Petition for Writ of Certiorari — Amertex Enterprises, Ltd. v. United States, 118 S. Ct. 851 (1998) (No. 97-583)

Supreme Court brief1998

Ask Donna

What actually matters in this document.

Text

af “—— woe

(1)

07-588 JUL 3 1 1997.

No. OFFICE OF THE CLERK

In The

Supreme Court of the United States

~~

October Term, 1996

AMERTEX ENTERPRISES, LTD.,

Petitioner,

VS.

THE UNITED STATES OF AMERICA,

Respondent.

On Petition for a Writ of Certiorari to the United States

Court of Appeals for the Federal Circuit

PETITION FOR A WRIT OF CERTIORARI

JOSEPH H. REITER

Counsel of Record

KOSTOS AND LAMER, P.C.

Attorneys for Petitioner

1608 Walnut Street

Suite 1300

Philadelphia, Pennsylvania 19103

(215) 545-0570

utz

ae (800) 3 APPEAL « (800) 5 APPEAL « (800) BRIEF 21

i

QUESTIONS PRESENTED FOR REVIEW

On a contract with the United States, is the contractor

deprived of its right to sue for breach damages by agreeing to

continue performing the contract despite the United States

breach by cardinally changing the contract from a mass-

production contract to a research and development contract

where:

1. The agreement to continue performance contains no

language which can be interpreted as a waiver of accrued breach

damages;

2. The United States was in no way prejudiced by the

contractor’s election to continue performance; and

3. The United States was aware that a claim for those

damages would be presented?

ii

LIST OF PARTIES

The names of all parties to the proceedings in the Court

whose judgment is sought to be reviewed here appears in the

caption of the case. There is no parent or subsidiary company

of any party to be listed.

iii

TABLE OF CONTENTS

Page

Questions Presented for Review ................... i

stniecp testy cag TE Ree Oe ST ee RR ESE ii

oe a a BREN ETE et GRE Oe CE ili

MO NR eri oe iv

soe anes cc ap antie CSE OO OAT a em l

statement of Jurisdiction ................:....... l

I oe l

Reasons for Granting the Writ .................... “4

I. The Federal Circuit Decision Has So Far Departed

From The Accepted And Usual Course Of Judicial

Proceedings And Sanctioned Such A Course By

The United States Court Of Federal Claims As To

Call For An Exercise Of This Court’s Power Of

I hae kc boc resins a 4

Il. The Federal Circuit’s Opinion Directly Conflicts

With Numerous Decisions In Various Circuits,

Which, Based On Modern Views Of Contract Law,

Hold That A Non-Breaching Party To A Contract

Does Not Lose Its Right To Sue For Breach

Damages By Failing To End The Contract And

Agreeing To Continue Performance. ......... 9

iv

Contents

Page

Ill. The Writ Should Be Granted Because The Case Is

An Important One Over And Above Its Conflict

With Other Circuits And Well-Settled Law. ... 12

CCINOIOD kbc cg cick cance oabewss vb kbeeeee bees 13

TABLE OF CITATIONS

Cases Cited:

Allied Materials and Equipment Co. v. The United States,

SOF Fo eee Cis Cas ROT). wn ks SiN VK CRRA REE 4

Cities Service Helex, Inc. v. The United States, 543 F.2d

5 CC. CE ISTO: e kivickcc cee eek 4,6,9

Dunkin’ Donuts of America, Inc. v. Minerva, Inc., 950 F.2d

1566 CRUG AE TGR). nk Gis aa ees 9, 10

First Citizens Federal Savings and Loan Association v.

Worthen Bank and Trust Company, NA, 919 F.2d 510

Ei He. GR ae Rae eay operant eran yy) Ueno 9,10

Fuller Company v. Brown Minneapolis Tank and

Fabricating Company, 678 F. Supp. 506 (E.D. Pa.

SPR) eee Si TE ees oe ee eee 9, 10, 11

Havoco v. Hilco, 799 F.2d 349, on remand, Havoco of

America Ltd. v. Hilco, Inc., 750 F. Supp. 946, affirmed,

971 2G tok CAL ISR) PO es 9,11

Contents

Page

Laka Tool & Stamping Co. v. The United States, 639 F.2d

738 (Ct. Cl. 1980), cert. denied, 454 U.S. 1086 (1981)

Pr re ree PEE ee PS ee Pe ee re ren oe 4

Phillips, Etc., Construction Company v. Seymour et al.,

TE Tien OE TET ED «ho hin so ahah he khakis OE i

S. Leo Harmony, Inc. v. Binks Manufacturing Company,

597 F. Supp. 1014 (S.D.N.Y. 1984) .............. 10, 11

Sitlington v. Fulton, 281 F.2d 552 (10th Cir. 1960).... 9, 10

Statutes Cited:

Oe Wa ONE ve Sb Vcd ecb ake ees sce l

OF Un Ot OE ess kcal ]

Other Authorities Cited:

Contracts, Calamari and Perillo, 3rd Edition, at Page 458

NaN Oa YON OE ped Kick an ss bese dass cs 6

Pe ANOS iii os vise his Oko bac cham ocws 6

RINNE UENO 5s i5s a e 6

17A Am. Jur. 2d (Revised), Contracts § 731 ......... 6

The Uniform Commercial Code ................... 6

vi

Contents

APPENDIX

Appendix A — Decision Of The United States Court Of

Appeals For The Federal Circuit Decided February 24,

MOE EETENL ELE Lee ere ee ere ey oe

Appendix B — Dissenting Opinion By Circuit Judge

Newman Of The United States Court Of Appeals For

The Federal Circuit Dated February 24, 1997 .....

Appendix C -— Opinion And Order On Liability And

Damages Of The United States Court Of Federal Claims

EOtes OCRMBST 1D; TIPS. oan sc tensk vs sedders

Appendix D — Order Of The United States Court Of

Appeals For The Federal Circuit Denying Combined

Petition For Rehearing And Suggestion For Rehearing

Fe RE PAP OS Ba LOOT. Fave ccrcnwosseuduiss

Page

la

9a

14a

1

Petitioner, Amertex Enterprises, Ltd. (“Amertex”), requests

that a Writ of Certiorari issue to review the Judgment and

Opinion of the United States Court of Appeals for the Federal

Circuit entered in this action on February 24, 1997 (Petition

For Combined Petition For Rehearing And Suggestion For

Rehearing Jn Banc denied by Order entered on May 2, 1997),

which affirmed a Final Judgment of The United States Court of

Federal Claims.

OPINIONS BELOW

The Opinion of the Court of Appeals (Petitioner's Appendix,

Page 3) is not reported. It has been designated as “not citable as

precedent”. The Opinion of the United States Court of Federal

Claims (Petitioner’s Appendix, p. 14a) is unreported.

STATEMENT OF JURISDICTION

The Opinion of the Court of Appeals (Petitioner’s Appendix,

Page 3) was entered on February 24, 1997. A timely Combined

Petition For Rehearing And Suggestion For Rehearing Jn Banc

was denied on May 2, 1997. (Petitioner’s Appendix, p. 191a).

The Court has jurisdiction pursuant to 28 U.S.C. § 1254(1).

STATEMENT OF THE CASE

The case involves the issue of whether a Government

contractor loses its right to sue for breach damages already

accrued, when it agrees to continue performance despite the

Government’s breach. It arises under the Contract Disputes Act

of 1978, 41 U.S.C. § 601, et seg. Petitioner, Amertex Enterprises,

Ltd. (“Amertex”), at the time a participant in the Small Business

Administration 8(a) program for “economically and socially

disadvantaged” contractors, was awarded Contract No. DLA100-

85-C-0402 on February 25, 1985, for 2,415,885 Chemical

2

Protective Suits at a firm fixed price of $39.88 each, for a total

of $96.35 million. The contractual delivery schedule called for

deliveries of some 200,000 units per month ending in January,

1987.

By the end of 1988 (nearly two years after the Contract

should have been completed), as a result of what the Court of

Federal Claims (“the COFC”) found to be defective Government-

provided specifications, as well as numerous Government-

initiated specification changes, Amertex had delivered

approximately 1.1 million of the 2.4 million Chemical Protective

Suits. According to the COFC, as a result of the Government’s

failure to properly test the specification prior to issuing the

underlying solicitation, the numerous changes and corrections

were necessary in order for the applicable specifications to be

suitable for mass production, to the point where the Contract,

again according to the COFC, became, “at least in part, a

research and development contract”.

Following a Default Termination of the Contract on January

6, 1989, Amertex filed several claims, including a breach of

contract claim, founded on the doctrine of cardinal change, i.e.,

that the Government had materially altered the fundamental

contractual undertaking, by turning the fixed-price production

contract on which Amertex had bid into a research and

development vehicle.

Despite its finding that the contract had become, due to

1. Unbeknownst to Amertex, for classified reasons under code name

“Operation Cement Elephant”, the Government rushed the specification

through the development process, so that the normal testing procedures

were not followed. As a result, what the COFC found to be untested and

flawed specification were incorporated, without warning or disclaimer,

into the largest mass production contract the agency (the Defense Logistics

Agency/Defense Personnel Support Center) had ever awarded.

3

Government actions, “at least in part a research and development

contract”, the COFC rejected Amertex’ Claim of Cardinal

Change/Breach. According to the COFC, Amertex’ “potentially

convincing” claim was “fatally undercut” by its August, 1988

(five months before the Default Termination and three and one-

half years after award) execution of a bilateral Modification (i.e.,

P00037) incorporating a new delivery schedule and altering the

method of payment from progress payments to payment upon

delivery. The total dollar amount of the contract remained

unchanged. The COFC neither explained its reasoning nor

offered any case citations in support of this critical holding.

The Court of Appeals of the Federal Circuit (“the Federal

Circuit”), through its deciding panel (in a 2-1 decision), affirmed

the decision of the COFC, holding that Amertex’ signing of the

Modification incorporating a new delivery schedule was an

“implicit” agreement by Amertex to perform the modified

contract, thereby operating as a waiver of the right to assert a

breach claim for damages already accrued. The Modification,

however, in question contained no waiver or release language

and was negotiated with knowledge by all parties that Amertex

would be submitting a claim for damages already accrued.’ Like

the COFC, the panel cited no law, regulation or case decision

supporting its holding. The dissent asserted that absent an

express waiver in the Modification, Amertex’ claim could not

2. Specifically, the Modification in question, PO00037, contained a

caveat, which read as follows:

It is agreed further that the execution of this

modification will not be construed by either party

as an endorsement by either party of any negotiation

position with respect to the settlement of

modifications POOOO! and P00002.

(Petitioner’s Apper.dix, p. 190a).

4

be held to have been waived, citing, inter alia, Laka Tool &

Stamping Co. v. The United States, 639 F.2d 738, 743 (Ct. Cl.

1980), cert. denied, 454 U.S. 1086 (1981); Cities Service Helex,

Inc. v. The United States, 543 F.2d 1306, 1313 (Ct. Cl. 1976);

and Allied Materials and Equipment Co. v. The United States,

569 F.2d 562, 563-64 (Ct. Cl. 1978).

REASONS FOR GRANTING THE WRIT

I.

THE FEDERAL CIRCUIT DECISION HAS SO FAR

DEPARTED FROM THE ACCEPTED AND USUAL

COURSE OF JUDICIAL PROCEEDINGS AND

SANCTIONED SUCH A COURSE BY THE UNITED

STATES COURT OF FEDERAL CLAIMS AS TO CALL

FOR AN EXERCISE OF THIS COURT’S POWER OF

SUPERVISION.

The COFC held that Amertex deprived itself of the right to

claim breach damages attributable to an acknowledged cardinal

change when it agreed to continue performance. Specifically,

the COFC held as follows:

Notwithstanding the evidence supporting

Plaintiff’s plausible and potentially

convincing cardinal change assertion,

Plaintiff's position on this issue is fatally

undercut by the bilateral modification made

to the delivery schedule in 1988.

(Petitioner’s Appendix, pp. 146a-147a).

This holding, unsupported by citation of law, was adopted

by the Court of Appeals. The Modification alluded to contained

a eS nannies

5

no waiver language’ and did not change the total contract price.

(Petitioner’s Appendix, p. 190a).

The Decision of the Court of Appeals to uphold and endorse

the concept of “implicit waiver” is a radical departure from

Federal Case law, as enunciated both by this Court and the courts

of other circuits.

As early as 1875, this Court reasoned, in Phillips, Etc.,

Construction Company v. Seymour et al., 91 U.S. 646, 651:

... if A. agree to deliver a horse, buggy, and

harness on Monday, and B. accepts delivery

of the horse and buggy, can he refuse to pay

any thing, though he accepts delivery of the

harness on Tuesday? This is absurd. He

waives, by this acceptance, the point of time

as to the harness, at least so far as A.’s right

to recover the agreed sum is concerned. If B.

have suffered any damage by the delay, he

can recover it by an action on A.’s covenant

to deliver on Monday; ...

The Court went on to point out that the contractor, plaintiff

in error Phillips, did not “waive its right to damage”, but waived

only its right to “forfeiture”. 91 U.S. 646 at 652.

So basic is the concept that one does not renounce his right

to damages when, after breach, he continues to perform, that it

can be found in the most elementary treatises on contract law.

For instance, West Publishing Company, in its Hornbook series

on Contracts, instructs the reader:

3. Actually, it contained a saving clause. See Footnote 1, supra.

Thus, rather than “implicitly” waiving its damage claims, Amertex

explicitly preserved them.

6

If the breach is material, the aggrieved party

may cancel the contract. He may sue also for

a total breach if he can show that he would

have been ready, willing and able to perform

but for the breach. However, he also has the

option of continuing with the contract and

sue for a partial breach.

Contracts, Calamari and Perillo, 3rd Edition, at Page 458;

emphasis supplied.

Likewise, the widely accepted American Jurisprudence

states the following on the issue:

Where there has been a material breach, the

injured party has an election of continuing

performance, or of ceasing to perform, or of

repudiating the contract. Any act by the

injured party indicating an intent to continue

will operate as a conclusive election, not

depriving him of his right of action for the

breach which has already taken place, but

depriving him of any excuse for ceasing

performance on his own part.

17A Am. Jur. 2d (Revised), Contracts § 731; emphasis supplied.

The court below’s predecessor, the United States Court of

Claims, whose precedents are meant to be binding on the Federal

Circuit, came to the same conclusion two decades ago in Cities

Service Helex v. The United States, 543 F.2d 1306 (Ct. Cl. 1976)

(The case, cited by the dissenting Judge in the instant case, was

ignored in the majority opinion). In Cities Service Helex, supra,

the court, citing the Restatement, Williston, Corbin and The

Uniform Commercial Code, among others, reiterated what this

7

Court had held in Phillips, Etc., Construction Company, supra,

i.e., one does not forfeit a claim for breach damages by agreeing

to continue performance. The United States Court of Claims

reasoned as follows:

A material breach does not automatically and

ipso facto end a contract. It merely gives

the injured party the right to end the

agreement; the injured party can choose

between canceling the contract and

continuing it. If he decides to close the

contract and so conducts himself, both parties

are relieved of their further obligations and

the injured party is entitled to damages to the

end of the contract term (to put him in the

position he would have occupied if the

contract had been completed). Jf he elects

instead to continue the contract, the

obligations of both parties remain in force

and the injured party may retain only a claim

for damages for partial breach. See generally

5 S. Williston, Contracts §§ 638-88 (3d ed.

W. Jaeger 1961); Restatement of Contracts

§§ 317, 309-10 (1932); 17 Am.Jur.2d

Contracts §§ 446-47, 489, 503, 510 (1964);

Acme Process Equip. Co. v. United States,

171 Ct.Cl. 324, 334-37, 347 F.2d 509, 515-

16 (1965), rev’d on other grounds, 385 U.S.

138 (1966); Airco, Inc. v. United States, 205

Ct.Cl. 493, 497-99, 504 F.2d 1133, 1135-37

(1974); DeVito v. United States, 188 Ct.Cl.

979, 990-991, 413 F.2d 1147, 1153-54

(1969); Ling-Temco-Vought, Inc. v. United

States, 201 Ct.Cl. 135, 144-50. 475 F.2d 630,

636-39 (1973); Northern Helex Co. v. United

8

States, 197 Ct.Cl. 118, 125-26, 455 F.2d 546,

551 (1972).

. .. [S]Jome courts and commentators and the

Uniform Commercial Code have modified

various aspects of this strict view. In

Northern Helex Co. v. United States, 197

Ct.Cl. 118, 455 F.2d 546 (1972), the court

adopted the position that the injured party

may itself continue performance in certain

circumstances and yet reserve its right to

claim material breach without the breaching

party’s assent. Jd. at 129-30, 455 F.2d at 553;

see Uniform Commercial Code § 1-207.

