Appendix — Southwest Marine, Inc. v. San Diego Bay Keeper

Supreme Court brief2001

Ask Donna

What actually matters in this document.

Text

la

APPENDIX

UNITED STATES COURT OF APPEALS

FOR THE NINTH CIRCUIT

Nos. 99-56532, 99-56545

D.C. No. CV-96-01492-RMB

Natural Resources Defense Council; San Diego Baykeeper,

Kenneth J. Moser,

Plaintiff-Appellees,

V.

Southwest Marine, Inc.,

Defendant-Appellant

Appeal from the United States District Court

for the Southern District of California

Rudi M. Brewster, District Judge, Presiding

Argued and Submitted

August 10, 2000—Pasadena, California

Filed December 19, 2000

Before: KOZINSKI, GRABER, and FISHER, Circuit

Judges.

GRABER, Circuit Judge:

Defendant Southwest Marine, Inc., appeals from the

district court’s judgment for Plaintiffs Natural Resources

Defense Council (NRDC), San Diego Baykeeper, and

2a

Kenneth J. Moser, in their citizen enforcement action under

§ 505(a) of the Clean Water Act (CWA), 33 U.S.C. § 1365(a).

In response to Defendant’s challenge, we hold: Plaintiffs

have standing to bring this action, Plaintiffs’ notice letter

was adequate, Defendant’s. violations were ongoing, the

district court’s injunctive measures were not an abuse of

discretion, and the district court’s civil penalty was not an

abuse of discretion. Accordingly, we affirm.

FACTS AND PROCEDURAL BACKGROUND

Defendant operates a large shipyard on San Diego Bay.

Its principal business is repairing and maintaining marine

vessels. Among other things, Defendant’s shipyard removes

old paint from ships and then repaints them. Defendant

commonly removes old paint by blasting the ships’ hulls

with abrasive grit, composed primarily of particles of

copper, that is conveyed on streams of compressed air.

Defendant uses about 4 million pounds of copper grit per

year for blasting old paint from ships and generates about

4,800 pounds of paint waste per year.

Defendant repaints ships with “antifouling paints,”

which are paints that are formulated to prevent the growth

of aquatic organisms, such as barnacles and algae, on the

bottoms of ships. Those paints contain compounds that are

toxic to aquatic life.

Defendant’s shipyard contains five piers, at which ships

are moored while they are being repaired, and two floating

drydocks, on which ships rest, out of the water, to allow

repair, blasting, and repainting of parts that are normally

underwater. When Plaintiffs filed their complaint,

Defendant also was operating a marine railway, which is a

device that is used to pull ships onto the shore for repair.

Shipyards like Defendant’s generate large amounts of

wastes and pollutants, including paint chips and abrasive

grit. Those wastes and pollutants are discharged into

adjacent waters through - among other means -- storm

3a

water runoff, tidal action, leaks, spills, and overspray. A

1993 report by the California Regional Water Quality

Control Board showed elevated concentrations of copper,

tributyltin, and zinc — all of which are present in the

materials used and the wastes generated at Defendant's

shipyard -- in the sediments adjacent to the shipyard. The

report concluded that Defendant appeared to have

discharged copper, tributyltin, and zinc into San Diego Bay,

that Defendant’s management practices appeared to be

inadequate to prevent such discharges, and that the

discharges might have long-term negative effects on the

water quality of the Bay and on its suitability for human

use.

Defendant had applied for and received a National

Pollutant Discharge Elimination System (NPDES) permit

from the California Regional Water Quality Control Board

in 1983. In 1992, Defendant had obtained coverage under

the State Water Resources Control Board’s 1991 General

Industrial Permit for storm water discharges. That permit

supplemented Defendant’s NPDES permit; the storm water

permit- applied to discharges of pollutants through storm

water, and the NPDES permit applied to other discharges.

Both permits required Defendant to develop and

implement plans to limit its discharges of pollutants into the

Bay. Rather than relying on specific numerical effluent

limitations, the permits required Defendant to create and

follow “Best Management Practices” (BMPs).! Defendant

adopted a written BMP plan on January 15, 1992.

1 BMPs are

schedules of activities, prohibitions of practices, maintenance

procedures, and other management practices to prevent or

reduce the pollution of “waters of the United States.” BMPs

also include treatment requirements, operating procedures,

and practices to control plant site runoff, spillage or leaks,

sludge or waste disposal, or drainage from raw material

storage.

4a

The storm water permit also required Defendant to

develop and implement a Storm Water Pollution Prevention

Plan (SWPPP) and a Storm Water Pollution Monitoring

Plan (SWPMP). The permit specified that the SWPPP was

required to include, among other things:

e a description of sources that might add significant

quantities of pollutants to storm water discharges;

e adetailed site map;

e a description of materials that had been treated,

stored, spilled, disposed of, or leaked into storm

water discharges since November 1988;

e a description of the management practices that

Defendant employed to minimize contact between

storm water and pollutants from vehicles,

equipment, and materials;

e a description of existing structural and

nonstructural measures to reduce pollutants in

storm water discharges;

e a description of methods of on-site storage and

disposal of significant materials;

40 C.F.R. § 122.2. As described in Defendant’s current NPDES permit,

BMPs may be “structural” (e.g., tarpaulins and shrouds to enclose work

areas, retention ponds, devices such as berms to channel water away

from pollutant sources, and treatment facilities) or “non-structural” (e.g.,

good housekeeping, preventive maintenance, personnel training,

inspections, and record-keeping).

5a

a description of outdoor storage, manufacturing, and

processing activities;

a list of pollutants likely to be present in significant

quantities in storm water discharges and an

estimate of the annual amounts of those pollutants

in storm water discharge;

a record of significant leaks or spills of toxic or

hazardous pollutants to storm water;

a summary of existing data describing pollutants in

storm water discharge;

a description of Defendant’s storm water

management controls, including good housekeeping

procedures, preventive maintenance, and measures

to control and treat polluted storm water; and

a list of the specific individuals responsible for

developing and implementing the SWPPP.

Defendant submitted its SWPPP in December 1992.

The SWPPP required Defendant, among other things, (1) to

perform daily inspections to ensure that its shipyard was

complying with the requirements of its BMP plan, and (2) to

maintain records of those inspections.

On April 30, 1996, Plaintiffs sent Defendant a notice

letter, as required by 33 U.S.C. § 1365(b)(1)(A), advising

Defendant that it was violating the CWA and that Plaintiffs

intended to sue under the CWA’s citizen enforcement

provisions. A copy of the notice letter and its attachments

appears as an Appendix at the end of this opinion.

6a

As discussed below, a party who wishes to sue under the

CWA’s citizen enforcement provisions may not commence an

action until at least 60 days after giving notice of intent to

sue. On August 27, 1996, more than 60 days after sending

their notice letter, Plaintiffs filed this action. Four days

earlier, on August 23, 1996, Defendant had submitted a

revised SWPPP and SWPMP. Those revised plans

_ addressed, and attempted to correct, many of the

shortcomings described in Plaintiffs’ notice letter.

In September 1996, Defendant moved to dismiss this

action, arguing that Plaintiffs’ notice letter did not comply

with the CWA’s requirements and, in particular, that the

letter was not specific enough to inform Defendant of what

standards it allegedly had violated. The district court

denied Defendant’s motion in a published opinion. Natural

Res. Def. Council, Inc. v. Southwest Marine, Inc., 945 F.

Supp. 1330 (S.D. Cal. 1996).

Defendant then moved for summary judgment, arguing

(1) that the district court lacked subject matter jurisdiction

because Plaintiffs’ allegations of ongoing violations were

neither made in good faith nor based on reasonable

investigation; (2) that, even if the district court had subject

matter jurisdiction, summary judgment was appropriate

because Plaintiffs could not prove ongoing violations at trial;

and (3) that Plaintiffs’ claims were moot.

After continuing the motion to allow more time for

discovery, the district court denied summary judgment in an

unpublished order. In denying Defendant’s motion, the

court concluded (1) that it had subject matter jurisdiction

because Plaintiffs had alleged continuing violations in good

faith; (2) that there were disputed issues of material fact as

to whether Defendant (a) had developed an adequate

SWPPP and monitoring plan, as required by its storm water

permit, and (b) had adequately implemented or was

adequately implementing such plans; and (3) that Plaintiffs’

action was not moot.

Ta

While district court proceedings were pending,

Defendant’s permits were revised twice. First, Defendant’s

storm water permit was superseded by a new storm water

permit, which took effect May 1, 1997. Second, both the

storm water permit and Defendant’s NPDES permit were

superseded by a new NPDES permit. That permit was

issued on October 15, 1997, but was stayed on March 27,

1998, by the Superior Court of the County of San Diego.

The superior court lifted that stay later in 1998, and the

revised permit became effective at that time.”

Defendant also revised a number of its practices related

to storm water while this matter was before the district

court. Among other things, Defendant revised its BMP

plan, as required by its most recent NPDES permit;

installed a storm water diversion system covering most (but

not all) of its facility; hired a new environmental compliance

manager; installed a roof to prevent storm water from

reaching hazardous materials; and removed polluted

sediments from the area of its marine railways.

This action was tried to the court between November 2

and December 3, 1998. Both sides presented evidence and

expert testimony about conditions at Defendant’s facility,

and the district court made three visits to the facility.

On March 2, 1999, the district court found in Plaintiffs’

favor in an unpublished order. After reaffirming its earlier

rulings that Plaintiffs had standing and that the notice letter

was adequate, the court concluded (1) that Defendant’s

SWPPP and monitoring plan, as revised in August 1996,

were adequate; but (2) that Defendant had failed to

implement those plans adequately, thereby violating its

< Defendant has operated under three storm water permits during the

pendency of this litigation. The provisions of those permits that

Defendant was found to have violated, and to which we refer in this

opinion, have remained essentially consistent in all three permits.

va hatin Soa iia ial

eee ee ee th i

8a

permit and the CWA. The court imposed injunctive relief

and a civil penalty of $799,000.

The district court then asked Plaintiffs to prepare

proposed findings of fact and conclusions of law. Plaintiffs

submitted proposed findings on May 7, 1999, and

Defendants filed objections thereto. The district court held

hearings on July 13 and August 19, 1999, to consider

Defendant’s objections. Defendant argued, among other

things, that the district court’s proposed injunction was too

broad and too costly. To address those arguments, the

district court asked the parties to submit additional

evidence concerning the proposed injunction.

On September 7, 1999, the district court issued its

findings of fact and conclusions of law. The court found: (1)

that Plaintiffs had presented “convincing evidence” that

Defendant had not made the required inspections that it

claimed to have made; (2) that, even accepting Defendant’s

statement that it had made the required inspections,

Defendant had not maintained adequate records of those

inspections, with the result that a large number of

inspection reports were missing; (3) that the reports that

Defendant had provided demonstrated a pattern of poor

housekeeping at Defendant’s facility and showed that

violations, when reported, were not always remedied in a

timely manner; (4) that Defendant’s inadequate

implementation of its plans had led to “significant

contributions of pollutants to Defendant’s leasehold”; (5)

that Defendant’s leasehold within the Bay was “devoid of

life”; (6) that the evidence conclusively demonstrated that

substantial quantities of pollutants from Defendant’s

paint-blasting operations had entered San Diego Bay in

Defendant’s storm water discharges; (7) that Defendant’s

failure to implement its storm water plans adequately was

contributing to and perpetuating the contamination of its

marine leasehold; and (8) that the harm to Defendant’s

leasehold “could be remedied by Defendant with improved

:

Fe

‘A -

-

aS

$

i

+

9a

practices.” Based on those findings, the court concluded: (1)

that it had subject matter jurisdiction over the action; (2)

that Plaintiffs had standing; (3) that Defendant had violated,

and was continuing to violate, the relevant permits and

plans; and (4) that Defendant’s failure to implement its plans

adequately was the result of “systemic problems” and

“overall inadequacies” in implementation, rather than mere

“snapshots” of isolated violations.

The district court’s findings of fact and conclusions of law

also reiterated the injunctive relief and civil penalties that

the court had imposed in its earlier order. In response to

Defendant’s objections, the court entered a limited stay

governing several provisions of the injunction, to allow the

parties to submit further studies and evidence. On March 6,

2000, the district court heid its final hearing regarding the

limited stay. After making minor changes to the injunction,

the court lifted the stay in an unpublished order dated

March 7, 2000.

In its injunction, the court ordered Defendant (1) to test

its storm water discharges for significant pollutants before

releasing them into the Bay; (2) to sweep, after every shift,

uncontained areas in which operations may have caused

deposits of debris and to provide mats and air hoses so that

workers could clean their shoes after leaving such areas; (3)

to make daily inspections of its facilities (except when the

shipyard is not operating) and keep records of those

inspections; (4) to test the water column around each vessel

that is being blasted or painted to determine if those

operations are contributing to pollution in the Bay; (5) to

correct conditions that might allow pollutants to enter the

Bay, within four hours if feasible; (6) to repair or replace

shrouds that are in poor repair; (7) to capture all storm

water coming off its piers (the district court allowed

Defendant 18 months to comply with this condition); and (8)

to erect and maintain concrete berms in areas of the facility

from which runoff might enter the Bay. The court rejected

10a

Plaintiffs’ argument that Defendant should be required to

remediate the contamination of the sediments ‘n its marine

leasehold.

This timely appeal followed.

DISCUSSION

Defendant challenges the district court’s rulings on (1)

standing, (2) the adequacy of Plaintiffs’ notice letter, (3)

ongoing violations, (4) the terms of the injunction, and (5)

the civil penalty. We will address each of those issues in

turn.

I. Standing

_ First, Defendant argues that the district court erred in

holding that Plaintiffs had standing to bring this action. We

review de novo the question whether a party has standing

to bring an action. LSO, Ltd. v. Stroh, 205 F.3d 1146, 1152

(9th Cir. 2000).

In order to satisfy Article III’s standing requirements in

a CWA citizen enforcement action, “a plaintiff must show (1)

it has suffered an ‘injury in fact’ that is (a) concrete and

particularized and (b) actual or imminent, not conjectural or

hypothetical; (2) the injury is fairly traceable to the

challenged action of the defendant; and (3) it is likely... that

the injury will be redressed by a favorable decision.”

Friends of the Earth, Inc. v. Laidlaw Envtl. Servs., Inc., 120

S. Ct. 693, 704 (2000). An association like NRDC “has

standing to bring suit on behalf of its members when its

members would otherwise have standing to sue in their own

right, the interests at stake are germane to the

organization’s purpose, and neither the claim asserted nor

the relief requested requires the participation of individual

members in the lawsuit.” Id.

Defendant argues that Plaintiffs cannot satisfy any of

the three requirements for Article III standing. We

disagree.

bs

s

.*

2

&

=

@

s

=

oe

lla

First, Plaintiffs showed “injury in fact.” The Supreme

Court has held that “environmental plaintiffs adequately

allege injury in fact when they aver that they use the

affected area and are persons ‘for whom the aesthetic and

recreational values of the area will be lessened’ by the

challenged activity.” Id. at 705 (quoting Sierra Club v.

Morton, 405 U.S. 727, 735 (1972)). Here, members of the

plaintiff organizations, and individual plaintiff Kenneth

Moser, testified that they have derived recreational and

aesthetic benefit from their use of the Bay (including areas

of the Bay next to Defendant’s shipyard), but that their use

has been curtailed because of their concerns about pollution,

contaminated fish, and the like. Those averments are

sufficient to satisfy the “injury in fact” component of Article

III standing.

Second, the injury is “fairly traceable” to the challenged

activity. This requirement,-more precisely, is that there

must be “a causal connection between the injury and the

conduct complained of -- the injury has to be ‘fairly ...

trace[able] to the challenged action of the defendant, and not

... th{e] result [of] the independent action of some third

party not before the court.’” Lujan v. Defenders of Wildlife,

504 U.S. 555, 560 (1992) (quoting Simon v. Eastern Ky.

Welfare Rights Org., 426 U.S. 26, 41-42 (1976)). Plaintiffs

presented evidence that the sediments in Defendant’s

marine leasehold contained elevated concentrations of

pollutants, that Defendant had discharged the same

pollutants, and that Defendant’s marine leasehold was

“devoid of life.” That evidence was sufficient- to

demonstrate that Plaintiffs’ injury was “fairly traceable” to

Defendant’s conduct. As the Fourth Circuit has noted, the

threshold requirement of “traceability does not mean that

plaintiffs must show to a scientific certainty that defendant’s

effluent ... caused the precise harm suffered by the

plaintiffs” in order to establish standing. Friends of the

Earth, Inc. v. Gaston Copper Recycling Corp., 204 F.3d 149,

12a

161 (4th Cir. 2000) (en banc) (citations and internal quotation

marks omitted). To satisfy this requirement, “(rjather than

pinpointing the origins of particular molecules, a plaintiff

must merely show that a defendant discharges a pollutant

that causes or contributes to the kinds of injuries alleged in

the specific geographic area of concern.” Id. (citation and

internal quotation marks omitted); see also Sierra Club v.

Cedar Point Oil Co., 73 F.3d 546, 558 (5th Cir. 1996) (to the

same effect); Public Interest Research Group of New Jersey,

Inc. v. Powell Duffryn Terminals Inc., 913 F.2d 64, 72 (3d

Cir. 1990) (same). Plaintiffs made that showing in this case.

