R. §§1500-1508) apply to all federal agencies. NEPA regulations applicable to State Department actions, which

supplement the CEQ regulations, are found at 22 C.F.R. Part 161.

22

Congressional Research Service

7

Keystone XL Pipeline Project: Key Issues

Permit application, the State Department was required to begin a new NEPA process and,

eventually, determine whether that project would serve the national interest.

To prepare an EIS, the State Department is required to obtain input from “cooperating agencies,”

which include any agency with jurisdiction by law or with special expertise regarding any

environmental impact associated with the project.25 Cooperating agencies for the Keystone XL

Project include the U.S. Environmental Protection Agency (EPA); the Department of

Transportation’s Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of

Pipeline Safety (OPS); the Department of the Interior’s Bureau of Land Management, U.S. Fish

and Wildlife Service, and National Park Service; the U.S. Army Corps of Engineers; the U.S.

Department of Agriculture’s Farm Service Agency, Natural Resources Conservation Service, and

Rural Utilities Service; the Department of Energy’s Western Area Power Administration; and state

environmental agencies.

On March 1, 2013, the State Department released the draft EIS for the 2012-proposed Keystone

XL Project as a supplement to the final EIS prepared for the 2008 Presidential Permit application

(released in August 2011).26 The draft EIS evaluates potential impacts associated with the route

from Montana to Steele City, NE, that avoids the Nebraska Sand Hills and excludes the proposed

Gulf Coast Project. According to the State Department, the 2013 draft EIS includes a

“comprehensive review of the new route in Nebraska as well as any significant new

circumstances or information that is now available on the largely unchanged route in Montana

and South Dakota. It also expands and updates information that had been included in the 2011

Final Environmental Impact Statement that was prepared for the previous Keystone XL

application.”27

EPA Rating of the Environmental Impact Statement

In addition to its role as a cooperating agency, EPA is also required to review and comment

publicly on the EIS and rate both the adequacy of the EIS itself and the level of environmental

impact of the proposed project.28 Rating the EIS takes place after the draft is issued. The EIS

could be rated either “Adequate,” “Insufficient Information,” or “Inadequate.” EPA’s rating of a

project’s environmental impacts may range from “Lack of Objections” to “Environmentally

Unsatisfactory.” In rating the impact of the action itself, EPA would specify one of the following:

“Lack of Objections,” “Environmental Concerns,” “Environmental Objections,” or

25

40 C.F.R. §1508.5. Also, Executive Order 13337 directs the Secretary to refer an application for a Presidential Permit

to other specifically identified federal departments and agencies on whether granting the application would be in the

national interest.

26

See U.S. Department of State, “New Keystone XL Pipeline Application” webpage at http://www.keystonepipelinexl.state.gov/. On March 8, 2013, EPA listed the draft EIS in its weekly “Environmental Impacts Statements; Notice of

Availability,” in the Federal Register, see 78 Federal Register 15012. The State Department refers to the EIS released

in March 2013 as a “Draft Supplemental” EIS. This reference apparently reflects the fact that the 2013 draft EIS draws

largely from (or supplements) documentation and analysis included in the final EIS issued for the Keystone XL Project

in 2011. However, for purposes of NEPA compliance, the submission of a new permit application in May 2012 started

the NEPA process anew. While it may draw from the 2011 final EIS, the 2013 draft EIS is a new NEPA document—

not a supplement to an EIS prepared for a different, albeit similar, Presidential Permit application.

27

See footnote 26.

28

For more information, see the U.S. Environmental Protection Agency’s “Environmental Impact Statement (EIS)

Rating System Criteria” at http://www.epa.gov/compliance/nepa/comments/ratings.html.

Congressional Research Service

8

Keystone XL Pipeline Project: Key Issues

“Environmentally Unsatisfactory.” The federal agency, in this case the Department of State,

would then be required to respond to EPA’s rating, as appropriate.

The State Department accepted public comments on the draft EIS until April 22, 2013. “Public”

comments could come from a range of interested stakeholders, including local, state, tribal, or

federal agencies. EPA reviewed the draft EIS and submitted comments on it to the State

Department.29 EPA’s comments are on its assessment of the proposed project’s impacts and the

adequacy of the draft EIS itself. It rated the draft EIS as “EO-2” (Environmental Objections—

Inadequate Information). EPA states that, while the agency believes the draft EIS strengthens the

analysis presented to date in the NEPA process, it recommends several improvements to the

analysis of the proposed project’s impacts and to mitigate certain impacts. Specifically, EPA

recommended the following:

•

Greenhouse Gas Emissions—use monetized estimates of the social cost of the

greenhouse gas (GHG) emissions from a barrel of oil sands crude compared to

average U.S. crude. EPA noted that TransCanada’s market analysis and its

conclusion that oil sands crude will find a way to market with or without the

Project are central to the draft EIS conclusions regarding the Project’s potential

GHG emissions. As a result, the agency asserts that the final EIS should be based

on an updated energy-economic modeling effort. The final EIS should also

explore specific ways the United States might work with Canada to promote

efforts to reduce GHG emissions from oil sands crude production.

•

Pipeline Safety—in the wake of a 2010 Enbridge spill of oil sands crude in

Michigan, incorporate into its permit conditions various steps intended to

improve potential oil spill response and cleanup.

•

Pipeline Routes Across the Ogallala Aquifer—provide in the final EIS more

detail on pipeline route alternatives that would parallel the existing Keystone

Pipeline, and likely further reduce potential environmental impacts to

groundwater resources, or explain why these alternatives were not considered.

•

Community and Environmental Justice Impacts—document in its permit

conditions TransCanada’s commitments to conduct cleanup and restoration and

to provide alternative water supplies to affected communities in the event of an

oil discharge affecting surface waters or groundwater.

Now that EPA and other public and agency comments have been submitted, the State Department

must respond to those comments and possibly modify the draft EIS to address them. After it does

so, the State Department may issue a final EIS. The time it may take the department to do so will

depend on various factors, including the scope and the nature of the comments to which it must

respond. After the final EIS is issued, the State Department may begin the 90-day period to make

the national interest determination.

Major milestones in the NEPA process, for both the 2008 and 2012 Presidential Permit

applications, are listed in Table 1, below. (For discussion of NEPA milestones associated with the

2008 permit application, see Appendix B.)

29

Letter from the U.S. Environmental Protection Agency’s Cynthia Giles, Assistant Administrator for Enforcement and

Compliance Assurance to Jose Fernandez and Kerri-Ann Jones, Assistant Secretaries, U.S. Department of State,

available online at http://epa.gov/compliance/nepa/keystone-xl-project-epa-comment-letter-20130056.pdf.

Congressional Research Service

9

Keystone XL Pipeline Project: Key Issues

Table 1. Milestones in the NEPA process for the Keystone XL Project

Federal, State, and Company Actions Relevant to the NEPA Compliance Process

Date

Party

Description

NEPA Compliance Milestones Relevant to TransCanada’s 2008 Presidential Permit Application

Sept.

2008

TransCanada

Application for a Presidential Permit submitted to the State Department to

authorize the Keystone XL Pipeline Project.

Apr. 16,

2010

State

Department

Draft EIS for the proposed Keystone XL Pipeline project released for public

comment.

July 16,

2010

EPA

Agency rates the draft EIS as “Inadequate,” noting that potentially significant

impacts were not evaluated, that more information and analysis was needed, and

the draft EIS would need revision and again be made available for public review.

Apr. 15,

2011

State

Department

Supplemental draft EIS issued.

June 6,

2011

EPA

Agency rates the supplemental draft EIS as having “Insufficient Information” and

the action as having “Environmental Objections”; recommends additional

analysis on a range of issues to be addressed in the final EIS.

Aug. 26,

2011

State

Department

Final EIS issued; 90-day public comment related to the national interest

determination process begins.

Nov. 22,

2011

Governor of

Nebraska

Signed legislation passed during special session directing the Nebraska

Department of Environmental Quality (DEQ) to collaborate with the State

Department to gather information necessary for a supplemental EIS.

Nov.

2011

Nebraska

DEQ/State

Department

Agencies begin to negotiate a Memorandum of Understanding (MOU) regarding

their collaboration on the supplemental final EIS. Nebraska DEQ hires a

contractor to delineate the “Sand Hills” region alternative routes must avoid.

Dec. 23,

2011

Congress

The Temporary Payroll Tax Cut Continuation Act of 2011 (P.L. 112-78)

requires the Secretary to issue a permit for the project within 60 days, unless

the President determines the project is not in the national interest.

Jan. 18,

2012

State

Department

Department denies the Presidential Permit for Keystone XL asserting that the

60-day deadline under P.L. 112-78 did not provide sufficient time to obtain

information necessary to assess the project’s national interest.

Feb. 3,

2012

State

Department

Formal permit denial issued; State Department and Nebraska DEQ suspend

work on MOU regarding a supplemental EIS.

Feb.

2012

TransCanada

State Department is informed of the company’s intent to continue with the Gulf

Coast Project (a pipeline that would not require an EIS if constructed apart from

the lager project that requires authorization via a Presidential Permit).

April 19,

2012

TransCanada

Submits to Nebraska DEQ, Initial Report Identifying Alternative and Preferred

Corridors for Nebraska Reroute; public meetings on newly proposed routes follow.

NEPA Compliance Milestones Relevant to TransCanada’s 2013 Presidential Permit Application

May 4,

2012

TransCanada

Application for a Presidential Permit submitted to the State Department to

authorize the reconfigured Keystone XL Pipeline Project with a Nebraska route.

June, 15,

2012

State

Department

Publishes in the Federal Register: “Notice of Intent To Prepare a Supplemental

Environmental Impact Statement (SEIS) and To Conduct Scoping and To Initiate

Consultation Under Section 106 of the National Historic Preservation Act for

the Proposed TransCanada Keystone XL Pipeline Proposed To Extend From

Phillips, MT (the Border Crossing) to Steele City, NE.”

March 1,

2013

State

Department

Releases draft EIS for the 2012 Keystone XL Project for public comment.

Congressional Research Service

10

Keystone XL Pipeline Project: Key Issues

Date

Party

Description

April 22,

2013

State

Department

Deadline for submission of public comments on the draft EIS.

April 23,

2012

EPA

The proposed project and draft EIS is rated “EO-2,” meaning EPA has

“Environmental Objections,” regarding the project’s impacts, and that the draft

EIS includes “Insufficient Information”; recommends mitigation efforts to address

project impacts and additional analysis that should be included in the final EIS.

Source: Congressional Research Service, based on a review of events during, and affecting, the NEPA process

conducted for the 2008 and 2012 Presidential permit applications for the Keystone XL Project.

The National Interest Determination

Generally, after a final EIS is issued, a federal agency may issue a final record of decision (ROD)

for the project. However, for a Presidential Permit, issuance of the final EIS represents the

beginning of a 90-day public review period during which the State Department gathers

information from those necessary to inform its national interest determination. Ultimately, a

decision regarding issuance of a Presidential Permit for a pipeline project would be reflected in a

combined “Record of Decision and National Interest Determination,” issued by the State

Department.30 That document, required under elements of both NEPA and E.O. 11424, formalizes

the selection of a project alternative.

During the 90-day public review period for the 2008 Presidential Permit application, the State

Department held public meetings in each of the six states through which the proposed pipeline

would pass and in Washington, DC.31 The meetings were intended to give members of the public

additional opportunity to voice their opinions on issues they thought should be taken into account

in determining whether granting or denying the Presidential Permit would be in the national

interest. During the review period, the State Department received input from state, local, and

tribal officials as well as members of the public.

