Appendix — City of Vernon v. Southern California Edison Co.

Supreme Court brief1992

Ask Donna

What actually matters in this document.

Text

FILED

JUL 20 1992

OFHGE OF THE €LESK

In the Supreme Court

OF THE

United States

OCTOBER TERM 1992

CiTy OF VERNON,

Petitioner.

VS.

SOUTHERN CALIFORNIA EDISON COMPANY,

Respondent.

APPENDIX TO

PETITION FOR A WRIT OF CERTIORARI

TO THE UNITED STATES COURT OF APPEALS

FOR THE NINTH CIRCUIT

HUFSTEDLER, KAUS & ETTINGER

SHIRLEY M. HUFSTEDLER

355 S. Grand Avenue

Thirty-Ninth Floor

Los Angeles, California

90071-3101

Telephone: (213) 617-7070

& WALKER

Twenty-Third Floor

GOLDBERG, FIELDMAN

& LETHAM, P.C.

Davipb C. HJELMFELT, P.C.

CHANNING D. STROTHER, JR.

110 Fifteenth Street, N.W.

Washington, D.C. 20005

Telephone: (202) 46344800

Attorneys for Petitioner

PAUL, HASTINGS, JANOFSKY

555 South Flower Street

Los Angeles, California 90071

Telephone: (213) 683-6223

Bowne of Los Angeles, Inc., Law Printers (213) 627-2200

l

APPENDIX

No. 90-5628 1

FOR PUBLICATION

UNITED STATES COURT OF APPEALS

FOR THE NINTH CIRCUIT

CITY OF VERNON,

Plaintiff-Appellant,

V.

SOUTHERN CALIFORNIA EDISON COMPANY,

Defendant-Appellee.

Appeal from the United States District Court

for the Central District of California

Maniana R. Pfaelzer, District Judge, Presiding

Argued and Submitted

October 11, 1991 — Pasadena, California

Filed February 7, 1992

Before: Mary M. Schroeder, Edward Leavy and

Ferdinand F. Fernandez, Circuit Judges.

Opinion by Judge Fernandez D.C. No. CV-83-8137-MRP

OPINION

SUMMARY

Antitrust

Affirming in part, reversing in part and remanding a district

court grant of summary judgment, the court of appeals held that a

public utility did not engage in anticompetitive conduct by deny-

ing a city access to power transmission lines or engaging in a

group boycott that prevented the city from obtaining bulk power

from other suppliers.

Appellant City of Vernon received electric power from South-

ern California Edison Company and other electrical utilities over

Edison’s transmission lines. It was Edison’s responsibility to see

that Vernon received all of the power it needed. Most of Edison’s

5

conduct with respect to Vernon was regulated by the FERC,

including the wholesale rates Edison charged, the terms of inte-

gration agreements, and transmission rights on Edison’s high

voltage lines. Vernon brought an action against Edison alleging

that Edison had engaged in anticompetitive conduct by denying

Vernon access to power transmission lines, filing discriminatory

rate schedules, and engaging in a group boycott that prevented

Vernon from obtaining bulk power from other suppliers. Vernon

sought damages and injuntive relief on each of its claims. The

district court granted summary judgment for Edison, and denied

reconsideration of its decision.

[1] Vernon did not appear to dispute the fact that retail

customers would pay increased rates if it received the access

sought. Nor did Vernon appear to dispute the fact that Edison

was legitimately concerned about the retail rates in making its

facilities access decisions. [2] Thus, the district court did not err

in granting summary judgment against Vernon on its relative size

share access claim. Vernon failed to show just why Edison was

required to cease using its own facility so that Vernon could begin

using it. This was not a case where Edison simply refused to

supply Vernon with its power needs. The demand that Edison

turn over its facility to a city simply because the city could save

money by obtaining cheaper power stands the essential facility

doctrine on its head. [3] In addition, Vernon cited no authority in

support of its theory that “reasonably” access to Edison’s facilities

must take the form of relative size share access.

[4] Although the integrated operations agreement was one way

in which Edison could meet its obligation to provide reasonable

access to its essential facilities, the district court held that to the

extent that Edison had a duty to integrate Vernon’s power

purchases, the duty was limited by legitimate business justifica-

tions. Edison offered none. [5] Had that determination been

made at the end of a trial, there would not be error, summary

judgment was another matter entirely. [6] Even though Edison

had a duty to integrate capacity resources on reasonable notice,

there was nothing to suggest that Edison was required to do so

through the speciai condition 12 claim. Thus, summary judgment

on this claim was appropriate.

Le ne oar

3

[7] The court noted that the contractual nght to interrupt

service did not grant Edison the freedom to act anticompetitively.

[8] Nonetheless, summary judgment was appropriate on this

claim. There was no evidence that transmission was interrupted at

any time at the behest of any person employed by Edison other

than a dispatcher, who was acting as he did for unknown reasons.

There was no evidence that any person with management or

supervisory authority ever told any dispatchers to interrupt or to

refuse transmissions for any anticompetitive reason or that dis-

patchers were acting on a policy of wrongfully refusing or inter-

rupting transmission. Summary judgment on this claim was

appropniate. [9] Nor was any evidence introduced by Vernon that

Edison conspired with anyone to deny access to the Pacific

Intertie. Because the Sherman Act requires “concerted action”

by more than one entity, the district court properly granted

judgment on this claim. [10] Concerning Vernon’s Edison-

Nevada Power boycott claims, the court agreed that Vernon’s

evidence was far too weak. There was no evidence that unnamed

Edison dispatchers entered into conspiracies with Nevada Power

dispatchers to boycott Vernon’s attempt to purchase power.

[11] The court agreed with the district court that the serious

flaws in the only damage study that could be proffered to the jury

placed Vernon in the position of having no proper proof of

damages at all. Thus, the district court did not err when it

awarded summary judgment based upon his lack of evidence.

[12] However, the court reversed the denial of injunctive relief as

to the integrated operations agreement and remanded to the

district court for consideration of the propriety of such relief if

Edison unreasonably refused access to its essential facilities.

COUNSEL

Shirley M. Hufstedler, Hufstedler, Kaus & Ettinger, Los Angeles,

California, for the plaintiff-appellant.

Paul G. Bower, Gibson, Dunn & Crutcher, Los Angeles, Califor-

nia, for the defendant-appellee.

r

4

OPINION

FERNANDEZ, Circuit Judge:

The City of Vernon (“Vernon”) brought this action against

Southern California Edison Company (“Edison”) and alleged

that Edison had engaged in anticompetitive conduct by denying

Vernon access to power transmission lines, by filing discrimina-

tory rate schedules, and by engaging in a group boycott that

prevented Vernon from obtaining bulk power from other suppli-

ers. Vernon sought damages and injunctive relief on each of its

claims. The district court granted summary judgment in favor of

Edison. Vernon appeals. We affirm in part and reverse in part.

BACKGROUND

Edison is an investor-owned fully integrated public utility,

which generates, transmits, and distributes electric power within

its service area, an area which includes much of Central and

Southern California. Vernon is located in Edison’s service area,

but it has its own electric distribution system, and is the sole

provider of retail electric service within its own boundaries.

Vernon is bounded by Edison territory and by the City of Los

Angeles, which also has its own service territory operated by the

Los Angeles Department of Water and Power.

Although Vernon distributes power at retail within its bounda-

ries, it generates a very small portion of its own electricity. Thus,

it obtains most of its power in bulk elsewhere and receives it over

Edison’s transmission lines. That wholesale power is purchased

from Edison or from other electrical utilities. It is Edison’s

responsibility to see to it that Vernon receives all of the power

that it needs. Edison also purchases power from and sells it to

other utilities.

Vernon and Edison have a long history of disputes over rates,

access to Edison’s transmission facilities, and the integration of

non-Edison power-sources into Edison’s operating system for the

5

benefit of Vernon.' Most of Edison’s conduct with respect to

Vernon is regulated by the Federal Energy Regulatory Commis-

sion (FERC), including the wholesale rates Edison charges, the

terms of integration agreements, and transmission rights on

Edison’s high voltage lines.’

Vernon’s denial of access claims (sometimes called foreclosure

claims) are based upon Edison’s refusal to provide relative size

share® access to its transmission lines, particularly the Pacific

Intertie* and lines from the desert Southwest. Vernon also claims

entitlement to what the district court characterized as “unlim-

ited”’ access to Edison’s 220 kV network.°

‘Integration of non-Edison power sources requires Edison to transmit

power obtained from other sources while giving credit to the wholesale

customer which obtained the outside power capacity credit because

Edison need not maintain as much power generation capacity if power

can be imported.

*The FERC regulates Edison’s conduct pursuant to the Federal Power

Act. 16 U.S.C. § 824.

“Relative size share” simply refers to Vernon’s theory that if it uses,

for example, 1.5% of the electricity transmitted into the Edison territory

then it should receive 1.5% of the firm transmission access to the EHV

(Extra High Voltage) transmission lines. While Vernon’s damage study

based damages on an assumption that it was entitled to relative size

share access, Vernon claims that it should receive a “fair share” and

Edison has failed to propose any other way of calculating Vernon’s fair

share.

“The Pacific Intertie is a group of high-power transmission lines which

bring hydroelectric power to Edison’s control area from the Pacific

Northwest. Edison shares ownership in the Pacific Intertie with several

other utilities, so that it is entitled to only a portion of the lines’ total

capacity. The lines consist of two 500 kV AC lines, and one 800 kV DC

line.

*The 220 kV network is the local transmission net work through which

Edison transmits energy directly to its retail and wholesale customers.

Vernon’s claim is that its access should be unlimited unless there is

insufficient capacity to meet the total demand. In that case, Vernon

contends that “the constraint on the system should be shared.”

r

6

Vernon claims that Edison has refused to enter into reasonable

agreements to integrate Vernon's firm purchases from other

sources. These claims involve a generic Integrated Operations

Agreement (IOA) and Special Condition 12 (SC-12). The IOA

which Edison submitted to Vernon provided that outside power

resources could be integrated into Edison’s service system on such

terms and at such time as Edison deemed appropnate. The FERC

determined that parts of the IOA, including the absence of a

reasonable notice provision, were unreasonable. Southern Cal.

Edison Co., 41 F.E.R.C. 961,188 at 61,493-94 (1987) and

Southern Cal. Edison Co., 52 F.E.R.C. 961,299 at 62,202-03

(1990), vacated in part, 55 F.E.R.C. J 61,258 (1991). SC-12 was

entered into as a partial settlement of Vernon’s claims that Edison

was unreasonably denying integration and access. SC-12 permits

Vernon to import and obtain capacity credit for outside resources

without integration pursuant to an IOA.

Vernon also asserts that Edison acted anticompetitively in

interrupting or refusing transmission from Nevada Power Com-

pany (Nevada Power) to Vernon. It also claims that Edison and

Nevada Power engaged in a group boycott designed to keep

Vernon from purchasing power from Nevada Power. Vernon and

Edison entered into a contract for interruptible transmission

service under which Vernon could purchase power from outside

supplier on a non-firm basis. That power would then be transmit-

ted over Edison lines. The contract provided for interruption by

Edison at any time and for any reason.

The parties brought several motions for summary judgment,

including those which ultimately resulted in judgment for Edison

on all claims. The district court granted summary judgment on

the foreclosure claims on several grounds. As to Vernon’s claim

that it was entitled to relative size share access, the district court

determined that Edison had established a legitimate business

reason for its refusal to provide the requested access, which

Vernon had failed to refute. Summary judgment on the integra-

tion claims was granted on the ground that Edison had shown a

legitimate business justification for not providing for integration

on eighteen months’ notice. The court granted summary judg-

ment on the SC-12 claims because Edison had no obligation to

7

offer SC-12 and its failure to offer it sooner was not an antitrust

violation. The court granted summary judgment on the inter-

ruptible transmission service claims because Vernon had not

quantified damages. The court viewed that claim as arising from a

contractual dispute, and found no material issue of fact regarding

whether Edison’s reasons for interruptir 2 were legitimate.

The district court also granted Edison’s motion for summary

judgment on its claims that Edison had discriminated against

Vernon in its rates® and on the claim that Edison and Nevada

Power engaged in a group boycott against Vernon. The court

concluded that summary judgment was appropriate because

Vernon had presented no evidence of damages and Vernon had

failed to introduce evidence sufficient to sustain a finding of

concerted action. Eventually, the court determined that judgment

was appropnate on all of Vernon’s claims, including a claim that

Edison had conspired with others to deny access to the Pacific

Intertie. Vernon asked the district court to compel Edison to bring

a motion for summary judgment on the latter claim, but the

district court declined to require the filing of a separate motion.

After entry of judgment, Vernon filed a timely motion for

reconsideration. The district court declined to reconsider its

decision.’ Vernon filed a timely notice of appeal.

JURISDICTION AND STANDARD OF REVIEW

The district court had jurisdiction under 15 U.S.C. §§15 and

26. We have jurisdiction under 28 U.S.C. § 1291.

We review a grant of summary judgment de novo. Jmage

Technical Serv., Inc. V. Eastman Kodak Co., 903 F.2d 612. 614

(9th Cir. 1990), cert. granted, 111 S. Ct. 2823, 115 L. Ed. 2d 994

*Vernon has not appealed the district court’s grant of summary

judgment on its rate claim.

’Though Vernon appealed from the denial of its motion for reconsid-

eration, it presented no argument on appeal that the district court

abused its discretion in denying the motion. In any event, we find no

abuse of discretion because Vernon should have been able to present

evidence of pretext, if any, at the original summary judgment hearings.

8

(1991). We must determine, viewing the evidence in the light

most favorable to the nonmoving party, whether there are any

genuine issues of material fact and whether the district court

correctly applied the relevant substantive law. /d.

Summary judgment is appropmiate if the nonmoving party bears

the ultimate burden of proof at trial as to an element essential to

its case, and fails to make a showing sufficient to establish a

genuine dispute of fact with respect to the existence of that

element. Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S. Ct.

2548, 2552, 91 L. Ed. 2d 265 (1986).

DISCUSSION

To establish a violation of Section 2 of the Sherman Act, 15

U.S.C. § 2(§ 2), Vernon would have to show (1) that Edison

possessed monopoly power in the relevant market; (2) that it

willfully acquired or maintained that power, and (3) that Vernon

suffered a causal antitrust injury. Oahu Gas Serv., Inv. v. Pacific

Resources, Inc., 838 F.2d 360, 363 (9th Cir.), cert. denied, 488

U.S. 870, 109 S.Ct. 180, 102 L. Ed. 2d 149 (1988). An attempt to

monopolize is also actionable under § 2. Attempted monopoliza-

tion has three elements: “specific intent to monopolize, predatory

or anticompetitive conduct and a dangerous probability of suc-

cess.”” Drinkwine v. Federated Publications, Inc., 780 F.2d 735,

740 (9th Cir. 1985), cert. denied, 475 U.S. 1087, 106 S. Ct. 1471,

89 L. Ed. 2d 727 (1986). Vernon would also be required to show

causal antitrust injury in an attempted monopoly case. California

Computer Products, Inc. v. IBM Corp., 613 F.2d 727, 736 (9th

Cir. 1979).

To establish a violation of Section | of the Sherman Act, 15

U.S.C. § 1 (§ 1), Vernon would have to prove “three elements:

(1) an agreement or conspiracy among two or more persons or

distinct business entities: (2) by which the persons or entities

intend to harm or restrain competition; and (3) which actually

restrains competition.” Morgan, Strand, Wheeler & Biggs v.

Radiology, Ltd., 924 F.2d 1484, 1488 (9th Cir. 1991) (citation

and quotations omitted).

acne iesiniieieriaae tee neniiinlieiiiel

A. Essential Facility Claims.

Vernon’s foreciosure claims are based on its assertion that the

EHV transmission lines, such as the Pacific Intertie and the

Southwest lines, as well as the 220 kV grid, are essential facilities

to which Edison has improperly refused Vernon access. In our

opinion in the companion to this case, City of Anaheim vy.

Southern California Edison Co., No. 90-56375, slip op. 1221 (9th

Cir. 1991), filed on the same date as this opinion, we have

outlined the nature of the essential facility doctrine and the

elements necessary to prove liability for the refusal to allow use if

an essential facility. Jd. at slip op. 1233-36. See also Alaska

Airlines, Inc. v. United Airlines, Inc., No. 90-55162, slip op.

