Petition for Writ of Certiorari — Chemtura Canada Canada Co. Co./CIE v. United States (Nos. 06-853, 06-1014, 06-865)

Supreme Court brief2006

Ask Donna

What actually matters in this document.

Text

Suprame Count

ce i

No. 06-

Tex,

riivs Or THE CLERK

IN THE

Supreme Court of the United States

CHEMTURA CANADA CO//CIE

(formerly known as CROMPTON CO./CIE,

formerly known as UNIROYAL CHEMICAL LIMITED),

Petitioner,

V

UNITED STATES OF AMERICA and

HERCULES INCORPORATED,

Respondents.

Own PETITION FOR A WRIT OF CERTIORARI TO THE

UNITED STATES COURT OF APPEALS

FOR THE EIGHTH CIRCUIT

PETITION FOR A WRIT OF CERTIORARI

STEVEN W. QUATTLEBAUM

E. B. Cuices [V*

JosePH R. FALASCO

QUATTLEBAUM. GROOMS,

Tutt & Burrow PLLC

11i Center Street. Suite 1900

Little Rock, Arkansas 72201

(501) 379-1700

* Counsel of Record Attorneys for Petitioner |

YOS 346)

i

QUESTIONS PRESENTED FOR REVIEW

1. Whether the Eighth Circuit erred in holding — contrary

to the Second, Third, Fifth, Seventh, Ninth, Tenth, and

Eleventh Circuits — that an entity that exercised no control

over the disposal or treatment of hazardous substances, and

had neither the authority nor the opportunity to control the

disposal or treatment of hazardous substances, may

nevertheless be held liable as one that “arranged for” the

disposal or treatment of hazardous substances under

§ 107(a) of the Comprehensive Environmental Response,

Compensation, and Liability Act, 42 U.S.C. § 9601 ef seq.

2. Whether retroactive application of § 107(a) of the

Comprehensive Environmental Response, Compensation,

and Liability Act, 42 U.S.C. § 9601 et seq., to impose

unforeseeable joint-and-several liability for over $110 million

based on lawful, non-negligent conduct involving only about

$1.5 million in transactions violates the Fifth Amendment

to the United States Constitution. ;

ii

CORPORATE DISCLOSURE STATEMENT

Chemtura Canada Co./Cie, formerly known as Crompton

Co./Cie, formerly known as Uniroyal Chemical Limited, is

wholly owned by Crompton European Holdings B.V., a Dutch

company, and is indirectly wholly owned by Chemtura

Corporation, whose stock is publicly traded on the New York

Stock Exchange.

ill

TABLE OF CONTENTS

QUESTIONS PRESENTED FOR REVIEW

CORPORATE DISCLOSURE STATEMENT

TABLE OF CONTENTS

TABLE OF CITED AUTHORITIES

TABLE OF APPENDICES

OPINIONS BELOW

JURISDICTION

STATUTORY AND CONSTITUTIONAL

PROVISIONS INVOLVED

STATEMENT OF THE CASE

REASONS FOR GRANTING THE PETITION ...

I. The Eighth Circuit’s Interpretation Of

CERCLA Arranger Liability Conflicts With

The Statutory Language And The Decisions

Of Other Courts of Appeals. .............

Contents

II. The Court of Appeals’ Opinion Imposes

Unforeseeable Joint-And-Several Liability

For Over $110 Million Based On Lawful,

Non-Negligent Conduct In. vlving Only

About $1.5 Million In Transactions In

Violation Of The Fifth Amendment To The

United States Constitution. .............. 15

CONCLUSION

TABLE OF CITED AUTHORITIES

Cases:

Amcast Indus. Corp. v. Detrex Corp., 2 F.3d 746

(7th Cir. 1993), cert. denied, 510 U.S. 1044 (1994)

Coeur D’Alene Tribe v. Asarco Inc., 280 F. Supp.2d

1094 (D. Idaho 2003)

Connolly v. Pension Benefit Guar. Corp., 475 U.S.

211 (1986)

Concrete Sales and Servs., Inc. v. Blue Bird Body

Co., 211 F.3d 1333 (11th Cir. 2000)

Eastern Enterprises v. Apfel, 524 U.S. 498 (1998) ...

Page

6, 16, 17, 18, 19

Franklin County Conv. Facilities v. American

Premier, 240 F.3d 534 (6th Cir. 2001)

Freeman v. Glaxo Wellcome, Inc., 189 F.3d 160

(2d Cir. 1999)

General Elec. Co. v. AAMCO Transmissions, Inc.,

962 F.2d 281 (2d Cir. 1992)

Geraghty and Miller, Inc. v. Conoco Inc., 234 F.3d

917 (Sth Cir. 2001), cert. denied, 533 U.S. 950

(2001)

Cited Authorities

Jones-Hamilton Co. v. Beazer Materials & Servs.,

Inc., 973 F.2d 688 (9th Cir. 1992)

Kaiser Aetna v. United States, 444 U.S. 164 (1979)

Kaiser Aluminum & Chem. Corp. v. Bonjorno,

494 U.S. 827 (1990)

Landgraf v. USI Film Prods., 511 U.S. 244 (1994)

Mathews v. Dow Chem. Co., 947 F. Supp. 1517

(D. Colo. 1996)

Morton Intern., Inc. v. A.E. Staley Mfg. Co., 343 F.3d

669 (3d Cir. 2003)

Pneumo Abex Corp. v. High Point, Thomasville and

Denton R.R. Co., 142 F.3d 769 (4th Cir. 1998) ..

Raytheon Constructors, Inc. v. Asarco, Inc., 368 F.3d

1214 (10th Cir. 2003)

South Florida Water Mgmt. Dist. v. Montalvo,

84 F.3d 402 (11th Cir. 1996)

United States v. Aceto Agric. Chems. Corp., 872 F.2d

Page

ays 2 Lee... Baer rere ere ear tom 82

Vil

Cited Authorities

Page

United States v. Alcan Aluminum Corp., 315 F.3d

179 (2d Cir. 2003)

United States v. Bestfoods, 524 U.S. 51 (1998)

United States v. Cello-Foil Prods., Inc., 100 F.3d

1227 (6th Cir. 1996) 7, & 14% 3

United States v. Gurley, 43 F.3d 1188 (8th Cir.1994)

United States v. Hercules, Inc., 247 F.3d 706

(8th Cir. 2001) 1, 3, 5, 6, 8, 10, 18

United States v. Iron Mountain Mines, Inc.,

881 F.Supp. 1432 (E.D. Cal. 1995) 12

United States v. Shell Oil Co., 294 F.3d 1045

(9th Cir. 2002)

United States v. TIC Inv. Corp., 68 F.3d 1082

(8th Cir. 1995)

United States v. Vertac Chem. Corp., 453 F.3d 1031

(8th Cir. 2006) Los Se oe ee Be

United States v. Vertac Chem. Corp., 46 F.3d 803

(8th Cir. 1995)

United States v. Vertac Chem. Corp., 364 F. Supp.2d

941 (E.D. Ark. 2005)

vill

Cited Authorities

Page

United States v. Vertac Chem. Corp., 79 F. Supp.2d

1034 (E.D. Ark. 1999), vacated, 247 F.3d 706 (8th

Cir.), cert. denied, 534 U.S. 1065 (2001) 5, 8, 19

United States v. Vertac Chem. Corp., 33 F. Supp.2d

769 (E.D. Ark. 1998)

United States v. Vertac Chem. Corp., 966 F. Supp.

1491 (E.D. Ark. 1997), aff’d in part and rev’d in

part, 247 F.3d 706 (8th Cir.), cert. denied,

534 U.S. 1065 (2001)

United States v. Vertac Chem. Corp., 756 F. Supp.

1215 (E.D. Ark. 1991), aff’d, 961 F.2d 786

(8th Cir. 1992)

United States v. Vertac Chem. Corp., 671 F. Supp.

595 (E.D. Ark. 1987), vacated, 855 F.2d 856

(8th Cir. 1988) (table)

United States v. Vertac Chem. Corp., 588 F. Supp.

1294 (E.D. Ark. 1984)

United States Constitution:

U.S. Const. amend V

ix

Cited Authorities

Rules:

Sup. Ct. R. 10(a)

Sup. Ct. R. 10(c)

Statutes:

26 U.S.C. §§ 9701-22

28 U.S.C. § 1254

28 U.S.C.

28 U.S.C.

28 U.S.C.

33 U.S.C. § 1345

42 U.S.C. § 6973

ree

i ae gO 6) ae 2,3, 4, 6, 14

42 U.S.C. § 9613

x

TABLE OF APPENDICES

Appendix A — Opinion Of The United States Court

Of Appeals For The Eighth Circuit Filed July 13,

Appendix B — Opinion Of The United States District

Court For The Eastern District Of Arkansas,

Western Division Dated March 30, 2005

Appendix C — Opinion Of The United States Court

Of Appeals For The Eighth Circuit Filed April 10,

Appendix D — Memorandum Opinion And Order

Of The United States District Court For The

Eastern District Of Arkansas, Western Division

Dated October 23, 1998

Appendix E — Opinion Of The United States District

Court For The Eastern District Of Arkansas Dated

May 21, 1997

Appendix F — Order Of The United States Court

Of Appeals For The Eighth Circuit Denying

Petition For Rehearing Filed September 19,

]

Chemtura Canada Co./Cie, formerly known as Crompton

Co./Cie, formerly known as Uniroyal Chemical Limited

(“Uniroyal”), petitions this Court for a writ of certiorari to the

United States Court of Appeals for the Eighth Circuit.

OPINIONS BELOW

The relevant opinions of the Court of Appeals are published

at United States v. Hercules, Inc., 247 F.3d 706 (8th Cir. 2001)

(Appendix C), and United States v. Vertac Chemical

Corporation, 453 F.3d 1031 (8th Cir. 2006) (Appendix A). The

relevant opinions of the United States District Court for the

Eastern District of Arkansas are published at United States v.

- Vertac Chemical Corporation, 966 F. Supp. 1491 (E.D. Ark.

1997) (Appendix E), United States v. Vertac Chemical

Corporation, 33 F. Supp.2d 769 (E.D. Ark. 1998) (Appendix

D), and United States v. Vertac Chemical Corporation, 364

F. Supp.2d 941 (E.D. Ark. 2005) (Appendix B).

JURISDICTION

The Court of Appeals filed its opinion on July 13, 2006.

The Court of Appeals denied a timely petition for rehearing and

rehearing en banc on September 19, 2006. This Court has

jurisdiction under 28 U.S.C. § 1254.

STATUTORY AND CONSTITUTIONAL

PROVISIONS INVOLVED

Section 107(a) of the Comprehensive Environmental

Response, Compensation, and Liability Act provides, in

pertinent part:

Notwithstanding any other provision or rule of

law, and subject only to the defenses set forth in

2

subsection (b) of this section— ... (3) any person

who by contract, agreement, or otherwise arranged

for disposal or treatment, or arranged with a

transporter for transport for disposal or treatment,

of hazardous substances owned or possessed by such

person, by another party or entity, at any facility or

incineration vessel owned or operated by another

party or entity and containing such hazardous

substances ... shall be liable... .

42 U.S.C. § 9607(a).

The Fifth Amendment to the United States Constitution

provides, in pertinent part: “No person shall be .. . deprived of

... property, without due process of law; nor shall private

property be taken for public use, without just compensation.”

STATEMENT OF THE CASE

This petition arises from actions brought by the United

States, the State of Arkansas, and Hercules Incorporated

(“Hercules”) against Uniroyal, culminating in a judgment of

joint-and-several liability for over $110 million under the

Comprehensive Environmental Response, Compensation, and

Liability Act (“CERCLA”), 42 U.S.C. § 9601 et seq. The District

Court originally had subject-matter jurisdiction under 28 U.S.C.

§§ 1331 and 1335, 42 U.S.C. § 6973, and 33 U.S.C. § 1345.

The District Court had subject-matter jurisdiction over claims

later added under 42 U.S.C. §§ 9607 and 9613. The Court of

Appeals had jurisdiction over the relevant appeals under 28

U.S.C. § 1291.

The United States initially developed the Vertac Chemical

Corporation (“Vertac”) site in Jacksonville, Arkansas, as a

munitions factory in the 1930s. The site was sold in the 1940s

3

to Reasor-Hill Corporation (“Reasor-Hill”), now a defunct

company. Reasor-Hill began manufacturing phenoxy herbicides,

including trichlorophenoxyacetic acid (“2,4,5-T”), at the site in

1958. In 1961, Hercules bought the site, and, in 1974, Hercules

leased the site to Transvaal, Inc., the predecessor to Vertac. Vertac

bought the site from Hercules in 1976. Hercules produced 2,4,5-

T at the site from 1961 until 1970. Vertac produced 2,4,5-T

at the site from 1971 until 1979. Site operators produced

the other principal product manufactured at the site,

dichlorophenoxyacetic acid (“2,4-D”), from 1958 until 1986.

See United States v. Vertac Chem. Corp., 453 F.3d 1031, 1036-

38 (8th Cir. 2006).

In 1980, the United States Environmental Protection Agency

sued Vertac and Hercules for an injunction against the discharge

of hazardous waste at the site. United States v. Hercules, Inc.,

247 F.3d 706, 713 (8th Cir.), cert. denied, 534 U.S. 1065 (2001).

“The Arkansas Department of Pollution Control and Ecology

sought similar relief under state law.” Id.:“Several years later,

the [District Court] approved consent decrees representing a

negotiated remedial plan to address the containment and

monitoring of waste.” /d. (citing United States v. Vertac Chem.

Corp., 588 F. Supp. 1294, 1296-97 (E.D. Ark. 1984)). “The

lawsuit was later converted into” an action under CERCLA. Id.

Although Vertac stipulated that it was an owner and

operator of the site liable to the government for

response costs under CERCLA, it ultimately failed

to comply with the consent decrees and eventually

sold its assets to third parties, forcing the [District

Court] in 1987 to appoint a receiver to handle the

company’s affairs.

Id. (citing United States v. Vertac Chem. Corp., 671 F. Supp.

595, 623-24 (E.D. Ark. 1987), vacated, 855 F.2d 856 (8th Cir.

4

1988) (table); United States v. Vertac Chem. Corp., 756 F. Supp.

1215 (E.D. Ark. 1991), aff’d, 961 F.2d 786 (8th Cir. 1992)).

“In an effort to identify all those potentially liable for

environmental harm at the site, numerous additional parties,

including the United States Department of Defense, were

brought into the suit.” Jd. “These parties filed various cross-

claims, counterclaims, and third part complaints; many of the

parties settled [for a few million dollars] and entered into consent

decrees.” Jd. at 713-14.

The Court of Appeals summarized the pertinent facts as to

Uniroyal:

Uniroyal was one of Vertac’s customers and

purchased 2,4,5-T and other products from Vertac

in the 1970s. In 1978, Vertac informed Uniroyal that

it lacked the funds to purchase enough 1,2,4,5-

tetrachlorobenzene (TCB), a key ingredient in the

manufacture of 2,4,5-T, to fulfill its contractual

obligations to Uniroyal. Uniroyal agreed to supply

Vertac with enough TCB to create some 1.3 million

pounds of 2,4,5-T that was to be shipped back to

Uniroyal. Vertac did not purchase the TCB directly

from Uniroyal, but instead reduced the amount it

charged Uniroyal for the 2,4,5-T to reflect the value

of the TCB that Uniroyal had supplied. This

arrangement was embodied in two separate contracts

and was carried out between March 1978 and March

1979. The 2,4,5-T that was produced with Uniroyal’s

TCB represents less than one percent of the more

than 150 million pounds of 2,4-D and 2,4,5-T that

were manufactured at the site over the course of its

operation.

Vertac, 453 F.3d at 1038. The District Court found that Uniroyal

owned the TCB throughout the manufacturing process. The

5

Court of Appeals upheld that finding as not “clearly erroneous.”

Hercules, 247 F.3d at 721.

Notwithstanding the issue of ownership, the parties

stipulated in the District Court that Uniroyal exercised no

control over Vertac’s manufacture of 2,4,5-T or over the

operation of the site. The District Court found that “Uniroyal

was in no position to manage the disposal of any hazardous

materials.” United States.v. Vertac Chem. Corp., 79

F. Supp.2d 1034, 1040 (E.D. Ark. 1999), vacated on other

grounds, 247 F.3d 706 (8th Cir.), cert. denied, 534 U.S. 1065

(2001). No one ever challenged that factual finding on appeal.

Former employees and officers of Vertac testified that

Uniroyal had no authority to control Vertac’s operations. That

Uniroyal did not have the authority or opportunity to control

the disposal or treatment of hazardous substances at the

Vertac site was implicit in the decisions of the District Court

and the Court of Appeals. See United States v. Vertac Chem.

Corp., 966 F. Supp. 1491 (E.D. Ark. 1997), aff’d in part and

rev'd in part, 247 F.3d 706 (8th Cir.), cert. denied, 534 US.

1065 (2001).

Although Uniroyal never had the opportunity to control

any aspect of Vertac’s disposal or treatment of any hazardous

substances, the District Court found Uniroyal liable as an

entity that “arranged for” the disposal or treatment of

hazardous substances under CERCLA § 107(a)(3), holding

that “actual control [is] not necessary for arranger liability.”

Vertac, 966 F. Supp. at 1501. Uniroyal challenged that

decision on appeal, but the Court of Appeals affirmed.

Hercules, 247 F.3d at 720; Vertac, 453 F.3d at 1047.

Uniroyal also argued that retroactive application of

CERCLA on the facts of this case violated the Due Process

6

and Takings Clauses of the Fifth Amendment to the United

States Constitution because Uniroyal’s liability was

unforeseeable and substantially disproportionate to

Uniroyal’s conduct. The Court of Appeals initially recognized

that inquiry into the constitutionality of CERCLA in this case

would be “essentially ad hoc and fact intensive.” Hercules,

247 F.3d at 722 (citing Eastern Enterprises v. Apfel, 524 U.S.

498, 523 (1998) (plurality opinion)). However, the Court of

Appeals ultimately rejected Uniroyal’s as-applied

constitutional challenge without any analysis of the facts of

the case. Vertac, 453 F.3d at 1047-48.

Uniroyal first asks this Court to resolve a split among

the Courts of Appeals concerning the standard for imposing

“arranger liability” under CERCLA. Here, the Eighth Circuit

— contrary to the Second, Third, Fifth, Seventh, Ninth, Tenth,

and Eleventh Circuits — held an entity that exercised no

control over the disposal or treatment of hazardous

substances, and possessed neither the authority nor the

opportunity to control the disposal or treatment of hazardous

substances, liable as one that “arranged for’ the disposal or

treatment of hazardous substances. This petition thus raises

an important issue that was decided by the Court of Appeals

in a manner that conflicts with the decisions of other Courts

of Appeals. This Court should resolve that conflict. Sup. Ct.

