Gu the Gnited States Court of Claims

No. 50403

(Decided January 11, 1955)

RUSSELL H. WILLIAMS, d/b/a WILLIAMS EQUIP-

MENT CO., AND REED & MARTIN, INC., A COR-

PORATION v. THE UNITED STATES

Mr. William H. Ferguson for the plaintiffs. Mr. Donald

McL. Davidson was on the briefs.

Mr. Kendall M. Barnes, with whom was Mr. Assistant

Attorney General Warren E. Burger, for the defendant.

OPINION

Jones, Chief Judge, delivered the opinion of the court:

This case involves a contract between the plaintiffs and

the defendant for the construction of a paved road at Fair-

banks, Alaska. The facts have been set out in detail in our

findings and will be referred to only to the extent necessary

for an understanding of the issues which gave rise to the suit.

The principal issue has to do with the amount of borrow

material which was excavated by the plaintiffs and put in

place on the road. The contract provided for payment for

the borrow material at $1.29 per cubic yard and the payment

for hauling the material beyond a certain distance at a unit

price of 32 cents per cubic-yard mile. The borrow material

yardage to be paid for was to be measured in its original

position in the borrow pit, which yardage was to be computed

by the average end area method, and the overhaul item was

to be paid upon the measurement of material in its original

position times the overhaul distance in miles and fractions

thereof. In other words, an important consideration in de-

termining the amount due the plaintiffs was a determination

of the amount of borrow material in its original position.

(1A)

NR ADHERE AP ARO EH ORY sl BE ATI TAD EE BY aces ARG MOTT BE eR IE Cy Pm of ate " AL Roeser aii

2A

The face of the quarry rose from a flat surface at a steep,

though not vertical, angle. The average end area method

contemplated that surveys be made of the vertical profile of

the quarry at frequent intervals along its face, both at the

beginning and at the end of the quarrying operations. The }

extent to which the profile upon final survey had receded

from its original position would then be the basis for meas-

uring the amount of material that had been removed from

the quarry. At or about the time the plaintiffs began work a t

survey was made of the quarry. After some 30 or 40 percent

of the excavation work had been completed, a slide occurred

at the quarry in which a large amount of material moved

downward and outward toward the base line where the plain-

tiffs were operating. The amount of material moved was esti-

mated by a witness for the defendant as from 30,000 to 50,000

cubic yards, and by witnesses for the plaintiffs as from 200,000

to 400,000 cubic yards. <A fair statement from the evidence

would be that defendant’s witness was too conservative and

the estimates of plaintiffs’ witnesses excessive. Whatever

may be the correct amount, when we consider that the total

amount of material moved, as computed by plaintiffs, was

99,592 cubic yards and that 34,596 had been removed at the

time of the slide, the possible effect of such a slide on the com-

putation of material in place by the average end area method

can be seen.’ Not only did material come into the area from

FI RT ROE B 8

Fy

[ ,

“ae.

2The slide created several difficulties in applying this method of measure- 5

ment. A considerable part of the material which had broken loose as a result 2

of the slide was still on the face of the quarry at the time of the final survey. i

In fact, in certain parts of the quarry the final survey profiles indicated that |

the face of the cliff had expanded over the original profile lines. The slide

material, as a result of having been dislodged from its original position, had

expanded considerably beyond the volume it occupied in the original position.

This expansion tended to make the profile lines of the final survey appear to

have receded less than they would otherwise have done. To the extent, there-

fore, that such slide material was still on the face of the quarry the end area

method tended to understate the net volume of material in place actually

removed from the face of the quarry by the plaintiffs. The slide also created |

fissures, some of which had the effect of moving the face of the quarry forward v

beyond the point where it would otherwise have been. This again tended to

understate the amount of material removed by plaintiffs when using the end

area method. The defendant made no corrections for these factors in its

computations.

Furthermore, the slide carried substantial amounts of material from parts

of the quarry that had not originally been surveyed into parts where the

plaintiffs’ quarrying operations were going forward. It became necessary,

therefore, to find out the original profile of the unsurveyed parts of the quarry.

This could be done only by use of interpolations from those parts of the quarry F

3A

outside for which no cross section had been prepared, but also

certain points on the original survey were wiped out.

After the contract was completed the contracting officer

caused a final survey to be made and on a comparison of that

survey with the original survey computed the borrow ma-

terial excavated as 69,349.7 cubic yards. During the course

of the contract plaintiffs had been paid for this item on a

truck-measurement basis, on which basis the borrow material

removed had been computed at 99,592 cubic yards, that is,

some 30,000 more than the contracting officer computed on

the average end area method. The plaintiffs took an appeal

from that decision of the contracting officer to the Commis-

sioner of Roads for Alaska, the designated representative

of the head of the department, who affirmed the decision of

the contracting officer. This suit followed.

When this case was tried and when a report thereon was

filed by the commissioner, the last word on the question of

the finality of the decision of the head of the department had

been stated by the Supreme Court in United States v. Wun-

derlich, 342 U.S. 98, in which the Court said that a decision

made by the head of the department under the “Disputes”

clause of a government contract was final and conclusive un-

less fraud on his part was alleged and proved. The com-

missioner found that fraud, as measured by the formula set

out by the Supreme Court in that decision, had not been

established by the plaintiffs. However, after the report

had been filed, the Congress passed and the President signed

Public Law 356, 83d Congress, 2d Session, which provided

that the decision of the head of any department or agency

in any contractual dispute shall not be final and conclusive

where “the same is fraudulent or capricious or arbitrary or

so grossly erroneous as necessarily to imply bad faith, or is

not supported by substantial evidence.”

We are satisfied from the evidence and have found as a

fact that the decision of the head of the department was not

supported by substantial evidence. In reaching this con-

clusion we have considered the evidence on both sides in

order to determine whether it appears that the evidence in

support of the administrative decision can fairly be said to

which had been surveyed at the beginning, a process which tended to create

some inaccuracies.

4A

be substantial in the face of opposing evidence. See Willa-

point Oysters v. Ewing, 174 F. 2d 676, certiorari denied 338

U. S. 860. In a recent decision by the Supreme Court,

Universal Camera Corp v. National Labor Relations Board,

840 U. S. 474, 487, the Court made the following statement

with respect to the rule relating to substantiality of evidence

to support an administrative decision:

Whether or not it was ever permissible for courts to

determine the substantiality of evidence supporting a

Labor Board decision merely on the basis of evidence

which in and of itself justified it, without taking into

account contradictory evidence or evidence from which

conflicting inferences could be drawn, the new legisla-

tion [Administrative Procedures Act and Taft-Hart-

ley Act] definitively precludes such a theory of review

and bars its practice. The substantiality of evidence

must take into account whatever in the record fairly de-

tracts from its weight. This is clearly the significance

of the requirement in both statutes that courts consider

the whole record.

The fact that there is evidence, considered of and by itself,

to support the administrative decision is not sufficient where

there is opposing evidence so substantial in character as to

detract from its weight and render it less than substantial on

the record as a whole.

As we view the evidence, it is difficult to see how it could be

said that there was substantial evidence to support the de-

cision made by the contracting officer and the head of the

department in the face of the opposing evidence. What

these administrative officials tried to do was to compute the

amount of borrow material removed by the use of a method

which had been made impossible of accurate application

because of the slide which had occurred. It is true that the

contract provided for the use of this method but only as a

means of determining the amount of material removed for

which the plaintiffs were to be paid. The real question was

how much material had been removed. Not only were some

of the original survey elevations wiped out but also substan-

tial amounts of material came from outside into the area

where the plaintiffs were working and from which material

had been removed. These factors contributed to errors in

comparing the original survey with the final survey for the

oA

purpose of a comparison of the material removed. Defendant

recognized some of these difficulties and undertook through

interpolations or estimates to supply the original survey

elevations which were wiped out, and otherwise compensate

for the changed conditions. That it did not do so in a satis-

factory manner is plainly evident from the opposing evidence

which was before the administrative officials when the final

decision was made and which they contend confirmed the

original dec.sion.

In the first place, when the plaintiffs complained of the

decision of the contracting officer, the possibility of error was

recognized and an effort made to check that computation.

The first method used was to have a mass diagram prepared

of material in place on the road.?,- Then a computation was

prepared which would show the amount of borrow material

in place in its original position in the quarry which would

be required to produce the material in place on the road as

shown by the mass diagram. This computation resulted in

a determination of 66,566.5 cubic yards of borrow material

as compared with 64,735.9 cubic yards used in the contracting

officer’s determination for roadway embankment (69,349.7

less 4,613.8, which represented material rejected in spoils pile

at the quarry and overburden). While the amount so com-

puted was not substantially greater than the amount com-

puted by the contracting officer, it failed to take into account,

as shown by finding 25, substantial amounts of material

which were used and for which the plaintiffs were entitled to

be paid. With these omitted amounts added to the 66,566.5

cubic yards which were computed, the amount becomes sub-

stantially greater than that allowed in the final determina-

tion.

A second check on the accuracy of the average end area

method was made while the appeal was pending through

what is known as a specific gravity test. By such a test it

was expected that a determination could be made of a change

2This diagram was evidently made by comparing the plans of the vertical

cross sections before and after the road was built. The road as finished

deviated in certain respects from the plans with the result that additional

borrow was required over that contemplated on the plans. Furthermore, the

new road was built on top of an old road which sank in some places during

the construction and thus required additional fill. Neither of these factors

was accounted for in the mass diagram.

6A

in volume from a solid rock condition of the material in the

quarry to a disturbed condition of the same material in a

truck, that is, a determination of the percentage of swells or

voids in the material loaded in a truck as compared with the

material in a solid condition in the quarry.’ In spite of the

fact that in making the test a 3-ton truck was used instead

of a 6-ton or larger truck of the type in use by the plantiffs

during their operations, and that the allowance for the swell

factor was unfavorable to the plaintiffs, a yardage was com-

puted of 76,000 cubic yards instead of 69,349.7 determined

by the contracting officer. We are convinced that with the

use of a truck of the proper size and with the swell factor

appropriately resolved an even greater disparity would have

been shown.

3 The specific gravity method used by the defendant consisted of two parts.

The first part determined that a 3-ton truck loaded level to the bed of the

truck contained 33 percent voids and 67 percent solid rock by volume. The

33 percent figure was arrived at by taking the specific gravity of representative

samples of rock and applying this specific gravity to the weight and volume

of the load of a 3-ton truck loaded level to the top of its bed. It does not

appear, however, that this 33 percent figure was intended to represent the

exact increase in the volume of material from its virgin state to its volume

loaded on the truck since no account was taken of voids that might occur in

the material in the virgin state. Furthermore, the amount of voids in a small

3-ton truck might well be considerably less than the voids in 6-, 7-, or 8-ton

trucks which were the types of sizes actually used. The following computa-

tion, though not made by defendant’s engineers, is significant. Assuming that

the total cubic yards of plaintiffs’ truck-count figures took into account a

uniform swell factor of 25 percent, then the uncorrected volume of material

removed amounts to 132,789 cubie yards; if the plaintiffs’ truck-count figure

used a swell factor of 20 percent, then the uncorrected volume amounts to

124,490 cubic yards. Applying the 33 percent swell factor of the specific

gravity test to those figures yields 88,946 and 83,408 cubic yards, respectively.

The other part of the specific gravity method determined the percentage

of voids in the heaped load on a truck having a sideboard level capacity

of 6.35 cubic yards. The bed of this truck had inside dimensions of 6.6’ x

10.0’ x 2.6’ as compared to 6.5’ x 7.96’ x 1.56’ of the truck that was used in

the previous test. The volume of the heap on such a truck was estimated to

be ten-eighths of the volume of the heap on a test truck, or ten-eighths of

1.28 cubic yards which equals 1.60 cubic yards. The total load yardage for

such a truck in heaped condition was, therefore, 6.35 cubic yards plus 1.60

cubic yards, which equals 7.95 cubic yards. Applying the 33 percent figure

computed above, the engineers arrived at an actual volume of rock of 5.33

cubie yards. The defendant's engineers further assumed that such heaped

6.35 cubic yard trucks were credited with actually having hauled seven cubic

yards of material in the plaintiffs’ truck-count computation. The basis for

this assumption is not clear. Dividing 5.33 into 7, the defendant determined

that plaintiffs had only excavated 76 percent of the amount with which

they were credited under the truck-count method. This percentage was then

applied generally to the total cubic yardage which the truck-count method

had credited to the plaintiffs, that is, 76 percent of 99,592 cubic yards, which

is approximately 76,000 cubic yards.

LT eS Se te.

eet SR AME, GG SHORES. - ‘ A 6 ATE LL LD,

7A

The third type of evidence before the head of the depart-

ment when the final decision was made was the truck-meas-

urement basis contended for by the plaintiffs. Prior to the

commencement of the hauling operation, defendant’s resident

engineer and a representative of the plaintiffs measured each

of the trucks on the job and calculated the dimensions of their

gross load when heaped full. The volume of each truck as

measured was reduced by a swell factor to allow for voids in

the material in the trucks as compared with the material in

its undisturbed state in the quarry. Each load was checked

by inspectors of the defendant both upon departure from

the borrow pit and on delivery at the read. Monthly prog-

ress payments were made to the plaintiffs by the defendant on

the basis of these tabulations. The total yardage computed

by this method was 99,592 cubic yards. The major objection

raised by the defendant to the accuracy of such computation

was that sufficient allowance was not made for swells or voids

in the material. In our findings we have agreed that some

more allowance should be made for voids than was made in

that computation but we are satisfied from the evidence that

such allowance should be less than that contended for by

the defendant and therefore the amount computed on this

basis would likewise be substantially more than that allowed

by the head of the department.

What we have, therefore, is a situation wherein the head

of the department made a determination of an amount of

material removed which was substantially less than the

amount computed by any one of three other methods. When

we consider the inaccuracies which would certainly result

from an attempted use of the average end area method under

the changed conditions resulting from the slide, it is difficult

to see how three other computations, all of which resulted

in substantially greater amounts, could be said to give any-

thing approaching a confirmation of the amount determined

by the head of the department. The contradictory and con-

flicting evidence so detracts from the weight of the evidence

in support of the decision as to leave it without substantial

support. On the contrary we are convinced that the sub-

stantial weight of the evidence supports an amount in excess

of that allowed by the head of the department. In our find-

ee, ATRL gy LS TE

‘

.

e

:

: >

:

>

j

be

7

.

“1g

NRHA Tht

#Y NPD

ASST,

ELIOT RST

338960—55——_3

x

*

RY

ee

NYO PRS TAT TEL ALAR RENTS COG ET SNR =|

8A

ings we have found that 84,471 cubic yards of borrow ma-

terial were excavated which is 15,121.3 cubic yards more than

that allowed by the defendant. Since the contract price was

$1.29 per cubic yard for the excavation of this borrow mate-

rial, the plaintiffs are entitled to recover $19,506.48 on this

item.

Since the amount allowable for the overhaul item varies in

direct proportion to the volume of borrow material removed,

the cubic-yard miles allowable on this item is 267,727.8 in-

stead of 217,032.4, that is, 50,695.4 cubic-yard miles more

than allowed by the defendant. At the contract price of 82

cents per cubic-yard mile, this amounts to $16,222.53, which

the plaintiff's are entitled to recover on this item.

The other issue in the case involves questions of law and

arises out of an entirely different set of facts from those just

discussed. One of the items involved in the contract was the

paving of the road with asphalt. In order to do this work,

the plaintiffs had considered renting or buying an asphalt

plant in the State of Washington. The rental cost of such

a plant would have been approximately $10,700. After the

job got under way, the plaintiffs learned that there was a

plant located at Ladd Air Force Base which was under the

jurisdiction of one Major Russell who was responsible for

the maintenance of the roads at the Air Force Base. One of

the plaintiffs made inquiry of Major Russell as to whether

arrangements could be made for the plaintiffs to use the

plant. Major Russell suggested that certain roads on the

Base needed seal coating and if plaintiffs would do this work

they could use the plant on the road job. After certain

negotiations during which Major Russell represented that

he had been given authority to enter into the agreement, the

plaintiffs submitted a written proposal which was accepted by

Major Russell as Air Installation Officer, whereby the plain-

tiffs agreed to seal coat the main paved roads on the base in

return for the use of the asphalt plant to produce asphalt for

the road job.