14751, 14762-68 (9th Cir. Oct. 29, 1991). Of course, that same

law applies here. |

However, in this case the district court assumed for purposes of

the summary judgment motion “that there was competition

between Edison and Vernon, that Edison had monopoly power in

a properly defined market, and that Edison’s transmission lines

are essential facilities.” Therefore, we will only determine

whether given those assumptions Edison has committed an anti-

trust violation by refusing to give all of the access to the facilities

that Vernon desires.®

1. Relative Size Share Access.

The district court determined that there were no genuine issues

of material fact with respect to Edison’s claim that it had a

legitimate business justification for refusing relative size share

access. Vernon asserted that Edison’s business justification was

insufficient as a matter of law, but also asserted that the alleged

justification was untrue. However, as noted by the district court,

Vernon did not point to any facts in opposition to Edison’s motion

for summary judgment which would create a material issue of

“We note that the district court granted summary judgment on at least

some of the claims because Vernon failed to offer sufficient proof of

damages from alleged misconduct. We will address the damages issue in

Part C of this opinion.

10

fact. Instead, Vernon argued that if the asserted justification was

not insufficient as a matter of law, a jury should be permitted to

decide whether a slight increase in retail prices to Edison's

customers was a legitimate business reason for Edison’s refusal to

grant relative size share transmission access.

[1] At the time of the summary judgment motion, Vernon did

not appear to dispute the fact that retail customers would pay

increased rates if it received the access sought — indeed,

Vernon’s damage study reflected that fact. Nor did Vernon appear

to dispute the fact that Edison was legitimately concerned about

the retail rates in making its facilities access decisions.’

[2] The district court did not err in granting summary judg-

ment against Vernon on the relative size share access claim.

Although the defendant generally has the burden of coming

forward with a legitimate business justification after the plaintiff

has shown evidence of monopolistic intent, the plaintiff, in this

case Vernon, ultimately has the burden of proving that the

defendant acted without a legitimate business justification. mage

Technical, 903 F.2d at 620 n.9; Calculators Hawaii, Inc. v.

Brandt, Inc., 724 F.2d 1332, 1339 (9th Cir. 1983). Cf Aspen

Skiing Co. v. Aspen Highlands Skiing Corp., 472 U.S. 585, 608-

611, 105 S. Ct. 2847, 2860-61, 86 L. Ed. 2d 467 (1985)

(implying that defendant has burden of production and proof). In

order to survive summary judgment, Vernon had to point to

evidence demonstrating that there was a genuine issue of material

fact as to whether Edison in fact acted on the asserted grounds.

Having failed to do so, summary judgment was appropriate.

Furthermore, Vernon fails to demonstrate just why Edison is

required to cease using its own facility so that Vernon can begin

using it. This is not a situation where Edison had no use for the

facility and arbitrarily denied someone else its use. See MC/

Communications Corp. v. American Tel. & Tel. Co., 708 F.2d

1081, 1133 (7th Cir.) (AT&T was not asked to abandon its

facilities; no business reason shown for refusal), cert. denied, 464

*It is legitimate for Edison to refuse access that will affect its rates to

the detriment of its customers. See City of Anaheim, slip op. 1237.

ee

1]

U.S. 891, 104 S. Ct. 234, 78 L. Ed. 2d 226 (1983). Nor is it a

case where Edison simply refused to supply Vernon with its power

needs. See Otter Trail Power Co. v. United States, 410 U.S. 366,

378, 93 S. Ct. 1022, 1030, 35 L. Ed. 2d 359 (1973). In fine,

Edison clearly had a use for its lines. As we pointed out in City of

Anaheim, slip op. 1236, the demand that Edison turn over its

facility to a city simply because the city could save money by

obtaining cheaper power stands the essential facility doctrine on

its head.

[3] But, even had Vernon offered some evidence which raised

a material issue of fact with respect to Edison’s reasons for

refusing relative size share access, we can find no authority — and

Vernon has pointed to none — which supports Vernon’s theory

that “reasonable” access to Edison’s facilities must take the form

of relative size share access. Even more to the point, Vernon

admits that it never requested relative size share access to

Edison’s transmission facilities. The district court properly

granted summary judgment.

2. Integrated Operations Agreement.

[4] The IOA was one way in which Edison could meet its

obligation to provide reasonable access to its essential facilities.

The district court held that to the extent that Edison had a duty to

integrate Vernon’s power purchases, the duty was limited by

legitimate business justifications. The court found no triable issue

of fact on this claim and determined that summary judgment was

appropriate because Edison had a legitimate business justification

for not providing for an eighteen month notice period'® when the

FERC had determined that a three year period was reasonable.

Assuming, as the district court did, that Edison is a monopolist

in control of an essential facility, it must not unreasonably deny

access to the facility to its competitors. MCI, 708 F.2d at 1132.

Given that predicate, we conclude that Edison had a duty to

‘The 18 month period versus three year period engendered confusion

because Vernon’s damage study was based on the 18 month notice

period provided in Special Condition 12.

12

integrate purchases of outside resources upon reasonable notice.

Despite the assumptions made in Vernon’s damage study,

Vernon’s complaint is not that Edison refused to allow integration

on 18 months’ notice, but that Edison refused to allow integration

until it felt like it. The IOA proposed by Edison did not contain a

particular notice period — integration occurred at Edison’s dis-

cretion.'' The FERC determined that Edison’s discretionary stan-

dard was unreasonable, and that a three year period was

reasonable notice. Southern Cal. Edison Co., 41 F.E.R.C. at

61,493-94; Southern Cal. Edison Co., 52 F.E.R.C. at 62,202-03."

Edison offered no legitimate business reason for its refusal to

provide a reasonable notice period. Rather, in support of its

motion for summary judgment, it simply asserted that it had no

duty under the antitrust laws to provide integration on reasonable

notice. We find little merit in that contention. In any event, it

seems unlikely that Edison could have prevailed on a claim that it

had a legitimate business reason for refusing to establish a

reasonable notice period. The integration agreement provided

benefits not only to the municipal utility, but to Edison as well.

Edison would be able to avoid adding additional generating

capacity and it also received a portion of the integrated electricity

as reserves. The municipality would be able to lower its costs.

Thus, in refusing to provide for a reasonable notice period, Edison

was foregoing a benefit to itself and its ratepayers. Cf Aspen

Skiing, 472 U.S. at 608, 105 S.Ct. at 2860. A trier of fact might

well conclude that Edison had no legitimate business reason for

refusing to enter into a reasonable IOA.

''As characterized by the FERC, the IOA would have permitted

Edison to “subordinate a completed city project [desired to be inte-

grated] to an Edison project that may still be in the early stages of

development or which may be deferred or never completed.” Southern

Cal. Edison Co., 41 F.E.R.C. at 61,494.

"The district court did not determine what notice requirement would

be reasonable, but concluded that no liability could be imposed for

refusal to adopt a notice period of less than three years. Vernon asserted

before the FERC that a three year period was reasonable and the FERC

agreed.

13

[5] In other words, based upon all of the assumptions that the

district court made for summary judgment purposes, it is possible

that a trier of fact would find that Edison’s IOA position could

have been an attempt to use monopoly power to eleminate

competition. Had the determination of the district court been

made at the end of a trial, there would not be error; summary

judgment is another matter entirely.'°

3. Special Condition 12 Claim.

[6] The district court found that Edison had no obligation

under the antitrust laws to offer SC-12 to Vernon, particularly

where Edison could reasonably require three years notice for

integration of capacity resources. Even though Edison had a duty

to integrate capacity resources on reasonable notice, there is

nothing to suggest that Edison was required to do so through SC-

12. In addition, it appears that there are no damages attributable

to Edison’s failure to implement SC-12 sooner which are separa-

ble from Edison’s failure to provide for integration on reasonable

terms. As Vernon contends that SC-12 was only a partial correc-

tion of the defects in the IOA, there would appear to be no

additional losses from any delay or limitation in SC-12 over and

above the losses allegedly caused by the improper IOA. Summary

judgment on this claim was appropriate.

4. Interruptible Transmission Service.

The district court concluded that three grounds supported

summary judgment on Vernon’s claims that Edison improperly

denied, interrupted or curtailed Interruptible Transmission Ser-

vice (ITS) from Nevada Power to Vernon. First, the court

concluded that Vernon had failed to quantify any damages from

the interruptions.'* Second, the court concluded that an antitrust

claim could not be based on a contractual dispute as to the

reasonableness of conduct.” Finally, the court concluded that

‘However, see the damage discussion in Part C of this opinion.

'’See our discussion of damages in Part C of this opinion.

14

Vernon had failed to demonstrate that Edison’s reasons for

interrupting transmission were not legitimate.

[7] We are not convinced that antitrust liability may not be

predicated on conduct which also happens to create a contract

dispute. It is certainly true that a claimed breach of contract by

unreasonable conduct, standing alone, should not give rise to

antitrust liability. But in this case, Vernon is not simply claiming

that Edison breached its contract. Instead, Vernon is claiming

that by preventing the purchase of electricity from Nevada Power,

Edison acted anticompetitively and without a legitimate business

reason. The fact that Vernon and Edison have a contract allowing

Edison to interrupt transmission “for any reason” is beside the

point. The contractual nght to interrupt service does not grant

Edison the freedom to act anticompetitively. See California v.

Chevron Corp., 872 F.2d 1410, 1414 (9th Cir. 1989) discussing

pendent state law claims to antitrust case), cert. denied, 493 U.S.

1076, 110 S. Ct. 1126, 107 L. Ed. 2d 1032 (1990). See also City

of Long Beach v. Standard Oil, 872 F.2d 1401 (9th Cir. 1989)

(discussing antitrust claims in action related to California v.

Chevron), amended, 886 F.2d 246, cert. denied, 493 U.S. 1076.

110 S. Ct. 1126, 107 L. Ed. 2d 1032 (1990). In short, Edison

might avoid contractual liability through the interruption provi-

sion, although even that is questionable, California v. Chevron

Corp., 872 F.2d at 1414, but the contractual limitation does not

speak to antitrust concerns.

That, however, does not itself demonstrate that summary

judgment was inappropnate. At first blush, Vernon’s evidence

seems to raise an issue of fact as to whether Edison’s asserted

business justifications for interrupting transmission were legiti-

mate. There was some evidence from which a trier of fact could

conclude that Vernon encountered refusals to provide transmis-

sion even when Edison had capacity available.

Nonetheless, summary judgment was appropriate on this claim.

It is not enough for a party to content itself once it has produced a

mere scintilla of evidence to support its case. Rather, as the

Supreme Court held in Matsushita Elec. Indus. Co., Ltd. v.

Zenith Radio Corp., 475 U.S. 574, 587, 106 S. Ct. 1348, 1356, 89

L. Ed. 2d 538 (1986), the record must be sufficient to “lead a

en |

15

rational trier of fact to find for the non-moving part ...” That

requirement was underscored in Anderson v. Liberty Lobby, Inc.,

477 U.S. 242, 248, 106 S. Ct. 2505, 2510, 91 L. Ed. 2d 202

(1986) where the Court held that the evidence must have

sufficient strength to allow a reasonable jury to “return a verdict

for the nonmoving party.” Here the evidence does not reach that

level.

Vernon’s evidence consists of an entry in a Nevada Power log

that indicates that on one occasion there was a refusal to allow

transmission if Nevada Power was “purchasing [power] from the

east,” and a sworn statement and a deposition from a single

former Nevada Power dispatcher, Richard Greenwalt.

[8] Greenwalt’s testimony was to the effect that there was on

occasion a refusal to allow transmission which prevented Nevada

Power from making a sale to Vernon. He indicated that some

possibly improper statements were made to him “reasonably

often” or were “very common.” His exact meaning is not clear.

More than that, he gave absolutely no specifics as to person or as

to time. Detail of a kind that would allow evaluation of the

accuracy of his recall or of the consistency and extent of the acts

is missing. Certainly, there was no evidence that transmission was

interrupted at any time at the behest of any person employed by

Edison other than a dispatcher, who was acting as he did for

unknown reasons. There was no evidence that any person with

management or supervisory authority ever told any dispatchers to

interrupt or to refuse transmissions for any anticompetitive reason

or that dispatchers were acting on a policy of wrongfully refusing

or interrupting transmission. There was no evidence produced to

show that any management level personnel ever approved or

ratified wrongful transmission interruptions or refusals.

It is important to remember that this is not a simple tort case

where a single incident is enough to support liability. The claim in

this case is that there was relatively long-term activity aimed at

crushing a competitor. If proved, antitrust liability and treble

damages would be imposed upon Edison. Yet, Vernon proposed

to proceed with this complex antitrust case based upon evidence

which almost entirely consisted of statement from a former

Nevada Power employee operating at a fairly low level. As

16

already mentioned, his statements were that unknown employees

of Edison, operating at a similarly low level, interrupted transmis-

sion from time to time improperly. Who did it remains unknown.

When they did it remains equally unknown. There is an almost

total absence of detail. Against that Edison did all one could do: it

submitted numerous affidavits from Nevada Power and Edison

employees who stated that they never did those things or even

heard of them. Their testimony, which was uncontested and

unchallenged, indicates that if the threats did occur they were

neither frequent no uniformly issued.

We agree with the district court that antitrust liability must be

composed of stronger stuff. In so doing we do not mean to suggest

that lower level employees cannot involve a corporation in anti-

trust liability. Nor do we suggest that credibility determinations

should be made at the time of summary judgment.

As to the former, we recognize that even if an employee is

violating express corporate policy, the corporation might still be

held responsible. As long as the employee is acting within the

scope of his employment, imposition of liability upon the corpora-

tion is appropriate. See United States v. Portac, Inc., 869 F.2d

1288, 1293 (9th Cir. 1989), cert denied, US. » 111 S.

Ct. 129, 112 L. Ed. 2d 97 (1990); United States v. Hilton Hotels

Corp., 467 F.2d 1000, 1004-07 (9th Cir. 1972), cert. denied, 409

U.S. 1125, 93 S. Ct. 938, 35 L. Ed. 2d 256 (1973). See also

American Society of Mechanical Engineers, Inc. v. Hydrolevel

Corp., 456 U.S. 556, 102 S. Ct. 1935, 72 L. Ed. 2d 330 (1982).

Nevertheless, we do not believe that the employee’s position

within the organization can be entirely ignored when we are

attempting to determine whether antitrust activity was afoot at

all. For example, in each of the cases just cited a conspiracy to act

for anticompetitive reasons was clearly present and the employee

involved wielded a good deal of authority. In Hilton Hotels there

was a full blown conspiracy and the employee in question was the

purchasing agent for the hotel in question. 467 F.2d at 1004. In

Portac, also, there clearly was a conspiracy and, again, the

employee involved was the sole purchasing agent for the defen-

dant. 869 F.2d at 1293. Finally, in American Society of Mechani-

cal Engineers there was a clear conspiracy to violate the antitrust

17

laws. One of the participants was the chairman of the subcommit-

tee that issued a letter designed to carry out the anticompetitive

intentions. 456 U.S. at 560-62, 102 S. Ct. at 1939-40. The letter

was then signed by the secretary of the committee itself, and

carried great weight in the engineering industry. /d. at 561-64, 102

S. Ct. at 1940-41. In the case at hand, however, the most Vernon

has shown is that one or more unidentified members of an

amorphous group of Edison dispatchers occasionally unnecessa-

rily interrupted power transmissions for largely unexplained rea-

sons, some of which may have been improper. They did so while

pursuing a myriad of transactions conducted over a long period.

Nor need we or should we evaluate credibility at summary

judgment. See McLaughlin v. Liu, 849 F.2d 1205, 1207 (9th Cir.

1988). Nevertheless, the testimony of Mr. Greenwalt, even if

accepted, would not be sufficient to allow a rational trier of fact to

impose antitrust liability on Edison. The question here is not

simply whether Edison can be held liable for the proven antitrust

violations of employees acting with apparent authority, see Hilton

Hotels, 467 F.2d at 1004 and Portac, 869 F.2d at 1293, but

whether a rational jury could conclude that there were antitrust

violations in the first place. In evaluating that question, the fact

that Mr. Greenwalt could not recall any names, dates or times

further indicates that Vernon has not raised a factual dispute

sufficient to survive summary judgment.

In sum, more evidence that that produced by Vernon would be

needed to impose liability upon Edison on this claim. The district

court did not err when it granted summary judgment.

