Electricity Transmission Cost Allocation
Congressional research reportDec 18, 2012
Ask Donna
What actually matters in this document.
Text
Electricity Transmission Cost Allocation
(name redacted)
Specialist in Energy Policy
(name redacted)
Legislative Attorney
December 18, 2012
Congressional Research Service
7-....
www.crs.gov
R41193
CRS Report for Congress
Prepared for Members and Committees of Congress
Electricity Transmission Cost Allocation
Summary
Perhaps the most contentious electricity transmission financing issue is cost allocation for new
interstate transmission lines—that is, deciding which electricity customers pay how much of the
cost of building and operating a new transmission line that crosses several states. This report
provides background and analysis of current transmission cost allocation policy and issues.
For many years, the Federal Energy Regulatory Commission (FERC) declined to go beyond
establishing general principles as set forth in its Order No. 890, which addressed “undue
discrimination and preference” in the providing of transmission services. Transmission cost
allocation proposals made by transmission service providers were therefore reviewed by FERC to
ensure compliance with the general principles outlined in Order No. 890 and the Federal Power
Act (FPA). However, there were calls for FERC to provide a clearer framework for cost
allocation. The decision of the Seventh Circuit in Illinois Commerce Commission v. FERC, to
reject a cost allocation plan approved by FERC which would have permitted “socialization” of
the costs for some new transmission projects (i.e., allowing the costs to be spread widely among
ratepayers in the PJM Interconnection, even those who do not substantially or clearly benefit
from a project) encouraged FERC to seek more clarity with respect to cost allocation. Congress
also entered the fray in the form of legislative proposals that would amend the Federal Power Act
to include new transmission cost allocation guidelines that FERC would be required to follow.
In 2009 FERC decided to take an in-depth look at cost allocation and other transmission planning
issues as part of a new docket. FERC observed that its “best remaining opportunity to eliminate
barriers to new transmission construction may therefore be to provide greater certainty in its
policies for allocating the cost of new transmission facilities, particularly for facilities that cross
multiple transmission systems.” FERC requested comments from stakeholders on transmission
planning issues.
After receiving and reviewing comments from stakeholders and offering a proposed rule in 2010,
FERC published Order No. 1000, a final rule reforming FERC’s transmission planning and cost
allocation requirements for transmission service providers, on July 21, 2011. The final rule
required transmission service providers to (1) participate in a regional transmission planning
process; (2) amend their transmission tariffs to provide for consideration of public policy; (3)
remove from their tariffs a federal right of first refusal for certain new transmission facilities; and
(4) improve coordination between neighboring transmission planning regions.
The Final Order comes as state renewable portfolio standards and the upcoming U.S.
Environmental Protection Agency (EPA) regulations for coal power plants may drive demand for
new transmission lines. The uncertainty regarding the implications for generation resources of
upcoming EPA regulations has caused some utilities to delay decisions on building new
generation, with plans to satisfy (at least interim) power needs from power markets until the
regulatory clarity they seek is provided.
This report analyzes recent developments concerning transmission cost allocation leading up to
Order No. 1000, as well as the contents of the order and their potential impact on the transmission
planning process in the future. FERC acknowledges that some key questions may only be
answered in the compliance filing process.
Congressional Research Service
Electricity Transmission Cost Allocation
Contents
Introduction...................................................................................................................................... 1
Background and History .................................................................................................................. 2
The Federal Power Act .............................................................................................................. 2
Development of the Interstate Transmission Grid and FERC Oversight Prior to Order
No. 890 ................................................................................................................................... 3
FERC Order No. 890 ................................................................................................................. 5
Examples of Cost Allocations Under Order 890 ....................................................................... 6
PJM Interconnection ........................................................................................................... 7
New England ISO (NE-ISO) ............................................................................................... 8
Florida Power and Light Company (FPL) ........................................................................... 8
Duke Energy Carolinas and Progress Energy Carolinas ..................................................... 8
Concluding Comments on Cost Allocation Examples ........................................................ 9
Illinois Commerce Commission v. FERC .................................................................................. 9
Legislative Efforts to Dictate Transmission Cost Allocation Principles.................................. 11
Order No. 1000 .............................................................................................................................. 12
Background to the Rulemaking and Initial Comments............................................................ 12
The Final Rule ......................................................................................................................... 15
Planning Requirements ..................................................................................................... 15
Cost Allocation Requirements ........................................................................................... 15
Nonincumbent Developer Requirements .......................................................................... 17
Compliance ....................................................................................................................... 18
Specific Observations on the Final Rule ................................................................................. 18
Planning Requirements ..................................................................................................... 18
Cost Allocation Requirements ........................................................................................... 19
Nonincumbent Developer Requirements .......................................................................... 20
General Comments .................................................................................................................. 21
Update on Order 1000 ....................................................................................................... 22
Contacts
Author Contact Information........................................................................................................... 22
Congressional Research Service
Electricity Transmission Cost Allocation
Introduction
Construction of new long-distance transmission lines has become a hotly debated energy policy
issue. Advocates see enhancements to the transmission grid as necessary for exploiting remote
sources of renewable power and improving the reliability of the transmission system. Others
argue that there are less costly and intrusive means of meeting energy needs than a large
transmission build-out.
Estimates of the cost of expanding the transmission grid to increase renewable power delivery
and other goals run into the tens of billions of dollars. For example (all figures in nominal
dollars):
•
The estimated transmission cost of the Joint Coordinated System Plan to bring
Great Plains wind power to the East Coast ranges from $49 billion to $80
billion.1
•
A Department of Energy (DOE) study of expanding the use of wind power
estimated transmission expansion costs of $60 billion by 2030.2
•
A study of transmission funding requirements for all purposes for the period 2010
to 2030 estimated total costs of about $300 billion.3
•
The North American Electric Reliability Corporation (NERC) identified 39,000
circuit-miles of projected high-voltage transmission over the next 10 years, with
roughly one-third of these transmission facilities used to integrate variable and
renewable resources.4
Perhaps the most contentious transmission financing issue is cost allocation for new interstate
transmission lines—that is, determining which customers must bear the costs of building and
operating new transmission lines that cross several states. This report provides background and
analysis of current transmission cost allocation policy and issues. The balance of the report is
organized as follows:
•
Background and history, including a discussion of federal authority under the
Federal Power Act.
•
Cost allocation policy at the federal and state levels in the years prior to the
adoption by the Federal Energy Regulatory Commission (FERC) of Order No.
1000.5
1
Executive summary to the Joint Coordinated System Plan 2008, p. 6, http://www.jcspstudy.org/. Note that the cost of
the transmission is modest compared to the estimated cost of the generation needed to meet demand and, in one
scenario, renewable energy goals ($674 billion to $1,050 billion).
2
U.S. Department of Energy, 20% Wind Energy by 2030, Washington, D.C., July 2008, p. 98,
http://www1.eere.energy.gov/windandhydro/pdfs/41869.pdf.
3
Marc Chupka et al., Transforming America’s Power Industry: The Investment Challenge 2010 - 2030, prepared by the
Brattle Group for The Edison Foundation, Washington, DC, November 2008, p. 40, http://www.eei.org/ourissues/
finance/Documents/Transforming_Americas_Power_Industry.pdf.
4
North American Reliability Corporation, 2010 Long-Term Reliability Assessment, October 2010,
http://www.nerc.com/files/2010%20LTRA.pdf.
5
Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, Order No. 1000,
76 FR 49,842 (August 11, 2011), 136 FERC ¶ 61,051 (2011).
Congressional Research Service
1
Electricity Transmission Cost Allocation
•
A review of the transmission planning and cost allocation reforms in Order No.
1000.
