Opposition Brief — S&M Constructors, Inc. v. Foley Co.
Supreme Court brief1992
Ask Donna
What actually matters in this document.
Text
No. 92-56
In The “a
Supreme Court of the United States
October Term, 1992
¢
S&M CONSTRUCTORS, INC.,
Petitioner,
“THE FOLEY COMPANY,
Respondent.
¢
Petition For A Writ Of Certiorari
To The United States Court Of Appeals
For The Eighth Circuit
¢
RESPONDENT’S BRIEF IN OPPOSITION
=
Kevin E. GLYNN
Counsel of Record
WituaM J. DEBAUCHE
NiewaLp, Wa.peck & BROWN
1200 Main Street, Suite 4100
Kansas City, Missouri 64105
(816) 471-7000
Counsel for Respondent
_—
COCKLE LAW BRIEF PRINTING CO, oo 225-6964
OR CALL COLLECT (402) 342-283
£
4 ~
Oy head
A in Fn
QUESTION PRESENTED
1. When a subcontractor has filed a demand for
arbitration under an arbitration clause in its subcontract
with a general contractor, and when the general contrac-
tor has filed a counterclaim against the subcontractor in
that arbitration, may the subcontractor have the entire
arbitration stayed by court order because the subcontrac-
tor would also like to assert claims against the United
States Government in separate proceedings?
il
LIST OF PARTIES
Respondent the Foley Company has no subsidiary or
parent corporations.
ili
TABLE OF CONTENTS
Page
Question Presented........................2....... i
a ka 5d y bk wu a vcvscecancccdce. ii
rs iii
ge ak sv k ks kG ae dy sacs ccnaccscaea, iv
i EE 1
a 2
Statement of the Case............................. 2
Summary of Argument.......................0.-.. 9
a 10
eC SS da we 4 5d a4 vada cc nace uncauacce 16
Ne oii vad css 5.054 sc anaevseasices App. 1
iv
TABLE OF AUTHORITIES
Page
Cases
AT&T Technologies, Inc. v. Communication Workers
OS Amie, So US. CEP CIPRO won ose cass ca nkains 13
Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213
SPP Tee Ter eT ey Ty Ter or eer ETT Tree 10, 15
Grinnell Fire Protection Systems Co., Inc. v. Regents
of University of California, 554 F.Supp. 495 (N.D.
ee N85 AA aN SARC e nds UREN EREA RRR OR GH OG Cees 15
Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth,
e., Ge Ui BES CEI) «oc i cho ccenns 9, 10, 11, 14, 15
Moses H. Cone Memorial Hospital v. Mercury Con-
struction Corp., 460 U.S. 1 (1983)........... 10, 11, 15
S&M Constructors, Inc. v. The Foley Co., 959 F.2d 97
OO Te UN ooo cc ceels i ee 1
Shearson/American Express, Inc. v. McMahon, 482
cs o> 2. 3g Perr e Terr ere 9, 10, 12, 15
United States of America for the use and benefit of
Capital Electric Construction Co., Inc. v. Pool &
Canfield, Inc., 778 F.Supp. 1088 (W.D. Mo. 1991) .... 14
Wilko v. Swan, 346 U.S. 427 (1953)...............048. 15
STATUTES
Bik ee Bs ere Tere rer er eer er ee TT. 11
PMA EKG EAS oe RR AE NORA ES Ceo ke eee 11
Oe Seas Oe aA soos Wek dak an Ab AwASh OE RE MER eee 9
ns SEED 40 5 oan voce 430 4 NK Ad PNR eu RATIO 2
Vv
TABLE OF AUTHORITIES - Continued
Page
Ol UO, BOR We Oe ose ivse ee ee & iz
ee Eee ee eee errr me 2
Gh UR | GO cnn eck ccvsieeted sre ess eee 2
OE VOM 8 OOo. ieveanc alice oe eee 2
No. 92-56
ry
In The
Supreme Court of the United States
October Term, 1992
¢
S&M CONSTRUCTORS, INC.,
Petitioner,
THE FOLEY COMPANY,
Respondent.
¢
Petition For A Writ Of Certiorari
To The United States Court Of Appeals
For The Eighth Circuit
+
RESPONDENT’S BRIEF IN OPPOSITION
¢
OPINIONS BELOW
The pertinent opinions below are included in the
Petitioner’s Appendix and in Respondent's Appendix.
The opinion of the United States Court of Appeals for the
Eighth Circuit, reported at 959 F.2d 97 (8th Cir. 1992), is
reprinted as Appendix A to Petitioner’s Appendix. The
opinion of the United States District Court for the West-
ern. District of Missouri, Western Division, Case No.
92-0412-CV-W-6, which is unreported, is reprinted as
Appendix B to Petitioner’s Appendix.
County, Missouri, dated February 10, 1992, is unreported
and is included in Respondent’s Appendix, pages 1-2.
Respondent agrees that Petitioner’s Petition was filed
within ninety (90) days of the judgment of the United
States Court of Appeals for the Eighth Circuit, and that a
Writ of Certiorari may be granted to review cases in the
Courts of Appeals pursuant to 28 U.S.C. §1254(1).
2
A copy of the Order of the Circuit Court of Jackson
¢
JURISDICTION
STATUTES
There are no constitutional issues involved in this
case and no constitutional provisions are pertinent.
Respondent does not believe that the Contract Disputes
Act of 1978, 41 U.S.C. §601 et seqg., governs this case, but
acknowledges that petitioner has advanced arguments
containing 41 U.S.C. §§602, 605 and 606 of the Contract
Disputes Act of 1978. Respondent believes that only 9
U.S.C. §2 applies to this case.
*
STATEMENT OF THE CASE
Petitioner S&M Constructors, Inc. has submitted an
inaccurate, incomplete account of the facts. Respondent
the Foley Company incorporates the statement of the
facts set forth in the opinion of the United States Court of
Appeals for the Eighth Circuit (Petitioner’s Appendix,
pages A-1 through A-5). In addition, the Foley Company
will address S&M Constructors’ misstatements of fact and
—— nw ee
will provide additional facts which have a bearing on the
issues in this case.
The dispute between the parties arose out of S&M
Constructors’ subcontract with general contractor the
Foley Company for construction services at a federal
project known as Power Reliability Enhancement Pro-
gram (AJCC), Fort Ritchie, Maryland (herein “the Pro-
ject”).
Disputes arose between S&M Constructors and the
Foley Company on the Project and while construction
was still underway, S&M Constructors filed a Demand for
Arbitration with the American Arbitration Association on
October 24, 1990. (Respondent’s Appendix, pages 3-5).
Foley filed an Application to Stay Arbitration on Decem-
ber 6, 1990. S&M Constructors filed an Answer to Foley’s
Application to Stay Arbitration, on February 18, 1991.
S&M argued that arbitration should be compelled.
(Respondent’s Appendix, pages 6-11). On September 27,
1991, Foley dismissed its Application to Stay Arbitration
upon the agreement of the parties. (Respondent’s Appen-
dix, pages 12-14).
On November 1, 1991, counsel for S&M Constructors
and Foley attended a preliminary hearing with the arbi-
trators and a schedule for the arbitration was set, with
the arbitration hearing to commence on February 3, 1992.
Pursuant to the schedule set on November 1, Foley Com-
pany filed an Amended Answer and Counterclaim on
December 16, 1991, alleging damages of more than $2.3
million against S&M Constructors. (Respondent's Appen-
dix, pages 15-19). Both S&M Constructors and Foley
Company filed Statements of Facts in the arbitration for
the benefit of the arbitrators on January 16, 1991.
(Respondent’s Appendix, pages 20-29).
On January 23, 1992, S&M Constructors filed a Peti-
tion for a Temporary Restraining Order and a Preliminary
Injunction in the Circuit Court of Jackson County, Mis-
souri, to stop the arbitration from commencing. (Respon-
dent’s Appendix, pages 30-36). The Circuit Court of
Jackson County, Missouri initially issued a temporary
restraining order until the matter could be heard, but
then dissolved the temporary restraining order and
denied S&M Constructors’ motion for preliminary injunc-
tion on February 10, 1992. (Respondent’s Appendix,
pages 1-2).
On February 14, 1992, S&M Constructors filed a
Motion for Temporary Restraining Order in the United
States District Court, Western District of Missouri, to stop
the arbitration. (Respondent’s Appendix, pages 37-44).
The United States District Court issued its decision on
February 21, 1992, denying S&M Constructors’ Motion.
(Petitioner's Appendix, pages A6-A9).
On February 24, 1992, S&M Constructors filed several
pleadings in the United States Court of Appeals for the
Eighth Circuit, including a Motion for Stay Pending
Appeal, and a Motion for Temporary Stay of Arbitration.
(Respondent’s Appendix, pages 45-48). The United States
Court of Appeals for the Eighth Circuit issued its decision
denying S&M’s Motions on March 16, 1992. (Petitioner’s
Appendix, pages Al-A5).
S&M Constructors filed a Motion in the United States
Court of Appeals for the Eighth Circuit on March 18,
1992, to stay enforcement of the Court of Appeals’ deci-
sion pending an application to this Court for a Petition
for Writ of Certiorari. The United States Court of Appeals
issued its decision denying S&M Constructors’ Motion on
March 27, 1992.
The American Arbitration Association rescheduled
the arbitration for March 31, 1992. On March 30, 1992, one
day before the arbitration was scheduled to commence,
S&M Constructors filed a Chapter 11 bankruptcy Petition
in the United States Bankruptcy Court for the Northern
District of Ohio, Case No. B92-11872. S&M Constructors’
bankruptcy is still pending.