Upon the approval of that agreement by Major Russell,

the plaintiffs proceeded to carry out their part of the agree-

ment which they did by seal coating some nine or ten miles of

roads in a manner satisfactory to the Air Force Base author-

ities. The value of such work was in excess of $10,000.

9A

In the meantime, Major Russell had forwarded to his

superior officer copies of the agreement which he had ap-

proved for seal coating of the roads in return for the use

of the asphalt plant by the plaintiffs. Shortly after the

seal-coating job had been completed but prior to the time

when the asphalt plant had been delivered to the plaintiffs,

Major Russell’s superior officer advised him that there was

no authority for such an agreement and that work there-

under should be stopped immediately. Major Russell re-

plied that the work had already been completed and urged

that since the plaintiffs had carried out their part of the

agreement and since the agreement was in the best interests

of the Government, the plaintiffs should be permitted to use

the asphalt plant. However, Major Russell’s superior of-

ficer refused to change his position. Major Russell advised

the plaintiffs of his inability to carry out the agreement but

suggested that arrangements be made to have the plant bor-

rowed by the Alaska Road Commission and then rented by

the Commission to the plaintiffs. Major Russell stated that

if this could be arranged he would arrange for payment for

the work which had already been done by the plaintiffs at

Ladd Field. As a result the asphalt plant was turned over

by Major Russell to the Alaska Road Commission which, in

turn, made it available to the plaintiffs at a rental figure of

$1.30 per ton. In agreeing orally to that rental figure, the

plaintiffs relied upon the assurance previously given by

Major Russell that they would be paid for the work which

they had already performed at Ladd Field.

The plaintiffs used the asphalt plant in paving the roads

under their contract. At or about the time the paving was

completed, Major Russell advised the paintiffs that payment

could not be made by the defendant for the seal-coating work

which had been performed by them at Ladd Field. There-

upon the plaintiffs refused to sign a change order prepared

by the Alaska Road Commission reducing the unit price of

asphalt by $1.30 per ton. However, the contracting officer, in

the final settlement under the plaintiffs’ contract, directed

that the change order be considered a written order changing

the specifications and that the rental stipulated therein be

deemed to be an equitable adjustment of the contract price.

ee — a

10A

Upon completion of the contract, it was determined that

7,820.3 tons of asphalt had been actually used and accordingly

$10,166.39 was deducted from payments to the plaintiffs,

On appeal to the head of the department, the decision of the

contracting officer was affirmed. No amount has been paid

to the plaintiffs on account of the work which they did at

Ladd Field.

What the plaintiffs are suing for is the amount just re-

ferred to which was deducted from amounts otherwise due

them under the contract involved in this proceeding. No

question is raised by the defendant as to the fact that the

plaintiffs performed the services or that the services were

worth at least the amount now sued for. The sole defense

of the defendant is that since Major Russell was not a con-

tracting officer with full authority to bind the Government

in the fullest contractual sense, the plaintiffs cannot recover

on this item. Surely, compelling reasons would be required

to have any court sanction any such inequitable result and

we do not think such reasons exist. Whatever might be said

with respect to the lack of authority on the part of Major.

Russell to enter into a binding contract, it is certainy true

that the plaintiffs proceeded in an entirely appropriate and

proper manner in entering into the agreement and did so

only after they were assured by Major Russell that he had

authority to do so. Likewise, Major Russell had also pro-

ceeded in good faith in the entire matter and had been assured

by Washington that such an arrangement would be satisfac-

tory. The roads that were seal coated were wholly within

the base where the contracting officer was located. It seems

incredible that he did not know all about the agreement and

by his inaction ratify it. Certainly he did not repudiate the

agreement, and he did not appear as a witness. The plaintiffs

carried out their part of the agreement for which the Gov-

ernment received the benefit. We feel that there then arose

an implied contract under which the defendant was obligated

to pay the value of the services rendered by the plaintiffs.

Recovery is accordingly allowable for this item in the amount

deducted under the contract, $10,166.39. Cf. W. H. Arm-

strong and Company v. United States, 98 C. Cls. 519, 529;

Lewis Joseph Stiers, et al. v. United States, 121 C. Cls. 157,

11A

172; and Pacific Maritime Association v. United States, 123

C. Cls. 667, 676.

Judgment will accordingly be entered for $19,506.48 for

the material item, $16,222.53 for the overhaul item, and

$10,166.39 for the asphalt plant item, making a total of

$45,895.40.

It is so ordered.

Laramore, Judge; Mavpen, Judge; Wurtaxer, Judge;

and LirrteTon, Judge, concur.

FINDINGS OF FACT

The court, having considered the evidence, the report of

Commissioner Richard H. Akers, and the briefs and argu-

ment of counsel, makes findings of fact as follows:

1, At all times material to this proceeding the plaintiff,

Russell H. Williams, was engaged in the contracting busi-

ness in Alaska as an individual under the name of Williams

Equipment Company with his principal place of business

in Fairbanks, Alaska. For convenience, that plaintiff will

sometimes hereinafter be referred to as “Williams.”

At all times material to this proceeding the plaintiff,

Reed & Martin, Inc., was an Alaska corporation with its prin-

cipal place of business in Fairbanks. It was engaged in the

contracting business, normally business construction.

2. During the early part of 1950, the plaintiffs entered into

a joint venture agreement for the purpose of submitting a

bid to the defendant, acting through the Department of the

Interior, Alaska Road Commission, for the construction of a

highway from Fairbanks to College and a portion of the

Steese Highway, a total distance of approximately 5.74

miles. Williams was the manager of the operation and the

other plaintiff did not actively participate therein except

in connection with the securing of an asphalt mixing plant

hereinafter referred to.

3. The plaintiffs were advised on March 16, 1950, by John

R. Noyes, Commissioner of Roads for Alaska, that their bid

in the total amount of $389,713.10 based upon the estimated

quantities set out in the invitation for bids and the unit prices

bid by them had been accepted, that the formal contract was

being prepared for their signatures, and that that letter would

BLS ILO OF SLL ETS

12A

constitute notice to proceed within 15 calendar days after

its receipt.

4. Under date of March 28, 1950, the formal contract cover-

ing the work was signed. That contract bore the number

1-arc—4263 and was signed on behalf of the defendant by A. F.

Ghiglione, Chief Engineer, Alaska Road Commission, as

contracting oflicer. It provided that the plaintiffs would

furnish the materials and perform the work for constructing

the highway from Fairbanks to College and a portion of the

Steese Highway in consideration of payment of the unit

prices set forth in the bid schedule in strict accordance with

the specifications, schedules, and drawings specifically desig-

nated in the contract. The contract further provided that

the work was to be commenced within 15 calendar days

after receipt by the contractor of notice to proceed and be

completed by October 15, 1950, subject to such extensions

as might be authorized under the contract. The work was

started at or about the time required, namely, about April 4,

1950, and, as will hereinafter appear, was completed

September 30, 1950, and accepted October 9, 1950.

5. The bid schedule, copy of which was annexed to and

made part of the contract, read in part as follows:

OAR Pay names, with unit bid price written in Unit

Item words (pay name defined on page shown | bid Amount

quantity in parentheses) | price bid

. . s e s

26 (1) 57,000 | Cu. Yds. Unclassified Excavation for Borrow,

Case 1, at One dollar and twenty-nine cents

Sr DE Fe Cay PE swank batd veseevemnwan $1. 29 $73, 530

.

28 (2) 187,000 | Cu. Yd. Mi. Special Overhaul of Borrow

(1,000’ freehaul), at Thirty-two cents per

FE Cia BP nce caw bans an secnenaanses .32 59, 840

. . . . .

140 (1) 8,000 | Tons (Class F Pavement, Type F-1) Plant

Mixture, Grading A-1, at Twelve dollars |

and no cents per ton (274).................. 12.00 96, 000

|

. . . . .

|

6. The contract contained, among other provisions, the

following:

Articie 4. Changed conditions.—Should the contrac-

tor encounter, or the Government discover, during the

progress of the work, subsurface and/or latent condi-

tions at the site materially differing from those shown

on the drawings or indicated in the specifications, or

Se i els Eee Se Nee Ne Se ee ee Oe ona oS ee ee ee Pn) Lh oon see) Oe oie heel ee. ee

«

f

|

'

if

;

t

13A

unknown conditions of an unusual nature differing ma-

terially from those ordinarily encountered and generally

recognized as inhering in work of the character provided

for in the plans and specifications, the attention of the

contracting oflicer shall be called immediately to such

conditions before they are disturbed. The contracting

oflicer shall thereupon promptly investigate the condi-

tions, and if he finds that they do so materially differ

the contract shall, with the written approval of the head

of the department or his duly authorized representative

be modified to provide for any increase or decrease o

cost and/or difference in time resulting from such

conditions.

Anricie 15, Disputes—Except as otherwise specifi-

cally provided in this contract, all disputes concerning

uestions of fact arising under this contract shall be

decided by the contracting officer subject to written

appeal by the contractor within 80 days to the head of

the department concerned or his duly authorized repre-

sentative, whose decision shall be final and conclusive

upon the parties thereto. In the meantime the con-

tractor shall diligently proceed with the work as directed.

Arricte 16. Payments to contractors.—(a) Unless

otherwise provided in the specifications, partial pay-

ments will be made as the work progresses at the end of

each calendar month, or as soon herentber as practicable,

on estimates made and approved by the contracting offi-

cer. In preparing estimates the material delivered on

the site and preparatory work done may be taken into

consideration.

* * * * *

7. Specifications FP-41 issued by the Federal Works

Agency, Public Roads Administration, and incorporated in

the contract by reference, provided in part as follows:

Irem 26.—Borrow

DeEscriIPpTION

26-1.1 This item shall consist of excavating approved

material from borrow pits, when sufficient quantities of

suitable material are not available from other excava-

tions, and the disposing of all excavated material, all in

accordance with these specifications and in conformity

with the lines, grades, and dimensions shown on the plans

or as directed by the engineer.

26-1.2 Material to be used as topping for embank-

ments, as a cushion for rock embankments, or for rein-

forcing unsatisfactory subgrade soil or for backfilling

FR AE MEIER LOT TE OR 7 OE A BEON,

14A

cuts, where excavation below de is authorized, shall

be obtained under this item when satisfactory material

for the special purpose is not obtainable from other

excavations.

26-1.3 Se.ecrion or Sources.—Material for this item

shall be obtained under the terms of case 1 and/or case 2

described below.

Case 1.—When case 1 is called for in the bid schedule,

the sources of borrow material shall be indicated on the

plans and/or designated by the engineer, and the con-

tractor shall be relieved of the responsivility of obtain-

ing the right to take the material from such sources.

s

e * r *

MATERIALS

26-2.1 Material for this item shall be material se-

lected by the engineer as —— ee for the

particular embankment or backfili for which the mate-

rial is intended. The material shall be obtained from

the approved borrow sources.

MernHop oF MEASUREMENT

264.1 The yardage to be paid for shall be the num-

ber of cubic yards of material (including the yardage

of overburden stripped from pits) measured in original

position and computed by average end area method, ex-

cavated and acceptably disposed of in embankment,

backfill, or as otherwise ordered, except that when case 2

is called for in the bid schedule, the yardage of over-

burden stripped from pits (unless used as borrow ma-

terial) shall not be included in the yardage to be paid

for. The measurement shall not fechas the yardage of

any excavation performed prior to the taking of eleva-

tions and measurements of the undisturbed ground.

Basis or PAYMENT

26-5.1 The yardage, measured as provided above,

shall be paid for at the contract unit price per cubic

yard for “Unclassified Excavation for Borrow, Case 1,”

or “Unclassified Excavation for Borrow, Case 2,” as the

case may be, * * *.

Irem 28.—SpectaL OvERHAUL or Borrow

(Cubic-yard-mile basis)

DESCRIPTION

28-1.1 This item shall consist of authorized haulin

in excess of the free haul distance of any material pai

PRGA #

= aad GRADY TREE TOAD OO IRL TERETE LES AE BASLE Cee Hea ek AE ECP DARE ASAE ARTE —7

15A

for under BORROW (case 1) and disposed of as re-

quired under the various items prescribed for the dis-

posal of such material.

The free haul distance shall be 500 feet or 1,000 feet,

whichever is called for in the bid schedule. Only one

free haul distance shall be provided in any one contract.

Meruop oF MEASUREMENT

98-4.1 The number of cubic-yard-miles of special

overhaul of borrow to be paid for shall be the product

of the volume of the pina oe material, measured in

its original position, in cubic yards, by the overhaul dis-

tance in miles and fractions thereof. The overhauled

material shall be the material comprehended within the

terms of 1.1 above and hauled as directed more than

the free haul distance (as designated in the bid sched-

ule). The overhaul distance shall be the distance be-

tween the centers of volume of the overhauled material

in its original position and after placing, less the free

haul distance (as designated in the bid schedule).

+ ’ * * *

Basis or PAYMENT:

28-5.1 The cubic-yard miles, determined as provided

above, shall be paid for at the contract unit price per

cubic-yard mile for “Special Overhaul of Borrow (500

feet free haul)” or “Special Overhaul of Borrow (1,000

feet free haul),” as the case may be, which price and

payment shall constitute full compensation for all labor,

—* tools, and incidentals necessary to complete

the item.

Under general requirements in the same specifications ap-

peared the following provisions:

Art. 7.14 No Warver or Lreat Ricurs.—The Gov-

ernment shall not be precluded or estopped by any meas-

urement, estimate, or certificate made either before or

after the completion and acceptance of the work and pay-

ment therefor from showing the true amount and char-

acter of the work performed and materials furnished by

the contractor, nor from showing that any such measure-

ment, estimate, or certificate is untrue or is incorrectly

made, nor that the work or materials do not in fact con-

form to the contract. The Government shall not be

precluded or estopped, notwithstanding any such meas-

urement, estimate, or certificate and payment in accord-

ance therewith from recovering from the contractor or

16A

his sureties, or both, such damages as it may sustain by

reason of his failure to comply with the terms of the

contract. Neither the acceptance by the engineer or by

his representatives, nor wd haga for or acceptance

of the whole or any part of the work, nor any extension

of time, nor any possession taken by the engineer shall

operate as a waiver of any portion of the contract or of

any power herein reserved, or of any right to damages.

A waiver of any breach of the contract shall not be held

to be a waiver of any other or subsequent breach.

;

k

8. Special provisions which were also made a part of the

contract read as follows:

Control of Material

*

* *

Materials suitable for Borrow, Item 26 (1) may be

obtained from the following source :

Deposit B-1

1.5 Mi. from Sta. 73+00+ Steese Highway, via Steese

signs and Lazelle Road.

eposit A-1 is an existing stockpile, therefore, no

clearing or stripping will be required.

Deposit B-1 is known locally as the Birch Hill Quarry.

The Contractor will be required to secure material from

a fresh face. The cost of cleaning an approach to the

face, and the cost of any necessary clearing and strip-

ping, shall be considered as included in the unit bid

price for Itean 26 (1), Unclassified for Borrow.

If it becomes necessary to obtain such material from

other sources, allowance will be made for actual net

increased haul and will be paid for at the unit price set

forth for Item 28 (2) Cu. Yd. Mi., Special Overhaul of

Borrow, provided that the quantity shall be determined

by truck measurement at point of delivery. The dis-

tance shall not be subject to freehaul, but shall be the

actual mileage of haul occasioned by the changed loca-

tion of the material sources as compared to the haul

which would have been necessary had all the material

been acquired at the designated point. No change in

the location of the source of the material shall be made

without approval in writing by the Engineer, provided

that no reduction in the contract unit price shall be

made if consideration of the entire contract undertaking

should result in a net decrease in haul.

* *

2 ERR: IGE Miah 35 LEP

So a

17A

9, The following “general notes” appeared upon sheet 2 of

the contract plans for the highway :

1. Alignment and grades are subject to adjustment.

2. Depths of surfacing, base course and borrow are com-

pacted thicknesses.

3. Curves shall be widened and super-elevated as staked

by the Engineer.

4, Approaches shall be constructed to all existing side

roads with a minimum width for driveways of 12’.

Approach fills shall be constructed with Borrow.

Surfacing shall consist of 6’’ of Crushed Gravel Base

Course. Pipes shall be installed according to the

Pipe List on sheet 3 of these Plans.

5. An extra allowance of 1820 cu. yd. of Excavation and

5500 cu. yd. of Borrow has been included in the Esti-

mate of Quantities to cover possible stripping and

backfilling of poor material encountered during con-

struction.

