Appendix — Beazer East, Inc. v. Mead Corp.
Supreme Court brief2006
Ask Donna
What actually matters in this document.
Text
10a
through December 31, 1999, were recoverable CERCLA
response costs. In August 2002 the District Court issued a
thorough opinion largely rejecting Mead’s challenges to
Beazer’s costs. The court determined that Beazer had incurred
recoverable response costs of $4,805,137.60 through the end
of 1999 and entered judgment against Mead for 67.5% of this
amoumt, or $ 3,243,467.80. Pursuant to the parties’
stipulation, in September 2002, the Court further ordered
Mead to pay pre-judgment interest in the amount of
$1 ,538,164.03. Finally, in October 2002, the District Court
entered a declaratory judgment requiring Mead to pay 67.5%
of Beazer’s ongoing response costs associated with
implementing the AOC. The order also provided a framework
for resolution of disputes over the necessity and NCP-
consistency of such costs.
Mead timely appealed these orders. In December 2002,
we assigned the case for mediation pursuant to the Third
Circuit's Appellate Mediation Program, L.A.R. 33. The
parties strenuously dispute what transpired at the February
26, 2003, mediation session. Beazer claims that the parties
reached an oral agreement while Mead claims that the
tentative agreement reached at mediation was conditioned on
further management approval which was ultimately denied. In
May 2003, Beazer moved this Court to enforce the alleged
oral settlement and dismiss Mead’s appeal with prejudice. The
motion was referred to this panel and we decide it here along
with Mead’s appeals.
III .Jurisdiction
The District Court had jurisdiction over this case under 42
U.S.C. § 9613(b), which vests exclusive jurisdiction of
CERCLA claims in the federal courts, as well as under 28
U.S.C. §§ 1331 and 1332. Horsehead Industries, Inc. v.
lla
Paramount Communications, Inc., 258 F.3d 132, 140 (3d
Cir. 2001); Beazer 1, 34 F.3d at 210. We have appellate
jurisdiction over the appeal from the District Court's final
orders described above pursuant to 28 U.S.C. § 1291.
Horsehead Industries, 258 F.3d at 140. Finally, we have
original jurisdiction over Beazer’s motion to enforce the
alleged settlement agreement. See Fed. R. App. Pro. 33
(“The court may, as a result of the [mediation], enter an order
controlling the course of the proceedings or implementing any
settlement agreement.”). See aiso Herrnreiter v. Chi. Hous.
Auth. , 281 F.3d 634, 637 (7th Cir. 2002).
V. Discussion
A. Enforcement of the alleged oral settlement.
Beazer’s motion to specifically enforce the alleged oral
settlement reached at the appellate mediation and to dismiss
this appeal with prejudice must be rejected. Both Local
Appellate Rule (LAR) 33.5 and sound judicial policy compel
the conclusion that parties to an appellate mediation session
are not bound by anything short of a written settlement. Any
otlier rule would seriously undermine the efficacy of the
Appellate Mediation Program by compromising the
confidentiality of settlement negotiations.‘
* Federal Rule of Appellate Procedure 33 gives appellate courts the
power to order settlement conferences and to “implement{]} any
s>ttlement agreement” reached as a result of such conferences. Fed.
R. App. P. 33. The Third Circuit has established an Appellate
Mediation Program to implement this general directive. Local
Appellate Rule 33.0. The program is subject to the rules and
procedures provided in the Local Appellate Rules. /d.
12a
Beazer requests enforcement of the alleged oral settlement
but admits that there are genuine factual disputes regarding
whether the parties actually reached an agreement.’ Mead
correctly argues that we cannot resolve these disputes without
violating the confidentiality rule, LAR 33.S(c). With
exceptions not relevant here, Rule 33.5(<) provides that no
one at the mediation session - neither mediator, counsel, nor
party - may disclose “statements made or information
developed during the mediation process.” The provision
further provides that “the parties are prohibited from using
any information obtained as a result of the mediation process
as a basis for any motion or argument to any court.” LAR
33.5(c) (emphases added). Beazer cannot prove the existence
or terms of the disputed oral settlement without violating this
provision’s broadly stated prohibitions.°
* Beazer asserts that the parties reached an oral agreement at the
mediation conference but that Mead’s management ultimately
reneged on the agreement while it was being reduced to writing
over the course of the following weeks. Mead contends that the
parties only reached “a tentative resolution of some of the financial
terms.” According to Mead, this resolution was non-binding
because it exceeded Mead’s representatives’ settlement authority.
According to Beazer, Mead’s representatives never indicated that
the agreement reached at the mediation session was conditioned on
subsequent approval by Mead’s management.
® It is true that the rule also provides that “notwithstanding the
foregoing, the bare fact that a settlement has been reached as a
result of mediation shall not be considered confidential.” LAR
33.5(c). However, this exception is unavailing. Beazer may assert
the “bare fact” that a settlement was reached but may not offer any
evidence supporting this assertion. Since Mead asserts that no
settlement was reached, there is no way for us to resolve the
dispute.
13a
Beazer argues that the rule is not so sweeping. Beazer
concedes that it may not use information obtained at the
conference in any argument going to the merits of the appeal,
but contends that it must be able to use that information for
the limited purposes of proving the existence and terms of a
settlement. This argument is unpersuasive. First, the rule is
stated in the broadest possible language and docs not
contemplate any such exception. Second, Beazer’s proposed
exception would effectively undermine the rule and would
compromise the effectiveness of the Appellate Mediation
Program. A confidentiality provision “permits and encourages
counsel to discuss matters in an uninhibited fashion often
leading to settlement.” Lake Utopia Paper Lid. v. Connelly
Containers, Inc., 608 F.2d 928, 929 (2d Cir. 1979). If
counsel know beforehand that the proceedings may be laid
bare on the claim that an oral settlement occurred at the
conference, they will “of necessity . . . feel constrained to
conduct themselves in a cautious, tight-lipped, non-committal
manner more suitable to poker players in a high-stakes game
than to adversaries attempting to arrive at a just resolution of
a civil dispute.” /d.; see also Herrnreiter, 281 F.3d at 637
(“A motion to implement a conference settlement easily could
be a strategy to pierce the confidentiality of the negotiations
and inform the judges of the parties’ position, rather than to
carry Out an agreement actually reached.”). Third, Beazer’s
proposed exception would require appellate courts to receive
evidence and resolve factual disputes, tasks more properly
suited to the district courts. See Herrnreiter, 281 F.3d at 637.
We must also consider LAR 33.5(d), which provides that
“no party shall be bound by statements or actions at a
mediation session unless a settlement is reached.” The rule
further provides that “if a settlement is reached, the
agreement shall be reduced to writing and shall be binding
upon all parties to the agreement.” Mead argues that the most
l4a
“straightforward” reading of this rule is that no agreement is
binding until it is written. Mead’s reading is serial: 1) if the
parties reach an agreement, 2) then that agreement shall be
written down, and 3) then, and only then, the agreement shall
be binding. However, the grammatical structure of the rule is
consistent with a parallel construction: 1) if the parties reach
an agreement, 2)a) then it shall be reduced to writing, and,
2)b) then it shall be binding. Under this reading, the
agreement is binding because it has been reached, not because
it has been written down.
The “parallel” construction of Rule 33.5(d) -- which
would make oral settlement agreements binding on the parties
-- is irreconcilable with Rule 33.5(c), because, as described
above, there is no way to prove the existence or terms of a
disputed oral settlement without violating the confidentiality
provision. Therefore, we adopt Mead's “serial” reading of
Rule 33.5(d), according to which an agreement is not binding
unless it is reduced to writing. We note that the Ninth Circuit
adopted a serial interpretation of similar language in Barnett
v. Sea Land Serv., Inc., 875 F.2d 741, 743-44 (9th Cir.
1989).’
” As in this case, the parties in Barnett entered into mediation, but
one of the parties refused to sign a settlement agreement prepared
by another p#rty after the mediation took place and argued that no
settlement fad been reached. Jd. Relying on Local Rule 39.1, a
confidentiality provision governing mediation proceedings in the
Western District of Washington, the District Court prohibited the
party seeking to enforce the alleged agreement from eliciting
testimony from the mediator about whether a settlement had been
reached. /d. Local Rule 39.1 is very similar to the Third Circuit's
LAR 33.5(c) & (d). After providing that mediation proceedings and
statements are privileged, the rule states that “no party shall be
bound by anything done or said at the conference unless a
1Sa
Further, Judge Easterbrook’s opinion in Herrnreiter
provides persuasive policy justifications (or requiring written
settlements.* In Herrnreiter the parties admitted that they had
reached an oral settlement at a voluntary appellate mediation
session but they did not agree on the terms. /d. at 636. The
court denied the defendant’s motion to implement the oral
settlement. /d. at 637. The court noted that there is no
transcript of appellate mediation sessions and that settlement
conference attorneys presiding over such sessions promise
both sides that nothing that transpires at the conference will
be revealed to the judges; the court finally observed that
appellate courts are not well-positioned to conduct factfinding
missions. /d. Accordingly, the court concluded that nothing
short of a mutually satisfactory written settlement agreement
could terminate an appeal. /d. “Any other approach would
compromise the confidentiality of the negotiations, require the
settlement attorneys to become witnesses in appellate
factfinding proceedings, and substantially complicate the
disposition of litigation.” /d. All of these concerns are equally
present in this case. In fact, the argument for preserving
confidentiality of proceedings is even stronger in this case,
where participation in the appellate mediation program is
settlement is reached, in which event the agreement upon a
settlement shall be reduced to writing and shall be binding upon all
the parties to that agreement.” /d. The Ninth Circuit interpreted this
language to mean that “until a settlement is reduced to writing, it
is not binding upon the parties.” /d. at 744.
* If there are analogous local rules governing the Seventh Circuit's
appellate mediation program the Court in Herrnreitter did not
address them. Rather, it interpreted the text of Fed. R. App. Pro.
33, which does not contain a confidentiality provision, and the
practice of the Seventh Circuit’s Settlement Conference Office. 281
F.3d at 637-38.
l6a
mandatory and the mediation is directed by a court-employed
mediator of a judicial officer. See In re Anonymous, 283 F.3d
627, 636-37 (4th Cir. 2002) (citation omitted).
Beazer complains that if Mead’s interpretation of Rules
33.5(c) and (d) is accepted then parties will be able to enter
into oral agreements at settlement conferences and simply
back out on a whim, significantly deterring the federal policy
of encouraging settlements. See D.R. v. East Brunswick Bd.
of Educ., 109 F.3d 896, 901 (3d Cir. 1997). Beazer also
relies on our oft-repeated position that a written agreement is
not necessary to render a settlement enforceable. See, e.z.,
Green v. John H. Lewis & Co., 436 F.2d 389, 390 (3d Cir.
1970) (citations omitted). Mead’s first argument is simply
incorrect: if parties know beforehand that only a written
settlement agreement is binding, they will be sure to
memorialize their agreement in writing at the end of the
mediation session. Its second argument is based on basic
common law contract principles, see Main Line Theatres, Inc.
v. Paramount Film Distributing Corp. , 298 F.2d 801, 803 (3d
Cir. 1962), and has no application where specific court rules
provide otherwise.
For all these reasons, Beazer’s motion to enforce the
alleged oral settlement agreement and dismiss the appeal is
denied.
B. The District Court’s Referral to the Magistrate Judge.
Mead argues that the Magistrates Act, 28 U.S.C. § 636,
does not authorize the District Court’s referral to the
Magistrate Judge, over Mead’s objection, of the equitable
allocation issue. Mead contends that, for that reason, the
Magistrate Judge lacked jurisdiction to conduct a hearing or
issue a Report and Recommendation. Mead further asserts
17a
District Court's putative de novo review did not rectify the
improper referral. We agree with Mead on both points.”
The jurisdiction of magistrate judges is limited by statute
and may not be augmented by the federal courts. See Thomas
v. Whitworth, 136 F.3d 756, 758 (1ith Cir. 1998) (citing
NLRB v. A-Plus Roofing, Inc., 39 F.34-1410, 1415 (9th Cir.
1994)). The District Court did not rely on any specific
provision of the Magistrates Act in its order of referral or its
order rejecting Mead's objections to the referral, but it is
clear from the context that the court considered the equitable
allocation issue a “pretrial matter” under § 636(b)(1)."
Beazer argues in the alternative that the referral could be re-
characterized as a designation of the Magistrate Judge to serve
as a special master under § 636(b)(2) and Federal Rule of
Civil Procedure 53(b). Beazer also argues that the referral
was permissible under § 636(b)(3), which authorizes
magistrate judges to undertake “such additional duties as are
not inconsistent with the Constitution and laws of the United
States.” We conclude that the referral was not proper under
any provision of the Magistrates Act."
* The scope of a magistrate judge's authority is a question of law
over which this Court exercises plenary review. Bowers v. NCAA,
346 F.3d 402, 410 (3d Cir. 2003).
We agree with the Fifth Circuit that “good practice would
indicate that court orders of designation or reference state plainly
under what statutory provision the court is proceeding.” Archie v.
Christian, 808 F.2d 1132, 1137 (Sth Cir. 1987) (en banc); see also
Silberstein v. Silberstein, 859 F.2d 40, 42 (7th Cir. 1988).
"' The District Court also held that Mead’s objections to the referral
were untimely because Mead did not immediately object but waited
until the Magistrate Judge had issued a scheduling order
18a
1. Equitable allocation is not a “pretrial matter.”
We first consider whether the equitable allocation
proceeding referred to the Magistrate Judge is correctly
characterized as a “pretrial matter.” The Magistrates Act
withorizes district courts to appoint magistrate judges to
consider pretrial matters without regard to the parties’
contemplating implementation of the referral. Mead correctly
argues that objections to a magistrate judge’s authority are
jurisdictional and may be raised at any time. Government of Virgin
Islands v. Williams, 892 F.2d 305, 309 (3d Cir. 1989). Further, for
reasons provided in the next section of this opinion we conclude
that the Magistrate Judge essentially held a trial on the equitable
allocation issue, and trials may not be conducted by a magistrate
judge without the parties’ consent. 28 U.S.C. § 636(c)\(1). Even if
this consent requirement could be waived, a question we need not
District Court's order of referral cannot be construed as a waiver.
Mead objected to the Magistrate Judge's authority to consider the
equitable allocation issue just after the Magistrate Judge entered its
scheduling order and long before the Magistrate Judge had begun
to consider the merits of this issue, much less receive the parties’
submissions or hold a hearing.
We note that Beazer has failed on appeal to respond to any of
Mead's arguments on this point. Of course, an appelice does not
concede that a judgmezi sisould be reversed by failing to respond to
an appellant's argument in favor of reversal. See Singletary v.
Continental lilinois Nat'l Bank, 9 F.3d 1236, 1240 (7th Cir. 1993).
However, the appellee “waives, as a practical matter anyway, any
objections not obvious to the court to specific points urged by the
{appeliant].” Hardy v. City Optical Inc. , 39 F.3d 765, 771 (7th Cir.
1994) (citations omitted).
19a
consent. 28 U.S.C. § 636(b)(1)."2 The District Court
considered the equitable allocation proceeding a pretrial
matter because it constituted a “significant step” in resolving
the case:
First, the identification of the equitable factors that
will be relevant in an ultimate disposition of this case
essentially is a pretrial matter and constitutes a
significant step in resolving the parties’ current
dispute. In addition, submitting briefs in support of an
aliocation of Beazer’s clean-up costs among the parties
likewise is a pretrial undertaking which is necessary to
narrow the issues for trial.
The District Court's reasoning is misleading and without
supporting authority. First, the District Court significantly
understates the significance and scope of the referral. The
parties did not simply “submit briefs” in support of the
equitable allocation issue -- they presented extensive
testimonial and documentary evidence over the course of a
12-day hearing. At the conclusion of this hearing the
Magistrate Judge not only identified equitable factors but also
applied those factors to make a recommendation as to the
allocation of liability among the parties. Second, by the
District Court’s reasoning, any issue in the case could be
could be considered by a magistrate judge in a “pretrial”
proceeding so long as the Court later conducted a “trial” on
at least one issue. Whether a given issue is a “pretrial
'? The magistrate judge may hear and decide nondispositive pretrial
matters but may only issue a report and recommendation on
dispositive pre-trial matters. Compare 28 U.S.C. § 636(b)(1)(A)
with id. at § 636(b)(1)(B); see also Fed. R. Civ. P. 72; United
States v. Polishan, 336 F.3d 234, 239 (3d Cir, 2003); NLRB v.
Frazier, 966 F.2d 812, 816 (3d Cir. 1992).
20a
matter,” however, turns on the nature of the issue itself, not
on the position in which it falls in the sequence of decision.
A CERCLA contribution action consists of determining
which parties are liable under CERCLA and apportioning the
liable parties’ shares in an equitable manner. See 42 U.S.C.
§§ 9607(a) & 9613(f)(1); New Jersey Turnpike Authority v.
PPG Industries, Inc. , 197 F.3d 96, 104 & n.7 (3d Cir. 1999);
Kalamazoo River Study Group v. Menasha Corp., 228 F.3d
648, 656-57 (6th Cir. 2000). Here, the first phase was
uncontested: Mead, Beazer, and KII are each liable as current
or former owners and operators of the Woodward Coke Plant.