5. The Pacific Intertie.

[9] Vernon asserted that Edison violated § | by conspiring with

others to prevent Vernon from obtaining access to the Pacific

Intertie.'* We recognize that in Vernon’s § | claim with respect to

the Pacific Intertie, Edison, no Vernon, would have the burden of

'SWhile Edison contends that Vernon abandoned its Pacific Intertie

claims, it is clear from the record that Vernon did not do so. We find no

error in the district court’s entry of judgment on this claim without a

18

proving that it had a legitimate business purpose for foreclosing

access. Image Technical, 903 F.2d at 618 n.5. However, a review

of the record does not reveal any evidence adduced by Vernon

that Edison conspired with anyone to deny access to the Pacific

Intertie. A § | violation requires “concerted action” by more than

one entity. The Jeanery, Inc. v. James Jeans, Inc., 849 F.2d 1148,

1152 (9th Cir. 1988).'° The district court properly granted

judgment on this claim.

B. Edison-Nevada Power Boycott Claims.

To prevail on a claim under § 1, Vernon would have been

required to show concerted action on the part of Edison and

Nevada Power. The Jeaney, 849 F.2d at 1152. The district court

granted summary judgment on the horizontal boycott claims on

the grounds that Vernon had failed to show evidence of damages

from the alleged boycott and because Vernon had failed to offer

evidence of concerted action.

We agree with Vernon that a conspiracy to monopolize may

exist even where one of the conspirators participates involuntarily

or under coercion. Calnetics Corp. v. Vokswagen of America, Inc.,

532 F.2d 674, 682 (9th Cir.), cert. denied, 429 U.S. 940, 97 S. Ct.

355, 50 L. Ed. 2d 309 (1976). To survive summary judgment, a

plaintiff must point to evidence “‘that tends to exclude the

possibility’ that the alleged conspirators acted independently.”

Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574,

588, 106 S. Ct. 1348, 1356, 89 L. Ed. 2d 538 (1986) (citation

omitted); Morgan, Strand, 924 F.2d at 1488. Edison makes much

of this language and suggests that Vernon’s evidence does not

exclude the possibility of independent action. But Matsushita

does not extend quite as far as Edison suggests. Following its

“exclude the possibility” language, the Court stated that the

formal motion for summary judgment, since Vernon acceded to the

entry of judgment on this claim.

‘Vernon also conceded that it had not segregated damages on the

Pacific Intertie claims. See our discussion of damages in Part C of this

opinion.

19

nonmoving party, “in other words, must show that the inference

of conspiracy is reasonable in light of the competing inferences of

independent action or collusive action that could not have

harmed” it. /d., 475 U.S. at 588, 106 S. Ct. at 1356-57. Neverthe-

less, Vernon did not even meet this somewhat lesser standard.

[10] Here, too, Vernon’s evidence was far too weak. First,

there is no evidence that the alleged acts by the unnamed Edison

dispatchers were more than random, unauthorized acts by em-

ployees. There was no showing, in other words, that these Edison

dispatchers entered into conspiracies with Nevada Power dis-

patchers to boycott Vernon’s attempt to purchase power. Second,

if Edison refused to transmit Nevada Power's electricity over

Edison lines, Nevada Power had no choice but to acquiesce. That

does not make it a conspirator. Third, as the district court noted,

it would be most difficult to draw a reasonable inference of

conspiracy where there was no meeting of the minds. Instead,

according to Vernon’s evidence, Edison had to continually

threaten Nevada Power dispatchers and they did not necessarily

accede to those threats. The district court did not err.

C. Damages.

Vernon presented the court with a damage study which was, at

best, seriously flawed. That resulted in findings that because no

damages had been properly shown, there was an independent

reason to grant summary judgment on various claims against

Edison. Vernon asserts that the district court erred. We do not

agree. Indeed, the deficiencies in that study undermine Vernon’s

whole case.

The principles which the courts follow in deciding this issue are

well described in MCI. There the court reviewed a damage verdict

and in so doing made the following observations:

Once causation of damages has been established, the

amount of damages may be determined by a just and

reasonable estimate as long at the jury verdict is not the

product of speculation or guess work. Since the Supreme

Court has been willing to accept a degree of uncertainty in

the calculation of damages, strict proof of what damages

20

have been caused by which acts has not been required. Not

requiring strict disaggregation of damages among the various

unlawful acts of the defendant serves to prevent a defendant

from profiting from his own wrongdoing and makes sense

when damages arise from a series of unalwful acts interwined

with one another.

The courts have always distinguished between proof of

causation of damages and proof of the amount of damages.

Thus, the courts have been consistent in requiring plaintiffs

to prove in a reasonable manner the link between the injury

suffered and the illegal practices of the defendant.

708 F.2d at 1161 (citations omitted).

The court continued as follows at page 1163:

There is nothing inconsistent between requiring proof that

damages were caused by illegal acts and the rule that a

plaintiff need not disaggregate damages among those acts

found to be unlawful. In this case, the trial court granted

summary judgment for AT & T on seven of the twenty-two

counts in the complaint. In addition, the jury found for

AT &T on five of the fifteen counts it considered. The jury

found for MCI on two counts relating to Hi-Lo tariffs, two

counts relating to the tariffs filed with state agencies, and six

counts relating to interconnection. In addition, this court has

now determined that the jury’s findings for MCI on the

pricing and pre-announcement of Hi-Lo as well as the

finding relating to denial of multipoint interconnections must

be set aside.

MCI assumed in the preparation of its damage study that

all twenty-two of AT & T’s acts charged were illegal. In fact,

liability has now been established with respect to only seven

of the twenty-two counts of alleged monopolization. MCI’s

lost profits study does not establish any variation in the

outcome depending on which acts of AT & T were held to be

legal and which illegal.

21

The result was a remand for a new trial on the damage issue.

We accepted that view in Farley Transp. Co., Inc. v. Santa Fe

Trail Transp. Co., 786 F.2d 1342, 1352 (9th Cir. 1985) (footnote

omitted), where we, too, declared that the plaintiff's “utter failure

to make any segregation between damages attributable to lawful

competition and that attributable to the unlawful scheme to

deviate from the tariff rate requires reversal of the verdict and

remand for a new trial on the amount of damages.” Cf. William

Inglis & Sons Baking Co. v. Continental Baking Co., Inc., 942

F.2d 1332, 1341 (9th Cir. 1991) (where lost profits calculation

was wholly speculative, the district court should have granted

judgment notwithstanding the verdict).

Here, of course, the matter came up before trial commenced

and at a time when the only possibly admissible damage study

was before the court. That study failed to segregate the losses, if

any, caused by acts which were not antitrust violations from those

that were. Nor did Vernon attempt or offer to make corrections.

Rather, according to its own expert Stephen Flanagan, speaking

in the context of the group boycott claim, Vernon would not or

could not do so. That might well have been because Vernon’s

deeply flawed study is the handmaiden of its equally flawed theory

that it should have proportionate firm access to Edison’s whole

system at all times.

The question remaining is whether the district court was

nevertheless required to allow Vernon to go to the jury with its

erroneous approach or to give it still another opportunity to refine

a study that, according to Vernon, could not be refined. We think

not.

We dealt with a similar situation in McGlinchy v. Shell Chem.

Co., 845 F.2d 802 (9th Cir. 1988). There the damage studies of

the plaintiffs were plainly insufficient, so the district court ex-

cluded them. We held that the absence of a proper study meant

that the plaintiffs “could make no showing about the amount of

damages.” Jd. at 808. As a result, there was no “competent

evidence from which a jury could fairly estimate damages,” id. at

808, and summary judgment was proper. See also ILC Peripherals

Leasing Corp. v. International Business Mach. Corp., 458 F.

Supp. 423, 434 (N.D. Cal. 1978) (summary judgment granted

ae

where the damage study did not separate effects of various acts so

that “there was no basis in the record for the jury to determine

what the effect on damages would be if it found one or more of

the challenged acts lawful.’’)

In McGlinchy, we cited our earlier case of Dolphin Tours Inc.

v. Pacifico Creative Serv., Inc., 773 F.2d 1506 (9th Cir. 1985), a

case in which the damage study presented at the time of summary

judgment was also flawed. There, however, the flaws did not

appear to be insurmountable and we opined that “Dolphin has

presented evidence from which a jury could reasonably estimate

the amount of Dolphin’s injury without speculation if Dolphin’s

damage evidence were filled in by testimony at trial.” /d. at 1513.

We had confidence in that possibility because it appeared that the

date already existed even though it had not yet been placed in the

proposed damage report. Moreover, we said, if the repair was not

made the district court could grant a directed verdict or a

judgment notwithstanding the verdict.

Here we have no such confidence. Vernon insists that all of

Edison’s acts contributed to the damage figure, but the district

court and we have already found that many of those acts were

proper. It might be argued that since Vernon had a contract with

Nevada Power which was to save Vernon $80,000 per month and

did not, there was at least a loss of that amount, damage studies

notwithstanding. However, that argument would suffer from the

same flaw because there is no indication of what part of that

$80,000 loss of savings was due to proper interruptions of service

and what part to improper ones, or for that matter, due to other

factors entirely.

[11] In short, we agree with the district court that the serious

flaws in the only damage study which could be profferred to the

jury placed Vernon in the position of having no proper proof of

damages at all. Thus, the district court did not err when it

awarded summary judgment based upon this lack of evidence.

D. Injunctive Relief.

[12] Injunctive relief might be appropriate if Edison has

unreasonably refused access to its essential facilities. Otter Tail

23

Power Co., 410 U.S. at 381-82, 93 S. Ct. at 1031-32. The court

did not grant any injunctive relief because it concluded that

Edison had not violated the antitrust laws. However, summary

judgment on Vernon’s claim that Edison’s refusal to provide for a

reasonable notice term in the IOA was proper only because

Vernon failed to quantify damages which resulted from that

conduct. Thus, it is possible that Vernon will be entitled to

injunctive relief if it can prove an antitrust violation. We therefore

must reverse the denial of injunctive relief as to the IOA claim

only and remand the case to the district court to determine the

propriety of injunctive relief.

CONCLUSION

Here, as in City of Anaheim, slip op. 1221, we need only decide

whether the actions of Edison violated the antitrust laws. The

district judge held that Edison did not violate those laws, and,

even if it did, Vernon did not properly delineate damages. For the

most part we agree.

Therefore, we affirm the district court in every respect save one.

That one is: the district court erred in granting summary judg-

ment on Vernon’s claim for injunctive relief arising out of

Edison’s refusal to develop reasonable terms for integrated opera-

tions agreements.’

AFFIRMED IN PART, REVERSED IN PART AND RE-

MANDED FOR FURTHER PROCEEDINGS. The parties

shall bear their own costs on appeal.

"We deny Edison’s motion ot strike portions of Vernon’s brief and

excerpts.

24

Filed April 21, 1992

Cathy Caterson, Clerk, U.S. Court of Appeals

No. 90-56281

NOT FOR PUBLICATION

UNITED STATES COURT OF APPEALS

FOR THE NINTH CIRCUIT

CITY OF VERNON,

Plaintiff-Appellant,

wi

So. CALIFORNIA EDISON COMPANY

Defendant-Appellant,

ORDER

Before: SCHROEDER, LEAVY, and FERNANDEZ, Circuit

Judges.

The panel has unanimously voted to deny the appellant's

petition for rehearing. The suggestion for rehearing en banc was

circulated to the active judges of the court, and no judge re-

quested a vote for en banc consideration.

The petition for rehearing and the suggestion for rehearing en

banc are accordingly DENIED.

25

CASE NO. CV 83-2°37 MRP

UNITED STATES DISTKICT COURT

CENTRAL DISTRICT OF CALIFORNIA

CITY OF VERNON, CALIFORNIA

Plaintiff,

V.

SOUTHERN CALIFORNIA EDISON COMPANY,

Defendant.

FINDINGS OF FACT AND CONCLUSIONS OF LAW IN

SUPPORT OF ORDER GRANTING EDISON’S MOTION

FOR SUMMARY JUDGMENT ON PLAINTIFF'S FORE-

CLOSURE CLAIMS

Having read and considered the papers and evidence submitted

in connection with defendant Southern California Edison Com-

pany’s (“Edison’s”) Motion for Summary Judgment on plaintiff's

foreclosure damage claims, associated motions of defendant

Edison and plaintiff the City of Vernon (“Vernon”) and the

pleadings filed herein, and having heard oral argument with

respect to the proposed findings and conclusions and objections

thereto, the Court finds and concludes as follows:

A.

FINDINGS OF FACT

1. INTRODUCTION

1.1 Plaintiff Vernon’s First Amended and Supplemental

Complaint in this action alleged, inter alia, that Edison violated

§§ 1 and 2 of the Sherman Act through a pattern of conduct

commencing in 1961 and continuing into the present. Vernon’s

contentions fall into three basic categories: (i} those relating to

the terms and conditions of Vernon’s access to Edison’s transmis-

sion lines and access to non-Edison sources of power (the “fore-

closure” claims); (2) those concerning Edison’s rates; and

(3) those asserting a conspiracy between Edison and the Nevada

Power Company to boycott Vernon.

26

1.2. Edison has filed motions for partial summary judgment on

Vernon's § 2 rate and § | group boycott claims, and for summary

judgment on Vernon's foreclosure claims.

Decision Granting Motions for Summary Judgment with Respect

to Rate Claims and Group Boycott Claims” filed March 7, 1990

(the “‘Memorandum of Decision”), the Court granted Edison’s

motions for partial summary judgment on the plaintiff's rate and

boycott claims.

1.3 By its Order dated March 1, 1990 and “Memorandum of

1.4 These Findings of Fact and Conclusions of Law are made

in connection with the Court’s Order dated March 1, 1990

granting Edison’s Motion for Summary Judgment on Plaintiff's

Foreclosure Damage Claims.

2. FACTUAL BACKGROUND

(a) Southern California Edison Company

2.1 Defendant Edison is an investor-owned utility that pro-

vides electric service in central and southern California, within a

service territory established by the California Public Utilities

Commission (“CPUC”).

2.2 Edison, as a fully integrated electric utility, generates,

transmits, and distributes electricity.

2.3 Edison provides electric service to residential, commer-

cial, and industnal customers located throughout its service

territory.

2.4 Edison also purchases electricity from and sells electricity

to other utilities located outside its service territory.

2.5 Edison operates its own electric “control area.” A “con-

trol area’ can be viewed as an area or system within which the

operation of all generation, transmission and distribution facilities

must be coordinated so that the system is operated as a synchro-

nized integrated whole, at the same frequency, and in a reliable

fashion. Typically every major utility operates a control area.

27

(b) Vernon and the Other Resale Cities

26 Plaintiff is a California municipality that owns its own

distribution system and provides electric service at retail within its

boundaries. While Vernon has some generating capacity, most of

the power it sells is acquired through wholesale purchases from

Edison or other bulk power suppliers.

2.7 Vernon occupies an area of approximately 5.06 square

miles and is located within Edison’s service territory. Vernon has

common boundaries with the City of Les Angeles, the service

territory of the Los Angeles Department of Water and Power

(“LADWP”) and other cities in Los Angeles County that are

also within Edison’s service territory. Vernon is primarily an

industrial city.

2.8 In addition to Vernon, Edison’s “wholesale” or “resale”

customers include the cities of Anaheim, Azusa, Banning, Colton,

and Riverside (the “Cities”). Because they purchase from Edison

wholesale electricity that they resell to their retail customers,

Vernon and the Cities are sometimes referred to as “Resale

Cities.” Like Vernon, the Cities are located within Edison's

service territory and each own their own distribution systems and

provide electric service at retail within their boundaries. Because

Vernon and the Cities do not operate their own control areas and

are within Edison’s control area, Edison has the ultimate respon-

sibility for meeting their system load requirements.

+9 From 1962 to 1977, Vernon purchased all of its electricity

that it resold to its resale customers from Edison pursuant to an

operating agreement entered into by the parties. Since 1977,

Vernon has been a partial requirements Customer of Edison.

4.10 Vernon and Edison entered into a limited Integrated

Operations Agreement (“IOA”) restricted to Vernon’s participa-

tion in the Palo Verde Nuclear Generating Station located in

Arizona. Vernon has an ownership interest in this generation

facility and has participated through the Southern California

Public Power Authority, in which it is a member. The Edison-

Vernon Palo Verde IOA is Exhibit P to the O'Malley Opposition

Declaration.