Third, Plaintiffs demonstrated that a favorable decision

would redress their injuries. A plaintiff who seeks

injunctive relief satisfies the requirement of redressability

by alleging a continuing violation or the imminence of a

future violation of an applicable statute or standard. See

Steel Co. v. Citizens for a Better Env’t, 523 U.S. 83, 108

(1998). Plaintiffs alleged that Defendant was continuing to

violate its permits; what is more, as discussed below, they

proved continuing violations at trial. Because they sought

an injunction to halt those continuing violations, Plaintiffs

satisfied the requirement of redressability.

In sum, the district court did not err in holding that

Plaintiffs had standing to bring this action.

II. Netice--Subject Matter Jurisdiction

Next, Defendant argues that Plaintiffs’ notice letter was

insufficient. Under the CWA,

No action may be commenced-

(1) under subsection (a)(1) of this section --

(A) prior to sixty days after the plaintiff has given

notice of the alleged violation (i) to the

Administrator, (ii) to the State in which the alleged

vioiation occurs, and (iii) to any alleged violator of

the standard, limitation, or order...

i

s

2

*

va

k¢

=

13a

33 U.S.C. § 1365(b). The applicable regulation provides that

the notice

shall include sufficient information to permit the

recipient to identify the specific standard, limitation,

or order alleged to have been violated, the activity

alleged to constitute a violation, the person or

persons responsible for the alleged violation, the

location of the alleged violation, the date or dates of

such violation, and the full name, address, and

telephone number of the person giving notice.

40 C.F.R. § 135.3(a).

If a party seeking to bring a citizen enforcement action

has not complied with the CWA’s notice requirement, then

the district court in which that action is brought lacks

subject matter jurisdiction and must dismiss the action.

Washington Trout v. McCain Foods, Inc., 45 F.3d 1351, 1354

(9th Cir. 1995); see also Hallstrom v. Tillamook County, 493

U.S. 20, 26 (1989) (requiring strict compliance with notice

requirement for citizen enforcement action under the

Resource Conservation and Recovery Act). “In practical

terms, the notice must be sufficiently specific to inform the

alleged violator about what it is doing wrong, so that it will

know what corrective actions will avert a lawsuit.” Atlantic

States Legal Found., Inc. v. Stroh Die Casting Co., 116 F.3d

814, 819 (7th Cir. 1907). We review de novo the district

court’s conclusion that Plaintiffs’ notice was adequate. See

Washington Trout, 45 F.3d at 1353.

The district court treated Plaintiffs’ notice letter as

alleging two separate, but related, violations concerning the

pollution prevention plans required by its permits and the

CWA. The first was Defendant’s failure to prepare

adequate plans; the second was Defendant’s failure to

implement adequate plans.

With regard to those issues, Plaintiffs’ notice letter

clearly satisfies some of the requirements of notice. The

14a

letter was mailed to the appropriate entities. See 40 C.F.R.

§ 135.3(a). It identified the persons giving notice and the

persons responsible for the alleged violation. Although the

letter did not identify a specific date, or a specific location

within Southwest Marine’s facility, it nevertheless satisfied

those requirements as well. See id. Plaintiffs were not

alleging that a particular discharge from a particular pipe on

a particular day had violated the CWA. Rather, they were

alleging that Defendant had failed to prepare and

implement plans that were required by its permit. As the

district court correctly noted, the failure to develop and

implement pollution prevention plans are violations

“occurring at the facility in general.” Southwest Marine, 945

F.. Supp. at 1333. Moreover, “the deficiencies in these plans

are ongoing, so there is no specific date that can be alleged

‘as the date of the violation.” Id.

The parties’ dispute before us centers on the specificity

of the notice letter. See 40 C.F.R. 135.3(a) (requiring that a

notice letter “include sufficient information to permit the

recipient to identify the specific standard, limitation, or

order alleged to have been violated, [and] the activity

alleged to constitute a violation”). The notice letter

generally raises the issues of the preparation and

implementation of an adequate SWPPP. Our first question

is whether the notice letter raised those issues adequately

to satisfy the requirements of the CWA.

As to the alleged failure to prepare an adequate plan, the

notice. letter was clearly adequate, and we do not

understand Defendant to argue otherwise. The letter

charged, among other things, that Defendant had failed to

prepare an SWPPP that complied with the specific

requirements of Defendant’s storm water permit; identified

the source of the requirement that Defendant prepare an

adequate SWPPP; and explained the ways in which

Defendant’s then-existing SWPPP did not comply with the

storm water permit.

152

Defendant argues, however, that the notice letter was

not sufficient with regard to Plaintiffs’ allegation that it

failed to implement an adequate plan. Specifically,

Defendant asserts that the district court lacked jurisdiction

to consider Plaintiffs’ allegations of “poor housekeeping.”

The notice letter alleges that Defendant failed to implement

an adequate SWPPP, including a “good housekeeping”

provision. “Good housekeeping’ was required under

Defendant’s storm water permits. Defendant acknowledges

that the court’s reference to “poor housekeeping” does

“arguably correspond” to Plaintiffs’ reference to storm

water controls and good housekeeping in Attachment 2 of

the notice letter. See Appendix A at Attachment 2, page 1.

Nevertheless, Defendant argues that Plaintiffs failed to

refer to, or identify, the “good housekeeping” provision of its

revised SWPPP and, thus, failed to provide any information

about how Defendant had violated that specific plan

provision. The difficulty with that argument is that the

notice letter predates the plan provisions to which

Defendant refers. Plaintiffs mailed their notice letter in

April 1996. The “good housekeeping” provision to which

Defendant refers, and which Defendant cites in its brief, is

contained in Defendant’s revised SWPPP, which was filed in

August 1996. Although we require strict compliance with

the CWA’s notice requirement, we do not require

citizen-plaintiffs to refer to provisions of plans that do not

exist.

We hold that the notice letter was sufficient, on the date

it was mailed, to allow the district court to exercise

jurisdiction over Plaintiffs’ “good housekeeping” claims.

Defendant was operating under a storm water permit that

was designed to prevent discharges of toxic pollutants

through storm water. That permit required Defendant to

prepare and implement an SWPPP that included a “good

housekeeping” provision. The permit expiained that “[gjood

housekeeping requires the maintenance of clean, orderly

16a

facility areas that discharge storm water. Material handling

areas shall be inspected and cleaned to reduce the potential

for pollutants to enter the storm water conveyance system.”

Plaintiffs’ notice letter sufficiently alleged that Defendant

had failed to prepare and implement such a plan.

And Defendant obviously understood at least some of

the alleged violations. In response to Plaintiffs’ letter,

Defendant completely revised its SWPPP and SWPMP

within four months, adding sections that specifically made

reference to the requirements that Plaintiffs had identified.

See Atlantic States, 116 F.3d at 820 (concluding that notice

was sufficiently specific where the defendant, after

receiving notice, took immediate steps to cure the problems

identified in the notice letter). And, as noted, Defendant

made substantial changes to its facility and operations

during the pendency of this litigation, concededly in an

attempt to remedy some of the inadequacies of which

Plaintiffs had complained.

The second and more theoretical question that

Defendant’s argument raises is what, if any, effect

Defendant’s post-notice alterations of its plans and facilities

had on the adequacy of the notice letter. If a defendant

receives a proper notice letter alleging that it has failed to

prepare and implement an adequate plan and, in response,

prepares a new plan and begins to implement it before the

complaint is filed, is the otherwise proper notice letter

defective for failing to identify and discuss the new plan and

its implementation? In those circumstances, must a

citizen-plaintiff send a new notice letter? We think not.

Subject matter jurisdiction is established by providing a

notice that is adequate on the date it is given to the

defendant. The defendant’s later changes to its operations

and plans may affect standing, see Steel Co., 523 US. at

105-06; the question of ongoing violations or remedies, see

Gwaltney of Smithfield, Ltd. v. Chesapeake Bay Found.,

Inc., 484 U.S. 49, 64 (1987); or mootness, see Laidlaw, 120 S.

17a

Ct. at 708.3 But such changes do not retroactively divest a

district court of jurisdiction under 33 U.S. C. § 1365 (b).

Defendant also cites Washington Trout and Hallstrom in

support of its argument that notice was inadequate. Those

cases are distinguishable from this one. In Washington

Trout and Hallstrom, the plaintiffs had failed to comply with

the facial requirements for notice set out in the applicable

statutes and regulations.

In Washington Trout, the plaintiffs mailed the defendant

a letter alleging improper discharges of p«{lutants; however,

“the letter did not provide the address and phone number of

the named plaintiff, nor did it furnish the identity, address,

and phone number of [the other plaintiffs].” 45 F.3d at 1352.

Further, “the notice failed to specifically identify the dates”

of the allegedly unlawful discharges. Jd. This court held

that those failures to comply with 40 C.F.R. § 135.3(a)

precluded the district court from assuming jurisdiction over

any part of the plaintiffs’ action. Jd. at 1354-55.

In Hallstrom, the plaintiffs filed a citizen enforcement

action under the Resource Conservation and Recovery Act,

which contains a notice provision that is substantively

identical to the CWA’s notice provision. See 42 U.S.C.

§ 6972(b). The Supreme Court held that the district court

lacked subject matter jurisdiction over the plaintiffs’ action

because the plaintiffs had failed to give any notice to the

EPA or to the appropriate state agency as § 6972(b)

requires. See Hallstrom, 493 U.S. at 33.

Those cases establish that the CWA’s notice

requirement is strictly construed and that compliance with

3 Using Defendant’s corrective actions as evidence of its

understanding of Plaintiffs’ letter might seem to suggest a strategy of

avoiding remedial measures so as not to create unfavorable evidence.

Such corrective actions, however, would benefit a defendant on issues of

standing, mootness, and remedy, as illustrated by the cases cited in the

text.

18a

the notice requirement is a prerequisite to a citizen

enforcement action. But this case presents a different

problem. Unlike in Washington Trout and Hallstrom, the

question in this case is not whether the district court had

subject matter jurisdiction over any part of Plaintiffs’

action; Defendant does not contest that the notice was

adequate as to the allegation that it had failed to prepare an

adequate SWPPP. Rather, the question is whether the

district court exercised jurisdiction over particular issues

that were not raised in the notice letter and, thus, were

beyond the scope of the court’s jurisdiction.

We have resolved that question in Plaintiffs’ favor. As

discussed above, we hold that Plaintiffs, letter gave

Defendant adequate notice of all the claims over which the

district court exercised jurisdiction. Accordingly, the

district court did not err in concluding that Plaintiffs’ notice

letter satisfied the requirements of 33 U.S.C. § 1365(b).

III. Evidence of Ongoing Violations

Next, Defendant argues that the district court erred in

concluding that it had committed “ongoing violations” of

requirements in its storm water permit. We review findings

of fact for clear error and conclusions of law de novo.

Russian River Watershed Prot. Comm. v. City of Santa

Rosa, 142 F.3d 1136, 1140 (9th Cir. 1998). We review de

novo a district court’s interpretation of an NPDES permit

when its terms are unambiguous. Jd. at 1141.

The CWA “does not permit citizen suits for wholly past

violations”; rather, the statute “confers jurisdiction over

citizen suits when the citizen-plaintiffs make a good-faith

allegation of continuous or intermittent violation.”

Gwaltney, 484 U.S. at 64. Here, the district court properly

concluded that Plaintiffs had made such good-faith

allegations and thereby had satisfied Gwaltney’s threshold

requirement for jurisdiction.

19a

To prevail at trial, a citizen-plaintiff must prove that

ongoing violations actually have occurred. “[A] citizen

plaintiff may prove ongoing violations ‘either (1) by proving

violations that continue on or after the date the complaint is

filed, or (2) by adducing evidence from which a reasonable

trier of fact could find a continuing likelihood of a recurrence

in intermittent or sporadic violations.’ ” Sierra Club v.

Union Oil Co., 853 F.2d 667, 671 (9th Cir. 1988) (quoting

Chesapeake Bay Found., Inc. v. Gwaltney of Smithfield,

Ltd., 844 F.2d 170, 171-72 (4th Cir. 1988)). This court also

has adopted the Fourth, Circuit’s conclusion that

“fijntermittent or sporadic violations do not cease to be

ongoing until the date when there is no real likelihood of

repetition.’ [Chesapeake Bay Found., 844 F.2d] at 172

(emphasis added).” Id.

Defendant groups three arguments under this heading.

First, Defendant argues that the district court erred in

holding that it had violated any condition of its storm water

permit. We disagree. As noted, the district court found

that Defendant had failed to make -- or had failed to keep

records of -- numerous daily inspections of its facility. Those

daily inspections — and records of the inspections — were

required by Defendant’s 1992 and 1996 SWPPPs. The

SWPPPs, in turn, were required by Defendant’s storm

water permit, which contemplated that Defendant would

inspect its facility and keep records of its inspections. The

district court also found that the inspection reports that

Defendant did produce revealed “a pattern of poor

housekeeping.” Defendant’s own inspection reports showed

that the “good housekeeping” standard was not met

uniformly and that violations were not always remedied

quickly.

Moreover, the district court found that Defendant’s

failure adequately to implement its SWPPP “led to

significant contributions of pollutants” to the Bay from

Defendant’s discharges. The court further found that those

20a

discharges contributed to the contamination of Defendant’s

marine leasehold and that the leasehold is “devoid of life.”

Those findings are supported by evidence and, accordingly,

are not clearly erroneous. Each of Defendant’s successive

storm water permits has specifically prohibited discharges

that cause adverse effects on the environment. For

example, Defendant’s current storm water permit prohibits

discharges that degrade marine communities, cause adverse

effects on the environment, or result in harmful

concentrations of pollutants in marine sediments. Because

the district court found that Defendant’s failure to

implement its storm water plans led to discharges that

violated those standards, the court’s conclusion that

Defendant violated its storm water permit was not error.

Second, Defendant argues, “[eJlven assuming arguendo

that Southwest Marine did not, at some point in time,

implement its stormwater plans adequately, it was legal

error for the district court to find an ongoing violation of

that permit requirement.” (Emphasis in original.) As a

threshold matter, we reject Defendant’s argument that we

review this question for legal error. The district court’s

conclusion that Defendant’s violations were ongoing was a

finding of fact, which we must affirm unless clearly

erroneous. See Union Oil, 853 F.2d at 671 (stating that a

plaintiff could prove a continuing violation “by adducing

evidence from which a reasonable trier of fact could find a

continuing likelihood of a recurrence in intermittent or

sporadic violations”).

Here, the district court found that Defendant had failed

to implement its plans adequately even after Plaintiffs filed

their complaint. As the district court noted, there is

evidence of incidents of poor housekeeping during the

pendency of this action. Defendant argues that the district

court’s finding of an ongoing violation “improperly combines

several discrete and unrelated workplace incidents.” But

the district court found that the ongoing violations

2la

“present[ed] a picture of overall inadequacies,” not mere

“snapshots.” Notwithstanding Defendant’s argument, we

may not disturb that finding if it is supported by evidence.

And it is; the evidence on which the district court relied was

sufficient to permit a reasonable trier of fact to find “a

continuing likelihood of a recurrence in intermittent or

sporadic violations.” Union Oi, 853 F.2d at 671.

Accordingly, the district court’s finding of a continuing

violation was not clearly erroneous.

Third, Defendant argues that, even if there is sufficient

evidence in the record to establish an ongoing violation of

the permit, we should nevertheless remand for the distric*

court to explain further the factual and legal basis for its

decision. Because we conclude that the district court has

provided sufficient factual and legal support for its decision,

we do not agree that remand is necessary or appropriate.

IV. The Injunction

Next, Defendant argues that the injunction was

improper. District courts have “broad latitude in fashioning

equitable relief when necessary to remedy an established

wrong.” Alaska Ctr. for the Env’t v. Browner, 20 F.3d 981,

986 (9th Cir.1994). We review a district court’s decision to

issue an injunction under the CWA, and its determination of

the scope of that injunction, for abuse of discretion. See

Natural Res. Def. Council, Inc. v. Texaco Ref. & Mktg., Inc.,

906 F.2d 934, 937 (8d Cir. 1990) (so holding); see also

Weinberger v. Romero-Barcelo, 456 U.S. 305, 320 (1982)

(describing decision to award or deny injunction as an

exercise of a district court’s equitable discretion).

Defendant contends that the district court abused its

discretion by imposing requirements that are not contained

in Defendant’s permits or plans. By so doing, Defendant

argues, the district court essentially overrode the existing

permits. According to Defendant, that was improper for

two reasons: (1) it was an abuse of discretion, and (2) it

22a

violated principles of separation of powers by usurping the

authority of the executive-branch agencies that issued the

permits. Because those arguments both turn on the

underlying question whether the district court overrode

Defendant’s existing permits, we address the arguments

together.

Defendant is correct that a district court’s equitable

powers under the CWA are limited to enforcing standards,

limitations, and orders that have been violated. 33 U.S.C. §

1365(a). That enforcement authority does not allow

equitable measures that are wholly unrelated to a violation

of an existing standard, limitation, or order. Nor may a

district court exercise its general equitable authority to

override the terms of a properly issued permit. See City of

Milwaukee v. States of Illinois & Michigan, 451 U.S. 304,

320 (1981) (“Federal courts lack authority to impose more

stringent effluent limitations under federal common law

than those imposed by the agency charged by Congress

with administering this comprehensive scheme.”).

