Appendix — Industrial Risk Insurers v. Cotton Bros. Baking Co.
Supreme Court brief1992
Ask Donna
What actually matters in this document.
Text
la
APPENDIX
UNITED STATES COURT OF APPEALS
FIFTH CIRCUIT
No. 90-4128
COTTON BROTHERS BAKING COMPANY, ING.,
Plaintiff-A ppellee,
INDUSTRIAL RISK INSURERS,
Defendant-T hird-Pa rty
Plaintiff-Appellant,
V.
BAKER PERKINS Foop MACHINERY, INC.,
Third-Party Defendant-
Appellant.
COTTON BROTHERS BAKING COMPANY, INC.,
Plaintiff-A ppellee,
BAKER PERKINS, INC.,
Defendant-A ppellant.
BAKER PERKINS, INC.,
Plaintiff-A ppellant,
COTTON BROTHERS BAKING COMPANY, INC.,
Defendant-A ppellee.
2a
Appeals from the United States District Court
for the Western District of Louisiana
Sept. 13, 1991
Before POLITZ, WILLIAMS, and JONES, Circuit
Judges.
POLITZ, Circuit Judge:
This appeal poses complex damages and liability issues
resulting from a fire at Cotton Brothers Baking Co., Inc.,
a bakery in Alexandria, Louisiana, on Friday, February
13, 1981. Multiple suits resulted. The matters were tried
in part by a jury and in part by the bench and the
ultimate judgments are now before us on appeal. For
the reasons assigned we modify those judgments and, as
modified, affirm.
Background
At the time it was severely damaged by fire, Cotton
Brothers Baking Co., Inc., was one of eight subsidiaries
of Cotton Bros., Inc. Each subsidiary was independently
incorporated and occupied a single location, but the com-
panies operated as a single integrated enterprise in the
commercial baking industry. Gene Cotton served as presi-
dent and CEO of the parent company and of each sub-
sidiary, and the membership of the boards of directors of
each company was identical.
The damage to the Alexandria bakery was substantial
and its effect was felt throughout the Cotton Bros. organi-
zation. In order to minimize the impact on production as
a whole, Cotton Bros. shifted some of the prior Alexandria
production to other facilities and purchased products from
competitors for resale under the Cotton label.
3a
Cotton Bros. contacted Baker Perkins, Inc., a Michigan
industrial baking supplier, about replacement of the two
principal pieces of equipment destroyed in the fire, an
oven and a rack proofer. After substantial negotiations
and site surveys, Baker Perkins contracted with Cotton
Bros. Baking Co., Ine. to install the equipment. The
initial submission was an offer by Baker Perkins dated
February 20, 1981, and included an accelerated installa-
tion price of $1,354,820. Another proposal, which did not
placement cost differential, contemplated a “start-up” date
eight months later than that specified in the final agree-
ment.’ The initial offer included the following details:
SHIPPING AND INSTALLATION
SCHEDULE ACCELERATED
INSTALLATION
Order Placement 2-22-81
Shipment 5- 1-81
Start Erection 6-12-81
Final Shipment 6-26-81
start-up [sic] 9-21-81
Schedule predicated on order placement by February
22, 1981. Any delay in order placement beyond that
date will directly effect [sic] final dates of shipment,
erection and final start-up beyond those listed above.
Despite the timing calling for order placement by Febru-
ary 22, the proposal was accepted verbally by Cotton
Bros. on March 6, 1981, followed by a signing on March
19. This final submission constituted a counter-proposal
which Baker Perkins approved and accepted on May 14,
1981. Start-up actually occurred in the late spring of
1982.
‘Some equipment was replaced rather than repaired. “Start-up”
refers to resumption of baking production.
4a
Cotton Bros. also filed a claim with its insurer, In-
dustrial Risk Insurers (IRI), under policies protecting
against both fire property damage to equipment and busi-
ness interruption. Significantly, the policies did not list
Cotton Bros., Inc. as an insured but, instead, named three
of the subsidiaries and five separate premises. The busi-
ness interruption policy provided in pertinent part:
SECTION I
A. Recovery in the event of loss hereunder shall
be the ACTUAL LOSS SUSTAINED by the In-
sured resulting directly from such interruption
of business, but not exceeding the reduction in
gross earnings less charges and expenses which
do not necessarily continue during the interrup-
tion of business, for only such length of time as
would be required with the exercise of due dili-
gence and dispatch to rebuild, repair or replace
such described property as has been damaged or
destroyed, commencing with the date of such
damage or destruction and not limited by the
date of expiration of this Policy. Due considera-
tion shall be given to the continuation of normal
charges and expenses, including payroll expense,
to the extent necessary to resume operations of
“the Insured with the same quality of service
which existed immediately preceding the loss.
SECTION IIi
A. EXPENSES RELATED TO REDUCING LOSS.
—This Policy Also covers:
1. such expenses as are necessarily incurred for
the purpose of reducing loss under this Policy
(except expense incurred to extinguish a fire),
and
2. such expenses, in excess of normal, as would
necessarily be incurred in replacing any finished
5a
stock used by the Insured to reduce loss under
this Policy, but in no event shall the aggregate
of such expenses exceed the amount by which the
loss otherwise payable under this Policy is hereby
reduced.
IRI, which was involved in the Cotton Bros. decision to
accept the accelerated Baker Perkins contract, hired a
team of accountants to audit the records of Cotton Bros.
and to adjust claims arising from the interruption of
business policy. Cotton Bros. also assembled a group for
the same purpose, composed of in-house personnel and
accountants from its retained accounting firm, Ernst &
Whinney. By their own admission, neither the Ernst &
Whinney personnel nor the Cotton Bros. in-house staff
had any experience with interruption of business insur-
ance claims. They relied on the expertise—and good faith
—of IRI’s accountants to accurately calculate those losses.
The Cotton Bros. team submitted a document to the IRI
team entitled “Methodology for Computing the Cost of
Business Interruption,’ which the district court found
contained patent errors in application of business inter-
ruption insurance. IRI accepted the document without
comment and made no effort to assist Cotton Bros. in
correcting errors.” Additionally, IRI insisted that as Cot-
ton Bros., Inc. was not a named insured, only the damages
directly related to Cotton Bros. Baking Co. (the Alex-
andria bakery entity), could be used to calculate losses.
*The methodology involved a line-item reimbursement by IRI
for identifiable extra costs that were incurred as a result of the
business interruption. The district court found this approach
operated as nothing more than an extra expense policy, ‘ta form
of insurance coverage to reimburse the insured for specific items
of extra expense over and above the normal expense which the
insured incurred. ...” The district court further found that as
early as 1970 both IRI and Cotton Bros. intended that a full and
complete business interruption policy be confected, rather than an
extra expense policy.
6a
IRi’s payments to Cotton Bros. under the business inter-
ruption policy eventually totaled $3,585,761.97.
Once Cotton Bros., with IRI support, approved the ac-
celerated purchase agreement with Baker Perkins to re-
place destroyed equipment, IRI substantially changed its
position with respect to the amount it owed Cotton Bros.,
and, further, the insurance policy under which that
amount was to be paid. Initially approved as a fire insur-
ance recovery, the payment was then changed, minus the
acceleration premium, into a business interruption re-
covery, for which IRI stood to benefit because it could take
a credit against Cotton’s gross earnings loss. Eventually
IRI paid the lower estimate and purported to advance the
remaining acceleration as an expediting expense, repay-
able if Baker Perkins failed to perform timely its acceler-
ated schedule.
Several lawsuits resulted. Cotton Bros. Baking Co. sued
Baker Perkins in the Western District of Louisiana for
damages arising from the latter’s delay in completing the
installation of the oven and proofer. Baker Perkins coun-
terclaimed for the $209,000 unpaid balance on the original
contract, and other ancillary equipment installation con-
tracts. Baker Perkins also filed an action in the Eastern
District of Michigan against Cotton Bros. for an amount
and under causes of action identical to its counterclaim
in the parallel action. That case was transferred to the
Western District of Louisiana, where Cotton Bros. coun-
terclaimed, asserting the same claims as Cotton Bros.
Baking Co. in the original action. Baker Perkins moved,
inter alia, to dismiss all claims for damages asserted by
Cotton Bros. given that the insurance contract named
Cotton Bros. Baking Co. The district court promptly
denied that motion, which came after three and one-half
years of litigation in which Cotton Bros. had admitted
Baker Perkin’s allegation that the two parties had entered
into a valid contract. The district court did, however,
dismiss Cotton Bros. Baking Co.’s claims against Baker
7a
Perkins. A jury determined that Baker Perkins had
breached the contract, that Cotton Bros. had sustained
$2,065,575 in damages resulting from the breach, and
that Cotton Bros. was 35%¢ responsible for the breach.
Accordingly, the district court awarded Cotton Bros.
$1,242,624 plus legal interest from the date of judicial
demand in the Baker Perkins case. The district court
directed a verdict in Cotton Bros.’ favor in Baker Perkins’
suit for $209,000.
In an action consolidated with the Baker Perkins suit,
Cotton Bros. Baking Co. and Cotton Bros. brought suit
in the Western District of Louisiana against IRI claiming
damages under the business interruption policy. After a
bench trial involving substantial taking of evidence, the
trial court reformed the original insurance policy to make
and include Cotton Bros., Inc., as a named insured at all
relevant times, entered judgment in favor of Cotton Bros.
Baking Co. and Cotton Bros. for the $324,735 “advanced”
by IRI in the accelerated contract dispute, and awarded
state law insurer-delay penalties, attorney’s fees, and pre
judgment interest. Additionally, the court awarded Cot-
ton Bros. $4,498,000 in damages* plus penalties, attor-
ney’s fees and prejudgment interest less $427,460.67
credit to be equitably applied upon payment of IRI’s
judicial obligation to Cotton Bros. The credit was ap-
plied by the court based on an acceptance by Cotton Bros.
that the amount ought not be clasified as earnings dam-
ages. Finally, the district court ordered IRI subrogated to
* Cotton Bros. introduced evidence indicating its actual earnings
were a loss of $2,535,000 and its projected earnings were $3,361,000,
resulting in a reduction of gross earnings of $5,896,000. These
projections were based on a business interruption period running
from February 13, 1981 through September 25, 1982. The trial
court, however, determined that the business interruption period
terminated on May 8, 1982, when the replacement oven and proofer
went into operation. The court, accordingly, adjusted the $5,896,000
figure to $4,498,000, based on proportionately reduced actual earn-
ings of negative $1,933,926 and projected earnings of $2,564,073.
8a
the Cotton Bros. recovery in the Baker Perkins action,
contingent upon IRI’s payment of all other obligations
resolved in that litigation.
Dissastisfaction abounded. Baker Perkins and IRI
timely appealed.
Analysis
Before us are appeals, as noted, from both a bench
trial and a jury trial. At the bench trial, the district
court construed an unambigous contract and awarded
damages based on calculations related to that contract.
Such construction presents a question of law for which
our review is de novo. Southern Natural Gas Co. v.
Pursue Energy, 781 F.2d 1079 (5th Cir. 1986).
The IRI Litigation
IRI raises three issues on appeal. First, it asserts that
the trial court erred by not crediting the $3,585,761.97
which IRI had already paid under the business interrup-
tion policy against the $4,498,000 judgment awarded be-
low. The judgment was for claims under section IA of
the business interruption policy designed to compensate
Cotton Bros. for the actual loss incurred as a result of the
fire. The district court had found that the $3,858,761.97
paid by IRI under the line-item methodology ought not be
treated as payments for Cotton Bros.’ actual Joss sustained
because the line-item approach was not fueled by any
measure of earnings. The court thus treated the amount
as costs incurred in mitigation of the net loss caused by
the fire, payable under sections IIIA of the policy.
In this the trial court erred. Failure to credit IRI for
its prior payments would result in a double recovery by
Cotton Bros. The Louisiana courts have underscored the
importance of applying business interruption insurance
in a manner which avoids double recovery.
We hold that the business interruption clause in
the policy in this case is unambiguous. The language
9a
of the policy sets forth the formula for calculating
the amount of actual loss by an insured when busi-
ness is interrupted, and allows the business to re-
main in the same financial condition as before the
loss. Although the policy is designed to protect the
insured, it is also designed to prevent the insured
from being placed in a better position than if no loss
or interruption of business had occurred.
United Land Invesiors, Inc. v. Northern Ins. Co., 476 So.2d
432, 436 (La.App.1985) (emphasis original). While the
methodology used did not reflect accurately the lost earn-
ings experienced by Cotton Bros., the payments nonethe-
less represented compensation for lost earnings. The
$4,498,000 calculated by the trial court as the actual loss
Cotton Bros. sustained includes the difference between
projected earnings had there not been a fire $2,564,073),
and actual earnings during the period of business inter-
ruption (a loss of $1,933,926). The loss figure did not
include the $3,585,761.97; if it did, then actual earnings
during the interruption period would be _ (positive)
$1,651,835.97, and the reduction in gross earnings (pro-
jected minus actual) only $912,238.03.
The court would have been correct in excluding the
$3,585,761.97 had an equal amount been excluded from
the actual loss figure based on expenses incurred by Cot-
ton Bros. Simply stated, if these line-item expenses were
not included in the actual earnings figure, then Cotton
Bros. lost $1,933,926 during the business interruption
period. However, review of the record discloses no such
exclusion from actual losses. Accordingly, the Cotton
Bros, judgment against IRI for claims under section IA
of the business interruption policy is modified to
$912,238.03.
The Accelerated Premium
IRI next contends that the trial court erred by award-
ing Cotton Bros. the $324,735 which IRI deducted from
payments to Cotton Bros. for having replaced rather
10a
than repaired its oven and proofer, and for having done
so at an accelerated schedule.* We disagree. The facts
attendant to the March 6, 1981 acceptance by Cotton of
IRI’s draft of a proof of loss reflected IRI’s willingness
to pay $1,188,425 under the fire policy, and $165,575
under the business interruption policy.’ The fire policy
figure included the $159,160 replacement cost of the oven
and proofer.
Immediately after the meeting, Cotton Bros. verbally
accepted the Baker Perkins proposal discussed at the
March 6 meeting. We perceive no error in the district
court’s recounting of the subsequent facts:
Cotton was committed. IRI then refused payment.
Now Cotton was compromised. Cotton had exercised
extraordinary diligence in its efforts to rebuild and
restore in the shortest time as possible to the evident
benefit of both IRI and itself. It had been successful
in securing the contractor most capable of doing a
competent job in the shortest time possible. It had
settled its claim against IRI for the loss of the
proofer and the oven for a sum proposed by IRI’s
own agent. IRI now refused to pay. Incredible!
The trial court then determined that IRI’s decision to
deny the coverage—and later to recast a partial payment
as an “advance” on the chance of Baker Perkins’ timely
completion of the work—was a strong-arm attempt to
*The amount represents the cost differential of replacement
rather than repair, $159,160, plus the acceleration premium,
$165,575. Cotton Bros. does not quibble with the deduction of an-
other $182,655, representing the cost of a cascade apparatus,
equipment used to load the proofer.
5 See Notes from Insurance Meeting 6, March 6, 1981. Exhibit
122A. “Tom Simpson advised that Mr. Bud Jarratt had gotten
with the IRI and they prepared another partial settlement of the
claim. They have agreed to pay $531,200 on the proofer and
$658,045 on the oven which totals $1,189,245.”
lla
deny the existence of an enforceable agreement. With
respect to the $159,160 cost differential, the trial court
properly, therefore, held IRI to the agreement it had
forged on March 6, 1981, by awarding judgment in favor
of Cotton Bros.
The acceleration premium, which the district court
apparently erroneously lumped in with the fire insurance
policy, should have been treated as an expediting ex-
pense, given its mitigating effect on Cotton Bros.’ losses.
The contractually-mandated test is not, as IRI suggests,
whether the accelerated schedule was met by Baker
Perkins, but, instead, whether the expense was one
“necessarily incurred for the purpose of reducing loss
under [the business interruption] Policy.” * The district
court found that the Cotton Bros. contract with Baker
Perkins under the accelerated scheduling plan was just
such an expense. IRI points to no contrary evidence. The
trial court did not err.‘
insurance: Its Theory and Practice 103 (1986) (emphasis orig-
inal) :
It should also be noted that, in the application of the ex-
pediting expense provision, a different timing approach may
be taken than in the case of the basic business interruption
loss. In the case of expediting expense, hindsight must be
used because only after the fact is it possible to determine
whether or not there was an actual savings and how much
it is. This should create no problem because the two compen-
sation provisions have entirely different purposes and each
stands on its own feet.