Some courts have shared Professor Corbin’s

view that an election should not be conclusive

unless facts giving rise to an estoppel exist;

either the breaching party must have changed

his position in reliance on the injured party’s

failure to cancel or the injured party’s

conduct must be such that it would be unjust

to allow him to change his position. 5A A.

Corbin, Contracts § 1220 (1964); Western

Transmission Corp. v. Colorado Mainline,

Inc., 376 F.2d 470, 472 (10th Cir. 1967); see

United States v. Chichester, 312 F.2d 275,

282 (9th Cir. 1963); 5 S. Williston, supra,

§ 686, at 289-91; cf. Ling-Temco- Vought, Inc.

v. United States, supra at 145-46, 475 F.2d

at 636-37 (court stressed extra expense

incurred by Government); DeVito v. United

States, supra (elements of waiver of default

in delivery include reliance and continued

9

performance of delinquent party). The

authors of the Uniform Commercial Code has

also rejected the mechanical application of

the doctrine of election of remedies:

“Whether the pursuit of one remedy bars

another depends entirely on the facts of the

individual case”. Uniform Commercial Code

§ 2-703, Comment 1.

543 F.2d at Pages 1313-1314; emphasis supplied.

In addition to overlooking the tenets of this Court, learned

treatises, and its own decisions, the court below overlooked the

law as pronounced by other Circuit Courts of Appeals. See II,

infra.

Il.

THE FEDERAL CIRCUIT’S OPINION DIRECTLY

CONFLICTS WITH NUMEROUS DECISIONS IN

VARIOUS CIRCUITS, WHICH, BASED ON MODERN

VIEWS OF CONTRACT LAW, HOLD THAT A NON-

BREACHING PARTY TO A CONTRACT DOES NOT

LOSE ITS RIGHT TO SUE FOR BREACH DAMAGES BY

FAILING TO END THE CONTRACT AND AGREEING TO

CONTINUE PERFORMANCE.

The Decision below is in direct conflict with the following

decisions from other Circuits: Sitlington v. Fulton, 281 F.2d

552 (10th Cir. 1960); First Citizens Federal Savings and Loan

Association v. Worthen Bank and Trust Company, NA, 919 F.2d

510 (9th Cir. 1990); Dunkin’ Donuts of America, Inc. v. Minerva,

Inc., 950 F.2d 1566 (11th Cir. 1992). Havoco v. Hilco, 799

F.2d 349, on remand, Havoco of America Ltd. v. Hilco, Inc.,

750 F. Supp. 946, affirmed, 971 F.2d 1332 (7th Cir. 1986); Fuller

10

Company v. Brown Minneapolis Tank and Fabricating Company,

678 F. Supp. 506 (E.D. Pa. 1987); S. Leo Harmony, Inc. v. Binks

Manufacturing Company, 597 F. Supp. 1014 (S.D.N.Y. 1984).

The Tenth Circuit, in Sitlington, supra, held that the non-

breaching party to a contract for the sale of property (in this

instance, the buyer) had a choice upon the other party’s (i.e.,

the seller’s) breach: (1) Rescind the contract and sue for breach;

or (2) Require performance, retaining a cause of action for

damages.

According to the Tenth Circuit:

Any act by the injured party indicating an

intent to continue performance is deemed a

conclusive election. But by the election to

continue performance he does not forego his

right of action to recover damages caused by

the breach. [citing, inter alia, Williston on

Contracts, 2nd Edition § 1334 at Page 3749].

The Eleventh Circuit, in Dunkin’ Donuts of America, Inc. v.

Minerva, supra, was faced with a suit arising out of a franchise

agreement, where the franchisee continued in performance after

a breach. The majority held that under Arizona law, *he

franchisee still had the right to maintain an action for partial

breach; the dissent argued that the franchisee’s right was to sue

for total breach.

In First Citizens’ Federal Savings and Loan Association v.

Worthen Bank and Trust Company, supra, the Ninth Circuit held

that a non-breaching party, when faced with a material breach

by the other party may elect to rescind the contract or may opt

for performance and a right of action for damages.

1]

The Seventh Circuit also recognizes the innocent party’s

right to continue performance without waiving its right to sue

for damages. In Havoco v. Hilco, supra, the court’s opinion stated

the principle thusly:

It is clear that under Illinois law, a waiver

can be implied from conduct [citations

omitted]. It is also clear that an essential

element of waiver is that the injured party

intended to affirm the contract and intended

to abandon his right to recover damages.

[citations omitted]. “If the intention to waive

is implied from conduct, the conduct should

speak the intention clearly”. Barkers Trust

Company v. Pacific Employees Insurance

Company, 288 F.2d 106, 111 (9th Cir., 1960).

799 F.2d at 353-354.

Both the Third and Second Circuits have taken the same

position, enunciated in District Court decisions. Of special

interest is the decision by the Eastern District of Pennsylvania

(Third Circuit), in Fuller Company v. Brown Minneapolis Tank

and Fabricating Company, supra. The court held that a party

who continues to perform on a cardinally-changed contract loses

the right to cease performance; its remedy is limited to a claim

for damages. 678 F. Supp. at 509-510.

The District Court for the Southern District of New York

(Second Circuit) held, in S. Leo Harmony, Inc. v. Binks

Manufacturing Company, supra, that the non-breaching party

to a contract could elect not to abandon performance, complete

the contract and sue for damages traceable to the defendant's

breach.

12

Il.

THE WRIT SHOULD BE GRANTED BECAUSE THE

CASE IS AN IMPORTANT ONE OVER AND ABOVE ITS

CONFLICT WITH OTHER CIRCUITS AND WELL-

SETTLED LAW.

By labeling its Decision as non-precedential, when, as noted

in the dissent, stare decisis was to the contrary, the court below

crafted a special, secret law for a socially and economically-

disadvantaged company. The effect is not unlike the effect of

Caligula’s law. (That Roman Emperor was fond of placing his

edicts high on the public pillars where they could not be read,

and then enforcing the edicts selectively). The suggestion that

there can be unstated agreements in written modifications,

whether they involve contractor claims or interpretation of

contract provisions, is so sweeping and fraught with peril that it

takes on equal protection and due process aspects.

Although Amertex was granted a forum in which it could

be heard, it was denied the benefit of a nationally accepted,

deciding principle available to others and upon which it had a

right to rely, i.e., a contractor does not lose its right to claim

breach damages when it agrees to continue performance.

Certainly, if the majority decision is well-grounded in law, is

holding (i.e. that a bilateral modification extending the delivery

schedule implicit[ly] carries with a waiver of the right to breach

of contract damages) is of considerable importance to the

Government Contract legal community as Petitioner submits, it

is and certainly precedential value. If, as Petitioner submits, it

is not well-grounded in law, then the decision amounts to

singling out this Government contractor unconstitutionally by

adopting a rule that applies only to it.

13

CONCLUSION

The Writ should be granted. It is now undisputed that

Amertex and its bank subsidized research and development for

a contract falsely awarded under the guise of being a mass-

production contract, supported by design specifications. In

deciding the case, the court below has overlooked its own

decisions, misapprehended the established law of “election of

remedies”, and brought itself into conflict with principles

applied and cases decided by other circuits and its own precedent

when it concluded that continued performance waives accrued

breach damages.

Respectfully submitted,

JOSEPH H. REITER

Counsel of Record

KOSTOS AND LAMER, P.C.

Attorneys for Petitioner

1608 Walnut Street

Suite 1300

Philadelphia, Pennsylvania 19103

(215) 545-0570

la

APPENDIX A — DECISION OF THE UNITED STATES

COURT OF APPEALS FOR THE FEDERAL CIRCUIT

DECIDED FEBRUARY 24, 1997

NOTE: Pursuant to Fed. Cir. R. 47.6, this

disposition is not citable as precedent. It is a

public record. The disposition will appear in

tables published periodically.

United States Court of Appeals for the Federal Circuit

96-5070

AMERTEX ENTERPRISES, LTD.,

Plaintiff-Appellant,

Vv.

THE UNITED STATES,

| Defendant-Appellee.

DECIDED: February 24, 1997

Before NEWMAN, MICHEL and SCHALL, Circuit Judges.

Opinion for the court filed by Circuit Judge MICHEL. Dissenting

opinion filed by Circuit Judge NEWMAN.

MICHEL, Circuit Judge.

Amertex Enterprises, Ltd. (“Amertex”) appeals the

consolidated, post-trial decision of December 15, 1995 of the

Court of Federal Claims, Nos. 90-684, 91-1700, and 92-402,

2a

Appendix A

denying its claim for cardinal change breach of a contract,

granting its claim for an equitable adjustment for delay caused

by the United States (“government”), holding that the

government's termination for default was justified, and offsetting

the equitable adjustment with the amount of unliquidated

progress payments due to the justified termination. The case

was submitted for decision after oral argument on December 5,

1996. Because we agree with the trial court that Amertex waived

its cardinal change claim by entering into bilateral modifications,

and because the trial court did not reversibly err in its calculation

of delay damages, or holding of justified default termination,

we affirm.

BACKGROUND

The detailed facts of the case are set out in the opinion of

the Court of Federal Claims. Amertex Enterprises, Ltd. v. United

States, Nos. 90-684 C, 91-1700, and 92-402 (Fed. Cl. 1995). In

brief, Amertex was awarded a government contract for the

production of chemical warfare protective suits (“chemsuits”)

on February 25, 1985. A total of 2,415,885 chemsuits were to

have been produced by December 29, 1986. In the words of the

Court of Federal Claims, “[f]rom its inception, this procurement

was plagued by poor decisions, mistakes, and miscommunication

that delayed and disrupted Amertex’s performance of its

obligations.” During the course of performance, the government

issued 42 modifications and eight amendments to the contract,

totaling over 100 changes to the specifications for the chemsuits.

Also during the course of performance, and after many of these

unilateral modifications and amendments, Amertex and the

government entered into bilateral modifications of the contract

which provided for a revised payment scheme and delivery

schedule. The government eventually terminated the contract

3a

Appendix A

for default on January 6, 1989, over two years after the original

deadline. Amertex had delivered fewer than half of the chemsuits

it had agreed to deliver in the original contract.

Amertex submitted ‘wo claims to the Contracting Officer,

one challenging the termination for default, and the second

alleging a breach of the contract through cardinal change and

seeking an equitable adjustment based on delay and disruption

allegedly caused by the government. Both claims were denied,

and Amertex filed suit in the United States Court of Federal

Claims, which denied Amertex’s cardinal change claim and

default termination challenge, but granted in part its claim for

an equitable adjustment. This appeal timely followed.

DISCUSSION

Decisions of the Court of Federal Claims are subject to only

limited review. Factual findings are reviewed for clear error,

while legal conclusions are reviewed de novo. Alger v. United

States, 741 F.2d 391, 393 (Fed. Cir. 1984).

I.

Amertex first appeals the holding that the series of changes

that the government made to the contract did not constitute a

cardinal change. This court reviews the holding of a cardinal

change de novo. See, e.g., AT&T Communications, Inc. v. Wiltel,

Inc., 1 F.3d 1201, 1207-08 (Fed. Cir. 1993). A cardinal change:

occurs when the government effects an

alteration in the work so drastic that it

effectively requires the contractor to perform

duties materially different from those

4a

Appendix A

bargained for. By definition, then a cardinal

change is so profound that it is not

redressable under the contract, and thus

renders the government in breach.

AT&T Communications, | F.3d at 1205 (citing Allied Materials

& Equip. Co. v. United States, 569 F.2d 562, 563-64 (Ct. Cl.

1978)). As to Amertex’s cardinal change claim, the Court of

Federal Claims stated:

Notwithstanding the evidence supporting

plaintiff’s plausible and potentially

convincing cardinal change assertion,

plaintiff’s position on this issue is fatally

undercut by the bilateral modification made

to the delivery schedule in 1988.

Although Amertex argues that, when presented with the

bilateral modifications, it “could not ... walk away” from the

contract, it has neither pleaded nor proven duress. The signed

modifications evidence a meeting of the minds and, since

the modifications changed both parties’ obligations, are

supported by consideration. Thus, the bilateral modifications

-are enforceable contracts which replace the parallel provisions

of the original contract. As noted above, the bilateral

modifications included modifications to the delivery schedule

and the payment scheme. By agreeing to these modifications,

Amertex implicitly agreed to a changed specification and added

costs it accrued thereby. As stated by the Court of Federal

Claims, “[i]Jn essence, Amertex promised to produce the

modified chempro suit, with all changes which had been made

to July 1988 and given the numerous other government-caused

difficulties, on a schedule contemplating half the pace as the

Sa

Appendix A

original contract.” Moreover, by advancing payment due dates

to delivery installment dates, Amertex bargained for and received

an infusion of working capital that was needed in light of

performance difficulties but that was not contemplated in the

original payment scheme. Since Amertex agreed to the changes,

it implicitly agreed that the changes were within the changes

clause of the contract. There can only be a cardinal change if

the government required Amertex to perform materially different

duties from those bargained for in the contract as modified.

Amertex does not so allege.

Amertex argues that Air-A-Plane Corp. v. United States,

408 F.2d 1030 (Ct. Cl. 1969), suggests a different result. In Air-

A-Plane, a plaintiff was allowed to pursue both an equitable

adjustment through the Armed Forces Board of Contract Appeals

(“ASBCA”) and a cardinal change claim through the Court of

Claims. In rejecting the government’s argument that the plaintiff

was estopped from pursuing its cardinal change claim by virtue

of its equitable adjustment claim, the court stated:

This is an instance of an imposed election of

remedies which seems to us unfair to

contractors. One who was confident that

Government modifications created a cardinal

change, for which he could go to court at

once, would still be well advised to pursue

his administrative remedy under the Changes

clause. If he failed to do so and the court

decided that the alterations were not cardinal

but within the clause, the contractor could

well be left without any remedy at all —

though it was clear that he was entitled to

some compensation on one basis or the other.

Id. at 1034.

6a

Appendix A

Amertex asserts that the instant situation is analogous —

that it should not be required to decline to enter into the

modification at the peril of losing its cardinal change claim.

We disagree with Amertex’s reasoning. Air-A-Plane turned

on the procedural limitations of the ASBCA at the time the case

was brought. At that time, the ASBCA did not have jurisdiction

to hear cardinal change claims. Jd. Here, it was possible for

Amertex to make both equitable adjustment and cardinal change

claims in the same forum (as it did). Thus, there was no “imposed

election of remedies” as criticized in Air-A-Plane. Although

Amertex did need to decide whether to enter into the

modifications or seek cardinal change breach remedies, this was

a business choice, not mandated by jurisdictional statutes.

Il.

Since there was no cardinal change, Amertex is entitled only

to an equitable adjustment for delay damages caused by the

government. Amertex appeals the Court of Federal Claims’

finding that the government was solely responsible for only 36%

of the 952 days of delay in the contract. Delay must be

apportioned solely to one party for damages to be awarded.

Blinderman Constr. Co. v. United States, 695 F.2d 552, 559 (Fed.

Cir. 1982). Thus, Amertex cannot recover for any of the

government’s delay that is concurrent or intertwined with other

delays. Commerce Int'l Co. v. United States, 338 F.2d 81, 90

(Ct. Ci. 1964). The determination of delay causation is a question

of fact. J.D. Hedin Constr. Co. v. United States, 347 F.2d 235,

245 (Ct. Cl. 1965).

Amertex argues that the trial court misapplied Critical Path

Methodology (“CPM”) in calculating delay. CPM looks only to

7a

Appendix A

delay along the “critical path,” that is, those parts of a project

that, if delayed, delay the entire project, to determine allocation

of delay. Delay in non-critical path components of the project,

because it does not delay the completion of the entire project,

does not result in allocation of delay. CPM has typically been

used in construction contracts where the determination of those

parts of the project on the critical path is straightforward. See,

e.g., Haney v. United States, 676 F.2d 584, 595 (Ct. Cl. 1982);

G.M. Shupe, Inc. v. United States, 5 Cl. Ct. 662, 728 (1984);

Sterling Millwrights, Inc. v. United States, 26 Cl. Ct. 49, 75

(1992).

The trial court here recognized that CPM is most useful in

those contexts where the determination of the critical path is

straightforward, but, nonetheless, was “unpersuaded that CPM

is useless in the more complex manufacturing context.” Although

Amertex argues that the Court of Federal Claims incorrectly

applied CPM, it does not argue, nor can it, that the court was

even obligated to apply CPM, or any particular modification of

CPM, for use in this manufacturing context.

We have carefully reviewed the Court of Federal Claims’

detailed and thoughtful delay analysis. Although the analysis

that the court did is certainly not the only conceivable method

of analysis, and although there may be improvements that could

have been made to the analysis (for instance, analysis of the

causal effect of early government-caused delay on later Amertex-

caused delay), we cannot hold that the analysis is clearly

erroneous. Neither can we hold that the failure of the Court of

Federal Claims to separately label disruption costs (costs caused

by the government by creating more work for Amertex, not

merely delaying Amertex’s ability to perform) was clearly

erroneous.

