Petition for Writ of Certiorari — Palmieri v. New York State Department of Environmental Conservation (No. 06-1134)

Supreme Court brief2006

Ask Donna

What actually matters in this document.

Text

Live , 2007

No. eae

3 belt ne . tke f

In The

Supreme Court of the

Gnuited States

*

PAUL PALMIERI,

Petitioner,

-against-

NEW YORK STATE DEPARTMENT OF

ENVIRONMENTAL CONSERVATION, ERIN M.

CROTTY,. Commissioner and MOLLY T.

McBRIDE, Administrative Law Judge,

Respondents.

On Petition for Writ of Certiorari to the United

States Court of Appeals for the Second Circuit

ee eens

Se

PETITION FOR A WRIT OF CERTIORARI

nes

a

R. BERTIL PETERSON

Counsel of Record, Attorney for

Petitioner and Staff Counsel for

The Coalition of Landlords,

Homeowners & Merchants, Inc.

28 East Main Street

Babylon, New York 11702

(631) 376-2110

Sd

QUESTION PRESENTED FOR REVIEW

Did petitioner’s refusal to surrender his Fourth

Amendment right to security in his property

necessitate the denial of his permit application?

Did petitioner fail to meet his burden of

demonstrating that respondent’s demand for a pre-

permit inspection on his property was unreasonable

and unnecessary in order to evaluate petitioner’s

application for a tidal wetlands permit authorizing

construction of a dock extension and boat lifts in the

water 92 feet away form petitioner’s yard?

Does CPLR 306-b provide courts with discretion to

__extend a complainant’s time to serve defendants in

order to avoid the kind of miscarriage of justice that

took place in this case, in light of the deprivation by

the respondent of the petitioner’s Fourth Amendment

rights?

Did the ruling of the Commissioner of the NYSDEC

demonstrate an utter disregard for the United States

Constitution that should be vacated, annulled and

reversed?

Was the lower court’s dismissal of petitioner’s

petition upon the ground that it was time barred a

miscarriage of justice?

Did respondent, as punishment for his refusal to

abide a violation of his Fourth Amendment rights,

unreasonably refuse to conduct a pre-permit

QUESTION PRESENTED FOR REVIEW

(Continued)

inspection of the area adjacent to, and beneath, an

existing dock that protrudes 92 feet away from

petitioner’s yard and into the bay using a boat, a

method which had been used previously during a pre-

permit inspection of petitioner’s prior tidal wetlands’

permit application and which is the only reasonable

way of inspecting the area in question?

Should the “special needs” test be expanded to permit

a governmental agency to deny a private property

owner his right against unreasonable searches, and to

be secure in his property, as protected by the Fourth

Amendment to the United States Constitution under

circumstances where a governmental agency seeks

access to private property as part of a construction

permit process, not an emergency criminal

investigation or prevention?

Should all private owners of waterfront property be

stripped of their Fourth Amendment right against

unreasonable searches and seizures and to be secure

in their property because their rear property faces a

body of water?

Did respondent, as punishment for petitioner’s refusal

to abide a violation of his Fourth Amendment rights,

unreasonably refuse to conduct a pre-permit

inspection of the area adjacent to, and beneath, an

existing dock that protrudes 92 feet away from

petitioner’s yard and into the bay using a boat, a

li

10.

11.

12.

QUESTION PRESENTED FOR REVIEW

(Continued)

method which had been used previously during a pre-

permit inspection of petitioner’s prior tidal wetlands’

permit application and which is the only reasonable

way of inspecting the area in question?

Could respondents even conduct a warrantless

pre-permit inspection, while on petitioner’s property,

of an area in a bay adjacent to, and beneath, an

existing dock that protrudes 92 feet away from

petitioner’s yard?

Was respondents’ denial of petitioner’s tidal

wetlands’ permit application, as punishment for his

refusal to abide a violation of his Fourth Amendment

Rights, upon the ground that petitioner refused to

give his consent to a pre-permit warrantless

inspection of his property and the area adjacent to,

and beneath, an existing dock that protrudes 92 feet

away from his yard and into the bay, a violation of

petitioner’s right against unreasonable search and

seizure under the Fourth Amendment to the United

States Constitution?

Assuming that respondents demonstrated a_ special

need” to enter petitioner’s property, did such need

constitute a constitutionally acceptable exception to

plaintiff's right not to be subjected to an unreasonable

search and seizure under the Fourth Amendment to

the United States Constitution?

ill

13.

14.

15.

16.

QUESTION PRESENTED FOR REVIEW

(Continued)

Is a warrantless pre-permit inspection during which

representatives of a governmental agency walk

through closed gates across the front yard, side yard,

and entire length of the back yard of petitioner’s

private residential property a minimal intrusion?

Was a warrantless pre-permit inspection on

petitioner’s private residential property a matter of

governmental interest?

Did respondent governmental agency demonstrate

disregard for its own rules and the rule of law by not

deeming petitioner’s application for a wetlands’

permit complete pursuant to ECL §70-0109(1)(a) and

(b) and 6 NYCRR §621.5 (b)(2) and by failing to

send petitioner its first notice of incomplete

application within 15 days of its receipt of

petitioner’s permit application as the afore-mentioned

rules require?

Did the respondent governmental demonstrate

disregard for its own rules and the rule of law by not

deeming petitioner’s application for a wetlands’

permit complete pursuant to ECL §70-0109(1)(d) and

by failing to send petitioner its second notice of

incomplete application within 15 days of its receip’ of

additional information from petitioner as the afore-

mentioned rules require?

iV

LIST OF PARTIES

The parties are the petitioner, Paul Palmieri, and the

respondent, the New York State Department of

Environmental Conservation hereatter (“DEC”).

TABLE OF CONTENTS

ee he ee ieee ee ae i

PONS 6G bE eae Lees ee ees Vv

emia ae ee Vv

ey Oe IN oi kc: So ee ae ke Ree vi

ee PN oe ne a ee re x

SN I fg el eae ae te es eran nag l

Eo NE I i i i i a ee a I

Srmlemment OF WuittsGitiOn. ow wc eee eee ]

Constitutional Provision and Statutes Involved ......... I

nn ir a ee eee ek as f-

SI 3 td ee ag hee ee es 5

RI po Fe) Sas oe ee eS ey ee nee 16

TABLE OF AUTHORITIES

Cases: Page(s)

Brooklyn Housing and Family

Services, Inc. v. Lynch,

_191 Misc.2d 341 (Kings Co. Sup. Ct. 2002) .......... 12

Colon v. Bailey,

26 A.D.3d 454, 455-456,

810 N.Y.S.2d 511

DRE I oc he OR re Ue oe 2, 14 (twice)

DiCarlo v. City of New York,

286 A.D.2d 363, 365 (24 Dept. 2001) .... 1... eee. 5

Dutchess County D.S.S. v. Day

Wey heehee ko 7 (thrice)

Leader v. Maroney, Ponzini & Spencer,

Pe WE es a ae tsb eR a on ee 11 (twice)

Matter of Atlantic Cement Co. v. Williams,

cae eee Oe, FO CS et. TFET) i ow ee ee ks, 4

Matter of Benlevi Obedian & Belevi v.

New York State Dept. of Envtl. Conservation,

144 A.D.2d 358, 361 (2d Dept. 1988),

appeal dismissed 74 N.Y 2d 650 (1989) ............... 4

Matter of Calm Lake Dev. v.

Town Bd. of Town of Farmington,

213 A726 979 (" Dest. 1995)... 2. ee ee 5

vi

Cases: Page(s)

Matter of Northern Metro.

Residential Healthcare Facility v. Novello,

24 A.D.3d 1069, n. 1 (3d Dept. 2005) ................ 5

Matter of Oak Is. Beach Assn. v. Flacke,

96 A.D.2d 841, 465 N.Y.S.2d 596

(2d Dept. 1983) motion for leave denied

oe et od | er ee 2, 5 (twice), 10

Matter of Paul Palmieri, appellant, v.

New York State Department of

Environmental Conservation, respondent,

31 A.D.3d 647 (2d Dept. 2006) motion

for leave denied 2006 N.Y. LEXIS 3585

(November 21, 2006)

Matter of Paul Palmieri, appellani, v.

New York State Department of

Environmental Conservation, et al. respondents,

2006 NY Slip Op 5793; 2006 N.Y. App.

Div. LEXIS 9378 under Appellate Division

Docket No. 2004-5943; Suffolk County

Index No. 3925/02

Matter of Saltzman v. Board

of Appeals of Vil. of Roslyn,

26 A.D.3d 505, 506, 811 N.Y.S.2d 99

ep | Bee meprarat ere ee _.. 2, 14 (twice)

Cases: Page(s)

Matter of Thompson v. Department of

Envil. Conservation of the State of New York,

132 A.D.2d 665 (2d Dept. 1987) app. den.

71 N.Y.S.2d 803 (1988) ..... Sick oats eo tile ele 4,5

Palmieri v. Lynch,

392 F.3d 73 73 (2d Cir. 2004)

cert. denied 126 S.Ct. 424,

S65 L. BEAR Fee CaO Oe os hee dha. 4 (twice)

Rochester Canoe Club v. Jorling,

150 Misc.2d 321

Cre Se, ee OO. Bee Ssh eee eee 8,15

Spinnenweber v. New York State

Department of Environmental Conservation

120 A.D.2d 172 (3d Dept. 1986) ..............

Town of Islip v. Powell

78 Misc.2d 1007

mp: Sh. Se, BO ok ee ee

Vernonia School Dist. 47J v. Acton,

515 U.S. 646, 654-661, 115 S.Ct. 2386,

ee Yb)... | ne errr ree re orn Gs.

Statutes:

GO MTCRR Seton Gi 116) 5 nee ee aeeiews

OG NVCRM ane Gil Fe . se oo ee eee

Vili

Statutes: Page(s)

EE 2,4

ES SS l

CPLR Section 306-b ........ 2, 11 (four times), 14 (twice)

CPLR Section 307 (1) and (2) . 2, 12 (twice), 13 (twice), 14

EE re 2,9

Er 2, 13

Conservation Law Section 429-c .................05. 2

Conservation Law Section 432(1) ................ 2,10

ee 2,8

ECL Section 15-0503

ECL Section 15-0505

CS 2, 8 (twice)

ECL Section 15-0905 ... 2, 7 (thrice), 9, 10 (thrice), 14, 15

ECL Section 25-0404 .......... 2, 5, 6, 7 (twice), 10, 15

General Construction Law Section 20 ........... 2, 7,10

Peavemetnon Law pection3Z.6..................... 2,7

1X

TABLE OF APPENDICES

APPENDIX A

Decision of the Court of Appeals,

State of New York, Dated and

Entered November 21, 1006 ................ la

APPENDIX B

Decision of the Appellate Division,

Second Department, State of New

York, dated and Entered July 18, 2006....... 2a-4a

APPENDIX C

Order of Supreme Court, State of

New York, County of Suffolk, Dated

and Filed January 5, 2005 ................. Sa-9a

APPENDIX D

Memorandum Decision of Supreme Court,

State of New York, County of Suffolk,

Dated and Filed May 5, 2003 ............ 10a-21la

APPENDIX E

Decision of the Commissioner, State

of New York, Department of

Environmental Conservation,

Dated and Filed April 7, 2004 .......... 22a- 33a

TABLE OF APPENDICES

(Continued)

APPENDIX F

Hearing Report of Administrative

Law Judge Molly T. McBride

Dated January 30,2004 ..........

APPENDIX G

Ruling of the Commissioner, State

of New York, Department of

Environmental Conservation,

Dated and Filed February 1, 2002...

APPENDIX H

Ruling on Motion and Summary

Report of Molly McBride (ALJ)... .

APPENDIX I

Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations

xi

alae. 34a- 46a

Mesias Sla- 66a

_... 67a- 103a

OPINIONS BELOW

The opinion of the Court of Appeals, State of New

York, the court below, is reported at 2006 N.Y. LEXIS 3585

(November 21, 2006), and the opinion of the Appellate

Division of State Supreme Court, Second Department, is

reported at 31 A.D.3d 647 (2d Dept. 2006). The opinion of

the Supreme Court of the State of New York, County of

Suffolk, is not reported.

DATE JUDGMENT ENTERED

The order of the Supreme Court of the State of New

York, County of Suffolk, which is dated January 5, 2005 was

filed on January 5, 2005.

STATEMENT OF JURISDICTION

This Court has jurisdiction under 28 U.S.C. Section

1257.

CONSTITUTIONAL PROVISION

AND STATUTES INVOLVED

The constitutional provision involved is the Fourth

Amendment to the U.S. Constitution which provides:

“The right of the people to be secure in their persons,

houses, papers, and effects, against unreasonable

searches and seizures, shall not be violated, and no

warrants shall issue, but upon probable cause,

supported by oath or affirmation, and particularly

describing the place to be searched, and the persons

or things to be seized.”

The statutes involved are 6 NYCRR Sections

621.1{c], 621.7[f] and 621.15[b], Civil Practice Law and

Rules (“CPLR”) Sections 306-b, 307(1) and (2), CPLR Rules

2103(b)(2) and 3025(a), Conservation Law Sections 429-c

and 432(1), Environmental Conservation Law (“ECL”)

Sections 15-0501, 15-0503, 15-050 15-0515, 15-0905 and

25-0404, General Construction Law Section 20 and

Navigation Law Section 32.

STATEMENT OF THE CASE

This is an appeal from a decision and order dated and

entered on November 21, 2006 of the Court of Appeals of

the State of New York denying petitioner’s motion for leave

to appeal an order of the Appellate Division, Second

Department, dated and entered in the office of the Clerk of

the Appellate Division on July 18, 2006, holding that the visi

prius court properly dismissed the petitioner’s petition as

time barred; the nisi prius court correctly applied the 30-day

limitations period in ECL 25-0404 and held that the petition,

filed 57 days after the determination of the Commissioner of

the State of New York Department of Environmental

Conservation (hereafter “DEC”) was untimely citing Matter

of Oak Is. Beach Assn v. Flacke, 96 A.D.2d 841 (2d Dept.

1983) mot. leave den. 62 N.Y .2d 606 (1984); the petitioner

offered no good cause for his delay in serving the DEC, and

that branch of his cross motion which was for leave to extend

the time for service was made over three months after his

first attempt at service; and that the nisi prius court

providently exercised its discretion in denying that branch of

the cross motion citing Matter of Saltzman v. Board of

Appeals of Vil. of Roslyn, 26 A.D.3d 505, 506, 811 N.Y.S.2d

99 (2d Dept. 2006) and Colon v. Bailey, 26 A.D.3d 454, 455-

456, 810 N.Y.S.2d 511 (2d Dept. 2006)).

In a companion case, argued in, and decided by the

Appellate Division, Second Department, on the same day’;

decided by the Court of Appeals of the State of New York,

on the same day, for which review is being sought in a

petition for a writ of certiorari that will be submitted to this

Court on the same day as the within petition, the Appellate

Division, Second Department, ruled as follows:

“In a proceeding pursuant to CPLR article 78 to

review a determination of the New York State

Department of Environmental Conservation pursuant

to Environmental Conservation Law articles 15 and

—25 that, inter alia, the petitioner’s application for a

permit to extend his dock was incomplete, the

petitioner appeals, as limited by his brief, from stated

portions of a judgment of the Supreme Court, Suffolk

County (Baisley, J.), dated July 25, 2003, which, inter

alia, upon, in effect, determining that the petitioner’s

wetland permit was complete, directed an

administrative hearing on the issue of whether an

inspection of his property by the Department of

Environmental Conservation was reasonably

necessary.

“Ordered that the judgment is affirmed insofar as

appealed from, with costs

l. Reported as /n the Matter of Paul Palmieri, appellant, v.

New York State Department of Environmental

——~ Conservation et al., respondents, 2006 NY Slip Op 5793,

31 A.D.3d 645, 820 N.Y.S.2d 77, 2006 N.Y. App. Div.

LEXIS 9378 under Appellate Division Docket No. 2004-

5943, Suffolk County Index No. 3925/02.

*

.

“The Supreme Court, in effect, determined that the

petitioner’s wetlands permit application was

complete. However, the fact that an application is

complete does not preclude the Department of

Environmental Conservation (hereinafter the DEC)

from requesting supplemental information, including

an on-site inspection, during the postcompletion

review of an application (see 6 NYCRR 621.1[c];

621.7[f]; 621.15[b]; Matter of Benlevi Obedian &

Benlevi v. New York State Dept. of Envil.