7IRI’s contention that Cotton Bros.’ award of the $324,735 con-
stitutes unjust enrichment is without merit. IRI argues that it
advanced Cotton Bros. the funds in order to pay Baker Perkins,
but that Cotton Bros. has not paid the money over to Baker Per-
kins. Cotton Bros. could only be unjustly enriched in the first
instance to the extent that it received a judgment beyond the
amount which it owes or has paid Baker Perkins. Baker Perkins
and Cotton Bros. stipulate that of the $209,000 owing to Baker
Perkins, only a portion relates to expediting expenses, 7.e., the
12a
Statutory Penalties
In its final enumeration of error,, IRI challenges the
district court’s assessment of a 12% statutory penalty
on monies awarded to Cotton Bros. under the IRI policies.
IRI contends that the district court misapplied the ap-
plicable state statute, La.R.S. § 22:658, which subjects
insurers found “arbitrary, capricious, or [acting] with-
out probable cause” to a 12% penalty plus reasonable
attorney’s fees, upon failure to make payment within 60
days of receipt of proof of loss.* Proof of loss is defined
as that point in time when the insurer had adequate
knowledge of the loss. Hart v. Allstate Ins. Co., 487 So.2d
823 (La.1983). The district court’s assessment of penal-
ties was based on its finding that IRI effected a “stone-
walling” stratery in every aspect of its dealings with
Cotton Bros. The strategy began with a continuing—
and unjustified, in light of its lonestanding relationship
with Cotton Bros.—contention that only the accounts of
the Alexandria bakery, and not Cotton Bros. in toto, were
applicable to the business interruption loss calculations.
IRI also provided little, and at times incorrect, advice to
its insured on the correct methodology for calculation of
business losses. The district court found that IRI’s in-
struction to its accounting team ‘“‘was intended to induce
error by Cotton. The instruction was made for the illicit
purpose of inhibiting and defeating Cotton’s right to file
any claim for earnings damages under Section IA and
ITA of the policy. The stonewall position of IRI was ar-
bitrary, capricious, in bad faith and without probable
cause.” Simultaneously, the dispute regarding the Baker
Perkins replacement contract was simmering, in a situa-
tion described supra, for which the district court specifi-
cally imputed to IRI an attempt to strong-arm its insured
into an unfavorable bargaining position.
acceleration premium. Our holding with respect to the companion
Baker Perkins litigation disposes of the funds in question, leaving
no party unjustly enriched.
8 Since amended to require payment within 30 days.
13a
The characterization of an insurer’s failure or refusal
to pay is a question of fact, Smith v. State Farm Fire &
Cas. Co., 695 F.2d 202 (5th Cir.1983), and propriety of
assessment of insurer penalties is likewise, “in part a
factual determination,” United Land Investors, 476 So.2d
at 438. IRI’s arguments leave us unpersuaded that the
district court, sitting as the trier of fact, was clearly
erroneous in its factual findings.
The court did err, however, in assessing statutory
penalties on the entire $4,498,000 which it awarded Cot-
ton Bros. on the business interruption policy, as well as
the $324,735 awarded on the fire policy. In the first
instance, having modified the former judgment to
$912,238.03, we would affirm the assessment of penalties
only as applied to that amount; howevef, the trial court
committed further error by assessing penalties on
amounts already advanced by IRI to its insured. IRI’s
contention that the district court erroneously attached a
statutory penalty on a portion of the funds which the
court ordered “equitably credited” to IRI upon payment
of all sums awarded at bar, is well taken. That amount,
$427,460.67, was advanced to Baker Perkins; IRI cannot
now be held to pay a penalty for not having acvanced
that sum of money. This would have the effect of compen-
sating Cotton Bros. for the loss of the use of funds of
which it, in fact, had use. We therefore modify the dis-
trict court’s award of statutory penalties to reflect a
12% penalty on the $484,877.36 difference between the
judgment and the credit.
Having affirmed the $324,735 in whole, however, we
affirm the penalties with respect to that additional
amount.
The Baker Perkins Litigation
In the companion action also, before the court, Baker
Perkins first argues that the district court erred by
holding that Cotton Bros., rather than Cotton Bros. Bak-
ing Co., was permitted to recover for breach of the re-
l4a
placement contract. Baker Perkins correctly advances the
notion that under Louisiana law a corporation is not per-
mitted to bring a cause of action on behalf of a wholly-
owned subsidiary corporation, Eximco, Inc. v. Trane Co.,
737 F.2d 505 (5th Cir.1984), and that there must be
privity of contract for recovery for a breach. Impressive
Builders, Inc. v. Ready Mix, Inc., 585 So.2d 1844 (La.
App. 1988). The trial court did not, however, entertain
an impermissible lawsuit; instead, it properly concluded
that Cotton Bros. rather than Cotton Bros. Baking Co.
was the proper party to the contract. This was within the
equitable powers of the district court. As the Louisiana
Court of Appeal informs:
“In interpreting contractual provisions about which
there exists some doubt, a court must seek the true
intention of the parties, even, if to do so necessitates
a departure from the literal meaning of the agree-
ment.” In such cases, the law is never so inflexible
as to bind parties to a contract which neither in-
tended.
... The established method of resolving a mutual
mistake in a contract is reformation of the agreement
to reflect the true intent of the parties.
Placid Refining Co. v. Privette, 523 So.2d 865, 868 (cita-
tions omitted), vacated on rehearing on other grounds,
523 So.2d 870 (La.App.1988).
The district court’s action, which came in response to a
motion by Baker Perkins to amend was appropriate in
the instant ease, given the underlying procedural posture
of the case. The original suit was, in fact, Cotton Bros.
Baking Co.’s action against Baker Perkins, an action
brought in the Western District of Louisiana. Four days
later, Baker Perkins brought its suit against Cotton Bros.,
Inc., alleging inter alia, a contract with the parent com-
pany and seeking recovery for the unpaid balance of the
contract price.
15a
The district court interpreted Baker Perkins’ motion
to amend as an eleventh-hour ploy to defeat the Cotton
Bros. counterclaim (filed as a Rule 13(a) compulsory
counterclaim) by disclaiming the existence of a contract
it had spent three and one-half years urging in litigation.
In light of Baker Perkins’ longstanding business relation-
ship with Cotton Bros., its acceptance of earlier payments
for the contract from Cotton Bros. (not Cotton Bros.
Baking Co.), its frequent correspondence with Cotton
Bros. during the negotiations for the contract, and Baker
Perkins’ over-three-year delay in seeking leave to amend
its complaint to change the name of the defendant, the
court acted within its discretion in holding Baker Perkins
to the facts it had alleged and which its defendant,
Cotton Bros., candidly and appropriately had admitted.
Our holding in Hall v. Aetna Casualty and Surety Co.,
617 F.2d 1108 (5th Cir.1980), presents an analogous
situation. There, we held that the district court did not
abuse its discretion in disallowing an insurer to substan-
tially amend its answer, mid-trial, from a position of
admitting coverage under an insurance policy to one ex-
cluding coverage under a previously “overlooked” provi-
sion. “The trial judge recognized, however, that this final
amendment would clearly prejudice the opposing party
and simply came too late.” Jd. at 1110-11. A similar find-
ing obtains in the instant case. As Judge Scott incisively
wrote:
In the case at bar, the plaintiff, Baker Perkins,
brought suit, alleging a contract with the defendant
parent corporation and sought recovery of funds due
under the contract. Cotton Bros., Inc. admitted the
allegation and pleaded its counter-claim which was
compulsory under Rule 13(a) of the Federal Rules
of Civil Procedure. The parties labored under these
facts for three and a half years before Baker Per-
kins moved to amend its complaint to correct “a
mistake” made by its Michigan counsel when naming
the defendant, contracting party.
l6a
We are of the opinion that Baker Perkins was
well aware of who it was suing and why it was
doing so.
Cotton Bros.’ good faith reliance on the veracity of
Baker Perkins’ pleadings was well-founded; there was
ample evidence that Cotton Bros. was indeed the proper
party in this case.* We perceive no abuse of discretion
in this instance.
The Limitation of Liability Provision
Baker Perkins next maintains that the trial court mis-
construed a limitation of liability provision in the oven
and proofer contract. The provision declares:
WARRANTY
Seller warrants the apparatus to be as _ specified
herein; and will correct any defects in the apparatus
which develop under normal and proper use and
maintenance within twelve months after erection
(defective parts to be replaced F.O.B. factory), pro-
vided Buyer shall have given prompt notice to Seller
of any such defects. The foregoing Warranties are
EXPRESSLY IN LIEU OF ALL WARRANTIES
® McKnight v. Blanchard, 667 F.2d 477 (5th Cir.1982), cited by
Baker Perkins, is inapposite. In that inmate’s civil rights action
an order was entered substituting the current sheriff for his prede-
cessor, “but retaining as party the predecessor sheriff originally
sued.” The inmate complained only of a clerical change in the
caption of the case, “apparently fearing that the ‘et al.’ does not
include the ‘Lubbock County Jail.’” We deemed his contention
meritless, holding “The administrative captioning of the suit ob-
viously has no effect on what cause of action and what parties
are (or are not) joined in the substantive allegations of the plead-
ings.” Jd. at 482. In the instant case, Baker Perkins is not being
held to its original pleadings merely on the basis of the caption’
given the case. Instead, its three-plus years litigation with the
facts it alleged, and which Cotton Bros. admitted and relied upon
are the operative concerns of the court.
17a
WHATSOVER, EXPRESSED, IMPLIED AND
STATUTORY, INCLUDING, WITHOUT LIMITA-
‘TION, THE IMPLIED WARRANTIES OF MER-
CHANTABILITY AND FITNESS. Seller will in
no event be liable to Buyer or others for any direct,
indirect, special or consequential damages or loss of
production or loss of profits resulting from any cause
whatsoever, including but not limited to defective
workmanship or materials or any delay, act, error
or omission of Seller. Seller shall be notified of, and
reserve the right to be present at, any test which
Buyer may make in relation to operation. All equip-
ment manufactured by others, but included as part
of this contract, will be subject to standard war-
ranty as issued by this manufacturer.
The district court held that this disclaimer was effective
only with respect to redhibitory vices, and not for the
purpose urged by Baker Perkins, 7.e., exclusion of claims
for lost profits flowing from delay in performance of the
contract. We agree. Baker Perkins reurges and under-
scores its contention that the presence of the three
words “or any delay” in the warranty section of the
contract essentially forecloses discussion on this point.
We disagree. The Louisiana Court of Appeal has con-
cisely stated the fundamental rules of contract construc-
tion prevalent in Louisiana:
The interpretation of a contract begins with the
document itself... . La.C.C. Art. 2046 states that
when the words of a contract are clear and explicit
and lead to no absurd consequences, no further in-
terpretation may be made in search of the intent of
the parties. If a court does attempt to discern the
intent of the parties, the contract must be interpreted
in light of other provisions so that each is given the
meaning suggested by the contract as a whole.
Grant v. Ouachita Nat’l Bank, 536 So.2d 647, 651 (La.
App.1988) (citing La.C.C. arts. 2045-57). The district
18a
court correctly identifled the warranty paragraph as one
pertaining only to defects in the items being sold.
Clearly and unambigously the paragraph begins with the
words, “Seller warrants the apparatus to be as specified
herein. . . .” Delivery, which the district court held
was the portion of the contract applicable to Baker
Perkins’ delay, has a separate paragraph in the con-
tract.’° Significantly, the delivery paragraph provides a
limited variety of situations for which Baker Perkins’
delay in delivery would be excused, none of which per-
tain to the instant case. Logically, then, Baker Perkins
may be held liable for those delays in delivery not caused
by the enumerated excused conditions. Under Baker
Perkins’ strained interpretation of the offer it tendered
to Cotton Bros., no liability whatsoever would accrue
from even indefinite delay in delivery, notwithstanding
lack of contract-specified justification. Such a reading
fails to give meaning to the delivery provision of the
contract, as well as to the premium which Baker Perkins
charged Cotton Bros. for accelerated installation. Read-
ing the entire contract in a light giving meaning to the
whole, we perceive no error in the district court’s con-
clusion."
10 DELIVERY
Seller shall be excused for any delay in delivery, or any part
delivery, hereunder, if caused by fire, explosion, flood, epidemic,
war, interruption or delay in transportation, labor troubles or any
cause beyond its reasonable control. In case of delay caused by
Buyer’s failure to furnish necessary information as to details to
be determined by Buyer, Seller may extend date for shipment for
at Seller’s factories. In case shipment shall be delayed by Buyer’s
a reasonable time, based on period of Buyer’s delay and conditions
failure to furnish shipping instructions on request, or otherwise
by Buyer, Seller may as [sic] its option invoice material ready for
shipment, and payment therefore shall be made in accordance with
the terms hereof, substituting the invoice for the Bill of Lading.
11 Baker Perkins also appeals the directed verdict on the issue of
contract start-up date. We perceive no error in the court’s memo:
randum opinions of August 18, 1987, and January 23, 1990, in
19a
Evidence of Damages
Baker Perkins asserts that Cotton Bros.’ claims should
have been dismissed for lack of legally-sufficient evidence
causally linking Baker Perkins’ breach of contract with
the damages Cotton Bros. sustained. Baker Perkins’ ar-
gument is a threefold contention that: (a) the consoli-
dated books of the Cotton Bros. family of corporations
were used rather than only Cotton Bros.; (b) the con-
tract damages were not separated from the fire damages;
and (¢) Cotton Bros. relied on faultily-prepared regres-
sion analysis studies for its profits projections.
We find each of the arguments unavailing. Our stand-
ard of review for consideration of attacks on jury dam-
age awards is well-settled. We “consider[] all the evi-
dence and avoid{] second-guessing conflicts in the evi-
dence or credibility determinations. This court will not
disturb a jury verdict based on substantial evidence and
reasonable inferences.” Snyder v. Whittaker Corp., 839
F.2d 1085, 1090 (5th Cir. 1988) (citations omitted).
With respect to the consolidated Cotton Bros. accounts,
this evidence was appropriate given the district court’s
reformation of the Baker Perkins contract. The district
court noted Baker Perkins’ longtime association with the
Cotton Bros. operation and its understanding of how Cot-
ton Bros. operated. Moreover, substantial evidence was
introduced explaining how Cotton Bros. mitigated its
damages: by shifting Alexandria production throughout
its corporate family of bakeries. In that light, the district
court did not err in permiting evidence of Cotton Bros.’
damages to be presented on the basis of the consolidated
financial records of the corporation.
which it held that the start-up date contemplated for the contract,
based on the actions of Baker Perkins, was September 21, 1981.
The district court further correctly held that Baker Perkins prof-
fered no evidence probative on why it could not have performed the
contract within that time frame and thus declined to present the
issue to the jury.
20a
Baker Perkins’ argument that the evidence did not link
its breach of contract with the damages alleged was spe-
cifically rejected by the district court. Within the thou-
sands of pages of transcripts generated at trial are
numerous indications of the methodologies used to project
loss and the dates upon which the liability of Baker
Perkins was calculated. “Obviously,” argues Baker Perk-
ins, “the fire caused far greater damage than any delay
which may have been caused by Baker Perkins.” That
fact, however, is neither obvious nor proven on the record.
What is clear from consideration of the evidence is that
after the jury was presented both sides of the argument,
it was instructed specifically on the requirements under
state law that a causal link be proven between the breach
and the damages alleged,’ and arrived at a reasonable
calculation of both the damages and the degree to which
Cotton Bros.’ own fault contributed to the delay in the
12 The district court instructed:
The primary aim or principal of the law of damages for
breach of contract is to place the plaintiff in the same position
in which he would have been if the contract had been fulfilled.
Or to place the plaintiff in the same position which he would
have occupied had the breach of contract not occurred. In de-
termining whether Cotton Brothers had sustained any damages
attributable to Baker Perkins breach of contract, you must
keep in mind that under Louisiana law first damages in breach
of contract must be proven with reasonable certainty and sec-
ondiy a claim for the lost profits cannot be supported by a
mere statement of loss nor by speculation or conjecture unless
direct evidence is unavailable. But in cases where direct evi-
dence is not available to establish the exact extent of loss
caused by a breach of contract report [sic] the customary or
foreseeable profits as a measure of damages is proper. In
other words, it is Cotton Brothers!’] burden to prove by a pre-
ponderance of the evidence that the damages Cotton Brothers
claims from Baker Perkins including loss of profits were in
fact sustained and if so, that such damages were caused by
Baker Perkins. Under Louisiana law a party to a contract
remains responsible for the damages caused by its breach of
that contract so long as the other contracting party has acted
reasonably and within its legal rights.
