Petition for Writ of Certiorari — Essex Electro Engineers, Inc. v. Widnall

Supreme Court brief1997

Ask Donna

What actually matters in this document.

Text

Supreme Court, U.S.

rage

, \

‘gy. 417 SEP - 8 1997

No.orric OF THE CLERK

IN THE

Supreme Court of the United States

OcTOBER TERM, 1997

Essex ELECTRO ENGINEERS. INC.

Petitioner

Vv.

SHEILA E. WIDNALL.

SECRETARY OF THE AIR FORCE.

Respondent,

On Petition for a Writ of Certiorari to the

United States Court of Appeals for the Federal Circuit

PETITION FOR A WRIT OF CERTIORARI

CHARLES E. RALEY

Counsel of Record

W. DREW MALLENDER

WATT, TIEDER & HOFFAR, L.L.P

7929 Westpark Drive

Suite 400

McLean, Virginia 22102

(703)749-1000

Attomeys for Petitioner

September 5, 1997

QUESTION PRESENTED

Under 41 U.S.C. §§ 607, is a dismissal by an

agency board without prejudice to refiling a “decision”

from which an appeal to the United States Court of

Appeals for the Federal Circuit is mandatory within one

hundred twenty days or is such a dismissal “other

appropriate action” by the board with the matter to be

reinstated if the cause for the interlocutory dismissal is

removed within three years as required by Rule 30 issued

under the authority of the Act?

1i

PARTIES TO THE PROCEEDING

Petitioner is Essex Electro Engineers, Inc., a small

business concer. Pursuant to Supreme Court Rule 29.6,

petitioner states that it has no parent company or

subsidiaries.

A343

TABLE OF CONTENTS

Page

QUESTION PRESENTED ..................... i

PARTIES TO THE PROCEEDING ............. li

Some Wr PAD TIuiGe .................005. iv

So 8 SES | 1

Ot te 2

STATUTORY PROVISIONS AND RULES ......... 2

STATEMENT OF THECASE ................... 6

The Relationship Between the Parties........... 6

The Proceedings Below...................... 8

REASONS FOR GRANTING THE PETITION ..... 10

The Appellate Court has Abrogated the Rule Issued

for the Board to Carry Out the Provisions of the Act

and Contradicted the “Norm” Defined by this Court..1Z

Essex has been Foreclosed from its Right to

an Efficient and Fair Resolution of its Claims .... 16

ES 21

SE a a Attached

lv

TABLE OF AUTHORITIES

Page

Cases:

Beam, James B., Distilling Co. v. Georgia,

501 U.S. 529, 111 S.Ct. 2439 (1991). 12, 14-15

Califomia v. Harvier,

700 F.26 1217 (th Ce. 1965) ............ 13

Dawco Construction, Inc. v. United States,

930 F.2d 872 (Fed.Cir. 1991)..... 8,9, 10, 11,

17,18, 19-21

Ellett, James M., Construction Co.

v. United States,

93 F.3d 1537 (Fed.Cir. 1996) .......... 12, 19

Electronics & Space Corp., ASBCA No. 37352,

Se 20

Die WN ET ok ee en ieee 20

Mayfair Consiruction Company v.

United States, 841 F.2d 1576 (Fed.Cir. 1988),

cert. den., 488 U.S. 980 (1988) ...... 7-11, 18

Mediax Interactive Technologies, Inc.,

ASBCA No. 43961, 93-3 BCA] 26,071 ..... 20

Mesa v. United States,

Oi F.oG au (110) Ge. 1905) ...... 2.22055. 13

Midland Maintenance, Inc..,

ENG BCA Nos. 6080, et a/.,

OG-T BOA G27 OGs «www ecw ee 20-21

Peters v. Welsh Development Agency,

920 F.2d 438 (7th Cir. 1990) ............. 13

Reflectone, Inc. v. Dalton,

60 F.3d 1572 (Fed.Cir.1995)...... 10, 11, 12,

15-21

reversing, Reflectone, Inc., ASBCA No. 43081,

93-1 BCA 925,812 .......... 8, 20

Page

Cases [Continued]:

United States v. Grumman Aerospace Corp.,

927 F.2d 575 (Fed.Cir. 1991),

cert.denied, 502 U.S. 919, 112 S.Ct. 330 ... 20

Statutes, Rules, and Other Authorities:

28 U.S.C. § 1254(1) . 0.2 ee. 2

28 U.S.C.§ 1291.0... ee 4,12

28 U.S.C.§ 1292 ................. 2,4, 5, 12-13

28 U.S.C.§ 1295 ................. 2,4, 5, 12, 14

41U.S.C.§ 401 ....... 0... eee ee 3

44 U.S.C. S GOS ow. ce en cn wen 117.1

41U.S.C.§ 607 ................. i, 2, 3, 5, 12-14

OT UDG. BGS go cc eee anne eeee weenie 2

P.L. 102-572, § 907, 6 Stat.4518 ............. 20

PRR SDAA occ ieee aces reas dea en 18

FAR § 49.101(d) ........0.0. 000.000.0000, 8

Supreme Court Rule 29.6 ............. ...... ii

Federal Claims Court Rule 41(b) .............. 13

O.F.P.P. Board Rule $ ...............0008- 4,14

O.F.P.P. Board Rule 30......... 4,10, 11, 14, 16,

20, 21

S.Rep. No. 1118, 95th Cong., 2d Sess. 4 (1978),

repnnted, 1978 U.S.C.C.A.N. 5235 ........ 17

Blacks Law Dictionary,

W¥@Ot, Gir OG. (TOG) oc 5 cies vac vse ew ues 13

eee

IN THE

Supreme Court of the United States

OCTOBER TERM, 1997

No.

Essex ELECTRO ENGINEERS, INC.

Petitioner,

V.

SHEILA E. WIDNALL,

SECRETARY OF THE AIR FORCE,

Respondent,

—_—_———_

On Petition for a Writ of Certiorari to the

United States Court of Appeals for the Federal Circuit

PETITION FOR A WRIT OF CERTIORARI

Essex Electro Engineers, Inc. ["Essex’],

respectfully petitions for a writ of certiorari to review the

judgment of the United States Court of Appeals for the

Federal Circuit.

OPINIONS BELOW

The Federal Circuit's decision, published at 116

F.3d 461, is reproduced in the Appendix (App.) at 1.

The dismissal of Essex’s appeals without prejudice by

the Armed Services Board of Contract Appeals

2

["Board”], published at 94-2 BCA J 26,902, is

reproduced at App. 10. The reconsideration by the

Board affirming the dismissal without prejudice,

published at 95-1 BCA ¥] 27,302, is reproduced at App.

6. The Board’s decision not to reinstate Essex’s

appeals after the cause for the dismissal was removed,

published at 96-2 BCA 4] 28,600, is reproduced at App.

4.

JURISDICTION

The Board had jurisdiction for its final decision

not to reinstate the appeals under 41 U.S.C. § 607. The

earlier dismissal without prejudice by the Board was

based on finding that at the time it lacked jurisdiction to

proceed with the appeals to a decision. The Court of

Appeals had jurisdiction under 41 U.S.C. §§ 607 and

609 and 28 U.S.C. § 1295. The judgment of the Court

of Appeals was entered June 24, 1997. This Court has

jurisdiction to issue the Writ under 28 U.S.C. § 1254(1).

STATUTORY PROVISIONS AND RULES

This case requires an analysis to resolve the

inherent tension that exists between the statutory

authority of the agency boards to render “decisions” or

to “take other appropriate action” on submitted appeals

under 41 U.S.C. § 607 and the consequent effect on

appeal rights to the Federal Circuit. This analysis is

particularly critical in the absence of rules issued under

this Court's authority in 28 U.S.C. § 1292(e) and

involves consideration of the following provisions:

3

41 U.S.C. § 607. Agency boards of contracts

appeals.

(d) Jurisdiction.

Each agency board shall have jurisdiction

to decide any appeal from a decision of a

contracting officer...In exercising this jurisdiction,

the agency board is authorized to grant any relief

that would be available to a litigant asserting a

contract claim in the United States Court of

Federal Claims.

(e) Decisions.

An agency board shall provide to the

fullest extent practicable, informal, expeditious,

and inexpensive resolution of disputes, and shall

issue a decision in writing or take other

appropriate action on each appeal submitted....

(g) Review.

(1) The decision of an agency board of

contract appeals shall be final, except that--

(A) a contractor may appeal such a

decision to the United States Court of Appeals for

the Federal Circuit within one hundred twenty

days after the date of receipt of a copy of such

decision....

(h) Procedural guidelines.

Pursuant to the authority conferred under

the Office cf Federal Procurement Policy Act [41

U.S.C. § 401 et seq.J, the Administrator is

authorized and directed, as may be necessary or

desirable to carry out the provisions of this

ee

+

chapter, to issue guidelines with respect to

criteria for the establishment, functions, and

procedures of the agency boards....

Agency Board Rule 5. Motions.

(a) Any motion addressed to the jurisdiction of

the Board shall be promptly filed....The Board

shall have the right at any time and on its own

initiative to raise the issue of its jurisdiction to

proceed with a particular case, and shall do so by

an appropriate order, affording the parties an

opportunity to be heard thereon.

Agency Board Rule 30. Suspensions; dismissal

without prejudice.

...In certain cases, appeals docketed

before the Board are required to be placed in a

suspense status and the Board is unable to

proceed with disposition thereof for reasons not

within the control of the Board. Where the

suspension has continued, or may continue, for

an inordinate length of time, the Board may, in its

discretion, dismiss such appeals from its docket

without prejudice to their restoration when the

cause of suspension has been removed. Unless

either party or the Board acts within three years

to reinstate any appeal dismissed without

prejudice, the dismissal shall be deemed with

prejudice.

28 U.S.C. § 1291. Final decisions of district courts.

... The jurisdiction of the United States Court of

Appeals for the Federal Circuit shall be limited to

the jurisdiction described in sections 1292(c) and

(d) and 1295 of this title.