8a

Appendix A

Ill.

Finally, Amertex challenges the Court of Federal Claims’

upholding of the default termination. The court held that the

government met its burden of proof that Amertex’s financial

condition at the time of the default termination made it

reasonably likely that the contractor would be unable to finish

performance in the remaining time. See Lisbon Contractors, Inc.

v. United States, 828 F.2d 759, 765 (Fed. Cir. 1987). The court

further held that Amertex did not have a valid defense of excuse

because the poor financial condition of the company was not

primarily caused by the acts or omissions of the government.

See TGC Contracting Corp. v. United States, 736 F.2d 1512,

1515 (Fed. Cir. 1984).

Amertex argues that the factual findings relied on by the

Court of Federal Claims are in error. We have carefully

considered Amertex’s arguments and discern no clear error in

the Court of Federal Claims’ analysis. Based on these underlying

facts, the court reached the correct legal conclusion that the

default termination was justified.

IV.

The Court of Federal Claims correctly held that the bilateral

modifications are binding and therefore there was no cardinal

change, and there was no clear error in the allocation of delay

or default termination factual analysis. The decision of the Court

of Federal Claims is therefore affirmed.

9a

APPENDIX B — DISSENTING OPINION BY CIRCUIT

JUDGE NEWMAN OF THE UNITED STATES COURT OF

APPEALS FOR THE FEDERAL CIRCUIT

DATED FEBRUARY 24, 1997

NOTE: Pursuant to Fed. Cir. R. 47.6, this

disposition is not citable as precedent. It is a

public record. The disposition will appear in

tables published periodically.

United States Court of Appeals for the Federal Circuit

96-5070

AMERTEX ENTERPRISES, LTD.,

Plaintiff-Appellant,

Vv.

THE UNITED STATES,

~, Defendant-Appellee.

NEWMAN, Circuit Judge, dissenting.

I respectfully dissent, for the Court of Federal Claims

applied incorrect law in holding that the contract modification

of the payment and delivery schedules, three and a half years

after commencement of the two-year contract, was a waiver by

Amertex of any claim that the government had cardinally

changed the contract. There was no waiver or release of such a

claim, at any time.

The Court of Federal Claims made many findings relevant

to the extent of the changes in the design specifications, and

10a

Appendix B

how these changes affected Amertex’s performance. The court

found as fact that the design was new and untested, that the

specifications were inadequate or incorrect, and that the contract

was not performable in accordance with its terms. The court

concluded that “The fixed price contract became, in part, a

research and development contract.” However, following this

exposition, the court found as follows:

The unreasonable rejection of the second

First Articles and the other unreasonable acts

by the government which undermined this

project hampered mass production and,

arguably, fundamentally changed the nature

of this contract.

Notwithstanding the evidence supporting

plaintiff’s plausible and potentially

convincing cardinal change assertion,

plaintiff’s position on this issue is fatally

undercut by the bilateral modifications made

to the delivery schedule in 1988.

Thus although the Court of Federal Claims found that the claim

of cardinal change was “plausible and potentially convincing,”

the court apparently inferred either release or waiver. That

conclusion is incorrect, for the modification to the delivery

schedule did not release or waive this claim, which related not

to delivery, but to all of the contract changes. So substantive

and financially significant a change in the contractor’s rights

can not be inferred from a contract modification that is silent

on the matter of release of claims. See Laka Tool & Stamping

Co. v. United States, 639 F.2d 738, 743 (Ct. Cl. 1980) (contractor

did not waive claim for equitable adjustment when contract

lla

Appendix B

modification did not contain an express waiver of the claim),

cert. denied, 454 U.S. 1086 (1981).

The modification simply extended the delivery dates of the

now delayed product, and provided for payment based on

deliveries. It neither expressly nor by implication withdrew from

the contractor the legal right to recover on an otherwise valid

claim that the contract had been cardinally changed.

The panel majority offers the theory that since Amertex did

not allege duress in accepting the contract modification, it can

not argue that it did not waive its claim. Duress, alleged or not,

is not at issue. The contractor was not required to walk away

from the contract instead of entering into the modified delivery

and payment terms, in order to preserve a claim for cardinal

change.

“Under established case law, a cardinal]

change is a breach. It occurs when the

government effects an alteration in the work

so drastic that it effectively requires the

contractor to perform duties materially

different from those bargained for. By

definition, then a cardinal change is so

profound that it is not redressable under the

contract, and renders the government in

breach.”

AT & T Communications, Inc. v. Wiltel, Inc., 1 F.3d 1201, 1205

(Fed. Cir. 1993) (quoting Allied Materials & Equip. Co. v. United

States, 569 F.2d 562, 563-64 (Ct. Cl. 1978)).

Cardinal change relates to changes in the entire contract,

12a

Appendix B

with all of its modifications. Atlantic Dry Dock Corp. v. United

States, 773 F. Supp. 335, 339-40 (M.D. Fla. 1991):

[D]etermining the merits of a cardinal change

claim requires an examination of the totality

of the circumstances surrounding the project

and the many modifications. . . . These facts

cannot be nown until the project is

completed or nearly completed.

Indeed, had Amertex wal ed away from the contract, such an

action could have speeded Amertex’s financial demise, for

progress payments were being retained. A business decision to

continue to perform does not waive a contractor’s recourse to

remedy on a theory of cardinal change. Cities Service Helex

ne. v. United States, 543 F.2d 1306, 1313 (Ct. Cl. 1976):

A material breach does not automatically and

ipso facto end a contract. It merely gives the

injured party the right to end the agreement;

the injured party can choose between

canceling the contract and continuing it.

See Allied Materials, 569 F.2d at 564 (“Undoubtedly, the

cautious contractor might often proceed under the revised

coniract because of doubt whether he could invo e the cardinal

change doctrine.”)

The Court of Federal Claims did not mae a final finding

on the issue of cardinal change, instead holding that any claim

on this ground was waived. The panel majority has ratified this

error by requiring duress while ignoring the absence of either

waiver or release. It is irrelevant whether there were hard

13a

Appendix B

economic decisions made by Amertex; the question of law is

whether there was a waiver or release of this claim, and there

plainly was not. The decision of the Court of Federal Claims,

since based on incorrect law, should be vacated, and the matter

returned to the trial court for final determination of the issue of

cardinal change.

l4a-

APPENDIX C — OPINION AND ORDER ON LIABILITY

AND DAMAGES OF THE UNITED STATES COURT OF

FEDERAL CLAIMS DATED DECEMBER 15, 1995

UNITED STATES COURT OF FEDERAL CLAIMS

December 15, 1995

Nos. 90-684 C, 91-1700 and 92-402 (consolidated)

AMERTEX ENTERPRISES, LTD.,

Plaintiff,

versus

UNITED STATES OF AMERICA,

Defendant.

Marc Lamer, Philadelphia, Pa., for plaintiff. Ruth E.

Ganister, Philadelphia, Pa., of counsel.

Sheryl L. Floyd, Washington, D.C., with whom was Frank

W. Hunger, Assistant Attorney General, for defendant. S. Lane

Tucker and Sandra Guydon, Washington, D.C., of counsel.

OPINION AND ORDER ON LIABILITY AND DAMAGES

TURNER, Judge.

This opinion addresses the merits of three consolidated

cases (filed pursuant to the Contract Disputes Act, 41 U.S.C.

§ 605(a)) involving a multi-million dollar supply contract. Final

post-trial arguments were conducted on June 21, 1994. This

decision resolves both liability and damages.

—————————aaaEEeEeEeEeEeEeEeEeEeEeEwee

15a

Appendix C

Plaintiff agreed to manufacture over 2.4 million chemical

protective (chempro) suits for defendant in exchange for

approximately $96 million. After more than four years of

intermittent delay, defendant terminated the contract for default,

contending that plaintiff's poor financial condition endangered

completion of the contract. The parties blame one another,

almost exclusively, for plaintiff’s slow progress and financial

problems.

Upon consideration of voluminous testimony and thousands

of exhibits presented during a trial spanning eight weeks over a

period of several months, and, further, upon consideration of

extensive briefing, it is concluded as follows: First, plaintiff

failed to prove that defendant breached the contract under the

theory of cardinal change. Second, plaintiff demonstrated that

it deserves an equitable adjustment for that portion of delay

and disruption attributable solely to defendant. Third, not-

withstanding those delay and disruption damages, defendant

proved that the termination for default was justified. Fourth,

defendant established its right to the balance of unliquidated

progress payments less the amount of plaintiff's equitable

adjustment,

I,

The parties’ versions of relevant events could hardly be more

diametric. Their antagonism compounds the exceptionally

tangled facts giving rise to this contract dispute. In such a

context, Justice Jackson’s observation seems apt: “It can never

be made simple, but we can try to avoid making it needlessly

complex.” Dobson v. Commissioner of Internal Revenue, 320

U.S. 489, 495 (1943) (describing tax law). With this goal in

mind, we chronicle the life of the contract in dispute.

16a

Appendix C

A. Solicitation & Award

On September 7, 1984, the United States government'

solicited sealed bids for the mass production of chempro suits.

DX-2001.? The manufacture of these chemical warfare protective

uniforms involved both the sewing of a nylon cotton (nyco) twill

outer garment treated with quarpel water-proofing and the

attaching of a lining sewn from a nylon tricotton (tricot) material

laminated with a special charcoal. The chempro design also

required the attachment of butyl-coated reinforcement patches

and special “atropine” pockets designed to allow the wearer to

gain access to antitoxin syringes kept near the body for warmth.

In all, the technical data package (TDP) detailing assembly of

the garments required more than 162 manufacturing operations

for each chempro suit, referenced twenty-one primary

specifications, and imposed stringent testing requirements on

both components and final products. DX-3078.

The solicitation requested bids for the manufacture of

millions of chempro suits in accordance with specification MIL-

S-43926D, called “specification D.” In internal memoranda, the

government described this procurement as “an accelerated

program designed to correct a critical deficiency in the standard

1. For clarity, the terms “defendant” or “government” will be used

in place of the acronyms for the several government agencies involved in

this contract. On cefendant’s side, the chempro suit procurement involved

cooperation among the Defense Personnel Support Center, United States

Army Natick Research & Development Laboratories, Defense Logistics

Agency, Defense Contract Audit Agency, and numerous subdivisions

within these agencies. The specific government actor will be mentioned

only when necessary.

2. Defendant's and plaintiff's trial exhibits are cited as “DX-" and

“PX-,” respectively. References to trial transcripts are designated as “Tr.”

17a

Appendix C

chemical protective overgarment.” DX-2155. Amertex

Enterprises, Ltd., (Amertex) submitted a unit price bid of $39.88

per chempro suit for the production of the uniforms within a

670 day period. Amertex’s bid was 1.3 %, or 52 cents, lower per

suit than the closest bid of a qualified, experienced competitor.

PX-284. Five firms bid within twenty-five percent of Amertex’s

bid. DX-2153.

Before accepting Amertex’s bid, however, the government

conducted two detailed pre-award surveys of the company. These

surveys concluded that Amertex was capable of successfully

performing the terms of the solicitation. In particular, the

government determined that Amertex possessed the experience,

production capacity, accounting system, and quality control

procedures necessary to fulfill the procurement requirements.

DX-2015. In fact, Amertex had participated in the production

of millions of chempro suits under a previous design of the suit,

specification B. PX-284. The company also had manufactured

hundreds of thousands of fragmentation vests, military shirts,

and duffle bags for the government on other contracts. PX-284.

The government also examined whether Amertex was

certified as a small business under the government’s 8(a)

program. 13 C.F.R. §§ 121 & 124 (1984). The government

elected to offer this enormous and expedited procurement as a

“total small business set-aside” for contractors employing no

more than 500 workers. DX-2001. Such a set-aside necessarily

required that the government provide the selected prime

contractor and its subcontractors with compatible patterns and

consistent interpretations for the production of the 2.4 million

chempro suits. Amertex fulfilled the small business requirement.

Upon completion of the pre-award surveys, the government

18a

Appendix C

selected Amertex as the lowest responsive and responsible

bidder. On February 25, 1985, the government awarded to

Amertex contract number DLA100-85-C-0402. DX-2002. In the

contract, the government accepted Amertex’s bid unit price and

Amertex agreed to produce 2,415,885 chempro suits for

$96,345,493.80. The contract set forth a rapid delivery schedule

and referenced numerous specifications, many of which were

modified after contract award.

B. Testing of the Specifications

From its inception, this procurement was plagued by poor

decisions, mistakes, and miscommunication that delayed and

disrupted Amertex’s performance of its obligations. Even prior

to contract award, government actions created an unstable

foundation for successful completion of the contract. For

instance, defendant ignored the recommendation of the designers

of the new suit that the garment be tested for mass production

through the use of an “expanded First Article.”? DX-2127. This

type of First Article is described in the “Memorandum of

Agreement for Clothing, Textiles, and Equipment Between

Defense Personnel Support Center and U.S. Army Natick

Research & Development Laboratories [Natick]” as follows:

In this procedure, a contractor makes a

quantity of items under production conditions

to determine the validity of the technical data.

The contractor is required to critically review

the TDP prior to and during first article

production and to make all required changes.

3. “First Articles” are preliminary samples, or prototypes, of the

garment.

19a

Appendix C

PX-1. In contrast, when a First Article is not “expanded,” the

contractor is required to make a nominal quantity to demonstrate

the ability to interpret the TDP so as to produce an acceptable

finished item. PX-1. Generally, an unexpanded First Article is

used either after the initial procurement of a new specification

or when revisions involve “simple” clothing items.

The design engineers urged that the revised patterns and

specifications for the chempro suit be verified under mass

production conditions through the manufacture of several

hundred suits in the full range of sizes. See PX-2; Tr. 7941-42

(Levell). The engineers recommended an expanded First Article

because the technical data package for specification D involved,

in their words, “major changes” from the preceding

specification. PX-2. These changes included the addition of buty!

protective pieces at the elbows and the knees; the use of the

chemical phoschek with the state-of-the-art additive

polyethylene oxide (polyox) in the mixture (slurry) for the

charcoal laminated lining (“Type III” charcoal laminate); the

addition of atropine syringe pockets on the coat; the addition of

other pockets on the sleeves; the addition of gussets at the leg

closures; the redesign of the chest pockets to incorporate side

entrance; the addition of hip pockets on the trousers; and the

change to bellows-type pockets with flaps on the trousers.

In light of these revisions, the engineering memorandum

indicates that there were concerns about sending specification

D into full-scale production without adequate testing via an

expanded First Article. Tr. 7940-41 and 7943-48 (Levell). When

an expanded First Article is not used, the government usually

requires the contractor to produce a “standard” First Article of

fifty suits of varying sizes before full-scale production can begin.

Tr. 4702-04 (Hepner), Tr. 4498 (Pease), Tr. 3077-78 (Price).

Nevertheless, the government chose to use a First Article of five

20a

Appendix C

units, that is, five samples to be produced individually rather

than en masse. DX-2001. Had the government used an expanded

First Article, the contractor would have known that the new

specifications had not been tested for accuracy in mass

production. Indeed, under an expanded First Article, once a

contractor “certifies [that] the TDP is adequate for mass

production, future changes (other than product improvement)

are made at no cost to the government.” PX-1.

To justify its decision to override the engineering

recommendation for an expanded First Article, the government

relied in part on the testimony of Lisa Hepner, a quality specialist

for the government. Although the use of an expanded First Article

is normal after the issuance of such a revised specification (Tr.

4199), Hepner testified that no such testing was necessary

because, in her opinion, the changes from the previous

specification were minor. Tr. 4676.

The government’s heavy reliance on Hepner’s opinion in

this instance was misplaced. At the time of the decision, Hepner

had held her position for less than a year, had only one month

of government training courses, and had no professional

experience in the manufacturing or sewing industries. DX-3333.

The changes to the specification, on their face, cannot reasonably

be dismissed as “minor.” The engineers contemporaneously

assessed that specification D embodied “major changes.” Some

of these major changes were needed, urgently, to correct a

“critical deficiency” in the previous specification for the

chempro suits, which were called “overgarments” at that time.‘

4. Indeed, it appears that defendant “rushed” specification D into

production because an expanded First Article would have lengthened this

expedited procurement for the new chempro suits designed to correct a

> potentially lethal defect in the old garments. See DX-2132; DX-2155.

PE TE ee

21a

Appendix C

We are similarly unpersuaded by defendant’s other main

explanation for its decision to override the engineering

recommendation for an expanded First Article. At trial, the

government insisted that no expanded First Article was warranted

because the adequacy of specification D had already been tested

prior to the solicitation. To support this contention, the

government notes that Winfield Manufacturing Company

(Winfield), one of Amertex’s competitors, produced 200 of the

chempro overgarments in July 1983. The government evaluated

fifty of the suits and identified 158 defects. DX-2138. Even

though the government recognized that the Winfield suits had

“an exceptional amount of deficiencies,” it observed that “the

lot should be accepted since none will affect the serviceability,

or involved any of the unique design changes for which the end

item was produced, or will be evaluated for, in field testing.”