See 42 U.S.C. § 9607(a)i). The equitable apportionment
phase was divided into two proceedings: a proceeding
(conducted by the Magistrate Judge) to determine the parties’
equitable shares of response costs on a percentage basis, see
42 U.S.C. § 9613(f)(1), and a separate proceeding (conducted
by the District Court) to determine which of Beazer's actual
costs qualify as recoverable response costs, see 42 U.S.C.
§ 9607(a)(4)(B). Contrary to the District Court's assertions,
then, the issue referred to the Magistrate Judge was not a
precursor to resolution of the ultimate issue -- it was one of
the ultimate issues to be tried. In fact, it was the only issue in
the case unique to contribution claims. Whether a party is
liable and which costs are recoverable are questions governed
by CERCLA's liability provision, 42 U.S.C. § 9607. The
contribution provision, section 9613(f)(1), provides that “in
resolving contribution claims, the court may allocaie response
costs among liable parties using such equitable factors as the
court determines are appropriate.” This was the very task
referred to the Magistrate Judge.
Further, this task required the Magistrate Judge to resolve
factual disputes going to the merits of the case. In Banks v.
United States, 614 F.2d 95 (6th Cir. 1980), the court
2la
reasoned that section 636(b)(1) was carefully drafted to avoid
granting magistrate judges the authority to perform fact-
finding on the merits of case because that function is the
essence of a trial, and magistrate judges cannot conduct trials
without the parties’ consent:
The statute clearly contemplates that a magistrate be
allowed to help a district judge with a variety of pre-
cannot conduct a trial itself. Under our system of law,
when there are factual controversies, there must be a
trial. Only when a party is entitled to judgment as a
matter of law may a trial be aborted. See e.g. Fed R.
Civ. P. 12, 56. Congress was careful to recognize this
distinction when it amended the Federal Magistrate's
Act. The Act permits a magistrate to prepare proposed
findings on a variety of “case dispositive” motions
such as summary judgment. Except for prisoner's
cases, the act does not permit the magistrate to
perform fact-finding on the merits of a case. That is
the exclusive function of a district judge. Indeed, the
magistrate judge's role is to free the judge from pre-
trial wrangling so that he can try cases.
22a
Id. at 97." In this case the Magistrate Judge did not facilitate
the District Court's ultimate adjudicatory function - he
assumed that function. In the course of making his Report and
Recommendation, the Magistrate Judge resolved two critical
factual disputes. First, the he determined that Mead was
responsible for approximately 90% of the waste at the
Woodward Coke Plant. Second, he found that the parties to
the 1974 purchase agreement intended that Mead would not
be responsible for any environmental liabilities at the Piant.
By making these findings, he tried part of the case and
usurped the role of the District Judge. Accordingly, the
equitable allocation proceeding conducted by the Magistrate
Judge is not a “pretrial matter” under 28 U.S.C. § 636(b)(1).
One further argument warrants mention. Beazer and che
District Court imply that the equitable allocation proceeding
conducted by the Magistrate Judge was a “pretrial matter”
simply because it preceded the recoverable costs proceeding
conducted by the District Court. This is mere happenstance.
The proceedings could have been held in the reverse order or
held together. As discussed above, the important issue is not
the order of decision but the nature of decision - both the
equitable allocation proceeding and the recoverable costs
'’ This interpretation is supported by the legislative history of the
Magistrate's Act and its amendments. See, ¢e.g., H.R. Rep. No. 94-
1609, at 7 (1976) (explaining that the magistrate judge is to “assist
the district judge in a variety of pretrial and preliminary matters
thereby facilitating the ultimate and final exercise of the
adjudicatory function at the trial of the case.”); see also Gomez v.
United States, 490 U.S. 858, 872, 104 L. Ed. 2d 923, 109 S. Ct.
2237 & n.23, 490 U.S. 858, 104 L. Ed. 2d 923, 109 S. Ct. 2237
(1989) (collecting legislative history for the proposition that
“magistrates should handle subsidiary matters to enable district
judges to concentrate on trying cases”).
23a
proceeding required the decisionmaker to resolve factual
disputes going to the ultimate issues in the case.
2. Equitable allocation cannot be referred to a special
master without the parties’ consent.
Beazer argues that, even if the referral is not authorized
by § 6306(b)(1), we should recharacterize the referral as a
designation of the Magistrate Judge to serve as a special
master under § 636(b)(2). We need not reach the issue of
whether an appellate court can save a flawed referral in this
manner because we hold that the designation of a Magistrate
Judge to conduct an equitable allocation without the parties’
consent would constitute an abuse of discretion.'* See Sierra
Club v. Browner, 257 F.3d 444, 446 (9th Cir. 2001)
(designation of special master is reviewed for abuse of
discretion); American Cyanamid Co. v. Ellis-Foster Co. , 298
F.2d 244, 247 (3d Cir. 1962) (same).
‘* At least one circuit court has suggested in dictum that an
improper referral under § 636(b)(1) could be re-characterized as a
designation of a magistrate judge to serve as a special master per §
636(b)(2) and Rule 53(b). In Callier v. Gray, 167 F.3d 977, 983
(6th Cir. 1999), the court upheld an ambiguous referral to a
magistrate judge of a damages issue under the “additional duties”
provision, § 636(b)(3). The court noted that Rule 53(b) might have
served as an “additional basis for jurisdiction of the magistrate
judge on the damages dispute,” but concluded that it did not need
to reach the issue. /d. at 983 n.10. The court entertained this idea
even though the referral in that case was made specifically under
§ 636(b)(1)(B), not § 636(b)(2). We take no position on this issue.
24a
Sect.on 636(b)\(2) provides in pertinent part that a judge
“may designate a magistrate judge to serve as a special miaster
pursuant to the applicable provisions of this title and the
Federal Rules of Civil Procedure” without the parties’
consent. The applicable Federal Rule is Rule 53(b), which
provides for references to special masters:
A reference to a master shall de the exception and not
the rule. In actions to be tried by a jury, a reference
shali be made only when the issues are complicated;
in actions to be tried without a jury, save in matters of
account and of difficult computation of damages, a
reference shall be made only upon a showing that
some exceptional condition requires it.'°
The non-jury standard of review applies here. Thus, unless
the proceeding referred to the Magistrate Judge in this case is
characterized as part of a “difficult computation of damages,”
the reference can only be justified upon a showing that some
“exceptional condition” required it.
Beazer makes no argument that any “exceptional
condition” exists in this case, nor does Beazer argue that the
Magistrate Judge performed any difficult computations.
Rather, Beazer contends that the referral was proper because
the equitable allocation proceeding conducted by the
Magistrate Judge was a “predicate” to a “difficult
computation of damages” performed by the District Court.
Beazer’s expansive reading of Rule 53(b) is at odds with the
Supreme Court's restrictive interpretation.
'® Both § 636(b)(2) and Rule 53(b) provide that a magistrate judge
may be designated as a special master without regard to Rule
5Xb)’s limitations upon consent of the parties. Because Mead did
not consent, this exception is inapplicable.
25a
In La Buy v. Howes Leather Co. , 352 U.S. 249, 256, 259,
1 L. Ed. 2d 290, 77 S. Ct. 309 (1957), the Court affirmed the
appellate court’s issuance of a writ of mandamus compelling
the District Court io vacate its order referring essentially the
entirety of two complex antitrust cases to a special master.
The Court noted that while masters could “aid judges” in the
performance of specific duties, they could not be permitted to
“displace the court.” /d. at 256; see also Prudential Ins. Co.
v. United States Gypsum Co. , 991 F.2d 1080, 1086 (3d Cir.
1993) (“A district court has no discretion to delegate its
adjudicatory responsibility in favor of a decision maker who
has not been appointed by the President and confirmed by the
Senate.”) (citing La Buy); In re Bituminous Coal Operators’
Ass'n. 292 U.S. App. D.C. 309, 949 F.2d 1165, 1168 (D.C.
Cir. 1991) (“Rule 53 . . . authorizes the appointment of
special masters to assist, not to replace, the adjudicator,
whether judge or jury, constitutionally indicated for federal
court litigation”). The Court found that the references at issue
“amounted to little less than an abdication of the judicial
function depriving the parties of a trial before the court on the
basic issues involved in the litigation.” La Buy, 352 U.S. at
256." The Court acknowledged, however, that difficult
'® The Court also rejected the judge’s claim that docket congestion,
complexity, and length of time necessary for trial constituted
“exceptional circumstances” justifying the reference. Jd. at 258-59;
see also Charles Alan Wright & Arthur R. Miller, 9A Federal
Practice and Procedure § 2605, at 662 (2d ed. 1994) (noting that
the Court rejected “the three most obvious matters” that might be
thought to constitute “exceptional conditions”); Jn re Armco, Inc.,
770 F.2d 103, 105 (8th Cir. 1985) (“Beyond matters of account,
difficult computation of damages, and unusual discovery, it is
difficult to conceive of a reference of a nonjury case that will meet
the rigid standards of the La Buy decision.”) (internal quotations
omitted).
26a
damages computations could sometimes be referred to a
master without the parties’ consent. “The detailed accounting
required to determine the damages suffered by each plaintiff
might be referred to a master after the court has determined
the over-all liability of defendants, provided the circumstances
indicate that the use of the court's time is not warranted in
receiving the proof and making the tabulation.” /d. at 259.
Accountings and other damages computations may be
referred without the parties’ consent because they generally
do not call for any peculiar judicial talent or insight. See 9A
Charles Alan Wright & Arthur R. Miller, Federal Practice
and Procedure § 2605 at 655-66 (2d ed. 1994). Equitable
apportionment, on the other hand, is a quintessentially judicial
endeavor. CERCLA’s contribution provision authorizes the
court to “allocate response costs among liable parties using
such equitable factors as the court determines are
appropriate.” 42 U.S.C. § 9613(f)(1). In a given case, “a
court may consider several factors or a few, depending on the
totality of the circumstances and equitable considerations.”
New Jersey Turnpike Authority v. PPG Industries, Inc., 197
F.3d 96, 104 (3d Cir. 1999) (citation omitted). This flexible
inquiry involves discretion, judgment, and legal reasoning
that simply is not connoted by the phrase “difficult
computation of damages.” This case provides a good
illustration of this point.
The Magistrate Judge's proposed allocation turned chiefly
on three factors: 1) volume of waste should be the pre-
eminent equitable factor given CERCLA’s over-arching
“polluter-pays” principle; 2) Mead was responsible for
approximately 90% of the waste; and 3) Mead was
nonetheless entitled to a reduction in its share based on the
parties’ intent that Mead would not be responsible for future
environmental liabilities. In weighing these factors, only the
27a
second is reasonably related to a “computation of damages.”
The other two turn on questions of law, policy, equity, and
contractual intent. Further, even with respect to weighing the
second factor, the computations performed by the Magistrate
Judge were not “difficult” - they entailed elementary
subtraction and addition of percentages. The Magistrate Judge
did not crunch any numbers to determine that Mead was
responsible for 90% of the waste on the site; rather, he
decided which expert's percentage estimates were more
convincing. In fact, even this decision largely turned on a
legal question: should Beazer be able to recover all of its
response costs based on an AOC ordered under the Resource
Conservation and Recovery Act that required investigation
and monitoring of the entire industrial site, or should it be
limited, as Mead’s chief expert contended, to costs that would
have been assessed under a more modest hypothetical AOC
issued pursuant to CERCLA? Thus, the issues referred to the
Magistrate Judge here were not akin to a complicated
accounting or difficult damages calculation. Rather, they were
foremost among the “basic issues” to be tried, and the District
Court's referral of those issues without the parties’ consent
was “an abdication of the judicial function.” La Buy, 352
U.S. at 256.
Beazer also argues that our opinion in Beazer / ended the
“liability phase” of this case, that everything that occurred on
remand constituted the “damages phase,” and therefore
everything on remand could have been properly referred to a
master. This formalistic argument is inconsistent with La
Buy's reasoning. In United States v. Microsoft Corp., 331
U.S. App. D.C. 121, 147 F.3d 935, 954-55 (D.C. Cir.
1998), the D.C. Circuit Court of Appeals vacated a reference
to a special master to determine the parties’ rights under a
complex consent decree. Seeking to uphold the reference, the
Department of Justice invoked the “well-established tradition”
28a
allowing special masters to oversee compliance during the
remedial phase of litigation, arguing that the reference to
oversee implementation of the consent decree fell squarely
within that tradition. /d. at 954. (citations omitted). The court
rejected this position, holding that “the matters referred to the
master are no more “remedial” than would be those of any
total referral of a contract case. The concern about
nonconsensual references turns on the determination of rights,
not on a formalistic division of the juridical universe into pre-
trial, trial and post-trial. It is for this reason that special
masters may not decide dispositive pretrial motions.” /d.
(citation omitted). Similarly, the reference here involved a
complex and delicate determination of equities.
We note, however, that there is some support for Beazer’s
position. In United States v. Conservation Chemical Co. , 106
F.R.D. 210, 216 (W.D. Mo. 1985), the District Court
referred all pretrial and discovery matters as well as the trial
on the merits to a special master without the parties’ consent.
The reference included “the authority to hold hearings and
issue recommendations on the claims for . . . apportionment
of costs.” /d. Predictably, the Eighth Circuit Court of Appeals
held that no “exceptional condition” justified the District
Court's sweeping reference. In re Armco, 770 F.2d 103, 105
(8th Cir. 1985). But then, without explaining its reasoning,
the court affirmed ail aspects of the reference except for the
trial on the liability issues. Thus, the court affirmed reference
of all post-liability damages proceedings. /d. Although not
explicitly stated, this reference necessarily covered any
equitable allocation proceedings that might be necessary to
resolve contribution claims brought by any of the liable
patties.
The Armco Court’s unexplained decision to uphold the
reference of dispositive matters without any showing of
29a
exceptional conditions has been met with perplexity by two
other circuit courts. Stauble v. Warrob, Inc., 977 F.2d 690,
696 (1st Cir. 1992) (noting that the court was “baffled” by the
Armco Court's decision to authorize reference of dispositive
pre-trial motions); /n re United States, 816 F.2d 1083, 1091
(6th Cir. 1987) (noting the court’s inability “to follow the
[Armco] Court’s reasoning” on this issue). We also do not
consider Armco to be persuasive authority. It is possible that
the Armco Court was overly solicitous towards the District
Court’s Rule 53(b) reference because it perceived that the
District Court required an extraordinary degree of flexibility
to handle an enormous CERCLA case involving more than
250 parties. See 9A Wright & Miller, Federal Practice and
Procedure § 2605, at 666 (“Despite the restrictive standard
set out in the La Buy case, the actual utilization of masters
under Rule 53(b) in the past two decades has been quite
lively[,] undoubtedly [in response to} the rapid growth of
complex litigation in the federal courts, particularly in cases
requiring significant scientific and technical knov"'«dge, [and]
management skills”). In contrast, this case does not present
similar administrative challenges -- there are only three
parties, and one, KII, has played only a minor role in the
proceedings.
Accordingly, we reject Beazer’s contention that the
District Court could have designated the Magistrate Judge to
hear the equitable allocation issue as a special master without
Mead’s consent.
3. Equitable allocation cannot be referred under the
“additional duties” clause.
Finally , we reject Beazer’s suggestion that the referral was
proper under the “additional duties” clause. 28 U.S.C.
§ 636(b)(3). This clause covers only subsidiary matters in the
30a
absence of the parties’ consent, and equitable allocation is
central, rather than subsidiary, to a CERCLA contribution
action.
The parties’ consent or lack thereof is a key factor in
deciding whether a referral is authorized under the “additional
duties” clause. In Gomez v. United States, 490 U.S. 858,
876, 104 L. Ed. 2d 923, 109 S. Ct. 2237 (1989), the Court
held that this clause did not authorize magistrate judges to
supervise voir dire proceedings in a criminal case over a
defendant’s objection. However, in Peretz v. United States,
501 U.S. 923, 932-36, 115 L. Ed. 2d 808, 111 S. Ct. 2661
(1991), the Court held that the “additional duties” clause did
authorize the reference of voir dire in a criminal case where
the defendant consented to the reference. The Court reasoned
that the scope of the clause varied significantly according to
whether the parties’ consented to the reference. See Peretz,
501 U.S. at 931-33; Gomez, 490 U.S. at 870-71. As the
Court explained in Gomez and reiterated in Peretz, the scope
of § 636(b)(3)’s residuary clause had to be interpreted in light
of the duties specifically authorized in the other sections of
the Act. Peretz, 501 U.S. at 930-31 (citing Gomez, 490 U.S.
at 864). The Court explained that “the duties that a magistrate
judge may perform over the parties’ objections are generally
subsidiary matters not comparable to supervision of jury
selection. However, with the parties’ consent, a district judge
may delegate to a magistrate judge supervision of entire civil
and misdemeanor trials. These duties are comparable in
responsibility and importance to presiding over voir dire ata
felony trial.” Peretz, 501 U.S. at 932.
