Petitioners Brief — City of Menasha v. Furton
Supreme Court brief1945
Ask Donna
What actually matters in this document.
Text
19
IN THE
SUPREME COURT OF THE UNITED STATES
Ocroser Term, 1945
No.
CITY OF MENASHA,
Petitioner,
vs.
CLARENCE FURTON, TRUMAN FURTON, LUKE
FURTON, FRED FURTON, ann RALPH JOHN-
SON, Co-PaRTNERS DOING BUSINESS AS F'urtToN BroTHers
Construction Company,
Respondents.
BRIEF IN SUPPORT OF PETITION FOR WRIT
OF CERTIORARI.
The Opinion of the Court Below.
The opinion of the Cireuit Court below is reported in
149 F. (2d) 945 and at R. 115-119.
Jurisdiction.
The statement concerning jurisdiction is set forth in
the petition and is incorporated herein by reference.
Statement of the Case.
The statement of the case appears in the petition and is
incorporated herein by reference.
20
Specifications of Error.
The Cireuit Court of Appeals for the Seventh Circuit
erred in the following respects:
1. In holding, in conflict with the decisions of this
Court, that Rule 56(c) of the Rules of Civil Procedure re.
quires that on motion for summary judgment by defend.
ant, the Court must accept plaintiffs’ fact allegations
and statements in their affidavits, and only on the assump-
tion of their verity, yet insufficient, may summary judg-
ment be entered against them, excluding establishment
of contrary facts beyond controversy by affidavits sub
mitted by the defendant.
2. In reversing the judgment of the District Court with
directions to try all issues without ascertainment, or pro-
vision for ascertainment, of material facts which exist
without substantial controversy, contrary to the letter and
spirit of Rule 56(d) of the Rules of Civil Procedure.
3. In holding (in conflict with the decisions of this
Court) that the alleged representations of elevation of
underlying rock contained in the plans and specifications,
under the facts and circumstances disclosed in the record,
might be held to be warranties and the basis for recovery
by plaintiffs for breach of warranty.
4. In reversing the summary judgment of the District
Court dismissing plaintiffs’ complaint.
at
ARGUMENT.
The Holding of the Lower Court that Rule 56(c) of the
Rules of Civil Procedure requires that on Motion for
Summary Judgment by Defendant the Defendant must
Accept Plaintiffs’ Fact Allegations and Statements in
their Affidavits and Only on the Assumption of their
Verity, Yet Insufficient, may Summary Judgment be
Entered against them is in Conflict With the Decisions
of this Court.
Rule 56(c) of the Rules of Civil Procedure provides in
part:
‘¢. .. The judgment sought shall be rendered forth-
with if the pleadings, depositions, and admissions on
file, together with the affidavits, if any, show that
except as to the amount of damages there is no genuine
issue as to any material fact and that the moving
party is entitled to a judgment as a matter of law.’’
The holding of the lower Court is in conflict with the de-
cision of this Court in the case of
Sartor v. Arkansas Nat. Gas, 321 U. S. 620, 64 S.
Ct. 724, 88 L. Ed. 967 (cited with approval in
Associated Press v. U. 8S. —U.S.—, 65 S. Ct.
1416, 89 L. Ed. 1512, 1515).
In this case this Court stated the correct interpretation
of Rule 56(c) of the Rules of Civil Procedure as being
that summary disposition should be on evidence which a
jury would not be at liberty to disbelieve, and which would
require a directed verdict for the moving party.
The meaning of the Court is clarified by its citation of
American Insurance Co. v. Gentile Bros. Co., (C.C.A. 5th)
109 F. (2d) 732, 735, in which is cited the case of Port of
99
Palm Beach Dist. v. Goethals, (C.C.A. 5th) 104 F. (2d)
706, 709, and by its citation of the case of Wittaker v. Cole.
man, (C.C.A. 5th) 115 F. (2d) 305, 306.
Application of the ‘erroneous rule by the lower Court
obviously resulted in the Court ignoring the fact that there
was no order of defendant’s engineer in writing direct-
ing performance of the work, a condition precedent to
recovery of compensation for the work as extra or ad-
ditional work pursuant to the contract. The great im-
portance of this single fact in the ultimate result at which
the Court arrived will be. developed in a subsequent head-
ing into which the subject fits more logically.