On November 10, 2011, during the public review period for the 2008 permit application, the State

Department stated that it received public comments on a wide range of issues including the

project’s potential impact on jobs, pipeline safety, health concerns, the societal impact of the

project, and oil extraction in Canada.32 Concern regarding the proposed pipeline route through the

Sand Hills area of Nebraska was identified as one of the most common issues raised. Comments

regarding that pipeline route were consistent with the environmental impacts identified in the

final EIS with regard to the unique combination of characteristics of the Sand Hills region (e.g., a

high concentration of wetlands of special concern, a sensitive ecosystem, and extensive areas of

very shallow groundwater). Further, the Nebraska legislature convened a special session to

consider the legislation that would establish regulations applicable to pipeline siting within the

state.

30

For example, see U.S. Department of State, “Record of Decision and National Interest Determination, TransCanada

Keystone Pipeline, LP Application for Presidential Permit,” February 25, 2008, http://www.cardnoentrix.com/keystone/

project/SignedROD.pdf.

31

U.S. Department of State press release, “Keystone XL Final Environmental Impact Statement Released; Public

Meetings Set,” August 26, 2011, http://www.state.gov/r/pa/prs/ps/2011/08/171082.htm.

32

U.S. Department of State, “Keystone XL Pipeline Project Review Process: Decision to Seek Additional

Information,” Media Note, PRN 2011/1909, Office of the Spokesperson, November 10, 2011.

Congressional Research Service

11

Keystone XL Pipeline Project: Key Issues

Facing the prospect of new state pipeline siting regulations applicable to the Sand Hills, together

with the concern about the Keystone XL pipeline’s specific “preferred” route, the State

Department announced that it needed additional information about alternative pipeline routes

avoiding the environmentally sensitive Sand Hills area in Nebraska before moving forward with

its national interest determination.33 Although the State Department did not decide that

environmental issues led to a determination that the proposed project was not in the national

interest, environmental issues identified in the final EIS, and further stressed in public comments,

led to its decision to delay that determination until it gathered this information. In a concurrent

press release, President Obama stated

Because this permit decision could affect the health and safety of the American people as

well as the environment, and because a number of concerns have been raised through a

public process, we should take the time to ensure that all questions are properly addressed

and all the potential impacts are properly understood.34

Subsequently, TransCanada announced that it would work with the State Department and the

Nebraska Department of Environmental Quality (DEQ) to conduct an environmental assessment

to define the best location for the Keystone XL pipeline in Nebraska. Further, the company stated

that it would “cooperate with these agencies and provide them with the information they need to

complete a thorough review that addresses concerns regarding the Sandhills region.”35

As noted previously, on December 23, 2011, the Temporary Payroll Tax Cut Continuation Act of

2011 was enacted (P.L. 112-78). Under Section 501, “Permit for Keystone XL Pipeline,” the

Secretary was required to grant the Presidential Permit for the Keystone XL pipeline project

within 60 days, unless the President determined that the pipeline would not be in the national

interest. On January 18, 2012, the State Department announced, with the President’s concurrence,

that the Presidential Permit for the proposed Keystone XL Pipeline would be denied at that time

because it was determined not to serve the national interest. That recommendation “was

predicated on the fact that the Department does not have sufficient time to obtain the information

necessary to assess whether the project, in its current state, is in the national interest.”36

The process of determining a project’s national interest illustrates the distinctly different, yet

interrelated requirements applicable to the NEPA process and the Presidential Permit application

process. Under NEPA, the State Department (or any other federal agency considering an action)

must fully assess the environmental consequences of an action and potential project alternatives

before making a final decision. NEPA does not prohibit a federal action that has adverse

environment impacts; it requires only that a federal agency be fully aware of and consider those

adverse impacts before selecting a final project alternative. That is, NEPA is intended to be part of

the decision-making process, not dictate a particular outcome. By contrast, issuance of a

Presidential Permit is predicated on the Secretary’s finding that the proposed project would serve

the national interest. Milestones in the State Department’s process to make its national interest

determination for the 2008 permit application are summarized in Table 2.

33

Ibid.

The White House, Office of the Press Secretary, “Statement by the President on the State Department’s Keystone XL

Pipeline Announcement,” November 10, 2011.

35

See TransCanada Corp., Media Advisory, “State of Nebraska to Play Major Role in Defining New Keystone XL

Route Away From the Sandhills,” November 14, 2011, available at http://www.transcanada.com/5896.html.

36

U.S. Department of State, Media Note, “Denial of the Keystone XL Pipeline Application,” January 18, 2012,

available at http://www.state.gov/r/pa/prs/ps/2012/01/181473.htm.

34

Congressional Research Service

12

Keystone XL Pipeline Project: Key Issues

Table 2. Milestones in National Interest Determination Process for the 2008

Keystone XL Pipeline

Date

Party

Description

Aug.Oct.

2011

State

Department

The 90-day public review period for national interest determination begins;

State Department holds public meetings in the six states through which the

proposed pipeline would pass and in Washington, DC.

Oct.

2011

Congress

Fourteen Members of Congress request the State Department Office of

Inspector General (IG) to investigate the department’s handling of the EIS and

national interest determination for the Keystone XL project.

Oct. 24,

2011

Governor of

Nebraska

The governor calls the Nebraska legislature into a special session to determine if

siting legislation can be crafted and passed for pipeline routing in Nebraska.

Nov. 4,

2011

State

Department

IG announces it is initiating a special review to determine to what extent the

department and all other parties involved complied with Federal laws and

regulations relating to the Keystone XL pipeline permit process.

Nov. 10,

2011

State

Department

The agency announces that additional information will be needed regarding

alternative pipeline routes that would avoid the Nebraska Sand Hills before

national interest determination can be made. Officials suggest that analysis

needed to prepare the supplemental EIS, including additional public comment,

could be completed as early as the first quarter of 2013.

Nov. 14,

2011

TransCanada

The company announces that it will work with the Nebraska Department of

Environmental Quality (DEQ) to identify a potential pipeline route that would

avoid the Nebraska Sand Hills.

Nov. 22,

2011

Governor of

Nebraska

The governor signs legislation passed during the special session directing the

Nebraska DEQ to work collaboratively with the State Department to gather

information necessary for a supplemental EIS.

Nov.

2011

Nebraska

DEQ/State

Department

The agencies begin negotiating a Memorandum of Understanding (MOU) to

collaborate on the supplemental EIS. Nebraska DEQ hires a contractor to

delineate the “Sand Hills” region that alternative routes must avoid.

Dec. 23,

2011

Congress

The Temporary Payroll Tax Cut Continuation Act of 2011 (P.L. 112-78)

requires the Secretary to issue a permit for the project within 60 days, unless

the President determines the project is not in the national interest.

Jan. 18,

2012

State

Department

The agency announces that it will deny the Keystone XL permit.

Source: Congressional Research Service, based on a review of events during, and affecting, the State Department’s

national interest determination for the 2008 Presidential Permit application for the Keystone XL pipeline project.

State Siting and Additional Environmental Requirements

As the NEPA compliance process for TransCanada’s permit application moves forward, it is

helpful to understand the distinction between what is required under NEPA itself and what may be

required pursuant to other environmental requirements identified within the context of the NEPA

process. NEPA itself requires federal agencies to identify the environmental impacts of an action

before proceeding with them and to involve the public in that process when environmental

impacts are significant. In the process of identifying a proposed project’s environmental impacts,

within the context of preparing the EIS, the lead agency should identify any compliance

obligations (licenses, permits, or approvals) established under additional state, tribal, and federal

law applicable to the portion of the project constructed in the United States.

Congressional Research Service

13

Keystone XL Pipeline Project: Key Issues

As noted above, the federal government does not currently exercise siting authority over oil

pipelines. Instead, pipeline siting for the Keystone XL Project must comply with any applicable

state law—which can vary from state to state. South Dakota, for example, required TransCanada

to apply for a permit for the Keystone XL Project from the state public utility commission, which

issued the permit on April 25, 2010.37 Montana requires a certificate from the state’s Department

of Environmental Quality.38

At the time of TransCanada’s initial application for a Presidential Permit, Nebraska did not have

any permitting requirements that applied specifically to the construction and operation of oil

pipelines, although a state statute did include an “eminent domain” provision to grant eminent

domain authority to oil pipeline companies unable to obtain the necessary property rights from

the relevant property owners.39 However, due to the controversy surrounding the Keystone XL

Project, Nebraska’s governor called a special session of its legislature to enact legislation to assert

state authority over pipeline siting. Subsequently, the state enacted two laws—one that would

affect the siting of the Keystone XL pipeline and one that outlines procedures for siting any future

oil pipeline in Nebraska.40 The latter requires an oil pipeline carrier proposing to construct a

major oil pipeline in Nebraska to file an application with the state’s Public Service Commission

and receive approval before beginning construction. Additionally, the law authorized the

commission to follow certain procedures before deciding whether a proposed oil pipeline would

serve the public interest.

Although there are limited federal requirements applicable to oil pipeline siting, there are

numerous local, state, tribal, and federal requirements applicable to pipeline construction,

operation, and maintenance. For example, the 2013 draft EIS for the Keystone XL Project lists

major permits, licenses, approvals, and consultation requirements for the proposed project that

would be required by federal, state, and local agencies prior to implementation of the project.41

Following are selected requirements included on that list:

•

The U.S. Army Corps of Engineers—issuance of a permit for sections of the

project that require placement of dredge and fill material in waters of the United

States, including wetlands (pursuant to Section 404 of the Clean Water Act), or

for pipeline crossings of navigable waters (pursuant to Section 10 of the Rivers

and Harbors Act);

•

The Environmental Protection Agency—review and issue National Pollutant

Discharge Elimination System permits for the discharge of pollutants in state

waters (pursuant to Section 402 of the Clean Water Act);

•

The Bureau of Land Management—grant temporary use permits for portions of

the project that would encroach on federal lands;

37

South Dakota Public Utilities Commission, Final Decision and Order; Notice of Entry Before the Public Utilities

Commission of the State of South Dakota, In the Matter of the Application by TransCanada Keystone Pipeline, LP for

a Permit Under the South Dakota Energy Conversion and Transmission Facilities Act to Construct the Keystone

Pipeline Project, HP07-001, http://puc.sd.gov/commission/orders/HydrocarbonPipeline/2008/hp07-001.pdf.

38

Montana Major Facility Siting Act, Title 75, Chapter 20.

39

Nebraska Rev. Stat. §57-1101.

40

See Nebraska governor Dave Heineman’s November 23, 2011, statement “Common Sense Solution,” available at

http://www.governor.nebraska.gov/columns/2011/11/23_solution.html.

41

U.S. Department of State, March 2013, Draft EIS, Section 1.9, “Permits, Approvals, and Regulatory Requirements.”

Congressional Research Service

14

Keystone XL Pipeline Project: Key Issues

•

U.S. Fish and Wildlife Service—consider impacts to federally listed endangered

species (pursuant to the Endangered Species Act) and provide a Biological

Opinion if the project is likely to adversely affect federally listed species.

•

Multiple state/county agencies—consult on and/or consider issuance of permits

for projects that cross navigable waters or state highways, or involve work

potentially affecting state streams, cultural resources, or natural resources.