Thus, in the absence of Mead’s consent, the referral
would only be authorized under § 636(b)(3) if we
characterized the equitable allocation proceeding as a
“subsidiary matter.” See Charles Alan Wright et al, 12
3la
Federal Practice & Procedure § 3068.1 at 329 (2d ed. 1997).
As explained in the previous two sections, equitable allocation
is central to Beazer’s CERCLA action, not subsidiary thereto.
Accordingly, the referral could not be authorized under the
“additional duties” clause over Mead's objection.
This conclusion is consistent with Congressional intent. As
the Court in Peretz explained, “the Act is designed to relieve
the district courts of certain subordinate duties that often
distract the courts from more important matters.” 501 U.S. at
934. In support of this assessment, the Court cited several
statements from the legislative history of the Act and its
various amendments. See, e.g., H.R. Rep. no. 94-1609, p. 7
(1976) (stating that a magistrate judge is to “assist the district
judge in a variety of pretrial and preliminary matters thereby
facilitating the ultimate and final exercise of the adjudicatory
function at the trial of the case”). Equitable allocation is at the
very core of a CERCLA contribution action and is not a
preliminary or subordinate matter.
4. Remand is required notwithstanding the District
Court’s purported de novo review.
Beazer contends, and the District Court reasoned, that any
flaw in the referral is corrected by the District Court’s
purported de novo review of the Magistrate Judge’s proposed
equitable allocation. This argument is unavailing.
First, as noted above, a magistrate judge’s authority is
jurisdictional. Without the parties’ consent, a magistrate judge
cannot conduct a trial or any part thereof, see 28 U.S.C.
§ 636(c)(1) (“upon the consent of the parties, a. . .
magistrate judge . . . may conduct any or all proceedings in
a jury or nonjery civil matter”), and “the mere existence of
a recommendation [and accompanying de novo review] will
32a
not change a full trial [or any part thereof] into a pre-trial
motion.” Jeffrey S. v. State Bd. of Educ. , 896 F.2d 507, 512
n.17 (11th Cir. 1990) (citing Hall v. Sharpe, 812 F.2d 644,
647 (11th Cir. 1987)). Second, § 636(b)(1)(B) provides that
certain dispositive pre-trial motions may be referred to a
magistrate judge, but the magistrate judge's proposal must be
reviewed de novo by the court. Mead correctly argues that
this provision would be meaningless if no specific statutory
delegation were necessary se long as the District Court
conducted a de novo review. Third, the District Court’s error
cannot be considered harmless no matter how admirable the
Magistrate Judge’s efforts may have been. See United States
v. Ruiz-Rodriguez, 277 F.3d 1281, 1293 n.17 (11th Cir.
2002) (“Harmless error analysis does not apply when a
magistrate judge lacks the power to act.”). Since the
Magistrate Judge lacked the power to conduct the equitable
allocation proceeding in this case, there was nothing for the
District Court to review."”
Although the issue of appropriate remedy is less settled
where the flawed referral is to a special master (or a
magistrate judge acting as a special master) rather than to a
magistrate judge qua magistrate judge, remand for a new trial
is the proper remedy even if the District Court’s referral
could be re-characterized as a designation of the Magistrate
Judge to serve as a special master. First, while at least two
courts of appeals have suggested that a remand for a new trial
may not be required where the district court reviews the
master’s report de novo, Sierra Club v. Browner, 257 F.3d
444, 447 (9th Cir. 2001) (vacating reference but declining to
'’ Because we conclude that the District Court could not save the
flawed referral no matter what level of review it conducted, we
need not consider whether it actually performed a de novo review
of the Magistrate Judge’s report and recommendation.
33a
decide whether de novo review by the district judge could
save a flawed reference), Stauble, 977 F.2d at 698 n.12
(same), we rejected a similar argument in Prudential. The
C strict Court in Prudential had stated that the reference was
limited to pre-trial motions, and that it would review every
conclusion of law proposed by the special master de novo.
991 F.2d at 1086 n.11. We reasoned, however, that de novo
review of legal matters could not save an improper referral
because such review was always available regardless of
whether the referral violated Rule 53(b). /d. That is, if de
novo review of legal issues cured referrals made in violation
of Rule 53(b), that provision would be meaningless.
Furthermore, the referral in this case encompassed
questions of fact as well as questions of law, and Rule
53(e)(2) provides that in non-jury trials the district court
“shall accept the master’s findings of fact unless clearly
erroneous.” Fed. R. Civ. Pro. 53(e)(2) (emphasis added);
Apex Fountain Sales, Inc. v. Kleinfeld, 818 F.2d 1089, 1097
(3d Cir. 1987) (noting that review of master’s legal
conclusions is plenary, but that district court must accept
master’s factual findings unless clearly erroneous). Relying on
this provision, the court in Microsoft rejected the argument
that de novo review can save an improper referral because the
master’s factual conclusions cannot be reviewed de novo
under Rule 53(e)(2). 147 F.3d at 955; see also Sierra Club,
257 F.3d at 448 (suggesting but not reaching same
conclusion). In this case the District Court claims that it
reviewed both the Magistrate Judge’s factual findings and its
legal conclusions de novo. This is inconsistent with Rule
53(e)(2), and a district court cannot cure one violation of Rule
53 by committing another. Finally, it would be inappropriate
to re-characterize the referral as a flawed designation of a
special master solely to avoid the remand required by case
law construing other provisions of the Magistrates Act.
34a
Accordingly, this case must be remanded for a new
equitable allocation proceeding before the District Court. We
note that Beazer’s contribution action is now in its fourteenth
year and will likely enjoy several more birthdays, partly
because our reversal today will require the parties to retread
well-worn ground. In an attempt to avoid further duplicative
litigation and speed this case towards its conclusion, we take
this opportunity to resolve two other issues raised by the
parties on appeal.
C. The District Court’s Equitable Allocation Was
Erroneous.
First, we agree with Mead that the District Court
committed legal error, and therefore abused its discretion, in
prioritizing the parties’ respective contributions of waste at
the Woodward Coke Plant in determining the appropriate
allocation of Beazer’s response costs."* The District Court
found that the parties to the 1974 sale intended that Mead
would not bear any environmental liability following the 1974
sale, but reduced Mead’s equitable share by only 20% in
recognition of this and related findings that we refer to here
'’ A district court's allocation of CERCLA response costs in a
contribution action is reviewed for abuse of discretion. See, e.g.,
Kalamazoo River Study Group v. Rockwell Intern. Corp., 274 F.3d
1043, 1047 (6th Cir. 2001). An abuse of discretion occurs when
“the district court's decision rests upon a clearly erroneous finding
of fact, an errant conclusion of law or an improper application of
law to fact.” International Union v. Mack Trucks, Inc., 820 F.2d
91, 95 (3d Cir. 1987).
35a
as the “purchase agreement factors,” all of which favor
Mead.”
The District Court's decision to prioritize the volume of
waste over the purchase agreement factors appears to follow
two related rationales explicitly developed in the Magistrate
Judge’s Report and Recommendation. The Magisirate Judge
concluded that “CERCLA is premised upon the policy that the
‘polluter pays.’” Thus, the Magistrate Judge began from the
premise that cach party's equitable share should be driven by
its respective contribution of waste. The Magistrate Judge
deviated only slightly from this premise to account for the
equitable factors surrounding the 1974 sale. The Magistrate
Judge also concluded that it would be inconsistent with our
decision in Beazer / to allocate “all or even most” of the
response costs to Mead. The District Court somewhat
ambiguously adopted each rationale. However, neither Beazer
I, nor CERCLA itself, requires that the parties’ intent to shift
environmental risk be subordinated to the “polluter pays”
principle - as long as someone pays. Therefore, the District
Court's allocation, which was based in part on its agreement
'* The District Court found that the parties to the 1974 agreement
“intended that Mead be able to ‘walk away’ from the site, i.e., that
Mead would not indemnify [KCI, Beazer’s predecessor] for any
future costs at the site for any reason, including environmental
response costs.” The District Court also found that KCI purchased
the property pursuant to the doctrine of caveat emptor, that the
purchase agreement contained an “as is” clause, that KCI was “well
aware of the environmental condition of the site” after performing
a full inspection prior to purchase, and that “reasonable parties
negotiating the sale of an industrial site in Alabama in 1974 would
expect that the seller would not be held liable for any future
environmental costs.”
36a
with the Magistrate Judge's flawed reasoning, was an abuse
of discretion.
First, the Magistrate Judge’s and District Court's
prioritization of the “polluter pays” principle in equitable
allocation proceedings is inconsistent with CERCLA’s
courts to “allocate response costs among liable parties using
such equitable factors as the court determines are
appropriate.” 42 U.S.C. § 9613(f)(1). Courts examining this
language and its history have concluded that Congress
intended to grant the district courts significant flexibility in
determining equitable allocations of response costs, without
requiring the courts to prioritize, much less consider, any
specific factor. In a leading case, the Seventh Circuit Court of
Appeals explained that “the language of section 9613(f)
clearly indicates Congress’s intent to allow courts to
determine what factors should be considered in their own
discretion without requiring a court to consider any particular
list of factors.” Environmental Transportation Systems, Inc.
v. ENSCO, 969 F.2d 503, 508 (7th Cir. 1992); see also
United States v. R.W. Meyer, Inc., 932 F.2d 568, 576-77 (6th
Cir. 1991) (reasoning that section 9613(f)(1)’s language
“confirms the legislative intent to grant courts flexibility in
exercising their discretion”) (citations to legislative history
omitted). As we have held, “a court may consider several
factors or a few, depending on the totality of the
circumstances.” New Jersey Turnpike Authority v. PPG
Industries, Inc., 197 F.3d 96, 104 (3d Cir. 1999) (citation
omitted).
Accordingly, the “polluter pays” principle has no
canonical or transcendent importance under § 9613(f)(1); it is
certainly not the “primary policy” of contribution claims, as
implied by the District Court. It is simply one of many factors
37a
that may or may not bear on a given equitable allocation
determination. See Kerr-McGee, 14 F.3d at 326 (listing
possible factors). Specifically, there is no basis in CERCLA’s
text or history for prioritizing a priori the parties’ relative
contributions of waste over their contractual intent to allocate
environmental liability among themselves. To the contrary,
CERCLA expressly authorizes private indemnity agreements,
see 42 U.S.C. § 9607(e)(1); Fisher Development Co. v. Boise
Cascade Corp. , 37 F.3d 104, 110 (3d Cir. 1994) (finding in
§ 107(e)(1) “a policy favoring private ordering of ultimate
risk distribution”), and the District Court’s insistence on
elevating relative waste contribution is fundamentally
inconsistent with CERCLA’s policy of favoring private
indemnity agreements.
Second, Beazer | dealt with the legal interpretation of
Paragraph 4(c). As a matter of equity, however, the intent of
the parties, which is manifested by their actions and in the
written agreement, can be taken into account - no matter what
our legal conclusion was in Beazer I. Beazer I does not tip the
equitable scales one way or another. In Beazer I, we
determined that the 1974 agreement was governed by
Alabama law, 34 F.3d at 211-15, and that indemnification
agreements are enforceable under Alabama law only if they
contain “a plain and unambiguous expression of intent to
cover the cost of the liability in question.” /d. at 216.
Applying this standard, we concluded that “nothing in this
agreement demonstrates a clear and unambiguous intent to
transfer all CERCLA liability to [KCI].” /d. at 219. The
Magistrate !..‘%e correctly reasoned that Beazer ] reached no
conclusior re»,arding the parties’ actual intent; only that, as a
matter of .labama law, the contract did not contain a
sufficiently clear expression that KCI would indemnify Mead
against all environmental liability associated with the site. See
id. Thus, the Magistrate Judge concluded that “there is no
38a
inherent inconsistency in the ruling made on appeal and a
decision by this court that, as a matter of equity, the parties’
intentions concerning indemnity, to the extent they can be
divined from both the document and any other evidence
offered by the parties, should be considered in equitable
allocation.””
However, the Magistrate Judge further reasoned that
shifting all or most of the response costs to Beazer based on
the purchase agreement factors “would give the agreement,
found legally insufficient under Alabama law, the force of
* The Magistrate Judge properly cited Kerr-McGee Chemical Corp.
v. Lefton lron & Metal Co., 14 F.3d 321 (7th Cir. 1994) in support
of this distinction between legal and equitable rulings. In that case,
the District Court concluded that the relevant indemnification
provision was insufficiently clear as a matter of Illinois law, id. at
327, and consequently “ignored the [provision] when allocating
responsibility for cleanup costs.” /d. at 326. In dictum, the Seventh
Circuit concluded that this was error, reasoning that “although
contractual arrangements between parties are mot necessarily
determinative of statutory liability, Lefton’s intent to indemnify
Kerr-McGee- should be considered in the allocation of cleanup
costs.” /d. The court further explained that the fact that “Lefton --
with knowledge of the creosote on the site -- agreed that it took the
property “as is” and would assume future liabilities resulting from
that pollution is certainly a significant circumstance.” /d. The court
noted that “the fact that Kerr-McGee’s predecessor Moss-American
was the source of most of the pollution at the site may also weigh
in the “ourt’s analysis; this however is not reason to ignore other
relevant considerations.” /d. The issue of the appropriate weight to
be accorded to each factor was not before the court, and the court
had no occasion to suggest an answer to this question since it
ultimately concluded that the indemnification provision did cover
CERCLA liability, so no equitable allocation proceeding was
required. /d. at 327-28.
39a
law, and would place [the District] Court’s decision at odds
with the ruling made by the Court of Appeals.” This
conclusion does not follow from Beazer /.
The District Court, however, rejected Mead’s contention
that the Magistrate Judge had misinterpreted Beazer /. The
court quoted from its penultimate paragraph, seemingly for
the proposition that Mead’s “fair share” of Beazer’s response
costs should be greatly influenced, if not largely determined,
by Mead’s relative contributions of hazardous waste to the
site. The penultimate paragraph provides:
Our refusal to construe Paragraph 4(c) as a clear
promise by Beazer to indemnify Mead against
CERCLA response costs leaves both Beazer and Mead
responsible for their fair share of the cleanup costs
associated with the Coke Plant. That result reinforces
CERCLA policy. “Congress enacted CERCLA, a
complex piece of legislation ... to force polluters to
pay for costs associated with remedying their
pollution.” United States v. Alcan Aluminum Corp.
964 F.2d 252, 258 (3d Cir.1992).
34 F.3d at 219. Apparentiy, the District Court considered this
quotation from Alcan Aluminum to support (or perhaps
require) elevating the “polluter pays” principle above al! other
equitable factors.
The quoted paragraph does not warrant such significance.
The first two sentences uncontroversially state that holding
Mead and Beazer responsible for their fair share of cleanup
costs reinforces CERCLA policy. /d. at 219. The next
sentence, the quotation from Alcan Aluminum, is to the effect
that Congress intended that polluters pay for the costs of
remedying their pollution. /d. (quoting Alcan, 964 F.2d at
40a
258).”" The District Court apparently inferred from the
juxtaposition of these statements that each party’s “fair share”
must be more or less rigidly tied to its share of pollution at
the site. Such an interpretation is, however, fundamentally at
odds vith CERCLA’s contribution provision as well as with
CERCLA’s policy of favoring private indemnity agreements.
We note, moreover, that in the footnote at the end of the -
penultimate paragraph, the Beazer ] Court quoted the
“equitable factors” language of section 9607(a) and went on
to note that on remand, “the trial court will have to revisit the
parties’ contribution claims and correspondingly apportion
liability for attendant CERCLA response costs.” This
direction is significantly broader than a direction that liability
should be apportioned to reflect each party’s share of
pollution at the site - which the Beazer | Court could easily
have stated if that were its intent.
It is clear, then, that the District Court erred in
eliminating significant consideration of the parties’ intent in
its equitable allocation. See Kerr-McGee, 14 F.3d 321, 326
(“Although contractual arrangements between parties are not
necessarily determinative of statutory liability, Lefton’s intent
to indemnif’ Kerr-McGee should be considered in the
allocation of cleanup costs.”). Moreover, to the extent that the
court felt itself bound by the “polluter pays” principle or by
our oblique reference to that principle in Beazer I, that
conclusion was unwarranted. Because we conclude that the
District Court’s ultimate allocation of Beazer’s costs was
?! Alcan Aluminum had nothing to do with contribution actions
under § 113(f); the issues considered in Alcan Aluminum bore on
Alcan’s initial liability under CERCLA and to what degree it was
required to reimburse the government for clean-up costs. See 964
F.2d at 259, 267-71.
4la
predicated in large part on this error, that conclusion was an
abuse of discretion.
Mead would have us go further and prescribe that the
purchase agreement factors must be prioritized on remand,
but we think this is inappropriate. CERCLA places both the
selection and weighing of equitable factors in the sound
discretion of the district court, not the appellate court.
Accordingly, we leave these matters for the District Court to
decide on its own on remand, unfettered by the legal errors
discussed above.
D. Any Declaratory Judgment Should Contain a
Contingency Provision.