DX-2138.

Indeed, as Don Wadja (project director at Natick for

chempro suits prior to 1985) testified, the primary purpose of

the Winfield samples was to subject the suits to field testing,

i.e., Chemical agent and human factors (wear) testing, not to

verify that the design was sufficiently accurate for the mass

production of millions of the garments. Tr. 4151-53, 4162-64

(Wadja). Moreover, unlike Amertex, Winfield was not charged

with manufacturing its own quarpel-treated nyco and charcoal

laminated tricot lining. Winfield received the materials from the

government, along with one sample suit, a pattern, and a partial

table of operations. DX-2135; Tr. 4178-79 (Wadja). Additionally,

a Winfield representative, Weinsten, acknowledged at trial that

the samples were not manufactured under mass production

conditions. Tr. 7480 (Weinsten). The following exchange during

plaintiff's direct examination of Weinsten illustrates this point:

22a

Appendix C

Q: And in the course of that undertaking,

was there any effort to determine the mass

produced ability [mass produce-ability] of

the specification?

A: Not by us. It wasn’t part of the contract.

Tr. 7480 (Weinsten). We are convinced that the revised

specifications were not adequately tested for mass production.

Furthermore, the engineers recommended the use of the

expanded First Article in the memorandum dated May 31, 1984,

in spite of the Winfield suits of 1983. PX-2. The government

disregarded this recommendation, as rationalized in Hepner’s

testimony. In addition to not testing the revised specification

for “mass produce-ability,” the government elected to solicit the

manufacturing of millions of chempro suits even though it was

aware of several specific potential deficiencies with specification

D. These potential deficiencies included problems with suits

exceeding the weight requirements of the specifications and lack

of quality control provisions for the state-of-the-art charcoal

lining, among others. PX-3. Nonetheless, the government chose

to proceed with this accelerated 2.4 million unit procurement

by requiring the contractor to submit only five sample units

before advancing to full-scale production. This choice was but

one of the factors that contributed to the production disaster

that this contract became.

C. No Waiver Policy Change

Immediately following contract award, Amertex’s ability

to perform the expedited procurement successfully was

diminished by a change in the manner in which deviations were

ha i eS ea

23a

Appendix C

handled. On February 28, 1985, three days after the contract

was signed, defendant circulated a change in practice dubbed

the “No Waiver” policy, which required strict adherence to all

specifications, no matter how minor. DX-2161; DX-2349. This

policy interpreted a new regulation that became effective three

months after contract award. 48 C.F.R. § 46.407 (1985). Prior

to that time, the government traditionally allowed personnel

closely involved in a clothing procurement to give waivers for

deviations that did not affect serviceability of the item. See, e.g.,

PX-3; PX-307 (showing that the previous contractor using Type

III charcoal lining had routinely exceeded the weight

requirements and was granted waivers). In the case of the

chempro suit, those parts of the specification that had not been

revised had also not been strictly enforced in previous

procurements except when a nonconformance diverged

significantly from the specifications or adversely affected

serviceability.* One of the many examples of the past approach

toward chempro suit evaluation was the government’s acceptance

of the Winfield suits of 1983 even though 158 defects were

identified. DX-2138. According to the new interpretation, which

was not in place at the time of bid or award, deviations would

no longer be tolerated.

In an internal memorandum, the new regulation was

interpreted by the Defense Logistics Agency as follows:

[W]aivers are the exception, not the rule, and

5. See Tr. 73-74 (L. Jacobson) (stating that waivers were not an

issue because tolerances were implied when the company worked on a

previous version of the suit); Tr. 2054, 2204-06 (Ludwig) (noting that

inspectors on previous versions implied tolerances for mass production);

PX-284. See, e.g. Appeal of Vi-Mil, Inc., 82-2 BCA 15,840, 78,527,

ASBCA No. 25,111 (A.S.B.C.A., 1982). (noting that “although the

tolerances do not appear in the specifications it is undisputed . .. that

they have been allowed for many years ... .”). Cf. DX-2175.

24a

Appendix C

if the specification is wrong, take action to

change it, do not waive it .... In addition,

the [regulation] places approval of waivers

at the Center Command level as assurance

to the contract administration community that

when a waiver is approved it has been

reviewed at the highest level.

DX-2161. The purpose of the change was to improve the quality

of goods as well as to make contractual performance more

efficient by identifying and correcting inadequacies in

specifications rather than simply waiving the requirements. Cf.

DX-2166.

In the context of the Amertex chempro contract, however,

the policy’s effect was exactly the opposite. Signed prior to the

policy change, the contract between Amertex and the government

contemplated the rapid manufacture of millions of complex

garments produced through the coordination of several small

businesses. The decision to produce items in an accelerated

contract of this size involved financial assumptions related to

economies of scale, that is, cost efficiencies to be achieved under

expedited mass production conditions. See, e.g., Tr. 2994-2996

(Caldwell). In the Amertex contract, the interpretation of the

regulation as a No Waiver policy caused costly shutdowns and

slowed production for minor deviations while the contractor

awaited high level approval of waivers and clarifications. The

Situation was further aggravated because the revised

specification had not been tested for adequacy in mass

production. Thus, although the policy interpretation appeared

benevolent on its face, it was detrimental in practice because

the government repeatedly failed to give prompt clarification or

waivers for ambiguous or erroneous specifications.

25a

Appendix C

The new policy also applied to First Article approval

requirements. In a change from past practice, the government

decided to strictly evaluate all First Article submissions. In

particular, the Defense Logistics Agency made the following

interpretation:

The policy requires contracting officers to

use [the] specified accept/reject criteria as

the basis for first article approval decisions.

It also requires contracting officers to

disapprove first articles which are

manufactured with nonconforming parts and

materials. In addition . . . contracting officers

shall not grant conditional approval of first

articles without the specific approval of the

Center Command.

DX-2161. Those in charge of applying this interpretation in

evaluating the First Articles and mass production units seemed

to take the policy to an illogical extreme. As will be

demonstrated, in the Amertex contract, government personnel

applied the No Waiver interpretation as a “no tolerances” rule,

scrutinizing every sewing operation for deviations of as little as

1/32 of an inch, approximately the size of the period at the end

of this sentence. The policy interpretations for both the Amertex

First Articles and mass production units frequently resulted in

“overinspection” by government representatives.

Hence, the No Waiver Policy helped lay the foundation for

some of the intermittent delay and disruption that occurred on

this contract. The implementation of the new policy fostered an

inspection mindset that was often unreasonable. Government

inspectors seemed to ignore the fact that the chempro uniforms

26a

Appendix C

were not solicited as individually tailored dress uniforms but

were procured as an expedited mass production of millions of

battle garments requiring the coordination of different plants

employing hundreds of textile workers who were handling

numerous specifications, some of which had never been tested

or strictly enforced before. The numerous government

modifications to those specifications after contract award only

compounded the problems inherent in this situation.

D. Delay Analysis

Government actions thus sowed the seeds of delay and

disruption before plaintiff sewed a single stitch of this chempro

contract. At trial, however, the parties offered dramatically

conflicting evidence regarding fault for delay during the 1,411

days between contract award on February 25, 1985 and default

termination on January 6, 1989.° The contract set forth a schedule

requiring delivery of nearly a quarter of a million chempro suits

within eleven months, by January 31, 1986, and then monthly

deliveries of approximately 201,335 suits for a total of 2,415,885

by December 29, 1986. The parties agreed to a contract

performance period of 672 days. By the time of the default

termination, 1,411 days after award, however, Amertex had not

completed performance.

It is impossible to quantify with exactitude the amount of

and the responsibility for the delay and disruption in this case.

The contractor encountered a variety of problems of differing

magnitudes and durations. Perhaps in this type of case more

than others, determining delay involves particularly intuitive

assessments of the conflicting evidence. Nevertheless, we are

6. In counting days, the court, like the parties, does not count the

date of award, February 25, 1985, as a performance day.

27a

Appendix C

convinced that both parties share responsibility for the delay

and disruption that occurred. Moreover, we are confident that

the evidence adduced at trial provides a sufficient basis for

apportioning responsibility for the delay.

1. Evaluation of the Experts

The parties do not agree on the number of delay days, let

alone responsibility for that delay during the 1,411 days between

award and termination. Plaintiff, the party bearing the burden

of proof on the delay and disruption issue, contends that 984

delay days occurred and that the government caused 956 of them.

Defendant counters that there were more than 1,118 delay days,

only 94 of which were the sole responsibility of the government.

The delay experts of both parties had substantial and

comparable experience in schedule and delay analysis. The

experts differed sharply, however, in the thrust of their

methodology and the results of their analyses. For example,

plaintiff’s delay expert, Jayant Pandya, Project Director at Hill

International, Inc., calculated and attributed delay using an

analytical technique known as “critical path methodology”

(CPM). CPM is a method for determining which delays in a

multi-task project are critical, or controlling, in terms of actually

delaying completion. Defendant’s delay expert, Michael

D’Onofrio, a Professional Engineer at MDC Systems, offered

an alternative calculation and attribution of delay which

purportedly attached equal significance to every delaying

element in a manufacturing case like this. Moreover, D’Onofrio

criticized plaintiff’s use of CPM, contending that the

manufacturing context makes it impossible to isolate the specific

aspect of mass production that was “critical” or significant in

terms of delay.

28a

Appendix C

We credit the testimony of both delay experts but find the

testimony of neither to be persuasive in all areas. In our analysis,

we draw upon the opinions expressed by the experts of both

parties but rely extensively upon neither the methodology nor

determinations of any of them. Rather, as we explain, our

conclusions concerning quantification of delay and

responsibility for the delay are based upon our independent

assessment of the data amassed at trial.

a. Calculating Amount of Delay

In calculating delay, both parties’ experts analyzed the

amount of delay within specific time periods in diagrams called

“time impact analyses” (TIA’s). In particular, defendant’s expert

estimated the amount of delay that had occurred by certain dates,

one of which was June 30, 1988. By that time, plaintiff had

delivered more than a half-million chempro suits and had another

million suits in the production line. The contract originally

planned for a performance period of 672 days, with 340 days to

deliver 201,355 chempro suits and 332 additional days to deliver

the remaining 2.2 million suits.

D’Onofrio testified that 1,118 delay days occurred during

the 1,221-day period ending June 30, 1988.’ Thus, defendant

asserts that plaintiff made only 103 days of “progress” (1,221 —

1,118) despite the amount of production that had occurred by

that point. Defendant’s expert also maintained that additional

delays occurred between June 30, 1988 and termination on

January 6, 1989, but did not offer a delay figure for this period.

We believe that defendant’s calculation overstates the amount

of delay.

7. Defendant's expert stopped “counting” delay days for the last

six months of the contract, even though he acknowledged production

delays up to default termination.

29a

Appendix C

Plaintiff’s expert offered a more persuasive basis for

calculating the total amount of delay by analyzing the level of

production in each of twelve categories of chempro suit

operations.® Based on this analysis, Pandya opined that Amertex

experienced 984 delay days before default termination.

Our review of the production records and schedules on

which Pandya relied leads us to conclude that plaintiff’s estimate

was off by a slight margin. In addition to scrutinizing the

testimony and thousands of exhibits, we have tested the validity

of both parties’ delay arguments against Amertex’s actual

production levels. Upon analysis of the conflicting evidence,

we find that there were 952 delay days during the 1,411 calendar

days between contract award and termination.

b. Helpfulness of Critical Path Methodology

Defendant and its delay analyst maintained that CPM is

inappropriate in a manufacturing context due to the complexity

of mass production, and because such projects involve elements

which have unpredictable production times or durations, such

as the use of First Articles or a dependence on material suppliers.

It is true that the archetypical use of CPM is in the analysis of

construction projects. For instance, under CPM, a delay in

obtaining carpet would not actually delay the project if, at that

8. Amertex made a production plan with manufacturing goals and

tracked production levels in the following twelve categories: cut butyl,

cut coats (nyco), cut pants (nyco), cut lining, sew coats A (“A” indicates

outershell), sew pants A, sew lining, sew coats B (“B” indicates joining

lining with outershell), sew pants B, interim pack, final packing and

testing, and delivery. Of course, the actual production of the chempro

suits involved Amertex’s planning for and monitoring of production levels

on materials manufacturing, testing, and shipping, as well as the efficiency

of hundreds of sewing operations.

30a

Appendix C

time, the floor had not been completed (the “critical” task being

the completion of the floor). See, e.g. Haney v. United States,

230 Ct.Cl. 148, 676 F.2d 584, 595 (1982).

While CPM may be most useful in a simplified construction

context, we are unpersuaded that CPM is useless in the more

complex manufacturing context. (Defendant’s concerns about

the complexity and uncertainty in mass production are also

applicable to the use of CPM in construction cases, a use

defendant finds acceptable.) Furthermore, we do not agree that

the uncertainty of timing in manufacturing cases is a proper

ground for rejecting plaintiff’s CPM testimony. While the

manufacturing process necessarily involves estimations about

the durations of key events, Amertex’s master schedule, in

conjunction with the contractual delivery schedule, provides a

reasonable basis for comparing progress with production goals

for the purpose of analyzing delay. The parties have provided

the evidence necessary to adjust for any inadequacies in the “‘as-

planned” schedule.

However, we do not suggest that the use of CPM in a

manufacturing context is trouble free. The enormity and

complexity of the chempro suit contract does make it

exceptionally difficult to determine which item or items were

critical at different times during production. Moreover, the non-

linear, multi-tasking reality of mass production makes attributing

causation for delay especially laborious, even though the

chempro suit involved a linear sequence of operations with

specific estimates of duration. Despite these problems, CPM is

useful, but not conclusive, in analyzing the delay in this case.

c. Attributing Responsibility for Delay

Not surprisingly, Pandya attributed the vast majority of the

3la

Appendix C

delay to the government. D’Onofrio’s mirror testimony attributed

almost all of the delay to plaintiff. Out of 1,118 delay days,

D’Onofrio attributed 94 days solely to the government, 88 days

concurrently to both parties, and the remainder solely to

Amertex.

As the chronology of this contract unfolds, it will become

apparent that much of the delay is best categorized as

“concurrent.” We next set forth the factual findings relating to

responsibility for the 952 delay days that occurred during the

four years of the chempro contract.

E. Evaluating Delay Chronologically

1. Year One

After contract award on February 25, 1985, Amertex began

the process of making purchase orders for the chempro suits.

Almost immediately thereafter, however, preparations were

delayed when the contracting officer (CO) advised Amertex that

the government was planning to issue formal modifications of

the specifications. Tr. 135 (L. Jacobson). The parties discussed

the proposed changes at a meeting on April 9, 1985. PX-7; DX-

2162. The basic changes included the addition of a hydrostatic

test to verify the proper formulation of the chemicals phoschek

and polyox in the Type III charcoal laminate;° the change from

elastic sleeve closures to hook and pile (velcro) fasteners; the

replacement of the snaps on the coat with velcro fasteners; a

9. As mentioned earlier, the government sent the procurement into

solicitation without quality control provisions for the new charcoal slurry.

The addition of the hydrostatic test was intended to address this deficiency.

In another change from past practice, the government decided that it would

no longer accept contractor certification that the specification recipe for

the charcoal lining had been followed.

32a

Appendix C

change in the type of slide fasteners (zippers) from brass to

continuous element (plastic), and an increase in the length of

the garment. The specification was also to be changed from

specification D to specification E. DX-2162.

On May 24, 1985, three months after contract award,

Amertex received the official version of these changes in

unilateral modification PO00001, (P1). PX-12. Modification P1

provided that delays and costs would be finalized by the

administrative contracting officer.'® It would take the ACO three

months to make a contractual extension for P1 and three years

to finalize the increased costs related to this modification.

The parties had another post-award meeting on June 24-

25, 1985 to discuss additional specification issues. At these

meetings, the parties discussed problems with the state-of-the-

ert charcoal laminate passing the testing requirements and,

specifically, whether some of the tests had negative effects on

the others. Tr. 2821; 2880-81; 3433-34. These testing

requirements included the new hydrostatic resistance test, a

carbon tetrachloride test, weight test for the cloth, and a “ball-

burst,” or fabric strength, test. DX-2190; PX-13; PX-14; PX-

15; and PX-1007. The latter three standards were part of the

solicitation. The parties discussed other issues including the

“traceability” of treated materials for verification requirements

and the transportation of items between the prime contractor’s

facilities in Puerto Rico and subcontractor plants in Puerto Rico

and the continental United States.

