Appendix — United States v. Anthony Grace & Sons, Inc.
Supreme Court brief1966
Ask Donna
What actually matters in this document.
Text
ew
Supreme Court of the United States
OCTOBER TERM, 1965
No. 439
UNITED STATES, PETITIONER
vs.
ANTHONY GRACE & SONS, INC.
ON WRIT OF CERTIORARI TO THE UNITED STATES
COURT OF CLAIMS
INDEX
Original Print
Record from the United States Court of Claims
Petition : 1 1
Exhibit 3—Letter of acceptability from De-
partment of the Air Force to Anthony
Grace & Sons, Inc., dated October 29,
1958 .... 23 13
Exhibit 7—Letter, cancelling letter of ac-
ceptability, from Department of the Air
Force to Anthony Grace & Sons, Inc.,
dated October 1, 1959 .............0...0.02..000.-... 42 18
Defendant’s answer .............22.--.---.sccecccseeeeeeeeeeee-eee 44 20
ae
ii INDEX
Original Print
Record from the United States Court of Claims—
Continued
Defendant’s motion for summary ——
(omitted in printing) . ip Pe ESA wren 51 25
Exhibit Pap aeemD aR rot WN ; 51-A 25
Opinion of Armed Services Board of
Contract Appeals . ms B1-A 26
Letter cot Shales A, ree to
George S, Robinson, dated October
et ctcetoeiencns 61-L 40
Letter from Gee? ®. Robinace to , Sal-
vatore A, Locurto, dated October 19,
1959 . ead ei 61-N 42
Leiter ss - aiid iii: to ‘Sale
vatore A, Locurto, dated December
©, FID wevcacccvniniccinsssesseerererccenversererervers 61-0 438
Letter from Salvatore A. Locurto to
Secretary of the Air Force James H.
Douglas, dated December 16, 1959. §1-P 44
Letter from Captain Lloyd H, Purdy
to Anthony Grace & Sons, Inc., dated
December 22, 9859 .. sadconts 51-R 46
Paragraph 3% of Bid nk seein
Services Housing Project .......... 51-S 47
Opinion of Commissioner and aaa atl
for conclusion of law LEAMA LEE ES, 48
Opinion, Cowen, Chil... RE a 66
Dissenting opinion, Davis, J. ... i odeliiaicemhaa 9,5 a 88
Clerk's certificate (omitted in printing) ......... 219 91
Order allowing certiorari... Se ia hi ae ae 92
—
(fol. 1)
IN THE UNITED STATES COURT OF CLAIMS
No. 133-61
ANTHONY GRACE & Sons, INC., PLAINTIFF
Against
THE UNITED STATES OF AMERICA, DEFENDANT
PETITION—Filed April 5, 1961
The Petition of Anthony Graze & Sonis, Inc. respectfully
shows to this Honorable Court and alleges:
1, Plaintiff, Anthony Grace & Sons, Inc. is a New York
corporation with its principal office for the regular trans-
action of business at 151-45 6th Road, Whitestone, City
and State of New York.
2. Jurisdiction is conferred upon the Court of Claims
to render judgment in this action pursuant to 28 U.S.
Code, Section 1491,
8. Plaintiff is a building and construction contractor
who was, during the period herein set forth, qualified by
experience and financial responsibility to construct hous-
ing units fn accordance with the provisions of Section 408
(b) of Title IV of the Housing Amendment of 1955, as
amended,
4. On or about the Ist day of September, 1958, the De-
fendant, through the Department of Air Force, trans-
(fol. 2] mitted to the Plaintiff certain documents, includ-
ing Invitation For Bid (IFB) No, 19-608-59-15, relating
to the construction of 177 Units of Capehart Family
Housing at Topsham Air Force Station, Maine, designated
FHA Projects Nos, 022-81015-Air 12 and 022.81016-Air
18. Said bid had as its opening date September 30, 1958,
and
5.
was opened on that date.
In part pertinent hereto the Invitation defined the
undertaking of the bidders, including this Plaintiff, in the
following language:
A.
B.
[fol.
“2. Sealed bids (in triplicate) for the construction
through FHA insured mortgage financing of the
above described total housing project, including the
furnishing of all necessary labor, equipment and
materials and the performing of all work, services
and arrangements, in strict accordance with the
terms of a Letter of Acceptability and a Housing
Contract, specimen forms of each being attached
hereto, will be received at Installation Engineers
Office, Attention: Topsham Monitor, Topsham
A.F.B., Maine until 2:00 P.M, E.S.T. on 80 Septem-
ber, 1958.”
“1. b. When bids are received and after consulta-
tion with the Federal Housing Commissioner (here-
inafter called the ‘Commissioner’), the Department
determines the person, partnership, firm or corpora-
tion, qualified by experience and financial responsi-
bility, who has submitted the lowest acceptable bid.”
‘e, The Department issues to that bidder (herein-
after caller the ‘eligible bidder’) a Letter of Accept-
abilty. That letter requires the eligible builder,
among other things, to take four actions: first, to
form 2 new corporation(s) (hereinafter called the
‘mortgagor-builder’) ; second, to arrange financing
for the cost of the total project, including profit, by
Building Loan Agreements between the mortgagor-
builder and mortgage lenders (hereinafter called the
‘mortgagees’); third, to cause each mortgagee to
8] obtain the Commissioner’s Commitment for Insur-
ance; and fourth, to execute a three-party Housing
Contract which defines the rights and obligations of
the Department, the eligible builder and the mort-
gagor-builders. The Letter of Acceptability also re-
quires the Department to execute a lease of a project
site to each mortgagor-builder.”
C.
D.
[ fol.
“d. Once the foregoing arrangements are made,
the parties in interest effect a ‘closing’ in which the
relationships of the parties are definitely established
by the delivery of all legal instruments.”
“4... . Should the bidder find discrepancies in, or
omissions from, such Drawings and Specifications
or other documents attached hereto, or should he be
in doubt as to their meaning, he should at once noti-
fy the Contracting Officer, Otis Air Force Base,
Massachusetts, and obtain clarification prior to sub-
mitting a bid. Information given will be transmitted
to all known interested bidders, . . .”
“5. Under the provisions of Title IV of the Hous-
ing Amendments of 1955, as amended, the total prin-
ciple [sic] amount of the mortgages is limited, among
other things to the amount of the bid of the eligible
builder. However, the Davis Bacon Act and Section
212(a) of the National Housing Act as amended
require that wages paid to laborers and mechanics
be the prevailing wage as determined by the Secre-
tary of Labor not more than ninety (90) days prior
to the commencement of construction. Since more
than ninety (90) days may elapse from the date of
this Invitation for Bids to the commencement of con-
struction, the bids called for by this Invitation For
Bids will include a provision for adjustment of the
dollar amount therein specified to reflect any differ-
ence between the tentative minimum wage schedule
attached hereto and the applicable minimum wage
scheduie as finally determined by the Secretary of
Labor. Any such adjustment will be in an amount
4] determined by the Commissioner to reflect such
differences, and the amount of the lowest acceptable
bid and the FHA estimated total replacement cost
of the projects will be amended in the amount so
determined by the Commissioner; except that, if such
an adjustment would increase the amount of the bid
above the amount of any other statutory maximum
applicable to the insurable mortgages, the eligible
builder will have the option of reducing his bid to
such statutory maximum or of withdrawing his bid.
ti
E. “8. Each bidder is required to submit with his bid
a certified check in the amount of $25,000, payable to
the Treasurer of the United States, to insure that if
he is the lowest acceptable bidder for the total of 177
family housing units he will perform the necessary
preliminary steps and effect a closing with FHA
within the time prescribed in the Letter of Accepta-
bility, including the furnishing of an acceptable per-
formance and payment bond. In the event the lowest
acceptable bidder fails to effect a closing with FHA
within the time prescribed, his deposit will be for-
feited and become the property of the Government
as damages unless the Department finds that he has
made every effort to effect such closing and extends
the time to effect such closing. If the lowest accept-
able bidder effects a timely closing with the FHA
the amount of his deposit will be refunded to him
24 hours after the initial closing with FHA....
“a. ‘Timely Closing, as referred to in this para-
graph of the Invitation For Bids and closi:g period
as referred to elsewhere in these forms is construed
to be a period of approximately 60 days from the
date of opening of bids.”
F. “24. Bidders are further advised that the Housing
Contract will also be subject to certain other statu-
tory provisions with respect to labor and other mat-
ters as shown in the specimen form of Housing
Contract.”
[fol.5] 6. That the Contracting Officer is clearly identi-
fied as that Government officer resident at Otis Air Force
Base.
7. That additional documents transmitted with said
IFB included:
A. Plans and specifications prepared by Kelly &
Gruzen, architects.
B. A schedule of rates of wages determined by the
Secretary of Labor as applicable to the work to be
perfc ‘med. Said schedule is entitled, “Schedule A—
Rates of Wages Predetermination No. $23,731, Date
of Predeterminations June 19, 1958 Expiration Date
IRON SEAL AS PE NY TID ASS GLAAD, ARTES GET ORE” og SEE MRSC SPOR OR RE I
[fol.
5
of Predetermination September 18, 1958”. A copy
of this schedule is hereto annexed and made a part
hereof and designated Exhibit 1. In substance said
schedule sets forth minimum rates of wages per hour
for specific laborers and mechanics, including spe-
cifically designated building laborers (page 1); an
apprentice schedule (page 2) ; hourly rates for Build-
ing Construction personnel (page 3) ; and Heavy and
Highway Construction personnel (page 4).
C. A statement issued by the Federal Housing Ad-
ministration dated August 6, 1958 entitled, “Final
Appraisal and Eligibility Statement” consisting of a
Schedule A and Schedule B, together with a listing of
additive alternates. A copy of said statement is an-
nexed hereto and made a part hereof and designated
Exhibit 2. The aforementioned Schedule B spe-
cifically provided as follows:
“Off-site improvements to be furnished by the
Government and/or which the Government will
not be reimbursed out of mortgage proceeds:
(list items of off-site improvements
estimated above)
Certain earthwork, seeding, streets and paving,
sanitary sewer and necessary additions to sewer-
6] age disposal system, storm drainage, manholes,
headwalks, water and electrical distribution and
landscaping.”
D. A set of Specifications clearly segregating and
defining the scope and situs of the work to be per-
formed, namely, “Section 1 on-site, site preparation”
and “Section 2 on-site, Excavation, Filling and Back-
filling For Building Construction”,
1. That the said Section 2 in paragraph 2-01
defines the scope of on-site work, as follows:
“2-01 Scope
(a) Wo.k Included. The work covered by
this section of the Specifications consists in
furnishing all plant, labor, equipment and
materials and in performing all operations
=
in connection with excavating, filling, back-
filling and rough grading, complete for the
building and for building utilities lines to a
point five (5) feet outside the foundation
line, and other related items in strict accord-
ance with this Section of the Specifications
and the applicable Drawings, and subject to
the terms and conditions of the contract.”
“(b) Work not Included. Clearing and grub-
bing, excavation, filling and grading for
parking areas, roads, walks, drainage, sew-
ers and other sub-surface utilities systems,
and excavation for the building utilities be-
yond planes five(5) feet outside the building
line are not included under this Section of
the Specifications. Stripping of topsoil is
specified in Section 1, Site Preparation.”
8. That, on or about about September 30, 1958, Plain-
tiff duly submitted its bid bearing the same date in re-
sponse to and in accordance with and in reliance upon the
terms and conditions of said Invitation and documents
related and appended thereto. Plaintiff, in its bid, offered
to construct said housing and furnish the necessary serv-
[fol. 7] ices connected therewith at a base price of $2,-
653,022.00, and to furnish certain additive alternatives
at a price of $213,071.00 or a total price of $2,866,093.
9. Thereafter, by letter dated October 29, 1958, the De-
fendant, acting through the Department of Air Force, ad-
vised the Plaintiff that it was the “eligible bidder” and
had submitted the lowest acceptable bid. This letter of the
Department of Air Force and the documents referenced
therein, is entitled “Letter of Acceptability” and from it
emerges the contract between this Plaintiff and the De-
fendant. Said “Letter of Acceptability” is annexed hereto
and made a part hereof, and is designed Exhibit 3.
10. That said Letter of Acceptability, provided in part
as follows:
“2. Failure to perform all obligations prior to the
é time prescribed for closing will be just cause for
| cancelling all commitments undertaken with you in
PRI ae Ee
7
connection with the housing project and for the re
covery under your bid security of liquidated damages
in the sum of $25,000, together with actual damages
to the Department, such actual damages to be
itemized and determined by the Contracting Officer,
whose decision will be reduced to writing and fur-
nished to you by mail or otherwise. Such decision
shall be final and conclusive unless, within 30 days
from the receipt thereof, you appeal in writing to the
head of the Department or his duly authorized repre-
sentative, and his decision shall, unless determined by
us as necessarily to imply bad faith, or not supported
a court of competent jurisdiction to have been fraudu-
lent or capricious or arbitrary, or so grossly errone-
by substantial evidence, be final and conclusive. In
connection with any appeal under this paragraph
you will be afforded an opportunity to be heard and
to offer evidence in support of your appeal.”
“6. You are required to be ready for the closing on
or before January 8, 1959, and your failure to do so
(fol. 8] will indicate your inability to carry out the obliga-
tions and terms of your bid and this Letter of Accept-
ability, provided that the Contracting Office: may
extend the date of closing in writing upon your sub-
mission of written documented proof that the delay
was caused by conditions beyond your control.”
11. That Plaintiff duly entered upon performance of
the conditions of said contract on its part to be performed,
as s.t forth hereinabove in paragraph 5. Further, Plain-
tiff on or about the 19th day of November, 1958 applied
for an appropriate wage determination as required under
the following provision set forth in said Letter of Accept-
ability.
“1, n. Make aplication through the Contracting
Officer, Otis A.F.B., Massachusetts, to the Secretary
of Labor for an appropriate wage determination,
if necessary (on a Department of Labor form DB-11,
which will be supplied upon request by the Contract-
ing Officer) for use in the construction of the project,
and to furnish a copy of such wage determination
to the Contracting Officer and the Commissioner.
Such wage determination will be used by the Com-
missioner to increase or decrease the bid price in the
manner specified in your bid.”
12. That the original closing date of January 8, 1959
as set forth in the Letter of Acceptability, was, by mutual
consent of the parties, postponed and extended on several
occasions because of conditions beyond the control of the
Plaintiff and principally for the reason that Defendant
was unable and unwilling and in any event, did not furn-
ish to Plawtiff, as required by it under said Letter of
Acceptability, the appropriate and final revision applicable
to the final wage determination,
18. Plaintiff's repeated and successive best efforts to
secure such revisions arising out of said applicable and
appropriate wage determinations were unsuccessful, Con-
flicting rulings and interpretations arose within certain
(fol. 9} agencies of the Defendant, including the Director
of Federal Housing, Department of Labor and the Depart-
ment of the Air Force as to the appropriate increase ap-
plicable to this agreement. Plaintiff was not a party to
these conflicts and did not directly or indirectly contribute
thereto,
14. That, as heretofore stated in paragraph 11, Plain-
tiff, after having entered into performance under said
agreement, had, on the 19th day of November, 1958 made
application for an appropriate wage determination, It
was not until January 28, 1959 that Plaintiff received
two new schedules of wage rates, each dated January 28,
1959 and expiring April 29, 1959, herein referred to as
Decision 2A and 2B. A copy of said Decision 2A desig-
nated “Decision of the Secretary”, U.S, Department of
Labor, bears Decision No, T18 569 and is annexed here-
to and made a part hereof and designated Exhibit 4. It
sets forth hourly wage rates for various classifications,
including “Laborers (Building)". The companion De-
cision, referred to as Decision 2B, bears No, T14 020 and
is annexed hereto and made a part hereof and designated
Exhibit 5. It sets forth wage rates for “Heavy and High-
way Construction” under the subject of “Construction
. Streets and Roads in connection with Capehart Hous-
ng”.
A. The initial and base schedule of rates and re-
lated scope of work section of the specifications clear-
ly covered work from the building foundation line
“to a point five (5) feet outside the foundation line”
(Exhibit 1). The new schedule of rates (Decision
2A, Exhibit 4) arbitrarily disregarded the five (5)
feet limitation and extended the higher building con-
struction rates to all work beyond the five (5) ft.
from the foundation so as to cover all work in the
proposed project except for work covering construc-
tion of the streets,
B. The companion decision 2B (Exhibit 5) similar-
ly materially differs from the basic schedule of rates
d (Exhibit 1) and imposes the low rates of wages for
: “heavy and highway areas” on additional areas, not
: (fol.10] originally contemplated, namely, Section 1, Para-
graph 1.14 and Sections 28 and 29 of the specifica-
tions,
15. That the revisions evidenced in said Decisions 2A
and 2B (Exhibits 4 and 5) constituted a substantial
change in labor rates as well as applicable areas for which
the work at such rates was to be performed, materially
differing from the requirements and rates spelled out in
the original Invitation For Bid and the bid of the Plain-
tiff. Plaintiff promptly endeavored to expedite the pro-
cessing of a revision of its bid price by requesting the
Defendant through the Department of Air Force to re-
quest of the FHA a revised final appraisal and eligibility
statement,
16, That various conferences were held between Plain-
tiff and the interested Departments representing the
Defendant, including Department of Air Force, Depart-
ment of Labor, and the Federal Housing Administration,
and correspondence exchanged, all in an effort to finalize
the applicable labor rates pertinent to Plaintiff's per-
formance under its contract with the Defendant. Plain-
tiff was advised that it was entitled to an increase in
price as a result of said Decisions 2A and 2B, as is evi-
denced by letter Plaintiff received from the Federal Hous-
ing Administration dated May 18, 1959, copy of which
~ Deng hereto and made a part hereof and designated
t 6,
10
17. That, by telegram dated March 28, 1959 the Di-
rector of the Federal Housing Administration advised the
Plaintiff to prepare recalculation of price based on the
new wage schedules so that same might be reviewed.
