Appendix — United States v. Utah Construction and Mining Co
Supreme Court brief1965
Ask Donna
What actually matters in this document.
Text
Supreme Court of the United States
OCTOBER TERM, 1965
No. 440
UNITED STATES, PETITIONER
vs.
UTAH CONSTRUCTION AND MINING CO.
ON WRIT OF CERTIORARI TO THE UNITED STATES
COURT OF CLAIMS
INDEX
Original Print
Record from the United States Court of Claims
PIN sieictchationninsisstabibcidoel atlciedsdiniehcsidaneciiccgcbhis cine 1 1
Exhibit A—(Excerpts)—Articles 3, 4, 9,
15, 16(d), and GC-25 from Contract for
Construction between the United States
and Utah Construction Company, dated
BU NS hn aoe 20 15
INIT OI cst cersoens seb eidincociuss<etienies 26 19
Defendant’s amended answer ..................-00-0.-.--. 48 34
Commissioner’s order and memorandum re ap-
plicability of Bianchi decision —.......00........... 53 37
Exhibits to defendant’s supplemental brief
i 76 52
Concrete Aggregate Appeal No. 121—Part
1—Letter from Atomic Energy Commis-
sion to Utah Construction Company,
dated December 20, 1956 2.0.0.0... 76 52
ii INDEX
Original Print
Record from the United States Court of Claims—
Continued
Exhibits to defendant’s supplemental brief
(Excerpts )—Continued
Concrete Aggregate Appeal No. 121—Part
| Geeeiir shemales gic : iret CER ES 80 57
Brief of the contracting officer on
motion to dismiss Utah’s appeal for
its failure to make a timely pre-
sentation of its claim .............-.--------- 80 57
Decision of the Atomic Energy Com-
mission in Docket No. CA-121, Oc-
tober 1, 1959 ......-...--------------eerettete 87 64
Pier Drilling Appeal No. 87 -......-.--------------- 102 77
Memorandum of decision ..........-.---------- 102 77
Findings of fact and recommendation.. 103 78
Letters from Atomic Energy Commis-
sion to Utah Construction Company,
dated April 1, 1955, and April 19,
oi. onesanttinbanonnmemnverenivneontons 120 94
Shield Window Appeal No. 76 ......---------------- 125 99
Memorandum of decision .........-..---------- 125 99
Findings of fact and recommendation.. 126 100
Letter from Atomic Energy Commis-
sion to Utah Construction Company,
dated June 26, 1954 ...........-.---------+-- 148 121
Shield Door Appeal No. 95 .........------------------- 151 125
Memorandum of decision ...........-.--------- 151 125
Findings of fact and recommendation.. 152 126
Letter from Atomic Energy Commis-
sion to Utah Construction Company,
dated October 27, 1955 .........-..---------- 164 138
Opinion, Whitaker, J. ....---------------------- 167 142
Opinion, concurring, Cowen, Ch. Be cdcieiais 179 155
Opinion, concurring in part and dissenting in
a PATE, Davis, J. .--cceeccecescnneeeeeeeeeeeeeeeeeeceececeeennnnens 180 156
—~_ Order extending time to file certicrar 3... 188 164
Order allowing certiorari -...........------------------ee-rrrre 189 165
(foi. 1]
IN THE UNITED STATES COURT OF CLAIMS
No. 3-61
UTAH CONSTRUCTION AND MINING COMPANY, PLAINTIFF
vs,
THE UNITED STATES, DEFENDANT
PETITION—Filed January 6, 1961
1. Plaintiff, Utah Construction and Mining Company,
formerly and during the times hereir-mentioned known as
Utah Construction Company, is, ard at all times herein
pertinent was, a corporation organized and existing under
the laws of the State of Delaware, with its office and
principal place of business in the City and County of
San Francisco, State of California, now being located
at 550 California Street in said City and County.
2. On March 19, 1953, pursuant to competitive unit
price and lump-sum bids, plaintiffs was awarded and
entered into a contract with the defendant, acting by and
through the United States Atomic Energy Commission,
designated Contract No. AT (10-1) -645, under which plain-
[fol.2] tiff was to furnish the plant, equipment, labor and
materials and to perform the work, except as hereinafter
alleged, for the construction of a large assembiy and
maintenance area at the defendant’s National Reactor
Testing Station in Jefferson and Butte Counties, Idaho.
A copy of the contract, together with Advance Notice, In-
vitation No. AT (10-1) -645, Instructions to Bidders, plain-
tif’s bid, general conditions, special conditions, and per-
tinent drawings, schedules, specifications, addenda and
modifications are annexed hereto as Exhibit “A” and by
this reference made a part hereof.
3. In estimating its cost of the performance of the
work set forth in the plans and specifications, and the
addenda thereto, of said contract, and in submitting its
bid and entering into said contract for the performance
of such work, plaintiff relied on defendant’s express and
implied representations and warranties that:
(a) all work could be completed, at the latest, within
approximately one calendar year from the award of said
contract, or specifically, by March 30, 1954;
(b) all equipment and materials to be furnished by de-
fendant for the completion of said contract would be sup-
plied to plaintiff completely designated, tested, inspected,
and in a fit condition for installation or use at the respec-
tive times necessary to meet work schedules, and in the
ordinary and economical course of the performance of said
contract, and in accordance with the plans and specifica-
tions of said contract;
(ce) all specifications and plans, shop drawings and
models would be furnished at the respective times neces-
[fol. 3] sary to meet the work schedules, and in the ordi-
nary and economical course of the performance of said
contract;
(d) any and all decisions pertinent to changes or mate-
rial alterations of the required performance under said
contract would be made in a reasonable and prompt man-
ner, so as not to interfere unduly with plaintiff’s work
on said project, or to interfere with or preclude the ordi-
nary and economic course of the performance of said
contract;
(e) all plans and specifications, addenda thereto, and
modifications under said contract were intended and pre-
pared to produce a desired end-result, and were complete
and adequate to produce such desired end-result;
(f) all the information in defendant’s possession and
within its special knowledge concerning the conditions of
the job-site, and the materials and equipment to be fur-
nished by defendant was disclosed to all bidders, including
plaintiff ;
(g) the plans and specifications prepared by defendant
were complete, and not such as to mislead as to any item
of work covered by said contract;
(h) defendant would not cause plaintiff any delay in the
prosecution of its work, or protract the period of perform-
3
ance, or interfere in the performance of its work under
said control; and
(i) defendant would not make unreasonable, arbitrary
or excessive inspection demands, or arbitrarily or unrea-
sonably reject any of plaintiff’s completed work, or unduly
delay in approving completed phases of said contract.
[fol.4] 4. Plaintiff promptly commenced the perform-
ance of the contract work after receipt of defendant’s
Notice to Proceed, dated March 19, 1953, and during the
entire period of such performance under said contract,
defendant failed to perform in accordance with Said con-
tract, and its express and implied warranties and repre-
sentations; specifically, defendant did not formulate a de-
sired end-result prior to its Invitation to Bidders; defend-
ant did not prepare adequate plans and specifications for
tract, or for any end-result; defendant did not furnish
plans and specifications, shop-drawings, models, equipment
or materials in a timely manner, or in accordance with
work schedules, or in the ordinary and economical course
of the performance of said contract; defendant did not
furnish equipment or materials to plaintiff completely de-
signed, tested or inspected or in a condition fit for its
intended use; defendant did not disclose to plaintiff all
of its information concerning known job-site conditions
and government-furnished equipment and materials; de-
fendant did not make prompt or reasonable decisions with
respect to changes and materia] alterations of said con-
tract ; defendant interfered with and unnecessarily delayed
plaintiff in the prosecution of its work under said contract;
defendant arbitrarily, unreasonably and excessively de-
manded inspection of both plaintiff’s work in progress
and its completed work; defendant arbitrarily and unrea-
sonably rejected plaintiff’s work in progress and its com- ~
pleted work; defendant unreasonably and arbitrarily de-
layed approval of plaintiff’s completed work on said proj-
ect; and defendant intentionally misrepresented to plain-
(fol. 5] tiff that the contemplated work under said con-
tract, or subjectively contemplated by defendant, or the
desired end-result under said contract, or any end-result,
could be completed or produced within one calendar year.
a
4
5. As a result of defendant’s said misrepresentations
and failure to perform in accordance with said contract
and its implied and express warranties, plaintiff did not
complete its work on said project and under said contract,
the subsequent modifications and the change orders, num-
bering one-hundred thirty-six (136) in all, until on or
about January 7, 1955. All of plaintiff’s work required
by defendant on said project was completed within the
contract time as extended by defendant.
6. As a result of plaintiff’s detrimental reliance on said
defendant’s delays, misrepresentations and failures to per-
form in accordance with said contract and its implied and
express warranties, including, but not limited to, the acts
of defendant with respect to major phases of said contract,
hereinafter referred to, which independently and cumula-
tively constituted a breach of contract by defendant (sub-
paragraphs 7(a), (b), (ce), (d) and (e) herein), plaintiff
was obliged to pay increased excavation costs in the
amount of $17,734.63, added shield door costs in the
amount of $4,457.24, increased concrete finishing costs in
the amount of $109,356.00, added winter p.;otection costs
in the amount of $183,431.46, added administrative, over-
head and equipment costs in the amount of $216,717.63,
added labor costs in the amount of $79,844.18, and added
excessive inspection costs in the amount of $55,000.00.
None of the additional costs referred to herein would
[fol.6] have been incurred by plaintiff except for said
failures of defendant to perform in accordance with said
contract, representations and implied and express war-
ranties.
7. The delayed completion date of said contract, and
the increased costs to plaintiff herein referred to were due
in large part, but not limited to, the following acts of
defendant on the following specific phases of said con-
tract:
(a) Pier Drilling—Included in plaintiffs contract with
defendant, Exhibit “A” hereto, was the drilling and ex-
cavation for “piers” or foundation shafts for certain
building. to be constructed by plaintiff. In drilling the
shafts for the piers, plaintiff’s subcontractor encountered,
on or about June 1, 1953, conditions differing materially
«
5
from those indicated in the contract documents, namely,
“float rock” (individual rocks of various sizes, detached
from the principal bedrock by glacial or geological action
and subsequently covered by silt suspending such rocks
below the surface of the ground). Such changed condi-
tions delayed excavation procedures to such an extent that
plaintiff was forced to protect and perform subsequent
concrete work in inclement winter weather.
On or about February 18, 1955, plaintiff claimed addi-
tional compensation in the amount of $17,734,63 for the
extra costs of drilling said “float rock”. Defendant de-
nied said claim on April 1, 1955. On or about March 31,
1955, plaintiff claimed additional compensation in the
amount of $83,431.46 and a time extension of eleven
months for additional costs to cover winter protection
and performance resulting from the delayed excavation.
Defendant denied said claim on April 19, 1955.
[fol.7] On or about April 27, 1955, plaintiff appealed
from the above decisions to the Atomic Energy Commis-
sion’s Advisory Board on Contract Appeals, which found
that (1) the “float rock” encountered constituted a
“changed condition” within the meaning of Article 4 of
said contract, that (2) this condition caused some delay in
the drilling operation, (3) that no additional cost to plain-
tiff resulted from such changed condition, except insofar
as plantiff was liable over to its drilling subcontractor
(for which the Board recommended that the matter be
remanded to the Contracting Officer to determine) and
(4) that the excavation delay did not operate to delay
the pouring of concrete because such latter delay was due
primarily to a dispute over defendant’s failure to furnish
concrete aggregate of the quality specified in the contract
and such aggregate dispute was not before the Board in
the particular proceeding.
Defendant well knew, or should have known, of the
actual subsurface soil conditions and did in fact mislead
plaintiff and misrepresent such subsurface soil conditions.
Further, defendant did find that some delay was attribut-
able to the misleading specifications and misrepresenta-
tions prepared by defendant; however, defendant has not
compensated plaintiff for any of its increased costs as a
result thereof, namely (a) $17,934.63 for the additional
6
excavation work and for a fair and reasonable apportion-
ment of the total increased costs for added winter protec-
tion in the amount of $183,431.46, (b) added administra-
tive, overhead and equipment costs in the amount of $216,-
717.62, (c) added labor costs of $79,864.18, and (d) added
(fol. 8] excessive inspection costs of $55,000.00 attributa-
ble to such delay and failure to perform, to which plaintiff
is fully entitled. Plaintiff will ask leave of court to amend
this petition when the precise amount of such apportion-
ment has been determined.
(b) Concrete Aggregate—It was contemplated under
said contract and the specifications, that plaintiff would
pour approximately 18,000 cubic yards of concrete, On or
about July 17, 1958, defendant suspended plaintiff’s con-
crete mixing and pouring operations because of informa-
tion received by its Contracting Officer on the project that
the cement mixture being used was deficient in the
strength requirements as specified by the contract (Sec-
tion III, Division S-2). On or about July 21, 1953, de-
fendant’s Contracting Officer authorized resumption of
work “. . . pending an investigation and determination of
deficient strength requirements, . . .”
Subsequent tests revealed that the presence of small
sands, or “fines” in the concrete aggregate furnished by
defendant to plaintiff caused the deficient strength.
Thereafter, defendant undertook, through another con-
tractor, to clean the aggregate and remove such condition.
Further, defendant authorized plaintiff, at defendant’s
cost, to increase the corcrete mixture by one bag of ce
ment, thereby increasing the mixture to six, instead of
the originally specified five, bags of cement per cubic
yard. Such added bag of cement provided the necessary
strength, but increased plaintiff’s finishing costs.
On or about July 19, 1956, plaintiff presented a claim
to defendant’s Contracting Officer in the amount of $109,-
(fol. 9] 356.00 for additional costs incurred by plaintiff
due to defendant’s failure to furnish aggregate to meet
the specifications imposed by section S-2 as represented in
9C-18 of Exhibit “A” hereto, on the grounds that such
failure was a changed condition within the meaning of
Article IV of said contract.
7
Said Contracting Officer denied said claim on the
grounds that plaintiff’s claim was for breach of contract
or unliquidated damages and hence not within his juris-
diction. On appeal, Docket N 0. CA-121, Decision dated Oc-
aid plans and specifications, plaintiff was forced to pour
ement in severe and inclement winter weather at greatly
183,431.46, (b) added administrative, overhead and
yuipment costs in the amount of $216,717.63, (c) added
bor costs in the amount of $79,844.18, and (d) added
‘cessive inspection costs in the amount of $55,000.00
tributable to such delay and failure to perform. Plaintiff
ill ask leave of court to amend this petition when the
ol. 10] precise amounts of such apportionment have been
termined.
(c) Shield Doors—On or about May 12, 1953, plaintiff
cessary to the completion of the shield door installation
required by the plans and specifications. In accordance
th such plans and specifications, plaintiff submitted ven-
rs shop drawings to defendant on or about July 11,
53 for the intended purpose of determining whether the
yposed products were within the limits of contract spe-
cations. Defendant determined that certain features not
bearing on contract drawings should be added, namely,
cific finish requirements, stee] content, and specific ar-
igement and location of shield-door drive units,
Jefendant’s insistent imposition of additiona] design in-
mation and ultimate partial withdrawal and reversal
uch action on October 26, 1953, delayed a firm commit-
8
ment to said vendors from July until November 8, 1953.
Due to such delay on or about February 17, 1954, plain-
tiff was forced to postpone the pouring of concrete shield
doors, as well as the necessary concrete on the buildings’
and structures affected thereby, until June, 1954, or a
total of four months delay. Such delay in turn delayed
all phases of work, including, but not limited to, the Shield
Window and Amercoat Paint delays hereinafter referred
to.
On or about October 29, 1955, defendant’s Contracting
Officer denied plaintiff’s claim for extra work and delay
resulting from defendant’s inadequate plans, specifications
and shop drawings with respect to shield doors. On or
(fol. 11] about November 8, 1955, plaintiff appealed to the
Atomic Energy Commission’s Advisory Board on Contract
Appeals. Said Board of Appeals, in Docket No. 95, Find-
ings of Fact and Recommendations dated April 25, 1957,
upheld said Contracting Officer’s denial on the grounds
that added costs of work arising from the necessity of
completing inadequate design, plans, specifications or
drawings were not “changes” within the meaning of
Article III of said contract.
Plaintiff is entitled to recover from defendant all costs
resulting from defendant’s failure to furnish adequate
and complete plans and specifications, as well as its fail-
ure to disclose all facts within its knowledge, namely,
direct costs of extra work in the amount of $4,457.24 and
a fair and reasonable apportionment of (a) added winter
protection costs of $183,431.46, (b) added administrative,
overhead and equipment costs of $216,717.68, (c) added
labor costs of $79,844.18, and (d) added excessive inspec-
tion costs of $55,000.00 attributable to such delay and fail-
ure to perform. Plaintiff will ask leave of court to amend
this petition when the precise amount of such apportion-
ment has been determined.