5

28 U.S.C. § 1295. Jurisdiction of the United States

Court of Appeals for the Federal Circuit.

(a) The United States Court of Appeals for

the Federal Circuit shall have exclusive

jurisdiction--

(3) of an appeal from a final decision of

the United States Court of Federal Claims...

(10) of an appeal from a final decision of

an agency board of contract appeals pursuant to

section 8(g)(1) of the Contract Disputes Act of

1978 (41 U.S.C. 607(g)(1))...

28 U.S.C. § 1292. Interlocutory decisions.

(d)(2)...when any judge of the United States

Court of Federal Claims, in issuing an

interlocutory order, includes in the order a

statement that a controlling question of law is

involved with respect to which there is a

substantial ground for difference of opinion and

that an immediate appeal from that order may

materially advance the ultimate termination of the

litigation, the United States Court of Appeals for

the Federal Circuit may, in its discretion, permit

an appeal to be taken from such order, if

application is made to that Court within ten days

after the entry of such order.

(e) The Supreme Court may prescribe rules, in

accordance with section 2072 of this title, to

provide for an appeal of an interlocutory decision

to the courts of appeals that is not otherwise

provided for under subsection (a), (b), (c), or (d).

6

STATEMENT OF THE CASE

The Relationship Between the Parties

At the end of December, 1989, the government

awarded two competitive, fixed price, small business

contracts to Essex, Contract F41608-90-D-0410

["Contract-0410"] for Floodlight Sets and Contract

F41608-90-C-0409 ["Contract-0409"] for related spare

parts. [App. 10]. Essex could not proceed with

production and delivery until completion and government

approval of first article testing, which was scheduled for

August 2, 1990. Deliveries were scheduled to be

completed in February, 1991.

Beginning in March, 1990, and continuing through

July, 1990, Essex discovered and notified the

government of deficiencies in the government's

drawings and specifications [App. 11]. During meetings

in July, 1990, the government representatives reviewed

and discussed Essex’s plan to obtain diesel engine

generators for the floodlight sets from a source other

than the “Suggested Source” on the government's

drawing. [App. 11].

Yet, months later, after the drawing deficiencies

were corrected and Essex had completed the first article

and was ready to proceed with the testing, in January,

1991, a new contracting officer withheld approval to start

testing unless Essex used the “suggested” engine

generator or “qualified” Essex’s selected engine

generator source by performing criteria and testing in

addition to the first article tests in the Contract. [App.

13]. Essex immediately notified the contracting officer

that the additional qualification criteria and testing

7

violated the Contract and required a_ contract

modification. [App. 13-14]. In April, 1991, the

contracting officer again stated that he would not

authorize first article testing unless Essex either used

the “suggested” engine generator or qualified Essex's

selected source [App. 14]. In early May, 1991, Essex

notified tie contracting officer that it was his “obligation

to issve a Final Decision” ordering performance in

accordance with his interpretation. [App. 16].

The Government then issued “termination for

convenience” notices in late June, 1991, on “Contract-

0410” and in late July, 1991, on “Contract-0409." [App.

18].

Essex made a written submission for Contract-

0410 in June, 1992, containing a recitation of the facts

and seeking $635,434, as “[oJur Claim, certified as

required by the Act..for changes including the

Government-caused first article delays and production

disruption...[and] the previous disputes regarding the

specification control drawings and deficient Government

technical data...” [App. 19-20]. Essex further demanded

a contracting officer's decision and insisted “upon the

time requirements of the Contract Disputes Act for a

response to this claim.” [App. 20]. In July, 1992, Essex

made a similar submission for Contract-0409 seeking

$20,603, and including the foregoing statements, except

noting that, since the amount did not exceed $50,000,

a CDA certification was not necessary. [App. 22-23].

in essentially duplicate letters, in July and August,

1992, a Termination Contracting Officer ["“TCO"]

asserted that each of Essex’s submissions were “not a

claim for purposes of the Act.” The letters cited Mayfair

8

Construction Company v. United States, 841 F.2d 1576

(Fed.Cir. 1988), and Dawco Construction, Inc. v.

United States, 930 F.2d 872 (Fed.Cir. 1991). [App. 20-

24).

By letters in September and October, 1992,

Essex resubmitted its claims “solely for the purpose of

preserving Essex’s rights and in no way...a waiver of the

existence of the valid and lawful claim.” Essex noted

that the TCO had “already failed to take prompt action

to resolve the claims as required by FAR § 49.101(d)

[which is applicable to a small business concern such as

Essex] and the CDA...” [App. 24-28].

The Proceedings Below

No decisions by the contracting officer were

issued on Essex’s claims. After waiting six and seven

months, respectively, in January, 1993, Essex filed

notices of appeal to the Board from the contracting

officer's failure to decide. The appeals were docketed

as ASBCA No. 45663 and 45664. [App. 28]. Essex filed

its Complaints and served discovery requests in March,

1993. The government filed no answer to the

Complaints. Rather, in June, 1993, the government filed

a Motion for a Protective Order to foreclose any

discovery by Essex and a Motion to Dismiss, citing

Mayfair, supra., and Dawco, supra.

Ten months later in April, 1994, the Board

dismissed Essex’s appeals “without prejudice” to

resubmission of “proper” claims. The Board relied on

Mayfair, supra., and Dawco, supra., and its own

decision in Reflectone, Inc., ASBCA No. 43081, 93-1

BCA {| 25,512, holding that Essex’s submissions were

9

not CDA claims because “there was no underlying

dispute” before the claims were submitted and ‘[t]his

Board, of course, is obliged to follow the precedents of

the Federal Circuit.” [App. 30-31, 34].

Eleven days later, on May 5, 1994, Essex moved

the Board for reconsideration and, while continuing to

question the applicability and validity of Mayfair, supra..,

and Dawco, supra., Essex pointed out that its demand

of May 6, 1991, for a contracting officer's decision on

the specification control drawing dispute was itself a

proper CDA claim for an interpretation of contract terms

or, at least, evidenced a pre-existing dispute. [App. 8].

In November, 1994, the Board affirmed its earlier

dismissals without prejudice. [App. 9].

In the meantime, on June 14, 1993, Essex had

submitted a separate CDA certified claim for damages

for the government's breach and repudiation in ending

Contract-0410 in bad faith. Eight months later, no final

decision had been rendered by the contracting officer

and Essex filed another appeal to the Board, which was

docketed as ASBCA No. 47167. The filing of that

appeal allowed Essex to begin discovery.

After two years, in July, 1994, a contracting

officer issued a decision on Essex’s first claim, allowing

less than 10% and nothing for the increased costs for

the drawing deficiencies and the delays and disruptions.

Essex filed another appeal and requested consolidation

with its earlier appeals. Essex also filed another notice

of appeal from the contracting officer's continuing failure

to decide the initial claim on Contract-0409 and also

requested consolidation. To date, the merits of Essex's

claims have not been resolved.

10

On July 26, 1995, the United States Court of

Appeals for the Federal Circuit issued its en banc

decision in Reflectone, Inc. v. Dalton, 60 F.3d 1572

(Fed.Cir. 1995), specifically reversing the Board's

decision in Reflectone, supra., restricting Mayfair,

supra., and overruling Dawco, supra., and “all cases

relying on Dawco.” Thirteen days later, on August 8,

1995, Essex filed its motion to set aside the Board's

prior dismissals without prejudice and to reinstate the

appeals, citing the Board’s Rules, the guidance provided

by the Federal Rules of Civil Procedure, and the

decision in Reflectone. [App. 4].

More than one year later, in October, 1996, the

Board issued its decision, denying Essex’s motion to

reinstate the appeals and holding that the dismissals

were final. [App. 6]. Essex’s Appeal to the Federal!

Circuit followed immediately. On June 24, 1997, the

Court of Appeals affirmed the Board’s refusal to

reinstate, holding that the Board’s earlier dismissal.

without prejudice had become final 120 days after it was

entered and could not thereafter be appealed. The

Court reached its conclusion even though it recognized

that “Rule 30 provides that an appeal dismissed without

prejudice becomes an appeal dismissed with prejudice

if not reinstated within three years.” [App. 1-3].

REASONS FOR GRANTING THE PETITION

The decision of the Court of Appeals has affirmed

action by the Board which materially departs from the

authority for Board proceedings mandated by Congress

in the Contract Disputes Act, as implemented in the

Board’s own Rules, and alters the appellate jurisdiction

11

conferred on the Court of Appeals. Essex has thus

been denied access to the Board for a decision on the

merits of its initial appeals with the consequent denial of

fundamental rights afforded by the Act.

The Board dismissed Essex’s appeals “without

prejudice” by concluding that it was prevented from

proceeding to a decision based on its own Reflectone

decision, and because it was “obliged to follow” the

decisions of the Federal Circuit in Mayfair and Dawco,

supra., which had held that there can be no explicit or

presumed decision of a contracting officer if it is found

that no dispute had existed before a Contract Disputes

Act “claim” was submitted.’ Nine months after the

Board reconsidered and reiterated its dismissal without

prejudice, the Federal Circuit decided Reflectone,

supra., en banc, reversing, restricting, and overruling

every reason for the Board's inability to proceed with

Essex’s appeals. Essex immediately moved the Board

to reinstate its appeals. The Board's ultimate decision,

refusing to reinstate the appeals, rendered the

dismissals final with prejudice. The Court of Appeals

affirmed the Board’s refusal to vacate and reinstate for

two stated reasons [App. 2-3]:

1. Even though “Rule 30 provides that an appeal

dismissed without prejudice becomes an appeal

dismissed with prejudice if not reinstated within three

years...[i]t does not, however, provide a mechanism to

reinstate a dismissed appeal.” An appeal to the Federal

‘Explicit and presumed decisions by contracting

officers are defined in 41 U.S.C. § 605(a) and (c),

respectively.

12

Circuit from the earlier dismissals without prejudice was

required within 120 days from the date they were

entered and “could not thereafter be appealed. See

James B. Beam Distilling Co. v. Georgia, 501 U.S. 529,

541 (1991).”

