Evaluating the “Past Performance” of Federal Contractors: Legal Requirements and Issues

Congressional research reportFeb 5, 2015

Ask Donna

What actually matters in this document.

Text

Evaluating the “Past Performance” of Federal

Contractors: Legal Requirements and Issues

/name redacted/

Legislative Attorney

February 5, 2015

Congressional Research Service

7-....

www.crs.gov

R41562

Evaluating the “Past Performance” of Federal Contractors

Summary

Poor performance under a federal contract can have immediate consequences for contractors, who

could be denied award or incentive fees, required to pay damages, or terminated for default. In

addition, it could affect their ability to obtain future contracts because federal law generally

requires agencies to evaluate contractors’ past performance and consider past performance

information when making source selection decisions in negotiated procurements and determining

whether prospective contractors are “responsible.” “Past performance” refers to performance on

“active and physically completed contracts” and certain orders under existing contracts.

Federal law generally requires agencies to evaluate and document contractor performance on

contracts or orders whose value exceeds the simplified acquisition threshold (generally

$150,000). The evaluation must generally address the quality of the product or service supplied

by the contractor, its efforts to control costs, its timeliness and compliance with schedules, its

conduct of management or business relations, its performance in subcontracting with small

businesses, and other applicable factors (e.g., tax delinquency). The evaluation and any contractor

response comprise the past performance information that is stored in government databases (e.g.,

Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and

Integrity Information System (FAPIIS)) and may be used in future source selection decisions.

Federal law also generally requires agencies to consider contractors’ past performance when

making source selection decisions in negotiated procurements whose value exceeds the simplified

acquisition threshold. In a negotiated procurement, the contract is awarded to the offeror whose

proposal represents the “best value” for the government based on various factors identified in the

solicitation. These factors typically must include price and past performance. However, other

factors may be considered, and procuring agencies determine the weight given to various factors.

Additionally, agencies are required by law to consider whether the contractor has a “satisfactory

performance record” when determining whether the contractor is sufficiently “responsible” to be

awarded a federal contract. Agencies generally cannot award a contract without determining that

the contractor is “responsible.” While agencies are generally prohibited from repeatedly finding a

contractor nonresponsible based upon the same deficient past performance, they may debar or

suspend contractors for willful failure to perform under a contract or contracts, or for a history of

failure to perform or of unsatisfactory performance of a contract or contracts.

Reports alleging that contractors received new contracts or orders despite poor performance under

prior ones have recently prompted interest in the role that evaluations of past performance play in

contracting, as well as attempts by some Members of Congress and the Obama Administration to

strengthen requirements pertaining to performance evaluations. The 112th Congress enacted

legislation that requires the Department of Defense (P.L. 112-81) and the Federal Acquisition

Regulatory Council (P.L. 112-239) to develop “strateg[ies] for ensuring” that past performance

reports are timely, accurate and complete; and give contractors 14 days to comment on, rebut, or

supplement past performance reports. The 113th Congress also enacted legislation addressing

certain issues relating to past performance (P.L. 113-6, P.L. 113-291), although this legislation

was narrower in scope than that enacted by the 112th Congress. In addition, the Obama

Administration updated the Federal Acquisition Regulation (FAR) in 2013 to standardize the

factors used in evaluating contractors’ performance, and require that all past performance

information be entered into the Contractor Performance Assessment Reporting System (CPARS).

It made further updates to the FAR in 2014 to implement P.L. 112-81 and P.L. 112-239.

Congressional Research Service

Evaluating the “Past Performance” of Federal Contractors

Contents

Evaluating and Documenting Performance ..................................................................................... 2

Contents of Evaluations ............................................................................................................. 3

Procedures for Compiling, Posting, and Using Evaluations...................................................... 4

Contractor Challenges to Performance Evaluations .................................................................. 6

Consideration of Past Performance in Source Selection in Negotiated Procurements .................... 9

Past Performance as an Evaluation Factor .............................................................................. 11

Protesting Agency Evaluations of Past Performance............................................................... 15

Other Consideration of Past Performance in Source Selection ............................................... 16

Past Performance as a Criterion in Responsibility Determinations ............................................... 17

“Satisfactory Performance Record” As Condition for Contract .............................................. 18

Protests of Responsibility/Nonresponsibility Determinations ................................................. 19

De Facto Debarment ............................................................................................................... 20

Debarment and Suspension Under the FAR ............................................................................ 21

Tables

Table 1. Various Exchanges Potentially Involving Past Performance Information ....................... 14

Contacts

Author Contact Information........................................................................................................... 22

Congressional Research Service

Evaluating the “Past Performance” of Federal Contractors

P

oor performance under a federal contract can have immediate consequences for

contractors, who could potentially be denied award or incentive fees, required to pay

damages, or terminated for default.1 In addition, it can affect their ability to obtain future

contracts because federal law generally requires agencies to evaluate contractor’s “past

performance” and consider past performance information when making source selection decisions

in negotiated procurements and when determining whether prospective contractors are

“responsible.” “Past performance” refers to contractors’ performance on “active and physically

completed contracts” and certain orders under existing contracts.2

Reports alleging that some contractors received new contracts despite allegedly deficient

performance under prior or current contracts have recently prompted interest in the role that

evaluations of past performance play in federal contracting,3 as well as attempts by some

Members of Congress and the Obama Administration to improve agencies’ compilation and use

of past performance evaluations. The 112th Congress enacted legislation that requires the

Department of Defense (DOD) (P.L. 112-81) and the Federal Acquisition Regulatory Council

(P.L. 112-239) to develop “strateg[ies] for ensuring” that past performance reports are timely,

accurate and complete; and would give contractors 14 days to comment on, rebut, or supplement

past performance reports. The 113th Congress also enacted legislation addressing certain issues

relating to past performance, although such legislation was narrower in scope than that enacted in

the 112th Congress.4 In addition, the Obama Administration updated the Federal Acquisition

Regulation (FAR) in 2013 to standardize the factors used in evaluating contractors’ performance,

and require that all past performance information be entered into the Contractor Performance

Assessment Reporting System (CPARS).5 It made further updates to the FAR in 2014 to

implement P.L. 112-81 and P.L. 112-239.6 Contractors, however, have expressed concern that

increased emphasis on past performance information could lead to de facto debarment or

“blacklisting” of contractors.7

1

See 48 C.F.R. §§11.500-11.503 (liquidated damages); 48 C.F.R. §§16.401-16.406 (award and incentive fees); 48

C.F.R. §§49.401-49.406 (termination for default).

2

48 C.F.R. §2.101. As used here, an “order” is a request for work under an existing contract.

3

For example, concerns about contractors’ past performance factored significantly in discussions about the problematic

roll-out of HealthCare.gov. See generally archived CRS Report R43368, Contractors and HealthCare.gov: Answers to

Frequently Asked Questions , by (name redacted), (name redacted), and (name redacted).

4

See Consolidated and Further Continuing Appropriations Act, 2013, P.L. 113-6, §520(d), 127 Stat. 370 (March 26,

2013) (requiring the Department of Homeland Security Inspector General to include past performance problems in its

review of agency contracts awarded using other than “full and open competition”); Carl Levin and Howard P. “Buck”

McKeon National Defense Authorization Act for Fiscal Year 2015, P.L. 113-291, §821,—Stat.—(December 19, 2014)

(making failure to comply with a subcontracting plan under the DOD Comprehensive Subcontracting Plan Test

Program a factor in evaluations of past performance), id. at §824,—Stat.—(requiring that DOD regulations regarding

reverse auctions provide for past performance information created by third parties conducting reverse auctions on the

department’s behalf be made available to offerors).

5

See Dep’t of Defense, Gen. Servs. Admin., & Nat’l Aeronautics & Space Admin., Documenting Contractor

Performance: Final Rule, 78 Fed. Reg. 46783 (August 1, 2013).

6

See also Dep’t of Defense, Gen. Servs. Admin., & Nat’l Aeronautics & Space Admin., Contractor Comment Period,

Past Performance Evaluations,: Final Rule, 79 Fed. Reg. 31197 (May 30, 2014) (implementing changes made by P.L.

112-81 and P.L. 112-239).

7

See, e.g., Tom Spoth, Contractor Performance Data to Become Public, Federal Times, August 6, 2010, available at

http://www.federaltimes.com/article/20100806/ACQUISITION03/8060301; Matthew Weigelt, New Law Puts

Contractor Performance in Public Spotlight, Wash. Tech., August 5, 2010, available at

http://washingtontechnology.com/articles/2010/08/05/obama-opens-fapiis-to-the-public.aspx. Such contractors worry

that, as the weight given to past performance information increases, contractors will be effectively excluded from future

contract opportunities based upon information about them that they may not be aware of, or whose accuracy and

(continued...)

Congressional Research Service

1

Evaluating the “Past Performance” of Federal Contractors

This report provides an overview of existing legal requirements pertaining to past performance,

including the issues raised by contractors’ attempts to challenge (1) agency evaluations of their

past performance, (2) source selection decisions based, in part, on consideration of past

performance information, and (3) responsibility determinations.

Evaluating and Documenting Performance

While agencies have long informally evaluated contractors’ performance and generally kept some

records regarding this performance, at least during the term of the contract, they were not

required to compile evaluations of past performance until 1993. Then, as part of reforms requiring

agency consideration of past performance in certain source selection decisions, discussed below,

the Office of Federal Procurement Policy (OFPP) directed federal agencies to “[p]repare

evaluations of contractors’ performance on all new contracts over $100,000.”8 One year later,

Congress enacted the Federal Acquisition Streamlining Act (FASA) of 1994, which established a

statutory basis for agency evaluation of past performance.9 Among other things, FASA required

OFPP to prescribe

policies for the collection and maintenance of information on past contract performance that,

to the maximum extent practicable, facilitate automated collection, maintenance, and

dissemination of information and provide for ease of collection, maintenance, and

dissemination of information by other methods, as necessary.10

OFPP met this requirement, in part, by promulgating regulations regarding “contractor

performance information” in Subpart 42.15 of the FAR.11 These regulations, as amended,

(...continued)

objectivity they cannot meaningfully challenge (e.g., information communicated between agency personnel but not

incorporated into a formal evaluation of contractor performance). Commentators have also noted that increased

consideration of past performance can be seen to interject additional subjectivity into the procurement process. See,

e.g., Kimberly R. Heifetz, Striking a Balance Between Government Efficiency and Fairness to Contractors: Past

Performance Evaluations in Government Contracts, 51 Admin. L. Rev. 235, 254 (1998). It has been suggested that this

subjectivity could potentially give rise to more bid protests. See, e.g., Michael J. Davidson, Protest Challenges to

Integrity-based Responsibility Determinations, 14 Fed. Cir. Bar J. 473 (2004/2005). It has also been noted that not

every allegedly poor performance by a contractor is the contractor’s fault. See, e.g., id. at 502 (“Contractors are

frequently under investigation for alleged [misconduct], and in a large percentage of those cases the allegations are

either unfounded or unproven.”); George M. Coburn, Unfavorable Past Performance Determinations as De facto

Debarment, 31 Proc. Law. 26, 27 (1996) (“Experience shows that a contractor’s apparent ‘seriously deficient’

performance ... is sometimes found ... to be a performance failure that is beyond the contractor’s control and without

fault or negligence, and on occasion, one for which the Government is contractually liable.”).