S&M Constructors’ demand for arbitration sought
damages against the Foley Company in the amount of
$1,112,648.63. (Respondent’s Appendix, pages 3-5). S&M
Constructors filed a pleading explaining to the arbitrators
that this amount consists of claims against the Foley
Company for non-payment of invoices in the amount of
$297,215.25, and other claims in the amount of
$815,432.88 for delays in obtaining security clearances,
claims for additional work and claims for changed condi-
tions. (Respondent’s Appendix, Pages 25-29).
S&M Constructors’ contentions at pages 2 and 3 of its
Petition are incorrect and misleading. S&M Constructors’
Demand for Arbitration, filed on October 24, 1990, sought
compensation from the Foley Company for delay claims
and other claims which S&M Constructors now contends
are claims to be made against the Government under the
Contract Disputes Act. (Respondent’s Appendix, pages
3-5, 25-26). The Foley Company has claims against S&M
Constructors because S&M’s work was deficient, defec-
tive, delayed far past the schedule required by the Gov-
ernment, and not in conformance with the Government’s
contract documents. (Respondent’s Appendix, pages
15-24). Thus, it is inaccurate for S&M to state that S&M
“properly requested periodic payments under the S&M-
Foley subcontract, several of which payments were
refused by Respondent.” S&M Constructors sought not
only those payments, but also delay damages and other
claims in its Demand for Arbitration, and the Foley Com-
pany had legitimate claims against S&M Constructors at
the time of the presentation of the periodic pay requests
which far exceeded the amounts of those requests.
The first two sentences in the first full paragraph of
page 3 of S&M’s Petition are inaccurate as S&M Construc-
tors’ Demand for Arbitration initially included delay
damages and other claims which S&M Constructors
asserts against the Government as well. (Respondent’s
Appendix, pages 3-5, 25-26).
S&M’s statement on page 3 that “Petitioner was in
agreement with Respondent that the arbitration should
be delayed since the Government, as cause of the delay,
was-inextricably linked to this cause of action” is false as
S&M Constructors filed an Answer to Foley’s initial
Application to Stay Arbitration in which S&M Construc-
tors disagreed with that contention and argued that the
arbitration should proceed and that the Government was
not a necessary party. (Respondent’s Appendix, pages
6-11). S&M’s final paragraph on page 4 is also false for
the same reason. S&M omits the fact that the Foley Com-
pany dismissed the Application to Stay Arbitration on
7
September 27, 1991. (Respondent’s Appendix, pages
12-14).
The entire first paragraph on page 5 of S&M Con-
structors’ Petition is false and misleading. It is true that
S&M Constructors submitted claims to the Government
for security clearance delays and for other Government
acts and omissions. However, S&M Constructors has
alleged the same security clearance delay claims and
other claims against Foley Company in the arbitration,
beginning with its Demand for Arbitration and continu-
ing through its submission of a Pre-hearing Statement on
January 16, 1991, (Respondent's Appendix, pages 3-5,
25-29). The Foley Company does not have additional
claims filed against the Government which aggregate in
excess of $2,000,000 as contended by S&M Constructors.
Instead, the Foley Company has asserted these claims
against S&M Constructors, as explained in its Amended
Answer and Counterclaim and Statement of Facts in the
arbitration. (Respondent's Appendix, pages 15-24). At the
time of the filing of this Brief in Opposition, the Foley
Company has not submitted any claims to the Govern-
ment (although Foley may submit claims to the govern-
ment in the future in order to avoid the over three
hundred days of liquidated damages which the Govern-
ment has asserted against the Foley Company for the
delays caused by S&M Constructors).
S&M Constructors’ statement in the second para-
graph on page 5 of its Petition that “Petitioner’s demands
against respondent in the arbitration proceeding are pre-
cisely the same claims for equitable adjustment that Peti-
tioner has submitted to the Contracting Officer against
the United States Government” is not true as some of the
claims submitted by S&M Constructors, as described in
S&M’s Preliminary Statement, have not been submitted to
the Government and are brought against Foley only, such
as the claims for non-payment of invoices. (Respondent’s
Appendix, pages 25-29).
S&M Constructors mentions Foley’s initial Applica-
tion to Stay Arbitration, which was dismissed by agree-
ment of the parties on September 27, 1991. (Respondent’s
Appendix, pages 12-14). However, S&M omits the fact
that it has reversed its position 180 degrees from the
Answer which it filed to Foley’s initial Application to
Stay Arbitration. (Respondent’s Appendix, pages 6-11). In
that Answer, S&M Constructors argued that Foley should
be compelled to arbitrate despite the fact that some of the
claims may be presented against the Government under
the Contract Disputes Act. (Respondent’s Appendix,
pages 6-11).
S&M Constructors falsely states at pages 5 and 6 of
its Petition that “Respondent’s Counterclaim is based
primarily on the premise that Petitioner is the cause of
the obstruction of Respondent’s scheduling and, there-
fore, prevented Respondent’s completion of the Project in
a timely manner” and that these delay claims are really
the fault of the Government. Many of the Foley Com-
pany’s claims against S&M Constructors do not relate to
delays for which the Government had any responsibility.
Instead, many of Foley’s claims against S&M relate to
S&M’s defective and deficient work, such as tunneling a
hole in a mountain at the wrong elevation, overexcavat-
ing many areas, failing to control wet zones during shot-
crete work, performing improper scaling of rock, causing
noxious smoke and fumes to fill the tunnels, and failing
to pay subcontractors and suppliers even after Foley had
paid S&M to pay the subcontractors and suppliers.
(Respondent’s Appendix, pages 15-24). These claims are
not delay claims and do not involve the Government.
S&M Constructors’ statement in the first sentence of
the first full paragraph on page 6 omits the fact that
approximately one year after S&M sought to compel arbi-
tration (Respondent’s Appendix, page 6-11), S&M filed
pleadings and appeals in every imaginable forum to stay
the arbitration which S&M initiated. After every appeal
failed, and one day before the arbitration was to com-
mence, S&M filed for bankruptcy and the automatic stay
provisions of 11 U.S.C. §362 stayed the arbitration.
+
SUMMARY OF ARGUMENT
S&M Constructors’ Petition for Writ of Certiorari
should be denied because the decision of the United
States Court of Appeals for the Eighth Circuit correctly
. States the applicable decisions of this Court. The Court of
Appeals’ decision does not conflict with the decision of
any other United States Court of Appeals, does not con-
flict with any Missouri state court decisions, and does not
depart from the accepted and usual course of judicial
proceedings.
The United States Court of Appeals for the Eighth
Circuit correctly stated that this Court has decided that
arbitration brought pursuant to a contract clause must go
forward even if one of the parties claims that bifurcated
proceedings will result. Shearson/American Express, Inc. v.
McMahon, 482 U.S. 220 (1987); Mitsubishi Motors Corp. v.
10
Soler Chrysler-Plymouth, Inc., 473 U.S. 614 (1985); Dean
Witter Reynolds, Inc. v. Byrd, 470 U.S. 213 (1985); Moses H.
Cone Memorial Hospital v. Mercury Construction Corp., 460
U.S. 1 (1983).
S&M Constructors has failed to meet its burden to
show congressional intent to preclude a waiver of judicial
remedies for claims brought under the Contract Disputes
Act. Shearson/American Express, at 226-227; Mitsubishi
Motors Corp., at 628.
There is no legal authority in support of S&M’s con-
tention that when a subcontractor has made a demand for
arbitration under an arbitration clause in a contract with
the general contractor, and the general contractor files
counterclaims against the subcontractor in that arbitra-
tion, the subcontractor may have the entire arbitration
stayed because the subcontractor would like to bring
claims against another party in another dispute resolu-
tion forum. There is no merit in S&M’s position.
¢
ARGUMENT
The United States Court of Appeals for the Eighth
Circuit correctly decided this case, applying several deci-
sions of this Court which hold that a demand for arbitra-
tion under a contractual arbitration clause will be upheld
and the arbitration will be compelled to proceed even if
one party believes that the arbitration would result in
piecemeal litigation in other forums. Shearson/American
Express, Inc. v. McMahon, 482 U.S. 220 (1987); Mitsubishi
Motors Corp. v. Soler Chrysler-Plymouth, Inc., 473 U.S. 614
(1985); Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213
11
(1985); Moses H. Cone Memorial Hospital v. Mercury Con-
struction Corp., 460 U.S. 1 (1983). S&M’s arguments are
contrary to these decisions and S&M presents no contrary
authority of any consequence. S&M Constructors’ argu-
ments are without merit and this Court should deny
S&M’s Petition.
S&M Constructors filed the initial Demand for Arbi-
tration under its subcontract with the Foley Company.
S&M Constructors has not alleged that its subcontract
with the Foley Company should be revoked or that any
grounds exist for the revocation of the contract. Pursuant
to 9 U.S.C. §2, the arbitration clause in the subcontract
between S&M and Foley is “valid, irrevocable, and enfor-
ceable.” (Petitioner’s Appendix, page 13).
In Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth,
Inc., 473 U.S. 614 (1985), this Court held that an antitrust
dispute was subject to arbitration under the Federal Arbi-
tration Act, 9 U.S.C. §1 et seq., even if some of the claims
involved causes of action conferred by federal statutes.
This Court stated: “(b)y agreeing to arbitrate a statutory
claim, a party does not forego the substantive rights
afforded by the statute; it only submits to their resolution
in an arbitral, rather than a judicial, forum.” Id., at 628.
This Court also found that:
Having made the bargain to arbitrate, the party
should be held to it unless Congress itself has
evinced an intention to preclude a waiver of
judicial remedies for the statutory rights at
issue. Nothing, in the meantime, prevents a
party from excluding statutory claims from the
scope of an agreement to arbitrate. Id., at 628.
12
This Court restated this principle in Shearson/Ameri-
can Express and found that the burden is on the party
opposing arbitration to come forward with evidence of
Congressional intent to preclude a waiver of judicial
remedies for the statutory rights at issue. Id., at 226-227.