Finally, we are sympathetic with Mead’s contention that
the District Cowrt’s declaratory judgment fixing the parties’
equitable shares of future response costs should contain a
provision authorizing the parties to re-litigate the District
Court’s equitable allocation if new facts or future events
render the current division inequitable. For example, Mead
argues that once the investigatory phase of the case concludes
and the remedial phase ensues, the District Court's equitable
allocation would no longer be fair if any required remediation
is “primarily or exclusively directed to those areas of the Site
where Beazer is responsible for the majority of the
contamination.”
Because the equitable allocation proceeding in this case
must be conducted again on remand by the District Court, the
declaratory judgment already entered in this case is null and
void. If and when the District Court enters a new declaratory
judgment covering future costs, however, we agree with
Mead that the judgment should contain some kind of provision
authorizing the parties to re-litigate the allocation of those
42a
costs for good cause shown in response to new events or new
evidence that would reasonably bear upon the equity of the
allocation. Such contingency provisions are generally favored
in CERCLA contribution actions, see United States v. Davis,
261 F.3d 1, 45 (1st Cir. 2001) (quoting contingency provision
imposed by district court); Acushnet Co. v. Coaters, Inc. , 972
F. Supp. 41, 69 (D. Mass. 1997); Boeing Co. v. Cascade
Corp., 920 F. Supp. 1121, 1142 (D. Or. 1996), and we agree
with the wisdom of those cases. We leave the specific design
of the provision to the discretion of the District Court, with
the help of the parties. We recognize Beazer’s concern that
Mead might use such a provision to re-litigate issues that will
have already been decided in the equitable allocation
proceeding to be conducted on remand, but we think this
concern can be adequately addressed by application of the
‘law of the case’ doctrine.”
VI.Conclusion
For the reasons stated above, we will reverse the
judgments of the District Court and remand this action for
further proceedings consistent with this opinion.
2 Finally, contrary to Beazer’s suggestion, Federal Rule of Civil
Procedure 60(b) is insufficient to protect Mead’s rights if new
events render the initial allocation inequitable because motions
based on new evidence brought under that rule must be made “not
more than one year” after the judgment was entered.
43a
IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF
PENNSYLVANIA
[Filed October 8, 2002]
Civil Action No. 91-408
BEAZER EAST, INC.,
Plaintiff,
Counterdefendant,
v.
THE MEAD CORPORATION,
Defendant,
Counterclaimant,
Third-Party Plaintiff,
Third-Party Counterdefendant,
v.
KOPPERS INDUSTRIES, INC.,
Third-Party Defendant,
Third-Party Counterdefendant.
ee ee ee ee ee
44a
ORDER OF COURT
AND NOW, to-wit, this 8" day of October, 2002, IT IS
ORDERED that a declaratory judgment be, and the same
hereby is, issued in this civil action incorporating by
reference the Opinion and Order of this court entered on
August 29, 2002 (Document 345), and all other substantive
rulings of this court in this civil action including, but not
limited to, specifically its rulings and orders declaring
defendant, The Mead Corporation, (“Mead”) liable to
plaintiff, Beazer East, Inc., (“Beazer”) for 67.5% of all of
Beazer’s necessary response costs incurred consistent with the
National Contingency Plan (“NCP”) at the Woodward Coke
Plant, located in Dolomite, Alabama.
IT FURTHER IS ORDERED that Beazer timely shall
submit invoices for such costs to Mead for review and
payment; and, in the event that Mead has objections to the
costs submitted by Beazer, based on challenges to the
necessity and/or NCP-consistency of those costs, those
objections shall be filed by Mead with the court for
resolution. Mead shall have forty-five (45) days from the
receipt of Beazer’s Submission to Mead of the costs which
Beazer deems to be recoverable response costs within which
to file with the court Mead’s objections to the recoverability
of such costs along with a brief in support thereof; Beazer
shall have thirty (30) days after receipt of Mead’s objections
to file with the court Beazer’s response thereto and brief in
support thereof.
/s/
Gustave Diamond
United States District Judge
45a
Mark D. Shepard, Esq.
D. Matthew Jameson Ill, Esq.
Melissa L. Evans, Esq.
Babst Calland Clements & Zomnir, P.C.
Two Gateway Center, Eighth Floor
Pittsburgh, PA 15222
Jill M. Blundon, Esq.
Beazer East, Inc.
One Oxford Centre, Suite 3000
Pittsburgh, PA 15219
Van Carson, Esq.
Squire, Sanders & Dempsey L.L.P.
4900 Key Tower
127 Public Square
Cleveland, OH 44114, 1304
Charles R. McElwee, Ii, Esq.
Squire, Sanders & Dempsey L..L.P.
One Maritime Plaza, Suite 300
San Francisco, CA 94111
David E. White, Esq.
Thorp, Reed & Armstrong
One Riverfront Center
Pittsburgh, PA 15222
46a
IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF
PENNSYLVANIA
Civil Action No. 91-408
[Dated September 19, 2002]
BEAZER EAST, INC., )
Plaintiff, )
)
v. )
)
MEAD CORPORATION, )
Defendant. )
)
ORDER OF COURT
AND NOW, to-wit, this 19" day of September, 2002, IT
IS ORDERED that on or before September 26, 2002, counsel
for the plaintiff will provide the court and counsel for the
defendant with a proposed declaratory judgment to be entered
in this case along with a brief memorandum in support
thereof; and,
IT FURTHER IS ORDERED that on or before October
3, 2002, counsel for the defendant will provide the court and
counsel for the plaintiff with defendant’s response to
plaintiffs submission and, if appropriate, defendant’s
proposed declaratory judgment along with a brief
memorandum in support of its position.
/s/
Gustave Diamond
47a
United States District Judge
48a
IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF
PENNSYLVANIA
[Filed September 17, 2002]
Civil Action No. 91-408
BEAZER EAST, INC.,
Plaintiff,
V.
THE MEAD CORPORATION,
Defendant.
ed
ORDER OF COURT
AND NOW, this 17th day of September, 2002, in
accordance with the stipulation of plaintiff, Beazer East, Inc.
and defendant, The Mead Corporation (Document No. 348)
approved by the court on September 16, 2002, IT IS
ORDERED that prejudgment interest in the amount of
$1,538,164.03 be, and the same hereby is, added to the
judgment in favor of Beazer East, Inc. and against The Mead
Corporation entered by the court on the 29th day of August,
2002.
/s/
Gustave Diamond
United States District Judge
49a
CC: Mark D. Shepard, Esq.
D. Matthew Jamison III, Esq.
Melissa L. Evans, Esq.
Babst, Calland, Clements & Zomnir
Two Gateway Center, Eighth Floor
Pittsburgh, PA 15222
George P. Faines, Esq.
John H. Bingler, Jr., Esq.
Thorp, Reed & Armstrong-
One Oxford Centre, 14" Floor
Pittsburgh, PA 15219-2402
Alan M. Wiseman, Esq.
Thomas A. Isaacson, Esq.
Howrey & Simon
299 Pennsylvania Avenue, N.W.
Washington, D.C. 20004-2402
Van Carson, Esq.
Charles R. McElwee, II, Esq.
Squire, Sanders & Dempsey
127 Public Square
4900 Key Tower
Cleveland, OH 44114-1304
John E. Frey, Esq.
Wildman, Harrold, Allen & Dixon
225 West Wacker Drive
30" Floor
Chicago, IL 60606-1225
50a
IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT
OF PENNSYLVANIA
{Filed August 29, 2002]
Civil Action No. 91-408
BEAZER EAST, INC., )
)
Plaintiff, )
)
v. )
)
THE MEAD CORPORATION, )
)
Defendant. )
)
ORDER OF COURT
AND NOW, this 29" day of August, 2002, in accordance
with the opinion filed this day, IT IS ORDERED that
judgment be, and the same hereby is, entered in favor of
Beazer East, Inc., and against The Mead Corporation in the
amount of $3,243,467.80. This award is subject to the
addition of prejudgment interest as calculated in accordance
with the court’s rulings;
IT FURTHER IS ORDERED that counsel for the parties
shall apply the-eourt’s rulings on prejudgment interest to the
response costs awarded by the court and stipulate to the
applicable amount of prejudgment interest on or before
September 11, 2002; and,
5la
IT FURTHER IS ORDERED that on or before September
11, 2002, each party shall show cause why a declaration of
liability, in accordance with the findings and rulings of the
court to date will not provide the parties with adequate relief
for the response costs incurred and to be incurred in
implementing the administrative order of consent.
/s/
Gustave Diamond
United States District Judge
52a
IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT
OF PENNSYLVANIA
Civil Action No. 91-408
[Filed August 29, 2002]
BEAZER EAST, INC.,
Plaintiff,
v.
THE MEAD CORPORATION,
Defendant.
ed
OPINION
DIAMOND, DJ.
Beazer East, Inc. (“Beazer”) commenced this action in
March of 1991 under the Comprehensive Environmental
Response, Compensation and Liability Act (“CERCLA”)
seeking contribution for expenses that have been and will in
the future be incurred in cleaning up the Woodward Coke
Plant, an industrial site near Dolomite, Alabama. The site
consists of approximately 170 acres. Coke used in the
steelmaking industry was produced at an 83-acre plant on the
site from 1911 unti! 1998 when the plant was deactivated. The
plant was demolished in 1999. Beazer seeks recovery against
the Mead Corporation (“Mead”) as a prior owner and
53a
operator of the site from 1911 to 1974. Mead asserted a
counterclaim against Beazer as prior owner and operator of
the site (1974 to 1988) and joined the current owner of a
portion of the site and operator of the plant from 1988 to
1998, Koppers Industries, Inc. (“KII”). Mead’s third-party
claim against KII effectively was resolved in a prior phase of
the litigation that determined each party’s proportional
responsibility for Beazer’s recoverable response costs. In the
current phase of the litigation Beazer and Mead dispute which
of Beazer’s specifically claimed environmental costs incurred
through December 31, 1999, properly are recoverable in a
contribution, action under 42 U.S.C. §9613(f). Presently
before the court are Beazer and Mead’s revised proposed
findings of fact and conclusions of law submitted after a
three-day non-jury trial commencing on February 4, 2002.
For the reasons set forth below, the court will enter judgment
in Beazer’s favor in accordance with the rulings rendered
herein and direct the parties to stipulate to the applicable
amount of prejudgment interest under the court’s rulings.
The procedural history of this eleven year old complex
CERCLA action is protracted and will only be briefly
summarized here in light of the limited issues remaining for
resolution. The first phase of the litigation concerned the
parties’ respective rights and obiigations under the 1974 asset
purchase agreement through which Beazer acquired the site
from Mead; The parties filed cross-motions for summary
judgment based on the indemnity provisions of that agreement
and this court granted summary judgment in Mead’s favor.
Beazer appealed. The United States Court of Appeals for the
Third Circuit reversed and remanded for further proceedings,
explaining that the failure of the asset purchase agreement to
require either party to indemnify the other left “both Beazer
and Mead responsible for their fair share of the clean-up costs
associated with the Coke Plant.” Beazer East, Inc. v. Mead
54a
Corp., 34 F.3d 206, 219 (3d Cir. 1994). The court further
explained:
On remand, the trial court will have to revisit the
parties’ contribution claims and correspondingly
apportion liability for the attendant CERCLA response
costs.
Id. at 219 n.10. During this phase of the litigation Mead was
found to be a “responsible party” within the meaning of 42
U.S.C. §9607(a) and thus “for the purposes of CERCLA
liability.” Id. at 218, 219 n.10.
Following the return of the action to this court it was
remanded to Magistrate Judge Benson for further pretrial
proceedings. After considering a report and recommendation
and objections thereto, this court entered a memorandum
order on July 8, 1996, granting in part and denying part
Mead’s motion for partial summary judgment and referring
the matter back to the magistrate judge for a report (I)
identifying the equitable factors to be considered in the
parties’ cross claims for contribution under 42 U.S.C.
§9613(f) and (2) recommending a comprehensive allocation
of Beazer’s clean-up costs among the parties. See
Memorandum Order of July 8, 1996 (Document 193). After
lengthy proceedings that included a twelve-day hearing and
the submission of over 47 ring binders containing
approximately 1300 exhibits, the magistrate judge considered
the equitable allocation factors advocated by the parties and
issued a report on November 24, 1999, recommending
proposed findings of fact and conclusions of law. (Document
303). As part of this process the magistrate judge
recommended final allocation percentages reflecting cach
party’s equitable share of the CERCLA response costs
ultimately found to be recoverable.
$Sa
Each party filed objections to the magistrate judge’s
report. On March 7, 2000, this court issued a memorandum
and order granting in part Mead’s objections and adopting the
report as this court’s findings of fact and conclusions of law.
The court determined that “Mead is, in fact, responsible for
placing most of the contamination at the Woodward Coke
Plant” and under the most precise calculations available
“Mead placed approximately 90% of the waste on site.”
Findings of Fact and Conclusions of Law (Document 303) at
pp. 96-97. After considering a number of other factors which
were found to be relevant in apportioning the parties’
responsibilities for recoverable response costs, the court's
order provided:
The final, costs found recoverable in this action shall
be allocated as follows: The Mead Corporation -
67.5%; and Beazer East, Inc. - 32.5%.
Memorandum Order of March 7, 2000 (Document 308).
During this “allocation phase” of the case the parties agreed
that determinations regarding the recoverability of specific
costs would be left to a later phase in the litigation. See
Proposed Findings of Fact and Conclusions of Law of
November 24, 1999 (Document 303) at p. 17 n.6); Joint
Pretrial Stipulation (Document 320) at p. 3, 44.
After the parties appeared before the court for a
conference on March 21, 2000, an order was entered on April
5, 2000, setting forth the procedures and compliance dates
for the completion of the current phase of the litigation. The
purpose of this phase is to determine which of the specific
costs incurred by Beazer prior to December 31, 1999, are
CERCLA response costs for which Beazer is entitled to
contribution from Mead. See Joint Pretrial Stipulation at 45.
56a
At the commencement of this phase of the litigation
Beazer presented Mead with invoices totaling $5,008 ,709.00.
The parties agree that at least a portion of these invoices
reflect response costs at the site and that with minor
exceptions these cost documents are genuine business records
of Beazer and represent costs actually incurred by Beazer on
or before December 31, 1999. Id. at 44 24 & 28. They
further agree that at least $1,960,811.00 to $2,706,273.00
represent recoverable response costs incurred by Beazer and
that Mead bears a 67.5% responsibility for such costs. Id. at
44 29-30. Beazer’s cost documents reflecting its claimed
response costs through December 31, 1999, were admitted
into evidence at the trial. See Clerk’s Memorandum
(Document 336) at p. 4.
After reviewing Beazer’s proffered cost documents Mead
asserted that certain portions of them were not necessary
response costs under CERCLA and/or were not costs incurred
consistent with the National Contingency Plan (“NCP”).
Mead segmented its challenges into four categories: (1) post
risk assessment costs, (2) unnecessary sampling costs, (3)
programmatic activity and (4) inadequate documentation. See
Mead’s Pretrial Brief in Support of Judgment (Document
324) at p. 25. After reviewing Mead’s challenges, Beazer
reduced its claimed Costs to $4,993,488 .00 to account for any
possible duplication or inadequate documentation identified by
Mead. Trial Transcript (“TT”) of February 4, 2002 (Muck)
at 116-121; Plaintiff's Demonstrative Exhibits D-43 & D-45.
Beazer contended that many of Mead’s remaining objections
to the specific invoices previously had been litigated and
highlighted in its pretrial brief several of the court’s prior
findings and rulings, arguing that they essentially resolved
most of Mead’s challenges to the cost documents.
57a
In the pretrial stipulation the parties raised the issue of the
preclusive effect of the court’s prior rulings on the issues
raised in this phase of the litigation. On January 22, 2002,
the court issued a memorandum advising the parties that it
would not “revisit factual or legal issues that have been
considered and resolved in the process of arriving at the
percentages assigned to the respective parties for equitable
allocation and accordingly the [instant] phase of this litigation
[would] be limited to the consideration of matters beyond
those previously addressed and resolved by the court.”
Memorandum and order of January22, 2002 (Document No.
330) at p. 2. The order accompanying the memorandum
specifically provided:
The evidence presented at the [instant] phase of this
litigation shall be limited to whether the specific
invoices Beazer produced to Mead for activities at the
site through December 31, 1999, reflect recoverable
response costs, within the meaning of 42 U.S.C.
§9613(f). The court will give preclusive effect to its
prior findings of fact and conclusions of law and the
litigation will be limited to the remaining matters
raised in the parties’ submissions filed pursuant to the
court’s pretrial order of April 5, 2000. The parties
shall prepare for trial accordingly[.]
Id. at p. 8. At trial Mead insisted that the prior proceedings
did not resolve its “necessary” and “consistency” defenses as
they relate to Beazer’s specific cost documents. The Court
permitted the introduction of evidence and argument
concerning Mead’s objections to the extent it did not clearly
seek to revisit, circumvent or avoid the court’s previous
findings and rulings with the expressed understanding that the
previous findings and rulings would be given full force and
58a
effect. See TT of February 4, 2002 (Document 337) at pp.
21-26. Those findings and rulings are incorporated herein.