(d) Shield Windows—Pursuant to a letter of intent
issued by defendant to plaintiff in June, 1953, and Modi-
fications No, 2 and No. 4 of Exhibit “A” hereto, plaintiff
negotiated a contract with Corning Glass Works, under the
general direction of defendant, for the procurement of
shield windows, which were originally to be furnished
plaintiff by defendant for installation in the structure
designated in said contract as Building No. 607. As the
(fol. 12] result of defendant’s insistence, the following
language was inserted in plaintiff’s contract with Corn.
ing Glass Works:
(1) “All glass supplied will conform to the re-
quired specifications as tested and approved by the
Argonne National Laboratory.”
(2) “It is understood and agreed that all compo-
nents and assemblies of the shield windows are sub-
ject to the inspection of authorized Government repre-
sentatives in manufacturer’s plant and at site,”
(3) “The Corning Glass Works shall submit shop
drawings and samples . . . as required in sufficient
time to allow for processing and final approval to
preclude the possibility of delaying job progress.”
representatives and rejected all Type II windows. The
rejected glass was returned to Corning Glass Works on
or about July 9, 1954,
10
Corning Glass Works maintained that the glass in ques-
tion was within the tolerances established by defendant’s
plans and specifications and appealed to the Director of
Reactor Branch, United States Atomic Energy Commis-
sion for competent unbiased inspection. Such an inspec-
tion was conducted and, on or about February 1, 1955,
defendant reversed its decision and plaintiff was allowed
to proceed with its work after a further delay of 35 days.
On or about August 12, 1954, defendant discovered that
the mineral oils in one of the installed Type I windows
had acquired a cloudy haziness. On or about August 16,
1954, Corning Glass Works advised defendant, by letter,
that such cloudy condition had been encountered in other
locations and that it had been determined that the condi-
tion could be eliminated by de-colorizing the oil. Despite
this information defendant, on or about September 2, 1954,
rejected Type I windows, without inspection or testing,
on the ground that moisture in the windows was causing
the cloudiness. Defendant made no effort to test the oil
and determine whether actualities or prejudice was the
basis of its rejection until October 15, 1954, or 43 days
after the September 2, 1954 rejection. It was not until
October 26, 1954, or 105 days after the cloudy oil was first
[fol. 14] noted, that defendant’s representatives verbally
notified plaintiff that defendant’s rejection was erroneous
and that the cloudy oil was not plaintiff’s responsibility.
Installation of Type I.windows was completed five days
later.
Plaintiff presented a claim, undey Article IV of said
contract, to defendant’s Contracting Officer for the extra
work and costs of delay resulting from defendant’s erro-
neous, arbitrary, unreasonable and excessive inspection
and rejection, which was denied by said Contracting Offi-
cer on or about June 26, 1954. On or about June 26, 1954,
plaintiff appealed to the Atomic Energy Commission’s
Advisory Board on Contract Appeals and the Board, in
Docket No. 76, by Findings of Ract and Recommendation
dated July 23, 1957, found that plaintiff could not exercise
much, if any, discretion with respect to the procurement
of materials for the windows; that plaintiff, in assuming
defendant’s initial responsibilities under said contract at
il
defendant’s request, received no assistance from defend-
ant in the difficulties encountered with shield windows;
that the “modus operandi on changes and shop drawings
was not calculated to assure a maximum expedition ;” that
plaintiff performed to the best of its ability; that plaintiff
was “subjected to delays that were not of its making.”
Said Board allowed an extension of time under said con-
tract to November 2, 1954, plus such additional time neces-
sary to complete operations dependent upon window in-
stallation, but denied plaintiff’s claim for increased costs.
In addition to said extension of time, plaintiff is entitled
to a fair and reasonable apportionment of the (a) added
(fol. 15] winter protection costs of $183,431.46, (b) added
administrative, overhead and equipment costs of $216,-
717.63, (c) added labor costs of $79,844.18 and (d) added
excessive inspection costs of $55,000.00 attributable to
such delay and failure to perform. Plaintiff wil] ask leave
of court to amend this petition when the precise amount
of such apportionment has been determined.
(c) Amercoat Paint—In March of 1954, plaintiff dis-
covered that government furnished materials for the “hot
shop”, namely, top and bottom guide rails, four travelling
boom systems and miscellaneous items of machinery, were
of (1) questionable quality and (2) rust and mill scale
had not been removed before a factory coat of paint had
been applied, and (3) improper crating caused consider-
able transit damage.
Defendant directed plaintiff to perform the necessary
removal of rust and mill scale and to paint all govern-
ment furnished materials or equipment, including shield
doors, in the “hot shop” with “Amercoat”. Plaintiff
proceeded with such work, under protest, maintaining that
defendant’s painting specifications made no mention of
“Amercoat” paint being required on anything but the
walls of the “hot shop”. Plaintiff suspended and post-
poned the pouring of concrete in the “hot shop” until
May, 1954, dismantled assembled shield doors, sand-blasted
all surfaces and applied the “Amercoat” paint as re-
quested by defendant.
Defendant advised plaintiff in June, 1954 that shield
doors were “movable walls”, and hence within the paint-
2
12
ing specifications prepared by defendant. On or about
[fol. 16] December 6, 1954, after eight months of delay,
successor representatives of defendant reversed the earlier
decision of April, 1954, and agreed to a settlement formula
with respect to the added direct costs of the additional
required painting.
Plaintiff, in addition to such added direct costs, is
entitled to recover a fair and reasonable apportionment
of the total increase in (a) winter protection costs of
$183,431.46, (b) added adminisirative, overhead and
equipment costs of $216,717.63, (c) added labor costs of
$79,844.18, and (d) added excessive inspection costs of
$55,000.00 attributed to such delay and failure to perform.
Plaintiff will ask leave of court to amend this petition
when the precise amount of such apportionment has been
determined.
8. Plaintiff estimates that ninety per cent (90%) of
the aggregate of said additional costs referred to in para-
graphs 6 and 7 hereof were due to defendant’s delays
and failures to perform in accordance with said contract,
representations and implied and express warranties, on
the phrases of said project specified in sub-paragraphs
7(a), (b), (c), (d) and (e); therefore, plaintiff incorpo-
rates herein by reference said sub-paragraphs as the
major, aggragated, serious, independent and specific fail-
ures by defendant to perform in accordance with said
contract, representations, and implied and express war-
ranties.
9. Subsequent to the award by defendant on March 19,
1953, of said contract, Exhibit “A” hereto, and thereafter,
during the entire course of plaintiff’s work, including, but
(fol. 17] not limited to, the above five phases of said proj-
ect (sub-paragraphs 7(a), (b), (c), (d) and (e) herein),
and continuing until the work was completed and accepted
on January 7, 1955, defendant failed to make necessary
corrections relating to design and general arrangement, or
to pass upon shop drawings with reasonable promptness
in accordance with said contract.
On or about April 15, 1958, defendant’s Architect-
Engineer directed plaintiff to forward shop drawings for
approval to Los Angeles, California. Plaintiff objected
13
to such procedure on the grounds that the specifications
called for inspection by the defendant, presumably at the
job-site, and that such procedures would cause delay. On
or about April 27, 1958, defendant modified the Architect-
Engineer’s above direction and instructed plaintiff to sub-
mit shop drawings to the Architect-Engineer at Idaho
Falls, Idaho. This modified procedure compounded the
delays anticipated earlier by plaintiff since the Architect-
Engineer submitted such shop-drawings to its office in
Los Angeles, California, in spite of defendant’s modifica-
tion of April 27, 1953, and added a transmittal link in the
procedure for the submission and approval of shop-draw-
ings. During the entire course of plaintiff’s work there
was a five to seven week elapse of time between shop-
drawing submittal by plaintiff and approval by defendant
resulting in a four-month over-all delay on the project.
Defendant’s failure to promptly pass upon shop-drawings
was due partly to its lack of supervision and qualified
personnel at the job-site, necessitating transmittal of such
drawings to the Architect-Engineer’s main office in Los
(fol. 18] Angeles, California, and in large part, to inade-
quate specifications for which a desired end-result, if any,
could not be obtained by alteration of such drawings with-
out making in effect, major and material changes, alter-
ations and additions to such plans and specifications by
unreasonably, arbitrarily and excessively imposing on
plaintiff added design responsibility and extra work.
Defendant well knew at the time that it awarded said
contract to plaintiff that its end-result, as represented in
said contract, was not the end-result it would ultimately
desire; and, further, defendant well knew that the state-
ment of work and plans and specifications for this entire
project were not, as represented, adequate for producing
the end-result represented in said contract, or any end-
result which defendant desired.
As a result of defendant’s failure to formulate a de-
sired end-result prior to the award to plaintiff of said
contract, and, as a result of defendant’s failure to prepare
ad2quate plans and specifications for the construction and
completion of the end-result represented in said contract,
or aly end-result, and as a result of defendant’s attempt
to fcrmulate and carry out the actual end-result during
14
the course of plaintiff's work by imposing additional de-
sign and extra work through shop-drawing procedures,
said contract became, in effect, a nullity, and plaintiff was
obliged to incur actual costs of $6,415,858.75 for the com-
pletion of said contract, or $1,100,965.23 in excess of the
contract price of $5,314,893.52. .
10, No one other than the plaintiff is the owner of the
claims herein and no assignment or transfer of the same
[fol. 19] has been made, No other action has been had on
said claim in Congress, or by any of the departments ex-
cept as herein alleged, and plaintiff is justly entitled to
the amounts herein claimed from the United States, after
allowing all just credits and set offs.
WHEREFORE, plaintiffs prays (1) that said contract
be rescinded and declared null and void, and demands
judgment for its actual costs of performance on said proj-
ect in the amount of $6,415,858.73 plus a reasonable profit
of six per cent (6%) or a total of $6,800,809.73, less the
actual amount paid under said contract, $5,314,893.52, or
a total sum due of $1,485,916.21; or, alternatively, plain-
tiff demands judgment in the amount of $666,541.15 for
defendant’s delays on said project; or, alternatively, plain-
tiff demands judgment for ninety per cent (90%) of said
defendant’s delays occurring on the herein described ma-
- ~ of said contract, namely, the sum of $590,-
3.02.
/s/ Gardiner Johnson
111 Sutter Street,
San Francisco 4, California
Attorney for Plaintiff.
THomas E, STANTON, JR.,
CHARLES J, HEYLER,
Of Counsel,
15
' (fol. 20}
EXHIBIT A TO PETITION (EXCERPTS)
CONTRACT FOR CONSTRUCTION
This Contract, entered into this 19th day of March,
1953, by THE UNITED STATES OF AMERICA, here-
inafter called the Government, represented by the contract-
ing officer executing this contract, and UTAH CON.
STRUCTION COMPANY, a corporation organized and
existing under the laws of the State of Utah, of the city
of Salt Lake City in the State of Utah, hereinafter
called the contractor, witnesseth that the parties hereto
do mutually agree as follows:
(fol. 21]
e . . .
ARTICLE 3. Changes.—The contracting officer may at
any time, by a written order, and without notice to the
sureties, make changes in the drawings and/or specifica-
tions of this contract and within the general scope there-
of. If such changes cause an increase or decrease in the
amount due under this contract, or in the time required
for its performance, an equitable adjustment shall be
made and the contract shall be modified in writing accord-
ingly. Any claim for adjustment under this article must
be asserted within 10 days from the date the change is
ordered: Provided, however, That the contracting officer,
if he determines that the facts justify such action, may
receive and consider, and with the approval of the head
of the department or his duly authorized representative,
adjust any such claim asserted at any time prior to the
date of final settlement of the contract. If the parties
fail to agree upon the adjustment to be made the dispute
shall be determined as provided in Article 15 hereof. But
nothing provided in this article shall excuse the contrac-
tor from proceeding with the prosecution of the work so
changed,
ARTICLE 4, Changed conditions.—Should the contractor
encounter, or the Government discover, during the pro-
gress of the work subsurface and/or latent conditions at
16
the site materially differing from those shown on the
drawings or indicated in the specifications, or unknown
conditions of an unusual nature differing materially from
those ordinarily encountered and generally recognized as
inhering in work of the character provided for in the
plans and specifications, the attention of the contracting
officer shall be called immediately to such conditions be-
fore they are disturbed. The contracting officer shall
thereupon prompty investigate the conditions, and if he
finds that they do so materially differ the contract shall
be modified to provide for any increase or decrease of
cost and/or difference in time resulting from such con-
ditions.
"fol, 22]
* * * ”
ARTICLE 9. Delays—Damages.—-If the contractor re-
fuses or fails to prosecute the work, or any separable
part thereof, with such diligence as will insure its com-
pletion within the time specified in article 1, or any ex-
tension thereof, or fails to complete said work within
such time, the Government may, by written notice to
the contractor, terminate his right to proceed with the
work or such part of the work as to which there has
been delay. In such event the Government may take over
the work and prosecute the same to completion, by con-
tract or otherwise, and the contractor and his sureties
shall be liable to the Government for any excess cost
occasioned the Government thereby. If the contractor’s
right to proceed is so terminated, the Government may
take possession of and utilize in completing the work
such materials, appliances, and plant as may be on the
site of the work and necessary therefor. If the Govern-
ment does not terminate the right of the contractor to
proceed, the contractor shall continue the work, in which
event it will be impossible to determine the actual dam-
ages for the delay and in lieu thereof the contractor shall
pay to the Government as fixed, agreed, and liquidated
damages for each calendar day of delay until the work is
completed or accepted the amount as set forth in the
specifications or accompanying papers and the contractor
17
and his sureties shall be liable for the amount thereof:
ided, That the right of the contractor to proceed
shall not be terminated or the contractor charged with
* * * *
(fol. 23]
” * * *
ARTICLES 15, Disputes.—Except as otherwise specifi-
cally provided in this contract, all disputes concerning
questions of fact arising under this contract shall be
decided by the contracting officer subject to written appeal
by the contractor within 30 days to the head of the
department concerned or his duly authorized representa-
tive, whose decision shall be final and conclusive upon the
parties thereto. In the meantime the contractor shall
diligently proceed with the work as directed,
ARTICLE 16, Payments to contractors,—* * *
a
18
(d) Upon completion and acceptance of all work re-
quired hereunder, the amount due the contractor under
this contract will be paid upon the presentation of a
properly executed and duly certified voucher therefor,
after the contractor shall have furnished the Government
with a release, if required, of all claims against the Gov-
ernment arising under and by virtue of this contract,
other than such claims, if any, as may be specifically
excepted by the contractor from the operation of the
release in stated amounts to be set forth therein.
(fol. 24] 11/17/52
SPECIFICATIONS FOR CONSTRUCTION CONTRACT
GENERAL CONDITIONS
e * * *
F (fol. 25] ‘ =
GC-25 SUSPENSION OF WORK. The Commission
may by written order direct the Contractor to
suspend all or any part of the work for such
period of time as may be determined by the
Commission to be necessary or desirable for the
convenience of the Government. If such suspen-
sion delays the progress of the work and causes
additional expense or loss to the Contractor in
the performance of the work, not due to the fault
or negligence of the Contractor, the Commission
shall make an equitable adjustment in the con-
tract price and time of performance and modify
the contract accordingly; Provided, however,
that no adjustment will be made under this
article for suspensions ordered under any other
article of the contract or provision of the speci-
fications; and provided further, that any claim
for adjustment hereunder must be asserted with-
in 80 days from the date such suspension is
ordered. If the parties fail to agree upon the
adjustment to be made, the dispute shall be de-
termined as provided in the article of this con-
tract entitled “Disputes”.
* * * «
(fol. 26]
IN THE UNITED STATES COURT OF CLAIMS
No, 3-61
[Title Omitted]
DEFENDANT'S ANSWER—Filed November 1, 1961
As and for its answer herein defendant alleges as fol-
lows:
1. Defendant’s attorney does not have knowledge or in-
formation sufficient to form a belief as to the truth of the
allegations contained in paragraph 1 of the petition, and
defendant therefore denies them,
2. Defendant admits the allegations contained in para-
graph 2 of the petition except the defendant refers to all
allegations contained in paragraph 3 of the petition, and
defendant therefore denies them,
4, Answering paragraph 4 of the petition defendant
fendant admits that the work under the contract was
completed on or about January 7, 1955, and that the work
Defendant further alleges that any claims based on extra
work are irrelevant, immateria] and outside the Scope of
plaintiff’s claim filed herein for breach of contract, (See
page 5, items numbers 7 and 8 in plaintiff’s objection to
defendant’s motion for more definite statement filed here-
in September 27, 1961.)
7. Defendant denies the allegations contained in the
first. sentence of paragraph 7 of the petition.
7(a) Defendant admits the allegations contained in the
first sentence of subparagraph (a) of paragraph 7 of the
petition. Defendant denies the remaining allegations
contained in the first paragraph of subparagraph (a)
of paragraph 7. Defendant further alleges that plaintiff
never made any claim for “float rock” during the time
of the performance of the contract.
