Appendix — Williams Natural Gas Co. v. Kansas Pipeline Partnership
Supreme Court brief1997
Ask Donna
What actually matters in this document.
Text
ouproeme VOur, U.S.
FILED
Vv, D6 778 NOV 19 19%
OFFICE OF THE CLERK
Supreme Gut ft nited Stutes
TOBER TE 1996
WILLIAMS NATURAL GAS COMPANY,
Petitioner,
v.
KANSAS PIPELINE PARTNERSHIP,
Respondent
On Petition for Writ of Certiorari
to the Supreme Court of the State of Kansas
APPENDIX TO PETITION FOR
WRIT OF CERTIORARI
GARY W. BOYLE JAY V. ALLEN
COUNSEL OF RECORD THE WILLIAMS COMPANIES,
THE WILLIAMS COMPANIES, INC.
INC. 4100 ONE WILLIAMS CENTER
4100 ONE WILLIAMS CENTER TULSA, OKLAHOMA 74172
TULSA, OKLAHOMA 74172
(918) 588-2359
APPENDIX A
SUPREME COURT ORDER DISTRICT CASE NO.
IN THE SUPREME COURT
OF THE STATE OF KANSAS
DAVID P BATOW
WILLIAMS NATURAL GAS COMPANY
LEGAL DEPT 36TH FL
P O BOX 3288
TULSA OK 74101
KANSAS PIPELINE
PARTNERSHIP, PETITIONER,
Vv No. 96-75918-AS
THE STATE CORPORATION
COMMISSION OF THE STATE
OF KANSAS, RESPONDENT.
YOU ARE HEREBY NOTIFIED OF THE FOLLOWING
ACTION TAKEN BY THE COURT:
PETITION'S FOR REVIEW BY CURB, KCC &
WILLIAMS NATURAL GAS.
CONSIDERED BY THE COURT AND DENIED.
RESPONSES NOTED.
KCC DOCKET NOS. 192,506-U AND 192,507-U
DATE: 09/09/96.
CAROL G. GREEN
CLERK
APPENDIX B
No. 75,918
IN THE COURT OF APPEALS OF THE STATE OF
KANSAS
KANSAS PIPELINE PARTNERSHIP,
Appellant,
Vv.
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS,
Appellee.
SYLLABUS BY THE COURT
1. The Court of Appeals has exclusive jurisdiction to
review any action of the Kansas Corporation Commission
arising from a rate hearing. K.S.A. 1995 Supp. 66-1 18a(b).
2. The order under review in this case constitutes a final
agency action subject to judicial review.
3. K.S.A. 77-607 and K.S.A. 77-608 are construed and
applied.
4. K.S.A. 1995 Supp. 66-117 is construed and applied.
4 The scope of review of an agency action is set forth in
K.S.A. 77-621, which codified principles long recognized by
Kansas courts.
6. The cardinal rule of statutory construction is that the
intent of the legislature governs if that intent can be
ascertained.
intent of the legislature governs if that intent can be |
ascertained. '
7. If a general and a specific statute both apply to a given
situation, they should be read together and harmonized when
possible.
8. The Kansas Corporation Commission's authority is
limited to that conferred by statute.
9. A final order is one which terminates litigation on the
merits and leaves nothing to be done except to enforce the
result. In an agency setting, a final order needs to be more than
a mere procedural ruling.
10. In an administrative setting, finality should be
interpreted in a pragmatic way.
11. An agency's interpretation of a statute should be given
deference, but when reviewing a question of law, an appellate
court may substitute its judgment for that of the agency.
12. The legislature is presumed to understand the meaning
of the words it uses and the procedures it establishes.
13. When a statute is clear and unambiguous, a court must
give effect to the legislature's intent as expressed, rather than
determine what the law should or should not be.
14. An amendment involves a change or modification and
suggests an action by one of the parties to change, correct, or
revise.
15. Ordinarily, a change in statutory language is presumed
2
Bn ow
neeatiee ATR > ee AR. Me IR
to result from a legislative purpose to change its effect, but the
presumption is of little force if an amendment is adopted as
part of a general, technical revision to a statute.
16. Under the peculiar facts of this case, the relief sought
by Kansas Pipeline Partnership was deemed approved by
operation of law when the Kansas Corporation Commission
failed to finally act within 240 days of the application and
when neither of the exceptions of K.S.A. 1995 Supp. 66-117(b)
applies.
Appeal from the Kansas Corporation Commission.
Opinion filed May 17, 1996. Reversed.
James P. Zakoura, Richard W. Hird, and David J.
Roberts, of Smithyman & Zakoura, Chartered, of Overland
Park, and Fred J. Logan, Jr., of Logan & Logan, L.C., of Prairie
Village, for appellant.
Larry M. Cowger, of Kansas Corporation Commission,
for appellee.
Mark A. Burghart and W. Robert Alderson, of
Alderson, Alderson & Montgomery, L.L.C., of Topeka, for
intervenor Citizens’ Utility Ratepayer Board.
John C. Frieden and Kevin M. Fowler, of Frieden,
Haynes & Forbes, of Topeka, and David P. Batow and Gary W.
Boyle, of Williams Natural Gas Company, of Tulsa, Oklahoma,
for intervenor Williams Natural Gas Company.
Before ELLIOTT, P.J., ROYSE and KNUDSON, JJ.
ELLIOTT, J.: Kansas Pipeline Partnership (KPP) and
3
Western Resources, Inc., (WRI) entered into natural gas sales
and transportation contracts. KPP submitted the contracts to
the Kansas Corporation Commission (KCC) for approval
pursuant to K.S.A. 1995 Supp. 66-117(a). WRI also requested
KCC approval of the contracts and requested permission to
pass contract costs through to its customers. Complicating
matters, the KCC shifted a $ 5.9 million Linchpin Development
cost item from another rate hearing into this KPP application.
The other rate hearing is currently pending in this court as
appeal No. 75,730.
On judicial review, KPP asserts that because the KCC
failed to make a decision on these contracts and the
development cost item within time limits established by KCC
regulations and K.S.A. 1995 Supp. 66-117(b), the contracts and
other requested relief became "deemed approved" by operation
of law. This is the ultimate question for us to decide on the
merits of this appeal.
We agree with KPP and reverse.
A brief description of the major participants is as follows:
KPP is a natural gas public utility and the applicant before
the KCC.
The KCC is the state regulatory agency with the power
and authority to supervise and control intrastate natural gas
public utilities doing business in Kansas. See K.S.A. 66-101
et seq.
WRI is a class A natural gas public utility, authorized
to deliver natural gas to customers in Kansas, and was the other
signatory to the KPP contracts for which approval was sought.
4
< and
a ete ee a)
Be ee os
ene teh ahaa eter ewer Mk a teen De
ee
WRI also sought approval of the contracts, but has not
appealed the matter to this court.
Williams Natural Gas Company (WNG) is also a
natural gas public utility and is a marketplace competitor of
KPP.
The Citizens’ Utility Ratepayer Board (CURB) is a state
agency created to look out for the interests of individuals and
small businesses in regulating public utilities.
The Federal Energy Regulatory Commission (FERC)
is a federal agency regulating interstate pipelines which are
within its exclusive jurisdiction.
The five contracts may be summarized thus: The
contracts between KPP and WRI call for the sale and
transportation of increased volumes of natural gas for delivery
in Johnson, Wyandotte, Franklin, and Miami Counties in
Kansas. Two of the three gas purchase contracts require KPP
to deliver natural gas to the city gates at Ottawa, Paola, and
Osawatomie for a term of 20 years. The third gas purchase
contract calls for KPP to transport and sell natural gas to
delivery points in Johnson and Wyandotte Counties for a term
of 10 years.
The two transportation contracts call for the
construction of a 24-mile pipeline spur to connect the
Panhandle Eastern Pipeline Company's facilities to those of
WRI (the "Metcalf Contract"), and for KPP to provide natural
gas to WRI for Johnson and Wyandotte Counties commencing
‘n the year 2009 (the "2009 Contract”).
Jurisdiction
5
Without detailing the various dates on which various
pleadings were filed, we have determined the jurisdictional
filings by KPP are timely.
We have exclusive jurisdiction to review any action of
the KCC arising from a rate hearing. K.S.A. 1995 Supp.
66-118a(b). In KPP's original filing, it did not request a rate
increase, but WRI did. The WRI docket was consolidated with
the KPP filing. Additionally, the joinder of the Linchpin
Project Development costs into this proceeding made it an
action vena a to a prior rate case. See MAPCO
Ape. 24 527, 330-31, 704 P.2d 989 (1985); In re Application
of Southwestern Bell Tel. Co., 9 Kan. App. 2d 525, 529, 685
P.2d 304, rev. denied 236 Kan. 875 (1984).
The parties seem to agree that this case is closely
enough connected to an underlying rate case to give us
jurisdiction.
While we have determined we have jurisdiction under
K.S.A. 1995 Supp. 66-118a(b), a question still remains whether
the KCC order of November 22, 1995, is reviewable.
By applying the relevant considerations of
Southwestern Bell, the KCC order is a final agency action
entitling KPP to judicial review. The KCC's denial of KPP’s
arguments that the contracts were "deemed approved” due to
the expiration of time is a final decision on this issue. It has a
direct effect on KPP and presents a legal question for our
review. Further, ruling on this issue does not disrupt the
orderly process of adjudication in the administrative
proceeding. The November 22, 1995, KCC order is final
agency action subject to review.
6
In Southwestern Bell, we did not clearly state whether
we were considering a final agency decision or a nonfinal
agency decision ripe for interlocutory review. Either way, we
have jurisdiction to consider KPP's appeal. See K.S.A.
77-607(b), K.S.A. 77-608.
Merits
In orders mailed April 21 and 24, 1995, the KCC
suspended the effective dates of the contracts for 180 days of
their filing on March 31, 1995; the WRI rate request and the
KPP contract dockets were consolidated. After numerous
continuances, hearings were finally conducted between August
21, 1995, and September 6, 1995. At the close of the hearings,
the KCC closed the record, ordered briefs filed by October 6,
1995, and took the dockets under advisement.
After briefs were filed but before the KCC issued a
decision, FERC issued a draft order stating it had jurisdiction
over KPP as an interstate pipeline. When FERC asserts
jurisdiction, any state regulatory agency loses jurisdiction. As
a result, the KCC staff on November 1, 1995, requested a stay
pending a final order from FERC. KPP opposed the stay. The
KCC issued a stay on November 3, 1995, and on November 22,
1995, issued an order superseding the earlier order, in which it
found:
(1) Expiration of the initial 180-day time period set by the
KCC did not cause the contracts to be deemed
approved because that order was subject to further
KCC orders and KPP did not object to the closing of
the record as of October 6, 1995 (beyond the 180-day
period);
(2)
(3)
(4)
(1)
(2)
(3)
(4)
The KCC order of November 3, 1995, which was
within the 240-day limitation of K.S.A. 1995 Supp.
66-117(b) was “probably a sufficient adjudication
within the 240-day period of time”;
The KCC restarted the 240-day clock called for by
K.S.A. 1995 Supp. 66-117(b) because the FERC
finding of jurisdiction over KPP was a "substantial
alteration of the facts" forming the basis for the KPP
request; and
"a continued stay at this juncture serves the public
interest especially in light of the unbundling concerns
raised by staff should FERC ultimately find it has
jurisdiction” over KPP.
On December 8, 1995, several things occurred:
FERC stayed its assertion of jurisdiction over KPP and
clarified that KCC orders regarding KPP will remain in
effect until FERC made its final rulings in the case.
The KCC denied KPP's request to reconsider its
November 3, 1995, order because it was superseded by
the KCC order of November 22, 1995.
KPP requested reconsideration of the November 22
KCC order, which was denied on December 28, 1995.
FERC issued an order clarifying a prior order. In this
order, FERC stayed its assertion of jurisdiction over
KPP until 60 days after an order on the merits of
petitions for rehearing. FERC also ruled that,
meanwhile, KPP could continue to provide services,
_
collect rates on file with the KCC, and "undertake all
; ivi . I + i t [FERC] j tl : te tly
(Emphasis added.)