—

28

(c) Edison's Transmission Network

2.11 Edison’s transmission lines are a part of an intercon-

nected series of transmission lines connecting Edison with other

utilities located throughout the western United States. Edison’s

Extra High Voltage (“EHV”) transmission lines (generally oper-

ated at 500 kV or above) are used for the transmission of large

blocks of power from remote generation resources, including

those of other utilities, to the main grid of Edison’s transmission

system which is operated at 220 or 230 kilovolts or “kV” (the

“220 kV network’’).

2.12 One group of EHV transmission lines in which Edison

has nghts is the Pacific Intertie. The Pacific Intertie consists of

two 500 kV alternating current (“AC”) lines running from

Oregon through California (the “AC lines”) and one 800 kV

direct current (“DC”) line running from Oregon through Nevada

into Southern California (the “DC iine”’).

2.13 Edison’s EHV transmission lines to the Southwest con-

sist principally of 500 kV AC lines from the Los Angeles basin to

Nevada, Palo Verde (in Anzona) and the Four Corners area (in

New Mexico). Other EHV transmission lines to the Southwest

are owned by LADWP, San Diego Gas & Electric Company and

the Southern California Public Power Authority.

2.14 Edison’s 220-kV network, which consists of a grid or

network of 220 or 230 kV transmission lines, is situated in the

greater Los Angeles metropolitan area. Edison’s 220 kV network

connects with a number of major utilities, including LADWP and

the California Department of Water Resources (““CDWR”).

(d) Regulation

2.15 The terms and conditions of Edison’s rates and service to

its retail customers are regulated by the CPUC. The CPUC also

has jurisdiction over Edison in that Edison cannot dispose of its

assets or rights which are used or useful for service to retail

customers without CPUC approval.

2.16 Edison’s rates and terms of service to its resale custom-

ers are regulated by the FERC. Any agreements between Edison

29

and its Resale Cities, including Vernon, regarding resale service

or transmission must be filed with the FERC. Edison cannot

legally charge a rate or provide a service to a Resale City without

an appropriate FERC rate schedule for that rate or service being

in effect.

2.17 In 1972, in part as a result of certain antitrust claims

brought by the Cities, Edison and each of the Resale Cities

entered into settlement agreements. Those agreements, in addi-

tion to releasing Edison from antitrust liability for conduct prior to

that time, contemplated a framework within which the Resale

Cities could begin to acquire energy from other sources and

integrate it into the Edison system.

2.18 Integration is a contractual concept under which re-

sources and loads of independent parties are planned and operated

as if they were a single system.

2.19 The integration of resources into Edison’s system, as

opposed to the mere transmission of such energy by Edison is

important because of Edison’s rate structure. If Edison integrates

a proposed resource, Edison gives the customer credit not only for

the energy brought into the system, but also a “capacity credit”

for the reduction in generating capacity Edison must maintain.

2.20 Anaheim and Riverside, after five years of negotiations,

entered into IOAs with Edison to establish standards for the

integration and transmission of resources. These IOAs became

part of Edison’s rate schedules in 1979.

2.21 Vernon did not seek to participate in the negotiations for

IOAs that took place in the 1970s.

2.22 Azusa, Banning and Colton entered into IOAs similar to

those entered into by Anaheim and Riverside. These IOAs

became part of Edison’s rate schedules in 1981.

2.23 Since 1981, Edison has offered to enter into an IOA with

Vernon similar to the IOAs with the five Cities. Vernon, however,

has refused to enter into such a “generic” IOA.

2.24 Under the 1972 Settlement Agreements, and the Cities’

generic IOAs, Edison must provide the Resale Cities with all of

30

their requirements for electricity to the extent the Resale Cities

are unable to obtain power from others or from their own

facilities. The IOAs have allowed the Resale Cities to build their

own generation projects, to participate in joint projects with

others, and to purchase capacity from cthers.

2.25 Edison’s standard for the timing of capacity credit in the

generic IOAs, § 8.1.2.3 of the IOAs, past applications of that

standard, as well as other terms of the IOAs were challenged in

FERC Docket No. ER81-177. Although the decision in that

Docket is still subject to rehearing, the FERC concluded that the

standard set forth in § 8.1.2.3 of the generic IOAs was not just

and reasonable because it allowed Edison to discriminate unduly

in determining when a wholesale customer should begin receiving

capacity credits for a noticed resource. The FERC concluded that

a three-year notice requirement for partial requirements custom-

ers who intend to acquire and integrate a capacity resource was

reasonable. In that FERC Docket, Vernon proposed and sup-

ported the position that a three-year notice requirement should be

adopted for the integration of a capacity resource. Docket

No. ER 81-177, 27 FERC 63.053 at 65,205, incorporated by the

FERC in its decision (41 FERC 4 61,188 at 61,496). In addition,

the FERC found other terms in the generic IOA to be

unreasonable.

2.26 In this action, Vernon does not contend that a three-year

notice requirement for the integration of capacity is unreasonable.

(e) Special Condition 12

2.27 In addition to the IOAs, Special Condition 12 allows the

Resale Cities, in certain circumstances, to import and receive

credit for capacity obtained from sources other than Edison

without “integration” of the resource pursuant to the IOA.

2.28 Special Condition 12 arose, in part, out of an agreement

between Edison and Vernon regarding the operation of diesel

generators owned by Vernon. In July 1982, Edison and Vernon

entered into an agreement under which Edison committed to file

a tariff with the FERC which would provide Vernon with an

3]

opportunity to operate generation projects within the City of

Vernon, including Vernon’s diesel generators.

2.29 Special Condition 12 was included within a proposed

resale rate schedule filed by Edison with the FERC in October

1983. Under the terms of the July 1982 settlement, Vernon’s

diesel generators could be used by Vernon when they were

available for capacity and associated energy. Under Special Con-

dition 12, additional capacity and associated energy could be

generated or imported by Vernon by giving certain notices to

Edison, with the first notice due on or before July 1, 1985, for

generation or imports commencing during the two-year period

January 1, 1987 through December 31, 1988.

2.30 There is no provision for penalties if a resource noticed

by a Resale City under Special Condition 12 is not contracted for

or actually received by that City and no limit on the amount of a

City’s load that must be met by Special Condition 12 resources.

2.31 In June 1985, Vernon noticed approximately 27 MW of

Special Condition 12 resources from outside the City boundaries,

with credit to commence on January |, 1987. Prior to January 1,

1987, Vernon requested, and Edison agreed (although not obli-

gated to do so under Special Condition 12) that a purchase from

CDWR could substitute for the 27 MW of resources from other

utilities which Vernon had noticed. Edison provided Vernon firm

transmission service on Edison’s 220 kV network for the 27 MW

of Special Condition 12 resources from CDWR.

2.32 In June 1987, Vernon gave notice for all of the Special

Condition 12 resources that it felt it could handle for the period of

January 1, 1989 through December 31, 1990. That included

98 MW of capacity and associated energy during the summer and

62 MW of capacity and associated energy during the winter from

CDWR. Prior to the start of delivery of resources on January |,

1989, Edison again permitted Vernon to substitute for certain

Special Condition 12 resources previously noticed.

2.33 Vernon has used Special Condition 12 to reduce its

dependence on Edison for its capacity and energy needs.

32

(f) Interruptible Transmission Service

2.34 On or about December 15, 1981, Nevada Power Com-

pany (“NPC”) and Vernon entered into an Interconnection

Agreement providing, in part, for the sale of non-firm energy by

NPC to Vernon.

2.35 On or about January 5, 1982, Vernon and Edison entered

into an agreement for the integration and interruptible transmis-

sion service for non-firm energy purchased by Vernon from NPC.

The agreement was filed with the FERC and became part of

Edison’s rate schedules as of February 1, 1982.

2.36 Dunng 1982 and 1983, Vernon imported significant

quantities of non-firm energy from NPC _ under these

arrangements.

2.37 On or about December 23, 1983, Edison and Vernon

executed an agreement for the integration of, and interruptible

transmission service for, non-firm energy purchased by Vernon

from the CDWR.

2.38 The NPC and CDWR interruptible transmission service

(“ITS”) Agreement provided in part that the availability of

transmission service “shall be determined at the sole discretion of

Edison,” and Edison reserved the right to interrupt or curtail such

service “‘at any time and for any reason.” Edison has entered into

ITS agreements with the other Resale Cities that provide ITS on

all of Edison’s transmission lines. These agreements also provide

for interruption “‘at any time and for any reason.”

2.39 The form of interruptible transmission service contracts

offered by LADWP include a provision that allows LADWP to

interrupt or curtail such service “‘at any time and for any reason.”

One of Vernon’s consultants, Mr. Brodie, admitted that interrup-

tions of ITS for minimum load are not unusual in the industry and

that the owner of transmission facilities is expected to have a

priority of use of those facilities.

2.40 Although Edison’s ITS contracts with Vernon and its

other Resale Cities allow Edison to interrupt or curtail such

transmission service “‘at any time and for any reason,” Vernon has

not presented any evidence that when Edison did interrupt

33

Vernon’s transmission, that Edison did so for anticompetitive

reasons.

(g) Vernon's bulk power resources

2.41 In 1983, Vernon bought nearly all of its electricity from

Edison. By 1987, Vernon was purchasing less than one half of its

power from Edison.

2.42 As of 1989, Vernon’s non-Edison resources included the

following: (1) a diesel plant with peaking capacity of approxi-

mately 21.5 MW; (2) entitlements of an average of approxi-

mately 11 MW of peaking power and associated energy from

Hoover Dam; (3) a 10.6 MW interest in the Palo Verde Nuclear

Generation Station; and (4) two gas turbines with a total peaking

capacity of 11.2 MW. Vernon also purchases approximately

98 MW during the summer and 62 MW during the winter of

capacity and associated energy from the CDWR, and 30 MW of

capacity and associated energy from LADWP. In total, Vernon

currently has capacity from non-Edison resources of approxi-

mately 180 MW during the summer and 145 MW during the

winter.

2.43 Vernon’s electric requirements at its peak are approxi-

mately 195 MW, so during the summer months, Vernon has its

own non-Edison resources to obtain over 92% of its capacity.

2.44 In addition, Vernon is able to purchase economy energy

during off-peak hours from non-Edison sources at the rate of

approximately 70 MW.

2.45 Vernon operates its diesels, its Hoover power, CDWR,

and LADWP purchases, and the gas turbines, pursuant to

Edison’s Special Condition 12; Vernon’s Palo Verde ownership

interest is integrated pursuant to the Edison-Vernon Palo Verde

IOA.

2.46 Vernon is increasing its outside resources even beyond

what it had as of 1989.

34

3. VERNON’S FORECLOSURE DAMAGE CLAIMS

3.1 In support of its foreclosure claims, Vernon alleges that

Edison unlawfully restrained Vernon from purchasing bulk power

from suppliers other than Edison by denying Vernon access to its

transmission lines. Specifically, Vernon contends that Edison

should have given the City additional transmission -over the

Pacific Intertie and over certain other EHV lines extending to the

Southwest, as well as unconstrained transmission over Edison’s

220 kV network for Vernon’s purchases from CDWR. Vernon

further alleges that as a result of this foreclosure, as set out in

Claims I and II of Vernon’s First Amended Complaint, the City

was forced to purchase wholesale power from Edison at prices

higher than it would otherwise have had to pay. Vernon claims

that it was thus unable to compete with Edison in the provision of

retail electric service.

3.2 Vernon calculates its damages resulting from the foreclo-

sure as the difference between the rate Edison charged Vernon

and that which Vernon alleges it could have paid if Edison had

“foreclosed” Vernon’s access to the transmission lines.

3.3 Mr. Whitfield A. Russell, an engineer testifying on behalf

of Vernon, quantified these overcharge claims in five alternative

damage scenarios. Pursuant to the procedural schedule estab-

lished by the Court, Exhibit 2867 is the final version of Vernon’s

damage study and is the only one which could have been

presented by Vernon at trial.

3.4 Vernon’s damage study prepared by Mr. Russell includes

three principal damage scenarios, i.e., the Special Condition 12

capacity claims, the IOA capacity claims, and the energy-only

claim. The two capacity claim scenarios each offer an alternative

formulation, so that there are a total of five different damage

models in the Vernon study.

3.5 These alternative calculations, according to Vernon’s wit-

ness, produce damages ranging from a low of $14,969,341 under

the so called “Energy-Only” calculation to a high of $59,574,440

under the base case “Capacity Damage” calculation. Damages

are calculated for the years 1982 through 1987.

35

3.6 All five of the damage scenarios presented by Vernon

assume that Edison is obligated to provide Vernon with a relative

size share access to Edison’s EHV transmission lines, and uncon-

Strained access to Edison’s 220 kV network. The relative size

share access calculated by Mr. Russell is based upon the ratio of

Vernon’s load divided by Edison’s total load, including the load of

Vernon.

3.7 Under both of Vernon’s IOA capacity damage scenarios,

Vernon is assumed to be able to import new and additional

capacity and energy into the Edison control area, and receive

credit for capacity purchases, pursuant to the provisions of a

hypothetical IOA, upon 18-months notice to Edison of the

proposed additional capacity transactions.

3.8 Although Edison first made Special Condition 12 availa-

ble to Vernon in June 1984, such that resources noticed pursuant

to this provision could be imported to offset demand charges

beginning in January 1987, Vernon’s Special Condition 12 capac-

ity damage scenarios assume that this provision would have been

available for purposes of offsetting Vernon’s demand charge by

1983 rather than 1987.

3.9 In summary, the only conduct of Edison from which

Vernon claims quantifiable damages consists of: (1) the failure of

Edison to provide Vernon with relative size share access to its

EHV transmission lines and unconstrained access to its 220 kV

network; (2) the failure of Edison to provide Vernon with an

Integrated Operations Agreement containing terms acceptable to

Vernon, including a provision requiring Edison to accept into its

control area, and provide capacity credit for capacity imported on

18-months advance notice; and (3) the failure of Edison to have

Special Condition 12 included in its FERC resale rate schedules

four years earlier than this rate provision was included in Edison’s

FERC rate schedules.

3.10 Vernon’s damage study does not segregate damages as to

alleged foreclosure from any particular transmission line.

3.11 Vernon has also argued that Edison improperly inter-

rupted transmission service provided to Vernon for purchases of

non-firm energy from NPC and CDWR pursuant to the inter-

36

ruptible transmission service agreements between Vernon and

Edison. Vernon has not, however, quantified any damages specifi-

cally arising from this alleged conduct.

3.12 Vernon’s “relative size share” claim is premised on the

argument that Vernon is entitled to direct relative size share

acce.s to Edison’s EHV transmission lines, including Edison’s

entitlement on the Pacific Intertie and its transmission facilities

linking Edison with the desert Southwest. The relative size share

entitlement postulated by Vernon would give the City firm trans-

mission service over Edison’s EHV lines in an amount determined

by first calculating Vernon’s load as a proportion of Edison’s total

load and then multiplying this percentage figure by the megawatt

capacity of the particular transmission lines. Vernon claims that

Edison was obligated under the antitrust laws to offer this type of

access even in the absence of a specific request by the City and

even if Edison is unaware that access was desired.

3.13 The Court finds that Vernon has never made a formal

request to Edison for relative size share firm transmission access

3.14 In addition to this direct relative size share access,

Vernon contends that it is entitled to unlimited access to Edison’s

220 kV network provided there is sufficient capacity to meet the

total demand, and if the grid is unable to handle all the demand,

that the constraint on the system should be shared.

3.15 Edison admits that it has not given Vernon direct rela-

tive size share access to its transmission lines as assumed in

Vernon’s damage study.

3.16 If Edison granted Vernon relative size share access when

Edison was fully utilizing its transmission lines to import low cost

power, the result would be to shift the benefit of the low cost

power to Vernon and away from Edison’s other customers.

3.17 Exhibits A, B and C attached by Vernon to its “Double

Dip” Motion demonstrate the shifting of benefits that would

occur had Edison acceded to a Vernon demand for greater access

to Edison’s transmission lines.

3.18 Exhibit C is a specific example of how the type of access

assumed by Vernon in its damage claims would discriminate in

37

Vernon’s favor and against Edison’s retail customers. Page | of

that exhibit shows that the wholesale customer shares equally and

proportionately in the benefits of Edison’s low-cost imported

energy. Pages 2 and 3 of that exhibit reveal how providing a 10%

relative size share access, with the remainder purchased pursuant

to an average cost-based wholesale rate, would discriminate in

favor of the wholesale customers and against the retail customers.