Background and History
The Federal Power Act
The authority of the Federal Energy Regulatory Commission (FERC) to regulate interstate
electricity transmission is derived primarily from Sections 205 and 206 of the Federal Power Act
(FPA).6 Section 205 of the FPA provides that all rates and charges for the transmission of electric
energy subject to FERC’s jurisdiction, as well as rules and regulations affecting those rates, must
be “just and reasonable,” and that no public utility’s rates may “unduly discriminate” against any
customers.7 FERC’s section 205 authority has been characterized as “an essentially passive and
reactive” role.8
However, Section 206 of the FPA gives FERC a broader and more proactive rate authority:
Whenever the Commission, after a hearing had upon its own motion or upon complaint, shall
find that any rate, charge, or classification, demanded, observed, charged or collected by any
public utility for any transmission ... subject to the jurisdiction of the Commission, or that
any rule, regulation, practice, or contract affecting such rate, charge or classification is
unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine
the just and reasonable rate, charge, classification, rule, regulation, practice or contract to be
thereafter observed and in force, and shall fix the same by order.9
Section 206 thus permits FERC to make changes to existing utility rates, including transmission
charges, either on its own initiative or at the request of an interested party. In order to make such
changes, FERC must (1) find that the existing rates or practices are unjust, unreasonable, unduly
discriminatory, or preferential; and (2) show that its proposed changes are just and reasonable.10
Section 206 also allows FERC to establish a just and reasonable rule, regulation, or practice “to
be thereafter observed and in force,” and to “fix the same by order.”11
The statutory authority found in Section 206 of the FPA gives FERC broad authority to establish a
set of general principles to be applied in setting just and reasonable rates upon a finding of unjust,
unreasonable, unduly discriminatory, or preferential rates or practices in the industry. FERC has
cited its Section 206 authority in promulgating other significant rulemakings related to interstate
electricity transmission facilities, including Order No. 200012 (providing for the creation of
6
18 U.S.C. §824 et seq.
18 U.S.C. §824d(a) and (b).
8
City of Winfield v. FERC, 744 F.2d 871, 876 (D.C. Cir. 1984).
9
18 U.S.C. §824e(a).
10
Atlantic City Electric Company v. FERC, 295 F.3d 1, 9 (D.C. Cir. 2002) (citations omitted).
11
16 U.S.C. §824e(a).
12
Regional Transmission Organizations, Order No. 2000, 65 FR 809 (January 6, 2000), FERC Stats. & Regs., ¶ 31,089
(1999), order on reh’g, Order No. 2000–A, 65 FR 12,088 (March 8, 2000), FERC Stats. & Regs. ¶ 31,092 (2000),
affirmed sub nom. Public Utility District No. 1 of Snohomish County, Washington, et al. v. FERC, 272 F.3d 607 (D.C.
Cir. 2001).
7
Congressional Research Service
2
Electricity Transmission Cost Allocation
Regional Transmission Organizations to manage electricity transmission grids) and Orders 88813
and 89014 (requiring utilities to provide open access to transmission facilities and creating a pro
forma tariff for utilities to adopt for their transmission services). Most recently, FERC cited its
Section 206 authority when it issued Order No. 1000, the order that altered Commission policy on
transmission planning and cost allocation.
Development of the Interstate Transmission Grid and FERC
Oversight Prior to Order No. 890
FERC’s transmission cost allocation activities have often addressed complex projects with one or
more of the following types of characteristics:
•
May traverse multiple utility service territories and cross the boundaries between
power system planning areas.
•
May have multiple owners.
•
May provide benefits to many and diverse beneficiaries. These beneficiaries may
be difficult to accurately identify, and it may be even more difficult to quantify
the benefits.
However, cost allocation for these and other transmission lines was less contentious—or at least
less visible and pressing at the national level—in the past because of the nature of the industry
itself and federal/state regulation of the industry prior to the mid-1990s. Transmission lines were
historically constructed primarily by investor-owned utilities subject to traditional cost of service
regulation by state utility commissions. These utilities sold a “bundle” of electric power
transmission, generation, and distribution services to ratepayers as a single price. Customers in
the utility’s service area generally paid a share of the costs of transmission investments, whether
or not a particular transmission investment was of value to the customer; this universal sharing of
expenses is referred to as the “socialization” of costs.
Under this regulatory regime, cost allocation was therefore generally not a complex issue, since
the beneficiaries of the transmission service and the customers paying for the services were, in
effect, assumed to be the same—the utility’s entire set of captive ratepayers. As one analysis
points out, the bundling of costs made it possible and acceptable for cost allocation issues to be
“swept under the rug.”15
13
Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission Services by Public
Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888, 61 FR 21,540 (May
10, 1996), FERC Stats. & Regs. ¶ 31.036 (1996), order on reh’g, Order No. 888–A, 62 FR 12,274 (March 14, 1997),
FERC Stats. & Regs. ¶ 31,048 (1997), order on reh’g, Order No. 888–B, 81 FERC ¶ 61,248 (1997), order on reh’g,
Order No. 888–C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Policy Study Group,
et al. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
14
Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, 72 Fed. Reg. 12,266
(March 15, 2007), FERC Stats. & Regs. ¶ 31,241, order on reh’g, Order No. 890-A, 73 Fed. Reg. 2984 (January 16,
2008), FERC Stats. & Regs. ¶ 31,261 (2007).
15
Working Group for Investment in Reliable and Economic Electric Systems (WIRES), A National Perspective on
Allocating the Costs of New Transmission: Investment: Practice and Principles, September 2007, p. 32, footnote 34,
http://www.wiresgroup.com/images/Blue_Ribbon_Panel_-_Final_Report.pdf.
Congressional Research Service
3
Electricity Transmission Cost Allocation
Cost allocations, and related transmission planning issues, were also less contentious and visible
because of the historical development of the electric power grid. Transmission lines were first
built in the early 20th century by single utilities to move electricity to population centers from
relatively nearby power plants. As generation and transmission technology advanced, the
distances increased, but the model of a single entity building lines within its own service territory
to supply its own load still predominated. Over time, these local grids began to interconnect, due
to utilities building jointly owned power plants and because power companies began to grasp the
economic and reliability benefits of being able to exchange power.16 Nonetheless, this pattern of
development did not emphasize the construction of very long-distance inter-regional lines
involving multiple owners and jurisdictions, the kinds of projects likely to have difficult cost
allocation issues.
Cost allocation issues have become pressing in part because of the restructuring of the electric
power generation and transmission industries that began in the late 1970s. The Public Utility
Regulatory Policies Act of 1978 and the Energy Policy Act of 1992 had as one of their aims the
introduction of competition into generation service. In order to facilitate the ability of non-utility
generators to access the transmission grid, in 1996 FERC issued Orders 888 and 889, to establish
an open access regulatory regime for the transmission grid.17 These orders directed transmission
owners and operators to open their system to any connected generator or load on a “nondiscriminatory” basis (that is, without giving preference to their own generation or load). Rates
are to be cost or market based, and rates and conditions of service are to be embodied in an open
access transmission tariff (OATT) approved by FERC.
By allowing non-utility generators and loads to use the transmission system, open access broke
the formerly rigid link between the entities that built transmission and their captive ratepayers.
Now a new transmission line could be used by multiple entities to transmit or receive power. The
operational links between utilities and transmission were further weakened by FERC’s policy of
promoting regional transmission organizations (RTOs) in the 1990s and 2000s. In RTOs, utilities
retain ownership of the transmission grid but operational control is exercised by the RTO. The
object is to further ensure that the transmission grid is operated in a non-discriminatory fashion to
the benefit of all market participants.18
The restructuring of the transmission market had several consequences for transmission cost
allocation and planning:
•
Cost allocation became more complex and contentious because the clear links
that existed under traditional regulation between the parties that built, operated,
and benefited from new transmission lines were broken.
•
Under the traditional regulatory regime, distinctions between transmission
additions aimed at improving system reliability and those aimed at reducing the
costs of operating the power system (i.e., “economic” projects) had little
16
The power grid in the conterminous states now consists of three large interconnections: eastern, western, and
ERCOT (covering most of Texas). The linkages between these interconnections are limited and for most purposes the
three systems can be viewed as operationally independent.
17
FERC’s economic authority extends to “public utilities” engaged in interstate commerce, as defined by the Federal
Power Act.
18
The term independent system operator (ISO) is often used interchangeably with RTO. Strictly speaking, an
organization is an RTO only if it has been so designated by FERC, but these organizations operate the same.
Congressional Research Service
4
Electricity Transmission Cost Allocation
meaning. In the open access regime the distinction between reliability projects
and economic projects became an important one, since each type of project could
benefit different groups of customers to different degrees.