The time it took to complete the NEPA process was a focus of attention for the 2008 Presidential

Permit application. However, for past pipeline projects, obtaining all required local, state, tribal,

and federal permits, approvals, and licenses took a similar amount of time. By way of example,

for the Alberta Clipper pipeline project (another oil sands pipeline) completion of the NEPA

process, the national interest determination, and issuance of a Presidential Permit took

approximately two years. Obtaining the necessary permits, approvals, and licenses for

construction of the pipeline took an additional two years.

Legislative Efforts to Change Permitting Authority

In light of the State Department’s denial of the 2008 permit application for the Keystone XL

Project, some in Congress have sought alternative means to support development of the pipeline.

There were a number of legislative proposals in the 112th Congress to change the federal

permitting authority for the pipeline. H.R. 3548 would have transferred the permitting authority

over the Keystone XL Project from the State Department to the Federal Energy Regulatory

Commission (FERC), requiring the commission to issue a permit for the project within 30 days of

enactment.42 Other proposals, such as H.R. 3811 and S. 3445, would have directly shifted

permitting authority to Congress, effectively approving upon enactment the permit applications

filed by TransCanada in 2008 and 2012, respectively.

Similar legislation has been proposed in the 113th Congress, including legislative proposals from

the prior Congress that have been reintroduced. The Energy Production and Project Delivery Act

of 2013 (S. 17) would eliminate the Presidential Permit requirement for the reconfigured

Keystone XL Project. The Keystone for a Secure Tomorrow Act (H.R. 334) and a Senate bill to

approve the Keystone XL Project (S. 582) would directly approve the Keystone XL Project under

the authority of Congress to regulate foreign commerce. The Northern Route Approval Act (H.R.

3) would eliminate the Presidential Permit requirement for Keystone XL and require issuance of

permits for water crossings by the Army Corps of Engineers within 90 days of an application,

among other provisions. The Senate passed an amendment to the Fiscal 2014 Senate Budget

Resolution (S.Con.Res. 8) that would provide for the approval and construction of the Keystone

XL Project (S.Amdt. 494). The North American Energy Infrastructure Act (H.R. 3301) would

transfer permit authority for oil pipelines from the State Department to the Department of

Commerce; would require agencies to approve applications within 120 days of submission unless

they determine the project is not in the national security interest (as opposed to “national interest”

more generally); and would eliminate the need for new or revised Presidential Permits for

pipeline modifications (e.g., reversal of flow direction), among other provisions.

42

The Surface Transportation Extension Act of 2012, Part II (H.R. 4348), which passed in the House on April 18,

2012, also contained these provisions, but they were subsequently dropped from the bill in conference committee with

the Senate.

Congressional Research Service

15

Keystone XL Pipeline Project: Key Issues

Changing, or eliminating altogether, the State Department’s role in issuing cross-border

infrastructure permits may raise questions about the President’s executive authority (further

discussed in Appendix A). In response to H.R. 3548, for example, the State Department’s key

official on Keystone XL testified before Congress:

The legislation raises serious questions about existing legal authorities, questions the

continuing force of much of the federal and all of the state and local environmental and land

use management authority over the pipeline, and overrides foreign policy and national

security considerations implicated by a cross border permit, which are properly assessed by

the State Department.43

Such proposals may also raise some administrative and legal challenges for FERC or other

federal agencies. A senior FERC official testified that a proposal like H.R. 3548 would not

provide enough time for an “adequate” public record, provides no clear authority for enforcing

measures required in the EIS, does not articulate a process for authorizing alterations to the

pipeline route, and is unclear about permits required from other federal agencies, among other

concerns.44 For additional analysis of associated legal issues, see CRS Report R42124, Proposed

Keystone XL Pipeline: Legal Issues, by Adam Vann, Kristina Alexander, and Kenneth R. Thomas;

and CRS Report R43261, Presidential Permits for Border Crossing Energy Facilities, by Adam

Vann and Paul W. Parfomak.

Given the State Department’s initial permit denial, and opposition from various environmental

groups and stakeholders along the pipeline route, legal challenges are a possibility. However, in

the event of a challenge based on an environmental issue, the distinction between State

Department actions required under NEPA and those required under its authority to issue a

Presidential Permit would be relevant. NEPA does not create a private right of action. Instead,

judicial challenges to a federal agency action under NEPA are brought pursuant to the

Administrative Procedure Act (APA, 5 U.S.C. §§706 et seq.). Presidential actions, however, are

not subject to judicial review under the APA.45 That is, the final agency action reflected in an

ROD is subject to judicial review, but the State Department’s national interest determination,

made under its authority to issue a Presidential Permit, is not. For more analysis of the State

Department’s authority to grant a Presidential Permit, see Appendix A.

Arguments For and Against the Pipeline

Proponents of the Keystone XL Pipeline, including Canadian agencies and U.S. and Canadian

petroleum industry stakeholders, base their arguments supporting the pipeline primarily on

increasing the security and diversity of the U.S. petroleum supply and economic benefits,

43

Kerri-Ann Jones, Assistant Secretary of State for Oceans and International Environmental and Scientific Affairs,

Testimony before the House Energy and Commerce Committee, Subcommittee on Energy and Power Hearing on the

North American Energy Access Act, January 25, 2012.

44

Jeff Wright, Director, Office of Energy Projects, Federal Energy Regulatory Commission, Testimony before the

House Energy and Commerce Committee, Subcommittee on Energy and Power Hearing on the North American Energy

Access Act, January 25, 2012.

45

While the APA’s definition of “agency” does not specifically exclude or include the president, the Supreme Court

has held that exercises of presidential authority are not subject to judicial review because the president is not an agency

(Dalton v. Specter, 511 U.S. 462, 470 (1994)). The Court has also held that the APA does not apply to the president

based on separation of powers principles (Franklin v. Massachusetts, 505 U.S. 788, 800-01 (1992)).

Congressional Research Service

16

Keystone XL Pipeline Project: Key Issues

especially jobs. Pipeline opponents are generally environmental organizations and community

groups. Their concerns stem from issues that can be broadly categorized as the pipeline’s global

or community environmental impacts. “Global” impacts stem primarily from concern regarding

the lifecycle greenhouse gas (GHG) emissions associated with the development of Canadian oil

sands, compared to conventional oil or renewable fuels.46 Although the concern regarding GHG

emissions is focused primarily on the extraction process, opponents also argue that use of the oil

sands crude promotes continued U.S. dependency on fossil fuels. Concern over adverse

community impacts of the pipeline stems primarily from the risk of a potential release of heavy

crude, and the operators’ ability to respond to a release, particularly in remote areas. Communities

along the pipeline route are also concerned about impacts associated with the pipeline’s

construction and long-term use on private land—particularly its potential to affect farming and

cattle grazing.

Impact on U.S. Energy Security

In its Presidential Permit application, TransCanada asserts that constructing the proposed

Keystone XL Pipeline is in the U.S. national interest to maintain adequate crude oil supplies for

U.S. refineries. The application argues that the pipeline will allow U.S. refiners to substitute

Canadian supply for other foreign crude supply and to obtain direct pipeline access to secure and

growing Canadian crude output. In particular, the application asserts that the pipeline would allow

the United States to decrease its dependence on crude oil from Mexico and Venezuela, the two

largest oil exporters into the U.S. Gulf Coast.47 Consistent with this argument, some proposals

would seek to ensure that any crude oil and bitumen transported by the Keystone XL Pipeline, or

any resulting refined products, would have to remain in U.S. markets subject to a presidential

waiver allowing foreign export.48 Depending upon the circumstances, however, such restrictions

could raise concerns with respect to international trade agreements, among other considerations.

Energy security arguments have taken on additional weight in light of the recent geopolitical

tensions in the Middle East and North Africa. However, it is worth noting that even if Keystone

XL is built, prices for the crude oil it carries as well as for domestically produced oil from

elsewhere will continue to be affected by international events. The oil market is globally

integrated and events in major producer and consumer countries can affect prices everywhere.49

For example, the disruption of Libyan supply in early 2011 contributed to higher crude oil prices

in the United States, even though the United States imported almost no oil from Libya before the

unrest broke out.50

46

For additional analysis of greenhouse gas issues associated with Canadian oil sands crudes, see CRS Report R42537,

Canadian Oil Sands: Life-Cycle Assessments of Greenhouse Gas Emissions, by Richard K. Lattanzio.

47

TransCanada Keystone Pipeline, L.P., September 19, 2008, pp. 6-8.

48

On February 7, 2012, the House Energy and Committee rejected an amendment to H.R. 3548 offered by

Representative Edward Markey containing export restrictions.

49

This is the case unless the oil is stranded due to transport bottlenecks. Ironically, the bottleneck for crude oil flowing

south from the Midwest to the Gulf Coast—which Keystone XL would help alleviate—helped insulate Midwestern

crude oil prices from the impacts of unrest in the Middle East and North Africa. However, as is discussed below, this

may have benefited Midwestern refiners but probably did not significantly reduce costs for U.S. consumers.

50

For more about this, see CRS Report R41683, Middle East and North Africa Unrest: Implications for Oil and

Natural Gas Markets, by Michael Ratner.

Congressional Research Service

17

Keystone XL Pipeline Project: Key Issues

Canadian Oil Imports in the Overall U.S. Supply Context51

Gross U.S. imports of crude oil and petroleum products averaged 10.6 million bpd (Mbpd) in

2012.52 U.S. oil exports averaged 3.2 Mbpd (almost entirely refined petroleum products), leaving

net imports at 7.4 Mbpd.53 U.S. net imports have fallen by 5.1 Mbpd or 41% since they peaked in

2005 as a result of lower total oil consumption and higher domestic production. Some of this

decline could be mitigated in the near term as oil demand recovers from the recession. However,

there is increasing sentiment among forecasters that U.S. oil imports have passed their high water

mark already and may remain relatively flat or fall in the foreseeable future.54

Among the largest sources of U.S. gross oil imports are Canada (2.9 Mbpd), the Persian Gulf (2.1

Mbpd), Mexico (1.0 Mbpd), and Venezuela (0.9 Mbpd). Imports from the latter two sources have

decreased in recent years in part due to lower need for imports described above and in part due to

developments in those countries. Mexican production has been falling since 2004 because new oil

developments have not been able to offset depletion at Mexico’s giant Cantarell field. Imports

from Venezuela, another key source of U.S. imports, have also fallen. Venezuelan production

never fully recovered after a strike at its national oil company, Petróleos de Venezuela, in 20022003. Venezuelan production today is nearly 1 Mbpd less than that achieved in 2001. In recent

years, Venezuela has also been trying to diversify business away from the United States, for

example, by increasing exports to China.55

Meanwhile, Canadian production and exports to the United States have increased, primarily due

to growing output from the oil sands in western Canada. Energy markets in the United States and

Canada are well integrated by pipeline infrastructure; nearly all Canadian energy exports go to the

United States.56 Canadian oil production has increased about 0.7 Mbpd since 2005 and exports to

the United States have increased by 0.77 Mbpd (see Table 3).57 Some expect Canadian oil

production to grow by nearly 2 Mbpd by 2025 due to increased output from the oil sands.58

51

For a primer on the oil market, see CRS Video Brief Introduction to the Oil Market, at http://www.crs.gov/analysis/

Pages/WVB00002.aspx.

52

All data in this section are from the U.S. Energy Information Administration’s (EIA’s) Petroleum & Other Liquids

(http://www.eia.gov/petroleum/data.cfm), International Energy Statistics (http://tonto.eia.doe.gov/cfapps/ipdbproject/

IEDIndex3.cfm), and the Short Term Energy Outlook (http://www.eia.gov/forecasts/steo/).