2la
start-up date. Our review of the evidence discloses no
grounds upon which to disturb the findings of the jury.
Finally, Baker Perkins argues that the trial court erred
in allowing Cotton Bros. to employ the “least squares”
method of regression analysis to calculate the projected
earnings component of its lost earnings, basing its projec-
tions solely on past earnings data. Baker Perkins was
afforded ample opportunity to cross-examine witnesses who
undertook the projections in question, and to present
evidence contrary to the testimony of opposing witnesses.
Cf. Wilkins v. University of Houston, 654 F.2d 388, 403
(5th Cir.1981) (“Ideally, when a multiple regression anal-
ysis is used, it will be the subject of expert testimony and
knowledgeable cross examination from both sides. In this
manner, the validity of the model and the significance of
its results will be fully developed at trial, allowing the trial
judge to make an informed decision as to the probative
value of the analysis.”), vacated, 459 U.S. 809, 103 S.Ct.
34, 74 L.Ed.2d 47 (1982), on remand, 695 F.2d 134 (5th
Cir.1983). While the least squares method is subject to
misuse, we do not find that its use in this instance gave a
legally insufficient basis for the jury to make its findings.
The district court did not err in permiting the evidence.
Baker Perkins’ Claim for the Unpaid Contract Price
Baker Perkins argues that the trial court erred by
directing a verdict against its claim for the $209,000 con-
tract balance which Cotton Bros. stipulates remains un-
paid. We agree. The district court found that Baker
Perkins could not charge Cotton Bros. for that portion of
the contract price attributable toward accelerated per-
formance as Baker Perkins failed to perform its obliga-
tions timely.’* Lousiana law provides that “fi]ln case of
‘8 We note further that only $165,575 of the $209,000 was allo-
cable toward the acceleration premium; the remainder constituted
accounts payable from contracts not directly involved in this
litigation.
22a
reciprocal obligations, the obligor of one may not be put
in default unless the obligor of the other has performed
.. . his own obligation.” La.C.C. art. 1993. Cotton Bros.
may only collect damages for Baker Perkins’ failure to
perform its obligations under the accelerated schedule if
it pays the acceleration premium. This is especially true
in a case in which Cotton Bros. has successfully argued
in the IRI litigation that it is due compensation from its
insurer for having paid the acceleration premium. The
trial court erred; Baker Perkins is due this sum.
Prejudgment Interest
Baker Perkins contends that the trial court erred by
awarding prejudgment interest from the date of judicial
demand rather than the date of entry of judgment. The
crux of this contention is that the amount Baker Perkins
owed Cotton Bros. was not ascertainable until judgment
was granted. Baker Perkins relies on Alexander v. Bur-
roughs Corp., 359 So.2d 607 (La.1978), as support for its
argument. That case lends little succor to Baker Perkins’
position. Alexander was a redhibition case in which the
plaintiff (a receiver for a computer purchaser), sought
and received damages for the redhibitory defect and attor-
neys’ fees. The court discussed the long-standing issue
of whether legal interest ran from the date of formal
demand for rescission or from the date of judgment, and
held that the plaintiffs’ claim was ascertainable on the
former. The court further held that legal interest on
attorneys’ fees, which were not awarded until entry of
judgment, were to be dated from that day as that was the
date at which they became ascertainable. 359 So.2d at
613-14.
Baker Perkins takes the attorneys’ fees portion of
Alexander and stretches it to encompass the facts at bar.
Its contention is that the precise amount of damages were
not determined until the jury rendered its verdict.
23a
A more recent case, Mini Togs Products, Inc. v. Wal-
lace, 513 So.2d 867 (La.App.1987), carefully explains
Alexander and its codicil precedents in the context of a
contractual—rather than redhibitory—dispute and ar-
rives at a lucidly-explained conclusion that contract dam-
ages, even though unliquidated and not precisely ascer-
tainable until judgment, are “due from the moment of
active violation of the contract or from the time defendant
was put in default which was no later than the commence-
ment of the suit. Defendant’s debt or obligation to pay
money damages bears legal interest from the time the
damages were due.” 513 So.2d at 874. The court based
its conclusion on an analysis of the Alexander court’s use
of ‘ascertainable.”’
In using the term “ascertainable” the court did not
mean that the precise amount of the claim need be
liquidated or established without dispute in order for
legal interest to commence in a coniract claim. In the
Alexander case the amount of recovery was in dispute
throughout with the amount awarded by the district
court being changed by the court of appeal and then
again by the supreme court. What was meant was
that a debt or claim for the payment of money or
damages under a contract is ascertainable and be-
comes due on the date an active violation occurred
or the obligor was put in default, which can be earlier
but never later than judicial demand, and legal
interest runs from that date.
Mimi Togs, 513 So.2d. In light of this recent appellate
explanation of Alexander by former Chief Circuit Judge
Pike Hall,’* Baker Perkins’ argument to the contrary is
not persuasive. Cf. Meeks v. Huntington Sch., Inc., 489
So.2d 435 (La.App.1986) (fiinding fault with Alexander,
and holding that in salary case, the dispute is whether
interest dates from due date or date of judicial demand,
1 Now an Associate Justice of the Louisiana Supreme Court.
24a
and settling on the former). Interest accrues from the
date of judicial demand; the district court did not err.
Conclusion
The trial court erred by awarding Cotton Bros. a double
recovery as against IRI, and Cotton Bros.’ judgment for
claims arising from its business interruption insurance is
MODIFIED to $912,288.08. The district court’s award
of statutory insurer penalties is likewise MODIFIED to
reflect only a penalty on the amounts awarded, $484,877.36
for the business interruption, and $324,735 in expediting
expenses.
The district court erred as a matter of law by directing
a verdict against Baker Perkins in its $209,000 claim
against Cotton Bros. That judgment is REVERSED,
and judgment is RENDERED in favor of Baker Perkins
on that claim.
Subject to the modifications contained herein, the judg-
ments appealed are AFFIRMED.”
15 For clarity, we restate that all of the judgments now before
the court are rendered as follows:
1. Cotton Bros. v. IRI. Modified and rendered in the amount
of $912,238.03. Affirmed in the amount of $324,735. Subtract-
ing the equitable credit of $427,460.67, the net judgment is
$809,613.40 plus prejudgment interest and 12% penalties dat-
ing from January 12, 1983.
2. Cotton Bros. v. Baker Perkins. Affirmed in the amount of
$1,342,624. Prejudgment interest to date from February 7,
1984.
3. Baker Perkins v. Cotton Bros. Reversed and rendered in
the amount of $209,000. Prejudgment interest to date from
February 21, 1984.
25a
IN THE UNITED STATES DISTRICT COURT FOR
THE WESTERN DISTRICT OF LOUISIANA
ALEXANDRIA DIVISION
Civil Action No. 83-0150
COTTON BROTHERS BAKING COMPANY, INC.
versus
INDUSTRIAL RISK INSURERS
Civil Action No. 83-0578
COTTON BROTHERS BAKING COMPANY, INC.
versus
BAKER PERKINS, INC.
Civil Action No. 83-3237
BAKER PERKINS, INC.
versus
COTTON BROTHERS, INC.
26a
For Cotton Brothers Baking Company, Inc.:
DERMOT C. MCGLINCHEY and HENRI WOLBRETTE, III
MCGLINCHEY, STAFFORD, MINTZ & CELLINI
653 Magazine Street
New Orleans, LA 70130
FREDERICK B. ALEXIUS
PROVOSTY, SADLER AND DELAUNAY
Hibernia National Bank Building, Eighth Floor
Alexandria, LA 71301
For Industrial Risk Insurers:
P. ALBERT BINEVENU, JR., and JOHN W. WATERS, JR.
BIENVENU, FOSTER, RYAN & O’BANNON
1400 American Bank Building
New Orleans, LA 70103
HOWARD? B. GIST, JR.
GIST, METHVIN, HUGHES & MUNSTERMAN
Post Office Box 1871
Alexandria, LA 71301
For Baker Perkins, Inc.:
ESMOND PHELPS, II
PHELPS, DUNBAR, MARKS, CLAVERIE & SIMS
Thirtieth Floor, Texaco Center
400 Poydras Street
New Orleans, LA 70130
NAUMAN S&S. SCOTT
United States District Judge
OPINION
[Filed Jul. 31, 1989]
We have jurisdiction under 28 U.S.C. 1332. There is
diversity of citizenship between the plaintiffs and the
27a
defendant and the matter in controversy exceeds, exclusive
of interest and costs, the sum of $10,000.00.
Plaintiffs reside in and the instant claim arose in the
Western District of Louisiana. Venue therefore lies in
this district under 28 U.S.C. 1391 (a).
Plaintiffs Cotton Brothers Baking Company, Inc.
(Alexandria bakery) and Cotton Bros. Inc. (parent com-
pany) have brought suit against Industrial Risk Insurers
(IRI) claiming damages under an interruption of busi-
ness policy (IRI policy) issued by IRI on October 1, 1980
in favor of three (including Alexandria bakery) of five
corporate bakery subsidiaries owned and operated by
Cotton Bros., Inc. Cotton Bros., Inc. was not included
in the IRI policy as a named insured.
The interruption of business occurred as the result of
a fire in the Alexandria bakery plant, Alexandria, Loui-
siana on February 13, 1981.
Under the provisions of the IRI policy the only named
insured eligible to bring suit for an interruption result-
ing from a fire on the property of the Alexandria plant
was Cotton Brothers Baking Company, Inc. Suit was
filed on January 12, 1983 against IRI for loss or reduction
of gross earnings as provided in Sections IA and IIA of
the IRI policy (earnings damages) allegedly suffered by
the Alexandria bakery during the period of interruption
following the fire of February 13, 1981. The principal
issue between the parties during the entire period of trial
from the middle of September 1986 until the Friday be-
fore Christmas of that year was the methodology to be
used in the determination of earnings damages as pro-
vided in the policy under Sections IA and IIA. Plaintiff
eontends that the books and the records of the parent
corporation are the only books and records from which
such damages can be compiled. IRI has not paid any
earnings damages as provided under Sections IA and
IIA based on the records of its named insured Cotton
28a
Brothers Baking Company, Inc. (Alexandria bakery).
IRI simply refuses to recognize any damages except those
compiled on an item by item basis in which each item
claimed must be shown to be a direct result of the fire.
IRI made a general objection to any evidence based on the
books and records of the parent company because the parent
company was not a named insured under the IRI policy.
This case was tried by the plaintiff, Alexandria bakery,
and the defendant, IRI, until our ruling on the fourth
day of May 1988. On November 4, 1987, plaintiff Alex-
andria bakery, filed a pust-trial motion to permit the
filing of a second supplemental and amending complaint.
The said complaint prayed that the parent company,
Cotton Bros., Inc., be made a party to this suit and that
the interruption of business policy issued by IRI on Oc-
tober 1, 1980 be reformed so as to include Cotton Bros.,
as a named insured effective October 1, 1980. In our rul-
ings of May 4, 1988 and July 27, 1988 we allowed the
_ supplemento! and amending complaint to be filed, made
Cotton Bros., Inc. a party plaintiff effective from the
commencement of suit, but refrained from considering
and deciding the reformation of policy issue until a hear-
ing could be had at which the parties would have an
opportunity to introduce additional evidence. That hear-
ing was held on Febrary 27, 1989 and subsequently au-
thorities were submitted by both parties. We now con-
sider, (1) the issue of whether the policy issued by IRI
on October 1, 1980 should be reformed so as to include
Cotton Bros., Inc. as a “named insured” effective October
1, 1980 and (2) all other issues remaining for decision
in this proceeding.
To the extent any of the following Findings of Fact
constitute Conclusions of Law, they are adopted as Con-
clusions of Law; to the extent any of the following Con-
clusions of Law constitute Findings of Fact, they are
adopted as such.
29a
FINDINGS OF FACT
1. Cotton Brothers Baking Company, Inc. and Cotton
Bros., Inc. are Louisiana corporations with their principal!
place of business in Alexandria, Louisiana. Defendant
Industrial Risk Insurers is an unincorporated association
with its principal place of business located outside the
State of Louisiana. No member thereof is a citizen of
Louisiana. The fire of February 13, 1981 occurred in
Alexandria, Louisiana in the Western District of Loui-
siana and plaintiffs’ claims in this proceeding exceed the
sum of $10,000.00.
29 In 1952 and for some time thereafter the Cotton
interests (Cotton) consisted of one bakery located in
Alexandria, Louisiana.
8. Therafter and prior to 1976 Cotton acquired three
additional bakeries located at Shreveport and Baton
2ouge, Louisiana and Natchez, Mississippi. After these
acquisitions the four bakeries continued to operate inde-
pendently and in competition with each other in all fields,
including management, production, and sales to the public.
4. At some time prior to 1970 Cotton became interested
in protecting these separately and independently operated
bakery businesses from financial loss of income induced
by fire or other similar or named peril.
5. With this objective in view Cotton, through its
agent Alexander & Bolton (A & B), discussed with IRI
the relative merits of coverage: i. by extra expense
insurance or 2. by interruption of business insurance.
Extra expense insurance is a form of insurance coverage
to reimburse the insured for specific items of extra ex-
pense over and above the normal expense which the in-
sured incurred as-a result of damage to the insured’s
property by an insured peril such as fire. Damages under
such a policy have no connection whatsoever to the gross
earnings of the insured.
30a
An interruption of business policy insures the owner
of a business against reduction or loss of gross earnings
during the period of interruption. Damages consist of
the reimbursement of gross earnings lost in the insured’s
business less the recurring expenses which do not con-
tinue during the period of interruption. Needless to say
the principal item of damages in such a policy is the
loss. or reduction of gross earnings as shown on the books
of the insured’s business. Also included in damages
under an interruption of business policy are items of
extra expense necessarily incurred for the purpose of
reducing loss under the policy and such expenses, in ex-
cess of nermal, as would necessarily be incurred in re-
placing any finished stock used by the insured to reduce
loss under the policy.
6. On or about 1970 Cotton and IRI chose business
interruption type coverage. Both Cotton and IRI intended
at that time and at all times thereafter through October
1, 1980 to give the Cotton bakery operation full and com-
plete interruption of business coverage. To accomplish
this in 1970 IRI issued a separate policy to cover each of
four bakeries. In this way they achieved the intent of
both parties because each of the four bakery corporations
carried on its own separate and individual operation and
business. Actually they were in competition with each
other. Each of these bakery corporations was operating
independently and separately with no interdependence
between them, manufacturing its own production for sale
on the open market, packaging its own finished products,
and selling to its own customers. Therefore the books of
each corporation could serve as a basis for the deter-
mination of gross earnings and any increase or reduction
of gross earnings over a period of time. In this way the
common intent of both parties was achieved and complete
business interruption coverage of the entire Cotton bak-
ery operation continued until the reorganization of 1976.
7. In 1976 the Cotton bakery operation was completely
reorganized. The parent company, Cotton Bros., Inc.,
3la
was created and thereafter operated the Cotton bakery
operation through seven wholly-owned subsidiaries, as
one single bakery business. The seven wholly-owned sub-
sidiaries consisted of the four bakery corporations pre-
viously owned by Cotton and three newly created non-
bakery subsidiary corporations: an insurance subsidiary,
a transportation subsidiary and a procurement subsid-
iary. The insurance subsidiary handled all the health and
welfare, self-insurance and other insurance responsibili-
ties of the parent corporation and all subsidiaries. It did
not do business with the general public. The sole respon-
sibility of the transportation subsidiary was to furnish
and satisfy the transportation needs of the parent cor-
poration and its subsidiaries. Like the insurance sub-
sidiary it did no business with the general public. The
sole responsibility of the procurement subsidiary was to
furnish raw materials, supplies and equipment required
by the parent company and its subsidiaries. Like the
other two non-bakery subsidiaries, the procurement sub-
sidiary did no business with the general public.
After reorganization none of the bakery subsidiaries
produced the entire variety of bakery products it sold
to the public, as each of them had done previous to the
reorganization. An entirely new system of yroduction
was introduced. The parent corporation dictated or al-
located to each bakery subsidiary the type and amount
of bakery items each could produce, the amount that
each could retain for its own customers, to whom each
could ship the remainder and the amount and price at
which these shipments could be made. Thus the entire
production of each was dedicated to the single bakery
business of the parent corporation, Cotton Bros., Ine.