2. The Court of Appeals was not being

“inconsistent with James M. Ellett Construction Co. v.

United States, 93 F.3d 1537 (Fed.Cir. 1996). In that

case, the appellant filed a notice of appeal within 120

days of the judgment of the Court of Federal Claims and

requested a stay pending our decision in Reflectone, a

situation completely different from this one.”

The Appellate Court has Abrogated the Rule Issued

for the Board to Carry Out the Provisions of the Act

and Contradicted the “Norm” Defined by this Court

The Board's authority extends only to issuing a

“decision” on an appeal from a decision of a contracting

Officer or taking “other appropriate action” on a

submitted appeal. [41 U.S.C. § 607(d) & (e)]. The

Federal Circuit's jurisdiction on appeals that are required

to be filed “within one hundred twenty days” is limited to

review of a “decision” of the Board, with no mention of

reviewing “other appropriate action” the Board may take

on a submitted appeal. [41 U.S.C. §607 (g)(1)(A); 28

U.S.C. § 1295(a)(10)].

The Court of Federal Claims has explicit statutory

authority to issue interlocutory orders with the Federal

Circuit then having jurisdiction for a discretionary

appeal, if the necessary statement is included in the

lower court's order. [28 U.S.C. §§ 1291 & 1292(d)(2)].

“Interlocutory” is defined as “[s]omething intervening

ad eS Date erik Heine USI N Cale

i3

between the commencement and the end of a suit which

decides some point or matter, but is not a final decision

of the whole controversy.” Black’s Law Dictionary,

West, 6th ed., p. 815 (1990). A dismissal without

prejudice to refiling would not be an adjudication upon

the merits in a proceeding under Rule 41(b) of the Rules

of the Court of Federal Claims and would not be

appealable because it contemplates further proceedings

in the same forum. [Cf., Peters v. Welsh Development

Agency, 920 F.2d 438, 440 (7th Cir. 1990); California v.

Harvier, 700 F.2d 1217, 1218-19 (9th Cir. 1983); Mesa

v. U.S., 61 F.3d 20, 21 (11th Cir. 1995)].

The only statutory authority for the Board to issue

such interlocutory orders resides in the provision for

“other appropriate action” under procedural guidelines to

be issued “to carry out the provisions” of the Act. [41

U.S.C. § 607(d), (e) & (h)]. It must be recognized that,

while the authority of the Court of Federal Claims to

issue interlocutory orders and discretionary appeals from

those orders is clearly expressed in the statutory

provisions, the Supreme Court has not exercised its

rule-making authority to “provide for an appeal of an

interlocutory decision to the courts of appeals,” in

connection with such decisions by the Board. [28 U.S.C.

§ 1292(e)]. In addition, if interlocutory authority of the

Board resides in the provision for “relief that would be

available” in the Court of Federal Claims [41 U.S.C. §

607(d)], the Board’s dismissals of Essex’s appeals

without prejudice did not contain the statement required

for such a decision by the Court of Federal Claims that

would then give rise to a discretionary appeal to the

Federal Circuit. [28 U.S.C. § 1292(d)(2)].

14

Among the Rules that have been issued for the

Board “to carry out the provisions” of the Act, Rule 5

concerns the potential for a limitation on the Board’s

jurisdiction that would prevent it from proceeding to a

decision in a particular case. Rule 30 is the only Rule

which then addresses a dismissal without prejudice by

the Board, if the “Board is unable to proceed with

disposition...[of a case] for reasons not within the control

of the Board...” The Board may “dismiss such appeals

from its docket without prejudice to their restoration

when the cause of suspension has been removed.”

Either party or the Board may then act “within three

years to reinstate any appeal dismissed without

prejudice.” Contrary to the conclusion of the Federal

Circuit, Rule 30 establishes not only the mechanism but

also the time limit for reinstating “any appeal dismissed

without prejudice.” Such a dismissal is not a “final

decision of an agency board” under the Contract

Disputes Act from which an appeal to the Federal Circuit

is required within 120 days, particularly here, where the

predicate for the Board's dismissal was that there had

been no “claim” or decision of the contracting officer on

which the Board could render a decision in the appeals

under the Act. [41 U.S.C. § 607(g)(1)(A); 28 U.S.C. §

1295(a)(10)].

The Federal Circuit's citation to this Court's

decision in James 8. Beam Distilling Co. v. Georgia,

901 U.S. 529, 111 S.Ct. 2439, 115 L.Ed.2d 481 (1991),

is misplaced and neither expands the meaning of

“decision” of the Board, in contrast with “other

appropriate action” by the Board, nor does it restrict the

reinstatement period defined by Rule 30. James B.

Beam Distilling Co. involved an action filed in Georgia

seeking a refund of taxes paid under Georgia law

15

applicable to 1982 through 1984, based on a decision of

this Court in 1984, holding that similar laws in Hawaii

violated the Commerce Clause. The Court held that the

retroactivity of a decision is a choice-of-law question:

“As a matter purely of judicial mechanics, there

are three ways in which the choice-of-law

problem may be resolved. First, a decision may

be made fully retroactive, applying to the parties

before the court and to all others by and against

whom claims may be pressed, consistent with res

judicata and procedural barriers such as statutes

of limitations. This practice is overwhelmingly

the norm....” 501 U.S. at 535, 111 S.Ct. at 2443;

emphasis added.

As for a second way of resolving the problem, “a

purely prospective method of overruling” is used by

“announcing the new” as effective only after the date of

the decision. 501 U.S. at 536, 111 S.Ct. 2443. There

was no announcement of prospectivity by the Federal

Circuit in Reflectone, supra.

The third way of resolving the problem would be

“selective prospectivity” but that “breaches the principle

that litigants in similar situations should be treated the

same, a fundamental component of stare decisis and

the rule of law generally...[SJelective prospectivity

appears never to have been endorsed in the civil

context.” 501 U.S. at 537-38, 111 S.Ct. at 2444-5.

In its citation to James B. Beam, the Federal

Circuit below only refers to 501 U.S. at 541, without

discussing the foregoing choice-of-law analysis and the

“norm” defined by this Court. At the cited page in the

16

decision, this Court merely reiterated the rule that

retroactivity is limited only “by res judicata or by statutes

of limitation or repose.” A dismissal without prejudice to

refiling is not a decision on the merits and has no res

judicata effect. The only “limitation” that exists with

respect to a Board dismissal without prejudice is Rule

30 providing for reinstatement within a period of three

years if the cause for the dismissal is removed. The en

banc decision in Reflectone, supra., removed the cause

for the Board's dismissals of Essex’s appeals without

prejudice and Essex timely sought reinstatement within

sixteen months after the initial dismissals and less than

nine months after the Board’s reconsideration and

reiteration of the dismissals without prejudice.

Essex has been Foreclosed from its Right to an

Efficient and Fair Resolution of its Claims

In May, 1991, Essex submitted a written demand

for a contracting officer's final decision on the dispute

regarding the interpretation of the contract terms

applicable to the Specification Control Drawing. In

June, 1992, Essex submitted a written demand for a

contracting officer's final decision on an amount

exceeding $50,000 with a proper certification required

by the Contract Disputes Act. In July, 1992, Essex

submitted a written demand for a contracting officer's

final decision on an amount on the second contract

which was less than $50,000. In September and

October, 1992, Essex resubmitted its previous demands.

After more than five years, no decision has yet been

rendered on the merits of Essex’s claims and appeals to

the Board.

. 17

When it overruled the cause for the Board's

dismissal of Essex’s appeals wiithout prejudice, the

Federal Circuit acknowledged that--

“Dawco has proven to be inimical to at least two

goals of the CDA: providing for the efficient and

fair resolution of contract claims. See, Report of

the Senate Governmental Affairs Committee and

the Senate Judiciary Committee on the Contract

Disputes Act of 1978, S.Rep. No. 1118, 95th

Cong., 2d Sess. 4 (1978), reprinted in 1978

U.S.C.C.A.N. 5235, 5238."

ark

“A dispute requirement _ that allows the

government to unilaterally designate when a

submission becomes a ‘claim’ disrupts the

4 balance of power between the government and

contractors that the CDA sought to establish.

(/d.]...The purpose of awarding interest to

contractors from the submission date of a

successful claim is to compensate them for 2

legitimate cost incurred when required by the

government to perform the additional work of a

changed contract. /d...at 5266. Allowing the

government to unilaterally determine a claim's

submission date would vitiate this purpose.

: “The parties are not prevented or discouraged

i from settling their differences because the first

4 written demand for payment...is recognized and

treated as a CDA ‘claim.’ If anything, such a rule

promotes settlement by preventing

procrastination.” Reflectone, 60 F.3d at 1580, 82-

83.

RO on ee or

18

The dismissal of Essex’s appeals without

prejudice denied Essex’s right to fundamental “goals” in

the Contract Disputes Act, and has allowed massive

procrastination in the resolution of the merits of Essex’s

claims. In Reflectone, 60 F.3d at 1578, under the

heading, “Dawco’s Holding is Overruled’, the Federal

Circuit first discussed its prior decision in Mayfair

Construction Co., supra., which had served as the

underpinning for Dawco and for the Board's dismissal

without prejudice here. The Reflectone Court held that

Mayfair was “mistakenly quoted in Dawco,” because it

had been based on--

“...interim regulatory language incorporated into

the contract's disputes clause explicitly requiring

that a claim be in dispute when submitted....,

therefore, Mayfair provides no support for

requiring a pre-existing dispute in any case

involving contracts resulting from solicitations

issued after June 1, 1980.” Reflectone, 60 F.3d

at 1579.

The Reflectone Court then concluded:

“We hold that properly construed for its plain

meaning, the language of FAR 33.201 does not

require that a payment demand contained in a

purported CDA claim be in dispute before being

submitted for decision to the CO unless that

demand is a ‘voucher, invoice or other routine

request for payment.’ To the extent that Dawco

and cases relying on Dawco can be read to

suggest otherwise, they are overruled.” /d., 60

F.3d at 1583; emphasis added.

eal eR MANA kite Pps ABATE Ne <font eC) ele

4

‘

3

x

Y

x

=

4

‘

<

19

Further, on August 26, 1996, the Federal Circuit

decided James M. Ellett Constr. Company, Inc. v.