53

For context, the United States consumed 18.8 Mbpd in 2011, more than 20% of the world’s oil market. Net imports

are gross or total imports less total exports. This section will focus on gross imports, though it should be noted that

among U.S. petroleum exports about 0.2 Mbpd of petroleum products go to Canada and 0.4 Mbpd to Mexico.

54

For more analysis, see CRS Report R42465, U.S. Oil Imports and Exports, by Robert Pirog.

55

U.S. Energy Information Administration, “Country Analysis Brief: Venezuela,” February 2010,

http://www.eia.doe.gov/emeu/cabs/Venezuela/Oil.html.

56

For further analysis of U.S.-Canada energy trade, see CRS Report R41875, The U.S.-Canada Energy Relationship:

Joined at the Well, by Paul W. Parfomak and Michael Ratner.

57

As in the United States, Canadian consumption fell due to economic downturn. This allowed the increment in exports

to be higher than the increment in production.

58

Canadian Association of Petroleum Producers (CAPP), Crude Oil: Forecast, Markets, and Pipelines, June 2011, p.

2, http://www.capp.ca/forecast/Pages/default.aspx.

Congressional Research Service

18

Keystone XL Pipeline Project: Key Issues

Table 3. U.S. Oil Imports

(millions of barrels per day)

2005

2006

2007

2008

2009

2010

2011

2012

Canada

2.18

2.35

2.45

2.49

2.47

2.53

2.79

2.95

Mexico

1.66

1.70

1.53

1.30

1.21

1.28

1.20

1.03

Persian Gulf OPEC

2.33

2.21

2.16

2.37

1.68

1.71

1.86

2.15

Other OPEC

3.25

3.30

3.82

3.58

3.09

3.19

2.69

2.10

Rest of the World

4.29

4.14

3.50

3.17

3.24

3.08

2.96

2.36

Total

13.71

13.70

13.46

12.91

11.69

11.79

11.50

10.59

Source: Energy Information Administration, http://www.eia.doe.gov

Notes: Table 3 contains data for gross oil and petroleum product imports.

Oil Sands, Keystone XL, and the U.S. Oil Market

Oil sands (also referred to as tar sands) are a mixture of clay, sand, water, and heavy black

viscous oil known as bitumen. Oil sands require more processing than conventional crude oil. Oil

sands are processed to extract the bitumen, which can then be sent to refineries in one of two

forms. Bitumen can be upgraded into “syncrude,” a light crude that is suitable for pipeline

transport and is relatively easy to refine. Alternatively, bitumen can be blended with lighter

hydrocarbons to form a heavy crude (diluted bitumen or “dilbit”) that can be transported by

pipeline. The bulk of oil sands supply growth is expected to be in the form of the latter.59

Most oil sands imports into the United States currently go to the Midwest, where refineries have

been investing in complex refining capacity to process growing volumes of heavy Canadian

crude.60 The U.S. Gulf Coast region already has a large amount of complex refining capacity and

is well suited for processing Canadian heavy crude oil. Gulf Coast refiners currently process

heavy crudes from Venezuela, Mexico, and elsewhere. Complex refineries in the Gulf Coast may

be best equipped to handle a large increase of heavy oil sands crude, though some may still need

to adjust processes and make new capital investments in equipment to accommodate particular

crudes’ characteristics,61 especially if the new Canadian crudes will be used in large amounts.62

There are 58 refineries in the Gulf Coast region (potentially served by the proposed Gulf Coast

Project) that could process heavy crude oil similar in composition to the oil that Keystone XL

pipeline would carry from Alberta.63 Crudes from the U.S. Bakken formation are light crudes.

59

CAPP, 2011, p. 7.

CAPP, 2011, p. 13. According to CAPP, refineries adding capacity to process more heavy oil in the Midwest include

those in Roxana, IL; Whiting, IN, and Detroit, MI.

61

Baker Hughes, Planning Ahead for Effective Canadian Crude Processing, Baker Petrolite White Paper, 2010,

http://www.bakerhughes.com/assets/media/whitepapers/4c2a3c8ffa7e1c3c7400001d/file/28271canadian_crudeoil_update_whitepaper_06-10.pdf.pdf&fs=1497549.

62

For a description of which units refineries may need to add (or have added) to be able to process more Canadian oil

sands supply, see Praveen Gunaseelan and Christopher Buehler, “Changing US Crude Imports Are Driving Refinery

Upgrades,” Oil and Gas Journal, August 10, 2009.

63

TransCanada Keystone Pipeline, L.P., May 2012 Presidential Permit application submitted to the U.S. Department of

State (see footnote 3), p. 14.

60

Congressional Research Service

19

Keystone XL Pipeline Project: Key Issues

Oil production from the oil sands is increasing, as is production from the Bakken and other areas

of the U.S. Midwest.64 Transport options to carry crude from the Midwest to the Gulf Coast are

limited. (In the past, crude oil had been shipped up from the Gulf Coast to Midwestern refineries.)

The resulting abundance of crude oil in the Midwest has driven down crude oil prices in that

region relative to Gulf Coast and international crude markets. Midwestern refiners benefit from

the lower cost of crude, but it does not translate to substantially lower consumer prices for

gasoline or other products in the region. The Midwest still brings in refined products from the

Gulf Coast, which keeps refined products prices in line with national and international levels.65

Oil sands producers are interested in Keystone XL because it would expand their market reach

into the Gulf Coast. The Gulf Coast region holds half of U.S. refining capacity, including a

substantial amount of technologically advanced capacity capable of processing heavy sour crudes

in large volumes. Reaching a larger market and one with more advanced refining capacity could

increase the price these producers receive for their crude. For their part, Gulf Coast refiners are

interested in the Keystone XL pipeline because it increases the supply of heavy sour crude in the

Gulf Coast region, potentially bringing down their input costs relative to the options they

currently have available. Canadian Natural Resources Limited, an oil sands producer, and Valero

Energy Corporation, a large U.S. refiner, are among those that contracted for shipping capacity on

the Keystone XL pipeline.

With expanded pipeline capacity extending to the U.S. Gulf Coast, Canadian oil sands crude may

compete with other heavy crudes such as those from Mexico, Venezuela, and elsewhere.66 It is

difficult to predict precisely how this competition will play out, but it may take place through

shifting discounts or premiums on crude oils from various sources.67 It may be possible for

Canadian oil supplies to effectively “push out” waterborne shipments from other countries,

although this depends on a wide range of market conditions. Waterborne crudes may more easily

go to other destinations than Canadian crudes, though like Canadian crudes they can be tied to

specialized refining capacity, as is true for Venezuelan heavy crudes.

There is concern that increased supply of crude to the Gulf Coast may result in larger petroleum

product exports rather than contributing to lower domestic fuel cost. Although the United States is

a net importer of oil and petroleum products, it does export some petroleum products. U.S.

petroleum product exports rose when domestic demand declined in the wake of the recession

while foreign demand for certain fuels, such as diesel, remained relatively robust. Issues around

potential export of Canadian crude oil carried on Keystone XL or export of products made from

that crude oil are addressed in CRS Report R42465, U.S. Oil Imports and Exports, by Robert

Pirog.

If Keystone XL secures growing oil sands output for the United States, it could push out seaborne

crudes from elsewhere, regardless of where the product is ultimately sold. If the absence of the

pipeline encourages Canadian oil sands producers and pipeline companies to find an alternate

64

See increased U.S. crude oil production in the Midwest under the PADD2 heading at the following source: Energy

Information Administration, U.S. Department of Energy, Crude Oil Production (by PADD), Petroleum & Other

Liquids, http://www.eia.gov/dnav/pet/pet_crd_crpdn_adc_mbblpd_a.htm.

65

Adjusted for transport costs and other regional differences.

66

Center for Energy Economics and Bureau of Economic Geology, Overview of the Alberta Oil Sands, University of

Texas at Austin, 2006, p. 16, http://www.beg.utexas.edu/energyecon/documents/overview_of_alberta_oil_sands.pdf.

67

For more about the U.S. refining system, see CRS Report R41478, The U.S. Oil Refining Industry: Background in

Changing Markets and Fuel Policies, by Anthony Andrews et al.

Congressional Research Service

20

Keystone XL Pipeline Project: Key Issues

export route through the Canadian West Coast, Canadian supplies may displace heavy oil supplies

in other markets and potentially allow relatively more overseas imports coming into the Gulf

Coast. This possibility is discussed further below.

It should be noted that Keystone XL aims to alleviate two potential bottlenecks in the pipeline

transportation system: Between Western Canada and the United States, and between the U.S.

Midwest and the Gulf Coast. Existing pipelines between Canada and the United States have spare

capacity to carry rising Canadian production for the time being. According to some estimates,

additional capacity, such as Keystone XL, may not be needed until 2019.68 The latter bottleneck,

between the Midwest and the Gulf Coast, is already at capacity and, as described above, has

resulted in a discount for crude oil in the Midwest (though not for petroleum products). The Gulf

Coast Pipeline Project, the lower leg of originally proposed Keystone XL pipeline, would address

this second bottleneck and help alleviate the discount for Midwestern crudes.

Other Pipeline Projects

Apart from Keystone XL, several other pipeline proposals could help carry growing Canadian

crude oil supplies to the U.S. Gulf Coast. On October 16, 2011, Enbridge announced it would

purchase ConocoPhillips’ share of the Seaway pipeline and reverse its direction to bring crude oil

from the Midwest to the Gulf Coast. ConocoPhillips had kept the pipeline running northward to

serve its refinery in Ponca City, OK. However, the glut of oil in the Midwest had resulted in the

pipeline running at low volumes. Nonetheless, ConocoPhillips had been uninterested in reversing

the pipeline. ConocoPhillips, which is spinning off its refining business,69 sold its share of

Seaway to Enbridge. Enbridge and Seaway shareholder Enterprise Products Partners L.P. reversed

the direction of crude oil flows on the Seaway pipeline to enable it to transport oil from Cushing,

OK, to the U.S. Gulf Coast. The pipeline began running southward at an initial capacity of

150,000 bpd in 2012, with capacity expected to increase to 400,000 bpd in 2013. The reversal and

expansion are expected to reduce the glut of crude oil in the Midwest and reconnect Midwestern

crude prices to global prices (driving the U.S. Benchmark West Texas Intermediate crude

higher).70

Prior to the Seaway sale, Enbridge had reported significant commitments for two new pipeline

projects: Flanagan South, which would carry oil from Illinois to Oklahoma, and Wrangler, which

would carry oil from Oklahoma to Texas.71 According to Enbridge, the project would duplicate

existing routes and would not cross an international border, so it would not require a Presidential

Permit. Enbridge already has cross border pipeline capacity connecting Alberta to Illinois.

However, according to press reports, Wrangler has been canceled in light of the Seaway purchase

and reversal.72 Enbridge is moving forward with the Flanagan South project, which will have an

initial capacity of about 600,000 bpd and run alongside Enbridge’s existing Spearhead pipeline

68

Testimony of Jim Burkhard, U.S. Congress, Senate Committee on Energy and Natural Resources, US and Global

Energy Outlook for 2012, 112th Cong., 2nd sess., January 31, 2012.

69

ConocoPhillips, “ConocoPhillips Pursuing Plan to Separate into Two Stand-Alone, Publicly Traded Companies,”

press release, July 14, 2011, http://www.conocophillips.com/EN/newsroom/news_releases/2011news/Pages/07-142011.aspx.

70

Jenny Gross, “NYMEX Oil Gets Boost From Pipeline Reversal,” Wall Street Journal, April 22, 2012.