S&M Constructors has failed to meet its burden as it
has shown no congressional intent to preclude a waiver
of judicial remedies for claims brought under the contract
Disputes Act of 1978, 41 U.S.C. §601 et seg. S&M Con-
structors states that despite its initial Demand for Arbi-
tration against the Foley Company, in which it sought all
of its present claims against the Foley Company, it now
wants to bring some of its claims in a separate proceeding
under the Contract Disputes Act. S&M has stated no legal
authority and shown no congressional intent in support
of its contention that claims under the Contract Disputes
Act of 1978 should be considered non-arbitrable as a
matter of law, if such claims also fall within the arbitra-
tion clause of a contract.
Apart from these legal precedents, S&M Construc-
tors’ arguments are based upon a false and misleading
factual contention that all of the claims between S&M
Constructors and the Foley Company are also claims
which could be brought against the United States Gov-
ernment. The pleadings filed in the arbitration by both
S&M Constructors and the Foley Company disprove this
contention and show instead that both parties have
brought claims in the arbitration which are asserted only
against each other, and which could not possibly be
brought against the United States Government. (Respon-
dent’s Appendix, pages 3-5, 15-29). The Foley Company
has claims against S&M Constructors for S&M’s defective
13
and non-conforming work such as tunneling into a moun-
tain at the wrong elevation, failure to control wet zones
during shotcrete work, improper scaling of rock during
tunneling work, allowing noxious smoke and fumes to
enter tunnels, and failure to pay subcontractors and sup-
pliers even though the Foley Company had paid S&M
Constructors to pay those subcontractors and suppliers.
These claims are brought by the Foley Company against
S&M Constructors, not the United States Government.
Similarly, S&M Constructors has claims which can be
brought only against the Foley Company, such as S&M’s
allegations that the Foley Company has wrongfully with-
held payments for invoices from S&M Constructors.
Thus, this case does not involve claims which were
brought in arbitration but which could also be brought
against the United States Government. This case could
not be simply transferred as a whole out of the arbitration
proceeding and into a proceeding against the United
States Government under the Contract Disputes Act.
S&M Constructors complains at page 8 of its Petition
that the United States Government could not be a party to
the proposed arbitration proceeding. However, this is a
common situation in construction arbitration proceed-
ings, as often one of the parties wishes that a surety,
architect, engineer or owner’s representative, who is not
a party to the arbitration agreement, could be brought
into the arbitration to share in the responsibility. This
Court and the United States Court of Appeals for the
Eighth Circuit have held that “arbitration is a matter of
contract and a party cannot be required to submit to
arbitration any dispute which he has not agreed to sub-
mit.” AT&T Technologies, Inc. v. Communication Workers of
14
America, 475 U.S. 643, 648 (1986); United States of America
for the use and benefit of Capital Electric Construction Co.,
Inc. v. Pool & Canfield, Inc., 778 F.Supp. 1088, 1090 (W.D.
Mo. 1991). The Court in Capital Electric, supra, held that a
subcontractor seeking to arbitrate with a general contrac-
tor under an arbitration clause in its subcontract could
not force a surety company, not a party to that contract, to
arbitrate. The fact that the United States Government is
not a party to the S&M-Foley contract is of no conse-
quence to the enforceability of the contract’s arbitration
clause. S&M Constructors could have excluded claims
against the United States Government from the contrac-
tual arbitration clause, but did not. Mitsubishi Motors, at
628.
S&M Constructors states on page 9 of its Petition that
the United States Court of Appeals for the Eighth Circuit
erred in not considering the “unique context of govern-
ment contracting”. S&M’s contention is contrary to this
Court’s holding in Mitsubishi Motors Corp., supra that
“(h)aving made the bargain to arbitrate, the party should
be held to it unless Congress itself has evinced an inten-
tion to preclude a waiver of judicial remedies for the
statutory rights at issue.” Id. at 628. S&M Constructors
has failed to show any congressional intent to preclude a
waiver of judicial remedies in the context of government
contracting. The “factual distinction” urged by S&M Con-
structors in the first paragraph on page 9 of its Petition is
not supported by any legal authority and représents only
an invention of S&M Constructors. S&M’s arguments in
the first full paragraph at page 10 of its Petition fail for
the same reason.
15
S&M Constructors relies on Grinnell Fire Protection
Systems Co., Inc. v. Regents of University of California, 554
F.Supp. 495 (N.D. Cal. 1982), but that case is inapplicable.
As noted by the United States Court of Appeals for the
Eighth Circuit, Grinnell does not involve the Contract
Disputes Act, involves the staying of diversity litigation,
and was decided before this Court’s decisions in Mit-
subishi Motors Corp., supra; Shearson/American Express,
supra; Moses H. Cone Memorial Hospital, supra; and Dean
Witter Reynolds, supra.
S&M Constructors relies on Wilko v. Swan, 346 U.S.
427 (1953), but this Court has held that an argument
based upon Wilko v. Swan is no longer persuasive under
these circumstances. Shearson/American Express, Inc. v.
McMahon, 482 U.S. 220, 231-232 (1987).
S&M Constructors’ rhetoric about the “grave need”
for this Court to examine this issue ignores S&M’s failure
to come forward and meet its burden to show that Con-
gress has shown an intent to preclude a waiver of judicial
remedies for claims brought under the Contract Disputes
Act. Mitsubishi Motors Corp., at 628; Shearson/American
Express, Inc., at 226-227. S&M Constructors cites no appli-
cable legal authority and presents no Congressional
intent in support of its arguments. The decision of the
Eighth Circuit Court of Appeals is correct and S&M Con-
structors’ arguments are without merit.
¢
16
CONCLUSION
For these reasons, petitioner’s Petition for Writ of
Certiorari should be denied.
Respectfully submitted,
Kevin E. GLYNN
Counsel of Record
WituiAM J. DEBAUCHE
Nigwa_p, WALDEcK & BROWN
1200 Main Street, Suite 4100
Kansas City, Missouri 64105
(816) 471-7000
Counsel for Respondent
App. 1
IN THE CIRCUIT COURT OF
JACKSON COUNTY, MISSOURI
AT KANSAS CITY
S&M CONSTRUCTORS, INC., )
ee Case No.
Plaintiff, CV92-1585
VS. ) Civil F
THE FOLEY COMPANY,
Defendant. )
ORDER DISSOLVING TEMPORARY RESTRAINING
ORDER AND DENYING PRELIMINARY INJUNCTION
This matter comes on for hearing before the Court
this 10th day of February, 1992. Plaintiff appears by coun-
sel Robert Andrews and Ronald Kraft and defendant
Foley Company appears by counsel Kevin Glynn and by
representative Ken Kure.
After hearing argument and reviewing the briefs of
the parties on the legal issues involved the Court finds
that:
1. A valid arbitration agreement exists between the
Parties as a provision of the written contract between the
parties.
2. The law obtaining in this state favors the enforce-
ment of arbitration agreements.
3. The Court determines that the disputes between
the parties are encompassed in the arbitration agreement.
4. The Court finds that the agreement to arbitrate
was freely entered into between the parties.
App. 2
5. The Court finds that pursuant to Section 435.355
of the Missouri Revised Statutes and having found exis-
tence of a valid arbitration agreement the Court is
required to dissolve the temporary restraining order
heretofore entered.
NOW THEREFORE IT IS ORDERED that the tempor-
ary restraining order heretofore entered is dissolved and
the Petition for Temporary Injunction is denied. The costs
of this action are assessed against the plaintiff.
/s/ Preston Dean
Judge
Date: February 10, 1992
Time: 9:30 A.M.
Copies to:
Kevin E. Glynn
Ronald Kraft
Robert Andrews
App. 3
MEDIATION Please consult the Construction Industry Medi-
ation Rules regarding mediation procedures. If you want the
AAA to contact the other party and attempt to arrange a
mediation, please check this box.
CONSTRUCTION INDUSTRY ARBITRATION RULES
DEMAND FOR ARBITRATION
Date: October 24, 1990
To: Name Foley Company
(of party upon whom the demand is made)
Address 7501 Front Street
City and State Kansas City, Missouri
ZIP Code 64120
Telephone (816) 241-3335 Fax (816) 241-4321
Name of Attorney -
(if known)
Attorney’s Address
City and State ZIP Code
Telephone (_ ) Fax
The named claimant, a party to an arbitration agree-
ment contained in a written contract, dated February 27,
1989, providing for arbitration under the Construction
Industry Arbitration Rules, hereby demands arbitration
thereunder.
(Attach the arbitration clause or quote it hereunder.)
SEE ATTACHMENT “A”
Nature oF DispuTe:
Moneys owing under contract, for additional
work performed, and for delay damages.
App. 4
CLAIM oR RetieF SoucHT: (amount, if any)
Monetary relief: $1,112,648.63
Please indicate the industry category of each party:
CLAIMANT: ___ Owner ___ Architect
___ Landscape Architect
___ Engineer __ Contractor
_x_ Subcontractor (specify tunnelling)
Interior Designer _ Other
RESPONDENT: — Owner ___ Architect
___ Landscape Architect
___ Engineer x_ Contractor
___ Subcontractor (specify __)
Interior Designer __ Other
HEARING LocaLe Requestep: Washington, D.C. -
(City and State)
You are hereby notified that copies of our arbitration
agreement and of this demand are being filed with the
American Arbitration Association at its Washington, D.C.
Regional office, with the request that it commence the
administration of the arbitration. Under the rules, you
may file an answering statement after notice from the
administrator.
Signed /s/ Robert J. Andrews Jr.
(May be signed by attorney)
Robert J. Andrews, Jr.
Title Attorney for Claimant
Name of Claimant S&M Constructors, Inc.
