Petition for Writ of Certiorari — Palmieri v. New York State Department of Environmental Conservation (No. 06-1135)

Supreme Court brief2006

Ask Donna

What actually matters in this document.

Text

Supreme Court of the

Gnited States

e

PAUL PALMIERI,

Petitioner,

-against-

NEW YORK STATE DEPARTMENT OF

ENVIRONMENTAL CONSERVATION,

Respondent.

On Petition for Writ of Certiorari to the United

States Court of Appeals for the Second Circuit

Sacieand

i

PETITION FOR A WRIT OF CERTIORARI

a aaaall ——

a ——

R. BERTIL PETERSON

Counsel of Record, Attorney for

Petitioner and Staff Counsel for

The Coalition of Landlords,

Homeowners & Merchants, Inc.

28 East Main Street

Babylon, New York 11702

(631) 376-2110

®

QUESTIONS PRESENTED FOR REVIEW

Did respondents, as punishment for his refusal to

allow a violation of his Fourth Amendment rights,

unreasonably deny petitioner a wetlands permit to

build an extension of an existing dock that protrudes

approximately 92 feet away from his yard and into a

bay because petitioner refused to give his consent to a

warrantless pre-permit inspection of his home, deck,

backyard fencing, bulkhead, dock and two boat lifts?

Should the “special needs” test be expanded to permit

a governmental agency to deny a private property

owner his right against unreasonable searches,

seizures, and to be secure in his property, as protected

by the Fourth Amendment to the United States

Constitution, under circumstances where the

governmental agency seeks access to private property

as part of a construction permit process, not an

emergency criminal investigation or prevention?

Should all private owners of waterfront property be

stripped of their Fourth Amendment right against

unreasonable searches, seizures and to be secure in

their property because their rear property faces a body

of water?

Did respondents, as punishment for petitioner’s

refusal to allow a violation of his Fourth Amendment

rights, unreasonably refuse to conduct a pre-permit

inspection of the area adjacent to, and beneath, an

existing dock that protrudes 92 feet away from

petitioner’s yard and into the bay using a boat, a

QUESTIONS PRESENTED FOR REVIEW

_ (CONTINUED)

method which had been used previously during a pre-

permit inspection of petitioner’s prior tidal wetlands’

permit application and which is the only reasonable

way of inspecting the area in question?

Could respondents even conduct a warrantless pre-

permit inspection, while on petitioner’s property, of

an area in a bay adjacent to, and beneath, an existing

dock that protrudes 92 feet away from petitioner’s

yard?

Was respondents’ denial of petitioner’s tidal

wetlands’ permit application, as punishment for his

refusal to allow a violation of his Fourth Amendment

Rights, upon the ground that petitioner refused to

give his consent to a pre-permit warrantless

inspection of his property and the area adjacent to,

and beneath, an existing dock that protrudes 92 feet

away from his yard and into the bay, a violation of

petitioner’s right against unreasonable search and

seizure under the Fourth Amendment to the United

States Constitution?

Assuming that respondents demonstrated a “special

need” to enter petitioner’s property, did such need

constitute a constitutionally acceptable exception to

plaintiff's right not to be subjected to an unreasonable

search and seizure under the Fourth Amendment to

the United States Constitution?

ii

10.

11.

QUESTIONS PRESENTED FOR REVIEW

(CONTINUED) |

Is a warrantless pre-permit inspection during which

representatives of a governmental agency walk

through closed gates, across the front yard, side yard,

and entire length of the back yard of petitioner’s

private residential property a minimal intrusion?

Was a warrantless pre-permit inspection on

petitioner’s private residential property a matter of

governmental interest?

Did the respondent governmental agency demonstrate

disregard for its own rules and the rule of law by not

deeming petitioner’s application for a wetlands’

permit complete pursuant to ECL §70-0109(1)(a) and

(b) and 6 NYCRR §621.5 (b)(2) and by failing to

send petitioner its first notice of incomplete

application within 15 days of its receipt of

petitioner’s permit application as the afore-mentioned

rules require?

Did the respondent government agency demonstrate

disregard for its own rules and for the rule of law by

not deeming petitioner’s application for a wetlands’

permit complete pursuant to ECL §70-0109(1)(d) and

by failing to send petitioner its second notice of

incomplete application within 15 days of its receipt of

additional information from petitioner as the afore-

mentioned rules require?

LIST OF PARTIES

The parties are the petitioner, Paul Palmieri, and the

respondents, the New York State Department of

Environmental Conservation hereafter (“DEC”), Erin M.

Crotty, Commissioner, and Molly T. McBride,

Administrative Law Judge.

TABLE OF CONTENTS

Questions Presented for Review .................... i

I oo ka Wa cy ee eee ee eT iv

UME RI og SS oe Svs en eee ee eee iv

Te Ae SUID ook kbs oo oe Rs ee eS Vv

Tile ot AS. 5 sk i ee Se eee xii

| PREP ee ee PO On Ee rH on

ny IE I oo oo in bes we nie wow ee oO ]

URNNNONE OE FUTURE sn on cet ivess 1

Constitutional Provision and Statute Involved .......... ]

gS eee ee ye ee

TURIN sec brie oe oes aera ee 16

CE Sis a has eo ae 28

iV

TABLE OF AUTHORITIES

Cases: Page(s

Ambry v. Bd. of Trustees of

N.Y. City Fire Department,

296 A.D.26 S82 CAG DCM. 2007) 5 owe eens 11-12

Anobile v. Pelligrino,

203 F.36 107, 420 GGCi. 2008) 6c cece ones 20

Bd. of Educ. of Indep. School Dist.

No. 92 of Pottawatomie County v. Earls,

536 U.S 822, 829, 122 S.Ct. 2559,

O55 CE FE To Ce 5 5 ES 12, 21, 23, 24

Brookhaven v. Ronkonkoma Realty Corp.,

154 A.D.26:665 (26 Dept. 1969)... 0. ces. 12, 20

California v. Ciraolo,

476 U.S. 207, 213, 106 S.Ct. 1809,

Pe Ree er CD keh ee Pees 25, 26

Camara v. Municipal Court of the

City and County of San Francisco,

387 U.S. 523, 540, 87 S.Ct. 1727,

Te ee EE UPTE So pa oe eee ees , 20, 23, ZF:

Colon v. Bailey,

26 A.D.3d 454, 455-456,

810 N.Y.S.2d 51]

CE Ss GOOD. recs saacced Rie eee 6

Cases: Page(s)

DiCarlo v. City of New York,

286 A.D.2d 363, 365 (2d Dept. 2001) .......0........ -

Dow Chemical Co. v. United States,

476 U.S. 227, 106 S.Ct. 1819,

ee ne a ee mee 25-26, 26

Florida v. Riley,

488 U.S. 445, 109 S.Ct. 693,

ee Cie ORO RATE ws an odes aN wel 26

Fry v. Village of Tarryton,

NE He POE UPPED hs oka ek eed els Ohne 12

Griffin v. Wisconsin,

483 U.S. 868, 873, 107 S.Ct. 3164,

55 po ES. 7) Eng eae meer AiraiG Sites 21, 22, 24

Heimbach v. Commissioner,

136 Mic.2d 1 (Sup. Ct. Albany Co. 1987) ............ 17

Leventhal v. Knapek,

Pe POPE: BOOED jcc See dceaesteuewces 22

Matter of Atlantic Cement Co. v. Williams,

IZPAD.2E C4, 90d Dent. 1967)... 2. es 3

Matter of Benlevi Obedian & Belevi v.

New York State Dept. of Envtl. Conservation,

144 A.D.2d 358, 361 (2d Dept. 1988),

appeal dismissed 74 N.Y.2d 650 (1989) ............ 3, 18

vi

Cases:

Matter of Calm Lake Dev. v.

Town Bd. of Town of Farmington,

213 A.D.2d 979 (4" Dept. 1995) ..............

Matter of Northern Metro.

Residential Healthcare Facility v. Novello,

24 A.D.3d 1069, n. 1 (3d Dept. 2005) ..........

Matter of Oak Is. Beach Assn. v. Flacke,

96 A.D.2d 841, 465 N.Y.S.2d 596

Ce BOE. SPE oor Os eh ree ee eee en ees

Matter of Paul Palmieri, appellant, v.

New York State Department of

Environmental Conservation, respondent,

2006 NY Slip Op 5794; 2006 N.Y. App.

Div. LEXIS 9379 under Appellate Division

Docket No. 2005-02686; Suffolk County

ee See BE. ce ee ee wake we ee ao

Matter of Saltzman v. Board

of Appeals of Vil. of Roslyn,

26 A.D.3d 505, 506, 811 N.Y.S.2d 99

oe ee. ee

Matter of Thompson v. Department of

Envtl. Conservation of the State of New York,

132 A.D.2d 665 (2d Dept. 1987) app. den.

MUSEO Ge.

Vil

Cases: Page(s)

Michigan + _‘lifford,

464 U.S.287, 291-92,

104 S.Ct. 641, 78 L.Ed.2d 477 (1984) ............. 20, 21

National Treasury Employees Union v. Von Raab,

489 U.S. 656, 109 S.Ct. 1384,

SEF Rca OOF CAPONE ee eee 22

New Jersey v. T.L.O.,

469 U.S. 325, 342, 105 S.Ct. 733, :

Se ee FRIEND oS LE ee 21 (twice)

Nicholas v. Goord,

No. 01 Civ. 7891, 2003

U.S. Dist. LEXIS 1621,

at *50 (S.D.N.Y. February 6, 2003).............. 3 Sys

O’Connor v. Ortega,

480 U.S. 709, 724, 107 S.Ct. 1492,

94 L.BG.26 TIVCI9ST). 2 eg ei eee ins 4 Weese 24

Palmieri v. Lynch,

392 F.3d 73 73 (2d Cir. 2004)

cert. denied 126 S.Ct. 424, 163 L.Ed.2d 323 (2005) ... 3,4

Reed v. Schneider,

Giz F Sap. ZIG TE DON.Y. 1905) «i ies ie 27

Skinner v. Railway Labor Executive ’s Assn.,

489 U.S. 602, 109 S.Ct. 1402,

HOS 52 ee Ore CPOE ke cle ed od bo oe de eae

Vill

Cases: Page(s)

Sokolov v. Village of Freeport,

re 20

Stender v. Albany,

188 A.D.2d 986 (3d Dept. 1992)

ey Ge sr 23

Tayntor v. NYS Department of

Envronmental Conservation,

See rae ee 7) 02 EO, IDBT) ow eee ees 17

United States v. Hatfield,

pee we tee, oe clo Cw. 2003)... ......-06.--- 26

United States v. Jenkins,

od ES 26

United States v. Knights,

534 U.S. 112, 122 8.Ct. 387,

| Bo) |) ) rr rrr 22

United States v. Knotts,

460 U.S. 276, 103 S.Ct. 1081,

a 25

United States v. Newton,

Be ee ee a? COIN, F. 2002)... wee ees 22

United States v. Paulino, :

See eee C7 iC 1988) .............6....:.. 20

Cases: Page(s)

United States v. Reilly,

Po he Vath, BAT e Oe. TOG) noon ccc aewens 26

Vernonia School Dist. 47J v. Acton,

515 U.S. 646, 654-661, 115 S.Ct. 2386,

EFe MA DOUEIGOED 6 ooo veeh eek 3, 4, 21, 23, 24

Statutes:

Beds SND lad ee ede eee er ree 11,19

ay SPE. ck hele sk Ch UKE eee ee eee 12

CME. c's ob 'k-a bo ie leh Reka ae ee eae 5

hs. SOE = abaya Ce eke ees bee 17

ECL 70-0109 (a), (b) and{c).......... 16-17 (twice), 18

ECL 70-0109(1)(a) and (b) ............... ii, 11, 16-17

Saas POE 3 3 eo oe She eee ee wae ee 18

Ory eae cs o's ¥ carne bee evades ene. 11, 19

6NARR CLIO MD 2... ee 3,14

Pre Cae ae ok op a he oa ee eee 14

Ca ee 11,14

CHYTRR SIS Ls Se 11,19

Statutes: —= Page(s

Ree ee ii, 11, 17, 18

Ce OE os ks 2, 3, 15 (twice), 16

GNVCRE G21.90Ne) 2... 5. eee eee 3, 11, 19

Cire 0 3, 12, 14 (twice)

“pth NSS eee See eer ee see 12

RNR 3 oe ee ae 12

CN A Nh ei. 14

xl

\

TABLE OF APPENDICES

APPENDIX A

Decision of the Court of Appeals,

State of New York, Dated and

Entered November 21,1006 .............. la-2a

APPENDIX B

Decision of the Appellate Division,

Second Department, State of New

York, dated and Entered July 18, 2006....... 3a-5a

APPENDIX C

Judgment of Supreme Court, State of

New York, County of Suffolk, Dated

July 25, 2003 and Entered August 8, 2003 ... . 6a-9a

APPENDIX D

Memorandum Decision of Supreme Court,

State of New York, County of Suffolk,

Dated and Filed May 5, 2003 ............ 10a-21a

APPENDIX E

Decision of the Commissioner, State

of New York, Department of

Environmental Conservation,

Dated and Filed April 7,2004 .......... 22a- 33a

Xi!

TABLE OF APPENDICES

(Continued)

APPENDIX F

Hearing Report of Administrative

Law Judge Molly T. McBride

Dated January 30,2004 ............... 34a- 46a

APPENDIX G

Ruling of the Commissioner, State

of New York, Department of

Environmental Conservation,

Dated and Filed February 1, 2002........ 47a- 50a

APPENDIX H

Ruling on Motion and Summary

Report of Molly McBride (ALJ) ......... Sla- 66a

APPENDIX I

Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations ... . 67a- 132a

Xili

OPINIONS BELOW

The opinion of the Court of Appeals, State of New

York, the court below, is reported at 2006 N.Y. LEXIS 3587

(November 21, 2006); and the opinion of the Appellate

Division of State Supreme Court, Second Department, is

reported at 31 A.D.3d 645 (2d Dept. 2006). The opinion of

the Supreme Court of the State of New York, County of

Suffolk, is not reported.

DATE JUDGMENT ENTERED

The judgment of the Supreme Court of the State of

New York, County of Suffolk, which is dated July 25, 2003,

was entered on August 8, 2003.

STATEMENT OF JURISDICTION

This Court has jurisdiction under 28 U.S.C. Section

1257.

CONSTITUTIONAL PROVISION

AND STATUTES INVOLVED

The constitutional provision involved is the Fourth

Amendment to the U.S. Constitution which provides:

“The right of the people to be secure in their persons,

houses, papers, and effects, against unreasonable

searches and seizures, shall not be violated, and no

warrants shall issue, but upon probable cause,

supported by oath or affirmation, and particularly

describing the place to be searched, and the persons

or things to be seized.”

STATEMENT OF THE CASE

This is an appeal from a decision and order dated and

entered on November 21, 2006 of the Court of Appeals of

the State of New York denying petitioner’s motion for leave

to appeal an order of the Appellate Division, Second

Department, dated and entered in the office of the Clerk of

the Appellate Division on July 18, 2006, holding that (1)

under the circumstances of this case, the nisi prius court

properly directed an administrative hearing on the issue of

whether an inspection of petitioner’s property was reasonably

necessary, (2) the Fourth Amendment to the United States

Constitution does not bar a warrantless inspection of his

premises; (3) a request by respondents for an on-site

inspection of the wetlands and adjacent areas on his property,

in order to review the accuracy and impact of petitioner’s

permit application, fell within the special needs exception to

the Fourth Amendment’s warrant requirement; (4) in this

instance, the state’s interest in protecting wetlands is strong;

(5) petitioner’s expectation of privacy was diminished by the

fact that his yard was open and exposed to the Great South

Bay, that he applied for a permit to build in tidal wetlands,

that he had previously consented to periodic inspections, and

that the inspection would be a minimal intrusion; and (6)

petitioner’s remaining contentions were without merit; and

affirmed the Judgment dated July 25, 2003 and entered on

August 8, 2003 of the Supreme Court of Suffolk County

(Baisley, J.) and undated Memorandum Decision, which

Judgment and Memorandum Decision granted the petition to

the extent that petitioner was held to be entitled to an

adjudicatory hearing pursuant to 6 NYCRR §621.7(f),

otherwise denied the petition; and determined that petitioner

would have the burden at such hearing of demonstrating that

respondent’s demand for an on-site inspection of petitioner’s

property is not reasonably necessary in order to evaluate

petitioner’s application for a wetland’s permit (6 NYCRR

§624.9(b)(1)).

The July 18, 2006 decision and order of the Appellate

Division, Second Department, provides in pertinent part as

follows:

“The Supreme Court, in effect, determined that the

petitioner’s wetlands permit application was

complete. However, the fact that an application is

complete does not preclude the Department of

Environmental Conservation (hereinafter the DEC)

from requesting supplemental information, including

an on-site inspection, during the post-completion

review of an application (see 6 NYCRR 621.1{[c],

621.7[f] and 621.15[b]; Matter of Benlevi Obedian &

Benlevi v. New York State Dept. of Envitl.