Conservation, 144 AD2d 358, 361 [1988]; Matter of

Atlantic Cement Co. v. Williams, 129 AD2d 84, 90

[1987]). Under the circumstances of this case, the

Supreme Court properly directed an [*2]

administrative hearing on the issue of whether an

inspection of the petitioner’s property was reasonably

necessary.

“Contrary to the petitioner’s contention, the Fourth

Amendment to the United States Constitution does

not bar a warrantless inspection of his premises (see

Palmieri v. Lynch, 392 F3d 73 [2004], cert denied

546 US _, 126 S Ct 424 [2005]; see also Vernonia

School Dist. 47.J Acton, 515 US 646 [1995]; Matter

of Thompson v. Department of Envil. Conservation of

State of NY, 132 AD2d 665 [1987]). A request by the

DEC for an on-site inspection of the wetlands and

adjacent areas on his property, in order to review the

accuracy and impact of the petitioner’s permit

application, fell within the special needs exception to

the Fourth Amendment’s warrant requirement (see

Palmieri v. Lynch, supra). \n this instance, the state’s

interest in protecting wetlands is strong. Moreover,

the petitioner’s expectation of privacy was

diminished by the fact that his yard was open and

exposed to the Great South Bay, that he applied for a

permit to build in tidal wetlands, that he had

previously consented to periodic inspections, and that

the inspection would be a minimal intrusion (id; see

also Vernonia School Dist. 47J v. Acton, supra;

Matter of Thompson v. Department of Envil.

Conservation of State of N.¥., supra).

The petitioner’s remaining contentions are without

merit (see Matter of Northern Metro. Residential

Healthcare Facility, Inc. v. Novello, 24 AD3d 1069,

1071 n 1 [2005]; DiCarlo v. City of New York, 286

AD2d 363, 365 [2001], Matter of Calm Lake Dev. v.

Town Bd. of Town of Farmington, 213 AD2d 979

[1995]). Florio, J.P., Crane, Ritter and Fisher, JJ.,

concur. |

LEGAL ARGUMENT

The decision and order of the Appellate Division,

Second Department, erroneously ruled that the Supreme

Court of Suffolk County had correctly applied the 30-day

limitations period contained in ECL 25-0404 when it held

that petitioner’s petition, filed 57 days after the determination

of the Commissioner of the New York State Department of

Environmental Conservation (hereafter “the DEC”), was

untimely in reliance upon the case of Matter of Oak Is. Beach

Assn. v. Flacke, supra.

Petitioner contends that the 30-day statute of

limitations contained in ECL §25-0404 that was applied by

the Appellate Division in the case of Matter of Oak Is. Beach

Assn. v. I'lacke, supra. should not have been applied in this

case and that the 60-day statute that is contained in ECL §15-

0905 was the applicable statute to be applied in the case at

bar.

The Petitioner’s Article 78

Proceeding Is Not Time Barred:

Annexed as an exhibit to the petitioner’s petition to

the nisi prius court was a copy of the April 7, 2004 decision

of Erin Crotty, Commissioner of the New York State

Department of Environmental Conservation. The caption of

that decision states as follows: “In the Matter - of- the

application for a tidal wetlands permit, use and protection of

water permit, and water quality certification pursuant to the

Environmental Conservation Law (ECL) Articles 15 and 25,

and title 6 of the Official Compilation of Codes, Rules and

Regulations of the State of New York (6 NYCRR) parts 608

and 661 - by- Paul Palmieri, Applicant, PERMIT

APPLICATION NO. | - 4720 - 00666/00009".

Thus, petitioner’ application was brought pursuant to

both Article 25 and Article 15 of the Environmental

Conservation Law (“ECL”).

In the nisi prius court, the NYSDEC made the claim

that petitioner applied for “two” permits, one a “tidal wetland

permit” and the other a “use and protection of waters

permit”. This claim was erroneous. Petitioner applied for

one permit, not two, pursuant to two articles of the

Environmental Conservation Law (ECL”), Articles 15 and

25.

The nisi prius court, the Appellate Division and the

Court of Appeals all applied the 30-day statute of limitations

for Article 78 proceedings found in ECL Section 25-0404

and ignored the 60-day statute of limitations contained in

ECL Section 15-0905. As will be demonstrated, application

of the 30-day statute of limitations rather than the 60-day

statute of limitations to petitioner’s Article 78 proceeding

constituted error.

Under New York law, statutes which relate to the

same subject matter must be construed together unless a

contrary legislative intent is expressed (See Dutchess County

D.S.S. v. Day, 96 N.Y.2d 149 (2001)). Courts must

harmonize the various provisions of related statutes and

construe them in a way that renders them internally

compatible (/d.). Another well-established rule of statutory

construction in the state of New York provides that a general

statute yields to a specific or special statute” (id).

ECL Section 15-0905 (the 60-day statute) applies to

all proceedings before the NYSDEC that are “affected by a

decision made pursuant to [Article 15]” (ECL §15-0905).

Subdivision | of Section 15-0503, which is contained in

Article 15 of the ECL, states that no “dock, pier, wharf or

other structure, temporary or permanent, used as a landing

place on waters, shall be erected, reconstructed or repaired . .

. without a permit” [from the Department of Environmental

Conservation} ”. Therefore, ECL Section 15-0503 is more

specific than is ECL §25-0404 (the 30-day statute of

limitations) which applies to all persons “aggrieved by the

issuance, denial, suspension, or revocation of a permit”.

Not only is ECL §15-0503 more specific than is ECL

§25-0404, it has been in existence longer and is derived from

Section 32 of the Navigation Law (L. 1965, ch. 955, §9) and

Section 429-c of the Conservation Law.

New York courts have consistently applied 60-day

statute of limitations contained in ECL Section 15-0905 to

the denial of permits to build a dock (See i.e. Spinnenweber

v. New York State Department of Environmental

Conservation, 120 A.D.2d 172 (3d Dept. 1986); Zown of

Islip v. Powell, 78 Misc.2d 1007 (Sup. Ct. Suff. Co. 1974);

Rochester Canoe Club v. Jorling, 150 Misc.2d 321 (Sup. Ct.

Mon. Co. 1991)).

Pursuant to Section 15- 0503(1)(b) the term

‘reconstructed’ as used in relation to docks, wharves,

platforms, breakwaters, mooring or other structures Means

“the substantial rebuilding of structures or facilities and shall

not apply to ordinary maintenance or repair of existing

functional structures or facilities, such as repainting,

redriving pilings or replacing broken boards in docks”.

The decision of Commissioner Crotty concludes at

page 10 that “[a]pplicant has applied to the Department for

the privilege of constructing a long extension to a dock in a

protected tidal wetland”.

Based upon the foregoing, Commissioner’s April 7,

2004 decision was governed by the 60-day statute of

limitations contained in Article 15 of the ECL and not by the

30-day statute contained in Article 25 of the ECL.

Section 15 - 0515 of the ECL entitled “Review”

provides that “[a] determination, order or issuance,

modification or denial of a permit, pursuant to Sections 15 -

0501, 15 - 0503 and 15 - 0505 shall be reviewable in a

proceeding pursuant to article 78 of the Civil Practice Law

and Rules”.

Section 15 - 0905 of the ECL, also entitled “Review”

provides in relevant part as follows:

“|. The applicant or any person or public

corporation, who or which has filed a notice of ©

appearance in the proceedings before the department

and is affected by a decision made pursuant to this

article, may review such decision under the

provisions of article 78 of the Civil Practice Law and

rules.

“2. A special proceeding for such review must be

commenced within 60 days after the service in person

or by mail of a copy of the decision upon the attorney

of record of the applicant and of each person who has

filed a notice of appearance, or to.such applicant in

person directly if not represented by an attorney.”

Annexed to petitioner’s Article 78 petition as Exhibit

“A” was a letter dated April 13, 2004 from James T.

McClymonds, Chief Administrative Law Judge, to

petitioner’s attorney enclosing a copy of the April 7, 2004

decision of Commissioner Croty. Pursuant to ECL Section

15 - 0905(2), petitioner had 60 days from the date of Mr.

McClymonds letter to commence his Article 78 proceeding

against the DEC and, pursuant to CPLR Rule 2103(b) (2),

had an additional 5 days because the decision was mailed to

petitioner’s attorney. Therefore, petitioner had 65 days

within which to commence his Article 78 proceeding

measured from the date of mailing of the decision to

petitioner’s attorney.

This means that since the decision of Commissioner

Crotty was mailed on April 13, 2004, excluding the date of

mailing (See New York’s General Construction Law §20),

petitioner’s Article 78 proceeding could be commenced on or

before June 17, 2004. In fact, petitioner’s Article 78

proceeding was commenced on June 3, 2004 by the filing of

a Notice of Petition, Petition and Exhibits, two (2) weeks

short of the expiration of 65 days from the date of mailing of

Commissioner Crotty’s decision to the petitioner’s attorney.

In Spinnenweber v. New York State Department of

Environmental Conservation, supra., the court ruled: “ECL

15 - 0905(1) formerly Conservation Law §432(1), provides

that any person who is affected by a decision made pursuant

‘to this article’ may seek judicial review of such decision

under the provisions of CPLR article 78. ECL 15 - 0905(2)

formerly Conservation Law §432(2), provided, however, that

such proceeding must be commenced within 60 days of that

decision”. (emphasis supplied)

The lower courts’ reliance upon Matter of Oak Beach

Association, Inc. v. Flacke, supra. is misplaced because that

case concerned application of the 30-day statute of limitation

contained in ECL §25-0404 to a permit to extend and widen

a pier, not as in the case at bar, a permit for the construction

of a dock which is expressly governed by the 60-day statute

of limitations contained in ECL §15-0905.

Accordingly, such part of the respondent’s motion as

sought the dismissal of petitioner’s petition upon the ground

that it was commenced untimely should have been, in all

respects, DENIED.

10

Petitioner Offered a Good Cause

for His Delay in Serving the DEC:

The Lower Courts Should Have Exercised

Their Discretion to Extend Petitioner’s Time

to Effectuate Service Pursuant to CPLR 306-b:

The DEC admitted at page | of its memorandum of

law that “[t]his proceeding was initiated 57 days after the

date of the Commissioner’s April 7, 2004 order, by the filing

of the notice of petition and petition on June 3, 2004" but

claimed that, pursuant to CPLR §306-b, petitioner failed to

serve the DEC within fifteen days after the expiration of the

statute of limitations applicable to a challenge of the

wetlands permit denial.

Pursuant to CPLR §306-b, petitioner was required to

serve the DEC on or before June 21, 2004, which was the

fifteenth day after expiration on June 6, 2004 of the 60 day

statute of limitations.

In Leader v. Maroney, Ponzini & Spencer, 97 N.Y .2d

95 (2001), New York’s Court of Appeals determined the

standards by which a court may, “upon good cause shown or

in the interest of justice” exercise its discretion to extend a

plaintiff s time to effectuate service pursuant to CPLR §306-

b.

In Leader, the Court ruled that in enacting CPLR

§306-b, the Legislature gave a court two separate standards

by which to measure an application for an extension of time

to serve. Although the “good cause” standard encompasses

“reasonably diligent efforts at service”, a court may also

consider any other factor in making its determination,

1]

including length of delay in service, the promptness of a

plaintiff's request for an extension of time and prejudice to

the defendant, which is wholly lacking in this case.

As set forth herein, petitioner made reasonably

diligent efforts to serve the DEC, the length of delay in

service was minimal, petitioner promptly requested an

extension of time and there was no prejudice to the DEC

(Brooklyn Housing and Family Services, Inc. v. Lynch, 191

Misc.2d 341 (Kings Co. Sup. Ct. 2002)). Accordingly,

petitioner requests that this Court exercise its discretion,

reverse the lower courts and excuse any delay that may have

occurred in serving the DEC with petitioner’s Notice of

Petition, Petition and exhibits.

Petitioner Made Reasonably Diligent

Efforts to Serve; Length of Delay Was

Minimal, Petitioner Promptly Requested

an Extension of Time; and There Was No

Prejudice to the DEC:

Personal service on a state agency such as the DEC

can be made by “(1) delivering the summons to . . . the chief

executive officer of such agency . . . or (2) by mailing the

summons by certified mail, return receipt requested . . . to the

chief executive officer of such agency, and by personal

service upon the state in the manner provided by subdivision

one of this section” (CPLR Section 307(2)).

CPLR Section 307(1) provides that “[p]ersonal

service upon the state shall be made by delivering the

summons to an assistant attorney-general at an office of the

attorney - general or to the attorney - general within the

state”.

12

in accordance with CPLR Sections 307(1) and (2), on

June 8, 2004, petitioner personally served the Attorney

General of the State of New York with copies of his initial

Article 78 Notice of Petition, Petition and Exhibits but did

not serve copies upon the DEC as required by CPLR 307(2).

However, on June 24, 2004, petitioner served a copy

of his Supplemental Notice of Petition’ , together with copies

of his initial Petition and Exhibits on the DEC by mailing

same U.S. Express Mail, certified mail, return receipt

requested, to the DEC which the DEC received on June 25,

2004; and, on June 25, 2004, served a copy of the

Supplemental Notice of Petition, together with copies of his

initial Petition and Exhibits on the State of New York “by

personal service upon the state in the manner provided by

subdivision one of this section”.

On July 26, 2004, petitioner served his second

Supplemental Notice of Petition dated July 15, 2004,

together with copies of his initial Petition and Exhibits, upon

Erin M. Crotty, Chief Executive Officer of the DEC by

mailing same U.S. Express Mail, “certified mail, return

receipt requested, to . . . the chief executive officer of

such agency” and upon the State of New York by personal

wm

Pursuant to CPLR Rule 3025(a) petitioner was permitted

to supplement his notice of petition “once without leave of

court within twenty days after its service”. Alternatively,

CPLR Rule 3025(a) provides that petitioner could

supplement his notice of petition “within twenty days aficr

service of a pleading responding to it”. Since it is a

matter of record that the DEC has never served a pleading

responding to petitioner's Article 78 petition, the time

within which petitioner could supplement his notice of

petition never even began to run.

13

service in the manner provided by CPLR Rule 307(1), viz.

upon the Attorney General.

Therefore, the first time that the DEC was served

with copies of petitioner’s Notice of Petition, Petition and

Exhibits was June 24, 2004. Since petitioner had until on or

before June 21, 2004 to timely serve the DEC pursuant to

CPLR §306-b, service upon the DEC on June 24, 2004 was a

mere three days late and service on June 25, 2004 was a mere

four days late.

Therefore, petitioner made diligent efforts to

effectuate service upon the DEC, the length of delay in

service was minimal, petitioner promptly requested an

extension of time and there was no prejudice to the DEC.

Consequently, the lower courts should have exercised their

discretion to extend petitioner’s time to effectuate service

pursuant to CPLR §306-b.

The lower courts’ reliance upon the cases of Matter

of Saltzman v. Board of Appeals of Vil. of Roslyn, supra. and

Colon v. Bailey, supra. constituted error. In Sa/tzman, the

petitioners waited a year and a half before seeking an

extension of time and in Colon, the plaintiffs eschewed due

diligence by, inéer alia, failing to produce their process

server, without explanation, other than to say that he was not

available, did not otherwise ask to proceed at the hearing,

and instead asked for an adjournment of approximately six

weeks to produce their process server.

If the lower courts’ decisions and orders are permitted

to stand, the body of law applicable to the 60-day statute of

limitations contained in ECL Section 15-0905 which

expressly applies to the denial of permits to build a dock (See

14

i.e. Spinnenweber v. New York State Department of

Environmental Conservation, supra., lown of Islip v.

Powell, supra.,; Rochester Canoe Club v. Jorling, supra.)

will be hopelessly confused with the body of law applying -

ECL §25-0404 (the 30-day statute of limitations) to persons

“aggrieved by the issuance, denial, suspension, or revocation

of a permit”.

The lower courts’ decisions and orders involve a

matter of public importance and involves an important

question of law. The 60-day statute of limitations contained

in ECL §15-0905 has never been addressed by this Court.

CONCLUSION

The petition should be granted.

Respectfully submitted,

R. Bertil Peterson

Counsel of Record

Attorney for Petitioner and

Staff Counsel for

The Coalition of Landlords,

Homeowners & Merchants, Inc.

Attorney for Petitioner

28 East Main Street

Babylon, New York 11702

(631) 376-2110

16

Appendix A - Decision of the Court of Appeals, State

New York, Dated and Entered November

21, 2006 [la]

STATE OF NEW YORK

COURT OF APPEALS

Ata session of the Court, held at Court

of Appeals Hall in the City of Albany

on the twenty-first day of November, 2006

PRESENT, HON. JUDITH KAYE, Chief Judge, presiding

2-10 Mo. No. 1023

In the Matter of Paul Palmieri,

Appellant,

Vv.

