Appendix — Citizens' Utility Ratepayer Board v. Kansas Pipeline Partnership
Supreme Court brief1997
Ask Donna
What actually matters in this document.
Text
og F&O
W) 96 956 DE 9 19%
opect OF iit CLERK
No.
TEE TEE EEE
IN THE
SUPREME COURT OF THE UNITED STATES
OCTOBER TERM, 1996
CITIZENS’ UTILITY RATEPAYER BOARD,
Petitioner,
Vv.
KANSAS PIPELINE PARTNERSHIP,
Respondent.
On Petition for Writ of Certiorari
to the Supreme Court of the State of Kansas
APPENDIX TO PETITION FOR
WRIT OF CERTIORARI
Walker Hendrix Mark A. Burghart
Counsel of Record Alderson, Alderson &
Citizens’ Utility Montgomery, L.L.C.
; Ratepayer Board 2101 S.W. 21st Street
1500 S.W. Arrowhead Road Topeka, Kansas 66604
Topeka, Kansas 66614 (913) 232-0753
(913) 271-3200
SP RS OES UII: AN, oe AE
APPENDIX A
SUPREME COURT ORDER DISTRICT CASE NO.
IN THE SUPREME COURT
OF THE STATE OF KANSAS
DAVID P BATOW
WILLIAMS NATURAL GAS COMPANY
LEGAL DEPT 36TH FL
P O BOX 3288
TULSA OK 74101
KANSAS PIPELINE
PARTNERSHIP, PETITIONER,
V No. 96-75918-AS
THE STATE CORPORATION
COMMISSION OF THE STATE
OF KANSAS, RESPONDENT.
YOU ARE HEREBY NOTIFIED OF THE FOLLOWING
ACTION TAKEN BY THE COURT:
PETITION’S FOR REVIEW BY CURB, KCC &
WILLIAMS NATURAL GAS.
CONSIDERED BY THE COURT AND DENIED.
RESPONSES NOTED.
KCC DOCKET NOS. 192,506-U AND 192,507-U
DATE: 09/09/96.
CAROL G. GREEN
CLERK
APPENDIX B
No. 75,918
IN THE COURT OF APPEALS OF THE STATE OF
KANSAS
KANSAS PIPELINE PARTNERSHIP,
Appellant,
V.
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS,
Appellee.
SYLLABUS BY THE COURT
l. The Court of Appeals has exclusive jurisdiction to
review any action of the Kansas Corporation Commission
arising from a rate hearing. K.S.A. 1995 Supp. 66-118a(b).
2. The order under review in this case constitutes a
final agency action subject to judicial review.
3. K.S.A. 77-607 and K.S.A. 77-608 are construed and
applied.
4. K.S.A. 1995 Supp. 66-117 is construed and applied.
a The scope of review of an agency action is set forth
in K.S.A. 77-621, which codified principles long recognized
by Kansas courts.
6. The cardinal rule of statutory construction is that the
intent of the legislature governs if that intent can be
ascertained.
7
te If a general and a specific statute both apply to a
given situation, they should be read together and harmonized
when possible.
8. The Kansas Corporation Commission’s authority is
limited to that conferred by statute.
9. A final order is one which terminates litigation on
the merits and leaves nothing to be done except to enforce
the result. In an agency setting, a final order needs to be
more than a mere procedural ruling.
10. In an administrative setting, finality should be
interpreted in a pragmatic way.
11. An agency’s interpretation of a statute should be
given deference, but when reviewing a question of law, an
appellate court may substitute its judgment for that of the
agency.
i The legislature is presumed to understand the
meaning of the words it uses and the procedures it
establishes.
13. When a statute is clear and unambiguous, a court
must give effect to the legislature’s intent as expressed,
rather than determine what the law should or should not be.
14. An amendment involves a change or modification
and suggests an action by one of the parties to change,
correct, or revise.
15. Ordinarily, a change in statutory language is
presumed to result from a legislative purpose to change its
2
a en i A a
effect, but the presumption is of little force if an amendment
is adopted as part of a general, technical revision to a
statute.
16. Under the peculiar facts of this case, the relief
sought by Kansas Pipeline Partnership was deemed approved
by operation of law when the Kansas Corporation
Commission failed to finally act within 240 days of the
application and when neither of the exceptions of K.S.A.
1995 Supp. 66-117(b) applies.
Appeal from the Kansas Corporation Commission.
Opinion filed May 17, 1996. Reversed.
James P. Zakoura, Richard W. Hird, and David J.
Roberts, of Smithyman & Zakoura, Chartered, of Overland
Park, and Fred J. Logan, Jr., of Logan & Logan, L.C., of
Prairie Village, for appellant.
Larry M. Cowger, of Kansas Corporation
Commission, for appellee.
Mark A. Burghart and W. Robert Alderson, of
Alderson, Alderson & Montgomery, L.L.C., of Topeka, for
intervenor Citizens’ Utility Ratepayer Board.
John C. Frieden and Kevin M. Fowler, of Frieden,
Haynes & Forbes, of Topeka, and David P. Batow and Gary
W. Boyle, of Williams Natural Gas Company, of Tulsa,
Oklahoma, for intervenor Williams Natural Gas Company.
Before ELLIOTT, P.J., ROYSE and KNUDSON, JJ.
ELLIOTT, J.: Kansas Pipeline Partnership (KPP)
and Western Resources, Inc., (WRI) entered into natural gas
sales and transportation contracts. KPP submitted the
contracts to the Kansas Corporation Commission (KCC) for
approval pursuant to K.S.A. 1995 Supp. 66-117(a). WRI.
also requested KCC approval of the contracts and requested
permission to pass contract costs through to its customers.
Complicating matters, the KCC shifted a $ 5.9 million
Linchpin Development cost item from another rate hearing
into this KPP application. The other rate hearing is currently
pending in this court as appeal No. 75,730.
On judicial review, KPP asserts that because the KCC
failed to make a decision on these contracts and the
development cost item within time limits established by KCC
regulations and K.S.A. 1995 Supp. 66-117(b), the contracts
and other requested relief became "deemed approved" by
operation of law. This is the ultimate question for us to
decide on the merits of this appeal.
We agree with KPP and reverse.
A brief description of the major participants is as follows:
KPP is a natural gas public utility and the applicant before
the KCC.
The KCC is the state regulatory agency with the
power and authority to supervise and control intrastate
natural gas public utilities doing business in Kansas. See
K.S.A. 66-101 et seq.
WRI is a class A natural gas public utility,
authorized to deliver natural gas to customers in Kansas, and
4
was the other signatory to the KPP contracts for which
approval was sought. WRI also sought approval of the
contracts, but has not appealed the matter to this court.
Williams Natural Gas Company (WNG) is also a
natural gas public utility and is a marketplace competitor of
KPP.
The Citizens’ Utility Ratepayer Board (CURB) is a
state agency created to look out for the interests of
individuals and small businesses in regulating public utilities.
The Federal Energy Regulatory Commission (FERC)
is a federal agency regulating interstate pipelines which are
within its exclusive jurisdiction.
The five contracts may be summarized thus: The
contracts between KPP and WRI call for the sale and
transportation of increased volumes of natural gas for
delivery in Johnson, Wyandotte, Franklin, and Miami
Counties in Kansas. Two of the three gas purchase contracts
require KPP to deliver natural gas to the city gates at
Ottawa, Paola, and Osawatomie for a term of 20 years. The
third gas purchase contract calls for KPP to transport and
sell natural gas to delivery points in Johnson and Wyandotte
Counties for a term of 10 years.
The two transportation contracts call for the
construction of a 24-mile pipeline spur to connect the
Panhandle Eastern Pipeline Company’s facilities to those of
WRI (the "Metcalf Contract"), and for KPP to provide
natural gas to WRI for Johnson and Wyandotte Counties
commencing in the year 2009 (the "2009 Contract").
Jurisdiction
Without detailing the various dates on which various
pleadings were filed, we have determined the jurisdictional
filings by KPP are timely.
We have exclusive jurisdiction to review any action
of the KCC arising from a rate hearing. K.S.A. 1995 Supp.
66-118a(b). In KPP’s original filing, it did not request a
rate increase, but WRI did. The WRI docket was
consolidated with the KPP filing. Additionally, the joinder
of the Linchpin Project Development costs into this
proceeding made it an action intimately related to a prior
rate case. See MAPCO Intrastate Pipeline Co. v. Kansas
Corporation Comm’n, 10 Kan. App. 2d 527, 530-31, 704
P.2d 989 (1985); In re Application of Southwestern Bell Tel.
Co., 9 Kan. App. 2d 525, 529, 685 P.2d 304, rev. denied
236 Kan. 875 (1984).
The parties seem to agree that this case is closely
enough connected to an underlying rate case to give us
jurisdiction.
While we have determined we have jurisdiction
under K.S.A. 1995 Supp. 66-118a(b), a question still
remains whether the KCC order of November 22, 1995, is
reviewable.
By applying the relevant considerations of
Southwestern Bell, the KCC order is a final agency action
entitling KPP to judicial review. The KCC’s denial of
KPP’s arguments that the contracts were "deemed approved"
due to the expiration of time is a final decision on this issue.
It has a direct effect on KPP and presents a legal question
6
for our review. Further, ruling on this issue does not
disrupt the orderly process of adjudication in the
administrative proceeding. The November 22, 1995, KCC
order is final agency action subject to review.
In Southwestern Bell, we did not clearly state whether
we were considering a final agency decision or a nonfinal
agency decision ripe for interlocutory review. Either way,
we have jurisdiction to consider KPP’s appeal. See K.S.A.
77-607(b), K.S.A. 77-608.
Merits
In orders mailed April 21 and 24, 1995, the KCC
suspended the effective dates of the contracts for 180 days of
their filing on March 31, 1995; the WRI rate request and the
KPP contract dockets were consolidated. After numerous
continuances, hearings were finally conducted between
August 21, 1995, and September 6, 1995. At the close of
the hearings, the KCC closed the record, ordered briefs filed
by October 6, 1995, and took the dockets under advisement.
After briefs were filed but before the KCC issued a
decision, FERC issued a draft order stating it had
jurisdiction over KPP as an interstate pipeline. When FERC
asserts jurisdiction, any state regulatory agency loses
jurisdiction. As a result, the KCC staff on November 1,
1995, requested a stay pending a final order from FERC.
KPP opposed the stay. The KCC issued a stay on November
3, 1995, and on November 22, 1995, issued an order
superseding the earlier order, in which it found:
(1) Expiration of the initial 180-day time period set by
the KCC did not cause the contracts to be deemed
7
(2)
(3)
(4)
(1)
(2)
approved because that order was subject to further
KCC orders and KPP did not object to the closing of
the record as of October 6, 1995 (beyond the 180-day
period);
The KCC order of November 3, 1995, which was
within the 240-day limitation of K.S.A. 1995 Supp.
