Petition for Writ of Certiorari — Alexandria Historical Restoration & Preservation Commission v. Federal Highway Administration
Supreme Court brief2000
Ask Donna
What actually matters in this document.
Text
Supremé Court, U.S.
FILED
991947 JUNO 5 200
OFFICE OF THE CLERK
No.
IN THE
Supreme Court of the United States
ALEXANDRIA HISTORICAL RESTORATION AND
PRESERVATION COMMISSION, ET AL.,
Petitioners,
Vv.
FEDERAL HIGHWAY ADMINISTRATION, ET AL.,
Respondents.
ON PETITION FOR A WRIT OF CERTIORARI TO THE UNITED
STATES COURT OF APPEALS FOR THE DISTRICT OF
COLUMBIA CIRCUIT
PETITION FOR WRIT OF CERTIORARI
S. William Livingston*
Mitchell F. Dolin
Thomas L. Cubbage III
COVINGTON & BURLING
_ 1201 Pennsylvania Ave., NW
Washington, DC 20004-2401
(202) 662-6000
Attorneys for Petitioners
* Counsel of Record
QUESTION PRESENTED
In preparing the Environmental Impact Statement
required by the National Environmental Policy Act
(“NEPA”) for a multi-billion dollar highway and bridge
project through a landmark historic district, the
Department of Transportation analyzed only alternatives
with twelve lanes, disregarding ten-lane alternatives that
would accomplish the principal aims of the agency, but
would accommodate marginally less traffic than that
projected for peak hours during the year 2020.
The question presented is:
Whether the court of appeals erred in holding,
contrary to other circuit courts, that a federal agency may
narrow the range of alternatives for a project that is
analyzed under NEPA by excluding from consideration an
alternative that does not fully satisfy a narrowly defined
non-environmental objective, but that would substantially
achieve the general goals of the project with less adverse
environmental impact.
PARTIES TO THE PROCEEDING AND RULE 29.6
STATEMENT
The petitioners are the Alexandria Historical
Restoration and Preservation Commission, the Historic
Alexandria Foundation, and the Coalition for a Sensible
Bridge, Inc. The Coalition for a Sensible Bridge, Inc., is a
not-for-profit corporation that has no parent corporation or
publicly held securities.
The respondents in this case are the Federal
Highway Administration, Kenneth Wykle, Administrator
of the Federal Highway Administration, and Rodney E.
Slater, Secretary of Transportation.
TABLE OF CONTENTS
Page
Pee RI II ID os cnnicisssissssctacscasasecorsesensnnincves i
PARTIES TO THE PROCEEDING AND RULE
PE AR IEE ibicijecinis nd ticvectssdieestitetiinncasnssnsornsozseovns ii
ERI GMT MT EG cassincssnssvcsacsessacrnccarsesesensnsocenscet iii
TABRLES OR AUTHORITIES. oon. secaccscccssssecsasscesesoseseseseseses Vv
I cpamiuicncs ]
tcc 2 ERLE NE RODE ATT 1
STATUTORY AND REGULATORY
PROVISIONS NIU tad ictbadissccdscdcisbcssacesnssansecesoun 1
STATEMENT OF THE CASE. ............cccecscscscccssesescscsoees ]
REASONS FOR GRANTING THE WRIT..............0.0.0-. 7
I. The Court Of Appeals’ Ruling Conflicts With ?
The Decisions Of Other Circuits ....0.........c.ccccscceceseseee 8
II. The Court Of Appeals’ Ruling Undermines
NEPA By Endorsing A Method By Which
Agencies Can Avoid Meaningful Compliance
SEI RCE Ce Sa nen 14
I hah tecicciinictckesaciailccisiiiasthibiicincdssendsicsitsns 16
Appendix A (Court of Appeals Opinion)....................... la
Appendix B (Denial of Rehearing) ................ccccceseses0-. 25a
Appendix C (Denial of Rehearing En Banc)............... 26a
\
Appendix D (District Court Opinion)....................:2++ 27a
Appendix E (Statutory and Regulatory Provisions).....54a
iv
TABLE OF AUTHORITIES
Page
Cases
Citizens Against Burlington, Inc. v. Busey,
See ae BO Cs GE BIE DP vivesicsscnenesenciccnecensaice 13, 15
City of Bridgetown v. FAA, _F.3d___,
2000 WL 355521 (8th Cir. Apr. 7, 2000)............ 9, 10, 14
Natural Resources Defense Council, Inc. v.
Morton, 458 F.2d 827 (D.C. Cir. 1972) .u.......cccsssssceseeees 14
North Buckhead Civic Association v. Skinner,
903 F.2d 1533 (Lith Cir. 1990).............ceceeeee 10, 12, 13
Simmons v. United States Army Corps of
Engineers, 120 F.3d 664 (7th Cir. 1997) ................... 9,11
Van Abbema v. Fornell, .
OPT P26 GIS CIM Ce, TOBE nn sceciecneevnceccnecsvess 9, 13, 15
Statutes and Regulations
Ns ON 5
ae HI iid iis tieeeesctsosenpiniinddationpeecizsedconsssannaisans 1
A Ain I API II Fins cncicscinis siennihactnnnnhisatsioonsoeesanacon 7,8
QE UA. © TOAD oscsiocstisececrisocsnctoascascennsecieeseoce wed
see il ence Lice ht ELS RE OS OS MEA IR OE 5
BP NON Ms GIA screech EIS SS 6
og Ee eat) Me REORRE SERRA Ta SR ge ete eRe 6
OME Mas © EMO earivecscscsstssb scsthneiss Bees. incchcswchbectis 8
Other Authority
Michael E. Lackey, Jr., Misdirecting NEPA:
Leaving the Definition of Reasonable Alternatives
in the EIS to the Applicants,
60 GEO. WASH. L. REV. 1232 (1992) ...............:se000 13, 15
OPINIONS BELOW
The opinion of the court of appeals, Appendix
(“App.”) 1a-24a, is reported at 198 F.3d 862. The orders
of the court of appeals denying rehearing and rehearing en
banc, App. 25a-26a, are unreported. The opinion of the
district court, App. 27a-53a, is reported at 46 F. Supp. 2d
35S,
JURISDICTION
The judgment of the court of appeals was entered
on December 17, 1999. App. la. A petition for rehearing
was denied on March 7, 2000. App. 25a. The jurisdiction
of this Court is invoked under 28 U.S.C. § 1254.
STATUTORY AND REGULATORY PROVISIONS
INVOLVED
Provisions of the National Environmental Policy
Act and the regulations implementing the Act are
reproduced, in relevant part, at App. 54a-56a.
STATEMENT OF THE CASE
The Woodrow Wilson Memorial Bridge provides
the southern Potomac River crossing for the Capital
Beltway. The Bridge and Beltway pass through
Alexandria, Virginia, a densely populated and historically
Significant city whose eastern border is the Potomac River.
The Bridge, built in 1961, currently has six lanes,
creating a bottleneck on the eight-lane Beltway. App. 2a.
In addition, traffic across the Bridge exceeds the capacity
for which it was designed. According to 1997 Department
of Transportation (“DOT”) estimates, usage of the Bridge
is expected to be around 275,000 vehicles per day in 2020,
]
a
with a maximum of 300,000 vehicles per day. App. 28a,
44a. In November 1997, DOT approved a highway/bridge
project that would replace the current six-lane Bridge with
two side-by-side, six-lane bridges and would expand four
nearby interchanges on the Beltway with new ramps and
flyovers to separate traffic into local and through traffic
lanes on the bridges and their approaches. App. 28a.
Although the Beltway has only eight lanes, DOT
focused from the outset of its planning on replacing the
Bridge with a crossing of twelve lanes, including two for
high-occupancy vehicles (“HOV”). In 1991, DOT issued a
draft Environmental Impact Statement (“EIS”), comparing
five “build” proposals for replacing the Bridge. Each of
the alternatives in the draft proposed doubling the size of
the river crossing from six to twelve lanes, and included a
similar expansion along a five-mile corridor of the
Beltway on each side of the river. App. 2a-3a, 29-300.
As the court of appeals put it, “[rJeaction to the
draft was less than enthusiastic; the Administration was
criticized for assessing inadequately the environmental and
cultural impacts of its proposal, and for failing to
coordinate its work with that of interested governmental
agencies and community groups.” App. 3a. As a result,
DOT purportedly “went back to the drawing board.” Jd.
A second draft EIS was published in January 1996.
The 1996 draft described six “build” alternatives; once
again, all of the alternatives had twelve lanes. The only
significant differences among the alternatives were the
form (i.e. drawbridge, suspension bridge, or tunnel) and
location of the river crossing (i.e., at the site of the current
Bridge or one-half mile south). App. 31a.
Also in 1996, DOT asked the local Transportation
Planning Board to determine whether the anticipated
2
project would conform to the requirements or the Clean
Air Act, which forbids federal approval of projects that
would prevent or delay a region’s compliance with federal
air quality standards. See 42 U.S.C. § 7506(c\(1)(B).
DOT requested a “conformity analysis” for a new bridge
built with space for twelve lanes, but for which only ten
lanes would be opened for use until some indefinite future
date. The Board determined that a ten-lane bridge would
conform, but no conformity analysis was then done for a
twelve-lane bridge. App. 31a-32a.
DOT issued its Final EIS in September 1997. The
Final EIS gave detailed consideration to eight alternative
proposals (seven “build” alternatives and a “no build”
alternative), comparing them on a range of criteria
including capacity, cost, and environmental impacts. Like
both of the prior draft EISs, every “build” alternative
scrutinized in the Final EIS had twelve lanes (including
HOV lanes), as well as a configuration that separated local
and express traffic. The only material difference among
the proposed alternatives was the type of river crossing;
the “build” alternatives included a range of tunnel and
bridge types. App. 4a. Although the Final EIS briefly
mentioned eight- and ten-lane options, it did not afford
them full treatment as formal “alternatives” because DOT
concluded that narrower river crossings would fall short of
meeting DOT’s projections of the Bridge’s traffic needs in
2020. Id. No alternative with fewer than twelve lanes was
subjected to a detailed environmental impact analysis in
the Final EIS.
scantined ese erat 2 dim iaae > SIOV ction was
considered “in stages o study ... [but] was dropped at
that time ... because it was insufficient from a functional, safety
ae ea standpoint.” App. 32a. That conclusion follows
3
4
;
j
In November 1997, DOT issued its Record of
Decision approving the Preferred Alternative identified in
the Final EIS: a highway project that calls for replacing
the Bridge with two paral!el drawbridges, each with space
for six lanes (including one lane for HOV traffic). App.
28a. The two six-lane bridges would more than double the
width of the existing Bridge and would rise an additional
twenty feet above the River. Jd. The approved project
also entails reconstructing a five-mile stretch of the
Beltway to accommodate twelve lanes, notwithstanding
the eight-lane width of most of the Beltway. In particular,
the approved project authorizes substantial redesign and
reconstruction of the four interchanges closest to the
crossing (two on either side of the River) to separate local
and express traffic into the twelve-lane configuration. Jd.
The City of Alexandria filed suit in early 1998 to
challenge the Record of Decision on grounds that it
violated the National Environmental Policy Act
(“NEPA”), the Clean Air Act, the National Historic
Preservation Act, and the Department of Transportation
Act. Three interested organizations—the petitioners
here—intervened as plaintiffs. After both sides filed
motions for summary judgment, the City and DOT reached
a settlement agreement, leaving petitioners as the sole
plaintiffs. App. 5a.
ease if not exclusively, from the supposedly reduced rush-
our capacity of a ten-lane, no-HOV crossing com to a
twelve-lane crossing with HOV lanes. DOT’s own analysis
showed, however, that a ten-lane crossing could handle up to
295,000 vehicles per day, or 98 percent of DOT’s 1997 estimate of
the maximum daily vehicular usage in 2020. App. 44a.
(Moreover, DOT later decreased its estimate of maximum in
2020 to 295,000 vehicles per day. See Final Supplemental EIS, at
p. 4-4 (Apr. 14, 2000).)
The district court entered summary judgment for
petitioners. App. 27a-53a. The district court ruled that
DOT violated NEPA in two respects. First, the court
determined that DOT failed to provide a detailed analysis
in the EIS for all reasonable alternatives for the project,
including specifically a ten-lane river crossing. The court
noted that the Final EIS’s statement of the purpose and
need of the project “hardly provides an unequivocal basis
for eliminating ten-lane alternatives from consideration,”
that a ten-lane structure could accommodate up to 98
percent of the estimated maximum demand in 2020, and
that DOT itself had characterized the project as a ten-lane
river crossing for Clean Air Act compliance purposes.
App. 44a-45a. Second, the court ruled that the Final EIS
inadequately discussed the environmental impacts of
construction activities, providing a discussion “of such a
broad and generic nature that-it could apply to practically
any construction project undertaken by” DOT. App. 46a.
The court also ruled that DOT violated the Clean Air Act
by approving construction of a twelve-lane structure after
performing a “conformity analysis” for only a ten-lane
bridge. App. 38a. Finally, the court ruled that DOT
violated Section 106 of the National Historic Preservation
Act, 16 U.S.C. § 470f, and Section 4(f) of the Department
of Transportation Act, 49 U.S.C. § 303, by failing to
complete the process of identifying all historic sites, parks,
and other protected resources that might be affected by all
aspects of the project before issuing the Record of
Decision. App. 50a.