10. In the Amertex contract, two different types of modifications

were issued: the “P” series, those modifications to the contract signed by

the procurement contracting officer (PCO), and the “A” series,

amendments to the contract signed by the administrative contracting

officer (ACO).

eer nats ee PEPER eR PRO Nya ME ee Te

7

33a

Appendix C

Three weeks later, on July 18, 1985, the parties executed a

bilateral agreement, P2, which made two additional changes to

the contract. This modification changed the specifications by

correcting the size of the velcro fasteners for the atropine pockets

and imposed a new component test requiring infrared reflection

limits for the nyco outer shell cloth. PX-16. This modification

also required Amertex to submit to the PCO within 30 days a

proposed delivery extension for the P2 changes. P2 also provided

that the ACO would finalize any price adjustment resulting from

the changes therein.

On July 31, 1985, the parties executed another bilateral

agreement, Al, allowing Amertex to apply for permission to

purchase “Long Lead Time Items and to commence Essential

Production work prior to First Article Approval.” DX-2002. This

amendment to the contract explicitly provided that the agreement

changed neither price nor delivery. DX-2002. Al allowed

Amertex to begin receiving progress payments to cover the costly

expense of obtaining large quantities of base materials necessary

for production build-up.'' According to the terms of the

amendment, however, any non-essential preparatory work was

still at the contractor’s risk.

a. The “90-Day” Delay

On August 19, 1985, the PCO determined that Amertex was

entitled to a schedule extension totalling 90 days as a result of

11. These materials included carbon, butyl, tricot, polyurethane

foam, and nyco. DX-2173. The estimated cost of the first batch of

materials was $6.9 million. Defendant authorized progress payments up

to $6,994,501, subject to a 95% reimbursement limitation under Defense

Acquisition Regulation 7-104.35. DX-2201. By the end of 1985, Amertex

would receive payments totalling $5,244,018, which covered less than

one-third of the incurred costs for materials only. DX-2273.

34a

Appendix C

modifications P1 and P2. PX-20. That 90-day period was

calculated by comparing the contract award date, February 25,

1985, with the date that Amertex received P1, which was May

26, 1985. PX-15. The government did not transmit to Amertex

the new patterns that corresponded with the formal changes in

Pi until June 19, 1985."* Defendant issued P2 a month after

that.

At trial, Amertex disputed the validity of the 90-day period

as an accurate and reasonable calculation of the amount of delay

caused by P1 and P2. For instance, Amertex contends that its

performance of the contract was delayed because crucial

preparations were slowed pending receipt of both the formal

modifications and patterns. Plaintiff also claims that the 90-day

figure was a premature calculation because it was not clear how

much additional time would be necessary to produce components

conforming to the two new testing requirements of P1 and P2.

Moreover, plaintiff contends that, at the time, it was not clear

what the net effect of the new fasteners would be in terms of

production time and cost.

The government proposed a bilateral modification, P-3,

incorporating the 90-day assessment for P] and P2 and a

provision waiving all delay claims for Pl and P2. Amertex

refused to waive its claim for delay damages as a result of P1

and P2 and, accordingly, did not sign the modification allowing

only a 90-day extension to the contract.

12. PX-20. Plaintiff also suggests government delay for the late

transmission of the patterns and refers to DPSC Form 4234, APR 87, at

21, which describes Defense Acquisition Regulation § 52.245-1008. PX-

221. However, as Amertex presented no evidence that the government's

failure to send the new patterns actually delayed plaintiff, we do not find

any delay specifically for the late transmission of the patterns.

35a

Appendix C

Unilateral modification P3 poses another complication,

however, which exemplifies the miscommunication and

uncertainty that permeated the contract performance. Both

parties refer to P3 as the “90-day extension.” However, P3

modified the First Article and mass production delivery schedule

from a schedule set forth in a modification that was never issued

by the government. P3 explicitly changed the First Article

submission deadline from August 24, 1985 to November 22,

1985, a period of 90 days. However, P3 actually extended the

date for the completion of the contract by only 89 days (from

December 29, 1986 to March 28, 1987). Nonetheless, D’Onofrio

opined that the government was solely responsible for

compensable, nonconcurrent delay for the “90 days” embodied

in P3. Therefore, we find the government solely responsible

for at least 90 days of delay for modifications P1 and P2. Whether

Amertex actually proved in excess of these 90 days of

compensable delay and disruption for P1 and P2 changes is

addressed hereafter.

b. The First Article Submissions

The next significant aspect of Year One in terms of delay

relates to the contract’s requirement that Amertex submit five

First Articles. The contract incorporated the solicitation’s First

Article provision. That clause stated, in part, that “[bJefore First

13. In defendant's 1989 decision on Amertex’s delay claim, the

contracting officer did not count the 90-day delay in P3 against the

government. DX-3252. Defendant suggested, instead, that Amertex

delayed the project by not having all of the slurry equipment until late

July. Amertex offered convincing evidence that this item was not critical

and that the slurry could be mixed by hand for the five sample units.

Defendant also noted that one of three nyco suppliers stopped production,

but Amertex established both that it had sufficient nyco on hand and that

this item was not on the critical path prior to First Article approval.

36a

Appendix C

Article approval, the acquisition of materials or components for,

or the commencement of production of, the balance of the

contract quantity are at the sole risk of the contractor.” DX-2001.

By reference to the solicitation, the contract set forth a

production scheme which allowed the contractor 180 days to

prepare the five-unit First Article, then thirty days for the

government to review those samples, followed by 130 days for

the contractor to build-up production rapidly in order to make

the first delivery of 201,335 suits. Accordingly, First Article

preparation was on the “critical” path of production during this

period of the contract; both parties acknowledged that First

Article preparation was a prerequisite to production. Thus, any

delay in First Article approval delayed the performance of the

contract as a whole.

The contract signed February 25, 1985 incorporated by

reference the First Article provisions in paragraph IIS of the

solicitation. In so doing, the contract created another ambiguity

that complicates the determination of delay during the first year

of the contract. The contract referred to the solicitation’s First

Article provisions which required the delivery of the five samples

within 180 days of the contract award. In direct contravention

of that provision, the contract also explicitly states that the First

Articles were due on June 4, 1985, or within 98 days. The record

is unclear about which due date was in effect and each of the

parties makes internally conflicting statements. At one point,

plaintiff had even developed a master schedule conforming to

this earlier date. However, in Post-Trial Briefs, defendant and

plaintiff both refer to the initial due date of the First Articles as

August 24 or August 25, 1985, respectively, which is

approximately 180 days from award. See I Def.’s Post-Trial Br.

1 (1993); Pl.’s Post-Trial Br. 16 (1993). We deem August 24,

37a

Appendix C

1985 to be the operative first deadline for First Article

submission.

As noted, modification P3 changed that deadline for First

Article presentation. On August 19, 1985, because of the changes

in modifications P! and P2, the government decided to extend

the First Article deadline by approximately 90 days, from August

24 until November 22, 1985. PX-20. Thus, prior to the August

24 deadline for the First Articles, the CO issued a determination

that Amertex was entitled to 90 days of “excusable” delay due

to “numerous specification and pattern changes.” PX-20. That

determination was approved by the government internally on

August 28. At about this time, a disagreement arose about the

waiver language in modification P3, which set forth the 90-day

extension. In response, the government unilaterally issued P3

which changed the First Article deadline to November 22.

Regardless of the parties’ other disagreements about the

modification spawned by the August 19 determination, P3 is a

binding modification of the contract’s delivery schedule. P3

explicitly imposed a new First Article delivery deadline of

November 22. Even though at trial the parties made contradictory

Statements about the new First Article deadline, we find that

both parties contemporaneously considered the new deadline to

be November 22, 1985. This has significant ramifications for

the calculation of delay based on what actually transpired during

the First Article submissions.

1) The First Set of Samples

Amertex submitted five First Articles on about September

10, 1985, two months ahead of the November 22 deadline set

by modification P3. DX-2216. Those First Articles were rejected

38a

Appendix C

by the government on September 18, 1985.'* Had the initial First

Articles been approved, Amertex would have been authorized

to proceed with production ahead of schedule. Nevertheless,

because September 10 was well in advance of the contractual

deadline, the rejection of those First Articles cannot be said to

have truly “delayed” or extended the project for purposes of

compensable delay. Therefore, any impropriety in that rejection

is immaterial to the determination of the extent to which the

contract was delayed beyond the 672-day performance period

originally agreed.

In response to the rejection of the September First Articles,

Amertex opted to submit new First Articles by the binding

deadline rather than to appeal the rejection of the first

submission. Tr. 163. While Amertex was preparing for the second

submission, the government unilaterally issued modification P4

which made several new changes.'° P4 changed the applicable

specification from “E” to “F (GL).” Additionally, P4 authorized

the limited use of brass zippers, altered new specifications that

had been inserted by modifications Pl and P2, and corrected

some “discrepancies found between the patterns and

14. The government attempts to defend its rejection of the

September First Articles, in part, by citing plaintiff's November 29, 1985

letter accompanying the second First Articles. DX-2254. In that letter,

Amertex stated: “We acknowledge the comments of your letter dated 7

October 1985 in which you pointed out the defects encountered in the

first five Chemical Protective Suits submitted for First Article evaluation.”

DX-2254.

15. P4 also stated that any price or delivery extension would be

finalized by the ACO. The changes in P4 were definitized almost a year

and a half later in a bilateral amendment to the contract, A3, dated March

9, 1987. DX-2002. A3 fixed the cost of the changes in P4 at $1,240 and

contained a release of liability for the P4 changes. DX-2002.

39a

Appendix C

specifications” relating to the atropine pocket construction and

to the trousers. DX-2002. Then, on November 4, 1985, the parties

agreed to modification P5, approving certain subcontractors and

designating locations for government inspection of chempro

components. Bilateral modification P5 provided that no delay

in deliveries would result from the changes therein. With the

modified contract specifications and patterns, Amertex continued

working toward the November deadline for the First Articles.

2) The Second Set of Samples

Amertex submitted the second set of First Articles on

November 29, 1986, seven days late. PX-26. Amertex avers that

it was tardy because it was awaiting clarification of the

specifications for the zippers on the legs of the trousers. DX-

2254. However, it appears that plaintiff received clarification

by telephone around November 12. Therefore, Amertex’s

evidence is insufficient to support its contention that the

government is responsible for Amertex’s submission of the

November First Articles seven days late. Furthermore, the

contract forbade Amertex to begin full-scale production until

the First Articles were approved; consequently, these seven days

delayed performance of the contract and are chargeable to

Amertex.

In the letter transmitting the November First Articles,

Amertex acknowledged the presence of some deviations in the

new set of samples. DX-2254. Amertex described these

deviations as minor and correctable in production and,

alternatively, as due to inconsistencies between the specifications

and the patterns. Jd.

On December 18, 1985, the government, through quality

40a

Appendix C

assurance specialist Hepner, indicated its concern about some

discrepancies between the specifications and the First Articles.

In response to these criticisms, Amertex reiterated, with greater

specificity, its position that the deviations were minor and

correctable in production. See, e.g., DX-2262. At the same time,

Amertex requested that the government not further delay

authorization to commence production. /d.

The government ignored this request and officially rejected

the second submission on December 30, 1985. DX-2268. This

was one day later than allowed by the solicitation, which

provided that the government had “30 days .. . [to] notify the

Contractor, in writing, of the conditional approval, approval, or

disapproval of the first article.” DX-2001. D’Onofrio

acknowledged defendant’s sole responsibility for this one day

of delay for tardy evaluation and we so find.

The key issue for attributing the remaining delay in Year

One is the propriety of the government’s rejection of the

November First Articles. The parties disagree about

responsibility for the delay associated with that rejection. In

the December 30 letter rejecting those samples, the government

identified 109 defects. (Some of the deviations were found on

every suit and thus were counted five times.) On a superficial

level, such a significant number of defects would suggest that

the government acted reasonably and should bear no

responsibility for the delay related to the rejection. On closer

examination, however, we find that the government improperly

rejected the November samples'® and thus delayed the

performance of the contract.

16. All of these samples were destroyed by the government during

First Article evaluation. DX-2268.

aoe Ci ac aes ae at ae ates anal

4la

Appendix C

a) Bases for Second Sample Rejection

The production of a single chempro suit in the Amertex

contract involved nearly 200 manufacturing operations. Some

of these operations were crucial to the effectiveness of the

uniforms in the event of chemical exposure. Other operations

were not so closely related to the efficacy of the suit, such as

the operation prescribing the stitch for finishing the raw edge

of material for a pocket. Indeed, the table of defects for

specification F classified over 200 potential deviations as

“minor,” “major,” or “critical.” PX-235. In its rejection of the

November First Articles, the government scored 109

imperfections, 103 of which were classified as minor deviations.

In the rejection of the November First Articles, the

government scored as defects numerous unreasonably picayune

items. These defects included 32 instances in which a stitch

margin, such as the placement of a belt loop on the trousers,

was purportedly out of alignment by as little as 1/32 of an inch.

Defendant also scored 13 defects for the presence of stubs, small

knots of thread on the face of fabric which are inherent to the

weaving process. Regarding the alleged stub deviations, plaintiff

presented persuasive evidence that the government’s

specifications were defective in that no slubs whatsoever were

tolerated in the end product but slubs were acceptable in the

component fabric.

As to the other minor deficiencies, plaintiff provided

compelling evidence that these deviations were most probably

the result of either incorrect interpretations by the examiners or

inconsistent specifications. Even government witnesses at trial

conceded that the minor defects were mentioned only for

advisory purposes. Tr. 4708 (Hepner) and Tr. 5875 (Marshall).

42a

Appendix C

Such minor imperfections should not have been allowed to keep

plaintiff's plants idle, delaying the start of mass production.

The remaining scored defects cast further doubt on the

propriety of the government’s rejection of the November First

Articles. Specifically, Hepner testified that she identified 5

“major” defects relating to some, but not all, of the “bartacks,”

a particular kind of stitching.’ Hepner claimed that after ripping

apart the bartacks, she counted only 14 stitches instead of the

28 required by the specifications.

Plaintiff offered strong evidence that the number of stitches

could not be counted accurately after a bartack is made because

the perforations are extremely close together.'* The evidence

also supported plaintiff’s contention that Amertex made all

bartacks using an unvarying setting of 28 stitches via cam

operated sewing machines. Tr. 2034-36 (Ludwig).

Defendant also contends that the rejection of the November

samples was justified because the First Articles contained one

instance in which a velcro sleeve tab was out of alignment by a

quarter of an inch. At the time, the defect table classified a

“sleeve tab set crookedly or poorly shaped” as minor, but a

“sleeve tab and pile tape out of alignment or not able to be

fastened properly” as critical. PX-235. Hepner scored one minor

17. Hepner similarly scored 20 “minor” defects for bartacks in

which she counted only 14 stitches.

18. Moreover, a person could mistakenly conciude that there were

half as many stitches as there really were; that is, those experienced in

textile manufacture count stitches by the number of perforations made

by a needle. A novice might conclude that a piece of thread between two

perforations was one stitch, whereas those in the industry would count

two stitches.

43a

Appendix C

and one critical defect for two deviations involving the sleeve

tabs: the former for a “crooked” sleeve tab and the latter for a

“1/4 inch” deviation.

The table of defects, however, neither specified the

distinction between “crooked” and “out of alignment,” nor

prescribed any measure for tolerances necessary for mass

production of the suits. There is also no evidence that the velcro

tab in the First Article did not fasten; instead, in the detailed

rejection letter, only a quarter inch variation in the tab was

identified. Moreover, the deficient ambiguity in the table of

defects was later corrected, clarifying that only if the tabs were

So misaligned that they could not be fastened could such

deviations be called “critical.”'® In sum, we find that had

defendant acted properly in its evaluation of the First Articles,

the quarter inch misalignment of the velcro tab would have been

considered both minor and easily correctable.

Finally, the evidence relating to the third First Article, which

was submitted on January 22, 1988, also bears on the

persuasiveness of the government's witnesses relating to the

November First Articles.” The government concluded that there

were zero defects in the third set of samples, that is, that they

were perfect. PX-43 (stating “[n]o departures were found:

production is authorized”). At trial, however, plaintiff used the

19. PX-127. Furthermore, the velcro sleeve specification, which had

been added by P1, had not been previously verified as accurate for mass

production. In fact, the velcro tab operation was corrected and adjusted

several times during the life of the contract.

20. It is also noteworthy that in a later chronology of the garment,

the government noted that it made specification changes on December

26, 1986 “resulting from Ist article to clarify Table of Defects such that

it coincides with Table of Operations requirements.” DX-59.

44a

Appendix C

one suit preserved from the January submission to illustrate the

disparities in the government’s position. The suit was shown to

have some obvious but easily correctable defects that would have

caused rejection had the inspectors applied the same “no

tolerances” approach as was used in the earlier submissions.

Moreover, the government’s position was weakened by

Hepner’s insistence that in January she ignored at least five

defects in the third First Article submission because Amertex’s

president promised that the operation would be performed

properly in production. Those deviations involved the placement

of a snap next to a seam in contravention of the specification’s

faulty requirement that the snap be placed through the seam.”!