All of this was accomplished under the direction of
Gene Cotton. When the parent corporation and the three
non-bakery subsidiaries were created in 1976, these three
non-bakery subsidiaries as well as the four formerly in-
dependert bakeries became wholly owned subsidiaries of
|
32a
the parent corporation. Gene Cotton, president and chief
executive officer of the parent corporation, was also pres-
ident and chief executive officer of all seven subsidiaries.
As such he had the power and control to carry out, on a
day to day basis, in detail the aims and purposes of the
reorganization and to see that the aims, policies and ef-
forts of all subsidiaries, including the bakery subsid-
laries, were dedicated to the promotion ayd success of
the single bakery business operated by the parent com-
pany. Thus the bakery subsidiaries lost all semblance
of their former independence. They no longer controlled
their health and welfare and other insurance, their trans-
portation or their procurement needs. Since Gene Cotton
was president and chief executive officer of each supply-
ing subsidiary as well as each consuming subsidiary, he
set the terms and conditions of all contracts and agree-
ments between the subsidiaries; including price, at which
all these inter-subsidiary services were provided. Thus
none of the agreements or contracts between the seven
subsidiaries were arm-length transactions negotiated and
concluded by officers motivated by the separate and in-
dependent interest each of the subsidiaries involved, but
rather by the interest of the parent corperation—the
single operation. In every instance these contracts
amounted to Gene Cotton, wearing one hat, doing busi-
ness with Gene Cotton wearing another hat, for the
open and declared benefit of Gene Cotton wearing the
hat of the parent company.
8. A very clear illustration of the monumental effect
which the reorganization had on the previously inde-
pendent bakery corporations is furnished by the experi-
ence of the Natchez bakery subsidiary. After reorganiza-
tion that plant produced nothing but sweet goods such as
pies, cakes, pastries and breakfast bakery products.
Ninety percent of that output was shipped to the three
other bakery subsidiaries under contracts dictated and
controlled by the parent company. These shipments were
delivered to the other three bakery subsidiaries by trans-
33a
port units furnished by the transportation subsidiary
under contracts dictated by the parent company. In order
for Natchez to compete in its sales area it was necessary
for Natchez to acquire from the three other bakery sub-
sidiaries all the rolls, buns, brown and serve, and various
types of loaves, ete. which it sold to the public. If the
comptroller was right in estimating that sweet goods
provided twenty percent of the total bakery goods neces-
sary to compete on the market then the sweet goods re-
tained by Natchez comprised twenty percent of the bakery
products sold by Natchez in its sales to the public. Thus
Natchez had to acquire eighty percent of the products
sold by it in its sales area from the other three bakery
subsidiaries. With its health, welfare and other insurance
items, its transportation needs, its procurement needs
furnished under controlled contracts; ninety percent of
its production sold to the three other bakery subsidiaries
under controlled contracts, and eighty percent of the
products sold by it being acquired by controlled contracts,
there is absolutely no way that the Natchez operations
could be considered an independent bakery business or
that its books could reflect a genuine and actual loss or
gain of gross earnings, as if it were a separate business.
We find that the recrganization converted the Cotton
bakery operation into one single bakery business owned
and operated on a day to day basis by the parent com-
pany: that the books and records of the parent com-
pany were the only books and records which could serve
as a basis for determining gross earnings of the Cotton
bakery business and that the books and records of none
of the bakery subsidiaries could serve this purpose."
9. Nevertheless in 1976 IRI, on its own initiative and
without any request or direction from Cotton, abandoned
its practice of issuing four separate interruption of bus-
iness poliices to cover each of the Cotton bakeries. Why
1In its post hearing suggested findindgs and conclusions and
supporting briefs, IRI does not address these issues.
34a
did IRI issue a single combined policy? IRI states that
it did so because the four bakery subsidiaries had become
“interdependent”. A glance at any Webster’s dictionary
will disclose that this term means “to depend upon one
another”, “mutual dependence” and “mutually depend-
ent”. How did IRI know that they had become “inter-
dependent” and what were the changes in operation which
made them “interdependent”? IRI knew that the parent
company, Cotton Bros., Inc., had been created; that Cot-
ton Bros., Inc. was now the sole owner of seven sub-
sidiaries including the bakery subsidiaries; that Gene
Cotton, president and chief executive officer of the parent
company, was also president and chief executive of each
of the seven subsidiaries; that, through its exclusive own-
ership and exclusive direction, the parent company had
assumed and exercised absolute control over the day to
day operation of each of the bakery subsidiaries; that
the parent company had utilized its absolute control to
reallocate the production of each of the bakery subsid-
iaries; that as a result of this reallocation each of the
bakery subsidiaries had ceased to produce the entirety of
the bakery products which it sold to the public. In fact,
none of them produced even one-half of the production
which each of them sold to the public. These are the
changes in operation by which the bakery subsidiaries
became “interdependent”.
IRI had to have knowledge of these changes to conclude
that the bakery subsidiaries were in fact “interdepend-
ent”. Certainly IRI was aware of the most important
element of “interdependency”—the reallocation of pro-
duction. IRI was the fire insurer, and as fire insurer,
made frequent inspections of each bakery’s machinery,
equipment and safety devices, especially at this time of
unusual change. Those IRI inspectors were certainly
aware of the exchange and relocation of machinery and
equipment made necessary by the reallocation of produc-
tion between the bakery subsidiaries and also the results
in terms of the amount and type of production each
35a
bakery subdivision was required to produce. Both Cotton
and IRI intended to give full interruption of business
coverage to the Cotton bakery operation. But having all
the factual information necessary to make the determi-
nation, they simply failed to realize that the reorganiza-
tion had merged the four formerly independent bakery
businesses into one single bakery business owned, man-
aged and operated by Cotton Bros., Inc.’
10. The evidence establishes beyond possible doubt that
the single policy issued by IRI in 1976, omitting Cotton
Bros., Inc. as a named insured, was intended to cover
the flow of gross earnings from the combined production
of the four bakery subsidiaries owned, managed, oper-
ated and controlled as a single business by Cotton Bros.,
Ine. It was the mutual mistake of IRI and Cotton that
Cotton Bros., Inc. was not identified as the sole named
insured. Having made the mistake when the policy was
issued, IRI certainly should have realized the mistake
and corrected it in April of 1977 when A & B, in corre-
spondence with Mr. Penn of IRI, questioned the validity
of the coverage and disclosed that production of the
Natchez plant was restricted to sweet items and that
ninety percent of that production was shipped to the other
three bakery subsidiaries. Mr. Penn brought an end to
the correspondence by assuring A & B that the Cotton
business was fully covered by the “blanket policy” con-
cept. Mr. Penn never explains how the “blanket policy”
concept is to be applied to earnings damages under Sec-
tions IA and IIA of the policy. Certainly IRI paid no
such damages in this case.
IRI’s failure to include Cotton Bros., Inc. as a named
insured on the policies of 1976 and 1980 effectively de-
prived Cotton of its right to make a claim under Sections
1A and 11A of the policy (earning damages), the specific
risk that IRI was paid to cover.
1In its post hearing suggested findings and conclusions and
supporting briefs, IRI does not address these issues.
86a
11. Although the failure to name Cotton Bros., Inc.,
in the policy was the mutual mistake of Cotton and IRI,
that mistake was initiated by IRI which issued the single
policy on its own form without a request or direction from
Cotton. When IRI issued its policy of October 1, 1980,
the Cotton bakery business still was operating in the man-
ner in which it had been reorganized in 1976 except that
Cotton Bros., Inc. had acquired an additional bakery
(Monroe, Louisiana). There were now five bakery sub-
sidiaries instead of four. IRI continued to require its
worksheets from the separate baker subsidiaries, but all
these worwsheets, at least all of those in evidence, were
signed by the comptroller or the vice-president of finance
of the parent company. Changes in operation for the pur-
poses of efficiency or economy were made repeatedly,
ignoring completely that each of the subsidiaries was
separately incorporated. For instance, customer routes
were regularly transferred from one bakery subsidiary to
another. Officers in the subsidiaries were promoted to the
parent company.
On October 1, 1980, IRI simply renewed the policy of
1976. There is no doubt that both Cotton and IRI in-
tended on October 1, 1980 that the IRI policy give full and
complete coverage to the Cotton bakery business. It fail-
ure to do so was the mutual mistake of Cotton and IRI.
12. On Friday, February 13, 1981, a fire erupted in
the Alexandria bakery on U.S. Highway 71 South in Alex-
andria. The Alexandria bakery was the largest. of the
bakery subsidiaries. It contained three production lines.
Its principal line was a combination line which produced
brown and serve and loaf bread. One small line produced
burger buns and the other small line produced hard
bread and hard buns. The combination line was almost
completely destroyed. Brown and serve comprised 75% to
80° of the Alexandria bakery’s production. None of the
other subsidiaries produced brown and serve. Alexandria
was Cotton’s sole source of that production.
.. ...
37a
13. The effect of the fire on the Alexandria bakery and
on the Cotton bakery business was serious. The parent
company was unable to produce loaf bread and brown and
serve products in its Alexandria plant over the months of
the interruption. For a less lengthy time is could not pro-
duce from the small lines. These products had to be pur-
chased from competitors at prices higher than Cotton’s
costs of manufacture. At times the inferior quality of the
purchased items caused dissatisfaction among Cotton cus-
tomers and even provoked cancellation of-purchase con-
tracts. Other forms of disruption were the questionable
success of making up production from other plants; the
utilization of normally productive workers (as far as the
production of bakery products was concerned) in non-
productive work such as the very substantial clean-up
operation, unforeseen repairs and the gigantic job of in-
stalling replacement equipment under supervision of
Baker Perkins representatives. Accounting personnel had
to take substantial leave from normal responsibilities to aid
specially hired accountants in the company’s attempts to
determine its losses. Immediately after the fire, Gene Cot-
ton and a number of other Cotton officials were totally
involved in clean-up efforts; in negotiations with IRI and
with Baker Perkins trying to determine what repairs or
replacement would have to be made to restore the facili-
ties that were destroyed by fire; securing contract pro-
posals, accelerating those proposals, determining the final
contract and the financing of the contract. There was
continuous contact with the same parties in their efforts
to accelerate the performance of the replacement contract
to the evident advantage of both the parent company and
IRI. Also involved were the increased costs and involve-
ment of transportation vehicles and personnel. Indeed
the effect of the fire on the parent company’s bakery busi-
ness was more than serious, it was devastating.
14. On the very day of the fire Gene Cotton contacted
Baker Perkins to send a representative to Alexandria to
38a
examine the extent of the fire damage for the purpose of
making proposals for the repair or replacement of the
damaged facilities as expeditiously as possible. Two or
three days thereafter Cotton, with the knowledge and con-
sent of IRI, flew to Saginaw, Michigan to receive and dis-
cuss Baker Perkins’ proposals and to conclude a contract
as soon as possible. Gene Cotton chose Baker Perkins for
this endeavor because Cotton had been doing business with
Baker Perkins since 1953. Most of Cotton’s equipment,
including the oven and the proofer and some of the other
equipment involved in the fire, had been manufactured by
Baker Perkins. Baker Perkins was therefore the manu-
facturer most familiar with the plant and with the capa-
bilities, the location and the pattern of operation of Cot-
ton’s machinery and equipment.
Baker Perkins first presented two proposals, one a
repair proposal and the other a replacement proposal.
Under the former proposal Baker Perkins was to com-
plete repairs of the oven and proofer by January 1982 at
a cost of $1,030,085.00. However, this was not a firm
contract. Since Baker Perkins had not been able to make
an accurate determination of the damage to the oven, and
might not be able to do so until the repaired equipment
was in operation, it reserved the right to take additional
time and make additional repairs and charges if such
repairs became necessary. Secondly, Baker Perkins pro-
posed to replace the proofer and the oven by June 1, 1982
for the price of $1,189,245.00. With the knowledge and
consent of IRI, Gene Cotton rejected these proposals be-
cause of the long length of time required for installation.
At the vigorous urging of Gene Cotton, Baker Perkins
submitted a third proposal. For an increased price of
$1,354,820.00 Baker Perkins would accelerate replace-
ment so as to assure “start-up” of normal production by
September 21, 1981. Cotton, as IRI was aware, was de-
pending on money to be received from IRI in the adjust-
ment of Cotton’s claims under the fire policy. The sig-
39a
nificant reduction in the length of the business interrup-
tion period was mutually beneficial to IRI and Cotton.
Cotton, with the approval of IRI, accepted the third
proposal.
15. The Alexandria fire illustrates the extreme inter-
dependence of the various Cotton subsidiaries and the
absolute futility of omitting Cotton Bros., Inc. as the
named insured. The bakery business, at the level at which
Cotton was competing, is a very demanding business. The
entire production for today is on customer shelves to-
morrow. The pressure to produce required Cotton to oper-
ate its bakeries 20 hours a day, 6 days a week. There is
no surplus inventory at either end of the delivery route to
ease the impact of mistake or delay. In order to compete,
the bakery products had to be fresh. The crisis here was
far different from the crisis which would have occurred if
the Alexandria bakery was still operating as a separate
and independent business on October 1, 1980. An inde-
pendent operation in Alexandria would have affected only
production and customers of the Alexandria bakery. The
evidence here precludes such a finding. In this instance,
the parent corporation was relying on its Alexandria sub-
sidiary to furnish certain bakery items, principally brown
and serve, to all of its other bakery subsidiaries. The
inability of the Alexandria bakery to produce brown and
serve was not felt by the Alexandria bakery alone. Every
bakery subsidiary in the Cotton operation lost its allocated
portion of that production. The Alexandria customers
were no more severely affected that those of Shreveport,
Baton Rouge, Monroe or Natchez. Certainly the custom-
ers of the other bakery subsidiaries were not arms length
customers of Alexandria. The reorganization had indeed
converted five independent bakery businesses into one
business owned, controlled and operated on a day to day
basis by the parent corporation.
16. Gene Cotton was the expediter in this crisis. He
had the problem of maintaining an unusually high cash
40a
flow to continue operating the highly complex and com-
petitive business described above. Suddenly he had in
addition, the responsibility and tremendous expense of
immediate replacement of a major portion of the parent
company’s production, by purchase from competitors, by
establishing new lines in other bakery subsidiaries, by re-
allocation or otherwise; an unexpected clean-up operation;
the fate of employees idled by the fire; the restructuring
of transporation and procurement to meet the crisis and,
most importantly, the execution and performance of a
replacement or repair contract.? Although it was impor-
tant to IRI that the interruption be terminated as soon
as possible, it was infinitely more important to Gene
Cotton and his business to achieve this result. He had an
additional problem. He did not have the money to do it.
IRI knew this. Baker Perkins had required that the
proofer and oven replacement contract be executed on or
before February 22, 1981. Gene Cotton had negotiated
the contract and could have accepted it immediately, had
the funds been available. Funds did become available
from IRI on March 6, 1981, and Cotton instantly tele-
phoned his acceptance to Baker Perkins, which did not
protest the delay. The major portion of the testimony by
deposition of R. F. Kelley, President of Baker Perkins,
was his amazement, mounting irritation and annoyance
at Gene Cotton’s continued, unending and persistent de-
mands for more speed, for quicker deliveries.
Gene Cotton was able to retain some of the employees
made idle by the destruction in the Alexandria plant. He
continued their employment and used them initially in
“clean-up” operations and later in the installation of
equipment under supervision of Baker Perkins. At other
times they were free to perform whatever duties the
2 For a picture of the situation immediately following the fire
see reports of meetings held by representatives of Cotton Bros.,
Inc., IRI and others. Exhibits P-67, 68A, 101, 122 and 122A. (par.
16)
4la
Alexandria bakery could find for them, such as the clean-
up and/or maintenance of equipment idled or less severly
damaged by the fire. IRI has alleged that Gene Cotton
contributed to the delay by directing these employees to
take a Christmas vacation and to perform duties other
than their duties under the supervision of Baker Perkins.
The record reflects, as noted by Mr. Kulzer below, that
there were many periods, sometimes extended periods,
when Baker Perkins failed to make scheduled deliveries
of equipment fcr installation. Cotton’s employees could
not install equipment when the equipment had not yet
been delivered. Certainly Cotton could not allow them to
remain idle during the periods of non-delivery. IRI has
failed to produce any protest by Baker Perkins or any
evidence indicating what particular Baker Perkins in-
stallation was delayed or for what period of time, or that
Gene Cotton had anything to gain by delaying Baker
Perkins. We find that due diligence and dispatch was
exercised by plaintiffs to rebuild, repair or replace the
property and equipment destroyed and/or damaged by
the fire as required by the IRI policy.