Application of this rule by the lower Court probably
caused the Court to ignore facts submitted by defendant
which supplemented facts presented by plaintiffs but
appear to controvert such facts because with the sup-
plementary facts the ultimate fact is contradictory to
the fact inferred from the partial presentation. These
facts will likewise be developed later.
Il.
The lower Court Erred in Reversing the Judgment of the
District Court with Directions to Try All Issues Without
Ascertainment, or Provision for Ascertainment, of Ma-
terial Facts Which Exist Without Substantial Contro-
versy, Contrary to the Letter and Spirit of Rule 56(d)
of the Rules of Civil Procedure.
Rule 56(d) of the Rules of Civil Procedure provides as
follows:
‘‘Rule 56(d). Case Nor Furzty ApsupicaTEp on
Motion. If on motion under this rule judgment is
not rendered upon the whole case or for all the re-
lief asked and trial is necessary, the Court at the
hearing of the motion, by examining the pleadings
and the evidence before it, and by interrogating coun-
23
sel shall, if practicable, ascertain what material
facts exist without substantial controversy, and
what material facts are actually and in good faith con-
troverted. It shall thereupon make an order specify-
ing the facts that appear without substantial
controversy, including the extent to which the amount
of damages or other relief is not in controversy and
direct such further proceedings in the action as are
just. Upon the trial of the action the facts so specified
shall be deemed established and the trial shall be
conducted accordingly.”’ ;
The District Court rendered judgment on the whole
case dismissing plaintiffs’ complaint. Therefore the oc-
easion for it to ascertain what material facts exist without
substantial controversy and what material facts are actual-
ly and in good faith controverted did not arise.
When the Appellate Court determined to reverse the
judgment of the District Court the same situation was
created as if the District Court had not rendered judg-
ment on the whole case. Is not the Appellate Court
then bound by the rule to ascertain what material facts
exist without substantial controversy, and what material
facts are actually and in good faith controverted? Or
is it then bound to remand the cause to the District Court
with directions that afford to the District Court oppor-
tunity to make such ascertainment?
That question has not been, but should be settled by this
Court.
Remanding the cause as the Lower Court did, with di-
rections to try all issues, was either without regard to
the letter and spirit of Rule 56(d) and the beneficial re-
sults intended to be accomplished thereby, or it was a
determination that not a single material fact exists without
substantial controversy, a situation which it will be
demonstrated later herein is not present in this case.
PORE AOE GFL LL IL CS IIE NO ‘
24
ITI.
The Lower Court Erred in Holding that the Alleged
Representations of Elevation of Underlying Rock Con.
tained in the Plans and Specifications, Under the Facts
and Circumstances Disclosed in the Record, Might be
Held to be Warranties and the Basis for Recovery by
Plaintiffs for Breach of Warranty.
MacArthur Bros. Co. v. U. S. 258 U. 8. 6, 42 S. Ct. 225,
66 L. Ed. 433.
Where representations in the contract and _ specifica- T
tions were alleged that a portion of the work would be § not
done in the ‘‘dry’’ and a portion in the ‘‘wet’’ and to do @ the :
the work in the ‘‘dry’’ the construction of certain coffer @ and
dams was specified and unanticipated conditions were @it sl
met and performance of the work became more expensive @ site
than anticipated, demurrer to the petition was sustained § delin
and the ruling affirmed on appeal to this Court. state
There was a similar statement to that in the proposal a
in the case at bar that the proposal was made with a full on
knowledge of the kind, quantity and quality of the plant, wil.
work, and materials required. In
The Court commented:
The Company’s ‘‘investigation may or may not 9), f
have been adequate. It, however, took its chances ies
on that. But in reality there was no representation
by the government nor is it alleged that the govern-
ment had knowledge superior to the knowledge of
the company. The latter acquired knowledge only
by the aid of their divers as work progressed. Such
being the situation does not the case present one of
misfortune rather than misrepresentation?’’