Plaintiff’s president, Leo Jacobson, convincingly testified that

he never made such a statement because following the

specification to the letter would have destroyed the seam of the

trousers, critically damaging the functionality of the suit.”

Furthermore, even with the deviations in the third First Article,

defendant’s own expert testified that he would have “bought”

the samples. Tr. 5789 (Marshall). Hepner maintained that any

defect was cause for rejection, even though that was not the

normal practice. Tr. 4707-08 (Hepner).

All of these reasons convince us that the government acted

21. Bud Marshall, one of defendants sewing experts, agreed that

the operation could not be performed according to the specification

because doing so would damage the fastener “almost 100% of the time”

and also cut the stitches that hold the back seam of the pants together. Tr.

5947-48.

22. Even though this specification requirement was plainly

defective, it took the government nearly fifteen months to transmit to

Amertex formal permission to move the location of the snap. PX-118.

45a

Appendix C

improperly in its outright rejection of the November First

Articles. We are persuaded that defendant should be held

accountable for the delay damages resulting from its application

of a “no tolerances,” or perfection, standard during the November

First Article inspection.

b) Assigning Legal Responsibility for the

Second Rejection

Aside from disputing plaintiff’s factual evidence, defendant

attempts to justify the rejection of the November samples with

essentially two legal arguments. First, defendant contends that

it is not responsible for unreasonably delaying the project

because plaintiff has not established by “well-nigh irrefragable

proof” that the government acted in “bad faith.” Second,

defendant claims that it acted reasonably because it could reject

due to the presence of any defect. These contentions merit

additional discussion.

Defendant seems to suggest that, even if the government

acted unreasonably in rejecting the samples and delaying

production, in the absence of incontrovertible bad faith, plaintiff

cannot prevail on the First Article issue. Proof of bad faith,

however, let alone “well-nigh irrefragable proof” of malice, has

never been the touchstone for proving entitlement to an equitable

adjustment for damages caused by delay and disruption. Instead,

to recover for delay, plaintiff must prove that defendant

unreasonably delayed the completion of the contract, the

defendant proximately caused the delay, and that plaintiff’s costs

were increased as a result. See, e.g., Mega Constr. Co. v. United

States, 29 Fed.Cl. 396 (1993). Reasonableness, not bad faith, is

the essence of delay analysis. Cf. J.D. Hedin Constr. Co. v.

United States, 171 Ct.Cl. 70, 347 F.2d 235 (1965).

46a

Appendix C

Furthermore, the cases cited by defendant are not delay and

disruption cases, but are cases involving allegations of bad faith

termination. See, e.g., Sanders v. U.S. Postal Service, 801 F.2d

1328, 1331 (Fed.Cir. 1986) (citing Kalvar Corp., Inc. v. United

States, 211 Ct.Cl. 192, 543 F.2d 12980 (1976), cert. denied,

434 U.S. 830 (1977)). The strength of Kalvar’s “well-nigh

irrefragable proof” language appears to have been restrained

by the Court of Appeals for the Federal Circuit's subsequent

conclusion that a contracting officer’s decision to terminate a

contract for default may be set aside for reasons short of bad

faith. Darwin Constr. Co., Inc. v. United States, 811 F.2d 593

(Fed.Cir. 1987). Even in a termination claim, the circuit court

stated: “There is nothing in these decisions to support the

Government’s contention that the aggrieved contractor must add

another layer of proof by demonstrating that the decision was

also made in bad faith.” Jd. at 598. Similarly, there is no support

for extending the bad faith burden to the settled law relating to

proof of fault and injury in the delay claim regime.

As to defendant's second assertion, that the government is

entitled to reject outright the First Articles based on the presence

of a single deviation, we are similarly unpersuaded. The contract

itself is internally conflicting. For example, the specifications

contain a clause that states that the samples “shall be examined

for the defects specified in 4.4.3.1 and 4.4.3.2. The presence of

any defect shall be cause for rejection of the First Article.” PX-

235. Yet, the contract also states that there are three options for

First Article submissions: accept, conditionally accept, or reject.

DX-2001. The contract further indicates that unconditional or

conditional approval does not relieve the contractor of the

obligation to comply with the specifications during production.

DX-2002. If rejection were mandated by the presence of any

defect, then the availability of conditional approval would be

devoid of meaning. One contractual provision, like a statutory

47a

Appendix C

provision, should not be read in a way that renders accompanying

provisions superfluous. See, e.g., Northwest Marine Iron Works

v. United States, 203 Ct.Cl. 629, 639, 493 F.2d 652, 657 (1974).

Moreover, regardless of the superficial clarity of the “any

defect” language, the court is not bound to follow the literal

language when doing so would lead to absurd results. Jd. Cf.

United States v. Wilson, 503 U.S. 329, 334 ( 1992); United States

v. Providence Journal Co., 485 U.S. 693, 708, 710 ( 1988)

(Stevens, J., dissenting); Best Power Technology Sales Corp. v.

Austin, 984 F.2d 1172, 1175-76 (Fed.Cir. 1993). In the case at

bar, the production of a single chempro suit involved numerous

operations and hundreds of potential deviations that were graded

by their severity. Accordingly, it would be unreasonable, if not

absurd, to interpret the contract as giving defendant unlimited

power to deny acceptance, or conditional acceptance, based on

the presence of a single imperfection, no matter how slight.

The appropriateness of this construction of the contract is

buttressed by the contract’s Default Clause, which gives the

government the right to terminate the contract for default based

on the rejection of a First Article. DX-2002. Although defendant

did not default terminate the contract at this early juncture, the

severe implications of rejection warrant our approach to

reviewing First Article evaluations. In termination cases, the

ability to terminate for any deviation in the items delivered has

been modified by the “substantial compliance” rule. See, e.g.,

Radiation Technology, Inc. v. United States, 177 Ct.Cl. 227, 232,

366 F.2d 1003, 1005 (1966); see also Appeal of U.S. Optics

Corp., 75-2 BCA 11,603, ASBCA No. 18,972 (A.S.B.C.A., Nov.

25, 1975). In general, this rule modifies the doctrine of strict

conformity, which, when “coupled with a summary termination

power, would place in the hands of a contracting officer an

unfettered right to reject... .” Radiation Technology, 366 F.2d

48a

Appendix C

at 1005. The substantial compliance rule strikes a balance

between the competing rights of both parties.

The Armed Services Board of Contract Appeals has had

frequent opportunity to examine this rule in the special context

of First Article rejections. Over the past three decades, the Board

has addressed dozens of First Article rejection cases and has

refined the substantial compliance rule into the “correctable”

(also known as the “easily correctable”) standard. The Board

has consistently held that:

[T]he Government may not demand strict

compliance with the specifications [with

respect to First Articles] as with supplies

tendered for final delivery. The purpose of a

First Article is to discover defects. Therefore,

if defects are discovered and are easily

correctable in production the Government

may not reject the [samples].

Appeals of Defense Technology Corp., 91-3 BCA 24,189,

ASBCA No. 39,551, ASBCA No. 40,308 (A.S.B.C.A., July 17,

1991) (citation omitted). Accordingly, “[dJeficiencies in a first

article that are correctable in production are not a valid basis

for an outright disapproval . . . .” Appeal of Advanced Precision

Industries, Inc., 89-2 BCA 21,597, ASBCA No. 34,676

(A.S.B.C.A., Jan. 9, 1989); see International Tel. & Tel. Corp.,

ITT Defense Communication Division v. United States, 206

Ct.Cl. 37, 509 F.2d 541 (1975). Indeed, in a case strikingly

similar to plaintiff’s, the Board applied this standard in favor of

another chempro suit manufacturer whose second set of First

Articles had been rejected. Appeal of Winfield Mfg. Co., 88-1

BCA 20,353, ASBCA No. 34,901 (A.S.B.C.A., Nov. 19, 1987).

49a

Appendix C

The Board’s well-reasoned approach to reviewing decisions to

reject First Articles is equally applicable to the controversy at

bar.

Additionally, rejecting the samples was especially

inappropriate in light of the government’s election to use a five

unit, as opposed to an expanded, First Article. The government's

Chief of Technical and Quality Assurance Division, Director of

Clothing and Textiles had stated: “The ultimate purpose of the

first article is to demonstrate that the contractor possesses the

technical expertise necessary to produce the specification item

and to ensure a product with requisite quality.” PX-287. On

cross-examination, Hepner, the quality assurance representative

who made the decision to reject the November First Articles,

concurred that this was in fact the purpose of a small-sample

First Article. Tr. 4701. The government inspectors apparently

ignored both this purpose and the well-settled “easily

correctable” standard in withholding approval of the November

First Articles.

Although the evidence at trial was conflicting, we are

convinced that all of the defects identified were easily

correctable and not significant. Therefore, we find that the

government acted unreasonably and improperly in rejecting the

second First Article submission. The improper rejection resulted

in a 53 day delay in the authorization of production and this

entire amount is charged to the government.

c. Other Significant Events at the End of Year One

During the First Article process, the government informed

Amertex that several changes to the specifications were in

process, including a correction for performing the sleeve tab

50a

Appendix C

operation. PX-35. The changes were not issued before the end

of the first year of the contract and did not arrive until well after

mass production was authorized by the government.”

Additionally, Amertex informed the government that the

specifications did not provide an adequate method for spot or

stain removal. PX-28. Several spots had been scored on the

September First Article submission and, accordingly, the

contractor was concerned about meeting the specification

requirement for cleanliness. Also, during handling, the charcoal

lining had an inherent tendency to generate charcoal! dust that

smudged the outer shell. In January 1986, defendant provided a

soap and water method for removing stains, but noted that great

care had to be taken with the garments because any soap residue

would destroy the water resistant finish. PX-33. Ultimately, this

stain removal method would prove to be inadequate for many

of the marks inherent to the mass production of such a garment,

including some which were caused by an interaction between

the required quarpel coated thread and the specified fabric

components.

In addition to these issues, on January 17, 1986, defendant

modified the specifications to increase the allowable weight of

the charcoal lining.** This modification, P6, implicitly

recognized the unavoidable increase in weight caused by the

modified specification requirements. In fact, the letter

recommending the weight increase stated: “These changes

23. These modifications were formally incorporated in the contract

in June 1986 by modification P7. DX-2002.

24. The maximum allowable weight per square yard of the lining

cloth was increased from 9.5 ounces to 10 ounces. The modification also

corrected two other inconsistencies in which the specifications

contradicted the patterns or were otherwise inadequate. PX-40.

Ni ear” ya a errr ee re aay eae ei otc a occ

Sla

Appendix C

[were] required to eliminate the unnecessary restrictiveness of

the existing requirements.” PX-29. P6, a unilateral modification,

also included a clause providing that no increased costs or delays

would be allowed for this change. Plaintiff did not sign that

modification nor was plaintiff asked to do so.

Moreover, as noted above, defendant rejected Amertex’s

second First Article submission on December 30, 1985. PX-32.

Amertex received provisional approval of its third set of First

Articles on January 28, 1986, but did not receive authorization

to proceed until February 24, because the government needed

to complete additional testing of the samples. During this period,

Amertex notified the government that its preparatory work had

been delayed as a result of numerous government actions during

the first year. PX-37. On January 28, 1986, Amertex estimated

that its build-up schedule had been delayed by 105 days more

than the 90 days allowed by modification P3. Therefore, plaintiff

requested a delivery extension for this amount of time, with final

delivery to be made by July 13, 1987. PX-37. Defendant did not

issue an official delivery extension until nearly fifteen months

after this request.

Additionally, while awaiting First Article approval, Amertex

began small-scale production build-up at its own risk. By the

time that authorization for mass production was received on

February 24, 1986, Amertex had cut approximately 59,358 units

25. At that time, Amertex advised the government that it

“understood” the changes made through modification P7. At the same

time, Amertex also advised the government that the company was in the

process of quantifying the economic impact of changes and noted the

delay to preparatory work caused by the modifications. Additionally, as

Amertex later stated, once mass production began, the discrepancies and

impossibilities started impacting the company’s ability to meet the plan.

DX-3233 at 4; see infra.

52a

Appendix C

of butyl,”° 72,118 units of nyco for both coats and trousers, and

had sewn 14,670 nyco coat outer shells and 15,670 nyco trouser

outer shells. Because of the deficiencies in the lining

specifications, Amertex had only cut 50 units of lining prior to

First Article approval. However, because First Article approval

was on the critical path of production during this period, any

delay in lining production caused by defective specifications

did not yet manifest in delay to the project as a whole.

d. Distribution of Delay in Year One

There were 154 delay days during the 364 day period

encompassing the first year of the contract. D’Onofrio

acknowledged government responsibility for 90 days of delay

related to the first two modifications of contract and four delay

days due to tardy evaluations of the First Articles. Of the

remaining 60 days, the court finds that plaintiff is solely

responsible for seven delay days for late submission of the

November First Articles. We further find that the government is

solely responsible for 53 delay days resulting from the

unreasonable rejection of the November First Articles.

Accordingly, for the first year of production, the government

was solely responsible for 147 days of delay, and Amertex was

solely responsible for seven days.”’ This delay and disruption

26. Units are used rather than yards of material for the purpose of

tracking production of the garments. To say that 59,358 units of butyl

were cut, for instance, indicates that Amertex had cut sufficient butyl for

the production of 59,358 chempro suits.

27. From this point onward, we divide delay into two categories:

first, that caused solely by the government, and second, that caused either

solely by Amertex or concurrently by both parties. Only delay caused

solely by defendant is compensable; thus, it is unnecessary to differentiate

with respect to delay not solely attributable to defendant.

53a

Appendix C

meant that Amertex and its subcontractors had almost half a

year of “down-time” before receiving authorization to begin full-

scale production.

2. Year Two

Once Amertex received authorization to proceed in late

February 1986, the chempro suit production was fraught with

mistakes and disruptions caused by both parties. Overinspection

and inadequacies in the specifications, however, were not the

only causes of production difficulties. The government also

experienced substantial delays in approving butyl because of

complications at its testing site, Aberdeen Proving Grounds

(Aberdeen). Amertex, too, experienced problems in its cutting

operations that adversely affected its sewing production.

Furthermore, at the beginning of the second year of the

contract, some financial issues arose which implicate both the

delay and termination claims. Ultimately, Amertex’s cash-flow

Status provoked the break-down of the parties’ contractual

relationship. The contractor’s financial difficulties began to

crystallize near the start of the second year. At that time, two

financial issues were outstanding: compensation for long-lead

time items (LLTI) and also for P1 and P2 changes.

First, in terms of LLTI payments, the manufacture of

chempro suits involved the coordination of four functional

categories of production: materials supply, materials cutting,

sewing, and packing. Amertex had obtained approval in

amendment A] to begin essential pre-production work, such as

materials purchase, prior to First Article approval. The

government also authorized advance progress payments to cover

this work and it set-aside about $7 million to do so.

54a

Appendix C

The LLTI charges were subject to the same reimbursement

rate as ordinary progress payments which were available after

First Article acceptance. The contract provided that Amertex

was entitled to progress payments up to 95% of incurred costs

on the contract price of $96,345,493.80. In addition to Amertex’s

own equity, plaintiff arranged for a $5 million line of credit with

Banco Popular de Puerto Rico (Banco Popular) to cover the

remaining 5%.

By the time Year Two began and First Article approval was

obtained, Amertex had incurred more than $16 million in

expenses for materials alone. DX-2273. This amount was

exclusive of fixed and variable costs related to preparing

facilities for production, employing workers, making the First

Article samples, and performing research and development

related to complying with the P1 and P2 modifications, as well

as Amertex’s expenses for manufacturing in advance of

authorization to proceed. By the first week of January, Amertex

had received about $5 million toward expenses for LLTIs.

Another $1.5 million payment request was being processed but

had not yet been paid.

On January 10, 1986, Amertex requested (with itemized

documentation) an additional long-lead time progress payment

for the $9.7 million dollar gap between sunk material costs

($16,741,701) and the amount initially authorized for early

purchase of essential materials ($6,994,501). DX-2273. The

government disregarded this request, stating in internal

commentary that this large gap in funding for materials costs

“won’t make any difference once [First Article] approval comes

through.” Jd. As described earlier, the First Article sample was

not approved until February 24, 1986, the one-year anniversary

of the contract. Two more months would pass (until April 28,

1986) before Amertex received progress payments that covered

Ln nner nc cc ener eee ne ee ee ee eee eee a

55a

Appendix C

the amount of its January request. As noted, that $16 million

covered only material purchases; Amertex was financing the

remainder of its mounting expenses apparently without progress

payment reimbursement up to that point.