R. 10(a).

Uniroyal next asks this Court to decide whether

retroactive application of CERCLA to impose unforeseeable,

staggering joint-and-several liability that is disproportionate

to the actor’s lawful, non-negligent conduct violates the Fifth

Amendment to the United States Constitution. The

transactions at issue between Uniroyal and Vertac involved

approximately $1.5 million, yet the Court of Appeals’

decision could result in the imposition of liability on Uniroyal

for over $110 million in response costs. This petition raises

an important federal question that was decided by the Court

of Appeals in conflict with the decisions of this Court. This

Court should address that question. Sup. Ct. R. 10(c).

REASONS FOR GRANTING THE PETITION

The Eighth Circuit’s Interpretation Of CERCLA

Arranger Liability Conflicts With The Statutory

Language And The Decisions Of Other Courts of

Appeals.

Section 107(a)(3) of CERCLA imposes liability on “any

person who by contract, agreement, or otherwise arranged

for disposal or treatment ... of hazardous substances .. .

owned or possessed by such person... .” 42 U.S.C.

§ 9607(a)(3). For arranger liability to attach, a person must

both “own[{] or possess[]” hazardous substances and

“arrange[] for” their disposal or treatment. Jd. “CERCLA

does not define the phrase ‘arranged for.’” South Florida

Water Mgmt. Dist. v. Montalvo, 84 F.3d 402, 406 (1 Ith Cir.

1996) (internal citations omitted); see also United States v.

Cello-Foil Prods., Inc., 100 F.3d 1227, 1231 (6th Cir. 1996)

(same); Amcast Indus. Corp. v. Detrex Corp., 2 F.3d 746,

751 (7th Cir. 1993) (same), cert. denied, 510 U.S. 1044

(1994). CERCLA’s legislative history provides little guidance

in determining the meaning of these words. Montalvo, 84

F.3d at 406 n. 6; United States v. Aceto Agric. Chems. Corp.,

872 F.2d 1373, 1380 n. 8 (8th Cir. 1989). “Congress has left

this task to the courts, and the courts have at times struggled

with the contours of ‘arranger liability’ under § 107(a)(3).”

Montalvo, 84 F.3d at 406.

.

The parties stipulated that Uniroyal exercised no control

over the manufacture of 2,4,5-T or over the operation of the

Vertac site. The District Court found that “Uniroyal was in

no position to manage the disposal of any hazardous

materials.” Vertac, 79 F. Supp.2d at 1040. Nonetheless, both

the District Court and the Court of Appeals held Uniroyal

liable as an arranger, reasoning that Uniroyal owned the TCB

throughout Vertac’s manufacturing process and that control

is not “necessary” to expose a person to arranger liability.

Vertac, 966 F. Supp. at 1501; Hercules, 247 F.3d at 720.

The holding that control is unnecessary conflicts with the

plain language of § 107(a)(3), which requires that a person

both “owned or possessed” the hazardous substances and

“arranged for” their disposal or treatment. See Morton Intern.,

Inc. v. A.E. Staley Mfg. Co., 343 F.3d 669, 676-77 (3d Cir.

2003). The Court of Appeals read the words arranged for

out of § 107(a)(3) and rendered this central language of the

statute superfluous.

The Courts of Appeals have adopted differing standards

for the imposition of CERCLA arranger liability. The Third

Circuit recognized:

Almost all of our sister circuit courts have adopted

a standard for “arranger liability,” but the

standards adopted vary. See Geraghty and Miller,

Inc. v. Conoco Inc., 234 F.3d 917, 929 (Sth Cir.

2001), cert. denied, 533 U.S. 950, 121 S.Ct. 2592,

150 L.Ed.2d 751 (2001); Freeman v. Glaxo

Wellcome, Inc., 189 F.3d 160, 164 (2d Cir. 1999);

Pneumo Abex Corp. v. High Point, Thomasville

and Denton R.R. Co., 142 F.3d 769, 775 (4th Cir.

1998); United States v. Cello-Foil Products, Inc.,

100 F.3d 1227, 1231-32 (6th Cir. 1996); South

9

Florida Water Management District v. Montalvo,

84 F.3d 402, 407 (11th Cir. 1996); Amcast

Industrial Corporation v. Detrex Corp., 2 F.3d

746, 751 (7th Cir. 1993); Jones-Hamilton Co. v.

Beazer Materials & Servs., Inc., 973 F.2d 688,

695 (9th Cir. 1992); United States v. Aceto

Agricultural Chems. Corp., 872 F.2d 1373, 1381-

82 (8th Cir. 1989).

Morton, 343 F.3d at 676-77.

Even before the decisions below, the Eighth Circuit had

advanced the most liberal interpretation of the words

arranged for. See Mathews v. Dow Chem. Co., 947 F. Supp.

1517, 1523 (D. Colo. 1996) (citing Aceto, 872 F.2d at 1378-

82). In Aceto, the Court of Appeals emphasized that, because

of an allegation of ownership, it was reasonable to infer from

the complaint that the defendants had the authority to control

the waste-disposal practices at issue. 872 F.2d at 1383.

However, in the case at bar, the Court of Appeals discounted

the importance of that conclusion. Despite the fact that, in

Aceto, there was no meaningful difference between the

CERCLA claim and the claim under the Resource

Conservation and Recovery Act, 42 U.S.C. § 6973 et seq.

(“RCRA”), the Court of Appeals below reasoned:

Although we stated in Aceto that “it may be

reasonably inferred that [defendants] had the

authority to control the way in which the

pesticides were formulated,” . . . this observation

came as part of our discussion of RCRA and was

not necessary to our prior conclusion that the

complaint stated a valid claim under CERCLA.

Indeed, in the portion of Aceto that discussed

10

CERCLA, we specifically rejected the defendants’

contention that control is required in every

circumstance. To support their argument, the

defendants in Aceto quoted NEPACCO, 810 F.2d

at 743, for the proposition that they should “escape

liability because they had no authority to control”

the formulation and disposal process.... We

distinguished NEPACCO by observing that a

finding of control had been necessary in that case

only because ownership was lacking. . . . The

Aceto defendants, however, unlike those in

NEPACCO, “actually owned the hazardous

substances, as well as the work in process,” ...

and thus an arguable absence of control did not

mandate dismissal of the complaint. Control,

therefore, is not a necessary factor in every case

of arranger liability... .

Hercules, 247 F.3d at 720 (internal citations omitted).

Holding that the imposition of arranger liability does not

require a finding of control, the Court of Appeals departed

from its earlier interpretation of CERCLA arranger liability.

The Court of Appeals had unequivocally stated, “We agree

... that, in the wake of United States v. Gurley, 43 F.3d

1188 (8th Cir.1994),] and [United States v. Vertac Chemical

Corporation, 46 F.3d 803 (8th Cir. 1995)], a finding of

arranger liability requires some level of actual participation

in, or exercise of control over, activities that are causally

connected to, or have some nexus with the arrangement for

disposal of hazardous substances or the off-site disposal

itself.” United States v. TIC Inv. Corp., 68 F.3d 1082, 1087-

88 (8th Cir. 1995). Indeed, in an earlier appeal in this very

case, the Court of Appeals held that the United States

11

Department of Defense was not liable for any response costs

because it did not control the disposal of hazardous substances.

Vertac, 46 F.3d at 809. The Court of Appeals’ current standard

for arranger liability, as articulated below, reaches much further

than these earlier cases.

Numerous Courts of Appeals have rejected the Eighth

Circuit’s approach. At the other end of the spectrum, the United

States Court of Appeals for the Second Circuit held:

Congress employed traditional notions of duty and

obligation in deciding which entities would be liable

under CERCLA as arrangers for the disposal of

hazardous substances. Accordingly, this court

concludes that it is the obligation to exercise control

over hazardous waste disposal, and not the mere

ability or opportunity to control the disposal of

hazardous substances that makes an entity an

arranger under CERCLA’s liability provision.

General Elec. Co. vy. AAMCO Transmissions, Inc., 962 F.2d 281,

286 (2d Cir. 1992) (emphasis in original). The Second Circuit

observed that “courts have found that ownership of hazardous

substance, when combined with actual control over the process

that generates the hazardous waste, supports arranger liability.”

Id. at 287. In the Second Circuit, even “the opportunity or ability

to control a third-party’s waste disposal practices” does not

suffice to hold a person “liable as an entity that ‘otherwise

arranged for’ disposal or transport of hazardous waste.” /d. at

286. The United States Court of Appeals for the Fifth Circuit

cited the Second Circuit’s opinion with approval. See Geraghty

and Miller, Inc. v. Conoco, Inc., 234 F.3d 917, 929 (Sth Cir.

2000), cert. denied, 533 U.S. 950 (2001).

12

Likewise, the United States Court of Appeals for the

Third Circuit has explained, “Ownership or possession of

the hazardous substance must be demonstrated, but this factor

alone will not suffice to establish liability. A plaintiff must

also demonstrate either control over the process that results

in a release of hazardous waste or knowledge that such a

release will occur during the process.” Morton, 343 F.3d at

677-78.

Using the Eighth Circuit’s earlier cases, the United States

Court of Appeals for the Ninth Circuit expressed its view as

follows:

To summarize our view of Aceto and NEPACCO,

and to assess the interrelationship of the factors

of ownership, possession, and control over waste

disposal, we can do no better than to quote from

Judge Levi’s careful opinion in United States v.

Iron Mountain Mines, Inc., 881 F.Supp. 1432

(E.D. Cal. 1995). He writes:

It is true that some cases impose arranger

liability on parties who did not literally own

or physically possess hazardous waste at the

time it was disposed of or released. But in

each of these cases the party either was the

source of the pollution or managed its

disposal by the arranger [citing numerous

cases, including Aceto and NEPACCO|.

No court has imposed arranger liability on a

party who never owned or possessed, and

never had any authority to control or duty to

dispose of, the hazardous materials at issue.

13

See, e.g., General Elec. Co. v. AAMCO

Transmissions, Inc., 962 F.2d 281, 286 (2d

Cir. 1992) (“it is the obligation to exercise

control over hazardous waste disposal, and

not the mere ability or opportunity to control

the disposal of hazardous substances that

makes an entity an arranger under CERCLA’s

liability provision”) (emphasis in original).

United States v. Shell Oil Co., 294 F.3d 1045, 1058-59 (9th

Cir. 2002).

The United States Court of Appeals for the Eleventh

Circuit interpreted the Eighth Circuit’s decision in Aceto as

Uniroyal did. The Eleventh Circuit rejected the plaintiffs’

reliance on Aceto in South Florida Water Management

District v. Montalvo, 84 F.3d 402 (11th Cir. 1996). The

Montalvo panel noted that, in Aceto, the Eighth Circuit had

concluded that “it was possible to infer the manufacturers

exercised some control over the formulator’s mixing

process.” Jd. at 408. The Eleventh Circuit found that the

Montalvo plaintiffs had not alleged that the defendants “had

sufficient knowledge of or control over plaintiffs’ disposal

practices to be held liable” as “arrangers” for the disposal of

hazardous substances. /d. at 409. And the United States Court

of Appeals for the Eleventh Circuit has ruled,

If Congress wishes to impose liability on parties

who contract for services that produce hazardous

waste, it, not us, has the authority to do so. We

emphasize, however, that our opinion does not

foreclose the possibility that a party could so

control and benefit from another company’s

id

production of hazardous waste that arranger

liability would arise under 42 U.S.C. § 9607(a)(3).

Concrete Sales and Servs., Inc. v. Blue Bird Body Co., 211

F.3d 1333, 1339 (Lith Cir. 2000). See Amcast Indus. Corp.

v. Detrex Corp., 2 F.3d 746, 751 (7th Cir. 1993) (“The words

(‘arranged for’] imply intentional action. The only thing that

Detrex arranged for Transport Services to do was to deliver

TCE to Elkhart’s storage tanks. It did not arrange for spilling

the stuff on the ground.”), cert. denied, 510 U.S. 1044 (1994).

The United States Court of Appeals for the Tenth Circuit

applied this Court’s decision in United States v. Bestfoods,

524 U.S. 51 (1998), which defined the standard for “operator

liability” to require one to “manage, direct, or conduct

operations specifically related to pollution, that is, operations

having to do with the leakage or disposal of hazardous waste,

or decisions about compliance with environmental

regulations,” to cases involving arranger liability. Raytheon

Constructors, Inc. v. Asarco, Inc., 368 F.3d 1214, 1217 (10th

Cir. 2003).

If the United States had brought this case in the Second,

Third, Fifth, Seventh, Ninth, Tenth, or Eleventh Circuit,

Uniroyal likely would not have been held liable under

CERCLA as one that “arranged for” the disposal or treatment

of hazardous substances. At the same time, in addition to the

Eighth Circuit, the United States Court of Appeals for the

Sixth Circuit imposes arranger liability in the absence of a

finding of control. The Sixth Circuit held that “a party can

be responsible for ‘arranging for’ disposal, even when it has

no control over the process leading to the release of

substances.” United States v. Cello-Foil Prods., Inc., 100 F.3d

1227, 1232 (6th Cir. 1996). The appropriate inquiry,

15

according to the Sixth Circuit, “is whether the party intended

to enter into a transaction that included an ‘arrangement for’

the disposal of hazardous substances.” /d. at 1231.

The Courts of Appeals’ differing standards for the

imposition of CERCLA arranger liability generate confusion

and inequity in the marketplace. While the Second Circuit

requires an obligation to control the disposal or treatment of

hazardous substances to impose arranger liability, the Eighth

Circuit held Uniroyal liable as an arranger despite the absence

of even the opportunity to control the disposal or treatment

of hazardous substances. Liability for environmental cleanup

costs is often staggering: Here, the judgment potentially

exposes Uniroyal to liability for over $110 million. This

Court should resolve the split among the Circuit Courts of

Appeals and provide a uniform standard for the imposition

of CERCLA arranger liability.

II. The Court of Appeals’ Opinion Imposes Unforeseeable

Joint-And-Several Liability For Over $110 Million

Based On Lawful, Non-Negligent Conduct Involving

Only About $1.5 Million In Transactions In Violation

Of The Fifth Amendment To The United States

Constitution.

The Court of Appeals rejected Uniroyal’s as-applied

challenge to CERCLA’s constitutionality on the ground

that it had previously rejected challenges to CERCLA’s

constitutionality. Vertac, 453 F.3d at 1047-48. The Court of

Appeals ruled that the retroactive application of CERCLA is

never unconstitutional, even when a retroactive application

imposes severe liability on a limited class of parties that could

not have anticipated the liability and the liability is

substantially disproportionate to the parties’ experience and

settled expectations.

16

“(T]he presumption against retroactive legislation is

deeply rooted in our jurisprudence.” Landgraf v. USI Film

Prods., 511 U.S. 244, 265 (1994). The retroactive application

of legislation that imposes unexpected, severe, and

disproportionate liability violates the Fifth Amendment to

the United States Constitution. Eastern Enterprises v. Apfel,

524 U.S. 498 (1998). “Elementary considerations of fairness

dictate that individuals should have an opportunity to know

what the law is and to conform their conduct accordingly;

settled expectations should not be lightly disrupted.”

Landgraf, 511 U.S. at 265. The “principle that the legal effect

of conduct should ordinarily be assessed under the law that

existed when the conduct took place has timeless and

universal appeal.” Jd. (quoting Kaiser Aluminum & Chem.

Corp. v. Bonjorno, 494 U.S. 827, 855 (1990) (Scalia, J.,

concurring)). CERCLA does not expressly provide for

retroactivity, and Uniroyal’s activities giving rise to CERCLA

liability in this case predated CERCLA and were lawful and

non-negligent. Nonetheless, Uniroyal was unexpectedly held

jointly and severally liable for over $110 million in CERCLA

response costs.

In Eastern Enterprises, this Court held the Coal Industry

Retiree Health Benefit Act of 1992 (the “Coal Act”),

26 U.S.C. §§ 9701-22, unconstitutional as applied to impose

retroactive liability on a company to pay health benefits to

over 1,000 of its former employees. Although there was no

single opinion for the Court, Justice O’Connor, writing for a

plurality that included Chief Justice Rehnquist, Justice Scalia,

and Justice Thomas, distilled three factors of “particular

significance” from prior cases: “The economic impact of the

regulation, its interference with reasonable investment

backed expectations, and the character of the governmental

action.” Eastern Enters., 524 U.S. at 523; see also Kaiser

17

Aetna v. United States, 444 U.S. 164, 174-75 (1979). The

plurality opined that, while several prior cases had upheld

retroactive statutes, their imposition of retroactive liability was

“confined to short and limited periods required by the

practicalities of producing national legislation.” Eastern Enters.,

524 U.S. at 526. The plurality concluded that the Takings Clause

of the Fifth Amendment forbids the application of a statute in a

particular case if the law “imposes severe retroactive liability

on a limited class of parties that could not have anticipated the

liability, and [if] the extent of that liability is substantially

disproportionate to the parties’ experience.” /d. at 528-29.

Justice Kennedy, concurring in the judgment and dissenting

in part, agreed that the Coal Act, as applied to Eastern

Enterprises, was arbitrary and therefore unconstitutional. Justice

Kennedy rested his decision on the Due Process Clause of the

Fifth Amendment rather than on the Takings Clause. That said,

Justice Kennedy stated that he was “in full accord with many of

the plurality’s conclusions[.]” /d. at 539. He agreed that “[t]he

plurality’s careful assessment of the history and purpose of the

statute in question demonstrates the necessity to hold it arbitrary

and beyond the legitimate authority of the Government to enact.”

Id.

The four dissenters likewise recognized that retroactive

application of a federal statute may be unconstitutional under

the Due Process Clause of the Fifth Amendment. The dissenters

explained that, “like the plurality,” they “would inquire if the

law” as applied retroactively was “fundamentally unfair or

unjust.” /d. at 558 (Breyer, J., joined by Stevens, Souter, and

Ginsburg, JJ., dissenting). “{TJhe Due Process Clause can offer

protection against legislation that is unfairly retroactive[,] for

... @ law that is fundamentally unfair because of its retroactivity

is a law that is basically arbitrary.” /d. at 557. The dissent noted

18

that the same three factors articulated by the plurality could

properly be applied in the due process, rather than takings,

context. Jd. (citing Connolly v. Pension Benefit Guar. Corp.,

475 U.S. 211, 227 (1986)). The dissenters concluded that,

on the facts before them, retroactive application of the Coal

Act to Eastern Enterprises was not fundamentally unfair or

unjust. But every Justice in Eastern Enterprises agreed with

the core proposition that “an unfair retroactive assessment

of liability upsets settled expectations, and ... thereby

undermines a basic objective of law itself.” Id. at 558 (Breyer,

J., joined by Stevens, Souter, and Ginsburg, JJ., dissenting);

compare id. at 532 (plurality) (“Retroactivity is generally

disfavored in the law, in accordance with fundamental notions

of justice that have been recognized throughout history”)

(internal quotation marks and citations omitted); id. at 547

(Kennedy, J., concurring in the judgment) (“for centuries our

law has harbored a singular distrust of retroactive statutes”).