•
In the open access regime, much of the responsibility for transmission planning
shifted from utilities to either RTOs or, in the markets without RTOs, a plethora
of other planning organizations built around utilities, generators, and other
stakeholders.19
FERC Order No. 890
Prior to the adoption of Order No. 1000 in the summer of 2011, FERC’s most significant
articulation of the principles applicable to transmission cost allocation was Order No. 890, issued
by FERC in February 2007. The purpose of the order was to improve the operation of the open
access transmission market created by Order Nos. 888 and 889, including establishment of cost
allocation procedures as an element of transmission planning.20
Order No. 890 established nine transmission planning principles, of which one is “Cost
Allocation—a process must be included for allocating costs of new facilities that do not fit under
existing rate structures, such as regional projects.”21 This principle was included because FERC
found that “[t]he manner in which the costs of new transmission are allocated is critical to the
development of new infrastructure. Transmission providers and customers cannot be expected to
support the construction of new transmission unless they understand who will pay the associated
costs.”22
19
Examples of these non-RTO planning organizations include ColumbiaGrid in the northwest
(http://www.columbiagrid.org/), CapX 2020 in and around Minnesota (http://www.capx2020.com/), and the North
Carolina Transmission Planning Collaborative (http://www.nctpc.org/nctpc/).
20
The objectives of Order 890 were to amend “the regulations and the pro forma open access transmission tariff
adopted in Order Nos. 888 and 889 to ensure that transmission services are provided on a basis that is just, reasonable
and not unduly discriminatory or preferential. The final rule is designed to: (1) strengthen the pro forma open-access
transmission tariff, or OATT, to ensure that it achieves its original purpose of remedying undue discrimination; (2)
provide greater specificity to reduce opportunities for undue discrimination and facilitate the Commission’s
enforcement; and (3) increase transparency in the rules applicable to planning and use of the transmission system.”
Preventing Undue Discrimination and Preference in Transmission Service, FERC Order No. 890, 72 Fed. Reg. 12266
(March 15, 2007), FERC Stats. & Regs. ¶ 31,241, order on reh’g, Order No. 890-A, 73 FR 2984 (January 16, 2008),
FERC Stats. & Regs. ¶ 31,261 (2007), order on reh’g and clarification, Order No. 890-B, 73 FR 39092 (July 8, 2008),
123 FERC ¶ 61,299 (2008), order on reh’g, Order No. 890-C, 74 FR 12540 (March 25, 2009), 126 FERC ¶ 61,228
(2009), order on clarification, Order No. 890-D, 74 FR 61511 (November 25, 2009), 129 FERC ¶ 61,126 (2009).
21
The other eight principles are (1) Coordination—the process for consulting with transmission customers and
neighboring transmission providers; (2) Openness—planning meetings must be open to all affected parties; (3)
Transparency—access must be provided to the methodology, criteria, and processes used to develop transmission
plans; (4) Information Exchange—the obligations of and methods for customers to submit data to transmission
providers must be described; (5) Comparability—transmission plans must meet the specific service requests of
transmission customers and otherwise treat similarly-situated customers (e.g., network and retail native load)
comparably in transmission system planning; (6) Dispute Resolution—an alternative dispute resolution process to
address both procedural and substantive planning issues must be included; (7) Regional Participation—there must be a
process for coordinating with interconnected systems; (8) Economic Planning Studies—study procedures must be
provided for economic upgrades to address congestion or the integration of new resources, both locally and regionally.
Id.
22
FERC Stats. & Regs. ¶ 31,241 at P 496.
Congressional Research Service
5
Electricity Transmission Cost Allocation
A particular concern of FERC was cost allocation for long-distance transmission projects that
would cross multiple utility service areas and state jurisdictions. Another concern was the
treatment of projects that would yield economic benefits to multiple parties. According to FERC:
… we are not modifying the existing mechanisms to allocate costs for projects that are
constructed by a single transmission owner and billed under existing rate structures. Our
intent is not to upset existing cost allocation methods applicable to specific requests for
interconnection or transmission service under the pro forma OATT. The cost allocation
principle discussed herein is intended to apply to projects that do not fit under the existing
structure, such as regional projects involving several transmission owners or economic
projects….[emphasis added]23
FERC chose to leave transmission owners and operators with significant but not unlimited
latitude in establishing cost allocation policies. On the one hand, FERC stated that it “will not
impose a particular allocation method for such projects, but rather will permit transmission
providers and stakeholders to determine their own specific criteria which best fit their own
experience and regional needs.”24 On the other hand, FERC did conclude that “some overall
guidance [on cost allocation] is appropriate.”25 FERC’s overriding premise was that “‘[a]llocation
of costs is not a matter for the slide-rule. It involves judgment on a myriad of facts. It has no
claim to an exact science.’”26 FERC would therefore “allow regional flexibility in cost allocation
and, when considering a dispute over cost allocation, exercise our judgment by weighing several
factors.”27 Three factors were listed by FERC:
First, we consider whether a cost allocation proposal fairly assigns costs among participants,
including those who cause them to be incurred and those who otherwise benefit from them.
Second, we consider whether a cost allocation proposal provides adequate incentives to
construct new transmission. Third, we consider whether the proposal is generally supported
by state authorities and participants across the region.
These three factors are interrelated. For example, a cost allocation proposal that has broad
support across a region is more likely to provide adequate incentives to construct new
infrastructure than one that does not. The states, which have primary transmission siting
authority, may be reluctant to site regional transmission projects if they believe the costs are
not being allocated fairly. Similarly, a proposal that allocates costs fairly to participants who
benefit from them is more likely to support new investment than one that does not. Adequate
financial support for major new transmission projects may not be obtained unless costs are
assigned fairly to those who benefit from the project.28
Examples of Cost Allocations Under Order 890
The transmission planning processes required by Order 890 were generally filed by utilities and
RTOs (in the form of amendments to their OATTs) by December 7, 2007. The processes were
23
Id. at P 558.
Id.
25
Id. at P 559.
26
Id. at P 559, citing Colorado Interstate Gas Co. v. Federal Power Commission, 324 U.S. 581, 589 (1945).
27
Id.
28
Id. at P 560. See also FERC’s Transmission Planning Process Staff White Paper, August 2, 2007, pp. 17-19,
http://www.ferc.gov/industries/electric/indus-act/oatt-reform/order-890/white-paper.pdf.
24
Congressional Research Service
6
Electricity Transmission Cost Allocation
usually accepted by FERC as filed or accepted with requirements for amendment to ensure
compliance with Order 890’s planning principles. Several examples are shown below to illustrate
the diversity of approaches used throughout the nation. Although most of these approaches
involve a combination of beneficiary pays (also referred to as “participant funding”) and
socialization of costs, the details are wholly dissimilar. While Order No. 1000 (discussed in detail
later in this report) has been adopted recently, FERC will continue to allow the regions to define
their own allocation methods. Therefore, the methods briefly summarized here are useful
examples of the methodology that may carry over to filings in compliance with Order No. 1000.
PJM Interconnection29
The cost allocation process established by PJM and approved by FERC allocated costs in terms of
the physical characteristics and purpose of the proposed transmission line:
•
The cost of projects planned by individual utilities to meet local needs rather than
system-wide needs are to be charged to the customers in the zones of PJM that
benefit (i.e., beneficiary pays).
•
Beneficiaries are also to pay for new projects with a rating of less than 500
kilovolts (kV). FERC directed PJM and its customers to develop a standard
methodology for allocating the costs of such projects.
•
For “backbone” transmission projects with a rating of 500 kV or greater—that is,
the proposed lines with the greatest capability to move large amounts of
electricity—costs would be socialized throughout the PJM Interconnection (i.e.,
all customers within PJM would pay a portion of the costs of the facilities,
regardless of their location relative to where the upgrades were made, on the
assumption that all customers would benefit from these “backbone” upgrades).30
The socialization of the costs of 500 kV and greater facilities was controversial from the outset;
for example, the Illinois utility commission reportedly characterized it as “not only unjust and
unreasonable, but patently irrational.”31 On August 6, 2009, the United States Court of Appeals
for the Seventh Circuit, in response to petitions filed by the Ohio and Illinois utility commissions,
rejected PJM’s cost socialization approach and remanded the issue to FERC. The court stated that
FERC is not authorized to approve a pricing scheme that requires a group of utilities to pay
for facilities from which its members derive no benefits, or benefits that are trivial in relation
to the costs sought to be shifted to its members.… No doubt there will be some benefit to the
midwestern utilities just because the network is a network, and there have been outages in
the Midwest. But enough of a benefit to justify the costs that FERC wants shifted to those
utilities? Nothing in the Commission’s opinions enables an answer to that question.”32
29
PJM is the RTO covering a large area centered around the mid-Atlantic region of the United States. “PJM” originally
stood for Pennsylvania, New Jersey and Maryland, but the RTO now encompasses all or part of 13 states and the
District of Columbia.