On appeal, our scope of review is set forth in K.S.A.
77-621, which codified principles repeatedly recognized by
Kansas courts. See, ¢.g., Kansas Gas & Elec. Co. v. Kansas
Corporation Comm'n, 239 Kan. 483, 497-98, 720 P.2d 1063
(1986); Midwest Gas Users Ass'n v. Kansas Corporation
Commission, 3 Kan. App. 2d 376, 380-81, 595 P.2d 735, rev.
denied 226 Kan. 792 (1979).
Further, we recognize that the cardinal rule of statutory
construction is that the intent of the legislature governs if that
intent can be ascertained. City of Wichita v. 200 South
Broadway, 253 Kan. 434, 436, 855 P.2d 956 (1993).
As indicated earlier, at the close of the technical
hearings, the KCC ordered the filing of briefs by October 6,
1995. KPP did not object to the October 6 date, although it
was beyond the 180 days mentioned in the original suspension
orders which expired on September 27, 1995. Accordingly, we
shall concentrate our evaluation of this appeai on the 240-day
limitation contained in K.S.A. 1995 Supp. 66-117(b).
The KCC has never suggested this case is not controlled
by K.S.A. 1995 Supp. 66-117(b). Although the statute does not
specifically list "gas purchase contracts” or "gas service
agreements," clearly these would fall within "practice
pertaining to the service or rates of such public utility.” See
K.S.A. 1995 Supp. 66-117(a).
CURB argues this case is governed by K.S.A. 1995
Supp. 66-1,203, which specifically applies to natural gas public
9
utilities. Pursuant to that statute, every natural gas public
utility regulated by the KCC must furnish the KCC with copies
of all contracts between natural gas public utilities and all
jurisdictional services to be rendered by the utility. WNG also
urged this position during oral arguments. This statute applies
specifically to natural gas public utilities regulated by the KCC,
while K.S.A. 1995 Supp. 66-117(b) merely applies to all public
utilities regulated by the KCC.
If a general and a specific statute both apply to a given |
situation, they should be read — and nay nen |
possible. See Kansas Racing . an:
Racing Comm'n, 244 Kan. 343, 353, 710 P.2d 423 (1989) The
provisions of these two statutes can be read consistently.
K.S.A. 1995 Supp. 66-117(b) applies when any public |
utility is requesting a change in its rates or services that will |
have an impact on its customers. On the other hand, 66-1,203
requires a natural gas public utility to file copies of its rates and
contracts, even if no changes are requested. Although the
statutes overlap to some extent, they are not inconsistent and
both are applicable.
At last, we reach the core question for our
determinztion: Is KPP’s request for relief "deemed approved"
by the KCC's failure to issue a final order on the proposed
changes within the 240-day period mandated by K.S.A. 1995 :
Supp. 66-117(b)? We answer in the affirmative.
Preliminarily, at oral argument, the KCC acknowledged
that 66-117 is the only statute permitting suspension of an
effective date, and CURB candidly, but reluctantly, agreed that
66-117 controls this appeal.
10
ee
No one contests that the KCC's authority is limited to
that conferred by statute. Citi
Cities Service Gas Co. v. State
Corporation Commission, 197 Kan. 338, 342, 416 P.2d 736
(1966); Kansas-Nebraska Natural Gas Co. v. Kansas
Corporation Commission, 4 Kan. App. 2d 674, 675, 610 P.2d
121, rev. denied 228 Kan. 806 (1980). We must determine
what now happens when the KCC fails to exercise the power
conferred on it by statute.
K.S.A. 1995 Supp. 66-117(b) specifically provides that
the KCC shall not delay the effective date of a proposed change
in rate or many practice pertaining to service for more than 240
days beyond the date the utility filed its application with the
KCC.
The statute further provides that if the KCC has not
issued a final order within those 240 days, then "the schedule
shall be deemed approved by the commission and the proposed
change shall be effective immediately, except that (1) ... any
amendment to an application . . . which increases the amount
sought by the public utility . . . or substantially alters the facts
used as a basis for requested change . . . shall, at the option of
the commission, be deemed a new application and the 240-day
period shall begin again from the date of the filing of the
amendment, and (2) if hearings are in process before the
commission . . . on the last day of such 240-day period, such
period shall be extended to the end of such hearings plus 20
days to allow the commission to prepare and issue its final
order." K.S.A. 1995 Supp. 66-117(b) (Emphasis added.)
No one contends the hearing was "in process before the
commission" on the 240th day. The KCC closed the record and
took the matter under advisement prior to expiration of the
240-day period. The question is whether either of the KCC
1]
orders of November 3 and 22, 1995, was a "final order" for
purposes of 66-117(b). If so, both were entered within the
240-day clock. If not, we must decide whether the KCC acted
properly in restarting the 240-day clock. We note that the KCC
closed the record in these consolidated dockets at the
conclusion of hearings on September 6, 1995. So far as we can
determine, the KCC never reopened the record in these
consolidated dockets. See K.A.R. 82-1-230(k), (1).
KPP filed its request for approval of the five contracts
on March 31, 1995; the 240th day thereafter would be
November 29, 1995. On November 2, FERC issued a draft
order asserting jurisdiction over KPP, and on November 3 the
KCC, sua sponte, determined the dockets should be stayed.
Then on November 22, 1995, the KCC issued another
order affirming its order of November 3 and ordering these
dockets be stayed until FERC took final, appealable action.
This order also purported to restart the 240-day clock ("to the
extent, if any, that it applies") as of November 2, 1995. The
KCC also stated its November 22 order superseded its
November 3 order.
"Final order” has been defined as one which terminates
the litigation on the merits and leaves nothing to be done
except to enforce the result. Black's Law Dictionary 630 (6th
ed. 1990). In an administrative setting, a final order needs to be
more than a mere procedural ruling, and “finality” should be
Southwestern Bell Tel. Co. v.
12
~. net 2 Sas nein
In the present case, the KCC orders enter a stay pending
a decision by FERC. A "stay" is a suspension of a case.
Black's Law Dictionary 1413 (6th ed. 1990). By entering a
stay, the KCC did not issue a final order in the proceeding.
Accordingly, this case presents a good example of when
a KCC order can be final agency action under 77-607(b)(1), but
not a final order under 66-117(b). The KCC's decision
rejecting KPP’s argument the contracts should be deemed
approved (66-117[b]) is a final ruling on that statutory
interpretation question. Nothing is unresolved, rendering it a
final agency action under 77-607(b)(1). On the other hand,
since the KCC has made no ruling regarding whether KPP’s
contracts should be approved, it has not entered a final order on
the proposed changes under 66-1 17(b).
As WNG argues, both times the "deemed approved"
language appears in the statutes, the phrase refers to a
"schedule." “Schedule” is not defined in any statute or any
KCC regulation which we have been able to discover, and the
parties have not referred us to any such definition. The general
definition of "schedule" would cover almost, any filing, and
pragmatically, we conclude the KPP contracts and other
documents appended to its application meet the requirement of
a schedule. See K.A.R. 82-1-231; Black's Law Dictionary
1344 (6th ed. 1990).
The KPP contracts would change the practices
pertaining to services made available by KPP for WRI's
customers. Accordingly, the changes set forth in the contracts
fall under the provisions of 66-117(b) requiring KPP to request
approval of the changes.
Before leaving this aspect of the case, we need to
13
discuss the legislative history for 66-117. Dramatic changes
were made to KCC procedures in 1960 by the enactment of
S.B. 881. L. 1980, ch. 200. Minutes of hearings before the
House Ways and Means Committee on the bill make clear the
legislature was aware it was making significant changes.
Minutes to a hearing on April 8, 1980, report that Senator
Frank Gaines supported the bill which would permit a utility to
automatically get the increase sought when the KCC did not act
within a certain time frame. See House Ways and Means
Committee, 1980 Session, Minutes of April 8, 1980, p. 1.
Throughout the debate on S.B. 881, the KCC was given only
180 days to decide a case, but the final bill changed this to 240
days.
Most of the testimony before the Ways and Means
Committee uses the term "utility rate cases” in discussing the
bill, but the term is never defined. Further, "schedule" is not
mentioned, except in a proposed draft of the bill. A main
proponent of the bill was Southwestern Bell Telephone
Company (SWB), which argued time limits were not new and
had been adopted by numerous regulatory agencies across the
country. Testimony of Bill Ewing (SWB), Attached to Minutes
of House Ways & Means Committee, April 8, 1980.
Opposing S.B. 881 was Pete Loux, then chair of the
KCC. He argued the states which had adopted time limits had
much larger staffs or were responsible for regulating fewer
companies. Chairman Loux also presented a staff position
paper authored by Brian Moline, then general counsel of the
KCC. Moline expressed concern that the language of S.B. 881
was very broad and cautioned that the bill "changes long
established public policy of Kansas." KCC Staff Position on
S.B. 881, Attached to Minutes of House Ways & Means
Committee, April 8, 1980, at 4.
14
:
:
;
i
ar loa ad
Our review of the legislative history convinces us the
purpose of S.B. 881 was to adopt time limits to remedy delays
utilities had experienced with the KCC. Nothing in the
legislative history suggests the legislature intended to
distinguish between "pure" rate cases and hybrid cases that
could be considered “arising from a rate hearing" and thus
appropriate for exclusive review by this court.
While S.B. 881 does not refer specifically to 66-1 18a,
giving us exclusive jurisdiction over appeals arising from a rate
hearing, the bill did amend 66-1 18g, setting the time limits in
which we must decide such cases.
Nothing we have discovered suggests the time limits
covered by S.B. 881 were intended to be different for rate cases
under 66-117 as opposed to cases arising from a rate hearing
pursuant to 66-118g. If a case arises from a rate hearing for
purposes of 66-118g, legislative history suggests the time
limits of 66-117(b) would also apply.
No one really contests that this case is one arising from
a rate hearing. Under the express language of 66-117(b), the
schedules/contracts are deemed approved and the proposed
changes take effect immediately unless a final order is issued
by the KCC within 240 days of KPP's application, or unless
one of the exceptions applies.
Here, no final order was issued. As a result, our final
question is whether the KCC had the statutory power and
authority to restart the 240-day clock under the peculiar facts
of this case.
K.S.A. 1995 Supp 66-117(b) provides that after 240
days, the schedule is deemed approved except where an
15
amendment to an application seeks an increase in the amount
sought or substantially changes the facts used as a basis for the
requested change.
The KCC interprets the statute broadly to include any
change of the facts, regardless of whether an amendment to the
application has been filed. We are unable to agree with the
KCC's interpretation.
Here, none of the parties filed any amendment to the
application for proposed change that increased the amount
sought by the KPP. Thus, the only way this proceeding could
be extended is if the KCC were correct in finding (1) that
FERC's preliminary assertion of Jurisdiction substantially
altered the facts used as a basis for the requested change and
(2) that this gave the KCC the option to deem a new
application had been filed.
240-day clock. WNG asserts that 66-1 17(b) simply does not
apply. As previously held, the legislature did not distinguish
KCC regulations provide for specific procedures to
follow when a public utility wants to revise or amend its
application or schedules. See K.A.R. 82-1-231(d). Further,
Chairman Loux, in his letter to Mike Hayden, then chair of the
16
House Ways and Means Committee, specifically voiced his
concern whether an amendment by an applicant would restart
the time clock. Loux Memo dated April 8, 1980, attached to
House Ways and Means Committee Minutes.
FERC issued its initial order on November 2, 1995.
Yet in its order of November 22, the KCC recognized it had
continuing jurisdiction over KPP. FERC then stayed its earlier
order and clarified that KPP was allowed to undertake all
activities authorized by the KCC. The KCC did not issue its
order denying KPP's petition to reconsider until December 28,
1995.
The KCC argues that the FERC order asserting
jurisdiction over KPP was a substantial alteration of the facts.
An agency's interpretation of a statute should be given
deference, but when reviewing a question of law, we may
substitute our judgment for that of the agency. See Hickey v.