66-117(b) was “probably a sufficient adjudication
within the 240-day period of time";
The KCC restarted the 240-day clock called for by
K.S.A. 1995 Supp. 66-117(b) because the FERC
finding of jurisdiction over KPP was a "substantial
alteration of the facts" forming the basis for the KPP
request; and
"a continued stay at this juncture serves the public
interest especially in light of the unbundling concerns
raised by staff should FERC ultimately find it has
jurisdiction" over KPP.
On December 8, 1995, several things occurred:
FERC stayed its assertion of jurisdiction over KPP
and clarified that KCC orders regarding KPP will
remain in effect until FERC made its final rulings in
the case.
The KCC denied KPP’s request to reconsider its
November 3, 1995, order because it was superseded
by the KCC order of November 22, 1995.
(3) KPP requested reconsideration of the November 22
KCC order, which was denied on December 28,
1995.
(4) | FERC issued an order clarifying a prior order. In
this order, FERC stayed its assertion of jurisdiction
over KPP until 60 days after an order on the merits
of petitions for rehearing. FERC also ruled that,
meanwhile, KPP could continue to provide services,
collect rates on file with the KCC, and “undertake all
other activities authorized by [FERC] and the KCC."
(Emphasis added.)
On appeal, our scope of review is set forth in
K.S.A. 77-621, which codified principles repeatedly
recognized by Kansas courts. See, e.g., Kansas Gas &
Elec. Co. v. Kansas Corporation Comm’n, 239 Kan. 483,
497-98, 720 P.2d 1063 (1986); Midwest Gas Users Ass’n v.
Kansas Corporation Commission, 3 Kan. App. 2d 376,
380-81, 595 P.2d 735, rev. denied 226 Kan. 792 (1979).
Further, we recognize that the cardinal rule of
statutory construction is that the intent of the legislature
governs if that intent can be ascertained. City of Wichita v.
200 South Broadway, 253 Kan. 434, 436, 855 P.2d 956
(1993).
As indicated earlier, at the close of the technical
hearings, the KCC ordered the filing of briefs by October 6,
1995. KPP did not object to the October 6 date, although it
was beyond the 180 days mentioned in the original
suspension orders which expired on September 27, 1995.
Accordingly, we shall concentrate our evaluation of this
appeal on the 240-day limitation contained in K.S.A. 1995
Supp. 66-117(b).
The KCC has never suggested this case is not
controlled by K.S.A. 1995 Supp. 66-117(b). Although the
Statute does not specifically list "gas purchase contracts" or
"gas service agreements," clearly these would fall within
"practice pertaining to the service or rates of such public
utility." See K.S.A. 1995 Supp. 66-117(a).
CURB argues this case is governed by K.S.A. 1995
Supp. 66-1,203, which specifically applies to natural gas
public utilities. Pursuant to that statute, every natural gas
public utility regulated by the KCC must furnish the KCC
with copies of all contracts between natural gas public
utilities and all jurisdictional services to be rendered by the
utility. WNG also urged this position during oral arguments.
This statute applies specifically to natural gas public utilities
regulated by the KCC, while K.S.A. 1995 Supp. 66-117(b)
merely applies to all public utilities regulated by the KCC.
If a general and a specific statute both apply to a
given situation, they should be read together and harmonized
when possible. See Kansas Racing Management, Inc. v.
Kansas Racing Comm’n, 244 Kan. 343, 353, 770 P.2d 423
(1989). The provisions of these two statutes can be read
consistently.
K.S.A. 1995 Supp. 66-117(b) applies when any
public utility is requesting a change in its rates or services
that will have an impact on its customers. On the other
hand, 66-1,203 requires a natural gas public utility to file
copies of its rates and contracts, even if no changes are
10
—
requested. Although the statutes overlap to some extent, they
are not inconsistent and both are applicable.
At last, we reach the core question for our
determination: Is KPP’s request for relief “deemed
approved" by the KCC’s failure to issue a final order on the
proposed changes within the 240-day period mandated by
K.S.A. 1995 Supp. 66-117(b)? We answer in the
affirmative.
Preliminarily, at oral argument, the KCC
acknowledged that 66-117 is the only statute permitting
suspension of an effective date, and CURB candidly, but
reluctantly, agreed that 66-117 controls this appeal.
No one contests that the KCC’s authority is limited
to that conferred by statute. Cities Service Gas Co. v. State
Corporation Commission, 197 Kan. 338, 342, 416 P.2d 736
(1966); Kansas-Nebraska Natural Gas Co. v. Kansas
Corporation Commission, 4 Kan. App. 2d 674, 675, 610
P.2d 121, rev. denied 228 Kan. 806 (1980). We must
determine what now happens when the KCC fails to exercise
the power conferred on it by statute.
K.S.A. 1995 Supp. 66-117(b) specifically provides
that the KCC shall not delay the effective date of a proposed
change in rate or many practice pertaining to service for
more than 240 days beyond the date the utility filed its
application with the KCC.
The statute further provides that if the KCC has not
issued a final order within those 240 days, then "the
schedule shall be deemed approved by the commission and
the proposed change shall be effective immediately, except
il
that (1) ... amy amendment to an application . . . which
increases the amount sought by the public utility . . . or
substantially alters the facts used as a basis for requested
change . . . shall, at the option of the commission, be
deemed a new application and the 240-day period shall begin
again from the date of the filing of the amendment, and (2)
if hearings are in process before the commission . . . on the
last day of such 240-day period, such period shall be
extended to the end of such hearings plus 20 days to allow
the commission to prepare and issue its final order." K.S.A.
1995 Supp. 66-117(b) (Emphasis added.)
No one contends the hearing was "in process before
the commission" on the 240th day. The KCC closed the
record and took the matter under advisement prior to
expiration of the 240-day period. The question is whether
either of the KCC orders of November 3 and 22, 1995, was
a "final order" for purposes of 66-117(b). If so, both were
entered within the 240-day clock. If not, we must decide
whether the KCC acted properly in restarting the 240-day
clock. We note that the KCC closed the record in these
consolidated dockets at the conclusion of hearings on
September 6, 1995. So far as we can determine, the KCC
never reopened the record in these consolidated dockets.
See K.A.R. 82-1-230(k), (1).
KPP filed its request for approval of the five
contracts on March 31, 1995; the 240th day thereafter would
be November 29, 1995. On November 2, FERC issued a
draft order asserting jurisdiction over KPP, and on
November 3 the KCC, sua sponte, determined the dockets
should be stayed.
12
Then on November 22, 1995, the KCC issued
another order affirming its order of November 3 and
ordering these dockets be stayed until FERC took final,
appealable action. This order also purported to restart the
240-day clock ("to the extent, if any, that it applies") as of
November 2, 1995. The KCC also stated its November 22
order superseded its November 3 order.
"Final order" has been defined as one which
terminates the litigation on the merits and leaves nothing to
be done except to enforce the result. lack’ Ww
Dictionary 630 (6th ed. 1990). In an administrative setting,
a final order needs to be more than a mere procedural
ruling, and "finality" should be interpreted in a pragmatic
way. Southwestern Bell Tel. Co. v. Kansas Corporation
Commission, 6 Kan. App. 2d 444, 452-53, 629 P.2d 1174,
rev. denied 230 Kan. 819 (1981). See Oilfield Fluid Motor
Carriers v. Kansas Corporation Comm’n, 234 Kan. 983,
988, 677 P.2d 982 (1984).
In the present case, the KCC orders enter a stay
pending a decision by FERC. A "stay" is a suspension of a
case. Black’s Law Dictionary 1413 (6th ed. 1990). By
entering a stay, the KCC did not issue a final order in the
proceeding.
Accordingly, this case presents a good example of
when a KCC order can be final agency action under
77-607(b)(1), but not a final order under 66-117(b). The
KCC’s decision rejecting KPP’s argument the contracts
should be deemed approved (66-117[b]) is a final ruling on
that statutory interpretation question. Nothing is unresolved,
rendering it a final agency action under 77-607(b)(1). On the
other hand, since the KCC has made no ruling regarding
13
whether KPP’s contracts should be approved, it has not
entered a final order on the proposed changes under
66-117(b).
As WNG argues, both times the "deemed
approved" language appears in the statutes, the phrase refers
to a "schedule." "Schedule" is not defined in any statute or
any KCC regulation which we have been able to discover,
and the parties have not referred us to any such definition.
The general definition of "schedule" would cover almost any
filing, and pragmatically, we conclude the KPP contracts and
other documents appended to its application meet the
requirement of a schedule. See K.A.R. 82-1-231; Black’s
Law Dictionary 1344 (6th ed. 1990).
The KPP contracts would change the practices
pertaining to services made available by KPP for WRI’s
customers. Accordingly, the changes set forth in the
contracts fall under the provisions of 66-117(b) requiring
KPP to request approval of the changes.
Before leaving this aspect of the case, we need to
discuss the legislative history for 66-117. Dramatic changes
were made to KCC procedures in 1980 by the enactment of
S.B. 881. L. 1980, ch. 200. Minutes of hearings before the
House Ways and Means Committee on the bill make clear
the legislature was aware it was making significant changes.
Minutes to a hearing on April 8, 1980, report that Senator
Frank Gaines supported the bill which would permit a utility
to automatically get the increase sought when the KCC did
not act within a certain time frame. See House Ways and
Means Committee, 1980 Session, Minutes of April 8, 1980,
p. 1. Throughout the debate on S.B. 881, the KCC was
14
given only 180 days to decide a case, but the final bill
changed this to 240 days.
Most of the testimony before the Ways and Means
Committee uses the term "utility rate cases" in discussing the
bill, but the term is never defined. Further, "schedule" is
not mentioned, except in a proposed draft of the bill. A main
proponent of the bill was Southwestern Bell Telephone
Company (SWB), which argued time limits were not new
and had been adopted by numerous regulatory agencies
across the country. Testimony of Bill Ewing (SWB),
Attached to Minutes of House Ways & Means Committee,
April 8, 1980.
Opposing S.B. 881 was Pete Loux, then chair of the
KCC. He argued the states which had adopted time limits
had much larger staffs or were responsible for regulating
fewer companies. Chairman Loux also presented a staff
position paper authored by Brian Moline, then general
counsel of the KCC. Moline expressed concern that the
language of S.B. 881 was very broad and cautioned that the
bill "changes long established public policy of Kansas."
KCC Staff Position on S.B. 881, Attached to Minutes of
House Ways & Means Committee, April 8, 1980, at 4.
Our review of the legislative history convinces us the
purpose of S.B. 881 was to adopt time limits to remedy
delays utilities had experienced with the KCC. Nothing in
the legislative history suggests the legislature intended to
distinguish between "pure" rate cases and hybrid cases that
could be considered “arising from a rate hearing" and thus
appropriate for exclusive review by this court.