Conservation, 144 AD2d 358, 361; Matter of Atlantic

Cement Co. v. Williams, 129 AD2d 84, 90). Under

the circumstances of this case, the Supreme Court

properly directed an [*2] administrative hearing on

the issue of whether an inspection of the petitioner’s

property was reasonably necessary.

“Contrary to the petitioner’s contention, the Fourth

Amendment to the United States Constitution does

not bar a warrantless inspection of his premises (see

Palmieri v. Lynch, 392 F3d 73, cert denied 126 S Ct

424; see also Vernonia School Dist. 47J v. Acton, 515

US 646; Matter of Thompson v. Department of Envil.

Conservation of State of N.Y., 132 AD2d 665). A

request by the DEC for an on-site inspection of the

wetlands and adjacent areas on his property, in order

to review the accuracy and impact of the petitioner’s

permit application, fell within the special needs

exception to the Fourth Amendment’s warrant

requirement (see Palmieri v. Lynch, supra). In this

instance, the state’s interest in protecting wetlands is

strong. Moreover, the petitioner’s expectation of

privacy was diminished by the fact that his yard was

open and exposed to the Great South Bay, that he

applied for a permit to build in tidal wetlands, that he

had previously consented to periodic inspections, and

that the inspection would be a minima! intrusion (id. ;

see also Vernonia School Dist. 47J v. Acton, supra;

Matter of Thompson v. Department of Envil.

Conservation of State of New York, supra).

“The petitioner’s remaining contentions are without

merit (see Matter of Northern Metro. Residential

Healthcare Facility v. Novello, 24 AD3d 1069, n 1;

DiCarlo v. City of New York, 286 AD2d 363, 365;

Matter of Calm Lake Dev. v. Town Bd. of Town of

Farmington, 213 AD2d 979).”

In a companion case, argued in, and decided by the

Appellate Division, Second Department, on the same day’;

decided by the Court of Appeals of the State of New York,

on the same day, for which review is being sought in a

petition for a writ of certiorari that will be submitted to this

L. Reported as /n the Matter of Paul Palmieri, appellant, v.

New York State Department of Environmental

Conservation respondent, 2006 NY Slip Op 5794; 2006

N.Y. App. Div. LEXIS 9379 under Appellate Division

Docket No. 2005-02686; Suffolk County

Index No. 13500/04.

Court on the same day as the within petition, the Appellate

Division, Second Department, ruled as follows:

“In a proceeding pursuant to CPLR article 78 to

review a determination of the New York State

Department of Environmental Conservation that an

on-site inspection of the wetlands and adjacent areas

on the petitioner’s property was reasonably necessary

for the review of his application for a permit to

extend his dock pursuant to Environmental

Conservation Law articles 15 and 25, and that his

application was denied unless and until he allowed

the inspection, the petitioner appeals, as limited by

his brief, from so much of an order and judgment

(one paper) of the Supreme Court, Suffolk County

(Baisley.), dated January 5, 2005, as granted that

branch of the respondent’s motion which was to

dismiss the petition as time-barred, denied that

branch of his cross-motion which was for leave to

extend the time to personally serve the respondent,

and dismissed the proceeding.

“ORDERED that the order and judgment is affirmed

insofar as appealed from, with costs.

“Contrary to the petitioner’s contention, the Supreme

Court properly dismissed the petition as time-barred.

The Supreme Court correctly applied the 30-day

limitations period in ECL 25-0404 and held that the

petition, filed 57 days after the determination of the

Commissioner of the State of New York Department

of Environmental Conservation (hereinafter the

DEC), was untimely (see Matter of Oak Is. Beach

Assn. v. Flacke, 96 A.D.2d 841, 465 N.Y.S.2d 596).

“Furthermore, the petitioner offered no good cause

for his delay in serving the DEC, and that branch of

his cross motion which was for leave to extend the

time for service was made over three months after his

first attempt at service. Accordingly, the Supreme

Court providently exercised its discretion in denying

that branch of the cross motion (see Matter of

Saltzman v. Board of Appeals of Vil. of Roslyn, 26

A.D.3d 505, 506, 811 N.Y.S.2d 99; Colon v. Bailey,

26 A.D.3d 454, 455-456, 810 N.Y.S.2d 511).

“In light of our determination, we need not reach the

petitioner’s remaining contentions.

“FLORIO, J.P., CRANE, RITTER and FISHER, JJ.,

concur.”

Petitioner’s Article 78 proceeding arose out of the

respondents’ denial of his application for a tidal wetlands’

permit authorizing construction of an extension to an existing

dock presently protruding approximately 92 feet into the

Great South Bay.

In 1991, petitioner applied for, and was granted, a

tidal wetlands’ permit for the reconstruction of his bulkhead

and the construction of a 52 foot fixed pier with additional

pilings and two boat lifts. Following construction of these

improvements, in January of 1993, petitioner applied for

another tidal wetlands’ permit to extend his existing 52 foot

dock an additional 110 feet and to add two more boat lifts.

Although that permit application was denied by the DEC on

November 4, 1993, following petitioner’s request for an

administrative hearing, a settlement was reached wherein the

DEC agreed to issue petitioner a permit for a dock extension

of 40 feet and for the construction of an additional boat lift

after it had conducted a pre-permit inspection by boat of an

area in the Great South Bay behind petitioner’s property in

the area adjacent to and beneath petitioner’s then existing

dock.

Petitioner submitted another application to the DEC

for a wetlands’ permit in May of 1999, seeking to extend his

92 foot dock by 50 feet and to add another boat lift. Ina

letter sent to petitioner dated April 7, 2000 by Mark C.

Carrara, its Deputy Permit Administrator, the DEC

acknowledged that it had received petitioner’s application for

a wetlands’ permit “on June 7, 1999”. Approximately 36

days later, the DEC sent petitioner its first Notice of

Incomplete Application dated July 13, 1999, informing

petitioner that his application was incomplete in that he had

failed to submit photographs, project plans, a location map, a

recent survey, proof that the proposed dock extension and

boat lift were reasonable and necessary and information as to

how many boats would be moored. After it received

petitioner’s photographs, project plans and a location map on

January 20, 2000, the DEC waited almost three months

before sending petitioner a second “Notice of Incomplete

Application” dated March 13, 2000 indicating that

petitioner’s application was still incomplete as he had failed

to submit a recent survey of the project site. Thereafter, by

letter dated April 7, 2000, the DEC informed petitioner that

his application was complete except for a pre-permit

inspection on his property. When petitioner refused to give

the DEC his consent to conduct a pre-permit inspection on

his property, insisting instead that the DEC conduct its pre-

permit inspection of the bottom of the bay adjacent to, and

beneath, the proposed location of the dock extension

(approximately 92 feet into the bay) by boat, a method which

the DEC had used in performing its prior pre-permit

inspections of the bottom of the bay adjacent to, and beneath,

petitioner’s present dock, the DEC denied his wetlands’

permit application by “Notice of Permit Denial” dated July 7,

2000 upon the ground that petitioner failed to give his

consent to a pre-permit inspection on his property. The

Notice of Permit Denial further informed petitioner that he

had a right to request an adjudicatory hearing pursuant to 6

NYCRR 621.7(f), which he did by letter dated August 3,

2000.

The hearing, which was initially scheduled for March

21, 2001, was adjourned to June 25, 2001 due to DEC staff

unavailability. When neither petitioner nor his attorney

appeared on the adjourned date of the hearing, the DEC

moved for administrative judicial intervention contending

that petitioner’s failure to appear at the re-scheduled hearing

should be considered as an abandonment or withdrawal of

his request for a hearing or a default; or alternatively, that the

DEC’s denial of petitioner’s permit application shouid be

affirmed without the need for an adjudicatory hearing upon

the ground that controlling administrative case law precluded

a hearing until petitioner consented to a pre-permit

inspection on his property. Petitioner opposed the motion

upon the grounds that the DEC failed to confirm the

adjourned hearing date and to provide proof of publication of

the notice of hearing. Petitioner’s attorney, in a letter dated

April 27, 2000, contended that the DEC could conduct a

review of petitioner’s permit application in a manner less

intrusive than a pre-permit inspection on his property,

particularly since there was an alternative method of

inspection, namely by boat, which the DEC had used in

performing prior inspections relating to petitioner’s

wetlands’ permit applications of the bottom of the bay,

adjacent to, and beneath, petitioner’s present dock.

Petitioner’s attorney further contended that conditioning a

permit upon a non-consensual pre-permit inspection on

petitioner’s property violated petitioner’s rights under the

Fourth Amendment to the U.S. Constitution.

In an undated decision (hereafter the “McBride

Ruling”) rendered on the DEC’s motion by Administrative

Law Judge Molly McBride (hereafter “ALJ”), the ALJ ruled

that there was no confirmation that petitioner’s attorney saw

the notice of the adjourned hearing and determined “Frankly,

scheduling errors occur and such a severe penalty as

requested by [DEC] Staff is not warranted here”. With

respect to the DEC’s alternate request for relief, the ALJ

determined that the DEC could not determine whether the

application met the standards for permit issuance unless it

was permitted to conduct a pre-permit inspection on

petitioner’s property; and that if it could not be determined

whether the standards had been met, petitioner’s permit

application could not be deemed complete. The ALJ

recommended that the Notice of Permit Denial be vacated

and replaced with a Notice of Incomplete Application; ruled

that petitioner’s request for a hearing be treated as void since

such a request could not be made in response to a Notice of

Incomplete Application; and concluded that there could be

no further processing of petitioner’s application until it was

complete.

In a ruling dated February 1, 2002 (hereafter the

“Commissioner’s Ruling”), the Commissioner of the DEC

(Erin M. Crotty), adopted the decision of the ALJ

commenting as follows:

“T find that the Applicant’s [petitioner] tidal wetland

application under review must be deemed incomplete

for the purposes of permit processing under the

Department’s Uniform Procedures, 6 NYCRR part

621. The Applicant’s denial of access to his property

prevented Department Staff from evaluating the on-

site conditions and the proposed project. The ability

to gather such information is necessary to make the

determination that the permit application is complete.

The applicant’s actions effectively relieves

Department Staff from taking any further action on

the permit application until access to the site and site

information is available for Staffs review. Further, |

am determining that the Applicant’s request for

hearing on its [sic.] proposed project is void until

such time as the site access and the necessary

information is made part of the permit application.

Thereafter, if and when said information is supplied

and Staffs redetermination is to deny the proposed

project, then the applicant will be afforded a hearing

on Staffs denial of the requested permit”.

Thereafter, petitioner commenced an Article 78

proceeding by service of a notice of petition and verified

petition; and subsequently served an amended verified

petition. In his amended petition, petitioner sought a

judgment annulling and vacating the Commissioner's Ruling

to the extent that it affirmed those portions of the McBride

Ruling determining that petitioner’s application was

incomplete and that petitioner’s request for a hearing was

void; and also sought review of the McBride Ruling

10

contending that (A) pursuant to 6 NYCRR 621.4(K), a pre-

permit inspection on petitioner’s property by a DEC staff

member is not one of the requirements for a complete permit

application, although petitioner had no objection to a pre-

permit inspection on petitioner’s property by a private

environmental consultant, which is expressly authorized by 6

NYCRR 621.4(K)(iii)), (B) the McBride decision violated

the provisions of ECL 70-0109(1)(a) and (b) and 6 NYCRR

621.5(b) which deem an application complete unless the

DEC mails a written notice that the application is incomplete

within 15 calendar days of its receipt of the permit

application, (C) the McBride Ruling improperly relied on an

Interim Decision of the Deputy Commissioner of the DEC

dated November 6, 2000 (the “Bath Storage decision”) in

holding that an adjudicatory hearing is not available for

review of a permit denial based on the incompleteness of the

application, and (D) the DEC’s conditioning of the issuance

of a permit upon its receipt of petitioner’s consent to a pre-

permit inspection on petitioner’s property violated

petitioner’s right against unreasonable search and seizure

under the Fourth Amendment to the United States

Constitution.

Petitioner further contended that his property does not

come within the DEC’s wetland permit jurisdiction pursuant

to ECL 15-0505(1) and 6 NYCRR 608.5; and that his permit

application should be deemed approved on the basis of the

five day demand provisions of 6 NYCRR 621.9(b) and (c).

The nisi prius court refused to consider the latter contention

upon the ground that it had not been raised at the

administrative level in reliance upon the cases of Ambry v.

1]

Bd. of Trustees of N.Y. City Fire Department, 298 A.D.2d

582 (2d Dept. 2002); and Fry v. Village of Tarrytown, 89

N.Y.2d 714 (1997)).

The nisi prius court determined that petitioner’s

contention that the DEC’s conditioning of the issuance of a

permit upon its receipt of petitioner’s consent to a pre-permit

inspection on petitioner’s property violated petitioner’s night

against unreasonable search and seizure under the Fourth

Amendment to the United States Constitution was without

merit; and held that whenever the DEC can demonstrate a

“reasonable need” for the scientific information obtainable

through a pre-permit inspection, such inspection would

constitute a valid condition to a wetlands’s permit in reliance

upon the case of 7hompson v. Department of Environmental

Conservation, 132 A.D.2d 665 (2d Dept. 1987) app. den. 71

N.Y.2d 803 (1988) and 6 NYCRR 621.15(b)).

The nisi prius court eschewed such cases as Stender

v. Albany, 188 A.D.2d 986 (3d Dept. 1992) app. dis. 81

N.Y.2d 1006 (1993); and Brookhaven v. Ronkonkoma Realty

Corp., 154 A.D.2d 665 (2d Dept. 1989) based upon its

opinion that a pre-permit inspection on petitioner’s property

constituted a “minimal intrusion” upon the property, that

petitioner had a “diminished expectation of privacy” in his

property and that a pre-permit inspection on petitioner’s

property was a matter of governmental interest in reliance

upon ECL 25-0102, 6 NYCRR 661.1, 661.9(b); and Board of

Education v. Earls, 536 U.S. 822, 829, 122 S.Ct. 2559, 153

L.Ed.2d 735 (2002)), which rulings petitioner disputed in his

12

appeals to the Appellate Division of State Supreme Court,

Second Department, and New York State Court of Appeals.

Petitioner also challenged that part of the

Commissioner’s Ruling that relieved the DEC from any

further action including a hearing on petitioner’s application

until he complied with its demand for a pre-permit inspection

on his property.

In reaching its determination, the nisi prius court

expressly found that since the Commissioner adopted the

McBride Ruling as its own, it was constrained to review the

findings in that ruling in order to determine its efficacy.

The nisi prius court found that the record established

that initially the DEC had afforded petitioner the right to a

public adjudicatory hearing in the Notice of Permit Denial

but that such hearing was adjourned because of the DEC’s

inability to proceed. Although neither the petitioner nor his

attorney appeared on the adjourned date of that hearing, the

ALJ subsequently determined that petitioner should not be

deprived of his right to an adjudicatory hearing based. merely

upon this ground.

The nisi prius court found that the ALJ, by

characterizing petitioner’s application as incomplete,

determined that no further action, including the adjudicatory

hearing, would be taken, that the ALJ’s determination

constituted error and that petitioner should have been

afforded the opportunity at an adjudicatory hearing to

demonstrate whether the DEC’s request for a pre-permit

13

inspection on petitioner’s property was reasonable and

necessary. Petitioner contends that under no circumstances

can the DEC condition the grant of a permit application upon

a non-consensual pre-permit inspection on petitioner’s

property.

Although following the submission of his tidal

wetlands’ permit application to the DEC, petitioner was

served with at least two “incomplete notices” which did not

require a pre-permit inspection on petitioner’s property,

nevertheless, the nisi prius court determined that

notwithstanding that 6 NYCRR 661.12(a)(1), 6 NYCRR

621.3 and 6 NYCRR 621.4(k) do not specifically provide for

a pre-permit inspection as a prerequisite for a complete

application, the DEC had the authority to require pre-permit

inspections based upon its general authority to request

supplemental information during the course of permit review

to enable it to make the findings and determinations required

by law, citing 6 NYCRR 621.1(d), additional information

“which is reasonably necessary to make any findings or

determinations required by law”, citing 6 NYCRR 621.15(b)

and that, the NYSDEC could fix a date for receipt of such

additional information and if it was not timely submitted it

“may be grounds for denial of the application”, citing 6

NYCRR 621.15(b).

The nisi prius court further found that in this case,

petitioner’s application could be denied upon the ground that

without a pre-permit inspection on petitioner’s property, the

DEC could not determine whether or not petitioner’s

proposal complied with the standards for permit issuance.

14

The nisi prius court ruled that petitioner, upon his

request therefor pursuant to 6 NYCRR 621.7(f), was entitled

to an adjudicatory hearing on whether or not the DEC’s

demand for a pre-permit inspection on petitioner’s property

was “reasonably necessary” to make the required findings or

determinations with regard to petitioner’s permit application;

that the ALJ’s reliance on the Bath Storage decision was

misplaced; and that petitioner was entitled to an adjudicatory

hearing pursuant to 6 NYCRR 621.7(f) at which petitioner

would have the burden of demonstrating that the DEC’s

demand for a pre-permit inspection on petitioner’s property

was not reasonably necessary in order to evaluate his

application for a wetland’s permit, but the petition was

otherwise denied.