8

Exec. Office of the Pres., Office of Mgmt. & Budget, Office of Fed. Procurement Policy, Final Issuance of Policy

Letter 92-5, 58 Federal Register 3573, 3575 (January 11, 1993). OFPP Policy Letter 92-5 further added that

“[e]valuations shall be made during contract performance, as required for contract administration purposes and at the

time the work under the contract is completed.” Id. Previously, the FAR requireed evaluations of contractor

performance only “at the time the work under the contract or order is completed,” or on an interim basis, in the case of

multiyear contracts. 48 C.F.R. §42.1502(a) (2012). However, the FAR was amended in August 2013 to require, among

other things, that past performance be evaluated “at least annually and at the time the work under a contract or order is

completed.” Documenting Contractor Performance, 78 Fed. Reg. at 46788 (codified at 48 C.F.R. §42.1502(a)).

9

P.L. 108-355, §1091(b), 108 Stat. 3272 (October 13, 1994) (codified at 41 U.S.C. §1126).

10

Id.

11

Gen. Servs. Admin., Nat’l Aeronautics & Space Admin., & Dep’t of Defense, Federal Acquisition Regulation; Past

Performance Information, 60 Federal Register 16718, 16719-20 (March 31, 1995).

Congressional Research Service

2

Evaluating the “Past Performance” of Federal Contractors

currently prescribe the content of contractor performance evaluations, as well as procedures for

the compilation, posting, and use of such evaluations.

The requirement that agencies evaluate contractor performance was imposed, in part, because

“performance assessment is a basic ‘best practice’ for good contract administration, and is one of

the most important tools available for ensuring good contract performance.”12 Additionally,

Congress and the executive branch hoped that written evaluations of contractor performance

would “improve the amount and quality of performance information available to source selection

teams,” which would, in turn, “enable agencies to better predict the quality of, and customer

satisfaction with, future work.”13 However, although OFPP, in particular, anticipated that agencies

would ultimately be able to rely almost exclusively on agency performance evaluations in their

source selection decisions,14 this does not seem to have occurred, as discussed below.15

Contents of Evaluations

Under Subpart 42.15 of the FAR, agencies are generally required to evaluate contractors’

performance on contracts or orders valued in excess of $150,00016 ($30,000 for architect-engineer

contracts, $650,000 for construction contracts) “at least annually and at the time the work under a

contract or order is completed.”17 Prior to August 2013, Subpart 42.15 left the content of this

evaluation largely to the agency’s discretion, requiring only the evaluation of the contractor’s

performance on and efforts to achieve any small business subcontracting goals.18 Agencies were

encouraged to consider other factors, such as “the contractor’s record of conforming to contract

12

Exec. Office of the Pres., Office of Mgmt. & Budget, Office of Fed. Procurement Policy, Best Practices for

Collecting and Using Current and Past Performance Information, May 2000, at Foreword, available at

http://www.whitehouse.gov/omb/best_practice_re_past_perf.

13

Id.

14

Office of Fed. Procurement Policy, A Guide to Best Practices for Past Performance, at 19 & 36 (1995) (copy on file

with the author) (encouraging agencies to rely on evaluations completed pursuant to Subpart 42.15 of the FAR in the

source selection process “to the maximum extent practicable”).

15

See infra notes 89 to 91 and accompanying text.

16

This amount generally represents the simplified acquisition threshold. However, in the case of supplies or services to

be used in support of a contingency operation or to facilitate defense against or recovery from nuclear, biological,

chemical, or radiological attack, the simplified acquisition threshold increases to $300,000 for contracts to be awarded

and performed inside the United States, and $1 million for contracts to be awarded and performed outside the United

States. 48 C.F.R. §2.101.

17

48 C.F.R. §42.1502(b) (general requirement); 48 C.F.R. §42.1502(e) (construction contracts); 48 C.F.R. §42.1502(f)

(architect-engineer contracts). Agencies must also evaluate performance on any construction or architect-engineer

contract that is terminated for default, regardless of its value, as well as on orders valued in excess of $150,000 placed

under the Federal Supply Schedules or an interagency contract. 48 C.F.R. §42.1502(c) & (f). They are, however, not

required to evaluate performance on orders valued in excess of $150,000 under single-agency task or delivery order

contracts, although they may conduct such evaluations if doing so “would produce more useful past performance

information for source selection officials.” 48 C.F.R. §42.1502(d). It should also be noted that agencies are not

prohibited from evaluating contractors’ past performance on contracts whose value is below the relevant monetary

thresholds, even if the contract does not expressly provide for such evaluations. See, e.g., Jacqueline R. Sims LLC v.

United States, No. 13-174C, No. 13-196C, Opinion and Order (Fed. Cl., February 25, 2014) (copy on file with the

author) (rejecting the argument that the agency exceeded its authority under the FAR, and breached the contract’s

terms, by preparing performance evaluations for contracts whose value was below the simplified acquisition threshold).

18

48 C.F.R. §42.1502(g) (2012). Section 8(d) of the Small Business Act requires that all contracts whose expected

value exceeds $650,000 ($1.5 million for construction contracts) incorporate a “subcontracting plan” that provides the

“maximum practicable opportunity” for various types of small businesses to participate in performing the contract. See

15 U.S.C. §637(d)(4)(D) (negotiated procurements); 15 U.S.C. §637(d)(5)(B) (sealed-bid procurements).

Congressional Research Service

3

Evaluating the “Past Performance” of Federal Contractors

requirements and to standards of good workmanship,” but were not obligated to do so under the

FAR provisions then in effect.19 The situation changed in August 2013, however, when the FAR

was amended to require that evaluation factors for each assessment generally

include, at a minimum, the following:

(i) [t]echnical (quality of product or service)[;]

(ii) [c]ost control [;]

(iii) [s]chedule/timeliness[;]

(iv) [m]anagement or business relations[;]

(v) [s]mall business subcontracting ...[; and]

(vi) [o]ther (as applicable) (e.g., late or nonpayment to subcontractors, trafficking violations,

tax delinquency, failure to report in accordance with contract terms and conditions, defective

cost or pricing data, terminations, suspension and debarments).20

Other factors could be considered in the agency’s discretion. Any required or other factors are

typically incorporated into a “performance assessment clause” or similar clause in the contract.21

Prior to August 2013, such clauses established the categories that agencies would use in rating

performance and the metrics used in applying particular ratings to specific conduct, both of which

could be quite broad.22 However, the 2013 FAR amendments standardized the rating categories to

be used by agencies, as well as defined how each rating (e.g., exceptional, marginal) is to be

used.23

Procedures for Compiling, Posting, and Using Evaluations

Subpart 42.15 of the FAR also requires agencies to follow certain procedures when compiling,

posting, and using performance evaluations. The contracting officer, or someone else who has

been delegated this responsibility, is to prepare the evaluation.24 However, the evaluation should

19

48 C.F.R. §42.1501 (2012). When the FAR was initially revised to require evaluation of contractor performance,

some contractors and commentators objected to certain of these criteria, most notably the contractor’s “commitment to

customer satisfaction” and “business-like concern for the customer’s interest,” on the grounds that the criteria are

inherently subjective. See, e.g., Unfavorable Past Performance Determinations, 31 Proc. Law. at 27. Despite such

concerns, however, their implementation does not appear to have generated particular controversy, beyond the

controversy generally associated with the issuance of allegedly biased or erroneous performance evaluations. See infra

note 39 and accompanying text.

20

48 C.F.R. §42.1503(b)(2)(i)-(vii).

21

See, e.g., Colonna’s Shipyard, Inc., ASBCA No. 56940, 2010-2 B.C.A. ¶ 34,494 (2010) (contractor’s performance to

be evaluated based on “technical (quality of product),” “schedule (timeliness of performance)” and “management”).

22

See, e.g., id. (performance to be rated as exceptional, very good, satisfactory, or marginal, with the marginal rating

used for performance that “does not meet some contractual requirements. The contractual performance of the element

or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective

actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.”).

23

See 48 C.F.R. Tables 42-1 & 42-2.

24

48 C.F.R. §42.1503(a)(1)-(2). If no other person is designated, the contracting officer is responsible for performance

evaluations. 48 C.F.R. §42.1503(a)(2).

Congressional Research Service

4

Evaluating the “Past Performance” of Federal Contractors

generally be based on the experiences of the technical office, the program management office,

and quality assurance and end users, where appropriate, as well as those of the contracting

office.25 A copy of the evaluation should be provided to the contractor “as soon as practicable

after [its] completion,”26 with the contractor then having “up to 14 calendar days ... to submit

comments, rebutting statements, or additional information.”27 Prior to May 2014, contractors had

“a minimum of 30 days” to submit such information.28 However, the FAR was amended in May

2014 to shorten this period, in conformity with the requirements of P.L. 112-81 and P.L. 112-239.

Disagreements between the contractor and the contracting officer are reviewed “at a level above

the contracting officer,” although “[t]he ultimate conclusion on the performance evaluation is a

decision of the contracting agency.”29

The evaluation and any response from the contractor should be marked “source selection

information” and submitted to the Contractor Performance Assessment Reporting System

(CPARS),30 from which it is “automatically transmitted” to the Past Performance Information

Retrieval System (PPIRS).31 Marking the evaluation and response as “source selection

information” ensures that they cannot be released to anyone other than eligible government

personnel, or the contractor whose performance was evaluated, for at least three years.32 Because

of this limitation on access to performance evaluations, access to the CPARS and PPIRS

databases are similarly limited, and information about a contractor in these databases can only be

viewed by authorized government personnel or the contractor in question.33 Access to the Federal

Awardee Performance Integrity Information System (FAPIIS), which includes PPIRS information

25

48 C.F.R. §42.1503(a)(1)(i).

48 C.F.R. §42.1503(d).Delays of several months in completing evaluations would not necessarily be seen to be

impermissible under the FAR. See, e.g., Gray Owl Servs., Inc. v. United States, No. 13-963C, 2014 U.S. Claims LEXIS

793 (Fed. Cl., August 14, 2014). However, depending upon the circumstances, delays of several years could potentially

be seen to raise issues. See, e.g., Public Warehousing Co. K.S.C., ASBCA No. 58078, 2013-1 B.C.A. ¶ 35,460

(declining to dismiss a contractor’s claim regarding a performance evaluation whose issuance had been delayed for four

years “[b]ecause the [contracting officer’s] commitment to issue a decision by a specific date ... was not met and was in

actuality contingent upon the resolution of the criminal and civil cases filed against [the contractor in federal district

court].”); Metag Insaat Ticaret A.S., ASBCA No. 58616, 2013-1 B.C.A. ¶ 35,454 (“We find this extended passage of

time without a [contracting officer’s] decision to be unreasonable given the nature of the claim, and supports an appeal

on a deemed denial basis.”).

27

48 C.F.R. §42.1503(d).

28

48 C.F.R. §42.1503(b) (2012).

29

48 C.F.R. §42.1503(d). Some contracts contain language to the effect that the final performance rating is “the

unilateral determination of the reviewing official” and not subject to dispute or appeal beyond the agency. See, e.g.,

Colonna’s Shipyard, Inc., ASBCA No. 56940, 2010-2 B.C.A. ¶ 34,494 (2010). However, similar language has been

found to be unenforceable when used in other contexts. See, e.g., Burnside-Ott Aviation Training Center v. Dalton, 107

F.3d 854 (Fed. Cir. 1997) (finding that certain award fee determinations are reviewable notwithstanding contract

language like that quoted above), aff'g Burnside-Ott Aviation Training Center, ASBCA No. 43184, 96-1 B.C.A. ¶

28,102 (1996); Puyallup Tribe of Indians, ASBCA No. 29802, 88-2 B.C.A. ¶ 20,640 (contract’s sovereign immunity

provision cannot nullify the disputes clause), aff’d F.2d 1096 (Fed. Cir. 1989). See also infra notes 43 to 55 and

accompanying text.