The court of appeals reversed on all issues other
than those concerning the Clean Air Act, which DOT did
not appeal. App. la-24a. With respect to NEPA’s
requirement that an EIS must consider all reasonable
alternatives, the court held that it was not improper for
DOT to exclude any alternative smaller than twelve lanes
5
from consideration in the Final EIS. According to the
court of appeals, DOT defined the project’s objective as
satisfying expected peak hours traffic demand at the
crossing site in 2020, and thus a ten-lane alternative could
be excluded because of its inability to satisfy fully DOT’s
forecasted peak-hour needs in 2020. Apn. 1la-13a. The
court also stated that DOT’s decision to analyze only ten-
lane structures for Clean Air Act purposes did not
undermine this conclusion, because NEPA and Clear Air
Act analyses “have different time horizons.” App. 14a;
but see 23 C.F.R. § 450.322(a); 40 C.F.R. § 93.118(b)
(requiring Clean Air Act conformity findings to be made
for a 20-year horizon).
REASONS FOR GRANTING THE WRIT
This case presents fundamental questions
concerning the procedural constraints imposed on federal
agencies by the National Environmental Policy Act. The
court of appeals’ decision conflicts with decisions of other
courts of appeals in applying NEPA and undermines the
express purposes of the Act by permitting a federal agency
to limit the range of alternatives analyzed under NEPA to |
only those alternatives that fully satisfy an unreasonably
narrow definition of the functional purpose of the project
at issue.
Aside from exacerbating a circuit court split
concerning a vital statute that applies to all “major Federal
actions,” 42 U.S.C. § 4332(2)(C) (App. 54a), the result
reached below is of considerable importance because in
this case it would allow DOT to proceed immediately with
a currently-estimated $2.5 billion construction project
through the National Register “Old and Historic District”
of Alexandria, Virginia, including the area commonly
known as Old Town. Alexandria is “one of America’s
most historic cities.” App. 29a. It contains an
extraordinary collection of historic resources, including a
National Register Historic District, a National Historic
Landmark District, three individual National Historic
Landmarks, and many properties listed or eligible for
listing on the National Register of Historic Places. Jd.
Alexandria’s historic sites and other environmental
resources will be adversely affected by the project
approved by DOT, which concededly has not taken a “hard
look” at any smaller alternative to the approved project.
I. THE COURT OF APPEALS’ RULING
CONFLICTS WITH THE DECISIONS OF
OTHER CIRCUITS.
The D.C. Circuit’s restrictive view of the
requirements imposed by NEPA, while consistent with that
recently embraced by a divided panel of the Eighth Circuit,
conflicts with decisions of the Seventh and Eleventh
Circuits on the same issues.
NEPA requires federal agencies to take a hard look
at environmental issues by preparing a “detailed
statement” in an EIS on “the environmental impact” and
“alternatives to the proposed action.” 42 U.S.C. §
4332(2)(C) (App. 54a). As part of the required analysis,
an agency must “[rjigorously explore and objectively
evaluate all reasonable alternatives” to a proposed project.
40 C.F.R. § 1502.14 (emphasis added) (App. 55a). The
discussion of alternative projects is the “heart of the
[EIS].” Id.
According to the D.C. Circuit, NEPA’s requirement
that “all reasonable alternatives” be considered calls for an
inquiry into “whether an agency’s objectives are
reasonable, and whether a particular alternative is
reasonable in light of these objectives.” App. 9a. The
decision of the court of appeals in this case makes clear
that in defining the objectives for a project, an agency is
not “substantively constrain[ed]” by NEPA. App. 10a.
This means, among other things, that an agency may
exclude all environmental factors from consideration in
defining the objective by which the reasonableness of
alternatives is considered under NEPA. Thus, an agency is
free to define the functional objective of a project—as it
did in this case—in a fashion that effectively narrows the
range of alternatives that can meet the stated objective to
ones that have virtually indistinguishable environmental
impacts. The court of appeals thus held that DOT could
exclude from consideration in the EIS an alternative that
would not meet the agency’s narrowly defined objective.
App. 13a.
The Seventh Circuit’s decisions establish a
different NEPA standard, which requires agencies to
undertake a broader analysis in complying with the statute.
In Simmons v. United States Army Corps of Engineers, 120
F.3d 664 (7th Cir. 1997), that court held that an agency
does not enjoy a free hand in defining the objectives of a
project for NEPA purposes:
One obvious way for an agency to slip past the
strictures of NEPA is to contrive a purpose so
slender as to define competing “reasonable
alternatives” out of consideration (and even out of
existence). The federal courts cannot condone an
agency’s frustration of Congressional will. If the
agency constricts the definition of the project’s
purpose and thereby excludes what truly are
reasonable alternatives, the EIS cannot fulfill its
role. Nor can the agency satisfy the Act. Jd. at
666.
See also Van Abbema v. Fornell, 807 F.2d 633, 638 (7th
Cir. 1986) (“the evaluation of ‘alternatives’ mandated by
NEPA is to be an evaluation of alternative means to
accomplish the general goal of an action”).”
* A similar interpretation of NEPA was recently advanced by
J mu Pad, Fd 2000 WLS ene Ce
Bridgeton v. FAA, _ F.3d 2000 WL 355521, at *14 (8th Cir.
Apr. 7, 2000) (R. Amold, J. ) (concluding that a runway
alternative was improperly excluded fom te EIS onthe bass tha
it did not “provide independent simultaneous IFR arrival
” which “is only one way of achieving” the project’s
(.. continued)
9
The Eleventh Circuit also has disagreed with the
position taken by the court of appeals in this case that an
agency may exclude from its analysis under NEPA any
alternative that does not fully satisfy the stated objective,
including alternatives that would achieve most of the
desired result with considerably less adverse
environmental impact. App. 13a. In North Buckhead
Civic Association v. Skinner, 903 F.2d 1533 (11th Cir.
1990), the Eleventh Circuit agreed with the objectors to a
highway project that requiring the agency to consider
alternatives that only partly satisfy the project’s objectives
serves NEPA because “a discussion of alternatives that
would only partly meet the goals of the project may allow
the decision maker to conclude that meeting part of the
goal with less environmental impact may be worth the
tradeoff with a preferred alternative that has greater
environmental impact.” Jd. at 1542; accord City of
Bridgeton, _ F.3d at _, 2000 WL 355521, at *15 (R.
Arnold, J., dissenting). Although the Eleventh Circuit held
in North Buckhead that the agency did not violate NEPA
by failing to consider an alternative that would fall short of
satisfying the project’s transportation goals, it did so
because there was no evidence that the alternative
proposed by the objectors would have a less severe
environmental impact. 903 F.2d at 1542.? According to
general goal a ee ee eee See delay”
at the St. Louis ). The panel majority in that case did not
agree. Id. at *6-7 (deeming reasonable the exclusion of a runway
alternative from the EIS because it lacked simultaneous IFR arrival
capability).
* In this case, although DOT refused to se errs
of the environmental impacts of any
twelve lanes, there is substantial evidence in the apr arene ee
record that a smaller river crossing would have lesser
(...continued)
10
the court of appeals opinion in this case, however, an
agency need never consider alternatives that would only
“partly meet” the agency’s defined goal, no matter how
great the environmental benefits of such an alternative
might be and no matter how close the alternative comes to
meeting that goal.
The modes of analysis required by the D.C. Circuit
and the other referenced circuits are irreconcilable. For
example, Simmons involved the Corps of Engineers’
approval of the construction of a dam to create a new
reservoir in Illinois to supply drinking water both to the
City of Marion and to the Lake of Egypt Water District.
In preparing its EIS, the Corps considered the project’s
purpose to be “finding or creating a single source to supply
both Marion and the ... Water District.” Jd. at 669. The
Seventh Circuit held that this definition was unreasonably
narrow in light of the underlying problem to be addressed:
“The general goal of Marion’s application is to supply
water to Marion and the Water District—not to build (or
find) a single reservoir to supply that water.” Jd. The
Corps therefore violated NEPA by excluding from
consideration any alternative that could solve the general
problem, but that did not satisfy the Corps’ narrower
objective of creating a single source to supply both
markets.
In contrast, the D.C. Circuit in this case refused to
step back from DOT’s narrow definition of its objective to
consider the underlying problems being addressed. As the
EIS stated and the district court found, the general goal of
the project is to “address[] the future transportation needs
environmental im . See App. 43a; see also, e.g., C.A. App.,
Vol. VIII, p. 91 (Final EIS).
11
of the region.” App. 44a. Moreover, according to the
discussion in the Final EIS of the “Purpose of and Need
for Action,” the needs to be addressed by the project are
numerous: removal or rehabilitation of the aging structure
that is currently in use; improvement of safety through the
addition of roadside “breakdown lanes”; elimination of the
bottleneck created when eight lanes of traffic on the
Beltway converge into six lanes on the Bridge; lessening
the frequency with which the drawbridge must be opened
for maritime traffic; accommodating the volume of local,
regional, and interstate traffic that is expected to be
crossing the River in the vicinity of Alexandria through the
year 2020; and protecting the surrounding environment,
including both its natural and cultural resources. C.A.
App., Vol. I, pp. 107-16 (Final EIS).
Considering the numerous goals of the project,
including that of protecting the environment, it is evident
that less environmentally onerous alternatives—such as a
ten-lane crossing with simplified land-side interchanges—
would satisfy the agency’s basic aims.‘ For example, a
ten-lane crossing would eliminate structural concerns
about the existing Bridge, sharply reduce the safety
problems, remove the current bottleneck, and substantially
deal with projected traffic levels even twenty years hence,
while having far fewer adverse environmental effects. At
the same time, because satisfaction of forecasts of traffic
demand two decades in the future is inherently uncertain
and a matter of degree, this is a paradigmatic case where,
‘ Petitioners believe that these goals could be addressed by a wide
cane Gt ee ton oe ee ee oreeeeee OF Sak eee
i ing a bridge or tunnel ing with less than twelve lanes at
the existing site or construction of an additional crossing miles
downstream.
- as the Eleventh Circuit stated, “the decision maker [could]
-.- conclude that meeting part of the goal with less
environmental impact may be worth the tradeoff with a
preferred alternative that has greater environmental
impact.” North Buckhead, 903 F.2d at 1542. But only a
NEPA analysis that takes a hard look at a broader range of
alternatives can permit the decision maker to reach that
conclusion.
The court of appeals, however, held that the
alternatives that needed to be analyzed under NEPA could
be determined solely by whether or not they satisfied what
the court deemed DOT’s real objective, on which it said
the agency “focused specifically”: “the traffic needs that
will exist twenty years after the project’s approval” at the
current crossing site “during peak commuting hours.”
App. 10a-1la. In, emphasizing a single functional
objective of the project—rather than the underlying
reasons for and diverse goals of the proyect—the court of
appeals rejected the Seventh and Eleventh Circuits’
approach, an approach the D.C. Circuit has explicitly
rejected before. See Citizens Against Burlington, Inc. v.
Busey, 938 F.2d 190, 199 (D.C. Cir. 1991) (expressly
disagreeing with the Seventh Circuit’s view in Van
Abbema that the reasonableness of alternatives should be
judged by the “general goal” of the project); see also
Michael E. Lackey, Jr., Misdirecting NEPA: Leaving the
Definition of Reasonable Alternatives in the EIS to the
Applicants, 60 GEO. WASH. L. REV. 1232, 1257, 1268
(1992) (discussing D.C. Circuit’s disagreement in Citizens
Against Burlington with Seventh Circuit).°
* The analysis employed by the D.C. Circuit in the 1990s actually
—— aah ial which was similar to that
13
I. THE COURT OF APPEALS’ RULING
- UNDERMINES NEPA BY ENDORSING A
METHOD BY WHICH AGENCIES CAN AVOID
MEANINGFUL COMPLIANCE WITH THE ACT.
The decisions requiring an agency to analyze
alternatives that could achieve the general goal of the
project, thus precluding the agency from focusing its
analysis so narrowly as to exclude a range of alternatives
with meaningfully - different environmental impacts, are
correct. Judge Amold cogently discussed the problem
with the view of NEPA expressed by the court of appeals
in this case in a recent dissenting opinion:
Is the fact ... that [an alternative excluded from the
EIS] is inferior, purely as a matter of air-
transportation policy, to [FAA’s preferred
alternative] sufficient to justify the exclusion of [the
former] from detailed analysis? I think not. This is
exactly the sort of thing that NEPA was designed
for. The possibility that some substantive benefits
of a project might not be great enough to justify its
environmental costs is exactly the point of NEPA.
In the end, the agency will make this decision, but
it is allowed to do so, under the statute, only after a
detailed explanation of alternatives. City of
Bridgeton, _F.3dat___, 2000 WL 355521, at *15
(R. Arnold, J., dissenting).
of the Seventh Circuit. Indeed, the court of appeals below
purported to distinguish Gatien ae aeracend Se “contin ws Tog
= its own 2 sen ot Iding that alternatives ues
mere iytomnn ear dvua ally caneabanadeies
: the problem.’”” App. 12a-13a (quoting Natural Resources
—_ Council, Inc. v. Morton, 458 F.2d 827, 836 (D.C. Cir.