The historical basis for Beazer’s contribution claim arose
as a result of its compliance with (1) initial requests by and
(2) subsequent administrative orders entered into with the
United States Environmental Protection Agency (“EPA”) and
the Alabama Department of Environmental Management
(“ADEM”). The site became the target of investigations by
the EPA and ADEM in the early 1980's after the Resource
Conservation and Recovery Act (“RCRA”) became effective.
Initial soil, surface water and sediment testing was conducted
in 1985 and groundwater monitoring programs were initiated
in 1986. These activities were performed by Beazer, the EPA
and ADEM and the collected data was used by the EPA as
part of its initial investigation and characterization of the site.
The EPA advised Beazer that historical treatment and disposal
of hazardous wastes at the site were a concern under RCRA.
Beazer notified Mead on September 18, 1986, that historical
waste disposal practices at the site might become the subject
of a RCRA §3008(h) corrective action order and invited Mead
to join Beazer in negotiating with the EPA regarding any
required corrective action pursuant to a mutually agreed upon
method of sharing Costs. Mead denied any responsibility for
the historical waste disposal practices at the site on the ground
that the asset purchase agreement made Beazer solely
responsible for all such practices.
On March 22, 1988, Beazer notified Mead that an EPA
contractor was about to conduct a facility assessment at the
site “to investigate prior disposal activities at the plant” and
invited Mead to be present and observe the process. Mead
declined. On November 28, 1990, Beazer notified Mead of
its receipt of a proposed administrative order of consent
59a
(“AOC”) prepared by the EPA and again invited Mead to
participate in the negotiation of a final order. Mead declined.
On July 8, 1991, Beazer and the EPA became partics to
an AOC entered under §3008(h) of RCRA. The order made
a finding that “the hazardous waste and/or hazardous
constituents identified [during prior sampling at the site] pose
a threat to human health or the environment” and that there
had “been a release of hazardous waste and/or hazardous
constituents into the environment from the facility.” AOC
(Plaintiff's Trial Exhibit 443) at 4, 7. The AOC directed
Beazer to develop a work plan “designed to define the
presence, magnitude, extent, direction and rate of movement
of any hazardous wastes and/or hazardous constituents, within
and beyond the Facility boundary,” and
to conduct those investigations necessary to: (1)
characterize the potential pathways of contaminant
migration; (2) characterize the source(s) of
contamination; (3) define the degree and extent of
contamination; (4) identify actual or potential
receptors; and (5) support the development of
alternatives from which a corrective measure will be
selected by EPA.
Id. at 8. The EPA concluded that the actions required by the
AOC “are necessary to protect human health or the
environment” and it further reserved the right to “determine
that certain tasks, including investigatory work or engineering
evaluations, are necessary to protect human health or the
environment in addition to the tasks and deliverables included
in the work plans [to be developed and performed by Beazer]
when new information indicates that such additional work is
necessary.” Id. at 7, 10.
60a
A RCRA facility investigation (“RFI”) was initiated to
satisfy the obligations set forth in the AOC. Its overall
objectives were to:
@ Characterize the nature and extent of constituents of
interest(“COI”) within and beyond the facility
boundary;
@ Determine and characterize the sources of COI:
@ Define and characterize the potential pathways of
constituent migration;
@ Identify and characterize actual and potential human and
environmental receptors and assess the potential risks
posed to such receptors; and
@ Gather the data necessary to support the development,
evaluation and selection of corrective measures or
alternatives, as necessary.
RFI (Plaintiff's Trial Exhibit 443) at pp. 1, 2; AOC at p. 8.
Beazer’s contractor submitted an RFI work p. «. in September
of 1991, which was approved by the EPA. The RFI obligated
Beazer to characterize the hydrogeologic conditions, soil and
rock units, surface water and sediment, and topographical and
climatic conditions at the site. RFI at pp. 12-16. The RFI was
designed to investigate the entire site as a hole due to its size,
the close proximity of the various hazardous substances and
areas of concern, the similarity of COI among the potential
source areas, the technical difficulty of segmenting potential
releases from any particular area and the need to focus on the
common potential migration pathways at the site. Findings of
Fact and Conclusions of Law (Document No. 303) at pp. 20-
21.
61a
RFI Phase I activities began on February 3, 1992. Major
Phase I activities included soil borings, test pits, soil
sampling, monitoring well installation and groundwater
sampling, aquifer characterization, surface water and
sediment investigation, preliminary ecological investigation
and additional groundwater sampling. Joint Pretrial
Stipuiation at 415. RFI Phase II activities began on
September 11, 1995, and concluded on September 24, 1996.
Major activities during this phase included preliminary
planning, site reconnaissance, dye tracer study, naturai
potential survey and magnetometer surv*\ , surface water and
sediment sampling, ecological and wetlands reconnaissance
survey, soil boring and sampling, coke and coke fill sampling,
monitoring well installation and groundwater sampling,
downhole geophysical surveys, aquifer pump test, and
pipeline testing. Id. at 416.
Beazer submitted a draft Phase I and II RFI and
groundwater quality assessment report to the EPA and ADEM
on March 7, 1997. The report included a risk assessment
prepared by Beazer’s contractor, Ogden Environmental, and
a response to ADEM’s requirement that Beazer complete a
groundwater quality assessment. The risk assessment
advanced and sought to support the proposition that estimated
non-cancer and excess lifetime cancer risks posed by the site
are within acceptable target ranges. Beazer is still waiting for
the environmental agencies’ formal substantive response to its
report and risk assessment.
In March of 1999, Beazer submitted a Site Conceptual
Model for groundwater flow and in April of 2000, ADEM
required Beazer to submit a draft Phase II] RFI work plan
outlining the means by which additional groundwater
sampling would be conducted. The Phase III investigation is
designed to identify the potential migration of hazardous
62a
substances into the groundwater beyond the boundaries of the
site. Its primary focus is on the flow patterns of deeper and
off-site ground water.
Beazer employed a multi-tiered process to identify, verify,
monitor and segregate the environmental costs initiated at the
site pursuant to the AOC. A project/environmental manager
was assigned to the site. TT of February 4, 2002,
(Brourman) at 31, 54. This individual assisted in the selection
of environmental consultants that performed environmental
work at the site and oversaw the work they performed. Id. at
54-55. Compliance with NCP requirements was always a
goal and numerous steps were taken to achieve that goal,
including quality control of the data collected, use of
accredited laboratories, developing a community relations
plan and so forth. Id. at 56.
When an invoice from an environmental consultant or
outside contractor reflecting work undertaken to comply with
the AOC was reviewed by Beazer, it was subjected to a multi-
level review process. Id. at 57. The invoice was reviewed by
the accounting department and a tracking label providing key
information needed in the verification process to follow was
attached to it. Id. at 58. The accounting department reviewed
any numbers or mathematica! computations appearing on the
invoice, cross referenced it to the specific location and the
applicable work order, and performed any other pertinent
administrative verification. Id. The invoice would then be
forwarded to Beazer’s project/environmental manager for
technical review. This included verifying that the work was
in compliance with the purchase order and any applicable
change orders, and was otherwise consistent with the
objectives and actual work being performed at the site. Id. at
59-60. All invoices were coded to a specific site and at
Woodward Coke the invoices also were correlated to the
63a
specific tasks outlined in the AOC. Id. at 62. The
project/environmental manager would then perform a
breakdown of any specific charges for individual tasks to
verify their accuracy and compliance with the governing,
purchase order. Id. Additional data or explanatory material
was requested from the consultant whenever necessary. Id. at
64. After completion of the technical review the invoices
were returned to the accounting department for payment. Id.
at 58. Payments for larger amounts required explicit approval
from Beazer’s chief financial officer. Id.
A multi-level review process also was undertaken to
segregate the cost documents Beazer tendered to Mead.
Initially the accounting department was given a beginning and
ending date for the retrieval of invoices. TT of February 4,
2002 (Muck) at 116. All invoices within that time frame that
were coded to Woodward Coke were pulled from Beazer’s
environmental, cost ledgers. Id. Then each invoice was
reviewed to verify that it was a true cost attributable to
complying with the AOC. Id. at 127. During this process
various expenses that were not true environmental costs
attributable to the implementation of the AOC were deducted.
Id. at 118, 126. This review was undertaken by Beazer’s
chief financial officer, Karen Mance, with assistance from the
technical staff, including the project/environmental manager.
Id.; Deposition of Karen Mance (Document 333) at il. She
reviewed the invoices and eliminated costs such as property
management costs, plant operation costs, outside counsel fees,
and travel costs of internal personnel connected to the instant
litigation or not specifically related to the implementation of
the AOC. Id. at 11-16. Other amounts such as costs
estimated to be attributable to groundwater monitoring and
quality assessment for a RCRA regulated unit not associated
with Mead’s operation of the plant were then computed and
deducted. TT of February 4, 2000 (Muck) at 118; Mance
64a
Denrosition at 12. These calculations were made with the
assistance of technical personnel and in-house counsel and
were based upon the hypothetical costs of installing four
groundwater wells and the estimated costs of monitoring
them. Mance Deposition at 12-13.
As previously noted, Beazer has produced to Mead and
submitted into the record approximately 3,600 pages of
invoices to support the costs it contends ‘are recoverable
response costs. Beazer has categorized these costs into the
following categories: groundwater quality assessment, outfall
area study, remed_al field investigation, risk assessment,
waste disposal, RFI work plan, monitoring outfall (plant
lake), Part B post-closure permit application, travel - legal
and technical, community relations, and conceptual design -
lagoon remediation. Beazer’s cost documents are
professionally organized and easy to reference.
Beazer does not dispute its obligation to prove its invoices
reflect recoverable response costs incurred at the site on or
before December 31, 1999. It asserts it has presumptively
and factually done so. In other words, Beazer argues that the
circumstances leading to and surrounding the implementation
of the AOC coupled with a review of its technical
requirements establish that the generated invoices were
necessary costs of response incurred consistent with the NCP.
It further argues that the AOC is the functional equivalent of
a CERCLA §106 or §122 order and the cost documents as a
whole (1) identify the source of the release and the response
actions taken, (2) accurately account for the costs incurred,
and (3) identify the risks to public health and the
environment; all of which demonstrate compliance with the
applicable regulations and provisions of the NCP and indicate
Beazer’s claimed costs were incurred as part of an
undertaking designed to produce a CERCLA quality clean-up.
65a
Mead contends in general that Beazer has applied an
inappropriate standard for determining whether its
investigative costs are recoverable response costs. It argues
that the work performed pursuant to the AOC should not be
presumed to meet the necessary and consistency requirements
of CERCLA. And, even if such a presumption is appropriate,
a specific review of Beazer’s cost documents assertediy
demonstrates a significant amount of the costs were not
incurred pursuant to the AOC and/or were not “necessary
costs of response” or “incurred consistent with the NCP.”
From Mead’s perspective the cost documents continue to
reflect non-recoverable expenditures in the form of (1) double
billing/inadequate documentation, (2) programmatic costs
incurred in complying with independent environmental
regulatory programs, (3) unrecoverable post risk assessment
costs and (4) unnecessary sampling costs.
Beazer sufficiently has demonstrated the costs it incurred
in complying with the AOC were generated in a setting that
presumptively satisfies CERCLA’s necessary and consistency
requirements. The record also demonstrates that as a whole
Beazer’s cost documents do reflect necessary costs of
response incurred consistent with the NCP that were
generated as part of an environmental remediation effort
designed to produce a CERCLA quality clean-up.
Accordingly, Beazer’s claimed response costs are
presumptively recoverable and Beazer is entitled to recover its
claimed costs unless Mead’s specific challenges have led the
court to conclude otherwise.
“Congress enacted CERCLA, a complex piece of
legislation ... to force polluters to pay for costs associated
with remedying their pollution.” Beazer East, 34 F.3d at 219
(quoting United States v. Alcan Aluminum Corp., 964 F.2d
252, 258 (3d Cir.1992)). CERCLA is a remedial statute
66a
which is to be construed liberally to effectuate its goals and
one of its principal concerns is assuring that those who are
responsible for environmental conditions bear the costs of
remedying those conditions. [d. (citing, inter alia, B.F.
Goodrich vy, Murtha, 958 F.2d 1192, 1197 (2d Cir. 1992)).
Generally, CERCLA initially imposes strict liability on
potentially responsible parties. With limited exception, a
potentially responsible party who has incurred costs associated
with hazardous substance clean-up and site remediation may
recoup that poriion of its expenditures which exceed its fair
share of the overall liability through the contribution and
equitable apportionment mechanism engrafted into CERCLA
by the Superfund Amendments and Re-Authorization Act, 42
U.S.C. §9613(f). See New Castle County v. Halliburton
NVS Corp., 111 F.3d 1116, 1122 (3d Cir. 1997).
A private party may recover contribution under CERCLA
for any “necessary cests of response incurred ... consistent
with the national contingency plan.” 42 U.S.C. §9607(a)(4)
(B); see also 40 C.F.R. §330.700(c)(2). The party seeking
contribution has the burden of demonstrating that its identified
costs satisfy both the necessary and consistency requirements
of the statute. Foster vy. United States, 926 F.Supp. 199, 203
(D.D.C. 1996). Also, as a general matter response costs
must have been incurred in a reasonable manner. Langford-
Coaldale Water Authority v. Tonolli Corp., 4 F.3d 1209,
1219 (3d Cir. 1993); Northwestern Mutual Ins. Co. v.
Aulantic Research, 847 F.Supp. 389, 401 (E.D.Va. 1994). In
other words, costs incurred for needless measures that do not
come within the ambit of CERCLA’s necessity and
consistency requirements are not recoverable. Id.
Beazer is entitled to seek contribution for ali necessary
“response costs associated with a release or threatened release
of hazardous materials.” 42 U.S.C. §9607(a)(4)(B).
67a
“*Response’ [under CERCLA] means remove, removal,
remedy, and remedial action.” 42 U.S.C. §9601(25).
“Removal” includes “such actions as may be necessary to
monitor, assess, and evaluate the release or threat of release
of hazardous substances ....” 42 U.S.C. §9601(23). Thus,
CERCLA contemplates that investigative costs incurred to
assess, characterize and evaluate the threat of a release are
response costs. See, e.g, Bowen Engineering v. State of
Reeve, 799 F.Supp. 467, 476 (D.N.J. 1992) (citing Jones v.
Inmont Corp., 584 F.Supp. 1425, 1429 (S.D.Oh. 1984)).
In order to prove its identified costs satisfy the necessity
requirement, Beazer must prove “(1) that the costs were
incurred in response to a threat to human health or the
environment and (2) that the costs were necessary to address
that threat.” Foster, 926 F.Supp. at 203 (quoting G.J. Leasing
Co. vy. Union Elec. Co., 854 F.Supp. 539, 561 (S.D.IIl.
1994) (emphasis in original)). In the area of investigatory
costs this requirement generally is understood to mean that “a
claimant’s investigatory costs must be precipitated by a release
of a hazardous substance and necessary to the remediation
thereof.” Id. (citing Gache v. Town of Harrison, 813 F.Supp.
1037, 1046 (S.D.N.Y. 1993) & Artesian Water Co. v.
Government of New Castle County, 659 F.Supp. 1269; 1278
(D.Del. 1987)). The threat to public health or the environment
must be actual and real. J.G. Leasing Co., 854 F.Supp. at
562 (citing Matter of Bell Petroleum Services, Inc., 3 F.3d
889, 904-906 (Sth Cir. 1993)). A hypothetical threat is
insufficient. Id. In addition, the release or threatened release
must have caused the claimant to have incurred the response
costs. Id. (citing 42 U.S.C. §9607(a)(4); Dedham Water Co.
v. Cumberland Farms Dairy, Inc., 872 F.2d 453, 459 (ist
Cir. 1992)).
68a
The EPA has determined that all actions undertaken to
comply with the AOC are a necessary response to a release
and ongoing threat of release of hazardous substances into the
environment and are actions needed to protect human health
or the environment. In the AOC the EPA made a finding that
“{t}here has been a release of hazardous waste and/or
hazardous constituents into the environment.” AOC
(Plaintiff's Trial Exhibit 443) at §V(4). It further determined
that all actions required under the AOC are “necessary to
protect human health or the environment.” Id. at §V(5).
These determinations were based upon the initial and
subsequent investigations and sampling at the site which
confirmed that there had been a release of hazardous
substances within the meaning of CERCLA. The EPA also
determined that the ongoing investigation and characterization
activities under the AOC are necessary and appropriate steps
toward assessing potential measures designed to select feasible
and reasonable measures to clean-up the site and eliminate the
threat of a future release. The EPA’s determinations were
made within its area of technical expertise and are entitled
to deference. See Commonwealth of Pa., Dept. of
Environmental Resources v. U.S.E.P.A., 932 F.2d 269, 272
(3d Cir. 1991). It follows that Beazer’s activities undertaken
to comply with the AOC are costs incurred in response to a
threat to human health or the environment and are necessary
to address that threat.