30

48 C.F.R. §42.1503(d).

31

48 C.F.R. §42.1503(f).

32

41 U.S.C. §2102(a) (prohibiting disclosure of source selection information); 41 U.S.C. §2101(7) (defining “source

selection information”). See also 48 C.F.R. §42.1503(d) (“Disclosure of such information could cause harm both to the

commercial interest of the Government and to the competitive position of the contractor being evaluated as well as

impede the efficiency of Government operations.”)

33

See generally CRS Report R43111, Transforming Government Acquisition Systems: Overview and Selected Issues,

by (name redacted).

26

Congressional Research Service

5

Evaluating the “Past Performance” of Federal Contractors

along with contractor-submitted information and information from other federal databases, was

originally similarly limited.34 However, although Congress subsequently required that most

FAPIIS information be made publicly available on the web,35 past performance information was

explicitly exempted from such disclosure because of its protected status as source selection

information.36

Subpart 42.15 of the FAR further requires that agencies “use” recent evaluations of past

performance stored in PPIRS,37 but it does not specify for what they are to be used. This

provision presumably refers to consideration of agency past performance evaluations in source

selection decisions, as discussed in the following section. However, nothing in Subpart 15.3 of

FAR, which generally governs use of past performance as an evaluation factor, expressly requires

consideration in source selection decisions of the past performance evaluations that agencies are

required to complete under Subpart 42.15.38

Contractor Challenges to Performance Evaluations

Because of the potential use of agency performance evaluations in source selection decisions,

contractors are generally concerned about the contents of their evaluations and want to ensure that

these evaluations are accurate and unbiased.39 However, their ability to challenge their

evaluations outside the agency was historically limited, and they could generally only allege

improprieties in their evaluations in the course of bid protests challenging agency source selection

decisions based, in part, on the contents of these evaluations.40 This arguably afforded contractors

little relief from erroneous or biased evaluations because (1) the focus of the protest is upon the

34

See Duncan Hunter National Defense Authorization Act for FY2009, P.L. 110-417, §§871-873, 122 Stat. 4555-58

(October 14, 2008). Among other things, FAPIIS also includes brief descriptions of all civil, criminal, and

administrative proceedings involving federal contracts that resulted in a conviction or finding of fault, as well as all

terminations for default, administrative agreements, and nonresponsibility determinations relating to federal contracts,

within the past five years for all persons holding a federal contract or grant worth $500,000 or more.

35

See Consolidated Appropriations Act, 2010, P.L. 111-212, §3010, 124 Stat. 2340 (July 29, 2010) (“Section 872(e)(1)

of the Clean Contracting Act of 2008 (subtitle G of title VIII of Public Law 110–417 ... is amended by adding at the

end the following: ‘In addition, the Administrator shall post all such information, excluding past performance reviews,

on a publicly available Internet website.’”) (emphasis added).

36

48 C.F.R. §42.1503(d). See also Dep’t of Defense, Gen. Servs. Admin., & Nat’l Aeronautics & Space Admin.,

Federal Awardee Performance and Integrity Information System: Final Rule, 75 Federal Register 14059, 14063 (March

23, 2010).

37

48 C.F.R. §42.1503(g) (“Agencies shall use the past performance information in PPIRS that is within three years (six

for construction and architect-engineer contracts) of the completion of performance of the evaluated contract or order,

and information contained in the Federal Awardee Performance and Integrity Information System (FAPIIS), e.g.,

terminations for default or cause.”) (emphasis added). However, Subpart 42.15 elsewhere states that “[t]hese

evaluations may be used to support future award decisions.” 48 C.F.R. §42.1503(d).

38

Policy guidance from OFPP does, however, encourage agencies to use performance evaluations completed under

Subpart 42.15 of the FAR for source selection purposes. See supra note 14 and accompanying text.

39

See, e.g., Todd Constr., L.P. v. United States, 85 Fed. Cl. 34, 36 (2008) (“Given the increasing importance of

performance reviews and prejudice to contractors from erroneous ratings, there should be some judicial forum available

to consider challenges to the fairness and accuracy of evaluations.”).

40

A “bid protest” is a formal, written objection to an agency’s solicitation for bids or offers, cancelation of a

solicitation, or award or proposed award of a contract. 31 U.S.C. §3551(1)(A)-(D). For more on bid protests, see CRS

Report R40228, GAO Bid Protests: An Overview of Time Frames and Procedures, by (name redacted) and (name

redacted). More recently, GAO has suggested that bid protests are not the proper forum to dispute the substance of

performance evaluations required under Subpart 42.15 of the FAR. See Ocean Tech. Servs., Inc., B-288659 (November

27, 2001).

Congressional Research Service

6

Evaluating the “Past Performance” of Federal Contractors

reasonableness of the contracting officer’s source selection decision, not the reasonableness of the

evaluation of the contractor’s past performance,41 and (2) the judicial and administrative tribunals

hearing bid protests give substantial deference to the contracting officer’s determinations in the

source selection process.42

More recently, however, disputes over performance evaluations have come to be seen as potential

claims under the Contract Disputes Act (CDA) of 1978. This trend began in 2004, when the U.S.

Court of Federal Claims issued its decision in Record Steel & Construction, Inc. v. United

States.43 The contractor in Record Steel had sued seeking, among other things, a declaratory

judgment that its evaluation be “corrected to reflect accurately” its performance under the

contract.44 The government countered by asserting that the court lacked jurisdiction because,

while the Tucker Act waives the government’s sovereign immunity as to “claims” arising under

the CDA, Record Steel’s letter to the contracting officer requesting that its performance rating be

reevaluated and changed did not constitute a claim since it did not seek relief “as a matter of

right” or arising from or related to the contract.45 The court disagreed.46 It found that it had

jurisdiction, assuming the other requirements of the CDA were met,47 because Record Steel’s

letter to the contracting officer constituted a “claim” as that term is defined in the FAR.48 In

reaching this conclusion, the court found that a request for reevaluation and/or change of

performance ratings was a “claim of right” because the FAR requires agencies to prepare such

evaluations for contracts of the size and type held by Record Steel.49 The court also rejected the

government’s assertion that the precedent of the boards of contract appeals, which had long

41

See, e.g., BLR Group of Am. v. United States, 84 Fed. Cl. 634, 647 (2008) (“It is conceivable that by the time the

contractor is able to challenge the evaluation, ... fading memories could hinder the contractor’s chances of success.”).

In addition, the contracting officer making the source selection decision is not necessarily the same person, or even

with the same agency, that produced the allegedly biased or erroneous evaluation of the contractor’s performance.

42

See infra notes 99 to 104 and accompanying text. Some commentators also suggest that challenges to past

performance evaluations raised during bid protests make the procurement process less efficient by disrupting agency

operations. See BLR Group, 84 Fed. Cl. at 647 (“The efficiency of the procurement process would be compromised by

forcing a contractor to protest an issue that could have been resolved at an earlier time under the [Contract Disputes

Act].”).

43

62 Fed. Cl. 508 (2004).

44

Id. at 509.

45

Id. 518-19. As sovereign, the United States is immune to suit without its consent. See, e.g., United States v.

Sherwood, 312 U.S. 584, 586 (1941). The Tucker Act waives this immunity as to claims against the United States

founded in the U.S. Constitution, federal statutes or regulations, or express or implied contracts with the United States.

28 U.S.C. §1491(a)(1). It also provides the court with “jurisdiction to render judgment upon any claim by or against, or

dispute with, a contractor arising under section 10(a)(1) of the Contract Disputes Act of 1978, including ...

nonmonetary disputes in which a decision of the contracting officer has been issued under section 6 of that Act.” 28

U.S.C. §1491(a)(2).

46

Record Steel, 62 Fed. Cl. at 518.

47

For example, for the Court of Federal Claims to have jurisdiction over a CDA “claim,” the claim must have been

made in writing and submitted to the contracting officer for a decision. See 41 U.S.C. §7103(a).

48

Record Steel, 62 Fed. Cl. at 518. The CDA itself does not define “claim,” nor did the contract in question. The FAR,

however, defines a “claim” as “written demand or written assertion by one of the contracting parties seeking, as a

matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief

arising under or relating to the contract.” 48 C.F.R. §2.101 (definitions). See also 48 C.F.R. §52.233-1(c) (standard

Disputes clause used in federal procurement contracts).

49

Record Steel, 62 Fed. Cl. at 519 (noting that FAR Subpart 36.201(a)(1), which governs contracting for construction,

required the agency to prepare a performance evaluation).

Congressional Research Service

7

Evaluating the “Past Performance” of Federal Contractors

declined to exercise jurisdiction over challenges to performance evaluations, meant that the court

lacked jurisdiction.50

Then, on May 6, 2010, the Armed Services Board of Contract Appeals (ASBCA) also found that

it has jurisdiction over contractor challenges to performance evaluations.51 Previously, in a series

of decisions issued between 1991 and 2006, the ASBCA and other boards of contract appeals had

found that they lacked jurisdiction in such cases because a “performance evaluation under a

contract is an administrative matter not a Government claim, and a contractor’s request that a

contracting officer change an evaluation is not a contractor’s claim.”52 Like the decision in

Record Steel, the May decision of the ASBCA relied on the FAR’s definition of “claim” to find

that the contractor’s request that the board “rescind” the contractor’s evaluation constituted a

claim, although the board grounded the contractor’s entitlement to a “fair and accurate”

performance evaluation in the terms of the contract and the “implied ... duty of good faith and fair

dealing inherent in every contract,” not the FAR.53 A subsequent decision by the ASBCA

expanded upon the May decision by suggesting that earlier board decisions had been

misconstrued as holding that the boards always lacked jurisdiction over contractor challenges to

performance evaluations,54 and that the government’s duty to provide an “accurate and fair”

performance evaluation arises from both the FAR and the contract.55

Nonetheless, despite these recent decisions finding that the federal courts and boards of contract

appeals have jurisdiction to hear contractor challenges to allegedly erroneous or biased

performance evaluations, it is presently unclear what, if any, relief they might be able to grant.

This question was first directly addressed in the Court of Federal Claims’ decision on July 22,

50

Id. at 521. However, a subsequent decision of the Court of Federal Claims distinguished between performance

evaluations and PPIRS entries, finding that, while contractors are entitled by the FAR to a “fair and accurate”

performance evaluation, they are not similarly entitled to a “properly formatted PPIRS entry” since the relevant

regulations and policy guidelines “do not address the manner in which a PPIRS entry is displayed or formatted.” BLR

Group, 84 Fed. Cl. at 639. This decision also suggested that final Contractor Performance Assessment Reports

(CPARs) are not final decisions of the contracting officer for purposes of the CDA because they are issued by a

reviewing official, who is above the contracting officer, not the contracting officer. However, while only final decisions

of the contracting officer are generally disputable, the plaintiff’s claim survived because, assuming the reviewing

official is seen as issuing the performance evaluation, the contracting officer issues no decision, and the contracting

officer is otherwise required by the CDA to issue a decision “within a reasonable time,” or the claim is deemed denied.

BLR Group, 84 Fed. Cl. at 648.

51

Versar, Inc., ASBCA No. 56857, 2010-1 B.C.A. ¶ 34,437 (2010).