14
The court of appeals decision in this case provides
DOT, which undertakes or approves numerous
construction projects, with a roadmap for avoiding any
significant NEPA analysis in virtually every case. By
defining the transportation purpose of a project in narrow
terms, such as enabling “x” cars per day or “y” passengers
per hour to use a particular road, the agency could justify
its refusal to take a hard look in the EIS at the
environmental impacts of any smaller alternatives on the
ground that they do not satisfy the chosen objective even
though they may only barely miss the mark. In such cases,
agency decision makers will never receive the information
needed to weigh competing functional benefits versus
environmental impacts. In effect, the court of appeals’
decision has licensed DOT, and indeed any federal agency,
to refuse to give detailed consideration in an EIS to any
alternative that would not fully satisfy a single non-
environmental goal specified by the agency. This result
would be totally inconsistent with Congress’s clear
-\ commentator has observed that the D.C. Circuit
“erred [in Citizens Against Burlington] by not following
the Van Abbema court’s approach of considering the
alternatives to the proposed action in light of the general
goals of the project.” Lackey, supra, 60 GEO. WASH. L.
REV. at 1268. This observation highlights the need for
Supreme Court review of the D.C. Circuit’s application of
its approach to NEPA in this case. The correct
enforcement of this vital statute should not depend upon
the fortuity of the venue in which a particular action must
be brought.
15
CONCLUSION
The petition for a writ of certiorari should be
granted to resolve the conflict in the circuit courts on this
fundamental issue concerning the application of NEPA.
Respectfully submitted,
S. William Livingston*
Mitchell F. Dolin
Thomas L. Cubbage III
COVINGTON & BURLING
1201 Pennsylvania Ave. NW
Washington DC 20004-2401
(202) 662-6000
Attorneys for Petitioners
June 5, 2000 *Counsel of Record
16
oe
3 LLL LALO tee
ware
A ae Oe dee ae De ta et ee TT
PAIN POO DOF Le gr ER eg RGIOP 2 AIHA Sg Pte (8 Di eT oy aS re
e
APPENDIX A
UNITED STATES COURT OF APPEALS
FOR THE DISTRICT OF COLUMBIA CIRCUIT
No. 99-5220
City of Alexandria, Virginia, et al.,
Appellees,
Vv.
Rodney E. Slater, Secretary, U.S. Department
of Transportation, et al.,
Appellants.
Appeal from the United States District Court
for the District of Columbia (98CV00251)
December 17, 1999
Before: Silberman, Williams, and Randolph, Circuit
Judges.
Opinion for the Court filed by Circuit Judge Silberman.
SILBERMAN, Circuit Judge: Appellees challenged
the Federal Highway Administration’s approval of plans to
replace the Woodrow Wilson Memorial Bridge. The
district court held that the Administration violated the
National Environmental Policy Act and the National
Historic Preservation Act. We reverse.
I.
The Woodrow Wilson Memorial Bridge is a
microcosm of the Washington, D.C. metropolitan area’s
traffic congestion problems. Built in 1961, the six-lane
la
structure carries the Capital Beltway over the Potomac
River, connecting the City of Alexandria, Virginia, to
Prince George’s County, Maryland; originally intended to
serve as a Washington bypass for interstate travelers, it
became increasingly used by commuters as the region's
population grew. As a result, traffic volume on the Bridge
has increased to over 160,000 vehicles per day, more than
twice the capacity the structure was designed to
accommodate; congestion is particularly acute during peak
hours, where the configuration of an eight-lane Beltway
feeding into a six-lane bridge—in addition to steadily
increasing local traffic in the surrounding communities—
has produced one of the worst rush-hour “bottlenecks” in
the region. These congestion problems have created
harmful collateral consequences: the heavy volume on the
Bridge has contributed to an accident rate nearly double
that of similar facilities in the region, and has expedited
the deterioration of the Bridge’s structure to the point
where the Bridge is projected to be structurally unsound by
2004.
Efforts to replace the Bridge began over ten years
ago, when the Federal Highway Administration, in
cooperation with its coordinate agencies in Maryland,
Virginia, and the District of Columbia, began examining
alternative approaches to solving the Bridge’s capacity and
structural problems. The Administration began to study
the potential effects of rebuilding the Bridge on the
surrounding communities early in the project's
development, commissioning surveys of historic and
archaeological resources in areas likely to be affected by
the projects. The Commission also started the process,
mandated by the National Environmental Policy Act
(NEPA), 42 U.S.C. § 4321 et seg. (1994), of considering
the environmental impacts of alternative project designs.
In 1991 the Administration issued a draft Environmental
2a
Impact Statement (EIS) for public comment; this statement
Suggested and compared five proposals for replacing the
Bridge. Each of the alternatives in the draft proposed
expanding the river crossing from six to twelve lanes, and
included a similar expansion of the five-mile Beltway
corridor approaching the river crossing from the east and
west.
Reaction to the draft was less than enthusiastic; the
Administration was criticized for assessing inadequately
the environmental and cultural impacts of its proposal, and
for failing to coordinate its work with that of interested
governmental agencies and community groups. By its
own admission concerned that “a region-wide consensus
about the new bridge had not been reached,” the
Administration went back to the drawing board. In
response the Administration organized a “Coordination
Committee” composed of elected and administrative
Officials from the region to enhance community and
intergovernmental cooperation. The Committee revisited
the entire process of developing alternative Bridge designs,
ultimately soliciting and considering over 350 proposals
from interested individuals and organizations, and
increased the Administration’s public outreach efforts in
affected communities. In the meantime, pursuant to its
obligations under section 106 of the National Historic
Preservation Act, 16 U.S.C. § 470f (1995 & Supp.), and
section 4(f) of the Department of Transportation Act, 49
U.S.C. § 303 (1997), the Administration continued to
' More specifically, the project would widen. the Beltway to
twelve lanes_between Telegraph Road in Alexandria and Route
210 in Prince George’s County.
3a
assess the project's potential impacts on_ historic,
archaeological, and cultural resources in the area.
In 1997, the Administration issued its Final
Environmental Impact Statement (the “Final EIS”). The
Final EIS gave detailed consideration to eight alternative
proposals (seven “build” alternatives and a baseline “no
build” alternative), comparing them on a range of criteria
including vehicle capacity, cost, and extent of
environmental impacts. As was the case with the draft
each of the “build” alternatives scrutinized in the Final EIS
had twelve lanes; each alternative also had a lane
configuration that separated local and express traffic, and
contained a lane dedicated for High Occupancy Vehicle
usage. The critical difference among the proposed
alternatives was the type of river crossing; the seven
“build” alternatives included a range of tunnel and bridge
designs. Although the Final EIS discussed narrower eight-
and ten-lane options, it did not afford them full treatment
as formal “alternatives” because the Administration
concluded, on the basis of traffic projections, that narrower
_ river crossings would fail short of meeting the Bridge’s
long-term traffic needs. Among the eight options the
Administration designated a “Preferred Alternative” that
would replace the Bridge with twc-parallel six-lane
drawbridges (one drawbridge for eastbound and one for
westbound traffic) clearing the Potomac’s navigational
channel by seventy feet at their highest points. The
Administration also included ‘= the Final EIS a sixty-page
“Section 4(f) Evaluation” identifying and offering plans to
mitigate the effects of the Preferred Alternative and all
other build alternatives on public parks, wildlife refuges,
and historic sites.
After a brief comment period the Administration
approved the Preferred Alternative in a Record of Decision
4a
and submitted, as is required by section 106 of the
National Historic Preservation Act, a Memorandum of
Agreement evidencing the Administration’s cooperation
with state historic preservation officers in identifying
historic sites that might be impacted. The Memorandum
identified and offered mitigation plans for several historic
sites, but it also noted that the Administration had not yet
identified properties to be used for “construction staging,
dredge disposal, wetland mitigation, or other ancillary
activities” during the period of the Bridge’s construction.
The City of Alexandria filed an action in the district
court challenging the Administration’s approval of the
project, and the district court permitted three Alexandria-
based organizations that opposed the Administration’s
proposed alternative (collectively the “Alexandria
Coalition” or “appellees”) to intervene as plaintiffs. The
City alleged that the Administration had violated a host of
regulatory provisions, including the National
Environmental Policy Act, section 106 of the National
Historic Preservation Act, and section 4(f) of the
Department of Transportation Act.” After both sides had
filed for summary judgment the City of Alexandria settled
its claim with the Administration, leaving the Alexandria
Coalition as the only remaining plaintiffs.
The district court ruled in favor of the Alexandria
Coalition. See City of Alexandria v. Slater, 46 F. Supp. 2d
35 (D.D.C.1999). The court concluded that the
Administration had violated NEPA by not affording
> The City also alleged that the Administration sore very
Air Act by failing to conduct a conformity analysis for the twelve-
lane alternative. The district court agreed, but the
Administration does not appeal this finding.
Sa
detailed consideration to a ten-lane river crossing as a
“reasonable alternative” in the Final EIS, and that the Fina!
EIS’ treatment of the temporary environmental impact of
the construction phase of the project was too cursory to
satisfy NEPA. Relying upon our recent decision in
Corridor H Alternatives, Inc. v. Slater, 166 F.3d 368
(D.C.Cir.1999), the district court also determined that the
Administration had violated section 106’s requirement that
an agency “take into account” the effects of a proposed
project on protected historic properties by postponing the
identification of the sites that were to be used for
construction-related “ancillary activities.” Because an
agency must complete the section 106 identification
process before it can satisfy section 4(f)’s requirement that
an agency use “all possible planning to minimize harm” to
historic sites, the court concluded that the Admiriistration
had necessarily failed to comply with section 4(f) as well.
The district court remanded the project to the
Administration; the Administration appealed, as it is
entitled to do. See Occidental Petroleum Corp. v. SEC,
873 F.2d 325, 330 (1989) (when district court remand
obliges agency to take further actions under an arguably
incorrect legal standard an immediate appeal is
appropriate).
Il.
aie
The National Environmental Policy Act’s mandate
“is essentially procedural,” Vermont Yankee Nuclear
Power Corp. v. Natural Resources Defense Council, Inc.,
435 U.S. 519, 558 (1978); the statute requires that agencies
assess the environmental consequences of federal projects
by following certain procedures during the decision-
making process. See Citizens Against Burlington, Inc. v.
Busey, 938 F.2d 190, 193-94 (D.C. Cir. 1991). Before
6a
approving a project, an agency must prepare a “detailed
statement ... [on] the environmental impact of the
proposed action, any adverse environmental effects which
cannot be avoided should the proposal be implemented,
[and] alternatives to the proposed action.” 42 U.S.C. §
4332(2)(C)(i)-(iii). These general prescriptions are given
sharper focus in the Council on Environmental! Quality's
regulations,’ which require agencies to prepare
environmental impact statements; at the “heart of the
environmenta! impact statement” is the requirement that an
- agency “rigorously explore and objectively evaluate” the
projected environmental impacts of all “reasonable
' ~ alternatives” for completing the proposed action. 40
C.F.R. § 1502.14.
__. Appellees argue, and the district court agreed, that
the Administration violated NEPA by failing to deem a
ten-lane bridge a “reasonable alternative” in the Final EIS.
They observe that a ten-lane bridge would constitute a
significant improvement over the existing six-lane
structure, and would reduce congestion with considerably
less impact on environmental and cultural resources than
each of the twelve-lane alternatives compared by the
Administration. In addition to having a narrower river
crossing, appellees point out that a ten-lane alternative
would have a smaller construction “footprint” along the
* The Council on Environmental Quality has no express regu
authority under the National Environmental Policy Act; i
to Oe TY A ions by
President Carter’s Executive No. 11991, 42 . 26,967
(1977). Because the Administration does not challenge the
Council’s regulatory authority, we treat the Council’s i
as binding on the agency. But see Scott C. Whitney, The Role of
the Pres ‘s Council on Environmental Quality in the 1990s and _
Beyond, 6 J. ENVTL. L. & Liv. 81 (1991).
7a
entire five-mile stretch of the Beltway that will be under
| construction, and would require smaller interchanges at
| each of the four points of access to the Beltway in the
| project corridor. The Administration responds that the ten-
| lane alternative favored by appellees was excluded after
| studies determined that it did not meet the traffic capacity
| needs of the project. The Administration also argues that
the difference between the environmental-impacts of the
two projects is less than appellees suggest; a ten-lane
bridge would impact only 1.6 fewer acres of parkland and
12.9 fewer acres of natural resources over the entire length
| of the project corridor, and would have an identical impact
on cultural resources.
How are the merits of appellees’ argument to be
assessed? After all, the phrase “reasonable alternative,”
standing alone, offers no guidance to a reviewing court.
Something can only be an “alternative” by reference to
something else; “the term ‘alternatives’ is not self-
defining.” Vermont Yankee, 435 U.S. at 551. The Council
| on Environmental Quality, for its part, does little to clarify
| the baseline against which a “reasonable alternative” is to
be measured; its regulations at times appear to contrast the
“alternatives” to the “proposal,” suggesting that the range
of reasonable alternatives are to be selected by reference to
the project implemented. See 40 C.F.R. s 1502.14. But
that approach would seem to bias the process. See, e.g.,
Calvert Cliffs’ Coordinating Comm., Inc. v. U.S. Atomic
Energy Comm'n, 449 F.2d 1109, 1114 (D.C. Cir. 1971).
And even if we were to understand an “alternative” to be
defined by reference to the proposal actually selected, our
interpretive task would hardly be easier, as “the adjective
‘reasonable’ is no more self-defining than the noun that it
modifies.” Citizens Against Burlington, 938 F.2d at 195.