Defendant admits the allegations contained in the sec-
ond paragraph of subparagraph (a) of paragraph 7 of
the petition.
(fol. 28] Answering the third paragraph of subpara-
graph (a) which begins “On or about April 27,” defend-
ant admits that plaintiff took an appeal to the Atomic
Energy Commission’s Advisory Board on Contract Ap-
peals and that that Board in Docket No. 87 heard the
appeai, and rendered a decision. Defendant refers to this
decision of that Board for a complete statement of the
decision of the Board. Defendant further alleges that
there is no allegation contained in the petition that this
decision was arbitrary, capricious, or not supported by
substantial evidence.
Defendant further alleges that any discussion based on
“changed conditions” is irrelevant, immaterial and out-
side the scope of this cause of action for a breach of
contract. (See page 5, items numbers 7 and 8 in plain-
tiff’s objection to defendant’s motion for more definite
statement filed herein September 27, 1961.)
Defendant denies the allegations contained in para-
graph 4 of subparagraph (a) of paragraph 7 of the peti-
tion which begins “Defendant well knew, or should have
known,”. Defendant incorporates by reference herein its
allegations made in paragraph 6 of this answer concerning
the irrelevance and immaterially of claims based on extra
work under plaintiff’s breach of contract theory. Defend-
ant further specifically denies that plaintiff is entitled
to receive any sum from the defendant.
21
Answering the second paragraph of 7(b) of the petition
defendant admits that there were fines in the concrete ag-
gregate furnished by the defendant to the plaintiff. De-
fendant denies that the fines in the concrete aggregate
Answering the third paragraph of 7(b) of the petition
which begins “On or about J uly 19, 1956,” defendant ad-
mits that plaintiff presented this claim to the Contracting
Officer long after all of the work under the subject con-
trace was completed.
Answering paragraph 4 of paragraph 7( b) of the peti-
tion which begins “Said Contracting Officer” defendant
admits that the Contracting Officer denied the claim and
further admits that the plaintiff took an appeal (Docket
No. CA-121) to the Contract Appeals Board and that
the decision rendered on that appeal denied the plaintiff’s
(fol. 30] claim. Defendant refers to the Contracting Offi-
cer’s decision and to the decision of the Hearing Examin-
er for a complete statement of these decisions,
Defendant further alleges that there is no allegation
contained in the petition that this decision by the Hearing
Examiner was arbitrary, capricious or not supported by
a
substantial evidence. Defendant further alleges that
plaintiff did not petition the Atomic Energy Commission
for a review of the Hearing Examiner’s decision even
though it had a right to petition for this review under
the terms of the applicable regulations for administrative
remedies, Defendant further alleges that under these
same regulations in the absence of such a petition for
review, the decision of the Hearing Examiner became
the final action of the Commission sixty days after it was
rendered,
Defendant denies the allegations contained in para-
graph 6 of subparagraph 7(b) which begins “Due to the
delays”. Defendant further incorporates herein by refer
ence its allegations contained in paragraphs 6 and 7 of
this answer at pages above concerning the irrele
vance and immateriality of claims based on extra work
and changed conditions under plaintiff's theory of breach
oi contract.
Tic) Defendant's attorney does not have knowledge
or information sufficient to form a belief as to the truth of
the allegations contained in the first sentence of para-
graph 7(c) of the petition and defendant therefore de-
nies them. Defendant denies the remaining allegations
contained in the said paragraph, :
Defendant denies the allegations contained in the second
paragraph of subparagraph 7(c) of the petition.
[fol. 81} Answering the third paragraph of subpara-
graph 7(c) of the petition which begins “On or about
October 29, 1955,” defendant admits that plaintiff's claim
was denied by the Contracting Officer, and that the
Atomic Energy Commission's Advisory Board on Contract
Appeals in a decision dated April 25, 1957 (Docket No.
95) upheld the Contracting Officer’s denial. The defend-
ant refers to the Contracting Officer’s decision and to the
Roard decision for a complete statement of these decisions,
Defendant further alleges that there is no allegation
contained in the petition that the decision of the rd
was arbitrary, capricious or not supported by substantial
evidence,
Defendant denies the allegations contained in paragraph
4 of subparagraph 7(c) of the petition which begins
_ .
“Plaintiff is entitled” and specifically denies that plaintiff
is entitled to recover any sum from the defendant, De-
fendant incorporates herein by reference its allegations
contained in paragraphs 6 and 7 at pages above
concerning the irrelevance and immateriality of claims
7(d) Defendant admits the allegations contained in
the first sentence of paragraph 7(d) of the petition, Fur
ther answering the said subparagraph, defendant admits
that the quoted la age from the plaintiff's contract with
Corning Glass Works Which is set out at the top of
12 of the petition appears in that contract. Defendant
(fol. 832] denies that the language appears in the contract
as a result of defendant’s insistence, Defendant refers
to the plaintiff's entire contract with Corning Glass
— for a complete statement of its terms and con-
itions,
Defendant denies the allegations contained in the second
paragraph of subpa eraph 7(d). Defendant further
alleges that substantially all of the diagrams, specifica-
tions and shop drawings for the windows had been ap-
proved on a date prior to December 80, 1958 when the
plaintiff finally entered into the negotiated price
ment with the defendant for the installation of the shield
windows. Accordingly, any costs for delays on account
of approval of the shop drawings which occurred prior
to the time the plaintiff entered into this negotiated agree-
ment were, or should have been, included in the price
es — the ee ee in the third
paragrap sudparagraph 7(d) of the petition which
begins “On or about February 18, 1954”,
dant denies the allegations contained in para-
graph 4 of subparagraph 7(d) of the petition, and de.
fendant further alleges that the work under this contract
was completed on or about January 7, 1955 as plaintiff
alleges in paragraph 5 of the petition,
Answering the first Sentence of paragraph 5 of sub-
paragraph 7(d) defendant alleges that defendant and
24
representatives of the plaintiff discovered the cloudy
haziness in one of the shield windows. Answering the
[fol. 33] second sentence of the said paragraph defendant
admits that it received a letter concerning this condition
from the Corning Glass Works and refers to that letter
for a statement of its contents. Defendant denies the
third sentence of the said paragraph and specifically de-
nies that it rejected the windows. Defendant alleges that
its representative advised the plaintiff that it would be
proceeding with the installation of the windows at its own
risk if it installed them prior to the time that the matter
of the haze condition was cleared up. Defendant denies
the allegations contained in the fourth sentence of the
said paragraph. Defendant denies the allegations con-
tained in the fifth sentence of the said paragraph and
specifically denies that any delay in the installation of the
windows held up any of the other contract work which
remained to be done. Answering the last sentence of the
said paragraph defendant admits that practically all of
the work of the installation of the Type I shield windows
had been completed prior to the time that the hazy condi-
tion was discovered and that this work was entirely com-
pleted shortly after plaintiff recommenced it.
Answering paragraph 6 of subparagraph 7(d) defend-
ant admits that the plaintiff presented a claim to the Con-
tracting Officer and that after the denial of this claim
the plaintiff appealed to the Atomic Energy Commission’s
Advisory Board on Contract Appeals. Defendant further
admits that in Docket No. 76 the Board decided that the
plaintiff was entitled to an extension of time but was not
entitled to any extra compensation. Defendant refers to
[fol. 34] the decisions of the Contracting Officer and the
Board for a complete statement of these decisions.
Defendant further alleges that there is nothing in the
plaintiff’s petition which alleges that the said decision
of the Board was arbitrary, capricious or not supported
by substantial evidence.
Defendant denies the allegations contained in the last
paragraph of subparagraph 7(d) which begins “In ad-
dition to said extension of time” and specifically denies
that plaintiff is entitled to receive any sum from the de-
25
fendant. Defendant incorporates herein by reference its
statements in paragraphs 6 and 7 at pages above
concerning the irrelevance and immateriality of claims
based on extra work and changed conditions under plain-
tiff’s theory of breach of contract.
7(e)* Defendant denies all of the allegations contained
in all of the paragraphs of the petition beginning with
numbered paragraph 7(e) and continuing down to para-
graph 8, ;
In clarification of these items of claim the defendant
deems it necessary to make the following allegations:
There were 3 claims by the plaintiff concerned with Amer-
coat Paint under this contract. One of these claims was
(fol. 35] tract in which plaintiff was again fully compen-
sated for that work. The third claim was on account of
the withholding of funds from the plaintiff by the defend-
ant because certain of the plaintiff’s Amercoat Paint work
cracked and peeled and had to be redone by another con-
tractor at defendant’s expense. This third claim was the
subject of a reservation in the release which was exe
cuted by the plaintiff and which is discussed in defend-
ant’s affirmative defense number I at page below.
This third claim was later also paid by the defendant.
Accordingly, all of the plaintiff’s claims for Amercoat
Paint have been fully paid and settled, and the only one
8. Defendant denies the allegations contained in para-
graph 8 of the petition.
* This paragraph is again marked in the petition (c) but probably
should be (e),
a
9. Defendant denies the allegations contained in the
first paragraph of numbered paragraph 9 of the petition.
Answering the second paragraph in numbered para-
graph 9 defendant admits that in order to save time de-
fendant’s Architect-Engineer directed plaintiff to forward
shop drawings for approval to its office at Los Angeles,
(fol. 36] California. Answering the second sentence of
the said paragraph defendant admits that the plaintiff
objected to this procedure on the ground, among others,
that under this arrangement it would have to pay the air
mail postage for the forwarding of the drawings. Defend-
ant refers to that letter for a full statement of its con-
tents. Defendant admits the allegations contained in the
third sentence of the said paragraph which ends with the
phrase “at Idaho Falls, Idaho”. Defendant further alleges
that in certain instances approval of shop drawings was
waived in order to expedite the work. Defendant denies
all of the remaining allegations contained in all of the re-
maining paragraphs of paragraph 9.
Defendant incorporates herein by reference its allega-
tions contained in paragraphs 6 and 7 above concerning
the irrelevance and immateriality of claims based on
extra, work and changed conditions under plaintiff’s theory
of breach of contract.
10. Defendant denies the allegations contained in the
first sentence of paragraph 10 of the petition. Defend-
ant’s attorney does not have knowledge or information
sufficient to form a belief as to the truth of the allega-
tions contained in the remainder of paragraph 10 of the
petition, and defendant therefore denies them. Defend-
ant further specifically denies that the plaintiff is due
any sum from the defendant.
11. Defendant denies each and every allegation con-
tained in the petition including those in the Wherefore
en which are not specifically admitted or qualified
erein.
(fol. 37] AFFIRMATIVE DEFENSES
I. Release
12. In a release dated March 22, 1957, plaintiff herein
released the Government from all claims arising under, in
27
Amercoat appeal.
Subsequent to the execution of this release, defendant
paid the plaintiff the sum of $5,606.39 in settlement of the
Amercoat Paint appeal. Accordingly, all claims under
this contract except those for shield windows, pier drilling,
shield doors and concrete aggregate are forever released.
Consequently, in so far as any claims in plaintiff’s peti-
tion relate to or arise in connection with any matters
except the shield windows, pier drilling, shield doors, and
concrete aggregate, these claims are barred by the said
release,
II. Payments
pe) Concrete Aggregate And Related Claims (Pet.
7(b))
Defendant caused the aggregate to be cleaned, and on
March 20, 1954 paid plaintiff according to the account
which it had stated. This fulfillment by the defendant
of all of plaintiff’s requests as they were expressed in the
two letters of July 23 and 31, and the statement of ac-
count of February 9, including extra payment for gen-
eral expense constitutes a complete settlement of all Phases
of this claim.
28
(b) Amercoat Paint
By agreement of the parties in Contract Modification
20, items 4 and 7, plaintiff was fully compensated for all
of its claims based on Amercoat painting, cleaning, etc.
except for the claim which it reserved in the release.
Subsequent to the execution of the release, defendant also
paid that claim which had been reserved. Accordingly,
all of plaintiff’s claims based upon or arising in connec-
be with Amercoat Paint have been fully paid and satis-
ed.
III. Estoppel
14(a) Concrete Aggregate And Amercoat Paint
Defendant incorporates by reference here its allega-
tions contained in paragraphs 13(a) and (b) immediately
above. After statement of account or price negotiations
followed by payment, and the lapse of a considerable peri-
od of time, plaintiff is estopped from adding to the set-
[fol. 39] tled claims other alleged costs which are allegedly
based upon these settled claims.
(b) Shield Window Claim
Defendant incorporates here by reference its allega-
tions in paragraph 7(d) above concerning the fact that
at the time plaintiff entered into the negotiated price
agreement with defendant for installation of the shield
windows substantially all of the shop drawings had al-
ready been approved. Having entered into this negotiated
price agreement, plaintiff is estopped from now asserting
delay costs based on delivery of shop drawings which
occurred prior to the execution of the price agreement.
IV. Failure To Exhaust Administrative Remedies
15(a) Finishing And Other Costs Based On The Ap-
gregate Claim
More than one year after the work under the subject
contract was completed, plaintiff presented a claim con-.
cerning these alleged finishing and other-costs based on the
aggregate claim to the Contracting Officer. The Contract-
ing Officer denied the claim. Subsequently the Atomic
Energy Hearing Examiner held in Docket No. CA-121
that this late claim by plaintiff was untimely under the
29
[fol.40] (b) Pier Drilling (Docket No. 87)
On February 18, 1955
» approximately a month after
completion of the entire contract, plaintiff first presented
a claim for “float rock” in connection with pier drilling
for the foundation. Defendant alleges that this was an
untimely presentation of a claim which arose, if it arose
at all, at the very beginning of the contract in the Spring
of 1953.
Still later plaintiff presented a larger claim for ad-
ditional compensation and an extensij i i
whether or not plaintiff was thus actually liable to its
subcontractor,
After the matter was remanded to the Co
Officer, that officer wrote plaintiff in a letter dated July
(fol. 41] (ce) Amercoat Paint
Plaintiff never took an administrative appeal in con-
nection with the two items of its Amercoat Paint claim
which were settled by items 4 and 7 of Modification 20,
30
Accordingly, all claims based on these items are barred by
plaintiff’s failure to exhaust its administrative remedies
as well as by plaintiff's acceptance of payment in settle-
ment of these items.
(d) Dockets Numbers 76 and 95
These claims concerning shield windows and shield doors
were also remanded to the Contracting Officer for a deter-
mination of whether plaintiff was entitled to further ex-
tensions of time. Plaintiff was requested by letter dated
July 25, 1958 to notify the Contracting Officer if it wished
to proceed further in these matters, Plaintiff having re-
ceived extensions of time by contract modification did not
make such a request and accordingly it failed to exhaust
its administrative remedies in this regard. Therefore
any matters which were encompassed in these appeals
that appear in plaintiff’s petition are barred by its failure
to exhaust administrative remedies.
(e) Other Administrative Appeals
In addition to the administrative appeals which are dis-
cussed above, plaintiff herein began the processing of two
other appeals. These were Dockets Nos, 91 and 96 con-
cerning extensions of time, and a claim in connection with
generators.
The Atomic Energy Commission Advisory Board re-
manded these matters back to the Contracting Officer for
[fol. 42] further proceedings. The petition contains no
allegations that these decisions were arbitrary capricious
or not supported by substantial evidence. After the re-
mand, plaintiff abandoned the generator claim and never
requested further proceedings regarding the time ex-
tensions because it received sufficient extension by negoti-
ation. Accordingly, in so far as any matters contained in
the present petition are encompassed by these appeals
which plaintiff allowed to die such matters are barred in
this Court by plaintiff’s failure to exhaust available ad-
ministrative remedies.
V. Laches
16. (a) On February 18, 1955, more than a month
after the work under the subject contract was completed,
31
(b) Conerete Aggregate
On March 20, 1954, defendant paid plaintiff accovding
(fol. 43] to its statement of account for extra cement and
for supervision, genera] expense and profit in connection
therewith.
(ec) Shield Doors
Plaintiff did not present this claim until after the com-
pletion of the contract and accordingly defendant was pre-
vented from promptly investigating the situation and from
mitigating the damages, if there were any. Accordingly,
this claim should be barred by laches,
(d) Shield Windows
(1) Claim For Delay In The Delivery Of Shop Draw-
ings Which Occurred Prior To The Execution Of The
Negotiated Price Agreement. On December 30, 1953 plain-
tiff and defendant entered into a negotiated price agvee-
ment for the installation by plaintiff of the shield win-
dows. Defendant had a right to rely upon the fact that
the price which was fixed in this agreement took into ac-
count any prior damages and delays which the plaintiff
might have suffered in connection with the shield windows.