52

TLT Constr. Corp., ASBCA No. 53769, 02-2 B.C.A. ¶ 31,969 (2002). See also Aim Constr., ASBCA No. 52540, 071 BCA ¶ 33,466 (2006); Franklin’s Cleaning & Supply Co., GSBCA No. 16527, 06-1 BCA ¶ 33,139 (2005); G.

Bliudzius Contractors, ASBCA No. 42365, 92-1 BCA ¶ 24,605 (1991); Konoike Constr. Co., ASBCA No. 40910, 91-3

BCA ¶ 24,170 (1991).

53

Versar, Inc., ASBCA No. 56857, 2010-1 B.C.A. ¶ 34,437 (2010) (“[T]he Air Force was contractually obligated to

complete a performance assessment in good faith that was fair and accurate.”). This reliance on the “implied ... duty of

good faith and fair dealing inherent in every contract” is potentially significant because it could encompass aspects of

the performance evaluation process that are not explicitly addressed in the contract or regulations (e.g., the formatting

of PPIRS entries).

54

Colonna’s Shipyard, Inc., ASBCA No. 56940, 2010-2 B.C.A. ¶ 34,494 (2010). According to the board, the initial

case involving a past performance evaluation found only that the issuance of a performance evaluation, per se, did not

constitute a claim. The board in Colonna’s Shipyard also noted that a subsequent case found that the board had

jurisdiction when a performance rating claim is based upon a contract’s disputed terms. See Sundt Construction, Inc.,

ASBCA No. 56293, 09-1 BCA ¶ 34,084 (2009).

55

Colonna’s Shipyard, Inc., ASBCA No. 56940, 2010-2 B.C.A. ¶ 34,494 (2010). The contractor here also noted that

the government had an implied duty to produce an unbiased and accurate performance evaluation, but the board did not

address this issue.

Congressional Research Service

8

Evaluating the “Past Performance” of Federal Contractors

2009, in Todd Construction, L.P. v. United States.56 Todd Construction had asked the court to (1)

determine that the Air Force’s final evaluation of its performance was unlawful and should be set

aside and (2) direct the Air Force to remove the final performance evaluation from the

Construction Contractor Appraisal Support System (CCASS).57 The court, however, found that

neither form of relief was within its authority.58 It found that, while it has inherent authority to

grant declaratory relief,59 a declaration of rights would not resolve the case at hand because it

would not cause the performance evaluation to be changed or removed from CCASS.60 It

similarly found that its statutory authority to remand the case to the agency with directions that

the agency take “proper and just” steps could only be used to direct the agency’s attention to

matters that the court believes require further action to create an adequate record of the agency’s

decision, not to mandate particular factual determinations.61 Subsequent board of contract appeals

decisions also found that the boards lack authority to order an agency to rescind a poor

performance evaluation or revise the agency’s evaluation.62

Consideration of Past Performance in Source

Selection in Negotiated Procurements

Although not expressly required to do so, agencies appear to have considered past performance

when selecting vendors in “negotiated procurements” since at least the 1960s.63 A negotiated

56

88 Fed. Cl. 235 (2009). A December 9, 2008, decision in this case had found that the court had jurisdiction over the

contractor’s challenge to its performance evaluation on the same grounds discussed in Record Steel. See 85 Fed. Cl. 34

(2008).

57

Todd Constr., 88 Fed. Cl. at 248. Prior to July 1, 2009, agencies were not required to submit their performance

evaluations to PPIRS, and some, such as DOD, maintained their own databases (e.g., CCASS).

58

Id. at 243-44.

59

Id. (quoting Ex Parte McCardle, 74 U.S. (7 Wall.) 506, 514 (1868) (“Jurisdiction is power to declare the law.”)).

60

Id. at 244 (“If the Court possess only the power to say ‘no, the performance evaluation is not fair and accurate,’ but

no authority to order any other action, the plaintiff would be essentially no better off than it is today. Even if the Court

could say ‘the performance evaluation should be set aside,’ but had no power to require any entity to take any action on

that conclusion, the declaratory relief would be meaningless.”). In so finding, the court distinguished prior cases, where

it had granted declaratory relief, from the present case by characterizing the prior cases as involving “live disputes” of

the “yes” or “no” sort, where “the consequences flowing from [the court’s] answer did not require further intervention

from a court or board.” Id. (citing CW Gov’t Travel, Inc. v. United States, 63 Fed. Cl. 369, 387-90 (2004) (declaring

whether the contract entitled the contractor to be the exclusive service provider); Alliant Techsystems, Inc. v. United

States, 178 F.3d 1260, 1271 (Fed. Cir. 1999) (declaring whether the exercise of an option was valid); Malone v. United

States, 849 F.2d 1441, 1445 (Fed. Cir. 1988) (declaring whether a termination for default was valid).

61

Todd Constr., 88 Fed. Cl. at 244-46. See 28 U.S.C. §1491(a)(2) (“In any case within its jurisdiction, the court shall

have the power to remand appropriate matters to any administrative or executive body or official with such direction as

it may deem proper and just.”). In its 2009 decision, the court granted Todd Construction the right to amend its

complaint, which the court had characterized as “not contain[ing] sufficient factual allegations to suggest entitlement to

remand,” in light of the recent decisions by the Supreme Court in Bell Atlantic Corp. v. Twombly and Ashcroft v. Iqbal.

88 Fed. Cl. at 249. Subsequently, in 2010, the court found that revised complaint failed to state a basis on which relief

could be granted. See Todd Constr., L.P. v. United States, 94 Fed. Cl. 100, 116 (2010), aff’d by, 656 F.3d 1306 (Fed.

Cir. 2011).

62

Colonna’s Shipyard, Inc., ASBCA No. 56940, 2010-2 B.C.A. ¶ 34,494 (2010) (contractor seeking a declaration that

its performance scores are erroneous and a violation of the contract, as well as remand to the contracting officer with

instructions or advice on correcting the evaluation); Versar, Inc., ASBCA No. 56857, 2010-1 B.C.A. ¶ 34,437 (2010)

(contractor seeking rescission of the performance evaluation).

63

See, e.g., Educ. Servs., B-156860 (July 26, 1965) (request for proposals (RFP) stating that NASA would solicit

information about prospective contractors’ past performance from all available government sources and consider this

(continued...)

Congressional Research Service

9

Evaluating the “Past Performance” of Federal Contractors

procurement is one in which the contract is awarded to the vendor whose proposal represents the

“best value” for the government.64 This is not necessarily the vendor whose proposal has the

lowest price, but rather the vendor whose proposal represents the greatest overall benefit to the

government given its price, technical merit, and relationship to other evaluation criteria specified

in the request for proposals (RFP).65 Such consideration of past performance in source selection

decisions was not, however, standardized or required until the mid-1990s.66 Then, in 1993, OFPP

issued guidelines that required agencies to consider past performance information in all

negotiated procurements valued in excess of $100,000.67 This requirement was given a statutory

basis one year later, when Congress enacted FASA.68 FASA directed OFPP to promulgate

“standards for evaluating past performance with respect to cost (when appropriate), schedule,

compliance with technical or functional specifications, and other relevant performance factors

that facilitate consistent and fair evaluation by all executive agencies.”69 OFPP did so by

promulgating regulations in 1995-1997 regarding consideration of past performance information

in negotiated procurements.70 These regulations were codified in FAR Subpart 15.3 and fully took

effect in 1999.71 Subpart 15.3, as amended, currently governs use of past performance as an

evaluation factor in negotiated procurements.

Congress and the executive branch required agencies to consider past performance in source

selection decisions in the hope that the government would obtain better performance under its

contracts—and better value for its procurement dollars—by shifting the basis of its source

selection decisions. Previously, agencies conducting negotiated procurements had relied heavily

on what some commentators described as “complex technical and cost proposals,” which these

commentators asserted had “no correlation to the contractor’s ability to perform the job.”72

(...continued)

information in its evaluation).

64

See 48 C.F.R. §15.101 (best value as the goal of negotiated procurements); 48 C.F.R. §2.101 (defining “best value”).

65

Defense agencies were first authorized to conduct negotiated procurements in certain circumstances in 1948. Armed

Services Procurement Act, P.L. 80-413, 62 Stat. 21 (February 19, 1948). Civilian agencies received similar

authorization in 1949. Federal Property and Administrative Services Act, P.L. 81-152, 63 Stat. 377 (June 30, 1949).

This authority was subsequently expanded when Congress enacted the Competition in Contracting Act of 1984. See

P.L. 98-369, §§2701-2753, 98 Stat. 1175 (July 18, 1984).

66

Previously, in 1986, Congress enacted legislation requiring defense agencies to consider “quality” in every source

selection decision in which cost/price is not the only factor considered. See Joint Resolution Making Continuing

Appropriations for the Fiscal Year 1987, and for Other Purposes, P.L. 99-591, §101 [Title IX, §924(a)-(b)], 100 Stat.

3341-153 (October 30, 1986) (codified at 10 U.S.C. §2305). “Quality” was defined as including the “prior experience

of the offeror.” Id. However, prior experience can be distinguished from past performance, and this provision was

repealed by FASA. See infra note 105; P.L. 103-355, §1013(a), 108 Stat. 3255 (October 13, 1994).

67

58 Federal Register 3573.

68

P.L. 108-355, §1091(b), 108 Stat. 3272 (October 13, 1994) (codified at 41 U.S.C. §1126).

69

Id.

70

Dep’t of Defense, Gen. Servs. Admin., & Nat’l Aeronautics & Space Admin., Part 15 Rewrite: Contracting by

Negotiation and Competitive Range Determination, 62 Federal Register 51224 (September 30, 1997); 60 Federal

Register at 16718-19.

71

The requirement was phased in, with procurements with higher values being subject to the requirement sooner than

those with lower values. See, e.g., 60 Federal Register at 16719 (procurements valued in excess of $1 million subject to

the requirement July 1, 1995; those valued in excess of $500,000, by July 1, 1997; and those valued in excess of

$100,000, by January 1, 1999).

72

Nathanael Causey, Past Performance Information, De facto Debarments, and Due Process: Debunking the Myth of

Pandora’s Box, 29 Pub. Cont. L.J. 637, 640 (1999/2000). See also Steven Kelman, Procurement and Public

Management: The Fear of Discretion and the Quality of Government Performance 40 (1990) (quoting a government

employee as saying “We deal with written lies,” when describing his agency’s reliance on contractors’ technical

(continued...)

Congressional Research Service

10

Evaluating the “Past Performance” of Federal Contractors

Consideration of past performance in source selection decisions was seen as an alternative to

reliance on such proposals, especially by those who characterized past performance information

as the best indicator of a contractor’s ability to provide quality goods and services at a reasonable

cost.73 Such consideration was not intended to exclude contractors with poor performance

histories from future contracts. Rather, it was anticipated that certain contractors with poor

performance histories would be able to compensate for this in other aspects of their proposals

(e.g., offering lower prices, partnering with companies with better records),74 while others would

be found nonresponsible for purposes of particular contracts or excluded from government

contracting generally through the operation of other legal authorities.75

Past Performance as an Evaluation Factor

Subpart 15.3 of the FAR currently requires agencies to consider past performance or some other

non-cost evaluation factor in all procurements, although the requirements differ somewhat

depending upon the value of the procurement:

•

With procurements valued at or below the simplified acquisition threshold

(generally $150,000), agencies must consider past performance or some other

non-cost evaluation factor (e.g., technical excellence, management capability).76

•

With procurements whose value exceeds the simplified acquisition threshold,

agencies must consider past performance unless the contracting officer

documents why past performance is not an appropriate evaluation factor for the

acquisition.77

Subpart 15.3 further requires (1) that agencies’ evaluation of past performance be in accordance

with the terms of the solicitation,78 and (2) that contractors’ performance in subcontracting with

small disadvantaged businesses be considered when evaluating their past performance.79

(...continued)

proposals when making source selection decisions).