Pursuant thereto, Plaintiff submitted to the FHA a sched-
ule representing revised costs reflecting said Decisions
2A and 2B, the then current wage determinations.
18. Thereafter, conferences were held with officials of
Department of Air Force and Department of Labor and
flowing therefrom and in accordance therewith Plaintiff
prepared a revised schedule of prices based on the current
{fol. 11] Department of Labor wage rates submitting
same to the FHA and Department of Air Force on or
about May 14, 1959.
19. During this entire period, the closing date originally
scheduled for January 8, 1959 had been adjourned from
time to time and the Plaintiff expressed its desire and
willingness to set a firm closing date in their letter to the
Department of Air Force dated July 2, 1959 immediately
upon the interested agencies within the Government re-
solving the appropriate increases applicable to the wage
determinations pertinent to this particular contract.
20. That thereafter, through no fault of Plaintiff, but
wholly through the negligence, failure and refusal of the
Defendant, acting through its duly authorized representa-
tives, Plaintiff was unable to secure the appropriate in-
creases in said wage determinations, despite its best ef-
forts to do so.
21. That on or about June 26, 1959 the Department of
the Air Force advised Plaintiff that it would not grant
any revisions in the current wage scales allowing Plaintiff
additional increase in contract price.
22. That on October 1, 1959, the Department of Air
Force cancelled the Letter of Acceptability theretofore en-
tered into with Plaintiff, a copy of which letter is hereto
annexed and made a part hereof and designated Exhibit
7.
23. That on October 7, 1959 Plaintiff unsuccessfully
sought to continue in its performance under said agree-
ment, which offers and opportunities were denied Plaintiff,
ee n
24. That on or about December 31, 1959 Plaintiff en-
tered an appeal with the Armed Services Board of Con-
tract Appeals ASBCA #6167. Said ASBCA, on June 29,
1960, dismissed Plaintiff’s appeal on the ground that
Plaintiff’s appeal was not filed within the required 30
(fol. 12] day period from the alleged decision of the Con-
tracting Officer. Said Board of Contract Appeals, however,
did not consider any questions or matters other than the
timeliness of the appeal and did not accept the Plaintiff’s
position that they did not recognize the particular official
of the Department of Air Force as its Contracting Officer
or the letter from said official as a “final decision”.
25. That Defendant’s arbitrary and capricious action,
in direct violation of its contractual obligations, made it
impossible for the Plaintiff to continue in its efforts to
perform under this contract by refusing to issue the ap-
propriate revised wage determination reflecting pertinent
increases applicable to the contract. To the contrary, said
Defendant wilfully and without cause unilaterally altered
the scope of work provisions and sought to issue and did
issue wage schedules in direct contravention of its con-
tractual obligations.
26. That Defendant has failed, neglected and refused,
without just cause, to permit Plaintiff in continuance of
said agreement and that the Plaintiff has duly performed
all the conditions of the said contract on its part to be
performed so far as it was permitted so to do by the said
Defendant.
27. The Plaintiff is ready and willing and able to per-
form said agreement in accordance with the terms there-
of, including the wage schedules applicable to and refer-
enced in said Letter of Eligibility theretofore granted it.
28. That Plaintiff's damages, arising out of Defend-
ant’s breach of this agreement, including sums expended ~
by Plaintiff in its performance under the agreement prior
to cancellation thereof, counsel fees, and proposed profit,
together with interest and including sum deposited in the
amount of $25,000, in accordance with the terms and con-
ditions of its agreement, is in the amount of $450,000.
na reeyamtenepacneeenito a
12
(fol. 13] WHEREFORE, Plaintiff demands judgment in the
sum of $450,000, together with interest, costs, disburse-
ments and legal fees.
DAVID FROMSON,
Attorney for Plaintiff
Office & P.O, Address
Franklin National Bank
Building
600 Old Country Road
Garden City, New York
[fols. 14-22] ** *
13
(fol. 23]
EXHIBIT 8 TO PETITION
29 OCT 1958
Gentlemen:
1. Your bid dated September 30, 1958, in the amount of
$2,866,098, offering to construct through mortgage financ-
ing the housing projeci consisting of 177 units at Top-
sham Air Force Station, Maine (Invitation No. 19-603-
59-15, FHA Projects Nos. 022-81015-Air 12 and 022-
81016-Air-13) under Title IV of the Housing Amend-
ments of 1955 (Public Law 345, 84th Congress), as
amended, has been determined by the Department of the
Air Force (hereinafter referred to as the “Department” )
after consultation with the Federal Housing Commissioner
(hereinafter called the “Commissioner”’) to be the lowest
acceptable bid. This acceptance of your bid price of
$2,866,093 includes the construction and provision of the
following Additive Alternates: No. 1 Carports; No, 2
Garbage Disposal Units; No. 8 Gutters and Downspouts;
No. 4 Hardwood Floors; No. 5 Venetian Blinds; No. 6
Combination Storm and Screen Sash; No. 7 Outdoor
Clothes Dryers; No. 8 TV Antenna System; No. 9 Side-
walks; No, 10 Ceramic Tile; No. 11 Landscaping; and
No. 12 Landscaping. The above Additive Alternates were
contained in paragraph 10 of the Invitation For Bids, as
amended, and paragraph 1 of the Bid Form, and are in-
cluded in the plans and specifications. Issuance of this
Letter of Acceptability obligates you, at your expense and
within the condition of your bid security, to:
a. Complete in conformity with the requirements of the
Federal Housing Commissioner the corporate organization
ANTHONY GRACE & Sons INc.
RECEIVED
NOV 8 1958
\f0..24] of Topsham AFB Housing, Inc., and Topsham
AFB Housing No. Two, Inc., (hereinafter referred to as
the “Mortgagor-Builder”) in accordance with the laws of
the State of Delaware, with each having a paid-in capital
ne
—
14
stock of $1,000, cause them to be qualified to do business
in the State in which the housing project is to be located,
cause the mortgagor-builder to hold an immediate election
of officers with authority on behalf of the mortgagor-
builder to execute with the Department two leases of land
from the Department, to execute the Housing Contract
hereinafter referred to, and such other instruments as
may be required by the Commissioner or the mortgagee.
b. Immediately following such incorporation of the two
corporations and election of officers, cause the stockhalders
of the mortgagor-builder to execute a stock transfer and
escrow agreement for each of the corporations in a form
approved by the Commissioner.
ce. Complete the necessary arrangements with a mort-
gage lender acceptable to the Commissioner as a mort-
gagee for financing the total cost, including your profit, of
said housing project through the execution of mortgages
and mortgage notes for a period of tweny-five years and
bearing interests at four and one-quarter per centum per
annum, with the option of prepayment without penalty at
the end of fiteen years; cause the mortgagor-builder and
said mortgage lender to enter into a Building Loan Agree-
ment for each corporation, a specimen form of which is
attached to the Invitation For Bids; cause said mortgage
lender to apply to the Commissioner for mortgage insur-
ance for each corporation, and take all steps necessary to
cause the Commissioner to issue a Commitment for Insur-
ance to provide insurance during and after construction
of said housing project.
d. Cause the mortgagor-builder to execute in Topsham,
Maine, two leases, a form of which is attached to the
Invitation For Bids, with the appropriate officer of the
Department.
[fol. 25] e. Make arrangements for and obtain such
title insurance policies or other evidence of title, based
upon the surveys of the housing project sites and the
descriptions contained in the leases mentioned in the
preceding subparagraphs, as may be required by such
mortgagee and the Commissioner, or either of them. For
this purpose, you may obtain from the Contracting Officer
copies of the surveys made in connection with the Archi-
tect-Engineer contract.
a
15
f. Make all necessary arrangements with the Depart-
ment or otherwise for the utility services required and be
prepared at the closing (as defined in your bid) to furnish
evidence in the form of written contracts or commitments
that there will be made avaliable to you during the con-
struction period at the housing project sites such utility
services as will be adequate for construction.
g. Be prepared to pay or cause to be paid prior to or
at the closing: (1) to the Commissioner, the filing fee,
processing fee, commitment fee and initial premium for
mortgage insurance during the construction period; (2) to
the Contracting Officer, $60,500 representing the cost of
the Architect-Engineer services for the design of the
Housing Project, the inspection fee in the amount of
$44,704, and the sum of $2,000 as consideration for the
two leases; and (3) any other expenses incurred by the
mortgagor-builder and the bidder pursuant to the Invi-
tation For Bids and the documents thereto attached.
h. Be prepared at the closing to furnish a properly
executed performance and payment bond (FHA Form
2452C, Performance Bond-Dual Obligee, FHA Form
2452CP, Payment Bond-Dual Obligee) as required pur-
suant to Article XIII of the form of Housing Contract
attached to the Invitation For Bids.
i. Execute prior to or at the time of closing the Hous-
ing Contract and all other documents required to be exe-
cuted or delivered by you at such closing.
(fol. 26] j. Cause the mortgagor-builder and the mort-
gagee through their duly authorized representatives prior
to or at the time of closing to execute all documents re-
quired to be executed and delivered by them respectively
at the closing.
k. Furnish the Air Force representative with two (2)
photostatic copies of each of the FHA Commitments for
Insurance and the FHA Project Analyses as soon as pos-
sible after issuance thereof, and two copies of all addition-
al closing papers required by the Commissioner or said
mortgagee.
1. Furnish prior to the closing an approved and exe-
cuted Trade Payment Breakdown, FHA Form 2536, in-
cluding the signature thereon of the mortgagor-builder.
16
m. Acknowledge in writing receipt of this letter of ac-
ceptability and attach an estimated schedule showing dates
upon which you will have accomplished the several steps
required above.
n. Make application through the Contracting Officer,
Otis Air Force Base, Massachusetts, to the Secretary of
Labor for an appropriate wage determination, if neces-
sary, (on a Department of Labor Form DB-11 which will
be supplied upon request by the Contracting Officer) for
use in the construction of the project, and furnish a copy
of such wage determination to the Contracting Officer and
the Commissioner. Such wage determination will be used
by the Commissioner to increase or decrease the bid price
in the manner specified in your bid.
2. Failure to perform all obligations prior to the time
prescribed for closing will be just cause for cancelling all
commitments undertaken with you in connection with the
housing project and for the recovery under your bid se-
curity of liquidated damages in the sum of $25,000, to-
gether with actual dawages to the Department, such ac-
tual damages to be itemized and determined by the Con-
tracting Officer, whose decision will be reduced to writing
and furnished to you by mail or otherwise. Such decision
(fol. 27] shall be final and conclusive unless, within 30
days from the receipt thereof, you appeal in writing to the
head of the Department or his duly authorized representa-
tive, and his decision shall, unless determined by a court
of competent jurisdiction to have been fraudulent or
capricious or arbitrary, or so grossly erroneous as neces-
sarily to imply bad faith, or not supported by substantial
evidence, be final and conclusive. In connection with any
appeal under this paragraph you will be afforded an op-
portunity to be heard and to offer evidence in support of
your appeal.
3. All payments to the Contracting Officer shall be by
certified or cashier’s check made payable to the Treasurer
of the United States, and all payments to the Commis-
sioner shall be by certified or cashier’s check made payable
to the Commissioner of FHA, but separate checks shall be
made to each, respectively.
a '
4. This Letter of Acceptability commits the Department
to execute two leases substantially in the form attached to
the Invitation For Bids upon compliance by you with the
provisions of subparagraph “a” hereof ; and to enter into
negotiations with you for any utility services to be furn-
ished by the Department during the construction period.
5. You are required to furnish written proof satisfac-
tory to the Contracting Officer within 30 days of the date
of this Letter of Acceptability that you have a firm ar-
rangement (1) with an acceptable financial institution to
furnish the contstruction fin:.ncing evidenced by the filing
of an application for mortgage insurance with the Federal
Housing Insuring Office; and (2) a written commitment
by a qualified lender to purchase the mortgage as a long-
term lender, Your failure to furnish this proof within
the 30 days will be determined to be evidence that you are
unable to fulfill the terms of you bid and this Letter of
Acceptability and result in this Letter of Acceptability
being of no further effect, provided that the Contracting
Officer in writing may extend the date for furnishing the
(fol. 28] information required in (1) and (2) above, upon
your submission of written documented proof that the de-
lay was caused by conditions beyond your control.
6. You are required to be ready for the closing on or
before January 8, 1959, and your failure to do so will in-
dicate your inability to carry out the obligations and
terms of your bid and this Letter of Acceptability, pro-
vided that the Contracting Officer may extend the date of
closing in writing upon your submission of written docu-
mented proof that the delay was caused by conditions be-
yond your control.
Sincerely yours,
| GEORGE S. ROBINSON
Deputy Special Assistant for Installations
Anthony Grace & Sons, Inc,
151-45 6th Road
Whitestone
Queens, New York
{fols. 29-41] ** *
18
[fol, 42] EXHIBIT 7 TO PETITION
DEPARTMENT OF THE AIR FORCE
WASHINGTON
OFFICE OF THE SECRETARY
OCT 1 1959
Gentlemen:
1. In your letter to the Department of the Air Force
dated July 2, 1959 you have indicated an unwillingness to
set a closing date for your contract to build a 177 unit
family housing project at Topsham Air Force Station,
Maine. Paragraph 6 of the Letter of Acceptability dated
October 29, 1958 required you to be ready for closing on
or before 8 January 1959. The Department, at your re-
quest, has repeatedly extended this closing date in an
effort to have resolved the questions raised by you pertain-
ing to the application of certain wage rates to the con-
struction of the project. On 26 June 1959 you were in-
formed by letter as to the position of the Department and
requested to state your position within 10 days of the date
of the letter. Your reply of July 2, 1959 indicating an un-
willingness to set a closing date constitutes a failure on
your part to perform your obligations under your bid and
under the letter of acceptability.
2. You have alleged in your letter that a failure of the
Department to act promptly in this matter has caused the
long delay in resolving the questions of applicable wage
rates. In this connection, your attention is directed to the
fact that your request for a determination of the position
of the Air Force was not made until 29 May 1959, over
four months subsequent to the date when you were re-
quired to be ready for closing.
{fol.48] 3. Accordingly, pursuant to paragraph 2 of
the letter of acceptability, the Department hereby cancels
all commitments undertaken with you in connection with
Co ON IRE,
19
the housing project, reserving all its rights with respect
to the recovery of damages,
Sincerely,
GEORGE S, ROBINSON
Deputy Special Assistant for Installation
Anthony Grace & Sons, Ince,
151-45 6th Road
Whitestone
Queens, New York
Sa
| CC: S. Locurto
| I. Monforte
| S. Pollack
File
20
[fol. 44]
IN THE UNITED STATES COURT OF CLAIMS
No. 133-61
[Title Omitted]
DEFENDANT’S ANSWER—Filed July 19, 1961
Defendant, in answer to the petition filed herein, ad-
mits, denies, and alleges as follows:
1. Denies the allegations of paragraph 1 for lack of in-
formation znd knowledge sufficient to form a belief as to
the truth thereof.
2. Alleges that the allegations of paragraph 2 are ones
of law not requiring answer.
3. Admits the allegations contained in paragraph 3.
4, Admits the allegations contained in paragraph 4 ex-
cept as to the date the Air Force transmitted certain
documents and the Invitation for bids to the plaintiff,
which defendant denies for lack of information and
[fol. 45] knowledge of defendant’s attorneys sufficient to
form a belief as to the truth thereof; avers that the In-
vitation was dated August 22, 1958.
5. Admits that the paragraphs quoted, insofar as they
are correctly quoted, are part of the aforesaid Invitation
for Bids but alleges that they are not quoted in sequence,
that the paragraphs quoted do not constitute all of the
pertinent portions thereof, that reference to the whole
instrument and the documents annexed thereto is neces-
sary for an understanding thereof, and that the document
speaks for itself.
6. Admits the allegations contained in paragraph 6.
[In only one place is any reference made to contracting
officer, i.e., paragraph 4 quoted by plaintiff at p. 3.]
——————
21
7. Admits that the documents listed by plaintiff in
paragraph 7, among others, accompanied the Invitation
for Bids; insofar as said quotations by plaintiff in the ex-
hibits attached to its petition conform to the Bid docu-
ments, admits them and insofar as they do not conform
to the Bid documents, denies them; alleges further that
said documents speak for themselves.
8. Admits the allegations contained in paragraph 8.
9. Admits the allegations contained in the first and
third sentences of paragraph 9; admits the allegations of
the second sentence down to and including the words
“Letter of Acceptability” but denies that there emerged
a contract between plaintiff and defendant as a result
thereof; answering further, defendant avers that the
[fol. 46] conditions enunciated in the Letter of Accepta-
bility constituted conditions precedent to the housing con-
tract, that plaintiff never agreed to or effected a closing
of said contract and that in accordance with paragraph 6
thereof the Letter of Acceptability was withdrawn; de-
fendant further alleges that the failure to effect a closing
of the contract was due to plaintiff’s own fault.