However, plaintiff later presented a claim based in part
upon alleged delays which occurred prior to the execution
(fol. 44] of the price agreement. This late presentation
of this portion of the claim damaged the defendant and
prevented its making a prompt investigation of the situa-
tion and mitigating damages, if there were any. Accord-
ingly, this claim should be barred by laches,
(2) Presentation Of A More Limited Claim Than The
One Which Is Presented Here. Even when the contractor
first presented this claim to the Contracting Officer (on
June 23 and 24, 1954) it only alleged three conditions
which were: lateral movement and distortion of the |
Koroseal gaskets under compression, specifications which
were too indefinite, and use of a selective assembly pro-
cedure in the assembly of the shield windows.
It was only later, during November 1955, at the Board
Hearing that plaintiff raised numerous other issues such
as revisions made under the contract, delays in submitting
drawings, etc. This delay in the presentation of these
various claims and issues by the plaintiff prevented the
defendant from promptly investigating the situation and
mitigating damages, if there were any. Accordingly, this
entire claim concerning shield windows should be barred
by laches.
(e) Amercoat Paint Claims
By payment of these various claims as alleged in para-
graph 13(b) above, defendant had a right to believe that
these claims were settled. Plaintiff by raising matters
based upon these claims at this late date has obviously
prevented the defendant from promptly investigating the
situation and mitigating damages, if any, which occurred
in connection with these new matters based upon the old
claims. Accordingly, these claims should be barred by
laches.
{fol.45] (f) Delay In The Presentation Of The Entire
laim
The work under this contract was completed on Janu-
ary 7, 1955. However, plaintiff waited 5 years and 364
days until January 6, 1961 before filing its petition in this
Court. This further delay in addition to those recited in
the foregoing paragraphs compounds defendant’s damage.
For defendant will obviously encounter considerably more
difficulty and will have to incur considerably more expense
in defending this action than would have been necessary
had the petition been filed promptly, or even within a
reasonable time after completion of the contract. This
is particularly true in a construction case such as this
where most of the contract workers scatter to other loca-
tions soon after the completion of the job. Five years and
364 days later they are considerably more diffiez!+ to lo-
cate, and their memories are less vivid than would have
been true had the petition been filed promptly. Accord-
ingly, this entire claim should be barred by laches,
VI. Equitable Estoppel
17. Defendant incorporates here by reference all of
paragraph 16 and all of its subparagraphs immediately
above except the last sentence in the paragraph and in
each subparagraph. Defendant substitutes the following
sentence in place of the last sentence in each instance.
“Accordingly, this claim should be barred by equitable
estoppel.”
(fol. 46] WHEREFORE, defendant prays that plaintiff’s
petition be dismissed.
/s/ William H. Orrick, Jr.
Assistant Attorney General
Civil Division
/s/ Melford O. Cleveland
Attorney, Civil Division
Department of Justice
(fol. 47] [File Endorsement Omitted]
(fol. 48]
IN THE UNITED STATES COURT OF CLAIMS
No. 3-61
[Titie Omitted]
DEFENDANT’S AMENDED ANSWER—Filed November 30,
1961
Pursuant to Rule 18(a) of the Rules of this Court de
fendant amends its answer as follows:
2. Paragraph 2 of defendant’s answer is deleted and
the following paragraph is substituted therefor:
2. Defendant admits the allegations contained in
paragraph 2 of the petition with the exception of the
phrase “except as hereinafter alleged”. Defendant
denies the allegations contained in this phrase. De-
fendant refers to all the contract documents and
drawings for an ascertainment of their contents.
7(b) Defendant substitutes the following sentence in
place of the second sentence in subparagraph 7(b) of its
answer:
Defendant admits that some of the concrete mixture
being used was deficient in the strength require-
ments as specified by the contract.
Defendant substitutes the following sentence in place of
the third sentence in the second paragraph of subpara-
graph 7(b) of its answer:
Defendant admits that it had fines removed from
some of the concrete aggregate.
[fol.49] 7(c) Defendant substitutes the following sen-
tence in place of the first sentence in the third para-
graph of subparagraph 7(c) of the petition:
Answering the third paragraph of subparagraph
7(c) of the petition which begins “On or about Oc-
tober 29, 1955,” defendant acmits that plaintiff's
claim which was in the sum of $4,457.25 for eleven
decision.
7(d) Defendant substitutes the following sentence in
place of the first sentence in subparagraph 7(d) of its
answer:
Defendant refers to this letter of plaintiff’s dated
April 21, 1953, for a full Statement of its contents.
13. (a) Defendant inserts ‘the following paragraph as
paragraph 13(a) of the answer:
(fol.50] After investigation the AEC determined that
in 47 cases out of the 111 pier holes on which drill-
ing had been commenced, lava bedrock was en-
countered above elevation 4747’. The contractor was
thereafter permitted to drill each pier hole two feet
into solid lava bedrock and stop whether this bed-
rock was encountered above or below elevation 4747’;
and was paid for this two feet at the rate provided
for solid lava rock excavation. (The subject of “float
rock” was never mentioned ai that time.)
Plaintiff accepted this adjustment together with
the payments made in accordance with its terms, and
recommended and finished the pier drilling without
protest. This payment made under these circum-
stances which was accepted by plaintiff without pro-
test constitutes a complete settlement of all phases
of the pier drilling claim.
(b) Defendant changes numbered paragraph 13(a) in
the original answer to numbered paragraph 13(b) in
the amended answer.
(c) Defendant changes numbered paragraph 13(b)
in the original answer to numbered paragraph 13(c)
in the amended answer.
14. (a) Defendant substitutes the following for the
heading and first sentence in paragraph 14(a) of the
answer:
14. (a) Pier Drilling, Concrete Aggregate, And
Amercoat Paint
Defendant incorporates by reference here its alle-
gations contained in paragraphs 13(a), (b), and
(c) immediately above.
(b) Defendant substitutes the following sentence in
place of the last sentence in paragraph 14(b) of the
answer.
Having entered into this negotiated price agreement,
plaintiff is estopped from now asserting delay costs
based upon any activities in connection with the
shield windows which occurred prior to the execu-
tion of the price agreement.
{fol.51]) All other language in the original answer re-
mains as it was originally filed.
37
WHEREFORE, defendant prays that plaintiff’s peti-
tion be dismissed.
/8/ William H. Orrick, Jr,
Assistant Attorney General
Civil Division
/8/ Melford O. Cleveland
/s/ James F. Merow
Attorney, Civil Division
Department of Justice
(fol. 52] [File Endorsement Omitted]
[fol. 53]
IN THE UNITED STATES COURT OF CLAIMS
No. 3-61
[File Endorsement Omitted ]
[ Title Omitted]
COMMISSIONER’s ORDER AND MEMORANDUM RE APPLICA-
BILITY OF BIANCHI DECISION—February 18, 1964
In March 1958 the plaintiff was awarded a contract to
construct an assembly and maintenance area for the
Atomic Energy Commission’s National Reactor Testing
Station in Idaho for completion a year later. The con-
tract was completed on Jan
ing been extended by
made by the plaintiff
sidered in whole or in part administratively relate to
Pier Drilling, Concrete Aggregates, Shield Doors, Shield
Windows, and Amercoat Paint. Another general catch-
all claim sounding in breach of contract is alleged in par-
agraph 9 of the petition but was not claimed adminis-
tratively.
{fol.54] On March 22, 1957, the parties entered into a
Receipt and Release under which, in consideration of the
payment of $52,382.92, the plaintiff released the Gov-
ernment from all claims “of whatever kind or char-
acter, arising under, in connection with or by virtue of”
the contract, with certain enumerated exceptions cover-
ing the administrative claims for Shield Windows, Pier
Drilling, Shield Door, Concrete Aggregate, and Amer-
coat Paint.
On June 17, 1963, the undersigned commissioner di-
rected the parties to file briefs to enable him to decide
to what extent the case is bound by the decision in United
States v. Bianchi, 373 U.S. 703 (1963). Briefs were
filed by the parties indicating the need for a separate
determination as to each of the several claims con-
tained in the petition. In order to ascertain the exact
nature of the administrative determinations the com-
missioner borrowed from the defendant the administrative
files i each of the administrative appeals, and examined
carefully as to each the contractor’s claims and the de-
cisions of both the contracting offices and the AEC on
appeal. As a result of such examination, and in con-
sideration of the briefs of the parties, certain conclu-
sions were reached as set forth in the following para-
graphs:
(fol. 55] Pier Drilling Claim
At the outset of its contract performance the plaintiff
ran into float rock in drilling holes in the ground for con-
crete piers. On June 1, 1953, it notified the contracting
officer that it had encountered subsurface conditions ma-
terially differing from those indicated in the drawings
and specifications. On February 18 and March 81, 1955,
the plaintiff filed its formal claims with the contracting
officer, the first requesting payment of the increased
39
by the changed subsurface condi-
tions, and the second demanding payment of its costs re-
a
40
The net effect of the foregoing recital of ad‘ \.aistra-
tive proceedings is that first, the Board has ratified the
decision of the contracting officer that the plaintiff's
excavation difficulties at the outset of the contract were
not responsible for the delay in pouring concrete in
the winter months and the consequent winter protection
expenses; and second, the plaintiff has failed to exhaust
[fol. 57] any administrative remedy it might have with
reference to the excessive drilling costs it experienced as
the result of changed subsurface conditions found by the
The Board had no authority to adjudicate the first ele-
ment of plaintiff’s claim because the relief sought was for
the recovery of unliquidated damages for delays allegedly
caused by the Government. The Board’s sole power un-
der the contract was to adjudicate equitable adjustment
for the changed subsurface conditions, and the plaintiff's
expenses providing winter protection for the freshly
poured concrete could not be paid as part of an equitable
adjustment because it was not expended in direct rela-
tion to the drilling either in point of time or in func-
tion. Since the Board could not adjudicate such a claim,
its findings as to the cause of the delay lack the finality
accorded by the disputes clause to findings of fact under
the Disputes Clause, for findings made as to facts under-
lying a claim cognizable only in the courts are merely ad-
visory. Therefore, in reviewing the decision on this ele-
ment of the claim the court is not restricted to the ad-
ministrative record but may receive and consider evidence
de novo.
As to the remanded part of the claim, the determina-
tion of the amount of the excess diilling costs is a mat-
ter of fact under the changed conditions clause, but the
determination of whether plaintiff can sue in behalf of its
(fol. 58] subcontractor is a matter of law because it in-
volves a legal interpretation of the subcontract pro-
visions or a legal analysis of any other circumstances
which might prevent the subcontractor’s recovery from
the plaintiff. The plaintiff had to establish both of
these propositions in order to recover administratively,
and no doubt the agency was ready and willing to pass
41
6: them both if the plaintiff had prosecuted its claim to
the end, even though strictly speaking the Board had
no authority to adjudicate the legal issue with any fin-
ality. However, since it is obvious that the Board would
have done so, it cannot be said that the plaintiff had no
administrative remed available. Whether or not the
claim. But as to that part of the claim relating to
excess costs of drilling the court’s action is restricted to
a determination of whether the decision below (if any)
was arbitrary, capricious, or not Supported by substantial
evidence in the administrative record.
The contract involved a large quantity of concrete con-
struction. It provided that the contractor could pur-
chase suitable aggregates from Government supplies or
from other sources, but imposed no obligation on the
42
up to specification requirements. While this was being
{fol.60] done it directed the plaintiff to increase the
strength of the concrete by adding one sack of cement
in each cubic yard of concrete mix. This was done for
several months until the condition of the aggregate im-
proved to the point that adequate strength was obtained
without using the extra sack of cement. Pursuant to
plaintiff’s request of July 31, 1958, for payment of the
extra cement used as a changed condition, and plaintiff’s
later billing in February 1954 in the amount of $8,640.93
for the cost of the extra cement including “supervision,
general expense, and profit”, the defendant issued Modi-
fication No. 6, part of which reimbursed the plaintiffs in
the amount it had claimed for this item. The contract
was completed in January 1955, and it was not until July
1956 that plaintiff filed a claim with the contracting offi-
cer for approximately $109,000 for costs stated to have
been incurred because of the poor condition of the aggre-
gates.
The contracting officer rejected the claim on the
grounds that it appeared to be one for breach of contract,
not properly before him under the Disputes Article, and
in the alternative that (1) the claim was untimely, and
(2) the plaintiff had failed to explain the nature of the
additional costs it was claiming.
{fol.61] The plaintiff duly appealed to the AEC in
January 1957 under Article 15 of the contract and re
quested a hearing.
In March 1957 the plaintiff executed a general receipt
and release under which, for $52,382.92, it released the
defendant from all claims “arising under, in connection
with or by virtue of” the contract, specifically excepting
cert xin enumerated claims including “Concrete aggregate
claim for additional compensation to Contractor’’,
Under newly inaugurated procedures of the AEC the
plaintiff’s appeal was assigned to a Hearing Examiner.
In May 1959 the contracting officer filed motions to dis-
miss the appeal proceeding for lack of jurisdictiun [i.e.,
breach of contract], and failure to make timely presenta-
tion of claim, and filed a third motion for a more definite
statement. A hearing was held before the Hearing Ex-
43
aminer on the motions, Subsequently the plaintiff filed
a brief in opposition to the motions.
On October 1, 1959, the Hearing Examiner filed his
decision which contained findings and determinations.
The plaintiff's appeal was denied and the contracting offi-
cer’s motion to dismiss for plaintiff’s failure to make a
timely presentation of its claim was granted. No hear-
ing on the merits was held. The plaintiff did not petition
the AEC for review of the Hearing Examiner’s decision
[fol.62] The decision of the Hearing Examiner dis-
cussed all phases of the appeal, made specific findings of
fact, and dismissed the appeal on the stated ground that
the claim was not timely. However, the decision also ob-
served that, although plaintiff had based its claim under
the Changed Conditions Article, the article was not ap-
plicable because the condition of the aggregates was vis-
ible on inspection and hence was not an unknown condi-
tion. Moreover, if the plaintiff's theory was on breach of
warranty of fitness of the aggregates, such a claim would
not be within the jurisdiction of the AEC.
It must be concluded that the Bianchi decision does not
apply to the claim for aggregates, primarily vecause the
decision of the Hearing Examiner of the AEC was predi-
cated upon oral argument of counsel addressed to disposi-
tive motions, and was not based upon a hearing on the
merits affording plaintiff an opportunity (as it had re-
quested) to prevent evidence. Further, the Hearing Ex-
aminer disposed of the appeal on the stated ground that
the claim was not timely in its presentation, although
neither the contract nor any cited regulations prescribe a
definite time for the filing of such claims other than the
requirement of the Changed Conditions Article that
notice of a claim thereunder be given immediately by the
contractor. Whether a claim such as the present one,
sounding in unliquidated damages, filed one and one-half
(fol. 63] years after completion of performance under
the contract is timely is a question involving the discre-
tionary judgment of this court, assuming that in any
event the agency has jurisdiction over such a claim. The
44
contracting officer felt that he had no such jurisdiction
because the claim was for unliquidated damages.
If the claim was for unliquidated damages for breach
of warranty that the aggregates were suitable and is thus
beyond the jurisdiction of the agency, then three conse-
quences ensue to the defendant’s position:
(1) No requirement existed that the claim be appealed
to the AEC.
_ (2) The defendant’s argument fails that the plaintiff
has failed to exhaust its administrative remedy by fail-
ing to seek a review by the AEC of the adverse decision
of the Hearing Examiner.
(3) There need be no remand to the AEC to hold a
hearing on the merits.
It is not specifically mentioned by the defendant in its
brief, but in comparable situations the Government has
urged that factual decisions by the agency underlying le-
gal decisions over which the agency lacks jurisdiction,
nevertheless possess finality on review by this court. In
view of the rulings by the court in comparable situations
any argument, if made, that the Hearing Examiner’s de-
cisions as to the facts possess finality, would not be ten-
able.
[fol.64] The plaintiff is entitled to a de novo trial on
the issue of concrete aggregates, and no finality attaches
to the AEC decision on this item of the claim.
Shield Windows Claim
Under the original contract the plaintiff was to install
shield windows to be furnished by the defendant. Shield
windows were elaborate viewing apertures to permit per-
sonnel to watch developments inside specially insulated
rooms, without radioactive leakage. They involved special
seals and several thicknesses of special glass filled with
fluid which would shield radioactive rays but not impede
vision. Shortly after the award of the contract a Modifi-
cation was issued requiring the plaintiff to furnish the
shield windows by subcontract with a Government-ap-
proved supplier, and a subcontract was let to Corning,
which was about the only supplier experienced in this
45
limited field. There is strong indication that during the
performance of the contract the Government and its firm
tractor to the plaintiff, because of the latter’s lack of ef-
fective control.
{fol. 65] The plaintiff experienced difficulties with the
assembling and installation of the shield windows, In
June 1954 the plaintiff notified the contracting officer that
changed conditions had been encountered materially alter-
ing the scope of the work and forcing plaintiff to suspend
all operations until the extent of the changed conditions
cording to specifications, The plaintiff contended that the
design of the Architect-Engineer for the gaskets was
faulty and that the defendant’s Architect-Engineer was
the AEC and requested a hearing which was held.