25
Simpson v. U. 8. 172 U. S. 372, 19 S. Ct. 222, 43 L, Ed. 482.
This case involved the construction of a dry-dock and
the excavation of the pit or basin for the dock. Borings
to a depth of from 39 to 46 feet were made by the Navy
Department and the result of these borings was delineated
on a profile plan purporting to show the character of
the underlying soil, and showed that the soil was stable
and contained no quicksand. A copy of this plan was
given to the Contractor before it submitted its bid. The
location of the dry-dock was to be fixed by the engineer
later.
The Court clearly defines the issue as being whether or
not the United States by the written contract guaranteed
the nature of the soil under the site of the proposed dock
and assumed the entire burden which might arise in case
it should be ascertained that the soil under the selected
site differed to the detriment of the contractor from that
delineated upon the plan. The Court failed to find ‘‘any
statement or agreement, or even intimation that any war-
ranty, express or implied, in favor of the contractor was
entered into concerning the character of the underlying
soil.’’
In the MacArthur case the Court distinguishes the fol-
lowing three cases where the opposite result was reached
and warranties were found. These decisions point out
the features or elements essential to the finding of a
varranty, which are missing in the case at bar.
Hollerback v. U. S., 233 U. S. 165, 34 S. Ct. 553, 58 L. Ea.
898.
In this case the specifications contained positive repre-
entations as to the character of material to be en-
‘ountered, and contrary thereto the contractor ran into crib
vork 4,3’ high consisting of sand logs filled with stone, a
26
structure erected by the same agency for which the con.
tract on which the suit was based was being performed,
The court distinguishes the Simpson case.
U. 8. v. Atlantic Dredging Co., 253 U. S. 1, 40 S. Ct. 423,
64 L. E. 735.
In this case the Court characterized the representations
as follows:
‘*Representations made by the government were
deceptive in that the test borings gave information to
the government not imparted to bidders of materials
more difficult to excavate than those shown by the
maps and specifications.’’
Christie v. U. S. 237 U. S. 34, 35 8. Ct. 565, 59 L. Ed. 933.
In this case the Court pointed out ‘‘the time not being
sufficient for the contractors to make their own borings,
they relied upon the government borings.’’
The decision of the lower Court on the facts in the ree-
ord in the case at bar is in conflict with the decisions of
this Court. A review of those facts is contained under the
following heading.
IV.
’
On the Facts Beyond Controversy Presented in the Record
the Lower Court Erred in Reversing the Summary Judg-
ment of the District Court Dismissing the Amended
Complaint.
We summarize under this heading our comments on
the facts, as the most concise and logical method of show-
ing the relation of the facts to the matters to which we
have hereinbefore referred. We use as subheads the
factual issues enumerated by the lower Court as requiring
determination in remanding the cause for trial.
27
1. Were the bed rock representations in the drawings
warranties upon which plaintiffs could and did rely
in entering into the contract?
On plaintiffs’ own showing the representations were
only those contained in the plans and specifications (R.
12), were approximations of the elevation of underlying
rock relating particularly to the foundations upon which
structures were to be erected and not to the floor of the
basin (R. 97) and with no representations as to the method
to be employed in performance of the work or conditions
to be met in execution of the contract.
ESS OS lS
On plaintiffs’ own showing they were reauired to inform
themselves as to the actual conditions and requirements
of the work (R. 17, 21) knew before the contract was
executed that no test borings had been made, and that
information in reference to the elevation of underlying
rock was indefinite, and the defendant had no superior
knowledge. (R. 69-70.)
Plaintiffs’ complaint is only as to method of perform-
ance of the work, that it was more expensive than contem-
plated, and the difficulties are all related to the existence
of a softer material, or the presence of more water than
anticipated (R. 12-13) in the construction of a project sur-
rounded on three sides by bodies of water end below the
level thereof. (R. 97.)