10. Admits that the paragraphs quoted from the Letter
of Acceptability in paragraph 10 appear in said Letter
and insofar as said quotations conform to the aforemen-
tioned document admits them and insofar as they do not
conform to the aforementioned document, denies them ;
alleges further that said Letter of Acceptability speaks
for itself,
11. Admits that plaintiff entered upon performance of
the conditions precedent to the contract and that plain-
tiff applied for a wage determination but avers that
plaintiff refused to accept the applicable wage determina-
tions issued by the Department of Labor.
12. Denies the allegations in paragraph 12, except ad-
mits that the original closing date of January 8, 1959,
was postponed and extended on several occasions but avers
that such postponements and extensions were because of
plaintiff’s refusal to accept the appropriate wage deter-
minations furnished and because FHA determined that
application of the interpretation of the wage determina-
tions by plaintiff would result in a mortgage in excess of
the statutory limit set forth in Section 803(b) (3) (B)
of the National Housing Act (12 U.S.C. 1748b).
(fol. 47} 18. Denies the allegations contained in para-
graph 13, except admits that the wage revisions were not
consummated because of plaintiff's repeated refusals to
accept applicable wage determinations issued by the De-
partment of Labor as interpreted by FHA and the De-
partment of the Air Force; by way of further answer
defendant avers that plaintiff delayed submitting neces-
sary information to process the application for mortgage
insurance and required fees,
14, Admits that the plaintiff made application for ap-
propriate wage determinations and that, on January 28,
1959, plaintiff received two new schedules of ny rates;
denies the remaining allegations on the ground that they
constitute conclusions of law.
15. Denies the allegations of the first sentence of para-
graph 15; avers that the Government attorneys lack
sufficient information and knowledge sufficient to form
a belief as to the truth of the allegations of the second
sentence and they are therefore denied,
16. Admits the allegations contained in paragraph 16
except avers that the date of the FHA letter referred to
in the second sentence was March 18, 1959, not May 18,
1959,
17. Admits that by telegram dated March 28, 1959, the
Director of the Federal Housing Administration requested
that plaintiff submit an amended application suk louse
and advised that the entire situation would be reviewed;
avers that defendant's attorneys lack sufficient informa-
tion and knowledge sufficient to form a belief as to
whether said application and figures were submitted,
[fol. 48} 18, Admits that conferences were held with of-
fficials of the Department of Air Force and Labor but
denies the remaining allegations for lack of information
and knowledge of counsel for the defendant,
19, Admits that the original closing date of January
8, 1959, had been extended from time to time but, ex-
cept as so admitted, denies all remaining allegations and
specifically denies that the referenced letter of July 2,
1959, indicated a desire and willingness to set a firm
closing date,
—
20, Denies the allegations in paragraph 20; answering
further, defendant alleges that defendant was willing at
all times pertinent hereto to issue a revision in the con-
tract price based on the applicable wage determinations
but that plaintiff refused to accept the applicable wage
increases offered by the FHA in accordance with law,
21. Denies the allegations contained in paragraph 21
and, answering further, alleges that on June 26, 1959,
the Department of the Air Force advised plaintiff ‘that it
did not concur in plaintiff's position regarding justifica-
tion for an increase in the contract price and in the same
letter asked plaintiff for advice as to whether it intended
to effect a closing,
22. Admits the allegations of paragraph 22 but alleges
further that plaintiff failed to perform its obligations un-
der the Letter of Acceptability by refusing to close the
contract, causing the defendant, a year after the opening
of bids, to withdraw said Letter of Acceptability,
23. Denies the allegations contained in paragraph 23.
(fol. 49] 24, Admits the allegations contained in para-
graph 24,
25. Denies the allegations of paragraph 25,
26. Denies the allegations of paragraph 26.
27. Denies the allegations of paragraph 27.
28. Denies that plaintiff is entitled to the amount
sought or to any other amount or to any other relief
and denies that defendant breached its agreement or is
indebted to plaintiff for the sum claimed or for any other
sum, Defendant affirmatively alleges that the retention
it of the $25,000.00 was in accord with the provisions
the Letter of Acceptability and constituted reasonable
liquidated damages,
29. Denies each and every allegation not hereinbefore
expressly admitted, denied, or qualified,
AFFIRMATIVE DEFENSE
30. Defendant alleges that plaintiff's failure to file a
timely appeal after the withdrawal by the Air Force of
the Letter of Acceptability constitutes a failure to ex-
haust avaliable administrative remedies and, further,
that plaintiff has also failed to avail itself of adminis-
24
trative remedies dealing with the problem of minimum
wage rates in that it failed to seek withdrawal of its bid
and release, as provided for, when escalation raised the
per unit price of Capehart housing above the statutory
maximum,
[fol. 50] WHEREFORE, defendant prays for dismissal] of
the petition.
WILLIAM H. ORRICK, JR.
Assistant Attorney General
Civil Division
DAVID ORLIKOFF
Attorney, Civil Division
Department of Justice
Mary J. TURNER
Attorney, Of Counsel
Department of Justice
25
(fol. 51]
IN THE UNITED STATES COURT OF CLAIMS
No, 133-61
* * * *
DEFENDANT’S MOTION FoR SUMMARY JUDGMENT—
Filed October 18, 1963
[Omitted in printing]
(fol. 51-A]
EXHIBIT A TO DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT (EXCERPTS)
ARMED SERVICES BOARD OF
CONTRACT APPEALS
WASHINGTON, D. C.
ASBCA No. 6167
Appeal of—
Anthony Grace & Sons, Ine.
Under Invitation No. 19-603-59- 15,
dated 22 August 1958, and
Letter of Acceptability,
dated 29 October 1958
APPEARANCES FOR THE GOVERNMENT:
BRIGADIER GENERAL A, W. RigsBy, USAF
Chief Trial Attorney
WILBUR J. SMOLKA, Esq.
Trial Attorney
APPEARANCES FOR THE APPELLANT:
SALVATORE A. LocurTo, Esq.
ON MOTION TO DISMISS
The instant contract, which became operative upon
dispatch by the Government of the Letter of Acceptability
described above, related to the construction of 177 units
of Capehart Family Housing at Topsham Air Force Sta-
tion, Maine.
In the covering letter by which the cited Invitation was
forwarded appellant was notified that “The following
listed documents are applicable to this project and are
furnished for your information and use: (Bidders’ Check
List is also enclosed)
“a, INVITATION FOR BIDS (IFB) 19-603-59-15
ae . * e
“eo, Letter of Acceptability
oe * a e
“i, Department of Labor Wage Determination No.
S 23,731
* * * #)
The opening portion of the Invitation also notified ap-
pellant that:
“1. a. The Department of the Air Force (herein-
after called the ‘Department’) issues an Invitation
[fol. 51-B] For Bids and receives bids,
“bh, When bids are received and after consultation
with the Federal Housing Commissioner (herein-
after called the ‘Commissioner’), the Department
determines the person, partnership, firm or corpora-
tion, qualified by experience and financial responsi-
bility, who has submitted the lowest acceptable bid.
“ce, The Department issues to that bidder (herein-
after called the ‘eligible builder’) a Letter of Accept-
ability. That letter requires the eligible builder,
among other things, to take four actions: first, to
form 2 new corporation(s) (hereinafter called the
‘mortgagor-builder’) ; second, to arrange financing
for the cost of the total project, including profit, by
Building Loan Agreements between the mortgagor
builder and mortgage lenders (hereinafter called the
‘mortgagees’) ; third, to cause each mortgagee to ob-
ott
tain the Commissioner’s Commitment for Insurance;
and fourth, to execute a three-party Housing Con-
tract which defines the rights and obligations of the
Department, the eligible builder and the mortgagor-
builders. The Letter of Acceptability also requires
the Department to execute a lease of a project site
to each mortgagor-builder,
“d. Once the foregoing arrangements are made,
the parties in interest effect a ‘closing’ in which the
relationships of the parties are definitely established
by the delivery of all legal instruments. Among other
things at the closing, each mortgagor-builder delivers
to its mortgagee a note and mortgage with an amorti-
zation period of 25 years (with the option of pre-pay-
ment without premium at the end of 15 years) and
bearing interest at not to exceed four and one quar-
ter (44) per centum per annum, and the eligible
builder deposits in escrow with the mortgagees the
capital stock of the newly formed mortgagor-builder
corporations for ultimate delivery to the Department,
in accordance with the escrow agreements,
. . a” *
27
In part pertinent hereto the Invitation went on to de-
fine appellant’s undertaking in the following language: .
“2. Sealed bids (in triplicate) for the construction
through FHA insured mortgage financing of the
above described total housing project, including the
furnishing of all necessary labor, equipment and
materials and the performing of all work, services
and arrangements, in strict accordance with the
terms of a Letter of Acceptability and a Housing
Contract, specimen forms of each being attached
hereto, will be received at Installation Engineers
Office, attention: Topsham Capehart ‘Monitor, Top-
[fol. 51-C] sham AFS, Maine until 2:00 P.M EST on 80
September 1958. Riis
. oJ eo a
“4. The bidder should carefully examine the pro-
visions of the form of Housing Contract attached
a
hereto, including the Drawings and Specifications
made a part thereof; visit the site of the housing
projects; and fully inform himseif as to all conditions
and matters which can in any manner affect the
financing of the construction and the constructing
of the housing projects or their cost. Should the
bidder find discrepancies in, or omissions from, such
Drawings and Specifications or other documents at-
tached hereto, or should he be in doubt as to their
meaning, he should at once notify the Contracting
Officer, Otis Air Force Base, Massachusetts, and ob-
tain clarification prior to submitting a bid. Infor-
mation given will be transmitted to all known inter-
ested bidders.
“5, Under the provisions of Title IV of the Hous-
ing Amendments of 1955, as amended, the total prin-
ciple [sic] amount of the mortgages is limited, among
other things to the amount of the bid of the eligible
builder. However, the Davis Bacon Act and Section
212(a) of the National Housing Act as amended
require that wages paid to laborers and mechanics
be the prevailing wage as determined by the Secre-
tary of Labor not more than ninety (90) days prior
to the commencement of construction. Since more
than ninety (90) days may elapse from the date of
this Invitation For Bids to the commencement of
construction, the bids called for by this Invitation For
Bids will iaclude a provision for adjustment of the
dollar amount therein specified to reflect any differ-
ence between the tentative minimum wage schedule
attached hereto and the applicable minimum wage
schedule as finally determined by the Secretary of
Labor. Any such adjustment will be in an amount
determined by the Commissioner to reflect such dif-
ferences, and the amount of the lowest acceptable bid
and the FHA estimated total replacement cost of the
projects will be amended in the amount so determined
by the Commissioner; except that, if such an adjust-
ment would increase the amount of the bid above the
amount of any other statutory maximum applicable
to the insurable mortgages, the eligible builder will
—_
29
have the option of reducing his bid to such statutory
maximum or of withdrawing his bid.
* * * *
“8. Each bidder is required to submit with his bid
a certified check in the amount of $25,000, payable
(fol. 51-D] to the Treasurer of the United States, to
insure that if he is the lowest acceptable bidder for
the total of 177 family housing units he will perform
the necessary preliminary steps and effect a closing
_ with FHA within the time prescribed in the Letter
of Acceptwhility, including the furnishing of an
acceptable performance and payment bond. In the
event the lowest acceptable bidder fails to effect a
closing with FHA within the time prescribed, his
deposit will be forfeited and become the property of
the Government as damages unless the Department
finds that he has made every effort to effect such
closing and extends the time to effect such closing.
If the lowest acceptable bidder effects a timely clos-
ing with the FHA the amount of his deposit wi!! be
refunded to him 24 hours after the initial closing
with FHA. The deposits of unsuccessful bidders will
be returned to them not later than 60 days after the
opening of the bids. Each prospective bidder is ad-
vised that the failure to submit such certified check
with his bid will render his bid defective and will
be cause for its rejection,
“a. “Timely Closing’ as referred to in this para-
graph of the Invitation For Bids and closing period
as referred to elsewhere in these forms is constured
to be a period of approximately 60 days from the
date of opening of bids.
* * + *
“24. Bidders are further advised that the Housing
Contract will also be subject to certain other statu-
tory provisions with respect to labor and other mat-
ters as shown in the specimen form of Housing Con-
tract.
. .
The cited Letter of Acceptability, which presumably
conformed to the specimen letter attached to the Invita-
tion and which notified appellant that its bid had been
accepted, contained the following stipulation:
“2 Failure to perform all obligations prior to the
time prescribed for closing will be just cause for
cancelling all commitments undertaken with you in
connection with the housing project and for the
recovery under your bid security of liquidated dam-
ages in the sum of $25,000, together with actual
damages to the Department, such actual damages to
be itemized and determined by the Contracting Offi-
cer, whose decision will be reduced to writing and
furnished to you by mail or otherwise. Such decision
shall be final and conclusive unless, within 80 days
from the receipt thereof, you appeal in writing to
the head of the Department or his duly authorized
representative, and his decision shall, unless deter-
mined by a court of competent jurisdiction to have
(fol. 51-E] been fraudulent or capricious or arbitrary,
or so grossly erroneous as necessarily to imply bad
faith, or not supported by substantial evidence, be
final and conclusive. In connection with any appeal
under this paragraph you will be afforded an oppor-
tunity to be heard and to offer evidence in support
of your appeal.”
As lowest acceptable bidder under the Invitation appel-
lant had of course posted a bid deposit with the Govern-
ment in the sum of $25,000.00 as required. Following
receipt of the Letter of Acceptability a dispute arose
between the parties which, to the limited extent revealed
in the arguments made at the hearing of this motion,
exclusively concerned itself with the application and effect
of certain wage determinations rendered by the Secretary
of Labor. As a result of the disagreement “the closing”,
hereinbefore mentioned and stipulated originally to take
place on or before 8 January 1959, was postponed until a
later date. Neither passage of time nor ensuing discus-
sions served to smooth the way to unanimity of opinion
with the result that by letter dated 1 October 1959 the
Government advised appellant as follows:
eames
$1
“Gentlemen :
“1. In your letter to the Department of the Air Force
dated July 2, 1959 you have indicated an unwilling-
ness to set a closing date for your contract to build
177 unit family housing project at Topsham Air
Force Station, Maine. Paragraph 6 of the Letter of
Acceptability dated October 29, 1958 required you
to be ready for-closing on or before 8 January 1959.
The Department, at your request, has repeatedly
extended this closing date in an effort to have re-
solved the questions raised by you pertaining to the
application of certain wage rates to the construction
of the project. On 26 June 1959 you were informed
by letter as to the position of the Department and
requested to state your position within 10 days of the
date of the letter. Your reply of July 2, 1959 indi-
cating an unwillingness to set a closing date consti-
tutes a failure on your part to perform your obliga-
be under your bid and under the letter of accepta-
ty.
“2. You have alleged in your letter that a failure of
the Department to act promptly in this matter has
caused the long delay in resolving the questions of ap-
plicable wage rates. In this connection, your atten-
tion is directed to the fact that your request for a
determination of the position of the Air Force was
not made until 29 May 1959, over four months sub-
sequent to the date when you were required to be
ready for closing.
(fol. 51-F] “8. Accordingly, pursuant to paragraph 2 of
the letter of acceptability, the Department hereby
cancels all commitments unc urtaken with you in con-
nection with the housing project, reserving all its
rights with request to the recovery of damages.”
The above letter of 1 October 1959 was signed by The
Deputy Special Assistant For Installations, Office of the
Secretary of the Air Force, the same official who in keep-
ing with normal practice previously signed the Letter of
Acceptability by which appellant’s low bid was accepted
by the Government.
Under date of 7 October 1959 appellant, through coun-
sel, addressed that official in a letter which read:
[ fol.
“Dear Sir:
“Receipt is hereby acknowledged of your letter
dated October Ist, 1959, wherein you have advised
me and my client, Anthony Grace & Sous, Inc., that
the Department of the Air Force has cancelled its
committment [sic] in connection with the above re-
ferred to Housing Projects.
“My client has never indicated an unwillingness
to set a closing date, as alleged in your letter, but
rather has made all possible efforts to cooporate with
your Department.
“An examination of your files will indicate that
there is correspondence dated as early as November,
1958, countless trips to Washington and Maine, and
many conferences with the FHA Bangor, Maine, De-
partment of Labor, Washington, D. C., and the offices
of Lt, Col, Wayne R. Pipher and Col, Goddard.
“In addition thereto the necessary Delaware corpo-
rations were organized and the certificates filed in
Delaware on January 12th, 1959, and the same quali-
fied in Maine on March 10th, 1959. It was the fail-
ure to your office to apply the Wage Determinations,
as issued by the Department of Labor prior to clos-
ing that gave rise to the existing problems. In ad-
dition thereto, a notice of cancellation was not sent
out by the Air Force until my letter dated September
22nd, 1959, inquiring as to the status of the subject
Housing Project, was received by your office.
“Throughtout all this time you have held my
client’s bid check in the sum of $25,000.00, and I am
therefore requesting that the bid check be returned
to my client, Anthony Grace & Sons, Inc., immediate-
ly upon receipt of this letter.