In his appeals to the Appellate Division of New York

State Supreme Court, Second Department, and the New York

State Court of Appeals, the petitioner contended, inter alia,

that the nisi prius court’s rulings were erroneous as a matter

of law because no governmental agency may condition the

grant of a permit application upon a non-consensual pre-

permit inspection on private residential property irrespective

of whether or not it was reasonably necessary in order to

evaluate an application for a permit.

In a letter sent to petitioner dated April 7, 2000 by

Mark C. Carrara, its Deputy Permit Administrator, the DEC

admitted that it had received petitioner’s application for a

tidal wetlands’ permit “on June 7, 1999”. Approximately 36

days later, the DEC sent petitioner a Notice of Incomplete

Application dated July 13, 1999 informing petitioner that his

15

application was incomplete in that he was required to submit

photographs, project plans, a location map, a recent survey,

proof that the proposed dock extension and boat lift were

reasonable and necessary and information as to how many

boats would be moored. After it received petitioner’s

photographs, project plans and a location map on January 20,

2000, the DEC waited almost three months before sending

petitioner a second “Notice of Incomplete Application” dated

March 13, 2000 indicating that petitioner’s application was

still incomplete as he had failed to submit a recent survey of

the project site. Thereafter, by letter dated April 7, 2000, the

DEC informed petitioner that his application was complete

except for a pre-permit inspection on his property.

Following petitioner’s refusal to give his consent to a pre-

permit inspection on his property, the DEC denied his

wetlands’ permit application by “Notice of Permit Denial”

dated July 7, 2000 upon the ground that petitioner failed to

give his consent to a pre-permit inspection on his property.

The Notice of Permit Denial further informed petitioner that

he had a right to request a public hearing pursuant to 6

NYCRR 621.7(f) which he did by letter dated August 3,

2000.

LEGAL ARGUMENT

Subdivision (1) of ECL 70-0109 provides in relevant

part as follows:

“(a) On or before fifteen calendar days after the

receipt of an application for a permit which has been

filed in a manner and in a form prescribed by the

department, the department shall mail written notice

16

to the applicant of its determination whether or not

the application is complete.

“(b) If the department fails to mail written notice to

an applicant of its determination whether or not an

application is complete within such fifteen calendar

day period, the application shall be deemed

complete.”

The regulations of the DEC provide in relevant part at

6 NYCRR 621.5 as follows: “(b) The Department shall mail

notice of its determination of completeness or

incompleteness to the applicant . . . (2). . . on or before 15

calendar days after receipt of the application”; and “(f) If the

department fails to mail notice of its determination of

completeness or incompleteness to the applicant within the

time limit specified above, the application shall be deemed

complete”.

The intent of the legislature in enacting ECL 70-0109

was “to establish reasonable time periods for administrative

agency action on permits” (ECL 70-0103); and “in order to

set in motion the timetable set forth in the uniform

procedures and compel that the permit application continue

to be processed” (Heimbach v. Commisioner, 136 Misc.2d 1

(Albany Co. 1987). Any other construction would result in

permit applications being held in administrative limbo,

neither denied, granted, or processed, as occurred in the case

at bar (/d.).

In Jayntor v. NYS Department of Environmental

Conservation, 130 A.D.2d 571 (2d Dept. 1987), the court

found that a letter mailed by the DEC on August 17, 1983

within 15 days of its receipt of a permit application received

17

on August 2, 1983 was mailed timely. However, in Benlevi

v. NYS Department of Environmental Conservation, 144

A.D.2d 358 (2d Dept. 1988) appeal dismissed 74 N. Y.2d 650

(1989) the court ruled that an application for a permit must

be deemed complete because the DEC had failed to send the

petitioners a notice of incomplete application within 15 days

of the agency’s receipt of the permit application.

In the case at bar, after receiving petitioner’s permit

application on June 7, 1999, the DEC waited until July 13,

1999 before sending petitioner its Notice of Incomplete

Application, a period of 36 days. Therefore, based upon

ECL 70-0109 and 6 NYCRR §621.5, petitioner’s permit

application should have been deemed complete.

As mentioned above, the DEC received petitioner’s

photographs, project plans and a location map on January 20,

2000 but waited until March 13, 2000 to send him its second

Notice of Incomplete Application. Assuming the subsequent

submission by petitioner of photographs, project plans and a

location map constituted a re-submission of the application

or the submission of additional information, ECL §70-

0109(1)(d) provides that such submission “shall commence a

new fifteen calendar day period for department review of the

additional information for purposes of determining ©

completeness”. Therefore, the DEC failed to observe the 15

day period for mailing petitioner written notice of his

incomplete application Twice!

If petitioner’s permit application was deemed to be

complete before the DEC requested a pre-permit inspection

on petitioner’s property, the DEC cannot subsequently

require petitioner’s consent to a pre-permit inspection on his

property as a condition precedent to a completed permit

18

application. Nor can it deny petitioner a wetlands’ permit

based upon his refusal to give the DEC consent to enter upon

his property in order to conduct a pre-permit inspection. Nor

could the nisi prius court require petitioner to attend an

adjudicatory hearing for the sole purpose of determining

whether or not the DEC’s demand for a pre-permit inspection

On petitioner’s property was “reasonably necessary” for it to

make the required findings or determinations with regard to

petitioner’s permit application.

As well, the nisi prius court’s rulings were erroneous

as a matter of law because no governmental agency may

condition the grant of a permit application upon a non-

consensual pre-permit inspection on private property

irrespective of whether or not it was reasonably necessary in

order to evaluate an application for a permit; a pre-permit

inspection on petitioner’s property by a DEC staff member is

not one of the requirements for a complete permit

application; petitioner had no objection to a pre-permit

inspection on his property by a private environmental

consultant, which is expressly authorized by 6 NYCRR

621.4(K)(iii); that the DEC by conditioning the issuance of a

permit upon its receipt of petitioner’s consent to a pre-permit

inspection on his property violated petitioner’s right against

unreasonable search and seizure-under the Fourth

Amendment to the United States Constitution; that

petitioner’s property does not come within the DEC’s

wetland permit jurisdiction pursuant to ECL 15-0505(1) and

6 NYCRR 608.5; and that petitioner’s permit application

should have been deemed approved on the basis of the five

day demand provisions of 6 NYCRR 621.9(b) and (c).

An ordinance that requires an owner of residential

property to submit to an inspection of his property violates

19

the owner’s right to be free from searches as guaranteed by

the Fourth Amendment to the United States Constitution

(See Camara v. Municipal Court of San Francisco, 387 U.S.

523, 540, 87 S.Ct. 1727, 18 L.Ed.2d 930 (1967); Sokolov v.

Village of Freeport, 52 N.Y.2d 341 (1981) (an intrusion

upon a Citizen’s property as a condition precedent to the

issuance of a permit is impermissible), Town of Brookhaven

v. Ronkonkoma Realty Corp., 164 A.D.2d 665 (2d Dept.

1989) (The Town of Brookhaven may not compel a property

owner to submit to a physical inspection of his premises, nor

may it penalize the owner for failing to comply with the

permit requirements of the Zoning Code).

The lower courts applied the “special needs” doctrine

to this case. Previously, this doctrine had only been applied

to “extraordinary situations” (United States v. Paulino, 850

F.2d 93, 97 (2d Cir. 1988)); commercial enterprises, public

facilities governed by regulatory schemes and to the living

spaces of paroles. “Neither the Supreme Court nor this Court

has ever permitted warrantless administrative searches of a

person’s residence unless: exigent circumstances exist[ed],

business was conducted in the home, or the search was

directed at convicted felons still serving sentences of

probation or parole” (Anobile v. Pelligrino, 303 F.3d 107,

120 (2d Cir. 2002) (emphasis supplied); Michigan v.

Clifford, 464 U.S. 287, 291-92, 104 S.Ct. 641, 78 L.Ed.2d

477 (1984)).

The “special needs” exception has never before been

applied to inspections of private property and its owners who

have absolutely no criminal involvement.

Warrantless searches are permissible only when there

exists an immediate and weighty public need to sacrifice the

20

Fourth Amendment protections afforded our citizens

(Michigan v. Clifford, supra. at 464 U.S. 293 (fire fighters

may enter a burning building to “fight the blaze’’)).

The threshold issue to be determined in any given

case is whether or not a “special need” actually exists. If

there exists no “special need” beyond the normal need for

law enforcement, application of the “special need” exception

cannot be justified (Nicholas v. Goord, No. 01 Civ. 7891,

2003 U.S. Dist. LEXIS 1621, at *50 (S.D.N.Y. February 6,

2003); New Jersey v. T.L.O., 469 U.S. 325, 342, 105 S.Ct.

733, 83 L.Ed.2d 720 (1985) because “the delay inherent in

obtaining a warrant would make it more difficult for

probation officials to respond quickly to evidence of

misconduct (citation omitted) and would reduce the deterrent

effect that the possibility of expeditious searches would

otherwise create (citation omitted)” (Griffin v. Wisconsin,

483 U.S. 868, 873, 107 S.Ct. 3164, 9 L_Ed.2d 709 (1987)).

Therefore, under Griffin, absent some urgency to perform a

search without a warrant and a concomitant need to deter

criminal activity, there can exist no “special need” beyond

the normal need for law enforcement, particularly where, as

here, the DEC conditioned the issuance of a wetlands’ permit

upon petitioner’s consent to an otherwise illegal inspection

of his private residential property.

Every case in which this Court applied the “special

needs” exception involved (1) some urgency to perform the

search without a warrant and (2) the need to deter some

criminal or other pernicious activity (New Jersey T.L.O.,

supra.), Vernonia School District 47J v. Acton, 515 U.S.

646, 654-661, 115 S.Ct. 2386, 132 L.Ed.2d 564 (1995);

Board of Education v. Earls, 536 U.S. 822, 122 S.Ct. 2559,

153 L.Ed.2d 735 (2002) (a case relied upon by the nisi prius

21

court that involved drug testing); Griffin v. Wisconsin,

supra., United States v. Knights, 534 U.S. 112, 122 S.Ct.

587, 151 L.Ed.2d 497 (2001); United States v. Newton, 181

F.Supp.2d 157 (E.D.N.Y. 2002); Skinner v. Railway Labor

Executive ’s Assn., 489 U.S. 602, 109 §.Ct. 1402, 103

L.Ed.2d 639 (1989); National Treasury Employees Union v.

Von Raab, 489 U.S. 656, 109 S.Ct. 1384, 103 L.Ed.2d 685

(1989); Leventhal v. Knapek, 266 F.3d 64 (2d Cir. 2001)).

The “special needs” exception should not be routinely

invoked whenever a warrantless inspection is required

pursuant to a “regulatory scheme”; it should not be invoked

in the absence of a need beyond the normal need for law

enforcement; it should not be invoked unless the warrant and

probable-cause requirement is impracticable; it should not be

invoked absent any need to deter criminal activity; it should

not be invoked absent some urgency to perform the search

without a warrant; and it should not be invoked against an

ordinary citizen by making entry upon his property a

condition to the issuance of a tidal wetlands’ permit, which

in this case the DEC has sought to do.

The nisi prius court ruled that the DEC had a

“reasonable need” that outweighed the plaintiff's expectation

of privacy. However, application of the “special needs”

exception requires a threshold analysis whether there exists

any “special need”, and it cannot be assumed that every

governmental regulation gives birth to a “special need” as a

condition precedent to the issuance of a permit. Even if the

DEC did have a legitimate “special need” beyond the normal

need for law enforcement to make the warrant and probable-

cause requirement impracticable, the inquiry does not end

there since “[e]ven where a court concludes that a statute or

program qualifies as a ‘special need, beyond the normal need

22

for law enforcement,’ the reasonableness of the intrusion

must still be evaluated through a balancing analysis”

(Nicholas v. Goord, supra.).

The U.S. Supreme Court has articulated three factors

to be considered in determinating whether governmental

intrusion upon the individual’s expectation of privacy is

justified by the “special needs” of the government: (1) the

nature of the privacy interest upon which the search intrudes,

(2) the character of the intrusion that is complained of and

(3) the nature and immediacy of the governmental concern at

issue, and the efficacy of the means for meeting it (Vernonia

Sch. Dist. 47J v. Acton, supra.; Bd. of Educ. v. Earls, supra.).

None of these factors supports an extension of the

“special needs” exception to the DEC’s requirement that it be

permitted to invade petitioner’s property as a condition

precedent to its issuance to petitioner of a wetlands’ permit.

The right to exclude government agents from the home and

the curtilage surrounding the home is the bed rock of Fourth

Amendment jurisprudence. That protection is being violated

by the DEC when it required petitioner to consent to a pre-

permit inspection on his property as a condition to the

issuance to petitioner of a wetlands’ permit. The purpose

served by this entry - inspection requirement of the permit

granting process - was neither weighty nor immediate.

Application of the balancing test to this case weighs

heavily against applying a novel and far reaching extension

of the “special needs” exception in order to negate

petitioner’s Fourth Amendment rights.

It is palpable that the nature of the DEC’s

governmental interest does not warrant application of the

“special needs” exception and the opinion of the nisi prius

court in this case does not recite a single legitimate

governmental interest that would have been compromised

had it refused to refer the issue to administrative review, let

alone to have placed the burden of proof upon the petitioner

to demonstrate that a pre-permit inspection on his property

was not reasonably necessary. Although the lower courts

perceived an interest to perform a regulatory inspection in

order to protect the natural resources and the public beaches

and waterways, no pellucid reason is given why such interest

is, in any way, compromised unless petitioner’s Fourth

Amendment protections are compromised. No cogent reason

has been advanced why the warrant and probable-cause

requirement is impracticable. No reason has been suggested

why violating petitioner’s Fourth Amendment rights, in any

way, protects the natural resources and the public beaches

and waterways.

Inherent in the lower courts’ opinions is the fact that

the DEC lacked any immediate need to inspect petitioner’s

property. If there existed no immediate need to inspect

petitioner’s property, it would logically follow that no

governmental interest would be at stake requiring the lower

courts to abide the DEC’s violation of petitioner’s Fourth

Amendment protections; and, there existed no reason for the

DEC to forego the warrant requirement of the Fourth

Amendment (Board of Education v. Earls, supra. at 536 U.S.

836); Vernonia School District 47J v. Acton, supra. at 515

U.S. 662-663); Griffin v. Wisconsin, supra. at 483 U.S. 876;

O’Connor v. Ortega, 480 U.S. 709, 724, 107 S.Ct. 1492, 94

L.Ed.2d 714 (1987)).

In this case, there is no evidence in the record that

petitioner had begun construction or was otherwise engaged

24

in conduct that could potentially damage the wetlands. All

of the parties agreed, including petitioner, that construction

could not commence absent a permit; and, it is undisputed

that the DEC had adamantly refused to grant petitioner a

permit unless he gave his consent to a pre-permit inspection

on his property, which petitioner, just as adamantly, refused

to give the DEC.

Without doubt, petitioner’s home and curtilage are

entitled to the most stringent Fourth Amendment protection.

The lower courts’ attempt to minimize any intrusion upon

petitioner’s property ignores facts that are critical to an

appropriate analysis of petitioner’s Fourth Amendment

. protections. The entry by DEC personnel upon petitioner’s

property as a condition precedent to the issuance of a

wetlands’ permit raises serious Fourth Amendment concerns

that cannot be characterized as de minimus (Camara v.

Municipal Court of San Francisco, supra. at 387 U.S. 530-

31 (“even the most law-abiding citizen has a very tangible

interest in limiting the circumstances under which the

sanctity of his home may be broken by official authority”)).

The lower courts opined that petitioner had a

diminished expectation of privacy in the curtilage around his

home. It is an elemental proposition, which petitioner does

not dispute, that private areas of a home or curtilage visible

to members of the public are not protected from inspection

by governmental agents so long as they do not enter upon the

property and view such private areas from a permissible

vantage point such as a public road or waterway (United

States v. Knotts, 460 U.S. 276, 103 S.Ct. 1081, 75 L.Ed.2d

55 (1983); California v. Ciraolo, 476 U.S. 207, 213, 106 St.

Ct. 1809, 90 L.Ed.2d 210 (1986); Dow Chemical Co. v.

25

United States, 476 U.S. 227, 106 S.Ct. 1819, 90 L.Ed.2d 226

(1986)).

However, quite plainly, even if a person’s living

room can be seen from the street by passers-by through a

glass window, that fact does not permit entry of the home by

governmental agents because physical entry upon the

property is much more intrusive than a mere visual

inspection from the periphery (Dow Chemical Co. v. United

States, supra. at 237 (finding that aerial inspection of area in

question was permissible but stating that “[a]ny actual

physical entry by [the] EPA into any enclosed area would

raise significantly different questions”); United States v.