8a
ewe
We have resolved this difficulty by evaluating an
agency’s choice of “reasonable alternatives” in light of the
objectives of the federal action; as then-Judge Thomas put
it in Citizens Against Burlington, “(t]he goals of an action
delimit the universe of the action's reasonable
alternatives.” Jd. But that approach of course requires that
we first consider whether the agency has reasonably
identified and defined its objectives. The agency’s choice
of alternatives are, then, evaluated in light of these stated
objectives; an alternative is properly excluded from
consideration in an environmental impact statement only if
it would be reasonable for the agency to conclude that the
alternative does not “bring about the ends of the federal
action.” Jd. We engage in both of these inquiries—
whether an agency’s objectives are reasonable, and
whether a particular alternative is reasonable in light of
these objectives—with considerable deference to the
agency’s expertise and policy-making role. Jd. at 196.
The district court’s opinion suggests that the
Administration improperly defined its objectives,
criticizing the Administration for narrowing its choice of
alternatives “based on a set of criteria that focused
primarily on transportation and safety issues.” City of
Alexandria, 46 F. Supp. 2d at 44. This description of the
Administration’s objectives is an accurate one; while the
“Statement of Purpose and Need” in the Final EIS
references several objectives (including protecting the
environment), it focuses on the region’s traffic needs. But
it hardly follows that the Administration violated NEPA.
As mentioned above, NEPA’s injunction that agencies
consider the environmental impacts of “all reasonable
alternatives” does not substantively constrain an agency’s
choice of objectives; to the contrary, it is those very
objectives that provide the point of reference for a
determination whether an alternative is “reasonable” in the
9a
first place. By suggesting that the Administration violated
NEPA because it did not sufficiently prioritize
q environmental goals, the district court. subtly—and
| impermissibly—transformed a procedural statute into a
substantive one. See Baltimore Gas & Elec. Co. v. Natural
Resources Defense Council, Inc., 462 U.S. 87, 97, (1983)
Be (“Congress in enacting NEPA ... did not require agencies
| to elevate environmental concerns over other appropriate
| considerations.”) The proper question to ask at the outset
| of a NEPA inquiry is not whether the Administration
| focused on environmental goals but rather—as we noted—
| whether its stated objectives were reasonable. It seems
| rather obvious to us that it is not unreasonable in
articulating its objectives for an agency to “focus primarily
| on transportation and safety issues” when replacing a
| massively congested and structurally unsound bridge. C7
Corridor H, 166 F.3d at 374 (affirming the
Administration’s rejection of highway alternatives that did
not meet the transportation and safety needs of the region).
More in keeping with our precedent, the district
court also determined that a ten-lane alternative was
reasonable—and therefore should have been given greater
attention—in light of these objectives. The district court
arrived at this conclusion by characterizing the
Administration as “articulat[ing] the problem as one of
addressing the future transportation needs of the region.”
“Such a broad statement of purpose and need,” the district
court explained, “hardly provides an unequivocal basis for
eliminating ten-lane alternatives from consideration.” City
of Alexandria, 46 F. Supp. 2d at 44. This might be so, had
the Administration truly characterized its objectives in
such general terms. But it did not. As is required by
statute, see 23 U.S.C. § 109(b), the Administration instead
focused specifically—in its Statement of Purpose and
Need and elsewhere—on the traffic needs that will exist
10a
OEeEEEE——EEEEOEE——————
twenty years after the project’s approval, and its analyses
based on 2020 traffic projections demonstrate that a ten-
lane bridge would be insufficient. The Administration’s
studies show that appellees’ preferred design (a ten-lane
configuration without an HOV lane) would be able to
accommodate less than half of the per-hour capacity of the
Administration’s preferred alternative, causing peak-hour
traffic queues of significantly greater length and extended
duration; accident rates would also be markedly higher on
a ten-lane structure.
The district court ignored this data, instead focusing
exclusively on an Administration study showing that a ten-
lane bridge would be able to accommodate up to 295,000
vehicles per day, a number only slightly smaller than the
projected daily traffic flow on the Bridge in 2020. City of
Alexandria, 46 F. Supp. 2d at 44. But that study
apparentiy assumed an even flow of traffic throughout the
day (which, of course, is unrealistic). Whatever the total
number of vehicles that will cross in a 24-hour period, the
relevant question is how long during peak commuting
hours it will take to cross the bridge. Appellees also do
not seriously challenge the Administration’s findings,
instead protesting that these studies establish little more
than the “truism ... that a ten-lane bridge would carry
somewhat less traffic than a twelve-lane bridge.” It is not
apparent to us why this proposition has less force in the
case because it is a “truism.”
Appellees’ more fundamental argument is that,
regardless of its shortcomings in satisfying future traffic
needs, we must hold a ten-lane bridge to be a reasonable
alternative in light of our statement in Natural Resources
Defense Council, Inc. v. Morton that an agency should not
“disregard alternatives merely because they do not offer a
complete solution to the problem.” 458 F.2d 827, 836
lla
(D.C. Cir. 1972). Appellees overread Morton. In that case
an environmental group challenged the Secretary of the
Interior’s proposed sale of oil and gas leases to submerged
lands in the Gulf of Mexico; the Secretary sought to sell
these properties as part of a cross- agency effort, initiated
by the President, to increase American energy supplies.
We held that the Secretary’s environmental impact
statement violated NEPA because it failed to consider
alternatives outside of the Department of the Interior’s
jurisdiction; we also noted that the agency could not
exclude alternatives “supplying only part of the energy that
the lease sale would yield.” Jd at 836. This broad
articulation of “reasonable alternatives” was compelled by
the national scope of the problem being addressed: “When
the proposed action is an integral part of a coordinated
plan to deal with a broad problem, the range of alternatives
that must be evaluated is broadened.” Jd. at 835.
Morton thus stands for the same proposition as
Citizens Against Burlington: namely, that a “reasonable
alternative” is defined by reference to a project’s
objectives. Morton explained that, within the context of a
coordinated effort to solve a problem of national scope, a
solution that lies outside of an agency’s jurisdiction might
be a “reasonable alternative”; so might an alternative
within that agency’s jurisdiction that solves only a portion
of the problem, given that other agencies might be able to
provide the remainder of the solution. Such a holistic
definition of “reasonable alternatives” would, however,
make little sense for a discrete project within the
jurisdiction of one federal agency, as we recognized in
Morton when we contrasted the Secretary’s action with
12a
that of building “a single canal or dam.”4 Id. Concerned
with severe traffic conditions in the Capital Region,
Congress has authorized the Administration to replace the
Woodrow Wilson Memorial Bridge. The Administration
has sole responsibility for solving this problem; were it to
build a ten-lane bridge, no one else would step in and
alleviate the congestion that would result.* In this context,
it is simply a non sequitur to call a proposal that does not
“offer a complete solution to the problem” a “reasonable
alternative.”
: One other point merits brief discussion. In finding
a ten-lane alternative reasonable, the district court noted
that the Administration only conducted a Clean Air Act
conformity analysis for the use of ten lanes on the Bridge.
See City of Alexandria, 46 F. Supp. 2d at 45. If the
Administration only expects ten lanes to be open, the
district court reasoned, how can it fail to consider a ten-
. We doubt the continuing vitality of the rather expansive view of
NEPA eet io ren, since subsequent S e Court
cases have directly criticized us for overreading statute’s
mandate. See Baltimore Gas & Elec. Co., 462 U.S. at 97; Vermont
Yankee, 435 U.S. at 554; Kleppe v. Sierra Club, 427 U.S. 390
(1976). Morton, after all, suggested that the Secretary should have
deemed as “reasonable alternatives” Congress’ ability to reduce oil
import quotas and the Federal Power Commission’s authority to
change its natural gas pricing policies. 458 F.2d at 835, 837. To
be sure, Vermont Yankee cited with approval our statement in
Morton stressing the limits of an agency’s obligations under
NEPA, 435 U.S. at 551, but we wonder whether Morton’s holding
can be squared with Vermont Yankee’s injunction that “the
‘detailed statement of alternatives’ cannot be found wanting
simply because the agency failed to include every alternative
device and thought conceivable by the mind of man.” Jd
* As the Administration determined, there are no apparent and
feasible independent rail transit options that could be combined to
a ten-lane bridge to satisfy transportation needs.
13a
lane bridge as a reasonable alternative under NEPA? The
answer is that the Clean Air Act and NEPA inquiries have
different time horizons; while a project must show
conformity with the Clean Air Act at the time it is
approved, see 42 U.S.C. § 7506(c)(1) (1995), the
consideration of reasonable alternatives under NEPA
requires, as mentioned above, an assessment of traffic
needs in 2020. Accordingly the Administration did not
violate the National Environmental Policy Act by failing to
include a ten-lane bridge proposal as a “reasonable
alternative” in its Final Environmental Impact Statement.
B.
Once an agency identifies the “reasonable
alternatives” to a proposed action, NEPA and Council on
Environmental Quality regulations also require an agency
to identify the “adverse environmental effects” of each
alternative. See 42 U.S.C. § 4332(2)(C\ii); 40 C.F.R. §
1502.16. The district court found fault with the
Administration’s treatment of the temporary “construction
impacts” that would arise during the period that the Bridge
was being built. Again, we disagree.
The district court focused on the brevity of the
“Construction Impacts” section of the Final EIS, which
covers only four pages and, according to the district court,
“is of such a broad and generic nature that it could apply to
practically any construction project undertaken by the
{Administration].” City of Alexandria, 46 F. Supp. 2d at
45. While the Administration’s discussion might have
been more thorough, we think the district court’s
assessment of the Administration’s treatment of these
issues too harsh. The Administration addresses a range of
expected construction impacts, including the
construction’s likely effect on local traffic, air quality, area
noise levels, water quality and wetlands, cultural
Ida
resources, and visual effects. The level of detail of these
assessments varies; it is worth noting, in light of the
district court’s focus on the terseness of the
Administration’s analysis, that some of the shorter
analyses are the most eminently reasonable. Take, for
instance, the Administration’s discussion of | traffic
impacts. The Administration acknowledges that the
construction project will affect traffic flow on several
Alexandria roadways, and may also cause potential delays
in the delivery of emergency services. It also offers a
range of mitigation strategies: six lanes of the Bridge will
be kept open at all times to minimize rush-hour
congestion; some access (even if circuitously routed) will
be maintained to all roads and areas; there will be no
disruption of marine traffic on the Potomac; the public will
be notified of temporary road closings through the news
media, the posting of signs, and the creation of a “project
activities” hotline. Perhaps appellees would prefer the
Administration to set forth in the Final EIS a
comprehensive plan detailing precisely which streets will
be closed, and which alternative routes will be established,
but that is not mandated by NEPA. See, e.g., Robertson v.
. Methow Valley Citizens Council, 490 U.S. 332, 353 (1989)
(“[I]t would be inconsistent with NEPA[ ] ... to demand
the presence of a fully developed plan that will mitigate
environmental harm before an agency can act.”).
We think the terseness of the Administration’s
discussion of construction impacts is justified for other
reasons as well. The Administration typically delays the
identification of “construction staging” sites—locations
used to store materials and equipment during project
construction—until the design stage of the project. As will
' be discussed infra, this practice is permissible under the
Statute and is arguably required by the Administration’s
governing regulations. Since the Administration did not
15a
identify the location of these areas, it of course could not
identify the accompanying environmental impacts with
precision. But this does not mean that the Administration
did not consider, on a more general level, what those
| impacts would be; the Final EIS identifies several potential
| staging areas, and notes that each of these sites are in
| “previously disturbed” areas with “minimal natural
resources.” -The Administration’s brevity is particularly
understandable given the numerous regulatory constraints
| that will limit the extent of construction activities. As the
| Administration notes, Maryland and Virginia require
_ construction contractors to limit noise levels in “noise
sensitive areas adjacent to the project area” to eighty
| decibels—a noise level comparable to- that currently
| produced by traffic on some stretches of the highway.
Similar federal and state regulatory provisions require the
mitigation of any short-term construction impacts on
wetland and aquatic resources, constrain the emissions of
dust from construction-related activities and equipment,
and limit the Administration’s selection of construction
staging areas. The Final EIS’ reference of these provisions
is important, as it indicates the Administration’s awareness
of the maximum impact that the construction may cause.
We also note that agencies are enjoined by the
Council on Economic Quality to develop environmental
impact statements that are “no longer than absolutely
necessary” and that discuss impacts “in proportion to their
significance.” 40 C.F.R. § 1502.2(b)-(c). The
Administration points out that each of the seven “build”
alternatives would have similar construction impacts, thus
making a detailed discussion of each of their effects
redundant. More fundamentally, while the disruption
caused by the construction of a project as significant as
this one is by no means trivial, it is relatively modest in
both scope and duration when compared to the |
16a
environmental impact of the project as a whole. To. be
sure, ‘there is a point at which an agency's analysis
ventures from the “tolerably terse to the intolerably mute,”
Greater Boston Television Corp. v. FCC, 444 F.2d 841,
~ 852 (D.C. Cir. 1970), but we simply do not think that the
Administration’s analysis of construction impacts reaches
that point.
iil.
' A.
The district court concluded that the Administration
also failed to identify adequately the effect that \its
preferred alternative will have on historic resources in the
project area, as is required under two distinct but
overlapping statutes: section 106 of the National Historic
Preservation Act and section 4(f) of the Department of
Transportation Act. Section 106, like NEPA, is essentially
a procedural statute; it requires that agencies “take into
account the effect of [an] undertaking on any district, site,
building, structure, or object that is included in or eligible
for inclusion in the National Register [of Historic Places].”