Address (to be used in connection with this case) 29100
Hall Street
App. 5
City and State Solon, Ohio ZIP Code 44139
Telephone (216) 248-0376 Fax (216) 248-8248
Name of Attorney Andrews & Ryan
Attorney’s Address 29100 Hall Street
City and State Solon, Ohio ZIP Code 44139
Telephone (216) 248-2009 Fax (216) 248-8248
To institute proceedings, please send three copies of
this demand with the administrative fee, as provided for
the rules, to the AAA. Send the original demand to the
respondent.
App. 6
IN THE CIRCUIT COURT OF
JACKSON COUNTY, MISSOURI
AT KANSAS CITY
THE FOLEY COMPANY
Plaintiff,
) CASE NO.
)
)
-VS- )
)
)
)
CV90-032241
S&M CONSTRUCTORS, INC.
Defendant.
DEFENDANT’S ANSWER TO PLAINTIFF’S
APPLICATION TO STAY ARBITRATION
Now comes S&M Constructors, Inc. (“S&M”) in
response to Plaintiff’s Application, pursuant to R.S.Mo.
Section 435.355 and prays that this Court deny Plaintiff’s
Application to Stay Arbitration and prays for an order to
compel arbitration. In support of this Answer, S&M
states:
1. S&M is an Ohio corporation in good standing
with its offices at 29100 Hall Street, Solon, Ohio 44139.
2. Upon information and belief, The Foley Co.
(“Foley”), is a Missouri corporation in good standing,
with its offices at 7501 Front Street, Kansas City, Missouri
64120.
3. S&M is a subcontractor of Foley for a United
States Army Corps of Engineers project known as the
Power Reliability Enhancement Program, Fort Ritchie,
Maryland. The subcontract between S&M and Foley con-
tains an Arbitration and Enforcement Cost Clause requir-
ing that “disputes arising under this Agreement, or any
App. 7
instrument made to carry out the terms of this Agree-
ment, shall, where permitted by law, be submitted to
arbitration in accordance with the then obtaining rules of
the American Arbitration Association.” The arbitration
clause requires any hearings to be held in Kansas City,
Missouri. A copy of the subcontract and the arbitration
clause are annexed hereto as Exhibit “A”.
4. As a result of numerous irreconcilable disputes
between S&M and Foley, S&M filed a demand for arbitra-
tion that is currently before the American Arbitration
Association, Kansas City, Missouri.
5. The American Arbitration Association, by letter
dated November 26, 1990, requested the parties to choose
arbitrators and requested Foley to file its Answer and any
counterclaim by December 6, 1990. A copy of the letter of
the American Arbitration Association is annexed hereto
as Exhibit “B”.
6. Foley responded to the American Arbitration
Association by letter dated December 5, 1990 that trans-
mitted Foley’s Answer and Counterclaim in the arbitra-
tion styled S&M Constructors, Inc. and the Foley
Company, Case No. 57 110 0079 90 as well as a copy of its
Application to Stay Arbitration filed with this Court. A
copy of the transmittal letter and Answer and Counter-
claim of Foley are annexed hereto as Exhibit “C”.
7. Inits Application to Stay Arbitration, Foley states
that the subcontract with S&M provides, in Attachment 5,
Schedule D, paragraph 1, that “all the various contract
documents between the Owner and the Foley Co. are
incorporated by reference as if fully rewritten herein and
shall be binding upon and provide entitlement to, mutatis
App. 8
mutandis, The Foley Company Co. and Subcontractor.”
See Exhibit “A”, Attachment 5.
8. Foley maintains that the incorporation by refer-
ence language of Attachment 5, Schedule D, Paragraph 1
incorporates into the subcontract the “disputes” clause
contained in the prime contract between the United States
Army Corps of Engineers and Foley, which disputes
clause is binding upon S&M as subcontractor.
9. Similarly, Foley maintains that S&M is bound by
the provisions of the prime contract governing
“Changes,” which dictates a procedure for the assertion
of cost increases or changes in time of performance.
10. It is Foley’s contention that the Disputes and
Changes clauses of its contract with the United States
Army Corps of Engineers, by virtue of their incorporation
by reference, are the sole dispute resolution provisions
available to S&M.
11. Foley’s interpretation of the incorporation by
reference of the terms of the prime contract is at odds
with the plain language of the subcontract between Foley
and S&M, which states that “disputes arising under this
Agreement, or under any instrument made to carry out the
terms of this Agreement, shall . . . be submitted to arbitra-
tion....” [Emphasis Supplied] Through its incorporation
by reference, the prime contract is part of the subcontract
and as is clear from the foregoing, disputes arising under
this Agreement, including any disputes with respect to
the interpretation and application of the disputes and
changes clauses, are subject to arbitration.
App. 9
12. Foley, as the drafter of the contract, made no
reservation or limitation under the arbitration clause with
respect to the disputes or changes clauses of its prime
contract. Therefore, it must be bound by the terms of its
agreement with S&M to subject all disputes to arbitration.
At the least, the conflict between the provisions of the
prime and subcontract constitute an ambiguity that must
be construed against Foley as drafter. Slotkin v. Wilmering,
464 F.2d 418 (1972); Eastmont Construction Co. v. Transport
Mfg. & Equipment Co., 301 F.2d 34 (1962).
13. The American Arbitration Association requested
comments by S&M’s counsel to Foley’s Application to
Stay Arbitration, which comments set forth the foregoing
arguments. A copy of the request for comments and
response of S&M’s counsel are annexed hereto as Exhibit
a So
14. By letter dated January 11, 1991, the American
Arbitration Association stated in pertinent part:
The American Arbitration Association, after
reviewing the contentions of the parties and the
arbitration agreement, has determined that an
issue as to arbitrability exists which may be
determined by an arbitrator.
A copy is annexed hereto as Exhibit “E”.
15. The agreement to arbitrate contained in the
S&M subcontract with Foley is controlling when viewed
on the basis of both the plain meaning of the contract and
in the context of Foley as the party drafting the sub-
contract that contained the arbitration clause. This posi-
tion is consistent with the view expressed by the Third
Circuit Court of Appeals in Sharon Steel Corp. v. Jewell
App. 10
Coal & Coke Co., 735 F.2d 775, 778-779 (3rd Cir. 1984). The
Court held that “so long as the appellate’s claim of arbi-
trability was plausible, interpretation of the contract
should have been passed on to the arbitrator.” See, e.g.,
Pearl St. Development Corp. v. Conduit & Foundation Corp.,
41 N.Y.2d 167, 391 N.Y.S.2d 98 (1976); East Bernadino Cty.
Water Dist. v. City of San Bernadino, 109 Cal. Rptr. 510
(1973).
16. S&M requests that this Court find an agreement
to arbitrate between the parties and thereby allow this
matter to be resolved by arbitration before the American
Arbitration Association. -
WHEREFORE, Defendant S&M Constructors, Inc.
prays that this Honorable Court deny Plaintiff’s Applica-
tion to Stay Arbitration and enter its Order requiring
Plaintiff, The Foley Company, to arbitrate.
KRAFT, BROWER, GORDON and
ZELDIN
By: /s/ Ronald L. Kraft
Ronald L. Kraft - MO #21382
Attorney for Defendant
9237 Ward Parkway, Suite 200
P.O. Box 33156
Kansas City, MO 64114-0156
Telephone (816) 361-4800
Fax (816) 361-9865
OF COUNSEL
Robert J. Andrews, Jr.
Andrews & Ryan
29100 Hall St.
Solon, Ohio 44139
(216) 248-2009
App. 11
CERTIFICATE OF SERVICE
I hereby certify that a copy of the above and forego-
ing Defendant’s Answer to Plaintiff's Application to Stay
Arbitration was served by courier service this 18th day of
February, 1991, on:
Mr. Kevin E. Glynn
and Mr. William J. DeBauche
NIEWALD, WALDECK & BROWN
2500 Commerce Tower
911 Main Street
Kansas City, MO 64105
/s/ Ronald L. Kraft “4
Ronald L. Kraft
Attorney for Defendant
App. 12
IN THE CIRCUIT COURT OF
JACKSON COUNTY, MISSOURI
AT KANSAS CITY
THE FOLEY COMPANY,
)
fs. ) Case No.
Plaintiff, ) CV90-32241
“ ) Civil B
) (Filed
S&M CONSTRUCTORS, INC., Sep. 27 1991)
)
Defendant.
PLAINTIFF’S STIPULATION OF
DISMISSAL WITHOUT PREJUDICE
COMES NOW plaintiff, the Foley Company, by and
through its counsel; and dismisses its Application to Stay
Arbitration without prejudice.
NIEWALD, WALDECK & BROWN
A Professional Corporation
2500 Commerce Tower
911 Main Street
Kansas City, MO 64105
Telephene (816) 471-7000
Telecopier (816) 474-0872
/s/ William J. DeBauche
Kevin E. Glynn #21935
William J. DeBauche #32674
ATTORNEYS FOR PLAINTIFF
THE FOLEY COMPANY
App. 13
I hereby certify that a
true and correct copy of
the above and foregoing was
served by telecopier this
27 day of
SEPTEMBER, 1991 to:
Ronald Kraft
Kraft, Brower, Gordon
and Zeldin
9237 Ward Parkway, Suite 200
Kansas City, Missouri 64114
Robert Andrews
Andrews and Ryan
21900 Hall Street
Solon, OH 44139
Attorneys for Defendant
S&M Constructors, Inc.
/s/ William J. DeBauche
Attorneys for Plaintiff
The Foley Company
“App. 14
* IN THE CIRCUIT COURT OF
JACKSON COUNTY, MISSOURI
AT KANSAS CITY
THE FOLEY COMPANY,
)
Plaintiff, one
baa ) CV90-32241
S&M CONSTRUCTORS, INC., Civil B
Defendant. )
ORDER
The Court has reviewed plaintiff’s Stipulation of Dis-
missal Without Prejudice. The Court hereby dismisses
plaintiff’s Application to Stay Arbitration without preju-
dice, with each party to bear its own costs.