6. Deposits for Borrow, Base and Surfacing are shown

on sheet No. 1 and described in the Special Provisions.

On the cross-sections for the road an estimated quantity

of approximately 51,000 cubic yards of borrow material was

shown as required. To that was added the 5,500 cubic yards

of borrow set out in note 5 above, and the total amount so

arrived at was further increased by a small yardage to make

the even figure of 57,000 cubic yards which was shown in the

bid schedule as the estimated amount of borrow required for

the project. It was also considered that the borrow material

under compaction would yield approximately 62,700 cubic

yards of embankment. The cross-sections do not show any

separate amount computed as required for driveways and

intersections. The original survey was deficient in that

it had not taken full cognizance of these driveways and

intersections.

The pipe list which appeared on sheet 3 of the contract

drawings listed 87 different pipe locations, 70 of which re-

quired the installation of pipe for the first time, 8 of which

required the extension of existing pipe, and 9 of which

required the removal of an existing pipe and the placement

of a new one. It was estimated that 1,726 linear feet of

15-inch culvert pipe, 30 linear feet of 21-inch culvert pipe,

436 linear feet of 24-inch culvert pipe, and 146 linear feet of

:

TA cece |

18A

36-inch culvert pipe would be required, of which 30 feet of

21-inch pipe, 14 feet of 24-inch pipe, and 36 feet of 36-inch

pipe were for extensions to existing culverts. In carrying

out the work, the plaintiffs installed a total of only 69 more

linear feet of pipe than were called for on the above pipe list.

10. At the time the contract involved in this proceeding

was entered into and carried out, Col. John R. Noyes was

Commissioner of Roads for Alaska. Colonel Noyes was

graduated from West Point with a degree of Bachelor of

Science in 1923, and from Cornell University with a degree

of Civil Engineering in 1926. He has been on active duty in

the Army since his graduation from West Point and most of

his work has been of an engineering nature. During the

period 1926 to 1933, he was assigned as an assistant at the

Alaska Road Commission. In 1946 he was placed on an inter-

departmental committee dealing with Alaskan affairs which

later, in 1948, indirectly led to his appointment as Commis-

sioner of Roads for Alaska.

The contracting officer was Angelo F. Ghiglione. He

received a bachelor’s degree from the University of Wash-

ington, and a master’s degree from the Massachusetts Insti-

tute of Technology—both in civil engineering. Immediately

after his graduation he started working permanently for the

Alaska Road Commission in 1933 and, except for a period of

military service when he was in the Civil Engineering Corps

of the Navy from 1941 to 1944, he has been continuously

employed by the Alaska Road Commission. He held various

positions with the Alaska Road Commission prior to 1947, in

which year he was promoted to assistant chief engineer, and

in April 1949 to chief engineer. As chief engineer he became

the contracting officer on the contract involved in this pro-

ceeding. In 1951 he was made Commissioner of Roads for

Alaska.

11. In 1948, the road-building program in Alaska expanded

greatly. Prior to 1948 appropriations had not been more

than $5,000,000 a year. Commencing in 1948, they were

about $25,000,000 a year. This was brought about by the

adoption of a program for hard surfacing as well as by the

extension of the normal work for new construction and

maintenance. The Alaska Road Commission had to be ex-

SSS

OLEAN kein Rite

rR et

—_

19A

panded very greatly in order to take care of the work. It

utilized the services of the United States Bureau of Public

Roads very largely in initiating the program. The United

States Bureau of Public Roads prepared specifications and

supervised the work in a number of cases. The Alaska Road

Commission had been building roads in Alaska since 1905,

but not paved roads. Since this work had been carried out

by its own hired crews and not by contractors, the experience

of the Alaska Road Commission with road contracts of the

type involved in this proceeding was somewhat limited.

The contract involved in this proceeding was the first con-

tract entered into by the Alaska Road Commission for the

construction of a hard-surface road in the Fairbanks district

which was to be supervised by that Commission. It had

entered into two other contracts for hard-surface roads in

that area at or about that time but their supervision was by

the Bureau of Public Roads. On June 1, 1949, the Alaska

Road Commission had executed a contract for the construc-

tion of Haynes Highway, a distance of forty miles, and on

March 15, 1950, had executed a contract for the construction

of a road three and one-half miles long at or near Anchorage.

Both were hard-surface roads and both were under the com-

plete supervision of the Alaska Road Commission. They

were outside the Fairbanks district.

12. At the time the contract was entered into, Colonel

Noyes recognized the lack of knowledge and experience of

the personnel in the Fairbanks area with contracts of the

type about to be carried out. The district engineer, Frank

Nash, had grown up with the road work in Alaska but he was

not adequately informed on a jobof that kind. The assistant

district engineer, Milton C. Zimmerman, while a well trained

engineer with some years experience in Alaska, was likewise

inexperienced on a job of this character. Because of this

situation, Colonel Noyes gave more than the usual attention

to the job. In addition, the Alaska Road Commission

obtained for resident engineer James L. Foster, a competent

engineer who had had considerable experience in work of

the character involved. Because of the weakness in the dis-

trict office, Foster was granted more authority than was

usually given to a resident engineer in carrying out a job of

20A

that kind. Since this was the Commission’s first paved road

job in the Fairbanks district and one of their first jobs of

that kind which was being carried out without assistance

from the United States Bureau of Public Roads, he (Noyes)

told Foster he was anxious that a good job be done. Noyes

also told Foster that in the event he was unable to secure

decisions from Nash, he (Foster) should communicate di-

rectly with him (Noyes). On two occasions when Williams

took up matters with Nash, Nash told Williams that Foster

was resident engineer and that matters pertaining to the job

should be taken up with him. While Foster was under

Nash and Zimmerman, most of the decisions which had to be

made on the job with respect to carrying out the work were

made by Foster without much assistance from them. How-

ever, Foster submitted his reports through the district office

and conferred with both Nash and Zimmerman from time

to time with respect to the manner in which the work should

be carried on.

13. The Birch Hill Quarry which was designated in the

contract as the source of borrow material was located approx-

imately one and one-half miles east of the eastern terminal

of the road construction on the Steese Highway. The length

of the face of the quarry on which the plaintiffs were working

was about 650 feet and it had a height of 100 to 125 feet.

When the plaintiffs started work, the quarry, which was vir-

gin material not previously excavated, lay on about a 45 per-

cent slope, that is, it rose 45 feet for each 100 feet in the face

of the slope. In taking material from the quarry, the lay of

the material was changed in substantial part to about a

60 percent slope which was the steepest at which the material

would remain in place.

The material was a micaceous schist lying in planes four

to six inches in width. The deposit was conic in shape and

the plaintiffs were working on one of the sloping faces. The

material was not a solid wall of rock, but was laminated and

had further disintegrated to some extent by the action of the

weather upon it. While the evidence does not clearly estab-

lish the extent to which voids may have existed in the virgin

material before it was disturbed in the plaintiffs’ operation,

whatever voids existed, except for broken material on the sur-

21A

face, were smaller in magnitude than the voids in the material

after it was removed by the plaintiffs. Small slides, in addi-

tion to the major slide hereinafter referred to, occurred from

time to time during the operation. ‘The excavation was per-

formed by power shovel which operated from the toe of the

slope and loaded the material into trucks. No blasting was

required or employed except two small shots to loosen the

frozen toe area at the beginning of the operation. The ma-

terial, loaded as just described, was delivered by the trucks

to the road and formed the base course for the road. It was

compacted on the road by traffic, including the plaintiffs’

vehicles, moving over it during the period of operations and

by the use of a caterpillar tractor.

14. No survey had been made of the part of Birch Hill

Quarry where the plaintiffs were required to secure the bor-

row material prior to the execution of the plaintiffs’ contract.

However, since the contract provided that borrow pit mate-

rial, referred to in the bid schedule as Item 26 (1), and spe-

cial overhaul of borrow, Item 28 (2), were to be paid for on

the basis of the number of cubic yards of material measured

in original position in the quarry and computed by the aver-

age end area method, the defendant caused a survey to be

made of the quarry immediately before the plaintiffs began

excavation work. This survey was done in large part by the

stadia method by making profiles of the face of the quarry

at 25-foot intervals from an established base line 1,000 feet

long and parallel with the main slope of the quarry. There

was a relatively flat plane at the top and extending back from

the quarry, and the profiles just referred to extended back on

this plane for distances ranging from 25 to 50 feet. Since

the face of the quarry was irregular, inaccuracies could result

by the use of the stadia method under such circumstances.

However, this method is often used and is usually found rea-

sonably accurate within a margin of error of 5 percent. The

chain method of survey which was used to a relatively small

extent takes much longer but produces results accurate within

a margin of error of 1 percent.

15. It iscustomary on contracts of this type, where the final

quantity is to be established by cross-sections, to make prog-

ress payments on the basis of a measurement of trucks, a

22A

determination of the load carried by each truck including

the heap on the truck and swell in the material, and a count

of the number of trips made by each truck. Prior to the

commencement of the hauling of borrow from the quarry,

defendant’s resident engineer, James T. Foster, and a repre-

sentative of the plaintiffs measured each of the trucks on the

job and calculated the dimensions of their gross load when

heaped full. Each of the trucks was numbered and the

number painted on its side. The volume of each truck as

measured was reduced by a swell factor to allow for voids

in the material in the trucks as compared with the material

in its undisturbed state in the quarry. A somewhat larger

swell factor was used in the smaller trucks because of the

greater compaction of the load in a large truck, the greater

likelihood of fine material filling voids that might arise dur-

ing loading, and the fact that the cab on the larger truck

held a larger heap at that end. However, that difference in

the factor on the smaller trucks became of relative unim-

portance on the job for the reason that the so-called smaller

trucks, seven cubic yards in capacity or less, were used for

only a short time during the operations.

The yardage for each truck, adjusted in the manner indi-

cated above to represent yardage in place, was recorded

against the number of each truck. Thereafter, throughout

the course of the job, a representative of the resident en-

gineer’s office checked each truck that left the borrow pit and

listed its number, yardage, and time of departure. Another

inspector from the resident engineer’s office on the job noted

the time of arrival of each truck, yardage, and the place where

delivered. A representative of the plaintiffs also checked

yardage and placement of the material on the road. These

three reports on yardage were reconciled each day and the

resident engineer furnished to the plaintiffs a weekly report

on the yardage hauled and the yard mile tabulation based

upon the method of calculation just described. Monthly

progress payments were made to the plaintiffs on the basis

of these tabulations. Likewise the plaintiffs paid their

hauling subcontractors on the same basis of calculation of

yardage.

16. As shown in finding 14, the base line of the quarry for

the survey made by defendant was 1,000 feet long and par-

8 RCIA NIE AISNE SL OAR te NOE EE Y , : vom.

23A

allel with the main slope of the quarry. The plaintiffs’

operations in the quarry covered only approximately 650

feet, that is, from station 3+50 to station 10+00. The toe

of the slope at station 3+50, which was the eastern limit

of the plaintiffs’ operations, commenced about 90 feet back

from the base line and the toe of the slope at other points

between station 3+50 and station 10+00 varied from that

distance back of the base line to a close proximity to the

base line at stations 8+25 and 8+75 and approximately 50

feet at station 10+00. The power shovel operated at the

toe of the slope and toward the steep embankment of the

quarry, that is, in a northerly direction. Approximately 92

percent of the material excavated by the plaintiffs during

their period of operations came from between stations 6+ 50

and 9+ 50.

17. Prior to May 11, 1950, the plaintiffs had excavated and

moved from the quarry 34,596 cubic yards of material com-

puted on the truck measurement basis heretofore described.

On May 11, 1950, a large slide occurred at the site where

excavation work was being carried on by the plaintiffs in

the quarry—partially burying the shovel and killing the

shovel operator. At the time of the slide, the power shovel

was operating about in the area of station 7+00 to station

8+50, that is, from 150 to 300 feet from the western end of

the borrow area. A large amount of material moved down-

ward and outward toward the base line where the plaintiffs

were operating. The slide covered approximately 500 feet

along the face of the slope encompassing the area about

between stations 4+75 to 10+00. A large amount of mate-

rial moved as a result of the slide though no accurate

determination of the quantity can be made from the evidence

in the record nor was any attempt made to determine the

extent of the slide when it occurred. A witness for defendant

estimated that not more than 30,000 to 50,000 cubic yards

of material were involved in the slide, whereas witnesses

for the plaintiffs estimated from 200,000 to 400,000 cubic

yards. Cracks, fissures, and crevasses were opened up north

of the face of the slope and on the slope itself. The biggest i

crevasse was immediately above the slide area and was about Hy

50 feet along, 10 feet wide, and at least 20 feet deep. At

least some of the cracks, fissures or crevasses were outside

838960—55———4

iF

:

‘

Hd

Pd

:

4

i

&

é

¥

ie

;

f

A RAGA 2 HE ESO EEE

POI PET FAN EMER ICA

al atid

26A

21. The work on the contract involved in this proceeding

was completed on September 30 and formally accepted by

the Alaska Road Commission on October 9, 1950. As here-

tofore shown, the work under Item 26 (1), Unclassified Ex-

cavation for Borrow, was completed on or shortly after June

30, 1950.

Foster remained on the job as resident engineer until about

September 16, 1950, at which time, because of his own illness

or illness in his family or some other reason, he returned to

California and did not thereafter return to his job in Alaska.

At the time he left, the Alaska Road Commission expected

that he would return within a few days and his job was not

filled on a permanent basis until some months later when

it appeared that he would not return to Alaska. No one else

connected with the Alaska Road Commission was as familiar

with the work as Foster, and his absence from the job made

it more difficult for the Alaska Road Commission to prepare

the final estimates and ultimately deal with the controversies

involved in this proceeding. However, during the period

July to September, the greater part of which time Foster

was on the job, the survey referred to in finding 22 was

made. What connection Foster had with this final survey

does not definitely appear, though in his weekly reports for

July 23 and August 6, 1950, there are notations to the effect

that the survey was being made.

22. Under the average end area method provided in the

contract for computing the amount of borrow material re-

moved, it was contemplated that a survey would be made of

the quarry after the excavation was completed for compari-

son with the original survey. The excavation was completed

about June 30, 1950, and during the period July, August, and

September, 1950, the office of the Alaska Road Commission

at Fairbanks caused such a survey to be made. The same

base line was used as in the original survey and cross-sections

were prepared, using the same stations as in the original

survey, that is, stations 25 feet apart. Since the original

survey did not cover the entire area from which material

had slid into the quarry, the original profiles were extended

by interpolations, under recognized engineering procedure,

to cover certain areas not covered by the original survey.

7 —

-

BEE APA SRP RE # WLI

274A

The use of interpolations is subject to certain inaccuracies

but usually provides a reasonable degree of accuracy.

The interval between the original survey and the final

survey as plotted was used as a basis for computing the ma-

terial removed from the quarry. No allowance was made

for swell or voids in the quarry which may have been created

in the material remaining in the quarry by reason of the slide.

That computation showed the total amount of borrow ma-

terial excavated as 68,888.32 cubic yards and the number of

cubic-yard miles of special overhaul for borrow as 202,582.

On that basis the final estimate was prepared by the resident

engineer and approved by the district office of the Alaska

Road Commission. This estimate was a reduction in the

borrow material item from 99,592 cubic yards, as reported on

the truck measurement basis, to 68,888.52, that is, a reduction

of 30,703.68 cubic yards which, at the contract price of $1.29

per cubic yard, amounted to a reduction in the amount to be

paid to the plaintiffs of $39,607.75. Similarly on the over-

haul item, it meant a reduction from 311,570 cubic-yard

miles to 202,532, that is, a reduction of 109,038 which, at 32

cents per cubic-yard mile, amounted to a reduction in the

amount to be paid to the plaintiffs of $34,892.16.