Hatfield, 333 F.3d 1189, 1198 (10th Cir. 2003) (explaining

that if the officer had “physically invaded the curtilage to

make his observation, that would have constituted a search

subject to the proscriptions of the Fourth Amendment’);

United States v. Jenkins, 124 F.3d 768, 774 (6" Cir. 1997)

(“Visual inspection from a lawful vantage point, however, is

quite different from the physical assault on defendants’

backyard that occurred in this case”); United States v. Reilly,

76 F.3d 1271, 1279 (2d Cir. 1996) (noting the fact that

information was gathered “only after the officers invaded the

area” put that case in “stark contradistinction to the situation

in Dunn, where the officers stood outside the protected

curtilage”); Florida v. Riley, 488 U.S. 445, 449 (1989)

(“[T]he home and its curtilage are not necessarily protected

from inspection that involves no physical invasion. . . As a

general proposition, the police may see what may be seen

‘from a public vantage point where [they have] a right to

be’”); California v. Ciraolo, supra. at 476 U.S. 213 (“The

Fourth Amendment protection of the home has never been

extended to require law enforcement officers to shield their

eyes when passing by a home on public thoroughfares. Nor

26

does the mere fact that an individual has taken measures to

restrict some views of his activities preclude an officer’s

observations from a public vantage point where he has a right

to be. . .”)).

In this case, the DEC refused to inspect the bottom of

the Great South Bay adjacent to, and beneath, a dock

extending approximately 92 feet into the bay and insisted

that it be permitted to enter upon petitioner’s property to

conduct the inspection. The lower courts’ overly dismissive

view of the physical intrusion that would have occurred in

this case trivializes the importance of the Fourth Amendment

protections at stake. The fact that the inspection at issue in

this case would involve a mere intrusion upon petitioner’s

privacy does nothing to excuse the constitutional violation,

as the lower court propounds, but rather exacerbates it

(Camara v. Municipal Court of San Francisco, supra. at 387

U.S. at 531 (“the possibility of criminal entry under the guise

of official sanction is a serious threat to personal and family

security”).

There exists no case that suggests that a trespass, de

minimus or otherwise, into an individual’s backyard does not

constitute a Fourth Amendment violation since “any

unauthorized physical penetration [is] a search” (Reed v.

Schneider, 612 F.Supp. 216, 220 (E.D.N.Y. 1985)).

27

CONCLUSION

The petition should be granted.

Respectfully submitted,

R. Bertil Peterson

Counsel of Record

Attorney for Petitioner and

Staff Counsel for

The Coalition of Landlords,

Homeowners & Merchants, Inc.

Attorney for Petitioner

28 East Main Street

Babylon, New York 11702

(631) 376-2110

28

Appendix A - Decision of the Court of Appeals, State

New York, Dated and Entered November

21, 2006 [1a - 2a]

STATE OF NEW YORK

COURT OF APPEALS

At a session of the Court, held at

Court of Appeals Hall in the City

of Albany of the twenty-first day

of November, 2006

PRESENT, HON. JUDITH KAYE, Chief Judge, presiding

2-10 Mo. No. 1016

In the Matter of Paul Palmieri,

Appellant,

¥:

New York State Department of

Environmental Conservation et al.,

Respondents.

The appellant having filed notice of appeal and a

motion for leave to appeal to the Court of Appeals in the

above cause, papers having been submitted thereon and due

deliberation having been thereupon had, it is

ORDERED, on the Court’s own motion, that the

appeal be and the same hereby is dismissed, without costs,

upon the ground that the order appealed from does not finally

-la-

Appendix A

[Decision of the Court of Appeals, State of

New York, Dated and Entered November 21, 2006]

determine the proceeding within the meaning of the

Constitution; and it is

ORDERED, that the said motion for leave to

appeal be and the same hereby is denied.

S/

; Stuart M. Cohen

Clerk of the Court

Appendix B - Decision of the Appellate Division, Second

Department, State of New York, Dated and

Entered July 18, 2006 [3a - Sa]

APPELLATE DIVISION

SECOND DEPARTMENT

In the Matter of Paul Palmieri,

Appellant,

V.

New York State Department of

Environmental Conservation et al.,

Respondents.

Docket No. 2004 - 5943

Suffolk Co. Index No. 3925/02

2006 NY Slip Op 5793; 31 A.D.3d 645

820 N.Y.S.2d 77, 2006 N.Y. App. Div. LEXTS 9378

In a proceeding pursuant to CPLR article 78 to

review a determination of the New York State Department of

Environmental Conservation pursuant to Environmental

Conservation Law articles 15 and 25 that, inter alia, the

petitioner’s application for a permit to extend his dock was

incomplete, the petitioner appeals, as limited by his brief,

from stated portions of a judgment of the Supreme Court,

Suffolk county (Baisley, J.), dated July 25, 2003, which, inter

alia, upon, in effect, determining that the petitioner’s wetland

permit was complete, directed an administrative hearing on

the issue of whether an inspection of his property by the

Appendix B

[Decision of the Appellate Division, Second Department,

State of New York, Dated and Entered July 18, 2006]

Department of Environmental Conservation was reasonably

necessary.

Ordered that the judgment is affirmed insofar as

appealed from, with costs.

The Supreme Court, in effect, determined that the

petitioner’s wetlands permit application was complete.

However, the fact that an application is complete does not

preclude the Department of Environmental Conservation

(hereinafter the DEC) from requesting supplemental

information, including an on-site inspection, during the

postcompletion review of an application (see 6 NYCRR

621.1[c]; 621.7[f]; 621.15[b]; Matter of Benlevi Obedian &

Benlevi v. New York State Dept. of Envtl. Conservation, 144

AD2d 358, 361 [1988]; Matter of Atlantic Cement Co. v.

Williams, 129 AD2d 84, 90 [1987]). Under the

circumstances of this case, the Supreme Court properly

directed an [*2] administrative hearing on the issue of

whether an inspection of the petitioner’s property was

reasonably necessary.

Contrary to the petitioner’s contention, the Fourth

Amendment to the United States Constitution does not bar a

warrantless inspection of his premises (see Palmieri v.

Lynch, 392 F3d 73 [2004], cert denied 546 US _, 126SCt

424 [2005]; see also Vernonia School Dist. 47J Acton, 515

US 646 [1995]; Matter of Thompson v. Department of Envil.

Conservation of State of NY, 132 AD2d 665 [1987]). A

-4a-

Appendix B

[Decision of the Appellate Division, Second Department,

State of New York, Dated and Entered July 18, 2006]

request by the DEC for an on-site inspection of the wetlands

and adjacent areas on his property, in order to review the

accuracy and impact of the petitioner’s permit application,

fell within the special needs exception to the Fourth

Amendment’s warrant requirement (see Palmieri v. Lynch,

supra). In this instance, the state’s interest in protecting

wetlands is strong. Moreover, the petitioner’s expectation of

privacy was diminished by the fact that his yard was open

and exposed to the Great South Bay, that he applied for a

permit to build in tidal wetlands, that he had previously

consented to periodic inspections, and that the inspection

would be a minimal intrusion (id; see also Vernonia School

Dist. 47J v. Acton, supra; Matter of Thompson v.

Department of Envtl. Conservation of State of N.Y., supra).

The petitioner’s remaining contentions are without

merit (see Matter of Northern Metro. Residential Healthcare

Facility, Inc. v. Novello, 24 AD3d 1069, 1071 n 1 [2005];

DiCarlo v. City of New York, 286 AD2d 363, 365 [2001];

Matter of Calm Lake Dev. v. Town Bd. of Town of

Farmington, 213 AD2d 979 [1995]). Florio, J.P., Crane,

Ritter and Fisher, JJ., concur.

Appendix C - Judgment of Supreme Court, State

of New York, County of Suffolk,

Dated July 25, 2003 and Entered

August 8, 2003 [6a - 9a]

At an IAS Term, Part 36 [of]

the Supreme Court of the State

of New York, held in and for

the County of Suffolk, at the

Supreme Court, Riverhead,

New York on the 25" day of

July, 2003

SUPREME COURT OF THE STATE OF NEW YORK

COUNTY OF SUFFOLK

Paul Palmieri,

Petitioner, Index No.

02-03925

V.

Baisley, J.

New York State Department of

Environmental Conservation;

ERIN M. CROTTY, Commissioner;

and MOLLY T. McBRIDE, JUDGMENT

Administrative Law Judge,

Respondents.

Petitioner Paul Palmieri, by his attorney Law Offices

of Timothy M. McEnaney, Esq., staff counsel to the

Coalition of Landlords, Homeowners, and Merchants, Inc.,

having commenced a proceeding under CPLR Article 78 on

-6a-

Appendix C

[Judgment of Supreme Court, State of New York, County

of Suffolk, Dated July 25, and Entered August 8, 2003]

March 4, 2002, by the filing of a notice of petition and

verified petition, and respondents having duly appeared by

Eliot Spitzer, Attorney General, State of New York, by

Gregory J. Nolan, Assistant Attorney General, and petitioner

having then served and filed an amended verified petition

dated April 2, 2002, challenging a Department of

Environmental Conservation (“NYSDEC”) Ruling of the

Commissioner dated February 1, 2002, which ruling

determined that petitioner’s application for a permit to

extend a dock and install additional boatlifts was incomplete

because petitioner refused to allow agency staff to inspect the

site of the proposed project; and respondents having served

and filed a verified answer to the amended petition dated July

22, 2002, together with a copy of the administrative record of

said Ruling and an affirmation in opposition to the petition of

Assistant Attorney General Gregory J. Nolan dated July 22,

2002, with exhibits, and a memorandum of law in opposition

to the petition; and petitioner having served and filed a reply

affirmation dated August 26, 2002, with exhibits, made by

Joseph F. Battista, Esq., of counsel to petitioner’s counsel,

together with an affidavit of petitioner sworn to on August

26, 2002, with exhibits, which reply asserted a new claim, to

wit, that petitioner was entitled to a permit because of an

alleged “five day demand letter” sent pursuant to ECL

Section 70-0109.3(b) and 6 NYCRR Section 621.9(b); and

respondents having served and filed (after obtaining leave of

court with consent of petitioner’s counsel) a sur-reply

memorandum of law in opposition to the petition dated

December 4, 2002 together with affidavits in support of the

sur-reply, with exhibits, sworn to by William R. Adriance on

-Ja-

Appendix C

{Judgment of Supreme Court, State of New York, County

of Suffolk, Dated July 25, and Entered August 8, 2003]

December 3, 2002, Michael A. Mascelli on December 4,

2002, Emily Limbach on December 4, 2002, and an

affirmation with exhibits in support or the sur-reply made by

Gregory J. Nolan, Esq. on December 4, 2002; and petitioner

having served and filed a “Second reply Affirmation” dated

January 15, 2003 made by Joseph F. Battista, Esq., of

counsel to petitioner’s counsel, together with an affidavit of

petitioner sworn to on January 15, 2003, with exhibits; and

petitioner having submitted additional exhibits to the court

under cover of correspondence dated February 20, 2003; and

the court, after due deliberation, on the 5" day of May, 2003,

having made and filed a Memorandum decision [sic.] (a copy

of which is annexed hereto and made a part hereof)

determining that the DEC had jurisdiction to either grant or

deny a tidal wetlands permit for petitioner’s proposed

project, that NYSDEC’s attempt to enforce a non-consensual

site inspection of petitioner’s property did not violate

petitioner’s constitutional rights; that petitioner’s claim for a

permit based on the five day demand provisions of 6

NYCRR Section 621.9(b)(c) had not been raised at the

administrative level and so was not considered by the court;

and that when petitioner’s permit application was denied on

the ground that without a site inspection NYSDEC cold not

determine whether or not the petitioner’s proposal complied

with the standards for permit issuance, petitioner was entitled

to an adjudicatory hearing pursuant to 6 NYCRR Section

621.7(f),

NOW, on motion of Eliot Spitzer, Attorney General

of the State of New York and attorney for respondents, it is

-Sa-

Appendix C

[Judgment of Supreme Court, State of New York, County

of Suffolk, Dated July 25, and Entered August 8, 2003]

ADJUDGED, DECREED, AND DECLARED, that

the petition is granted to the extent that petitioner is held to

be entitled to an adjudicatory hearing pursuant to 6 NYCRR

Section 621.7(f); and its is further

ORDERED, ADJUDGED AND DECREED, that the

petition is otherwise denied, and it is further

ORDERED, ADJUDGED AND DECREED, that the

petition [sic.] shall have the burden at such hearing of

demonstrating that NYSDEC’s demand for an on-site

inspection of the petitioner’s property is not reasonably

necessary in order to evaluate the petitioner’s application for

a wetlands permit (6 NYCRR Section 624.9(b)(1).

ENTER

GRANTED

JUL 25, 2003

S/ _ Paul J. Baisley, Jr.

Edward P. Romaine J.S.C.

Clerk of Suffolk County

-9a-

Appendix D - Memorandum Decision of Supreme Court,

State of New York, County of Suffolk,

Dated and Filed May 5, 2003 [10a - 21a]

MEMORANDUM

SUPREME COURT, SUFFOLK COUNTY LA.S. PART 36

Paul Palmieri, By: Baisley, J.S.C.

Petitioner, Dated: May 5, 2003

V. Index No. 02-3925

New York State Department of Mot. Seq. #001-

Environmental Conservation; ERIN SDISPSJ

M. CROTTY, Commissioner;

and MOLLY T. McBRIDE, Return Date: 4-3-02

Administrative Law Judge, Adjourned: 1-16-

03

Respondents.

TIMOTHY M. McENANEY, ESQ.

Attorney for the Plaintiffs

28 East Main Street

Babylon, New York 11702

ELIOT SPITZER, ESQ.

New York State Attorney General

By: Gregory J. Nolan, Esq.

120 Broadway, 26" Floor

New York, New York 10271-0332

-10a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003}

This Article 78 proceeding arises out of respondent’s

denial of petitioner’s application for a tidal wetland permit.

The petitioner owns property located in Babylon, New York

which adjoins the Great South Bay. The property is

improved by the petitioner’s house and backyard fencing.

The rear of the property, which is adjacent to the water, is

improved with a bulkhead, a 92 foot long dock extending

outward from the bulkhead and three boat lifts.

In 1991 the petitioner applied for and was granted

tidal wetlands permits for the reconstruction of a bulkhead

and construction of a 30 foot by 10 foot ramp, a 5 foot by 45

foot float and pilings and a 52 foot fixed pier with additional

pilings and two boat lifts. Following construction of these

improvements and in January of 1993, the petitioner applied

for another tidal wetlands permit to extend the existing 52

foot dock an additional 110 feet and to add two more boat

lifts. This application was denied by the respondent, the

New York State Department of Environmental Conservation

(NYSDEC), on November 4, 1993. Following the

petitioner’s request for an administrative hearing, a

settlement was reached wherein it was greed that a permit

would be issued for a dock extension of 40 feet and for

construction of an additional boat lift (Administrative

Record, pages 22-23).

The petitioner submitted the current application for a

tidal wetlands permit in May of 1999. He sought to extend

the existing 92 foot dock by 50 feet and to add another boat

lift. By a NOTICE OF INCOMPLETE APPLICATION

-lla-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

(Incomplete Notice) dated July 13, 1999, NYSDEC informed

the petitioner that his application was incomplete in that he

was required to submit photographs, project plans, a location

map, a recent survey, proof that the proposed dock extension

and boat lift were reasonable and necessary and information

as to how many boats would be moored (Administrative

Record, page 56). The petitioner was served with a second

“Notice of Incomplete Application” (Second Incomplete

Notice) which indicated that his application was still

designated as incomplete as he had failed to submit a recent

survey of the project site (Administrative Record, page 64).

By letter dated April 7, 2000, NYSDEC informed the

petitioner that his application was complete except for an on- —

site inspection. Following petitioner’s continued refusal to

allow NYSDEC to conduct an on-site inspection, NYSDEC

denied the permit application by “Notice of Permit Denial”

(Notice of Denial), dated July 7, 2000. NYSDEC denied the

application on the ground that the petitioner failed to allow

NYSDEC to conduct an on-site inspection of the property.

The Notice of Deiiial further informed the petitioner that he

had a right to a public hearing pursuant to NYCRR 621.7(f).

Subsequently, the petitioner requested a hearing on the denial

of the permit.’ The hearing, which was initially scheduled

for March 21, 2001, was adjourned to June 25, 2001 because

of NYSDEC staff unavailability. Neither the petitioner nor

his attorney appeared at the adjourned hearing.

l. In NYSDEC’s request for a hearing, it indicated that a

Notice of Complete Application was not required since the

proposed activity was classified as a minor project.

-12a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003}

NYSDEC then moved for administrative judicial

intervention. On the motion NYSDEC contended that the

petitioner’s failure to appear at the re-scheduled hearing

should be considered as an abandonment or withdrawal of

the request for a hearing or a default. NYSDEC contended

alternatively, that NYSDEC’s denial of the permit

application should be affirmed without the need for an

adjudicatory hearing on the ground that controlling

administrative case law precludes a hearing until petitioner

consents to an on site inspection. Petitioner opposed the

motion on the grounds that NYSDEC failed to confirm the

adjourned hearing date and to provide proof of publication of

the notice of hearing.’