New York State Department of

Environmental Conservation,

Respondent.

A motion for leave to appeal to the Court of Appeals

in the above cause having heretofore been made upon the

part of the appellant herein and papers having been submitted

thereon and due deliberation having been thereupon had, it is

ORDERED, that the said motion be and the same

hereby is denied.

S/

Stuart M. Cohen

Clerk of the Court

~-la-

Appendix B - Decision of the Appellate Division, Second

Department, State of New York, Dated and

Entered July 18, 2006 [2a - 4a]

APPELLATE DIVISION

SECOND DEPARTMENT

In the Matter of Paul Palmieri,

Appellant,

V.

New York State Department of

Environmental Conservation,

Respondents.

Docket No. 2005 - 2686

Suffolk Co. Index No. 13500/04

2006 NY Slip Op 5794; 31 A.D.3d 647

819 N.Y.S.2d 76, 2006 N.Y. App. Div. LEXTS 9379

In a proceeding pursuant to CPLR article 78 to

review a determination of the New York State Depariment of

Environmental Conservation that an on-site inspection of the

wetlands and adjacent areas on the petitioner's property was

reasonably necessary for the review of his application for a

permit to extend his dock pursuant to Environmental

Conservation Law articles 15 and 25, and that his application

was denied unless and until he allowed the inspection, the

petitioner appeals, as limited by his brief, from so much of an

order and judgment (one paper) of the Supreme Court,

Suffolk County (Baisley.), dated January 5, 2005, as granted

that branch of the respondent’s motion which was to dismiss

-2a-

Appendix B

{Decision of the Appellate Division, Second Department,

State of New York, Dated and Entered July 18, 2006]

the petition as time-barred, denied that branch of his cross-

motion which was for leave to extend the time to personally

serve the respondent, and dismissed he proceeding.

ORDERED that the order and judgment is affirmed

insofar as appealed from, with costs.

Contrary to the petitioner’s contention, the Supreme

Court properly dismissed the petition as time-barred. The

Supreme Court correctly applied the 30-day limitations

period in ECL 25-0404 and held that the petition, filed 57

days after the determination of the Commissioner of the State

of New York Department of Environmental Conservation

(hereinafter the DEC), was untimely (see Matter of Oak Is.

Beach Assn. v. Flacke, 96 A.D.2d 841, 465 N.Y.S.2d 596).

Furthermore, the petitioner offered no good cause for

his delay in serving the DEC, and that branch of his

cross motion which was for leave to extend the time

for service was made over three months after his first

attempt at service. Accordingly, the Supreme Court

providently exercised its discretion in denying that

branch of the cross motion (see Matter of Saltzman v.

Board of Appeals of Vil. of Roslyn, 26 A.D.3d 505,

506, 811 N.Y.S.2d 99; Colon v. Bailey, 26 A.D.3d

454, 455-456, 810 N.Y.S.2d 511).

Appendix B

[Decision of the Appellate Division, Second Department,

State of New York, Dated and Entered July 18, 2006|

In light of our determination, we need not reach the

petitioner’s remaining contentions. FLORIO, J.P., CRANE,

RITTER and FISHER, JJ., concur.

-493-

Appendix C - Order of Supreme Court, State of New

York, County of Suffolk, Dated and Filed

January 5, 2005 [5a - 9a]

SHORT FORM ORDER INDEX NO. 04-13500

SUPREME COURT - STATE OF NEW YORK

LA.S. PART 36 - SUFFOLK COUNTY

PRESENT:

Hon. _ PAUL J. BAISLEY, JR.

Justice of the Supreme Court

MOTION DATE 6-3-04 (#001 & 002)

10-07-04 (#003 & 004)

ADJ. DATE 10-14-04

Mot. Seq.#001- CASEDISP

002- MG

003-MD

004-XMD

ceieaacieicioailedaiascedlasiibae diciiaiionsaphiad xX

PAUL PALMIERI,

Petitioner,

-against-

NEW YORK STATE DEPARTMENT OF

ENVIRONMENTAL CONSERVATION,

Respondent.

Appendix C

{Order of Supreme Court, State of New York,

County of Suffolk, Dated and Filed January 5, 2005]

R. BERTIL PETERSON, ESQ.

Attorney for the Petitioner

28 East Main Street

Babylon, New York 11702

ELIOT SPITZER, ESQ.

Attorney General for the

State of New York

By: Gregory J. Nolan, Esq.

120 Broadway, 26" Floor

New York, New York 10271-0332

Upon the following papers numbered | to 39 read on

this Article 78 proceeding and motions to dismiss and cross

motion to extend time to serve petition; Notice of

Petition/Petition and supporting papers 1- 11; Motion and

supporting papers 12- 17; 18- 22; 23- 28; Answering

Affidavits and supporting papers 29- 33; Replying Affidavits

and supporting papers 34- 39; Other ; (anc-after-hearing

counsel m-supportand opposed tothe mottan) it 1s,

ORDERED that the motion (motion sequence no.

002) by respondent New York State Department of

Environmental Conservation for a dismissal of the petition

(motion sequence no. 001) on the basis that the proceeding

was untimely commenced and for lack of personal

jurisdiction is granted to the extent that the proceeding is

dismissed as time barred; and it is further

-6a-

{Order of Supreme Court, State of New York,

County of Suffolk, Dated and Filed January 5, 2005]

ORDERED that the motion (motion sequence no.

003) by respondent New York State Department of

Environmental Conservation for a dismissal of the

petitioner’s supplemental notice and petition is denied as

moot; and it is further

ORDERED that the cross-motion (motion sequence

no. 004) by petitioner for leave to extend the time to

personally serve respondent New York State Department of

Environmental Conservation in accordance with CPLR

Section 306-b is denied as moot.

In this Article 78 proceeding petitioner seeks a

judgment annulling and reversing a determination by the

Commissioner of the respondent New York State

Department of Environmental Conservation (NYSDEC)

adopting the recommendation of an Administrative Law

Judge, made after an adjudicatory hearing, that petitioner

failed to meet his burden of demonstrating that the

NYSDEC’s request for an on-site inspection of petitioner’ s

real property was not reasonable and necessary to evaluate

his application for a tidal wetlands permit and that

petitioner’s failure to allow such inspection necessitated the

denial of his permit application. The adjudicatory hearing

was conduced at the direction of this Court by its decision,

dated May 5, 2003 (Baisley, J.), in a prior Article 78

proceeding commenced be petitioner after the NYSDEC

declared his tidal wetlands permit incomplete because he had

~

[Order of Supreme Court, State of New York,

County of Suffolk, Dated and Filed January 5, 2005]

declined to allow the NYSDEC to conduct an on-site

inspection of his property.’

Respondent NYSDEC now moves to dismiss the

petition on the basis that the proceeding was untimely

commenced. Pursuant to ECL Section 25-0404, any person

aggrieved by the denial of a tidal wetlands permit may within

thirty (30) days from the date of the commissioner’s order

seek judicial review pursuant to CPLR Article 78. The

thirty-day period runs from the date of the order, not its

service (Oak Island Beach Ass’n v. Flecke |sic.|, 96 AD2d

841, 465 NYS2d 596 [1983] app den 62 NY2d 606, 482

NYS2d 1023).

Since the Commissioner’s order is dated April 7,

2004, and the petition herein was not filed until 57 days later,

on June 3, 2004, the proceeding was not timely commenced

(see Obedian v. New York State Department of

Environmental Conservation, 108 AD2d 749, 485 NYS2d

98 [1985]). Petitioner’s attempt to re-characterize the

petition as one seeking judicial review in accordance with

ECL 15-0515, which would thus entitle the proceeding to the

sixty-day period of limitations provided for such

proceedings, is without merit. The administrative law judge,

the Commissioner and the petitioner himself all clearly

referred to and treated petitioner’s permit application as one

| The Article 78 proceeding was entitled Palmieri v. New

York State Department of Environmental Conservation,

and was filed under Suffolk County Index No. 02-3925.

-Sa-

{Order of Supreme Court, State of New York,

County of Suffolk, Dated and Filed January 5, 2005]

for a tidal wetlands permit under Title 25 of the

Environmental Conservation Law. Respondent NYSDEC’s

motion to dismiss the petition is therefore granted

Respondent NYSDEC’s additional motion to dismiss the

petitioner’s supplemental notice of petition and petition and

petitioner’s cross-motion for leave to extend the time to

personally serve respondent NYSDEC are both denied, as

moot.

Accordingly, the proceeding is dismissed.

Dated: January 5, 2005 S/

X FINAL DISPOSITION _ NON-FINAL

DISPOSITION

i)

The Court acknowledges that petitioner would also be

required to obtain a permit under Title 5 of Article 15

(Protection of Waters) of the ECL for his proposed dock

Nevertheless, tn the absence of a tidal wetlands permit he

may not build that dock.

-9a-

Appendix D - Memorandum Decision of Supreme Court,

State of New York, County of Suffolk,

Dated and Filed May 5, 2003 [10a - 21a]

MEMORANDUM

SUPREME COURT, SUFFOLK COUNTY 1I.A.S. PART 36

Paul Palmieri, By: Baisley, J.S.C.

Petitioner, Dated: May 5, 2003

Vv. Index No. 02-3925

New York State Department of Mot. Seq. #001-

Environmental Conservation; ERIN SDISPSJ

M. CROTTY, Commissioner;

and MOLLY T. McBRIDE, Return Date: 4-3-02

Administrative Law Judge, Adjourned: 1-16-

03

Respondents.

TIMOTHY M. McENANEY, ESQ.

Attorney for the Plaintiffs

28 East Main Street

Babylon, New York 11702

ELIOT SPITZER, ESQ.

New York State Attorney General

By: Gregory J. Nolan, Esq.

120 Broadway, 26" Floor

New York, New York 10271-0332

-10a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

This Article 78 proceeding arises out of respondent’s

denial of petitioner’s application for a tidal wetland permit.

The petitioner owns property located in Babylon, New York

which adjoins the Great South Bay. The property is

improved by the petitioner’s house and backyard fencing.

The rear of the property, which is adjacent to the water, is

improved with a bulkhead, a 92 foot long dock extending

outward from the bulkhead and three boat lifts.

In 1991 the petitioner applied for and was granted

tidal wetlands permits for the reconstruction of a bulkhead

and construction of a 30 foot by 10 foot ramp, a 5 foot by 45

foot float and pilings and a 52 foot fixed pier with additional

pilings and two boat lifts. Following construction of these

improvements and in January of 1993, the petitioner applied

for another tidal wetlands permit to extend the existing 52

foot dock an additional 110 feet and to add two more boat

lifts. This application was denied by the respondent, the

New York State Department of Environmental Conservation

(NYSDEC), on November 4, 1993. Following the

petitioner’s request for an administrative hearing, a

settlement was reached wherein it was greed that a permit

would be issued for a dock extension of 40 feet and for

construction of an additional boat lift (Administrative

Record, pages 22-23).

The petitioner submitted the current application for a

tidal wetlands permit in May of 1999. He sought to extend

the existing 92 foot dock by 50 feet and to add another boat

lift. By a NOTICE OF INCOMPLETE APPLICATION

-lla-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

(Incomplete Notice) dated July 13, 1999, NYSDEC informed

the petitioner that his application was incomplete in that he

was required to submit photographs, project plans, a location

map, a recent survey, proof that the proposed dock extension

and boat lift were reasonable and necessary and information

as to how many boats would be moored (Administrative

Record, page 56). The petitioner was served with a second

“Notice of Incomplete Application” (Second Incomplete

Notice) which indicated that his application was still

designated as incomplete as he had failed to submit a recent

survey of the project site (Administrative Record, page 64).

By letter dated April 7, 2000, NYSDEC informed the

petitioner that his application was complete except for an on-

site inspection. Following petitioner’s continued refusal to

allow NYSDEC to conduct an on-site inspection, NYSDEC

denied the permit application by “Notice of Permit Denial”

(Notice of Denial), dated July 7, 2000. NYSDEC denied the

application on the ground that the petitioner failed to allow

NYSDEC to conduct an on-site inspection of the property.

The Notice of Denial further informed the petitioner that he

had a right to a public hearing pursuant to NYCRR 621.7(f).

Subsequently, the petitioner requested a hearing on the denial

of the permit.’ The hearing, which was initially scheduled

for March 21, 2001, was adjourned to June 25, 2001 because

of NYSDEC staff unavailability. Neither the petitioner nor

his attorney appeared at the adjourned hearing.

f In NYSDEC’s request for a hearing, it indicated that a

Notice of Complete Application was not required since the

proposed activity was classified as a minor project.

-|2a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

NYSDEC then moved for administrative judicial

intervention. On the motion NYSDEC contended that the

petitioner’s failure to appear at the re-scheduled hearing

should be considered as an abandonment or withdrawal of

the request for a hearing or a default. NYSDEC contended

alternatively, that NYSDEC’s denial of the permit

application should be affirmed without the need for an

adjudicatory hearing on the ground that controlling

administrative case law precludes a hearing until petitioner

consents to an On site inspection. Petitioner opposed the

motion on the grounds that NYSDEC failed to confirm the

adjourned hearing date and to provide proof of publication of

the notice of hearing.’

An undated decision was rendered on the petitioner’s

motion by Administrative Law Judge Molly McBride (ALJ,

the “McBride Ruling”). Initially, the ALJ determined that

there was no confirmation that petitioner’s attorney saw the

notice of the adjourned hearing. The ALJ further determined

“Frankly, scheduling errors occur and such a sever penalty as

requested by Staff [NYSDEC] is not warranted here”

(Administrative Record, page 7). With regard to NYSDEC’s

2. Petitioncr’s attorney, in a letter dated April 27, 2000,

contended that NYSDIC could conduct a review of the

permit application in a manner less intrusive than an on-

site inspection, particularly where there ts an aliernative

method of inspection such as from a waterway.

Petitioner's attorney further contended that a non-

consensual on-site inspection was tantamount to an illegal

-|3a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

alternate request for relief, the ALJ determined that

NYSDEC could not determine whether the application met

the standards for permit issuance without conducting an on-

site inspection. The ALJ decided that if it cannot be

determined whether the standards have been met, then the

application cannot be deemed complete. The ALJ

recommended that the Notice of Denial be vacated and

replaced with a Notice of Incomplete Application. The ALJ

further recommended that the petitioner’s request for a

hearing be treated as void since such a request could not be

made in response to a Notice of Incomplete Application.

The ALJ concluded that there could be no further processing

of the petitioner’s application until it was complete.

In a Ruling dated February |, 2002, the respondent

Erin M. Crotty as the Commissioner of NYSDEC, adopted

the decision of the ALJ (the Commissioner’s Ruling). The

Commissioner commented in the Ruling:

“] find that the Applicant’s tidal wetlands application

under review must be deemed incomplete for the

purposes of permit processing under the

Department’s Uniform Procedures, 6 NYCRR part

621. The Applicant’s denial of access to his property

prevented Department Staff from evaluating the on-

site conditions and the proposed project. The ability

to gather such information is necessary to make the

determination that the permit application is complete.

The Applicant’s actions effectively relieves

Department Staff from taking any further action on

-14a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003}

the permit application until access to the site and site

information is available for Staffs review. Further, I

am determining that the Applicant’s request for

hearing on its proposed project is void until such time

as the site access and the necessary information is

made part of the permit application. Thereafter, if

and when said information is supplied and Staffs

redetermination is to deny the proposed project, then

the Applicant will be afforded a hearing on Staffs

denial of the requested permit” (Administrative

Record, pages 2 to 3).

Petitioner then commenced this special proceeding by

service of a notice of petition and verified petition.

Petitioner subsequently served an amended verified petition.

Petitioner seeks in the amended petition a judgment

annulling and vacating the Commissioner’s ruling to the

extent it affirms those portions of the McBride ruling

determining that the petitioner’s application was incomplete

and that the petitioner’s request for a hearing was void.

Petitioner also seeks a review of the McBride Ruling.