/s/ Gene R. Martin
Judge
Date: September 27, 1991
Copies to:
Kevin E. Glynn _
Ronald Kraft
Robert Andrews |
App. 15
AMERICAN ARBITRATION ASSOCIATION
S & M CONSTRUCTORS, INC.
and
THE FOLEY COMPANY
Case No.
57 110 0079 90
THE FOLEY COMPANY’S ANSWER AND
AMENDED COUNTERCLAIM
COMES NOW the Foley Company and for its Answer
and Amended Counterclaim, states:
1. Foley denies all of the allegations of S & M’s
Demand for Arbitration.
2. Foley is a Missouri corporation in good standing,
with its offices at 7501 Front Street, Kansas City, Missouri
64120.
3. S & M is an Ohio corporation with its offices at
29100 Hall Street, Solon, Ohio 44139.
4. S & M entered into a subcontract with Foley ona
project for the United States Corps of Engineers known as
Power Reliability Enhancement Program (AJCC), Fort
Ritchie, Maryland (herein “the project”).
5. In the course of S & M’s performance of its sub-
contract with Foley on the Project, S & M failed to per-
form its subcontract properly as (a) S & M was delinquent
in its performance on the submittals which were required
before initiation of work activity, (b) S & M started its
performance on the Project behind the schedule which
they had provided, (c) S & M failed to perform its wor! in
a timely fashion in accordance with the requirements of
lt oan
App. 16
the contract and in accordance with the approved sched-
ule; (d) S & M failed to pay its subcontractors and sup-
pliers, including amounts which Foley paid to S & M for
payment by S & M to those subcontractors and suppliers,
and (e) S & M’s work has been defective and deficient
and not in conformance with the contract requirements,
among other failures of performance by S & M.
6. Asa result of S & M’s delays, its defective, defi-
cient and non-conforming work, and its failures to pay its
subcontractors and suppliers, among other failures of
performance by S & M, S & M has breached its sub-
contract with Foley, has been negligent in the perfor-
mance of its subcontract, and in addition, S & M has
failed to comply with the indemnity clause in its sub-
contract with Foley.
7. Asa result of all of these failures by S & M, Foley
has sustained damages as set forth on Exhibit A, which is
attached. These damages are based on a projected com-
pletion date of January 25, 1992, and may be adjusted if
the project is completed on a different date.
WHEREFORE the Foley Company denies all of the
allegations of S & M Constructors, Inc.’s Demand for
Arbitration and prays that S & M Constructors, Inc. may
recover nothing on its Demand for Arbitration, and the
Foley Company prays for an award of damages on its
Counterclaim against S & M Contractors, Inc. in an
amount of $2,359,849.12, based on a projected completion
App. 17
date of January 25, 1992, and for ali costs, and for any
other relief which this panel may deem appropriate.
NIEWALD, WALDECK & BROWN
A Professional Corporation
2500 Commerce Tower
911 Main Street
Kansas City, Missouri 64105
(816) 471-7000
/s/ William J. DeBauche
Kevin E. Glynn #21935
William J. DeBauche #32674
ATTORNEYS FOR THE
FOLEY COMPANY
| hereby certify that a true and
correct copy of the above and fore-
going was mailed this 16 day of
DECEMBER, 1991 to:
Robert J. Andrews, Jr.
Andrews and Ryan
21900 Hall Street
Solon, Ohio 44139
Attorneys for S & M Constructors
/s/ William J. DeBauche
Attorneys for the Foley Company
App. 18
EXHIBIT A
SUMMARY OF DAMAGES
Subcontractors Cost
Pioneer Electric, Inc.
ACandS
W. C. Wiedenmann & Sons
D. L. George & Sons
Foley Company
Smoke-outs
Overexcavation Keyway Barrier
“C”, Substation Invert, Reservoir
Bottom, “B” Invert, “C” Invert,
“F” Invert
Scaling Areas “C” & “D”
Scaling Areas “B”, “E” & “PF”
Remove Fan Line Area “C”
Correct Wet Zones Area “G”
Overtime-Acceleration
Overexecavation in Area “G”
Overexcavation — At Cooling Towers
Assist S & M Coring Shotcrete
Install Chainlink Area “D”
Tight Removal Barrier “B”,
Intersection “F” & “G”, Sump Area “G”
Assist S&M Remove Tights & Grout
Voids
Engineering Error in “F”
Test Rock Bolts & Replace
Deficient Bolts
Cleanup & Dispose of Contaminated
Oil & Soil
Scheduling
Consulting Fees
Attorney Fees
Extended Field Overhead
Extended Home Office Overhead
116,280.08
1,817.00
29,826.00
64,132.26
, 9,832.54
53,722.02
12,228.79
15,529.19
605.27
1,585.89
25,479.73
82,081.05
29,397.58
475.44
2,586.38
3,720.00
18,597.24
30,620.98
3,389.59
1,210.00
4,000.00
20,000.00
46,578.08
426,579.27
222,272.00
App. 19
Liquidated Damages
Performance Cost Increase
Subtotal
Profit
Total
350,300.00
576,471.00
2,145,317.38
214,531.74
$2,359,849.12
App. 20
AMERICAN ARBITRATION ASSOCIATION
S & M CONSTRUCTORS, INC.
AND Case No. 57 110 0079 90
THE FOLEY COMPANY
THE FOLEY COMPANY’S STATEMENT OF FACTS
The Foley Company’s Amended Counterclaim
against S & M Constructors arises from S & M’s delays
and deficient and nonconforming work performed on its
subcontract with Foley, the general contractor, on a pro-
ject known as the Alternate Joint Communications Center,
a military installation in Pennsylvania. The contract was
administered by the U.S. Army Corps of Engineers from
its Fort Ritchie, Maryland office.
The project site contains national alternative commu-
nication centers in hardened facilities for the Department
of Defense, built into a mountain about seventy-five
miles from Washington, D.C. The project at issue in this
arbitration involved enlarging and modernizing the cen-
ter and enhancing the reliability of the mechanical sys-
tems. Foley’s contract involved increasing the size of the
facility by constructing additional tunnels and work
rooms. Much of the work took place in new areas of the
mountain not previously excavated or blasted. S & M
entered into a subcontract with Foley to perform blasting,
excavation and tunneling work. Foley Company per-
formed the general and mechanical construction follow-
ing S & M’s work.
App. 21
A summary of Foley’s claims against S & M are
contained on Exhibit A to Foley’s Amended Counter-
claim. Foley’s damages caused by 5S & M total
$2,359,849.12, assuming a completion date of January 25,
1992.
‘\
S & M’s performance of its subcontract was deficient
from the beginning, as S & M was delinquent in transmit-
ting submittals which were requisite prior to the initia-
tion of work activity. S & M commenced its performance
behind the schedule which it had provided. S & M’s
performance was deficient in many other instances as the
work progressed, so that Foley sustained 310 days of
delay to its work on the project as a result of S & M's
delinquent and deficient performance. The Corps of Engi-
neers has assessed liquidated damages against Foley at a
cost of $1,150.00 per day, for a total of approximately
$350,000.00 in liquidated damages assessed against Foley
as a result of S & M’s delinquent and deficient perfor-
mance.
S & M’s performance of its tunneling work was
defective, deficient and not in conformance with the con-
tract documents. S & M overexcavated many areas on the
project, including the tunnel inverts in Areas B, C and F;
the cooling tower and heat exchanger foundations located
in Area B; the keyway at the blast barrier in Area C; the
electrical substation invert, the reservoir bottom; and the
Mechanical Room in Area G. In addition, S & M was
responsible for an error in the elevation of Tunnel F. The
contract documents contained specific limits for excava-
tion, which S & M consistently breached.
App. 22
As a result of S & M’s excavation errors in many
areas, Foley Company in its subsequent performance of
the general and mechanical construction work was forced
to incur additional costs and delays because of Foiey’s
need to perform additional work to make up for S & M’s
excavation errors.
The Corps of Engineers would not accept S & M’s
shotcrete work in Area G, as S & M did not properly
control the wet zones in that area during construction.
The Corps would not accept the work until the wet zones
were properly abated. S & M refused to perform this
work, which was required by its subcontract, and Foley
was forced to perform it for S & M.
The Corps of Engineers also found S & M’s work in
several areas unacceptable with regard to the scaling of
rock from the invert to the apex. The Corps would not
permit any following work to be performed in these areas
tor safety reasons. S & M refused to perform this scaling
work in a manner acceptable to the Corps. Foley per-
formed S & M’s scaling work for S & M to keep the job
from being further delayed.
S & M also caused Foley to incur costs and time
delays due to smoke outs caused by S & M’s failure to
comply with the contract requirements for temporary
utilities. Noxious smoke and fumes emanated from exis-
ting tunnels and vent shafts, and the Corps found that
this problem was caused by S & M’s failure to perform its
work in accordance with the contract.
Foley has also learned that S & M failed to pay some
of its suppliers and subcontractors, even though Foley
App. 23
had paid S & M for the pay estimates for the time frame
when those costs were incurred.
The contract between Foley and S & M allows Foley
to charge its consulting fees and attorney’s fees for this
proceeding to S & M, and these amounts are included in
Exhibit A.
Foley has also charged extended overhead in <Accor-
dance with the formulas approved by the Courts. Foley
has charged S & M for the liquidated damages which the
Corps has charged Foley and which are attributable to S
& M’s delays. The excessive period of delay caused to
Foley by S & M’s breaches and failures caused Foley to
incur performance cost increases in several areas and
these costs are included on Foley’s Exhibit A as well.