An undated decision was rendered on the petitioner’s

motion by Administrative Law Judge Molly McBride (ALJ,

the “McBride Ruling”). Initially, the ALJ determined that

there was no confirmation that petitioner’s attorney saw the

notice of the adjourned hearing. The ALJ further determined

“Frankly, scheduling errors occur and such a sever penalty as

requested by Staff [NYSDEC] is not warranted here”

(Administrative Record, page 7). With regard to NYSDEC’s

2. Petitioner's attorney, in a letter dated Apn! 27, 2000,

contended that NYSDEC could conduct a review of the

permit application in a manner less intrusive than an on-

site inspection, particularly where there is an alternative

method of inspection such as from a waterway

Petitioner’s attorney further contended that a non-

consensual on-site inspection was tantamount to an illegal

warrantless search.

-|3a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

alternate request for relief, the ALJ determined that

NYSDEC could not determine whether the application met

the standards for permit issuance without conducting an on-

site inspection. The ALJ decided that if it cannot be

determined whether the standards have been met, then the

application cannot be deemed complete. The ALJ

recommended that the Notice of Denial be vacated and

replaced with a Notice of Incomplete Application. The ALJ

further recommended that the petitioner’s request for a

hearing be treated as void since such a request could not be

made in response to a Notice of Incomplete Application.

The ALJ concluded that there could be no further processing

of the petitioner’s application until it was complete.

In a Ruling dated February 1, 2002, the respondent

Erin M. Crotty as the Commissioner of NYSDEC, adopted

the decision of the ALJ (the Commissioner’s Ruling). The

Commissioner commented in the Ruling:

“T find that the Applicant’s tidal wetlands application

under review must be deemed incomplete for the

purposes of permit processing under the

Department’s Uniform Procedures, 6 NYCRR part

621. The Applicant’s denial of access to his property

prevented Department Staff from evaluating the on-

site conditions and the proposed project. The ability

to gather such information is necessary to make the

determination that the permit application is complete.

The Applicant’s actions effectively relieves

Department Staff from taking any further action on

-14a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

the permit application until access to the site and site

information is available for Staffs review. Further, I

am determining that the Applicant’s request for

hearing on its proposed project is void until such time

as the site access and the necessary information is

made part of the permit application. Thereafter, if

and when said information is supplied and Staffs

redetermination is to deny the proposed project, then

the Applicant will be afforded a hearing on Staffs

denial of the requested permit” (Administrative

Record, pages 2 to 3).

Petitioner then commenced this special proceeding by

service of a notice of petition and verified petition.

Petitioner subsequently served an amended verified petition.

Petitioner seeks in the amended petition a judgment

annulling and vacating the Commissioner’s ruling to the

extent it affirms those portions of the McBride ruling

determining that the petitioner’s application was incomplete

and that the petitioner’s request for a hearing was void.

Petitioner also seeks a review of the McBride Ruling.

Petitioner contends that: (i) pursuant to 6 NYCRR 621.4(k),

an on-site inspection by a NYSDEC staff member is not one

of the requirements for a complete permit,’ (ii) the McBride

decision violates the provisions of ECL 70-0109(1)(a)(b) and

6 NYCRR 621.5(b) which deem an application complete

3. Petitioner avers that he has no objection to an on-site

inspection by a private environmental consultant pursuant

to 6 NYCRR 621.4(k)(iii).

-15a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

unless NYSDEC mails a Written [sic.] notice that the

application is incomplete within 15 calendar days, (ii) the

ALJ in the McBride Ruling improperly relied on an Interim

Decision of the Deputy Commissioner of NYSDEC, dated

November 6, 2000 (the Bath Storage decision) in holding

that an adjudicatory hearing is not available for review of a

permit denial based on the incompleteness of the application,

and (iv) NYSDEC’s attempt to enforce a non-consensual,

warrantless site inspection violates petitioner’s right against

unreasonable search and seizure under the Fourth

Amendment of the United States Constitution. Petitioner

further contends that his property does not come wthin

NYSDEC’s wetland permit jurisdiction pursuant to ECL

[15-]0505(1) and 6 NYCRR 608.5.

- Petitioner’s claim that NYSDEC lacked jurisdiction

to either grant or deny a tidal wetlands permit for the

petitioner’s project is considered first. Article 25 of the

4. Petitioner’s attorney also contended in the reply

affirmation that the permit application should be deemed

approved on the basis of the five day demand provisions

of 6 NYCRR 621.9(b)(c). The Court did not consider this

contention since the issue was not raised at the

administrative level (Ambry v. Bd. of Trs. of N.Y. City

Fire Dep't, 298 A.D.2d 582, 748 N.Y.S.2d 681 [2002)).

The cases cited by the petitioner to the contrary are

inapposite since this issue does not relate to whether the

Court has subject matter jurisdiction over this Article 78

proceeding (Cf, Fry v. Village of Tarrytown, 89 NY2d

714, 658 N.Y.S.2d 205 (19971) (sic.).

-16a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003}

Environmental Conservation Law (Tidal Wetlands Act) was

enacted as an expression of the State’s public policy “to

preserve and protect tidal wetlands. . . ” (ECL 25-0102).

Although the provisions of ECL 0505(1) and 6 NYCRR

608.5 acknowledge the Towns’ control over the wetlands in

the Counties of Nassau and Suffolk, these provisions should

not be interpreted to preclude joint control over the issuance

of wetland permits by the respective governmental entities

(see, Huntington v. Albicocco, 66 AD2d 886, 411 NYS2d

675 [1978]). The provisions of Article 25 specifically state

that the tidal wetland permits issued by NYSDEC shall be in

addition to, and not in lieu of, any such permits required by

the affected local municipality (ECL 25-0401(1); Weinberg,

Practice Commentaries, McKinney’s Cons Laws of NY,

Book 17 1/2, ECL Section 25-0401, p. 433; see, 6 NYCRR

661.3).

Petitioner’s contention that NYSDEC’s attempt to

enforce a non-consensual site inspection of his property

violates his constitutional rights is also without merit.

Where NYSDEC can demonstrate a reasonable need for the

scientific information obtained by an on-site inspection, such

inspections may be valid criteria for a wetlands permit

(Thompson v. Department of Environmental Conservation,

132 AD2d 665, 518 NYS2d 36 [19871 [sic.] app. den. 71

NY2d 803, 527 NYS2d 769; see, 6 NYCRR 621.15(b)). The

cases cited by the petitioner (see Stender v. Albany, 188

AD2d 986, 592 NYS2d 70, 547 NYS2d 68 [1992], app. dis.

81 NY2d 1006, 599 NYS2d 805; Brookhaven v. Ronkoma

[sic.] Realty Corp., 154 AD2d 665, [19891) [sic.] are

-17a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

inapposite in that an on-site inspection is a minimal intrusion

and petitioner’s project poses a diminished expectation of

privacy and as well is a matter of significant governmental

interest (ECL 25-0102; 6 NYCRR 661.1, 661.9(b)(1); see Bd

of Educ. v. Earls, 536 US 822, 829, 122 § Ct 2559, 153 L Ed

2d 735 [2002]).

Petitioner’s other contentions in effect challenge that

part of the Commissioner’s Ruling that NYSDEC is relieved

from any further action including a hearing on the

petitioner’s application until he complies with its demand for

an on-site inspection. In reaching this determination the

Commissioner adopted the McBride Ruling as his own.

Accordingly, in order to determine the efficacy of the

Commissioner’s Ruling, the court must review the findings

in the McBride Ruling.

The record establishes that initially NYSDEC

afforded the petitioner the right to a public adjudicatory

hearing in the Notice of Denial. This hearing was adjourned

because of NYSDEC’s inability to proceed. Although

neither the petitioner nor his attorney appeared at the

adjourned date of the hearing, the ALJ subsequently

determined that petitioner should not be deprived of his right

to a hearing on this ground. The ALJ, by characterizing the

petitioner’s application as incomplete, determined that no

further action, including the adjudicatory hearing, could be

taken. The Court finds that this was error and petitioner _

should have been afforded the opportunity at an adjudicatory

-18a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

hearing to demonstrate whether NYSDEC’s request for an

on-site inspection was reasonable and necessary.”

Following petitioner’s submission of his tidal

wetlands permit, he was served with the Incomplete Notices

which did not require an on-site inspection. The

requirements for a complete application are listed in 6

NYCRR 661.12(a)(1), 6 NYCRR 621.3 and under the

circumstances of this case, also in 6 NYCRR 621.4(k).

Although these sections do not specifically provide for an

on-site inspection as a prerequisite for a complete

application, NYSDEC has the general authority to request

supplemental information during the course of permit review

to enable it [to] make the findings and determinations

required by law (6 NYCRR 621.1(d)). NYSDEC may also

request during the permit review process additional

information “which is reasonably necessary to make any

findings or determinations required by law” (6 NYCRR

621.15(b), emphasis added). NYSDEC may fix a date for

receipt of the additional information and if the information is

3 The ALJ found that NYSDEC could not determine if the

petitioner’s application met the standards for permit

issuance without an on-site inspection. This finding was

premature, not having been based on evidence adduced

in an adjudicatory hearing.

-19a-

Appendix D

[Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003}

not timely submitted it “may be grounds for denial of the

application” (6 NYCRR 621.15(b), emphasis added).°

Here petitioner’s application was denied on the

ground that without a site inspection NYSDEC could not

determine whether or not the petitioner’s proposal complied

with the standards for permit issuance. Petitioner, upon his

request pursuant to 6 NYCRR 621.7(f), was entitled to an

adjudicatory hearing on whether or not NYSDEC’s demand

for an on-site inspection was reasonably necessary to make

the required findings or determinations with regard to the

petitioner’s permit application. The ALJ’s reliance on the

Bath Storage decision is misplaced. the Deputy

Commissioner in Bath Storage noted:

“There may be times when an application is

determined to be complete by Staff but after further

review, Staff requests additional information in

accordance with 6 NYCRR 621.15(b). In some of

these instances, adjudication might proceed on points

of dispute where a reasonable interpretation

indicates that supplemental information is necessary

6. NYSDEC, in its memorandum of law in opposition to the

petition, requests that “should the DEC’s action not be

found to be a non-reviewable determination that Palmien’s

permit application is incomplete, it should be viewed

as a denial of the application on the ground that Palmien

failed to meet his burden of establishing that his proposed

project meets all applicable regulatory standards” (pages

17-18).

-20a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003}

to complete staff's review. Such is not the case in

this proceeding” (amended verified petition, Exhibit

G, page 5, emphasis added).

In the case at bar NYSDEC had determined that

petitioner’s application was complete except for information

to be derived from an on-site inspection which NYSDEC

believed was reasonably necessary for its review of the

petitioner’s permit. Requiring an adjudicatory hearing on

this issue would not, as the Deputy Commissioner opined in

Bath Storage, turn “the permitting process on its head.”

Accordingly, this petition is granted to the extent that

petitioner is held to be entitled to an adjudicatory hearing

pursuant to 6 NYCRR 621.7(f), and is otherwise denied.

Petitioner shall have the burden at such hearing of

demonstrating that NYSDEC’s demand for an on-site

inspection of the petitioner’s property is not reasonably

necessary in order to evaluate the petitioner’s application for

a wetlands permit (6 NYCRR 624.9(b)(1)).

Settle judgment on five days’ notice.

PAUL J. BAISLEY, JR.

JSC.

-2la-

Appendix E - Decision of the Commissioner, State of New

York, Department of Environmental

Conservation, Dated and Filed April 7,

2004 [22a - 33a]

STATE OF NEW YORK DEPARTMENT

OF ENVIRONMENTAL CONSERVATION

625 Broadway

Albany, New York 12233-1550

In the Matter

-of-

the application for a tidal wetlands permit,

use and protection of water permit, and water

quality certification pursuant to the

Environmental Conservation Law (ECL)

articles 15 and 25, and Title 6 of the Official

Compilation of Codes, Rules and Regulations

of the State of New York (6 NYCRR)

Parts 608 and 661

-by

PAUL PALMIERI

Applicant.

PERMIT APPLICATION No. 1-4720-00666/00009

DECISION OF THE COMMISSIONER

April 7, 2004

-22a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

DECISION OF THE COMMISSIONER

The attached hearing report, except for the section

headed “Recommendation,” of Administrative Law Judge

(“ALJ”) Molly T. McBride in the matter of the application of

Paul Palmieri for a tidal wetlands permit, protection of

waters permit, and water quality certification is hereby

adopted as the decision in this matter subject to the following

additional findings and conclusions.

This matter is before the Department of

Environmental Conservation (“Department”) pursuant to an

order of Supreme Court, Suffolk County (see Matter of

Palmieri v. New York State Dept. of Envtl. Conservation,

Sup Ct, Suffolk County, May 5, 2003, Baisley, J., Index No.

02-3925). In that order, Supreme Court remanded the matter

to the Department to afford applicant Paul Palmieri an

adjudicatory hearing on the issue of whether Department

staff's demand for an on-site inspection of applicant’s

property is reasonably necessary in order to evaluate

applicant’s application for a tidal wetlands permit (see id. at

6). The court placed the burden upon applicant to

demonstrate that the Department’s demand is not reasonably

necessary in order to evaluate his application (see id.).

The hearing record demonstrates that applicant failed

to meet his burden of proof that Department staff's request to

inspect the project site from applicant’s property is not

reasonably necessary. Accordingly, for the reasons stated in

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

the hearing report and in this decision, I affirm Department

staff's denial of the permit application.

Discussion

As an initial matter, it is important to note the narrow

scope of the issue remanded for hearing by Supreme Court,

Applicant devotes significant portions of his post-hearing

brief to the ALJ to the argument that Department staff's

demand for a pre-permit inspection on applicant’s property to

evaluate his wetlands permit application constitutes an

unreasonable intrusion and unconstitutional search in

violation of the Fourth Amendment of the United States

Constitution, and an illegal trespass under New York law. In

its order in the CPLR article 78 proceeding initiated by

applicant, however, Supreme Court expressly rejected these

arguments. The court held:

“{ Applicant’s] contention that NYSDEC’s attempt to

enforce a non-consensual site inspection of his

property violates his constitutional rights is also

without merit. Where NYSDEC can demonstrate a

reasonable need for the scientific information

obtained by an on-site inspection, such inspections

may be valid criteria for a wetlands permit .. . The

cases cited by the petitioner . . . are inapposite in that

an on-site inspection is a minimal intrusion and

petitioner’s project poses a diminished expectation of

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004)

privacy and as well is a matter of significant governmental

interest”

(id. at 4-5 [citations omitted]; see also Palmieri v. Lynch, US

Dist Ct, Ed NY, Aug. 29, 2003, Seybert, J., 00-CV-3225

[dismissing similar claims under federal! law that the

Department’s on-site inspection violated applicant’s 4"

Amendment rights]).

The court also expressly recognized that the

Department has the authority to request during the permit

review process additional information that is “reasonably

necessary” to make any findings or determinations required

by law in connection with the permit application, and that an

applicant’s failure to provide such information may be

grounds for denial of an application (see id. at 5 [citing 6

NYCRR 621.1(d) and 621.15(b)]). Thus, applicant’s

arguments under federal and state law were rejected by

Supreme Court, and are not presently before the Department

on this remand.

Accordingly, the narrow issue presented for hearing

is whether Department staffs demand for an on-site

inspection complied with the regulatory requirement of 6

NYCRR 621.15(b), that is whether the demand was

“reasonably necessary” to make the required findings or

determinations with regard to applicant’s tidal wetlands

permit application (see id. at 6). As noted above, Supreme

Court expressly placed the burden of proof on applicant (see

-25a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

id. [citing 6 NYCRR 624.9(b)(1)]). The regulations

applicable to permit hearing procedures establish that the

party bearing the burden of proof must sustain that burden by

a preponderance of the evidence unless a higher standard has

been established by statute or regulation (see 6 NYCRR

624.9[c]).

Review of the hearing record reveals that applicant

failed to carry his burden of proof. A preponderance of the

credible evidence presented at the hearing establishes that

on-site inspections by Department staff are reasonably

necessary to evaluate tidal wetland permit applications, and

to determine whether statutory and regulatory standards for

permit issuance can be met [see Environmental Conservation

Law 25-0402 & 25-0403, and 6 NYCRR 661.9(b)].

On-site inspections are reasonably necessary to allow

the Department to most efficiently and effectively carry out

its statutory and regulatory obligations. The record

demonstrates that, due to the high volume of permit

applications filed with the Department’s Region 1 office, the

limited number of available inspectors must conduct

numerous tidal wetland permit application inspections per

day in an area covering both Nassau and Suffolk Counties.

Department staff's witness testified that on-site

inspections are important in order to obtain the

environmental information necessary for the evaluation of a

tidal wetlands permit application with respect to the

-26a-

ee

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

applicable statutory and regulatory criteria. As testified, such

on-site inspections provide significant information,

including, for example, information on the upland

topography, the extent and types of vegetated areas, the

values of upland areas as buffers, existing structures, and

drainage patterns.