23. In computing the final yardage of borrow material

which had been removed from the quarry by the use of the

two surveys, 27 cross-sections taken 25 feet apart were used,

that is, from station 3+950 to station 10+00 which was

the area where the excavation was carried out. Four of

these sections were found wholly negative and six others

partly negative. A negative section is one in which the final

ground is above the original ground, that is, more material

than there was at the start of the excavation. A partly nega-

tive section is where some portion of the final ground is above

the original ground. The defendant deducted yardage to the

extent of the negative and partly negative sections. The

following tabulation shows the amount of material com-

puted for each section, including the sections shown as nega-

tive or partially negative:

28A

Btation Cubic yards

3-+50 653. 7

38+75 1, 306.9

4+00 1,519.9

4425 1, 133.3

°4+50 618.5

Partially Negative___ 4+75 145. 4

TG oi ita tthe stats wons oe a ie ene 5+00 —12.5

Partially Negative___ 5425 —25.5

Negative__- 5+50 —31.5

Partially Negative____ = meee 5+75 157.4

POSHGliy NGGRIVG. 36s n oe cansimenenees 6+00 —29. 4

Negative i este ean anise arian 6425 417.1

Partinity NGGRUV6. <n ncn cc che c acne ncncacnssce 6+50 1, 852.3

6+ 75 3, 321.8

7+00 4, 613.8

7425 5, 291.2

7+50 5, 707.4

7+75 6, 289.3

8+00 6, 974

8425 7, 398.6

8+50 7,521.7

8+75 6, 116.6

9+00 4,156.4

9+25 2, 970. 4

9+50 1, 605.1

Partially Negative_____-_--.--- - 9475 — N22. a

Negative............. = 10+00

69, 349. 7

The total amount shown above differs from the final esti

mate referred to in the previous finding by 461.38 cubic yards

which represented overburden removed by the plaintiffs but

which the Commission did not at first recognize for pay

purposes as borrow material. In the final determination,

however, the total of 69,349.70 cubic yards was allowed. It

was allocated as follows:

64,735.90 cubic yards to roadway embankment.

4,152.42 cubic yards rejected in spoils pile at quarry.

461.38 cubic yards overburden.

24. Shortly prior to November 25, 1950, the district engi-

neer forwarded to the plaintiffs the final estimate referred

to in finding 22, and on November 25, 1950, the plaintiffs wrote

the district engineer as follows:

RS SI

4

%

oe”, TRE

LTRS REIT,

29A

This will acknowledge receipt of your final estimate

on the College Road job, Contract No. 1-arc—426s. |

In checking your quantities shown on the estimate

we find that there are great discrepancies between esti-

mate No. 4 and the final quantities.

Since the quantities of previous estimates were deter-

mined by load slips, weight slips, cross sections and

records which were compiled and maintained by the

Resident Engineer who furnished the supervision and

control on this job, and in view of the discrepancy be-

tween the final quantities and those previously approved

we cannot accept this estimate without complete

substantiating data used in the compilation of your

quantities.

It is impossible for us to understand how such a great

discrepancy could be possible on a job with competent

administration and control.

We hereby request that the Contractor be furnished

complete supporting data including copies of field notes

on quarry sections, all preliminary and final sections

and other supporting data used in determining the final

quantities.

25. Because of their dissatisfaction with the foregoing de-

termination by the district engineer, the plaintiffs took the

matter up with the contracting officer. Various conferences

and discussions were had with the contracting officer and

other representatives of the Alaska Road Commission in con-

nection with which, and other conferences after the decision

by the contracting oflicer, the Alaska Road Commission made

available to the plaintiffs and to a consulting engineer re-

tained by them all field books, profiles, and engineering data

of the Alaska Road Commission having to do with the proj-

ect. While these discussions were being had, the contracting

officer caused the district engineer to prepare a mass diagram

of the material in place on the road and compute the quan-

tity of borrow material in place on the road. This computa-

tion resulted in a determination of material in place in the

roadway of 66,566.5 cubic yards. The computation was

made as a check on the reasonable accuracy of the amount

of the borrow material which had been previously deter-

mined by the average end area method as used for roadway

embankment, namely, 64,735.90 cubic yards. It also afforded

a basis of comparison with the estimates of borrow material

required as set out in finding 9. For such purposes, it failed

30A

to take into consideration indeterminate amounts of material

as follows:

(a) The road in question was built on a gravel road which

had been in existence for many years and which had been

reinforced with gravel the preceding year. In that area

such roads, when subjected to traffic in the thawing period

during the spring, often give way due to frost or mud boils

and other soft conditions in the road. The plaintiffs began

placing material on the road before it had thawed. When

the ground underneath thawed, some of the material placed

thereon sank and had to be replaced. In addition mud boils

developed from time to time over the road and additional

material was required in the places where they occurred. It

had been estimated 5,500 cubic yards would be required to

replace unsuitable soil. The plaintiffs were authorized to

excavate certain areas where the major mud boils occurred.

The total area so excavated was 6,952 cubic yards and that

area was filled by material from the quarry. Allowing for

the expansion of the material, the estimated quantity in place

in the quarry of 5,500 cubic yards of borrow material to be

used to replace unsuitable soil would not be substantially less

than that required to fill the 6,952 cubic yards of excavation.

However, a reasonable conclusion from the evidence is that

additional borrow material was required on account of mud

or frost boils which were not excavated and on account of

places where the road sank during the thawing season.

(b) As shown in finding 9, the original survey was defi-

cient in that it had not taken full cognizance of driveways

and intersections for which borrow material was required.

The plaintiffs performed the work in connection with these

driveways and intersections as directed by the resident engi-

neer and in doing so used more borrow material than had

been included in the original estimate.

(c) During the course of construction it was found neces-

sary to make a change in the location of the road which

made an increase in the estimated quantity of borrow mate-

rial required of approximately 2,000 cubic yards. An error

in chaining occurred in the original survey which also in-

creased the estimated quantity by an indeterminate but

smaller amount than that required for the change in location.

(d) An indeterminate amount of borrow material, in ad-

Lo ramet

31A

dition to the original estimate, was required for a fill at a

place on the road known as the Noyes Slough by reason of

incomplete cross-sections which were available when the

original estimate was made.

26. After the study referred to in the preceding finding had

been made, a conference was held in April 1951 at the office

of the Alaska Road Commission in Juneau which was at-

tended by representatives of the plaintiffs and of the Alaska

Road Commission, and which lasted for two days. Follow-

ing that conference, the contracting officer allowed a number

of the claims which the plaintiffs had submitted, but denied

the claims for Item 26 (1) and 28 (2), Unclassified Exca-

vation for Borrow and Overhaul of Borrow Material.

27. The plaintiffs took an appeal from the foregoing deci-

sion of the contracting officer to the Commissioner of Roads

for Alaska, the designated representative of the head of the

department. At the conference in Juneau, referred to in

the preceding finding, the suggestion was discussed of having

a specific gravity test made of the material in the quarry as

a further check on the accuracy of the amount previously

determined through the use of the average end area method.

By such a test it was expected that a determination could be

had of the change in volume from a solid rock condition

of the material in the quarry to a disturbed condition of the

same material in a truck, that is, a determination of the

percentage of swell or voids in the material loaded in a truck

as compared with the material in a solid condition in the

quarry. Upon or prior to the return of Zimmerman, con-

struction engineer on the project at Juneau and a partici-

pant in the conference at Juneau, Noyes, Commissioner of

Roads, and Ghiglione, contracting officer, either authorized

or instructed Zimmerman to cause a specific gravity test of

the kind referred to above to be made. Samples of solid

rock material, varying in dimensions from head to fist size,

were obtained from two locations in the quarry and the

specific gravity of these samples was determined by standard

engineering methods. A truck load (using a 3-cubic-yard

truck) was taken from each location. The loads were

heaped at the quarry. After the trucks were driven to the

yard of the Alaska Road Commission in Fairbanks, some

two miles from the quarry, the heaped portion of the load

ef

seh SAE SEIT

NECN ET LO EEE LTTE TLL IODIDE DELILE LILLIE LEIS LA DEEL DERI AEE

32A

was struck off to make a water level and any holes visible

were filled by placing material from the quarry therein. The

trucks so loaded were then weighed and a determination

made of the weight of the material therein. By applica-

tion of the specific gravity of this material to the weight of

a 3-cubic-yard load, it was determined that a 3-cubic-yard

truck load contained 33 percent voids. By the application

of that percentage of voids to the yardage as determined

on the truck measurement basis contended for by the plain-

tiffs, a calculated quantity of 76,000 cubic yards was deter-

mined for the borrow material in place in the quarry which

had been removed by the plaintiffs. Sucha result was consid-

ered by the Alaska Road Commission as tending to support

its determination of the borrow material removed as com-

puted by the average end area method.

The plaintiffs did not know that the specific gravity test

referred to above was being made and were not given an

opportunity to participate therein. No 3-cubic-yard trucks

were used by the plaintiffs on the job—the smallest hay-

ing a capacity of six or seven cubic yards—and these

smaller trucks were used for only a short time at the begin-

ning of the job. The trucks used for most of the work had

a capacity in excess of seven yards. The representatives of

the Alaska Road Commission used the smaller truck because

such a truck happened to be working in the quarry at the

time, and without any intent to be unfair to the plaintiffs,

However, a more accurate determination and tending to be

more favorable to the plaintiffs would have resulted by the

use of trucks of the sizes which were used in performing

the work.

In considering the plaintiffs’ appeal, the Commissioner

of Roads made a study of the various items in controversy,

including the effect thereon of the specific gravity test re-

ferred to above, and under date of June 15, 1951, wrote the

plaintiffs allowing some of the claims on appeal. With

respect to the items “Unclassified Excavation for Borrow”

and “Special Overhaul of Borrow,” he increased slightly the

quantities which had been allowed by the contracting officer e

but otherwise disallowed the claims. On these two items his

rulings were as follows:

D Det

.

=

SI 24

eh :

é

¥

ps

i

33A

Ivem No. 26 (1) Unclassified Excavation for Borrow

The District Engineer has now completed further

studies of the Birch Hill Quarry rock. By careful

weighing of loaded trucks and laboratory determination

of the specific , ating of numerous representative rock

samples it has been determined that a truck struck to

water-level capacity after a two-mile haul contained

33% voids. In other words, it took only 4 yards of

solid rock to fill a 6-yard truck. These tests were made

with great care being exercised to obtain typical load-

ings, excessive oversize was avoided, and normal fines

were carefully included. When struck off after a two-

mile haul, any open holes in the top of the load were

carefully hand filled.

Heaped loads were also carefully weighed. These

tests proved that a heaped truck credited, during the

course of the work, with a 7-yard load actually contained

only 5.33 yards of solid rock. In other words, by actual

weight tests it was found that a typical heaped truck

contained only 76% of the solid rock that it was credited

with during the truck count tabulations. It is reported

by the Contractor that 15% swell factor was used in

determining the yardage credited to each truck by the

truck count method. Multiplying the 85% credited by

the 76% of credited yardage determined by weight meas-

urements gives an actual capacity of 65% of the in place

yardage, which closely checks the initial weight determi-

nation of voids in a struck load. It therefore appears

sound to apply to the truck load credit of 99,962 yards

a factor of 76%, which would result in a calculated quan-

tity of 76,000 cubic yards. This is based on careful load-

ing to the ideal capacity as explained above, so is con-

sidered a reasonable verification of the 64,736 delivered

cubic yards that our engineers have already established

from cross sections of the borrow pits and checked

against the 66,567 cubic yards found to exist in the

embankment.

It is therefore concluded that the truck count method

claimed by the contractor is not the most accurate

method of determination of the quantities contemplated

by the contract, and that the cross sections of the exist-

ing and reconstructed surfaces of the borrow pit, as used

by the resident engineer, are the most accurate and are

equitable and final. In regard to Mr. Ferguson’s brief,

it is not agreed that the Government representatives at

the Juneau conference accepted the conclusion that the

contract method of measurement became impossible as

a result of the slide. Neither is it conceded that Mr.

re ———— |

34A

Foster “recognized the impossibility of using the con-

tract method of measurement” or at any time intended

to rely upon the truck count for final determination of

uantities. Ifso, why did the resident engineer require

the continuation of cross sectioning of the quarry in uly

and August when the slide occurred on May 11

Under Article 6.1, Sources of Material, the Special

Provisions state that “the cost of any necessary clearin

and stripping shall be considered as included in the unit

rice bid Sa tern 26 (1).” The resident engineer there-

ore rule[d] 461.38 cubic yards of the spoil pile as over-

burden stripping for which no pe lange was due. How-

ever, Specifications FP-41, in Article 26-4.1 provide for

inclusion of the yardage of overburden stripped from é

borrow pits, and the Special Provisions of this contract

failed to modify the provisions of that Article. What-

ever the initial intent of Article 6.1 of the Special Provi-

sions, it is not conclusive, and it is therefore concluded

that Article 26-4.1 of Specifications FP-41 shall govern,

and that the entire 69,349.7 cubic yards calculated as j

excavated from the Birch Hill Quarry shall be allowed «

as the final pay bey under Item 26 (1). This yard- ie

age was disposed of by delivering 64,736 cubic yards to a

the roadway, wasting 4,152.4 cubic yards as rejected é

material, and removing 436.1 cubic yards of overburden.

* & s & s %

Irem No. 28 (2) Cu.-Yd.-Mile Special Overhaul

of Borrow

This item is, of course, directly proportionate to the

quantity of the borrow under Item 26 (1). Since the

truck count measurement of the borrow has been found

unreliable as to quantity, it must also be determined

unreliable as to overhaul. A recheck of the mass dia-

ms, showing the disposition of the borrow, gives a

nal quantity on this item of 217,032.4 cubic yard miles.

28. On July 20, 1951, the plaintiffs requested a reconsidera-

tion of the decision by the Commissioner of Roads and on

July 30, 1951, the Commissioner of Roads affirmed his prior

decision in a letter to counsel for the plaintiffs as follows:

We now have the letter, addressed to us by Mr. Fer-

uson under date of July 20, protesting the June 15

or he of the Commissioner of Roads for Alaska.

You refer to quantities supported by “sound engineer-

ing practices.” In view of the contract terms we con-

tend that the cross sections of the borrow pit are the

only engineering practices that may be relied upon in

—-

35A

this case. We believe that accurate results have been

obtained from the reconstructed position of that part of

the pit which was affected by the slide but had not been

initially cross sectioned. As previously explained, we

rely upon this cross sectional method of, a

volume of the material in its original position. We have

confidence in those quantities because the volume of the

embankment, as now in place, strongly supports the cal-

culated excavation quantities and a load rv specific

gravity test gives further confirmation. You contend

that the “test referred to in your decision clearly indi-

cates” erroneous calculations. We believe that a care-

fully loaded and subsequently hand packed test truck

would certainly hold more rock than the average of

trucks hauling under job conditions. We therefore be-

lieve that the factor derived from the load test, as applied

to the truck count, gives a very reasonable confirmation

of our calculated 64,736 excavated yards when it shows

an ideal, hand packed, capacity of 76,000 yards. :

You now suggest a compromise. In matters of this

nature the contracting officer, or other official of the

executive department of the Government, has no author-

ity to compromise. However, what you really offer is

not a compromise but the establishment of another

method of measurement, or rather the re-examination of

one of the methods we have already used asa check. We

do not believe that such a re-examination would produce

results materially differing from the test made by our

forces, which was conscientiously carried out under pro-

cedures stipulated by recognized authorities. We there-

fore see little to be gained by further tests, but certainly

have no objection to your client’s making whatever tests

he desires.

The June 15, 1951, decision of the authorized repre-

sentative of the head of the department is therefore

reaffirmed and is final.

29. The decision of the contracting officer, which was

affirmed on appeal to the Commissioner of Roads, with

respect to the total amount of borrow material excavated

and similarly with respect to the overhaul item, was not

supported by substantial evidence. When all the evidence

is considered, and the different methods of measurement are

put together, it is a reasonable conclusion that at least

84,471 cubic yards of borrow material were excavated in-

stead of 69,349.7 cubic yards allowed by the defendant, that

is, 15,121.38 cubic yards more than allowed which, at the

;

AOE SAE Ce eee |

36A

contract price of $1.29 per cubic yard, amounts to $19,506.48,

Since the amount allowable for the overhaul items varied

in direct proportion to the volume of borrow material re-

moved, the cubic-yard miles allowable are 267,727.8 instead

of 217,032.4; that is, 50,695.4 cubic-yard miles more than

allowed by the defendant, which, at the contract price of

32 cents per cubic-yard mile, amounts to $16,222.53.

30. One of the items involved in carrying out the contract

involved herein was paving the road with asphalt. To per-

form that work it was necessary for the plaintiffs to have

an asphalt plant. At the time they submitted their bid and

entered into the contract, the plaintiffs contemplated renting

or buying one of two asphalt plants located in the State of

Washington. The rental costs including transportation,

erection and dismantling would have been approximately

$10,700.