51-G] “I am also advising you that my client,
Anthony Grace & Sons, Inc., is reserving all of its
rights with respect to recovery of damages due to the
failure of the Department of the Air Force to com-
ply with all of the bid instructions and regulations
thereby creating the situation that exists.”
In response the Deputy Special Assistant for Installa-
tions advised appellant’s counsel as follows:
“19 October 1959
“Dear Mr. Locurto:
“I have your letter of 7 October 1959, requesting
the return of the $25,000 check deposited by your
client, Anthony Grace & Sons, Inc., as security for
its bid on the Topsham project. Since the | epart-
ment’s cancellation of its commitments was compelled
by your client’s repeated refusals to perform its
obligations under its bid and the Letter of Accepta-
bility, with the result that it was necessary to revise
the plans and rebid the project, the return of the
bid security would be manifestly improper. Your
request must therefore be denied.”
The most the Government is able to say with regard to
appellant’s receipt of the Government’s letter of 19
October 1959 is that it was released on 20 October 1959,
for dispatch to U. S. Post Office channels and ultimate de-
livery to the addressee, It would appear however that
for some unknown reason the letter never reached the
hands of appellant’s counsel. Prompted by a concern that
his letter of 7 October 1959 was still unanswered appel-
lant’s counsel made inquiry by telephone on 4 December
1959; a copy of the letter of 19 October 1959 was furn-
ished him by mail on 8 December 1959. Shortly thereafter
the following notice of appeal was filed:
“Dear Mr. Douglas:
“As counsel for Anthony Grace & Sons, Ine., I
have been requested to appeal the decision of Mr.
George S. Robinson dated October Ist, 1959,
“On October 7th, 1959, I formally appealed the de-
cision in Robinson’s letter dated October Ist, 1959
: and in my reply requested the return of my client’s
: bid deposit check and also set forth facts in con-
tradiction to Mr. Robinson’s allegations. Hearing
nothing further, on December 4th, 1959, I called the
office of the Department of the Air Force, and spoke
with Mr, Samuel Hanenberg concerning a reply to my
Ee
appeal dated October 7th, 1959. I thereafter, on
December 9th, 1959, received a letter from Mr. Han-
(fol. 51-H] enberg wherein he furnished me with a copy
of a reply sent to my office by Mr. Robinson on Oc-
tober 19th, 1959. This letter was never received by
my office.
“You are hereby notified of my intention to appeal
the decision of Mr. Robinson to withdraw and cancel
the Letter of Acceptability dated October 29th, 1958
and his refusal to return the $25,000.00 bid deposit.
I am of the opinion that the facts and circum-
stances as set forth in my letter forwarded to Mr.
Robinson on October 7th, 1959, clearly sets forth that
the delays caused by the Government Agencies in-
volved made it impossible for the builder to comply
with the terms of the Letter of Acceptability.
“In view of the aforementioned, the Letter of Ac-
ceptability should have been terminated for the con-
venience of the Government and the $25,000.00 bid
deposit returned to Anthony Grace & Sons, Inc.
“T request that this Notice of Appeal, as previously
set forth in my letter dated October 7th, 1959 be
processed in accordance with the Rules of the Armed
Services Board of Contract Appeals. Upon receipt
of Notice of Docketing I will file a formal Bill of
Complaint.
“T sincerely request that this appeal be expedited
= order that a hearing be held at the earliest possible
ate.”
After the foregoing notice was forwarded appellant also
received a letter from the procurement contracting con-
tracting officer, who was stationed at Otis Air Force
Base, Massachusetts, the installation responsible for the
issuance of the Invitation cited above. The letter, dated
22 December 1959, was as follows:
“Gentlemen:
“Reference is made to letter dated 1 October 1959 ad-
dressed to you and letter addressed to Salvatore A.
Locurto, Esq., dated 1 October 1959, both signed by
Mr. George S. Robinson, Deputy Special Assistant
for Installations and both in regard to cancellation
———
35
of all commitments undertaken with you in connec-
tion with the Capehart Housing Project at Topsham
Air Force Station, Maine. Mr. Robinson was acting
in my behalf and I agree with the action taken by
him in this matter.”
The Government has moved that the appeal be dismissed
upon the ground that there is no timely appeal before the
Board. It argues that the requirements of a decision and
an appeal were exclusively fulfilled by the Government’s
letter of 1 October 1959 and appellant’s 16 December
(fol. 51-I] 1959 appeal notice respectively; and that since
the interval between receipt of the former and filing of
the latter is in excess of thirty days no jurisdiction at-
taches.
Although it raises other grounds, appellant argues for
denial of the motion principally on the ground that the
only correspondence which constituted an appealable de-
cision was the letter dated 19 October 1959; and inas-
much as that letter was not received until 8 December
1959 appeallant’s appeal notice of 16 December 1959
was more than adequate to vest the Board vith juris-
diction. An examination of appellant’s letter of 16 De-
cember 1959 reveals that the argument appellant now
advances in connection with the motion represents a com-
plete departure from the position taken when the letter
was written. On 16 December 1959 appellant unequivocal-
ly labelled the Government’s letter of 1 October 1959 as
the “decision” and the reply thereto of 7 October 1959 as
“my appeal”. For reasons hereinafter set forth we are
persuaded that appellant’s characterization was correct
in the instance of the first letter and incorrect with re-
spect to the second.
Appellant likewise suggests that the Deputy Special
Assistant for Installations who signed the Government’s
1 October 1959 letter was not the contracting officer for
the purposes of a decision rendered pursuant to the “dis-
putes clause” of the Letter of Acceptability; and in this
regard points to the letter written to appellant by the
contracting officer, Otis Air Force Base, under date of 22
December 1959. If we were to accept appellant’s sug-
gestion it would be necessary to ignore undisputed evi-
dence that the Deputy Special Assistant for Installations
was the Government’s representative in all dealings of
legal consequence between the parties. The Otis Air Force
Base contracting officer was at all times a virtual stranger
to appellant. On the other hand, the Deputy Special
Assistant for Installations signed the Invitation upon
which appellant bid; signed the Letter of Acceptability,
the letter of 1 October 1959, and the letter of 19 October
1959 which appellant now claims forms the basis of a
timely appeal; and at all times headed the office with
which appellant dealt in connection with the contract.
Appellant nowhere alleges that the presence of the signa-
ture of the Deputy Special Assistant for Installations on
the 1 October 1957 letter misled appellant with regard to
its right of appeal. Indeed the record shows quite the con-
trary. As indicated by argument upon the motion, appel-
lant did not question the Government’s 1 October 1959
letter on the ground that its signatory was the Deputy
Special Assistant for Installation but rather because in
appellant’s view “issues” were not reached until appel-
lant received the 19 October 1959 letter wherein the
Government refused to return appellant’s bid deposit.
As has just been intimated, appellant also implies that
the Government’s 1 October 1959 letter was not a final
decision because “an actual issue” between the parties
had not yet been reached. Even a hurried reading of the
letter demonstrates that contention is worthy of no con-
sideration. What could have more finality than a letter
(fol. 51-J] which told appellant insofar as the instant
contract is concerned that “the Department hereby cancels
all commitments undertaken with you in connection with
the housing project * * *”?
The parties are in complete agreement that it was and
is their mutual interpretation that in the event a timely
appeal is taken thereunder the “disputes paragraph” of
the Letter of Acceptability confers jurisdiction on the
Board to review a decision relating to cancellation of
commitments, withholding of bid security, and itemization
and determination of actual damages. The Government’s
letter of 1 October 1959 is such a decision. That appellant
so understood it is established by the contents of the open-
a——,
37
ing paragraph of the letter appellant wrote on 7 October
1959. The latter however falls short of meeting the re-
quirements of a notice of appeal. Although it mentions
that appellant “is reserving all of its rights with respect
to recovery of damages due to the failure of the Depart-
ment of the Air Force to comply with all of the bid in-
structions and regulations thereby creating the situation
that exists”, in the circumstances here present it would
be unjust to read into that language a declaration of a
then present intent on appellant’s part to invoke the right
of appeal. Appeal of Reading Clothing Manufacturing
Co., ASBCA No, 3912, 57-1 BCA 1290, 7 May 1957. That
the foregoing conclusion is the correct or.e and that appel-
lant itself did not on 7 October 1959 consider that it was
declaring such an intent is evidenced by appellant’s ac-
count of the reason why it made a telephonic inquiry on
4 December 1959. As stated by appellant during argu-
ment on the instant motion, the sole purpose of the 4 De-
cember telephone call was to obtain information as to why
the Government had not furnished “an answer” to appel-
lant’s 7 October letter. If appellant on 4 December 1959
(or previously) considered its 7 October 1959 letter to be
a notice upon the Government that an appeal would be
forthcoming, no inquiry into the matter of “an answer”
would have been instituted because no reply could have
reasonably been expected.
With respect to the argument that 8 December 1959 is
the critical date exclusively determinative of appellant’s
right to be heard on the merits of the controversy (first
raised in oral argument and written memorandum sub-
mitted in connection with the instant appeal) our here-
inbefore expressed conclusion that the Government’s 1
October 1959 letter was an appealable, final decision re-
quires that we go no further than decide whether the
Government, during the thirty day period following the
letter’s receipt by appellant, agreed to reconsider the de-
cision therein contained. No such agreement is asserted
and we find none in the record before us. Since there is
no evidence that the Government ever assented to recon-
sideration of the 1 October 1957 decision, appellant’s
appeal to be timely should have been filed within thirty
Nees.»
a
38
days of 7 October 1957, the date which the record shows
beyond peradventure of a doubt to be the date on which
appellant was in receipt of the decision.
{fol.51-K] In accordance with the foregoing the Gov-
ernment’s motion is granted and the appeal is dismissed.
Dated 29 June 1960.
/s/ Henry F. Mlotkowski,
HENRY F, MLOTKOWSKI,
Lt. Colonel, USAF
Member of Division No. 3,
Air Force Contract Appeals Panel
I Concur
/s/ George W. Crawford
GEORGE W. CRAWFORD
Chairman of the Air Force Contract
Appeals Panel 2nd Member of
Division No. 3
DONALD W. NOFRI,
Lt. Colonel, USAF
Member of Division No. 3,
Air Force Contract Appeals Panel,
did not participate in this decision.
——
I certify that the foregoing is a true copy of the find-
ings of fact, decision and views of the Air Force Con-
tract Appeals Panel of the Armed Services Board of Con-
tract Appeals in ASBCA No. 6167, appeal of Anthony
Grace & Sons, Inc., under Invitation No. 19-603-59-15,
dated 22 August 1958 and Letter of Acceptability, dated
29 October 1958. I further certify that there has been
filed with the Recorder a statement by the Chairmen of
the respective Panels of the Board that they have re-
viewed on behalf of their respective Services the above-
captioned decision of the Air Force Contract Appeals
Panel and that in their opinion further, formal and ex-
clusive decision by the three Panel Chairmen is not re-
Dated
GEoRGE L. HAWKES, Recorder
Armed Services Board of
Contract Appeals
(fol. 51-L]
October 7th, 1959
Mr. George S. Robinson, Deputy Special
Assistant for Installations
Department of the Air Force
Temporary Building 8
89th Street and Newark Street N W
Washington, D. C.
RE: Topsham Air Force Station
FHA Project Nos, 022-8105
and 022-8106
Dear Sir:
Receipt is hereby acknowledged of your letter datec
October 1st, 1959, wherein you have advised me and my
client, Anthony Grace & Sons, Inc., that the Department
of the Air Force has cancelled its committment in con-
nection with the above referred to Housing Projects.
My client has never indicated an unwillingness to set a
closing date, as alleged in your letter, but rather has made
all possible efforts to cooperate with your Department.
An examination of your files will indicate that there is
correspondence dated as early as November, 1958, count-
less trips to Washington and Maine, and many confer-
ences with the FHA Bangor, Maine, Department of Labor,
Washington, D.C., and the offices of Lt. Col. Wayne R.
Pipher and Col. Goddard.
In addition thereto the necessary Delaware corporations
were organized and the certificates filed in Delaware on
January 12th, 1959, and the same qualified in Maine on
March 10th, 1959. It was the failure to your office to
apply the Wage Determinations, as issued by the Depart-
ment of Labor prior to closing that gave rise to the exist-
ing problems. In addition thereto, a notice of cancella-
tion was not sent out by the Air Force until my letter
dated September 22nd, 1959, inquiring as to the status of
the subject Housing Project, was received by your office.
41
(fol. 61-M]
Mr, George S, Robinson October 7th, 1959
Throughout all this time you have held my client’s bid
eck in the sum of $25,000.00, and I am therefore re-
questing that the bid check be returned to my client,
Pig J Grace & Sons, Inc., immediately upon receipt of
this letter.
I am also advising you that my client, Anthony Grace
& Sons, Inc., is reserving all of its rights with respect to
recovery of damages due to the failure of the Depart-
ment of the Air Force to comply with all of the bid in-
structions and regulations thereby creating the situation
that exists.
Very truly yours,
SALVATORE A, LOcURTO
S
A: VT
L
ce: Lt. Col. Anderson, Maj. Gen. M. R. Tidwell, Jr.
(fol. 51-N]
DEPARTMENT OF THE AIR FORCE
WASHINGTON
OFFICE OF THE SECRETARY
19 October 1959
Dear Mr. Locurto:
I have your letter of 7 October 1959, requesting the
return of the $25,000 check deposited by your client,
Anthony Grace & Sons, Inc., as security for its bid on
the Topsham project. Since the Department’s can: Jla-
tion of its commitments was compelled by your client’s
repeated refusals to perform its obligations under its bid
and the Letter of Acceptability, with the result that it
was necessary to revise the plans and rebid the project,
the return of the bid security would be manifestly im-
proper. Your request must therefore be denied.
Sincerely yours,
/s/ George S. Robinson
GEORGE S. ROBINSON
Deputy Special Assistant for Instailations
Mr. Salavatore A. Locurto
391 East 149th Street
Bronx 55, New York
ec: Major General M, R. Tidwell, Jr.
Lt. Colonel J. B. Anderson
ih ape Lalani oee home ee a
EE NN TN et RE Pk RSS ATER
(fol. 51-0)
DEPARTMENT OF THE AIR FORCE
WASHINGTON
OFFICE OF THE SECRETARY
7 Dec 1959
Dear Mr. Locurto:
During our telephone conversation on December 4, 1959,
you stated that the Air Force had not replied to your
letter of October 7, 1959, with respect to the Topsham
Air Force Station Capehart Project. Inclosed for your
information is a copy of a letter to you dated October 19,
1959, from Mr. George §, Robinson, Deputy Special As-
sistant for Installations, Office of the Secretary of the Air
Force.
Sincerely yours,
/8/ Samuel Hanenberg
SAMUEL HANENBERG
Assistant General Counsel]
Incl.
Mr. Salvatore A, Locurto
°°] East 149th Street
Bronx 55, New York
44
(fol. 51-P]
December 16th, 1959
Honorable James H. Douglas
Secretary of the Air Force
Washington 25, D.C.
RE: Topsham Air Force Station,
Maine, 177 Unit Capehart
Housing Project
Dear Mr. Douglas:
As counsel for Anthony Grace & Sons, Inc., I have
been requested to appeal the decision of Mr. George Ss.
Robinson dated October Ist, 1959.
On October 7th, 1959, I formally appealed the decision
in Robinson’s letter dated October 1st, 1959 and in my
reply requested the return of my client’s bid deposit
check and also set forth facts in contradiction to Mr.
Robinson’s allegations. Hearing nothing further, on De-
cember 4th, 1959, I cailed the office of the Department of
the Air Force, and spoke with Mr. Samuel Hanenberg
concerning a reply to my appeal dated October 7th, 1959.
I thereafter, on December 9th, 1959, received a letter
from Mr. Hanenberg wherein he furnished me with a
copy of a reply sent to my office by Mr. Robinson on
} ~ ao 19th, 1959. This letter was never received by my
office.
You are hereby notified of my intention to appeal the
decision of Mr. Robinson to withdraw and cance] the
Letter of Acceptability dated October 29th, 1958 and his
refusal to return the $25,000.00 bid deposit. I am of the
opinion that the facts and circumstances as set forth in
my letter forwarded to Mr. Robinson on October 7th,
1959, clearly sets forth that the delays caused by the
Government Agencies involved made it impossible for the
builder to comply with the terms of the Letter of Ac-
ceptability.
a ——————
45
[fol. 51-Q]
Honorable James H. Douglas December 16, 1958
In view of the aforementioned, the Letter of Accepta-
bility should have been terminated for the convenience of
the Government and the $25,000.00 bid deposit returned to
Anthony Grace & Sons, Inc,
I request that this Notice of Appeal, as previously set
forth in my letter dated October 7th, 1959 be processed
in accordance with the Rules of the Armed Services
Board of Contract Appeals. Upon receipt of Notice of
Docketing I will file a formal Bill of Complaint.
I sincerely request that this appeal be expedited in
order that a hearing be held at the earliest possible date.
Very truly yours,
SALVATORE A. LOCURTO
Vv
>A.
7
g opm
George S. Robinson
Anthony Grace & Sons, Inc,
46
[fol.51-R] © PROCUREMENT OFFICE
PR 22 December 1959
Topsham Air Force Station Capehart Housing Project
Anthony Grace & Sons, Inc.