But here the district court permissibly found violations

of extant permits. The key question is what a district court

may do, pursuant to its equitable powers, in aid of enforcing

standards, limitations, and orders that have been violated.

According to Defendant, a court may do little more than

tell the violator to comply with the applicable requirements.

Thus, Defendant says, the district court in this case should

have “simply order[ed] Southwest Marine to comply with

specifically-identified pollution plan provisions.”

We do not agree that a district court’s equitable

authority is so cramped. The authority to “enforce” an

existing requirement is more than the authority to declare

that the requirement exists and repeat that it must be

followed. So long as the district court’s equitable measures

are reasonably calculated to “remedy an established wrong,”

23a

they are not an abuse of discretion. Alaska Ctr., 20 F.3d at

986

We conclude that the injunctive measures satisfy that

standard. Those measures all are consistent with, and

complementary to, existing permit requirements. The

requirement that Defendant’s employees sweep open areas

where debris may have accumulated (or certify that there

was no debris to sweep) and wipe their feet on mats after

leaving such areas is a good housekeeping measure designed

to remove pollutants from areas where storm water

accumulates, as contemplated in Defendant’s permits; the

requirement that Defendant fix and maintain its shrouds is

consistent with the permit requirement for structural

BMPs, such as shrouds, that provide overhead coverage; the

requirement that Defendant install concrete berms is

consistent with the requirement for structural BMPs, such

as berms, that channel or route storm water away from

sources of pollutants; the requirement that Defendant

conduct water-column testing around each vessel that is

being blasted or painted is consistent with the permit

requirements for storm-water monitoring; the requirement

that Defendant make daily inspections and keep records of

those inspections is consistent with numerous permit

requirements requiring monitoring and recordkeeping (and,

further, is almost identical to a provision in Defendant’s

original BMP plan); the requirement that Defendant correct

potentially dangerous conditions within four hours, if

feasible, is consistent with permit requirements for prompt

response in cases of leaks and spills; and the requirements

that Defendant capture storm water coming off piers and

test storm water discharges before releasing them into the

Bay are consistent with the requirement that Defendant not

discharge storm water that adversely affects the

environment or degrades marine communities on

Defendant’s leasehold, which the district court found had

24a

been rendered devoid of life by (among other things)

Defendant’s discharges.

The injunctive measures are consistent with the terms of

Defendant’s storm water permits and seek to enforce the

requirements of those permits and the relevant plans. They

are not identical to the requirements of the plans and

permits, but complement those requirements. In imposing

those injunctive measures, the district court did not

override agency determinations or supersede existing

permit requirements. Rather, it properly exercised its

equitable authority to enforce existing requirements with

which Defendant had failed to comply.

Our conclusion that those provisions of the injunction

were consistent with Defendant’s storm water permit also

disposes of Defendant’s separation-of-powers argument.

Because the district court merely enforced the permits, it

did not “usurp” the authority of the executive branch.

Defendant also argues that the district court failed to

balance the equities or make the necessary findings before

issuing its injunction. We are unpersuaded. The district

court considered Defendant’s testimony concerning the cost

and difficulty of the various injunctive measures. The

district court also heard testimony throughout the trial

about the extreme degree of environmental degradation in

the Bay in general, and on Defendant’s leasehold in

particular. The court temporarily stayed the injunction to

allow further argument and evidence, and eventually

modified the original injunction with respect to testing,

containment of runoff, and cleanup. Finally, in its order

lifting the temporary stay, the court noted that it was

mindful of the cost that it was imposing on Defendant, but

concluded that the cost was outweighed by the need for

swift corrective action and the fragility of the local marine

environment. The district court’s findings and balancing of

the equities were adequate to justify its injunction.

25a

In sum, we conclude that the district court’s injunction

was not an abuse of discretion. We also conclude that the

injunction did not violate the separation-of-powers doctrine.

Therefore, we affirm the injunction in its entirety.

V. Civil Penalties

Finally, Defendant argues that the district court abused

its discretion in imposing a civil penalty of $799,000, because

the penalty is excessive, unreasonable, and unsupported by

evidence. We review for abuse of discretion the amount of a

civil penalty under the CWA. Leslie Salt Co. v. United

States, 55 F.3d 1388, 1397 (9th Cir. 1995).

The district court imposed the penalty pursuant to 33

U.S.C. § 1319(d), which provides, as relevant: “Any person

who violates ... any permit condition or limitation ... shall be

subject to a civil penalty not to exceed $25,000 per day for

each violation.” Ifa district court finds a violation, then civil

penalties under 33 U.S.C. § 1319(d) are mandatory. Leslie

Salt, 55 F.3d at 1397. A district court has discretion to set

the amount of a penalty (up to the statutory maximum) and

is instructed to consider the seriousness of the violation, any

economic benefit that resulted from the violation, any

history of violations by the party to be penalized, that

party’s good-faith efforts to comply with the applicable

requirements, the economic effect of the penalty on the

violator, and “such other matters as justice may require.” 33

US.C. § 1319(d).

The district court found that Defendant had been in

violation of the CWA for 799 days when the trial began and,

after considering the statutory factors, imposed a penalty of

$1,000 for each of the 799 days of violation. However, the

court also ordered that the penalty will be reduced by the

amount of the cost of any actions that Defendant takes to

improve its storm water diversion system and any changes

that Defendant makes to its facilities to comply with the

court’s injunction.

26a

Thus, the amount of the penalty actually is $799,000

minus the cost of such physical alterations. In challenging

the injunction, Defendant presented evidence that one such

alteration ~— the installation of a storm-water diversion

system -— would cost more than $1 million by dself.

Accordingly, anticipated alterations, when offset against the

$799,000 civil penalty, will reduce the penalty to zero. In

the circumstances, we cannot agree that the penalty is

excessive, and we hold that the district court did not abuse

its discretion.

CONCLUSION

For the reasons stated, we AFFIRM the district court’s

judgment in favor of Plaintiffs, the injunction, and the civil

penalty.

April 30, 1996

Certified Mail - Return Receipt R ted

Art Engle

President Southwest Marine, Inc.

P.O. Box 13308

San Diego, California

92170-3308

Lawrence Killeen

Executive Director

San Diego Unified Port District

P.O. Box 488

San Diego, California

92112

Re: Notice of Intent to Sue for Violations of the Clean

Water Act

Dear Messrs. Engle and Killeen:

We write to notify you that the San Diego

BayKeeper and the Natural Resources Defense Council

(““NRDC’”) believe that Southwest Marine, Inc. and the San

Diego Unified Port District (“Port District”) are violating

the Federal Water Pollution Control Act, 33 U.S.C. §§

1251-1376 (“Clean Water Act” or “Act’”’), as described below.

The information currently available to us indicates

that Southwest Marine and the Port District have violated

and continue to violate requirements concerning discharges

from the Southwest Marine facility at the foot of Sampson

Street in the City of San Diego. These requirements,

including requirements related to discharges associated

29a

with or ancillary to industrial manufacturing and treatment,

are embodied in the Act, its implementing regulations, and

National Pollutant Discharge implementing regulations, and

National Pollutant Discharge Elimination System

(“NPDES”) Permit No. CA0107697. This permit was issued

pursuant to the Act by the California Regional Water

Quality Control Board, San Diego Region (“Regional

Board”) on or around April 18, 1983. The requirements with

which we believe Southwest Marine and the Port District

have failed to comply are set forth in Attachment 1 to this

letter. See also 33 U.S.C. §§ 1311(a), 1314(e), & 1365, 40

C.F.R. Subpart K.

Additionally, the information currently available to

us indicates that Southwest Marine and the Port District

have violated and continue to violate NPDES General

Permit No. CAS000001 governing stormwater discharges

associated with industrial activities in California (“General

Industrial Permit”). The General Industrial Permit”). The

- General Industrial Permit was issued pursuant to the Act

by the California State Water Resources Control Board

(“State Board”) on or around November 19, 1991, and

amended by the State Board on or around September 17,

1992. Coverage under and compliance with the General

Industrial Permit are required before Southwest Marine can

lawfully discharge stormwater associated with industrial

activity. The General Industrial Permit requirements with

which we believe Southwest Marine and the Port District

have failed to comply are set forth in Attachment 2 to this

letter. See also 33 U.S.C. §§ 1311(a), 1342(p), & 1365, 40

C.F.R. § 122.26.

The San Diego BayKeeper and NRDC hereby notify

you of their intent to sue Southwest Marine and the Port

District for their failure to comply with requirements

embodied in the Clean Water Act, the Act’s implementing

regulations, NPDES Permit No. CA0107697, and the

30a

General Industrial Permit. With this letter, the

undersigned give notice of the alleged violations to the

following parties: Art Engle as owner and/or managing

agent of Southwest Marine; Lloyd A. Schwartz as registered

agent in California of Southwest Marine; Lawrence Killeen

as the head of the Port District; the Administrator of the

United States Environmental Protection Agency (“EPA”);

the Regional Administrator of EPA; the Executive Officer

of the State Board; and the Acting Executive Officer of the

Regional Board.

We believe that this notice of intent to sue

sufficiently states the grounds for complaint. This notice

covers all violations through the present. A suit, when filed,

will also address any violations that occur after service of

this notice letter. The San Diego BayKeeper and NRDC

intend to sue on behalf of their organizations and their

respective members.

The San Diego BayKeeper and NRDC pursue

negotiation whenever possible. This negotiation policy

applies to all types of environmental disputes, including

enforcement of stormwater pollution prevention

requirements. In keeping with this policy, we invite you to

discuss your Clean Water Act compliance with us.

If you have any question about the issues raised in

this letter or if you believe any of our allegations are

incorrect, please contact us by telephone, telecopy or mail.

We can be reached at the offices of the San Diego

BayKeeper, listed on the first page of this letter. NRDC’s

office location is as follows: 6310 San Vicente Blvd., Suite

250, Los Angeles, California 90048, (213) 934-6900 (voice),

(213) 934-1210 (facsimile). If you wish to contact us before

we file a complaint, we request that you do so as quickly as

possible. We intend to file suit 60 days after the date of this

letter. See 33 U.S.C. § 1365(b)(1)(a).

3la

Sincerely,

/s/ Everett L. DeLano, III /s/ Ken Moser ennaneseee

Everett L. DeLano, III Ken Moser

Senior Project Attorney Executive Director

San Diego BayKeeper/ San Diego BayKeeper

Natural Resources Defense

Council

Enclosures

ce: Carol Browner

Administrator

U.S. Environmental Protection Agency

401 M Street, S.W.

\ Washington, D.C. 20460

Felicia Marcus

Regional Administrator, Region 9

U.S. Environmental Protection Agency

75 Hawthorne Street

San Francisco, CA 94105

Walt Pettit

Executive Director

State Water Resources Control Board

901 P Street

Sacramento, CA 95814

John Robertus

Acting Executive Officer

California Regional Water Quality Control Board

San Diego Region

9771 Clairemont Mesa Blvd., Suite B

San Diego, CA 92124-1331

32a

Lloyd A. Schwartz

Registered Agent

Southwest Marine

P.O. Box 13308

San Diego, California

92170-3308

33a

Attachment 1

The information currently available to the San Diego

BayKeeper and NRDC indicates that Southwest Marine and

the Port District have violated the Act, its implementing

regulations, and NPDES Permit No. CA0107697. These

violations include, but are not limited to, the following:

1) NPDES Permit No. CA0107697 Parts B.3 (p. 7)

& D.7 (p. 10) and 40 C.F.R. § 125.104(b), requiring

the development and implementation of best

management practices programs, including, but not

limited to:

e establishing specific objectives for control of toxic

and hazardous pollutants by predicting direction,

rate of flow and total quantity of pollutants; and,

e addressing the following points for ancillary

activities: material inventory; material

compatibility; reporting and notification

procedures; visual inspections; preventive

maintenance; and, security.

2) NPDES Permit No. CA0107697 Part C.5 (p. 8),

prohibiting concentrations of toxic substances in

waters that produce detrimental physiological

responses in human, plant, animal, or aquatic life.

3) NPDES Permit No. CA0107697 Part E.10 (p. 14)

and 40 C.F.R. § 125.104(c)(1), requiring the submittal

of a complete permit application.

, 34a

Attachment 2

The information currently available to the San Diego

BayKeeper and NRDC indicates that Southwest Marine and

the Port District have violated the General Industrial

Permit. These violations include, but are not limited to, the

following:

1) Parts B.1 & B22 (p. 3)!, prohibiting stormwater

discharges that adversely impact human health or

the environment, and prohibiting stormwater

discharges that cause or contribute to a violation of

any applicable water quality standards, respectively.

2) Part C.2 (p. 3) and Section A (pp. 5-7), requiring

the development and implementation of a

Stormwater Pollution Prevention Plan, including,

but not limited to:

e listing pollutants likely to be present in

stormwater in significant quantities and

estimating the annual quantities of these

pollutants, Section A.4.d; and,

e describing the stormwater management controls

appropriate for the facility (for example,

stormwater pollution prevention personnel,

preventive maintenance, good housekeeping,

spill prevention and response, stormwater

management practices, erosion and sediment

controls, employee training, and inspections),

Section A.5.

1 Part, Section, and Page references are to the General Industrial

Permit.

35a

3) Part C.3 (p. 3) and Section B (pp. 9-16), requiring

the development and implementation of a monitoring

and reporting plan, including, but not limited to:

e conducting an annual site inspection, Section

B.5.a;

e conducting visual observations of all stormwater

discharge locations during the first hour of one

storm event per month that produces significant

stormwater discharge, Section B.5.c;

e collecting and analyzing samples of stormwater

discharge from at least two storm events, Section

B.5.d;

e analyzing samples of stormwater discharge for

toxic chemicals and other pollutants that are

likely to be present in stormwater discharge in

significant quantities, Section B.5.d.ii;

collecting samples from all locations where

stormwater is discharged or, in the alternative,

adequately establishing and documenting that

stormwater discharges from different locations are

substantially identical, Section B.11;

notifying the Regional Board, and, if applicable,

appropriate local agency, of instances of non-

compliance with General Industrial Permit

requirements, Section B.17.

36a

UNITED STATES DISTRICT COURT

SOUTHERN DISTRICT OF CALIFORNIA

No. 96-CV-1492-B AJB

Natural Resources Defense Council,

San Diego BayKeeper, Kenneth J. Moser,

Plaintiffs,

Southwest Marine, Inc.,

Defendant.

ORDER: (1) LIFTING LIMITED STAY OF

ENFORCEMENT OF JUDGEMENT; (2) DENYING ANY

FURTHER STAY PENDING APPEAL; AND (3)

SETTING HEARING ON PLAINTIFF’S MOTION FOR

ATTORNEY’S FEES

FILED: March 7, 2000

I. Order Lifting Limited Stay Of Enforcement Of

Judgment

This Court entered judgment on the above-mentioned

case on September 7, 1999 pursuant to Findings of Fact and

Conclusions of Law. Upon motion of Defendant, this Court

also entered a Limited Stay of Enforcement of Judgment on

September 7, 1999, by the terms of which this Court stayed

for a period of 90 days the execution of certain portions of its

judgment in order to permit the parties to submit

37a

alternative or the most feasible methods to accomplish the

corrective action.

Good cause appearing, after review of the parties’ papers

with respect to Defendant’s Motion for Further Stay of

Enforcement of Judgment, after hearing oral argument, and

after being fully advised, this Court now lifts the previously

imposed Limited Stay of Enforcement of Judgment.

With respect to Paragraph 42 of the Findings of Fact

and Conclusions of Law, if Southwest Marine shall discharge

runoff into the bay because of an inability of its present

landslide containment system to handle the runoff,

Defendant shall sample the initial discharge from each point

of discharge and shall perform chemical analysis and toxicity

testing immediately thereafter and shall record these

results for future reference. Defendant only need test the

initial discharge, if any, from each rain event. A rain event

is considered to be rain that is immediately preceded by six

hours of dry weather.

With respect to Paragraph 43 of the Findings of Fact

and Conclusions of Law (“Sweepdowns”), the Court clarifies

the requirement that Defendant shall furnish a sufficient

number of mats in addition to its air hose brushing and clean

up so that workers exiting the ship area shall wipe their

shoes to remove contaminants.

With respect to Paragraph 45 of the Findings of Fact

and Conclusions of Law (“Water Column Testing”), the

“surface layer” shall be defined to be “microlayer.” “Surface

layer testing” shall consist of the testing of the “microlayer”

and shall be within the top fifty micrometers. The

remainder of the water column testing requirement shall

remain unchanged.

With respect to Paragraph 48 of the Findings of Fact

and Conclusions of Law concerning the capture of storm

water coming off of any and all piers, Defendant shall have

18 months from the date of the filing of this order to comply

38a

with this judgment. Defendant shall build its Pier

Stormwater Diversion Facility with respect to a five-year

storm criteria.

II. Order Denying Any Further Stay Of Enforcement

Of Judgment Pending Appeal

Any further stay of enforcement of judgment pending

the appeal of this Court’s judgment is DENIED.