Some courts, including the Court of Appeals below in

one opinion, have recognized that Eastern Enterprises can

provide a basis to challenge a retroactive application of

CERCLA. See, e.g., Hercules, Inc., 247 F.3d at 722 (stating

that “inquiry into the constitutionality of CERCLA ... would

be ‘essentially ad hoc and fact intensive’”) (quoting Eastern

Enterprises); Coeur D’Alene Tribe v. Asarco Inc., 280 F.

Supp.2d 1094, 1111 (D. Idaho 2003) (“Defendants’ argument

that the retroactive application of CERCLA in this case is a

taking or in violation of the due process clause of the

Constitution as discussed in Eastern Enterprises [] is

reserved until the dollar amount of the damages is established

in the second phase of the trial.””). Other courts have refused

to apply Eastern Enterprises to evaluate the constitutionality

of the retroactive application of CERCLA on the ground that

the decision has no precedential effect. See, e. g., United States

19

v. Alcan Aluminum Corp., 315 F.3d 179, 189 (2d Cir. 2003)

(“The only binding aspect of [Eastern Enterprises] is its

specific result, and so the authority of Eastern Enterprises

is confined to its holding that the Coal Act is unconstitutional

as applied to Eastern Enterprises.”); Franklin County Conv.

Facilities vy. American Premier, 240 F.3d 534, 552 (6th Cir.

2001) (holding that ‘Eastern Enterprises has no precedential

effect [on the retroactive application of CERCLA] because

no single rationale was agreed upon by the Court’).

The judgment in this case holds Uniroyal jointly and

severally liable for over $110 million in response costs as a

result of lawful, non-negligent conduct involving only $1.5

million in transactions. As the District Court recognized,

“Uniroyal and Hercules are left ‘holding the bag’ for Vertac,

who at least arguably caused the greatest amount of harm.”

Vertac, 79 F. Supp.2d at 1036. Retroactive application of

CERCLA can result in this sort of large-scale, unexpected

liability and thereby undermine the “free, dynamic society”

that is “fostered by a rule of law that gives people confidence

about the legal consequences of their actions.” Landgraf, 511

U.S. at 266. The Court of Appeals’ ruling that the retroactive

application of CERCLA is never susceptible to an as-applied

constitutional challenge fails to address this Court’s opinion

_in Landgraf and directly contradicts the views of all the

Justices of this Court in Eastern Enterprises. This Court

should decide whether the retroactive application of

CERCLA can violate the Constitution and whether it does

so as to Uniroyal in this case.

20

CONCLUSION

For all these reasons, the petition for a writ of certiorari to

the United States Court of Appeals for the Eighth Circuit should

be granted.

Respectfully submitted,

STEVEN W. QUATTLEBAUM

E. B. Cues ['V*

JoserH R. FALAsco

QUATTLEBAUM, GROOMS,

TuLL & Burrow PLLC

111 Center Street, Suite 1900

Little Rock, Arkansas 72201

(501) 379-1700

Attorneys for Petitioner

* Counsel of Record

APPENDIX

la

APPENDIX A — OPINION OF THE UNITED STATES

COURT OF APPEALS FOR THE EIGHTH CIRCUIT

FILED JULY 13, 2006

UNITED STATES COURT OF APPEALS

FOR THE EIGHTH CIRCUIT

Nos. 05-3147, 05-3153.

Submitted: March 13, 2006.

Filed: July 13, 2006.

Rehearing and Rehearing En Banc Sept. 19, 2006"

UNITED STATES of America,

Plaintiff/Appellee,

Arkansas Department of Pollution Control and Ecology,

Plaintiff,

V.

VERTAC CHEMICAL CORPORATION,

Defendant,

Hercules, Inc.,

Defendant/Appellant,

* Chief Judge Loken did not participate in the consideration or

decision of this matter.

2a

Appendix A

Inter-Ag Corporation; Department of Defense; Dow

Chemical Corporation; Velsicol Chemical Corporation; John

Does, 1-5; Chemtura Corporation, formerly known as

Crompton Co., formerly known as CIE, formerly known

as Uniroyal Chemical Limited,

Defendants,

John Doull, Ph.D., M.D.; Karl K. Rozman, Ph.D.; William

J. Waddell, M.D.; K. Roger Hornbrook, Ph.D.; Daniel M.

Byrd, III, Ph.D., D.A.B.T.; Robert Golden, Ph.D.; B. Frank

Vincent, Ph.D.; American Council on Science and Health,

Amici on behalf of Appellant.

United States of America,

Plaintiff/Appellee,

Arkansas Department of Pollution Control and Ecology,

Plaintiff,

Fe

Vertac Chemical Corporation; Hercules, Inc.; Inter-Ag

Corporation; Department of Defense; Dow Chemical

Corporation; Velsicol Chemical Corporation;

John Does, 1-5;

Defendants,

Crompton Co./CIE,

Defendant/Appeltant.

3a

Appendix A

Before WOLLMAN, FAGG, and RILEY, Circuit Judges.

WOLLMAN, Circuit Judge.

Hercules, Inc. (Hercules) and Crompton Co./Cie

(Uniroyal)' raise constitutional claims and argue that the

district court? erred in assigning and apportioning liability

for environmental cleanup costs pursuant to the

Comprehensive Environmental Response, Compensation and

Liability Act (CERCLA), 42 U.S.C. § § 9601-0675, as

amended by the Superfund Amendments and Reauthorization

Act of 1986 (SARA), Pub.L. No. 99-499, 11 Stat. 1613. We

affirm.

I. BACKGROUND

This case involves twenty-six years of litigation and

numerous district court and appellate opinions, both

published and unpublished. At issue is the cost the United

States has incurred in its environmental cleanup efforts at

the Vertac Chemical Plant site in Jacksonville, Arkansas (the

Jacksonville site or the site). The full procedural and factual

history of this case has been discussed in several previous

decisions. This opinion will address the relevant portions of

each.

1. As of January 30, 2001, Uniroyal Chemical Limited changed

its name to Crompton Co./Cie. For consistency, we will use Uniroyal

throughout this opinion.

2. The Honorable George. Howard, Jr., United States District

Judge for the Eastern District of Arkansas.

4a

Appendix A

A. Factual History

The Jacksonville site was originally developed by

the federal government in the 1930s as a munitions factory.

In the late 1940s, the site was sold to Reasor-Hill Corporation

(Reasor-Hill), a now-defunct company. Reasor-Hill

first manufactured various pesticides, but began

manufacturing phenoxy herbicides in 1958. These

herbicides included dichlorophenoxyacetic acid (2,4-D) and

trichlorophenoxyacetic acid (2,4,5-T), synthetic hormones

that kill weeds or brush by accelerating growth to the point

of natural death. Although these herbicides biodegrade into

harmless substances, the manufacture of 2,4,5-T (but not 2,4-

D) creates a toxic byproduct that is now viewed as hazardous

to humans, 2,3,7,8-tetrachlorodibenzo-p-dioxin (dioxin).

While Reasor-Hill operated the site, an unknown quantity of

these and other untreated chemical wastes from the

production processes flowed through cooling ponds on the

west side of the plant into a nearby stream, Rocky Branch

Creek. Other wastes were stored in drums stacked in a field

on the site.

In 1961, Hercules bought the site and continued to

manufacture herbicides, including 2,4-D and 2,4,5-T, at the

plant until 1970. During this period, Hercules sold the bulk

of its product to the United States Department of Defense as

the defoliant Agent Orange, a herbicide made from a mixture

of 2,4-D and 2,4,5-T that was used in Vietnam to clear jungle

undergrowth.

Soon after Hercules took over the site, it buried the

deteriorating drums left by Reasor-Hill in unlined trenches

Sa

Appendix A

in the southeast corner of the site. Until late 1964, Hercules

continued Reasor-Hill’s practice of discharging untreated

waste water directly into Rocky Branch Creek. Hercules then

constructed a waste water pretreatment system, but the system

did not remove dioxin. It consisted of a neutralization trench

designed to reduce the acidity of the water, an equalization

basin designed to stabilize the rate of flow into the City of

Jacksonville’s sewage system, and a pump and pipe to deliver

the treated water to the sewage system. The system’s

equalization basin frequently overflowed during heavy

rainfalls, and it leaked.

After it learned of the toxicity of dioxin in 1965, Hercules

instituted a toluene extraction process designed to remove

organic impurities from 2,4,5-T products. This process

yielded residue (stillbottoms) containing extremely high

levels of dioxin. Hercules placed this residue in drums, some

of which it buried at the site and some of which it disposed

of at a nearby landfill. Hercules acknowledges that numerous

leaks and spills occurred during its operation of the site.

When the drums leaked in the process area before being

transported to the drum burial pit, Hercules’s practice was

to place any contaminated soil into the drum.

In 1970, Hercules ceased production at the site. Hercules

cleaned out all of its equipment and production vessels,

buried its waste, and shipped empty drums off-site. In 1971,

it leased the facility to Transvaal, Inc., which later became

Vertac Chemical Corp. (Vertac).’

3. Transvaal reorganized as Vertac in 1976. In this opinion, we

will refer to both corporations as Vertac.

6a

Appendix A

Vertac continued to manufacture 2,4-D and 2,4,5-T and

followed Hercules’s practice of burying most of the waste.

In 1975, however, Vertac began shipping its 2,4-D waste to

off-site landfills and began to store its 2,4,5-T stillbottoms

above ground with the hope that the waste would someday

be recycled. In 1976, Vertac purchased the site from Hercules.

Vertac voluntarily ceased manufacturing 2,4,5-T and 2,4,5-

TP on March 15, 1979.

On February 26, 1980, the United States Environmental

Protection Agency (EPA) issued a proposed rule under the

Toxic Substances Control Act to prevent Vertac from

disposing of the dioxin from the Jacksonville site. This rule,

known as the Vertac Rule, became final later that year and

prohibited the off-site disposal of 2,4-D wastes that contained

dioxin. If Vertac could show that a batch of 2,4-D produced

waste that was free of dioxins, it could dispose of that waste

and all subsequent 2,4-D waste off-site.

According to testimony at the hearing on the proposed

rule, Vertac had approximately 3200 drums of wastes

resulting from the production of 2,4-D. The first set of

samples taken from seven hundred drums of waste resulting

from the initial production of 2,4-D revealed dioxin levels

of approximately twenty parts per billion (ppb). The samples

were later sent to Wright State University and Monsanto

Company for testing. Monsanto could not detect any dioxin

with its analytical equipment, but Wright State detected

.7 ppb. In a second sampling of 1000 drums, it detected .5

ppb and the next sampling showed .3 ppb. Because the 2,4-

D waste contained dioxin, Vertac stopped analyzing samples

of the waste and allowed the drums to accumulate. Later

7a

Appendix A

testing by the State of Arkansas, as well as the results of trial

burns, revealed the presence of dioxin in the drums.

Vertac continued its operations until 1986. In 1987, it

abandoned the site, and the site went into receivership. By

then, there were nearly 29,000 drums at the site that contained

waste materials including 2,4-D, 2,4,5-T, and dioxin. Some

drums were labeled T waste, some D waste, some were

marked T and D, and some were not marked at all. Many of

these markings were indistinguishable or unreadable. More

than 15,000 drums were stored outside and exposed to the

elements. The drums were stacked three high on deteriorating

pallets and were failing at a rate of between five to three

hundred drums per week.

Many of the drums had corroded and leaked,

contaminating the soil, groundwater, and buildings at the site.

Contamination was found in other areas of the site, at the

landfills, in nearby neighborhoods, and in the grounds

adjacent to the site. After Vertac abandoned the plant, the

EPA took over the site, closed down all operations, and

assumed cleanup responsibilities that have cost well over

$110 million to date.

To carry out its response measures, the EPA divided the

site into five units: off-site areas, operable units 1, 2, and 3,

and the incineration response action. Several removal actions

addressed the immediate threat posed by the drummed waste

left on the site when it was abandoned. Four remedial actions

addressed the long term solutions for the rest of the site and

the surrounding area affected by the site. For each of the

remedial actions, the National Contingency Plan required the

8a

Appendix A

EPA to (1) conduct a remedial investigation of the site

conditions, including an endangerment assessment of the

threats posed by the contamination at the site; (2) perform a

feasibility study examining the various technical alternatives

for remediating the site; (3) take public comment on the EPA’s

proposed remedial action plan based on the alternatives

discussed in the feasibility study; (4) compile an

administrative record for remedial action decision making;

and (5) issue a written record of decision (ROD) explaining

the Regional Administrator’s reasoning in selecting the final

remedial action plan and responding to the public comments

received.

Uniroyal was one of Vertac’s customers and purchased

2,4,5-T and other products from Vertac in the 1970s. In 1978,

Vertac informed Uniroyal that it lacked the funds to purchase

enough 1,2,4,5-tetrachlorobenzene (TCB), a key ingredient

in the manufacture of 2,4,5-T, to fulfill its contractual

obligations to Uniroyal. Uniroyal agreed to supply Vertac

with enough TCB to create some 1.3 million pounds of 2,4,5-

T that was to be shipped back to Uniroyal. Vertac did not

purchase the TCB directly from Uniroyal, but instead reduced

the amount it charged Uniroyal for the 2,4,5-T to reflect the

value of the TCB that Uniroyal had supplied. This

arrangement was embodied tn two separate contracts and was

carried out between March 1978 and March 1979. The 2,4,5-

T that was produced with Uniroyal’s TCB represents less

than one percent of the more than 150 million pounds of

2,4-D and 2,4,5-T that were manufactured at the site over

the course of its operation.

9a

Appendix A

B. Procedural History’

On October 12, 1993, the district court granted the

government’s motion for summary judgment, holding that

Hercules was jointly and severally liable under CERCLA

sections 107(a)(2) and (3) for the response costs incurred by

the United States with regard to the Jacksonville site.

42 U.S.C. § 9607(a)(2) and (3); United States v. Vertac Chem.

Corp., 841 F.Supp. 884 (E.D.Ark.1993). Hercules moved for

reconsideration, arguing that disputed issues of fact existed

regarding divisibility. On November 1, 1993, the district court

denied Hercules’s motion, finding H ies had failed

to present evidence in support of its divisibility of harm

defense.

Hercules appealed that decision, and we reversed and

remanded the case to the district court to reconsider

Hercules’s claim of divisibility in light of the legal standards

enunciated in our April 11, 2001, opinion.’ United States v.

Hercules, Inc., 247 F.3d 706 (8th Cir.2001) (VVertac X/). In

October and December 2001, the district court held an

evidentiary hearing on Hercules’s divisibility of harm

4. Litigation began in 1980. For a description of the early

procedural history, see United States v. Hercules, Inc., 247 F.3d 706

(8th Cir.2001) and United States v. Vertac Chem. Corp., 966 F.Supp.

1491 (E.D.Ark.1997).

5. In its most recent opinion, the district court noted an

inconsistency in our April 11, 2001, opinion. In that opinion, we

meant to vacate: (1) the unpublished opinion issued on October 12,

1993, and (2) the denial of the motion to reconsider issued on

Nevemiber 1, 1993.

10a

Appendix A

defense, resulting in a transcript of some 2300 pages in

length. The parties submitted post-hearing briefs, together

with a voluminous record that included documents, exhibits,

transcripts, depositions, and the administrative record. The

district court considered the entire record, applied the law as

stated in Vertac XI, and held that Hercules had failed to

establish its divisibility of harm defense, with the exception

of one off-site landfill, the Rogers Road landfill (a divisibility

finding that the government does not challenge). United

States v. Vertac Chem. Corp., 364 F.Supp.2d 941

(E.D.Ark.2005) (Vertac XII).

In its final judgment following its March 30, 2005,

memorandum opinion and order, the district court held that

Hercules and Uniroyal were jointly and severally liable to

the United States for the following amounts: (1) Hercules,

in the amount of $119,318,504, plus any additional response

costs, and (2) Uniroyal, in the amount of $110,410,161, plus

any additional costs. The district court had previously

allocated the amount of contribution of the total response

costs for which each entity was jointly and severally liable.

To the extent that the United States enforces its judgment,

Hercules is entitled to contribution from Uniroyal in an

amount equal to 2.6 percent of $110,410,161, and Uniroyal

is entitled to contribution from Hercules in an amount equal

to 97.4 percent of $110,410,161.

On appeal, Hercules argues that the district court erred

in apportioning liability. Uniroyal argues that we should

overturn our holding in Vertac X/ that affirmed the district

court’s holding that Uniroyal was liable. Hercules and

Uniroyal further argue that the district court’s imposition of

retroactive liability was unconstitutional.

lla

Appendix A

II. HERCULES’S LIABILITY

Hercules challenges the district court’s liability

determination on both legal and factual grounds. We will

first address Hercules’s contention that the district court

applied the wrong legal standard in determining whether

Hercules established its divisibility of harm defense. We will

then turn to Hercules’s argument that the drummed waste,

the stillbottoms, Operable Unit 1 (OU-1), the Jacksonville

Landfill, the soils, and the groundwater are each separate

sites capable of further apportionment.

We review de novo the district court’s legal conclusions.

Richardson v. Sugg, 448 F.3d 1046, 1052 (8th Cir.2006). We

review its factual findings for clear error. /d. “Using this

standard, we will overturn a factual finding only if it is not

supported by substantial evidence in the record, if it is based

on an erroneous view of the law, or if we are left with the

definite and firm conviction that an error was made.” Id. We

give due regard to the district court’s opportunity to judge

the credibility of the witnesses. Id. “A district court’s choice

between two permissible views of evidence cannot be clearly

erroneous.” Tadlock v. Powell, 291 F.3d 541, 546 (8th

Cir.2002).

A. Legal Standard

Hercules contends that the district court erred in

concluding that the site could not be separated into divisible

geographic units. As to the drums, Hercules argues that the

district court failed to consider whether there existed a single,

divisible harm and addressed only whether there existed

[2a

Appendix A

distinct harms. The thrust of Hercules’s arguments is factual,

however, and the district court applied the appropriate legal

standard.

In Vertac XI we held that a defendant must prove by a

preponderance of the evidence that there exists a reasonable

basis for divisibility. Vertac XI, 247 F.3d at 717.