73

The FAR, however, views past performance information as “one indicator of an offeror’s ability to perform the

contract successfully.” See 48 C.F.R. §15.305(a)(2)(i).

74

See, e.g., Steven Kelman & Mathew Blum, Past Performance as an Evaluation Factor—Strengthening the

Government’s Best Value Decisions, 38 Gov't Cont. 37 (October 2, 1996) (“[The offerors] always have the opportunity

to offset a marginal performance record with an aggressive price proposal or a strong showing in other factors that are

being considered.”); Alliant Techsystems, Inc., B-260215.4, B-260215.5 (August 4, 1995) (suggesting that a contractor

that is aware of potentially adverse past performance information can explain that information or otherwise revise its

proposal). Dr. Kelman was the administrator of OFPP during the mid-1990s.

75

See infra notes 108 to 147 and accompanying text.

76

48 C.F.R. §15.304(c)(2).

77

48 C.F.R. §15.304(c)(3)(i) & (iii).

78

48 C.F.R. §15.304(d). Additionally, Subpart 15.3 requires that agency solicitations (1) provide offerors with the

opportunity to identify past or current contracts for similar efforts with any entity; (2) authorize offerors to provide

information on problems encountered with identified contracts and the offeror’s corrective actions; and (3) make clear

that an offeror without relevant past performance, or for whom information on past performance is not available, may

not be evaluated either favorably or unfavorably on this factor. 48 C.F.R. §15.305(a)(2)(ii) & (iv).

79

48 C.F.R. §15.305(a)(2)(v). Additionally, when the solicitation involves “bundling,” agencies’ evaluation of past

performance must assess the offeror’s performance in meeting goals in any subcontracting plans incorporated in prior

contracts. 48 C.F.R. §15.304(c)(3)(ii) & (4). “Bundling” refers to the consolidation of two or more requirements for

goods or services previously provided or performed under separate smaller contracts into a solicitation for a single

(continued...)

Congressional Research Service

11

Evaluating the “Past Performance” of Federal Contractors

Beyond these requirements, however, Subpart 15.3 generally gives agencies broad discretion in

their use of the past performance evaluation factor.80 Agencies may define what constitutes “past

performance” for purposes of the procurement, including any subfactors that comprise the past

performance evaluation factor.81 They may also determine what performances qualify as “recent”

and “relevant” for purposes of the procurement,82 as well as whose performances are considered

when past performance is evaluated (e.g., prime contractors, subcontractors, key employees).83

Additionally, agencies may determine what role the “past performance” factor plays in relation to

other evaluation factors. Agencies are required to consider cost/price and the quality of the

product or service, along with past performance, in all negotiated procurements.84 However,

depending upon their requirements, they may consider a range of other factors, such as corporate

experience, management, key personnel and staffing plan, organizational capacity, “proven plan

to achieve efficiency and cost-effectiveness,” “continuous enhancement of processes and

systems(s),” and the offeror’s small business status.85 Moreover, agencies have broad discretion in

(...continued)

contract that is likely to be unsuitable for award to a small business because of its size or scope. See 15 U.S.C.

§632(o)(2). For further discussion of bundling, see CRS Report R41133, Contract “Bundling” Under the Small

Business Act: A Legal Overview, by (name redacted).

80

See 48 C.F.R. §15.304(c) (“The evaluation factors and significant subfactors that apply to an acquisition and their

relative importance are within the broad discretion of agency acquisition officials,” subject to certain narrow limits).

Although the factors and subfactors considered must relate to the procurement, contractors’ ability to challenge

agencies’ use of allegedly improper factors is limited by the deference that judicial and administrative tribunals give to

agencies’ selection of evaluation criteria. See, e.g., SML Innovations, Inc., B-402667.2 (October 28, 2010) (“[W]e will

not object to the use of particular evaluation criteria so long as they reasonably relate to the agency’s needs in choosing

a contractor that will best serve the government’s interests.”).

81

See 48 C.F.R. §15.304(d) (requiring only that the agency describe the “general approach for evaluating past

performance information” in the solicitation). See also Brican Inc., B-402602 (June 17, 2010) (evaluation of past

performance based on experience and past performance); CapRock Government Solutions, Inc.; ARTEL, Inc.; Segovia,

Inc., B-402490, B-402490.2, B-402490.3, B-402490.4, B-402490.5 (May 11, 2010) (evaluation of past performance

based on (1) conformance to contract requirements; (2) standards of workmanship; (3) schedule; (4) business relations;

(5) management of key personnel; (6) management of subcontractors; and (7) record of complying with subcontracting

goals).

82

See 48 C.F.R. §15.305(a)(2) (requiring that the “currency” and “relevance” of past performance information be

considered, but not prescribing what is meant by either of those terms). See also Dorado Services, B-401930.3 (June 7,

2010) (defining relevant performance as that under contracts requiring the offeror to perform refuse and recycling

services of the same or similar complexity and recent performance as that within the past five years).

83

Agencies are encouraged to consider past performance information regarding predecessor companies, key personnel

who have relevant experience, or subcontractors that will perform “major or critical” aspects of the work, but are not

required to do so. 48 C.F.R. §15.305(a)(2)(iv). See, e.g., Brican Inc., B-402602 (June 17, 2010) (past performance of

subcontractors considered); CapRock Government Solutions, Inc.; ARTEL, Inc.; Segovia, Inc., B-402490, B-402490.2,

B-402490.3, B-402490.4, B-402490.5 (May 11, 2010) (noting that nothing in the RFP indicated that the past

performance of the prime contractor was more important than that of the subcontractors); JSW Maintenance, Inc., B400581.5 (September 8, 2009) (past performance of key employees considered). Any such consideration must,

however, be consistent with the terms of the solicitation. See, e.g., Quality Servs. Int’l LLC, B-410156 (November 3,

2014) (finding that the agency had improperly credited the awardee with past experience it had earned through a joint

venture because the way in which such experience was credited was inconsistent with the terms of the solicitation).

84

48 C.F.R. §15.304(c)(1) (price/cost); 48 C.F.R. §15.304(c)(2) (quality of the product or service). Certain other

evaluation factors must be used in specific circumstances. For example, the extent of proposed subcontracting with

small businesses must be an evaluation factor for contracts that involve bundling and offer a significant opportunity for

subcontracting. 48 C.F.R. §15.304(c)(4).

85

See, e.g., Source Diversified, Inc., B-403437.2 (December 16, 2010) (corporate experience); Industrial Constr. &

Trading Co., B-403849 (December 13, 2010); Int’l Medical Corps, B-403688 (December 6, 2010) (key personnel and

staffing plan, organizational capacity); Delta-21 Resources, Inc., B-403586 (November 10, 2010) (“proven plan to

achieve efficiency and cost-effectiveness,” “continuous enhancement of processes and systems(s)”); Washington(continued...)

Congressional Research Service

12

Evaluating the “Past Performance” of Federal Contractors

assigning various weights to the evaluation factors.86 Past performance need not be the most

heavily weighted factor,87 and poor scoring on the past performance factor could be offset by

higher scores on other factors, particularly if little weight is given to past performance.88

Agencies also generally have broad discretion in their consideration of various sources of

information about contractors’ past performance. Much of the information used in evaluating

contractors’ past performance comes from questionnaires or customer surveys submitted by the

contractor,89 although agencies have,90 and often explicitly reserve,91 the right to consider other

information. This can include any evaluations of contractor performance that agencies were

required to prepare under Subpart 42.15 of the FAR. It should be noted, however, that Subpart

15.3 does not require agencies to consider evaluations prepared pursuant to Subpart 42.15 in

source selection decisions,92 although Subpart 42.15 does require “use” of such evaluations, and

failure to consider them could be found unreasonable under the “close at hand” doctrine.93 While

the federal courts and the Government Accountability Office (GAO) have held that contracting

officers need not consider all possible information about a contractor’s past performance when

(...continued)

Harris Group, B-401794, B-401794.2 (November 16, 2009) (offeror’s small business status).

86

See 48 C.F.R. §15.304(e)(1)-(3) (requiring only that the solicitation indicate whether all non-cost/non-price

evaluation factors are (1) significantly more important than cost/price; (2) approximately equal to cost/price; or (3)

significantly less important than cost/price).

87

See, e.g., Source Diversified, Inc., B-403437.2 (December 16, 2010) (product description and corporate experience

weighted more heavily than past performance); ITW Military GSE, B-403866.3 (December 7, 2010) (technical merit

weighted more heavily than past performance); L&N/MKB, Joint Venture, B-403032.3 (December 16, 2010) (price as

important as technical merit and past performance combined). Guidance issued by OFPP in 1995 recommended that

past performance be at least 25% of the non-cost factors, or at least equal to or more important than any other non-cost

factor. See Guide to Best Practices, supra note 14, at 16-18. Agencies were not required to abide by this guidance,

however.

88

It should also be noted that agencies evaluating past performance often rate it using broad descriptors (e.g.,

substantial, satisfactory, limited, and unknown). See, e.g., Dorado Services, B-401930.3 (June 7, 2010). Additionally,

vendors’ past performance is considered only in relation to that of the other vendors who submitted offers, not in the

abstract. Thus, a company whose past performance has been less than stellar, but does not result in a nonresponsibility

determination or exclusion, could be selected for award if the past performance of the other offerors was equally or

more problematic.

89

MFM Lamey Group, LLC, B-402377 (March 25, 2010) (solicitation requesting offerors to submit up to five past

performance questionnaires completed by former customers); SDV Solutions, Inc., B-402309 (February 1, 2010) (RFP

requiring offeror to ensure that at least three past performance questionnaires are submitted by former customers).

90

See, e.g., Seattle Sec. Servs., Inc. v. United States, 45 Fed. Cl. 560, 568 (1999) (agency has right to consider

information derived from the personal knowledge of the evaluators).

91

See, e.g., Dorado Services, B-401930.3 (June 7, 2010) (RFP granting the procuring agency the right to consider data

obtained from the government and other sources); Shaw-Parsons Infrastructure Recovery Consultants, LLC; Vanguard

Recovery Assistance, JV, B-401679.4, B-401679.5, B-401679.6, B-401679.7 (March 10, 2010) (agency reserving the

right to use “outside knowledge,” including agency knowledge of the firm’s performance); CMI Management, Inc., B402172, B-402172.2 (January 26, 2010) (RFP reserving the agency’s right to use PPIRS information).

92

The situation is different with responsibility determinations, where agencies are explicitly required to consider

agency performance evaluations input into CPARS/PPIRS. See infra notes 116 to 122 and accompanying text.

93

See, e.g., Contrack Int’l, Inc., B-401871.5, B-401871.6, B-401871.7 (May 24, 2010) (finding that the Army Corps of

Engineers unreasonably failed to consider negative information contained in three Contractor Performance Assessment

Reports about the awardee). The allegedly poor performance by the awardee in Contrack had also been the subject of

news coverage and a report by the Department of Defense Office of the Inspector General. Absent such coverage or

reports, however, it is unclear how a protester would know of potentially adverse performance evaluations contained in

PPIRS or other agency sources given the restrictions on access to source selection information.