In making this determination, the Court is mindful of the

cost imposed on Defendant with respect to its September 7,

1999 Judgment. The Court is also mindful of the

countervailing need for swift corrective environmental

action, the fragility of the bay’s marine eco-system, and the

almost certain inevitability of necessary corrective action on

the part of Southwest Marine.

III. Order Setting Hearing On Plaintiffs’ Motion For

Attorney’s Fees

With respect to Plaintiffs’ Motion for Attorney’s Fees,

Plaintiffs’ reply brief is due on May 2, 2000 and Defendant’s

supplemental reply is due on May 9, 2000. Defendant’s

supplemental reply shall be no longer than 10 pages.

Thereafter the Motion for Attorneys Fees will be

considered submitted, with hearing to be held on May 23,

2000 at 9 a.m. in Courtroom 2.

Parties are encouraged to stipulate to a reasonable fee

award for Plaintiffs’ fees in order to obviate the need for

hearing. If parties are unable to stipulate to a reasonable

fee award thereby necessitating this Court to determine a

reasonable fee award, this Court will award attorney’s fees

for the hearing to that party which comes the closest to the

fees awarded by the Court. That amount will be either

added to or subtracted from the attorney’s fees awarded at

the hearing.

IT ISSO ORDERED.

39a

Dated [3-7-00] /s/ Rudi M. Brewster

UNITED STATES SENIOR

DISTRICT JUDGE

ce: All Parties

Magistrate Judge

40a

UNITED STATES DISTRICT COURT

SOUTHERN DISTRICT OF CALIFORNIA

No. 96-1492-B AJB

Natural Resources Defense Council,

San Diego BayKeeper, Kenneth J. Moser,

Plaintiffs,

v.

Southwest Marine. Inc.,

Defendant.

LIMITED STAY OF ENFORCEMENT OF JUDGMENT

FILED: September 7, 2000

The Court has on this day entered Judgment in this

case, pursuant to Findings of Fact and Conclusions of Law.

Enforcement of the Judgment shall be and is hereby stayed

as to the following provisions of the Findings of Fact and

Conclusions of Law only:

Paragraph 48. Enforcement of only the following

portion of paragraph 48 is stayed pending completion of the

process set forth below:

Defendant shall have sixty days to prepare engineering

alternatives, with supporting cost data, to implement the

Court’s requirement that SWM “shall capture all

stormwater coming off any and all piers.” Defendant shall

present these alternatives, along with the underlying data,

4la

to Plaintiffs after the sixty-day period. Plaintiffs shall have

thirty days to respond as desired to the alternatives.

Defendant shall have ten days to reply. This enforcement

proposal shall then be considered submitted for further

action by the Court. The Court shall select the option it

considers to meet its requirement in the most reasonable

manner.

SWMWM’s failure to prepare and submit an alternative

program to the Court within the stated period shall be

deemed a decision not to do so, and Paragraph 48 shall

thereafter remain in full force and effect as written.

Paragraph 43. Enforcement of only the following

portion of Paragraph 43 is stayed pending completion of the

process set forth below:

Because the Court’s requirement to “conduct sweep

downs after every shift of areas in which operations may

have caused deposit of debris” may be unreasonable, the

Court notes that it has modified its sweepdown

requirement. As modified, the requirement applies only to

non-contained areas of the shipyard. However, the Court

orders Defendant to evaluate whether workers upon exiting

a contained area with accumulations of blast material are

“tracking” this blast material into non-contained areas

which, in turn, may be entering San Diego Bay. Defendant

shall evaluate the feasibility of a “sanitation station,” i.e., a

location where workers could remove debris from their

boots and/or clothes which otherwise might be deposited in

non-contained areas. Defendant’s proposal for this process

shall be filed and served within thirty days. Plaintiffs will

have ten days in which to respond to this material, after

which Defendant will have ten days to reply. The Court

shall select its remedy promptly thereafter.

SWMW’s failure to submit this finding and/or study to the

Court within the stated period shall be deemed a decision

not to do so.

42a

Paragraph 45. Enforcement of only the following

portion of paragraph 45 is stayed pending completion of the

process set forth below:

Defendant shall evaluate the benefits and cost

effectiveness of substituting “microlayer” testing such as

that set forth in the Kocan Declaration submitted with

Plaintiffs’ Status Report, i.e., providing that “surface

samples” be sea-surface micro layer samples, the top 50

micrometers (um) of water, in place of or as part of the

Court’s requirement that SWM perform water column

testing as described in paragraph 45 of the Findings of Fact

and Conclusions of Law. Defendant shall have thirty days

in which to conduct this evaluation, after which its findings

shall be presented to Plaintiffs. Plaintiffs will have thirty

days in which to review this material. Plaintiffs’ comments

shall be presented te Defendant, who will have ten days to

reply. After this time period, this material will be presented

to the Court as stated above.

SWM’s failure to prepare and submit an alternative

program to the Court within the stated period shall be

deemed a decision not to do so, and Paragraph 45 shall

thereafter remain in full force and effect as written.

Paragraph 42. Enforcement of only the following

portion of paragraph 42 is stayed pending completion of the

process set forth below:

..- no release shall be allowed until the results of

such testing have been received. No discharge shall

be allowed, unless testing results demonstrate that

the effluent complies with NPDES permit limits.

Southwest Marine shall operate or modify its storm

water retention system so as to allow conformance

with this requirement throughout its physical

facility.

The Court acknowledges that Defendant’s existing

stormwater containment system exceeds current regulatory

43a

requirements. The Court understands that the proposed

test-before-release requirement may require significant

capital increases to expand the retention system because of

the time delay associated with toxicity testing. This

expenditure may be unnecessary in light of the current

knowledge of the toxicity and pollution content of

Defendant’s stormwater over and above the first half-inch of

rainfall. The Court also recognizes there are limitations

both inherent in (mechanically-fed inflow and gravity

outflow) and outside (San Diego City sewer capacity

restrictions) of Defendant’s physical plant which may

require Defendant to retain captured stormwater for a

period of time during which a rain event may exceed the

holding capacity.

Therefore, in the interim, Defendant shall take the

following steps:

a. Early Release

Defendant shall release water from its diversion system

to the city sewer system as early as and to the greatest

extent possible during a rain event.

b. Release of Excess

Captured rainwater, only to the extent that it exceeds

the current capacity of the diversion system and the ability

to early release water to the city sewer system, may be

released to the Bay even though test results have not been

received and despite test results which demonstrate

pollutants exceeding NPDES permit standards.

c. Testing

First quarter-inch: Should SWM reasonably anticipate a

release of stormwater to the Bay because of a rain event

that may exceed the diversion system’s capacity, SWM

shall test the captured rainwater at approximately the first

+o

quarter-inch level. Defendant shall take split samples,

providing one sample to Plaintiffs.

Released water: For every release to the Bay, SWM

shall take split samples of the water upon initial release and

perform toxicity and contaminant testing. Furthermore,

this outflow to the Bay shall also be tested at each new

quarter-inch of water exiting the diversion system into San

Diego Bay. The results of such testing shall be recorded and

maintained and provided to the Court and Plaintiffs in

summary form at six-month intervals, assuming that a

release was allowed in any particular six-month period.

Should these test results demonstrate that water above the

capacity of the existing retention system is harmful to the

Bay, the Court will consider ordering capital improvements

at that time.

Correlated Tables: Defendant shall investigate the

feasibility of correlating toxicity results to the presence of

individual and/or multiple contaminants in water. The

results of this investigation shall be filed and served within

thirty days. Plaintiffs shall have ten days in which to

respond. Defendants shall then have ten days to reply. The

Court may thereafter enter such further orders for remedial

action as shall appear just and necessary.

The Court has set a status hearing on January 27, 2000

at 2:00 p.m., at which time the Court expects to lift this Stay

of Enforcement and issue such modifications as may be just

and necessary to the ordered injunctive relief. All other

provisions of the Findings of Fact and Conclusions of Law

and Judgment shall remain in full force and effect as

written.

IT IS SO ORDERED.

DATED: [9-1-99] /s/ Rudi M. Brewster _

UNITED STATES SENIOR

DISTRICT JUDGE

45a

UNITED STA‘'ES DISTRICT COURT

SOUTHERN DISTRICT OF CALIFORNIA

Case No. 96-1492-B AJB

Natural Resources Defense Council,

San Diego BayKeeper, Kenneth J. Moser,

Plaintiffs,

v.

Southwest Marine, Inc.,

Defendant.

JUDGMENT FOR MONETARY DAMAGES AND

INJUNCTIVE RELIEF

FILED: September 7, 1999

This case having come to trial on November 3, 1998,

before the Honorable Rudi M. Brewster, United States

Senior District Judge, presiding without a jury; and,

The court having issued its Decision in Plaintiffs favor

on March 3, 1999; and

The court having issued Findings of Fact and

Conclusions of Law on_[9-]]_, 1999,

NOW, THEREFORE, it is hereby ORDERED that,

for good cause shown, Judgment is hereby entered in favor

of plaintiffs Natural Resources Defense Council, San Diego

BayKeeper and Kenneth J. Moser and against defendant

46a

Southwest Marine, Inc., as provided for in the Findings of

Fact and Conclusions of Law.

IT IS FURTHER ORDERED that this Court shall

retain jurisdiction over this matter for the next three (3)

years ending March 3, 2002, and that Plaintiffs may petition

this Court, upon a showing of good cause, to extend this

Court’s jurisdiction fo an additional reasonable time

sufficient to ensure that Defendant is complying with the

requirements of the Clean Water Act and the terms of this

Judgment as set forth in the Findings of Fact and

Conclusions of Law.

IT IS FURTHER ORDERED that plaintiffs, as the

prevailing party, shall recover their attorneys’ fees, experts’

fees, related non-taxable expenses and taxable costs from

defendant in an amount to be determined by the Court.

Plaintiffs shall serve and file their motion for attorneys’ fees

and costs no later than thirty (80) days following the entry

of judgment.

IT IS SO ORDERED.

Dated: [9-1-99] /s/ Rudi M. Brewster

United States Senior District Judge

47a

UNITED STATES DISTRICT COURT

SOUTHERN DISTRICT OF CALIFORNIA

Case No. 96CV1492-B AJB

Natural Resources Defense Council,

San Diego BayKeeper, Kenneth J. Moser,

Plaintiffs,

v.

Southwest Marine, Inc.,

Defendant.

FINDINGS OF FACT AND CONCLUSIONS OF LAW

FILED: September 7, 1999

I. INTRODUCTION

This matter came on regularly for trial on November 3,

1998, before the Honorable Rudi M. Brewster, United

States Senior District Judge, presiding without a jury.

Charles Stevens Crandall, Everett L. DeLano III and Scott

H. Peters appeared as counsel for plaintiffs. Steven

McDonald, E. Patrick Swan and Lloyd Schwartz appeared

as counsel for defendant. Pursuant to F.R.Civ.P. 16 and

Civil Local Rule 16.1(f)(10)(b), the Court makes the

following findings and fact and conclusions of law:

1. This is an action for injunctive relief, civil Penalties,

and declaratory relief by Plaintiffs Natural Resources

Defense Council (“NRDC”), San Diego BayKeeper

48a

(“BayKeeper”), and Kenneth J. Moser against Southwest

Marine, Inc. (“SWM” or “Defendant”) for violations of the

Federal Clean Water Act (“CWA”), the implementing

regulations, and permits issued to SWM by the State of

California pursuant to the CWA.

II. STANDING

2. Plaintiff Kenneth J. Moser recreates on San

Diego Bay (“the Bay”). Up to and including the time of

trial, he lived near the Bay and worked on its waterftont as

the Executive Director of San Diego BayKeeper. Mr. Moser

resigned as Executive Director of BayKeeper effective

January 1, 1999, but he still resides in San Diego, he is still

employed by BayKeeper, and remains a member of that

organization and Plaintiff NRDC. Plaintiff Moser regularly

uses San Diego Bay in a variety of ways. He has aesthetic,

health, recreational, scientific and economic interests in San

Diego Bay, including the areas within and immediately

adjacent to SWM’s leasehold.

3. Other members of NRDC and BayKeeper live on

or near the Bay. At least one of BayKeeper’s members can

see the SWM facility from his home. Some of these

members volunteer time toward efforts to protect the Bay

from pollution and some of them participate in public

associations and task forces dedicated to planning future

uses of the Bay. Members of NRDC and BayKeeper

regularly use the Bay in at least the following ways:

boating, sailing, kayaking, wading, sightseeing, fishing,

scuba diving, shell fish gathering, swimming, and walking.

These members have aesthetic, health, recreational,

scientific and economic interests in San Diego Bay, including

the areas within and immediately adjacent to SWM’s

leasehold.

4. Each of the Plaintiffs Moser, NRDC and

BayKeeper has suffered, and will continue to suffer, actual

49a

and threatened harms to their interests as a result of SWM’s

ongoing conduct.

5. The injuries proven by the Plaintiffs are

redressible by the orders made by the Court.

III. JURISDICTION AND VENUE

6. The Court has personal jurisdiction over the

parties pursuant to 28 U.S.C. § 1331.

7. The Court has subject matter jurisdiction to 33

U.S.C. § 1365(a), which states that district courts have

jurisdiction to enforce alleged violations of effluent

standards, limitations, or orders.

8. Venue is proper in this Court pursuant to 33

U.S.C. § 1365(c) since the source in question is located in the

City and County of San Diego.

9. By a letter dated April 30, 1996 (the “Notice

Letter”), Trial Exhibit 12, Plaintiffs gave notice to SWM

that it was in violation of its NPDES Permit, the General

Industrial Permit, the CWA and their implementing

regulations.

10.The Notice Letter adequately apprised

Defendant that Plaintiffs were going to sue defendant

because SWM had not properly developed and adequately

implemented a Storm Water Pollution Prevention System

(“SWPPP”), a Best Management Practices (“BMP”), or

Stormwater Pollution Prevention and Monitoring Program

(“SWPPMP”). Natural Resources Defense Council V.

Southwest Marine, 945 F.Supp. 1330, 1333 (S.D. Cal. 1996).

IV. ADMITTED FACTS

11. The following facts were agreed to by the parties

and required no proof:

12. Defendant operates a shipyard at the foot of

Sampson Street in the City of San Diego. Its principal

business is the repair of marine vessels, mostly for the

United States Navy.

50a

13. Defendant engages in numerous industrial

activities and the facility includes marine railways, dry

docks, piers and wharfs, a painting area, a reclamation yard,

a sandblast area and assembly and work areas. Industrial

activities at the facility include, but are not limited to,

abrasive blasting, hydro blasting, paint application, tank

cleaning, mechanical repair and maintenance, structural

repair and assembly, strength. testing, equipment cleaning,

engine repair and installation, hydraulic repair and

installation, tank emptying, fueling, pattern making, boiler

cleaning, carpentry, refurbishing and modemization, air

conditioning and refrigeration repair, sheet metal

fabrication, and fiberglass repair.

14. From time to time the following materials have

been used at Defendant’s facility: abrasive blast grit,

anticorrosive paints, antifouling paints, oils, lubricants,

greases, fuels, weld, detergents, cleaners, rust inhibitors,

paint thinners, and solvents, hydrocarbons or chlorinated

solvents, degreasers, acids, caustics, resins, adhesives,

cements, sealants, zinc, and chlorine. .

15. SWM’s first National Pollutant Discharge

Elimination (“NPDES”) permit was issued by the Regional

Water Quality Control Board, San Diego Region

(““RWQCB’) on April 18,1983, RWQCB Order No. 83-11 (the

“1983 NPDES Permit”). The Regional Water Quality

Control Board and the State Water Resources Control

Board enforce that permit.

16.On November 19, 1991, the State Water

Resources Control Board (“SWRCB’) issued a general

permit applicable to storm water discharges from industrial

facilities in California, SWRCB Order No. 91-13-DWQ (as

amended by Order No. 92-12-DWQ)(the “1991 General

Industrial Permit”). On or before October 1, 1992, SWM

filed a Notice of Intent with the SWRCB to be permitted

under the 1991 General Industrial Permit.

5la

17. The 1991 General Industrial Permit requires

facilities, including SWM, to implement a Storm Water

Pollution Prevention Plan (“SWPPP”), to reduce or

eliminate industrial storm water pollution.

18. On August 23,1996, SWM amended its SWPPP.

19. On August 27, 1996, Plaintiffs filed the Complaint

herein.

20. On March 31, 1997, the SWRCB issued a new

general permit applicable to the discharge of storm water

from industrial facilities in California, SWRCB Order No.

97-03-DWQ, (the “1997 General Industrial Permit”) and this

new permit replaced the 1991 General Industrial Permit.

21. On October 15,1997, the RWQCB issued a new

NPDES permit (the “1997 NPDES Permit”) that replaced

both the 1983 NPDES Permit and the 1997 General

Industrial Permit.

22. On March 27, 1998, the Superior Court for the

County of San Diego stayed the effectiveness of the 1997

NPDES Permit but that stay was lifted as of the completion

of trial.

23. SWM’s 1983 NPDES Permit requires the

development and implementation of a Best Management

Practices Program (“BMP Program”).