71

Bradley Olson, “Enbridge Pursuing Alternative to Transcanada’s Keystone XL,” Bloomberg, November 9, 2011.

72

Ben Lefebvre, “Enterprise Products Cancels Wrangler Pipeline,” Dow Jones Newswires, November 16, 2011.

Congressional Research Service

21

Keystone XL Pipeline Project: Key Issues

(see Figure 3).73 Like Keystone XL/Gulf Coast Project, Flanagan South and a southbound

Seaway may facilitate increased flow of Canadian crude to the U.S. Gulf Coast.

In February 2013, Enbridge also announced a proposal to convert segments of existing natural

gas pipeline owned by Trunkline Gas Company to carry crude oil from western Canada and North

Dakota to refineries in the eastern Gulf of Mexico. The pipeline conversion could potentially

carry up to 660,000 bpd from the market hub at Patoka, IL, more than 700 miles to St. James,

LA.74

73

Enbridge, “Flanagan South Project Fact Sheet,” April 1, 2012, http://www.enbridge.com/

FlanaganSouthPipeline.aspx.

74

Enbridge, “Enbridge and Energy Transfer Join to Provide Crude Oil Pipeline Access to Eastern Gulf Coast Market,”

press release, February 15, 2013.

Congressional Research Service

22

Figure 3. Proposed Enbridge Flanagan South Pipeline Route

Source: Enbridge, “Flanagan South Project Fact Sheet,” April 1, 2012, http://www.enbridge.com/FlanaganSouthPipeline.aspx.

CRS-23

Keystone XL Pipeline Project: Key Issues

Rail Transportation

While the oil industry has been making substantial investments in pipeline capacity to relieve

transportation bottlenecks for Canadian crudes, there has also been a substantial increase in oil

transportation from the region by rail. As the State Department’s 2013 DEIS for the Keystone XL

project states:

In the past 2 years, there has been exponential growth in the use of rail to transport crude oil

throughout North America, primarily originating from the Bakken in North Dakota and

Montana, but also increasingly utilized in other production areas, including the [Western

Canadian Sedimentary Basin]. Because of the flexibility of rail delivery points, once loaded

onto trains the crude oil could be delivered to refineries, terminals, and/or port facilities

throughout North America, including the Gulf Coast area.75

Consistent with this view, both Canadian National Railway and Canadian Pacific Railway

reportedly have long been pursuing a “pipeline on rails” business strategy, including new track

investments, to move Canadian crudes to new markets throughout North America.76 While the

potential volumes associated with rail transportation of crude would likely be lower than pipeline

volumes, they could still be significant. Increasing cross-border movements of crude oil by rail

does not require State Department approval, so such an approach seeks to avoid regulatory

delays.

As rail volumes have increased, some policy makers have expressed concern about the potential

safety of crude transport by rail compared to pipelines. These concerns have been exacerbated by

several significant accidents in the United States and Canada involving rail transport of crude

oil.77 The most serious accident was the July 2013 derailment and explosion of a rail-borne crude

oil shipment through Lac-Mégantic, Quebec, Canada, which killed 47 people and burned much of

the downtown area.78 Some analysts in the Keystone XL Pipeline debate have asserted that these

rail accidents underscore the need for a new pipeline as, in their view, a safer mode of

transportation for Canadian crudes.79 However, safety comparisons between the two

transportation modes are complicated by spill frequency vs. spill volume issues, which leave

assertions about relative safety open to debate.80

Canadian Oil to East and West Coast Markets

There are proposals to increase the capacity for oil from Alberta to reach the Canadian east and

west coast. Currently, nearly all of Canada’s oil exports go to the United States, mostly through

75

U.S. Department of State, March 2013, Draft EIS, Section 5.1, “No Action Alternatives.”

Nathan Vanderklippe, “CN, CP Push for a ‘Pipeline on Rails,’” The Globe and Mail, February 7, 2011.

77

See, for example, David Sheppard and Jeffrey Jones, “Train Hauling Canadian Oil Derails in Minnesota,” Reuters,

March 27, 2013.

78

Brian Mann, “Lac-Mégantic Blast Leaves Impact on Town, Rail Industry,” National Public Radio, October 14, 2013.

79

Diana Furchtgott-Roth and Kenneth P. Green, Intermodal Safety in the Transport of Oil, Fraser Institute, October

2013, http://www.fraserinstitute.org/uploadedFiles/fraser-ca/Content/research-news/research/publications/intermodalsafety-in-the-transport-of-oil.pdf.

80

See, for example: Rory Johnston, “Train vs. Pipeline: What’s the Safest Way to Transport Oil?” Christian Science

Monitor, Energy Voices blog, October 22, 2013, http://www.csmonitor.com/Environment/Energy-Voices/2013/1022/

Train-vs.-pipeline-What-s-the-safest-way-to-transport-oil.

76

Congressional Research Service

24

Keystone XL Pipeline Project: Key Issues

north-south pipelines. Only one major oil pipeline extends from Alberta to Canada’s west coast:

the Trans Mountain Pipeline, which is owned by Houston-based Kinder Morgan and has a

capacity of 300,000 bpd. Some of the oil from the Trans Mountain Pipeline is loaded onto tankers

and shipped from Vancouver. Nearly all of the quantities shipped by sea go to the United States,

with a small amount going to China and other Asian countries.81 Proposals for additional east and

westbound capacity include the following.

•

Kinder Morgan has plans to expand the Trans Mountain Pipeline to 850,000 bpd

by 2017, more than doubling its existing capacity, and expanding west coast

shipping facilities.82 The expansion has received the necessary commitments

from parties interested in shipping additional crude volumes. Some shippers are

interested in using the additional capacity to export more Canadian crude oil to

Asia. Kinder Morgan still needs regulatory approvals from Canadian authorities

and is working to gain the support of stakeholders.83 There is some opposition to

the project, including from groups concerned about additional tanker traffic near

Vancouver and potential oil spill risks.84

•

Enbridge has proposed a new pipeline: the Northern Gateway project would have

a 525,000 bpd capacity to send oil from Edmonton to Kitimat, British

Columbia.85 However, Northern Gateway faces opposition from groups including

some First Nations communities and environmental groups.86

•

Several projects are considering moving oil east rather than to the west coast.

According to reports, TransCanada is considering a pipeline project sending oil

east from Alberta to Quebec and New Brunswick, which could also carry crude

bound for export.87 Enbridge is also interested in expanding eastbound capacity

by reversing its Line 9 Pipeline.88 Some suggest this could potentially lead to oil

sands crude traveling east, through Montreal and then through another pipeline to

Portland, ME, from which point it could be exported.89 As with other pipeline

projects, these also face opposition from environmental groups concerned about

oil spill risks and/or generally opposed to oil sands development.

81

According to the Global Trade Atlas, about 0.5% of Canadian crude exports went to China in 2011 (accessed April

25, 2012).

82

Christopher Smith, “KMEP Advances Trans Moutain Crude Pipeline Expansion,” Oil & Gas Journal, April 6, 2012.

83

David Ebner and Justine Hunter, “U.S. Company Plans Billion-Dollar Expansion of Trans Mountain Pipeline,” The

Global and Mail, April 13, 2012.

84

Jeff Lee, “Vancouver Council, Park Board to Formally Oppose Kinder Morgan Pipeline Expansion,” Vancouver Sun,

April 24, 2012.

85

Enbridge, “Northern Gateway at a Glance,” press release, 2011, http://www.northerngateway.ca/project-info/

northern-gateway-at-a-glance. The project would also include a pipeline to allow the import of 193,000 bpd of

condensate, a light hydrocarbon that can be blended with bitumen to allow pipeline transport.

86

“Northern Gateway Pipeline: Alberta, B.C. Agree to Drop Compensation Issue from their Talks,” Canadian Press,

November 5, 2013.

87

Nathan Vanderklippe and Shawn McCarthy, “TransCanada Looks East as Gateway Pipeline Gets Bogged Down,”

The Globe and Mail, March 22, 2012.

88

“Enbridge Pipelines Inc. - Line 9 Reversal Phase I Project (OH-005-2011),” (Project Application), National Energy

Board (Government of Canada), http://www.neb-one.gc.ca/clf-nsi/rthnb/pplctnsbfrthnb/nbrdgln9phs1/nbrdgln9phs1eng.html.

89

Matt Dodge, “Court Decision Affects South Portland-Montreal Pipeline,” Maine Biz, April 3, 2012; Yadullah

Hussain, “Pipeline Plan to Send Crude from Montreal to Maine Raises Ire in New England,” Financial Post, May 22.

2013.

Congressional Research Service

25

Keystone XL Pipeline Project: Key Issues

These projects reflect anticipated growth of western Canadian oil production and an interest by

Canadian oil producers to diversify their available markets beyond U.S. customers, especially to

reach rapidly growing Asian oil demand.

Canadian interests assert that Canadian oil sales to Asian markets, where oil demand is growing

rapidly, are more likely if greater shipments to the United States are not possible.90 A study

commissioned by the U.S. Department of Energy suggested that

if pipeline projects to the [British Columbia] coast are built, they are likely to be utilized.

This is because of the relatively short marine distances to major northeast Asia markets,

future expected growth there in refining capacity and increasing ownership interests by

Chinese companies especially in oil sands production. Such increased capacity would alter

global crude trade patterns. Western Canadian Sedimentary Basin (WCSB) crudes would be

“lost” from the USA, going instead to Asia. There they would displace the world’s balancing

crude oils, Middle Eastern and African predominantly OPEC grades, which would in turn

move to the USA. The net effect would be substantially higher U.S. dependency on crude

oils from those sources versus scenarios where capacity to move WCSB crudes to Asia was

limited.91

Economic Impact of the Pipeline

In addition to supply diversity arguments, some Keystone XL pipeline proponents support the

project based on economic benefits associated with expanding U.S. pipeline infrastructure. A

study by the Energy Policy Research Foundation, for example, concludes that “the Keystone

expansion would provide net economic benefits from improved efficiencies in both the

transportation and processing of crude oil of $100 million-$600 million annually, in addition to an

immediate boost in construction employment.”92 A 2009 report from the Canadian Energy

Research Institute (CERI) commissioned by the American Petroleum Institute similarly

concludes that

As investment and production in oil sands ramps up in Canada, the pace of economic activity

quickens and demand for US goods and services increase rapidly, resulting in an estimated

343 thousand new US jobs between 2011 and 2015. Demand for U.S. goods and services

continues to climb throughout the period, adding an estimated $34 billion to US GDP in

2015, $40.4 billion in 2020, and $42.2 billion in 2025.93

These CERI estimates apply to the entire oil sands industry, however, not only the Keystone XL

project, and they are derived from a proprietary economic analysis which has not been subject to

external review. Some stakeholders point to State Department and other studies reporting much

lower anticipated economic benefits.94 In July 2013, President Obama reportedly stated that the

90

Edward Welsch, “TransCanada: Oil Sands Exports Will Go to Asia if Blocked in U.S.,” Dow Jones Newswires, June

30, 2010.

91

EnSys Energy & Systems, Inc., Keystone XL Assessment: Final Report, Prepared for the U.S. Department of Energy,

Office of Policy & International Affairs, December 23, 2010, p. 118.

92

Energy Policy Research Foundation, Inc., The Value of the Canadian Oil Sands (….to the United States): An

Assessment of the Keystone Proposal to Expand Oil Sands Shipments to Gulf Coast Refiners, Washington, DC,

November 29, 2010, p. 2, http://www.eprinc.org/pdf/oilsandsvalue.pdf.

