Line 5 Pipeline: Relocation and Permitting

Congressional research reportJan 23, 2026

Ask Donna

What actually matters in this document.

Text

INSIGHTi

Line 5 Pipeline: Relocation and Permitting

Updated January 23, 2026

Line 5 is a 30-inch diameter, 645-mile pipeline owned by Enbridge carrying crude oil and natural gas

liquids from Superior, WI, to Sarnia, Ontario (Figure 1). A key segment of Line 5 is an underwater

crossing at the Straits of Mackinac—between Michigan’s upper and lower peninsulas—where it runs

across the lakebed. This crossing has been an environmental concern due to the risk of a “worst case” oil

spill into the Great Lakes. Another key segment crosses the Bad River Reservation in northern Wisconsin,

where there are also environmental concerns.

Figure 1. Enbridge Line 5 Pipeline

Source: CRS using data from Platts, and Esri Data & Maps.

Under the terms of various state agreements, Enbridge plans to replace the Michigan pipeline segment

with a new one constructed through a tunnel beneath the lakebed, and it plans to reroute the Wisconsin

segment around the reservation. Both plans require federal approval. However, the State of Michigan and

tribal groups, for different reasons, are seeking to permanently shut down Line 5. Whether the pipeline

should continue operating is the subject of litigation, federal oversight, and a U.S.-Canada treaty dispute.

Congressional Research Service

https://crsreports.congress.gov

IN11798

CRS INSIGHT

Prepared for Members and

Committees of Congress

Congressional Research Service

2

Michigan Easement Challenges

Line 5 was constructed in 1953 as part of a pipeline system linking oil fields in Alberta, Canada, to

refineries in the Great Lakes region. At the time, Michigan granted Enbridge’s predecessor—Lakehead

Pipe Line Company—an easement to cross the Straits of Mackinac. In October 2018, Michigan and

Enbridge entered an agreement whereby Enbridge would construct a tunnel under the straits and replace

the existing Line 5 segment with a new segment through the tunnel. The agreement was followed by a

December 2018 state statute creating the Mackinac Straits Corridor Authority, which subsequently

authorized assignment of easement rights for tunnel construction.

Notwithstanding Enbridge’s prior state agreements, in 2019, a new gubernatorial administration filed a

complaint in state court seeking to shut down the lakebed segment of Line 5 due to it being a “public

nuisance” that was “likely to cause pollution.” On November 13, 2020, Michigan officials notified

Enbridge that the 1953 easement was being revoked, requiring the Line 5 lakebed segment to cease

operating within 180 days—which would effectively shut down the entire pipeline. Since that time,

Line 5 has continued operating, but there has been ongoing litigation in both federal and state courts

regarding the easement and the pipeline. Most recently, on January 6, 2026, Michigan filed an appeal of a

federal court ruling that the state lacked the authority to order a Line 5 shutdown because the pipeline is

under exclusive federal jurisdiction. On April 23, 2025, a federal appeals court upheld a lower court’s

ruling that Enbridge could sue Michigan’s governor for revoking the easement. On June 30, 2025, the

U.S. Supreme Court agreed to consider an aspect of the litigation.

Tunnel Permit Requirements

In April 2020, prior to the revocation of the Michigan easement, Enbridge filed a joint application with

the Michigan Department of Environment, Great Lakes, and Energy (EGLE) and the U.S. Army Corps of

Engineers (Corps) to build the Line 5 tunnel. In January 2021, EGLE announced that it had approved

Enbridge’s application for permits required to build the tunnel. EGLE stated that the existing pipeline

“poses an unacceptable risk to the Great Lakes,” but nevertheless concluded that the project could comply

with state environmental laws. On December 1, 2023, the Michigan Public Service Commission (MPSC)

separately approved Enbridge’s siting application to the commission for the tunnel project, concluding

that “without the pipeline’s operation, suppliers would need to use higher-risk and costlier alternative fuel

supply sources.” On April 2, 2025, tribal groups filed an appeal with the Michigan Supreme Court

seeking to overturn a lower court’s decision upholding the MPSC’s approval.

The Corps has permitting authority over the proposed tunnel project pursuant to Section 404 of the Clean

Water Act (33 U.S.C. §1344) and Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. §403). In

June 2023, the Corps stated that its environmental review of Enbridge’s permit applications would be

“limited to the proposed crossing of the Straits of Mackinac,” including associated construction activities.

Some advocates have expressed concerns about the greenhouse gas emissions associated with the fossil

fuels passing through the pipeline. The agency stated that “these factors are not within the Corps’ scope of

analysis.”

In April 2025, the Corps announced that, in accordance with President Trump’s Executive Order 14156

(“Declaring a National Energy Emergency”), the tunnel project was “subject to special emergency

permitting procedures.” On November 13, 2025, the Corps issued a Supplemental Draft Environmental

Impact Statement for the tunnel project, initiating a comment period ending December 5, 2025.

Congressional Research Service

3

Bad River Reservation Easement

The Bureau of Indian Affairs granted the original easement for Line 5 across the Bad River Reservation in

1953. The easement expired in 2013. Subsequently, the Bad River Band of Lake Superior Chippewa

(tribe) has been seeking the removal of the pipeline from its reservation due to concerns about a potential

oil spill. In June 2023, a federal court ordered Enbridge to reroute Line 5 around the tribal land in

Wisconsin—or shut it down—within three years. Both the tribe and Enbridge have appealed this ruling to

the U.S. Court of Appeals for the 7th Circuit. The tribe opposes a project to reroute the pipeline outside the

reservation but still within its watershed. In November 2024, the Wisconsin Department of Natural

Resources issued state permits required for the reroute. Most recently, on December 16, 2025, the tribe

filed a complaint in federal court challenging a Corps permit for the reroute project.

U.S.-Canada Pipeline Treaty

The Canadian government has strongly supported the continued operation of Line 5. Canada has sought to

intervene though public statements and court filings, citing a 1977 pipeline treaty with the United States

that, among other provisions, prohibits a “public authority in the territory of either” from instituting “any

measures … which are intended to, or which would have the effect of, impeding, diverting, redirecting or

interfering with in any way the transmission of hydrocarbon in transit.” In October 2021, Canada

announced that it was formally invoking the dispute settlement provision of the treaty regarding Line 5.

Canadian and U.S. officials have been “engaged in ongoing negotiations” regarding the treaty dispute, but

details have not been publicly released.

Author Information

Paul W. Parfomak

Specialist in Energy Policy

Disclaimer

This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff

to congressional committees and Members of Congress. It operates solely at the behest of and under the direction of

Congress. Information in a CRS Report should not be relied upon for purposes other than public understanding of

information that has been provided by CRS to Members of Congress in connection with CRS’s institutional role.

CRS Reports, as a work of the United States Government, are not subject to copyright protection in the United

States. Any CRS Report may be reproduced and distributed in its entirety without permission from CRS. However,

as a CRS Report may include copyrighted images or material from a third party, you may need to obtain the

permission of the copyright holder if you wish to copy or otherwise use copyrighted material.

IN11798 · VERSION 8 · UPDATED

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.