Department staff's witness noted that on-site

inspections afford a comprehensive view of the shoreline and

upland areas. From the vantage point of the height of the

bulkhead, it provides an opportunity to observe, among other

things, water flow patterns and te condition of the areas

seaward from the bulkhead.

Moreover, a preponderance of the credible evidence

demonstrates that the Department had a reasonable need for

the environmental information that wold have been obtained

by an on-site inspection in this particular case. Review of

applicant’s permit application materials submitted in 1991,

1993, and 1999, respectively, suggest that the underwater

area under applicant’s dock may be subject to significant

sedimentation and accretion. Thus, applicant’s own

application materials revealed that a significant degree of

sedimentation or accretion was underway in the shoals, mud

flats, and littoral zone just seaward of applicant's property

that required evaluation before a permit could be issued.

-27a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

Staff's witness provided detailed reasons why access

to the upland area of applicant’s property was necessary,

including to confirm that accretion was occurring and, if so,

to evaluate its source. He testified that an upland inspection

on applicant’s property would include, for example,

determining the sources and nature of run off from the

property, inspecting the condition of the landward side of the

bulkhead, and inspecting the shoreline adjacent to the

property from a vantage point that allowed a comprehensive

view.

Staff's witness also indicated that the best vantage

point for assessing water quality and the condition of the

shoals and mud flats seaward of the bulkhead was from the

bulkhead itself, and that walking out on applicant’s dock

would provide a more effective means of observing

underwater vegetation growth in the vicinity of the dock.

Applicant did not challenge staff's assertion that an

assessment of the upland area of the project site was a

necessary part of the permit application review. Rather,

applicant’s contention at hearing was that staff could access

the project site either by boat or along the shoreline, and

could conduct the inspection from either of those two routes

without crossing or stepping foot on applicant’s property.

The weight of the record evidence demonstrates that

both alternatives suggested by applicant would provide a

much less effective means for conducting the appropriate

-28a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

inspection, both upland and in the water itself. In addition,

the two alternatives are impracticable, more costly, time

consuming, and wasteful of limited Departmental resources.’

With respect to an inspection by boat, the record indicates

that boats appropriate for use in the waters adjacent to

applicant’s project are not available to Department staff that

review tidal wetlands permit application review.”

] Use of a boat, practically and as a matter of Department

policy, requires at least two staff members in order to both

operate the boat and conduct the inspection. The record

clearly establishes that inspections conducted during

routine, high-volume review of tidal wetland applications

are usually conducted by one inspector from land.

2 Applicant introduced a list of boats (see Exh C) that are

utilized by the Department, and argued that a Department-

owned sixteen-foot Boston whaler was available to staff

to use. Applicant did not establish by a preponderance of

the evidence that the Boston whaler was available to staff

to use.

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

More importantly, the record indicates that inspection

of the upland area, the shoreline, and the relevant underwater

areas would be less effective and significantly hindered if it

had to be conducted from a boat rather than from applicant’s

property. Staff's witness testified that inspection by boat,

due to safety considerations, would best be conducted during

high tide, a condition less favorable to effective inspection of

underwater shoals and mud flats, and where projects

involving a dock are concerned.

Applicant referred to staff using a boat in 1995 to

visit off-shore around his dock following the Department’ s

denial of a prior permit application. This does not compel

the conclusion that access to applicant’s property is not

reasonably necessary to evaluate applicant’s 1999 permit

application. To the contrary, the circumstances surrounding

staff's use of a boat at that time demonstrates such use is

atypical and out of the ordinary.’

3 Applicant contends that staff also visited his site in 1991

by boat. This contention was not corroborated and, thus,

the contention was not established by the preponderance

of the evidence. Moreover, the record is entirely silent

concerning the circumstances surrounding the 1991 visit,

assuming it occurred by boat.

-30a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

As the record demonstrates, significant obstacles and

costs are associated with applicant’s second offered

alternative of an inspection from the shoreline. applicant

failed to establish that access to the shoreline from a public

location was generally known. Moreover, applicant failed to

establish that use of the shoreline would be a safe mens of

gaining access to the project site. At most, applicant’s

witness established that the shoreline was rocky and sandy,

but did not otherwise establish its condition. In contract,

Department staff's witness noted potential hazards associated

with walking along similar shorelines, including the

difficulty of walking over algae-covered rocks and the

presence of sinkhole-like features under the water.

Applicant also failed to indicate the height of the

bulkhead or otherwise establish the bulkhead would not

effectively block the view of the upland area and the area

landward of the bulkhead to a viewer standing on the

shoreline (or a viewer from a boat). To the contrary, staff's

witness testified that bulkheads in the area are generally

about six feet high.

Photographs entered into evidence by the applicant

are the only record evidence of the actual height of the

bulkhead in this case (see Exhs F, G, and H). Those

photographs suggest that the bulkhead is taller than an adult

male, and support the reasonable inference that the view of

the upland area would be significantly blocked to an

inspector of average height standing on the shoreline. In any

-3 la-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

event, applicant fails to establish, by a preponderance of the

evidence, that such an inspector could effectively conduct the

necessary inspection of the upland area from the shoreline or

from a boat.

Conclusion

The hearing record demonstrates that applicant failed

to carry his burden of establishing, by a preponderance of the

evidence, that staff's demand to conduct an on-site

inspection was not reasonably necessary to make the required

permit application. The weight of the record evidence

supports the conclusion that such access was reasonably

necessary, and that applicant’s two proposed alternatives to

On-site inspection would impose an unreasonable burden

upon the limited resources of the Department and

significantly hinder the necessary environmental assessments

required to determine whether applicant’s application meets

with statutory and regulatory criteria.

Applicant has applied to the Department for the

privilege of constructing a long extension to a dock ina

State-protected tidal wetland. Because staff's request during

the permit application review process for an on-site

inspection was reasonably necessary to make the findings

and determinations required by law, applicant’s refusal to

allow the on-site inspection is ground for denial of the 1999

permit application. Therefore, Department staff's

-32a-

Appendix E

|Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004}

determination to deny the 1999 permit application is

affirmed.

For the New York State

Department of Environmental

Conservation

S/

By: Erin M. Crotty, Commissioner

Dated: April 7, 2004

Albany, New York

Appendix F - Hearing Report of Administrative Law

Judge Molly T. McBride Dated and Filed

January 30, 2004 [34a- 46a]

STATE OF NEW YORK DEPARTMENT

OF ENVIRONMENTAL CONSERVATION

625 Broadway

Albany, New York 12233-1550

In the Matter

-of-

the application for a tidal wetlands permit,

use and protection of water permit, and water

quality certificate pursuant to the

Environmental Conservation Law (ECL)

Articles 15 and 25, and Title 6 of the Official

Compilation of Codes, Rules and Regulations

of the State of New York (6 NYCRR)

Parts 608 and 661 by

PAUL PALMIERI

PERMIT APPLICATION No. 1-4720-00666/00009

HEARING REPORT

-by-

Molly T. McBride

Administrative Law Judge

January 30, 2004

-34a-

Appendix F

[Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004}

PROCEEDINGS

In May 1999, an application for permits from the

New York State Department of Environmental Conservation

(Department) was made by Paul Palmieri (applicant), 123

East Shore Road, Babylon, New York, for a tidal wetlands

permit, protection of waters permit and water quality

certificate pursuant to ECL Article 25 and 6 NYCRR 661.

The application was denied on July 7, 2000 and applicant

requested an adjudicatory hearing. A hearing was scheduled

for March 27, 2001 but was adjourned due to the

unavailability of Staff's witness. The hearing was

rescheduled fer June 25, 2001. Applicant failed to appear for

the hearing. Department Staff served a notice of motion for

administrative judicial intervention on or about June 28,

2001 asking that the permit application be denied due to

applicant’s failure to appear at the hearing. Applicant

opposed tfie motion. Department Staff had also moved for

an order affirming its denial of the application due to

applicant’s refusal to allow Staff to conduct a site visit as

part of the permit review process.

The motion was denied with regard to applicant’s

failure to appear for the hearing. By order of Commissioner

Erin M. Crotty dated February 1, 2002, the application was

deemed incomplete due to Department Staff's inability to

enter the property for a site inspection and the hearing

request was deemed void. Applicant commenced a

proceeding in New York State Supreme Court pursuant to

Article 78 of New York Civil Practice Law and Rules

-3Sa-

Appendix F

[Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

(CPLR) challenging the Commissioner’s order. Supreme

Court, Suffolk County, by order of Justice Paul Paisley, Jr.

dated May 5, 2003, remanded the matter to the Department

for a hearing on the sole issue of whether an on-site

inspection by Department Staff, as part of the permit

application review, was reasonably necessary.

BACKGROUND

This applicant has a history of filing permit

applications with the Department for projects at this site. In

1991 applicant applied for a permit to reconstruct a bulkhead

and to construct a 30' x 10' ramp and a S' x 45' float and

pilings. The permit was issued. Approximately 5 months

later, applicant applied for a permit to construct a 52' fixed

pier with additional pilings. This application was also

granted. In 1993, one year after the second permit was

issued, applicant sought to expand the existing 52' pier an

additional 110', to add 2 boat lifts with 80,000 Ib. and 16,000

lb. capabilities and to add 4 mooring pilings clusters. Staff

denied this application. A hearing was requested by

applicant after the denial. The parties entered into settlement

discussions. During these discussions, a site visit was done

by Department Staff via boat. Ultimately, the parties

resolved the matter and a Stipulation of Settlement was

entered into on May 30, 1995 wherein applicant agreed to

modify the application and reduce the extension of the boat

dock from 110' to 40' and to reduce the boat lift request from

two boat lifts to one boat lift. Based upon the changes made

to the application as a result of the settlement, Staff withdrew

-36a-

Appendix F

[Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

its objections to the issuance of the permit and a permit was

issued in June 1995.

In May 1999 applicant applied for a permit to

construct an additional 50’ extension of the dock and to add

an 80,000 lb. boat lift. This is basically what was requested

by applicant in his 1993 application, when combined with

what was permitted in June 1995.

The May 1999 application was denied by Staff by

letter dated July 7, 2000. The Notice of Permit Denial states,

in part: “You failed to allow Department Staff to inspect the

property to observe the conditions at the site in order to

determine whether or not your proposal complies with the

standards for permit issuance. Therefore, this application for

permit is hereby denied.” It is undisputed that applicant has

refused Staff access to his property to inspect it as part of the

permitting process. Applicant contends that Staff can

conduct whatever inspection is necessary without entering

his property.

Pursuant to the Order of the Supreme Court, a

hearing was conducted on October 8, 2003 at the Babylon

Public Library, 211 route 109, West Babylon, New York

before Administrative Law Judge Molly T. McBride. The

proceedings began with a legislative hearing at

approximately 10:40 a.m. Applicant appeared with his

counsel, Franklin Wilks, Esq. from the Coalition of

Landlords, Homeowners and Merchants. The Department

appeared by Craig L. Elgut, assistant regional attorney. No

-37a-

EE

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

persons came forward to speak on the project. At the

conclusion of the legislative hearing, an issues conference

was convened. No other persons, agencies or organizations

participated in the hearing process as parties or sought party

status. At the conclusion of the issues conference, the

adjudicatory hearing was immediately commenced on the

sole issue of whether the Department’s demand to conduct an

inspection of the project site from applicant’s property as

part of the permit application review was reasonably

necessary. The Supreme Court placed the burden of proof

for this issue on applicant.

The following witnesses testified on behalf of

applicant: Paul Palmieri and Aram Terchunian, First Coastal

Corp., applicant’s environmental consultant. Charles T.

Hamilton, regional supervisor of the Department’s Office of

Natural Resources, Region One, Stony Brook, New York

testified on behalf of the Department.

The parties submitted post-hearing briefs and the

hearing record closed on December 31, 2003 upon receipt of

the briefs.

POSITION OF THE PARTIES

Applicant

Applicant maintains that the Department can conduct

its permit application review without accessing his property.

He contends that the Department can conduct its site

-38a-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

inspection from the water, by boat, or by walking along the

shoreline after entering it from a public access point.

Department

The Department contends that the application can not

be reviewed to determine if the standards for a tidal wetlands

permit have been met without Department personnel

accessing applicant’s property. Department Staff also argues

that applicant’s suggestion of using a boat is not practical

because they can rely on having boats available to do site

inspections.

FINDINGS OF FACT

1. In May 1999, Paul Palmieri, applicant, 123 East

Shore Drive, Babylon, New York, applied for a tidal

wetlands and protection of waters permit and water quality

certificate to expand an existing 92' dock structure by 50 feet

and add an 80,000 pound boat lift at his property noted

above. The proposed project is located on the Great South

Bay, in the Town of Babylon, County of Suffolk.

2. The existing dock structure was permitted by the

Department in three phases. The first phase permitted was to

reconstruct a bulkhead and to construct a 30’ x 10’ ramp and

a 5'x 45' float and pilings. The permit was issued in 1991.

Approximately 5 months later, applicant applied for a permit

to construct a 52' fixed pier with additional pilings which

was also granted. A third permit application, filed in 1993,

-39a-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

one year after the second permit was issued, sought to

expand the existing 52' pier an additional 110', to add 2 boat

lifts with 80,000 Ib. and 16,000 Ib. capabilities and to add 4

moorings pilings clusters. This application was denied.

After a request for a hearing was filed by applicant, the

matter was resolved by an agreement between the parties

which provided for the extension of the boat dock by 40'

rather than 110' and the addition of one boat lift rather than

two.

3. Applicant refused Department Staff access to his

property in 1995 during the review of his 1993 permit

application.

4. Department Staff attempted to access applicant’s

property during its review of the current permit application

and applicant has refused Department Staff access to his

property.

5. Department Staff notified applicant by letter dated

April 7, 2000 that it would need to access the property to

conduct a site inspection and complete the permit application

review.

6. By letter dated July 7, 2000 the Department denied

the latest permit application because it could not gain access

to applicant’s property to complete the permit application

review.

-40a-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

7. Applicant filed a request for a hearing on the

permit application denial. A hearing was scheduled but

adjourned at the request of Staff as witnesses were

unavailable. The hearing was rescheduled but applicant and

his counsel filed to appear on the rescheduled date.

8. Department Staff moved for an order determining

the hearing process abandoned based upon applicant’s failure

to appear for the hearing or, in the alternative, for an order

affirming Staff's denial of the permit application based upon

applicant’s refusal to allow Department Staff on his property

to conduct the site inspection.

9. Commissioner Erin M.Crotty, by order dated

February 1, 2002, denied the motion to dismiss due to

applicant’s failure to appear. The order also deemed the

application incomplete based upon the Staff's inability to

access applicant’s property and, therefore, the hearing

request was voided.

10. Applicant commenced a proceeding in New York

Supreme Court, Suffolk County, pursuant to CPLR Article

78 Challenging the Commissioner’s order. Supreme Court,

Suffolk County (Baisley, J.), by decision dated May 5, 2003

granted the petition to the extent of remanding the matter to

the Department for a hearing to allow applicant an

opportunity to demonstrate the Department’s request for an

on-site inspection was not reasonable and necessary to

evaluate the application for a wetland permit, and otherwise

denied the petition. The decision placed the burden of proof

-4la-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

on applicant for the hearing. The hearing was held on

October 8, 2003.

11. Applicant testified at the October 8, 2003 hearing

that he will not agree to Department Staff entering his

property as part of the permit review process. Applicant

countered Department Staff's request with his suggestion

that Department Staff inspect the project site by boat from

the Great South Bay or enter the shoreline from a public

access point and walk to applicant’s project site. Applicant

has not provided a specific route, specific entry point, nor

provided details to Staff as to what they would find on any

route that they may take to applicant’s property if they did in

fact enter the shoreline from a public access point and walk

to his property.

12. Applicant was advised by Department Staff in

writing that a boat was not available to them to conduct a site

inspection. Applicant did not allow Staff onto his property

after being told that a boat was not available.

13. Department Staff routinely conducts permit

application reviews from an applicant’s property.

Department Staff testified as to numerous reasons why they

need access to applicant’s property as part of this permit

application review.

14. Department Staff testified as to why the

alternatives posed by applicant (walking shoreline or boat

inspection) are not adequate for the permit application

-42a-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

review in this case. Those methods would not allow Staff to

obtain all necessary information to assess the application. By

way of example, Staff testified that there has been an

abnormal amount of accretion in the area around the boat

dock (water depth changed from 5-6' to 2 /% to less than 4'

from 1991 to the date of this application) and Staff would

need to evaluate the upland, as well as the dock location to

assess possible causes/problems. Charles Hamilton

identified approximately twelve items he would be

inspecting from applicant’s property with respect to the

accretion problem alone. Also, from applicant’s property

Staff would have an elevated spot to view organisms and

plants from the water that would not be readily visible from

the shoreline or from a boat in the water. The inspector can

view the shoals and mudflats below for other factors as well.

Based upon those findings, a second site inspection may be

warranted at which time Staff would come out with testing

gear and take some samplings for testing.