The proper standard for determining divisibility

... is that the defendant show either distinct harms

or a reasonable basis for apportioning causation

for a single harm. A defendant need not prove that

its waste did not, or could not, contribute to any

of the harm at a CERCLA site in order to establish

divisibility, because it is also possible to prove

divisibility of single harms based on volumetric,

chronological or other types of evidence. A site

may also be divisible if a defendant can establish

that it consists of non-contiguous areas of

contamination.

Id. at 719 (internal quotations and citations omitted). We

noted that proving divisibility is a “very difficult proposition”

and that where the harms are incapable of division, the district

court should not make an arbitrary apportionment. /d. at 717.

In its opinion, the district court applied the standard for

determining divisibility as set forth in Vertac X/. The district

court first considered whether Hercules established a

reasonable basis for divisibility by proving by a

preponderance of the evidence that the site could be divisible

13a

Appendix A

on a geographical basis.© Under its geographical

apportionment theory, Hercules argued that each operable

unit within the Jacksonville site is a separate site for purposes

of divisibility. In considering and ultimately rejecting

Hercules’s argument, the district court found that the EPA

divided the site into operable units for the purposes of

remediation and that the “operable units did not solely

address geographical portions of the Site.” Vertac XII, 364

F.Supp.2d at 951.

With regard to the drums, Hercules argues that the district

court erroneously held that cross-contamination and

commingling of dioxin prevented Hercules from establishing

a reasonable basis for divisibility. In Vertac XI, we held that

a single harm may be treated as divisible when it is possible

to discern the degree to which different parties contributed

to the damage. “Single harms may also be treated as divisible

in terms of degree, based, for example on the relative

quantities of waste discharged into the stream. Divisibility

of this type may be provable even where wastes have become

cross-contaminated and commingled.” 247 F.3d at 718

(internal quotations omitted). Hercules, however, did not

argue that the drums caused a single, divisible harm that could

be apportioned based on relative quantities of waste or

volumetric evidence. As the government points out, this

argument would have been inconsistent with Hercules’s

6. We have considered Hercules’s argument concerning

the information contained in one of the government’s exhibits

(Exhibit K). Because the district court expressly stated at the time it

granted the government's motion to withdraw the exhibit that it would

not rely on the exhibit in ruling on Hercules’s divisibility defense,

we conclude that this argument is without merit.

l4a

Appendix A

argument that it should not be held liable for any of the

drummed waste.

B. Drummed Waste

The 28,500 drums contained 2,4-D and 2,4,5-T

stillbottom wastes, dioxin, and other hazardous and toxic

substances. When the site went into receivership, the drums

were leaking, corroding, and failing. By February 1989, the

failed drums had been placed inside new, larger drums

(overpacked). Because the drums contained corrosive

materials, maintenance of the drums was an ongoing process.

The EPA determined that the wastes on the site posed a threat

to public health and welfare and the environment. The

drummed material was considered acutely hazardous waste,

and the EPA chose to dispose of the wastes by incineration.

The Arkansas Department of Pollution Control and Ecology

(ADPC & E) managed the incineration from 1989 until June

1993, when the EPA took over the on-site incineration of the

drums.

Hercules argues that the district court clearly erred in

finding the following: (1) the EPA and the ADPC & E decided

to incinerate the 2,4-D waste drums because of the dioxin

contained therein; (2) Hercules was responsible for the cross-

contamination of the plant equipment causing 2,4-D waste

drums to contain dioxin; and (3) Hercules was responsible

for the commingling of the 2,4-D waste and the dioxin

contaminated soil, causing the drums to contain dioxin.

Hercules first argues that it should not be held liable for

the cost of incinerating the 2,4-D waste drums because those

15a

Appendix A

drums would have been incinerated regardless of whether

they were contaminated with dioxin. The district court

concluded that Hercules’s argument did not “withstand

scrutiny” and found that the EPA and Arkansas were

concerned that a potential fire, explosion, or tornado could

spread dioxin into the environment. Vertac XII, 364

F.Supp.2d at 953. Thus, the district court determined that

“fijt was not, as Hercules argues, the dirt in the drums that

drove the incineration; rather it was the dioxin in the dirt

that drove the incineration of the drums.” /d.

As the district court noted, in the factual background of

the case, the Vertac Rule permitted Vertac to landfill the

2,4-D waste drums only after showing that the drums

contained no dioxin. This was never shown, and Phyllis

Moore, Ph.D., the former director of the ADPC & E, and

Randall Mathis, her successor, testified (1) that time was of

the essence, (2) that further testing was expensive and time

consuming, (3) that the 2,4-D drums were corroding and

failing, and (4) that the drums posed an imminent risk of fire

and explosion.

Dr. Moore was involved in the initial decision to

incinerate the 2,4-D waste drums. Although she stated that

the “issue of dirt” did not influence her decision, Dr. Moore

testified that a primary concern was the presence of dioxin

in the 2,4-D waste drums, regardless of whether it was

transmitted to the drums by cross-contamination at the

production facility or by the overpacking of the drums with

contaminated soil. J.A. at 26433-34. She further testified that

it was important that the method of incineration satisfy the

requirements of the ADPC & E and the EPA for destruction

l6a

Appendix A

of dioxin. Regarding the ultimate decision to incinerate,

Dr. Moore testified that the state “would have looked at other

options” if there had been no dioxin in any of the drums.

J.A. at 26445. We thus reject Hercules’s argument that the

incineration of the 2,4-D drums was in no way attributable

to dioxin.

Hercules next argues that the district court clearly erred

in finding that the equipment at the plant contaminated

2,4-D waste with dioxin after Hercules had cleaned the

production vessels in 1970. The district court found that “the

cleanup of the equipment was not as thorough as portrayed

by Hercules, and that the plant equipment was cross-

contaminated with 2,4-D, 2,4,5-T, and dioxin.” Vertac XI,

364 F.Supp.2d at 952. The district court rejected Hercules’s

theory that Vertac’s chemical production: flushed the dioxin

out of the production vessels.

In its brief, Hercules recites portions of Arthur

Treisback’s affidavit, which was excluded as hearsay at trial

and is not part of the record on appeal, and relies primarily

on Treisback’s deposition testimony, portions of which were

read into evidence by Richard Karkkainen during his

testimony. Treisback was Hercules’s plant manager in charge

of the 1970 plant cleanup, and Karkkainen was Vertac’s

director of environment and safety from 1979 to 1986.

Karkkainen testified that Treisback’s deposition testimony

described the common practice of cleaning plant equipment

and, although Karkkainen had no personal knowledge of the

cleaning, that it was likely that Hercules followed the

common practice. J.A. at 26458. Karkkainen further testified

that there was no indication that the cleaning process was

successful. J.A. at 26562.

17a

Appendix A

The district court also heard the testimony of Reeddie

Ray and Stephen Quigley. Ray worked for Hercules from

1964 to 1970 and was involved in the plant cleanup. Ray

testified extensively about how the equipment was cleaned.

To clean the tanks, “[w]e washed them out with a water

hose.... Only time we heated the water if there was sediment

in the bottom of the tank.” Regarding the process lines,

“Process lines were cleaned with steam.... We had to

' disassemble the lines to get water out of the tank.” Ray did

not recall using any solvents: “The only time we used solvent

is where we wanted to take the sediment and circulate and

dissolve something in it, but I don’t think we used solvent.

I think we just used water and steam, that’s all.” J.A. at 27522-

2? Quigley, Uniroyal’s expert, testified that it was unlikely

that solvents were used to clean the equipment and even if

they were, it is likely that some contamination would remain

in the equipment. J.A. at 28089-90. Given the evidence before

the district court, we conclude that it did not err in finding

that dioxin remained in the plant after Hercules’s 1970

cleaning.

Hercules contends that the district court clearly erred in

rejecting its flushing theory. According to this theory, after

Vertac shifted plant production exclusively to products that

do not generate dioxin, about ten production runs would have

flushed out any significant amount of dioxin remaining in

the plant equipment. Because Vertac stopped producing

2,4,5-T in March 1979, three years after Hercules sold the

plant to Vertac, Hercules argued that there could be no

detectable dioxin in the 2,4-D waste in late 1979, when Vertac

began to accumulate the 2,4-D waste drums. The district court

disregarded the flushing theory as, “just that-a theory” and

18a

Appendix A

noted that “[a]fter nearly eight years of only 2,4-D production,

dioxin and 2,4,5-T were present in plant equipment.”

Vertac XII, 364 F.Supp.2d at 952.

We conclude that the district court did not err in rejecting

Hercules’s flushing theory.’ The district court stated that,

because the plant equipment contained dioxin and 2,4,5-T

after nearly eight years of 2,4-D production, “the evidence

basically disproves the theory.” The finding that dioxin was

present in the plant equipment is supported by the evidence.

An EPA inventory of the process vessels and tanks in the

central process area of the Jacksonville site showed that 140

of the 213 process vessels contained chemical material

including 2,4-D, 2,4,5-T, and dioxin. J.A. at 19779-80. Of

the ninety-six vessels sampled, more than half were

contaminated with dioxin at levels greater than 0.3 ppb. J.A.

at 19780. Hercules argues that the data showing

contamination of the plant equipment was untrustworthy, but

Hercules has failed to show that the EPA or the district court

relied on that evidence. Hercules’s expert witness, Randal

Maud, Ph.D., served as the project manager for Hercules at

the Jacksonville site to assess the environmental

consequences of the site. He testified that the unreliable data,

“would likely not be used because of the quality assurance

problems.” J.A. at 28256.

Finally, with regard to the drummed waste, Hercules

argues that the district court erred in holding Hercules liable

7. Hercules argues that the government’s attorncy made a

judicial admission supporting Hercules’s flushing theory. Having

reviewed the record, we conclude that the statements in question

did not rise to the level of a binding judicial admission.

19a

Appendix A

for the waste that was placed in the drums during

overpacking. Hercules contends that either the placement of

the dioxin-contaminated soil into the 2,4-D drums constituted

a second disposal under CERCLA, for which it is not liable,

or that the overpacking by Vertac or the EPA constituted a

superseding cause, thereby relieving Hercules of liability.

Hercules does not dispute, however, that it contaminated the

soil with dioxin at the Jacksonville site.

As the district court recited in its decision, disposal under

CERCLA is defined as the “discharge, deposit, injection,

dumping, spilling, leaking, or placing of any solid waste or

hazardous waste into or on any land or water so that such

. waste ... may enter the environment.” 42 U.S.C.

8§ 6903(3), 9601(29). Hercules caused dioxin to enter the

environment, thereby disposing of the waste. That Vertac and

the EPA overpacked leaking drums in an effort to contain

the further contamination of the site does not absolve

Hercules of CERCLA liability. Accordingly, Hercules

remains responsible for the ongoing contamination caused

by the dioxin, for that contamination was not solely caused

by the act of a third party.

C. Stillbottoms

Hercules argues that the stillbottom waste was not

disposed of until after Hercules sold the plant and that thus

it is not responsible for any of the costs related to that

disposal. Vertac began accumulating 2,4,5-T stillbottom

drums on-site in 1975, and it bought the plant from Hercules

in 1976. Hercules claims that Vertac merely stored the waste

for the purpose of later recycling, and thus did not dispose

20a

Appendix A

of the waste until 1979, when the registration for 2,4,5-T

was suspended. Accordingly, Hercules claims that the 2,4,5-

T stillbottom drums constituted a distinct harm and that it

should not be liable for their incineration.

Section 103(a) of CERCLA holds liable “any person who

at the time of disposal of any hazardous substance owned or

operated any facility at which such hazardous substances

were disposed of.” 42 U.S.C. § 9607(a)(2). The term

“facility” includes, “any site or area where a hazardous

substance has been deposited, stored, disposed of, or placed.”

42 U.S.C. § 9601(9). Finally, as we recounted above, disposal

includes placing hazardous waste in a manner that allows

the waste to enter the environment. Simply stated, the district

court found that Hercules owned a facility at which hazardous

waste was allowed to enter the environment. Specifically, it

found that the stillbottoms leaked onto the ground when

Hercules owned the plant. This finding is supported by

Quigley’s expert testimony: “[W]hen the wastes

[stillbottoms] were put into drums for disposal, they were

put into recycle drums, ... and those recycle drums did leak,

some of them instantaneously upon having the waste put in

them, and other times shortly after the waste being put in

them.” J.A. at 28082. Robert Fischer, a chemist with Hercules

and Vertac, also testified that the deterioration of the T drums

was one of the major sources of dioxin contamination at the

site. J.A. at 27060. In light of this testimony, we conclude

that the district court did not clearly err in holding Hercules

liable for the incineration of the stillbottoms.

2la

Appendix A

D. Operable Unit 1

OU-1 consisted of the above-ground media, including

the process vessels (e.g. the storage tanks, chemical reaction

vessels) in the central process area. The ROD for OU-1

required that plant equipment be dismantled and salvaged to

the extent possible and that all other nonsalvageable material

be placed in an on-site landfill. Any hazardous material not

suitable for the landfill was to be incinerated. Hercules

implemented the remedy pursuant to Unilateral

Administrative Order (UAO) issued by the EPA.

Hercules argues that the district court erred in holding it

liable for the cleanup of OU-1, including the demolition,

removal, and disposal of plant buildings and equipment, and

their process waste contents. Hercules admits liability for

part of the OU-1.' It contends that it established a reasonable

basis of divisibility for further apportioning liability. Hercules

argues that the district court erred in finding (1) that the plant

buildings were demolished because they contained dioxin,

(2) that Hercules was responsible for the contamination of

the equipment, the shredded trash, and the pallets, and (3)

that the EPA’s response action was not arbitrary or capricious.

The district court found that “[t]he buildings were

demolished because the risk of collapse might cause release

and human exposure to herbicide process contamination,

including unacceptable levels of TCDD [dioxin].” We

conclude that the record adequately supports this finding.

8. Hercules accepted responsibility for the spent carbon wastes

it generated.

22a

Appendix A

Maud testified that the EPA was concerned about the

buildings because they were falling into disrepair and because

“they contained large amounts of asbestos siding and roofing

and asbestos interiors, some of which also contained dioxin

dust.” J.A. at 28265. The ROD states that in the event of a

catastrophe, “Based on the 2,3,7,8-TCDD (dioxin)

concentrations found in [OU-1], human exposure to

concentrations in excess of those considered acceptable ...

could occur.” J.A. at 19811.

Hercules further contends that the district court clearly

erred in finding that Hercules was responsible for the

contamination of the plant equipment. In his expert testimony,

Eugene Meyer, Ph.D., affirmed the statement from his 1998

affidavit that “[t]he presence of 2,3,7,8-TCDD [dioxin] was

established through samples in all of the following: surface

and subsurface materials collected from the site sewers,

distillation bottoms, waste activated carbons, leachate from

on-site buildings, trash, shredded pallets, and the sludges

generated during the treatment of waste waters.” J.A. at

27928. Although Hercules’s project manager for EPA

compliance, Douglas Keilman, opined that Hercules did not

cause the contamination, his opinion was based on the

flushing theory. For the reasons stated above, we again

conclude that the district court did not clearly err in rejecting

that theory.

The district court found that “Hercules cannot establish

that it was not the source of the contamination on the

shredded trash and pallets.” Vertac XII, 364 F.Supp.2d at 955.

The shredded trash included things like hard hats, broken

tools, and tyvex suits, and the pallets were used to store

23a

Appendix A

drummed waste at the site. Although Keilman testified that

the trash had been accumulating since 1980, there was no

evidence to show that Vertac, and not Hercules, caused the

contamination of the trash. The district court found that the

pallets were contaminated by both leaking drums and

contaminated soil. Because Hercules is responsible for the

contaminated soil, the district court did not err in further

holding it responsible for the pallets.

Finally, Hercules argues that the EPA’s issuance of a

UAO requiring Hercules to dismantle and to landfill the

equipment and buildings at the site was arbitrary and

capricious. We disagree. Section 113(j) of CERCLA allows

a defendant to avoid paying response costs to the extent that

it can show that the response action was arbitrary and

capricious. 42 U.S.C. § 9613(j). Hercules does not argue that

the disposal of the building and equipment is arbitrary and

capricious, but rather that the EPA was arbitrary and

capricious in issuing a UAO. To support the issuance of a

UAO, there must be evidence that there ‘may be an imminent

and substantial endangerment to the public health or welfare

or the environment because of an actual or threatened release

of a hazardous substance from a facility.” 42 U.S.C. § 9606(a)

(emphasis added). Because the record contains sufficient

evidence to support the EPA’s determination that the

cautionary “may be” threat of imminent substantial

endangerment had been established, its decision to issue the

UAO was not arbitrary and capricious.

24a

Appendix A

E. Jacksonville Landfill

The district court found that Hercules disposed of

hazardous wastes at the Jacksonville Landfill and held

Hercules liable for the cleanup costs associated with the

landfill. In its investigation, the EPA found rusting drums

and piles of “white fibrous, absorbent-type materials” at the

Jacksonville Landfill. Tests confirmed the presence of dioxin,

2,4,5-T, and other chemicals associated with the Jacksonville

site. In its ROD, the EPA called for the excavation of

contaminated soils, the replacement and capping of the

excavated areas with clean soil, and the cleaning and removal

of large refuse items. The contaminated soil and drums were

incinerated at the site. Although Hercules admits that it took

some nonhazardous waste to the Jacksonville Landfill, it

argues that the district court clearly erred in finding that

Hercules disposed of hazardous wastes at the Jacksonville

Landfill, and it contends that the EPA’s response was arbitrary

and capricious.

We conclude that the district court’s finding is supported

by substantial evidence. Indeed, the district court cited the

testimony by four Hercules employees that they took

chemical wastes to the Jacksonville Landfill. Billy Honey

worked maintenance at the plant from the time Hercules

bought it until it closed. J.A. at 26291. He testified that he

hauled drums filled with chemical waste to the Jacksonville

Landfill. J.A. at 26299-300. Doyce Shurley worked for

Hercules in the early 1960s, and he recalled taking a barrel

of stillbottoms to the landfill. Vincent Dodson worked for

Hercules in the late 1960s, and he testified that chemical

wastes were disposed of at the landfill. When asked what

25a

Appendix A

type of waste was taken to the Jacksonville landfill, Leroy

Jordan replied, “We took [waste] from each trash pick-up

point. We took it from every rig and barrels. We cleaned out

the incinerator and carried that stuff over there. Anything

that they needed to get rid of, and that included benzen

barrels, trash from the lunchroom, barrels of goop, acid,

anything and everything.” J.A. at 26352.

Hercules argues that this testimony should be discredited

because it presented contradictory evidence to counter it. The

short answer to this contention is to note once again that a

district court’s choice between two permissible views of the

evidence is no basis for a conclusion that its factual finding

is clearly erroneous. Tadlock, 291 F.3d at 546.