Petitioner contends that: (i) pursuant to 6 NYCRR 621.4(k),

an on-site inspection by a NYSDEC staff member is not one

of the requirements for a complete permit,’ (ii) the McBride

decision violates the provisions of ECL 70-0109(1)(a)(b) and

6 NYCRR 621.5(b) which deem an application complete

3. Petitioner avers that he has no objection to an on-site

inspection by a private environmental consultant pursuant

to 6 NYCRR 621.4¢(k)(i1)

-|5a-

Appendix D

[Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003}

unless NYSDEC mails a Wiiiten [sic.] notice that the

application is incomplete within 15 calendar days, (iii) the

ALJ in the McBride Ruling improperly relied on an Interim

Decision of the Deputy Commissioner of NYSDEC, dated

November 6, 2000 (the Bath Storage decision) in holding

that an adjudicatory hearing is not available for review of a

permit denial based on the incompleteness of the application,

and (iv) NYSDEC’s attempt to enforce a non-consensual,

warrantless site inspection violates petitioner’s right against

unreasonable search and seizure under the Fourth

Amendment of the United States Constitution. Petitioner

further contends that his property does not come wthin

NYSDEC’s wetland permit jurisdiction pursuant to ECL

0505(1) and 6 NYCRR 608.5.*

Petitioner’s claim that NYSDEC lacked jurisdiction

to either grant or deny a tidal wetlands permit for the

petitioner’s project is considered first. Article 25 of the

4. Petitioner’s attorney also contended in the reply

affirmation that the permit application should be deemed

approved on the basis of the five day demand provisions

of 6 NYCRR 621.9(b)(c). The Court did not consider this

contention since the issue was not raised at the

administrative level (Ambry v. Bd. of Trs. of N.Y. City

Fire Dep 't, 298 A.D.2d 582, 748 N.Y.S.2d 681 [2002}).

The cases cited by the petitioner to the contrary are

inapposite since this issue does not relate to whether the

Court has subject matter jurisdiction over this Article 78

proceeding (Cf, Fry v. Village of Tarrytown, 89 NY2d

714, 658 N.Y.S.2d 205 (19971) (sic.).

-16a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003}

Environmental Conservation Law (Tidal Wetlands Act) was

enacted as an expression of the State’s public policy “to

preserve and protect tidal wetlands. .. ” (ECL 25-0102).

Although the provisions of ECL 0505(1) and 6 NYCRR

608.5 acknowledge the Towns’ control over the wetlands in

the Counties of Nassau and Suffolk, these provisions should

not be interpreted to preclude joint control over the issuance

of wetland permits by the respective governmental entities

(see, Huntington v. Albicocco, 66 AD2d 886, 411 NYS2d

675 [1978]). The provisions of Article 25 specifically state

that the tidal wetland permits issued by NYSDEC shall be in

addition to, and not in lieu of, any such permits required by

the affected local municipality (ECL 25-0401(1); Weinberg,

Practice Commentaries, McKinney’s Cons Laws of NY,

Book 17 1/2, ECL Section 25-0401, p. 433; see, 6 NYCRR

661 3).

Petitioner’s contention that NYSDEC’s attempt to

enforce a non-consensual site inspection of his property

violates his constitutional rights is also without merit.

Where NYSDEC can demonstrate a reasonable need for the

scientific information obtained by an on-site inspection, such

inspections may be valid criteria for a wetlands permit

(Thompson v. Department of Environmental Conservation,

132 AD2d 665, 518 NYS2d 36 [19871 [sic.] app. den. 71

NY2d 803, 527 NYS2d 769; see, 6 NYCRR 621.15(b)). The

cases cited by the petitioner (see Stender v. Albany, 188

AD2d 986, 592 NYS2d 70, 547 NYS2d 68 [1992], app. dis.

81 NY2d 1006, 599 NYS2d 805; Brookhaven v. Ronkoma

[sic.] Realty Corp., 154 AD2d 665, [19891) [sic.] are

-17a-

Appendix D. |

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

inapposite in that an on-site inspection is a minimal intrusion

and petitioner’s project poses a diminished expectation of

privacy and as well is a matter of significant governmental

interest (ECL 25-0102; 6 NYCRR 661.1, 661.9(b)(1); see Bd

of Educ. v. Earls, 536 US 822, 829, 122 S Ct 2559, 153 L Ed

2d 735 [2002]).

Petitioner’s other contentions in effect challenge that

part of the Commissioner’s Ruling that NYSDEC is relieved

from any further action including a hearing on the

petitioner’s application until he complies with its demand for

an on-site inspection. In reaching this determination the

Commissioner adopted the McBride Ruling as his own.

Accordingly, in order to determine the efficacy of the

Commissioner’s Ruling, the court must review the findings

in the McBride Ruling.

The record establishes that initially NYSDEC

afforded the petitioner the right to a public adjudicatory

hearing in the Notice of Denial. This hearing was adjourned

because of NYSDEC’s inability to proceed. Although

neither the petitioner nor his attorney appeared at the

adjourned date of the hearing, the ALJ subsequently

determined that petitioner should not be deprived of his right

to a hearing on this ground. The ALJ, by characterizing the

petitioner’s application as incomplete, determined that no

further action, including the adjudicatory hearing, could be

taken. The Court finds that this was error and petitioner

should have been afforded the opportunity at an adjudicatory

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

hearing to demonstrate whether NYSDEC’s request for an

on-site inspection was reasonable and necessary.”

Following petitioner’s submission of his tidal

wetlands permit, he was served with the Incomplete Notices

which did not require an on-site inspection. The

requirements for a complete application are listed in 6

NYCRR 661.12(a)(1), 6 NYCRR 621.3 and under the

circumstances of this case, also in 6 NYCRR 621 .4(k).

Although these sections do not specifically provide for an

on-site inspection as a prerequisite for a complete

application, NYSDEC has the general authority to request

supplemental information during the course of permit review

to enable it [to] make the findings and determinations

required by law (6 NYCRR 621.1(d)). NYSDEC may also

request during the permit review process additional

information “which is reasonably necessary to make any

findings or determinations required by law” (6 NYCRR

621.15(b), emphasis added). NYSDEC may fix a date for

receipt of the additional information and if the information is

5. The ALJ found that NYSDEC could not determine if the

petitioner’s application met the standards for permit

issuance without an on-site inspection. This finding was

premature, not having been based on evidence adduced

in an adjudicatory hearing.

-19a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003]

not timely submitted it “may be grounds for denial of the

application” (6 NYCRR 621.15(b), emphasis added).°

Here petitioner’s application was denied on the

ground that without a site inspection NYSDEC could not

determine whether or not the petitioner’s proposal complied

with the standards for permit issuance. Petitioner, upon his

request pursuant to 6 NYCRR 621.7(f), was entitled to an

adjudicatory hearing on whether or not NYSDEC’s demand

for an on-site inspection was reasonably necessary to make

the required findings or determinations with regard to the

petitioner’s permit application. The ALJ’s reliance on the

Bath Storage decision is misplaced. the Deputy

Commissioner in Bath Storage noted:

“There may be times when an application is

determined to be complete by Staff but after further

review, Staff requests additional information in

accordance with 6 NYCRR 621.15(b). In some of

these instances, adjudication might proceed on points

of dispute where a reasonable interpretation

indicates that supplemental information is necessary

6. NYSDEC, in its memorandum of law in opposition to the

petition, requests that “should the DEC’s action not be

found to be a non-reviewable determination that Palmieri’s

permit application is incomplete, it should be viewed

as a denial of the application on the ground that Palmieri

failed to mect his burden of establishing that his proposed

project meets all applicable regulatory standards” (pages

17-18).

-20a-

Appendix D

{Memorandum Decision of Supreme Court, State of New

York, County of Suffolk, Dated and Filed May 5, 2003}

to complete staff's review. Such is not the case in

this proceeding” (amended verified petition, Exhibit

G, page 5, emphasis added).

In the case at bar NYSDEC had determined that

petitioner’s application was complete except for information

to be derived from an on-site inspection which NYSDEC

believed was reasonably necessary for its review of the

petitioner’s permit. Requiring an adjudicatory hearing on

this issue would not, as the Deputy Commissioner opined in

Bath Storage, turn “the permitting process on its head.”

Accordingly, this petition is granted to the extent that

petitioner is held to be entitled to an adjudicatory hearing

pursuant to 6 NYCRR 621.7(f), and is otherwise denied.

Petitioner shall have the burden at such hearing of

demonstrating that NYSDEC’s demand for an on-site

inspection of the petitioner’s property is not reasonably

necessary in order to evaluate the petitioner’s application for

a wetlands permit (6 NYCRR 624.9(b)(1)).

Settle judgment on five days’ notice.

PAUL J. BAISLEY, JR.

JSC.

Appendix E - Decision of the Commissioner, State of New

York, Department of Environmental

Conservation, Dated and Filed April 7,

2004 [22a - 33a]

STATE OF NEW YORK DEPARTMENT

OF ENVIRONMENTAL CONSERVATION

625 Broadway

Albany, New York 12233-1550

In the Matter

<Of-

the application for a tidal wetlands permit,

use and protection of water permit, and water

quality certification pursuant to the

Environmental Conservation Law (ECL)

articles 15 and 25, and Title 6 of the Official

Compilation of Codes, Rules and Regulations

of the State of New York (6 NYCRR)

Parts 608 and 661

-by

PAUL PALMIERI

Applicant.

PERMIT APPLICATION No. 1-4720-00666/00009

DECISION OF THE COMMISSIONER

April 7, 2004

-22a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

DECISION OF THE COMMISSIONER

The attached hearing report, except for the section

headed “Recommendation,” of Administrative Law Judge

(“ALJ”) Molly T. McBride in the matter of the application of

Paul Palmieri for a tidal wetlands permit, protection of

waters permit, and water quality certification is hereby

adopted as the decision in this matter subject to the following

additional findings and conclusions.

This matter is before the Department of

Environmental Conservation (“Department”) pursuant to an

order of Supreme Court, Suffolk County (see Matter of

Palmieri v. New York State Dept. of Envtl. Conservation,

Sup Ct, Suffolk County, May 5, 2003, Baisley, J., Index No.

02-3925). In that order, Supreme Court remanded the matter

to the Department to afford applicant Paul Palmieri an

adjudicatory hearing on the issue of whether Department

staff's demand for an on-site inspection of applicant’s

property is reasonably necessary in order to evaluate

applicant’s application for a tidal wetlands permit (see id. at

6). The court placed the burden upon applicant to

demonstrate that the Department’s demand is not reasonably

necessary in order to evaluate his application (see id.).

The hearing record demonstrates that applicant failed

to meet his burden of proof that Department staff's request to

inspect the project site from applicant’s property is not

reasonably necessary. Accordingly, for the reasons stated in

-23a-

Appendix E

|Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

the hearing report and in this decision, I affirm Department

staff's denial of the permit application.

Discussion

As an initial matter, it is important to note the narrow

scope of the issue remanded for hearing by Supreme Court,

Applicant devotes significant portions of his post-hearing

brief to the ALJ to the argument that Department staff's

demand for a pre-permit inspection on applicant’s property to

evaluate his wetlands permit application constitutes an

unreasonable intrusion and unconstitutional search in

violation of the Fourth Amendment of the United States

Constitution, and an illegal trespass under New York law. In

its order in the CPLR article 78 proceeding initiated by

applicant, however, Supreme Court expressly rejected these

arguments. The court held:

“{ Applicant’s] contention that NYSDEC’s attempt to

enforce a non-consensual site inspection of his

property violates his constitutional rights is also

without merit. Where NYSDEC can demonstrate a

reasonable need for the scientific information

obtained by an on-site inspection, such inspections

may be valid criteria for a wetlands permit .. . The

cases cited by the petitioner . . . are inapposite in that

an On-site inspection is a minimal intrusion and

petitioner’s project poses a diminished expectation of

-24a-

Appendix E

{Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

privacy and as well is a matter of significant governmental

interest”

(id. at 4-S [citations omitted]; see also Palmieri v. Lynch, US

Dist Ct, Ed NY, Aug. 29, 2003, Seybert, J., 00-CV-3225

| dismissing similar claims under federal law that the

Department’s on-site inspection violated applicant’s 4"

Amendment rights]).

The court also expressly recognized that the

Department has the authority to request during the permit

review process additional information that is “reasonably

necessary” to make any findings or determinations required

by law in connection with the permit application, and that an

applicant’s failure to provide such information may be

grounds for denial of an application (see id, at 5 [citing 6

NYCRR 621.1(d) and 621.15(b)]). Thus, applicant’s

arguments under federal and state law were rejected by

Supreme Court, and are not presently before the Department

on this remand.

Accordingly, the narrow issue presented for hearing

is whether Department staffs demand for an on-site

inspection complied with the regulatory requirement of 6

NYCRR 621.15(b), that is whether the demand was

“reasonably necessary” to make the required findings or

determinations with regard to applicant’s tidal wetlands

permit application (see id. at 6). As noted above, Supreme

Court expressly placed the burden of proof on applicant (see

-25a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

id. [citing 6 NYCRR 624 .9(b)(1)]). The regulations

applicable to permit hearing procedures establish that the

party bearing the burden of proof must sustain that burden by

a preponderance of the evidence unless a higher standard has

been established by statute or regulation (see 6 NYCRR

624.9[c]).

Review of the hearing record reveals that applicant

failed to carry his burden of proof. A preponderance of the

credible evidence presented at the hearing establishes that

on-site inspections by Department staff are reasonably

necessary to evaluate tidal wetland permit applications, and

to determine whether statutory and regulatory standards for

permit issuance can be met [see Environmental Conservation

Law 25-0402 & 25-0403, and 6 NYCRR 661.9(b)].

On-site inspections aze reasonably necessary to allow

the Department to most efficiently and effectively carry out

its statutory and regulatory obligations. The record

demonstrates that, due to the high volume of permit

applications filed with the Department’s Region | office, the

limited number of available inspectors must conduct

numerous tidal wetland permit application inspections per

day in an area covering both Nassau and Suffolk Counties.

Department staff's witness testified that on-site

inspections are important in order to obtain the

environmental information necessary for the evaluation of a

tidal wetlands permit application with respect to the

-26a-

Appendix E

|Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 204;

applicable statutory and regulatory criteria. As testified, such

on-site inspections provide significant information,

including, for example, information on the upland

topography, the extent and types of vegetated areas, the

values of upland areas as buffers, existing structures, and

drainage patterns.

Department staff's witness noted that on-site

inspections afford a comprehensive view of the shoreline and

upland areas. From the vantage point of the height of the

bulkhead, it provides an opportunity to observe, among other

things, water flow patterns and te condition of the areas

seaward from the bulkhead.

Moreover, a preponderance of the credible evidence

demonstrates that the Department had a reasonable need for

the environmental information that wold have been obtained

by an on-site inspection in this particular case. Review of

applicant’s permit application materials submitted in 1991,

1993, and 1999, respectively, suggest that the underwater

area under applicant’s dock may be subject to significant

sedimentation and accretion. Thus, applicant’s own

application materials revealed that a significant degree of

sedimentation or accretion was underway in the shoals, mud

flats, and littoral zone just seaward of applicant’s property

that required evaluation before a permit could be issued.

-27a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004

Staff's witness provided detailed reasons why access

to the upland area of applicant’s property was necessary,

including to confirm that accretion was occurring and, if so,

to evaluate its source. He testified that an upland inspection

on applicant’s property would include, for example,

determining the sources and nature of run off from the

property, inspecting the condition of the landward side of the

bulkhead, and inspecting the shoreline adjacent to the

property from a vantage point that allowed a comprehensive

view.

Staff's witness also indicated that the best vantage

point for assessing water quality and the condition of the

shoals and mud flats seaward of the bulkhead was from the

bulkhead itself, and that walking out on applicant’s dock

would provide a more effective means of observing

underwater vegetation growth in the vicinity of the dock.

Applicant did not challenge staff's assertion that an

assessment of the upland area of the project site was a

necessary part of the permit application review. Rather,

applicant’s contention at hearing was that staff could access

the project site either by boat or along the shoreline, and

could conduct the inspection from either of those two routes

without crossing or stepping foot on applicant’s property.

The weight of the record evidence demonstrates that

both alternatives suggested by applicant would provide a

much less effective means for conducting the appropriate

-28a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

inspection, both upland and in the water itself. In addition,

the two alternatives are impracticable, more costly, time

consuming, and wasteful of limited Departmental resources.

With respect to an inspection by boat, the record indicates

that boats appropriate for use in the waters adjacent to

applicant’s project are not available to Department staff that

review tidal wetlands permit application review.’

l Use of a boat, practically and as a matter of Department

policy, requires at least two staff members in order to both

operate the boat and conduct the inspection. The record

clearly establishes that inspections conducted during

routine, high-volume review of tidal wetland applications

are usually conducted by one inspector from land.

to

Applicant introduced a list of boats (sce Exh C) that are

utilized by the Department, and argued that a Department-

owned sixteen-foot Boston whaler was available to staff

to use. Applicant did not establish by a preponderance of

the evidence that the Boston whaler was available to staff

to use.