Kansas Corporation Comm'n, 244 Kan. 71, 76, 765 P.2d 1108
(1988).
We note that the KCC was aware as early as June 2,
1995, that FERC was considering asserting jurisdiction over
KPP. Since the parties were aware of FERC's interest in KPP
for 5 months, we are unable to understand how FERC's order
of November 2, 1995, is a substantial alteration of the facts
used as a basis for the requested approval of contracts. The
facts supporting the proposed changes remained the same
although the status of the parties may well have been altered.
Simply put, the punctuation of the statute in light of the
legislative history precludes the KCC's interpretation of
66-117(b).
17
The legislature is presumed to understand the meaning
of the words it uses and procedures it establishes. State Bank
Commissioner v. Emery, 19 Kan. App. 2d 1063, 1071, 880
P.2d 783 (1994). And when a statute is clear and
unambiguous, we must give effect to the legislature's intent as
expressed, rather than determine what the law should or should
not be. Martindale v. Tenny, 250 Kan. 621, Syl. P 2, 829 P.2d
561 (1992).
Finally, we must decide whether the statutory phrase
“substantially alters the facts used as a basis for such requested
change of rate" modifies "any amendment” or whether it
applies to any change regardless of origin. Grammatically, we
have no hesitancy in holding “amendment” is the controlling
noun which is the subject of the modifying phrase.
An amendment makes a change or modification.
Black's Law Dictionary 81 (6th ed. 1990). It suggests an action
by one of the parties to change, correct, or revise. No action
was taken by KPP, WRI, or the KCC to change or modify the
application which would trigger the provisions of 66-117(b).
Further review of the legislative history concerning the
evolution of this provision supports our conclusion that an
amendment is required.
The phrase “which amendment” contained in the
original 1980 legislation, was deleted in 1988, as part of
legislation that broadened application of the administrative
procedures act. The legislation changed all time limits from
being written out, to numerals (i.¢., two hundred forty, to 240).
See L. 1988, ch. 356, at 225.
When the phrase under scrutiny is read to include
"which amendment” the original intent of the legislature is
clearer. The 1988 changes were the result of S.B. 334, which
made some substantive changes to the administrative
procedures act, but overall appears to be a technical bill to
"clean up” the statutes by converting to numerals.
Ordinarily, a change in statutory language is
presumed to result from a legislative purpose to change its
effect. Schuhs v. Schuhs, 20 Kan. App. 2d 98, 99, 883 P.2d
1225 (1994). But this presumption is of little force if an
amendment is adopted as part of a general, technical revision
to a statute. Board of Education U.S.D. 512 v. Vic Regnier
Builders, Inc., 231 Kan. 731, 736, 648 P.2d 1143 (1982).
We do not view the deletion of the phrase "which
amendment” by the legislature in 1988 as a substantive change
intended to modify the meaning of 66-117(b). Rather, the
change was merely part of a larger bill seeking to bring
consistency to statutes under the administrative procedures act.
At the time the original provisions imposing time limits
on the KCC were adopted, the House Ways and Means
Committee rejected without discussion a suggestion that would
have given the KCC more flexibility in deciding cases under
the new time limits. House Ways and Means Committee
Minutes, May 2, 1980, p. 2.
Thus, the legislature was intent on forcing the KCC to
act within prescribed time limits; if it does not, the proposed
changes take effect. In 1980, the legislature recognized the
increased burden the time limits would place on KCC staff.
Senator Frank Gaines assured members of the House that
adequate funds would be provided for the KCC "to adequately
and efficiently carry out the provisions of this act” and further
19
"gave his personal assurance that funds would be provided."
House Ways and Means Committee Meeting, May 2, 1980, p.
#
CURB asks us not to abandon or ignore the "thousands"
of hours of staff work and the "hundreds of thousands of
dollars” of legal and technical analysis expended on the five
contracts submitted for approval. But legislative history makes
clear that was precisely an anticipated result should the KCC
fail to make a final decision within the time limits provided by
K.S.A. 1995 Supp. 66-117(b).
The contracts and related requests contained in KPP's
consolidated KCC dockets must be deemed approved by
operation of law.
Reversed.
20
DE YER OR Om
APPENDIX C
PP ee CY Se ET
RATS TMI Ot ay
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS
Before Commissioners: Susan M. Seltsam, Chair
F. S. Jack Alexander
Timothy E. McKee
Docket No.
192,506-U
In the Matter of the Filing
of Kansas Pipeline Partnership for
approval and to make effective
certain firm gas purchase contracts
between Kansas Pipeline
Partnership and Western Resources,
Inc.
Docket No.
192,391-U
In the Matter of the Application of )
Western Resources for an order )
approving certain contracts with )
Kansas Pipeline Partnership, and )
authorizing inclusion of costs related )
to such contract in Western )
Resources’ purchased gas adjustment )
clause for recovery from its customers.)
In the Matter of the Filing of Kansas ) Docket No.
Pipeline for approval andto make ) 192,507-U
effective certain gas transportation )
service agreements between Kansas )
Pipeline Partnership and Western) ENTERED
Resources, Inc. ) NOV 3 1995
ORDER
On October 25, 1995, the Federal Energy Regulatory
Commission (FERC) decided during their administrative
meeting that KansOk Partnership (KansOk), Kansas Pipeline
Partnership (Kansas Pipeline) and Riverside Pipeline
Company, L.P. (Riverside) constituted an interstate pipeline
subject to FERC's jurisdiction. In response to FERC's action
and draft order, the Kansas Corporation Commission Staff
(Staff) filed a Motion for Stay of Proceedings on November,
1995.
Pursuant to K.S.A. 77-526(g), the Kansas Corporation
Commission (Commission) must issue an order within 30
(thirty) days after the conclusion of the hearing or submission
of findings. In this case, parties submitted their findings of
fact and conclusions of law on October 6, 1995. Accordingly,
the Commission has through November 6, 1995, in which to
issue an order or extend the period of time in which to issue a
final order ‘or good cause shown.
The Commission notes that on November 2, 1995,
FERC issued an initial order and Kansas Pipeline et al. was
ordered to file an application for certificate authorization. The
Commission, on its own motion, has determined that a stay of
the above referenced dockets is appropriate until all parties
have had an opportunity to respond to the Motion for Stay of
Proceedings filed by Staff and until such time as the period for
rehearing before FERC has passed and final appealable action
has been taken.
IT IS, THEREFORE, BY THE COMMISSION
ORDERED:
1. The above-referenced dockets are stayed
pending further order of this Commission.
2. All parties may file a response to Staff's Motion
for Stay of Proceedings on or before November 14, 1995.
2
EE
.
A party may file a petition for reconsideration of this
order within fifteen (15) days from the date of this order. If
service is by mail, three (3) additional days may be added to
the fifteen (15) day time limit to petition for reconsideration.
The Commission retains jurisdiction over the subject
matter and the parties for the purpose of entering such further
order or orders as it may deem necessary,
BY THE COMMISSION IT IS SO ORDERED.
Seltsam, Chr.; Alexander, Com., McKee, Com
Dated: November 3, 1995
[ORDER MAILED |
[NOV 3 1995
[JUDITH MCCONNELL |
[EXECUTIVE DIRECTOR!
a
Judith McConnell
Executive Director
APPENDIX D
_
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS
Before Commissioners: Susan M. Seltsam, Chair
F. S. Jack Alexander
Timothy E. McKee
Docket No.
192,506-U
In the Matter of the Filing
of Kansas Pipeline Partnership for
approval and to make effective
certain firm gas purchase contracts
between Kansas Pipeline
Partnership and Western Resources,
Inc.
ed
Docket No.
192,391-U
In the Matter of the Applicationof )
Western Resources for an order )
approving certain contracts with )
Kansas Pipeline Partnership, and )
authorizing inclusion of costs related )
to such contract in Western )
Resources’ purchased gas adjustment )
clause for recovery from its customers.) ,
Docket No.
192,507-U
In the Matter of the Filing of Kansas
Pipeline for approval and to make
effective certain gas transportation
service agreements between Kansas
Pipeline Partnership and Western
Resources, Inc.
ENTERED
NOV 22 1995
ee ee ee ee eee ee”
ORDER
This matter is before the Kansas Corporation
Commission (Commission) on the Motion of Commission Staff
(Staff) for Stay of Proceedings. On November 1, 1995, Staff
requested a stay of proceedings “pending a final order in
Federal Energy Regulatory Commission (FERC) Docket Nos.
RP95-212-000 and RP95-395-000." (Staffs motion, p. 1).
Staff based its request for stay on FERC's ruling on October 25,
1995, and Draft Order which provides that “the natural gas
transmission systems of KansOk Partnership, KPP and
Riverside Pipeline Company, L.P. (collectively referred to as
Kansas Pipeline) constitute an interstate natural gas pipeline
system subject to FERC jurisdiction under the Natural Gas
Act.” (Staffs motion, p.2). Staff argued that the Commission,
after FERC's ruling and issuance of a Section 7 Certificate to
Kansas Pipeline, would not have jurisdiction. Staff believes
further action would constitute “a wasteful and inefficient use
of the Commission's resources and would be unnecessary under
the present circumstances.” (Staff's motion, p.3).
"On November 2, 1995, FERC issued an official order
memorializing the action taken on October 25, 1995. On
November 3, 1995, the Commission stayed the above-
captioned cases pending an opportunity for all parties to
respond to Staff's Motion for Stay of Proceedings and until
such time as the period for rehearing has passed before FERC
and final appealable action has been taken.
For purposes of Staff's motion and the responses filed
thereto, Staff appeared by Larry Cowger; Kansas Pipeline
Partnership (Kansas Pipeline) appeared by James P. Zakoura
and Richard W. Hird; Western Resources, Inc. (Western
Resources) appeared by J. Michael Peters; Williams Natural
2
= oe ee ee eee eT
Gas Company (WNG) appeared by John C. Frieden and Kevin
M. Fowler, and the Cities of Ottawa and Paola, Kansas,
appeared by Robert L. Bezek, Jr.
Kansas Pipeline argues the process outlined by FERC
in its November 2, 1995 Order - “an application for certificate,
approval of terms and conditions of service, approval of rates,
and transitioning existing operations to be in compliance with
FERC Order No. 636 — could extend well over a year, and
perhaps more." (Kansas Pipeline's response, p.3). Kansas
Pipeline is seeking a stay of FERC's November 2, 1995 Order
and also intends to seek rehearing of that Order.
Kansas Pipeline argues the Commission is without
power to stay this action. Specifically, Kansas Pipeline
references the Commission's April 21, 1995 Orders in Docket
Nos. 192,506-U and 192,507-U which granted a 180-day
suspension period from the date the applications were filed on
March 31, 1995. Kansas Pipeline argues the suspension period
expired on September 27, 1995. Since there were no further
suspensions issued, Kansas Pipeline contends the contracts in
Docket Nos. 192,506-U and 192,507-U became effective on
September 27, 1995. (Kansas Pipeline's response p. 5).
Moreover, Kansas Pipeline contends even if FERC
arguably assumed jurisdiction on November 2, 1995, the
suspension period expired prior to FERC's order. In the
alternative, Kansas Pipeline argues that the Commission must
issue an order within 240 days, no later than November 29,
1995, or the contracts are deemed approved. K.S.A. 66-117.
(Kansas Pipeline's response, p.6)
Kansas Pipeline believes Staffs request for a stay is
“unusual, extraordinary and inappropriate.“ (Kansas Pipeline's
3
response, p.6). Only WNG, according to Kansas Pipeline, will
benefit from a stay and "the contracts may become null and
void simply by the passage of time..." (Kansas Pipeline's
response, p.7).
to have jurisdiction. If the Commission were not to regulate
Kansas Pipeline, prior to the issuance of a FERC certificate,
Kansas Pipeline would be in “jurisdictional limbo." (Kansas
Pipeline's response, p.8). Further, Kansas Pipeline intends to
pursue all available avenues of appeal regarding FERC's
November 2, 1995 Order. Staff's motion, according to Kansas
Pipeline, would place it in “regulatory limbo for an
indeterminate amount of time" and would constitute an
unconstitutional taking without compensation if it could not
charge “fair, just and reasonable rates." (Kansas Pipeline's
response, p.10). Kansas Pipeline believes a Commission
decision would be beneficial to the FERC and approval of the
applications would benefit consumers. (Response, pp.10-12).