24. The Clean Water Act and the General Industrial

Permit req aire certain technologies to reduce and eliminate

storm water pollution from Defendant’s facility and require,

among other things, the development of a SWPPP, and a

monitoring and reporting program, and other specific

requirements set forth therein.

25. Defendant adopted a BMP Plan January 15, 1992.

This written plan was not changed until the adoption of a

BMP Program Manual on January 12, 1998.

V. ADDITIONAL FINDINGS OF FACT

The Court makes the following additional findings of

fact:

52a

A. Adequacy of the Stormwater Plans Vis-A-Vis

Permit Requirements

26. Despite early deficiencies, Defendant has

developed stormwater prevention plans and _ best

management practices (“BMPs”) which are adequate under

the law, irrespective of which standard of review -- Best

Available Technology (“BAT”), Best-Conventional Pollutant

Control Technology (“BCT”) or reduction of runoff to the

Maximum Extent Practicable (“MEP”) is applied to the

question of adequacy. While plaintiffs presented examples

of plan inadequacies, Defendant demonstrated that

allegations of inadequacies had either been corrected or

were covered within existing categories of the permits. This

court’s visits to the shipyard have revealed demonstrable

improvement.

27. Defendant is not the stereotypical environmental

“bad actor.” The court is convinced that Defendant has

made a good faith effort in its attempt to implement

environmental protections. That effort may have been less

aggressive without the pendency of this lawsuit. However,

whatever the effect of this lawsuit, the plans as written are

deemed adequate.

B. Plan Implementation

28. Based on evidence presented at trial, SWM’s

implementation and enforcement of its SWPPPs, BMPs and

SWPPMP are inadequate. That inadequacy existed prior to

the time of the filing of this action and continues to this day.

As such, plaintiffs have demonstrated to the Court “a

continuing likelihood of recurrence in intermittent or

sporadic violation” of those issues in its notice letter. See

Sierra Club v. Union Oil Co., 853 F.2d 667, 671 (9th Cir.

1988).

29. Plaintiffs have presented convincing evidence

that Defendant did not make the inspections Defendant

claimed to have made. Even if the Court accepted

53a

Defendant’s evidence, the failure to maintain those records

demonstrates inadequate practices and a lack of sufficient

execution of their above-mentioned programs. Defendant

provided no satisfactory explanation for why approximately

53% of these inspection reports are missing.

30. For those inspection reports presented to the

court, a pattern of inadequate housekeeping is evident.

Violations, even when reported, were not always timely

remedied. While a_ substantial portion of these

implementation violations may not have a direct effect on

environment, these violations likely had some impact.

Defendant maintained that the problems cited to the Court

are mere “snapshots,” and should not be taken for

systematic problems. While such an argument has surface

attraction, it is ultimately unconvincing. Tirst, except for

this court’s most recent visit to SWM, Defendant had

adequate opportunity to remedy deficiencies prior to the

inspecting party’s arrival. Second, evidence to some extent

is always of the “snapshot” variety. As stated, taken

cumulatively, the evidentiary glimpses of Defendant’s

operations present a picture of overall inadequacies.

C. Causal Harms

31. Plaintiffs demonstrated that the implementation

inadequacies have led to significant contributions of

pollutants to Defendant’s leasehold and, as such, San Diego

Bay. While this case presents complications because of the

substantial amount of historically-caused contaminated

sediments in Defendant’s leasehold, this court finds that

Defendant’s failed to implement adequately its required

plans is contributing to and perpetuating the contamination

of the offshore leasehold.

32. Trial experts agreed that the offshore leasehold

was “devoid of life.” The question presented at trial was

whether the stormwater coming from Defendant’s landside

facility had and has causal connection to the environmental

54a

condition of that offshore habitat. While no one accident of

faulty implementation can be said to have caused a level of

pollution so as to harm marine life, taken cumulatively, the

Court finds that the evidence presented demonstrates that

Defendant’s operations have contributed to the

contamination of San Diego Bay.

33. The evidence conclusively demonstrated that

contaminants are entering the marine habitat. The testing

performed by Defendant revealed that substantial

quantities of pollutants - metals and toxics -- have entered

the Bay in Defendant’s stormwater discharges and because

of blasting operations. Second, the Court is convinced by

the evidence presented that, but for new infusions of

contaminants by stormwater or faulty operations, the

pattern of contaminated sediments would have revealed a

decreasing trend in levels of contamination. The Campbell

Shipyard Study (Trial Exhibit 127) undercut the testimony

of Defendant’s exvert Barrick. The long-existing presence

of paint chips and abrasive grit in the sedimentation in the

leasehold may help explain the lack of a decreasing trend,

but it is not a conclusive answer. Third, che Court is

convinced that the causal harms to the Bay are harms that

could be remedied by Defendant with improved practices.

VI. CONCLUSIONS OF LAW

34. Plaintiffs have demonstrated that: (1) they have

been and are being subjected to an actual and threatened

harm; (2) the harm is fairl’ traceable to Defendant’s

complained-of conduct; and, (3) there is a likelihood that the

requested relief will assist in redressing the alleged injuries.

35. Each plaintiff is suffering an injury-in-fact caused

by the specific violations alleged in the Notice Letter and

Complaint, which is redressible in this action. Therefore,

each plaintiff has standing to maintain this action.

55a

36. Existing and continuing violations of the Clean

Water Act, the implementing regulations, and SWM’s

permits have occurred at SWM since August 26, 1996.

37. Civil penalties should be imposed against

Defendant.

38. Injunctive relief should be provided to Plaintiffs.

39. Subject matter jurisdiction is proper.

40. SWM has been and is violating the Clean Water

Act, its regulations and SWM’s~-permits in numerous

respects by failing adequately to implement and enforce

water pollution prevention controls.

VII. RELIEF

A. Equitable Relief

41. The Clean Water Act vests courts with broad

authority to fashion appropriate equitable remedies. See 33

U.S.C. § 1365(a). Based on that broad authority, this court

shall retain jurisdiction over this matter for three years

from March 3, 1999. Plaintiffs may petition the court to

extend this court’s jurisdiction. Upon good cause showing,

the Court may extend its jurisdiction for a reasonable time

sufficient to ensure that Defendant is complying with the

requirements of the Act.

B. Specific Directi

42. Testing. To the maximum extent possible,

Southwest Marine shall allow no discharge of stormwater

effluent from any pipe discharging into the Bay until testing

has been performed for every significant known and

potential pollutant that may result from shipyard operations

and may be contained in the effluent. Such testing shall be

performed prior to any anticipated release and no release

shall be allowed until the results of such testing have been

received. No discharge shall be allowed unless testing

results demonstrate that the effluent complies with NPDES

permit limits. Southwest Marine shall operate or modify its

stormwater retention system so as to allow conformance

56a

with this requirement throughout its physical facility.

Southwest Marine shall maintain records of such testing,

and make copies available for review by this Court and

Plaintiffs at Defendant’s expense.

43. Sacepden ant cemtiaiiee, Southwest

Marine shall conduct sweep-downs after every shift of

non-contained areas in which operations may have caused

deposit of debris. After each sweep-down, certification will

be made that no debris remains in the area. Alternatively,

Southwest Marine shall certify that no debris was created

and thus no sweep-down was necessary. All certifications

shall clearly identify the certifying employee and shall be

made subject to penalty of perjury. Cleanup of contained

areas shall be addressed by the Court after further briefing

by the parties as set forth in the Court’s Stay filed herewith.

44. Inspections and Recordkeeping. Southwest

Marine shall make daily inspections of its physical plant.

Records shall be maintained for each inspection. Conditions

causing or having the potential of cause pollutants to enter

the Bay shall be noted in detail. No such inspections shall

be required for periods in which the shipyard is not

conducting operations. Inspection reports shall note such

time periods. All daily inspections shall be certified as

correct, and each report shall clearly identify the certifying

employee and shail be made subject to penalty of perjury.

45. Water Column Testing. On one occasion for each

vessel — whether in drydock or at pier side - on which

blasting or painting operations are conducted, Defendant

shall perform testing of the surrounding water to determine

if such operations are contributing to pollution levels in San

Diego Bay. Such testing shall be performed on a day in

which blasting or painting operations constitute a majority

of the operations conducted during the shift. Should no such

day exist, testing shall be done on the day of greatest

' blasting or painting activity. Defendant shall divide such

testing equally between painting and blasting operations.

57a

Within two hours of such blasting or painting activity,

Defendant shall perform water column pollution tests in at

least four locations surrounding the vessel. Such locations

shall be located within 50 to 100 feet distance from the

vessel, and at least 200 feet apart from each other. For each

location, water shall be sampled at the surface, and at each

20-foot interval between the water surface and the bottom

of the Bay. The results of such tests shall be certified in a

manner consistent with the provisions of this Decision, and

shall be finished on a quarterly basis to the Magistrate

Judge, with one copy provided to Plaintiffs.

46. Correction Action. Conditions with potential to

allow pollutants to enter the Bay shall be corrected within

four hours after observation. Southwest Marine shall certify

that such corrective action has been made. Shouid it not be

feasible to take corrective action within four hours,

Defendant shall take corrective action in an expeditious

manner. Defendant shall state in writing the reason why it

was not feasible. Feasibility should be narrowly construed

and should, with reason, apply only to mechanical or

structural problems. All certifications shall note the manner

of corrective action and the time period in which such action

was taken. All certifications shall clearly identify the

certifying employee and shall be made subject to penalty of

perjury.

B. Physical Plant Improvement

47. Shrouds. Southwest Marine shall repair and/or

replace shrouds which are in poor repair, defined as in a

state that may allow more than de minimis quantities of

debris from blasting, painting, or other similar operations

from entering the Bay. Such repair and/or replacement

shall take place within a reasonably expeditious peniod of

time. Defendant subsequently shall maintain and/or replace

shrouds which do not meet this criterion.

58a

48. Piers. Southwest Marine shall capture all

stormwater runoff coming off any and all piers. No scuttling

of runoff from piers will be allowed. Defendant shall take

steps to meet this requirement in a reasonably expeditious

manner.

49. Berms. Southwest Marine shall erect and

maintain concrete berms in all areas of its physical plant

from which runoff may enter the Bay. In areas that

experience significant pooling of water, and which threaten

to cause discharge into the Bay, Defendant shall pump out

such areas on an expeditious basis so as not to allow such

discharges. Should areas, including piers, be constructed or

re-constructed, Defendant instead may rely on sloping and

drainage so long as such a drainage system will

accommodate flows from even heavy periods of rainfall.

Should this alternative be taken, berms need not be

constructed. Should this alternative be taken, Defendant

shall certify to the court that such a system is as adequate as

any berm system.

50. Contaminated Sediments Cleanup. Without

deciding the question of its jurisdiction to order cleanup of

Defendant’s contaminated sediments to specific standards,

the Court declines to accept Plaintiffs’ invitation to issue

such an order at this time. As noted, the majority of the

pollution existing in the off-shore leasehold is present

because of historical practices at the shipyard before

Defendant obtained ownership. Defendant has begun the

process of remediation on the marine railways. Defendant

will soon begin the process of remediating the rest of the

leasehold. The cleanup standard to which the rest of the

leasehold must comply will be determined after hearings

before the State Water Resources Control Board. The court

chooses not to interfere in that process, and sees insufficient

reason why Plaintiffs should be accorded financial assistance

at this time to be involved in that process.

C. Penalties

59a

51. Penalty Amount The Clean Water Act

mandates civil penalties for the violations found in this

lawsuit. See 33 U.S.C. § 1319(d). Such penalties may not

exceed $25,000 per day. Id. Orders issued by this Court on

November 30, 1999 and January 28, 1999 have concluded

that civil penalties are available to the Plaintiffs. While civil

penalties are mandatory if the Court finds violations, the

amount assessed is wholly within the discretion of the court.

See Atlantic States Legal Foundation v. Tyson Foods, Inc.,

897 F.2d 1128, 1142 (11th Cir. 1990); Stoddard v. Western

Carolina Regional Sewer Authority, 784 F.2d 1200, 1208 (4th

Cir. 1986). “In determining the amount of a civil penalty the

court shall consider the seriousness of the violation or

violations, the economic benefit (if any) resulting from the

violation, any history of such violations, any good-faith

efforts to comply with the applicable requirements, the

economic impact of the penalty on the violator, and such

other matters as justice may require.” 33 U.S.C. § 1319(d).

52. The Court does not believe such factors can be

mechanistically applied. Any violation of the Clean Water

Act should be regarded as serious. However, Defendant’s

violations have not been willful in the sense of a specific

intent to violate. Moreover, while this Court has concluded

that there is a link between tne violations and harm to the

Bay, the causation is less-than-direct. There has been no

showing that any particular valuation has resulted in

immediate harm; the effect is apparent when taken on a

cumulative basis. Defendant’s experts have convinced the

Court that the harms caused ere not grave ones, at least in

the context of the already polluted conditions. Such a

conclusion allows the Court to find that Defendant did not

act with deliberate indifference to the health of the Bay,

Certainly, this is not a case of massive spills and fish-kills.

The Court also believes that Defendant has made good-faith

efforts to meet the dictates of the Act’s requirements,

though it has fallen short with regard to implementation.

60a

However, failure to meet the standards required by the Act

have resulted in an economic benefit to Defendant.

53. The Court is aware that Defendant’s

improvements have resulted from significant investment.

But those investments were as required. Shortfalls have

come from a lack of sufficient attention and application of

dollars and manpower. Moreover, Defendant’s efforts were

prodded in significant measure by this lawsuit. To achieve

the goal of deterrence, a penalty must be high enough so

that the discharger cannot “write it off’ as an acceptable

environmental trade-off for doing business. .See PIRG v

Powell Duffryn Terminals, Inc., 720 F.Supp. 1158, 1166

(D.N.J. 1989).

54. Based on a review of the facts of this case, as

applied to the above-required factors, the Court imposes a

penalty of $1,000 per day for each day Defendant has been

in violation of the Act through poor implementation of its

plans from the date of the filing of the lawsuit - August 27,

1996 -- until the day before trial, November 3, 1998, for a

total of 799 days, or $799,000. Payment of this provisional

penalty will be held stayed for a period of three years, from

the date of the filing of this Decision.

55. Credit against the provisional penalty. The

_ penalty upon Defendant shall be reduced for direct costs

incurred only for the following expenditures: (1) after the

date of filing of the lawsuit, steps taken to improve its

stormwater diversion system; and (2) for steps taken by

Defendant with regard to changes in its physical plant to

comply with this Decision. Direct costs are defined to

include labor and materials. Direct costs shall include those

direct costs incurred relating to stormwater mitigation as

marginal additions to costs incurred in upgrading,

improving, rehabilitating, or constructing structures at the

shipyard.

6la

56. Defendant may record the direct costs associated

with these improvements and present this record to the

magistrate judge after expiration of the three-year period

for the Court’s review. Plaintiffs may file a response to this

filing. Once the court has determined an appropriate credit,

based on review of the parties’ filings, such credit will be

subtracted from the provisional penalty. At that time, any

Penalty remaining shall be paid to the U.S. Treasury, with

interest at the legal rate from the date of this Decision. Any

credits in excess of the penalty will mean no penalty shall be

owed to the U.S. Treasury but otherwise have no effect.

The Court shall have the discretion to include cots which

have not actually been incurred, but which Defendant can

demonstrate will be incurred at a time shortly after the

expiration of the three-year period.

57. The intent of the Clean Water Act is to maintain

and protect the waters of the United States. The Court

believes that the penalty/credit remedy established by this

Decision will better serve to forward that intent than simple

penalties.

D. Enforcement Procedures

58. Magistrate Judge Oversight. Consistent with

28 U.S.C. § 636(b))()-(3), all reporting requirements

mandated by this Decision shall be filed with the magistrate

judge assigned to this case. Plaintiffs may bring before the

magistrate judge any petition for relief or contempt based

on activities or omissions that Plaintiffs regard as violations

of the injunction. In response, Defendant may file

objections to such a petition. The magistrate judge shall

have discretion to order and hold an evidentiary hearing.

The magistrate judge shall make a report and

recommendation to this Court based on the evidence

presented, along with a recommendation of remedy if

deemed necessary. Should this Court decide relief is

merited, it may confirm in part or whole the report and

recommendation. Alternatively, this Court may proceed

62a

with any further hearings it deems necessary or may order

such additional relief it deems necessary.

59. Reporting Requirement. Southwest Marine

shall compile and maintain a record of its daily inspection

reports. On a quarterly basis, one copy of this record shall

be delivered to the magistrate judge and one copy to

Plaintiffs counsel. Southwest Marine shall also provide to

Plaintiffs on a quarterly basis the sweep-down certification

reports and corrective action reports.

: 60. Inspections. Plaintiffs shall be allowed access to

Defendant’s facility for inspection on four occasions per

year, for the next three years. During the calendar year, no

more than two inspections shall be allowed in any six-month

period. Two inspections may be made on days without

precipitation. Two of the inspections may be made on days

with precipitation. Unused inspection days shall not carry

over to the next calendar year. The duration of any

inspection shall not exceed two hours from actual start of

the walk-through. Plaintiffs shail be allowed no more than

four individuals on any one inspection, and no more than

two individuals may be experts. Plaintiffs shall provide, at

minimum a two-hour notice before arrival. The hours of

potential shall be limited to 9:00 a.m. to 3:00 p.m., Monday

through Friday.