-29a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

More importantly, the record indicates that inspection

of the upland area, the shoreline, and the relevant underwater

areas would be less effective and significantly hindered if it

had to be conducted from a boat rather than from applicant’s

property. Statf’s witness testified that inspection by boat,

due to safety considerations, would best be conducted during

high tide, a condition less favorable to effective inspection of

underwater shoals and mud flats, and where projects

involving a dock are concerned.

Applicant referred to staff using a boat in 1995 to

visit off-shore around his dock following the Department’s

denial of a prior permit application. This does not compel

the conclusion that access to applicant’s property is not

reasonably necessary to evaluate applicant’s 1999 permit

application. To the contrary, the circumstances surrounding

staff's use of a boat at that time demonstrates such use is

atypical and out of the ordinary.”

3 Applicant contends that staff also visited his site in 1991

by boat. This contention was not corroborated and, thus,

the contention was not established by the preponderance

of the evidence. Moreover, the record is entirely silent

conceming the circumstances surrounding the 1991 visit,

assuming it occurred by boat.

-30a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

As the record demonstrates, significant obstacles and

costs are associated with applicant’s second offered

alternative of an inspection from the shoreline. applicant

failed to establish that access to the shoreline from a public

location was generally known. Moreover, applicant failed to

establish that use of the shoreline would be a safe mens of

gaining access to the project site. At most, applicant’s

witness established that the shoreline was rocky and sandy,

but did not otherwise establish its condition. In contract,

Department staff's witness noted potential hazards associated

with walking along similar shorelines, including the

difficulty of walking over algae-covered rocks and the

presence of sinkhole-like features under the water.

Applicant also failed to indicate the height of the

bulkhead or otherwise establish the bulkhead would not

effectively block the view of the upland area and the area

landward of the bulkhead to a viewer standing on the

shoreline (or a viewer from a boat). To the contrary, staff's

witness testified that bulkheads in the area are generally

about six feet high.

Photographs entered into evidence by the applicant

are the only record evidence of the actual height of the

bulkhead in this case (see Exhs F, G, and H). Those

photographs suggest that the bulkhead is taller than an adult

male, and support the reasonable inference that the view of

the upland area would be significantly blocked to an

inspector of average height standing on the shoreline. In any

-3la-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004]

event, applicant fails to establish, by a preponderance of the

evidence, that such an inspector could effectively conduct the

necessary inspection of the upland area from the shoreline or

from a boat.

Conclusion

The hearing record demonstrates that applicant failed

to carry his burden of establishing, by a preponderance of the

evidence, that staff's demand to conduct an on-site

inspection was not reasonably necessary to make the required

permit application. The weight of the record evidence

supports the conclusion that such access was reasonably

necessary, and that applicant’s two proposed alternatives to

on-site inspection would impose an unreasonable burden

upon the limited resources of the Department and

significantly hinder the necessary environmental assessments

required to determine whether applicant’s application meets

with statutory and regulatory criteria.

Applicant has applied to the Department for the

privilege of constructing a long extension to a dock in a

State-protected tidal wetland. Because staff's request during

the permit application review process for an on-site

inspection was reasonably necessary to make the findings

and determinations required by law, applicant’s refusal to

allow the on-site inspection is ground for denial of the 1999

permit application. Therefore, Department staff's

-32a-

Appendix E

[Decision of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed April 7, 2004|

determination to deny the 1999 permit application is

affirmed.

For the New York State

Department of Environmental

Conservation

S/ OC a eee eee

By: Erin M. Crotty, Commissioner

Dated: April 7, 2004

Albany, New York

Appendix F - Hearing Report of Administrative Law

Judge Molly T. McBride Dated and Filed

January 30, 2004 [34a- 46a]

STATE OF NEW YORK DEPARTMENT

OF ENVIRONMENTAL CONSERVATION

625 Broadway

Albany, New York 12233-1550

In the Matter

-of-

the application for a tidal wetlands permit,

use and protection of water permit, and water

quality certificate pursuant to the

Environmental Conservation Law (ECL)

Articles 15 and 25, and Title 6 of the Official

Compilation of Codes, Rules and Regulations

of the State of New York (6 NYCRR)

Parts 608 and 661 by

PAUL PALMIERI

PERMIT APPLICATION No. 1-4720-00666/00009

HEARING REPORT

-by-

Molly T. McBride

Administrative Law Judge

January 30, 2004

-34a-

Appendix F

|Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

PROCEEDINGS

In May 1999, an application for permits from the

New York State Department of Environmental Conservation

(Department) was made by Paul Palmieri (applicant), 123

East Shore Road, Babylon, New York, for a tidal wetlands

permit, protection of waters permit and water quality

certificate pursuant to ECL Article 25 and 6 NYCRR 661.

The application was denied on July 7, 2000 and applicant

requested an adjudicatory hearing. A hearing was scheduled

for March 27, 2001 but was adjourned duc to the

unavailability of Staff's witness. The hearing was

rescheduled for June 25, 2001. Applicant failed to appear for

the hearing. Department Staff served a notice of motion for

administrative judicial intervention on or about June 28,

2001 asking that the permit application be denied due to

applicant’s failure to appear at the hearing. Applicant

opposed the motion. Department Staff had also moved for

an order affirming its denial of the application due to

applicant’s refusal to allow Staff to conduct a site visit as

part of the permit review process.

The motion was denied with regard to applicant’s

failure to appear for the hearing. By order of Commissioner

Erin M. Crotty dated February 1, 2002, the application was

deemed incomplete due to Department Staff's inability to

enter the property for a site inspection and the hearing

request was deemed void. Applicant commenced a

proceeding in New York State Supreme Court pursuant to

Article 78 of New York Civil Practice Law and Rules

-3Sa-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

(CPLR) challenging the Commissioner’s order. Supreme

Court, Suffolk County, by order of Justice Paul Paisley, Jr.

dated May 5, 2003, remanded the matter to the Department

for a hearing on the sole issue of whether an on-site

inspection by Department Staff, as part of the permit

application review, was reasonably necessary.

BACKGROUND

This applicant has a history of filing permit

applications with the Department for projects at this site. In

1991 applicant applied for a permit to reconstruct a bulkhead

and to construct a 30' x 10' ramp and a 5' x 45' float and

pilings. The permit was issued. Approximately 5 months

later, applicant applied for a permit to construct a 52' fixed

pier with additional pilings. This application was also

granted. In 1993, one year after the second permit was

issued, applicant sought to expand the existing 52' pier an

additiona! 110’, to add 2 boat lifts with 80,000 Ib. and 16,000

Ib. capabilities and to add 4 mooring pilings clusters. Staff

denied this application. A hearing was requested by

applicant after the denial. The parties entered into settlement

discussions. During these discussions, a site visit was done

by Department Staff via boat. Ultimately, the parties

resolved the matter and a Stipulation of Settlement was

entered into on May 30, 1995 wherein applicant agreed to

modify the application and reduce the extension of the boat

dock from 110' to 40' and to reduce the boat lift request from

two boat lifts to one boat lift. Based upon the changes made

to the application as a result of the settlement, Staff withdrew

-36a-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

its objections to the issuance of the permit and a permit was

issued in June 1995.

In May 1999 applicant applied for a permit to

construct an additional 50' extension of the dock and to add

an 80,000 lb. boat lift. This is basically what was requested

by applicant in his 1993 application, when combined with

what was permitted in June 1995.

The May 1999 application was denied by Staff by

letter dated July 7, 2000. The Notice of Permit Denial states,

in part: “You failed to allow Department Staff to inspect the

property to observe the conditions at the site in order to

determine whether or not your proposal complies with the

standards for permit issuance. Therefore, this application for

permit is hereby denied.” It is undisputed that applicant has

refused Staff access to his property to inspect it as part of the

permitting process. Applicant contends that Staff can

conduct whatever inspection is necessary without entering

his property.

Pursuant to the Order of the Supreme Court, a

hearing was conducted on October 8, 2003 at the Babylon

Public Library, 211 route 109, West Babylon, New York

before Administrative Law Judge Molly T. McBride. The

proceedings began with a legislative hearing at

approximately 10:40 a.m. Applicant appeared with his

counsel, Franklin Wilks, Esq. from the Coalition of

Landlords, Homeowners and Merchants. The Department

appeared by Craig L. Elgut, assistant regional attorney. No

-37a-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004}

persons came forward to speak on the project. At the

conclusion of the legislative hearing, an issues conference

was convened. No other persons, agencies or organizations

participated in the hearing process as parties or sought party

status. At the conclusion of the issues conference, the

adjudicatory hearing was immediately commenced on the

sole issue of whether the Department’s demand to conduct an

inspection of the project site from applicant’s property as

part of the permit application review was reasonably

necessary. The Supreme Court placed the burden of proof

for this issue on applicant.

The following witnesses testified on behalf of

applicant: Paul Palmieri and Aram Terchunian, First Coastal

Corp., applicant’s environmental consultant. Charles T.

Hamilton, regional supervisor of the Department’s Office of

Natural Resources, Region One, Stony Brook, New York

testified on behalf of the Department.

The parties submitted post-hearing briefs and the

hearing record closed on December 31, 2003 upon receipt of

the briefs.

POSITION OF THE PARTIES

Applicant

Applicant maintains that the Department can conduct

its permit application review without accessing his property

He contends that the Department can conduct its site

-38a-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

inspection from the water, by boat, or by walking along the

shoreline after entering it from a public access point.

Department

The Department contends that the application can not

be reviewed to determine if the standards for a tidal wetlands

permit have been met without Department personnel

accessing applicant’s property. Department Staff also argues

that applicant’s suggestion of using a boat is not practical

because they can rely on having boats available to do site

inspections.

FINDINGS OF FACT

1. In May 1999, Paul Palmieri, applicant, 123 East

Shore Drive, Babylon, New York, applied for a tidal

wetlands and protection of waters permit and water quality

certificate to expand an existing 92' dock structure by 50 feet

and add an 80,000 pound boat lift at his property noted

above. The proposed project is located on the Great South

Bay, in the Town of Babylon, County of Suffolk.

2. The existing dock structure was permitted by the

Department in three phases. The first phase permitted was to

reconstruct a bulkhead and to construct a 30’ x 10' ramp and

a 5' x 45' float and pilings. The permit was issued in 1991.

Approximately 5 months later, applicant applied for a permit

to construct a 52' fixed pier with additional pilings which

was also granted. A third permit application, filed in 1993,

-39a-

Appendix F

[Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

one year after the second permit was issued, sought to

expand the existing 52' pier an additional 110', to add 2 boat

lifts with 80,000 Ib. and 16,000 lb. capabilities and to add 4

moorings pilings clusters. This application was denied.

After a request for a hearing was filed by applicant, the

matter was resolved by an agreement between the parties

which provided for the extension of the boat dock by 40°

rather than 1 10' and the addition of one boat lift rather than

two.

3. Applicant refused Department Staff access to his

property in 1995 during the review of his 1993 permit

application.

4. Department Staff attempted to access applicant’s

property during its review of the current permit application

and applicant has refused Department Staff access to his

property.

5. Department Staff notified applicant by letter dated

April 7, 2000 that it would need to access the property to

conduct a site inspection and complete the permit application

review.

6. By letter dated July 7, 2000 the Department denied

the latest permit application because it could not gain access

to applicant’s property to complete the permit application

review.

-40a-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

7. Applicant filed a request for a hearing on the

permit application denial. A hearing was scheduled but

adjourned at the request of Staff as witnesses were

unavailable. The hearing was rescheduled but applicant and

his counsel filed to appear on the rescheduled date.

8. Department Staff moved for an order determining

the hearing process abandoned based upon applicant’s failure

to appear for the hearing or, in the alternative, for an order

affirming Staff's denial of the permit application based upon

applicant’s refusal to allow Department Staff on his property

to conduct the site inspection.

9 Commissioner Erin M.Crotty, by order dated

February 1, 2002, denied the motion to dismiss due to

applicant’s failure to appear. The order also deemed the

application incomplete based upon the Staff s inability to

access applicant’s property and, therefore, the hearing

request was voided.

10. Applicant commenced a proceeding in New York

Supreme Court, Suffolk County, pursuant to CPLR Article

78 Challenging the Commissioner’s order. Supreme Court,

Suffolk County (Baisley, J.), by decision dated May 5, 2003

granted the petition to the extent of remanding the matter to

the Department for a hearing to allow applicant an

opportunity to demonstrate the Department’s request for an

on-site inspection was not reasonable and necessary to

evaluate the application for a wetland permit, and otherwise

denied the petition. The decision placed the burden of proof

-4la-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

on applicant for the hearing. The hearing was held on

October 8, 2003.

11. Applicant testified at the October 8, 2003 hearing

that he will not agree to Department Staff entering his

property as part of the permit review process. Applicant

countered Department Staff's request with his suggestion

that Department Staff inspect the project site by boat from

the Great South Bay or enter the shoreline from a public

access point and walk to applicant’s project site. Applicant

has not provided a specific route, specific entry point, nor

provided details to Staff as to what they would find on any

route that they may take to applicant’s property if they did in

fact enter the shoreline from a public access point and walk

to his property.

12. Applicant was advised by Department Staff in

writing that a boat was not available to them to conduct a site

inspection. Applicant did not allow Staff onto his property

after being told that a boat was not available.

13. Department Staff routinely conducts permit

application reviews from an applicant’s property.

Department Staff testified as to numerous reasons why they

need access to applicant’s property as part of this permit

application review.

14. Department Staff testified as to why the

alternatives posed by applicant (walking shoreline or boat

inspection) are not adequate for the permit application

-42a-

Appendix F

[Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

review in this case. Those methods would not allow Staff to

obtain all necessary information to assess the application. By

way of example, Staff testified that there has been an

abnormal amount of accretion in the area around the boat

dock (water depth changed from 5-6' to 2 2 to less than 4'

from 1991 to the date of this application) and Staff would

need to evaluate the upland, as well as the dock location to

assess possible causes/problems. Charles Hamilton

identified approximately twelve items he would be

inspecting from applicant’s property with respect to the

accretion problem alone. Also, from applicant’s property

Staff would have an elevated spot to view organisms and

plants from the water that would not be readily visible from

the shoreline or from a boat in the water. The inspector can

view the shoals and mudflats below for other factors as well.

Based upon those findings, a second site inspection may be

warranted at which time Staff would come out with testing

gear and take some samplings for testing.

15. The Department’s Region One office, where this

application is pending, receives approximately 4,000 tidal

wetland permit applications each calendar year. Each permit

application requires review by Department Staff and four

Staff members are responsible for all tidal wetlands

applications inspections. The alternative methods proposed

by applicant would be too time consuming to employ on a

regular basis in the Department’s application reviews.

16. Charles Hamilton testified that he conducted 27

site inspections on the day before this hearing. He testified

-43a-

Appendix F

|Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

that that number of site inspections is not unusual due to the

volume of permit applications received in their office each

year. His other inspectors typically conduct 10-15

inspections per day. If he and his Staff were required to use

a boat or take a circuitous route to applicant’s property to

conduct site inspections, they would not be able to complete

as many site inspections and application processing would be

delayed.

17. Applicant permitted his environmental consultant

and employees to conduct a site inspection from his property.

18. Supreme Court, Justice Baisley, held that “Where

NYSDEC can demonstrate a reasonable need for the

scientific information obtained by an on-site inspection, such

inspections may be valid criteria for a wetlands permit.”

(Baisley Memorandum Decision, p. 4, citing Thompson v.

Dept. of Environmental Conservation 132 AD 2d 665).

CONCLUSIONS OF LAW

1. Section 624.9(b)(1) of 6 NYCRR states: “The

applicant has the burden of proof to demonstrate that its

proposal will be in compliance with all applicable laws and

regulations administered by the department.” Further, the

Memorandum Decision of Justice Baisley remanding this

matter for a hearing placed the burden of proof on applicant

to show why the Department’s demand for an on-site

inspection of applicant’s property is not reasonably necessary

in order to evaluate the application.

-44a-

Appendix F

| Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

2. This permit application is for a tidal wetlands

permit, protection of waters permit and water quality

certificate.

3. Section 661.1 of 6 NYCRR states, in part, “It is

the public policy of the State to preserve and protect tidal

wetlands, and to prevent their despoliation and destruction,

giving due consideration to the reasonable economic and

social developments of the State.” The Department is

entrusted with implementing the state’s tidal wetlands policy.

4. Section 661.9(b) of 6 NYCRR identifies the

standards for a tidal wetlands permit to be issued. In

summary, the applicable standards require a showing that the

permitted activity will preserve and protect tidal wetlands,

prevent the despoliation and destruction of wetlands, and not

have an undue adverse impact on the present or potential

value of the wetlands for marine food production, wildlife

habitat and flood and hurricane and storm control.