Western Resources’ response calls attention to the
“commercial transactions for which time is important."
(Western Resources’ response, p.3). Western Resources also
believes the Commission “must reconcile its intended stay of
these proceedings in light of its April 20, 1995 Suspension
Order....". (Western Resources’ response, p.3). And finally,
Western Resources requests the Commission to tule
“expeditiously.” (Western Resources’ response, p.3).
WNG seeks reconsideration of the Commission's June
22, 1995 Order [denial of WNG’s motion for denial of stay] and
July 26, 1995 Order [denial of WNG’s motion to dismiss for
lack of subject matter jurisdiction] based on the “materially
changed circumstances" and requests that all pending
applications be dismissed without prejudice until such time as
FERC determines it "does not have jurisdiction over Kansas
Pipeline Partnership under the Natural Gas Act." (WNG's
response, p.2) WNG concurs with Staffs basis for a stay, but
believes dismissal of the pending applications on jurisdictional
grounds to be more appropriate. (WNG’s response, p.2)
WNG has argued that these proceedings are subject to
K-S.A. 66-117 and KAR. 82-1-231 but contends "it is unclear
whether the 240-day period prescribed in K.S.A. 66-117(b) is
applicable." WNG believes the Commission's Stay granted on
November 3, 1995, “to determine whether the Commission has
any continuing jurisdiction over the contracts and/or whether
the decision by FERC is effectively an amendment or
modification to the applications filed by joint applicants is
likely a sufficient adjudication or otherwise fulfills the
requirements under K.S.A. 66-117." (WNG's response, pp.3-
4). Arguably, the contracts may be “deemed approved"
pursuant to K.S.A. 66-117(b), notwithstanding the stay. WNG
contracts for lack of subject matter jurisdiction. (WNG's
response, p.5)
The Cities of Ottawa and Paola, Kansas (Ottawa and
Paola) believe "no valid reason exists for the Commission to
avoid deciding the above, to deny the approval of the five gas
and transportation contracts filed by Kansas Pipeline and deny
the pass-through of costs, resulting from the contracts to
Western Resources.” (Ottawa and Paola’s response, pp. 1-2).
Ottawa and Paola stated that the two main issues, whether to
approve the five gas contracts and whether to approve the pass-
through, are briefed and ready for decision. In the event FERC
removes jurisdiction from the Commission, Ottawa and Paola
contend the Commission would still have jurisdiction to
consider the pass-through issue. (Ottawa and Paola's response,
p. 2). Ottawa and Paola believe "[tJhe ability to acquire right
of way, utility easements and the utility franchise itself is
clouded by the lack of a decision regarding the gas and
transportation contracts." Moreover, "regarding the approval
and pass-through of these contract costs, there will always be
a question as to whether the franchise can be condemned with
or without the gas contracts." (Ottawa and Paola’s response,
pp. 2-3). Ottawa and Paola believe they will suffer harm if no
decision is made. (Ottawa and Paola's response, p. 3).
In the event the Commission believes the FERC
decision has the impact of removing jurisdiction, Ottawa and
Paola recommend the Commission dismiss this proceeding
without prejudice prior to the expiration of 240 days to avoid
approval of these contracts and impose certain conditions.
Those conditions would include the requirement that the refiled
action be submitted on the record that exists and that a decision
be rendered within a specified period of time, i.e., 60 (sixty)
days. (Ottawa and Paola's response, pp. 3-4). And finally, if
Kansas Pipeline and Western Resources make any
modifications to these contracts, then the prior contracts should
be deemed denied and the new contracts resubmitted with
6
notice to all parties and “without requiring agreement to
confidentiality contracts." (Ottawa and Paola's response, p. 4).
Staff filed a reply to the responses to Staff's motion for
stay. Staff set forth a brief procedural history of these
consolidated dockets. On April 20, 1995, the Commission
suspended for 180 days from the date of the applications,
approval of these agreements “subject to further order or orders
of the Commission.” (Docket Nos. 192,506-U and 192,507-U).
On April 27, 1995, the commission consolidated the above
three dockets upon Western Resource's motion. The
Commission set a procedural schedule by order dated May 10,
1995. Two subsequent orders modified the procedural
schedule and ultimately an evidentiary hearing commenced on
August 21, 1995. (Staffs reply, pp. 2-3). The evidentiary
hearing ended September 6, 1995, and parties were ordered to
file briefs and/or findings of fact and conclusions of law on or
before October 6, 1995. Staff interprets these orders as
superseding the prior suspension orders. While staff believes
"the Commission's orders modifying the procedural order
obviously extended the proceedings past the originally
scheduled 180 days, it would have apparently been helpful to
some parties had the Commission explicitly spelled out in un
order the fact that by extending its procedural orders past
September 27, 1995, the original suspension order had been
modified." (Staffs reply, p. 3). Accordingly, Staff now
requests the Commission to make this explicit finding at this
time.
Staff contends the only arguable “operation of law" date
to apply to these applications is contained in K.S.A. 66-117(b).
The statute first “provides that if a utility files ‘a schedule
showing the changes to be made,' such proposed schedule shall
be deemed approved if not suspended by the Commission
within thirty (30) days of its filing." (Staffs reply, pp. 3-4).
7
Moreover, the statute requires that the effective date of the
changes proposed may not be delayed beyond 240 days from
the date of filing. Staff references other statutory authority:
[T]he specific statute requiring the filing of
contracts by natural gas utilities, K.S.A 66-
1,203, makes no mention of the 240-day
requirement, nor does the statute authorizing a
hearing on gas rates, K. S.A. 66-1,204." (Staff's
reply, p. 4). In fact, case law discussing the
Comudalan duty to imvestigate the
reasonableness of contracts filed by a public
utility have indicated that such duty flows from
general grant of power and authority contained
in K.S.A. 66-101 (c.f. K.S.A. 66-1,201) which
likewise does not reference any 240-day
requirement. Central Kansas Power Co. v.
State Corp. Commission, 316 P.2d 277, 181
Kan. 817 (1957).
(Staffs reply, p. 4). Staff stated that the expiration of the 240-
day requirement, for argument purposes, would require a
decision on the contracts by November 27, 1995.
Staff highlights an exception to the 240-day rule and
argues its applicability here. K.S.A. 66-117(b)(1) provides:
(1) for purposes of the foregoing provisions
regarding the period of time within which the
commission shall act on an application, any
amendment to an application for a proposed
change in any rate, which increases the amount
sought by the public utility or common carrier
or substantially alters the facts used as a basis
for such requested change of rate, shall, at the
option of the commission, be deemed a new
application and the 240-day period shall begin
again from the date of the filing of the
amendment.
(Staffs reply, pp. 4-5 citing K.S.A 66-117(b\(1)). Staff
believes the Commission should exercise its discretion under
this provision. Staff concurs witii WNG’s interpretation that
the “Commission order to stay these proceedings to determine
whether it has any continuing jurisdiction over the contracts
and/or whether the decision by the Federal Energy Regulatory
Commission (FERC) is effectively an amendment or
ne ee ee ee 2
requirements under K.S.A. 66-117" (Staffs reply, p. 5). Staff
also interprets FERC's decision which subjects Kansas
Pipeline’s pipe gas transmission systems to federal jurisdiction
"is a matter which ‘substantially alters the facts used as a basis
for such requested change . . .'K.S.A. 66-117(b)" would enable
the Commission to exercise its discretion to restart the 240-day
period. (Staffs reply, p. 5).
There appears to be a consensus among the parties,
according to Staff, that the Commission has jurisdiction until
FERC grants Kansas Pipeline the Section 7 Natural Gas Act
authority. Even though the Commission continues to have
jurisdiction for at least a short period of time "does not mean .
. the Commission should exercise that authority and approve
expansion of the KPP interstate system through the proposed
construction projects envisioned in the current applications.“
(Staff's reply, pp. 5-6). Staff believes approving additional
sales volumes from Kansas Pipeline to Western Resources
would be “unwise” since FERC Order 636 would require
9
Kansas Pipeline "to cease its merchant function."
reply, p. 6).
(Staff's
Staff has outlined three options available to the
Commission at this time:
First, dissolve the stay and
determine this matter on the merits,
issuing an order no later than November
27, 1995, (in which case Staff would
refer the Commission to its Post-
Hearing Brief and urge that the
applications be denied for lack of
merit).;
Second, issue an order restarting
the 240-day period due to the
November 2, 1995 FERC Order finding
KPP (Kansas Pipeline) to be subject to
federal NGA jurisdiction and maintain
its stay of these proceedings until FERC
resolves any petition for rehearing filed
by KPP; or
Finally, to dissolve the stay and
to reconsider its Orders of June 22,
1995, and June 26, 1995, in light of the
pursuant to the NGA. Such an order
10
would also have to be issued no later
than November 27, 1995.
(Staff's reply, p. 6). Staff recommends, out of the options
presented, that the Commission reaffirm its order staying this
action pending a final order from FERC on reconsideration and
that the Commission restart the 240-day period based on the
fact that FERC's order substantially altered the basis for the
requested change. Staff believes the legislature contemplated
relief from the 240-day period for circumstances such as these
and neither Kansas Pipeline nor Western Resources should use
this provision to pressure the Commission into a decision.
(Staff's reply, p.8).
Kansas Pipeline takes issue with StafPs suggestion that
the 180-day suspension orders were extended by "implication."
Kansas Pipeline argues that "[p}rior to September 27, 1995, the
Commission could arguably have entered an order extending
the suspension period up to the full 240 days; however, neither
Staff, nor any other party, requested such an extension and the
Commission did not do so on its own motion or of its own
accord." (Kansas Pipeline's reply, pp.3-4). Kansas Pipeline
does not believe the deadline for submission of briefs after the
expiration of the 180-day suspension order to constitute a
written statement pursuant to K.S.A. 66-117. Kansas Pipeline
also does not believe an “order by implication" satisfies the
requirement that orders must be in writing. K.A.R. 2-1-232.
(Kansas Pipeline's reply, p.5). Kansas Pipeline did not suggest
that the Commission lost jurisdiction after expiration of the
suspension orders. Kansas Pipeline also disputes Staff's
reference to K.S.A. 66-1,203 and 66-1,204 for the proposition
that the 240-day period is inapplicable. Kansas Pipeline
believes only K.S.A. 66-117(b) governs time limitations in
11
Docket Nos. 192,506-U and 192,507-U. (Kansas Pipeline’s
reply, p.6)
Kansas Pipeline disagrees with Staff's recommendation
that FERC'’s November 2, 1995 Order altered the facts used as
the basis for the change in rates. Kansas Pipeline does not
believe the Commission's order staying this proceeding
constitutes an adjudication on the merits or sufficient grounds
to restart the 240-day time period. Kansas Pipeline believes
the three options presented by staff are erroneous and ignore
the statutory deadlines. (Kansas Pipeline’s reply, pp.8-9).
WNG has filed a reply to Kansas Pipeline’s response to
Staffs Motion for Stay. WNG suggests the following
alternatives for Commission action:
(i) entering an order of dismissal for lack
of subject matter jurisdiction (without
prejudice to further consideration on the
merits in the event of a final
determination that FERC lacks
jurisdiction over its operations) no later
than November 27, 1995;
Gi) fismissing KPP's licati
each is amended on or before
November 27, 1995, to address the
materially changed factual
circumstances presented by FERC's
November 2, 1995 Order; or
(iii) denying KPP's applications on the
merits for the factual and legal reasons
set forth in the post-hearing
12
submissions of the Staff and the
Intervenors.
(WNG's reply, p.2)
WNG recognizes the Commission's problem as to
whether it has jurisdiction after FERC's November 2, 1995
Order in Docket Nos. RP95-212-000 and RP95-395-000.