15
While S.B. 881 does not refer specifically to
66-118a, giving us exclusive jurisdiction over appeals arising
from a rate hearing, the bill did amend 66-118g, setting the
time limits in which we must decide such cases.
Nothing we have discovered suggests the time limits
covered by S.B. 881 were intended to be different for rate
cases under 66-117 as opposed to cases arising from a rate
hearing pursuant to 66-118g. If a case arises from a rate
hearing for purposes of 66-118g, legislative history suggests
the time limits of 66-117(b) would also apply.
No one really contests that this case is one arising
from a rate hearing. Under the express language of
66-117(b), the schedules/contracts are deemed approved and
the proposed changes take effect immediately unless a final
order is issued by the KCC within 240 days of KPP’s
application, or unless one of the exceptions applies.
Here, no final order was issued. As a result, our final
question is whether the KCC had the statutory power and
authority to restart the 240-day clock under the peculiar facts
of this case.
K.S.A. 1995 Supp 66-117(b) provides that after 240
days, the schedule is deemed approved except where an
amendment to an application seeks an increase in the amount
sought or substantially changes the facts used as a basis for
the requested change.
The KCC interprets the statute broadly to include
any change of the facts, regardless of whether an amendment
to the application has been filed. We are unable to agree
with the KCC’s interpretation.
16
eyre xe eS
Here, none of the parties filed any amendment to the
application for proposed change that increased the amount
sought by the KPP. Thus, the only way this proceeding
could be extended is if the KCC were correct in finding (1)
that FERC’s preliminary assertion of jurisdiction
substantially altered the facts used as a basis for the
requested change and (2) that this gave the KCC the option
to deem a new application had been filed.
The KCC does not directly address the problem
created by the failure of anyone to file an amendment to the
application. CURB does not address the need for an
amendment either; rather, it argues the KCC was in
substantial compliance with the statutory mandate when it
restarted the 240-day clock. WNG asserts that 66-117(b)
simply does not apply. As previously held, the legislature
did not distinguish between types of rate hearings in enacting
S.B. 881. The legislature intended the time limits to apply to
all hearings requesting a change, including those arising
from a rate hearing.
KCC regulations provide for specific procedures to
follow when a public utility wants to revise or amend its
application or schedules. See K.A.R. 82-1-231(d). Further,
Chairman Loux, in his letter to Mike Hayden, then chair of
the House Ways and Means Committee, specifically voiced
his concern whether an amendment by an applicant would
restart the time clock. Loux Memo dated April 8, 1980,
attached to House Ways and Means Commitiee Minutes.
FERC issued its initial order on November 2, 1995.
Yet in its order of November 22, the KCC recognized it had
continuing jurisdiction over KPP. FERC then stayed its
earlier order and clarified that KPP was allowed to undertake
17
all activities authorized by the KCC. The KCC did not issue
its order denying KPP’s petition to reconsider until
December 28, 1995.
The KCC argues that the FERC order asserting
jurisdiction over KPP was a substantial alteration of the
facts. An agency’s interpretation of a statute should be given
deference, but when reviewing a question of law, we may
substitute our judgment for that of the agency. See Hickey
v. Kansas Corporation Comm ’n, 244 Kan. 71, 76, 765 P.2d
1108 (1988).
We note that the KCC was aware as early as June 2,
1995, that FERC was considering asserting jurisdiction over
KPP. Since the parties were aware of FERC’s interest in
KPP for 5 months, we are unable to understand how FERC’s
order of November 2, 1995, is a substantial alteration of the
facts used as a basis for the requested approval of contracts.
The facts supporting the proposed changes remained the
same although the status of the parties may well have been
altered.
Simply put, the punctuation of the statute in light of
the legislative history precludes the KCC’s interpretation of
66-117(b).
The legislature is presumed to understand the
meaning of the words it uses and procedures it establishes.
State Bank Commissioner v. Emery, 19 Kan. App. 2d 1063,
1071, 880 P.2d 783 (1994). And when a statute is clear and
unambiguous, we must give effect to the legislature’s intent
as expressed, rather than determine what the law should or
should not be. Martindale v. Tenny, 250 Kan. 621, Syl. P
2, 829 P.2d 561 (1992).
18
Finally, we must decide whether the statutory phrase
"substantially alters the facts used as a basis for such
requested change of rate" modifies "any amendment” or
whether it applies to any change regardless of origin.
Grammatically, we have no hesitancy in _ holding
"amendment" is the controlling noun which is the subject of
the modifying phrase.
An amendment makes a change or modification.
Black’s Law Dictionary 81 (6th ed. 1990). It suggests an
action by one of the parties to change, correct, or revise.
No action was taken by KPP, WRI, or the KCC to change
or modify the application which would trigger the provisions
of 66-117(b).
Further review of the legislative history concerning
the evolution of this provision supports our conclusion that
an amendment is required.
The phrase "which amendment" contained in the
original 1980 legislation, was deleted in 1988, as part of
legislation that broadened application of the administrative
procedures act. The legislation changed all time limits from
being written out, to numerals (i.e., two hundred forty, to
240). See L. 1988, ch. 356, at 225.
When the phrase under scrutiny is read to include
"which amendment" the original intent of the legislature is
clearer. The 1988 changes were the result of S.B. 334,
which made some substantive changes to the administrative
procedures act, but overall appears to be a technical bill to
"clean up" the statutes by converting to numerals.
19
Ordinarily, a change in statutory language is
presumed to result from a legislative purpose to change its
effect. Schuhs v. Schuhs, 20 Kan. App. 2d 98, 99, 883 P.2d
1225 (1994). But this presumption is of little force if an
amendment is adopted as part of a general, technical revision
to a statute. Board of Educati .D. 512 v. Vi
Builders, Inc., 231 Kan. 731, 736, 648 P.2d 1143 (1982).
We do not view the deletion of the phrase "which
amendment" by the legislature in 1988 as a substantive
change intended to modify the meaning of 66-117(b).
Rather, the change was merely part of a larger bill seeking
to bring consistency to statutes under the administrative
procedures act.
At the time the original provisions imposing time
limits on the KCC were adopted, the House Ways and
Means Committee rejected without discussion a suggestion
that would have given the KCC more flexibility in deciding
cases under the new time limits. House Ways and Means
Committee Minutes, May 2, 1980, p. 2.
Thus, the legislature was intent on forcing the KCC
to act within prescribed time limits; if it does not, the
proposed changes take effect. In 1980, the legislature
recognized the increased burden the time limits would place
on KCC staff. Senator Frank Gaines assured members of the
House that adequate funds would be provided for the KCC
"to adequately and efficiently carry out the provisions of this
act" and further "gave his personal assurance that funds
would be provided." House Ways and Means Committee
Meeting, May 2, 1980, p. 1.
20
CURB asks us not to abandon or ignore the
"thousands" of hours of staff work and the “hundreds of
thousands of dollars" of legal and technical analysis
expended on the five contracts submitted for approval. But
legislative history makes clear that was precisely an
anticipated result should the KCC fail to make a final
decision within the time limits provided by K.S.A. 1995
Supp. 66-117(b).
The contracts and related requests contained in KPP’s
consolidated KCC dockets must be deemed approved by
operation of law.
Reversed.
21
: APPENDIX C
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS
Before Commissioners: Susan M. Seltsam, Chair
F. S. Jack Alexander
Timothy E. McKee
Docket No.
192,506-U
In the Matter of the Filing )
of Kansas Pipeline Partnership for _)
approval and to make effective )
certain firm gas purchase contracts )
)
)
)
between Kansas Pipeline
Partnership and Western Resources,
Inc.
Docket No.
192,391-U
In the Matter of the Application of )
Western Resources for an order )
approving certain contracts with )
Kansas Pipeline Partnership, and )
authorizing inclusion of costs )
related to such contract in Western )
Resources’ purchased gas adjustment )
clause for recovery from its )
customers. )
Docket No.
192,507-U
In the Matter of the Filing of Kansas )
Pipeline for approval and to make _—s+)
effective certain gas transportation )
service agreements between Kansas_ )
) ENTERED
) NOV3 1995
Pipeline Partnership and Western
Resources, Inc.
ORDER
On October 25, 1995, the Federal Energy Regulatory
Commission (FERC) decided during their administrative
meeting that KansOk Partnership (KansOk), Kansas Pipeline
Partnership (Kansas Pipeline) and Riverside Pipeline
Company, L.P. (Riverside) constituted an interstate pipeline -
subject to FERC’s jurisdiction. In response to FERC’s
action and draft order, the Kansas Corporation Commission
Staff (Staff) filed a Motion for Stay of Proceedings on
November, 1995.
Pursuant to K.S.A. 77-526(g), the Kansas
Corporation Commission (Commission) must issue an order
within 30 (thirty) days after the conclusion of the hearing or
submission of findings. In this case, parties submitted their
findings of fact and conclusions of law on October 6, 1995.
Accordingly, the Commission has through November 6,
1995, in which to issue an order or extend the period of time
in which to issue a final order for good cause shown.
The Commission notes that on November 2, 1995,
FERC issued an initial order and Kansas Pipeline et al. was
ordered to file an application for certificate authorization.
The Commission, on its own motion, has determined that a
stay of the above referenced dockets is appropriate until all
parties have had an opportunity to respond to the Motion for
Stay of Proceedings filed by Staff and until such time as the
period for rehearing before FERC has passed and final
appealable action has been taken.
IT IS, THEREFORE, BY THE COMMISSION
ORDERED:
i The above-referenced dockets are stayed
pending further order of this Commission.
2. All parties may file a response to Staff's
Motion for Stay of Proceedings on or before November 14,
1995.
A party may file a petition for reconsideration of this
order within fifteen (15) days from the date of this order. If
service is by mail, three (3) additional days may be added to
the fifteen (15) day time limit to petition for reconsideration.
The Commission retains jurisdiction over the subject
matter and the parties for the purpose of entering such
further order or orders as it may deem necessary.
BY THE COMMISSION IT IS SO ORDERED.
Seltsam, Chr.; Alexander, Com.; McKee, Com.
Dated: November 3, 1995
[ORDER MAILED ]
[NOV 3 1995 ]
{JUDITH MCCONNELL ]
[EXECUTIVE DIRECTOR |]
/s/
Judith McConnell
Executive Director
APPENDIX D
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS
Before Commissioners: ~~ Susan M. Seltsam, Chair
F. S. Jack Alexander
Timothy E. McKee
In the Matter of the Filing
of Kansas Pipeline Partnership for
approval and to make effective
certain firm gas purchase contracts
between Kansas Pipeline
Partnership and Western Resources,
Inc.
In the Matter of the Application of
Western Resources for an order
approving certain contracts with
Kansas Pipeline Partnership, and
authorizing inclusion of costs related
to such contract in Western
Resources’ purchased gas adjustment
Clause for recovery from its customers.