To these facts plaintiffs added proofs that when the
absence of rock at the anticipated elevation where some
of the baffle walls were to be erected was discovered, they
submitted an estimate of extra work in trenching and
lowering of baffle walls of $9107.00 (R. 76), defendant’s
engineer foretold that the amount of work required would
probably be less than estimated (R. 77), final directions
in writing were issued by defendant’s engineer that trench-
ing for the footings only for the baffle walls should
28
be performed, in other words the foundations need not
be lowered, or more excavation performed than in dig-
ging trenches in which the footings under the baffle walls
were to be placed (R. 80-81) and that the final allowance
for this extra approved by plaintiffs was only $3000.50
(R. 84) or less than one-third the original estimate as fore-
told by defendant’s engineer.
By these facts alone plaintiffs established agreement
that the result of the absence of underlying rock at the
anticipated elevation required the performance of only
extra or additional work in payment of which the plaintiffs
accepted the sum of $3000.50. (R. 84.) ’
To these facts defendant added proof that in their
proposal plaintiffs certified, before the contract was
executed, that they had informed themselves fully in re-
gard to the conditions to be met in execution of the con-
tract. (R. 95.)
Consideration is necessary of non-completion of the
work, non-payment of lien claims, and non-assertion by
plaintiffs of any claim for a long time, all admitted by
plaintiffs, with details supplied by defendant, but since
the lower court treated these as separate factual issues,
they are discussed later in this brief.
We submit that by dismissing the original complaint
(R. 10-11) with substantially the same showing, the Dis-
trict Court established it as the law of the case that plain-
tiffs had no cause of action for breach of warranty; but
regardless of the correctness of that contention, the finding
of the lower court that a cause of action for breach
of warranty may exist on the facts presented by this
record is in conflict with the law on the subject, well es-
tablished by the decisions of this court.
2. Was plaintiffs’ failure to make the payments neces-
sary for the completion of the contract excused (a) by
29
defendant’s failure to make all payments due the
plaintiffs or (b) by the added cost and trouble trace-
able to the rock bottom representations?
It will be noted that this question recognizes as a premise
non-completion of the work and non-payment of lien
claims. (R. 14.) Plaintiffs’ alleged cause of action, how-
ever, rests on the premise that the work was completed
and the contract performed, but at an added expense
ereated by the alleged misrepresentation.
Reference to the contract establishes no right in plain-
tiffs to payment until completion of the work and pay-
ment of lien claims. (R. 19.)
So plaintiffs seek to excuse their delinquency by claim-
ing that defendant’s failure to pay plaintiffs caused fi-
nancial stringency of the plaintiffs and made it impossible
for plaintiffs to proceed and to pay lien claims. (R. 14.)
Financial stringency is an untenable excuse in the face of
performance bond with surety. (R. 34.)
~od
“
The lower court extracts from those allegations the
additional excuse (b) that the added cost and trouble
traceable to the alleged misrepresentations prevented
performance. But that is not the exeuse the plaintiffs
offer, or what the lower court meant because it describes
plaintiffs’ default as ‘‘failure to make the PAYMENTS
necessary for completion of the contract’’ (R. 119) there-
by placing plaintiffs’ default and defendant’s alleged
dereliction on a dollar and cents basis, the non-payment
of a specific sum or sums.
What did defendant owe? What could plaintiffs claim
it owed?
Not a sufficient amount under the contract. The amount
withheld (R. 47) was far less than the amount unpaid on
lien claims. (R. 55.)
30
Not damages for breach of warranty. Such claim must
be based on performance of the contract, admittedly not
accomplished. Claim of non-payment of the very amount
in litigation as a basic element of the right to recover that
amount is fallacious reasoning in a circle.
Payment for extra or additional work under the terms
of the contract is all that could be asserted. And thus
the allegations of paragraph 13 of the amended complaint
(R. 14) which we have termed ‘‘deceptive and confusing”
entered into the consideration of the matter and led the
lower court to a confused legal result, as we propose to
demonstrate.
A claim for recovery for extra or additional work under
the terms of the contract was never asserted by plaintiffs,
either in the original complaint (R. 2-5), the amended
complaint (R. 11-15), or in the Appellate Court. (2. 130.)