30
FERC, Order No. 494, PJM Interconnection LLC, Dockets EL-05-121-000 and -002, April 19, 2007; PJM
Interconnection, Compliance filing in response to FERC Order No. 890, Docket OA08-32, December 7, 2009.
31
Jason Fordney, “Exelon, Illinois Commission and DP&L Protest PJM Allocation of Upgrade Costs,” Platts Electric
Utility Week, February 9, 2009.
32
Illinois Commerce Comm'n v. FERC, 576 F.3d 470, 476-477 (7th Cir. 2009) (italics in original) (citations omitted).
Congressional Research Service
7
Electricity Transmission Cost Allocation
This decision is discussed in greater detail below.
New England ISO (NE-ISO)
In NE-ISO the costs of reliability investments with region-wide benefits are paid for by all
customers in the RTO. A reported $4 billion in reliability investments have been made and
allocated region-wide since 2004. The ISO’s rules also provide for cost socialization for
economic investments that provide regional benefits, but “[t]hus far [i.e., through November
2009] there have been no Market Efficiency Upgrades determined to be needed through the
regional system planning process.”33 This experience illustrates how cost socialization for
reliability upgrades can be more easily justified than for economic upgrades. This is because a
failure at one point in a regional grid can potentially disrupt the entire system, while an economic
upgrade may benefit only a subset of the region, making it harder to justify region-wide cost
allocation.
Florida Power and Light Company (FPL)
FPL follows cost allocation procedures approved by the Florida Reliability Coordinating Council
(FRCC), the regional electric grid reliability entity (but not a RTO) covering most of Florida. In
brief, a party may be able to recover a portion of its costs for a new transmission project intended
to serve incremental load or generation if, among other factors, the upgrade will affect the
reliability of the FRCC grid and the transmission owner participates in the FRCC Regional
Transmission Planning Process. If these criteria are met, a portion of the costs associated with the
project will be split evenly between the customers in the zone with the need for the project and
the “sources or cluster of sources” that are creating the need.34
Duke Energy Carolinas and Progress Energy Carolinas
These utilities made a joint filing in response to Order 890. Both companies participate in the
North Carolina Transmission Planning Collaborative (NCTPC) regional transmission planning
process and adopted the organization’s standard cost allocation approach. In summary, that
approach defines exceptions to the general principle that investments in the transmission grid
should be allocated to the initiating utility company and its ratepayers (i.e., beneficiaries pay).
One exception is “Regional Reliability Projects” included in the NCTPC planning process. These
are projects undertaken by one utility that has region-wide reliability benefits; in this case costs
are allocated to other utilities in proportion to the savings each company receives by not having to
undertake its own reliability project.
The second exception is Regional Economic Transmission Path projects that reduce the cost of
transmission service across two or more utility systems. These are envisioned as projects with
multiple participants who will pay the upfront costs of the project. In return the participants will
receive back their investment via payments made by the utilities over a period of up to 20 years.
The utilities in turn will have the opportunity to recover the cost of these payments from
33
FERC Docket AD09-8-000, Transmission Planning Processes Under Order No. 890, “Comments of New England
Power Pool,” November 23, 2009, p. 3.
34
Florida Power & Light Co., Order 890 OATT Compliance Filing – Attachment K, FERC Docket No. OA08-29,
December 7, 2009, pp. 14-16.
Congressional Research Service
8
Electricity Transmission Cost Allocation
ratepayers.35 Economic projects must be included in the NCTPC planning process to qualify for
this type of cost allocation.36
Concluding Comments on Cost Allocation Examples
The examples presented above are only four of the dozens of Order No. 890 cost allocation
filings made with FERC. Nonetheless, they do illustrate several points about current cost
allocation policy at the federal and state levels. First, there is no uniformity in the cost allocation
procedures, and at least to date FERC has declined to go beyond establishing general principles.
Second is the regional focus of all four processes. NE-ISO and PJM are multi-state RTOs and
inherently take a regional perspective, but even the FPL, Duke, and Progress Energy processes
are tied back to regional transmission planning organizations. This is consistent with FERC’s
efforts to encourage a regional perspective on transmission planning that incorporates many
stakeholders in the planning process. Third, these examples illustrate the complexity involved in
socializing transmission costs. The PJM process was rejected by a federal court and remanded to
FERC. The NE-ISO process for socializing the costs of economic projects has never been used.
The NCTPC and FPL cost socialization processes for regional reliability upgrades are fairly
straightforward, but the NCTPC process for socializing economic project costs involves a multistep procedure extending for up to 20 years. FPL did not include socialization of economic
projects in its filing.
Illinois Commerce Commission v. FERC
The debate over the proper method of allocation of transmission costs has not been confined to
the executive and legislative branches of government. In Illinois Commerce Commission v.
FERC,37 the U.S. Court of Appeals for the Seventh Circuit heard a challenge to FERC’s approval
of a cost allocation proposal for certain new transmission facilities in the PJM Interconnection.38
Two state utility commissions in Midwestern states protested a FERC-approved allocation of
transmission costs for the PJM interconnection that required pro rata contributions from all
utilities in the region; that is, the utilities in the PJM region would increase their rates by a
uniform amount sufficient to cover the cost of the new facilities.39 According to the court, FERC’s
rationale for this pro rata increase was that (1) some of the PJM members entered into similar pro
rata cost sharing agreements in the past and would like to continue to allocate costs in that
manner; (2) the burden of determining which parties would benefit from the new transmission
(and to what degree they would benefit) would be onerous and would likely result in litigation;
and (3) that every member of the PJM Interconnection would benefit from the new transmission
facilities because the reliability of the entire network would improve.40
35
That is, the utilities involved retain ownership in the project and recover its capital costs from ratepayers.
Duke Energy Carolinas LLC and Progress Energy Carolinas LLC., Order 890 OATT Compliance Filing –
Attachment K, FERC Docket Nos. OA08-50 and -51, December 7, 2009, pp. 15 – 16, and the attached “NCTPC
Transmission Cost Allocation” statement.
37
576 F.3d 470 (7th Cir. 2009).
38
The court also heard a challenge to the approved cost allocation method for certain upgrades to existing facilities;
however, that discussion is not germane to the subject of this memorandum, and therefore is not discussed here.
39
576 F.3d at 474.
40
Id.
36
Congressional Research Service
9
Electricity Transmission Cost Allocation
The court held that the FERC-approved pro rata rate increase for recovery of transmission costs
was not supported by substantial evidence.41 The court quickly dispatched FERC’s two arguments
in favor of the reasonableness of the pro rata rates. According to the court, the fact that previous
arrangements among the PJM members had pro rata cost sharing arrangements in the past carried
no weight.42 The court rejected FERC’s argument regarding the difficulty of measuring benefits
and the likelihood of litigation, because of an absence of evidence of the relative difficulty of
assessing the benefits.43 The court did not dismiss the possibility of such a finding, noting that
feasibility concerns can play a role in rate determinations.44 However, in this instance, the court
found that FERC had not offered a sufficient explanation for this factor and the role it played in
the rate decision.45
The court spent more time addressing FERC’s third line of reasoning: that the new transmission
facilities would benefit every PJM member, and therefore that the costs should be allocated
among all of them. As the court acknowledged, even though the purpose of the new facilities was
to satisfy demand for eastern customers in the PJM system, the entire PJM system would benefit
from greater reliability as a result.46 However, the court found that it was possible that such
secondary benefits could be minor in relation to the costs to customers not in the eastern region
expected to benefit directly from the new transmission capacity, and that FERC had not provided
any information by which these benefits could be assessed.47 According to the court:
[i]f FERC cannot quantify the benefits to the midwestern utilities from new ... lines in the
East, but it has an articulable and plausible reason to believe that the benefits are at least
roughly commensurate with those utilities’ share of the total electricity sales in PJM’s
region, then ... the Commission can approve PJM’s proposed pricing scheme on that basis.