In the Matter of the Filing of Kansas
Pipeline for approval and to make
effective certain gas transportation
service agreements between Kansas
Pipeline Partnership and Western
Resources, Inc.
)
Docket No.
192,506-U
Docket No.
192,391-U
Docket No.
192,507-U
ENTERED
NOV 22 1995
ORDER
This matter is before the Kansas Corporation
Commission (Commission) on the Motion of Commission
Staff (Staff) for Stay of Proceedings. On November 1,
1995, Staff requested a stay of proceedings "pending a final
order in Federal Energy Regulatory Commission (FERC)
Docket Nos. RP95-212-000 and RP95-395-000." (Staff's
motion, p. 1). Staff based its request for stay on. FERC’s
ruling on October 25, 1995, and Draft Order which provides
that "the natural gas transmission systems of KansOk
Partnership, KPP and Riverside Pipeline Company, L.P.
(collectively referred to as Kansas Pipeline) constitute an
interstate natural gas pipeline system subject to FERC
jurisdiction under the Natural Gas Act." (Staff's motion,
p.2). Staff argued that the Commission, after FERC’s ruling
and issuance of a Section 7 Certificate to Kansas Pipeline,
would not have jurisdiction. Staff believes further action
would constitute "a wasteful and inefficient use of the
Commission’s resources and would be unnecessary under the
present circumstances." (Staff's motion, p.3).
On November 2, 1995, FERC issued an official order
memorializing the action taken on October 25, 1995. On
November 3, 1995, the Commission stayed the above-
captioned cases pending an opportunity for all parties to
respond to Staff's Motion for Stay of Proceedings and until
such time as the period for rehearing has passed before
FERC and final appealable action has been taken.
For purposes of Staff’s motion and the responses filed
thereto, Staff appeared by Larry Cowger; Kansas Pipeline
Partnership (Kansas Pipeline) appeared by James P.
2
a aa aia ea
AIO oa taba Steel, 22 Kure Aecnaen st are A Lael one
Zakoura and Richard W. Hird; Western Resources, Inc.
(Western Resources) appeared by J. Michael Peters;
Williams Natural Gas Company (WNG) appeared by John C.
Frieden and Kevin M. Fowler; and the Cities of Ottawa and
Paola, Kansas, appeared by Robert L. Bezek, Jr.
Kansas Pipeline argues the process outlined by FERC
in its November 2, 1995 Order -- "an application for
certificate, approval of terms and conditions of service,
approval of rates, and transitioning existing operations to be
in compliance with FERC Order No. 636 -- could extend
well over a year, and perhaps more." (Kansas Pipeline’s
response, p.3). Kansas Pipeline is seeking a stay of FERC’s
November 2, 1995 Order and also intends to seek rehearing
of that Order.
Kansas Pipeline argues the Commission is without
power to stay this action. Specifically, Kansas Pipeline
references the Commission’s April 21, 1995 Orders in
Docket Nos. 192,506-U and 192,507-U which granted a
180-day suspension period from the date the applications
were filed on March 31, 1995. Kansas Pipeline argues the
suspension period expired on September 27, 1995. Since
there were no further suspensions issued, Kansas Pipeline
contends the contracts in Docket Nos. 192,506-U and
192,507-U became effective on September 27, 1995.
(Kansas Pipeline’s response p. 5).
Moreover, Kansas Pipeline contends even if FERC
arguably assumed jurisdiction on November 2, 1995, the
suspension period expired prior to FERC’s order. In the
alternative, Kansas Pipeline argues that the Commission nust
issue an order within 240 days, no later than November 29,
1995, or the contracts are deemed approved. K.S.A. 66-
117. (Kansas Pipeline’s response, p.6)
Kansas Pipeline believes Staff’s request for a stay is
"unusual, extraordinary and inappropriate." (Kansas
Pipeline’s response, p.6). Only WNG, according to Kansas
Pipeline, will benefit from a stay and "the contracts may
become null and void simply by the passage of time...."
(Kansas Pipeline’s response, p.7).
Kansas Pipeline maintains the Commission continues
to have jurisdiction. If the Commission were not to regulate
Kansas Pipeline, prior to the issuance of a FERC certificate,
Kansas Pipeline would be in "jurisdictional limbo." (Kansas
Pipeline’s response, p.8). Further, Kansas Pipeline intends
to pursue all available avenues of appeal regarding FERC’s
November 2, 1995 Order. Staff's motion, according to
Kansas Pipeline, would place it in "regulatory limbo for an
indeterminate amount of time” and would constitute an
unconstitutional taking without compensation if it could not
charge "fair, just and reasonable rates." (Kansas Pipeline’s
response, p.10). Kansas Pipeline believes a Commission
decision would be beneficial to the FERC and approval of
the applications would benefit consumers. (Response, pp.10-
12).
eee ee a
Western Resources’ response calls attention to the
"commercial transactions for which time is important."
(Western Resources’ response, p.3). Western Resources also
believes the Commission "must reconcile its intended stay of
these proceedings in light of its April 20, 1995 Suspension
Order....". (Western Resources’ response, p.3). And
finally, Western Resources requests the Commission to rule
"expeditiously." (Western Resources’ response, p.3).
4
,
WNG seeks reconsideration of the Commission’s June
22, 1995 Order [denial of WNG’s motion for denial of stay]
and July 26, 1995 Order [denial of WNG’s motion to
dismiss for lack of subject matter jurisdiction] based on the
"materially changed circumstances" and requests that all
pending applications be dismissed without prejudice until
such time as FERC determines it "does not have jurisdiction
over Kansas Pipeline Partnership under the Natural Gas
Act." (WNG’s response, p.2) WNG concurs with Staff’s
basis for a stay, but believes dismissal of the pending
applications on jurisdictional grounds to be more
appropriate. (WNG’s response, p.2)
WNG has argued that these proceedings are subject
to K.S.A. 66-117 and K.A.R. 82-1-231 but contends "it is
unclear whether the 240-day period prescribed in K.S.A. 66-
117(b) is applicable." WNG believes the Commission’s stay
granted on November 3, 1995, "to determine whether the
Commission has any continuing jurisdiction over the
contracts and/or whether the decision by FERC is effectively
an amendment or modification to the applications filed by
joint applicants is likely a sufficient adjudication or otherwise
fulfills the requirements under K.S.A. 66-117." (WNG’s
response, pp.3-4). Arguably, the contracts may be "deemed
approved” pursuant to K.S.A. 66-117(b), notwithstanding the
stay. WNG previously sought a stay from the Commission,
pending final outcome at FERC, and also sought dismissal
of these proceedings for lack of subject matter jurisdiction.
WNG believes FERC’s action on October 25, 1995,
constitutes a material change in circumstances to warrant
reconsideration of WNG’s previous motion to dismiss.
Dismissing the action without prejudice would avoid
any "possibility that the proposed contracts may be deemed
5
approved’ without Commission action after November 26,
1995." (WNG’s response, p.5). While WNG "endorses...
Staff's rationale for a stay" WNG seeks dismissal of the
contracts for lack of subject matter jurisdiction. (WNG’s
response, p.5)
The Cities of Ottawa and Paola, Kansas (Ottawa and
Paola) believe "no valid reason exists for the Commission to
avoid deciding the above, to deny the approval of the five
gas and transportation contracts filed by Kansas Pipeline and
deny the pass-through of costs, resulting from the contracts
to Western Resources." (Ottawa and Paola’s response, pp. 1-
2). Ottawa and Paola stated that the two main issues,
whether to approve the five gas contracts and whether to
approve the pass-through, are briefed and ready for decision.
In the event FERC removes jurisdiction from the
Commission, Ottawa and Paola contend the Commission
would still have jurisdiction to consider the pass-through
issue. (Ottawa and Paola’s response, p. 2). Ottawa and
Paola believe "[t]he ability to acquire right of way, utility
easements and the utility franchise itself is clouded by the
lack of a decision regarding the gas and transportation
contracts." Moreover, "regarding the approval and pass-
through of these contract costs, there will always be a
question as to whether the franchise can be condemned with
or without the gas contracts." (Ottawa and Paola’s response,
pp. 2-3). Ottawa and Paola believe they will suffer harm if
no decision is made. (Ottawa and Paola’s response, p. 3).
In the event the Commission believes the FERC
decision has the impact of removing jurisdiction, Ottawa and
Paola recommend the Commission dismiss this proceeding
without prejudice prior to the expiration of 240 days to avoid
approval of these contracts and impose certain conditions.
6
Those conditions would include the requirement that the
refiled action be submitted on the record that exists and that
a decision be rendered within a specified period of time, i.e.,
60 (sixty) days. (Ottawa and Paola’s response, pp. 3-4).
And finally, if Kansas Pipeline and Western Resources make
any modifications to these contracts, then the prior contracts
should be deemed denied and the new contracts resubmitted
with notice to all parties and "without requiring agreement
to confidentiality contracts." (Ottawa and Paola’s response,
p. 4).
Staff filed a reply to the responses to Staff’s motion
for stay. Staff set forth a brief procedural history of these
consolidated dockets. On April 20, 1995, the Commission
suspended for 180 days from the date of the applications,
approval of these agreements “subject to further order or
orders of the Commission." (Docket Nos. 192,506-U and
192,507-U). On April 27, 1995, the commission
consolidated the above three dockets upon Western
Resource’s motion. The Commission set a procedural
schedule by order dated May 10, 1995. Two subsequent
orders modified the procedural schedule and ultimately an
evidentiary hearing commenced on August 21, 1995.
(Staff's reply, pp. 2-3). The evidentiary hearing ended
September 6, 1995, and parties were ordered to file briefs
and/or findings of fact and conclusions of law on or before
October 6, 1995. Staff interprets these orders as superseding
the prior suspension orders. While staff believes "the
Commission’s orders modifying the procedural order
obviously extended the proceedings past the originally
scheduled 180 days, it would have apparently been helpful
to some parties had the Commission explicitly spelled out in
an order the fact that by extending its procedural orders past
September 27, 1995, the original suspension order had been
7
modified." (Staff's reply, p. 3). Accordingly, Staff now
requests the Commission to make this explicit finding at this
time.
Staff contends the only arguable "operation of law"
date to apply to these applications is contained in K.S.A. 66-
117(b). The statute first "provides that if a utility files ’a
schedule showing the changes to be made,’ such proposed
schedule shall be deemed approved if not suspended by the
Commission within thirty (30) days of its filing." (Staff's
reply, pp. 3-4). Moreover, the statute requires that the
effective date of the changes proposed may not be delayed
beyond 240 days from the date of filing. Staff references
other statutory authority:
[T]he specific statute requiring the filing of
contracts by natural gas utilities, K.S.A. 66-
1,203, makes no mention of the 240-day
requirement, nor does the statute authorizing
a hearing on gas rates, K.S.A. 66-1,204."