Beazer has demonstrated sufficiently that in general its
costs in complying with the AOC should enjoy a presumption
of necessity and consistency under CERCLA. Mead’s
contention that such a presumption is inappropriate because
the AOC was entered under §3008(h) of the RCRA is
unpersuasive. While Mead correctly notes that the preamble
to the 1990 NCP indicates a RCRA corrective action is not
entitled to a presumption of necessity and consistency under
69a
CERCLA merely because it requires a private party to
conduct clean-up activities, see Mead’s Brief in Support of
Judgment (Document 341) at p. 7, it equally is clear that
response actions undertaken pursuant to RCRA can justify
presumptive cost recovery under CERCLA where the
activities are from a technical perspective analogous to those
that would have been required under an order issued by the
EPA pursuant to §106 or §122 of CERCLA and the costs
incurred are substantially similar to those that would have
been incurred under CERCLA. Those circumstances are
present here.
The AOC is the functional equivalent of and mandates a
substantially similar process to what would be required under
a §122 administrative order on consent under CERCLA. As
a general matter the investigatory and characterization
components of a response action under CERCLA begin with
a remedial preliminary assessment (“PA”) and a remedial
sight inspection (“SI”). See 40 C.F.R. §300.420. “A
remedial PA shall consist of a review of existing information
about a release such as information on the pathway of
exposure, exposure targets, and source and nature of release.”
40 C.F.R. §300.420(a)(2). A PA report must include a
description of the release, a description of the probable nature
of the release, a recommendation on further action and a
recommendation on whether a SI or removal action or both
should be undertaken. 40 C.F.R. §300.420(4). If a SI is
chosen, it must build upon the information gathered from the
PA, involve both on and off site field investigation efforts and
sampling, and utilize a process for obtaining data of sufficient
quality and quantity to “achieve adequate data for use in site
evaluation and hazard ranking system activities.” 42 C.F.R.
§300.425. If a remedial SI is performed, the lead agency
performing the investigation must prepare a report containing:
70a
(I) A description/history/nature of waste handling;
(ii) A description of known contaminants;
(iii) A description of pathways of migration of
contaminants;
(iv) An identification and description of human and
environmental targets; and
(v) A recommendation on whether further action is
warranted.
Id. The entire process is designed to provide the data and
information necessary to perform a _ remedial
investigation/feasibility study and permit the EPA to select
appropriate remedial actions. See 42 C.F.R. §300.430.
As noted above, the AOC obligates Beazer to engage in a
substantially similar process. The AOC specifically required
Beazer to complete a RCRA Facility Investigation Work Plan
for the entire site which was “designed to define the presence,
magnitude, extent, direction and rate of movement of any
hazardous waste and/or, hazardous constituents, within and
beyond the facility boundary.” Id. at §VI(A)(1) & (2). As
part of this process Beazer had to conduct the “investigations
necessary to: (1) characterize the potential pathways of
contaminant migration; (2) characterize the source(s) of
contamination; (3) define the degree and extent of
contamination; (4) identify actual or potential receptors; and
(5) support the development of alternatives from which a
corrective measure will be selected by the EPA.” Id. at
§VI(A)(2). Beazer also was required to submit both
preliminary and final RFI reports to the EPA and develop a
data collection quality assurance plan, a data management
plan, a _ health and safety plan and a_ public
involvement/community relations plan. Id. at §vi(A)(3). In
fulfilling these obligations Beazer is required to provide
monthly progress reports to the EPA and ADEM and the EPA
Tila
has expressly reserved the right to modify and/or make
changes to all of Beazer’s required submissions and
deliverables. Upon completion of the RFI, the AOC obligates
Beazer to submit a corrective measures study to inform the
EPA’s selection of a corrective measure or measures for the
site. Id. at §V1(B)(4) & (5). Finally, the EPA may require
Beazer to perform additional tasks, including investigatory
work or engineering evaluations, if in its judgment such
actions are necessary to protect human health or the
environment due to the receipt of new information indicating
“that such additional work is necessary.” Id. at §VI(C)(11).
A comparison of the manner in which the release of
hazardous substances at the site has been investigated reveals
its substantial similarity with the general process to be
employed under CERCLA and the NCP. The RFI work plan
initiated a series of investigative measures designed to assess
and characterize the nature of the release, the potential
pathways of migration, the human and environmental
receptors placed at risk by the migration and to provide the
information necessary to make informed decisions about
future action. The work was performed in incremental steps
in order to permit the EPA or ADEM to expand or modify its
scope based upon gained information. Internal and external
data validation controls were maintained. Both on and off site
sampling has been utilized and the entire process is designed
to generate the information needed to evaluate remedial
alternatives and select an appropriate remedial measure.
Moreover, each parties’ expert witness offered an opinion
on when investigation and characterization activities
performed under an independent statute or regulation should
be deemed presumptively consistent with costs that would be
incurred under CERCLA. Both acknowledged that where
investigative and pre-remedial activities have been undertaken
72a
pursuant to an independent environmental statute or
regulation, the resulting costs are recoverable under CERCLA
if from a technical perspective the governing order is similar
to a consent decree that would be entered under §122 of
CERCLA. In fact, Mead’s expert, Dr. Ball, acknowledged
that when an independent consent order is similar to and
structurally consistent with a model §122 CERCLA consent
order from a technical perspective, then any costs incurred in
implementing that order presumptively comply with
CERCLA’s necessity and consistency requirements. See TT
of February 5, 2002 (Document 338) (Dr. Ball), at p. 137.
The AOC is conceptually similar to and from a technical
perspective contains the functionally equivalent sections of the
EPA’s model administrative order on consent, for a remedial
investigation/feasibility study under CERCLA. Compare
Plaintiff's Exhibit 569 with Plaintiff's Exhibit 443; see also
Testimony of Dr. Ball on Cross-Examination, TT of February
5, 2002, at pp. 132-38. And Beazer’s expert, Jay Vandeven,
directly and convincingly opined that (1) necessary costs of
response under CERCLA include “costs and activities that are
necessary to characterize the nature and extent of
contamination at the site, develop data for risk assessment,
and develop data for developing, analyzing and selecting a
remedial alternative at a site” and (2) from a technical
perspective the investigation at the Woodward Coke Facility
would have progressed in essentially the same manner if it had
been undertaken pursuant to CERCLA as opposed to RCRA.
See Testimony of Jay Vandeven, February 5, 2002, Trial
Transcript at pp. 48-49 and February 6, 2002, Trial
Transcript at pp. 4-7.
Beazer’s undertakings to comply with the AOC also are
presumptively consistent with the NCP. The NCP is “a series
of regulations promulgated by the EPA to establish
73a
procedures, criteria and responsibilities for response actions
conducted both by the government and private parties.” The
Reading Co v. City of Philadelphia, 823 F.Supp. 1218, 1239
(E.D.Pa. 1993) (quoting Ambrogi_v. Gould, Inc., 750
F.Supp. 1233, 1238 (M.D.Pa. 1990)). To be consistent with
the NCP from a substantive perspective, a private party’s
response actions must be aimed at bringing conditions at a
toxic waste site into compliance with applicable environmental
and public health requirements. Artesian Water Co., 659
F.Supp at 1296. Under the provisions of the 1990 NCP “a
private party response action will be considered consistent
with the NCP if the action, when evaluated as a whole, is in
substantial compliance with the applicable requirements ...
and results ina CERCLA-quality clean-up.”'
' The parties each used the 1990 version of the NCP in conducting
their review of Beazer’s Cost documents. Since the passage of
CERCLA in 1980, there have been three versions of the NCP in
effect: 1982, 1985 and 1990. While it is understood that response
costs are to be evaluated in conjunction with the NCP in force at the
time the costs are incurred, the courts have generally agreed that
the 1990 version merely clarified the standard of compliance set
forth in the 1985 version and as a result most courts have applied
the “substantial compliance” standard as clarified to costs incurred
both before and after 1990. See Reading Co., 823 F.Supp. at 1239-
1240; Nashua Corp. v. Norton Co., 116 F.Supp.2d 330, 353
(N.D.N.Y. 2000); Sherman-Williams Co. v. ARTRA Group, Inc.,
125 F.Supp.2d 739, 753 (D.Md. 2000). The EPA chose the
“substantial compliance” standard in order to ensure that cost
recovery actions for meritorious clean-up activities were not
defeated by a talismanic application of the NCP” s detailed
requirements. 55 Fed.Reg. 8666, 8993 (1990). This court will
employ the substantiai compliance standard as well.
7y4a
Consistency with the NCP also requires a private party to
generate and maintain documentation to support all response
and remedial actions taken at a site. “In general, [the}
documentation shall be sufficient to provide the source and
circumstances of the release, the identity of responsible
parties, the response action taken, accurate accounting of
federal, state or private party costs incurred for response
actions, and impacts and potential impacts to the public health
and welfare and the environment.” 40 C.F.R. §300.700°)
(5)(ii). Beyond these general requirements “the NCP simply
does not contain any specific standards concerning the
documentation of costs.” United States v. Findett Corp., 75
F.Supp.2d 982, 991 (E.D.Mo. 1999); United States v.
Chrysler Corp., 168 F.Supp.2d 754, 759 (N.D.Ohio 2001).
Nor do the regulations elaborate on what is meant by
“accurate accounting” or “sufficient” documentation. Id.
Consequently, compliance with the documentation and
accounting requirements of the NCP can factually be satisfied
through the submission of documentation and cost summaries
that as a whole (1) identify the general nature of the action
taken, (2) identify the cost incurred and (3) establish a nexus
between the claimed cost and the response or remedial action
taken or to be taken at the site. Id.
The practical inability of applying the detailed procedures,
criteria and goal-oriented requirements of the NCP to pre-
remedial activities undertaken to investigate, characterize and
monitor a release or threatened release of hazardous
substances when no remedial measures have been selected at
a site has been recognized by essentially every court that has
squarely considered the issue. See Donahey v. Bogle, 987
F.2d 1250, 1255-56 (6th Cir. 1993) (“Although consistency
with the NCP is a necessary element for recovery of remedial
costs, it does not necessarily follow that consistency with the
NCP is required for recovery of monitoring or investigative
75a
costs”) following Carlyle Piermont Corp. v. Federal Paper
Board Co., 742 F.2d 814 (S.D.N.Y. 1990), vacated on other
grounds 512 U.S. 1201 (1994)); Artesian Water Co., 659
F.Supp. at 1294 (“the detailed NCP provisions governing
other response actions cannot reasonably be applied to
preliminary monitoring and evaluation of a release of
hazardous substances”), affirm’d, 851 F.2d 643, 647 (3d Cir.
1988) (the plaintiff's failure to demonstrate consistency with
the NCP led the district court “to deny recovery for all claims
except for costs of monitoring, an instance where the
procedural requirements were not pertinent”); Foster, 926
F.Supp. at 203 (“because the detailed NCP provisions
governing other response action cannot reasonably be applied
to preliminary monitoring and evaluation of a release of
hazardous substances, ... investigatory costs are generally
recoverable irrespective of their consistency with the NCP”)
(citing numerous additional cases in support) (citations
omitted); Marriott Corp. v. Simkins Indus., Inc., 825
F.Supp. 1575, 1583 (S.D.Fla., 1993) (“courts that have
considered the issue of investigatory costs’ consistency with
the NCP are in agreement that these costs are recoverable
irrespective of their consistency with the NCP”) (collecting
cases); City of New York v. Chemical Waste Disposal Corp.,
836 F.Supp. 968, 980 (E.D.N.Y. 1993) (“the costs of initial
investigation and monitoring of a release are recoverable,
however, without [showing they are consistent with the
NCP]”).
In light of the conceptual difficulties of applying the
detailed remedial provisions of the NCP to initial investigation
and monitoring costs, a number of courts have deemed
CERCLA’s consistency requirement to be satisfied where a
private party’s pre-remedial costs were undertaken in a
manner designed to further the fundamental purposes of
CERCLA: prompt detection of a release or threatened release
T6a
of hazardous substances and the removal or remediation of
any such substance. See, e.g., HRW _ Systems, Inc. vy.
Washington Gas Light Co., 823 F.Supp. 318 344 (D.Md.
1993) (consistency with the NCP investigatory and will be
deemed present where monitoring activities are designed to
characterize the release, describe its probable nature and lead
to recommendations regarding future actions); Northwestern
Mutual Life Ins. Co. v. Atlantic Research Corp., 847 F.Supp.
389, 400-01 (E.D.Va. 1994) (investigatory activities
undertaken to assess the nature of a release of hazardous
substances at a facility and to identify feasible remedial
alternatives are consistent with the NCP); Nashua Corp. vy.
Norton Co., 116 F.Supp.2d 330, 352-53 (N.D.N.Y. 2000)
(costs incurred “at the preliminary remedial evaluation phase”
in order to identify potential remedial measures and assess
their feasibility sufficiently comply with the NCP).
A similar standard is appropriate in this case. The AOC
obligates Beazer to conduct an in depth RFI investigation
designed to generate sufficient data from which to characterize
the nature and extent of the contamination at and beyond the
site, identify and understand the sources of that
contamination, identify and understand the pathways of the
contamination and characterize the actual and potential ways
in which the contamination poses risks to human health and
the environment. Beazer’s investigation and monitoring
activities under the AOC are designed to characterize a known
release of hazardous substances, describe the probable nature
of that release and lead to recommendations regarding future
action as to that release. The procedures being employed are
designed to produce reliable data regarding all environmental
mediums that potentially could be affected by the
contamination. These activities have been and are being
undertaken in accordance with direct oversight by the EPA
and ADEM. It follows that the investigation and monitoring
T7a
activities undertaken at the site have been designed to
characterize the release, described its probable nature,
generate adequate data from which alternative remedial,
measures can be identified, and lead to recommendations
regarding future actions.
The AOC also is designed to lead to a CERCLA-quality
clean-up. It obligates Beazer to perform a corrective
measures study after completing a final RCRA facility
investigation report. The stages of the RFI are designed to
assure adequate data from which to analyze the risks
presented. The object of the CMS is to identify and
development alternative corrective measures, compare the
effectiveness and efficiency of those alternatives and permit
the EPA to select the most effective measures to remediate the
site. See Exhibit B to the AOC, Plaintiff's Exhibit 443 at p.
5,172. Beazer’s activities undertaken to comply with the
AOC are thus designed to lead to an effective clean-up of the
hazardous wastes present at the site and satisfy the general
requirements needed to establish presumptive consistency with
the NCP.
Finally, Beazer’s cost documents sufficiently comply with
the applicable requirements in 40 C.F.R. §300.700(c)(5) &
(6). As a whole Beazer’s cost documents sufficiently identify
the source and circumstances of the release, the nature of the
action taken to assess, characterize and monitor the nature of
that release, the costs incurred as a result of the actions taken
and the aspects of the AOC the activity was designed to
achieve.
The AOC is substantially similar to a §122 administrative
order on consent for a remedial investigation/feasability study
under CERCLA. Beazer’s investigative activities pursuant to
the AOC are from a technical perspective the functional
78a
equivalent of what would have been required under a
CERCLA-based investigation. Beazer’s investigative
activities were as a general matter undertaken as a necessary
response to a release and threatened release of hazardous
substances that pose an imminent danger to human health and
the environment. Beazer’s investigation and monitoring
activities have been performed in order to (1) characterize the
release, (2) describe its probable nature, (3) generate adequate
data from which alternative remedial measures can be
identified and (4) provide the information necessary to make
informed decisions about future remedial action. Beazer’s
activities performed to implement the AOC are designed to
lead to a CERCLA-quality clean-up. Beazer has employed
adequate and reliable methods to (1) identify the cost of its
investigative and monitoring activities and (2) the purpose
those activities served toward accomplishing the various
components of the AOC. It follows that Beazer’s cost
documents presumptively meet the requirements governing a
private party contribution action under CERCLA.
Mead contends four categories of Beazer’s cost documents
are non-recoverable because they either reflect activities that
were not undertaken to comply with the AOC or are otherwise
beyond the scope of CERCLA’s recoverable response costs.
These include: (1) instances of double billing or insufficient
documentation, (2) programmatic costs incurred in order to
comply with operational requirements under RCRA or the
Clean Water Act (“CWA”), (3) post risk assessment costs and
(4) the excessive and unneeded gathering of data at the site.
Each of these categories is addressed below.
In its pretrial brief Mead identified a number of invoices
allegedly reflecting instances of double billing. It also
highlighted invoices that assertedly did not provide sufficient
information to determine whether the claimed costs qualified
79a
as a necessary cost of response. Prior to trial Beazer
eliminated a number of its invoices in order to make
adjustments for instances of alleged double billing.
Notwithstanding these adjustments, Mead continues to contend
that Beazer’s cost documents reflect instances of double
billing and similar nonrecoverable expenses.
Mead specifically challenges an invoice by Dow
Environmental for “resampling” services in the amount of
$55,984.76. See Plaintiff's Exhibit 565 at Bates No. 3249.
Beazer’s environmental manager at Woodward Coke, Mr.