As can be seen on page 3, as a result of the “double dip,”’ the

energy costs of the wholesale customer are decreased, with

additional costs imposed on the retail customers. This dispropor-

tionate access would result in the wholesale customer obtaining a

higher percentage of its requirements from the low-cost power,

while the retail customers would receive a lower percentage of

their requirements from the same source.

3.19 To the extent the foregoing Findings of Fact are also

Conclusions of Law, they are to be construed as Conclusions of

Law as well.

B.

CONCLUSIONS OF LAW

4. STANDARDS FOR GRANTING SUMMARY

JUDGMENT

4.1 Summary judgment is a useful tool for narrowing the

issues to be tried in antitrust proceedings. See Matsushita Electric

Industrial Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 585-86

(1986); Richards v. Nielsen Freight Lines, 810 F.2d 898, 902 (9th

Cir. 1987); Universal Analytics, Inc. v. MacNeal-Schwendler

Corp., 707 F. Supp. 1170, 1173-74 (“Universal Analytics’).

4.2 Summary judgment is appropriate in an antitrust case

involving a regulated electric utility. See City of Mt. Pleasant,

Iowa v. Associated Electric Coop, Inc., 838 F.2d 268, 273 (8th

Cir. 1988) (the court expressly declined to accept the plaintiff's

‘That is, access to low-cost energy both from direct transmission use

and indirectly through Edison’s resale rates.

38

contention that “a different, heightened standard for summary

judgment applies in complex antitrust cases.”’).

4.3 A moving party is entitled to summary judgment when

“there is no genuine issue as to any matenal fact” and the movant

“is entitled to a judgment as a matter of law.” See Fed. R. Civ.

Proc. 56(c). Under the Celotex Court’s interpretation of this rule,

summary judgment is mandated “against a party who fails to

make a showing sufficient to establish the existence of an element

essential to that party’s case, and on which that party will bear the

burden of proof at trial.” Celotex Corp. v. Catrett, supra, 477 U.S.

at 322.

4.4 The Court concludes that there is no genuine issue as to

any material fact, and that Edison’s Foreclosure Motion can be

decided as a matter of law. The Court further notes that Vernon

appears to agree with Edison that in this case, the sufficiency of

Edison’s proffered business justification is a matter of law and is

thus appropriate for resolution pursuant to Edison’s Foreclosure

Motion. Vernon explicitly states that “Edison’s asserted business

reasons for denying access to Vernon are insufficient as a matter

of law.” Vernon's Statement of Genuine Issues,’ Issue No. 4, at 3.

See, id., Issue Nos. 5, 12-13, at 3-4. Moreover, Vernon failed to

submit any facts sufficient to controvert or raise a factuat dispute

underlying the issue of legitimate business justification. See, e.g.,

Vernon's Opposition Memorandum at 22-27.

5. ELEMENTS OF A § 2 CLAIM FOR MONOPOLIZA-

TION AND ATTEMPTED MONOPOLIZATION

5.1 To prove the offense of monopolization under § 2, Vernon

must show that (1) Edison possesses monopoly power in a

relevant market, (2) Edison willfully acquired or maintained that

power, and (3) Vernon suffered causal antitrust injury. Oahu Gas

Service, Inc. v. Pacific Resources, Inc., 838 F.2d 360, 363 (9th

“Vernon's Statement of Genuine Issues” refers to Vernon's State-

ment of Genuine Issues of Fact Submitted in Opposition to Edison’s

Foreclosure Motion.

39

Cir.), cert. denied, 109 S. Ct. 180 (1988) (“Oahu Gas Service’),

Catlin v. Washington Energy Co., 791 F.2d 1343, 1347 (9th Cir.

1986).

5.2 To prevail on a claim of attempted monopolization under

§ 2, Vernon must demonstrate that (1) Edison had the specific

intent to control prices or destroy competition; (2) Edison en-

gaged in predatory or anticompetitive conduct directed towards

accomplishing that unlawful purpose; (3) there was a dangerous

probability that Edison would succeed in its endeavors: and

(4) Vernon suffered causal antitrust injury. See California Com-

puter Products, Inc. v. IBM Corp., 613 F.2d 727, 736 (9th Cir.

1979).

5.3 To show that Vernon’s claims constitute § 2 violations

under either theory, Vernon must show that these claims consti-

tute anticompetitive conduct that caused antitrust injury to

Vernon.

5.4 In its Foreclosure Motion, Edison assumed, solely for the

purposes of the Foreclosure Motion, that there was competition

between Edison and Vernon, that Edison had monopoly power in

a properly defined market, and that Edison’s transmission lines

are essential facilities. For the purpose of ruling on this Foreclo-

sure Motion, the Court also makes these assumptions, and makes

no findings and has reached no conclusions on the issues of

competition, monopoly power, or essential facilities.

5.5 In regard to the issue of whether Edison’s transmission

lines are essential facilities, the Court finds that there are factual

questions on this issue, and that such factual questions required

the denial of Vernon’s Motion for Partial Summary Judgment on

the Essential Facilities Claim (Vernon’s “Essential Facilities

Motion”’). The Court notes, however, that credible arguments can

be made that Edison’s transmission facilities are not essential

facilities within the meaning of the antitrust laws.

5.6 With respect to the issue of franchise competition, the

Court finds that there are factual questions and that such factual

questions required the denial of Vernon’s Motion for Partial

Summary Judgment on the Franchise Competition Claims

(Vernon’s “Franchise Competition Motion’’).

40

6. ANTITRUST OBLIGATIONS IMPOSED UPON A

COMPANY WITH MONOPOLY POWER

6.1 There is no general unqualified duty for a firm possessing

monopoly power to cooperate with its business rivals. Aspen

Skiing Co. v. Aspen Highlands Skiing Corp., 472 U.S. 585, 600.

6.2 A monopolist has no duty to reduce its prices in order to

help consumers, Berkey Photo, Inc..v. Eastman Kodak Co., 603

F.2d 263, 294 (2d Cir. 1979), cert. denied, 444 U.S. 1093 (1980),

or any obligation to extend a helping hand to new market entrants

or to help its competitors survive or expand their businesses,

California Computer Products, Inc. v. IBM, supra, 613 F.2d at

744.

6.3 As the Ninth Circuit has recently acknowledged:

[I]t is consistent neither with Berkey Photo nor with the

body of antitrust law as a whole to say that a holder of lawful

monopoly power must passively concede every time someone

else demands the right to do some portion of what that firm

does, regardless of whether the services at issue are per-

formed within the scope of the lawfully acquired monopoly

and regardless of whether the ‘monopolist’ is merely con-

ducting itself in a way that any other (non-monopolist) firm

would under the circumstances.

Catlin v. Washington Energy Co., 792 F.2d at 1347, quoting

Grason Electric Co. v. Sacramento Mun. Utility Dist., 571

F. Supp. 1504, 1517 n.17 (E.D. Cal. 1983).

6.4 There are certain occasions, however, when a court will

impose affirmative obligations on a monopolist. See, e.g., Aspen

Skiing Co. v. Aspen Highlands Skiing Corp., 472 U.S. at 601.

Where the monopolist’s competitor is the monopolist’s customer

as well, the antitrust laws may impose duties on the monopolist to

ensure that the monopolist’s conduct does not unjustifiably impair

its customer’s ability to compete. See Olympia Equipment Leas-

ing, 797 F.2d at 376; Oahu Gas Serv., 838 F.2d at 368.

6.5 Although affirmative duties are imposed on a monopolist,

“[t]hese duties are not absolute, however, they arise only when

there is no justification for refusing to aid a competitor.” Oahu

i

4]

Gas Service, supra, 838 F.2d at 368; Aspen Skiing, supra, 472

U.S. at 604-05. Thus, even if the monopolist has affirmative

duties to its competitors, if the monopolist had a legitimate

business justification for its conduct, the plaintiff cannot prevail

on its claim of a violation of § 2. See, e.g., Oahu Gas Service,

supra, 838 F.2d at 368; Image Technical Service, Inc. v. Eastman

Kodak Co., 90 Daily Journal D.A.R. 4702, 4705 (9th Cir. 1990);

Theee Movies of Tarzana v. Pacific Theatres, Inc., 828 F.2d 1395,

1400-1401 (9th Cir. 1987), cert. denied, 108 S. Ct. 1028 (1988).

See also, Universal Analytics, supra, 707 F. Supp. at 1180.

6.6 Under this standard, even the presence of a predatory

motive “will not make otherwise lawful conduct (i.e., conduct

engaged in for a legitimate business purpose) unlawful.” Univer-

sal Analytics, supra, 707 F. Supp. at 1180 (citation omitted). As

the Ninth Circuit in Oahu Gas Service stated:

Where a monopolist’s refusal to aid a competitor is based

partially on a desire to restrict competition, we determine

antitrust liability by asking whether there was a legitimate

business justification for the monopolist’s conduct. See Aspen

Skiing Co. v. Aspen Highlands Skiing Corp., 472 U.S. 585,

105 S. Ct. 2847, 86 L.Ed.2d 467 (1985): Dimidowich v. Bell

& Howell, 8Q3 F.2d 1473, 1478 (9th Cir. 1986)>Drinkwine v.

Federated Publications, Inc., 780 F.2d 735, 740 (9th Cir.),

cert. denied, 475 U.S. 1087, 106 S. Ct. 1471, 89 L.Ed.2d 727

(1986).

Oahu Gas Service, supra, 838 F.2d at 368.

6.7 Under this view of the legitimate business justification

defense, the Ninth Circuit has found a variety of conduct not to

be in violation of the antitrust laws. See, e.g, Oahu Gas Service,

838 F.2d at 360 (monopolists-suppliers’ decision not to expand

refinery justified where investment required would have resulted

in negative return because of price controls); The Jeanery, Inc. v.

James Jeans, Inc, 849 F.2d 1148, 1159-60 (9th Cir. 1988)

(improvement of the defendant’s distribution network); Mozart

Co. v. Mercedes-Benz of North America, Inc., 833 F.2d 1342,

1349 (9th Cir. 1987), cert. denied, 109 S. Ct. 179 (1988)

(“Mozart”) (quality control over the products and services pro-

42

vided by the defendant); Drinkwine v. Federated Publications,

Inc., 780 F.2d 735, 740 (9th Cir. 1985), cert. denied, 475 U.S.

1087 (1986) (same).

7. THE CONDUCT CHALLENGED BY VERNON DOES

NOT VIOLATE § 2 OF THE SHERMAN ACT

(a) Vernon's Relative Size Share Access Claim —

7.1 Even assuming that Edison has monopoly power and

viewing Edison’s transmission facilities and nights as an “essential

facility”, Vernon cannot sustain its allegations of an antitrust

violation premised on Edison’s refusal to provide relative size

share transmission access. Under the essential facilities doctrine,

Edison is only required to give Vernon reasonable access to its

transmission network. See, e.g., Southern Pacific Communications

Co. v. AT&T Co., 740 F.2d at 1009; In Re Air Passenger

Computer Reservations Systems Antitrust Litigation, 694

F. Supp. 1443, 1451 (C.D. Cal. 1988). Reasonable access does

not include that which would harm Edison’s other customers or

~which would be impractical. Southern Pacific Communications

Co. v. AT&T Co., supra, 740 F.2d at 1009, quoting Hecht v. Pro-

Football, Inc., 570 F.2d 982, 992-93 (D.C. Cir. 1977), cert.

denied, 436 U.S. 956 (1978).

7.2 Moreover, even complete denial of access to an essential

facility is not an antitrust violation where there is-a tegitimate

business justification for the denial. See, e.g. Image Technical

Service, Inc. v. Eastman Kodak Co., supra, 90 Daily Journal

D.A.R. at 4705; Becker v. Egypt News Co., Inc., 713 F.2d 363,

366 (8th Cir. 1983); Venture Technology Inc. v. Nat'l Fuel Gas

Co., 1980-81 Trade Cas. (CCH) ¥ 63,780, at 78-169 (W.D.N.Y.

1981), rev'd on other grounds, 685 F.2d 41 (2d Cir.), cert. denied,

459 U.S. 1007 (1982).

7.3 Under the standards articulated in the foregoing cases,

Edisen’s failure to allow Vernon “relative size share” access to

Edison’s EHV lines is not unlawful anticompetitive conduct.

Vernon has conceded that if Edison granted Vernon the access it

has demanded, the costs for Edison’s other customers would

increase. Even assuming competition exists between Edison and

43

Vernon, Edison is not obligated by the antitrust laws to confer a

benefit on Vernon at the expense of its own customers. Town of

Massena v. Niagara Mohawk Power Corp., 1982-82 Trade Cases

(CCH) ¥ 63,526 (N.D.N.Y. 1980), see also, Hecht, 570 F.2d at

992-93 (“antitrust laws do not require that an essential facility be

shared if such sharing would be impractical or would inhibit the

defendant’s ability to serve its customers adequately”).

7.4 Edison’s justification for not granting Vernon relative size

share access is distinguishable from that proffered by the utility,

and rejected by the Supreme Court, in Otter Tail Power Co. v.

United States, 410 U.S. 366, 372 reh'g denied, 411 U.S. 910

(1973). In Otter Tail, the Court addressed a situation where the

Otter Tail Power Company had refused to sell wholesale power to

municipal systems and refused to wheel power as well. Otter

Tail’s total refusats were motivated by an intent to retain the

municipals as -all-requirements customers. This result was

achieved by these absolute refusals to deal on an “essential

facility.” Otter Tail did not argue that it lacked excess transmis-

sion Capacity to provide transmission service or that its transmis-

sion system could not accommodate new imports wheeled into its

municipal customers. Otter Tail’s only justification for its refusals

to deal was the desire to keep its municipals (and future

municipals) as captive customers.

7.5 The facts now before this Court are not analogous to

those of Otter Tail. First, Edison has not refused to sell wholesale

power to Vernon. Edison has had in place a partial requirements

_ resale rate and there is no evidence that Edison ever threatened,

or even suggested, that it would terminate that service. Second,

Edison has not refused to wheel power to Vernon. As is stated

above, Edison has provided Vernon with significant transmission ~

service (or “wheeling”) for outside resources, and as a result,

Vernon is now buying relatively little power from Edison. Most of

Vernon’s power needs are being met from- outside resources

“wheeled” to Vernon’by Edison. Third, Edison’s denial of access

to its transmission system was motivated by a desire to benefit its

own customers rather than just Vernon. This is a legitimate

business justification.

44

7.6 As a matter of law, Edison’s conduct with respect to

transmission has not been unreasonably exclusionary.

(b) Vernon's IOA Claim

7.7 The issue in regard to the IOA claim is not whether

Edison can foreclose access to outside resources since it is clear

that Edison has offered Vernon an IOA and access to outside

resources. An IOA and access has been made available to Vernon

on the same terms and conditions as for the other Resale Cities;

Vernon made a decision to restrict its owr IOA to its Palo Verde

purchases.

7.8 As with Vernon’s demand for relative size share access, to

the extent that Edison had a duty to integrate Vernon’s power

purchases, that duty is not absolute; it is limited “by Edison’s

legitimate business justifications.

7.9 Even assuming an obligation of Edison to furnish a

different IOA than what was actually offered to Vernon, the

Court concludes that Edison had a legitimate business justifica-

tion for not providing Vernon with an IOA with only an 18-month

notice period for capacity additions to the Edison control area.

-7.10 The Court further notes that Vernon has previously

asserted, and the FERC has concluded, that a three-year notice

~ period is appropriate, and hence antitrust liability cannot be

premised in this action based upon an IOA that has only an 18-

month notice period.

7.11 Vernon’s damage study improperly assumes that the

failure of Edison to provide an IOA with an 18-month notice

provision was unlawful, since the failure to provide Vernon with

an IOA with an 18-month notice provision is not an antitrust

violation.

712 Vernon has presented no evidence which raises a iniable

issue of fact with respect to the IOA. »

(c) Vernon's Special Condition 12 Claim

7.13 In that the Court has concluded that there is and has

been a legitimate business justification for Edison refusing to

45

allow the import of capacity resources into the Edison control

area on less than three-years’ notice, the Court further concludes

that Edison was under no obligation under the antitrust laws to

offer Special Condition 12 to Vernon.

7.14 Vernon’s Special Condition 12 claim is analogous to that

raised by the plaintiff in Olympia Equipment Leasing Co. v.