(Staff's reply, p. 4). In fact, case law
discussing the Commission’s duty to
investigate the reasonableness of contracts
filed by a public utility have indicated that
such duty flows from general grant of power
and authority contained in K.S.A. 66-101
(c.f. K.S.A. 66-1,201) which likewise does
not reference any 240-day requirement.
Central Kansas Power Co. v. State Covp.
Commission, 316 P.2d 277, 181 Kan. 817
(1957).
(Staff’s reply, p. 4). Staff stated that the expiration of the
240-day requirement, for argument purposes, would require
a decision on the contracts by November 27, 1995.
Staff highlights an exception to the 240-day rule and
argues its applicability here. K.S.A. 66-117(b)(1) provides:
(1) for purposes of the foregoing provisions
regarding the period of time within which the
commission shall act on an application, any
amendment to an application for a proposed
change in any rate, which increases the
amount sought by the public utility or
common carrier or substantially alters the
facts used as a basis for such requested
change of rate, shall, at the option of the
commission, be deemed a new application and
the 240-day period shall begin again from the
date of the filing of the amendment.
(Staff's reply, pp. 4-5 citing K.S.A. 66-117(b)(1)). Staff
believes the Commission should exercise its discretion under
this provision. Staff concurs with WNG’s interpretation that
the "Commission order to stay these proceedings to
determine whether it has any continuing jurisdiction over the
contracts and/or whether the decision by the Federal Energy
Regulatory Commission (FERC) is effectively an amendment
or modification to the application ~— by joint applicants, ,
ikel ient_adjudicati therwi Ils
requisements under K.S.A. 66-117. " (Staff's reply, p. 5).
Staff also interprets FERC’s decision which subjects Kansas
Pipeline’s pipe gas transmission systems to federal
jurisdiction "is a matter which ’substantially alters the facts
used as a basis for such requested change... .” K.S.A. 66-
9
117(b)" would enable the Commission to exercise its
discretion to restart the 240-day period. (Staff's reply, p. 5).
There appears to be a consensus among the parties,
according to Staff, that the Commission has jurisdiction until
FERC grants Kansas Pipeline the Section 7 Natural Gas Act
authority. Even though the Commission continues to have
jurisdiction for at least a short period of time "does not mean
. . the Commission should exercise that authority and
approve expansion of the KPP interstate system through the
proposed construction projects envisioned in the current
applications." (Staff's reply, pp. 5-6). Staff believes
approving additional sales volumes from Kansas Pipeline to
Western Resources would be "unwise" since FERC Order
636 would require Kansas Pipeline "to cease its merchant
function." (Staff's reply, p. 6).
Staff has outlined three options available to the
Commission at this time:
First, dissolve the stay
and determine this matter on
the merits, issuing an order no
later than November 27, 1995,
(in which case Staff would
refer the Commission to its
Post-Hearing Brief and urge
that the applications be denied
for lack of merit).;
Second, issue an order
restarting the 240-day period
due to the November 2, 1995
FERC Order finding KPP
10
(Kansas Pipeline) to be subject
to federal NGA jurisdiction
and maintain its stay of these
proceedings until FERC
resolves any petition for
rehearing filed by KPP; or
Finally, to dissolve the
stay and to reconsider its
Orders of June 22, 1995, and
June 26, 1995, in light of the
materially changed
circumstances, and dismiss all
pending applications without
prejudice to further
consideration of the merits in
the unlikely event FERC
reverses its Order and
determines that it does not
have jurisdiction over KPP
pursuant to the NGA. Such an
order would also have to be
issued no later than November -
27, 1995.
(Staff's reply, p. 6). Staff recommends, out of the options
presented, that the Commission reaffirm its order staying this
action pending a final order from FERC on reconsideration
and that the Commission restart the 240-day period based on
the fact that FERC’s order substantially altered the basis for
the requested change. Staff believes the legislature
contemplated relief from the 240-day period for
circumstances such as these and neither Kansas Pipeline nor
11
Western Resources should use this provision to pressure the
Commission into a decision. (Staff’s reply, p.8).
Kansas Pipeline takes issue with Staff's suggestion
that the 180-day suspension orders were extended by
"implication." Kansas Pipeline argues that "[p]rior to
September 27, 1995, the Commission could arguably have
entered an order extending the suspension period up to the
full 240 days; however, neither Staff, nor any other party,
requested such an extension and the Commission did not do
sO On its Own motion or of its own accord." (Kansas
Pipeline’s reply, pp.3-4). Kansas Pipeline does not believe
the deadline for submission of briefs after the expiration of
the 180-day suspension order to constitute a written
statement pursuant to K.S.A. 66-117. Kansas Pipeline also
does not believe an “order by implication" satisfies the
requirement that orders must be in writing. K.A.R. 2-1-232.
(Kansas Pipeline’s reply, p.5). Kansas Pipeline did not
suggest that the Commission lost jurisdiction after expiration
of the suspension orders. Kansas Pipeline also disputes
Staff's reference to K.S.A. 66-1,203 and 66-1,204 for the
proposition that the 240-day period is inapplicable. Kansas
Pipeline believes only K.S.A. 66-117(b) governs time
limitations in Docket Nos. 192,506-U and 192,507-U.
(Kansas Pipeline’s reply, p.6)
Kansas Pipeline disagrees with Staff’s
recommendation that FERC’s November 2, 1995 Order
altered the facts used as the basis for the change in rates.
Kansas Pipeline does not believe the Commission’s order
staying this proceeding constitutes an adjudication on the
merits or sufficient grounds to restart the 240-day time
period. Kansas Pipeline believes the three options presented
12
by staff are erroneous and ignore the statutory deadlines.
(Kansas Pipeline’s reply, pp.8-9).
WNG has filed a reply to Kansas Pipeline’s response
to Staff's Motion for Stay. WNG suggests the following
alternatives for Commission action:
(i) entering an order of dismissal for lack
of subject matter jurisdiction (without
prejudice to further consideration on
the merits in the event of a final
determination that FERC lacks
jurisdiction over its operations) no
later than November 27, 1995;
(ii) | dismissing KPP’s applications unless
each is amended on or before
November 27, 1995, to address the
materially changed factual
circumstances presented by FERC’s
November 2, 1995 Order; or
(iii) denying KPP’s applications on the
merits for the factual and legal reasons
set forth in the post-hearing
submissions of the Staff and the
Intervenors.
(WNG’s reply, p.2)
WNG recognizes the Commission’s problem as to
whether it has jurisdiction after FERC’s November 2, 1995
Order in Docket Nos. RP95-212-000 and RP95-395-000.
WNG is concerned that Commission inaction would result in
13
the "unpalatable possibility that the proposed contracts may
become effective by operation of law after November 27,
1995.". (WNG’s reply, p.2)
WNG also outlines the procedural history of these
dockets. WNG references the fact that Kansas Pipeline
never argued the contracts were effective by operation of law
on September 27, 1995, when the hearing was extended to
accommodate Dr. Stalon’s testimony, one of Kansas
Pipeline’s witnesses. (WNG’s reply, p.7). Nor did Kansas
Pipeline, according to WNG, make this representation when
the Commission announced the briefing schedule on
September 6, 1995.
WNG believes that "[i]f the time limits of K.S.A. 66-
117(b) are applicable to these proceedings, this statute
further provides that ’any amendment to an application for
a proposed change’ which ’substantially alters the facts used
as a basis for such requested change’ may, in the
Commission’s discretion, *be deemed a new application and
the 240-day period shall begin again from the date of the
filing of the amendment.’" (WNG’s reply, p.8). Although
Kansas Pipeline has not filed an amendment, WNG interprets
the FERC’s November 2, 1995 Order as changing the
"factual bases for these applications." (WNG’s reply, p.8).
For instance, WNG referenced the fact that the proposed
contracts bundle both sales and transportation while as
interstate pipeline, those services would need to be
unbundled. (WNG’s reply, p.8).
WNG contends Kansas Pipeline’s position before the
Kansas Corporation Commission, maintaining that the
Commission has ongoing jurisdiction, is inconsistent with its
position before FERC. Kansas Pipeline has sought a stay
14
from FERC’s November 2, 1995 Order on the grounds that
FERC is depriving the Commission of its "regulatory
jurisdiction." (WNG’s reply, pp.8-9)
WNG also cites page 18 of FERC’s November 2,
1995 Order "which sought . . . to prohibit KPP from
‘constructing new pipelines or any expansions or extensions
of existing pipelines without [Federal Energy Regulatory]
Commission approval to the extent such construction requires
Commission approval. See FERC Docket No. RP95-395-
000 (Complaint of Williams Natural Gas Company, dated
July 21, 1995, p. 63 at { (e)).". (WNG’s reply, p.10).
Moreover, before any construction for facilities or extension
are put in force, the interstate pipeline must have a FERC
certificate. (WNG’s reply, p.10). WNG cites authority
which support the proposition that a state utilities
Commission cannot exercise concurrent jurisdiction with
FERC. 15 USC § 717f(c)(1)(A); Cascade Natural Gas
Corp. v. F.E.R..C., 955 F.2d 1412 (10th Cir. 1992):
National Fuel Gas Supply Corp. v. Public Service Comm’n
of State of New York, 894 F.2d 571 (2d Cir. 1990).
WNG suggests that Kansas Pipeline could seek an
interim certificate from FERC to avoid any detrimental
impact on its proposals. (WNG’s reply, p.11). Moreover,
WNG states that "none of the proposed contracts involve
sales or transportation of natural gas during the 1995-96
winter heating season." In summary, WNG seeks dismissal
"of the pending applications for lack of subject matter
jurisdiction (without prejudice to further consideration on the
merits in the event of a final determination that FERC lacks
jurisdiction over its operations) no later than November 27,
1995, or to immediately dismiss KPP’s pending applications
unless it amends each no later than November 27, 1995, to
15
address the materially changed factual circumstances
presented by FERC’s November 2, 1995 Order and, in such
event, to restart the 240-day period for a final order hearing
if deemed necessary." (WNG’s reply, p. 12). In the
alternative, WNG seeks to have the Commission deny
Kansas Pipeline’s applications or "issue an _ order
disapproving any mew services and related pipeline
construction on or before November 27, 1995." (WNG’s
reply, p. 12).
Findings and Conclusions
The Commission does not give any credence to the
argument raised by Kansas Pipeline that the subject contracts
(Docket Nos. 192,506-U and 192,507-U) became effective
by operation of law on September 27, 1995, the expiration
of the 180-day suspension orders. The suspension orders
entered April 20, 1995, clearly provided they were subject
to any further order(s) of the Commission. Subsequent
procedural orders setting this matter for hearing superseded
the earlier suspension orders and the Commission so finds.