Hercules contends that the EPA’s response to the

Jacksonville landfill was inappropriate for the following

reasons: (1) the cancer potency factor used by the EPA in its

risk assessment constitutes a rule under the Administrative

Procedures Act (APA) that must be overturned because it

was not subject to notice and comment, and (2) the EPA’s

exposure assumptions were arbitrary and capricious.

We disagree.

The cancer potency factor was used to calculate the risk

and to set dioxin cleanup standards for the soil and sediments

at the Jacksonville site. To determine whether a statement

by an agency is a legislative rule or policy, we apply the

two-part test of McLouth Steel Prod. Corp. v. Thomas, 838

F.2d 1317, 1320 (D.C.Cir.1988). A policy statement (1) does

not have a binding effect; it does not impose any rights and

obligation; and (2) a policy “genuinely leaves the agency and

26a

Appendix A

its decisionmakers free to exercise discretion.” /d. (internal

quotations omitted). The district court concluded that the

“Health Assessment Document which set forth the cancer

potency factor does not impose any rights [or] obligations.

It is at most only a technical and advisory report. It did not

obligate the agency or public in determining acceptable risks

associated with dioxin.” United States v. Vertac Chem. Corp.,

33 F.Supp.2d 769, 779 (E.D.Ark.1998) (Vertac IX ).

This finding is adequately supported by the record. As

the district court noted, the EPA Regional Administrator

considered the lower figure proposed by Hercules’s

contractor, ChemRisk, and rejected it. Indeed, in the ROD

for the Jacksonville landfill, the EPA addressed why

ChemRisk’s calculations would not be used, “Hercules Inc.

submitted a report prepared by ChemRisk which provided

calculations resulting in cleanup goals differing from EPA’s

for dioxin. The report utilized certain calculations and

assumptions which were contrary to EPA guidance and

resulted in cleanup goals much less restrictive than those

calculated by the EPA.” J.A. at 16407. The document goes

on to discuss the discrepancies between the EPA’s and

ChemRisk’s methods of calculating site related risks and to

explain that the EPA rejected ChemRisks proposal because

“ChemRisk’s proposed cleanup goals, using EPA’s risk

assessment approach, would not result in excess cancer risks

(after remediation) within the acceptable risk range.” J.A. at

16408. The EPA considered Hercules’s comments on the

EPA’s application of the cancer potency factor with regard

to the cleanup levels at the site and responded to the

comments in the final RODs.

27a

Appendix A

Hercules argues that the exposure assessments used by

the EPA were arbitrary and capricious and did not justify the

remedial order. Having considered the ROD and related

evidence, we conclude that this argument is without merit.

F. Soils and Groundwater

The revised ROD for Operable Unit 2 (OU-2) addressed

contaminated on-site soils, foundations, and underground

utilities and off-site soils and sediments that had been

excavated from off-site areas and stored on the site. The

remedy selected required the excavation of dioxin

contaminated soil, and the disposal of this soil in an on-site

containment vault. The ROD for Operable Unit 3 (OU-3)

dealt with groundwater contamination under the site. It states

that “groundwater contamination at the site is complex,

resulting from past waste management and disposal practices.

Sources of contamination include on-site landfills, spills and

discharges into the central ditch, Reasor Hill well, and other

parts of the central process area.” J.A. at 20136.

Hercules argues that the soil and groundwater

contamination were divisible as successive harms based on

the relative production volumes of 2,4,5-T and 2,4,5-TP

attributable to Hercules from 1961 until it sold the plant in

1976 and to Vertac from that point until it ceased production

of 2,4,5-T in 1979. Based on the estimated production figures,

Keilman determined that Hercules was responsible for

70.74% of the EPA’s response costs. J.A. at 27177. To reach

this figure, Hercules relied on the following assumptions and

evidence: (1) Hercules assumed that leaks and spills took

place at roughly the same frequency and severity during the

28a

Appendix A

plant’s production of 2,4,5-T and 2,4,5-TP; (2) Keilman

testified that prior to 1965, most of the dioxin left the plant

with the product; (3) Hercules offered evidence that the half-

life of dioxin in soil is approximately twelve years, though

it ranged from a few days to decades; and (4) Hercules touted

its housekeeping and maintenance practices as being far

superior to those of Vertac.

The district court determined that this evidence was not

sufficiently concrete and specific to apportion the harm. Most

importantly, there was no evidentiary basis for Hercules’s

assumption that the release of wastes at the site was related

to production volumes, nor was there any testimony that there

was any reasonably constant ratio or direct correlation

between the releases of dioxin and production of dioxin

generating products. As the district court pointed out and as

the record reveals, the production methods changed over the

years, the specifications for the product varied, Hercules and

Vertac used different methods of disposal of dioxin

contaminated filter paper and cardboard drums, and each

companies experienced different plant eruptions. Although

Hercules may be able to fairly estimate the production

volumes of 2,4,5-T and 2,4,5-TP from the time it owned the

plant, the district court correctly held that it cannot establish

the inferences necessary to prove a reasonable basis for

apportionment of harm.

Hercules argues that the EPA’s response choices for the

soils, groundwater, and off-site areas are arbitrary and

capricious and that Hercules should not be held liable for

the corresponding response costs. Having considered the

record, we conclude that Hercules’s argument is without

merit.

29a

Appendix A

III. UNIROYAL’S LIABILITY

Uniroyal argues that we should hold that it is not liable

as an arranger under CERCLA, and thus overturn the panel’s

decision in Vertac XI. ““When a case has been decided by

this court on appeal and remanded to the district court, every

question which was before this court and disposed of by its

decree is finally settled and determined.” Klein v. Arkoma

Prod. Co., 73 F.3d 779, 784 (8th Cir.1996). Absent

intervening controlling authority, we are bound by the

decision of the previous panel. Liberty Mut. Ins. Co. v. Elgin

Warehouse & Equip., 4 F.3d 567, 571 (8th Cir. 1993). Uniroyal

pointed to no new controlling authority, and thus the

affirmance of the district court’s finding of liability in Vertac

XI is the law of the case. Because that holding is not “clearly

erroneous” nor does letting it stand “work a manifest

injustice,” we refuse to disturb it. Liberty Mut. Ins. Co., 4

F.3d at 570-71.

IV. RETROACTIVITY

Hercules and Uniroyal contend that the retroactive

application of CERCLA to impose liability is unconstitutional

under the Supreme Court’s decision in Eastern Enterprises

v. Apfel, 524 U.S. 498, 118 S.Ct. 2131, 141 L.Ed.2d 451

(1998). We previously resolved this exact issue in United

States v. Dico, in which we held that CERCLA’s retroactive

application remained constitutional after Eastern Enterprises.

Dico, 266 F.3d 864, 879-880 (8th Cir.2001). We are thus

bound by our Circuit’s precedent and accordingly will not

revisit the issue. See United States v. Wright, 22 F.3d 787,

30a

Appendix A

788 (8th Cir.1994) (“[A] panel of this Court is bound by a

prior Eighth Circuit decision unless that case is overruled

by the Court sitting en banc.”).

V. CONCLUSION

The judgment is affirmed.

3la

APPENDIX B — OPINION OF THE UNITED STATES

DISTRICT COURT FOR THE EASTERN DISTRICT

OF ARKANSAS, WESTERN DIVISION

DATED MARCH 30, 2005

UNITED STATES DISTRICT COURT

E.D. ARKANSAS

WESTERN DIVISION

No. CIV. 4:80CV00109GH

UNITED STATES OF AMERICA,

Plaintiff,

V.

VERTAC CHEMICAL CORP., et al.,

Defendants.

March 30, 2005.

MEMORANDUM OPINION AND ORDER

GEORGE HOWARD, JR., District Judge.

The Vertac Site in Jacksonville, Arkansas, has been the

focus of litigation for 25 years. The history of the Vertac

Site and Off-Site areas has been discussed in numerous prior

decisions.' This Court previously found both Hercules

1. United Sates vy. Vertac Chem. Corp., 489 F.Supp. 870

(E.D.Ark.1980); United States v. Vertac Chem. Corp., 588 F.Supp.

1294 (E.D.Ark.1984); United States v. Vertac Chem. Corp., 671

(Cont'd)

32a

Appendix B

Incorporated (“Hercules”) and Uniroyal Chemical Limited

(“Uniroyal”)? jointly and severally liable under the

Comprehensive Environmental Response, Compensation

and Liability Act of 1980 (“CERCLA”), 42 U.S.C. §§ 9601

et seq. for all response costs incurred and to be incurred by

the United States at the Site and related areas, and entered

judgment in the amount of $102,878,641.35. United States

v. Vertac, 33 F.Supp.2d 769 (E.D.Ark.1998). In what was

hoped to be the last decision in this matter, the Court allocated

the costs between Hercules and Uniroyal. United States v.

Vertac, 79 F.Supp.2d 1034 (E.D.Ark.1999).

GENESIS OF THIS DECISION

On October 12, 1993, the Court granted the United

States’ motion for summary judgment and found that

Hercules was jointly and severally liable under Section

107(a)(2) and (3) of CERCLA, 42 U.S.C. § 9607(a)(2) and

(3) for the response costs incurred by the United States with

regard to the Vertac Site. Hercules moved for reconsideration,

(Cont'd)

F.Supp. 595 (E.D.Ark.1987), vacated, 855 F.2d 856 (8th Cir. 1988);

United States v. Vertac Chem. Corp., 756 F.Supp. 1215

(E.D.Ark.1991), aff’d, 961 F.2d 796 (8th Cir. 1992); United States v.

Vertac Chem. Corp., 966 F.Supp. 1491 (E.D.Ark.1997); United States

v. Vertac Chem. Corp., 33 F.Supp.2d 769 (E.D.Ark.1998); United

States v. Vertac Chem. Corp., 79 F.Supp.2d 1034 (E.D.Ark.1999).

See also O'Dell v. Hercules, Inc., 687 F.Supp. 450

(E.D.Ark.1988)(O ’Dell-Bridges), aff'd 904 F.2d 1194 (8th Cir.1990).

2. As of January 30, 2001, the name of Uniroyal Chemical

Limited was changed to Crompton Co./Cie. For ease and consistency,

the Court will continue to use the name Uniroyal.

33a

Appendix B

at which time it argued that disputed issues of fact existed

regarding divisibility. The Court, on November 1, 1993,

denied the motion for reconsideration, finding, inter alia,

that Hercules had failed to present evidence in support of its

divisibility of harm argument.

On December 19, 1999, Hercules appealed the Court's

summary judgment ruling, arguing in part that the harm at

the Site is divisible. On April 11, 2001, the Eighth Circuit

Court of Appeals reversed the Court’s summary judgment

against Hercules on the issue of liability and remanded the

case for the Court to “address evidence supporting divisibility

in light of the proper legal standards.” United States v.

Hercules, Inc., 247 F.3d 706, 719 (8th Cir.2001). The Eighth

3. The Eighth Circuit’s decision is somewhat confusing. The

court stated that it was vacating United States v. Vertac Chem. Corp.,

841 F.Supp. 884 (E.D.Ark.1993) (“Vertac V”). Vertac V however

dealt only with the liability of the United States. In that case, Vertac,

Hercules and the State of Arkansas argued that the United States

should be held liable under CERCLA for its role in the production

of Agent Orange. The United States filed a motion for partial

summary judgment asking that the Court find that it is not liable.

fhe Court found the United States not to be liable, denying the

motions of Vertac, the State of Arkansas, and Hercules and granting

the motion of the United States.

The Eighth Circuit Court of Appeals affirmed the Court’s

conclusion that the United States was not liable as an “operator” or

“arranger” in United States v. Vertac Chem. Corp., 46 F.3d 803 (8th

Cir.1995) (‘Vertac VI’).

(Cont'd)

34a

Appendix B

Circuit also vacated the Court’s judgments on response costs,

United States v. Vertac Chem. Corp., 33 F.Supp.2d 769

(E.D.Ark.1998) (“Vertac IX’’) and allocation, United States v.

Vertac Chem. Corp., 79 F.Supp.2d 1034 (E.D.Ark.1999)

(“Vertac X”) pending the Court’s reconsideration of Hercules’

claim of divisibility. 247 F.3d at 721.

The Court scheduled a limited evidentiary hearing on the

divisibility of harm defense raised by Hercules. The hearing

was held between October 9 and 19, 2001 and December 11

and 12, 2001. The parties subsequently filed post-hearing briefs.

The record, needless to say, is voluminous, comprising not only

the numerous filed documents, but exhibits and transcripts

admitted at the evidentiary hearing, exhibits and transcripts of

the various trials in this action, evidentiary and deposition

testimony of other federal actions involving Hercules, and the

(Cont'd)

Vertac V did not grant summary judgment on the United States’

motion for summary judgment against Hercules on the issue of

liability and did not address Hercules’ argument concerning

divisibility of harm. The finding of joint and several liability of

Hercules was issued in an unpublished decision entered on October

12, 1993. (document no. 1826) (granting United States’ motion for

partial summary judgment against Hercules on the issue of liability

under CERCLA). The subsequent order denying Hercules’ motion

for reconsideration on the issue of divisibility, also unpublished,

was entered on November |, 1993 (document no. 1875)(denying

Hercules’ motion for reconsideration of October 12, 1993 Order).

Should the Eighth Circuit again address this case, it might want

to clarify the record. It is unclear whether the Court’s decision in

841 F.Supp. 884 and affirmed in 46 F.3d 803 concerning the United

States’ liability should have been vacated.

35a.

Appendix B

52,000-page Administrative Record (AR) for the Site which

has been filed in this action as 8 compact discs (see docket

entry 2454). The Court has worked diligently to carefully review

the record in considering this case.

FACTUAL BACKGROUND

The Vertac Chemical Plant Site (“Site”) consists of

approximately 93 acres in Jacksonville, Arkansas. The Site was

originally developed by the federal government in the 1930s as

a munitions factory. Around 1948, Reasor-Hill Corporation

(“Reasor-Hill”), a now defunct company, purchased the Site

and first formulated finished insecticide products, primarily

DDT, aldrin, dieldrin, and toxaphene. In the mid-1950s, Reasor-

Hill modified the plant and began manufacturing phenoxy

herbicides, primarily 2,4, dichlorophenoxyacetic acid (“2,4-D”),

2,4,5 trichlorophenoxyacetic acid (“2,4,5-T”) and 2,4, 5

trichloropropionic acid (“2,4,5-TP” or “Silvex”). United States

v. Vertac Chem. Corp., 489 F.Supp. 870, 873 (E.D.Ark.1980)

(“Vertac I’). The chlorinated compound 2,4,5-trichlorophenol

(2,4,5-TCP or TCP) was an intermediate in the 2,4,5-T

manufacturing process. The manufacture of 2,4,5-T creates a

highly toxic byproduct, 2,3,7,8-tetrachlorodibenzo-p-dioxin

(“dioxin” or “TCDD”) that is now viewed as hazardous to

humans. Vertac XI] at 712. All of the herbicide related compounds

are listed hazardous wastes under the Resource Conservation

and Recovery Act (RCRA), 42 U.S.C. § 6921, 40 C.F.R.

§§ 261.31, 261.33, and the compounds 2,4,5-T, 2,4,5-TCP, 2,4,5-

TP are designated as “Acute Hazardous Wastes” under RCRA.

40 C.F.R. § 261.31. Additionally, all of the phenoxy herbicides

and TCP are designated as hazardous substances under

CERCLA. See 42 U.S.C. 9601(14); 40 C.F. R § 302.4.

36a

Appendix B

Reasor-Hill did not have a process to treat the waste

water that was produced. United States v. Vertac Chem. Corp.,

966 F.Supp. 1491, 1494 (E.D.Ark.1997) (“Vertac VIII”).

While Reasor-Hill operated the Site, an unknown quantity

of untreated chemical wastes from the production process

flowed through cooling ponds on the west side of the plant

into a nearby stream. Reasor-Hill disposed of large quantities

of pesticide (insecticide) and phenoxy herbicide wastes by

leaving the wastes in drums on the Site. Vertac Jat 874.

Hercules bought the Site from Reasor-Hill in 1961 and

continued to manufacture herbicides, including 2,4-D and

2,4,5-T, at the plant until 1971. United States v. Hercules,

247 F.3d 706, 712 (8th Cir.2001)(“Vertac XI’). When it

commenced operations at the Plant, Hercules found and then

buried on-site thousands of drums of pesticide and herbicide

wastes left by Reasor-Hill. Vertac VIII at 1494-95. The

southeast corner of the Site where Hercules buried the drums

was known as the Reasor-Hill drum burial area.

Hazardous substances, including insecticides, phenoxy

herbicides and TCDD dioxin, Jeached and flowed from the

Reasor-Hill drum burial area into Rocky Branch Creek.

Until late 1964, Hercules continued Reasor-Hill’s

practice of discharging untreated wastewater directly into

Rocky Branch Creek. Vertac / at 874. The waste water which

resulted from the manufacturing of 2,4,5-T or 2,4,5-TP

contained dioxin. Jd. In 1964, Hercules constructed a waste

water pretreatment system, which consisted of a

neutralization trench designed to reduce the acidity of the

water, an equalization basin designed to stabilize the rate of

37a

Apoendix B

flow into the City of Jacksonville’s sewage system, and a

pump and pipe to deliver the treated waste water to the

Jacksonville sewage system. Jd. The waste water pretreatment

system did not remove the dioxin. The basin frequently

overflowed directly into Rocky Branch Creek during heavy

rainfalls, and leaked.

Hercules manufactured formulations of 2,4,5-T, Silvex

and 2.4.-D acids for commercial customers. It used some of

the same equipment to manufacture both 2,4-D and 2,4,5-T

products, but the equipment could not manufacture both

simultaneously.

In 1964, Hercules was awarded a contract to produce

Agent Orange for the U.S. Department of Defense (“DOD").*

It produced and supplied Agent Orange to DOD through

1968. Agent Orange was a 50/50 mixture of the butyl esters

of 2,4,5-T and 2,4,-D acids; a much more concentrated form

of the acids than that sold by Hercules to its commercial

customers. Dioxin was formed as a by-product during the

production of Agent Orange. Vertac VIII at 1494. Due to strict

specifications in the Agent Orange contracts, Hercules was

forced to discard as waste more significant quantities of

material that did not meet specifications than was discarded

during production for commercial customers. At the same

time, Hercules continued manufacturing 2,4,5-T, silvex and

2.4-D for its commercial customers. As a result of the

increased production, the volume of wastes generated at the

Plant also increased.

4. Agent Orange was an herbicide used as a defoliant in

Vietnam. United States v. Vertac Chem. Corp., 46 F.3d 803, 805 (8th

Cir. 1995).