Western Union Telegraph Co., supra, 797 F.2d at 376, and was

rejected by the court in that case. In Olympia, the plaintiff alleged

that Western Union’s withdrawal of assistance in marketing telex

equipment constituted a Sherman Act § 2 violation. The court

rejected the plaintiff's contention. Reasoning that a monopolist

has no generalized duty to extend a helping hand to its competi-

tors. The court concluded that Western Union’s withdrawal of

voluntary assistance could not possibly constitute a § 2 viofation.

7.

If a monopolist does extend a helping hand, though not

required to do so, and later withdraws it as happened in this

case, does not incur antitrust liability? We think not..

Since Westen Union had no duty to encourage the entry of

new firms into the equipment market, the law would be

perverse if it made Western Union’s encouraging gestures

the fulcrum of an antitrust violation.

Id., 797 F.2d at 376.

7.15 This rationale applies equally to Vernon’s contentions

concerning the availability of Special Condition 12. Here, Edison

had no duty under the antitrust laws to provide Special Condition

12 treatment to Vernon. Having no such obligation, its failure to

provide Special Condition 12 earlier than it actually did cannot be

the basis of a § 2 violation.

7.16 The Court concludes that Edison had a legitimate busi-

ness justification for not implementing Special Condition 12

earlier than it did.

7.17 Vernon’s damage study improperly assumes that the

failure of Edison to initiate Special Condition 12 earlier than it

did was unlawful, since the failure to initiate Special Condition 12

earlier was not an antitrust violation.

46

7.18 Vernon has presented no evidence which raises a triable

issue of fact with respect to Special Condition 12.

7.19 Because two of Vernon’s damage scenarios are predi-

cated upon the existence of Special Condition 12 years before it

was actually offered, the conduct underlying these scenarios is not

a violation of § 2 of the Sherman Act.

(d) Vernon's Interruptible Transmission Service Claim

7.20 The granting of summary judgment with respect to

Vernon’s contentions based upon purportedly improper denials,

interruptions, or curtailments of ITS for nonfirm energy is man-

dated on three separate grounds.

7.21 First, Vernon has failed to quantify any damages arising

from any of these interruptions. As the Court explained in its

“Memorandum of Decision” (at 14-16), a plaintiff must show

some measurable damages flowing from an antitrust injury in

order to meet the requirements of § 4 of the Clayton Act, 15

U.S.C. § 15. Vernon has failed to make this showing.

7.22 Second, Vernon’s concerns in regard to interruptions at

best involve the interpretation of contract language giving Edison

discretion as to when interruptions can be made. A contractual

dispute as to the reasonableness of conduct is not enough to

support an antitrust claim. See Universal Analytics, supra, 707

F. Supp. 822, 828 (N.D. Cal. 1986). See, also, Colorado Inter-

state Gas Co. v. Natural Gas Pipeline Co., 19892 Trade Cas.

(CCH) § 68,751, at 61,950 (10th Cir.).

7.23 Third, the Court concluded that Vernon has failed to

demonstrate that Edison’s reasons for interrupting were not

legitimate.

~ 8 THE CHALLENGED CONDUCT VIEWED SEPA-

RATELY AND AS A WHOLE

8.1 In examining Edison’s conduct that is alleged to give rise

to damages, the Court has concluded that the challenged conduct

does not constitute a violation of § 2 of the Sherman Act. None of

the challenged conduct individually amounts to an antitrust

p

47

violation and viewing the conduct in its totality does not change

any of the conclusions as to the propriety of the conduct.

8.2 At times in its opposition, Vernon argued that a number

of other Edison alleged acts or conduct constituted evidence of

violations of the antitrust laws. Vernon, however, failed to link any

of these other alleged acts to any quantifiable damages, and

Vernon makes no claim of damages or injury arising from these

alleged acts. Nor has Vernon presented any arguments to demon-

Strate that any such acts or conduct has any sort of synergistic

effect when viewed as a whole.

8.3 Accordingly, for the reasons set out at pages 19-20 of the

Court’s Memorandum of Decision, the Court concludes that

summary judgment in favor of Edison and against Vernon is

appropriate.

9. CONCLUSIONS

9.1 To the extent that the foregoing Conclusions of Law are

also Statements of Fact, they are intended to be Findings of Fact

as well.

9.2 Defendant Edison is entitled to summary judgment on

Vernon’s foreclosure damage claims in this action.

9.3 Having granted summary judgment in favor of defendant

Edison and against plaintiff Vernon on all damage claims in this

action and made the above stated Findings and Conclusions, the

Court asked plaintiff Vernon to advise the Court of what re-

mained for trial. Vernon advised the Court that the foregoing

Findings of Fact and Conclusions of Law address and dispose of

all remaining claims of Vernon herein, including those in Claim I

of the First Amended Complaint for which Vernon is seeking

relief. As a consequence, judgment in this action should now be

entered in favor of defendant Edison and against plaintiff Vernon,

with Edison to recover its costs of suit herein. -

Dated: August 30, 1990

MARIANA R. PFAELZER

Mariana R. Pfaelzer

United States District Judge

48

CERTIFICATION OF SERVICE

I hereby certify that I have served the foregoing APPEL-

LANT’S DOCKET SHEET on all parties of record in this

proceeding, Civil No. 90-56281, by placing a copy of the docu-

ment in a properly addressed envelope and sending by overnight

courier to the following parties or attorneys of parties:

Paul G. Bower, Esq.

Gibson, Dunn & Crutcher

2029 Century Park East

Suite 3860

Los Angeles, California 90067-3026

DATED: December 12, 1990

JOSEPH J. OMALLEY

Joseph J. O’Malley

Attorneys of Record for

Plaintiff-Appellant City of Vernon

49

CASE NO. CV 83-8137 MRP

UNITED STATES DISTRICT COURT

CENTRAL DISTRICT OF CALIFORNIA

CITY OF VERNON, CALIFORNIA,

Plaintiff,

i

SOUTHERN CALIFORNIA EDISON COMPANY,

Defendant.

JUDGMENT

The Court having granted Edison’s Motions for Summary

Judgment on plaintiff's foreclosure claims, rate claims and group

boycott claims, and having filed its Memorandum of Decision and

Findings of Fact and Conclusions of Law thereon, and the issues

having been duly heard and a decision having been duly rendered,

IT IS HEREBY ORDERED AND ADJUDGED that the

plaintiff City of Vernon take nothing in this action, that this

action be dismissed on the merits and with prejudice, and that

defendant Southern California Edison Company shall recover

from plaintiff City of Vernon its costs in this action in the amount

of $

DATED: August 30, 1990

Mariana R. Pfaelzer

United States District Judge

50

GIBSON, DUNN & CRUTCHER

PAUL G. BOWER

ARTHUR L. SHERWOOD

RICHARD D. HALL

333 South Grand Avenue

Los Angeles, California 90071

(213) 229-7000

David N. Barry, III

RICHARD K. DURANT

JANET K. LOHMANN

2244 WALNUT GROVE AVENUE

ROSEMEAD, CALIFORNIA 91770

(818) 302-3844

Attorneys for Defendant

Southern California Edison Company

NO. 83-8137-MRP (MCX)

UNITED STATES DISTRICT COURT

CENTRAL DISTRICT OF CALIFORNIA

CITY OF VERNON,

Plaintiff,

Vv.

SOUTHERN CALIFORNIA EDISON COMPANY,

Defendant.

ORDER DENYING VERNON

MOTION FOR RECONSIDERATION

HEARING: October 15, 1990

10:00 a.m.

Courtroom of the Honorable Mariana R. Pfaelzer

TRIAL DATE: None

The motion of plaintiff City of Vernon “For Reconsideration of

this Court’s Granting of Defendant Southern California Edison

Company’s Motion for Summary Judgment on Plaintiffs Fore-

closure Damage Claims” (the “Motion”) came on for hearing

5]

before the Court on October 15, 1990, with counsel for both

parties appearing. After hearing and considering the arguments of

counsel and the papers filed in connection with this Motion, and

the Court having determined that there is not good cause for the

granting of the Motion, the Motion of the plaintiff City of Vernon

is hereby denied.

DATED: October 22, 1990

Mariana R. Pfaelzer

United States District Judge

PREPARED AS TO FORM:

GIBSON, DUNN & CRUTCHER

PAUL G. BOWER

ARTHUR L. SHERWOOD

RICHARD D. HALL

DaAvID N. Barry, III

RICHARD K. DURANT

JANET K. LOHMANN

By

Arthur L. Sherwood

Attorneys for Defendant

Southern California Edison Company

APPROVED AS TO FORM:

PAUL HASTINGS, JANOFSKY. &

WALKER

JOSEPH J. O’MALLEY

By

Joseph J. O’Malley

Attorneys for Planitiff

City of Vernon

§°

~

No. 90-1544

UNITED STATES COURT OF APPEALS

FOR THE DISTRICT OF COLUMBIA CIRCUIT

September Term, 1990

SOUTHERN CALIFORNIA EDISON COMPANY,

Petitioner

VS.

FEDERAL ENERGY REGULATORY COMMISSION,

Respondent

FILED July 5, 1991

ORDER

Upon consideration of petitioner's motion for voluntary dismis-

sal and it being represented that no opposition thereto will be

filed, it is

ORDERED that petitioner’s motion be granted. The Clerk is

directed to send a certified copy of this order to respondent in lieu

of formal mandate.

FOR THE COURT:

Constance L. Dupré, Clerk

By: /s/ MARYANNE McMAIN

MaryAnne McMain

Deputy Clerk

53

[27 FERC { 63,053]

Southern California Edison Company, Docket No. ER81-177-

002 (Phase II) Initial Decision

(Issued May 18, 1984)

Jacob Leventhal, Presiding Administrative Law Judge

Procedural History

The genesis of this proceeding lies with a rate increase tendered

for filing by Southern California Edison Company (Edison or

Company) on December 16, 1980.... The instant proceeding,

entitled Phase II, was severed from the general rate filing after

Vernon’s request for phasing, dated March 17, 1982. was granted

on May 3, 1983....

Essentially, Phase II was established to determine the reasona-

bleness of the Integrated Operations Agreement (IOA), a series

of identical agreements which Edison has entered into indepen-

dently with Cities. The IOA is a document which enumerates the

services to be provided by Edison to its customers and dictates the

terms and conditions of those services. Acceptance of the IOA

has been treated by Edison as a condition precedent to a cus-

tomer's receipt of partial-requirements service. Vernon does not

presently receive such service but is desirous of becoming a

partial-requirements customer of Edison’s. Vernon, however,

takes issue with the terms of the IOA proffered by Edison in

return for rendering the partial-requirements service. Vernon

maintains that this JOA, which is identical to those already in

existence with Cities, contains provisions which are unreasonable

and onerous. Cities have joined with Vernon in requesting a major

alteration of the IOA.

54

[65,195]

Il. Amount of Energy Available Under Scheduled TOU-R When

a City Capacity Resource Is Not in Operation

The Joint Statement of Issues (Exhibit 302) poses the issue as

follows:

Is the method in the IOA for establishing the responsibility

for meeting a city’s load requirements a fair and reasonable

approach, or does this method result in unfair and unreason-

able restrictions on the amount of energy which can be

purchased by : a city under Schedule TOU-R?

This issue involves Sections 15.1.2, 16.2, and 16.2.2.1 of the

Integrated Operations Agreement (IOA). The Cities, who are

signatories of the IOA, and Vernon, which is not a signatory,

Suggest an amendment of the terms of these sections on the

ground that they result in an unjust, unreasonable, and discrimi-

natory rate. The problem, more concisely, concerns the provisions

of these sections which provide that the amount of energy

available to a city each hour under the partial-requirements rate

schedule TOU-R shall be the total energy requirement of the city

during that hour reduced by the greater of (i) the energy during

that hour from the city’s integrated resources, or (ii) the amount

of energy capability associated for that hour with the then

effective capacity credit.

Under the terms of the IOA, a city’s own generation units are

integrated with Edison’s capacity. The capacity credit is calcu-

lated by taking the rated capability of those units and reducing it

by the amount of reserve the city contributes to the Edison

system.

The critical problem arises when a city’s generating facilities

are closed down for periodic maintenance, repair, or any other

reason. Then, the JA provides that the city shall purchase from

Edison “contract energy.’ Contract energy is based upon the

incremental costing concept which assumes that the use of

Edison’s facilities consumes the most expensive fuel.

55

According to Edison, the IOA divides the load of a city into

two parts with the capacity credit as the dividing line. Up to the

limit of its capacity credit, the city is responsible for supplying its

own energy needs. If it cannot do so, then it may either replace

the energy from

[65,196]

some other source or purchase contract energy from Edison. This

is a below-the-line transaction.

For energy requirements above the Capacity credit, the city is

charged on an average cost basis. This is an above-the-line

transaction.

Edison defends this practice on the ground that the city is not

paying a demand charge for energy within the limits of its

Capacity credit. If this provision were to be eliminated, Edison

asserts that the cost of maintaining the utility’s capacity would be

passed on to other customers and therefor would be unfair.

* * *

[65,197]

+ * o

Ruling

. * *

Thus the question is: Do the partial-requirements customers

taking energy under the IOA and the TOU-R schedule pay the

demand charge associated with the Capacity credit?

The testimony and the briefs deal with the issue at some length.

However, at the core of the controversy is whether the demand

charge paid by the partial-requirements customers under the IOA

and the TOU-R schedule include Capacity required to replace the

Customer’s own generation for which it has received a Capacity

credit. If a demand charge has been paid, the customer is entitled

to the energy up to the limit of the demand at average system

cost.

56

I agree with Staff that the partial-requirements customer

should be able to purchase the maximum amount of energy

[65,198]

each hour associated with the maximum demands it imposes on

the Edison system as reduced by the capacity credit it receives. I

similarly agree with Staff that incremental pricing is appropriate

for customers who have not paid their fully allocated costs.

* * *

Edison attempts to distinguish the present proceedings from

either Kansas or Northern. Edison argues that the latter case

involved a true capacity reservation which prompted the Judge to

find that the limitation was not cost justified and would result in

an overrecovery of energy costs. However, the decision also

turned on the proposition that a customer is entitled to the energy

for which a demand charge has been paid.

The argument made by Edison that Northern involved another

type of capacity reservation is also not convincing. Although the

details of the tariff provision differ from those in the present

proceeding, the principle enunciated is the same. If the partial-

requirements customer pays demand charges on the same basis as

the full-requirements customer, it should be entitled to the same

energy charges up to the limit of the demand charge.

Edison has complete control of the dispatch of Cities’ generat-

ing units since their units are integrated with Edison’s units.

Edison operates the Cities’ units according to control area re-

quirements. Edison does not schedule power to the Cities like it

does with utilities outside its control area. (Ex. 367-T at 9-11.)

Since Edison does not operate Cities’ generating units according

to Cities’ requirements, its premise that the IOA’s capacity credit

provision changes the character of the Cities-Edison relationship

is not accurate. In reality, Cities’ relationship with Edison is

always that of a utility-customer and never one of utility-to-

utility. Edison is responsible for supplying all of Cities’ energy

needs — and thus all energy within the limit of the demand

charge should be supplied on an average cost basis.

57

The Cities, with generation, are in fact full-requirement cus-

tomers, and they are properly receiving the same TOU-R rate as a

customer without generation. Granting a demand credit for the

use of a City’s generating unit does, by definition, classify it as a

partial-requirements customer, but only on paper. In Northern

and Kansas, the Cities there operated their generation indepen-

dently of the suppliers. A partial-requirements customer of

Edison does not truly operate its generation as baseload or

peaking since Edison has complete control over the customer’s

generation. Edison operates these units as if they were owned by

Edison. (Id. at 9.) For the use of that generation, the Cities

obtain a credit against its demand charge. But all of a city’s load is

part of the control area load, whether or not it has its own

generation, and Edison is responsible for the entire control area

load.

I find that adoption of Staffs Proposal will eliminate the

undesirable portion of the IOA relating to this issue.

III. City Contribution to Installed Reserves

Section 12.2 of the IOA provides that the city’s contribution to

installed capacity reserves (expressed as a percent of the rated

capability of the city’s capacity resources) is determined annually

and shall be equal to the average of the five annual reserve

margins (expressed as a percentage of annual peak) of the

combined firm loads of the parties planned for the next five years.