Moreover, on September 6, 1995, the Commission
specifically directed the parties to file briefs and/or findings
of fact and conclusions of law by October 6, 1995. No
objection was raised by Kansas Pipeline or any other party
to the October 6, 1995 date for purposes of closing the
record. Had the parties felt the contracts became effective
September 27, 1995, there would have been no need for
briefs, etc. The Commission deems Kansas Pipeline’s
failure to timely object to the Commission’s September 6,
1995 bench ruling as a waiver of their objection.
The Commission concurs with WNG’s contention that
the Commission’s Order of November 3, 1995, is probably
16
| Se oe
SDS RT es © 6TR a TRE EE Re RS ee ee, MN SN RI Os ee!
a sufficient adjudication within the 240-day period of time.
The Commission’s Order granting the stay was based on
FERC’s official Order of November 2, 1995, which
memorialized FERC’s decision from its October 25, 1995
agenda.
The Commission adopts Staff’s recommendation and,
to the extent (if any) K.S.A. 66-117(b) applies, shall restart
the 240-day clock. K.S.A. 66-117(b) specifically grants the
Commission discretion to restart the 240-day time period
when a substantial alteration of the facts occurs which
formed the basis for Kansas Pipeline’s requested change,
i.e., FERC’s finding that Kansas Pipeline is an interstate
pipeline subject to the NGA. The Commission shall restart
the 240-day clock as of November 2, 1995, the date of
FERC’s order finding Kansas Pipeline to be an interstate
pipeline.
The Commission recognizes the concerns raised by
Ottawa and Paola as to the need to have a decision in order
to determine outstanding franchise and easement questions.
However, the Commission believes that a continued stay at
this juncture serves the public interest especially in light of
the unbundling concerns raised by Staff should FERC
ultimately find it has jurisdiction over Kansas Pipeline. The
Commission believes the benefits to a short stay pending
FERC’s issuance of a final appealable order outweighs any
potential harm caused by the delay. The Commission shall
continue to exercise jurisdiction over Kansas Pipeline until
such time as FERC grants Kansas Pipeline certificates or
otherwise resolves the pending dockets (Docket Nos. RP95-
212-000 and RP95-395-000). The Commission does not,
however, believe this requires the Commission to decide
whether to approve contracts, which may not be appropriate
17
under FERC Order 636, as a prudent exercise of the
Commission’s discretion at this time.
IT IS, THEREFORE, BY THE COMMISSION
ORDERED THAT:
1. The Commission’s procedural orders setting
these consolidated dockets for hearing superseded any prior
suspension orders.
a The Commission affirms its November 3,
1995 Order and stays consideration of these dockets until
FERC has taken final appealable action.
3. The Commission shall restart the 240-day time
period (to the extent, if any, that it applies) as of November
2, 1995.
A party may file a petition for reconsideration of this
order within fifteen (15) days from the date of this order. If
service is by mail, three (3) additional days may be added to
the fifteen (15) day time limit to petition for reconsideration.
The Commission retains jurisdiction over the subject
matter and the parties for the purpose of entering such
further order or orders as it may deem necessary.
BY THE COMMISSION IT IS SO ORDERED.
Seltsam, Chr.; Alexander, Com.; McKee, Com.
Dated: November 22, 1995.
18
[ORDER MAILED ]
[NOV 22 1995 ]
[JUDITH MCCONNELL }
[EXECUTIVE DIRECTOR ]
/s/
Judith McConnell
Executive Director
19
APPENDIX E
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS
Before Commissioners: Susan M. Seltsam, Chair
F. S. Jack Alexander
Timothy E. McKee
Docket No.
192,506-U
In the Matter cf the Filing
of Kansas Pipeline Partnership for
approval and to make effective
Certain firm gas purchase contracts
between Kansas Pipeline
Partnership and Western Resources,
Inc.
Nee eee eee we
In the Matter of the Application of ) Docket No.
Western Resources for an order ) 192,391-U
approving certain contracts with )
Kansas Pipeline Partnership, and )
authorizing inclusion of costs related )
to such contract in Western )
Resources’ purchased gas adjustment )
Clause for recover from its customers. )
In the Matter of the Filing of Kansas ) Docket No.
Pipeline for approval and to make ) 192,507-U
effective certain gas transportation )
service agreements between Kansas_ )
Pipeline Partnership and Western ) ENTERED
Resources, Inc. ) DEC 8 1995
ORDER
This matter is before the State Corporation
Commission of the State of Kansas (Commission) on Kansas
Pipeline Partnership’s (KPP’s) Petition for Reconsideration
or, in the Alternative, Petition for Hearing. KPP appeared
by James P. Zakoura, Richard W. Hird and Fred J.
Logan, Jr. KPP seeks reconsideration of the Commission’s
November 3, 1995 Order which preliminarily stayed the
above-captioned actions due to FERC’s Order issued on
November 2, 1995, and in order to give parties an
opportunity to respond to Staff’s Motion for Stay. After the
parties were given an opportunity to file responses to Staff’s
Motion for Stay, the Commission issued a subsequent order
on November 22, 1995, which supersedes the Commission’s
November 3 Order.
Accordingly, KPP’s petition for reconsideration and
request for a hearing on the November 3, 1995 Order is
denied since the November 22, 1995 Order supersedes the
November 3, 1995 Order and continues the stay of these
proceedings.
IT IS, THEREFORE, BY THE COMMISSION
ORDERED THAT:
Kansas Pipeline Partnership’s Petition for
Reconsideration or, in the Alternative, Petition for Hearing
is denied.
Kansas Pipeline Partnership has exhausted its
administrative remedies as to the November 3, 1995 Order.
The Commission retains jurisdiction over the subject
matter and the parties for the purpose of entering such
further order or orders as it may deem necessary.
BY THE COMMISSION IT IS SO ORDERED.
Seltsam, Chr.; Alexander, Com.;: McKee, Com.
Dated: December 8, 1995
[ORDER MAILED ]
[DEC 8 1995 ]
[JUDITH MCCONNELL ]
[EXECUTIVE DIRECTOR ]
_/s/
Judith McConnell
Executive Director
APPENDIX F
Da Pe
7 fai ds)
~
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS
Before Commissioners: Susan M. Seltsam, Chair
F. S. Jack Alexander
Timothy E. McKee ;
In the Matter of the Filing )
of Kansas Pipeline Partnership for _)
approval and to make effective )
certain firm gas purchase contracts)
between Kansas Pipeline )
Partnership and Western Resources, )
Inc. )
In the Matter of the Application of _)
Western Resources for an order )
approving certain contracts with )
Kansas Pipeline Partnership, and )
authorizing inclusion of costs related )
to such contract in Western )
Resources’ purchased gas adjustment )
clause for recover from its customers.)
In the Matter of the Filing of Kansas )
Pipeline for approval and to make
effective certain gas transportation
service agreements between Kansas
Pipeline Partnership and Western
Resources, Inc.
Nee ee Ne
ORDER
Docket No.
192,506-U
Docket No.
192,391-U
Docket No.
192,507-U
ENTERED
DEC 28 1995
This matter is before the Kansas Corporation
Commission (KCC) on Kansas Pipeline Partnership’s (KPP)
"Petition for Reconsideration of November 22, 1995 Order."
KPP appeared by James P. Zakoura, Richard W. Hird and
Fred J. Logan, Jr. The KCC notes that it has filed a petition
for rehearing before the Federal Energy Regulatory
Commission (FERC) in Docket Nos. RP95-212-000 and
RP95-395-000 which is still pending. The resolution of
these FERC dockets will determine the jurisdictional issues
regarding KPP. The KCC recognizes that Western
Resources, Inc., one of the Joint Applicants, will remain
Kansas jurisdictional notwithstanding FERC’s ruling.
Western Resources, Inc. has not sought reconsideration of
the November 22, 1995 Order or responded to KPP’s
petition for reconsideration. Accordingly, the Commission
finds no reason to alter its prior decision at this time. The
Order of November 22, 1995 is affirmed for the reasons
stated in that Order and the stay of the above-captioned
dockets will remain in place subject to further order or
orders of the KCC.
IT IS, THEREFORE, BY THE COMMISSION
ORDERED THAT: KPP’s "Petitior: for Reconsideration of
November 22, 1995 Order" is deniec!. KPP has exhausted
its administrative remedies as to the November 22, 1995
Order.
The KCC retains jurisdiction over the subject matter
and the parties for the purpose of entering such further order
or orders as it may deem necessary.
eT
BY THE COMMISSION IT IS SO ORDERED.
Seltsam, Chr.; Alexander, Com.; McKee, Com.
Dated: December 28, 1995
[ORDER MAILED
[DEC 28 1995
[JUDITH MCCONNELL
[EXECUTIVE DIRECTOR
feed heeeend feemosd teswmed
/s/
Judith McConnell
Executive Director
APPENDIX G
AMENDMENT XIV - CITIZENSHIP; PRIVILEGES
AND IMMUNITIES; DUE PROCESS; EQUAL
PROTECTION; APPORTIONMENT OF
REPRESENTATION; DISQUALIFICATION OF
OFFICERS; PUBLIC DEBT; ENFORCEMENT
Section 1. Ali persons born or naturalized in the
United States, and subject to the jurisdiction thereof, are
citizens of the United States and of the State wherein they
reside. No state shall make or enforce any law which shall
abridge the privileges or immunities of citizens of the United
States; nor shall any state deprive any person of life, liberty,
or property, without due process of law: nor deny to any
person within its jurisdiction the equal protection of the laws.
Section 2. Representatives shall be apportioned
among the several states according to their respective
numbers, counting the whole number of persons in each
state, excluding Indians not taxed. But when the right to vote
at any election for the choice of electors for President and
Vice President of the United States, Representatives in
Congress, the executive and judicial officers of a state, or
the members of the legislature thereof, is denied to any of
the male inhabitants of such state, being twenty-one years of
age, and citizens of the United States, or in any way
abridged, except for participation in rebellion, or other
crime, the basis of representation therein shal] be reduced in
the proportion which the number of such male Citizens shall
bear to the whole number of male citizens twenty-one years
of age in such state.
Section 3. No person shall be a Senator or
Representative in Congress, or elector of President and Vice
President, or hold any office, civil or military, under the
United States, or under any state, who, having previously
taken an oath, as a member of Congress, or as an officer of
the United States, or as a member of any state legislature, or
as an executive or judicial officer of any state, to support the
Constitution of the United States, shall have engaged in
insurrection or rebellion against the same, or given aid or
comfort to the enemies thereof. But Congress may by a vote
of two-thirds of each House, remove such disability.
Section 4. The validity of the public debt of the
United States, authorized by law, including debts incurred
for payment of pensions and bounties for services in
suppressing insurrection or rebellion, shall not be
questioned. But neither the United States nor any state shall
assume or pay any debt or obligation incurred in aid of
insurrection or rebellion against the United States, or any
claim for the loss or emancipation of any slave; but all such
debts, obligations and claims shall be held illegal and void.