In a state of desperation at Baker Perkins’ lack of
performance, Gene Cotton hired a responsible and trusted
employee of Baker Perkins, James Reid (Reid) in Febru-
ary, 1982. Reid was the very person whom Baker Perkins
had sent to Alexandria on the day after the fire to esti-
mate and ascertain the damage done by the fire. All
Baker Perkins’ proposals for repair or replacement were
based on his findings. IRI’s Mr. Kulzer noted in his
August, 1982 report the efforts by Gene Cotton to reduce
the delays caused by Baker Perkins:
“As previously reported, Baker-Perkins incurred de-
lays in shipping and installing the equipment. The
insured constantly attempted to push B-P’s schedules
and has documented his steps carefully. His smartest
action was to hire Janus [sic] Reid away from B-P
shortly prior to shipment of the equipment. Mr. Reid
42a
supervised and expedited the instllations and obvi-
ously prevented further delays in start up with his
deep knowledge of the equipment and personal rela-
tionship with the B-P installations.” (emphasis
ours)
IRI’s contention that Gene Cotton was more interested
in modernization of the equipment, than he was in the
installing of it, is not tenable, especially when IRI men-
tions no instances in which such alleged activity affected
or delayed any specific Baker Perkins installation. In
any operation when the damaged or destroyed equipment
is replaced by new equipment, to install is to modernize.
The atmosphere of the meetings between plaintiffs and
IRI establishes that Gene Cotton was the individual who
made, far and away, the most vigorous and dedicated
effort to expedite the end of the interruption period. The
financial crisis brought on by the fire, the lack of cash
flow, could be remedied only by the resumption of normal]
production by the Cotton bakery operation. Gene Cotton
stated this position repeatedly, and his actions were con-
sistent with it.
17. Although specification of a period of interruption
can never be exact, we find that Cotton exercised the re-
quired due diligence and dispatch to rebuild, repair or
replace, at the earliest date possible, the property and
equipment destroyed in the fire of February 13, 1981 and
that production equal to February 13, 1981 production
was achieved on May 8, 1982. See paragraph 28, infra.
We agree with IRI that the delidder did not replace
any equipment damaged or destroyed by the fire. Before
the fire the delidding operation was accomplished manu-
ally by two employees. This activity occurred at the end
of the interruption period when most of the other equip-
ment had already been installed so that it did not inter-
fere seriously with installation of other equipment. How-
ever it did have the effect of extending that period. We
43a
find that 3% of the interruption period was caused by
the installation of this equipment and that Cotton Bros.
Ine. was responsible for that delay.
However, we find that Cotton’s responsibility for delay
is offset by the delay occasioned by IRI’s refusal to pay
the $1,354,820.00 March 6, 1981 proof of loss to Cotton
under IRI’s fire policy for the destruction of Cotton’s
oven and proofer. See par. 24, infra. 1RI was in contact
with Baker Perkins throughout the period around March
6. 1981 when Cotton verbally accepted the accelerated
contract to replace that equipment. Within days after
that acceptance Baker Perkins President Kelly issued an
interoffice memorandum halting performance of Baker
Perkins’ accelerated replacement contract until further
notice. We find no explanation for this inappropriate
action except Baker Perkins’ knowledge of IRI’s refusal
to pay the March 6, 1981 proof of loss. Baker Perkins’
February 22 deadline had already been exceeded by 12
days. IRI’s unlawful actions forcing Cotton to convert
$324,735.00 of the agreed fire loss to expediting expense
under the interruption of business policy consumed at
least seven or eight additional days. If that delay caused
Cotton to lose favorable placement in Baker Perkins’ list
of orders, the delay could be even more substantial.
We find therefore that both Cotton and IRI performed
acts which may have delayed “start-up” to May 8, 1982.
Although the extent of delay caused by each cannot be
ascertained, we find that they were approximately equal
so that neither party shall be penalized.*
3 We disagree with the jury in Civil Action 83-3237-A, Baker
Perkins, Inc. versus Cotton Bros., Inc. There the jury determined
that Baker Perkins, Inc. was responsible for 65% and Cotton
Bros., Inc. for 35% of that portion of the business interruption
period beginning September 21, 1981 and terminating May 8, 1982.
We have found, on the other hand, that Cotton Bros., Inc. was
responsible for 3% of the delay during that period, and that IRI
was equally responsible so that neither of them shall be penalized.
44a
18. IRI’s contention that the adoption of Baker Per-
kins’ repair proposal would have assured “start-up” in
45 weeks is irrelevant since IRI was as fully responsible
as Cotton for rejecting the repair proposal and accepting
the accelerated replacement contract.
It is also completely discredited by the evidence. The
repair proposal, on its face, was not a firm proposal. It
explicitly limited repairs to those defects apparent at the
time of initial examination and, very significantly, did
not cover defects which might be disclosed after the equip-
ment went into operation. Baker Perkins reserved the
right to require additional time and additional money to
accomplish any repairs not apparent at the time of the
original examination. In fact subsequent inspections dis-
closed that the proofer was a total loss and that the oven
could not be repaired to meet safety standards. Neither
could be repaired; both had to be replaced.
In addition, unlike the two replacement contracts which
provided for “start-up” by June 1, 1982 and September
21, 1981, respectively, the repair proposal provided only
that the physical repair of the proofer and the oven would
be completed in 45 weeks. This language is on the face
of the proposal. Mr. Reid who drafted the proposal for
Baker Perkins emphasized repeatedly in his testimony
that additional tests, including tests with dough in the
pans, had to be completed successfully before “start-up”
could be achieved. The time necessary to accomplish this
is always uncertain. It could be three weeks; it could be
three months. IRI’s contention must be rejected.
19. Immediately after the fire, each of the parties
formed a team of certified public accountants to adjust
the plaintiffs’ claims under the interruption of business
policy. The plaintiffs’ team was composed of members of
Ernst & Whinney, CPAs, including Arthur J. Parham,
and was headed by Percy Raybourn, Vice President of
45a
Finance of Cotton Bros., Inc.* This team also included
representatives from W. E. Long & Company, specialists
in bakery operations. The team designated by IRI was
composed of members of the firm, Matson, Driscoll &
Damico, CPAs, led by Michael Driscoll, a senior partner
in the firm.
None of the members of the Cotton team had any edu-
cation, training or experience in the adjusting of insur-
ance claims and particularly claims under interruption
of busines policies. The IRI team, on the other hand,
did have such experience; all of them were intimately
famitiar with and had been involved in the adjusting of
interruption of business claims. Driscoll was not simply
a CPA, he was offered by IRI and recognized by this
Court as an expert in interruption of business insurance
who had been involved in the adjustment or litigation
of over one thousand interruption of business claims. In
most of these instances, he had represented insurance
companies and had been retained many times by IRI.
20. The IRI policy was intended to provide full cov-
erage for the Cotton bakery business. The oniy named
insureds were three of the subsidiary bakeries in the
Cotton Brothers operation, located in Alexandria, Shreve-
port, and Natchez: Cotton Brothers Baking Company,
Inc., Cotton Baking Company, Inc., and Cotton’s Holsum
Bakers, Inc., respectively. The policy did not mention
Cotton Bros., Inc. as a named insured, although Cotton
Bros., Inc. had been operating the Cotton bakery opera-
4 For reasons undisclosed by the record, a rift occurred between
Cotton and Alexander & Bolton on or about the time of the Febru-
ary 18, 1981 fire. No member of that firm was included in the
Cotton team or took part in the determination of Cotton’s claim
methodology or the drafting of interruption proofs of loss. There
is no evidence that Cotton sought or received their advice on those
subjects. The only evidence of any activity on their part was their
attendance at some of the meetings mentioned in Note 2, supra,
and Gene Cotton challenged their presence at those meetings.
46a
tion as a single bakery business on a day to day basis
since the reorganization of 1976. However, the policy de-
scribed five locations (Alexandria, Shreveport, Natchez,
Baton Rouge, and Monroe) as covered premises and fur-
ther provided that the loss of any of these locations should
be adjusted with and payable to the subsidiary bakery
corporation located at the site of the loss. Separate cov-
erage amounts were assigned to each location and aggre-
gated on October 1, 1980 to $39,816,000.00.
21. We have found previously that both Cotton and
IRI intended in 1976 and all times thereafter through
October 1, 1980, to give the Cotton bakery operation full
and complete interruption of business coverage. However,
the fire on February 13, 1981, compelled IRI to re-
examine its policy and its position as insurer under that
policy. It had possessed, since the reorganization of 1976,
all the information necessary to determine that the sub-
sidiary bakeries, though still incorporated, had become so
interdependent with the other subsidiaries and so com-
pletely controlled by the parent corporation that they
were merely production plants for the bakery business
owned, controlled and being operated on a day to day
basis by the parent company.
Raybourn has testified that the indebtedness of the
subsidiaries {except the procurement subsidiary) was
paid out of the general fund of the parent corporation.
If IRI did not know this prior to February 13, 1981, it
certainly knew it shortly thereafter, when IRI had ac-
cess to the books of these subsidiaries while auditing the
claims submitted by Cotton. IRI knew specifically that
all of the replacement equipment ordered in the name of
the Alexandria plant; invoiced, shipped to, installed in,
and belonging to the Alexandria plant; was paid for out
of the general fund of Cotton Bros., Inc.
IRI, at some time during the auditing period and prior
to September, 1981, knew that the IRI policy, as written,
did not provide interruption of business coverage to the
EE
47a
Cotton bakery business as was intended by all parties to
the policy. They knew that, after the 1976 reorganiza-
tion, the bakery subsidiaries had lost their separate iden-
tities and had become so interdependent with the other
subsidiaries and so dominated and controlled by Cotton
Bros., Inc. that they were no longer viable and proper
interruption of business insureds. Although IRI stoutly
proclaims the validity of its policy, there is not one in-
stance in which it has shown or even suggested that a
claim for earnings damages can be supported by the books
of the Alexandria bakery. Not one of its experts, includ-
ing Driscoll, has made such a declaration. The fact that
the books and records of the named insured. Cotton
Brothers Baking Company, Inc. (the Alexandria bakery
subsidiary), cannot serve as a basis for a claim for earn-
ings damages under the IRI policy, is the basic element
of IRI’s strategy of defense to avoid the payment of earn-
ings damages under Sections IA and IIA of the policy.
It knew that Cotton Bros., Inc. was the only party own-
ing and operating the Cotton bakery business so that
Cotton Bros., Inc. alone had an interruption of business
risk. Had IRI continued the good faith that it had ex-
hibited during the 10 years that it had been collecting
premiums from Cotton, it, on its own initiative, could
and should have issued an endorsement making Cotton
Bros., Inc. a named insured, thus providing Cotton the
interruption of business coverage for which Cotton had
paid. Instead, IRI chose to ignore the evidence before
it; to profit by its inadvertent omission of Cotton Bros.,
Inc. as a named insured; to ignore its duty to correct
that mistake so that the Cotton bakery business would re-
ceive the interruption of business coverage intended.
This is the beginning of IRI’s strategy to defeat inter-
ruption of business coverage by depriving the Cottons of
access to the books and records of Cotton Bros., Inc. This
effort began shortly after the fire of February 13, 1981,
as above set forth and has continued to this day. From
the very commencement of this proceeding, IRI has made
48a
a continuing objection to the admission of evidence based
on the books and records of the parent company to estab-
lish earnings damages as provided in the policy. Its sole
basis for that objection is that Cotton Bros., Ine. is not
a named insured in the policy. IRI’s strategy is further
reflected in the pleadings and throughout the trial of this
suit including its strenuous opposition to the reformation
of the policy. We find that IRI should have made Cotton
Bros., Inc. a named insured on its own initiative at some
time prior to September 1981, in order to give full in-
terruption of business insurance coverage to the Cotton
bakery business which had been operated by Cotton Bros.,
Ine. on a day to day basis since the reorganization of
1976. Indeed, upon a simple letter request it did make
Cotton Bros., Inc. a named insured with no additional
payment of premium by an endorsement dated July 28,
1982.5 We find that its failure to make such an endorse-
ment during the auditing period prior to September 1981
was a breach of its prior intent and its duty to give full
interruption of business coverage to the bakery business
owned and operated by Cotton Bros., Inc., IRI’s failure
to do so was part of a scheme to deny such coverage to
Cotton and its failure to act was arbitrary, capricious
and in absolute bad faith.
5 At the request of A & B, IRI, without protest, made- Cotton
Bros., Inc. a named insured by an endorsement dated July 28, 1982.
Since there was no difference in Cotton’s method of operation be-
tween October 1, 1980 and July 28, 1982, we consider this an ad-
mission by IRI that Cotton Bros., Inc. could have been included in
the policy as a named insured on October 1, 1980. In order to
carry out the intention of the parties and afford the Cotton bakery
business the coverage it had been paying for since 1970, Cotton
Bros., Inc. should have been so named.
The last paragraph of Post-fire Endorsement No. 8, dated Sep-
tember 26, 1981, was included at IRI’s initiative and requested by
no one. These endorsements establish that endorsements were
regularly made by IRI in a most informal manner and on its own
initiative.
49a
22. IRI hired Matson, Driscoll & Damico on February
18, 1981, only five days after the occurrence of the fire.
They were retained by IRI because, according to their
testimony, they were not in the usual business of audit-
ing but specialized in adjusting interruption of business
claims. Driscoll was qualified and offered by IRI and ac-
cepted by the Court as an expert on the adjustment of in-
terruption of business claims.
Cotton’s team of auditors knew nothing about interrup-
tion of business insurance, but they did know that no
items listed in any proof of loss submitted by them to
IRI would be paid without the approval of IRI based on
the recommendation of IRI’s auditing team. Conse-
quently, Percy Raybourn, by telephone, by personal con-
tact and in meetings, sought advice, help and recommen-
dations from Michael Driscoll and other members of IRI’s
team for developing a proper methodology to calculate
Cotton’s interruption of business losses. The result—
6 Testimony of Arthur J. Parham, Jr., Tr. vol. 22 pp. 4978-4981.
Q What was your understanding, Mr. Parham, about what
your task was regarding assisting Mr. Raybourn to prepare
some sort of methodology for computing this claim?
A Mr. Raybourn indicated we were going to have to try to
identify each and every type of expense, lost revenue, that
sort of thing and on a line item by line item approach in order
to submit claims to the insurance company that they would
accept.
Q Okay, Mr. Parham, I want to show you a document cap-
tioned methodology for computing the cost of business inter-
ruption which has previously been admitted in evidence as
plaintiff’s exhibit 66 and ask you if you recognize that?
Yes, sir, I do. I wrote this.
You wrote it?
This memorandum.
What was its purpose, sir? ~
> OP >
The purpose was as I mentioned a moment ago to begin
the document and approach if you would methodology to as-
semble the information necessary to submit claims to the in-
surance company and as you see if you read through this, it
~ 50a
STONEWALL. Conversation, pleasantries, but—STONE-
WALL.
was very detailed in the sense that there were a number of
specific line items mentioned and we thought it necessary at
that point based on the suggestions of the insurance company
and its representative to go through and try to quantify each
and every one of the items to submit a claim.
Q Did you ever meet with any representative of the insurance
company to determine whether their line item approach was
what the insurance company wanted?
A Together with several other people from my firm, Ernst and
Whinney and several management people at Cotton Brothers.
I say several, I think it was just Mr. Raybourn. We met with
Mr. Mike Driscoll of the Madison Driscoll firm of Alexandria
I think sometime in late March of 1981 and we viewed this
methodology.
Q With Mr. Driscoll, was it your impression or your under-
standing of what Mr. Driscoll’s feelings were?
A Well, before any work was done of a significant nature
before investing a lot of time, we wanted to make sure that
the approach that Mr. Raybourn had originally thought neces-
sary was going to be acceptable to the insurance company.
We didn’t want to spend a lot of time doing something that
would have to be redone so we reviewed the contents of this
document with Mr. Driscoll at that point.
Q And what is anything did he indicate regarding this
document?
A He indicated that a line item approach would be necessary
in order to submit a claim.
He made some suggestions about some of the things in this
document as well.
Q You remember any of the specifics of that?
A Not really.
Q If, Mr. Parham, at the time you prepared this, did you
expect that the methodology cutlined in this document would
be able to account for all of the actual losses sustained by
Cotton Brothers as a result of this business interruption?