But it cannot use the presumption to avoid the duty of “comparing the costs assessed against
a party to the burdens imposed or benefits drawn by that party.”48
The impact of this decision on cost allocation going forward is not entirely clear. On the one
hand, as several observers have noted, the case appears to create a new obligation for FERC to
reconsider and potentially discard pro rata allocation of transmission costs.49 However, the ruling
seems to be directed more at FERC’s procedural failure to justify the ratemaking than a
substantive failure in the application of the law. The court repeatedly mentioned that FERC’s
arguments in favor of the pro rata allocation were dismissed not because such a cost allocation
method was unreasonable on its face, but rather because FERC had failed to demonstrate the
reasonableness of the rates. Perhaps the most significant restriction on FERC articulated by the
Seventh Circuit is that FERC must show reason to believe that the benefits received by the parties
are “at least roughly commensurate” with the pro rata cost allocation.50
41
Id. at 478.
Id. at 475.
43
Id.
44
Id.
45
Id.
46
Id. at 476.
47
Id.
48
Id. at 477.
49
Appeals Court Sets Precedent In Rejecting FERC Socialized Grid Costs, EnergyWashington Week (August 26,
2009).
50
576 F.3d. at 477.
42
Congressional Research Service
10
Electricity Transmission Cost Allocation
Legislative Efforts to Dictate Transmission Cost Allocation
Principles
As described above, the FPA’s only direction regarding the allocation of transmission costs are
that the rates charged for transmission service must be “just and reasonable.” This gives FERC
broad authority to dictate transmission cost allocation policy, although that authority has its
limits, as the Illinois Commerce Commission decision demonstrates. However, in recent years
Members of Congress have introduced legislation intended to provide a tighter framework for
FERC’s transmission cost allocation policy.
In the 112th Congress, at least one bill has been introduced that would amend the FPA to
specifically address transmission cost allocation. S. 400, introduced on February 17, 2011, by
Senator Bob Corker, would amend Section 205 of the Federal Power Act to provide that:
No rate or charge for or in connection with the transmission of electric energy contained in
any filing made [by a public utility] after June 17, 2010 shall be considered just and
reasonable unless the rate or charge is based on an allocation of costs for new transmission
facilities that is reasonably proportionate to measurable economic or reliability benefits
projected, as determined by the Commission, to accrue to the 1 or more persons that pay the
rate or charge.
This was not the first legislative effort to adopt principles for transmission cost allocation
requiring that costs be allocated in a way that is “reasonably proportionate to measurable
economic or reliability benefits.” During the 111th Congress, the Senate Committee on Energy
and Natural Resources reported out of committee S. 1462, the American Clean Energy
Leadership Act. The bill contained an amendment proposed by Senator Corker that would direct
FERC to issue a new electricity transmission cost allocation rule that could allow for “allocation
of the costs of high-priority national transmission projects to load-serving entities within all or a
part of a region, except that costs shall not be allocated to a region, or sub-region, unless the costs
are reasonably proportionate to measurable economic and reliability benefits.”51
When the amendment to S. 1462 was proposed during the 111th Congress, some advocates of new
electricity transmission construction expressed concern that it would limit FERC’s ability to
spread costs widely among all users in a given region.52 They also argued that the benefits from a
new transmission project may accrue over many years and therefore may not presently be
“measurable.”53 FERC Chairman Jon Wellinghoff was also critical of the amendment, saying that
it would both restrict the Commission’s ability to spread transmission costs across the region and
also needlessly tie up FERC in litigation over individual transmission cost allocations.54 Three
former FERC chairmen also voiced their disapproval of the amendment, noting in a letter that the
amendment could “hamstring” FERC and that the language could jeopardize planned
infrastructure investment due to uncertainty about cost recovery.55
51
S. 1462 (111th Congress), at §121.
Transmission Groups Push Senate Cost Allocation Provision Changes, EnergyWashington Week, (August 12, 2009).
53
Id.
54
Wellinghoff Criticizes Corker Transmission Cost Sharing Amendment, EnergyWashington Week (October 7, 2009).
55
Id.
52
Congressional Research Service
11
Electricity Transmission Cost Allocation
However, others voiced support for the amendment. A coalition of utilities offered its support,
noting that they believe transmission facility costs should be allocated narrowly in order to focus
on those receiving clear benefits from the new or upgraded facilities.56 Their concern was that the
broad allocation of costs could result in the subsidization of transmission with mostly localized
benefits (for example, Midwest wind power facilities) by those outside the area of direct benefit.57
Others argued that socialization of transmission costs over wide areas would give long-distance
transmission projects an economic advantage over alternatives (such as the local development of
renewable power, including off-shore wind farms, and energy efficiency) which might be
preferable if the playing field was kept level.58
Order No. 1000
After the ruling in Illinois Commerce Commission v. FERC and legislative efforts to amend the
FPA to direct FERC transmission cost allocation decisions, FERC initiated a rulemaking
proceeding to formulate a clearer policy for transmission cost allocation.
Background to the Rulemaking and Initial Comments
FERC initiated Docket AD09-8, Transmission Planning Processes under Order No. 890, on June
30, 2009.59 FERC’s first action under this docket, in September 2009, was to hold technical
conferences on transmission planning with transmission owners, operators, and other stakeholders
in Atlanta, Phoenix, and Philadelphia. Based on these meetings, the Commission concluded that
significant issues remained with the effectiveness of transmission planning generally and regional
and inter-regional planning specifically; the treatment of certain types of electricity resources in
the planning process (such as renewable power); and cost allocation for new transmission
projects. In relation to cost allocation, the Commission found that:
Determining the costs and benefits of adding transmission infrastructure to the grid is a
complex process, particularly for projects that affect multiple systems and therefore may
have multiple beneficiaries. At the same time, the expansion of regional power markets and
the increasing adoption of renewable energy requirements have led to a growing need for
transmission projects that cross multiple utility and RTO systems. There are few rate
structures in place today that provide the allocation and recovery of costs for these intersystem projects, creating significant risk for developers that they will have no identified
group of customers from which to recover the cost of their investment. [emphasis added]60
Following these meetings, FERC signaled, in an October 8, 2009, notice requesting comments on
cost allocation and other transmission planning issues, that it may take a more direct approach
toward cost allocation processes than in the past. The Commission noted that its “best remaining
56
Transmission Cost Allocation Fight Intensifies With New Pro-Corker Group, EnergyWashington Week (November
11, 2009).
57
Id.
58
Id.
59
Filings under this docket can be accessed through the FERC docket search web page, at http://elibrary.ferc.gov/
idmws/docket_search.asp.
60
FERC, Docket No. AD09-8-000, Transmission Planning Processes Under Order No. 890, “Notice of Request for
Comments,” October 8, 2009, p. 5.
Congressional Research Service
12
Electricity Transmission Cost Allocation
opportunity to eliminate barriers to new transmission construction may therefore be to provide
greater certainty in its policies for allocating the cost of new transmission facilities, particularly
for facilities that cross multiple transmission systems.”61 The specific questions for which FERC
requested comments also provide a window into FERC’s thinking. The questions included,
among others:
•
How can the beneficiaries of a specific project be identified, and should the
delineation of beneficiaries include generators in addition to loads? The unstated
but concomitant question is how should the level of benefits, and therefore the
cost responsibility of different customer groups, be determined? This goes to the
heart of the issue raised by the Seventh Circuit’s rejection of the PJM
Interconnection cost allocation process.62
•
Should cost allocation processes be designed to cover larger geographic regions?
This would seem to raise the contentious issue of whether costs should be
allocated over large areas and perhaps interconnection-wide.
•
Should cost allocations be static or change over time? This question was posed
by FERC as a general issue, and specifically in respect to transmission lines
which are initially built with overcapacity in anticipation of demand growth.
•
How, if at all, should non-quantifiable costs and benefits be incorporated into
cost allocations?63
By the end of November 2009 FERC had received 103 sets of comments. The comments manifest
a wide range of opinions on how FERC should proceed. For example:
•
American Electric Power, a large utility company operating within the PJM, SPP,
and ERCOT RTOs, argued for interconnection-wide planning and cost allocation
for extra-high voltage transmission lines, to be implemented by a FERC
rulemaking.64
•
Southern Company, a large southeastern utility operating outside of RTOs,
rejected the whole notion that problems with transmission planning and cost
allocation were inhibiting transmission development. Southern concluded that:
A significant misconception being promoted by certain aspects of the industry
in the name of promoting renewable resources is that the current transmission
planning processes and cost allocation methodologies are obstacles to the
expansion of the transmission grid. This is not the case. The reason that more
inter-regional transmission projects are not being built, at least in the
Southeast, is that they have not proven to be economic as compared to other
options. As a result, those who would benefit from these projects desire to
have other entities subsidize their costs by seeking to mandate the planning of
61
Id. at 7 (emphasis added).