Section 5. The Congress shall have power to enforce,
by appropriate legislation, the provisions of this article.
APPENDIX H
66-117. Change of rates or schedules; procedure;
effective date; higher rates of return in certain cases;
hearing; property tax surcharge authorized. (a) Unless
the state corporation commission otherwise orders, no
common carrier or public utility over which the commission
has control shall make effective any changed rate, joint rate,
toll, charge or classification or schedule of charges, or any
rule or regulation or practice pertaining to the service or
rates of such public utility or common carrier except by
filing the same with the commission at least 30 days prior to
the proposed effective date. The commission, for good
cause, may allow such changed rate, joint rate, toll, charge,
charge or classification or schedule of charges, or rule or
regulation or practice pertaining to the service or rates of
any such public utility or common carrier to become
effective on less than 30 days’ notice. If the commission
allows a change to become effective on less than 30 days’
notice, the effective date of the allowed change shall be the
date established in the commission order approving such
change, or the date of the order if no effective date is
otherwise established. Any such proposed change shall be
shown by filing with the state corporation commission a
scheduic showing the changes, and such changes shall be
plainly indicated by proper reference marks in amendments
or supplements to existing tariffs, schedules or
Classifications, or in new issues thereof.
(b) Whenever any common carrier or public
utility governed by the provisions of this act files with the
State corporation commission a schedule showing the changes
desired to be made and put in force by such public utility or
common carrier, the commission either upon complaint or
upon its own motion, may give notice and hold a hearing
upon such proposed changes, Pending such hearing, the
commission may suspend the operation of such schedule and
defer the effective date of such change in rate, joint rate,
toll, charge or classification or schedule of charges, or any
rule or regulation or practice pertaining to the service or
rates of any such public utility or common carrier by
delivering to such public utility or common carrier a
statement in writing of its reasons for such suspension. The
commission shall not delay the effective date of the proposed
change in rate, joint rate, toll, charge or classification or
schedule of charges, or in any rule or regulation or practice
pertaining to the service or rates of any such public utility or
common carrier, more than 240 days beyond the date the
public utility or common carrier filed its application
requesting the proposed change. If the commission does not
suspend the proposed schedule within 30 days of the date the
same is filed by the public utility or common carrier, such
proposed schedule shall be deemed approved by the —
commission and shall take effect on the proposed effective
date. If the commission has not issued a final order on the
proposed change in any rate, joint rate, toll, charge or
classification or schedule of charges, or any rule or
regulation or practice pertaining to the service or rates of
any such public utility or common carrier, within 240 days
after the carrier or utility files its application requesting the
proposed change, then the schedule shall be deemed
approved by the commission and the proposed change shall
be effective immediately, except that (1) for purposes of the
foregoing provisions regarding the period of time within
which the commission shall act om an application, any
amendment to an application for a proposed change in any
rate, which increases the amount sought by the public utility
or common carrier or substantially alters the facts used as a
basis for such requested change of rate, shall, at the option
of the commission, be deemed a new application and the
240-day period shall begin again from the date of the filing
of the amendment, and (2) if hearings are in process before
2
the commission on a proposed change requested by the
public utility or common carrier on the last day of such 240-
day period, such period shall be extended to the end of such
hearings plus 20 days to allow the commission to prepare
and issue its final order.
(c) Except as provided in subsection (b), no
change shall be made in any rate, toll, charge, classification
or schedule of charges or joint rates, or in any rule or
regulation or practice pertaining to the service or rates of
any such public utility or common carrier, without the
consent of the commission. Within 30 days after such
changes have been authorized by the state corporation
commission or become effective as provided in subsection
(b), copies of all tariffs, schedules and Classifications, and all
rules and regulations, except those determined to be
confidential under rules and regulations adopted by the
commission, shall be filed in every station, office or depot
of every such public utility and every common carrier in this
state, for public inspection.
(d) Upon a showing by a public utility before the
state corporation commission at a public hearing and a
finding by the commission that such utility has invested in
projects or systems that can be reasonably expected (1) to
produce energy from a renewable resource other than nuclear
for the use of its customers, (2) to cause the conservation of
energy used by its customers, or (3) to bring about the more
efficient use of energy by its customers, the commission may
allow a return on such investment equal to an increment of
from 1/2% to 2% plus an amount equal to the rate of return
fixed for the utility’s other investment in property found by
the commission to be used or required to be used in its
services to the public. The commission may also allow such
3
higher rate of return on investments by a public utility in
experimental projects, such as load management devices,
which it determines after public hearing to be reasonable
designed to cause more efficient utilization of energy and in
energy conservation programs or measures which it
determines after public hearing provides a reduction in
energy usage by its customers in a cost-effective manner. _
(e) Whenever, after the effective date of this act,
an electric public utility, a natural gas public utility or a
combination thereof, files tariffs reflecting a surcharge on
the utility’s bills for utility service designed to collect the
annual increase in expense charged on its books and records
for ad valorem taxes, such utility shall report annually to the
state corporation commission the changes in expense charged
ad valorem taxes. For purposes of this section, such
amounts charged to expense on the books and records of the
utility may be estimated once the total property tax payment
is known. If found necessary by the commission or the
utility, the utility shall file tariffs which reflect the change
as a revision to the surcharge. Upon a showing that the
surcharge is applied to bills in a reasonable manner and is
calculated to substantially collect the increase in ad valorem
tax expense charged on the books and records of the utility,
or reduce any existing surcharge based upon a decrease in ad
valorem tax expense incurred on the books and records of
the utility, the commission shall approve such tariffs within
30 days of the filing. Any over or under collection of the
actual ad valorem tax increase charged to expense on the
books of the utility shall be either credited or collected
through the surcharge in subsequent periods. The
establishment of a surcharge under this section shall not be
deemed to be a rate increase for purposes of this act. The
net effect of any surcharges established under this section
4
shall be included by the commission in the establishment of
base rates in any subsequent rate case filed by the utility.
(f) Except as to the time limits prescribed in
subsection (b), proceedings under this section shall be
conducted in accordance with the provisions of the Kansas
administrative procedure act.
APPENDIX I
66-1223. Consumer counsel, powers. The consumer
counsel may do the following:
(a) Represent residential and small commercial
ratepayers before the state corporation commission;
(b) function as an official intervenor in cases filed
with the state corporation commission, including rate increase
requests;
(c) initiate actions before the State corporation
commission;
(d) represent residential and commercial ratepayers
who file formal utility complaints with the state corporation
commission;
(€) intervene in formal complaint cases which
would affect ratepayers; and
(f) make application for a rehearing or seek judicial
review of any order or decision of the State corporation
commission.
APPENDIX J
No. 96-75918-A
IN THE SUPREME COURT
OF THE STATE OF KANSAS
KANSAS PIPELINE PARTNERSHIP
Petitioner,
v.
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS, -
Respondent.
CITIZENS’ UTILITY RATEPAYER BOARD’S
PETITION TO SUPREME COURT FOR REVIEW OF
COURT OF APPEALS’ DECISION
Mark A. Burghart, No. 10251
ALDERSON, ALDERSON &
MONTGOMERY, L.L.C.
2101 S.W. 21st Street
Topeka, Kansas 66604-3174
(913) 232-0753
Attorney for Intervenor
Citizens’ Utility Ratepayer Board
I, PRAYER FOR REVIEW
COMES NOW the Intervenor, Citizens’ Utility
Ratepayer Board ( "CURB"), and requests the Supreme Court
to review the Court of Appeals’ decision in this matter.
CURB is aggrieved by the decision which deprives ratepayers
of the State of Kansas the Opportunity for a hearing on the
merits to determine the Propriety of five gas purchase and
transportation contracts entered into between Kansas Pipeline
Partnership ("KPP") and Western Resources, Inc. ("WRI").
As hereinafter noted, the decision of the Court of Appeais
extinguishes ratepayers’ fundamental due process rights to a
hearing on the merits of the subject agreements. The Court’s
ruling that the contracts are deemed approved by operation of
law without consideration of the merits of the contracts is
contrary to fundamental Fourteenth Amendment due process
principles. CURB respectfully requests that the Supreme
Court review the decision of the Court of Appeals, reverse
that decision, and remand the cause to the State Corporation
Commission ( "Commission") for appropriate action.
Il. DATE OF THE DECISION OF THE
COURT OF APPEALS
The date of the Court of Appeals’ decision is May 17,
1996. A complete copy of the Court of Appeals’ decision is
appended hereto as Appendix A.
Itl. STATEMENT OF THE ISSUE IN THE APPEAL
UPON WHICH REVIEW IS SOUGHT
WAS THE CITIZENS’ UTILITY RATEPAYER
BOARD AND THE RATEPAYERS WHOM THE
BOARD REPRESENTS DEPRIVED OF THEIR
DUE PROCESS RIGHTS TO A HEARING AFTER
THE COURT OF APPEALS RULED THAT THE
GAS PURCHASE AND TRANSPORTATION
CONTRACTS WERE DEEMED APPROVED BY
OPERATION OF LAW PURSUANT TO K:S.A. 66-
117(b)?
IV. STATEMENT OF FACTS
This case involves an appeal from a decision of the
Commission in which KPP sought approval of certain gas
purchase and transportation contracts entered into with WRI.
On March 15, 1995, WRI filed an application with the
Commission for approval of the contracts and for authority
to recover related charges through its purchase gas adjustment
clause ("PGA"). (R. Vol. 1, p. 1.) On March 31, 1995, KPP
filed an application with the Commission seeking approval of
certain gas transportation service agreements ("ISAs")
between KPP and WRI. (R. Vol. 1, p. 5.) On that same
date, KPP filed an application for approval and to make
effective certain firm gas purchase contracts ("GPCs")
between KPP and WRI. (R. Vol. 1, p. 63.)
Extensive hearings were conducted on the subject
contracts over a period of several weeks. Prior to the
hearing, extensive prehearing discovery was served by the
applicants and intervenors. Twenty-four witnesses offered
testimony the eleven days of the technical hearing.
2
The Commission had initially on April 20 and 21,
1995, entered several suspension orders suspending the TSAs
and GPCs for not more than 180 days from the date of
application. (R. Vol. 1, p. 143a and 143c.)
At the conclusion of the technical hearing, the parties
were ordered to file post-hearing briefs. Subsequently, on
November 1, 1995, Commission Staff filed a motion for stay
of proceedings. (R. Vol. 26, p. 185.) That motion was based
on a determination that had been made by the Federal Energy
Regulatory Commission (FERC) that it had jurisdiction over
the subject contracts because KPP constituted an interstate
pipeline. On November 3, 1995, the Commission entered an
order staying the proceedings. (R. Vol. 26, p. 208.) The
Commission followed the November 3, 1995 order with a
November 22, 1995 order wherein it ruled: (1) Subsequent
procedural orders issued by the Commission superseded the
original suspension orders issued in the case; (2) the
November 3, 1995 order issued by the Commission was
affirmed staying the consideration of these dockets until
FERC had taken final appealable action; and (3) the 240-day
time period (to the extent, if any, that it applies) was
restarted as of November 2, 1995. (R. Vol. 27, p. 146.)