A Well, I guess early on I had hoped that such a formulation
such methodology would but it became obvious fairly soon
there was just no way that an approach like this coud gather
5la
Receiving no advice or direction from the IRI team,
the Cotton team was forced to proceed, relying solely on
its auditing expertise and the IRI policy. The Cotton
auditors were intimately familiar with the Cotton bakery
operation and they knew that the business was a single
bakery business owned and operated by Cotton Bros.,
Inc. They also became aware that the books and records
of the Alexandria subsidiary could not serve as a basis
for interruption of business claims as described in the
October 1, 1980 policy. Faced with a policy offering
only the books and records of the Alexandria bakery sub-
sidiary as a basis for a reduction of gross earnings loss,
how could they possibly draft a methodology or a proof
of loss as described in Schedule IA and IIA of the policy?
However, had Cotton Bros., Inc. been included as a named
insured, it is probable that the Cotton team could have
drafted an appropriate methodology under which inter-
ruption of business claims by Cotton Bros., Inc. could be
determined. The policy, as written and without including
Cotton Bros., Inc. as a named Insured, rendered this prob-
ability an impossibility. Receiving no advice or instruc-
tion from IRI or the IRI team, the Cotton team began its
labors to draft a methodology containing no items relat-
ing to reduction of gross earnings. In fact, earnings. the
very risk being insured, is not even mentioned—only “line
items” directly connected with the fire. Finally, on May
8, 1981, (here we quote the IRI brief)
“The Cotton team delivered to Driscoll the final draft
of a document which they had developed entitled:
all the costs and all the lost revenue that the company was
experiencing.
Q First you thought it could and later you decided it could
not?
A Yes, sir, due to my lack of prior business interruption
experience at that point I though maybe we could capture all
the information we needed but it was impossible once we got
into it in more detail. (emphasis ours)
52a
“Methodology for Computing the Cost of Business
Interruption”. The approach had been developed by
Raybourn and the Cotton team and Driscoll felt that
the approach was proper. He did not make or sug-
gest changes in the metodology. [sic] His roll [sic]
was to audit Cotton’s claims submissions which
would follow, in order to review and then discuss
with the Cotton team any accounting problems, prior
to expected meetings between Cotton and IRI. He
was not asked by IRI to and did not calculate the
loss.” (emphasis-ours and citations to transcript
omitted )
Could there be a more precise, a more deliberate stra-
tegy of concealment, of bad faith?
Although IRI chose experts eminently qualified in the
field of interruption of business insurance, it deliberately
instructed them to make no use of that expertise. IRI
deliberately instructed its experts to remain silent and to
make no corrections and give no advice on the methodology
employed in the drafting of an interruption of business
claim—just audit no matter how inappropriate the meth-
odology may be. The STONEWALL strategy was in-
structed by IRI and examination of the methodology and
the proofs of loss submitted by the Cotton team disclosed
no items which fit Driscoll’s definition of an interruption
of business claim. See paragraph 23, infra. Yet, when
Cotton’s methodology was presented to Driscoll on May 8,
1981, “Driscoll felt that the approach was proper.” Dris-
coll, mindful of IRI’s instructions, said nothing; made no
correction or suggestion. We find that IRI’s instruction,
in conjunction with its failure to make Cotton Bros., Inc.
a named insured, was intended to induce error by Cotton.
The instruction was made for the illicit purpose of inhibit-
ing and defeating Cotton’s right to file any claim for
earnings damages under Sections IA and IIA of the
policy. The stonewall position of IRI was arbitrary, ca-
pricious, in bad faith and without probable cause.
a es a
53a
23. IRI has contended and continues to contend
through this entire proceeding that the only damages
available to plaintiffs under the policy are “line by line”
or “line items” directly connected with the fire. This con-
tention simply crystalizes in a different form IRI’s deter-
mination to deny Cotton’s right to earnings damages. It
defies the clear and concise language of Sections IA and
IIA. See paragraph 29, infra. It defies the definition
supplied by IRI’s own expert Driscoll, who testified:
“Well, basically when you are looking at a business
interruption loss you are confined or you are more
interested in the profit and loss section of a financial
statement that would be your sales, your various
costs of sales elements .... And what you eventually
try to do is you try to project just like a company
would try to project what they are going to do next
year. You try to project what the company would
have done for the period of interruption had there
been no loss then you compare it to what they actu-
ally did do and the different number is the amount
of loss.”
Yet, through the device of IRI’s strategy, Cotton has been
induced to make claims limited to so-called line items and
has been deprived of the right to make a claim under the
principal risk insured by the policy. IRI knew and knows
that its Form E policy is entitled BUSINESS INTER-
RUPTION GROSS EARNINGS FORM. The form pro-
vides for two types of damages: 1) reduction of gross
earnings during the period of interruption as described
in Section IA and Section IIA of the policy and by the
quote of Michael Driscoll referred to above, and 2)
expenses related to reducing loss as described in Section
III. If the damages recoverable under Sections IA and
IIA are in law a determination of reduction of gross
earnings during the period of interruption, then IRI has
paid no reduction of gross earnings damages. Not one
item paid under the proofs of loss can satisfy Driscoll’s
54a
definition of that type of damage. When asked about
Raybourn’s line by line methodology for the determination
of interruption of business losses, Driscoll stated:
“T don’t know what the—where the term line by line
came from. The method is not referred to the
methodology and first preparation of the claim
which was in three segments by Cotton Brothers is
now regarding or referred to as line by line and that
is basically in his method. I assume it must have
been his terminology, certainly was not mine.”
The fact that certain witnesses such as Gene Cotton and
Raybourn might have testified that items in the proofs of
loss were Section IA and IIA damages must be attributed
to their lack of knowledge and experience and to the mis-
guidance or lack of guidance induced by the strategy
adopted in bad faith by IRI as described in paragraphs
21 and 22 above. A policy restricting damages to line
item claims is an extra expense policy. We have found
previously that Cotton, on the advice of IRI, rejected
extra expense coverage in favor of interruption of busi-
ness coverage. See paragraphs 5 and 6, supra. IRI, in
absolute defiance of Sections IA and IIA, has restricted
damages to those afforded by an extra expense policy.
This is yet another example of IRI’s arbitrary, capri-
cious and bad faith attempt to deny, without probable
cause, Cotton’s right to earnings damages as provided in
Sections IA and ITA.
24. The February 13, 1981 fire brought extreme finan-
cial strain on Cotton’s bakery operation. Lack of suffi-
cient cash flow and of sufficient funds to pay Baker
Perkins for the replacement equipment, made replace-
ment contingent upon IRI’s payments under the fire pol-
icy. This is why it was necessary for Cotton to secure
IRI’s agreement to Cotton’s choice of the accelerated con-
tract for the replacement of the oven and proofer for the
sum of $1,354,820.00. IRI agreed to that choice and
55a
IRI’s adjuster, Jarratt, drafted and presented to Cotton
a proof of loss in the amount of $1,354,820.00 as payment
under the fire policy for the loss of the oven and the
proofer. Gene Cotton signed and accepted this proof of
loss on March 6th and returned it to IRI for payment.
Based on IRI’s commitment, and thinking that full pay-
ment was assured, Gene Cotton, on that very afternoon,
called Baker Perkins by telephone and accepted the
$1,354,820.00 replacement contract. Cotton was com-
mitted. IRI then refused payment. Now Cotton was
compromised. Cotton had exercised extrordinary diligence
in its efforts to rebuild and restore in the shortest time as
possible to the evident benefit of both IRI and itself. It
had been successful in securing the contractor most capa-
ble of doing a competent job in the shortest time possible.
It had settled its claim against IRI for the loss of the
proofer and the oven for a sum proposed by IRI’s own
agent. IRI now refused to pay. Incredible!
Cotton vigorously protested that the proof of loss pre-
sented by Jarratt on behalf of IRI became an enforceable
contract settling the claim when accepted on March 6,
1981 by Gene Cotton. But IRI, possessor of the money,
was prosecutor, judge and jury. Cotton had no means of
enforcing its enforceable contract. It could not sue. Time
was of the essence. As IRI well knew the destruction of
the oven and proofer was a loss insured under the fire
policy, not the interruption of business policy, and Jar-
ratt’s proposal, as it should, agreed to pay Cotton the
exact cost (agreed to by IRI) of replacing that equipment.
From his previous conversations and negotiations with
IRI, Cotton was well aware of the conditions under which
IRI would agree to restore the payment originally pro-
posed by Jarratt. Cotton was forced to accept payment
of $1,030,085.00, $234,735.00 less than originally offered
by Jarratt (IRI), for the loss under the fire policy. This
is the cost suggested by Baker Perkins under its repair
proposal, which was lowest of the three proposals sub-
56a
mitted by Baker Perkin and, as we have previously found,
was not a firm proposal or a viable alternative.
IRI had a vital interest in the accelerated contract.
That contract advanced the termination of the period of
interruption from June 1, 1982 to September 21, 1981.
IRI suggests that, at the gratuitous request of Cotton’s
attorney, Alexius, it had gratiously advanced $324,735.00
as expediting expense to be repaid to IRI if Baker Per-
kins failed to perform the accelerated contract timely.
IRI calls it Cotton’s gamble. We find that IRI advanced
nothing. Viewed with its contemporanous refusal to pay
the full amount of the March 6, 1981 proof of loss, we
call it a strong-arm attempt by IRI to shift to Cotton the
entire risk of Baker Perkins possible failure to perform.
The first paragraph of the proposal letter of Alexius
referred to by IRI is as follows: *
“Pursuant to our several conversations, Cotton
Bros. Baking Company, Inc., is willing to propose a
solution to the adjustment problems which have
arisen since IRI rejected the proofs of loss prepared
by GAB and submitted by Mr. Cotton on March 6,
1981. You are advised, however, that our proposition
is made in a spirit of compromise only, and is not to
be considered a derrogation [sic] from our prior
position that an enforceable contract of settlement
matured when Mr. Cotton accepted your March 6,
1981, proposal.” (emphasis ours)
We find that IRI’s actions as set forth above were
deliberate, arbitrary, capricious, in absolute bad faith
and without probable-cause.
25. In a slightly similar situation the Cotton team had
claimed on its September, 1981 proof of loss the sum of
$182,655.00, as cost of the cascade, a piece of equipment
used to in-load the proofer. IRI paid that item. Later
* Exhibit P-137, IRI’s Exhibit No. 1.17.2.
57a
IRI, characterizing this piece of equipment as “expediting
expense’, reduced their later payment to Cotton by this
amount. Although the purchase of this equipment ex-
pedited nothing, we find that Cotton had agreed to pay for
that item and to its characterization as “expediting ex-
pense” as a vehicle to repay IRI. IRI was entitled to
reimburse itself for the $182,655.00 that it had paid by
this arrangement with Cotton.
26. In Civil Action No. 83-3237, entitled Baker Per-
kins, Ine. v. Cotton Bros., Inc., the latter cross-claimed
for damages including loss of gross earnings damages
and received a jury award of $1,342,624.00. The entire
jury award consisted of loss of gross earnings suffered
by Cotton Bros. Inc. from the projected date of comple-
tion of Baker Perkins’ accelerated contract, September
21, 1981, to May 8, 1982.
CONCLUSIONS OF LAW
27. As we have shown previously, it has been the in-
tention of Cotton and IRI since 1970 to give the Cotton
bakery operation full insurance protection and coverage
against the risk of loss or reduction of gross earnings as
defined in the policy during any period of interruption
of business as defined in the policy. This is what the
parties intended and this is what the policy was designed
to accomplish.
The Cotton bakery operation in 1970 consisted of four
separate corporations, each of which owned and operated
their separate bakery businesses just as they had done
prior to the acquisition by the Cottons. There was no
interdependency among them. They operated in competi-
tion with each other. Thus, although they were owned by
Cotton, they were separate and independent bakery busi-
nesses and it followed from this that the books and rec-
ords of each would reflect accurately the increase or de-
crease in gross earnings for specific periods of time.
58a
Cotton’s bakery operation was effectively insured by
making the individual bakery corporations named _ in-
sureds and this coverage continued to be effective as long
as the bakery business of each of these companies con-
tinued to be operated independently, separately and in
competition with each other.
~ However after the reorganization of 1976, there was
but one Cotton bakery business and that one business was
owned, controlled and operated on a day to day basis by
Cotton Brothers, Inc. Thus Cotton Brothers, Inc. was the
sole indispensable named insured in any policy designed
to give interruption of business coverage to the Cotton
bakery business.
Under Louisiana law, an insurance policy may be re-
formed after proof that it does not express the actual
contract intended by the parties due to mutual error or
mistake. Kolmaister v. Connecticut General Life Insur-
ance Co., 370 S.2d 630 (La. App. 4th Cir. 1979), writ
denied, 373 So.2d 531 (La. 1979). See Phillips Oil Co. »v.
OKC Corp., 812 F.2d 265 (5th Cir. 1987). Where, as
here, the mutual mistake concerns identity of the named
insured and destroys coverage on the risk actually as-
sumed by the insurer, the insurer is estopped to deny its
liability even in the absence of reformation and estopped
from opposing reformation of its policy to cover such
risks incurred by the party at interest. Bonadona v.
Guccione, 362 So.2d 740 (La. 1978); Fontenot v. Amer-
ican Fidelity Fire Ins. Co., 386 So.2d 165 (La. App. 3d
Cir. 1980).
It is our conclusion that, through the mutual mistake
of Cotton and IRI, Cotton Bros., Inc. was not ineluded as
a named insured in the policy issued in 1976; that the
renewal of that policy on October 1, 1980 perpetuated
the error; that neither Cotton nor IRI intended in 1976
or 1980 to reduce the full interruption of business cover-
age afforded previously by the fovr separate interruption
- 59a
of business policies and that the policy issued October 1,
1980 should be reformed so as to include Cotton Bros.,
Inc. as a named insured effective October 1, 1980.
28. We have found that Cotton exercised due diligence
and dispatch to rebuild, repair or replace, at the earliest
date possible, as required by the policy, the property and
equipment destroyed in the fire of February 13, 1981 and
that production equal to the February 13, 1981 production
was achieved on May 8, 1982. We conclude therefore that
the period of interruption extended from February 13,
1981 to May 8, 1982, inclusive.
29. IRI drafted its October 1, 1980 renewal policy on
an IRI Form E entitled “BUSINESS INTERRUPTION
GROSS EARNINGS FORM FOR MANUFACTURING
OR MERCANTILE OPERATIONS” (emphasis ours). The
policy provides for two types of damages: 1) reduction of
gross earnings as provided in Section IA and IIA, and
2) expenses related to reducing loss as provided in Section
IITA. We shall not discuss the latter type because there
is no dispute regarding IRI’s payment of Section III
claims. Reduction of gross earnings are described in the
policy as follows:
SECTION I
A. Recovery in the event of loss hereunder shall be
the ACTUAL LOSS SUSTAINED by the In-
sured resulting directly from such interruption
of business, but not exceeding the reduction in
gross earnings less charges and expenses which
do not necessarily continue during the interrup-
tion of business, for only 2uch length of time as
would be required with the exercise of due dili-
gence and dispatch to rebuild, repair or replace
such described property as has been damaged or
destroyed, commencing with the date of such
damage or destruction and not limited by the
date of expiration of this Policy. Due considera-
60a
tion shall be given to the continuation of normal
charges and expenses, including payroll expense,
to the extent necessary to resume operations of
the Insured with the same quality of service
which existed immediately preceding the loss.
SECTION II
A. GROSS EARNINGS—For the purpose of this
insurance “gross earnings’ are defined as the
sum of:
1. total neét sales value of production (manufac-
turing operations),
2. total net sales of merchandise (mercantile
operations), and
3. other earnings derived from operations of the
business, less the cost of:
4. raw stock from which such production is
derived,
5. supplies consisting of materials consumed di-
rectly in the conversion of such raw stock into
finished stock or in supplying the service(s) sold
by the Insured,
6. merchandise sold, including packaging mate-
rials therefor, and
7. service(s) from outsiders (not employees of
the Insured) for resale which do not continue
under contract.