Illinois Commerce Comm’n v. FERC, 576 F.3d 470 (7th Cir. 2009).
63
FERC, Docket No. AD09-8-000, Transmission Planning Processes Under Order No. 890, “Notice of Request for
Comments,” October 8, 2009, p. 7-8. An example of a non-quantifiable benefit may be the use of existing transmission
right of ways for new or upgraded transmission lines, in order to avoid the time and controversy that can accompany
efforts to place lines in new right of ways.
64
FERC Docket No. AD09-8-000, Transmission Planning Processes Under Order No. 890, “Comments of American
Electric Power Service Corporation,” November 23, 2009, pp. 23-24.
62
Congressional Research Service
13
Electricity Transmission Cost Allocation
these projects through restructured “top-down” planning processes and through
the broad socialization of the costs of such uneconomic transmission projects.65
•
The New England Power Pool Participants Committee (a committee of
stakeholders operating within the NE-ISO) stated that “it would be helpful for the
Commission to provide policy guidance on how it would treat a range of cost
allocation options.” [emphasis in the original]66 However, the committee was
opposed to the establishment of interconnection-wide or national cost allocation
rules, or to the notion of interconnection-wide cost allocation.67
•
The Southwest Power Pool RTO suggested that FERC implement standardized
rules for inter-regional transmission planning and cost allocation. It also
supported the establishment of cost allocation processes across broad areas, such
as the Eastern Interconnection.68 SPP stated that:
attempts to precisely define benefits are misplaced. The real benefits of a major
transmission project, as part of a robust EHV network, over its useful life will
never be fully captured in an economic model as there are many benefits that
fall outside the scope of economic modeling. While precise analysis may be
desirable, the limitations of such analysis must be acknowledged. Moreover, it
is important to recognize that doing nothing also has a cost…. Currently, SPP
is working to implement a cost allocation method that would even provide
more cost sharing for regional projects and simplify the cost allocation.69
•
In virtually complete contradiction to the position of SPP, the Electricity
Consumers Resource Council (ELCON), an association of industrial electricity
users, emphasized that cost allocation should follow a fundamental principal of
“beneficiary pays.” Rather than viewing the issue of allocating benefits as a
stumbling block to transmission project development, ELCON stated that:
[A]s FERC notes in the Request [for comments], how to allocate costs is “not a
new problem.” Indeed, courts have developed a carefully crafted body of law to
guide the allocation of the costs of transmission investment, centering on the
principle that the beneficiaries of a service are to pay for it.
[T]hose who are allocated costs based on actual, demonstrable benefits are less
likely to object to the construction of new transmission facilities than those who
are allocated costs based on an assumption that they will receive some general,
unquantifiable benefit. The “beneficiary pays” model is, therefore, more likely to
reduce controversy and assure that future transmission would be built where the
costs truly are justified.70
65
FERC Docket No. AD09-8-000, Transmission Planning Processes Under Order No. 890, “Initial Comments of
Southern Company Services, Inc.,” November 23, 2009, p. 3.
66
FERC Docket No. AD09-8-000, Transmission Planning Processes Under Order No. 890, “Comments of New
England Power Pool,” November 23, 2009, p. 7.
67
FERC Docket No. AD09-8-000, Transmission Planning Processes Under Order No. 890, “Comments of New
England Power Pool,” November 23, 2009, pp. 7 - 8.
68
FERC Docket AD09-8-000, Transmission Planning Processes Under Order No. 890, “Comments of Southwestern
Power Pool, Inc., Regarding Transmission Planning Processes Under Order No. 890,” November 23, 2009, p. 12.
69
Id. at p. 13.
70
FERC Docket AD09-8-000, Transmission Planning Processes Under Order No. 890, “Comments of the Electricity
Consumers Resource Council” November 23, 2009, pp. 2 and 14.
Congressional Research Service
14
Electricity Transmission Cost Allocation
The diversity of these comments indicated the lack of agreement on how FERC should have
proceeded in respect to cost allocation. In November 2009, at about the same time these
comments were filed, a transmission trade group and a consortium of environmental groups filed
separate petitions with FERC asking the Commission to establish a rulemaking to set
transmission cost allocation standards.71
The Final Rule72
The rulemaking proceeding culminated with the issuance of Order No. 1000 on July 21, 2011.
Order No. 1000 states that the Commission is amending Order No. 890 to ensure that FERCjurisdictional transmission services are provided at just and reasonable rates, and on a basis that is
just and reasonable, and not unduly discriminatory or preferential. The following paragraphs
summarize the Final Rule (which becomes effective October 11, 2011) and its major
requirements.
Planning Requirements
Order No. 1000 establishes three requirements for transmission planning:
•
Public utility transmission providers are required to participate in a regional
transmission planning process that satisfies Order No. 890 principles and
produces a regional transmission plan.
•
Local and regional transmission planning processes must consider transmission
needs driven by public policy requirements established by state or federal laws or
regulations.
•
Public utility transmission providers in each pair of neighboring planning regions
must coordinate to determine if more efficient or cost-effective solutions are
available.
Order No. 1000 further requires that each transmission provider participate in a regional
transmission planning process that includes both a regional cost allocation method for the cost of
new transmission facilities selected in a regional transmission plan and an interregional cost
allocation method for the cost of certain new transmission facilities located in two or more
neighboring transmission planning regions.
Cost Allocation Requirements
Order No. 1000 establishes three additional requirements for transmission cost allocation:
•
Regional transmission planning process must have a regional cost allocation
method for a new transmission facility selected in the regional transmission plan
71
Peter Behr, “FERC Enters a Maze of Questions About Renewable Energy Transmission,” The New York Times,
November 23, 2009, http://www.nytimes.com/cwire/2009/11/23/23climatewire-ferc-enters-a-maze-of-questions-aboutrenewa-29763.html?scp=3&sq=Conservation%20Law%20Foundation&st=cse.
72
Transmission Planning and Cost Allocation by Transmission, 136 FERC ¶ 61,051, 76 Fed. Reg. 49,842 (August 11,
2011).
Congressional Research Service
15
Electricity Transmission Cost Allocation
for purposes of cost allocation. The cost allocation method must satisfy six
regional cost allocation principles.
•
Neighboring transmission planning regions must have a common interregional
cost allocation method for a new interregional transmission cost facility that the
regions select. Cost allocation method must satisfy six similar interregional
cost allocation principles.
•
Participant-funding of new transmission facilities is permitted, but is not allowed
as the regional or interregional cost allocation method unless the individual
market participants agree to it.
While FERC declines to specify a standard or preferred methodology in Order No. 1000, it does
require each regional or interregional cost allocation method to satisfy six generalized cost
allocation principles:
•
Regional cost allocation principle 1: The cost of transmission facilities must be
allocated to those within the transmission planning region that benefit from those
facilities in a manner that is at least roughly commensurate with estimated
benefits.73
Interregional cost allocation principle 1: The costs of a new interregional
transmission facility must be allocated to each transmission planning region in
which that transmission facility is located in a manner that is at least roughly
commensurate with the estimated benefits of that transmission facility in each of
the transmission planning regions.74
•
Regional cost allocation principle 2: Those that receive no benefit from
transmission facilities, either at present or in a likely future scenario, must not be
involuntarily allocated any of the costs of those transmission facilities.75
Interregional cost allocation principle 2: A transmission planning region that
receives no benefit from an interregional transmission facility that is located in
that region, either at present or in a likely future scenario, must not be
involuntarily allocated any of the costs of that transmission facility.76
•
Regional cost allocation principle 3: If a benefit to cost threshold is used to
determine which transmission facilities have sufficient net benefits to be selected
in a regional transmission plan for the purpose of cost allocation, it must not be
so high that transmission facilities with significant positive net benefits are
excluded from cost allocation.77
Interregional cost allocation principle 3: If a benefit-cost threshold ratio is used
to determine whether an interregional transmission facility has sufficient net
benefits to qualify for interregional cost allocation, this ratio must not be so large
73
Id. at P 622.