Congressional Research Service

13

Evaluating the “Past Performance” of Federal Contractors

evaluating such performance for source selection purposes,94 GAO, in particular, has noted that

some information may be so “close at hand” that agencies cannot reasonably ignore it. For

example, in Shaw-Parsons Infrastructure Recovery Consultants, LLC, GAO found that the

Federal Emergency Management Agency (FEMA) acted unreasonably when it relied solely on

information regarding past performance submitted by the contractor, and failed to consider

information contained in customer questionnaires that FEMA had required the offerors to

submit.95 GAO noted that, while the solicitation may have given FEMA discretion to seek out

additional information, FEMA “could not simply ignore” the questionnaires once it had them

because they were “close at hand.”96

Agencies generally need not seek out information that would mitigate potentially adverse past

performance information contained in the sources they consult,97 although there are a few

circumstances in which they must do so, as Table 1 illustrates. They are also generally free to

draw their own inferences regarding contractors’ past performance from the sources they consult

so long as these inferences are reasonable. However, Subpart 15.3 does require contracting

officers to take into account “[t]he currency and relevance of the information, source of the

information, context of the data, and general trends in contractor’s performance” when

considering past performance information.98

Table 1. Various Exchanges Potentially Involving Past Performance Information

Type of Exchange

Clarifications

Authorized or

Required?

Authorized

Limited exchanges between the government and

offerors that may occur when award without

discussions is contemplated

Communications

Exchanges between the government and offerors

after receipt of proposals leading to the establishment

of the competitive rangeb

Past Performance Information

Addressed

Relevance of past performance

information

Adversea past performance information

to which the offeror has not previously

had the opportunity to respond

Required

Adversea past performance information

to which the offeror has not previously

had the opportunity to respond

94

See, e.g., SDA, Inc., B-256075, B-25606 (May 2, 1994) (“[W]e do not think that the agency had to ‘go behind’ the

opinions expressed by the references and conduct further independent investigation as to the adequacy or quality of the

protester’s performance.”); IGIT, Inc., B-275299.2 (June 23, 1997) (agency need not contact all sources listed by the

offeror).

95

B-401679.4; B-401679.5; B-401679.6; B-401679.7 (March 10, 2010).

96

Id. Particularly in the wake of GAO’s 2013 decision in Triad International Maintenance Corp., B-408374

(September 5, 2013), it has been suggested that the “close at hand” doctrine can be seen to apply to (1) past

performance information referenced in the protester’s proposal; (2) other past performance information in the agency’s

possession; (3) the protester’s past performance as an incumbent for the same agency supplying the same supplies or

performing the same services; and (4) past performance information otherwise known to the agency’s evaluator from

the evaluator’s prior involvement on the contract to which the information pertains. See Michael R. Golden, GAO’s

Close at Hand Doctrine in Light of Triad Decision, Law360, May 21, 2014.

97

See, e.g., Cessna Aircraft Co., B-261953.5 (February 5, 1996); SDA, Inc., B-256075, B-25606 (May 2, 1994).

98

48 C.F.R. §15.305(a)(2)(i).

Congressional Research Service

14

Evaluating the “Past Performance” of Federal Contractors

Type of Exchange

Discussions

Authorized or

Required?

Required

Exchanges between the government and offerors

after the establishment of the competitive range that

are undertaken with the intent of allowing the offeror

to revise its proposal

Past Performance Information

Addressed

Adversea past performance information

to which the offeror has not previously

had the opportunity to respondc

Source: Congressional Research Service, based on FAR Part 15.306.

a.

The fact that another vendor is rated higher for past performance does not necessarily mean that the

information on any lower rated vendors is “adverse.” See, e.g. Value CAD, B-272936 (November 7, 1996).

b.

The “competitive range” consists of the most highly rated offerors, to one or more of whom an award is

likely to be made. 48 C.F.R. §15.306(c)(1).

c.

It is possible that poor past performance information could be corrected for, as well as explained, during

discussions. This is not the case during clarifications and communications, when any information shared

must be “historical” and is not subject to change or improvement. See, e.g., Alliant Techsystems, Inc.,

B-260215.4, 260215.5 (August 4, 1994).

Protesting Agency Evaluations of Past Performance

Contractors that object to the procuring activity’s evaluation of their own past performance, or

that of the winning offeror, in making its source selection decision could potentially file a bid

protest challenging the decision with the Court of Federal claims or the GAO, although protesters

must overcome significant hurdles to disturb a challenged award.99 The protester first has to

demonstrate standing to bring the protest, which generally requires that the protester be in line for

the award if the protest is sustained.100 Then, assuming that the protester has standing, it has to

allege defects in the evaluation process sufficient to overcome the substantial deference that GAO

and the federal courts accord to contracting officers’ evaluations of past performance.101 This

generally means that the protester must allege that the evaluation was unreasonable, not

adequately documented, or not in accordance with the law or the terms of the solicitation.102

Protests that fail to allege one of these three things are generally seen as “mere disagreements ...

99

One study of bid protests conducted in the 1990s found that GAO had sustained only 13 out of 300 protests

challenging agencies’ use of past performance information in the period between December 1992 and May 1997. See

Only Four Percent of GAO Protests Involving ‘PPI’ Evaluations Are Sustained, GAO Defends Results, 67 Fed. Cont.

Rep. 590-91 (May 19, 1997). This study does not appear to have been updated or replicated.

100

But see Arora Group, B-288127 (September 14, 2001) (recognizing a bidder whose proposal was ranked fifth as an

interested party only because its protest challenged the agency’s application of the evaluation criteria in general and, if

successful, could have placed the contractor in line for the award).

101

See, e.g., Dorado Services, B-401930.3 (June 7, 2010) (“As a general matter, the evaluation of an offeror’s past

performance is within the discretion of the contracting agency, and we will not substitute our judgment for reasonably

based past performance ratings.”).

102

See, e.g., JSW Maintenance, Inc., B-400581.5 (September 8, 2009) (“Our Office examines an agency’s evaluation

of past performance to ensure that it was reasonable and consistent with the stated evaluation criteria and applicable

statutes and regulations; however, the necessary determinations regarding the relative merits of the offerors’ proposals

are primarily matters within the contracting agency’s discretion.... [O]ur office will not question an agency’s

determinations absent evidence that those determinations are unreasonable or contrary to the stated evaluation

criteria.”). It should also be noted that the focus of the protest is upon the determinations of the contracting officer who

made the source selection decision, not that of any contracting officer who previously gave an offeror a poor

performance evaluation. See supra note 41 and accompanying text.

Congressional Research Service

15

Evaluating the “Past Performance” of Federal Contractors

as to the relative merit of competing proposals” and are denied.103 Moreover, beyond having

broad discretion in determining whether particular past performance merits a particular rating,

contracting officers also have broad discretion in determining which proposal represents the “best

value” for the government. GAO and the federal courts have expressly approved of agencies’

selection of contractors with lower past performance ratings over contractors with higher, or even

“perfect,” ratings, notwithstanding the fact that the solicitation calls for past performance to be

given more weight than price in the source selection decision.104

Other Consideration of Past Performance in Source Selection

Agencies sometimes also consider contractors’ past performance in source selection decisions in

ways that do not entail use of the past performance evaluation factor. For example, agencies may

consider past performance as a component of other evaluation factors (e.g., experience, mission

capability), as well as its own factor.105 Additionally, under FASA, agencies may use past

performance as a factor in determining with whom to place certain orders under multiple-award

contracts.106 Subpart 16.5 of the FAR, which implements the relevant provisions of FASA,

encourages contracting officers to take into account “[p]ast performance on earlier orders under

the contract, including quality, timeliness and cost control” when developing procedures for

ensuring that all contractors holding a multiple-award contract have a “fair opportunity” to be

considered for orders exceeding $5 million.107 Such consideration does not involve a source

selection decision, per se, because the sources were selected at the time when the contract was

awarded, and only those sources holding a multiple-award contract are eligible for orders placed

103

Compare Dorado Services, B-401930.3 (June 7, 2010) (finding that the contracting officer’s assignment of a

“substantial confidence” rating to the awardee was not unreasonable despite the fact that the awardee had received

lower ratings and more unfavorable comments from its references and experienced more performance problems under

its contracts) with Brican Inc., B-402602 (June 17, 2010) (sustaining the protest because nothing in the record indicated

that the contracting officer had credited the protester with the performance of its subcontractor, while it had so credited

the awardee).

104

See also Truetech, Inc., B-402536.2 (June 2, 2010) (“[S]ource selection officials in a negotiated procurement have

broad discretion in determining the manner and extent to which they will make use of the technical and price evaluation

results; price/technical tradeoffs may be made, and the extent to which one may be sacrificed for the other is governed

only by the test of rationality and consistency with the established evaluation factors.”); FN Manufacturing, LLC, B403059.4, B-402059.5 (March 22, 2010) (“It is well-settled that an agency properly may select a lower-rated, lowerpriced proposal” even if the RFP states that price is less important than technical merit).

105

Software Eng’g Servs. Corp. v. United States, 85 Fed. Cl. 547, 550 (2009) (using “mission capability” as an

evaluation factor and defining “mission capability” to include “directly-related current or past performance”). Offerors’

experience, which is akin to past performance, is sometimes also considered as a separate evaluation factor, although

agencies are generally not required to give offerors an opportunity to address adverse information regarding their prior

experience through clarifications, communications, or discussions. See, e.g., CMI Management, Inc., B-402172, B402172.2 (January 26, 2010) (relevant experience as an evaluation factor); Moore Medical Corp., B-261758 (October

26, 1995) (upholding agency’s determination not to conduct discussions regarding prior experience, in part, because

prior experience differs from past performance).

106

See P.L. 103-355, §1004, 108 Stat. 3249-54 (October 13, 1994) (procurements of defense agencies); id. at §1054,

108 Stat. 3261-65 (procurements of civilian agencies). Under a “multiple-award contract,” the government enters

agreements with several vendors to supply goods or services. It can then generally award work to any of these vendors

by issuing task or delivery orders. See generally CRS Report R40516, Competition in Federal Contracting: Legal

Overview, by (name redacted).

107

48 C.F.R. §16.505(b)(1)(v)(A)(1). This requirement would not necessarily ensure that a particular order is placed

with the contractor who has the best past performance record, however, in part because agencies are legally obligated to

order certain minimum quantities of goods or services from each contractor holding a multiple-award contract. See,

e.g., 48 C.F.R. §16.504(a)(1); Peter J. Brandon, AGBCA No. 91-186-1, 92-1 B.C.A. ¶ 24,648 (1991).

Congressional Research Service

16

Evaluating the “Past Performance” of Federal Contractors

under it. However, it is akin to a source selection decision in that it effectively determines who

supplies particular goods to, or performs particular work for, the procuring activity.