D. Attorneys’ Fees

61. As the prevailing party, Plaintiffs are entitled to

an award of their attorneys’ and experts’ fees -— including

travel costs -- resulting from this litigation. See 33 U.S.C.

§ 1365(d). Plaintiffs shall prepare and present to the Court a

summary of their fees incurred in this action within thirty

days of the filing of the Judgment. Defendant may file

objections to the summary with the Court. Plaintiffs’ fees

may include work entailed in complying with the

requirements of this Decision as specified below. _

63a

62. Plaintiffs shall also be awarded attorneys’ fees for

the reasonable costs entailed with monitoring Southwest

Marine’s compliance with this Court’s dictates, i.e., those

costs associated with reviewing inspection reports and

conducting inspections. These fees may include actual time

spent during inspections for each attorney and a maximum

of eight hours total per year for review of Defendant’s

required reports. Time spent in compliance with these

maximum hours may be presented to the Court at the end of

the calendar year. Upon such submission and approval,

Defendant shall pay to Plaintiff these fees.

63. Plaintiffs may also be awarded attorneys’ fees

should they be the prevailing party in any motion brought

before the Court to enforce compliance with this Court’s

decision.

IT IS SO ORDERED.

Dated: [9-1-99] /s/ Rudi M. Brewster ss

Honorable Rudi M. Brewster

United States Senior District

Judge

64a

UNITED STATES DISTRICT COURT

SOUTHERN DISTRICT OF CALIFORNIA

Case No. 96-1492-B -BAJB

Natural Resources Defense Council,

San Diego BayKeeper, Kenneth J. Moser,

Plaintiffs,

Southwest Marine, Inc.,

Defendant.

DECISION

FILED: March 3, 1999

I. Introduction

The instant matter having been presented to the Court

after a bench trial, and upon review of the trial testimony

and exhibits and of both Plaintiffs’ and Defendant’s

post-trial briefs, the Court makes the following Decision.

II. Standing and Adequacy of Notice

As stated during trial, this Court has found that

Plaintiffs have standing before this Court. Plaintiffs have

demonstrated constitutionally cognizable injuries. Despite

the progress made by Defendant in improving and

enhancing its operations, Plaintiffs’ allegations are not moot.

Finally, this Court has determined that the notice provided

to Defendant by Plaintiffs was adequate under the law.

65a

III. Adequacy of the Stormwater Plans vis-a-vis Permit

Requirements

This Court finds that despite early deficiencies,

Defendant has developed stormwater prevention plans and

Best Management Practices (“BMPs”) which are adequate

under the law, irrespective of what standard — BAT, BCT,

or MEP -— is applied to the question of adequacy.” While

Plaintiffs presented examples of plan inadequacies,

Defendant effectively demonstrated that allegations of

inadequacies had either been corrected or were covered

within existing categories of the permits. This Court’s visits

to the shipyard have revealed demonstrable improvement.

The testimony of Defendant’s experts - Dr. Roesner, Mr.

Curtis, Mr. Austin, and Mr. Halfax - as to the adequacy of

the plans was compelling.

Defendant is not the stereotypical environmental “bad

actor.” The Court is convinced that Defendant has made a

good-faith effort in its attempt to implement environmental

protections. That effort may have been less aggressive

without the pendency of Plaintiffs lawsuit. However,

whatever the effect of this lawsuit, the plans as written are

deemed adequate.

IV. Plan Implementation

Though the Court finds Defendant’s plans adequate,

based on the evidence presented at trial, this Court finds

that Defendant’s implementation/enforcement of its

stormwater prevention plans has been inadequate. That

inadequacy existed prior to the time of the filing of Plaintiffs

suit and continues to this day. As such, Plaintiffs have

demonstrated to the Court “a continuing likelihood of

recurrence in intermittent or sporadic violation” of those

issues in its notice letter. See Sierra Club v. Union Oil Co.,

853 F.2d 667, 671 (9th Cir. 1988).

Plaintiffs have presented convincing evidence that

Defendant did not make the inspections Defendant claims to

66a

have made. Even if the Court accepted Defendant’s

evidence, the failure to maintain those records demonstrates

shoddy practices and a lack of seriousness with which

Defendant has viewed this requirement. Defendant has

provided no satisfactory explanation for why approximately

fifty-three percent of these inspection reports are missing.

For those inspection reports presented to the Court, a

pattern of poor housekeeping is evident. Violations, even

when reported, were not always timely remedied. While a

substantial portion of these implementation violations may

not have had a direct effect on the environment, these

violations likely had some impact.

Defendant has maintained that the problems cited to

this Court are mere “snapshots,” and should not be taken for

systemic problems. While such an argument has surface

attraction, it is ultimately unconvinang. First, except for

this Court’s most recent visit to Southwest Marine,

Defendant had adequate opportunity to remedy deficiencies

prior to the inspecting party’s arrival. Second, evidence to

some extent is always of the “snapshot” variety. As stated,

taken cumulatively, the evidentiary glimpses of Defendant’s

operations present a picture of overall inadequacies.

V. Causal Harms

Plaintiffs have demonstrated that the implementation

inadequacies have led to significant contributions of

pollutants to Defendant’s leasehold and, as such, San Diego

Bay.

While this case presents complications because of the

substantial amount of historically-caused contaminated

sediments in Defendant’s leasehold, this Court finds that

Defendant’s failure to implement adequately its required

plans has contributed to and perpetuated the contamination

of the off-shore leasehold.

Trial experts agreed that the off-shore leasehold is

“devoid of life.” The question presented a’ trial was

67a

whether the stormwater coming from Defendant’s landside

facility had a causal connection to the environmental ©

condition of that offshore habitat. While no one incident of

faulty implementation can be said to have caused a level of

pollution so as to harm marine life, taken cumulatively, the

Court finds that the evidence presented demonstrates that

Defendant’s operations have contributed to the

contamination of San Diego Bay.

First, the evidence conclusively demonstrates that

contaminants are entering the marine habitat. The testing

performed by Defendant revealed substantial quantities of

pollutants - metals and toxics - have entered the Bay in

Defendant’s stormwater discharge and because of blasting

operations. Second, the Court is convinced by the evidence

presented that, but for new infusions of contaminations by

stormwater or faulty operations, the pattern of

contaminated sediments would have revealed a decreasing

trend in levels of concentration. The testimony of Mr.

Barrick was undercut by the Campbell shipyard study. The

persistence of paint chips and abrasive grit and lack of

sedimentation in the leasehold may help explain the lack of a

decreasing trend, but it is not a conclusive answer. Third,

the Court is convinced that the causal harms to the Bay are

harms that could be remedied by Defendant with improved

practices.

VI. Relief

A. Equitable Relief

The Clean Water Act vests courts with broad authority

to fashion appropriate equitable remedies. See 33 U.S.C.

§ 1365(a). Based on that broad authority, this Court shall

retain jurisdiction over this matter for three years from the

date of the filing of this Decision. Plaintiffs may petition the

Court to extend this Court’s jurisdiction. Upon good cause

showing, the Court may extend its jurisdiction for a

68a

reasonable time sufficient to ensure that Defendant is

complying with the requirements of the Act.

L Specific Directi

a. Testing

To the maximum extent possible, Southwest Marine

shall allow no discharge of stormwater effluent from any

pipe discharging into the Bay until testing has been

performed for every significant known and potential

pollutant that may result from shipyard operations and may

be contained in the effluent. Such testing shall be

performed prior to any anticipated release and no release

shall be allowed until the results of such testing have been

received. No discharge shall be allowed unless testing

results demonstrate that the effluent complies with NPDES

permit limits. Southwest Marine shall operate or modify its

stormwater retention system so as to allow conformance

with this requirement throughout its physical facility.

Southwest Marine shall maintain. records of such testing,

and make copies available for review by this Court and

Plaintiffs at Defendant’s expense.

b. Sweep downs and certifications

Southwest Marine shall conduct sweep downs after

every shift of areas in which operations may have caused

deposit of debris. After each sweep down, certification will

be made that no debris remains in the area. Alternatively,

Southwest Marine shall certify that no debris was created

and thus no sweep down was necessary. All certifications

shall clearly state the certifying employee and shall be made

subject to penalty of perjury.

c. Inspections and Recordkeeping

Southwest Maxine shall make daily inspections of its

physical plant. Records shall be maintained for each

inspection. Conditions causing or having the potential to

cause pollutants to enter the Bay shall be noted in detail. No

such inspections shall be required for periods in which the

69a

shipyard is not conducting operations. Inspection reports

shall note such time periods. All daily inspections shall be

certified as correct, and each report shall clearly state the

certifying employee and shall be made subject to penalty of

perjury.

d. Water Column Testing

On one occasion for each vessel - whether in drydock or

at pier side - on which blasting or painting operations are

conducted, Defendant shall perform testing of the

surrounding water to determine if such operations are

contributing to pollution levels in San Diego Bay. Such

testing shall be performed on a day in which blasting or

painting operations constitute a majority of the operations

conducted during a shift. Should no such day exist, testing

shall be done on the day of greatest blasting or painting

activity. Defendant shall divide such testing equally

between painting and blasting operations.

Within two hours of such blasting or painting activity,

Defendant shall perforin water column pollution tests in at

least four locations surrounding the vessel. Such locations

shall be located within 50 to 100 feet distance from the

vessel, and at least 200 feet apart from each other. For each

location, water shall be sampled at the surface, and at each

20-foot interval between the water surface and the botiom

of the Bay.

The results of such tests shall be certified in a manner

consistent with the provisions of this Decision, and shal] be

furnished on a quarterly basis to the Magistrate Judge, with

one copy provided to Plaintiffs.

it C tive Acti

Conditions with potential to allow poilutants to enter the

Bay shall be corrected within four hours after observation.

Southwest Marine shall certify that such corrective action

has been made. Should it not be feasible to take corrective

action within four hours, Defendant shall take corrective

70a

action in an expeditious manner. Defendant shall state in

writing the reason why it was not feasible. Feasibility

should be narrowly construed and should, with reason,

apply only to mechanical or structural problems.

All certifications shall note the manner of corrective

action and the time period in which such action was taken.

All certifications shall clearly state the certifying employee

and shall be made subject to penalty of perjury.

2. Physical Plant Improvements

a. Shrouds

Southwest Marine shall repair and/or replace shrouds

which are in poor repair, defined as in a state that may allow

more than de minimis quantities of debris from blasting,

painting, or other similar operations from entering the Bay.

Such repair and/or replacement shall take place within a

reasonably expeditious period of time. Defendant

subsequently shall maintain and/or replace shrouds which do

not meet this criterion.

b. Piers

Southwest Marine shall capture all stormwater runoff

coming off any and all piers. No scuttling of runoff froxa

piers will be allowed. Defendant shall take steps to meet

this requirement in a reasonably expeditious manner.

c. Berms

Southwest Marine shall erect and maintain concrete

berms in all areas of its physical plant from which runoff

may enter the Bay. In areas that experience significant

pooling of water, and which threaten to cause discharge into

the Bay, Defendant shall pump out such areas on an

expeditious basis so as not to allow such discharges. Should

areas, including piers, be constructed or re-constructed,

Defendant instead may rely on sloping and drainage so long

as such a drainage system will accommodate flows from even

heavy periods of rainfall. Should this alternative be taken,

berms need not be constructed. Should this alternative be

Tla

taken, Defendant shall certify to the Court that such a

system is as adequate as any berm system.

3. Contaminated Sediments Cleanup

Without deciding the question of its jurisdiction to order

cleanup of Defendant’s contaminated sediments to specific

standards, the Court declines to accept Plaintiffs’ invitation

to issue such an order at this time. As noted, the majority of

the pollution existing in the off-shore leasehold is present

because of historical practices at the shipyard before

Defendant obtained ownership. Defendant has begun the

process of remediation on the marine railways. Defendant

will soon begin the process of remediating the rest of the

leasehold. The cleanup standard to which the rest of the

leasehold must comply will be determined after hearings

before the State Water Resources Control Board. The

Court chooses not to interfere in that process, and sees

insufficient reason why Plaintiffs should be accorded

financial assistance at this time to be involved in that

process.

B. Penalties

1. _ Penalty Amount

The Clean Water Act mandates civil penalties for the

violations found in this lawsuit. See 33 U.S.C. § 1319(d).

Such penalties may not exceed $25,000 per day. Id. Orders

issued by this Court on November 30, 1999 and January 28,

1999 have concluded that civil penalties are available to the

Plaintiffs. While civil penalties are mandatory if the Court

finds violations, the amount assessed is wholly within the

discretion of the court. See Atlantic States Legal

Foundation v. Tyson Foods, Inc., 897 F.2d 1128, 1142 (11th

Cir. 1990); Stoddard v. Western Carolina Regional Sewer

Authority, 784 F.2d 1200, 1208 (4th Cir. 1986). “In

determining the amount of a civil penalty the court shall

consider the seriousness of the violation or violations, the

economic benefit (if any) resulting from the violation, any

72a

history of such violations, any good-faith efforts to comply

with the applicable requirements, the economic impact of

the penalty on the violator, and such other matters as

justice may require.” 33 U.S.C. § 1319(d).

The Court does not believe such factors can be

mechanistically applied. Any violation of the Clean Water

Act should be regarded as serious. However, Defendant’s

violations have not been willful in the sense of a specific

intent to violate. Moreover, while this Court has concluded

that there is a link between the violations and harm to the

Bay, the causation is less-than-direct. There has been no

showing that any particular violation has resulted in

immediate harm; the effect is apparent when taken on a

cumulative basis. Defendant’s experts have convinced the

Court that the harms caused are not grave ones, at least in

the context of the already polluted conditions. Such a

conclusion allows the Court to find that Defendant did not

act with deliberate indifference to the health of the Bay.

Certainly, this is not a case of massive spills and fish-kills.

The Court also believes that Defendant has made good-faith

efforts to meet the dictates of the Act’s requirements,

though it has fallen short with regard to implementation.

However, failure to meet the standards required by the Act

have resulted in an economic benefit to Defendant. The

Court is aware that Defendant’s improvements have

resulted from significant investment. But those

investments were as required. Shortfalls have come from a

lack of sufficient attention and application of dollars and

manpower. Moreover, Defendant’s efforts were prodded in

significant measure by this lawsuit. To achieve the goal of

deterrence, a penalty must be high enough so that the

discharger cannot “write it off as an acceptable

environmental trade-off for doing business. See PIRG v.

Powell Duffryn Terminals. Inc., 720 F.Supp. 1158, 1166

(D.N.J. 1989).

73a

Based on a review of the facts of this case, as applied to

the above-required factors, the Court imposes a penalty of

$1,000 per day for each day Defendant has been in violation

of the Act through poor implementation of its plans from the

date of the filing of the lawsuit - August 27, 1996 — until the

day before trial, November 3, 1998, for a total of 799 days, or

$799,000. Payment of this provisional penalty will be held

stayed for a period of three years from the date of the filing

of this Decision.

2. Credits against the provisional penalty

The penalty imposed upon Defendant shall be reduced

for direct costs incurred only for the following expenditures:

(1) after the date of filing of the lawsuit, steps taken to

improve its stormwater diversion system; and (2) for steps

taken by Defendant with regard to changes in its Physical

plant to comply with this Decision. Direct costs are defined

to include labor and materials. Direct costs shall include

those direct costs incurred relating to stormwater mitigation

as marginal additions to costs incurred in upgrading,

improving, rebabilitating, or constructing structures at the

shipyard.

Defendant may record the direct costs associated with

these improvements and present this record to the

magistrate judge after expiration of the three-year period

for the Court’s review. Plaintiffs may file a response to this

filing. Once the Court has determined an appropriate credit,

based on review of the parties’ filings, such credit will be

subtracted from the provisional penalty. At that time, any

penalty remaining shall be paid to the U.S. Treasury, with

interest at the legal rate from the date of this Decision. Any

credits in excess of the penalty will mean no penalty shall be

owed to the U.S. Treasury but otherwise have no effect.

The Court shall have the discretion to include costs which

have not actually been incurred, but which Defendant can

demonstrate will be incurred at a time shortly after the

expiration of the three-year period.

T4a

The intent of the Clean Water Act is to maintain and

protect the waters of the United States. The Court believes

that the penalty/credit remedy established by this Decision

will better serve to forward that intent than simple

penalties.

Consistent with 28 U.S.C. § 636(b)(1)-(3), all reporting

requirements mandated by this Decision shall be filed with

the magistrate judge assigned to this case. Plaintiffs may

bring before the magistrate judge any petition for relief or

contempt based on activities or omissions that Plaintiffs

regard as violations of the injunction. In_ response,

Defendant may file objections to such a petition. The

magistrate judge shall have discretion to order and hold an

evidentiary hearing. The magistrate judge shall make a

report and recommendations to this Court based on the

evidence presented, along with a recommendation of remedy

if deemed necessary. Should this Court decide relief is

merited, it may confirm in part or whole the report and

recommendation. Alternatively, this Court may proceed

with any further hearings it deems necessary or may order

such additional relief it deems necessary.

2. Reporting Requirement

Southwest Marine shall compile and maintain a record of

its daily inspection reports. On a quarterly basis, one copy

of this record shall be delivered to the magistrate judge and

one copy to Plaintiffs’ counsel. Southwest Marine shall also

provide to Plaintiffs on a quarterly basis the sweep down

certification reports and corrective action reports.