WNG is concerned that Commission inaction would result in
the “unpalatable possibility that the proposed contracts may
become effective by operation of law after November 27,
1995.". (WNG’s reply, p.2)
WNG also outlines the procedural history of these
dockets. WNG references the fact that Kansas Pipeline never
argued the contracts were effective by operation of law on
27, 1995, when the hearing was extended to
accommodate Dr. Stalon's testimony, one of Kansas Pipeline’s
witnesses. (WNG's reply, p.7). Nor did Kansas Pipeline,
according to WNG, make this representation when the
Commission announced the briefing schedule on September 6,
1995.
WNG believes that "[i}f the time limits of K.S.A. 66-
117(b) are applicable to these proceedings, this statute further
provides that ‘any amendment to an application for a proposed
change’ which ‘substantially alters the facts used as a basis for
such requested change’ may, in the Commission's discretion,
'be deemed a new application and the 240-day period shall
begin again from the date of the filing of the amendment.”
(WNG's reply, p.8). Although Kansas Pipeline has not filed an
amendment, WNG interprets the FERC's November 2, 1995
Order as changing the "factual bases for these applications.“
(WNG's reply, p.8). For instance, WNG referenced the fact
13
that the proposed contracts bundle both sales and transportation
while as interstate pipeline, those services would need to be
unbundled. (WNG’s reply, p.8).
WNG contends Kansas Pipeline's position before the
K te ete item. dhe
Commi we ang “eres _ ene ung aiaty tos
position before FERC. Kansas Pipeline has sought a stay from
FERC's November 2, 1995 Order on the grounds that FERC is
depriving the Commission of its “regulatory jurisdiction."
(WNG's reply, pp.8-9)
WNG also cites page 18 of FERC's November 2, 1995
Order “which sought . . . to prohibit KPP from ‘constructing
new pipelines or any expansions or extensions of existing
pipelines without [Federal Energy Regulatory] Commission
approval to the extent such construction requires Commission
approval. See FERC Docket No. RP95-395-000 (Complaint
of Williams Natural Gas Company, dated July 21, 1995, p. 63
at J (e))." (WNG's reply, p.10). Moreover, before any
construction for facilities or extension are put in force, the
interstate pipeline must have a FERC certificate. (WNG’s
reply, p.10). _WNG cites authority which support the
proposition that a state utilities Commission cannot exercise
concurrent jurisdiction with FERC. 15 USC § 717f{c(1A),
Cascade Natural Gas Corp. v. FE.R..C., 955 F.2d 1412 (10th
Cir. 1992); National Fuel Gas Supply Corp. v. Public Service
Comm'n of State of New York, 894 F.2d 571 (2d Cir. 1990).
WNG suggests that Kansas Pipeline could seek an
interim certificate from FERC to avoid any detrimental impact
on its proposals. (WNG’s reply, p.11). Moreover, WNG states
that “none of the proposed contracts involve sales or
transportation of natural gas during the 1995-96 winter heating
14
season.” In summary, WNG seeks dismissal “of the pending
applications for lack of subject matter jurisdiction (without
prejudice to further consideration on the merits in the event of
a final determination that FERC lacks jurisdiction over its
operations) no later than November 27, 1995, or to
immediately dismiss KPP’s pending applications unless it
amends each no later than November 27, 1995, to address the
materially changed factual circumstances presented by FERC's
November 2, 1995 Order and, in such event, to restart the 240-
day period for a final order hearing if deemed necessary."
(WNG's reply, p. 12). In the alternative, WNG seeks to have
the Commission deny Kansas Pipeline's applications or “issue
an order disapproving any new services and related pipeline
construction on or before November 27, 1995." (WNG’s reply,
p. 12).
Find + Conctusi
The Commission does not give any credence to the
argument raised by Kansas Pipeline that the subject contracts
(Docket Nos. 192,506-U and 192,507-U) became effective by
operation of law on September 27, 1995, the expiration of the
180-day suspension orders. The suspension orders entered
April 20, 1995, clearly provided they were subject to any
further order(s) of the Commission. Subsequent procedural
orders setting this matter for hearing superseded the earlier
suspension orders and the Commission so finds. Moreover, on
September 6, 1995, the Commission specifically directed the
parties to file briefs and/or findings of fact and conclusions of
law by October 6, 1995. No objection was raised by Kansas
Pipeline or any other party to the October 6, 1995 date for
purposes of closing the record. Had the parties felt the
contracts became effective September 27, 1995, there would
have been no need for briefs, etc. . The Commission deems
15
Kansas Pipeline’s failure to timely object to the Commission's
September 6, 1995 bench ruling as a waiver of their objection.
The Commission concurs with WNG’s contention that
the Commission's Order of November 3, 1995, is probably a
sufficient adjudication within the 240-day period of time. The
Commission's Order granting the stay was based on FERC's
official Order of November 2, 1995, which memorialized
FERC’'s decision from its October 25, 1995 agenda.
The Commission adopts Staff's recommendation and,
to the extent (if any) K.S.A. 66-117(b) applies, shall restart the
240-day clock. K.S.A. 66-117(b) specifically grants the
Commission discretion to restart the 240-day time period when
a substantial alteration of the facts occurs which formed the
basis for Kansas Pipeline's requested change, ic., FERC's
finding that Kansas Pipeline is an interstate pipeline subject to
the NGA. The Commission shall restart the 240-day clock as
of November 2, 1995, the date of FERC's order finding Kansas
Pipeline to be an interstate pipeline.
The Commission recognizes the concerns raised by
FERC grants Kansas Pipeline certificates or otherwise resolves
the pending dockets (Docket Nos. RP95-212-000 and RP95-
16
395-000). The Commission does not, however, believe this
requires the Commission to decide whether to approve
contracts, which may not be appropriate under FERC Order
636, as a prudent exercise of the Commission's discretion at
IT IS, THEREFORE, BY THE COMMISSION
ORDERED THAT:
1. The Commission's procedural orders setting
these consolidated dockets for hearing superseded any prior
suspension orders.
2. The Commission affirms its November 3, 1995
Order and stays consideration of these dockets until FERC has
taken final appealable action.
3. The Commission shall restart the 240-day time
period (to the extent, if any, that it applies) as of November 2,
1995.
A party may file a petition for reconsideration of this
order within fifteen (15) days from the date of this order. If
service is by mail, three (3) additional days may be added to
the fifteen (15) day time limit to petition for reconsideration.
matter and the parties for the purpose of entering such further
order or orders as it may deem necessary.
BY THE COMMISSION IT IS SO ORDERED.
Seltsam, Chr.; Alexander, Com.; McKee, Com.
Dated: November 22, 1995.
17
[ORDER MAILED ]
[NOV 22 1995 ]
[JUDITH MCCONNELL ]
[EXECUTIVE DIRECTOR]
Judith McConnell
18
APPENDIX E
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS
Before Commissioners: Susan M. Seltsam, Chair
F. S. Jack Alexander
Timothy E. McKee
In the Matter of the Filing
of Kansas Pipeline Partnership for
approval and to make effective
) Docket No.
certain firm gas purchase contracts)
)
)
)
192,506-U
between Kansas Pipeline
Partnership and Western Resources,
Inc.
In the Matter of the Application of ) Docket No.
Western Resources for an order ) 192,391-U
approving certain contracts with )
Kansas Pipeline Partnership, and )
authorizing inclusion of costs related )
to such contract in Western )
Resources’ purchased gas adjustment)
clause for recover from its customers.)
In the Matter of the Filing of Kansas ) Docket No.
Pipeline for approval and to make _—i+?) 192,507-U
effective certain gas transportation )
service agreements between Kansas _ )
Pipeline Partnership and Western _+) ENTERED
Resources, Inc. ) DEC 8 1995
ORDER
This matter is before the State Corporation Commission
of the State of Kansas (Commission) on Kansas Pipeline
Partnership's (KPP's) Petition for Reconsideration or, in the
Alternative, Petition for Hearing. KPP appeared by James P.
Zakoura, Richard W. Hird and Fred J. Logan, Jr. KPP seeks
reconsideration of the Commission's November 3, 1995 Order
which preliminarily stayed the above-captioned actions due to
FERC's Order issued on November 2, 1995, and in order to
give parties an opportunity to respond to Staffs Motion for
Stay. After the par’.es were given an opportunity to file
responses to Staff's Motion for Stay, the Commission issued a
subsequent order on November 22, 1995, which supersedes the
Commission's November 3 Order.
Accordingly, KPP's petition for reconsideration and
request for a hearing on the November 3, 1995 Order is denied
since the November 22, 1995 Order supersedes the November
3, 1995 Order and continues the stay of these proceedings.
IT IS, THEREFORE, BY THE COMMISSION
ORDERED THAT:
Kansas Pipeline Partnership's Petition for
Reconsideration or, in the Alternative, Petition for Hearing is
denied.
Kansas Pipeline Partnership has exhausted its
administrative remedies as to the November 3, 1995 Order.
The Commission retains jurisdiction over the subject
matter and the parties for the purpose of entering such further
order or orders as it may deem necessary.
BY THE COMMISSION IT IS SO ORDERED.
Seltsam, Chr.; Alexander, Com.; McKee, Com.
Dated: December 8, 1995
[ORDER MAILED ]
[DEC 8 1995 ]
[JUDITH MCCONNELL |]
[EXECUTIVE DIRECTOR]
:
Judith McConnell
Executive Director
APPENDIX F
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS
Before Commissioners: Susan M. Seltsam, Chair
F. S. Jack Alexander
Timothy E. McKee
In the Matter of the Filing
of Kansas Pipeline Partnership for
approval and to make effective
certain firm gas purchase contracts
between Kansas Pipeline
Partnership and Western Resources,
Inc.
In the Matter of the Application of
Western Resources for an order
Kansas Pipeline Partnership, and
authorizing inclusion of costs related )
to such contract in Western )
Resources’ purchased gas adjustment )
clause for recovery from its customers.)
i ol ee ee a a
In the Matter of the Filing of Kansas
Pipeline for approval and to make
effective certain gas transportation
service agreements between Kansas
Pipeline Partnership and Western
Resources, Inc.
ORDER
Docket No.
192,506-U
Docket No.
192,391-U
Docket No.
192,507-U
ENTERED
DEC 28 1995
This matter is before the Kansas Corporation
Commission (KCC) on Kansas Pipeline Partnership's (KPP)
"Petition for Reconsideration of November 22, 1995 Order."
KPP appeared by James P. Zakoura, Richard W. Hird and Fred
J. Logan, Jr. The KCC notes that it has filed a petition for
rehearing before the Federal Energy Regulatory Commission
(FERC) in Docket Nos. RP95-212-000 and RP95-395-000
which is still pending. The resolution of these FERC dockets
will determine the jurisdictional issues regarding KPP. The
KCC recognizes that Western Resources, Inc., one of the Joint
Applicants, will remain Kansas jurisdictional notwithstanding
FERC's ruling. Western Resources, Inc. has not sought
reconsideration of the November 22, 1995 Order or responded
to KPP's petition for reconsideration. Accordingly, the
Commission finds no reason to alter its prior decision at this
time. The Order of November 22, 1995 is affirmed for the
reasons stated in that Order and the stay of the above-captioned
dockets will remain in place subject to further order or orders
of the KCC.
IT IS, THEREFORE, BY THE COMMISSION
ORDERED THAT: KPP's "Petition for Reconsideration of
November 22, 1995 Order" is denied. KPP has exhausted its
administrative remedies as to the November 22, 1995 Order.
The KCC retains jurisdiction over the subject matter
and the parties for the purpose of entering such further order or
orders as it may deem necessary.
BY THE COMMISSION IT IS SO ORDERED.
Seltsam, Chr.; Alexander, Com.; McKee, Com.