16 U.S.C. § 470f. To comply with section 106, an agency
must consult with state historic preservation officers to
ensure that historic properties in the project area are
thoroughly identified and the effects that the project will
have on them fully assessed. See 36 C.F.R. § 800.4-.5.°
The usual product of this consultation process is a
Memorandum of Agreement among the consulting parties
signifying agreement upon how the detrimental effects wil]
? The Council has recently promulgated regulations revising
section 106 process. 64 Fed.Reg. 27,044 (1999). Our citations are
i existed at the time the Administration
17a
be “taken into account.” Even where disagreement
precludes the completion of a Memorandum of Agreement
an agency may implement a project after receiving and
considering comments from the Advisory Council on
Historic Preservation. See id. at 800.6(c).
On the other hand, section 4(f), unlike the other
statutes at issue in this case, imposes a substantive
mandate on the Administration: It prohibits the agency
from taking an action that “uses” a historic resource unless
there is “no prudent and feasible alternative to using that
land” and the agency engages in “all possible planning” to
“minimize harm” to the sites.’ 49 U.S.C. § 303(c); see
also Citizens to Preserve Overton Park v. Volpe, 401 U.S.
402 (1971). Department of Transportation regulations
require the Administration to “make the section 4(f)
approval” at the same time that it approves its final EIS or
issues its Record of Decision, 23 C.F.R. § 771.135(1); the
Administration ordinarily complies with this requirement
by publishing a separate “Section 4(f) Evaluation” along
with its final EIS, which identifies the project’s effects on
historic properties in the project area and the efforts the
agency has taken to mitigate those effects. In order to
comply with 4(f)’s substantive requirements, it is of course
necessary first to identify historic sites in the project area;
accordingly, we have observed that compliance with
section 4(f) is predicated upon completion of the section
106 process. See Corridor H Alternatives, Inc. v. Slater,
166 F.3d 368, 371 (1999).
” In addition to historical sites, other properties—including parks,
recreational areas, and wildlife preserves—are protected by section
4(f).
The central dispute between the parties is not about
whether, but about when, the Administration must
complete its identification of historic properties. The
Administration has been “taking into account” the effect of
the proposed project on historic sites since the project’s
inception, conducting several surveys which led to the
identification of 23 National Register-listed or National
Register-eligible properties, and 36 underwater or
terrestrial archaeological sites in the project area. The
Administration also identified and visited each National
Register-listed property in Alexandria for the purpose of
determining, among other things, the “visual impacts” that
various alternative bridge proposals would have on each
site. The result was publication of a Memorandum of
Agreement and a Section 4(f) Evaluation with or prior to
the Administration’s approval of the project; these
documents identify seven historic sites that will be affected
by the project.and another six that may be, and offers plans
to minimize and mitigate the project’s impact on these
properties.
The district court did not question the overall
legitimacy or thoroughness of these studies.* (Indeed,
appellees cannot identify a single historic resource in the
* Appellees point to the Administration’s decision to-reduce the
size of the “Area of Potential Effects” in 1997, and suggest that the
appellees do not point to an ere outside of the new
“reduced” Area of Potential wil
by the project.
19a
project area that the Administration failed to “take into
account.”” Instead, the district court concluded that the
Administration violated section 106 by deciding to
postpone the identification of sites where it would conduct
certain _ construction-related _activities, including
construction staging areas (the locations where contractors
will store materials and mobilize construction activities),
wetland mitigation areas, and dredge disposal sites. While
the likely impact of these activities, which the
Administration describes as “ancillary,” are minimal when
compared to those of the project as a whole, it is at least
conceivable that they could ultimately affect section 106
properties. Acknowledging this possibility, but noting that
it usually defers the identification of such properties until
the “design stage” of a large highway project, the
Administration included promissory language in its
Memorandum of Agreement binding it to fulfill its section
106 responsibilities when selecting these sites. The district
court thought that these prospective terms ran afoul of our
° Amicus Sierra Club rather inventively that the
Administration failed to treat as a section 106/4() property the
Hunting Terrace apartment complex in Alexandria, but it is not
eligible for inclusion in the National Register of Historic Places,
and therefore is not a protected property under either section 106
or section 4(f). See 23 C.F.R. § 771.135(e); 36 C._F.R. § 800.2(e).
Showing similar ingenuity, appellees argue that the Administration
violated sections 106 and 4(f) because “the boundaries of
Freedman's Cemetery have still not yet been determined.” They
apparently believe that since the site’s precise location is unknown
(and, it seems, unknowable), it is by definition i ible to know
for certain the “effect” that the construction will on the site,
thus placing the Administration in violation of sections 106 and
4(f). To set forth the logic of this is to refute it. Cf
Hoonah Indian Ass'n v. Morrison, 170 F.3d 1223, 1231-32 (9th
Cir.1999) (inability of Forest Service to identify location of Indian
march justified decision not to designate it a section 106 property).
20a
recent decision in Corridor H Alternatives, Inc. v. Slater,
166 F.3d 368 (D.C. Cir. 1999), in which we held that the
Administration could not postpone the entire section 106
process until after it issued its Record of Decision.
We think that district court misconstrued our
holding in Corridor H. In that case, the Administration
postponed the entire section 106 process for a major
highway corridor; its Record of Decision instead adopted
a “Programmatic Agreement” dividing the highway into
fourteen segments, and promised that it would not begin
construction of a particular segment before completing the
section 106 process for that segment. We held that this
Agreement impermissibly abrogated the Administration’s
responsibility to assess the project’s impact on historic
properties during the planning stages of the project. See
166 F.3d at 373. But that is not the case here, since the
Administration has identified historic properties along the
entire project corridor and documented its findings prior to
approval in both a Memorandum of Agreement and a
Section 4(f) Evaluation. All that has been deferred is the
identification of sites that might be impacted by a small
number of “ancillary activities.” This is quite
distinguishable from the “Programmatic Agreement” we
proscribed in Corridor H.
The Administration did not postpone the
identification of these properties “merely to avoid having
to complete its 4(f) and 106 analyses,” as the district court
said. 46 F. Supp. 2d at 47. As the Administration points
out, the precise identification of these sites requires
“substantial engineering work” that is not conducted until
the design stage of the project; indeed the Administration
is required to conduct such “final design activities” after it
completes its Final EIS. 23 CF.R. § 771.113(a){iii).
Furthermore, then-existing Council regulations explicitly
2la
encouraged flexible, staged planning in the section 106
process. See 36 C.F.R. § 800.3(b) (section 106 procedures
“may be implemented ... in a flexible manner”); 36 C.F.R.
§ 800.3(c) (section 106 regulations should not be
interpreted to “prohibit phased compliance at different
stages in planning.”). Appellees respond that- the
Administration could nonetheless “feasibly” identify these
sites without doing “final design” plans for the project.
But the standard of “feasibility,” while relevant to whether
an agency may use 4(f) properties, has no application in
determining when the agency must identify them. We
think that, particularly where the sites postponed are
merely ancillary to the project, section 106 and the
identification prerequisites of section 4(f) do not forbid the
rational planning process adhered to by the
Administration.
We also think that the Administration satisfied
section 4(f)’s substantive provisions- Appellees barely
bother to argue that the Administration did not comply
with section 4(f)(1)’s requirement that it consider all
“prudent and feasible alternative[s]” to using protected
properties. The reason for this gap in appellees’ otherwise
vigorous presentation is obvious enough. For while the
Administration is required to give the protection of 4(f)
property “paramount importance” in determining whether
an alternative is “prudent,” Overton Park, 401 U.S. at 412-
13, we have squarely held that an alternative cannot be a
prudent one if it does not satisfy the transportation needs
of the project. See Citizens Against Burlington, 938 F.2d
at 204. In light of this limitation, appellees can only win
under section 4(f){1) if they establish one of two
propositions: They must show that a narrower Bridge
satisfies the transportation needs of the project, aa
ola
must offer a “prudent” project alternative that does not
impact the 4(f) properties used by the Administration's
preferred design. The former question we have already
resolved in the Administration's favor, and appellees do
not advance an alternative highway route that has a less
significant impact on 4(f) properties.
Appellees do argue with greater enthusiasm that the
Administration violated section 4(f)(2)’s requirement that
the agency engage in “all possible planning” to minimize
harm to 4(f) properties, but this argument is equally
unpersuasive. Tc begin at the broadest level of generality,
appellees do not question the Administration’s express
findings that, among the seven “prudent and feasible”
alternatives compared in the Final EIS, the preferred
alternative “results in the least overall impact to section
4(f) resources.” Cf Druid Hills Civic Ass'n, Inc. v. FHWA,
772 F.2d 700, 716 (11th Cir. 1985) (noting that “section
4(f)(2) requires a simple balancing process which totals the
harm caused by each alternate route to section 4(f) areas
and selects the option which does the least harm”). At the
site- specific level, the Administration made several
Significant project modifications to avoid or minimize
impacts to section 4(f) properties, including altering an
interchange design to avoid impactirlg a schoolground and
eliminating the construction of a temporary Beltway
Overpass to minimize the risk of harm to Freedman’s
Cemetery. Where the Administration could identify no
feasible and prudent plan for avoiding impact to a 4(f) site,
it offered plans to mitigate that impact; for instance, it
proposed substantial improvements to Jones Point Park,
arguably the most significant 4(f) property impacted by the
project. Further recitation of the Administration’s
mitigation efforts is possible, but unnecessary; suffice it to
say that, after a thorough review of the record, we have
little difficulty concluding that the Administration
23a \
complied with its responsibilities under section 4(f) of the
Department of Transportation Act.'°
* * * *
During the course of our consideration of this case,
appellees have attempted to bolster their position by
pointing to the opposition of prominent legislators to the
project, and by noting the hurdles to ultimate
congressional approval that still lie in the Administration’s
path. These political impediments are irrelevant to us but
they indicate where appellees should concentrate their
efforts. We have been admonished by the Supreme Court
with respect to the very statute that is at the heart of this
case to avoid using its requirements as a vehicle to impose
our own judgment. Vermont Yankee, 435 U.S. at 554. Our
obligation is not to further our beau ideal of a bridge
design, but merely to ensure that the procedures mandated
by these statutes have been complied with. We hold that
the Administration has satisfied the requirements of
NEPA, the National Historic Preservation Act, and the
Department of Transportation Act, and reverse.
So ordered.
have
that our holding it could defer the identification of section 4(f)
properties that might be impacted by construction and
APPENDIX B
UNITED STATES COURT OF APPEALS
FOR THE DISTRICT OF COLUMBIA CIRCUIT
No. 99-5220
City of Alexandria, Virginia, Appellee,
v.
Rodney E. Slater, Secretary, U.S. Department
of Transportation, et al., Appellants
Alexandria Historic Restoration and Preservation
Commission, Coalition for a Sensible Bridge, Inc. and
Historic Alexandria Foundation, Appellees.
March 7, 2000
Before: Silberman, Williams, and Randolph, Circuit
Judges
ORDER
Upon consideration of appellees’ petition for
rehearing filed February 1, 2000, it is
ORDERED that the petition be denied.
Per Curiam
For the Court:
Mark J. Langer, Clerk
By: /s/ Robert A. Bonner
Robert A. Bonner
Deputy Clerk
APPENDIX C
UNITED STATES COURT OF APPEALS
FOR THE DISTRICT OF COLUMBIA CIRCUIT
No. 99-5220
City of Alexandria, Virginia, Appellee,
, »
Rodney E. Slater, Secretary, U.S. Department
of Transportation, et al., Appellants
Alexandria Historic Restoration and Preservation
Commission, Coalition for a Sensible Bridge, Inc. and
Historic Alexandria Foundation, Appellees.
March 7, 2000
Before: Edwards, Chief Judge; Silberman, Williams,
Ginsburg, Sentelle, Henderson, Randolph, Rogers, Tatel
and Garland, Circuit Judges
ORDER
Upon consideration of appellees’ petition for
rehearing en banc, and the absence of a request by any
member of the court for a vote, it is
ORDERED that the petition be denied.
Per Curiam
For the Court:
Peep ores eo Mark J. Langer, Clerk
: By: /s/ Robert A. Bonner
Robert A. Bonner
Deputy Clerk
Circuit Judge Henderson did not participate in this matter.
26a
APPENDIX D
UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLUMBIA
City of Alexandria, Virginia
Plaintiff,
Alexandria Historic Restoration
and Preservation Commission, et
al. 3 Civil Action No.
Plaintiff-Intervenors 98-0251 (SS)
We
Rodney EE. Slater, US.
Department of Transportation, et
al.,
Defendants
MEMORANDUM OPINION
This matter comes before the Court on Cross-
Motions for Summary Judgment.'! The relevant
undisputed facts are set forth below.
The Woodrow Wilson Bridge (the “Bridge”) is a
six-lane drawbridge linking interstates I-495 and I-95. It is
designed to carry approximately 75,000 vehicles per day
, The named Plaintiff, the City of Alexandria, is no longer a party
to this action. Accordingly, reference is made to Plaintiff-
Intervenors only in the body of the opinion. \
27a
across the Potomac river. It lies a few miles south east of
the Nation’s Capitol and just north of the historic City of
Alexandria, Virginia. The Bridge was opened to traffic in
1961. Added use in recent years has caused increased
traffic problems on the Bridge and at its interchanges.