151-45 - Sixth Road
Whitestone, New York
Gentlemen :
Reference is made to letter dated 1 October 1959 ad-
dressed to you and letter addressed to Salvatore A.
Locurto, Esq., dated 1 October 1959, both signed by Mr.
George S. Robinson, Deputy Special Assistant for Instal-
lations and both in regard to cancellation of all commit-
ments undertaken with you in connection with the Cape-
hart Housing Project at Topsham Air Force Station,
Maine. Mr. Robinson was acting in my behalf and I agree
with the action taken by him in this matter.
Yours very truly,
LLoyp H. PURDY
Captain, USAF
Contracting Officer
Copies to:
Salvatore A. Locurto, Esq.
391 E 149th St.
Bronx 55, New York
Hq USAF
AFOCE-HC (2)
Col Nelson
Lt Col Podolak
ae
(fol. 51-S)
DEPARTMENT OF THE AIR FORCE
* * * *
BID FORM
ARMED SERVICES HOUSING PROJECT
* e & +
[fol.51-T] 3. The bidder understands that, if this bid is
determined to be the lowest acceptable bid, the Depart-
ment will issue io him a Lettér of Acceptability in the
form attached to the Invitation For Bids, and the bidder
[fol. 51-U] agrees that upon issuance of such Letter of
Acceptability he becomes obligated to carry out its terms
within the times therein Stated, at his own expense, with-
in the conditions of his bid security, and without further
acceptance, award, advice or other action by the Depart-
ment.
Such obligations include an obligation to cause perform-
ance by the mortgagor-builder corporations, to be formed
by the bidder, of each and every act required of it in the
[fols. 52-154] * * *
48
(fol. 155}
IN THE UNITED STATES COURT OF CLAIMS
No. 133-61
ANTHONY GRACE & Sons, INC.
v.
THE UNITED STATES
OPINION OF COMMISSIONER AND RECOMMENDATION FOR
CoNCLUSION OF Law—Filed September 22, 1964
To the honorable the CHIEF JUDGE AND ASSOCIATE
JUDGES OF THE UNITED STATES COURT OF
CLAIMS:
The following opinion and recommendation for conclu-
sion of law are submitted pursuant to the order of the
court under Rule 54(b) :
In this action plaintiff seeks to recover its bid deposit
and damages it allegedly incurred as a result of cancella-
tion by defendant of commitments made by the Depart-
ment of the Air Force to plaintiff for the construction
of a military housing project under the Capehart Act.’
[fol. 156] The case is before the court on defendant’s
motion for summary judgment on the grounds that plain-
tiff has failed to exhaust its administrative remedies and
has failed to state a claim for which relief may be
granted.
On August 22, 1958, the Department of the Air Force
issued an invitation for bids for the construction of 177
142 U.S.C. §§ 1594-1594j(f); 12 U.S.C. §§ 1748-17481. For a
brief explanation of the procedures under the Capehart Act, see
Anthony P. Miller, Inc. V. United States, Ct.Cl. No. 3-62, decided
April 5, 1963.
__ —————————
49
military Capehart housing units at Topsham Air Force
Station in Maine. The invitation, after setting forth the
purposes of the Capehart Act, provided in pertinent part:
[fol.
* * * *
4. The bidder should carefully examine the pro-
visions of the form of Housing Contract attached
hereto, including the Drawings and Specifications
made a part thereof; visit the site of the housing
projects; and fully inform himself as to all condi-
tions and matters which can in any manner affect the
financing of the construction and the constructing
of the housing projects or their cost. Should the
bidder find discrepancies in, or omissions from, such
Drawings and Specifications or other documents at-
tached hereto, or should he be in doubt as to their
meaning, he should at once notify the Contracting
Officer, Otis Air Force Base, Massachusetts, and
obtain clarification prior to submitting a bid. In-
formation given will be transmitted to all known
interested bidders.
5. Under the provisions of Title IV of the Housing
Amendments of 1955, as amended, the total principle
amount of the mortgages is limited, among other
things to the amount of the bid of the eligible builder.
However, the Davis Bacon Act and Section 212(a)
of the National Housing Act as amended require that
157] wages paid to laborers and mechanics be the
prevailing wage as determined by the Secretary of
Labor not more than ninety (96) days prior to the
commencement of construction. Since more than
ninety (90) days may elapse from thie date of this
Invitation For Bids to the commencement of con-
struction, the bids called for by this Invitation For
Bids will include a provision for adjustment of the
dollar amount therein specified to reflect any differ-
ence between the tentative minimum wage schedule
attached hereto and the applicable minimum wage
schedule as finally determined by the Secretary of
Labor. Any such adjustment will be in an amount
determined by the Commissioner to reflect such dif-
ferences, and the amount of the lowest acceptable
adjustment would increase the amount of the bid
above the amount of any other statutory maximum
applicable to the insurable mortgages, the eligible
builder will have the option of reducing his bid to
such statutory maximum or of withdrawing his bid.
8. Each bidder is required to submit with his bid
a certified check in the amount of $25,000, payable to
the Treasurer of the United States, to insure that if |
he is the lowest acceptable bidder for the total of 177
family housing units he will perform the necessary ;
preliminary steps and effect a closing with FHA
within the time prescribed in the Letter of Accepta-
bility, including the furnishing of an acceptable per-
formance and payment bond. In the event the lowest j
acceptable bidder fails to effect a closing with FHA ;
within the time prescribed, his deposit will be for-
feited and become the property of the Government
as damages unless the Department finds that he has
made every effort to effect such closing and extends
the time to effect such closing. If the lowest accepta-
ble bidder effects a timely closing with the FHA the
amount of his deposit will be refunded to him 24
hours after the initial closing with FHA. The de-
posits of unsuccessful bidders will be returned to
besa not later than 60 days after the opening of the
ids. ...
[fol. 158] a. “Timely Closing” as referred to in this
paragraph of the Invitation For Bids and closing
period as referred to elsewhere in these forms is con-
strued to be a period of approximately 60 days from
the date of opening of bids.
OE ag er es
a EN A Mt ik tte OTERO TE
Slt Si ee, Pee oo eS
12. Bidders are advised that the maximum total of
the insurable mortgages may not exceed the lesser
of three items being (1) amount of the lowest ac-
ceptable bid. (2) FHA Total of the estimated re-
51
placement cost of the property or projects or (3) an
average per family unit of $16,500 less the estimated
value of any usable utilities within the property or
projects where owned by the Department or fur-
nished by other than mortgage proceeds. Attention
is invited to FHA’s Final Appraisal and Eligibility
Statements attached hereto. The bidder will be re-
quired to pay the fees and costs prescribed in such
statements.
. * . *
22. The eligible builder, and all his subcontractors,
will be required to pay all mechanics and laborers
employed for working directly upon the sites of the
housing projects not less than the prevailing wages
as determined by the Secretary of Labor. A tenta-
tive wage scale is attached hereto. Such tentative
wage scale is, however, subject to revision prior to
actual start of construction in accordance with Sec-
retary of Labor reqirements. For the effect of such
revision see paragraph 5 above.
we * * ”
Bid Form:
8. The bidder understands that, if this bid is deter-
mined to be the lowest acceptable bid, the Department
will issue to him a Letter of Acceptability in the
form attached to the Invitation For Bids, and the
bidder agrees that upon issuance of such Letter of
Acceptability he becomes obligated to carry out its
terms within the times therein stated, at his own ex-
pense, within the conditions of his bid security, and
[fol. 159] without further acceptance, award, advice or
other action by the Department. Such obligations in-
clude an obligation to cause performance by the
mortgagor-builder corporations, to be formed by the
bidder, of each and every act required of it in the
Letter of Acceptability, to cause the execution by
said mortgagor-builder corporations of a Housing
Contract containing the same terms, conditions, pro-
visions and Drawings and Specifications as the speci-
men form of Housing Contract with good and suffi-
Es
[fol.
cient surety or sureties as required therein, within
the times specified in and in accordance with the
Letter of Acceptability.
* * * *
4. The Bidder represents that he is aware of the
statutory requirements of Section 212(a) of the
National Housing Act, as amended, and of the Davis
Bacon Act that wages to be paid to laborers and
mechanics employed in the construction of the proj-
ects are required to be not less than those contained
in the prevailing wage determination of the Secretary
of Labor, and that, in order to comply with these
statutory provisions, the bid price is subject to in-
crease or decrease by an amount determined by the
Federal Housing Commissioner (hereinafter called
the “Commissioner’”) to represent the difference in
the “Total Estimate of Replacement Cost of the
Total Project,” computed according to the wage
schedule attached to the Invitation For Bids, and
computed according to the wage schedule as amended
by the “prevailing wage determination” as that term
is defined in Paragraph 19 of the specimen form of
the Housing Contract attached to the Invitation For
Bids. Moreover, the Bidder realizes that, if the
amount of his bid as specified in the Letter of Ac-
ceptability, is thereby increased so as to exceed the
maximum total amount of the insurable mortgages
as determined by the Commissioner, the Bidder shall
have the option of reducing his bid to the amount of
the maximum total insurable mortgages as deter-
mined by the Commissioner, or of withdrawing his
bid.
* * * *
160] 8. The bidder. agrees that, if issued a Letter
of Acceptability, and if he does not exercise the op-
tion of withdrawing his bid pursuant to Paragraph
4 above, he will commence the work called for by the
Drawings and Specifications within 15 calendar days
after the date of closing, and that he will complete
the work called for by the Housing Contract as
RAE RES a
a—e,
expeditiously as possible, but in no event later than
450 calendar days after date of closing.
* * * *
Attached to the invitation for bids was a tentative
minimum wage schedule which contained the following
introductory language:
The latest wage determination made by the Secre-
tary of Labor for the country in which the work is
being performed is included herein. The complete
determination is incorporated in the contract specifi-
cations regardless of whether the Contractor will em-
ploy all the classes of laborers and mechanics listed.
The schedule set forth the minimum rates of wages per
hour for certain classes of laborers and mechanics, ap-
prentices, building construction personnel, and heavy and
highway construction personnel. The rates in the schedule
for the heavy and highway construction personnel were
lower than the rates for the building construction person-
nel. The schedule bore an expiration date of September
18, 1958.
There were also attached to the invitation for bids,
specifications which defined the scope and situs of the
work to be performed.
(fol. 161] These specifications included a breakdown into
“Section 1 on-site, site preparation” and “Section 2 on-
site, Excavation, Filling and Back-filling for Building
Construction.” Section 1 of paragraph 1-18 of the speci-
fications provided in part:
On Site
Site Preparation
1-18 EXCAVATION, TRENCHING, AND BACK-
FILLING FOR UTILITIES SYSTEM:
(a) The work consists of furnishing all plant,
labor, equipment, appliances, and materials, and in
performing all operations in connection with excava-
tion, trenching, and backfiling for utilities system,
complete, in strict accordance with this section of the
specifications and the applicable drawings,
etic
(b) All excavation for utilities systems occurring
within the enclosing walls or appurtenances of build-
ings or other structures and out to a line 5 feet out-
side of the walls or appurtenances thereof, is covered
under EXCAVATION and GRADING FOR BUILD-
ING CONSTRUCTION, and is not included under
this section of the specifications.
Section 2 of paragraph 2-01 of the specifications pro-
vided :
2-01 Scope
(a) Work Included. The work covered by this sec-
tion of the Specifications consists in furnishing all
plant, labor, equipment and materials and in per-
forming all operations in connection with excavating,
filling, backfilling and rough grading, complete for
the building and for building utilities lines to a point
five (5) feet outside the foundation line, and other
related items in strict accordance with this Section
of the Specifications and the applicable Drawings,
[fol. 162] and subject to the terms and conditions of the
contract.
(b) Work not Included. Clearing and grubbing, ex-
cavation, filling and grading for parking areas, roads,
walks, drainage, sewers and other sub-surface utili-
ties systems, and excavation for the building utili-
ties beyond planes five (5) feet outside the building
line are not included under this Section of the Speci-
fications. Stripping of topsoil is specified in Section
1, Site Preparation.
On or about September 30, 1958, plaintiff submitted its
bid to construct the housing project at a base price of
$2,653,022, with an additional price of $213,071, for cer-
tain additive alternatives, or at a total price of $2,866,093.
Plaintiff submitted with its bid a deposit, as required by
paragraph 8 of the invitation for bids, in the amount of
$25,000.
On October 29, 1958, Mr. George S. Robinson, deputy
special assistant for installations, Department of the Air
Force sent to plaintiff a “Letter of Acceptability” in
55
which plaintiff was advised that its bid of $2,866,098,
for the housing project, including the additives, was the
lowest acceptable bid; and, in which, plaintiff was fur-
ther advised of its obligations to complete a number of
arrangements before the “closing” which was scheduled
on or before January 8 1959. The letter of acceptability
specified that among the arrangements which plaintiff
was to make prior to the closing was the following:
(fol. 163]
* * * *
n. Make application through the Contracting Offi-
cer, Otis Air Force Base, Massachusetts, to the Secre-
tary of Labor for an appropriate wage determina-
tion, if necessary, (on a Department of Labor Form
DB-11 which will be supplied upon request by the
Contracting Officer) for use in the construction of
the project, and furnish a copy of such wage deter-
mination to the Contracting Officer and the Commis-
sioner. Such wage determination will be used by the
Commissioner to increase or decrease the bid price
in the manner specified in your bid.
The letter of acceptability also provided in part:
2. Failure to perform all obligations prior to the
time prescribed for closing will be just cause for
cancelling all commitments undertaken with you in
connection with the housing project and for the re-
covery under your bid security of liquidated damages
in the sum of $25,000, together with actual] damages
to the Department, such actual damages to be item-
ized and determined by the Contracting Officer, whose
decision will be reduced to writing and furnished to
you by mail or otherwise. Such decision shall be final
and conclusive unless, within 30 days from the receipt
thereof, you appeal in writing to the head of the
Department or his duly authorized representative,
and his decision shall, unless determined by a court of
competent jurisdiction to have been fraudulent or
capricious or arbitrary, or so grossly erroneous as
necessarily to imply bad faith, or not Supported by
substantial evidence, be final and conclusive. In con-
nection with any appeal under this paragraph you
will be afforded an opportunity to be heard and to
offer evidence in support of your appeal.
6. You are required to be ready for the closing on
or before January 8, 1959, and your failure to do so
will indicate your inability to carry out the obliga-
tions and terms of your bid and this Letter of Ac-
ceptability, provided that the Contracting Officer
may extend the date of closing in writing upon your
{fol. 165] submission of written documented proof that
the delay was caused by conditions beyond your con-
trol.
On November 19, 1958, pursuant to the obligations
specified in the letter of acceptability, plaintiff made a
request of the Secretary of Labor for an appropriate
wage determination. On January 28, 1959, there were
issued by the Secretary of Labor two separate wage rate
decisions, with expiration dates of April 29, 1959. One of
the decisions contained a description of work as “General
Construction of 177 family housing units” and set forth
rates for laborers and mechanics, apprentices and build-
ing construction personnel. The other decision contained
a description of work as “Cynstruction of Streets and
Roads in connection with Capehart Housing” and set
forth rates for heavy and highway construction personnel.
As in the instance of the tentative minimum wage sched-
ule which was attached t) the invitation for bids, the rates
set forth in the wage rate decisions for the heavy and
highway construction personnel were lower than the rates
for the building construction personnel.
After receiving the wage rate decisions of the Secretary
of Labor, plaintiff concluded that the effect of the de-
cisions was to require it to pay the higher building con-
struction rates for a greater area of the work than pro-
[fol. 166] vided by the specifications, and that plaintiff’s
bid price should be increased, in accordance with the
letter of acceptability, to reflect the higher rates. In
essence, plaintiff’s position was that under the specifi-
eations it was required to pay the higher building con-
—
57
struction rates for work to a point 5 feet outside the
building foundation line, and that for work beyond this
point it was required to pay only the lower heavy and
highway construction rates; but, that under the descrip-
tions of work contained in the decisions it was required
to pay the higher building construction rates for all work
beyond the above-indicated point, except for work covering
construction of streets and roads. Because of difference
between the parties arising out of the foregoing decisions,
the original closing date of January 8, 1959, set forth in
the letter of acceptability, was extended on several oc-
casions while conferences were held by the parties on the
matter.
By letter of March 18, 1959, the director of the Federal
Housing Administration advised plaintiff that there would
be an increase in the wage rates allowed plaintiff in some
categories where the promulgated rates had been increased,
but that there had been no change in the rates for either
heavy and highway personnel or for building construction
(fol. 167] power operators and that he had not been able
to justify an increase based upon plaintiff's interpreta-
tion.
On May 29, 1959, following exchanges of correspondence
and meetings of the parties, plaintiff requested a deter-
mination of the Department of the Air Force relative to
plaintiff’s interpretation of the pertinent documents from
which plaintiff concluded that it was entitled to an ad-
ditional increase of $85,884 in bid price. By letter of
June 26, 1959, plaintiff was advised by George S. Robin-
son, deputy special assistant for installations, Department
of the Air Force that he did not concur in plaintiff’s
position. The letter continued:
If you intend to effect a closing, you should advise
me promptly in order that the Letter of Accepta-
bility may be amended. If you decide not to effect a
closing, or advice as to your intention is not with-
drawn in 10 days, the letter of acceptability will be
withdrawn,
On July 2, 1959, plaintiff wrote to Mr. Robinson that
it did not approve of his decision; that, as a result of the
delay in the matter, plaintiff had sustained considerable
i
58
monetary losses; and, that plaintiff was not in a position
—— a definite closing date until the matters were re-
solved.