38a

Appendix B

In 1965, Hercules discovered that in the manufacture of

2,4,5-T, dioxin was generated in the process, specifically in

the dechlorinator, also known as the “sputnik.”° In that same

year, it began utilizing a “toluene extraction” system during

which dioxin and other impurities that were extracted

underwent a distillation process producing a residue

(stillbottoms). The toluene stillbottoms were contaminated

with TCDD and 2,3,7,8-tetrachloro-dibenzo-furan (TCDF).

Hercules buried drums of toluene stillbottoms and 2,4-D

wastes at the Site and disposed of them in the landfill areas.

Vertac VIII, at 1494. See also Vertac I at 875.

The drums were allowed to collect in the process areas,

sometimes for several months, before being transported to

the drum burial pit. The drums were thin gauge and were in

poor condition. Leakage occurred at the point of storage and

in transporting the drums to the drum burial area. Hercules’

practice was to scoop up any contaminated soil around the

leaking drum and place it into the drum.

Between June of 1964 and May of 1968, Hercules

produced almost 3 million gallons of undiluted Agent Orange

for DOD.

After the Agent Orange contracts terminated in 1968,

Hercules continued manufacturing 2,4,5-T, silvex and 2,4-

D for commercial customers until June 1970. Vertac VIII at

1495-96. In late 1970, Hercules ceased production at the Site

5. Tr.2001 at 877. The dechlorinator is the vessel in which

dioxin in formed during the process of making trichlorophenol.

Hercules later increased the number of “sputniks” from one to three.

39a

Appendix B

and cleaned it or “mothballed” it for the winter as Hercules

began to seek a buyer or lessee of the Plant.

On October 1, 1971, Hercules leased the Site to

Transvaal, Inc. (“Transvaal”) which later became Vertac

Chemical Corporation (“Vertac”). Among the actions

Transvaal took prior to starting operations was the

redrumming of about 50 to 100 55-gallon drums of 2,4,5-T

wastes, some of which were leaking.’ Transvaal continued

to manufacture 2,4,-D, 2,4,5-T and 2,4,5-TP and continued

to bury wastes on site. In 1975, Transvaal began shipping its

2,4-D waste to off-site landfills and began to store its 2,4,5-

T stillbottoms above ground with the hope of recycling the

waste. Vertac XI at 712. All waste burial took place while

Hercules owned the plant.

In August of 1976, Transvaal purchased the Site from

Hercules and reorganized as Vertac. Vertac continued to make

2.4-D, 2,4,5-T and 2,4,5-TP. Vertac J at 874. Vertac continued

its operations until 1986, when it abandoned the Site

altogether.

On February 28, 1979, the Environmental Protection

Agency (“EPA”) suspended many of the uses of 2,4,5-T.

Vertac I at 875. On March 15, 1979, Vertac voluntarily ceased

6. The extent of Hercules’ cleanup of the plant is in dispute

and is discussed below.

7. December 12, 1988 Deposition of Jerry Keister, p. 6-7

8. The drums of the toluenc stillbottoms were still on-site when

the State of Arkansas ordered them to be redrummed. 2001 Tr. at

734.

40a

Appendix B

manufacturing 2,4,5-T and 2,4,5-TP and overpacked its 2,4,5-

T stillbottom drums. /d.’

In 1980, Vertac recommenced the manufacture of 2,4-

D. It began redrumming, or overpacking, leaking drums that

it had accumulated on site.'° Spilled material along with dirt,

dust, and debris were scooped up and placed into the

overpacking drums.

EPA found that the 2,4-D wastes had been contaminated

with TCDD. On February 26, 1980, EPA issued a proposed

rule under the Toxic Substances Control Act (“TCSA”) to

prevent Vertac from disposing of TCDD wastes from the Site.

The rule, known as the “Vertac Rule,” became effective

March 11, 1980'' and final May 19, 1980.

The Vertac Rule prohibited the off-site shipment of 2,4,-

D wastes which contained TCDD.'? However, if Vertac could

show that a batch of 2,4-D was manufactured and produced

wastes free of dioxins, it could ship those wastes and all

subsequent wastes for off-site disposal unless it went back

to manufacturing 2,4,5-T. Vertac IX at 780.

According to testimony at the hearing on the proposed

rule, Vertac had approximately 3200 drums of wastes

9. The recontainerization was pursuant to a June 15, 1979 Order

by the Arkansas Department of Pollution Control and Ecology

(“ADPC & E”). Vertac I at 875-876.

10. 2001 Tr. at 354

11. 45 Fed.Reg. 15592

12. Id.

4la

Appendix B

resulting from the production of 2,4,-D. Analysis by Vertac

of three samples from 700 drums of wastes resulting from

the initial production of 2,4-D revealed TCDD levels of

approximately twenty parts per billion (“ppb”).'* Vertac then

sent samples of its 2,4-D wastes to Wright State University

and to Monsanto for testing. Monsanto was unable to detect

TCDD with its analytical equipment, but Wright State

detected TCDD in composite samples taken from 700 drums

of “D” wastes of .7 ppb 2,3,7,9-TCDD.'* Vertac IX at 780. It

subsequently found .5 ppb in another sampling of 1000 drums

and a third sampling done on an undisclosed number of drums

found .3ppb TCDD.'°

Finding that dioxin was present in the 2.4-D wastes,

Vertac stopped sampling and allowed the “D” wastes to

accumulate. Subsequent testing by the State of Arkansas as

well as the results of trial burns revealed the presence of

TCDDs and TCDFs in the drums. Vertac IX at 781.'° Both

TCDD and TCDF were generated exclusively in the

manufacture of 2,4,5-T and 2,4,5-TP, but not in the

manufacture of 2,4-D.

Sed

13. 45 Fed.Reg. 22678

14. Hercules contends that the Monsanto results of non-detect

were more reliable thas the Wright State University results, although

Hercules’ witness Robert Fisher acknowledged that Wright State had

a high resolution mass spectrometer which Monsanto did not have.

15. 2001 Tr. at 1647.

16. See also e.g., 2001 Tr. at 1665-1678 discussing results

obtained in 1993 by Richard Ehrhart, EPA Remedial Project Manager

for the incineration project of about 400 drums of 2,4-D wastes.

42a

Appendix B

The 2,4-D waste drums, because of the acidic nature of

their contents and their condition resulting from their storage

and handling, failed at a rapid rate. Beside being stored on

soil, the drums were also stacked several deep, three high,

and unbanded, by the thousands.

Vertac ceased operations in 1986 and abandoned the Site

in 1987. Vertac VIII at 1495.'’ When Vertac abandoned the

Site in January of 1987, there were nearly 29,000 drums

containing waste materials, including 2,4,5-T, 2,4,-D and

dioxin. “Many of these drums had corroded and leaked,

contaminating more soil, groundwater, and buildings at the

site.” Vertac XI at 712. Over 15,000 drums stored outside

were exposed to the elements. “Drums were stacked three

high on deteriorating pallets.” Vertac IX at 772. The drums

were failing at a rate of between five to 300 per week.'®

“EPA determined that the wastes on the site posed a threat

to public health and welfare and the environment. Residents

in the area could be exposed to hazardous substances and

should a large release occur, in the event of a tornado, fire,

or continued poor maintenance, the toxic waste could

contaminate the environment. EPA initiated a removal action

in 1987 to stabilize the drums and tanks and to provide site

security.” Vertac IX at 772.

17. See also United States v. Vertac Chem. Corp., 671 F.Supp.

595 (E.D.Ark.1987) for a description of Vertac’s actions in 1986

and 1987. The Eighth Circuit Court of Appeals vacated the decision

because Inter-Ag, the entity who purchased Vertac’s assets, had not

been joined as a party to the action. 855 F.2d 856 (8th Cir.1988)

(Table).

18. 2001 Tr. at 1427, Ex. 8073.

43a

Appendix B

Some of the drums were labeled “T” waste, some were

labeled “D” waste, some were marked “T” and “D” and some

were not marked at all. Many of the markings were

indistinguishable or unreadable. Vertac, 671 F.Supp. at 606.

“The drummed material was considered acutely

hazardous waste and was characterized as ‘F-listed’ wasted

under applicable ... RCRA regulations, 42 C.F.R. Part 261,

App. VII.” Vertac IX at 772. EPA chose to dispose of the

wastes by incineration. When the incineration of the drums

commenced, the contents of the drums were found to nave

different wastes including 2,4,-D, 2,4,5-T, 2,4,5-TP, dioxins,

dibenzofurans, and all sorts of various materials ranging from

dirt to broken pipes. EPA completed the on-site incineration

of the 2,4-D drummed waste in October, 1994. The remaining

3260 drums of 2,4,5-T wastes were shipped off-site for

incineration. Off-site shipment was completed in March,

1996. Vertac IX at 774.

SCOPE OF REVIEW

Hercules argues that in its latest order the court of appeals

vacated all previous findings of fact of this Court. That is,

the Court is now free to consider new evidence and new facts.

Hercules basically contends that the only evidence the Court

may now consider is that which was introduced at the hearing

on divisibility of harm that the Court conducted in 2001.

The Court ordered a hearing to consider additional

evidence on the issue of divisibility of harm. The Court finds

that it can consider the existing record. The Eighth Circuit

merely remanded the case for the Court to determine, based

44a

Appendix B

on the record, whether Hercules had established a basis for

establishing divisibility of harm. The Court of Appeals did not

remand for a new tnial.

The United States has already established, and the Court

has previously found, that there were releases and threats of

releases of hazardous substances during the time Hercules

owned or operated the Site, which caused the United States to

incur response costs. This is sufficient to establish Hercules’

liability under CERCLA for response costs. However, it does

not resolve the issue of liability completely. Hercules can “escape

joint and several liability” if it can demonstrate that the harm

incurred at the Site is divisible. United States v. Alcan Aluminum

Corp., 315 F.3d 179, 185 (2d Cir.2003).

The universal starting point for divisibility of harm

analyses in CERCLA cases is the Restatement

(Second) of Torts, which provides for the

apportionment of damages among two or more

parties when at least one is able to show either

(1) “distinct harms” or (2) a “reasonable basis for

determining the contribution of each cause to a single

harm.” Restatement (Second) of Torts § 433A

(1965).

Vertac XI, at 717.

Section 433A of the Restatement (Second) of Torts entitled

“Apportionment of Harm to Causes,” provides as follows:

(1) Damages for harm are to be apportioned

among two or more causes where

45a

Appendix B

(a) there are distinct harms, or

(b) there is a reasonable basis for

determining the contribution of each

cause to a single harm.

In other words, the defendant must prove that “there is a

way to determine what portion of the harm (i.e. the hazardous

substances present at the facility and the response costs

incurred in dealing with them) is fairly attributable to the

defendant as opposed to other responsible parties.” United

States vy. Manzo, 279 F.Supp.2d 558, 562 (D.N.J.2003)

(quoting United States v. Rohm & Haas Co., 2 F.3d 1265,

1280 (3d Cir.1993)). “ ‘Distinct harms’ are ‘those that may

properly be regarded as separate injuries.’ ” Vertac X/ at 717.

The burden is on Hercules to establish that there is a

reasonable basis for divisibility of harm. That burden is

substantial. United States v. Alcan Aluminum Corp., 315 F.3d

179, 185 (2d Cir.2003). The evidence in support of

divisibility “must be concrete and specific.” Vertac X/ at 718.

“{T]he question whether there is a reasonable basis for

apportionment depends on whether there is sufficient

evidence from which the court can determine the amount of

harm caused by each defendant.” In the Matter of Bell

Petroleum Svcs., Inc., 3 F.3d 889, 903 (Sth Cir.1993)(Bell

Petroleum). “(Where causation is unclear, divisibility is not

an opportunity for courts to ‘split the differetice’ in an attempt

to achieve equity.” /d. A court should not settle on a

compromise amount that it believes approximates the relative

responsibility of the parties. If in doubt, the court should

impose joint and several liability. United States v. Township

of Brighton, 153 F.3d 307, 319 (6th Cir.1998).

46a

Appendix B

ANALYSIS

Hercules advances several arguments in support of its

divisibility defense. It advances a type of “geographical

apportionment” theory, that is, that the harm at the Site is

divisible on the basis of operable units.'? Each operable unit

should be considered, according to Hercules, a separate

“site.” As to these different areas, Hercules argues that it is

liable only for the harm that it caused. Different approaches

are used, depending on the area. Thus, with regard to the

incineration of the drummed wastes, Operable Unit 1 (plant

equipment) (“OU-1”) and the Jacksonville and Rogers Road

landfills, Hercules contends that it has no liability. As to the

remaining sites, Hercules admits that it has some

responsibility for contamination of on site soils and

groundwater and the Off-Site Areas. It argues, however, that

the Court should apply a volumetrics approach for dividing

the harm.

19. Operable unit means a discrete action that comprises

an incremental step toward comprehensively

addressing site problems. This discrete portion of a

remedial response manages migration, or eliminates

or mitigates a release, threat of a release, or pathway

of exposure. The cleanup of a site can be divided

into a number of operable units, depending on the

complexity of the problems associated with the site.

Operable units may address geographical portions

of a site, specific site problems, or initial phases of

an action, or may consist of any set of actions

performed over time or any actions that are

concurrent but located in different parts of a site.

40 C.F.R. § 300.5.

47a

Appendix B

EPA and Uniroyal assert that Hercules cannot establish

that the harm is divisible because of the extensive cross-

contamination and commingling of dioxin and other

hazardous substances throughout all areas of the Site. They

note that Hercules’ operations and extensive waste disposals

at the Plant and on other areas of the Site from 1961 to 1971

contributed massive amounts of dioxin and other hazardous

substances to the Site. Furthermore, Hercules also owned

the Plant during the first five years of Transvaal/Vertac’s

operations there, and it is therefore legally responsible under

CERCLA for Vertac’s waste disposals during the period from

1971-1976.

The EPA divided the Site into separate operable units

for purposes of facilitating the remediation. The attempt to

apportion the harm based on operable units was rejected by

the court in United States v. Manzo, 279 F.Supp.2d 558, 574

(D.N.J.2003). “An operable unit is ‘a discrete action that

comprises an incremental step toward comprehensively

addressing site problems.’ 40 C.F.R. § 300.5. It is not a site,

although it ‘may address geographical portions of a site.’ “

Furthermore, in Manzo as here, the operable units did not

solely address geographical portions of the Site.*°

20. Randal Maud, Hercules’ cxpert in environmental

remediation and Project Manager at the Site, testified that the Site

was divided into “logical areas of study.” At first Operable Unit |

was all engineering structures above the land surface and Operable

Unit 2 was everything at land surface and below. Ground water was

spun off into a separate operable unit for administrative purposes

2001 Tr. at 2068-69.

48a

Appendix B

The Court is not persuaded that EPA’s selection

of remedial actions alone is a basis for dividing the harm.

See Washington v. United States, 922 F.Supp. 421, 428

(W.D.Wash.1996)(EPA’s selection of remedial actions

provides no basis for apportioning harm).

The Court will proceed to address the arguments raised

by Hercules, and determine whether there is a basis to divide

the harm in each of the areas.

Drummed Wastes

As discussed above, when EPA arrived at the Site after

Vertac abandoned in it found over 28,000 drums of waste

stored on the Site. The drummed wastes were incinerated as

part of a series of continuing removal actions that the State

of Arkansas and the EPA began in 1987.

There is no dispute that the 2,4-D waste drums were

accumulated on the Site beginning in late 1979, at least three

years after Hercules had sold the plant site to Vertac. Had

the drums merely contained identifiable 2,4-D wastes, the

Court might find that Hercules’ divisibility of harm argument

had merit. But, because they contained other hazardous

substances which were produced while Hercules owned the

plant, Hercules must demonstrate a basis for finding the harm

divisible.

Hercules makes several arguments to support its

contention that it is not liable for the incineration of the

drummed wastes. It has consistently contended that

the approximately 25,000 drums of 2,4-D waste and

49a

Appendix B

approximately 3,000 drums of 2,4,5-T still bottoms left

behind when Vertac abandoned the Site on January 31, 1987,

were each “distinct” harms, to which Hercules did not cause

EPA’s response costs.

Dioxin was found in the drums. The United States posits

two sources of contamination of the 2,4-D drums with TCDD,

TCDF,2,4,5-T and 2,4,5-TP One is the cross-contamination

from the equipment, especially equipment used in both the

production of 2,4-D and 2,4,5-T. The second source is the

contaminated soil, trash, debris and other materials placed

into the drums during the multiple overpackings. The soil

could have been contaminated with dioxin produced during

Hercules’ operation of the plant. No one can say that the

dioxin in the “D” drums did not come from Hercules.

Despite Hercules’ contention that the drums didn’t leak,

there is ample evidence to show that the drums of 2,4,5-T

still bottoms did leak on the ground when Hercules owned

the plant?! The on-site soils, especially, in the process area,

contained hazardous chemicals.*?

The soil was contaminated with wastes generated by

Hercules and Vertac. The drummed wastes stored on site

leaked at one time or another and had to be overpacked.

21. Robert Fisher, a chemist with Hercules and Vertac, and one

of the persons considered most knowledgeable about Hercules’

operations, testified that the deterioration of the T drums was one of

the major sources of dioxin contamination at the Site. 2001 Tr. at

907.

22. See e.g. Remedial Investigation and Feasibility Study for

a

OU

50a

Appendix B

During overpacking, the chemical material that had leaked

out on to the soil would be scooped up and put into the

overpacked drum. Thus, the D-drums most likely contained

soil contaminated by Hercules’ operations which had been

scooped up when the corroding drums were overpacked.

Hercules argues that it could not have caused the waste

to be contaminated through the production process or through

the p acement of contaminated dirt into the drums at a later

date. With regard to the production process, Hercules argues

that it thoroughly cleaned out the production vessels in 1970,

while looking for a buyer or lessee.

The same equipment was used to produce 2,4,-D and

2,4,5-T. Testimony at the hearing revealed that the cleanup

of the equipment was not as thorough as portrayed by

Hercules, and that the plant equipment was cross-

contaminated with 2,4-D, 2,4,5-T and dioxin.’

Hercules also relies on a “flushing theory,” i.e., that the

thousands of batches of material Vertac ran through the

production vessels would have thoroughly flushed the, dioxin

from the vessels to the point when it would be virtually non-

existent.** Thus, there should not have been, according to

Hercules, any residual contamination in the 2,4-D drums

23. See discussion of clean-up of OU-1, infra.

24. According to the “flushing theory,” if one makes a batch of

2,4,5-T and leaves i0% of the 2,4,5-T in the process vessel, each

subsequent batch of 2,4-D made would reduce the amount of 2,4,5-

T in the product such that in the period of time from 1971 to 1979

there would be less than one molecule remaining in any initial

resiaae) material. 2001 Tr. at 366-367.