Second, it is noteworthy that at the outset of Year Two,

defendant had not finalized the price adjustment that Amertex

was due for the changes in P1 and P2. Perhaps the most

significant aspect of these changes related to the imposition of

the hydrostatic test to verify the formulation of state-of-the-art

slurry for the polyurethane foam. Defendant was aware, through

its frequent consultations, of the significant time and money

expended by Amertex’s subcontractors in their Struggle to

manufacture a cured polyurethane foam that conformed to the

requirements of that test, especially in conjunction with the other

lining specifications such as the weight requirement and the ball-

burst and the CCL, tests.”

28. The modified specifications for the state-of-the-art charcoal

lining also hampered Amertex’s ability to secure approved lining for

introduction into the production line. Shortly before production

authorization, the government eliminated the “unnecessar[ily]” restrictive

weight requirement for the lining material. PX-29. However, lining

produced according to the specifications continued to fail other testing

requirements. Tr. 2880-86 (Sallavanti).

To pass the new hydrostatic test requirement, the lining had to be

cured at high heat. Tr. 3432-34; Tr. 2878-81. The government’s expert on

the lining cloth acknowledged that the specifications relating to the burst

requirement were flawed. Tr. 4250-51 (McKinney); DX-2351. After

months of problems with the lining specifications, the government

changed the ball-burst test requirements in recognition of this problem.

DX-2002. Issued July 23, 1986, unilateral modification P12 noted that

any costs and delay would be finalized by the ACO. No adjustment specific

to P12 was ever issued.

56a

Appendix C

Even though P1 had been issued nine months before First

Article approval, Amertex had not received even a provisional

adjustment by the time Year Two began. Five months prior to

First Article approval, Amertex submitted a cost estimate of

$11,210,210 for Pl and P2 changes. This estimate included

disbursed costs, such as research and development for the lining,

and also prospective costs, such as materials and labor related

to the substitution of the velcro fasteners. That estimate did not

purport to cover any delay compensation relating to the issuance

of Pi and P2. The government had not finished its review of the

proposal and audits of the prime contractor and subcontractors

by the time of First Article approval.

Shortly after the start of Year Two, Amertex revised its

estimate of P! and P2 costs to $15,662,531. Amertex did not

receive a provisional adjustment for costs related to P] and P2

until nearly two years after production was authorized.

(Eventually, in January 1988, the government allowed a

provisional increase in the contract price for those first year

modifications in an amount over $8 million, which was finalized

in September 1988 at $12.9 million.) Thus, Amertex began Year

Two without an agreement on compensation for the changes

issued in Year One and the government would not finally

definitize those changes until just months before the default

termination, which was based in part on Amertex’s financial

condition.

Although these financial disagreements do not entitle

Amertex to delay compensation, they do shed light on the context

in which production build-up began. Due to the lack of prompt

compensation for these expenses combined with the 154 delay

days in Year One, Amertex and its subcontractors began Year

Two under financial strain. This financial stress grew worse as

those 154 delay days stretched into nearly three years worth of

57a

Appendix C

delay and disruption during the life of the chempro contract.

We next determine how many of the 952 delay days (between

award and termination) occurred during the year following First

Article approval.

a. Delay Days in Year Two

The second year of contract performance covers the period

from February 25, 1986 through February 28, 1987. During this

period, 369 days elapsed, but Amertex made very few days of

progress toward completion of the contract. Based on the expert

testimony concerning this issue as well as the production records,

we find that there were 304 delay days during Year Two. Thus,

Amertex took a year to manufacture the quantity of chempro

suits that it had originally planned to make during about two

months of production time.

The parties presented sharply conflicting theories regarding

responsibility for the delay. The evidence indicates that both

Amertex and the government contributed to the delay and

disruption during the second year of the contract. Nonetheless,

Amertex provided strong evidence of the government’s delay

separate and apart from its own (even though plaintiff’s experts

underestimated the amount of delay caused by company

mistakes). Plaintiff proved defendant’s sole responsibility for a

portion of the delay in Year Two. The causes of delay in this

period may best be understood by examining the production

circumstances in each of the two halves of the year. In the

following sections, we describe the factual predicates to our

apportionment of the 304 delay days.

1) The First Six Months of Authorized Production

From February 25, 1986 through August 31, 1986, 188 days

58a

Appendix C

elapsed. During these six months, Amertex’s manufacturing

processes moved forward at a very slow pace. According to the

solicitation and contract plan, Amertex was to deliver 201,335

Suits to the government within about six months of First Article

approval. Amertex’s actual production levels during this six

month period fell far short of those expectations.

Indeed, according to the contract schedule unilaterally

imposed by modification P3, Amertex was required to deliver

more than one million suits by the end of August. P3, the 90-

day extension, did not include all of the excusable delay in Year

One nor, obviously, did it contemplate any schedule adjustment

for excusable delays encountered in the first half of Year Two.

The rapid delivery schedule imposed by modification P3 was

consistent, however, with the parties’ expectations that the

contract involved an expedited production of chempro suits. To

say the least, Amertex’s progress in Year Two was anything but

expedited.

We find that plaintiff experienced 155 delay days in the

first half of Year Two. That is, Amertex made only about 33

days worth of progress toward its production goals during

roughly half a year’s time.”

Attributing responsibility for delay in a case such as this is

not susceptible to surgical precision. Instead, assigning fault

for the delay causation here involves a subjective but reasoned

assessment of the totality of the evidence introduced at trial.

a) Actual Production Levels

Amertex’s production strategy planned for staggered

29. Specifically, we make the following delay day/progress day

findings: February 25 to March 31, 30 delay days/5S days of progress;

April, 28/2; May, 26/5; June, 25/5; July, 22/9; August 24/7.

59a

Appendix C

production such that a sufficient quantity of materials would be

cut in order to support the sewing production lines and likewise

a sufficient quantity of sewn material would be “built-up” to

Support the packing operations. In addition to securing an

adequate supply of materials, the strategy to produce 2.4 million

chempro suits involved the coordination of materials cutting,

sewing, and packing. Cutting encompassed four main Categories:

butyl cutting, nyco cutting (coats), nyco cutting (trousers), and

charcoal lining cutting. Sewing included five main categories:

sewing “part-A” (outer shell) coats, sewing part-A trousers,

sewing linings, sewing “part-B” (joining linings and outer shells)

coats, and sewing part-B trousers. Packing involved three

primary categories: interim packing of finished units in Puerto

Rico, final packing and testing in the continental United States,

and delivering the suits to the government.

In this way, the Amertex plan called for a build-up of about

three months in materials cutting before the target output of

200,000 cut parts per month in each of the four cutting categories

would be reached. Similarly, Amertex planned to build-up

sewing production to about 200,000 sewn parts per month in

each of the five sewing categories before the target output of

200,000 in each grouping per month would be reached.

Specifically, Amertex made a reasonable plan that would

have fulfilled the contractual schedule and consisted in essence

of the following synchronized schedule: First, for butyl and nyco

cutting to proceed at the same rate; then, once about 100,000

“kits” of butyl and nyco were prepared, for the use of such kits

in the outer shell sewing; at that same time, for lining cutting to

begin; then, once about 150,000 units of lining were cut, for

lining sewing to begin; then, once about 100,000 outer shells

were accumulated, for the joining of sewn linings and outer

60a

Appendix C

shells to begin; finally, for packing operations to begin once

about 100,000 suits were completed.

During the first half of Year Two, Amertex was not able to

fulfill this scheduling plan. Amertex did, however, try to alleviate

the effect of the problems in Year Two by commencing its sewing

operations in advance of the plan’s build-up schedule.

To illustrate our discussion of the causes of slow production

during this six month period, we recap the production outputs

at the start of Year Two. Amertex tracked and coordinated the

productive output and also recorded cumulative production levels

by month.” The following table shows the cumulative production

in units at the end of the months that demarcate the parameters

of this part of Year Two, February and August 1986:

Table 1: Cumulative Levels of Production

First Half of Year Two

Category 2/28/86 8/31/86

Cut Buty! (Sets) 59,358 265,602

Cut Nyco (Coats) 72,118 327,378

Cut Nyco (Pants) 72,118 327,378

Cut Lining (Sets) 50 328,562

| Sew Outer shells A (Coats) 14,670 121,863

Sew Outer shells A (ants) 15,670 —*115,328

| Sew Linings (Sets) 0 48,144

Sew Linings & Shells B (Coats) 0 408

Sew Linings & Shells B (Pants) 6 18,744

Interim Packing 0 0

Final Packing & Testing 0 0

Delivery 0 0

30. For consistency, cumulative production at the ends of months

is compared, even though Year Two began on February 25, 1986.

eee ee : OOO ee. eee

6la

Appendix C

As the table shows, butyl cutting lagged behind nyco cutting

for coats and trousers at the start of Year Two. By March,

Amertex cut 59,358 units of butyl, which was all but 4800 units

of the butyl that had been approved by the end of February

(64,158 units). PX-297. Also, due to problems with the lining

specifications, almost no lining material was available for cutting

or sewing prior to authorization to proceed. Amertex’s

subcontractors were able, however, to perform some part-A

work, that is, to sew the nyco and butyl cut parts into outer shells.

The lack of lining precluded any part-B work, which involved

the attachment of sewn linings to sewn outer shells.

From February through August, Amertex cut about 200,000

units of butyl. Due to delays in butyl testing at Aberdeen,

Amertex had almost no butyl available for cutting in April, none

in May, June, and most of July. Amertex did cut about 150,000

units in March and about another 50,000 in July. We examine

the butyl-caused delays in greater detail in the next section.

Because of the government’s delay in buty] approval,

Amertex’s monthly nyco cutting levels surpassed buty] cutting

in every month but March. This situation disrupted plaintiff's

production schedule, which planned for butyl and nyco cutting

to proceed at the same pace. Synchronicity in these items was

necessitated by the specification’s requirement that the outer

shell be constructed of nyco reinforced with butyl. During the

first half of Year Two, the rate of nyco cutting grew for about

taree months, slowed in June, progressed in July, and then slowed

again in August. Nonetheless, by August 31, 1986, Amertex had

made a cumulative cut of 327,378 units of nyco for coats and

the same quantity for trousers.

According to the plan, butyl and nyco were to produced in

parity in terms of units. (Each suit required about three yards of

62a

Appendix C

nyco for each half yard of butyl.) Moreover, regardless of the

contractor’s plan, the specifications required that the outer shell

consist of nyco with butyl reinforcements in several locations.

Similarly, due to the limited shelf life of the charcoal lining

material, it was not practical to expedite the linings for

integration into the chempro suits without an assured availability

of butyl. Lining manufacture and cutting had to be closely

monitored to calibrate lining sewing with part-A outer shell

sewing so that these operations would dovetail into part-B

procedures that joined the lining with the outer shell. Because

of the drought in butyl supply, lining cutting inevitably eclipsed

butyl cutting. Lining cutting grew steadily during the first six

months of production, with a slight drop in July. By the end of

August 1986, Amertex had 328,562 units of lining, a negligibly

greater quantity than cut outer shell units and more units than

cut butyl.

The sewing of the outer shell coats and pants by Amertex’s

subcontractors, Lajas and Apparel Art, proceeded at a very slow

pace during the first three months of Year Two, increased

somewhat during June and July, and dropped slightly during

August.*' Sewing part-A required parity in available nyco and

butyl cut parts. Additionally, the level of sewing operations

31. After the nearly half-year of government caused delay in Year

One, Amertex’s relations with its subcontractors were strained at the outset

of authorized production. Frustrated with the amount of delay and

disruption experienced on the contract, Lajas laid off workers in May.

Because Lajas was responsible for the part-A sewing of trousers, this

layoff caused a disparity between the level of part-A production of coats

versus pants.

32. PX-240. Butyl was required for six of the 15 primary part-A

categories of coat operations and for three of the 13 primary part-A

(Cont'd)

63a

Appendix C

had to be monitored in order to maintain a sufficient backlog of

materials so that the assembly line would not run out of supplies.

During times of material shortage, Amertex explained that the

sewing subcontractors had a rational preference to keep

production lines flowing at 2 slow pace rather than to speed

through all available cut work and be required to cease

production, losing specially trained workers to other apparel

companies.

By the end of August 1986 (i.e., during the first six months

of authorized production), Amertex had completed the sewing

of 121,863 part-A coat outer shells and 1 15,863 part-A trouser

outer shells. This cumulative quantity is approximately the

amount that the contractor originally planned to build-up during

the first five and a half weeks of production.

Amertex did not begin to sew linings until April 1986. For the

remaining months in the first half of Year Two, Amertex sewed on

average 11,500 lining sets per month. This lining sewing was ahead

of schedule in that originally the company had scheduled lining

sewing to begin once there was a backlog of about 150,000 lining

Cut pieces to support the assembly line. Despite this “early” start,

by the end of August 1986, Amertex had completed only slightly

more sewn lining sets than it had planned to produce in the first

two weeks of build-up of this item.

During the first half of Year Two, Amertex also began its

part-B sewing, attaching sewn linings to sewn outer shells, ahead

(Cont'd)

Categories of trouser operations. /d. Amertex's witnesses established that

part-A work could not proceed without sufficient quantities of butyl in

the sewing assembly line. In each coat, for example, butyl was needed

for the atropine pocket protective piece, the under sleeve elbow patch,

the sleeve pocket protective piece, the top sleeve elbow patch, and the

chest pocket protective pieces. Id .

EE

64a

Appendix C

of its production plan in terms of backlog of material to support

the assembly line. Yet, due to the reduced levels of production

in the other categories, Amertex did not start part-B work until

July, four months after authorization to proceed. Even then, the

specification deficiencies on the coat stalled part-B coat

production work to such an extent that only 408 coats had been

sewn by the end of August. In contrast, although also proceeding

at a sluggish pace, 18,744 part-B trousers were completed by

August 31, 1986. For both part-B garments, there was an

insufficient amount of part-A and lining sewn work to feed full-

blown production build-up.

Furthermore, because few sets of coats and pants were

completely sewn by the end of August, plaintiff did not proceed

to pack, present for final testing, or deliver any garments during

the first half of Year Two. In these ways, Amertex’s production

output fell far short of its own plan and the contractual delivery

schedule. During this period, however, the government issued

no “show cause” letters based on the contractor’s slow

production or failure to fulfill the delivery schedule in

modification P3.

b) Assessing Responsibility for Delay

Each party contends that the other was the primary cause

of delay between February 25, 1986 and August 31, 1986.

Plaintiff’s witnesses placed great emphasis on the effect of the

lack of government approved butyl] on the production processes,

asserting that butyl availability was controlling. In contrast,

defendant’s scheduling and production experts theorized that

almost all of the delay was due to defective cutting slowing the

sewing production and that none of this delay was attributable

solely to the government.

We next examine the merits of the parties’ contentions about

65a

Appendix C

responsibility for delay by focusing on the three key issues of

this period: the effect of tardy butyl testing, the effect of bad

cutting on sewing operations, and the effect of changes and

inadequacies in the specifications on production in general.

(1) Butyl Issues

The specifications referred to in the contract provided that

Amertex was required to submit samples of butyl for

toxicological testing at Aberdeen before the material could be

used in the production of the chempro suits. DX-2003. The

contract also mandated that defendant take no more than 30

working days to test and approve butyl. DX-2002; DX-2003.

Butyl was a key component in the initial operations for the

chempro outer shell. Each outer shell kit required sufficient nyco

and butyl cut pieces for one chempro suit. Tr. 472-73 (L.

Jacobson). Butyl was required for six of the 15 primary part-A

divisions of coat operations and for three of the 13 primary part-

A divisions of trouser operations.” In this way, the availability

of butyl for cutting could pace the cutting of nyco, as well as

the sewing operations.

Since before First Article approval, Aberdeen had regularly

failed to approve butyl within the contractual time limit and

had approved butyl at an unpredictable rate for purposes of

planning for butyl availability. This sporadic “pattern”

33. PX-240. Amertex’s witnesses established that part-A work could

not proceed without sufficient quantities of butyl in the sewing assembly

line. In each coat, for example, butyl was needed for the atropine pocket

protective piece, the under sleeve elbow patch, the sleeve pocket protective

piece, the top sleeve elbow patch, and the chest pocket protective pieces.

PX-240.

34. The term “to approve” is used to mean both “to test” and “to

(Cont'd)

66a

Appendix C

continued during the first six months of Year Two. Following

authorization to proceed with production, the government made

a surge in butyl approval. Amertex, through its subcontractor

Gentex, cut 151,680 units by the end of March 1986. PX-297 at

12. Gentex was able to rapidly integrate this large quantity of

butyl into its cutting assembly lines even though Amertex’s

production plan did not contemplate cutting that much buty! in

a thirty day period until about the third month of production

build-up.

Gentex cut the remaining approved buty! (1,920 units worth)

during the first week of April. PX-297 at 12. The government

failed to approve any more buty! in April. Gentex kept Amertex

and the government informed that the delays in butyl testing

would restrict the subcontractor’s cutting output and,

consequently, the overall delivery schedule. See, e.g., DX-2377.