No other costs shall be deducted in determining
gross earnings. Jn determining gross earnings
due consideration shall be given to the experi-
ence of the business before the date of damage or
destruction and the probable experience there-
after had no loss occurred, (emphasis ours)
6la
The purpose of the damages provided in Sections I and
II above are described by Driscoll, as we have previously
quoted: “you try to project what the company would have
done for the period of interruption had there been no
loss then you compare it to what they actually did do and
the different number is the amount of loss.” The policy
language above “sets forth the formula for calculating the
amount actually lost by an insured when business is inter-
rupted, and allows the business to remain in the same
financial condition as before the loss.’ United Land In-
vestors, Inc. v. Northern Insurance Co. of America, 476
So.2d 432 (La. App. 2d Cir. 1985). See also Cora Pub,
Inc. v. Continental Casualty Co., 619 F.2d 48 (5th Cir.
1980).
The formula for calculating the insured’s loss is in
terms of reduction of gross earnings, as quoted verbatim
above from the policy, and is “unambiguous and consti-
tute[s] the law between the contracting parties.” United
Land Investors, supra at 436 (citing Rogers v. American
Ins. Co., 338 F.2d 240 (8th Cir. 1964); Associated Pho-
tographers v. Aetna Casualty and Surety Co., 677 F.2d
1251 (8th Cir. 1982); Kastern Associated Coal Corp. v.
Aetna Casualty and Surety Co., 642 F.2d 1068 (3d Cir.
1980) ).
A ‘projection’ of earnings is an accepted method of
calculating business interruption loss. See Associated
Photographers, supra. Indeed, the policy language -ap-
proves, if not requires, the use of ‘projected’ earnings:
In determining gross earnings due consideration
shall be given to the experience of the business before
the date of damage or destruction and the probable
experience thereafter had no loss occurred. (empha-
sis ours)
Accordingly, we hold that the projections presented by
plaintiff of its business interruption losses conform to the
terms of the policy.
62a
Cotton has submitted for our consideration three pro-
jections as a basis for its claim of reduction of gross
earnings damages.
Lost earnings need only be proved to a reasonable cer-
tainty. See Borden, Inc. v. Howard Trucking Co., 454
So.2d 1081 (La. 1983). The law does not require mathe-
matical precision or absolute exactness in determining the
amount of lost earnings: “the trier of fact must be af-
forded much discretion in the determination of such dam-
ages where the evidence clearly shows that damage is
proven but not capable of proof to a mathematical or legal
certainty.” Rosenblath v. Louisiana Bank & Trust Co.
432 So.2d 285, 290 (La. App. 2d Cir. 1983). See Palmer
v. Connecticut Railway & Lighting Co., 311 U.S. 544,
561, 61 S.Ct. 379, 85 L.Ed. 336, 343 (1941) (“Certainty
as to the amount goes no further than to require the basis
for a reasoned conclusion.”’) Accordingly, where it is not
possible to state or prove a perfect measure of lost earn-
ings, “courts have reasonable discretion to assess damages
based upon all the facts and circumstances of the case.”
Tide Craft, Inc. v. Red Ball Oxygen Co., 514 So.2d 664
(La. App. 2d Cir. 1987), writ denied, 516 So.2d 135-36
(La. 1987). See Roshong v. Travelers Ins. Co., 281 So.2d
785, 789 (La. App. 3d Cir. 1973).
Among the three projections presented by Cotton at
the trial, labelled the- “yellow”, “blue”, and “gray” pro-
jections, we consider the blue projection of $4,498,000.00
on lost income for the period February 14, 1981 through
May 8, 1982, as the best calculation of damages.
Our reasons for choosing the blue projection are
straightforward.
The “blue” projection was prepared by Parham of
Ernst & Whinney using the “least squares method” to
forecast earning through the interruption period. Par-
ham used the audited financial statements of the parent
Cotton Bros., Inc. for the years 1976 through 1980, less
63a :
non-recurring expenses, and with “historical data points”,
calculated a “regression analysis projection”. The pro-
jected earnings were then subtracted from the actual
earnings. The blue projection corresponds exactly to the
method set forth in the policy and attested to by Driscoll
(par, 23, supra).
The “gray” projection, also prepared by Parham,
freezes Cotton’s 1980 earnings and simply projects the
1980 earnings without assuming any increase (or de-
crease). On the other hand, the blue projection is based
precisely on the years (1976-1980) before the fire when
Cotton operated as a single bakery operation following its
reorganization.
The “yellow” projection, although prepared before the
fire, was prepared by Cotton management, not by an in-
dependent CPA or auditor. Further, this ‘internal’ pro-
jection is based only on the years 1978-1980 and _ uses,
instead of actual income, a formula of “converting pounds
produced to sales’. Also, because Cotton prepared the
yellow projection to support an application for a large
bank loan, it is, more probably than not, too optimistic.
IRI objects to the use of Cotton’s projections, citing
Wilkins v. University of Houston, 654 F.2d 388 (5th Cir.
1981), on petition for rehearing, 662 F.2d 1156 (5th
Cir. 1981). Wilkins warns that statistical evidence “must
be employed with great care’ even if such evidence is
the “best, if not the only, means” of proof available.
Wilkins, supra at 403. In particular, IRI complains that
Cotton’s projections fail to account for Cotton’s loss of
a major contract with Winn-Dixie, for a labor strike and
for the effects of a recession. Cf. Wilkins, supra at 402.
However, these events occurred after the period of busi-
ness interruption ended, May 8, 1982.
We conclude therefore that Cotton is entitled to
$4.498.000.00 as damages under Sections IA and IIA of
64a
the policy, with interest as set forth in paragraph 33,
infra.
30. IRI made the following payments under the policy:
3-23-81 $ 162,367.50
9-15-81 $1,425,289.35
1-29-82 $ 912,250.32
12-22-82 $1,053,276.00
4-4-83 $ 32,578.80
$3,585,761.97
The issue of what part of these payments if any
should be considered earnings damages under Sections
IA and IIA has not been addressed by the parties. Ob-
viously, since only reduction of earnings damages are in
contest, only reduction of earnings damages paid by IRI
should be credited against IRI’s reduction of earnings
liability. We cannot determine from the record what
proofs of loss were paid or rejected by IRI or the grounds
upon which such actions were taken. Nor can we deter-
mine which categories of claimed losses properly belong
under Section III and which have been allocated to Sec-
tions IA and IIA.* This compels the conclusion that IRI
is entitled to no credit whatsoever for payment of earn-
ings damages. This conclusion, though eminently rational,
offends equity. It is certainly possibly that IRI paid cer-
tain cost items which do not fit the definitions of Sections
8 We find that the record, though vast, is not sufficient in detail
for us to determine the basis on which items of the proofs of loss
were paid or rejected by IRI. We have determined however that
there are no items related to reduction of gross earnings as de-
scribed in Sections IA and IIA so that none of the cost items
recognized and paid by IRI fit the description in the policy on the
definition of its expert, Driscoll. Therefore, as a matter of right,
IRI is not entitled to credit for the payment of any IA and IIA
damages whatever. However, in its trial memorandum filed Sep-
tember 30, 1986 (page 3) IRI declares that $427,460.67 of the funds
paid by it to Cotton represent payment for claims for reduction of
gross earnings less non-continuing charges and expenses.
65a
IA and IIA or Section III but which in some way involved
or affected earnings. IRI itself has stated, without ex-
planation, that it paid $427,460.67 in earnings damages
and $3,158,302.10 [sic] in “extra expenses’. As we have
declared previously, we cannot verify the accuracy of this
allocation. We do know that IRI paid $3,585,761.97 in
total damages, and that they state that $3,158,302.10 of
that amount was Section III damages. The remaining
$427,460.67 in cost items cannot be classified legally as
earnings damages as defined by the policy. Nevertheless
the $427,460.67 was accepted by Cotton and we hold in
equity that IRI should receive credit. However, because
this credited amount was part of IRI’s scheme to restrict
Cotton’s recovery to line item damages and to deny Cotton
any Section [A and ITA damages, IRI’s credit shall not
be applied until Cotton’s total damages plus penalties,
interest and attorney’s fees have been adjudged.
We recognize that the $182,655.00 (cost of cascade)
was rightfully withheld by IRI. That item was withheld
with the assent of Cotton as repayment for the cost of the
cascade.
31. We have held that IRI is not entitled to the
$324,735.00 so-called “expediting expense” because that
money belonged to Cotton under the fire policy proof of
loss drafted and presented by IRI’s Jarratt to Cotton and
accepted by Gene Cotton on March 6, 1981. See par. 24,
supra. That acceptance made IRI absolutely and uncon-
ditionally liable for $1,354,820.00 as payment under the
fire policy for the loss of the oven and proofer. Under
La.R.S. 22:658, IRI was absolutely and unconditionally
obliged to pay the full amount of that accepted proof of
loss on or before sixty days from March 6, 1981.
We hold IRI’s refusal to pay the full amount of the
March 6,-1981 proof of loss drafted and presented by
IRI and accepted by Cotton was arbitrary, capricious, in
bad faith and without just cause and that Cotton should
66a
have judgment against IRI in the amount of $324,735.00
with penalties and attorney’s fees under La.R.S. 22.658
and interest.°
32. In Civil Action No. 83-3237, entitled Baker Perkins,
Inc. versus Cotton Bros., Inc., the latter cross-claimed for
damages, including loss of gross earnings damages, and
received a jury award of $1,342,624.00 for loss of gross
earnings. Louisiana law is well-settled that an insurer is
entitled to be subrogated to the rights of its insured after
payment of the latter’s claim. La. C.C. art. 1829; Aetna
Insurance Co. v. Naguin, 488 So.2d 950 (La. 1986) ; Joe
E. Freund, Inc. v. Insurance Company of North America,
261 F.Supp. 131 (W.D. La. 1966).
IRI is not entitled to subrogation so long as the IRI
policy does not Cotton Bros., Inc. as a named insured.
Since we have reformed the policy to make Cotton Bros.,
Inc. a named insured, and since the entire jury award
consisted of earnings damages suffered by Cotton Bros.,
Inc., IRI is entitled to subrogation and is entitled to
credit against the principal award, penalties, attorney’s
fees and prejudgment interest in favor of Cotton Bros.,
Inc. in this proceeding.’°
* We have jurisdiction here. Cotton has specifically contested
IRI’s reduction of the $1,354,820.00 due Cotton for the fire loss of
the oven and proofer on the ground that the mutually executed
proof of loss was an enforceable contract settling that claim (see
La. R.S. 22:658), reserving all of its rights. We simply have acted
on the rights so reserved.
10 Plaintiff has cited Fort Motor Credit Co. v. State Farm Mutual
Automobile Insurance Co., 309 So.2d 914 (La. App. 3d Cir. 1975)
and Powers v. Calvert Fire Insurance Co., 216 S.C. 309, 57 S.E.2d
638 (1950) as authority for the contention that subrogation in
this proceeding is an equitable doctrine and should not be available
to IRI because IR! joined with Baker Perkins, Inc. in contesting
the claim of Cotton Bros., Inc. to loss of earnings damages. We
hold that those authorities are not pertinent here. IRI has a per-
fect right to contest plaintiff’s claims to such damages as part of
its own defense in this proceeding and the equitable doctrine en-
67a
However, IRI is not entitled to subrogation until it has
paid to Cotton Bros., Inc. the entire amount of the judg-
ment rendered in this Opinion. Upon such payment by
IRI, the jury verdict and judgment for Cotton Bros.,
Inc. in Civil Action No. 83-3237 shall become the property
of IRI. Cotton Bros., Ine. shall make a written legal
assignment to IRI upon IRI’s request. IRI shall assume
the costs (and risks) of collecting the judgment rendered
in Civil Action No. 83-3237.
33. Louisiana law governs the award of prejudgment
interest, and 28 U.S.C. § 1961 governs the award of post-
judgment interest in this case. Nissho-wai Co. v. Occi-
dental Crude Sales, Inc., 848 F.2d 613 (5th Cir. 1988).
Under Lauisiana law, legal interest is due “at least
from date of judicial demand on a claim for damages aris-
ing out of breach of contract, regardless of whether the
precise amount of the claim is unliquidated, disputed or
not ascertainable with certainty at the time suit is filed.”
Mini Togs Products, Inc. v. Wallace, 513 So.2d 867 (La.
App. 2d Cir. 1987), writs denied, 515 So.2d 447 (La.
1987). See also, Smith v. State Farm Fire and Casualty
Co., 695 F.2d 202 (5th Cir. 1983) (interest on penalty
and fee awards under LSA-R.S. 22:658 also commences
from date of judicial demand).
Accordingly, plaintiffs shall receive legal interest from
the date suit was filed in accordance with La. C.C. art.
2924, and from date of judgment in accordance with 28
U.S.C. $1961 on the entire amount of the judgment
rendered in this Opinion.
nunciated in plaintiff’s authorities cannot be interpreted to deprive
IRI of that right.
It is possible, despite the American rule, that IRI’s subrogation
should be reduced by reasonable attorney’s fees expended by Cotton
in its suit against Baker Perkins. Because of the attorney’s fees
awarded under LSA-R.S. 22:658, we refuse to do so. See para. 34,
infra.
68a
34. LSA-R.S. 22:658 provides that insurers who arbi-
trarily, capriciously, or without probable cause fail to pay
any claim within sixty days of proof of loss" are liable
for the amount of the loss as well as a penalty of 12%
of “the total amount of the loss” and all reasonable attor-
ney’s fees “for the prosecution and collection of such
loss.” If the insurer has made a “partial payment’, the
penalty is 12% of the difference between the amount
tendered and the amount actually owed. LSA-R.S. 22:658.
See Fuqua v. Aetna Casualty & Surety Co., 542 So.2d
1129 (La.App. 3d Cir. 1989).
Whether an insurer’s failure or refusal to pay its
arbitrary, capricious or without probable cause within
the meaning of the statute is a question of fact to be
determined in light of the facts and circumstances of the
particular case. Smith v. State Farm Fire and Casualty
Co., 695 F.2d 202, 205 (5th Cir. 1983) (citations omitted).
In particular, it is a determination that “depends pri-
marily on the facts known to the insurer at the time of its
actions.” Scott v. Insurance Co. of America, 485 So.2d
50, 52 (La. 1986). “The words arbitrary and capricious
.. . do not necessarily imply an opprobrious connotation.”
Steadman v. Pearl Assurance Co., 167 So.2d 527, 531
(La. App. 4th Cir. 1964). Rather, arbitrary conduct
merely “implies an abuse of one’s authority or power.”
Id. Further, the fact that an insurer mis-reads or mis-
interprets the clear and unambiguous provisions of its
own policy does not relieve the insurer of liability under
LSA-R.S. 22:658. Fidelity & Casualty Co. of N. Y. v.
Superior Casing Crews, Inc., 642 F.2d 147, 150 (5th Cir.
1981). The insurer, not the insured, takes the risk of
misinterpreting its own policy provisions. Marks v.
Trinity Universal Insurance Co., 531 So.2d 516 (La.
11 A ‘satisfactory proof of loss’ for purposes of LSA-R.S. 22:658
is that which provides the insurer with sufficient facts to apprise
the insurer of the insured’s claim or to acquire knowledge of the
insured’s loss. See Hart v. Allstate Insurance Co., 437 So.2d 823
(La. 1983).
69a
App. 2d Cir. 1988). Insurers are “charged with knowl-
edge of their policy’s contents.” Carney v. American
Fire & Indemnity Co., 871 So.2d 815 (La. 1979). Ae-
cordingly, an insurer may be deemed arbitrary and capri-
cious for failing to properly assess and pay damages which
fully compensate the insured, where the policy requires
that the insured be fully compensated. Higginbotham v.
New Hampshire Indemnity Co., 498 So.2d 1149 (La.
App. 3d Cir. 1986).
The facts of this case are distinctive. The stonewall
position undertaken by IRI, which conduct we find as
arbitrary, capricious, in absolute bad faith and without
probable cause, precluded Cotton from submitting a proof
of loss that would have compensated Cotton as provided
for by IRI’s policy. To this very day, IRI resists any
claims calculated according to Sections IA and IIA of its
policy. This conduct is an absolute abuse of IRI’s ‘power’
and position as ultimate arbiter of what losses are prop-
erly payable under its policy provisions. IRI’s conduct
goes beyond mere breach of contract. It offends accept-
able notions of business ethics.
IRI’s refusal to assist Cotton in caiculating claims
properly payable to Cotton under the policy constitutes
precisely the conduct which Louisiana law proscribes. An
insurer must timely pay what is due the insured. IRI has
never even deigned to consider what is properly due
Cotton and certainly there can be no doubt that IRI knew
that Cotton was entitled to interruption of business
(earnings) damages.