3. Inspections

Plaintiffs shall be allowed access to Defendant’s facility

for inspection on four occasions per year, for the next three

years. During the calendar year, no more than two

inspections shall be allowed in any six-month period. Two

T5a

inspections may be made on days without precipitation.

Two of the inspections may be made on days with

precipitation. Unused inspection days shall not carry over

into the next calendar year.

The duration of any inspection shall not exceed two

hours from actual start of the walk-through. Plaintiffs shall

be allowed no more than four individuals on any one

inspection, and no more than two individuals may be

experts. Plaintiffs shall provide, at minimum, a two-hour

notice before arrival. The hours of potential inspection shall

be limited to 9:00 a.m. to 3:00 p.m., Monday through Friday.

D. Attorneys’ Fees

As the prevailing party, Plaintiffs are entitled to an

award of their attorneys’ and experts’ fees - including travel

costs - resulting from this litigation. See 33 U.S.C. § 1365(d).

Plaintiffs shall prepare and present to the Court a summary

of their fees incurred in this action. Defendant may file

objections to the summary with the Court. Plaintiffs’ fees

may include work entailed in complying with the

requirements of this Decision as specified below.

Plaintiffs shall also be awarded attorneys’ fees for the

reasonable costs entailed with monitoring Southwest

Marine’s compliance with this Court’s dictates, i.e. those

costs associated with reviewing inspection reports and

conducting inspections. These fees may include actual time

spent during inspections for each attorney and a maximum

of eight hours total per year for review of Defendant’s

required reports. Time spent in compliance with these

maximum hours may be presented to the Court at the end of

the calendar year. Upon such submission and approval,

Defendant shall pay to Plaintiffs these fees.

Plaintiffs may also be awarded attorneys’ fees should

they be the prevailing party in any motion brought before

the Court to enforce compliance with this Court’s decision.

VII. Conclusion

76a

Plaintiffs shall prepare for this Court proposed findings

of fact and conclusions of law, and judgment, consistent with

this Decision. This document shall be submitted to the

Court within 30 days of the filing of this Decision.

Defendant shall have fifteen days from receipt to respond

with objections.

IT ISSO ORDERED.

Dated: [3-2-99] /s/ Rudi M. Brewster

United States Senior District

Judge

ee: All Parties

Magistrate Judge

77a

UNITED STATES DISTRICT COURT

SOUTHERN DISTRICT OF CALIFORNIA

Case No. 96-1492-B (AJB)

Natural Resources Defense Council,

San Diego BayKeeper, Kenneth J. Moser,

Plaintiffs,

v. -

Southwest Marine, Inc.,

Defendant.

ORDER DENYING DEFENDANT'S MOTION FOR

SUMMARY JUDGMENT AND DENYING

DEFENDANT'S MOTIONS TO STRIKE

FILED: November 26, 1991

_ 1. Case Type and Jurisdiction

This is a citizen enforcement action for alleged violations

of the Federal Water Pollution Control Act (FWPCA). 33

U.S.C. § 1365. The Court has federal question jurisdiction

pursuant to 28 U.S.C. § 1331 and 33 U.S.C. § 1365(a)(1).

II. Background

Plaintiffs Natural Resources Defense Council, Inc.

(““NRDC”), San Diego Baykeeper, Inc., and Kenneth Moser

filed suit against Southwest Marine, Inc. for allegedly

violating numerous provisions of the Federal Water

78a

Pollution Control Act, 33 U.S.C. §§ 1365 et seg. Plaintiffs

allege that Defendants unlawful and excessive discharges of

water pollution from its bayside facility contribute noxious

pollutants to San Diego Bay and the Pacific Ocean, and that

Defendant has failed to develop and/or implement several

environmental compliance and monitoring plans as required

by the FWPCA.

Defendant operates a ship repair and modernization

facility located at the foot of Sampson Street in San Diego.

The facility includes marine railways, dry docks, piers,

wharfs, a reclamation yard, a sand blast area, and assembly

and work areas. Plaintiffs allege that Defendant discharges

materials into San Diego Bay from the following activities:

floating drydock deballasting, floating drydock submergence

and emergence, floating drydock operations, marine railway

operations. berth and pier operations, stormwater, boiler

and cogeneration feedwater, fire protection system

discharges, cooling water, and miscellaneous flows.

Plaintiffs allege that these unlawful discharges pollute San

Diego Bay and the Pacific Ocean.

Plaintiffs include two environmental public interest

groups whose members use San Diego Bay for recreation

and one individual who uses San Diego Bay for recreation.

To file a citizen suit under the FWPCA, a party must

deliver sixty days advance notice of the alleged violations to

the EPA, relevant state agency, and the alleged violator. 33

U.S.C. § 1365(b)(1)(A). On April 30, 1996, Plaintiffs sent a

letter to Defendant copied to the requisite federal and state

offices, declaring their intent to sue to redress Defendant’s

alleged violations. The statutory notice provision has now

been satisfied because more than sixty days have passed

since notice was provided, and no governmental agencies

have acted to redress the alleged violations. Defendant

previously filed a motion to dismiss claiming that Plaintiffs’

notice letter was deficient. On November 5, 1996, the Court

denied this motion.

79a

Plaintiffs’ claims focus on alleged violations of two

separate programs of the National Pollutant Discharge

Elimination System (“NPDES”) that regulate Defendant’s

discharges into San Diego Bay under the FWPCA.

Defendant’s industrial discharges are governed under its

own site-specific NPDES industrial discharge permit, and

its stormwater discharge is regulated by the standards of

the NPDES California General Industrial Permit.

Defendant was issued NPDES Permit No. CA0107697 for

its industrial discharges in 1983, and it secured coverage

under the NPDES General Industrial Permit No.

CAS000001 in 1992.1 All discharges not authorized by and

in conformance with NPDES permits violate the FWPCA.

Plaintiffs’ first cause of action alleges the following

violations of Defendant’s industrial discharge NPDES

permit: (1) Defendant pollutes San Diego Bay by

discharging toxic pollutants and hazardous substances; and

(2) Defendant has failed to develop and implement an

adequate Best Management Practices Program (“BMP”).

Plaintiffs’ second cause of action alleges that Defendant’s

stormwater discharge violates the NPDES General

Industrial Permit by: (1) failing to eliminate non-stormwater

discharges from the stormwater system, (2) failing to

develop and implement a stormwater Pollution Prevention

Plan (“SWPPP”), and (3) failing to develop and implement a

Monitoring and Reporting Program, also described as a

Stormwater Pollution Prevention Monitoring Plan

(““SWPPMP”).

On January 6, 1997, Defendant filed a motion for

= summary judgment. Defendant argued that the Court

lacked subject matter jurisdiction because Plaintiffs’

allegations of ongoing violations were not made in good faith

1 Water Quality Order No. 91-13-DWQ (as amended by Water Quality

Order 92-12 DWQ) issued pursuant to Section 402 of the Act, 33 U.S.C.

$1342.

80a

or based upon a reasonable investigation. Furthermore,

Defendant argued that, even if the Court exercises subject

matter jurisdiction, summary judgment should be granted

because Plaintiffs failed to establish that they can prove

ongoing violations at trial. Finally, Defendant argued that

Plaintiffs’ claims were moot. On February 3, 1997, the Court

ordered that the motion be continued to allow Plaintiffs

more time to conduct discovery.

III. Discussion

A. Standard of Law

Federal Rule of Civil Procedure 56(c) provides that

summary judgment is appropriate if the “pleadings,

depositions, answers to interrogatories, and admissions on

file, together with the affidavits, if any, show that there is

no genuine issue as to any material fact and that the moving

party is entitled to judgment as a matter of law.” One of the

principal purposes of the rule is to dispose of factually

unsupported claims or defenses. Celotex Corp. v. Catrett,

477 US. 317, 325 (1986).

In considering a motion for summary judgment, the

court must examine all the evidence in the light most

favorable to the non-moving party. United States v.

Diebold, Inc., 369 U.S. 654, 655 (1962). A moving party who

does not bear the burden of proof at trial may discharge his

burden of showing that no genuine issue of material fact

remains by demonstrating that “there is an absence of

evidence to support the non-moving party’s case.” Celotex,

477 U.S. at 325. The moving party is not required to

produce evidence showing the absence of a genuine issue of

material fact on such issues, nor must the moving party

support its motion with evidence negating the non-moving

party’s claim, Lujan v. National Wildlife Federation, 497.

U.S. 871, 885 (1990). Instead, “the motion may, and should

be granted so long as whatever is before the District Court

demonstrates that the standard for the entry of judgment,

. 8la

as set forth in Rule 56(c), is satisfied.” Lujan, 497 U.S. at

885 (quoting Celotex, 477 U.S. at 323).

B. Motion for Summary Judgment

1. Subject Matter Jurisdiction

As discussed above, Plaintiffs’ allegations of violations of

the two NPDES permits include claims of ongoing illegal

discharges and failure to develop and implement required

supporting plans. The alleged illegal discharges would

result, at least in part, from the deficiency of the plans.?

The deficient plans, as cited by Plaintiffs’ Complaint, are the

BMP required for the industrial permit and the SWPPP and

SWPPMP for the stormwater permit.

On August 23, 1997, four days prior to the filing of this

suit Defendant submitted a revised SWPPP to the San

Diego Regional Water Quality Control Board (“Regional

Board”). Attached to the new SWPPP was the 1992 version

of Defendant’s BMP and a first SWPPMP. Defendant

contends that the allegations in Plaintiffs’ Complaint that

refer to their failure to develop and implement a BMP,

SWPPP and SWPPMP (collectively, the “plans”) refer to

the old versions of these plans. Under the new versions,

Defendant alleges that there will be no continuing violations

of the FWPCA, and therefore the Court lacks subject

matter jurisdiction over this case.

Section 505(a) of the FWPCA provides that “any citizen

may commence a civil action on his own behalf - (1) against

any person ... who is alleged to be in violation of (A) an

effluent standard or limitation, .. .” 33 U.S.C. § 1365(a).

2 The Court finds it unnecessary at this time to determine whether

the allegations of ongoing illegal discharges form the basis of an

independent cause of action or whether they are offered as evidence to

support Plaintiffs’ claims that Defendant has failed to develop and

implement required plans. If the claims are to be pursued

independently, Plaintiffs may later be required to show that such claims

were adequately noticed in its April 30, 1996 letter to Defendant.

82a

The Supreme Court interpreted the phrase ‘to be in

violation’ to require either an ongoing violation or the

likelihood of a future violation of the FWPCA, and to bar

citizen suits maintained wholly on past violations. Gwaltney

of Smithfield v. Chesapeake Bay Foundation, Inc., 484 U.S.

49, 61-64,67 (1987). To establish subject matter jurisdiction

over a FWPCA suit, a plaintiff need only make goodfaith

allegations of ongoing continuous or intermittent violations.

Sierra Club v. Union Oil Co., 853 F.2d 667,670 (9th Cir.

1988); see also Gwaltney, 484 U.S. at 64. To defeat

jurisdiction, a defendant must show that the allegations fail

to satisfy the “reasonable inquiry” requirements of Rule 11.

Sierra Club v. Union Oil, 853 F.2d at 669; see FED. R. CIV.

P. 11.

Two sets of Plaintiffs’ claims must be subjected to the

good-faith pleading standard: (1) the illegal discharge claims

and (2) the failure to develop and implement required plans

claims.

a. Illegal Effluent Discharges

Plaintiffs allege that Defendant continues to discharge

water pollution into San Diego Bay in violation of its

industrial discharge permit and the stormwater discharge

regulations. The Complaint states that Defendant “has

violated, and continues to violate, numerous requirements of

the [Clean Water] Act governing the discharge and

abatement of polluted water, polluted stormwater, and

other substances (‘water pollution’) into San Diego Bay.”

Effluent discharges, particularly rain-induced

stormwater drainage, arc inherently intermittent and

sporadic and qualify as a continuing discharge even when

they do not occur every day. As long as Defendant’s facility

is exposed to rain and tidal activity, discharges will occur.

See Molokai Chamber of Commerce v. Kukui, 891 F. Supp.

1389, 1401 (D. Hawaii 1995) (circumstances where pollutant

is discharged in stormwater each time it rains constitutes a

83a

continuing discharge). Therefore, the Court has subject

matter jurisdiction over these claims if it finds that Plaintiffs

could in good faith allege a likelihood that illegal discharges

might recur in the future.

Plaintiffs submit a document from the Regional Board

that details a pattern of NPDES permit violations at

Defendant’s facility, with twenty-four violations over a

period of ten years.? Plaintiffs also submit an affidavit from

one of their attorneys which states that “[bJased on my

continuins review and knowledge of the evidence in this

case, ' continue to believe that Defendant is violating the

Act in numerous respects.” This evidence of a longstanding

pattern of violations sufficiently suggests a likelihood of

continued sporadic or intermittent violations in the future.

3 These violations, recorded between October 30, 1986 and June

16, 1995, include violations of both the stormwater General

Industrial Permit and the Industrial NPDES pemit. The

documentation includes: (1) a document from the Regional

Board evidencing 24 discharges in violation of the FWPCA. (2)

three of Defendant’s annual reports to the Regional Board

which plaintiffs allege demonstrate Defendant’s violation of

stormwater discharge requirements; and (3) a Staff Report from

the Regional Board that indicates that the sediments in San

Diego Bay adjacent to Defendant’s facility are high in heavy

metals and other pollutants. See P1 . NOS Exs. 1, 2, 3, 5, 6.

These documents evidence a pattern of violations over at least

the past ten years. This pattern warrants a presumption that

these discharges could continue in the future. The presumption

created by ten years of illegal discharges cannot be defeated by

four days of compliance during the brief period between the

adoption of the new SWPPP and the filing of the Complaint.

In February, Defendant moved to strike this document for lack of

foundation because it did not attribute any authorship. Plaintiffs now

supply the deposition testimony of Kristin Schwall of the Regional

WaterBoard staff, who claims the chart was authored by her for use by

the board in its ordinary course of business. Pla. Supp. Opp. p. 9, fn. 6,

Pla. Supp. NOL Ex. 2, pp. 8- 10. Therefore, Defendant’s motion to strike

is denied.

84a

Defendant contends that its new environmental

compliance and monitoring plans will ensure that there are

no future violations. However, the exercise of subject

matter jurisdiction requires only a showing that allegations

were made in good faith, and not actual proof. Plaintiffs

may in good faith doubt Defendant’s promises in view of its

history of noncompliance. Finally, as discussed below,

Plaintiffs have alleged specific instances of continuous and

ongoing illegal discharges. Therefore, subject matter

jurisdiction exists over the illegal discharge claims.

b. Environmental Compliance and Monitoring Plans

Plaintiffs allege in their Complaint that Defendant has

failed te “develop and implement” a BMP, SWPPP and a

SWPPMP as required by the Federal Water Pollution

Control Act. Plaintiffs state that Defendant (1) has failed to

implement a BMP that adequately serves to reduce and

eliminate discharges of water pollution from its facility; (2)

has failed to implement a SWPPP that lists pollutants likely

to be present in Stormwater or that provides for the

Stormwater management controls appropriate for the

facility; and (3) has failed to comply with the regulations

governing a SWPPMP by failing to conduct adequate visual

observations of Stormwater discharge, failing to collect and

analyze samples of Stormwater, and failing to notify the

Regional Board of instances of non-compliance. The

Complaint provides more specific examples of how these

plans are deficient and suggests the likelihood of other

inadequacies.

Defendant argues that its implementation of new plans

four days before Plaintiffs filed their Complaint deprives the

Court of subject matter jurisdiction over Plaintiffs’ claims

that these plans are legally inadequate. In making this

argument, Defendant assumes that its new plans remedy all

violations embodied in the old plans. If these new plans still

do not fully comply with the Federal Water Pollution

Control Act, then there is a continuing violation of the

85a

F WPCA and the Court has subject matter jurisdiction over

these claims. See City of New York v. Anglebrook Limited

Partnership, 891 F.Supp.. 900, 905 (S.D.N.Y. 1995) (finding

subject matter jurisdiction because “the City claims a

present violation - a flawed plan filed in violation of permit

requirements -- that is an actionable violation of an effluent

standard under § 1365(f)(6)”).

Defendant submits a declaration from an environmental

consultant (who used to be their Industrial Environmental

Manager) which states that their new plans are all in

compliance with their permits and the FWPCA. Austin

Decl. 4412, 16, 20, 22. Upon the completion of the additional

discovery time allotted by the Court, Plaintiffs argue that

the “new evidence establishes that [Defendant’s] conduct

has been far worse than originally known. This new

evidence lends further support to plaintiffs’ contentions that

the plans themselves, and {Defendant’s] implementation of

them, are deficient.”

The Court differentiates between alleged deficiencies in

the development of the required plans and deficiencies in

the implementation of such plans. If Plaintiffs objected only

to the former, then the adoption of new plans would

terminate the cause of action as strictly a past violation

unless Plaintiffs made good faith allegations that the new

plans were also legally deficient. If however, Plaintiffs’

Complaint alleges implementation deficiencies, then

Plaintiffs can in good faith fear that the substitution of one

allegedly hollow plan for another may not change

Defendant’s behavior.