Brourman, explained that the invoice reflected the costs of
validation for the resampling of data collected by another
vendor. TT of February 4, 2002 (Document 337) at 71. The
initial data could not be validated due to mistakes of the
contractor gathering the samples, ES&E. Because ES&E was
responsible for the mistakes leading to the need to resample,
“ES&E voluntarily re-did the sampling and analysis at their
costs, that include[d] both the field work and the laboratory
portion.” Id. at 71-72. However, Dow Industrial was paid
for its quality assurance/quality control work for both the
initial sampling and the resampling because it was not
responsible for ES&E’s mistakes and Beazer did not request
ES&E to pay the Dow invoice on Beazer’s behalf. It was
Beazer’s practice to avoid having one vendor collect directly
from another; instead, Beazer would have paid one vendor
and then demanded an off-setting credit from the other. TT
of February 4, 2002 (Brourman) at 104. Beazer was unable
to locate in its invoices any specific credit provided by ES&E
to account for the portion of the Dow Environmental invoice
of July 29, 1996, reflecting resampling charges. Under such
circumstances Dow Environmental’s resampling invoice of
July 29, 1996, for $55,984.76 is not a recoverable response
cost.
80a
Mead attacks a series of invoices from a vendor known as
“Dames & Moore.” These invoices were submitted for
community relations work. The invoices indicate the work
was performed at Beazer’s “wood treatment plant” in
Dolomite, Alabama. See Plaintiff's Exhibit 561 at Bates Nos.
1850-60. Brourman explained that Beazer did not own a
wood treatment plant in Dolomite and therefore the work had
to have been done in conjunction with Woodward Coke. See
TT of February 4, 2002 at 76. Mead notes that Brourman
admitted on cross-cxamination that it was just as likely a
scenario that the address of Woodward Coke in Dolomite,
Alabama, hed been entered in error as opposed to the
designation of a “wood treatment plant.” Id. at 83. Mead
thus argues that the record demonstrates equally plausible
scenarios and therefore Beazer has not met its burden.
The record contains sufficient evidence to support
Beazer’s treatment of the Dames & Moore invoices as
attributable to Woodward Coke. First, Brourman noted in his
direct testimony that the tracking sticker attached to the
invoices by Beazer at the time the invoices were processed
designated the activity to “582”, the control number for the
Woodward Coke plant. This designation was made on each
Dames & Moore invoice included in Beazer’s cost documents.
Second, the invoices reflect a period of service commencing
on July 27, 1991, which immediately followed Beazer’s entry
into the AOC. The AOC required Beazer to establish a
community relations program. The invoices reflect the types
of activities one would expert to be performed in developing
and initiating a community reiations program at a large RCRA
site. Finally, the invoices reflect activity through November
1, 1991, which correlates to the time when complying with
the community relations component of the AOC would have
been appropriate and necessary. Under these circumstances
8la
the record supports Beazer’s inclusion of the Dames & Moore
invoices in its cost documents.
Mead contends several of Beazer’s invoices should be
excluded because a reasonable person cannot utilize the
supporting documentation to determine the nature of the
actions taken and their relationship to Beazer’s obligations
under the AOC. It also challenges three invoices from ES&E
_ that were designated as “non-billable charges” without further
explanation. Mead identified these invoices in categories “D-
1” and “D-2,” in its trial exhibit “M-11.”
In response Brourman indicated that when the invoices in
these categories were received and processed by Beazer they
were treated as environmental costs for activities at
Woodward Coke and on that basis they were included in
Beazer’s recoverable response costs. Brourman was not able
to provide any further information on the invoices in category
“D-1.” ES&L’s project manager also was unable to provide
further explanation regarding either category of invoices.
Under these circumstances the invoices in the amount of
$35,041.09 in category “D-1,” were insufficiently
documented and are not properly included in Beazer’s
recoverable response costs.
Beazer adequately met its burden of proof on the costs
reflected in category “D-2.” Brourman explained that the
costs in “D-2" reflected work that was beyond the scope of
ES&E’s initial contract at the site but nevertheless was work
that was essential to performing the contract. As part of
ES&E’s work in analyzing the field samples taken from the
site, ES&E was asked to develop an electronic database from
which the sample results could be examined and manipulated
in different ways. ES&E agreed that a certain amount of its
employees’ time would be consume learning curve needed to
82a
“get up to speed in figuring that exercise out” and as a result
ES&E had agreed to charge Beazer only for what was
“reasonable to expect of an experienced contractor.” TT of
February 4, 2002 at 73. A “non-billable charges” designation
was used as an accounting mechanism to track separately the
hours devoted to developing the electronic database. Beazer’s
employees reviewed the actual work performed to develop the
database and Brourman approved the amounts billed to Beazer
as reasonable for the services provided. Id. Beazer paid the
approved invoices. Id. Analyzing the data generated from
the field sampling was an essential part of formulating the risk
assessment. Under these circumstances ES&E’s “non-billable-
invoices” were sufficiently connected to Beazer’s obligations
under the AOC and accordingly these charges are recoverable
response costs.
Mead contends two types of costs should be eliminated
because they represent programmatic operating costs incurred
solely to comply with independent requirements under RCRA
or the Clean Water Act (“CWA”): (1) national pollution
discharge elimination system (“NPDES”) costs (categorized
by Beazer as outfall area study and monitoring: outfall plant
lake costs); and (2) other RCRA costs (categorized by Beazer
as groundwater quality assessment and part B post-closure
application costs). Mead argues that Beazer incurred and
would have incurred these environmental costs solely as a
function of independent environmental regulations applicable
to its ongoing operations of the plant and therefore they are
independent of the historical disposal practices addressed
through the AOC. Specifically, Mead identifies $37,079.72
in costs which it claims are nonrecoverable NPDES costs tied
solely to Beazer’s compliance with the CWA during the
83a
ongoing operation of the plant.? The record does not support
Mead’s contention that these costs did not serve any purpose
in Beazer’s compliance with the AOC and were incurred
solely as a result Df independent environmental regulations.
In the prior phase of this litigation Mead argued that its
liability to Beazer should not include programmatic costs that
Beazer would have incurred separately from its costs of
complying with the AOC. Arguments concerning this issue
were raised by both parties’ experts and after considering
Mead’s objections to the magistrate judge’s proposed findings
of fact and conclusions of law, this court concluded that “even
assuming that some undertakings may coincidentally serve a
dual purpose for Beazer, this factor in itself does not make
such undertakings unnecessary for proper monitoring and
remediation of the site.” Memorandum and Order of Court
of March 7, 2000 (Document 308) at 17. Mead has advanced
no authority to undermine the court's determination.
Moreover, contrary to Mead’s assertions in its post-trial
brief in support of judgment, the record adequately
demonstrates that the various costs Mead has placed into its
“programmatic costs” category were incurred as part of
Beazer’s compliance with the AOC and thus represent
necessary costs of response incurred consistent with the NCP.
Mead essentially concedes that if the activities within this
category were necessary to comply with any aspect of the
AOC, then they properly are included in Beazer’s recoverable
* Separate and apart from the obligations set forth in the AOC,
ADEM’s regulations requirea Beazer to perform a groundwater
quality assessment at the site. Beazer obtained permission from
ADEM to combine its groundwater quality assessment obligations
with its groundwater monitoring activities required under the RFI.
84a
response costs. See Mead’s Post-Trial Brief in Support of
Judgment (Document 341) at 18 (“To the extent that costs
were incurred in the RCRA closure activities that could
conceivably also [have] been of use in the §3008(h) corrective
action efforts, they have not been deducted [by Mead].”). It
argues, however, that these costs were incurred solely for
independent regulatory compliance purposes.
The record does not support Mead’s assertion that the
costs in question served only an independent regulatory
purpose. Jay Vandeven provided the following assessment of
these costs in his rebuttal expert report:
This issue was raised in previous expert reports by
myself and Dr. Ball, and addressed by the court. The
costs questioned by Dr. Ball relate to the monitoring
of water quality in wells installed to comply with
Woodward Coke plant RCRA permit and NPDES-
permitted outfalls.
That these activities are associated, in part, with
RCRA and NPDES compliance is not disputed;
indeed, the amount of money Beazer is seeking to
recover from Mead includes a discount for the costs
associated with programmatic requirements.
However, the remaining costs after the discount are
indeed recoverable and have been incurred in a
manner consistent with the NCP. The data generated
by the monitoring of RCRA compliance groundwater
monitoring wells and NPDES outfalls have been and
will continue to be used in the RFI. For example,
the RFI contains a number of potentiometric surface
maps, which are used to understand groundwater flow
patterns. Each of these maps were developed using
85a
groundwater elevation data from the RCRA
compliance wells.
The NPDES outfall in question monitors discharges
from the South Pond, which is a regulated Solid Waste
Management Unit (SWMU). As a SWMU, the South
Ponds are a potential source for releases of chemicals
to the environment. Monitoring of potential releases
from this SWMU is an integral component of the RFI.
Therefore, it is clear from my review of the site
documents that no costs are “due solely to the
operation of the Woodward Coke plant.” Rather, a
portion of the costs were associated with activities that
had multiple purposes. In addition, the activities in
question continue to be required by ADEM even
though the plant has ceased operation and has been
demolished. Consequently, the costs associated with
these activities cannot be due solely to the operations
of the Woodward Coke pliant.
Rebuttal Expert Report of Jay Vandeven (Document 319) at
pp. 18-19. Mr. Vandeven’s trial testimony further explained
the manner and means by which the data and resulting
knowledge gained from the activities underlying these costs
were used as part of Beazer’s response actions. For example,
in conducting the groundwater quality assessment for the RFI,
data taken from any particular location or well could not be
separated from the data gathered from other monitoring
locations. He explained:
From a technical perspective, you really can’t
separate, the data that you gather from [wells put in
around one particular RCRA regulated unit} from the
data that you gathered during the rest of the RFI.
86a
For instance, a big part of the RFI at the site is
characterizing the nature of the groundwater flow. To
do that, you take water level measurements in the
wells and develop a map of how groundwater flows.
Well, the water levels from those RCRA wells were
used in developing the RFI groundwater maps. They
are used for, at least, dual purposes.
TT of February 4, 2002 (Vandeven) at 162-63. Thus, Mead’s
general arguments concerning Beazer’s NPDES and RCRA
groundwater sampling are unavailing. Similarly, the data
gathered for the “outfall area study” was used to identify the
migration of Contaminants that originated in the South Pond,
a RCRA management unit. The sampling attempted to
identify and characterize contaminants generated from the
historical waste disposal at the site that resulted from various
tars and coking bi-products being released into the South Pond
during the years it was used as part of the industrial process.
Id. This activity was part of the AOC. Id. at 163. A similar
investigation was undertaken in conjunction with the plant
lake. Id. at 167. It too sought to monitor and characterize
groundwater that was leaving the site and flowing into
Opossum Creek, which is one of the primary receptors and
points of concern identified by the EPA and ADEM. Both
outfall area studies monitored the movement of constituents
through the groundwater from onsite locations to remote and
offsite locations. Id. at 167. Both sought to characterize
releases from RCRA units on site, including historical
disposal sites and solid waste management units. Id. at 168.
And, all monitoring and characterization of groundwater and
its flow through the karst terrain contributed to the
formulation of the site conceptual model for groundwater
flow. It follows that these costs are recoverable costs of
response incurred consistent with the NCP.
87a
Mead’s contends that the monitoring and sampling
activities associated with the actual closure of three RCRA
regulated units reflect nonrecoverable response costs because
the activity was not aimed at producing data useful to the
formulation of the risk assessment. Although | the
investigation, characterization and monitoring activities
associated with closing these units did not lead to data used in
the risk assessment, these costs are nevertheless recoverable
response costs.
First, two of the three RCRA regulated units that are now
controlled by a part B RCRA permit were produced by onsite
historical waste disposal practices that resulted in hazardous
wastes being present on the site for a number of decades. TT
of February 6, 2002 (Document 339) (Vandeven) at 47. The
costs associated with the closure, remediation and post-closure
monitoring of these units relate to onsite historical waste
disposal practices, and two of the units were operated prior to
Beazer purchasing the site from Mead. Id. at 53. The
activities undertaken in conjunction with these units is thus
directed at monitoring, controlling and remediating the release
of hazardous substances generated by historical waste disposal
practices.
Second, this court previously considered and rejected
Mead’s contention that the site should be segregated into
distinct operable units, with responsibility being allocated
based upon the parties’ respective use or association with
those units. Instead, the court held that consistent with
traditional field and agency practice, the investigation,
characterization and assessment of the site must be examined
and analyzed as a whole. See Findings of Fact and
Conclusions of Law of November 24, 1999 (Document 303),
at 70-78, 95 (“Any allocation in this case must encompass the
entire site, and must include investigation expenses that have
88a
resulted in certain areas of the site being found not to need
remediation. ”).
Third, the basic aims of an RFI under RCRA (and a
remedial investigation under CERCLA as well) are to
determine the nature and extent of contamination at the site,
use all of the data available to conduct a risk assessment and
examine and evaluate feasible remedial alternatives. Id. at 29.
The various activities that Mead contends are “nonrecoverable
RCRA regulated unit closure costs” segregated by Dr. Ball
into the “C-1” category have contributed and will continue to
contribute to the site-wide characterization of the
contamination and its potential to migrate. Understanding the
entire picture is essential to identifying and evaluating,
feasible remedial alternatives. TT of February 6, 2002
(Document 339) (Vandeven) at 29, 33, 52 (“All sampling
analysis at the site provides for characterization of the nature
and extent of contamination as required by the AOC.”) & 53.
In addition, the closure, remediation and monitoring of the
historical Waste disposal units already are part of the goal to
be obtained by implementing the AOC, the actual remediation
of the site. Accordingly, these costs- properly are included as
recoverable response costs.’
> The court agrees with Mead as to two particular costs placed in
this category by Dr; Ball. It is well settled that RCRA does not in
itself provide for the recovery of past costs incurred in the
treatment, storage and disposal of hazardous wastes. See Meghrig
vy. KFC Western, Inc., 516 U.S. 479, 484 (1996). Consequently,
recovery is appropriate under a RCRA-based program only where
recovery of the claimed costs is warranted under CERCLA. Id. at
487-88. The $6,000.00 post-closure application fee paid to ADEM
reflects a purely administrative RCRA cost and the cost itself lacks
any potential to contribute to the characterization of the site or the
evaluation of potential remedial measures. Thus, it will be
89a
Mead’s contention that its CERCLA liability was
extinguished by Beazer’s submission of a risk assessment to
the environmental agencies on March 3, 1997, also is
Unavailing. At the completion of Phase I and II of the RFI
Beazer submitted a risk assessment to ADEM as an appendix
to its report on those phases. The risk assessment was
excluded.
In addition, Beazer agreed that a deduction is appropriate for
the costs of installing and monitoring the wells for one of the post-
closure units because one unit was created exclusively by Beazer’s
operations at the site. Beazer deducted $365,299.00 from its
Claimed costs as reflective of installing and monitoring four RCRA
ground wells at a hypothetical RCRA regulated unit. This
calculation was made based on the estimated costs which would
have been required by the K060 regulated unit at the site.
Testimony from Beazer’s environmental project manager indicated
that the unit had five wells associated with it, not four. Based On
Beazer’s average cost for each of the four wells, an additional
deduction of $91,324.75 is appropriate.
The remaining costs placed in the “C-1” category by Dr. Ball
are recoverable. Dr. Ball reviewed Beazer’s invoices to determine
whether on their face the invoices reflected activities that “were
referenced in the risk assessment or were reasonably necessary to
produce the risk assessment.” TT of February 5, 2002 (Ball) at 94;
see also id. at 95. If the invoice did not demonstrate its purpose in
this process, Dr. Ball placed it in “C-1.” Id. at 95. This approach
is contrary to the substantial compliance standard mandated by the
1990 NCP. Furthermore, the court has reviewed the remaining
invoices in this category and is satisfied that they reflect monitoring
and data-gathering activities that are essential to characterizing and
understanding the site as a whole in conjunction with assessing the
nature of the release, understanding its potential risks and
evaluating feasible remedial measures.
90a
prepared by Beazer’s contractor, Ogden, and provided in
pertinent part:
Estimated non-cancer risks resulting from potential
exposures to site related constituents are all below the
U.S. EPA’s target Hazard Index of 1.0, for all
receptors in all media at all exposure areas. Similarly
all estimated excess lifetime cancer risks are within the
U.S. EPA’s target risk range of 1 x 10° (1 in
1,000,000) and 1 x 10° (1 in 10,000).
Defendant’s Exhibit M-14 at p. ES-2. Mead notes that “the
entire Ogden risk assessment is extremely conservative” and
expressly indicates that conservative assumptions have been
employed in developing it. Mead’s Post-Trial Brief in Support
Of Judgment (Document 341) at 21 (citing Defendant's
Exhibit M-14 at p. 7-1). Mead further contends that the risk
assessment has been accepted by ADEM because it has
approved Beazer’s report on the Phase I & II RFI activities
and has not indicated any disagreement with the risk
assessment.‘
Based on the above, Mead argues that “the primary focus
of CERCLA and the NCP is the elimination of unacceptable
risk to human health and the environment” and because a
determination of no unace “table risk has been made through
Beazer’s risk assessment, no further action would be required
under CERCLA. From Mead’s perspective all activities at
the site subsequent to the submission of the risk assessment
* Mead bolsters this argument by asserting that “from the CERCLA
perspective, Beazer is the ‘lead agency’” and as a result a
determination has been made that no further remedial action within
the meaning of CERCLA will be necessary at the site.