(fol. 66] On July 23, 1957 the AEC Advisory Board on
ances for additional costs incurred because of the alleged
and specifications were adequate to achieve the desired
result, assuming the plaintiff’s competence, Plaintiff con-
tended that the delays it suffered were not its responsi-
bility but were due in part to the AEC’s arbitrary action
——
in bypassing plaintiff and in part to the arbitrary action
of the Architect-Engineer and the Corning Glass Com-
pany.
At the conclusion of a remarkably thoughtful and sym-
pathetic opinion the Board denied plaintiff’s appeal for
an equitable adjustment for increased costs but allowed
the appeal for an extension of time for excusable delay,
and remanded the latter to the contracting officer for
computation. The question for remand became moot
when the defendant extended the plaintiff’s overall time
to the actual contract completion date. The Board made
a series of specific findings of fact which in effect put the
blame for the series of delays on neither side to the ex-
clusion of the other, and instead held that the delays were
[fol. 67] chiefly the result of the inherent difficulties of
assembling and installing shield doors and windows rec-
ognized to be beyond the knowledge and experience of any
person or company, and which involved new techniques.
The Board findings enumerated the specific delays
which apparently involved a substantial total of lost time.
It does not appear in the decision that the plaintiff par-
ticularized or even totaled its claim for equitable adjust-
ment, so it cannot be determined from the administrative
record what part of its claim would be for direct costs
reimbursable under the contract and what part (if any)
would be delay damages. Assuming that, the Board
would have had no jurisdiction to adjudicate a claim for
delay damages (quite apart from the authority of the
agency to settle such a claim), it is apparent that the
basic issue involved in the administrative proceeding was
whether the plaintiff was unreasonably delayed by actions
of the Government, a typical delay damages type of in-
quiry sounding in unliquidated damages.
Accordingly, since the final settlement and release en-
tered into on March 22, 1957 reserved plaintiff’s claim for
“additional compensation” covering the shield windows
complaint, it is concluded that the decision of the Board
lacks finality, that the Bianchi decision does not apply,
and that the plaintiff is entitled to a de novo trial in this
court on the question of delays. It is urged, however,
(fol. $8] that the parties give full consideration to the
47
possibility of obviating or at least curtailing the trial by
adoption of the administrative record, which includes
many exhibits and a 453-page transcript of testimony
taken during a three-day hearing. It may be that the
requirements of the parties as to the facts of the claim
may be fully satisfied in the existing record, and that
they would merely want the court to reappraise the evi-
dence de novo without any bar of finality to overcome.
Finally, the defendant alleges in its answer that plain-
tiff has failed to allege that the action of the Board was
arbitrary, capricious, etc. Assuming that the Board had
no jurisdiction over the type of claim it considered, such
allegations in *he petition would be superfluous.
Shield Door Claim
On January 28, 1955, the plaintiff submitted a claim
of $4,457.25 to the contracting officer in the form of a
proposal for a change order covering extra work on cer-
tain shield doors ordered by the Architect-Engineer a
year earlier by means of changes made on shop drawings
prepared by plaintiff’s subcontractor. By a supplemental
letter plaintiff asked for a time extension due to the de-
lays involved.
{fol.69] On October 27, 1955, the contracting officer
denied the claim on the principal ground that the plain-
tiff had presented its claim a year late instead of within
10 days, as required by the Changes Article, and on the
further ground that the changes made by the Architect-
Engineer to the shop drawings did not change the con-
tract drawings and specifications and thus constitute ex-
tra work. The plaintiff appealed to the AEC and a hedr-
ing was held before the ABCA. Through mistake no re-
porter was present to transcribe the testimony, but by
agreement of the parties this was waived.
The Board made its decision on April 25, 1957, deny-
ing plaintiff's claim for adjustment under the chanr-s
clause but granting its claim for a time extension, re-
manding the latter to the contracting officer to determine
the amount of the time extension. As to the major part
of the plaintiff’s claim the Boaré: held that, while the con-
tract drawings were inexcusably in error, the specifica-
tions themselves were adequate, so that the changes made
by the Architect-Engineer to the subcontractor’s shop
drawings did not constitute changes under the changes
clause. As to other changes, made by the Architect-En-
gineer to the subcontractor’s shop drawings, the Board
held that they did constitute changes to the contract
drawings and specifications, but that the plaintiff’s fail-
ure to present its claim within the 10-day period pre-
scribed by the Changes Article barred any right to re-
covery, although the contracting officer had the discretion
to consider such a claim but was not required to, The
[fol. 70] Board then remanded the plaintiff’s claim for a
time extension to the contracting officer to determine the
amount.
Three major points are to be made: First, the failure
of the Board to prepare a transcript of its hearing pre-
vents an adequate review by the court, and this lack is
not cured because the plaintiff may have agreed to hav-
ing no transcript made. The omission could be corrected
by return of the claim to the Board for rehearing, but it
is not believed that the Bianchi decision requires such a
remand in every case where the prospect of even greater
delay would be assured. The Lianchi decision must be
read with discretion, and the Supreme Court’s admonition
against “delay at its worst” should be given considera-
tion. To return the claim to the Board for a redetermi-
nation on the basis of a complete record would ada per-
haps several more years to the ultimate decision of a
claim already 10 years old in its inception.
Second, it is observed that certain aspects of this item
of claim might well have been subjected to a dispositive
motion (if seasonably brought), such as the delay in pres-
entation of the claim administratively and possibly the
lack of authority of the Architect-Engineer, thus avoiding
a trial.
Third, it is noted that at no time did the plaintiff claim
administratively anything other than its direct costs, and
made no claim for delay damages as it makes for the first
(fol. 71] time in paragraph 7 (c) of its petition. On
March 22, 1957, the plaintiff executed a full receipt and
release with enumerated exceptions, including “Shield
49
Door Claim for additional compensation to Contractor”.
In view of the fact that the contracting officer was em-
powered to settle all kinds of claims (whether liquidated
gotiations leading up to the final release would preclude
the contractor from advancing it later as an afterthought.
It would be a disservice to the contracting officer to per-
mit a contractor to remain silent as to his potential
ment, and then, after agreement is reached on a sup-
posedly all-inclusive amount, the contractor reveals his
new claims, The willingness of the contracting officer to
enter into a final payment agreement would necessarily
be substantially affected by his knowledge of delay claims,
and if the contractor remains silent he is bound by his
acceptance of the final settlement by way of accord and
satisfaction, The particular reservation which the plain-
tiff inserted in the release in question would mean to the
(fol. 72] which plaintiff had held quietly in reserve. The
precise situation was present in the recommendations for
conclusions of law filed by this commissioner in Brock ¢&
Blevins Company, Inc., v. United States, No. 292-59, on
December 6, 1963, and the reasoning given there is in-
corporated here by reference.
In short, the plaintiff is entitled to a de novo trial on
those shield door costs which it claimed adrainistratively,
but not as to any collateral delay costs which it advanced
subsequent to the execution of the reisase on March 22,
1957,
Amercoat Paint Claim
In March 1954 it was discovered that various metal
components furnished by defendant for the “hot shop” re-
quired de-rusting and painting with Amercoat. Plaintiff
performed this work under protest, contending that it
was outside of the painting xpecifications and involved
dismantling, sandblasting, ete. There wa3 some disagree- |
ment as to whether Amercoating the shield doors should
be considered as part of the plaintiff’s obligation to Amer-
coat the “hot shop” walls. The contracting officer’s deci-
sion in June 1954 that shield doors were movable walls
and thus were contract obligations of plaintiff to paint
was reversed in December 1954 by successor Government
representatives, and the parties agreed to a settlement
{fol. 73] formula as to the direct costs of the extra paint-
ing. It does not appear that the plaintiff made any ad-
ministrative claim for delay damages in this connection
as it is urging here. The defendant contends that plain-
tiff was paid in full for this Amercoating claim, and that
the only reservation in the release executed by plaintiff in
March 1957 was as to an amount withheld but subse-
quently paid to plaintiff for some defective paint work.
The defendant also says that the present claim for extra
work and changed conditions is not relevant to a breach
of contract action.
Since the plaintiff did not advance its present claim for
delay damages at any time prior to execution of the re
lease in March 1957 and the sole claim reserved in the
release was later paid, on the principle of accord and sat-
isfaction the plaintiff should be barred from further re-
covery. The immediate issue is whether Bianchi applies
to preclude a de novo consideration of the administrative
decision, and the above observation as to accord and sat-
isfaction is technically not relevant and should perhaps
be the subject of an appropriate motion. However, since
the object of the present proceeding is to ascertain what
areas of the claim will require trial, it is relevant to rule
that, for other reasons, a trial here should be denied and
court review be limited to an examination of the adminis-
trative record.
(fol. 74] Delay-damage Claim
In paragraph 9 of its petition the plaintiff claims
$1,100,965.23 for defendant’s failure throughout the con-
tract to (1) “formulate a desired end-result prior to the
award”, and (2) “prepare adequate plans and specifica-
tions”, thereby “imposing additional design and extra
51
work through shop-drawing procedures”, It was alleged
as part of this clai S procedure for
extent certain parts of
ratively as described in
amount claimed), so tha ve been cogniz-
able by the AEC even i ted. But the
fact that it had not
in the release would
(fol. 75] other speci
subject-matter for a
accorded, but
time in the peti-
administratively,
but a dispositive motion should
/8/ C. Murray Bernhardt,
Commissioner.
February 18, 1964
52
(fol. 76]
EXHIBITS TO DEFENDANT'S SUPPLEMENTAL BRIEF
CONCRETE AGGREGATE APPEAL No. 121, PART 1
UNITED STATES
ATOMIC ENERGY COMMISSION
P. 0. BOX 1221
IDAHO FALLS, IDAHO
December 20, 1956
In Reply Refer To:
OC:WLR
Utah Construction Company
142 East Third South Street
Salt Lake City, Utah
Attention: Mr. Glen Staker
Gentlemen:
By letter dated July 16, 1956, you presented to me for
decision as Contracting Officer under Contract AT (10-1)-
645 your claim for additional compensation in the amount
of $109,356.00, which sum you represent you were re
quired to expend as a result of the “Commission’s failure
to furnish concrete aggregate that would meet the con-
tract specifications”. Inasmuch as all the work under the
contract was completed and accepted January 7, 1955,
my investigation of your claim has been restricted to (1)
a review of the Commission’s records and (2) discussions
with those few Commission and Ralph M. Parsons Com-
pany employees presently in the vicinity of Idaho Falls
who had any connection with the work being performed
under Contract AT (10-1)-645. As a result of that limited
investigation I have made the following findings and de-
terminations in accordance with the provisions of Article
15. of the contract entitled “Disputes” and Section 3.10
of the Rules of Procedure of United States Atomic En-
Commission Advisory Board of Contract Appeals
(10 C.F.R. Chapter 1, Part 3). A copy of those rules is
attached for your convenience.
53
FINDINGS
1, On March 19, 1953, the Government and the Utah
Construction Company entered into Contract AT(10-1)-
645 for the performance of certain construction work.
2. SC-18. Concrete Aggregate of Section II—Special
Conditions of that contract provides, in part, that “Con-
crete Aggregate suitable for all standard portland cement
concrete requirements on this job will be available to this
Contractor at the price of $2.90 per ton from the Com-
mission’s stockpile near the ANP Area”.
Registered Mail
Return Receipt Requested
(fol. 77] 8. The Contractor’s July 16, 1956 claim for
additional compensation is predicated on a failure of the
Commission to make available suitable concrete aggregate
in accordance with the provisions of SC-18 of the contract
and is therefore a claim for damages for an alleged
breach of contract by the Commission which is not prop-
erly before me for consideration under the Disputes Ar-
ticle,
DETERMINATION
It is my determination from the above findings that your
claim is one for damages for breach of contract which
cannot properly be considered under the Disputes Article.
Nevertheless, I make the following additional] findings of
fact, without prejudice to this determination, in order
to insure compliance with Section 3.10 of the above-
referenced Rules of Procedure.
FINDINGS
4. Utah was not required by any provision of the con-
tract to use the concrete aggregate which the Commission
made available and SC-21 of Section II—Special Condi-
tions of the contract applies only to mandatory Govern-
ment-furnished property.
5. Cylinder tests conducted during June and July in-
dicated the concrete being placed on the ANP Project
54
varied greatly with respect to compressive strength and
that some of the concrete did not meet the minimum
strength requirements established by Table 3A of Divi-
sion S-2 of the Technica] Specifications.
6. Utah claimed the wide variation in the compressive
strengths of the concrete being placed on the ANP Proj-
ect and the failure, in several instances, of the concrete to
meet minimum strength requirements was due to the fact
that the concrete aggregate which was being made availa-
ble by the Commission was “overburdened with fine ma-
terials and seriously deficient in the coarser parts”.
7. Tests made during July 1953 of the concrete aggre-
gate being made available to Utah by the Commission re-
vealed that the percentage of concrete aggregate passing
the smaller sized screens exceeded the allowable percent-
ages set forth in the gradation tables contained in
Division S-2 of the Technical Specifications of the con-
tract.
8. By letter dated July 21, 1953, over the signature of
J. Warren Evans, Chief, Construction Branch, the Com-
mission authorized Utah to increase the “five (5) sacks
of cement per cubic yard as outlined in Section III,
Division S-2, Page 7 in subparagraph (2), under para-
graph b. ‘Proportioning Limitations’, to six (6) sacks
of cement per cubic yard” pending an investigation and
determination of the deficiencies in the strength of “re
cent concrete placed on the ANP Project”.
[fol.78] 9. By letter dated July 31, 1958 over the
signature of Glen Staker, Project Manager, Utah noti-
fied the Commission that it regarded the poor quality of
the concrete aggregate being “furnished” by the Commis-
sion as a changed condition under its contract and that
said letter was to be regarded as notification of that
changed condition.
10. The only monetary relief requested by the Con-
tractor in its July 31, 1958 letter was payment for the
additional cement used in making concrete if the Com-
mission decided to utilize the existing concrete aggregate
with the additional of one extra bag of cement per cubic
year of concrete mix.
11. Utah was authorized and did use one extra bag of
cement per cubic year of concrete mix placed on the
55
ANP Project from July 21 to October 30, 1958, by which
time another Contractor had substantially completed re-
processing the 1-114” to 34” coarse concrete aggregate,
12. By letter to the Commission dated February 7,
1954, Utah presented its cost for adding the one bag of
to the concrete mix one bag of cement to each cubic yard
of structural concrete placed under the contract between
July 21 and October 30, 1958, as directed by the Resident
Engineer, in consideration of payment to the Contractor
of an additional $8,640.93.
14. Although any failure of the Commission to make
available suitable concrete aggregate under the contract
would constitute a breach of contract rather than a
changed condition as alleged in Utah’s July 31, 1958
letter, Utah received all the monetary relief requested in
its July 31, 1953 letter, which relief fully compensated
the Contractor for the matter brought to the Contract-
ing Officer’s attention by its July 31, 1958 letter.
15. Although the concrete aggregate made available
by the Commission may well have been a contributing
factor in the production of below strength concrete by
Utah, it was not the sole cause of that condition.
16. Although the Contractor’s July 16, 1956 claim for
additional compensation is predicated on the Commission’s
failure to make available concrete aggregate of the proper
quality, as was its July 31, 1953 claim, the former is in
fact a separate and distinct claim which had never been
mentioned or presented to the Contracting Officer for
consideration prior to July 16, 1956.
17. The submission of the Contractor’s July 16, 1956
claim was not timely and the delay in presenting such
claim has acted to the prejudice of the Commission in
the investigation of the claim, especially with respect to
[fol. 79] making findings as to whether the concrete ag-
gregate made available by the Commission did in some
Way ca ise an increase in the cost of finishing the con-
56
crete placed on the ANP Project and the extent, if any,
to which the increased cost alleged by the Contractor was
attributable to the concrete aggregate used.
18. Utah has not indicated the nature of the additional
costs alleged to have been incurred, nor has it indicated,
even in a general manner, how the concrete aggregate
made available by the Commission was responsible for an
increase in the cost of finishing the concrete.
19. The sole support for Utah’s July 16, 1956 claim
consists of (i) a computation which indicates that Utah’s
actual concrete finishing costs exceeded its estimated
concrete finishing costs (with a contingency factor of 50
per cent) by $109,356.00, and (ii) a bare allegation that
the Contractor was forced to expend that entire sum be-
cause the Commission failed to “furnish concrete aggre-
gate that would meet the contract specifications”.