Travel demand across the Bridge now far exceeds the
capacity for which it was designed. Projected travel in
2020 is estimated around 275,000 vehicles per day,
requiring up to 18 lanes through the Bridge corridor. In
part because of these projections, Congress passed the
Woodrow Wilson Memorial Bridge Authority Act of 1995,
providing for large-scale improvements at the river
crossing site. It is the general consensus that the Woodrow
Wilson Bridge needs to be replaced.
On November 25, 1997, the Federal Highway
Administration (“FHWA”) issued its Record of Decision
(“ROD”) approving a $1.6 billion highway project (the
“approved project”) which calls for replacing the Bridge
with two parallel drawbridges, each with space for four
general purpose lanes, one merge/diverge lane, and future
accommodation of one High Occupancy Vehicle (“HOV”)
or “other type” lane.? The two new bridges would increase
by about 260% the width of the river crossing now served
by the Bridge and would rise an additional twenty feet
above the Potomac River. The approved project also
entails reconstructing a five mile stretch of the connecting
interstate routes 495 and I-95 to accommodate twelve
lanes: eight general purpose lanes, two merged/diverge
lanes and two HOV lanes. In addition, the approved
project authorizes substantial redesign and reconstruction
of the four interchanges on either side of the bridge. The
? Hereinafter, the “8-2-2” lane configuration.
28a \
drawbridges would pass through Alexandria, Virginia’s
Historic District thirty feet south of the Bridge’s present
location.
Alexandria is one of America’s most historic cities.
Approximately one square mile of Alexandria is listed as a
National Register Historic District. This District preserves
the atmosphere of an early Virginian town, and contains
three — individually-designated National _ Historic
Landmarks.’ The approved project would pass through the
southernmost portion of Alexandria four blocks south of
the Alexandria National Historic Landmark District.
1. NEPA Compliance
The initial step to replace the Woodrow Wilson
Bridge began in 1989 when the FHWA held a Bridge
improvement design competition. While nothing
substantial emerged from this effort, on May 17, 1990, the
FHWA published a Notice of Intent to prepare a Draft
Environmental Impact Statement (“DEIS”). The Notice
stated that the purpose of the DEIS was to evaluate
proposals to “improve the Woodrow Wilson Bridge and
the I-95 approach roadway network between Telegraph
Road in Virginia, and Indian Head Highway in Maryland.”
55 Fed. Reg. 20556-02 (May 17, 1990). ;
Pursuant to the May 17 Notice, the first DEIS was
published in August 1991. Joint Appendix at pp. 003371-
3757.* It-contained detailed evaluations of six alternatives
requiring construction of a new river crossing and
> Gadsby’s Tavern, Christ Church, and the Franklin and Armfield
Slave Pen.
* Hereinafter, reference to the Joint Administrative Record will
appear as “JA.”
29a
improved interchanges (so-called “build” alternatives), and
an evaluation of one alternative requiring only repair of the
existing Bridge (the “no build” alternative). All of the
build alternatives presented in the 1991 DEIS were
comprised of twelve lanes or more. JA003376-78.
Furthermore, the 1991 DEIS twelve-lane buiid alternatives
all called for physical separation of the local and express
traffic, and complete reconstruction of certain
interchanges. Despite the forseeable enormity of the
construction required by the project, the 1991 DEIS
included only three pages of analysis of potential
construction impacts resulting from the various build
alternatives.
In early 1992 the FHWA formed an independent
review team (“IRT”) to review and identify areas in the
1991 DEIS that might be challenged in court. JA003878.
The IRT was composed of government attorneys and
related professionals from the FHWA, Maryland, Virginia
and the District of Columbia. JA003880. Although the
IRT stated that the DEIS was “adequate,” it found several
serious deficiencies in the 1991 DEIS, including failure to
discuss construction impacts adequately, failure to
critically analyze the assumption that HOV lanes would be
added to the Beltway, and failure to evaluate additional
regional impacts adequately. Additionally, the IRT noted
that the National Historic Preservation Act (“NHPA”)
Section 166 analysis had not yet been initiated. 5A003879.
Shortly after the IRT concluded its review the FHWA ran
a traffic analysis for a ten-lane river crossing. JA003898.
In June, 1992, the FHWA formed a Coordination
Committee, comprised of elected officials and senior
government executives from affected jurisdictions to
coordinate project development. The FHWA intended to
arrive at its preferred alternative project design through a
30a
“funneling” process. Accordingly, in the Spring of 1994
the Coordination Committee solicited suggestions for
project alternatives from all interested individuals and
organizations. | While most of the Suggestions the
Committee received dealt with the river crossing portion of
the project, the entire five-mile corridor was open for
comment. In evaluating suggestions, the Committee
applied a stepwise process of elimination. The Committee
first weeded out suggestions it deemed duplicative, beyond
the scope of the study, technically infeasible, or not in
keeping with the project’s purpose and need.
After initial screening, the FHWA combined the
remaining suggestions into “unique and distinct crossing
options and project area improvements.” JA000068.
These were then merged into a set of “end-to-end”
alternatives: i.e. alternatives covering all facets of the
project. The Coordination Committee reduced the number
of end-to-end alternatives by applying three Measures of
Effectiveness (“MOE”). The final MOE application
results were presented in the January 1996 Supplemental
Draft EIS (“SDEIS”). The six 1996 SDEIS build
alternatives all had twelve lanes. Thus, the January 1996
SDEIS contained six “end-to-end” project alternatives, the
only major design difference between them being the form
(e.g. bridge or tunnel) and location of the river crossing.
2. CAA Compliance
Pursuant to the Clean Air Act, in May 1996, the
Region II Administrator of the FHWA asked the
Transportation Planning Board (“TPB”) to determine
regional air quality conformity for a Bridge replacement
with twelve lanes but “opening with only 10-lanes until the
conditions for multi-modal, regional travel are reached.”
[Ex. 75.] In July, 1996, the TPB issued a draft conformity
analysis for a “new 10 lane facility with either a $1.00 or
3la
$1.50 toll each way.” [Ex. 76 at JA005185. para 130.]
The draft conformity analysis found that a ten-lane bridge
replacement with a $1.00 to $1.50 toll would conform to
National Capital Region air quality standards.°
On September 27, 1996, days after the close of the
comment period on the July 1996 SDEIS and nine days
after the conformity assessment was approved, the
Coordination Committee selected its Preferred Alternative.
Then, pursuant to NEPA, the study team began preparation
of the Final EIS (“FEIS”). The FEIS was released on
September 2, 1997.
The FEIS explains the omission of ten-lane
alternatives by stating that such configurations “cannot
satisfactorily address the transportation needs of the
region.” FEIS JA000109-113. The FEIS reports that the
ten-lane, no-HOV option was considered “in the early
stages of the study ... [but] was dropped at that time ...
because it was insufficient from a functional, safety and
operational standpoint.” JA000109. That conclusion
follows solely from the reduced capacity of a ten-lane
versus a twelve-lane crossing. At the same time, the FEIS
notes that social, cultural and environmental impacts
produced by a ten-lane alternative would be “essentially
the same” as those produced by a twelve-lane alternative.
JA000113. To support its conclusion, the FEIS includes a
one page “Environmental Impact Matrix” purporting to
break down the impacts of ten-and twelve-lane
configurations with respect to fifteen environmental, social
and cultural factors. JA000465. This table, in essence,
* The concept underlying imposition of a toll is based on the
theory that a substantial toll will “drive away” certain price
conscious prospective users.
32a
purports to demonstrate that the cumulative negative
effects on cultural, natural, and social resources of a
twelve-lane alternative are not substantially different from
those produced by a ten-lane alternative.
It is undisputed that alternatives with fewer than
~ twelve lanes, without HOV lanes and physical separation
of local and express traffic, were not subjected to detailed
NEPA analysis. FHWA has maintained that such
alternatives were properly excluded from NEPA analysis
since they would not meet the purpose and need of the
project.
3. NHPA and DOTA Compliance
Beginning in 1991 and pursuant to Section 106 of
the National Historic Preservation Act and Section 4(f) of
the Department of Transportation Act (“DOTA”), the
FHWA began taking into account the potential effects of
the project on sites eligible for listing on the National
Register of Historic Places. The FHWA conducted
investigations identifying cultural resources which might
be adversely affected by the project, and solicited
comments from interested parties. Between 1996 and
1995, the FHWA continued conducting cultural resource
investigations which included, inter alia, research at the
relevant State Historic Preservation Offices, the Library of
Congress, and the National Archives. In addition, the
FHWA coordinated archaeological excavations, aerial
photographic surveys, and other field work aimed at
identifying cultural and historic resources. JA000230.
In 1995, the FHWA defined the area of potential
effects (“APE”) of the project, demarcating the area which
might be negatively impacted by the project. In January
1996, the FHWA issued a Cultural Resources Technical
Report (“CRTR”). The CRTR purported to serve as an
33a
“integrated compilation of all previous terrestrial and
underwater archaeological/historic resource surveys,
investigations, and determinations of effect,” according to
the FHWA. JA005629. Also in 1996, the FHWA
circulated two proposed Memoranda of Agreement
(“MOA”). Under Section 106 implementing regulations,
the MOA represents formal agreement among the
consulting parties as to how adverse effects of the project
will be taken into account. 36 C.F.R. § 800.5. The two
proposed 1996 MOAs were not signed by the consulting
parties. Subsequent to the 1996 CRTR, the FHWA
performed additional cultural and technical studies. In
1997, the FHWA substantially reduced the size of the
project’s APE, and circulated three more proposed MOAs.
See JA006313. Signature to the final, October 1997, MOA
was made predicate to future participation in identification
of protected properties and mitigation efforts. See
JA002100, JA006839. The final, October 1997, MOA
was signed by the City of Alexandria, the District of
Columbia State Historic Preservation Officer, the
Maryland State Historic Preservation Officer, the Virginia
State Historic Preservation Officer, the National Park
Service, and the FHWA. Several interested parties did not
sign the final MOA, including the Alexandria Historical
Restoration and Preservation Commission and Old Town
Civic Association. The City of Alexandria, which signed
the final MOA, noted in an addendum to its signature page
“the City ... continues to believe that the FHWA has not
adequately taken into account the effect of the [approved
project] on historic resources, as required by Section
106{[of the National Historic Preservation Act].”
JA006841.
34a
ANALYSIS
1. Standard of Review
Summary judgment is appropriate if there is no
genuine issue as to any material fact and the moving party
is entitled to judgment as a matter of law. Fed. R. Civ. P.
56(c). In considering a motion for summary judgment the
Court must assume the evidence of the non-movant, “and
States, 445 F.Supp. 832, 835 (D.D.C.1978) (“summary
the agency's action will be overtumed if it is found to be
arbitrary, capricious, an abuse of discretion, or otherwise
28 (D.D.C.
ark v. Volpe,
| appropriate as the questions presented before this Court are
solely legal in nature.
| II. Compliance with the Clear Air Act
Congress enacted the Clean Air Act (“CAA”) in
order “to protect and enhance the Nation's air quality, to
initiate and accelerate a national program of research and
| development designed to control air pollution, to provide
| technical and financial assistance to the States in the
| execution of pollution control programs, and to encourage
the development of regional pollution control programs.”
42 U.S.C. § 7401(b) (1988). Pursuant to the CAA, to
protect the public health, the EPA established National
Ambient Air Quality Standards (“NAAQS”) which reflect
the maximum concentration levels of particular pollutants
| (criteria pollutants) allowable. See 42 U.S.C. § 7409
(1991). Responsibility for achieving and maintaining the
r NAAQS falls on the states, which are required to submit
| state implementation plans (“SIPs”) to the EPA specifying
| the manner in which they will achieve and maintain the
| NAAQS for various criteria pollutants. See 42 U.S.C. §
| 7407. The EPA and the states have designated different
| regions according to the level of criteria pollutants in each
| area. See id. A region which has not attained the NAAQS
for a certain criteria pollutant is designated a
“nonattainment” area. The National Capital area where
the approved project is located has been designated a
“nonattainment” area for Ozone.
|
|
| In 1990 Congress amended the CAA in an effort to
| spur progress toward attainment of the NAAQS. A key
: component of the 1990 CAA amendments was the addition
of a requirement that all federal agencies and
instrumentalities undertaking activities in a nonattainment
area ensure that their project will conform to the relevant
SIP. This is known as the “conformity requirement”. In
36a
order to conform, the federally approved project must not
cause or contribute to new violations, increase the
frequency or severity of existing violations, or delay
attainment of the NAAQS. See 42 U.S.C. § 7506(c)(1)(B).
This requirement is repeated in the EPA regulations
pertaining to federally assisted or approved transportation
projects. See 40 C.F.R. 93.101 et seq. (requiring a
conformity analysis for all transportation projects prior to
agency approval, funding or implementation).
In May, 1996, the FHWA conducted a conformity
analysis for a ten-lane river- crossing with tolls pursuant to
the Bridge project. In 1997, the FHWA issued its ROD,
approving a twelve-lane river crossing. The Plaintiff-
intervenors argue the FHWA must perform a conformity
analysis for a twelve-lane river crossing with no tolls, and
that the ten-lane, with tolls conformity analysis is
insufficient under the CAA.