United States, 93 F.3d 1537 (Fed.Cir. 1996), which was

an appeal from a final judgment entered by the Court of

Federal Claims dismissing Ellett’s suit in relying on

Dawco, supra. AS a consequence of its en banc

decision in Reflectone, “overruling the cases upon which

the trial court had relied in dismissing Ellett's complaint,”

the Court reversed and remanded Ellett’s case to the

lower court for further proceedings. E//ett, 93 F.3d at

1539. Also, pertinent to the termination claims here, the

Court in El/ett, observed:

“it is difficult to conceive of a less routine

demand for payment than one which is submitted

when the government terminates a contract for its

convenience. Such a demand...is certainly less

routine than a request for an equitable

adjustment.” /d., 93 F.3d at 1542.

The Board's own Rules, issued under the

statutory authority for guidelines to “carry out the

provisions” of the Contract Disputes Act, deny finality to

a dismissal without prejudice for a period of three years

and render “any appeal” subject to reinstatement when

the cause for dismissal has been removed within that

period. The cause for the dismissal of Essex’s appeals

without prejudice was emphatically removed by the

Federal Circuit's decision in Reflectone, as was further

emphasized by the Federal Circuit's decision in E/ett.

Yet, when Essex acted to obtain reinstatement of its

appeals, the Board refused.

The Board's decision denying reinstatement cited

neither its Rules nor any authority. It referenced only its

20

Opinion in Electronics & Space Corp., ASBCA No.

37352, 95-1 BCA J 27,306. [App. 5]. Yet, that case had

not involved Dawco, supra., nor Reflectone, supra., nor

the Board's Rule 30. In Electronics & Space, the

contractor sought to vacate a prior dismissal that had

been entered in Electronics & Space Corp., ASBCA No.

37352, 92-2 BCA ¥ 24,978, which had been based on

the Federal Circuit’s decision in United States v.

Grumman Aerospace Corp., 927 F.2d 575 (Fed.Cir.

1991), cert. denied, 502 U.S. 919, 112 S.Ct. 330. The

Grumman decision had held that the CDA certification

was a jurisdictional prerequisite to a CDA “claim.” As

the Board held in Electronics & Space, 95-1 BCA ¥

27,306, Grumman Aerospace, supra., Was never

overruled and, when Congress eliminated any

jurisdictional effect in the CDA certification, it expressly

barred a_ retroactive effect. Federal Courts

Administration Act of 1992, Public Law No. 102-572, §

907, 6 Stat. 4518. Electronics & Space Corp. was

patently inapposite to the instant situation.

In reality, the Board’s decision here created a

direct conflict with its own decision in Mediax Interactive

Technologies, Inc., ASBCA No. 43961, 93-3 BCA J

26,071, at p. 129,582 [dismissal without prejudice “did

not render appellant's original proposal a ‘nullity’

preventing consideration seven years later], and with a

decision by the Engineers Board of Contract Appeals in

an identical situation. In Midland Maintenance, Inc..,

ENG BCA Nos. 6080, et al., 96-1 BCA J 27,983, the

Board had earlier dismissed the appeals for lack of

jurisdiction based on the Federal Circuit's initial panel

decision in Reflectone, which had affirmed the Board's

dismissal in Reflectone, Inc., 93-1 BCA § 25,512.

Then, after the en banc decision in Reflectone, Inc. v.

Pet ea oe st een ve.

AOE eid site

Meee PY aes Ca ce eee

filly OUP Lert Stomp GUO poly tad Auld dance ey

ON Den ane RO ee

Diba iy aide Rta ia, Sot Ret P ii tere

21

Dalton, supra., vacated the panel decision, reversed the

Board's decision, and overruled Dawco, supra., the

Board in Midland, 96-1 BCA J 27,983, vacated its

earlier dismissals and reinstated the dismissed appeals.

Rule 30, issued to “carry out the provisions” of the

Contract Disputes Act, is the same for the Engineers

Board of Contract Appeals as it is for the Armed

Services Board of Contract Appeals.

Well within three years, the reason that prevented

the Board from proceeding to a decision and caused the

interlocutory dismissal of Essex's appeals without

prejudice ceased to exist when the Federal Circuit

decided Reflectone, supra. The appeals were required

to be reinstated as provided in Rule 30. The Board's

ultimate decision refusing to do so was plainly wrong, as

is the Federal Circuit's decision to affirm that refusal.

CONCLUSION

For these reasons, Essex’s petition for writ of

certiorari should be granted.

Respectfully submitted,

CHARLES E. RALEY

Counsel of Record

W. DREW MALLENDER

WATT, TIEDER & HOFFAR, L.L.P.

7929 Westpark Drive

Suite 400

McLean, Virginia 22102

(703)749-1000

Attorneys for Petitioner

September 5, 1997

BC RR TEARAA, neviivnuamenaialill “evi :

IN THE

Supreme Court of the United States

: OCTOBER TERM, 1997

NO.

ESSEX ELECTRO ENGINEERS, INC..,

Petitioner,

V.

SHEILA E. WIDNALL,

: SECRETARY OF THE AIR FORCE,

‘ Respondent,

: On Petition for a Writ of Certiorari to the

; United States Court of Appeals for the Federal Circuit

| APPENDIX

APPENDIX

TABLE OF CONTENTS

Essex Electro Engineers, Inc., v.

Widnall, 116 F.3d 461 (Fed.Cir. 1997) ....... 1

Essex Electro Engineers, Inc.,

ASBCA Nos. 45663, 45664,

es ie 4

Essex Electro Engineers, Inc.,

ASBCA Nos. 45663, 45664,

poe... GS-1 BOAT 2! cue... «6... cee eee 7

Essex Electro Engineers, Inc.,

ASBCA Nos. 45663, 45664,

a 10

h-

UNITED STATES COURT OF APPEALS

FOR THE FEDERAL CIRCUIT

97-1046

ESSEX ELECTRO ENGINEERS, INC.,

Appellant,

V.

AIR FORCE,

Appellee.

DECIDED: June 24, 1997

Before MAYER, Circuit Judge, SKELTON, Senior Circuit

Judge, and BRYSON, Circuit Judge.

PER CURIAM.

Essex Electro Engineers, inc. appeals the decision

of the Armed Services Board of Contract Appeals.

ASBCA Nos. 45663 and 45664, 96-2 BCA J 28,600,

denying Essex's motion to vacate the board's prior

decision dismissing Essex's appeal without prejudice, for

lack of jurisdiction. We affirm.

Essex entered into two contracts with the Air Force

for the manufacture and delivery of floodlight sets and

spare parts. Prior to completion of the contracts, the Air

Force terminated the contracts for convenience. Essex

then submitted settlement proposals to the termination

contracting officer (TCO), seeking termination costs and

interest on these costs. Relying on Mayfair Construction

Co. v. United States, 841 F.2d 1576 (Fed.Cir. 1988), and

1

Dawco Construction, Inc. v. United States, 930 F.2d 872

(Fed.Cir. 1991), the TCO determined that the interest

Essex sought was not recoverable and that each

submission was a “voucher, invoice, or other routine

request for payment that [was] not in dispute when

submitted and [was] not a claim for purposes of the

[Contract Disputes] Act.” Essex appealed the decision to

the board, which dismissed the appeal for lack of

jurisdiction, also relying on this court's Mayfair and Dawco

cases, as well as the board's decision in Reflectone, Inc.,

ASBCA No. 43081, 93-1 BCA ¥ 25,512 (1992).

More than eight months later, we reversed the

board's decision in Reflectone, holding that a submission

need not be in dispute before it can be a claim under the

Act. Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed.Cir.

1995)(en banc)(overruling Dawco, in part). Thirteen days

later, Essex moved to vacate the board's earlier

dismissal, and asked for retroactive application of this

court's Reflectone. The board denied the motion.

The board's first decision was not the result of

inadvertent error or a mistake of law. It correctly relied

upon precedent binding at the time, and Essex chose not

to appeal. As a result, that decision became final 120

days after it was entered, 41 U.S.C. § 607(g)(1)(A)

(1994), and could not thereafter be appealed. See,

James B. Beam Distilling Co. v. Georgia, 501 U.S. 529,

541 (1991).

Essex argues that ASBCA Rule 30 permits

reopening an appeal up to three years after it has been

dismissed. Rule 30 provides that an appeal dismissed

without prejudice becomes an appeal dismissed with

prejudice if not reinstated within three years. It does not,

however, provide a mechanism to reinstate a dismissed

2

et At a pe GE OO tt ag Vit

a Tih. ihe SE A a Rate sto Lilies i a Ril Is eet

eh eee

appea!. Nor is the result reached today inconsistent with

James M. Ellett Construction Co. v. United States, 93

F.3d 1537 (Fed.Cir. 1996). In that case, the appellant

files a notice of appeal within 120 days of the judgment of

the Court of Federal Claims and requested a stay pending

our decision in Reflectone, a situation completely different

from this one.

Accordingly, the decision of the Armed Services

Board of Contract Appeals is affirmed.

AFFIRMED.

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of --

)

)

Essex Electro Engineers, Inc. ) ASBCA Nos. 45663

) and 45664

Under Contract Nos. )

F41608-90-D-0410 )

)

F41608-90-C-0409

OPINION BY ADMINISTRATIVE JUDGE PAUL

ON APPELLANT'S MOTION TO VACATE EARLIER OPINIONS

Dated: October 15, 1996

On 20 April 1994, the Board issued a decision, 94-

2 BCA ¥ 26,902, in which it dismissed these appeals

without prejudice for lack of jurisdiction. Noting that

appellant Essex Electro Engineers, Inc.'s (Essex)

termination for convenience settlement proposals were

not in dispute at the time they were submitted, we held

that Essex had not filed cognizable claims under the

Contract Disputes Act, 41 U.S.C. §§ 601 ef seg. (CDA).