Past Performance as a Criterion in

Responsibility Determinations

Ever since the FAR was promulgated in 1984,108 agencies have considered whether contractors

have a “satisfactory performance record,” among other things, in determining whether they are

sufficiently “responsible” to be awarded a government contract.109 Agencies are prohibited from

awarding a contract to a contractor who has not been determined to be affirmatively

responsible.110 Then, in 1995, after the issuance of OFPP Policy Letter 92-5 and the enactment of

FASA, OFPP amended Subpart 9.1 of the FAR to further require that agencies consider “relevant

past performance information,” as defined in Subpart 42.15, when making responsibility

determinations.111 Guidance issued by OFPP shortly thereafter clarified that agencies are to use

consideration of past performance in the responsibility determination process—not the source

selection process—as a means of avoiding contractors with poor performance histories:

A contractor with a record of unsatisfactory past performance should be screened out of the

selection process as part of the responsibility determination. If a contractor’s past

performance record passes the responsibility determination, then the record should be

compared to the other responsible offerors to determine the offeror that provides the best

value to the Government.112

However, it should be noted that, while OFPP characterizes the responsibility determination

process as the means for “screening out” contractors with poor past performance, agencies may

not use nonresponsibility determinations to punish contractors for poor performance, and poor

performance or even default on one or several prior contracts does not necessarily constitute

adequate grounds for a nonresponsibility determination.113 Additionally, as discussed below, any

use of the responsibility determination process to avoid a contractor with poor past performance

108

Dep’t of Defense, Gen. Servs. Admin., & Nat’l Aeronautics & Space Admin., Establishing the Federal Acquisition

Regulation (Part 2 of 12), 48 Federal Register 42102 (September 19, 1983). Agencies were required to determine that

prospective contractors were responsible before the FAR was promulgated, and consideration of contractor’s

performance record was generally a component of this responsibility determination process. See John Cibinic, Jr. &

Ralph C. Nash, Jr., Formation of Government Contracts 403-04 (3d ed. 1998).

109

48 C.F.R. §9.104-1(c). Other factors include (1) whether the contractor has adequate financial resources to perform

the contract, or the ability to obtain them; (2) whether the contractor is able to comply with the required or proposed

delivery schedule; (3) whether the contractor has a satisfactory record of integrity and business ethics; (4) whether the

contractor has the necessary organization, experience, accounting and operational controls, and technical skills, or the

ability to obtain them; (5) whether the contractor has the necessary production, construction, and technical equipment

and facilities, or the ability to obtain them; and (6) whether the contractor is otherwise qualified and eligible to receive

an award under applicable laws and regulations. 48 C.F.R. §9.104-1(a)-(b), (d)-(g).

110

48 C.F.R. §9.103(b). See also 48 C.F.R. §9.103(a) (“Purchases shall be made from, and contracts shall be awarded

to, responsible prospective contractors only.”).

111

60 Federal Register at 16718. Subpart 9.1 was also amended to preclude prospective contractors being found

nonresponsible because they lack a relevant performance history. Id. They could, however, still be found

nonresponsible because they lack the necessary experience. See, e.g., CEA Indus., Inc., B-169160 (May 4, 1970).

112

Guide to Best Practices for Past Performance, supra note 14, at 11.

113

See, e.g., Marine Eng'rs Beneficial Ass'n, B-181265 (November 27, 1974).

Congressional Research Service

17

Evaluating the “Past Performance” of Federal Contractors

must be short-term and procurement-specific so as to avoid de facto debarment of the

contractor.114 For dealings with a contractor to be avoided long-term and/or government-wide, the

contractor would need to be formally excluded from government contracting (i.e., debarred or

suspended).115

“Satisfactory Performance Record” As Condition for Contract

Because of the amendments made to Subpart 9.1 of the FAR in 1995, past performance has

traditionally played a unique role in the responsibility determination process. Until recently,

“relevant past performance” information was the only information that contracting officers were

required by law to consider when making responsibility determinations.116 They otherwise had

broad discretion as to what and how much information to consider,117 although they were

encouraged to consider certain information (e.g., commercial sources of supplier information,

preaward survey reports, business and trade associations).118 This changed in 2008, when

Congress enacted legislation requiring contracting officers to consider the information contained

in FAPIIS when making responsibility determinations.119 FAPIIS is required to contain, among

other things, brief descriptions of civil, criminal, and administrative proceedings involving federal

contracts that resulted in a conviction or finding of fault, as well as terminations for default,

administrative agreements, and nonresponsibility determinations relating to federal contracts,

within the past five years for all persons holding a federal contract or grant worth $500,000 or

more.120 Consideration of this information would arguably be most helpful in assessing

responsibility criteria other than whether the contractor possesses a satisfactory performance

record (e.g., whether the contractor has a satisfactory record of integrity and business ethics).

However, because FAPIIS includes information from CPARS/PPIRS,121 the requirement to

consider the information in FAPIIS arguably augments agency consideration of past performance

evaluations.122

114

See infra notes 135 to 142 and accompanying text.

See 48 C.F.R. §§9.400-9.409.

116

See, e.g., 48 C.F.R. §9.105-1(c) (2008).

117

See, e.g., John C. Grimberg Co. v. United States, 185 F.3d 1297, 1303 (Fed. Cir. 1999) (“[T]he contracting officer is

the arbiter of what, and how much, information he needs.”). Contracting officers must obtain “information sufficient to

be satisfied” that the prospective contractor is responsible. 48 C.F.R. §9.105-1(a). However, the contractor bears the

responsibility of ensuring that the contracting officer has sufficient information. Sec. Assistance Forces & Equip. Int'l,

Inc., B-194876 (November 19, 1980). An affirmative determination is improper if not based on “sufficient”

information. 48 C.F.R. §9.105-1(a). However, the amount of information needed depends upon the conclusions that can

be drawn from it. See, e.g., John F. Small & Co., Inc., B-207681.2 (December 6, 1982). Determinations must also be

supported by the record and based on the most current information available. See, e.g., 48 C.F.R. §9.105-2(b)(1); Gary

Aircraft Corp., B-174455 (July 6, 1972).

118

48 C.F.R. §9.105-1(c)(1)-(5) (“In addition, the contracting officer should use the following sources of information

... ”) (emphasis added).

119

P.L. 110-417, §872(b)(1) & (c), 122 Stat. 4356 (October 14, 2008).

120

Id.

121

Because FAPIIS contains past performance information, access to FAPIIS was initially restricted to authorized

government personnel. Although Congress subsequently required the information contained in FAPIIS to be made

publicly available on the web, it expressly excluded evaluations of past performance. See supra notes 31 to 36 and

accompanying text.

122

It should be noted, however, that even when contracting officers are required to consider particular information

when making responsibility determinations, they are not bound by any recommendations contained in the information

that they consider. See, e.g., Carl Weissman & Sons, Inc., B-190304 (February 17, 1978).

115

Congressional Research Service

18

Evaluating the “Past Performance” of Federal Contractors

Additionally, Subpart 9.1 of the FAR, which governs responsibility determinations, establishes a

presumption that contractors who are, or recently have been, “seriously deficient” in contract

performance are nonresponsible unless the contracting officer determines that the circumstances

were beyond the contractor’s control, or the contractor has taken appropriate corrective action.123

Subpart 9.1 does not define what constitutes a “serious deficiency” in performance, but GAO and

the courts have found that it could potentially include delinquent performance, delivery of

nonconforming items, failure to adhere to contract specifications, late deliveries, poor

management or technical judgment, failure to correct production problems, failure to perform

safely, and inadequate supervision of subcontractors.124

Protests of Responsibility/Nonresponsibility Determinations

Contractors’ ability to challenge agency determinations that they are nonresponsible, or that

another contractor is responsible, is limited. Judicial and other tribunals that hear protests of

contract awards do not routinely review contracting officers’ responsibility determinations

because such determinations are “practical, ... not legal determination[s]”125 and “are not readily

susceptible to judicial review.”126 The GAO hears protests regarding responsibility determinations

only when the protester alleges that “definitive responsibility criteria”127 were not met, or

“identif[ies] evidence raising serious concerns that ... the contracting officer unreasonably failed

to consider available relevant information or otherwise violated statute or regulation.”128 The

federal courts similarly consider the merits of protested responsibility determinations only when

the protester’s allegations that the agency’s determination was arbitrary and capricious, an abuse

of discretion, or otherwise not in accordance with the law can survive a preliminary motion to

dismiss.129 Moreover, judicial and administrative tribunals decline to overturn contracting

123

48 C.F.R. §9.104-3(b).

See, e.g., Campbell Indus., B-238871 (July 3, 1990) (poor management and technical judgment); Ford Motor Co.,

B-207179 (January 20, 1983) (late deliveries); United Power & Control Sys., Inc., B-184662 (December 27, 1978)

(nonconforming items); Bill Ward Painting & Decorating, B-184612 (January 28, 1976) (unsafe performance;

inadequate supervision of subcontractors); Marine Eng'rs Beneficial Ass'n, B-181265 (November 27, 1974) (failure to

take corrective action); Kennedy Van & Storage Co., Inc., B-180973 (June 19, 1974) (failure to adhere to

specifications); Land-Air, Inc., B-166969 (September 2, 1969) (delinquent performance).

125

Peter Kiewit Sons’ Co. v. U.S. Army Corps of Eng’r, 714 F.2d 163, 167 n.18 (D.C. Cir. 1983).

126

YRT Servs. Corp. v. United States, 28 Fed. Cl. 366, 394 (1993). These tribunals also take the view that federal

agencies “bear the burden of difficulties experienced in obtaining the required performance.” See, e.g., News Printing

Co. v. United States, 46 Fed. Cl. 740, 746 (2000).

127

Definitive responsibility criteria are “special standards” that contractors must meet in order to be determined

responsible for specific acquisitions. 48 C.F.R. §9.104-2(a). Contracting officers may incorporate such standards into

solicitations when unusual expertise, special facilities, or specific experience or equipment are necessary to ensure that

the government’s needs are satisfied. See, e.g., Breland Co., B-217552 (February 21, 1985) (unusual expertise); Aero

Corp., B-201581 (June 23, 1981) (special facilities).

128

See, e.g., Gov’t Accountability Office, Office of General Counsel, Bid Protests at GAO: A Descriptive Guide 40 (9th

ed. 2009), available at http://www.gao.gov/decisions/bidpro/bid/d09417sp.pdf. Prior to 2003, the GAO exercised even

more limited jurisdiction over protested responsibility determinations, hearing only protests alleging “bad faith” by

agency officials or failure to meet definitive criteria. However, the GAO changed its policy in response to the decision

by the U.S. Court of Appeals for the Federal Circuit in Impresa Construzioni Geom. Domenico Garufi v. United States,

238 F.3d 1324 (Fed. Cir. 2001).

129

Watts-Healy Tibbitts v. United States, 84 Fed. Cl. 253 (2008). Claims that agency actions are arbitrary and

capricious, an abuse of discretion, or otherwise not in accordance with the law derive from the Administrative

Procedure Act (APA). The APA allows persons “suffering legal wrong because of agency action” to seek judicial

review of that action. See 5 U.S.C. §702 (right of review); 5 U.S.C. §706 (2)(A) (arbitrary and capricious standard).