Gentex repeatedly asked Aberdeen to “expedite” the testing of

butyl. As of April 29, 1986, Amertex was awaiting approval of a

quantity of butyl sufficient to incorporate into more than 200,000

outer shells.*°

In May, no butyl was approved. Gentex wrote Amertex

advising that “the current status of testing at Aberdeen will result

in further serious delays in receiving approved material at Gentex

for production, and that unless corrected, will put the entire

production system at risk .. . .” PX-53. Amertex then contacted

DPSC, requesting assistance in expediting the testing. DPSC

(Cont'd)

accept.” The government's tardiness in approving butyl was not due to

inadequacies or deviations in the materials tested. Only one lot of butyl

experienced some testing failure during this period.

35. Each suit required about a half-yard of butyl to be stitched into

key areas. Tr. 474.

67a

Appendix C

then contacted Aberdeen about the “inordinate delays” and

advised that the delays could “result in breach of contract.”

Despite these efforts, no butyl was approved in June. By

that time, Amertex elected to allow the cumulative cutting of

nyco to exceed the cumulative cut of butyl in order to put some

additional material into the sewing production lines. To the extent

that Amertex tried to mitigate the lack of butyl through preparing

kits without a key component, plaintiff’s assembly lines could

make only limited progress in sewing. Butyl was, indisputably,

an integral part of the manufacturing of the chempro suits at the

outer shell stage; no matter how much nyco could be cut and

shipped in advance of the butyl, the design of the chempro outer

shells meant that Amertex’s subcontractors could not complete

more outer shell units than butyl units were available.

At the beginning of July, Gentex reiterated the production

delay impact of having no butyl available. The subcontractors

had also been complaining about the lack of sufficient quantities

of butyl for sewing in the preceding three months. In late July,

defendant released 67,044 units of butyl. PX-65 (noting that

the buty! situation had restricted output severely); PX-297. When

butyl finally became available in July, Amertex shipped butyl

cut pieces to its assembly lines by air-freight. PX-68. Even

though 280,002 units of butyl had been approved for cutting

and Gentex had cut 265,602 units by the end of July, nyco cutting

remained ahead of butyl cutting, with 291,858 units in the

former. By the end of the first haif of Year Two, butyl cutting

was behind nyco cutting by about 60,000 units.

By the end of August 1986, butyl had only been approved

in two out of six months. Butyl testing had been delayed to such

an extent that shortly after the end of this period (in September

68a

Appendix C

1986), the government created a surge in butyl approval in the

amount of more than a half-million units.

The extensive butyl delays in this period adversely affected

the unofficial delivery schedule the parties had been following

in lieu of the P3 schedule. Amertex had kept the government

apprised of the way in which butyl was slowing delivery, as

reported in a government memorandum:

Initial delivery due 1/86. Contractor claimed

excusable delay, agreed to revised schedule

commencing 8/86 .... Tox[icological]

testing of butyl coated nylon was delayed

(spring ‘86) when [the Environmental

Protection Agency] shut down test lab at

Aberdeen ... for about two months ....

Amertex claimed additional excusable delay

as a result [with delivery commencing]

11/86.

PX-71 (noting also that there was a “large number of

spec[ification] changes issued”).

In sum, during the first six months after First Article

approval, the butyl approval problem stunted plaintiff’s ability

to build-up its production levels to the point needed to expedite

the production of the garments. This situation not only delayed

performance of the contract but was a violation of the explicit

provisions of the contract itself. Yet, throughout the life of the

contract, defendant continually exceeded this contractual time

limit.*°

36. For 22 of 44 months, no buty! was approved. PX-297. (Amertex’s

first submission of butyl for testing occurred in late July 1985, almost

(Cont'd)

ee ee ee ee

69a

Appendix C

This pattern of sporadic approval of butyl followed by

months with no approved butyl wreaked havoc on Amertex’s

ability to plan production, maintain its cutting operations, retain

employees, and achieve production efficiencies. Tr. 786-87 and

474-77 (L. Jacobson); Tr. 7673-76 (Pullo); Tr. 2505-06; PX-

291. During the first half of Year Two, Amertex immediately

cut most butyl! that was approved yet spent nearly three months

with no butyl to put into the production line.

A year and a half after the worst of the butyl testing delays,

the government wrote in a contract newsletter:

{C]ontinued Government delays in testing of

Butyl Fabric at Aberdeen . . . had caused this

material to become the pacing item for

contract performance. As long as this

condition persists the Government is

exposed, not only to excusable delays in

product delivery, but also to claims for delay

costs already estimated by the contractor to

exceed $7 million.

PX-284.

During the first half of Year Two, buty! testing delays

prolonged the performance period of the contract; such delays

to the program caused by slow buty] approval were not subsumed

by or entirely concurrent with other problems on the contract.

(Cont'd)

contemporaneously with contract amendment Al which authorized

essential pre-production work in advance of First Article approval.)

Testing times ranged from a low of five days to a high of 270 days with

a mean testing time of about two months. DX-3337 at 256-57. Only 12

of the 74 lots submitted were tested within 30 days. /d.

70a

Appendix C

The lack of butyl for cutting had a delaying impact that

was Of a different duration and magnitude than the other

obstacles encountered by plaintiff. Indeed, had Amertex been

efficient in all other operations, contract performance still would

have been substantially delayed and the government’s tardy buty]

approval would have been responsible for almost all of that delay.

However, as the following discussion reveals, Amertex did not

achieve close to optimal production, and therefore the amount

of delay for which the government is solely responsible is

diminished significantly. We find the government solely

responsible for 70 delay days, less than half of the delay in this

period.

(2) Poor Cutting and Its Effect of Sewing Levels

The government presented strong evidence, consisting in

part of contemporaneous correspondence, that Amertex’s

production was delayed due to poor cutting. The evidence shows

that a small, but nevertheless deleterious, percentage of the fabric

was Cut improperly. Additionally, some of the cut parts had

inadequate surveillance marking. These cutting problems slowed

plaintiff’s sewing operations and aggravated the already strained

environment in which Year Two began. Some margin of error is,

of course, inherent in the mass production process, especially

at the beginning of a manufacturing operation. Yet, both the

degree and persistence of the cutting problems on the chempro

contract exceeded the expectations of all participants. These

cutting problems were a substantial cause of delay in this period

in that they controlled the rate at which the already low supply

of cut parts could be utilized for the production of sewn units.

The cutting problems were present before the outset of Year

Two. See, e.g., DX-2281 (describing problems including

imprecise cutting of small parts like pockets and flaps). Amertex

Tla

Appendix C

had even received a “quality deficiency record” (QDR) for the

presence of some defective parts cut smaller than pattern, chest

pockets in particular. DX-2301. As stated earlier, however, these

problems were not “critical” in terms of delay prior to

authorization to proceed.

Two days after First Article approval, Amertex wrote to its

cutting subcontractor, Gentex, describing some of the problems

and “strongly suggest[ing] that. . . a Gentex representative come

to Puerto Rico as soon as possible... . If they are not corrected

soon, these problems will only get bigger and costly.” DX-2312.

Those cutting problems included misplaced drill holes and

poorly cut small parts such as pockets and flaps, including parts

that had excess selvage.”’ There were also problems with notches

being omitted or cut poorly. DX-2314. Unfortunately for all

concerned, those cutting problems were not corrected promptly.

In our evaluation of delay, we find highly significant a

memorandum by one of the Gentex representatives who went

to Puerto Rico in response to Amertex’s request. DX-2327. In

that March 14, 1986 memo, the representative noted that “60%

of the problems were actual cutting problems and 40% were

material defect problems.” Plainly, the contractor was

experiencing a higher rate of defects than it considered to be

acceptable at the time and this slowed progress.

Another observation in the Gentex memo indicated that the

pace in the factory was “very low” and that it seemed as if the

plants had only recently started operations. However, the

representative’s visit occurred only about two and a half weeks

after production was authorized. Had Amertex not started some

advance production at its own risk, the company would not even

37. Selvage is unusable material at the edge of a roll of fabric.

72a

Appendix C

have had sewing operations on-line by that time. Because some

quantity of poor cut parts was being shipped and slowing build-

up, we find plaintiff responsible for some delay.

In April, the cutting problems continued. The government

issued a QDR citing discrepancies relating to “inadequate

incoming inspection system to detect deficiencies.” After

plaintiff reconfigured its 100% inspection policy for cutwork,

Amertex returned two cut lots to Gentex because of continued

problems relating to drill holes, notches, selvage, and the

precision of cuts for small parts like collars. DX-2358; DX-

2362.

These problems continued to occur in May, along with some

surveillance marking and pinhole problems in the linings coming

from Gentex. The sewing subcontractors were distressed over

the continued degree of poor cutting. For example, in late May,

Amertex’s subcontractor, Lajas, noted that it had suffered “a

great amount of losses because of bad quality in the cut work

and shading problems in the fabric.” DX-2402. However, that

same letter noted the adverse effect of the slow cutting rate that

resulted from lack of butyl, stating “we stopped operations three

times because of lack of work.” /d.

In June and July, the problems with cut parts coming from

Gentex continued. At the end of the month, Amertex complained

yet again to Gentex about the “lack of acceptable quality cut

parts ....” DX-2458. Leo Jacobson, Amertex’s president,

emphasized, “It is impossible to build up efficiency in this

38. DX-2352. That QDR also noted problems such as a surveillance

control number missing from “one cut part” of charcoal lining, in addition

to a few other traceability issues.

73a

Appendix C

manner.” DX-2458. Amertex also found a sudden increase in

the quantity of the lining materials being cut too small for the

patterns. DX-2496. The problems with the notches and drill holes

in the nyco persisted.

By August, plaintiff decided to transfer the cutting

operations from Gentex to one of its own plants in Puerto Rico.

DX-2528. At trial, Amertex tried to minimize the relevance of

the cutting problems that culminated in its decision to terminate

the cutting part of its agreement with Gentex.”* It is possible

that Amertex decided to take-over cutting operations for some

combination of reasons, but we find that the evidence of cutting

problems leading up to the transfer speaks for itself, The

termination, or phase-out, of the cutting operations at Gentex

resulted in a drop in nyco cutting, even though lining cutting

experienced a 67% increase during August. Additionally, none

of the 14,400 units of butyl] that had not been cut in July was cut

in August.

By the end of the first half of Year Two, Amertex had sewn

about one-half of the butyl and one-third of the nyco into outer

shells. This production output was roughly consistent with the

production plan which contemplated the completion of 107,500

each of coat and pant outer shells by the time that 250,000 butyl

units were cut. However, it is undeniable that part-A production

was disrupted by problems in the cutting.

As noted, Amertex’s production levels were so far off the

contractual plan that 155 delay days occurred in this six-month

period. Even if the defect rate for nyco was only about the 4%

39. Gentex remained responsible for obtaining materials for

Amertex's cutting operations and for packing the chempro suits for final

shipment to the government.

el

74a

Appendix C

figure credibly determined by plaintiff’s production expert, that

rate undoubtedly had an adverse impact on output.“ This is so

especially because the contract required that all fabric parts in a

chempro suit be matched for shade and be traceable to the same

production lots. Therefore, any poor cutting beyond the amount

inherent to an efficient mass production operation impeded the

sewing process. The sewing process was already slowed due to

there being fewer cut parts than planned as a result of the butyl

delays discussed earlier.

Perhaps more significant was the effect of problems with

the lining cuts and surveillance numbers. This problem in the

supply of lining cut parts resulted in a 280,000 unit gap between

cut linings and sewn linings, which was about 100,000 units

more than planned. The low quantity of linings then delayed

the start of part-B sewing. Amertex’s own documents note that

“70% of [lining] work being processed was not acceptable” in

late July. DX-2458; DX-2496.

Ultimately, Amertex billed Gentex $75,991.88 for direct and

indirect costs associated with butyl cutting. DX-3346. Amertex

excluded about $3 million worth of costs from its delay and

disruption claim for delays caused by problems in the materials

during the life of the contract. Tr. 8175 (Madera).

Without engaging in insoluble hypotheticals, we note that

had there been no buty/ testing delays slowing the cutting of all

materials, the unacceptably high percentage of cut part

40. We assume, without deciding, that the error rate for nyco was

at least 4% and exceeded the amount contemplated by the parties to the

contract as inherent to mass production. The specific defect rate is not

relevant since the inadequacies in the cut parts delayed performance

regardless of the percentage of the problem.

75a

Appendix C

inadequacies would have affected any increased level of cutting

that would have been possible. Indeed, due to the problems with

cut parts, we are persuaded that more than half of the delay to

the completion of the contract occurring during this period

cannot be attributed to the sole responsibility of the government.

However, we are not convinced that the problems with the cut

parts would account for all of the delay in this period especially

in light of the butyl situation discussed earlier and the

specification problems we turn to next.

(3) Specifications and Enforcement

The butyl and cutting problems do not reveal the whole story

of the six months following the government's authorization of

production. The specifications continued to evolve and

government inspection policies combined with lengthy delays

in correcting or waiving specification problems continued to

hamper production. Numerous Specification and pattern

problems remained unrésolved including a lack of tolerances,

seam location inadequacies, and conflicts within the

specifications. |

About one month into authorized production, the

government conducted a thorough plant visit to review the

“quality assurance status” of the chempro suit manufacturing

process. PX-47. The trip report, written by Bruce Dansby, a

quality assurance supervisor, indicated that problems with

inadequacies in the specifications were hampering production.

The specification problems identified included the following:

the fact that the specifications were ambiguous in indicating

when the butyl was to be sewn heavy-side or “face up,” and the

difficulty in determining after cutting a roll of butyl which side

was the heavy side on each of the parts; two concerns relating

to the clarity of the specifications for the pocket flaps; and at

76a

Appendix C

least seven other specification inadequacies. PX-47. In

particular, the government noted that it needed to “add

tolerances,” “clarify” the pocket stitching, “correct” the order

of construction of the new velcro sleeve tabs, and “add” new

defects to the table of defects. PX-59.

The pocket flap problem was not resolved until early 1988.

The specification stated vaguely: “sew around the flap.” Amertex

reasonably interpreted this to mean sewing three sides while

stitching the fourth side in the seam attaching the flap. The

government issued a QDR in April for failing to sew the flap on

all four sides. Subsequent problems relating to the flap included

seam margin tolerances and whether the bartack had to be sewn

all the way through to the trousers. There is no reasonable

explanation for the years it took for the government to resolve

these and other issues.

The trip report is significant for two other reasons. First,

Dansby reported that he asked Hepner, the DPSC technical

representative, about “ ‘Lessons Learned’ from previous

contracts [and] [s]he said that this was a newly revised

specification [therefore] not too much from the past would

“pertain to this new procurement.” PX-47 at 5. This position

stands in sharp contrast to the government’s litigating position

that the revisions to the old specification were minor and no

expanded First Article was necessary to test the adequacy of the

specifications. The effect of this government stance was that

past tolerances and understandings about deviations inherent to

mass production of the suit would not apply. The past practice

was to allow reasonable tolerances for manufacturing.

Second, the government’s new position was that “if no

tolerance is given in the specification, then the operation would

77a

Appendix C

have to be ‘exactly as specified’ or it would be scored as a

defect.” PX-47. This is especially significant because 26

operations apparently had either no stitch tolerance or were

written with a 1/64 of an inch tolerance. PX-284. Both parties’

apparel experts basically agreed that such tolerances, or lack

thereof, were unworkable for mass production.

The government repeatedly asserted at trial that there was

not a “no tolerances” policy in effect, but we are convinced that

there was, and it had the effect of slowing operators in their

sewing operations because of the company’s reasonable fear

based on its actual early experience with this contract that every

deviation would be scored and its final products would fail

government inspection for minor defects. The First Article

debacle certainly made such a concern quite rational. Many

operations in the specifications had no tolerance given because

past practice was to imply tolerances reasonable for mass

production of the item. Even defendant’s production expert

acknowledged that a contractor must have tolerances in order

to mass produce a garment. Tr. 5980-81. Amertex actually

engaged in a higher level of inspection due to the policy.

Nonetheless, it is impossible to produce millions of garments

in an expedited and efficient manner in an atmosphere in which

the government expressed its intent to score every single

deviation with no tolerances implied.*!

41. The government repeatedly ignored the specification problems

caused by a combination of specifications with missing tolerances and

quality assurance personnel who refused to imply tolerances necessary

for mass production. For example, there was a problem with the inspection

of the cut parts relating to drill holes, which are the result of holding

stacks of fabric hundreds of layers thick in order to cut and also mark

notches. Tr. 914-15. The specification did not provide a tolerance for

this item; therefore, Amertex requested that tolerances be established.

(Cont'd)

78a

Appendix C

Also in April 1986, a new modification was issued, P7,

which included changes for the lining specifications and the

sleeve tabs. Tha

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.