93

Canadian Energy Research Institute, The Impacts of Canadian Oil Sands Development on the United States’

Economy, Final Report, Calgary, Alberta, October 2009, p. vii.

94

See, for example, Cornell University Global Labor Institute, Pipe Dreams? Jobs Gained, Jobs Lost by the

(continued...)

Congressional Research Service

26

Keystone XL Pipeline Project: Key Issues

Keystone XL pipeline might create 2,000 temporary construction jobs and 50 to 100 permanent

jobs.95 With the separation of the Gulf Coast Project from the northern segment of the original

proposal, the potential economic impact of the reconfigured Keystone XL project has clearly

changed. Consequently, it is difficult to determine what specific economic and employment

impacts may ultimately be attributable to the Keystone XL pipeline. Nonetheless, given the

physical scale of the project, it could be expected to increase employment and investment at least

during construction.

Lifecycle Greenhouse Gas Emissions

Oil production from oil sands is controversial because it has significant environmental impacts,

including emissions of greenhouse gases during extraction and processing, disturbance of mined

land, and impacts on wildlife and water quality.96 In a June 2013 speech about climate change,

President Obama remarked

Allowing the Keystone [XL] pipeline to be built requires a finding that doing so would be in

our nation’s interest. And our national interest will be served only if this project does not

significantly exacerbate the problem of carbon pollution.97

Thus, of the environmental factors under consideration, greenhouse gas emissions attributed to

the development of Keystone XL may be the key determinant of whether the project will be

granted a Presidential Permit.

Because bitumen in oil sands cannot be pumped from a conventional well, it must be either

mined, usually using strip mining or open pit techniques, or extracted with underground heating

methods.98 Large amounts of water and natural gas are also required (for heating) during the

extraction process.99 The magnitude of the environmental impacts of oil sands production, in

absolute terms and compared to conventional oil production, has been the subject of numerous,

and sometimes conflicting, studies and policy papers.100 Some stakeholders who object to oil

sands projects oppose the Keystone XL pipeline because it expands access to new markets for the

oil produced by those projects, thereby encouraging what they consider to be further

environmentally destructive oil sands development. As discussed earlier, however, if oil sands

(...continued)

Construction of Keystone XL, September 28, 2011; National Wildlife Federation, “TransCanada Exaggerating Jobs

Claims for Keystone XL,” November 9, 2010, http://www.dirtyoilsands.org/files/Keystone_XL_Jobs_11-09-10.pdf.

95

Glenn Kessler, “President Obama’s Low-Ball Estimate for Keystone XL Jobs,” Washington Post, July 30, 2013.

96

For more analysis of oil sands and their environmental impacts, see CRS Report RL34258, North American Oil

Sands: History of Development, Prospects for the Future, by Marc Humphries.

97

President Barack Obama, “Remarks by the President on Climate Change,” Georgetown University, Washington, DC,

June 25, 2013, http://www.whitehouse.gov/the-press-office/2013/06/25/remarks-president-climate-change.

98

U.S. Bureau of Land Management, “About Tar Sands,” web page, January 11, 2011, http://ostseis.anl.gov/guide/

tarsands/index.cfm.

99

Cecilia Jamasmie, “The Challenges and Potential of Canada’s Oil Sands,” Mining, September-October 2010, pp. 7-8.

100

For an example of contrasting views, see IHS CERA Inc., Oil Sands, Greenhouse Gases, and US Oil Supply,

Getting the Numbers Right, 2010; and Natural Resources Defense Council, “Setting the Record Straight: Lifecycle

Emissions of Tar Sands,” November 2010.

Congressional Research Service

27

Keystone XL Pipeline Project: Key Issues

production can be diverted to other markets (e.g., Asia), preventing the Keystone XL project may

not necessarily limit oil sands development.101

Some stakeholders object to the Keystone XL pipeline because it would increase U.S. supplies of

oil, and thereby perpetuate the nation’s dependence on imported fossil fuels and increase carbon

emissions from the transportation sector.102 Acknowledging this concern, in a public forum on

October 20, 2010, Secretary of State Clinton reportedly remarked that “we’re either going to be

dependent on dirty oil from the [Persian] Gulf or dirty oil from Canada … until we can get our act

together as a country and figure out that clean, renewable energy is in both our economic interests

and the interests of our planet.”103 Critics of the State Department’s draft and supplemental draft

EIS assert that the environmental review overlooks the pipeline project’s overall impact on

greenhouse gas emissions, for example, from the extraction and refining processes. To address

those potential emissions, EPA recommended that the final EIS include discussion of mitigation

approaches for greenhouse gas emissions from extraction activities that are either currently used

or could be employed to help lower lifecycle greenhouse gas emissions.104 However, others have

argued that whether the Keystone XL Pipeline is constructed would have little bearing on

greenhouse gas emissions as there are likely to be other export routes available for Canadian oil

sands crude, and therefore, the same crude oils would still be transported and refined, albeit in

different locations.105 For further analysis of greenhouse gas emissions associated with the

Canadian oil sands, see CRS Report R42537, Canadian Oil Sands: Life-Cycle Assessments of

Greenhouse Gas Emissions, by Richard K. Lattanzio.

Private Land Use and Oil Spill Impacts

For the proposed Keystone XL Project, approximately 88% of the land affected by pipeline

construction and operation would be privately owned, with the remaining 12% primarily state and

federal land.106 Private land uses along the proposed pipeline routes are primarily agricultural—

farming and cattle ranching. The pipeline’s construction and continued operation would involve a

50-foot-wide permanent right-of-way along the length of the pipeline. Keystone agreed to

compensate landowners for losses on a case-by-case basis. However, a concern among

landowners and communities along the route is the potential for their land or water (used for

drinking, irrigation, or recreation) to be contaminated by an accidental release (spill) of oil. That

concern is heightened in areas where the pipeline will be located near or would cross water or is

in a remote location.

101

For more analysis of oil sands, including the environmental effects of its extraction, see CRS Report RL34258,

North American Oil Sands: History of Development, Prospects for the Future, by Marc Humphries.

102

See, for example: Natural Resources Defense Council, Tar Sands Invasion: How Dirty and Expensive Oil from

Canada Threatens America’s New Energy Economy, May 2010.

103

See Secretary of State Hillary Clinton’s “Remarks on Innovation and American Leadership to the Commonwealth

Club,” San Francisco, CA, October 15, 2010, available at http://www.state.gov/secretary/rm/2010/10/149542.htm.

104

See EPA’s July 16, 2010, letter to the U.S. Department of State rating the supplemental EIS for the Keystone XL

pipeline project, available at http://yosemite.epa.gov/oeca/webeis.nsf/%28PDFView%29/20100126/$file/

20100126.PDF. Discussion of the analysis of GHG emissions is included on pp. 3-4.

105

EnSys Energy & Systems 2010, p. 116.

106

U.S. Department of State, March 2013, Draft EIS: “Section 4.9, Land Use, Recreation, and Visual Resources,” p.

4.9-2.

Congressional Research Service

28

Keystone XL Pipeline Project: Key Issues

A primary environmental concern of any oil pipeline is the risk of an oil spill. In estimating

potential environmental impacts, several factors will be important—including the size and

location of the release, leak, or spill, and how quickly it is remediated. An oil spill on land would

not necessarily result in surface or groundwater contamination. The potential for a spill to reach

water would depend on factors such as its proximity to a water source (e.g., on or near a creek or

stream or located on land where the groundwater table is close to the surface) and the

characteristics of the environment into which the crude oil is released (e.g., porous underlying

soils), and the volume of the spill, its duration, and the viscosity and density of the crude oil

involved.

The size of potential spills and the type of oil that would likely be released from the Keystone XL

Pipeline have been issues of concern to opponents of the project. In its July 16, 2010, comments

on the draft EIS for the Keystone XL Project, EPA expressed particular concern over the potential

adverse impacts to surface and ground water from pipeline leaks or spills. That concern stemmed

from two areas—the toxicity of chemical diluents that may be used to allow bitumen to be

transported by pipeline and the lack of risk assessment for potential “serious or significant spills,”

including an evaluation of spill response procedures in the wake of such a spill.

Concerns reflected in EPA’s letter were realized 10 days later when the Enbridge Energy Partners’

Alberta Pipeline ruptured near Marshall, MI. The resulting spill released crude into a tributary

creek of the Kalamazoo River and traveled approximately 40 miles downstream in the

Kalamazoo River. Initially estimated by Enbridge as a release of approximately 800,000 gallons

of crude, EPA subsequently estimated that over 1.1 million gallons were released. The spill

resulted in over 220 areas of moderate-to-heavy contamination, including over 200 acres of

submerged oil on the river bottom and over 300 solidified oil deposits.107 Enbridge estimates that

cleanup will cost approximately $700 million.

The Enbridge spill highlighted several issues of concern among environmental groups and

communities along the pipeline route—in particular, the nature of the heavy crude likely carried

by the Keystone XL Pipeline. The heavy crude (diluted bitumen, or dilbit) in the Enbridge spill

had been diluted with benzene and other hazardous constituents. Following the spill, high levels

of benzene in the air prompted the issuance of voluntary evacuation of residents in the area.

Concern over the presence of similarly toxic constituents, particularly the degree to which the

level of toxic constituents may be unknown at the time of a release, has been an ongoing concern

among environmental and community groups.

The Enbridge spill was considered a “very large spill” and not necessarily one that would be

likely along the Keystone XL pipeline route. However, in its first year of operation,

TransCanada’s Keystone pipeline experienced 14 spills. Although mostly minor, one spill at the

Ludden, ND, pump station resulted in the release of 21,000 gallons of oil. Like the Enbridge

release, that release was first reported by local citizens, not as a result of the Keystone’s release

detection equipment. A March 29, 2013, release of oil sands crude from an Exxon Mobil pipeline

in Mayflower, AR, has continued to draw attention to the risk of potential spills from crude oil

pipelines.108 These incidents have made pipeline opponents concerned that such spills may be

107

For more information see EPA’s regarding the response to the Enbridge oil spill at http://www.epa.gov/

enbridgespill/.

108

Arkansas Department of Environmental Quality, “Mayflower Oil Spill Response,” fact sheet, March 30, 2013,

http://www.adeq.state.ar.us/hazwaste/mayflower_oil_spill_2013/files/mayflower_pipeline-_fact_sheet.pdf.

Congressional Research Service

29

Keystone XL Pipeline Project: Key Issues

significant and that, absent a witness to a spill, a leak in a remote area could potentially go

undetected for a long period.

The Enbridge spill also demonstrates that cleanup of oil sands dilbit presents certain challenges.

Dilbit is a relatively heavy crude oil mixture compared to other crude oils. In general, heavier oils

are more persistent and present greater technical challenges in removal after a spill compared to

lighter oils. Over two years after the Enbridge spill, cleanup efforts continue. After the spill,

public access to 39 miles of the river system was banned to protect public health and safety. In

March 2013, the EPA ordered Enbridge to implement containment and dredging of submerged oil

to prevent continued migration of oil downstream to the Kalamazoo River.109 The first three-mile

segment of river reopened to the public on April 27, 2012. Elements of the cleanup are expected

to last until 2015. For further analysis of environmental issues associated with the Keystone XL

project, see CRS Report R42611, Oil Sands and the Keystone XL Pipeline: Background and

Selected Environmental Issues, coordinated by Jonathan L. Ramseur.