Dated: December 28, 1995
{ORDER MAILED ]
[DEC 28 1995 ]
[JUDITH MCCONNELL ]
[EXECUTIVE DIRECTOR]
Ls/
Judith McConnell
Executive Director
APPENDIX G
AMENDMENT XIV - CITIZENSHIP; PRIVILEGES AND
IMMUNITIES; DUE PROCESS; EQUAL PROTECTION;
APPORTIONMENT OF REPRESENTATION;
DISQUALIFICATION OF OFFICERS; PUBLIC DEBT;
ENFORCEMENT
Section 1. All persons born or naturalized in the United
States, and subject to the jurisdiction thereof, are citizens »f the
United States and of the state wherein they reside. No state
shall make or enforce any law which shall abridge the
privileges or immunities of citizens of the United States; nor
shall any state deprive any person of life, liberty, or property,
without due process of law; nor deny to any person within its
jurisdiction the equal protection of the laws.
Section 2. Representatives shall be apportioned among
the several states according to their respective numbers,
counting the whole number of persons in each state, excluding
Indians not taxed. But when the nght to vote at any election for
the choice of electors for President and Vice President of the
United States, Representatives in Congress, the executive and
judicial officers of a state, or the members of the legislature
thereof, is denied to any of the male inhabitants of such state,
being twenty-one years of age, and citizens of the United
States, or in any way abridged, except for participation in
rebellion, or other crime, the basis of representation therein
shall be reduced in the proportion which the number of such
male citizens shall bear to the whole number of male citizens
twenty-one years of age in such state.
Section 3. No person shall be a Senator or
Represeniative in Congress, or elector of President and Vice
President, or hold any office, civil or military, under the United
States, or under any state, who, having previously taken an
oath, as a member of Congress, or as an officer of the United
States, or as a member of any state legislature, or as aa
executive or judicial officer of any state, to support the
Constitution of the United States, shall have engaged in
insurrection or rebellion against the same, or given aid or
comfort to the enemies thereof. But Congress may by a vote of
two-thirds of each House, remove such disability.
Section 4. The validity of the public debt of the United
States, authorized by law, including debts incurred for payment
of pensions and bounties for services in suppressing
insurrection or rebellion, shall not be questioned. But neither
the United States nor any state shall assume or pay any debt or
obligation incurred in aid of insurrection or rebellion against
the United States, or any claim for the loss or emancipation of
any slave; but all such debts, obligations and claims shall be
held illegal and void.
Section 5. The Congress shall have power to enforce,
by appropriate legislation, the provisions of this article.
APPENDIX H
66-117. Change of rates or schedules; procedure;
effective date; higher rates of return in certain cases;
hearing; property tax surcharge authorized. (a) Unless the
state corporation commission otherwise orders, no common
carrier or public utility over which the commission has control
shall make effective any changed rate, joint rate, toll, charge or
classification or schedule of charges, or any rule or regulation
or practice pertaining to the service or rates of such public
utility or common carrier except by filing the same with the
commission at least 30 days prior to the proposed effective
date. The commission, for good cause, may allow such
changed rate, joint rate, toll, charge, charge or classification or
schedule of charges, or rule or regulation or practice pertaining
to the service or rates of any such public utility or common
carrier to become effective on less than 30 days’ notice. If the
commission allows a change to become effective on less than
30 days’ notice, the effective date of the allowed change shall
be the date established in the commission order approving such
change, or the date of the order if no effective date is otherwise
established. Any such proposed change shall be shown by
filing with the state corporation commission a schedule
showing the changes, and such changes shall be plainly
indicated by proper reference marks in amendments or
supplements to existing tariffs, schedules or classifications, or
in new issues thereof.
(b) | Whenever any common carrier or public utility
governed by the provisions of this act files with the state
corporation commission a schedule showing the changes
desired to be made and put in force by such public utility or
common carrier, the commission either upon complaint or upon
its own motion, may give notice and hold a hearing upon such
proposed changes, Pending such hearing, the commission may
suspend the operation of such schedule and defer the effective
date of such change in rate, joint rate, toll, charge or
classification or schedule of charges, or any rule or regulation
or practice pertaining to the service or rates of any such public
utility or common carrier by delivering to such public utility or
common carrier a statement in writing of its reasons for such
suspension. The commission shall not delay the effective date
of the proposed change in rate, joint rate, toll, charge or
classification or schedule of charges, or in any rule or
regulation or practice pertaining to the service or rates of any
such public utility or common carrier, more than 240 days
beyond the date the public utility or common carrier filed its
application requesting the proposed change. If the commission
does not suspend the proposed schedule within 30 days of the
date the same is filed by the public utility or common carner,
such proposed schedule shall be deemed approved by the
commission and shall take effect on the proposed effective
date. If the commission has not issued a final order on the
proposed change in any rate, joint rate, toll, che ge >
classification or schedule of charges, or any rule or regulon
or practice pertaining to the service or rates of any such public
utility or common carrier, within 240 days after the carrier or
utility files its application requesting the proposed change, then
the schedule shall be deemed approved by the commission and
the proposed change shall be effective immediately, except that
(1) for purposes of the foregoing provisions regarding the
period of time within which the commission shall act on an
application, any amendment to an application for a proposed
change in any rate, which increases the amount sought by the
public utility or common carrier or substantially alters the facts
used as a basis for such requested change of rate, shall, at the
option of the commission, be deemed a new application and the
240-day period shall begin again from the date of the filing of
the amendment, and (2) if hearings are in process before the
commission on a proposed change requested by the public
utility or common carrier on the last day of such 240-day
period, such period shall be extended to the end of such
2
inca
hearings plus 20 days to allow the commission to prepare and
issue its final order.
(c) Except as provided in subsection (b), no change
shall be made in any rate, toll, charge, classification or
schedule of charges or joint rates, or in any rule or regulation
Or practice pertaining to the service or rates of any such public
utility or common carrier, without the consent of the
commission. Within 30 days after such changes have been
authorized by the state corporation commission or become
effective as provided in- subsection (b), copies of all tariffs,
schedules and classifications, and all rules and regulations,
except those determined to be confidential under rules and
regulations adopted by the commission, shall be filed in every
station, office or depot of every such public utility and every
common carrier in this state, for public inspection.
(d) Upon a showing by a public utility before the
state corporation commission at a public hearing and a finding
by the commission that such utility has invested in projects or
systems that can be reasonably expected (1) to produce energy
from a renewable resource other than nuclear for the use of its
customers, (2) to cause the conservation of energy used by its
customers, or (3) to bring about the more efficient use of
energy by its customers, the commission may allow a return on
such investment equal to an increment of from 1/2% to 2% plus
an amount equal to the rate of return fixed for the utility's other
investment in property found by the commission to be used or
required to be used in its services to the public. The
commission may also allow such higher rate of return on
investments by a public utility in experimental projects, such
as load management devices, which it determines after public
hearing to be reasonable designed to cause more efficient
utilization of energy and in energy conservation programs or
3
measures which it determines after public hearing provides a
reduction in energy usage by its customers in a cost-effective
manner.
(e) | Whenever, after the effective date of this act, an
electric public utility, a natural gas public utility or a
combination thereof, files tariffs reflecting a surcharge on the
utility's bills for utility service designed to collect the annual
increase in expense charged on its books and records for ad
valorem taxes, such utility shall report annually to the state
corporation commission the changes in expense charged ad
valorem taxes. For purposes of this section, such amounts
charged to expense on the books and records of the utility may
be estimated once the total property tax payment is known. If
found necessary by the commission or the utility, the utility
shall file tariffs which reflect the change as a revision to the
surcharge. Upon a showing that the surcharge is applied to
bills in a reasonable manner and is calculated to substantially
collect the increase in ad valorem tax expense charged on the
books and records of the utility, or reduce any existing
surcharge based upon a decrease in ad valorem tax expense
incurred on the books and records of the utility, the
commission shall approve such tariffs within 30 days of the
filing. Any over or under collection of the actual ad valorem
tax increase charged to expense on the books of the utility shall
be either credited or collected through the surcharge in
subsequent periods. The establishment of a surcharge under
this section shall not be deemed to be a rate increase for
purposes of this act. The net effect of any surcharges
established under this section shall be included by the
commission in the establishment of base rates in any
subsequent rate case filed by the utility.
(f) Except as to the time limits prescribed in
subsection (b), proceedings under this section shall be
conducted in accordance with the provisions of the Kansas
administrative procedure act.
APPENDIX I
IN THE SUPREME COURT OF THE STATE OF KANSAS
KANSAS PIPELINE PARTNERSHIP,
Appellant,
vs.
THE STATE CORPORATION COMMISSION
OF THE STATE OF KANSAS,
Appellee.
PETITION FOR REVIEW
APPEAL OF INTERVENOR WILLIAMS NATURAL GAS
COMPANY FROM THE KANSAS COURT OF APPEALS
Kevin M. Fowler #11227
Frieden, Haynes & Forbes
400 SW 8th Street, P. O. Box 639
Topeka, Kansas 66601
(913) 232-7266
Counsel for Intervenor
Williams Natural Gas Company
PRAYER FOR REVIEW
Williams Natural Gas Company ("WNG") respectfully
prays that the Kansas Supreme Court review the decision of the
Kansas Court of Appeals in the case of Kansas Pipeline
Partnership v. State Corporation Commission, No. 96-75,918,
on the grounds that this case presents an important question of
constitutional law and there is a need for this Court to exercise
its supervisory authority pursuant to Kansas Supreme Court
Rule 8.03(e)(1). Additionally, the importance of the impact of
the Court of Appeals’ ruling on Kansas ratepayers clearly
merits this Court's review of the case. K.S.A. 20-3018(b)(1).
DATE OF COURT OF APPEALS’ DECISION
The Court of Appeals rendered its decision in this case
on May 17, 1996.
STATEMENT OF ISSUES FOR REVIEW
1. Whether a statute that allows gas transportation
and construction contracts to be "deemed approved” without a
consideration on the merits violates the United States
Constitution's Fourteenth Amendment.
2. Whether the Court of Appeals erred by ignoring
arguments raised by the parties in this proceeding, including
invited error, procedural estoppel, and the Court's failure to
properly apply K.AR. 82-1-214.
STATEMENT OF FACTS
This is an appeal from a decision by the Corporation
Commission of the State of Kansas ("KCC") in a docket filed
by Kansas Pipeline Partnership (“KPP") seeking approval of
five contracts (the "Contracts") with Western Resources, Inc.
a i ata nt alii P
("WRI"). The KCC held extensive hearings after exhaustive
discovery in which KPP, WNG, KCC Staff, CURB, and
various other parties were active participants. All parties
submitted briefs. Before the KCC could issue a final decision,
the Federal Energy Regulatory Commission ("FERC") ruled
that KPP is actually part of a single interstate pipeline system
subject to =— exclusive re under the Natural Gas
Riverside Pipeline Co. 73 FERC 1 61, 160 (1995), Upon
learning of FERC's jurisdiction, the KCC determined the new
jurisdictional status was, in effect, an amendment of the
application to approve the Contracts and, on that basis,
restarted the 240-day statutory decision period, if that period
even applied. The KCC stayed further action in the
consolidated dockets. KPP brought this appeal seeking a
determination that the Contracts are deemed approved because
the KCC failed to issue a final order within 240 days.
The Court of Appeals determined the 240-day time
limit on a final decision by the KCC contained in K.S.A. 66-
117(b) (the "Statute") applies to this matter. This Court should
review that determination because the Court of Appeals
interpreted the Statute incorrectly when it held that the Statute
applies to this application to approve contracts. Brief of WNG
at 6-9. The Court of Appeals’ Opinion ("Opinion") also
ignored several arguments raised by the parties. If those
arguments had been fully considered by the court, it should
have affirmed the KCC's action staying this matter pending a
final decision by FERC concerning its jurisdiction.
Furthermore, the Opinion ignores the provisions of K.A.R. 82-
1-214. Most important, K.S.A. 66-117(b), as applied by the
court, violates the Constitution's guarantee of due process of
law by effectively removing WNG's right to notice and an
opportunity to be heard on the merits. WNG filed a Motion for
2
Rehearing En Banc with the Court of Appeals on June 4, 1996.
WNG urges this Court to grant its Petition for Review and find
that the Contracts are not deemed approved by operation of
law.