15. The Department’s Region One office, where this

application is pending, receives approximately 4,000 tidal

wetland permit applications each calendar year. Each permit

application requires review by Department Staff and four

Staff members are responsible for all tidal wetlands

applications inspections. The alternative methods proposed

by applicant would be too time consuming to employ ona

regular basis in the Department’s application reviews.

16. Charles Hamilton testified that he conducted 27

site inspections on the day before this hearing. He testified

-43a-

Appendix F

[Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

that that number of site inspections is not unusual due to the

volume of permit applications received in their office each

year. His other inspectors typically conduct 10-15

inspections per day. If he and his Staff were required to use

a boat or take a circuitous route to applicant’s property to

conduct site inspections, they would not be able to complete

as many site inspections and application processing would be

delayed.

17. Applicant permitted his environmental consultant

and employees to conduct a site inspection from his property.

18. Supreme Court, Justice Baisley, held that “Where

NYSDEC can demonstrate a reasonable need for the

scientific information obtained by an on-site inspection, such

inspections may be valid criteria for a wetlands permit.”

(Baisley Memorandum Decision, p. 4, citing Thompson v.

Dept. of Environmental Conservation 132 AD 2d 665).

CONCLUSIONS OF LAW

1. Section 624.9(b)(1) of 6 NYCRR states: “The

applicant has the burden of proof to demonstrate that its

proposal will be in compliance with all applicable laws and

regulations administered by the department.” Further, the

Memorandum Decision of Justice Baisley remanding this

matter for a hearing placed the burden of proof on applicant

to show why the Department’s demand for an on-site

inspection of applicant’s property is not reasonably necessary

in order to evaluate the application.

-44a-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

2. This permit application is for a tidal wetlands

permit, protection of waters permit and water quality

certificate.

3. Section 661.1 of 6 NYCRR states, in part, “It is

the public policy of the State to preserve and protect tidal

wetlands, and to prevent their despoliation and destruction,

giving due consideration to the reasonable economic and

social developments of the State.” The Department is

entrusted with implementing the state’s tidal wetlands policy.

4. Section 661.9(b) of 6 NYCRR identifies the

standards for a tidal wetlands permit to be issued. In

summary, the applicable standards require a showing that the

permitted activity will preserve and protect tidal wetlands,

prevent the despoliation and destruction of wetlands, and not

have an undue adverse impact on the present or potential

value of the wetlands for marine food production, wildlife

habitat and flood and hurricane and storm control.

5. Standards for issuance of a water quality

certification are found at 6 NYCRR 608.9 and the protection

of waters permit issuance standards are found at 6 NYCRR

608.8.

6. Department Staff identified numerous reasons why

they need access to applicant’s property to conduct the

permit application review and why applicant’s alternatives

are not acceptable. Applicant has not met his burden of

proof to show why access to this property is not reasonably

-45a-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

necessary as part of the permit application review.

Department Staff provided specific sworn testimony as to

why that type of inspection would not be sufficient.

RECOMMENDATION

I recommend that the Commissioner find that

applicant has not met his burden of proof to show that

Department Staff's request for access to his property as part

of its permit application review is not reasonably necessary.

Department Staff has indicated that they must deny the

permit application because they were denied access to the

property. Therefore, I recommend that the Commissioner

affirm Staff's denial of the permit application unless

Respondent provides Department Staff the necessary access

to his property within 20 days of the Commissioner’s

decision. If applicant provides Department Staff with the

necessary access, then I recommend that Staff conduct the

site inspection and take the appropriate action on the

application.

-46a-

Appendix G - Ruling of the Commissioner, State of New

York, Department of Environmental

Conservation, Dated and Filed February

1, 2002 [47a - 50a]

STATE OF NEW YORK

DEPARTMENT OF

ENVIRONMENTAL CONSERVATION

625 Broadway

Albany, New York 12233-1010

In the Matter

-of-

the Application for a tidal wetlands permit,

pursuant to Environmenta! Conservation

Law of the State of New York (“ECL”)

Article 25 and Title 6 of the Official

Compilation of Codes, Rules and Regulations

of the State of New York (“6 NYCRR”)

Part 661 by

PAUL PALMIERI

Applicant

Application No. 1-4720-00666/00009

RULING OF THE COMMISSIONER

February |, 2002

-47a-

Appendix G

[Ruling of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed February 1, 2002}

Pursuant to 6 NYCRR Part 624.8(b)(1) Staff of the

New York State Department of Environmental Conservation

(“DEC Staff’, “Department”) duly served a motion for

administrative judicial intervention upon Paul Palmieri (the

“Applicant”) on or about June 28, 2001. Said motion was

supported by the affirmation of assistant regional attorney

Craig L. Elgut, Esq. and the affidavit of DEC staff Charles T.

Hamilton, Supervisor of Natural Resources, Region One.

Applicant opposed said motion by affidavit of Richard

Young, Esq., counsel for Applicant.

The motion seeks an Order determining the

Applicant’s failure to appear for a hearing an abandonment

of the hearing process, thereby deeming the applicant’s

request for a hearing on his tidal wetlands application

withdrawn and denying any further administrative remedy.

In the alternative, Staff seeks an Order that affirms Staff ‘s

denial of tie permit application due to the permit application

being incomplete.

Staff documents by affirmation of Craig L. Elgut,

Esq. that:

(i) Applicant applied for a tidal wetlands permit

to expand a residential dock an additional 50

feet and to add an 80,000 Ib. boat lift:

(ii) By letter dated July 7, 2000 DEC Staff denied

the application after notifying applicant that

-48a-

Appendix G

[Ruling of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed February 1, 2002}

the Staff required access to the site to

complete the application review and Staff was

denied access;

(iii) | Applicant requested a hearing after receipt of

the denial;

(iv) An adjudicatory hearing was rescheduled to

be held on June 25, 2001.

A copy of the motion and supporting papers and the

Applicant’s opposing affidavit were filed with the Office of

Hearings and Mediation Services. The hearing and the

motion were assigned to Administrative Law Judge Molly T.

McBride (“ALJ”). Attached to this Ruling is the ALJ’s

Ruling on Motion and Summary Report, which I adopt as my

own, subject to my comments below.

Under the Department’s permit processing rules,

applicants are required to supply Department Staff with

sufficient information to afford Staff a reasonable

opportunity to evaluate information in determining whether

to approve, modify or deny a request for a Department

permit. As set forth in the ALJ’s report, applicants must

supply this information or otherwise cause their application

to be deemed incomplete requiring further information

before Staff can make a reasonable determination on the

proposed project.

-49a-

Appendix G

[Ruling of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed February 1, 2002]

I find that the Applicant’s tidal wetlands application

under review must be deemed incomplete for the purposes of

permit processing under the Department’s Uniform

Procedures, 6 NYCRR Part 621. The Applicant’s denial of

access to his property prevented Department Staff from

evaluating the on-site conditions and the proposed project.

The ability to gather such information is necessary to make

the determination that the permit application is complete.

The Applicant’s actions effectively relieves Department Staff

from taking any further action on the permit application until

access to the site and site information is available for Staffs

review. Further I am determining that the Applicant’s

request for hearing on its proposed project is void until such

time as the site access and the necessary information is made

part of the permit application. Thereafter, if and when said

information is supplied and Staff's redetermination is to deny

the proposed project, then the Applicant will be afforded a

hearing on Staff's denial of the requested permit.

For the New York State Department

of Environmental Conservation

S/

By: ErinM. Crotty, Commissioner

Date: Albany, New York

February 1, 2002

-50a-

Appendix H - Ruling on Motion and Summary Report of

Molly McBride (ALJ) [51a - 66a]

STATE OF NEW YORK

DEPARTMENT OF

ENVIRONMENTAL CONSERVATION

625 Broadway

Albany, New York 12233-1010

In the Matter

-of-

the Application for a tidal wetlands permit,

pursuant to Environmental Conservation

Law of the State of New York (“ECL”)

Article 25 and Title 6 of the Official

Compilation of Codes, Rules and Regulations

of the State of New York (“6 NYCRR”)

Part 661 by

PAUL PALMIERI

Applicant

Application No. 1-4720-00666/00009

RULING ON MOTION AND SUMMARY REPORT

-BY-

S/

Molly McBride

Administrative Law Judge

-Sla-

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)]

PROCEDURAL BACKGROUND

Applicant Paul Palmieri ("Applicant”) applied to the

New York State Department of Environmental Conservation

(""DEC'”, "Staff", "Department') in May, 1999 for a tidal

wetlands permit pursuant to ECL Article 25 and 6 NYCRR

661. The application was denied on July 7, 2000 and

Applicant requested an adjudicatory hearing. A hearing was

scheduled for March 27, 2001 but was adjourned due to the

unavailability of Staff's witness. The hearing was

rescheduled for June 25, 2001. Applicant failed to appear for

the hearing. DEC Staff served a notice of motion for

administrative judicial intervention pursuant to 6 NYCRR

624.8(b)(i) on or about June 28, 2001. DEC Staff submitted

the following in Support of the motion: affirmation of

assistant regional attorney Craig L. Elgut, Esq. and the

affidavit of Charles T. Hamilton, Supervisor of Natural

Resources for the DEC, Region One, sworn to on June 28,

2001. Applicant opposed the motion by Affirmation of

Richard W. Young, Esq. counsel for Applicant, dated July

9,2001.

Staff's Motion was served on the Office of Hearings

and Mediation Services as was Applicant's opposing papers.

The hearing and now this motion were assigned to

Administrative Law Judge Molly T. McBride ("ALJ").

Staff moves for an order deeming the Applicant's

failure to appear at an adjudicatory hearing as an

abandonment of the hearing process which in turn deems the

-52a-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)]

Applicant's request for a hearing withdrawn. In the

alternative, Staff seeks an Order that affirms Staffs denial of

the permit application.

BACKGROUND

Applicant owns a private residence at 123 East Shore

Road, Babylon, New York, on the Great South Bay. This

Applicant has a history of filing permit applications with the

Department. In 1991 the Applicant applied for a permit to

reconstruct a bulkhead and to construct a 30' x 10' ramp and

a 5' x 45' float and pilings. The permit was issued.

Approximately 5 months later, Applicant applied for a permit

to construct a 52' fixed pier with additional pilings. This

application was also granted.

One year after the second permit was issued,

Applicant sought to expand the exiting 52' pier an additional

110’, to add 2 boat lifts with 80,000 Ib. and 16,000 Ib.

capabilities and to add 4 mooring pilings clusters. Staff

denied this application. A hearing was requested by the

Applicant after the denial. The parties entered into settlement

discussions and ultimately resolved the matter. A Stipulation

of Settlement was entered into by the parties on May 30,

1995 wherein the Applicant agreed to modify the application

and reduce the extension of the boat dock from 110' to 40’

and to reduce the boat lift request from two boat lifts to one

boat lift. Based upon these changes, Staff withdrew its

objections to the issuance of the permit and a permit was

issued in June, 1995.

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)|

In May, 1999 the Applicant applied for a permit to

construct an additional 50’ extension of the dock and to add

an 80,000 Ib. boat lift. This is basically what was requested

by the Applicant in his 1995 application, when combined

with what was permitted in June, 1995.

The May, 1999 application was denied by Staff by

letter dated July 7, 2000. The Notice of Permit Denial states,

in part: "You failed to allow Department Staff to inspect

your property to observe the conditions at the site in order to

determine whether or not your proposal complies with the

standards for permit issuance. Therefore, this application for

permit is hereby denied." It is undisputed that Applicant has

refused Staff access to his property to inspect it as part of the

permitting process. Applicant contends that Staff can

conduct whatever inspection is necessary from the water,

without entering his property.

An adjudicatory hearing was scheduled for March 27,

2001 in Babylon, New York. The hearing was adjourned due

to the unavailability of Staffs witness. The parties finally

settled on June 25, 2001 as the rescheduled date for the

hearing. The ALJ served on both parties by facsimile, a letter

dated May 10, 2001 and a Notice of Public Hearing

confirming the June 25, 2001 hearing date. The ALJ and

Staff appeared at the hearing site on June 25, 2001. Neither

the Applicant nor his counsel appeared. Counsel for the

Applicant later indicated that he did not believe that a firm

date had been set for the hearing.

-54a-

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)}

STAFF’S POSITION

Staff seeks a denial of the application based on

Applicant's failure to appear for the hearing and due to the

incompleteness of the application. Staff advised Applicant

that an inspection of his property, from his property rather

than by boat, is essential for the review of the application.

Absent the inspection, the permit can not be granted.

APPLICANT’S POSITION

Applicant's counsel's affidavit in opposition to the

motion only addresses Staff's request to deny the application

based on Applicant’s failure to attend the hearing. However,

he has addressed the issue of the site inspection in earlier

correspondence with the Department. Applicant has denied

the DEC all access to his property. He insists that Staff

conduct its inspection from the least intrusive manner

available that being from the waterway."’

_ FINDINGS OF FACT

After a review of the pleadings and papers submitted

herein by the parties, 1 find that the following facts are not in

dispute:

: By letter dated April 27, 2000, counsel for the Applicant

advised DEC that his client would not consent to an

inspection from the property and suggested an inspection

from the water.

-55a-

Appendix H

jRuling on Motion and Summary

Report of Molly McBride (ALJ)]

By application dated May 25, 1999 Applicant

Paul Palmieri applied for a tidal wetlands

permit to construct a 50' extension to an

existing pier and to add one boat lift.

Staff attempted to inspect Applicant's property

in April, 2000 as part of the application

review process. Access was denied by the

Applicant.

By letter dated July 7, 2000 DEC Permit

Administrator Mark Carrara advised

Applicant's counsel that due to Applicant's

failure to allow an inspection from the

property, the permit application was being

denied.

A Notice of Permit Denial was issued to the

Applicant by the DEC on July 7, 2000. The

Notice stated, in part, "You failed to allow

Department staff to inspect the property to

observe the conditions at the site in order to

determine whether or not your proposal

complies with the standards for permit

issuance. Therefore, this application for

permit is hereby denied."

Applicant requested an adjudicatory hearing

on the denial of the application.

-56a-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)]

6. The hearing was scheduled for June 25, 2001

in Babylon, New York. Applicant failed to

appear for the hearing.

DISCUSSION

6 NYCRR 624.6(c) allows for the bringing of a

motion at any time. Motions made prior to the hearing shall

be filed with the ALJ and served on all parties. The ALJ

shall then rule upon the motion prior to the completion of

testimony. 6 NYCRR 624.8(b)(i) grants the authority to an

ALJ to rule upon all motions and requests, including those

that decide the ultimate merits of the case.

DISMISSAL DUE TO

APPLICANT'S FAILURE TO APPEAR

Staff requests that the Applicant be denied an

adjudicatory hearing due to his failure to appear for the

hearing scheduled for June 25, 2001. Applicant claims to

have not been aware that the hearing was rescheduled. To

deny the hearing based upon the Applicant's failure to appear

for the hearing is a drastic remedy. While the Notice for the

hearing was sent by facsimile by the Office of Hearings to

the Applicant's counsel on May 10, 2001, there is no

confirmation that counsel saw that letter and Notice.

Frankly, scheduling errors occur and such a severe penalty as

requested by Staff is not warranted here. Also, Staff has

submitted no law in support of the request.

-S7a-

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)}

RIGHT TO INSPECT

The application is for a tidal wetlands permit. Tidal

wetlands in New York State are regulated by Part 661 of 6

NYCRR. It is the public policy of the State to protect and

preserve tidal wetlands and to prevent their despoliation and

destruction. Part 661.2(a) states: "Tidal wetlands constitute

one of the most vital and productive areas of the natural

world and collectively have many values . . . Therefore, the

protection and preservation of tidal wetlands is essential."

There are five standards that govern whether the Department

will issue a tidal wetlands permit. Those standards are

defined at 6 NYCRR 661.9(b)(i)-(v).

The Applicant has the burden of establishing that the

applicable standards will be met. 6 NYCRR 661.9(a)

| In the instant case, the Applicant failed to allow Staff

onto his property. Staff notified Applicant in writing that it

was a necessary part of the permit process to have access to

the property to conduct the inspection. Despite being

notified of the Department's need to inspect, the Applicant

continued to deny access. As stated, the Applicant has not

addressed the issue of an inspection from the property in his

opposing papers. However, in April, 2000 Applicant's

attorney sent a letter to DEC indicating that his client would

not consent io the inspection from his property. Counsel

cited 3 cases in support of his position that the inspection

from the property was tantamount to an illegal and

warrantless search. After reviewing the cases cited, I

-58a-

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)}|

disagree. The circumstances of those cases, which I will

address below, were significantly different than here and,

therefore, the rulings are not controlling here.

The leading case cited by the Applicant is Sokolov v.

Village of Freeport, 52 N.Y.2d 341. In Sokolov, the Court of

Appeals held that a Village ordinance that required an

inspection of residential rental property in order for the

owner to rent out the property was a warrantless search and

therefore unconstitutional. The Village had enacted an

ordinance requiring all owners of rental property to have a

permit issued before renting the property. The permit would

only be issued after the Village inspected the property. The

Court held “We hold today that the imposition of a penalty

upon a landlord for renting his premises without first

consenting to a warrentless search violates the property

owner's Fourth Amendment rights." (Sokolov at 343) The

Court noted that if the property owner does not consent. he

will he deprived of the economic benefit of his property.