124

Congressional Research Service

19

Evaluating the “Past Performance” of Federal Contractors

officers’ responsibility determinations in many of the protests that they do hear. They generally

overturn a determination only when the protester can show that the determination was clearly

unreasonable given the record before the contracting officer.130 The GAO and the courts have also

held that a contracting officer’s determination is not unreasonable merely because another

contracting officer made a different determination after considering the same information.131

De Facto Debarment

Because the focus of a responsibility determination is upon the contractor’s ability to satisfy the

needs of the government under a particular proposed contract, the responsibility determination

process is not designed to exclude contractors with allegedly deficient past performance, or other

problems, from future dealings with the government. To the contrary, any use of it to this effect

could potentially be found to constitute de facto debarment. The federal courts developed the

concept of de facto debarment as a way of ensuring that agencies do not deprive contractors of

the due process to which they are entitled in formal exclusion proceedings (i.e., debarment and

suspension) by effectively excluding contractors by other means.132 Repeated determinations of

nonresponsibility based on the same alleged conduct by the contractor have been found to

constitute de facto debarment,133 as have statements or other conduct evidencing an intent to

exclude a contractor from future government contracts.134 For example, in Old Dominion Dairy

Products, Inc. v. Secretary of Defense, the Air Force was found to have de facto debarred a

contractor when the contracting officer determined that the contractor lacked integrity and was

nonresponsible after another contracting officer had determined that the contractor was

nonresponsible due to billing irregularities.135 Similarly, in Art-Metal-USA, Inc. v. Solomon, the

130

See, e.g., Impresa Construzioni, 238 F.3d at 1334-35. Courts may permit limited depositions of contracting officers

in order “to plac[e] on the record the basis for [their] responsibility determination.” Id. at 1339. There is usually no

parallel need to depose contracting officers when they determine a contractor is nonresponsible because their files must

contain documents stating the basis for the nonresponsibility determination, among other things. See 48 C.F.R. §9.1052(a)(1).

131

See, e.g., MCI Constructors, B-240655 (November 27, 1990); S.A.F.E. Exp. Corp., B-151834 (April 22, 1983).

132

Contractors who are suspended or debarred must be given notice of their exclusion and an opportunity for a hearing,

although the timing of the notice, in particular, differs for debarment and suspension. The concept of de facto

debarment appears to have been introduced by the U.S. Court of Appeals for the District of Columbia Circuit’s decision

in Gonzalez v. Freeman. 334 F.2d 570 (D.C. Cir. 1964). Although the Gonzelez decision concerned the process due to

contractors in de jure debarment, the court noted that the possibility of de facto debarment. Id. at 573.

133

Shermco Indus. v. Secretary of the Air Force, 584 F. Supp. 76, 93-94 (N.D. Tex. 1984) (“[A] procuring agency

cannot make successive determinations of nonresponsibility on the same basis; rather it must initiate suspension or

debarment procedures at the earliest practicable moment following the first determination of nonresponsibility.”); 43

Comp. Gen. 140 (August 8, 1963) (finding that multiple determinations of nonresponsibility can be tantamount to

debarment). However, multiple contemporaneous nonresponsibility determinations made on the same basis do not

necessarily constitute de facto debarment, especially when the determinations are based on the most current

information available. See, e.g., Mexican Intermodal Equip., S.A. de C.V., B-270144 (January 31, 1996) (two

responsibility determinations were not “part of a long-term disqualification,” but were “merely a reflection of the fact

that the determinations were based on the same current information.”).

134

Peter Kiewit Sons’ Co. v. U.S. Army Corps of Eng'rs, 534 F. Supp. 1139 (D.D.C. 1982), rev'd on other grounds,

714 F.2d 163 (D.C. Cir. 1983) (internal government directive to hold awards to the contractor “in abeyance” for an

indefinite period); Conset Corp. v. Cmty. Servs. Admin., 655 F.2d 1291 (D.C. Cir. 1981) (circulation of a

memorandum alleging that a grant recipient had a conflict of interest, coupled with a subsequent refusal to approve the

firm for a grant); Related Indus., Inc. v. United States, 2 Cl. Ct. 517 (1983) (contracting officer stated that “under no

circumstances will he award any contract” to the contractor); Leslie & Elliott Co. v. Garrett, 732 F. Supp. 191 (D.D.C.

1990) (statement that the contractor was an “administrative burden”).

135

631 F.2d 953, 955-56 (D.C. Cir. 1980).

Congressional Research Service

20

Evaluating the “Past Performance” of Federal Contractors

General Services Administration was found to have de facto debarred a contractor when it

determined that the contractor was nonresponsible for a new contract and suspended its existing

contracts in response to concerns that it had supplied “inferior products.”136 In both cases, the

courts noted that the challenged agency conduct effectively excluded the contractor without

providing the contractor with the notice or opportunity for a hearing that the contractor would

have received had they been formally debarred or suspended. The courts thus enjoined the agency

conduct that resulted in de facto debarment or granted other relief to the contractor.

Cases that involve de facto debarment sometimes also involve unconstitutional deprivation of

contractors’ liberty interests.137 This generally occurs when contractors are excluded from

government contracts without notice or a hearing because of concerns about their integrity, as

contractors have a cognizable liberty interest in being “free from ‘stigmatizing’ governmental

defamation having an immediate and tangible effect on [their] ability to do business.”138

However, depending upon the circumstances, concerns about past performance could be

implicated in concerns about integrity.139

Debarment and Suspension Under the FAR

Agencies also have legal authority under Subpart 9.4 of the FAR to debar or suspend contractors

for willful failure to perform under a contract or a history of failure to perform.140 Debarment and

suspension are government-wide and last for a fixed period of time.141 Such exclusions may,

however, only be implemented to protect the government, not to punish the contractor,142 and the

agency could be found to have violated the Administrative Procedure Act (APA) if it

subsequently excludes the contractor for conduct that it was aware of when it determined that the

contractor was responsible. For example, in Lion Raisins, Inc. v. United States, the U.S. Court of

Federal Claims found that the U.S. Department of Agriculture’s (USDA’s) suspension of a

136

473 F. Supp. 1, 5-6 (D.D.C. 1978).

See, e.g., Peter Kiewit, 534 F. Supp. 1139 (finding that a government directive to hold all awards to contractor “in

abeyance” due to concerns about the contractor’s integrity, without providing notice or an opportunity to be heard,

constituted de facto debarment and deprived the contractor of a protected liberty interest). A court could, however, find

an improper de facto debarment without finding a denial of due process. See, e.g., Shermco Indus., 584 F. Supp. at 9394. Contractors do not have property interests in prospective government contracts, only liberty interests in certain

circumstances. See, e.g., Transco Security, Inc. of Ohio v. Freeman, 639 F.3d 318, 321 (6th Cir. 1981) (“[D]eprivation

of the right to bid on government contracts is not a property interest.”).

138

Old Dominion Dairy Prods., 631 F.2 at 955-56. In addition, one court recently found that de facto debarment need

not be based on charges of lack of integrity to give rise to Fifth Amendment due process protections. See Phillips v.

Mabus, 894 F. Supp. 2d (D.D.C. 2012).

139

See, e.g., Reeve Aleutian Airways, Inc. v. United States, 982 F.2d 594 (D.C. Cir. 1993) (suspension by the

Commercial Airlift Review Board for safety reasons imposed a stigma on the contractor that “implicates the carrier’s

integrity”). But see Southeast Kansas Community Action Program, Inc. v. Lyng, 758 F. Supp. 1430 (D. Kan. 1991)

(allegation of incompetence on part of contractor is not stigmatizing); Smith & Wesson v. United States, 782 F.2d 1074

(1st Cir. 1986) (same).

140

48 C.F.R. §9.406-2(b)(1)(i)(A)-(B) (debarment); 48 C.F.R. §9.407-2(c) (suspension upon “adequate evidence” of

“any other cause of so serious or compelling a nature that it affects the present responsibility” of the contractor).

141

Debarred contractors are generally ineligible for government contracts for a fixed period of time, which can vary

depending upon the authority under which the contractor is debarred and the seriousness of the conduct underlying the

debarment, while suspended contractors are generally ineligible for the duration of any investigation into or litigation

involving their conduct. See 48 C.F.R. §9.406-4(a)(1) (debarment); 48 C.F.R. §9.407-4(a) (suspension).

142

48 C.F.R. §9.402(b) (“The serious nature of debarment and suspension requires that these sanctions be imposed only

in the public interest for the Government’s protection and not for purposes of punishment.”).

137

Congressional Research Service

21

Evaluating the “Past Performance” of Federal Contractors

contractor for falsifying raisin certifications violated the APA, given that the USDA knew of the

contractor’s conduct when making five prior determinations that the contractor was

“responsible.”143 While the decision in Lion Raisins has been criticized by some commentators144

and distinguished by some courts,145 it has been followed or cited approvingly by others146 and

could potentially be read to preclude agencies from debarring or suspending contractors under the

FAR based on “stale” allegations of wrongdoing.147 “Stale” allegations of wrongdoing could

potentially include allegations of poor performance under contracts completed some time ago.

Author Contact Information

(name redacted)

Legislative Attorney

[redacted]@crs.loc.gov, 7-....

143

51 Fed. Cl. 238, 247-48 (2001) (“The USDA awarded plaintiff five contracts between the completion of its

investigation in May 1999 and its decision to suspend plaintiff in January 2001. The USDA statutorily was obligated to

make an affirmative finding of plaintiff’s responsibility before awarding each of those contracts. In other words, five

times between May 26, 1999, and February 1, 2001, the USDA itself affirmed that plaintiff’s business practices met the

standards for present responsibility. Significantly, by the USDA’s own representations, it did so despite the possession

of all the evidence that it would later use to suspend plaintiff. The court finds these facts dispositive of the issue of

plaintiff’s present responsibility.”) (internal citations omitted).

144

See, e.g., Protest Challenges to Integrity-based Responsibility Determinations, 14 Fed. Cir. Bar J. at 499-500

(“Contrary to the court’s opinion, the contracting officer’s affirmative responsibility determination is a decision by a

single contracting officer, not that of the entire agency. The responsibility determination is limited to that specific

contract and does not bind the agency on any responsibility determination beyond it. Moreover, while the lack of

present responsibility determination by [a Suspension or Debarment Official] binds the contracting officer and

preempts the normal contracting officer responsibility determination, the converse is not true. To the extent the court

decided otherwise, the case was wrongly decided.”).

145

See Kirkpatrick v. White, 351 F. Supp. 2d 1261 (N.D. Ala. 2004) (noting that the investigation underlying the

suspension in the instant case was not completed until eight months after the suspension was imposed, unlike in Lion

Raisins); Gulf Group, Inc. v. United States, 61 Fed. Cl. 338 (2004) (noting that the testimony of the decision maker in

the instant case was not inconsistent with the documentation of his decision, unlike in Lion Raisins).

146

See, e.g., Todd Constr., 88 Fed. Cl. 235; Arch Chems., Inc. v. United States, 64 Fed. Cl. 380 (2005); S.K.J. &

Assocs. v. United States, 67 Fed. Cl. 218 (2005).

147

See Protest Challenges, 14 Fed. Cir. Bar J. at 503 (suggesting that Lion Raisins gave agencies “greater incentive to

act quicker” when determining whether to exclude a contractor).

Congressional Research Service

22

EveryCRSReport.com

The Congressional Research Service (CRS) is a federal legislative branch agency, housed inside the

Library of Congress, charged with providing the United States Congress non-partisan advice on

issues that may come before Congress.

EveryCRSReport.com republishes CRS reports that are available to all Congressional staff. The

reports are not classified, and Members of Congress routinely make individual reports available to

the public.

Prior to our republication, we redacted names, phone numbers and email addresses of analysts

who produced the reports. We also added this page to the report. We have not intentionally made

any other changes to any report published on EveryCRSReport.com.

CRS reports, as a work of the United States government, are not subject to copyright protection in

the United States. Any CRS report may be reproduced and distributed in its entirety without

permission from CRS. However, as a CRS report may include copyrighted images or material from a

third party, you may need to obtain permission of the copyright holder if you wish to copy or

otherwise use copyrighted material.

Information in a CRS report should not be relied upon for purposes other than public

understanding of information that has been provided by CRS to members of Congress in

connection with CRS' institutional role.

EveryCRSReport.com is not a government website and is not affiliated with CRS. We do not claim

copyright on any CRS report we have republished.