5. Standards for issuance of a water quality

certification are found ai 6 “ YCRR 608.9 and the protection

of waters permit issuance stamdards are found at 6 NYCRR

608.8.

6. Department Staff identified numerous reasons why

they need access to applicant’s property to conduct the

permit application review and why applicant’s alternatives

are not acceptable. Applicant has not met his burden of

proof to show why access to this property is not reasonably

-4Sa-

Appendix F

{Hearing Report of Administrative Law Judge

Molly T. McBride Dated and Filed January 30, 2004]

necessary as part of the permit application review.

Department Staff provided specific sworn testimony as to

why that type of inspection would not be sufficient.

RECOMMENDATION

I recommend that the Commissioner find that

applicant has not met his burden of proof to show that

Department Staff's request for access to his property as part

of its permit application review is not reasonably necessary.

Department Staff has indicated that they must deny the

permit application because they were denied access to the

property. Therefore, I recommend that the Commissioner

affirm Staff's denial of the permit application unless

Respondent provides Department Staff the necessary access

to his property within 20 days of the Commissioner’s

decision. If applicant provides Department Staff with the

necessary access, then I recommend that Staff conduct the

site inspection and take the appropriate action on the

application.

-46a-

Appendix G - Ruling of the Commissioner, State of New

York, Department of Environmental

Conservation, Dated and Filed February

1, 2002 [47a - 50a]

STATE OF NEW YORK

DEPARTMENT OF

ENVIRONMENTAL CONSERVATION

625 Broadway

Albany, New York 12233-1010

In the Matter

-of-

the Application for a tidal wetlands permit,

pursuant to Environmental Conservation

Law of the State of New York (“ECL”)

Article 25 and Title 6 of the Official

Compilation of Codes, Rules and Regulations

of the State of New York (“6 NYCRR”)

Part 661 by

PAUL PALMIERI

Applicant

Application No. 1-4720-09666/00009

RULING OF THE COMMISSIONER

February 1, 2002

-47a-

Appendix G

[Ruling of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed February 1, 2002]

Pursuant to 6 NYCRR Part 624.8(b)(i) Staff of the

New York State Department of Environmental Conservation

(“DEC Staff’, “Department”) duly served a motion for

administrative judicial intervention upon Paul Palmieri (the

“Applicant”) on or about June 28, 2001. Said motion was

supported by the affirmation of assistant regional attorney

Craig L. Elgut, Esq. and the affidavit of DEC staff Charles T.

Hamilton, Supervisor of Natural Resources, Region One.

Applicant opposed said motion by affidavit of Richard

Young, Esq., counsel for Applicant.

The motion seeks an Order determining the

Applicant’s failure to appear for a hearing an abandonment

of the hearing process, thereby deeming the applicant’s

request for a hearing on his tidal wetlands application

withdrawn and denying any further administrative remedy.

In the alternative, Staff seeks an Order that affirms Staff ‘s

denial of the permit application due to the permit application

being incomplete.

Staff documents by affirmation of Craig L. Elgut,

Esq. that:

(i) Applicant applied for a tidal wetlands permit

to expand a residential dock an additional 50

feet and to add an 80,000 Ib. boat lift:

(ii) By letter dated July 7, 2000 DEC Staff denied

the application after notifying applicant that

-48a-

Appendix G

[Ruling of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed February |, 2002]

the Staff required access to the site to

complete the application review and Staff was

denied access;

(iii) | Applicant requested a hearing after receipt of

the denial;

(iv) An adjudicatory hearing was rescheduled to

be held on June 25, 2001.

A copy of the motion and supporting papers and the

Applicant’s opposing affidavit were filed with the Office of

Hearings and Mediation Services. The hearing and the

motion were assigned to Administrative Law Judge Molly 1

McBride (“ALJ”). Attached to this Ruling is the ALJ’s

Ruling on Motion and Summary Report, which I adopt as my

own, subject to my comments below.

.

Under the Department’s permit processing rules,

applicants are required to supply Department Staff with

sufficient information to afford Staff a reasonable

opportunity to evaluate information in determining whether

to approve, modify or deny a request for a Department

permit. As set forth in the ALJ’s report, applicants must

supply this information or otherwise cause their application

to be deemed incomplete requiring further information

before Staff can make a reasonable determination on the

proposed project.

-49a-

Appendix G

{Ruling of the Commissioner, State of New York,

Department of Environmental Conservation,

Dated and Filed February 1, 2002]

I find that the Applicant’s tidal wetlands application

under review must be deemed incomplete for the purposes of

permit processing under the Department’s Uniform

Procedures, 6 NYCRR Part 621. The Applicant’s denial of

access to his property prevented Department Staff from

evaluating the on-site conditions and the proposed project.

The ability to gather such information is necessary to make

the determination that the permit application is complete.

The Applicant’s actions effectively relieves Department Staff

from taking any further action on the permit application until

access to the site and site information is available for Staff's

review. Further I am determining that the Applicant’s

request for hearing on its proposed project is void until such

time as the site access and the necessary information is made

part of the permit application. Thereafter, if and when said

information is supplied and Staff's redetermination is to deny

the proposed project, then the Applicant will be afforded a

hearing on Staff's denial of the requested permit.

For the New York State Department

of Environmenta! Conservation

S/ :

By: — Erin M. Crotty, Commissioner

Date: Albany, New York

February 1, 2002

-50a-

Appendix H - Ruling on Motion and Summary Report of

Molly McBride (ALJ) [Sla - 66a]

STATE OF NEW YORK

DEPARTMENT OF

ENVIRONMENTAL CONSERVATION

625 Broadway

Albany, New York 12233-1010

In the Matter

-of-

the Application for a tidal wetlands permit,

pursuant to Environmental Conservation

Law of the State of New York (“ECL”)

Article 25 and Title 6 of the Official

Compilation of Codes, Rules and Regulations

of the State of New York (“6 NYCRR”)

Part 661 by

PAUL PALMIERI

Applicant

Application No. 1-4720-00666/00009

RULING ON MOTION AND SUMMARY REPORT

-BY-

~ Molly McBride

Administrative Law Judge

-Sla-

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)|

PROCEDURAL BACKGROUND

Applicant Paul Palmieri ("Applicant”) applied to the

New York State Department of Environmental Conservation

(“DEC', "Staff", "Department') in May, 1999 for a tidal

wetlands permit pursuant to ECL Article 25 and 6 NYCRR

661. The application was denied on July 7, 2000 and

Applicant requested an adjudicatory hearing. A hearing was

scheduled for March 27, 2001 but was adjourned due to the

unavailability of Staff's witness. The hearing was

rescheduled for June 25, 2001. Applicant failed to appear for

the hearing. DEC Staff served a notice of motion for

administrative judicial intervention pursuant to 6 NYCRR

624.8(b)(i) on or about June 28, 2001. DEC Staff submitted

the following in Support of the motion: affirmation of

assistant regional attorney Craig L. Elgut, Esq. and the

affidavit of Charles T. Hamilton, Supervisor of Natural

Resources for the DEC, Region One, sworn to on June 28,

2001. Applicant opposed the motion by Affirmation of

Richard W. Young, Esq. counsel for Applicant, dated July

9.2001.

Staff's Motion was served on the Office of Hearings

and Mediation Services as was Applicant's opposing papers.

The hearing and now this motion were assigned to

Administrative Law Judge Molly T. McBride ("ALJ").

Staff moves for an order deeming the Applicant's

failure to appear at an adjudicatory hearing as an

abandonment of the hearing process which in turn deems the

-52a-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)}

Applicant's request for a hearing withdrawn. In the

alternative, Staff seeks an Order that affirms Staffs denial of

the permit application.

BACKGROUND

Applicant owns a private residence at 123 East Shore

Road, Babylon, New York, on the Great South Bay. This

Applicant has a history of filing permit applications with the

Department. In 1991 the Applicant applied for a permit to

reconstruct a bulkhead and to construct a 30' x 10' ramp and

a 5' x 45' float and pilings. The permit was issued.

Approximately 5 months later, Applicant applied for a permit

to construct a 52' fixed pier with additional pilings. This

application was also granted.

One year after the second permit was issued,

Applicant sought to expand the exiting 52' pier an additional

110’, to add 2 boat lifts with 80,000 Ib. and 16,000 lb.

capabilities and to add 4 mooring pilings clusters. Staff

denied this application. A hearing was requested by the

Applicant after the denial. The parties entered into settlement

discussions and ultimately resolved the matter. A Stipulation

of Settlement was entered into by the parties on May 30,

1995 wherein the Applicant agreed to modify the application

and reduce the extension of the boat dock from 110’ to 40’

and to reduce the boat lift request from two boat lifts to one

boat lift. Based upon these changes, Staff withdrew its

objections to the issuance of the permit and a permit was

issued in June, 1995.

-53a-

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)]

In May, 1999 the Applicant applied for a permit to

construct an additional 50' extension of the dock and to add

an 80,000 Ib. boat lift. This is basically what was requested

by the Applicant in his 1995 application, when combined

with what was permitted in June, 1995.

The May, 1999 application was denied by Staff by

letter dated July 7, 2000. The Notice of Permit Denial states,

in part: "You failed to allow Department Staff to inspect

your property to observe the conditions at the site in order to

determine whether or not your proposal complies with the

standards for permit issuance. Therefore, this application for

permit is hereby denied." It is undisputed that Applicant has

refused Staff access to his property to inspect it as part of the

permitting process. Applicant contends that Staff can

conduct whatever inspection is necessary from the water,

without entering his property.

An adjudicatory hearing was scheduled for March 27,

2001 in Babylon, New York. The hearing was adjourned due

to the unavailability of Staffs witness. The parties finally

settled on June 25, 2001 as the rescheduled date for the

hearing. The ALJ served on both parties by facsimile, a letter

dated May 10, 2001 and a Notice of Public Hearing

confirming the June 25, 2001 hearing date. The ALJ and

Staff appeared at the hearing site on June 25, 2001. Neither

the Applicant nor his counsel appeared. Counsel for the

Applicant later indicated that he did not believe that a firm

date hed been set for the hearing.

-54a-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)]

STAFF’S POSITION

Staff seeks a denial of the application based on

Applicant's failure to appear for the hearing and due to the

incompleteness of the application. Staff advised Applicant

that an inspection of his property, ftom his property rather

than by boat, is essential for the review of the application.

Absent the inspection, the permit can not be granted.

APPLICANT’S POSITION

Applicant's counsel's affidavit in opposition to the

motion only addresses Staff's request to deny the application

based on Applicant’s failure to attend the hearing. However,

he has addressed the issue of the site inspection in earlier

correspondence with the Department. Applicant has denied

the DEC all access to his property. He insists that Staff

conduct its inspection from the least intrusive manner

available that being from the waterway."'

FINDINGS OF FACT

After a review of the pleadings and papers submitted

herein by the parties, 1 find that the following facts are not in

dispute:

1. By letter dated April 27, 2000, counsel for the Applicant

advised DEC that his client would not consent to an

inspection from the property and suggested an inspection

from the water

-5Sa-

to

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)|

By application dated May 25, 1999 Applicant

Paul Palmieri applied for a tidal wetlands

permit to construct a 50' extension to an

existing pier and to add one boat liit.

Staff attempted to inspect Applicant's property

in April, 2000 as part of the application

review process. Access was denied by the

Applicant.

By letter dated July 7, 2000 DEC Permit

Administrator Mark Carrara advised

Applicant's counsel that due to Applicant's

failure to allow an inspection from the

property, the permit application was being

denied.

A Notice of Permit Denial was issued to the

Applicant by the DEC on July 7, 2000. The

Notice stated, in part, "You failed to allow

Department staff to inspect the property to

observe the conditions at the site in order to

determine whether or not your proposal

complies with the standards for permit

issuance. Therefore, this application for

permit is hereby denied."

Applicant requested an adjudicatory hearing

on the denial of the application.

-56a-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)]|

6. The hearing was scheduled for June 25, 2001

in Babylon, New York. Applicant failed to

appear for the hearing.

DISCUSSION

6 NYCRR 624.6(c) allows for the bringing of a

motion at any time. Motions made prior to the hearing shall

be filed with the ALJ and served on all parties. The ALJ

shall then rule upon the motion prior to the completion of

testimony. 6 NYCRR 624.8(b)(i) grants the authority to an

ALJ to rule upon all motions and requests, including those

that decide the ultimate merits of the case.

DISMISSAL DUE TO

APPLICANT'S FALLURE TO APPEAR

Staff requests that the Applicant be denied an

adjudicatory hearing due to his failure to appear for the

hearing scheduled for June 25, 2001. Applicant claims to

have not been aware that the hearing was rescheduled. To

deny the hearing based upon the Applicant's failure to appear

for the hearing is a drastic remedy. While the Notice for the

hearing was sent by facsimile by the Office of Hearings to

the Applicant's counsel on May 10, 2001, there is no

confirmation that counsel saw that letter and Notice.

Frankly, scheduling errors occur and such a severe penalty as

requested by Staff is not warranted here. Also, Staff has

submitted no law in support of the request.

-57a-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)

RIGHT TO INSPECT

The application is for a tidal wetlands permit. Tidal

wetlands in New York State are regulated by Part 661 of 6

NYCRR. It is the public policy of the State to protect and

preserve tidal wetlands and to prevent their despoliation and

destruction. Part 661.2(a) states: “Tidal wetlands constitute

one of the most vital and productive areas of the natural

world and collectively have many values .. . Therefore, the

protection and preservation of tidal wetlands is essential."

There are five standards that govern whether the Department

will issue a tidal wetlands permit. Those standards are

defined at 6 NYCRR 661.9(b)(i)-(v).

The Applicant has the burden of establishing that the

applicable standards will be met. 6 NYCRR 661 .9(a)

In the instant case, the Applicant failed to allow Staff

onto his property. Staff notified Applicant in writing that it

was a necessary part of the permit process to have access to

the property to conduct the inspection. Despite being

notified of the Department's need to inspect, the Applicant

continued to deny access. As stated, the Applicant has not

addressed the issue of an inspection from the property in his

opposing papers. However, in April, 2000 Applicant's

attorney sent a letter to DEC indicating that his client would

not consent to the inspection from his property. Counsel

cited 3 cases in support of his position that the inspection

from the property was tantamount to an illegal and

warrantless search. After reviewing the cases cited, I

-58a-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)|

disagree. The circumstances of those cases, which | will

address below, were significantly different than here and,

therefore, the rulings are not controlling here.

The leading case cited by the Applicant is Sokolov v.

Village of Freeport, 52 N.Y.2d 341. \n Sokolov, the Court of

Appeals held that a Village ordinance that required an

inspection of residential rental property in order for the

owner to rent out the property was a warrantless search and

therefore unconstitutional. The Village had enacted an

ordinance requiring all owners of rental property to have a

permit issued before renting the property. The permit would

only be issued after the Village inspected the property. The

Court held “We hold today that the imposition of a penalty

upon a landlord for renting his premises without first

consenting to a warrentless search violates the property

owner's Fourth Amendment rights." (Sokolov at 343) The

Court noted that if the property owner does not consent. he

will he deprived of the economic benefit of his property.

Here, the Applicant is seeking a privilege. He is asking to be

allowed to construct a pier extension and add a boat lift into

the Great South Bay. The issue is, does the construction

harm the delicate nature of the tidal wetlands. The DEC is

entrusted with the important task of preserving and

protecting tidal wetlands. That job requires the Department

to carefully review each application for a tidal wetlands

permit to ensure that it meets the standards enumerated in

part 661. As stated by Charles Hamilton, DEC Region One

supervisor of Natural Resources, the Department can not

-59a-

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)}

complete their job without inspecting the property. The

suggestion of the Applicant that the inspection take place

from the water is not viable. Staff has refuted that in the

Hamilton affidavit. First it would be wrong to have the

Applicant dictate to Staff how they should do their job. But,

more importantly, it is crucial for Staff to have complete

access to the wetlands and no other type of inspection will

suffice. Staff has been entrusted with the responsibility of

ensuring that the existing and potential values of tidal

wetlands for marine food production and wildlife habitat and

other values associated with tidal wetlands are protected.

The Hamilton affidavit addresses why an inspection

from the Applicant's property is a necessary part of this

application process. Hamilton asserts that Staff must

conduct an extensive site review to assess a specific project

and it's specific wetland environment. (Hamilton, p.2) By

denying Staff access, Staff is denied the opportunity to

conduct a meaningful technical review of the project site as

required by the regulations. (Hamilton, p.2),"... , staff

must access the condition of the wetlands in the area of the

existing structure as well as the area where the proposed

extension would be located. Staff needs to determine

whether the existing structure is causing impacts which may

be compounded by increasing the size of the structure."