ARGUMENT AND AUTHORITIES
The Court of Appeals made several errors that merit
this Court granting WNG’s Petition for Review and reversing
the Court of Appeals’ decision. In particular, the court's
application of the Statute deprived WNG’s nght to due process
under the Constitution. Additionally, the Court ignored
important arguments raised by WNG and other parties. Kansas
ratepayers will suffer substantial financial harm if this Court
does not review and reverse the Court of Appeals’ decision.
L THE COURT OF APPEALS’ APPLICATION OF THE
STATUTE VIOLATES CONSTITUTIONAL DUE
PROCESS.
Kansas Supreme Court Rule 8.03(e)(1) grants a party
Supreme Court review as a matter of right whenever a case
involves a constitutional issue. The Court of Appeals’
application of K.S.A. 66-117(b) violates the constitutional
rights of the parties to this proceeding. The court's
determination that the 240-day time period for rate cases
applies to the approval of these Contracts seriously negated
WNG's right to notice. Because the KCC did not require that
KPP give the notice and make the filings required for rate
cases, no party received the notice prong of procedural due
process to which they were entitled. Moreover, by determining
the Statute operates to remove WNG’s and other parties’ right
to a determination on the merits and by effectively cutting off
WNG's right to appeal the KCC's interim rulings, the court also
3
ROE NR PS ey
removed the parties’ opportunity to be heard. Because the
essence of procedural due process is notice and an opportunity
to be heard, the court's interpretation of K.S.A. 66-117(b)
rendered the Statute unconstitutional as applied. WNG is
entitled to a review of the Court of Appeals' Opinion because
that decision violates WNG’s constitutional rights. On review,
WNG urges this Court to find that the Contracts are not
deemed approved by operation of law.
a D p Reaui Noti
Opportunity to Be Heard.
The United States Constitution provides that the State
shall not "deprive any person of life, liberty, or property,
without due process of law... ." U.S. Const. amend. XIV.
The protection provided by the Due Process Clause requires, at
a minimum, "that deprivation of life, liberty, or property by
adjudication be preceded by notice and opportunity for hearing
appropriate to the nature of the case." Mullane v. Central
Hanover Bank & Trust Co,, 339 U.S. 306, 313 (1949). The
court's application of K.S.A. 66-117(b) prevented WNG from
receiving those protections.
B. WNG Was Entitled to Due Process.
1. WNG Had a Protectible Interest.
A complete Due Process Clause analysis presents two
inquiries for the Court: (1) was WNG deprived of a protected
interest and (2) if so, what process was due? Logan v.
Zimmerman Brush Co., 455 U.S. 422, 428 (1981). Asa
competitor of KPP, WNG had a protectible interest in
participating in this proceeding.
Kansas law provides WNG with the mght, as an
interested competitor of KPP, to intervene and participate in
KCC proceedings that affect WNG. K.AR. §§ 82-1-225, 82-1-
228 (1994). Because it is grounded in state law, this right is a
form of "property" right, to which due process protection must
be given. Logan, 455 U.S. at 430. WNG’s ownership of
substantial pipeline assets in Kansas, its employment of 300
Kansas citizens (R. Vol. 12, 1685-4 through 1685-5), and its
provision of gas transportation services vital to the citizens of
Kansas confirm that WNG has valuable property rights that
deserve the protection of the Due Process Clause.
The court's application of K.S.A. 66-117(b) denied
WNG the constitutional protection to which it is entitled. The
Contracts, if deemed approved, will take significant contract
demand from WNG and transfer it to KPP. R. Vol. 14, 2410-
14. Contract demand is the service WNG sells and the vehicle
by which it recovers its operating expenses and a reasonable
rate of return established by FERC. It is the only source of
earnings its significant pipeline assets generate. The approval
of the Contracts will give KPP control of more than 50% of the
gas transportation service market for Kansas City. Without
these unwise contracts, WNG will serve about 73% of that
market. R. Vol. 14, 2410-6 through 2410-7. WNG is entitled
to the due process protection provided for by the United States
Constitution in this case, which threatens WNG with a loss of
its valuable property rights.
3. WNG Should Have Been Provided
Notice and an Opportunity to Be Heard.
Because WNG had an established property right in the
proceedings, the Court must next determine what process was
required to protect that right. Generally, the Due Process
5
SPE OO a SS SN ES
Mies a
NA he TT IRE IRE IE) 26S i EDI a INE Peak he em She RS
idee Ri bed ore
Clause has been held to protect litigants who seek to protect
property or redress grievances in an adjudicative setting.
Logan, 455 U.S. at 429. Several United States Supreme Court
opinions provide due process analyses of cases analogous to
the one presented to this Court.
In Societe Internationale v. Rogers, 357 U.S. 197
(1958), the Court determined that a party's case should not be
dismissed based upon non-compliance with procedural rules.
In particular, the Court noted the Due Process Clause limits the
power of courts "to dismiss an action without affording a party
the opportunity for a hearing on the merits of his cause." Id.
at 209. In Rogers, the Court found a due process violation
when the plaintiffs case was dismissed because of the
plaintiff's good-faith failure to comply with a court order. In
this case WNG did not take any action that led to its loss of
protection. Instead, the action that led to the deprivation of
WNG's rights was taken by a third party — the KCC.
Nonetheless, the Court of Appeals’ interpretation of K.S.A.
66-117(b) resulted in a complete loss of WNG’s right to a
decision on the merits based entirely on the inaction of the
KCC. The loss of WNG’s due process protection thus resulted
from no fault of WNG whatsoever. Compared to the plaintiff
in Rogers, WNG has an even stronger argument that it is
entitled to a hearing to protect its interests.
Logan v. Zimmerman Bmush Co., 455 U.S. 422 (1981)
presents an even more compelling in*»rpretation of the Due
Process Clause. There the Court determined the dismissal of
an employment claim because an agency neglected to act
within a statutory time requirement violated the Due Process
Clause. The statute in Logan was similar to K.S.A. 66-117(b).
It required an agency to hold a hearing within 120 days of the
filing of a complaint. Jd, at 424. When the agency
6
inadvertently set the hearing date for five days after the
statutory period, the claim was challenged by the employer and
eventually dismissed. Id, at 426-27. In reversing that
determination, the Supreme Court noted that once a state
confers a property right like the right to a hearing, any statutory
limitation on the right will be subjected to constitutional
scrutiny. Id, at 432. "[T]he State may not finally destroy a
property interest without first giving the putative owner an
opportunity to present his claim of entitlement.” Id, at 434.
WNG's situation is clearly analogous. The Court of
Appeals’ application of the Statute operated to bar WNG's
participation in a determination on the merits in the same
manner that Logan's rights were barred. Like the agency in
Logan, the KCC failed to follow the State's procedural
guidelines. As in Logan, WNG was not at fault. In fact, WNG
was powerless to stop the Statute's application. To deny
WNG's rights under such circumstances is patently unfair and
clearly violates the Due Process Clause.
A property owner's rights “are not diminished by the
fact that the State may have specified its own procedures that
it may deem adequate for determining the preconditions to
adverse official action." Vitek v. Jones, 445 U.S. 480, 491
(1980). Unfortunately, WNG’s rights were diminished by the
court's application of K.S.A. 66-117(b). Because such
application removed WNG's due process protection, this Court
should grant this Petition and reverse the Court of Appeals.
The court's decision also had the effect of removing
hpi as omar 2.08 AS See
Kan. App. 2d 93, 819 P.2d 138 (1992). WNG filed a motion
with the KCC seeking dismissal of the applications for failure
7
EBT Te NI BP te SOR IS EIU MS TORTS IRS TER AERC
to give the notice required by a rate case and make the filings
required in a rate case. R. Vol. 1, 304. At KPP's insistence,
the KCC denied WNG’s motion and declined to force KPP to
give notice and make filings required in a rate case. That
decision necessarily included a determination that this
proceeding was not a rate case. The requirements for filings
and proper notice apply in a rate case because the KCC must
make a prompt decision. In other cases there is no artificial
time limit and therefor no similar need for heightened
procedural notice. The court's determination that the Contracts
are deemed approved by operation of law turned this case on its
head by applying the strict, punitive time limits of the Statute
in a case where none of the notice and procedural safeguards
applied to rate cases have been enforced. The combination of
the KCC's failure to require the notice and filings associated
with a rate case and the court's application of the 240-day time
limit had the effect of denying WNG and other parties the
notice to which they are entitled by the most fundamental
concepts of due process.
The KCC's ruling on WNG's motion seeking dismissal
of the Applications leads to another important consideration in
this case. WNG's exception to the KCC's ruling on WNG's
motion remains preserved for consideration on appeal of the
KCC's final ruling in this docket. The court's ruling that the
Contracts are deemed approved by operation of law removed
WNG's right to appeal the KCC's ruling on WNG's motion
because it eliminated a final order and the right of WNG to
appeal from such an order. If WNG had been permitted a right
to appeal the KCC's denial of its motion, WNG would have had
an opportunity to reverse an approval of the Contracts even if
that decision were based on the merits of the Contracts. The
court's elimination of WNG’s right to an appeal on this critical
issue amounted to a further denial of WNG's due process
protection.
Tl. THIS APPEAL PRESENTS IMPORTANT ISSUES
THAT MERIT SUPREME COURT REVIEW.
Even if WNG is not entitled to a review as a matter of
right, this Court should grant WNG's Petition because of the
important issues involved. The Court of Appeals’ decision in
this case will have an impact that affects a significant portion
of the Kansas population. If the Contracts remain "deemed
approved," Kansas ratepayers could eventually pay for the
Contracts’ costs through WRI's gas rates. Additionally, this is
a case of first impression. As the Court of Appeals’ Opinion
recognized, no published decision has ever determined the time
limits in K.S.A. 66-117 apply to utility contracts. These two
factors clearly merit this Court's review. K.S.A. 20-3018(b){1).
On June 10, 1996, WRI filed a response to KCC's
Motion for Rehearing in the Court of Appeals. In that
response, WRI attempts to “piggyback” the Court of Appeals’
approval of the Contracts into a method by which WRI can
pass the Contracts’ costs along to Kansas ratepayers. As WNG,
CURB, KCC Staff, and others set forth at length at the hearing
in this matter, the Contracts are unwise and significantly over-
priced. Based on the compelling showing on the merits, the
KCC would not have approved the Contracts or WRI's
application for pass-through of the costs. Had the KCC
approved the Contracts on the merits, its decision would have
been reversed on appeal. Thus, in this appeal, WRI and KPP
are attempting to accomplish by the KCC's omission an end
which they could not accomplish by the KCC's volition. This
Court should not permit such a result in a matter of such great
public importance. Clearly, based upon the magnitude of the
9
costs to be paid by Kansas ratepayers, this appeal presents
issues of great importance to the Kansas public. ;
Quite apart from the threat of millions of dollars of
unnecessary utility bills, this appeal raises issues of first
impression for this Court. The Court of Appeals applied
K.S.A. 66-117 to the Contracts. As the Court's Opinion noted,
no previous decision has held contracts to fall within the scope
of the statute. Because this appeal presents matters of first
impression that will likely arise again, the Court should grant
WNG’s Petition and review and reverse the Court of Appeals’
decision.
IV. CONCLUSION.
This Court should grant WNG’s Petition for Review and
find that the Contracts are not deemed approved by operation
of law. This is a case of first impression which considers
issues of significant importance to the citizens of Kansas.
Moreover, the Court of Appeals’ decision renders K.S.A. 66-
117 unconstitutional as applied. The court's ruling effectively
deprived WNG of its constitutional night to notice and an
opportunity to be heard and must therefor be reversed. The
Court of Appeals’ Opinion in this case also ignored important
arguments and the facts supporting the conclusion that KPP is
estopped from arguing the 240-day time limit included in
K.S.A. 66-117(b) should apply in this case. The Court of
Appeals incorrectly interpreted K.S.A. 66-17(b) and that
interpretation should be reversed on review.