31. After the contract was executed the plaintiffs learned

that there was an asphalt plant at Ladd Air Force Base in

Fairbanks. In April 1950 a representative of the plaintiffs

called upon Maj. Leon Russell, the Air Installation Officer

at that place, to determine whether the plaintiffs could rent

the asphalt plant located there. Major Russell advised the

plaintiffs’ representative that the roads on the airfield needed

seal coating and that if the plaintiffs would seal coat certain

roads on the base, he would allow them to use the asphalt

plant in return for such service. On April 8, 1950, the

plaintiffs wrote Major Russell, in part, as follows:

We are now deferring our plans for the purchase and

shipment of any asphalt equipment for the College Road

job which we are under contract to the Alaska Road

Commission. Asa result of our talk with you concerning

this matter, we are sure that an equitable arrangement

can be consummated which will definitely work out to the

advantage of the Government, and also save our firm

considerable capital investment for such a small quantity

of asphalt mix required for this job.

32. The representative of the plaintiffs had further con-

versations with Major Russell and arrived at a mutually

agreeable proposal along the line indicated in the preceding

finding. Major Russell said among other things that he

would go through channels and find out if he had the author-

37A

fe ity to enter into such an agreement. About the middle of

3 May 1950, Major Russell advised plaintiffs that he had been

granted the authority to make the deal and that plaintiffs

should write him a letter setting out the agreement thereto-

fore reached. On May 17, 1950, the plaintiffs wrote the

following letter to the Office of the Air Installation Officer,

Ladd Air Force Base, for the attention of Major Russell,

on which Major Russell indicated his approval as set out

below:

Reference is made to our recent conversation regard-

ing the Asphalt Plant. We wish to submit the following

agreement for your consideration.

1. The Contractor agrees to accomplish the following

work items on Ladd Air Force Base for the Air

Installations Officer during the 1950 Construction

Season :

a. Seal coat the main paved roads which includes

approximately nine lineal miles of road. Seal coat

to consist of 30+ of chips and .25 gal. of asphalt per

square yard.

b. Operate and maintain the Asphalt Mixing Plant

located in the 500 zone, and produce a maximum of

10,000 tons of asphalt mix. Mix to be delivered to

A. I. O. operated trucks at the Asphalt Plant.

2. The Air Installations Officer agrees to furnish the

f Contractor with the following materials and equip-

‘ ment for prosecution of work items listed above:

a. Asphalt Plant and all allied equipment in oper-

ating condition.

b. Foreman for Asphalt Plant who will oversee

equipment only.

c. All fuel oil, oils, and grease for A. I. O. owned

equipment.

d. Chips and aggregate at bulkhead.

e. All equipment required for applying seal coat

with the exception of dump trucks. (The Contractor

is to hire a distributor operator specified by the

A. I. O. for operation of the Government owned

asphalt distributor.)

8. In return for the work to be accomplished by the

Contractor as listed in pee #1 above, the Air

Installations Officer will permit the Contractor to use

the Asphalt Mixing Plant for producing approxi-

E mately 10,000 tons of mix for the Contractor’s job

near Fairbanks, Alaska. At no time will the pro-

duction of asphalt mix for the Contractor’s require-

ments be allowed to interfere with production of

ena |

Leese, ee

vad attsesat a

int

ee eee eee

5 SRL Re LRAT PS

SN Seige

38A

asphalt mix for the A. I. O. requirements, providing

the Contractor is given three days advance notice.

Submitted:

[s]} Russernn H. Witii1aMs,

Williams Equipment Company.

Reed and Martin, Ine.

A Joint Venture.

Approved :

[s] Leon Russet,

Air Installation Officer.

33. Major Russell, the Air Installation Officer, had charge

of the maintenance of roads, buildings, and facilities of Ladd

Air Force Base. He was not, however, a contracting officer.

34. Seal coating referred to in the letter of May 17, 1950,

was the application of a surface dressing to an asphalt sur-

face to prevent water from entering into the pores of the

asphalt. It is maintenance work which is required to be done

at intervals of approximately two years. The plaintiffs did

the seal coating called for under the terms of the letter of

May 17, 1950, placing a seal coat on some nine or ten miles

of roadway at Ladd Field and otherwise fulfilling the terms

and conditions set out in that letter. The work was begun

about the middle of June 1950 and completed shortly after

July 1, 1950. The fair value of that work was not less than

$10,166.39, the amount deducted from the plaintiffs’ contract

price as shown in finding 39.

35. On June 9, 1950, Major Russell forwarded copies of the

letter of May 17, 1950 (referred to in finding 32) to his supe-

rior officer. Under date of July 13, 1950, Major Russell was

advised by radiogram by his superior officer that there was

no authority for an agreement of the type set out in the letter

of May 17, 1950, and that work thereon should be stopped

immediately. On July 18, 1950, in response to the foregoing

radiogram, Major Russell advised his superior officer that

the plaintiffs had already completed their part of the agree-

ment and urged that it was in the best interest of the Gov-

ernment that the agreement be carried out in its entirety.

His letter reads in part as follows:

c. Mr. Williams agreed that if the base would fur-

nish the plant, he would do the work, as per the attached

agreement.

39A

d. This was believed to be a good proposition whereby

the Government would gain pa ob ly by getting a

job done at very little cost, by the use of equipment which

would otherwise be idle.

e. This Agreement was cleared through Base Legal

Department and [wJas signed by the Air Installation

Oflicer and the Contractor.

f. This proposition was gprs rs to Washington and

no objections were received, provided certain facts were

covered in the Agreement, which are believed to be

covered.

g. On 1 June 1950 the Williams Construction Com-

pany started the seal coating and completed same. Mr.

Williams proceeded with the rest of the bargain and in

all ways has carried out his part of the Agreement.

2. It is felt that it is of the best interest to the Govern-

ment that this agreement be carried out in its entirety,

and is considered good business.

On July 18, the Headquarters of the Alaskan Air Com-

mand formally advised the Commanding General, Ladd Air

Force Base, that such an agreement was unauthorized and

that, therefore, favorable consideration could not be given

thereto.

36. Shortly after he received the radiogram of July 13,

1950, referred to in the preceding finding, Major Russell ad-

vised plaintiffs of his inability to carry out his agreement

to deliver the asphalt plant and suggested that arrangements

be made to have the plant borrowed by the Alaska Road

Commission from Ladd Air Force Base and then rented by

the Alaska Road Commission to the plaintiffs. Major Rus-

sell stated that if this could be arranged, he would arrange

for payment for the work which had already been done by

the plaintiffs at Ladd Field.

37. After discussions with the plaintiffs, officials of the

Alaska Road Commission and Major Russell, the District

Engineer of the Alaska Road Commission sent the following

letter to the Commanding Officer, Fairbanks, Alaska:

Williams Equipment Company and Reed & Martin,

Inc., have a contract with the Alaska Road Commission

for constructing the Fairbanks to College and portion

of Steese Highway Road Project.

We have been informed that there is an asphalt plant

at Ladd Field, which, if proper arrangements cob be

made between the contractor and the Air Installation

388960—55 5

dort, INGRAM I GAOL ANY AM PEER GAA et IM

ee

40A

Officer for use of the plant would materially aid in an

-—. completion of the road project.

our consideration of this matter would be greatly

appreciated.

On July 20, 1950, Major Russell transmitted the above

letter to his superior officer with the recommendation that

the request be granted.

The Alaska Road Commission had a policy against renting

Government-owned equipment to any of its contractors since

it was felt such action might prejudice other bidders on a

project. However, since no other asphalt plant could be

made available to complete this project before the close of the

season, an exception was made in this case and the request

made for the loan of the plant as set out above. The request

was granted and the plant was made available for the use

of the plaintiffs. It was not in good operating condition at

that time and it accordingly became necessary for the plain-

tiffs to do considerable work thereon and make certain

repairs before it could be used. It was thereafter used by

the plaintiffs as contemplated in the performance of the

contract.

38. Discussions were had between plaintiffs and repre

sentatives of the Alaska Road Commission as to the proper

rental for the asphalt plant. It was agreed that had plain-

tiffs rented the plant in the State of Washington as originally

contemplated, the rental, transportation charges, costs of

erection and dismantling would total about $10,700. That

amount was divided by the estimated quantity of plant mix

to be laid giving a figure of $1.30 per ton as a rental figure

for the plant. While the plaintiffs orally agreed to that

rental figure, when they did so they relied upon the assurance

previously given by Major Russell that they would be paid

by the Ladd Air Force Base authorities for the work hereto- 2

fore referred to which they had done at Ladd Field. Shortly —

thereafter Major Russell advised the plaintiffs that payment

could not be made for the seal coating which had been per-

formed at Ladd Field. As a result of the failure to receive

payment for the work which they had performed at Ladd

Field, the plaintiffs refused to sign a change order prepared

by the Alaska Road Commission reducing the unit price of

EE - © ae

aaa PRETRIAL NONE at mot sre ce ccrmneteamanaamemmmmmmmemmenasatsianiiadtesmanibiicmmadizainmsiminteasibeauemansaes

2

RDRP Rh OR ROR ETS onl

41A

asphalt per ton by $1.30 which reduced the estimated total

of the contract by $10,790.

39. Under date of October 13, 1950, the contracting officer

directed that the change order be considered a written order

changing the specifications and that the rental stipulated

therein be deemed to be an equitable adjustment of the con-

tract price. He advised plaintiffs of their right to appeal

from that determination to the designated representative of

the head of the department. This was one of the matters

discussed at the conference in April 1951 heretofore referred

to and was within the scope of the appeal taken by plaintiffs

to the designated representative of the head of the depart-

ment. In denying the appeal such representative stated in

his letter of June 15, 1951, as follows:

LOA AIRS:

Prant RENTAL

The decision of the Contracting Officer set forth in

his letter of October 13 has been reviewed and is hereby

affirmed by the undersigned as Authorized Representa-

tive of the Head of the Department. Since the Change

Order, previously presented to you, modifies the unit

price of Item No. 140 (1), in strict accordance with the

initial agreement, the modified price has been used in

the accompanying voucher rather than indicating a de-

duction for plant rental. In order that final settlement

on this contract may be made it is again requested that

you execute Change Order No. 2 and return the indi-

cated papers to this office.

The plaintiffs refused to execute the change order. Upon

completion of the contract, it was determined that 7,820.3

tons of asphalt had been actually used and accordingly

$10,166.39 was deducted from payments to the plaintiffs. No

amount has been paid to the plaintiffs on account of the

work done at Ladd Field.

CONCLUSION OF LAW

Upon the foregoing findings of fact, which are made a

part of the judgment herein, the court concludes that as a

matter of Jaw the plaintiffs are entitled to recover, and it is

therefore adjudged and ordered that they recover of and

from the United States forty-five thousand eight hundred

ninety-five dollars and forty cents ($45,895.40).

42A

Gn the Gnited States Court of Glaims

No. 47331

(Decided January 11, 1955)

GENERAL CASUALTY COMPANY OF AMERICA,

CENTRAL SURETY AND INSURANCE CORPO.

RATION, WACKER CORPORATION, AND N. E.

DAUGHERTY, D/B/A N. E. DAUGHERTY CON.

STRUCTION COMPANY

Vv.

THE UNITED STATES

Mr. Ernest Hubbell and Mr. Clifford B. Kimberly for the

plaintiffs.

Mr. Carl Eardley, with whom was Mr. Assistant Attorney

General Warren EF’. Burger, for the defendant.

OPINION

Laramore, Judge, delivered the opinion of the court:

This suit arises out of a contract to construct an airport

at Zanesville, Ohio, and the petition is stated in two counts,

Count one of the petition, a Lucas Act claim, was dismissed

by this court on January 8, 1952. Count two is a contract

claim for equipment rental and expense, ditch rock excava-

tion, gravel processing plant, overtime wages, delayed dam-

ages, unpaid balance of contract price, shale excavation and

rock excavation.’

Plaintiff Daugherty entered into a contract with defend-

ant, acting by and through the Civil Aeronautics Adminis-

tration, for the construction of an airport at Zanesville, Ohio.

The contract price was estimated to be $1,047,328. The ac-

1No mention is made in plaintiffs’ briefs as to processing plant claim or

the claim for overtime wages. We assume and will treat them as having

been abandoned. In any event the processing plant was installed at the

election of the contractor, since the contract permitted the use of any one

of several methods.

ll

43A

cepted bid price included a unit price of 25 cents per cubic

yard for grading and $1.35 per cubic yard for rock excava-

tion.

On May 18, 1943, plaintiff Daugherty executed and deliv-

ered to the defendant payment and performance bonds both

executed by plaintiffs, General Casualty Company and Cen-

tral Surety & Insurance Corporation, in the sum of

$418,931.20 each.

Plaintiff Daugherty received notice to proceed effective

June 10, 1943. The project was to be completed within 150

calendar days thereafter. Daugherty began operations on

June 17, 1943. The facts are sufficiently set out in the opin-

ion below.

The plaintiffs’ first cause of action is based upon the alle-

gation that the Government coerced plaintiffs into equipping

the job for full scale operations, after the cosureties had taken

over the work, before a resumption date was apparent or

determined.

Plaintiffs say that after the cosureties had taken over the

work and near the end of the winter shutdown under a stop

order issued by defendant, the cosureties were required to

equip the job with the large amount of heavy construction

machinery which would be required for full scale operations,

long before a possible resumption date was apparent or

determined.

Plaintiffs further say that the cosureties upon demand of

defendant furnished evidence that they would be ready to

perform when work could be resumed and for the purpose

had sufficient equipment on the job to begin full scale opera-

tions by April 1, 1944. But defendant required the cosureties

to comply with its demands that equipment be placed on

the job forthwith and threatened that if they did not comply

large payments due plaintiffs for work done would be with-

held and made the further threat to default the cosureties on

the contract. The cosureties say that such action on the part

of the defendant was coercion and that in the period when

they were required to equip the job from April 1 to May 10,

1944, they performed no pay item work and by having fur-

nished the equipment demanded incurred thereby an unneces-

sary expense of $13,283.97.

Be als

PE SIS SRST

—— RIPEN RENAN SEIN AN OGL OAR OE a

444A

The contract specifications provided, as to equipment, in

part as follows:

2.1 General. The Contractor shall maintain on the job

sufficient equipment of the types needed to complete all

the work in accordance with the requirements of this

specification within the contract time. He may use any

type of earth-moving equipment capable of accomplish-

ing the specified and required results. * * *

Daugherty made strong but unsuccessful efforts to get suffli-

cient equipment which was in working order. He fell behind

in rental payments on some equipment which was then with-

drawn from the job by the equipment owners. After numer-

ous warnings, it was finally necessary to terminate the right

of Daugherty to proceed effective as of November 24, 1943.

An examination of the evidence indicates that defendant

made two demands: (1) that plaintiffs furnish information

concerning equipment availability by March 10; (2) that

plaintiffs bring their equipment to the site by April 15, or

sooner, if weather conditions permitted.

Since the damage about which plaintiffs complain con-

cerns the loss of rental on equipment brought to the site in

April, it is apparent that the alleged breach of contract

concerns demand number two,

On January 28, 1944, the contracting officer advised plain-

tiffs that 52 calendar days remained for the completion of

the work; that to complete in the contract time plaintiffs

“must have sufficient equipment on the job by April 15, 1944,

or sooner, if weather conditions permit, to operate on a full

scale basis.”

Normal grading operations commence in the Zanesville

area about March 15, but due to unseasonable weather plain-

tiffs were not able to commence work until May 1 and notice

to proceed was not issued until May 10. In January the

reasonable expectation was that grading operations would

commence about March 15. At that time, January, such a

demand could not be called unreasonable. Thus, if the

demand was not a breach of contract in January, it was not

a breach of contract in April, for the plaintiffs’ loss resulted

not from compliance with the order but from the unseason-

able weather which prevented the issuance of the notice to

|

)

|

45A

proceed at the expected time. It has been held that the

Government is not responsible for the vagaries of the

weather. Warren Brothers Roads Co. v. United States, 123

C. Cls. 48, 79.

Inasmuch as grading operations would normally commence

about March 15, any prudent contractor would have been

prepared to proceed shortly thereafter. Hence plaintiffs’

movement of equipment to the site in April was a normal

action and one which would have taken place regardless of

any demand by the defendant.

Therefore, it must be concluded that plaintiffs brought the

grading equipment to the site in April not because of threats,

but because it was what any prudent contractor would have

done. It was not a breach of the contract by the Government

and the plaintiffs could not recover on this claim.