(Hamilton, p. 5) Applicant does not address any of these

issues in it's opposing papers. While Applicant's counsel

submitted case law that he alleges supports his client's

position that an inspection is a warrantless search, he has

offered no response to Staffs specific arguments on why they

-60a-

Appendix H

[Ruling on Motion and Summary

Report of Molly McBride (ALJ)|

need to enter the property in this case. Applicant has never

stated how Staff can determine if the application meets the

standards for permit issuance without actually inspecting the

property.

I find staff's arguments persuasive and agree that in

order to meet the duties imposed by Part 661, an inspection

of the site is necessary.

The Applicant's attorney also cited 7own of

Brookhaven v. Ronkoma Realty Corp., 154 A.D. 2d 665,

Second Dept:, 1989. This case also involved an ordinance

requiring rental property to be inspected and a permit issued

prior to rental. For the same reasons cited in Sokolov, the

Court found that the ordinance was unconstitutional. Finally,

Applicant cited People v. Ost, 121 A. D. 2d 571, Second

Dept., 1986. In Ost, the police had entered the defendant's

business, without a warrant, examined his books, without

permission, and used the information gathered to charge the

defendant criminally. The Court found the warrantless

inspection a violation of the defendant's constitutional rights

and the charges were dismissed. For obvious reasons the

facts in Ost can not be equated with the facts here.

One of the differences between a tidal wetlands

permit and a permit to operate rental property is that the tidal

wetlands permit is asking for a privilege, not a right. There

is no right to a tidal wetlands permit. The Applicant here

will not lose his property in any way or suffer economic

harm if the permit is not granted. There is no monetary or

-6la-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)|

criminal penalty for him if he fails to allow the inspection.

The only consequence is that the application must be denied.

The Applicant is still free to enjoy his property as he did

before filing the application. He has previously been granted

permits to construct the pier, reconstruct the bulkhead and

install a boat lift. The pier has already been extended from

it's initial $2' to 92'. The Applicant is free to chose [sic. }

which route to take. He has elected to refuse Staff access to

his property. Surprisingly, the permits previously issued to

the Applicant all provide the DEC with the right to enter the

property to ensure that the permit conditions are being

complied with. All permits issued by the DEC grant the

Department that right. Applicant has already consented, by

accepting the permits, to Staff entering his property. It is

illogical for Applicant to deny access to Staff as a part of this

application. However, that is his right.

Staff can not determine if the application meets the

standards for permit issuance without inspecting the

property. Therefore, the application is incomplete. Staff has

no discretion with regards to applying the standards. If it can

not be determined that the standards are met, the application

simply can not be deemed complete.

DENIAL DUE TO INCOMPLETENESS

Staff argues in it's motion that the application is in

fact incomplete due to the lack of an inspection. Staff

notified Applicant in writing on April 1, 2000 that it was a

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)]

necessary part of the permit process to have access to the

property to conduct the inspection. At that time, Mark

Carrara, Deputy Permit Administrator for the DEC stated to

the Applicant that the permit application would be denied if

Staff was not allowed to inspect the property. Despite being

notified of the Department’s need to inspect, the Applicant

continued to deny access.

Clearly, the application can not be reviewed by Staff

without the inspection and therefore, the application is in

essence incomplete. Staff cites the Interim Decision in Bath

Petroleum Storage, Inc, November 6, 2000 in support of it's

argument that the completeness of the application is an issue

that is not subject to review.

The Interim Decision, issued by Deputy

Commissioner Cari Johnson held that there is a bar against

adjudicating the completeness of a permit application in 6

NYCRR section 624.4(c)(7).

A review of relevant administrative decisions reveal

the basis for the bar. The purpose of the prohibition

where an application is deemed complete is to give an

Applicant comfort and certainty that its application

cannot be undone at the hearing stage, i.e., assertions

by intervening parties to adjourn the hearing on

incompleteness grounds. See, Matter of Applications

of Department of Sanitation Southwest Brooklyn

Incinerator, Interim Decision, March 2, 1994. ".

the completeness determination . . . is intended to

-63a-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)}

reflect the point at which the application contains

sufficient information to commence regulatory

review." Matter of LaFever Excavating, Inc., Interim

Decision, October 28, 1991. ".. . once the

completeness determination is made, there is no

turning back." Matter of Applications of NYC

Department of Environmental Protection, Preliminary

Ruling of ALJ, Match 24, 1994; See also, Matter of

Applications of Fulton County Board of Supervisors,

Decision of Commissioner, February 13, 1987. Bath

at p.7

I agree with Staff that the application is in fact

incomplete when Staff can not access the property. The

Applicant bears the burden of showing that the application

meets the standards enumerated in Part 661. That burden is

met with written submissions AND an inspection of the

site. The application information submitted must be field

verified. Qualified, trained biologists visit the site to assess

the area. A tidal wetlands permit can be issued only if the

proposed activity meets the standards for permit issuance in

6 NYCRR 661.9(b)(i)-(v). Nothing in Part 661 gives Staff

the discretion to work outside of these standards. Obviously,

Staff can not assess whether the standards are met without

sending trained professionals to the site to do their job. If

Staff can not determine if the standards arc met, Staff can not

conduct a complete the [sic.] review of the application.

Appendix Ht

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)|

Based upon the Interim Decision in Bath, | have no

authority to review Staffs determination that the application

is incomplete.

CONCLUSION

Staff has requested that the denial of the application

based upon incompleteness be affirmed or in the alternative,

the application be dismissed due to the Applicant's failure to

attend the hearing. Staff has cited no legal authority to deny

the application solely due to Applicant's failure to appear at

the hearing. Further, the penalty is too harsh to deny the

application when Applicant's attorney claims to not have

been aware of the hearing being scheduled. Also, the permit

denial issued by the Department was not the proper vehicle

in this circumstance. Staff acknowledges that the application

is incomplete. Staffs remedy to that particular circumstance

is to issue an [sic.] Notice of Incomplete Application rather

than a denial of the application based upon incompleteness.

RECOMMENDATION

Based upon the record before me and the Findings of

Fact herein, I recommend that the Notice of Denial be

vacated and that Staff's determination that the application ts

incomplete as stated in correspondence to the Applicant and

the motions papers herein, be deemed a Notice of Incomplete

Application. Further, the Request for Hearing filed by the

Applicant is void since such a request can not be made in

response to a Notice of Incomplete Application. The

-65a-

Appendix H

{Ruling on Motion and Summary

Report of Molly McBride (ALJ)|

application can not be processed further until such time as it

is complete. This Ruling can be referred to the

Commissioner for final determination.

-66a-

Appendix I - Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations

[67a - 103a|

The constitutional provision involved is the Fourth

Amendment to the U.S. Constitution which provides:

“The right of the people to be secure in their persons,

houses, papers, and effects, against unreasonable

searches and seizures, shall not be violated, and no

warrants shall issue, but upon probable cause,

supported by oath or affirmation, and particularly

describing the place to be searched, and the persons

or things to be seized.”

The Statutes involved are:

ECL § 15-0505 entitled “Protection of navigable

waters; excavation or fill; permit” provides:

1. No person, local public corporation or interstate

authority shall excavate or place fill below the mean

high water level in any of the navigable waters of the

state, or in marshes, estuaries, tidal marshes and

wetlands that are adjacent to and contiguous at any

point to any of the navigable waters of the state and

that are inundated at mean high water level or tide,

without a permit issued pursuant to subdivision 3 of

this section. For the purposes of this section, fill shall

include, but shall not be limited to, earth, clay, silt,

sand, gravel, stone, rock, shale, concrete (whole or

fragmentary), ashes, cinders, slag, metal, or any other

similar material whether or not enclosed or contained

by (1) crib work of wood, timber, logs, concrete or

-67a-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations|

metal, (2) bulkheads and cofferdams of timber

sheeting, bracing and piling or steel sheet piling or

steel H piling, separated or in combination. Nothing

contained in this section is intended to be, nor shall

be construed to limit, impair or affect the

memorandum of understanding which any state

department enters into with the Department of

Environmental Conservation or the general powers

and duties of the Department of Transportation

relating to canals or the general powers and duties of

the Department of Environmental Conservation

relating to flood control.

6 NYCRR §621.1 entitled “Definitions” provided:

(a) Adjudicatory public hearing means a trial type

proceeding which provides the opportunity for

adjudication on the basis of evidence, including direct

testimony and cross examination provided under

article 3 of the State Administrative Procedure Act,

section 70-0109 of the Environmental Conservation

Law (ECL), section 621.6 of this Part and Part 624 of

this Title.

(b) Chief permit administrator means an employee

of the department located in the main office of the

department and designated to act on the

commissioner's behalf in carrying out this Part.

-68a-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

(c) Commissioner means the Commissioner of

Environmental Conservation, or any employee of the

department designated to act on the commissioner's

behalf in carrying out this Part.

(d) Complete application means an application for a

permit which is in an approved form and is

determined by the department to be complete for the

purpose of commencing review of the application but

which may need to be supplemented during the

course of review in order to enable the department to

make the findings and determinations required by

law.

(e) Delegated permit means a permit issued by the

department for which a comparable permit may be

required by Federal law. Delegated permits are issued

by the department for the following programs:

(1) Resource Conservation and Recovery Act

(RCRA) of 1976, 42 USC 6901 et seq., 1984 (see

section 621.16 of this Part) (ECL article 27, title 9)

for any hazardous waste management facilities

(HWMEF) or remedial action plans (RAP) under ECL

article 27, title 9 except those limited to the disposal

of waste containing polychlorinated biphenyl (PCB)

only.

-69a-

Appendix I

|Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

(2) Clean Water Act (CWA) amendments, 33 USC

1251 et seq., 1987 (see section 621.16 of this Part)

(ECL article 17, titles 7 and 8) for any State pollutant

discharge elimination systems (SPDES) permit

involving an industrial or municipal discharge under

ECL article 17, titles 7 and 8.

(3) Clean Air Act (CAA) amendments, 42 USC 7401

et seq., 1990 for any air pollution control source

under ECL article 19 subject to the following Federal

requirements:

(i) prevention of significant deterioration (PSD);

(ii) new source review in nonattainment areas; or

(iii) title V facility permits.

(f) Department means the New York State

Department of Environmental Conservation, or a

local agency to which the department has delegated

permitting or review authority.

(g) Emergency means an event which presents an

immediate threat to life, health, property, or natural

resources.

(h) ENB (Environmental Notice Bulletin) means the

publication of the department published pursuant to

section 3-0306 of the ECL, accessible on the

-70a-

Appendix I

|Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

department's Internet web site at

http://www.dec. state.ny.us.

(1) PA means the United States Environmental

Protection Agency.

(j) Legislative public hearing means a proceeding

which provides an opportunity for public comment

provided by section 621.7 of this Part.

(k) Local government means a village, town, city or

county.

(1) Major project means any action requiring a

permit identified in section 621.2 of this Part, which

is not specifically defined as minor.

(m) Minor project means any action listed as minor

in section 621.4 of this Part, subject to the

reservations of section 621.3(c)(3) of this Part. All —

actions identified as Type II in Parts 617 and 618 of

this Title are minor. Minor projects are projects

which by their nature and with respect to their

location are not likely to have a significant effect on

the environment.

(n}-Modification means any change or amendment

whatsoever to a permit that is currently in force,

including transfer form one person to another.

-7la-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

(o) Permit means any permit, certificate, license or

other form of department approval, suspension,

modification, revocation, renewal, reissuance or

recertification, including any permit condition and

variance, that is issued in connection with any

regulatory program listed in section 621.2 of this Part.

(p) Person means any corporation, firm, partnership,

association, trust, estate, one or more individuals, any

other legal entity or any unit of Federal, State or local

government or any agency or subdivision thereof,

including any State department, bureau, commission,

board or other agency, public authority or public

benefit corporation.

(q) Project means any action requiring one or more

permits identified in section 621.2 of this Part.

(r) Regional permit administrator means an

employee of the department located in each of the

nine regional offices of the department and

designated to act on the commissioner's behalf in

carrying out this Part.

(s) Regulatory agency means the department, another

state agency, or a local government having any form

of jurisdiction over a project.

(t) Renewal means the reissuance, recertification or

extension of any permit for previously approved

-72a-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

activities which will be continuing on the same site

without material change.

(u) SOR means the State Environmental Quality

Review Act, article 8 of the Environmental

Conservation Law and Parts 617 and 618 of this

Title.

(v) Tentative determination means a notice of intent

to issue or deny a permit.

(w) 7itle V facility permit means a permit, which is

issued by the department pursuant to Subpart 201-6

of this Title, for a facility or a defined area source,

group, or category of emission units at a facility.

(x) Variance means relief from the provisions of

specific permit program implementing regulations as

provided herein.

6 NYCRR §621.7 entitled “Determination to conduct

a public hearing” provided:

(a) After a permit application for a major project is

complete (see provisions of sections 621.3 through

621.5 of this Part), and notice in accordance with

section 621.6 of this Part has been provided, the

department shall evaluate the application and any

comments received on it to determine whether a

public hearing will be held. If a public hearing must

be held, the applicant and all persons who have filed

-73a-

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

comments shall be notified by mail. This shall be

done within 60 calendar days of the date the

application is complete. A public hearing may be

either adjudicatory or legislative.

(b) The determination to hold an adjudicatory public

hearing shall be based on whether the department's

review raises substantive and significant issues

relating to any findings or determinations the

department is required to make pursuant to the

Environmental Conservation Law, including the

reasonable likelihood that a permit applied for will be

denied or can be granted only with major

modifications to the project because the project, as

proposed, may not meet statutory or regulatory

criteria or standards. In addition, where any

comments received from members of the public or

other interested parties raise substantive and

significant issues relating to the application, and

resolution of any such issue may result in denial of

the permit application, or the imposition of

significant conditions thereon, the department shall

hold an adjudicatory public hearing on the

application.

(c) Regardless of whether the department holds +i:

adjudicatory public hearing, a determination to hold a

legislative public hearing shall be based on the

following:

-Tha-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

(1) if a significant degree of public interest exists;

(2) to fulfill the requirements of section 617.8 of this

Title; or

(3) for HWMEF permits or RAPs, if notification of

opposition to a draft permit or RAP, and a request for

a hearing is received during the public comment

period.

(d) Mere expressions of general opposition to a

project are insufficient grounds for holding an

adjudicatory public hearing on a permit application.

In order to raise substantive and significant issues,

written comments expressing objection or opposition

to an application must explain the basis of that

opposition and identify the specific grounds which

could lead the department to deny or impose

significant conditions on the permit.

(e) The department normally does not require public

hearings in connection with applications for minor

projects, as identified in sections 621.3 and 621.4 of

this Part. If a public hearing is required for a minor

project, the application shall be treated as a major

project for purposes of this Part.

(f) Ifa permit for a project is denied, or is issued

with significant conditions attached and an

adjudicatory public hearing was not held, then the

-75Sa-

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

applicant may request that one be held. Such a

request must be made within 30 calendar days of the

date of the mailing of either the notice of denial or the

permit with conditions. The hearing shall commence

within 45 calendar days of the date of receipt of the

request.

(g) Ifa public hearing on an application is required

to be held, it shall commence on or before 90

calendar days after the date the application is

complete.

(h) The public adjudicatory hearing will be held

according to the provisions of Part 624 of this Title.

6 NYCRR § 621.15 entitled “Special provisions”

provided:

(a) Any time period specified in this Part rhay be

extended for good cause, by mutual written consent

of the applicant and the department. The EPA must

be notified in those cases where a proposed extension

will exceed the time periods established in Federal

regulation. This provision does not supersede the

requirement that the public can request judicial

review in State court if a title V permit is not issued

within 18 months of the date that an application is

complete.

-76a-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

(b) At any time during the review of an application

for a new permit, modification, or renewal, the

department may request in writing any additional

information which is reasonably necessary to make

any findings or determinations required by law. Such

a request shall be explicit, and shall indicate the

reasonable date by which the department is to receive

the information. Failure to provide such information

by the date specified in the request may be grounds

for denial of the application.

(c) The department may issue general permits to

allow work to eliminate damage caused by natural

disasters or extraordinary weather not unique to a

particular locality, including repair or replacement in

location and in kind of facilities which existed prior

to the damage. Processing of such permits need not

follow the full procedural requirements of this Part.