In reaching its decision, the Board relied upon a host of

precedents, including Dawco Construction Inc. v. United

States, 930 F.2d 872 (Fed.Cir. 1991), and Reflectone,

Inc., ASBCA No. 43081 93-1 BCA 7] 25,512. Essex filed

a timely motion for reconsideration which we denied in a

decision, 95-1 BCA J 27,302, dated 18 November 1994.

Essex did not perfect an appeal to the United States

Court of Appeals for the Federai Circuit.

On 26 July 1995, the Federal Circuit issued its

opinion in Reflectone, Inc. v. Dalton, 60 F.3d 1572

(Fed.Cir. 1995), in which it reversed the Board's decision

and overruled its opinion in Dawco, supra. On 8 August

3

t

*

4

f

i

Sickithimmbnkes stmadate tater esac co cea t tn cop

BOER

SP ae

0 a ATS ENE

1995, Essex filed a motion to vacate our earlier decision

dismissing its appeals for lack of jurisdiction. It cited, inter

alia, the Federal Circuit's opinion in Reflectone and “the

guidance provided by the Federal Rules of Civil

Procedure.” The parties briefed this issue extensively

over a period of several months.

DISCUSSION

A similar situation arose in Electronics & Space

Corp., ASBCA No. 37352, 95-1 BCA 4] 27,305. Appellant

moved to vacate the Board's earlier decision, 92-2 BCA

{| 24,978, “which found the certification of appellant's

claim for over $7 million was inadequate and dismissed

the appeal without prejudice...” After we issued our initial

decision, appellant failed either to file a motion for

reconsideration or to perfect an appeal with the Federal

Circuit. Subsequently, our appellate court issued a string

of decisions which undermined earlier opinions upon

which the Board had relied. Thereupon, appellant filed its

motion to vacate.

Citing the FRCP as guidance, the Board ruled that

its earlier decision was not “the result of an inadvertent

error or a mistake of law under such exceptional

circumstances as would justify vacating” it. The Board

noted also “[a]ppellant's decision not to seek court review

of the adverse Board decision,” as well as its delay in

filing the motion to vacate. We denied the motion.

It is true that, in this instance, Essex filed a timely

motion for reconsideration; however, like the appellant in

Electronics & Space, supra, it did not appeal to the

Federal Circuit. It thus acquiesced in the correctness of

our decision until it became award of the appellant court's

decision in Reflectone, supra. At the time we issued our

5

initial opinion, the Board was correct in relying upon such

binding precedent as Dawco, supra. Therefore, it cannot

be stated that our decision was “the result of an

inadvertent error or a mistake of law.” As a result of

Essex's failure to appeal, the decision became final and

constitutes the law of this case.

CONCLUSION

The motion is denied.

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of --

)

)

Essex Electro Engineers, Inc. ) ASBCA Nos. 45663

) and 45664

Under Contract Nos. )

F41608-90-D-0410 )

)

F41608-90-C-0409

OPINION BY ADMINISTRATIVE JUDGE PAUL

ON APPELLANT'S MOTION FOR RECONSIDERATION

Dated: November 18, 1994

In a lengthy decision issued on 20 April 1994, 94-2

BCA {| 26,902, the Board dismissed appellant Essex

Electro Engineers, Inc.'s (Essex) appeals without

prejudice for lack of jurisdiction. Explicating the

underlying facts in great detail, we ruled that “[iJt is now

well-settled that when the parties are in a pre-dispute,

negotiation posture, a contractor's submissions will not be

considered claims even though he has invoked the CDA

[Contract Disputes Act] and has characterized his

submissions as claims.” We also gave credence to the

affidavit of the Government's auditor which attributed the

time consumed in processing Essex's submissions to

Essex’ lack of cooperation rather than to any delay on the

Government's part.

Essex subsequently filed a motion for

reconsideration in which it set forth 5-1/2 pages of “facts”

and several pages of “discussion.” A detailed review of

Essex's “facts” demonstrates that appellant has failed to

elicit any new material and has simply distilled the factual

narratives from its earlier briefs. Similarly, Essex's legal

7

arguments are largely a recitation of the contentions

which it had already raised in this proceeding.

The boards of contract appeals have repeatedly

denied motions for reconsideration where a party has

presented no new evidence or arguments which were not

considered in the initial decision. Boeing Aerospace

Operations, Inc., ASBCA No. 46274, 46275 (slip op. 9

Nov. 1994): Scott Peterson Construction Co., ASBCA No.

47028 (slip op. 15 Aug. 1994); Optimal Data Corp.,

NASABCA No. 381-2, 85-2 BCA 4] 18,165, affd, 802 F.2d

469 (Fed.Cir. 1986); Ben Henderson Logging, AGBCA

No. 86-288-1, 86-3 BCA 4] 19,212; Eagle Contracting,

Inc., AGBCA No. 92-197-R, 93-1 BCA J 25,320.

Moreover, as the United States Claims Court held in

Weaver-Bailey Contractors, Inc. v. United States, 20

Cl.Ct. 158, 158-59 (1990): “[A] motion for reconsideration

should not be used as a substitute for an appeal.” To the

extent that Essex has simply rehashed facts and

arguments which we have already carefully considered,

we see no basis for altering our decision.

Two matters raised by Essex, however, deserve

further analysis. First, in a supplement to its motion,

Essex contends that the Board's decision in S-TRON,

ASBCA No. 45890, 94-2 BCA 4 26,957, is “in direct

conflict with the decision in the instant appeals.” Essex is

mistaken. In S-TRON, supra, we took jurisdiction over the

appeal at least partially on the basis that the Government

had delayed “for an unreasonable length of time” in

processing the contractor's submissions. Here, we gave

credence in our initial decision to the auditor's affidavit

which attributed the time consumed in processing Essex's

submissions to Essex rather than to the Government.

The auditor's affidavit was unrebutted, and Essex has not

convinced us that we erred in this regard. Hence, our

8

decision in S-TRON, supra, is distinguishable from our

initial decision in these appeals.

Essex also belatedly attacks the auditor's affidavit

and contends, somewhat surprisingly, that it was not

given an opportunity to rebut the auditor's statements.

First, the Board simply notes that, as pointed out by the

Government in its opposition brief, Essex could have

rebutted these assertions if it chose to do so. Indeed.

Essex filed a motion to strike the auditor's affidavit:

however, it did not append to its motion any evidentiary

materials rebutting his statements. Therefore, this

argument must fail. Finally, even at this juncture, Essex

has not persuaded us that we erred by giving credence to

the auditor's assertions.

CONCLUSION

We have reconsidered our initial decision and

affirm it.

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of --

)

)

Essex Electro Engineers, Inc. ) ASBCA Nos. 45663

) and 45664

Under Contract Nos. )

F41608-90-D-0410 )

)

F41608-90-C-0409

OPINION BY ADMINISTRATIVE JUDGE PAUL

Dated: April 20, 1994

The Government moves to dismiss these appeals

for lack of jurisdiction, asserting that appellant's

termination for convenience settlement proposals were

not proper claims under the Contract Disputes Act of 1978

(CDA), 41 U.S.C. §§ 601-613. Appellant Essex Electro

Engineers, Inc. (Essex) opposes the Government's

motions. It contends that the settlement proposals were

presented to the contracting officer under a disputatious

context, and, thus, constituted proper CDA claims. We

present the following facts solely for the purpose of

resolving these motions.

FACTUAL BACKGROUND

The Government awarded Essex contract No.

F41608-90-D-0410 (0410), for the supply of an indefinite”

quantity of TF-1 floodlight sets (ASBCA No. 45663), and

contract No. F41608-90-C-0409 (0409), for the supply of

spare parts for the TF-1 floodlight sets (ASBCA No.

45664). Both contracts contained the following relevant

clauses:

10

TERMINATION FOR CONVENIENCE

OF THE GOVERNMENT

(FIXED-PRICE) (Apr 1984)

(a) The Government may terminate

performance of the work under this contract in

whole or, from time to time, in part if the

Contracting Officer determines that a termination

is in the Government's interest. The Contracting

Officer shall terminate by delivering to the

Contractor a Notice of Termination specifying the

extent of termination and the effective date.

zx**

(i) The Contractor shall have the right of

appeal, under the Disputes clause, from any

determination made by the Contracting Officer...

xx

DISPUTES (Apr 1984)

(a) The contract is subject to the Contract

Disputes Act of 1978 (41 U.S.C. 601-613).

(R4, tab 1)

In July 1990, Essex informed the Government that

it had discovered several defects in the design drawings

during the course of assembling the first article unit

(complaint at 7). On 10 July 1990, the Government

conducted a post-award conference at Essex's facility.

During the conference, appellant advised the Government

of its intention to substitute an alternate engine and

generator. At the Government's request, appellant

agreed to provide sufficient information demonstrating

that the alternate engine and generator met the “form, fit

11

and function” requirements of contract No. 0410 (ASBCA

45663, R4, tab 29).

By letter dated 8 January 1991, the contracting

officer (CO) stated that if appellant intended to use an

alternate engine and generator -- as discussed during the

10 July 1990 post-award conference -- it had to submit a

substitution proposal, including “all relevant technical and

pricing data.” The CO asserted:

2. If the contractor intends to make any

substitution of part numbers identified in notes, bill

of materials, or control drawings; the contractor

shall submit alternate items for coordination. This

requirement is specifically stated in the contract on

AFLC Form 762 page 9, Note 7.1, sentence two,

“Any substitution of parts from data package shall

be coordinated with government procurement

agency prior to installation.”