The monthly estimates of we~’ performed, approved by
plaintiffs, establish lack of oc: claim throughout the
progress of the work. (R. 84-o., 54, 66-67, 68-69.)
Defendant supplied some of the proofs that no claim was
asserted until, pursuant to the contract, upon determi-
nation of the defendant’s engineer and authority vested
in him (R. 23-24), the cont~act was declared in default. (R.
61-65.)
Non-payment by defendant with no request or demand
for payment, or even assertion of claim cannot be asserted
by plaintiffs as excuse for plaintiffs’ default.
Under the terms of the contract (R. 25) such claim could
not be asserted in the absence of written order from de-
fendant’s engineer, and timely submission of claim, the
absence of which were established beyond controversy.
(R. 51, 74.)
The excuses urged by plaintiffs are not material factual
issues.
31
3, Lack of written order by the engineer for the addition-
al work and expense, or a waiver by the parties of
such written order.
There is no factual issue as to written order as just
stated.
Waiver by the parties of such written order is not
pleaded, asserted or claimed by plaintiffs. The extent of
their assertion is the indirect assertion (Par. 13, R. 14)
of ‘the engineer’s direction in writing’? and when the
existence of this writing was challenged (R. 51), it was
not produced.
It was error on the part of the lower court to create
out of such circumstances an issue as to waiver of written
notice, not raised by the parties themselves. That error
demonstrates the fallacy in reasoning into which the lower
court fell by concluding that the allegations of para-
graph 13 of the amended complaint (R. 14) were an as-
sertion of claim for compensation for performance of
extra or additional work pursuant to the contract, not only
the assertion of excuse for non-completion of the contract
and non-payment of lien claims as that paragraph plainly
states. That fallacy is more conspicuous in view of the
pronouncement by plaintiffs’ counsel to the Appellate
Court that plaintiffs were not asserting such claim. (R.
130.)
4. Other factual questions raised by defendant, including
controversy as to the completeness of the work and
dispute as to time for completion of the work.
There are no other material factual issues raised by
defendant. Neither are the two specified by the lower
court. Specification of two issues, and exclusion of speci-
fication of others, would lead to the conclusion that the
lower court itself could point out no others.
32
Plaintiffs admit non-completion of the work and non.
payment of lien claims (R. 14) and that is all that is
material on that subject.
There is no substantial dispute as to time for completion
of the work. The bare facts were referred to by de.
fendant that the contract provided for completion on or
before the 30th day of June, 1942, ‘‘time being of the es.
sence of the contract’’ (R. 18), the contract was declared
in default February 2, 1943 (R. 64-65) and on plaintiffs’
own showing claim was submitted March 4, 1943 and the
work was then only substantially completed and lien claims
remained unpaid. (R. 74,14.) Defendant presented proof
that an extension of time for performance was granted.
(R. 56.)
The time of performance is material in showing that
while it was longer than contemplated, yet no claim for
compensation as set forth in the complaint was asserted
by plaintiffs during all the time that the work was in
progress. That does not make the question of time of
performance a material factual issue.
33
CONCLUSION.
Mindful of the rules of this Court, we have labored
diligently to present the questions, involved in as concise
form as possible. Presentation of the questions are un-
usually involved with factual matters and the errors
charged to the lower court have aggravated that involve-
ment. The task has been difficult, and we hope, capable of
accomplishment within the limitations prescribed by this
Court.
We have attempted to demonstrate that important ques-
tions of federal procedure pertaining to the summary judg-
ment rule are involved and that the alleged errors of
the lower court are more than a misinterpretation of well
established and important legal principles but amount to
a departure from the accepted and usual course of judicial
procedure, an assertion which is not extravagant, if this
Court will envision what would happen when this case
reached trial before the District Court with the directions
issued by the Appellate Court. The trial judge would be
restricted from exercising his judgment in determining
certain material facts in reference to which no additional
proofs can be offered because the Appellate court had
directed that all facts were in issue and such a trial would
be contrary to all orderly judicial procedure.
Respectfully submitted,
Emu Hersa,
Counsel for Petitioner.
Metvin F. Crowrey,
Harvey ©. Harrwie,
Of Counsel.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.