20. Utah has not submitted evidence in support of its
July 16, 1956 claim which would justify my finding that
Utah incurred any additional cost for finishing concrete
placed on the ANP Project as a result of the quality of
concrete aggregate made available by the Commission,
DETERMINATION
As previously stated, it is my determination that your
July 16, 1956 claim is a claim for damages for breach
of contract which is not properly before me for considera-
tion under the Disputes Article. However, even if that
determination were overruled, it is my further deter-
mination in view of findings 4 through 20 that your July
16, 1956 clair must be denied in its entirety.
Very truly yours,
ALLAN C, JOHNSON, Manager
Idaho Operations Officer
Contracting Officer
Enclosure:
Rules of Procedure
oc E&C USAF E&C M
WLRowberry:jm Ashton Heasley Leppich Johnson
12-20-56
57
[fol. 80]
CONCRETE AGGREGATE APPEAL No. 121, PART 2
UNITED STATES ATOMIC ENERGY COMMISSION
HEARING EXAMINER
FOR
CONTRACT APPEALS
Docket No. 121
RECEIVED
May 21, 1959
U.S.A.E.C.
Public Document Room
APPEAL OF UTAH CONSTRUCTION COMPANY
UNDER CONTRACT No. AT (10-1) -645
Brief of the Contracting Officer on Motion to Dismiss
Utah’s Appeal for its Failure to Make a Timely
Presentation of its Claim
This brief is submitted on behalf of the Contracting
Officer, United States Atomic Energy Commission (here-
inafter referred to as the “Commission”), Idaho Opera-
tions Office, Idaho Falls, Idaho, in support of his motion
to dismiss the appeal of UTAH CONSTRUCTION COM-
PANY (hereinafter referred to as the “Contractor” )
for failure to submit its claim for additional conipensation
due to alleged increase in concrete finishiug costs for
approximately three years after the Contractor submitted
its notice of a “changed condition” and for approximately
one and one-half years after all work under the subject
contract had been accepted.
FACTUAL SUMMARY
In the instant case the alleged changed condition was
encountered on July 16, 1953. By letter dated July 21,
1953 the Commission directed the Contractor to add an
extra bag of cement to the concrete mix “pending an in-
vestigation and determination of deficient strengt
quirements .. .” (Encl. 7 of Record on Appeal, he
after termed “Record”). Tests revealed that the
erete being placed did not comply with the strengt
quirements of the contract (Encl. 8, Record). On
$1, 1958 the Contractor transmitted to the Comm
its “notice” of a “changed condition” (Encl. 10, Rec
The only monetary relief requested in this letter of
$1, 1953 was for the cost of adding an additional b
cement.
[fol. 81] The Commission concluded its investig:
(see Encls. 11 and 12, Record), and decided to cor
the addition of the extra bag of cement until certs
the conerete aggregates had been screened to elin
the excess fines. This was done under a contract
another contractor (Encl. 17, Record), after the
tractor refused the job (Encl. 15, Record). After c
of the aggregates were screened, the Commission’
thorization to use the extra bag of cement was re
(Encl. 18, Record). Thereafter, the Contractor sub!
its costs for the extra bag of cement (Encl. 20, Re
saying nothing with respect to any other costs
might be incurred in the future or which were then
incurred as a result of the alleged “changed condi
Acting in good faith, on the basis of the Contractor’s
representations and incidations that it desired reim
ment only for the added bag of cement, the Comn
to the Contractor’s proposal and enterec
Modification No. 6 to the subject contract which pr
for payment for the added bag of cement in the a
requested by the Contractor (Encl. 5, Record). '
after, the Commission continued its regular course ¢
duct, relying on the fact that Modification No.
finally disposed of the entire controversy surroundi:
quality of aggregate and the Contractor’s claim
thereon. It was not until approximately three
after the controversy concerning the aggregates
that the Commission was made aware of the instant,
purportedly based on facts arising out of this sam
troversy.
ngth re-
, herein-
the con-
ngth re-
On July
mmission
Record).
r of July
al bag of
stigations
continue
ertain o*
eliminate
ract with
the Con-
ay certain
jion’s au-
3 revoked
submitted
Record),
sts which
hen being
ondition”.
or’s prior
eimburse-
ymmission
ered into
| provided
e amount
). There-
se of con-
‘fo. 6 had
nding the
‘im based
ree years
tes began
ant, claim,
same con-
7 59
LEGAL ANALYSIS
In the Appeal of Frontier Drilling Company, USAEC-
BCA, Docket No. 93 (Novy, 1956), the AEC’s Advisory
Board of Contract Appeals stated:
“Unlike other articles of the standard contract, where
the notice requirement serves only to insure a review
of the claim while evidence on the merits is available,
the requirement in Article 4 serves a second function.
Extra costs involved in the Changes and Delay-
Damages situations have already occurred; but in the
Changed Condition situation the Contracting Officer
may, given immediate notice, not only discover the true
facts, but, if he so desires, prevent or reduce the
(fol. 82] costs by appropriate change orders. It is for
this reason that the Board ruled in Appeal of Mc-
Kee, Docket No. 10, that the notice under Article
4 must not only warn of the condition but of the in-
tent to claim extra costs.” (Emphasis added.)
In the Appeal of Utah Construction Company, USAEC-
BCA, Docket No. 95 (April 1957), the Board stated:
“In general it is true, as the Board has said in other
opinions, that the primary purpose of early notice is to
afford the Contracting Officer an opportunity to ascer-
tain the facts while they are fresh, and that, there-
fore, if the facts can still be determined, a late claim
should be decided on its merits. However, we have
recognized an additional purpose in early filing of
claims under the ‘Changed Condition’ article—namely
an opportunity to mitigate damage by deletion of,
or changes in, the work required.” (Emphasis added. )
it is quite apparent that since the Contractor in the
instant case did not present the subject claim for approxi-
mately three years after it had submitted its notice of a
“changed condition”, the Commission was not afforded
the opportunity to mitigate damages, if any. The Board’s
interpretation of the notice requirement in the aforecited
cases finds clear-cut and convincing support in the two
equitable theories of estoppel and laches.
The instant case presents the classic case for the appli-
cation of the principles of equitable estoppel. One of the
many facets of the doctrine of equitable estoppel is that
of acquiescence. In Harvey Radio Laboratories, Inc. v.
he aaa States, 126 Ct. Cl. 383, 391 (1953), the court
stated:
“When a party ‘with knowledge or the means of
knowledge of his rights and of the material facts does
what amounts to a recognition of the transaction as
existing, or acts in a manner inconsistent with its
repudiation, or permits the other party to deal with
the subject matter under the belief that the trans-
action has been recognized, or abstains for a consid-
erable length of time from impeaching it, so that the
other is reasonably induced to suppose that it is
recognized, there is acquiescence, and the transaction,
though it be originally impeachable becomes unim-
peachable.”
[fol. 88] In Mahoning Investment Co. v. United States,
78 Ct. Cl. 231, 247 (1933), the court stated:
“All that is shown in these cases [of acquiescence]
is that the acts of the party estopped were such as to
mislead the party claiming the estoppel to continue
in the course already begun, believing the same to be
acceptable to the party estopped.”
It is clear that the Contractor had means of knowledge
of its rights since it had previously filed a claim pursuant
to Article 4 of the General Provisions of the contract,
and since it obviously had complete and sole control of its
cost records, including the costs of concrete finishing.
From the period of July 16, 1953 until February 5,
1954 the only subjects of discussion between Contractor
and the Commission with respect to the entire controversy
were the strength aspects of the concrete and the Con-
tractor’s sole monetary claim, which was for the ad-
ditional bag of cement. On February 5, 1954 the Con-
tractor and the Commission entered into Modification No.
6 to the subject contract which finally disposed of the
Contractor’s claim. There would seem to be no question
but that the Contractor recognized the contract modifi-
cation as disposing of its only monetary claim and that
it permitted the Commission to believe that the modifica-
61
tion had finally disposed of the entire controversy. This
latter proposition is particularly compelling since the Con-
tractor abstained for approximately two and one-half
years (from February 1954 to July 1956) from impeach-
ing the contract modification as not being dispositive of
the entire controversy.
In Joseph Behr & Sons, Inc. v. The United States, 137
Ct. Cl. 688, 689 (1957), the plaintiff had purchased cer-
tain war surplus materials from the Government. The
plaintiff claimed that there was a shortage in certain
items and made a claim therefor which was subsequently
satisfied. More than a year after the sale had been
[fol. 84] consummated the plaintiff claimed that additional
items were missing and claimed $25,387.80 therefor. The
court stated:
“In the first place, we think it is estopped to assert
the claim sued on. When it presented its claim for
the shortage of cots and the saw, and for pilferage
from the trucks, it made no mention of the alleged
shortage for which it now sues, although it says it
knew of them at the time. And when it later paid
the balance of the purchase price, less the amount
claimed for the cots and the saw and the pilferage
from the trucks, it deducted nothing for the items
for which it now sues, and made no mention of them.
“When claim was made on account of the cots, the
saw, and the pilferage from the trucks, defendant
sent its agent McMillen to Maui to investigate, but
he made no investigation of the alleged shortage
now asserted, because no claim with respect thereto
had then been made. When, more than a year later,
the present claim was first asserted, plaintiff had
disposed of all of the goods and no investigation
was possible,
“Under such circumstances, we think plaintiff has
waived the claim on which it sues, and is estopped
from asserting it.”
It is noted that in the instant case the Commission
made an investigation concerning the strength require-
ments of the concrete as they were affected by the quality
of aggregate but no investigation was made with respect
to the claim now asserted, because no claim had then
been made. If the Contractor, within a reasonable time
after it had given its “notice” of a “changed condition”
had also notified the Commission that the quality of
aggregate furnished by the Commission was causing an
increase in finishing costs, the Contracting Officer could
have made an investigation with respect to the finishing
costs, and if he found the Contractor’s allegations were
true, and that the same constituted a “changed condi-
tion”, he could have prevented or reduced the costs by
appropriate change orders or other action. Appeal of
Frontier Drilling Co.; Appeal of Utah Construction Co.,
supra. To presently allow the Contractor to assert its
claim would clearly result in prejudice and injury to the
Commission, since the Contractor has precluded the Com-
mission from preventing or reducing the damages, if any.
[fol.85] The doctrine of laches is substantially similar
to the doctrine of estoppel. It is generally stated that a
claim will be barred on the ground of laches where there
is a delay in asserting the claim; lack of knowledge or
notice on the part of the defendant that the claimant
would assert such a claim; and a injury or prejudice to
the defendant in the event the complainant’s claim is
allowed; e.g., Galliher v. Cadwell, 145 U.S. 368, 372, 373
(1892) ; Southern Pac. Co. v. Bogert, 250 U. S. 483, 488,
489 (1919); Holmberg v. Armbrecht, 327 US. 392
(1946). The fact that there was a delay in asserting the
claim for approximately three years after the notice of the
changed condition readily appears from a reading of the
Contractor’s notice of a changed condition dated July 31,
1958, the Contractor’s present claim dated July 19, 1956
and the affidavit of the Contracting Officer and the accept-
ance of work (which documents are attached to the sub-
ject motion). The affidavit of the Contracting Officer also
states that the Commission did not have notice or knowl-
edge of the Contractor’s present claim prior to July 19,
1956. As heretofore stated, the delay by the Contractor
in submitting its present claim has acted to the prejudice
of the Commission.
CONCLUSION
_ The conclusion seems inescable that the Contractor did
not comply with the notice requirement of the “Changed
Conditions” article since the Commission was not afforded
the opportunity to mitigate damages, if any; that the
Contractor acquiesced in the proceedings to dispose of the
only monetary claim which it had presented, inducing
the Commission to believe that no further claim would be
presented ; that the Commission has been prejudiced there-
hy; that the Contractor “slept on” its present claim for
an unreasonable period of time; and, therefore, the Con-
tractor is estopped from asserting its present claim or
barred therefrom by reason of laches or precluded there-
from by reason of Article 4 of the General Provisions of
the contract.
(fol. 86] To allow a contractor’s claim under circum-
stances similar to the instant case would set a precedent
which would make a farce out of the notice requirement of
the “Changed Conditions” article. A contractor could
submit an initial notice and claim and then, after all the
work was completed, he would be allowed to “re-open”
his original claim to include any costs which he “feels”
are attributable to the “changed condition”, thereby en-
tirely precluding the Contracting Officer from mitigating
damages, if any, and requiring its claim to be judged
on the basis of facts which, if they exist at all, are en-
tirely inadequate due to the passage of time; and, in the
case of subsurface conditions, such facts are literally
buried. As the Supreme Court of the United States stated
in Dickerson v. Colgrove, 100 U.S. 578, 581 (1880):
“There is no rule more necessary to enforce good
faith than that which compels a person to abstain
from asserting claims which he has induced others
to suppose he would not rely on.”
Therefore, it is respectfully requested that the Con-
tracting Officer’s motion be granted.
64
DISPOSITION OF THE MOTION
Without prejudice to any other motion the Contracting
Officer might present, it is respectfully requested that
the Hearing Examiner make a full disposition of this
motion prior to taking any other action with respect to
this appeal. It is the position of the Contracting Officer
that this motion is dispositive of the appeal and, there-
fore, will preclude the necessity of a hearing on the merits.
/s/ Howard K. Shapar
Attorney for the Contracting Officer
USAEC, Idaho Operations Office
Iraho Falls, Idaho
(fol. 87]
RECEIVED
Oct. 5, 1959
U.S.A.E.C.
Public Document Room
TO ic rerinctresese snore sengtenrrnenvignstmeoners
UNITED STATES OF AMERICA
ATOMIC ENERGY COMMISSION
Docket No. CA-121
IN THE MATTER OF THE APPEAL
OF
UTAH CONSTRUCTION COMPANY
UNDER ConTRACT No. AT (10-1) -645
Appearances
Gardner Johnson, Esq. for
Utah Construction Company
Howard K. Shapar, Esq. and W. L. Rowberry, Esq. for
The Contracting Officer of the Atomic Energy Commission
DEcIsIoN—October 1, 1959
Utah Construction Company of Salt Lake City, (Utah)
executed a contract on March 19, 1958 with the United
States Atomic Energy Commission and was therein desig-
nated as “Contractor” to construct a large assembly and
maintenance area at the Commission’s National Reactor
Testing Station in Idaho. Among other obligations, it was
contemplated that Utah would pour approximately 18,000
cubic yards of concrete.
Upon completion of that work, in so far as herein mate-
rial, a dispute has arisen between the Contracting Officer
and Utah concerning the availability, suitability, and use
[fol. 88] Some of the important clauses are as follows;
others are set forth later in the decision where detailed
“Article 1. Statement of the Work. The contractor
shall furnish ( except as the specifications may other-
wise provide) the plant, equipment, labor and ma-
terials and perform the work necessary for the con-
struction .. . . in strict accordance with the specifi-
cations, schedules, and drawings, all of which are
made a part hereof and designated as follows: Spe-
cifications, Invitation No. AT (10-1)-645,....
“Article 4. Changed Conditions. Should the con-
tractor encounter, or the Government discover, during
the progress of the work subsurface and/or latent
conditions at the site materially differing from those
shown on the drawings or indicated in the specifica-
tions, or unknown conditions of an unusual nature
differing materially from those ordinarily encountered
and generally recognized as inhering in work of the
character provided for in the plans and specifications,
the attention of the Contracting Officer Shall be
called immediately to such conditions before they
are disturbed. The Contracting Officer shall there-
upon promptly investigate the conditions, and if he
finds that they do so materially differ the contract -
shall . . . be modified to provide for any increase or
decrease of cost and/or difference in time resulting
from such conditions.”
The acceptance of the bid provided:
“In compliance with your Invitation for Bids No.
AT (10-1)-645, dated December 22, 1952, the under-
signed hereby proposes to furnish the plant, equip-
ment, labor and materials (except as the specifica-
se may otherwise provide) and perform the
work, .. .”
The specifications of the general conditions for the con-
struction contract provided, in part:
“GC-11. It is understood and agreed thet the Con-
tractor has, by careful examination, satisfied himself
as to the nature and location of the work, the char-
acter, quality, and quantity of the materials which
will be required . . . . and all other matters which
can in any way affect the work under the contract.
“GC-18 Claims for Extras. The Contractor shall,
when ordered in writing by the Commission, perform
extra work and furnish extra material . . . shall be
paid for at actual necessary cost as determined by
the Commission, plus 10% for superintendence gen-
[fol. 89] eral expense and profit. The actual necessary
cost will include all expenditures for material, labor,
including compensation for insurance and social] se-
curity taxes, and supplies furnished by the Contrac-
tor, and a reasonable allowance for the use of the
plant and equipment where required, this allowance
to be agreed upon in writing before the work is be-
gun, but will, in no case, include allowance for
office expenses, general superintendence or other gen-
eral expenses.”