Regardless of design, construction, and safety measures, the Keystone XL pipeline will likely

have some number of spills over the course of its operating life. The unique oil spill response

efforts necessary for heavy crudes like dilbit make an accurate assessment of potential oil spill

risk particularly relevant when addressing concerns expressed by opponents to the Keystone XL

Pipeline. The need for more conclusive analysis of potential risks associated with the transport of

dilbit was addressed, in part, in the Pipeline Safety, Regulatory Certainty, and Job Creation Act of

2011 (P.L. 112-90, enacted January 16, 2012). In particular, under Section 16, “Study of

transportation of diluted bitumen,” the Secretary of Transportation is required to conduct an

analysis to determine whether there is any increased risk of a release for pipeline facilities

transporting diluted bitumen. In response to that directive, the PHMSA contracted with the

National Academy of Sciences to conduct a full and independent study of this topic. The

Academy’s report “did not find any pipeline failures unique to the transportation of diluted

bitumen or evidence of physical or chemical properties of diluted bitumen shipments that are

outside the range of those of other crude oil shipments.”110

Issues with the Original Pipeline Route Across the Sand Hills

In the process of examining factors necessary to determine whether the Presidential Permit for the

original Keystone XL Project was in the national interest, the State Department decided that it

needed to assess potential alternative pipeline routes that would avoid the Sand Hills region of

Nebraska. Unique characteristics of the Sand Hills—including its high concentration of wetlands,

extensive areas of very shallow groundwater, and its sensitive ecosystem—were identified as

factors that resulted in increasing public concern over the proposed pipeline location. For these

reasons, TransCanada announced it would work with the Nebraska DEQ to identify a potential

pipeline route that would avoid the Sand Hills. New pipeline routes through Nebraska, identified

in the 2013 draft EIS, reflect the work between TransCanada and Nebraska DEQ.

109

Environmental Protection Agency, “Re: Order pursuant to §311(c) of the Clean Water Act (Docket No. CWA 13215-13-001) for Recovery of Submerged Oil from the En bridge Line 6B Discharge near Marshall, MI,” Cover letter,

March 14, 2013, http://www.epa.gov/enbridgespill/ar/enbridge-AR-1719.pdf.

110

National Research Council, Effects of Diluted Bitumen on Crude Oil Transmission Pipelines, TRB Special Report

311, June 25, 2013.

Congressional Research Service

30

Keystone XL Pipeline Project: Key Issues

To understand concerns about the potential environmental impacts of a pipeline crossing the Sand

Hills (also referred to as the Sandhills), an understanding of the unique size and structure of the

region is useful. The Sand Hills region is a 19,600 square mile sand dune formation stabilized by

native grasslands that cover 95% of its surface. The surface is highly susceptible to wind erosion

if the grassland is disturbed.111 Below its surface lie hundreds of feet of coarse sand and gravel.

Essentially, the porous soil acts like a giant sponge that quickly absorbs precipitation, allowing

very little to run off. In some areas, the water table reaches the land surface—a characteristic that

creates lakes that dot the region as well as 1.3 million acres of wetlands. The loose, porous soil

and sensitivity to wind erosion have been factors contributing to a lack of development on the

Sand Hills. As a result, the region contains the most intact natural habitat of the Great Plains of

the United States. The porosity of the soil is also relevant because the Sand Hills sits atop the

Ogallala Aquifer—one of the largest freshwater aquifer systems in the world.112

The highly porous soil of the Sand Hills makes it a significant recharge zone in the northern

Ogallala Aquifer. That is, the sandy, porous soil of the Sand Hills allows a significant amount of

surface water to enter (recharge) the aquifer system. Water from the aquifer also accounts for a

significant amount of water use—78% of the region’s public water, 83% of irrigation water in

Nebraska, and 30% of water used in the United States for irrigation and agriculture.

Potential impacts to the Ogallala Aquifer and the Sand Hills identified in the final EIS for

TransCanada’s original permit application included groundwater contamination after an

accidental spill or leak of crude oil during the construction or operation of the proposed pipeline.

Along the preferred route of the originally proposed pipeline configuration, areas in the Sand

Hills region were identified as locations where the water table may be close to the surface. The

depth to groundwater was less than 10 feet for approximately 65 miles of the preferred pipeline

route in Nebraska. Both the soil porosity and the close proximity of groundwater to the surface

increase the potential that a release of oil from the pipeline could contaminate groundwater in the

region.113

On January 13, 2013, the governor of Nebraska approved a proposed reroute of the Keystone XL

pipeline through Nebraska.114 The new route alternatives proposed for the Nebraska section of the

Keystone XL pipeline avoids the Sand Hills and certain areas nearby with similar soil properties.

111

For more information, see the Department of the Interior’s U.S. Fish and Wildlife Service web page on the Sand

Hills at http://www.fws.gov/mountain-prairie/pfw/ne/ne4.htm.

112

The entire Ogallala Aquifer system stretches across eight states generally from north to south to include South

Dakota, Nebraska, Wyoming, Colorado, Kansas, Oklahoma, New Mexico, and Texas and underlies about 174,000

square miles.

113

Generally, a release of crude oil to land would not necessarily result in groundwater contamination. In addition to

the depth from the land surface to groundwater and the characteristics of the environment into which the crude oil is

released (e.g., characteristics of the underlying soils), the potential for crude oil to reach groundwater would depend on

factors such as the volume of the spill, the duration of the release, and the viscosity and density of the crude oil.

114

See U.S. Department of State, March 2013, Draft EIS: “Volume III. Appendix A. Governor Approval of the

Keystone XL Project in Nebraska.”

Congressional Research Service

31

Keystone XL Pipeline Project: Key Issues

Figure 4. Keystone XL Project—Pipeline Route in Nebraska

Comparison of Currently and Previously Proposed Project Segments

Source: State Department, March 2013, “Draft Supplemental

Environmental Impact Statement for the Keystone XL Project: Executive

Summary,” p. ES-7.

Congressional Research Service

32

Keystone XL Pipeline Project: Key Issues

Appendix A. Presidential Permitting Authority115

The executive branch has exercised permitting authority over the construction and operation of

“pipelines, conveyor belts, and similar facilities for the exportation or importation of petroleum,

petroleum products” and other products at least since the promulgation of Executive Order 11423

in 1968.116 Executive Order 13337 amended this authority and the procedures associated with the

review, but did not substantially alter the exercise of authority or the delegation to the Secretary

in E.O. 11423.117 However, the source of the executive branch’s permitting authority is not

entirely clear from the text of these Executive Orders. Generally, powers exercised by the

executive branch are authorized by legislation or are inherent presidential powers based in the

Constitution. E.O. 11423 makes no mention of any authority, and E.O. 13337 refers only to the

“Constitution and the Laws of the United States of America, including Section 301 of title 3,

United States Code.”118 Section 301 simply provides that the President is empowered to delegate

authority to the head of any department or agency of the executive branch.

The legitimacy of this permitting authority has been addressed by federal courts. In Sisseton v.

United States Department of State, the plaintiff Tribes filed suit and asked the court to suspend or

revoke the Presidential Permit issued under E.O. 13337 for the TransCanada Keystone

Pipeline.119 The U.S. District Court for the District of South Dakota found that the plaintiffs

lacked standing because they would be unable to prove their injury could be redressed by a

favorable decision.120 The court determined that even if the plaintiff’s injury could be redressed,

“the President would be free to disregard the court’s judgment,” as the case concerned the

President’s “inherent Constitutional authority to conduct foreign policy,” as opposed to statutory

authority granted to the President by Congress.121

The court further found that even if the Tribes had standing, the issuance of the Presidential

Permit was a presidential action, not an agency action subject to judicial review under the

Administrative Procedure Act (APA).122 The court stated that the authority to regulate the crossborder pipeline lies with either Congress or the President.123 The court found that “Congress has

failed to create a federal regulatory scheme for the construction of oil pipelines, and has delegated

this authority to the states. Therefore, the President has the sole authority to allow oil pipeline

border crossings under his inherent constitutional authority to conduct foreign affairs.”124 The

115

For a more expansive treatment of this topic, see CRS Report R42124, Proposed Keystone XL Pipeline: Legal

Issues, by Adam Vann, Kristina Alexander, and Kenneth R. Thomas, and CRS Report R43261, Presidential Permits

for Border Crossing Energy Facilities, by Adam Vann and Paul W. Parfomak.

116

Providing for the performance of certain functions heretofore performed by the President with respect to certain

facilities constructed and maintained on the borders of the United States, 33 Federal Register 11741, August 16, 1968.

117

Issuance of Permits With Respect to Certain Energy-Related Facilities and Land Transportation Crossings on the

International Boundaries of the United States, 69 Federal Register 25299, May 5, 2004.

118

Ibid.

119

659 F. Supp. 2d 1071, 1078 (D. S.D. 2009).

120

Ibid. at 1078.

121

Ibid. at 1078, 1078 n.5.

122

See ibid. at 1080-81.

123

Ibid. at 1081.

124

Ibid.

Congressional Research Service

33

Keystone XL Pipeline Project: Key Issues

President could delegate his permitting authority to the U.S. Department of State, but delegation

did not transform the permit’s issuance into an agency action reviewable under the APA.125

In Sierra Club v. Clinton,126 the plaintiff Sierra Club challenged the Secretary’s decision to issue a

Presidential Permit authorizing the Alberta Clipper pipeline. Among the plaintiff’s claims was an

allegation that issuance of the permit was unconstitutional because the President had no authority

to issue the permits referenced in E.O. 13337 (in this case, for the importation of crude oil from

Canada via pipeline).127 The defendant responded that the authority to issue Presidential Permits

for these border-crossing facilities “does not derive from a delegation of congressional authority

... but rather from the President’s constitutional authority over foreign affairs and his authority as

Commander in Chief.”128 The U.S. District Court for the District of Minnesota agreed, noting that

the defendant’s assertion regarding the source of the President’s authority has been “well

recognized” in a series of Attorney General opinions, as well as a 2009 judicial opinion.129 The

court also noted that these permits had been issued many times before and that “Congress has not

attempted to exercise any exclusive authority over the permitting process. Congress’s inaction

suggests that Congress has accepted the authority of the President to issue cross-border

permits.”130 Based on the historical recognition of the President’s authority to issue these permits

and Congress’s implied approval through inaction, the court found the Presidential Permit

requirement for border facilities constitutional.

125

Ibid. at 1082.

689 F.Supp.2d 1147 (D. Minn. 2010).

127

Ibid. at 1162.

128

Ibid.

129

Ibid. at 1163 (citing 38 U.S. Atty Gen. 162 (1935); 30 U.S. Op. Atty. Gen. 217 (1913); 24 U.S. Op. Atty. Gen. 100;

and Natural Resources Defense Council (NRDC) v. U.S. Department of State, 658 F.Supp.2d 105, 109 (D.D.C. 2009)).

The court in NRDC held that the State Department’s issuance of a presidential permit under Executive Order 13337

was not subject to judicial review under the Administrative Procedure Act for abuse of discretion because “the issuance

of presidential permits is ultimately a presidential action.” 658 F. Supp. 2d at 109, 111-12. The court said that to allow

judicial review of such decisions would raise separation of powers concerns. Ibid. at 111.

130

Ibid.; see also Youngstown Sheet and Tube Co. v. Sawyer, 343 U.S. 579 (1952) (establishing a three-part test for

analyzing the validity of presidential actions in relation to constitutional and congressional authority).