Id.
75
Id. at P 637.
76
Id.
77
Id. at P 646.
74
Congressional Research Service
16
Electricity Transmission Cost Allocation
as to exclude a transmission facility with significant positive net benefits from
cost allocation.78
•
Regional Cost Allocation Principle 4: The allocation method for the cost of a
transmission facility selected in a regional transmission plan must allocate costs
solely within that transmission planning region unless another entity outside the
region or another transmission planning region voluntarily agrees to assume a
portion of those costs.79
Interregional Cost Allocation Principle 4: Costs allocated for an interregional
transmission facility must be assigned only to transmission planning regions in
which the transmission facility is located. Costs cannot be assigned involuntarily
under this rule to a transmission planning region in which that transmission
facility is not located.80
•
Regional Cost Allocation Principle 5: The cost allocation method and data
requirements for determining benefits and identifying beneficiaries for a
transmission facility must be transparent with adequate documentation to allow a
stakeholder to determine how they were applied to a proposed transmission
facility.81
Interregional Cost Allocation Principle 5: The cost allocation method and data
requirements for determining benefits and identifying beneficiaries for an
interregional transmission facility must be transparent with adequate
documentation to allow a stakeholder to determine how they were applied to a
proposed interregional transmission facility.82
•
Regional Cost Allocation Principle 6: A transmission planning region may
choose to use a different cost allocation method for different types of
transmission facilities in the regional transmission plan, such as transmission
facilities needed for reliability, congestion relief, or to achieve Public Policy
Requirements.83
Interregional Cost Allocation Principle 6: The public utility transmission
providers located in neighboring transmission planning regions may choose to
use a different cost allocation method for different types of interregional
transmission facilities, such as transmission facilities needed for reliability,
congestion relief, or to achieve Public Policy Requirements.84
Nonincumbent Developer Requirements
The Final Rule curtails the existing right of first refusal for incumbent transmission providers
previously had to build new transmission lines. FERC concludes in Order No. 1000 that retaining
78
Id.
Id. at P 657.
80
Id.
81
Id. at P 668.
82
Id.
83
Id. at P 685.
84
Id.
79
Congressional Research Service
17
Electricity Transmission Cost Allocation
a federal right of first refusal for transmission facilities selected in a regional transmission plan
for purposes of cost allocation could result in rates for FERC-jurisdictional services that are
unjust and unreasonable, or could otherwise result in undue discrimination by public utility
transmission providers. This aspect of the Final Rule will not affect any state or local laws or
regulations regarding the construction of transmission facilities (including but not limited to siting
or permitting), or the following types of projects:
•
The transmission facility is not in a regional transmission plan for purpose of cost
allocation.
•
The transmission facility is not a result of an upgrade to existing transmission
facilities, such as a tower change out or reconductoring.
•
The new transmission facility has already been subject to a regional process
which allows non-incumbent developers to compete with incumbents.
Compliance
Order No. 1000 will take effect on October 11, 2011, 60 days after publication in the Federal
Register. Each public utility transmission provider is required to make a compliance filing by
October 11, 2012, or within 12 months of the effective date of the Final Rule. Compliance filing
for interregional transmission coordination and interregional cost allocation must be filed within
18 months of the effective date, that is by April 11, 2013. FERC expects that some RTO regions
may submit their existing procedures as being compliant with Order No. 1000’s regional cost
allocation requirements.
Order No. 1000 does not provide details regarding how FERC might enforce the Final Rule.
Public utility transmission providers are given schedules for compliance filings, and revision of
OATT schedules to reflect cost allocation methods as transmission providers are required to show
that they meet the provisions of the Final Rule. It is possible that potential issues regarding the
formation of regions could affect transmission provider compliance.
Specific Observations on the Final Rule
Planning Requirements
The need for transmission planning has traditionally resulted from load growth and the need to
connect new power generation resources to load centers. More recently, an increased focus on
power markets and reliability has caused discussion on the need for new transmission lines. With
Order No. 1000, FERC has issued regulations which seek to add state and federal public policies
as a factor in the decision-making process concerning which transmission projects emerge from
planning processes as construction projects. However, FERC’s use of the word “consider”85 with
regard to state or federal public policy requirements (i.e., as a factor in the planning process) may
not be enough of an imperative to actually push such transmission projects forward.
85
Order No. 1000 requires that public utility transmission providers establish a process for identifying those
transmission needs driven by Public Policy Requirements that are to be considered in the transmission planning
process. Id. at P 546.
Congressional Research Service
18
Electricity Transmission Cost Allocation
In the wake of the issuance of the Final Rule, the American Public Power Association (APPA)
observed that FERC may already have had the authority to move transmission projects forward
which are driven by the needs of load-serving entities (LSEs). APPA believes that transmission
planning should also focus on LSE needs as stipulated in the FPA, which by necessity may likely
include transmission facilities to access renewable resources as mandated by state RPS
requirements and other clean energy resources necessitated by state and federal environmental
regulations.86 APPA refers to section 217(b)(4) of the FPA, which states following:
The Commission shall exercise the authority of the Commission under this Act in a manner
that facilitates the planning and expansion of transmission facilities to meet the reasonable
needs of load-serving entities to satisfy the service obligations of the load-serving entities ...
Cost Allocation Requirements
Definition of benefits will likely be key in determinations of cost allocation. Order No. 1000
discusses many different types of potential benefits (e.g., economic, reliability, system-wide, etc.)
but does not seek to define specifically what a benefit is. The definition of benefits will lead to
the identification of beneficiaries, and thence to the identification of how much and to whom
costs will be allocated to. FERC is not prescribing a particular definition of “benefits” or
“beneficiaries” in this Final Rule. FERC noted that “[i]n our view, the proper context for further
consideration of these matters is on review of compliance proposals and a record before us.”87
FERC does not propose interconnection-wide cost allocation as a regional allocation method for
transmission facilities. The regions will define benefits, and FERC considers at least three
primary areas for benefits will be considered—reliability, economics and public policy. Order No.
1000 states there will be no cost allocation where there is no benefit:
Those that receive no benefit from new transmission facilities, either at present or in a likely
future scenario, must not be involuntarily allocated any of the costs of those facilities. That
is, a utility or other entity that receives no benefit from transmission facilities, either at
present or in a likely future scenario, must not be involuntarily allocated any of the costs of
those facilities.88
FERC also believes this Final Rule will protect transmission customers from free riders, that is,
those who receive benefits without paying for them. Order No. 1000 addresses the “free rider”
issue by invoking cost-causation principles:
In Order No. 890, the Commission recognized that the cost causation principle provide that
costs should be allocated to those who cause them to be incurred and those that otherwise
benefit from them. We conclude now that this principle cannot be limited to voluntary
arrangements because if it were “the Commission could not address free rider problems
associated with new transmission investment, and it could not ensure that rates, terms and
conditions of jurisdictional service are just and reasonable and not unduly discriminatory.89
86
Inside EPA - CLEAN ENERGY REPORT, Public Power Says FERC Clean Energy Order Abdicates Legal
Requirement, August 22, 2011, http://cleanenergyreport.com/iwpfile.html?file=aug2011%2Fce08222011_appa.pdf.
87
136 FERC at P 624.
88
Id. at P 219.
89
Id. at P 84.
Congressional Research Service
19
Electricity Transmission Cost Allocation
FERC is allowing the regions to define themselves, with the caveat that there must be more than
one utility in a region. Existing RTOs or ISOs are considered “natural regions that have
agreements in place already that will define those regions.”90 FERC expects that these regions
will be defined by transmission-owning utilities.91 It should also be recognized that some RTOs
stretch over non-continuous areas, which may lead to some RTO/ISOs or their members being in
more than one transmission planning region.
The definition of transmission-owning utility may be a complicating factor as some
owners/operators of generation facilities have been designated as transmission owners for
reliability purposes.92 Such entities could also be impacted by aspects of requirements from the
Final Rule.