A special condition respecting concrete aggregate was:
| Concrete aggregate suitable for all
standard portland cement . . . aggregate require
67
ments on this job will be available to this Contrac-
tor at the price of $2.90 per ton from the Commis-
sion’s stockpiles near the . . . Area.
Approximate quantities of various gradations availa-
ble in the concrete aggregate stockpiles are as fol-
This Contractor shall assume full responsibilty for
the total 50,000 tons of stockpiled aggregate and
shall make his own arrangements for all loading and
handling in connection with his concrete batching
operations, . . .
While Utah
Government-fu
“. . . Government-owned materials held in storage
by the Commission at the . +. Station . . . Subject to
the right of the Contractor to inspect and reject the
materials for good and sufficient reason prior to ac-
ceptance, the Contractor shal] reecive such materials
in their then condition, without warranty expressed
or implied on the part of the Commission as to serv-
iceability or fitness for use.”
Uath filed a claim approximately a year and a half
ter the work was completed and accepted, and sought
approximately $109,000 for costs Stated to have been
incurred because of the poor condition of the aggregates.
i i ision and found
on, and, in the
ve, he found that the appeal did not involve a
conditio:. within the contemplation of that clause
contract, and finally that there had not been a
timely presentation of the claim. An appeal having been
taken from that decision in accordance with the Rules of
the Commission for procedure in contract appeals, the
Contracting Officer filed 3 motions: (1) to dismiss for
failure to make a timely presentation of the claim; (2)
68
to dismiss for lack of jurisdiction, because either (a)
the asserted claim is not within the terms of changed
conditions clause of the contract, or (b) the asserted
claim is for unliquidated damages; and (3) for a more
definite statement of the claim.
An oral argument was held in Idaho Falls, Idaho on
June 9, 1959, on these motions and briefs in support
thereof, after which the Contractor filed an answering
brief on July 23, 1959 and the Contracting Officer filed
a reply brief on August 28, 1959.
It appears without dispute that sometime prior to July
17, 1953, the Contractor commenced work, and that on
July 17 the Contracting Officer, through the Chief of the
Construction Branch, suspended a portion, at least, of the
concrete mixing and pouring in view of information re-
ceived by him through tests that the cement mixture when
placed in cast compression cylinders was deficient in the
strength requirements as specified by the contract. On
July 21, 1958, the Contracting Officer authorized resump-
tion of work and stated that “.... pending an investiga-
tion and determination of deficient strength require-
ments, .. .” Utah was authorized to increase the concrete
[fol. 91] mix by one bag of cement thereby increasing to
6, instead of the originally specified 5, bags of cement
per cubic yard. From this point on in the transaction
there appears to be a difference of views as to the cause
of the deficient strength in the poured concrete and the
costs involved in the full correction of that condition.
The substance generally des gnated as “aggregates”
used by Utah in the concrete mix was located in a pile
on the site of the Reactor Testing Station, and was nearby
te the location where the mixing of cement and aggre
gates occurred, and also near to the place where it was
poured into final form. After the information had been
received that there was a deficiency in the strength re
quirements, tests were then undertaken of the aggregates.
These revealed the presence of small sands, or “fines”
which may have contributed in some way to the problems
of deficiency in the strength requirements.
After this discovery, the Contracting Officer undertook
the cleaning of the aggregates to remove this condition.
This was done through another contractor selected for this
single purpose and at cost to the Contracting Officer of
$7,744. The provisions of the applicable specifications
respecting cement mixtures contain detailed definitions
of fine and course aggregates, and directions as to per-
missible limits of deleterious substances and organic im-
purities as well as strength requirements in a concrete
mix. The proportioning limitations, as mentioned, first
provided for 5 sacks of cement per cubic yard, but this
was changed, when it was determined that the cement
mixture produced by the Contractor was deficient in
strength, to 6 sacks per cubic yard. The contract pro-
[fol. 92]vided authority for this change in proportioning
of the cement mixture under this clause, S2-03 (c):
“(1) Changes by Engineer may be made during
progress of work should it be found impracticable
to obtain concrete of required workability and
strength with materials being furnished by Con-
tractor; in such cases, changes in proportions or
materials or both, may be made as necessary to secure
required results.”
Utah, in its appeal, relies upon 2 of its letters addressed
to the Atomic Energy Commission; one written July 23
and one on July 31, 1953 in reference to this deficient
strength condition being due to the condition of the aggre-
gates. The first letter states, among other things that:
“a visual examination of the aggregate piles reveals... .
clean aggregate free from these objectionable small fines
while in the center .. . the aggregate is coated together
by these fines...” This letter also referred to the Com-
mission’s directive to add a bag of cement with the com-
ment: “We... will expect to be reimbursed for the
(5) bag limit.” And further, the letter concluded : ee
since the aggregate furnished by the AEC, which we are
required to use under the terms of the contract, does not
in any classification meet the specifications set up by the
contract, we cannot be responsible if the result in con-
crete does not live up to the requirements .. . we request
that steps be taken immediately to furnish us with con-
crete aggregates that will meet the specifications.”
70
The letter of July 31 had similar conclusions . . . “im-
mediate steps be taken to furnish us with aggregates...”
and, further, “. . . this letter our formal notification that
materially changed conditions have been discovered in the
quality of the aggregate . . . furnished by the AEC. More
importantly, this letter requested 4 things: “If the AEC
[fol. 93] does not elect to furnish us with... . aggregate
which will meet the specifications set forth in Paragraph
S-2-02' of the Structural Concrete Specifications:
1. The contract be modified and that compliance with
this section of the specification be waived.
2. The modifications show that this waiver is being
made at the request and for the convenience of the
Atomic Energy Commission.
3. If it is the decision of the Atomic Energy Com-
mission that the present aggregate be utilized by
the addition of one extra bag of cement per yard of
concrete mixed, that the same be considered an ad-
ditional expense to the contractor above and beyond
the original scope of the contract, which shall be
a fully unquestioned reimbursable item.
4. The modification relieve the Contractor from any
responsibility for unsatisfactory conditions that
may result from the use of the present deficient
aggregate.
The direction for the addition of one bag of cement was
effective from July 21, 1952 to October 30, 1953; after
this latter date the mix was in accordance with the orig-
inal specifications of 5 bags per cubic yard. By a report
dated November 6, 1958, tests revealed that after the
cleaning by the other contractor, the aggregates were
determined to be unusually clean.
[fol. 94] Following these events, Utah, on February 9,
1954, referring to (a) the direction to use an extra bag of
cement, and (b) its own letter of July 23 requesting re
imbursement, submitted a statement in the amount of
$8,640.00, which included provisions for the cost of cement
and for its “Supervision, General Expense, and Profit.”
1§2-01 of this Division of Technical Specifications provides in
part: “SCOPE: The Contractor shall furnish all . . . material. ..
to complete all structural concrete.”
71
(Underlines added) This statement was paid by the Com-
mission as reflected by Modification No. 6 to the con-
tract, which is particularly important in that it not only
paid the aforesaid claim, but embraced many other items
which related to other phases of the contract, such as hot
shop tunnel in a building, locomotive pit, flushwood door,
ete. The modification recited that the parties agreed to
modify the contract “in the following particulars, but in
no others;” and then followed with the one payment of
$8,640.03 for the hen ction hm oe to the cost and
genera] expense in adding a g of cement per yard.
The record in this case also reveals that the Commis-
sion engineers become dissatisfied with the rate of prog-
ress by Utah in completing the contract, and expressed its
dissatisfaction in a letter dated March 29, 1954. At or
about the same time, Utah claimed an extension in con-
tract performance time was due because of various mat-
reservation respecting any other claim or contention in any
of these 14 modifications, and until July 19, 1956, Utah
ing that it claimed $109,356, which is stated to be due
because the Commission failed tc furnish suitable aggre-
gates to Utah and it “. . . was forced to expend an ad-
ditional sum of $109,356.00, as fully shown in the at-
tached enclosures . . .”*
?It was also to this enclosure that the Contracting Officer’s mo-
tion was directed to have a more definite Statement. The enclosure
72
After the hearing of the oral argument, Utah stated
that it rested its case upon its allegation that the situa-
tion in reference to the aggregates was “an unknown
condition® of an unusual nature differing materially
from that ordinarily encountered or generally recognized
as inhering in work of the character provided for in the
plans and specifications.”
This recitation of these several facts has been made be-
cause it appears to be clear that Utah has failed to
promptly notify the Contracting Officer of any claim it
might have in relation to the condition of the aggregates.
[fol. 96] In fact, it would seem that Utah might be con-
sidered to have misled the Contracting Officer by filing a
claim in 1956 after requesting certain specific action in
its letter of July 31, 1953 which the Contracting Officer
fulfilled by cleaning the aggregates,‘ and by making the
requested payment not only for the extra bag of cement,
’ but also the “general expense” in connection with it. This
payment alone, of one general expense claim, while not
stressed at the hearing or in the motion papers, could be
construed as settlement of an account stated, which would
of itself bar any further claims. The statement of an
item in an account or claim, followed by the payment
thereof, operates to eliminate controversy in reference
thereto.
Reed v. Thomas, 134 Kans 849, 8 Pac 2nd 379
See: Restatement of Contracts, Sec, 422
Willistor. on Contracts, Sec, 1862
84 A, L. R, 114
In any event, the determination of a timely filing or
conversely, an untimely one, must depend upon the vary-
set forth a computation of cost for a certain quantity of concrete
mix, not identified for the time period involved as compared with
an estimate of a normal cost,
‘This claim of lack of knowledge is to be contrasted with the
statement in Utah’s July 23, 1953 letter that: “A visual examina-
tion of the aggregate pile . . reveals . .” coupled with its certifica-
tion at the time of its bid that it had visited the site, and also its
agreement that it understood the quality of materials required.
‘The obligation of the Contracting Officer to do this is not clear.
73
ing circumstances of particular cases.° In some instances,
perhaps a filing made 2 months after an incident alleged
to give cause to additional expense would be untimely, in
others, maybe a year after an event would be considered
timely. Whatever be the time interval, however, two
aspects of a filing are fundamental, (a) the filing must
give the Contracting Officer time to mitigate the extent
[fol. 97] of the claim, if possible, and (b) the asserted
claim must indicate an intention to claim a dollar amount.
This latter element, of course, excludes both the July 23
and July 31, 1953 jetters from being sufficient.
Appeal of Frontier Drilling Company, USAEC-BCA
DOCKET NO. 93 (1957)
The Contracting Officer contends that while consideration
of laches and estoppel are distinct, yet the necessary in-
gredients of both are present here. While those matters
might be more fully developed on a record if this case
were heard on its merits, it is concluded that there is not
any need to do so for the untimely character of the 1956
claim, which was the first indication of a dollar amount,°
seems readily apparent from the circumstances surround-
ing this transaction shown in the present record. The
filing in 1956 was made approximately three years after
the letter describing a changed condition, and approxi-
mately one and one half years after all work under the
contract had been accepted.
The Contracting Officer also argues further that to con-
sider specifically the basis urged by Utah for its claim
shows equally conclusively that the changed conditions
clause has no application. The initial facet of Utah’s
contention that the condition of the aggregate was un-
known at the time of the contract was executed in March,
letters are the basis of the appeal, the claims there made were paid;
if the 1956 letter is the basis, the time interval is more than usual
and no justification for late filing was given.
* Other than the statement of February 9, 1954, Specifying ce-
ment costs and general expense, which was paid.
74
1958 appears directly contrary to Utah’s admission 4
months later that even a visual examination of the stock-
pile showed excessive “fines”. Utah also urges that the
condition of the stockpile was as fathomless as if the
needed aggregates were underground and test borings
would lend no aid as to their character. Utah, in fact,
stated at the oral argument that it believed there was not
any difference here whether the aggregates were above
{fol. 98] ground or underground, apparently regardless
of what the visual examination revealed. The Contracting
Officer also contends that the standard changed condition
clause applies generally to an unknown underground
condition related specifically to the main objective of the
work to be accomplished, such as an excavation needed
for footings for a building contracted to be constructed.
For those situations, however, of conditions that are
readily observable the Contracting Officer contends the
relief under a changed conditions clause is not available,
and while a hearing on the merits might better enable the
Contracting Officer to present the factual support for this
contention, the disposition of the claim as untimely obvi-
ates a determination of that phase of his contention. Like-
wise, if Utah argues that the description of the aggre-
gates as “suitable” implied any warranty as to condition,
or fraud in that representation, the remedy for unliqui-
dated damages is beyond the jurisdiction of this proceed-
ing. Suffice it to say, however, that Utah rests its case
upon the changed conditions clause and the facts relied
upon by Utah do not support that view. Utah also urges that
this case be set down for hearing on the merits to per-
mit Utah to expand this presentat n, but the substance
of Utah’s claim is in the existing record. If the condition
of the aggregates was observable upon a “visual examina-
tion”, it must be presumed that Utah, the bidder, when it
visited the site, looked at what there was to see.’ Credence
must be given to Utah’s admission that it could see the
“fines” that may have caused, but it is not certain that
’ The contractor was to be charged with such knowledge of the
physical conditions of the site as could have been gained by a rea-
sonable site investigation. Bailey-Lewis-Williams of Georgia, Inc.,
ASBCA No. 4997, Army Appeals Panel 59-1, 5-11-59, BCA-2225.
that alone caused the deficiency in strength of the con-
crete mix.
(fol. 99] The foregoing determinations make it unneces-
sary to resolve the Contracting Officer’s motion for a more
definite statement by Utah of the portions of the Con-
tracting Officer’s decision from which the appeal is taken.
In addition to the foregoing findings and determina-
tions, the Hearing Examiner finds:
1. Utah Construction Company (Utah), a Utah
Corporation, was the contractor, as designated in a
contract executed un March 29, 1953 with the
United States Atomic Energy Commission for the
purpose of constructing a large assembly and main-
tenance area at the Commission’s Reactor Testing
Station in Idaho,
2. Utah duly entered upon the performance of that
contract which included the construction of several
buildings, many appurtenant facilities, as well as
the pavement of a large area with a concrete mix
specified to be laid according to a formula com-
prising ingredients in proportions detailed in the
contract, and including concrete and aggregates.
3. The contract contained a provision respecting the
availability of aggregates which were described
as suitable, as quoted in the foregoing findings,
but did not impose any obligation on Utah to use
those aggregates nor on the Commission to furnish
them,
4. The condition of the aggregates or the use of that
portion thereof containing excessive fines in the
{fol.100] concrete mix and in part causing a deficiency
in the strength requirements was corrected by the
addition of an extra bag of cement as directed by
the Commission’s engineer on J uly 17, 1953.
5. The Commission never held Utah responsible for
the condition of the concrete mix having a defiency
in the strength requirements,
6. Utah requested additional payment for the ad-
dition made by it to the concrete mix between July
21, 1958 and October 30, 1953 and the Commission
paid the amount designated in the Utah statement
which included provisions for both the added ce-
— and also for general expense as computed by
7. The Government warranty for Government-furn-
ished material provided for the performance of the
contract did not extend to the aggregates utilized
by Utah.
8. The requests made by Utah in its July 17 and
July 31, 1953 letters, after the direction to Utah
to use an additional bag of cement in the concrete
mix, were sufficiently fulfilled by the Commission
and the Commission could properly conclude in
1958 as well as on March 20, 1954, when payment
therefore was made, that Utah had no further
claim for this transaction respecting excessive fines,
or the condition of the aggregates, or for additional
general expense in connection therewith. :
9. The statement for additional expense filed by Utah
and dated July 19, 1956 in be amount of $109,356
[fol. 101] and described to be an itional cost incurred
on account of the Commission’s failure to furnish
concrete aggregate that would meet contract speci-
fications, was untimely filed and was an untimely
presentation of a specific dollar claim.
DECISION
The appeal of the Utah Construction Company in the
amount of $109,356 is denied and its claim rejected.
Further, the motion of the Contracting Officer is granted
to dismiss the appeal from the decision of the Contract-
ing Officer for failure to make a timely presentation of
its claim.
SAMUEL W. JENSCH
Presiding Officer
Issued :
October 1, 1959
Germantown, Maryland
{fol. 102]
Prex DRILLING APPEAL No, 87
MEMORANDUM OF DECISION
“ IN THE MATTER OF THE APPEAL
OF
THE UTAH CONSTRUCTION COMPANY
UNDER CONTRACT No. AT(10-1)-645
Docket No. 87
I hereby adopt the recommendation of the Advisory Board
on Contract Appeais dated April 30, 1957, that this appeal
be (1) remanded to the Contracting Officer for further
consideration of the claim for increased costs due to the
“float rock,” issue, but not as to any costs attributable to
the delay beyond the completion of the drilling and (2) be
denied in all other respects.