Exhibit A contains other items which Foley will
explain in full at the arbitration. In this Statement, Foley
has presented the arbitrators with many of the most
significant delays and costs caused by S & M.
Foley believes that it owes nothing on S & M’s claim,
as S & M is seeking relief for areas of work in which S &
M performed deficient and non-conforming work and in
which S & M delayed Foley’s work. Further, Foley has
expended significantly more money to perform and cor-
rect S & M’s work than S & M contends remains as
unpaid contract balances. The amount withheld by Foley
App. 24
is a great deal less than the costs caused to Foley by S &
M’s delays and deficient and non-conforming work.
NIEWALD, WALDECK & BROWN
A Professional Corporation
2500 Commerce Tower
911 Main Street
Kansas City, Missouri 64105
(816) 471-7000
-, /s/ William J. DeBauche
Kevin E. Glynn #21935
William J. DeBauche #32674
ATTORNEYS FOR THE
FOLEY COMPANY
I hereby certify that a true and
correct copy of the above and fore-
going was mailed this 16 day of
January, 1991 to:
Robert J. Andrews, Jr.
Andrews and Ryan
4403 St. Clair Avenue
Cleveland, Ohio 44103-1125
Attorneys for S & M Constructors
/s/ William J. DeBauche
-, Attorneys for The Foley Company
-
SS ae ee
App. 25
AMERICAN ARBITRATION ASSOCIATION
S&M CONSTRUCTORS, INC.
and Case No. 57 110 0079 90
FOLEY COMPANY
PRE-HEARING STATEMENT OF
S&M CONSTRUCTORS, INC.
S&M Constructors, Inc. (“S&M”) and Foley Company
(“Foley”) entered into a subcontract dated February 27,
1989 in the amount of $5,200,000.00 for the performance
of certain excavation and shotcreting work at the Power
Reliability Enhancement Program (AJCC) (“Project”) Fort
Ritchie, Maryland. Foley was the prime contractor for the
Project under Contract No. DACA31-89-C-0008 which
contract was incorporated by reference into the S&M
subcontract.
From the outset of the Project, S&M experienced
numerous delays in the commencement and conduct of
its work, and performed work in excess of contract
requirements. These delays and extra work have been
due solely to the failure of the Government and/or Foley
to perform in accordance with the terms and specifica-
tions of the primary contract and hence the S&M/Foley
subcontract. By the terms of the subcontract agreement,
the obligations of the Government are assumed towards
S&M by Foley.
Foley has withheld payment from S&M in the
amount of $297,215.75 which is owing by Foley to S&M
under its subcontract, and has refused to compensate
S&M for its expenses incurred as a direct result of these
EE
App. 26
delays, and certain requirements for equipment rentals
and for extra work. As a result, S&M has made a demand
for arbitration pursuant to Attachment 5, Schedule D of
the subcontract seeking monetary relief in the amount of
$1,112,648.63. Of the monetary relief sought, $297,215.75
represents amounts wrongly withheld by Foley under the
subcontract and $815,432.88 represents compensation
sought for delays relating to security clearance, addi-
tional work and changed conditions.
Under the terms and specifications of the prime con-
tract, certain areas of the Project were “restricted” and
required security clearance for all personnel working in
such areas. Specifically, the prime contract under Part IV,
Section L —- Instructions, Conditions and Notice to Bid-
ders stated under L.28
Security Conditions Affecting Work:
Some of the work required by this solicitation
may require access to restricted areas. Occasio-
nal delay in obtaining authorization for access
to these areas or escort to a work site may be
anticipated.
No time period is set forth in the Fort Ritchie contract
as required for obtaining security clearance. Before
S&M’s final schedule Foley/Government personnel rep-
resented that sixty (60) days should be scheduled and
anticipated by the Contractor as required to obtain secu-
rity clearances.
S&M, in reasonable reliance on such representations,
diligently and timely applied for security clearances for
its personnel but was unable to obtain security clearances
for the requisite number of skilled workers to commence
App. 27
and prosecute the work as scheduled. When S&M was
able to commence work, it was forced to do so without
the requisite number of supervisors and crew to perform
the work as originally scheduled and as reasonably antic-
ipated. At variance with its intended schedule but in
order to begin to accomplish its work, S&M was forced to
change its work schedule from three eight-hour shifts to
two ten-hour shifts. This modification of its anti¢gipated
procedure, necessitated by the unjustified secufity clear-
ance delays, and in contradiction to express’ representa-
tions made by upper-tier representatives, further delayed
S&M’s work due to the loss of efficiency caused by
extended work shifts and made S&M’s work more costly
because of the greater utilization of premium time to
enhance production.
The security clearance delays were well in excess of
the 60 days represented as required, or — for that matter —
any other reasonable standard, and interfered with the
proper execution of S&M’s work by limiting the number
of skilled personnel available to the project. S&M seeks
an equitable adjustment of its contract price and time for
these delays on the basis of constructive change, Govern-
ment/Foley furnished property, and failure to provide
access to the work. It is S&M’s contention that these are
compensable, not just excusable, delays.
S&M is also seeking an equitable adjustment in con-
tract price and time for directed changes for additional
work performed to seal water leaks after the required
shotcrete had been successfully applied. In addition,
S&M is seeking equitable adjustment in contract price
and time for changed conditions in the Area D Upshaft
which constituted a delay to S&M’s work. As a result of
App. 28
the changed condition, new plans had to be formulated,
and as a result, additional delays were suffered by S&M.
In all, S&M is seeking an equitable adjustment to its
contract in the amount of $1,112,648.63 and 184 calendar
days. These delays are at the heart of the arbitration
between S&M and Foley. S&M is seeking redress for the
balance of its contract amount plus compensable extra
work costs and extended delays, while Foley is seeking
compensation for delays allegedly caused by S&M, lost
performance and extended overhead relative to the
delays, liquidated damages and for additional costs rela-
tive to the direct and indirect cost of repairs which Foley
apparently claims were necessitated by S&M’s failure
properly to perform its work. In total, Foley is seeking
$2,359,849.12 in its Counterclaim.
Certain components of Foley’s claim are inconsistent.
Assuming, arguendo, that S&M’s delays are found not to
be either compensable or excusable, Foley is not entitled
to both actual and liquidated damages for delays caused by
S&M. Rather, Foley would be limited to the contract
provisions calling for liquidated damages. Moreover, cer-
tain of Foley’s claims relating to overexcavation are nec-
essary construction costs, and part of the inherent risk,
assumed by Foley when it deleted from S&M’s proposed
scope of subcontract work, and decided to take upon
itself, the obligation to perform the concrete work follow-
ing excavation. Foley was warned by S&M representa-
tives that the work deleted was more expensive than
Foley anticipated because of the impossibility (under-
stood by everyone familiar with underground construc-
tion — which Foley was not) of precisely controlling the
manner in which rock breaks in blasting. It is Foley’s
App. 29
contention that S&M improperly excavated in certain
areas, causing Foley additional expense. In fact, S&M
employed industry standard techniques to control break
as appropriate and practicable. Nevertheless, the rock
breakage, an inevitable concomitant of the drill-and-blast
method, is ultimately a function of geology.
-
While there are other numerous specific areas of
dispute to be determined in this proceeding, S&M’s basic
position is that Foley cannot impose upon S&M the
responsibility for delays that are actually compensable to
S&M and which resulted from causes attributable solely
to Foley and/or the Government as a result of Foley and/
or the Government's failure properly to understand or
schedule its own work.
Respectfully submitted,
ANDREWS & ASSOCIATES
JANUARY 16, 1992
/s/ Robert J. Andrews, Jr.
ROBERT J. ANDREWS, JR.
Regis. No. 0025043
4403 St. Clair Avenue
Cleveland, OH 44103-1125
(216) 881-8030
Attorney for Claimant
App. 30
IN THE CIRCUIT COURT OF
JACKSON COUNTY, MISSOURI
AT KANSAS CITY
S&M CONSTRUCTORS, INC.
Plaintiff,
)
) CV92-1585
)
V. )
)
)
)
Case No.
Division
THE FOLEY COMPANY, (Filed Jan. 23, 1992)
Defendant.
PETITION FOR TEMPORARY RESTRAINING ORDER
AND PRELIMINARY INJUNCTION
COMES NOW plaintiff S&M Constructors, Inc.
(“S&M”) and prays for judgment ordering a temporary
restraining order of the arbitration proceedings between
S&M and The Foley Company (“Foley”), Case No. 57 110
0079 90, before the American Arbitration Association,
Kansas City, Missouri, scheduled to commence February
3, 1992, and that a preliminary injunction be issued there-
after, enjoining such arbitration. In support of its Petition
S&M states:
1. S&M is an Ohio corporation in good standing
with its offices at 29100 Hall Street, Solon, Ohio 44139.
2. Foley is a Missouri corporation in good standing
with its offices at 7501 Front Street, Kansas City, Missouri
64120.
3. The dispute in arbitration arose under S&M’s
subcontract with Foley for excavation and other heavy
underground construction services rendered at United
States Army Corps of Engineers (“Corps of Engineers”)
eT
App. 31
project known as the Power Reliability Enhancement Pro-
gram (AJCC), Fort Ritchie, Maryland (“Project”) for
which Foley was the general contractor.
4. S&M and Foley have filed claims with the Corps
of Engineers for equitable adjustment for compensable
delays resulting from the failure of the United States
Government to grant security clearances for S&M’s per-
sonnel in a timely manner, for changed conditions and for
additional work, which claims aggregate in excess of
$2,000,000. To date, the Contracting Officer for the Project
has not made a final determination of these claims.
5. In the scheduled arbitration proceedings, S&M
has made a demand against Foley for the same claims for
equitable adjustment as set forth in paragraph 4.