By letter dated October 1, 1959, Mr. Robinson advised
plaintiff that its letter of July 2, 1959, “indicating an
[fol. 168] unwillingness to set a closing date constitutes a
failure on your part to perform your obligations under
your bid and under the letter of acceptability.” The letter
continued :
* * * *
8. Accordingly, pursuant to paragraph 2 of the
letter of acceptability, the Department hereby cancels
all commitments undertaken with you in connection
with the housing project, reserving all its rights with
respect to the recovery of damages.
By letter dated October 7, 1959, addressed to Mr.
Robinson, plaintiff, through its counsel, denied that it
had indicated an unwillingness to set a closing date,
charged the Air Force with the responsibility for the
then existing problems, requested return of the bid de-
posit, and stated that plaintiff “is reserving all of its
rights with respect to recovery of damages due to the
failure of the Department of the Air Force to comply with
all of the bid instructions and regulations thereby creat-
ing the situation that exists.”
By letter dated October 19, 1959, Mr. Robinson replied
to plaintiff’s counsel that the cancellation of the commit-
ments was compelled by plaintiff’s “repeated refusals
to perform its obligations under its bid and the Letter of
Acceptability, with the result that it was necessary to
revise the plans and rebid the project,” and that the re-
quest for the return of the bid deposit was denied. For
(fol. 169] some unexplained reason, the letter of October
19, 1959, did not reach plaintiff’s counsel, who, prompted
by concern that he had received no reply to his letter of
October 7, 1959, made inquiry by telephone of defendant
on December 4, 1959, and was then furnished a copy
of the letter of October 19, 1959, which he received on
December 9, 1959.
By letter dated December 16, 1959, plaintiff’s counsel
wrote to the Secretary of the Air Force as follows:
OEE NES PRED e SERS
EER, ERAS TTR —————
pe wy
[ fol.
As counsel for Anthony Grace & Sons, Inc., I have
been requested to appeal the decision of Mr. George S.
Robinson dated October Ist, 1959.
On October 7th, 1959, I formally appealed the de-
cision in Robinson’s letter dated October Ist, 1959
and in my reply requested the return of my client’s
bid deposit check and also set forth facts in contra-
diction to Mr. Robinson’s allegations. Hearing noth-
ing further, on December 4th, 1959, I called the
office of the Department of the Air Force, and spoke
with Mr, Samuel Hanenberg concerning a reply to
my appeal dated October 7th, 1959. I thereafter,
on December 9th, 1959, received a letter from Mr.
Hanenberg wherein he furnished me with a copy of a
reply sent to my office by Mr. Robinson on October
19th, 1959. This letter was never received by my
office.
You are hereby notified of my intention to appeal
the decision of Mr. Robinson to withdraw and cancel
the Letter of Acceptability dated October 29th, 1958
and his refusal to return the $25,000.00 bid deposit.
I am of the opinion that the facts and circumstances
as set forth in my letter forwarded to Mr. Robinson
on October 7th, 1959, clearly sets forth that the de-
lays caused by the Government Agencies involved
170] made it impossible for the builder to comply
with the terms of the Letter of Acceptability.
In view of the aforementioned, the Letter of Ac-
ceptability should have been terminated for the con-
venience of the Government and the $25,000.00 bid
deposit returned to Anthony Grace & Sons, Inc,
I request that this Notice of Appeal, as previously
set forth in my letter dated October 7th, 1959 be pro-
cessed in accordance with the Rules of the Armed
Services Board of Contract Appeals. Upon receipt
of Notice of Docketing I will file a formal Bill of
Complaint.
I sincerely request that this appeal be expedited in
order that a hearing be held at the earliest possible
date.
By letter dated December 22, 1959, the procurement
contracting officer advised plaintiff that Mr. Robinson
had been acting in his behalf in regard to cancellation of
the commitments and that he agreed with the action taken
by Mr. Robinson.
The letter of December 16, 1959, to the Secretary of
the Air Force from plaintiff’s counsel was docketed by the
Armed Services Board of Contract Appeals on December
31, 1959. Thereafter, the Government moved to dismiss
the appeal on the grounds that Mr. Robinson’s letter of
October 1, 1959, canceling the commitments undertaken
with plaintiff, was “an appealable decision”; and, that no
written appeal was taken from that letter or from Mr.
Robinson’s letter of October 19, 1959 within 30 days, as
[fol.171] provided by paragraph 2 of the letter of ac-
ceptability.
Plaintiff contended before the Board that the letter of
October 1, 1959, from Mr. Robinson was not a final de-
cision within the “disputes clause” (paragraph 2) of the
letter of acceptability, but that, nevertheless, the letter of
October 7, 1959, from plaintiff’s counsel did constitute an
appeal; that the only correspondence from the Govern-
ment which constituted an appealable decision within the
disputes clause was the letter from Mr. Robinson of Oc-
tober 19, 1959, and that since that letter was not received
until December 8, 1959, the letter of December 16, 1959,
from plaintiff’s counsel containing the appeal notice was
timely. Plaintiff also contended that Mr. Robinson, the
deputy special assistant for installations, who signed
pertinent letters on defendant’s behalf was not the con-
tracting officer for the purposes of the disputes clause,
and that plaintiff had already filed its appeal by the time
the contracting officer had, by his letter of December 22,
1959, made his decision.
The Board concluded that the letter of October 1, 1959,
from Mr. Robinson constituted an appealable decision and
was at the time so regarded by plaintiff; and that the let-
ter of October 7, 1959, from plaintiff’s counsel did not
[fol. 172] contain “a then present intent * * * to invoke
the right of appeal,” and, hence, did not constitute an ap-
peal within the disputes clause. Since the December 16,
61
1959, letter from plaintiff’s counsel] containing the appeal
notice was after the period of 30 days from the October
1, 1959, letter, the Board found that the appeal was not
timely. Regarding the status of Mr. Robinson, the Board
stated in effect that he had been “the Government’s
representative in all dealing of legal consequence between
the parties,” had signed the invitation for bids, the letter
of acceptability, and various other pertinent letters, in-
cluding the letter from which plaintiff contended it had
appealed, and that the contracting officer “was at all times
a virtual stranger” to plaintiff,
Accordingly, the Board, on June 29, 1960, granted
the Government’s motion and dismissed the appeal.
In considering the issue of timeliness of plaintiff's
appeal to the Armed Services Board of Contract Appeals,
it is apparent that the question presented, namely, inter-
pretation of the provisions of the cont.act documents
which set forth the specifies of an appeal and the corres-
ponding interpretation of the effect of letters which alleg-
edly constituted “decisions” and/or “appeals,” is a ques-
tion of law; hence, it and related factual issues are to be
(fol. 173] resolved independently by the court even though
the sole record before the court is the administrative rec-
ord. P.L.S. Coat & Suit Corp. v. United States, 148 Ct.Cl.
296 (1960); Beacon Construction Co. v. United States,
Ct.Cl. No. 44-58, decided March 6, 1963, 314 F. 2d 501;
WPC Enterprises, Incorporated v. United States, Ct.Cl.
No. 256-59, decided October 11, 1963, 323 F, 2d 874;
Stein Bros. Mfg. Co. v. United States, Ct.Cl. No. 389-59,
decided July 12, 1963; Wingate Construction Co. v. United
States, Ct. Cl. No. 394-60, decided January 24, 1964.
The parties are agreed that the governing provisions
of the contract documents regarding an appeal appear in
paragraph 2, the “disputes clause,” of the letter of ac-
ceptability which, though heretofore set forth, bears re-
peating for closer examination, as follows:
2. Failure to perform all obligations prior to the
time prescribed for closing will be just cause for
cancelling all commitments undertaken with you in
connection with the housing project and for the re-
covery under your bid security of liquidated damages
in the sum of $25,000, together with actual damages
to the Department, such actual damages to be item-
ized and determined by the Contracting Officer, whose
decision will be reduced to writing and furnished
to you by mail or otherwise. Such decision shall be
final and conclusive unless, within 30 days from the
receipt thereof, you appeal in writing to the head
of the Department or his duly authorized representa-
tive, and his decision shall, unless determined by a
court of competent jurisdiction to have been fraudu-
(fol. 174] lent or capricious or arbitrary, or so grossly
erroneous as necessarily to imply bad faith, or not
supported by substantial evidence, be final and con-
elusive. In connection with any appeal under this
paragraph you will be afforded an opportunity to be
heard and to offer evidence in support of your appeal.
In light of the foregoing disputes clause, let us turn to
the pertinent language of the letter of October 1, 1959, to
plaintiff from Mr. Robinson to determine if there was
therein a “decision” which would become “final and con-
clusive” unless appealed from within 30 days. This per-
tinent language reads:
am * * .
3. Accordingly, pursuant to paragraph 2 of the
letter of acceptability, the Department hereby cancels
all commitments undertaken with you in connection
with the housing project, reserving all its rights with
respect to the recovery of damages.
A fair reading of the provisions of the disputes clause
compels the conclusion that the decision of the contracting
officer should include not only language canceling the
commitments, but also language setting forth a conclusion
regarding recovery of the bid security and itemization of
such actual damages which the contracting officer deter-
mined should be recovered.
It is clear from the pertinent language of the October 1,
1959, letter that all of the elements of a decision required
[fol. 175] by the disputes clause are not present, because
the only reference to damages (whether liquidated or
actual) is that defendant was “reserving all its rights
———
63
with respect to the recovery of damages.” Upon reading
this letter, plaintiff could not tell whether defendant had
decided to recover liquidated damages, whether defend-
ant was claiming actual damages or in what amount, or
even when defendant expected to reach a conclusion as to
liquidated or actual damages. Conceivably, plaintiff could
have concluded that if there was to be no recovery sought
by defendant of liquidated damages or of actual damages,
it would be satisfied for the commitments to be canceled
and would not appeal; but, plaintiff could not make an
intelligent determination on the matter from the contents
of the letter. It is concluded that the letter did not con-
stitute a “decision” within the disputes clause, even
though, as defendant points out, plaintiff in subsequent
correspondence did refer to the “decision” in the October
1, 1959, letter. Having reached this conclusion, it is un-
necessary to consider whether or not the letter of October
7, 1959, from plaintiff’s counsel requesting return of the
bid deposit and advising that plaintiff was “reserving all
of its rights with respect to recovery of damages” con-
[fol. 176] stitutes an appeal, because the letter from
plaintiff’s counsel of December 16, 1959, which admittedly
constituted an appeal was within the 30-day period after
the receipt by plaintiff’s counsel on December 8, 1959,
of defendant’s letter of October 19, 1959. It is likewise
unnecessary to consider the question raised by plaintiff as
to the status of Mr. Robinson, the deputy special assistant
for installations.
It is accordingly concluded that plaintiff did make time-
ly appeal and, therefore, did exhaust its administrative
remedies, and is entitled to seek relief in this court.
Defendant contends that, irrespective of the issue of
exhaustion of administrative remedies, plaintiff may not
maintain its action in the court, because under the terms
of the letter of acceptability plaintiff could not refuse
to “close” a Capehart contract over a disagreement on the
administrative determinations of appropriate minimum
wages for the housing project, and that such determina-
tions are not subject to judicial review.
Plaintiff has pleaded in its petition that defendant
“unilaterally altered the scope of work provisions” and
issued “wage schedules in direct contravention of its con-
64
[fol. 177] tractual obligations,” and that defendant’s ac-
tion made it impossible for plaintiff to continue in its
efforts to perform under the contract. Plaintiff further
contends that its interpretation of the plans and specifica-
tions is correct “in light of the interpretation given such
ove and specifications by custom and usage in the
trade.”
Obvivusly the parties are in disagreement over the
nature of the issue presented and, of course, the Armed
Services Board of Contract Appeals, having reached its
decision solely on the matter of the timeliness of plain-
tiff’s appeal, did not consider any other issue.
If the issue could be stated in the terms which are sug-
gested by defendant, then it could be resolved solely on the
basis of the contract documents before the court. Plain-
tiff alleges in effect, however, that defendant did some-
thing more than merely make an administrative deter-
mination of appropriate minimum wages, but that defend-
ant unilaterally altered the scope of work provisions and
that defendant’s action made it impossible for plaintiff to
perform; i.e. that defendant, rather than plaintiff, was
at fault. Since the issue then, at least as presented by
plaintiff, involves an alleged breach of contract, this
court is not in the consideration of the issue, subject to
(fol. 178] the strictures of United States v. Carlo Bianchi
& Co., Inc., 373 U.S, 709 (June 3, 1968), pertaining to a
question arising under a “disputes” clause. There appear,
moreover, to be factual issues bearing on the alleged
breach which should be resolved, but, regarding which,
the record in its present state before the court is barren.
For example, the question of the custom and usage in the
trade from which plaintiff derives its conclusion that its
interpretation of the plans and specifications is correct
might properly be explored. Again, it is probable that the
conduct and/or statements of the parties, in their numer-
ous conferences over the matters in dispute, might have
significant bearing on whether plaintiff or defendant was
at fault. This is not to suggest that the foregoing should
necessarily be the subject of testimony at a trial, but only
that, because of its peculiar history, the case does not in
its present posture contain a record touching on the vari-
ous factual issues which plaintiff, in its reply to defend-
ant’s motion for summary judgment, requests opportunity
to try.
(fol. 179)
RECOMMENDATION FOR CONCLUSION OF LAW
It is recommended that the court adopt the following
concusion of law:
On the administrative record and briefs of the parties
and for the reasons stated above, the court concludes as a
matter of law that defendant’s motion for summary judg-
ment is denied,
Respectfully submitted,
RICHARD ARENS, Commissioner.
[fols, 180-195] * * *
66
[fol. 196]
IN THE UNITED STATES COURT OF CLAIMS
No. 133-61
ANTHONY GRACE & Sons, INC.
Vv.
THE UNITED STATES
David Fromson for the plaintiff.
David Orlikoff, with whom was Assistant Attorney
General John W. Douglas, for the defendant. Mary J.
Turner was on the brief.
Before COWEN, Chief Judge, LARAMORE, DURFEE, DAVIS
and COLLINS, Judges.
OPINION—Decided May 14, 1965
ON DEFENDANT’S MOTION FOR SUMMARY JUDGMENT
CowEN, Chief Judge, delivered the opinion of the court:
In this action plaintiff seeks to recover its bid deposit
and damages it allegedly incurred as a result of cancella-
tion by defendant of commitments made by the Depart-
ment of the Air Force to plaintiff for the construction of
a military housing project under the Capehart Act. The
case is before the court on defendant’s motion for sum-
mary judgment on the grounds that plaintiff has failed
142 U.S.C. §§ 1594-1594j; 12 U.S.C. §§ 1748-1748i. For a brief
explanation of the procedures under the Capehart Act, see Anthony
P. Miller, Inc. v. United States, No. 3-62, Ct. Cl. April 5, 1963.
— ——————
67
to exhaust its administrative remedies and has failed to
state a claim for which relief may be granted.
This motion was referred to Trial Commissioner Rich-
ard Arens, under Rule 54(b), for his opinion and recom-
mendations for a conclusion of law. Commissioner Arens
has submitted an opinion and recommendaticns, The de-
(fol. 197] fendant sought review of both, and the case was
set for argument. The plaintiff submitted on the briefs
but the defendant presented oral argument.
I
The first issue is whether the plaintiff failed to exhaust
its administrative remedies because its appeal to the
Board of Contract Appeals from the cancellation (and the
refusal to return its deposit) was untimely (as the Board
held). Commissioner Arens’ opinion concludes that the
appeal was not untimely and the Board erred in dismiss-
ing it on that ground, The court agrees (with slight
modifications) with that portion of the Commissioner’s
opinion (set forth in Part III, infra) and adopts it, as so
modified, as the basis for rejecting the defendant’s argu-
ment that plaintiff is barred from suing in this court be-
cause it failed properly to exhaust its administrative
remedy.
The second issue is whether, in any event, plaintiff
states a cause of action. Defendant contends that, irre-
spective of the issue of exhaustion of administrative reme-
dies, plaintiff may not maintain its action because under
the terms of the letter of acceptability plaintiff could not
refuse to “close” a Capehart contract over a disagreement
on the administrative determinations of appropriate mini-
mum wages for the housing project, and that such de-
terminations are not subject to judicial review.
Plaintiff has pleaded in its petition that defendant
“unilaterally altered the scope of work provisions” and
issued “wage schedules in direct contravention of its con-
tractual obligations,” and that defendant’s action made it
impossible for plaintiff to continue in its efforts to per-
form under the contract. Plaintiff further contends that
its interpretation of the plans and specifications is correct
—
“in light of the interpretation given such plans and speci-
fications by custom and usage in the trade.”
Thus, the parties are in disagreement over the nature
of the issue presented and, of course, the Armed Services
Board of Contract Appeals, having reached its decision
solely on the matter of the timeliness of plaintiff’s appeal,
did not consider any other issue.
{fol. 198] The Trial Commissioner recommended that
the decision on defendant’s contention that plaintiff fails
to state a cause of action should be resolved only after
trial. In the Trial Commissioner’s view, the issues are
not now precisely framed; evidence as to the conduct of
the parties may shed some light on the issues, and there
are unresolved issues of fact.