/8/ R. W. Cook
Deputy General Manager
[fol. 108] /s/ H. M. Leppich
UNITED STATES ATOMIC ENERGY COMMISSION
ADVISORY BOARD ON CONTRACT APPEALS
IN THE MATTER OF THE APPEAL
OF
UTAH CONSTRUCTION COMPANY
UNDER CONTRACT No. AT (10-1) -645
Docket No. 87
FINDINGS OF FACT AND RECOMMENDATION
RosBerT KINGSLEY
3518 University Avenue
Los Angeles 7
California
EDMUND R. PURVES
1735 New York Avenue, N.W.
Washington 6, D.C.
{fol. 104]
UNITED STATES ATOMIC ENERGY COMMISSION
ADVISORY BOARD ON CON TRACT APPEALS
Docket No, 87
(Pier Drilling)
IN THE MATTER OF THE APPEAL
UTAH Constmvorion COMPANY
UNDER ConTRACT No, AT (10-1) -645
FINDINGS OF FACT AND RECOMMENDATION
JURISDICTION
The present appeal was taken by the Contractor, the
Utah Construction Company, 101 Bush Street, San Fran-
cisco, California, the prime Contractors under Contract
No. AT(10-1)-645 with the Atomic Energy Commission,
on April 27, 1955, from decisions dated April 1, 1955, and
April 19, 1955, by the Manager of the Idaho Operations
Office and the Contracting Officer, Atomic Energy Com-
mission, Idaho Falls, Idaho.
The appeal is in two parts—
(1) From the Contracting Officer’s April 1, 1955, de-
cision denying the Contractor’s claim of February 18,
1955, for additiona) compensation in the amount of $17,-
784.63 for the drilling of materia! alleged to be “float
rock,” the existence of which the Contractor contended
constituted changed conditions in the pier drilling con-
tract within the meaning of Article IV—Changed Con-
ditions of the Contract; and
(2) The Contracting Officer’s decision of April 19,
1955, denying the Contractor’s
winter protection, which costs allegedly would not have
(fol. 105] been incurred had the drilling, unhampered by
float rock, proceeded in accordance with the projected
schedule of operations.
For purposes of simplification in this Findings of Fact
and Recommendation, the term “Contractor” shall desig-
nate the Utah Construction Company, the term “Subcon-
tractor” shall designate the George Casey Company of
Los Angeles, California, and the term “Architect-Engi-
neer” or “A-E” shall designate the Ralph M. Parsons
Company, the Government’s representative for conducting
the inspection of ‘the work performed under Contract
AT (10-1) -645.
Article 15 of the General Provisions of the prime con-
tract provides that:
“Disputes. Except as otherwise specifically provided
in this contract, all disputes concerning questions of
fact arising under this contract shall be decided by
the contracting officer subject to written appeal by
the contractor within 30 days to the head of the de-
partment concerned or his duly authorized represen-
tative, whose decision shall be final and conclusive
upon the parties thereto. In the meantime the con-
tractor shall diligently proceed with the work as di-
rected.”
The appeal was within the time provided and jurisdic-
tion of the Advisory Board on Contract Appeals, United
States Atomic Energy Commission, is clear.
PROCEDURE
An initial hearing in the matter was held in Confer-
ence Room “B”, Atomic Energy Building, Idaho Falls,
Idaho, on November 11, 1955. Although two other wit-
nesses were called and testified, the initial hearing was
held primarily to accommodate one of the Government
witnesses, Mr. McDowell, who was available only on that
occasion, being present in the room when the hearing
on Docket 76 was taking place and being one of the wit-
nesses on that other case. Mr. McDowell was due to
leave for foreign lands at the termination of the hearings
81
{fol. 106] on November 11, 1955. The hearing was re-
sumed in Room 59, Federal Office Building, Civic Center,
San Francisco, California, on J anuary 24, 1956, before
Advisory Board members Edmund R. Purves and Robert
Kingsley. Gardiner J ohnson, Esquire, of the firm of
Johnson and Stanton, San Francisco, California, and
Peter Jacobson, Esquire, of San Francisco, California,
appeared on behalf of the Contractor ; W. L. Rowberry,
Esquire, Attorney of Idaho Falls, Idaho, appeared on be-
half of the Atomic Energy Commission, Mr. Purves act-
ed as Chairman of the panel,
At the termination of the hearing both parties were
requested to submit briefs,
The hearings were time-consuming and the files in this
case are voluminous. In the opinion of the Board, both
the time consumed and the material in the files are exces-
sive inasmuch as the issue itself is relatively simple and
the questions more or less factual. It appeared to the
Board that much of the testimony was irrelevant. The
Board must make mention of the fact that it was ham-
pered by the absence of qualified expert witnesses,
BACKGROUND
The Utah Construction Company, prime Contractors
for the construction of Assembly and Maintenance Area,
Aircraft Propulsion Project, Contract AT (10-1) -645,
USAEC National Reactor Testing Station, Idaho Falls,
Idaho, included in its contract the drilling and excavation
for piers or foundation shafts. The Subcontractor under
the Contractor for this drilling and excavation was
the George Casey Company of Los Angeles, California.
However, the Contractor’s claim is on behalf of itself.
The hearings were not concerned with any dispute be-
tween the Contractor and its Subcontractor or any
(fol. 107] relations between the two. The Contractor
claimed that, in excavating for or drilling the shafts for
the piers, conditions were encountered differing materi-
ally from those indicated on the contract documents and
from the data furnished by those documents. The prin-
cipal deviation from the furnished data is alleged to have
the existence of, and the encountering of, what is
spoken of throughout this issue as “float rock.” This is
a term not universally used in the construction industry
throughout the United States. However, it does appear
to be a term which is simply expressive in itself to de-
seribe a condition. This condition is the existence of in-
dividual stones or rocks of various sizes, detached from
the principal bedrock by glacial or other geologic action,
and subsequently covered by silt or other deposits so that
the individual stones or rocks are suspended in the de-
posits below the surface of the ground. (When such
stones or rocks have worked their way to the surface
they are generally known as field stone.) However, it is
possible for “float rock” to exist below the surface and,
by reason of the absence of field stone on the surface of
the ground, give no indication of its existence. It is
also conceivable that core borings will fail to reveal the
existence of “float rock.” Float rock obviously presents
difficulties in excavating and extracting the excavated
material, especially when the excavation is confined to a
series of holes of relatively small diameter. In such cir-
cumstances, float rock would present, to the excavator, a
problem of extraction, comparable in difficulty with the
excavating and extraction of solid rock. No indication of
the existence of “float rock” was furnished to the Con-
tractor. The Government may not have been aware of
the existence of float rock, and we assume that it was not.
(fol. 108] Lava contour maps were furnished showing
the depth at which solid lava rock would be encountered
as near as the depth could be ascertained from borings.
Borings are admittedly an indifferent method at. best,
but the only method currently available. It developed at
the hearing that bedrock was encountered in some places
above the levels indicated on the drawings. The Contractor
claimed that the Government withheld information and
that the encountering of the “float rock” considerably de
layed the excavation, to such an extent that the Con-
tractor was forced into protecting the subsequent concrete
work against the winter weather. The excavation was
actually the form for the concrete piers to support the
building. Delays were encountered which brought the
actual pouring to the winter months with a consequent
risk of damage by freezing—a risk which the Contractor
had to guard against and the cost for which guarding
was not included in his original contract.
The Government claimed that the excavator did not
ciently; his equipment was old and faulty; and the gen-
eral operational problems, which included the traffic
problems incident to the hauling away of excavated ma-
terial, were not solved skillfully.
(fol. 109] By letter of June 1, 1953, the Contractor al-
leged sub-surface conditions materially different from those
shown on the drawings and indicated and described in
the specifications and ceased operations for pier drilling
ae ameordance with Article 4 of the contract, which is as
ollows:
they are disturbed. The contracting officer shall
thereupon promptly investigate the conditions, and
if he finds that they do so materially differ the con-
tract shall, with the written approval of the head
of the department or his duly authorized representa-
tive, be modified to provide for any increase or de-
crease of cost and/or difference in time resulting
from such conditions.”
The Commission wrote the Contractor on June 2, 1953,
directing it to proceed with the work. On the basis of its
June 1, 1953, notice, the Contractor, by letter of Febru-
ary 18, 1955, and its enclosures, presented a claim for
$17,934.63 for the increased cost of excavation resulting
from encountering the “float rock.” As noted, by its
letter of March 31, 1955, the Contractor claimed an ad-
ditional $83,431.46, as the increased costs of construction
of the building resulting from the delays caused by the
“float rock” problemi.
DISCUSSION
For the reasons set out below, the Board concludes:
(1) That “float rock” was encountered and that this
did constitute a “changed condition” within the meaning
of Article 4;
(2) That this condition caused some delay in the drill-
ing operations;
ffol.110] (8) But that this delay did not operate to
delay the building construction; and
(4) That no additional cost to the Contractor resulted
from the “float rock” condition, except insofar as it is
liable over to its subcontractor.
As in other cases that have come to the attention of
the Board, we find here that the absence of qualified ex-
pert testimony on behalf of either party is not only a
source of annoyance, in that the Board does not feel con-
fident that all questions have been answered correctly
from a technical point of view, but also we feel that
the presence of expert witnesses would have served to
expedite hearings. It seems to the Board that in this
case the question as to whether or not the Contractor
encountered conditions unanticipated by anyone (assum-
ing, as we do, that the Government was not privy to in-
formation which it did not afford the bidders) should have
been relatively simple to determine. Such a determina-
tion did not require a parade of witnesses, some of whom
threw little light on the issue before the Board. It is
true that the Government produced two witnesses, Mr.
West and Mr. McDowell, who though not technically
trained, nevertheless possessed sufficient rudimentary ex-
corollary questions as to whether or not the Contractor’s
operation was performed efficiently. Here we have only
the off-the-cuff criticism of men who were not trained
or experienced in the multitude of problems involved in
excavating and in the disposing of the excavated materi-
als, and in the other hampering physical conditions, but
(fol. 111] also were unable to comment expertly on such
questions as to whether or not the delays encountered or
assumed were sufficient to force the Contractor into pour-
ing concrete during winter conditions. The Board, there-
fore, has had to draw its own conclusions from the tes-
timony of partisan witnesses who were not necessarily
completely expert in those fields on which they were
testifying.
It is recognized that much of the evidence in general in
courts is circumstantial and from biased witnesses, but
in this instance we are dealing with questions of fact and
questions of scientific knowledge, which, if properly pre-
sented to the Board, would facilitate the work of the
Board and expedite the settlement of the issues involved.
I
The basis issue around which this dispute revolves is
whether or not the existence of what is termed “float
rock” constituted an unforeseen and unknown condition
causing delay within the meaning of Article 4. There
certainly would appear to be sufficient evidence that
“float rock” was encountered. Whether or not this might
have been foreseen is open to very little conjecture in the
eyes of the Board.
On one of the estimated drawing (No. ANP-004-IDO-
1) the diagram of the results of the core borings indi-
cates the existence of gravel at approximately elevation
4732 feet. It is significant that the existence of gravel
appears, insofar as the estimating drawings are con-
cerned, in only one location. If this existence of gravel
had been indicated in more than one location, then the
bidder might have assumed that gravel existed in general
throughout the area. If the Government had reason to
imagine that gravel or “float rock” was prevalent through-
out the area, then it was culpable in not having advised
{fol. 112] the bidders of its belief. Test borings are in-
conclusive but they are our only present means of deter-
mining subsurface conditions. Presumably at some future
date science will dévise a method of accurately disclos-
ing subsurface conditions throughout an entire given
area. Test borings are essentially spot checks and ob-
viously incomplete and inconclusive.
The Board is of the opinion that, following common
practice and procedures and customary assumptions, the
Contractor was well within its rights in estimating that
the excavation would be simple and capable of being per-
formed by rotary rigs until bedrock was struck.
The Board is intrigued by the theory (expressed in the
Contracting Officer’s Findings) that the term “gravel”
ean include “float rock.” Although there appears to be a
dictionary definition which would substantiate this as-
sumption, we are sure that it would be a rare Contractor
in any part of the United States who would think that
gravel is anything other than an ingredient of concrete,
the material for the foundation bed of a slab, or the
material for a garden path—none of which would present
serious difficulties in extracting from mother Earth.
The contract called fox various types of estimates on
excavation. Naturally, the excavation of simple earth
costs the least per vuit measure excavated. Un
87
material would cost more than simple earth, and bedrock,
naturally, would be the most expensive to excavate.
There is some question as to the classification in which
“float rock” would fall. It is the opinion of the Board
that “float rock” would be unclassified. It is obvious to
anyone with any experience in digging, or to any farmer
or rancher who has ever dug holes for fence posts, that
digging proceeds with ease until stone is encountered.
Digging with ordinary implements through solid rock is
impossible and extracting loose stone from a post hole,
(fol. 113] the stone being imbedded in the earth, is
difficult with varying degrees. In any case, it is far more
difficult and time-consuming than the excavating of earth.
The difficulty increases with the size of stone encountered ;
and when the stone exceeds in diameter ihe diameter of
the excavation the difficulty may be nearly as @reat as if a
solid rock were encountered, and equally as difficult if
the stone is of any appreciable depth. In fact, “float
rock” (if the term “gravel” is used to describe it) could
be of sufficient size as to constitute bedrock for all prac-
tical purposes.
The testimony is not clear as to the amount and kind of
“float rock” encountered, but that it was encountered by
the Contractor does not appear to have been successfully
contradicted by the Government.
A considerable amount of testimony revolves around
and efficiency of planning with
rotary rig was obviously pro-
y_make inefficient use of the equipment
at his disposal. We find that the selection of equipment
[fol.114] A second criticism of efficiency advanced by
the Government concerns the maneuvering of equipment
on the site and the sequence of drilling the several shafts
as they were sunk, and the traffic problems incidental
to the arriving, loading and departing of trucks. There
was no evidence presented to convince the Board that the
Contractor had not organized his work and carried out
his part of the work in as satisfactory a method as was
possible under the circumstances which prevailed. Again
we find that the procedures used were reasonable and
proper.
The Government claimed that, under General Condition
II, it was incumbent upon the Contractor to satisfy him-
self as to the conditions encountered. However, manifest-
ly a Contractor cannot satisfy himself as to subsurface
conditions unless some information is given to him. He
can only assume that conditions will be satisfactory and
if he assumes they are unsatisfactory, then the latter
assumption, when taken in competition with other bid-
ders who have not mage the assumption, are almost cer-
tain to insure that he will lose the award of the contract,
especially in public bidding. The Board does not find
the Government’s position tenable on its insistence on a
liberal interpretation of General Condition II. This is
insisting on the Contractor’s gambling extensively on the
unknown. A good deal of testimony and time at the
hearing was taken up with matters relating to the au-
thorship, authenticity, and even whereabouts of certain
charts and work records. It is not clear to the Board
how these documents would assist in determining wheth-
er or not changed conditions had occurred, although they
might have thrown some light on the amounts that might
be due the Contractor, should the Contractor’s claims
for delay have been upheld.
It is worthy of note that bedrock was encountered in
places at elevations higher than had been indicated or
anticipated. This, while resulting in a saving to the
(fol. 115] Government, does not reflect well on the ac-
curacy of the information which the Government fur-
nished to the bidders.
II
The Government claims the following:
“1, The concrete batch plant operated by the Contrac-
tor (Tr. p. 146) was not put into operation until
May 26, 1953 (Tr. pp. 227-285), by which time
over thirty pier holes had been drilled and were
available for the pouring of concrete piers (Gov.
Ex. I).
“2. The drilling of pier holes remained substantially
ahead of the concrete pouring of piers until ap-
proximately the 29th of June (Gov. Ex. I), and
the concrete pouring of piers was never delayed
for lack of an available pier hole in which con-
crete could be poured (Tr. p. 121),
“8. At times pier holes were
and there is evidence that drilled pier holes had
area was completed by July 3, 1953 (Tr. pp. 820,
821), but the concrete for the storage pool was
not poured until approximately July 30, 1953, al-
most four weeks later (Tr. pp. 232, 2388). This
delay occurred as a result of a question concern-
ing the quality of the concrete aggregate (Tr. pp.
249, 250).
“5. No concrete was poured on July 17, 18, 19 and
20, again due to the question concerning the quali-
ty of the concrete aggregate (Tr. pp. 253-255),
and the concrete pouring operations were limited
thereafter, allegedly for the same reason (Tr. pp.
260-270).
“6. All placement of concrete for piers had been com-
pleted by July 31, 1953 (Tr. p. 169; Enel. 7),
but concrete pouring of the first wall for Building
No. 607 did not commence until August 11, 1953
(Tr. pp. 245, 250) [although the forms had been
placed three weeks prior to that time (Tr. p. 271) ],
due to the question concerning the quality of the
concrete aggregate (Tr. p. 245), and the concrete
pouring did not proceed steadily thereafter, but
was delayed due to other interruptions unrelated
to the pier drilling (Tr. p. 250).
“7, All placement of concrete for the piers w
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.