9la
were undertaken to comply with the regulatory requirements
of RCRA and any costs Beazer incurred after that date “were
‘on its own nickel’ because the costs would no longer be
necessary costs of response pursuant to CERCLA, since they
no longer were incurred in response to a threat to human
health or the environment.” Id. at 21. Because the risk
assessment purportedly established that no further action was
required under CERCLA, Mead contends that all costs
incurred after May 3, 1997, are not recoverable response
costs.
Mead’s contention that the risk assessment extinguished its
liability under CCRCLA is specious. First, while Beazer is
“the lead agency” under various provisions of the NCP, the
determination of whether further corrective measures and/or
additional activities leading to remediation of the site will be
required under the AOC is a determination that remains with
the environmental agencies. No provision of the AOC
explicitly or implicitly grants Beazer the authority to decide
that its obligations to perform a corrective measure study and
implement any remedies selected by the agencies have been
extinguished by its assessment of the risk posed by the site.
Second, ADEM’s letter of August 24, 2000 - indicating
the draft Phase I & II RFI and groundwater assessment reports
prepared by Beazer’s contractor have been “approved” -
cannot be read to support Mead’s contention that the
conclusions advanced in the risk assessment have been
accepted by ADEM and therefore no further response actions
or remedial measures under CERCLA will be necessary. See
Defendant's Exhibit M-15. The letter merely indicates that
the reports have been approved, which can only be understood
to mean that Beazer has fulfilled the requirements of the work
plan governing Phase I & Il investigation activities and
developed a risk assessment. See TT of February 6, 2002
92a
(Vandeven) at 56. In other words, the letter simply means
that Beazer met the requirements of Phase I and Phase II of
the RIF work plan and has developed the risk assessment as
required by the terms of the AOC-id- And ADEM’s intent
to further investigate and characterize the potential migration
of hazardous substances before substantively approving the
risk assessment and moving to the corrective measures
component of the AOC is evident by the reference in the letter
to the “Phase III RFI work plan” under negotiation between
ADEM and Beazer. It also is evident that the need for the
Phase III work arose as a result of areas of concern generated
from the submitted reports. Defendant's Exhibit M-15; TT of
February 6, 2002 (Vandeven) at 55-56; TT of February 5,
2002 (Vandeven) at 7, 29-30.
Third, it is a well-accepted premise that the risk
assessment is only one step in the CERCLA decision-making
process. See Rebuttal Expert Report of October 2000 at pp.
13-14; TT of February 6, 2002 at 28-31. It is merely one
piece of information that will be used by the environmental
agencies along with all other available information in making
their own assessment of the acceptable and unacceptable risks
that remain at the site. Id.
The author of the Ogden risk assessment, Dr. Magee, also
expressed the same view. In conjunction with questioning
regarding Ogden’s decisions to include or exclude particular
chemicals in a risk assessment presented to an environmental
agency, Dr. Magee provided the following insight as to how
a risk assessment is prepared and presented:
As is typical in the work that I do for clients, I view
my job to put a realistic defensible risk assessment on
the table first time through that’s consistent with the
law and the regulations and the guidance but that
93a
wears the client’s hat rather than the agency’s hat
because I’m working for the client.
We know full well that the agency may often, and
usually does, disagree with many of the assumptions
and approaches that we take. So that the numbers of
this report, which is the favorable report to start the
negotiation with the agency, concludes simply that
nothing has to be done anywhere.
But I don’t believe for a minute that nothing will
have to be done anywhere. Because I believe that
they’re going to say, up in the ponds, you have shown
that if a trespasser gets in there and touches some of
the sediment, it won’t hurt them. But you didn’t say a
darn thing about the ecology, the ecological receptors.
Or you assume that if trespassers get on the site
and contact the average of all the soil across one or
two areas, that there won’t be a problem. But you
didn’t consider that they might go preferentially to this
very small, what we would call, hot spot; what would
be the answer if they went just there?
On groundwater, you assume no use of the
groundwater directly beneath the site. While we
might, all agree that it’s unlikely that someone would
drop a well there and make that their drinking water,
they could use the water for industrial process water.
Again, not atypical of any site, the negotiation that
goes on between the PRP and the agency is just that,
and we haven't seen how they responded to this yet.
So from my general experience on sites that have
these kinds of chemicals in them at these levels, I am
94a
sure that some remediation will be required. And it
will be my job then, if I’m asked to continue working
on it, to focus it in and make it be reasonable and cost
effective, selective removal in just this area, capping
and so forth.
Deposition testimony of Dr. Magee at pp. 48-50. In other
words, the initial risk assessment submitted by Beazer is
anticipated to be a mere first step in the bargaining process
between the EPA/ADEM and Beazer with regard to what
additional response/remediation activities will be required at
the site. Absent written notice from the EPA/ADEM
indicating Beazer has complied with all of its obligations
under the AOC, there is no factual or legal basis for this court
to conclude that subsequent response and remediation
activities at the site will fall outside the “necessary” and
“consistency” requirements of CERCLA.
Furthermore, to extrapolate the proposition that no
unacceptable risk remains at the site and therefore no further
remedial measures will be required from the siatements made
in the risk assessment fails to acknowledge the role of the
EPA in evaluating the information generated from agency-
directed investigations. Ogden’s risk assessment did not
purport to render a conclusion on whether the site continues
to present an acceptable or unacceptable risk. The assessment
merely advances an objective proposition regarding general,
site-wide estimated non-cancer and excess lifetime cancer
risks. The assessment is based upon numerous assumptions
about the hazardous substances present, the likely pathways of
exposure, the likely receptors and future expected land and
water use. It docs not purport to address the need or lack
thereof for future remedial action.
95a
Guidance documents from the EPA indicate clearly that
mere objective findings reflecting the presence of hazardous
wastes within an acceptable target range does not mean that a
CERCLA-quality remedial measure will not subsequently be
required by the EPA at the site. In a memorandum providing
guidance on the use of a risk assessment in the CERCLA
decision-making process, the EPA has emphasized that a
finding within the agency’s acceptable target range will not
eliminate the agency’s discretion to require further remedial
action based on other pertinent factors. EPA’s Office of Solid
Waste and Emergency Response advises that “the EPA uses
the general 10(-4) to 10(-6) risk range as a ‘target range’
within which the Agency strives to manage risks as part of a
Superfund clean-up,” but further emphasizes:
(a) A risk manager may also decide that a baseline risk
level less than 10“ is unacceptable due to-site specific-
reasons and that remedial action is warranted [and
similarly} EPA may determine that risks less than | x
10% are not sufficiently protective and warrant
remedial action.
(b) Other chemical-specific ARARS [applicable
regulations and applicable requirements] may also be
used to determine whether a site warrants remediation.
(c) The upper boundary of the risk range is not a
discreet line at 1 x 10*....
Role of the Baseline Risk Assessment in the Superfund
Remedy Selection Decisions, EPA Office of Selid Waste and
Emergency Response (OSWER), 1991, Base 9355.3-30; see
also Rebuttal Expert Report by Jay Vandeven at pp. 12-13;
TT of February 6, 2002 (Vandeven) at 30-31.
96a
The AOC incorporates the EPA’s authority to evaluate as
a whole all risks presented by the site. All of Beazer’s work
under the AOC is submitted for agency review. The EPA and
ADEM retain the express right to require additional
investigation, characterization; monitoring or remedial action
whenever in the agencies’ judgment the data submitted by
Beazer requires such measures and the EPA reserves the right
to select and require the implementation of corrective
measures. See, e.g., AOC at pp. 7-8. The EPA and ADEM
have not substantively approved the Ogden risk assessment or
released Beazer from any further obligations under the AOC;
to the contrary, they have required additional RFI work
pertaining to deep and off-site groundwater flow. Under these
circumstances Mead’s contention that the Ogden risk
assessment eliminated any further basis for cost recovery
under CERCLA lacks sufficient evidentiary support and
Beazer’s post March 7, 1997, response costs are recoverable
to the extent they are not otherwise precluded by the court’s
-—_——Tulings.
Mead’s assertion that Beazer engaged in inefficient and
excessive sampling at the site, thereby rendering a substantial
portion of the data collected “unnecessary” for the purposes
of assessing risk and selecting a remedial action, also is
without merit. Mead argues that in accordance with the NCP,
“(t]he purpose of the remedial investigation (“RI”) is to
collect data necessary to characterize adequately the site for
the purpose of developing and evaluating effective remedial
alternatives.” 42 C.F.R. §300.430(d). It then notes that a
number of the samples collected during Phases I & II of the
RFI were not used by Ogden in formulating the risk
assessment. It reasons “that the risk assessment is the
essential document for identifying and evaluating effective
remedial alternatives and therefore “only those data necessary
to support a risk assessment for the Woodward Coke Site are
97a
recoverable under the NCP.” Mead’s Post-Trial Brief in
Support of Judgment at p. 23.
Mead reduces its “unnecessary” sampling arguments to a
set of mathematical formulas. The total number of samples
made available to Ogden for formulating the risk assessment
was 662. Ogden used a maximum number of 368
investigative samples in evaluating the mediums of concern
(soil, groundwater, sediment and surface water) and thus from
Mead’s perspective a total of 294 samples were not used in
calculating the risk. Mead’s expert then tabulated the
estimated cost of gathering the 662 samples and subtracted
44% from this total (i.e., 294/662 equals .44).
As a further refinement of this requested reduction Mead
notes that while 368 samples represent the maximum number
used by Ogden for an individual contaminant of concern, in
certain of the medium of concern Ogden used far fewer
samples to calculate the risk. For example, to calculate the
risk for some contaminants of concern in the soil, Ogden
needed only 34 samples and for others Ogden used the
maximum number of samples available, 93. From these
premises Mead reasons:
Thus, although Ogden used the additional data, they
were clearly not necessary to complete the risk
assessment, as the minimum number was used for
many of the [contaminants of concern]. In aggregate,
the minimum number of samples used by Ogden is
166, as opposed to the maximum aggregate of 368.
Therefore, as further refinement of the percentage
listed above, the investigation and laboratory costs that
are not recoverable under CERCLA and the NCP
98a
equal approximately 74% - (662 minus 167)/662 - of
the total sampling related costs claimed by Beazer.
The deduction from Beazer’s costs that should be
made if one looks solely at the data used in the risk
assessment is $1 ,154,018.67 (44% of $2,622,769.71 -
the “total E/F costs” ...; if the deduction is based
upon the efficient data needs (that is the number of
samples-which would have satisfied the risk
assessment needs) the deduction is $1 ,964,976.07 ....
Mead is willing to “split the difference” with Beazer
between the deduction based upon the “inefficient”
risk assessment number and the deduction based upon
the efficient risk assessment number; thus, the
deduction Mead proposes for this item is
$1,559,497.37 ($1,964,978 + $1,154,018 =
$3,118,994 +2).
Id. at 25-26. In other words, Mead advocates that only the
minimum amount of data samples needed to formulate the risk
assessment, as calculated after the fact, can be found to be
necessary costs of response incurred consistent with the NCP.
Mead’s mathematical efficiency arguments are flawed on
many levels. First, the court already has considered and
rejected Mead’s contention that Beazer engaged in inefficient
and/or ineffective methods of gathering and processing the
information used in characterizing the site. In the previous
phase of the litigation Mead argued that there was evidence of
“over testing” by Beazer in that it did more testing under
RCRA than would have been “necessary” under CERCLA,
pointing to purported over sampling during Phase II of the
RFI work plan as an example. See Findings of Fact and
Conclusions of Law of November 24, 1999 at p. 52. Mead
also challenged Beazer’s methods of sampling as inefficient
99a
and lacking quality control. Id. After considering these
matters, the court rejected Mead’s challenges on the grounds
that there was nothing “suspect” in the manner in which
Beazer proceeded with its sampling programs under Phase I
& Il of the RFI and Dr. Ball’s criticisms merely reflected “the
type of difference in professional opinion referred to by the
USEPA in guidance documents, and which is to be expected
from site to site.” Id. at 53.
The court explained that identifying the most efficient
approach to investigating a site under CERCLA was not
grounds for excluding additional costs as unnecessary because
such a rigid approach “leaves no room for the accepted notion
that professional judgment might vary from site to site.” Id.
at 54, 74. It then made the following finding:
54. Dr. Ball’s criticisms of the manner in which the
site was addressed under RCRA do not suffice to
establish that any of the actions taken are inconsistent
with the national contingency plan. The manner in
which a site is addressed under RCRA or CERCLA
differs from site to site, and a certain amount of
professional style (for lack of a better word) or
judgment is inherent in the system. Dr. Ball has
established only that he would have conducted the site
inspection and remediation differently: he has not
established that anything actually done at the site was
inconsistent with the NCP.
Id. at p. 78, 454. Indeed, the court rejected the proposition
that efficiency arguments based upon hindsight are a proper
means of identifying necessary costs of response incurred
consistent with the NCP. The court opined:
100a
15. Recovery of costs pursuant to CERCLA requires
that actions taken be “consistent with” the NCP. There
is no requirement that the actions be no more than are
necessary. There is no authority for viewing the
consistency of actions taken in hindsight, i.e., by
arguing that certain actions may not have been
necessary. In short, there is no requirement that a
remedial investigation [be] “perfect” before costs
expended will be found to be consistent with the
“NCP” and, therefore, recoverable in a CERCLA
action.
16. Mead, through the testimony of Dr. Ball, seems to
assert that any action which would not be forced upon
a PRP under CERCLA would not be “consistent” with
the NCP. The court disagrees. Again, the NCP vests
discretion in individual professionals involved in the
investigation and remediation of a particular site to
select from a range of options. There is no support in
the law for Dr. Ball’s hypothesis, and the expert
testimony offered by Beazer concerning the practices
in the field is entirely to the contrary.
Id. at p. 98, 44 15, 16. Thus, the court already has ruled that
the necessity and consistency requirements under CERCLA
are not limited to the minimal means of investigating and
characterizing the risk posed by a site as measured with
hindsight.
Second, Mead’s attempt to reduce the necessity and
consistency requirements of CERCLA to encompass only
those tasks undertaken to gather data directly used in
formulating a risk assessment reflects a_ significant
misapprehension of the CERCLA decision-making process
and the information needed to perform that process efficiently
10la
and effectively. The applicabie regulation does indicate that
“the purpose of the remedial investigation is to collect data
necessary to adequately characterize the site for the purpose
of developing and evaluating effective remedial alternatives.”
42 C.F.R. §300.430(d). But, it does not follow from that
proposition that only the gathering of the data actually used to
support a risk assessment constitutes recoverable costs under
the NCP.
The AOC obligated Beazer to collect data to characterize
the site, delineate the nature and extent of the contamination
present, and perform a baseline risk assessment. Beazer has
gathered the data to characterize the site and published a draft
Phase I & II RFI report. All of the data collected was used in
formulating the RFI report, and the risk assessment was but
one component part of that report. Rebuttal Expert Report of
Jay Vandeven at p. 23. ADEM reviewed the report and
mandated additional investigation above and beyond the data
collected during the first two phases of the RFI investigation
prior to requiring Beazer to undertake the process of
completing a corrective measures study. Thus, the steps
Beazer has been required to take in implementing the AOC
demonstrate clearly that collecting the data necessary to
evaluate remedial alternatives effectively encompasses far
more than a “private party’s formulation of a risk
assessment.”
> A review of the persuasive expert testimony of record more than
adequately supports this proposition. As Jay Vandeven highlighted
in his rebuttal expert report:
Data collected during the course of an investigation have
many purposes and uses. These data are used to develop
conceptual models of the site, to delineate the nature and
extent of contamination, to evaluate groundwater flow and
102a
Third Beazer’s obligation to perform the RFI Phase III
contaminant transport, to document site conditions for
evaluation of remedial alternatives, and to assess risk. The
risk assessment, which is only one component of the RFI,
does use all. the data available in a qualitative manner and
a subset of the data in a quantitative manner to evaluate
exposure pathways and calculate an excess lifetime cancer
risk and hazard index. All of the information from the
various phases of the RFI, including the risk assessment,
when complete, will be considered by ADEM when they
ultimately select a remedy at the site.
Rebuttal Expert Report of Jay Vandeven at p. 22. At trial he
reiterated the multifaceted use of data in conducting an initial
CERCLA or RCRA investigation, emphasizing that the basic
objectives under both RCRA and CERCLA are to characterize the
nature and extent of the contamination at the site and then to
develop remedies to address the risk posed to human health and the
environment. TT of February 6, 2002 (Vandeven) at 8.
Dr. Magee, the vice president and principal toxicologist of
Ogden Environmental and chief architect of the risk assessment,
similarly emphasized the multi-purposes for collecting data during
the course of a CERCLA site investigation. He repeatedly
emphasized that the entire data selection and evaluation process
leading to the formulation of a risk assessment has a bearing on and
informs the decision-making process concerning the assumptions
underlying the risk assessment and the selection of the data used to
formulate the assessment. Deposition Testimony of Dr. Magee
(Document 331) at pp. 25-30. For example, all of the groundwater
samples were en
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.