6. Foley has filed a counterclaim in the arbitration
proceedings seeking $2,359,849.12 for losses and extra
expense caused by S&M’s delays substandard perfor-
mance of its subcontract with Foley. Foley contends that
S&M’‘s delays in turn have delayed and impacted Foley’s
scheduling and completion of the Project in a timely
manner.
7. The delays for which Foley is basing its counter-
claim are, for the most part, concurrent with the delays
that are the basis of S&M’s claim for equitable adjust-
ment, and, similarly are based on commissions or omis-
sions on the part of the United States Government.
8. The subcontract between S&M and Foley has
caused a unique and conflicting situation based on the
contradictory terms of the subcontract governing dispute
App. 32
resolution. The S&M-Foley subcontract provides in
Attachment 5, Schedule D, paragraph 1 as follows:
1. Incorporation Provision. All the various con-
tract documents between the Owner and The
Foley Co. are incorporated by reference as if
fully rewritten herein and shall be binding upon
and provide entitlement to, mutatis mutandis,
The Foley Co. and Subcontractor.
Exhibit A annexed hereto.
Foley’s contract with the Owner, the United States Army
Corps of Engineers, contains a Disputes clause which
requires that “all disputes arising under or relating to this
contract shall be resolved under this clause.” A copy of
this Disputes clause is annexed hereto as Exhibit B. The
Disputes clause requires that any claims must first be
submitted to the United States Army Corps of Engineers
Contracting Officer for a written decision, which decision
shall be final unless the contractor appeals or files suit
under the Contracts Disputes Act 41 U.S.C. Sections
601-613.
9. In addition to the Disputes clause which is incor-
porated by reference into the subcontract between S&M
and Foley, the subcontract provides in Attachment 5,
Schedule D, paragraph 2, as follows:
2. Arbitration and Enforcement Costs - It is
agreed that disputes arising under this Agree-
ment, or under any instrument made to carry
out the terms of this Agreement, shall, where
permitted by law, be submitted to arbitration in
accordance with the then obtaining rules of the
American Arbitration Association. Any hearing
shall be held in Kansas City, MO. Any costs
App. 33
including, without limitation, legal fees incurred
by either party in the successful enforecement of
any rights hereunder, shall be borne by the
party against which said rights are enforced.
Exhibit A annexed hereto.
10. The foregoing arbitration clause is the basis for
the arbitration proceedings scheduled to commence on
February 3, 1992 in Kansas City, Missouri.
11. The conflict that arises by virtue of the contra-
dictory provisions for dispute resolution contained in
Attachment 5 of the subcontract is that a bifurcated pro-
ceeding has resulted. First, S&M has made its claims, as
has Foley, through the Government contract mandated
disputes resolution process, for equitable adjustment
based on compensable delays, additional work and
changed conditions for which claims a determination has
not yet been made. Second, the arbitration proceeding
involves claims identical with those claimed for in accor-
dance with the Government contract mandated disputes
resolution process. Third, the counterclaims asserted by
Foley in the arbitration are similarly identical with those
Foley has submitted in accordance with the Government
contract mandated disputes resolution process and are
integrally tied to a determination of the validity of S&M’s
claims relating to delays which may either be compens-
able or excusable delays and therefore a valid defense to
Foley’s counterclaims. ;
12. The result of commencing arbitration at this
time could be conflicting results that would be inequita-
ble to the parties by failing to provide a means by which
to redress these conflicts. By way of example, S&M could
App. 34
prevail in the arbitration, winning its award and defeat-
ing Foley’s counterclaim, yet Foley could lose its claim
before the Corps of Engineers or Board of Contract
Appeals which may find Foley is not entitled to addi-
tional compensation and that its delays (which would
include S&M’s) were neither compensable nor excusable.
In this instance, Foley would have no means of redress
because of the inherent limitation on the appeal of arbi-
tration awards. Similarly, S&M might prevail before the
Corps of Engineers or the Board of Contract Appeals with
a finding that its delays were compensable, yet lose in
arbitration and would have no means to reconcile its
position. Such a potential conflicting result indicates that
the issues are not yet ripe for arbitration.
13. In addition to the issue of potentially irreconcil-
able results, S&M maintains that the current arbitration
proceeding must be enjoined based on the preemption of
federal procurement.
14. The Project as well as Foley’s contract with the
Corps of Engineers is governed by federal government
procurement law which dictates the means and methods
of dispute resolution. By virtue of the incorporation of
Foley’s contract into S&M’s subcontract, the dispute reso-
lution mechanism dictated by Government regulations
are controlling and preempt the consensual provisions of
the subcontract relating to arbitration. Such a determina-
tion is clearly required where, as in the instant case, the
parties have submitted their disputes for resolution by
the Corps of Engineers Contracting Officer pursuant to
the Disputes clause of the prime contract.
App. 35
15. S&M maintains that should arbitration proceed,
such proceedings would be in violation of federal law
governing dispute resolution for government contracts
and that S&M, and indeed Foley, may sustain irreparable
harm resulting from conflicting decisions by the Corps of
Engineers and the arbitration for which result S&M has
no adequate remedy at law.
WHEREFORE, plaintiff S&M respectfully prays that:
A. This Court, by its order, temporarily restrain the
defendant from proceeding to arbitration before the
American Arbitration Association in Case No. 57 110 0079
90.
B. This Court, by its order, preliminarily enjoin the
defendant from proceeding to arbitration before the
American Arbitration Association in Case No. 57 110 0079
90.
App. 36
C. This Court grant such further relief as it deems
just and proper.
Respectfully submitted,
KRAFT, BROWER, GORDON AND
ZELDIN
By: /s/ Ronald L. Kraft
Ronald L. Kraft - MO #21382
By: /s/ Robert B. Zeldin
Robert B. Zeldin - MO #22372
9237 Ward Parkway, Suite 200
P.O. Box 33156
Kansas City, MO 64114-0156
Telephone (816) 361-4800
Fax (816) 361-9865
ATTORNEYS FOR PLAINTIFF
Of Counsel:
ANDREWS & ASSOCIATES
4403 St. Clair Avenue
Cleveland, OH 44103
Telephone (216) 881-8030
Fax (216) 881-3928
cecilia
App. 37
IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF MISSOURI
S&M CONSTRUCTORS, INC. ) CASE NO.
29100 Hall Street )
Solon, Ohio 44139
Plaintiff
JUDGE
(Filed Feb. 14, 1992)
-Vs-
)
)
)
)
THE FOLEY COMPANY ) 92-0142-CV-W
7501 Front Street )
Kansas City, Missouri 64120 .
)
Defendant
MOTION FOR TEMPORARY RESTRAINING ORDER
Now comes Plaintiff S&M Constructors, Inc. (“S&M”)
pursuant to Rule 65(b) of the Federal Rules of Civil
Procedure and moves this Court for a temporary restrain-
ing order to prevent Defendant The Foley Company
(“Foley”) from proceeding to arbitration with S&M in
Case No. 57 110 0079 90 before the American Arbitration
Association, Kansas City, Missouri, which was originally
scheduled to commence February 3, 1992. In support of
its Motion, S&M states:
1. S&M is an Ohio corparation in good standing,
with its offices at 29100 Hall Street, Solon, Ohio 44139.
2. Foley is a Missouri corporation in good standing,
with its offices at 7501 Front Street, Kansas City, Missouri.
3. Jurisdiction is predicated upon both diversity of
citizenship within the terms of 28 U.S.C. §1332 and
Federal subject matter jurisdiction under the Federal
App. 38
Arbitration Act, 9 U.S.C. §1 et seg. and the Contracts
Dispute Act of 1978, 41 U.S.C. §601 et seq.
4. The dispute between the parties arose out of
S&M’s subcontract with Foley for excavation and other
heavy underground construction services rendered at
United States Army Corps of Engineers (“Corps of Engi-
neers”) project designated as the Power Reliability
Enhancement Program (AJCC) (“Project”), Fort Ritchie,
Maryland.
5. Foley is the general contractor for the Project
under the prime contract with the Corps of Engineers and
contracted with the United States Government for all
construction aspects of the Project.
6. The S&M-Foley subcontract provides in Attach-
ment 5, Schedule D, paragraph 1:
1. Incorporation Provision. All the various con-
tract documents between the Owner and The
Foley Co. are incorporated by reference as if
fully rewritten herein and shall be binding upon
and provide entitlement to, mutatis mutandis,
The Foley Co. and subcontractor.
[Exhibit A annexed hereto.]
7. Foley’s prime contract with the Owner, the
United States Army Corps of Engineers, contains a Dis-
putes clause which states that “this contract is subject to
the Contracts Disputes Act of 1978, (414 S.C. 601-613)”
and which requires that “all disputes arising under or
relating to this contract shall be resolved under this
clause.” A copy of this Disputes clause is annexed hereto
as Exhibit B. The Disputes clause requires that any claims
App. 39
must first be submitted to the Corps of Engineers Con-
tracting Officer for a written decision, which decision
shall be final unless the contractor appeals to the Board of
Contract Appeals or files suit in the Claims Court under
the Contracts Dispute Act of 1978, 41 U.S.C. §601 et seq.
8. Whereas the Disputes clause of the prime con-
tract is incorporated by reference into the S&M-Foley
subcontract, the subcontract also provides in Attachment
5, Schedule D, paragraph 2:
2. Arbitration and Enforcement Cost. It is
agreed that disputes arising under this Agree-
ment, or under any instrument made to carry
out the terms of this Agreement, shall, where
permitted by law, be submitted to arbitration in
accordance with the then obtaining rules of the
American Arbitration Association. Any hearing
shall be held in Kansas City, Missouri. Any costs
including without limitation, legal fees incurred
by either party in the successful enforcement of
any rights hereunder, shall be borne by the
party against which said rights are enforced.