Accordingly, IRI is liable for the statutory penalty of
12% on the $4,498,000.00 in earnings not paid under
IRI’s business interruption policy and $324,735.00 not
paid under IRI’s property damage (fire) policy and for
the attorney’s fees '* incurred by Cotton in prosecuting
2 The decision on the merits is a “final decision” for purposes of
appeal as a matter of law under 28 U.S.C. § 1291 even though the
70a
its claim against IRI, with interest on the whole as set
forth in paragraph 33.
CONCLUSION
35. IRI issued an interruption of business policy in
favor of the three (really all five) subsidiary bakeries as
named insureds and intended to cover the Cotton bakery
business. All parties admit that the fire of February 13,
1981 was an occurrence in the contemplation of the policy
and that it took place on the prroperty of a named
insured, the Alexandria subsidiary. Indeed IRI has paid
substantial Section IIIA damages under the policy. The
primary purpose of the policy was to protect Cotton’s
income, i.e. the possible reduction of gross earnings which
might be suffered by the Cotton bakery business during
the period required to restore production as it existed on
the date of the fire (interruption of business damages
under the provisions of Sections IA and iJA). As we
have seen, not one item of damage paid by IRI.fits the
definition of interruption of business (reduction of earn-
ings) damages as defined by its own expert or by its
policy. IRI has not paid one cent in earnings damages.
It follows that if the fire had occurred at the Shreveport,
amount of attorney’s fees for the litigation remains to be deter-
mined. Budinich v. Becton Dickinson and Co., 486 U.S. , 108 S.Ct.
1717, 100 L.Ed.2d 178 (1988).
The parties may stipulate by compromise the amount of attor-
ney’s fees. If they have not done so prior to September 10, 1989,
Cotton Brothers Baking Company, Inc. and Cotton Bros., Inc. shall
file on or before October 10, 1989 a motion to set attorney’s fees,
including fees for the filing and submission of this motion and
also projected or suggested fees for answering and trial of appeal
if any. Plaintiffs should file with their said motion all bills sub-
mitted and paid and all supporting documentary evidence along with
appropriate authorities and suggested findings of fact and conclu-
sions of law. Local Rule 20.16 of the Western District of Louisiana.
IRI may file opposition on or before November 10, 1989 accom-
panied by any supporting documentary evidence, authorities and
suggested findings of fact and conclusions of law.
T1la
Monroe, Natchez or Baton Rouge plant, under IRI’s inter-
pretation of the policy and under its Strategy, it would
have been liable for the same amount of interruption of
business damages—none, Following IRI’s interpretation
and strategy to its logical conclusion, IRI, under its
$39,000,000.00 interruption of business policy was obliged
to pay no interruption of business damages. The inter-
ruption of business risk was solely the risk of Cotton
Bros., Inc. IRI cannot be allowed to avoid all business
interruption (earnings) damages, simply because of its
own failure to include Cotton Bros., Inc. as a named
insured in the policy. We have determined that IRI’s
contentions are not persuasive.
We conclude therefore, that as a matter of law:
That the interruption of business insurance policy
number 31815935 issued October 1, 1980 by Industrial
Risk Insurers in favor of Cotton Brothers Baking Com-
pany, Inc., et al should be reformed so as to make ard
include Cotton Bros., Inc. as a named insured effective
October 1, 1980; that
There should be judgment in favor of Cotton Brothers
Baking Company, Ine. and Cotton Brothers, Ine. and
against Industrial Risk Insurers in the amount of
$324,735.00 plus penalties and attorney’s fees under
LSA-R.S. 22:658 with pre-judgment interest from Janu-
ary 12, 1983 in accordance with Louisiana Civil Code
article 2924 and post-judgment interest thereon in accord-
ance with 28 U.S.C. § 1961; that
There should be judgment herein in favor of Cotton
Brothers, Ine. and against Industrial Risk Insurers in
the amount of $4,498,000.00 plus penalties and reason-
able attorney’s fees under LSA-R.S. 22:658 with pre-
judgment interest thereon from January 12, 1983 in ac-
cordance with Louisiana Civil Code article 2924 and post-
judgment interest in accordance with 28 U.S.C. § 1961,
less a credit against this total amount allowed and decreed
eee aaa
72a
in equity in favor of Industrial Risk Insurers in the
amount of $427,460.67;
That, upon payment by Industrial Risk Insurers to
Cotton Bros., Inc. of the entire amount (less credit)
awarded in the preceding paragraph, Industrial Risk In-
surers shall be subrogated to all rights, title and interest
of Cotton Bros., Inc. in and to Civil Action No. 83-3237
of the United States District Court for the Western Dis-
trict of Louisiana entitled Baker Perkins, Inc. versus
Cotton Brothers, Inc. and in accordance with said sub-
rogation and upon request of Industrial Risk Insurers,
Cotton Bros., Inc. should execute in favor of Industrial
Risk Insurers a valid, legal and written assignment of
all its rights, title and interest in Civil Action No. 83-
3237 described above.
DONE AND SIGNED at Alexandria, Louisiana, this
31st day of July, 1989.
/s/ Nauman § Scott
United States District Judge
73a
IN THE UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
No. 90-4128
COTTON BROTHERS BAKING COMPANY, INC.,
Plaintiff-A ppellee,
versus
INDUSTRIAL RISK INSURERS,
Defendant-Third Party
Piaintiff-A ppellant,
versus
BAKER PERKINS Foop MACHINERY, INC..
Third-Party Defendant-
Appellant.
COTTON BROTHERS BAKING CoMPANY, INC.,
Plaintiff-A ppellee,
versus
BAKER PERKINS, INC.,
Defendant-A ppellant.
BAKER PERKINS, INC..
Plaintiff-A ppellant,
versus
COTTON BROTHERS BAKING CoMPANY, INC..
Defendant-A ppellee.
Appeals from the United States District Court
for the Western District of Louisiana
T4a
SUBSTITUTED OPINION ON REHEARING
(Opinion September 18, 1991, 5th Cir.,
1991, F.2d ——)
(January 6, 1992)
Before POLITZ, WILLIAMS, and JONES, Circuit
Judges.
PER CURIAM:
The opinion of this court dated September 13, 1991,
as revised on denial of rehearings dated October 10,
1991, is reported at 941 F.2d 380 (5th Cir. 1991).
On November 25, 1991 we sua sponte recalled our man-
date for further consideration of the applications for re-
hearing. We now revise and correct our original opin-
ion which, as revised and corrected herein, is reaffirmed
and reinstated. Other than as granted herein, the peti-
tions for rehearing are denied. The mandate shall issue
forthwith.
The portion of the opinion subtitled “The IRI Litiga-
tion,” reported at 941 F.2d 385 and enumerated as head-
note [2], is deleted and the following is substituted:
IRI raises three issues on appeal. First it asserts
that the trial court erred by not crediting $3,585,761.97
which it had paid under the business interruption
policy against the $4,498,000 damages judgment
rendered by the district court. IRI contended on ap-
peal that the trial court granted the award to Cotton
solely in satisfaction of Section IA of the policy.
The record does not support that contention. Section
IA notes the insured’s rights to receive loss of earn-
ings damages; Section IIA defines such damages and
establishes the method of ascertaining such. These
sections, in full, provide as follows:
75a
SECTION I
Recovery in the event of loss hereunder
shall be the ACTUAL LOSS SUSTAINED
by the Insured resulting directly from such
interruption of business, but not exceeding
the reduction in gross earnings less charges
and expenses which do not necessarily con-
tinue during the interruption of business.
for only such length of time as would be
required with the exercise of due diligence
and dispatch to rebuild, repair on replace
such described property as has been dam-
aged or destroyed, commencing with the
date of such damage or destruction and not
limited by the date of expiration of this
Policy. Due consideration shall be given
and expenses, including payroll expense, to
the extent necessary to resume operations
of the Insured with the same quality of
service which existed immediately preced-
ing the loss.
SECTION II
GROSS EARNINGS.—For the purposes of
this insurance “gross earnings” are defined
as the sum of:
1. total net sales value of production
(manufacturing operations) ,
2. total net sales of merchandise (mer-
cantile operations), and
3. other earnings derived from operations
of the business, less the cost of:
4. raw stock from which such production
is derived,
es lies consist f aterials con-
2. Supplles consisting of materials con
sumed directly in the conversion of such
76a
raw stock into finished stock or in supply-
ing the service(s) sold by the Insured,
6. merchandising sold, including packaging
materials therefor, and
7. service(s) purchased from _ outsiders
(not employees of the Insured) for resale
which do not continue under contract.
No other costs shall be deducted in deter-
mining gross earnings. In determining
gross earnings due consideration shall be
given to the experience of the business be-
fore the date of damage or destruction and
the probable experience thereafter had no
loss occurred. (Emphasis ours. )
Michael Driscoll was IRI’s lead expert on inter-
ruption of business insurance. He headed the IRI
committee empowered to approve or reject proofs
of loss for such insurance claims. When asked how
interruption of business claims should be deter-
mined he testified: “You try to project what the
company would have done for the period of inter-
ruption had there been no loss, then you compare
it to what they actually did do and the different
number is the amount of the loss.” When Cotton’s
auditors sought instructions from Driscoll on the
committee’s requirements for the payment of these
proofs of loss, Driscoll directed a “line item” pro-
cedure which is appropriate only for claims under
Section III of the policy. Section III only indirectly
relates to damages. Under the policy Cotton was
obligated to mitigate damages. Section III entitled
Cotton to repayment for each item of expense it in-
curred in its efforts to mitigate damages during the
15 months in which its business was interrupted.
Section III provides in pertinent part:
77a
SECTION III
A. EXPENSES RELATED TO REDUCING LOSS.
—This Policy also covers:
1. such expenses as are necessarily incurred for
the purpose of reducing loss under this Pol-
icy (except expense incurred to extinguish a
fire), and
2. such expenses, in excess of normal, as would
necessarily be incurred in replacing any fin-
ished stock used by the Insured to reduce
loss under this Policy... .
As instructed, the claims were presented to IRI’s
committee using the line item procedure and pay-
“23)
ments of $3,585,761.97 were made.
This issue is brought into proper perspective when
we focus on the purpose of this insurance—to pro-
tect Cotton from losses caused by business interrup-
tion, including loss of earnings and additional ex-
penses incurred in an effort to stay in business.
As a result, however, of tactics described by the dis-
trict court as “stonewalling,” which we discuss in
the subsection on statutory penalties reported at
941 F.2d 386-87 and enumerated as headnote [4],
Cotton did not make the computations detailed in
Section IIA. No proofs of loss of such damages were
ever invited or submitted and none were paid. The
record is devoid of acceptable evidence showing that
IRI made any payments whatever for business in-
terruption losses. In this settling, we must reject
IRI’s contention that it is entitled as a matter of
law to a credit against the damages award for the
payment of the $3,585,761.97, other than the credit
for the $427,460.67 allowed in equity by the dis-
trict court.
The last two paragraphs of that portion of the opin-
ion subtitled “Statutory Penalties,” reported at 941 F.2d
ee
78a
387 and enumerated as headnote [5], is deleted and the
following is substituted:
We reject the IRI contention that the district court
erred in assessing statutory penalties on the entire
$4,498,000 (less $427,460,67) which it awarded Cot-
ton Brothers on the business interruption policy, as
well as on the $324,735 awarded on the fire policy.
We perceive no error therein.
The first paragraph of that portion of the opinion
subtitled “Conclusion,” reported at 942 F.2d 932, is
deleted and we substitute the following:
IRI’s assignments of error are rejected.
Finally, we delete paragraph 1 of footnote 15, reported
at 941 F.2d 392, and substitute the following:
1. Cotton Bros. v. IRI. Affirmed in the amounts of
$324,735 and $4,498,000 (less a credit of $427,460.67)
plus statutory penalties under La. R.S. 22:658, and
prejudgment interest from January 12, 1983 to date
of judgment under Louisiana Civil Code article 2924
and post-judgment interest as provided by 28 U.S.C.
§ 1961. Upon issuance of our mandate the district
court may award appropriate attorney’s fees as dis-
cussed in this opinion.
79a
IN THE UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
No. 90-4128
COTTON BROTHERS BAKING COMPANY, ING.,
Plaintiff-A ppellee,
versus
INDUSTRIAL RISK INSURERS.
Defendant-Third Party Pla inti ff
Appellant,
versus
BAKER PERKINS Foop MACHINERY, INC..
Third Pa rty Defe ndant-A ppellant.
COTTON BROTHERS BAKING COMPANY, INC..
Plaintiff-A ppelle 6.
versus
BAKER PERKINS, INC..
Defendant-A ppe llant.
BAKER PERKINS. INC..
Pla inti ff-A pp llant,
versus
COTTON BROTHERS BA KING COMPANY, INC..
De fe ndant-A ppellee.
te
ORDER
[Filed Mar. 6, 1992]
80a
Appeals from the United States District Court
for the Western District of Louisiana
Before POLITZ, WILLIAMS and JONES, Circuit Judges.
BY THE COURT:
IT IS ORDERED that the motion of appellant Indus-
trial Risk Insurers’ to recall mandate in the referenced
eause is DENIED.
/s/ HAP
2/18/92
/s/ JGW
2-20-92
/s/ ENJ
3/3/92
Sla
UNITED STATES COURT OF APPEALS
FIFTH CIRCUIT
No. 90-4128
COTTON BROTHERS BAKING COMPANY, INc.,
Plaintiff-A ppellee,
V.
INDUSTRIAL RISK INSURERS,
Defendant/Third-Party
Plaintiff-A ppellant,
¥e
BAKER PERKINS Foop MACHINERY, INC.,
Third-Party Defendant-
Appellant.
COTTON BROTHERS BAKING CoMPANY, INC.,
Plaintiff-A ppellee,
Ws
BAKER PERKINS, INC.,
Defendant-A ppellant.
BAKER PERKINS, INC.,
Plaintiff-A ppellant,
Ve
COTTON BROTHERS BAKING COMPANY, INC.,
Defendant-A ppellee.
Appeal from the United States District Court
for the Western District of Louisiana
Nauman S. Scott, Judge
82a
Oct. 10, 1991
ON PETITIONS FOR REHEARING
(Opinion September 13, 1991, 5th Cir.1991, 941 F.2d 380)
Before POLITZ, WILLIAMS, and JONES, Circuit
Judges.
PER CURIAM:
The opinion of this court reported at 941 F.2d 380 (5th
Cir.1991), as ecrrected and revised herein, is reaffirmed
and reinstated.
We delete the final paragraph on slip op. page 6144 and
substitute:
The court erred, however, in assessing statutory
penalties on the entire $4,498,000 which it awarded
Cotton Bros. on the business interruption policy, as
well as the $324,735 awarded on the fire policy. Hav-
ing modified that portion of the judgment to
$912,238.03, we affirm the assessment of penalties
only as applied to that amount plus the $324,735 fire
policy award. In addition, after issuance of the man-
date the trial court may award attorney fees, as it
deems appropriate, on this aspect of the judgment.
We delete the first numbered paragraph of footnote 15,
slip op. page 6151, and substitute:
1. Cotton Bros. v. IRI. Modified and rendered in the
amount of $912,238.03. Affirmed in the amount of
$324,735. The net judgment is thus $1,236,973.03
plus the statutory penalty of 12% ($148,436.76),
with prejudgment interest on those amounts dating
from January 12, 1983.
As revised, the original opinion is REINSTATED.
Other than the foregoing, the petitions for rehearing
filed herein are DENIED.
83a
IN THE UNITED STATES COURT OF APPEALS
lOR THE FIFTH CIRCUIT
No. 90-4128
CoTTON BROTHERS BAKING COMPANY,
Plaintiff-A ppellee,
versus
INDUSTRIAL RISK INSURERS,
Defendant-Third Party
Plaintiff-A ppellant,
versus
BAKER PERKINS FooD MACHINERY, INC.,
Third Party Defendant-
Appellant.
CoTTON BROTHERS BAKING COMPANY,
Plaintiff-A ppellee,
versus
BAKER PERKINS, INC.,
Defendant-A ppellant.
BAKER PERKINS, INC.,
Plaintiff-A ppellant,
versus
CoTroN BROTHERS BAKING COMPANY,
Defendant-A ppellee.
ORDER
[Filed No. 25. 1991]
84a
Appeals from the United States District Court
for the Western District of Louisiana
ORDER:
The Court hereby recalls its mandate sua sponte issued
in the above cause on November 4, 1991 pending further
consideration of this case before this Court.
/s/ Henry A. Politz
United States Circuit Judge
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.