Sla

Appendix B

which were generated and stored by Vertac between the fall

of 1979 and 1986.

Hercules’ flushing theory remains just that-a theory. It

has not been subjected to scientific testing and validation.

Rather the evidence basically disproves the theory. After

nearly eight years of only 2,4-D production, dioxin and 2,4,5-

T were present in the plant equipment.

Hercules contends that the presence of dioxin in the 2,4-

D waste drums did not influence the decision to incinerate.

Hercules points to testimony by Dr. Phyllis Moore, Director

of the ADPC & E, who made the initial decision to incinerate

the drums, that the presence of dirt in the drums did not

influence the decision to incinerate.> Hercules further argues

that the placement of contaminated dirt into the drums would

constitute a separate “disposal” of hazardous substances

under CERCLA. Additionally, the redrumming efforts took

place after August, 1976, when Hercules sold the plant to

Vertac and therefore Hercules had nothing to do with the

redrumming efforts.

None of these arguments withstand scrutiny. A number

of witnesses, particularly from the State, testified about the

rationale for incineration. There was no doubt that the

drummed wastes presented a hazard to the area. EPA and the

State of Arkansas were concerned that because of the manner

in which the drums were stored, the risk of fire and explosion,

as well as the possibility of tornadoes, could spread the dioxin

25. Dr. Moore testified that the issue of “dirt” did not influence

the decision. 2001 Tr. at 279. However, she stated that the major

concern with the drums was the presence of dioxin. 2001 Tr. at 282.

52a

Appenaix B

into the environment. Additionally, witnesses testified that

because time was of the essence, testing a large number of

the drums to determine whether dioxin was present would

have been costly and time-consuming.”° It was not, as

Hercules argues, the dirt in the drums that drove the

incineration; rather it was the dioxin in the dirt that drove

the incineration of the drums.

Hercules also attacks the validity of the tests. The Court

is not in a position to discredit the testing procedures or

results. Witnesses from all parties maintained different

positions with regard to the testing results. The Court cannot

find as a matter of law that certain test results were not

reliable.

Hercules advances other innovative arguments to support

its contention that it did not cause some of the drums to be

contaminated with dioxin. One of these is that the placement

of the dirt into the drums is in itself a separate disposal.

“Disposal” under CERCLA has the same meaning

as “disposal” under the Solid Waste Disposal Act. 42 U.S.C.

§ 9601(29) The Solid Waste Disposal Act defines “ “disposal”

as the discharge, deposit, injection, dumping, spilling,

leaking, or placing of any solid waste or hazardous waste

into or on any land or water so that such solid waste or

hazardous waste or any constituent thereof may enter the

environment or be emitted into the air or discharged into

any waters, including ground waters.” 42 U.S.C. § 6903(3).

Hercules “disposed of” hazardous substances because it

placed those hazardous substances in a manner that allowed

26. See e.g. 2001 Tr. at 542, 1787.

53a

Appendix B

them to enter the environment. Attempts to further subdivide

actions in an attempt to escape liability borders on the absurd.

Hercules also argues that it is relieved of liability under

the doctrine of “superseding cause.” Restatement (Second)

of Torts, § 440. Comment b. It points to a number of actions

taken which would relieve it of responsibility.

The Court cannot find that “superseding cause” is a basis

for divisibility. The Restatement must be followed “only to

the extent that it is compatible with the provisions of

CERCLA.” 247 F.3d at 717. Recognizing a “superseding

cause” theory in this situation “would not be compatible”

with the strict liability provisions of CERCLA. Even

assuming the theory is applicable in CERCLA cases, it is

not applicable here.

The mere fact that other causes intervene between

the original act of negligence and the injury for

which recovery is sought is not sufficient to

relieve the original actor of liability, if the injury

is the natural and probable consequence of the

original negligent act or omission and is such as

might reasonably have been foreseen as probable.

Butler v. Arkansas Power & Light Co., 186 Ark.

611, 54 S.W.2d 984 [(1932)]; Arkansas Power &

Light Co. v. Marsh {195 Ark. 1135, 115 S.W.2d

825 (1938)], supra; Hayes v. Missouri Pac. R.R.

Co., 208 Ark. 370, 186 S.W.2d 780 (1945). The

original act or omission is not eliminated as a

proximate cause by an intervening cause unless

the latter is of itself sufficient to stand as the cause

54a

Appendix B

of the injury. Butler v. Arkansas Power & Light

Co., supra; Arkansas Power & Light Co. v. Marsh,

supra. The intervening cause must be such that

the injury would not have been suffered except

for the act, conduct or effect of the intervening

agent totally independent of the ‘acts or omission

constituting the primary negligence.

Pollard v. Union Pacific R. Co., 75 Ark.App. 75, 79, 54

S.W.3d 559, 562-563 (Ark.App.2001)

Here, the Court cannot find that the harms associated

with the drummed wastes, i.e., the contamination, would not

have occurred except for the totally independent acts of EPA,

the State of Arkansas, or Vertac.

“Moreover, the intervening act or omission of a third

person is not a superseding cause when the original actor’s

negligent conduct is a substantial factor in bringing about an

injury, if the actor, at the time of his negligent conduct,

realized that a third person might so act or if the intervening

act is a normal response to a situation created by the actor’s

conduct and the manner in which it is done ts not

extraordinarily negligent.” Ouachita Wilderness Institute,

Inc. v. Mergen, 329 Ark. 405, 415, 947 S.W.2d 780, 785

(Ark. 1997) There is no evidence that any action of any other

person or entity was “extraordinarily negligent” so as to

relieve Hercules of liability.

Hercules has not demonstrated that the drums did not

contain any hazardous substances that Hercules produced.

Hercules cannot show that any of those hazardous substances

5Sa

Appendix B

in the drums that were attributable to Hercules can be

distinguished from the hazardous substances in the drums that

were attributable to Vertac. There is evidence of cross

contamination of equipment. Vertac and Hercules used the same

equipment to make 2,4,-D and 2,4,5-T. Subsequent years of only

2,4,-D production did not rid the equipment of dioxin. Dioxin

was present in the soils; contaminated soil was placed in the

D-drums when they were overpacked. The soil, dust, shredded

pallets, shredded trash and the process areas were permeated

with TCDD, TCDF, 2,4-D, 2,4,5-T, 2,4,5-TP, chlorinated

benzenes and other hazardous wastes. The drum overpacking

process therefore added TCDD, TCDF and other hazardous

substances into the 2,4-D waste drums. The inner drums

continued to corrode, combining the contents of the inner drums

with those used in the overpacking.

Hercules cannot establish that it was not responsible for

the dioxin in the soil which was ultimately placed in the drums.

Even Hercules’ expert witnesses, Robert Fisher and Douglas

Keilman, both of whom worked for Hercules could not say that

the source of the dioxin in the “D” drums did not come from

Hercules.”’

The Court finds that Hercules has not provided any concrete

and specific evidence that the hazardous substances in the drums

were “distinct” such that Hercules should not be held responsible

for the costs incurred with the incineration of the drummed

wastes.

27. 2001 Tr. at 907-908. See also testimony of Steven Quigley,

an expert in environmental engineering for Uniroyal, who opined

that there is no way to identify the source of the 2,3,7,8-TCDD in

the D drums. 2001 Tr. at 1940.

56a

Appendix B

OU-I (Above Ground Media)

Hercules argues that the Court must look to the remedies

chosen and the situations which created the need for those

remedies to determine whether the harm is divisible with

respect to OU-1. Hercules divies up OU-1, declaring that it

is responsible for some harm but not for other.** That is, the

several different media should be characterized as “distinct”

environmental harms. |

Hercules contends that it cannot be held responsible for

hazardous materials in the tanks, vessels and equipment. It

claims that it removed all of its hazardous wastes when it

completely disassembled and cleaned out all the plant

equipment in 1971. Testimony at the hearing revealed that

the cleanup of the equipment was not as thorough as portrayed

by Hercules, and that all hazardous wastes were not

removed.”°

Furthermore, that Hercules cleaned the plant in 1971 is

irrelevant, because Hercules is liable as an owner while it

leased the plant to Transvaal. As an owner, it is responsible

for the contamination attributable to Transvaal’s operations.

See Nurad, Inc. v. William E. Hooper & Sons Co., 966 F.2d

837, 846 (4th Cir.1992) wert. denied sub nom., Mumaw v.

Nurad, Inc., 506 U.S. 940, 113 S.Ct. 377, 121 L.Ed.2d 288

(1992){§ 9607(a)(2) imposes liability on owner of facility at

time disposal of hazardous waste); United States v. R.W.

28. It accepts responsibility for the costs related to the spent carbon.

29. See testimony of Reedie Ray, a former Hercules plant worker

who was involved in the plant cleaning process. 2001 Tr. at 1369.

57a

Appendix B

Meyer, Inc., 889 F.2d 1497, 1507 (6th Cir.1989), cert. denied,

494 U.S. 1057, 110 S.Ct. 1527, 108 L.Ed.2d 767 (1990).

In addition to its argument concerning the 1971 plant

cleanup, Hercules relies on its “flushing theory” to establish

that the hazardous substances found in the equipment were

not its own. As discussed above, the theory is not valid. ‘That

2,4,5-T and dioxin were found in the equipment after 8 years

of just 2,4-D production disproves Hercules’ theory.

Similarly, Hercules cannot establish that it was not the

source of the contamination on the shredded trash and pallets.

The pallets, which were used to store drummed wastes at

the site, became contaminated with the 2,4,5-T, 2,4-D and

dioxin leaked from the drums.*® The pallets also became

contaminated because they were in contact with the

contaminated soil.

Hercules also contaminated the buildings. Dioxin was

found in leachate from the buildings.*’ Wipe samples from

the buildings in OU-1 revealed reportable quantities of

dioxin. Dioxin was found in storage vessels.” The 1974

Sputnik eruption contaminated nearby buildings.

Hercules contends that the threat posed by the plant

buildings was the threat of collapse, as well as asbestos

contained in some building materials. Hercules argues that

it did not cause these threats. Vertac, in abandoning the plant

30. See exhibit 1149.

31. 2001 Tr. at 1771.

32. See Exhibits 1149 and 1150.

58a

Appendix B

and letting it fall into disrepair, was responsible for the

possibility of building collapse. The United States was

responsible for asbestos being in the buildings when it built

them to house the Arkansas Ordnance Plant.

Hercules is wrong. Asbestos was not the cause for the

remediation. The buildings were demolished because the risk

of collapse might cause release and human exposure to

herbicide process contamination, including unacceptable

levels of TCDD.

In sum, Hercules has not presented evidence to

demonstrate that it was not the source of the 2,4,5-T and

dioxin in the above-ground media, and therefore it is

responsible for the costs incurred with regard to OU-1.

OU-2 (Soils, Foundations and Underground Utilities)

Hercules argues that the harm at OU-2 can be

characterized as “successive.” Hercules contends that the

principles of Bell Petroleum apply with regard to OU-2.

According to Hercules, dioxin, a single harm, drove the

remedy. Synergistic effects, relative toxicity or differential

migratory potential are not factors. The contribution of each

harm can be reasonably estimated based on the production

volume of 2,4,5-T and 2,4,5-TP. Hercules would apportion

harm based on the production records of the 2,4,5-T and

2,4,5-TP that Hercules and Vertac produced during the years

each of them owned the plant.

59a

Appendix B

According to the OU-2 Record of Decision (“ROD”),

extensive dioxin contamination was found in soils in the

blowout area, the east drum storage area, around and to the

east of the broiler house, in the area of the existing and former

chlorination plants, and around the maintenance area.

Other contaminants of concern such as chlorophehols,

chlorobenzenes and chlorophenoxyacids were also

found throughout the Site soils, in relative concentrations

paralleling dioxin concentrations. **

“Where, as in this case, hazardous substances are

commingled, a defendant cannot rely on merely volumetric

evidence. Evidence must be produced ‘disclosing the

individual and interactive qualities of the substances

deposited’ at the Site.” United States v. Vertac, 966 F.Supp.

1491, 1504 (E.D.Ark.1997) (quoting United States v.

Monsanto Co., 858 F.2d 160, 172 (4th Cir.1988), cert. denied,

490 U.S. 1106, 109 S.Ct. 3156, 104 L.Ed.2d 1019 (1989)).

Additionally, proof of “relative toxicity, migratory potential,

degree of migration and synergistic capacity” of the

hazardous substances at the Site is relevant to the divisibility

of harm inquiry. United States v. Alcan Aluminum Corp., 315

F.3d 179, 186 (2d Cir.2003) (citation omitted) “(T]he volume

of waste of a particular generator is not an accurate predictor

of the risk associated with the waste because the toxicity or

migratory potential of a particular hazardous substance

generally varies independently of the volume .. .” United

States v. Chem-Dyne Corp., 572 F.Supp. 802, 811 (S.D.Ohio

1983).

33. See ROD for OU# 2, Exhibit 6815, p. 30-35.

60a

Appendix B

EPA contends that the Hercules has failed co present

accurate production records. Hercules counters that exact

numbers are not necessary; estimates suffice if they form a

reasonable basis for apportioning the harm. “If the expert

testimony and other evidence establishes a factual basis for

making a reasonable estimate that will fairly apportion

liability, joint and several liability should not be imposed in

the absence of exceptional circumstances.” Bell Petroleum,

3 F.3d at 903.

EPA asserts that Hercules’ reliance on sales records does

not establish a reasonable basis for dividing the harm.

Estimates of production were made because some of the

production records were lost. Unlike the pure volumetric

approach in Beil, the sales records fail to adequately account

for all the production. They do not account for product made

and not sold, off-spec material disposed of at the Site, or for

operational and waste disposal differences.

The volumetric approach presupposes that leaks and

spills took place at roughly the same amount and same

frequency and severity during the production of 2,4,5-T and

2,4,5-TP. Douglas Keilman, Hercules’ project manager

involved in the remediation and an expert witness for

Hercules, conceded that in order to use volumetric evidence,

he had to assume that the release of hazardous substances

was constant over time.** If that assumption is correct, then,

according to Hercules, the amount of dioxin contributed to

the soils would be roughly proportionate to the production

volume. Based on its calculations, Hercules contends that it

is responsible for 70.74% of EPA’s response costs for OU-2.

34. 2001 Tr. at 1323-24.

6la

Appendix B

The evidence, however, does not support the assumption

on which Hercules relies. There is no way to quantify the

releases of wastes at the Site with production volumes, and

there was not a constant ratio or direct correlation between

the two. Leaks and spills occurred regularly during the years

Hercules owned the Site. Production methods differed over

the years, resulting in differences in the amount of waste

generated. Until 1966, Hercules operated a blower or dryer

at the acid plant that spewed dioxin-bearing flaked acid

material around the Site. Thus, according to EPA, more

TCDD would have been in the waste than in the product

after Hercules installed the toluene wash process. The DOD

changed the specifications for the formulation of Agent

Orange during the time it was produced, precluding the

assumption that the ratio of waste to production volume

remained constant. The concentration of active ingredients

in the DOD product was different than that in the commercial

product. Additionally, waste disposal methods differed, with

some methods producing more contamination than others.’

The sputnik eruptions reveal the difficulty in relying on

volumetrics as a basis for divisibility of harm, and point to

35. For example, Hercules used a “tee-pee” burner to dispose of

its filter paper and cardboard drums that were contaminated with

hazardous substances. The tee-pee burner was essentially a device for

open burning. It was a large metal structure with a screen on the top,

about 30 to 40 feet tall. 2001 Tr. at 143, 740. The filter paper was coated

with 2,4,5-T, 2,4-D, as well as other chlorinated hydrocarbons.

2001Tr. at. 345-46. The cardboard drums contained TCB, a chlorinated

hydrocarbon which may produce dioxins when burned. The release of

hazardous substances into the air resulting from the burning may have

caused an unknown amount of dioxin contamination at the Site. Vertac

did not burn any wastes on the Site.

62a

Appendix B

the conclusion that production is not directly correlated to the

release of waste. The evidence reveals that there were as many

as twenty sputnik eruptions at the Site while Hercules owned

the plant, and another ten when it leased the plant to Transvaal.

The eruptions spread dioxin over the Site and Off-Site areas.

The worst eruption occurred in 1974 when Transvaal leased

the Site from Hercules.*®

Here there were differences in the operations, as well as

the generation and disposal of wastes, making this situation

unlike that in Bell Petroleum, where there was only one media

and one manner of disposal. There is no evidence in this case

that the generation of waste was proportional to the production

of product.

The manufacturing process at the Site yielded hazardous

substances other than dioxin. Hercules has provided no evidence

regarding the effect of these other substances on the migration

or transport of dioxin. It has presented no evidence regarding

the relationship between the volume of dioxin or other hazardous

substances generated, the release of dioxin or other hazardous

substances, and the harm at the Site.

Hercules did not present evidence of the relative toxicity,

migratory potential and degree of migration, and synergistic

effects or capacities of the various hazardous substances

deposited at the Site. It contends they are irrelevant as the

decision to remediate was based solely on dioxin. Thus,

these factors did not come into play in the selection and

implementation of remedies.

36. 2001 Tr. at 885. The most serious process upset was the

1974 sputnik eruption in terms of generation of dioxin.

63a

Appendix B

Hercules’ argument essentially places the burden on EPA

to prove it considered the “synergistic effects” and that its

failure to include mention of it in the ROD means that there

is no need for Hercules to present evidence. While EPA

may not have referred to synergistic effects of various

contaminants, it did consider the various hazardous

substances present at the Site, not relying solely on dioxin.

As the court cautioned in Monsanto, “[{vjolumetric

contributions provide a reasonable basis of apportioning

liability only if it can be reasonably assume, or it has been

demonstrated, that independent factors had no substantial

effect on the harm to the environment.” United States v.

Monsanto Co., 858 F.2d 160, 173 n. 27 (4th Cir.1988)

(emphasis added). Hercules has not demonstrated that

independent factors had no substantial effect on the harm.

For example, according to the testimony at the hearing,

the half-life of dioxin is affected by different conditions. *’

Hercules did not present any evidence as to the rate the dioxin

broke down at the Site and Off-Site areas based on photolysis,

dissipation and other factors. It did not present any evidence

of possible synergistic effects of the combinations of dioxin

with other toxic materials, such as 2,4-D and 2,4,5-T. In sum,

the Court finds that Hercules has not established a basis to

divide the harm at OU-2.

37. 2001 Tr. at 1195.

64a

Appendix B

Off-Site Areas

The Off-Site areas include soils, the floodplains and stream

sediments of Rocky Branch Creek and Bayou Meto, sanitary

sewer lines, and two municipal sewer plants and their structures.