KPP petitioned for reconsideration of the November
22, 1995 order. That petition for reconsideration was denied
on December 28, 1995. (R. Vol. 27, p. 184.)
KPP requested review of the December 28, 1995
order to the Court of Appeals. In a decision issued May 17,
1996, the Court of Appeals held that the Commission had not
acted on the applications within the time period prescribed by
K.S.A. 66-117(b) and, therefore, the contracts were deemed
approved by operation of law. The Commission, CURB and
3
Williams Natural Gas ("WNG") have petitioned the Court of
Appeals for rehearing. CURB now petitions this Court to
review the decision of the Court of Appeals. Although
captioned as a petition for review, this pleading may also be
deemed a notice of appeal to the Supreme Court as a matter
of right. Since a question under the Fourteenth Amendment
arises from the Court of Appeals’ decision, the appeal to this
Court may be made as a matter of right. (See K.S.A. 60-
2101(b).)
Vv. ARGUMENT AND AUTHORITIES
A. CURB And The Ratepayers It Represents Are
Entitled To Due Process of Law.
The decision of the Court of Appeals has effectively
denied CURB and the ratepayers which it represents their
statutory right to inquire into the propriety of the gas
purchase and transportation contracts that directly affect
Kansas ratepayers. CURB has argued at various times during
this appeal that the administrative process before the
Commission, wherein the contracts were subject to extensive
review, must be allowed to work, and that ratepayers are
statutorily entitled to have the contracts considered in light of
the wealth of testimony offered during the technical hearing
which was conducted by the Commission. (CURB Brief at
15-16.) CURB further argued that the Court should not
allow default to be taken against the ratepayers of the state
by a strict reading of K.S.A. 66-117(b). That statute
provides generally that the Commission must act on
applications filed with the Commission within 240 days,
unless certain conditions are satisfied.
The Court of Appeals’ decision which upheld the
application of K.S.A. 66-117(b) has denied Kansas ratepayers
their fundamental due process rights. The Fourteenth
Amendment to the U.S. Constitution provides in part:
"[N]or shall any state
deprive any person of
life, liberty, or
property, without due
process of law... ."
Due process requires, when liberty or property rights
protected by the Fourteenth Amendment are involved, the
right to a hearing prior to the taking. Stoldt v. City of
Toronto, 234 Kan. 957, 964, 678 P.2d 153 (1984). CURB
and the ratepayers it represents have been precluded by the
Court of Appeals’ application of K.S.A. 66-117(b) from
pursuing a meaningful hearing and have been deprived of a
protected property interest.
B. CURB And _ Kansas Ratepayers Have A
Protected Property Interest.
CURB is a creature of statute having been formed in
1989. (See K.S.A. 66-1222, et seg.) Operating through its
Consumer Counsel, CURB is statutorily empowered to:
1. Represent residential and small commercial
ratepayers before the State Corporation Commission;
2. Function as an official intervenor in cases
filed with the State Corporation Commission,
including rate increase requests;
3. Initiate actions before the State Corporation
Commission;
4. Represent residential and commercial
ratepayers who file formal utility complaints with the
State Corporation Commission;
5. Intervene in formal complaint cases which
would affect ratepayers; and
6. Make application for a rehearing or seek
judicial review of any order or decision of the State
Corporation Commission.
(See K.S.A. 66-1223.)
The thrust of the legislation was to create an advocate
for residential and small commercial ratepayers in utility
proceedings before the Commission. CURB has been
empowered statutorily to pursue matters on behalf of
ratepayers whenever ratepayers could be adversely affected
by the decision of the Commission. The statutory foundation
for CURB to protect the interests of ratepayers is solid. That
statutory empowerment rises to the level of a protected
property interest for Kansas ratepayers.
The ability of CURB to represent ratepayers is a
constitutionally protected one in light of the decisions from
the U.S. Supreme Court which establish the parameters for
protected property interests. The hallmark of property is an
individual entitlement grounded in state law, which cannot be
removed except "for cause." A cause of action is a species
of property protected by the Fourteenth Amendment’s due
process clause. Mullane v. Central Hanover Bank & Trust
6
Co., 339 U.S. 306 (1950). Here the Legislature has
specifically created the authority for CURB to file causes of
action on behalf of ratepayers before the Commission.
K.S.A. 66-1222, et seq. creates a protected property interest
in ratepayers. That property interest is protected by the
Fourteenth Amendment’s due process clause. The Court of
Appeals’ decision compromises CURB’s right to intervene in
and participate in matters pertinent to Kansas ratepayers.
Ratepayers have had their right io participate guaranteed
under K.S.A. 66-1223 extinguished without due process of
law.
This deprivation is particularly egregious when one
considers that CURB’s right to pursue causes of action on
behalf of ratepayers is taken away through no fault of CURB.
The Court of Appeals failed to recognize that it is the
ratepayers and not the Commission who ultimately would
suffer the consequences of the subject contracts. Yet, the
Court of Appeals would take away the statutory right of
CURB to pursue such matters simply for the reason that the
Commission did not purportedly issue a decision within the
required timeframe. The application of K.S.A. 66-117(b) to
the facts in this case results in constitutional harm being
inflicted on unsuspecting ratepayers of the state. This
deprivation requires reversal of the Court of Appeals’
decision.
C. Due Process Dictates That CURB Be Allowed
A Hearing And A Decision On The Merits Of
The Disputed Contracts.
Property rights once conferred by the Legislature
cannot be withdrawn without due process of law. The
Fourteenth Amendment requires as a matter of due process an
7
opportunity to be heard granted at a meaningful time and in
a meaningful manner. Armstrong v. Manzo, 380 U.S. 545,
552 (1965). Where the state has conferred a property
interest, that interest cannot be taken without constitutional,
procedural due process. Kosik v. Cloud County Community
College, 250 Kan. 507, 512, 827 P.2d 59, cert. denied 113
S.Ct. 195, 121 L.Ed.2d 138 (1992).
While the Legislature may elect not to confer a
property interest, it may not constitutionally authorize the
deprivation of such an interest, once conferred, without
appropriate procedural safeguards. The adequacy of statutory
procedures for deprivation of a statutorily created property
interest must be analyzed in constitutional terms. Vitek v.
Jones, 445 U.S. 480, 490-491 (1980). Here ratepayers are
granted a statutory right to participate in rate proceedings
through CURB. CURB and its constituency were deprived
of their statutory right to intervene and participate in an
administrative proceeding conducted solely for the purpose of
determining the prudency of certain contracts the burden of
which would fall ultimately on ratepayers. The Court of
Appeals’ endorsement of KPP’s suggested application of
K.S.A. 66-117(b) deprives Kansas ratepayers of their
statutorily granted property interest without due process of
law. Some form of hearing is required before the owner of
the property interest is finally deprived of such interest.
Board of Regents v. Roth, 408 U.S. 564, 570-571 (1972).
It is the statutory scheme embodied in K.S.A. 66-
117(b) that destroys ratepayers’ property interest, by
operation of law, v"henever the Commission fails to act on an
application in a timely manner. K.S.A. 66-117(b) is
defective for constitutional reasons. The Kansas Legislature
created CURB to serve as a watch dog for ratepayer interests.
8
The specific authority of CURB to maintain causes of action
on behalf of ratepayers cannot be taken by the application of
K.S.A. 66-117(b).
There is no public policy which would support the
conclusion that ratepayers should have their right to challenge
the subject contracts terminated by a technical application of
K.S.A. 66-117(b) and through no fault of the ratepayers.
CURB is entitled to have the Commission consider the merits
of the contracts based upon the substantiality of the evidence.
In Logan v. Zimmerman Brush Co., et al., 455 U.S.
422 (1982), the U.S. Supreme Court held that a state may not
terminate a complaining party’s cause of action because a
state official, for reasons beyond the complaining party’s
control, failed to comply with a statutorily mandated
procedure. In that case, the complaining party brought an
employment-related claim under the Illinois Fair Employment
Practices Act. That Act provided that the Illinois Fair
Employment Practices Commission had 120 days within
which to convene a fact finding conference designed to
obtain evidence, ascertain the positions of the parties, and
explore the possibility of negotiated settlement. It was
discovered that the hearing inadvertently had been scheduled
after the expiration of the 120-day period. Through a strict
application of the statutory language regarding the 120-day
limitation, the complaining party’s cause of action was
dismissed by the lower court. The 120-day period was
deemed to be jurisdictional.
Citing Mullane, supra, the U.S. Supreme Court held
that the complaining party’s cause of action was, in fact, a
property interest protected by the Fourteenth Amendment.
The Court held that the complaining party was entitled to an
9
opportunity granted at a meaningful time and in a meaningful
manner for a hearing appropriate to the nature of the case.
Since the complaining party was denied that opportunity, the
Supreme Court reversed.
The factual setting in the instant case is analogous to
that in Logan. Here, the Legislature has created a statutory
cause of action through CURB to protect and advance the
interests of residential and small commercial ratepayers in the
state. The decision of the Court of Appeals that the contracts
between KPP and WRI have gone into effect by operation of
law effectively deprives ratepayers of the state their cause of
action without due process of law. K.S.A. 66-117(b) as
applied by the Court to the facts of this case is
unconstitutional. CURB is entitled to have its day in Court.
The decision of the Court of Appeals should be reversed and
the case remanded to the Commission for further
proceedings. The ratepayers of the state should not be
saddled with the consequences of these contracts, which have
not been approved based upon their merits, by a technical
application of K.S.A. 66-117(b). To do so would result in a
deprivation of ratepayer rights simply for the cause of
expediency.
CURB had previously asked the Court of Appeals not
to abandon or ignore thousands of hours of staff work and
hundreds of thousands of dollars of legal and technical
analysis expended on the five contracts submitted for
approval. The Court of Appeals rejected that plea. CURB
now renews that request to this Court. The failure to allow
the contracts to be considered based on the evidence
introduced at the administrative hearing would run afoul of
the constitutional due process principles enunciated in Logan.
10
VI. CONCLUSION
In light of the arguments advanced above, CURB
respectfully requests that the Supreme Court review the
decision of the Court of Appeals, reverse that decision and
remand the cause to the Commission for further proceedings.
Respectfully submitted,
/S/
Mark A. Burghart, No. 10251
W. Robert Alderson, No. 6629
ALDERSON, ALDERSON &
MONTGOMERY, L.L.C.
2101 S.W. 21st Street
Topeka, Kansas 66604-3174
(913) 232-0753
Attorney for Intervenor,
Citizens’ Utility Ratepayer Board
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.