Established regulatory principles may also bear on the definition of benefits, especially if rate
recovery extends to state jurisdictions or if states (or portions of states) are considered planning
regions. Timing is very important to the definition of benefits, as principles of intergenerational
equity may arise. FERC has stated that consideration of public policies should be limited to
existing policies. The time frame to which these existing policies apply would likely be used as
the limit to the planning horizon for which benefits and their costs could be allocated to
beneficiaries based on established “cost-causation” principles. Alternatively, under “used and
useful” ratemaking principles, the allocation of costs could be spread over the life of the
transmission facility asset itself, and the benefits timeline may be allocated over such a lifespan.
Nonincumbent Developer Requirements
FERC makes a distinction between a transmission facility in a regional plan, and a transmission
facility selected in a regional plan for purposes of cost allocation. FERC considers the latter a
more efficient/cost-effective solution to regional needs, presumably by virtue of being selected
pursuant to a Commission-approved regional planning process, even though there are no standard
procedures for a process likely to be approved by FERC. FERC assumes that the region will
select the most efficient solution since a cost-allocation scheme has been settled on by
transmission owning interests. This distinction also seems to illuminate the partial elimination of
a right of first refusal (ROFR) of a transmission provider to build a transmission facility chosen
for regional cost allocation. FERC is not preempting any state or local law or regulation that
establishes a ROFR, and only eliminates the ROFR in this very limited situation.
Order No. 1000 notes that each transmission provider would be required to amend its OATT if a
transmission facility project selected in a regional plan for purposes of cost allocation is delayed.
Local utilities would then be allowed to consider alternative solutions to ensure that reliability
needs and service obligations are met.
90
E&E TV, FERC - Chairman Wellinghoff discusses commission’s challenges in crafting transmission rule, July 26,
2011, http://www.eenews.net/tv/transcript/1382.
91
Response to question at FERC briefing on Final Rule. July 22, 2011.
92
For example, on June 16, 201, FERC denied an appeal by two wind farm generators (Cedar Creek Wind Energy,
LLC and Milford Wind Corridor Phase I, LLC.) against a NERC order to register as transmission owners and
operators. NERC had ordered the generators to comply with transmission-related reliability requirements applicable to
transmission-owners and operators because of high voltage (i.e., above 100 kV) tie-lines interconnecting their
generating facilities to the bulk power system. Cedar Creek Wind Energy LLC, Milford Wind Corridor Phase I, LLC,
136 FERC P 61,241 (2011).
Congressional Research Service
20
Electricity Transmission Cost Allocation
General Comments
Order No. 1000 is broadly intended to ensure that there is enough transmission capacity to meet
future U.S. electricity needs, and provide for the allocation of new costs to build the transmission
facilities by “identify[ing] transmission facilities that more efficiently or cost-effectively meet the
region’s reliability, economic and public policy requirements.”93
In paragraph 29 of Order No. 1000, FERC cites the expectations of the U.S. Department of
Energy and NERC with regard to the expansion of high-voltage transmission lines and facilities,
with up to a third of this new transmission capacity intended to serve new variable and renewable
energy generation. State renewable energy portfolio standards are seen as a major driver of this
new capacity. However, with most of the best regions for wind and solar resources located in the
western United States, and many of the load centers and many states with RPS requirements in
the eastern part of the country, some observers have discussed the potential for long, interstate
transmission lines to carry renewable energy to markets in the east. Order No. 1000 allows for
neighboring transmission planning regions to work out interregional plans for state public policies
such as RPS requirements. In the absence of a federal renewable energy or clean energy standard,
an imperative for a west-to-east, multistate renewable energy transmission line is unlikely, but a
segmented build-out of transmission facilities could accomplish a similar goal if benefits to local
regions can be shown. In that instance, the technologies and facility designs chosen to accomplish
the build out could be crucial to a benefits determination since alternating current transmission
lines have the potential for future “on- and off-ramps” to serve load growth along such routes,
while direct current transmission lines are limited in that capability.
Federal regulations may reduce the need for states or regions to have their own regulations to
address the same or similar issues. As such, federal regulations ease interstate commerce because
a multiplicity of state regulations is avoided, especially when the regulations developed in states
and regions addressing a specific issue can differ substantially. In Order No. 1000, FERC intends
to provide broad guidance on planning transmission facilities and cost allocation, while allowing
regions to tailor such arrangements to their own or interregional requirements with consideration
given to public policy goals:
The cost allocation principles are not intended to prescribe a uniform approach, but rather
each public utility transmission provider should have the opportunity to first develop its own
method or methods. Also, we recognize that regional differences may warrant distinctions in
cost allocation methods.94
Thus, in providing such discretion, FERC leaves the door open for broad interpretation of the
regulations, with the likelihood that a wide variation of plans will result.
FERC states in Order No. 1000 that transmission planners should seek the most efficient and
cost-effective ways to meet the transmission needs of regions. Order No. 1000 also identifies a
transmission facility selected in a regional plan for cost allocation purposes as a “more efficient
or cost-effective solution to regional transmission needs.”95 Sometimes, the optimal location of a
power generation facility can ease congestion-related reliability issues, and present a cost
93
Order No. 1000, 136 FERC at P 11.
Id. at P 604.
95
Id at P 7.
94
Congressional Research Service
21
Electricity Transmission Cost Allocation
effective solution with potential benefits to other regional transmission needs. It is not clear to
what extent the regional transmission planners will be required to think broadly and consider a
power generation solution when considering Order No. 1000 requirements for the most “efficient
or cost-effective solution” to regional power needs.
The Final Order comes as state renewable portfolio requirements and the upcoming U.S.
Environmental Protection Agency (EPA) regulations for coal power plants96 may increase
demand for new transmission lines. The uncertainty regarding the implications for generation
resources of upcoming EPA regulations has caused some utilities to delay decisions on building
new generation, with plans to satisfy (at least interim) power needs from power markets until the
regulatory clarity they seek is provided. Some commenters expect that shortfalls in transmission
capacity in some regions of the United States may have possible impacts on reliability resulting
from these additional needs. State public utility commission decisions authorizing new power
plants in rate base to replace retired coal plants will likely impact regional transmission planning
decisions.
There are many issues and many questions beyond those discussed in this report which will likely
arise as the many different stakeholders involved move to understand and satisfy their obligations
under the Final Rule. FERC acknowledges that some key questions may only be answered in the
compliance filing process.
Update on Order 1000
FERC issued Order 1000-A97 on May 17, 2012, to deny many rehearing requests for its Order
1000, affirming that all jurisdictional electric transmission providers must comply with Order
1000’s requirements to participate in regional and interregional planning processes for planning
new transmission facilities. Transmission cost allocation methods specified in Order 1000 are to
be employed for these new transmission facilities.
FERC subsequently issued Order 1000-B98 on October 18, 2012, to uphold its previous Orders
1000 and 1000-A, and to make clarifications to its rule. FERC again denied any requests for
rehearing of Order 1000 or Order 1000-A.
Author Contact Information
(name redacted)
Specialist in Energy Policy
[redacted]@crs.loc.gov, 7-....
(name redacted)
Legislative Attorney
[redacted]@crs.loc.gov, 7-....
96
CRS Report R41914, EPA’s Regulation of Coal-Fired Power: Is a “Train Wreck” Coming?, by (name redacted)
and (name redacted).
97
139 FERC ¶ 61,132.
98
141 FERC ¶ 61,044.
Congressional Research Service
22
EveryCRSReport.com
The Congressional Research Service (CRS) is a federal legislative branch agency, housed inside the
Library of Congress, charged with providing the United States Congress non-partisan advice on
issues that may come before Congress.
EveryCRSReport.com republishes CRS reports that are available to all Congressional staff. The
reports are not classified, and Members of Congress routinely make individual reports available to
the public.
Prior to our republication, we redacted names, phone numbers and email addresses of analysts
who produced the reports. We also added this page to the report. We have not intentionally made
any other changes to any report published on EveryCRSReport.com.
CRS reports, as a work of the United States government, are not subject to copyright protection in
the United States. Any CRS report may be reproduced and distributed in its entirety without
permission from CRS. However, as a CRS report may include copyrighted images or material from a
third party, you may need to obtain permission of the copyright holder if you wish to copy or
otherwise use copyrighted material.
Information in a CRS report should not be relied upon for purposes other than public
understanding of information that has been provided by CRS to members of Congress in
connection with CRS' institutional role.
EveryCRSReport.com is not a government website and is not affiliated with CRS. We do not claim
copyright on any CRS report we have republished.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.