Even where a motion for summary judgment meets the
technical requirements for the granting of the motion, the
court may in its discretion deny the motion. See Ct. Cl.
R. 64; Fed. R. Civ. P. 56; Williams v. Howard Johnson’s
Inc. of Washington, 323 F. 2d 102 (4th Cir. 1963); S. J.
Groves & Sons Co, v. Ohio Turnpike Commission, 315 F.
2d 285 (6th Cir. 1963). Denial of the motion is appro-
priate when the legal issues are of particular significance,
or particularly complex, or where the legal issues can be
intelligently resolved only upon a fully developed record.
See Kennedy v. Silas Mason Co., 334 U.S. 249 (1948) ;
Pacific American Fisheries, Inc. v. Mu'laney, 191 F. 2d
137 (9th Cir. 1951). We believe this to be a proper case
for the exercise of that discretion.”
II
Having determined that the Armed Services Board of
Contract Appeals improperly refused to consider plain-
2 See 6 Moore F. P. §§ 56.15[6],'56.16 (2d Ed. 1953), the former
section comments at pp. 2158-2159:
“«* * * the court must necessarily evaluate the character of
_ the record in light of the legal issues; and it should take care
not to adjudicate difficult or complicated legal issues, either of
a private or public nature, upon an inadequate factual basis. A
sound appraisal may demand that the motion be denied and
that the case proceed to trial. * * *” See also United States v.
Small, 24 F.R.D. 429 (S.D.N.Y. 1959).
=
tiff’s appeal on its merits (Part III hereof), we must con-
sider whether we should suspend action in this court and
direct the plaintiff to return the case to the Board, or
whether we should deny defendant’s motion and remand
the litigation to our Trial Commissioner,
It is an accepted principle that where the administra-
tive remedy is inadequate, a party will no longer be re-
quired to exhaust that remedy as a prerequisite to main-
taining an action in court. Davis, Administrative Law,
(fol. 199] § 189 (1951) This court has entertained an
action without requiring further recourse to the contrac-
tual administrative procedures where the contracting of-
ficer has refused to render a decision as required by the
contract or has delayed his decision excessively. Mazxan
Dress Corp. v. United States, 126 Ct. Cl. 484, 115 F.
Supp. 439 (1953) ; United States Casualty Co. v. United
States, 107 Ct. Cl. 46, 67 F. Supp. 950 (1946). The same
rule has been applied where the head of the agency simi-
larly erred. Southeastern Oil Florida, Inc. v. United
States, 127 Ct. Cl. 480, 115 F. Supp. 198 (1953); Heid
Bros., Inc. v. United States, 69 Ct. Cl. 704 ( 1930) ; Cape
Ann Granite Co., Inc. v. United States, 100 Ct. Cl. 53,
cert. denied, 321 U.S. 790; Cf. Hele v. United States, 100
Ct. Cl. 289 (1948) and 108 Ct. Cl. 472 (1945).
In Southeastern Oil Florida, supra, the plaintiff had
contracted to transport government gasoline. The con-
tracting officer determined that the plaintiff was respon-
sible for the contamination of some of the gasoline and
withheld moneys due under the contract. The contractor
pursued his remedies under the contract and appealed to
the Secretary of the Navy. For 2 years the appeal was
not acted upon, and the contractor filed suit. This court
commented, 127 Ct. Cl. 480, 484:
Defendant argues that because plaintiff’s appeal to
the head of the department is stil] pending, this
court has no jurisdiction of plaintiff’s claim. It is
69
5 See generally, Brister & Koester Lumber Corp. v. United States,
188 F. 2d 986 (D.C. Cir. 1951) ; United States v. Blake, 161 F. Supp.
76 (E.D.N.C. 1958) ; Wessel, Duval & Co. v. United States, 126 F.
Supp. 79 (S.D.N.Y. 1954).
_ nee.
70
true that a contractor must exhaust the administra-
tive remedies provided in the contract before it is en-
titled to bring suit in this court. United States v.
Blair, 321 U.S. 730, 735; United States v. Holpuch
Co., 328 U.S. 234, 240. These cases also set forth
the exception to this rule, however, which is that a
contractor is not prevented from suing in this court
where the administrative appeal procedure provided
in its contract is, in fact, inadequate or unavailable.
In the Blair case, the Supreme Court recognized that
(p. 736) :
If it were shown that the appeal procedure
provided in the contract was in fact inadequate
* * * we would have a quite different case.
Likewise, in the Holpuch decision, the Supreme
Court stated that (p. 240):
And in the absence of some clear evidence that
the appeal procedure is inadequate or unavail-
[fol. 200] able, that procedure must be pursued and ex-
hausted before a contractor can be heard to com-
plain in a court.
In this case, the plaintiff having appealed to the
head of the department, and the head of the depart-
ment having failed for more than two years to indi-
cate whether he would or would not take jurisdiction
of the appeal, the plaintiff was justified in regard-
ing the administrative appeal procedure as _inade-
quate and in filing its suit in this court. Having
filed its suit, it was not required te abandon that suit
and resume the administrative procedure.
We must now query whether the decision in United
States v. Carlo Bianchi & Co., Inc., 373 U.S. 709 (1963)
alters the rule announced in the cases cited above. Since
the Bianchi case was handed down, this court has decided
that the failure of the contracting officer to perform his
adjudicatory functions permits an action to be maintained
in this court without any further administrative proceed-
ings, C. J. Langenfelder & Sons, Inc. v. United States,
No. 291-68, Ct. Cl., February 19, 1965, 334 F. 2d 600;
Satan isbe idea Reb notice mee oie ee
SPREE LIER PERLE PIES ON tC MTT
71
H. B. Zachry Co, v. United States, No. 332-61, Ct. Cl.,
April 16, 1965. We believe that if a contracting officer’s
failure to act allows immediate recourse to the courts, it
follows a fortiori that a similar lack of action by a con-
tract appeals board should also permit such immediate
resort to the courts.
The decisions in Langenfelder and Zachry, supra, dic-
tate that in the case before us, we retain the case for trial
in this court.
[fol. 201] We believe that this result is in accord with
the Supreme Court’s decision in the Bianchi case, supra.
Justice Harlan, speaking for the majority in that case,
made the following observations on the sanctions to be
imposed by this court when confronted with an unaccept-
able administrative record. (873 U.S. 709, 717-718) :
* * * Second, in situations where the court believed
that the existing record did not warrant such a
course, but that the departmental determination
could not be sustained under the standards laid down
by Congress, we see no reason why the court could
not stay its own proceedings pending some further
action before the agency involved. Cf. Pennsylvania
R. Co. v. United States, 363 U.S. 202. Such a stay
would certainly be justified where the department
had failed to make adequate provision for a record
“In cases where the court’s decision was contrary to that of the
administrative boards and the board had made no findings on the
quantum of an equitable adjustment determined to be due, this court
retained the case and permitted a trial on that issue, E. H. Sales,
Inc. v. United States, No. 75-61, Ct. Cl., January 22, 1965. Jack
Stone Co. v. United States, No. 312-62, April 16, 1965.
But see, Utah Construction and Mining Co. v. United States, No.
8-61, Ct. Cl., December 11, 1964, where the court resolved, on a hy-
pothetical basis, the disposition of the concrete aggregate claim
which had been rejected by the administrative board as untimely.
The issue of whether to suspend proceedings was not, at that time,
squarely before the court; the issue was only marginally raised by
defendant and was not briefed. Since that time, in this and sev-
eral other cases, we have had the benefit of argument, briefs, and
more detailed reflection on the question. Therfore, the conclusion in
the Utah case does not, in view of the circumstances under which it
was made, foreclose our reconsideration of the issue.
a
that could be subjected to judicial scrutiny, for it
was clearly part of the legislative purpose to achieve
uniformity in this respect. And in any case in which
the department failed to remedy the particular sub-
stantive or procedural defect or inadequacy, the sanc-
tion of judgment for the contractor would always be
available to the court.
The foregoing comment must be read in, the light of
the Supreme Court’s policy to expedite the disposition of
such litigation—a policy stated in the same opinion at
page 717 as follows:
* * * The consequences of such a procedure [duplica-
tion of trials] would in many instances be a needless
duplication of evidentiary hearings and a heavy ad-
ditional burden in time and expense required to bring
litigation to an end.
A suspension of proceedings in this court for additional
action by an administrative board should be ordered only
where the suspension will actually expedite handling of
the litigation or where the Supreme Court has indicated
that a stay of court proceedings is justified. It should be
emphasized that we have no remand power in these cases.
Therefore, where an appeals board has refused jurisdic-
tion in a case, or where its prior decisions demonstrate
that it will not entertain jurisdiction of a particular dis-
(fol. 202] pute, a return of the proceedings to the board
is a useless gesture which will be productive only of fur-
ther delay in the litigation.°
It is to be noted that in Bianchi, the Supreme Court did
not have before it, nor did it discuss, a situation where
a contract appeals board has refused jurisdiction. But
the Court in that case squarely addressed itself to the
problems of delay. Accordingly, we conclude that the re-
5’ The Armed Services Board of Contract Appeals has consistently
held that it did not have jurisdicticn to review the decisions of the
Federal Housing Commissioner on contracts such as that in issue
here, Len Co. and Associates, 1962 BCA 17854 (ASBCA 1962); An-
thony Grace & Sons, Inc., 1962 BCA 17882 (ASBCA 1962) ; see also
Centex Constr. Co. v. United States, No. 342-60, Ct. Cl., June 7,
1963.
73
tention of this case for trial in this court best accords
with the enunciated policy of speeding contract litigation.*
Ill
Commissioner Arens’ opinion on the timeliness of plain-
tiff’s appeal to the Board of Contract Appeals, as modified
and adopted by the court, is as follows:
On August 22, 1958, the Department of the Air Force
issued an invitation for bids for the construction of 177
military Capehart housing units at Topsham Air Force
Station in Maine. The invitation, after setting forth the
purposes of the Capehart Act, provided in pertinent part:
4. The bidder should carefully examine the provi-
sions of the form of Housing Contract attached here-
to, including the Drawings and Specifications made a
part thereof; visit the site of the housing projects ;
and fully inform himself as to all conditions and mat-
ters which can in any manner affect the financing of
the construction and the constructing of the housing
projects or their cost. Should the bidder find discrep-
ancies in, or omissions from, such Drawings and
Specifications or other documents attached hereto, or
should he be in doubt as to their meaning, he should
at once notify the Contracting Officer, Otis Air Force
Base, Massachusetts, and obtain clarification prior to
submitting a bid. Information given will be trans-
mitted to all known interested bidders.
(fol. 203] 5. Under the provisions of Title IV of the
Housing Amendments of 1955, as amended, the total
principle [sic] amount of the mortgages is limited,
among other things to the amount of the bid of the
eligible builder. However, the Davis-Bacon Act and
Section 212(a) of the National Housing Act as
amended require that wages paid to laborers and me-
chanics be the prevailing wage as determined by the
Secretary of Labor not more than ninety (90) days
* See Schultz, Wunderlich Revisited: New Limits on Judicial Re-
view of Administrative Determination of Government Contract Dis-
putes, 29 Law & Contemp. Prob. 115, 127 (1964); Spector, Js Jt
“Bianchi’s Ghost”—Or “Much Ado About Nothing” ?, 16 Ad. L. Rev.
265, 289 (1964).
74
prior to the commencement of construction. Since
more than ninety (90) days may elapse from the
date of this Invitation For Bids to the commence-
ment of construction, the bids called for by this Invi-
tation For Bids will include a provision for adjust-
ment of the dollar amount therein specified to reflect
any difference between the tentative minimum wage
schedule attached hereto and the applicable minimum
wage schedule as finally determined by the Secretary
of Labor, Any such adjustment will be in an amount
determined by the Commissioner to reflect such dif-
ferences, and the amount of the lowest acceptable bid
and the FHA estimated total replacement cost of the
projects will be amended in the amount so deter-
mined by the Commissioner; except that, if such an
adjustment would increase the amount of the bid
above the amount of any other statutory maximum
applicable to the insurable mortgages, the eligible
builder will have the option of reducing his bid to
such statutory maximum or of withdrawing his bid.
8. Each bidder is required to submit with his bid a
certified check in the amount of $25,000, payable to
the Treasurer of the United States, to insure that if
he is the lowest acceptable bidder for the total of 177
family housing units he will perform the necessary
preliminary steps and effect a closing with FHA
within the time prescribed in the Letter of Accepta-
bility, including the furnishing of an acceptable per-
formance and payment bond. In the event the lowest
acceptable bidder fails to effect a closing with FHA
within the time prescribed, his deposit will be for-
feited and become the property of the Government
as damages unless the Department finds that he has
made every effort to effect such closing and extends
the time to effect such closing. If the lowest accepta-
ble bidder effects a timely closing with the FHA the
amount of his deposit will be refunded to him 24
hours after the initial closing with FHA. The de-
posits of unsuccessful bidders will be returned to
— a later than 60 days after the opening of
e i ‘ ** #
a
75
(fol. 204] a. “Timely Closing” as referred to in this
paragraph of the Invitation For Bids and closing
period as referred to elsewhere in these forms is
construed to be a period of approximately 60 days
from the date of opening of bids.
12. Bidders are advised that the maximum total of
the insurable mortgages may not exceed the lesser of
three items being (1) amount of the lowest accepta-
ble bid, (2) FHA Total of the estimated replacement
cost of the property or projects or (8) an average
per family unit of $16,500 less the estimated value
of any usable utilities within the property or projects
where owned by the Department or furnished by
other than mortgage proceeds, Attentiin is invited to
FHA’s Final Appraisal and Eligibility Statements
attached hereto. The bidder will be required to pay
the fees and costs prescribed in such statements,
22. The eligible builder, and al! his subcontyactors,
will be required to pay all mechanics and laborers
employed for working directly upon the sites of the
housing projects not less than the prevailing wages
as determined by the Secretary of Labor. A tentative
wage scale is attached hereto. Such tentative wage
scale is, however, subject to revision prior to actual
start of construction in accordance with Secretary of
Labor requirements. For the effect of such revision
see paragraph 5 above,
Bid Form:
8. The bidder understands that, if this bid is deter-
mined to be the lowest acceptable bid, the Department
will issue to him a Letter of Acceptability in the form
attached to the Invitation For Bids, and the bidder
agrees that upon issuance of such Letter of Accept-
ability he becomes obligated to carry out its terms
within the times therein stated, at his own expense,
within the conditions of his bid security, and without
———
76
further acceptance, award, advice or other action by
the Department. Such obligations include an obliga-
tion to cause performance by the mortgagor-builder
corporations, to be formed by the bidder, of each and
every act required of it in the Letter of Acceptability,
to cause the execution by said mortgagor-builder
corporations of a Housing Contract centaining the
same terms, conditions, provisions and Drawings and
[fol. 205] Specifications as the specimen form of Housing
Contract with good and sufficient surety or sureties as
required therein, within the times specified in and in
accordance with the Letter of Acceptability.
4. The Bidder represents that he is aware of the
statutory requirements of Section 212(a) of the
National Housing Act, as amended, and of the Davis
Bacon Act that wages to be paid to laborers and
mechanics employed in the construction of the proj-
ects are required to be not less than those contained
in the prevailing wage determination of the Secretary
of Labor, and that, in order to comply with these
statutory provisions, the bid price is subject to in-
crease or decrease by an amount determined by the
Federal Housing Commissioner (hereinafter called
the “Commissioner”) to represent the difference in
the “Total Estimate of Replacement Cost of the Total
Project,” computed according to the wage schedule
attached to the Invitation For Bids, and computed
according to the wage schedule as amended by the
“prevailing wage determination” as that term is de-
fined in Paragraph 19 of the specimen form of the
Housing Contract attached to the Invitation For
Bids. Moreover, the Bidder realizes that, if the
amount of his bid as specified in the Letter of Ac-
ceptability, is thereby increased so as to exceed the
maximum total amount of the insurable mortgages
as determined by the Commissioner, the Bidder shall
have the option of reducing his bid to the amount of
the maximum total insurable mortgages as deter-
mined by the Commissioner, or of withdrawing his
bid.
_
77
8. The bidder agrees that, if issued a Letter of Ac-
ceptability, aud if he does not exercise the option of
withdrawing his bid pursuant to Paragraph 4 above,
he wviil commence the work called for by the I raw-
ings and Specifications within 15 calendar days after
the date of closing, and that he will complete the
work called for by the Housing Contract as expedi-
tiously as possible, but in no event later than 450
calendar days after date of closing.
Attached to the invitation for bids was a tentative
minimum wage scledule which contained the following in-
troductory language:
The latest wage determination made by the Secre-
tary of Labor for the country in which the work is
(fol. 206] being performed is included herein. The com-
plete determination is incorporated in the contract
specifications regardless of whether the Contractor
will employ all the classes of laborers and mechanics
listed.
The schedule set forth the minimum rates of wages per
hour for certain classes of laborers and mechanics, ap-
prentices, building construction personnel, and heavy and
highway construction personnel. The rates in the schedule
for the heavy and highway construction personne] were
lower than the rates for the building construction person-
nel. The schedule bore an expiration date of September
18, 1958.