Hercules posits that the Off-Site environmental harm can be

characterized as “successive.” As with OU-2, Hercules states

that because the remedy was based entirely on the presence of

dioxin, the synergistic effects, relative toxicity, and differential

migratory potential were not factors. Hercules argues that the

production volumes of Hercules and Vertac for 2,4,5-T and

2,4,5-TP are a basis to find divisibility of harm. Hercules further

contends that because Hercules and Vertac never owned or

operated these off-site areas, their respective liabilities can only

be as an “arranger.”

That Hercules did not own the off-site areas does not mean

that it can only be held liable as an “arranger.” CERCLA defines

“facility” broadly to include:

(A) any building, structure, installation, equipment,

pipe or pipeline (including any pipe into a sewer or

publicly owned treatment works), well, pit, pond,

lagoon, impoundment, ditch, landfill, storage

container, motor vehicle, rolling stock, or aircraft,

or

(B) any site or area where a hazardous substance

has been deposited, stored, disposed of, or placed,

or otherwise come to be located; but does not include

any consumer product in consumer use or any vessel.

42 U.S.C. § 9601(9). The Plant Site and Off-Site areas are not

distinct facilities, but are one facility for purposes of liability

under CERCLA.

65a

Appendix B

The definition of facility “applies not only to traditional

waste sites ... but also to any ‘area’ in and around which

hazardous substances have ‘come to be located... ’” Axel

Johnson, Inc. v. Carroll Carolina Oil Co., Inc., 191 F.3d 409,

417 (4th Cir.1999) (citations and internal quotations omitted).

The Tenth Circuit recently reviewed how federal courts

have interpreted “facility” under CERCLA, finding that

the circuits that have applied the defined term

“facility” have done so with a broad brush. See

Uniroyal Chem. Co., 160 F.3d at 245 (applying

broad definition of facility in an action under

§ 107 and stating “[iJn examining the contours of

§ 9601(9), it is apparent that facility is defined in

the broadest possible terms, encompassing far

more than traditional waste sites. It expressly

includes buildings, pipelines, motor vehicles,

rolling stock, wells, and aircraft. 42 U.S.C.

§ 9601(9)(A).”) (emphasis supplied); United

States v. Rohm and Haas Co., 2 F.3d 1265, 1279

(3d Cir.1993) (examining liability under § 107 and

noting “we think it evident from the broad

statutory definition of ‘facility’ that Congress did

not intend EPA to be straight-jacketed in this

manner in situations involving a _ release

transcending property boundaries”); 3550 Stevens

Creek Assocs. v. Barclays Bank of Cal., 915 F.2d

1355, 1360 n. 10 (9th Cir.1990) (determining

liability under § 107 and noting broad construction

of the term “facility,” “such that in order to show

that an area is a ‘facility,’ the plaintiff need only

66a

Appendix B

show that a hazardous substance under CERCLA is

placed there or has otherwise come to be located

there”) (internal citations omitted); New York v.

Shore Realty Corp., 759 F.2d 1032, 1043 n. 15 (2d

Cir.1985) (“CERCLA defines the term ‘facility’

broadly to include any property at which hazardous

substances have come to be located”); see also

Quaker State Minit-Lube, Inc. v. Fireman’s Fund Ins.

Co., 52 F.3d 1522, 1525 (10th Cir. 1995) (In a § 9607

action, “[t]he EPA designated the Ekotek Site

[consisting of three surface impoundments, piles and

pits of waste material, underground tanks, and an

underground drain field] a CERCLA facility

pursuant to 42 U.S.C. § 9601(9) because of

contamination by hazardous substances.”) (emphasis

supplied).

In a § 107 action, the Fourth Circuit noted that simply

because “‘a property could be divided [into multiple facilities]

does not, however, mean that it must be so divided for CERCLA

purposes.” Axel Johnson, Inc. v. Carroll Carolina Oil Co., 191

F.3d 409, 418 (4th Cir.1999). There, the hazardous substances

were not located only in the storage tanks and their associated

spill areas; rather, they were located throughout the property.

The court, after noting the “untenability of the contention that

anything that could be designated as a separate facility must be

so designated,” applied the broad definition of facility, and noted

that “[nJo court has held .. . that any area that could qualify as

a facility under the definition must be considered a separate

facility.” /d. at 417-18 (emphasis supplied); see also Tyson, 299

F.Supp.2d at 709 (treating plant or “an area [that] is managed

as a whole ... [as] a single facility for CERCLA purposes”).

ad

67a

Appendix B

We recognize that in a § 107 action, the

hazardous substances may have contaminated

large parts of a plant, while initially being emitted

from only one tank. See Axel Johnson, 191 F.3d

at 417. However, the underlying purpose of § 103,

that is, the alerting of government officials of a

potential hazardous substance release that may

require federal and local government response

assistance, is best served through treating the

Dorman Farm as a single facility. Solely owned

by Seaboard, it is managed and operated as one

facility, with one particular site purpose

(producing swine products). See also Akzo

Coatings, Inc. v. Aigner Corp., 960 F.Supp. 1354,

1359 (N.D.Ind.1996) (rejecting the argument that

each contamination source is a separate facility

because such argument “could have disastrous

consequences, for ultimately every separate

instance of contamination, down to each separate

barrel of hazardous waste, could feasibly be

construed to constitute a separate CERCLA

facility”), aff'd in part, vacated in part by, 197

F.3d 302 (7th Cir.1999); Quaker State Minit-Lube,

52 F.3d at 1525 (10th Cir.1995) (entire site, which

consisted of surface impoundments, piles and pits

of waste material, underground tanks, and an

underground drain field considered a facility for

§ 9607); Cytec Indus. v. B.F. Goodrich Co., 232

F.Supp.2d 821, 836 (S.D.Ohio 2002) (“This court

concludes that usually, although perhaps not

always, the definition of facility will be the entire

site or area, including single or contiguous

68a

Appendix B

properties, where hazardous wastes have been

deposited as part of the same operation or

management.”); Clear Lake Props. v. Rockwell

Int’l Corp., 959 F.Supp. 763, 767-68

(S.D.Tex.1997) (rejecting an attempt to create

unnatural boundaries between a building and the

site on which it is located).

Sierra Club v. Seaboard Farms Inc., 387 F.3d 1167, 1174-1175

(10th Cir.2004) (finding that farm complex as a whole, as

opposed to every barn, lagoon and land application area on

complex, constituted single “facility” under CERCLA)

In this case, the contamination from the Site migrated to

the contiguous off-site areas. Hercules contributed to the

contamination of the off-site areas when it operated the Plant

Site from 1961 to 1971 and when it leased the Plant Site to

Transvaal from 1971 to 1976, during which time Transvaal’s

Operations further contaminated the Plant Site and Off-Site

Areas. Therefore, Hercules is liable as an owner under section

107(a)(2) for contamination in the Off-Site Areas.

The Court has already discussed the flaws with applying a

volumetrics approach to the divisibility of harm with regard to

OU-2. The same analysis applies to the Off-Site areas. The Court

cannot find that the harm at the Off-Site areas is divisible based

on production volumes.

OU-3 (Groundwater)

Hercules states that it did not cause the groundwater

contamination which resulted from Vertac’s ownership and

operation of the Site after August, 1976. Hercules contends that

69a

Appendix B

the response costs associated with the remediation of

groundwater contamination are divisible as a successive harm.

Generalized organic compounds drove the remedy and,

according to Hercules, the costs can be apportioned based on

volumetrics because there are no synergistic or interactive effects

of the chemicals of concern, i.e., organics, upon each other. That

is, the amount of organic chemicals generated in the production

process, which would have been the source of contamination

of the groundwater, would have been proportional to total

production volume of all products, not just 2,4,5-T and 2,4,5-

TP. Furthermore, Hercules contends that the manufacturing

processes did not change materially over the time that Hercules

and Vertac operated the plant. Here, Hercules posits that the

Court should use total production volume to determine the

amount of harm caused by Hercules.

The flaws associated with Hercules’ volumetrics approach

discussed above apply equally to its argument with respect to

groundwater contamination. Furthermore, the evidence supports

a finding that Hercules disproportionately contaminated the

groundwater. There is no dispute that thousands of drums of

2,4-D and 2,4,5-T were buried on site during the time Hercules

owned the Site. The burying of such wastes in unlined pits

contributed to the groundwater contaminat‘on at the Site.

Furthermore, when Hercules operated the Site, waste was

poured into a well, resulting in contamination of the

groundwater.** Hercules is liable for the contamination of the

groundwater, not only as a result of its practices, but those

of Transvaal. “[GJround water contamination at the site is

complex, resulting from past water management and disposal

38. 2001 Tr. at 1968-69.

70a

Appendix B

practices. Sources of contamination include on-site landfills,

spills and discharges into the central ditch, Reasor Hill well,

and other parts of the central process area.”?? The dioxin

spewed from the sputnik eruption in 1974 contaminated the

groundwater.*? Sputnik waste which was probably

contaminated with dioxin was dumped in the marshy area

adjacent to the Boiler House.*! Furthermore, the record

establishes that Hercules’ operations contaminated other

areas encompassed by OU-3, such as the process area and

soils, including areas on the east side of the central ditch.

Hercules tries to distinguish the drum burial areas from

OU-3. Such an attempt is without merit. It admitted that it

was liable for ground water contamination. Hercules buried

drums containing hazardous wastes on site. The OU-3

remedial includes the burial areas and Hercules is responsible

for the contamination resulting from the burial of the drums.”

The contaminants of concern in the ground water were

released and disposed by Reasor-Hill, Hercules and

Transvaal/Vertac. Hercules has not produced any specific

evidence upon which to divide the harm.

Landfills

As Hercules never owned or operated the two landfills,

its liability arises as an arranger for the disposal of hazardous

39. Exhibit 6854, ROD for OU# 3, at p. 31.

40. See Exhibit 7513 at p. 124.

41. 2001 Tr. at 1245.

42. See Exhibit 6854, ROD for Operable Unit # 3.

Tila

Appendix B

substances at the landfills. Hercules argues that there is no

evidence that it ever disposed of CERCLA hazardous waste

at..the landfills.

Rogers Road Landfill

The Rogers Road Landfill is a ten-acre tract that the City

of Jacksonville acquired on September 16, 1953. Hercules

contends that it did not send any of its waste, garbage or

trash to the Rogers Road Landfill because it was closed

during the years that Hercules operated the plant. Hercules

states that the Rogers Road Landfill was opened from 1953

until 1959, closed between 1959 and 1973, and then reopened

for a brief period from 1973-1974. The exact dates that the

landfill was open are unclear; the Eighth Circuit in O’Dell v.

Hercules, Inc., 904 F.2d 1194, 1197 (8th Cir.1990) found

that “{t]he Rogers Road landfill had been closed by the city

of Jacksonville in 1959. However, unofficial dumping

occurred at Rogers Road.”*”

Fifteen to 50 drums of dioxin contaminated waste were

disposed of at the landfill. They were not labeled and were

very corroded.** Hazardous substances identical to those

generated by Hercules at the Site were found at the landfill,

43. See also Exhibit 8099, Technical Assistance: Rogers Road

Landfill. “From 1953 until 1974, approximately one-half of the site

was used intermittently as a municipal waste disposal facility and

an open dump.” But see 2001 Tr. at 349, deposition testimony of

Stephen Veale, remedial project manager for EPA, who stated that

Rogers Road was opened from 1953 to 1959, closed from 1959 to

1973 and then open again in 1973 to 1974.

44. Exhibit 6895, ROD for Rogers Road Landfill, pg. 1-4.

72a

Appendix B

including 2,3,7,8-TCDD, 2,4-D, 2,4,5-T, and 2,4,5-TP.** In

addition, Dieldrin, an herbicide produced by Reasor-Hill, was

found.

EPA in the ROD concluded that no detailed records were

found to prove how the contaminants of concern were placed

at the landfill.*° To establish Hercules’ liability for harm at

the Rogers Road landfill, EPA relies on the testimony of Alsie

Glover, who lived next door to the Rogers Road landfill and

in between it and the Graham Road landfill. She testified in

the O’Dell-Bridges trial that the Rogers Road Landfill was

opened from 1961 to 1967 and accessible during the years

Hercules operated its Jacksonville Plant.*7 She saw barrels

at the Rogers Road dump with the name “Hercules

Manufacturing Company.”** Photographs of the drums at the

landfill reveals no such labels or markings. The ROD states

that there were no discernable markings on the drums.‘?

Vincent Dodson, who worked for Hercules from the

summer of 1967 through 1969, testified in the O’Dell-Bridges

trial that the 55-gallon barrels he took to the Graham Road

landfill did not have Hercules’ name or logo.® Duane Reel,

45. Id. at 1-32.

46. AROOI821.

47. 2001 Tr. at 165.

48. 2001 Tr. at 171.

49. Exhibit 6895, p. 1-4.

50. Testimony of Vincent Dodson, O'Dell-Bridges trial, Feb.

16, 1988, p. 277.

73a

Appendix B

who was city engineer for the City of Jacksonville during

the time of the remediation, testified that the drums he

observed at the landfill did not have any labels on them.°*!

Martin Swanson, a remedial project manager for the

Jacksonville Site, testified that there were no marking on

the drums at the Rogers Road landfill and that there were no

materials at the landfill that had Hercules markings on them.*?

Billy Roberts began working for Reasor-Hill in 1954, and

worked almost continuously at the Site for 48 years.** He

stated that Reasor-Hill disposed of its filter paper at the

landfill. He recalled going to Rogers Road once and to the

Jacksonville landfill twice for Reasor-Hill. He could not state

definitely that he ever went to Rogers Road for Hercules.**

Also supporting Hercules’ position that it did not dispose

of wastes at Rogers Road is the presence of dieldrin. Dieldrin

was produced by Reasor-Hill, who operated the Site during

the time the Rogers Road landfill was opened. EPA states

that Hercules may have disposed of some of the Dieldrin

wastes that had been left by Reasor-Hill when Hercules

purchased the plant. This, of course, is speculation. It is

equally, if not more plausible, based on the testimony of Billy

Roberts, that Reasor-Hill disposed of the chemical wastes at

the landfill.

The Court also notes that the residents around the

landfills used empty barrels for their personal use, such as

51. 2001 Tr. at 151.

52. 2001 Tr. at 1524.

53. 2001 Tr. at 2050.

54. 2001 Tr. at 2054-55.

74a

Appendix B

for burning trash or for barbecue grills. They also used the

landfill to dump their wastes. It is quite possible that the

barrels could have been placed in the landfill by the

residents.°°

The Court finds that Hercules has met its burden of

establishing that it is not responsible for the harm caused at

the Rogers Road landfill. Thus, Hercules will not be

responsible for the costs incurred by the government with

respect to the Rogers Road landfill.

Jacksonville Landfill (also known as the Graham Road

Landfill or City Dump)

The Jacksonville Municipal Landfill Superfund Site is

an eight-acre plot purchased by the City of Jacksonville in

June, 1960. The landfill has been referred to as the

Jacksonville Landfill, the Graham Road Landfill, the Graham

Road Dump and the Jacksonville City Dump. About forty of

the eighty acres were used by the City for landfilling until

the landfill was closed in 1973.°

Between 15 and 50 drums were disposed of in an area

referred to as the “drum disposal area,” located behind the

pipeline on the south end of the landfill property. “Most of

the drums have corroded completely away, leaving piles of

white, fibrous, adsorbent-type materials.’*’ The contaminants

55. 2001 Tr. at 66-67, 191-194.

56. ARO02384.

57. AR002389.

75a

Appendix B

of concern that were detected were 2,3,7,8-TCDD, 2,4-D,

2,4,5-T, 2,4,5-TP and 2,4-DCP.*8

Hercules admits that it took some waste to the Graham

Road Landfill. However, Hercules states that the trash that

was taken did not contain hazardous substances. Thus,

Hercules contends that it was not responsible for the presence

of the hazardous substances, particularly the filter paper in

which the chemicals of concern were found, at the

Jacksonville Landfill.

The Court need not dwell long on Hercules’ argument.

The record is replete with testimony of Hercules’ employees

who took chemical wastes to the “city dump.” Vincent

Dodson, who worked for Hercules in the late 1960s, testified

that chemical wastes, including those that came from leaks

and spills and the Sputnik explosions, were scooped up,

placed in barrels and dumped at the Jacksonville landfill>°

Doyce Shurley, who worked for Hercules in the early 1960s,

remembered going to the Jacksonville Landfill two or three

times for Hercules to dispose of trash. He believed that he

once disposed of a barrel of toluene stillbottoms.®© Billy

Honey also testified that when he worked for Hercules he

hauled drums which contained chemical waste to the Graham

Road landfill.°' Similarly, LeRoy Jordan confirmed that he

58. ARO002396-97.

59. 2001 Tr. at 55, 70.

60. 2001 Tr. at 212.

61. 2001 Tr. at 144, 146-147.

76a

Appendix B

disposed of both liquid and solid waste barrels at the Graham

Road site for Hercules.°?

That the drums only contained filter paper, as Hercules

contends, does not absolve Hercules of arranging for the

disposal of hazardous substances. Filter paper was used in

the manufacture of 2,4-D, 2,4,5-T, and 2,4,5-TP and Hercules

used it in its product formulation. Filter paper was caked

with various wastes including TCDD.

Hercules also relies on “geographic considerations” as

a basis for limiting its harm. In United States v. Township of

Brighton, 153 F.3d 307, 320 (6th Cir. 1998), the court stated

that if the Township “could show that its ‘operating’ activities

were completely limited to a discrete and measurable section

of the property, and that the releases onto or from that section

represented a discrete and measurable harm, this would

provide a reasonable basis for apportionment.”

The non-contiguous areas, according to Hercules, are the

north and south sides of the Jacksonville landfill, areas which

were divided by a natural gas pipeline and opened for use at

different times. It contends that it only deposited waste on

the north side of the landfill, and it is therefore not responsible

for the response costs associated with the waste on the south

side of the landfill.

EPA presented a photograph of the Jacksonville Landfill

dated July 1969 showing that there was waste disposal south

62. 2001 Tr. at 200-202.

77a

Appendix B

of the pipeline right-of-way as of 1969. Vincent Dodson

testified that he disposed of wastes south of the pipeline.

Hercules cannot show that the trash, filter paper, and other

materials disposed of at the Jacksonville landfill were not

contaminated with hazardous substances, including dioxin,

2,4,5-T and 2,4-D. It also cannot demonstrate that it is not the

source of the contamination at the Jacksonville City landfill.

Thus, the Court finds that Hercules has not established a basis

to divide the harm at the Jacksonville City landfill.

Constitutionality of CERCLA

Hercules contends that the retroactive application

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Petition for Writ of Certiorari — Chemtura Canada Canada Co. Co./CIE v. United States (Nos. 06-853, 06-1014, 06-865) | Frix