The plaintiffs’ second claim is for recovery of the alleged

cost of ditch rock excavation. Plaintiff Daugherty subcon-

tracted the drainage work to the Weikel Construction

Company.

The profile drawings of the drainage structures showed

them to be located in an area and in a strata of soil classified

on the boring log as “Horizon C” material defined as “hard,

impervious, silty clay” which was “relatively hard and

impervious.”

In digging the trenches rock was encountered which had

to be blasted and the subcontractor was paid therefor at the

rate of $5 per cubic yard.

The fact that plaintiff Daugherty anticipated rock is

evidenced by the terms of the subcontract. The uncontested

evidence is that the subcontract carried a provision, the pur-

port of which was to protect the subcontractor against rock

should it be encountered. It also appears from the evidence

that rock was anticipated below grade on this part of the

job. The evidence further shows that blasting is ordinarily

necessary because of the confined nature of this type of

excavation.

Thus plaintiffs’ contention that they are entitled to recover

an additional amount because of an alleged changed condi-

tion is without foundation. Furthermore, there is nothing

in the evidence to disclose that plantiffs ever called the atten-

¢

,

&

:

AERIALS MOREE Ne emer |

2 IIT CyB NNN TSE Nak LR PRAT PL RS TALIIE IRENA LPOG AT Me eT AREER

46A

tion of the contracting officer to an alleged changed condition

in connection with this portion of the work.

Either failure to show a changed condition or failure to

give notice of a changed condition would prevent recovery

of plaintiffs on this claim. Having failed to show a changed

condition, this item of plaintiffs’ claim is denied.

The third claim of plaintiffs is for the unpaid balance of

contract price withheld from plaintiffs’ cosureties and ap-

plied to payment of taxes owed by plaintiff Daugherty.

At the time Daugherty’s contract was terminated defend-

ant was indebted to him in the amount of $56,783.56 for work

performed.

Defendant accepted the offer of the cosureties to complete

the contract but stated that claim to all sums due under

the contract at time of termination could not then be al-

lowed since there was at the time of termination a valid

assignment of money due under the contract in favor of the

LaSalle Industrial Finance Corporation. This was satis-

factory to the cosureties who then did go ahead with the

work without a supplemental contract. On January 3, 1944,

the Comptroller General certified as due the LaSalle Corpo-

ration, as assignee of Daugherty, the sum of $56,783.56.

Before a check was issued, a tax levy was filed against the

contractor in the amount of $45,366, in connection with the

Zanesville contract and $12,863.10 assessed in connection

with other work. The defendant thereupon refused the de-

mand of the cosureties for payment of the amount earned

by Daugherty prior to the termination of his right to pro-

ceed and by appropriate bookkeeping entries defendant set

off the sum due Daugherty against his tax indebtedness.

Plaintiffs contend the surety companies had a prior lien

to the amount in dispute and are entitled in this claim to

recover said amount. The law is tothe contrary. It has been

settled that the Government which has funds in its posses-

sion may apply said funds against amounts owed to the

Government by a prime contractor. United States v. Mun-

sey Trust Company, 332 U.S. 234; Standard Accident In-

surance Company v. United States, 119 C. Cls. 749.

The contractor could not, by assignment, transfer greater

rights than he had himself and as a matter of law the Gov-

47A

ernment had the right to set off the sums due under the

contract against the amount of taxes due and owing by

plaintiff Daugherty. Thus, plaintiffs are not entitled to re-

cover on this claim.

The plaintiffs’ third cause of action is for rock and shale

excavation.

The issues presented in this claim are (1) whether defend-

ant misrepresented the materials; (2) whether the shale

constituted a changed condition; (3) if so, whether Daugh-

erty gave notice as required by article 4; (4) whether decision

of a contracting officer, affirmed by the head of the depart-

ment, that (a) there was no rock, (b) there was no notice of

a changed condition, (c) there was no changed condition, are

final and conclusive; (5) the extent of plaintiffs’ recoverable

damages, if any.

The site of the proposed airport was a rugged hilly country

cut by deep ravines with ground elevations varying from

elevation 870 to 917. It was estimated that approximately

two million cubic yards of material would have to be moved

in order to flatten out the site for airport purposes. To

assist bidders the defendant made borings at intervals of

500 feet along the center lines of the runways and notified

the bidders that hand augers were used for this purpose.

Such augers bring up earth in granular form. At stages 33

on the E/W runway and 38 on the NW/SE runway, inter-

mediate borings were made between the regular intervals

mentioned. All borings, 35 in number, were represented by

defendant on the contract drawings. The defendant’s engi-

neer making the hand auger borings, found the soil to lie

generally in three horizons, as follows:

A. Brown topsoil, from zero to six inches in depth.

B. Yellow tan silty clay, six inches to nine feet in

depth.

C. Light tan silty clay and blue clay relatively im-

pervious and hard from nine feet in depth to grade.

The engineer reported also some evidence of shale and

loose rock below grade, but the charts and borings did not

show that plaintiffs would encounter hard shale as found

in later excavation. The borings were not all examined

scientifically, but only four samples thereof were submitted

i

5

> |

RRA SN CA

48A

to the Flood Soils Laboratory for analysis, and the table

of soils characteristics in the contract drawings was appar-

ently based upon the laboratory report. This fact was un-

known to plaintiffs. The defendant did not deliberately

misrepresent the materials it thought would be encountered

or hold back any information it had from plaintiffs.

There was a duty on the part of defendant, if it made bor-

ings, to fully disclose such facts as were found. Ranieri y,

United States, 96 C. Cls. 494, 506. This it did, and we can

find no reason to hold that the defendant misrepresented

the facts to such an extent as to cause a breach of contract

on its part.

The second, third, and fourth issues presented by this

claim are for the purposes of this opinion grouped.

The borings and data made and furnished by defendant

were inadequate, and plaintiffs encountered shale in locations

and amounts seriously in excess of those indicated by the

drawings. In these respects the contract drawings were not

approximately correct. Plaintiff Daugherty’s reasonably

careful inspection of the site gave no indication to him that

he would encounter materials any different from those repre-

sented on the contract drawings.

The total quantity of excavated materials moved was

2,056,262 cubic yards.

In July 1943 plaintiff Daugherty encountered hard shale

and concluded that it could best be removed by breaking it

up with a rooter. A rooter is a heavy blade which projects

into the ground and operates on the principle of a plow.

Daugherty’s rooter had three teeth, but after experimenta-

tion it was found that in some areas the hard shale could more

easily be rooted by removing two of the teeth, thus giving

increased power to the operation. The rooter was powered

by a crawler-type tractor having 110 drawbar horsepower.

The hard shale could not have been removed by pans used in

taking out clay without first rooting it. Considerable quan-

tities of soft shale were also encountered. This was “grad-

ing” and was handled with the same equipment, pans, and

tractors as used on dirt.

The defendant classified the material, now claimed by the

plaintiffs to have been hard shale and rock, as “grading” in

each of the 1943 monthly estimates, and plaintiff Daugherty

494

was paid upon that basis. Daugherty did, however, protest

orally in September 1943 to the resident engineer about such

payment. The following month in a letter to the engineer

in charge of design and construction, he stated that 200,000

cubic yards of hard shale had been encountered slowing

operations but did not claim a changed condition for purposes

of reclassification or payment. Previously Daugherty’s

engineer and two successive superintendents made strong

oral representations about a changed condition to defend-

ant’s resident engineer and his assistants and asked that pay-

ment be made for rock. This was refused upon the basis that

it was being rooted and therefore was grading within the

contract classifications. Plaintiffs’ engineer also told the

resident engineer that he was going to cross section the hard

materials and make claims for additional compensation

therefor. The resident engineer was requested to cross sec-

tion the materials but declined to do so. Plantiffs requested

the resident engineer to have representatives present while

plaintiffs took elevations, but he did not do so. The

resident engineer did not report to the contracting officer the

representations made by plaintiff Daugherty about the

changed conditions encountered until March 30, 1944. The

first such claim was made by the contractor in writing on

February 4, 1944, after counsel had been retained and was

for 193,000 cubic yards of rock alleged to have been excavated

in 1943. This claim was denied February 10, 1944.

Plaintiff Daugherty had not excavated a shale bank near

the runway intersection and when the work was resumed

in 1944 the cosureties contended that this shale constituted

rock within the contract definition. The pertinent specifi-

cations provided as follows:

3.1 General. * * *

All material encountered shall be considered as unclas-

sified excavation unless otherwise specified. The Con-

tractor shall inform and satisfy himself as to the

character, quantity and distribution of all material to be

excavated. No payment will be made for any excavated

material which is used for purposes other than those

designated, * * *

* * * * e

3.3-b Classification of Excavation. <All excavated ma-

terial will be classified as “Grading,” or “Rock

Excavation.”

an semen eng

Tees

50A

(1) Grading shall consist of the removal and satis-

factory dis 1 of all loam, sand, clay, gravel, soft

shale, soft slate, old gravel, broken stone or ituminous

macadam pavements, loose or decomposed rock, boul-

ders of less than one-half (14) cubic yard in volume

and all other materials not otherwise classified under

these specifications.

(2) Rock Excavation. Rock excavation shall include

all solid rock and boulders having a volume of one-half

(14) cubic yard or more, and all shale or ledge rock

which cannot be removed with an extra heavy duty

rooter powered with a crawler-type tractor having 110

drawbar horsepower in good condition and on firm foot-

ing, or a modern power shovel of three-fourths (%)

cubic yard capacity in good condition, without continu-

ous drilling or blasting; although blasting may be re-

sorted to, to facilitate the work. * * *

* * * * a

The special proposal conditions provided in part as fol-

lows:

10. Locat Conprrions: Bidders or their authorized

nts are expected to inspect the site of the work or to

otherwise thoroughly acquaint themselves with local

conditions as may affect performance of the contract

and to reasonably anticipate the difficulties to be en-

countered therein. \

11. Borrncs: Borings where shown were made by

means of a hand auger. Borings were made at. the

hi ag locations shown on the drawings, and the

character and depth of materials found are believed to

be approximately correct.

* * * * *

The contract provided in part as follows:

Arricts 3. Changes.—The contracting officer may at

any time, by a written order, and without notice to the

sureties, make changes in the drawings and/or speci-

fications of this contract and within the general scope

thereof. If such changes cause an increase or decrease

in the amount due under this contract, or in the time

required for its performance, an equitable adjustment

shall be made and the contract shall be modified in

writing accordingly. Any claim for adjustment under

this article must be asserted within 10 days from the

date the change is ordered: Provided, however, That

the contracting officer, if he determines that the facts

justify such action, may receive and consider, and with

the approval of the head of the department or his duly

authorized representative, adjust any such claim asserted

51A

at any time prior to the date of final settlement of the

poten Bg if the parties fail to agree upon the adjust-

ment to be made the dispute shall be determined as

provided in article 15 hereof. But nothing provided

in this article shall excuse the contractor from proceeding

with the prosecution of the work so changed.

Arricie 4. Changed conditions.—Should the contrac-

tor encounter, or the Government discover, during the

progress of the work subsurface and/or latent conditions

at the site materially differing from those shown on the

drawings or indicated in the specifications, or unknown

conditions of an unusual nature differing materially from

those ordinarily encountered and generally recognized as

inhering in work of the character provided for in the

plans and specifications, the attention of the contracting

officer shall be called immediately to such conditions

before they are disturbed. The contracting officer shall

thereupon promptly investigate the conditions, and if

he finds that they do so materially differ the contract

shall, with the written approval of the head of the de-

partment or his duly authorized representative, be modi-

fied to provide for any increase or decrease of cost and/or

difference in time resulting from such conditions.

e

* t * s

Article 15. Disputes.—Except as otherwise specifi-

cally provided in this contract, all disputes concerning

uestions of fact arising under this contract shall be

decided by the contracting officer subject to written

appeal by the contractor within 30 days to the head of

the department concerned or his duly authorized repre-

sentative, whose decision shall be final and conclusive

upon the parties thereto. In the meantime the contractor

shall diligently proceed with the work as directed.

It was agreed that a test would be made to see if the ma-

terial could be handled by a three-quarter cubic yard shovel

without continuous drilling or blasting. The test was made

in May 1944. The shovel handled the materials with diffi-

culty, but was able to do so without drilling or blasting.

The shovel did stick sometimes and it required several passes

with the bucket to get a load, whereas in gravel, dirt, or

clay this would not have been necessary. As a consequence

of the test, defendant declined to pay for “rock.” The plain-

tiffs’ cosureties then completed the contract and were paid

for “grading.” The plaintiffs did not rely solely on the

three-quarter cubic yard shovel but also used a one-yard

shovel which had more power, approximately twice the

IPRS Chit DEERE 5d

sande?

sp eB BGG STR AS! HR IRIE XN ok

Teh BAR eS

52A

weight of the smaller shovel, and was more efficient. The

material could have been moved with the smaller shovel alone

without blasting, but this would have required much addi-

tional time which was not available. Even with the larger

shovel the teeth would break off in the hard shale and both

machines required considerable repair in this regard. This

shale not only was hard to excavate and required more time

than clay, but also did not compact well and required more

loads to the fills, increasing costs.

It will be noted that article 4 of the contract provided

“should the contractor encounter, * * * during the progress

of the work subsurface and/or latent conditions at the site

materially differing from those shown on the drawings or

indicated in the specifications * * *.”

This case in principle is much like the case of W. C. Shep-

herd v. United States, 125 C. Cls. 724, 737, where the court

said:

We do not think there can be any question but that

the wet material was unforseen by both plaintiff and de-

fendant. It was an unknown, subsurface condition

differing materially from that shown by the drawings,

specifications and borings, and one which could not have

reasonably been anticipated from a study of the draw-

ings, borings and samples, or by an examination of the

site. * * * Plaintiff 1s therefore entitled under article

4 o fthe contract to recover the full excess costs of exca-

vating, hauling, and placing the wet material on the fill,

unless limited in his recovery by a matter hereinafter

discussed.

In the instant case we do not think there can be any ques-

tion but that there was an unknown subsurface condition

differing materially from that shown by the drawings, speci-

fications and borings, and one which could not have reason-

ably been anticipated from a study of the drawings,

specifications and borings, or by an examination of the site.

Plaintiffs are therefore entitled, under article 4, of the

contract, to recover the cost of excavating materials different

from those shown on the drawings, specifications and borings,

if notice was given as required by article 4.

Having found a changed condition under article 4, it

then becomes necessary to determine whether Daugherty gave

notice as required by article 4.

53A

This question is also settled by the decision of this court

in the Shepherd case, supra, wherein the court ruled that

calling the attention of the resident engineer to conditions

constituted compliance with article 4 of the contract.

Article 21 (b) of the contract provided that “The term

‘contracting officer’ as used herein shall include his duly

appointed successor or his authorized representative.”

In both the Shepherd case and in the instant case the resi-

dent engineer was clothed by the contracting officer with

authority to be on the job and see that the work was per-

formed. In the Shepherd case the court held that the resi-

dent engineer was the authorized representative of the

contracting officer, that the resident engineer had the duty

to communicate to the contracting officer matters which were

brought to his attention regarding conditions encountered

in the excavation, and that notice to the resident engineer

constituted compliance with the contract. In the instant

case Daugherty protested orally to the resident engineer in

September 1943 and a month later in a letter to the engineer

called his attention to the fact that hard shale had been

encountered. Previously Daugherty’s engineer and two suc-

cessive superintendents made strong oral representations

about a changed condition to defendant’s resident engineer

and his assistants and asked that payment be for rock.

It would be inane indeed to suppose that the resident engi-

neer was at the site for no purpose. We believe as in the

Shepherd case, supra, that the resident engineer was the

authorized representative of the contracting officer.

Plaintiff Daugherty’s responsibility ended when notice was

given to the authorized representative of the contracting

officer. Ifthe resident engineer did nothing, certainly it was

no fault of the plaintiff Daugherty. He did all that was

required of him under the contract.

That plaintiffs’ cosureties made claim of a changed con-

dition in 1944 there can be no doubt. On March 30, 1944,

the resident engineer acknowledged to his superior the fact

that plaintiffs were claiming rock. The claim was made

in writing under date of February 4, 1944, and was denied

February 10, 1944.