3. Installation of substitute parts without

coordination is cause for disapproval of the first

article and first article testing.... “Nonconformance

with any specified requirements or presence of one

or more deviations may constitute cause for

rejection.” Deviation as used in this context

includes all deviations from commercial parts

specified or controlled by government furnished

data.

xx

5. With specific reference to substitution of an

alternate item for Generator Set, Diesel Engine-

6KW, identified by 8324322-10 in government

furnished data, Note 2 on drawing 8324322

specifies MODEL NO 6.0 DJE-3CE/24365AE as

12

a i Dai

the proper part. If, as EEE has indicated,

Substitution for this generator is planned, then EEE

is required to identify the proposed alternate

generator set and submit a proposal, including all

relevant technical and pricing data, to verify

equivalence and compliance to requirements to

Diesel Driven Generator Set, 8324322-10. EEE's

previous attempts to provide the needed

information through DCMDC GCAB-FC (Mrs. Krist)

letter 17 Sept 90 (Atch 1) did not provide sufficient

technical information for us to determine whether

this proposed alternate generator set will be an

acceptable substitute for the specified generator

set.

6. In reflection on the development to this contract

requirement, no substitution of an alternate

generator set was intended or provided for in the

first article testing requirements. The specification

control drawing is not complete enough to meet all

of the salient characteristics of the Air Force

needs. In order to qualify any substitute generator

set, the criteria outlined in Generator Set Appendix

(ATCH #2) must be met and additional first article

tests are required.

(ASBCA 45663, R4, tab 41)

On 14 January 1991 appellant stated that it had

completed the fabrication of the first article test unit and

requested that the Government establish a date to

commence first article testing. In addition, Essex

characterized the CO's demand that the installation of the

engine in the first article test unit be qualified and

Subjected to additional tests to be n violation of both the

explicit terms of the contract and of DOD-STD-100C:

13

Based on the foregoing we request you reconsider

the statement in the Letter Para 6.... The drawings

are specification of the contract and are warranted

by the Government to be complete, accurate, and

current, and that if followed will result in an item

conforming to the contract requirements. The

attachment that you cite is not part of the contract.

The addition of ATCH #2 of the contract would

required the issuance of a contract modification.

zx

Based on the foregoing, we do not believe that

there is a unilateral uncompensated right in the

Government to refuse to accept as First Articles

and Production Units, supplies meeting contract

requirements because they are fabricated using

the Essex generator.

(ASBCA 45663, R4, tab 42)

By letter dated 25 April 1991, the CO stated he

would authorize first article testing to commence only if

Essex either 1) provided a first article test unit which

contained the exact engine suggested in the

Government's specification control drawing or 2) qualified

an alternate engine in accordance with the requirements

of the CO's letter of 8 January 1991:

1. In your 14 January 91 letter, paragraph 1, it is

“ stated that Essex Electro Engineers (Essex) had

previously informed SA-ALC that the first Article

has been completed and that Essex is ready to

schedule first article testing. That statement is not

consistent with the available information. No

written notice of a completed first article unit was

received until your letter of 12 April 1991. In view

14

a

of the discussion below, it would seem impossible

for a first article to be completed especially with the

open issues regarding your Proposed substitution

of the engine/generator set, the problems hat you

encountered regarding the mast assembly and the

issue of the compressor that you allege has

become obsolete.

2. It is noted in your correspondence and

conversations that you unequivocally ignore the

Significance of note 7.1 of the AFLC Form 762,

which is an integral part of the contract... The

intent of this note is to give the PCO the right to

review and approve any substitute parts. The

contractor is obligated to submit sufficient data to

permit a proper evaluation of the impact on unit

operation.

3. It is stated in your 14 Jan 91 letter, “Essex is

entitled and obligated to rely on the adequacy of

your Specification Control Drawing for the

procurement of an_ interchangeable part.”

However, you fail to note the following germane

and significant facts:

a) Note 7.1 of the AFLC Form 762, modifies the

drawing in that approval by the PCO is required

before a substitution can be made.

b) What you are Proposing is an engine/generator

set of your own manufacture, apparently untested

and only theoretical.

Cc) In an attempt to work with you and not

categorically deny your proposal, we have

repeatedly requested that you provide

15

supplementary information so that we could

adequately evaluate your proposed alternate.

d) You have repeatedly refused or delayed

submission of adequate data.

xx *

12. The Government is entitled and obliged to rely

upon the integrity and tenacity of those companies

and individuals with whom we contract. Your

failure to identify your proposed substitution of the

engine/generator set to the PCO prior to award or

even early in the First Article production process,

as well as your refusals to provide adequate

information and data for us to evaluate your

proposed change violates a relationship in which

the producer receives fair and reasonable

consideration and the government receives a

usable item. It is incomprehensible that a

manufacturer would insist on substituting an

untested, major component of a system and not

comply with the desires of the purchaser to

evaluate its effect on performance, especially

when the terms of the contract give that specific

right.

(ASBCA 45663, R4, tab 47)

On 6 May 1991 appellant responded by stating that

it had been prepared to commence first article testing in

January 1991. Appellant concluded by requesting a final

decision to be issued if the CO disagreed with its

interpretation of the contractual requirements:

We hereby respond to your letter dated April

25, 1991. We reject the implicit and explicit

16

EEE

SERGEY WR BR ERAN SN int

ree

As ei cali dha SE air Rc noc AM ce cmb de oe is saalntbcssuans ts cae nse tease ee

invective in your letter and the threats implicit in

that invective. We request an early meeting with

you to discuss and resolve the contract issues

discussed herein. In particular we require and

desire an immediate resolution of the

Government's use of Previously undisclosed

contract interpretations and requirements to justify

a refusal to cooperate in the conduct of

contractually required First Article tests on the

completed Essex First Article unit.

zs**

Your {] 12 is insulting and demeaning to our

Status as a reputable small business Supplier to

the Government of the United States. We are

distressed that an individual endowed with a U.S.

Government Contracting Officers [Sic] warrant

should consider it appropriate to require

performance on a matter other than by the terms

of the contract, and threaten to besmirch Essex's

integrity and tenacity because Essex would not

involuntarily accede to what you have

acknowledged were “unacceptable terms.”

It is Essex [sic] desire to provide the flood

lights at the accepted Price and in accordance with

the contract requirements. If you disagree with our

interpretation of the requirements then it is your

obligation to issue a Final Decision documenting

an ordered performance in accordance with that

interpretation. A delivery schedule does not

presently exist in the Contract. Any schedule

unilaterally mandated by you must be reasonable.

zee

| would suggest an early meeting at which

17

we may discuss this contract and how we are to

proceed.

(ASBCA 45663, R4, tab 48)

By letter dated 28 June 1991, the Termination

Contracting Officer (TCO) notified Essex that Contract-

0410 was being terminated for the convenience of the

government:

NOTICE OF TERMINATION FOR CONVENIENCE

Contract Number F41608-90-D-0410, dated 27

December 1989, and order 0001, dated 27

December 1989 are completely terminated under

contract Clause No 1-684, effective 28 June

1991... Detailed instructions follow...

Termination modifications will follow.

(ASBCA 45663, R4, tab 6) The TCO terminated

Contract-0409 for the convenience of the Government on

22 July 1991 (ASBCA 45664, tab 7).

By letter of 11 July 1991, the TCO provided

instructions to appellant regarding the preparation of the

settlement proposal under Contract-0410. The letter

provided, in relevant part:

In accordance with our telephone conversation of

10 Jul 91, enclosed are the following forms to be

used by your firm in preparation of a Settlement

Proposal on subject completely terminated

contract.

xx

Should you be considering settlement expenses,

18

Der acerca ae i a sn

FAR 31.205-42 addresses this subject. Please

maintain separate records for the directly, charged

settlement expenses, the time, type of task

performed, and employee performing the effort.

The cost must be reasonable, i.e. related to time a

person or company would expend on their own, in

the normal conduct of business, without expecting

reimbursement by another party.

zx

Please advise me no later than 2 August 91 of the

estimated amount of your proposal to facilitate the

required recommendation for release of excess

funds in accordance with FAR 49.105-2.

(Gov't mot. exh. A)

Modification P00001 for Contract-0410 and

modification P00001 for Contract-0409 confirmed the

termination of both contracts for the convenience of the

Government. The modifications were signed by the TCO

on 2 August 1991 (ASBCA 45564, R4, tab 2: ASBCA

45663, R4, tab 7)

Essex proffered its submission under Contract-

0410 on 26 June 1992 in which it requested payment of

$635,434. The submission stated in part:

In accordance with the Contract Disputes Act and

FAR § 49.114, as well as the termination of the

referenced Contract allegedly for the convenience

of the Government on June 28, 1991, enclosed

you will find our Claim, certified as required by the

Act. The enclosure includes Claims for changes

including the Government-caused first article

delays and production disruption, as well as the

19

Government's breach by its wrongful termination in

bad faith, totaling $635,434, after crediting prior

progress payments. In accordance with the cited

Regulation, the enclosure encompasses the

previous demands for final decisions submitted by

Essex on May 6, 1991, with respect to disputes

regarding specification control drawings and

deficient Government technical data on which

interest has been accruing since that date.

zx*

In accordance with the Contract Disputes Act, we

hereby certify that the enclosed claim is made in

good faith, that supporting data is accurate and

complete to the best of our knowledge and belief,

and that the amount requested accurately reflects

the contract adjustment for which Essex Electro

Engineers, Inc., believes the Government is liable.

In addition, consistent with the current state of

decisions, negotiation of this claim is abandoned,

a final decision is hereby demanded, the net

payment claimed is a sum certain, and, although

we will consider accepting a reasonable and timely

payment by you of the amount due in order to

resolve this matter, we insist upon the time

requirements of the Contract Disputes Act for a

response to this claim.

The proposal was signed by Frank J. Pawlowski, Essex's

president (ASBCA 45663, R4, tab 52).

By letter of 1 July 1992, the TCO responded to

Essex's submission under Contract-0410, stating in

relevant part:

Reference your 26 June 1992 subrfittal in

20

)

:

-

:

response to the termination of the subject contract.

It has been noted that in your cover letter

Submitting subject termination settlement proposal.

you certified the proposal as a claim.

Please be advised that under the Contract

Disputes Act of 1978, “a voucher, invoice, or other

routine request for payment that is not in dispute

when submitted is not a claim for the purpose of

the Act.” In Mayfair Construction Company v.