* * *

The nub of the dispute is really whether the price the Cities are

paying for the service received is higher than warranted. Under

the

[65,199]

IOA, a city’s TOU-R billing demand is reduced by a capacity

credit. This credit is computed by subtracting the reserve margin

from the rated capability of the city’s generation. Thus, a higher

reserve margin results in a lesser capacity credit with a resulting

greater billing demand.

eT ae

58

Cities, Vernon, and Staff cbject to the method used and the

calculation of the reserve margin for a city. The opposition notes

that for its own reserve, Edison uses 18%+ or —2% applied to its

load to convert the percent reserve to kilowatts. The Edison

percentage is a target reserve used for planning, not billing. On

the other hand, the projected reserve percentage directly affects

the capacity credit and consequently the cost of energy to the

cities. Thus, they and Staff contend that for billing purposes a

precise standard is needed for application to the cities. They

propose a flat eighteen percent, the center point of the band used

by Edison for its own reserve calculation. The eighteen percent is

to be applied to the city’s load, not capacity. If conditions change,

as it is recognized could occur, the reserve margin can be

amended in future rate proceedings. (Staff 1.B. at 41-45.)

* + *

Ruling

[65,200]

he formula used to convert percent reserve requirements to

kilowatts should be the same for a city as it is for Edison. Under

the proposal by Vernon, supported by Staff, the city’s capacity

credit is used as a proxy for the load of the resale city and thus

applies the percentage to the capacity credit. This is a reasonable

method and is adopted here.

The proposal by Cities, Vernon, and Staff for the application of

eighteen percent to the Cities’ load to ascertain the required

reserve margin leads to a reasonable result and is also adopted.

Section 12.2 will be amended accordingly.

* * *

[65,201]

VI. Qualifications for Integration of City Capacity resources

VII. Procedures for Integration of City Capacity Resources

VIII. Qualifications for Integration of City Transmissions

Facilities

59

Issues VI, VII, and VIII present questions as to the reasonable-

ness of various provisions of Section 8 of the Integrated Opera-

tions Agreement pertaining to the qualifications and procedures

for integrating city Capacity resources and transmission facilities.

Although these three issues have been individually briefed by

some of the parties, they will be discussed together under ihis

heading since they are similar in content.

[65,202]

Section 8.1.2.]

Section 8.1.2.1 is the first of these provisions to be discussed by

the parties. It reads as follows:

A City Capacity Resource Proposed by City shall be of

appropriate size, type, reliability, design and operating char-

acteristics and shall be capable of performing in a manner

equivalent to Edison Capacity Resources.

* * *

Ruling

Rather than clarifying the qualifications for integration of a city

capacity resource, Edison’s proposal would create more ambigu-

ity. Not only would it be extremely difficult to ascertain whether

the California standard has been met, as Vernon and Staff point

out, it does not add anything of value to “good utility practice.”

Section 8.1.2.1 as it stands now, is also unacceptable. It leaves to

much discretion in Edison’s hands for rejecting a proposed inte-

gration. At the same time it creates an undue burden on a City to

try to duplicate Edison’s facilities. Accordingly, the proposal put

forth by Staff, Vernon, and Cities is adopted.

* * *

... On balance, the existing provisions are not unfair and the

recommended changes are rejected.

| ae

60

Section 8.1.3.3

Section 8.1.3.3 is controversial for much the same reason as

Section 8.1. Section 8.1.3.3 states:

Within 60 days of the later of (i) receipt by Edison of the

information on a proposed City Capacity Resource pursuant

to Section 8.1.3.1 or (ii) the agreement on Transmission

Facilities as required by Section 8.1.2.5, Edison shall inform

City in writing as to its decision regarding acceptance for

integration of the proposed City Capacity Resource. If such

proposed City Capacity Resource meets the qualifications for

integration, Edison shall use its best efforts to integrate the

proposed City Capacity Resource. If such proposed City

Capacity Resource meets the qualifications for integration,

Edison shall use its best efforts to integrate the proposed City

Capacity Resource. If Edison concludes that the proposed

City Capacity Resource does not meet the qualifications for

integration, Edison shall so inform City of Edison’s opinion

and shall, based upon Edison’s preliminary studies, fully state

in detail the reasons for its conclusion. Thereafter, within 30

days following a request by City, Edison shall make available

for examination by City, the plans and specifications for

similar Edison existing or planned capacity resources.

. * +

Ruling

The request that Edison “use its best efforts” to integrate be

deleted is granted for the same reason it was granted with respect

to Section 8.1. Its presence connotes an excessive amount of

discretion in the integration determination. However, there is no

merit to Vernon’s other complaints. The phrases objected to are

not onerous. Accordingly, Section 8.1.3.3 will remain in effect as

is, except that Edison’s obligation to integrate shall be absolute if

the proposed city capacity resource meets the qualifications for

integration.

* * *

[65,208]

+ * w

61

[65,212]

XIII. Peaking and Intermediate Capacity

Issue XIII has been set forth in the Joint Statement of Issues

as follows:

Whether the IOA should be revised to cover the City’s

peaking and/or intermediate generating facilities and, if so,

what the revision should be.

This issue has arisen due to the IOA’s failure to provide for

peaking or intermediate generating facilities, stemming from its

inability to differentiate between baseload, intermediate, and

peaking units.

Cities, Staff, and Vernon are in accord that the root of the

problem lies with the energy restrictions imposed by IOA Section

15.1 and the contract energy provision in Section 16.2. Accord-

ingly, they all agree that the modifications to the above IOA

sections proposed in Issues II and IV would alleviate the flaws

addressed under this heading as well.

Edison, while apparently conceding that a revision is required

in order to allow a city to make economic use of peaking and

intermediate facilities, disagrees with the solution offered by

Cities, Staff, and Vernon.

* * *

The opposition of Cities, Vernon, and Staff is well taken. The

rulings made on Issues II and IV dispose of the problem posed

here. Edison is urging the addition of a new section to the IOA by

the adoption of one of three alternative Suggestions. They main-

tain, and I agree, that the problem has become moot. Further

change is not necessary.

The proposed addition to the IOA sponsored by Edison is

rejected.

62

Findings and Conclusions

Upon consideration of the evidentiary record and the briefs in

this proceeding, it is found and concluded:

(1) Southern California Edison is a public utility under the

Federal Power Act.

(2) The Integrated Operations Agreement herein involve sales

of electric energy and are subject to the junsdiction of this

Commission.

(3) The sections of the Integrated Operations Agreement shall

be modified in compliance with the rulings made in this decision.

(4) The terms and conditions of service contained in the

agreements as modified by the rulings made above have been

shown to be just and reasonable and otherwise lawful.

[41 FERC { 61,188]

Southern California Edison Company, Docket No. ER81-177-

002 (Phase II)

Opinion No. 289; Opinion and Order on Initial Decision

(Issued November 19, 1987)

Before Commissioners: Martha O. Hesse, Chairman; Anthony

G. Sousa, Charles G. Stalon, Charles A. Trabandt and

C. M. Naeve.

{ Note: Initial Decision of the Presiding Administrative Law

Judge, issued May 18, 1984, appears at 27 FERC 4 63,053]

[Opinion No. 289 Text]

1. Introduction and Summary

The case commenced on December 16, 1980, when Southern

California Edison Company (Edison) filed for a general rate

increase for firm service to its wholesale customers. Subsequently,

the proceeding was separated into two phases. Phase I involved

various cost-of-service and rate design issues.' The instant pro-

ceeding, Phase II, deals with the reasonableness of an Integrated

Operations Agreement (IOA) between Edison and certain mu-

nicipal customers.

63

The IOA is a generic agreement which the Cities of Anaheim.

Riverside, Banning, Colton and Azusa, California (Cities) have

each entered into as a Precondition to receiving partial require-

ments service from Edison under rate schedule TOU-R. The City

of Vernon, California (Vernon) has also been offered partial

requirements, integrated operations service similar to that pro-

vided to Cities, but disputes the reasonableness of the IOA which

has been offered to Vernon by Edison. Cities join Vernon in its

dispute with Edison over specific provisions of the generic IOA.

Cities’

[61,490]

existing IOAs with Edison allow them existing IOAs with Edison

allow them to: receive Capacity and energy credit for resources

they may integrate with Edison’s system; pay TOU-R rates when

these integrated resources meet defined availability, scheduling

and reserve requirements: purchase generally higher priced con-

tract energy” or replacement capacity when the integrated re-

source requirements are not met: Participate to some extent in

partial ownership of Edison’s new generating units; and receive

various other integrated operations services and rights. The IOAs

are intended to provide a practical procedure by which Cities can

meet some or all of their electric loads through acquisition of non-

Edison resources, while remaining within Edison’s control area.

Vernon is also eligible to receive partial requirements service

under rate schedule TOU-R. Vernon has not signed the same

type of “generic IOA” entered into by Cities, but does have a

resource-specific IOA with Edison for purposes of integrating its

interest in the Palo Verde Nuclear Generation Station.’ Addition-

ally, Vernon owns diesel generators which are nonintegrated and

operate on its side of Edison’s billing meters. Vernon does not

have a broad agreement with Edison for integrated operation of

other resources.

This proceeding is presently before the Commission on excep-

tions to an Initial Decision in Phase II.4 Briefs On and Opposing

Exceptions were filed by Cities, Edison, Vernon’ and the Commi-

sion trial staff (staff).

64

There are ten issues before the Commission on exceptions, as

follows:°

I. the standard and burden of proof to be applied in

modifying the IOAs;

II. the amount of energy available under Schedule TOU-

R when a City capacity resource is not in operation;

III. the City contribution to installed reserve;

IV. the energy dispatched by Edison from City’s reserve

capacity;

VI. the qualifications for integration of City capacity

resources,

VII. the procedures for integration of City capacity

resources;

VIII. the qualifications for integration of City transmis-

sion facilities;

IX. the replacement capacity;

XI. the contract energy pricing; and

XIII. the peaking and intermediate capacity.

II. Discussion

We affirm the Judge with additional discussion on Issues I and

II. We affirm the Judge on other grounds on Issue IV. We reverse

the Judge on Issues VII and XIII. We summarily affirm the

Judge on Issues III, VI, VIII, 1X and XI.

A. ISSUE I — The Standard and Burden of Proof to be

Applied in Modifying the IOAs

The issue presented is what standard applies when Edison’s

customers, i.e., Cities, seek to modify their executed contracts,

and who bears the burden of proof. We summarily affirm the

Judge’s ruling concerning the standard and burden of proof with

respect to Vernon. We also summarily affirm the Judge’s ruling

65

that Cities can challenge individual provisions of the IOA rather

than having to show that the IOA in

[61,491]

“its totality is unreasonable.”’ We affirm the Judge’s ruling on

Issue I subject to the following clarification of his discussion on

the Mobile-Sierra doctrine.*

Mobile-Sierra establishes the applicable standard governing

rate increases which may be allowed in cases where the utility and

the customer have entered into a contract in which the rate is

fixed for the life of the contract or some other specified period.

Under Mobile-Sierra, a utility with such a fixed-rate contract

cannot file for a rate increase’ under section 205 of the Act that is

contrary to the contract. It can obtain relief under section 206 of

the Act only if it can show that the rates under the contract are

“sO low as to adversely affect the public interest — as where it

might impair the financial ability of the public utility to continue

its service, cast upon other customers an excessive burden. or be

unduly discriminatory.”'°

The Judge stated that Cities “are required to show that the

provisions of the contract are not in the public interest because

the terms are unjust and unreasonable.”'' He ruled that the

Proper method of challenging Cities’ executed IOAs is under

section 206 of the Act where the burden is on Cities and staff as

complainants to establish a prima facie case that the provisions

are unjust and unreasonable. However, the Judge also ruled that

the ultimate burden of persuasion as to the justness and reasona-

bleness of the terms lies with Edison. !

* * *&

Edison states that the IOA provides only Edison with the

option, in limited circumstances, of seeking to modify the rates in

the IOA, and that there is no right reserved by either party to seek

modification of other provisions in the IOA. Edison argues that in

the absence of any reserved right to seek changes, the terms and

conditions of service may be modified only upon a showing that

they are against the public interest.

66

We do not agree. In determining the meaning of the contract,

general principles of contract interpretation apply. As the court

said in Papago Tribal Utility Authority v. FERC in a rate revision

contest, “‘[i]n the absence of ambiguity the intent of the parties

to a contract must be as ascertained from the language thereof

without resort to parol evidence or extrinsic circumstances.’ ”’°

The IOA does not contain any provision which indicates that

Cities waived their nght to seek modification of the IOAs’ terms

and conditions under section 206 of the Act.

[61,492]

We agree with the Judge that Cities and staff have the burden

of coming forward and establishing a prima facie case that the

provisions in the IOA are unjust or unreasonable. However, as the

Judge further correctly noted, section 206 of the Act does not

refer to burden of proof. Thus, it is controlled by section 556(d)

of the Administrative Procedure Act, which imposes the burden

on “the proponent of a rule or order,” but the burden imposed is

one of coming forward with a prima facie case, not the ultimate

burden of persuasion.” Therefore, once Cities and staff present a

prima facie case for relief, the burden shifts to the respondent

Edison to make a persuasive defense.”

B. ISSUE II — Amount of Energy Available Under Schedule

TOU-R When A City Capacity Resource Is Not In Operation

We affirm the Judge’s ruling on Issue II, with the following

discussion. The issue presented is whether the IOA piaces unjust

or unreasonable restrictions on the amount of energy which can

be purchased by a city under rate schedule TOU-R.

* * *

Edison also states that even if a city’s capacity resources were

idle during Edison’s monthly system peak hour, providing reduced

reliability benefits, in the next rate case Edison would not be able

to allocate additional demand costs to the wholesale class since a

city’s capacity credit is always subtracted from the class 12 CP

aia

67

demand for cost allocation purposes. Edison thus views its rela-

tionship with the partial

[61,493]

requirements cities as fundamentally different from that with its

other customers, warranting the pricing of energy corresponding

with idle city Capacity resources at incremental costs. What

Edison overlooks, however, is that a city contributes reserves

along with its capacity resources to compensate Edison for un-

foreseen and planned unit Outages.

Staff argues that the situation described by Edison is extreme

in that a city’s use of a disproportionately large amount of average

Cost energy would occur, if at all, only during relatively short

intervals. The existing IOA prices energy associated with any

unavailable city capacity, during every hour, at Edison’s incre-

mental energy cost. As stated by staff: “[W ]hile there is a kernel

of truth to Edison’s claim that staff's remedy is not totally perfect,

Edison’s alternative remains fundamentally unfair to the IOA

cities.””"* We agree, and believe that staff's proposed remedy to

this problem, adopted by the Judge, is the most reasonable one

presented in the instant proceeding.

C. ISSUE IV — Energy Dispatched by Edison From City's

Reserve Capacity

The issue presented is whether Edison derives a benefit from

energy associated with a city’s reserve Capacity that is not ade-

quately reflected in the IOA and, if so, whether revision of the

IOA is necessary. The Judge stated that Edison receives a cost

benefit” from dispatching a city’s reserve Capacity under the

IOA, but that the benefit has been virtually eliminated through

his ruling in Issue II. Furthermore, he stated that any residual

inequity would be de minimis.*° Although we agree with the

results of the Judge’s ruling, we do so on different grounds.

We agree with Vernon”’ that the J udge’s ruling on Issue II does

not moot Issue IV; however, we do not believe Vernon’s proposed

banking arrangement” is an appropriate remedy. For reliability

purposes, Edison must maintain at least a minimum reserve level

>

68

on its system. Under the IOA, a city is required to contribute

reserve capacity for resources integrated with Edison’s system, a

principle uncontested in this proceeding. Because it has adequate

system reserves, Edison can operate Cities’ resources, including

reserve capacity, to achieve a decrease in system energy costs.

The opportunity to realize this benefit, however, is derived from

the integrated operation of Edison’s control area. This savings

inures to the benefit of all Edison’s customers, including Cities.

Cities will reveive their pro rata share of the system energy

benefit.’ The proposed treatment of the energy benefit to

Edison’s system derived from operating a city’s reserve capacity is

thus reasonable under the IOA.

D. ISSUE VII — Procedures for Integration of City Capacity

Resources

Issue VII involves the appropriate time limit or standard under

which Edison must allow integration of a proposed city capacity

resource with its system. We reverse the Judge regarding sections

8.1.2.3, 8.1.2.4 and 8.1.2.6. We adopt a modified form of staff's

proposal to delete section 8.1.2.4 and revise sections 8.1.2.3 and

8.1.2.6.