When the contracting officer and the head of the depart-

ment denied and failed to recognize a changed condition

54A

where plaintiff encountered 216,755 cubic yards of hard shale

which was not indicated in the borings and contract draw-

ings and which was more difficult of removal than grading,

and when said officers failed to make an equitable adjustment

for removal thereof, the determination was arbitrary and

was not supported by substantial evidence.

Thus, the decision of the contracting officer, affirmed by

the head of the department, is not final and conclusive and

not binding on the parties hereto.

Therefore, we find that notice of a changed condition un-

der article 4 was given the contracting officer and plaintiffs

are entitled to recover because of such changed condition.

Great Lakes Dredge & Dock Company v. United States, 116

C. Cls. 679, cert. den. 342 U. S. 953; Loftis v. United States,

110 C. Cls. 551.

We then approach the question of the extent of plaintiffs’

recoverable damages.

The following are the sums allowed and paid by the de-

fendant on the disputed materials at 25 cents per cubic yard,

the quantities and character of excavation claimed by plain-

tiffs, and the sums claimed therefor :

Cubic Unit Total Balance

yards price claimed Allowed

I iciiniccindninnsennmienly 418,851 | $0.65 |$272, 253.15 |$104, 712.75 | $167, 540.40

OOD ON iis icinictinasnecaasnsese 216, 755 1.35 | 292,619.25 | 54,188.75 | 238, 430. 50

685, 606 |........ 564, 872.40 | 158,901.50 | 405, 970.90

The 418,851 cubic yards of material plaintiffs claim was

hard shale and which had to be rooted was not hard shale

and was removed in part with the equipment plaintiffs admit

using thereon; viz, a rooter with three teeth powered by a

crawler-type tractor having 110 drawbar horsepower, after

which pans were used. There was not blasting. We believe

that the material, while difficult of removal, was grading

within the terms of the specifications, for which plaintiffs

have been fully paid at the contract price for grading of 25

cents per cubic yard.

The 216,755 cubic yards was hard laminated shale of a

type not shown on-the contract drawings nor by the de-

fendant’s original borings.

55A

In May 1944 when the work was almost completed the

defendant caused borings to be made by the H. C. Nutting

Company, a firm of soil experts. Out of some 17 borings,

three were made within the area where the plaintiffs con-

tended they encountered shale and rock in excavation, and

the borings showed shale of various characteristics, together

with some conglomerate limestone. On two of the three

holes the material was hard enough to get core samples with

a rotary core drill with diamond tools for cutting. On the

other holes a sample tube was driven in with a No. 225 ham-

mer using a three inch stroke.

To excavate this material required shovels and sometimes

a rooter with one tooth powered by two tractors, one pushing

and one pulling. The 216,755 cubic yards could not for the

most part have been removed in any efficient manner without

a one-yard shovel supplementing the three-quarter yard

shovel and by being loosened in some areas with a single tooth

rooter powered by two tractors. The job could have been

completed with a rooter powered by one tractor and with the

use of a three-quarter cubic yard shovel, but it would have

taken “forever andaday.” Plaintiffs did not have and were

unable to obtain equipment and supplies required for exten-

sive drilling and blasting.

In the completion of the project the cosureties expended

the sum of $1,584,942.27 of which $487,882.90 wasaloss. The

cosureties have paid up to December 31, 1951, a total of

$493,991.64 which is the sum claimed by them of any judg-

ment rendered herein.

Plaintiffs filed a claim for rock and shale excavation on

February 17, 1945. The contracting officer denied the claim

on June 4, 1945.

In addition, as we have heretofore noted, it was necessary

to use a one-yard shovel, aproximately twice the weight of

the smaller shovel, and even then the teeth would break off in

the hard shale causing considerable repairs and delays. This

shale was not only hard to excavate and required more time,

but did not compact well and required more loads to the fills,

increasing costs.

It is apparent from the evidence that the 216,755 cubic

yards of excavation was not rock nor was it grading within

338960—55——-6

Pe Ca er eee Pee OT EEE eT OT

56A

the terms of the contract for which the plaintiffs were paid

at the contract price of 25 cents per cubic yard. A fair and

reasonable price for excavation of hard shale would be

approximately 65 cents per cubic yard.

Plaintiffs have been paid $54,188.75 at the contract price

for grading.

Therefore, we find because of a changed condition under

article 4 of the contract plaintiffs are entitled to judgment in

the sum of $86,702, which is based upon excavation of 216,755

cubic yards at 65 cents per cubic yard, less the sum of $54,-

188.75 paid plaintiffs at the rate of 25 cents per cubic yard.

The final item of plaintiffs’ claim is for $4,337.91, the

amount withheld by defendant at the termination of plain-

tiffs’ contract for delay under article 9 of the contract.

Article 9 of the contract reads as follows:

Articie 9. Delays—Damages.—If the contractor re-

fuses or fails to prosecute the work, or any separable

part thereof, with such diligence as will insure its com-

pletion within the time specified in article 1, or any

extension thereof, or fails to complete said work within

such time, the Government may, by written notice to

the contractor, terminate his right to proceed with the

work or such part of the work as to which there has

been delay. In such event the Government may take

over the work and prosecute the same to completion, by

contract or otherwise, and the contractor and his sure-

ties shall be liable to the Government for any excess

cost occasioned the Government thereby. If the con-

tractor’s right to proceed is so terminated, the Govern-

ment may take possession of and utilize in completing

the work such materials, appliances, and plant as may

be on the site of the work and necessary therefor. If

the Government does not terminate the right of the

contractor to proceed, the contractor shall continue the

work, in which event the actual damages for the delay

will be impossible to determine and in lieu thereof the

contractor shall pay to the Government as fixed, agreed,

and liquidated damages for each calendar day of delay

until the work is completed or accepted the amount as

set forth in the specifications or accompanying papers

and the contractor and his sureties shall be lable for

the amount thereof: Provided, That the right of the

contractor to proceed shall not be terminated or the

contractor charged with liquidated damages because of

any delays in the completion of the work due to un-

57A

foreseeable causes beyond the control and without the

fault or negligence of the contractor, including, but not

restricted to, acts of God, or of the public enemy, acts

of the Government, acts of another contractor in the

erformance of a contract with the Government, fires,

hoods, epidemics, quarantine restrictions, strikes, freight

embargoes, and unusually severe weather or delays of

subcontractors due to such causes, if the contractor shall

within 10 days from the beginning of any such delay

(unless the contracting officer, with the a. of the

head of the department or his duly authorized repre-

sentative, shal] grant a further period of time prior

to the date of final settlement of the contract) notify

the contracting officer in writing of the causes of delay,

who shall ascertain the facts aoa the extent of the delay

and extend the time for completing the work when in

his judgment the ow of Foct justify such an exten-

sion, and his findings of fact thereon shall be final and

conclusive on the parties hereto, subject only to appeal,

within 30 days, by the contractor to the head af the

department concerned, whose decision on such appeal

as to the facts of delay and the extension of time for

completing the work shall be final and conclusive on the

parties hereto.

As we have previously stated, the delay in completing

the job was due to unforeseen conditions encountered. Fur-

thermore, the contractor did not refuse or fail to prosecute

the work, or any separable part thereof, with such diligence

as would insure its completion within the time specified in

article 1, or any extension thereof.

In the light of the above and our decision as to changed

conditions encountered, we believe the defendant had no right

to withhold said sum as damages for delay. Plaintiff is en-

titled to judgment on this claim in the sum of $4,337.91.

Plaintiff Daugherty rented equipment and _ received

property from the Maxon Construction Company, becoming

indebted thereby in the sum of $875.32. The Maxon Con-

struction Company assigned its claim to defendant.

Daugherty is indebted to defendant in the sum of $875.32, and

defendant is entitled to recover this amount from plaintiffs

on its counterclaim.

Mapven, Judge; Lirrteton, Judge; and Jones, Chief

Judge, concur.

58A

Wuiraker, Judge, dissenting:

The court says the refusal of the contracting officer to make

an equitable adjustment when conditions were encountered

differing from those shown on the contract documents was

arbitrary and not supported by substantial evidence. I do

not believe the record justifies this.

The specifications in section 3.3-b (1) defined grading to

include soft shale, and in paragraph (2) defined rock exca-

vation as follows:

Rock excavation shall include all solid rock and

boulders having a volume of one-half (14) cubic yard or

more, and all shale or ledge rock which cannot be re-

moved with an extra heavy duty rooter powered with

a crawler-type tractor having 110 dmwbar horsepower

in good condition and on firm footing, or a modern

wer shovel of three-fourths (34) cubic _ capacity

in good condition, without continuous drilling or blast-

ing * * *.

The opinion of the majority shows thatthe parties agreed

on a test to see if the material could be handled by a three-

fourths (34) cubic yard shovel without continuous drilling

or blasting. The opinion stated the result of the test as fol-

lows:

* * * The shovel handled the materials with difficulty,

but was able to do so without drilling or blasting. The

shovel did stick sometimes and it required several passes

with the bucket to get a load, whereas in gravel, diri,

or clay this would not have been necessary. * * * The

plaintiffs did not rely solely on the taree-quarter cubic

yard shovel but also used a one-yard shovel which had

more power, approximately twice the weight of the

smaller shovel, and was more efficieat. The material

could have been moved with the smaller shovel alone

without blasting, but this would have required much

additional time which was not avaiable. Even with

the larger shovel the teeth would break off in the hard

shale and both machines required considerable repair in

this regard. * * *

As a consequence of the test made, defendant declined

to pay for rock and insisted that the plentiff was entitled

to be paid only for “grading.”

wey eee

Bs: a

yor

59A

Had I been the contracting officer I might have come

toa contrary conclusion, but I cannot say that h’s conclusion

was arbitrary or not supported by substantial evidence, be-

cause of the provisions of section 3.3-b of the specifications.

This section shows that it was contemplated that shale

might be encountered. If it was soft shale it came within

the scope of “grading” as defined in subparagraph (1). If

it was hard shale, it was to be classified as “rock excavation”

as defined in subparagraph (2). Shale was to be included

within rock excavation only when it “cannot be removed

with an extra heavy duty rooter powered with a crawler-

type tractor having 110 drawbar horsepower in good condi-

tion and on firm footing, or a modern power shovel of three-

fourths (34) cubic yard capacity.” The test showed that

this shale could be removed with a power shovel of three-

fourths cubic-yard capacity. It is true it was difficult to so

remove it, but it was not impossible and, hence, there was a

basis for the contracting officer’s determination that the ma-

terial did not come within the definition of “rock excava-

tion,” but within the definition of “grading.” There were

but two classifications of excavation provided for in the

contract, to wit, “grading” and “rock excavation.” There

was no intermediate classification.

I see no justification for making an equitable adjustment

in the contract price. It is true the borings made by de-

fendant did not show shale, but the specifications show that

it was expected that shale might be encountered, and they

provided payment for its excavation—as “grading” if it

was soft, and as “rock” if it was hard. Under the specifica-

tions it had to be classified as one or the other; there was no

intermediate classification.

There was a substantial basis for the contracting officer’s

determination that this was not rock excavation and, hence,

it must be classified as “grading.” Since there was substan-

tial evidence to support the contracting officer’s decision, it

is binding on us.

I must, therefore, respectfully dissent.

sisson aise:

Sak toes

ia eOPAS.

60A

FINDINGS OF FAOT

The court, having considered the evidence, the report of

Commissioner Marion T. Bennett, and the briefs and argu-

ment of counsel, makes findings of fact as follows:

1. Plaintiff, General Casualty Company of America, is a

corporation duly organized and existing under the laws of

the State of Washington with principal offices in Seattle, and

engaged in the business of undertaking contracts of surety-

ship.

Plaintiff, Central Surety and Insurance Corporation, is a

Missouri corporation with its principal office in Kansas City,

Missouri, and likewise engaged in the general surety business,

Plaintiff, Wacker Corporation, is duly organized and ex-

isting under the laws of the State of Illinois with its prin-

cipal office in Chicago and is the legal successor in interest

of the LaSalle Industrial Finance Corporation to all matters

stated herein. The Wacker Corporation is a nominal party

plaintiff and waives any claim to any part of the proceeds

of the claim asserted in this suit.

N. E. Daugherty is an individual residing in Indianapolis,

Indiana, and at all times sated herein did business under

the firm name of N. E. Daugherty Construction Company.

2. On April 14, 1943, defendant, acting through the De-

partment of Commerce, Civil Aeronautics Administration,

advertised for proposals for furnishing the materials and

performing work required for the construction of grading,

draining, paving and fencing of an airport at Zanesville,

Ohio. The plaintiff, N. E. Daugherty, submitted a bid

which was accepted on May 12, 1943, and on May 18, 1943,

a contract, No. C3ca-2323, was entered into between Daugh-

erty and the defendant, acting through O. J. Starr, Civil

Aeronautics Administration Administrative Officer. The

contract price was estimated to be $1,047,328.00. The ac-

cepted bid price included a unit price of 25 cents per cubic

yard for grading and $1.35 per cubic yard for rock

excavation.

3. On May 18, 1943, plaintiff Daugherty executed and de-

livered to the defendant payment and performance bonds

both executed by plaintiffs, General Casualty Company and

61A

Central Surety & Insurance Corporation, hereinafter re-

ferred to as the co-sureties, in the sum of $418,931.20 each,

guaranteeing the satisfactory performance and completion

of the contract.

4, Plaintiff Daugherty received notice from the defendant

on May 27, 1943, to proceed with construction effective June

10, 1943. The project was to be completed within 150 cal-

endar days thereafter. Daugherty began operations on June

17, 1943. On June 19, 1943, Daugherty assigned to LaSalle

Industrial Finance Corporation all moneys due or to become

due under the contract, as provided in the Assignment of

Claims Act.

5. This suit arises out of the aforesaid contract and

the petition is stated in two counts. Count One of the peti-

tion, a Lucas Act claim, was dismissed by the Court on

January 8, 1952. Count Two is a contract claim covering

the following items with adjusted sums sought:

Equipment rentals and expense__-__- $13, 283. 97

Additional excavation ee - 00

iil FH CRORVAUON one nae ence -_ 138,395.00

Gravel processing plant-_---___- . 6,125.00

Overtime wages . 2,959.85

Delay damages_-- -- 4,337.91

Unpaid balance of contract price 57, 813. 37

RIO ORC VEO rite eae nt ainint oc wean cima nenmunaetas $167, 540. 40

ROCK OCDE ON oi Soman canna capa ane wensemcn canbe 238, 430. 50

503, 886. 00

With exception of the item for additional excavation,

which has been abandoned by the plaintiffs, the items above

will be treated in the order listed.

EQUIPMENT RENTAL CLAIM

6. The proposal conditions stated in part, “The satisfac-

tory completion of the proposed contract depends to a major

extent upon the availability of proper equipment for con-

struction purposes * * *”, The specifications provided, as

to equipment, in part as follows:

2.1 General. The Contractor shall maintain on the job

suflicient equipment of the types needed to complete all

the work in accordance with the requirements of this

specification within the contract time. He may use any

|

eee DSRS

62A

type of earth-moving equipment capable of accomplish-

ete specified ead semined venilia. re F

Daugherty made strong but unsuccessful efforts to get suf-

ficient equipment which was in working order. He fell be-

hind in rental payments on some equipment which was then

withdrawn from the job by the equipment owners. After

numerous warnings that the contract would be terminated

unless progress increased, it was finally necessary to terminate

the right of Daugherty to proceed effective as of November

24, 1943.

7. The defendant, through the Civil Aeronautics Admin-

istration, accepted an offer of the co-sureties to undertake

completion of the project by a letter of intent on November 29,

1943, reading, in part, as follows:

This acceptance is contingent upon your proceeding

with the construction with such diligence as will insure

its completion within the time remaining under the

contract. It is to be understood that any excess costs

occasioned the Government because of delays in com-

Seven this project will be chargeable to the N. E,

augherty Construction Company, as principal on the

original contract, and to you as co-surety up to the limit

of your bonded obligation.

On December 6, 1943, the co-sureties were given a notice to

proceed in accordance with the letter of intent on all work

remaining to be completed, the notice effective on Decem-

ber 7, 1943. Another notice, effective the same date, stopped

all work except clearing, drainage, and fencing, until such

time as a new notice to proceed should issue. Weather did

not permit construction to proceed again until May 10, 1944,

as hereafter noted.