Here, the Applicant is seeking a privilege. He is asking to be

allowed to construct a pier extension and add a boat lift into

the Great South Bay. The issue is, does the construction

harm the delicate nature of the tidal wetlands. The DEC is

entrusted with the important task of preserving and

protecting tidal wetlands. That job requires the Department

to carefully review each application for a tidal wetlands

permit to ensure that it meets the standards enumerated in

part 661. As stated by Charles Hamilton, DEC Region One

supervisor of Natural Resources, the Department can not

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)]

complete their job without inspecting the property. The

~ suggestion of the Applicant that the inspection take place

from the water is not viable. Staff has refuted that in the

Hamilton affidavit. First it would be w.ong to have the

Applicant dictate to Staff how they should do their job. But,

more importantly, it is crucial for Staff to have complete

access to the wetlands and no other type of inspection will

suffice. Staff has been entrusted with the responsibility of

ensuring that the existing and potential values of tidal

wetlands for marine food production and wildlife habitat and

other values associated with tidal wetlands are protected.

The Hamilton affidavit addresses why an inspection

from the Applicant's property is a necessary part of this

application process. Hamilton asserts that Staff must

conduct an extensive site review to assess a specific project

and it's specific wetland environment. (Hamilton, p.2) By

denying Staff access, Staff is denied the opportunity to

conduct a meaningful technical review of the project site as

required by the regulations. (Hamilton, p.2),"..., staff

must access the condition of the wetlands in the area of the

existing structure as well as the area where the proposed

extension would be located. Staff needs to determine

whether the existing structure is causing impacts which may

be compounded by increasing the size of the structure."

(Hamilton, p. 5) Applicant does not address any of these”

issues in it's opposing papers. While Applicant's counsel

submitted case law that he alleges supports his client's

position that an inspection is a warrantless search, he has

offered no response to Staffs specific arguments on why they

-60a-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)}

need to enter the property in this case. Applicant has never

stated how Staff can determine if the application meets the

standards for permit issuance without actually inspecting the

property.

| find staff's arguments persuasive and agree that in

order to meet the duties imposed by Part 661, an inspection

of the site is necessary.

The Applicant's attorney also cited 7own of

Brookhaven v. Ronkoma Realty Corp., 154 A.D. 2d 665,

Second Dept:, 1989. This case also involved an ordinance

requiring rental property to be inspected and a permit issued

prior to rental. For the same reasons cited in Sokolov, the

Court found that the ordinance was unconstitutional. Finally,

Applicant cited People v. Ost, 121 A. D. 2d 571, Second

Dept., 1986. In Ost, the police had entered the defendant's

business, without a warrant, examined his books, without

permission, and used the information gathered to charge the

defendant criminally. The Court found the warrantless

inspection a violation of the defendant's constitutional! rights

and the charges were dismissed. For obvious reasons the

facts in Ost can not be equated with the facts here.

One of the differences between a tidal wetlands

permit and a permit to operate rental property is that the tidal

wetlands permit is asking for a privilege, not a right. There

is no right to a tidal wetlands permit. The Applicant here

will not lose his property in any way or suffer economic

harm if the permit is not granted. There is no monetary or

-6la-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)}

criminal penalty for him if he fails to allow the inspection.

The only consequence is that the application must be denied.

The Applicant is still free to enjoy his property as he did

before filing the application. He has previously been granted

permits to construct the pier, reconstruct the bulkhead and

install a boat lift. The pier has already been extended from

it's initial 52' to 92'. The Applicant is free to chose [sic. |

which route to take. He has elected to refuse Staff access to

his property. Surprisingly, the permits previously issued to

the Applicant all provide the DEC with the right to enter the

property to ensure that the permit conditions are being

complied with. All permits issued by the DEC grant the

Department that right. Applicant has already consented, by

accepting the permits, to Staff entering his property. It is

illogical for Applicant to deny access to Staff as a part of this

application. However, that is his right.

Staff can not determine if the application meets the

standards for permit issuance without inspecting the

property. Therefore, the application is incomplete, Staff has

no discretion with regards to applying the standards. If it can

not be determined that the standards are met, the application

simply can not be deemed complete.

DENIAL DUE TO INCOMPLETENESS

Staff argues in it's motion that the application is in

fact incomplete due to the lack of an inspection. Staff

notified Applicant in writing on April 1, 2000 that it was a

-62a-

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)}

necessary part of the permit process to have access to the

property to conduct the inspection. At that time, Mark

Carrara, Deputy Permit Administrator for the DEC stated to

the Applicant that the permit application would be denied if

Staff was not allowed to inspect the property. Despite being

notified of the Department’s need to inspect, the Applicant

continued to deny access.

Clearly, the application can not be reviewed by Staff

without the inspection and therefore, the application is in

essence incomplete. Staff cites the Interim Decision in Bath

Petroleum Storage, Inc, November 6, 2000 in support of it's

argument that the completeness of the application is an issue

that is not subject to review.

The Interim Decision, issued by Deputy

Commissioner Carl Johnson held that there is a bar against

adjudicating the completeness of a permit application in 6

NYCRR section 624.4(c)(7).

A review of relevant administrative decisions reveal

the basis for the bar. The purpose of the prohibition

where an application is deemed complete is to give an

Applicant comfort and certainty that its application _

cannot be undone at the hearing stage, i.e., assertions

by intervening parties to adjourn the hearing on

incompleteness grounds. See, Matter of Applications

of Department of Sanitation Southwest Brooklyn

Incinerator, Interim Decision, March 2, 1994. "...

the completeness determination . . . is intended to

-63a-

Appendix H

[Ru’*-< on Motion and Summary

Re... of Molly McBride (ALJ)}

reflect the point at which the application contains

sufficient information to commence regulatory

review." Matter of LaFever Excavating, Inc., Interim

Decision, October 28, 1991. ".. . once the

completeness determination is made, there is no

turning back." Matter of Applications of NYC

Department of Environmental Protection, Preliminary

Ruling of ALJ, Match 24, 1994; See also, Matter of

Applications of Fulton County Board of Supervisors,

Decision of Commissioner, February 13, 1987. Bath

at p.7

I agree with Staff that the application is in fact

incomplete when Staff can not access the property. The

Applicant bears the burden of showing that the application

meets the standards enumerated in Part 661. That burden is

met with written submissions AND an inspection of the

site. The application information submitted must be field

verified. Qualified, trained biologists visit the site to assess

the area. A tidal wetlands permit can be issued only if the

proposed activity meets the standards for permit issuance in

6 NYCRR 661.9(b)(i)-(v). Nothing in Part 661 gives Staff

the discretion to work outside of these standards. Obviously,

Staff can not assess whether the standards are met without

sending trained professionals to the site to do their job. If

Staff can not determine if the standards arc met, Staff can not

conduct a complete the [sic.] review of the application.

-64a-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)|

Based upon the Interim Decision in Bath, I have no

authority to review Staffs determination that the application

is incomplete.

CONCLUSION

Staff has requested that the denial of the application

based upon incompleteness be affirmed or in the alternative,

the application be dismissed due to the Applicant's failure to

attend the hearing. Staff has cited no legal authority to deny

the application solely due to Applicant's failure to appear at

the hearing. Further, the penalty is too harsh to deny the

application when Applicant's attorney claims to not have

been aware of the hearing being scheduled. Also, the permit

denial issued by the Department was not the proper vehicle

in this circumstance. Staff acknowledges that the application

is incomplete. Staffs remedy to that particular circumstance

is to issue an [sic.] Notice of Incomplete Application rather

than a denial of the application based upon incompleteness.

RECOMMENDATION

Based upon the record before me and the Findings of

Fact herein, | recommend that the Notice of Denial be

vacated and that Staff's determination that the application is

incomplete as stated in correspondence to the Applicant and

the motions papers herein, be deemed a Notice of Incomplete

Application. Further, the Request for Hearing filed by the

Applicant is void since such a request can not be made in

response to a Notice of Incomplete Application. The

-6Sa-

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)}

application can not be processed further until such time as it

is complete. This Ruling can be referred to the

Commissioner for final determination.

Appendix I - Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations

[67a - 132a]

The constitutional provision involved is the Fourth

Amendment to the U.S. Constitution which provides:

“The right of the people to be secure in their persons,

houses, papers, and effects, against unreasonable

searches and seizures, shall not be violated, and no

warrants shall issue, but upon probable cause,

supported by oath or affirmation, and particularly

describing the place to be searched, and the persons

or things to be seized.”

The Statutes involved are:

ECL § 15-0505 entitled “Protection of navigable

waters; excavation or fill; permit” provides:

1. No person, local public corporation or interstate

authority shali excavate or place fill below the mean

high water level in any of the navigable waters of the

state, or in marshes, estuaries, tidal marshes and

wetlands that are adjacent to and contiguous at any

point to any of the navigable waters of the state and

that are inundated at mean high water level or tide,

without a permit issued pursuant to subdivision 3 of

this section. For the purposes of this section, fill shall

include, but shall not be limited to, earth, clay, silt,

sand, gravel, stone, rock, shale, concrete (whole or

fragmentary), ashes, cinders, slag, metal, or any other

similar material whether or not enclosed or contained

by (1) crib work of wood, timber, logs, concrete or

-67a-

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

metal, (2) bulkheads and cofferdams of timber

sheeting, bracing and piling or steel sheet piling or

steel H piling, separated or in combination. Nothing

contained in this section is intended to be, nor shall

be construed to limit, impair or affect the

memorandum of understanding which any state

department enters into with the Department of

Environmental Conservation or the general powers

and duties of the Department of Transportation

relating to canals or the general powers and duties of

the Department of Environmental Conservation

relating to flood control.

ECL §25-0102 entitled “Declaration of policy”

provides:

It is declared to be the public policy of this state to

preserve and protect tidal wetlands, and to prevent

their despoliation and destruction, giving due

consideration to the reasonable economic and social

development of the state.

ECL § 25-0404 entitled “Judicial review” provides:

Any person aggrieved by the issuance, denial,

suspension, or revocation of a permit may within

thirty days from the date of the commissioner's order

seek judicial review pursuant to article seventy-eight

of the civil practice law and rules in the supreme

court for the county in which the tidal wetlands

-68a-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations}

affected are located. In the event that the court may

find that the determination of the commissioner

constitutes the equivalent of a taking without

compensation, and the land so regulated otherwise

meets the interest and objectives of this act it may, at

the election of the commissioner, either set aside the

order or require the commissioner to acquire the tidal

wetlands or such rights in them as have been taken,

proceeding under the power of eminent domain.

ECL §70-0103 entitled “Legislative findings and

declarations” provides:

The legislature finds and declares that:

|. It is the intent of the legislature to assure the fair,

expeditious and thorough administrative review of

regulatory permits.

2. It is the intent of the legislature that, to the extent

feasible and appropriate, statutory and regulatory

procedures shall be made uniform and inconsistencies

and redundancies shall be eliminated.

3. It is the intent of the legislature to establish

reasonable time periods for administrative agency

action on permits.

4. It is the intent of the legislature to encourage

public participation in government review and

-69a-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

decision-making processes and to promote public

understanding of all government activities.

5. It is the intent of the legis! ture that, to the

maximum extent feasible, a comprehensive project

review approach shall replace separate and individual

permit application reviews.

ECL §70-0109 entitled “Time periods for department

action On permit applications provides:

1. (a) On or before fifteen calendar days after the

receipt of an application for a permit which has been

filed in a manner and in a form prescribed by the

department, the department shall mail written notice

to the applicant of its determination whether or not

the application is complete.

(b) If the department fails to mail written notice to an

applicant of its determination whether or not an

application is complete within such fifteen calendar

day period, the application shall be deemed complete.

(c) If the department determines the application is

not complete, the notice shall include a concise

statement of the respects in which the application is

incomplete.

-70a-

Appendix |

|Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations}

d) The resubmission of the application or the

submission of such additional information shall

commence a new fifteen calendar day period for

department review of the additional information for

purposes of determining completeness.

(e) If the department determines the application is

complete, the notice shall so state.

2. (a) Immediately upon determining that an

application is complete, the department shall cause a

notice of application to be published in the next

available environmental notice bulletin which shall

be not later than ten calendar days after the date of

such determination and not less than once during the

fifteen calendar day period following such

determination in a newspaper having general

circulation in the area in which the project is

proposed to be located, and shall provide notice to the

chief executive officer of each municipality in which

the proposed project is located, and may direct the

applicant to provide such reasonable notice and

opportunity for comment to the public as the

department deems appropriate. Newspaper

publications shall be provided by the applicant.

(b) The time period for public comment on a permit

application shall be stated in the notice of application.

-7la- :

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

3. (a) Within the time periods specified in

subparagraphs (i) and (ii) of this subdivision and

subject to the provisions of subdivisions four, five

and six of this section, the department shall make a

decision on an application for a permit by mailing the

applicant a permit, a permit with conditions or a

statement that the permit applied for has been denied.

(i) Inthe case of an application for a permit for

which no public hearing has been held, such decision

shall be mailed on or before ninety calendar days

after the department mails written notice to the

applicant that the application is complete or on or

before ninety calendar days after the application is

deemed complete pursuant to the provisions of this

article.

(ii) In the case of an application for a permit for

which a public hearing has been held, the department

shall mail its decision to the applicant and to all

parties to the hearing on or before sixty calendar days

after receipt by the department of a complete record,

as that term is defined in paragraphs (a)

through (e) of subdivision one of section three

hundred two of the state administrative procedure act.

(b) If the department fails to mail a decision on an

application for a permit within the time periods

specified, the applicant may cause notice of such

failure to be made to the department by means of

-72a-

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations}

certified mail return receipt requested addressed to

the commissioner. If, within five working days after

the receipt of such notice, the department fails to mail

a decision, the application shall be deemed approved

and a permit deemed granted subject to any standard

terms or conditions applicable to such a permit.

However, no permit shall be deemed approved where

such permit is issued in lieu of a federal permit

pursuant to an authorization granted to the state

pursuant to either Public Law 94-580, the "Federal

Resource Conservation and Recovery Act of 1976",

or Title V of Public Law 101-549, the "Clean Air

Act", and where the issuance of a permit in such a

manner is contrary to such authorization.

4. The time periods for a department decision on an

application for a permit as specified in subdivision

three of this section shall be suspended pending

receipt by the department of any final environmental

impact statement and any explicit findings related to

a proposed project as may be required pursuant to

article eight (environmental quality review) of this

chapter when the department is not the lead agency as

that term is used in rules and regulations adopted by

the department pursuant to section 8-0113 of said

article.

5. The department shall make no decision and no

permit shall be deemed granted until the applicant has

paid all applicable fees and costs.

-73a-

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

6. Any time period specified in this article may be

waived and extended for good cause by written

request by the applicant with the consent of the

department, or by the written request of the

commissioner or his designee with the consent of the

applicant.

6 NYCRR §608.5 entitled “Excavation or placement

of fill in navigable waters” provides:

(a) Permit required. No person, local public

corporation or interstate authority may excavate from

or place fill, either directly or indirectly, in any of the

navigable waters of the state or.in marshes, estuaries,

tidal marshes and wetlands that are adjacent to an

contiguous at any point to any of the navigable waters

of the state, and that are inundated at mean high water

level or tide, without a permit issued pursuant to this

Part.

6 NYCRR §621.1 entitled “Definitions” provided:

(a) Adjudicatory public hearing means a trial type

proceeding which provides the opportunity for

adjudication on the basis of evidence, including direct

testimony and cross examination provided under

article 3 of the State Administrative Procedure Act,

section 70-0109 of the Environmental Conservation

Law (ECL), section 621.6 of this Part and Part 624 of

this Title.

Appendix i

|Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

(b) Chief permit administrator means an employee

of the department located in the main office of the

department and designated to act on the

commissioner's behalf in carrying out this Part.

(c) Commissioner means the Commissioner of

Environmental Conservation, or any employee of the

department designated to act on the commissioner's

behalf in carrying out this Part.

(d) Complete application means an application for a

permit which is in an approved form and is

determined by the department to be complete for the

purpose of commencing review of the application but

which may need to be supplemented during the

course of review in order to enable the department to

make the findings and determinations required by

law.

(e) Delegated permit means a permit issued by the

department for which a comparable permit may be

required by Federal law. Delegated permits are issued

by the department for the following programs:

(1) Resource Conservation and Recovery Act

(RCRA) of 1976, 42 USC 6901 et seq., 1984 (see

section 621.16 of this Part) (ECL article 27, title 9)

for any hazardous waste management facilities

(HWMEBP) or remedial action plans (RAP) under ECL

article 27, title 9 except those limited to the disposal

-7Sa-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations|

of waste containing polychlorinated biphenyl (PCB)

only.

(2) Clean Water Act (CWA) amendments, 33 USC

1251 et seq., 1987 (see section 621.16 of this Part)

(ECL article 17, titles 7 and 8) for

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.