(d) General permits may also be issued by the

department for projects that are determined not to

have a significant impact on the environment, and

that have been subjected to the full procedural

requirements of this Part for major projects. General

permits under the SPDES program and the air

pollution control program in accordance with Part

201 of this Title may be issued for regulated activities

for which the department determines that all the

requirements of this subdivision have been met.

-77a-

Appendix ]

[Cows * -utional Provisions, Treaties,

Statutes, Ordinances and Regulations}

(e) The department may require as a condition to a

permit, and prior to commencement of work, that the

permittee post a bond or other financial assurance

acceptable to the department of specified amount

with the department. This is to ensure faithful

compliance with the terms of the permit, and is used

for the indemnification of the State for any costs

which might result from failure to so comply. The

bond or other financial assurance shall remain in

effect until the work is completed to the satisfaction

of the department.

(f) Where this Part requires exchange of written

materials within specified time periods, postmark

dates shall satisfy the requirements, when not

otherwise specifically provided.

(g) The department may issue a research,

development, and demonstration permit for any

hazardous waste treatment facility which proposes to

utilize an innovative and experimental hazardous

waste treatment technology or process for which

permit standards have not been promulgated under

section 373-1.9 of this Title. This permit must

include terms and conditions to assure protection of

human health and the environment.

(1) Variances from permit application and issuance

requirements of this Part may be granted by the

-78a-

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

department, except there may be no variance from

any provisions requiring public participation.

(2) Such permits may be issued for a period not to

exceed one year and may not be renewed more than

three times, with each renewal period not to exceed

one year. Experimental permits may be revoked when

it is determined by the department to be necessary to

protect human health and the environment.

(3) These permit applications are subject to all other

procedural requirements of this Part.

28 U.S.C. Section 1257(a) entitled “State courts,

certiorari provides:

(a) Final judgments or decrees rendered by the

highest court of a State in which a decision could be

had, may be reviewed by the Supreme Court by writ

of certiorari where the validity of a treaty or statute of

the United States is drawn in question or where the

validity of a statute of any State is drawn in question

on the ground of its being repugnant to the

Constitution, treaties, or laws of the United States, or

.where any title, right, privilege, or immunity is

specially set up or claimed under the Constitution or

the treaties or statutes of, or any commission held or

authority exercised under, the United States.

-79a-

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

CPLR Section 306-b entitled “Service of the

summons and complaint, summons with notice, third-party

summons and complaint, or petition with notice of petition

or order to show cause” provides:

Service of the summons and complaint, summons

with notice, third-party summons and complaint, or

petition with a notice of petition or order to show

cause shall be made within one hundred twenty days

after the filing of the summons and complaint,

summons with notice, third-party summons and

complaint, or petition, provided that in an action or

proceeding, except a proceeding commenced under

the election law, where the applicable statute of

limitations is four months or less, service shall be

made not later than fifteen days after the date on

which the applicable statute of limitations expires. If

service is not made upon a defendant within the time

provided in this section, the court, upon motion, shall

dismiss the action without prejudice as to that

defendant, or upon good cause shown or in the

interest of justice, extend the time for service.

CPLR Section 307 entitled “Personal service upon

the state

1. Personal service upon the state shall be made by

delivering the summons to an assistant attorney-

general at an office of the attorney-general or to the

attorney-general within the state.

-80a-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

2. Personal service on a state officer sued solely in an

official capacity or state agency, which shall be

required to obtain personal jurisdiction over such an

officer or agency, shall be made by (1) delivering the

summons to such officer or to the chief executive

officer of such agency or to a person designated by

such chief executive officer to receive service, or (2)

by mailing the summons by certified mail, return

receipt requested, to such officer or to the chief

executive officer of such agency, and by personal

service upon the state in the manner provided by

subdivision one of this section. Service by certified

mail shall not be complete until the summons is

received in a principal office of the agency and until

personal service upon the state in the manner

provided by subdivision one of this section is

completed. For purposes of this subdivision, the term

"principal office of the agency" shall mean the

location at which the office of the chief executive

officer of the agency is generally located. Service by

certified mail shall not be effective unless the front of

the envelope bears the legend "URGENT LEGAL

MAIL" in capital letters. The chief executive officer

of every such agency shall designate at least one

person, in addition to himself or herself, to accept

personal service on behalf of the agency. For

purposes of this subdivision the term state agency

shall be deemed to refer to any agency, board, bureau,

commission, division, tribunal or other entity which

-8la-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

constitutes the state for purposes of service under

subdivision one of this section.

CPLR Rule 2103 entitled “Service of papers”

provides:

(a) Who can serve. Except where otherwise

prescribed by law or order of court, papers may be

served by any person not a party of the age of

eighteen years or over.

(b) Upon an attorney. Except where otherwise

prescribed by law or order of court, papers to be

served upon a party in a pending action shall be

served upon the party's attorney. Where the same

attorney appears for two or more parties, only one

copy need be served upon the attorney. Such service

upon an attorney shall be made:

1. by delivering the paper to the attorney personally;

or

2. by mailing the paper to the attorney at the address

designated by that attorney for that purpose or, if

none is designated, at the attorney's last known

address; service by mail shall be complete upon

mailing; where a period of time prescribed by law is

measured from the service of a paper and service is

by mail, five days shall be added to the prescribed

period; or

-82a-

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

3. If the attorney's office is open, by leaving the

paper with a person in charge, or if no person is in

charge, by leaving it in a conspicuous place; or if the

attorney's office is not open, by depositing the paper,

enclosed in a sealed wrapper directed to the attorney,

in the attorney's office letter drop or box; or

4. by leaving it at the attorney's residence within the

state with a person of suitable age and discretion.

Service upon an attorney shall not be made at the

attorney's residence unless service at the attorney's

office cannot be made; or

5. by transmitting the paper to the attorney by

facsimile transmission, provided that a facsimile

telephone number is designated by the attorney for

that purpose. Service by facsimile transmission shall

be complete upon the receipt by the sender of a signal

from the equipment of the attorney served indicating

that the transmission was received, and the mailing of

a copy of the paper to that attorney. The designation

of a facsimile telephone number in the address block

subscribed on a paper served or filed in the course of

an action or proceeding shall constitute consent to

service by facsimile transmission in accordance with

this subdivision. An attorney may change or rescind a

facsimile telephone number by serving a notice on the

other parties; or

-83a-

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

6. by dispatching the paper to the attorney by

overnight delivery service at the address designated

by the attorney for that purpose or, if none is

designated, at the attorney s last known address.

Service by overnight delivery service shall be

complete upon deposit of the paper enclosed in a

properly addressed wrapper into the custody of the

overnight delivery service for overnight delivery,

prior to the latest time designated by the overnight

delivery service for overnight delivery. Where a

period of time prescribed by law is measured from

the service of a paper and service is by overnight

delivery, one business day shall be added to the

prescribed period. “Overnight delivery service"

means any delivery service which regularly accepts

items for overnight delivery to any address in the

state; or

7. [Expires and repealed Sept 1, 2009] by

transmitting the paper to the attorney by electronic

means where and in the manner authorized by the

chief administrator of the courts by rule upon the

party's written consent. The subject matter heading

for each paper sent by electronic means must indicate

that the matter being transmitted electronically is

related to a court proceeding.

(c) Upon a party. If a party has not appeared by an

attorney or the party's attorney cannot be served,

service shall be upon the party by a method specified

-84a-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

in paragraph one, two, four, five or six of subdivision

(b) of this rule.

(d) Filing. If a paper cannot be served by any of the

methods specified in subdivisions (b) and (c), service

may be made by filing the paper as if it were a paper

required to be filed.

(e) Parties to be served. Each paper served on any

party shall be served on every other party who has

appeared, except as otherwise may be provided by

court order or as provided in section 3012 or in

subdivision (f) of section 3215. Upon demand by a

party, the plaintiff shall supply that party with a list of

those who have appeared and the names and

addresses of their attorneys.

(f) Definitions. For the purposes of this rule:

1. "Mailing" means the deposit of a paper enclosed in

a first class postpaid wrapper, addressed to the

address designated by a person for that purpose or, if

none is designated, at that person's last known

address, in a post office or official depository under

the exclusive care and custody of the United States

Postal Service within the state;

2. "Electronic means" means any method of

transmission of information between computers or

other machines designed for the purpose of sending

-85a-

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations}

and receiving such transmissions, and which allows

the recipient to reproduce the information transmitted

in a tangible medium of expression,

3. "Facsimile transmission" means any method of

transmission of documents to a facsimile machine at

a remote location which can automatically produce a

tangible copy of such documents.

CPLR Rule 3025(a) entitled “Amended and

supplemental pleadings” provides:

(a) Amendments without leave. A party may amend

his pleading once without leave of court within

twenty days after its service, or at an time before the

period of responding to it expires, or within twenty

days after service of a pleading responding to it.

ECL Section 15-0501 entitled “Protection of certain

streams; disturbances of stream beds; permit” provides:

1. Except as provided in subdivisions 4, 5, 6 and 7 of

this section, no person or public corporation shall

change, modify or disturb the course, channel or bed

of any stream as defined in subdivision 2, or remove

any sand, gravel or other material from the bed or

banks of such a stream without a permit issued

pursuant to subdivision 3 of this section.

-86a-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations}

2. For the purposes of this section, stream shall mean

that portion of any fresh surface watercourse, except

lakes or ponds having a surface area greater than ten

acres at mean low water level, for which the

department has adopted or may hereafter adopt

pursuant to section 17-0301, any of the following

classifications or standards:

AA and AA (T),

A and A(T),

B and B (7),

C(T)

Small ponds or lakes with a surface area at mean low

water level of ten acres or less, located in the course

of a stream, shall be considered a part of the stream

and subject to regulation under this section.

3. Permit.

a. Before granting a permit, a permit renewal or a

permit modification pursuant to this section, the

department shall ascertain the probable effect on the

health, safety and welfare of the people of the state,

and the effect on the natural resources of the state,

including soil, forests, water, fish and aquatic

-87a-

Appendix I

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

resources therein, likely to result from the proposed

project or work.

b. In order to minimize the disturbance of a stream

and in order to prevent unreasonable erosion of soil,

increased turbidity of the waters, irregular variations

in velocity, temperature and level of waters, the loss

of fish and aquatic wildlife and the destruction of

natural habitat thereof, and the danger of flood or

pollution, the department shall review the permit

application or request for renewal or modification of

an existing permit and may approve the manner and

the extent to which the stream bed or channel may be

changed, altered or modified and may limit the

quantity of sand, gravel or other material to be

removed, designate the location in the bed, channel or

banks of the stream from which the sand, gravel or

other material may be removed, or it may deny the

permit or request.

c. The rules and regulations adopted by the

department to implement this section and the

provisions of article 70 of this chapter and rules and

regulations adopted thereunder shall govern the

processing of permit applications, renewals,

modifications, suspensions and revocations under this

section.

4. No permit under this section shall be required of

any local public corporation which has entered into a

-88a-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

written memorandum of understanding with the

department establishing the plan of operation to be

followed in carrying out projects or work affecting

water courses so as to afford proper protection to the

public beneficial uses of such water courses.

5. No permit under this section shall be required of

any state department or state public corporation. State

departments and state public corporations may enter

into a written memorandum of understanding with

the department concerning projects or work of the

type for which a permit would be required under this

section if the project or work were undertaken by a

person or local public corporation. The memorandum

may establish procedures for review by the

department of the plans for such projects or work and

for written recommendations by the department with

respect thereto.

6. No permit under this section shall be required for

emergency work in a stream or on its banks which is

immediately necessary to protect the health, safety

and well-being of any person or persons or to prevent

damage to personal or real property, provided that the

department is given written notification by registered

mail or telegraph within forty-eight hours after the

commencement of the work and within forty-eight

hours following the completion of such work.

Whenever emergency work is performed as provided

in this subdivision, it shall be performed in a manner

-89a-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

that will cause the least change, modification,

disturbance or damage to the course or bed of the

stream and its banks.

7. No permit under this section shall be required for

certain agricultural activities of persons and

corporations actively cultivating land devoted to

agriculture whether or not the same be along a stream

or watercourse as described in subdivision 2;

providing that these agricultural activities consist

only of crossing and recrossing of such streams or

watercourses by livestock or by wheeled farm

equipment normally used for traditional agricultural

purposes; or the use of such stream or watercourse for

withdrawal of water for irrigation where such

withdrawal does not require altering the bed, banks or

course of the stream in any manner.

8. The requirements of this section shall be in

addition to those specified in section 15-0505 of this

title, provided however, that the department may, by

rule and regulation, provide that only one application

for a permit or request for renewal or modification of

an existing permit need be filed with the proposed

project or work requires a department permit under

this section and section 15-0505 of this title.

ECL § 15-0503 entitled “Protection of water bodies;

permit” provides:

-90a-

Appendix I

jConstitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

1. Except as provided in subdivision [fig 1] 3 of this

section

a. No dam [fig 1] shall be erected, constructed,

reconstructed or repaired by any person or local

public corporation without a permit issued pursuant

to subdivision [fig 2] 2 of this section. As used in this

section, and section 15-0511 of this title, "dam"

means any artificial barrier including any earthen

barrier, together with its appurtenant works, which

impounds or will impound waters, provided it has (1)

a height equal to or greater than fifteen feet or (2) a

maximum impoundment capacity equal to or greater

than three million gallons; except that for purposes of

this section a dam shall not include any structure

which has (i) a height equal to or less than six feet

regardless of the structure's impoundment capacity, or

(ii) an impoundment capacity not exceeding one

million gallons regardless of the structure's height.

b. Except where a lease or other appropriate

conveyance of an interest authorizing the use and

occupancy of state-owned lands underwater has been

obtained from the commissioner of general services

pursuant to subdivision seven of section seventy-five

of the public lands law, no dock, wharf, platform,

breakwater, mooring, or other structure in, on or

above waters shall be erected, placed, constructed,

reconstructed, or expanded after the effective date of

this paragraph by any person or local public

-9la-

Appendix I

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

corporation without a permit issued pursuant to

subdivision [fig 1] 2 of this section. The term

"reconstructed" as used [fig 2] in relation to docks,

wharves, platforms, breakwaters, mooring or other

structures pursuant to this paragraph shall mean the

substantial rebuilding of structures or facilities and

shall not apply to ordinary maintenance or repair of

existing functional structures or facilities, such as

repainting, redriving pilings or replacing broken

boards in docks.

c. A city, town, village or county may submit to the

commissioner a local law or ordinance regulating

docks or other structures as described in paragraph b

of this subdivision. The commissioner shall review

such law or ordinance to determine whether it

provides environmental protection comparable to, or

greater than, the provisions of such paragraph and any

regulations promulgated thereunder. If the

commissioner determines that the local law or

ordinance submitted meets such requirements, the

commissioner may delegate, upon such terms and

conditions as he or she deems appropriate, to the

local government the authority to administer the

permit program and to charge a fee for permit

processing. Any delegation may be revoked by the

commissioner if he or she finds that the local

government has failed to carry out the program in

accordance with the terms of the delegation.

-92a-

Appendix |

[Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

2. Permits.

a. Before granting a permit, a permit renewal or a

permit modification pursuant to this section, the

department shall ascertain the probable effect on the

health, safety and welfare of the people of the state,

and the effect on the natural resources of the state

likely to result from the proposed project or work.

b. The department shall review the permit

application or request for renewal or modification of

an existing permit and may approve the manner and

extent to which the waters of the state or the banks

and shore thereof will be affected by the proposed

project or work and may grant or deny the permit or

request, or may grant the permit or request with such

conditions as might appear necessary to safeguard

life, property and natural resources during and after

the execution of the proposed project or work.

c. The rules and regulations adopted by the

commissioner to implement this section and the

provisions of article 70 of this chapter and rules and

regulations adopted thereunder shall govern permit

applications, renewals, modifications, suspensions

and revocations under this section.

d. The requirements of this section shall be in

addition to those specified in sections 15-0501 and

15-0505 of this title, provided however, that the

-93a-

Appendix |

{Constitutional Provisions, Treaties,

Statutes, Ordinances and Regulations]

department may, by rule and regulation, provide that

only one application for a permit or request for

renewal or modification of an existing permit need be

filed when the proposed project or work requires a

department permit under this section and any other

section of this title.

3. The requirement of a permit pursuant to this

section shall not apply to the following facilities:

a. A dock, pier, wharf or other structure used solely

as a landing place on water providing dockage for

five or fewer boats and encompassing within its outer

perimeter an area less than four thousand square feet;

b. A mooring facility providing mooring for fewer

than ten boats;

c. Seasonal repl

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Petition for Writ of Certiorari — Palmieri v. New York State Department of Environmental Conservation (No. 06-1134) | Frix