[Annexed hereto as Exhibit A.]
This arbitration clause is the basis for the pending
arbitration proceeding.
9. In accordance with the Disputes clause of the
prime contract between Foley and the Corps of Engi-
neers, S&M, through Foley, has filed claims with the
Corps of Engineers for equitable adjustment for compens-
able delays resulting from the failure of the United States
Government to grant security clearances for S&M’s per-
sonnel in a timely manner and for other reasons; Foley
has additional claims against the government which
. App. 40
aggregate in excess of $2,000,000.00. S&M’s claims are
and Foley’s claims are soon to be before the Contracting
Officer for the Project and have not yet been decided.
10. S&M’s demand against Foley in the arbitration
proceeding is for the same claims for equitable adjust-
ment as in S&M and Foley’s claims against the Govern-
ment. Foley has filed a counterclaim in the arbitration
seeking $2,359,849.22 for losses and extra expense caused
by S&M’s delays and for its substandard performance
under the S&M-Foley subcontract.
11. Foley’s counterclaim is based on the premise
that S&M’s delays have delayed and obstructed Foley’s
scheduling and have, therefore, prevented Foley’s com-
pletion of the Project in a timely manner.
12. The delays upon which Foley is basing its coun-
terclaim are, for the most part, concurrent with the delays
that are the basis of the S&M and Foley claim for equita-
ble adjustment submitted to the Contracting Officer, and,
thus, are based on commissions or omissions of the
United States Government. The United States Govern-
ment, which would not be party to an arbitration between
Foley and S&M, is thus a necessary party whose presence
is required properly to resolve nearly all of the disputes
between the parties. Foley itself recognized this fact when
on December 6, 1990 it-filed its own Application to Stay
Arbitration in the Circuit Court of Jackson County, Mis-
souri at Kansas City.
13. The dispute between S&M and Foley raises a
question of the conflict between Federal law governing
the government procurement process and dispute resolu-
tion thereunder and the subcontract arbitration clause. It
App. 41
is S&M’s position that i) the Disputes clause and dispute
resolution remedies under the United States Government
procurement law and the Contracts Disputes Act of 1978
preempt consensual remedies such as arbitration, ii) there
has been an election to proceed under the Disputes clause
and the parties have not exhausted their administrative
remedies thereunder and, iii) Federal law governing gov-
ernment contracts is controlling to stay arbitration in this
instance.
14. The failure to issue a temporary restraining
order will cause irreparable harm to S&M since it will
then be committed to concurrent bifurcated proceedings
a) under the Disputes resolution process before the Corps
of Engineers and b) pursuant to arbitration. Such a deci-
sion creates duplicative effort and results which may be
inconsistent with judicial or legal economy and result in
inconsistent and irreconcilable decisions.
15. Both S&M and Foley have claims within the
Disputes resolution process mandated by Foley’s prime
contract with the Corps of Engineers and both seek equi-
table adjustment based on compensable damages, addi-
tional work and changed conditions.
16. With respect to S&M, the arbitration proceeding
involves claims identical to those subject to resolution
under the Disputes resolution.process mandated by the
prime Government contracts ~
17. Foley’s counterclaims in arbitration are gener-
ally identical with the claims Foley has submitted under
the prime contract’s Disputes clause and are integrally
tied to a determination of the validity of S&M’s claims
relative to delays which may either be compensable or
App. 42
excusable delays, and therefore, a valid defense to Foley’s
counterclaim.
18. The consequence of commencing arbitration at
this time could be conflicting results that would be ineq-
uitable to the parties by failing to provide a means to
redress these conflicts.
19. Such conflicting results would do irreparable
harm to S&M in the event S&M prevailed in one forum
but lost in another since there is no means to reconcile
these positions and awards in arbitration are effectively
unappealable.
20. The construction of subcontracts let under a
prime contract with the Government is governed by Fed-
eral law. American Pipe & Steel Corp. v. Firestone Tire &
Rubber, 292 F.2d 640 (9th Cir. 1961).
21. When, as in the instant case, there is a conflict of
policy between the dispute resolution process mandated
by the prime government contract and alternative means
of dispute resolution, Federal law has favored the Federal
Dispute resolution process or mechanism. See, Grinnell
Fire Protection Systems Co., Inc. v. Regents of the University
of California, 554 F.Supp. 495 (N.D. Cal. 1982); cf Bache
Halsey Stuart, Inc. v. French, 425 F.Supp. 1231 (D.D.C.
1977).
22. By incorporating the Disputes Clause of the
prime contract into the subcontract and by exercising
their rights thereunder, Foley and S&M have elected that
the Disputes clause and the Contract Disputes Act of 1978
is their rightful and primary avenue of redress. Once
there has been a final decision rendered pursuant to the
App. 43
Government contract dispute resolution process, any
remaining matters which do not involve the government
may be resolved in accordance with the arbitration clause
of the subcontract. Clearly, the dispute between S&M and
Foley is not, at this juncture, ripe for arbitration.
23. Upon the granting of S&M’s request for a tem-
porary restraining order, S&M shall file an application to
this Court for a Preliminary Injunction pursuant to Rule
65(a) of the Federal Rules of Civil Procedure.
WHEREFORE, plaintiff S&M Constructors, Inc. prays
that this Court grant its request for a temporary Restrain-
ing Order staying defendant The Foley Company from
proceeding to arbitration.
Respectfully submitted,
KRAFT, BROWER, GORDON
AND ZEDLIN
By: /s/ Ronald L. Kraft
RONALD L. KRAFT (Mo#21382)
9237 Ward Parkway, Suite 200
P.O. Box 33156
Kansas City, Missouri 64114-0156
Telephone (816) 361-4800
Fax (816) 361-9865
Of Counsel:
Robert J. Andrews, Jr.
Andrews & Associates
4403 St. Clair Avenue
Cleveland, Ohio 44103-1125
App. 44
STATE OF OHIO )
») SS:
COUNTY OF CUYAHOGA )
VERIFICATION
I, Ronan S. Marra, declare as follows:
I am Vice President of S&M Constructors, Inc. Plain-
tiff in the above captioned action and make this declara-
tion on behalf of Plaintiff in my capacity as Vice President
of Plaintiff.
I have read the foregoing Motion for Temporary
Restraining Order and know its contents. I am informed
and believe that the matters stated in the Motion are true,
and on that ground allege that the matters stated in it are
true.
I certify under penalty of perjury that the foregoing
is true and correct.
Executed this 10th day of February, 1992 at Cleve-
land, Ohio.
/s/ Ronan S. Marra
RONAN S. MARRA
SUBSCRIBED AND SWORN to before me, a Notary
Public this 12th day of February, 1992.
/s/ Charles H. Manning
Notary Public
CHARLES H. MANNING, ATTORNEY
NOTARY PUBLIC, State of Ohio
My Commission Has No Expiration Date
App. 45
IN THE COURT OF APPEALS
EIGHTH CIRCUIT
UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF MISSOURI
S&M CONSTRUCTORS, INC. : Case No.
Plaintiff-Appellant 92-0142-CV-W-6
-VS- : JUDGE
FOLEY COMPANY
: MOTION FOR
Defendant-Appellee : TEMPORARY STAY
OF ARBITRATION
WHILE MOTION TO
ENJOIN A DISTRICT
COURT ORDER IS
PENDING
Now comes the Plaintiff-Appellant, S&M Construc-
tors, Inc., by and through counsel, and respectfully
requests that this Honorable Court issue a one week
injunction of an order denying Plaintiff-Appellant’s
Motion to Stay Arbitration and issue an Order to Stay
Said Arbitration Pending Appeal.
This motion is being made pursuant to Rule 8 of the
Federal Rules of Appellate Procedure. Counsel has previ-
ously moved for a stay in District Court. Counsel has also
moved for an injunction by this Court of the District
Court Order Pending Appeal which is attached hereto.
The District Court denied counsel's application, and with
an arbitration set for February 25, 1992, it is necessary to
obtain an order staying arbitration while the motion and
the appeal are pending. The reasons supporting the
ones .
App. 46
granting of this motion are set forth in the following
brief.
Respectfully submitted,
KRAFT, BROWER, GORDON AND
ZEDLIN
/s/ Ronald L. Kraft
RONALD L. KRAFT
(MO Regis. 21382)
Attorney for Plaintiff-Appellant
App. 47
IN THE COURT OF APPEALS
EIGHTH CIRCUIT
UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF MISSOURI
S&M CONSTRUCTORS, INC. : Case No. 92-0142-CV-
Plaintiff-Appellant a
Ve : JUDGE
FOLEY COMPANY
: MOTION TO STAY
Defendant-Appellee - AN ORDER OF THE
: DISTRICT COURT
PENDING APPEAL
AND FOR AN
IMMEDIATE AND
TEMPORARY
INJUNCTION
STAYING
PROCEEDINGS
PENDING APPEAL
Now comes the Appellant, S&M Constructors, Inc.,
by and through counsel, and respectfully requests that
this Honorable Court stay the order denying its Motion to
Stay Arbitration while the order is challenged on appeal
and grant an Immediate Temporary Injunction Staying
Arbitration Pending Appeal.
This motion is being made pursuant to Rule 8 of the
Federal Rules of Appellate Procedure. Counsel previously
moved for a stay in the Federal District Court. The Dis-
trict denied counsel’s application and it is therefore nec-
essary to stay the scheduled arbitration while this appeal
App. 48
is pending. The reasons supporting the granting of this
motion are set forth in the- following brief.
Respectfully submitted,
KRAFT, BROWER, GORDON AND
ZEDLIN
/s/ Ronald L. Kraft
RONALD L. KRAFT
(MO Regis. 21382)
Attorney for Plaintiff-Appellant
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.