There were also attached to the invitation for bids,
specifications which defined the Scope and situs of the
work to be performed,
These specifications included a breakdown into “Section
1 on-site, site preparation” and “Section 2 on-site, Exca-
vation, Filling and Back-filling for Building Construc-
tion.” Section 1 of paragraph 1-18 of the specifications
provided in part:
On Site
Site Preparation
1-18 EXCAVATION, TRENCHING, AND BACK-
FILLING FOR UTILITIES SYSTEM:
(a) The work consists of furnishing all plant,
labor, equipment, appliances, and materials, and in
performing all operations in connection with excava-
tion, trenching, and backfilling for utilities system,
complete, in strict accordance with this section of the
specifications and the applicable drawings.
(b) All excavation for utilities systems occurring
within the enclosing walls or appurtenances of build-
ings or other structures and out to a line 5 feet out-
side of the walls or appurtenances thereof, is covered
under EXCAVATION AND GRADING FOR
BUILDING CONSTRUCTION, and is not included
under this section of the specifications.
* — + *
Section 2 of paragraph 2-01 of the specifications pro-
vided :
2-01 Scope
(a) Work Included. The work covered by this section
of the Specifications consists in furnishing all plant,
labor, equipment and materials and in performing all
operations in connection with excavating, filling, back-
[fol. 207] filling and rough grading, complete for the
building and for building utilities lines to a point
five (5) feet outside the foundation line, and other
related items in strict accordance with this Section
of the Specifications and the applicable Drawings,
and subject to the terms and conditions of the con-
tract.
(b) Work not Included. Clearing and grubbing, ex-
cavation, filling and grading for parking areas, roads,
walks, drainage, sewers and other sub-surface utili-
ties systems, and excavation for the building utilities
beyond planes five (5) feet outside the building line
are not included under this Section of the Specifica-
.
tions. Stripping of topsoil is specified in Section 1,
Site Preparation.
On or about September 30, 1958, plaintiff submitted its
bid to construct the housing project at a base price of
$2,653,022, with an additional price of $213,071, for cer-
tain additive alternatives, or at a total price of $2,866,093.
Plaintiff submitted with its bid a deposit, as required by
paragraph 8 of the invitation for bids, in the amount of
$25,000. |
On October 29, 1958, Mr. George S, Robinson, deputy
special assistant for installations, Department of the Air
Force, sent to plaintiff a “Letter of Acceptability” in
which plaintiff was advised that its bid of $2,866,098, for
the housing project, including the additives, was the lowest
acceptable bid; and, in which, plaintiff was further ad-
vised of its obligations to complete a number of arrange-
ments before the “closing” which was scheduled on or be-
fore January 8, 1959. The letter of acceptability specified
that among the arrangements which plaintiff was to make
prior to the closing was the following:
* * * *
n. Make application through the Contracting Offf-
cer, Otis Air Force Base, Massachusetts, to the Secre-
tary of Labor for an appropriate wage determina-
tion, if necessary, (on a Department of Labor Form |
DB-11 which wil] be supplied upon request by the
Contracting Officer) for use in the construction of the
project, and furnish a copy of such wage determina-
tion to the Contracting Officer and the Commissioner.
Such wage determination will be used by the Com-
missioner to increase or decrease the bid price in the
manner specified in your bid.
The letter of acceptability also provided in part:
(fol. 208] 2. Failure to perform all obligations prior to
the time prescribed for closing will be just cause for
cancelling all commitments undertaken with you in
connection with the housing project and for the re-
covery under your bid security of liquidated damages
in the sum of $25,000, together with actual damages
to the Department, such actual damages to be item-
ized and determined by the Contracting Officer, whose
decision will be reduced to writing and furnished to
you by mail or otherwise. Such decision shall be
final and conclusive unless, within 30 days from the
receipt thereof, you appeal in writing to the head
of the Department or his duly authorized representa-
tive, and his decision shall, unless determined by a
court of competent jurisdiction to have been fraudu-
lent or capricious or arbitrary, or s0 grossly errone-
ous as necessarily to imply bad faith, or not sup-
ported by substantial evidence, be final and conclu-
sive. In connection with any appeal under this para-
graph you will be afforded an opportunity to be heard
and to offer evidence in support of your appeal.
+ * * *
6. You are required to be ready for the closing on
or before January 8, 1959, and your failure to do so
will indicate your inability to carry out the obliga-
tions and terms of your bid and this Letter of Ac-
ceptability, provided that the Contracting Officer may
extend the date of closing in writing upon your sub-
mission of written documented proof that the delay
was caused by conditions beyond your control.
On November 19, 1958, pursuant to the obligations
specified in the letter of acceptability, plaintiff made a re-
quest of the Secretary of Labor for an appropriate wage
determination. On January 28, 1959, there were issued
by the Secretary of Labor two separate wage rate de-
cisions, with expiration dates of April 29, 1959. One of
the decisions contained a description of work as “General
Construction of 177 family housing units” and set forth
rates for laborers and mechanics, apprentices and build-
ing construction personnel. The other decision contained
a description of work as “Construction of Streets and
Roads in connection with Capehart Housing” and set
forth rates for heavy and highway construction person-
nel. As in the instance of the tentative minimum wage
schedule which was attached to the invitation for bids, the
rates set forth in the wage rate decisions for the heavy
[fol. 209] and highway construction personnel were lower
than the rates for the building construction personnel.
a ——
81
After receiving the wage rate decisions of the Secretary
of Labor, plaintiff concluded that the effect of the deci-
sions was to require it to pay the higher building con-
struction rates for a greater area of the work than pro-
vided by the specifications, and that plaintiff’s bid price
should be increased, in accordance with the letter of ac-
ceptability, to reflect the higher rates. In essence, plain-
tiff’s position was that under the specifications it was re-
quired to pay the higher building construction rates for
work to a point 5 feet outside the building foundation line,
and that for work beyond this point it was required to
pay only the lower heavy and highway construction rates ;
but, that under the descriptions of work contained in the
decisions it was required to pay the higher building con-
struction rates for all work beyond the above-indicated
point, except for work covering construction of streets
and roads. Because of difference between the parties
arising out of the foregoing decisions, the original closing
date of January 8, 1959, set forth in the letter of ac-
ceptability, was extended on several occasions while con-
ferences were held by the parties on the matter.
By letter of March 18, 1959, the director of the Federal
Housing Administration advised plaintiff that there would
be an increase in the wage rates allowed plaintiff in some
categories where the promulgated rates had been in-
creased, but that there had been no change in the rates
for either heavy and highway personnel or for building
construction power operators and that he had not been
able to justify an increase based upon plaintiff’s interpre-
tation.
On May 29, 1959, following exchanges of correspond-
ence and meetings of the parties, plaintiff requested a
determination of the Department of the Air Force relative
to plaintiff’s interpretation of the pertinent documents
from which plaintiff concluded that it was entitled to an
additional increase of $85,834 in bid price. By letter of
June 26, 1959, plaintiff was advised by George S. Robin-
son, deputy special assistant for installations, Department
of the Air Force, that he did not concur in plaintiff’s
position. The letter continued:
a
—
82
If you intend to effect a closing, you should advise
me promptly in order that the Letter of Acceptability
[fol. 210] may be amended. If you decide not to effect a
closing, or advice as to your intention is not with-
drawn in 10 days, the letter of acceptability will be
withdrawn.
On July 2, 1959, plaintiff wrote to Mr. Robinson that it
di@® not approve of his decision; that, as a result of the
delay in the matter, plaintiff had sustained considerable
monetary losses; and, that plaintiff was not in a position
to set a definite closing date until] the matters were re-
solved.
By letter dated October 1, 1959, Mr. Robinson advised
plaintiff that its letter of July 2, 1959, “indicating an un-
willingness to set a closing date constitutes a failure on
your part to perform your obligations under your bid and
under the letter of acceptability.” The letter continued:
* * * *
3. Accordingly, pursuant to paragraph 2 of the
letter of acceptability, the Department hereby cancels
all commitments undertaken with you in connection
with the housing project, reserving all its rights with
respect te the recovery of damages.
By letter dated October 7, 1959, addressed to Mr. Robin-
son, plaintiff, through its counsel, denied that it had indi-
cated an unwillingness to set a closing date, charged the
Air Force with the responsibility for the then existing
problems, requested return of the bid deposit, and stated
that plaintiff “is reserving all of its rights with respect to
recovery of damages due to the failure of the Department
of the Air Force to comply with all of the bid instructions
and regulations thereby creating the situation that exists.”
By letter dated October 19, 1959, Mr. Robinson replied
to plaintiff’s counsel that the cancellation of the commit-
ments was compelled by plaintiff’s “repeated refusals to
perform its obligations under its bid and the Letter of
Acceptability, with the result that it was necessary to re-
vise the plans and rebid the project,” and that the request
. for the return of the bid deposit was denied. For some
unexplained reason, the letter of October 19, 1959, did not
reach plaintiff’s counsel, who, prompted by concern that
he had received no reply to his letter of October 7, 1959,
made inquiry by telephone of defendant on December 4,
1959, and was then furnished a copy of the letter of Oc-
tober 19, 1959, which he received on December 9, 1959.
(fol. 211] By letter dated December 16, 1959, plaintiff’s
counsel wrote to the Secretary of the Air Force as follows:
As counsel for Anthony Grace & Sons, Inc., I have
been requested to appeal the decision of Mr. George
S. Robinson dated October Ist, 1959,
On October 7th, 1959, I formally appealed the de-
cision in Robinson’s letter dated October Ist, 1959
and in my reply requested the return of my client’s
bid deposit check and also set forth facts in contra-
diction to Mr. Robinson’s allegations. Hearing noth-
ing further, on December 4th, 1959, I called the office
of the Department of the Air Force, and spoke with
Mr. Samuel Hanenberg concerning a reply to my ap-
peal dated October 7th, 1959. I thereafter, on Decem-
ber 9th, 1959, received a letter from Mr. Hanenberg
wherein he furnished me with a copy of a reply sent
to my office by Mr. Robinson on October 19th, 1959.
This letter was never received by my office,
You are hereby notified of my intention to appeal
the decision of Mr. Robinson to withdraw and cancel
the Letter of Acceptability dated October 29th, 1958
and his refusal to return the $25,000.00 bid deposit.
I am of the opinion that the facts and circumstances
as set forth in my letter forwarded to Mr. Robinson
on October 7th, 1959, clearly sets forth that the de-
lays caused by the Government Agencies involved
made it impossible for the builder to comply with the
terms of the Letter of Acceptability.
In view of the aforementioned, the Letter of Ac-
ceptability should have been terminated for the con-
venience of the Government and the $25,000.00 bid
deposit returned to Anthony Grace & Sons, Ine,
I request that this Notice of Appeal, as previously
set forth in my letter dated October 7th, 1959 be
processed in accordance with the Rules of the Armed
Services Board of Contract Appeals. Upon receipt of
Notice of Docketing I will file a formal Bill of Com-
plaint.
I sincerely request that this appeal be expedited in
— that a hearing be held at the earliest possible
te.
By letter dated December 22, 1959, the procurement
contracting officer advised plaintiff that Mr. Robinson had
been acting in his behalf in regard to cancellation of the
commitments and that he agreed with the action taken by
Mr. Robinson,
The letter of December 16, 1959, to the Secretary of the
Air Force from plaintiffs counsel was docketed by the
[fol. 212] Armed Services Board of Contract Appeals on
December 31, 1959. Thereafter, the government moved to
dismiss the appeal on the grounds that Mr. Robinson’s
letter of October 1, 1959, canceling the commitments un-
dertaken with plaintiff, was “an appealable decision” ;
and, that no written appeal was taken from that letter
or from Mr. Robinson’s letter of October 19, 1959, within
30 days, as provided by paragraph 2 of the letter of ac-
ceptability.
Plaintiff contended before the Board that the letter of
October 1, 1959, from Mr. Robinson was not a final de-
cison within the “disputes clause” (paragraph 2) of the
letter of acceptability, but that, nevertheless, the letter of
October 7, 1959, from plaintiff’s counsel did constitute an
appeal; that the only correspondence from the government
which constituted an appealable decision within the dis-
putes clause was the letter from Mr. Robinson of October
19, 1959, and that since that letter was not received until
December 8, 1959, the letter of December 16, 1959, from
plaintiff’s counsel containing the appeal notice was timely.
Plaintiff also contended that Mr. Robinson, the deputy
special assistant for installations, who signed pertinent
letters on defendant’s behalf was not the contracting
officer for the purposes of the disputes clause, and that
plaintiff had already filed its appeal by the time the con-
tracting officer had, by his letter of December 22, 1959,
made his decision.
The Board concluded that the letter of October 1, 1959,
from Mr. Robinson constituted an appealable decision and
85
was at the time so regarded by plaintiff; and that the
letter of October 7, 1959, from plaintiff’s counsel did not
contain “a then present intent * * * to invoke the right
of appeal,” and, hence, did not constitute an appeal with-
in the disputes clause. Since the December 16, 1959, letter
from plaintiff’s counsel containing the appeal notice was
after the period of 30 days from the October 1, 1959,
letter, the Board found that the appeal was not timely.
Regarding the status of Mr. Robinson, the Board stated in
effect that he had been “the Government’s representative
in all dealings of legal consequence between the parties,”
had signed the invitation for bids, the letter of accepta-
bility, and various other pertinent letters, including the
letter from which plaintiff contended it had appealed, and
([fol. 218] that the contracting officer “was at all times
a virtual stranger” to plaintiff.
Accordingly, the Board, on June 29, isp
0, granted the
government’s motion and dismissed the ap
eal.
(1960) ; Beacon Construction Co. v. United States, 314
F, 2d 501 (Ct. Cl. 1963) ; WPC Enterprises, Incorporated
v. United States, 323 F. 24 874 (Ct. Cl. 1963); Stein
Bros. Mfg. Co. v. United States, 337 F. 2d 861 (Ct. Cl.
1963) ; Wingate Construction Co. v. United States, No.
394-60 Ct. Cl., January 24 1964,
The parties are agreed that the governing provisions of
the contract documents regarding an appeal appear in
paragraph 2, the “disputes clause,” of the letter of ac-
ceptability which, though heretofore set forth, bears re-
peating for closer examination, as follows:
2, Failure to perform all obligations prior to the
time prescribed for closing will be just cause for can-
celling all commitments undertaken with you in con-
nection with the housing project and for the recovery
under your bid security of liquidated damages in the
sum of $25,000, together with actual damages to the
Department, such actual damages to be itemized and
determined by the Contracting Officer, whose decision
will be reduced to writing and furnished to you by
mail or otherwise. Such decision shall be final and
conclusive unless, within 30 days from the receipt
thereof, you appeal in writing to the head of the De-
partment or his duly authorized representative, and
his decision shall, unless determined by a court of
competent jurisdiction to have been fraudulent or
capricious or arbitrary, or so grossly erroneous as
necessarily to imply bad faith, or not supported by
(fol. 214] substantial evidence, be final and conclusive.
In connection with any appeal under this paragraph
you will be afforded an opportunity to be heard and
to offer evidence in support of your appeal.
In light of the foregoing disputes clause, let us turn to
the pertinent language of the letter of October 1, 1959,
to plaintiff from Mr. Robinson to determine if there was
therein a “decision” which would become “final and con-
clusive” unless appealed from within 30 days. This per-
tinent language reads:
” * 7 7.
8. Accordingly, pursuant to paragraph 2 of the
letter of acceptability, the Department hereby cancels
all commitments undertaken with you in connection
with the housing project, reserving all its rights with
respect to the recorvery of damages.
A fair reading of the provisions of the disputes clause
compels the conclusion that the decision of the contracting
officer should include not only Janguage canceling the com-
mitments, but also languag« setting forth a conclusion
regarding recovery of the bid security and itemization of
such actual damages which the contracting officer deter-
mined should be recovered.
— ————————
87
It is clear from the pertinent language of the October 1,
1959, letter that all of the elements of a decision required
by the disputes clause are not present, because the only
reference to damages (whether liquidated or actual) is
that defendant was “reserving all its rights with respect
to the recovery of damages.” Upon reading this letter,
plaintiff could not tell whether defendant had decided to
recover liquidated damages, whether defendant was claim-
ing actual damages or in what amount, or even when de-
fendant expected to reach a conclusion as to liquidated
or actual damages. Conceivably, plaintiff could have con-
cluded that if there was to be no recovery sought by de-
fendant of liquidated damages or of actual damages, it
would be satisfied for the commitments to be caneeled and
would not appeal; but, plaintiff could not make an intelli-
gent determination on the matter from the contents of the
letter. It is concluded that the letter did not constitute a
“decision” within the disputes clause, even though, as
(fol. 215] defendant points, out, plaintiff in subsequent
correspondence did refer to the “decision” in the October
1, 1959, letter. Having reached this conclusion, it is un-
necessary to consider whether or not the letter of October
7, 1959, from plaintiff’s counsel requesting return of the
bid deposit and advising that plaintiff was “reserving all
of its rights with respect to recovery of damages” con-
stitutes an appeal, because the letter from plaintiff’s coun-
sel of December 16, 1959, which admittedly constituted an
appeal was within the 30-day period after the receipt
by plaintiff’s counsel on December 8, 1959, of defendant’s
letter of October 19, 1959. It is likewise unnecessary to
consider the question raised by plaintiff as to the status
Bc Robinson, the deputy special assistant for instal-
ations.
It is accordingly concluded that plaintiff did make time-
ly appeal and, therefore, did exhaust
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.