Under section 8.1.2.4, a proposed city capacity resource must

be “compatible with (i) resources planned to serve the Edison

Control Area, (ii, the resource schedule, and (iii) other resource

plans periodically submitted by either party to regional agencies

and organizations.” Thus Edison may determine that a city’s

resource is unacceptable by merely altering its resource plan or

submitting other resource plans to unspecified “regional agencies

and organizations.” Section 8.1.2.3 states that integration of such

a proposed city capacity resource shall not require Edison to defer

a proposed capacity resource listed by Edison in the current

resource schedule for which Edison has made substantial financial

or other commitments towards construction, unless the parties

[61,494]

otherwise agree. This provision should be read in conjunction

with section 8.1.2.6, which states that the parties shall agree upon

— °°.

69

the date when such city Capacity resource shall first be included in

the resource schedule for planning purposes.

We agree with Vernon that these Provisions give Edison and

undue amount of discretion. Moreover, even if Edison does not

abuse its discretion, these provisions unreasonably place a city in

an uncertain situation, i.e., guessing whether and when Edison

will permit integration. An example illustrates the potential prob-

lem. Edison is not obligated to integrate a City capacity resource

when Edison’s own Proposed resource would be deferred as a

result. Thus, section 8.1.2.3 would require a city to defer the

resource even though Edison may have the flexibility to defer that

Project or a different project or to include in its plans additional

megawatts of capacity that had been contemplated for a slightly

later date. In short, the IOA would hold a city to a higher

Standard of planning than is normal industry practice. In normal

practice, projects are constantly being added, subtracted, de-

ferred, and accelerated, and the total Capacity available at a given

time is never precisely the capacity level that was previously

planned.

The IOA does not allow for the fact that a city’s involvement in

a project may typically occur at a different stage of project

development than Edison’s involvement. Edison will usually be

involved with a project from its conception. On the other hand, a

city cannot feasibly add Capacity in large increments and may

invest in projects that are already underway. Since the IOA does

not accommodate the difference in lead time inherent in the

difference in the Stage of project development, a city is at a

disadvantage when an attempt is made to coordinate integration

under the IOA with the commencement of a commercial opera-

tion of a generating facility. The result is that the IOA authorizes

Edison to subordinate a completed city project to an Edison

project that may still be in the early stages of development or

which may be deferred or never completed.?®

It is reasonable to maintain the “substantial commitment”

standard of section 8.1.2.3, but with a modification. As proposed

by staff, the IOA would provide a three-year notice for the

integration of a city capacity resource if the resource is less than

fifty percent of a city’s peak load, and a five-year notice if the

70

Capacity resource is greater than fifty percent of a city’s load and

one percent of Edison’s system load. A city seeking to diversify its

sources of capacity would generally make an impact on Edison’s

system of less than one percent of system load. Edison’s capacity

resource planning appears sufficiently flexible to accommodate

such a de minimis fluctuation in Edison’s system resources,

especially in light of a proposed three-year notice for the integra-

tion of a city capacity resource. Indeed, currently Edison requires

a three-year notice of termination for its full requirements cus-

tomers.*© Thus, if any of these customers turn to alternative

sources, Edison apparently believes that such a notice is sufficient

for its planning purposes. Consequently, under these circum-

stances staff's proposed three-year notice requirement for partial

requirements customers who intend to acquire and integrate a

capacity resource®’ is reasonable. However, we find that the

record does not support staff's further proposal that under certain

load conditions a more protective five-year notice provision is

appropriate.

E. ISSUE XIII — Peaking and Intermediate Capacity

The issue presented is whether the IOA should be revised to

specifically address a city’s peaking and/or intermediate resources

and, if so, what the revision should be.

[61,495]

On exceptions, Vernon and Edison claim that the instant

problem is not moot, as stated by the Judge. However, both

Vernon and Edison endorse the concept of voluntary negotiations

ragarding this problem. Furthermore, Vernon, Cities and Edison

note that this issue is before the Commission in Docket No.

ER84-75-000, and can be pursued in that proceeding.

Edison has presented three possible approaches to revising the

IOA to cover a city’s peaking and intermediate generating

facilties.”

As one option, a city may wish to acquire a peaking or

intermediate facility which it dispatches itself on its side of the

meter, after giving Edison adequate notice of the acquisition. The

71

record shows that Edison has an arrangement with Vernon for

operation of its diesel generating units on Vernon’s side of the

4)

meter.

As a second option, a city may wish to integrate a peaking or

intermediate facility under the current IOA provisions. Edison

notes that this may be economically vaiable for a peaking facility

with low energy costs, such as a hydropower peaking resource. A

city would receive a capacity credit against its TOU-R demand

charge and receive the value of low cost energy generated by its

facility as an offset against TOU-R energy charges.

As a third option, a city would receive Capacity credit for a

peaking facility, but its exposure to purchasing contract energy

would be limited. A city would only be obligated to pay incremen-

tal energy costs when its peaking unit was unavailable or un-

scheduled during designated and agreed upon peak hours, and

then only when a city load is above its base load Capacity credit

line and exceeds the rate of delivery of a city’s billing demand.

Overall, Edison states that Vernon is taking the unfair position

that a city should be able to integrate and receive Capacity credit

for intermediate and peaking facilities

[61,496]

without regard to whether such facilities would be useful and

needed in Edison’s control area. Edison claims that its offer to

voluntarily negotiate along the lines of its three proffered propos-

als provides a reasonable vehicle for resolution of this issue.

Edison submits that the Commission should correct the Judge

by noting that the problem is not moot in the instant proceeding.

Vernon indicates that a combination of adopting its recommenda-

tions under Issue IV and voluntary negotiations between the

parties is appropriate. Edison and Cities appear to prefer that the

issue be pursued in other dockets.

* * *

We reverse the Judge’s ruling that his holding on Issues II and

IV disposes of the issue here and that the issue is moot. We find

that this record does not present the substantial evidence neces-

72

~~

sary to modify the existing IOA to specifically address the

acquisition and operation of a city’s peaking and intermediate

resource. We note, however, that it appears that the parties are

pursuing Issue XIII through other Commission proceedings.”

The Commission orders:

(A) The Initial Decision issued in Docket No. ER81-177-002

(Phase II]) on May 18, 1984 is hereby affirmed and adopted

except to the extent modified or reversed herein. Exceptions to

the Initial Decision not granted in this Opinion are hereby denied.

(B) Within 45 days following the date of issuance of this

order, Edison shall file any necessary amendments to the subject

IOAs with Cities in accordance with the findings and conclusions

of this decision and with the Commission’s regulations. In the

event a request for rehearing is pending at the close of the 45-day

period, however, the aforementioned filing shall be made no later

than 30 days from the date the request for rehearing is disposed

of.

(C) Subdocket 002 of Docket No. ER81-177 is hereby termi-

nated. A new subdocket will be assigned to the compliance filing

ordered in Ordering Paragraph (B).

[ Footnotes Omitted ]

73

PUBLIC UTILITIES REPORTS — 122 PUR&4th

Re SCEcorp

Additional applicants: Southern California

Edison Company; San Diego Gas and Electric Company

Decision 91-05-028

Application 88-12-035

California Public Utilities Commission

May 8, 1991

ORDER disapproving a proposed merger between Southern Cali-

fornia Edison Company and San Diego and Electric Company.

2. The Commission's Review

Early in this proceeding, applicants contended that the pro-

posed merger’s impact on transmission access and competition in

bulk power sales markets were within the exclusive jurisdiction of

FERC. We reject this contention for reasons articulated twenty

years ago. Northern California Power Agency v. Public Util. Com.

5S Cal.3d 370 (1971), delcared:

It is no longer open to serious question that in reaching a

decision to grant or deny a certificate of public convenience

and necessity, the commission should consider the anti-trust

implications of the matter before it. The Commission itself

has stated: ‘There can be no doubt that competition is a

relevant factor in weighing the public interest’...

Although the commission is not bound by the dictates of

the antitrust laws, it is clear that antitrust concepts are

intimately involved in a determination of what action is in

the public interest, and therefore the commission is obligated

to weigh antitrust policy, [citations omitted.] ... This is not

to suggest, however, that regulatory agencies have jurisdic-

tion to determine violations of antitrust laws. [citations

omitted] Nor ar the agencies strictly bound by the dictates of

these laws, for they can and do approve actions which violate

74

antitrust policies where other economic, social, or political

considerations are found to be of overriding importance. In

short, the antitrust laws are merely another tool which a

regulatory agency employs to a greater or lesser degree to

give ‘understandable content to the broad statutory concept

of the public interest.’ [citations omitted ]

. * »

It is true that sections 4, 9, 15, and 15a of Title 15 of the

United States Code give the federal courts exclusive jurisdic-

tion over antitrust actions brought by the federal government

and over certain private suits under the federal antitrust laws.

However, those sections clearly do not foreclose the Com-

mission from consideration of antitrust matters... . (5

Cal.3d 377-378.)

. * *

As applicants note at OB, p. VI-27, we have used federal

precedents in the past, and do so in this decision, due to the

well-developed body of available federal antitrust authority.”

However, our decision making authority over this merger,

and its broad public interest aspects, is not so limited that it

must be premised on whether the acquisition violates federal

antitrust statutes.

246-247

We now review the historical examples addressed by the

parties.”

First, the evidence of Edison’s abuse of Interruptible Transmis-

sion Service (ITS) curtailment, provided by Edison’s former

Energy Control Center Senior Operations Supervisor McCann, is

not rebutted effectively by applicants. Applicants’ argument, that

Resale Cities benefit as Edison customers whenever Edison

curtails in order to take cost-effective firm or economy energy,

misses the point. Even if true, this justification ignores the

economic harm to Resale Cities, as retail competitors of Edison,

caused by the abuse of ITS curtailment procedures (McCann,

75

Exh. 44,100, pp. 24-30). It is precisely this type of competitive

harm, rooted in the competition between Edison and the Resale

Cities to obtain least cost resources to meet their retail customers’

needs, which must be assessed in the review of this merger’s

vertical impacts.

257

* * *

In connection with claimed line-loading problems which argua-

bly prevented Nevada Power from selling power to Vernon

(Attorney General’s Opinion, p. 30), the effect of Edison’s

actions was to shift a portion of the loop flow burden to NPC

while also precluding Vernon’s purchase from NPC.

258

In connection with Edison’s refusal to schedule nonfirm trans-

mission more than an hour in advance, it appears that Edison has

the ability to supply nonfirm transmission to the Resale Cities on

a prescheduled basis and that there is no Operational impediment

in issue. Edison would retain the ability to interrupt prescheduled

ITS to the same extent and on the same terms as interruptible

transmission provided on an hour-by-hour basis. The problem is a

refusal to provide for prescheduling by contract or otherwise.

Without the ability to preschedule, the Resale Cities cannot

compete meaningfully with Edison for nonfirm purchases

258

The real question is whether Edison has merely played “hard

ball’’ with the Resale Cities in the interests of its native load

customers, or whether at times it has crossed this line and has

used its transmission dominance to undercut the cities’ efforts to

lower costs to their retail customers. Based on the historical

evidence, it is reasonable to conclude the latter. In sum, these

76

historical examples demonstrate that Edison has used its strategic

control over transmission to the competitive disadvantage of other

utilities, who are buyers and sellers in the relevant interregional

transmission markets and in the network transmission market.

The then Attorney General is correct that it is reasonable to infer

that the merged utility, dominated by Edison, will continue

Edison’s past transmission access policies, unless effective mitiga-

tion measures are imposed.

A second issue bearing upon present circumstances is the

already heavily concentrated state of transmission markets, as

noted by DRA and the then Attorney General. The latter’s expert

testified that the majority of available capacity from the SW

during 1993 to 2000 is controlled by Edison. He asserts that this

control, combined with Edison’s transmission access policies, has

effectively forced other utilities to attempt to build new transmis-

sion lines not otherwise needed. The testimony that Edison

engineered the LADWP swap to remove LADWP as a partici-

pant in the Mead-Adelanto project, in order to prevent or hamper

construction of that line (Mays, RT 5126-30), is undisputed. This

is also disturbing because Mead-Adelanto is one of the planned

lines upon which Edison relies in countering adverse testimony

concerning its transmission access policies.

259

. ” .

Element No. 4, feasibility of access, raises issues discussed

previously in connection with native load customer demands. We

do not contemplate a requirement that applicants share an essen-

tiai facility it such sharing would be infeasible or otherwise would

inhibit their ability to serve customers adequately. It is true that

pro-competitive access to transmission lines must be tempered by

native load requirements. However, the record is undisputed that,

notwithstanding the demands and needs of native load customers

and the obligation to serve, the merger partners have historically

provided transmission access to others for purposes not related to

native load needs. Network facilities are built to serve Edison’s

77

entire service area load, including the load of the Resale Cities.

And, import transmission lines are built with a view to the needs

of total load area requirements, including those of the Resale

Cities. These determinations are consistent with previous findings

on the merger’s competitive impacts in the defined transmission

markets.

The fact that ratepayers may ultimately benefit from this

redistribution of wealth if the price of SW nonfirm bulk power is

depressed is not a justification for ignoring the cornpetitive injury

to the SW shot-term bulk power markets associated with the

exercise of buyer market power. Ratepayers may be short-term

winners, but will be long-term losers if there are adverse long-

term efficiency consequences of the merged company’s exercise of

buyer market power in this market. Therefore, it would be

shortsighted to ignore or minimize the consequences of the

exercise of buyer market power just because it may favorably

impact California ratepayers in the near term.

Findings of Fact

100. the effect of Edison’s actions in connection with the

claimed line-loading problems preventing Nevada Power from

selling power to Vernon, was to shift a portion of the loop flow

burden to NPC, while also precluding Vernon’s purchase from

NPC.

309

102. Edison has the ability to supply nonfirm transmission to

the Resale Cities on a pre-scheduled basis, and there is no

operational impediinent issue which would support Edison’s re-

fusal to schedule nonfirm transmission more than one hour in

advance; Edison would retain the ability to interrupt pre-sched-

uled ITS to the same extent and on the same terms as inter-

ruptible transmission provided on an hour-by-hour basis.

103. Without the ability to pre-schedule, the Resale Cities

cannot meaningfully compete with Edison for nonfirm purchases.

105. The above-noted historical examples demonstrate that

Edison has used its strategic control over transmission to the

competitive disadvantage of other utilities, who are buyers and

sellers in the relevant interregional transmission markets, and who

are located in the network transmission market.

106. Applicants do not dispute the fact that Southern Cities

have borne a proportionate share of the Pacific Intertic costs, as

well as the cost of Edison’s transmission facilities in general,

through their wholesale and fully-allocated transmission rates.

309

& * *

109. Edison controls the majfority of available [transmission ]

capacity from the SW during 1993 to 2000, and this control plus

Edison’s transmission access policies have effectively forced other

utilities to explore the construction of new transmission lines that

might not otherwise be needed.

310

* * *

117. Several new transmission lines currently under study will

not be constructed in sufficient time to constitute effective ease of

entry under § 3.3 of the Merger Guidelines; Edison is making no

effort to construct DPV2 prior to 1997, and seveal other lines are

either on hold or in the study phase (Mead-Phoenix, Mead-

Adelanto, and Utah-Nevada).

118. In the case of the Mead-Phoenix, Mead-Adelanto, and

Utah-Nevada proposed transmission lines, LADWP’s role is

crucial to the participation of the Resale Cities, and its absence

may adversely affect the viability of these projects from the

————————————————————————————————————————EI7~*7~™

79

prospective of the Resale Cities, thus vitiating an ease of entry

determination under § 3.3 of the Merger Guidelines.

3 ge

310

* * *

130. Notwithstanding the demands and needs of native load

customers, and the obligation to serve, the merger partners have

provided transmission access to others for purposes not related to

native load needs.

131. Network facilities are built to serve Edison’s entire ser-

vice area load, including the Resale Cities’ load, and import

transmission lines are built with a view to the needs of total load

area requirements, including those of Resale Cities. These deter-

minations are consistent with previous findings on the merger’s

competitive impacts on the defined transmission markets.

311

* * *

133. Given the geographic impediments associated with the

Cajon and San Gorgonio Passes, the relevant transmission lines

between California and the SW are nonduplicable. Furthermore,

the physical constraints noted by intervenors in connection with

the L.A. [Edison] Basin and service area facilities also indicate

that these lines are nonduplicable.

311

* « *

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.