United States, 841 F.2d 1576 (Fed.Cir. 1988), the

Court held that a termination settlement proposal

was not a claim under the Contract Disputes Act,

and could not be converted into a claim by the

contractor's certification. The Court's reasoning

was that at the time of the proposal submission the

parties were still in a “pre-dispute negotiation

Posture.” In the absence of a dispute, the Court

held that the contractor was not entitled to interest.

Further, per FAR 49.112-2(d), Interest, “The

Government shall not Pay interest on the amount

due under a settlement or a settlement by

determination.” See also DA WCO Construction,

Inc. v. United States, 930 F.2d 872 (Fed.Cir.

1991).

In accordance with the above, your submission

cannot be considered a claim within the meaning

of the Contract Disputes Act. | have every reason

to believe that we will be able to reach a mutual

settlement through negotiations.

ek *

Your current proposal is being processed normally,

i.€., plant clearance has been requested

21

(approximate turn around time-six months) and a

DCAA Audit has been requested in accordance

with FAR 49.107. As questions arise regarding

items in your proposal, you will be contacted. After

all termination reviews and plant clearance have

been completed, negotiations can begin to resolve

your termination settlement proposal.

To date, no discussions subsequent to the initial

conference have taken place on this contract.

Since a settlement has never been discussed,

there is nothing to indicate this cannot be

negotiated, nor is this matter considered to be at

an impasse.

(Gov't mot., exh. B)

Essex proffered its submission under Contract-

0409 on 22 July 1992 in which it requested payment of

$20,603. It stated, in pertinent part, as follows:

In accordance with the Contract Disputes Act and

FAR § 49.114, as well as the termination of the

referenced Contract allegedly for the convenience

of the Government, effective August 12, 1991,

enclosed you will find Essex's Claim, which does

not require the certification under the Act because

it is less than $50,000. The enclosed Claim for

$20,603, involves the unamortized costs and profit

associated with the spare parts (CLIN 0002) and

the provisioning data (CLIN 0004) and post-

termination expenses.

In accordance with the Contract Disputes Act, the

enclosed Claim is submitted to you for a final

decision. IN addition, consistent with the current

22

State of decisions, negotiation of this claim is

abandoned, a final decision is hereby demanded,

the net payment claimed is a Sum certain, and,

although we will consider accepting a reasonable

and timely payment by you of the amount due in

order to resolve this matter, we insist upon the

time requirements of the Contract Disputes Act for

@ response to this claim. Further, if you consider

the enclosure to be a routine invoice or voucher

and not a claim, we demand payment within thirty

days or interest will accrue in accordance with the

Prompt Payment Act.

(ASBCA 45664, R4, tab 8)

By letter of 21 August 1991, the TCO responded to

appellant's proposal under Contract-0409, Stating:

It is noted that your 22 July 1992 submission of

your termination settlement proposal is certified as

a claim. It is also noted that this is your first

Submission as a result of the termination. No

reviews have been done previously regarding the

facts or amount contained therein. in addition, you

refer to the contract number as F41608-90-D-

0409.

Please be advised that under the Contract

Disputes Act of 1978, “a voucher, invoice, or other

routine request for payment that is not in dispute

when submitted is not a claim for th purpose of the

Act.” In Mayfair Construction Company v. United

States, 841 F.2d 1576 (Fed.Cir. 1988), the Court

held that a termination settlement proposal was not

a Claim under the Contract Disputes Act, and could

not be converted into a claim by the contractor's

23

certification. The Court's reasoning was that at the

time of the proposal submission the parties were

still in a “pre-dispute negotiation posture.” In the

absence of a dispute, the Court held that the

contractor was not entitled to interest. Further, per

FAR 49.112-2(d), Interest, “The Government shall

not pay interest on the amount due under a

settlement or a settlement by determination.”

In accordance with the above, | do not recognize

your certified submission as a claim within the

meaning of the Contract Disputes Act. | have

every reason to believe that we will be able to

reach a mutual settlement through negotiations.

xx*t

| consider contract F41608-90-D-0410/0001 and

contract F41608-90-C-0409 separate contracts.

They were awarded separately and | am treating

them separately. Since they are separate, please

submit separate documentation to support the

proposal for contract F41608-90-0409 so that

proper consideration can be given to that proposal.

xx*

Your Termination Settlement Proposal is being

process through normal channels. Plant clearance

and DCAA Audit have been requested. Once |

have received the requested reports, | will be

ready to open negotiations to settle this matter.

(ASBCA 45664, R4, tab 9)

By letter dated 16 September 1992, referencing

both Contract-0410 and Contract-0409, Essex, by its

attorney, contended:

24

Your letter of August 21, 1992. to our client,

Essex Electro Engineers, Inc.. regarding “Contract

F41608-90-C-0409”, indicates a certain amount of

confusion apparently attributable to your opinion

that Contract-0409 is somehow separable from the

above referenced Contract-0410. Regardless of

the manner in which you may choose to process

the claims submitted on the contracts, your opinion

fails to recognize that two contract numbers exist

only because the Government elected to create

two documents covering the requirements of a

Single solicitation, F41608-89-R-4743, and

Contract-0409 explicitly refers to its companion

Contract-0410. Also, your reference to “separate

documentation” was submitted on June 26, 1992,

and on July 22, 1992, of the “amount Claimed” for

each contract number on the forms and with the

certification on the forms prescribed by the TCO.

[See, FAR § 52.249-2(d).]

z**

Also, your reference to a certification of the claim

dated July 22, 1992. for Contract-0409 is not

understood since a CDA certification of the claim

was not provided and is not required because it

does not exceed $50,000. The claim dated June

26, 1992, for Contract-0410 included the

necessary CDA certification because it exceeds

$50,000.

Your letter disputes Essex's Claims and

Statutory right to interest and references Mayfair

Construction Company v. United States, 841 F.2d

1576 (Fed.Cir. 1988) and FAR § 49.112-2(d). As

you must know from a review of Mayfair, that

decision rested on an interim “Disputes”

25

Regulation which is not applicable here, and did

not address the specific requirements of the CDA

as requiring a “Dispute” before a “Claim” could

exist. The only evidence that could exist for your

apparent contention that each claim here is “a

voucher, invoice, or other routine request for

payment” that is not disputed would be your

immediate payment of the full amount of each

claim.

More recent decisions since Mayfair, Dawco

Construction Co., Inc. v. United States, 930 F.2d

872 (Fed.Cir. 1991), and Essex Electro Engineers,

Inc. v. United States, 960 F.2d 1576 (Fed.Cir.

1992), cert. pending, regrettably also contradict the

CDA and its legislative history as well as other

precedents in holding that all negotiations between

the parties must be abandoned in order for a claim

to exist. As noted in the claims for Contract-0409,

Essex has unqualifiedly abandoned negotiations

and demanded a final decision. We reject.your

premise that the Government may dictate when a

claim exists by the expedient of choosing when, if

ever, to characterize the matter as being “in

dispute.”

In addition, even if your reference to an

agency regulation, FAR § 49.112-2, was applicable

to this situation where negotiations have been

abandoned, that regulation has not force or effect

since it directly contradicts the CDA and its

legislative history. The executive agencies lack

the legislative authority to withhold a statutory right

enacted by Congress.

Accordingly, your dispute of the claims and

26

a

the statutory right to interest is unavailing. Further,

your stated belief that “we will be able to reach a

mutual _ settlement through _ negotiations”

unfortunately cannot occur because, in order to

preserve Essex's rights, Essex has been forced by

the foregoing decision to abandon all negotiations

and proceed in accordance with the law.

zee

Your agency has a track record; i.e.,

Contract N00140-85-C-1436 and DAAE07-87-C-

2665, of delays for years before any effort is made

to resolve terminations for convenience while the

contractor is left with financing the Government's

debt. We have no intention of allowing that record

to re-occur. While you have already failed to take

prompt action to resoive the claims as required by

FAR § 49.101(d) and the CDA and you have

disputed the claims, the right to interest and the

inclusion of the description of the “Target-Essex

Strategy”, there are some legal precedents, again

contradicting the CDA and its legislative history,

indicating a need for a resubmission of termination

claims in order for them to be considered claims.

Also, your letter cannot be reconciled with the CDA

unless it is simply a request for additional time as

Provided in the Act.

Consequently, taking your letter as a

request for additional time to resolve the claim and

in order to preserve Essex's rights in the event that

a forum might conclude that the existence of a

Claim depends upon a resubmission, enclosed is a

copy of the claim of June 26, 1992, for contract-

0410 with a renewed certification in accordance

with the language in the Contract Disputes Act. A

27

resubmission of the claim for Contract-0409 of July

22, 1992, will be made if no resolution has

occurred within the time required by the CDA.

This resubmission is made solely for the

purpose of preserving Essex's right and in no way

constitutes a waiver of the existence of the valid

and lawful claim submitted on June 26, 1992, and

on which interest is accruing from the receipt of

that claim to the date of payment of the amount

due. Further, this resubmission is not an offer to

negotiate nor to do other than proceed with the

formal claims process under the Contract Disputes

Act.

(ASBCA 45664, R4, tab 10)

By letter dated 2 October 1992, Essex resubmitted

its “claim” under Contract-0409. It stated:

As discussed in our letter of September 16,

1992, and subject to the same terms and

conditions stated therein, enclosed is_ the

resubmission of the subject claim.

(ASBCA 45664, R4, tab 11)

Appellant filed two notices of appeal on 27 January

1993. The Board docketed the appeal under Contract-

0410 as ASBCA No. 45663 and the appeal under

Contract-0409 as ASBCA No. 45664.

The Government attached the affidavit of DCAA

auditor Howard M. Salita to its 16 September 1993

Response to appellant's opposition. The affidavit stated,

in pertinent part:

28

iene ei tapas nar ct cea cee eee ee

The DCAA was not dilatory in its efforts to audit

Appellant's proposals. In fact the reverse is true.