The Court has jurisdiction to adjudicate implementation

failures because the development of new plans does not

extinguish the continuing nature of Defendant’s

implementation failures. If Defendant failed to coilect

samples or eliminate illegal discharges under the old plans,

there is reason to believe that they wili continue to fail to do

so wider the new plans. If the opposite presumption were

86a

true, a defendant could always draft a new plan when

threatened with litigation and claim a complete defense. A

potential plaintiff would be forced to wait until defendant

violated the FWPCA under its new plan before it could file

suit. Defendant could then create yet another new plan, and

the cycle would begin again.

At the time of the February hearing, it was not clear to

the Court whether it had jurisdiction to adjudicate the

alleged development failures of the plans. Defendant had

submitted an affidavit attesting that its new plans were in

compliance with all requirements of its permits and the

FWPCA. See Austin Decl. {J 12, 16, 20, 22, while Plaintiffs

had not clearly disputed these assertions as to both

development and implementation. However, Plaintiffs’

supplemental opposition, prepared with the benefit of

additional discovery, has satisfied the Court’s concerns.

Plaintiffs’ supplemental opposition alleges that

Defendant’s former environmental coordinator testified in a

recent deposition that Defendant’s BMP plan was deficient

as recently as 1995. Defendant has not revised its BMP

since 1992, and it submitted the 1992 version with its 1996

SWPPP. An adequate BMP is an important element of

compliance for both of Defendant’s NPDES permits. Many

of Defendant’s past discharge violations occurred under the

1992 BMP that is still in effect today. Defendant’s refiling of

the same BMP with its revised SWPPP does not end good

faith speculation that violations of the stormwater permit

arc likely to continue in the future. Furthermore,

Defendant has not supported its motion for summary

judgment of the industrial discharge claim, since it never

revised the BMP that forms the basis of Plaintiffs’

contentions.

Therefore, the Court may exercise subject matter

jurisdiction over Plaintiffs’ claims that Defendant has failed

to develop adequ: 2 plans as required by its NPDES

permits.

87a

2. The Merits: Proof or Evidence of Ongoing and

Future Violations

Plaintiff may survive Defendant’s motion for summary

judgment “either (1) by proving violations that continue on

or after the date the complaint is filed, or (2) by adducing

evidence from which a reasonable trier of fact could find a

continuing likelihood of recurrence in intermittent or

sporadic violations.” Sierra Club v. Union Oil, 853 F.2d at

671.

In February, Plaintiffs argued that they could not yet

prove the extent and severity of the FWPCA wiolations

because there had been no meaningful discovery. The Court

continued the motion for summary judgment at that time to

allow ample time for the discovery sought by Plaintiffs,

pursuant to FED. R. CIV. P. 56(f). Now that this discovery

has been completed, the Court seeks to determine whether

any material questions of fact remain that prevent judgment

from being entered at this time.

Plaintiffs can prevail at trial by showing either that

Defendant’s plans are inadequate facially or as applied, or

by establishing that there are or will likely be ongoing

violations of the NPDES permits.

a. Are the Plans Defective as Written?

EPA’s regulations define “best management practices”

as “schedules of activities, prohibitions of practices,

maintenance procedures, and other management practices

to prevent or reduce the pollution of ‘waters of the United

States.’ BMPs also include treatment requirements,

operating procedures, and practices to control plant site

runoff, spillage or leaks, sludge or waste disposal, or

drainage from raw material storage.” 40 C.F.R. § 122.2.

Defendant’s BMP, last modified in 1992, is an important

element of both its industrial and stormwater discharge

responsibilities.

88a

As discussed above in regards to subject matter

jurisdiction, a defective or inadequate BMP would implicate

both of Defendant’s NPDES permits. Plaintiffs argue that a

material question of fact on this point is created by

statements of a former employee of Defendant. Plaintiffs’

supplemental opposition cites deposition testimony of Daniel

Mills, Defendant’s former environmental coordinator. Mills

answered that there was “some internal concern over the

usability” of the BMP; that the plan “wasn’t really designed

as a policy that was effective” because it was “developed by

an outside agency not for [Defendant];” and that there was

discussion about the BMP to make the plan more specific to

Defendant’s facility.

However, the Mills excerpts do not include any direct

admission that the BMP’s shortcomings rise to the level of a

NPDES violation. In fact, Mills also testified that he

believed that the SWPPP, which necessarily includes the

BMP, is legally adequate. By their nature, no BMP will

ever be perfect, and consideration of improvements by itself

does not constitute any admission. It is interesting that

Mills apparently did not use the BMP in his daily inspection

routines (See Pl. Supp. NOL Ex. 3, p. 65), but Plaintiffs do

not explicitly allege that such a failure is a per se violation of

the permits.

Therefore, Mills’ statements do not prove that the BMP

was legally defective. However, do they constitute evidence

from which a reasonable trier of fact could find a continuing

likelihood of future violations? If a jury interpreted Mills’

testimony to mean that the BMP was not used by Defendant

in its daily practices, such a finding would help to support a

finding for Plaintiffs.

Plaintiffs next argue that the plans are insufficient as

evidenced by Defendant’s own past record of violations.

Defendant has not revised its BMP since 1992, and it

submitted the 1992 version with its 1996 SWPPP. An

adequate BMP is an important element of compliance for

89a

both of Defendant’s NPDES permits. Many of Defendant’s

past discharge violations occurred under the same 1992

BMP that is still in effect today. Therefore, these violations

are not only past violations, but also evidence a present and

ongoing failure to maintain an adequate BMP as required by

the NPDES permits.

Defendant argues that Plaintiffs have failed to provide

expert testimony essential to their case. In its reply,

Defendant notes that Plaintiffs’ first opposition stated:

This case involves numerous technical issues.

At the appropriate time, plaintiffs will designate

experts on various matters. These experts will

provide their opinions about matters such as

[Defendant’s] non-compliance with the law, the

effects such noncompliance has on _ the

environment and how [Defendant] must address

its noncompliance and ameliorate any problems

created by its activities.

Defendant maintains that Plaintiffs have failed to

deliver on this promise, and therefore have failed to refute

the testimony of Defendant’s experts that the plans do not

violate the NPDES permits. Defendant offers the expert

testimony of Mr. Dana Austin, an environmental consultant

retained by Defendant since 1996. Mr. Austin served as

Defendant’s Corporate Manager of Environmental Affairs

from 1991-1995, and, in his words, “was the person

principally responsible for overseeing the compliance of

corporate and divisional industrial operations with

environmental regulations ... [including] the Clean Water

Act.” Defendant relies heavily on what it claims to be the

undisputed expert assertions by Austin that since August

‘23, 1996, Defendant has implemented all necessary plans

and is otherwise in compliance with the conditions of its two

NPDES permits. Austin Declaration 44 11, 12, 15, 16, 19,

20, and 22. Defendant argues that Plaintiffs have failed to

rebut this expert testimony with expert testimony of their

90a

own, and that therefore summary judgment must be

granted. These contentions from the Austin Declaration

form the entirety of Defendant’s separate statement of

undisputed facts in support of its motion for summary

judgment.

The Court finds that the allegations and evidence

submitted by Plaintiffs place in dispute the assertions made

by Mr. Austin. Expert testimony can be rebutted by factual

allegations in lieu of contrary expert testimony.

Furthermore, Plaintiffs argue that the testimony of Austin

has been seriously impeached. They claim that his

deposition revealed that his “conclusory opinions were

exposed for their lack of significance,” and that he “took a

classic ‘head-in-the-sand’ approach to Defendant’s

culpability. Plaintiffs further allege that Austin “never

bothered to review highly relevant evidence.”

Next, Plaintiffs allege that Defendant’s SWPPP is

defective on its face because it fails to list all likely

pollutants in its stormwater discharges. SWPPPs must

include a “list of pollutants that are likely to be present in

stormwater discharge in significant quantities, and an

estimate of the annual quantities of these pollutants in

stormwater discharge.” Defendant’s NOL Ex. 3, Sec. A.

4(d). Plaintiffs submit a Regional Board staff memorandum,

dated April 19, 1996, that discusses Defendant’s proposed

SWPPP. The internal memo noted that Defendant’s

“sampling plan does not include analysis for all materials

[Defendant] is known to be handling such as rust inhibitors,

solvents, chlorine, anticorrosive and antifouling paints,

cooling and fire waters, petroleum chemicals. Annual

reports have no data on TBT, PAH, PCB, and TPE. PI.

NOL Ex. 4, p. 1. Defendant’s list of ten possible stormwater

pollutants in its implemented SWPPP does not include any

of the chemicals cited-by the region staff member. Def.

NOL Ex. 2, SWPPP Section C. These contentions, not

9la

directly countered by Defendant, leave a triable question of

fact as to the sufficiency of the SWPPP.

The Court finds that triable issues of fact remain

whether Defendant adequately developed the necessary

plans to be in compliance with its NPDES permits.

b. Is the Implementation of the Plans

Deficient?

Plaintiffs supply testimony and documented evidence

that allegedly shows that Defendant violates the NPDES

permits in practice. Before reviewing these allegations, it

must be noted that Plaintiffs are not suing Defendant for

specific discharges; rather, evidence of past behavior is

offered to show a pattern that could support a finding of

ongoing and/or likely future violations by Defendant.4

Among the factors outlined in Union Oil, Plaintiffs may

satisfy their burden of proof by establishing violations that

continue on or after the date the complaint is filed. Any

argument by Defendant that concedes (or fails to refute) a

post-Complaint violation but professes a current compliance

is an attempt at a mootness defense. While courts have

recognized that the doctrine of mootness prevents the

maintenance of a suit when “there is no reasonable

expectation that the wrong will be repeated,” the Defendant

bears a heavy burden to establish mootness and must

demonstrate that it is “absolutely clear that the allegedly

wrongful behavior could not reasonably be expected to

occur. ... Mootness doctrine thus protects defendants from

the maintenance of suit under the Clean Water Act based

solely on violations wholly unconnected to any present or

future wrongdoing, while it also protects plaintiffs from

4 The evidence of past behavior is only offered to support Plaintiffs’

claim that the required plaintiff documents are inadequate. Therefore,

the sufficiency of Plaintiffs’ Notice Letter is not implicated by the use of

this evidence. Defendant’s Reply (at p. 3) contemplates that evidence of

a discharge could provide evidence of a failure of a compliance plan.

92a

defendants who seek to evade sanction by predictable

protestations of repentaince and reform.” Gwaltney, 484

U.S. at 66-67 (citations and internal quotation marks

omitted).

Plaintiffs allege, and Defendant responds to, the

following specific violations:

1. Plaintiffs allege that Defendant’s marine railways

“remain a serious and ongoing water pollution problem and

currently result in the ongoing discharge of contaminated

water and materials into San Diego Bay.” Plaintiffs allege

that on their March 25, 1997 site visit, they conducted

physical sampling of the marine railways area, and that

laboratory analysis of the samples revealed high levels of

copper. zinc, oil and grease. Pla. Supp. NOL Ex. 20, pp. 2-4.

Plaintiffs allege that the conditions at the marine

railways violate both permits. The NPDES permit requires

that sump areas and waste dams be cleaned out on a regular

basis, and “within one working day of vessel departure.”

BMP #s 9, 12; Def. NOL Ex. 2. No ship was in the railway

during the site visit and therefore a finding could be

supported that Defendant fialed to clean the railway as

required. Furthermore, the polluted condition of the

railway could dallow non-stormwater dischrages prohibited

by the stormwater permit. Therefore. the condition of the

marine railways involves triable issues of fact that could

support NPDES permit violations.

2. Plaintiffs allege that their site inspections of Defendant’s

facility, conducted in March and April 1997, “revealed

ongoing violations.” Plaintiffs allege that Defendant has a

“history of ‘preparing’ for such inspections in such a way

that conceals the usual operating practices.” Even still, they

allege that their inspections revealed violations of the

permits. In addition to the marine railway discussed above,

plaintiff Kenneth Moser stated in his sworn declaration that

the condition of the shipyard and grounds violated the

93a

NPDES permits. Moser testifies that he collected samples,

later analyzed by Pacific Treatment Analytical Services,

Inc., that revealed significant quantities of oil, grease,

copper and zinc.

The stormwater General Permit includes a “good

housekeeping” provision that requires the maintenance of

“clean, orderly facility areas that discharge stormwater.”

General Permit No. CAS000001, Section A.5(c). The

evidence of alleged presence of toxic chemicals creates a

triable issue of fact as to whether Defendant violated the

“good housekeeping “ clause.

3. Plaintiffs allege that Defendant’s employees do not

conduct BMP inspections on a daily basis, as allegedly

required by both permits. Plaintiffs allege that Defendants

have failed to provide in discovery reports for “numerous

days,” including between August 29 and September 4, 1996.

Plaintiffs maintain that it is therefore reasonable to assume

that these records are unavailable because the inspections

were never conducted.

Defendants argue that BMP inspections are not

required. Defendant’s own SWPPP provides that

“{iInspections are conducted both on a daily (Daily BMP

Inspection) and Bi-Monthly ... basis. Def. NOL Ex. 2

SWPPP § FGi). While the provisions of the General

Industrial Permit do not require daily inspections, they do

require dischargers to include inspection plans to be

approved as part of their SWPPMP. Dischargers are

required to abide by the terms of their SWPPPs and

SWPPMPs. Some degree of deviation from individual plans

not required by the General Permit probably should be

disregarded, or companies would have a disincentive to

propose plans stronger than the minimal requirements. The

absence of a few days of reports is a de minimis violation,

unless a showing of bad faith is made. However, the claim

that “numerous” reports are missing may create a liable

question of fact.

94a

4. Plaintiffs allege that, at the time of the filing of the

Complaint, Defendant was discharging 2.16 million gallons

per day of chlorine-contaminated water in violation of the

stormwater permit. The page in their lodgements that

supports this finding appears to be missing (they cite Pla.’s

Supp NOL Ex. 15 attachment at 3). According to the

deposition of Armando DeQuesada, Defendant’s

environmental manager, the chlorination of “seawater

intake” stopped near the end of 1996. Pla. Supp. NOL Ex. 9,

p. 165-166. Therefore, these violations were occurring

condnuously at the time the Complaint was filed in August

1996. This individual claim is vulnerable to a mootness

defense because it appears that Defendant has installed a

new system that has ended these discharges. The Court

reserves judgment on this question for future proceedings, if

necessary.

5. Plaintiffs allege that stormwater collected in

February 1997 “revealed the highest levels of the pollutants

Total Suspended Solids (“TSS”), copper and lead ever

reported in [Defendant’s] stormwater.” Plaintiffs provide as

an exhibit a data sheet from Defendant’s records that

includes a series of numbers apparently reporting levels of

various chemicals at various times and places between 1992

and 1997. Pla. Supp. NOL Ex. 18, p. 57. The levels of the

three above-mentioned chemicals were in fact higher on

February 10, 1997 at outfall #2, than any of the other eight

dates included in the chart.

_ Defendants counter the February data by arguing that

Plaintiffs failed to provide expert testimony or to show that

the reported concentrations “adversely impact human

health or the environment.” Defendant is correct that the

data alone does not establish a prima facie violation;

however, the information was offered by Plaintiffs to

impeach. The assertion that the new SWPPP has improved

Defendant’s stormwater performance.

95a

Plaintiffs further allege that Defendant does not monitor

the adequacy of the required list of stormwater discharge

pollutants on its SWPPP. Plaintiffs offer deposition

testimony of Mr. Armando DeQuesada, Defendant’s

environmental manager who compiled the 1997 samples.

Mr. DeQuesada said that he did not conduct any additional

independent research to determine whether the SWPPP list

was satisfactory. It is not clear that he was aware of any of

the alleged deficiencies in the original list as noted by a

Regional Board staff member and discussed above in this

Order. In any case, Plaintiffs argue that he had a duty to

monitor stormwater discharges and update the list if

warranted.

From this record, it appears that unresolved material

questions of fact could support a finding that Defendant is

failing to effectively implement its SWPPP by failing to

conduct sufficient reports and testing, and by taking

insufficient action to minimize non-stormwater discharges.

6. Plaintiffs allege that Defendant continues to fail to

gather at least two samples per rainy season, and that

Defendant continues to fail to collect samples from all

locations where stormwater is discharged, or, in the

alternative, establish that stormwater discharges from

different locations are substantially identical. Plaintiffs

provide a report submitted by Defendant to the Regional

Board in June 1996. Question 9 of the Report asks:

Section B.5.d of the General Permit requires that

stormwater samples from at least two storms be

collected and analyzed. a. How many storms did

you sample? Answer: 0 (NONE). b. How many

stormwater discharge points are located at your

facility? Answer: 5. Did you sample from every

discharge point? Answer: No. If you did not

sample from every discharge point, attach an

explanation why you did not or attach a

96a

justification as to why certain discharge points are

substantially identical.

Pla.’s NOL Ex. 1, p. 4. Plaintiffs allege that Defendant

did not attach any explanation or justification.

Furthermore, Plaintiffs point to the stormwater

analyses conducted by Defendant between 1992-1997, as

noted above. These reports indicate substantially different

results at different outfalls from nearly conte

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.