Respectfully submitted,
ls/_
John C. Frieden #06592
Kevin M. Fowler #11227
Frieden, Haynes & Forbes
400 SW 8th Street, P. O. Box 639
Topeka, Kansas 66601
(913) 232-7266
David P. Batow, General Counsel
Gary W. Boyle, Senior Attorney
Jay V. Allen, Attorney
Williams Natural Gas Company
4100 One Williams Center
Tulsa, Oklahoma 74172
(918) 588-2359
Counsel for Intervenor
Williams Natural Gas Company
1]
APPENDIX J
beta eerlliatintn et
IN THE COURT OF APPEALS OF THE STATE OF
KANSAS
KANSAS PIPELINE PARTNERSHIP, )
)
Petitioner/Appellee, )
)
v. )
) Case No.
) 96-75918-A
)
THE STATE CORPORATION )
COMMISSION OF THE STATE )
OF KANSAS, )
)
MOTION FOR REHEARING EN BANC
COMES NOW Intervenor, Williams Natural Gas
Company ("WNG"), and pursuant to Supreme Court Rules
7.02(b) and 7.05, files this motion seeking rehearing en banc of
the ruling of the Court of Appeals determining that Appellees’
contracts were approved as a matter of law. The Opinion of the
Court, dated May 17, 1996, is attached hereto. WNG
respectfully requests the Court reconsider this decision.
ARGUMENT
L BACKGROUND.
This is an appeal from a decision by the Corporation
Commission of the State of Kansas ("KCC") in a docket filed
by Kansas Pipeline Partnership ("“KPP") seeking approval of
five contracts (the "Contracts”) with Western Resources, Inc.
("WRI"). The KCC held extensive hearings after exhaustive
discovery in which KPP, WNG, KCC Staff, CURB, and
submitted briefs. Before the KCC could issue a final decision,
the Federal Energy Regulatory Commission ("FERC") ruled
that KPP is actually part of a single interstate pipeline system
Ee ae ee ee ee
Riverside Pipeline Co. 73 FERC { 61, 160 (1995), Upon
learning of FERC's jurisdiction, the KCC determined the new
jurisdictional status was, in effect, an amendment of the
application to approve the Contracts and, on that basis,
restarted the 240-day statutory decision period, if that period
even applied to this matter. The KCC stayed further action in
the consolidated dockets. KPP brought this appeal seeking a
determination that the Contracts are deemed approved because
the KCC failed to issue a final order within 240 days.
This Court determined the 240-day time limit contained
in K.S.A. 66-117(b) (the "Statute") applies to this matter and
the change in KPP’s jurisdictional status was not an amendment
of the application. WNG seeks rehearing in this Court because
the Court's Opinion ignores several arguments raised by the
parties. If those arguments had been fully considered by the
Court, it should have affirmed the KCC's action staying this
matter until the conclusion of the restarted 240-day decision
period or a final decision by FERC concerning its jurisdiction.
Furthermore, the Court's Opinion ignores the provisions of
K.AR. 82-1-214. Most important, K.S.A 66-117(b), as
applied by this Court, violates the Constitution's guarantee of
due process of law by effectively removing WNG’s and other
parties’ notice and opportunity to be heard on the merits. WNG
urges the Court to grant its Motion for Rehearing and find that
the Contracts are not deemed approved by operation of law.
2
IV. THECOURT'S APPLICATION OF THE STATUTE
VIOLATES CONSTITUTIONAL DUE PROCESS.
The Court's application of K.S.A. 66-117(b) violates the
constitutional rights of the parties to this proceeding. This
Court's determination that the 240-day time period for rate
cases applies to the approval of these Contracts seriously
negates WNG’s right to notice. Because the KCC did not
require that KPP give the notice and make the filings required
for rate cases, no party has received the notice prong of
procedural due process to which they were entitled. Moreover,
by determining that the Statute operates to remove WNG’s and
other parties’ right to a determination on the merits of the
reasonableness and public interest invoked by the proposed
Contracts and by effectively cutting off WNG’s right to appeal
the KCC's interim rulings, the Court has also removed the
parties’ opportunity to be heard. Because the essence of
procedural due process is notice and an opportunity to be
heard, this Court's interpretation of K.S.A. 66-117(b) renders
the Statute unconstitutional as applied. WNG urges the Court
to reconsider its decision in light of the constitutional rights of
the parties and to find that the Contracts are not deemed
approved by operation of law.
A b p Reaui Noti
Opportunity to Be Heard.
The United States Constitution provides that the State
shall not “deprive any person of life, liberty, or property,
without due process of law... ." U.S. Const. amend. XIV.
The protection provided by the Due Process Clause requires, at
2 minimum, “that deprivation of life, liberty, or property by
3
adjudication be preceded by notice and opportunity for hearing
appropriate to the nature of the case." Mullane v, Central
Hanover Bank & Trust Co., 339 U.S. 306, 313 (1949). This
Court's application of K.S.A. 66-117(b) prevents WNG from
receiving those protections.
B. WNG Was Entitled to Due Process.
l. WNG Had a Protectible Interest.
A complete Due Process Clause analysis presents two
inquiries for the Court: (1) was WNG deprived of a protected
interest and (2) if so, what process was due? Logan v.
Zimmerman Brush Co,, 455 U.S. 422, 428 (1981). Asa
competitor of KPP, WNG had a protectible interest in
participating in thie fing
Kansas law provides WNG with the right, as an
interested competitor of KPP, to intervene and participate in
KCC proceedings that affect WNG. K._AR. §§ 82-1-225, 82-1-
228 (1994). Because it is grounded in state law, this right is a
form of “property” right, to which due process protection must
be given. Logan, 455 U.S. at 430. WNG's ownership of
substantial pipeline assets in Kansas, its employment of 300
Kansas citizens (R. Vol. 12, 1685-4 through 1685-5) and its
provision of gas transportation services vital to the citizens of
Kansas confirm that WNG has valuable property rights that
deserve the protection of the Due Process Clause.
This Court's application of K.S.A. 66-117(b) has denied
WNG the constitutional protection to which it is entitled. The
Contracts that are the subject of this proceeding, if deemed
approved, will take significant contract demand from WNG
and transfer it to KPP. R. Vol. 14, 2410-14. Contract demand
4
is the service WNG sells and the vehicle by which it recovers
its operating expenses and a reasonable rate of return
established by FERC. It is the only source of earnings that the
significant pipeline assets it owns can generate. The approval
of the Contracts will give KPP control of more than 50% of the
gas transportation service market for Kansas City. Without
these unwise contracts, WNG will serve about 73% of that
market. R. Vol. 14, 2410-6 through 2410-7. WNG is entitled
to the due process protection provided for by the United States
Constitution in this case, which threatens WNG with a loss of
its valuable property rights.
2. WNG Should Have Been Provided
Notice and an Opportunity to Be Heard.
Because WNG had an established property right in the
proceedings, the Court must next determine what process was
required to protect WNG's rights. Generally, the Due Process
Clause has been held to protect litigants who seek to protect
property or redress grievances in an adjudicative setting.
Logan, 455 U.S. at 429. Several United States Supreme Court
opinions provide due process analyses of cases analogous to
the one presented to this Court.
In Societe Internationale v. Rogers, 357 U.S. 197
(1958), the Court determined that a party's case should not be
dismissed based upon non-compliance with procedural rules.
In particular, the Court noted that the Due Process Clause
limits the power of courts "to dismiss an action without
affording a party the opportunity for a hearing on the merits of
his cause." Jd. at 209. In Rogers, the Court found a due
process violation when the plaintiffs case was dismissed
because of the plaintiffs good-faith failure to comply with a
court order. In this case WNG did not take any action that led
5
deprivation of WNG's rights was taken by a third party -- the
KCC. Nonetheless, this Court's interpretation of K.S.A. 66-
117(b) results in a complete loss of WNG's right to a decision
on the merits based entirely on the inaction of the KCC. The
loss of WNG's due process protection thus resulted from no
fault of WNG whatsoever. Compared to the plaintiff in
Rogers, WNG has an even stronger argument that it is entitled
to a hearing to protect its interests.
Logan v. Zimmerman Brush Co., 455 U.S. 422 (1981)
presents an even more compelling interpretation of the Due
of an employment claim because an agency neglected to act
inadvertently set the hearing date for five days after the
statutory period, claim was challenged by the employer and
eventually dismissed. Id. at 426-27. In reversing that
determination, the Supreme Court noted that once a state
confers a property right like the right to a hearing, any statutory
limitation on the right will be subjected to constitutional
scrutiny. Id, at 432. "(T]he State may not finally destroy a
property interest without first giving the putative owner an
opportunity to present his claim of entitlement." Id. at 434.
WNG's situation is clearly analogous. The Statute
operated to bar WNG's participation in a determination on the
merits in the same manner that Logan's rights were barred.
Like the agency in Logan, the KCC failed to follow the State's
procedural guidelines. As in Logan, WNG was not at fault. In
fact, WNG was powerless to stop the Statute's application. To
6
LO ON eT RE et
deny WNG’s rights under such circumstances is patently unfair
and clearly violates the Due Process Clause.
A property owner's rights "are not diminished by the
fact that the State may have specified its own procedures that
it may deem adequate for determining the preconditions to
adverse official action." Vitek v. Jones, 445 U.S. 480, 491
(1980). Unfortunately, WNG's rights were diminished by this
Court's application of K.S.A. 66-117(b). Because such
application removed WNG's due process protection, the Court
should grant WNG's Motion for Rehearing.
This Court's decision also has the effect of removing
wore right to notice inherent i in its due process <4 See
Kan. App.2d 93, 819 P-2d 138 (1992) The Court will recall
that WNG filed a Motion with the KCC seeking dismissal of
the applications for failure to give the notice required by a rate
case and make the filings required in a rate case. R. Vol. 1,
304. At KPP's insistence, the KCC denied WNG's motion and
declined to force KPP to give notice and make filings required
in a rate case. That decision necessarily included a
determination that this proceeding was not a rate case. The
requirements for filings and proper notice apply in a rate case
because the KCC must make a prompt decision. In other cases
there is no artificial time limit and therefor no similar need for
heightened procedural notice. This Court's determination that
the Contracts are deemed approved by operation of law has
turned this case on its head by applying the strict, punitive time
limits of the Statute in a case where none of the notice and
procedural safeguards applied to rate cases have been enforced.
The combination of the KCC's failure to require the notice and
filings associated with a rate case and this Court's application
of the 240-day time limit have the effect of denying WNG and
4
other parties the notice to which they are entitled by the most
fundamental concepts of due process.
The KCC's ruling on WNG's motion seeking dismissal
of the Applications leads to another important consideration on
rehearing in this case. WNG's exception to the KCC's ruling
on WNG's motion remains preserved for consideration on
appeal of the KCC's final ruling in this docket. This Court's
ruling that the Contracts are deemed approved by operation of
law removes WNG's right to appeal the KCC's ruling on
WNG's motion because it eliminates a final order and the right
of WNG to appeal from such an order. If WNG had been
permitted a right to appeal the KCC's denial of its motion,
WNG would have had an opportunity to reverse an approval of
the Contracts even if that decision was based on the merits of
the Contracts. This Court's elimination of WNG's right to an
appeal on this critical issue amounts to a further denial of
WNG's due process protection.
V. CONCLUSION.
This Court should grant WNG's Motion for Rehearing
En Banc and, after rehearing, find that the Contracts are not
deemed approved by operation of law. The Court's Opinion in
this case ignored important arguments and the facts that
support the conclusion that KPP is estopped from arguing the
240-day time limit included in K.S.A. 66-117(b) should apply
in this case. Most important, this Court has applied the Statute
in a manner that violates the Due Process Clause of the United
States Constitution. This Court's ruling effectively deprives
WNG of its constitutional right to notice and an opportunity to
be heard and must therefor be reversed.
Respectfully submitted,
ls/
John C. Frieden #06592
Kevin M. Fowler #11227
Frieden, Haynes & Forbes
400 SW 8th Street, P.O. Box 639
Topeka, Kansas 66601
(913) 232-7266
David P. Batow, General Counsel
Gary W. Boyle, Senior Attorney
Jay V. Allen, Attorney
Williams Natural Gas Company
4100 One Williams Center
Tulsa, Oklahoma 74172
(918) 588-2359
Counsel for Intervenor
Williams Natural Gas Company
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.