Defendants state they do not need to perform a
conformity analysis for the approved project because it is
not significantly different from the ten-lane project that
was found to conform. Specifically, they contend that
since initially only ten lanes will be opened, the design
scope of the approved project as initially operated does not
_ differ from the ten-lane design assumed for the purposes of
the conformity analysis. They admit, however, that when
the river crossing becomes twelve lane operational as
anticipated, they will have to perform a new conformity
analysis.°
: Defendants put forth the same argument with respect to the issue
37a
opine wen
Neither the plain language of the CAA, nor the
applicable regulations, provide the agency any such
leeway. The statute and regulations state a conformity
analysis must be completed prior to the approval, adoption,
or implementation of a project. See 42 U.S.C. § 7506; 40
C.F.R. § 93.102. The EPA regulations define a project in
toto, not, as only that part of a project that is constructed
and used initially. See 40 C.F.R. § 93.101. The logical
extent of defendant’s argument, if adopted, would be to
allow an agency to define a project differently depending
on what particular purpose the agency has in mind at the
time. For example, for NEPA purposes, the agency has
defined the project as a twelve lane project; Yet, for CAA
purposes, the approved project is only ten lanes in size.
Such inconsistency in agency reasoning is unacceptable.
Plaintiff-intervenors further claim that the FHWA
must perform another conformity analysis because the size
of the interchanges has changed. Again, the FHWA
disagrees. Defendants argue that consideration of the size
of interchanges is immaterial for conformity analysis
purposes. They note the regulations cite only to the
number and location of the interchanges, not the size. This
argument ignores the plain language of the regulation
which states that design scope “includes” such things as
the “number and location of interchanges ... etc”. See 40
C.F.R. § 93.101 (emphasis added). This language does not
limit solely to a consideration of the location and number
of interchanges. The regulation contemplates otherwise.
In this instance, the approved project consists of expanded
provision of tolls on the bridge is uncertain, as the states of both
Maryland and Virginia oppose tolls. If the approved project does
not include tolls, the Defendants maintain, a new conformity
analysis will be done.
38a
interchanges necessary to accommodate the larger carrying
capacity of a twelve-lane bridge. Just as the number of
lanes may have an effect on air quality, due to the increase
in emissions caused by more vehicles, so may the size of
interchanges. Defendants must consider this factor in
analyzing the project’s impact on regional air quality
before approval of the preferred alternative in the ROD.’
Ill. Failure to Comply with NEPA’s
Reasonable Alternatives Requirement
Plaintiff-intervenors allege Defendants violated the
National Environmental Protection Act (“NEPA”) by
failing to analyze all reasonable alternatives to their
preferred action when preparing the FEIS, and by failing to
take the required “hard look” at the environmental and
other impacts of the preferred action.
NEPA states that any federal agency undertaking a
“major federal action{]” likely to “significantly affect the
human environment” must prepare an Environmental
Impact Statement. The EIS must provide a “detailed
Statement” of the environmental impacts of the action,
possible alternatives, and measures to mitigate adverse
effects of the proposed action. See 42 U.S.C. §
4332(2)(C). While NEPA does not mandate any particular
result, it requires the agency to follow particular
procedures in its decision-making process. The purpose of
these procedures is to ensure the agency has before it the
” The EPA informed the FHWA ie, Soap, 1997 that it had
“concerns about the air uality analysis o project in the FEIS”.
Specifically, EPA stated “it is not clear that the proposed price
will conform to the Clean Air Act implementation goals”. June
11, 1997 Letter to Mr. David C. Lawton, Director Office of
Planning and Program Development from EPA.
39a
ee ee
best possible information in order to make an “intelligent,
optimally beneficial decision” and to ensure the public is
fully apprized of any environmental risks that may be
associated with the preferred action. Calvert Cliffs’
Coordinating Comm., Inc. v. U.S. Atomic Energy Comm’n,
449 F.2d 1109, 1114 (D.C.Cir.1971).
A key component of the EIS is the analysis of
“reasonable alternatives.” 40 C.F.R. § 1502.14(a).
Agencies must “rigorously explore and objectively
evaluate all reasonable alternatives” prior to selecting a
specific project. Sierra Club. v. Watkins, 808 F.Supp. 852
(D.D.C.1991). Alternatives that present a feasible solution
to the project’s stated purpose and need of the project are
reasonable. See Citizens Against Burlington, Inc., v.
Busey, 938 F.2d 190, 193-94 (D.C. Cir. 1991). While an
agency may decline to give rigorous consideration to
proposals that fall far short of the project’s purpose and
need, an agency may not eliminate an otherwise
reasonable alternative solely because it presents only a
partial solution to the stated purpose and need for the
project. See NRDC v. Morton, 458 F.2d 827, 836 (D.C.
Cir. 1972). Indeed this Circuit has held that it is
unreasonable “to disregard alternatives merely because
they do not offer a complete solution to the problem.” Jd.
at 836. | However, agencies need not consider every
conceiveable alternative. In determining the appropriate
set of reasonable alternatives to be given “rigorous”
consideration in the EIS, agencies must be guided by a
“rule of reason.” Busey at 194-195.
A second requirement of NEPA is that agencies
take a “hard look” at the environmental impacts of their
action. Agencies must consider the environmental effects
of their actions “to the fullest extent possible” in order to
satisfy this hard look requirement. See 42 U.S.C. § 4332.°
The D.C. Circuit has interpreted this statutory provision to
require that “environmental issues be considered at every
important stage in the decision making process.” Calvert
Cliffs’, 449 F.2d at 1118. In addition, the FHWA’s own
NEPA policy requires the agency give “balanced
consideration” to transportational and safety factors,
environmental impacts, and national, State, and local
environmental goals in selecting its preferred alternative.
See 23 C.F.R. § 771.105(b).
A. Standard of Review
A court, in reviewing an alleged NEPA violation, is
limited to determining whether the agency complied with
the statute’s procedural requirements. Busey at 195. So
long as an agency has considered all reasonable
alternatives and taken the requisite “hard look” at
environmental factors, its substantive decision will not be
overturned by a court unless it is “arbitrary, capricious, or
an abuse of discretion.” See Marsh v. Oregon Natural
Resources Council, 490 U.S. 360, 377 (1989).
Notwithstanding the judicial deference given to an
agency’s substantive choice, the D.C. Circuit has required
“strict compliance” with NEPA’s “inflexible” procedural
requirements. See 449 F.2d at 1109.
* The CEQ regulations implementing NEPA mirror this statutory
requirement. 40 C.F.R. §§ 1502.1 and 1502.2(b). (An agency’s
EIS must provide a “full and fair” discussion of the significant
environmental impacts” of the project.)
4la
ren
B. Failure to Analyze all Reasonable Alternatives
Plaintiff-intervenors contend the FHWA did-not
consider “all reasonable alternatives” prior to selecting its
preferred action. They allege the FHWA predetermined
the project’s lane configuration and unreasonably failed to
consider the diminished environmental impact of a ten-
lane alternative with smaller interchanges.
Defendants claim the agency did in fact consider an
appropriate range of reasonable alternatives, including ten-
and eight-lane _ bridge-crossings.” According to
Defendants, the FHWA gave ample consideration to a ten-
lane alternative, and took a hard look at the environmental
impacts of such a project.'® Indeed, at several places in the
FEIS the FHWA notes that the ten-lane project was
rejected after such consideration because it failed to meet
the purposes and needs of the project. Specifically, the
FEIS states that any bridge-crossing with fewer than
twelve lanes and no HOV capacity could not alleviate
projected future traffic congestion. Furthermore, the FEIS
notes that the environmental, socio-economic, and cultural
benefits of a ten-lane crossing are minimal. To support
this position Defendants cite to a one-page “Environmental
Impact Matrix” (“Matrix”) in the FEIS which compares
* In 1995 the Coordination Committee dropped the eight-lane
alternative because it was projected that it would not alleviate
traffic congestion on and around the bridge, nor could it
accommodate HOV lanes on the river crossing.
'© The FHWA cites to three pages in the FEIS that discusses the
various costs and benefits of a ten-lane project as opposed to a
twelve lane. In addition, they cite to a May 1996 retreat at which
time the Coordination Committee discussed a ten lane alternative,
weighed the comparative environmental and other impacts, and
decided that environmenta! benefits of the ten lane were minimal.
42a
various ten and twelve lane alternatives vis-a-vis {iiteen
environmental, socio-economic, and cultural factors. See
JA000465.
This Court finds that the FEIS does not support
FHWA’s claim that they gave the ten-lane alternative
adequate consideration. The Environmental Impact Matrix
does not begin to give a complete indication of the
environmental, social, and cultural costs and benefits of a
ten-lane versus a twelve-lane crossing. For example, the
Matrix shows that both ten- and twelve-lane alternatives
would affect five public parks. Yet no indication is given
as to the nature or extent of any such impact on the five
parks. The analysis of air impact in the Matrix
demonstrates this point even more fully. The Matrix
indicates no adverse impact[.]
Additional deliberation is required before the
agency can conclude that its twelve lane proposal will
have zero impact on air quality, when it has yet to
undertake any conformity analysis as required by the
CAA. Indeed, the EPA, in reviewing the draft FEIS,
indicated that the FEIS’s analysis of “air impact” was
inadequate. See June 11, 1997 Letter to. Mr. David C.
Lawton, Director Office of Planning and Program
Development from EPA.
The consideration that the FHWA gave to a ten-
lane alternative prior to the publication of the FEIS
demonstrates the agency’s insufficient analysis as well. In
soliciting proposals for its 1990 concept competition, the
agency specified that all plans be a minimum of fourteen
lanes and have HOV capacity. Thus, in its first Draft EIS,
the agency did not consider a ten-lane alternative. Then,
between 1992 and 1996 when the Coordination Committee
was reviewing proposals, the narrowing of alternatives was
based on a set of criteria that focused primarily on
43a
transportation and safety issues[.} JA000109. This
narrowing was done without the benefit of any detailed
analysis of the environmental and cultural costs and
benefits of a ten-lane or smaller bridge-crossing.
Defendant’s state that they did not need to give
detailed consideration to a ten-lane alternative because it
did not meet the agency’s stated purpose and need for the
project. The FEIS in its “Project Need” statement
articulates the problem as one of addressing the future
transportation needs of the region within the context of the
Constrained Long-Range Plan for the National Capitol
Region. Such a broad statement of purpose and need
hardly provides an unequivocal basis for eliminating ten-
lane alternatives from consideration without rigorous”
comparison of the environmental, socio-economic, and
cultural benefits. Moreover, the limited analysis the
FHWA did on a ten-lane alternative demonstrates that it
could possibly provide a partial solution to the problem.
The FHWA’s own traffic analysis of a ten-lane alternative
demonstrates that it can handle up to 295,000 vehicles per
day. This is close to total satisfaction of the estimated
maximum 300,000 vehicles per day which will cross the
river in 2020. To eliminate all ten-lane alternatives from
“rigorous” consideration simply because they fall short of
the total future estimated demand by 2 percent does not
stand up to the rule of reason which must guide the agency
in making its determination.
Given that a ten-lane alternative presents a feasible
alternative, the FHWA should have assessed closely the
benefits associated with it. The three pages discussing the
environmental and other benefits of a ten-lane project, and
the Matrix comparing them, falls short of providing the
kind of detailed analysis necessary to support an agency's
decision under NEPA."!
There is a logical inconsistency in the agency’s
reasoning. First, the FHWA attempts to support its
decision under NEPA by stating that a ten-lane bridge
without HOV lanes could not satisfy the “statement of
purpose and need”. In contrast, for purposes of the CAA,
the FHWA characterizes the project as a ten-lane river
crossing The FHWA’s effort to re-characterize the
fundamental nature of the approved project so as to satisfy .
both NEPA and CAA cannot be reconciled. The river
crossing is either ten lanes or it is twelve. It cannot be
both.
C. Failure to Adequately Assess Construction Impacts
The Plaintiff-intervenors further claim the FHWA
failed to take the required “hard look” at the immediate
and long-term impacts associated with the construction of
the approved project. Specifically, they point to
insufficient identification and assessment of the
construction impacts in the FEIS.
NEPA requires the agency make available to public
officials and citizens the environmental impacts of an
action prior to selecting a preferred course of action. See
Simmons v. U.S. Army Corps of Engineers, 120 F.3d 664
'' Obviously, reconsideration of the lane configuration will require
further review of the various interchange designs that accompany
the river-crossing portion of the project. In light of this Opinion it
is assumed the agency will consider all reasonable interchange
alternatives as part of its reconsideration of final end-to-end
alternatives. Therefore, this Court need not consider in detail
Plaintiff-intervenors claim that defendants failed to consider
reasonable alternatives to its “preferred” interchange designs.
45a
(7th Cir. 1997). In order to satisfy this requirement, the
FEIS must identify and analyze the effects the project is
projected ti have on environmental factors. See NRDC v.
Hodel, 865 F.2d 288, 294 (D.C. Cir. 1988). The 1997
FEIS prepared by the FHWA in anticipation of their ROD
failed to do this. Defendants cite to approximately four
pages in the FEIS which discuss the construction impacts
likely to be associated with the project as evidence of their
compliance. However, the discussion of construction
impacts is of such a broad and generic nature that it could
apply to practically any construction project undertaken by
the FHWA. For example, in identifying and quantifying
the amount of air emissions, the FEIS flatly states “the
construction phase has the potential of temporarily
impacting ambient air quality due to emissions from
construction equipment and dust from earthwork and the
utilization of unpaved roads.” The FEIS neither attempts
to quantify such air emissions, nor describes how such
impact could affect the human and non-human
environment. Discussions of noise,'? visual,'? and other
impacts in this section are similarly vague and non-
informative. Such terse summaries of the likely effects do
not come close to providing the public with the kind of
information necessary to weigh the environmental costs
and benefits of the project. The Environmental Protection
Agency noted as much in its assessment of the Draft FEIS.