The contractor was dilatory in its efforts to provide

the Government substantiation for many of the

questions raised during the audit. Essex has

caused a considerable delay in, and prolonged the

auditing process of its own proposals.

| must first point out that Appellant's

termination settlement proposals are not routine

termination settlement proposals. Most routine

settlement proposals require the audit of only one

contract. Under Contract 1410 Essex actually had

three audits built into one proposal.

The auditor concluded his affidavit by stating: “[T]he lack

of response and cooperation by Essex during our audit

efforts significantly impacted the time needed to complete

these audits.” (Gov't. resp., exh. A) 1/

On 31 September 1993, appellant filed a motion to

Strike the Government's “Response,” stating that the

“Governments 'Response’...boils down to nothing more

than a position that Essex may not pursue a resolution

here because the Government has refused to undertake

any action to resolve the claim and thus has avoided

giving voice to a ‘dispute’ and because the Government

issued multiple terminations which allegedly ‘overloaded’

its ‘audit' employee.” (App. mot. to strike at 2).

DECISION

It is axiomatic that “[aJll claims by a contractor

against the Government relating to a contract shall be in

writing and submitted to the contracting officer for a

decision.” (41 U.S.C. § 605(a)) Another prerequisite for

29

a Claim is that the parties must be involved in an existing

dispute. Dawco Construction Inc. v. United States, 930

F.2d 872 (Fed.Cir. 1991). In addition, if the contractor's

claim for money exceeds $50,000, it must be properly

certified. W.M. Schlosser Co. v. United States, 705 F.2d

1336 (Fed.Cir. 1983). Finally, a contractor must submit,

in writing, a “clear and unequivocal statement that gives

the contracting officer adequate notice of the basis and

amount of the claim.” Contract Cleaning Maintenance,

Inc. v. United States, 811 F.2d 586, 592 (Fed.Cir. 1987).

Appellant contends that both its 26 June 1992 and

22 July 1992 submissions are proper CDA claims in that

they: 1) expressly stated they were claims; 2) contained

the required certification language (when necessary); and

3) demanded the TCO's final decision. The Government

disagrees, arguing that Essex's submissions were merely

routine termination for convenience settlement proposals.

It also contends that since there was no dispute prior to

the submission of the proposals, they do not qualify as

claims under the CDA.

Under Dawco, supra., a cost proposal is not a

claim unless the parties are already in dispute over the

amount requested when the proposal is submitted.

Reflectone, Inc., ASBCA No. 43081, 93-1 BCA ¥ 25,512.

Furthermore, “[a] dispute cannot be manufactured and

interest cannot be made applicable by the mere assertion

that a submission is a claim.” Essex Electro Engineers,

Inc., ASBCA No. 46202 (decided 20 December 1994),

citing CPI Corp. v. United States, 25 Ci.Ct. 451, 455

(1992). It is also well-settled that a termination for

convenience proposal is ordinarily not considered a claim

when submitted. Mayfair Construction Company, ASBCA

No. 30800, 87-1 BCA 4 19,542, affd, Mayfair

Construction Company v. United States, 841 F.2d 1576

30

————

(Fed.Cir.), cert. denied, 488 US. 980 (1988).

Accordingly, appellant's submissions of 26 June 1992 and

22 July 1992 were merely the first Step in the opening of

negotiations. Reflectone, supra.; Electrodynamics,

ASBCA No. 43224, 93-1 BCA § 25,303: Hugo Auchter

GmbH, ASBCA No. 33123, 88-3 BCA {] 20,926. 2/

We find nothing in the record to establish the

existence of a certified dispute contemporaneous with the

submission of the 26 June 1992 or the 22 July 1992

settlement proposals. Therefore, neither of these

Submissions constituted a claim. Moreover, as the

Submissions were not claims, the requirement that a final

decision be issued within 60 days under the CDA did not

apply.

The events following Essex's 26 June 1992 and 22

July 1992 submissions present the issue in a different

light. Appellant's resubmissions (dated 16 September

1992 and 2 October 1992, respectively) did in fact invoke

the CDA, purported to “resubmit the termination claims,”

and- asserted that an appeal would be filed if a final

decision or other resolution was not forthcoming in 60

days. We recently faced a similar situation in Essex

Electro Engineers, Inc., ASBCA No. 46202 (slip op. 20

December 1993), where the Board held that no claim

existed because there was no underlying dispute.

It is now well-settled that when the parties are ina

pre-dispute negotiation posture, a_ contractor's

resubmissions will not be considered claims even though

he has invoked the CDA and has characterized his

submissions as claims. See Mayfair, supra. at 1577; CP/

Corp., supra. at 455. Here, the correspondence between

the parties did not rise to the level of a pre-dispute,

negotiation posture. The TCO's correspondence of 1 July

re |

en

1992 and 21 August 1992 served only to clarify to Essex

the process guiding the terminations for convenience and

to put it on notice that neither of its submissions was

considered a claim under the CDA. At best, the TCO

seemed overly optimistic that the parties would reach a

“mutual settlement through negotiations” once he had

received the requested “plant clearance” and “DCAA

audit” reports. Thus, we find that there was no “objective

manifestation” by the TCO that appellant's “claims” could

not be settled or that an “impasse” had been reached in

the negotiation process by failing to agree upon the

amount of a termination settlement as provided in the

Termination for Convenience clause. See R.G. Robbins

Co., ASBCA No. 26251, 82-1 BCA ¥ 15,643; Saco

Defense, Inc., ASBCA Nos. 44792, 45171, 93-3 BCA J

26,029.

When a contractor submits a certified claim in

excess of $50,000, the contracting officer, within 60 days

of receipt of the claim, must either issue a decision or

inform the contractor when a decision will be issued. 41

U-S.C. § 605(c)(2). If the contracting officer fails to

respond within 60 days, the contractor may appeal the

claim to the board of contract appeals based upon the

rationale that the Government has failed to act within a

“reasonable time.” 41 U.S.C. § 605(c)(3) and (5).

However, if the contracting officer does not

possess the requisite information, then he is not obliged

to render a decision. See Gauntt Construction Co.,

ASBCA No. 33323, 87-3 BCA ¥] 20,221. “Without such

information the contracting officer would be precluded

from making a meaningful review of the claim and thus be

unable to make the requested determination.” Logus

Manufacturing Co., ASBCA No. 26436, 82-2 BCA

16,025 at 79,416. To require the contracting officer to

32

render a decision on the basis of inadequate information

would amount to “an exercise in futility.” Logus, supra. \n

Such a situation, we would lack jurisdiction to consider the

purported appeal. J. J. Bonavire Co., ASBCA No. 29846,

86-2 BCA J 18,788.

It is not unreasonable for a TCO, in accordance

with standard procedures governing Termination

Settlement Proposals, to request a plant clearance and a

DCAA audit (as mandated by FAR 49.107) when

reviewing proposed settlement costs See generally,

Swiss Products, inc., ASBCA No. 40031, 93-3 BCA 7q

26,163; R.G. Robbins, supra. Here, the TCO apprised

Essex of this procedure and further indicated a

willingness to “open negotiations and settle this matter’

once he had received the reports.

It is not unreasonable to assume that a contractor

would provide full cooperation during the course of an

audit in order to settle its costs. Here, the auditor's

affidavit states the contrary. In fact, according to the

auditor, the time consumed by these audits was

attributable to Essex, not to the Government: “[T]he lack

of response and cooperation by Essex during our audit

efforts significantly impacted the time needed to complete

these audits.” (Emphasis added) In light of the affidavit,

unrebutted by appellant, and the surrounding

circumstances, we find that the contracting officer's failure

to render a final decision was reasonable.

Appellant also contends that the submissions

constituted claims for interest under the CDA. It is

axiomatic, however, that a request for CDA interest

cannot exist without an underlying claim under the Act.

CPT Corp., supra at 455, quoting Mayfair, supra at 1578:

Nab-Lord Associates v. United States, 682 F.2d 940, 943-

33

44, 230 Ct.Cl. 694 (1982). “Interest is...an adjunct to an

underlying claim with respect to the principal liability. By

terms of the [CDA], no interest arises absent some other

claim.” Essex, supra at 766. Because appellant's

termination for convenience settlement proposals were

not proper CDA claims, Essex is not entitled to interest

under the Act's provisions.

We find it unnecessary to address appellant's

contentions that such decisions as Mayfair, supra; Dawco,

supra, and Essex, supra, are a contradiction of the CDA

and its legislative history in holding that all negotiations

between the parties must be abandoned in order for a

claim to exist. These contentions were presented

verbatim previously by appellant (Gov't. resp., exh. B) and

were rejected by the Claims Court in 1991 (Essex Electro

Engineers, Inc. v. United States, 22 Cl.Ct. 757 (1991))

and later on appeal by the Federal Circuit in 1992 (Essex

Electro Engineers Inc., v. United States, 960 F.2d 1576

(Fed.Cir. 1992)). this Board, of course, is obliged to

follow the precedents of the Federal Circuit.

CONCLUSION

The Government's motion to dismiss for lack of

jurisdiction is granted, and the appeals are dismissed

without prejudice to the submission of proper claims to the

contracting officer.

NOTES

1. We deny Essex's motion to. strike the

Government's response.

2. Essex also contends that its demand of 6 May

34

———aoOeeeee aaa. 2.2.2.2.2.2.2.Q__

1991 for a CO's decision demonstrated that the

parties were in dispute prior to its 26 June 1992 or

22 July 1992 submissions. However. upon review

of the record, we do not view appellant's 6 May

1991 demand as a proper CDA submission.

Absent were the “clear and unequivocal

Statements that gives the contracting officer

adequate notice of the basis and amount of the

Claim." Contract Cleaning, supra. at 592. Essex

merely stated that if the CO disagreed with its

interpretation of the requirements of the contract,

then it was the CO's “obligation to issue a Final

Decision documenting an ordered performance in

accordance with that interpretation.”

35

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Petition for Writ of Certiorari — Essex Electro Engineers, Inc. v. Widnall · 522 U.S. 916 | Frix