8. In a letter on January 28, 1944, the contracting officer

told the co-sureties that 52 calendar days remained to com-

plete all work under the contract and that in order to accom-

plish the job it would be necessary for them to have sufi-

cient equipment on the site by April 15, 1944, or sooner if

weather conditions permitted, to operate on a full-scale

basis. The co-sureties were requested to advise the defend-

ant not later than March 1 what arrangements had been

made to procure the necessary equipment and were instructed

to list it. The threat was made that the last payment esti-

63A

mate covering work performed by Daugherty would not be

released until this was done and, further, that unless the

defendant was satisfied with the answer of the co-sureties,

their right to proceed would be terminated and the work

given to others.

In a letter on February 26, 1944, the contracting officer

stated no concrete evidence had yet been received that suit-

able arrangements had been or were being made by the

co-sureties, but extended to March 15, 1944, the deadline for

submission of the data requested in the letter of January 28.

Thereafter, by telegram, the co-sureties were advised that the

deadline had been moved back to March 10 and that, weather

permitting, a proceed order might be issued effective March

15. A meeting with representatives of the co-sureties was

set for March 11 in Chicago.

9. In the meantime, on March 7, 1944, the co-sureties fur-

nished the defendant with the requested information, point-

ing out they had already invested almost half a million dol-

lars in the enterprise and had every intention of completing

the contract. They insisted the organization, finances, and

equipment necessary for this purpose were available. At

the conference in Chicago the defendant expressed further

dissatisfaction, however, and informed the co-sureties that

the commitments received for equipment did not appear to

be either firm or adequate in amount. The co-sureties there-

upon promised to get further equipment, made a prompt

effort to do so and by March 21 had made substantial prog-

ress in that direction.

The co-sureties were moving equipment onto the site by

the middle of March and had sufficient equipment there to

resume full operations by April 1944. Normally, grading

and excavation work could have started by about March 15

in that area but there was an abnormal amount of rain and

freezing weather in March and April 1944 which made it

necessary to postpone operations until May. The co-sureties

were permitted to begin work on May 1 and the resume

order was issued May 10, no time being charged against the

co-sureties in the interval.

10. On February 17, 1945, the plaintiffs presented a claim

to the contracting officer for $14,387.19 for machinery rentals

ae

ye

pe staal

r

64A

incurred prior to May 10, 1944. In the pending svit this

sum is reduced to $13,283.97 because nothing is now claimed

for the month of March, the rental expenditures being for

the month of April and up to May 10, the date of the resume

order. It is found that the sum claimed was spent and that

it does not include any rental on equipment owned by

Daugherty. The plaintiffs contend that they should have

been permitted to secure the necessary equipment within a

reasonable time after which a possible resumption date was

apparent or determined. The plaintiffs, however, had no

choice due to the fact defendant withheld a payment, threat-

ened to cancel the right to proceed and in view of the further

facts that plaintiffs had already spent several hundred thou-

sand dollars in winter work and in cleaning up the Daugh-

erty obligations.

11. The contracting officer denied the claim on June 4,

1945, stating:

The lack of proper and sufficient equipment particularly

during the latter stages of the construction influenced

greatly our decision to terminate the prime contractor’s

right to proceed. Since the co-sureties had indicated

that they intended to utilize the prime contractor's

organization in the completion of the contract, we were

concerned about the adequacy of the equipment to be

furnished for this work. For this reason we corre-

sponded and conferred with representatives of the sure-

ties to insure that the completion of this project vital to

the Armed services would not be delayed. Our primary

purpose in these dealings was to ascertain that necessary

equipment would be delivered to the site in time to per-

mit the opening of construction as soon as weather con-

ditions were favorable.

Although weather conditions did not permit further

construction until May 10, 1944, it is held that the Gov-

ernment is no more liable for the cost of the rental on

equipment during this stand-by period than it is for

rental costs on equipment held inactive by reason of

unfavorable weather during the construction season.

Your claim in the amount of $14,387.19 is, therefore,

disallowed.

On June 16, 1945, plaintiffs appealed to the Administrator

of Civil Aeronautics in Washington, D. C., and by letter of

August 22, 1945, the Administrator ruled as follows:

* * * At the time the sureties took over there was no

65A

showing that they were in a position to resume opera-

tions with adequate equipment. The co-sureties had in-

dicated their intention to utilize the prime contractor’s

organization in completing the contract and it is reason-

able to assume that the Gevernment would be concerned

about the adequacy of the equipment to be furnished b

the co-sureties for completing the work. Althoug

weather conditions did not permit resumption of opera-

tions until May 10, 1944, it would not have been good

business practice for the Government to have waited

until that date to satisfy itself that the sureties were

ready to begin as soon as weather permitted. The Gov-

ernment could not afford to defer enforcing the require-

ments of the contract but of necessity had to be certain

that the sureties were in a position to resume operations

with adequate equipment at the earliest possible date.

DITCH ROCK CLAIM

12. Plaintiff Daugherty subcontracted the drainage work

for the airport to the Weikel Construction Company. The

specifications in the prime contract provided, in part:

4.1 General. The unit prices bid for all items shall be

full compensation for furnishing all labor, materials,

equipment, and incidentals necessary to complete work

in accordance with the plans and specifications.

4.2 Pipes and Storm Sewer Lines. All pipe lines will

be measured and paid for per lineal foot in place. Unit

price shall include trench excavation, disposal of exca-

vation material, and backfill, except granular backfill

which will be paid for separately.

The profile drawings of the drainage structures showed

them to be located in an area and in a strata of soil classified

on the boring log as “Horizon C” material defined as “hard,

impervious, silty clay” which was “relatively hard and im-

pervious.” In digging the trenches, rock was encountered

which had to be blasted. It amounted to 2,679 cubic yards

of sandstone and conglomerate. The subcontractor de-

manded payment for removal of rock at the rate of $8.00

per cubic yard. The co-sureties settled the claim for $13,-

395.00 which was computed at the rate of $5.00 per cubic

yard. This was a fair and reasonable settlement. The

prime contract had fixed a price of $1.50 per lineal foot of

pipe in place. The uncontested evidence is, however, that

the subcontract carried a provision identified by one of

hee _)

66A

plaintiff's principal witnesses, the purport of which was

to protect the subcontractor against rock should it be en-

countered. The subcontract is not in evidence. It appears,

however, from the weight of the evidence that rock was an-

ticipated below grade on this part of the job. Blasting is

ordinarily necessary because of the confined nature of this

type of excavation, where hard materials are encountered

and ditch digging equipment will not suffice. There is noth-

ing in the evidence to disclose that plaintiff ever called the

attention of the contracting officer to an alleged changed

condition in connection with this portion of the work.

13. Plaintiffs filed a claim for recovery of the alleged cost

of excavating this material on February 17, 1945. The con-

tracting officer denied the claim on June 4, 1945, stating in

part as follows:

* * * While you found it necessary to blast to remove

some of the material in drainage ditches, it is considered

that from the information shown on the plans, such a

contingency should have been anticipated and provided

for. Fou will note that the borings shown on the log

were all made down the center-line of the runways,

Even at this point, considerably removed from the loca-

tion of the underdrains, shale was shown to exist in

some areas at the level of the drainage trenches. The

profile drawings of the drainage structures showed them

to be located over the majority of the airpo.t area in

the strata of soil classified on the boring log as “Horizon

C” material and defined as “relatively hard and imper-

vious”. A reasonable interpretation of this definition

should have put the bidder on notice that the material

to be encountered was of such hardness as to require

removal, in the confines of a narrow drainage ditch, by

special methods other than with ordinary trenching

machinery. The fact that blasting was resorted to does

not justify a further allowance for the removal of this

strata of impervious material since the price quoted per

lineal foot for placing of the sewer pipes was to include

all expenses incident thereto.

Plaintiffs appealed to the head of the Department who

affirmed the decision of the contracting officer.

GRAYEL-PROCESSING PLANT CLAIM

14. The specifications provided for the uniform mix of

base course materials in accordance with specification CAA

35 A-83a, which stated in part:

67A

3.3. Equirment, General. The base course material

shall be mixed by a travelling mixing machine or by a

central mixing machine. The use of road mix will onl

be permitted when so provided in the proposal. All

equipment must be in good working condition and ap-

proved by the Engineer. Whatever type of equipment

is used must produce a uniform and well-pulverized

Nl alan

On April 24, 1943, a supplement to the above specification

was issued modifying the provisions on road mixing. This

supplement permitted such mixing of base course material,

provided pulverizing-mixing methods and machines were

used. A power-driven, rotary-type pulverizing machine that

would be satisfactory was specified. However, the supple-

ment went on to say—

If the base course material is delivered to the runway

in such uniform, mixed and pulverized state that no

admixture will be required to meet the specified require-

ments, ordinary road mixing methods will be permitted

for mixing in the water without the use of pulverizing-

mixing machines.

15. Production of base course materials was started in the

fall of 1943. Plaintiff Daugherty did not have any of the

mixing plants listed in the specifications but was using a

crushing plant at his gravel pit. The defendant tested the

materials and on or about September 27, 1943, advised

Daugherty that his method was not producing satisfactory

results and would not meet specifications unless a central

stabilizing plant was used. The fact is that some of the

materials were satisfactory and were placed with defendant’s

permission to speed up the job although defendant felt that

properly specified methods were not being used. Uniformity

of mixture was achieved largely by road mixing, but without

the specified pulverizing-mixing machine. Not enough sat-

isfactory materials were being produced, however, without

equipment listed in the specifications.

16. Plaintiff Daugherty brought a pug mill (usable as a

central mixing plant) to the site in September but it was

never placed in operation. When it became apparent the

job would have to be finished the following spring, the plain-

tiff with defendant’s consent and at its suggestion, com-

68A

menced to stockpile base course materials after bad weather

set in about October 23, although base course was placed

occasionally thereafter. The effect of the stockpiling opera-

tion was to mix the materials and, assisted by winter snows

and rains and by moving them a second time in the spring, a

uniformity required by the specifications was achieved. As

a consequence, the pug mill was never used. Stockpiling was

not at the time contemplated by plaintiff as a substitute for

methods listed in the specifications because it would have

required double handling and it became an expedient method

only because the construction season turned unfavorable

before the work was finished. Such a method was not pro-

vided for in the contract. Had it not been used, however,

plaintiff would have had to employ one of the methods con-

templated by the specifications, demanded by defendant, and

utilizing authorized machines.

17. On February 17, 1945, the plaintiffs filed a claim for

the sum of $9,996.79, also named in their petition, contending

that the pug mill was installed at defendant’s insistence

but was never necessary and that the said sum represented

the cost thereof from which the contractor received no use

or value. The contracting officer on June 4, 1945, denied the

claim. The plaintiffs appealed to the head of the Depart-

ment who, on August 22, 1945, aflirmed the decision of the

contracting officer, stating in part:

It must be held that the installation of this plant was at

the election of the contractor since the contract. per-

mitted the use of any one of several methods. It must

be held that the contractor installed the central mixin

plant in order that he might meet the requirements o

the specifications. In any event, in the absence of a

. protest, which the contractor had a right to make under |

the contract provisions, it does not appear that there |

is any basis for a contention that the Government should

bear the expense of such installation.

18. Plaintiff Daugherty owned the pug mill erected as

heretofore noted and in this suit plaintiffs seek payment for |

its having been set up and dismantled under the circum-

stances described above. The evidence on plaintiffs’ costs

regarding this item is meagre but not incredible. It is found |

that the reasonable cost to plaintiffs was $6,125.00.

-

69A

CLAIM FOR OVERTIME WAGES

19. The special proposal conditions which were made a

part of the contract provided in part as follows:

26. RecuLations Reiatine To Overtime Wace Com-

PENSATIONS Executive Orper 9240: (a) On and after

October 1, 1942, all of the requirements of Executive

Order 9240, dated September 9, 1942, relating to Over-

time Wage ae shall be observed by the con-

tractor, during the war, in the performance of this con-

tract, except insofar as it may be determined by the

Secretary of Labor, pursuant to Executive Order 9248,

that the provisions of Executive Order 9240 do not

apply. e requirements of Executive Order 9240 are

as follows:

(1) No premium wage of extra compensation shall be

paid to any employee in the United States, its terri-

tories or possessions for work on Saturday or Sunday

except where such work is performed by the employee

on the sixth or seventh day worked in his regularly

scheduled workweek and as 5 ve se i rovided.

a. Where because of emergency conditions an em-

ployee is eg to work for seven consecutive days in

any regularly scheduled workweek a premium wage of

double time compensation shall be paid for work on the

seventh day.

20. On December 9, 1943, the project engineer called atten-

tion of the plaintiffs to the requirement of Executive Order

9240 as to payment of double time on the seventh day and of

the heavy penalty for not doing so. A list of the names of

531 of those who should be so paid, in defendant’s opinion,

was provided plaintiffs.

On January 20, 1944, plaintiff Daugherty replied to the

notice of December 9, 1943, stating that by agreement with

the union the workers did not expect to be paid double time

but that by paying time and a half for Saturdays and Sun-

days this amounted to straight time for Saturday and double

time for Sunday. Defendant was asked to withdraw its

demand that double time be paid for Sunday and assurance

was given that while the arrangement made by plaintiffs

“perhaps stretched some” the exacting letter of the contract,

there was no intention to violate it, but only to expedite

completion of the job in harmony with all concerned. The

upshot of it was, however, that plaintiffs did pay $2,959.85

70A

to satisfy demands of defendant that the Executive Order

be complied with and this sum was over and above sums

already paid.

21. On February 5, 1944, the contracting officer advised

plaintiffs as follows:

The Department of Labor has recently ruled in response

to an application from this Administration, that the

Wage Stabilization Agreement for the Building and

Construction Trades Industry applies to all defense

- construction carried on by the AA. Consequently,

Executive Order No. 9240 is not applicable and we will

not be required to insist on the observance of the provi-

sion regarding double-time compensation.

As a consequence of this exemption, plaintiffs, thereafter,

were not required to pay double time.

22. On or about December 1, 1944, plaintiffs claimed reim-

bursement of the double-time compensation paid for work

performed on the seventh day. The claim was rejected by

the contracting officer and plaintiffs were notified on De-

cember 29, 1944, that this was so because the provisions of

Executive Order 9240 were a part of the invitation for

bids which resulted in the contract and that it must be as-

sumed that the cost of compliance therewith was taken into

account by Daugherty in preparation of his bid since no

exception was taken to those provisions. It was pointed

out that the order did not require payment for time and

a half on Saturdays and defendant stated that the increased

cost to plaintiffs was not due to the order but caused by

the labor union’s insistence that time and a half be paid for

Saturday work.

23. An appeal was taken on January 25, 1945, to the head

of the Department, as provided by the contract. On Feb-

ruary 17, 1945, and again on June 4, 1945, the claim was

the subject of further correspondence between plaintiffs and

the contracting officer. On June 16, 1945, the appeal to the

head of the Department was outlined in further detail and

the argument made that the labor union at no time claimed

double pay and was not responsible for these increased costs,

otherwise the workers would not have accepted time and

a half payment for the seventh day. On August 22, 1945,

71A

the head of the Department affirmed the decision of the

contracting officer for the same reasons given by the latter

on December 29, 1944.

CLAIM FOR DELAY DAMAGES

24. Plaintiff Daugherty and defendant executed the stand-

ard Government construction contract containing Article 9

as follows:

Artictr 9. Delays—Damages.—lf the contractor re-

fuses or fails to prosecute the work, or any separable

part thereof, with such diligence as will insure its com-

pletion within the time specified in article 1, or any ex-

tension thereof, or fails to complete said work within

such time, the Government may, by written notice to the

contractor, terminate his right to proceed with the

work or such part of the work as to which there has

been delay. In such event the Government may take

over the work and prosecute the same to completion, by

contract or otherwise, and the contractor and his sure-

ties shall be liable to the Government for any excess

cost oceasioned the Government thereby. If the con-

tractor’s right to proceed is so terminated, the Govern-

ment may take possession of and utilize in completing

the work such materials, appliances, and plan as may

be on the site of the work and necessary therefor. If

the Government does not terminate the right of the

contractor to proceed, the contractor shall continue the

work, in which event the actual damages for the delay

will be impossible to determine and in lieu thereof the

contractor shall pay to the Government as fixed, agreed,

and liquidated damages for each calendar day of delay

until the work is completed or accepted the amount as

set forth in the specifications or accompanying papers

and the contractor and his sureties shall be liable for

the amount thereof: Provided, That the right of the

contractor to proceed

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Appendix — United States v. Williams · 349 U.S. 938 | Frix