The EPA stated that the FEIS should present a “worse case
'? The FEIS predicts that “an increase in project noise levels
would occur during the construction of the project” and
that a noise study “will be performed during design phase of
the study to analyze the potential noise impacts of specific
construction impacts.” JA000470.
'> The FEIS states only that “views may be temporarily affected.”
46a
quantitative estimate of potential acreage impacts to
wetlands and aquatic resources”, expand on the
development of a mitigation plan, and identify the impacts
on the federally-protected bald eagle and osprey. See June
11, 1997 Letter to Mr. David C. Lawton, Director Office
of Planning and Program Development from EPA. The
agency did not accept the EPA’s recommendation in
finalizing the FEIS.
[IV]. The FHWA Failed to Complete its Identification
of Protected Properties under the NHPA
Federally funded highway projects must comply
with both Section 106 of the National Historic
Preservation Act, 16 U.S.C. §§ 470f, 470h-2(f), and
Section 4(f) of the Department of Transportation Act, 49
U.S.C. § 303.
To satisfy Section 4(f), the FHWA must first
identify all protected properties that may be affected by a
potential project. See Corridor H. Alternatives, Inc. v.
Slater, 982 F.Supp. 24, 31 (D.D.C.1997). A property is
protected under the DOTA if it is “a park, recreation area,
or wildlife and waterfowl refuge of national, State, or local
significance, or land of an historic site of national, State, or
local significance (as determined by the Federal, State, or
local officials having jurisdiction over the park, area,
refuge, or site).” 49 U.S.C. § 303(c). The FHWA must
then determine if the project will “use” any protected
properties. Finally, if the project calls for “use” of
protected properties, the Secretary of the FHWA must do
“all possible planning” to minimize harm to those
properties. 49 U.S.C. § 303(c)\(2); See Druid Hills Civic
Ass'n, Inc. v. Federal Highway Admin., 833 F.2d 1545,
1547-48 (11th Cir. 1987).
47a
Section 106 of the National Historic Preservation
Act provides that any agency having jurisdiction over a
federally-assisted project “shall, prior to the approval of
expenditure of any Federal funds on the undertaking ...
take into account the effect of the undertaking on [any
district, site, building, structure, or object that is included
or eligible for inclusion in the National Register].” 16
U.S.C. § 470f. Under regulations implementing Section
106, the FHWA is required to identify historic properties
within the area of potential effects of the project, and must
perform an analysis of the likely impacts on those
properties. See 36 C.F.R. Part 800 (1998); Colorado
Indian Tribes v. Marsh, 605 F.Supp. 1425, 1435-38
(C.D.Cal.1985).
It is clear that compliance with Section 4(f) is
partially predicated upon completion of a Section 106
analysis of impacts on historic properties. The regulations
implementing Section 106 and Section 4(f) define historic
properties in substantially the same way. Sections 4(f)
regulations identify hiistoric properties as “all properties on
or eligible for the National Register of Historic Places.”
23 C.F.R. § 771.135(e). Regulations implementing
Section 106 define historic properties as all properties
listed on or eligible for listing on the National Register of
Historic Places. 36 C.F.R. § 800.2(e) (1998). Therefore,
to identify pursuant to Section 4(f) all places of historic
significance that will be used by a project, the agency must
have satisfied the Section 106 identification requirement.
See Corridor H Alternatives, Inc. v. Slater, 166 F.3d 368,
372 (D.C.Cir.1999). As Judge Hogan recently stated,
because “Section 4(f) duties with respect to historic sites
are tied to a review of historic resources under Section 106
of the NHPA, it follows that an agency must complete its
Section 106 determinations before it can begin compliance
with Section 4(f).” Corridor H, 982 F.Supp. at 32.
48a
Likewise, it follows that an agency cannot reasonably be
expected to do “all possible planning” to minimize harm to
protected properties as required by DOTA Section 4(f)
without first having completed a detailed and
comprehensive list of protected historic resources
potentially affected by the project.
Plaintiff-intervenors contend that FHWA violated
both Section 106 of the NHPA and Section 4(f) of the
DOTA. First, Plaintiff-intervenors claim that the FHWA
did not take sufficient steps to identify historic resources
which would be used by the project under Section 106.
Second, Plaintiff- intervenors maintain that the FHWA did
not do “all possible planning” to minimize harm as
statutorily required by Section 4(f) of the DOTA.
In support of their argument that the FHWA did not
conduct a sufficient NHPA and DOTA historic resource
identification process, plaintiff-intervenors point to
statements made in the MOA. The MOA, for example,
says that “the Project may have an effect on additional
properties [not identified in the MOA] that are eligible for
inclusion in the National Register, as the result of activities
related to implementation of the Project, including, but not
limited to construction staging, dredge disposal, wetland
mitigation, or other ancillary activities ...”. JA 002089.
Plaintiff-intervenors contend that the locations and effects
of such activities are reasonably forseeable, and therefore
could be designated prior to adoption of the approved
project in the ROD.; The MOA also envisions the
preparation of an Historic Resources Identification and
Evaluation Report (the “Report”), “identify[ing] and
evaluat[ing] the defining historical characteristics of the
Alexandria Historic District within the APE.” JA002090-
91. The plaintiff-intervenors point out that the MOA is
largely promissory in nature, providing little in the way of
49a
me Oe et ree eo
concrete identification of protected resources and
mitigation plans. By not identifying all protected
resources prior to approval, plaintiff- intervenors state that
the FHWA violated the DOTA and the NHPAJ.]
Defendants explain that since the project design has
not been completed as to certain activities, no
identification need be done at this point. The Defendants
in essence propose putting off decision on the location and
extent of construction staging and dredge disposal, as well
as certain undefined “ancillary activities.” This
necessarily puts off identification of protected resources
which might be affected by design of those elements. See
MOA at JA002089. The FHWA argues that such activities
may be legitimately dealt with by execution of the MOA.
The FHWA further claims that the Report does not
represent an effort to attenuate the Section 106
identification process, but to “continue the Section 106
consultation process” both as to identified properties and
those not yet identified. Def.[s’] Br. at 66.
The Section 4(f) process must be completed before
the ROD is issued. See 1999 WL 54795 at 6 [166 F.3d
368, 373] (citing the “explicit requirement” that “[the
FHWA] complete the section 4(f) process before [it] issues
the ROD”). Here, the identification process was not
completed prior to issuance of the ROD. Identification of
historic properties possibly affected by dredge disposal
sites and construction staging is expressly postponed. An
“Historic Resources Identification and Evaluation Report”
is exactly what the NHPA and DOTA call for; namely,
identification of historic sites and evaluation of the adverse
impacts on them. Such a report must be prepared as part
of the Section 106 process prior to the issuance of the
ROD.
That the ROD approves a project design postponing
full compliance with the NHPA and the DOTA is not
adequate. An agency is not allowed to approve a less-
than-fully designed project in the ROD merely to avoid
having to complete its 4(f) and 106 analyses. Such a
holding would vitiate the purposes behind Sections 4(f)
and 106. Where aspects of the project can be feasibly
determined prior to the ROD, those aspects should be
factored into the Section 4(f) and 106 analyses. Here, the
MOA merely reflects agreement by the signatory parties to
postpone identifying “properties” and mitigation
procedures.
Because this Court concludes that the FHWA has
failed to complete the required identification of protected
affected properties under Section 4(f) of the DOTA and
Section 106 of the NHPA, it need not address the Plaintiff-
intervenors’ argument that the FHWA failed to do “all
possible planning” as required by the DOTA Section 4(f).
This will have to be done in the agency’s reconsideration
of its project.
As Defendants have not complied with their
obligations under the CAA, NEPA, NHPA and the DOTA,
this Court has no choice but to hold that the agency abused
its discretion in issuing its ROD in 1997 and remand this
matter for further agency action. Accordingly,
construction on the new bridge can not commence until the
agency has fulfilled its responsibilities under these statutes.
The court is reluctant to order this action. These
statutes have as their purpose the protection of various
aspects of the public interest. Despite their intended
purpose, they often cause regulatory gridlock which results
in necessary projects being interminably delayed. It is
clear an expanded bridge crossing linking the North and
South at the Nation’s Capital is sorely needed. While a
5la
return to the simpler days of the past might better satisfy
the concerns of the public interest statutes involved here,
progress must nevertheless occur. Simply put, an
expanded bridge over the Potomac River is necessary if
this Nation’s Capital and its surrounding neighborhoods
are not going to suffer paralysis.
The City of Alexandria along with the other
municipal areas that would be affected by the proposed
construction have now all signed off on the project.’
'* Recently, the City of Alexandria, an original plaintiff in this
litigation, entered into a settlement with the Defendants. The
agreement calls for:
1. Construction of direct access to Eisenhower Avenue from
495.
2. Study of the impact of eliminating a Church Street exit ramp
from the project, and the implementation of design measures
to mitigate adverse impact on residential areas in the event
the exit ramp is not eliminated.
3. A commitment to harmonize the construction of an “urban
deck” with the redevelopment of Jones Point Park and
portions of the George Washington Parkway south.
4. A maximum width of the project in specific areas and the
absence of permanent physical structures in others.
5. The retention of certain project features that provide access to
connecting high-ways and interchanges, such as Route | and
1-195.
6. A study of the feasibility of a new river crossing south of the
Woodrow Wilson Bridge.
This appears to be a positive step in bringing this important
and worthwhile project to fruition. It would be hoped that at some
point the other plaintiffs would show similar flexibility in
resolving the particular issues of concern to them. Sometimes
citizens groups with well intended objectives get so caught up in
their own zeal that they lose sight of overall societal needs and the
public interest as a whole suffers. Without an appropriate and
(...continued) ‘
52a
While administrative reconsideration of the project is all
that this Court can order, the Project to be put on a real
time basis might require direct intervention -by the
Congress, which after balancing all the public interest
aspects could “by pass” the regulatory gridlock that has
developed.’
An appropriate order granting Plaintiff-intervenors’
motion for summary judgment and denying that of the
Defendants accompanies this Memorandum Opinion.
April 13, 1999 /s/ Stanley Sporkin
Stanley Sporkin
United States District Court
measured balance of all of society’s needs, the requirements of a
nation to tend to the needs of all of its citizens cannot be achieved. —
'* This court is somewhat puzzled by the proposed design of the
new bridge which calls for it to ody a “draw bridge.” It is estimated
that the bridge would be required to be opened some 200 times a
year. With a projected use by some 300,000 vehicles a day, traffic
bottlenecks caused by opening and closing the bridge could well
be intolerable. As this nation is about to enter the 21st Century, it
seems incongruous to be adopting a technology that would be
better understood by our grandparents of a century ago. Certainly
at this late date, a suspension bridge design would not require any
new engineering feat and would seem to meet the needs to
be served by the new Potomac River crossing. Since the project
needs to be “rethought” it is hoped that this issue would be
included in the “rethinking” process.
53a
APPENDIX E
National Environmental Policy Act, 42 U.S.C. §
4332(2):
The Congress authorizes and directs that, to the fullest
extent possible: (1) the policies, regulations, and public
laws of the United States shall be interpreted and
administered in accordance with the policies set forth in
this chapter, and (2) all agencies of the Federal
Government shall—
* * *
(C) include in every recommendation or report on
proposals for legislation and other major Federal actions |
significantly affecting the quality of the human
environment, a detailed statement by the responsible
official on— ;
(i) the environmental impact of the proposed action,
(ii) any adverse environmental effects which cannot be
avoided should the proposal be implemented,
(iii) alternatives to the proposed action,
(iv) the relationship between local short-term uses of
man’s environment and the maintenance and
enhancement of long-term productivity, and
(v) any irreversible and irretrievable commitments of
resources which would be involved in the proposed
action should it be implemented.
Prior to making any detailed statement, the responsible
Federal official shall consult with and obtain the
comments of any Federal agency which has jurisdiction
by law or special expertise with respect to any
environmental impact involved. Copies of such
54a
stater -ent and the comments and views of the appropriate
Federal, State, and local agencies, which are authorized
to develop and enforce environmental standards, shall be
made available to the President, the Council on
Environmental Quality and to the public as provided by
section 552 of Title 5, and shall accompany the proposal
through the existing agency review processes ....
Council on Environmental Quality regulations, 40
C.F.R. § 1502.14 (“Alternatives including the proposed
action”):
This section is the heart of the environmental impact
statement. Based on the information and analysis
presented in the sections on the Affected Environment (§
1502.15) and the Environmental Consequences (§
1502.16), it should present the environmental impacts of
the proposal and the alternatives in comparative form, thus
sharply defining the issues and providing a clear basis for
choice among options by the decisionmaker and the
public. In this section agencies shall:
(a) Rigorously explore and objectively evaluate all
reasonable alternatives, and for alternatives which were
eliminated from detailed study, briefly discuss the
reasons for their having been eliminated.
(b) Devote substantial treatment to each alternative
considered in detail including the proposed action so that
reviewers may evaluate their comparative merits.
(c) Include reasonable alternatives not within the
jurisdiction of the lead agency.
(d) Include the alternative of no action.-
(e) Identify the agency’s preferred alternative or
alternatives, if one or more exists, in the draft statement
55a
and identify such alternative in the final statement unless
another law prohibits the expression of such a
preference.
(f) Include appropriate mitigation measures not already
included in the proposed action or alternatives.
56a
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.