126

Congressional Research Service

34

Keystone XL Pipeline Project: Key Issues

Appendix B. Details of the Initial NEPA Review

The NEPA process for TransCanada’s 2008 Presidential Permit application for the Keystone XL

pipeline project included several significant milestones (summarized in Table 1). These events,

and resulting documents, will likely have varying degrees of influence over TransCanada’s 2012

permit application.

Draft EIS issued

The State Department released its draft EIS for the proposed Keystone XL Pipeline project for

public comment on April 16, 2010.131 The draft EIS identified TransCanada’s “preferred

alternative” for the project as well as other alternatives considered. On July 16, 2010, EPA rated

the draft EIS “Inadequate.”132 EPA found that potentially significant impacts were not evaluated

and that the additional information and analysis needed was of such importance that the draft EIS

would need to be formally revised and again made available for public review. Additional

criticism of the State Department’s implementation of the NEPA process followed an October 21,

2010, statement by Secretary Clinton that, while analysis of the project was not complete and a

final decision had not been made, the State Department was “inclined to” approve the project.133

Critics of the project, including some Members of Congress, stated that the Secretary’s statement

appeared to prejudge its permit approval for the pipeline proposal as a foregone conclusion.134

Supplemental Draft EIS Issued

The State Department issued a supplemental draft EIS on April 15, 2011. In addition to

addressing issues associated with EPA’s inadequacy rating, the supplemental draft EIS addressed

comments received from other agencies and the public. On June 6, 2011, EPA sent a letter to the

State Department that rated the supplemental draft EIS as having “Insufficient Information” and

having “Environmental Objections” to the proposed action.135 EPA acknowledged that the State

Department had “worked diligently” to develop additional information in response to EPA’s

comments and the large number of other comments on the draft EIS. However, EPA believed that

additional analysis needed to be included in the final EIS to fully respond to its earlier comments.

131

Documents submitted for the initial 2008 Presidential Permit application have now been archived by the State

Department. Documents related to that original application are available at http://keystonepipeline-xl.state.gov/archive/

index.htm.

132

U.S. Environmental Protection Agency’s July 16, 2010, letter to the U.S. Department of State commenting on the

draft EIS for the Keystone XL project is available at http://yosemite.epa.gov/oeca/webeis.nsf/%28PDFView%29/

20100126/$file/20100126.PDF.

133

See Secretary of State Hillary Clinton, “Remarks on Innovation and American Leadership to the Commonwealth

Club,” San Francisco, CA, October 15, 2010, available at http://www.state.gov/secretary/rm/2010/10/149542.htm. The

statement by Secretary Clinton was actually made in response to a question about the Alberta Clipper pipeline project

which received a Presidential Permit from the State Department in 2009; a State Department spokesman later clarified

that the Secretary was referring to the Keystone XL pipeline permit approval.

134

For example, see the October 21, 2010, letter from Senator Mike Johanns to Secretary Clinton expressing his

concern that her statement gave the appearance that approval of the pipeline was a foregone conclusion,

http://johanns.senate.gov/public/?a=Files.Serve&File_id=8b090aa5-76fe-41ca-a674-ae9e37db8d36.

135

U.S. Environmental Protection Agency’s June 6, 2011, letter to the U.S. Department of State commenting on the

supplemental draft EIS for the Keystone XL project is available at http://yosemite.epa.gov/oeca/webeis.nsf/

%28PDFView%29/20110125/$file/20110125.PDF?OpenElement.

Congressional Research Service

35

Keystone XL Pipeline Project: Key Issues

Among other items, EPA recommended that the State Department should do the following:

improve the analysis of the potential oil spill risks, including additional analysis of other

reasonable alternatives to the proposed pipeline route; provide additional analysis of potential oil

spill impacts, health impacts, and environmental justice concerns to communities along the

pipeline route and adjacent refineries; and improve its characterization of lifecycle greenhouse

gas emissions associated with Canadian oil sands crude.

In its June 6 letter to the State Department, EPA refers to agreements with the State Department

that certain deficiencies identified in the supplemental draft EIS would be addressed in the final

EIS. Further, in its conclusion, EPA stated that it would carefully review the final EIS to

determine if it fully reflects those agreements and if measures to mitigate adverse environmental

impacts are fully evaluated.

Final EIS Issued

On August 26, 2011, the State Department issued the final EIS for the proposed Keystone XL

Pipeline. Among other elements of the final EIS, it identified various major pipeline route

alternatives and an environmental analyses of potential impacts associated with those

alternatives.136

In October 2011, 14 Members of Congress wrote to the State Department’s Office of Inspector

General requesting an investigation of the department’s handling of the EIS and national interest

determination for the Keystone XL project.137 The request was prompted, in part, by press reports

suggesting bias or potential conflicts of interest in the State Department’s hiring of an outside

contractor to perform the EIS and in its communications with the pipeline’s developer,

TransCanada.138 On November 4, the Inspector General’s Office (IG) announced that, in response

to this request, it was initiating a special review “to determine to what extent the Department and

all other parties involved complied with Federal laws and regulations relating to the Keystone XL

pipeline permit process.”139 On February 9, 2012, the IG released its findings, reporting that the

State Department “did not violate its role as an unbiased oversight agency,” among other specific

findings generally supportive of the department’s Keystone XL permit review process.140

Public Review and National Interest Determination

Following the release of the Keystone XL project’s final EIS, a review period began to determine

if the proposed project was in the national interest. As part of the process for the Keystone XL

project, the State Department held public meetings in each of the six states through which the

136

Environmental analysis associated with pipeline project alternatives is provided in Volumes 1 and 2 of the final EIS.

U.S. Senator Bernard Sanders, et al., Letter to The Honorable Harold W. Geisel, Office of Inspector General, U.S.

Department of State, October 26, 2011.

138

See. for example, Elisabeth Rosenthal and Dan Frosch, “Pipeline Review Is Faced with Question of Conflict,” New

York Times, October 7, 2011.

139

Harold W. Geisel, United States Department of State, Office of Inspector General, “Information Memo for Deputy

Secretary Burns,” November 4, 2011, http://sanders.senate.gov/imo/media/doc/

Special%20Review%20Keystone%20XL%20Pipeline%20Nov%2020112.pdf.

140

Harold W. Geisel, United States Department of State, Office of Inspector General, Special Review of the Keystone

XL Pipeline Permit Process, AUD/SI-12-28, February 2012.

137

Congressional Research Service

36

Keystone XL Pipeline Project: Key Issues

proposed pipeline would pass and in Washington, DC.141 The meetings were intended to give

members of the public additional opportunity to voice their opinions on issues they thought

should be taken into account in determining whether granting or denying the Presidential Permit

would be in the national interest.142 During the review period, the State Department received input

from state, local, and tribal officials as well as members of the public.

After the public review period, the State Department issued a statement regarding the public

comments and its response to those comments.143 The State Department stated that it received

comments on a wide range of issues, including the Keystone XL project’s potential impact on

jobs, pipeline safety, health concerns, the societal impact of the project, and oil extraction in

Canada. Concern regarding the proposed pipeline route through the Sand Hills area of Nebraska

was identified as one of the most common issues raised. Comments regarding that pipeline route

were consistent with the environmental impacts identified in the final EIS with regard to the

unique combination of characteristics of the Sand Hills region.

In the final EIS, the preferred pipeline route through Nebraska would have been located entirely

above the Ogallala Aquifer. Potential impacts to the Ogallala Aquifer and the Sand Hills

identified in the final EIS include potential groundwater contamination after a release (e.g., a spill

or leak from a hole or damaged portion of the pipeline) of crude oil during the construction or

operation of the proposed pipeline. Both the soil porosity and the close proximity of groundwater

to the surface increase the potential that a release of oil from the pipeline could contaminate

groundwater in the region.

During the public review period, the governor of Nebraska called a special session of the

legislature to determine if siting legislation could be crafted and passed for pipeline routing in

Nebraska. Facing the prospect of new state pipeline siting regulations applicable to the Sand

Hills, together with the concern about the Keystone XL pipeline’s specific “preferred” route, the

State Department announced that it would require additional information about alternative

pipeline routes avoiding the environmentally sensitive Sand Hills area in Nebraska before moving

forward with its national interest determination.144 Although the State Department did not decide

that environmental issues led to a determination that the proposed project was not in the national

interest, environmental issues identified in the final EIS, and further stressed in public comments,

led to its decision to delay that determination until it gathered this information.

Although no new decision deadline was established, State Department officials suggested that it

would be “reasonable to expect that this process including a public comment period on a

supplement to the final EIS consistent with NEPA could be completed as early as the first quarter

of 2013.”145 In a prior press interview, President Obama also appeared to suggest that,

141

U.S. Department of State press release, “Keystone XL Final Environmental Impact Statement Released; Public

Meetings Set,” August 26, 2011, http://www.state.gov/r/pa/prs/ps/2011/08/171082.htm.

142

These additional public meetings are not part of the NEPA process. Considering the strong public interest in the

pipeline proposal (both opposed and in favor), the public hearings were part of the State Department’s national interest

determination.

143

U.S. Department of State, November 10, 2011.

144

U.S. Department of State, “Keystone XL Pipeline Project Review Process: Decision to Seek Additional

Information,” Media Note, PRN 2011/1909, Office of the Spokesperson, November 10, 2011.

145

U.S. Department of State, November 10, 2011.

Congressional Research Service

37

Keystone XL Pipeline Project: Key Issues

notwithstanding the delegation of Presidential Permit authority to the State Department, he would

be personally involved in the final decision on the Keystone XL Pipeline permit application.146

Directive to the President to Approve or Deny the Permit

In the wake of the State Department determination that supplemental analysis was needed,

Congress directed the President to make a determination on the Presidential permit application for

the Keystone XL pipeline. Specifically, the Temporary Payroll Tax Cut Continuation Act of 2011

(P.L. 112-78), enacted on December 23, 2011, included provisions requiring the Secretary to issue

a permit for the project within 60 days, unless the President publicly determined the project to be

not in the national interest.

Subsequently, the State Department, with the President’s consent, announced that it would deny

the Keystone XL permit on January 18, 2012. In its announcement the department stated that its

decision “was predicated on the fact that [P.L. 112-78] ... passed in December does not provide

sufficient time to obtain the information that we think is necessary to assess whether the project,

in its current state, is in the national interest.”147 However, the department also stated that its

decision did not preclude TransCanada from reapplying for a Presidential Permit in the future,

although such a reapplication “will trigger ... a completely new review process.”148

As a result of that denial, instead of developing a supplemental EIS incorporating analysis

applicable to a new pipeline route through Nebraska, a new Presidential permit application

process will be required. As a result, a “new” NEPA process will be required. Although much of

the analysis and documentation will likely be the same, issuance of a draft and final EIS, and

corresponding public and agency comment periods, will be required.

Author Contact Information

Paul W. Parfomak

Specialist in Energy and Infrastructure Policy

pparfomak@crs.loc.gov, 7-0030

Linda Luther

Analyst in Environmental Policy

lluther@crs.loc.gov, 7-6852

Robert Pirog

Specialist in Energy Economics

rpirog@crs.loc.gov, 7-6847

Adam Vann

Legislative Attorney

avann@crs.loc.gov, 7-6978

Acknowledgments

The authors would like to acknowledge the contributions of Kristina Alexander, Vanessa Burrows, and Jim

Uzel to the content of this report.

146

KETV NewsWatch 7, “Uncut: KETV’s Rob McCartney Interviews President Obama,” Omaha, NE, November 1,

2011, http://www.ketv.com/video/29652519/detail.html.

147

U.S. Department of State, January 18, 2012.

148

Ibid.

Congressional Research Service

38